PROCUREMENT PLAN (Textual Part) Project information: Cabo Verde: Resilient Tourism and Blue Economy Development in Cabo Verde Project (P176981) Project Implementation agency: UGPE (Unidade de Gestão de Projetos Especiais) Date of the Procurement Plan: June 23, 2022 Period covered by this Procurement Plan: 2022 - 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable. Works: is not applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Cabo Verde : Resilient Tourism and Blue Economy Development in Cabo Verde Project PLAN General Information Country: Cabo Verde 2022-06-25 Bank’s Approval Date of the Original Procurement Plan: 2024-07-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176981 GPN Date: 2022-06-23 Project Name: Resilient Tourism and Blue Economy Development in Cabo Verde Project Loan / Credit No: IDA / 71260, TF / B8414, IDA / 72720 Unidade de Gestao de Projectos Especiais Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - 07/RTBED/UGPE/2022 / Reha Component 1: Development Single Stage - One E Works (without pr 2023-05-1 bilitation of Ponte de Canal, i IDA / 71260 of integrated and resilient to Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-07-31 2022-12-23 2022-08-05 2022-09-16 2022-10-16 2022-11-20 nvelope equalification) SP 9 n Santo Antão urism and blue economy infr D astructure 20/RTBED/UGPE/2022 / Reha Component 1: Development Request for Bids - bilitation of a section 8 km of of integrated and resilient to Open - Internationa Single Stage - One E Works (without pr 2023-10-1 IDA / 71260 Prior Request for Bids 8,000,000.00 0.00 Signed 2022-12-26 2023-01-17 2022-12-31 2023-01-17 2023-02-11 2023-03-31 2023-03-13 2023-05-30 2023-04-17 2023-07-07 main road connecting Esparg urism and blue economy infr l nvelope equalification) SP 4 os and Santa Maria – Sal astructure D Request for Bids - 07/RTBED/UGPE/2023 - 2 / R Component 1: Development Single Stage - One E Works (without pr 2023-12-0 ehabilitation of Ponte de Can IDA / 71260 of integrated and resilient to Post Request for Bids Open - National 300,000.00 0.00 Signed 2023-02-20 2023-02-28 2023-02-25 2023-04-08 2023-04-11 2023-05-08 2023-06-07 2023-06-12 2023-07-18 nvelope equalification) SP 9 al, in Santo Antão urism and blue economy infr D astructure 34/RTBED/UGPE/2023 / Reha Component 1: Development Request for Quota Request for Quota Single Stage - One E 2024-05-2 bilitation of 2 trails in Ribeiro IDA / 71260 of integrated and resilient to Post Open - National tions (Non Bank-S 73,000.00 0.00 Signed 2023-09-30 2023-11-25 2024-02-15 tions nvelope 3 Grande, island of Santo Antã urism and blue economy infr PD) o, Cabo Verde astructure 35/RTBED/UGPE/2023 / Reha Component 1: Development Request for Quota bilitation of 2 trails in Paul ( P of integrated and resilient to Request for Quota Single Stage - One E 2024-05-2 IDA / 71260 Post Open - National tions (Non Bank-S 87,650.00 0.00 Signed 2023-09-30 2023-11-25 2024-02-15 ico da Cruz - Pé de Eucalipto) urism and blue economy infr tions nvelope 3 PD) , island of Santo Antão, Cabo astructure Verde 36/RTBED/UGPE/2023 / Reha Component 1: Development Request for Quota Request for Quota Single Stage - One E 2024-05-2 bilitation of 4 trails in Porto IDA / 71260 of integrated and resilient to Post Open - National tions (Non Bank-S 86,000.00 0.00 Signed 2023-09-30 2023-11-25 2024-02-15 tions nvelope 3 Novo, island of Santo Antão, urism and blue economy infr PD) Cabo Verde astructure 25-RTBED-UGPE-2023 / Expa Component 1: Development Request for Bids - nsion and completion of the of integrated and resilient to Single Stage - One E Works (without pr Under Imple 2024-08-1 IDA / 71260 Post Request for Bids Open - National 200,000.00 0.00 2023-10-31 2023-12-14 2023-11-05 2023-12-17 2024-02-09 2024-01-16 2024-02-20 cultural and arts center of Ri urism and blue economy infr nvelope