PROCUREMENT PLAN TEXTUAL PART Project information Country : Turkey Project Name : Green Industry Project Project Number : P179255 Project Implementation Agency: Ministry of Industry and Technology (MoIT), Directorate General for Industry (DGI) Date of the Procurement Plan: 28 April, 2023 Period covered by this Procurement Plan: 28 April, 2023 – 28 October, 2024 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Project Implementing Agency will select in STEP if the relevant procurement activity’s cost estimate will be published or not in the external web-site of the World Bank. II. Goods, Works and Non-consulting Services Procurement Procurement Method Prior Review Threshold Method Threshold Default Method for Good, Contract valued > USD RFB (International Works and Non-consulting 10M Works and > USD 2M Open Competition) Services (No selection for Goods and Non- method threshold) Consulting Services 1 Contracts valued < USD Contracts valued > USD RFB (National Open 30M for Works and < USD 10M for Works and > USD Competition) 2M for Goods and Non- 2M for Goods and Non- Consulting Services Consulting Services Works Contracts valued < USD200,000 – Goods and No prior review RFQ Non-consulting Services Contracts valued < USD100,000 Works Direct Selection No threshold. Justification Contracts valued ≥ USD is required at the PP 10M for Works and ≥ USD approval. 2M for Goods and Non- Consulting Services Commercial Practices No threshold. Used by No prior review. private beneficiaries only. III. Selection of Consultants Selection Method Selection Method Prior Review Threshold Threshold Quality and Cost Default Method (No Contract valued ≥ USD Based Selection selection method 1M (QCBS) threshold) Selection Based on Contracts valued < No prior review Consultants USD300,000 Qualification (CQS) Least Cost Selection No selection Method Contract valued ≥ USD (LCS) threshold 1M Direct Selection (DIR) No selection method Contract valued ≥ USD threshold 1M Justification is required at the PP approval Individual Consultants No selection method Contracts valued ≥ (INDV) threshold USD300,000 Commercial Practices No threshold. Used by No prior review. private beneficiaries only. The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1. The Bank’s Standard Procurement Documents: Shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. 2 For the procurements not subject to international competitive selection, Turkish translation of the Bank’s Standard Procurement Documents (SPD) with minor modifications will be used as to fit for purpose or the procurement documents agreed by the Bank shall be used. 2. Commercial Practices: The procurements under Components 1 and 2 of the Project shall be conducted by the beneficiaries in accordance with their well-established commercial practices as stipulated in the POM and confirmed by KOSGEB and TUBITAK respectively that these practices are consistent with the Bank’s Core Procurement Principles of value for money, economy, integrity, fit for purpose, efficiency, transparency and fairness. A list of the procurements performed by the beneficiaries under the Components 1 and 2 of the Project shall be recorded in a format agreed by the Bank and specified in the POM and these records will be uploaded into STEP by the KOSGEB/TUBITAK at least annually but not later than closing date of the project. 3. Review Procedure: The procurements under the project are subject to the Bank’s prior review as stipulated in above Paragraphs II and III and also as specified in the procurement schedule given below in Section V, and in STEP. 4. Procurement of Second Hand Goods: Not Applicable 5. Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable 6. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable 7. Procurement Packages with Methods and Time Schedule The estimated costs given in the attached tables include VAT. 3 PROCUREMENT PLAN TEXTUAL PART Project information Country : Turkey Project Name : Green Industry Project Project Number : P179255 Project Implementation Agency: KOSGEB Date of the Procurement Plan: April 28, 2023 Period covered by this Procurement Plan: April 08, 2023 – October 08, 2024 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan tables. