PROCUREMENT PLAN (Textual Part) Project information: Honduras Water Security in the Dry Corridor of Honduras (P169901) Project Implementation agency: Inversiones Estratégicas de Honduras (INVEST-H) Date of the Procurement Plan: 05/07/2021 Period covered by this Procurement Plan: 05/07/2021-05/07/2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised in November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Ley de Contratación del Estado (Decreto No. 74-2001) such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables Works: is applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Honduras : Water Security in the Dry Corridor of Honduras PLAN General Information Country: Honduras 2023-08-18 Bank’s Approval Date of the Original Procurement Plan: 2024-09-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169901 GPN Date: 2021-11-23 Project Name: Water Security in the Dry Corridor of Honduras Loan / Credit No: IDA / 66800 Secretaria de Agricultura y Ganaderia Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-SAG-366755-GO-RFQ / A Component 3: Project mana Solicitud de cotiza Single Stage - One E dquisición y renovación de lic IDA / 66800 gement and capacity buildin Posterior Open - National 15,000.00 0.00 Finalizado 2023-08-20 2024-02-24 2023-10-15 2024-02-26 2023-11-14 2024-03-13 ciones nvelope encias de software para la U g GP HN-SAG-366438-GO-RFQ / A Component 3: Project mana Solicitud de cotiza Single Stage - One E dquisición de Equipo Informá IDA / 66800 gement and capacity buildin Posterior Open - National 30,000.00 0.00 Finalizado 2023-08-19 2023-10-12 2023-12-08 2023-11-26 2024-04-17 ciones nvelope tico para la UGP g HN-SAG-393444-GO-RFQ / A Component 3: Project mana dquisiciones de Equipo para Solicitud de cotiza Single Stage - One E IDA / 66800 gement and capacity buildin Posterior Open - National 13,000.00 0.00 En ejecución 2023-11-25 2024-01-20 2024-02-19 Reproducción de Documento ciones nvelope g s y Proyector Multimedia. HN-SAG-366395-GO-RFB / A Component 3: Project mana Solicitud de oferta Single Stage - One E IDA / 66800 Posterior Open - National 150,000.00 0.00 Cancelado 2023-08-15 2023-11-03 2023-08-20 2023-10-01 2023-10-31 2023-12-05 2024-06-02 dquisición de tres vehículos p gement and capacity buildin s nvelope ara la UGP g HN-SAG-366395-GO-RFB-2 / Component 3: Project mana Solicitud de oferta Single Stage - One E Adquisición de Tres (3) Vehíc IDA / 66800 gement and capacity buildin Posterior Open - National 150,000.00 0.00 Cancelado 2024-01-15 2024-01-20 2024-03-02 2024-04-01 2024-05-06 2024-11-02 s nvelope ulos Pick Up Doble cabina 4x g 4 HN-SAG-408297-GO-RFQ / A Component 3: Project mana Solicitud de cotiza Single Stage - One E dquisición de tres vehículos t IDA / 66800 gement and capacity buildin Posterior Open - National 150,000.00 0.00 En ejecución 2024-03-05 2024-04-12 2024-04-30 2024-10-27 ciones nvelope ipo pick up g HN-SAG-408303-GO-RFQ / A Component 3: Project mana Solicitud de cotiza Single Stage - One E IDA / 66800 Posterior Open - National 20,000.00 0.00 Cancelado 2024-03-05 2024-04-30 2024-10-27 dquisición de medidores de c gement and capacity buildin ciones