PROCUREMENT PLAN (Textual Part) Project information: Mauritania- Water and Sanitation Sectoral Project-- P167328 Project Implementation agency: Ministry of Hydraulic and Sanitation (MHA) Date of the Procurement Plan: 25 December 2020 Period covered by this Procurement Plan: 28 September 2020 to 30 November 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. “Not Applicable” Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: “Not Applicable” Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Mauritania : Water and Sanitation Sectoral Project PLAN General Information Country: Mauritania 2021-01-13 Bank’s Approval Date of the Original Procurement Plan: 2024-08-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167328 GPN Date: 2020-12-21 Project Name: Water and Sanitation Sectoral Project Loan / Credit No: IDA / D5710 WATER AND SANITATION SECTORAL PROJECT Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Improvement 02/T/PSEA/2022 / Réhabiliter of access to drinking water a Open - Internationa Single Stage - One E 2023-02-2 et étendre le réseau AEP de IDA / D5710 A posteriori Appel d'offres 0.00 Signé 2022-05-10 2023-05-29 2022-05-15 2023-05-29 2022-06-26 2023-07-12 2022-07-26 2023-07-11 2022-08-30 2023-10-25 nd sanitation in Gorgol, Guid l nvelope 6 Kiffa imakha and Assaba Document na O1/T/PSEA/2022 / Réhabilite tional de pas r et étendre 62 systèmes de Component 1: Improvement sation des m distribution d’eau potable exi of access to drinking water a Open - Internationa Single Stage - One E archés - Proc 2023-03-0 IDA / D5710 A posteriori Appel d'offres 0.00 Annulé 2022-05-17 2022-05-22 2022-07-03 2022-08-02 2022-09-06 stants dans les localités rural nd sanitation in Gorgol, Guid l nvelope essus à une 5 es sélectionnées (Assaba - G imakha and Assaba enveloppe (D orgol - Guidimakha ) TPM ne prov enant pas de la Banque) na Document 03/T/PSEA/2021 / Réhabiliter tional de pas et étendre les réseaux AEP d Component 1: Improvement sation des m e 5 localités semi-urbaines ( of access to drinking water a Single Stage - One E archés - Proc 2023-05-0 Monguel et Maghama - Gorg IDA / D5710 A posteriori Appel d'offres Open - National 0.00 Annulé 2022-07-13 2022-07-26 2022-09-06 2022-10-06 2022-11-10 nd sanitation in Gorgol, Guid nvelope essus à une 9 ol ; Ould Yenjé - Guidimakha imakha and Assaba enveloppe (D ; Boumdeid et Barkeol - Assa TPM ne prov ba) enant pas de la Banque) na Document Component 2: Improving sus tional de pas tainable access to safe wate sation des m 04/T/PSEA/2021 / Réhabiliter r and sanitation for refugees Single Stage - One E archés - Proc En attente d 2023-04-0 et étendre le réseau AEP des IDA / D5710 A posteriori Appel d'offres Open - National 0.00 2022-06-15 2022-06-20 2022-08-01 2022-08-31 2022-10-05 and host communities in Ho nvelope essus à une 'exécution 3 servant le Camp de M'Bera dh Echargui and Hodh El Gh enveloppe (D arbi TPM ne prov enant pas de la Banque) na Document 05/T/PSEA/2021 / Réhabilitat Component 2: Improving sus tional de pas ion et étendre 20 systèmes tainable access to safe wate sation des m de distribution d’eau potable r and sanitation for refugees Single Stage - One E archés - Proc En attente d 2023-07-0 existants dans les localités ru IDA / D5710 A posteriori Appel d'offres Open - National 0.00 2022-08-24 2022-09-14 2022-10-26 2022-11-25 2023-01-06 and host communities in Ho nvelope essus à une 'exécution 5 rales sélectionnées (dans le dh Echargui and Hodh El Gh enveloppe (D Hodh Echargui et dans le Ho arbi TPM ne prov dh El Gharbi) enant pas de la Banque) na Document Component 2: Improving sus tional de pas tainable access to safe wate sation des m 06/T/PSEA/2021 / Réhabiliter r and sanitation for refugees Single Stage - One E archés - Proc 2023-06-2 et étendre les réseaux AEP d IDA / D5710 A posteriori Appel d'offres Open - National 0.00 Annulé 2022-08-23 2022-09-13 