Procurement Plan For Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project A World Bank Financed Project Project ID: P165129 [Procurement Plan Period: First 18 months of the Project] Covering the Period: January 2020 to June 2021 Submitted By Project Management Unit [PMU] Himachal Pradesh Forest Department Government of Himachal Pradesh India 2 3 PROCUREMENT PLAN Country: INDIA Borrower: Government of India on behalf of Government of Himachal Pradesh Project Name: Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project Project Implementation Agency: Project Management Unit [PMU], Himachal Pradesh Forestry Department [HPFD], Government of Himachal Pradesh Date of General Procurement Notice: December 18, 2019 Bank’s Approval Date of the Procurement Plan: Original … Revision 1: Revision 2: Date of the Procurement Plan: December 2019 Period covered by this Procurement Plan: January 2020 to June 2021 Applicable Procurement Rules. The Procurement of goods, works, consulting and non-consulting services to be financed by the Loan will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers [dated July 2016; revised November 2017 and August 2018], and the provisions of the Loan Agreement. If there is conflict between government decrees, rules, and regulations and the Bank Procurement Regulations, then Bank’s Procurement Regulations shall prevail. The project will be subject to World Bank Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants [“Anti-Corruption Guidelines”], dated October 15, 2006 and revised in January 2011 and as of July 1, 2016. The project will use the online tool Systematic Tracking of Exchanges in Procurement [STEP] to prepare, clear, and update its procurement plan, for monitoring procurement activities and for communication between the Borrower and the Bank. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under Paragraph 4.4 of the Procurement Regulations are set forth in STEP. Unless otherwise agreed with the World Bank, the World Bank’s Standard Procurement Documents [SPD], Requests for Proposals, and Forms of Consultant Contract will be used. Procurement under national procedures will be carried out based on National Procurement Procedures [NPP] conditions agreed with the Government of India. Procurement estimated at Indian Rupees [INR] 5 Lakhs and above will be submitted through government eProcurement systems provided by NIC 4 www.hptender.gov.in which have been assessed and deemed acceptable by the Bank against Multilateral Development Bank [MDB] requirements. Financial Management [FM] Manual. The FM Manual prepared for the project shall have a separate chapter on Procurement which will provide clear guidance on applicable procurement arrangement, procedures and thresholds, and shall be made available on the project website. Community Operations Manual [COM]. The COM prepared for the project will have clear directives for the community [GPs/individual beneficiaries] with regard to eligible procurement expenditures and agreed procurement arrangements, procedures and thresholds, and shall be made available on the project website. This will serve as a guidebook for procurement, with a view to providing operating instructions and bring in greater transparency and predictability in procurement procedures under the Project. Procurement Arrangements and Profile. Procurement under the Project will be carried out at the central level by the Project Management Unit [PMU] headed by the Chief Project Director [CPD] established for the Project, at the District level by the District Project Officers assisted by the Accounts Assistant at the District Level in each of the 10 District Project Offices [DPOs] located in the Districts covered under the Project [Shimla, Solan, Sirmour, Bilaspur, Hamirpur, Mandi, Kullu, Chamba, Kangra and Una], and by beneficiary GPs [supported by DPOs] at the GP level, in accordance with their approved Gram Panchayat Resource Management Plans [GP-RMP]/MG/OMIF. Officials of the PMU have prior experience of implementing a World Bank financed project and have also undergone training in STEP. GPs will need to be capacitated and provided basic procurement training on applicable procurement procedures and procurement documentation requirements outlined in COM, before initiating their procurements. To meet the readiness requirements of the Department of Economic Affairs [DEA] of the Government of India, the Project has already initiated and awarded contract for critical consultancy package for Environmental and Social Assessment to be retroactively financed by the Bank. The project envisages procurement of low-risk, low-value goods, works and services as below: a. Goods and Non-Consulting Services to be procured under the project are likely to include the following. At State/PMU level, purchase of IT Equipment such laptops, computers, printer, etc., procurement of printing services for IEC, office vehicles, office furniture, etc. are envisaged. At District and GP level, procurement activities will include procurement of Barbed Wire, U/Staple, Tools, Gunny Bags, Vermicompost/ Farm yard Manure, Sand, Seeds, Wooden posts/ poles, Seedlings, Grass tufts, Sign boards/hand prints, seed testing instrument, Seed, Fertilizer, Pesticide, Livestock - Small and Large Ruminants, Agricultural Tools and Implements, equipment, Farm machinery, e.g., power tiller, chaff cutters, pipes, tarpaulins, Medicines, supplements, sprinklers, seedlings, etc. b. Procurement of Minor Civil Works is likely to include the following. At State/ PMU level, procurement of minor civil works will include extension, refurbishment and repair of office buildings, etc. At District and GP level, procurement activities will include procurement of works for construction of Water storage tanks, water channels, vermicompost pits, livestock Mangers, foot bridges, water lifting pumps, GI pipes, accessories, installation of ropeways, Ponds, Check Dams, Subsurface Dykes, Sump Wells etc. and labor contracts for preparing land 5 for nursery, preparing nursery beds, water tank, works of filling gunny bags, sowing of seeds, preparing temporary nursery sheds, watering, hoeing, weeding, , fencing, bush cutting, pit digging, planting seedlings, preparing contour trenches, planting grass tufts, drainage line treatment works, fire management works, allowances and incentives for fire management, Spring development, eradication of exotic weed- lantana, etc. It may be noted that civil works at GP level are demand driven. There are no major civil works contracts envisaged in the project. c. Consultancy Services to be procured under the project are likely to include services for developing a web-based portal for Integrated Financial Management Information System [IFMS], Water Monitoring and Modelling, Value Chain Scoping Studies, Technical Support Study for addressing the needs of Transhumant, M and E, MIS, Baseline Survey, External and Internal Audit, Third Party Verification agent to verify achievement of Disbursement Related Results [DLR]s, need based assessments and studies, individual experts, etc. No consultancy services contracts envisaged at the District/Sub-district levels. The project includes several features of a decentralized, demand-driven project, and activities to be taken up at the community level by selected beneficiaries shall be as per the GP-RMP approved by the PMU of the HP Forestry Department/MG/OMIF. The threshold of procurement activities at community level is expected not to exceed Request for Quotation [RFQ] threshold. Community-level procurement shall follow Community-Driven Development [CDD] arrangements as per the Bank’s Procurement Regulations and as outlined in the Community Operations Manual [COM] currently under preparation. Given other on-going government programs, the activities to be funded following COM shall be identified upfront to avoid double-dipping and will require very close monitoring and oversight. Project Procurement Strategy for Development [PPSD] and Procurement Plan. According to the requirement of the Regulations, a Project Procurement Strategy for Development [PPSD] has been developed, based on which the Procurement Plan for the first 18 months has been prepared. The PPSD describes how procurement in this project will support the Project Development Objective [PDO] and deliver value for money under a risk-based approach. It provides adequate supporting market analysis for the selection methods detailed in the procurement plan. The procurement plan specifies for each contract: [i] a description of the activities/contracts; [ii] selection methods to be applied; [iii] estimated cost; [iv] time schedules; [v] World Bank review requirements; and [vi] any other relevant procurement information. PMU shall submit to the World Bank, for its review and approval, any updates of the procurement plan approved by the World Bank. The project will use Systematic Tracking of Exchanges in Procurement [STEP] system for all its procurement activities carried out at the PMU [Centre] and District levels. Summary from PPSD. The project is preparing its Procurement Strategy document. As per the draft document, the project’s total value is US $100 million of which procurement spend is approximately 80 %. Extensive market analysis has been carried out for procurement packages and decisions on packages are made to ensure adequate participation of bidders. Consultancy contracts are framed based on market research and packaging decided in terms of scope of services and period. Based on the need assessment, the project has decided to 6 use Government e Marketplace [GeM]1 for procurement of Goods up to US $100,000 and as mentioned under the paragraph in the Procurement Plan on National Procurement Procedures. Procurement Capacity Building. Though project staff has past experience of implementing World Bank financed HP Mid-Himalayan Watershed Development Project [HPMHWDP] governed by the Bank’s Procurement Guidelines, however, they need to be exposed to the Procurement Regulations applicable to the Project. HP Forestry Department will be sending key procurement staff of PMU and DPOs to the Indian Institute of Management [IIM], Lucknow or the Administrative Staff College of India [ASCI], Hyderabad from time to time to attend procurement training on World Bank Procurement Framework [PF] applicable to the project. Presently, project staff from PMU and two DPOs will be attending the two-week residential training program on World Bank Procurement Regulations conducted at ASCI, Hyderabad in February 2020. These officials will subsequently provide training to other project staffs prior to implementation of the procurement activities in the project. The PMU/DPOs/APOs will also provide basic procurement training to GPs/Beneficiaries once the Gram Panchayat Resource Management Plan [GP-RMP] is approved by DPO/PMU, and before commencing implementation of GP-RMP. The project officials can also avail of the free Massive Open Online Course on public procurement www.procurementlearning.org offered by the Bank to build their capacity. The Bank had already conducted one training on STEP for PMU officials and will organize STEP training again on need basis for the concerned DPOs staff in near