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Project Implementing Agency will select in STEP if the relevant procurement activity’s cost estimate will be published or not in the external web-site of the World Bank. II. Goods, Works and Non-consulting Services Procurement Procurement Method Prior Review Threshold Method Threshold RFB (International Default Method for Good, Contract valued ≥ USD 10M Open Works and Non-consulting Works and ≥ USD 2M for Competition) Services (No selection method Goods and Non-Consulting threshold) Services RFB (National Contracts valued < USD 30M Contracts valued ≥ USD 10M Open for Works and < USD 2M for for Works and ≥ USD 2M for Competition) Goods and Non-Consulting Goods and Non-Consulting Services Services 4 RFQ Works Contracts valued < No prior review USD200,000 – Goods and Non-consulting Services Contracts valued < USD100,000 Works Direct Selection No threshold. Justification is Contracts valued ≥ USD 10M required at the PP approval. for Works and ≥ USD 2M for Goods and Non-Consulting Services Commercial No threshold. Used by private No prior review. Practices beneficiaries only. III. Selection of Consultants Selection Method Selection Method Prior Review Threshold Threshold Quality and Cost Default Method (No Contract valued ≥ USD Based Selection selection method 1M (QCBS) threshold) Selection Based on Contracts valued < No prior review Consultants USD300,000 Qualification (CQS) Least Cost Selection No selection Method Contract valued ≥ USD (LCS) threshold 1M Direct Selection (DIR) No selection method Contract valued ≥ USD threshold 1M Justification is required at the PP approval Individual Consultants No selection method Contracts valued ≥ (INDV) threshold USD300,000 Commercial Practices No threshold. Used by No prior review. private beneficiaries only. The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1.The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection, Turkish translation of the Bank’s Standard Procurement Documents (SPD) with minor modifications will be used as to fit for 5 purpose or the procurement documents agreed by the Bank shall be used. 2. Commercial Practices: The procurements under Components 1 and 2 of the Project shall be conducted by the beneficiaries in accordance with their well-established commercial practices as stipulated in the POM and confirmed by KOSGEB and TUBITAK respectively that these practices are consistent with the Bank’s Core Procurement Principles of value for money, economy, integrity, fit for purpose, efficiency, transparency and fairness. A list of the procurements performed by the beneficiaries under the Components 1 and 2 of the Project shall be recorded in a format agreed by the Bank and specified in the POM and these records will be uploaded into STEP by the KOSGEB/TUBITAK at least annually but not later than closing date of the project. 3.Review Procedure: The procurements under the project are subject to the Bank’s prior review as stipulated in above Paragraphs II and III and also as specified in the procurement schedule given below in Section V, and in STEP. 4.Procurement of Second Hand Goods: Not Applicable 5.Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable 6.Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. 7. Procurement Packages with Methods and Time Schedule The estimated costs given in the attached tables include VAT. 6 PROCUREMENT PLAN TEXTUAL PART Project information Country : Türkiye Project Name : Green Industry Project Project Number : P179255 Project Implementation Agency: TÜBİTAK Date of the Procurement Plan: April 28, 2023 Period covered by this Procurement Plan: April 28, 2023 – October 28, 2024 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan tables. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Project Implementing Agency will select in STEP if the relevant procurement activity’s cost estimate will be published or not in the external web-site of the World Bank. II. Goods, Works and Non-consulting Services Procurement Procurement Method Prior Review Threshold Method Threshold RFB Default Method for Good, Contract valued ≥ USD 10M (International Works and Non-consulting Works and ≥ USD 2M for Open Services (No selection method Goods and Non-Consulting Competition) threshold) Services RFB (National Contracts valued < USD 30M Contracts valued ≥ USD 10M Open for Works and < USD 2M for for Works and ≥ USD 2M for Competition) Goods and Non-Consulting Goods and Non-Consulting Services Services 7 RFQ Works Contracts valued < No prior review USD200,000 – Goods and Non- consulting Services Contracts valued < USD100,000 Works Direct Selection No threshold. Justification is Contracts valued ≥ USD 10M required at the PP approval. for Works and ≥ USD 2M for Goods and Non-Consulting Services Commercial No threshold. Used by private No prior review. Practices beneficiaries only. III. Selection of Consultants Selection Method Selection Method Prior Review Threshold Threshold Quality and Cost Default Method (No Contract valued ≥ USD Based Selection selection method 1M (QCBS) threshold) Selection Based on Contracts valued < No prior review Consultants USD300,000 Qualification (CQS) Least Cost Selection No selection Method Contract valued ≥ USD (LCS) threshold 1M Direct Selection (DIR) No selection method Contract valued ≥ USD threshold 1M Justification is required at the PP approval Individual Consultants No selection method Contracts valued ≥ (INDV) threshold USD300,000 Commercial Practices No threshold. Used by No prior review. private beneficiaries