PROCUREMENT PLAN (Mandatory Requirements) Project information: [Bangladesh] [BD Rural Water, Sanitation and Hygiene for Human Capital Development Project] [P169342] Project Implementation agency: [Department of Public Health Engineering (DPHE)] Period covered by this Procurement Plan: Entire Project Period Preamble In accordance with paragraph 5.9 of the World Bank Procurement Regulations for IPF Borrowers, July 2016 [Revised in November, 2017] (“Procurement Regulations”), the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to record all procurement actions for the Project, including preparing, updating and clearing its Procurement Plan, and seeking and receiving the Bank’s review and No-objection to procurement actions as required. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents (SPDs) shall be used for goods, works and non- consulting services where international competition is required and for all consulting services, including their respective forms of contract. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act 2006 and the Public Procurement Rules 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: i. Lottery in award of contracts shall not be allowed; ii. Bidders’ qualification[s]/experience requirement[s] shall be mandatory; iii. Bids shall not be rejected based on percentage above or below the estimated cost; iv. Model Bidding Documents agreed with the Bank shall be used for all national open competitive procurement; v. The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations; vi. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. vii. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. When the Borrower uses other national procurement arrangements (other than national open competitive procurement), such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), such arrangements shall be consistent with the above requirements. As per paragraph 5.4 of the Procurement Regulations, the “Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework” as attached to this document shall form part of the Model Bidding Documents. Leased Assets: Not Applicable. Procurement of Second Hand Goods: Not Applicable. Domestic preference: as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works) as follows: Goods: Applicable; Works: Not applicable. Hands-on Expanded Implementation Support (HEIS): Not Applicable. Bank’s Procurement Prior Review Thresholds: contracts at or above the thresholds set out in table 1 below are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) Type of High risk Substantial Moderate Low risk procurement risk risk Works (including 5 10 15 20 turnkey, supply & installation of plant and equipment, and PPP) Goods, information 1.5 2 4 6 technology and non-consulting services Consulting 0.5 1 2 4 services: firms Consulting 0.2 0.3 0.4 0.5 services: Individual Notes: 1. These thresholds apply to all procurement activities regardless of their procurement/selection methods. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds. Consultant services covers a range of services that are of an advisory or professional nature. 2. In addition to the provisions of Table 1 above, and irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: (a) procurement processes involving contract negotiations, as described in Section VI, paragraphs 6.34-36, of the Procurement Regulations; (b) competitive dialogue; (c) sustainable procurement; (d) selection of probity assurance providers, as described in Section III, paragraph 3.3 of the Procurement Regulations; and (e) best and final offer. 3. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract or the package -when the selection document contains more than one lot/slice- , including all taxes and duties payable under the contract. Bid/ Proposal Evaluation Committee: [as per PPSD] Arrangement for CDD: [Describe] Fraud and Corruption (F&C) Checklist: Fraud and Corruption (F&C) checklist, as developed and provided by the Bank, shall be properly filled in during the evaluation and be attached with the evaluation report in case of contracts following national competitive procurement and request for quotations. Attachment 1 Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: PROCUREMENT Bangladesh : BD Rural Water, Sanitation and Hygiene for Human Capital Development Project PLAN General Information Country: Bangladesh 2021-04-29 Bank’s Approval Date of the Original Procurement Plan: 2023-09-12 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169342 GPN Date: Project Name: BD Rural Water, Sanitation and Hygiene for Human Capital Development Project Loan / Credit No: IDA / 67770, COFN / C1840 Department of Public Health Engineering Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned RWSHP-WD-80 / Public sanit ation and hygiene facilities & National Procure Response to Covid-19 ment Document - 5. COVID-19 emergency res Single Stage - One E 2022-10-0 hand washing station with ru COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 67,863.45 55,870.05 Signed 2021-12-14 2021-12-21 2021-12-19 2022-01-30 2022-01-17 2022-03-01 2022-02-02 2022-04-05 2022-02-25 ponse nvelope 2 nning water by instralling Tu ss (Non Bank-SPD bewell with overhead tank an ) d associated facilities at Paik gacha upazila RWSHP-WD-81 / Public sanit National Procure ation and hygiene facilities, R ment Document - esponse to Covid-19 hand wa 5. COVID-19 emergency res Single Stage - One E 2022-09-3 