Procurement Plan For Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project A World Bank Financed Project Project ID: P165129 [Procurement Plan Period: First 18 months of the Project] Covering the Period: January 2020 to June 2021 Submitted By Project Management Unit [PMU] Himachal Pradesh Forest Department Government of Himachal Pradesh India 2 3 PROCUREMENT PLAN Country: INDIA Borrower: Government of India on behalf of Government of Himachal Pradesh Project Name: Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project Project Implementation Agency: Project Management Unit [PMU], Himachal Pradesh Forestry Department [HPFD], Government of Himachal Pradesh Date of General Procurement Notice: December 18, 2019 Bank’s Approval Date of the Procurement Plan: Original … Revision 1: Revision 2: Date of the Procurement Plan: December 2019 Period covered by this Procurement Plan: January 2020 to June 2021 Applicable Procurement Rules. The Procurement of goods, works, consulting and non-consulting services to be financed by the Loan will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers [dated July 2016; revised November 2017 and August 2018], and the provisions of the Loan Agreement. If there is conflict between government decrees, rules, and regulations and the Bank Procurement Regulations, then Bank’s Procurement Regulations shall prevail. The project will be subject to World Bank Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants [“Anti-Corruption Guidelines”], dated October 15, 2006 and revised in January 2011 and as of July 1, 2016. The project will use the online tool Systematic Tracking of Exchanges in Procurement [STEP] to prepare, clear, and update its procurement plan, for monitoring procurement activities and for communication between the Borrower and the Bank. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under Paragraph 4.4 of the Procurement Regulations are set forth in STEP. Unless otherwise agreed with the World Bank, the World Bank’s Standard Procurement Documents [SPD], Requests for Proposals, and Forms of Consultant Contract will be used. Procurement under national procedures will be carried out based on National Procurement Procedures [NPP] conditions agreed with the Government of India. Procurement estimated at Indian Rupees [INR] 5 Lakhs and above will be submitted through government eProcurement systems provided by NIC 4 www.hptender.gov.in which have been assessed and deemed acceptable by the Bank against Multilateral Development Bank [MDB] requirements. Financial Management [FM] Manual. The FM Manual prepared for the project shall have a separate chapter on Procurement which will provide clear guidance on applicable procurement arrangement, procedures and thresholds, and shall be made available on the project website. Community Operations Manual [COM]. The COM prepared for the project will have clear directives for the community [GPs/individual beneficiaries] with regard to eligible procurement expenditures and agreed procurement arrangements, procedures and thresholds, and shall be made available on the project website. This will serve as a guidebook for procurement, with a view to providing operating instructions and bring in greater transparency and predictability in procurement procedures under the Project. Procurement Arrangements and Profile. Procurement under the Project will be carried out at the central level by the Project Management Unit [PMU] headed by the Chief Project Director [CPD] established for the Project, at the District level by the District Project Officers assisted by the Accounts Assistant at the District Level in each of the 10 District Project Offices [DPOs] located in the Districts covered under the Project [Shimla, Solan, Sirmour, Bilaspur, Hamirpur, Mandi, Kullu, Chamba, Kangra and Una], and by beneficiary GPs [supported by DPOs] at the GP level, in accordance with their approved Gram Panchayat Resource Management Plans [GP-RMP]/MG/OMIF. Officials of the PMU have prior experience of implementing a World Bank financed project and have also undergone training in STEP. GPs will need to be capacitated and provided basic procurement training on applicable procurement procedures and procurement documentation requirements outlined in COM, before initiating their procurements. To meet the readiness requirements of the Department of Economic Affairs [DEA] of the Government of India, the Project has already initiated and awarded contract for critical consultancy package for Environmental and Social Assessment to be retroactively financed by the Bank. The project envisages procurement of low-risk, low-value goods, works and services as below: a. Goods and Non-Consulting Services to be procured under the project are likely to include the following. At State/PMU level, purchase of IT Equipment such laptops, computers, printer, etc., procurement of printing services for IEC, office vehicles, office furniture, etc. are envisaged. At District and GP level, procurement activities will include procurement of Barbed Wire, U/Staple, Tools, Gunny Bags, Vermicompost/ Farm yard Manure, Sand, Seeds, Wooden posts/ poles, Seedlings, Grass tufts, Sign boards/hand prints, seed testing instrument, Seed, Fertilizer, Pesticide, Livestock - Small and Large Ruminants, Agricultural Tools and Implements, equipment, Farm machinery, e.g., power tiller, chaff cutters, pipes, tarpaulins, Medicines, supplements, sprinklers, seedlings, etc. b. Procurement of Minor Civil Works is likely to include the following. At State/ PMU level, procurement of minor civil works will include extension, refurbishment and repair of office buildings, etc. At District and GP level, procurement activities will include procurement of works for construction of Water storage tanks, water channels, vermicompost pits, livestock Mangers, foot bridges, water lifting pumps, GI pipes, accessories, installation of ropeways, Ponds, Check Dams, Subsurface Dykes, Sump Wells etc. and labor contracts for preparing land 5 for nursery, preparing nursery beds, water tank, works of filling gunny bags, sowing of seeds, preparing temporary nursery sheds, watering, hoeing, weeding, , fencing, bush cutting, pit digging, planting seedlings, preparing contour trenches, planting grass tufts, drainage line treatment works, fire management works, allowances and incentives for fire management, Spring development, eradication of exotic weed- lantana, etc. It may be noted that civil works at GP level are demand driven. There are no major civil works contracts envisaged in the project. c. Consultancy Services to be procured under the project are likely to include services for developing a web-based portal for Integrated Financial Management Information System [IFMS], Water Monitoring and Modelling, Value Chain Scoping Studies, Technical Support Study for addressing the needs of Transhumant, M and E, MIS, Baseline Survey, External and Internal Audit, Third Party Verification agent to verify achievement of Disbursement Related Results [DLR]s, need based assessments and studies, individual experts, etc. No consultancy services contracts envisaged at the District/Sub-district levels. The project includes several features of a decentralized, demand-driven project, and activities to be taken up at the community level by selected beneficiaries shall be as per the GP-RMP approved by the PMU of the HP Forestry Department/MG/OMIF. The threshold of procurement activities at community level is expected not to exceed Request for Quotation [RFQ] threshold. Community-level procurement shall follow Community-Driven Development [CDD] arrangements as per the Bank’s Procurement Regulations and as outlined in the Community Operations Manual [COM] currently under preparation. Given other on-going government programs, the activities to be funded following COM shall be identified upfront to avoid double-dipping and will require very close monitoring and oversight. Project Procurement Strategy for Development [PPSD] and Procurement Plan. According to the requirement of the Regulations, a Project Procurement Strategy for Development [PPSD] has been developed, based on which the Procurement Plan for the first 18 months has been prepared. The PPSD describes how procurement in this project will support the Project Development Objective [PDO] and deliver value for money under a risk-based approach. It provides adequate supporting market analysis for the selection methods detailed in the procurement plan. The procurement plan specifies for each contract: [i] a description of the activities/contracts; [ii] selection methods to be applied; [iii] estimated cost; [iv] time