PROCUREMENT PLAN (Textual Part) Project information: Pakistan Higher Education Development Project P- 161386 Project Implementation agency: Higher Education Commission Date of the Procurement Plan: May 15, 2019 Period covered by this Procurement Plan: May 15, 2019- May 15, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) Revised November 2017 and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Rules 2004, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable s] PROCUREMENT Pakistan : Higher Education Development in Pakistan PLAN General Information Country: Pakistan 2019-09-13 Bank’s Approval Date of the Original Procurement Plan: 2024-08-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161386 GPN Date: 2019-05-14 Project Name: Higher Education Development in Pakistan Loan / Credit No: IDA / 64380 Higher Education Commission Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-123692-GO-RFB / Ex Supporting Decentralized Hi pansion the PERN connectivit IDA / 64380 gher Education Institutes for Prior Direct Selection Direct 12,120,000.00 0.00 Canceled 2019-11-15 2019-11-20 2019-12-25 2020-06-22 y to Affiliated Colleges of Pak Improved Teaching and Lear istan ning PK-HEC-123699-GO-RFB / Pr Supporting Decentralized Hi Single Stage - One E ovisioning of Power backups IDA / 64380 gher Education Institutes for Prior Request for Bids Open - National 2,118,000.00 0.00 Canceled 2019-11-15 2019-11-20 2020-01-01 2020-01-31 2020-03-06 2020-09-02 nvelope related to PERN expansion Improved Teaching and Lear ning PK-HEC-133940-GO-RFP / Inf Equipping Students and Hig Request for Propo Open - Internationa rastructure to setup High Per IDA / 64380 her Education Institutions wi Prior Multi Stage 6,700,000.00 0.00 Canceled 2019-11-15 2019-11-20 2020-01-29 2020-06-16 2021-12-08 sals l formance Compute Services th Modern Technology under PERN PK-HEC-133944-GO-RFB / Eq Supporting Decentralized Hi uipping Colleges with Next G gher Education Institutes for Single Stage - Two E IDA / 64380 Prior Request for Bids Open - National 11,900,000.00 0.00 Canceled 2019-11-15 2019-11-20 2020-01-01 2020-03-15 2020-04-19 2020-10-16 eneration Networks and Audi Improved Teaching and Lear nvelope o/Video Technology ning Higher Education Manageme PK-HEC-133946-GO-RFP / ER Request for Propo Open - Internationa IDA / 64380 nt Information System and D Prior Multi Stage 19,500,000.00 0.00 Canceled 2019-11-15 2019-11-20 2020-01-29 2020-05-12 2020-06-16 2021-12-08 P Solution for HEIs sals l ata Driven Services PK-HEC-133994-GO-RFB / Ha Higher Education Manageme Open - Internationa Single Stage - Two E rdware Infrastructure for Digi IDA / 64380 nt Information System and D Prior Request for Bids 11,800,000.00 0.00 Canceled 2020-02-01 2020-02-06 2020-03-19 2020-06-01 2020-07-06 2021-01-02 l nvelope tization of Universities ata Driven Services PK-HEC-123673-CS-QCBS / D Higher Education Manageme evelopment of the Tool, Impl Single Stage - One E IDA / 64380 nt Information System and D Post Request for Bids Open - National 880,000.00 0.00 Canceled 2019-09-16 2019-09-21 2019-11-02 2019-12-02 2020-01-06 2020-07-04 ementation and Training for nvelope ata Driven Services Data Repository Portal. PK-HEC-123702-GO-RFB / Es Supporting Decentralized Hi Open - Internationa Single Stage - One E tablishment of Smart Classro IDA / 64380 gher Education Institutes for Prior Request for Bids 5,820,000.00 0.00 Canceled 2019-11-01 2019-11-06 2019-12-18 2020-01-17 2020-02-21 2023-12-31 l nvelope oms in Universities and Affilia Improved Teaching and Lear ted Colleges ning PK-HEC-133948-GO-RFP / St Higher Education Manageme Request for Propo Open - Internationa udent Life Cycle Solution for IDA / 64380 nt Information System and D Prior Multi Stage 36,600,000.00 0.00 Canceled 2019-11-15 2019-11-20 2020-01-29 2020-05-12 2020-06-16 2021-12-08 sals l HEIs ata Driven Services PK-HEC-133936-GO-RFP / Inf Equipping Students and Hig Request for Propo Open - Internationa Single Stage - Two E rastructure for the establish IDA / 64380 her Education Institutions wi Prior 8,700,000.00 0.00 Canceled 2019-12-15 2019-12-20 2020-01-31 2020-04-14 2020-05-19 2021-05-19 sals l nvelope ment for cloud services unde th Modern Technology r PERN PK-HEC-123696-GO-DIR / Str Supporting Decentralized Hi Request for Quota Single Stage - One E engthening the PERN Backbo IDA / 64380 gher Education Institutes for Prior Limited 8,275,000.00 0.00 Canceled 2019-11-20 2020-01-15 2024-06-30 tions nvelope ne and population of IP Upstr Improved Teaching and Lear eam ning PK-HEC-211458-GO-RFP / En Higher Education Manageme Request for Propo Open - Internationa terprise Resources Planning ( IDA / 64380 nt Information System and D Prior 5,500,000.00 0.00 Canceled 2020-12-29 2021-02-03 2021-03-16 2021-10-22 2021-03-22 2022-07-28 2021-01-10 2021-03-31 2021-05-06 2021-07-16 2021-08-30 2024-05-31 sals l ERP) -3 LOTs ata Driven Services PK-HEC-211652-GO-RFP / St Higher Education Manageme Request for Propo Open - Internationa udent Life Cycle Solution (SL IDA / 64380 nt Information System and D Prior 9,375,000.00 0.00 Canceled 2020-12-29 2021-02-03 2021-03-16 2021-12-14 2021-03-22 2022-07-28 2021-01-10 2021-03-30 2021-05-06 2021-07-16 2021-08-30 2024-05-31 sals l CS) -3 LOTS ata Driven Services PK-HEC-217178-GO-RFB / O Nurturing Academic Excellen Open - Internationa Single Stage - One E IDA / 64380 Post Request for Bids 600,000.00 565,442.32 Signed 2021-02-02 2021-03-04 2021-03-09 2021-03-10 2021-04-22 2021-04-22 2021-05-22 2021-12-21 2021-06-26 2022-03-24 2021-12-23 RICs / BICs Automation Platfo ce in Strategic Sectors l nvelope rm Capacity Building through Pa PK-HEC-223795-GO-RFQ / Su Request for Quota Single Stage - One E IDA / 64380 rtnerships, Project Managem Post Open - National 60,000.00 37,169.19 Signed 2021-03-19 2021-04-06 2021-04-27 2021-06-28 2021-05-27 pply of IT/Office Equipment tions nvelope ent, Monitoring and Evaluati on PK-HEC-291120-GO-DIR / Su Equipping Students and Hig Pending Impl rvey & Experience Managem IDA / 64380 her Education Institutions wi Post Direct Selection Direct 125,000.00 0.00 2022-04-22 2022-05-02 2022-05-27 2024-05-26 ementation ent Software th Modern Technology PK-HEC-334177-GO-DIR / Lic Equipping Students and Hig Pending Impl ense Procurement for SAP ER IDA / 64380 her Education Institutions wi Post Direct Selection Direct - National 355,000.00 0.00 2022-12-30 2023-01-04 2023-02-08 2023-08-07 ementation P Upgrade at HEC th Modern Technology Capacity Building through Pa PK-HEC-345535-GO-RFQ / Pr Request for Quota Single Stage - One E Under Imple IDA / 64380 rtnerships, Project Managem Post Open - National 40,000.00 0.00 2023-03-10 2023-03-30 2023-05-06 2023-06-05 ocurement of Laptops tions nvelope mentation ent, Monitoring and Evaluati on PK-HEC-347464-GO-RFB / De Equipping Students and Hig Open - Internationa Single Stage - One E sign, Supply and Installation IDA / 64380 her Education Institutions wi Prior Request for Bids 6,000,000.00 0.00 Signed 2023-03-10 2023-04-19 2023-03-17 2023-04-20 2023-05-01 2023-06-08 2023-05-31 2023-10-10 2023-06-29 2023-12-07 2023-12-26 l nvelope of Data Center POD and its C th Modern Technology omponents PK-HEC-352912-GO-RFB / Pr Equipping Students and Hig ocurement of Hardware and Open - Internationa Single Stage - One E IDA / 64380 her Education Institutions wi Prior Request for Bids 17,000,000.00 0.00 Signed 2023-03-31 2023-06-23 2023-04-07 2023-08-11 2023-05-22 2023-08-28 2023-06-21 2024-03-01 2023-07-26 2024-07-10 2024-05-31 Enterprise Resource Planning l nvelope th Modern Technology and Student Life Cycle Syste m (ERP/ SLCS) Page 1 PK-HEC-352924-GO-RFB / Su Equipping Students and Hig Open - Internationa Single Stage - One E pply and Installation of Datac IDA / 64380 her Education Institutions wi Prior Request for Bids 4,000,000.00 0.00 Signed 2023-03-30 2023-04-05 2023-04-06 2023-04-05 2023-05-21 2023-05-25 2023-06-20 2023-07-07 2023-07-25 2023-09-22 2023-11-02 l nvelope enter Network Components th Modern Technology PK-HEC-363822-GO-RFB / Up Equipping Students and Hig Single Stage - One E Under Imple gradation of ERP Solution at IDA / 64380 her Education Institutions wi Post Request for Bids Open - National 700,000.00 0.00 2023-05-30 2023-06-01 2023-06-05 2023-07-12 2023-06-27 2023-07-31 2023-07-27 2023-12-03 2023-08-25 2024-05-31 nvelope mentation HEC th Modern Technology PK-HEC-369008-GO-RFB / Pr Equipping Students and Hig Open - Internationa Single Stage - One E ocurement of Edge and IP Su IDA / 64380 her Education Institutions wi Prior Request for Bids 4,000,000.00 0.00 Signed 2023-06-30 2023-07-12 2023-07-10 2023-08-23 2023-08-24 2023-10-11 2023-09-23 2024-01-26 2023-10-22 2024-06-30 l nvelope rveillance Equipment th Modern Technology PK-HEC-369013-GO-RFB / Pr Equipping Students and Hig Open - Internationa Single Stage - One E ocurement of Video Conferen IDA / 64380 her Education Institutions wi Prior Request for Bids 3,500,000.00 0.00 Signed 2023-06-30 2023-07-12 2023-07-10 2023-10-04 2023-08-24 2023-10-19 2023-09-23 2024-01-26 2023-10-22 2024-06-24 l nvelope cing Equipment th Modern Technology PK-HEC-378804-GO-RFQ / Pr Capacity Building through Pa Request for Quota Single Stage - One E Under Imple ocurement of IT and Office E IDA / 64380 rtnerships, Project Managem Post Open - National 50,000.00 0.00 2023-09-10 2024-04-19 2023-10-21 2023-11-30 tions nvelope mentation quipment ent, Monitoring and Evaluati on PK-HEC-383819-GO-RFB / Pr Equipping Students and Hig ocurement of Hardware for C Open - Internationa Single Stage - One E Under Imple IDA / 64380 her Education Institutions wi Prior Request for Bids 12,500,000.00 0.00 2023-10-05 2023-11-15 2023-10-25 2024-01-15 2023-12-09 2024-01-30 2024-01-28 2024-07-19 2024-03-08 2024-06-06 loud, High-Performance Com l nvelope mentation th Modern Technology puting and Network Security PK-HEC-384774-GO-RFP / Pr Equipping Students and Hig ocurement of Software and S Request for Propo Open - Internationa Single Stage - Two E Under Imple IDA / 64380 her Education Institutions wi Prior 6,000,000.00 0.00 2023-10-06 2024-05-14 2023-10-26 2024-07-22 2023-12-10 2024-08-06 2024-02-28 2024-04-09 2024-06-18 ervices for Cloud and High-Pe sals l nvelope mentation th Modern Technology rformance Computing PK-HEC-384782-GO-RFP / Pr Equipping Students and Hig Request for Propo Open - Internationa Single Stage - Two E Under Imple ocurement of Software and S IDA / 64380 her Education Institutions wi Prior 3,000,000.00 0.00 2023-10-04 2023-11-14 2023-10-19 2024-02-02 2023-12-03 2024-02-14 2024-02-21 2024-08-21 2024-04-01 2024-06-10 sals l nvelope mentation ervices for Network Security th Modern Technology and Monitoring PK-HEC-384874-GO-DIR / Pro Equipping Students and Hig curement of Hardware for PE IDA / 64380 her Education Institutions wi Prior Direct Selection Direct - National 3,000,000.00 0.00 Signed 2023-10-05 2023-11-06 2023-10-10 2024-03-04 2023-11-09 2024-05-22 2024-01-08 RN Transmision Network Upg th Modern Technology radation PK-HEC-427563-GO-RFP / Pr Equipping Students and Hig ocurement of Software and S Request for Propo Open - Internationa Single Stage - Two E Under Imple IDA / 64380 her Education Institutions wi Prior 2,500,000.00 0.00 2024-05-22 2024-06-04 2024-06-01 2024-07-31 2024-07-21 2024-11-02 2024-12-07 2025-05-31 ervices for Learning Manage sals l nvelope mentation th Modern Technology ment System (LMS) PK-HEC-447307-GO-RFP / De Equipping Students and Hig Request for Propo Single Stage - Two E Pending Impl sign, Supply and Installation IDA / 64380 her Education Institutions wi Post Open - National 1,950,000.00 0.00 2024-09-06 2024-09-16 2024-10-11 2025-01-08 2025-02-12 2025-06-12 sals nvelope ementation of Blockchain for Documents th Modern Technology Authentication PK-HEC-447313-GO-RFP / De Equipping Students and Hig Request for Propo Single Stage - Two E Pending Impl