PROCUREMENT PLAN Project information: Solomon Islands; Pacific Islands Regional Oceanscape Program– Second Phase for Economic Recovery and Resilience (P177239) - Project Preparation Advance Project Implementation agency: Ministry of Fisheries and Marine Resources (MFMR) Date of the Procurement Plan: 1 November 2021 Period covered by this Procurement Plan: November 2021 – July 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP). Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable Interim Procurement Plan An interim plan approved by the World Bank for the period 1 Nov 2021. The Plan is for PMU staff costs and operational costs, and two consultancies, an international safeguards specialist and a short-term financial management specialist. The interim procurement plan has been approved for retroactive financing on November 1st, 2021. PPA Procurement Plan This Procurement Plan is proposed to start as soon as it is approved and funding received by the MFMR for PPA to be managed by the PMU. It is envisaged that all proposed activities would be executed between January 2022 till July 2022. SIG currently is experiencing revenue shortfalls precipitating in cash flow issues. In the event, that cash flow issues affect the funding of activities in the approved interim procurement plan, they will be financed by the PPA funds instead. Reimbursement to SIG will be made only for the activities actually financed by SIG. PMU will ensure that the reference number in both plans for the same activities will be the same. STEP for PPA has not been set up yet, however PMU will keep a numbering system to reflect each activity Direct Selection Rationale and Justification The direct selection method is the preferred procurement method for 6 of the consultancies positions for entirety of the PP period. This method is preferred for the following reasons; experience with PROP and the operating context, specialist technical knowledge and insight of MFMR and its priorities, core skills in project management, excellent performance of work undertaken under PROP I and consistency of approach in continuing work. Procurement Plan for PPA dated 1 November 2021 Cost Procurem Procureme Market Commence Re Implementi Activity Description Estimate ent nt Method approach Procureme f. ng Entity (US$) Category nt PMU Project Coordinator (costed in 1 MFMR 44,484.96 INDV Direct National Post Nov–Dec 21 the interim procurement plan) Design Preparation Consultant - Design Open Internationa 2 preparation work in collaboration with MFMR 40,000 INDV Post April 2022 Competitive l MFMR and other stakeholders PMU Procurement Officer (costed in 3 the approved Interim Procurement MFMR 11,661.26 INDV Direct National Post Nov –Dec 21 Plan) PMU Project Administrative & Financial Assistant (costed in the approved 4 MFMR 23,503.13 INDV Direct National Post Nov-Dec 21 Interim Procurement Plan as PMU Project Assistant) Short-term Financial Management Specialist (costed in the approved 5 MFMR 4,191.75 INDV Direct National Post April 22 Interim Procurement Plan as ST FM Consultant) ESF Safeguards Consultant – development of a social safeguards and environmental framework; training Internationa 6 MFMR staff and stakeholders MFMR 26,000 INDV Direct Post Nov-21 l (costed in the approved Interim Procurement Plan as Environmental and Social Safeguards Consultant) POM Consultant – development of the Open Internationa 7 Project Operations Manual (POM) and MFMR 18,000 INDV Post April 22 Competitive l training the PMU staff on the POM Monitoring and Evaluation Consultant – developing the M&E framework