schedules; [v] World Bank review requirements; and [vi] any other relevant procurement information. PMU shall submit to the World Bank, for its review and approval, any updates of the procurement plan approved by the World Bank. The project will use Systematic Tracking of Exchanges in Procurement [STEP] system for all its procurement activities carried out at the PMU [Centre] and District levels. Summary from PPSD. The project is preparing its Procurement Strategy document. As per the draft document, the project’s total value is US $100 million of which procurement spend is approximately 80 %. Extensive market analysis has been carried out for procurement packages and decisions on packages are made to ensure adequate participation of bidders. Consultancy contracts are framed based on market research and packaging decided in terms of scope of services and period. Based on the need assessment, the project has decided to 6 use Government e Marketplace [GeM]1 for procurement of Goods up to US $100,000 and as mentioned under the paragraph in the Procurement Plan on National Procurement Procedures. Procurement Capacity Building. Though project staff has past experience of implementing World Bank financed HP Mid-Himalayan Watershed Development Project [HPMHWDP] governed by the Bank’s Procurement Guidelines, however, they need to be exposed to the Procurement Regulations applicable to the Project. HP Forestry Department will be sending key procurement staff of PMU and DPOs to the Indian Institute of Management [IIM], Lucknow or the Administrative Staff College of India [ASCI], Hyderabad from time to time to attend procurement training on World Bank Procurement Framework [PF] applicable to the project. Presently, project staff from PMU and two DPOs will be attending the two-week residential training program on World Bank Procurement Regulations conducted at ASCI, Hyderabad in February 2020. These officials will subsequently provide training to other project staffs prior to implementation of the procurement activities in the project. The PMU/DPOs/APOs will also provide basic procurement training to GPs/Beneficiaries once the Gram Panchayat Resource Management Plan [GP-RMP] is approved by DPO/PMU, and before commencing implementation of GP-RMP. The project officials can also avail of the free Massive Open Online Course on public procurement www.procurementlearning.org offered by the Bank to build their capacity. The Bank had already conducted one training on STEP for PMU officials and will organize STEP training again on need basis for the concerned DPOs staff in near future. Procurement Planning. For each contract to be financed by the Loan, the different procurement methods or consultant selection methods to be used, the need for pre-qualification, estimated costs, prior review requirements, and time frame will be reflected in the Procurement Plan to be agreed between the Borrower and the Bank team. The Procurement Plan will be uploaded in STEP by PMU/DPOs and the approved procurement plan will be disclosed on the project website and Bank’s external website. The procurement plan for the first 18 months of project implementation and all its updates will be submitted to the Bank through STEP, and will lay out the appropriate, fit for purpose market approach and selection methods for procurement of goods, works, non-consulting and consulting services financed by the Bank. It will be updated at least annually or as required to reflect the actual project implementation needs and improvements in institutional capacity. eProcurement. Currently, the Himachal Pradesh Forestry Department of the Government of Himachal Pradesh is using e-procurement system for its procurement. However, PMU housed in the Forestry Department will be carrying out procurement using eProcurement for the first time in the project, therefore, their capacity building needs to be done for eProcurement. The project will make use of Government of India’s National Informatics Centre [NIC] platform assessed by the Bank against Multilateral Development Bank [MDB] requirements for procurements estimated at INR 5 Lakhs and above. Advance Contracting with Retroactive Financing. For effective project implementation and start-up, the project has initiated advance contracting of critical consultancies for Preparation of Environmental and Social Framework [ESF] and Project Implementation Plan [PIP], and procurement of small value goods such 1 https://gem.gov.in/ 7 as tools, gunny bags, seeds, IT equipment and accessories, vehicles, etc.] and works [very small value labor contracts for Development of Nurseries [52 nos.] in 26 clusters in 10 Districts covering 428 GPs. The total value of this spend is approximately 1.2 % of the Bank loan. Payment made by PMU/HPFD for these contracts following World Bank procurement procedures during the 12 months prior to the tentative Loan signing date shall be eligible for retroactive financing. Record Keeping. All records pertaining to award of tenders/selection of consultants, including tender notification/advertisement, register pertaining to sale and receipt of bids, bid/proposal opening minutes, bid/technical and financial evaluation reports, comparative statements, Goods, Receipt Note [GRN] and all correspondence pertaining to bid evaluation, communication sent to/with the Bank in the process, bid securities, and approval of invitation/evaluation of bids/proposals would be maintained by the PMU and at DPO/GP level. Contract Management. The PMU, HPFD will be responsible for overall procurement and contract management under the project. At the Centre, procurement staff will be responsible for contract monitoring and supervision of contracts awarded by PMU. At DPO level, contract monitoring and supervision will be done by technical staff at DPOs/APOs level [Agriculture, Animal Husbandry/Engineering staff of technical wing of DPO level and Forest Extension and Social Extension staff at APO level] to ensure timely delivery of quality outputs from the procurement contracts in the project areas. All payments will be made by DPOs for district and sub-district level procurements after receipt of Goods receipt Note [GRN]. Work Completion Certificates, etc. The Integrated Financial Management Information System [IFMIS] being developed under the Project will facilitate monitoring of various procurement activities in terms of physical and financial achievements on a monthly basis. The day to day monitoring of procurement activities will be done by APOs/DPOs at field level which will be updated in the online web-based system at district level and will be reviewed by PMU at the Centre. Complaint Handling Mechanism. A complaint handling mechanism to address procurement-related complaints under the Project will be developed and implemented by the PMU/DPOs to the satisfaction of the Bank. Upon receipt of complaints, immediate action would be initiated to acknowledge the complaint and to redress it within a reasonable timeframe. All complaints will be addressed at levels higher than the level at which the procurement process was undertaken, or the decision was taken. Any complaint received will also be forwarded to the Bank for information, and the Bank would be kept informed after the complaint is redressed. Leased Assets: Not Applicable Procurement of Secondhand Goods: Not Applicable Domestic Preference: The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement Thresholds and Prior Review Thresholds. The table below describes various procurement methods to be used for activities financed by the Loan. 8 Table 1: Procurement Thresholds Procurement approach and method Thresholds [US$ equivalent] Open International [Goods, IT, and >10 million Non-consulting services] – Request for Bids [RFB] Open National [Goods, IT, and Non- >100,000 and up to 10 million consulting services] – Request for Bids [RFB] National Request for Quotation Up to 100,000 [RFQ] – [Goods/Works/Non- consulting Services] Open International [Works] – >40 million Request for Bids [RFB] Open National [Works] - Request for >100,000 and up to 40 million Bids [RFB] Direct Selection With prior agreement, based on justification Framework Agreement For Goods/Works/Non-consulting services: According to paragraphs 6.57-6.59 of Section VI of the Regulations. For Consulting services: According to paragraph 7.33 of Section VII the Regulations. Force Account In accordance with paragraphs 6.54 and 6.55 of Section VI of the Procurement Regulations, and with prior agreement in Procurement plan with the Bank. Consulting Services [Firms] CQS: As per requirements of paragraphs 7.11 and 7.12 of Section VII of the Regulations. LCS, FBS: in justified cases QCBS, QBS: in all other packages Shortlist of National Consultants Up to 800,000 Procurement prior-review thresholds2. Based on the current procurement risk rating of ‘Moderate’, the World Bank will prior review the following contracts: (a) Works [including turnkey, supply and installation of plant and equipment and PPP]: All contracts more than US $15 million equivalent 2 Determination of whether a contract meets the prior review threshold is based on : (i) the total value of the contract, including all taxes and duties payable under the contract; (ii) a contract whose cost estimate was below the Bank’s prior review threshold is subject to prior review if the price of the lowest evaluated responsive bid (or, in the case of consulting services, the financial offer of the selected firm) exceeds such threshold at the bid evaluation stage; and (iii) in the case of a slice and package arrangement, the prior review threshold is determined based on the aggregate value of individual contracts to be awarded under such arrangement. 