PROCUREMENT PLAN Project information: Federal Republic of Ethiopia, The Republic of Madagascar, The Intergovernmental Authority of Development (IGAD), the Centre for Coordination of Agricultural Research and Development for Southern Africa (CCARDESA) Food System Resilience Program for Eastern and Southern Africa Phase 1 P178566 Project Implementation agency: Ministry of Agriculture (Ethiopia) Date of the Procurement Plan: October 13, 2022 Period covered by this Procurement Plan: October 2022 to June 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Proclamation No. 649/2009, The Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1)Ensure bidding opportunities are open to all contractors/Suppliers and service providers When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods Not Applicable Works Not Applicable Other Relevant Procurement Information. The project envisages procurement activities that will be implemented through CDD arrangement following the CDD Procurement manual which will be prepared by the client agreed with the Bank . PROCUREMENT Eastern and Southern Africa : Food Systems Resilience Program for Eastern and Southern Africa PLAN General Information Country: Eastern and Southern Africa 2023-03-07 Bank’s Approval Date of the Original Procurement Plan: 2024-08-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178566 GPN Date: 2022-10-21 Project Name: Food Systems Resilience Program for Eastern and Southern Africa Loan / Credit No: IDA / 71570, IDA / E0830, IDA / 71560 PADAP PROJECT UNIT MANAGEMENT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned T07-24/CN / Travaux de réha bilitation des périmètres de: LOT 1: Ranomainty Commun e Rurale Mahatsara, District Supporting the Sustainable Edital de Licitação de Brickaville, Région Atsina Development of Natural Res Single Stage - One E - Obras Direito Ci En attente d 2026-01-1 IDA / 71570 A posteriori Appel d'offres Open - National 6,847,500.00 0.00 2025-04-02 2025-04-07 2025-05-19 2025-06-18 2025-07-23 nana ources for Resilient Agricultu nvelope vil Francês (Franc 'exécution 9 LOT 2: Antsakoamileka Com ral Landscapes ês) SPD mune Rurale d’Antsakoamile ka, District de Soalala, Régio n Boeny LOT 3: Andromba Amont Co mmune Rura T 01-24/CN / Travaux de réh Demande d'offres abilitation des bureaux du FS Single Stage - One E - DTPM Petits trav En attente d 2025-09-2 IDA / 71570 Project Management A posteriori Appel d'offres Open - National 225,000.00 0.00 2025-02-03 2025-02-08 2025-03-22 2025-04-21 2025-05-26 RP: LOT1 UGP - LOT 2 ATSINA nvelope aux - (Processus à 'exécution 3 NANA - LOT 3 ITASY - LOT 4 F 1 enveloppe) ITOVINANY GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual F 01-23/CN / Acquisition, inst Passation de marc allation, maintenance, format IDA / 71570 Project Management A posteriori Direct - National 50,000.00 0.00 Signé 2023-09-28 2023-09-20 2023-09-30 2023-09-20 2023-10-12 2023-12-19 2026-09-26 hé de gré à gré ion et hébergement du logici el TOM²PRO F 02-23/CN / Acquisition de Single Stage - One E IDA / 71570 Project Management A posteriori Appel d'offres Open - National 400,000.00 0.00 Signé 2023-10-31 2024-01-10 2023-11-05 2024-01-10 2023-12-05 2024-02-09 2024-01-04 2024-03-14 2024-01-11 2024-03-11 5 véhicules tout terrain nvelope F 08-24/CN / Acquisition Équi pements informatiques: Lot 1 Single Stage - One E En attente d' : Ordinateurs portables et or IDA / 71570 Project Management A posteriori Appel d'offres Open - National 475,000.00 0.00 2024-05-14 2024-05-15 2024-06-14 2024-06-15 2024-07-09 2024-08-08 nvelope exécution dinateurs de bureau; Lot 2: I mprimantes mutifonctions (y compris MINAE) F 09-24/CN / Acquisition de Single