sign, Supply and Installation IDA / 64380 her Education Institutions wi Post Open - National 1,950,000.00 0.00 2024-09-06 2024-09-16 2024-10-11 2025-01-08 2025-02-12 2025-06-12 sals nvelope ementation of Identity Access Manageme th Modern Technology nt (IAM) PK-HEC-447314-GO-RFP / De Equipping Students and Hig sign, Supply and Installation Request for Propo Single Stage - Two E Pending Impl IDA / 64380 her Education Institutions wi Post Open - National 1,200,000.00 0.00 2024-09-06 2024-09-16 2024-10-11 2025-01-08 2025-02-12 2025-06-12 of Data Warehouse and Busi sals nvelope ementation th Modern Technology ness Intelligence Platform NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-192667-NC-DIR / Ma Equipping Students and Hig ssive Open Online Courses ( IDA / 64380 her Education Institutions wi Post Direct Selection Direct 95,000.00 74,971.63 Signed 2020-09-09 2020-07-11 2020-09-14 2020-10-19 2020-10-19 2020-12-15 2022-10-19 MOOCs) Platform at HEC th Modern Technology PK-HEC-280661-NC-DIR / Hig Higher Education Manageme her Education Data Repositor IDA / 64380 nt Information System and D Post Direct Selection Direct 120,000.00 0.00 Canceled 2022-02-28 2022-03-02 2022-03-05 2022-04-24 2024-06-30 y(HEDR) , Service Level Agre ata Driven Services ement PK-HEC-378807-NC-DIR / Ass Supporting Decentralized Hi essment of Students to prep IDA / 64380 gher Education Institutes for Post Direct Selection Direct - National 100,000.00 0.00 Canceled 2023-09-01 2023-09-14 2023-09-06 2023-10-05 2023-10-01 2024-04-30 are Report on Student Learni Improved Teaching and Lear ng Outcomes ning PK-HEC-384871-NC-RFQ / Pr Capacity Building through Pa Request for Quota Single Stage - One E Under Imple oduction of High-Quality Doc IDA / 64380 rtnerships, Project Managem Post Open - National 15,000.00 0.00 2023-10-20 2023-12-03 2024-01-18 2024-02-17 tions nvelope mentation umentaries under ISF Grant ent, Monitoring and Evaluati on PK-HEC-388842-NC-RFB / Sel Equipping Students and Hig Single Stage - Two E Under Imple ection of Firm for the Develo IDA / 64380 her Education Institutions wi Post Request for Bids Open - National 1,300,000.00 0.00 2023-10-30 2024-03-12 2023-11-09 2024-04-14 2023-12-01 2024-02-09 2024-03-15 2024-05-29 nvelope mentation pment of MOOCS th Modern Technology PK-HEC-437841-NC-RFQ / Pr Capacity Building through Pa Request for Quota Single Stage - One E Under Imple ocurement of Event Manage IDA / 64380 rtnerships, Project Managem Post Open - National 80,000.00 0.00 2024-07-18 2024-09-14 2024-09-29 tions nvelope mentation ment Services for Investor Co ent, Monitoring and Evaluati nnect Event 2024 on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-123657-CS-QCBS / N Supporting Decentralized Hi eed Assessment study for de gher Education Institutes for Quality And Cost- IDA / 64380 Prior Open - National 1,000,000.00 0.00 Canceled 2019-10-15 2019-10-29 2019-12-12 2020-01-09 2020-02-08 2020-03-14 2020-04-18 2020-10-15 veloping courses for Commu Improved Teaching and Lear Based Selection nity colleges and Associates ning Degree Program PK-HEC-123665-CS-QCBS / F Supporting Decentralized Hi acilitate the implementation gher Education Institutes for Quality And Cost- of the HEC’s mandate to roll IDA / 64380 Post Open - National 600,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 Improved Teaching and Lear Based Selection out 4-year Bachelor of Scienc ning e (BS) programs and Curricul a Revision PK-HEC-123666-CS-CQS / Dr Equipping Students and Hig Consultant Qualifi afting of ICT Strategy - Consu IDA / 64380 her Education Institutions wi Post Open - National 250,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2021-02-21 cation Selection ltancy th Modern Technology Page 2 PK-HEC-123674-CS-QCBS / C Higher Education Manageme Quality And Cost- onsultants to Assist HEC in th IDA / 64380 nt Information System and D Post Open - National 600,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 Based Selection e selection of the ERP Solutio ata Driven Services n PK-HEC-123678-CS-QCBS / S upport to the ORICs and BICs Nurturing Academic Excellen Quality And Cost- IDA / 64380 Prior Open - National 2,000,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2023-04-25 for the implementation of bot ce in Strategic Sectors Based Selection h the TTSF grant and the ISF – Consultants PK-HEC-123685-CS-QCBS / S Capacity Building through Pa Quality And Cost- tudies (Tracer study, Satisfac IDA / 64380 rtnerships, Project Managem Prior Open - National 2,000,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2023-04-25 Based Selection tion survey, gender study) ent, Monitoring and Evaluati on PK-HEC-133769-CS-CQS / Co Equipping Students and Hig Consultant Qualifi Open - Internationa nsultant to help develop an i IDA / 64380 her Education Institutions wi Post 300,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-18 2020-02-22 2021-02-21 cation Selection l mproved governance system th Modern Technology for PERN Capacity Building through Pa PK-HEC-123683-CS-QCBS / T Least Cost Selecti IDA / 64380 rtnerships, Project Managem Prior Open - National 1,000,000.00 0.00 Canceled 2019-10-15 2020-05-14 2019-10-30 2019-12-13 2020-01-10 2020-02-09 2020-03-15 2020-04-19 2024-06-30 hird party verification agency on ent, Monitoring and Evaluati on PK-HEC-180837-CS-CQS / Thi Capacity Building through Pa Consultant Qualifi rd Party Verification Agency- IDA / 64380 rtnerships, Project Managem Post Open - National 350,000.00 135,759.74 Signed 2020-06-18 2020-06-18 2020-07-09 2020-06-21 2020-08-22 2020-12-09 2020-09-21 2021-02-09 2020-10-26 2021-04-12 2021-04-24 cation Selection Consulting Firm ent, Monitoring and Evaluati on PK-HEC-217177-CS-CQS / Co Nurturing Academic Excellen Consultant Qualifi nsultancy for Capacity Buildi IDA / 64380 Post Open - National 200,000.00 0.00 Canceled 2021-02-10 2021-04-05 2021-03-03 2021-04-09 2021-04-16 2021-05-16 2021-06-20 2022-12-12 ce in Strategic