9 (b) Goods and Information Technology: All contracts > US $4 million equivalent (c) Non-consulting Services: All contracts > US $4 million equivalent (d) Consulting Services: Firms: All contracts >US $2 million equivalent (e) Consulting Services: Individuals: All contracts > US $400,000 equivalent (f) Direct Selection: The justification of Direct Selection for all contracts The above thresholds are for the initial 18-month implementation period. Based on the procurement performance of the project, these thresholds may be subsequently modified. Even for large-value post review cases, the inputs of the World Bank on technical specifications will be obtained by the project. Irrespective of the thresholds, Terms of Reference shall be prior reviewed by Bank. The prior review thresholds will also be indicated in the Procurement Plan. The Procurement Plan will be subsequently updated annually [or at any other time if required] and will reflect any change in the prior review thresholds. The details of National Procurement Procedures are outlined in the Procurement Plan. Prior review contracts. In the case of contracts subject to prior review, PMU, HPFD/DPOs will seek the World Bank’s no objection before granting/agreeing to: [a] an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; [b] any substantial modification of the scope of Works, goods, IT system; non-consulting services, or consulting services and other significant changes to the terms and conditions of the contract; [c] any variation order or amendment [except in cases of extreme urgency] that, singly or combined with all variation orders or amendments previously issued, increases the original contract amount by more than 15 percent; and [d] the proposed termination of the contract. Complaints received in all prior review cases shall be sent to Bank for review and the response to the complaint in such cases, shall be cleared with the Bank. Complaints with allegations of fraud and corruption, shall be shared with Bank, irrespective of the thresholds. Disclosure of procurement information. The following documents shall be disclosed on the project/state websites: [a] Procurement Plan and its updates; [b] an invitation for bids for procurement of Works, Goods, IT system procurement and non-consulting services; [c] request for expression of interest for selection/hiring of consulting services; [d] contract awards of Works, Goods, IT system procurement and non-consulting services procured following international and national procedures; [e] a list of contracts/purchase orders placed following RFQ [Request for Quotation] procedures on a quarterly basis; [f] a list of contracts following direct contracting [DC] on a quarterly basis; [g] an annual financial and physical progress report of all contracts; and [h] an action taken report on the complaints received on a quarterly basis. The following details shall be sent to the World Bank for publishing on the United Nations Development Business and the World Bank external website: [a] Specific Procurement Notice [i.e., invitation for bids] for procurement of Works, Goods, IT system procurement and non-consulting services using open international procedures; [b] Requests for Expression of Interests above US $800,000; [c] contract award details of all procurement of Works, Goods, IT system procurement and non-consulting services using open international procedure; and [d] a list of contracts/purchase orders placed following DC procedures on a quarterly basis. Further, the implementing agency will also publish on their websites any information required under the provisions of ‘suo moto’ disclosure as specified by the Right to Information Act. 10 National Procurement Procedure Conditions. National competition for the procurement of Works, Goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: I. Only the model bidding documents for National Competitive Procurement [NCP] agreed with the GOI Task Force [and as amended for time to time], shall be used for bidding. II. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. III. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises or enterprises from any given State. IV. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. V. Government e-Marketplace [GeM] set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations [RFQ] method. VI. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. VII. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. VIII. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. IX. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. X. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social [including sexual exploitation and abuse and gender-based violence], health and safety [“ESHS”] risks and impacts. Oversight and Monitoring by the Bank. All contracts not covered under prior review by the Bank will be subject to post review during implementation support missions and/or special post review missions, including missions by consultants hired by the Bank. The Bank may conduct, at any time, Independent Procurement Reviews [IPRs] of all the contracts financed under the loan. High risk procurements, if any, will be identified for increased procurement and contract management support and indicated in the procurement plan. Bank team will provide additional due diligence and independent review of the contract performance of such identified procurements. 11 Procurement Review by the PMU, HPFD. Independent procurement post review [PPR] with reporting requirements and agreed with the Bank [As per Para 4 of Annex II of the Procurement Regulations] will be undertaken for the project for PMU’s own internal due diligence. PMU will hire PPR consultants as per Terms of Reference and reporting requirements agreed with the Bank to conduct PPR of PMU and DPOs on a half yearly basis. Other Special Selection Arrangements/Requirement Procurement by communities will be governed by the procedures outlined in the Community Operations Manual [COM] currently under preparation and in accordance with Paras 6.52 and 6.53 of Section VI of the Regulations. COM will be disclosed on the Project website. Procurement Plan as per STEP Tables: 12 PROCUREMENT India : Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2020-07-09 Revised Plan Date(s): (comma delineated, leave blank if 2023-08-11 none) Project ID: P165129 GPN Date: 2019-12-19 Project Name: Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh Loan / Credit No: / , IBRD / 90410 District Project Office, Kullu, Himachal Pradesh Forestry Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-DPO, KULLU-159567-CW- RFQ / Work regarding Develo Component 1. Sustainable L pment of Chutti Bihal Nurser Request for Quota Single Stage - One E 2020-03-1 / and and Water Resource Ma Post Limited 5,418.00 5,148.13 Completed 2020-02-17 2020-01-27 2020-03-03 2020-02-12 y in Shamshi unit has been a tions nvelope 5 nagement warded to Sh. Mahender Sing h S/o Devi Ram, Village Thar ash PO Hurla. IN-DPO, KULLU-159568-CW- RFQ / Work regarding Develo Component 1. Sustainable L pment of Sajla Nursery of Na Request for Quota Single Stage - One E 2020-03-1 / and and Water Resource Ma Post Limited 4,895.00 4,650.34 Completed 2020-02-17 2020-01-27 2020-02-29 2020-02-12 ggar unit-II has been awarde tions nvelope 5 nagement d to Sh. Trilok Singh S/o Khim i Ram, Village Malahar PO Se obag, Teh & District Kullu. IN-DPO, KULLU-159571-CW- RFQ / Work regarding Develo pment of Dhungrugad Nurser Component 1. Sustainable L Request for Quota Single Stage - One E 2020-03-1 y in Banjar unit-I has been