only. The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1.The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection, Turkish translation of the Bank’s Standard Procurement Documents (SPD) with minor modifications will be used as to fit for purpose or the procurement documents agreed by the Bank shall be used. 8 2. Commercial Practices: The procurements under Components 1 and 3 of the Project shall be conducted by the beneficiaries in accordance with their well-established commercial practices as stipulated in the POM and confirmed by KOSGEB and TÜBİTAK respectively that these practices are consistent with the Bank’s Core Procurement Principles of value for money, economy, integrity, fit for purpose, efficiency, transparency and fairness. A list of the procurements performed by the beneficiaries under the Components 1 and 2 of the Project shall be recorded in a format agreed by the Bank and specified in the POM and these records will be uploaded into STEP by the KOSGEB/TÜBİTAK at least annually but not later than closing date of the project. 3.Review Procedure: The procurements under the project are subject to the Bank’s prior review as stipulated in above Paragraphs II and III and also as specified in the procurement schedule given below in Section V, and in STEP. 4.Procurement of Second Hand Goods: Not Applicable 5.Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable 6.Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. 7. Procurement Packages with Methods and Time Schedule The estimated costs given in the attached tables include VAT. 9 PROCUREMENT Turkiye : Türkiye Green Industry Project PLAN General Information Country: Turkiye 2024-02-14 Bank’s Approval Date of the Original Procurement Plan: 2024-09-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P179255 GPN Date: 2023-09-04 Project Name: Türkiye Green Industry Project Loan / Credit No: IBRD / 95390, IBRD / 95380 THE SCIENTIFIC AND TECHNOLOGICAL RESEARCH COUNCIL OF TÜRKİYE Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TUBITAK -G-RFQ-1 / 25 lapto Project management and ins Request for Quota Single Stage - One E IBRD / 95390 Post Limited - National 47,500.00 0.00 Completed 2024-02-19 2024-02-19 2024-03-06 2024-03-22 2024-03-08 2024-05-15 ps and 2 laser printers titutional development tions nvelope TUBITAK-G-RFQ-2 / Purchasi ng financial scoring software Project management and ins Request for Quota Single Stage - One E to analyze the financial situat IBRD / 95390 Post Limited - National 24,686.99 0.00 Signed 2024-05-08 2024-05-08 2024-06-10 2025-06-10 titutional development tions nvelope ions of beneficiaries who app lied to the project within the scope of the World Bank proj ect NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TÜBİTAK CS-INDV-1 / Employ Project management and ins Individual Consult ment of Financial Manageme IBRD / 95390 Post Open - National 217,000.00 0.00 Canceled 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-04-22 2024-05-01 2029-06-30 titutional development ant Selection nt Consultant TÜBİTAK CS-INDV-4 / Employ Project management and ins Individual Consult ment of Procurement and Co IBRD / 95390 Prior Open - National 108,500.00 0.00 Canceled 2024-03-11 2024-03-14 2024-04-05 2024-04-07 2024-05-01 2029-06-30 titutional development ant Selection ntract Management Consulta nt (part time) TÜBİTAK CS-INDV-2 / Employ Project management and ins Individual Consult ment of Monitoring and Evalu IBRD / 95390 Post Open - National 217,000.00 0.00 Canceled 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-13 2024-05-01 2029-06-30 titutional development ant Selection ation Consultant TÜBİTAK CS-INDV-3 / Employ Project management and ins Individual Consult IBRD / 95390 Post Open - National 217,000.00 0.00 Signed 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-13 2024-05-01 2029-06-30 ment of Environmental Cons titutional development ant Selection ultant -1- TÜBİTAK CS-INDV-5 / Employ Project management and ins Individual Consult ment of Occupational Health IBRD / 95390 Post Open - National 217,000.00 0.00 Signed 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-13 2024-05-01 2024-05-31 2029-06-30 titutional development ant Selection and Safety Consultant -1- TÜBİTAK CS-INDV-6 / Employ Project management and ins Individual Consult IBRD / 95390 Post Open - National 217,000.00 0.00 Signed 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-13 2024-05-01 2024-05-31 2029-06-30 ment of Social Consultant -1- titutional development ant Selection TÜBİTAK CS-INDV-7 / Employ Project management and ins Individual Consult IBRD / 95390 Post Open - National 246,000.00 0.00 Canceled 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-01 2029-06-30 ment of IT -1- titutional development ant Selection TÜBİTAK CS-INDV-9 / Employ Project management and ins Individual Consult IBRD / 95390 Post Open - National 217,000.00 0.00 Signed 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-13 2024-05-01 2029-06-30 