PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: Climate Resilient Water Services Project Total Finance ($): USD 100.0 Mln Project Number: P173734 Project Implementation agency THE WATER RESOURCES SERVICE UNDER THE MINISTRY OF AGRICULTURE OF THE KYRGYZ REPUBLIC DEPARTMENT FOR DEVELOPMENT OF DRINKING WATER SUPPLY AND WASTEWATER DISPOSAL Date of the Procurement Plan 15 March 22, 2022 Period covered by this Procurement 15 March 22, 2022 - 31-Dec-2028 Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), Borrower may use the procedures of “Unrestricted” and “Request for Quotations” methods as set forth in the Public Procurement Law dated April 14, 2022 № 27 with amendments dated January 30, 2023 N19 and July 25 2023 N147. When using the Unrestricted method the arrangements shall be subject to the provisions of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. • The request for bids/request for proposals document for civil works and supervision consultants shall require that Bidders/Proposers submitting Bids/Proposals present a signed Code of conduct form, Environmental and Social Performance Declaration and Management Strategies and Implementation Plans. Procurement Documents shall include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. • Bidding documents, including contract forms, acceptable to the Bank shall be used. Bidding documents including contract forms should include appropriate requirements for price adjustment (when applicable), insurance and contract termination. The contract conditions shall provide an appropriate allocation of responsibilities, risks, and liabilities informed by an analysis of which party is best placed to manage the risks, considering the costs and incentives of risk allocation.  Goods: Requirements to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts, including child labor standards, should be added to country’ own procurement documents.  All Unrestricted Bidding for civil works will be conducted using the Standard Procurement Document for Small Works (SPD) issued by the Bank until the country’ own procurement documents are revised and found acceptable. • The bidding process shall not be cancelled solely on the reason that the bid price of the lowest evaluated bidder is larger than the amount allocated by the Borrower for this procurement. • There shall be no preference of any kind applied during procurement of goods and civil works. • Banking support requirement shall not be applied for contracts under World Bank Project. • During the bidding process for civil works, the borrower shall require bidders to submit bids using the format of the Bill of Quantities acceptable to the Bank and provided in the bidding documents issued by the Borrower. The bidders shall use market prices for calculating the unit rates and the bid price. • Foreign bidders shall be allowed to participate in Unrestricted Bidding without restrictions of any kind. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement method such as “Request for Quotation” may be applied on the same conditions stated above for procuring limited quantities of readily available off-the-shelf goods and for simple works (current repairs, finishing repairs of premises, including existing utilities). Not less than three quotations shall be requested to ensure competition and adequate time should be provided to the participants to prepare their quotations. Use of the Direction Selection method may be appropriate when there is only one suitable firm or there is a justification in line with circumstances included in paragraph 6.9 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement “Not Applicable” PROCUREMENT Kyrgyz Republic : Climate Resilient Water Services Project PLAN General Information Country: Kyrgyz Republic 2022-12-10 Bank’s Approval Date of the Original Procurement Plan: 2024-08-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173734 GPN Date: 2023-01-31 Project Name: Climate