for the Open Internationa 8 Project and training the MFMR staff on MFMR 16,000 INDV Post April 22 Competitive l the framework data collection and reporting Civil Engineering Consultant – engineering quality assurance support Open Internationa 9 MFMR 20,000 INDV Post April 22 and advice for Noro civil works and Competitive l other upcoming civil work Procurement Consultant – procurement advice, training to the PMU and Open 10 MFMR 32,000 INDV National Post April 22 continuous advice and support on Competitive procurement activities. Legal Consultant – conduct legal Internationa 11 assessment on UNCLOS Article 73 MFMR 20,000 INDV Direct Post April 22 l compliance for Solomon Islands Internationa 12 Evaluation of the Observer Program MFMR 15,000 INDV Direct Post April 22 l UXO for Office extension and Auki 13 MFMR 10,000 Firm CQS National Post April 22 Fisheries Office 14 Geotech for Auki Fisheries Office MFMR 20,000 Firm CQS National Post April 22 Open 15 PMU Senior Procurement Officer MFMR 27,578 INDV National Post April 22 Competitive Open 16 PMU Project Accountant MFMR 27,578 INDV National Post April 22 Competition Open 17 PMU Safeguards Officer (time based) MFMR 7,000 INDV National Post April 22 Competition Total 362,997.10 *Forex 1 SBD = 0.1242 USD (15/10/21) Operating Costs* for PPA dated *Not procurable activities Cost Procureme Procuremen Market Commence Ref Implementin Review Activity Description Estimate nt t Method approach Procuremen . g Entity Type (US$) Category t Incremental operating costs for the PMU (fuel, oil, vehicle maintenance, insurance, office rental) 1 (some of the costs specifically rental, MFMR 60,000 Goods RFQ National Post Oct-21 utilities and fuel are costed in the approved Interim Procurement Plan in the amount of US$7,571.43) Cost incurred for training and workshops including with provincial governments and 2 MFMR 60,000 Goods RFQ National Post Oct-21 stakeholders to inform project design – MOFT Executive and PMU Consultations in the development of FADs 3 MFMR 2,340 Goods RFQ National Post Jan-21 regs Total 120,340 PROCUREMENT Solomon Islands : Solomon Islands: Pacific Islands Regional Oceanscape Program - Second Phase for Economic Resilience PLAN General Information Country: Solomon Islands Bank’s Approval Date of the Original Procurement Plan: 2022-04-25 Revised Plan Date(s): (comma delineated, leave blank if 2023-08-03 none) Project ID: P177239 GPN Date: 2023-06-02 Project Name: Solomon Islands: Pacific Islands Regional Oceanscape Program - Second Phase for Economic Resilience Loan / Credit No: IDA / V4200, IDA / 71050, IDA / E0300 Ministry of Fisheries and Marine Resources Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure Component 1 - Strengthenin ment Document - C1-CW-002 / Construction of Direct - Internation 2023-04-0 IDA / 71050 g Regional Collaboration and Prior Direct Selection 1 Envelope proce 2,000,000.00 0.00 Signed 2022-08-28 2022-10-26 2022-09-02 2022-12-21 2022-10-07 2023-03-29 National MCS Center in Noro al 5 National Capacity for Oceani ss (Non Bank-SPD c Fisheries ) Request for Bids - C2-CW-001 / Construction of Component 2 – Strengthenin Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-08-1 Malaita Fisheries Office in Au IDA / 71050 g Regional Collaboration and Post Request for Bids 1,399,685.00 0.00 2023-10-30 2023-11-04 2023-12-16 2024-01-15 2024-02-19 l nvelope (1 envelope proce lementation 7 ki National Capacity for Coasta ss) l Fisheries Request for Bids - Component 1 - Strengthenin C1 - CW - 001 / Construction Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-08-1 