Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other July 9, 2010 methods July 9, 2010 PROCUREMENT Kenya : Kenya Youth Employment and Opportunities PLAN General Information Country: Kenya 2017-02-12 Bank’s Approval Date of the Original Procurement Plan: 2023-03-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151831 GPN Date: 2017-04-03 Project Name: Kenya Youth Employment and Opportunities Loan / Credit No: IDA / 58120 Ministry of Public Service, Youth and Gender Affairs Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MPYG-12189-GO-RFB / Pr Strengthening youth policy d Single Stage - One E Under Imple IDA / 58120 Post Request for Bids Open - National 700,000.00 0.00 2017-04-07 2017-09-15 2017-04-12 2017-05-24 2017-06-23 2017-07-28 2018-01-24 ocurement of Motor Vehicles. evelopment and project man nvelope mentation agement KE-MPYG-12022-GO-RFQ / S Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl upply and delivery of interim IDA / 58120 evelopment and project man Post Limited 75,000.00 0.00 2017-05-17 2017-07-12 2018-01-08 tions nvelope ementation MIS equipment agement KE-MPYG-12182-GO-RFQ / Pr Strengthening youth policy d ocurement of equipment for Request for Quota Single Stage - One E Pending Impl IDA / 58120 evelopment and project man Post Limited 5,300.00 0.00 2017-04-30 2017-06-25 2017-12-22 PCU (Boardroom Chairs and L tions nvelope ementation agement ockable Cabinets) KE-MPYG-14305-GO-RFQ / Pr Strengthening youth policy d Single Stage - One E Pending Impl ocurement of ICT equipment IDA / 58120 evelopment and project man Post Request for Bids Open - National 150,000.00 0.00 2017-08-07 2017-08-12 2017-09-23 2017-10-23 2017-11-27 2018-05-26 nvelope ementation for PCU and targeted Countie agement s. KE-MPYG-53596-GO-RFQ / Pr Strengthening youth policy d Request for Quota Single Stage - One E ocurement of 40 No tablets f IDA / 58120 evelopment and project man Post Limited 16,000.00 13,793.11 Signed 2018-05-02 2018-11-15 2018-06-27 2019-05-08 2018-12-24 tions nvelope or capturing data for Cycle 2 agement KE-MPYG-53606-GO-RFQ / Pr Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl ocurement of 20 No. Laptops IDA / 58120 evelopment and project man Post Limited 14,500.00 0.00 2018-05-30 2018-07-25 2019-01-21 tions nvelope ementation for Cycle two counties agement KE-MPYG-88634-GO-RFQ / P Strengthening youth policy d urchase of 40 No of tablets fo Request for Quota Single Stage - One E IDA / 58120 evelopment and project man Post Limited 31,500.00 13,793.11 Signed 2019-01-23 2018-11-15 2019-03-20 2019-06-13 2019-09-16 r Cycle 3 Counties and 30 No tions nvelope agement for Cycle 4 Counties KE-MPYG-88635-GO-RFQ / P Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 5,400.00 0.00 2019-01-30 2019-03-27 2019-09-23 urchase of 10 No tablets(Rug evelopment and project man tions nvelope ementation ged) for PCU agement KE-MPYG-53579-GO-DIR / Pr Strengthening youth policy d Single Stage - One E ocurement of 6 No.Motor Veh IDA / 58120 evelopment and project man Post Request for Bids Open - National 420,000.00 0.00 Canceled 2018-04-13 2018-04-18 2018-05-30 2018-06-29 2018-08-03 2019-01-30 nvelope icles for Cycle 2 counties. agement KE-MPYG-108685-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Under Imple IDA / 58120 Post Limited 2,400.00 0.00 2019-04-17 2019-06-12 2019-12-09 4 No Glass Cabinets evelopment and project man tions nvelope mentation agement KE-MPYG-108687-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 300.00 0.00 2019-04-17 2019-06-12 2019-12-09 1 No. Coffee Table evelopment and project man tions nvelope ementation agement KE-MPYG-108688-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 750.00 0.00 2019-04-17 2019-06-12 2019-12-09 2 No. Secretarial desks evelopment and