Stage - One E En attente d' IDA / 71570 Project Management A posteriori Appel d'offres Open - National 215,000.00 0.00 2024-05-14 2024-05-17 2024-06-16 2024-06-26 2024-07-25 2024-09-23 Mobiliers et matériels de bur nvelope exécution eau F 11-24/CN / Acquisition de F Single Stage - One E En attente d' IDA / 71570 Project Management A posteriori Appel d'offres Open - National 200,000.00 0.00 2024-05-15 2024-05-18 2024-06-17 2024-06-27 2024-07-21 2024-08-21 ournitures de bureau nvelope exécution F 21-24/CN / Acquisitions ma Single Stage - One E En attente d' tériels électroniques et acces IDA / 71570 Project Management A posteriori Demande de prix Open - National 75,000.00 0.00 2024-05-19 2024-07-03 2024-08-07 nvelope exécution soires informatiques F 10-24/CN / Acquisition de c Single Stage - One E En attente d' IDA / 71570 Project Management A posteriori Appel d'offres Open - National 150,000.00 0.00 2024-08-01 2024-08-06 2024-09-05 2024-09-12 2024-10-06 2024-12-05 onsommables informatiques nvelope exécution F 01-24/CN / Mise en place d 'une plateforme digitaux au s ein du MINAE ( afin d'intégrer (Re-)building Resilient Agric Single Stage - One E En attente d' le système d'alerte sur la san IDA / 71570 A posteriori Demande de prix Open - National 25,000.00 0.00 2024-06-26 2024-08-21 2025-02-17 ulture Production Capacity nvelope exécution té végétale et animale, les n ormes de qualité des produit s agricoles, conseils agricoles ) (USID, DVFAR) F 12-24/CN / Acquisition de Single Stage - One E En attente d' IDA / 71570 Project Management A posteriori Demande de prix Open - National 20,000.00 0.00 2024-05-25 2024-07-20 2024-08-10 produits d'entretien nvelope exécution F 06-24/CN / Acquisition de Single Stage - One E En attente d' IDA / 71570 Project Management A posteriori Appel d'offres Open - National 995,000.00 0.00 2024-05-31 2024-06-05 2024-07-05 2024-07-20 2024-08-24 2024-12-22 11 véhicules tout terrain et d nvelope exécution e 18 motos F22-24/CN / Mise à jour du lo giciel de gestion financière et Passation de marc En attente d' IDA / 71570 Project Management A posteriori Direct - National 5,500.00 0.00 2024-08-28 2024-09-02 2024-09-08 2025-09-08 comptable TOM²PRO et ajout hé de gré à gré exécution des fonctionnalités (SET) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C 03-22/CN / Assistance tech nique pour le projet de mise (Re-)building Resilient Agric Passation de marc Direct - Internation en œuvre de cantine scolaire IDA / E0830 A priori 40,000,000.00 0.00 Signé 2023-07-20 2023-08-18 2023-07-25 2023-09-19 2023-09-18 2023-12-01 2028-08-22 ulture Production Capacity hé de gré à gré al basé sur les achats locaux - Home Grown School Feeding (HGSF) NC 09-24/CN / Achemineme (Re-)building Resilient Agric Passation de marc En cours d'ex IDA / 71570 A posteriori Direct - National 215,000.00 0.00 2024-04-23 2024-05-02 2024-04-24 2024-07-18 2024-04-28 2024-06-12 nt tracteurs ulture Production Capacity hé de gré à gré écution NC 07-24/DIA / Location bur Single Stage - One E En attente d' IDA / 71570 Project Management A posteriori Demande de prix Limited - National 45,000.00 0.00 2024-05-19 2024-07-03 2027-07-03 eau UER DIANA nvelope exécution NC 08-24/BOE / Location bur Single Stage - One E En attente d' IDA / 71570 Project Management A posteriori Demande de prix Limited - National 45,000.00 0.00 2024-05-19 2024-07-03 2024-12-30 eau UER BOENY nvelope exécution F 05-24/CN / Conception et Single Stage - One E En attente d' IDA / 71570 Project Management A posteriori Demande de prix Open - National 30,000.00 0.00 2024-07-03 2024-08-22 2025-02-18 mise en place du Site Web d nvelope exécution u FSRP Page 1 NC 06-24/CN / Financement