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 67,863.45 52,769.60 Signed 2021-12-12 2021-12-29 2021-12-17 2022-01-28 2022-01-20 2022-02-27 2022-02-24 2022-04-03 2022-03-31 shing station with running wa ponse nvelope 0 ss (Non Bank-SPD ter by installing Tubewell wit ) h overhead tank and associat ed facilities at shalikha Upazi la RWSHP-WD-82 / Public sanit ation and hygiene facilities, R National Procure esponse to Covid-19 ment Document - hand washing station with ru 5. COVID-19 emergency res Single Stage - One E 2022-09-3 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 135,726.90 112,036.15 Signed 2021-12-12 2021-12-09 2021-12-17 2022-01-28 2022-01-12 2022-02-27 2022-01-17 2022-04-03 2022-02-18 nning water by installing Tub ponse nvelope 0 ss (Non Bank-SPD ewell with overhead tank and ) associated facilities at Morel ganj nad Molla hat Upazila RWSHP-WD-83 / Public sanit ation and hygiene facilities, R National Procure esponse to Covid-19 ment Document - hand washing station with ru 5. COVID-19 emergency res Single Stage - One E 2022-09-3 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 135,726.90 101,009.27 Signed 2021-12-12 2022-03-10 2021-12-17 2022-01-28 2022-03-23 2022-02-27 2022-03-30 2022-04-03 2022-04-15 nning water by installing Tub ponse nvelope 0 ss (Non Bank-SPD ewell with overhead tank and ) associated facilities at Mohes pur and Hornakunda Upazila RWSHP-WD-84 / Public sanit ation and hygiene facilities, R National Procure esponse to Covid-19 ment Document - 5. COVID-19 emergency res Single Stage - One E 2022-09-3 hand washing station with ru COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 135,726.90 132,885.55 Signed 2021-12-12 2022-01-06 2021-12-17 2022-01-28 2022-03-30 2022-02-27 2022-04-04 2022-04-03 2022-05-10 ponse nvelope 0 nning water by installing Tub ss (Non Bank-SPD ewell with overhead tank and ) associated facilities at Agolhj ara nad Hizla Upazila RWSHP-WD-85 / Public sanit ation and hygiene facilities, R National Procure esponse to Covid-19 ment Document - 5. COVID-19 emergency res Single Stage - One E 2022-09-3 hand washing station with ru COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 67,863.45 50,408.25 Signed 2021-12-12 2021-12-29 2021-12-17 2022-01-28 2022-01-24 2022-02-27 2022-01-26 2022-04-03 2022-02-20 ponse nvelope 0 nning water by installing Tub ss (Non Bank-SPD ewell with overhead tank and ) associated facilities at Indurk ani Upazila RWSHP-WD-86 / Public sanit ation and hygiene facilities, R National Procure esponse to Covid-19 ment Document - hand washing station with ru 5. COVID-19 emergency res Single Stage - One E 2022-09-3 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 135,726.90 115,471.74 Signed 2021-12-12 2021-12-26 2021-12-17 2022-01-28 2022-01-11 2022-02-27 2022-04-06 2022-04-03 2022-04-28 nning water by installing Tub ponse nvelope 0 ss (Non Bank-SPD ewell with overhead tank and ) associated facilities at Ranga bali and Kalapara Upazila RWSHP-WD-87 / Public sanit ation and hygiene facilities, R National Procure esponse to Covid-19 ment Document - hand washing station with ru 5. COVID-19 emergency res Single Stage - One E 2022-10-0 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 135,726.90 73,347.76 Signed 2021-12-14 2021-12-19 2021-12-19 2022-01-30 2022-01-11 2022-03-01 2022-02-02 2022-04-05 2022-02-27 nning water by installing Tub ponse nvelope 2 ss (Non Bank-SPD ewell with overhead tank and ) associated facilities at Pabna Sadar and Iswardi Upazila RWSHP-WD-88 / Public sanit ation and hygiene facilities, R National Procure esponse to Covid-19 ment Document - 5. COVID-19 emergency res Single Stage - One E 2022-10-0 hand washing station with ru COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 67,863.45 50,575.15 Signed 2021-12-14 2021-12-21 2021-12-19 2022-01-30 2022-01-17 2022-03-01 2022-02-07 2022-04-05 2022-03-04 ponse nvelope 2 nning water by installing Tub ss (Non Bank-SPD ewell with overhead tank and ) associated facilities at Sariak andi Upazila RWSHP-WD-89 / Public sanit ation and hygiene facilities, R National Procure esponse to Covid-19 ment Document - 5. COVID-19 emergency res Single Stage - One E 2022-10-0 hand washing station with ru COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 135,726.90 100,928.16 Signed 2021-12-14 2021-12-27 2021-12-19 2022-01-30 2022-01-11 2022-03-01 2022-02-01 2022-04-05 2022-02-16 ponse nvelope 2 nning water by installing Tub ss (Non Bank-SPD ewell with overhead tank and ) associated facilities at Nacho le and Gomostapur RWSHP-WD-90 / Public sanit ation and hygiene facilities, R National Procure esponse to Covid-19 ment Document - 5. COVID-19 emergency res Single Stage - One E 2022-10-0 hand washing station with ru COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 135,726.90 96,581.07 Signed 2021-12-14 2021-12-26 2021-12-19 2022-01-30 2022-01-16 2022-03-01 2022-02-03 2022-04-05 2022-03-02 ponse nvelope 2 nning water by installing Tub ss (Non Bank-SPD ewell with overhead tank and ) associated facilities at Pangs a and kalukhali RWSHP-WD-91 / Public sanit ation and hygiene facilities, R National Procure esponse to Covid-19 ment Document - 5. COVID-19 emergency res Single Stage - One E 2022-10-0 hand washing station with ru COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 135,726.90 103,959.52 Signed 2021-12-14 2021-12-28 2021-12-19 2022-01-30 2022-01-20 2022-03-01 2022-03-02 2022-04-05 