project man tions nvelope ementation agement KE-MPYG-108689-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 2,960.00 0.00 2019-04-17 2019-06-12 2019-12-09 2 No. Workstation (4 way) evelopment and project man tions nvelope ementation agement KE-MPYG-108690-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 5,600.00 0.00 2019-04-17 2019-06-12 2019-12-09 1 No. Boardroom table 28 se evelopment and project man tions nvelope ementation ater agement KE-MPYG-108691-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 3,600.00 0.00 2019-04-17 2019-06-12 2019-12-09 4 No. Workstation (2 way) evelopment and project man tions nvelope ementation agement KE-MPYG-108692-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 1,000.00 0.00 2019-04-17 2019-06-12 2019-12-09 1 No. Reception desk evelopment and project man tions nvelope ementation agement KE-MPYG-108693-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 1,050.00 0.00 2019-04-17 2019-06-12 2019-12-09 3 No. High Back Orthopedic evelopment and project man tions nvelope ementation Chairs agement KE-MPYG-108694-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 6,860.00 0.00 2019-04-17 2019-06-12 2019-12-09 28 No. Office Chairs evelopment and project man tions nvelope ementation agement KE-MPYG-108695-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 370.00 0.00 2019-04-17 2019-06-12 2019-12-09 2 No. Executive Visitors Chair evelopment and project man tions nvelope ementation agement KE-MPYG-108696-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 720.00 0.00 2019-04-17 2019-06-12 2019-12-09 4 No. Secretarial chairs evelopment and project man tions nvelope ementation agement KE-MPYG-108697-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 630.00 0.00 2019-04-20 2019-06-11 2019-12-08 3 Sets of Visitors Chairs (3 W evelopment and project man tions nvelope ementation ay) agement KE-MPYG-108699-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 475.00 0.00 2019-04-21 2019-06-12 2019-12-09 5 No. Coat hangers evelopment and project man tions nvelope ementation agement KE-MPYG-108700-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 1,440.00 0.00 2019-04-20 2019-06-11 2019-12-08 8 No. Visitors chair evelopment and project man tions nvelope ementation agement KE-MPYG-108701-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 5,040.00 0.00 2019-04-22 2019-06-13 2019-12-10 28 No Boardroom chairs evelopment and project man tions nvelope ementation agement Page 1 KE-MPYG-108702-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl 10 No. Filing metallic Cabinet IDA / 58120 evelopment and project man Post Limited 3,500.00 0.00 2019-04-21 2019-06-12 2019-12-09 tions nvelope ementation with four drawers agement KE-MPYG-108703-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl 5 No. Wooden In and Out tra IDA / 58120 evelopment and project man Post Limited 850.00 0.00 2019-04-21 2019-06-12 2019-12-09 tions nvelope ementation y (4 shelves) with stand agement KE-MPYG-108704-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 1,040.00 0.00 2019-04-21 2019-06-12 2019-12-09 2 Sets of Filling Racks evelopment and project man tions nvelope ementation agement KE-MPYG-108705-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Limited 840.00 0.00 2019-04-23 2019-06-14 2019-12-11 3 No. Water dispensers Hot a evelopment and project man tions nvelope ementation nd Cold agement KE-MPYG-108706-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Supply and fitting of Curtain IDA / 58120 evelopment and project man Post Limited 5,800.00 10,743.67 Signed 2019-04-23 2018-10-16 2019-06-14 2019-05-14 2019-12-11 tions nvelope shears (all offices) - 100 Mtrs agement KE-MPYG-108707-GO-RFQ / Strengthening youth policy d Removal of old Locks and ins Request for