PROCUREMENT PLAN (Textual Part) Project information: Republic of Marshall Islands Sustainable Energy Development Project P160096 & P163699 Project Implementation agency: PREP2 PMU, Division of International Development Assistance-Ministry of Finance (DIDA-MOF), and SPC-Pacific Community Date of the Procurement Plan: May 10, 2018 Period covered by this Procurement Plan: May 1, 2018 to Nov 30, 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Code of 1988, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The procurement is open to all eligible firms from any country; 2. The request for bids/request for proposals document shall require the Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting signed contracts, confirming application of, and compliance with, the Bank's Anti- Corruption Guidelines, including without limitation the Bank's right to sanction and the Bank's inspection and audit rights; 3. Publication of contract award information; 4. Rights for the Bank to review procurement documentation and activities; and 5. An effective complaints mechanism. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Work) Goods: is not applicable; Works: is not applicable. PROCUREMENT Marshall Islands : Pacific Resilience Project II under the Pacific Resilience Program PLAN General Information Country: Marshall Islands 2018-10-21 Bank’s Approval Date of the Original Procurement Plan: 2023-03-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160096 GPN Date: 2018-06-19 Project Name: Pacific Resilience Project II under the Pacific Resilience Program Loan / Credit No: IDA / D1830, IDA / V0410 Project Implementation Unit, PREP II Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MH-PREP II-PIU-83439-CW-R Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E 2020-07-1 FB / NDMO Building Refurbish IDA / D1830 trengthening, Early Warning Post 750,000.00 0.00 Canceled 2019-11-23 2020-01-18 tions l nvelope 6 ment and Preparedness MH-PREP II-PIU-81920-CW-R Component 2: Strengthening Request for Propo Open - Internationa 35,312,500.0 2023-10-2 IDA / D1830 Prior Multi Stage 0.00 Canceled 2020-12-31 2021-01-05 2021-03-16 2021-06-28 2021-08-02 FP / Coastal Protection Works Coastal Resilience sals l 0 1 Request for Bids - MH-PREP II-PIU-239881-CW- Component 2: Strengthening Open - Internationa Single Stage - Two E 36,987,473.0 Under Imple 2024-02-0 IDA / D1830 Prior Request for Bids Works SPD (after 0.00 2021-12-01 2022-05-20 2022-02-16 2022-02-16 2021-12-06 2022-07-13 2022-04-27 2022-07-10 2022-08-14 RFB / Coastal Protection Wor Coastal Resilience l nvelope 0 mentation 5 prequalification) ks MH-PREP II-PIU-119118-CW- Component 1: Institutional S RFQ / Support for NDMO Stre Open - Internationa Single Stage - One E 2021-06-2 IDA / D1830 trengthening, Early Warning Prior Request for Bids 1,050,000.00 0.00 Canceled 2020-09-06 2020-09-11 2020-10-23 2020-11-22 2020-12-27 ngthening as per NDMO Roa l nvelope 5 and Preparedness dmap including NDMO Refurb ishment Works. MH-PREP II-PIU-252921-GO- Component 1: Institutional S RFQ / Support for NDMO Stre Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-11-1 IDA / D1830 trengthening, Early Warning Post Open - National 400,000.00 0.00 2023-03-27 2023-05-22 ngthening as per NDMO Roa tions nvelope or explanation) lementation 8 and Preparedness dmap including NDMO Refurb ishment Works GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-83438-GO-RF Component 4: Project and Pr Request for Quota Single Stage - One E Q / Office Equipment includin IDA / D1830 Post Open - National 61,000.00 0.00 Canceled 2019-08-05 2019-09-30 2020-03-28 ogram Management tions nvelope g Computers MH-PREP II-PIU-252918-GO- Component 4: Project and Pr Request for Quota Single Stage - One E RFQ / Office Equipment inclu IDA / D1830 Post Open - National 61,000.00 0.00 Signed 2021-10-05 2021-11-03 2021-11-30 2022-05-29 ogram Management tions nvelope ding Computers MH-PREP II-PIU-252920-GO- Component 1: Institutional S RFQ / Supply of IT equipment Request for Quota Single Stage - One E IDA / D1830 trengthening, Early Warning Post Open - National 50,000.00 39,155.87 Signed 2021-10-20 2021-11-11 2021-12-15 2022-07-14 2022-06-13 , outdoor equipment & office tions nvelope and Preparedness furniture under the NDMO Ro admap MH-PREP II-PIU-163821-GO- Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 40,000.00 0.00 Canceled 2020-05-05 2020-06-30 2020-12-27 RFB / Project Vehicle ogram Management tions nvelope MH-PREP II-PIU-301507-GO- Component 4: Project and Pr Request for Quota Single Stage - One E Under Imple IDA / D1830 Post Open - National 50,000.00 0.00 2022-07-20 2023-03-02 2022-09-14 2023-03-13 RFQ / Project Vehicle Resubm ogram Management tions nvelope mentation ission MH-PREP II-PIU-83436-GO-RF Component 1: Institutional S Open - Internationa Single Stage - One E Q / Emergency Communicati IDA / D1830 trengthening, Early Warning Prior Request for Bids 1,100,000.00 0.00 Canceled 2022-01-03 2022-01-08 2022-02-19 2022-03-21 2022-04-25 2022-10-22 l nvelope on Equipment Supply & Com and Preparedness mission MH-PREP II-PIU-347314-GO- Component 1: Institutional S Request for Quota Single Stage - One E Pending Impl RFQ / VHF Emergency Comm IDA / D1830 trengthening, Early Warning Post Limited 218,400.00 0.00 2023-03-12 2023-05-07 2023-11-03 tions nvelope ementation unications Equipment Supply and Preparedness MH-PREP II-PIU-348605-GO- Component 4: Project and Pr Request for Quota Single Stage - One E Pending Impl IDA / D1830 Post Open - National 10,000.00 0.00 2023-03-18 2023-05-13 2023-11-09 RFQ / Supply of Office Furnitu ogram Management tions nvelope ementation re for PIU MH-PREP II-PIU-342614-GO- Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E Pending Impl RFQ / IT Equipment to Suppo IDA / V0410 trengthening, Early Warning Post 48,700.00 0.00 2023-03-05 2023-04-30 2023-10-27 tions l nvelope ementation rt NDMO and Preparedness MH-PREP II-PIU-345824-GO- Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E Pending Impl RFQ / Non-IT Equipment Sup IDA / V0410 trengthening, Early Warning Post 9,900.00 0.00 2023-03-17 2023-05-12 2023-11-08 tions l nvelope ementation port to NDMO and Preparedness NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-81923-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 40,000.00 0.00 Canceled 2019-09-07 2019-11-02 2020-01-31 Q / M and E Satisfaction Surv ogram Management tions nvelope ey MH-PREP II-PIU-81925-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 150,000.00 26,050.00 Signed 2019-07-05 2019-08-30 2021-10-05 2019-10-29 Q / PIU IT Support ogram Management tions nvelope MH-PREP II-PIU-81924-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 20,000.00 0.00 Canceled 