Procurement Plan I. General 1. Project Information Country: Tanzania Project Name: Resilient Natural Resources Management for Growth Project Project ID: P150523 2. Project Implementation Agency: Ministry of Natural Resources and Tourism (MNRT) Tanzania National Parks (TANAPA) Tanzania Wildlife Management Authority (TAWA) National Irrigation Commission (NIrC) Rufiji Basin Water Board (RBWB) 3. Date of the Procurement Plan: June 2017 4. Period Covered by this Procurement Plan: First 18 Months Procurement Plan II. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works and Non-Consulting Services Procurement Approaches and Methods (US$ Prior Review millions) Category (US$ Open Open Request for millions) International National Quotation (RfQ) Works ≥5 ≥ 15.0 < 15 < 0.2 Goods, IT, and non- ≥1.5 ≥5 <5 < 0.1 consulting services B. Consulting Services Category Prior Review Short List of National Consultants (US$ (US$ million) millions) Consulting Engineering and Services Construction Supervision Consultants ≥ 0.5 <0.3 < 0.3 (Firms) Individual ≥ 0.2 NA. NA. 1 Consultants [Overall Project Procurement Risk is HIGH] Notes: Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National News Paper(s) of wide circulation and/or Regional News Paper(s). 2 III. Packages for Goods, Works and Non-Consulting Services Sr./ No Contract Description Estimate Review Market Selection Evaluation Procurement Prequa Domesti Expected Expected d Cost by Bank Approach Method Options Process: lificatio c date of date of (US$) (Prior/Pos (Open- (RFP, RFB, (BAFO, (Single/Multipl n Preferen bid/ Contract t) National/ RFQ, DS Rated e Stages; (Yes/ ce proposal Signature International etc.) Criteria One/Two No) (Yes/No) opening Limited etc.) etc.) Envelopes etc) Goods Works Non-Consulting Services 3 I. Packages for Consulting Services Sr. No Contract Description Estimated Review Market Selection Shortlisti Expected date of Expected date Cost (US$) by Bank Approach Method ng bid/ proposal of Contract (Prior/Pos (Open- (QCBS, FBBS, (Yes/ No) opening Signature t) National/ LCBS, QBS, International CQS, DS etc.) Limited etc.) 4 PROCUREMENT Tanzania : Tanzania: Resilient Natural Resource Management for Tourism and Growth PLAN General Information Country: Tanzania 2017-06-07 Bank’s Approval Date of the Original Procurement Plan: 2023-08-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150523 GPN Date: 2018-08-17 Project Name: Tanzania: Resilient Natural Resource Management for Tourism and Growth Loan / Credit No: IDA / Q9740, IDA / 61430 Ministry of Natural Resources and Tourism Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MNRT-375127-CW-RFB / CONSTRUCTION OF SOUTHE RN CIRCUIT TOURISM MARKE TING DESTINATION AND WIL Request for B DLIFE RESEARCH CENTRE AT 1. Strengthen management ids - Small W Open - Internationa Single Stage - One E Pending Imp 2024-12-1 KIHESA KILOLO-IRINGA IDA / 61430 and improve infrastructure i Prior Request for Bids orks SPD (1 e 0.00 2023-08-21 2023-08-26 2023-10-07 2023-11-06 2023-12-11 l nvelope lementation 0 n priority Protected Areas nvelope proc Lot 1 - Construction of South ess) ern circuit tourism marketing destination for TTB lOT 2 -Construction of Wildlif e Research Centre for TAWIRI GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 4. Project management, insti TZ-MNRT-16999-GO-RFQ / Pr tutional strengthening, quali Request for Quota Single Stage - One E ocurement of Printers and Co IDA / Q9740 Post Open - National 7,222.94 Completed 2017-06-11 2017-07-09 2019-04-10 2018-01-05 2019-05-01 ty assurance and control, an tions nvelope mputers d monitoring and evaluation 4. Project management, insti TZ-MNRT-40866-GO-RFQ / S tutional strengthening, quali Request for Quota Single Stage - One E upply of IT Equipment for PC IDA / 61430 Post Open - National 0.00 Canceled 2018-02-11 2018-04-08 2018-10-05 ty assurance and control, an tions nvelope U and M&E d monitoring and evaluation 4. Project management, insti TZ-MNRT-40876-GO-DIR / Lic tutional strengthening, quali ense for financial