Passation de marc En attente d' des sous-projets communaut IDA / 71570 Getting to Market A posteriori Direct - National 1,000,000.00 0.00 2024-09-20 2024-09-25 2024-10-30 2025-10-30 hé de gré à gré exécution aires et régionaux à travers l e FDA NC 10-24/CN / Prestations d' Single Stage - One E En attente d' IDA / 71570 Project Management A posteriori Appel d'offres Open - National 22,000.00 0.00 2024-07-08 2024-07-13 2024-08-12 2024-09-11 2024-10-16 2025-10-16 une Agence de Voyages nvelope exécution NC 11-24/CN / Prestations d' Single Stage - One E En attente d' IDA / 71570 Project Management A posteriori Appel d'offres Open - National 2,500.00 0.00 2024-07-11 2024-07-16 2024-08-15 2024-09-14 2024-10-19 2025-10-19 un Service traiteur nvelope exécution NC 12-24/CN / Conduite et m ise en place des activités de Supporting the Sustainable reboisement et restauration Development of Natural Res Single Stage - One E En attente d' IDA / 71570 A posteriori Appel d'offres Open - National 1,440,000.00 0.00 2024-08-09 2024-08-14 2024-09-25 2024-10-25 2024-11-29 2026-05-23 de paysage: - ources for Resilient Agricultu nvelope exécution LOT 1 UEIR DIANA - ral Landscapes LOT 2 UEIR ATSINANANA - LOT 3 UEIR FITOVINANY CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C 19-23-CN / Etude sur la sit Sélection fondée s En cours d'exécut uation de référence (Baseline IDA / 71570 Project Management A posteriori ur les qualification Open - National 40,000.00 0.00 2023-10-25 2023-10-24 2023-11-15 2023-11-09 2024-01-14 2024-02-19 2024-02-03 2024-02-23 2024-08-21 ion ) et élaboration d'un manuel s des consultants M&E C 11-23/CN / Recrutement d' un bureau d'étude pour l'étu de des CdV prioritaires du FS Sélection fondée s RP en 04 Lots: (Re-)building Resilient Agric En cours d'exécut IDA / E0830 A posteriori ur les qualification Open - National 50,000.00 0.00 2023-10-31 2024-03-19 2023-11-21 2024-01-20 2024-02-09 2024-02-29 2024-08-27 Lot 01: Filière lait ulture Production Capacity ion s des consultants Lot 02: Filière Arachide et hui le de table Lot 03: Filière Céréales Lot 04: Filière Légumineuses C 02-23/CN / Etude, C&S des travaux de réhabilitation/am énagement des P.I en 07 lots : 1-Ranomainty,CR Mahatsara Supporting the Sustainable Sélection fondée s 2-Antsakoamileka,CR Antsak Development of Natural Res Open - Internationa En cours d'exécut IDA / 71570 A priori ur la qualité et le 2,800,000.00 0.00 2023-11-02 2024-05-24 2023-12-14 2024-05-28 2024-01-10 2024-02-09 2024-03-02 2024-04-06 2024-04-26 2026-10-13 oamileka ources for Resilient Agricultu l ion coût 3-Andrombabe et Ambatomir ral Landscapes ahavavy 4-Sakavohitra,CR Anjahana 5-Sahena,CR Anjahana 6-Betsihaka 7-Secteur 3 du PI Marovoay C 05-24/CN / AUDITS EXTER Sélection au moin En cours d'exécut NES DES COMPTES DU PROJE IDA / 71570 Project Management A posteriori Open - National 30,000.00 0.00 2024-02-09 2024-04-15 2024-02-16 2024-02-16 2024-04-19 2024-03-17 2024-05-03 2024-03-24 2024-05-15 2024-04-07 2024-05-16 2024-04-30 2026-06-30 dre coût ion T- Exercices 2022-2023, 202 4 et 2025 C 08-24/CN / Actualisation d e l’étude technique, contrôle Sélection fondée s et surveillance pour les trava IDA / 71570 Getting to Market A posteriori ur les qualification Open - National 200,000.00 0.00 Annulé 2024-05-17 2024-05-22 2024-06-26 2024-07-26 2024-08-30 2025-02-26 ux de réhabilitation de la pist s des consultants e Betafo-Ambatonikolahy- Fa rihimena (28 km) C 02-24/CN / Recrutement d' un Consultant pour le renforc Sélection fondée s ement de l'accès des product (Re-)building Resilient Agric En attente d'exéc IDA / 71570 A posteriori ur les qualification Open - National 100,000.00 0.00 2024-09-03 