equalification) SP mentation 8 beira Grande - 7 Sois 7 Luas astructure D Request for Bids - 45/RTBED/UGPE/2023 / Reha Component 1: Development Open - Internationa Single Stage - One E Small Works SPD 2026-05-2 bilitation of Santa Maria pier IDA / 71260 of integrated and resilient to Post Request for Bids 3,200,000.00 0.00 Canceled 2024-04-30 2024-07-16 2024-07-16 2024-05-05 2024-09-24 2024-10-24 2024-11-28 l nvelope (2 envelope proce 2 and surrounding area - Sal urism and blue economy infr ss) astructure Request for Bids - 45/RTBED/UGPE/2024 / Reha Component 1: Development Open - Internationa Single Stage - Two E Small Works SPD Pending Imp 2025-07-1 bilitation of Santa Maria pier IDA / 71260 of integrated and resilient to Post Request for Bids 2,920,000.00 0.00 2024-08-09 2024-08-14 2024-09-25 2024-12-08 2025-01-12 l nvelope (2 envelope proce lementation 1 and surrounding area - Sal urism and blue economy infr ss) astructure 52-RTBED-UGPE-2024 / Wor Component 1: Development Request for Bids - ks of requalification of Bairro of integrated and resilient to Single Stage - One E Works (without pr Pending Imp 2025-05-0 IDA / 71260 Post Request for Bids Open - National 650,000.00 0.00 2024-07-15 2024-07-20 2024-08-31 2024-09-30 2024-11-04 S. Sebastião, the walking trai urism and blue economy infr nvelope equalification) SP lementation 3 l from the Fort of S. Felipe, a astructure D nd improved signage GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2: Enhancement 11/RTBED/UGPE/2022 / Ocea of inclusive and sustainable Request for Quota Single Stage - One E n Race: Set up of a Village Pa IDA / 71260 Post Open - National 270,000.00 0.00 Signed 2022-10-15 2022-12-10 2022-12-01 2023-06-08 management of tourism in a tions nvelope rk blue economy Component 2: Enhancement 12/RTBED/UGPE/2022 / Ocea of inclusive and sustainable Request for Quota Single Stage - One E n Race: Recreation and Enter IDA / 71260 Post Open - National 200,000.00 0.00 Signed 2022-10-15 2022-12-10 2022-12-16 2023-06-08 management of tourism in a tions nvelope tainment blue economy 15/RTBED/UGPE/2022 / RAC Component 2: Enhancement E VILLAGE HOSPITALITY PLAT of inclusive and sustainable Direct - Internation IDA / 71260 Post Direct Selection 60,000.00 0.00 Signed 2022-10-16 2022-10-10 2022-10-21 2022-10-19 2022-11-25 2022-12-21 2023-05-24 FORM - Tall Ship Oosterschel management of tourism in a al de. blue economy Component 2: Enhancement 14/RTBED/UGPE/2022 / Mark of inclusive and sustainable Request for Quota Single Stage - One E IDA / 71260 Post Open - National 30,000.00 0.00 Signed 2022-12-05 2023-01-30 2023-01-05 2023-07-29 eting & Communications management of tourism in a tions nvelope blue economy Component 2: Enhancement 50/RTBED/UGPE/2024 / Impu of inclusive and sustainable Request for Quota Single Stage - One E lsiona Communication Camp IDA / 71260 Post Open - National 3,000.00 0.00 Canceled 2024-02-14 2024-04-10 2024-10-07 management of tourism in a tions nvelope aign blue economy Component 2: Enhancement 49/RTBED/UGPE/2024 / New of inclusive and sustainable Request for Quota Single Stage - One E Pending Impl Brand Communication Materi IDA / 71260 Post Open - National 100,000.00 0.00 2024-06-05 2024-07-31 2025-01-27 management of tourism in a tions nvelope ementation al/Production blue economy CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02/RTBED/UGPE/2022 / Deta Component 1: Development iled urban plan (study) for th of integrated and resilient to Least Cost Selecti Open - Internationa e historic center of `Cidade V IDA / 71260 Post 250,000.00 0.00 Signed 2022-06-19 2022-06-30 2022-07-10 2022-07-11 2022-08-23 2022-11-16 2022-09-20 2022-12-28 2022-10-20 2023-03-10 2022-11-24 2023-07-06 2022-12-29 2023-08-03 2023-06-27 urism and blue economy infr on l elha`, according to UNESCO astructure guidelines (IPC, INGT, CMRGS ) 06/RTBED/UGPE/2022 / Map Component 1: Development ping (cartographic, digital, ph of integrated and resilient to Consultant Qualifi otographic) and physical sign IDA / 71260 Post Open - National 150,000.00 0.00 Signed 2022-07-08 2022-07-14 2022-07-29 2022-09-11 2022-10-17 2022-10-11 2022-12-07 2022-11-15 2022-12-10 2023-05-14 urism and blue economy infr cation Selection aling of 44 hiking trails (+-39 astructure 4 km in the 3 municipalities) 05/RTBED/UGPE/2022 / Prep Component 1: Development aratory Studies for the const of integrated and resilient to Quality And Cost- Open - Internationa ruction or upgrade of maritim IDA / 71260 Post 460,000.00 0.00 Signed 2022-07-08 2022-09-05 2022-07-29 2022-09-22 2022-09-11 2023-01-02 2022-10-09 2023-02-24 2022-11-08 2023-05-16 2022-12-13 2023-08-03 2023-01-17 2023-08-24 2024-01-17 urism and blue economy infr Based Selection l e passenger terminals locate astructure d on 4 islands (Praia, Sal, São Nicolau e Fogo) Component 2: Enhancement 09/RTBED/UGPE/2022 / TA fo of inclusive and sustainable Consultant Qualifi Open - Internationa r Rebranding of Cabo Verde IDA / 71260 Post 120,000.00 0.00 Signed 2022-08-30 2022-08-27 2022-09-20 2022-08-30 2022-11-03 2022-12-13 2022-12-03 2023-01-31 2023-01-07 2023-02-23 2023-07-06 management of tourism in a cation Selection l as a Tourism Destination blue economy Component 2: Enhancement 10/RTBED/UGPE/2022 / Draft of inclusive and sustainable Quality And Cost- Open - Internationa ing of Coastal Zone Plans for IDA / 71260 Post 200,000.00 0.00 Signed 2022-08-31 2022-09-02 2022-09-21 2022-09-13 2022-11-04 2023-01-26 2022-12-02 2023-03-13 2023-01-01 2023-10-13 2023-02-05 2023-12-01 2023-03-12 2023-12-21 2024-03-11 management of tourism in a Based Selection l Sal Island blue economy 13/RTBED/UGPE/2022 / Cont Component 1: Development racting Supervision/Inspectio of integrated and resilient to Quality And Cost- IDA / 71260 Post Open - National 302,000.00 0.00 Signed 2022-10-10 2022-10-07 2022-10-31 2022-12-14 2022-12-15 2023-01-11 2023-02-10 2023-02-10 2023-04-05 2023-03-17 2023-06-08 2023-04-21 2023-07-11 2024-04-20 n Service for the Road Espar urism and blue economy infr Based Selection gos Santa Maria – Ilha de Sal astructure Component 2: Enhancement 18/RTBED / TA to ITCV on De of inclusive and sustainable Consultant Qualifi Open - Internationa stination Online Communicati IDA / 71260 Post 200,000.00 0.00 Signed 2022-12-10 2023-01-02 2022-12-31 2023-02-10 2023-02-13 2023-06-06 2023-03-15 2023-11-23 2023-04-19 2023-12-01 2023-10-16 management of tourism in a cation Selection l on/Marketing blue economy 23-RTBED-UGPE-2023 / Tech Component 1: Development nical study for the upgrade of of integrated and resilient to Quality And Cost- IDA / 71260 Post Open - National 300,000.00 0.00 Signed 2023-02-12 2023-03-22 2023-03-05 2023-03-24 2023-04-18 2023-07-27 2023-05-16 2023-10-02 2023-06-15 2023-11-29 2023-07-20 2024-02-06 2023-08-24 2024-03-20 2024-08-23 the existing quay in Tarrafal urism and blue economy infr Based Selection de Santiago and its surroundi astructure ng areas 24-RTBED-UGPE-2023 / Stud Component 1: Development Consultant Qualifi y for the rehabilitation of the IDA / 71260 of integrated and resilient to Post Open - National 200,000.00 0.00 Canceled 2023-02-20 2023-05-11 2023-03-13 2023-04-26 2023-05-26 2023-06-30 2023-12-27 cation Selection fish market in Mindelo urism and blue economy infr astructure 29/RTBED/UGPE/2023 / TA to support co-management initi Component 2: Enhancement atives in artisanal fishing co of inclusive and sustainable Quality And Cost- Open - Internationa mmunities, to continue empo IDA / 71260 Post 300,000.00 0.00 Signed 2023-05-19 2023-05-23 2023-06-09 2023-05-30 2023-07-23 2023-09-05 2023-08-20 2023-10-18 2023-09-19 2023-12-28 2023-10-24 2024-03-14 2023-11-28 2024-04-08 2024-11-27 management of tourism in a Based Selection l wering communities in the su blue economy stainable and inclusive mana gement of their marine and c oastal resources. 