PROCUREMENT PLAN (Textual Part) Project information: [Central African Republic] [Electricity Sector Strengthening and Access Project] [P-176683] Project Implementation agency: [Project Implementation Unit in the Ministry of Development of Energy and Water resources] Date of the Procurement Plan: [December 20, 2021] Period covered by this Procurement Plan: [from December 20, 2021 to September 30, 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Law dated June 2008, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets “Not Applicable” Procurement of Second Hand Goods “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable/is applicable for those contracts identified in the Procurement Plan tables ; Works: is not applicable/is applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. PROCUREMENT Central African Republic : CAR-Electricity Sector Strengthening and Access Project PLAN General Information Country: Central African Republic 2021-12-20 Bank’s Approval Date of the Original Procurement Plan: 2024-08-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176683 GPN Date: Project Name: CAR-Electricity Sector Strengthening and Access Project Loan / Credit No: IDA / V3910, IDA / E0430 Water and Electricity Upgrading Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Demande d'offres PARSE/25/CW/RFB/23 / Trav Component 3: Institutional s Single Stage - One E - DTPM Petits trav En cours d'e 2024-07-0 aux de réhabilitation des loca IDA / E0430 trengthening, capacity buildi A posteriori Appel d'offres Open - National 420,000.00 0.00 2023-09-15 2024-08-22 2023-09-20 2023-11-01 2023-12-01 2024-01-05 nvelope aux - (Processus à xécution 3 ux de l'ACER et de l'Assistanc ng and implementation supp 1 enveloppe) e Technique. ort PARSE/027/CW/DIR/23 / OPE RATIONALISATION ET MAINTE Component 1: Solar Generat NANCE DE LA CENTRALE PHO ion and T&D upgrades for V Passation de marc Direct - Internation Autre (avec cham 2024-06-2 IDA / E0430 A posteriori 4,338,420.00 0.00 Signé 2023-11-14 2023-11-14 2023-11-19 2023-11-29 2023-12-24 2023-11-27 TOVOLTAÏQUE DE PUISSANCE RE integration and increased hé de gré à gré al p d'explication) 1 25MWC A DANZI (SITUEE A 1 access 8 KM DE BANGUI SUR LA RO UTE DE BOALI) PARSE/029/CW/RFB/24 / Rés eau - Travaux de renforceme nt du réseau de transmission Component 1: Solar Generat Demande d'offres par la construction d’une bou ion and T&D upgrades for V Open - Internationa Single Stage - Two E - DTPM Travaux (s 15,000,000.0 En cours d'e 2025-01-3 cle de 21 km en 110 kV (tron IDA / E0430 A priori Appel d'offres 0.00 2024-02-29 2024-04-20 2024-03-05 2024-04-16 2024-06-29 2024-08-03 RE integration and increased l nvelope ans préqualificati 0 xécution 0 çon Danzi - Sakaï) et la réhab access on) ilitation des sous-stations C e t A par le passage de 110 à 6 3 kV et l’augmentation de la capacité de 20 MVA PARSE/002/CW/RFB/24 / Mini Component 1: Solar Generat Demande d'offres réseau 3 villes-Fourniture et i ion and T&D upgrades for V Open - Internationa Single Stage - Two E - DTPM Petits trav 10,000,000.0 En cours d'e 2026-02-2 nstallation des équipements IDA / E0430 A priori Appel d'offres 0.00 2024-03-04 2024-05-09 2024-03-04 2024-05-21 2024-05-13 2024-07-26 2024-08-30 RE integration and increased l nvelope aux - (Processus à 0 xécution 1 d'électrification par mini rése access 1 enveloppe) au dans les villes de Birao, B ossembélé et Nola. PARSE/003/CW/RFB/24 / Mini Component 1: Solar Generat Demande d'offres réseau 2 villes-Fourniture et i ion and T&D upgrades for V Open - Internationa Single Stage - Two E - DTPM Petits trav En cours d'e 2026-02-2 nstallation des équipements IDA / E0430 A posteriori Appel d'offres 8,000,000.00 0.00 2024-03-06 2024-02-27 2024-03-06 2024-04-12 2024-05-15 2024-06-18 2024-07-28 2024-09-01 RE integration and increased l nvelope aux - (Processus à xécution 3 d'électrification par mini rése access 1 enveloppe) au dans les villes de Bangass ou et Bouar Demande de cota PARSE/033/CW/DIR/24 / CPV Component 1: Solar Generat tions - DTPM Petit Bambari Berberati - Opératio ion and T&D upgrades for V Passation de marc Direct - Internation En attente d 2024-12-1 IDA / E0430 A posteriori s travaux (urgenc 1,100,000.00 0.00 2024-05-09 2024-05-14 2024-06-18 nnalisation et Maintenance d RE integration and increased hé de gré à gré al 'exécution 5 e) - Sans compétit es centrales Hybrides de Ba access ion mbari et Berberati PARSE/035/CW/DIR/24 / Tran smission - Travaux de renforc ement du réseau de transmis Demande de cota sion par la construction d’un Component 2: Off-grid solar tions - DTPM Petit Passation de marc Direct - Internation 15,000,000.0 En cours d'e 2024-12-1 e boucle de 21km en 110kV ( IDA / E0430 systems for households and A priori s travaux (urgenc 0.00 2024-05-09 2024-06-27 2024-05-14 2024-07-16 2024-06-18 hé de gré à gré al 0 xécution 5 tronçon Danzi-Sakaï) et la ré productive uses e) - Sans compétit habilitation des sous-stations ion C et A par le passage de 110 à 63kV et l’augmentation de la capacité de 20MVA GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PARSE-APP22 / Mobiliers bur Component 3: Institutional s eau-Acquisition de mobiliers trengthening, capacity buildi Single Stage - One E IDA / V3910 A posteriori Appel d'offres Open - National 150,000.00 37,988.95 Signé 2022-01-03 2022-04-26 2022-01-08 2022-04-28 2022-02-19 2022-06-07 2022-03-21 2022-06-23 2022-04-25 2022-08-14 2022-10-22 pour les Consultants nouvelle ng and implementation supp nvelope ment recrutés de l’UGP. ort PARSE-APP23 / TOM²PRO-Fo Component 3: Institutional s urniture et mise en place du l trengthening, capacity buildi Passation de marc IDA / V3910 A posteriori Direct 10,000.00 8,201.20 Signé 2022-06-27 2022-05-31 2022-07-02 2022-07-05 2022-08-06 2022-07-22 2023-02-02 ogiciel TOM²PRO WINDOWS ( ng and implementation supp hé de gré à gré passage à la version Multi-Pr ort ojets) PARSE/01/GO/RFB/22 / Electr Component 1: Solar Generat ification 2 villes-Fourniture et ion and T&D upgrades for V Open - Internationa Single Stage - One E installation des équipements IDA / E0430 A priori Appel d'offres 6,500,000.00 0.00 Annulé 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-26 2024-03-24 RE integration and increased l nvelope d'électrification par mini rése access au dans les villes de Bangass ou et Bouar PARSE/03/GO/RFB/22 / Renfo rcement réseau-Fourniture et installation des équipements Component 1: Solar Generat de renforcement du réseau d ion and T&D upgrades for V Open - Internationa Single Stage - One E IDA / E0430 A priori Appel d'offres 7,000,000.00 0.00 Annulé 2023-08-10 2023-08-15 2023-09-26 2023-10-26 2023-11-30 2024-05-28 e transport par Bouclage du r RE integration and increased l nvelope éseau de transport par const access ruction de la liaison 110 KV p oste Danzi à poste C-C2 à Sa kai y compris réhabilitation d u poste C PARSE/17/GO/RFB/23 / 41 00 0 compteurs - Acquisition de Component 3: Institutional s 40 000 compteurs à prépaie trengthening, capacity buildi Open - Internationa Single Stage - One E En cours d'ex IDA / E0430 A priori Appel d'offres 6,000,000.00 0.00 2023-04-07 2023-05-23 2023-04-12 2023-07-27 2023-11-04 2023-06-05 2023-12-04 2023-11-27 2024-01-08 2024-02-06 2024-07-06 ment pour la pose sur les bra ng and implementation supp l nvelope amen nchements directs et de 1 00 ort 0 compteurs Intelligents pour les administrations PARSE/04/GO/RFB/23 / Travé e transformation - Fourniture Component 1: Solar Generat et installation d'une nouvelle ion and T&D upgrades for V Open - Internationa Single Stage - One E travée transformation au pos IDA / E0430 A priori Appel d'offres 4,500,000.00 0.00 Annulé 2023-09-14 2023-09-19 2023-10-31 2023-11-30 2024-01-04 2024-07-02 RE integration and increased l nvelope te A avec capacité de 25 MV access A y compris remplacement d es tableaux contrôle comma nde en numérique Page 1 PARSE/20/GO/RFB/23 / Déte ction défaut - Acquisition inst Component 3: Institutional s allation des équipements de trengthening, capacity buildi Open - Internationa Single Stage - One E En attente d' IDA / E0430 A priori Appel d'offres 2,000,000.00 0.00 2023-12-28 2024-01-02 2024-02-13 2024-03-14 2024-04-18 2024-10-15 mesures, de détection de déf ng and