manageme IDA / 61430 Post Direct Selection Direct 0.00 Canceled 2018-01-28 2018-02-02 2018-03-09 2018-09-05 ty assurance and control, an nt d monitoring and evaluation TZ-MNRT-82691-GO-UN / Pro 4. Project management, insti curement of Motor Vehicles f tutional strengthening, quali UN Agencies (Dire IDA / 61430 Prior Direct 339,714.00 Signed 2018-10-25 2019-11-25 2018-10-30 2021-04-09 2018-12-04 2020-08-09 2019-06-02 or the Project Coordination U ty assurance and control, an ct) nit and Implementing Agenci d monitoring and evaluation es TZ-MNRT-129698-GO-RFQ / 4. Project management, insti Supply of office equipment a tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 11,042.03 Completed 2019-09-14 2019-11-07 2019-11-09 2020-04-05 2020-05-07 2020-04-30 nd computers to support imp ty assurance and control, an tions nvelope rovement of institution capac d monitoring and evaluation ities TZ-MNRT-130397-GO-DIR / S 4. Project management, insti upply of EPICOR Licences, Co tutional strengthening, quali IDA / 61430 Post Direct Selection Direct 0.00 Canceled 2019-09-16 2019-09-21 2019-10-26 2020-04-23 nfiguration and Training of us ty assurance and control, an ers under REGROW Project d monitoring and evaluation TZ-MNRT-187392-GO-RFQ / 4. Project management, insti Supply of office equipment, R tutional strengthening, quali Request for Quota Single Stage - One E esearch equipment's and co IDA / 61430 Post Open - National 0.00 Canceled 2020-08-10 2020-10-05 2021-04-03 ty assurance and control, an tions nvelope mputers to support improve d monitoring and evaluation ment of institutional capaciti es- TAWIRI TZ-MNRT-194866-GO-RFQ / 4. Project management, insti Procurement of Moto vehicle tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 0.00 Canceled 2020-10-03 2020-11-28 2021-05-27 s for the Project Coordination ty assurance and control, an tions nvelope Unit d monitoring and evaluation TZ-MNRT-187377-GO-RFQ / 4. Project management, insti Supply of office equipment a tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 3,579.13 Completed 2020-09-26 2020-10-10 2020-11-21 2020-12-01 2021-05-20 2021-02-24 nd computers to support imp ty assurance and control, an tions nvelope rovement of institutional cap d monitoring and evaluation acities for TFS 4. Project management, insti TZ-MNRT-60449-GO-RFB / su tutional strengthening, quali Request for Quota Single Stage - One E pply of office furniture's for T IDA / 61430 Post Limited 2,808.79 Completed 2020-09-26 2020-09-08 2020-11-21 2021-04-17 2021-05-20 2022-02-26 ty assurance and control, an tions nvelope AWIRI office d monitoring and evaluation 4. Project management, insti TZ-MNRT-195448-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 0.00 Canceled 2020-09-26 2020-09-06 2020-11-21 2021-05-20 Supply of ICT Equipment's ty assurance and control, an tions nvelope d monitoring and evaluation TZ-MNRT-205778-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Supply of soil sampling equip IDA / 61430 and improve infrastructure i Post Limited 20,982.00 Completed 2020-11-25 2020-12-23 2021-01-20 2021-04-17 2021-07-19 2022-02-23 tions nvelope ment's and pasture meter n priority Protected Areas TZ-MNRT-205782-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Supply of range finder, binoc IDA / 61430 and improve infrastructure i Post Limited 15,415.30 Completed 2020-11-25 2020-11-30 2021-01-20 2021-04-17 2021-07-19 2022-02-23 tions nvelope ular and walker talker n priority Protected Areas 1. Strengthen management TZ-MNRT-205784-GO-RFQ / Request for Quota Single Stage - One E IDA / 61430 and improve infrastructure i Post Limited 6,831.17 Completed 2020-11-25 2020-11-30 2021-01-20 2021-04-17 2021-07-19 2022-02-23 supply of Sharman traps tions nvelope n priority Protected Areas 1. Strengthen management TZ-MNRT-205786-GO-DIR / S IDA / 61430 and improve infrastructure i Post Direct Selection Direct 18,568.33 Completed 2020-11-20 2021-02-19 2020-11-25 2020-09-04 2020-12-30 2021-04-17 2021-06-28 2021-07-02 upply of Animal Drugs n priority Protected