IDA / 71050 g Regional Collaboration and Prior Request for Bids 2,066,894.00 0.00 2023-10-30 2023-11-04 2023-12-16 2024-01-15 2024-02-19 of MFMR HQ Office Extension l nvelope (1 envelope proce lementation 7 National Capacity for Oceani ss) c Fisheries GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1-GO-003 / MCS Uniform, S Component 1 - Strengthenin Request for Quota Single Stage - One E Pending Impl afety Gears and Safety Equip IDA / E0300 g Regional Collaboration and Post Open - National 42,314.00 0.00 2023-06-24 2023-08-19 2024-02-15 tions nvelope ementation ment National Capacity for Oceani c Fisheries C2-GO-004 / Seeds, Gardeni Component 2 – Strengthenin Request for Quota Single Stage - One E Pending Impl ng Eqpt, Freezers, FADs, etc. IDA / E0300 g Regional Collaboration and Post Open - National 12,500.00 0.00 2023-05-06 2023-07-01 2023-12-28 tions nvelope ementation - Malaita National Capacity for Coasta l Fisheries C3-GO-002 / PMU Equipment Component 3 - Project Mana Request for Quota Single Stage - One E Pending Impl IDA / E0300 Post Open - National 7,500.00 0.00 2022-09-03 2022-10-29 2023-04-27 - Furnitures (desk, chair, cabi gement tions nvelope ementation net) Component 1 - Strengthenin C1-GO-002 / MCS Equipment Request for Quota Single Stage - One E Pending Impl IDA / E0300 g Regional Collaboration and Post Open - National 3,500.00 0.00 2023-03-11 2023-05-06 2023-11-02 (Container and Freezer) tions nvelope ementation National Capacity for Oceani c Fisheries C2-GO-003 / Diving gears (s Component 2 – Strengthenin Request for Quota Single Stage - One E norkels, flippers, etc.) - Malai IDA / E0300 g Regional Collaboration and Post Open - National 2,500.00 0.00 Canceled 2023-05-06 2023-07-01 2023-12-28 tions nvelope ta National Capacity for Coasta l Fisheries NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C1-NC-001 / Storage, Insura Component 1 - Strengthenin Direct - Internation Pending Impl nce and Transport for Constr IDA / 71050 g Regional Collaboration and Post Direct Selection 45,000.00 0.00 2022-08-12 2022-08-17 2022-09-21 2023-03-20 al ementation uction Materials (National MC National Capacity for Oceani S Centre, Noro) c Fisheries CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2 – Strengthenin MFMR - CS14 / Geotech for A Consultant Qualifi Pending Impleme IDA / V4200 g Regional Collaboration and Post Open - National 20,000.00 0.00 2022-04-19 2022-04-29 2022-05-19 2022-05-29 2022-06-13 2022-07-29 uki Fisheries Office cation Selection ntation National Capacity for Coasta l Fisheries MFMR - CS13 / UXO for Offic Component 2 – Strengthenin Consultant Qualifi Pending Impleme e extension and Auki Fisherie IDA / V4200 g Regional Collaboration and Post Open - National 10,000.00 0.00 2022-04-19 2022-05-03 2022-06-02 2022-06-20 2022-07-10 2022-07-29 cation Selection ntation s Office National Capacity for Coasta l Fisheries C2-CS-001 / Institutional Rev Component 1 - Strengthenin Consultant Qualifi Pending Impleme iew (Policy paper, road map. IDA / 71050 g Regional Collaboration and Post Open - National 137,500.00 0.00 2023-06-05 2023-06-26 2023-08-09 2023-09-08 2023-10-13 2024-04-10 cation Selection ntation M&E, HR audit, etc). National Capacity for Oceani c Fisheries C2-CS-002 / Project Manage Component 2 – Strengthenin Consultant Qualifi Open - Internationa Pending Impleme ment & Supervision - Constru IDA / E0300 g Regional Collaboration and Post 69,984.00 0.00 2023-04-18 2023-05-09 2023-06-22 2023-07-22 2023-08-26 2024-02-22 cation Selection l ntation ction of Malaita Fisheries Offi National Capacity for