2022-10-25 2022-11-24 2022-12-29 and host communities in Ho nvelope essus à une 7 e Oualata et de Tamchekett dh Echargui and Hodh El Gh enveloppe (D arbi TPM ne prov enant pas de la Banque) na Document Component 2: Improving sus tional de pas 07/T/PSEA/2021 / Réaliser 2 tainable access to safe wate sation des m 400 latrines dotées de dispos r and sanitation for refugees Single Stage - One E archés - Proc 2023-05-0 IDA / D5710 A posteriori Appel d'offres Open - National 0.00 Signé 2022-07-19 2023-09-12 2022-07-24 2024-07-19 2022-09-04 2023-10-12 2022-10-04 2023-12-20 2022-11-08 2024-05-31 itifs de lavage des mains dan and host communities in Ho nvelope essus à une 7 s le Camp de M'Bera dh Echargui and Hodh El Gh enveloppe (D arbi TPM ne prov enant pas de la Banque) na Document Component 2: Improving sus tional de pas 08/T/PSEA/2021 / Réaliser u tainable access to safe wate sation des m n dispositif d'évacuation des r and sanitation for refugees Single Stage - One E archés - Proc En attente d 2023-12-3 IDA / D5710 A posteriori Appel d'offres Open - National 0.00 2023-03-14 2023-03-19 2023-04-30 2023-05-30 2023-07-04 eaux pluviales dans le camp and host communities in Ho nvelope essus à une 'exécution 1 de M'Bera dh Echargui and Hodh El Gh enveloppe (D arbi TPM ne prov enant pas de la Banque) na Document Component 2: Improving sus tional de pas 11/T/PSEA/2022 / Réalisation tainable access to safe wate sation des m de 20 nouveaux forages et s r and sanitation for refugees Single Stage - One E archés - Proc En attente d 2023-07-0 IDA / D5710 A posteriori Appel d'offres Open - National 0.00 2022-09-08 2022-09-22 2022-11-03 2022-12-03 2023-01-07 oufflage er essais de pompag and host communities in Ho nvelope essus à une 'exécution 6 es de 10 forages existants dh Echargui and Hodh El Gh enveloppe (D arbi TPM ne prov enant pas de la Banque) na Document tional de pas 09/T/PSEA/2021 / Réaliser 8 Component 1: Improvement sation des m 05 latrines dans les écoles, le of access to drinking water a Single Stage - One E archés - Proc 2022-12-3 IDA / D5710 A posteriori Appel d'offres Open - National 0.00 Signé 2022-03-14 2022-10-27 2022-03-19 2022-04-30 2022-09-27 2022-05-30 2023-04-26 2022-07-04 2023-05-25 s centres de santé, ect,( repa nd sanitation in Gorgol, Guid nvelope essus à une 1 rtis en 3 lot) imakha and Assaba enveloppe (D TPM ne prov enant pas de la Banque) na Document tional de pas Component 1: Improvement sation des m 10/T/PSEA/2022 / Réalisation of access to drinking water a Single Stage - One E archés - Proc 2024-01-2 de 96 nouveaux forages (rep IDA / D5710 A posteriori Appel d'offres Open - National 0.00 Signé 2022-09-07 2022-09-05 2022-09-21 2022-11-02 2022-10-26 2022-12-02 2022-12-20 2023-01-19 2023-06-23 nd sanitation in Gorgol, Guid nvelope essus à une 5 artis en 3 lot) imakha and Assaba enveloppe (D TPM ne prov enant pas de la Banque) Demande d'o MR-WSSP-332245-CW-DIR / Component 2: Improving sus ffres - DTPM Réalisation de 40 forages d'e tainable access to safe wate Single Stage - One E Equipements 2024-01-0 xploitation en deux lots 1 et IDA / D5710 r and sanitation for refugees A priori Appel d'offres Open - National Yes 0.00 Signé 2023-03-20 2023-04-10 2023-03-25 2023-05-31 2023-05-06 2023-03-08 2023-06-05 2023-06-05 2023-07-10 2023-06-26 nvelope Conception ( 6 2 séparés par appel d'offres and host communities in Ho sans préquali ouvert dh Echargui and Hodh El Gh fication) arbi Component 2: Improving sus Demande d'o MR-WSSP-332620-CW-RFB / tainable access to safe wate ffres - DTPM Réalisation de 40 forages d'e Single Stage - One E En cours d'e 2023-12-0 IDA / D5710 r and sanitation for refugees A priori Appel d'offres Open - National Yes Travaux (san 0.00 2023-02-13 2023-06-27 2023-02-18 2023-06-30 2023-04-01 2023-08-03 2023-05-01 2023-10-30 2023-06-05 xploitation dans les Hodhs El nvelope xécution 2 and host