PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo – Regional Disease Surveillance Systems Enhancement - P167817 Project Implementation agency: UGP PDSS Date of the Procurement Plan: June 2019 Period covered by this Procurement Plan: June 2019 – December 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Western and Central Africa : Regional Disease Surveillance Systems Enhancement Project (REDISSE) Phase IV PLAN General Information Country: Western and Central Africa 2019-12-30 Bank’s Approval Date of the Original Procurement Plan: 2024-08-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167817 GPN Date: 2020-05-18 Project Name: Regional Disease Surveillance Systems Enhancement Project (REDISSE) Phase IV Loan / Credit No: IDA / 64990, IDA / D5080, IDA / D5160, IDA / 64980 CAR-MINISTRY OF HEALTH AND POPULATION- National Technical Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CF-CAR-MSPP-CTN-206765-C Component 2: Strengthenin W-RFQ / Réhabilitation de 6 l g Emergency Planning and Single Stage - One E 2021-11-0 IDA / D5080 A posteriori Demande de prix Limited 190,000.00 0.00 Annulé 2021-03-15 2021-05-10 abos de districts de la Région Management Capacity to Ra nvelope 6 Sanitaire n°2 (RS2) pidly respond to Outbreaks CF-CAR-MSPP-CTN-206769-C Component 2: Strengthenin W-RFQ / Réhabilitation de 4 l g Emergency Planning and Single Stage - One E 2021-11-2 IDA / D5080 A posteriori Demande de prix Limited 190,000.00 0.00 Annulé 2021-04-04 2021-05-30 abos de districts de la Région Management Capacity to Ra nvelope 6 Sanitaire n°4 (RS4). pidly respond to Outbreaks CF-CAR-MSPP-CTN-206770-C Component 2: Strengthenin W-RFQ / Réhabilitation de 3 l g Emergency Planning and Single Stage - One E 2021-11-2 IDA / D5080 A posteriori Demande de prix Limited 190,000.00 0.00 Annulé 2021-04-04 2021-05-30 abos de districts de la Région Management Capacity to Ra nvelope 6 Sanitaire n°5 (RS5) pidly respond to Outbreaks CF-CAR-MSPP-CTN-206773-C Component 2: Strengthenin W-RFQ / Réhabilitation de 6 l g Emergency Planning and Single Stage - One E 2021-12-0 IDA / D5080 A posteriori Demande de prix Limited 190,000.00 0.00 Annulé 2021-04-10 2021-06-05 abos de districts de la Région Management Capacity to Ra nvelope 2 !sanitaire n°6 (RS6) pidly respond to Outbreaks CF-CAR-MSPP-CTN-153719-C Component 2: Strengthenin W-RFQ / Réhabilitation de 5 l g Emergency Planning and Single Stage - One E 2021-10-0 IDA / 64990 A posteriori Demande de prix Limited 190,000.00 0.00 Annulé 2021-02-15 2021-04-12 aboratoires de districts sanit Management Capacity to Ra nvelope 9 aires de la Région Sanitaire n pidly respond to Outbreaks °1 (RS1) CF-CAR-MSPP-CTN-206766-C Component 2: Strengthenin W-RFQ / Réhabilitation de 8 l g Emergency Planning and Single Stage - One E 2021-11-1 IDA / D5080 A posteriori Demande de prix Limited 190,000.00 0.00 Annulé 2021-03-25 2021-05-20 abos de districts de la Région Management Capacity to Ra nvelope 6 Sanitaire n°3 (RS3) pidly respond to Outbreaks CF-CAR-MSPP-CTN-153714-C Component 1: Strengthening W-RFQ / Réhabilitation de 5 l Surveillance and Laboratory Single Stage - One E 2021-10-3 IDA / D5080 A posteriori Demande de prix Limited 190,000.00 0.00 Annulé 2021-03-08 2021-05-03 abos de santé animale dans l Capacity to Rapidly detect O nvelope 0 a région de Bambari utbreaks CF-CAR-MSPP-CTN-151849-C W-RFB / Réhabilitation du ce Component 2: Strengthenin ntre de traitement des épidé g Emergency Planning and Single Stage - Two E 2022-03-2 IDA / D5080 A posteriori Appel d'offres Open - National 700,000.00 0.00 Annulé 2021-04-20 2021-04-25 2021-06-06 2021-08-19 2021-09-23 mies de Bangui et 13 centres Management Capacity to Ra nvelope 2 dans les districts de priorité pidly respond to Outbreaks 1 gestion situation exception nelle CF-CAR-MSPP-CTN-212329-C Component 1: Strengthening W-RFQ / Réhabilitation du ce Surveillance and Laboratory Single Stage - One E 2021-11-1 IDA / D5080 A posteriori Demande de prix Limited 195,000.00 0.00 Annulé 2021-03-20 2021-05-15 ntre de cours d'épidémiologi Capacity to Rapidly detect O nvelope 1 e à la Faculté des Sciences d utbreaks e Santé à Bambari CF-REDISSE IV-016-RFQ / Ré habilitation du poste de contr Component 2: Strengthenin ôle sanitaire de Ouango Sao g Emergency Planning and Single Stage - One E 2021-12-1 IDA / D5080 A posteriori Demande de prix Limited 100,000.00 87,335.43 Signé 2021-04-25 2021-11-25 2021-06-20 2021-12-31 sur le long du fleuve Oubang Management Capacity to Ra nvelope 7 ui pour la prevention de la m pidly respond to Outbreaks aladie a virus Ebola (MVE) et COVID19 CF-CAR-MSPP-CTN-225264-C Component 2: Strengthenin W-RFQ / Réhabilitation du po g Emergency Planning and Single Stage - One E 2021-12-1 ste d'entrée de Mongoumba IDA / D5080 A posteriori Demande de prix Limited 100,000.00 80,747.81 Signé 2021-04-25 2021-10-26 2021-06-20 2022-02-24 Management Capacity to Ra nvelope 7 sur le fleuve Oubangui pour l pidly respond to Outbreaks utter contre EBOLA et COVID 19 CF-CAR-MSPP-CTN-225265-C Component 2: Strengthenin W-RFQ / Réhabilitation du po g Emergency Planning and Single Stage - One E 2022-01-0 ste d'entrée de Zinga sur le fl IDA / D5080 A posteriori Demande de prix Limited 100,000.00 81,428.37 Signé 2021-05-10 2021-10-29 2021-07-05 2021-12-31 Management Capacity to Ra nvelope 1 euve Oubangui pour lutter co pidly respond to Outbreaks ntre EBOLA et COVID 19 CF-CAR-MSPP-CTN-225266-C Component 2: Strengthenin W-RFQ / Réhabilitation du po g Emergency Planning and Single Stage - One E 2021-12-1 ste d'entrée de Gouga sur le IDA / D5080 A posteriori Demande de prix Limited 100,000.00 91,035.25 Signé 2021-04-20 2021-10-29 2021-06-15 2021-12-31 Management Capacity to Ra nvelope 2 fleuve Oubangui pour lutter c pidly respond to Outbreaks ontre EBOLA et COVID 19 Document nation CW-SENI-REDISSE IV - 163-R al de passation de Component 1: Strengthening FQ / Réhabilitation du labora s marchés - Proce Surveillance and Laboratory Single Stage - One E 2023-02-1 toire de Microbiologie Alimen IDA / D5080 A posteriori Demande de prix Limited ssus à une envelo 69,300.00 0.00 Signé 2022-06-25 2022-10-11 2022-08-20 2023-02-15 Capacity to Rapidly detect O nvelope 6 taire et du Laboratoire Natio ppe (DTPM ne pro utbreaks nal de Biologie Clinique Sant venant pas de la é Publique Banque) Document nation CW-SENI-REDISSE IV-165-RF al de passation de Component 1: Strengthening Q / Réhabiliter et équiper un l s marchés - Proce Surveillance and Laboratory Single Stage - One E 2023-05-1 ocal pour abriter la Coordinat IDA / D5080 A posteriori Demande de prix Limited ssus à une envelo 174,000.00 0.00 Annulé 2022-09-21 2022-11-16 Capacity to Rapidly detect O nvelope 5 ion Nationale du RSI (Directio ppe (DTPM ne pro utbreaks n de Surveillance Epidémiolo venant pas de la gique) Banque) Document nation CW-SENI-REDISSE IV - 166- al de passation de Component 1: Strengthening CW / Réhabiliter/Extension d s marchés - Proce Surveillance and Laboratory Single Stage - One E 2023-01-1 es bureaux de la Coordinatio IDA / D5080 A posteriori Appel d'offres Open - National ssus à une envelo 226,000.00 0.00 Signé 2022-03-28 2023-08-30 2022-04-02 2022-05-14 2022-02-04 2022-06-13 2023-10-17 2022-07-18 2022-03-30 Capacity to Rapidly detect O nvelope 4 n Générale du projet SENI-RE ppe (DTPM ne pro utbreaks DISSE IV (complément du fin venant pas de la ancement sur SENI) Banque) CW-SENI-REDISSE IV-164-RF Component 1: Strengthening Demande d'offres W / Réhabilitation / Fabricatio Surveillance and Laboratory Single Stage - Two E - DTPM Petits trav 2023-09-2 IDA / D5080 A posteriori Appel d'offres Open - National 650,000.00 0.00 Annulé 2022-10-24 2022-10-29 2022-12-10 2023-02-22 2023-03-29 n des hangars pour abriter le Capacity to Rapidly detect O nvelope aux (processus à 5 s PoE désignés du pays utbreaks deux enveloppes) Page 1 Document nation CF-REDISSE IV-023-02-RFB / Component 2: Strengthenin al d'appel d'offres Réhabilitation/l'extension du g Emergency Planning and Single Stage - Two E - Processus à 2 en En attente d 2024-07-0 IDA / D5080 A posteriori Appel d'offres Open - National 200,000.00 0.00 2023-08-07 2023-08-12 2023-09-23 2023-12-06 2024-01-10 bâtiment abritant le COUSP p Management Capacity to Ra nvelope veloppes (DTPM n 'exécution 8 our la direction de la surveill pidly respond to Outbreaks e provenant pas d ance e la Banque) Document nation CF-REDISSE IV-023-38-RFQ / Component 1: Strengthening al de passation de Réhabilitation du laboratoire Surveillance and Laboratory Single Stage - One E s marchés - Proce 2023-12-0 IDA / D5080 A posteriori Demande de prix Open - National 50,000.00 0.00 Annulé 2023-04-15 2023-06-10 vétérinaire du niveau central Capacity to Rapidly detect O nvelope ssus