Coasta ce in Auki l Fisheries Component 3 - Project Mana Consultant Qualifi Under Implement C4-CS-012 / Audits IDA / 71050 Post Open - National 65,589.00 0.00 2023-03-14 2023-03-14 2023-04-04 2023-05-18 2023-06-17 2023-07-22 2024-01-18 gement cation Selection ation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MFMR - CS03 / PMU Project P Component 3 - Project Mana Individual Consult IDA / V4200 Post Direct 11,661.26 8,365.79 Completed 2022-04-13 2021-11-19 2022-04-15 2021-11-19 2022-04-16 2021-11-19 2022-04-18 2021-11-20 2022-04-30 2022-04-30 rocurement Officer gement ant Selection MFMR - CS04 / PMU Administ Component 3 - Project Mana Individual Consult IDA / V4200 Post Direct 23,503.13 22,235.78 Completed 2022-04-13 2021-11-17 2022-05-03 2021-11-17 2022-05-13 2021-11-17 2022-06-02 2021-11-18 2022-07-29 2022-07-31 rative and Financial Assistant gement ant Selection Page 1 MFMR - CS07 / POM Consulta Component 3 - Project Mana Individual Consult nt – development of the Proje IDA / V4200 Post Open 18,000.00 0.00 Signed 2022-04-14 2022-04-11 2022-05-14 2022-08-15 2022-05-24 2022-08-18 2022-06-13 2022-08-24 2022-07-29 gement ant Selection ct Operations Manual (POM) MFMR - CS06 / ESF Safeguar Component 3 - Project Mana IDA / V4200 Post Direct Selection Direct 26,000.00 15,600.00 Completed 2022-04-14 2021-11-13 2022-04-24 2021-11-02 2022-05-02 2021-11-06 2022-07-29 2022-05-31 ds Consultant gement MFMR - CS09 / Civil Engineer Component 1 - Strengthenin Individual Consult ing Consultant – Noro civil wo IDA / V4200 g Regional Collaboration and Post Open 20,000.00 0.00 Signed 2022-04-19 2022-09-14 2022-05-18 2023-01-03 2022-05-23 2023-01-05 2022-06-27 2023-01-15 2022-07-29 ant Selection rks National Capacity for Oceani c Fisheries Component 1 - Strengthenin MFMR - CS12 / Evaluation  of Individual Consult Under Implement IDA / V4200 g Regional Collaboration and Post Open 15,000.00 0.00 2022-04-19 2023-05-04 2022-05-19 2022-05-29 2022-06-10 2022-07-29 the Observer Program ant Selection ation National Capacity for Oceani c Fisheries MFMR - CS11 / Legal Consult Component 1 - Strengthenin Individual Consult Under Implement ant – conduct legal assessme IDA / V4200 g Regional Collaboration and Post Direct 20,000.00 0.00 2022-04-19 2022-05-20 2022-05-09 2022-05-19 2022-06-08 2022-07-29 ant Selection ation nt on UNCLOS Article 73 National Capacity for Oceani c Fisheries MFMR - CS08 / Monitoring an Component 3 - Project Mana Individual Consult Pending Impleme IDA / V4200 Post Open 16,000.00 0.00 2022-04-19 2022-05-18 2022-05-23 2022-05-29 2022-07-29 d Evaluation Consultant gement ant Selection ntation MFMR - CS01 / PMU Project Component 3 - Project Mana Individual Consult IDA / V4200 Post Direct 44,484.96 39,856.45 Completed 2022-04-13 2021-11-17 2022-04-19 2021-11-17 2022-04-20 2021-11-17 2022-04-22 2021-11-18 2022-07-29 2022-07-31 Coordinator gement ant Selection MFMR - CS05 / Short-term Fi Component 3 - Project Mana IDA / V4200 Post Direct Selection Direct 4,191.75 0.00 Signed 2022-05-02 2022-09-19 2022-05-12 2022-09-21 2022-05-27 2022-07-20 2022-07-29 nancial Management Speciali gement st MFMR - CS17 / Environment Component 3 - Project Mana Individual Consult Under Implement al & Social safeguards Officer IDA / V4200 Post Open 7,000.00 0.00 2022-04-19 2022-05-20 2022-05-26 2022-06-09 2022-06-29 2022-07-29 gement ant Selection ation (time based) C1-CS-002 / Project Manage Component 1 - Strengthenin Direct - Internation Under Implement ment & Supervision - Nationa IDA / 71050 g Regional Collaboration and Post Direct Selection 188,060.00 0.00 2022-08-28 