PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Western and Central Africa : Harmonizing and Improving Statistics in West and Central Africa - Series of Projects 1 (HISWACA - SOP 1) PLAN General Information Country: Western and Central Africa Bank’s Approval Date of the Original Procurement Plan: 2024-01-18 Revised Plan Date(s): (comma delineated, leave blank if 2024-08-31 none) Project ID: P178497 GPN Date: Project Name: Harmonizing and Improving Statistics in West and Central Africa - Series of Projects 1 (HISWACA - SOP 1) Loan / Credit No: IDA / 73190 National Agency for Statistics and Demography Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SN-ANSD-SN-415222-NC-RF Demande de cota Component 3: Construction, Q / Travaux de cloisonnemen Single Stage - One E tions (DTPM ne pr En cours d'e 2024-08-3 IDA / 73190 Upgrading and Modernizatio A posteriori Demande de prix Limited - National 8,064.00 0.00 2024-04-03 2024-05-15 2024-05-30 t des locaux de l'Unité de Ge nvelope ovenant pas de la xécution 0 n of Physical Infrastructure stion du Projet (UGP) Banque) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FOURNIT-2024-010 / Acquisi Component 4: Project Manag Single Stage - One E En attente d' IDA / 73190 A posteriori Demande de prix Limited 29,373.00 0.00 2024-01-31 2024-03-27 2024-09-23 tion de mobilier de bureau ement, Monitoring, and Eval nvelope exécution uation SN-ANSD-SN-412336-GO-RF Component 3: Construction, Single Stage - One E En cours d'ex B / Acquisition et pose de troi IDA / 73190 Upgrading and Modernizatio A posteriori Appel d'offres Open - National 483,816.00 0.00 2024-03-19 2024-04-29 2024-03-25 2024-06-26 2024-05-09 2024-05-29 2024-07-03 2024-12-31 nvelope écution s (03) ascenseurs n of Physical Infrastructure SN-ANSD-SN-412491-GO-RF Component 4: Project Manag Single Stage - One E En attente d' Q / Acquisition de matériel a IDA / 73190 ement, Monitoring, and Eval A posteriori Demande de prix Limited - National 43,382.00 0.00 2024-03-25 2024-05-08 2024-09-30 nvelope exécution udiovisuel uation SN-ANSD-SN-412546-GO-RF Component 3: Construction, Single Stage - One E En cours d'ex B / Acquisition de matériel fr IDA / 73190 Upgrading and Modernizatio A posteriori Appel d'offres Open - National 401,904.00 0.00 2024-03-18 2024-05-21 2024-03-28 2024-06-21 2024-05-02 2024-05-17 2024-06-14 2024-11-30 nvelope écution oid en deux (02) lots n of Physical Infrastructure SN-ANSD-SN-412551-GO-RF Component 3: Construction, Single Stage - One E En attente d' Q / Acquisition de matériel d’ IDA / 73190 Upgrading and Modernizatio A posteriori Demande de prix Limited - National 16,788.00 0.00 2024-03-20 2024-05-06 2024-09-30 nvelope exécution électricité n of Physical Infrastructure SN-ANSD-SN-412565-GO-RF Component 3: Construction, Single Stage - One E En attente d' Q / Acquisition de matériel d IDA / 73190 Upgrading and Modernizatio A posteriori Demande de prix Limited - National 9,770.00 0.00 2024-03-18 2024-05-03 2024-08-30 nvelope exécution e plomberie n of Physical Infrastructure SN-ANSD-SN-415221-GO-RF Component 3: Construction, Q / Acquisition de logiciel en Single Stage - One E En attente d' IDA / 73190 Upgrading and Modernizatio A posteriori Demande de prix Limited - National 104,827.00 0.00 2024-03-22 2024-05-17 2024-08-15 deux lots suivie de la formati nvelope exécution n of Physical Infrastructure on du personnel (MS projet, Tompro, Tompaie) Component 1: Harmonizatio SN-ANSD-SN-439846-GO-RF n and Production of Core Sta Single Stage - One E