Sectors cation Selection ng of ORICs & BICs PK-HEC-256557-CS-CQS / Co Capacity Building through Pa nsultancy for National Acade rtnerships, Project Managem Consultant Qualifi Under Implement IDA / 64380 Post Limited 75,000.00 0.00 2021-10-05 2021-10-08 2021-10-19 2021-11-18 2021-12-23 2022-06-21 my for Higher Education(NAH ent, Monitoring and Evaluati cation Selection ation E) Strategic Planning on PK-HEC-256558-CS-CQS / Co Equipping Students and Hig Consultant Qualifi nsultancy for IT Security Asse IDA / 64380 her Education Institutions wi Post Limited 66,000.00 0.00 Canceled 2021-10-05 2021-10-08 2021-10-19 2021-11-18 2021-12-23 2022-06-21 cation Selection ssment th Modern Technology PK-HEC-256560-CS-CQS / Co Equipping Students and Hig Consultant Qualifi nsultancy for updating the Po IDA / 64380 her Education Institutions wi Post Limited 70,000.00 0.00 Canceled 2021-10-05 2021-10-08 2021-10-19 2021-11-18 2021-12-23 2022-06-21 cation Selection licy Framework for ICT th Modern Technology PK-HEC-256564-CS-QCBS / C Improving access and qualit onsultancy for Improving the Quality And Cost- Open - Internationa IDA / 64380 y of remote learning and sup Post 660,000.00 0.00 Canceled 2021-10-05 2021-10-08 2021-10-26 2021-11-16 2021-12-10 2022-10-31 2022-01-24 2022-12-15 2022-02-23 2023-01-10 2022-03-25 2022-04-22 2024-04-21 Revenue Generation of Public Based Selection l port to universities Sector Universities PK-HEC-256566-CS-CQS / Pr Higher Education Manageme Consultant Qualifi Under Implement obity Assurance Provider for IDA / 64380 nt Information System and D Post Limited 20,000.00 0.00 2021-10-05 2021-10-08 2021-10-19 2022-12-02 2021-11-02 2023-01-12 2021-11-19 2022-03-19 cation Selection ation ERP & SLCS Discovery Meetin ata Driven Services gs PK-HEC-256567-CS-QCBS / C Nurturing Academic Excellen Quality And Cost- Open - Internationa onsultancy - Innovator Seed IDA / 64380 Post 200,000.00 0.00 Canceled 2021-10-05 2021-10-26 2021-11-17 2022-01-01 2022-01-16 2022-01-30 2022-03-06 2023-09-07 ce in Strategic Sectors Based Selection l Fund Capacity Building Progr am PK-HEC-257206-CS-LCS / Co Nurturing Academic Excellen Least Cost Selecti Open - Internationa nsultancy – Innovator Seed F IDA / 64380 Post 200,000.00 190,486.95 Signed 2021-10-07 2021-10-07 2021-10-28 2021-10-16 2021-11-14 2021-12-17 2021-12-29 2022-01-31 2022-01-08 2022-02-21 2022-01-28 2022-03-08 2022-02-18 2022-04-12 2023-10-11 ce in Strategic Sectors on l und Capacity Building Progra m PK-HEC-281977-CS-LCS / Co Capacity Building through Pa Least Cost Selecti Open - Internationa Under Implement nsultancy for Strategic Com IDA / 64380 rtnerships, Project Managem Post 160,000.00 0.00 2022-03-10 2022-03-24 2022-03-25 2022-04-18 2022-04-11 2022-05-26 2022-06-05 2022-06-25 2022-07-16 2024-06-30 on l ation munication of HEDP ent, Monitoring and Evaluati on PK-HEC-345542-CS-CQS / Sel Capacity Building through Pa Consultant Qualifi Under Implement ection of Consulting Firm for IDA / 64380 rtnerships, Project Managem Post Open - National 120,000.00 0.00 2023-03-02 2023-03-01 2023-03-23 2023-03-30 2023-04-21 2023-05-29 2023-05-06 2023-06-26 2023-05-26 2024-06-30 cation Selection ation Third Party Verification ent, Monitoring and Evaluati on PK-HEC-123681-CS-QCBS / S Supporting Decentralized Hi election of Consulting Firm fo gher Education Institutes for Quality And Cost- IDA / 64380 Post Open - National 170,000.00 0.00 Canceled 2019-10-15 2019-11-05 2019-12-19 2020-01-16 2020-02-15 2020-03-21 2020-04-25 2021-04-25 r Study on Affiliation System Improved Teaching and Lear Based Selection of Public Sector Universities ning PK-HEC-350217-CS-CQS / Sel Capacity Building through Pa Consultant Qualifi ection of Firm for Study on Af IDA / 64380 rtnerships, Project Managem Post Open - National 170,000.00 0.00 Canceled 2023-03-21 2023-04-05 2023-04-11 2023-05-25 2023-07-17 2023-06-08 2023-07-02 2023-12-29 cation Selection filiation System of Public Sect ent, Monitoring and Evaluati or Universities on PK-HEC-350221-CS-CQS / Sel Capacity Building through Pa ection of Consulting Firm for rtnerships, Project Managem Consultant Qualifi Study on Contribution of Publ IDA / 64380 Post Open - National 40,000.00 0.00 Canceled 2023-03-22 2023-04-05 2023-04-12 2023-05-26 2023-07-17 2023-06-09 2023-07-03 2023-12-30 ent, Monitoring and Evaluati cation Selection ic Sector Universities towards on Sustainable Development Go als (SDGs) PK-HEC-353662-CS-CQS / Sel Capacity Building through Pa ection of Consulting Firm for rtnerships, Project Managem Consultant Qualifi IDA / 64380 Post Open - National 80,000.00 0.00 Canceled 2023-04-03 2023-04-04 2023-04-24 2023-06-07 2023-07-18 2023-06-21 2023-07-15 2023-12-12 Training Need Assessment of ent, Monitoring and Evaluati cation Selection Public Sector Universities of on Punjab and Sindh PK-HEC-373600-CS-CQS / Sel Capacity Building through Pa ection of Consulting Firm for rtnerships, Project Managem Consultant Qualifi Training of Public Sector HEIs IDA / 64380 Post Open - National 300,000.00 0.00 Canceled 2023-07-26 2023-08-25 2023-09-29 2023-10-14 2023-11-03 2024-06-30 ent, Monitoring and Evaluati cation Selection ' and Affiliated Colleges’ Facu on lty and Staff (Punjab, Sindh, and Baluchistan) PK-HEC-373602-CS-CQS / Sel Capacity Building through Pa ection of Consulting Firm for I rtnerships, Project Managem Consultant Qualifi IDA / 64380 Post Open - National 280,000.00 0.00 Canceled 2023-07-26 2023-07-25 2023-08-25 2023-09-29 2023-10-14 2023-11-03 2024-06-30 mproving the Financial Auton ent, Monitoring and Evaluati cation Selection omy and Governance of Publi on c Sector Universities PK-HEC-384872-CS-CQS / Sel Capacity Building through Pa Consultant Qualifi ection of Consulting Firm for IDA / 64380 rtnerships, Project Managem Post Open - National 15,000.00 0.00 Under Review 2023-10-13 2023-10-19 2023-11-12 2024-01-01 2024-01-21 2024-02-25 2024-06-14 cation Selection Establishing