Quota Single Stage - One E IDA / 58120 evelopment and project man Post Limited 1,630.00 4,061.46 Signed 2019-04-23 2018-10-16 2019-06-14 2019-05-14 2019-12-11 tallation of new locks for the tions nvelope agement main door, offices and store s - 10 No KE-MPYG-108708-GO-RFQ / I Strengthening youth policy d Request for Quota Single Stage - One E Under Imple IDA / 58120 Post Limited 520.00 0.00 2019-04-22 2019-06-13 2019-12-10 nstallation of 2 No. Grill door evelopment and project man tions nvelope mentation s agement KE-MPYG-108680-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl Executive desk 2.0 m with si IDA / 58120 evelopment and project man Post Limited 11,000.00 0.00 2019-06-22 2019-08-17 2020-02-13 tions nvelope ementation de units and drawers agement KE-MPYG-108681-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl 4 No. Executive desk 1.8 m w IDA / 58120 evelopment and project man Post Limited 38,000.00 0.00 2019-06-23 2019-08-18 2020-02-14 tions nvelope ementation ith side units and drawers agement KE-MPYG-135006-GO-RFQ / Strengthening youth policy d Procurement of 10 No all terr Request for Quota Single Stage - One E IDA / 58120 evelopment and project man Post Limited 4,500.00 25,073.54 Signed 2019-10-30 2019-10-15 2019-12-25 2020-05-17 2020-06-22 ain tyres size 275/70/R16 for tions nvelope agement vehicles attached to Kitui an d Turkana Counties KE-MPYG-135010-GO-RFQ / Procurement of 30 No. of ordi Strengthening youth policy d Request for Quota Single Stage - One E nary tyres size 255/70/R16 fo IDA / 58120 evelopment and project man Post Limited 10,500.00 12,214.38 Signed 2019-10-30 2019-10-15 2019-12-25 2020-03-17 2020-06-22 tions nvelope r vehicles attached to Kiamb agement u,Kisumu,Migori,Mombasa an d Nakuru counties KE-MPYG-135011-GO-RFQ / Strengthening youth policy d Procurement of 15 No. of tyr Request for Quota Single Stage - One E Pending Impl IDA / 58120 evelopment and project man Post Limited 6,750.00 0.00 2019-11-05 2019-12-31 2020-06-28 es size 265/65/R17 for vehicl tions nvelope ementation agement es at the PCU Nairobi. KE-MPYG-135013-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Procurement of 7No. of tyres IDA / 58120 evelopment and project man Post Limited 3,150.00 2,547.57 Signed 2019-11-05 2019-10-15 2019-12-31 2019-12-11 2020-06-28 tions nvelope size 9.5/R17.5 for the KYEOP agement mini bus KE-MPYG-70217-GO-RFB / Pr Strengthening youth policy d Single Stage - One E Pending Impl ocurement of 34 No of Motor IDA / 58120 evelopment and project man Post Request for Bids Open - National 1,350,000.00 0.00 2018-08-31 2018-09-05 2018-10-17 2018-11-16 2018-12-21 2019-06-19 nvelope ementation Vehicles for KYEOP -for all cy agement cles. KE-MPYG-251038-GO-RFQ / Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl Supply, Installation, and Com IDA / 58120 evelopment and project man Post Limited 15,000.00 0.00 2021-09-14 2021-11-09 2022-05-08 tions nvelope ementation missioning of KYEOP New Ser agement vers NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MPYG-12206-NC-RFQ / Pri Strengthening youth policy d Request for Quota Single Stage - One E Pending Impl IDA / 58120 Post Open - National 100,000.00 0.00 2017-04-12 2017-06-07 2017-12-04 nting of Promotional material evelopment and project man tions nvelope ementation s agement KE-MPYG-130596-NC-RFB / P Strengthening youth policy d Single Stage - One E rovision of insurance cover fo IDA / 58120 evelopment and project man Post Request for Bids Limited 169,730.00 1.84 Signed 2019-09-27 2019-11-19 2019-10-02 2019-12-04 2019-11-13 2019-12-04 2019-12-13 2019-03-06 2020-01-17 2020-06-25 2020-07-15 nvelope r LST and CBST trainees - All agement Cycles KE-MPYG-206745-NC-RFQ / Request for Quota Single Stage - One E Business