Areas 4. Project management, insti TZ-MNRT-201735-GO-RFB / tutional strengthening, quali Supply of Collar Equipment's IDA / 61430 Prior Direct Selection Direct 0.00 Canceled 2020-11-20 2020-11-25 2020-12-30 2021-06-28 ty assurance and control, an for TAWIRI office d monitoring and evaluation Page 1 4. Project management, insti TZ-MNRT-208411-GO-DIR / P tutional strengthening, quali rocurement of One Unit of M IDA / 61430 Post Direct Selection Direct 0.00 Canceled 2020-12-07 2021-02-19 2020-12-12 2020-12-17 2021-01-16 2021-07-15 ty assurance and control, an otor vehicle for PCU d monitoring and evaluation 4. Project management, insti TZ-MNRT-226293-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E SUPPLY OF ICT EQUIPMENTS IDA / 61430 Post Limited 40,452.75 Completed 2021-04-04 2021-04-06 2021-05-30 2021-07-14 2021-11-26 2022-03-31 ty assurance and control, an tions nvelope FOR TAWIRI d monitoring and evaluation 4. Project management, insti TZ-MNRT-228083-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 2,900.39 Completed 2021-01-24 2021-01-19 2021-03-21 2021-05-18 2021-09-17 2021-07-02 Supply of Laptop for TTB ty assurance and control, an tions nvelope d monitoring and evaluation 4. Project management, insti TZ-MNRT-228080-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 6,884.60 Completed 2019-05-24 2020-05-21 2019-07-19 2021-02-17 2020-01-15 2021-04-21 Supply of ICT Equipments ty assurance and control, an tions nvelope d monitoring and evaluation 4. Project management, insti TZ-MNRT-228082-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 4,397.11 Completed 2019-05-24 2020-05-21 2019-07-19 2021-02-17 2020-01-15 2021-04-21 Supply of Furnitures ty assurance and control, an tions nvelope d monitoring and evaluation 4. Project management, insti TZ-MNRT-234689-GO-DIR / S tutional strengthening, quali UPPLY OF COLLAR EQUIPMEN IDA / 61430 Post Direct Selection Direct 153,627.28 Signed 2021-05-31 2021-05-06 2021-06-05 2021-05-27 2021-07-10 2021-10-09 2022-01-06 ty assurance and control, an T FOR TAWIRI d monitoring and evaluation TZ-MNRT-233355-GO-RFQ / 4. Project management, insti SUPPLY OF ICT EQUIPMENTS tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 9,124.14 Completed 2021-06-26 2021-08-27 2021-08-21 2021-12-01 2022-02-17 2022-03-31 FOR COMMUNICATION SPECI ty assurance and control, an tions nvelope ALIST d monitoring and evaluation 4. Project management, insti TZ-MNRT-239701-GO-DIR / S tutional strengthening, quali IDA / 61430 Post Direct Selection Direct 81,011.83 Completed 2021-09-06 2021-09-24 2021-09-11 2021-09-28 2021-10-16 2021-12-11 2022-04-14 2022-05-11 UPPLY OF MOTORVEHICLE ty assurance and control, an d monitoring and evaluation TZ-MNRT-266807-GO-RFQ / 4. Project management, insti Designing, Printing and Suppl tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 8,634,384.58 Signed 2021-12-13 2021-12-14 2022-02-07 2022-03-06 2022-08-06 2022-07-08 y of Promotional Materials for ty assurance and control, an tions nvelope REGROW Project -PCU d monitoring and evaluation TZ-MNRT-266810-GO-RFQ / 4. Project management, insti Supply of Video Conference T tutional strengthening, quali Request for Quota Single Stage - One E Under Imple IDA / 61430 Post Limited 0.00 2021-12-13 2022-06-24 2022-02-07 2022-08-06 ools for REGROW Project - PC ty assurance and control, an tions nvelope mentation U d monitoring and evaluation TZ-MNRT-266811-GO-RFQ / 4. Project management, insti Designing, Printing and Suppl tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 59,310.68 Signed 2021-12-11 2021-12-14 2022-02-05 2022-02-23 2022-08-04 y of Promotional Materials for ty assurance and control, an tions nvelope Tourism destination for Sout d monitoring and evaluation hern Circuit - TTB 4. Project management, insti TZ-MNRT-263005-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E Procurement of ICT Equipme IDA / 61430 Post Limited 11,106.37 Signed 2021-12-13 2021-12-13 2022-02-07 2022-07-07 2022-08-06 ty assurance and control, an tions nvelope nt for TTB d monitoring