2019-10-05 2019-11-30 2019-12-30 Q / Translation Services ogram Management tions nvelope MH-PREP II-PIU-81919-NC-RF Component 2: Strengthening Request for Quota Open - Internationa Single Stage - One E IDA / D1830 Post 250,000.00 0.00 Canceled 2020-04-05 2020-05-31 2020-11-27 Q / UXO Removal Services Coastal Resilience tions l nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-83435-CS-QC Component 2: Strengthening Quality And Cost- Open - Internationa BS / Coastal Engineering Desi IDA / D1830 Prior 3,210,000.00 2,897,518.50 Signed 2018-10-30 2019-01-14 2018-11-20 2019-01-30 2019-01-03 2019-11-05 2019-01-31 2020-02-17 2019-03-02 2020-04-06 2019-04-06 2020-09-07 2019-05-11 2020-10-21 2021-04-30 Coastal Resilience Based Selection l gn & Supervision Firm MH-PREP II-PIU-81918-CS-UN Component 1: Institutional S UN Agencies (Dire / Community DRM and Emerg IDA / D1830 trengthening, Early Warning Prior Direct 500,000.00 500,000.00 Signed 2020-01-09 2021-06-02 2021-12-29 ct) ency Communications Traini and Preparedness ng (IOM-UN) Component 1: Institutional S MH-PREP II-PIU-81916-CS-CQ Consultant Qualifi Open - Internationa IDA / D1830 trengthening, Early Warning Post 190,000.00 0.00 Canceled 2018-11-30 2018-12-21 2019-02-03 2018-11-06 2019-03-05 2019-04-09 2019-08-07 S / NDMO Building Design cation Selection l and Preparedness MH-PREP II-PIU-119121-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / NDMO Structural Analysi IDA / D1830 trengthening, Early Warning Post 190,000.00 0.00 Canceled 2019-06-30 2019-07-21 2019-09-03 2019-10-03 2019-11-07 2020-05-05 cation Selection l s and Refurbishment Design and Preparedness MH-PREP II-PIU-163827-CS-C Component 1: Institutional S Consultant Qualifi QS / NAP Community Consult IDA / D1830 trengthening, Early Warning Prior Limited 500,000.00 0.00 Under Review 2020-05-05 2021-04-11 2020-05-19 2021-09-21 2020-06-18 2022-04-19 2020-07-23 2021-01-19 cation Selection ation and Preparedness MH-PREP II-PIU-110299-CS-C Component 4: Project and Pr Consultant Qualifi IDA / D1830 Post Limited 300,000.00 218,501.11 Signed 2020-04-16 2021-05-31 2020-04-30 2021-09-29 2020-05-30 2022-05-27 2020-07-04 2022-07-17 2020-12-31 QS / Communications and Me ogram Management cation Selection dia Firm MH-PREP II-PIU-217361-CS-Q CBS / Design of New NDMO Component 1: Institutional S Quality And Cost- Open - Internationa Warehouse and Office Accom IDA / D1830 trengthening, Early Warning Prior 550,000.00 0.00 Signed 2021-02-05 2021-09-16 2021-02-26 2021-11-30 2021-04-11 2022-05-01 2021-05-09 2022-06-23 2021-06-08 2022-09-27 2021-07-13 2023-02-12 2021-08-17 2023-03-20 2022-08-17 Based Selection l modation and Structural Anal and Preparedness ysis of the Existing NDMO Bui lding MH-PREP II-PIU-163844-CS-Q Component 1: Institutional S Quality And Cost- Open - Internationa CBS / Vulnerability and Planni IDA / D1830 trengthening, Early Warning Prior 600,000.00 0.00 Canceled 2020-03-17 2020-04-07 2020-05-21 2020-06-18 2020-07-18 2020-08-22 2020-09-26 2021-09-26 Based Selection l ng Consultancy Firm and Preparedness MH-PREP II-PIU-303510-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / Vulnerability and Planni IDA / D1830 trengthening, Early Warning Prior 500,000.00 0.00 Under Review 2022-07-24 2022-07-30 2022-08-14 2022-09-06 2022-09-27 2022-11-09 2022-10-27 2022-12-01 2023-05-30 cation Selection l