implementation supp l nvelope exécution aut, commandes à distance d ort ans les postes et centre de c ommande PARSE/15/GO/RFB/23 / Pomp es solaires - Fourniture et ins Component 2: Off-grid solar Open - Internationa Single Stage - One E En attente d' tallation des kits solaires pou IDA / E0430 systems for households and A priori Appel d'offres 4,500,000.00 0.00 2023-12-21 2023-12-26 2024-02-06 2024-03-07 2024-04-11 2024-10-08 l nvelope exécution r l'alimentation des pompes productive uses de forages y compris les rése rvoirs de stockages, PARSE/07/GO/RFB/23 / Renfo rcement réseau - Recruteme Component 1: Solar Generat nt d'une firme chargé de la f ion and T&D upgrades for V Open - Internationa Single Stage - One E En attente d' IDA / E0430 A priori Appel d'offres 3,250,000.00 0.00 2023-12-20 2023-12-25 2024-02-05 2024-03-06 2024-04-10 2024-10-07 ourniture et de l'installation d RE integration and increased l nvelope exécution es équipements de renforce access ment du réseau de distributi on. PARSE/02/GO/RFB/22 / Electr Component 1: Solar Generat ification 3 villes-Fourniture et ion and T&D upgrades for V Open - Internationa Single Stage - One E installation des équipements IDA / E0430 A priori Appel d'offres 8,500,000.00 0.00 Annulé 2023-09-14 2023-09-19 2023-10-31 2023-11-30 2024-01-04 2024-07-02 RE integration and increased l nvelope d'électrification par mini rése access au dans les villes de Bangass ou et Bouar PARSE/08/GO/RFB/22 / Matér Component 1: Solar Generat iels lignes - Fourniture de câb ion and T&D upgrades for V Open - Internationa Single Stage - One E IDA / E0430 A priori Appel d'offres 3,250,000.00 0.00 Annulé 2023-04-20 2023-11-10 2023-04-25 2023-11-21 2023-06-06 2024-01-17 2023-07-06 2024-04-19 2023-08-10 2024-02-06 les, poteaux et accessoires p RE integration and increased l nvelope our le raccordement électric. access PARSE-APP21 / Equipements informatiques-Acquisition de Component 3: Institutional s divers matériels et équipeme trengthening, capacity buildi Single Stage - One E En attente d' IDA / V3910 A posteriori Appel d'offres Open - National 175,000.00 0.00 2023-09-15 2023-09-20 2023-11-01 2023-12-01 2024-01-05 2024-07-03 nts informatiques et électriqu ng and implementation supp nvelope exécution es pour les Consultants nouv ort ellement recrutés de l’UGP. PARSE/18/GO/RFB/22 / Logis Component 3: Institutional s tique compteurs-Acquisition trengthening, capacity buildi Single Stage - One E En attente d' IDA / E0430 A posteriori Appel d'offres Open - National 250,000.00 0.00 2023-04-17 2023-04-22 2023-06-03 2023-07-03 2023-08-07 2024-02-03 de Moyens logistiques pour l ng and implementation supp nvelope exécution a pose des compteurs ort PARSE/22/GO/RFQ/23 / Acha Component 3: Institutional s Single Stage - One E En cours d'ex t de matériels de communica IDA / E0430 trengthening, capacity buildi A posteriori Demande de prix Open - National 20,000.00 0.00 2023-05-31 2023-07-26 2024-01-22 nvelope écution tion pour l'UGP et l'ENERCA. ng and implementation supp ort PARSE/14/GO/RFB/22 / Solair e bâtiments publics-Fournitur e et instalation des kits solair Component 2: Off-grid solar Open - Internationa Single Stage - One E En cours d'ex es pour l'électrification hors r IDA / E0430 systems for households and A priori Appel d'offres 25,000,000.00 0.00 2023-12-15 2024-03-01 2024-03-01 2023-12-20 2024-05-10 2024-06-09 2024-07-14 2026-01-05 l nvelope écution éseau des institutions publiq productive uses ues (Centres de santé, Ecoles , Batiments administratifs ou Mairie) PARSE/23/GO/RFB/23 / Remp Component 3: Institutional s lacement cellules - Fournitur trengthening, capacity buildi Open - Internationa Single Stage - One E En attente d' IDA / E0430 A priori Appel d'offres 4,200,000.00 0.00 2023-10-13 2023-10-18 2023-11-29 2023-12-29 2024-02-02 2024-07-31 e et remplacement des cellul ng and implementation supp l nvelope exécution es existantes par des CCN à ort Boali1 et au Poste A. PARSE/028/GO/DIR/23 / Four Component 1: Solar Generat niture et installation d'un sys ion and T&D upgrades for V Passation de marc Direct - Internation En cours d'ex tème