2022-03-24 ponse nvelope 2 nning water by installing Tub ss (Non Bank-SPD ewell with overhead tank and ) associated facilities at Sibala ya and Harirampur Page 1 National Procure RWSHP-WD-30 / Community ment Document - based Small Piped Water su 1. Investments in water sup Single Stage - One E Pending Imp 2022-11-1 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 3,438,116.54 0.00 2022-01-31 2022-02-05 2022-03-19 2022-04-18 2022-05-23 pply Scheme for Mymensingh ply nvelope lementation 9 ss (Non Bank-SPD district and upazilas. ) National Procure RWSHP-WD-31 / Community ment Document - 1. Investments in water sup Single Stage - One E 1,526,876.2 2022-12-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 Signed 2022-03-06 2022-03-28 2022-03-11 2022-04-22 2022-04-27 2022-05-22 2022-06-05 2022-06-26 2022-06-14 ply nvelope 1 3 pply Scheme for Sherpur sad ss (Non Bank-SPD ar and upazilas ) National Procure RWSHP-WD-34 / Community ment Document - based Small Piped Water su 1. Investments in water sup Single Stage - One E 2022-11-1 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 2,292,077.69 0.00 Signed 2022-01-31 2022-03-23 2022-02-05 2022-03-19 2022-05-09 2022-04-18 2022-05-18 2022-05-23 2022-06-18 pply Scheme for Kurigram sa ply nvelope 9 ss (Non Bank-SPD dar and upazilas ) National Procure RWSHP-WD-40 / Community ment Document - based Small Piped Water su 1. Investments in water sup Single Stage - One E 2022-11-1 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 0.00 Signed 2022-01-27 2022-03-23 2022-02-01 2022-03-15 2022-05-05 2022-04-14 2022-05-11 2022-05-19 2022-06-27 pply Scheme for Chottogram ply nvelope 5 ss (Non Bank-SPD district 3 upazilas ) National Procure RWSHP-WD-41 / Community ment Document - based Small Piped Water su 1. Investments in water sup Single Stage - One E Under Imple 2022-11-1 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 2,292,077.69 0.00 2022-01-27 2022-03-22 2022-02-01 2022-03-15 2022-04-25 2022-04-14 2022-05-24 2022-05-19 pply Scheme for different up ply nvelope mentation 5 ss (Non Bank-SPD azilas of Comilla district ) National Procure RWSHP-WD-48 / Community ment Document - based Small Piped Water su 1. Investments in water sup Single Stage - One E Under Imple 2022-12-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 2,292,077.69 0.00 2022-03-09 2022-03-23 2022-03-14 2022-04-25 2022-04-28 2022-05-25 2022-05-09 2022-06-29 pply Schemes for different u ply nvelope mentation 6 ss (Non Bank-SPD pazilas of sunamgonj district ) National Procure RWSHP-WD-49 / Community ment Document - based Small Piped Water sup 1. Investments in water sup Single Stage - One E Pending Imp 2022-11-1 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,146,038.85 0.00 2022-01-30 2022-02-04 2022-03-18 2022-04-17 2022-05-22 ply Schemes for Moulvibazar ply nvelope lementation 8 ss (Non Bank-SPD sadar and 1 upazila of mouvi ) bazar district National Procure RWSHP-WD-51 / Community ment Document - 1. Investments in water sup Single Stage - One E 2022-11-1 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 301,589.17 0.00 Signed 2022-01-27 2022-08-07 2022-02-01 2022-03-15 2022-08-24 2022-04-14 2023-01-10 2022-05-19 2023-02-16 ply nvelope 5 pply Scheme for Magura distr ss (Non Bank-SPD ict ) National Procure RWSHP-WD-53 / Community ment Document - 1. Investments in water sup Single Stage - One E Pending Imp 2022-11-1 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 603,178.34 0.00 2022-01-26 2022-01-31 2022-03-14 2022-04-13 2022-05-18 ply nvelope lementation 4 pply Scheme for Jhenaidah di ss (Non Bank-SPD strict ) National Procure RWSHP-WD-54 / Community ment Document - 1. Investments in water sup Single Stage - One E Under Imple 2022-11-1 based Small Piped Water su IDA / 67770 Post Request for Bids Open - National 1 Envelope proce 603,178.34 0.00 2022-01-27 2022-04-21 2022-02-01 2022-03-15 2022-05-17 2022-04-14 2022-05-22 2022-05-19 ply nvelope mentation 5 pply Scheme for Barisal distri ss (Non Bank-SPD ct 2 upazilas ) National Procure RWSHP-WD-56 / Community ment Document - 1. Investments in water sup Single Stage - One E Under Imple 2022-11-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 603,178.34 0.00 2022-02-03 2022-02-08 2022-03-22 2022-04-21 2022-05-26 ply nvelope mentation 2 pply Scheme for Patuakhali d ss (Non Bank-SPD istrict ) National Procure RWSHP-WD-57 / Community ment Document - 1. Investments in water sup Single Stage - One E 2022-11-1 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 603,178.34 0.00 Signed 2022-01-30 2022-03-21 2022-02-04 2022-03-18 2022-05-11 2022-04-17 2022-06-05 2022-05-22 2022-06-21 ply nvelope 8 pply Scheme for Pabna sadar ss (Non Bank-SPD and 1 upazila ) National Procure RWSHP-WD-58 / Community ment Document - 1. Investments in water sup Single Stage - One E Under Imple 2022-11-1 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 301,589.17 0.00 2022-01-31 2022-06-19 2022-02-05 2022-03-19 2022-07-05 2022-04-18 2022-07-18 2022-05-23 ply nvelope mentation 9 pply Scheme for Bogura distr ss (Non Bank-SPD ict ) National Procure RWSHP-WD-59 / Community ment Document - based Small Piped Water su 1. Investments in water sup Single Stage - One E 2022-11-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 603,178.34 436,002.74 Signed 2022-02-03 2022-03-27 2022-02-08 2022-03-22 2022-04-26 2022-04-21 2022-05-18 2022-05-26 2022-06-30 pply Scheme for Chapainaba ply