future. Procurement Planning. For each contract to be financed by the Loan, the different procurement methods or consultant selection methods to be used, the need for pre-qualification, estimated costs, prior review requirements, and time frame will be reflected in the Procurement Plan to be agreed between the Borrower and the Bank team. The Procurement Plan will be uploaded in STEP by PMU/DPOs and the approved procurement plan will be disclosed on the project website and Bank’s external website. The procurement plan for the first 18 months of project implementation and all its updates will be submitted to the Bank through STEP, and will lay out the appropriate, fit for purpose market approach and selection methods for procurement of goods, works, non-consulting and consulting services financed by the Bank. It will be updated at least annually or as required to reflect the actual project implementation needs and improvements in institutional capacity. eProcurement. Currently, the Himachal Pradesh Forestry Department of the Government of Himachal Pradesh is using e-procurement system for its procurement. However, PMU housed in the Forestry Department will be carrying out procurement using eProcurement for the first time in the project, therefore, their capacity building needs to be done for eProcurement. The project will make use of Government of India’s National Informatics Centre [NIC] platform assessed by the Bank against Multilateral Development Bank [MDB] requirements for procurements estimated at INR 5 Lakhs and above. Advance Contracting with Retroactive Financing. For effective project implementation and start-up, the project has initiated advance contracting of critical consultancies for Preparation of Environmental and Social Framework [ESF] and Project Implementation Plan [PIP], and procurement of small value goods such 1 https://gem.gov.in/ 7 as tools, gunny bags, seeds, IT equipment and accessories, vehicles, etc.] and works [very small value labor contracts for Development of Nurseries [52 nos.] in 26 clusters in 10 Districts covering 428 GPs. The total value of this spend is approximately 1.2 % of the Bank loan. Payment made by PMU/HPFD for these contracts following World Bank procurement procedures during the 12 months prior to the tentative Loan signing date shall be eligible for retroactive financing. Record Keeping. All records pertaining to award of tenders/selection of consultants, including tender notification/advertisement, register pertaining to sale and receipt of bids, bid/proposal opening minutes, bid/technical and financial evaluation reports, comparative statements, Goods, Receipt Note [GRN] and all correspondence pertaining to bid evaluation, communication sent to/with the Bank in the process, bid securities, and approval of invitation/evaluation of bids/proposals would be maintained by the PMU and at DPO/GP level. Contract Management. The PMU, HPFD will be responsible for overall procurement and contract management under the project. At the Centre, procurement staff will be responsible for contract monitoring and supervision of contracts awarded by PMU. At DPO level, contract monitoring and supervision will be done by technical staff at DPOs/APOs level [Agriculture, Animal Husbandry/Engineering staff of technical wing of DPO level and Forest Extension and Social Extension staff at APO level] to ensure timely delivery of quality outputs from the procurement contracts in the project areas. All payments will be made by DPOs for district and sub-district level procurements after receipt of Goods receipt Note [GRN]. Work Completion Certificates, etc. The Integrated Financial Management Information System [IFMIS] being developed under the Project will facilitate monitoring of various procurement activities in terms of physical and financial achievements on a monthly basis. The day to day monitoring of procurement activities will be done by APOs/DPOs at field level which will be updated in the online web-based system at district level and will be reviewed by PMU at the Centre. Complaint Handling Mechanism. A complaint handling mechanism to address procurement-related complaints under the Project will be developed and implemented by the PMU/DPOs to the satisfaction of the Bank. Upon receipt of complaints, immediate action would be initiated to acknowledge the complaint and to redress it within a reasonable timeframe. All complaints will be addressed at levels higher than the level at which the procurement process was undertaken, or the decision was taken. Any complaint received will also be forwarded to the Bank for information, and the Bank would be kept informed after the complaint is redressed. Leased Assets: Not Applicable Procurement of Secondhand Goods: Not Applicable Domestic Preference: The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement Thresholds and Prior Review Thresholds. The table below describes various procurement methods to be used for activities financed by the Loan. 8 Table 1: Procurement Thresholds Procurement approach and method Thresholds [US$ equivalent] Open International [Goods, IT, and >10 million Non-consulting services] – Request for Bids [RFB] Open National [Goods, IT, and Non- >100,000 and up to 10 million consulting services] – Request for Bids [RFB] National Request for Quotation Up to 100,000 [RFQ] – [Goods/Works/Non- consulting Services] Open International [Works] – >40 million Request for Bids [RFB] Open National [Works] - Request for >100,000 and up to 40 million Bids [RFB] Direct Selection With prior agreement, based on justification Framework Agreement For Goods/Works/Non-consulting services: According to paragraphs 6.57-6.59 of Section VI of the Regulations. For Consulting services: According to paragraph 7.33 of Section VII the Regulations. Force Account In accordance with paragraphs 6.54 and 6.55 of Section VI of the Procurement Regulations, and with prior agreement in Procurement plan with the Bank. Consulting Services [Firms] CQS: As per requirements of paragraphs 7.11 and 7.12 of Section VII of the Regulations. LCS, FBS: in justified cases QCBS, QBS: in all other packages Shortlist of National Consultants Up to 800,000 Procurement prior-review thresholds2. Based on the current procurement risk rating of ‘Moderate’, the World Bank will prior review the following contracts: (a) Works [including turnkey, supply and installation of plant and equipment and PPP]: All contracts more than US $15 million equivalent 2 Determination of whether a contract meets the prior review threshold is based on : (i) the total value of the contract, including all taxes and duties payable under the contract; (ii) a contract whose cost estimate was below the Bank’s prior review threshold is subject to prior review if the price of the lowest evaluated responsive bid (or, in the case of consulting services, the financial offer of the selected firm) exceeds such threshold at the bid evaluation stage; and (iii) in the case of a slice and package arrangement, the prior review threshold is determined based on the aggregate value of individual contracts to be awarded under such arrangement. 9 (b) Goods and Information Technology: All contracts > US $4 million equivalent (c) Non-consulting Services: All contracts > US $4 million equivalent (d) Consulting Services: Firms: All contracts >US $2 million equivalent (e) Consulting Services: Individuals: All contracts > US $400,000 equivalent (f) Direct Selection: The justification of Direct Selection for all contracts The above thresholds are for the initial 18-month implementation period. Based on the procurement performance of the project, these thresholds may be subsequently modified. Even for large-value post review cases, the inputs of the World Bank on technical specifications will be obtained by the project. Irrespective of the thresholds, Terms of Reference shall be prior reviewed by Bank. The prior review thresholds will also be indicated in the Procurement Plan. The Procurement Plan will be subsequently updated annually [or at any other time if required] and will reflect any change in the prior review thresholds. The details of National Procurement Procedures are outlined in the Procurement Plan. Prior review contracts. In the case of contracts subject to prior review, PMU, HPFD/DPOs will seek the World Bank’s no objection before granting/agreeing to: [a] an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; [b] any substantial modification of the scope of Works, goods, IT system; non-consulting services, or consulting services and other significant changes to the terms and conditions of the contract; [c] any variation order or amendment [except in cases of extreme urgency] that, singly or combined with all variation orders or amendments previously issued, increases the original contract amount by more than 15 percent; and [d] the proposed termination of the contract. Complaints received in all prior review cases shall be sent to Bank for review and the response to the complaint in such cases, shall be cleared with the Bank. Complaints with allegations of fraud and corruption, shall be shared with Bank, irrespective of the thresholds. Disclosure of procurement information. The following documents shall be disclosed on the project/state websites: [a] Procurement Plan and its updates; [b] an invitation for bids for procurement of Works, Goods, IT system procurement and non-consulting services; [c] request for expression of interest for selection/hiring of consulting services; [d] contract awards of Works, Goods, IT system procurement and non-consulting services procured following international and national procedures; [e] a list of contracts/purchase orders placed following RFQ [Request for Quotation] procedures on a quarterly basis; [f] a list of contracts following direct contracting [DC] on a quarterly basis; [g] an annual financial and physical progress report of all contracts; and [h] an action taken report on the complaints received on a quarterly basis. The following details shall be sent to the World Bank for publishing on the United Nations Development Business and the World Bank external website: [a] Specific Procurement Notice [i.e., invitation for bids] for procurement of Works, Goods, IT system procurement and non-consulting services using open international procedures; [b] Requests for Expression of Interests above US $800,000; [c] contract award details of all procurement of Works, Goods, IT system procurement and non-consulting services using open international procedure; and [d] a list of contracts/purchase orders placed following DC procedures on a quarterly basis. Further, the implementing agency will also publish on their websites any information required under the provisions of ‘suo moto’ disclosure as specified by the Right to Information Act. 10 National Procurement Procedure Conditions. National competition for the procurement of Works, Goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: I. Only the model bidding documents for National Competitive Procurement [NCP] agreed with the GOI Task Force [and as amended for time to time], shall be used for bidding. II. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. III. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises or enterprises from any given State. IV. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. V. Government e-Marketplace [GeM] set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations [RFQ] method. VI. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. VII. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. VIII. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. IX. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. X. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social [including sexual exploitation and abuse and gender-based violence], health and safety [“ESHS”] risks and impacts. Oversight and Monitoring by the Bank. All contracts not covered under prior review by the Bank will be subject to post review during implementation support missions and/or special post review missions, including missions by consultants hired by the Bank. The Bank may conduct, at any time, Independent Procurement Reviews [IPRs] of all the contracts financed under the loan. High risk procurements, if any, will be identified for increased procurement and contract management support and indicated in the procurement plan. Bank team will provide additional due diligence and independent review of the contract performance of such identified procurements. 11 Procurement Review by the PMU, HPFD. Independent procurement post review [PPR] with reporting requirements and agreed with the Bank [As per Para 4 of Annex II of the Procurement Regulations] will be undertaken for the project for PMU’s own internal due diligence. PMU will hire PPR consultants as per Terms of Reference and reporting requirements agreed with the Bank to conduct PPR of PMU and DPOs on a half yearly basis. Other Special Selection Arrangements/Requirement Procurement by communities will be governed by the procedures outlined in the Community Operations Manual [COM] currently under preparation and in accordance with Paras 6.52 and 6.53 of Section VI of the Regulations. COM will be disclosed on the Project website. Procurement Plan as per STEP Tables: 12 PROCUREMENT India : Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2020-10-20 Revised Plan Date(s): (comma delineated, leave blank if 2024-08-29 none) Project ID: P165129 GPN Date: 2019-12-19 Project Name: Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh Loan / Credit No: IBRD / 90410 District Project Office, Chamba, Himachal Pradesh Forestry Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned DPO/IDP/CHA/NURSERY/UPU R/NUH / Development of Nur sery sites including water sto Component 1. Sustainable L rage ponds, fencing of sites, i Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 3,000.00 36.78 Completed 2020-02-23 2019-12-30 2020-03-15 2020-02-04 nspection paths, preparation tions nvelope 1 nagement of nursery beds, irrigation fac ility etc. and raising of seedli ngs in 2 nurseries at differen t locations in the target area IN-DPO, CHAMBA-RFQ- NURS ERY 2020-21 / Raising of 150 000 seedlings in 3 different n urseries of different species i. Component 1. Sustainable L Request for Quota Single Stage - One E 2021-09-3 e. Salix spp, Dendrocalamus IBRD / 90410 and and Water Resource Ma Post Limited 42,000.00 14,043.60 Completed 2020-10-04 2020-01-02 2020-10-24 2020-05-26 tions nvelope 0 strictus (Bamboo), Sapindus nagement muckrossii (Soapnut) etc fro m October, 2020 onward for plantations in the rainy seaso n of 2021 in the project areas . IN-DPO, CHAMBA-RFQ- NRY DEV. / Development of Nurse ry sites including water stora Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-3 ge ponds, fencing of sites, in IBRD / 90410 and and Water Resource Ma Post Limited 6,500.00 0.00 Canceled 2020-10-03 2020-10-24 tions nvelope 1 spection paths, preparation o nagement f nursery beds, irrigation facil ity etc. in 2 nurseries at diffe rent locations in the target ar ea IN-DPO, CHAMBA-RFQ- FENC ING 1100 /HA / Pre-monsoon/ advance work i.e. fencing of Component 1. Sustainable L plantation area with wooden Request for Quota Single Stage - One E 2020-09-3 IBRD / 90410 and and Water Resource Ma Post Limited 5,500.00 3,907.53 Completed 2020-06-17 2020-06-15 2020-07-08 2020-08-05 fence post and barbed wire f tions nvelope 0 nagement or raising of plantation in the rainy season of 2020 in the f orest area to increase tree co ver by planting 1100 plants p er/ha. IN-DPO, CHAMBA-RFQ- PLAN TING 1100/HA / Raising of pla Component 1. Sustainable L ntations In the rainy season Request for Quota Single Stage - One E 2020-10-3 IBRD / 90410 and and Water Resource Ma Post Limited 5,800.00 4,326.93 Completed 2020-06-22 2020-06-29 2020-07-13 2020-08-13 of 2020 along drainage line tions nvelope 1 nagement on both side of stream with f ast growing forestry species @ 1100 plants per/ha. IN-DPO, CHAMBA-RFQ- FENC ING- 800/HA / Pre-monsoon/ advance work i.e. fencing of Component 1. Sustainable L plantation area with wooden Request for Quota Single Stage - One E 2020-09-3 IBRD / 90410 and and Water Resource Ma Post Limited 10,200.00 7,425.69 Completed 2020-06-17 2020-06-15 2020-07-08 2020-08-05 fence post and barbed wire f tions nvelope 0 nagement or raising of plantation in the rainy season of 2020 in the f orest area having open cano py @ 800 plants per/ha. IN-DPO, CHAMBA-RFQ- PLAN TING 800/HA / Raising of plan Component 1. Sustainable L tations in the rainy season of Request for Quota Single Stage - One E 2020-10-3 IBRD / 90410 and and Water Resource Ma Post Limited 8,600.00 6,745.35 Completed 2020-06-22 2020-06-29 2020-07-13 2020-08-13 2020 in the forest area havin tions nvelope 1 nagement g open canopy (tree density l ess than 0.4) @ 800 plants p er/ha. IN-DPO, CHAMBA-RFQ- FENC ING 400/HA / Pre-monsoon/ a dvance work i.e. fencing of pl Component 1. Sustainable L antation area with wooden fe Request for Quota Single Stage - One E 2020-09-2 IBRD / 90410 and and Water Resource Ma Post Limited 4,800.00 4,351.39 Completed 2020-06-17 2020-06-15 2020-07-08 2020-08-13 nce post and barbed wire for tions nvelope 5 nagement raising of plantation in the rai ny season of 2020 in the fore st area to increase tree cover by planting 400 plants per/ha . IN-DPO, CHAMBA-RFQ- PLAN TING 400/HA / Raising of plan Component 1. Sustainable L tations in the rainy season of Request for Quota Single Stage - One E 2020-10-3 IBRD / 90410 and and Water Resource Ma Post Limited 2,300.00 2,127.18 Completed 2020-06-22 2020-06-29 2020-07-13 2020-08-13 2020 in the forest area to inc tions nvelope 1 nagement rease the forest density enric hment plantation @ 400 plan ts per/ha. IN-DPO, CHAMBA-RFQ- CONT . TRENCHING / Contour trenc Component 1. Sustainable L hing in plantation areas alon Request for Quota Single Stage - One E 2021-11-0 IBRD / 90410 and and Water Resource Ma Post Limited 6,000.00 4,276.14 Completed 2020-10-22 2020-10-22 2020-11-12 2020-11-20 g with grass seed sowing in t tions nvelope 7 nagement he bunds of trenches to cons erve moisture and enhance a vailability of grasses IN-DPO, CHAMBA-RFQ- LANT ANA 75-100% / Management Component 1. Sustainable L of exotic species - Removal o Request for Quota Single Stage - One E 2020-09-3 IBRD / 90410 and and Water Resource Ma Post Limited 7,200.00 6,052.80 Completed 2020-06-17 2020-06-15 2020-07-08 2020-08-05 f Lantana from target area wi tions nvelope 0 nagement th 75 to 100% infestation by cut root stock method (CRS) IN-DPO, CHAMBA-RFQ- LANT ANA 25% / Management of e Component 1. Sustainable L Request for Quota Single Stage - One E 2020-09-3 xotic species - Removal of La IBRD / 90410 and and Water Resource Ma Post Limited 1,900.00 645.67 Completed 2020-06-17 2020-05-30 2020-07-08 2020-08-13 tions nvelope 0 ntana from target area by cu nagement t root stock method (CRS) Page 1 IN-DPO, CHAMBA-RFQ- DLT / Treatment of Drainage Lines by undertaking various Soil C Component 1. Sustainable L onservation Works by constr Request for Quota Single Stage - One E 2021-11-1 IBRD / 90410 and and Water Resource Ma Post Limited 20,000.00 0.00 Canceled 2020-10-22 2020-11-20 ucting Vegetative check barri tions nvelope 5 nagement ers, Dry stone check barriers, Create Wire check barriers, C ement concrete check barrie rs and Grass tufts planting DPO/CBA/PLANTATION(W)/D LT/2020-21 / Raising of plant ation in winter season of 202 Component 1. Sustainable L 0-21 along the drainage line Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 12,000.00 0.00 Canceled 2020-10-27 2020-11-16 with 1100 plants / Ha. It invol tions nvelope 1 nagement ves multiple contracts. Limite d approach is adopted as the prospective bidders are avail able at different locations. DPO/CBA/DLT-2/2020-21 / Tr eatment of Drainage Lines by undertaking various Soil Con Component 1. Sustainable L servation Works by construct Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 20,000.00 25,751.96 Completed 2020-12-15 2021-02-08 2021-01-09 2021-03-15 ing Vegetative check barriers tions nvelope 1 nagement , Dry stone check barriers, Cr eate Wire check barriers, Ce ment concrete check barrier s and Grass tufts planting IN-DPO, CHAMBA-RFQ- NRY MAINT.2019-20 / Maintenanc e of Nursery planting stock (s Component 1. Sustainable L Request for Quota Single Stage - One E 2021-07-1 eedlings) raised during the y IBRD / 90410 and and Water Resource Ma Post Limited 19,000.00 0.00 Canceled 2020-06-12 2020-07-03 tions nvelope 9 ear 2019-20 in different nurs nagement eries. This activity involves m ultiple contracts with limited approach. DPO/CBA/NURSERY-RAISING/ 2020-21 / Raising of 100000 seedlings in Chowari Nursery of different species i.e. Salix Component 1. Sustainable L Request for Quota Single Stage - One E 2021-06-0 spp, Dendrocalamus strictus IBRD / 90410 and and Water Resource Ma Post Limited 23,500.00 16,948.04 Completed 2020-11-19 2021-01-08 2020-12-06 2021-07-21 tions nvelope 4 (Bamboo), Sapindus muckros nagement sii (Soapnut) etc from Dece mber, 2020 onward for plant ations in the rainy season of 2021 in the project areas. IN-DPO, CHAMBA-RFQ- NRY DEV-CHOWARI / Developmen t of 2 Nurseries sites includin Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-3 g water storage ponds/ tank, IBRD / 90410 and and Water Resource Ma Post Limited 3,400.00 552.47 Completed 2020-11-19 2021-01-06 2020-12-06 2021-02-20 tions nvelope 1 fencing of sites, inspection p nagement aths, preparation of nursery beds, irrigation facility etc. u nder APO Chamba & Chowari . DPO/CBA/PLT(W)/REAFF/202 0-21 / Raising of plantation in winter season of 2020-21 for Component 1. Sustainable L Re-afforestation of degraded Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 60,000.00 13,844.09 Completed 2020-10-27 2020-10-27 2020-12-07 2020-12-13 Forest by planting 800 plants tions nvelope 1 nagement / Ha. It involves multiple cont racts. Limited approach is ad opted as the prospective bid ders are available at differen t locations IN-DPO, CHAMBA-RFQ- LANT ANA (W) / Management of ex Component 1. Sustainable L otic species - Removal of Lan Request for Quota Single Stage - One E 2021-03-1 IBRD / 90410 and and Water Resource Ma Post Limited 18,000.00 8,143.71 Completed 2020-11-19 2020-06-12 2020-12-03 2020-12-13 tana from target area with di tions nvelope 2 nagement fferent level of infestation %a ge by cut root stock method (CRS). DPO/CBA/PLT(W)/ENRICHME NT/2020-21 / Raising of plant ation in winter season of 202 Component 1. Sustainable L 0-21 Enrichment planting of Request for Quota Single Stage - One E 2021-06-3 IBRD / 90410 and and Water Resource Ma Post Limited 70,700.00 12,993.45 Completed 2020-10-27 2020-10-27 2020-11-16 2020-12-13 degraded forests 400 plants / tions nvelope 0 nagement Ha. It involves multiple contr acts. Limited approach is ado pted as the prospective bidd ers are available at different l ocations. DPO-CBA-WHS-2020-21 / Co nstruction of Water Harvesti Component 1. Sustainable L ng Structures as a primary so Request for Quota Single Stage - One E 2021-06-3 IBRD / 90410 and and Water Resource Ma Post Limited 27,000.00 0.00 Canceled 2021-02-26 2021-03-15 urce of water for providing su tions nvelope 0 nagement pply of water to the storage t anks to be constructed on th e farmer's field. DPO-CBA-ST-2020-21 / Cons truction of Water storage ta Component 1. Sustainable L Request for Quota Single Stage - One E 2021-06-3 nks as a source of water stor IBRD / 90410 and and Water Resource Ma Post Limited 30,000.00 0.00 Canceled 2021-02-26 2021-03-15 tions nvelope 0 age for providing supply of w nagement ater to the field of the comm unities farmers. DPO-CBA-KUHL-2020-21 / Co Component 1. Sustainable L nstruction of Water channels Request for Quota Single Stage - One E 2021-06-3 IBRD / 90410 and and Water Resource Ma Post Limited 10,000.00 0.00 Canceled 2021-02-26 2021-03-15 as a source of water supply t tions nvelope 0 nagement o farmers field of the commu nities. DPO-CBA-NRY DEV.