PROCUREMENT PLAN (Textual Part) Project information: Bangladesh: Exports Competitiveness for Jobs (EC4J), P156113 Project Implementation agency: Ministry of Commerce (MoC) Date of the Procurement Plan: September 18, 2017 Period covered by this Procurement Plan: from September 2017 to June 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules 2008, as amended in August 2009), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a) e-GP system of the country for national competitive bidding (NCB) shall be followed using Standard/Model Procurement documents satisfactory to the Bank b) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; c) Bids should be submitted and opened in public in one location immediately after the deadline for submission; d) Lottery in award of contracts shall not be allowed; e) Bidders’ qualification/experience requirement shall be mandatory f) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Bangladesh : Export Competitiveness for Jobs PLAN General Information Country: Bangladesh 2017-09-18 Bank’s Approval Date of the Original Procurement Plan: 2023-07-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156113 GPN Date: 2017-09-17 Project Name: Export Competitiveness for Jobs Loan / Credit No: IDA / 60420 Ministry of Commerce Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned W6-2 / Construction of Boun dary Wall and Gates for Gene 3. Public Investment Facility Single Stage - One E 2022-02-2 ral Engineering Technology C IDA / 60420 for Infrastructure Constraint Post Request for Bids Open - National 300,000.00 279,371.18 Signed 2021-04-20 2021-05-27 2021-04-25 2021-05-16 2021-06-21 2021-05-30 2021-08-31 2021-06-27 2021-09-22 nvelope 2 enter-2 (GETC-2) at Bangaba s ndhu Hi-Tech City, Kaliakoir, Gazipur. W6-3 / Construction of Boun 3. Public Investment Facility dary Wall and Gates for Desi Single Stage - One E 2022-04-2 IDA / 60420 for Infrastructure Constraint Post Request for Bids Open - National 500,000.00 505,469.14 Signed 2021-04-19 2021-10-27 2021-04-24 2021-05-15 2021-11-25 2021-05-29 2021-12-31 2021-07-03 2022-01-07 gn and Technology Center (D nvelope 9 s TC) at Kashimpur, Gazipur. W6-1 / Construction of Boun National Procure dary Wall and Gates for Gene 3. Public Investment Facility ment Document - Single Stage - One E 2022-10-3 ral Engineering Technology C IDA / 60420 for Infrastructure Constraint Post Request for Bids Open - National 1 Envelope proce 750,000.00 725,674.98 Signed 2021-10-13 2021-05-27 2021-10-18 2021-11-15 2021-06-28 2021-11-29 2021-08-31 2022-01-03 2021-09-22 nvelope 0 enter-1 (GETC-1) at Bangaba s ss (Non Bank-SPD ndhu Sheikh Mujib Industrial ) City, Mirsarai, Chattogram. W6-5 / Development of Six S National Procure toried Academic Building and 3. Public Investment Facility ment Document - Single Stage - One E 2023-03-3 Infrastructures for ‘Banglade IDA / 60420 for Infrastructure Constraint Post Request for Bids Open - National 1 Envelope proce 1,822,000.00 0.00 Canceled 2021-12-15 2022-03-22 2021-12-20 2022-01-17 2022-04-20 2022-02-16 2022-03-30 nvelope 0 sh Institute of Plastic Enginee s ss (Non Bank-SPD ring and Technology (BIPET)’ ) W 6-5 / Development of Six National Procure Storied Academic Building an 3. Public Investment Facility ment Document - Single Stage - One E 1,660,024.5 2023-06-3 d Infrastructures for Banglad IDA / 60420 for Infrastructure Constraint Post Request for Bids Open - National 1 Envelope proce 1,822,000.00 Signed 2022-05-12 2022-05-17 2022-05-17 2022-05-31 2022-06-01 2022-06-21 2022-06-20 2022-07-05 2022-06-27 nvelope 5 0 esh Institute of Plastic Engine s ss (Non Bank-SPD ering and Technology (BIPET) ) W4 / Construction of Bangab Request for Bids - andhu Design & Technology 2. Productivity