ng Consultancy Firm and Preparedness MH-PREP II-PIU-163825-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / Community Vulnerability IDA / D1830 trengthening, Early Warning Post 250,000.00 0.00 Canceled 2020-05-03 2020-05-24 2020-07-07 2020-08-06 2020-09-10 2021-03-09 cation Selection l Mapping and Training and Preparedness MH-PREP II-PIU-163847-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa Pending Impleme QS / Climate Financing Techn IDA / D1830 trengthening, Early Warning Post 200,000.00 0.00 2023-06-01 2023-06-22 2023-08-05 2023-09-04 2023-10-09 2024-04-06 cation Selection l ntation ical Assistance and Preparedness INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-81917-CS-CD Component 2: Strengthening S / Coastal Vulnerability Asse IDA / D1830 Prior Direct Selection Direct 500,000.00 592,782.00 Signed 2019-04-04 2019-10-02 2019-04-14 2019-12-10 2019-06-18 2020-03-17 2020-01-10 Coastal Resilience ssment Firm MH-PREP II-PIU-81834-CS-IN Component 1: Institutional S Individual Consult DV / Emergency Communicat IDA / D1830 trengthening, Early Warning Post Open 120,000.00 64,425.00 Terminated 2019-04-30 2019-06-14 2019-06-18 2019-09-19 2019-07-09 2019-11-01 2019-08-13 2019-11-20 2020-06-08 ant Selection ion Specialist and Preparedness MH-PREP II-PIU-81915-CS-CD Component 2: Strengthening IDA / D1830 Prior Direct Selection Direct 50,000.00 0.00 Canceled 2018-11-16 2018-11-26 2019-01-30 2022-11-10 S / Coastal Design Adviser Coastal Resilience Component 1: Institutional S MH-PREP II-PIU-81927-CS-IN Individual Consult IDA / D1830 trengthening, Early Warning Post Open 480,000.00 0.00 Canceled 2018-10-15 2018-12-03 2018-12-24 2019-01-28 2021-01-17 DV / DRM and CCA Adviser ant Selection and Preparedness MH-PREP II-PIU-81928-CS-IN Component 1: Institutional S Individual Consult DV / Disaster and Climate Ris IDA / D1830 trengthening, Early Warning Post Open 202,500.00 0.00 Canceled 2018-10-15 2018-12-03 2018-12-24 2019-01-28 2021-01-17 ant Selection k Governance Adviser and Preparedness MH-PREP II-PIU-81926-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Limited 180,000.00 0.00 Canceled 2018-12-28 2019-01-02 2019-01-23 2019-02-27 2019-08-26 DV / Ebeye Project Represent Coastal Resilience ant Selection ative Component 1: Institutional S MH-PREP II-PIU-109655-CS-I Individual Consult IDA / D1830 trengthening, Early Warning Prior Open 324,000.00 648,000.00 Signed 2018-05-01 2018-01-03 2018-06-19 2018-08-24 2018-07-10 2018-09-27 2018-08-24 2018-09-27 2020-12-31 NDV / DRM&CCA Adviser ant Selection and Preparedness MH-PREP II-PIU-109653-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Prior Open 720,000.00 790,313.00 Signed 2017-02-14 2016-11-30 2017-03-28 2017-03-24 2017-04-20 2017-05-01 2017-05-01 2017-05-01 2020-05-14 NDV / Project Manager ogram Management ant Selection MH-PREP II-PIU-109656-CS-I Component 2: Strengthening Individual Consult IDA / D1830 Post Open 80,280.00 80,280.00 Completed 2018-04-18 2018-05-31 2018-06-06 2018-05-24 2018-06-27 2018-05-24 2018-07-31 2018-07-31 2020-07-01 NDV / Ebeye Project Represe Coastal Resilience ant Selection ntative MH-PREP II-PIU-109654-CS-I Component 1: Institutional S Individual Consult NDV / Disaster and Climate R IDA / D1830 trengthening, Early Warning Prior Open 206,750.00 602,200.00 Signed 2018-04-01 2018-02-01 2018-05-20 2019-08-06 2018-06-10 