Post Audit Functi ent, Monitoring and Evaluati on at HEC on PK-HEC-384873-CS-CQS / Sel Capacity Building through Pa ection of Consulting Firm for rtnerships, Project Managem Consultant Qualifi Under Implement IDA / 64380 Post Open - National 200,000.00 0.00 2023-10-11 2024-05-16 2023-11-05 2024-08-16 2024-01-04 2024-01-18 2024-02-11 2024-06-30 Marketing and Communicatio ent, Monitoring and Evaluati cation Selection ation n Support Services on Page 3 PK-HEC-423651-CS-CQS / Sel Capacity Building through Pa ection of Consulting Firm for rtnerships, Project Managem Consultant Qualifi Under Implement Assessment of Students Satis IDA / 64380 Post Open - National 50,000.00 0.00 2024-04-26 2024-04-26 2024-05-26 2024-08-06 2024-07-15 2024-08-04 2024-09-03 2025-03-22 ent, Monitoring and Evaluati cation Selection ation faction and Graduate Trackin on g Study in Higher Education PK-HEC-444325-CS-CQS / Sel ection of Consulting Firm for Capacity Building through Pa Development and Implement rtnerships, Project Managem Consultant Qualifi IDA / 64380 Post Open - National 35,000.00 0.00 Under Review 2024-08-10 2024-08-16 2024-08-31 2024-10-14 2024-11-13 2024-12-07 2025-06-30 ation of Environment, Health, ent, Monitoring and Evaluati cation Selection Safety & Social Management on System Framework for the Pa kistani Universities PK-HEC-444335-CS-CQS / Sel Capacity Building through Pa ection of Consulting Firm for rtnerships, Project Managem Consultant Qualifi Under Implement E-waste Management Plan fo IDA / 64380 Post Open - National 20,000.00 0.00 2024-08-10 2024-08-16 2024-08-31 2024-10-14 2024-11-13 2024-12-17 2025-03-17 ent, Monitoring and Evaluati cation Selection ation r ICT Procurements in HEC an on d Universities across Pakista n PK-HEC-447295-CS-CQS / Sel ection of Consulting Firm to c Capacity Building through Pa onduct Tracer Study for Pakis rtnerships, Project Managem Consultant Qualifi Pending Impleme IDA / 64380 Post Open - National 35,000.00 0.00 2024-08-30 2024-09-20 2024-11-03 2024-12-03 2024-12-31 2025-04-30 tani Startups Graduated from ent, Monitoring and Evaluati cation Selection ntation Academic Incubators at HEIs on of Pakistan (Facilitated throu gh ORICs, BICs and ISF Progr am) PK-HEC-447297-CS-CQS / Sel Capacity Building through Pa Consultant Qualifi Pending Impleme ection of Consulting Firm to c IDA / 64380 rtnerships, Project Managem Post Open - National 55,000.00 0.00 2024-08-30 2024-09-20 2024-11-03 2024-12-03 2024-12-31 2025-04-30 cation Selection ntation onduct Grants Impact Study ent, Monitoring and Evaluati on INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-HEC-134012-CS-INDV / C Nurturing Academic Excellen Individual Consult onsultant for Remodeling of IDA / 64380 Post Open 250,000.00 0.00 Canceled 2019-10-01 2019-11-03 2019-11-13 2019-11-19 2020-11-18 ce in Strategic Sectors ant Selection Business Incubation Centers Capacity Building through Pa PK-HEC-134422-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 36,694.53 Signed 2019-09-16 2019-09-24 2019-10-12 2020-05-21 2019-10-17 2020-06-09 2019-10-23 2020-06-29 2024-06-30 ogram Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134423-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 0.00 2019-09-16 2019-09-22 2019-10-12 2020-02-26 2019-10-17 2020-04-28 2019-10-23 2024-06-30 ogram Specialist - IT ant Selection ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134424-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 0.00 2019-09-16 2019-09-22 2019-10-12 2020-02-26 2019-10-17 2019-10-23 2024-06-30 ogram Specialist - Academics ant Selection ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134428-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Prior Open 300,000.00 88,066.87 Signed 2019-09-16 2019-09-22 2019-10-12 2020-05-21 2019-10-17 2020-06-09 2019-10-23 2020-06-16 2024-06-30 ogram Specialist-R&D ant Selection ent, Monitoring and Evaluati on PK-HEC-123559-CS-INDV / T Capacity Building through Pa echnical Assistance for devel rtnerships, Project Managem Individual Consult Pending Impleme IDA / 64380 Post Open 100,000.00 0.00 2019-10-15 2019-11-08 2019-11-29 2020-01-03 2021-01-02 opment of Criteria for enhanc ent, Monitoring and Evaluati ant Selection ntation ed autonomy -Consultancy on Capacity Building through Pa PK-HEC-134417-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 3,003.34 Signed 2019-09-16 2019-09-16 2019-10-12 2020-02-26 2019-10-17 2020-02-26 2019-10-23 2021-06-02 2024-10-21 ocurement Specialist ant Selection ent, Monitoring and Evaluati on PK-HEC-134418-CS-INDV / M Capacity Building through Pa Individual Consult onitoring & Evaluation Specia IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 2,937.52 Signed 2019-09-16 2019-09-16 2019-10-12 2020-03-06 2019-10-17 2020-03-06 2019-10-23 2020-04-26 2024-06-30 ant Selection list ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134420-CS-INDV / C Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 2,937.52 Signed 2019-09-16 2019-09-16 2019-10-12 2020-02-26 2019-10-17 2020-02-26 2019-10-23 2020-04-19 2024-06-30 ommunication Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134431-CS-INDV / E Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 270,000.00 0.00 Canceled 2019-09-16 2019-09-16 2019-10-12 2019-10-17 2019-10-23 2024-06-30 nvironmental Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-134432-CS-INDV / S Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 270,000.00 0.00 Canceled 2019-09-16 2020-04-14 2019-10-12 2019-10-17 2019-10-23 2024-06-30 ocial Specialist ant Selection ent, Monitoring and Evaluati on PK-HEC-145841-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Open 100,000.00 0.00 Canceled 2019-11-15 2019-10-08 2019-12-11 2020-04-17 2019-12-16 2019-12-22 2020-12-21 onsultant (ORIC/BIC mapping ce in Strategic Sectors ant Selection ) PK-HEC-134419-CS-INDV / Fi Capacity Building through Pa Individual Consult nancial Management Speciali IDA / 64380 