Enhancement Open - Internationa Single Stage - One E Works (without pr 15,250,000.0 Under Imple 2025-03-1 IDA / 60420 Prior Request for Bids 0.00 2023-02-16 2023-03-09 2023-03-09 2023-03-14 2023-04-20 2023-05-02 2023-06-04 2023-07-23 Center for Leathergoods and Program l nvelope equalification) SP 0 mentation 4 Footwear (BDTCLF), Kashimp D ur, Gazipur. W2 / Construction of Center Request for Bids - of Excellence for Engineering 2. Productivity Enhancement Open - Internationa Single Stage - One E Works (without pr 20,450,000.0 Under Imple 2025-03-1 IDA / 60420 Prior Request for Bids 0.00 2023-02-16 2023-03-13 2023-03-09 2023-03-14 2023-04-20 2023-05-02 2023-06-04 2023-07-23 and Technology (CEET) at Ba Program l nvelope equalification) SP 0 mentation 4 ngabandhu Hi-Tech City, Kali D akoir, Gazipur. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GD8 / Office furniture, equip 4. Project Management, Mon Single Stage - One E IDA / 60420 Post Request for Bids Open - National 190,000.00 161,304.61 Signed 2018-01-04 2018-05-15 2018-01-09 2018-02-20 2018-05-31 2018-03-22 2018-06-21 2018-04-26 2018-07-19 2018-07-25 ment and decoration itoring & Evaluation nvelope GD4 / Stationaries for Projec 4. Project Management, Mon Single Stage - One E IDA / 60420 Post Request for Bids Open - National 19,000.00 0.00 Canceled 2017-11-30 2017-12-05 2017-12-19 2017-12-29 2018-02-02 2019-02-02 t Office itoring & Evaluation nvelope GD-09 / Procurement of Four 4. Project Management, Mon Request for Quota Single Stage - One E (04) Laptop Computer & One IDA / 60420 Post Limited 6,330.00 5,857.52 Signed 2018-03-16 2018-04-05 2018-05-11 2018-04-19 2018-11-07 itoring & Evaluation tions nvelope (01) Multi Function Printer GD-10 / Supply and Installati 4. Project Management, Mon Request for Quota Single Stage - One E IDA / 60420 Post Limited 6,330.00 5,655.99 Signed 2018-05-11 2018-05-10 2018-06-15 2018-05-17 2018-12-12 on of office Furniture for the itoring & Evaluation tions nvelope Project Office GD-11 / Supply and Installati 4. Project Management, Mon Request for Quota Single Stage - One E on of Office Equipment for th IDA / 60420 Post Limited 6,330.00 0.00 Canceled 2018-05-12 2018-06-16 2018-12-13 itoring & Evaluation tions nvelope e Office of PIU GD-12 / Supply and Installati 4. Project Management, Mon Request for Quota Single Stage - One E on of Split Type Air condition IDA / 60420 Post Limited 6,330.00 5,918.50 Signed 2018-05-11 2018-05-10 2018-06-15 2018-05-17 2018-12-12 itoring & Evaluation tions nvelope er (AC) for the PIU Office G2-3 / Office equipments for 2. Productivity Enhancement Single Stage - One E Pending Impl IDA / 60420 Post Request for Bids Open - National 49,000.00 0.00 2023-05-28 2023-06-02 2023-06-16 2023-06-17 2023-07-22 2024-01-18 BIPET Program nvelope ementation G2-4 / Furniture & Fixtures f 2. Productivity Enhancement Single Stage - One E Pending Impl IDA / 60420 Post Request for Bids Open - National 34,000.00 0.00 2023-05-28 2023-06-02 2023-06-16 2023-06-30 2023-07-28 2024-01-24 or BIPET Program nvelope ementation G8-1 / Supply and Installatio 4. Project Management, Mon Single Stage - One E Pending Impl n of Desktop, Laptop Comput IDA / 60420 Post Request for Bids Open - National 24,000.00 0.00 2023-05-28 2023-06-02 2023-06-16 2023-06-30 2023-07-28 2024-01-24 itoring & Evaluation nvelope ementation ers, Printers and office equip ment's. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GD1 / Hiring of office space f 4. Project Management, Mon Single Stage - One E IDA / 60420 Post Request for Bids Open - National 270,000.00 211,321.01 Signed 2017-10-15 2018-01-22 2017-10-20 2018-02-13 2017-11-19 2018-02-20 2018-01-03 2018-03-22 2018-02-07 2018-04-19 2023-06-30 or PIU itoring & Evaluation nvelope GD2-3 / Hiring three Vehicle 4. Project Management, Mon Single Stage - Two E IDA / 60420 Post Request for Bids Open - National 278,481.00 246,459.41 Signed 2017-12-07 2018-10-14 2017-12-14 2018-01-08 2018-11-08 2018-04-20 2018-11-14 2018-05-14 2018-12-13 2023-06-30 s-SUV-01nos and Microbus-0 itoring & Evaluation nvelope 2nos. Page 1 NCS-01 / Hiring a Passenger 4. Project Management, Mon Request for Quota Single Stage - One E Vehicle ( 8 Seated) for Short- IDA / 60420 Post Limited 6,330.00 5,527.35 Signed 2018-03-16 2018-03-18 2018-05-11 2018-03-27 2018-11-07 itoring & Evaluation tions nvelope term (3/4 Months) on monthl y rental basis S-27 / Video awareness Cam 1. Market Access Support Pr IDA / 60420 Post Direct Selection Direct 36,000.00 26,255.75 Signed 2018-07-05 2018-07-01 2018-07-10 2018-07-02 2018-08-21 2018-07-10 2019-02-17 paign for Leather Sector ogram S-30 / TV Broadcasting of Vi 1. Market Access Support Pr deo Documentary and Scrolli IDA / 60420 Post Direct Selection Direct 50,000.00 40,556.58 Signed 2018-07-26 2018-08-01 2018-07-29 2018-08-06 2018-08-12 2018-08-09 2018-12-10 ogram ng of Key Messages to Redu ce Flay-cuts S 12-5 / International Plastic, Packaging, and Printing Indus trial Fair (IPF-2023) in Collab 1. Market Access Support Pr Under Imple IDA / 60420 Post Direct Selection Direct - National 95,000.00 0.00 2023-02-12 2023-02-09 2023-02-17 2023-02-09 2023-03-15 2023-09-11 oration with Bangladesh Plas ogram mentation tic Goods Manufacturers & E xporters Association (BPGME A). S12-6 / Selection of Event M anagement Firm for organizi ng ‘Bangladesh Business Su 1. Market Access Support Pr Pending Impl IDA / 60420 Post Direct Selection Direct - National 110,000.00 0.00 2023-02-26 2023-02-28 2023-03-08 2023-05-07 mmit 2023’ in Partnership wi ogram ementation th the Federation of Banglad esh Chambers of Commerce and Industry (FBCCI). S12-7 / Selection of Event M anagement Firm for Organizi 1. Market Access Support Pr Pending Impl ng ‘International Light Engine IDA / 60420 Post Direct Selection Direct - National 90,000.00 0.00 2023-02-27 2023-03-04 2023-03-14 2023-09-10 ogram ementation ering Expo -2023’ in Collabor ation with Light Engineering Sector Association. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S15 / Selection of ERF Mana 1. Market Access Support Pr Quality And Cost- Open - Internationa IDA / 60420 Prior 1,645,570.00 0.00 Canceled 2018-01-11 2018-03-02 2018-03-30 2018-04-27 2018-05-27 2018-07-01 2018-08-05 2023-06-30 gement Firm ogram Based Selection l S24 / Export Readiness Fund 1. Market Access Support Pr Quality And Cost- Open - Internationa (ERF) Manger for matching gr IDA / 60420 Prior 2,000,000.00 3,284,390.73 Signed 2018-05-14 2018-05-09 2018-06-08 2018-06-04 2018-07-30 2018-08-16 2018-08-27 2018-10-02 2018-09-26 2018-12-03 2018-10-31 2019-08-09 2018-12-05 2019-09-30 2022-05-18 ogram Based Selection l ant program S17 / Market Prioritization, E 3. Public Investment Facility Quality And Cost- Open - Internationa ngineering Design and Super IDA / 60420 for Infrastructure Constraint Prior 4,400,000.00 5,070,462.24 Signed 2018-05-30 2018-05-15 2018-06-20 2018-05-21 2018-08-08 2018-08-13 2018-09-09 2018-10-03 2018-10-14 2018-12-03 2018-11-22 2019-08-09 2018-12-27 2019-11-27 2022-12-31 Based Selection l vision of Cluster Infrastructur s e S29 / Feasibility Study of Tec 2. Productivity Enhancement Quality And Cost- Open - Internationa hnology Centres for Light (Ge IDA / 60420 Post 215,000.00 258,325.50 Signed 2018-07-18 2018-07-28 2018-08-15 2018-09-05 2018-09-12 2018-11-04 2018-10-10 2018-12-18 2018-10-17 2019-01-15 2018-10-31 2019-05-02 2018-12-05 2019-09-12 2019-12-05 Program Based Selection l neral) Engineering Sector