Resilient Water Services Project Loan / Credit No: IDA / E0090, IDA / 70810 The Water Resources Service under the Ministry of Agriculture of the Kyrgyz Republic Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B CREWSP/CW/C1.2/RFB/2 / Re ids - Works ( Infrastructure Investments a Single Stage - One E 2024-02-1 novation of the Head Office IDA / 70810 Post Request for Bids Open - National without preq 0.00 Signed 2023-07-10 2023-12-11 2023-07-15 2023-12-13 2023-08-26 2024-01-09 2023-09-09 2024-01-24 2023-10-21 2024-02-13 nd Service Improvements nvelope 8 and Water Center WRS ualification) SPD Request for B CREWSP/CW/C1.2/RFB/1 / M ids - Works ( Infrastructure Investments a Open - Internationa Single Stage - Two E Under Revie 2029-06-0 odernization of Kurshab-Sai ir IDA / 70810 Prior Request for Bids without preq 0.00 2024-08-28 2024-09-02 2024-10-14 2024-12-23 2025-01-29 nd Service Improvements l nvelope w 7 rigation scheme – Osh ualification) SPD Request for B CREWSP/CW/C1.2/RFB/3 / M ids - Works ( Infrastructure Investments a Open - Internationa Single Stage - Two E Under Revie 2027-10-1 odernization Kara-Unkur Irrig IDA / 70810 Prior Request for Bids without preq 0.00 2024-08-28 2024-09-02 2024-10-14 2024-12-23 2025-01-29 nd Service Improvements l nvelope w 6 ation Scheme -JalaL-Abad ualification) SPD Request for B REWSP/CW/C1.2/RFB/2 / Mod ids - Works ( Infrastructure Investments a Open - Internationa Single Stage - Two E Pending Imp 2026-07-2 ernization of Shakhimardan Ir IDA / 70810 Prior Request for Bids without preq 0.00 2024-08-28 2024-09-02 2024-10-14 2024-12-23 2025-01-29 nd Service Improvements l nvelope lementation 3 rigation Scheme -Batken ualification) SPD GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CREWSP/G/C.2.3/ICB/1 / Cre Institutional Strengthening f ation of biochemical laborato or Climate Resilient Service Open - Internationa Single Stage - One E ries in Bishkek and on the ter IDA / E0090 Delivery, Water Resources M Prior Request for Bids 0.00 Canceled 2024-01-03 2024-01-22 2024-03-04 2024-05-30 2024-07-01 2026-06-01 l nvelope ritory of the KSA basin (Depa anagement and Dam Manag rtment of Environmental Mon ement itoring (MoNRETS)) Institutional Strengthening f CREWSP/G/C.2.2/NCB/1 / Ins or Climate Resilient Service Single Stage - One E Pending Impl IDA / E0090 Post Request for Bids Open - National 0.00 2023-01-03 2023-01-08 2023-02-19 2023-03-21 2023-04-25 2023-06-15 trumentation for KSA Delivery, Water Resources M nvelope ementation anagement and Dam Manag ement CREWSP/G/C.2.3/RFB/1 / Lab Institutional Strengthening f oratory modernization for the or Climate Resilient Service Open - Internationa Single Stage - One E IDA / E0090 Prior Request for Bids 0.00 Signed 2023-05-15 2023-06-30 2023-05-28 2023-07-07 2023-07-09 2023-08-21 2023-09-07 2023-09-12 2023-10-19 2023-10-19 2024-02-16 Department of Environmenta Delivery, Water Resources M l nvelope l Monitoring anagement and Dam Manag ement CREWSP/G/C.3.1/RFQ/3 / IT E Project Management, M&E a Request for Quota Single Stage - One E IDA / E0090 Post Open - National 0.00 Canceled 2023-04-24 2023-05-26 2023-06-25 quipment and furniture for PI nd Professional Developmen tions nvelope U t CREWSP/G/C.2.3/RFQ/1 / Inst Institutional Strengthening f allation of a fire alarm syste or Climate Resilient Service Request for Quota Single Stage - One E Under Imple IDA / E0090 Post Open - National 0.00 2023-04-15 2023-06-12 2023-07-12 m for the Department of Envi Delivery, Water Resources M tions nvelope mentation ronmental Monitoring anagement and Dam Manag ement CREWSP/G/C.2.3/RFB/2 / Veh Institutional Strengthening f icles for the Department of E or Climate Resilient Service Single Stage - One E Under Imple IDA / E0090 Post Request for Bids Open - National 0.00 2023-06-26 2023-07-02 2023-06-28 2023-07-07 2023-07-14 2023-07-27 2023-07-28 2023-08-14 2023-09-28 nvironmental Monitoring for l Delivery, Water Resources M nvelope mentation