En attente d' Q / Acquisition de fourniture IDA / 73190 A posteriori Demande de prix Limited - National 16,128.00 0.00 2024-08-05 2024-09-13 2024-12-30 tistics using International Da nvelope exécution de bureau ta Quality Standards SN-ANSD-SN-439854-GO-RF Component 4: Project Manag Single Stage - One E En attente d' Q / Acquisition de matériel e IDA / 73190 ement, Monitoring, and Eval A posteriori Demande de prix Limited - National 25,804.00 0.00 2024-08-04 2024-09-15 2024-12-30 nvelope exécution t tenue de terrain deux (02 ) uation lots FOURNIT-2024-009 / Acquisi Component 4: Project Manag Single Stage - One E En attente d' tion de matériel roulant en d IDA / 73190 ement, Monitoring, and Eval A posteriori Appel d'offres Open - National 99,989.00 0.00 2024-08-12 2024-08-17 2024-09-26 2024-10-16 2024-11-20 2025-02-20 nvelope exécution eux (02) lots uation SN-ANSD-SN-415217-GO-RF B / Acquisition de matériel inf Component 3: Construction, Single Stage - One E En attente d' ormatique en neuf (09) lots IDA / 73190 Upgrading and Modernizatio A posteriori Appel d'offres Open - National 1,233,573.00 0.00 2024-08-05 2024-08-10 2024-09-19 2024-10-19 2024-11-23 2025-02-21 nvelope exécution ( ordinateur, vidéo projecteur n of Physical Infrastructure , imprimantes multi fonction, clés USB... etc ) SN-ANSD-SN-441571-GO-RF Component 3: Construction, Single Stage - One E En attente d' B / Acquisition de mobilier de IDA / 73190 Upgrading and Modernizatio A posteriori Appel d'offres Open - National 176,333.00 0.00 2024-07-30 2024-08-04 2024-09-15 2024-10-15 2024-11-19 2025-02-27 nvelope exécution bureau en trois (03) lots n of Physical Infrastructure SN-ANSD-SN-441891-GO-RF Component 4: Project Manag Single Stage - One E En attente d' B / Location de véhicule 4X4 IDA / 73190 ement, Monitoring, and Eval A posteriori Appel d'offres Open - National 145,145.00 0.00 2024-08-09 2024-08-14 2024-09-25 2024-10-25 2024-11-29 2025-05-28 nvelope exécution pick-up et Station Wagon uation Component 2: Statistical Mo SN-ANSD-SN-442217-GO-RF dernization, Institutional Ref Single Stage - One E En attente d' Q / Acquisition de matériel él IDA / 73190 A posteriori Demande de prix Limited - National 3,226.00 0.00 2024-08-24 2024-10-19 2024-12-30 orm, Human Capital, Data A nvelope exécution ectroménager ccessibility and Use SN-ANSD-SN-442303-GO-RF Q / Acquisition de supports pr Component 4: Project Manag Single Stage - One E En attente d' omotionnels pour la commun IDA / 73190 ement, Monitoring, and Eval A posteriori Demande de prix Limited - National 75,483.00 0.00 2024-08-25 2024-10-20 2024-12-31 nvelope exécution ication en quatre lots ( polos uation , t-shirt, kakemono, agenda... .........etc ) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SN-ANSD-SN-412863-NC-RF Q / Mise en place d'un systè Component 3: Construction, Single Stage - One E En attente d' me de géolocalisation du par IDA / 73190 Upgrading and Modernizatio A posteriori Demande de prix Limited - National 82,144.00 0.00 2024-04-01 2024-05-10 2025-03-31 nvelope exécution c automobile de l'ANSD ( acq n of Physical Infrastructure uisition de balise et abonnem ent) Page 1 SN-ANSD-SN-412489-NC-RF Q / Réalisation et pose de sig nalétique pour le siège de l' Component 4: Project Manag Single Stage - One E En attente d' ANSD, le bâtiment de l'UGP e IDA / 73190 ement, Monitoring, and Eval A posteriori Demande de prix Limited - National 80,636.00 0.00 2024-04-05 2024-05-13 2024-08-30 nvelope exécution t les Services Régionaux de l uation