2024-09-24 2024-10-14 2024-10-29 2024-11-19 2025-05-18 eurs et des acteurs des filièr ulture Production Capacity ution s des consultants es aux informations sur les p rix des produits agricoles sur le marché national et interna tional CI 03-24/CN / Recrutement d 'un cabinet expert en inform Sélection fondée s En attente d'exéc atique pour superviser et sou IDA / 71570 Getting to Market A posteriori ur les qualification Open - National 100,000.00 0.00 2024-05-20 2024-06-10 2024-06-30 2024-07-15 2024-08-08 2025-02-04 ution tenir l'équipe de gestion du s s des consultants ystème Zebuscan (24 mois) C 07-24/CN / Actualisation et mise à jour du Programme S Sélection fondée s En attente d'exéc ectoriel Agriculture, Elevage IDA / 71570 Project Management A posteriori ur les qualification Open - National 60,000.00 0.00 2024-07-08 2024-07-13 2024-08-17 2024-09-01 2024-09-25 2025-03-24 ution et Pêche et du Plan National s des consultants d'Investissement Agricole (PS AEP / PNIA) Sélection fondée s C 01-25/CN / Revue à mi-par En attente d'exéc IDA / 71570 Project Management A posteriori ur les qualification Open - National 50,000.00 0.00 2025-05-05 2025-05-10 2025-06-14 2025-07-14 2025-08-07 2026-02-03 cours ution s des consultants C 06-24/CN / Recrutement d' Sélection fondée s En attente d'exéc une firme pour l'Evaluation a IDA / 71570 Project Management A posteriori ur les qualification Open - National 15,000.00 0.00 2024-08-19 2024-09-09 2024-10-23 2024-11-13 2024-12-18 2025-04-17 ution nnuelle des indicateurs s des consultants C 03-24/CN / Etude sur la mi Supporting the Sustainable Sélection fondée s En attente d'exéc se en place de la certification IDA / 71570 Development of Natural Res A posteriori ur les qualification Open - National 50,000.00 0.00 2024-06-17 2024-06-22 2024-07-27 2024-08-26 2024-09-19 2025-03-18 ution carbone des activités de rebo ources for Resilient Agricultu s des consultants isement ral Landscapes C 09-24/CN / Études de Réha bilitation des Bureaux du FSR Sélection fondée s P : LOT1 - Bureau UGP, LOT2 En cours d'exécut IDA / 71570 Project Management A posteriori ur les qualification Open - National 25,000.00 0.00 2024-07-31 2024-08-21 2024-10-04 2024-11-03 2024-12-08 2025-03-08 - Bureau UEIR Atsinanana, LO ion s des consultants T3 - Bureau UEIR ITASY, LOT 4 Bureau UEIR FITOVINAGNY INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI 04-22/CN / Recrutement d IDA / 71570 Project Management A posteriori Individuel Open - National 18,000.00 0.00 Annulé 2023-03-31 2023-05-19 2023-06-09 2023-07-14 2024-01-10 'un Assistant Technique pour PRSA CI 02-23/CN / Recrutement d IDA / 71570 Project Management A posteriori Individuel Open - National 54,000.00 0.00 Signé 2023-04-28 2023-04-05 2023-06-16 2023-08-15 2023-07-07 2023-08-28 2023-08-11 2023-12-28 2026-08-10 ’un Responsable Financier CI 01-23/CN / Recrutement d IDA / 71570 Project Management A posteriori Individuel Open - National 66,000.00 0.00 Signé 2023-04-28 2023-04-05 2023-06-16 2023-05-30 2023-07-07 2023-05-31 2023-08-11 2023-06-04 2026-08-10 ’un Adjoint au Coordonnateur National Page 2 CI 03-23/CN / Recrutement d IDA / 71570 Project Management A priori Individuel Open - National 54,000.00 0.00 Signé 2023-04-28 2023-04-13 2023-06-16 2023-10-18 2023-07-07 2023-10-27 2023-08-11 2023-11-15 2026-08-10 ’un Responsable Passation d es Marchés CI 05-23/CN / Recrutement d 'un spécialiste en social au ni IDA / 71570 Project Management A posteriori Individuel Open - National 54,000.00 0.00 Signé 2023-04-11 2023-04-07 2023-05-30 2023-12-12 2023-06-20 2023-12-14 2023-07-25 2024-03-11 2026-07-24 veau de l'UGP CI 06-23/CN / Recrutement d 'un spécialiste en VBG au niv IDA / 