PROCUREMENT PLAN TEXTUAL PART Project information Country : Turkey Project Name : Turkey Resilient Landscape Integration Project (TULIP) Project Number : P172562 Project Implementation Agency: Directorate General of Forestry (OGM), General Directorate of Agricultural Reform (TRGM), State Hydraulic Works (DSI), General Directorate of Highways (KGM) Date of the Procurement Plan: May 03, 2021 Period covered by this Procurement Plan: From July 2021 to December 2022 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. Any procurement activity under the Project shall not be initiated before it is approved by the Bank through STEP. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Goods, Works and Non-consulting Services Procurement Procurement Method Prior Review Threshold Method Threshold RFB Default Method for Good, Works Contract valued > USD (International and Non-consulting Services (No 10M Works and > USD 2M Open selection method threshold) for Goods and Non- Competition) Consulting Services 1 RFB (National Contracts valued < USD 30M for Contracts valued > USD Open Works and < USD 2M for Goods 10M for Works and > USD Competition) and Non-Consulting Services 2M for Goods and Non- Consulting Services RFQ Works Contracts valued < No prior review USD200,000 – Goods and Non- consulting Services Contracts valued < USD100,000 Works III. Selection of Consultants Selection Method Selection Method Prior Review Threshold Threshold Quality and Cost Default Method (No Contract valued ≥ USD Based Selection selection method 1M (QCBS) threshold) Selection Based on Contracts valued < No prior review Consultants USD300,000 Qualification (CQS) Least Cost Selection No selection Method Contract valued ≥ USD (LCS) threshold 1M Direct Selection (DIR) No selection method Contract valued ≥ USD threshold 1M Justification is required at the PP approval Individual Consultants No selection method Contracts valued ≥ (INDV) threshold USD300,000 The terms of references of any audit, procurement or legal consultants financed by the project shall be sent to the Bank for its comments. IV. Special Arrangements 1.The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. For the procurements not subject to international competitive selection, Turkish translation of the Bank’s Standard Procurement Documents (SPD) with minor modifications will be used as to fit for purpose or the procurement documents agreed by the Bank shall be used. 2.Review Procedure: The procurements under the project are subject to the Bank’s prior review as stipulated in above Paragraphs II and III and also as specified in the procurement schedule given below in Section V, and in STEP. 3.Procurement of Second Hand Goods: Not Applicable 2 4.Domestic preference (as specified under paragraph 5.51 of the Procurement Regulations): Not applicable 5.Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable 6. Other Relevant Procurement Information - NA 7. Procurement Packages with Methods and Time Schedule The estimated costs given in the attached tables include VAT. 3 PROCUREMENT Turkiye : Turkey Resilient Landscape Integration Project (TULIP) PLAN General Information Country: Turkiye 2022-02-11 Bank’s Approval Date of the Original Procurement Plan: 2023-08-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172562 GPN Date: 2021-12-09 Project Name: Turkey Resilient Landscape Integration Project (TULIP) Loan / Credit No: IBRD / 92720 Cekerek Regional Support Team Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - TR-CEKEREK RST-299282-C Component 1: Investments i Single Stage - One E Small Works SPD 2022-12-3 W-RFB / Construction of Ceke IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 800,000.00 875,174.44 Signed 2022-06-27 2022-07-20 2022-06-28 2022-07-28 2022-08-22 2022-07-30 2022-08-22 2022-08-10 2022-09-19 nvelope (1 envelope proce 1 rek Recreation Area ation in targeted areas ss) TR-CEKEREK