2022-10-25 2022-09-07 2022-12-19 2022-11-11 2023-05-10 al ation l MCS Center in Noro National Capacity for Oceani c Fisheries Component 1 - Strengthenin C1-CS-003 / ePort Initiative S Individual Consult Under Implement IDA / E0300 g Regional Collaboration and Post Open - National 5,083.00 0.00 2022-09-05 2022-10-06 2022-10-24 2022-11-14 2022-12-19 2023-06-17 ystem Development Staff 1 ant Selection ation National Capacity for Oceani c Fisheries Component 1 - Strengthenin C1-CS-004 / ePort Initiative S Individual Consult Under Implement IDA / E0300 g Regional Collaboration and Post Open - National 5,083.00 0.00 2022-09-05 2022-10-06 2022-10-24 2022-11-14 2022-12-19 2023-06-17 ystem Development Staff 2 ant Selection ation National Capacity for Oceani c Fisheries Component 1 - Strengthenin C1-CS-005 / ePort Initiative S Individual Consult Under Implement IDA / E0300 g Regional Collaboration and Post Open - National 5,083.00 0.00 2022-09-05 2022-10-06 2022-10-24 2022-11-14 2022-12-19 2023-06-17 ystem Development Staff 3 ant Selection ation National Capacity for Oceani c Fisheries C1-CS-016 / Development of Component 1 - Strengthenin Individual Consult Open - Internationa Pending Impleme EM Information Management IDA / 71050 g Regional Collaboration and Post 31,250.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2024-02-03 ant Selection l ntation System National Capacity for Oceani c Fisheries C1-CS-017 / Study Fund on Component 1 - Strengthenin Individual Consult Open - Internationa Pending Impleme Harnessing Oceanic Fisheries IDA / 71050 g Regional Collaboration and Post 50,000.00 0.00 2022-09-25 2022-11-13 2022-12-04 2023-01-08 2023-07-07 ant Selection l ntation to National Economy National Capacity for Oceani c Fisheries C2-CS-003 / Legal Drafting ( Component 2 – Strengthenin Individual Consult Open - Internationa Pending Impleme Provincial Fisheries Ordinanc IDA / 71050 g Regional Collaboration and Post 45,000.00 0.00 2023-07-10 2023-08-28 2023-09-18 2023-10-23 2024-04-20 ant Selection l ntation es) National Capacity for Coasta l Fisheries Component 2 – Strengthenin C2-CS-004 / Legal Consultan Individual Consult Open - Internationa Pending Impleme IDA / E0300 g Regional Collaboration and Post 55,125.00 0.00 2023-10-03 2023-11-28 2023-12-19 2024-01-23 2024-07-21 t to develop Aquaculture Bill ant Selection l ntation National Capacity for Coasta l Fisheries Component 2 – Strengthenin C2-CS-005 / Marketing of BD Individual Consult Open - Internationa Pending Impleme IDA / E0300 g Regional Collaboration and Post 12,500.00 0.00 2023-08-07 2023-09-25 2023-10-16 2023-11-20 2024-05-18 M Products (Consultant) ant Selection l ntation National Capacity for Coasta l Fisheries Component 2 – Strengthenin C2-CS-006 / Senior CBRM Fis Individual Consult Under Implement IDA / 71050 g Regional Collaboration and Post Open - National 58,373.00 0.00 2023-05-15 2023-05-05 2023-07-03 2023-07-24 2023-08-28 2024-02-24 heries Staff 1 ant Selection ation National Capacity for Coasta l Fisheries Component 2 – Strengthenin C2-CS-007 / Senior CBRM Fis Individual Consult Under Implement IDA / 71050 g Regional Collaboration and Post Open - National 58,373.00 0.00 2023-05-15 2023-05-05 2023-07-03 2023-07-24 2023-08-28 2024-02-24 heries Staff 2 ant Selection ation National Capacity for Coasta l Fisheries Component 2 – Strengthenin C2-CS-008 / Data Collection Individual Consult Under Implement IDA / 71050 g Regional Collaboration and Post Open - National 19,748.00 0.00 2023-05-29 2023-05-05 2023-07-17 2023-08-07 2023-09-11 2024-03-09 Enumerator - Isabel ant