de contrôle numérique IDA / E0430 A priori 4,364,620.00 0.00 2023-11-15 2023-11-27 2023-11-20 2023-11-30 2023-12-25 2024-01-29 2024-06-22 RE integration and increased hé de gré à gré al amen y compris la liaison SCADA d access es postes 5,5 KV de Boali 1 e t 15KV de Bangui A PARSE/032/GO/RFB/24 / Véhi Component 3: Institutional s cules MDERH - Acquisition de trengthening, capacity buildi Open - Internationa Single Stage - Two E En cours d'ex IDA / E0430 A posteriori Appel d'offres 700,000.00 0.00 2024-04-17 2024-04-16 2024-04-17 2024-04-17 2024-06-26 2024-05-17 2024-09-08 2024-10-13 2026-04-06 véhicules pour le Ministère d ng and implementation supp l nvelope écution e l'Energie, l'ACER, l'ENERCA ort et l'UGP. PARSE/034/GO/RFB/24 / Kits solaires bâtiments - Fournitur e et installation des kits solai Component 2: Off-grid solar Open - Internationa Single Stage - Two E En cours d'ex res pour l'électrification hors IDA / E0430 systems for households and A priori Appel d'offres 25,000,000.00 0.00 2024-05-09 2024-05-09 2024-07-18 2024-09-30 2024-11-04 2026-04-28 l nvelope amen réseau des institutions publiq productive uses ues (Centres de santé, Ecoles , Bâtiments administratifs ou Mairies) PARSE/040/GO/DIR/24 / SUP Component 3: Institutional s RIMA 6-Mise à jour du systèm trengthening, capacity buildi Passation de marc Direct - Internation En cours d'ex e de vente des compteurs à IDA / E0430 A posteriori 200,000.00 0.00 2024-08-16 2024-08-22 2024-08-21 2024-08-22 2024-09-25 2025-03-24 ng and implementation supp hé de gré à gré al écution prépaiement de l'ENERCA pa ort r le passage à SUPRIMA 6. PARSE/038/GO/DIR/24 / Com Component 3: Institutional s pteurs supplémentaires- Acq trengthening, capacity buildi Passation de marc Direct - Internation En attente d' IDA / E0430 A priori 2,997,470.00 0.00 2024-08-30 2024-09-04 2024-10-09 2025-04-07 uisition de compteurs supplé ng and implementation supp hé de gré à gré al exécution mentaires à l'ENERCA. ort NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PARSE/05/NC/RFB/22 / Maint enance transformateurs- Tra vaux de maintenance des tra Component 1: Solar Generat nsformateurs 10 et 5 MVA ex ion and T&D upgrades for V Passation de marc Direct - Internation IDA / E0430 A posteriori 1,000,000.00 0.00 Annulé 2023-01-10 2023-01-15 2023-02-19 2023-08-18 traits respectivement des so RE integration and increased hé de gré à gré al us-stations B et A en vue de access servir de reserve sur le résea u de transmission (sécurité d e l'alimentation) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PARSE-APP1.1 / 15 MW Phot ovoltaïque-Recrutement d’un Component 1: Solar Generat Consultant (firme) pour les ét Sélection fondée s ion and T&D upgrades for V Open - Internationa udes de faisabilité économiq IDA / V3910 A posteriori ur la qualité et le 300,000.00 0.00 Signé 2022-01-10 2022-02-08 2022-01-31 2022-03-22 2022-03-16 2022-05-12 2022-04-13 2022-06-24 2022-05-13 2022-07-04 2022-06-17 2022-08-26 2022-07-22 2022-09-14 2023-07-22 RE integration and increased l ue/financières et technique ( coût access APS, APD et l'élaboration du DAO) pour la construction d’ un Centrale Solaire Voltaïque de 15 MW PARSE-APP1.2 / Réseau Tran smission-Recrutement d’un C onsultant (firme) pour les étu Component 1: Solar Generat Sélection fondée s des de faisabilité économiqu ion and T&D upgrades for V Open - Internationa En cours d'exécut IDA / V3910 A posteriori ur la qualité et le 350,000.00 0.00 2022-01-10 2022-02-09 2022-01-31 2022-03-22 2022-03-16 2022-05-12 2022-04-13 2022-06-27 2022-05-13 2022-07-05 2022-06-17 2022-07-22 2023-07-22 e/financières et technique (A RE integration and increased l ion coût PS, APD et DAO), ainsi que le access Contrôle et Surveillance en « option conditionnelle » pourl e renforcement du réseau d e transmission PARSE-APP2.1 / Hybride1, 2v illes-Recrutement d’un Consu ltant (firme) pour les études Component 2: Off-grid solar Sélection fondée s de faisabilité économique/fin Open - Internationa IDA / V3910 systems for households and A posteriori ur la qualité et le 600,000.00 0.00 Signé 2022-03-02 2022-02-23 2022-03-23 