communities in Ho s préqualifica Chargui et El Gharbi (lot2) dh Echargui and Hodh El Gh tion) arbi Document na Component 2: Improving sus tional de pas MR-WSSP-336655-CW-RFB / tainable access to safe wate sation des m Réalisation de 161 blocs de l r and sanitation for refugees Single Stage - One E archés - Proc 2023-12-0 IDA / D5710 A posteriori Appel d'offres Open - National 0.00 Signé 2023-02-15 2023-01-30 2023-02-20 2023-02-06 2023-04-03 2023-03-08 2023-05-03 2023-04-26 2023-06-07 2023-06-03 atrines publiques dans 97 loc and host communities in Ho nvelope essus à une 4 alités dh Echargui and Hodh El Gh enveloppe (D arbi TPM ne prov enant pas de la Banque) Page 1 Demande d'o MR-WSSP-335958-CW-RFB / Component 2: Improving sus ffres - DTPM Réalisation de 80 forages d'e tainable access to safe wate Single Stage - One E Petits travau 2025-02-2 xploitation en deux tranches IDA / D5710 r and sanitation for refugees A posteriori Appel d'offres Open - National 0.00 Annulé 2023-02-01 2023-04-19 2023-04-19 2023-02-06 2023-06-28 2023-07-28 2023-09-01 nvelope x - (Processu 2 de 2 tranches de 2 lots chacu and host communities in Ho s à 1 envelop n dh Echargui and Hodh El Gh pe) arbi Component 2: Improving sus Demande d'o MR-WSSP-332248-NC-DIR / R tainable access to safe wate ffres - DTPM éalisation de 161 blocs de lat Single Stage - One E 2023-11-2 IDA / D5710 r and sanitation for refugees A priori Appel d'offres Open - National Yes Travaux (san 0.00 Annulé 2023-02-07 2023-04-10 2023-02-12 2023-03-26 2023-04-25 2023-05-30 rines publics dans 97 localité nvelope 6 and host communities in Ho s préqualifica s dh Echargui and Hodh El Gh tion) arbi MR-WSSP-394979-CW-RFB / Réhabilitation et étendre en Demande d'o Component 1: Improvement 01 tranchede 30 systèmes d ffres - DTPM of access to drinking water a Single Stage - One E En attente d 2024-11-0 e distribution d’eau potable e IDA / D5710 A posteriori Appel d'offres Open - National Travaux (san 0.00 2024-01-22 2024-01-27 2024-03-09 2024-04-08 2024-05-13 nd sanitation in Gorgol, Guid nvelope 'exécution 9 xistants dans les localités rur s préqualifica imakha and Assaba ales sélectionnées (dans le H tion) odhEchargui et dans le Hodh El Gharbi) Demande de Component 2: Improving sus MR-WSSP-394976-CW-RFQ / cotations - D tainable access to safe wate Réaliser un dispositif d'évacu Single Stage - One E TPM Petits tr En attente d 2024-07-1 IDA / D5710 r and sanitation for refugees A posteriori Demande de prix Limited 0.00 2024-01-20 2024-03-16 ation des boues de vidange d nvelope avaux (urgen 'exécution 4 and host communities in Ho ans le camp de M'Bera ce) - Avec co dh Echargui and Hodh El Gh mpétition arbi MR-WSSP-397109-CW-RFB / Demande d'o Réhabiliter et étendre 80 sys Component 1: Improvement ffres - DTPM tèmes de distribution d’eau p of access to drinking water a Single Stage - One E 2024-10-0 IDA / D5710 A posteriori Appel d'offres Open - National Travaux (san 0.00 Signé 2023-12-15 2023-09-01 2023-12-20 2024-07-17 2024-01-31 2023-11-08 2024-03-01 2024-04-05 2024-04-05 2024-03-22 otable existants plusieurs lot nd sanitation in Gorgol, Guid nvelope 2 s préqualifica s dans les localités rurales sé imakha and Assaba tion) lectionnées (Assaba - Gorgol - Guidimakha ) Demande d'o MR-WSSP-432844-CW-RFB / Component 1: Improvement ffres - DTPM Travaux de réalisation de 14 of access to drinking water a Single Stage - One E En attente d 2025-08-1 IDA / D5710 A posteriori Appel d'offres Open - National Travaux (san 0.00 2024-08-18 2024-08-23 2024-10-04 2024-11-03 2024-12-08 nouveaux réseaux d’AEP au nd sanitation in Gorgol, Guid nvelope 'exécution 5 s préqualifica Gorgol imakha and Assaba tion) MR-WSSP-432847-CW-RFB / Demande d'o Component 1: Improvement Travaux de réalisation de 40 ffres - DTPM of access to drinking water a Single Stage - One E En attente d 2025-11-2 nouveaux réseaux d’AEP en IDA / D5710 A posteriori Appel d'offres Open - National Travaux (san 0.00 2024-08-05 2024-08-10 2024-09-21 2024-10-21 2024-11-25 nd sanitation in Gorgol, Guid nvelope 'exécution 5 deux lots distincts de 20 rése s préqualifica imakha and Assaba aux AEP chacun en Assaba et tion) au Guidimaka Component 2: Improving sus Demande d'o MR-WSSP-432970-CW-RFB / tainable access to safe wate ffres - DTPM Travaux de réalisation de 14 Single Stage - One E 2025-06-1 IDA / D5710 r and sanitation for refugees A posteriori Appel d'offres Open - National Travaux (san 0.00 Annulé 2024-08-28 2024-09-02 2024-10-14 2024-11-13 2024-12-18 nouveaux réseaux d’AEP dan nvelope 6 and host communities in Ho s préqualifica s les deux Hodhs dh Echargui and Hodh El Gh tion) arbi Demande de MR-WSSP-431943-CW-DIR / cotations - D Component 3: Institutional S Travaux de réalisation de hui Passation de marc TPM Petits tr En attente d 2024-11-0 IDA / D5710 upport, Capacity Building an A posteriori Direct - National 0.00 2024-06-27 2024-07-02 2024-08-06 t (08) nouveaux piézomètres hé de gré à gré avaux (urgen 'exécution 4 d Project Management pour le suivi de la nappe du ce) - Sans co Dhar mpétition Document na tional de pas MR-WSSP-441301-CW-RFB / Component 1: Improvement sation des m Réhabiliter et étendre les rés of access to drinking water a Single Stage - One E archés - Proc En attente d 2025-07-1 eaux AEP de 3 localités semi- IDA / D5710 A posteriori Appel d'offres Open - National 0.00 2024-09-27 2024-10-02 2024-11-13 2024-12-13 2025-01-17 nd sanitation in Gorgol, Guid nvelope essus à une 'exécution 6 urbaines (Maghama - Ould Y imakha and Assaba enveloppe (D enjé - et Boumdeid ) TPM ne prov enant pas de la Banque) na Document Component 2: Improving sus tional de pas MR-WSSP-441354-CW-RFB / tainable access to safe wate sation des m Travaux de réalisation de 25 r and sanitation for refugees Single Stage - One E archés - Proc En attente d 2025-07-1 nouveaux réseaux d’AEP en IDA / D5710 A posteriori Appel d'offres Open - National 0.00 2024-09-30 2024-10-05 2024-11-16 2024-12-16 2025-01-20 and host communities in Ho nvelope essus à une 'exécution 9 2 lots distincts de 13 et 12 A dh Echargui and Hodh El Gh enveloppe (D EP au 2 Hodhs arbi TPM ne prov enant pas de la Banque) na Document MR-WSSP-441357-CW-RFB / tional de pas Travaux de réalisation de 40 Component 1: Improvement sation des m nouveaux réseaux d’AEP en of access to drinking water a Single Stage - One E archés - Proc En attente d 2025-07-1 IDA / D5710 A posteriori Appel d'offres Open - National 0.00 2024-09-30 2024-10-05 2024-11-16 2024-12-16 2025-01-20 deux lots distincts de 20 rése nd sanitation in Gorgol, Guid nvelope essus à une 'exécution 9 aux AEP chacun en Assaba et imakha and Assaba enveloppe (D au Guidimaka TPM ne prov enant pas de la Banque) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01/F/PSEA/2021 / Acquisition Component 3: Institutional S Single Stage - One E de matériel informatique et IDA / D5710 upport, Capacity Building an A posteriori Demande de prix Open - National 0.00 Signé 2021-01-17 2021-03-14 2020-04-20 2021-09-10 nvelope matériel bureautique d Project Management Component 3: Institutional S 02/F/PSEA/2021 / Logiciel TE Passation de marc IDA / D5710 upport, Capacity Building an A posteriori Direct 0.00 Signé 2021-03-10 2021-05-05 2021-03-15 2021-05-05 2021-04-19 2021-05-05 2021-10-16 MPRO hé de gré à gré d Project Management 03/F/PSEA/2021 / Acquisition Component 3: Institutional S Passation de marc En cours d'ex 7 Véhicules(3 SW+4 PU) pour IDA / D5710 upport, Capacity Building an A posteriori hés auprès des ag Direct 0.00 2021-04-12 2021-03-22 2021-04-17 2021-03-22 2021-05-22 2021-11-18 écution l'UCP d Project Management ences de l'ONU 03/F/PSEA/2022 / Acquisition Component 3: Institutional S 6 véhicules (2 SW +4 PU) po Passation de marc IDA / D5710 upport, Capacity