à une envelo 7 de Yaloké utbreaks ppe (DTPM ne pro venant pas de la Banque) nation Document CF-REDISSE IV-023-02-RFQ / Component 1: Strengthening al de passation de Réhabilitation d'un bâtiment Surveillance and Laboratory Single Stage - One E s marchés - Proce 2024-01-0 aux normes standards au niv IDA / D5080 A posteriori Demande de prix Limited 90,000.00 0.00 Annulé 2023-05-13 2023-07-08 Capacity to Rapidly detect O nvelope ssus à une envelo 4 eau du point d'entrée désign utbreaks ppe (DTPM ne pro é de Béloko venant pas de la Banque) nation Document CF-REDISSE IV-023-29-RFQ / Component 1: Strengthening al de passation de Réhabilitation des laboratoire Surveillance and Laboratory Single Stage - One E s marchés - Proce 2023-12-0 IDA / D5080 A posteriori Demande de prix Limited 60,000.00 0.00 Annulé 2023-04-15 2023-06-10 s de santé humaine de l’hôpi Capacity to Rapidly detect O nvelope ssus à une envelo 7 tal régional RSN°1 - Boali utbreaks ppe (DTPM ne pro venant pas de la Banque) CF-REDISSE IV-023-40-RFQ / Component 2: Strengthenin Demande de cota l'extension du bâtiment abrit g Emergency Planning and Single Stage - One E tions (DTPM ne pr 2024-07-0 IDA / D5080 A posteriori Demande de prix Limited 200,000.00 0.00 Signé 2023-11-08 2023-11-14 2024-01-03 2024-03-25 ant le COUSP pour la directio Management Capacity to Ra nvelope ovenant pas de la 1 n de la surveillance pidly respond to Outbreaks Banque) Document nation CF-REDISSE IV-023-06-RFQ / Component 1: Strengthening al de passation de Réhabilitation du Laboratoire Surveillance and Laboratory Single Stage - One E s marchés - Proce 2024-02-0 IDA / D5080 A posteriori Demande de prix Limited 100,000.00 0.00 Signé 2023-06-10 2023-11-24 2023-08-05 2024-02-14 d'Entomologie médicale au L Capacity to Rapidly detect O nvelope ssus à une envelo 1 NBCSP utbreaks ppe (DTPM ne pro venant pas de la Banque) nation Document CF-REDISSE IV-023-37-RFQ / Component 1: Strengthening al de passation de Réhabilitation du laboratoire Surveillance and Laboratory Single Stage - One E s marchés - Proce En cours d'e 2024-11-2 IDA / D5080 A posteriori Demande de prix Limited - National 50,000.00 0.00 2024-04-07 2024-07-17 2024-06-02 vétérinaire du niveau régiona Capacity to Rapidly detect O nvelope ssus à une envelo xécution 9 l de Bambari utbreaks ppe (DTPM ne pro venant pas de la Banque) nation Document Component 2: Strengthenin al de passation de CF-REDISSE IV-023-12-RFQ / g Emergency Planning and Single Stage - One E s marchés - Proce 2024-12-0 Réhabilitation de laboratoire IDA / D5080 A posteriori Demande de prix Limited - National 200,000.00 0.00 Signé 2024-04-16 2024-08-01 2024-06-11 Management Capacity to Ra nvelope ssus à une envelo 8 de sciences biomédicales pidly respond to Outbreaks ppe (DTPM ne pro venant pas de la Banque) nation Document CF-REDISSE IV-023-36-RFQ / Component 1: Strengthening al de passation de Réhabilitation du laboratoire Surveillance and Laboratory Single Stage - One E s marchés - Proce 2024-12-1 IDA / D5080 A posteriori Demande de prix Limited - National 200,000.00 0.00 Signé 2024-04-27 2024-06-27 2024-06-22 2024-07-01 vétérinaire du niveau central Capacity to Rapidly detect O nvelope ssus à une envelo 9 de Bangui utbreaks ppe (DTPM ne pro venant pas de la Banque) nation Document CF-REDISSE IV-023-33-RFQ / Component 1: Strengthening al de passation de Réhabilitation des laboratoire Surveillance and Laboratory Single Stage - One E s marchés - Proce En attente d 2024-12-2 IDA / D5080 A posteriori Demande de prix Limited - National 60,000.00 0.00 2024-05-05 2024-06-30 s de santé humaine de l’hôpi Capacity to Rapidly detect O nvelope ssus à une envelo 'exécution 7 tal régional RSN°4 - Bambari utbreaks ppe (DTPM ne pro venant pas de la Banque) nation Document CF-REDISSE IV-023-35-RFQ / Component 1: Strengthening al de passation de Réhabilitation des laboratoire Surveillance and Laboratory Single Stage - One E s marchés - Proce 2024-12-2 s de santé humaine de l’hôpi IDA / D5080 A posteriori Demande de prix Limited - National 60,000.00 0.00 Signé 2024-05-07 2024-06-13 2024-07-02 2024-06-27 Capacity to Rapidly detect O nvelope ssus à une envelo 9 tal régional RSN°6 - Bangass utbreaks ppe (DTPM ne pro ou venant pas de la Banque) nation Document CF-REDISSE IV-023-30-RFQ / Component 1: Strengthening al de passation de Réhabilitation des laboratoire Surveillance and Laboratory Single Stage - One E s marchés - Proce 2024-12-2 IDA / D5080 A posteriori Demande de prix Limited - National 60,000.00 0.00 Signé 2024-04-30 2024-06-11 2024-06-25 2024-06-27 s de santé humaine de l’hôpi Capacity to Rapidly detect O nvelope ssus à une envelo 2 tal régional RSN°2 - Berberati utbreaks ppe (DTPM ne pro venant pas de la Banque) Document nation CF-REDISSE IV-023-32-RFQ / Component 1: Strengthening al de passation de Réhabilitation des laboratoire Surveillance and Laboratory Single Stage - One E s marchés - Proce 2024-12-1 s de santé humaine de l’hôpi IDA / D5080 A posteriori Demande de prix Limited - National 60,000.00 0.00 Signé 2024-04-22 2024-06-05 2024-06-17 2024-06-07 Capacity to Rapidly detect O nvelope ssus à une envelo 4 tal régional RSN°3 - Bossang utbreaks ppe (DTPM ne pro oa venant pas de la Banque) nation Document Component 1: Strengthening al de passation de CF-REDISSE IV-023-39-RFQ / Surveillance and Laboratory Single Stage - One E s marchés - Proce En attente d 2025-06-2 RÉHABILITATION DU LABORA IDA / D5080 A posteriori Demande de prix Limited - National 100,000.00 0.00 2024-11-05 2024-12-31 Capacity to Rapidly detect O nvelope ssus à une envelo 'exécution 9 TOIRE DE DEKOA utbreaks ppe (DTPM ne pro venant pas de la Banque) nation Document CF-REDISSE IV-023-34-RFQ / Component 1: Strengthening al de passation de Réhabilitation des laboratoire Surveillance and Laboratory Single Stage - One E s marchés - Proce En attente d 2025-06-2 IDA / D5080 A posteriori Demande de prix Limited - National 100,000.00 0.00 2024-11-05 2024-12-31 s de santé humaine de l’hôpi Capacity to Rapidly detect O nvelope ssus à une envelo 'exécution 9 tal régional RSN°5 - Bria utbreaks ppe (DTPM ne pro venant pas de la Banque) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF-CAR-MSPP-CTN-151937-G Component 2: Strengthenin O-RFQ / Achat de 10 télépho g Emergency Planning and Single Stage - One E IDA / 64990 A posteriori Demande de prix Limited 16,000.00 0.00 Annulé 2020-04-06 2020-06-01 2020-11-28 nes satellitaires pour les poin Management Capacity to Ra nvelope ts d’entrée pidly respond to Outbreaks CF-CAR-MSPP-CTN-151921-G Component 1: Strengthening O-RFB / Equipement pour 05 Surveillance and Laboratory Single Stage - One E IDA / 64990 A posteriori Appel d'offres Open - National 700,000.00 0.00 Annulé 2021-02-02 2021-02-07 2021-03-21 2021-04-20 2021-05-25 2021-11-21 labo vétérinaires et 35 labo d Capacity to Rapidly detect O nvelope e districts sanitaires utbreaks CF-CAR-MSPP-CTN-151852-G Component 1: Strengthening O-RFQ / Acquisition de 12pho Surveillance and Laboratory Single Stage - One E tocopieurs de grande capacit IDA / D5160 A posteriori Demande de prix Limited 36,000.00 0.00 Annulé 2020-04-20 2020-06-15 2020-12-12 Capacity to Rapidly detect O nvelope é pour les 02 directions et les utbreaks 07 regions sanitaires et 03 D R elevage CF-CAR-MSPP-CTN-151850-G Component 1: Strengthening O-DIR / Achat des équipemen Surveillance and Laboratory Passation de marc ts pour renforcer un réseau d IDA / D5160 A posteriori Direct 40,000.00 0.00 Annulé 2020-04-15 2020-04-20 2020-05-25 2020-11-21 Capacity to Rapidly detect O hé de gré à gré e laboratoire privés et des la utbreaks boratoires de santé publique CF-CAR-MSPP-CTN-151930-G O-RFQ / Achat de 59 télépho Component 4: Institutional C nes smart-phones+ logiciel A apacity Building, Project Ma Single Stage - One E va dar pour les 35 districts, r IDA / 64990 A posteriori Demande de prix Limited 45,000.00 0.00 Annulé 2021-03-20 2021-05-15 2021-11-11 nagement, Coordination and nvelope égions sanitaires et niveau c Advocacy entral et 09SA(02 central et 07 région) + téléphones sate llitaires Page 2 CF-CAR-MSPP-CTN-151922-G Component 2: Strengthenin O-RFQ / Achat de 10 réfrigéra g Emergency Planning and Single Stage - One E IDA / 64990 A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2020-04-20 2020-06-15 2020-12-12 teurs de 300l pour la conserv Management Capacity to Ra nvelope ation des réactifs pidly respond to Outbreaks CF-CAR-MSPP-CTN-151893-G Component 2: Strengthenin O-RFQ / Acquisition de 02 VS g Emergency Planning and Single Stage - One E IDA / 64990 A posteriori Demande de prix Limited 16,000.00 0.00 Annulé 2020-04-20 2020-06-15 2020-12-12 AT pour la connexion (01 dire Management Capacity to Ra nvelope ction santé animale