Selection ation National Capacity for Coasta l Fisheries Component 2 – Strengthenin C2-CS-009 / Data Collection Individual Consult Under Implement IDA / 71050 g Regional Collaboration and Post Open - National 19,748.00 0.00 2023-05-29 2023-05-05 2023-07-17 2023-08-07 2023-09-11 2024-03-09 Enumerator - Western ant Selection ation National Capacity for Coasta l Fisheries Component 2 – Strengthenin C2-CS-010 / Data Collection Individual Consult Under Implement IDA / 71050 g Regional Collaboration and Post Open - National 19,748.00 0.00 2023-05-29 2023-05-05 2023-07-17 2023-08-07 2023-09-11 2024-03-09 Enumerator - Temotu ant Selection ation National Capacity for Coasta l Fisheries C2-CS-011 / Study for small- Component 2 – Strengthenin Individual Consult Open - Internationa Pending Impleme scale fisheries statistics strat IDA / 71050 g Regional Collaboration and Post 20,000.00 0.00 2023-05-16 2023-07-04 2023-07-25 2023-08-29 2024-02-25 ant Selection l ntation egy National Capacity for Coasta l Fisheries C2-CS-012 / Studies: Develo Component 2 – Strengthenin Individual Consult Open - Internationa Pending Impleme ping and diversifying local va IDA / E0300 g Regional Collaboration and Post 50,000.00 0.00 2023-06-19 2023-08-07 2023-08-28 2023-10-02 2024-03-30 ant Selection l ntation lue chains National Capacity for Coasta l Fisheries C4-CS-002 / PMU Assistant P Component 3 - Project Mana Individual Consult Pending Impleme IDA / 71050 Post Open - National 179,420.00 0.00 2023-01-30 2023-03-20 2023-04-10 2023-05-15 2023-11-11 rocurement Officer gement ant Selection ntation C4-CS-003 / PMU Sr. Procure Component 3 - Project Mana Individual Consult IDA / 71050 Post Open - National 248,176.00 0.00 Signed 2022-08-15 2022-09-13 2022-10-03 2022-11-22 2022-10-24 2022-12-12 2022-11-28 2023-01-25 2023-05-27 ment Officer gement ant Selection C4-CS-004 / PMU Project Acc Component 3 - Project Mana Individual Consult IDA / 71050 Post Open - National 248,176.00 0.00 Signed 2022-08-15 2022-09-13 2022-10-03 2022-11-24 2022-10-24 2022-12-16 2022-11-28 2023-01-18 2023-05-27 ountant gement ant Selection C4-CS-006 / PMU Safeguards Component 3 - Project Mana Individual Consult Under Implement IDA / 71050 Post Open - National 20,866.00 0.00 2022-08-15 2022-08-15 2022-10-03 2022-10-24 2022-11-28 2023-05-27 Officer gement ant Selection ation Page 2 C4-CS-007 / PMU M&E Office Component 3 - Project Mana Individual Consult Pending Impleme r (to work with International IDA / 71050 Post Open - National 20,866.00 0.00 2022-08-29 2022-10-17 2022-11-07 2022-12-12 2023-06-10 gement ant Selection ntation Expert - time-based) C4-CS-008 / PMU Communit Component 3 - Project Mana Individual Consult Pending Impleme IDA / 71050 Post Open - National 13,041.00 0.00 2022-08-29 2022-10-17 2022-11-07 2022-12-12 2023-06-10 y Liaison Officer (time-based) gement ant Selection ntation C4-CS-010 / International M Component 3 - Project Mana Individual Consult Open - Internationa Pending Impleme IDA / 71050 Post 84,000.00 0.00 2022-08-29 2022-10-17 2022-11-07 2022-12-12 2023-06-10 &E Specialist (time-based) gement ant Selection l ntation C4-CS-011 / International Pr Component 3 - Project Mana Individual Consult Open - Internationa IDA / 71050 Post 78,000.00 0.00 Signed 2022-08-29 2022-09-19 2022-10-17 2023-01-03 2022-11-07 2023-01-11 2022-12-12 2023-01-15 2023-06-10 ocurement Specialist (time-b gement ant Selection l ased) C4-CS-001 / PMU Project Coo Component 3 - Project Mana Individual Consult IDA / 71050 Prior Direct - National 323,636.00 0.00 Signed 2022-07-20 2022-10-04 2022-07-20 2022-09-27 