Building an A posteriori Direct 0.00 Annulé 2022-05-19 2022-05-24 2022-07-12 2023-01-08 ur MHA dont deux véhicules hé de gré à gré d Project Management au profit du CNRE MR-WSSP-376063-GO-RFQ / Component 3: Institutional S Acquisition de logiciels en ge Single Stage - One E En attente d' IDA / D5710 upport, Capacity Building an A posteriori Demande de prix Limited 0.00 2023-10-07 2023-12-02 2024-01-31 stion de l’assainissement non nvelope exécution d Project Management collectif au profit de la DA MR-WSSP-376065-GO-RFQ / Fourniture de logiciel de sim Component 3: Institutional S Single Stage - One E En attente d' ulation hydrauliquse GISet d IDA / D5710 upport, Capacity Building an A posteriori Demande de prix Limited 0.00 2024-02-18 2024-04-14 2024-06-13 nvelope exécution e logiciel de simulation ARC d Project Management GIS/Water cad/Hammer/Cebe mail pour SNDE Page 2 MR-WSSP-394995-GO-RFB / Component 3: Institutional S Acquisition de deux véhicule Single Stage - One E En attente d' IDA / D5710 upport, Capacity Building an A posteriori Appel d'offres Open - National 0.00 2024-02-20 2024-02-25 2024-04-07 2024-05-07 2024-06-11 2024-09-09 s :1 Station Wagon et 1 Pick nvelope exécution d Project Management up au profit du CNRE 02/F/PSEA/2022 / Acquisition Component 3: Institutional S Single Stage - One E En attente d' d'unités de prospection géo IDA / D5710 upport, Capacity Building an A posteriori Appel d'offres Open - National 0.00 2022-06-14 2022-06-19 2022-07-31 2022-08-30 2022-10-04 2023-01-10 nvelope exécution physique et équipement au p d Project Management rofit au CNRE 01/F/PSEA/2022 / Equipeme Component 2: Improving sus nt réseau piézométriques tél tainable access to safe wate Single Stage - One E En attente d' émétrique des nappes de Dh IDA / D5710 r and sanitation for refugees A posteriori Appel d'offres Open - National 0.00 2024-02-15 2024-02-27 2024-04-09 2024-05-09 2024-06-13 2024-08-22 nvelope exécution ar et du Grés d'Aïoun (25) au and host communities in Ho profit du CNRE dh Echargui and Hodh El Gh arbi MR-WSSP-431947-GO-RFQ / Component 3: Institutional S Fourniture et Installation de Single Stage - One E En attente d' IDA / D5710 upport, Capacity Building an A posteriori Demande de prix Open - National 0.00 2024-07-20 2024-09-14 2024-11-13 10 enregistreurs pour le suivi nvelope exécution d Project Management de la nappe du Dhar et réhab ilitation des tètes MR-WSSP-432833-GO-RFQ / Component 3: Institutional S Single Stage - One E Acquisition de logiciels ARC IDA / D5710 upport, Capacity Building an A posteriori Demande de prix Limited - National 0.00 Annulé 2024-07-19 2024-09-13 2024-11-12 nvelope GIS et MOD FLOW au profit d d Project Management u CNRE MR-WSSP-432829-GO-DIR / Component 3: Institutional S Passation de marc En attente d' Acquisition de 05 véhicules IDA / D5710 upport, Capacity Building an A posteriori Direct - National 0.00 2024-06-13 2024-06-18 2024-07-23 2025-01-19 hé de gré à gré exécution 4X4 au profit de l’UCP d Project Management NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-WSSP-394994-NC-RFQ / Component 1: Improvement soufflage et essais de pompa of access to drinking water a Single Stage - One E En attente d' IDA / D5710 A posteriori Demande de prix Limited 0.00 2024-03-16 2024-05-11 2024-07-10 ges de 10 forages existants d nd sanitation in Gorgol, Guid nvelope exécution ans le cadre des réhabilitatio imakha and Assaba ns AEP (lot 1 et lot 2) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Institutional S 07/PI/PSEA/2021 / Recrutem Sélection au moin En cours d'exécut IDA / D5710 upport, Capacity Building an A posteriori Open - National 0.00 2021-06-15 2021-03-19 2021-07-06 2021-08-19 2021-09-16 2021-10-16 2021-11-20 2021-12-25 2022-06-23 ent Auditeur Externe dre coût ion d Project Management Component 1: Improvement Sélection fondée s 15/PI/PSEA/2021 / Recrutem of access