et COUS pidly respond to Outbreaks P) CF-CAR-MSPP-CTN-151944-G Component 1: Strengthening O-DIR / Acquisition d'équipe Surveillance and Laboratory Single Stage - One E ment des labos pour la Direct IDA / D5080 A posteriori Appel d'offres Open - National 400,000.00 0.00 Annulé 2021-03-15 2021-03-20 2021-05-01 2021-05-31 2021-07-05 2022-01-01 Capacity to Rapidly detect O nvelope ion de la Santé Humaine et la utbreaks Direction de la santé animale CF-CAR-MSPP-CTN-151888-G Component 2: Strengthenin Passation de marc O-UN / Achat des vaccins et a g Emergency Planning and IDA / D5160 A priori hés auprès des ag Direct 150,000.00 0.00 Annulé 2020-05-01 2020-05-06 2020-06-10 2020-12-07 utres intrants médicaux pour Management Capacity to Ra ences de l'ONU les zoonoses et les humains pidly respond to Outbreaks CF-CAR-MSPP-CTN-151861-G Component 2: Strengthenin O-RFQ / Achat de 49 motos ( g Emergency Planning and Single Stage - One E IDA / D5160 A posteriori Demande de prix Limited 245,000.00 0.00 Annulé 2020-03-06 2020-05-01 2020-10-28 35 points focaux ,07 régions Management Capacity to Ra nvelope sanitaires et 07 pour élevag pidly respond to Outbreaks e CF-CAR-MSPP-CTN-151945-G O-RFQ / Achat de 50 thermo- Component 2: Strengthenin flash et des kit médicaux d’u g Emergency Planning and Single Stage - One E IDA / 64990 A posteriori Demande de prix Limited 170,000.00 0.00 Annulé 2020-03-20 2020-05-15 2020-11-11 rgence et 55 dispositifs de la Management Capacity to Ra nvelope vage de mains +1000 équip pidly respond to Outbreaks ements de protection individ uelle CF-CAR-MSPP-CTN-151874-G Component 2: Strengthenin O-RFQ / Achat de 10 groupes g Emergency Planning and Single Stage - One E électrogènes de 03 KVA(7 ré IDA / D5160 A posteriori Demande de prix Limited 70,000.00 0.00 Annulé 2020-04-20 2020-06-15 2020-12-12 Management Capacity to Ra nvelope gions et 03 élevage pour sou pidly respond to Outbreaks tenir la reproduction des outil s de collecte. CF-CAR-MSPP-CTN-151940-G Component 1: Strengthening Passation de marc O-DIR / Achat des réactifs et IDA / D5080 Surveillance and Laboratory A posteriori Direct 300,000.00 288,212.90 Signé 2020-04-15 2021-03-10 2020-04-20 2021-03-29 2020-05-25 2021-04-13 2020-11-21 hé de gré à gré consommables pour tous les Capacity to Rapidly detect O secteurs utbreaks CF-CAR-MSPP-CTN-153717-G O-RFQ / Acquisition de 4 véh Component 4: Institutional C icules Pick Up et 2 Véhicules apacity Building, Project Ma Single Stage - One E type jeep à 8 place pour l'Uni IDA / D5080 A posteriori Appel d'offres Open - National 400,000.00 426,650.70 Signé 2021-01-12 2021-05-06 2021-01-17 2021-05-06 2021-02-28 2021-08-18 2021-03-30 2021-08-18 2021-05-04 2021-09-03 2021-10-31 nagement, Coordination and nvelope té de Coordination et la Direc Advocacy tion de la Santé Animale et 5 motos pour la composante V BG CF-REDISSE IV-109-RFQ / Ac Component 1: Strengthening quisition des deux (2) 2 Gene Surveillance and Laboratory Single Stage - One E IDA / D5080 A posteriori Demande de prix Limited 28,000.00 0.00 Signé 2022-05-04 2022-10-20 2022-06-29 2023-03-05 2022-12-26 xperts pour renforcer le diag Capacity to Rapidly detect O nvelope nostic de COVID 19 utbreaks CF-REDISSE IV - 116-RFQ / A chat de kits de visibilité (logo Component 4: Institutional C SENI-REDISSE IV, Appareils p apacity Building, Project Ma Single Stage - One E IDA / D5080 A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2022-06-14 2022-07-12 2022-08-09 2023-02-05 hoto, gadgets, Polo, Jackets... nagement, Coordination and nvelope ), des communiqués de press Advocacy e, des bulletins d'information , photos/vidéos etc. CF-REDISSE IV - 125 - RFQ / Component 1: Strengthening Single Stage - One E Reproduction des outils de co IDA / D5080 Surveillance and Laboratory A posteriori Demande de prix Limited 13,000.00 0.00 Annulé 2022-08-15 2022-10-10 2023-04-08 nvelope llecte des données Capacity to Rapidly detect O utbreaks CF - SENI-REDISSE IV - 132 - RFB / Acquisition des 300 Ta Component 1: Strengthening blettes androïd pour 250 FOS Surveillance and Laboratory Single Stage - One E IDA / D5080 A posteriori Appel d'offres Open - National 105,000.00 0.00 Signé 2022-05-23 2022-09-06 2022-05-28 2022-09-06 2022-07-09 2023-03-03 2022-08-08 2023-03-22 2022-09-12 2023-06-02 2023-03-11 A , 15 districts, 5 Régions Sa Capacity to Rapidly detect O nvelope nitaires, 50 Postes vétérinair utbreaks es et 15 Secteurs vétérinaire s pour la surveillance électro nique CF - SENI - REDISSE IV - 134 - RFB - GO / Acquisition des Component 1: Strengthening mobiliers de Bureau et fourni Surveillance and Laboratory Single Stage - One E tures pour le COUSP ,en tech IDA / D5080 A posteriori Appel d'offres Open - National 150,000.00 0.00 Annulé 2022-10-21 2022-10-26 2022-12-07 2023-01-06 2023-02-10 2023-08-09 Capacity to Rapidly detect O nvelope nologies de l'information et d utbreaks e la communication pour la g estion des opérations d'urge nce (niveau central et décent ralisé) CF - SENI - REDISSE IV - 137- Component 1: Strengthening RFQ / Acquisition des kits et Surveillance and Laboratory Single Stage - One E IDA / D5080 A posteriori Demande de prix Limited 9,000.00 0.00 Annulé 2022-04-19 2022-06-14 2022-12-11 dispositifs de lavage des mai Capacity to Rapidly detect O nvelope ns aux peuples autochtones utbreaks CF - SENI - REDISSE IV - 140 Component 1: Strengthening Single Stage - One E - RFQ / Reproduction des outi IDA / D5080 Surveillance and Laboratory A posteriori Demande de prix Limited 9,000.00 0.00 Annulé 2022-08-08 2022-10-03 2023-04-01 nvelope ls (Guide de formation FETP Capacity to Rapidly detect O de base) utbreaks CF-SENI-REDISSE IV-166-RF Component 1: Strengthening Q / Acquisition des médicam Surveillance and Laboratory Single Stage - One E IDA / D5080 A posteriori Demande de prix Limited 69,800.00 0.00 Annulé 2022-08-30 2022-10-25 2023-04-23 ents (stock de contingence) Capacity to Rapidly detect O nvelope pour la réponse aux urgence utbreaks s CF-CAR-MSPP-CTN-151935-G O-RFQ / Achat de fournitures Component 4: Institutional C de bureau + consommables i apacity Building, Project Ma Single Stage - One E nformatiques pour les Région IDA / 64990 A posteriori Demande de prix Limited 90,000.00 0.00 Annulé 2020-03-06 2020-05-01 2020-10-28 nagement, Coordination and nvelope s Sanitaires et les 13 points f Advocacy ocaux, 3 Directions et 7 sect eurs Elevage et Direction de la Santé animale et humaine CF-SENI-REDISSE IV - 167-RF Component 1: Strengthening B / Elaboration et Reproducti Surveillance and Laboratory Single Stage - One E IDA / D5080 A posteriori Appel d'offres Open - National 140,000.00 0.00 Annulé 2022-12-19 2022-12-24 2023-02-04 2023-03-06 2023-04-10 2023-10-07 on des différents outils de co Capacity to Rapidly detect O nvelope mmunication pour la prévent utbreaks ion des maladies Page 3 CF-REDISSE IV - 110 – RFB / Acquisition des matériels info rmatiques de dix (12) imprim Component 1: Strengthening antes et une grande imprima Surveillance and Laboratory Single Stage - One E nte multifonction pour les Poi IDA / D5080 A posteriori Appel d'offres Open - National 279,000.00 0.00 Annulé 2022-09-27 2022-10-02 2022-11-13 2022-12-13 2023-01-17 2023-07-16 Capacity to Rapidly detect O nvelope nts Focaux RSI, et les COUSP, utbreaks de Dix-sept (17) ordinateurs portables, 2 appareils photo et une caméra et les matériel s de communication. CF-REDISSE IV-0013-RFB / - Acquisition d'équipements et consommables de laboratoir Component 2: Strengthenin e pour les 15 districts sanitai g Emergency Planning and Single Stage - One E En attente d' IDA / D5080 A posteriori Appel d'offres Open - National 159,000.00 0.00 2022-09-28 2022-10-03 2022-11-14 2022-12-14 2023-01-18 2023-07-17 res, au niveau national et po Management Capacity to Ra nvelope exécution ur les 4 Laboratoires vétérina pidly respond to Outbreaks ires (panneaux solaires, chai ne de froids, microscopes, au tomates…..) CF - SENI-REDISSE IV-165-RF B / Reproduction des différen Component 1: Strengthening ts outils de collecte des donn Surveillance and Laboratory Single Stage - One E ées secondaires de compilati IDA / D5080 A posteriori Appel d'offres Open - National 175,000.00 0.00 Annulé 2022-10-17 2022-10-22 2022-12-03 2023-01-02 2023-02-06 2023-08-05 Capacity to Rapidly detect O nvelope on et de transmission du SNI utbreaks S (Registres PMA, PCA, Cane vas RMA et fiches de surveill ance hebdomadaire) CF-REDISSE IV-025-RFQ / Ac quisition de 05 véhicule 4x4 Component 2: Strengthenin pour Renforcer la capacité lo g Emergency Planning and Passation de marc IDA / D5080 A posteriori Direct - National 250,000.00 0.00 Signé 2022-12-09 2023-02-20 2022-12-14 2023-02-20 2023-01-18 2023-03-12 2023-07-17 gistique