RST-307656-C Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2022-12-3 W-RFQ / Sivas Forest Nursery IBRD / 92720 n Resilient Landscape Integr Post Open - National 59,000.00 0.00 Canceled 2022-09-11 2022-09-30 tions nvelope or explanation) 1 Directorate Road Constructio ation in targeted areas n Work TR-CEKEREK RST-307971-C W-RFQ / Sivas Forest Manage Component 1: Investments i ment Directorate Animal Can Request for Quota Single Stage - One E Other (with field f 2022-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 7,000.00 0.00 Canceled 2022-09-11 2022-09-30 opy Construction Work tions nvelope or explanation) 1 ation in targeted areas (Sivas Province Yıldızeli Distr ict Subasi Village) TR-CEKEREK RST-311277-C W-RFQ / Kayseri Forest Regio nal Directorate Yozgat Forest Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2022-12-3 Management Directorate Con IBRD / 92720 n Resilient Landscape Integr Post Open - National 18,000.00 0.00 Canceled 2022-08-31 2022-09-27 tions nvelope or explanation) 1 struction of scratching post, ation in targeted areas plaster and salt shaker for an imals within the scope of pas ture improvement. TR-CEKEREK RST-307969-C W-RFQ / Service Road Constr uction, Planting Services, Lan d Preparation Works (Sivas, Y Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2022-12-3 ıldızeli District Sarıcal Village IBRD / 92720 n Resilient Landscape Integr Post Open - National 22,500.00 0.00 Canceled 2022-09-11 2022-09-30 tions nvelope or explanation) 1 Eğrek Locality) ation in targeted areas (Although it has similar busin ess status with 307963-CW-R FQ, its field location and loca tions are very different regio ns.) TR-CEKEREK RST-307963-C W-RFQ / Service Road Constr uction, Planting Services, Lan d Preparation Works,(Sivas, Y Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2022-12-3 ıldızeli District Üyükyaylası Vi IBRD / 92720 n Resilient Landscape Integr Post Open - National 101,000.00 0.00 Canceled 2022-09-11 2022-09-30 tions nvelope or explanation) 1 llage Karababa Locality) ation in targeted areas (Although it has similar busin ess status to 307969-CW-RF Q, its field location and locati ons are very different region s.) TR-CEKEREK RST-315304-C W-RFQ / Sapling Planting Ser Component 1: Investments i vices, Land Preparation servi Request for Quota Single Stage - One E Other (with field f 2022-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 80,000.00 0.00 Canceled 2022-09-21 2022-11-01 ce procurement business (Siv tions nvelope or explanation) 1 ation in targeted areas as Yıldızeli District Üyükyayla sı Village Karababa Locality) TR-CEKEREK RST-315305-C W-RFQ / Sapling Planting Ser Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2022-12-3 vices, Land Preparation servi IBRD / 92720 n Resilient Landscape Integr Post Open - National 22,500.00 0.00 Canceled 2022-09-21 2022-11-01 tions nvelope or explanation) 1 ce procurement business (Siv ation in targeted areas as Yıldızeli District Sarıcal Vill age Eğrek Locality) TR-CEKEREK RST-351012-C Component 1: Investments i W-RFQ / Recreation Construc Request for Quota Single Stage - One E Other (with field f 2023-09-2 IBRD / 92720 n Resilient Landscape Integr Post Open - National 72,000.00 0.00 Canceled 2023-03-31 2023-05-26 tion Area (Wooden railing, Pa tions nvelope or explanation) 3 ation in targeted areas nel fence, Manhole and Sign Construction work.) TR-CEKEREK RST-354418-C W-RFQ / Amasya OBM Corum Forest Management Director Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2023-08-2 ate. Construction works withi IBRD / 92720 n Resilient Landscape Integr Post Open - National 116,000.00 0.00 Canceled 2023-04-15 2023-05-26 tions nvelope or explanation) 4 n the scope of afforestation a ation in targeted areas nd soil conservation works.