nvelope audal g HN-SAG-366371-GO-RFQ / A Component 3: Project mana Solicitud de cotiza Single Stage - One E dquisición de Mobiliario de Of IDA / 66800 gement and capacity buildin Posterior Open - National 20,000.00 0.00 Cancelado 2023-08-20 2024-01-26 2023-10-10 2024-01-08 ciones nvelope icina para la UGP g HN-SAG-378901-GO-RFQ / A Component 3: Project mana dquisición de Material Promo Solicitud de cotiza Single Stage - One E IDA / 66800 gement and capacity buildin Posterior Open - National 25,000.00 0.00 En ejecución 2024-07-03 2024-08-28 2024-09-27 cional e Impresión de Materia ciones nvelope g l Institucional del Proyecto HN-SAG-366773-GO-RFQ / A Component 3: Project mana Solicitud de cotiza Single Stage - One E Ejecución pe dquisición de Equipo Audiovi IDA / 66800 gement and capacity buildin Posterior Open - National 25,000.00 0.00 2024-07-03 2024-08-28 2024-11-26 ciones nvelope ndiente sual y Comunicaciones para g el Proyecto. HN-SAG-432682-GO-RFB / A Component 3: Project mana Solicitud de oferta Single Stage - One E dquisición de Mobiliario de Of IDA / 66800 gement and capacity buildin Posterior Open - National 45,000.00 0.00 En ejecución 2024-07-08 2024-08-09 2024-07-13 2024-08-24 2024-09-23 2024-10-28 2025-04-26 s nvelope icina para la UGP g HN-SAG-432730-GO-RFB / A Component 3: Project mana Solicitud de oferta Single Stage - One E Ejecución pe DQUISICIÓN DE TRES VEHÍCU IDA / 66800 gement and capacity buildin Posterior Open - National 150,000.00 0.00 2024-09-02 2024-09-07 2024-10-19 2024-11-18 2024-12-23 2025-06-21 s nvelope ndiente LOS TIPO PICK UP. g HN-SAG-444926-GO-RFQ / C AUDALÍMETROS ULTRASÓNIC Component 3: Project mana Solicitud de cotiza Single Stage - One E OS PORTÁTIL PARA MEDIR EL IDA / 66800 gement and capacity buildin Posterior Open - National 25,500.00 0.00 En ejecución 2024-08-20 2024-10-15 2025-04-13 ciones nvelope CAUDAL DEL AGUA CRUDA Y g POTABLE (INCLUYE CAPACITA CIÓN EN CAMPO). NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-SAG-366419-NC-RFQ / S ervicios Logísticos y Alimenta Component 1: Strengthening ción para evento Experiencia institutional capacity for wat Solicitud de cotiza Single Stage - One E Ejecución pe de ADA en otros países, en a IDA / 66800 Posterior Open - National 15,000.00 0.00 2023-09-16 2023-11-11 2023-12-11 er resources governance an ciones nvelope ndiente poyo a la gobernanza del ag d management ua a nivel nacional (iii) estruc turación de la Autoridad del Agua. HN-SAG-408042-NC-RFQ / M Component 3: Project mana Solicitud de cotiza Single Stage - One E Ejecución pe IDA / 66800 Posterior Open - National 10,800.00 0.00 2024-07-05 2024-08-30 2025-02-26 otorista / Mensajero I gement and capacity buildin ciones nvelope ndiente g HN-SAG-426419-NC-RFQ / M Component 3: Project mana Solicitud de cotiza Single Stage - One E Ejecución pe IDA / 66800 Posterior Open - National 10,800.00 0.00 2024-07-03 2024-08-28 2025-02-24 otorista / Mensajero II gement and capacity buildin ciones nvelope ndiente g HN-SAG-432685-NC-RFQ / A Component 3: Project mana dquisición de Póliza de Segur Solicitud de cotiza Single Stage - One E Ejecución pe IDA / 66800 gement and capacity buildin