a Statistique et de la Démogr aphie ( brainding / enseigne l umineux...) SN-ANSD-SN-429711-GO-RF Component 2: Statistical Mo Q / Renouvellement des licen dernization, Institutional Ref Single Stage - One E En attente d' ces logicielles et matérielles IDA / 73190 A posteriori Demande de prix Limited - National 96,234.00 0.00 2024-06-02 2024-07-15 2024-07-31 orm, Human Capital, Data A nvelope exécution pour les équipements d’inter ccessibility and Use connexion de l'ANSD SN-ANSD-SN-447732-NC-RF Q / Impression de documents Component 1: Harmonizatio (Rapports, documents analyt n and Production of Core Sta Single Stage - One E En attente d' iques, répertoires et annuair IDA / 73190 A posteriori Appel d'offres Open - National 241,908.00 0.00 2024-08-30 2024-09-09 2024-10-09 2024-10-24 2024-11-15 2024-12-30 tistics using International Da nvelope exécution es des localités, atlas démog ta Quality Standards raphiques, plaquettes et dépl iants et calendrier historique) du RGPH-5. SN-ANSD-SN-447733-NC-RF Component 4: Project Manag Q / Sélection d'un assureur g Single Stage - One E En attente d' IDA / 73190 ement, Monitoring, and Eval A posteriori Demande de prix Limited - National 69,266.00 0.00 2024-09-04 2024-10-18 2025-10-18 roupe maladie pour le person nvelope exécution uation nel du PHASAOC CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SERVC-2024-008 / Recrutem Component 3: Construction, Sélection fondée s En attente d'exéc ent d' un cabinet pour les ét IDA / 73190 Upgrading and Modernizatio A posteriori ur la qualité et le Open - National 795,320.00 0.00 2024-01-29 2024-02-19 2024-04-03 2024-05-01 2024-05-31 2024-07-05 2024-08-09 2025-08-09 ution udes architecturales et tech n of Physical Infrastructure coût niques SN-ANSD-SN-412788-CS-QB Component 1: Harmonizatio Sélection fondée s S / Recrutement d'un cabinet n and Production of Core Sta En attente d'exéc IDA / 73190 A posteriori ur les qualification Open - National 193,526.00 0.00 2024-04-30 2024-05-20 2024-07-03 2024-08-02 2024-08-29 2024-12-30 pour la mise en place d'un D tistics using International Da ution s des consultants ata innovation Lab Pour le SS ta Quality Standards N SN-ANSD-SN-441590-CS-QB S / Recrutement d'un cabine Component 3: Construction, t pour une mission d’Assistan Sélection fondée s En attente d'exéc IDA / 73190 Upgrading and Modernizatio A posteriori Open - National 483,816.00 0.00 2024-07-31 2024-08-20 2024-09-16 2024-10-07 2024-11-06 2024-12-06 2025-01-10 2027-12-06 ce à la Maîtrise d’Ouvrage (A ur la qualité ution n of Physical Infrastructure MO) à l’ENSAE en vue de la c onstruction de ses locaux SN-ANSD-SN-442243-CS-QC Component 2: Statistical Mo BS / Recrutement d'un cabin Sélection fondée s dernization, Institutional Ref En attente d'exéc et pour le renforcement des IDA / 73190 A posteriori ur les qualification Limited - National 22,861.00 0.00 2024-08-30 2024-09-06 2024-09-21 2024-10-11 2024-12-31 orm, Human Capital, Data A ution capacités des acteurs en mat s des consultants ccessibility and Use ière de planification stratégiq ue du développement. SN-ANSD-SN-447897-CS-CQ S / Recrutement d'un cabinet Component 3: Construction, Sélection fondée s En attente d'exéc d'études pour mener le diagn IDA / 73190 Upgrading and Modernizatio A posteriori ur les qualification Open - National 11,289.00 0.00 2024-09-06 2024-09-27 2024-11-10 2024-12-10 2025-01-14 2025-07-13 ution ostic (plomberie, électricité, f n of Physical Infrastructure s des consultants roid, etc.) de la rénovation d u siège de l'ANSD. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SERVC-2024-001 / Sélection d’un consultant pour une mis Component 3: Construction, En cours d'exame sion d’Assistance à la Maîtris IDA / 73190 Upgrading and Modernizatio A posteriori Individuel Open - National 129,018.00 0.00 2024-01-31 2024-01-31 2024-03-20 2024-04-10 2024-05-15 2027-05-17 n e d’Ouvrage (AMO) à l’ENSAE n of Physical Infrastructure en vue de la construction de ses locaux SERVC-2024-003 / Recrutem Component 4: Project Manag ent d'un spécialiste en questi En cours d'exame IDA / 73190 ement, Monitoring, and Eval A posteriori Individuel Open - National 29,029.00 0.00 2024-01-19 2024-01-31 2024-02-24 2024-03-01 2024-03-19 2027-12-31 on sociale du projet d'appui a n uation u système statistique nationa l (HISWACA) SERVC-2024-004 / Recrutem Component 4: Project Manag ent d'un responsable adminis En cours d'exame IDA / 73190 ement, Monitoring, and Eval A posteriori Individuel Open - National 29,029.00 0.00 2024-01-23 2024-01-31 2024-02-26 2024-03-08 2024-04-12 2027-12-31 tratif et financier du projet d' n uation appui au système statistique national (HISWACA) SERVC-2024-005 / Recrutem ent d'un spécialiste en sauve Component 4: Project Manag En cours d'exame garde environnemental du pr IDA / 73190 ement, Monitoring, and Eval A posteriori Individuel Open - National 29,029.00 0.00 2024-01-22 2024-01-31 2024-02-20 2024-03-01 2024-03-27 2027-12-31 n ojet d'appui au système stati uation stique national (HISWACA) SERVC-2024-007 / Recrutem Component 4: Project Manag ent d'un responsable en suivi En cours d'exame IDA / 73190 ement, Monitoring, and Eval A posteriori Individuel Open - National 29,029.00 0.00 2024-01-19 2024-01-31 2024-02-25 2024-03-11 2024-03-28 2027-12-31 et évaluation du projet d'app n uation ui au système statistique nati onal ( HISWACA) SERVC-2024-006 / Recrutem Component 4: Project Manag ent d'un comptable du projet En cours d'exame IDA / 73190 ement, Monitoring, and Eval A posteriori Individuel Open - National 29,029.00 0.00 2024-01-22 2024-01-31 2024-02-20 2024-03-01 2024-04-05 2027-12-31 d'appui au système statistiqu n uation e national (HISWACA) SERVC-2024-002 / Sélection d'un consultant chargé de l’ Component 3: Construction, En cours d'exame analyse environnementale ini IDA / 73190 Upgrading and Modernizatio A posteriori Individuel Limited 8,064.00 0.00 2024-01-31 2024-01-29 2024-02-05 2024-02-26 2024-04-01 2024-09-28 n tiale (AEI) du projet de déloc n of Physical Infrastructure alisation de l'ENSAE à Diamni adio SN-ANSD-SN-412799-CS-IND Component 1: Harmonizatio V / Recrutement d'un consult n and Production of Core Sta En attente d'exéc IDA / 73190 A posteriori Individuel Limited - National 56,445.00 0.00 2024-03-28 2024-04-02 2024-04-22 2024-05-27 2024-11-23 ant pour l'élaboration du mo tistics using International Da ution dèle économique du NINEA ta Quality Standards Page 2 SN-ANSD-SN-412801-CS-IND Component 1: Harmonizatio V / Recrutement d'un consul n and Production of Core Sta En attente d'exéc IDA / 73190 A posteriori Individuel Limited - National 56,445.00 0.00 2024-04-15 2024-04-20 2024-05-10 2024-06-14 2024-12-11 tant pour l'élaboration du m tistics using International Da ution odèle juridique du NINEA ta Quality Standards SN-ANSD-SN-412796-CS-IND V / Recrutement d'un consult Component 1: Harmonizatio ant international pour aider n and Production of Core Sta Limited - Internatio En attente d'exéc IDA / 73190 A posteriori Individuel 4,032.00 0.00 2024-03-28 