2022-07-20 2022-10-25 2022-07-20 2023-05-14 2023-01-16 rdinator gement ant Selection Component 1 - Strengthenin C1-CS-008 / EM Current Anal Individual Consult IDA / 71050 g Regional Collaboration and Post Direct - National 15,000.00 0.00 Signed 2023-05-01 2023-01-25 2023-05-11 2023-02-03 2023-06-01 2023-03-17 2023-07-06 2023-03-19 2024-01-02 yst 3 ant Selection National Capacity for Oceani c Fisheries Component 1 - Strengthenin C1-CS-010 / EM Current Anal Individual Consult Under Implement IDA / 71050 g Regional Collaboration and Post Direct - National 15,000.00 0.00 2023-05-01 2023-01-25 2023-05-11 2023-06-01 2023-07-06 2024-01-02 yst 5 ant Selection ation National Capacity for Oceani c Fisheries C4-CS-005 / PMU Project Ad Component 3 - Project Mana Individual Consult IDA / 71050 Post Direct - National 179,420.00 0.00 Signed 2022-07-20 2022-08-01 2022-07-20 2022-08-01 2022-07-20 2022-08-01 2022-07-20 2022-09-18 2023-01-16 ministrative and Financial As gement ant Selection sistant C4-CS-009 / International Sa Component 3 - Project Mana Individual Consult Direct - Internation IDA / 71050 Post 78,000.00 0.00 Signed 2022-08-01 2022-09-05 2022-08-11 2022-09-14 2022-09-01 2022-10-03 2022-10-06 2022-10-21 2023-04-04 feguards Specialist (time-bas gement ant Selection al ed) Component 1 - Strengthenin C1-CS-006 / EM Current Anal Individual Consult IDA / 71050 g Regional Collaboration and Post Direct - National 15,000.00 0.00 Signed 2023-05-01 2023-01-25 2023-05-11 2023-02-03 2023-06-01 2023-03-09 2023-07-06 2023-03-19 2024-01-02 yst 1 ant Selection National Capacity for Oceani c Fisheries Component 1 - Strengthenin C1-CS-007 / EM Current Anal Individual Consult IDA / 71050 g Regional Collaboration and Post Direct - National 15,000.00 0.00 Signed 2023-05-01 2023-01-25 2023-05-11 2023-02-03 2023-06-01 2023-03-06 2023-07-06 2023-03-19 2024-01-02 yst 2 ant Selection National Capacity for Oceani c Fisheries Component 1 - Strengthenin C1-CS-009 / EM Current Anal Individual Consult IDA / 71050 g Regional Collaboration and Post Direct - National 15,000.00 0.00 Signed 2023-05-01 2023-01-25 2023-05-11 2022-09-09 2023-06-01 2022-10-17 2023-07-06 2022-10-22 2024-01-02 yst 4 ant Selection National Capacity for Oceani c Fisheries Component 1 - Strengthenin Direct - Internation C1-CS-023 / EM- Satlink IDA / E0300 g Regional Collaboration and Post Direct Selection 74,411.00 0.00 Signed 2023-04-17 2023-04-01 2023-04-27 2023-06-13 2023-07-01 2023-07-01 2023-12-28 al National Capacity for Oceani c Fisheries MFMR - CS10 / Procurement Component 3 - Project Mana Individual Consult IDA / V4200 Post Open 32,000.00 0.00 Canceled 2022-04-19 2022-05-19 2022-05-29 2022-06-08 2022-07-29 Consultant gement ant Selection MFMR - CS02 / Design Prepa Component 3 - Project Mana Individual Consult IDA / V4200 Post Open 40,000.00 0.00 Canceled 2022-04-19 2022-05-09 2022-05-31 2022-07-05 2022-07-29 ration Consultant gement ant Selection MFMR - CS15 / PMU Senior P Component 3 - Project Mana Individual Consult IDA / V4200 Post Open 27,578.00 0.00 Canceled 2022-04-19 2022-05-19 2022-05-29 2022-06-18 2022-07-29 rocurement Officer gement ant Selection MFMR - CS16 / PMU Project A Component 3 - Project Mana Individual Consult IDA / V4200 Post Open 27,578.00 0.00 Canceled 2022-04-19 2022-05-19 2022-05-29 2022-06-18 2022-07-29 ccountant gement ant Selection C4-CS-013 / Project Coordina Component 3 - Project Mana Individual Consult Pending Impleme IDA / E0300 Post Open - National 132,614.00 0.00 2023-07-10 2023-08-28 2023-09-18 2023-10-23 2024-04-20 tor - PMU gement ant Selection ntation Page 3