2022-03-22 2022-05-06 2022-05-24 2022-06-03 2022-07-06 2022-07-03 2022-08-03 2022-08-07 2022-11-15 2022-09-11 2023-02-11 2023-09-11 ancières-techniques (APS, AP l productive uses coût D et DAO), ainsi que le Contr ôle et la Surveillance en « op tion conditionnelle » pour l'él ectrification de deux villes de la RCA PARSE-APP2.2 / Hybride2, 2v ille-Recrutement d’un Consul tant (firme) pour actualisatio Component 2: Off-grid solar Sélection fondée s n études de faisabilité écono Open - Internationa IDA / V3910 systems for households and A posteriori ur la qualité et le 400,000.00 0.00 Signé 2022-03-02 2022-02-23 2022-03-23 2022-03-25 2022-05-06 2022-05-21 2022-06-03 2022-07-06 2022-07-03 2022-08-10 2022-08-07 2022-12-22 2022-09-11 2023-02-04 2023-09-11 mique/financières-techniques l productive uses coût (APS, APD et DAO), ainsi que Contrôle et Surveillance en « option conditionnelle » pour l 'électrification hybride dans 2 villes PARSE-APP5 / EIES Hybrid-R ecrutement d’un Cabinet pou r la réalisation des EIES, les P Component 3: Institutional s Sélection fondée s GES y compris le PAR pour le trengthening, capacity buildi Open - Internationa IDA / V3910 A posteriori ur la qualité et le 400,000.00 0.00 Annulé 2022-05-04 2022-05-25 2022-07-08 2022-08-05 2022-09-04 2022-10-09 2022-11-13 2023-11-13 s travaux relatifs à l'électrific ng and implementation supp l coût ation des villes provinciales ( ort Nola, Bossémbélé, Bouar et Bangassou) par des solutions solaires ou hybrides en mini r éseau PARSE/16/CS/QCBS/22 / Guic hets subvention-Recrutemen Component 2: Off-grid solar Sélection fondée s Open - Internationa En attente d'exéc t d'un consultant/firme charg IDA / E0430 systems for households and A priori ur la qualité et le 17,000,000.00 0.00 2023-10-23 2023-11-13 2023-12-27 2024-01-24 2024-02-23 2024-03-29 2024-05-03 2025-05-03 l ution é des guichets de subvention productive uses coût s pour l'électrification hors ré seau. PARSE/21/CS/QCBS/22 / Autr Component 3: Institutional s Sélection fondée s es aspects-Recrutement d'un trengthening, capacity buildi Open - Internationa En attente d'exéc IDA / E0430 A priori ur la qualité et le 1,000,000.00 0.00 2023-03-21 2023-04-11 2023-05-25 2023-06-22 2023-07-22 2023-08-26 2023-09-30 2024-09-29 consultant chargé de l'appui i ng and implementation supp l ution coût nstitutionnel et organisationn ort el de l'ENERCA PARSE-APP07 / Conseiller 15 MW/mini réseau - Recruteme nt d'un Conseiller Transactio Component 3: Institutional s Sélection fondée s nnel pour l'assistance à la str trengthening, capacity buildi Open - Internationa En cours d'exécut IDA / V3910 A priori ur la qualité et le 1,500,000.00 0.00 2023-11-23 2023-12-14 2024-01-27 2024-02-24 2024-03-25 2024-04-29 2024-06-03 2025-06-03 ucturation de la mise en œuv ng and implementation supp l ion coût re solutions mini réseau et l'e ort xtension des 15MWc à Bangu i avec la participation des pa rtenaires privés et/ou public. PARSE/09/CS/QCBS/23 / Gest Component 2: Off-grid solar Sélection fondée s ionnaire de Fonds - Recrutem Open - Internationa En cours d'exécut IDA / E0430 systems for households and A priori ur la qualité et le 2,000,000.00 0.00 2023-05-24 2023-05-28 2023-06-14 2023-07-18 2023-07-28 2024-02-09 2023-08-25 2024-04-04 2023-09-24 2024-05-30 2023-10-29 2023-12-03 2024-12-02 ent d'un consultant/firme ges l ion productive uses coût tionnaire de fonds PARSE/10/CS/QCBS/23 / Age Component 2: Off-grid solar Sélection fondée s nce de Vérification - Recrute Open - Internationa En cours d'exécut IDA / E0430 systems for households and A priori ur la qualité et le 1,000,000.00 0.00 2023-08-10 2024-04-29 2023-08-31 2024-06-24 2023-10-14 2023-11-11 2023-12-11 2024-01-15 2024-02-19 2025-02-18 ment d'une agence de vérific l ion productive uses coût ation indépendante PARSE-APP7 / Conseiller 15 MW/mini réseau-Recrutemen t d'un Conseiller Transaction Component 3: Institutional s Sélection fondée s nel pour l'assistance à la stru trengthening, capacity buildi Open - Internationa IDA / V3910 A posteriori ur la qualité et le 1,500,000.00 0.00 Annulé 2022-01-19 2022-02-09 2022-03-25 