Posterior Open - National 4,000.00 0.00 2024-07-13 2024-09-07 2025-09-07 o de Vehículos para flota veh ciones nvelope ndiente g icular propiedad de la UGP. Page 1 HN-SAG-448623-NC-RFQ / I Component 1: Strengthening mpresión del Plan de Optimiz institutional capacity for wat Solicitud de cotiza Single Stage - One E Ejecución pe ación para la Modernización IDA / 66800 Posterior Open - National 1,500.00 0.00 2024-10-05 2024-11-30 2025-01-29 er resources governance an ciones nvelope ndiente de los Servicios Hidrológicos d management y Climáticos para la Cuenca Nacaome. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-SAG-366761-CS-QCBS / Component 3: Project mana Selección basada Contratación de firma para a IDA / 66800 gement and capacity buildin Posterior Open - National 150,000.00 0.00 Cancelado 2022-12-01 2023-12-22 2022-12-22 2023-02-04 2023-03-04 2023-04-03 2023-05-08 2023-06-12 2025-12-31 en calidad y costo uditoría del proyecto. g HN-SAG-399933-CS-QCBS / Revisión y actualización de E studios de Evaluación de Imp Component 2: Scaling up res actos y Riesgos Ambientales ilient hydraulic infrastructur Selección basada Open - Internationa y Sociales y de Planes de Ges IDA / 66800 Posterior 700,000.00 0.00 Cancelado 2024-01-15 2024-02-09 2024-02-05 2024-02-15 2024-03-20 2024-04-17 2024-05-17 2024-06-21 2024-07-26 2025-01-22 e for water security in the Dr en calidad y costo l tión Ambiental y Social (PGA y Corridor S) y Planes Asociados de los Sistemas Integrales de Agua Segura (SIAS) Manazapa, La Venta, La Paz y Curarén. HN-SAG-399922-CS-QCBS / Contratación de Servicios de Component 2: Scaling up res Consultoría Actualización de ilient hydraulic infrastructur Selección basada Open - Internationa IDA / 66800 Posterior 400,000.00 0.00 Cancelado 2024-01-15 2024-01-09 2024-02-05 2024-03-20 2024-04-17 2024-05-17 2024-06-21 2024-07-26 2025-01-22 Diseños Existentes de los Sis e for water security in the Dr en calidad y costo l temas Integrales de Agua Se y Corridor gura (SIAS) en Manazapa, La Venta, La Paz y Curarén. HN-SAG-408287-CS-QCBS / Contratación de Servicios de Component 2: Scaling up res Consultoría Actualización de ilient hydraulic infrastructur Selección basada Open - Internationa IDA / 66800 Posterior 600,000.00 0.00 En ejecución 2024-08-01 2024-02-14 2024-08-22 2024-02-15 2024-10-05 2024-11-02 2024-12-02 2025-01-06 2025-02-10 2026-02-10 Diseños Existentes de los Sis e for water security in the Dr en calidad y costo l temas Integrales de Agua Se y Corridor gura (SIAS) en Manazapa, La Venta, La Paz y Curarén. HN-SAG-432696-CS-CQS / R EVISIÓN Y ACTUALIZACIÓN D E LOS ESTUDIOS DE EVALUA CIÓN DE IMPACTOS Y RIESGO Component 2: Scaling up res Selección basada S AMBIENTALES Y SOCIALES ( ilient hydraulic infrastructur Open - Internationa IDA / 66800 Previa en calificaciones d 1,000,000.00 0.00 En ejecución 2024-07-08 2024-07-31 2024-07-29 2024-08-13 2024-09-11 2024-10-11 2024-11-15 2025-09-26 EsEIRAS), INCLUYENDO PLAN e for water security in the Dr l e consultores ES DE GESTIÓN AMBIENTAL Y y Corridor SOCIAL (PGAS) Y PLANES AS OCIADOS DE LOS SUBPROYE CTOS DE SISTEMAS INTEGRA LES DE AGUA SEGURA (SIAS). INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-SAG-366376-CS-INDV / O Component 3: Project mana IDA / 66800 Previa Individual Open - National 67,500.00 0.00 Cancelado 2023-08-15 2023-09-14 2023-09-24 2023-10-14 2025-12-30 ficial en Adquisiciones gement and capacity buildin g HN-SAG-366208-CS-CDS / C Component 3: Project mana Selección directa IDA / 66800 Posterior Direct - National 34,550.00 0.00 Finalizado 2022-12-01 2022-12-12 2022-12-14 2023-05-17 2022-12-30 2023-01-03 2023-08-31 2024-06-30 oordinadora del Proyecto gement and capacity buildin de consultores g HN-SAG-366367-CS-CDS / Es Component 3: Project mana Selección directa IDA / 66800 Posterior Direct - National 24,064.00 0.00 Firmado 2022-12-01 2022-12-12 2022-12-14 2023-05-24 2022-12-30 2023-01-03 2023-08-31 pecialista en Gestión Financi gement and capacity buildin de consultores era. g HN-SAG-366365-CS-CDS / Es Component 3: Project mana Selección directa IDA / 66800 Posterior Direct - National 22,114.00 0.00 Finalizado 2022-12-01 2022-12-12 2022-12-14 2023-05-17 2022-12-30 2023-01-05 2023-08-31 2024-03-31 pecialista Social gement and capacity buildin de consultores g HN-SAG-366368-CS-CDS / As Component 3: Project mana Selección directa istente Técnico del Asesor En IDA / 66800 gement and capacity buildin Posterior Direct - National 16,898.00 0.00 Finalizado 2022-12-01 2022-12-12 2022-12-14 2022-12-19 2022-12-30 2023-01-03 2023-08-31 2024-02-29 de consultores lace Institucional g HN-SAG-366369-CS-CDS / Es Component 3: Project mana Selección directa IDA / 66800 Posterior Direct - National 23,064.00 0.00 Firmado 2022-12-01 2022-12-12 2022-12-14 2023-05-17 2022-12-30 2023-01-03 2023-08-31 pecialista en Comunicaciones gement and capacity buildin de consultores g HN-SAG-366366-CS-CDS / As Component 3: Project mana Selección directa esor, Oficial y Enlace Instituci IDA / 66800 gement and capacity buildin Posterior Direct - National 34,350.00 0.00 Finalizado 2022-12-01 2022-12-12 2022-12-14 2023-05-17 2022-12-30 2023-01-03 2023-08-31 2023-12-31 de consultores onal de Recursos Hídricos g HN-SAG-366370-CS-CDS / Es Component 3: Project mana Selección directa IDA / 66800 Posterior Direct - National 22,864.00 0.00 Firmado 2022-12-01 2022-12-12 2022-12-14 2023-05-17 2022-12-30 2023-01-03 2023-08-31 pecialista Ambiental gement and capacity buildin de consultores g HN-SAG-366206-CS-CDS / Es Component 3: Project mana Selección directa IDA / 66800 Posterior Direct - National 22,864.00 0.00 Finalizado 2022-12-01 2022-12-12 2022-12-14 2023-08-28 2022-12-30 2023-01-02 2023-08-31 2023-12-30 pecialista en Adquisiciones I gement and capacity buildin de consultores g HN-SAG-366210-CS-CDS / As Component 3: Project mana Selección directa IDA / 66800 Posterior Direct - National 4,200.00 0.00 Finalizado 2022-12-01 2022-12-12 2022-12-14 2023-05-24 2022-12-30 2023-01-02 2023-08-31 2023-03-15 istente Administrativo y Logí gement and capacity buildin de consultores stico g HN-SAG-366781-CS-INDV / E Component 3: Project mana IDA / 66800 Posterior Individual Open - National 7,932.00 0.00 Firmado 2021-12-01 2021-11-09 2022-01-19 2023-10-20 2022-02-09 2023-10-20 2023-10-02 2023-11-01 2023-12-31 