PROCUREMENT PLAN (Textual Part) Project information: Preparation of Proposed Sustainable Forests and Livelihood Project Project Implementation agency: Forest Department of Ministry of Environment and Forest, Bangladesh Date of the Procurement Plan: September 13, 2017 Period covered by this Procurement Plan: September 2017 to June 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules 2008, as amended in August 2009) , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions : a) e-GP system of the country for national competitive bidding (NCB) shall be followed using Standard/Model Procurement documents satisfactory to the Bank b) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; c) Bids should be submitted and opened in public in one location immediately after the deadline for submission; d) Lottery in award of contracts shall not be allowed; e) Bidders’ qualification/experience requirement shall be mandatory f) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). “Not Applicable” PROCUREMENT Bangladesh : Sustainable Forests & Livelihoods (SUFAL) Project PLAN General Information Country: Bangladesh 2020-10-11 Bank’s Approval Date of the Original Procurement Plan: 2023-08-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161996 GPN Date: 2019-02-26 Project Name: Sustainable Forests & Livelihoods (SUFAL) Project Loan / Credit No: IDA / 63250 Public Works Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned WD 51 / Sub soil investigatio n for the construction of offic e building ,green house, staff Strengthening Collaborative Request for Quota Single Stage - One E 2020-12-2 dormitory ,nursery shed with IDA / 63250 Forest and Protected Areas Post Limited 10,420.00 3,691.26 Signed 2020-10-21 2020-11-11 2020-11-09 2020-11-25 tions nvelope 4 seed storage at Hathazari SF Management NTC, beat office and staff ba rrack at Rangunia and Beat o ffice at Rawzan. WD 52 / Sub soil investigatio n for the construction of ran Strengthening Collaborative Request for Quota Single Stage - One E 2020-12-0 ge office at Bashkhali, officer IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 3,443.19 Signed 2020-10-21 2020-11-10 2020-11-09 2020-11-13 tions nvelope 9 's dormitory & staff barrack a Management t Chattogram Sadar and staff barrack at Satkania WD 53 / Sub soil investigatio Strengthening Collaborative n for the construction of rang Request for Quota Single Stage - One E 2020-12-0 IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 3,150.35 Signed 2020-10-21 2020-10-25 2020-11-09 2020-11-06 e office and beat office at Mir tions nvelope 9 Management ersorai and staff barrack (2 n os) at Sitakundu. WD 54 / Sub soil investigatio n for the construction of beat Strengthening Collaborative Request for Quota Single Stage - One E 2020-12-0 cum check station & staff bar IDA / 63250 Forest and Protected Areas Post Limited 7,442.00 5,336.40 Signed 2020-10-21 2020-12-20 2020-11-09 2020-12-30 tions nvelope 9 rack at Chokoria and staff ba Management rrack, range office at Coxbaz ar Sadar WD 55 / Sub soil investigatio Strengthening Collaborative n for the construction of staff Request for Quota Single Stage - One E 2020-12-2 IDA / 63250 Forest and Protected Areas Post Limited 7,442.00 5,336.40 Signed 2020-10-21 2020-12-20 2020-11-09 2020-12-30 barrack, beat office at Ramu tions nvelope 4 Management and Ukhia and beat office at Teknaf WD 56 / Sub soil investigatio n for the construction of Gazi Strengthening Collaborative Request for Quota Single Stage - One E 2021-01-1 pur SFNTC main bldg, staff d IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 3,630.51 Signed 2020-11-22 2021-06-02 2020-12-10 2021-06-21 tions nvelope 0 ormitory, nursery shed cum s Management eed storage and green house . WD 57 / Sub soil investigatio n for the construction of Gazi pur SFNTC wildlife staff dorm Strengthening Collaborative Request for Quota Single Stage - One E 2020-12-2 itory, kaliakoir range office, b IDA / 63250 Forest and Protected Areas Post Limited 10,420.00 7,049.04 Signed 2020-10-21 2021-06-10 2020-11-09 2021-06-21 tions nvelope 4 eat office, staff barrack & Ga Management zipur Sadar staff barrack , Ka pasia camp office and Sripur Staff barrack. WD 58 / Sub soil investigatio n for the construction of Jass Strengthening Collaborative ore SFNTC office building, sta Request for Quota Single Stage - One E 2020-12-2 IDA / 63250 Forest and Protected Areas Post Limited 10,420.00 1,586.18 Signed 2020-10-21 2020-11-04 2020-11-09 2020-12-22 ff dormitory, Nursery shed wi tions nvelope 4 Management th seed storage, DFO office b uilding, Residence, and Jasso re Sadar staff barrack, Green house. WD 59 / Sub soil investigatio Strengthening Collaborative n for the construction of Offic Request for Quota Single Stage - One E 2020-12-0 IDA / 63250 Forest and Protected Areas Post Limited 2,980.00 2,903.12 Signed 2020-10-21 2021-09-28 2020-11-09 2021-10-08 er's dormitory and Staff Barr tions nvelope 3 Management ack at Barishal Sadar. WD 61 / Sub soil investigatio n for the construction of rang Strengthening Collaborative e office, beat office, staff bar Request for Quota Single Stage - One E 2020-12-2 IDA / 63250 Forest and Protected Areas Post Limited 8,930.00 4,316.90 Signed 2020-10-21 2021-01-04 2020-11-09 2021-01-26 rack at Charfasion & Doulatk tions nvelope 4 Management han range office & Monpura Camp office and Tajimuddin Camp office. WD 62 / Sub soil investigatio Strengthening Collaborative Request for Quota Single Stage - One E Pending Imp 2020-11-2 n for the construction of Panc IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 0.00 2020-10-21 2020-11-09 tions nvelope lementation 9 hagar-Debigonj Range office Management , Debigonj. WD 63 / Sub soil investigatio Strengthening Collaborative Request for Quota Single Stage - One E 2020-12-0 n for the construction of Jhina IDA / 63250 Forest and Protected Areas Post Limited 2,980.00 0.00 Canceled 2020-10-21 2020-12-14 2020-11-09 tions nvelope 3 igati range office and Sribord Management i staff barrack. WD 64 / Sub soil investigatio Strengthening Collaborative Request for Quota Single Stage - One E 2020-12-0 n for the construction of staf IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 