2018-09-14 2018-07-13 2018-09-14 2020-08-31 ant Selection isk Governance Adviser and Preparedness MH-PREP II-PIU-81838-CS-IN Component 4: Project and Pr Individual Consult DV / Communications & Medi IDA / D1830 Prior Open 240,000.00 0.00 Canceled 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2021-03-04 ogram Management ant Selection a Specialist MH-PREP II-PIU-110300-CS-I Component 1: Institutional S Individual Consult NDV / Strategic Emergency C IDA / D1830 trengthening, Early Warning Post Open 80,000.00 135,100.00 Completed 2019-07-30 2019-06-14 2019-09-17 2019-09-19 2019-10-08 2019-11-01 2019-11-12 2019-11-20 2020-05-10 ant Selection ommunications Adviser and Preparedness MH-PREP II-PIU-81832-CS-IN Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 30,000.00 0.00 Canceled 2020-03-01 2020-04-19 2020-05-10 2020-06-14 2020-08-13 DV / Mid-term Reviewer ogram Management ant Selection MH-PREP II-PIU-81841-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 150,000.00 0.00 Canceled 2019-09-30 2020-02-18 2019-11-18 2019-12-09 2020-01-13 2020-07-11 DV / Value Engineering Coastal Resilience ant Selection MH-PREP II-PIU-137152-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Prior Open 480,000.00 13,022.00 Terminated 2020-05-16 2020-02-17 2020-07-04 2020-05-14 2020-07-25 2020-08-02 2020-08-29 2020-08-10 2021-02-25 NDV / Project Manager Post 2 ogram Management ant Selection 020 MH-PREP II-PIU-109652-CS-I Component 2: Strengthening Individual Consult IDA / D1830 Post Open 470,000.00 470,000.00 Signed 2017-10-25 2017-10-31 2017-11-01 2017-11-07 2017-11-19 2017-11-15 2017-12-20 2018-01-09 2020-01-31 NDV / Original Civil Engineeri Coastal Resilience ant Selection ng Advisor Page 2 MH-PREP II-PIU-160075-CS-C Component 2: Strengthening IDA / D1830 Post Direct Selection Direct 150,000.00 154,975.00 Signed 2020-02-19 2020-03-05 2020-02-24 2020-04-17 2020-04-29 2020-06-17 2021-10-31 DS / Value Engineering Firm Coastal Resilience MH-PREP II-PIU-110298-CS-I Component 4: Project and Pr Individual Consult NDV / Local Communications IDA / D1830 Post Open 230,000.00 112,879.67 Terminated 2020-03-19 2020-05-19 2020-05-07 2020-09-14 2020-05-28 2020-10-15 2020-07-02 2020-11-03 2020-12-29 ogram Management ant Selection and M & E Officer MH-PREP II-PIU-81835-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 80,000.00 0.00 Canceled 2020-04-01 2020-05-20 2020-06-10 2020-07-15 2021-07-10 DV / Work Probity Assurance Coastal Resilience ant Selection Provider Component 1: Institutional S MH-PREP II-PIU-163845-CS-I Individual Consult IDA / D1830 trengthening, Early Warning Post Open 100,000.00 0.00 Canceled 2020-05-02 2021-03-23 2020-06-20 2020-07-11 2020-08-15 2021-02-11 NDV / NAP Coordinator ant Selection and Preparedness MH-PREP II-PIU-163848-CS-I Component 1: Institutional S Individual Consult NDV / Donor Coordination Te IDA / D1830 trengthening, Early Warning Prior Open 400,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 ant Selection chnical Assistance and Preparedness MH-PREP II-PIU-137154-CS-I Component 2: Strengthening Individual Consult NDV / Ebeye Project Represe IDA / D1830 Post Limited 100,000.00 0.00 Canceled 2020-07-01 2020-07-06 2020-07-27 2020-08-31 2021-02-27 Coastal Resilience ant Selection ntative Post 2020 MH-PREP II-PIU-81837-CS-IN Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 180,000.00 0.00 