nvelope 2 ss (Non Bank-SPD bganj district 2 upazila ) National Procure RWSHP-WD-60 / Community ment Document - 1. Investments in water sup Single Stage - One E 2022-11-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 603,178.34 393,882.68 Signed 2022-02-06 2022-03-27 2022-02-11 2022-03-25 2022-05-05 2022-04-24 2022-07-04 2022-05-29 2022-08-03 ply nvelope 5 pply Scheme for Rajbari distri ss (Non Bank-SPD ct ) National Procure RWSHP-WD-61 / Community ment Document - 1. Investments in water sup Single Stage - One E 2022-11-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 603,178.34 462,407.58 Signed 2022-02-02 2022-03-31 2022-02-07 2022-03-21 2022-05-09 2022-04-20 2022-06-14 2022-05-25 2022-06-24 ply nvelope 1 pply Scheme for Manikganj di ss (Non Bank-SPD strict ) National Procure RWSHP-WD-32 / Community ment Document - 1. Investments in water sup Single Stage - One E 2022-11-2 based Small Piped water sup COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 0.00 Signed 2022-02-06 2022-03-23 2022-02-11 2022-03-25 2022-05-05 2022-04-24 2022-05-22 2022-05-29 2022-06-29 ply nvelope 5 ply scheme ss (Non Bank-SPD ) National Procure RWSHP-WD-37 / Community ment Document - 1. Investments in water sup Single Stage - One E Under Imple 2022-11-2 based Small Piped water sup COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 2,292,077.69 0.00 2022-02-07 2022-03-23 2022-02-12 2022-03-26 2022-04-28 2022-04-25 2022-05-31 2022-05-30 ply nvelope mentation 6 ply scheme ss (Non Bank-SPD ) National Procure RWSHP-WD-45 / Community ment Document - 1. Investments in water sup Single Stage - One E Under Imple 2022-12-1 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 0.00 2022-03-02 2022-03-16 2022-03-07 2022-04-18 2022-04-27 2022-05-18 2022-06-22 ply nvelope mentation 9 pply Schemes ss (Non Bank-SPD ) National Procure RWSHP-WD-46 / Community- ment Document - 1. Investments in water sup Single Stage - One E Under Imple 2022-12-2 based Small Piped Water sup COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 0.00 2022-03-03 2022-03-28 2022-03-08 2022-04-19 2022-04-26 2022-05-19 2022-05-31 2022-06-23 ply nvelope mentation 0 ply Schemes for shylet distric ss (Non Bank-SPD t ) National Procure RWSHP-WD-42 / Community ment Document - 1. Investments in water sup Single Stage - One E Under Imple 2023-01-2 based small piped water sup COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 2,292,077.69 0.00 2022-04-07 2022-03-22 2022-04-12 2022-05-24 2022-04-25 2022-06-23 2022-05-24 2022-07-28 ply nvelope mentation 4 ply scheme ss (Non Bank-SPD ) National Procure RWSHP-WD-43 / Community ment Document - 1. Investments in water sup Single Stage - One E Under Imple 2023-01-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 0.00 2022-04-06 2022-04-11 2022-05-23 2022-06-22 2022-07-27 ply nvelope mentation 3 pply Scheme ss (Non Bank-SPD ) National Procure RWSHP-WD-44 / Community ment Document - 1. Investments in water sup Single Stage - One E 2023-01-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 0.00 Signed 2022-04-04 2022-03-24 2022-04-09 2022-05-21 2022-05-10 2022-06-20 2022-07-13 2022-07-25 2022-08-24 ply nvelope 1 pply Scheme ss (Non Bank-SPD ) RWSHP-WD-62 / Public sanit ation & hygiene facilities, Ne National Procure w Sanitation & hygiene facilit ment Document - ies in community clinics, + ru 2. Investments in sanitation Single Stage - One E 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 976,809.89 0.00 Signed 2022-04-04 2022-04-06 2022-04-09 2022-05-21 2022-05-10 2022-06-20 2022-10-04 2022-07-25 2022-12-12 nning water & associated faci and hygiene nvelope 1 ss (Non Bank-SPD lities in toilets of community ) clinics, Covid-19hand washin g station with running water by installing associated facilit ies Page 2 RWSHP-WD-63 / Public Sanit ation & hygiene facilities+Ne National Procure w Sanitation & hygiene facilit ment Document - ies in community clinics+ Pro 2. Investments in sanitation Single Stage - One E Pending Imp 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,465,214.83 0.00 2022-04-07 2022-04-12 2022-05-24 2022-06-23 2022-07-28 vision for running water &ass and hygiene nvelope lementation 4 ss (Non Bank-SPD ociated facilities in communit ) y clinics +Response to Covid- 19 handwashing station with running water & associated f acilities RWSHP-WD-64 / Public sanit ation & hygiene facilities+Ne National Procure w Sanitation & hygiene facilit ment Document - ies in community clinics+ Pro 2. Investments in sanitation Single Stage - One E Under Imple 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 732,607.42 0.00 2022-04-06 2022-04-06 2022-04-11 2022-05-23 2022-05-09 2022-06-22 2022-05-22 2022-07-27 vision for running water & as and hygiene nvelope mentation 3 ss (Non Bank-SPD sociated facilities of commu ) nity clinics +Response to Cov id-19 handwashing station wi th running water & associate d facilities RWSHP-WD-65 / Public sanit ation & hygiene facilities + N National Procure ew Sanitation & hygiene facil ment Document - ities in community clinics + P 2. Investments in sanitation Single Stage - One E 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,465,214.83 0.00 Signed 2022-04-05 2022-04-21 2022-04-10 2022-05-22 2022-06-09 2022-06-21 2022-06-21 2022-07-26 2022-07-25 rovision for running water & and hygiene nvelope 2 ss (Non Bank-SPD associated facilities in comm ) unity clinics +Response to C ovic-19 Sanitation facilities /s upplies, hand washing statio ns RWSHP-WD-66 / Public sanit ation & hygiene facilities + N National Procure ew Sanitation& hygiene facili ment Document - ties in community clinics + P 2. Investments in sanitation Single Stage - One E 1,882,188.3 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 2,197,822.25 Signed 2022-04-07 2022-04-11 2022-04-12 2022-05-24 2022-05-11 2022-06-23 2022-05-22 2022-07-28 2022-06-16 rovision for running water & and hygiene nvelope 9 4 ss (Non Bank-SPD associated facilities in comm ) unity clinics +Response to C ovic-19 Sanitation facilities /s upplies, hand washing statio n. RWSHP-WD-67 / Public sanit ation & hygiene facilities + N National Procure ew Sanitation & hygiene facil ment Document - ities in community clinics + P 2. Investments in sanitation Single Stage - One E 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 244,202.47 149,673.47 Signed 2022-04-06 2022-04-19 2022-04-11 2022-05-23 2022-05-09 2022-06-22 2022-05-19 2022-07-27 2022-07-22 rovision for running water & and hygiene nvelope 3 ss (Non Bank-SPD associated facilities in comm ) unity clinics toilets +Respons e to Covic-19 Sanitation facili ties, handwashing station. RWSHP-WD-68 / Public sanit ation & hygiene facilities + N National Procure ew Sanitation& hygiene facili ment Document - ties with Provision for runnin 2. Investments in sanitation Single Stage - One E 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 244,202.47 0.00 Signed 2022-04-05 2022-04-07 2022-04-10 2022-05-22 2022-04-24 2022-06-21 2022-05-17 2022-07-26 2022-06-11 g water & associated facilitie and hygiene nvelope 2 ss (Non Bank-SPD s in community clinics toilets ) +Response to Covic-19 Sanit ation facilities /supplies, han d washing station. RWSHP-WD-69 / Public sanit ation & hygiene facilities +N National Procure ew Sanitation & hygiene facil ment Document - ities in community clinics +Pr 2. Investments in sanitation Single Stage - One E Pending Imp 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 937,257.21 0.00 2022-04-06 2022-04-11 2022-05-23 2022-06-22 2022-07-27 ovision for running water & a and hygiene nvelope lementation 3 ss (Non Bank-SPD ssociated facilities communi ) ty clinics toilets +Response t o Covic-19 Sanitation facilitie s /supplies, handwashing stat ion RWSHP-WD-70 / Public sanit ation & hygiene facilities + N National Procure ew Sanitation&hygiene facilit ment Document - ies in community clinics +Pro 2. Investments in sanitation Single Stage - One E Under Imple 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,874,514.42 0.00 2022-04-06 2022-04-27 2022-04-11 2022-05-23 2022-06-05 2022-06-22 2022-07-06 2022-07-27 vision for running water& ass and hygiene nvelope mentation 3 ss (Non Bank-SPD ociated facilities in communit ) y clinics toilets +Response to Covic-19 Sanitation facilities /supplies, hand washing stat ion RWSHP-WD-71 / Public sanit ation & hygiene facilities +N National Procure ew Sanitation &hygiene facili ment Document - ties in community clinics +Pr 2. Investments in sanitation Single Stage - One E 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,640,200.12 0.00 Signed 2022-04-10 2022-03-23 2022-04-15 2022-05-27 2022-04-28 2022-06-26 2022-05-11 2022-07-31 2022-06-15 ovision for running water & a and hygiene nvelope 7 ss (Non Bank-SPD ssociated facilities in commu ) nity clinics toilets+Response to Covic-19 Sanitation faciliti es /supplies, hand washing st ation RWSHP-WD-72 / Public sanit ation &hygiene facilities + N National Procure ew Sanitation&hygiene facilit ment Document - ies in community clinics+Pro 2. Investments in sanitation Single Stage - One E Under Imple 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,874,514.42 0.00 2022-04-07 2022-04-12 2022-05-24 2022-06-23 2022-07-28 vision for running water &ass and hygiene nvelope mentation 4 ss (Non Bank-SPD ociated facilities in toilets of ) community clinics +Respons e to Covic-19 Sanitation facili ties /supplies, hand washing station. RWSHP-WD-73 / Public sanit ation&hygiene facilities + Ne National Procure w Sanitation&hygiene faciliti ment Document - es in community clinics +Pro 2. Investments in sanitation Single Stage - One E Pending Imp 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 702,942.91 0.00 2022-04-07 2022-04-12 2022-05-24 2022-06-23 2022-07-28 vision for running water& ass and hygiene nvelope lementation 4 ss (Non Bank-SPD ociated facilities in communit ) y clinics toilets +Response to Covic-19 Sanitation facilities /supplies, hand washing stat ion. RWSHP-WD-74 / Public sanit ation&hygiene facilities+New National Procure Sanitation &hygiene facilities ment Document - in community clinics +Provisi 2. Investments in sanitation Single Stage - One E Under Imple 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 702,942.91 0.00 2022-04-03 2022-03-31 2022-04-08 2022-05-20 2022-05-10 2022-06-19 2022-06-09 2022-07-24 on for running water& associ and hygiene nvelope mentation 0 ss (Non Bank-SPD ated facilities in community c ) linics toilets +Response to C ovic-19 Sanitation facilities /s upplies, hand washing statio n. RWSHP-WD-75 / Public sanit ation&hygiene facilities + Ne National Procure w Sanitation&hygiene faciliti ment Document - es in community clinics+Prov 2. Investments in sanitation Single Stage - One E Under Imple 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 702,942.91 0.00 2022-04-10 2022-04-15 2022-05-27 2022-06-26 