566.00 Signed 2020-10-21 2020-11-02 2020-11-09 2020-11-13 tions nvelope 9 f barrack (2 nos) at Shapaher Management , Naogaon. WD 65 / Sub soil investigatio Strengthening Collaborative n for the construction of , ka Request for Quota Single Stage - One E 2020-12-0 IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 2,936.49 Signed 2020-10-21 2021-01-18 2020-11-09 2021-02-05 malganj camp office, beat off tions nvelope 9 Management ice and Juri staff barrack. WD 66 / Sub soil investigatio n for the construction of Ghat Strengthening Collaborative Request for Quota Single Stage - One E 2020-12-0 ail range office & Shakhipur c IDA / 63250 Forest and Protected Areas Post Limited 7,442.00 1,874.83 Signed 2020-10-21 2020-10-28 2020-11-09 2020-12-09 tions nvelope 9 amp office, staff barrack , be Management at office and Modhupur staff barrack WD 67 / Sub soil investigatio Strengthening Collaborative Request for Quota Single Stage - One E 2020-11-2 n of Thakurgaon Sadar - Pirg IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 1,122.48 Signed 2020-10-21 2020-12-07 2020-11-09 2020-12-16 tions nvelope 9 onj Beat office, Thakurgaon S Management adar. WD 68 / Sub soil investigatio Strengthening Collaborative n for the construction of Sad Request for Quota Single Stage - One E 2020-12-0 IDA / 63250 Forest and Protected Areas Post Limited 7,442.00 7,098.88 Signed 2020-10-21 2020-11-12 2020-11-09 2020-12-01 ar officer's dormitory, DFO of tions nvelope 9 Management fice & beat office and Fulbari a staff barrack Page 1 WD 69 / Sub soil investigatio Strengthening Collaborative Request for Quota Single Stage - One E Pending Imp 2020-11-2 n for the construction of Lak IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 0.00 2020-10-21 2020-11-09 tions nvelope lementation 9 smipur sadar-Bhabanigonj Be Management at office. WD 70 / Sub soil investigatio Strengthening Collaborative n for the construction of Noa Request for Quota Single Stage - One E 2020-12-0 IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 0.00 Canceled 2020-10-21 2020-10-18 2020-11-09 khali Sadar DFO residence & tions nvelope 9 Management Hatia Camp office (2 nos) an d Hatia staff barrack. WD 71 / Sub soil investigatio Strengthening Collaborative n for the construction of Patu Request for Quota Single Stage - One E Pending Imp 2020-12-0 IDA / 63250 Forest and Protected Areas Post Limited 4,465.00 0.00 2020-10-21 2020-11-09 akhali camp office, Sadar DF tions nvelope lementation 3 Management O building and Staff barrack. WD 72 / Sub soil investigatio Strengthening Collaborative n for the construction of Amt Request for Quota Single Stage - One E Pending Imp 2020-12-0 IDA / 63250 Forest and Protected Areas Post Limited 4,465.00 0.00 2020-10-21 2020-11-09 oli camp office and Pathorgh tions nvelope lementation 3 Management ata camp office, staff barrack . WD 73 / Sub soil investigatio Strengthening Collaborative n for the construction of Mad Request for Quota Single Stage - One E Pending Imp 2020-12-0 IDA / 63250 Forest and Protected Areas Post Limited 4,465.00 0.00 2020-10-21 2020-11-09 habpur beat office and Chun tions nvelope lementation 3 Management arughat staff barrack (2 nos). WD 74 / Sub soil investigatio Strengthening Collaborative Request for Quota Single Stage - One E 2020-11-2 n for the construction of Shu IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 1,283.94 Signed 2020-10-21 2020-12-09 2020-11-09 2021-01-11 tions nvelope 9 namgonj-Chatak Beat office. Management WD 75 / Sub soil investigatio Strengthening Collaborative Request for Quota Single Stage - One E 2020-11-2 n for the construction of CCF' IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 1,389.72 Signed 2020-10-21 2021-06-13 2020-11-09 2021-06-21 tions nvelope 9 s Banglow. Management WD 77 / Digital survey for th e construction of office bldg, Strengthening Collaborative green house, staff dormitory, Request for Quota Single Stage - One E 2020-11-1 IDA / 63250 Forest and Protected Areas Post Limited 2,085.00 530.69 Signed 2020-10-21 2020-11-11 2020-11-09 2020-11-25 nursery shed with seed stora tions nvelope 9 Management ge at Hathazari & beat office, staff barrack at Rangunia an d beat office at Rawzan WD 78 / Digital survey for th e construction of range offic Strengthening Collaborative Request for Quota Single Stage - One E 2020-11-1 e at Bashkhali & officer's dor IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 472.23 Signed 2020-10-21 2020-11-04 2020-11-09 2020-11-12 tions nvelope 9 mitory, staff barrack at Chatt Management ogram Sadar and staff barrac k at Satkania WD 79 / Digital survey for th Strengthening Collaborative e constructionof range office, Request for Quota Single Stage - One E 2020-11-1 IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 872.69 Signed 2020-10-21 2021-01-14 2020-11-09 2021-02-03 beat office at Mirersorai and tions nvelope 9 Management staff barrack (2 nos) at Sitak undu WD 80 / Digital survey for th e construction of beat cum c heck station, staff barrack at Strengthening Collaborative Request for Quota Single Stage - One E 2020-11-1 Chokoria, staff barrack, rang IDA / 63250 Forest and Protected Areas Post Limited 2,980.00 2,358.63 Signed 2020-10-21 2020-12-01 2020-11-09 2020-12-15 tions nvelope 9 e office at Coxbazar Sadar, st Management aff barrack, beat office at Ra mu and Ukhia and beat office at Teknaf. WD 81 / Digital survey for G azipur SFNTC main bldg, staff dormitory, nursery shed, gre Strengthening Collaborative en house, Gazipur SFNTC wil Request for Quota Single Stage - One E 2020-12-2 IDA / 63250 Forest and Protected Areas Post Limited 3,275.00 2,846.00 Signed 2020-11-22 2021-06-10 2020-12-10 2021-06-21 dlife staff dormitory, kaliakoir tions nvelope 0 Management range office, beat office, staff barrack, Gazipur Sadar staff barrack, Kapasia camp Office and Sripur Staff barrack. WD 82 / Digital survey for th e construction of Jassore SFN Strengthening Collaborative TC office building, staff dormi Request for Quota Single Stage - One E 2020-11-1 IDA / 63250 Forest and Protected Areas Post Limited 2,085.00 386.10 Signed 2020-10-21 2020-11-04 2020-11-09 2020-12-22 tory, Nursery