-2021-22 / Development of Nursery sit es including water storage ta Component 1. Sustainable L Request for Quota Single Stage - One E 2022-03-3 nks, fencing of sites, inspecti IBRD / 90410 and and Water Resource Ma Post Limited 6,800.00 0.00 Completed 2021-05-03 2021-12-14 2021-05-25 2022-01-12 tions nvelope 1 on paths, preparation of nurs nagement ery beds, irrigation facility et c. in 2 nurseries at different l ocations in the Chamba & Ch owari. DPO-CBA-NRY MAINT/ 2021- 22 / Maintenance of Nursery Component 1. Sustainable L planting stock (seedlings) rai Request for Quota Single Stage - One E 2022-06-3 IBRD / 90410 and and Water Resource Ma Post Limited 25,000.00 0.00 Canceled 2021-05-03 2021-05-25 sed during the year 2020-21 tions nvelope 0 nagement in different nurseries. This ac tivity involves multiple contr acts with limited approach. DPO-CBA-NRY RAISING-2021 -22 / Raising of 150000 seedl ings in 3 different nurseries o Component 1. Sustainable L f different species i.e. Salix s Request for Quota Single Stage - One E 2022-06-3 IBRD / 90410 and and Water Resource Ma Post Limited 34,000.00 0.00 Completed 2021-11-02 2022-01-20 2021-11-22 2022-02-03 pp, Dendrocalamus strictus ( tions nvelope 0 nagement Bamboo), Sapindus muckross ii (Soapnut) etc from May, 2 021onward for plantations in the year 2022 in the project areas. Page 2 DPO-CBA-FENCING-DLT-202 1-22 / Pre-monsoon/ advance work i.e. fencing of plantatio n area with wooden fence po Component 1. Sustainable L Request for Quota Single Stage - One E 2022-03-3 st and barbed wire for raising IBRD / 90410 and and Water Resource Ma Post Limited 9,000.00 32,256.40 Completed 2021-06-02 2021-12-09 2021-06-22 2022-01-17 tions nvelope 1 of plantation in the rainy sea nagement son of 2021 in the forest are a to increase tree cover by pl anting 1100 plants per/ha. al ong the drainage lines. DPO-CBA-FENCING-RE-AFF.- 2021-22 / Pre-monsoon/ adva nce work i.e. fencing of plant Component 1. Sustainable L ation area with wooden fence Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 35,000.00 22,062.36 Completed 2021-06-02 2020-07-26 2021-06-22 2021-08-16 post and barbed wire for raisi tions nvelope 1 nagement ng of plantation in the rainy s eason of 2021 in the forest a rea to increase tree cover by planting 800 plants per/ha. in open forest. DPO-CBA-FENCING-ENRICHM ENT-2021-22 / Pre-monsoon/ advance work i.e. fencing of plantation area with wooden Component 1. Sustainable L Request for Quota Single Stage - One E 2022-03-3 fence post and barbed wire f IBRD / 90410 and and Water Resource Ma Post Limited 38,500.00 26,386.88 Completed 2021-06-02 2021-12-09 2021-06-22 2022-03-07 tions nvelope 1 or raising of plantation in the nagement rainy season of 2021 in the f orest area to increase tree co ver by planting 400 plants pe r/ha. Medium Density Forest. DPO-CBA-PLT-DLT-2021-22 / Raising of plantations In the Component 1. Sustainable L Request for Quota Single Stage - One E 2022-03-3 year 2021-22 along drainage IBRD / 90410 and and Water Resource Ma Post Limited 8,700.00 3,657.09 Completed 2021-06-22 2021-07-26 2021-07-12 2021-09-01 tions nvelope 1 line on both side of stream wi nagement th fast growing forestry speci es @ 1100 plants per/ha DPO-CBA-PLT-REAFF-2021-2 2 / Raising of plantations in t Component 1. Sustainable L Request for Quota Single Stage - One E 2022-03-3 he year 2021-22 in the forest IBRD / 90410 and and Water Resource Ma Post Limited 34,000.00 39,884.56 Completed 2021-06-22 2021-07-15 2021-07-14 2021-06-26 tions nvelope 1 area having open canopy (tre nagement e density less than 0.4) @ 80 0 plants per/ha. DPO-CBA-PLT-ENRICHMENT- 2021-22 / Raising of plantatio Component 1. Sustainable L Request for Quota Single Stage - One E 2022-03-3 ns in the year 2021-22 in the IBRD / 90410 and and Water Resource Ma Post Limited 38,500.00 25,786.50 Completed 2021-06-22 2021-12-09 2021-07-12 2022-01-17 tions nvelope 1 forest area to increase the fo nagement rest density enrichment plant ation @ 400 plants per/ha. DPO-CBA-PLT MAINT-DLT-20 21-22 / Maintenance of old pl Component 1. Sustainable L antations raised during the y Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 1,500.00 1,037.92 Completed 2021-06-22 2021-06-15 2021-07-12 2021-06-21 ear 2020-21 along drainage li tions nvelope 1 nagement ne with replanting of failed s eedlings and repair of fencin g etc. DPO-CBA-PLT MAINT- REAFF- 2021-22 / Maintenance of old Component 1. Sustainable L plantations raised during the Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 4,500.00 3,365.17 Completed 2021-06-22 2021-06-17 2021-07-12 2021-08-10 year 2020-21 in the reaffores tions nvelope 1 nagement tation with replanting of faile d seedlings and repair of fen cing etc. DPO-CBA-PLT-MAINT-ENR-20 21-22 / Maintenance of old pl Component 1. Sustainable L antations raised during the y Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 2,500.00 1,771.68 Completed 2021-06-22 2021-06-02 2021-07-12 2021-06-26 ear 2020-21 enrichment med tions nvelope 1 nagement ium density forest with repla nting of failed seedlings and repair of fencing etc. DPO-CBA-CONT TRENCH & G RASS SOW-2021-22 / Contou Component 1. Sustainable L r trenching in plantation area Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 40,000.00 12,881.65 Completed 2021-07-16 2022-02-28 2021-08-05 2022-03-19 s along with grass seed sowi tions nvelope 1 nagement ng in the bunds of trenches t o conserve moisture and enh ance availability of grasses DPO-CBA-DLT-2021-22 / Tre atment of Drainage Lines by various Soil Conservation wor Component 1. Sustainable L ks by constructing Vegetativ Request for Quota Single Stage - One E 2022-06-3 IBRD / 90410 and and Water Resource Ma Post Limited 400,000.00 69,209.82 Completed 2021-09-02 2021-01-20 2021-09-22 2022-03-18 e check barriers, Dry stone c tions nvelope 0 nagement heck barriers, Create Wire ch eck barriers and Cement con crete check barriers to reduc e the velocity of runoff and p rotection of banks. DPO-CBA-SPRING DEV-2021- 22 / Renovation of traditional Component 1. Sustainable L potable water bodies as a so Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 34,000.00 0.00 Canceled 2021-05-15 2021-05-31 urce of drinking water and st tions nvelope 1 nagement orage for excess water for su pply to the field of the comm unities farmers. DPO-CBA-LANTANA ERD-202 1-22 / Management of exotic Component 1. Sustainable L species - Removal of Lantana Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 50,000.00 49,319.03 Completed 2021-05-04 2016-07-12 2021-05-25 2021-08-14 from target area with differe tions nvelope 1 nagement nt level of infestation %age b y cut root stock method (CR S). DPO-CBA-MAINT-LANTANA-2 021-22 / Management of exo Component 1. Sustainable L tic species - Removal of Lant Request for Quota Single Stage - One E 2021-12-1 IBRD / 90410 and and Water Resource Ma Post Limited 2,500.00 0.00 Completed 2021-05-03 2021-06-02 2021-05-25 2021-06-22 ana from the old treated are tions nvelope 2 nagement as with different level of infes tation %age by cut root stoc k method (CRS). DPO-CBA-POND-2021-22 / C onstruction of Water ponds Component 1. Sustainable L Request for Quota Single Stage - One E 2022-03-3 as a source of water storage IBRD / 90410 and and Water Resource Ma Post Limited 58,000.00 16,409.19 Completed 2021-05-03 2022-01-23 2021-05-25 2022-02-19 tions nvelope 1 for recharge and providing w nagement ater to the wildlife of the are as. DPO-CBA-CCC DAM-2021-22 / Construction of small gravit Component 1. Sustainable L y check dam to store rain wa Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 120,300.00 0.00 Canceled 2021-05-07 2021-06-05 ter / run off from small strea tions nvelope 1 nagement ms as a source of water to th e storage tanks for irrigation to farmers field of the comm unities. Page 3 DPO-CBA-MCDAM-2021-22 / Construction of masonry che Component 1. Sustainable L Request for Quota Single Stage - One E 2022-03-3 ck dam to store rain water fo IBRD / 90410 and and Water Resource Ma Post Limited 278,300.00 0.00 Completed 2021-05-07 2022-02-21 2021-06-29 2021-08-09 tions nvelope 1 r the primary purpose of irrig nagement ation to farmers field of the c ommunities. DPO-CBA-INTAKE STRUCTUR E-2021-22 / Construction of i Component 1. Sustainable L ntake structures is to harvest Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 110,000.00 0.00 Canceled 2021-05-07 2021-05-29 sub-surface flow for the purp tions nvelope 1 nagement ose of making it available for the storage tanks for irrigatio n. DPO-SEC WATER STORAGE-2 021-22 / Construction of stor Component 2. Improved Agri Request for Quota Single Stage - One E 2022-03-3 age Tanks as a secondary so IBRD / 90410 cultural Productivity and Val Post Limited 70,000.00 0.00 Completed 2021-05-07 2021-12-31 2021-05-29 2022-06-07 tions nvelope 1 urce of water for supply of w ue Addition ater to the farmers fields. DPO-CBA-IRRIGATION CHAN NEL-2021-22 / Construction o Component 2. Improved Agri f Water channels as a source Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 cultural Productivity and Val Post Limited 70,000.00 14,157.29 Completed 2021-05-07 2021-09-29 2021-05-29 2021-11-22 of water supply to farmers fie tions nvelope 1 ue Addition ld of the communities from t he water harvesting structur e or local streams. DPO-CBA-RRWT-2021-22 / C onstruction of Roof Rain Wat Component 2. Improved Agri er Harvesting Structures as a Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 cultural Productivity and Val Post Limited 50,000.00 0.00 Canceled 2021-05-07 2021-05-29 source of water for growing v tions nvelope 1 ue Addition egetables on a small scale