aboratory research anagement and Dam Manag ement CREWSP/G/C.2.3/RFQ/2 / Pro Institutional Strengthening f curement of a graphite attac or Climate Resilient Service Request for Quota Open - Internationa Single Stage - One E IDA / E0090 Post 0.00 Canceled 2023-04-21 2023-06-01 2023-07-31 hment for the Department of Delivery, Water Resources M tions l nvelope Environmental Monitoring anagement and Dam Manag ement CREWSP/G/C.2.3/RFQ/3 / Pro Institutional Strengthening f curement of a spectrophoto or Climate Resilient Service Request for Quota Open - Internationa Single Stage - One E IDA / E0090 Post 0.00 Signed 2023-07-04 2023-07-07 2023-08-19 2023-09-05 2023-10-18 meter and graphite attachme Delivery, Water Resources M tions l nvelope nt for the Department of Envi anagement and Dam Manag ronmental Monitoring ement Institutional Strengthening f CREWSP/G/C.2.4/RFB/2 / Equ or Climate Resilient Service Open - Internationa Single Stage - One E Pending Impl ipment for remote sensing a IDA / E0090 Post Request for Bids 0.00 2025-07-03 2025-07-08 2025-08-19 2025-09-16 2025-10-28 2026-01-26 Delivery, Water Resources M l nvelope ementation nd control of dams anagement and Dam Manag ement Institutional Strengthening f CREWSP/G/C.2.4/RFB/1 / Pur or Climate Resilient Service Single Stage - One E chase of electro mobiles cars IDA / E0090 Post Request for Bids Open - National 0.00 Signed 2023-07-02 2023-07-02 2023-07-07 2023-07-07 2023-08-04 2023-07-27 2023-08-18 2023-08-15 2023-08-30 2023-09-15 2023-10-29 Delivery, Water Resources M nvelope for WRS and PIU (4 units) anagement and Dam Manag ement CREWSP/G/C.2.3/RFB/5 / Pro curement of laboratory auxili Institutional Strengthening f ary materials, overalls and m or Climate Resilient Service easuring instruments for the Single Stage - Two E Under Imple IDA / E0090 Delivery, Water Resources M Post Request for Bids Open - National 0.00 2024-01-15 2024-03-13 2024-01-20 2024-05-14 2024-02-04 2024-04-09 2024-02-25 2024-05-13 2024-03-17 2024-05-16 Environmental Monitoring De nvelope mentation anagement and Dam Manag partment (Lot #1- measuring ement instruments; Lo#2 - auxiliary equipment and materials; Lot #3 - laboratory clothing.) CREWSP/G/C.2.3/RFQ/4 / Pro Institutional Strengthening f curement of water pollution or Climate Resilient Service Request for Quota Open - Internationa Single Stage - One E IDA / E0090 Post 0.00 Canceled 2024-04-03 2024-04-23 2024-05-28 2024-07-27 measuring devices for the En Delivery, Water Resources M tions l nvelope vironmental Monitoring Depa anagement and Dam Manag rtment ement CREWSP/G/C.2.3/RFB/6 / Pro curement of water pollution measuring devices, laborator Institutional Strengthening f y auxilliary euipment and ma or Climate Resilient Service Open - Internationa Single Stage - One E Under Imple terials for the Environmental IDA / E0090 Delivery, Water Resources M Post Request for Bids 0.00 2024-07-15 2024-08-13 2024-07-19 2024-08-12 2024-08-30 2024-09-30 2024-11-11 2025-04-10 l nvelope mentation Monitoring Department (Lot anagement and Dam Manag 1: Water pollution measuring ement devices; Lot 2: Auxilliary equi pment and materials; Lot 3:M esurement equipment ) Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CREWSP/NC1/G/SSS/01 / For Institutional Strengthening f overseas tour to study intern or Climate Resilient Service Direct - Internation IDA / E0090 Post Direct Selection 0.00 Canceled 2024-01-15 2024-01-20 2024-02-24 2024-03-25 ational experience in irrigatio Delivery, Water Resources M al n water management anagement and Dam Manag ement CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CREWSP/CS/C.3.3/CQS/1 / Se Project Management, M&E a Consultant Qualifi Under Implement lection of a monitoring and e IDA / E0090 nd Professional Developmen Post Open - National 0.00 2023-01-03 2023-07-07 2023-01-24 2023-03-29 2023-04-28 2023-06-04 2027-12-31 cation Selection ation valuation consulting compan t y CREWSP/CS/C.3.2/LCS/1 / Au