Plan Competition A IDA / 58120 Support for job creation Post Limited 35,000.00 0.00 Canceled 2020-12-08 2021-02-02 2021-08-01 tions nvelope ward Ceremony KE-MPYG-217131-NC-RFQ / Request for Quota Single Stage - One E IDA / 58120 Support for job creation Post Limited 60,000.00 77,275.20 Signed 2021-02-02 2021-01-26 2021-02-21 2021-03-18 2021-03-14 BPC Award Ceremony Firm tions nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MPYG-6162-CS-QCBS / Co Strengthening youth policy d nsultancy Services for develo Quality And Cost- IDA / 58120 evelopment and project man Post Open - National 250,000.00 246,559.14 Signed 2017-02-09 2017-02-16 2017-03-02 2017-04-15 2018-02-01 2017-05-13 2017-06-12 2017-07-17 2018-05-16 2017-08-21 2018-03-30 2018-08-21 pment and design of a Mana Based Selection agement gement Information System ( MIS) KE-MPYG-12239-CS-CQS / Co Strengthening youth policy d nsultancy services for a firm Consultant Qualifi Pending Impleme IDA / 58120 evelopment and project man Post Open - National 13,500.00 0.00 2017-04-07 2017-04-28 2017-06-11 2017-07-11 2017-08-15 2018-02-11 to carry out beneficiary asses cation Selection ntation agement sment on catalytic funds KE-MPYG-12280-CS-CQS / Co nsultancy services for develo Strengthening youth policy d Consultant Qualifi Pending Impleme pment of a communication st IDA / 58120 evelopment and project man Post Open - National 98,000.00 0.00 2017-04-10 2017-05-01 2017-06-14 2017-07-14 2017-08-18 2018-02-14 cation Selection ntation rategy and management of agement major communication events under KYEOP Page 2 KE-MPYG-6667-CS-QCBS / Co nsultancy Services for provisi Strengthening youth policy d Quality And Cost- on of Core Business Skills Tra IDA / 58120 evelopment and project man Prior Open - National 1,400,000.00 0.00 Canceled 2017-02-09 2017-02-21 2017-03-02 2017-04-15 2017-05-13 2017-06-12 2017-07-17 2017-08-21 2018-08-21 Based Selection ining Providers for the Kenya agement Youth Employment and Oppo rtunities Project. KE-MPYG-6658-CS-QCBS / Co nsultancy services for Provisi Strengthening youth policy d Quality And Cost- on of Life Skills Training unde IDA / 58120 evelopment and project man Prior Open - National 1,400,000.00 0.00 Canceled 2017-02-09 2017-02-16 2017-03-02 2017-04-15 2017-05-13 2017-06-12 2017-07-17 2017-08-21 2018-08-21 Based Selection r Kenya Youth Employment a agement nd Opportunities Project. KE-MPYG-14169-CS-QCBS / Strengthening youth policy d Consultancy services for dev Quality And Cost- Open - Internationa IDA / 58120 evelopment and project man Post 350,000.00 296,519.12 Signed 2017-05-05 2017-05-09 2017-05-26 2017-07-09 2017-05-09 2017-08-06 2017-09-05 2017-10-10 2017-11-14 2017-11-28 2018-11-14 elopment of core business sk Based Selection l agement ills training curriculum KE-MPYG-14170-CS-QCBS / Consultancy services for Prov Strengthening youth policy d Quality And Cost- Open - Internationa ision of Life Skills Training un IDA / 58120 evelopment and project man Post 350,000.00 273,245.89 Signed 2017-05-05 2017-05-09 2017-05-26 2017-07-09 2017-05-09 2017-08-06 2017-09-05 2017-10-10 2017-11-14 2017-11-28 2018-11-14 Based Selection l der Kenya Youth Employmen agement t and Opportunities Project. KE-MPYG-52520-CS-FBS / De livery of core business skills t Strengthening youth policy d Fixed Budget Sele Open - Internationa raining to youth selected to p IDA / 58120 evelopment and project man Prior 6,500,000.00 6,398,006.40 Signed 2018-04-06 2018-04-27 2018-04-03 2018-06-10 2018-07-25 2018-07-08 2018-09-05 2018-08-07 2018-09-06 2018-09-11 2018-10-17 2018-10-16 2018-10-31 2019-10-16 ction l articipate in the Kenya Youth agement Employment and Opportuniti es Project (KYEOP) KE-MPYG-52522-CS-FBS / Co Strengthening youth policy d nsultancy