to drinking water a Open - Internationa IDA / D5710 A posteriori ur la qualité et le 0.00 Signé 2021-02-15 2021-02-11 2021-03-08 2021-02-16 2021-04-21 2021-07-12 2021-05-19 2021-09-30 2021-06-18 2021-11-05 2021-07-23 2021-12-06 2021-08-27 2022-06-09 2022-08-27 ent Maître d'Œuvre (MOE) nd sanitation in Gorgol, Guid l coût imakha and Assaba 16/PI/PSEA/2021 / Recrutem Component 3: Institutional S Sélection fondée s Open - Internationa ent Assistance Technique UC IDA / D5710 upport, Capacity Building an A posteriori ur la qualité et le 0.00 Annulé 2021-02-23 2021-02-18 2021-03-16 2021-04-29 2021-05-27 2021-06-26 2021-07-31 2021-09-04 2022-09-04 l P/Agences d'Exécution d Project Management coût Component 1: Improvement 16/S/PSEA/2021 / Recruteme Sélection fondée s of access to drinking water a Open - Internationa nt Assistance Technique UCP IDA / D5710 A posteriori ur la qualité et le 0.00 Signé 2021-02-26 2021-02-24 2021-03-19 2021-03-24 2021-05-02 2021-06-30 2021-05-30 2021-10-29 2021-06-29 2021-10-29 2021-08-03 2022-02-09 2021-09-07 2022-03-17 2022-09-07 nd sanitation in Gorgol, Guid l /Agences d'Exécution coût imakha and Assaba 21/PI/PSEA/2022 / Recrutem Component 1: Improvement Sélection fondée s ent de trois ONG chargées de of access to drinking water a En cours d'exécut IDA / D5710 A posteriori ur les qualification Open - National 0.00 2022-05-25 2023-06-27 2022-06-15 2022-07-29 2022-08-28 2022-10-02 2023-03-31 mener les campagnes de sen nd sanitation in Gorgol, Guid ion s des consultants sibilisation imakha and Assaba Component 2: Improving sus 22/PI/PSEA/2022 / Recrutem tainable access to safe wate Sélection fondée s ent de deux ONG chargées d En cours d'exame IDA / D5710 r and sanitation for refugees A posteriori ur les qualification Open - National 0.00 2022-09-14 2023-02-17 2022-10-05 2022-11-18 2022-12-18 2023-01-22 2023-07-21 e mener les campagnes de s n and host communities in Ho s des consultants ensibilisation dh Echargui and Hodh El Gh arbi 17/PI/PSEA/2021 / Recruter l Component 1: Improvement Sélection fondée s es ONG et mener les campag of access to drinking water a IDA / D5710 A priori ur les qualification Open - National 0.00 Annulé 2022-06-07 2022-06-28 2022-08-11 2022-09-10 2022-10-15 2023-04-13 nes de sensibilisation (compo nd sanitation in Gorgol, Guid s des consultants sante 1.2 et 2.2) imakha and Assaba Component 2: Improving sus 01/PI/PSEA/2022 / Elaborer l tainable access to safe wate Sélection fondée s es études pour l'assainissem En attente d'exéc IDA / D5710 r and sanitation for refugees A posteriori ur les qualification Open - National 0.00 2022-08-10 2022-08-31 2022-10-14 2022-11-13 2022-12-18 2023-06-16 ent pluvial du camp de Mberr ution and host communities in Ho s des consultants é dh Echargui and Hodh El Gh arbi Component 3: Institutional S Sélection fondée s 02/PI/S/PSEA/2022 / Audit or Open - Internationa IDA / D5710 upport, Capacity Building an A posteriori ur la qualité et le 0.00 Signé 2022-07-07 2022-06-20 2022-07-28 2022-09-15 2022-01-01 2022-10-20 2022-12-05 2022-11-19 2022-12-16 2023-01-05 2023-02-10 2023-02-09 2023-03-20 2023-06-14 ganisationnel de la SNDE l d Project Management coût Component 3: Institutional S Sélection fondée s 02/PI/PSEA/2022 / Audit orga IDA / D5710 upport, Capacity Building an A posteriori ur les qualification Open - National 0.00 Annulé 2022-06-09 2022-06-14 2022-06-30 2022-08-13 2022-09-12 2022-10-17 2023-04-15 nisationnel de la SNDE d Project Management s des consultants MR-WSSP-329496-CS-QCBS / SELECTION DES CONSULTAN T SUR LA BASE DE QUALITE E T COUT POUR LA REALISATIO N DE L'ETUDE ET ASSURER L Component 4: Contingency Sélection fondée s Open - Internationa E CONTROLE DES TRAVAUX IDA / D5710 Emergency Response Comp A priori ur la qualité et le 0.00 Annulé 2022-12-15 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2024-06-25 l ETUDE onent