Project Management, M&E a Least Cost Selecti Open - Internationa IDA / E0090 Post 0.00 Signed 2023-01-21 2023-03-17 2023-02-09 2023-03-30 2023-03-27 2023-05-05 2023-04-24 2023-06-19 2023-05-24 2023-06-27 2023-06-28 2023-07-17 2023-08-01 2023-08-19 2027-12-31 dit nd Professional Developmen on l t CREWSP/CS/C.1.2/QCBS/4 / Infrastructure Investments a Quality And Cost- Open - Internationa Consulting company for engi IDA / E0090 Prior 0.00 Canceled 2023-03-02 2023-03-23 2023-05-06 2023-06-03 2023-06-23 2023-07-28 2023-08-23 2027-12-31 nd Service Improvements Based Selection l neering services CREWSP/CS/C.1.2/QCBS/2 / Institutional Strengthening f Design and estimate docume or Climate Resilient Service Quality And Cost- Open - Internationa IDA / E0090 Post 0.00 Canceled 2022-02-14 2022-03-07 2022-04-20 2022-05-18 2022-06-17 2022-07-22 2022-08-26 2023-03-01 ntation of the Shakhimardan Delivery, Water Resources M Based Selection l river anagement and Dam Manag ement CREWSP/CS/C.1.2/QCBS/3 / Infrastructure Investments a Quality And Cost- Open - Internationa Design and estimate docume IDA / E0090 Post 0.00 Canceled 2022-02-14 2022-03-07 2022-04-20 2022-05-18 2022-06-17 2022-07-22 2022-08-26 2023-08-26 nd Service Improvements Based Selection l ntation of the Kara-Ungur riv er (Levaya Vetka) CREWSP/CS/C.1.2/QCBS/1. / Infrastructure Investments a Quality And Cost- Open - Internationa Design and estimate docume IDA / E0090 Prior 0.00 Canceled 2023-01-22 2023-02-12 2023-03-28 2023-04-25 2023-05-25 2023-06-29 2023-08-03 2027-12-31 nd Service Improvements Based Selection l ntation of the Kurshab river CREWSP/CS/C.1.2/QCBS/01 / Preparation of Detailed Desig Infrastructure Investments a Quality And Cost- Open - Internationa IDA / E0090 Prior 0.00 Under Review 2023-02-22 2023-03-06 2023-03-08 2023-03-13 2023-04-19 2023-05-29 2023-05-26 2023-08-02 2023-06-25 2023-10-03 2023-08-26 2023-10-03 2023-09-24 2023-10-18 2028-10-31 n, Assistance in procurement nd Service Improvements Based Selection l and Supervision of civil work s CREWSP/CS/C.3.3/CQS/3 / Se Institutional Strengthening f lection of a monitoring and e or Climate Resilient Service Consultant Qualifi Under Implement IDA / 70810 Post Open - National 0.00 2023-09-18 2024-08-06 2023-10-02 2023-11-06 2023-11-11 2023-11-30 2028-12-21 valuation consulting compan Delivery, Water Resources M cation Selection ation y anagement and Dam Manag ement CREWSP/CS/C.2.2/QCBS/1 / Institutional Strengthening f Consulting company for impl or Climate Resilient Service Quality And Cost- Open - Internationa Pending Impleme IDA / E0090 Prior 0.00 2025-01-15 2025-01-29 2025-03-03 2025-04-17 2025-05-17 2025-05-25 2025-06-22 2028-10-31 ementation of an existing dig Delivery, Water Resources M Based Selection l ntation ital information system anagement and Dam Manag ement CREWSP/CS/C.2.3/QCBS/1 / Institutional Strengthening f Modernization of the databas or Climate Resilient Service Quality And Cost- Open - Internationa Pending Impleme IDA / E0090 Post 0.00 2024-07-15 2024-07-29 2024-08-26 2024-09-25 2024-10-09 2024-10-24 2024-11-21 2025-11-16 e of the Department of Envir Delivery, Water Resources M Based Selection l ntation onmental Monitoring anagement and Dam Manag ement CREWSP/CS/C.3.5/CQS/1 / Se Project Management, M&E a lection of a consulting compa Consultant Qualifi Pending Impleme IDA / E0090 nd Professional Developmen Post Open - National 0.00 2024-10-15 2024-10-29 2024-11-18 2024-11-23 2025-01-12 2025-04-12 ny for the preparation of feas cation Selection ntation t ibility studies for future proje cts INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CREWSP/CS/C.2.3/IC/1 / Loca Institutional Strengthening f l consultant lawyer to update or Climate Resilient Service Individual Consult IDA / E0090 Post Open - National 0.00 Signed 2023-03-20 2023-04-12 2023-04-26 2023-05-15 2023-05-01 2023-05-30 2023-05-20 2023-06-01 2023-11-16 the regulatory and legal docu Delivery, Water