and evaluation 4. Project management, insti TZ-MNRT-266923-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E Supply of IC Equipment for P IDA / 61430 Post Limited 35,336.08 Completed 2021-12-13 2021-12-14 2022-02-07 2022-02-23 2022-08-06 2022-04-08 ty assurance and control, an tions nvelope CU and TAWIRI d monitoring and evaluation TZ-MNRT-281885-GO-DIR / P rocurement of Two (02) Units 1. Strengthen management of 4WD Standard Land Cruise IDA / 61430 and improve infrastructure i Post Direct Selection Direct 0.00 Signed 2022-03-01 2022-08-16 2022-03-06 2022-08-22 2022-04-10 2022-11-30 2022-10-07 r Station Wagon and One (01 n priority Protected Areas ) Unit of Special Filming Vehi cle 4WD Land Cruiser Double Cabin TZ-MNRT-298741-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Supply of Camera Traps for T IDA / 61430 and improve infrastructure i Post Limited 0.00 Signed 2022-06-12 2022-06-22 2022-08-07 2022-11-27 2023-02-03 tions nvelope AWIRI n priority Protected Areas 4. Project management, insti TZ-MNRT-298751-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E Supply of office equipment fo IDA / 61430 Post Limited 0.00 Completed 2022-06-12 2022-06-23 2022-08-07 2022-12-07 2023-02-03 2023-03-04 ty assurance and control, an tions nvelope r PCU d monitoring and evaluation TZ-MNRT-278600-GO-RFB / 1. Strengthen management Single Stage - One E Procurement of One (01) Unit IDA / 61430 and improve infrastructure i Post Request for Bids Limited 0.00 Canceled 2022-02-18 2022-03-11 2022-02-23 2022-03-15 2022-04-06 2022-05-06 2022-06-10 2022-12-07 nvelope of Overland Truck n priority Protected Areas 4. Project management, insti TZ-MNRT-263004-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E Procurement of Office Furnitu IDA / 61430 Post Limited 0.00 Canceled 2021-12-13 2021-12-13 2022-02-07 2022-08-06 ty assurance and control, an tions nvelope re for TTB d monitoring and evaluation TZ-MNRT-315129-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E SUPPLY OF ICT EQUIPMENT F IDA / 61430 and improve infrastructure i Post Limited 0.00 Signed 2022-09-21 2022-11-08 2022-11-09 2023-02-14 2022-12-09 tions nvelope OR PCU AND TTB n priority Protected Areas TZ- MNRT-311822-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Supply of field equipment an IDA / 61430 and improve infrastructure i Post Open - National 0.00 Signed 2022-09-03 2022-10-29 2022-11-24 2023-04-27 tions nvelope d supplies n priority Protected Areas TZ- MNRT-309778-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E supply of office furniture for IDA / 61430 and improve infrastructure i Post Open - National 0.00 Signed 2022-09-03 2022-10-29 2022-11-24 2023-04-27 tions nvelope TTB n priority Protected Areas TZ-MNRT-306355-GO-RFB / 1. Strengthen management Procurement of One (01) Unit IDA / 61430 and improve infrastructure i Post Direct Selection Direct - National 0.00 Canceled 2022-08-03 2022-08-08 2022-09-12 2023-03-11 of Overland Safari Truck for T n priority Protected Areas TB TZ-MNRT-311822-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E SUPPLY OF FIELD EQUIPMEN IDA / 61430 and improve infrastructure i Post Open - National 0.00 Canceled 2022-09-03 2022-10-29 2023-04-27 tions nvelope T AND SUPPLIES n priority Protected Areas TZ-MNRT-309778-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Supply of Office Furniture for IDA / 61430 and improve infrastructure i Post Open - National 0.00 Canceled 2022-09-03 2022-10-29 2023-04-27 tions nvelope TTB n priority Protected Areas Page 2 TZ-MNRT-356525-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Under Imple Procurement of ICT equipme IDA / 61430 and improve infrastructure i Post Limited 0.00 2023-05-24 2023-05-24 2023-07-19 2024-01-15 tions nvelope mentation nt for PCU n priority Protected Areas TZ-MNRT-366015-GO-DIR / P rocurement of One (01) unit 4. Project management, insti of 4WD Min Station Wagon a tutional strengthening, quali Direct - Internation Pending Impl IDA / 61430 Post Direct Selection 0.00 2023-08-14 2023-08-17 2023-09-21 2024-03-19 