71570 Project Management A posteriori Individuel Open - National 54,000.00 0.00 Annulé 2023-04-11 2023-04-07 2023-05-30 2023-06-20 2023-07-25 2026-07-24 eau de l'UGP CI 07-23/CN / Recrutement d En cours d'exécut 'un spécialiste sauvegarde e IDA / 71570 Project Management A posteriori Individuel Open - National 54,000.00 0.00 2023-04-11 2023-04-07 2023-05-30 2023-06-20 2023-07-25 2026-07-24 ion nvironnement pour l'UGP CI 04-23/CN / Recrutement d IDA / 71570 Project Management A posteriori Individuel Open - National 54,000.00 0.00 Signé 2023-07-20 2023-08-01 2023-09-07 2024-01-31 2023-09-28 2024-03-05 2023-11-02 2024-04-29 2026-11-01 ’un Responsable Routes et Pi stes C 01-22/CN / Appui à la tran sformation et à la résilience Sélection de cons (Re-)building Resilient Agric Direct - Internation En cours d'exécut des systèmes alimentaires d IDA / 71570 A priori ultants par entent 8,500,000.00 0.00 2023-07-25 2023-11-27 2023-08-04 2024-01-23 2023-10-08 2027-09-17 ulture Production Capacity al ion e Madagascar à travers la re e directe cherche pour le développem ent CI 08-23/CN / Recrutement d 'un Consultant national pour l En attente d'exéc IDA / 71570 Project Management A posteriori Individuel Open - National 15,000.00 0.00 2023-10-02 2023-11-28 2023-12-03 2023-12-12 2024-05-10 'élaboration du plan de prépa ution ration aux crises de sécurité alimentaire (FSCPP) CI 14-23/CN / Conduite d’un En attente d'exéc e évaluation des besoins en IDA / 71570 Project Management A posteriori Individuel Open - National 5,000.00 0.00 2023-09-29 2023-11-13 2023-11-23 2023-11-30 2023-12-30 ution RH et de formation CI 21-23-CN / Recrutement d En cours d'exécut IDA / 71570 Project Management A posteriori Individuel Open - National 200,000.00 0.00 2023-10-02 2024-01-30 2023-11-13 2023-11-28 2023-12-05 2026-11-19 e cinq Comptables régionaux ion T 02-23-ALG / Assistance tec hnique pour les travaux de ré habilitation de la piste en 4 l ots: Lot 1-Talata Volonondry-Sada Sélection de cons (Re-)building Resilient Agric Direct - Internation En cours d'exécut be-Analaroa: 66Km IDA / 71570 A priori ultants par entent 5,560,000.00 0.00 2023-10-16 2023-11-10 2023-12-30 2027-12-09 ulture Production Capacity al ion Lot 2-Ambalavato-Soanindrar e directe iny-Tsarahonenana: 47Km Lot 3-Imeritsiatosika-Miankot sorano: 17Km Lot 4- Betampona-Fenerive E st: 9Km CI 11-23/CN / Recrutement d IDA / 71570 Project Management A posteriori Individuel Open - National 35,000.00 0.00 Signé 2023-09-29 2023-09-28 2023-10-27 2024-02-15 2023-11-11 2024-04-30 2023-11-18 2024-05-22 2026-11-02 'un(e) Comptable national CI 07-22/CN / Actualisation d u manuel des opérations tec hniques, de procédures de la IDA / 71570 Project Management A posteriori Individuel Open - National 15,000.00 0.00 Signé 2023-09-28 2023-09-29 2023-11-16 2024-01-05 2023-12-07 2024-01-08 2024-01-11 2024-01-30 2024-02-25 passation des marchés et de gestion administrative, comp table, financière et budgétair e du PRSA C 02-22/CN / Développemen Sélection de cons (Re-)building Resilient Agric Direct - Internation En cours d'exécut t d'un produit de biocontrôle IDA / 71570 A priori ultants par entent 1,000,000.00 0.00 2023-10-18 2023-11-13 2023-10-28 2023-12-04 2024-01-01 2025-12-13 ulture Production Capacity al ion de l'aflatoxine à Madagascar e directe C 16-23/CN / Assistance tech Sélection de cons nique pour l'élaboration d’un (Re-)building Resilient Agric Direct - Internation IDA / 71560 A priori ultants par entent 1,100,000.00 0.00 Signé 2023-10-31 2023-10-31 2023-11-15 2023-11-16 2023-12-09 2024-02-23 2025-06-01 plan directeur sur l'élevage à ulture Production Capacity al e directe Madagascar (ILRI) C 01-23/CN / Etude