a / and and Water Resource Ma Post Limited 4,266.00 4,039.53 Completed 2020-02-17 2020-01-27 2020-02-29 2020-02-12 tions nvelope 5 warded to Sh. Goverdhan Du nagement tt S/o Devi Ram, Village Bom ul, PO Plach, Tehsil Banjar Di stt. Kullu. IN-DPO, KULLU-179766-CW- Component 1. Sustainable L RFQ / contour trenching out s Request for Quota Single Stage - One E 2021-03-1 IBRD / 90410 and and Water Resource Ma Post Limited 38,000.00 2,286.11 Completed 2020-07-31 2021-02-05 2020-11-19 2021-03-03 ide the plantations ares for w tions nvelope 5 nagement ater conservation and soil co nservation IN-DPO, KULLU-179773-CW- Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-1 RFQ / Grass seed sowingin pl IBRD / 90410 and and Water Resource Ma Post Limited 18,450.00 798.92 Completed 2020-07-31 2021-02-05 2020-11-28 2021-03-03 tions nvelope 5 antations (CT+non plantation nagement areas IN-DPO, KULLU-179850-CW- Component 1. Sustainable L Request for Quota Single Stage - One E 2021-06-0 IBRD / 90410 Post Limited 36,000.00 0.00 Signed 2021-03-06 2021-03-25 2021-04-10 2021-04-30 RFQ / Maintenance of 6 nos n and and Water Resource Ma tions nvelope 9 ursery nagement IN-DPO, KULLU-179830-CW- Component 1. Sustainable L RFQ / Development of Nurser Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 21,500.00 0.00 Canceled 2020-08-06 2020-10-01 y 3No for raising 375000plan tions nvelope 0 nagement ts and grass turfts IN-DPO, KULLU-179695-CW- Component 1. Sustainable L RFQ / Maintenance of three n Request for Quota Single Stage - One E 2021-02-0 IBRD / 90410 and and Water Resource Ma Post Limited 17,100.00 9.35 Completed 2020-06-17 2020-04-18 2020-08-12 2020-09-10 urseries one in each unit duri tions nvelope 8 nagement ng the current year IN-DPO, KULLU-179840-CW- Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-1 RFQ / Raising of 750000 plan IBRD / 90410 and and Water Resource Ma Post Limited 86,000.00 21,943.89 Completed 2020-08-06 2021-02-05 2020-11-09 2021-03-03 tions nvelope 5 ts in three new nurseries nagement IN-DPO, KULLU-179717-CW- Component 1. Sustainable L Request for Quota Single Stage - One E 2021-04-1 RFQ / Contour trenching in pl IBRD / 90410 and and Water Resource Ma Post Limited 40,000.00 2,329.23 Completed 2020-08-31 2021-02-05 2020-12-29 2021-03-03 tions nvelope 1 antation areas including gras nagement s seedlings IN-DPO, KULLU-179687-CW- Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-3 RFQ / Dev. and raising of pla IBRD / 90410 and and Water Resource Ma Post Limited 35,925.00 30,403.08 Completed 2020-10-14 2020-02-27 2020-12-09 2020-03-14 tions nvelope 1 nts in three nurseries nagement IN-DPO, KULLU-179783-CW- Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-1 RFQ / Planting grass turfts in IBRD / 90410 and and Water Resource Ma Post Limited 18,000.00 807.69 Completed 2020-07-31 2021-02-05 2020-11-28 2021-03-03 tions nvelope 5 plantations along DLT nagement IN-DPO, KULLU-179713-CW- Component 1. Sustainable L RFQ / Enrichment planting ov Request for Quota Single Stage - One E 2021-03-1 IBRD / 90410 and and Water Resource Ma Post Limited 82,000.00 7,010.63 Completed 2020-07-31 2021-05-11 2020-11-28 2021-02-03 er 82ha ,planting about 400 tions nvelope 5 nagement plants/Ha in medium density forest IN-DPO, KULLU-179704-CW- RFQ / Planting and fencing w ork along DLT over 131Ha,2 ha in each Nallah. Cumulativ Component 1. Sustainable L Request for Quota Single Stage - One E 2021-04-1 e value of this activity involv IBRD / 90410 and and Water Resource Ma Post Limited 99,000.00 65,764.85 Completed 2020-12-02 2020-11-05 2021-01-03 2021-02-20 tions nvelope 8 es multiple contracts based o nagement n low value and small minor l abor works. In addition geogr aphical conditions and terrai n are also different. IN-DPO, KULLU-179709-CW- RFQ / Reafforestation plantin g in open forest 800 plants/H Component 1. Sustainable L a (110 Ha.). Cumulative valu Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 138,000.00 64,970.02 Completed 2020-12-03 2020-11-05 2020-12-28 2021-02-19 e of this activity involves mul tions nvelope 1 nagement tiple contracts based on low value and small minor labor works. In addition geographic al conditions and terrain are also different. IN-DPO, KULLU-217248-CW- Component 1. Sustainable L RFQ / Raising of Nursery plan Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 15,000.00 1,362.88 Completed 2021-02-07 2022-01-13 2021-02-27 2022-02-01 ts in existing Nurseries durin tions nvelope 1 nagement g the year 2020-21 for planti ng in 20221-22 (P-II) IN-DPO, KULLU-236973-CW- RFQ / New Plantation along D Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 rainage Line 30 ha. (1100 Plt IBRD / 90410 and and Water Resource Ma Post Open - National 75,000.00 27,121.57 Completed 2021-07-29 2021-08-25 2022-01-25 tions nvelope or explanation) 1 s. per ha.), in three units of t nagement his Division for the current ye ar 2021-22. Page 1 IN-DPO, KULLU-236975-CW- RFQ / New Re-afforestation pl Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 antation 75 ha. (800 Plts. pe IBRD / 90410 and and Water Resource Ma Post Open - National 97,000.00 57,877.32 Completed 2021-07-30 2021-08-28 2022-01-25 tions nvelope or explanation) 1 r ha.), in three units of this Di nagement vision for the current year 20 21-22. IN-DPO, KULLU-236976-CW- RFQ / New Plantation Enrich Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2022-03-3 ment 54 ha. (400 Plts. per ha IBRD / 90410 and and Water Resource Ma Post Open - National 60,000.00 0.00 2021-07-29 2021-08-28 tions nvelope or explanation) mentation 1 .), in three units of this Divisi nagement on for the current year 2021- 22 IN-DPO, KULLU-237148-CW- RFQ / 1st year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 under Drainage Line plantati IBRD / 90410 and and Water Resource Ma Post Open - National 7,000.00 5,153.90 Completed 2021-07-29 2021-08-24 2022-01-09 tions nvelope or explanation) 1 on 40 ha. , in three units of t nagement his Division for the current ye ar 2021-22. IN-DPO, KULLU-237149-CW- RFQ / 1st year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 under Re-afforestation planta IBRD / 90410 and and Water Resource Ma Post Open - National 10,000.00 6,021.70 Completed 2021-07-29 2021-08-25 2022-01-09 tions nvelope or explanation) 1 tion 68 ha. , in three units of nagement this Division for the current y ear 2021-22. IN-DPO, KULLU-237150-CW- RFQ / 1st year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 under Enrichment plantation IBRD / 90410 and and Water Resource Ma Post Open - National 600.00 469.67 Completed 2021-07-29 2021-08-24 2021-12-29 tions nvelope or explanation) 1 9 ha. in three units of this Di nagement vision for the current year 20 21-22. IN-DPO, KULLU-237153-CW- Component 1. Sustainable L RFQ / Contour trenching in Pl Request for Quota Single Stage - One E Other (with field f 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 23,000.00 5,888.98 Completed 2021-07-29 2021-08-24 2022-02-19 antation areas 100 ha. in thr tions nvelope or explanation) 1 nagement ee units of this Division for th e current year 2021-22. IN-DPO, KULLU-237161-CW- RFQ / Contour trenching in O Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 ut side Plantation areas 60 h IBRD / 90410 and and Water Resource Ma Post Open - National 11,000.00 1,908.82 Completed 2021-07-29 2021-08-25 2022-02-08 tions nvelope or explanation) 1 a. in three units of this Divisi nagement on for the current year 2021- 22. IN-DPO, KULLU-237163-CW- RFQ / Grass seedling plantati Component 1. Sustainable L on (Re-afforestation + enrich Request for Quota Single Stage - One E Other (with field f 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 5,000.00 1,908.82 Completed 2021-07-29 2021-08-24 2022-02-08 ment + CT outside Plantation tions nvelope or explanation) 1 nagement ) 100 ha. in three units of thi s Division for the current yea r 2021-22. IN-DPO, KULLU-237165-CW- RFQ / Grass sowing in Draina Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 ge Line Treatment 40 ha. in t IBRD / 90410 and and Water Resource Ma Post Open - National 6,500.00 4,706.96 Completed 2021-07-29 2021-08-26 2022-02-08 tions nvelope or explanation) 1 hree units of this Division for nagement the current year 2021-22. IN-DPO, KULLU-237170-CW- Component 1. Sustainable L RFQ / Dry Stone Check Barrie Request for Quota Single Stage - One E Other (with field f 2022-04-0 IBRD / 90410 and and Water Resource Ma Post Open - National 70,000.00 58,027.13 Completed 2021-08-02 2021-08-27 2022-03-01 rs 1500 Cum in three units of tions nvelope or explanation) 7 nagement this Division for the current y ear 2021-22. IN-DPO, KULLU-237172-CW- Component 