(S oil tillage, sapling planting, b arbed wire construction work s.) TR-CEKEREK RST-362170-C Request for Bids - W-RFB / Recreation Construct Component 1: Investments i Single Stage - One E Small Works SPD 2023-12-3 ion Area. (Country Coffee, W IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 304,000.00 0.00 Signed 2023-05-26 2023-06-09 2023-05-31 2023-07-12 2023-07-25 2023-07-17 2023-07-26 2023-08-01 2023-08-06 nvelope (1 envelope proce 1 ooden Railing, Panel Fence, ation in targeted areas ss) Manhole Construction work.) TR-CEKEREK RST-362381-C W-RFQ / Kayseri OBM Sivas F orest Management Directorat e. Construction works within Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2023-12-3 the scope of afforestation an IBRD / 92720 n Resilient Landscape Integr Post Open - National 152,000.00 0.00 Signed 2023-06-25 2023-07-14 tions nvelope or explanation) 1 d soil conservation works. (S ation in targeted areas oil tillage, sapling planting, b arbed wire construction work s.) (Sivas Province Yildizeli Di strict Üyükyaylasi Village.) TR-CEKEREK RST-362383-C W-RFQ / Kayseri OBM Sivas F orest Management Directorat Component 1: Investments i Request for Quota Single Stage - One E Other (with field f 2023-12-3 e (Construction works within IBRD / 92720 n Resilient Landscape Integr Post Open - National 90,000.00 0.00 Signed 2023-06-25 2023-07-14 tions nvelope or explanation) 1 the scope of afforestation an ation in targeted areas d rehabilitation works.) (Sivas Province Yildizeli Distri ct Sarıcal village location.) TR-CEKEREK RST-307971-C Component 1: Investments i W-RFQ-2 / Kayseri OBM Sivas Request for Quota Single Stage - One E Other (with field f 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 11,000.00 0.00 Canceled 2023-06-25 2023-07-14 Forest Management Director tions nvelope or explanation) 1 ation in targeted areas ate, Animal Canopy Construc tion Work. Page 1 TR-CEKEREK RST-362505-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 10,000.00 0.00 Canceled 2023-06-25 2023-07-14 ate. (Construction works with tions nvelope or explanation) 1 ation in targeted areas in the scope of afforestation and pasture improvement wo rks.) TR-CEKEREK RST-362508-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 30,000.00 0.00 2023-06-25 2023-07-14 ate. (Construction works with tions nvelope or explanation) mentation 1 ation in targeted areas in the scope of afforestation) (Tokat Province Artova Distri ct Bebekderesi Village Locati on.) TR-CEKEREK RST-362514-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 51,000.00 0.00 2023-06-25 2023-07-14 ate. (Construction works with tions nvelope or explanation) mentation 1 ation in targeted areas in the scope of afforestation) (Tokat Province Yesilyurt Dist rict Sivri Village Location.) TR-CEKEREK RST-362515-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 55,000.00 0.00 2023-06-25 2023-07-14 ate.(Construction works withi tions nvelope or explanation) mentation 1 ation in targeted areas n the scope of afforestation) (Tokat Province, Yesilyurt Dis trict, Ekinli Village Location.) TR-CEKEREK RST-362517-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 62,000.00 0.00 2023-06-25 2023-07-14 ate.(Construction works withi tions nvelope or explanation) mentation 1 ation in targeted areas n the scope of afforestation) (Tokat Province, Artova Distri ct, Devecikargın Village Loca tion.) TR-CEKEREK RST-376109-C Component 1: Investments i W-RFQ / Kayseri OBM Sivas F Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Limited 27,000.00 0.00 2023-08-19 2023-09-29 orest Management Directorat tions nvelope or explanation) lementation 1 ation in targeted areas e, Animal Canopy Constructio n Work. TR-CEKEREK RST-376587-C W-RFQ / Amasya OBM Tokat Component 1: Investments i Forest Management Director Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Open - National 12,000.00 0.00 2023-08-22 2023-10-02 ate. (Construction works with tions nvelope or explanation) mentation 1 ation in targeted areas in the scope of afforestation and pasture improvement wo rks.) TR-CEKEREK RST-376591-C W-RFQ / Amasya OBM Corum Forest Management Director Component 1: Investments i Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 ate. Construction works withi IBRD / 92720 n Resilient Landscape Integr Post Open - National 86,000.00 0.00 2023-08-22 2023-10-02 tions nvelope or explanation) mentation 1 n the scope of afforestation a ation in targeted areas nd soil conservation works.