Services for Delive Fixed Budget Sele Open - Internationa IDA / 58120 evelopment and project man Prior 6,500,000.00 6,332,196.00 Signed 2018-04-09 2018-04-30 2018-03-29 2018-06-13 2018-08-24 2018-07-11 2018-08-13 2018-08-10 2018-09-06 2018-09-14 2018-10-05 2018-10-19 2018-10-30 2019-10-19 ry of life skills training to you ction l agement th selected to participate in t he KYEOP KE-MPYG-68522-CS-QCBS / Strengthening youth policy d Quality And Cost- Open - Internationa Monitoring of the Kenya Yout IDA / 58120 evelopment and project man Prior 700,000.00 165,341.02 Signed 2018-08-10 2018-08-31 2018-10-23 2018-10-14 2019-02-04 2018-11-11 2018-12-11 2019-05-22 2019-01-15 2019-10-22 2019-02-19 2020-02-05 2020-02-19 Based Selection l h Employment and Opportuni agement ties Project KE-MPYG-68861-CS-QCBS / P Strengthening youth policy d Quality And Cost- Open - Internationa rocurement of a firm to mana IDA / 58120 evelopment and project man Prior 300,000.00 388,084.06 Signed 2018-08-17 2018-09-07 2018-10-26 2018-10-21 2019-02-25 2018-11-18 2018-12-18 2019-07-17 2019-01-22 2020-03-09 2019-02-26 2020-03-31 2020-02-26 Based Selection l ge the innovation challenge agement KE-MPYG-68524-CS-QCBS / Consultancy services of a fir Strengthening youth policy d Quality And Cost- Open - Internationa m to conduct an extensive b IDA / 58120 evelopment and project man Prior 400,000.00 184,631.16 Signed 2018-09-30 2018-10-21 2018-10-14 2018-12-04 2019-02-04 2019-01-01 2019-01-31 2019-05-06 2019-03-07 2019-06-19 2019-04-11 2019-07-19 2020-04-10 Based Selection l eneficiary tracer study of th agement e KYEOP from March 2018 to 2021 KE-MPYG-68867-CS-QCBS / I Strengthening youth policy d mpact Evaluation for Busines Quality And Cost- Open - Internationa IDA / 58120 evelopment and project man Prior 1,300,000.00 2,135,881.04 Signed 2018-09-28 2018-10-19 2018-11-20 2018-12-02 2019-04-10 2018-12-30 2019-01-29 2019-06-03 2019-03-05 2019-10-01 2019-04-09 2019-11-05 2020-04-08 s Plan Competition, Grants a Based Selection l agement nd Business Development Se rvices. KE-MPYG-118557-CS-QCBS / Strengthening youth policy d In-Depth Financial Managem Quality And Cost- IDA / 58120 evelopment and project man Post Open - National 120,000.00 110,573.66 Signed 2019-07-01 2020-03-30 2019-07-22 2019-09-04 2020-05-28 2019-10-02 2020-06-30 2019-11-01 2020-07-07 2019-12-06 2020-01-10 2020-09-23 2021-01-09 ent and Management Inform Based Selection agement ation Systems Review KE-MPYG-149648-CS-CQS / C onsultancy Services for Digit Strengthening youth policy d al Training on Government C Consultant Qualifi IDA / 58120 evelopment and project man Post Open - National 200,000.00 0.00 Canceled 2019-12-27 2020-01-17 2020-01-17 2020-03-01 2020-03-31 2020-05-05 2020-11-01 atalytic Funds and Access to cation Selection agement Government Procurement Op portunities (AGPO) to youth KE-MPYG-164235-CS-QCBS / Consultancy Services for Digi tal Training on Government C Improving youth employabili Quality And Cost- IDA / 58120 Post Open - National 250,000.00 189,973.63 Signed 2020-03-13 2020-03-18 2020-03-27 2020-05-10 2020-05-14 2020-06-07 2020-06-16 2020-07-07 2020-06-23 2020-08-11 2020-06-26 2020-09-15 2020-07-10 2021-09-15 atalytic Funds and Access to ty Based Selection Government Procurement Op portunities (AGPO) to youth KE-MPYG-88626-CS-QCBS / Consultancy Services for Digi Strengthening youth policy d tal Delivery of Government C Quality And Cost- IDA / 58120 evelopment and project man Post Open - National 350,000.00 0.00 Canceled 2019-01-24 2019-04-04 2019-02-14 2019-03-30 2019-04-27 2019-05-27 2019-07-01 2019-08-05 2020-08-04 atalytic Funds and Access to Based Selection agement Government Procurement Op portunities (AGPO) to youth. KE-MPYG-243717-CS-QCBS / Strengthening