shed with seed tions nvelope 9 Management storage, DFO office building, Residence and Jassore Sadar staff barrack, Green house. WD 83 / Digital survey for th Strengthening Collaborative Request for Quota Single Stage - One E 2020-11-1 e construction of Officer's dor IDA / 63250 Forest and Protected Areas Post Limited 597.00 583.41 Signed 2020-10-21 2021-10-03 2020-11-09 2021-10-18 tions nvelope 9 mitory and Staff Barrack at B Management arishal Sadar WD 85 / Digital survey for th e construction of range office Strengthening Collaborative , beat office, staff barrack at Request for Quota Single Stage - One E 2020-11-1 IDA / 63250 Forest and Protected Areas Post Limited 1,786.00 764.08 Signed 2020-10-21 2021-01-04 2020-11-09 2021-01-26 Charfasion & Doulatkhan ran tions nvelope 9 Management ge office & Monpura Camp of fice and Tajimuddin Camp off ice WD 86 / Digital survey for th Strengthening Collaborative Request for Quota Single Stage - One E 2020-11-1 e construction of Jhinaigati ra IDA / 63250 Forest and Protected Areas Post Limited 597.00 479.04 Signed 2020-10-21 2020-12-14 2020-11-09 2020-12-31 tions nvelope 9 nge office and Sribordi staff b Management arrack. WD 87 / Digital survey for th Strengthening Collaborative Request for Quota Single Stage - One E 2020-11-1 e construction of staff barrac IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 235.50 Signed 2020-10-21 2020-11-12 2020-11-09 2020-11-13 tions nvelope 9 k (2 nos) at Shapaher, Naoga Management on. WD 88 / Digital survey for th Strengthening Collaborative Request for Quota Single Stage - One E 2020-11-1 e construction of kamaganj c IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 577.23 Signed 2020-10-21 2021-01-21 2020-11-09 2021-02-05 tions nvelope 9 amp office and beat office an Management d Juri staff barrack. WD 89 / Digital survey for th e construction of Ghatail ran Strengthening Collaborative Request for Quota Single Stage - One E 2020-11-1 ge office & Shakhipur camp o IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 1,108.56 Signed 2020-10-21 2020-10-28 2020-11-09 2020-12-09 tions nvelope 9 ffice, staff barrack , beat offic Management e, and Modhupur staff barrac k. WD 90 / Digital survey for th Strengthening Collaborative e construction of Sadar office Request for Quota Single Stage - One E 2020-11-1 IDA / 63250 Forest and Protected Areas Post Limited 1,490.00 990.51 Signed 2020-10-21 2020-11-23 2020-11-09 2020-12-01 r's dormitory, DFO office gazi tions nvelope 9 Management pur sadar, beat office and Ful baria staff barrack. WD 91 / Digital survey for th Strengthening Collaborative e construction of Noakhali Sa Request for Quota Single Stage - One E 2020-11-1 IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 1,160.74 Signed 2020-10-21 2020-11-03 2020-11-09 2020-12-08 dar DFO residence & Hatia C tions nvelope 9 Management amp office (2 nos) and Hatia staff barrack Page 2 WD 92 / Digital survey for th Strengthening Collaborative e construction of Patuakhali c Request for Quota Single Stage - One E Pending Imp 2020-11-1 IDA / 63250 Forest and Protected Areas Post Limited 895.00 0.00 2020-10-21 2020-11-09 amp office, Sadar DFO buildi tions nvelope lementation 9 Management ng and Staff barrack. WD 93 / Digital survey for th Strengthening Collaborative e construction of Amtoli cam Request for Quota Single Stage - One E Pending Imp 2020-11-1 IDA / 63250 Forest and Protected Areas Post Limited 895.00 0.00 2020-10-21 2020-11-09 p office and Pathorghata cam tions nvelope lementation 9 Management p office and staff barrack. WD 94 / Digital survey for th Strengthening Collaborative Request for Quota Single Stage - One E 2020-11-1 e construction of Madhabpur IDA / 63250 Forest and Protected Areas Post Limited 895.00 716.59 Signed 2020-10-21 2020-11-11 2020-11-09 2020-11-18 tions nvelope 9 beat office, Chunarughat staf Management f barrack (2 nos). WD 47 (CIVIL) / Construction Strengthening Collaborative for the Banobhaban HQ verti Single Stage - One E 1,034,013.8 2022-04-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1,170,238.00 Signed 2021-01-25 2021-02-01 2021-02-08 2021-03-10 2021-03-07 2021-03-24 2021-03-31 2021-04-12 2021-05-05 cal Expansion (2 floors: Civil, nvelope 5 9 Management sanitary and Internal Electrifi cation) WD 2 / Construction of Beat Strengthening Collaborative office, staff barrack with eart Single Stage - One E 2022-04-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 212,517.00 209,558.39 Signed 2021-02-01 2021-06-03 2021-02-08 2021-03-01 2021-06-21 2021-03-22 2021-08-03 2021-04-05 2021-09-29 h work, boundary wall, appro nvelope 2 Management ach road, small culvert etc at Rangunia,Chattogram. WD 3 / Construction of Beat Strengthening Collaborative office with earth work, bound Single Stage - One E 2022-03-2 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 90,828.00 89,224.19 Signed 2021-02-01 2021-06-03 2021-02-08 2021-03-01 2021-06-21 2021-03-03 2021-07-18 2021-03-17 2021-09-27 ary wall, approach road, smal nvelope 4 Management l culvert etc at Rawjan, Chatt ogram. WD 4 / Construction of rang Strengthening Collaborative e office with earth work, bou Single Stage - One E Pending Imp 2022-04-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 149,323.00 0.00 2021-02-01 2021-02-08 2021-03-01 2021-03-22 2021-04-05 ndary wall, approach road, s nvelope lementation 2 Management mall culvert etc at Bashkhali, Chattogram. WD 6 / Construction of Staff Strengthening Collaborative barrack with earth work, bou Single Stage - One E 2022-04-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 128,811.00 117,032.58 Signed 2021-02-01 2021-06-02 2021-02-08 2021-03-01 2021-06-20 2021-03-22 2021-06-20 2021-04-05 2021-10-01 ndary wall, approach road, s nvelope 2 Management mall culvert etc at Satkania, Chattogram. WD 26 / Construction of staff Strengthening Collaborative barrack (2 nos) with Earth w Single Stage - One E 2022-04-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 240,476.00 153,860.26 Signed 2021-02-01 2021-03-09 2021-02-08 2021-03-01 2021-03-25 2021-03-22 2021-05-19 2021-04-05 2021-06-11 ork, boundary wall, approach nvelope 2 Management road, small culvert etc at Sha