PROCUREMENT PLAN TEXTUAL PART Project information Country : Turkey Project Name : Turkey Resilient Landscape Integration Project (TULIP) Project Number : P172562 Project Implementation Agency: Directorate General of Forestry (OGM), General Directorate of Agricultural Reform (TRGM), State Hydraulic Works (DSI), General Directorate of Highways (KGM) Date of the Procurement Plan: May 03, 2021 Period covered by this Procurement Plan: From July 2021 to December 2022 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Goods, Works and Non-consulting Services Procurement Procurement Method Prior Review Threshold Method Threshold RFB Default Method for Good, Works Contract valued > USD (International and Non-consulting Services (No 10M Works and > USD 2M Open selection method threshold) for Goods and Non- Competition) Consulting Services 1 RFB (National Contracts valued < USD 30M for Contracts valued > USD Open Works and < USD 2M for Goods 10M for Works and > USD Competition) and Non-Consulting Services 2M for Goods and Non- Consulting Services RFQ Works Contracts valued < No prior review USD200,000 – Goods and Non- consulting Services Contracts valued < USD100,000 Works III. Selection of Consultants Selection Method Selection Method Prior Review Threshold Threshold Quality and Cost Default Method (No Contract valued ≥ USD Based Selection selection method 1M (QCBS) threshold) Selection Based on Contracts valued < No prior review Consultants USD300,000 Qualification (CQS) Least Cost Selection No selection Method Contract valued ≥ USD (LCS) threshold 1M Direct Selection (DIR) No selection method Contract valued ≥ USD threshold 1M Justification is required at the PP approval Individual Consultants No selection method Contracts valued ≥ (INDV) threshold USD300,000 The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1.The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection, Turkish translation of the Bank’s Standard Procurement Documents (SPD) with minor modifications will be used as to fit for purpose or the procurement documents agreed by the Bank shall be used. 2.Review Procedure: The procurements under the project are subject to the Bank’s prior review as stipulated in above Paragraphs II and III and also as specified in the procurement schedule given below in Section V, and in STEP. 3.Procurement of Second Hand Goods: Not Applicable 2 4.Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable 5.Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable 6. Other Relevant Procurement Information - NA 7. Procurement Packages with Methods and Time Schedule The estimated costs given in the attached tables include VAT. 3 PROCUREMENT Turkiye : Turkey Resilient Landscape Integration Project (TULIP) PLAN General Information Country: Turkiye 2022-02-11 Bank’s Approval Date of the Original Procurement Plan: 2024-09-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172562 GPN Date: 2021-12-09 Project Name: Turkey Resilient Landscape Integration Project (TULIP) Loan / Credit No: IBRD / 92720 Cekerek Regional Support Team Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - TR-CEKEREK RST-299282-C Component 1: Investments i Single Stage - One E Small Works SPD 2022-12-3 W-RFB / Construction of Ceke IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 800,000.00 875,174.44 Completed 2022-06-27 2022-07-20 2022-06-28 2022-07-28 2022-08-22 2022-07-30 2022-08-22 2022-08-10 2022-10-02 nvelope (1 envelope proce 1 rek Recreation Area ation in targeted areas ss) TR-CEKEREK RST-307656-C Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2022-12-3 W-RFQ / Sivas Forest Nursery IBRD / 92720 n Resilient Landscape Integr Post Open - National 59,000.00 0.00 Canceled 2022-09-11 2022-09-30 tions nvelope or explanation) 1 Directorate Road Constructio ation in targeted areas n Work TR-CEKEREK RST-307971-C W-RFQ / Sivas Forest Manage Component 1: Investments i ment Directorate Animal Can Request for Quota Single Stage - One E Other (with field f 2022-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 7,000.00 0.00 Canceled 2022-09-11 2022-09-30 opy Construction Work tions nvelope or explanation) 1 ation in targeted areas (Sivas Province Yıldızeli Distr ict Subasi Village) TR-CEKEREK RST-311277-C W-RFQ / Kayseri Forest Regio nal Directorate Yozgat Forest Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2022-12-3 Management Directorate Con IBRD / 92720 n Resilient Landscape Integr Post Open - National 18,000.00 0.00 Canceled 2022-08-31 2022-09-27 tions nvelope or explanation) 1 struction of scratching post, ation in targeted areas plaster and salt shaker for an imals within the scope of pas ture improvement. TR-CEKEREK RST-307969-C W-RFQ / Service Road Constr uction, Planting Services, Lan d Preparation Works (Sivas, Y Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2022-12-3 ıldızeli District Sarıcal Village IBRD / 92720 n Resilient Landscape Integr Post Open - National 22,500.00 0.00 Canceled 2022-09-11 2022-09-30 