coût APD ET DAO SELECTION DES L4ENTREPRI SE DE TRAVAUX CONTROLE Component 1: Improvement MR-WSSP-336560-CS-CQS / Sélection fondée s of access to drinking water a En cours d'exame Recrutement de firme pour él IDA / D5710 A posteriori ur les qualification Open - National 0.00 2023-01-20 2023-02-07 2023-02-10 2023-03-26 2023-04-25 2023-05-30 2023-11-26 nd sanitation in Gorgol, Guid n aboration de NIES forages s des consultants imakha and Assaba Page 3 Component 1: Improvement 23/PI/PSEA/2023 / Recrutem Sélection fondée s of access to drinking water a En attente d'exéc ent de firme pour élaboration IDA / D5710 A posteriori ur les qualification Open - National 0.00 2023-09-15 2023-10-06 2023-11-19 2023-12-19 2024-01-23 2024-07-21 nd sanitation in Gorgol, Guid ution de NIES forages s des consultants imakha and Assaba 24/PI/PSEA/2023 / Recrutem Component 3: Institutional S Sélection fondée s En attente d'exéc ent de cabinet de consultant IDA / D5710 upport, Capacity Building an A posteriori ur les qualification Open - National 0.00 2024-02-26 2024-03-18 2024-05-01 2024-05-31 2024-07-05 2024-10-03 ution pour élaboration d’un invent d Project Management s des consultants aire ONSER MR-WSSP-394972-CS-CQS / Component 1: Improvement Recrutement d’une ONG part Sélection fondée s of access to drinking water a En cours d'exécut enaire de mise en œuvre du IDA / D5710 A posteriori ur les qualification Limited 0.00 2023-12-15 2024-01-09 2023-12-29 2024-01-28 2024-03-03 2024-08-30 nd sanitation in Gorgol, Guid ion programme de prévention et s des consultants imakha and Assaba d’atténuation des risques de VBG-EAS/HS MR-WSSP-394982-CS-CQS / Component 3: Institutional S Sélection fondée s Recrutement de trois ONG ch En cours d'exécut IDA / D5710 upport, Capacity Building an A posteriori ur les qualification Open - National 0.00 2024-02-05 2024-03-25 2024-02-26 2024-04-10 2024-05-10 2024-06-14 2024-10-12 argées de mener les campag ion d Project Management s des consultants nes de sensibilisation au ca mp de Mberra MR-WSSP-394987-CS-QCBS / Component 3: Institutional S Sélection fondée s Recrutement de cabinet de c En attente d'exéc IDA / D5710 upport, Capacity Building an A posteriori ur la qualité et le Open - National 0.00 2024-02-19 2024-03-11 2024-04-24 2024-05-22 2024-06-21 2024-07-26 2024-08-30 2025-02-26 onsultants pour élaboration d ution d Project Management coût ’un audit technique et financi er et RH ONSER Component 2: Improving sus MR-WSSP-394996-CS-CQS / tainable access to safe wate Sélection fondée s Recrutement de firmes pour En attente d'exéc IDA / D5710 r and sanitation for refugees A posteriori ur les qualification Open - National 0.00 2024-02-26 2024-03-18 2024-05-01 2024-05-31 2024-07-05 2024-11-02 élaboration de EIES 2 centres ution and host communities in Ho s des consultants SNDE dh Echargui and Hodh El Gh arbi INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Institutional S 01/PI/PSEA/2020 / Recrutem IDA / D5710 upport, Capacity Building an A posteriori Individuel Open 0.00 Signé 2020-12-24 2020-06-19 2021-02-11 2020-06-23 2021-03-04 2020-07-27 2021-04-08 2020-09-22 2021-10-05 ent RAF UCP d Project Management Component 3: Institutional S 02/PI/PSEA/2020 / Recrutem IDA / D5710 upport, Capacity Building an A posteriori Individuel Open 0.00 Signé 2020-12-24 2020-06-19 2021-02-11 2020-06-22 2021-03-04 2020-07-27 2021-04-08 2020-09-23 2021-10-05 ent SPM UCP d Project Management Component 3: Institutional S 03/PI/PSEA/2020 / Recrutem IDA / D5710 upport, Capacity Building an A posteriori Individuel Open 0.00 Signé 2020-12-24 2020-06-19 2021-02-11 2020-06-22 2021-03-04 2021-07-27 2021-04-08 2020-09-22 2021-10-05 ent Assistant SPM UCP d Project Management 04/PI/PSEA/2020 / Recrutem Component 3: Institutional S ent Spécialiste Environneme IDA / D5710 upport, Capacity Building an A posteriori Individuel Open 0.00 Signé 