des équipes d'interv Management Capacity to Ra hé de gré à gré ention rapide (EIR) pour les i pidly respond to Outbreaks nvestigations d'alerte et les r éponses rapides aux épidémi es CF-REDISSE IV-023-09-RFQ / Component 1: Strengthening Acquisition de Thermocycler Surveillance and Laboratory Single Stage - One E IDA / D5080 A posteriori Appel d'offres Open - National 100,000.00 0.00 Annulé 2023-09-04 2023-09-09 2023-10-21 2023-11-20 2023-12-25 2024-06-22 ABI 7500 standard pour renfo Capacity to Rapidly detect O nvelope rcer le diagnostic de Monkey utbreaks pox CF-REDISSE IV-023-15-RFQ / Acquisition des matériels de chaine de froid les secteurs d Component 2: Strengthenin e l'élevage (Frigos, congélate g Emergency Planning and Passation de marc Direct - Internation IDA / D5080 A posteriori 50,000.00 0.00 Annulé 2023-02-27 2023-03-04 2023-04-08 2023-10-05 urs, panneaux solaires, bacté Management Capacity to Ra hé de gré à gré al ries trousse d'urgence) pour l pidly respond to Outbreaks a conservation des vaccins a ntirabiques avec le concours d'UNICEF CF-REDISSE IV-023-21-RFQ / Acquisition des équipements de technologies de l'informat Component 2: Strengthenin ion et de la communication p g Emergency Planning and Single Stage - One E our les COUSP aux niveaux d IDA / D5080 A posteriori Appel d'offres Open - National 130,000.00 0.00 Annulé 2024-01-08 2024-01-13 2024-02-24 2024-03-25 2024-04-29 2024-10-26 Management Capacity to Ra nvelope écentralisés (ordinateurs, vid pidly respond to Outbreaks éo projecteur, pointeur, appa reil Konftel 300Mx 4G:téléph one de conférence) ainsi qu'e n mobiliers et fournitures CF-REDISSE IV-023-26-RFQ / Acquisition de 15 ordinateurs portables, 10 imprimantes et Component 2: Strengthenin une grande imprimante multi g Emergency Planning and Single Stage - One E IDA / D5080 A posteriori Demande de prix Open - National 38,500.00 0.00 Signé 2023-04-04 2023-05-30 2023-06-06 2023-11-26 fonction pour les Points Foca Management Capacity to Ra nvelope ux RSI des différents secteur pidly respond to Outbreaks s (Élevage/Santé Animale, Sa nté humaine; Environnement , Eau et Forêt) CF-REDISSE IV-023-04-RFQ / Component 2: Strengthenin Achat de 2 ambulances pour g Emergency Planning and Passation de marc IDA / D5080 A posteriori Direct - National 150,000.00 0.00 Signé 2023-04-03 2023-04-11 2023-04-08 2023-04-14 2023-05-13 2023-07-27 2023-11-09 le transfert des cas suspects Management Capacity to Ra hé de gré à gré au niveau des PoE pidly respond to Outbreaks CF-REDISSE IV-023-24-RFQ / Component 2: Strengthenin Acquisition de 15 motos pour g Emergency Planning and Single Stage - One E IDA / D5080 A posteriori Demande de prix Limited 62,500.00 0.00 Signé 2023-03-29 2023-11-13 2023-05-24 2023-06-02 2023-11-20 les épidémiologistes et les PF Management Capacity to Ra nvelope surveillance pidly respond to Outbreaks CF-REDISSE IV-023-01-RFQ / Acquisition et fourniture des outils de travail (ordinateur, t Component 2: Strengthenin éléphone, mobiliers et fournit g Emergency Planning and Single Stage - One E ures de bureau) Acquisition d IDA / D5080 A posteriori Demande de prix Limited 31,000.00 0.00 Annulé 2023-07-01 2023-08-26 2024-02-22 Management Capacity to Ra nvelope es kits/dispositifs de lavage d pidly respond to Outbreaks es mains aux peuples autoch tones, Acquisition des triples emballages (tout type) mobili sable (50unités) CF-REDISSE IV-023-17-RFQ / Multiplication et vulgarisation Component 2: Strengthenin du Plan stratégique multisect g Emergency Planning and Single Stage - One E En attente d' IDA / D5080 A posteriori Demande de prix Limited 12,000.00 0.00 2023-03-04 2023-04-29 2023-10-26 oriel multirisque (épidémies, Management Capacity to Ra nvelope exécution Zoonoses, risques naturels, c pidly respond to Outbreaks himiques...): 1000 copies à 7 000 FCFA l'unité CF-REDISSE IV-023-22-RFQ / Component 2: Strengthenin Acquisition des équipements g Emergency Planning and Single Stage - One E En attente d' IDA / D5080 A posteriori Demande de prix Limited 85,000.00 0.00 2023-09-30 2023-11-25 2024-05-23 et mobiliers pour le nouveau Management Capacity to Ra nvelope exécution bâtiment de la direction de la pidly respond to Outbreaks surveillance CF-REDISSE IV-023-10-RFQ / Component 2: Strengthenin Frais d'installation de Therm g Emergency Planning and Single Stage - One E IDA / D5080 A posteriori Demande de prix Limited 9,000.00 0.00 Annulé 2023-12-02 2024-01-27 2024-07-25 ocycler ABI 7500 standard po Management Capacity to Ra nvelope ur renforcer le diagnostic de pidly respond to Outbreaks Monkeypox CF-REDISSE IV-023-16-RFQ / Component 2: Strengthenin Acquisition des divers kits de g Emergency Planning and Single Stage - One E IDA / D5080 A posteriori Appel d'offres Open - National 176,000.00 0.00 Annulé 2023-07-10 2023-07-15 2023-08-26 2023-09-25 2023-10-30 2024-04-27 support, de sécurité et des é Management Capacity to Ra nvelope quipements pour les points d pidly respond to Outbreaks ’entrée désignés CF-REDISSE IV-023-13-RFQ / Component 2: Strengthenin Acquisition des équipements g Emergency Planning and Single Stage - One E En attente d' IDA / D5080 A posteriori Demande de prix Limited 70,000.00 0.00 2023-10-21 2023-12-16 2024-06-13 pour le laboratoire de scienc Management Capacity to Ra nvelope exécution es biomédicales pidly respond to Outbreaks Page 4 CF-REDISSE IV-023-14-RFQ / Acquisition des matériels de Component 2: Strengthenin contention des chiens suspec g Emergency Planning and Single Stage - One E En attente d' ts de la rage et de captures d IDA / D5080 A posteriori Demande de prix Limited 55,000.00 0.00 2023-10-21 2023-12-16 2024-06-13 Management Capacity to Ra nvelope exécution es animaux domestiques err pidly respond to Outbreaks ants (Attrapes chiens, therm omètres, EPI, …etc.) pour qu atre régions CF-REDISSE IV-023-03-RFB / Component 1: Strengthening Open - Internationa Single Stage - One E Acquisition des doses de vac IDA / D5080 Surveillance and Laboratory A posteriori Appel d'offres 667,000.00 0.00 Signé 2023-08-28 2023-10-06 2023-09-02 2023-10-11 2023-10-14 2023-11-20 2023-11-13 2023-12-28 2023-12-18 2024-02-02 2024-06-15 l nvelope cins antirabiques canines Capacity to Rapidly detect O utbreaks CF-REDISSE IV-023-05-RFQ / Component 2: Strengthenin Acquisition et la distribution g Emergency Planning and Single Stage - One E En attente d' IDA / D5080 A posteriori Appel d'offres Open - National 228,000.00 0.00 2023-11-27 2023-12-02 2024-01-13 2024-02-12 2024-03-18 2024-09-14 des équipements/réactifs/con Management Capacity to Ra nvelope exécution sommables de laboratoire pidly respond to Outbreaks CF-REDISSE IV-108-RFQ / Ac quisition des incinérateurs et Component 1: Strengthening des outils de collecte des déc Surveillance and Laboratory Open - Internationa Single Stage - One E IDA / D5080 A posteriori Appel d'offres 250,000.00 0.00 Annulé 2023-12-07 2023-12-12 2024-01-23 2024-02-22 2024-03-28 2024-09-24 hets biomédicaux (sacs à po Capacity to Rapidly detect O l nvelope ubelle de 20L, 30L et 50 L, ro utbreaks uge et noir, poubelles à péda le 30 L et 50L pour les FOSAS ) CF-REDISSE IV-023-07-RFQ / Component 1: Strengthening Acquisition des équipements Surveillance and Laboratory Single Stage - One E En attente d' pour le laboratoire d'entomo IDA / D5080 A posteriori Demande de prix Limited 50,000.00 0.00 2023-12-10 2024-02-04 2024-08-02 Capacity to Rapidly detect O nvelope exécution logie médicale du LNBCSP (I utbreaks mmobiliers, réactifs et outils informatiques….). CF-REDISSE IV-023-20-CS / A Component 2: Strengthenin cquisition des matériels de c g Emergency Planning and Single Stage - One E IDA / D5080 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2023-12-16 2024-02-10 2024-08-08 haine de froid pour la conser Management Capacity to Ra nvelope vation des vaccins antirabiqu pidly respond to Outbreaks es. CF-115-REDISSE IV - RFB / A cquisition des équipements/r Component 1: Strengthening éactifs/consommables de lab Surveillance and Laboratory Open - Internationa Single Stage - One E En attente d' oratoire de microbiologie ali IDA / D5080 A posteriori Appel d'offres 886,000.00 0.00 2024-01-29 2024-02-03 2024-03-16 2024-04-15 2024-05-20 2024-11-16 Capacity to Rapidly detect O l nvelope exécution mentaire , et assurer l'achat utbreaks et la distribution des équipe ments et autres ( panneaux s olaires , chaines de froid , mi croscope). CF-REDISSE IV-023-038-RFQ Component 1: Strengthening Single Stage - One E En attente d' / Achats équipements et mob IDA / D5080 Surveillance and Laboratory A posteriori Demande de prix Limited - National 68,000.00 0.00 2024-05-05 2024-06-30 2024-12-27 nvelope exécution iliers pour le laboratoire Nati Capacity to Rapidly