nd Five (05) units of 4WD Sta ty assurance and control, an al ementation ndard Land Cruiser Station W d monitoring and evaluation agon Hard Top for PCU, TFS, RBWB and NIRC NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MNRT-315140-NC-RFQ / P 4. Project management, insti RITING AND SUPPLY OF PRO tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 0.00 Signed 2022-09-16 2022-11-08 2022-10-21 2023-02-01 2022-11-20 MOTIONAL MATRIALS FOR PC ty assurance and control, an tions nvelope U d monitoring and evaluation TZ-MNRT-324543-NC-RFQ / 1. Strengthen management DESIGNING AND PRINTING O Request for Quota Single Stage - One E IDA / 61430 and improve infrastructure i Post Limited 0.00 Signed 2022-11-07 2022-11-04 2023-01-02 2023-01-13 2023-07-01 F PROMOTIONAL MATERIALS tions nvelope n priority Protected Areas FOR KARIBU KUSINI 2022 TZ-MNRT-326000-NC-RFQ / 1. Strengthen management Designing, Printing and Suppl Request for Quota Single Stage - One E IDA / 61430 and improve infrastructure i Post Limited 0.00 Signed 2022-11-27 2022-12-14 2023-01-22 2023-03-27 2023-07-21 y of Promotional Materials for tions nvelope n priority Protected Areas Southern Tourism Circuit - TT B TZ-MNRT-362835-NC-RFQ / Designing, Printing and Suppl 1. Strengthen management y of Promotional Materials for Request for Quota Single Stage - One E Under Imple IDA / 61430 and improve infrastructure i Post Limited 0.00 2023-05-28 2023-06-05 2023-07-23 2024-01-19 Southern Circuit Cultural Tou tions nvelope mentation n priority Protected Areas rism Enterprises , Kilifair and Saba Saba Exhibitions for TT B. TZ-MNRT-375184-NC-RFQ / 1. Strengthen management Designing, developing and pr Request for Quota Single Stage - One E Pending Impl IDA / 61430 and improve infrastructure i Post Limited 0.00 2023-08-16 2023-10-11 2024-04-08 inting press Kits for the Sout tions nvelope ementation n priority Protected Areas hern Circuit for Tanzania Tou rist Board (TTB) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MNRT-17017-CS-QCBS / P 2. Strengthen alternative liv rovision of consultancy servic elihoods for targeted comm Quality And Cost- Open - Internationa es for environmental and soc IDA / Q9740 Prior 396,851.50 Signed 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-22 2017-06-27 2016-11-03 2018-06-27 unities in proximity to the pr Based Selection l ial impact assessment includi iority Protected Areas ng ESMF, RPF and PF TZ-MNRT-17022-CS-CQS / C onsultancy services to condu 2. Strengthen alternative liv ct a curriculum development elihoods for targeted comm Consultant Qualifi Pending Impleme workshop and elaborate a far IDA / Q9740 Post Open - National 0.00 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-27 2017-12-24 unities in proximity to the pr cation Selection ntation mer field school program on iority Protected Areas on-farm water and crop man agement in the irrigation sch eme on the usangu plains TZ-MNRT-17027-CS-QCBS / P 3. Strengthen landscape ma rovision of consultancy servic nagement and infrastructure es to undertake a reconnaiss Quality And Cost- Open - Internationa IDA / Q9740 investments in and upstrea Prior 539,043.75 Under Review 2017-06-06 2017-06-27 2017-06-27 2017-06-27 2017-06-27 2017-07-04 2017-10-27 2017-08-08 2016-11-02 2018-08-08 ance study of structural mea Based Selection l m of the Ruaha National Par sure to augment dry season f k lows in Ruaha National Park, Southern Tanzania TZ-MNRT-17052-CS-QCBS / Consultancy on locally based 1. Strengthen management tourism product developmen Quality And Cost- IDA / Q9740 and improve infrastructure i Prior Open - National 460,881.13 Signed 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-07-22 2017-06-27 2017-07-27 2018-06-27 t and socio- economic assess Based Selection n priority Protected Areas ment of communities adjace nt to selected protected area s in southern Tanzania TZ-MNRT-17054-CS-QCBS / c 3. Strengthen landscape ma onsultancy service to undert nagement and infrastructure Quality And Cost- ake a reconnaissance survey IDA / Q9740 