an d livestock for individual far mer in the homestead. DPO-CBA-BOURIES-2021-22 Component 1. Sustainable L / construction of spring are t Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 15,000.00 0.00 Canceled 2021-05-07 2021-05-29 he main source of drinking, d tions nvelope 1 nagement omestic and agricultural wat er of the communities. DPO-CBA-LIVESTOCKMANAG ER-2021-22 / Construction of Live Stock Mangers as a Live Component 2. Improved Agri Request for Quota Single Stage - One E 2022-03-3 stock Management Program t IBRD / 90410 cultural Productivity and Val Post Limited 50,000.00 5,008.53 Completed 2021-05-07 2021-11-10 2021-05-29 2021-12-12 tions nvelope 1 o promote efficient use of fod ue Addition ders provided to the commu nities involved in livestock re aring during the year 2021-2 2 DPO-CBA-FOOT BRIDGE-202 1-22 / Construction of Ropew Component 2. Improved Agri ays and foot Bridges to impro Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 cultural Productivity and Val Post Limited 100,000.00 8,810.74 Completed 2021-05-07 2021-09-02 2021-05-29 2022-03-03 ve connectivity of the farmer tions nvelope 1 ue Addition s from poor accessibility area s with the markets for supply of inputs and sale of produce . DPO/ CBA / TAP - D. TANK/S HED /2021-22 / The Procure ment of works under Tribal A Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2022-09-1 ction Plan to construct the di IBRD / 90410 cultural Productivity and Val Post Open - National 20,000.00 0.00 Canceled 2022-02-28 2022-03-17 tions nvelope or explanation) 3 pping tank and shed for lives ue Addition tock of transhumant (Settled / Migratory / using Project GP s as a route) during the year 2021-22. DPO/CBA/NRY MATIN/2022-2 3 / Maintenance of Nursery pl Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-10-0 anting stock (seedlings) raise IBRD / 90410 and and Water Resource Ma Post Open - National 10,000.00 0.00 Completed 2022-04-18 2022-05-05 2022-08-27 tions nvelope or explanation) 2 d during the year 2021-22 in nagement different three nurseries nurs eries. DPO/CBA/ADL PLT/2022-23 / Raising of plantations In the Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-12-2 year 2022-23 along drainage IBRD / 90410 and and Water Resource Ma Post Open - National 22,100.00 5,956.20 Completed 2022-06-13 2022-06-30 2022-07-12 tions nvelope or explanation) 7 line on both side of stream wi nagement th fast growing forestry speci es @ 1100 plants per/ha DPO/CBA/AFF PLT/2022-23 / Raising of plantations in the Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-03-3 year 2022-23 in the forest ar IBRD / 90410 and and Water Resource Ma Post Open - National 48,000.00 41,047.62 Completed 2022-06-13 2022-06-30 2022-08-08 tions nvelope or explanation) 1 ea having open canopy (tree nagement density less than 0.4) @ 800 plants per/ha. DPO/CBA/ENR PLT/2022-23 / Raising of plantations in the Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-12-2 year 2022-23 in the forest ar IBRD / 90410 and and Water Resource Ma Post Open - National 21,500.00 6,252.16 Completed 2022-06-13 2022-06-30 2022-08-22 tions nvelope or explanation) 7 ea to increase the forest den nagement sity enrichment plantation @ 400 plants per/ha DPO/CBA/CONTOUR/2022-23 / Contour trenching in plantat Component 1. Sustainable L ion areas along with grass se Request for Quota Single Stage - One E Other (with field f 2023-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 15,000.00 0.00 Completed 2022-04-18 2022-05-05 2023-02-06 ed sowing in the bunds of tre tions nvelope or explanation) 1 nagement nches to conserve moisture a nd enhance availability of gr asses DPO/CBA/GRASS TUFTS/202 2-23 / Planting of Grass Tufts Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-03-3 along Draining Line in plantat IBRD / 90410 and and Water Resource Ma Post Open - National 2,650.00 0.00 Completed 2022-05-16 2022-06-01 2023-03-06 tions nvelope or explanation) 1 ion areas to conserve moistu nagement re and enhance availability o f grasses DPO/CBA-SCW/2022-23 / Tre atment of Drainage Lines by various Soil Conservation wor Component 1. Sustainable L ks by constructing Vegetativ Request for Quota Single Stage - One E Other (with field f 2023-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 74,100.00 0.00 Completed 2022-04-18 2022-05-09 2022-10-10 e check barriers, Dry stone c tions nvelope or explanation) 1 nagement heck barriers, Create Wire ch eck barriers and Cement con crete check barriers to reduc e the velocity of runoff and p rotection of banks. DPO/CBA/WATER BOURIES/2 022-23 / Construction / Reno Component 1. Sustainable L vation of of spring / Water Ba Request for Quota Single Stage - One E Other (with field f 2023-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 19,500.00 0.00 Completed 2022-04-18 2022-05-09 2022-10-12 uries are the main source of tions nvelope or explanation) 1 nagement drinking, domestic and agric ultural water of the communi ties. Page 4 DPO/CBA/LANTANA ERD/202 2-23 / Management of exotic Component 1. Sustainable L species - Removal of Lantana Request for Quota Single Stage - One E Other (with field f 2023-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 62,200.00 0.00 Completed 2022-04-11 2022-04-29 2022-07-30 from target area with differe tions nvelope or explanation) 1 nagement nt level of infestation %age b y cut root stock method (CRS ). DPO/CBA/1ST MAINT. LANTA NA/2022-23 / Management of Component 1. Sustainable L exotic species - Removal of L Request for Quota Single Stage - One E Other (with field f 2023-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 16,000.00 0.00 Completed 2022-04-11 2022-04-25 2022-07-21 antana from the old treated tions nvelope or explanation) 1 nagement areas with different level of i nfestation %age by cut root stock method (CRS). DPO/CBA/MAINT. 2ND LANTA NA/2022-23 / Management of Component 1. Sustainable L exotic species - Removal of L Request for Quota Single Stage - One E Other (with field f 2023-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 2,100.00 0.00 Completed 2022-07-04 2022-07-22 2022-07-28 antana from the old treated tions nvelope or explanation) 1 nagement areas with different level of i nfestation %age by cut root stock method (CRS). DPO/CBA/POND/2022-23 / C onstruction of Water ponds Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-04-1 as a source of water storage IBRD / 90410 and and Water Resource Ma Post Open - National 18,900.00 0.00 Completed 2022-05-09 2022-06-13 2023-02-06 tions nvelope or explanation) 3 for recharge and providing w nagement ater to the wildlife of the are as. DPO/CBA/CCCD/2022-23 / C onstruction of small gravity c Component 1. Sustainable L heck dam to store rain water Request for Quota Single Stage - One E Other (with field f 2023-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 80,000.00 0.00 Completed 2022-04-18 2022-05-09 2022-10-12 / run off from small streams tions nvelope or explanation) 1 nagement as a source of water to the st orage tanks for irrigation to f armers field of the communit ies. DPO/CBA/MCDAM/2022-23 / Construction of masonry che Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-04-0 ck dam to store rain water fo IBRD / 90410 and and Water Resource Ma Post Open - National 28,200.00 0.00 Canceled 2022-04-18 2022-05-09 tions nvelope or explanation) 3 r the primary purpose of irrig nagement ation to farmer’s field of the communities. DPO/CBA/SSD MAKOWAL/20 22-23 / Construction of Sub S Component 1. Sustainable L urface Dykes (Machala) is to Request for Quota Single Stage - One E Other (with field f 2023-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 67,200.00 0.00 Completed 2022-04-18 2022-05-07 2022-10-12 harvest sub-surface flow for t tions nvelope or explanation) 1 nagement he purpose of making it avail able for the storage tanks for irrigation. DPO/CBA/SEC TANK LIFT/202 2-23 / Construction of Tanks f Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2023-03-3 or lift scheme as a secondary IBRD / 90410 cultural Productivity and Val Post Open - National 32,400.00 0.00 Completed 2022-04-18 2022-05-09 2022-06-23 tions nvelope or explanation) 1 source of water for supply of ue Addition water to the farmers fields. DPO/CBA/IRRIGATION CHAN NEL/2022-23 / Construction o Component 2. Improved Agri f Water channels as a source Request for Quota Single Stage - One E Other (with field f 2023-03-3 IBRD / 90410 cultural Productivity and Val Post Open - National 33,000.00 0.00 Completed 2022-04-18 2022-05-09 2022-10-12 of water supply to farmers fie tions nvelope or explanation) 1 ue Addition ld of the communities from t he water harvesting structur e or local streams. DPO/CBA/FOOT BRIDGE/202 2-23 / Construction of Ropew Component 2. Improved Agri ays and Foot Bridges to impr Request for Quota Single Stage - One E Other (with field f 2023-06-3 IBRD / 90410 cultural Productivity and Val Post Open - National 66,000.00 0.00 Completed 2022-07-18 2022-08-06 2022-08-27 ove connectivity of the farme tions nvelope or explanation) 0 ue Addition rs from poor accessibility are as with the markets for suppl y of inputs and sale of produ ce. DPO/CBA/SEC. WATER DISTR /2022-23 / Providing and layi ng of water distribution syste Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2023-06-3 m to the farmer’s field from t IBRD / 90410 cultural Productivity and Val Post Open - National 20,000.00 0.00 Completed 2022-07-30 2022-09-24 2022-10-12 tions nvelope or explanation) 0 he secondary storage tanks b ue Addition y way of sprinklers, water pip es, drip irrigation system etc. , for the year 2022-23. DPO/CBA/STORAGE TANK/ A Component 2. Improved Agri POCHM /22-23 / Constructio Request for Quota Single Stage - One E Other (with field f 2023-06-3 IBRD / 90410 cultural Productivity and Val Post Open - National 60,000.00 0.00 Completed 2022-08-08 2022-08-27 2023-03-29 n of Storage Tank as a secon tions nvelope or explanation) 0 ue Addition dary Structure in Chamba un it. DPO/CBA/STORAGE TANK/ A Component 2. Improved Agri POCHW /22-23 / Construction Request for Quota Single Stage - One E Other (with field f 2023-06-3 IBRD / 90410 cultural Productivity and Val Post Open - National 60,000.00 0.00 Completed 2022-08-08 2022-08-26 2022-10-12 of Storage Tank as a seconda tions nvelope or explanation) 0 ue Addition ry Structure in Chowari Unit. DPO/CBA-PLANTATION (WIN TER) /2022-23 / Raising of pl antations in the year 2022-2 3 ALD on both side of stream Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-04-3 with fast growing forestry sp IBRD / 90410 and and Water Resource Ma Post Open - National 60,000.00 0.00 Completed 2023-01-09 2023-01-30 2023-02-06 tions nvelope or explanation) 0 ecies 1100 P/Ha, having ope nagement n canopy (tree density less t han 0.4) 800 P / Ha. & increa se the forest density enrichm ent plantation 400 P / Ha. in Forest area DPO/CBA/LANTANA ERD (WI NTER)/2022-23 / Managemen Component 1. Sustainable L t of exotic species - Removal Request for Quota Single Stage - One E Other (with field f 2023-04-3 IBRD / 90410 and and Water Resource Ma Post Open - National 50,000.00 0.00 Canceled 2023-01-09 2023-01-30 of Lantana from target area tions nvelope or explanation) 0 nagement with different level of infestat ion %age by