detect O onal utbreaks CF-REDISSE IV-023-039-RFQ / Achat des kits de sécurité d Component 2: Strengthenin ’équipements de Protection I g Emergency Planning and Single Stage - One E En cours d'ex ndividuelle mobilisable en ca IDA / D5080 A posteriori Demande de prix Limited - National 87,000.00 0.00 2024-06-09 2024-07-15 2024-08-02 2024-09-02 Management Capacity to Ra nvelope écution s d'urgence (100 unités) et le pidly respond to Outbreaks s triples emballages (tout typ e) mobilisable en cas d'urgen ce (50 unités) CF-REDISSE IV-023-040-RFQ / Achat des équipements info Component 2: Strengthenin rmatique pour les points d’en g Emergency Planning and Single Stage - One E En cours d'ex IDA / D5080 A posteriori Demande de prix Limited - National 70,000.00 0.00 2024-05-27 2024-07-15 2024-07-22 2024-08-20 trée désignés frontaliers et le Management Capacity to Ra nvelope écution personnel santé nouvellemen pidly respond to Outbreaks t recrutés et les accessoires pour les Aires Protégées Component 2: Strengthenin CF-REDISSE IV-023-041-RFQ g Emergency Planning and Single Stage - One E En attente d' / Achat de fournitures de bur IDA / D5080 A posteriori Demande de prix Limited - National 30,000.00 0.00 2024-04-30 2024-06-25 2024-07-24 Management Capacity to Ra nvelope exécution eau et ancres pidly respond to Outbreaks CF-REDISSE IV -023-041-RFQ Component 2: Strengthenin / Reprographie des outils de g Emergency Planning and Single Stage - One E En attente d' IDA / D5080 A posteriori Demande de prix Limited - National 18,000.00 0.00 2024-05-30 2024-07-25 2024-08-23 collecte des données de la su Management Capacity to Ra nvelope exécution rveillance intégrée des mala pidly respond to Outbreaks dies et de riposte CF-REDISSE IV-023-05-RFB / Component 2: Strengthenin Acquisition des matériels de g Emergency Planning and Single Stage - One E En cours d'ex IDA / D5080 A posteriori Appel d'offres Open - National 135,000.00 0.00 2024-08-02 2024-08-07 2024-08-07 2024-08-09 2024-09-18 2024-10-18 2024-11-22 2025-05-21 chaine de froid pour les secte Management Capacity to Ra nvelope écution urs de l'élevage pidly respond to Outbreaks Component 2: Strengthenin CF-REDISSE IV-023-04-RFB / g Emergency Planning and Single Stage - One E En attente d' Achat des automates antibio IDA / D5080 A posteriori Appel d'offres Open - National 236,000.00 0.00 2024-09-30 2024-10-05 2024-11-16 2024-12-16 2025-01-20 2025-07-19 Management Capacity to Ra nvelope exécution gramme VITEK COMPACT 2 pidly respond to Outbreaks NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF-REDISSE IV-023-10-CS / T Component 2: Strengthenin ransport et installation des in g Emergency Planning and Single Stage - One E IDA / D5080 A posteriori Demande de prix Limited 45,000.00 0.00 Annulé 2023-09-09 2023-11-04 2024-05-02 cinérateurs au niveau des dis Management Capacity to Ra nvelope tricts pidly respond to Outbreaks CF-REDISSE IV-023-09-CS / Component 2: Strengthenin Maintenance des équipement g Emergency Planning and Single Stage - One E IDA / D5080 A posteriori Demande de prix Limited 60,000.00 0.00 Annulé 2023-06-24 2023-08-19 2024-02-15 s de laboratoires humains et Management Capacity to Ra nvelope vétérinaires avec une structu pidly respond to Outbreaks re qualifiée CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF-CAR-MSPP-CTN-153686-C S-CQS / Recrutement d'une fi Component 4: Institutional C rme pour la mise en œuvre d Sélection fondée s apacity Building, Project Ma es procédures standardisées IDA / 64990 A posteriori ur les qualification Open - National 20,000.00 0.00 Annulé 2020-04-20 2020-05-11 2020-06-24 2020-07-24 2020-08-28 2021-02-24 nagement, Coordination and pour la coordination des sect s des consultants Advocacy eurs y compris les autorités e n charge de la sécurité et cel le de la santé publique. Page 5 CF-CAR-MSPP-CTN-153720-C Component 2: Strengthenin Sélection fondée s S-CQS / Recrutement des ON g Emergency Planning and IDA / 64990 A posteriori ur les qualification Limited 60,000.00 0.00 Annulé 2020-07-20 2020-08-03 2020-09-02 2020-10-07 2021-04-05 G pour la sensibilisation sur l Management Capacity to Ra s des consultants a surveillance à base commu pidly respond to Outbreaks nautaire CF-CAR-MSPP-CTN-153698-C S-CQS / Recrutement d'une O Component 4: Institutional C NG pour élaborer et mettre e Sélection fondée s apacity Building, Project Ma n œuvre un plan de renforce IDA / 64990 A posteriori ur les qualification Limited 150,000.00 0.00 Annulé 2020-06-15 2020-06-29 2020-07-29 2020-09-02 2021-03-01 nagement, Coordination and ment de capacité des acteur s des consultants Advocacy s de la communication préala blement cartographiés selon l’approche :une seule santé CF-CAR-MSPP-CTN-151947-C S-CQS / Recrutement d' une f irme pour concevoir un plan Sélection fondée s Component 3: Public Health Open - Internationa de formation intégrant le vol IDA / 64990 A posteriori ur les qualification 150,000.00 0.00 Annulé 2020-10-15 2020-11-05 2020-12-19 2021-01-18 2021-02-22 2021-08-21 Workforce Development l et épidémiologique et intégr s des consultants er à la FACSS/ISDR la formati on des épidémiologistes de t errain CF-CAR-MSPP-CTN-153724-C Component 2: Strengthenin Sélection fondée s S-CQS / Recrutement d'une fi g Emergency Planning and IDA / 64990 A posteriori ur les qualification Open - National 50,000.00 0.00 Annulé 2021-01-25 2021-02-15 2021-03-31 2021-04-30 2021-06-04 2021-12-01 rme pour soutenir les évaluat Management Capacity to Ra s des consultants ions des JEE et OIE/PVS pidly respond to Outbreaks CF-CAR-MSPP-CTN-151951-C S-INDV / Recrutement d'une f irme pour élaborer et mettre Sélection fondée s Component 3: Public Health en œuvre un plan national m IDA / 64990 A posteriori ur les qualification Limited 40,000.00 0.00 Annulé 2020-09-15 2020-09-29 2020-10-29 2020-12-03 2021-06-01 Workforce Development ultisectoriel et multirisque de s des consultants préparation et d’action en ca s d’urgence de santé publiqu e. CF-CAR-MSPP-CTN-151942-C S-CQS / Recrutement d’une O Component 2: Strengthenin Sélection fondée s NG en vue de l’implication du g Emergency Planning and Open - Internationa IDA / 64990 A posteriori ur les qualification 30,000.00 0.00 Annulé 2020-10-01 2020-10-22 2020-12-05 2021-01-04 2021-02-08 2021-08-07 secteur privé dans la surveill Management Capacity to Ra l s des consultants ance épidémiologique des m pidly respond to Outbreaks aladies humaines et animale s CS-SENI-REDISS IV-161-INDV / Recrutement d'un consultan Component 1: Strengthening t International pour l' organis Surveillance and Laboratory Sélection au moin Open - Internationa ation des sessions et la Contr IDA / D5080 A posteriori 35,000.00 0.00 Annulé 2022-10-18 2022-11-08 2022-12-22 2023-01-19 2023-02-18 2023-03-25 2023-04-29 2023-10-26 Capacity to Rapidly detect O dre coût l ibution aux renforcements de utbreaks s capacités des des cadres d u MSP en Management et Le adersship (Coaching) CF-REDISSE IV-00-07-CS-IND / Recrutement d'une firme po Component 1: Strengthening Sélection fondée s ur effectuer un Etat des lieux Surveillance and Laboratory IDA / D5080 A posteriori ur les qualification Limited 200,000.00 0.00 Signé 2022-11-04 2022-12-05 2022-11-18 2023-08-11 2022-12-18 2023-10-24 2023-01-22 2023-10-27 2023-07-21 du réseau de laboratoires da Capacity to Rapidly detect O s des consultants ns le cadre "One Health" (car utbreaks tographie, fonctionnalité, ...) CF-REDISSE IV-023-02-CD / Component 2: Strengthenin Recrutement un consultant n Sélection fondée s g Emergency Planning and ational pour le suivi et contrô IDA / D5080 A posteriori ur les qualification Open - National 15,000.00 0.00 Annulé 2023-02-13 2023-03-06 2023-04-19 2023-05-19 2023-06-23 2023-12-20 Management Capacity to Ra le des travaux de réhabilitati s des consultants pidly respond to Outbreaks on du Point d'entre de Beloko CF- SENI - REDISSE IV - 127 Component 1: Strengthening – CS / Support technique equi Surveillance and Laboratory Sélection au moin pe NOVEL-T (contrat avec un IDA / D5080 A posteriori Open - National 21,000.00 0.00 Annulé 2022-11-07 2022-11-28 2023-01-11 2023-02-08 2023-03-10 2023-04-14 2023-05-19 2023-11-15 Capacity to Rapidly detect O dre coût prestataire) - Technical supp utbreaks ort or help desk services CF-SENI-REDISSE IV - 127-CS Component 1: Strengthening Sélection au moin / Support technique équipe N IDA / D5080 Surveillance and Laboratory A posteriori Open - National 21,000.00 0.00 Annulé 2022-10-10 2022-10-31 2022-12-14 2023-01-11 2023-02-10 2023-03-17 2023-04-21 2023-10-18 dre coût OVEL-T (contrat avec un pres Capacity to Rapidly detect O tataire) utbreaks CF-REDISSE IV-023-05-CS / R Component 1: Strengthening ecrutement d'un consultant i Sélection