specialista en Monitoreo y Ev gement and capacity buildin aluación g HN-SAG-366377-CS-CDS / C Component 2: Scaling up res onsultoría Individual de Espe ilient hydraulic infrastructur Selección directa cialista en Operación y Mant IDA / 66800 Posterior Direct - National 24,000.00 0.00 En ejecución 2023-09-11 2023-11-08 2023-09-21 2023-10-21 2024-04-18 e for water security in the Dr de consultores enimiento de la Represa José y Corridor Cecilio del Valle y Sistema de Agua Potable. HN-SAG-366386-CS-INDV / E Component 3: Project mana IDA / 66800 Posterior Individual Open - National 5,288.00 0.00 En ejecución 2023-08-15 2024-07-10 2023-09-23 2023-10-03 2023-11-03 2023-12-31 specialista Legal gement and capacity buildin g HN-SAG-366426-CS-INDV / E Component 3: Project mana IDA / 66800 Posterior Individual Open - National 5,288.00 0.00 Firmado 2023-08-14 2023-10-25 2023-09-22 2023-12-19 2023-10-07 2024-01-15 2023-10-31 2024-02-01 2023-12-31 specialista en Hidrometeorol gement and capacity buildin ógia g HN-SAG-366749-CS-INDV / A Component 3: Project mana IDA / 66800 Posterior Individual Open - National 3,600.00 0.00 Firmado 2023-08-14 2023-11-14 2023-09-22 2024-02-02 2023-10-07 2024-02-03 2023-11-04 2024-03-19 2023-12-31 sistente Administrativo y Log gement and capacity buildin ístico g Page 2 HN-SAG-367055-CS-INDV / E Component 3: Project mana IDA / 66800 Previa Individual Open - National 7,932.00 0.00 Firmado 2022-02-01 2023-10-13 2022-03-22 2024-01-15 2022-04-12 2024-03-04 2023-09-30 2024-02-14 2023-12-31 specialista en Adquisiciones I gement and capacity buildin I g HN-SAG-367057-CS-INDV / E Component 3: Project mana specialista en Agua Potable y IDA / 66800 gement and capacity buildin Posterior Individual Open - National 7,932.00 0.00 Firmado 2022-09-01 2022-01-07 2022-10-05 2023-11-01 2022-10-26 2023-11-28 2023-10-02 2024-01-03 2023-12-31 Saneamiento g HN-SAG-381656-CS-INDV / E Component 3: Project mana IDA / 66800 Previa Individual Direct - National 22,864.00 0.00 Cancelado 2022-12-02 2022-12-12 2022-12-17 2022-12-30 2023-08-31 specialista en Adquisiciones I gement and capacity buildin g HN-SAG-366387-CS-INDV / E Component 3: Project mana specialista en Gobernanza: A IDA / 66800 gement and capacity buildin Posterior Individual Open - National 2,644.00 0.00 Firmado 2023-11-20 2023-12-22 2023-12-15 2024-04-11 2023-12-25 2024-04-11 2024-01-14 2024-05-03 2024-03-13 sistencia Técnica y Consejo d g e Microcuencas HN-SAG-403547-CS-INDV / E Component 3: Project mana IDA / 66800 Previa Individual Open - National 39,060.00 0.00 En ejecución 2024-01-25 2024-03-04 2024-03-14 2024-08-22 2024-04-04 2024-08-29 2024-05-09 2024-11-05 specialista en Adquisiciones I gement and capacity buildin g HN-SAG-405918-CS-CDS / C ontratación de Servicios de A Component 3: Project mana Selección directa uditoría para el Proyecto de IDA / 66800 gement and capacity buildin Posterior Direct - National 90,000.00 0.00 Firmado 2024-02-15 2024-02-09 2024-02-25 2024-02-14 2024-04-30 2024-04-17 2024-10-27 de consultores Seguridad Hídrica en el Corre g dor Seco de Honduras HN-SAG-367052-CS-INDV / E Component 3: Project mana IDA / 66800 Posterior Individual