rtnerships, Project Managem Post Open 270,000.00 73,510.36 Signed 2019-09-16 2019-11-01 2019-10-12 2020-04-10 2019-10-17 2020-04-28 2019-10-23 2020-05-08 2024-10-21 ant Selection st ent, Monitoring and Evaluati on PK-HEC-172414-CS-CDS / Int Supporting Decentralized Hi ernational Expert/Consultant IDA / 64380 gher Education Institutes for Post Direct Selection Direct 53,000.00 49,000.00 Signed 2020-05-06 2020-04-14 2020-05-16 2020-04-02 2020-07-20 2020-04-24 2021-01-16 Research and Academic Gov Improved Teaching and Lear ernance ning PK-HEC-172415-CS-CDS / Int Supporting Decentralized Hi ernational Expert/Consultant IDA / 64380 gher Education Institutes for Post Direct Selection Direct 53,000.00 66,000.00 Signed 2020-05-06 2020-04-14 2020-05-16 2020-03-22 2020-07-20 2020-04-24 2021-01-16 Research, Teaching and Lear Improved Teaching and Lear ning ning PK-HEC-172417-CS-CDS / Int Supporting Decentralized Hi ernational Expert/Consultant IDA / 64380 gher Education Institutes for Post Direct Selection Direct 39,000.00 49,000.00 Signed 2020-05-06 2020-04-06 2020-05-16 2020-03-22 2020-07-20 2020-04-24 2021-01-16 Teaching & Learning Improved Teaching and Lear ning PK-HEC-172418-CS-CDS / Na Supporting Decentralized Hi tional Expert/Consultant Onli IDA / 64380 gher Education Institutes for Post Direct Selection Direct 10,400.00 27,114.79 Signed 2020-05-06 2020-04-06 2020-05-16 2020-04-18 2020-07-20 2020-04-23 2021-01-16 ne Instruction and Online Tec Improved Teaching and Lear hnology ning PK-HEC-173498-CS-CDS / Co Supporting Decentralized Hi ordinator for Educational Tec IDA / 64380 gher Education Institutes for Post Direct Selection Direct 5,000.00 4,544.08 Signed 2020-05-13 2020-05-14 2020-05-23 2020-05-28 2020-07-27 2020-06-18 2021-01-23 hnology Improved Teaching and Lear ning Page 4 PK-HEC-173499-CS-CDS / Co Supporting Decentralized Hi nsultant IT – Learning Manag IDA / 64380 gher Education Institutes for Post Direct Selection Direct 15,000.00 5,618.88 Signed 2020-05-13 2020-05-14 2020-05-23 2020-05-28 2020-07-27 2020-06-18 2021-01-23 ement System Improved Teaching and Lear ning PK-HEC-173490-CS-INDV / Pr Supporting Decentralized Hi Individual Consult ogramme Specialist - Teachi IDA / 64380 gher Education Institutes for Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-22 ant Selection ng & Learning Improved Teaching and Lear ning PK-HEC-173489-CS-INDV / Pr Supporting Decentralized Hi Individual Consult ogramme Specialist – Resear IDA / 64380 gher Education Institutes for Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-30 ant Selection ch and Knowledge Managem Improved Teaching and Lear ent ning PK-HEC-173487-CS-INDV / Pr Supporting Decentralized Hi ogramme Specialist - Acade gher Education Institutes for Individual Consult IDA / 64380 Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-30 mic Governance, Leadership Improved Teaching and Lear ant Selection and Management in HEIs ning PK-HEC-173485-CS-INDV / Pr Supporting Decentralized Hi Individual Consult ogramme Coordinator – Inter IDA / 64380 gher Education Institutes for Post Open 200,000.00 0.00 Canceled 2020-05-13 2020-06-09 2020-06-14 2020-07-10 2024-06-30 ant Selection nationalisation Improved Teaching and Lear ning Capacity Building through Pa PK-HEC-134421-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Prior Open 360,000.00 0.00 Canceled 2019-09-16 2019-09-22 2019-10-12 2019-10-17 2019-10-23 2024-06-30 oject Coordinator ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-173859-CS-INDV / Pr IDA / 64380 rtnerships, Project Managem Prior Direct Selection Direct 360,000.00 122,068.46 Signed 2020-05-19 2020-05-20 2020-05-29 2020-06-09 2020-08-02 2020-06-25 2024-06-30 oject Coordinator ent, Monitoring and Evaluati on PK-HEC-180214-CS-CDS / En Capacity Building through Pa vironmental Specialist for Ra IDA / 64380 rtnerships, Project Managem Post Direct Selection Direct 5,000.00 6,051.47 Signed 2020-06-16 2020-06-16 2020-06-26 2020-06-17 2020-07-11 2020-07-02 2020-09-09 pid Research & Innovation Ini ent, Monitoring and Evaluati tiative on PK-HEC-198929-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist - Research IDA / 64380 rtnerships, Project Managem Post Open 50,000.00 0.00 Canceled 2020-10-09 2020-11-27 2020-12-18 2021-01-22 2023-01-22 ant Selection and Research Management ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-198952-CS-INDV / E Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 100,000.00 56,403.51 Signed 2020-10-09 2020-08-14 2020-11-27 2021-04-06 2020-12-18 2021-04-06 2021-01-22 2021-04-24 2023-01-22 nvironmental Specialist ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-198956-CS-INDV / S Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 100,000.00 60,201.50 Signed 2020-10-09 2022-01-21 2020-11-27 2022-03-24 2020-12-18 2022-03-24 2021-01-22 2022-04-16 2021-07-21 ocial Development Specialist ant Selection ent, Monitoring and Evaluati on PK-HEC-198938-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist - Teaching a IDA / 64380 rtnerships, Project Managem Post Open 50,000.00 0.00 Canceled 2020-10-09 2020-11-27 2020-12-18 2021-01-22 2023-01-22 ant Selection nd Learning ent, Monitoring and Evaluati on PK-HEC-198922-CS-INDV / Pr Capacity Building through Pa ogram Specialist - Academic rtnerships, Project Managem Individual Consult IDA / 64380 Post Open 50,000.00 0.00 Canceled 2020-10-09 2020-11-27 2020-12-18 2021-01-22 2023-01-22 Leadership, Governance and ent, Monitoring and Evaluati ant Selection Financial Management on PK-HEC-198916-CS-INDV / E Capacity Building through Pa Individual Consult ducational Technology Speci IDA / 64380 rtnerships, Project Managem Post Open 30,000.00 15,277.72 Signed 2020-10-09 2020-08-15 2020-11-27 2020-12-09 2020-12-18 2020-12-10 2021-01-22 2020-12-15 2023-01-22 ant Selection alist ent, Monitoring and Evaluati on PK-HEC-198920-CS-INDV / K Capacity Building through Pa Individual Consult nowledge Management and IDA / 