fondée s Surveillance and Laboratory nternational pour Élaborer un IDA / D5080 A posteriori ur les qualification Limited 20,000.00 0.00 Annulé 2023-07-31 2023-08-14 2023-09-13 2023-10-18 2024-04-15 Capacity to Rapidly detect O outil d’évaluation de la qualit s des consultants utbreaks é des données selon les nor mes. CF-REDISSE IV-023-06-CS / R Component 4: Institutional C ecrutement d'un consultant i Sélection fondée s apacity Building, Project Ma nternationale pour l'élaborat IDA / D5080 A posteriori ur les qualification Limited 17,000.00 0.00 Signé 2023-07-17 2023-09-26 2023-07-31 2023-09-26 2023-08-30 2023-10-26 2023-10-04 2023-11-10 2024-04-01 nagement, Coordination and ion de la loi portant exercice s des consultants Advocacy de la biologie médicale en Ce ntrafrique CF-REDISSE IV-023-01-CS-IN D / Recrutement d'un consult ant international ou appui te Component 1: Strengthening Sélection fondée s chnique de l'OMS pour établir Surveillance and Laboratory IDA / D5080 A posteriori ur les qualification Limited 15,000.00 0.00 Annulé 2023-06-26 2023-07-10 2023-08-09 2023-09-13 2024-03-11 des termes de référence éno Capacity to Rapidly detect O s des consultants nçant le rôle et les responsab utbreaks ilités du PFN du RSI et assure r la formation de l'équipe mul tisectorielle du RSI CF-REDISSE IV-023-13-CS-IN D / Recrutements d'un consul tants national et national pou Component 2: Strengthenin Sélection fondée s r l'Appui à l'élaboration du co g Emergency Planning and IDA / D5080 A posteriori ur les qualification Limited 15,000.00 0.00 Annulé 2023-08-07 2023-08-21 2023-09-20 2023-10-25 2024-04-22 de de la santé publique, ateli Management Capacity to Ra s des consultants er de validation technique, e pidly respond to Outbreaks xamen par la commission de s textes, multiplication et dis sémination de la loi promulg uée CF-REDISSE IV-023-026-CS / Component 4: Institutional C L’audit externe des états fina apacity Building, Project Ma Sélection au moin Open - Internationa IDA / D5080 A posteriori 40,000.00 0.00 Signé 2024-06-10 2024-06-11 2024-07-01 2024-08-06 2024-08-14 2024-06-18 2024-09-11 2024-07-03 2024-10-11 2024-07-03 2024-11-15 2024-07-05 2024-12-20 2024-07-15 2025-06-18 nciers des exercices 2023, 2 nagement, Coordination and dre coût l 024 et la clôture du Projet RE Advocacy DISSE IV INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 6 CF-CAR-MSPP-CTN-151851-C Component 4: Institutional C S-INDV / Recrutement d'un S apacity Building, Project Ma IDA / D5080 A posteriori Individuel Open 30,600.00 2,349.37 Signé 2021-01-20 2021-03-02 2021-03-10 2021-09-03 2021-03-31 2021-09-03 2021-05-05 2021-09-12 2021-11-01 pécialiste en Passation des M nagement, Coordination and archés au niveau national Advocacy CF-CAR-MSPP-212336-CS-IN Component 4: Institutional C En cours d'exame DV / Recrutement d'un 2ème IDA / D5080 apacity Building, Project Ma A posteriori Individuel Open 30,000.00 0.00 2021-01-20 2021-03-03 2021-03-10 2021-03-31 2021-05-05 2021-11-01 n comptable pour le Projet SEN nagement, Coordination and I/REDISSE Advocacy CF-CAR-MSPP-212338-CS-IN Component 4: Institutional C DV / Recrutement d'un logisti IDA / D5080 apacity Building, Project Ma A posteriori Individuel Open 25,000.00 0.00 Annulé 2021-01-25 2021-04-17 2021-03-15 2021-04-05 2021-05-10 2021-11-06 cien du Projet SENI/REDISSE nagement, Coordination and Advocacy CF-REDISSE IV-001-CS-IND / Component 2: Strengthenin Recrutement d'un Consultant g Emergency Planning and En cours d'exame pour la révision et validation IDA / D5080 A posteriori Individuel Limited 18,000.00 0.00 2021-03-15 2021-09-30 2021-03-20 2021-04-10 2021-05-15 2021-11-11 Management Capacity to Ra n du guide de la Surveillance In pidly respond to Outbreaks tégrée des Maladies et de Ré ponses (SIMR) CF-CAR-MSPP-CTN-151863-C Component 4: Institutional C S-INDV / Recrutement d'un R IDA / 64990 apacity Building, Project Ma A posteriori Individuel Open 168,000.00 0.00 Annulé 2020-02-01 2020-03-21 2020-04-11 2020-05-16 2020-11-12 AF INTERNATIONAL REDISSE nagement, Coordination and IV Advocacy CF-CAR-MSPP-CTN-151848-C S-INDV / Recrutement d’un CI et un CN pour élaborer et m Component 4: Institutional C ettre en œuvre selon l’appro apacity Building, Project Ma IDA / D5160 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-06-01 2020-07-20 2020-08-10 2020-09-14 2021-03-13 che :Un seul monde, Une seu nagement, Coordination and le santé, un plan d’interventi Advocacy on nationale pour les urgenc es de santé publique survena nt aux points d’entrée en ver tu du RSI CF-CAR-MSPP-CTN-151950-C S-INDV / Recrutement d'un c Component 2: Strengthenin onsultant national pour élabo g Emergency Planning and IDA / 64990 A posteriori Individuel Open 25,000.00 0.00 Annulé 2020-07-15 2020-09-02 2020-09-23 2020-10-28 2021-04-26 ration, validation et producti Management Capacity to Ra on de la stratégie nationale p pidly respond to Outbreaks our les urgences en matière de santé publique. CF-CAR-MSPP-CTN-204402-C S-CDS / Recrutement d'un bu reau d'études sous l'approch Component 1: Strengthening e d'entente directe pour le co Sélection de cons Surveillance and Laboratory ntrôle des travaux de réhabili IDA / 64990 A posteriori ultants par entent Direct 70,000.00 0.00 Annulé 2020-11-16 2020-11-26 2021-01-30 2021-07-29 Capacity to Rapidly detect O tation du centre de traitemen e directe utbreaks t des épidémies de Bangui et de Moungba ainsi que la réha bilitation de l'immeuble abrit ant la Direction de Surveillan ce CF-CAR-MSPP-CTN-151847-C S-INDV / Recrutement d’un CI Component 4: Institutional C et de deux CN pour l'élabora apacity Building, Project Ma tion et la mise en œuvre d’un IDA / D5160 A posteriori Individuel Open 40,000.00 0.00 Annulé 2020-06-01 2020-07-20 2020-08-10 2020-09-14 2021-03-13 nagement, Coordination and mécanisme multisectoriel de Advocacy préparation et riposte conjoin t aux zoonoses prioritaires et élaborer un plan multi-dange r. CF-CAR-MSPP-CTN-151954-C S-INDV / Recrutement d'un c onsultant national et d’un in Component 2: Strengthenin ternational pour établir des a g Emergency Planning and ccords de coopération région IDA / 64990 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-06-01 2020-07-20 2020-08-10 2020-09-14 2021-03-13 Management Capacity to Ra aux et internationaux pour p pidly respond to Outbreaks ermettre le déploiement et la réception transfrontalière rap ide de personnels lors d’une urgence de santé publique ; CF-CAR-MSPP-CTN-151927-C S-INDV / Recrutement de deu Component 2: Strengthenin x consultants nationaux pour g Emergency Planning and IDA / 64990 A posteriori Individuel Open 10,000.00 0.00 Annulé 2020-08-15 2020-10-03 2020-10-24 2020-11-28 2021-05-27 élaborer et mettre en place u Management Capacity to Ra n plan de vaccination systém pidly respond to Outbreaks atique pour la santé animale CF-CAR-MSPP-CTN-151925-C Component 4: Institutional C S-INDV / Recrutement d'un C IDA / 64990 apacity Building, Project Ma A posteriori Individuel Open 27,000.00 0.00 Annulé 2020-02-01 2021-03-22 2020-03-21 2020-04-11 2020-05-16 2020-11-12 omptable nagement, Coordination and Advocacy CF-CAR-MSPP-CTN-151919-C Component 2: Strengthenin S-INDV / Recrutement d’un CI g Emergency Planning and et d’un CN pour l’élaboration IDA / D5160 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-08-15 2020-10-03 2020-10-24 2020-11-28 2021-05-27 Management Capacity to Ra d’une politique nationale cou pidly respond to Outbreaks vrant l’échange d’informatio ns avec les pays voisins CF-CAR-MSPP-CTN-151914-C Component 2: Strengthenin S-INDV / Recrutement d’un CI g Emergency Planning and et de 02 CN pour établir les r IDA / 64990 A posteriori Individuel Open 40,000.00 0.00 Annulé 2020-05-31 2020-07-19 2020-08-09 2020-09-13 2021-03-12 Management Capacity to Ra éseaux régionaux et internati pidly respond to Outbreaks onaux pour tester et notifier des agents pathogènes CF-CAR-MSPP-CTN-151855-C S-INDV / Sauvegarde environ Component 4: Institutional C nementale : recrutement de apacity Building, Project Ma IDA / D5160 A posteriori Individuel Open 220,000.00 0.00 Annulé 2020-12-01 2021-01-19 2021-02-09 2021-03-16 2021-09-12 02 consultants nationaux po nagement, Coordination and ur soutenir les activités de sa Advocacy uvegarde environnementale et sociale Component 2: Strengthenin CF-CAR-MSPP-CTN-151907-C g Emergency Planning and S-INDV / Recrutement d'un C IDA / 64990 A posteriori Individuel Open 108,000.00 0.00 Annulé 2020-01-02 2020-01-03 2020-02-20 2020-03-12 2020-04-16 2020-10-13 Management Capacity to Ra oordonnateur Technique pidly respond to Outbreaks CF-CAR-MSPP-CTN-151856-C S-INDV / Recrutement d’un(0 Component 1: Strengthening 1) consultant international et Surveillance and