Open - National 5,288.00 0.00 Cancelado 2022-09-01 2022-10-07 2022-10-20 2022-11-10 2023-09-30 2023-12-31 specialista en Presas gement and capacity buildin g HN-SAG-383479-CS-INDV / E Component 2: Scaling up res Open - Internationa xperto en Presas (Hormigón IDA / 66800 ilient hydraulic infrastructur Posterior Individual 100,000.00 0.00 Cancelado 2022-11-02 2022-11-07 2022-12-21 2023-10-02 2023-10-31 2024-10-31 l y Terraplén) y Sistemas de M e for water security in the Dr onitoreo y Corridor Component 2: Scaling up res HN-SAG-367056-CS-INDV / E Direct - Internation IDA / 66800 ilient hydraulic infrastructur Posterior Individual 100,000.00 0.00 Cancelado 2023-09-30 2023-10-24 2023-10-10 2023-10-20 2023-11-04 2024-11-03 xperto en Hidrología al e for water security in the Dr y Corridor Component 2: Scaling up res HN-SAG-383476-CS-INDV / E Direct - Internation IDA / 66800 ilient hydraulic infrastructur Posterior Individual 100,000.00 0.00 Cancelado 2023-09-28 2023-10-25 2023-10-08 2023-10-18 2023-11-02 2024-11-01 xperto en Hidromecanica al e for water security in the Dr y Corridor HN-SAG-366406-CS-INDV / M Component 3: Project mana IDA / 66800 Posterior Individual Open - National 1,800.00 0.00 Cancelado 2023-08-15 2023-09-15 2023-10-06 2023-10-31 2023-12-31 otorista / Mensajero I gement and capacity buildin g HN-SAG-408038-CS-INDV / E Component 3: Project mana Ejecución pendien specialista en Salud y Seguri IDA / 66800 gement and capacity buildin Posterior Individual Open - National 36,000.00 0.00 2024-06-30 2024-08-18 2024-09-08 2024-10-13 2025-04-11 te dad Ocupacional g HN-SAG-408039-CS-INDV / E Component 3: Project mana IDA / 66800 Posterior Individual Open - National 38,400.00 0.00 En ejecución 2024-05-31 2024-03-05 2024-07-19 2024-08-09 2024-09-13 2025-03-12 specialista en Reasentamient gement and capacity buildin o g HN-SAG-408041-CS-INDV / E Component 3: Project mana specialista en Género e Inclu IDA / 66800 gement and capacity buildin Posterior Individual Open - National 36,000.00 0.00 En ejecución 2024-06-30 2024-03-05 2024-08-18 2024-09-08 2024-10-13 2025-04-11 sión Social g HN-SAG-408033-CS-INDV / E Component 2: Scaling up res Open - Internationa specialista en Electromecáni IDA / 66800 ilient hydraulic infrastructur Posterior Individual 232,640.00 0.00 En ejecución 2024-06-01 2024-04-04 2024-07-20 2024-08-10 2024-09-14 2025-03-13 l ca Plantas de Tratamiento de e for water security in the Dr Agua Potable y Corridor HN-SAG-408028-CS-INDV / E Component 2: Scaling up res specialista en Operación y M ilient hydraulic infrastructur Open - Internationa IDA / 66800 Posterior Individual 232,640.00 0.00 En ejecución 2024-06-30 2024-04-04 2024-08-18 2024-09-08 2024-10-13 2025-04-11 antenimiento de Plantas de T e for water security in the Dr l ratamiento de Agua Potable y Corridor HN-SAG-421503-CS-INDV / E Component 3: Project mana IDA / 66800 Posterior Individual Open - National 126,893.00 0.00 En ejecución 2024-04-29 2024-05-02 2024-06-17 2024-08-05 2024-07-08 2024-08-07 2024-08-12 2027-12-31 specialista Social gement and capacity buildin g HN-SAG-407921-CS-INDV / E Component 3: Project mana Ejecución pendien