ment of Social Consultant -2- titutional development ant Selection TÜBİTAK CS-INDV-10 / Emplo Project management and ins Individual Consult IBRD / 95390 Post Open - National 217,000.00 0.00 Canceled 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-01 2029-06-30 yment of Social Consultant -3 titutional development ant Selection - TÜBİTAK CS-INDV-11 / Emplo Project management and ins Individual Consult yment of Occupational Healt IBRD / 95390 Post Open - National 217,000.00 0.00 Signed 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-13 2024-05-01 2024-05-31 2029-06-30 titutional development ant Selection h and Safety Consultant -2- TÜBİTAK CS-INDV-12 / Emplo Project management and ins Individual Consult yment of Occupational Healt IBRD / 95390 Post Open - National 217,000.00 0.00 Canceled 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-01 2029-06-30 titutional development ant Selection h and Safety Consultant -3- TÜBİTAK CS-INDV-13 / Emplo Project management and ins Individual Consult yment of Environmental Con IBRD / 95390 Post Open - National 217,000.00 0.00 Canceled 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-01 2029-06-30 titutional development ant Selection sultant -2- TÜBİTAK CS-INDV-14 / Emplo Project management and ins Individual Consult yment of Environmental Con IBRD / 95390 Post Open - National 217,000.00 0.00 Canceled 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-01 2029-06-30 titutional development ant Selection sultant -3- TÜBİTAK CS-INDV-8 / Employ Project management and ins Individual Consult IBRD / 95390 Post Open - National 246,000.00 0.00 Canceled 2024-03-11 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-01 2029-06-30 ment of IT -2- titutional development ant Selection Page 1 TÜBİTAK CS-INDV-R1 / Empl Project management and ins Individual Consult oyment of Financial Manage IBRD / 95380 Post Open - National 217,000.00 0.00 Canceled 2024-03-08 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-13 2024-05-01 2029-06-30 titutional development ant Selection ment Consultant TÜBİTAK CS-INDV-R2 / Empl Project management and ins Individual Consult oyment of Monitoring and Ev IBRD / 95390 Post Open - National 217,000.00 0.00 Canceled 2024-03-08 2024-03-11 2024-04-05 2024-04-05 2024-04-07 2024-05-13 2024-05-01 2029-06-30 titutional development ant Selection aluation Consultant TÜBİTAK CS-INDV-N3 / Empl Project management and ins Individual Consult Under Implement oyment of Environmental Co IBRD / 95390 Post Open - National 217,000.00 0.00 2024-08-07 2024-08-06 2024-09-06 2024-09-10 2024-10-01 2029-06-30 titutional development ant Selection ation nsultant -1- TÜBİTAK CS-INDV-N8 / Empl Project management and ins Individual Consult Under Implement oyment of Environmental Co IBRD / 95390 Post Open - National 217,000.00 0.00 2024-08-07 2024-08-06 2024-09-06 2024-09-10 2024-10-01 2029-06-30 titutional development ant Selection ation nsultant -2- TÜBİTAK CS-INDV-N5 / Empl Project management and ins Individual Consult Under Implement oyment of Occupational Heal IBRD / 95390 Post Open - National 217,000.00 0.00 2024-08-07 2024-08-06 2024-09-06 2024-09-10 2024-10-01 2029-06-30 titutional development ant Selection ation th and Safety Consultant TÜBİTAK CS-INDV-N6 / Empl Project management and ins Individual Consult Under Implement IBRD / 95390 Post Open - National 217,000.00 0.00 2024-08-07 2024-08-06 2024-09-06 2024-09-10 2024-10-01 2029-06-30 oyment of Social Consultant titutional development ant Selection ation TÜBİTAK CS-INDV-N7 / Empl Project management and ins Individual Consult Under Implement IBRD / 95390 Post Open - National 248,000.00 0.00 2024-08-07 2024-08-06 2024-09-06 2024-09-10 2024-10-01 2029-06-30 oyment of IT -1- titutional development ant Selection ation TÜBİTAK CS-INDV-N9 / Empl Project management and ins Individual Consult Under Implement IBRD / 95390 Post Open - National 248,000.00 0.00 2024-08-07 2024-08-06 2024-09-06 2024-09-10 2024-10-01 2029-06-30 oyment of IT -2- titutional development ant Selection ation TÜBİTAK CS-INDV-N4 / Empl Project management and ins Individual Consult Under Implement oyment of Procurement and IBRD / 95390 Prior Open - National 108,500.00 0.00 2024-08-07 2024-08-06 2024-09-22 2024-10-07 2024-11-01 2029-06-30 titutional development ant Selection ation Contract Management Consu ltant (part time) TÜBİTAK CS-INDV-R3 / Empl Project management and ins Individual Consult Pending Impleme oyment of Financial Manage IBRD / 95380 Post Open - National 217,000.00 0.00 2024-03-08 2024-04-05 2024-04-07 2024-05-01 2029-06-30 titutional development ant Selection ntation ment Consultant TÜBİTAK CS-INDV-R4 / Empl Project management and ins Individual Consult Pending Impleme oyment of Monitoring and Ev IBRD / 95380 Post Open - National 217,000.00 0.00 2024-03-08 2024-04-05 2024-04-07 2024-05-01 2029-06-30 titutional development ant Selection ntation aluation Consultant Page 2