paher, Naogaon. WD 32 / Construction of Bea Strengthening Collaborative t office with Earth work, boun Single Stage - One E 2022-04-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 94,581.00 77,859.11 Signed 2021-02-01 2021-12-14 2021-02-08 2021-03-01 2021-12-27 2021-03-22 2022-01-19 2021-04-05 2022-03-04 dary wall, approach road, sm nvelope 2 Management all culvert etc at Thakurgaon Sadar. WD 7 / Construction of Rang Strengthening Collaborative e office, Beat office with eart Single Stage - One E 2022-04-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 228,788.00 228,217.31 Signed 2021-02-01 2021-05-11 2021-02-08 2021-03-01 2021-05-31 2021-03-22 2021-06-28 2021-04-05 2021-07-20 h work, boundary wall, appro nvelope 2 Management ach road, small culvert etc at Mirersorai, Chattogram. WD 8 / Construction of Sitak undu Staff barrack and Foujd Strengthening Collaborative Single Stage - One E 2022-04-1 arhat Staff barrack with eart IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 239,514.00 234,914.83 Signed 2021-02-01 2021-05-11 2021-02-08 2021-03-01 2021-05-31 2021-03-22 2021-06-24 2021-04-05 2021-07-27 nvelope 2 h work, boundary wall, appro Management ach road, small culvert etc at Sitakundu ,Chattogram. WD 30 / Construction of Ran ge office at Ghatail and Cam Strengthening Collaborative Single Stage - One E 2022-04-1 p office, Staff barrack at Sha IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 438,523.00 431,593.81 Signed 2021-02-01 2021-05-05 2021-02-08 2021-03-01 2021-06-03 2021-03-22 2021-07-11 2021-04-05 2021-08-24 nvelope 2 khipur with Earth work, boun Management dary wall, approach road, sm all culvert etc in Tangail National Procure WD 16 / Construction of Staf Strengthening Collaborative ment Document - f barrack with Earth work, bo Single Stage - One E 2022-10-2 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 129,894.00 107,800.66 Signed 2021-08-16 2021-09-26 2021-08-23 2021-09-13 2021-10-17 2021-10-04 2021-12-08 2021-10-18 2022-01-05 undary wall, approach road, nvelope 5 Management ss (Non Bank-SPD small culvert etc at Gazipur s ) adar. WD 17 / Construction of Ca National Procure mp office at Kapasia and Staf Strengthening Collaborative ment Document - Single Stage - One E 2022-10-2 f barrack at Sripur with Earth IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 217,397.00 187,528.47 Signed 2021-08-16 2021-11-01 2021-08-23 2021-09-13 2021-11-17 2021-10-04 2021-12-06 2021-10-18 2022-01-20 nvelope 5 work, boundary wall, approac Management ss (Non Bank-SPD h road, small culvert etc in G ) azipur. National Procure WD 24 / Construction of Ran Strengthening Collaborative ment Document - ge office with Earth work, bo Single Stage - One E 2022-10-2 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 144,335.00 116,492.07 Signed 2021-08-16 2021-08-31 2021-08-23 2021-09-13 2021-09-16 2021-10-04 2021-10-31 2021-10-18 2021-12-22 undary wall, approach road, nvelope 5 Management ss (Non Bank-SPD small culvert etc at Jhinaigati ) , Sherpur. National Procure WD 25 / Construction of Staf Strengthening Collaborative ment Document - f barrack with Earth work, bo Single Stage - One E 2022-10-2 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 123,605.00 99,158.96 Signed 2021-08-16 2021-08-31 2021-08-23 2021-09-13 2021-09-16 2021-10-04 2021-09-16 2021-10-18 2021-12-22 undary wall, approach road, nvelope 5 Management ss (Non Bank-SPD small culvert etc at Sribordi, ) Sherpur. WD 28 / Construction of Ca National Procure mp office and beat office wit Strengthening Collaborative ment Document - Single Stage - One E Under Imple 2022-10-2 h Earth work, boundary wall, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 179,069.00 0.00 2021-08-16 2022-09-19 2021-08-23 2021-09-13 2021-10-04 2021-10-18 nvelope mentation 5 approach road, small culvert Management ss (Non Bank-SPD etc. at Komolgonj, Mouloviba ) zar. National Procure WD 29 / Construction of Staf Strengthening Collaborative ment Document - f barrack with Earth work, bo Single Stage - One E Under Imple 2022-10-2 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 128,363.00 0.00 2021-08-16 2022-09-08 2021-08-23 2021-09-13 2022-09-26 2021-10-04 2022-09-26 2021-10-18 undary wall, approach road, nvelope mentation 5 Management ss (Non Bank-SPD small culvert etc. at Juri, Mou ) lovibazar. National Procure WD 35 / Construction of Staf Strengthening Collaborative ment Document - f barrack with Earth work, bo Single Stage - One E 2022-10-2 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 128,086.00 101,430.23 Signed 2021-08-16 2021-10-07 2021-08-23 2021-09-13 2021-10-20 2021-10-04 2021-11-15 2021-10-18 2022-01-13 undary wall, approach road, nvelope 5 Management ss (Non Bank-SPD small culvert etc. at Fulbaria, ) Mymensing. WD 9 / Construction of Beat National Procure cum Check Station & Staff ba Strengthening Collaborative ment Document - Single Stage - One E 2023-01-1 rrack with earth work, bound IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 237,976.00 0.00 Signed 2021-10-11 2022-06-05 2021-10-18 2021-11-08 2022-06-22 2021-11-29 2022-07-18 2022-01-03 2023-03-23 nvelope 0 ary wall, approach road, smal Management ss (Non Bank-SPD l culvert etc at Chokoria, Cox' ) s Bazar Page 3 National Procure WD 11 / Construction of Staf Strengthening Collaborative ment Document - f barrack, Beat office with ea Single Stage - One E 2023-01-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 209,048.00 0.00 Signed 2021-10-11 2022-02-03 2021-10-18 2021-11-08 2022-02-28 2021-11-29 2022-03-31 2022-01-03 2022-05-30 rth work, boundary wall, appr nvelope 0 Management ss (Non Bank-SPD oach road, small culvert etc ) at Ramu, Cox's Bazar. National Procure WD 12 / Construction of Staf Strengthening Collaborative ment Document - f barrack, Beat office with ea Single Stage - One E 2023-01-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 220,952.00 0.00 Signed 2021-10-11 2022-02-03 2021-10-18 2021-11-08 2022-02-28 2021-11-29 2022-03-31 2022-01-03 2022-05-30 rth work, boundary wall, appr nvelope 0 Management ss (Non Bank-SPD oach road, small culvert etc ) at Ukhia, Cox's Bazar. National Procure WD 13 / Construction of bea Strengthening