Laboratory un(01) national pour mise en IDA / D5160 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-04-30 2020-06-18 2020-07-09 2020-08-13 2021-02-09 Capacity to Rapidly detect O place un système de transpo utbreaks rt et de transfert des échanti llons dans tous les secteurs e t zones difficiles d’accès. CF-CAR-MSPP-CTN-151853-C S-INDV / Recrutement d’un CI Component 4: Institutional C et d’un consultant internatio apacity Building, Project Ma nal pour élaborer un plan nat IDA / D5160 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-07-15 2020-09-02 2020-09-23 2020-10-28 2021-04-26 nagement, Coordination and ional de communication mult Advocacy irisque et multi-niveaux selon l’esprit :Un seul monde, Une seule santé ; Page 7 CF-CAR-MSPP-CTN-151859-C Component 4: Institutional C S-INDV / Recrutement d'un S IDA / D5160 apacity Building, Project Ma A posteriori Individuel Open 14,400.00 0.00 Annulé 2020-02-01 2020-03-21 2020-04-11 2020-05-16 2020-11-12 ecrétaire nagement, Coordination and Advocacy CF-CAR-MSPP-CTN-151882-C S-INDV / Recrutement de 02 consultants nationaux pour é Component 2: Strengthenin laborer et mettre en œuvre u g Emergency Planning and n mémorandum d’entente en IDA / D5160 A posteriori Individuel Open 150,000.00 0.00 Annulé 2020-10-15 2020-12-03 2020-12-24 2021-01-28 2021-07-27 Management Capacity to Ra tre les différents acteurs impl pidly respond to Outbreaks iqués dans la gestion des da ngers menaçant la santé et l a sécurité publique pour inté grer les 4 composantes du R SI CF-CAR-MSPP-CTN-151846-C S-INDV / Recrutement d'un c Component 1: Strengthening onsultant national et d’un co Surveillance and Laboratory IDA / D5160 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-08-15 2020-10-03 2020-10-24 2020-11-28 2021-05-27 nsultant international pour él Capacity to Rapidly detect O aborer et mettre en œuvre u utbreaks n plan relatif aux moyens mé dicaux CF-CAR-MSPP-CTN-151867-C S-INDV / Recrutement de 02 consultants nationaux pour é Component 2: Strengthenin laborer et mettre en œuvre u g Emergency Planning and n mémorandum d’entente ou IDA / D5160 A posteriori Individuel Open 20,000.00 0.00 Annulé 2020-11-01 2020-12-20 2021-01-10 2021-02-14 2021-08-13 Management Capacity to Ra protocole de collaboration en pidly respond to Outbreaks tre les autorités chargées de la sécurité et les secteurs de la santé animale ,humaine et environnementale CF-CAR-MSPP-CTN-151890-C S-INDV / Recrutement d’un c onsultant national et d’un co Component 2: Strengthenin nsultant international pour él g Emergency Planning and IDA / 64980 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 aborer et mettre en œuvre le Management Capacity to Ra s plans et procédures pour l’ pidly respond to Outbreaks envoi et la réception des mo yens médicaux lors d’une urg ence de santé publique CF-CAR-MSPP-CTN-151872-C S-INDV / Recrutement d’un c onsultant national et d’un co Component 2: Strengthenin nsultant international pour d g Emergency Planning and IDA / D5160 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 évelopper une évaluation et Management Capacity to Ra des plans pour la fermeture pidly respond to Outbreaks des écoles et autres zones d e rassemblement de masse p endant une épidémie. CF-CAR-MSPP-CTN-151878-C S-INDV / Recrutement d’un CI et 02CN pour cartographier e Component 1: Strengthening t évaluer les installations de l Surveillance and Laboratory IDA / D5160 A posteriori Individuel Open 40,000.00 0.00 Annulé 2020-05-31 2020-07-19 2020-08-09 2020-09-13 2021-03-12 abo, réseaux systèmes de g Capacity to Rapidly detect O estion de l’information de lab utbreaks oratoire existants à tous les niveaux (secteurs privés et p ublics). CF-CAR-MSPP-CTN-151857-C S-INDV / Recrutement d’un c Component 4: Institutional C onsultant national et d’un co apacity Building, Project Ma nsultant international pour d IDA / D5160 A posteriori Individuel Open 40,000.00 0.00 Annulé 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 nagement, Coordination and évelopper les capacités de re Advocacy cherche opérationnelle lord d es interventions d’urgence et élaborer le manuel d’interve ntion CF-CAR-MSPP-CTN-151916-C S-INDV / Recrutement d’un c onsultant international et un Component 2: Strengthenin national pour mettre en plac g Emergency Planning and IDA / 64990 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-03-15 2020-05-03 2020-05-24 2020-06-28 2020-12-25 e et suivi du mécanisme de c Management Capacity to Ra oordination pour l’approvisio pidly respond to Outbreaks nnement en réactifs et conso mmables(santé humaine et a nimale) CF-CAR-MSPP-CTN-151870-C S-INDV / Recrutement d’un CI Component 2: Strengthenin et un CN pour évaluer ,adapt g Emergency Planning and er et mettre en œuvre avec l IDA / D5160 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-05-31 2020-07-19 2020-08-09 2020-09-13 2021-03-12 Management Capacity to Ra es pays frontaliers les accord pidly respond to Outbreaks s bilatéraux et multilatéraux de coopération favorisant la mise en œuvre du RSI CF-CAR-MSPP-CTN-222208-C Component 4: Institutional C Sélection de cons S-CDS / Recrutement d'un co apacity Building, Project Ma IDA / D5080 A posteriori ultants par entent Direct 5,000.00 0.00 Annulé 2021-03-08 2022-02-03 2021-03-18 2021-05-22 2021-11-18 nsultant pour completer les s nagement, Coordination and e directe aisies dans le logiciel TOMPR Advocacy O CF-CAR-REDISSE-CTN-22216 Component 4: Institutional C En cours d'exame 9-CS-INDV / Recrutement d'u IDA / D5080 apacity Building, Project Ma A posteriori Individuel Open 125,000.00 0.00 2021-04-15 2021-03-24 2021-06-03 2021-06-24 2021-07-29 2022-01-25 n n Consultant International Au nagement, Coordination and diteur Interne Advocacy CF-CAR-MSPP-CTN-227766-C Component 4: Institutional C S-INDV / Recrutement d'un lo IDA / D5080 apacity Building, Project Ma A posteriori Individuel Open 36,000.00 0.00 Annulé 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 gisticien du Projet SENI/REDI nagement, Coordination and SSE Advocacy CF-CAR-MSPP-CTN-204402-C S-CDS-2 / Recrutement d'un Component 2: Strengthenin Sélection de cons bureau d'études chargé de la g Emergency Planning and IDA / 64990 A posteriori ultants par entent Direct 70,000.00 0.00 Annulé 2021-03-25 2021-03-10 2021-04-04 2021-06-08 2021-12-05 surveillance des travaux de r Management Capacity to Ra e directe éhabilitation de 4 points d'en pidly respond to Outbreaks trée sur le fleuve Oubangui. CF-CAR-MSPP-CTN-246872-C Component 4: Institutional C S-INDV / Recrutement d'un R apacity Building, Project Ma IDA / D5080 A posteriori Individuel Open 135,000.00 0.00 Annulé 2021-08-05 2021-09-13 2021-09-23 2021-10-14 2021-11-18 2022-05-17 esponsable Administratif et F nagement, Coordination and inancier International pour le Advocacy Projet SENI/REDISSE CF-CAR-MSPP-CTN-246873-C Component 4: Institutional C S-INDV / Recrutement d'un S apacity Building, Project Ma En cours d'exame IDA / D5080 A posteriori Individuel Open 115,000.00 0.00 2021-08-05 2021-09-21 2021-09-23 2021-10-14 2021-11-18 2022-05-17 pécialiste en passation des m nagement, Coordination and n archés international pour le P Advocacy rojet SENI/REDISSE CF-CAR-MSPP-CTN-253660-C Component 4: Institutional C S-INDV / Recrutement d'un(e apacity Building, Project Ma ) Spécialiste en Communicati IDA / D5080 A posteriori Individuel Open 30,000.00 0.00 Annulé 2021-09-16 2022-01-21 2021-11-04 2021-11-25 2021-12-30 2022-06-28 nagement, Coordination and on au sein de la Coordination Advocacy Générale du Projet SENI-REDI SSE IV Page 8 CF-CAR-MSPP-CTN-252991-C Component 4: Institutional C S-INDV / Recrutement d'un C apacity Building, Project Ma IDA / D5080 A posteriori Individuel Open 135,000.00 0.00 Annulé 2021-09-13 2021-11-01 2021-11-22 2021-12-27 2022-06-25 ontrôleur /Auditeur Interne d nagement, Coordination and u Projet SENI-REDISSE Advocacy CF-CAR-REDISSE-CTN-22216 Component 4: Institutional C 8-CS-INDV / Recrutement d'u apacity Building, Project Ma IDA / D5080 A posteriori Individuel Limited 80,000.00 0.00 Annulé 2021-03-19 2021-03-24 2021-04-14 2021-05-19 2021-11-15 n Spécialiste en environneme nagement, Coordination and nt et en sauvegarde sociale Advocacy CF-CAR-MSPP-CTN-151936-C S-CDS / Recrutement d’un co nsultant individuel en vue de Component 2: Strengthenin la mise en place du logiciel d g Emergency Planning and IDA / D5080 A posteriori Individuel Open 100,000.00 0.00 Annulé 2021-05-25 2021-07-13 2021-08-03 2021-09-07 2022-03-06 e surveillance inter connecté Management Capacity to Ra avec le DHIS 2, WAHIS au niv pidly respond to Outbreaks eau des districts ,des directio ns régionales de la santé /éle vage et au niveau central CF-REDISSE IV-002-CS-IND / Recrutement