in Bangladesh S33 / Production of 'Project I 1. Market Access Support Pr Consultant Qualifi ntroduction Video Document IDA / 60420 Post Limited 25,000.00 21,769.28 Signed 2018-09-26 2018-10-04 2018-10-10 2018-10-22 2018-11-09 2018-11-21 2018-12-14 2019-01-17 2019-06-12 ogram cation Selection ary' for EC4J Project S51 / Selection of Consultant 4. Project Management, Mon Consultant Qualifi IDA / 60420 Post Limited 55,000.00 66,101.72 Signed 2018-12-04 2018-12-09 2018-12-04 2019-01-03 2019-01-01 2019-01-23 2019-01-15 2019-02-06 2020-01-15 for ICT Solutions itoring & Evaluation cation Selection S50 / Staging Theater, Gamv ira and Folksongs for Industr 1. Market Access Support Pr Consultant Qualifi IDA / 60420 Post Limited 40,000.00 35,384.38 Signed 2019-02-03 2019-01-10 2019-02-17 2019-01-29 2019-03-03 2019-02-13 2019-03-17 2019-02-20 2019-07-15 y Level Awareness on Enviro ogram cation Selection nment, Social and Quality Co mpliances (ESQ) S45 / TV Broadcasting of Vid eo Documentary and Scrollin g of Key Messages before Eid 1. Market Access Support Pr Consultant Qualifi -ul-Adha 2019 to Reduce Flay IDA / 60420 Post Limited 52,000.00 50,810.17 Signed 2019-06-03 2019-06-13 2019-06-17 2019-07-07 2019-06-24 2019-07-16 2019-07-15 2019-07-18 2019-09-13 ogram cation Selection -cuts of the Raw Hides and W aste Management of Leather, Leather Goods and Footwear Sector. S53 / Consultancy Services f or Design and Supervision (D 2. Productivity Enhancement Quality And Cost- Open - Internationa &S) for the Establishment of IDA / 60420 Prior 1,700,000.00 1,616,573.25 Signed 2019-11-11 2019-12-05 2019-12-02 2019-12-09 2020-01-15 2020-04-17 2020-02-12 2020-06-29 2020-03-13 2020-09-02 2020-04-17 2020-11-26 2020-05-22 2020-12-18 2023-05-22 Program Based Selection l Technology Centers under Ex port Competitiveness for Jobs (EC4J) Project S46 / Consulting Services to Develop Environmental, Soci al and Quality (ESQ) Training 1. Market Access Support Pr Quality And Cost- Modules, Conduct ToT and C IDA / 60420 Post Open - National 205,000.00 204,477.62 Signed 2020-04-16 2020-05-07 2020-05-06 2020-06-19 2020-08-31 2020-07-17 2020-09-29 2020-08-16 2020-11-30 2020-09-20 2020-12-07 2020-10-25 2020-12-28 2021-10-25 ogram Based Selection ertification for Leather, Leath er Goods, Footwear, Plastics and Light Engineering Sector s in Bangladesh S47 / Consulting Services to Conduct Specialized Training on Environmental, Social and 1. Market Access Support Pr Fixed Budget Sele IDA / 60420 Post Open - National 230,000.00 234,374.15 Signed 2020-04-16 2020-05-07 2020-05-07 2020-06-20 2020-08-31 2020-07-18 2020-09-30 2020-08-17 2020-11-30 2020-09-21 2020-12-09 2020-10-26 2020-12-28 2022-04-19 Quality (ESQ) for Leather, Le ogram ction ather Goods, Footwear, Plasti cs and Light Engineering sect ors in Bangladesh S48 / Consulting Services to design and establish Market I 1. Market Access Support Pr Quality And Cost- Open - Internationa ntelligence System (Researc IDA / 60420 Prior 700,000.00 0.00 Canceled 2020-05-05 2020-07-07 2020-05-26 2020-07-08 2020-07-09 2021-03-23 2020-08-06 2021-05-12 2020-09-05 2021-08-24 2020-10-10 2020-11-14 2023-05-03 ogram Based Selection l h, Database, Maintenance) fo r the four targeted sectors un der EC4J Project S49 / Consulting Services of Market Development & Bran 1. Market Access Support Pr Quality And Cost- IDA / 60420 Post Open - National 425,000.00 431,952.62 Signed 2020-05-05 2020-06-25 2020-05-18 2020-07-01 2020-11-30 2020-07-29 2020-12-30 2020-08-28 2021-01-28 2020-10-02 2021-03-04 2020-11-06 2021-03-29 2023-04-25 ding for the four targeted sec ogram Based Selection tors under EC4J Project S52 / Consulting Services to showcase Bangladesh at the 1. Market Access Support Pr Quality