2022-07-31 ision for running water & ass and hygiene nvelope mentation 7 ss (Non Bank-SPD ociated facilities in toilets of ) community clinics +Respons e to Covic-19 Sanitation facili ties /supplies, handwashing station Page 3 RWSHP-WD-76 / Public sanit ation& hygiene facilities + N National Procure ew Sanitation &hygiene facili ment Document - ties in community clinics + P 2. Investments in sanitation Single Stage - One E Pending Imp 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 702,942.91 0.00 2022-04-10 2022-04-15 2022-05-27 2022-06-26 2022-07-31 rovision for running water&a and hygiene nvelope lementation 7 ss (Non Bank-SPD ssociated facilities in commu ) nity clinics toilets +Response to Covic-19 Sanitation faciliti es /supplies, hand washing s tation. RWSHP-WD-77 / Public sanit ation &hygiene facilities + N National Procure ew Sanitation&hygiene facilit ment Document - ies in community clinics +Pro 2. Investments in sanitation Single Stage - One E 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 702,942.91 0.00 Signed 2022-04-10 2022-04-21 2022-04-15 2022-05-27 2022-05-22 2022-06-26 2022-06-16 2022-07-31 2022-07-27 vision for running water &ass and hygiene nvelope 7 ss (Non Bank-SPD ociated facilities in toilets of ) community clinics +Respons e to Covic-19 Sanitation facili ties /supplies, handwashing station RWSHP-WD-78 / Public sanit ation& hygiene facilities + N National Procure ew Sanitation&hygiene facilit ment Document - ies in community clinics +Pro 2. Investments in sanitation Single Stage - One E Under Imple 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 937,257.21 0.00 2022-04-06 2022-04-06 2022-04-11 2022-05-23 2022-05-09 2022-06-22 2022-05-17 2022-07-27 vision for running water &ass and hygiene nvelope mentation 3 ss (Non Bank-SPD ociated facilities in toilets of ) community clinics +Respons e to Covic-19 Sanitation facili ties /supplies, hand washing station RWSHP-WD-79 / Public sanit ation & hygiene facilities +N National Procure ew Sanitation&hygiene facilit ment Document - ies in community clinics +Pro 2. Investments in sanitation Single Stage - One E Under Imple 2023-01-2 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 488,404.94 0.00 2022-04-06 2022-04-26 2022-04-11 2022-05-23 2022-05-18 2022-06-22 2022-08-03 2022-07-27 vision for running water & as and hygiene nvelope mentation 3 ss (Non Bank-SPD sociated facilities in toilets of ) community clinics+Response to Covic-19 Sanitation faciliti es /supplies, handwashing st ation National Procure RWSHP-WD-29 / Community ment Document - 1. Investments in water sup Single Stage - One E 2023-07-0 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 0.00 Signed 2022-09-15 2022-09-19 2022-09-20 2022-11-01 2022-10-23 2022-12-01 2022-12-08 2023-01-05 2023-02-27 ply nvelope 4 pply Scheme at Jamalpur Dist ss (Non Bank-SPD rict ) National Procure RWSHP-WD-35 / Community ment Document - 1. Investments in water sup Single Stage - One E 2023-07-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 2,865,097.12 0.00 Signed 2022-10-09 2022-09-08 2022-10-14 2022-11-25 2022-10-20 2022-12-25 2022-11-08 2023-01-29 2022-12-13 ply nvelope 8 pply Schemes at Kurigram Di ss (Non Bank-SPD strict ) National Procure RWSHP-WD-36 / Community ment Document - 1. Investments in water sup Single Stage - One E Under Imple 2023-07-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 0.00 2022-10-09 2022-10-14 2022-11-25 2022-12-25 2023-01-29 ply nvelope mentation 8 pply Scheme at Brahmanbari ss (Non Bank-SPD a District ) National Procure RWSHP-WD-38 / Community ment Document - 1. Investments in water sup Single Stage - One E Under Imple 2023-07-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 2,292,077.69 0.00 2022-10-06 2023-01-22 2022-10-11 2022-11-22 2023-02-06 2022-12-22 2023-02-14 2023-01-26 ply nvelope mentation 5 pply Scheme at Chandpur Di ss (Non Bank-SPD strict ) National Procure RWSHP-WD-39 / Community ment Document - 1. Investments in water sup Single Stage - One E 2023-07-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 0.00 Signed 2022-10-10 2022-09-19 2022-10-15 2022-11-26 2022-10-24 2022-12-26 2023-01-02 2023-01-30 2023-02-22 ply nvelope 9 pply Scheme at Chottogram ss (Non Bank-SPD District ) National Procure RWSHP-WD-47 / Community ment Document - 1. Investments in water sup Single Stage - One E 2023-07-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 0.00 Signed 2022-10-05 2022-09-13 2022-10-10 2022-11-21 2022-10-12 2022-12-21 2022-10-31 2023-01-25 2022-11-06 ply nvelope 4 pply Scheme at Habigonj Dist ss (Non Bank-SPD rict ) National Procure RWSHP-WD-33 / Community ment Document - 1. Investments in water sup Single Stage - One E Under Imple 2023-07-2 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 1,719,058.27 0.00 2022-10-06 2022-10-11 2022-11-22 2022-12-22 2023-01-26 ply nvelope mentation 5 pply Schemes at Gaibandha ss (Non Bank-SPD District ) National Procure RWSHP-WD-55 / Community ment Document - 1. Investments in water sup Single Stage - One E Pending Imp 2024-08-1 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 301,589.17 0.00 2023-10-30 2023-11-04 2023-12-16 2024-01-15 2024-02-19 ply nvelope lementation 7 pply Scheme for Pirojpur dist ss (Non Bank-SPD rict ) National Procure RWSHP-WD-52 / Community ment Document - based Small Piped Water su 1. Investments in water sup Single Stage - One E Pending Imp 2024-08-1 COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 603,178.34 0.00 2023-10-26 2023-10-31 2023-12-12 2024-01-11 2024-02-15 pply Schemes for Bagerhat di ply nvelope lementation 3 ss (Non Bank-SPD strict 2 upazilas ) National Procure RWSHP-WD-50 / Community ment Document - 1. Investments in water sup Single Stage - One E Pending Imp 2024-08-1 based Small Piped Water su COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 301,589.17 0.00 2023-10-29 2023-11-03 2023-12-15 2024-01-14 2024-02-18 ply nvelope lementation 6 pply Scheme for 1 upazila of ss (Non Bank-SPD khulna district ) National Procure RWSHP-WD-27 / Community ment Document - 1. Investments in water sup Single Stage - One E Pending Imp 2024-08-2 based small piped water sup COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 450,722.22 0.00 2023-11-06 2023-11-11 2023-12-23 2024-01-22 2024-02-26 ply nvelope lementation 4 ply scheme at Chottogram di ss (Non Bank-SPD strict. ) National Procure RWSHP-WD-25 / Community ment Document - 1. Investments in water sup Single Stage - One E Pending Imp 2024-08-3 based small piped water sup COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 450,722.22 0.00 2023-11-13 2023-11-18 2023-12-30 2024-01-29 2024-03-04 ply nvelope lementation 1 ply scheme at Nilphamari dis ss (Non Bank-SPD trict. ) National Procure RWSHP-WD-23 / Community ment Document - 1. Investments in water sup Single Stage - One E Pending Imp 2024-08-2 based small piped water sup COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 450,722.22 0.00 2023-11-07 2023-11-12 2023-12-24 2024-01-23 2024-02-27 ply nvelope lementation 5 ply scheme at Jamalpur distri ss (Non Bank-SPD ct. ) National Procure RWSHP-WD-26 / Community ment Document - 1. Investments in water sup Single Stage - One E Pending Imp 2024-08-2 based small piped water sup COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 450,722.22 0.00 2023-11-09 2023-11-14 2023-12-26 2024-01-25 2024-02-29 ply nvelope lementation 7 ply scheme at Brahmanbaria ss (Non Bank-SPD district. ) National Procure RWSHP-WD-24 / Community ment Document - 1. Investments in water sup Single Stage - One E Pending Imp 2024-08-3 based small piped water sup COFN / C1840 Post Request for Bids Open - National 1 Envelope proce 450,722.22 0.00 2023-11-12 2023-11-17 2023-12-29 2024-01-28 2024-03-03 ply nvelope lementation 0 ply scheme at Lalmonirhat di ss (Non Bank-SPD strict. ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RWSHP-GD-01 / Computer w 4. Project implementation an Single Stage - One E Under Imple ith printer and scanner for P COFN / C1840 Post Request for Bids Open - National 45,404.86 0.00 2022-03-15 2022-07-04 2022-03-20 2022-05-01 2022-05-31 2022-07-05 2023-01-01 d management nvelope mentation MU and DPHE field offices. RWSHP-GD-03 / Procuremen 4. Project implementation an Single Stage - One E Under Imple COFN / C1840 Post Request for Bids Open - National 7,062.98 0.00 2022-03-16 2022-05-12 2022-03-21 2022-05-02 2022-06-01 2022-07-06 2023-01-02 t of Photocopy machine d management nvelope mentation Page 4 RWSHP-GD-04 / Procuremen 4. Project implementation an Single Stage - One E Under Imple IDA / 67770 Post Request for Bids Open - National 17,657.45 0.00 2022-02-17 2022-05-08 2022-02-22 2022-04-05 2022-05-05 2022-06-09 2022-12-06 t of Office equipment d management nvelope mentation RWSHP-GD-06 / Procuremen 4. Project implementation an Single Stage - One E Under Imple COFN / C1840 Post Request for Bids Open - National 29,429.08 0.00 2022-03-22 2022-04-24 2022-03-27 2022-05-08 2022-06-07 2022-07-12 2023-01-08 t of Furniture & Fixtures d management nvelope mentation RWSHP-GD-02 / Computer w 4. Project implementation an Single Stage - One E Pending Impl ith printer and scanner for P COFN / C1840 Post Request for Bids Open - National 80,768.00 0.00 2023-10-08 2023-10-13 2023-11-24 2023-12-24 2024-01-28 2024-07-26 d management nvelope ementation MU and DPHE field offices. RWSHP-GD-05 / Procuremen 4. Project implementation an Single Stage - One E Pending Impl COFN / C1840 Post Request for Bids Open - National 13,900.00 0.00 2023-10-09 2023-10-14 2023-11-25 2023-12-25 2024-01-29 2024-07-27 t of Office Equipment d management nvelope ementation RWSHP-GD-07 / Procuremen 4. Project implementation an Single Stage - One E Pending Impl COFN / C1840 Post Request for Bids Open - National 13,900.00 0.00 2023-10-12 2023-10-17 2023-11-28 2023-12-28 2024-02-01 2024-07-30 t of Furniture & Fixtures d management nvelope ementation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RWSHP-SD-15 / Pre-feasibilit 1. Investments in water sup Quality And Cost- y Study, Design and supervi IDA / 67770 Prior Open - National 3,237,198.35 3,168,739.33 Signed 2021-08-19 2021-09-02 2021-09-09 2021-09-08 2021-10-23 2021-12-21 2021-11-20 2022-01-30 2021-12-20 2022-03-09 2022-01-24 2022-05-09 2022-02-28 2022-07-31 2023-02-28 ply Based Selection sion Technical Assistance co nsultancy RWSHP-SD-20 / feasibility st udy on appropriate water sup 1. Investments in water sup Quality And Cost- IDA / 67770 Prior Open - National 2,530,900.53 0.00 Signed 2021-09-25 2021-12-13 2021-10-16 2021-12-14 2021-11-29 2022-04-10 2021-12-27 2022-05-26 2022-01-26 2022-06-26 2022-03-02 2022-08-31 2022-04-06 2022-11-28 2023-04-06 ply technologies in climate ri ply Based Selection sk hot spots of coastal Areas RWSSP-SD-2 / Technical Assi stance (TA) Firm to develop Behavioral Change Communi 2. Investments