cut root stock m ethod (CRS). DPO/CBA/STORAGE TANK/ A Component 2. Improved Agri POCHM (W) /22-23 / Constru Request for Quota Single Stage - One E Other (with field f 2023-04-3 IBRD / 90410 cultural Productivity and Val Post Open - National 45,000.00 0.00 Canceled 2023-01-09 2023-01-30 ction of Storage Tank as a se tions nvelope or explanation) 0 ue Addition condary Structure in Chamba unit. DPO/CBA/STORAGE TANK/ A Component 2. Improved Agri POCHW (W) /22-23 / Constru Request for Quota Single Stage - One E Other (with field f 2023-04-3 IBRD / 90410 cultural Productivity and Val Post Open - National 45,000.00 0.00 Completed 2023-01-09 2023-01-30 2023-03-28 ction of Storage Tank as a se tions nvelope or explanation) 0 ue Addition condary Structure in Chowari unit. Page 5 DPO/CBA-SCW (W) /2022-23 / Treatment of Drainage Line s by various Soil Conservatio n works by constructing Vege Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-04-3 tative check barriers, Dry sto IBRD / 90410 and and Water Resource Ma Post Open - National 40,000.00 0.00 Completed 2023-01-09 2023-01-30 2023-02-27 tions nvelope or explanation) 0 ne check barriers, Create Wir nagement e check barriers and Cement concrete check barriers to re duce the velocity of runoff an d protection of banks. IN-DPO, CHAMBA-354786-C W-RFQ LANTANA ERD / Mana gement of exotic species - Er adication of invasive species Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 (Lantana camara ) from targ IBRD / 90410 and and Water Resource Ma Post Open - National 72,000.00 0.00 Signed 2023-04-27 2023-04-27 2023-05-16 2023-05-24 tions nvelope or explanation) 1 et areas approx 150 Ha. invol nagement ving 30 different locations wi th different level of infestatio n percentage by Cut Root Sto ck Method (CRS) during 2023 -24. IN-DPO, CHAMBA-360076-C W-RFQ NRY MAINT. / Mainten Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 ance of Nursery planting stoc IBRD / 90410 and and Water Resource Ma Post Open - National 10,000.00 0.00 Signed 2023-05-23 2023-06-13 2023-11-09 tions nvelope or explanation) 1 k (seedlings) raised during th nagement e year 2023-24 in 3 different nurseries. IN-DPO, CHAMBA-360081-C W-RFQ POND / Construction Component 1. Sustainable L of Water ponds for recharge Request for Quota Single Stage - One E Other (with field f 2024-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 7,000.00 0.00 Signed 2023-05-30 2023-06-20 2023-11-29 and providing water to the wi tions nvelope or explanation) 1 nagement ldlife of the areas. This activit y involves approx. 5 Nos cont racts. IN-DPO, CHAMBA-360085-C Component 1. Sustainable L W-RFQ SPRING / Renovation Request for Quota Single Stage - One E Other (with field f 2024-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 10,000.00 0.00 Signed 2023-06-01 2023-06-22 2024-06-20 of spring ( Water Bauries ). T tions nvelope or explanation) 1 nagement his activity involves Approx. 5 Nos. contracts. IN-DPO, CHAMBA-360086-C W-RFQ SCW / Treatment of D rainage Lines by various Soil Component 1. Sustainable L Conservation works by constr Request for Quota Single Stage - One E Other (with field f 2024-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 30,000.00 0.00 Signed 2023-06-02 2023-06-23 2023-09-28 ucting Vegetative check barri tions nvelope or explanation) 1 nagement ers, Dry stone check barriers, Create Wire check barriers a nd Cement concrete check b arriers to reduce the velocity of runoff. IN-DPO, CHAMBA-362135-C Component 1. Sustainable L W-RFQ PLT 2023-24 / Raising Request for Quota Single Stage - One E Other (with field f 2024-04-1 IBRD / 90410 and and Water Resource Ma Post Open - National 90,000.00 0.00 Signed 2023-06-12 2023-07-03 2023-07-12 of plantations (apprx.70 Ha. tions nvelope or explanation) 1 nagement ) in the year 2023-24 in the entire district. IN-DPO, CHAMBA-360071-C W-RFQ SWHS CBA / Construc Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 tion of secondary storage Ta IBRD / 90410 cultural Productivity and Val Post Open - National 90,000.00 0.00 Signed 2023-05-29 2023-06-19 2023-12-28 tions nvelope or explanation) 1 nk for Gravity Scheme involvi ue Addition ng approx. 10 different locati ons under APO Chamba IN-DPO, CHAMBA-360075-C W-RFQ SWHS CHW / Constru Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 ction of secondary storage t IBRD / 90410 cultural Productivity and Val Post Open - National 90,000.00 0.00 Signed 2023-05-29 2023-06-19 2024-07-04 tions nvelope or explanation) 1 ank for Gravity Scheme invol ue Addition ving approx. 12 different loca tions under APO Chowari IN-DPO, CHAMBA-368108-C W-RFQ 1ST MA. PLT / 1st yea Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 r maintenance of plantation ( IBRD / 90410 and and Water Resource Ma Post Open - National 13,200.00 0.00 Completed 2023-07-10 2023-07-31 2024-01-06 tions nvelope or explanation) 1 Approx. 99.50 Ha) in the yea nagement r 2023-24 in the entire distric t. IN-DPO, CHAMBA-368112-C W-RFQ 2ND MA PLT / 2nd Yea Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 r maintenance of Plantation ( IBRD / 90410 and and Water Resource Ma Post Open - National 14,000.00 0.00 Completed 2023-07-11 2023-08-01 2023-07-26 tions nvelope or explanation) 1 Approx. 164 Ha.) in the year nagement 2023-24 in the entire district. IN-DPO, CHAMBA-368113-C W-RFQ 3RD MA PLT / 3rd Yea Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 r maintenance of Plantation ( IBRD / 90410 and and Water Resource Ma Post Open - National 3,400.00 0.00 Completed 2023-07-12 2023-08-02 2023-07-14 tions nvelope or explanation) 1 Approx.) 86 Ha.) in the year nagement 2023-24 in the entire district. IN-DPO, CHAMBA-368114-C W-RFQ 1ST MA. LT / Manage ment of exotic species - Rem Component 1. Sustainable L oval of Lantana from the one Request for Quota Single Stage - One E Other (with field f 2024-04-0 IBRD / 90410 and and Water Resource Ma Post Open - National 18,200.00 0.00 Signed 2023-07-13 2023-08-03 2023-08-21 year old treated areas with di tions nvelope or explanation) 1 nagement fferent level of infestation %a ge by cut root stock method (CRS) (Approx 236.70 Ha.) in the entire district in Chamba. IN-DPO, CHAMBA-368115-C W-RFQ 2ND MA LT. / Manage ment of exotic species - Rem Component 1. Sustainable L oval of Lantana from the two Request for Quota Single Stage - One E Other (with field f 2024-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 15,600.00 0.00 Signed 2023-07-14 2023-08-04 2023-08-30 year old treated areas with di tions nvelope or explanation) 0 nagement fferent level of infestation %a ge by cut root stock method (CRS) (Approx. 238 Ha.) in th e entire district in Chamba. IN-DPO, CHAMBA-368118-C W-RFQ FOOT BRIDGE / Const ruction of Foot Bridges (Appr Component 2. Improved Agri ox. 5 Nos.) in the entire distri Request for Quota Single Stage - One E Other (with field f 2024-03-3 IBRD / 90410 cultural Productivity and Val Post Open - National 35,000.00 0.00 Signed 2023-07-08 2023-08-05 2024-02-26 ct in Chamba to improve con tions nvelope or explanation) 1 ue Addition nectivity of the farmers from poor accessibility areas with the markets for supply of inp uts and sale of produce IN-DPO, CHAMBA-368122-C W-RFQ MAKHOWAL / Constr uction of Sub Surface Dykes ( Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-2 Mackhowal) involving approx IBRD / 90410 and and Water Resource Ma Post Open - National 20,000.00 0.00 Signed 2023-07-17 2023-08-07 2023-12-04 tions nvelope or explanation) 4 . 10 different locations in the nagement entire district in Chamba to b e executed through contract ors on competitive basis. Page 6 IN-DPO, CHAMBA-368123-C W-RFQ SPRING DEV. / Renov Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 ation of spring ( Water Baurie IBRD / 90410 and and Water Resource Ma Post Open - National 12,000.00 0.00 Signed 2023-07-17 2023-08-07 2024-03-06 tions nvelope or explanation) 1 s ). This activity involves App nagement rox. 6 Nos. contracts. in the e ntire district in Chamba IN-DPO, CHAMBA-368124-C W-RFQ SWHS CHW2 / Constr Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 uction of secondary storage IBRD / 90410 cultural Productivity and Val Post Open - National 25,000.00 0.00 Signed 2023-07-10 2023-07-31 2024-02-26 tions nvelope or explanation) 1 Tank for Gravity Scheme invo ue Addition lving approx. 4 different loca tions under APO Chowari IN-DPO, CHAMBA-368125-C W-RFQ SWHS CHM2 / Constr Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 uction of secondary storage IBRD / 90410 cultural Productivity and Val Post Open - National 25,000.00 0.00 Signed 2023-07-12 2023-08-02 2024-03-14 tions nvelope or explanation) 1 Tank for Gravity Scheme invo ue Addition lving approx. 4 different locat ions under APO Chamba IN-DPO, CHAMBA-372656-C W-RFQ MAKHOWAL A / Const ruction of Sub Surface Dykes Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 (Mackhowal) involving appro IBRD / 90410 and and Water Resource Ma Post Open - National 10,000.00 0.00 Signed 2023-08-14 2023-09-05 2023-12-28 tions nvelope or explanation) 1 x. 5 different locations UNDE nagement R DPO, CHAMBA to be execu ted through contractors on c ompetitive basis. IN-DPO, CHAMBA-372660-C W-RFQ MAKHOWAL O / Const ruction of Sub Surface Dykes Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 (Mackhowal) involving appro IBRD / 90410 and and Water Resource Ma Post Open - National 10,000.00 0.00 Signed 2023-10-10 2023-10-31 2024-02-21 tions nvelope or explanation) 1 x. 5 different locations UNDE nagement R DPO, CHAMBA to be execu ted through contractors on c ompetitive basis. IN-DPO, CHAMBA-372661-C W-RFQ N / Construction of Su b Surface Dykes (Mackhowal) Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 involving approx. 10 different IBRD / 90410 and and Water Resource Ma Post Open - National 10,000.00 0.00 Signed 2023-11-13 2023-12-04 2024-03-14 tions nvelope or explanation) 1 locations UNDER DPO, CHAM nagement BA to be executed through c ontractors on competitive ba sis. IN-DPO, CHAMBA-372666-C W-RFQ CCCD / Construction o f Cement Concrete Check Da Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 m involving approx. 2 differe IBRD / 90410 and and Water Resource Ma Post Open - National 8,000.00 0.00 Signed 2023-09-25 2023-10-16 2024-03-14 tions nvelope or explanation) 1 nt locations UNDER DPO, CH nagement AMBA to be executed throug h contractors on competitive basis. IN-DPO, CHAMBA-372669-C W-RFQ CCCD NOV / Construc tion of Cement Concrete Che Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 ck Dam involving approx. 2 d IBRD / 90410 and and Water Resource Ma Post Open - National 8,000.00 0.00 Completed 2023-11-06 2023-11-27 2024-02-03 tions nvelope or explanation) 1 ifferent locations UNDER DPO nagement , CHAMBA to be executed thr ough contractors on competit ive basis. IN-DPO, CHAMBA-372671-C W-RFQ SWHS AUG. / Constru ction of secondary storage T Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-04-0 ank for Gravity Scheme invol IBRD / 90410 cultural Productivity and Val Post Open - National 21,000.00 0.00 Signed 2023-08-18 2023-09-08 2024-01-24 tions nvelope or explanation) 7 ving approx. 