And Cost- international sourcing show/t IDA / 60420 Post Open - National 465,000.00 471,324.75 Signed 2020-05-05 2020-06-24 2020-05-20 2020-07-03 2020-11-30 2020-07-31 2020-12-30 2020-08-30 2021-01-28 2020-10-04 2021-03-04 2020-11-08 2021-03-29 2023-04-27 ogram Based Selection rade events for the four targ eted sectors under EC4J Proje ct Page 2 S50-1 / Broadcasting of TVC through Television Channels and Social Media Campaign o n Key Messages before the Ei 1. Market Access Support Pr Consultant Qualifi IDA / 60420 Post Limited 50,000.00 51,481.06 Signed 2020-07-09 2020-07-10 2020-07-16 2020-07-21 2020-07-19 2020-07-23 2020-07-24 2020-07-25 2020-10-22 d-ul-Adha 2020 to ensure he ogram cation Selection alth safety measures, reduce flay-cut of the raw hides and environment friendly waste management S50-2 / Broadcasting of TVC through Television Channels and Social Media Campaign o n Key Messages before the Ei 1. Market Access Support Pr Consultant Qualifi IDA / 60420 Post Limited 55,000.00 50,693.44 Signed 2021-05-05 2021-05-16 2021-05-19 2021-06-16 2021-06-03 2021-06-27 2021-07-01 2021-06-30 2021-10-29 d-ul-Adha 2021 to ensure he ogram cation Selection alth safety measures, reduce flay-cut of the raw hides and environment friendly waste management. S50-3 / Awareness building Campaign (Broadcasting of T 1. Market Access Support Pr Consultant Qualifi Under Implement VC through Television Chann IDA / 60420 Post Limited 55,000.00 0.00 2022-06-09 2022-06-07 2022-06-16 2022-06-19 2022-06-29 2022-10-27 ogram cation Selection ation els and Social Media Campai gn on Key Messages before t he Eid-ul-Adha 2022) S11-1 / Awareness Campaig n through Television Channel s and Social Media on Key Me 1. Market Access Support Pr Consultant Qualifi Pending Impleme ssages before the Eid-ul-Adh IDA / 60420 Post Limited 49,400.00 0.00 2023-05-28 2023-06-07 2023-06-10 2023-06-16 2023-12-13 ogram cation Selection ntation a to ensure safety measures, reduce flay-cut of the raw hid es and environment friendly waste management. S12-8.1 / Organizing Sourcin 1. Market Access Support Pr Consultant Qualifi Pending Impleme g Show in collaboration with IDA / 60420 Post Limited 95,000.00 0.00 2023-07-27 2023-08-10 2023-08-20 2023-08-30 2023-10-29 ogram cation Selection ntation Leather Sector Association. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual S1 / Financial management 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 280,000.00 238,140.62 Signed 2017-09-10 2018-01-24 2017-11-27 2018-04-23 2017-12-14 2018-05-30 2018-01-18 2018-06-07 2021-01-17 Specialist (FMS) itoring & Evaluation ant Selection S2 / Procurement Specialist ( 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 275,000.00 238,140.62 Signed 2017-09-30 2018-01-29 2017-12-18 2018-04-23 2018-01-08 2018-05-30 2018-02-12 2018-06-07 2021-02-11 PS) itoring & Evaluation ant Selection S3 / Monitoring and Evaluati 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 265,900.00 232,419.53 Signed 2017-09-30 2018-01-08 2017-11-23 2018-04-23 2017-12-08 2018-05-30 2018-01-08 2018-06-05 2023-06-30 on Specialist itoring & Evaluation ant Selection S5 / Environmental Manage 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 53,000.00 47,628.12 Signed 2018-02-18 2018-02-22 2018-04-08 2018-05-07 2018-04-29 2018-06-07 2018-06-03 2018-06-12 2018-11-30 ment Specialist itoring & Evaluation ant Selection S6 / Social Management Spe 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 50,000.00 44,338.49 Signed 2018-02-18 2018-02-22 2018-04-08 2018-04-23 2018-04-29 2018-06-07 2018-06-03 2018-06-11 2018-11-30 cialist itoring & Evaluation ant Selection S4 / Technical Specialist(Mec 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 215,000.00 141,785.91 