(S oil tillage, sapling planting, b arbed wire construction work s.) TR-CEKEREK RST-377771-C W-RFB / Kayseri OBM Akdağ Request for Bids - Component 1: Investments i madeni Directorate of Forestr Single Stage - One E Small Works SPD Pending Imp 2023-12-3 IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 217,000.00 0.00 2023-08-28 2023-09-02 2023-10-14 2023-10-15 2023-10-19 y, 9 Village Furnaces constru nvelope (1 envelope proce lementation 1 ation in targeted areas ction work. ss) (Component: 1, Subcompone nt: 1.1, Thematic Title: 1.1.4. ) TR-CEKEREK RST-377783-C W-RFQ / TRGM Çorum Provin cial Directorate of Agriculture and Forestry, Pasture/Highla Component 1: Investments i Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-12-3 nd Improvement and Manage IBRD / 92720 n Resilient Landscape Integr Post Open - National 38,000.00 0.00 2023-09-02 2023-10-03 tions nvelope or explanation) lementation 1 ment. (Purchase of Canopy a ation in targeted areas nd Itch Piles-10 pcs) 5 canop y, 5 itch stakes. (Thematic Title: 1.1.2.3. Ran geland rehabilitation and ma nagement.) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-CEKEREK RST-307995-G Component 1: Investments i O-RFB / Yozgat Province TRG Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 545,000.00 0.00 Canceled 2022-08-10 2022-08-15 2022-09-14 2022-09-16 2022-09-29 2022-12-31 M forage plant hungarian vet nvelope ation in targeted areas ch seed procurement busines s TR-CEKEREK RST-314752-G Component 1: Investments i O-RFQ / Tokat Provincial Dire Request for Quota Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Open - National 98,500.00 0.00 Completed 2022-09-17 2022-11-12 2022-11-12 2022-12-31 2022-12-26 ctorate of Agriculture and For tions nvelope ation in targeted areas estry Wheat Seed Goods Pur chase Business TR-CEKEREK RST-314757-G O-RFQ / Tokat Provincial Dire Component 1: Investments i Request for Quota Single Stage - One E ctorate of Agriculture and For IBRD / 92720 n Resilient Landscape Integr Post Open - National 72,000.00 0.00 Completed 2022-09-17 2022-11-12 2022-12-05 2022-12-31 2022-12-26 tions nvelope estry Alfalfa Seed and Hunga ation in targeted areas rian Vetch Seed Procurement Business TR-CEKEREK RST-316294-G Component 1: Investments i O-RFB / Dairy Cattle Purchas Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Request for Bids Open - National 375,000.00 0.00 Canceled 2022-09-22 2022-10-24 2022-09-27 2022-10-27 2022-11-22 2022-11-06 2022-11-26 2022-12-31 e Business Within the Scope nvelope ation in targeted areas of Development of Livestock Activities TR-CEKEREK RST-319171-G Component 1: Investments i O-RFQ / Çorum Provincial Dir Request for Quota Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Limited 30,000.00 0.00 Completed 2022-10-14 2022-10-13 2022-11-20 2022-11-26 2022-12-31 2022-12-17 ectorate of Agriculture and F tions nvelope ation in targeted areas orestry Hungarian Vetch See d Procurement Business TR-CEKEREK RST-319174-G Component 1: Investments i O-RFQ / Sivas Provincial Dire Request for Quota Single Stage - One E IBRD / 92720 n Resilient Landscape Integr Post Limited 87,500.00 0.00 Completed 2022-10-14 2022-11-19 2022-11-20 2022-12-05 2022-12-31 2022-12-26 ctorate Of Agriculture and Fo tions nvelope ation in targeted areas restry Barley Seed Procurem etn Business Page 2 TR-CEKEREK RST-377125-G O-RFQ / Amasya OBM Çorum Forestry Operations Director Component 2: Institutional F Request for Quota Single Stage - One E Pending Impl ate Purchase of 3 Laptops an IBRD / 92720 ramework, Project Managem Post Open - National 4,500.00 0.00 2023-09-02 