tions nvelope or explanation) 1 Eğrek Locality) ation in targeted areas (Although it has similar busin ess status with 307963-CW-R FQ, its field location and loca tions are very different regio ns.) TR-CEKEREK RST-307963-C W-RFQ / Service Road Constr uction, Planting Services, Lan d Preparation Works,(Sivas, Y Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2022-12-3 ıldızeli District Üyükyaylası Vi IBRD / 92720 n Resilient Landscape Integr Post Open - National 101,000.00 0.00 Canceled 2022-09-11 2022-09-30 tions nvelope or explanation) 1 llage Karababa Locality) ation in targeted areas (Although it has similar busin ess status to 307969-CW-RF Q, its field location and locati ons are very different region s.) TR-CEKEREK RST-315304-C W-RFQ / Sapling Planting Ser Component 1: Investments i vices, Land Preparation servi Request for Quota Single Stage - One E Other (with field f 2022-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 80,000.00 0.00 Canceled 2022-09-21 2022-11-01 ce procurement business (Siv tions nvelope or explanation) 1 ation in targeted areas as Yıldızeli District Üyükyayla sı Village Karababa Locality) TR-CEKEREK RST-315305-C W-RFQ / Sapling Planting Ser Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2022-12-3 vices, Land Preparation servi IBRD / 92720 n Resilient Landscape Integr Post Open - National 22,500.00 0.00 Canceled 2022-09-21 2022-11-01 tions nvelope or explanation) 1 ce procurement business (Siv ation in targeted areas as Yıldızeli District Sarıcal Vill age Eğrek Locality) TR-CEKEREK RST-351012-C Component 1: Investments i W-RFQ / Recreation Construc Request for Quota Single Stage - One E Other (with field f 2023-09-2 IBRD / 92720 n Resilient Landscape Integr Post Open - National 72,000.00 0.00 Canceled 2023-03-31 2023-05-26 tion Area (Wooden railing, Pa tions nvelope or explanation) 3 ation in targeted areas nel fence, Manhole and Sign Construction work.) TR-CEKEREK RST-354418-C W-RFQ / Amasya OBM Corum Forest Management Director Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2023-08-2 ate. Construction works withi IBRD / 92720 n Resilient Landscape Integr Post Open - National 116,000.00 0.00 Canceled 2023-04-15 2023-05-26 tions nvelope or explanation) 4 n the scope of afforestation a ation in targeted areas nd soil conservation works.(S oil tillage, sapling planting, b arbed wire construction work s.) TR-CEKEREK RST-362170-C Request for Bids - W-RFB / Recreation Construct Component 1: Investments i Single Stage - One E Small Works SPD 2023-12-3 ion Area. (Country Coffee, W IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 304,000.00 0.00 Completed 2023-05-26 2023-06-09 2023-05-31 2023-07-12 2023-07-25 2023-07-17 2023-07-26 2023-08-01 2023-08-09 nvelope (1 envelope proce 1 ooden Railing, Panel Fence, ation in targeted areas ss) Manhole Construction work.) TR-CEKEREK RST-362381-C W-RFQ / Kayseri OBM Sivas F orest Management Directorat e. Construction works within Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2023-12-3 the scope of afforestation an IBRD / 92720 n Resilient Landscape Integr Post Open - National 152,000.00 0.00 Completed 2023-06-25 2023-07-14 2023-08-09 tions nvelope or explanation) 1 d soil conservation works. (S ation in targeted areas oil tillage, sapling planting, b arbed wire construction work s.) (Sivas Province Yildizeli Di strict Üyükyaylasi Village.) TR-CEKEREK RST-362383-C W-RFQ / Kayseri OBM Sivas F orest Management Directorat Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2023-12-3 e (Construction works within IBRD / 92720 n Resilient Landscape Integr Post Open - National 90,000.00 0.00 Completed 2023-06-25 2023-07-14 2023-08-09 tions nvelope or explanation) 1 the scope of afforestation an ation in targeted areas d rehabilitation works.) (Sivas Province Yildizeli Distri ct Sarıcal village location.) TR-CEKEREK RST-307971-C Component 1: Investments i W-RFQ-2 / Kayseri OBM Sivas Request for Quota Single Stage - One E Other (with field f 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 11,000.00 0.00 Canceled 2023-06-25 2023-07-14 Forest Management Director tions nvelope or explanation) 1 ation in targeted areas ate, Animal Canopy Construc tion Work. Page 1 TR-CEKEREK RST-362505-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 10,000.00 0.00 Canceled 2023-06-25 2023-07-14 ate. (Construction works with tions nvelope or explanation) 1 ation in targeted areas in the scope of afforestation and pasture improvement wo rks.) TR-CEKEREK RST-362508-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 30,000.00 0.00 Completed 2023-06-25 2023-07-14 2023-08-03 ate. (Construction works with tions nvelope or explanation) 1 ation in targeted areas in the scope of afforestation) (Tokat Province Artova Distri ct Bebekderesi Village Locati on.) TR-CEKEREK RST-362514-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 51,000.00 0.00 Completed 2023-06-25 2023-07-14 2023-08-03 ate. (Construction works with tions nvelope or explanation) 1 ation in targeted areas in the scope of afforestation) (Tokat Province Yesilyurt Dist rict Sivri Village Location.) TR-CEKEREK RST-362515-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 55,000.00 0.00 Completed 2023-06-25 2023-07-14 2023-08-05 ate.