Signed 2018-03-28 2019-03-27 2018-05-16 2019-05-29 2018-06-06 2019-05-30 2018-07-11 2019-07-01 2019-01-07 hanical/Electrical/Chemical E itoring & Evaluation ant Selection ngineer) 1. Market Access Support Pr Individual Consult S21 / Project Manager IDA / 60420 Post Limited 266,000.00 149,112.43 Signed 2018-04-15 2018-04-19 2018-04-20 2018-04-20 2018-05-04 2018-04-24 2018-06-01 2018-04-30 2023-07-15 ogram ant Selection S22 / Component Coordinato 1. Market Access Support Pr Individual Consult IDA / 60420 Post Limited 213,000.00 80,186.13 Signed 2018-04-15 2018-03-22 2018-04-20 2018-06-20 2018-05-04 2018-06-20 2018-06-01 2018-07-01 2023-07-07 r (Market Access) ogram ant Selection S23 / Component Coordinato 2. Productivity Enhancement Individual Consult IDA / 60420 Post Limited 213,000.00 79,479.59 Signed 2018-04-15 2018-09-13 2018-04-20 2018-09-19 2018-05-04 2018-10-10 2018-06-02 2018-10-25 2023-07-17 r (Productivity Enhancement) Program ant Selection S-25 / Land Management Sp 4. Project Management, Mon Individual Consult IDA / 60420 Post Limited 80,000.00 0.00 Canceled 2018-07-08 2018-07-13 2018-08-03 2018-09-07 2019-03-06 ecialist itoring & Evaluation ant Selection S-26 / Short Term Consultan 4. Project Management, Mon Individual Consult IDA / 60420 Post Limited 7,300.00 0.00 Canceled 2018-07-03 2018-07-08 2018-07-29 2018-09-02 2019-03-01 t DPP Revision itoring & Evaluation ant Selection S28 / Industry wise Awarene 1. Market Access Support Pr ss building Plan and Training IDA / 60420 Post Direct Selection Direct 83,133.00 80,850.94 Signed 2018-08-29 2018-09-20 2018-09-08 2018-09-26 2018-11-12 2018-10-17 2019-05-11 ogram Need Assessment (GAP analy sis) by BFTI S30 / Coordination and Com munication Consultation for L 1. Market Access Support Pr IDA / 60420 Post Direct Selection Direct 149,909.64 137,708.07 Signed 2018-08-29 2020-06-02 2018-09-08 2020-07-23 2018-11-12 2020-11-04 2022-06-30 eather , leather goods & Foot ogram wear Sector by Leather Secto r BPC S31 / Coordination and Com munication Consultation for L 1. Market Access Support Pr IDA / 60420 Post Direct Selection Direct 171,325.30 152,800.57 Signed 2018-08-29 2020-06-02 2018-09-08 2020-06-07 2018-11-12 2020-11-04 2022-06-30 ight Engineering and Electro ogram nics Sector by Light Enginee ring Sector BPC S32 / Coordination and Com 1. Market Access Support Pr munication Consultation for P IDA / 60420 Post Direct Selection Direct 107,078.31 99,464.52 Signed 2018-08-29 2020-06-02 2018-09-08 2020-07-23 2018-11-12 2020-11-04 2022-06-30 ogram lastics Sector by Plastics Sect or BPC S43 / Component Coordinato 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 150,000.00 79,479.59 Signed 2019-04-04 2019-04-01 2019-05-07 2019-05-23 2019-05-21 2019-05-29 2019-06-25 2019-06-16 2022-06-09 r-3 itoring & Evaluation ant Selection S44 / Monitoring and Evaluat 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 190,000.00 172,974.56 Signed 2019-05-09 2019-05-06 2019-06-11 2019-07-25 2019-06-25 2019-07-28 2019-07-23 2019-08-14 2023-03-22 ion (M&E) Specialist itoring & Evaluation ant Selection S5-1 / Environmental Manag 4. Project Management, Mon Individual Consult IDA / 60420 Post Direct 100,000.00 94,635.91 Signed 2019-05-28 2019-05-29 2019-06-07 2019-06-13 2019-06-14 2019-06-13 2019-06-28 2019-08-28 2021-06-27 ement Specialist itoring & Evaluation ant Selection S6-1 / Social Management S 4. Project Management, Mon Individual Consult IDA / 60420 Post Direct 100,000.00 94,635.91 Signed 2019-05-28 2019-05-29 2019-06-07 2019-06-13 2019-06-14 2019-06-13 2019-06-28 2019-08-28 2021-06-27 pecialist itoring & Evaluation ant Selection S54 / Land Management Spe 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 40,000.00 39,613.29 