Collaborative ment Document - t Office with earth work, bou 2023-01-1 IDA / 63250 Forest and Protected Areas Post Request for Bids 1 Envelope proce 98,500.00 0.00 Signed 2021-10-11 2022-01-17 2021-10-18 2021-11-08 2022-05-22 2021-11-29 2022-05-29 2022-01-03 2022-06-03 ndary wall, approach road, s 0 Management ss (Non Bank-SPD mall culvert etc at Teknaf, Co ) x's Bazar. National Procure WD 19 / Construction of Offi Strengthening Collaborative ment Document - cer's dormitory, staff barrack Single Stage - One E Under Imple 2023-01-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 288,298.00 0.00 2021-10-11 2022-08-24 2021-10-18 2021-11-08 2022-09-15 2021-11-29 2022-10-17 2022-01-03 with Earth work, boundary w nvelope mentation 0 Management ss (Non Bank-SPD all, approach road, small culv ) ert etc at Barishal National Procure WD 31 / Construction of Staf Strengthening Collaborative ment Document - f barrack with Earth work, bo Single Stage - One E 2023-01-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 134,536.00 0.00 Signed 2021-10-11 2022-02-07 2021-10-18 2021-11-08 2022-02-22 2021-11-29 2022-02-28 2022-01-03 2022-05-20 undary wall, approach road, nvelope 0 Management ss (Non Bank-SPD small culvert etc at Modhup ) ur, Tangail. National Procure WD 42 / Construction of Bea Strengthening Collaborative ment Document - t office with Earth work, boun Single Stage - One E Pending Imp 2023-01-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 103,214.00 0.00 2021-10-11 2021-10-18 2021-11-08 2021-11-29 2022-01-03 dary wall, approach road, sm nvelope lementation 0 Management ss (Non Bank-SPD all culvert etc at Madhabpur, ) Hobigonj. National Procure WD 44 / Construction of Bea Strengthening Collaborative ment Document - t office with Earth work, boun Single Stage - One E 2023-01-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 96,012.00 85,354.17 Signed 2021-10-11 2021-12-13 2021-10-18 2021-11-08 2021-12-28 2021-11-29 2022-03-21 2022-01-03 2022-04-27 dary wall, approach road, sm nvelope 0 Management ss (Non Bank-SPD all culvert etc at Chatak, Sun ) amganj WD 45 / Construction of CCF' National Procure s Banglow including Civil Wor Strengthening Collaborative ment Document - Single Stage - One E 2023-01-1 ks, ESMP, Internal Sanitary a IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 229,595.00 187,394.15 Signed 2021-10-11 2021-11-09 2021-10-18 2021-11-08 2021-11-21 2021-11-29 2021-12-05 2022-01-03 2022-01-13 nvelope 0 nd Water Supply and Internal Management ss (Non Bank-SPD Electrification work at Mirpur, ) Dhaka National Procure WD 37 / Construction of DFO Strengthening Collaborative ment Document - residence with Earth work, b Single Stage - One E 2023-01-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 185,571.00 146,018.39 Signed 2021-10-11 2021-11-03 2021-10-18 2021-11-08 2021-11-28 2021-11-29 2021-12-22 2022-01-03 2022-02-21 oundary wall, approach road, nvelope 0 Management ss (Non Bank-SPD small culvert etc at Noakhali ) sadar. WD 60 / Sub soil investigatio n for the construction of DFO Strengthening Collaborative Request for Quota Single Stage - One E 2020-12-0 office building and Staff Barr IDA / 63250 Forest and Protected Areas Post Limited 5,955.00 0.00 Canceled 2020-10-21 2020-11-09 tions nvelope 9 ack (2 nos) at Dinajpur Sadar Management and beat office at Nawabganj . WD 84 / Digital survey for th Strengthening Collaborative e construction of DFO office Request for Quota Single Stage - One E 2020-11-1 IDA / 63250 Forest and Protected Areas Post Limited 1,192.00 0.00 Canceled 2020-10-21 2020-11-09 building and Staff Barrack (2 tions nvelope 9 Management nos) at Dinajpur Sadar and b eat office at Nawabganj. WD 34 / Construction of Sta National Procure ff barrack, beat office with Ea Strengthening Collaborative ment Document - Single Stage - One E 2022-10-2 rth work, boundary wall, appr IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 209,790.00 0.00 Canceled 2021-08-16 2021-08-23 2021-09-13 2021-10-04 2021-10-18 nvelope 5 oach road, small culvert etc. Management ss (Non Bank-SPD at Muktagacha, Mymensing . ) WD 108 / Digital Survey for t Strengthening Collaborative Request for Quota he construction of office bldg Request for Quota Single Stage - One E Pending Imp 2022-02-0 IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 1,191.00 0.00 2021-12-15 2022-01-02 , greenhouse, staff dormitory tions nvelope lementation 1 Management PD) , nursery shed with seed stor age at Patiya SFNTC WD 76 / Sub soil investigatio Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E 2020-11-2 n for the construction of Cha IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 1,490.00 0.00 Canceled 2020-10-21 2020-11-09 tions nvelope 9 ttogram Town-Agrabad Staff Management PD) Quarter. WD 1 / Construction of office building of officer-in-charge, staff dormitory, nursery shed Strengthening Collaborative Single Stage - One E 2022-04-1 with seed storage and green IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 382,535.00 0.00 Canceled 2021-02-01 2021-02-08 2021-03-01 2021-03-22 2021-04-05 nvelope 2 house with earth work, boun Management dary wall, approach road, sm all culvert etc at Olinagar, Ha thazari, Chattogram. WD-84 / Digital Survey for th e construction of DFO office Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E 2022-02-1 building and one Staff Barrac IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 1,190.00 0.00 Signed 2021-12-30 2022-02-16 2022-01-17 2023-03-08 tions nvelope 6 k at Dinajpur Sadar and beat Management PD) office and one Staff Barrack at Birampur, Dinajpur WD 110 / Digital Survey for t he construction of Staff Barra Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-02-1 ck at Mymensingh Sadar, Be IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 893.00 0.00 2021-12-30 2022-01-17 tions nvelope lementation 6 at Office at Bhaluka and Ran Management PD) ge Office at Muktagacha, My mensingh WD-34 / Construction of Ra National Procure nge Office with Earth work, b Strengthening Collaborative ment Document - Single Stage - One E Under Imple 2023-05-0 oundary wall, approach road, IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 150,393.00 