Canceled 2019-07-30 2019-09-23 2019-09-17 2019-10-08 2019-11-12 2023-07-22 DV / Project Officer ogram Management ant Selection MH-PREP II-PIU-135263-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 190,000.00 0.00 Canceled 2019-09-27 2019-12-02 2019-11-15 2019-12-06 2020-01-10 2020-07-08 NDV / Implementation Suppo ogram Management ant Selection rt Specialist MH-PREP II-PIU-119120-CS-I Component 1: Institutional S Individual Consult NDV / Civil Engineering Advis IDA / D1830 trengthening, Early Warning Prior Open 470,000.00 0.00 Canceled 2019-08-19 2020-02-10 2019-10-07 2019-10-28 2019-12-02 2020-05-30 ant Selection er and Preparedness MH-PREP II-PIU-165685-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 255,000.00 70,000.00 Signed 2020-04-17 2019-12-16 2020-06-05 2020-06-09 2020-06-26 2020-06-09 2020-07-31 2020-06-09 2021-01-27 NDV / Project Officer ogram Management ant Selection MH-PREP II-PIU-165691-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 305,000.00 180,000.00 Terminated 2019-12-15 2019-12-01 2020-02-02 2020-01-09 2020-02-23 2020-02-01 2020-03-29 2020-02-10 2020-09-25 NDV / Implementation Suppo ogram Management ant Selection rt Specialist MH-PREP II-PIU-165694-CS-I Component 1: Institutional S Individual Consult NDV / Civil Engineering Advis IDA / D1830 trengthening, Early Warning Prior Open 770,000.00 734,375.00 Signed 2020-03-23 2020-05-06 2020-05-11 2020-04-24 2020-06-01 2020-07-27 2020-07-06 2020-08-04 2021-01-02 ant Selection er and Preparedness MH-PREP II-PIU-163846-CS-I Component 1: Institutional S Individual Consult NDV / Climate Change Adapt IDA / D1830 trengthening, Early Warning Prior Open 300,000.00 303,000.00 Terminated 2020-05-02 2020-05-06 2020-06-20 2020-07-09 2020-07-11 2020-08-11 2020-08-15 2020-08-15 2021-02-11 ant Selection ation Specialist and Preparedness MH-PREP II-PIU-202148-CS-C Component 4: Project and Pr IDA / D1830 Prior Direct Selection Direct 480,000.00 442,000.00 Under Review 2020-10-30 2020-11-20 2020-11-03 2020-12-01 2020-11-06 2021-01-07 2022-11-05 DS / PREP II Project Manager ogram Management 2021 MH-PREP II-PIU-205222-CS-C Component 4: Project and Pr DS / Project Management Su IDA / D1830 Prior Direct Selection Direct 86,820.00 82,200.00 Signed 2020-11-20 2020-12-22 2020-11-30 2021-02-09 2020-12-15 2021-03-09 2021-06-13 ogram Management pport Specialist Component 1: Institutional S MH-PREP II-PIU-234808-CS-C IDA / D1830 trengthening, Early Warning Post Direct Selection Direct 100,000.00 83,625.00 Signed 2021-05-22 2021-07-01 2021-06-01 2021-08-23 2021-08-05 2021-09-02 2022-02-01 DS / NAP Coordinator and Preparedness MH-PREP II-PIU-246795-CS-I Component 1: Institutional S Individual Consult Under Implement NDV / Disaster and Climate R IDA / D1830 trengthening, Early Warning Prior Open 400,000.00 0.00 2021-08-09 2021-10-11 2021-09-27 2022-03-30 2021-10-18 2022-04-23 2021-11-22 2022-05-21 ant Selection ation esilience Donor Coordination and Preparedness Adviser Component 1: Institutional S MH-PREP II-PIU-81836-CS-IN Individual Consult IDA / D1830 trengthening, Early Warning Post Open 60,000.00 0.00 Signed 2019-04-28 2022-06-23 2019-06-16 2023-02-19 2019-07-07 2023-02-19 2019-08-11 2019-11-09 DV / DRM Legislative Drafter ant Selection and Preparedness MH-PREP II-PIU-228529-CS-I Component 1: Institutional S Individual Consult NDV / Donor Coordination