64380 rtnerships, Project Managem Post Open 30,000.00 34,535.97 Signed 2020-10-09 2020-08-20 2020-11-27 2020-12-09 2020-12-18 2020-12-09 2021-01-22 2020-12-27 2023-01-22 ant Selection Communication Specialist ent, Monitoring and Evaluati on PK-HEC-202636-CS-INDV / N Capacity Building through Pa Individual Consult Pending Impleme ational Expert-Consultant Onl IDA / 64380 rtnerships, Project Managem Post Limited 5,500.00 0.00 2020-11-03 2020-11-08 2020-11-29 2021-01-03 2021-07-02 ant Selection ntation ine Instruction: Program Deli ent, Monitoring and Evaluati very on PK-HEC-202638-CS-INDV / N Capacity Building through Pa Individual Consult Pending Impleme ational Expert-Consultant Onl IDA / 64380 rtnerships, Project Managem Post Limited 5,500.00 0.00 2020-11-03 2020-11-08 2020-11-29 2021-01-03 2021-07-02 ant Selection ntation ine Instruction: Program Deli ent, Monitoring and Evaluati very on Capacity Building through Pa PK-HEC-208294-CS-INDV / Pr Individual Consult IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 128,125.07 Signed 2020-12-07 2020-12-10 2021-01-02 2021-02-01 2021-01-07 2021-02-01 2021-01-13 2021-03-30 2024-03-28 oject Coordinator ant Selection ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-210837-CS-INDV / E Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Post Direct 4,000.00 0.00 2020-12-18 2020-12-01 2020-12-19 2020-12-19 2020-12-21 2021-02-19 nvironmental Specialist ant Selection ation ent, Monitoring and Evaluati on PK-HEC-212740-CS-INDV / Fi Capacity Building through Pa Individual Consult nancial Specialist- Resource IDA / 64380 rtnerships, Project Managem Post Open 40,000.00 0.00 Canceled 2021-01-07 2021-02-25 2021-03-02 2021-03-17 2023-03-17 ant Selection Mobilization ent, Monitoring and Evaluati on PK-HEC-212742-CS-INDV / Pr Capacity Building through Pa Individual Consult oject Specialist- Resource Mo IDA / 64380 rtnerships, Project Managem Post Open 100,000.00 0.00 Canceled 2021-01-07 2021-01-28 2021-02-02 2021-02-17 2026-01-24 ant Selection bilization ent, Monitoring and Evaluati on PK-HEC-212744-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist- Resource M IDA / 64380 rtnerships, Project Managem Post Open 120,000.00 0.00 Canceled 2021-01-31 2021-03-12 2021-03-17 2021-04-01 2023-03-22 ant Selection obilization ent, Monitoring and Evaluati on PK-HEC-217176-CS-INDV / C Supporting Decentralized Hi Individual Consult onsultant Need Assessment IDA / 64380 gher Education Institutes for Post Limited 35,000.00 0.00 Canceled 2021-02-02 2021-02-07 2021-02-28 2021-04-04 2021-10-01 ant Selection Study QECs Improved Teaching and Lear ning Capacity Building through Pa PK-HEC-223755-CS-INDV / C Individual Consult IDA / 64380 rtnerships, Project Managem Post Limited 80,000.00 0.00 Canceled 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-09 2023-04-29 onsultant-Academics ant Selection ent, Monitoring and Evaluati on Supporting Decentralized Hi PK-HEC-223760-CS-INDV / C Individual Consult IDA / 64380 gher Education Institutes for Post Limited 45,000.00 37,904.48 Signed 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-05 2021-05-09 2021-07-15 2023-04-29 onsultant (Capacity Building) ant Selection Improved Teaching and Lear ning PK-HEC-223761-CS-INDV / C Supporting Decentralized Hi Individual Consult onsultant (Course Developm IDA / 64380 gher Education Institutes for Post Limited 45,000.00 40,446.04 Signed 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-05 2021-05-09 2021-06-21 2023-04-29 ant Selection ent) Improved Teaching and Lear ning Supporting Decentralized Hi PK-HEC-223781-CS-INDV / C Individual Consult IDA / 64380 gher Education Institutes for Post Limited 45,000.00 0.00 Canceled 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-09 2023-04-29 onsultant (Quality) ant Selection Improved Teaching and Lear ning Page 5 PK-HEC-223786-CS-INDV / C Nurturing Academic Excellen Individual Consult Pending Impleme IDA / 64380 Post Limited 35,000.00 0.00 2021-03-09 2021-03-14 2021-04-04 2021-05-09 2023-04-29 onsultant Research Grants ce in Strategic Sectors ant Selection ntation PK-HEC-223787-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Limited 35,000.00 59,429.85 Signed 2021-03-09 2021-04-15 2021-03-14 2021-05-05 2021-04-04 2021-05-06 2021-05-09 2021-06-07 2023-04-29 onsultant Research Grants ce in Strategic Sectors ant Selection PK-HEC-223790-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Limited 35,000.00 31,587.04 Signed 2021-03-09 2021-02-15 2021-03-14 2021-05-05 2021-04-04 2021-05-05 2021-05-09 2021-06-08 2023-04-29 onsultant Startups Ecosyste ce in Strategic Sectors ant Selection m PK-HEC-223791-CS-INDV / C Nurturing Academic Excellen Individual Consult IDA / 64380 Post Limited 30,000.00 0.00 Canceled 2021-03-09 2021-02-15 2021-03-14 2021-04-04 2021-05-09 2023-04-29 onsultant Innovators Seed Fu ce in Strategic Sectors ant Selection nd(ISF) PK-HEC-211642-CS-INDV / M Capacity Building through Pa Individual Consult onitoring & Evaluation Specia IDA / 64380 rtnerships, Project Managem Post Open 240,000.00 12,438.41 Signed 2021-04-15 2021-04-23 2021-05-06 2021-10-15 2021-05-11 2021-11-19 2021-05-18 2021-12-06 2023-05-18 ant Selection list ent, Monitoring and Evaluati on PK-HEC-231594-CS-INDV / N Capacity Building through Pa Individual Consult ational Expert/Consultant Onl IDA / 64380 rtnerships, Project Managem Post Open 48,000.00 17,218.71 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-31 2022-05-30 ant Selection ine Instruction: Program Deli ent, Monitoring and Evaluati very on PK-HEC-231597-CS-INDV / In Capacity Building through Pa Individual Consult ternational Expert/Consultant IDA / 64380 rtnerships, Project Managem Post Open 60,000.00 42,000.00 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-31 2022-05-30 ant Selection Research, Teaching and Lear ent, Monitoring and Evaluati ning on PK-HEC-231598-CS-INDV / In Capacity Building through Pa ternational Expert/Consultant