0.00 2022-02-20 2022-11-13 2022-02-27 2022-03-20 2022-11-28 2022-04-10 2023-01-17 2022-04-24 nvelope mentation 1 small culvert etc. at Rasulpur Management ss (Non Bank-SPD , Muktagacha, Mymensing ) WD 101 / Sub soil investigati Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-02-1 on for the construction of ra IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 1,488.00 0.00 2021-12-30 2022-01-17 tions nvelope lementation 6 nge office at Rangunia, Chatt Management PD) ogram WD 111 / Subsoil investigati Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-02-1 on for the construction of Sta IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 1,488.00 0.00 2021-12-30 2022-01-17 tions nvelope lementation 6 ff Barrack at Hathazari, Chatt Management PD) ogram WD-76 / Sub soil investigatio Strengthening Collaborative Request for Quota n for the construction of Sta Request for Quota Single Stage - One E Pending Imp 2022-02-1 IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 1,488.00 0.00 2021-12-30 2022-01-17 ff Quarter at Chattogram For tions nvelope lementation 6 Management PD) est Academy, Solosohor, Cha ttogram Page 4 WD-60 / Subsoil investigatio n for the construction of DFO Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E 2022-02-1 office building, one Staff Barr IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 5,952.00 0.00 Signed 2021-12-30 2022-01-18 2022-01-17 2022-02-15 tions nvelope 6 ack at Dinajpur Sadar and be Management PD) at office, one Staff Barrack at Birampur, Dinajpur WD 102 / Sub soil investigati Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-02-1 on for the construction of Be IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 1,488.00 0.00 2021-12-30 2022-01-17 tions nvelope lementation 6 at Office at Sapaher, Naogao Management PD) n National Procure WD 4A / Construction of ran Strengthening Collaborative ment Document - ge office with earth work, bo Single Stage - One E Under Imple 2023-05-0 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 150,393.00 0.00 2022-02-20 2023-03-23 2022-02-28 2022-03-21 2022-04-11 2022-04-25 undary wall, approach road, nvelope mentation 2 Management ss (Non Bank-SPD small culvert etc at Rangunia ) , Chattogram. National Procure WD 26-A / Construction of B Strengthening Collaborative ment Document - eat office with earth work, bo Single Stage - One E 2023-05-0 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 93,524.00 0.00 Signed 2022-02-20 2022-09-22 2022-02-27 2022-03-20 2022-10-19 2022-04-10 2022-11-03 2022-04-24 2023-02-06 undary wall, approach road, nvelope 1 Management ss (Non Bank-SPD small culvert etc at Shrionti, ) Shapaher, Naogaon WD 105 / Sub soil investigati on for the construction of Sta Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-02-1 ff Barrack at Mymensingh Sa IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 4,464.00 0.00 2021-12-30 2022-01-17 tions nvelope lementation 6 dar, Beat Office at Bhaluka a Management PD) nd Range Office at Muktagac ha, Mymensingh WD 103 / Subsoil investigati on for the construction of offi Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-02-1 ce bldg, greenhouse, staff do IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 5,952.00 0.00 2021-12-30 2022-01-17 tions nvelope lementation 6 rmitory, nursery shed with se Management PD) ed storage at Patiya SFNTC WD 10 / Construction of Staf f Barrack at Cox'sBazar Sada National Procure r Forest Colony, Range office Strengthening Collaborative ment Document - Single Stage - One E 2023-03-2 at PM Khali Range, Cox'sBaza IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 352,155.00 0.00 Signed 2022-01-05 2022-06-05 2022-01-12 2022-02-02 2022-06-27 2022-02-23 2022-07-07 2022-03-17 2022-08-18 nvelope 4 r Sadar and Beat office at Ko Management ss (Non Bank-SPD sturaghat, Cox'sbazar with e ) arthwork, boundary wall, app roach road, small culvert etc. WD 14 / Construction of Offi ce Building of Officer-in-Char National Procure ge, staff dormitory, nursery s Strengthening Collaborative ment Document - Single Stage - One E Under Imple 2023-04-1 hed cum seed storage and gr IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 383,750.00 0.00 2022-01-24 2022-04-28 2022-01-31 2022-02-21 2022-05-22 2022-03-14 2022-06-15 2022-04-05 nvelope mentation 2 eenhouse Earthwork and con Management ss (Non Bank-SPD struction of boundary wall, a ) pproach road, small culvert, etc at Gazipur National Procure WD 23 / Construction of Ran Strengthening Collaborative ment Document - ge office with Earth work, bo Single Stage - One E 2023-04-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 145,595.00 0.00 Signed 2022-01-24 2022-06-22 2022-02-01 2022-02-22 2022-07-06 2022-03-15 2022-07-20 2022-04-06 2022-08-28 undary wall, approach road, nvelope 3 Management ss (Non Bank-SPD small culvert etc at Debigonj, ) Panchagar National Procure WD 47-E/M / Vertical extensi Strengthening Collaborative ment Document - on of lifts (4 nos.) (Electrical Single Stage - One E 2023-04-0 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 101,785.00 0.00 Signed 2022-01-17 2022-02-13 2022-01-24 2022-02-14 2022-02-28 2022-03-07 2022-03-07 2022-03-29 2022-04-22 works) in BanoBhaban Head nvelope 5 Management ss (Non Bank-SPD Quarter at Agargaon, Dhaka ) WD 73 (R) / Sub soil investig Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-03-2 ation for the construction of IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 2,976.00 0.00 2022-02-03 2022-02-21 tions nvelope lementation 3 Chunarughat staff barrack (2 Management PD) nos). National Procure WD 5 / Construction of Staff Strengthening Collaborative ment Document - Barrack with earthwork, appr Single Stage - One E Pending Imp 2023-06-2 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 148,786.00 0.00 2022-04-18 2022-04-25 2022-05-16 2022-06-06 2022-06-20 oach road, culvert and exter nvelope lementation 0 Management ss (Non Bank-SPD nal water supply etc at Hatha ) zari, Chattogram WD 18 / Construction of 2 st oried office Bldg, Staff Dorm, National Procure DFO Offc, DFO Residence, 2 s Strengthening Collaborative ment Document - toried Staff Barrack, Nursery Single Stage - One E