youth policy d Engagement of a Firm to Con Quality And Cost- Open - Internationa Under Implement IDA / 58120 evelopment and project man Post 450,000.00 0.00 2021-07-23 2021-11-29 2021-08-13 2021-09-26 2021-10-24 2021-11-23 2021-12-28 2022-02-01 2023-02-01 duct Benfeficiary Tracer Stud Based Selection l ation agement ies for Cycle 2, 3, and 5 KE-MPYG-251008-CS-QCBS / Digital Training on Governme Quality And Cost- Under Implement nt Catalytic Funds and Acces IDA / 58120 Support for job creation Post Open - National 160,000.00 0.00 2021-09-10 2021-09-28 2021-10-01 2021-11-14 2021-12-12 2022-01-11 2022-02-15 2022-03-22 2023-03-22 Based Selection ation s to Government Procuremen t Opportunities to Youth KE-MPYG-274020-CS-QCBS / Improving labor market infor Quality And Cost- Provision of Online Job Place IDA / 58120 Post Open - National 250,000.00 0.00 Signed 2022-01-28 2022-01-27 2022-02-18 2022-04-03 2022-03-17 2022-05-01 2022-04-13 2022-05-31 2022-04-26 2022-07-05 2022-05-12 2022-08-09 2022-12-31 mation Based Selection ment Services for KYEOP Ben eficiaries KE-MPYG-321438-CS-QCBS / Improving youth employabili Quality And Cost- Under Implement Assignment 3 - Beneficiary Tr IDA / 58120 Post Open - National 250,000.00 0.00 2022-10-28 2022-10-31 2022-11-11 2022-12-09 2022-12-10 2022-12-24 2023-01-03 2023-01-28 2023-08-21 ty Based Selection ation acer Study for Cycles 5, 6, an d7 KE-MPYG-239154-CS-CQS / P rovision of Online Internship Improving labor market infor Consultant Qualifi IDA / 58120 Post Open - National 250,000.00 0.00 Canceled 2021-06-10 2021-06-28 2021-07-01 2021-08-14 2021-08-31 2021-09-13 2021-10-18 2022-04-16 and Employment Placement mation cation Selection Services For KYEOP Trainees KE-MPYG-348926-CS-QCBS / Improving youth employabili Quality And Cost- Pending Impleme Beneficiary Tracer Studies - A IDA / 58120 Post Open - National 220,000.00 0.00 2023-03-15 2023-04-05 2023-05-03 2023-05-31 2023-06-30 2023-07-21 2023-08-04 2023-10-03 ty Based Selection ntation ssignment 4 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 KE-MPYG-12269-CS-INDV / In Strengthening youth policy d Individual Consult Pending Impleme dividual Consultancy services IDA / 58120 evelopment and project man Post Limited 15,000.00 0.00 2017-04-07 2017-04-12 2017-05-03 2017-06-07 2017-12-04 ant Selection ntation for review of the National Yo agement uth Policy KE-MPYG-12230-CS-CQS / In Strengthening youth policy d Individual Consult Pending Impleme dividual Consultancy services IDA / 58120 evelopment and project man Post Open 25,000.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 ant Selection ntation for Life Skills Training agement KE-MPYG-12237-CS-CQS / Co Strengthening youth policy d nsultancy services for an indi Individual Consult Pending Impleme IDA / 58120 evelopment and project man Post Open 25,000.00 0.00 2017-04-27 2017-06-15 2017-07-06 2017-08-10 2018-02-06 vidual consultant for Core Bu ant Selection ntation agement siness Skills training KE-MPYG-6641-CS-INDV / Co Strengthening youth policy d nsultancy services for prepar Individual Consult IDA / 58120 evelopment and project man Post Open 98,000.00 0.00 Canceled 2017-02-09 2017-03-30 2017-04-20 2017-05-25 2017-11-21 ation of Communication Strat ant Selection agement egy and implementation of m ajor KYEOP events. KE-MPYG-14304-CS-INDV / In Strengthening youth policy d Individual Consult Under Implement dividual Consultancy for dev IDA / 58120 evelopment and project man Post Limited 35,000.00 31,999.99 2017-05-15 2017-05-20 2017-06-10 2017-07-15 2017-07-28 2018-01-11 ant Selection ation elopment of KYEOP interim M agement IS KE-MPYG-12034-CS-CQS / Co Strengthening youth policy d Individual Consult Pending Impleme nsultancy services for a Moni IDA / 58120 