1. Sustainable L RFQ / Crate Wire Check Barri Request for Quota Single Stage - One E Other (with field f 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 60,000.00 54,143.38 Completed 2021-08-02 2021-08-27 2022-03-03 ers 1200 Cum in three units tions nvelope or explanation) 1 nagement of this Division for the curren t year 2021-22. IN-DPO, KULLU-237179-CW- Component 1. Sustainable L RFQ / Construction of Ponds i Request for Quota Single Stage - One E Other (with field f Under Imple 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 42,000.00 0.00 2021-07-29 2021-08-24 n three units of this Division f tions nvelope or explanation) mentation 1 nagement or the current year 2021-22. IN-DPO, KULLU-237192-CW- Component 1. Sustainable L RFQ / Construction of Foot Br Request for Quota Single Stage - One E Other (with field f 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 90,000.00 17,526.83 Completed 2021-07-28 2021-08-27 2022-02-01 idges in three units of this Di tions nvelope or explanation) 1 nagement vision for the current year 20 21-22. IN-DPO, KULLU-237180-CW- RFQ / Cement Concrete Wate Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 r Harvesting Structure . in th IBRD / 90410 and and Water Resource Ma Post Open - National 43,000.00 4,550.79 Completed 2022-01-29 2022-02-28 2022-02-01 tions nvelope or explanation) 1 ree units of this Division for t nagement he current year 2021-22. IN-DPO, KULLU-273185-CW- RFQ / Construction of two n Component 1. Sustainable L umber RCC Tanks for Lift irri Request for Quota Single Stage - One E Other (with field f 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 15,000.00 7,776.72 Completed 2022-01-28 2022-02-17 2022-03-06 gation schemes in Shamshi u tions nvelope or explanation) 1 nagement nit of this division including l aying 0f GI pipes and installa tion of hydraulic pump motor . IN-DPO, KULLU-273189-CW- Component 1. Sustainable L RFQ / Construction of four nu Request for Quota Single Stage - One E Other (with field f 2022-03-2 IBRD / 90410 and and Water Resource Ma Post Open - National 21,000.00 131,722.42 Completed 2022-01-28 2022-02-17 2022-03-06 mber RCC tanks for gravity ir tions nvelope or explanation) 0 nagement rigation schemes including la ying of HDPE pipes. IN-DPO, KULLU-273228-CW- Component 1. Sustainable L RFQ / construction of crate wi Request for Quota Single Stage - One E Other (with field f 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 4,000.00 3,387.80 Completed 2022-01-28 2022-02-19 2022-03-03 re check barrier over Hurcha tions nvelope or explanation) 1 nagement Nallah in Shamshi unit IN-DPO, KULLU-287478-CW- RFQ / Nursery Seedling Produ ction in 6 Nurseries of 3 APO Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-03-1 units of this Division meet th IBRD / 90410 and and Water Resource Ma Post Open - National 7,000.00 0.00 2022-08-20 2022-09-19 tions nvelope or explanation) lementation 5 e requirement of Plants for m nagement aintenance of Plantation for t he F.Y. 2022-23. Multiple sm all contracts. IN-DPO, KULLU-287481-CW- Component 1. Sustainable L RFQ / Maintenance of 6 Nurs Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-3 IBRD / 90410 and and Water Resource Ma Post Open - National 20,000.00 0.00 2022-04-09 2022-05-04 eries in three units of this Di tions nvelope or explanation) mentation 1 nagement vision for the F.Y. 2022-23 m ultiple small contracts. Page 2 IN-DPO, KULLU-287488-CW- RFQ / Construction of Cemen Component 1. Sustainable L t Concrete Check Barriers in Request for Quota Single Stage - One E Other (with field f 2022-12-1 IBRD / 90410 and and Water Resource Ma Post Open - National 20,000.00 0.00 Canceled 2022-04-20 2022-06-16 three units of this Division at tions nvelope or explanation) 3 nagement different locations, comprisin g of multiple small contracts for F.Y. 2022-23. IN-DPO, KULLU-293963-CW- RFQ / This activity pertains to activity reference No. IN-DPO , Kullu-237182-CW-RFQ for Pr Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-12-0 imary Water Distribution (Pro IBRD / 90410 and and Water Resource Ma Post Open - National 25,000.00 6,179.97 Completed 2022-05-19 2022-06-12 2022-07-02 tions nvelope or explanation) 9 curement of G.I. Pipes & Pum nagement ps for Lift Irrigation Schemes ) of this Division for the year 2021-22, requiring RE-TENDE RING for 2022-23. IN-DPO, KULLU-287486-CW- RFQ / Construction of Dry Sto ne Check Barriers in three un its of this Division at different Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-1 locations, comprising of multi IBRD / 90410 and and Water Resource Ma Post Open - National 150,000.00 0.00 2022-06-20 2022-08-15 tions nvelope or explanation) mentation 1 ple small contracts for F.Y. 2 nagement 022-23.The Cumulative valu e of this activity involves mul tiple contracts of low value ( <7000 US$ each) IN-DPO, KULLU-287487-CW- RFQ / Construction of Crate Wire Check Barriers in three Component 1. Sustainable L units of this Division at differ Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-02-1 IBRD / 90410 and and Water Resource Ma Post Open - National 152,000.00 0.00 2022-06-20 2022-08-15 ent locations, comprising of tions nvelope or explanation) lementation 1 nagement multiple small contracts for F .Y. 2022-23.Cumulative value of this activity involves multi ple contracts of low value (< 7000 US$ each) IN-DPO, KULLU-293962-CW- RFQ / This activity pertains to activity reference No. IN-DPO Component 1. Sustainable L , Kullu-237181-CW-RFQ for Pr Request for Quota Single Stage - One E Other (with field f 2023-01-1 IBRD / 90410 and and Water Resource Ma Post Open - National 15,000.00 3,047.42 Completed 2022-06-19 2022-07-14 2022-08-18 imary Water Distribution (Pro tions nvelope or explanation) 0 nagement curement of HDPE Pipes for Gravity Schemes ) of this Div ision for the year 2021-22, re quiring RE-TENDERING for 20 22-23.. IN-DPO, KULLU-305501-CW- RFQ / New Reafforestation Pl antation for monsoon season Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-3 25 ha. (800 Plts. per ha.), in IBRD / 90410 and and Water Resource Ma Post Open - National 40,000.00 0.00 2022-08-02 2022-08-31 tions nvelope or explanation) mentation 1 three units of this Division. It nagement involves multiple small contr acts in different locations for the year 2022-23. IN-DPO, KULLU-305504-CW- RFQ / Drainage Line Treatme Component 1. Sustainable L nt Plantation for monsoon se Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-3 IBRD / 90410 and and Water Resource Ma Post Open - National 23,000.00 0.00 2022-08-02 2022-08-28 ason 10 ha. in three units of tions nvelope or explanation) mentation 1 nagement this Division. It involves multi ple small contracts in differe nt locations for the year 202 2-23. IN-DPO, KULLU-305506-CW- RFQ / New Enrichment Planta tion for monsoon season 26 Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-3 ha. (800 Plts. per ha.), in thr IBRD / 90410 and and Water Resource Ma Post Open - National 30,000.00 0.00 2022-08-02 2022-08-28 tions nvelope or explanation) mentation 1 ee units of this Division. It inv nagement olves multiple small contract s in different locations for the year 2022-23. IN-DPO, KULLU-305510-CW- RFQ / 1st year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-3 under Reafforestation planta IBRD / 90410 and and Water Resource Ma Post Open - National 12,000.00 0.00 2022-08-02 2022-08-30 tions nvelope or explanation) mentation 1 tion 74 ha. in three units of t nagement his Division for the current ye ar 2022-23. IN-DPO, KULLU-305516-CW- RFQ / 1st year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-3 under Drainage Line plantati IBRD / 90410 and and Water Resource Ma Post Open - National 6,500.00 0.00 2022-08-03 2022-08-28 tions nvelope or explanation) mentation 1 on 30 ha. , in three units of t nagement his Division for the current ye ar 2022-23. IN-DPO, KULLU-305518-CW- RFQ / 1st year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-01-3 under Enrichment plantation IBRD / 90410 and and Water Resource Ma Post Open - National 7,000.00 0.00 2022-08-04 2022-08-29 tions nvelope or explanation) lementation 1 86 ha. , in three units of this nagement Division for the current year 2022-23 IN-DPO, KULLU-305539-CW- RFQ / Renovation of Water B Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-03-1 uries15 No (Spring Well) in th IBRD / 90410 and and Water Resource Ma Post Open - National 30,000.00 0.00 Canceled 2022-08-12 2022-09-09 tions nvelope or explanation) 5 ree units of this Division for t nagement he Financial Year 2022-23. IN-DPO, KULLU-179845-CW- Component 1. Sustainable L Request for Quota Single Stage - One E 2021-06-3 IBRD / 90410 Post Limited 23,300.00 0.00 Canceled 2020-11-06 2021-01-01 RFQ / C/O village ponds 9No and and Water Resource Ma tions nvelope 0 nagement IN-DPO, KULLU-179789-CW- Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-1 IBRD / 90410 Post Limited 10,300.00 0.00 Canceled 2020-08-11 2020-12-09 RFQ / vegetative check barri and and Water Resource Ma tions nvelope 5 ers in DLT nagement IN-DPO, KULLU-179806-CW- RFQ / Crate wire check barrie rs. Cumulative value of this a Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-1 ctivity involves multiple contr IBRD / 90410 and and Water Resource Ma Post Limited 206,743.00 0.00 Canceled 2020-12-15 2021-01-07 tions nvelope 2 acts based on low value and nagement small minor labor works. In a ddition geographical conditio ns and terrain are also differ ent. IN-DPO, KULLU-179800-CW- RFQ / Dry stone Check barrie rs. Cumulative value of this a Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-2 ctivity involves multiple contr IBRD / 90410 and and Water Resource Ma Post Limited 111,051.00 0.00 Canceled 2020-12-15 2021-01-16 tions nvelope 0 acts based on low value and nagement small minor labor works. In a ddition geographical conditio ns and terrain are also differ ent. Page 3 IN-DPO, KULLU-237193-CW- RFQ / Roof Rain Water Harve Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 sting Structure (Individual) . i IBRD / 90410 and and Water Resource Ma Post Open - National 55,000.00 0.00 Canceled 2021-07-29 2021-08-24 tions nvelope or explanation) 1 n three units of this Division f nagement or the current year 2021-22 IN-DPO, KULLU-237178-CW- Component 1. Sustainable L RFQ / Plantation around the Request for Quota Single Stage - One E Other (with field f 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 2,200.00 0.00 Canceled 2021-07-29 2021-08-26 Bouries 2 ha. in three units of tions nvelope or explanation) 1 nagement this Division for the current y ear 2021-22. IN-DPO, KULLU-237168-CW- Component 1. Sustainable L RFQ / Vegetative Check Barri Request for Quota Single Stage - One E Other (with field f 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 4,500.00 0.00 Canceled 2021-07-29 2021-08-25 ers 1500 Rmt. in three units tions nvelope or explanation) 1 nagement of this Division for the curren t year 2021-22. IN-DPO, KULLU-237177-CW- Component 1. Sustainable L RFQ / Renovation of Water B Request for Quota Single Stage - One E Other (with field f 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 11,000.00 0.00 Canceled 2021-07-28 2021-08-24 auries 6 no. in three units of tions nvelope or explanation) 1 nagement this Division for the current y ear 2021-22. IN-DPO, KULLU-237310-CW- Component 1. Sustainable L RFQ / Repair of Irrigation Cha Request for Quota Single Stage - One E Other (with field f 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 15,000.00 0.00 Canceled 2021-07-29 2021-08-26 nnels/Kuhals in three units tions nvelope or explanation) 1 nagement of this Division for the curren t year 2021-22. IN-DPO, KULLU-237175-CW- Component 1. Sustainable L RFQ / Cement Concrete Che Request for Quota Single Stage - One E Other (with field f 2022-04-2 IBRD / 90410 and and Water Resource Ma Post Open - National 70,000.00 0.00 Canceled 2021-07-31 2021-08-28 ck Barriers 500 Cum. in three tions nvelope or explanation) 4 nagement units of this Division for the c urrent year 2021-22. IN-DPO, KULLU-242344-CW- Component 1. Sustainable L RFB / Construction of Ropew Request for Quota Single Stage - One E Other (with field f 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 22,000.00 0.00 Canceled 2021-08-02 2021-09-08 ays in three units of this Divi tions nvelope or explanation) 1 nagement sion for the current year 202 1-22. IN-DPO, KULLU-242362-CW- RFB / Construction of Roof Ra Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 in Water Harvesting Structur IBRD / 90410 and and Water Resource Ma Post Open - National 20,000.00 0.00 Canceled 2021-08-02 2021-09-06 tions nvelope or explanation) 1 e for Community in three uni nagement ts of this Division for the curr ent year 2021-22 IN-DPO, KULLU-237182-CW- RFQ / Primary Water Distribu Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 tion (G.I. Pipes & Pumps for li IBRD / 90410 and and Water Resource Ma Post Open - National 25,000.00 0.00 Canceled 2021-12-01 2022-02-28 tions nvelope or explanation) 1 fting scheme) in three units o nagement f this Division for the current year 2021-22. IN-DPO, KULLU-237181-CW- RFQ / Primary Water Distribu Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 tion (HDPE Pipes for Gravity IBRD / 90410 and and Water Resource Ma Post Open - National 15,000.00 0.00 Canceled 2021-11-20 2021-12-13 tions nvelope or explanation) 1 Schemes ) in three units of t nagement his Division for the current ye ar 2021-22. IN-DPO, KULLU-314240-CW- RFQ / linking & c/o Secondary WHS with primary source b Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-05-1 y HDPE pipes and pumps, for IBRD / 90410 cultural Productivity and Val Post Open - National 40,000.00 0.00 2022-09-25 2022-11-20 tions nvelope or explanation) lementation 9 minor lift irrigation schemes, ue Addition in three units of this division. It involves multiple contracts of low value during the year 2022-23 IN-DPO, KULLU-315117-CW- RFQ / Maintenance of of six n Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-05-2 urseries of this division from IBRD / 90410 and and Water Resource Ma Post Open - National 12,000.00 0.00 2022-10-05 2022-11-30 tions nvelope or explanation) mentation 9 Sept 2022 to March 2023. It i nagement nvolves multiple contract of s mall value. IN-DPO, KULLU-314248-CW- RFQ / Grass seed sowing on t he berms of contour trenches Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-03-2 inside plantations ( 42 Ha) in IBRD / 90410 and and Water Resource Ma Post Open - National 2,000.00 0.00 Canceled 2023-01-01 2023-02-05 2023-02-04 tions nvelope or explanation) 1 different locations of this divi nagement sion during winter season of 2022-23. It involves multiple contracts of small values. IN-DPO, KULLU-314237-CW- RFQ / linking & construction of Secondary WHS, with prim Component 2. Improved Agri ary source by HDPE pipes for Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 IBRD / 90410 cultural Productivity and Val Post Open - National 95,000.00 0.00 2023-01-01 2023-01-06 2023-02-15 minor gravity schemes at dif tions nvelope or explanation) mentation 5 ue Addition ferent locations in various G Ps of this division. It involves multiple contracts of small va lue during the year 2022-23 IN-DPO, KULLU-314241-CW- RFQ / Construction of Ponds f Component 1. Sustainable L or Water harvesting in differe Request for Quota Single Stage - One E Other (with field f 2023-06-1 IBRD / 90410 and and Water Resource Ma Post Open - National 30,000.00 0.00 Canceled 2023-01-02 2023-02-16 nt locations of this division. It tions nvelope or explanation) 6 nagement involves multiple contracts of small value for the year 2022 -23 IN-DPO, KULLU-314243-CW- RFQ / Raising of Re- Afforesta Component 1. Sustainable L ion plantations over 54 Ha of Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 IBRD / 90410 and and Water Resource Ma Post Open - National 80,000.00 0.00 2023-01-01 2022-12-22 2023-02-18 forest lands, during winter of tions nvelope or explanation) mentation 8 nagement 2022-23, in different location s of this division. It involves multiple contracts of low valu e IN-DPO, KULLU-314245-CW- RFQ / Raising of15 Ha Enrich Component 1. Sustainable L ment plantations in different Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-2 IBRD / 90410 and and Water Resource Ma Post Open - National 20,000.00 0.00 2023-01-02 2022-12-22 2023-02-21 locations of this division duri tions nvelope or explanation) mentation 1 nagement ng winter season of 2022-23. It involves multiple contracts of low value IN-DPO, KULLU-314246-CW- RFQ / Construction of contour trenches inside plantations( Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-06-1 42ha ) in different locations o IBRD / 90410 and and Water Resource Ma Post Open - National 10,000.00 0.00 Canceled 2022-12-31 2023-02-05 2023-02-19 tions nvelope or explanation) 9 f this division during the year nagement 2022-23 winter season. It inv olves multiple contracts of lo w value. Page 4 IN-DPO, KULLU-315118-CW- RFQ / C/O foot bridges in diff Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-2 erent locations of this divisio IBRD / 90410 cultural Productivity and Val Post Open - National 95,000.00 0.00 2022-12-30 2022-12-22 2023-02-27 tions nvelope or explanation) mentation 7 n during 2022-23 . It involves ue Addition multiple contracts of small va lue. IN-DPO, KULLU-305541-CW- RFQ / Construction of Sump Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-07-1 Wells (Intake Structure) for M IBRD / 90410 and and Water Resource Ma Post Open - National 2,500.00 0.00 Signed 2023-01-02 2022-12-22 2023-02-01 2023-01-12 tions nvelope or explanation) 1 inor Lift Irrigation Scheme in nagement GP Dhanogi APO Shamshi 1 No. for the F.Y. 2022-23. IN-DPO, KULLU-305533-CW- RFQ / 2nd year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-08-1 under Enrichment plantation IBRD / 90410 and and Water Resource Ma Post Open - National 500.00 0.00 2023-01-01 2022-12-22 2023-01-28 tions nvelope or explanation) mentation 2 9 ha. , in three units of this D nagement ivision for the current year 2 022-23. IN-DPO, KULLU-305529-CW- RFQ / 2nd year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-08-3 under Reafforestation plantat IBRD / 90410 and and Water Resource Ma Post Open - National 4,000.00 0.00 2023-01-02 2022-12-22 2023-01-30 tions nvelope or explanation) mentation 0 ion 68 ha. in three units of th nagement is Division for the current yea r 2022-23.. IN-DPO, KULLU-305528-CW- RFQ / 2nd year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-08-1 under DLT plantation 40 ha. , IBRD / 90410 and and Water Resource Ma Post Open - National 5,200.00 0.00 2023-01-02 2022-12-22 2023-01-31 tions nvelope or explanation) mentation 5 in three units of this Division nagement for the current year 2022-23. IN-DPO, KULLU-287489-CW- RFQ / Construction of Cemen t Concrete Primary Water Har Component 1. Sustainable L vesting Structure/Cement co Request for Quota Single Stage - One E Other (with field f Under Imple 2023-08-3 IBRD / 90410 and and Water Resource Ma Post Open - National 80,000.00 0.00 2023-01-03 2023-01-06 2023-03-03 ncrete Gravity Check Dams i tions nvelope or explanation) mentation 0 nagement n three units of this Division at different locations, compri sing of multiple small contrac ts for F.Y. 2022-23. IN-DPO, KULLU-287670-CW- RFQ / Construction of Ponds ( Component 1. Sustainable L Manual excavation) in three Request for Quota Single Stage - One E Other (with field f 2023-10-2 IBRD / 90410 and and Water Resource Ma Post Open - National 5,000.00 0.00 Canceled 2023-01-02 2023-02-19 units of this Division at differ tions nvelope or explanation) 1 nagement ent locations, comprising of multiple small contracts for F .Y. 2022-23. IN-DPO, KULLU-334232-CW- RFQ / Construction of Dry Sto ne Check Barriers in G.P. Sac Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-04-2 hani, Talara, Bhallan-II and R IBRD / 90410 and and Water Resource Ma Post Open - National 14,000.00 0.00 2023-01-21 2023-01-23 2023-02-19 tions nvelope or explanation) mentation 0 ote under APO IDP unit Sham nagement shi of this Division at differen t locations, comprising of mul tiple small contracts for F.Y. 2022-23. IN-DPO, KULLU-339055-CW- RFQ / Construction of Dry. St one Check Barrier over Duar a Nallah near Village Panjbe Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-05-3 ed in GP Sachani and Shogi N IBRD / 90410 and and Water Resource Ma Post Open - National 7,500.00 0.00 2023-02-11 2023-03-11 tions nvelope or explanation) lementation 1 allah in GP Talara under APO nagement IDP unit Shamshi of this Divis ion at different locations, co mprising of multiple small co ntracts for F.Y. 2022-23 IN-DPO, KULLU-363846-CW- RFQ / Maintenance of 5 Nurs Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-07-3 eries in three units of this off IBRD / 90410 and and Water Resource Ma Post Open - National 3,000.00 0.00 2023-06-03 2023-06-21 tions nvelope or explanation) lementation 1 ice for the month of June, 20 nagement 23 multiple small contracts f or the F.Y. 2023-24. IN-DPO, KULLU-363862-CW- RFQ / 1st year maintenance Component 1. Sustainable L under Re-afforestation planta Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 IBRD / 90410 and and Water Resource Ma Post Open - National 8,200.00 0.00 2023-06-24 2023-07-17 2023-07-20 tion 58ha. for monsoon seas tions nvelope or explanation) mentation 1 nagement on in three units of this Divisi on for the current year 2023- 24. IN-DPO, KULLU-363866-CW- RFQ / 1st year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 under along DLT plantation 6 IBRD / 90410 and and Water Resource Ma Post Open - National 1,300.00 0.00 2023-06-24 2023-07-17 2023-07-19 tions nvelope or explanation) mentation 1 ha. for monsoon season in th nagement ree units of this Division for t he current year 2023-24. IN-DPO, KULLU-363870-CW- RFQ / 1st year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 under Enrichment plantation IBRD / 90410 and and Water Resource Ma Post Open - National 2,600.00 0.00 2023-06-24 2023-07-17 2023-07-21 tions nvelope or explanation) mentation 1 32 ha. for monsoon season in nagement three units of this Division for the current year 2023-24 IN-DPO, KULLU-363876-CW- RFQ / 2nd year maintenance Component 1. Sustainable L under Re-afforestation planta Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 IBRD / 90410 and and Water Resource Ma Post Open - National 4,500.00 0.00 2023-06-25 2023-07-17 2023-07-19 tion 41ha. for monsoon seas tions nvelope or explanation) mentation 1 nagement on in three units of this Divisi on for the current year 2023- 24. IN-DPO, KULLU-363878-CW- RFQ / 2nd year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 under DLT plantation 16 ha. f IBRD / 90410 and and Water Resource Ma Post Open - National 2,400.00 0.00 2023-06-25 2023-07-17 2023-07-21 tions nvelope or explanation) mentation 1 or monsoon season in three nagement units of this Division for the c urrent year 2023-24 IN-DPO, KULLU-363881-CW- RFQ / 2nd year maintenance Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-3 under Enrichment plantation IBRD / 90410 and and Water Resource Ma Post Open - National 3,900.00 0.00 2023-06-26 2023-07-17 2023-07-22 tions nvelope or explanation) mentation 1 69 ha. for monsoon season in nagement three units of this Division for the current year 2023-24 IN-DPO, KULLU-369390-CW- RFQ / Maintenance of 5 Nurs eries i.e. Watering, weeding Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2024-03-3 & hoeing, shifting of plants et IBRD / 90410 and and Water Resource Ma Post Open - National 12,600.00 0.00 2023-07-15 2023-07-17 2023-08-05 tions nvelope or explanation) mentation 1 c. in three units of this office nagement for the month of July ,2023 to March, 2024 multiple small c ontracts for the F.Y. 2023-24. Page 5 IN-DPO, KULLU-369514-CW- RFQ / C/O Foot bridges in diff erent locations of this divisio Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-03-3 n ( GP Talogi, Pangan, Hallan, IBRD / 90410 cultural Productivity and Val Post Open - National 66,900.00 0.00 2023-07-22 2023-08-17 tions nvelope or explanation) lementation 1 Naggar, Bran, Bandrol, Dano ue Addition gi and Chheneur) during 202 3-24 . It involves multiple con tracts of small value. IN-DPO, KULLU-369517-CW- RFQ / Construction of Cemen t Concrete Primary Water Har Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-03-3 vesting Structure /Cement co IBRD / 90410 and and Water Resource Ma Post Open - National 5,000.00 0.00 2023-07-24 2023-08-24 tions nvelope or explanation) lementation 1 ncrete Check Dams in GP Fal nagement lan of Shamshi units of this D ivision at dat Jathang, compri sing of small contracts for F. Y. 2023-24. IN-DPO, KULLU-369522-CW- RFQ / linking & c/o Secondary WHS (MGI) with primary sour Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-03-3 ce by HDPE pipes , for minor IBRD / 90410 cultural Productivity and Val Post Open - National 22,000.00 0.00 2023-07-28 2023-08-30 tions nvelope or explanation) lementation 1 lift irrigation schemes of this ue Addition division. It involves multiple c ontracts of low value during t he year 2023-24 IN-DPO, KULLU-372626-CW- Component 1. Sustainable L RFQ / Construction of Vegeta Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-04-0 IBRD / 90410 and and Water Resource Ma Post Open - National 875.00 0.00 2023-09-17 2023-10-11 tive Check Barriers in Naggar tions nvelope or explanation) lementation 8 nagement units of this Division for F.Y. 2023-24. IN-DPO, KULLU-373604-CW- RFQ / Construction of Dry Sto Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-04-0 ne Check Barriers in three un IBRD / 90410 and and Water Resource Ma Post Open - National 75,500.00 0.00 2023-09-17 2023-10-12 tions nvelope or explanation) lementation 9 its Shamshi, Naggar & Banjar nagement of this Division for F.Y. 2023- 24. IN-DPO, KULLU-372640-CW- Component 1. Sustainable L RFQ / Construction