Under Imple 2023-06-2 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 1,537,262.00 0.00 2022-04-18 2022-06-30 2022-04-25 2022-05-23 2022-08-01 2022-06-13 2022-06-27 Shed & Green House includin nvelope mentation 7 Management ss (Non Bank-SPD g E/W, approach road, drain, ) deep tube well, pump house & external electrification, Sol ar Panel etc. at Jessore Sadar WD 20 / Construction of 2 st oried DFO office and staff bar National Procure rack at Dinajpur Sadar, 1 stor Strengthening Collaborative ment Document - Single Stage - One E 2023-06-2 ied beat office and 2 storied IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 880,952.00 0.00 Signed 2022-04-18 2022-08-11 2022-04-25 2022-05-23 2022-09-11 2022-06-13 2022-09-15 2022-06-27 2022-12-06 nvelope 7 staff barrack at Birampur incl Management ss (Non Bank-SPD uding Earth Work, Approach ) Road, External Electrification and External Water Supply WD 21 / Construction of One National Procure range office and One Staff Ba Strengthening Collaborative ment Document - rrack at Charkukrimukri, Bhol Single Stage - One E 2023-06-0 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 409,905.00 0.00 Signed 2022-04-04 2022-07-05 2022-04-11 2022-05-05 2022-07-21 2022-05-26 2022-12-05 2022-06-09 2023-01-15 a, One beat office at Bethua, nvelope 9 Management ss (Non Bank-SPD Charfasion, Bhola including E ) arth Work and Approach Roa d and Culvert etc. WD 22 / Construction of One Range office at Doulatkhan, National Procure Bhola, One Camp office at M Strengthening Collaborative ment Document - Single Stage - One E 2023-06-0 onpura, Bhola, and One Cam IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 425,190.00 0.00 Signed 2022-04-04 2022-05-31 2022-04-11 2022-05-05 2022-06-30 2022-05-26 2022-07-20 2022-06-09 2022-09-01 nvelope 9 p office at Tajimuddin, Bhola Management ss (Non Bank-SPD including Earth Work, Approa ) ch Road and External Water Supply etc. WD 33 / Construction of One 1 storied officer's dormitory, National Procure One 2 storied DFO office, and Strengthening Collaborative ment Document - Single Stage - One E 2023-06-2 One 2 storied Staff Barrack a IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 595,810.00 0.00 Signed 2022-04-18 2022-06-28 2022-04-25 2022-05-23 2022-07-20 2022-06-13 2022-08-25 2022-06-27 2022-10-08 nvelope 7 t Mymensingh Sadar includin Management ss (Non Bank-SPD g Earth Work, Approach Road ) & Culvert, External Electrifica tion and External Water Supp ly etc. WD 34A / Construction of 1 National Procure Storied Beat office at Bhaluk Strengthening Collaborative ment Document - Single Stage - One E Under Imple 2023-06-2 a, Mymensingh including Eart IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 120,905.00 0.00 2022-04-18 2022-06-28 2022-04-25 2022-05-16 2022-07-20 2022-06-06 2022-08-29 2022-06-20 nvelope mentation 0 h Work, Approach Road & Cul Management ss (Non Bank-SPD vert, External Electrification ) and External Water Supply et c. Page 5 WD 36 / Construction of One National Procure Beat Office at Lakshmipur Sa Strengthening Collaborative ment Document - Single Stage - One E 2023-06-0 dar including Earth Work, Ap IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 159,500.00 0.00 Signed 2022-04-04 2022-08-28 2022-04-11 2022-05-05 2022-09-14 2022-05-26 2022-10-13 2022-06-09 2023-01-15 nvelope 9 proach Road, External Electri Management ss (Non Bank-SPD fication and External Water S ) upply etc. WD 38 / Construction of Ca National Procure mp Office (2 Nos) and One St Strengthening Collaborative ment Document - aff Barrack at Hatiya, Noakha Single Stage - One E 2023-06-0 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 535,857.00 0.00 Signed 2022-04-04 2022-09-19 2022-04-11 2022-05-05 2022-10-11 2022-05-26 2022-10-26 2022-06-09 2023-01-03 li including Earth Work, Appr nvelope 9 Management ss (Non Bank-SPD oach Road, External Electrific ) ation and External Water Sup ply etc. WD 39 / Construction of One National Procure DFO office at Patukhali Sadar Strengthening Collaborative ment Document - Single Stage - One E Pending Imp 2023-06-1 , One Camp Office at Kolapar IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 632,774.00 0.00 2022-04-04 2022-04-11 2022-05-09 2022-05-30 2022-06-13 nvelope lementation 3 a, Mohipur, and One Staff Bar Management ss (Non Bank-SPD rack at Rangabali including E ) arth Work, Approach Road et c. National Procure WD 40 / Construction of One Strengthening Collaborative ment Document - Camp Office at Amtoli, Borgu Single Stage - One E Under Imple 2023-06-0 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 157,595.00 0.00 2022-04-04 2022-06-26 2022-04-11 2022-05-05 2022-05-26 2022-06-09 na including Earth Work and nvelope mentation 9 Management ss (Non Bank-SPD Approach Road etc. ) WD 41 / Construction of One National Procure Camp Office and One Staff B Strengthening Collaborative ment Document - Single Stage - One E 2023-06-0 arrack at Pathorghata, Borgu IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 380,952.00 0.00 Canceled 2022-04-04 2022-10-17 2022-04-11 2022-05-05 2022-11-02 2022-05-26 2022-10-17 2022-06-09 nvelope 9 na Including Earth Work, App Management ss (Non Bank-SPD roach Road, Culvert, etc. ) WD 43 / Construction of 2 St oried Staff Barrack at Shaltila National Procure , Chunarughat, and 2 Storied Strengthening Collaborative ment Document - Single Stage - One E Pending Imp 2023-06-2 Staff Barrack at Chunarughat IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 307,833.00 0.00 2022-04-18 2022-04-25 2022-05-16 2022-06-06 2022-06-20 nvelope lementation 0 SFNTC under Hobiganj Distric Management ss (Non Bank-SPD t including Earth Work, Appro ) ach Road, External Electrifica tion and External Water Supp ly etc. WD 116 / Subsoil investigati Strengthening Collaborative Request for Quota on for the construction of On Request for Quota Single Stage - One E Pending Imp 2022-05-2 IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 1,488.00 0.00 2022-04-07 2022-04-25 e Small Jetty with RCC Pillar a tions nvelope lementation 5 Management PD) t Char Kukri-Mukri, Bhola WD 118 / Subsoil investigati Strengthening Collaborative Request for Quota on for the