de mise Sélection de cons (Re-)building Resilient Agric en adéquation des matériels IDA / 71570 A posteriori ultants par entent Direct - National 90,000.00 0.00 Signé 2023-10-31 2023-11-02 2023-11-10 2023-12-14 2023-12-09 2024-03-06 2024-06-06 ulture Production Capacity agricoles dans les 13 régions e directe CI 18-23-CN / Recrutement spécialiste environnement et IDA / 71570 Project Management A posteriori Individuel Open - National 45,000.00 0.00 Signé 2023-09-29 2023-10-06 2023-11-18 2024-01-05 2023-12-03 2024-03-05 2023-12-23 2024-04-29 2026-12-07 Gestion des Ressources Natu relles CI 17-23-CN / Recrutement En cours d'exécut spécialiste en subventions à IDA / 71570 Project Management A posteriori Individuel Open - National 45,000.00 0.00 2023-09-29 2023-11-14 2023-11-18 2023-12-03 2023-12-23 2026-12-07 ion coûts partagés CI 15-23-CN / Recrutement expert en Agriculture et syst IDA / 71570 Project Management A posteriori Individuel Open - National 45,000.00 0.00 Signé 2023-09-25 2023-08-20 2023-11-14 2023-11-23 2023-11-29 2023-11-23 2023-12-19 2024-01-09 2026-12-03 ème alimentaire CI 19-23-CN / Recrutement d IDA / 71570 Project Management A posteriori Individuel Open - National 225,000.00 0.00 Signé 2023-09-28 2023-09-02 2023-11-17 2023-11-23 2023-12-02 2023-11-24 2023-12-22 2024-01-30 2026-12-06 e cinq Coordonateurs Région aux CI 09-23-CN / Recrutement c En attente d'exéc onsultant pour Elaboration d IDA / 71570 Project Management A posteriori Individuel Open - National 10,000.00 0.00 2023-09-29 2023-11-18 2023-12-03 2023-12-23 2024-03-22 ution es Manuels de Alliances Prod uctives, PPP, MG CI 10-23-CN / Recrutement En cours d'exécut IDA / 71570 Project Management A posteriori Individuel Open - National 45,000.00 0.00 2023-10-31 2024-02-07 2023-12-20 2024-01-04 2024-01-24 2027-01-08 auditeur interne ion CI 20-23-CN / Recrutement d e cinq Responsables Adminis IDA / 71570 Project Management A posteriori Individuel Open - National 200,000.00 0.00 Signé 2023-09-28 2023-10-20 2023-11-17 2024-02-13 2023-12-02 2024-04-19 2023-12-22 2024-05-08 2026-12-06 tratifs et financiers Régionau x CI 01-24/CN / Recrutement d e deux (02) stagiaires en pas IDA / E0830 Project Management A posteriori Individuel Open - National 10,000.00 0.00 Signé 2024-01-22 2024-01-29 2024-02-15 2024-03-18 2024-03-01 2024-03-28 2024-03-30 2024-04-08 2026-03-30 sation des marchés C 04-24/CN / Etude de faisab Sélection de cons En attente d'exéc ilité technique pour le traite IDA / 71570 Getting to Market A posteriori ultants par entent Direct - National 400,000.00 0.00 2024-05-21 2024-05-31 2024-07-17 2025-01-13 ution ment du Lavaka Mananasy e directe CI 19-24/CN / Recrutement d En attente d'exéc e cinq (05) Responsables Sui IDA / 71570 Project Management A posteriori Individuel Open - National 180,000.00 0.00 2024-05-14 2024-06-09 2024-06-14 2024-07-03 2027-07-03 ution vi Évaluation Régionaux Page 3 CI 20-24/CN / Recrutement d En cours d'exécut e 5 Responsables en Agricult IDA / 71570 Project Management A posteriori Individuel Open - National 180,000.00 0.00 2024-05-14 2024-06-01 2024-06-12 2024-06-17 2024-07-06 2027-07-06 ion ure et système alimentaire R égionaux CI 21-24/CN / Recrutement d e cinq (05) Responsables Rég En cours d'exécut IDA / 71570 Project Management A posteriori Individuel Open - National 180,000.00 0.00 2024-05-15 2024-06-01 2024-06-10 2024-06-17 2024-07-06 2027-07-06 ionaux en Environnement et ion Gestion des Ressources Natu relles CI 24-24/CN / Recrutement d e cinq (05) Assistants en Ges En cours d'exécut IDA / 71570 Project Management A posteriori Individuel Open - National 180,000.00 0.00 2024-05-16 2024-06-04 2024-06-11 2024-06-18 