5 different locati ue Addition ons UNDER DPO, CHAMBA to be executed through contrac tors on competitive basis. IN-DPO, CHAMBA-372674-C W-RFQ SHWS SEP / Construct ion of secondary storage Tan Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 k for Gravity Scheme involvin IBRD / 90410 cultural Productivity and Val Post Open - National 21,000.00 0.00 Signed 2023-09-13 2023-10-04 2024-01-24 tions nvelope or explanation) 1 g approx. 5 different location ue Addition s UNDER DPO, CHAMBA to be executed through contractor s on competitive basis. IN-DPO, CHAMBA-372677-C W-RFQ SWHS OCT / Construc tion of secondary storage Ta Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 nk for Gravity Scheme involvi IBRD / 90410 cultural Productivity and Val Post Open - National 21,000.00 0.00 Completed 2023-10-16 2023-11-06 2024-03-14 tions nvelope or explanation) 1 ng approx. 5 different locatio ue Addition ns UNDER DPO, CHAMBA to b e executed through contract ors on competitive basis. IN-DPO, CHAMBA-372678-C W-RFQ SWHS NOV. / Constru ction of secondary storage T Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 ank for Gravity Scheme invol IBRD / 90410 cultural Productivity and Val Post Open - National 21,000.00 0.00 Signed 2023-11-07 2023-11-28 2024-03-14 tions nvelope or explanation) 1 ving approx. 5 different locati ue Addition ons UNDER DPO, CHAMBA to be executed through contrac tors on competitive basis. IN-DPO, CHAMBA-372681-C W-RFQ SWHS DEC. / Constru ction of secondary storage T Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 ank for Gravity Scheme invol IBRD / 90410 cultural Productivity and Val Post Open - National 21,000.00 0.00 Signed 2023-12-05 2023-12-26 2024-03-14 tions nvelope or explanation) 1 ving approx. 5 different locati ue Addition ons UNDER DPO, CHAMBA to be executed through contrac tors on competitive basis. IN-DPO, CHAMBA-372684-C W-RFQ SCW 2 / Construction Component 1. Sustainable L of Soil conservation works ap Request for Quota Single Stage - One E Other (with field f 2024-05-3 IBRD / 90410 and and Water Resource Ma Post Open - National 30,000.00 0.00 Signed 2023-09-15 2023-10-06 2024-03-14 prox. 10 different locations U tions nvelope or explanation) 1 nagement NDER DPO, CHAMBA to be e xecuted through contractors on competitive basis. IN-DPO, CHAMBA-372758-C W-RFQ KUHL AUG / For the Li ning of Irrigation Channel (Ku Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 hl) involving approx. 4differe IBRD / 90410 cultural Productivity and Val Post Open - National 10,000.00 0.00 Signed 2023-08-21 2023-09-11 2023-12-04 tions nvelope or explanation) 1 nt locations UNDER DPO, CH ue Addition AMBA to be executed throug h contractors on competitive basis. Page 7 IN-DPO, CHAMBA-372762-C W-RFQ KUHL SEP. / For the Li ning of Irrigation Channel (Ku Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 hl) involving approx. 4 differe IBRD / 90410 cultural Productivity and Val Post Open - National 10,000.00 0.00 Signed 2023-09-25 2023-10-16 2024-01-24 tions nvelope or explanation) 1 nt locations UNDER DPO, CH ue Addition AMBA to be executed throug h contractors on competitive basis. IN-DPO, CHAMBA-372764-C W-RFQ FBRIDGE AUG / C/o of Foot Bridges (Approx. 3 Nos.) UNDER DPO, CHAMBA to imp Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 rove connectivity of the farm IBRD / 90410 cultural Productivity and Val Post Open - National 13,000.00 0.00 Signed 2023-08-21 2023-09-11 2024-02-26 tions nvelope or explanation) 1 ers from poor accessibility ar ue Addition eas with the markets for sup ply of inputs and sale of prod uce to be executed through c ontractors on competitive ba sis IN-DPO, CHAMBA-372768-C W-RFQFBRIDGE SEP / C/o of F oot Bridges (Approx. 3 Nos.) UNDER DPO, CHAMBA to imp Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 rove connectivity of the farm IBRD / 90410 cultural Productivity and Val Post Open - National 12,000.00 0.00 Signed 2023-09-20 2023-10-11 2024-02-26 tions nvelope or explanation) 1 ers from poor accessibility ar ue Addition eas with the markets for sup ply of inputs and sale of prod uce to be executed through c ontractors on competitive ba sis IN-DPO, CHAMBA-373492-C W-RFQ SCW 3 / Construction Component 1. Sustainable L of Soil conservation works ap Request for Quota Single Stage - One E Other (with field f 2024-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 20,000.00 0.00 Signed 2023-12-05 2023-12-26 2024-02-03 prox. 8 different locations UN tions nvelope or explanation) 1 nagement DER DPO, CHAMBA to be ex ecuted through contractors o n competitive basis. IN-DPO, CHAMBA-383272-C W-RFQ LANTANA OCT / Mana gement of exotic species - Er adication of invasive species Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-05-1 (Lantana camara ) from targ IBRD / 90410 and and Water Resource Ma Post Open - National 18,000.00 0.00 Signed 2023-10-09 2023-10-30 2024-03-14 tions nvelope or explanation) 8 et areas approx 30 Ha. in 4 d nagement ifferent locations with differe nt level of infestation percent age by Cut Root Stock Metho d (CRS) during 2023-24. IN-DPO, CHAMBA-383273-C W-RFQ PLT (W) / Raising of Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 winter plantations (apprx.26 IBRD / 90410 and and Water Resource Ma Post Open - National 35,000.00 0.00 Completed 2023-12-11 2024-01-01 2024-01-11 tions nvelope or explanation) 1 Ha.) in the year 2023-24 in t nagement he entire district Chamba. IN-DPO, CHAMBA-383274-C W-RFQ (NRY OCT) / Maintena Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 nce of Nursery planting stock IBRD / 90410 and and Water Resource Ma Post Open - National 12,000.00 0.00 Signed 2023-10-09 2023-10-30 2024-01-11 tions nvelope or explanation) 1 (seedlings) raised during the nagement year 2023-24 in 3 different n urseries. IN-DPO, CHAMBA-383275-C W-RFQ CONTOUR / Planting o f Grass Tufts along Draining L Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2024-03-3 ine and contour trenches in p IBRD / 90410 and and Water Resource Ma Post Open - National 19,500.00 0.00 Completed 2023-10-09 2023-10-30 2024-02-03 tions nvelope or explanation) 1 lantation areas (96 Ha. Appro nagement x.) to conserve moisture and enhance availability of grass es during 2023-24 IN-DPO, CHAMBA-383279-C W-RFQ (RRWHS) / Constructi Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2024-03-3 on of Roof Rain Water Harves IBRD / 90410 cultural Productivity and Val Post Open - National 25,000.00 0.00 Signed 2023-10-09 2023-10-30 2024-03-14 tions nvelope or explanation) 1 ting Structure in 5 different l ue Addition ocations (Approx.) under DP O Chamba. IN-DPO, CHAMBA-427170-C W-RFQ NRY MAINT / Mainten Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 ance of Nursery planting stoc IBRD / 90410 and and Water Resource Ma Post Open - National 10,000.00 0.00 2024-07-15 2024-08-05 tions nvelope or explanation) lementation 1 k (seedlings) raised during th nagement e year 2024-25 under DPO C hamba IN-DPO, CHAMBA-427172-C Component 1. Sustainable L W-RFQ 1ST MNT PLT / 1st ye Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 12,500.00 0.00 2024-07-15 2024-08-05 ar maintenance of plantation tions nvelope or explanation) lementation 1 nagement s in the year 2024-25 under DPO Chamba IN-DPO, CHAMBA-427182-C W-RFQ SCW / Treatment of D rainage Lines by various Soil Conservation works by constr Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-04-1 ucting Vegetative check barri IBRD / 90410 and and Water Resource Ma Post Open - National 40,000.00 0.00 2024-07-15 2024-08-05 tions nvelope or explanation) lementation 2 ers, Dry stone check barriers, nagement Create Wire check barriers a nd Cement concrete check b arriers to reduce the velocity of runoff under DPO Chamba dr 24-25 IN-DPO, CHAMBA-427183-C Component 1. Sustainable L W-RFQ SPRING / Renovation Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 10,000.00 0.00 2024-07-15 2024-08-05 of spring ( Water Bauries ) un tions nvelope or explanation) lementation 1 nagement der DPO Chamba during 202 4-25 IN-DPO, CHAMBA-427185-C W-RFQ LANTANA ERD / Mana Component 1. Sustainable L gement of exotic species - Er Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 50,000.00 0.00 2024-07-15 2024-08-05 adication of invasive species tions nvelope or explanation) lementation 1 nagement (Lantana camara ) by Cut Ro ot Stock Method (CRS) during 2024-25 under DPO Chamba. IN-DPO, CHAMBA-427187-C W-RFQ POND / Construction Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 of Water ponds for recharge IBRD / 90410 and and Water Resource Ma Post Open - National 5,000.00 0.00 2024-07-15 2024-08-05 tions nvelope or explanation) lementation 1 and providing water to the wi nagement ldlife of the areas under DPO Chamba IN-DPO, CHAMBA-427190-C Component 1. Sustainable L W-RFQ MAKHOWAL / Constru Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 15,000.00 0.00 2024-07-15 2024-08-05 ction of Sub Surface Dykes ( tions nvelope or explanation) lementation 1 nagement Mackhowal) under APO Chow ari Page 8 IN-DPO, CHAMBA-427194-C Component 2. Improved Agri W-RFQ TANK / Construction o Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 cultural Productivity and Val Post Open - National 30,000.00 0.00 2024-07-15 2024-08-05 f secondary storage Tank for tions nvelope or explanation) lementation 1 ue Addition Gravity Scheme under APO C howari IN-DPO, CHAMBA-427196-C Component 2. Improved Agri W-RFQ KUHL / For the Lining Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 cultural Productivity and Val Post Open - National 15,000.00 0.00 2024-07-15 2024-08-05 of Irrigation Channel (Kuhl) u tions nvelope or explanation) lementation 1 ue Addition nder DPO Chamba IN-DPO, CHAMBA-427197-C Component 2. Improved Agri W-RFQ BRIDGES / C/o Foot Br Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 cultural Productivity and Val Post Open - National 25,000.00 0.00 2024-07-15 2024-08-05 idges during the year 2024-2 tions nvelope or explanation) lementation 1 ue Addition 5 under APO Chowari IN-DPO, CHAMBA-434735-C Component 1. Sustainable L W-RFQ 2 MAINT PLT / 2nd ye Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 9,500.00 0.00 2024-07-15 2024-08-05 ar maintenance of plantation tions nvelope or explanation) lementation 1 nagement s in the year 2024-25 under DPO Chamba IN-DPO, CHAMBA-434739-C Component 1. Sustainable L W-RFQ 3 MAINT PLT / 3rd yea Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 8,000.00 0.00 2024-07-15 2024-08-05 r maintenance of plantations tions nvelope or explanation) lementation 1 nagement in the year 2024-25 under DP O Chamba IN-DPO, CHAMBA-434740-C W-RFQ 1ST LANTANA / Mana Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 gement of exotic species - Re IBRD / 90410 and and Water Resource Ma Post Open - National 11,800.00 0.00 2024-07-15 2024-08-26 tions nvelope or explanation) lementation 1 moval of Lantana from the o nagement ne year old treated areas un der DPO Chamba. IN-DPO, CHAMBA-434741-C W-RFQ 2NDLANTANA / Mana Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 gement of exotic species - Re IBRD / 90410 and and Water Resource Ma Post Open - National 16,500.00 0.00 2024-07-15 2024-08-05 tions nvelope or explanation) lementation 1 moval of Lantana from the t nagement wo year old treated areas un der DPO Chamba. IN-DPO, CHAMBA-436328-C Component 1. Sustainable L W-RFQ MAKHOWAL 2 / Const Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 12,000.00 