(Construction works withi tions nvelope or explanation) 1 ation in targeted areas n the scope of afforestation) (Tokat Province, Yesilyurt Dis trict, Ekinli Village Location.) TR-CEKEREK RST-362517-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 62,000.00 0.00 Completed 2023-06-25 2023-07-14 2023-08-09 ate.(Construction works withi tions nvelope or explanation) 1 ation in targeted areas n the scope of afforestation) (Tokat Province, Artova Distri ct, Devecikargın Village Loca tion.) TR-CEKEREK RST-376109-C Component 1: Investments i W-RFQ / Kayseri OBM Sivas F Request for Quota Single Stage - One E Other (with field f 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Limited 27,000.00 0.00 Completed 2023-08-19 2023-08-31 2023-09-29 2023-09-21 orest Management Directorat tions nvelope or explanation) 1 ation in targeted areas e, Animal Canopy Constructio n Work. TR-CEKEREK RST-376587-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 12,000.00 0.00 Completed 2023-08-22 2023-10-02 2023-10-05 ate. (Construction works with tions nvelope or explanation) 1 ation in targeted areas in the scope of afforestation and pasture improvement wo rks.) TR-CEKEREK RST-376591-C W-RFQ / Amasya OBM Corum Forest Management Director Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2023-12-3 ate. Construction works withi IBRD / 92720 n Resilient Landscape Integr Post Open - National 86,000.00 0.00 Completed 2023-08-22 2023-10-02 2023-09-27 tions nvelope or explanation) 1 n the scope of afforestation a ation in targeted areas nd soil conservation works.(S oil tillage, sapling planting, b arbed wire construction work s.) TR-CEKEREK RST-377771-C W-RFB / Kayseri OBM Akdağ Request for Bids - Component 1: Investments i madeni Directorate of Forestr Single Stage - One E Small Works SPD 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 217,000.00 0.00 Canceled 2023-08-28 2023-09-01 2023-09-02 2023-10-14 2023-10-02 2023-10-15 2023-10-19 y, 9 Village Furnaces constru nvelope (1 envelope proce 1 ation in targeted areas ction work. ss) (Component: 1, Subcompone nt: 1.1, Thematic Title: 1.1.4. ) TR-CEKEREK RST-377783-C W-RFQ / TRGM Çorum Provin cial Directorate of Agriculture and Forestry, Pasture/Highla Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2023-12-3 nd Improvement and Manage IBRD / 92720 n Resilient Landscape Integr Post Open - National 38,000.00 0.00 Canceled 2023-09-02 2023-10-03 tions nvelope or explanation) 1 ment. (Purchase of Canopy a ation in targeted areas nd Itch Piles-10 pcs) 5 canop y, 5 itch stakes. (Thematic Title: 1.1.2.3. Ran geland rehabilitation and ma nagement.) TR-CEKEREK RST-414325-C W-RFQ / TRGM Çorum Provin cial Directorate of Agriculture Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2024-06-2 and Forestry, Pasture/Highla IBRD / 92720 n Resilient Landscape Integr Post Open - National 88,000.00 0.00 Signed 2024-03-18 2024-05-13 2024-05-29 tions nvelope or explanation) 7 nd Improvement and Manage ation in targeted areas ment. (Purchase of Canopy a nd Itch Piles-10 pcs) 5 canop y, 5 itch stakes. TR-CEKEREK RST-414526-C W-RFB / Kayseri Regional Dir ectorate of Forestry, Yozgat, Request for Bids - Cekerek Candır village affore Component 1: Investments i Single Stage - One E Small Works SPD 2024-10-3 station and erosion control pr IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 374,000.00 0.00 Signed 2024-03-18 2024-03-27 2024-03-23 2024-04-22 2024-05-03 2024-05-06 2024-05-28 2024-06-17 2024-05-22 nvelope (1 envelope proce 0 oject in scope, dry wall thres ation in targeted areas ss) hold, wire threshold, sack set construction, land preparatio n, sapling procurement and p lanting afforestation works. TR-CEKEREK RST-417316-C W-RFQ / Kayseri Regional Dir ectorate of Forestry, Sivas Fo Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2024-12-2 rest Management Directorate IBRD / 92720 n Resilient Landscape Integr Post Open - National 61,500.00 0.00 Signed 2024-04-10 2024-06-05 2024-05-22 tions nvelope or explanation) 2 (Construction works within th ation in targeted areas e scope of rehabilitation work s.) (Sivas Province Yildizeli Di strict Yaglıdere village locatio n.) TR-CEKEREK RST-417313-C W-RFQ / Kayseri Regional Dir ectorate of Forestry, Sivas Fo Component 1: Investments i rest Management Directorate Request for Quota Single Stage - One E Other (with field f 2024-12-2 IBRD / 92720 n Resilient Landscape Integr Post Open - National 123,700.00 0.00 Signed 2024-04-10 2024-06-05 2024-05-17 (Construction works within th tions nvelope or explanation) 2 ation in targeted areas e scope of afforestation and soil protection.) (Sivas Provin ce Yildizeli District Ortaklar vi llage location.) TR-CEKEREK RST-417304-C W-RFQ / Kayseri