2022-04-22 2022-05-22 2022-06-26 2022-07-31 2023-07-31 cturation de la mise en œuvr ng and implementation supp l coût e solutions mini réseau et l'e ort xtension des 15MWc à Bangu i avec la participation des pa rtenaires privés et/ou publics PARSE/19/CS/QCBS/22 / Actu Component 3: Institutional s alisation études-Recrutement Sélection fondée s trengthening, capacity buildi Open - Internationa En cours d'exécut d'un consultant/firme chargé IDA / E0430 A posteriori ur la qualité et le 500,000.00 0.00 2023-08-31 2024-01-18 2023-09-21 2024-04-11 2023-11-04 2023-12-02 2024-01-01 2024-02-05 2024-03-11 2025-03-11 ng and implementation supp l ion de l'actualisation des études coût ort pour la surveillance et téléco nduite du réseau PARSE-APP14 / Business dév Component 3: Institutional s Sélection fondée s eloppement-Recrutement d’u trengthening, capacity buildi Open - Internationa En attente d'exéc IDA / V3910 A posteriori ur les qualification 150,000.00 0.00 2023-06-20 2023-06-27 2023-08-10 2023-09-09 2023-10-14 2024-04-11 n Consultant (firme) pour l’él ng and implementation supp l ution s des consultants aboration d’un business déve ort loppement. PARSE/12/CS/QCBS/22 / Assi stant Technique-Recrutemen Component 2: Off-grid solar Sélection fondée s Open - Internationa En cours d'exécut t d'un consultant/firme charg IDA / E0430 systems for households and A posteriori ur la qualité et le 500,000.00 0.00 2023-11-15 2023-08-30 2023-12-06 2024-01-19 2024-02-16 2024-03-17 2024-04-21 2024-05-26 2025-05-26 l ion é de l'électrification hors rés productive uses coût eau des institutions publique s PARSE/06/CS/CQS/22 / Etude Component 1: Solar Generat s renforcement réseau-Recru Sélection fondée s ion and T&D upgrades for V Open - Internationa En attente d'exéc tement d'un consultant charg IDA / E0430 A posteriori ur les qualification 250,000.00 0.00 2023-09-18 2023-10-09 2023-11-22 2023-12-22 2024-01-26 2024-07-24 RE integration and increased l ution é des études du renforcemen s des consultants access t du réseau de distribution PARSE-APP3 / Off Grid-Etude s APS/APD/DAO (option Ferm e), Contrôle et Surveillance ( Component 2: Off-grid solar Sélection fondée s option conditionnelle) pour d Open - Internationa En attente d'exéc IDA / V3910 systems for households and A posteriori ur la qualité et le 300,000.00 0.00 2022-03-23 2022-04-13 2022-05-27 2022-06-24 2022-07-24 2022-08-28 2022-10-02 2023-10-02 es solutions solaires hors rés l ution productive uses coût eau pour ménages en Zone R urale, Centres de Santé, Ecol es et usages productifs com me les pompes solaires pour l'agriculture. Page 3 PARSE-APP13 / Recherche ta Component 3: Institutional s Sélection fondée s lents-Recrutement d’une age trengthening, capacity buildi Open - Internationa En attente d'exéc IDA / V3910 A posteriori ur les qualification 100,000.00 0.00 2022-01-27 2022-02-17 2022-04-02 2022-05-02 2022-06-06 2022-12-03 nce pour la recherche de tale ng and implementation supp l ution s des consultants nts et renforcement de capac ort ités PARSE-APP12 / Sensibilisatio n Efficacité énergétique-Recr Component 3: Institutional s Sélection fondée s utement d’un Consultant (ON trengthening, capacity buildi Open - Internationa En cours d'exécut IDA / V3910 A posteriori ur les qualification 100,000.00 0.00 2022-01-20 2024-02-22 2022-02-10 2022-03-26 2023-02-18 2023-03-25 2023-09-21 G) pour mener une campagn ng and implementation supp l ion s des consultants e de sensibilisation sur le pro ort jet, l’efficacité énergétique et réduction des pertes. PARSE-APP11 / Business Pla Component 3: Institutional s n-Recrutement d’un Consulta Sélection fondée s trengthening, capacity buildi Open - Internationa En cours d'exécut nt (firme) pour l’élaboration IDA / V3910 A posteriori ur les qualification 100,000.00 0.00 2022-01-13 2023-08-30 2022-02-03 2024-02-29 2022-03-19 2022-04-18 2022-05-23 2022-11-19 ng and implementation supp l ion d’un plan d’électrification rur s des consultants ort ale, business plan et prospec tus d’investissement PARSE-APP10 / GIS réseau di Component 3: Institutional s Sélection fondée s stribution-Recrutement