investments in and upstrea Prior Open - National 562,591.20 Signed 2017-06-06 2017-06-23 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-07-17 2017-06-27 2017-07-23 2018-06-27 Based Selection of agricultural water manage m of the Ruaha National Par ment in usangu flats Souther k n Tanzania TZ-MNRT-40665-CS-QCBS / 4. Project management, insti Market research and product tutional strengthening, quali Quality And Cost- IDA / 61430 Prior Open - National 274,194.24 Signed 2018-01-30 2018-05-13 2018-02-20 2018-06-12 2018-04-05 2019-01-22 2018-05-03 2019-02-25 2018-06-02 2019-08-01 2018-07-07 2021-09-20 2018-08-11 2020-05-30 2019-08-11 market development strateg ty assurance and control, an Based Selection y d monitoring and evaluation TZ-MNRT-40894-CS-CQS / O 1. Strengthen management ption for PPP and private sect Consultant Qualifi IDA / 61430 and improve infrastructure i Post Open - National 0.00 Canceled 2018-03-05 2018-03-26 2018-05-09 2018-06-08 2018-07-13 2019-01-09 or investment opportunities i cation Selection n priority Protected Areas n the project area TZ-MNRT-57587-CS-QCBS / Consultancy services for desi 1. Strengthen management gning drawing and preparati Quality And Cost- IDA / 61430 and improve infrastructure i Post Open - National 0.00 Canceled 2018-04-13 2018-05-04 2018-06-17 2018-07-15 2018-08-14 2018-09-18 2018-10-23 2019-10-23 on of bill of quantity and tend Based Selection n priority Protected Areas er document for construction of southern circuit managem ent center TZ-MNRT-40895-CS-CQS / Th e Preparation of an Impleme 2. Strengthen alternative liv ntation Plan to Develop Viabl elihoods for targeted comm Consultant Qualifi IDA / 61430 Post Open - National 0.00 Canceled 2018-02-06 2018-02-27 2018-09-19 2018-04-12 2018-05-12 2018-06-16 2018-12-13 e Goods and Services Supply unities in proximity to the pr cation Selection Capacity in Selected Commu iority Protected Areas nities under the REGROW Pro ject TZ-MNRT-270518-CS-CQS / P 4. Project management, insti ROVISION OF CONSULTANCY tutional strengthening, quali Consultant Qualifi Under Implement SERVICE FOR FOR DEVELOP IDA / 61430 Post Open - National 0.00 2021-12-23 2022-01-07 2022-01-13 2022-01-21 2022-02-26 2022-03-23 2022-03-28 2022-08-19 2022-05-02 2022-10-29 ty assurance and control, an cation Selection ation MENT AND PRODUCTION OF d monitoring and evaluation CONTENT FOR SOCIAL MEDIA PLATFORMS Page 3 TZ-MNRT-270522-CS-CQS / P ROVISION OF CONSULTANCY 4. Project management, insti SERVICE FOR FACILITATION tutional strengthening, quali Consultant Qualifi IDA / 61430 Post Open - National 0.00 Signed 2021-12-23 2022-01-07 2022-01-13 2022-01-21 2022-02-26 2022-03-23 2022-03-28 2022-08-19 2022-05-02 2022-10-11 2022-10-29 OF FOUR (4) LOCAL CHANNE ty assurance and control, an cation Selection LS FOR 30 DAYS EACH TO DE d monitoring and evaluation VELOP DOMESTIC TOURISM P ROMOTIONAL VIDEOS TZ-MNRT-270524-CS-CQS / P 4. Project management, insti ROVISION OF CONSULTANCY tutional strengthening, quali Consultant Qualifi Under Implement SERVICE OF BROADCASTING IDA / 61430 Post Open - National 0.00 2021-12-23 2022-01-07 2022-01-13 2022-01-21 2022-02-26 2022-03-22 2022-03-28 2022-08-19 2022-05-02 2022-10-29 ty assurance and control, an cation Selection ation TANZANIA TOURISM DESTINA d monitoring and evaluation TION THROUGH TV SPOT WIT HIN USA AND CHINA TZ-MNRT-271999-CS-CQS / P 4. Project management, insti rovision of Consultancy Servi tutional strengthening, quali Consultant Qualifi IDA / 61430 Post Open - National 0.00 Signed 2022-01-14 2022-01-07 2022-02-04 2022-01-21 2022-03-20 2022-03-22 2022-04-19 2022-08-19 2022-05-24 2022-12-06 2022-11-20 ces for Upgrading a Biodivers ty assurance and control, an cation Selection ity Database d monitoring and evaluation TZ-MNRT-270516-CS-CQS / P 4. Project management, insti ROVISON OF CONSULTANCY tutional strengthening, quali Quality And Cost- Open - Internationa IDA / 61430 Post 0.00 Canceled 2022-01-14 2022-01-17 2022-02-04 2022-01-26 2022-03-20 2022-04-17 2022-05-17 2022-06-21 