Resources M ant Selection ments in terms of calculating anagement and Dam Manag the tariff for the DEM ement Institutional Strengthening f CREWSP/CS/C.2.3/IC/2 / Loca or Climate Resilient Service Individual Consult Under Implement l consultant economist to rev IDA / E0090 Post Open - National 0.00 2023-03-14 2023-03-28 2023-04-21 2023-04-21 2023-05-01 2023-10-28 Delivery, Water Resources M ant Selection ation iew the tariff of EMS services anagement and Dam Manag ement Institutional Strengthening f KG-DWRLI-354158-CS-CDS / or Climate Resilient Service Direct - Internation International Short-term Proc IDA / E0090 Post Direct Selection 0.00 Signed 2023-04-05 2023-04-03 2023-04-06 2023-04-06 2023-04-09 2023-04-17 2023-08-30 Delivery, Water Resources M al urement Specialist anagement and Dam Manag ement Institutional Strengthening f CREWSP/CS/C.2.3/IC/8 / Loca or Climate Resilient Service Individual Consult Under Implement l consultant quality and accre IDA / E0090 Post Open - National 0.00 2023-06-26 2023-06-29 2023-07-20 2023-07-19 2023-07-20 2023-08-05 2024-02-01 Delivery, Water Resources M ant Selection ation ditation consultant for DEM anagement and Dam Manag ement Institutional Strengthening f CREWSP/CS/C.2.2/IC/2 / Shor or Climate Resilient Service Individual Consult Pending Impleme t-term Consultant on the per IDA / E0090 Post Open - National 0.00 2023-11-05 2023-12-15 2023-12-23 2024-01-03 2024-12-31 Delivery, Water Resources M ant Selection ntation mitting system anagement and Dam Manag ement Institutional Strengthening f CREWSP/CS/C.2.2/IC/3 / Shor or Climate Resilient Service Individual Consult Pending Impleme t-term Consultant on monitor IDA / E0090 Post Open - National 0.00 2023-11-05 2023-11-27 2023-11-30 2023-12-03 2027-11-28 Delivery, Water Resources M ant Selection ntation ing and quality of water anagement and Dam Manag ement Institutional Strengthening f CREWSP/CS/C.2.2/DS/6 / IT-L or Climate Resilient Service IDA / E0090 Post Direct Selection Direct - National 0.00 Canceled 2023-06-22 2024-04-01 2023-06-22 2024-04-01 2028-12-31 AN Specialist Delivery, Water Resources M anagement and Dam Manag ement Institutional Strengthening f CREWSP/CS/C.2.2/DS/5 / CA or Climate Resilient Service IDA / E0090 Post Direct Selection Direct - National 0.00 Canceled 2023-06-22 2024-03-28 2023-06-22 2024-08-31 2028-12-31 D Specialist Delivery, Water Resources M anagement and Dam Manag ement Page 2 Institutional Strengthening f CREWSP/CS/C.2.2/IC/4 / Insti or Climate Resilient Service Individual Consult tutional Development Special IDA / E0090 Post Open - National 0.00 Canceled 2024-01-03 2024-02-24 2024-02-29 2024-03-04 2027-12-31 Delivery, Water Resources M ant Selection ist anagement and Dam Manag ement Institutional Strengthening f CREWSP/CS/C.2.2/DS/2 / Soc or Climate Resilient Service iology and Feedback Speciali IDA / E0090 Post Direct Selection Direct - National 0.00 Canceled 2023-01-21 2023-01-21 2023-01-23 2028-12-31 Delivery, Water Resources M st anagement and Dam Manag ement Institutional Strengthening f CREWSP/CS/C.2.4/IC/1 / Data or Climate Resilient Service Individual Consult base filling out Сonsultant (G IDA / E0090 Post Open - National 0.00 Canceled 2023-11-05 2023-12-24 2023-12-25 2024-01-01 2028-12-31 Delivery, Water Resources M ant Selection roup of independent experts) anagement and Dam Manag ement CREWSP/CS/C.2.4/IC/3 / Law Institutional Strengthening f yer for the development of th or Climate Resilient Service Individual Consult IDA / E0090 Post Open - National 0.00 Canceled 2022-11-05 2022-12-25 2022-12-28 2023-01-01 2028-12-31 e regulatory legal framework Delivery, Water Resources M ant Selection (Group of independent exper anagement and Dam Manag ts) ement Institutional Strengthening f CREWSP/CS/C.2.2/DS/1 / Env or Climate Resilient Service IDA / E0090 Post Direct Selection Direct - National 0.00 Canceled 2023-01-21 2023-01-31 2023-04-06 2028-12-31 ironmental Specialist Delivery, Water