0.00 2024-07-20 2024-08-10 ruction of Sub Surface Dykes tions nvelope or explanation) lementation 1 nagement (Mackhowal) under APO Cha mba IN-DPO, CHAMBA-436329-C Component 2. Improved Agri W-RFQ TANK 2 / Construction Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 cultural Productivity and Val Post Open - National 24,000.00 0.00 2024-07-20 2024-08-10 of secondary storage Tank fo tions nvelope or explanation) lementation 1 ue Addition r Gravity Scheme under APO Chamba IN-DPO, CHAMBA-436330-C Component 2. Improved Agri W-RFQ BRIDGE 2 / C/o Foot B Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 cultural Productivity and Val Post Open - National 24,000.00 0.00 2024-07-15 2024-08-05 ridges during the year 2024- tions nvelope or explanation) lementation 1 ue Addition 25 under APO Chamba IN-DPO, CHAMBA-446455-C W-RFQ LANTANA SEP / Mana gement of exotic species - Er adication of invasive species Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 (Lantana camara ) from targ IBRD / 90410 and and Water Resource Ma Post Open - National 60,000.00 0.00 2024-09-09 2024-09-30 tions nvelope or explanation) lementation 1 et areas approx 100 Ha. invol nagement ving 20 different locations wi th different level of infestatio n percentage by Cut Root Sto ck Method (CRS) during 2023 -24. IN-DPO, CHAMBA-446480-C W-RFQ DRY SEP / Treatment of Drainage Lines by various Soil Conservation works by c Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 onstructing Vegetative check IBRD / 90410 and and Water Resource Ma Post Open - National 90,000.00 0.00 2024-09-08 2024-09-29 tions nvelope or explanation) lementation 1 barriers, Dry stone check bar nagement riers, Create Wire check barri ers and Cement concrete che ck barriers to reduce the velo city of runoff under DPO Cha mba dr 24-25 IN-DPO, CHAMBA-446484-C Component 2. Improved Agri W-RFQ BRIDGE SEP / C/o Foo Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 cultural Productivity and Val Post Open - National 60,000.00 0.00 2024-09-08 2024-10-13 t Bridges during the year 202 tions nvelope or explanation) lementation 1 ue Addition 4-25 under DPO Chamba IN-DPO, CHAMBA-446486-C W-RFQ MAKHOWAL SP / Cons Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 truction of Sub Surface Dyke IBRD / 90410 and and Water Resource Ma Post Open - National 60,000.00 0.00 2024-09-08 2024-09-29 tions nvelope or explanation) lementation 1 s (Mackhowal) involving appr nagement ox. 20 different locations UN DER DPO, CHAMBA IN-DPO, CHAMBA-446491-C Component 2. Improved Agri W-RFQ TANK SEP / Constructi Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 cultural Productivity and Val Post Open - National 90,000.00 0.00 2024-09-08 2024-09-29 on of secondary storage Tan tions nvelope or explanation) lementation 1 ue Addition k for Gravity Scheme under DPO Chamba IN-DPO, CHAMBA-446498-C Component 1. Sustainable L W-RFQ POND SEP / Conserva Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 20,000.00 0.00 2024-09-08 2024-09-29 tion and management of fres tions nvelope or explanation) lementation 1 nagement hwater ponds and lakes and rivers and streams IN-DPO, CHAMBA-446501-C Component 2. Improved Agri W-RFQ RRHWS / Construction Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 cultural Productivity and Val Post Open - National 35,000.00 0.00 2024-09-08 2024-09-29 of Roof Rain Water Harvestin tions nvelope or explanation) lementation 1 ue Addition g Structure under DPO Cham ba IN-DPO, CHAMBA-446519-C Component 2. Improved Agri W-RFQ KUHL SEP / For the re Request for Quota Single Stage - One E Other (with field f Pending Imp 2025-03-3 IBRD / 90410 cultural Productivity and Val Post Open - National 50,000.00 0.00 2024-09-08 2024-09-29 novatio of Irrigation Channel tions nvelope or explanation) lementation 1 ue Addition (Kuhl) under DPO Chamba GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DPOIDPCBA/PROC/PBAGS/ 7 Component 1. Sustainable L Request for Quota Single Stage - One E 78-81/13-1-20 / Procurement IBRD / 90410 and and Water Resource Ma Post Limited 4,400.00 4,152.11 Completed 2020-02-09 2020-01-13 2020-02-28 2020-02-15 2020-08-26 2020-02-23 tions nvelope of Nursery bags nagement Page 9 DPO/CBA/B/WIRE(W)/2020-2 1 / Procurement of Barbed Wi Component 1. Sustainable L Request for Quota Single Stage - One E re for fencing of the plantatio IBRD / 90410 and and Water Resource Ma Post Limited 19,000.00 10,095.38 Completed 2020-10-30 2020-12-22 2020-11-15 2021-02-15 2021-03-31 2021-03-10 tions nvelope n areas to be planted in the nagement winter planting season of 20 20-21. IN-DPO, CHAMBA-RFQ- RABI- DEMO / Procurement of whea Component 2. Improved Agri t / vegetable seeds, fertilizer, Request for Quota Single Stage - One E IBRD / 90410 cultural Productivity and Val Post Limited 2,000.00 0.00 Canceled 2020-12-11 2021-01-01 2021-03-31 weedicides & insecticides for tions nvelope ue Addition demonstration of wheat crop on the farmers fields during r abi season of the year 2020- 21. DPO/CBA/F/POST(W)/2020-2 Component 1. Sustainable L 1 / Procurement of Eucalyptu Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 41,000.00 11,431.67 Completed 2020-10-27 2020-11-02 2020-11-18 2021-03-10 2021-03-31 2021-03-10 s Fence post for fencing of pl tions nvelope nagement antation during winter 2020- 21 DPO-CBA-NRY SEED - 2021-2 Component 1. Sustainable L Request for Quota Single Stage - One E 2 / Procurement of forest see IBRD / 90410 and and Water Resource Ma Post Limited 2,000.00 0.00 Completed 2021-10-05 2021-12-05 2021-11-29 2021-12-05 2022-03-31 2022-02-15 tions nvelope ds for raising nurseries durin nagement g the 2021-22 DPO-CBA-NRY FYM-2020-21 Component 1. Sustainable L / Procurement of Farm Yard Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 3,500.00 0.00 Canceled 2021-10-05 2021-10-25 2022-04-23 Manure & Vermi Compost for tions nvelope nagement raising nurseries during the 2 021-22 DPO-CBA-NRY SAND-2021-2 Component 1. Sustainable L Request for Quota Single Stage - One E 2 / Procurement of Sand for r IBRD / 90410 and and Water Resource Ma Post Limited 3,500.00 0.00 Completed 2021-10-05 2022-01-15 2021-10-25 2022-02-07 2022-03-31 2022-03-10 tions nvelope aising nurseries during the 2 nagement 021-22 DPO-CBA-NRY BAGS-2021-2 Component 1. Sustainable L 2 / Procurement of Nursery B Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 4,000.00 432.74 Completed 2021-10-02 2021-02-21 2021-10-23 2022-03-23 2022-03-31 2022-03-28 ags for raising nurseries duri tions nvelope nagement ng the financial year 2021-22 . DPO-CBA-PRY WATER DISTR- 2021-22 / This activity involv es the distribution of water fr Component 2. Improved Agri Request for Quota Single Stage - One E om the primary water harves IBRD / 90410 cultural Productivity and Val Post Limited 68,000.00 0.00 Canceled 2021-07-03 2021-07-30 2022-03-31 tions nvelope ting structure created under ue Addition component One to a seconda ry water storage structure co nstructed on private / comm unity land. DPO-CBA-DEMONSTRATION- 2021-22 / Procurement of im proved varieties of cereals, Component 2. Improved Agri pulses, spices, vegetable & Request for Quota Single Stage - One E IBRD / 90410 cultural Productivity and Val Post Limited 15,000.00 0.00 Completed 2021-05-07 2022-01-23 2021-05-29 2021-10-29 2022-03-31 2021-10-29 other high value crops seeds, tions nvelope ue Addition fertilizer, weedicides & insect icides for demonstration on t he farmers fields during the y ear 2021-22. DPO-CBA FLOCK MANAGEME NT-2021-22 / The Procureme Component 2. Improved Agri nt of Tarpaulins, drenching g Request for Quota Single Stage - One E IBRD / 90410 cultural Productivity and Val Post Limited 30,000.00 0.00 Canceled 2021-05-07 2021-05-29 2022-03-31 uns, castrators, Chaff Cutters tions nvelope ue Addition etc. for communities in proje ct areas involved in livestock rearing during the year 2021- 22. DPO-CBA-B WIRE-2021-22 / Component 1. Sustainable L Procurement of Barbed Wire Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 30,000.00 0.00 Completed 2021-05-07 2021-07-31 2021-05-29 2022-03-27 2022-03-31 2022-03-27 for fencing of the plantation tions nvelope nagement areas to be planted in the pla nting season of 2021-22. DPO-IDP-F POST -2021-22 / P Component 1. Sustainable L rocurement of Eucalyptus Fe Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 15,000.00 0.00 Completed 2021-05-07 2021-11-20 2021-05-29 2021-07-28 2022-03-31 2021-08-02 nce post for fencing of planta tions nvelope nagement tion during the year 2021-22. DPO-CBA-SEC. WATER DISTR -2021-22 / Installation of wat er distribution system to the Component 2. Improved Agri Request for Quota Single Stage - One E farmers field from the secon IBRD / 90410 cultural Productivity and Val Post Limited 30,000.00 0.00 Canceled 2021-08-04 2021-08-26 2022-03-31 tions nvelope dary storage tanks by way of ue Addition sprinklers, water pipes, drip i rrigation system etc., for the year 2021-22. DPO-CBA-TAP SHEARING MA Component 2. Improved Agri CHINE -2021-22 / The Procur Request for Quota Single Stage - One E IBRD / 90410 cultural Productivity and Val Post Open - National 11,000.00 0.00 Canceled 2022-02-28 2022-03-16 2022-06-30 ement of sheep Shearing Ma tions nvelope ue Addition chine for transhumant under Tribal Action Plan. DPO/CBA/BWIRE/2022-23 / P Component 1. Sustainable L rocurement of Barbed Wire f Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 15,000.00 0.00 Completed 2022-06-13 2022-06-30 2022-07-05 2022-07-30 2022-07-30 or fencing of the plantation a tions nvelope nagement reas to be planted in the plan ting season of 2022-23. DPO/CBA/F.POST/2022-23 / P Component 1. Sustainable L rocurement of Eucalyptus Fe Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 10,500.00 0.00 Completed 2022-06-13 2022-06-30 2022-08-16 2022-07-30 2022-08-16 nce post for fencing of planta tions nvelope nagement tion during the year 2022-23. DPO/CBA/FORESTRY SEED / Component 1. Sustainable L 2022-23 / Procurement of for Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 700.00 0.00 Completed 2022-07-04 2022-07-21 2023-02-15 2023-01-17 2023-02-16 est seeds for raising nurserie tions nvelope nagement s during the 2022-23 DPO/CBA/NRY BAGS/2022-2 Component 1. Sustainable L 3 / Procurement of Nursery B Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 3,000.00 0.00 Completed 2022-07-04 2022-07-25 2023-01-27 2023-03-31 2023-02-04 ags for raising nurseries duri tions nvelope nagement ng the financial year 2022-23 DPO/CBA/NRY SAND/2022-2 Component 1. Sustainable L Request for Quota Single Stage - One E 3 / Procurement of Sand for r IBRD / 90410 and and Water Resource Ma Post Open - National 1,350.00 0.00 Completed 2022-07-18 2022-09-08 2023-02-04 2023-06-30 2023-02-06 tions nvelope aising nurseries during the 2 nagement 022-23. DPO/CBA/FENCING MATERIA L/2022-23 / Procurement of B Component 1. Sustainable L Request for Quota Single Stage - One E arbed Wire & Fence Post for f IBRD / 90410 and and Water Resource Ma Post Open - National 15,000.00 0.00 Completed 2023-01-09 2023-01-30 2022-06-29 2023-04-30 2022-06-29 tions nvelope encing of the plantation area nagement s to be planted in the winter planting season of 2022-23. Page 10 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 11