in sanitation Quality And Cost- cation (BCC) materials for Ca COFN / C1840 Post Open - National 2,618,180.11 0.00 Signed 2022-02-17 2022-02-03 2022-03-10 2022-02-16 2022-04-23 2022-06-13 2022-05-21 2022-07-26 2022-06-20 2022-08-22 2022-07-25 2023-01-29 2022-08-29 2023-03-29 2023-08-29 and hygiene Based Selection mpaign, training manuals (fo r Local Government Institutio ns - LGIs & Health Workers), and their capacity building RWSHP-SD-3 / Technical Assi stance (TA) Firm for Behavio ural Change Communication 2. Investments in sanitation Quality And Cost- COFN / C1840 Prior Open - National 2,618,180.11 0.00 Signed 2022-06-28 2022-03-22 2022-07-19 2022-05-19 2022-09-01 2022-09-11 2022-09-29 2022-10-27 2022-10-29 2023-02-19 2022-12-03 2023-05-28 2023-01-07 2023-07-23 2024-01-07 (BCC) Campaign, training (for and hygiene Based Selection Local Government Institution s - LGIs & Health Workers) an d their capacity building. RWSHP-SD-18 / Selection of I T Firm for Providing Technica 3. Institutional strengthenin Consultant Qualifi l Assistance to Develop Infor COFN / C1840 Post Open - National 323,719.84 0.00 Signed 2022-09-14 2022-09-07 2022-10-05 2022-09-13 2022-11-18 2023-03-14 2022-12-18 2023-05-11 2023-01-22 2023-06-07 2023-07-21 g cation Selection mation Management and Vis ualization System for Project Monitoring. RWSHP-SD-14 / Assessing an d Piloting Innovative Integrat 2. Investments in sanitation Quality And Cost- Under Implement COFN / C1840 Post Open - National 179,629.62 0.00 2023-08-14 2023-08-08 2023-09-04 2023-08-13 2023-10-18 2023-11-15 2023-12-15 2024-01-19 2024-02-23 2025-02-22 ed Waste Management Syste and hygiene Based Selection ation m (fecal sludge and solid was te) for Rural Areas RWSHP-SD-19 / Engagement 3. Institutional strengthenin Quality And Cost- Pending Impleme COFN / C1840 Post Open - National 55,555.00 0.00 2023-09-25 2023-10-16 2023-11-29 2023-12-27 2024-01-26 2024-03-01 2024-04-05 2025-04-05 of Internal Audit Firm g Based Selection ntation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RWSHP-SD-04A / Financial M 4. Project implementation an Individual Consult IDA / 67770 Post Open 176,574.45 178,482.15 Signed 2021-06-30 2021-06-30 2021-08-18 2021-10-27 2021-09-08 2021-11-01 2021-10-13 2021-12-16 2022-04-11 anagement Specialist d management ant Selection RWSHP-SD-05A / Procureme 4. Project implementation an Individual Consult IDA / 67770 Prior Open 176,574.45 145,055.06 Signed 2021-06-30 2021-06-30 2021-08-18 2021-10-24 2021-09-08 2021-12-03 2021-10-13 2021-12-09 2022-04-11 nt Specialist d management ant Selection RWSHP-SD-07A / Water Sup 4. Project implementation an Individual Consult IDA / 67770 Post Open 176,574.45 182,190.09 Signed 2021-06-30 2021-06-30 2021-08-18 2021-10-24 2021-09-08 2021-10-31 2021-10-13 2021-11-26 2022-04-11 ply Specialist d management ant Selection RWSHP-SD-08A / Hydrogeolo 4. Project implementation an Individual Consult IDA / 67770 Post Open 170,688.64 182,190.09 Signed 2021-06-30 2021-06-30 2021-08-18 2021-10-27 2021-09-08 2021-11-01 2021-10-13 2021-11-26 2022-04-11 gist d management ant Selection RWSHP-SD-06 / Monitoring a 4. Project implementation an Individual Consult IDA / 67770 Post Open 170,688.64 166,059.36 Signed 2021-08-26 2021-09-13 2021-10-14 2022-02-27 2021-11-04 2022-03-07 2021-12-09 2022-04-03 2022-06-07 nd Evaluation Specialist d management ant Selection RWSHP-SD_09 / Environmen 4. Project implementation an Individual Consult IDA / 67770 Post Open 170,688.64 147,018.14 Signed 2021-08-26 2021-09-13 2021-10-14 2022-04-28 2021-11-04 2022-04-28 2021-12-09 2022-06-04 2022-06-07 tal Safeguard Specialist d management ant Selection RWSHP-SD-10 / Social Safeg 4. Project implementation an Individual Consult IDA / 67770 Post Open 170,688.64 166,059.36 Signed 2021-08-26 2021-09-13 2021-10-14 2022-02-27 2021-11-04 2022-03-07 2021-12-09 2022-04-03 2022-06-07 uard Specialist d management ant Selection P169342/RWSHP/SD-08 / Hy 4. Project implementation an Individual Consult IDA / 67770 Post Open 170,688.64 0.00 Canceled 2021-05-05 2021-04-29 2021-06-23 2021-07-14 2021-08-18 2022-02-14 drogeologist d management ant Selection P169342/RWSHP/SD-07 / Wa 4. Project implementation an Individual Consult IDA / 67770 Post Open 176,574.45 0.00 Canceled 2021-05-05 2021-04-29 2021-06-23 2021-07-14 2021-08-18 2022-02-14 ter Supply Specialist d management ant Selection P169342/RWSHP-SD-05 / Pro 4. Project implementation an Individual Consult IDA / 67770 Post Open 176,574.45 0.00 Canceled 2021-05-05 2021-04-29 2021-06-23 2021-07-14 2021-08-18 2022-02-14 curement Specialist d management ant Selection Page 5 P169342/RWSHP-SD-04 / Fin 4. Project implementation an Individual Consult IDA / 67770 Post Open 176,574.45 0.00 Canceled 2021-05-05 2021-04-29 2021-06-23 2021-07-14 2021-08-18 2022-02-14 ancial Management Specialis d management ant Selection t RWSHP-SD-12 / District Leve 4. Project implementation an Individual Consult COFN / C1840 Prior Open - National 734,549.73 0.00 Signed 2022-09-15 2022-09-14 2022-11-03 2023-05-21 2022-11-24 2023-06-18 2022-12-29 2023-07-14 2023-06-27 l Coordinator-13 Nos. d management ant Selection RWSHP-SD-11 / District Leve 4. Project implementation an Individual Consult COFN / C1840 Prior Open - National 678,045.90 0.00 Signed 2022-09-14 2022-09-14 2022-11-02 2023-05-18 2022-11-23 2023-06-18 2022-12-28 2023-07-14 2023-06-26 l Coordinator- 12 Nos. d management ant Selection Page 6