evelopment and project man Post Open 72,000.00 0.00 2017-05-18 2017-07-06 2017-07-27 2017-08-31 2018-02-27 ant Selection ntation toring and Evaluation officer. agement KE-MPYG-12033-CS-CQS / Co Strengthening youth policy d nsultancy services for a Proc Individual Consult IDA / 58120 evelopment and project man Prior Open 43,269.00 78,739.90 Signed 2017-05-18 2017-07-06 2017-07-27 2017-08-07 2017-08-31 2017-08-01 2018-02-27 urement Specialist to support ant Selection agement the implementing agencies KE-MPYG-51146-CS-INDV / D esign of an innovation challe Strengthening youth policy d nge for organizations dealing Individual Consult Pending Impleme IDA / 58120 evelopment and project man Post Open 60,000.00 0.00 2018-02-26 2018-04-16 2018-05-07 2018-06-11 2018-12-08 with the hard-to-serve Youth ant Selection ntation agement and Terms of Reference for fi rm that will implement the c hallenge KE-MPYG-77912-CS-CDS / In Strengthening youth policy d dividual Consultant - Procure IDA / 58120 evelopment and project man Prior Direct Selection Direct 60,000.00 106,850.63 Signed 2018-09-28 2018-10-23 2018-10-08 2018-12-12 2019-05-17 2019-06-10 ment support for KYEOP Impl agement ementing Agencies, KE-MPYG-77911-CS-CDS / In Strengthening youth policy d dividual Consultancy - Monito IDA / 58120 evelopment and project man Prior Direct Selection Direct 72,000.00 129,775.49 Signed 2018-09-27 2018-10-23 2018-10-07 2018-12-11 2019-05-17 2019-06-09 ring and Evaluation Specialist agement for KYEOP KE-MPYG-52585-CS-INDV / C Strengthening youth policy d onsultancy Services for Roll o Individual Consult IDA / 58120 evelopment and project man Prior Direct 36,000.00 62,314.56 Signed 2018-04-20 2018-12-14 2018-04-30 2018-05-21 2019-04-15 2018-06-25 2019-05-17 2018-12-22 ut and Capacity support Tech ant Selection agement nical Assistant for KYEOP KE-MPYG-104837-CS-CDS / Development of Interim MIS system - the consultant will d evelop and embed new mod Strengthening youth policy d ules into the interim manage IDA / 58120 evelopment and project man Prior Direct Selection Direct 160,000.00 158,259.20 Signed 2019-03-29 2019-04-08 2019-06-12 2019-05-17 2019-12-09 ment information system to agement meet the expanding needs of the project and also offer con tinued technical assistance t o the implementing agencies . KE-MPYG-118556-CS-CDS / C Strengthening youth policy d ommunication Consultant on IDA / 58120 evelopment and project man Prior Direct Selection Direct 20,000.00 18,441.68 Signed 2019-09-19 2019-12-04 2019-09-29 2019-11-18 2019-12-03 2020-02-10 2020-05-31 short term basis (4 months) agement KE-MPYG-123194-CS-INDV / Strengthening youth policy d Engagement of Individual Co Individual Consult IDA / 58120 evelopment and project man Post Open - National 72,000.00 23,688.66 Signed 2019-10-02 2020-11-26 2019-11-20 2020-12-22 2019-12-11 2021-02-18 2020-01-15 2021-05-27 2020-07-13 nsultant for Communication f ant Selection agement or KYEOP for a period of one year. KE-MPYG-159134-CS-INDV / Improving youth employabili Individual Consult MIS Assistant Developer and IDA / 58120 Post Limited 65,000.00 36,929.55 Signed 2020-02-17 2020-03-10 2020-02-22 2020-09-24 2020-03-14 2021-01-19 2020-04-18 2021-05-27 2021-04-18 ty ant Selection Infrastructure Support Consul tant KE-MPYG-181809-CS-CDS / K Improving youth employabili IDA / 58120 Prior Direct Selection Direct 200,000.00 191,614.49 Signed 2020-09-11 2020-12-11 2020-09-16 2020-12-11 2020-11-20 2021-12-17 2021-11-20 YEOP Tracer Studies for Cycl ty e 2 and 3 KE-MPYG-88615-CS-INDV-RE V / Individual Consultant for a Filed Supervisor to help su Individual Consult Pending Impleme pervise data collection and i IDA / 58120 Support for job creation Post Open 60,000.00 0.00 2019-02-25 2019-07-09 2019-07-23 