2023-10-13 2023-12-31 tions nvelope ementation d 1 Desktop Computer. ent, and Sustainability (Component:2, Subcompone nt: 2.2, Thematic Title: Projec t Management and Sustainab ility) TR-CEKEREK RST-377777-G O-RFQ / TRGM Çorum Provinc ial Directorate of Agriculture Component 1: Investments i and Forestry Pasture / Platea Request for Quota Single Stage - One E Pending Impl IBRD / 92720 n Resilient Landscape Integr Post Open - National 12,000.00 0.00 2023-09-02 2023-10-03 2023-12-31 u Rehabilitation and Manage tions nvelope ementation ation in targeted areas ment (Purchase of 25 animal drinking water basins.) (Thematic Title: 1.1.2.3. Ran geland rehabilitation and ma nagement.) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-CEKEREK RST-332049-NC -RFB / Survey Service Procur Component 2: Institutional F Single Stage - One E ement to be Carried out in 96 IBRD / 92720 ramework, Project Managem Post Request for Bids Open - National 145,000.00 0.00 Signed 2022-12-25 2023-02-11 2022-12-30 2023-02-10 2023-03-27 2023-02-20 2023-05-02 2023-03-12 2023-06-11 2023-08-09 nvelope Villages and 1440 Household ent, and Sustainability s for the Current Situation Su rvey CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-CEKEREK RST-354155-CS -CQS / Cekerek river basin fir Component 2: Institutional F Consultant Qualifi Under Implement st group micro-catchments n IBRD / 92720 ramework, Project Managem Post Open - National 230,000.00 0.00 2023-04-05 2023-05-31 2023-04-26 2023-06-09 2023-07-05 2023-07-09 2023-07-29 2023-12-31 cation Selection ation umber six and seven. Consul ent, and Sustainability tancy Service Procurement fo r Micro-Catchment Plans TR-CEKEREK RST-354225-CS -CQS / Cekerek river basin se Component 2: Institutional F Consultant Qualifi Under Implement cond group micro-catchment IBRD / 92720 ramework, Project Managem Post Open - National 197,000.00 0.00 2023-04-05 2023-05-31 2023-04-26 2023-06-09 2023-08-08 2023-07-09 2023-07-29 2023-12-31 cation Selection ation s number four and five. Cons ent, and Sustainability ultancy Service Procurement for Micro-Catchment Plans TR-CEKEREK RST-354227-CS -CQS / Cekerek river basin thi Component 2: Institutional F rd group micro-catchments n Consultant Qualifi Under Implement IBRD / 92720 ramework, Project Managem Post Open - National 183,000.00 0.00 2023-04-05 2023-05-31 2023-04-26 2023-06-09 2023-07-09 2023-07-29 2023-12-31 umber three and fourteen. C cation Selection ation ent, and Sustainability onsultancy Service Procurem ent for Micro-Catchment Plan s. TR-CEKEREK RST-354231-CS -CQS / Cekerek river basin fif Component 2: Institutional F Consultant Qualifi Under Implement th group micro-catchments n IBRD / 92720 ramework, Project Managem Post Open - National 167,000.00 0.00 2023-04-05 2023-05-31 2023-04-26 2023-06-09 2023-07-09 2023-07-29 2023-12-31 cation Selection ation umber eight and nine. Consul ent, and Sustainability tancy Service Procurement fo r Micro-Catchment Plans. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TR-CEKEREK RST-278210-CS Component 2: Institutional F Individual Consult -INDV / Hiring Procurement E IBRD / 92720 ramework, Project Managem Post Open 18,000.00 11,956.90 Signed 2022-02-09 2022-03-07 2022-03-04 2022-04-26 2022-03-04 2022-04-27 2022-03-08 2022-05-26 2023-03-08 ant Selection xperts for RSTs ent, and Sustainability TR-CEKEREK RST-278220-CS Component 2: Institutional F Individual Consult -INDV / Hiring M&E Experts fo IBRD / 92720 ramework, Project Managem Post Open 18,000.00 0.00 Canceled 2022-02-09 2022-03-07 2022-03-04 2022-03-04 2022-03-08 2023-03-08 ant Selection r RSTs ent, and Sustainability TR-CEKEREK RST-278221-CS Component 2: Institutional F Individual Consult -INDV / Hiring Financial Mana IBRD / 92720 ramework, Project Managem Post Open 18,000.00 0.00 Canceled 2022-02-09 2022-03-07 2022-03-04 2022-03-04 2022-03-08 2023-03-08 ant Selection gement Experts for RSTs ent, and Sustainability