of Crate Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-04-0 IBRD / 90410 and and Water Resource Ma Post Open - National 67,600.00 0.00 2023-09-16 2023-10-10 Wire Check Barriers in three tions nvelope or explanation) lementation 7 nagement units of this Division for the F .Y. 2023-24. IN-DPO, KULLU-372643-CW- RFQ / Construction of Cemen Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-03-2 t Concrete Check Barriers in IBRD / 90410 and and Water Resource Ma Post Open - National 43,600.00 0.00 2023-09-01 2023-09-30 tions nvelope or explanation) lementation 8 Banjar and Naggar units of th nagement is Division for the F.Y. 2023- 24. IN-DPO, KULLU-372644-CW- RFQ / Construction of Renova Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-03-3 tion of Water Bauries 20 No ( IBRD / 90410 and and Water Resource Ma Post Open - National 37,000.00 0.00 2023-09-03 2023-10-02 tions nvelope or explanation) lementation 1 Spring Well) in three units of nagement this Division for the F.Y. 2023 -24. IN-DPO, KULLU-372668-CW- Component 1. Sustainable L RFQ / Construction of Ponds ( Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-04-2 IBRD / 90410 and and Water Resource Ma Post Open - National 30,300.00 0.00 2023-10-04 2023-10-25 Manual excavation) in three tions nvelope or explanation) lementation 2 nagement units of this Division for the F .Y. 2023-24. IN-DPO, KULLU-372691-CW- RFQ / C/o of Sump Wells (Inta Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-03-3 ke Structure) 5No. for Minor IBRD / 90410 and and Water Resource Ma Post Open - National 13,300.00 0.00 2023-09-04 2023-09-29 tions nvelope or explanation) lementation 1 Lift Irrigation in three units of nagement this Division for the F.Y. 2023 -24. IN-DPO, KULLU-372699-CW- RFQ / Construction of CC Pri Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-04-0 mary Water Harvesting Struc IBRD / 90410 and and Water Resource Ma Post Open - National 35,250.00 0.00 2023-09-18 2023-10-10 tions nvelope or explanation) lementation 7 ture /CC Check Dams in thre nagement e units of this Division for the F.Y. 2023-24. IN-DPO, KULLU-372709-CW- RFQ / C/o Secondary WHS & l Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-04-1 inking with primary source fo IBRD / 90410 cultural Productivity and Val Post Open - National 98,000.00 0.00 2023-09-23 2023-10-14 tions nvelope or explanation) lementation 1 r Gravity Irrigation Scheme o ue Addition f this Division for the FY 2023 -24. IN-DPO, KULLU-372727-CW- RFQ / Construction of Second ary WHS 4 No. Lift Irrigation Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-04-1 Scheme & linking with primar IBRD / 90410 cultural Productivity and Val Post Open - National 20,000.00 0.00 2023-09-28 2023-10-21 tions nvelope or explanation) lementation 8 y source by HDPE/GI pipes in ue Addition APO unit Shamshi & Naggar of this division for the year 2 023-24. IN-DPO, KULLU-372732-CW- RFQ / C/o Lining of Traditiona Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-04-1 l Irrigation Channel/Kuhal of IBRD / 90410 cultural Productivity and Val Post Open - National 22,400.00 0.00 2023-09-20 2023-10-13 tions nvelope or explanation) lementation 0 2.5 Km in Naggar unit of this ue Addition Division for the F.Y. 2023-24. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DPO, KULLU-159376-GO- Component 1. Sustainable L Request for Quota Single Stage - One E RFQ / Procurement of bags fo IBRD / 90410 and and Water Resource Ma Post Limited 1,200.00 2,294.38 Completed 2020-10-16 2020-01-18 2020-12-11 2020-02-13 2021-06-09 2020-02-25 tions nvelope r raising plants in nursery 10 nagement qtls IN-DPO, KULLU-159566-GO- RFQ / Hot Dipped Coating IS: 4826-1968 Steel Barbed Wire for Fencing 12x14 SWG, 2 Str Component 1. Sustainable L Request for Quota Single Stage - One E and in 4 Barbs and 3-4 apart IBRD / 90410 and and Water Resource Ma Post Limited 1,142.00 89.54 Completed 2020-02-17 2020-01-18 2020-02-29 2020-02-13 2020-08-27 2020-02-22 tions nvelope without wooden spools confir nagement ming to ISI Specification 278- 1978 (Second Revision with a mendment No. 1 to 4 ISI Mar ked) & U-Nails made of 4 mm Wire. IN-DPO, KULLU-179681-GO- Component 1. Sustainable L Request for Quota Single Stage - One E RFQ / Procurement of Eucaly IBRD / 90410 and and Water Resource Ma Post Limited 675.00 0.00 Canceled 2020-07-12 2020-09-06 2021-03-31 tions nvelope ptus Fence post for fencing t nagement he New nurseries Page 6 IN-DPO, KULLU-179683-GO- Component 1. Sustainable L Request for Quota Single Stage - One E RFQ / Procurement of fence p IBRD / 90410 and and Water Resource Ma Post Limited 671.00 637.43 Completed 2020-06-17 2020-02-25 2020-08-12 2020-03-01 2021-02-08 2020-03-01 tions nvelope ost for nurseries nagement IN-DPO, KULLU-221140-GO- Component 2. Improved Agri Request for Quota Single Stage - One E RFQ / High Value Crops (Veg IBRD / 90410 cultural Productivity and Val Post Limited 2,500.00 300.64 Completed 2021-03-02 2021-03-25 2021-03-20 2021-03-26 2021-04-30 2021-04-27 tions nvelope etable) demonstration 30 No. ue Addition for F.Y. 2020-21. IN-DPO, KULLU-236979-GO- RFQ / Procurement of Barbed Component 1. Sustainable L Request for Quota Single Stage - One E Wire & U-nails for fencing of IBRD / 90410 and and Water Resource Ma Post Open - National 30,000.00 15,865.74 Completed 2021-07-28 2021-08-24 2021-09-12 2022-03-31 2021-10-03 tions nvelope new plantation 225 ha. in th nagement ree units of this Division for t he current year 2021-22. IN-DPO, KULLU-236983-GO- RFQ / Procurement of Woode Component 1. Sustainable L n Eucalyptus Fence Post for f Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 40,000.00 12,939.29 Completed 2021-07-29 2021-08-26 2021-09-12 2022-03-31 2021-11-21 encing of new plantation 184 tions nvelope nagement ha. in three units of this Divis ion for the current year 2021 -22. IN-DPO, KULLU-237183-GO- RFQ / Demonstration of CSA ( Climate Smart Agriculture) i. e. fodder demo. agronomic p Component 1. Sustainable L Request for Quota Single Stage - One E ractices, pest management,s IBRD / 90410 and and Water Resource Ma Post Open - National 30,000.00 3,860.89 Completed 2021-07-29 2021-08-25 2021-12-20 2022-03-31 2021-12-22 tions nvelope oil fertility management & ve nagement rmi composting etc. distributi on to farmers under three un its of this Division for the curr ent year 2021-22. IN-DPO, KULLU-237308-GO- RFQ / Nursery equipment's a nd machinery like HDPE Pipe, Component 1. Sustainable L HDPE Water Tanks, Sprinkler, Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 4,000.00 169.59 Completed 2021-08-17 2021-09-18 2021-09-08 2022-03-31 2021-09-08 Drip Irrigation System, Water tions nvelope nagement pumps, Water Canes, Nurser y Shades Net, Pesticides, Fun gicides & fertilizer for the cur rent year 2021-22 IN-DPO, KULLU-287671-GO- RFQ / On Farm Demonstratio n and promotion of CSA (Clim Component 1. Sustainable L ate Smart Agriculture) and Hi Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 3,000.00 0.00 Canceled 2022-04-15 2022-05-17 2023-03-15 gh Value Crop diversification tions nvelope nagement (Kharif & Rabi season) distrib ution to farmers under three units of this Division for the F .Y. 2022-23 IN-DPO, KULLU-237194-GO- Component 1. Sustainable L RFQ / Farmers Field Days 6 N Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 1,000.00 0.00 Canceled 2021-07-29 2021-08-25 2022-03-31 o. in three units of this Divisi tions nvelope nagement on for the current year 2021- 22. IN-DPO, KULLU-281246-GO- RFQ / Procurement of Life sa Component 1. Sustainable L Request for Quota Single Stage - One E ving multipurpose Medical Ki IBRD / 90410 and and Water Resource Ma Post Open - National 5,000.00 0.00 Canceled 2022-03-06 2022-04-03 2022-09-30 tions nvelope ts for nomads (Transhumant nagement & local shepherds ) of this Di vision. IN-DPO, KULLU-281239-GO- RFQ / This Procurement is for distribution of equipment's li Component 1. Sustainable L ke Tarpaulin, light weight Te Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 25,000.00 0.00 Canceled 2022-03-03 2022-04-13 2022-10-10 nt, sleeping bag, mat, Rucks tions nvelope nagement ack 65 ltr. capacity, solar mo bile charger 20 Wat with USB , to the transhumant and loc al shepherds under Tribal Act ion Plan. IN-DPO, KULLU-287672-GO- RFQ / Demonstration for Fod Component 1. Sustainable L der Augmentation to farmer Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 7,000.00 0.00 Canceled 2023-01-14 2023-02-27 2023-12-10 s under three units of this Di tions nvelope nagement vision for the F.Y. 2022-23. In volving procurement of seed s & others goods. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7