d’un trengthening, capacity buildi Open - Internationa En cours d'exécut IDA / V3910 A posteriori ur les qualification 150,000.00 0.00 2022-01-10 2023-08-29 2022-01-31 2024-02-29 2022-03-16 2022-04-15 2022-05-20 2022-11-16 Consultant (firme) pour l’étu ng and implementation supp l ion s des consultants de de modélisation GIS du ré ort seau de distribution. PARSE-APP6 / EIES OFF GRID -Réalisation des EIES, les PGE S y compris le PAR pour les tr Component 3: Institutional s Sélection fondée s avaux relatifs aux solutions s trengthening, capacity buildi Open - Internationa En cours d'exécut IDA / V3910 A posteriori ur les qualification 300,000.00 0.00 2022-05-04 2023-05-11 2022-05-25 2024-04-11 2022-07-08 2022-08-07 2022-09-11 2023-03-10 olaires hors réseau pour les ng and implementation supp l ion s des consultants ménages en Zone Rurale, Ce ort ntres de Santé, Ecoles et les usages productifs comme les pompes solaires pour l'agricu lture PARSE-APP4 / EIES 15 MW-R ecrutement d’un Cabinet pou r la réalisation des EIES, les P Component 3: Institutional s Sélection fondée s GES y compris le PAR, pour l trengthening, capacity buildi Open - Internationa IDA / V3910 A posteriori ur les qualification 300,000.00 0.00 Signé 2023-06-22 2023-05-11 2023-07-13 2023-08-29 2023-08-26 2023-10-13 2023-09-25 2023-11-10 2023-10-30 2023-11-16 2024-04-27 es travaux de construction d ng and implementation supp l s des consultants e la nouvelle ligne d’évacuati ort on HTB de la Centrale Solaire Photovoltaïque de 15 MWc co mplémentaire de Danzi vers l e poste C PARSE/11/CS/CQS/23 / Sensi bilisation, communication-Re Component 2: Off-grid solar Sélection fondée s En attente d'exéc crutement d'un consultant/fir IDA / E0430 systems for households and A posteriori ur les qualification Open - National 100,000.00 0.00 2023-09-27 2023-10-18 2023-12-01 2023-12-31 2024-02-04 2024-08-02 ution me chargé de la sensibilisati productive uses s des consultants on et de la communication su r le projet, INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PARSE-APP8 / PPSD-Recrute ment d’un Consultant Individ Component 3: Institutional s uel pour l’élaboration de la St trengthening, capacity buildi IDA / V3910 A posteriori Individuel Open 75,000.00 22,852.00 Signé 2021-12-13 2021-12-22 2022-01-31 2022-01-25 2022-02-21 2022-01-28 2022-03-28 2022-02-08 2022-09-24 ratégie de Passation des Mar ng and implementation supp ches du Projet pour promouv ort oir le Développement (PPSD). PARSE-APP9 / Manuel d'Exéc Component 3: Institutional s ution-Recrutement d’un Cons trengthening, capacity buildi IDA / V3910 A posteriori Individuel Open 50,000.00 21,972.77 Signé 2022-01-10 2022-04-20 2022-02-28 2022-05-31 2022-03-21 2022-06-15 2022-04-25 2022-06-20 2022-10-22 ultant Individuel pour la réali ng and implementation supp sation du Manuel d'Exécution ort du Projet. PARSE-APP6B / Gestion déch Component 3: Institutional s ets-Recrutement d'un Consul trengthening, capacity buildi En cours d'exécut IDA / V3910 A posteriori Individuel Open 50,000.00 0.00 2022-06-13 2022-06-28 2022-08-01 2022-08-22 2022-09-26 2023-03-25 tant individuel chargé de l'él ng and implementation supp ion aboration d'un Plan de Gestio ort n des Déchets. PARSE-APP6C / PPA-Recrute Component 3: Institutional s Sélection de cons ment d'un Consultant individ trengthening, capacity buildi IDA / V3910 A posteriori ultants par entent Direct 50,000.00 27,254.03 Signé 2022-06-16 2022-06-15 2022-06-26 2022-06-20 2022-08-30 2022-08-22 2023-02-26 uel chargé de l'élaboration d' ng and implementation supp e directe un Plan des Peuples Autochto ort ne. PARSE-APP5B / EIES Hybrid- Recrutement d'un Cabinet po Component 3: Institutional s ur la réalisation des EIES, les Sélection de cons trengthening, capacity buildi Direct - Internation En cours d'exécut PGES y comprennent le PAR IDA / V3910 A posteriori ultants par entent 400,000.00 0.00 2023-05-30 2023-09-29 2023-06-09 2023-08-13 2024-02-09 ng and implementation supp al ion pour les travaux relatifs à l'él e directe ort ectrification de 5 villes provin ciales par des solutions solair es ou hybrides en mini