d'un Consultant national pour l'élaboration et Component 2: Strengthenin la validation des principes dir g Emergency Planning and IDA / D5080 A posteriori Individuel Limited 17,000.00 0.00 Annulé 2021-03-22 2021-03-27 2021-04-17 2021-05-22 2021-11-18 ecteurs et des procédures op Management Capacity to Ra érationnelles standard (SOP) pidly respond to Outbreaks de la surveillance basée sur l es événements (santé humai ne et animale) CF-REDISSE IV-005-CS-IND / Recrutement d'un consultan Component 4: Institutional C t international pour le renforc apacity Building, Project Ma IDA / D5080 A posteriori Individuel Open 100,500.00 0.00 Annulé 2022-09-22 2022-11-10 2022-12-01 2023-01-05 2023-07-04 ement de capacité en surveill nagement, Coordination and ance électronique et appui a Advocacy la mise en œuvre (Elaboratio n de SOPs) CF-REDISSE IV-020-CS-IND / Recruter un consultant intern Component 1: Strengthening Sélection de cons ational pour le renforcement Surveillance and Laboratory Direct - Internation IDA / D5080 A posteriori ultants par entent 90,000.00 0.00 Signé 2022-10-07 2023-02-15 2022-10-17 2023-02-20 2022-12-21 2023-04-18 2023-06-19 de capacité en surveillance é Capacity to Rapidly detect O al e directe lectronique et appui à la mis utbreaks e en œuvre (Elaboration de S OPs) un consultant pour 6 m ois. CF-REDISSE IV-023-03-CS / S Component 2: Strengthenin Sélection de cons upport technique avec l'equi g Emergency Planning and Direct - Internation IDA / D5080 A posteriori ultants par entent 25,000.00 0.00 Signé 2023-02-27 2023-02-15 2023-03-09 2023-03-16 2023-05-13 2023-04-20 2023-11-09 pe NOVEL-T pour la mise en Management Capacity to Ra al e directe œuvre de AVADAR MD pidly respond to Outbreaks CF-REDISSE IV-023-11-CS-IN D / Recrutement d'un consult Component 4: Institutional C ant international pour le Renf apacity Building, Project Ma Open - Internationa IDA / D5080 A posteriori Individuel 25,000.00 0.00 Annulé 2023-06-05 2023-07-24 2023-08-14 2023-09-18 2024-03-16 orcement de capacités des c nagement, Coordination and l adres du MSP en Manageme Advocacy nt et Leadership (Coaching) e t organisation des sessions CF-REDISSE IV-023-13-CS / Sélection de cons Component 3: Public Health Direct - Internation En cours d'exame Mémorandum d'Entente avec IDA / D5080 A priori ultants par entent 1,290,500.00 0.00 2023-02-20 2023-03-21 2023-03-02 2023-04-18 2023-05-06 2023-12-12 2023-11-02 Workforce Development al n AFENET pour la formation FE e directe TP CF-REDISSE IV-023-10-CS-IN Component 2: Strengthenin D / Recrutement d'un consult g Emergency Planning and En attente d'exéc ant national pour le contrôle IDA / D5080 A posteriori Individuel Limited 23,000.00 0.00 2023-03-06 2023-03-11 2023-04-01 2023-05-06 2023-11-02 Management Capacity to Ra ution de la qualité des travaux de l pidly respond to Outbreaks 'extension du COUSP pour la direction de la surveillance CF-REDISSE IV-023-12-CS-IN D / Recrutements d'un consul tants international et nationa Component 4: Institutional C l pour l'Appui à l'élaboration apacity Building, Project Ma Open - Internationa IDA / D5080 A posteriori Individuel 35,000.00 0.00 Annulé 2023-07-10 2023-08-28 2023-09-18 2023-10-23 2024-04-20 du code de la santé publique, nagement, Coordination and l atelier de validation techniqu Advocacy e, examen par la commission des textes, multiplication et dissémination de la loi promu lguée CF-REDISSE IV-023-08-CS / R ecrutement d'un consultant n Component 1: Strengthening ational avec un profil biologis Surveillance and Laboratory IDA / D5080 A posteriori Individuel Limited 7,500.00 0.00 Signé 2023-05-29 2023-07-28 2023-06-03 2023-09-26 2023-06-24 2023-10-26 2023-07-29 2023-11-10 2024-01-25 te pour l'élaboration de la loi Capacity to Rapidly detect O portant exercice de la biologi utbreaks e médicale en Centrafrique CF-REDISSE IV-023-17-CS / R Component 2: Strengthenin ecrutement d'un consultant n g Emergency Planning and ational avec profil juridique p IDA / D5080 A posteriori Individuel Limited 7,500.00 0.00 Signé 2023-05-29 2023-07-26 2023-06-03 2023-09-26 2023-06-24 2023-10-26 2023-07-29 2023-11-10 2024-01-25 Management Capacity to Ra our l'élaboration de la loi port pidly respond to Outbreaks ant exercice de la biologie m édicale en Centrafrique CF-REDISSE IV-023-18-CS / R Component 1: Strengthening ecrutement de 4 Entomologis Surveillance and Laboratory IDA / D5080 A posteriori Individuel Limited 68,000.00 0.00 Signé 2023-10-16 2023-10-13 2023-10-21 2023-10-27 2023-11-11 2023-12-20 2023-12-16 2024-01-01 2024-06-13 te pour renforcer l'équipe de Capacity to Rapidly detect O surveillance au niveau nation utbreaks al CF-REDISSE IV-023-19-CS / R ecrutement d'un consultant n ational en appui technique p Component 1: Strengthening our l'élaboration des TDRs én Surveillance and Laboratory IDA / D5080 A posteriori Individuel Limited 5,000.00 0.00 Annulé 2023-10-23 2023-10-13 2023-10-28 2023-11-18 2023-12-23 2024-06-20 onçant le rôle et les responsa Capacity to Rapidly detect O bilités du point focal du règle utbreaks ment sanitaire international et assurer une formation a l’ équipe multisectoriel de la R CA. CF-REDISSE IV-023-22-CS / R Component 1: Strengthening En attente d'exéc ecrutement d'un Assistant P IDA / D5080 Surveillance and Laboratory A posteriori Individuel Open - National 28,340.00 0.00 2023-12-15 2024-02-02 2024-02-23 2024-03-29 2024-09-25 ution F REDISSE IV Capacity to Rapidly detect O utbreaks CF-REDISSE IV-023-023-CS / Component 1: Strengthening En attente d'exéc Recrutement de 2 Data Mana IDA / D5080 Surveillance and Laboratory A posteriori Individuel Limited - National 25,000.00 0.00 2024-06-09 2024-06-14 2024-07-05 2024-08-09 2025-02-05 ution gers pour le Point d'entrée d Capacity to Rapidly detect O e l’Aéroport utbreaks CF-REDISSE IV -023-024-DS / Component 1: Strengthening La migration des données his Sélection de cons Surveillance and Laboratory Direct - Internation toriques (programmes et proj IDA / D5080 A posteriori ultants par entent 154,000.00 0.00 Signé 2024-04-30 2024-04-14 2024-05-10 2024-04-16 2024-07-14 2024-04-24 2025-01-10 Capacity to Rapidly detect O al ets du MSP) du système nati e directe utbreaks onal d'information sanitaire ( SNIS) dans le DHIS 2 Page 9 CF-REDISSE IV-023-024-CS / RECRUTEMENT D’UN CONSU Component 2: Strengthenin LTANT NATIONAL ET INTERN g Emergency Planning and En cours d'exécut IDA / D5080 A posteriori Individuel Limited - National 40,000.00 0.00 2024-04-30 2024-04-24 2024-05-05 2024-04-29 2024-05-26 2024-08-09 2024-06-30 2024-12-27 ATIONAL POUR L’ÉLABORATI Management Capacity to Ra ion ON DU PLAN DE COMMUNICA pidly respond to Outbreaks TION MULTIRISQUES EN REP UBLIQUE CENTRAFRICAINE CF-REDISSE IV-023-025-CS / Component 2: Strengthenin RECRUTEMENT D'UN CONSUL g Emergency Planning and En cours d'exécut IDA / D5080 A posteriori Individuel Limited - National 5,000.00 0.00 2024-04-30 2024-04-24 2024-05-05 2024-04-29 2024-05-26 2024-08-09 2024-06-30 2024-12-27 TANT NATIONAL POUR LA CA Management Capacity to Ra ion RTOGRAPHIE ET RISQUES CH pidly respond to Outbreaks IMIQUES CF-REDISSE IV -023-025-DS / Component 4: Institutional C Sélection de cons Régularisation de l’audit exte apacity Building, Project Ma En cours d'exécut IDA / D5080 A posteriori ultants par entent Direct - National 23,640.00 0.00 2024-06-10 2024-06-11 2024-06-20 2024-06-20 2024-08-24 2025-02-20 rne du projet REDISSE IV des nagement, Coordination and ion e directe exercices 2021 et 2022 Advocacy CF-REDISSE IV-023-027-CS / Formation de 4 Entomologist Sélection de cons Component 3: Public Health Direct - Internation es en Entomologies Médicale IDA / D5080 A posteriori ultants par entent 72,000.00 0.00 Signé 2024-06-14 2024-06-28 2024-06-24 2024-06-28 2024-08-28 2024-06-07 2025-02-24 Workforce Development al a l’Institut National de Reche e directe rche Biomédicale de Kinshas a, RDC. CF-REDISSE IV-023-028-CS / Formation de 10 techniciens Sélection de cons de laboratoire en maintenanc Component 3: Public Health Direct - Internation En cours d'exécut IDA / D5080 A posteriori ultants par entent 83,340.00 0.00 2024-06-18 2024-06-28 2024-06-28 2024-06-28 2024-09-01 2025-02-28 e des équipements biomédic Workforce Development al ion e directe aux à Cotonou au Bénin a tra vers la Fondation Merieux CF-REDISSE IV-023-029-CS / Component 2: Strengthenin Sélection de cons Support technique avec l’équ g Emergency Planning and Direct - Internation En cours d'exécut IDA / D5080 A posteriori ultants par entent 15,500.00 0.00 2024-08-09 2024-07-29 2024-08-19 2024-08-01 2024-10-23 2025-04-21 ipe NOVEL-T pour la mise en Management Capacity to Ra al ion e directe œuvre de AVADAR Multi Dise pidly respond to Outbreaks ase progam Page 10