Te IDA / D1830 trengthening, Early Warning Prior Direct 400,000.00 0.00 Canceled 2021-04-30 2021-08-16 2021-05-10 2021-05-31 2021-07-05 2022-01-01 ant Selection chnical Assistance and Preparedness MH-PREP II-PIU-257808-CS-I Component 4: Project and Pr Individual Consult Under Implement NDV / Implementation Suppo IDA / D1830 Post Open 190,000.00 0.00 2021-10-31 2022-02-03 2021-12-19 2022-11-10 2022-01-09 2022-07-13 2022-02-13 2022-08-12 ogram Management ant Selection ation rt Specialist 2022 MH-PREP II-PIU-81840-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 120,000.00 0.00 Canceled 2019-11-30 2020-01-18 2020-02-08 2020-03-14 2020-09-10 DV / Contracts Disputes Boar Coastal Resilience ant Selection d Member MH-PREP II-PIU-301513-CS-I Component 1: Institutional S NDV / Senior Emergency Co Individual Consult IDA / V0410 trengthening, Early Warning Post Direct 80,000.00 0.00 Signed 2022-07-08 2022-07-14 2022-07-18 2022-08-11 2022-08-08 2022-08-16 2022-09-12 2023-03-11 mmunications Network Com ant Selection and Preparedness missioning Specialist MH-PREP II-PIU-137153-CS-I Component 1: Institutional S Individual Consult NDV / DRM&CCA Adviser pos IDA / D1830 trengthening, Early Warning Prior Open 324,000.00 0.00 Canceled 2021-01-01 2021-02-19 2021-03-12 2021-04-16 2021-10-13 ant Selection t 2020 and Preparedness MH-PREP II-PIU-327141-CS-C Component 1: Institutional S Direct - Internation DS / Climate Change Adaptat IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 Canceled 2022-11-23 2022-12-02 2022-12-03 2022-12-20 2023-02-06 2023-08-05 al ion Specialist 2023 and Preparedness MH-PREP II-PIU-301516-CS-I Component 1: Institutional S NDV / Junior Emergency Com Individual Consult IDA / D1830 trengthening, Early Warning Post Open 50,000.00 0.00 Canceled 2022-10-01 2022-11-19 2022-12-10 2023-01-14 2023-07-13 munications Network Commi ant Selection and Preparedness ssioning Specialist MH-PREP II-PIU-347593-CS-I Component 4: Project and Pr Individual Consult NDV / Communication and M IDA / D1830 Post Open - National 30,000.00 0.00 Under Review 2023-03-07 2023-02-13 2023-04-25 2023-05-16 2023-06-20 2023-12-17 ogram Management ant Selection onitoring & Evaluations Offic er MH-PREP II-PIU-81839-CS-IN Component 4: Project and Pr Individual Consult Open - Internationa Pending Impleme IDA / D1830 Post 30,000.00 0.00 2023-06-01 2023-07-20 2023-08-10 2023-09-14 2024-03-12 DV / End Term Reviewer ogram Management ant Selection l ntation MH-PREP II-PIU-81831-CS-IN Component 1: Institutional S Individual Consult Open - Internationa Pending Impleme DV / Change Management Ad IDA / D1830 trengthening, Early Warning Prior 480,000.00 0.00 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2021-03-04 ant Selection l ntation visor and Preparedness Page 3 MH-PREP II-PIU-327137-CS-C Component 1: Institutional S DS / Disaster and Climate Re Direct - Internation IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 Canceled 2022-11-23 2022-12-02 2022-12-03 2022-12-19 2023-02-06 2023-08-05 silience Donor Coordination A al and Preparedness dviser (DCR-DCA) 2023 MH-PREP II-PIU-327141-CS-C Component 1: Institutional S Direct - Internation Pending Impleme DS-2 / Climate Change Adapt IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 2023-03-16 2023-03-26 2023-05-30 2023-11-26 al ntation ation Specialist 2023 and Preparedness Page 4