IDA / 66800 Posterior Individual Open - National 19,326.00 0.00 2024-06-28 2024-08-16 2024-09-06 2024-10-11 2025-01-11 specialista II en Presas gement and capacity buildin te g HN-SAG-429004-CS-INDV / E Component 3: Project mana IDA / 66800 Previa Individual Open - National 133,455.00 0.00 En ejecución 2024-06-28 2024-08-05 2024-08-16 2024-09-06 2024-10-11 2027-12-11 SPECIALISTA EN ADQUISICIO gement and capacity buildin NES III g HN-SAG-432689-CS-INDV / E Component 3: Project mana specialista en Infraestructura IDA / 66800 gement and capacity buildin Posterior Individual Open - National 125,619.00 0.00 En ejecución 2024-07-08 2024-07-19 2024-08-26 2024-09-16 2024-10-21 2027-12-31 Hidráulica. g HN-SAG-435964-CS-INDV / E Component 1: Strengthening laboración de la Propuesta d institutional capacity for wat IDA / 66800 Posterior Individual Open - National 31,500.00 0.00 En ejecución 2024-08-01 2024-06-28 2024-09-19 2024-10-10 2024-11-14 2025-08-11 e Política Nacional de Gestió er resources governance an n Integral de los Recursos Hí d management dricos de Honduras. HN-SAG-438725-CS-INDV / C Component 3: Project mana IDA / 66800 Posterior Individual Open - National 184,353.00 0.00 En ejecución 2024-08-01 2024-07-23 2024-09-19 2024-10-10 2024-11-14 2027-12-31 OORDINADOR/A DEL PROYEC gement and capacity buildin TO g HN-SAG-438738-CS-INDV / F ortalecimiento de las Capaci Component 1: Strengthening dades Municipales en Gestió institutional capacity for wat n Integral de Recurso Hídrico IDA / 66800 Posterior Individual Open - National 32,300.00 0.00 En ejecución 2024-08-01 2024-07-10 2024-09-19 2024-10-10 2024-11-14 2025-05-13 er resources governance an (GIRH) y el Desarrollo de Tall d management eres de Capacitación en cuat ro municipios ubicados en el Corredor Seco de Honduras. HN-SAG-438748-CS-INDV / D Component 1: Strengthening iseño de Viveros Agroforestal institutional capacity for wat es Municipales y Comunitario IDA / 66800 Posterior Individual Open - National 27,700.00 0.00 En ejecución 2024-08-30 2024-07-10 2024-10-18 2024-11-08 2024-12-13 2025-04-12 er resources governance an s en Cuatro Municipios del Co d management rredor Seco de Honduras. HN-SAG-448622-CS-INDV / E Component 1: Strengthening specialista en Mantenimiento institutional capacity for wat Open - Internationa Ejecución pendien IDA / 66800 Posterior Individual 30,000.00 0.00 2024-09-30 2024-11-18 2024-12-09 2025-01-13 2025-03-14 de Radares Meteorológicos D er resources governance an l te oppler, Banda S. d management HN-SAG-448626-CS-INDV / E Component 3: Project mana Ejecución pendien IDA / 66800 Posterior Individual Open - National 100,472.00 0.00 2024-09-30 2024-11-18 2024-12-09 2025-01-13 2027-12-31 SPECIALISTA LEGAL gement and capacity buildin te g Page 3 HN-SAG-448627-CS-INDV / P ROPUESTA DE REGLAMENTO Component 1: Strengthening PARA EL USO, EXPLOTACIÓN institutional capacity for wat Ejecución pendien IDA / 66800 Posterior Individual Open - National 30,000.00 0.00 2024-09-30 2024-11-18 2024-12-09 2025-01-13 2025-10-10 Y APROVECHAMIENTO SOSTE er resources governance an te NIBLE DE LAS AGUAS DEL SU d management BSUELO Y SU NORMA TÉCNIC A. Page 4