TR-CEKEREK RST-278224-CS Component 2: Institutional F Individual Consult -INDV / Hiring Environmental IBRD / 92720 ramework, Project Managem Post Open 18,000.00 0.00 Canceled 2022-02-09 2022-03-07 2022-03-04 2022-05-02 2022-03-04 2022-03-08 2023-03-08 ant Selection Experts for RSTs ent, and Sustainability TR-CEKEREK RST-278225-CS Component 2: Institutional F Individual Consult -INDV / Hiring Social Experts IBRD / 92720 ramework, Project Managem Post Open 18,000.00 0.00 Canceled 2022-02-09 2022-03-07 2022-03-04 2022-03-04 2022-03-08 2023-03-08 ant Selection for RSTs ent, and Sustainability TR-CEKEREK RST-297080-CS Component 2: Institutional F Individual Consult -INDV / Recruitment of Monit IBRD / 92720 ramework, Project Managem Post Open 18,000.00 7,154.74 Signed 2022-05-26 2022-05-30 2022-06-16 2022-07-01 2022-06-18 2022-07-04 2022-06-24 2022-07-14 2022-12-31 ant Selection oring and Evaluation Speciali ent, and Sustainability st TR-CEKEREK RST-297085-CS Component 2: Institutional F Individual Consult -INDV / Recruitment of Enviro IBRD / 92720 ramework, Project Managem Post Open 18,000.00 7,144.15 Signed 2022-05-26 2022-05-30 2022-06-16 2022-06-28 2022-06-18 2022-07-04 2022-06-24 2022-07-14 2022-12-31 ant Selection nmental Specialist ent, and Sustainability TR-CEKEREK RST-297086-CS Component 2: Institutional F Individual Consult -INDV / Recruitment of Finan IBRD / 92720 ramework, Project Managem Post Open 18,000.00 1,212.67 Signed 2022-05-26 2022-05-30 2022-06-16 2022-06-27 2022-06-18 2022-07-01 2022-06-24 2022-07-11 2022-12-31 ant Selection cial Management Specialist ent, and Sustainability TR-CEKEREK RST-297087-CS Component 2: Institutional F Individual Consult -INDV / Recruitment Of Social IBRD / 92720 ramework, Project Managem Post Open 18,000.00 0.00 Canceled 2022-05-26 2022-06-27 2022-06-16 2022-06-18 2022-06-24 2022-12-31 ant Selection Development Specialist ent, and Sustainability TR-CEKEREK RST-306878-CS Component 2: Institutional F Individual Consult -INDV / Recruitment Of Social IBRD / 92720 ramework, Project Managem Post Open - National 18,000.00 0.00 Canceled 2022-08-01 2022-08-22 2022-08-22 2022-08-24 2022-08-30 2022-12-31 ant Selection Development Specialist ent, and Sustainability TR-CEKEREK RST-319168-CS Component 2: Institutional F Individual Consult -INDV / Recruitment Of Social IBRD / 92720 ramework, Project Managem Post Open - National 18,000.00 0.00 Canceled 2022-10-07 2022-10-06 2022-11-10 2022-11-28 2022-11-15 2022-11-30 2022-12-31 ant Selection Development Specialist ent, and Sustainability Page 3 TR-CEKEREK RST-333645-CS Component 2: Institutional F Individual Consult -INDV / Social Safeguard Exp IBRD / 92720 ramework, Project Managem Post Open - National 18,000.00 0.00 Signed 2022-12-30 2022-12-29 2023-01-23 2023-02-20 2023-01-26 2023-02-20 2023-02-01 2023-02-25 2023-12-31 ant Selection ert İndividual Consultant Rec ent, and Sustainability ruitment. TR-CEKEREK RST-333650-CS Component 2: Institutional F Individual Consult -INDV / Biodiversity Expert İn IBRD / 92720 ramework, Project Managem Post Open - National 18,000.00 0.00 Signed 2022-12-30 2022-12-29 2023-01-23 2023-02-17 2023-01-26 2023-02-20 2023-02-01 2023-02-25 2023-12-31 ant Selection dividual Consultant Recruitm ent, and Sustainability ent TR-CEKEREK RST-348802-CS Component 2: Institutional F Individual Consult -INDV / Procurement Expert İ IBRD / 92720 ramework, Project Managem Post Open - National 21,600.00 0.00 Canceled 2023-03-17 2023-03-20 2023-04-12 2023-04-17 2023-04-27 2023-12-31 ant Selection ndividual Consultant Recruit ent, and Sustainability ment TR-CEKEREK RST-358348-CS Component 2: Institutional F Individual Consult -INDV / Procurement Expert İ IBRD / 92720 ramework, Project Managem Post Open - National 21,600.00 0.00 Canceled 2023-04-28 2023-05-12 2023-05-21 2023-05-21 2023-05-25 2023-12-31 ant Selection ndividual Consultant Recruit ent, and Sustainability ment Page 4