2024-04-02 2024-04-30 2024-05-30 2024-11-26 à la réalisation de la note con tistics using International Da nal ution ceptuelle du Recensement N ta Quality Standards ational de l'Agriculture(RNA) SN-ANSD-SN-440191-CS-IND V / Recrutement d'un consult Component 2: Statistical Mo ant devant réaliser l'étude di dernization, Institutional Ref En attente d'exéc IDA / 73190 A posteriori Individuel Limited - National 32,255.00 0.00 2024-07-24 2024-07-29 2024-08-13 2024-09-13 2024-12-23 agnostique sur la rationalisat orm, Human Capital, Data A ution ion de l’organisation et la ges ccessibility and Use tion centralisée des ressourc es humaines SN-ANSD-SN-440201-CS-IND V / Selection d'un consultant Component 2: Statistical Mo pour l'élaboration du Cadre N dernization, Institutional Ref En attente d'exéc IDA / 73190 A posteriori Individuel Limited - National 24,191.00 0.00 2024-07-26 2024-07-31 2024-08-15 2024-09-10 2024-12-19 ational d'Assurance Qualité ( orm, Human Capital, Data A ution CNAQ) des données pour le ccessibility and Use Système Statistique National (SSN) SN-ANSD-SN-441601-CS-IND Component 2: Statistical Mo V / Sélection d'un consultant dernization, Institutional Ref En attente d'exéc IDA / 73190 A posteriori Individuel Limited - National 4,839.00 0.00 2024-08-01 2024-08-06 2024-08-27 2024-10-01 2024-10-31 pour l’animation du cours de orm, Human Capital, Data A ution Machine Learning 2 au profit ccessibility and Use des élèves ISE. SN-ANSD-SN-441604-CS-IND V / Sélection d' un consultan Component 2: Statistical Mo t pour l’animation du cours d’ dernization, Institutional Ref En attente d'exéc IDA / 73190 A posteriori Individuel Limited - National 4,839.00 0.00 2024-08-01 2024-08-06 2024-08-27 2024-10-01 2024-10-31 économétrie de la finance au orm, Human Capital, Data A ution profit des élèves ISE en derni ccessibility and Use ère année de formation pour l’option finance et actuariat. SN-ANSD-SN-442199-CS-IND V / Sélection d' un consultan Component 3: Construction, En attente d'exéc t statisticien ou Economiste p IDA / 73190 Upgrading and Modernizatio A posteriori Individuel Limited - National 11,853.00 0.00 2024-08-12 2024-08-17 2024-09-07 2024-10-12 2025-01-30 ution our la conduite de l’étude sur n of Physical Infrastructure la réforme institutionnelle de l’ENSAE SN-ANSD-SN-442209-CS-IND V / Sélection d' un consultan Component 3: Construction, En attente d'exéc t démographe pour la condu IDA / 73190 Upgrading and Modernizatio A posteriori Individuel Limited - National 11,853.00 0.00 2024-08-13 2024-08-18 2024-09-08 2024-10-13 2025-01-30 ution ite de l’étude sur la réforme i n of Physical Infrastructure nstitutionnelle de l’ENSAE SN-ANSD-SN-447729-CS-CQ Component 1: Harmonizatio S / Sélection d'un consultant n and Production of Core Sta En attente d'exéc pour la formation des agents IDA / 73190 A posteriori Individuel Limited - National 23,223.00 0.00 2024-09-05 2024-09-10 2024-09-30 2024-11-04 2025-05-03 tistics using International Da ution du Système statistique natio ta Quality Standards nal (SSN) en data science SN-ANSD-SN-447734-CS-CQ S / Recrutement d'un consult Component 2: Statistical Mo ant pour former le personnel dernization, Institutional Ref En attente d'exéc IDA / 73190 A posteriori Individuel Limited - National 8,064.00 0.00 2024-09-02 2024-09-07 2024-09-27 2024-10-29 2025-04-27 de l'ANSD sur l’acte uniforme orm, Human Capital, Data A ution relatif au Système Comptabl ccessibility and Use e des Entités à But Non Lucra tif (SYCEBNL). Page 3