construction of wil Request for Quota Single Stage - One E Pending Imp 2022-05-2 IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 1,488.00 0.00 2022-04-07 2022-04-25 dlife rescue center at Singra, tions nvelope lementation 5 Management PD) Thakurgaon, Dinajpur WD117 / Subsoil investigatio n for the construction of Natu Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-05-2 re Interpretation Center and IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 2,976.00 0.00 2022-04-07 2022-04-25 tions nvelope lementation 5 Deer Enclosure at Somoschur Management PD) a, Modhutila, Mymensingh WD119 / Subsoil investigatio Strengthening Collaborative Request for Quota n for the construction of Culv Request for Quota Single Stage - One E Pending Imp 2022-05-2 IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 2,976.00 0.00 2022-04-07 2022-04-25 ert and Corridor Over Road a tions nvelope lementation 5 Management PD) t Lawachara, Moulavibazar WD123 / Digital Survey for t he construction of Public Toil et, Gate & Ticket Counter, CC Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-05-2 Walking Trail, RCC Gol Ghar, IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 1,190.00 0.00 2022-04-07 2022-04-25 tions nvelope lementation 5 Signage, Guard Post, Bounda Management PD) ry Wall, and Wildlife Rescue Center at Birganj, Nababganj , and Singra, Thakurgaon, Di najpur WD-50/1 / Pond Excavation National Procure at Monupura, Bhola and Pond Strengthening Collaborative ment Document - Excavation, Construction of o Single Stage - One E Pending Imp 2023-10-1 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 186,905.00 0.00 2022-08-01 2022-08-08 2022-08-29 2022-09-19 2022-10-10 ne Small Jetty with RCC Pillar nvelope lementation 0 Management ss (Non Bank-SPD , one Foot Trail, one Pond Gh ) at along with Tube well instal lation at Charkukri Mukri, Bh ola WD 104 / Sub soil investigati Strengthening Collaborative Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-10-2 on for the construction of Ra IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 1,488.00 0.00 2022-09-08 2022-09-26 tions nvelope lementation 6 nge office at Sayestagonj, Ha Management PD) biganj, Sylhet WD 15 / Construction of one National Procure range office and one staff ba Strengthening Collaborative ment Document - rrack at Kachighata and one Single Stage - One E Pending Imp 2024-01-2 IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 410,071.43 0.00 2023-05-07 2023-05-14 2023-06-04 2023-06-25 2023-07-30 beat office at kasempur in Ka nvelope lementation 6 Management ss (Non Bank-SPD liakoir, Gazipur including eart ) hwork, boundary wall, appro ach road, small culvert, etc. WD47-V/E / Construction for National Procure the Banobhaban HQ vertical Strengthening Institutions, I ment Document - Single Stage - One E Pending Imp 2024-02-0 Expansion 9th floor including IDA / 63250 nformation Systems and Trai Post Request for Bids Open - National 1 Envelope proce 1,152,440.48 0.00 2023-05-07 2023-05-14 2023-06-11 2023-07-09 2023-08-13 nvelope lementation 9 Civil, Sanitary, Internal Electr ning ss (Non Bank-SPD ification, Electrical & Mechani ) cal Works WD 49 / Remaining works of National Procure CCF's Bunglow including eart Strengthening Collaborative ment Document - Single Stage - One E Pending Imp 2024-04-2 h filling, landscaping, approa IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 175,226.19 0.00 2023-05-07 2023-05-14 2023-06-04 2023-06-25 2023-07-30 nvelope lementation 5 ch roads, underground water Management ss (Non Bank-SPD reservoir, external electrifica ) tion National Procure WD 49-A / Other repair and Project Management, Monito Single Stage - One E ment Document - Pending Imp 2023-09-1 Maintenance (Planning Com IDA / 63250 Post Request for Bids Open - National 23,809.52 0.00 2023-04-24 2023-05-01 2023-05-15 2023-05-29 2023-06-19 ring and Reporting nvelope 1 Envelope proce lementation 7 mission) ss (Non Bank-SPD ) WD-41 / Construction of One National Procure Camp Office and One Staff B Strengthening Collaborative ment Document - Single Stage - One E 2024-06-1 arrack at Pathorghata, Borgu IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 506,464.29 0.00 Signed 2023-04-10 2022-10-17 2023-04-17 2023-05-15 2022-11-02 2023-06-05 2022-12-01 2023-06-19 2023-02-25 nvelope 8 na Including Earth Work, App Management ss (Non Bank-SPD roach Road, Culvert, etc. ) National Procure WD-46 / Renovation Works o Strengthening Collaborative ment Document - Single Stage - One E Pending Imp 2024-06-1 f Mohakhali Ban Bhaban (Civi IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 785,714.00 0.00 2023-08-22 2023-08-29 2023-09-26 2023-10-17 2023-11-21 nvelope lementation 8 l and Internal Electrification Management ss (Non Bank-SPD Works) ) Page 6 WD-1 / Construction of office building of officer-in-charge, National Procure staff dormitory, nursery shed Strengthening Collaborative ment Document - Single Stage - One E Pending Imp 2023-05-0 with seed storage and green IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 487,500.00 0.00 2022-02-20 2022-02-27 2022-03-20 2022-04-10 2022-04-24 nvelope lementation 1 house with earthwork, bound Management ss (Non Bank-SPD ary wall, approach road, smal ) l culvert etc at Patiya, Chatto gram. WD-46.1 / Renovation works of Mohakhali Ban Bhaban, Dh National Procure aka. (External Electrification Strengthening Collaborative ment Document - Single Stage - One E Pending Imp 2023-12-0 Works with Supply and Install IDA / 63250 Forest and Protected Areas Post Request for Bids Open - National 1 Envelope proce 285,715.00 0.00 2023-08-22 2023-08-29 2023-09-19 2023-10-10 2023-11-14 nvelope lementation 5 ation of Sub-Station Equipme Management ss (Non Bank-SPD nt, Generator, Lift, Solar & ) Related Works.) WD-61-R / Subsoil investigati Strengthening Collaborative Request for Quota on for the construction of be Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 63250 Forest and Protected Areas Post Limited tions (Non Bank-S 2,381.00 0.00 2023-08-25 2023-09-16 at office at Gosher Hat Beat, tions nvelope lementation 9 Management PD) Charfashion, Bhola GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7