2020-12-23 2021-01-17 2021-02-10 2021-02-17 2021-03-03 2021-02-23 2021-04-07 2021-02-27 2021-10-04 nt - Santé - Sécurité d Project Management 05/PI/PSEA/2020 / Recrutem Component 3: Institutional S ent Spécialiste des Questions IDA / D5710 upport, Capacity Building an A posteriori Individuel Open 0.00 Signé 2020-12-23 2021-01-17 2021-02-10 2021-02-23 2021-03-03 2021-02-23 2021-04-07 2021-02-26 2021-10-04 Sociales et Genre d Project Management Component 3: Institutional S 06/PI/PSEA/2021 / Recrutem IDA / D5710 upport, Capacity Building an A posteriori Individuel Open 0.00 Signé 2021-01-07 2021-01-27 2021-02-25 2021-03-31 2021-03-18 2021-03-31 2021-04-22 2021-04-08 2021-10-19 ent Auditeur Interne d Project Management Component 3: Institutional S 08/PI/PSEA/2021 / Recrutem IDA / D5710 upport, Capacity Building an A posteriori Individuel Open 0.00 Signé 2021-01-28 2021-01-27 2021-03-18 2021-03-31 2021-04-08 2021-03-31 2021-05-13 2021-04-07 2021-11-09 ent comptable d Project Management Component 3: Institutional S 09/PI/PSEA/2021 / Recrutem IDA / D5710 upport, Capacity Building an A posteriori Individuel Open 0.00 Signé 2021-01-28 2021-01-27 2021-03-18 2021-03-31 2021-04-08 2021-03-31 2021-05-13 2021-04-08 2021-11-09 ent Assisante de Direction d Project Management Component 3: Institutional S 10/PI/PSEA/2021 / Recrutem IDA / D5710 upport, Capacity Building an A posteriori Individuel Open 0.00 Annulé 2021-03-15 2021-05-03 2021-05-24 2021-06-28 2021-12-25 ent Logisticien d Project Management 11/PI/PSEA/2021 / Recrutem Component 3: Institutional S ent des jeunes diplômés com En attente d'exéc IDA / D5710 upport, Capacity Building an A posteriori Individuel Open 0.00 2021-04-12 2021-05-31 2021-06-21 2021-07-26 2022-01-22 me stagiaires(en lieu et plac ution d Project Management e d'agents administratifs et d e suivi) Component 3: Institutional S 18/PI/PSEA/2021 / Recrutem IDA / D5710 upport, Capacity Building an A posteriori Individuel Limited 0.00 Annulé 2021-04-12 2021-04-17 2021-05-08 2021-06-12 2021-12-09 ent chauffeurs d Project Management Component 3: Institutional S 19/PI/PSEA/2021 / Recrutem IDA / D5710 upport, Capacity Building an A posteriori Individuel Limited 0.00 Annulé 2021-02-10 2021-02-15 2021-03-08 2021-04-12 2021-10-09 ent Gardiens d Project Management Component 3: Institutional S 20/PI/PSEA/2021 / Recrutem IDA / D5710 upport, Capacity Building an A posteriori Individuel Limited 0.00 Annulé 2021-02-09 2021-02-14 2021-03-07 2021-04-11 2021-10-08 ent Plantons d Project Management MR-WSSP-394970-CS-INDV / Component 3: Institutional S En cours d'exécut Recrutement d’un Gestionnai IDA / D5710 upport, Capacity Building an A posteriori Individuel Limited 0.00 2023-12-11 2024-05-07 2023-12-16 2024-01-06 2024-02-10 2025-02-09 ion re 2 de contrat d Project Management MR-WSSP-394971-CS-INDV / Component 3: Institutional S En cours d'exécut Recrutement d’un assistant d IDA / D5710 upport, Capacity Building an A posteriori Individuel Limited 0.00 2023-12-11 2023-12-18 2023-12-16 2024-01-06 2024-02-10 2025-02-09 ion u spécialiste en Passation de d Project Management s Marchés MR-WSSP-394997-CS-CDS / Component 2: Improving sus Elaboration de NIES pour réh tainable access to safe wate Sélection de cons Direct - Internation En attente d'exéc abilitation du réseau et des b IDA / D5710 r and sanitation for refugees A posteriori ultants par entent 0.00 2024-01-30 2024-02-09 2024-04-14 2024-06-13 al ution oues de vidange du camp MB and host communities in Ho e directe erra dh Echargui and Hodh El Gh arbi MR-WSSP-431948-CS-INDV / Component 3: Institutional S Recrutement d'un hydrogéol En attente d'exéc IDA / D5710 upport, Capacity Building an A posteriori Individuel Open - National 0.00 2024-07-04 2024-08-22 2024-09-12 2024-10-17 2025-04-15 ogue expert en évaluation et ution d Project Management cartographie des ressources en eau Page 4