2019-08-27 2020-08-26 ant Selection ntation mplementation of interventio ns for the Impact Evaluations of Business Development Ser vices and Business Plan Com petition KE-MPYG-88615-CS-INDV / In dividual Consultant Services( 3 years contract) for a Field S Strengthening youth policy d upervisor to help supervise t Individual Consult IDA / 58120 evelopment and project man Prior Open 210,000.00 0.00 Canceled 2019-01-25 2019-02-25 2019-03-15 2019-07-03 2019-04-05 2019-05-10 2019-11-06 he data collection and imple ant Selection agement mentation of interventions fo r the impact evaluations of th e Business Development Ser vices and Business Plan Com petition. KE-MPYG-123390-CS-INDV / I ndividual Consultant Services (one year, renewable) for a Fi eld Supervisor to help superv Improving youth employabili Individual Consult IDA / 58120 Post Open 150,000.00 0.00 Canceled 2019-07-18 2019-01-10 2019-09-05 2019-09-26 2019-10-31 2020-04-28 ise the data collection and im ty ant Selection plementation of intervention s for the impact evaluations of the Business Development Services and Business Plan C ompetition. KE-MPYG-200072-CS-INDV / Improving youth employabili Individual Consult Selection of 2000 Individual IDA / 58120 Prior Limited 1,500,000.00 1,326,846.00 Signed 2020-12-04 2020-12-15 2020-12-09 2021-02-02 2020-12-16 2021-06-28 2021-01-06 2021-06-28 2022-01-06 ty ant Selection Master Craftsmen as IC KE-MPYG-206748-CS-CDS / I Strengthening youth policy d IDA / 58120 Post Direct Selection Direct 78,000.00 13,315.58 Signed 2020-12-11 2020-11-12 2020-12-21 2021-09-24 2021-02-24 2021-12-07 2021-08-23 mpact Evaluation Field Coord evelopment and project man inator agement KE-MPYG-173269-CS-CDS / P Improving youth employabili RIVATE SECTOR ORGANIZATI IDA / 58120 Prior Direct Selection Direct 2,800,000.00 0.00 Canceled 2020-05-12 2020-06-11 2020-05-22 2020-07-26 2021-07-26 ty ON FOR PLACEMENT OF YOU TH Page 4 KE-MPYG-230272-CS-INDV / Strengthening youth policy d Individual Consult Under Implement Engagement of Impact Evalu IDA / 58120 evelopment and project man Post Limited 78,000.00 0.00 2021-04-30 2021-06-15 2021-05-05 2021-05-26 2021-06-30 2021-12-27 ant Selection ation ation Field Coordinator agement KE-MPYG-258118-CS-INDV / Improving youth employabili Individual Consult Under Implement Additional Master Craftsmen IDA / 58120 Prior Limited 900,000.00 0.00 2021-10-19 2021-11-01 2021-10-24 2021-11-25 2021-11-14 2022-10-18 2021-12-19 2022-06-17 ty ant Selection ation for Cycle 7B counties - 1000 MCs KE-MPYG-287538-CS-CDS / E ngagement of an Individual C Strengthening youth policy d Under Implement onsultant to Continuously De IDA / 58120 evelopment and project man Post Direct Selection Direct 40,000.00 0.00 2022-03-30 2022-05-24 2022-04-09 2022-08-05 2022-06-13 2022-12-31 ation velop and Manage the Projec agement t Management Information S ystem - Cycle 7B KE-MPYG-287548-CS-CDS / R Strengthening youth policy d Under Implement oll Out and Capacity Support IDA / 58120 evelopment and project man Post Direct Selection Direct 35,000.00 0.00 2022-03-30 2022-04-15 2022-04-09 2022-08-05 2022-06-13 2022-12-31 ation Technical Assistant agement KE-MPYG-289242-CS-CDS / P Strengthening youth policy d Under Implement roject Communication Consul IDA / 58120 evelopment and project man Post Direct Selection Direct 28,000.00 0.00 2022-05-20 2022-05-24 2022-05-30 2022-08-03 2022-12-31 ation tant - Short Term (100 days) agement KE-MPYG-324737-CS-INDV / Strengthening youth policy d Individual Consult Under Implement Monitoring and Evaluation Sp IDA / 58120 evelopment and project man Post Open - National 70,000.00 0.00 2022-11-03 2022-11-12 2022-12-06 2022-12-13 2022-12-27 2023-08-31 ant Selection ation ecialist for KYEOP agement Page 5