Signed 2019-08-31 2019-09-01 2019-10-19 2019-10-09 2019-11-09 2019-10-10 2019-12-14 2019-11-21 2020-12-13 cialist itoring & Evaluation ant Selection Page 3 4. Project Management, Mon Individual Consult S55 / Procurement Specialist IDA / 60420 Post Open 60,000.00 54,634.60 Signed 2019-08-30 2020-08-17 2019-10-18 2020-12-22 2019-11-08 2020-12-22 2019-12-13 2020-12-28 2021-12-12 itoring & Evaluation ant Selection S56 / Executive Officer (Adm 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 60,000.00 56,024.51 Signed 2019-08-31 2019-09-01 2019-10-19 2019-10-14 2019-11-09 2019-11-26 2019-12-14 2019-12-25 2021-12-13 in & Finance) itoring & Evaluation ant Selection S57 / Executive Officer (ICT 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 60,000.00 56,590.42 Signed 2019-08-31 2019-09-01 2019-10-19 2019-10-09 2019-11-09 2019-10-10 2019-12-14 2019-10-15 2021-12-13 & Logistics) itoring & Evaluation ant Selection S58 / Executive Officer (Com 4. Project Management, Mon Individual Consult IDA / 60420 Post Open 60,000.00 55,175.66 Signed 2019-08-31 2019-09-01 2019-10-19 2019-10-14 2019-11-09 2019-10-15 2019-12-14 2019-10-29 2021-12-13 munications & Public Relatio itoring & Evaluation ant Selection ns) S65 / Short Term M&E Consu 4. Project Management, Mon Individual Consult IDA / 60420 Post Limited 20,000.00 17,686.59 Signed 2020-04-26 2020-06-14 2020-05-05 2020-06-21 2020-05-26 2020-06-22 2020-06-30 2020-07-16 2021-06-30 ltant itoring & Evaluation ant Selection S22-1 / Component Coordina 4. Project Management, Mon Individual Consult IDA / 60420 Post Direct 95,000.00 89,140.41 Signed 2020-06-28 2020-06-25 2020-07-02 2020-07-07 2020-07-04 2020-07-14 2020-07-14 2020-07-16 2022-07-04 tor-1 (Market Access) itoring & Evaluation ant Selection S23-1 / Component Coordina 4. Project Management, Mon Individual Consult tor-2 (Productivity Enhancem IDA / 60420 Post Direct 95,000.00 89,140.41 Signed 2020-06-28 2020-07-07 2020-07-02 2020-07-12 2020-07-07 2020-07-14 2020-07-21 2020-07-16 2022-07-11 itoring & Evaluation ant Selection ent Program) 4. Project Management, Mon Individual Consult Under Implement S4-1 / Technical Specialist IDA / 60420 Post Open 90,000.00 0.00 2020-08-12 2020-08-17 2020-09-30 2020-10-21 2020-11-25 2022-09-16 itoring & Evaluation ant Selection ation S43-1 / Component Coodinat 4. Project Management, Mon Individual Consult IDA / 60420 Post Direct 90,000.00 0.00 Under Review 2021-08-05 2021-05-17 2021-08-15 2021-08-19 2021-08-29 2023-06-30 or-3 itoring & Evaluation ant Selection 4. Project Management, Mon Individual Consult Pending Impleme S21-1 / Project Manager IDA / 60420 Post Open 95,000.00 0.00 2021-08-05 2021-09-07 2021-09-14 2021-09-28 2023-07-01 itoring & Evaluation ant Selection ntation S12-4 / Selection of Event M anagement Firm for Organizi ng ‘Bangladesh Trade and In 1. Market Access Support Pr IDA / 60420 Post Direct Selection Direct 115,000.00 0.00 Under Review 2021-10-13 2021-10-13 2021-10-14 2021-10-17 2021-11-16 vestment Summit’ in Collabo ogram ration with Dhaka Chamber o f Commerce & Industry (DCCI ). S46-1 / Consulting Services t o impart Basic Environmental , Social and Quality (ESQ) Tra 1. Market Access Support Pr ining through Respective Sec IDA / 60420 Post Direct Selection Direct 240,000.00 208,740.11 Signed 2021-12-02 2021-12-02 2021-12-07 2022-01-16 2021-12-30 2022-04-05 2022-12-30 ogram tor Associations for Leather, Leather Goods, Footwear, Pla stics and Light Engineering S ectors in Bangladesh S5-2 / Environmental Manag 4. Project Management, Mon Individual Consult IDA / 60420 Post Direct 25,000.00 21,026.05 Signed 2022-02-02 2022-02-13 2022-02-04 2022-02-13 2022-02-06 2022-02-14 2022-02-11 2022-03-02 2022-08-10 ement Specialist itoring & Evaluation