Regional Dir ectorate of Forestry, Sivas Fo Component 1: Investments i rest Management Directorate Request for Quota Single Stage - One E Other (with field f 2024-08-0 IBRD / 92720 n Resilient Landscape Integr Post Open - National 30,900.00 0.00 Canceled 2024-04-10 2024-06-05 , Animal Canopy Constructio tions nvelope or explanation) 4 ation in targeted areas n Work, Land Preparation Ser vices, Afforestation Services. (Sivas Province Yildizeli Distri ct Kavaksandal and Kaman vi llages location.) Page 2 TR-CEKEREK RST-427459-C W-RFQ / Kayseri Regional Dir ectorate of Forestry, Sivas Fo Component 1: Investments i rest Management Directorate Request for Quota Single Stage - One E Other (with field f 2024-09-1 IBRD / 92720 n Resilient Landscape Integr Post Open - National 31,500.00 0.00 Signed 2024-05-25 2024-07-20 2024-07-08 , Animal Canopy Constructio tions nvelope or explanation) 8 ation in targeted areas n Work, Land Preparation Ser vices, Afforestation Services. (Sivas Province Yildizeli Distri ct Kavaksandal and Kaman vi llages location.) TR-CEKEREK RST-432308-C W-RFQ / Amasya Regional Dİr ectorate of Forestry, Çorum F Component 1: Investments i orest Management, Kolanlı K Request for Quota Single Stage - One E Other (with field f 2024-12-1 IBRD / 92720 n Resilient Landscape Integr Post Open - National 403,000.00 0.00 Signed 2024-06-19 2024-08-14 2024-08-02 arnıkaya village erosion contr tions nvelope or explanation) 2 ation in targeted areas ol, vineyard erosion control p roject and Salbaş Truffle Graf ted oak afforestation applicat ion project works with partial bid in 3 lots. TR-CEKEREK RST-434136-C W-RFQ / Amasya Regional Dir ectorate of ForestryTokat For est ManagementÇimeköy De Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2024-12-2 vecikargın village Afforestati IBRD / 92720 n Resilient Landscape Integr Post Open - National 212,000.00 0.00 Signed 2024-06-29 2024-08-24 tions nvelope or explanation) 2 on projectsAlpudere Sulusara ation in targeted areas y districts erosion control pro ject, Artova district boyunpın ar village pasture improveme nt works with partial bid in 3 lots. TR-CEKEREK RST-440576-C W-RFQ / Kayseri Regional Dir ectorate of Forestry, Çayırala Component 1: Investments i n Forest Management Direct Request for Quota Single Stage - One E Other (with field f 2024-12-2 IBRD / 92720 n Resilient Landscape Integr Post Open - National 92,000.00 0.00 Canceled 2024-08-03 2024-09-28 orate, within the scope of Çe tions nvelope or explanation) 7 ation in targeted areas kerek River Basin Rehabilitati on Project, construction of th e structures and equipment o f the Cennet Creek Ecotouris m area. TR-CEKEREK RST-440599-C W-RFQ / General Directorate of Agricultural Reform, Tokat Component 1: Investments i Provincial Directorate of Agri Request for Quota Single Stage - One E Other (with field f Under Imple 2024-12-2 IBRD / 92720 n Resilient Landscape Integr Post Open - National 50,000.00 0.00 2024-08-14 2024-10-09 culture and Forestry, will carr tions nvelope or explanation) mentation 8 ation in targeted areas y out the construction of sha de nets, plasters, scratching posts, salt shakers and signs within the scope of Pasture R eclamation. TR-CEKEREK RST-446412-C W-RFQ / Kayseri Regional Dir ectorate of Forestry, Çayırala Component 1: Investments i n Forest Management Direct Request for Quota Single Stage - One E Other (with field f Under Imple 2024-12-2 IBRD / 92720 n Resilient Landscape Integr Post Open - National 91,000.00 0.00 2024-09-01 2024-10-27 orate, within the scope of Çe tions nvelope or explanation) mentation 6 ation in targeted areas kerek River Basin Rehabilitati on Project, construction of th e structures and equipment o f the Cennet Creek Ecotouris m area. TR-CEKEREK RST-447842-C W-RFB / Amasya Forest Regio Request for Bids - nal Directorate Tokat Forest Component 1: Investments i Single Stage - One E Small Works SPD Pending Imp 2025-02-1 Management Directorate 1 pi IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 590,000.00 0.00 2024-08-30 2024-09-04 2024-10-16 2024-11-15 2024-12-20 nvelope (1 envelope proce lementation 8 eces within the scope of Çek ation in targeted areas ss) erek River Basin Rehabilitatio n Project, Sulusaray Forest P ark Project Construction work . GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-CEKEREK RST-307995-G Component 1: Investments i O-RFB / Yozgat Province TRG Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 545,000.00 0.00 Canceled 2022-08-10 2022-08-15 2022-09-14 2022-09-16 2022-09-29 2022-12-31 M forage plant hungarian vet nvelope ation in targeted areas ch seed procurement busines s TR-CEKEREK RST-314752-G Component 1: Investments i O-RFQ / Tokat Provincial Dire Request for Quota Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Open - National 98,500.00 0.00 Completed 2022-09-17 2022-11-12 2022-11-16 2022-12-31 2022-12-30 ctorate of Agriculture and For tions nvelope ation in targeted areas estry Wheat Seed Goods Pur