2024-07-07 2027-07-07 tion des Risques Environnem ion entaux et Sociaux Régionaux CI 28-24/CN / Recrutement d e cinq (05) Responsables en IDA / 71570 Project Management A posteriori Individuel Open - National 180,000.00 0.00 Annulé 2024-05-17 2024-06-12 2024-06-17 2024-07-06 2027-07-06 Social Régionaux CI 23-24/CN / Recrutement d En cours d'exécut e cinq (05) Assistants Région IDA / 71570 Project Management A posteriori Individuel Open - National 180,000.00 0.00 2024-05-17 2024-07-18 2024-06-12 2024-06-17 2024-07-06 2027-07-06 ion aux en Passation des marché s CI 27-24/CN / Recrutement d En cours d'exame e Responsable irrigation au n IDA / 71570 Project Management A posteriori Individuel Open - National 72,000.00 0.00 2024-05-14 2024-08-20 2024-06-12 2024-06-22 2024-07-16 2027-07-16 n iveau UER Atsinanana et Boe ny CI 30-24/CN / Appui à la con En attente d'exéc duite d’une étude sur la fisca IDA / 71570 Getting to Market A posteriori Individuel Open - National 50,000.00 0.00 2024-05-14 2024-06-08 2024-06-18 2024-07-12 2025-01-08 ution lité de la filière viande rouge à Madagascar CI 08-24/CN / Recrutement d Sélection de cons En cours d'exécut 'un Responsable Administrati IDA / 71570 Project Management A posteriori ultants par entent Direct - National 46,800.00 0.00 2024-05-14 2024-06-13 2024-05-24 2024-06-18 2027-06-18 ion f et Financier de l'UGP e directe CI 31-24/CN / Recrutement d En attente d'exéc IDA / 71570 Project Management A posteriori Individuel Open - National 46,000.00 0.00 2024-05-14 2024-06-08 2024-06-18 2024-07-09 2027-07-09 u Coordinateur Régional Itas ution y CI 25-24/CN / Recrutement d IDA / 71570 Project Management A posteriori Individuel Open - National 45,000.00 0.00 Annulé 2024-05-17 2024-05-28 2024-06-18 2024-07-23 2027-07-23 e six (06) Secrétaires compta bles CI 17-24/CN / Recrutement C En attente d'exéc IDA / 71570 Project Management A posteriori Individuel Open - National 39,000.00 0.00 2024-05-16 2024-05-27 2024-06-06 2024-06-25 2027-06-25 hef d'Antenne Régionale Ano ution sy CI 09-24/CN / Recrutement d IDA / 71570 Project Management A posteriori Individuel Open - National 36,000.00 0.00 Annulé 2024-05-17 2024-06-11 2024-06-26 2024-07-20 2027-07-20 'un Responsable SIG CI 10-24/CN / Recrutement d IDA / 71570 Project Management A posteriori Individuel Open - National 36,000.00 0.00 Annulé 2024-05-27 2024-07-02 2024-07-17 2024-08-10 2027-08-10 'un Responsable en Commun ication CI 18-24/CN / Recrutement d En attente d'exéc 'un Expert en élevage Anten IDA / 71570 Project Management A posteriori Individuel Open - National 36,000.00 0.00 2024-05-27 2024-06-08 2024-06-09 2024-07-03 2027-07-03 ution ne Régionale Anosy CI 26-24/CN / Recrutement d En cours d'exécut 'un Responsable irrigation au IDA / 71570 Project Management A posteriori Individuel Open - National 36,000.00 0.00 2024-06-03 2024-07-17 2024-07-04 2024-07-05 2024-07-29 2027-07-29 ion niveau de l'UGP CI 29-24/CN / Recrutement d En cours d'exécut 'un Gestionnaire de contrats IDA / 71570 Project Management A posteriori Individuel Open - National 36,000.00 0.00 2024-05-27 2024-07-18 2024-06-27 2024-07-07 2024-07-31 2027-07-31 ion au niveau de l'UGP CI 04-24/CN / Recrutement d 'un Consultant Individuel en vue de l'Appui à la conduite En attente d'exéc IDA / 71570 Getting to Market A posteriori Individuel Open - National 35,000.00 0.00 2024-06-10 2024-07-20 2024-07-21 2024-08-14 2025-02-10 d'une étude juridique et instit ution utionnelle pour la mise en pl ace des coopératives/fédérat ion d'éleveurs de bovins CI 05-24/CN / Recrutement d 'un Consultant Individuel pou En attente d'exéc r l'Appui à la conduite d'une IDA / 71570 Getting to Market A posteriori