rtnerships, Project Managem Individual Consult IDA / 64380 Post Open 66,000.00 46,200.00 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-31 2022-05-30 Teaching, Research and Facu ent, Monitoring and Evaluati ant Selection lty Development on PK-HEC-231599-CS-INDV / N Capacity Building through Pa Individual Consult ational Expert/Consultant Onl IDA / 64380 rtnerships, Project Managem Post Open 18,000.00 18,000.00 Signed 2021-04-27 2021-04-28 2021-05-26 2021-07-26 2021-05-31 2021-07-26 2021-06-04 2021-07-31 2022-05-30 ant Selection ine Instruction and Online Te ent, Monitoring and Evaluati chnology on PK-HEC-269376-CS-INDV / C Supporting Decentralized Hi Individual Consult Under Implement onsultant Capacity Building - IDA / 64380 gher Education Institutes for Post Open 30,000.00 0.00 2021-12-20 2022-01-18 2022-01-18 2022-01-28 2022-02-12 2023-02-12 ant Selection ation UEP Improved Teaching and Lear ning PK-HEC-269379-CS-INDV / C Supporting Decentralized Hi Individual Consult Under Implement onsultant Capacity Building - IDA / 64380 gher Education Institutes for Post Open 30,000.00 0.00 2021-12-20 2022-01-18 2022-01-18 2022-08-26 2022-01-28 2022-08-26 2022-02-12 2023-02-12 ant Selection ation QECAC Improved Teaching and Lear ning Capacity Building through Pa PK-HEC-273516-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Post Open 60,000.00 0.00 2022-01-18 2022-02-03 2022-03-09 2022-03-24 2022-03-14 2022-03-24 2022-03-24 2024-03-23 ogram Specialist ant Selection ation ent, Monitoring and Evaluati on PK-HEC-273524-CS-INDV / C Capacity Building through Pa Individual Consult ontract Management Speciali IDA / 64380 rtnerships, Project Managem Post Open 48,000.00 38,953.91 Signed 2022-01-18 2022-01-18 2022-03-09 2022-03-24 2022-03-19 2022-03-24 2022-03-29 2022-04-14 2022-06-13 ant Selection st ent, Monitoring and Evaluati on PK-HEC-280667-CS-INDV / E Capacity Building through Pa Individual Consult Under Implement ducation Technology Speciali IDA / 64380 rtnerships, Project Managem Post Open 40,000.00 0.00 2022-02-28 2022-04-14 2022-05-05 2022-06-09 2024-06-30 ant Selection ation st ent, Monitoring and Evaluati on PK-HEC-289626-CS-INDV / Pr Capacity Building through Pa Individual Consult ogram Specialist IT IDA / 64380 rtnerships, Project Managem Post Open 95,000.00 66,488.89 Signed 2022-04-15 2022-04-14 2022-05-20 2022-08-26 2022-05-25 2022-08-26 2022-05-31 2022-09-04 2024-06-30 ant Selection For Supporting Comp-3 &4 ent, Monitoring and Evaluati on PK-HEC-289627-CS-INDV / M Capacity Building through Pa Individual Consult Under Implement onitoring & Evaluation Specia IDA / 64380 rtnerships, Project Managem Post Open 70,000.00 0.00 2022-04-15 2022-04-14 2022-05-20 2022-05-25 2022-06-04 2024-06-03 ant Selection ation list ent, Monitoring and Evaluati on PK-HEC-289630-CS-INDV / C Improving access and qualit Individual Consult onsultant- University Autono IDA / 64380 y of remote learning and sup Post Open 24,000.00 23,602.41 Signed 2022-04-15 2022-04-14 2022-05-25 2022-08-26 2022-05-30 2022-08-26 2022-06-14 2022-09-02 2024-06-03 ant Selection my port to universities Capacity Building through Pa PK-HEC-313409-CS-INDV / Pr Individual Consult Open - Internationa Under Implement IDA / 64380 rtnerships, Project Managem Post 150,000.00 0.00 2022-09-01 2022-09-02 2022-10-04 2022-10-09 2022-10-15 2024-06-30 oject Coordinator ant Selection l ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-314935-CS-INDV / Pr Individual Consult Open - Internationa Under Implement IDA / 64380 rtnerships, Project Managem Post 100,000.00 0.00 2022-09-08 2022-10-03 2022-10-12 2022-12-16 2022-10-22 2022-11-01 2024-06-30 ogram Specialist- Academics ant Selection l ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-320705-CS-INDV / Pr Individual Consult Open - Internationa Under Implement IDA / 64380 rtnerships, Project Managem Post 60,000.00 0.00 2022-10-19 2022-10-11 2022-12-08 2022-12-13 2022-12-23 2024-06-30 ogram Specialist ant Selection l ation ent, Monitoring and Evaluati on Capacity Building through Pa PK-HEC-330240-CS-INDV / Pr Individual Consult Under Implement IDA / 64380 rtnerships, Project Managem Post Open - National 100,000.00 0.00 2022-12-07 2022-12-12 2023-01-25 2023-02-15 2023-03-22 2024-06-30 ocurement Specialist ant Selection ation ent, Monitoring and Evaluati on PK-HEC-355464-CS-INDV / S Capacity Building through Pa Individual Consult election of Contract & HR Ma IDA / 64380 rtnerships, Project Managem Post Open - National 30,000.00 0.00 Canceled 2023-04-07 2023-04-07 2023-05-23 2023-06-06 2023-06-30 2024-06-30 ant Selection nagement Specialist ent, Monitoring and Evaluati on PK-HEC-391695-CS-INDV / S Capacity Building through Pa Individual Consult election of Contract & HR Sp IDA / 64380 rtnerships, Project Managem Post Limited 17,000.00 0.00 Canceled 2023-11-10 2024-01-03 2023-11-15 2023-11-30 2023-12-25 2024-06-30 ant Selection ecialist ent, Monitoring and Evaluati on PK-HEC-441471-CS-INDV / S Capacity Building through Pa Individual Consult Under Implement election of Contract Manage IDA / 64380 rtnerships, Project Managem Post Open - National 15,000.00 0.00 2024-07-28 2024-07-31 2024-09-15 2024-09-25 2024-10-15 2025-06-30 ant Selection ation ment Specialist ent, Monitoring and Evaluati on PK-HEC-441473-CS-INDV / S Capacity Building through Pa Individual Consult Under Implement election of Consultant Univer IDA / 64380 rtnerships, Project Managem Post Open - National 20,000.00 0.00 2024-07-28 2024-07-31 2024-09-15 2024-09-25 2024-10-15 2025-06-30 ant Selection ation sity/ Financial Autonomy ent, Monitoring and Evaluati on PK-HEC-441475-CS-INDV / S Capacity Building through Pa Individual Consult Under Implement election of Financial Manage IDA / 64380 rtnerships, Project Managem Post Open - National 30,000.00 0.00 2024-07-28 2024-07-31 2024-09-15 2024-09-25 2024-10-15 2025-06-30 ant Selection ation ment Specialist ent, Monitoring and Evaluati on Page 6