chase Business TR-CEKEREK RST-314757-G O-RFQ / Tokat Provincial Dire Component 1: Investments i Request for Quota Single Stage - One E ctorate of Agriculture and For IBRD / 92720 n Resilient Landscape Integr Post Open - National 72,000.00 0.00 Completed 2022-09-17 2022-11-12 2022-12-09 2022-12-31 2022-12-30 tions nvelope estry Alfalfa Seed and Hunga ation in targeted areas rian Vetch Seed Procurement Business TR-CEKEREK RST-316294-G Component 1: Investments i O-RFB / Dairy Cattle Purchas Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 375,000.00 0.00 Canceled 2022-09-22 2022-10-24 2022-09-27 2022-10-27 2022-11-22 2022-11-06 2022-11-26 2022-12-31 e Business Within the Scope nvelope ation in targeted areas of Development of Livestock Activities TR-CEKEREK RST-319171-G Component 1: Investments i O-RFQ / Çorum Provincial Dir Request for Quota Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Limited 30,000.00 0.00 Completed 2022-10-14 2022-10-13 2022-11-20 2022-11-30 2022-12-31 2022-12-21 ectorate of Agriculture and F tions nvelope ation in targeted areas orestry Hungarian Vetch See d Procurement Business TR-CEKEREK RST-319174-G Component 1: Investments i O-RFQ / Sivas Provincial Dire Request for Quota Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Limited 87,500.00 0.00 Completed 2022-10-14 2022-11-19 2022-11-20 2022-12-09 2022-12-31 2022-12-30 ctorate Of Agriculture and Fo tions nvelope ation in targeted areas restry Barley Seed Procurem etn Business TR-CEKEREK RST-377125-G O-RFQ / Amasya OBM Çorum Forestry Operations Director Component 2: Institutional F Request for Quota Single Stage - One E ate Purchase of 3 Laptops an IBRD / 92720 ramework, Project Managem Post Open - National 4,500.00 0.00 Completed 2023-09-02 2023-10-13 2023-11-22 2023-12-31 2023-12-07 tions nvelope d 1 Desktop Computer. ent, and Sustainability (Component:2, Subcompone nt: 2.2, Thematic Title: Projec t Management and Sustainab ility) TR-CEKEREK RST-377777-G O-RFQ / TRGM Çorum Provinc ial Directorate of Agriculture Component 1: Investments i and Forestry Pasture / Platea Request for Quota Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Open - National 12,000.00 0.00 Canceled 2023-09-02 2023-10-03 2023-12-31 u Rehabilitation and Manage tions nvelope ation in targeted areas ment (Purchase of 25 animal drinking water basins.) (Thematic Title: 1.1.2.3. Ran geland rehabilitation and ma nagement.) Page 3 TR-CEKEREK RST-377124-G O-RFQ / Kayseri OBM Sivas F orestry Management Director Component 1: Investments i Request for Quota Single Stage - One E ate, 12 Dairy Cattle Purchase IBRD / 92720 n Resilient Landscape Integr Post Open - National 49,000.00 0.00 Canceled 2023-09-02 2023-10-03 2023-12-22 tions nvelope Business within the Scope of ation in targeted areas Livestock Development Activi ties. (Component: 1, Subcom ponent: 1.1, Thematic Title: 1 .1.4.) TR-CEKEREK RST-380842-G O-RFQ / TRGM Tokat Provinci al Directorate of Agriculture and Forestry, Purchasing and Component 1: Investments i Request for Quota Single Stage - One E distribution of 80 milking ma IBRD / 92720 n Resilient Landscape Integr Post Open - National 37,300.00 0.00 Completed 2023-09-18 2023-10-29 2023-10-23 2023-12-31 2023-10-26 tions nvelope chines to 80 enterprises in Ar ation in targeted areas tova, Sulusaray and Yeşilyurt districts within the scope of i mproving barn conditions. (Thematic Title: 1.1.2.2.) TR-CEKEREK RST-382392-G O-RFQ / Tokat Provincial Dire ctorate of Agriculture and For estry, Within the scope of Inc Component 1: Investments i Request for Quota Single Stage - One E reasing Efficiency and Qualit IBRD / 92720 n Resilient Landscape Integr Post Open - National 18,150.00 0.00 Completed 2023-09-27 2023-10-28 2023-11-07 2023-12-31 2023-11-23 tions nvelope y in Chickpea Agriculture, 10, ation in targeted areas 000 kg of chickpea seeds pur chase.Thematic Title:1.1.2.2.I ncome generation and divers ification of livelihoods areas TR-CEKEREK RST-382389-G O-RFQ / Tokat Provincial Dire ctorate of Agriculture and For estry Purchase of 100.000 kg Component 1: Investments i Request for Quota Single Stage - One E barley seeds within the scop IBRD / 92720 n Resilient Landscape Integr Post Open - National 55,500.00 0.00 Completed 2023-10-05 2023-11-05 2023-11-13 2023-12-31 2023-11-22 tions nvelope e of Increasing Efficiency and ation in targeted areas Quality in Barley Agriculture. Thematic Title:1.1.2.2 Incom e generation and transition d iversification for ruralareas TR-CEKEREK RST-382385-G O-RFQ / Corum Provincial Dir ectorate of Agriculture and F orestry, Purchase of 34,250 k Component 1: Investments i Request for Quota Single Stage - One E g barley seeds within the sco IBRD / 92720 n Resilient Landscape Integr Post Open - National 18,500.00 0.00 Completed 2023-10-05 2023-11-05 2023-11-13 2023-12-31 2023-11-22 tions nvelope pe of Increasing Area, Produc ation in targeted areas tivity and Quality in Forage C rops Cultivation. Thematic Title: 1.1.2.1 