Individuel Open - National 35,000.00 0.00 2024-06-24 2024-07-25 2024-08-15 2024-09-19 2025-03-18 ution étude sur la place des organi sations de producteurs de fo urrage CI 13-24/CN / Recrutement d En cours d'exécut IDA / 71570 Project Management A posteriori Individuel Open - National 21,000.00 0.00 2024-05-17 2024-07-11 2024-06-17 2024-06-24 2024-07-15 2027-07-15 'un Assistant Financier pour l' ion UGP CI 16-24/CN / Recrutement d En cours d'exécut 'un Technicien en Informatiq IDA / 71570 Project Management A posteriori Individuel Open - National 21,000.00 0.00 2024-05-20 2024-06-01 2024-06-20 2024-06-30 2024-07-21 2027-07-21 ion ue au niveau de l'UGP CI 12-24/CN / Recrutement d En cours d'exécut 'un Assistant administratif au IDA / 71570 Project Management A posteriori Individuel Open - National 15,000.00 0.00 2024-05-22 2024-07-11 2024-06-22 2024-07-13 2024-08-06 2027-08-06 ion niveau de l'UGP CI 02-24/CN / Recrutement d 'un spécialiste de la régleme ntation dans le domaine de l' En attente d'exéc IDA / 71570 Getting to Market A posteriori Individuel Open - National 10,000.00 0.00 2024-09-17 2024-10-27 2024-11-17 2024-12-22 2025-05-31 élevage pour appuyer dans l ution es réglementations nationale s sur la digitalisation de la ge stion des données CI 06-24/CN / Recrutement d 'un consultant individuel pou En attente d'exéc IDA / 71570 Project Management A posteriori Individuel Open - National 5,000.00 0.00 2024-06-04 2024-07-14 2024-07-24 2024-08-22 2024-11-20 r l’Élaboration du manuel de ution collaboration entre le FSRP et le FDA CI 11-24/CN / Recrutement d En cours d'exécut 'un (01) Spécialiste en Passat IDA / 71570 Project Management A posteriori Individuel Open - National 36,000.00 0.00 2024-05-31 2024-07-18 2024-07-01 2024-07-22 2024-08-15 2027-08-15 ion ion des Marchés pour l 'UGP CI 15-24/CN / Recrutement d En cours d'exécut IDA / 71570 Project Management A posteriori Individuel Open - National 21,000.00 0.00 2024-06-27 2024-07-04 2024-08-15 2024-09-05 2024-10-10 2027-10-10 'un Logisticien au niveau de l ion 'UGP CI 32-24/CN / Recrutement d En attente d'exéc 'un Consultant Individuel Exp IDA / 71570 Project Management A posteriori Individuel Direct - National 14,000.00 0.00 2024-06-07 2024-06-17 2024-07-08 2024-08-12 2025-02-08 ution ert en Pistes et Infrastructure s Page 4 CI 14-24/CN / Recrutement d En cours d'exécut 'un Assistant en charge de la IDA / 71570 Project Management A posteriori Individuel Direct - National 21,000.00 0.00 2024-05-31 2024-07-18 2024-06-10 2024-06-17 2024-07-04 2027-07-04 ion comptabilité public CI 33-24/CN / RECRUTEMENT D’UN SPECIALISTE EN LUTTE ET PREVENTION AUX :VIOLEN CES BASEES SUR LE GENRE ( En cours d'exécut VBG) / EXPLOITATIONS ET AB IDA / 71570 Project Management A posteriori Individuel Direct - National 54,000.00 0.00 2024-07-01 2024-07-18 2024-07-11 2024-08-01 2024-09-05 2027-09-05 ion US SEXUEL ET HARCELEMEN T SEXUEL (VBG/ EAS et HS), VIOLENCES CONTRE LES ENF ANTS (VCE) AU NIVEAU DE L’ UNITE DE GESTION DU FSRP CI 07-24/CN / Recrutement d 'un consultant individuel pou En attente d'exéc IDA / 71570 Project Management A posteriori Individuel Open - National 20,000.00 0.00 2024-08-22 2024-10-10 2024-10-31 2024-12-05 2025-06-03 r l’Élaboration de stratégie d ution e communication pour le Proj et C 10-24/CN / Etudes sur les t ravaux de réhabilitation des Sélection de cons piste Arivonimamo Mandiava Direct - Internation En attente d'exéc IDA / 71570 Getting to Market A priori ultants par entent 993,000.00 0.00 2024-08-31 2024-09-10 2024-11-14 2025-08-11 to de la région Itasy (49 Km) al ution e directe et piste Betafo Ambatonikola hy Farihimena (28 Km) de la région de Vakinakaratra Page 5