2022-07-26 2023-07-26 SERVICE FOR DIGITAL BILLBO ty assurance and control, an Based Selection l ARDS ADVERTISEMENT IN EU d monitoring and evaluation ROPE AND TANZANIA TZ-MNRT-286005-CS-QCBS / PROVISION OF CONSULTANC 1. Strengthen management Quality And Cost- Open - Internationa Under Implement Y SERVICES FOR DIGITAL BIL IDA / 61430 and improve infrastructure i Post 0.00 2022-03-25 2022-06-15 2022-04-15 2022-08-12 2022-05-29 2022-06-26 2022-07-26 2022-08-30 2022-10-04 2023-10-04 Based Selection l ation LBOARDS ADVERTISEMENT I n priority Protected Areas N EUROPE AND TANZANIA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MNRT-17056-CS-INDV / u ndertaking of an assessment 2. Strengthen alternative liv of current benefit sharing mo elihoods for targeted comm Individual Consult IDA / Q9740 Post Open 31,500.00 Signed 2017-06-06 2016-01-15 2017-06-06 2016-08-15 2017-06-06 2016-10-10 2017-06-27 2016-10-21 2017-12-24 dels associated with with nat unities in proximity to the pr ant Selection ural resources and tourism a iority Protected Areas nd lesson learned from best practises 4. Project management, insti TZ-MNRT-17058-CS-INDV / I tutional strengthening, quali Individual Consult IDA / Q9740 Post Open 28,331.15 Completed 2017-06-06 2017-06-06 2017-06-06 2016-10-20 2017-06-06 2016-12-05 2017-06-27 2016-12-16 2017-12-24 2018-02-01 nstitutional assessment ty assurance and control, an ant Selection d monitoring and evaluation TZ-MNRT-18592-CS-INDV / C 4. Project management, insti onsultancy Services for revie tutional strengthening, quali Individual Consult wing the existing documents IDA / Q9740 Post Open 99,957.00 Signed 2017-06-20 2017-07-20 2017-06-20 2015-11-17 2017-06-20 2016-02-15 2017-07-11 2016-03-15 2018-01-07 ty assurance and control, an ant Selection and preparation of Project Im d monitoring and evaluation plementation manual (PIM) fo r REGROW Project. 4. Project management, insti TZ-MNRT-40659-CS-INDV / T tutional strengthening, quali Individual Consult IDA / 61430 Post Open 0.00 Canceled 2018-01-28 2018-03-18 2018-04-08 2018-05-13 2018-11-09 raining need asesment ty assurance and control, an ant Selection d monitoring and evaluation 4. Project management, insti TZ-MNRT-40899-CS-INDV / D tutional strengthening, quali Individual Consult IDA / 61430 Post Open 0.00 Canceled 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2018-12-10 evelopment of web page ty assurance and control, an ant Selection d monitoring and evaluation TZ-MNRT-57593-CS-INDV / C onsultancy service for prepar 4. Project management, insti ation of communication strat tutional strengthening, quali Individual Consult IDA / 61430 Post Open 0.00 Canceled 2018-04-23 2019-11-21 2018-06-11 2018-07-02 2018-08-06 2019-02-02 egy for Resilient natural Reso ty assurance and control, an ant Selection urces management for Touris d monitoring and evaluation m and Growth (REGROW) Pro ject TZ-MNRT-57596-CS-INDV / C onsultancy services for estab 4. Project management, insti lishment of baseline for Moni tutional strengthening, quali Individual Consult IDA / 61430 Post Open 159,500.00 Signed 2018-04-20 2020-02-04 2018-06-08 2021-04-14 2018-06-29 2021-10-26 2018-08-03 2021-11-23 2019-01-30 toring and Evaluation for Resi ty assurance and control, an ant Selection lient natural Resource Manag d monitoring and evaluation ement for Tourism and Growt h (REGROW) Project TZ-MNRT-57448-CS-INDV / p 4. Project management, insti rovision of Financial Manage tutional strengthening, quali Individual Consult IDA / 61430 Prior Open 0.00 Canceled 2018-04-15 2018-05-13 2018-06-03 2018-06-24 2018-07-29 2019-01-25 ment support services by Jun ty assurance and control, an ant Selection e 2018 d monitoring and evaluation 4. Project management, insti TZ-MNRT-57449-CS-INDV / P tutional strengthening, quali Individual Consult rovision of procurement supp IDA / 61430 Prior Open 0.00 Canceled 2018-04-10 2018-05-13 2018-05-29 2018-06-19 2018-07-24 2019-01-20 ty assurance and control, an ant Selection ort services by June 2018 d monitoring and evaluation