Sustai nable and climate-friendly ag ricultural. TR-CEKEREK RST-385798-G O-RFQ / Tokat Provincial Dire ctorate of Agriculture and For Component 1: Investments i estry purchased 60,000 kg of Request for Quota Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Open - National 36,200.00 0.00 Completed 2023-10-17 2023-11-17 2023-11-24 2023-12-31 2023-11-30 composed fertilizer within th tions nvelope ation in targeted areas e scope of pasture improvem ent works. (Thematic Tittle: 1 .1.2.3. Pasture Rehabilitation and Management) TR-CEKEREK RST-387318-G O-RFQ / Sivas Provincial Dire ctorate of Agriculture and For estry Purchase of 87.000 kg Component 1: Investments i Request for Quota Single Stage - One E barley seeds within the scop IBRD / 92720 n Resilient Landscape Integr Post Limited 45,500.00 0.00 Completed 2023-10-25 2023-11-07 2023-11-30 2023-11-14 2023-12-30 2023-11-30 tions nvelope e of Increasing Efficiency and ation in targeted areas Quality in Barley Agriculture. (Thematic Title: 1.1.2.2 Susta inable and climate-friendly a gricultural practices) TR-CEKEREK RST-414334-G O-RFQ / TRGM Çorum Provinc Component 1: Investments i ial Directorate of Agriculture Request for Quota Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Open - National 50,200.00 0.00 Signed 2024-03-18 2024-05-13 2024-05-27 2024-08-11 and Forestry Pasture / Platea tions nvelope ation in targeted areas u Rehabilitation and Manage ment (Purchase of 25 animal drinking water basins.) TR-CEKEREK RST-417389-G O-RFQ / General Directorate Component 1: Investments i Request for Quota Single Stage - One E of Agricultural Reform, Tokat IBRD / 92720 n Resilient Landscape Integr Post Open - National 26,000.00 0.00 Canceled 2024-03-31 2024-05-26 2024-10-23 tions nvelope Provincial Directorate of Agri ation in targeted areas culture and Forestry, Purchas e of 50 breeding sheep. TR-CEKEREK RST-417328-G O-RFQ / General Directorate Component 1: Investments i Request for Quota Single Stage - One E of Agricultural Reform, Sivas IBRD / 92720 n Resilient Landscape Integr Post Open - National 40,000.00 0.00 Canceled 2024-04-10 2024-06-05 2024-08-04 tions nvelope Provincial Directorate of Agri ation in targeted areas culture and Forestry, chickpe a seed purchase. TR-CEKEREK RST-423386-G O-RFB / Cekerek River Basin Rehabilitation Project in the s Component 1: Investments i Single Stage - One E cope, General Directorate of IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 448,000.00 0.00 Canceled 2024-04-28 2024-05-27 2024-05-03 2024-06-02 2024-07-01 2024-06-16 2024-07-28 2024-10-26 nvelope Agricultural Reform, Tokat Pr ation in targeted areas ovincial Directorate of Agricu lture and Forestry, Purchase of 50 breeding sheep. TR-CEKEREK RST-433384-G O-RFQ / General Directorate Component 1: Investments i Request for Quota Single Stage - One E of Agricultural Reform, Yozga IBRD / 92720 n Resilient Landscape Integr Post Open - National 45,000.00 0.00 Signed 2024-06-29 2024-08-24 2024-07-31 2024-10-23 tions nvelope t Provincial Directorate of Agr ation in targeted areas iculture and Forestry, Hungar ian Vetch seed purchase. TR-CEKEREK RST-437669-G O-RFB / General Directorate of Agricultural Reform, Sivas Component 1: Investments i Single Stage - One E Under Imple Provincial Directorate of Agri IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 140,000.00 0.00 2024-07-12 2024-07-26 2024-07-17 2024-08-28 2024-09-27 2024-11-01 2024-12-31 nvelope mentation culture and Forestry, purchas ation in targeted areas e of 300 sheep and 12 rams within the scope of Çekerek River Basin Rehabilitation Pro ject. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 TR-CEKEREK RST-332049-NC -RFB / Survey Service Procur Component 2: Institutional F Single Stage - One E ement to be Carried out in 96 IBRD / 92720 ramework, Project Managem Post Request for Bids Open - National 145,000.00 0.00 Completed 2022-12-25 2023-02-11 2022-12-30 2023-02-10 2023-03-27 2023-02-20 2023-05-02 2023-03-12 2023-06-15 2023-08-09 2023-12-15 nvelope Villages and 1440 Household ent, and Sustainability s for the Current Situation Su rvey TR-CEKEREK RST-420678-NC -RFQ / Kayseri Regional Direc torate of Forestry, Sivas Fore Component 1: Investments i Request for Quota Single Stage - One E st Management Directorate ( IBRD / 92720 n Resilient Landscape Integr Post Open - National 66,000.00 0.00 Signed 2024-04-20 2024-06-15 2024-06-05 2024-09-13 tions nvelope Within the scope of soil cons ation in targeted areas ervation Planting services, m aintenance services, weeding , hoeing, etc. and afforestatio n services. TR-CEKEREK RST-420683-NC -RFQ / Kayseri Regional Direc torate of Forestry, Sivas Fore Component 1: Investments i Request for Quota Single Stage - One E st Management Directorate ( IBRD / 92720 n Resilient Landscape Integr Post Open - National 29,000.00 0.00 Signed 2024-04-20 2024-06-15 2024-06-05 2024-09-13 tions nvelope Within the scope of rehabilita ation in targeted areas tion Planting services, mainte nance services, weeding, hoe ing, etc. and afforestation ser vices. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-CEKEREK RST-354155-CS -CQS / Cekerek river basin fir Component 2: Institutional F Consultant Qualifi st group micro-catchments n IBRD / 92720 ramework, Project Managem Post Open - National 230,000.00 0.00 Signed 2023-04-05 2023-05-31 2023-04-26 2023-06-09 2023-07-05 2023-07-09 2023-08-08 2023-07-29 2023-08-09 2023-12-31 cation Selection umber six and seven. Consul ent, and Sustainability tancy Service Procurement fo r Micro-Catchment Plans TR-CEKEREK RST-354225-CS -CQS / Cekerek river basin se Component 2: Institutional F Consultant Qualifi cond group micro-catchment IBRD / 92720 ramework, Project Managem Post Open - National 197,000.00 0.00 Signed 2023-04-05 2023-05-31 2023-04-26 2023-06-09 2023-08-08 2023-07-09 2023-08-24 2023-07-29 2023-08-25 2023-12-31 cation Selection s number four and five. Cons ent, and Sustainability ultancy Service Procurement for Micro-Catchment Plans TR-CEKEREK RST-354227-CS -CQS / Cekerek river basin thi Component 2: Institutional F rd group micro-catchments n Consultant Qualifi IBRD / 92720 ramework, Project Managem Post Open - National 183,000.00 0.00 Signed 2023-04-05 2023-05-31 2023-04-26 2023-06-09 2023-09-15 2023-07-09 2023-09-15 2023-07-29 2023-09-15 2023-12-31 umber three and fourteen. C cation Selection ent, and Sustainability onsultancy Service Procurem ent for Micro-Catchment Plan s. TR-CEKEREK RST-354231-CS -CQS / Cekerek river basin fif Component 2: Institutional F Consultant Qualifi th group micro-catchments n IBRD / 92720 ramework, Project Managem Post Open - National 167,000.00 0.00 Signed 2023-04-05 2023-05-31 2023-04-26 2023-06-09 2023-10-03 2023-07-09 2023-10-03 2023-07-29 2023-10-04 2023-12-31 cation Selection umber eight and nine. Consul ent, and Sustainability tancy Service Procurement fo r Micro-Catchment Plans. TR-CEKEREK RST-396393-CS -CQS / İntegrated basin plan consultancy service procure ment. Integrated basin plan Component 2: Institutional F Consultant Qualifi preparation work for micro b IBRD / 92720 ramework, Project Managem Post Open - National 291,000.00 0.00 Signed 2023-12-11 2023-12-11 2024-01-01 2024-02-14 2024-01-19 2024-02-24 2024-02-19 2024-03-15 2024-02-19 2024-11-10 cation Selection asin plan studies carried out ent, and Sustainability over 876,000 ha. (Componen t: 2) - (Main Component: 2.1) (Application for integrated la ndscape management.) TR-CEKEREK RST-397468-CS -CQS / Cekerek river basin fo urth group Micro catchments. Component 2: Institutional F Consultancy Service Procure Consultant Qualifi IBRD / 92720 ramework, Project Managem Post Open - National 976,000.00 0.00 Canceled 2023-12-18 2023-12-21 2024-01-08 2024-02-21 2024-03-02 2024-03-22 2024-09-18 ment for Micro catchment Pla cation Selection ent, and Sustainability ns (Component: 2) - (Main Co mponent: 2.1) (Application fr amework for integrated lands cape management.) TR-CEKEREK RST-408567-CS -CQS / Cekerek river basin fo urth group Micro catchments Component 2: Institutional F number one and two. Consult Consultant Qualifi IBRD / 92720 ramework, Project Managem Post Open - National 245,000.00 0.00 Signed 2024-02-12 2024-02-13 2024-03-04 2024-04-17 2024-04-30 2024-04-27 2024-05-03 2024-05-17 2024-04-30 2024-11-13 ancy Service Procurement for cation Selection ent, and Sustainability Micro catchment Plans (Com ponent: 2) - (Main Componen t: 2.1) (Application for integr ated landscape management .) TR-CEKEREK RST-408585-CS -CQS / Çekerek river basin is the sixth group, micro basins Component 2: Institutional F numbered ten, eleven and tw Consultant Qualifi IBRD / 92720 ramework, Project Managem Post Open - National 300,000.00 0.00 Signed 2024-02-12 2024-02-13 2024-03-04 2024-04-17 2024-04-10 2024-04-27 2024-05-03 2024-05-17 2024-04-30 2024-11-13 elve. Micro Catchment Plans cation Selection ent, and Sustainability Consultancy Service Procure ment (Component: 2) - (Main Component: 2.1) (Integrated landscape management appli cation.) TR-CEKEREK RST-408599-CS -CQS / Çekerek river basin is the seventh group, micro bas ins numbered thirteen, fiftee Component 2: Institutional F Consultant Qualifi n and sixteen. Micro Catchm IBRD / 92720 ramework, Project Managem Post Open - National 298,000.00 0.00 Signed 2024-02-12 2024-02-13 2024-03-04 2024-04-17 2024-04-15 2024-04-27 2024-05-02 2024-05-17 2024-04-18 2024-11-13 cation Selection ent Plans Consultancy Servic ent, and Sustainability e Procurement (Component: 2) - (Main Component: 2.1) (I ntegrated landscape manage ment application.) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-CEKEREK RST-278210-CS Component 2: Institutional F Individual Consult -INDV / Hiring Procurement E IBRD / 92720 ramework, Project Managem Post Open 18,000.00 11,956.90 Signed 2022-02-09 2022-03-07 2022-03-04 2022-04-26 2022-03-04 2022-04-27 2022-03-08 2022-05-29 2023-03-08 ant Selection xperts for RSTs ent, and Sustainability TR-CEKEREK RST-278220-CS Component 2: Institutional F Individual Consult -INDV / Hiring M&E Experts fo IBRD / 92720 ramework, Project Managem Post Open 18,000.00 0.00 Canceled 2022-02-09 2022-03-07 2022-03-04 2022-03-04 2022-03-08 2023-03-08 ant Selection r RSTs ent, and Sustainability Page 5 TR-CEKEREK RST-278221-CS Component 2: Institutional F Individual Consult -INDV / Hiring Financial Mana IBRD / 92720 ramework, Project Managem Post Open 18,000.00 0.00 Canceled 2022-02-09 2022-03-07 2022-03-04 2022-03-04 2022-03-08 2023-03-08 ant Selection gement Experts for RSTs ent, and Sustainability TR-CEKEREK RST-278224-CS Component 2: Institutional F Individual Consult -INDV / Hiring Environmental IBRD / 92720 ramework, Project Managem Post Open 18,000.00 0.00 Canceled 2022-02-09 2022-03-07 2022-03-04 2022-05-02 2022-03-04 2022-03-08 2023-03-08 ant Selection Experts for RSTs ent, and Sustainability TR-CEKEREK RST-278225-CS Component 2: Institutional F Individual Consult -INDV / Hiring Social Experts IBRD / 92720 ramework, Project Managem Post Open 18,000.00 0.00 Canceled 2022-02-09 2022-03-07 2022-03-04 2022-03-04 2022-03-08 2023-03-08 ant Selection for RSTs ent, and Sustainability TR-CEKEREK RST-297080-CS Component 2: Institutional F Individual Consult -INDV / Recruitment of Monit IBRD / 92720 ramework, Project Managem Post Open 18,000.00 7,154.74 Signed 2022-05-26 2022-05-30 2022-06-16 2022-07-01 2022-06-18 2022-07-04 2022-06-24 2022-07-17 2022-12-31 ant Selection oring and Evaluation Speciali ent, and Sustainability st TR-CEKEREK RST-297085-CS Component 2: Institutional F Individual Consult -INDV / Recruitment of Enviro IBRD / 92720 ramework, Project Managem Post Open 18,000.00 7,144.15 Signed 2022-05-26 2022-05-30 2022-06-16 2022-06-28 2022-06-18 2022-07-04 2022-06-24 2022-07-17 2022-12-31 ant Selection nmental Specialist ent, and Sustainability TR-CEKEREK RST-297086-CS Component 2: Institutional F Individual Consult -INDV / Recruitment of Finan IBRD / 92720 ramework, Project Managem Post Open 18,000.00 1,212.67 Signed 2022-05-26 2022-05-30 2022-06-16 2022-06-27 2022-06-18 2022-07-01 2022-06-24 2022-07-14 2022-12-31 ant Selection cial Management Specialist ent, and Sustainability TR-CEKEREK RST-297087-CS Component 2: Institutional F Individual Consult -INDV / Recruitment Of Social IBRD / 92720 ramework, Project Managem Post Open 18,000.00 0.00 Canceled 2022-05-26 2022-06-27 2022-06-16 2022-06-18 2022-06-24 2022-12-31 ant Selection Development Specialist ent, and Sustainability TR-CEKEREK RST-306878-CS Component 2: Institutional F Individual Consult -INDV / Recruitment Of Social IBRD / 92720 ramework, Project Managem Post Open - National 18,000.00 0.00 Canceled 2022-08-01 2022-08-22 2022-08-22 2022-08-24 2022-08-30 2022-12-31 ant Selection Development Specialist ent, and Sustainability TR-CEKEREK RST-319168-CS Component 2: Institutional F Individual Consult -INDV / Recruitment Of Social IBRD / 92720 ramework, Project Managem Post Open - National 18,000.00 0.00 Canceled 2022-10-07 2022-10-06 2022-11-10 2022-11-28 2022-11-15 2022-11-30 2022-12-31 ant Selection Development Specialist ent, and Sustainability TR-CEKEREK RST-333645-CS Component 2: Institutional F Individual Consult -INDV / Social Safeguard Exp IBRD / 92720 ramework, Project Managem Post Open - National 18,000.00 0.00 Signed 2022-12-30 2022-12-29 2023-01-23 2023-02-20 2023-01-26 2023-02-20 2023-02-01 2023-03-02 2023-12-31 ant Selection ert İndividual Consultant Rec ent, and Sustainability ruitment. TR-CEKEREK RST-333650-CS Component 2: Institutional F Individual Consult -INDV / Biodiversity Expert İn IBRD / 92720 ramework, Project Managem Post Open - National 18,000.00 0.00 Signed 2022-12-30 2022-12-29 2023-01-23 2023-02-17 2023-01-26 2023-02-20 2023-02-01 2023-03-02 2023-12-31 ant Selection dividual Consultant Recruitm ent, and Sustainability ent TR-CEKEREK RST-348802-CS Component 2: Institutional F Individual Consult -INDV / Procurement Expert İ IBRD / 92720 ramework, Project Managem Post Open - National 21,600.00 0.00 Canceled 2023-03-17 2023-03-20 2023-04-12 2023-04-17 2023-04-27 2023-12-31 ant Selection ndividual Consultant Recruit ent, and Sustainability ment TR-CEKEREK RST-358348-CS Component 2: Institutional F Individual Consult -INDV / Procurement Expert İ IBRD / 92720 ramework, Project Managem Post Open - National 21,600.00 0.00 Canceled 2023-04-28 2023-05-12 2023-05-21 2023-05-21 2023-05-25 2023-12-31 ant Selection ndividual Consultant Recruit ent, and Sustainability ment TR-CEKEREK RST-412718-CS -INDV / Procurement Expert I ndıvıdual Consultant Recruıt Component 2: Institutional F Individual Consult ment. (Component: 2 Applica IBRD / 92720 ramework, Project Managem Prior Open - National 24,000.00 0.00 Canceled 2024-03-18 2024-03-26 2024-04-15 2024-04-22 2024-05-20 2024-12-31 ant Selection tion framework for integrated ent, and Sustainability landscape management / Su b-Component: 2.2 Project ma nagement and sustainability) Page 6