ant Selection S6-2 / Social Management S 4. Project Management, Mon Individual Consult IDA / 60420 Post Direct 25,000.00 21,029.37 Signed 2022-02-02 2022-02-01 2022-02-04 2022-02-13 2022-02-06 2022-03-14 2022-02-11 2022-03-02 2022-08-10 pecialist itoring & Evaluation ant Selection S3-1 / Monitoring and Evalua 4. Project Management, Mon Individual Consult Pending Impleme IDA / 60420 Post Open 60,000.00 0.00 2022-02-20 2022-03-24 2022-03-27 2022-04-06 2023-06-30 tion (M&E) Specialist itoring & Evaluation ant Selection ntation S43-2 / Component Coodinat 4. Project Management, Mon Individual Consult Pending Impleme IDA / 60420 Post Open 57,000.00 0.00 2022-02-20 2022-03-28 2022-03-31 2022-04-06 2023-06-30 or-3 itoring & Evaluation ant Selection ntation S30-2 / Consultant for Coordi 4. Project Management, Mon Individual Consult nation of Market Access Supp IDA / 60420 Post Direct 40,000.00 38,011.06 Signed 2022-05-25 2022-05-25 2022-06-01 2022-05-26 2022-06-08 2022-06-20 2022-06-18 2022-07-08 2023-06-18 itoring & Evaluation ant Selection ort Program S30-3 / Consultant for Coordi 4. Project Management, Mon Individual Consult nation of Productivity Enhanc IDA / 60420 Post Direct 30,000.00 27,292.83 Signed 2022-05-25 2022-05-25 2022-06-15 2022-05-26 2022-07-06 2022-06-20 2022-08-24 2022-07-08 2023-05-21 itoring & Evaluation ant Selection ement Program S30-1 / BIPET Works Supervi 4. Project Management, Mon Individual Consult Pending Impleme IDA / 60420 Post Limited 15,000.00 0.00 2022-10-06 2022-10-20 2022-11-03 2022-12-08 2023-06-06 sion Engineer itoring & Evaluation ant Selection ntation S12-5 / 'Bangladesh Plastic, Packaging & Printing Showca sing in Malaysia 2022’ in Coll 1. Market Access Support Pr IDA / 60420 Post Direct Selection Direct - National 95,000.00 0.00 Canceled 2022-10-06 2022-10-16 2022-11-22 2023-02-20 aboration with Bangladesh Pl ogram astic Goods Manufacturers & Exporters Association (BPGM EA). S1-1 / Financial Managemen 4. Project Management, Mon Individual Consult Pending Impleme IDA / 60420 Post Open - National 79,920.00 0.00 2023-05-31 2023-07-03 2023-07-10 2023-07-31 2024-01-27 t Specialist itoring & Evaluation ant Selection ntation S 3-1 / Monitoring & Evaluati 4. Project Management, Mon Individual Consult Pending Impleme IDA / 60420 Post Open - National 78,000.00 0.00 2023-05-30 2023-07-02 2023-07-09 2023-07-21 2025-06-30 on Specialist itoring & Evaluation ant Selection ntation 4. Project Management, Mon Individual Consult Pending Impleme S4-2 / Technical Specialist IDA / 60420 Post Open - National 79,920.00 0.00 2023-05-30 2023-07-02 2023-07-09 2023-07-23 2025-06-30 itoring & Evaluation ant Selection ntation S5-3 / Environmental Manag 4. Project Management, Mon Individual Consult Pending Impleme IDA / 60420 Post Open - National 79,920.00 0.00 2023-05-28 2023-06-26 2023-06-29 2023-07-09 2025-06-30 ement Specialist (Assignmen itoring & Evaluation ant Selection ntation t Based) S6-3 / Social Management S 4. Project Management, Mon Individual Consult Pending Impleme IDA / 60420 Post Open - National 79,920.00 0.00 2023-05-30 2023-07-02 2023-07-09 2023-07-23 2025-06-30 pecialist (Assignment Based) itoring & Evaluation ant Selection ntation S56-1 / Executive Officer (Ac 4. Project Management, Mon Individual Consult Pending Impleme IDA / 60420 Post Open - National 48,000.00 0.00 2023-05-28 2023-06-30 2023-07-07 2023-07-17 2025-06-30 counts & Finance) itoring & Evaluation ant Selection ntation S 30-1 / Junior Consultant-El 4. Project Management, Mon Individual Consult Pending Impleme IDA / 60420 Post Open - National 48,000.00 0.00 2023-05-28 2023-06-17 2023-06-18 2023-07-09 2025-06-30 ectrical (Assignment Based) itoring & Evaluation ant Selection ntation Page 4