résea u PARSE/24/CS/CDS/23 / Conc eption locaux - Recrutement Component 3: Institutional s d'un Consultant individuel po trengthening, capacity buildi IDA / E0430 A posteriori Individuel Open - National 50,000.00 0.00 Signé 2023-07-31 2023-09-20 2023-09-18 2024-01-29 2023-10-09 2024-01-30 2023-11-13 2024-02-13 2024-05-11 ur la conception et le suivi de ng and implementation supp s travaux de réhabilitation de ort s locaux de l'ACER et l'Assist ance Technique. PARSE/026/CS/INDV/23 / Site Web - Recrutement d’un Con sultant Individuel chargé de l Component 3: Institutional s a création d’un site Web et d’ trengthening, capacity buildi En cours d'exécut IDA / E0430 A posteriori Individuel Open - National 30,000.00 0.00 2023-10-11 2023-11-08 2023-11-29 2024-03-19 2023-12-20 2024-01-24 2024-07-22 une application internet pour ng and implementation supp ion le compte du Ministère charg ort é du Développement de l’Ene rgie et des Ressources Hydra uliques (MDERH). PARSE/030/CS/CDS/24 / Elab Component 3: Institutional s oration d’un plan d’améliorat trengthening, capacity buildi Direct - Internation En cours d'exécut IDA / E0430 A posteriori Individuel 55,000.00 0.00 2024-02-23 2024-02-27 2024-03-04 2024-03-25 2024-04-29 2024-10-26 ion de la gestion et de perfor ng and implementation supp al ion mance de l’ENERCA (Phase 2 ort ) PARSE/031/CS/CDS/24 / CON Component 3: Institutional s Sélection de cons TROLE DES TRAVAUX DE CO trengthening, capacity buildi Direct - Internation En cours d'exécut IDA / E0430 A posteriori ultants par entent 350,000.00 0.00 2024-02-23 2024-02-26 2024-03-04 2024-05-08 2024-11-04 NSTRUCTION DE LA CENTRAL ng and implementation supp al ion e directe E PHOTOVOLTAÏQUE DE DAN ort ZI PARSE/031/CS/INDV/24 / AT i ndividuel - Recrutement d'un Component 3: Institutional s consultant individuel pour l'a trengthening, capacity buildi Open - Internationa En cours d'exécut IDA / E0430 A posteriori Individuel 170,000.00 0.00 2024-02-26 2024-04-08 2024-04-15 2024-05-06 2024-06-10 2024-12-07 ssistance technique au dével ng and implementation supp l ion oppement du solaire hors rés ort eau pour le compte de l'ACE R. Page 4 PARSE/036/CS/CDS/24 / Con seiller juridique- Recrutemen Component 3: Institutional s t d'un consultant individuel, c Sélection de cons trengthening, capacity buildi Direct - Internation En cours d'exécut onseiller juridique en transac IDA / E0430 A posteriori ultants par entent 50,000.00 0.00 2024-05-17 2024-05-23 2024-05-27 2024-05-22 2024-07-31 2025-01-27 ng and implementation supp al ion tion pour la revue de l'offre d e directe ort e mise en œuvre de 15 MWc complémentaires à Danzi en République Centrafricaine PARSE/037/CD/CDS/24 / Con seiller financier- Recrutemen Component 3: Institutional s t d’un consultant individuel, c Sélection de cons trengthening, capacity buildi Direct - Internation En cours d'exécut onseiller financier en transac IDA / E0430 A posteriori ultants par entent 50,000.00 0.00 2024-05-17 2024-05-23 2024-05-27 2024-05-22 2024-07-31 2025-01-27 ng and implementation supp al ion tion pour la revue d’offre de e directe ort SCATEC pour la mise en œuv re de l'extension de 15MWc s upplémentaire à Danzi PARSE/039/CS/CDS/24 / ICR Component 3: Institutional s Sélection de cons PURACEL- Recrutement d’un trengthening, capacity buildi Direct - Internation En cours d'exame IDA / E0430 A posteriori ultants par entent 50,000.00 0.00 2024-07-05 2024-07-04 2024-07-15 2024-09-18 2025-03-17 consultant individuel pour l’él ng and implementation supp al n e directe aboration du Rapport d’Achè ort vement du PURACEL. PARSE/041/CS/CDS/24 / Cont rôle transmission- Recruteme nt d'un Consultant pour la su Component 1: Solar Generat Sélection de cons pervision et contrôle des trav ion and T&D upgrades for V Direct - Internation En attente d'exéc IDA / E0430 A posteriori ultants par entent 530,000.00 0.00 2024-09-02 2024-09-12 2024-11-16 2025-05-15 aux renforcement du réseau RE integration and increased al ution e directe de transmission par la constr access uction d’une boucle de 21 k m en 110 KV et la réhabilitati on des sous-stations C et A. Page 5