TZ-MNRT-65394-CS-INDV / C 4. Project management, insti onsultancy Services for provi tutional strengthening, quali Individual Consult IDA / 61430 Post Open 0.00 Canceled 2018-06-07 2018-06-07 2018-07-26 2018-08-16 2018-09-20 2019-03-19 sion of Environmental and So ty assurance and control, an ant Selection cial Safeguards Management d monitoring and evaluation and supervision. TZ-MNRT-187352-CS-INDV / Facilitate the establishment 1. Strengthen management Individual Consult of an e- learning training plat IDA / 61430 and improve infrastructure i Post Open 0.00 Canceled 2020-09-01 2021-03-10 2020-10-20 2020-11-10 2020-12-15 2021-06-13 ant Selection form on southern tourism cir n priority Protected Areas cuit for international travel a gents for TTB TZ-MNRT-196123-CS-INDV / 1. Strengthen management Consultancy services for pre Individual Consult IDA / 61430 and improve infrastructure i Post Limited 0.00 Canceled 2020-10-01 2021-03-10 2020-10-06 2020-10-27 2020-12-01 2021-05-30 paration of design and printi ant Selection n priority Protected Areas ng Southern Circuit Tourism Map for TTB TZ-MNRT-234690-CS-CQS / 1. Strengthen management Consultancy work for a Statis Individual Consult IDA / 61430 and improve infrastructure i Post Limited 0.00 Canceled 2021-06-21 2021-08-22 2021-06-26 2021-09-20 2021-07-17 2021-08-21 2022-02-17 tic Training for Wildlife Resea ant Selection n priority Protected Areas rchers at the TAWIRI TZ-MNRT-254343-CS-INDV / 4. Project management, insti Provision of Consultancy Serv tutional strengthening, quali Individual Consult IDA / 61430 Post Limited 27,000.00 Completed 2021-09-27 2021-09-21 2021-10-02 2021-09-30 2021-10-23 2021-11-13 2021-11-27 2021-12-02 2022-05-26 2022-06-01 ices of Procurement Speciali ty assurance and control, an ant Selection st for REGROW Project d monitoring and evaluation Page 4 TZ-MNRT-234690 - CS-CQS - 4. Project management, insti 1 / Consultancy work for a St tutional strengthening, quali Individual Consult IDA / 61430 Post Limited 15,000.00 Completed 2021-06-21 2021-08-22 2021-06-26 2021-09-20 2021-07-17 2021-12-08 2021-08-21 2021-12-22 2022-02-17 2022-01-18 atistic Training for Wildlife Re ty assurance and control, an ant Selection searchers at the TAWIRI d monitoring and evaluation TZ-MNRT-306399-CS-CDS / P rovision of Consultancy Servi ce for Environmental and Soc 1. Strengthen management ial Impact Assessment Study IDA / 61430 and improve infrastructure i Post Direct Selection Direct - National 0.00 Signed 2022-08-03 2022-08-12 2022-08-13 2022-09-02 2022-10-17 2023-04-09 2023-04-15 for the Construction of South n priority Protected Areas ern Circuit Tourism Marketin g Destination Centre and Wil dlife Research Centre at Kihe sa Kilolo in Iringa Municipal. TZ-MNRT-306381-CS-CDS / Consultancy service for prep aration of detailed engineeri 1. Strengthen management ng design, tender document Direct - Internation IDA / 61430 and improve infrastructure i Post Direct Selection 0.00 Signed 2022-09-12 2022-09-08 2022-09-22 2022-09-08 2022-11-26 2023-03-04 2024-04-30 and supervision of constructi al n priority Protected Areas on of the Southern Circuit To urism Marketing Destination and Wildlife Research Centre at Kihesa Kilolo in Iringa for T TB and TAWIRI TZ-MNRT-325456-CS-INDV / 1. Strengthen management Provision of Consultancy Serv Individual Consult Pending Impleme IDA / 61430 and improve infrastructure i Post Open - National 0.00 2022-11-17 2023-01-05 2023-01-26 2023-03-02 2023-08-29 ices for development of Sout ant Selection ntation n priority Protected Areas hern Tourism Circuit Map TZ-MNRT-325457-CS-INDV / Consultancy Services to facili 1. Strengthen management tate establishment (develop Individual Consult Under Implement IDA / 61430 and improve infrastructure i Post Open - National 0.00 2022-11-17 2022-11-22 2023-01-05 2023-01-26 2023-03-02 2023-08-29 ment) of an e - learning traini ant Selection ation n priority Protected Areas ng platform on Tanzania Sout hern Tourism Circuit for Inter national Travel Agents and M edia Page 5