Resources M anagement and Dam Manag ement CREWSP/CS/C.2.4/IC/2 / Inter Institutional Strengthening f national Consultant for Devel or Climate Resilient Service Individual Consult Open - Internationa IDA / E0090 Post 0.00 Canceled 2023-11-06 2023-12-02 2023-12-12 2024-01-02 2024-10-31 opment of Technical Guidelin Delivery, Water Resources M ant Selection l es for Dams (Group of indepe anagement and Dam Manag ndent experts) ement CREWSP/CS/C.2.4/IC/7 / Loca Institutional Strengthening f l consultant to supervise the or Climate Resilient Service Individual Consult IDA / E0090 Post Open - National 0.00 Under Review 2023-12-25 2024-08-13 2024-01-24 2024-01-26 2024-02-11 2025-06-10 management of dams and le Delivery, Water Resources M ant Selection vees for th WRS anagement and Dam Manag ement Institutional Strengthening f CREWSP/CS/C.2.4/IC/8 / Loca or Climate Resilient Service Individual Consult l legal counsel for the WRS D IDA / E0090 Post Open - National 0.00 Under Review 2023-12-25 2024-08-13 2024-01-17 2024-01-19 2024-02-04 2025-06-03 Delivery, Water Resources M ant Selection am and Levee Authority anagement and Dam Manag ement CREWSP/CS/C.2.4/IC/9 / Loca Institutional Strengthening f l Consultant Hydrogeologist f or Climate Resilient Service Individual Consult Under Implement IDA / E0090 Post Open - National 0.00 2023-12-25 2024-04-30 2024-01-17 2024-01-19 2024-02-04 2025-06-03 or theWRS Dam and Dams A Delivery, Water Resources M ant Selection ation uthority anagement and Dam Manag ement CREWSP/CS/C.2.4/IC/10 / Loc Institutional Strengthening f al Consultant hydraulic engi or Climate Resilient Service Individual Consult IDA / E0090 Post Open - National 0.00 Under Review 2023-12-25 2024-08-13 2024-01-17 2024-01-19 2024-02-04 2025-06-03 neering consultant for the W Delivery, Water Resources M ant Selection RS Dam and Dams Authority anagement and Dam Manag ement CREWSP/CS/C.2.4/IC/4 / Rep Institutional Strengthening f ublican Dam Management Su or Climate Resilient Service Individual Consult IDA / E0090 Post Open - National 0.00 Canceled 2023-11-05 2023-12-24 2023-12-26 2024-01-01 2028-12-31 pervision Consultant (Group Delivery, Water Resources M ant Selection of independent experts) anagement and Dam Manag ement CREWSP/CS/C.2.4/DS/5 / Inte Institutional Strengthening f rnational Consultant for Deve or Climate Resilient Service Individual Consult Direct - Internation Under Implement IDA / E0090 Post 0.00 2024-03-13 2024-03-18 2024-03-21 2024-03-23 2024-05-09 2025-10-30 lopment of Technical Guideli Delivery, Water Resources M ant Selection al ation nes for Dams anagement and Dam Manag ement Institutional Strengthening f CREWSP/CS/C.2.2/DS/4 / Info or Climate Resilient Service rmation Technology Consulta IDA / E0090 Post Direct Selection Direct - National 0.00 Canceled 2023-01-21 2023-01-21 2023-01-23 2028-12-31 Delivery, Water Resources M nt anagement and Dam Manag ement Institutional Strengthening f CREWSP/CS/C.2.2/DS/3 / Con or Climate Resilient Service tent administrator and web d IDA / E0090 Post Direct Selection Direct - National 0.00 Canceled 2024-04-22 2024-04-26 2024-04-28 2028-12-30 Delivery, Water Resources M esigner anagement and Dam Manag ement CREWSP/CS/C.2.3/IC/3 / Inter Institutional Strengthening f national consultant to prepar or Climate Resilient Service Individual Consult Open - Internationa Pending Impleme IDA / E0090 Post 0.00 2024-05-15 2024-06-06 2024-06-06 2024-06-15 2024-12-12 e the roadmap and to prepar Delivery, Water Resources M ant Selection l ntation e the monitoring plan for the anagement and Dam Manag DEM ement Institutional Strengthening f CREWSP/CS/C.2.3/IC/4 / Nati or Climate Resilient Service Individual Consult Pending Impleme onal consultant to modernize IDA / E0090 Post Open - National 0.00 2024-08-29 2024-10-17 2024-11-07 2024-12-12 2026-06-05 Delivery, Water Resources M ant Selection ntation the DEM information system anagement and Dam Manag ement Page 3