24-RTBED-UGPE-2023 - 2 / S Component 1: Development Consultant Qualifi Open - Internationa tudy for the rehabilitation of IDA / 71260 of integrated and resilient to Post 200,000.00 0.00 Signed 2023-05-31 2023-05-30 2023-06-21 2023-05-30 2023-08-04 2023-09-29 2023-09-03 2024-01-15 2023-10-08 2024-02-07 2024-04-05 cation Selection l the fish market in Mindelo urism and blue economy infr astructure 30/RTBED/UGPE/2023 / Anal Component 2: Enhancement ysis of demersal resources wi of inclusive and sustainable Consultant Qualifi Open - Internationa TF / B8414 Post 100,000.00 0.00 Signed 2023-08-30 2023-08-28 2023-09-20 2023-09-15 2023-11-03 2023-11-28 2023-12-03 2024-03-06 2024-01-07 2024-03-08 2024-07-05 th tourism and export deman management of tourism in a cation Selection l d blue economy 33/RTBED/UGPE/2023 / Cont ratação de uma firma para at ualização dos instrumentos a Component 3: Project Imple Consultant Qualifi IDA / 72720 Post Limited 120,000.00 0.00 Signed 2023-05-02 2023-08-28 2023-05-16 2023-08-31 2023-06-15 2023-09-18 2023-07-20 2023-09-20 2024-01-16 mbientais e sociais do Projec mentation Support cation Selection to Turismo Resiliente e Dese nvolvimento da economia az ul Component 2: Enhancement 37/RTBED/UGPE/2023 / Draft of inclusive and sustainable Quality And Cost- Open - Internationa ing of Coastal Zone Plan Sant IDA / 71260 Post 100,000.00 0.00 Canceled 2023-09-22 2023-10-05 2023-10-13 2023-10-05 2023-11-26 2023-12-24 2024-01-23 2024-02-27 2024-04-02 2025-04-02 management of tourism in a Based Selection l iago (POOC-M Santiago) blue economy Component 2: Enhancement 40/RTBED/UGPE/2023 / TA to of inclusive and sustainable Quality And Cost- Open - Internationa Under Implement support hiking tourism on Ca IDA / 71260 Post 400,000.00 0.00 2023-10-31 2023-10-09 2023-11-21 2023-10-11 2024-01-04 2024-02-01 2024-03-02 2024-04-06 2024-05-11 2025-05-11 management of tourism in a Based Selection l ation bo Verde blue economy Component 2: Enhancement 37/RTBED/UGPE/2023-2 / Dr of inclusive and sustainable Quality And Cost- Open - Internationa Under Implement afting of Coastal Zone Plan S IDA / 71260 Post 200,000.00 0.00 2023-10-06 2023-10-05 2023-10-27 2023-10-06 2023-12-10 2024-01-07 2024-02-06 2024-03-12 2024-04-16 2025-04-16 management of tourism in a Based Selection l ation antiago (POOC-M Santiago) blue economy 41/RTBED/UGPE/2023 / Cont Component 2: Enhancement racting an international mark of inclusive and sustainable Quality And Cost- Open - Internationa Under Implement et representation firm to sup IDA / 71260 Post 750,000.00 0.00 2023-10-31 2023-10-11 2023-11-21 2023-10-12 2024-01-04 2024-02-01 2024-03-02 2024-04-06 2024-05-11 2025-05-11 management of tourism in a Based Selection l ation port ITCV´s marketing effort i blue economy n selected/prioritized Europe an source market(s). 42/RTBED/UGPE/2023 / Deve Component 2: Enhancement lopment of origin and sustain of inclusive and sustainable Quality And Cost- Open - Internationa Under Implement IDA / 71260 Post 250,000.00 0.00 2023-10-31 2023-10-12 2023-11-21 2023-10-16 2024-01-04 2024-02-01 2024-03-02 2024-04-06 2024-05-11 2025-05-11 ability certification/labelling f management of tourism in a Based Selection l ation or fisheries/aquaculture prod blue economy ucts in Cabo Verde 44/RTBED/UGPE/2023 / Stud Component 2: Enhancement y on opportunities for solar e of inclusive and sustainable Consultant Qualifi Open - Internationa Under Implement TF / B8414 Post 250,000.00 0.00 2023-10-31 2023-10-11 2023-11-21 2023-10-12 2024-01-04 2024-02-03 2024-03-09 2024-09-05 nergy solutions in coastal infr management of tourism in a cation Selection l ation astructure blue economy 46/RTBED/UGPE/2023 / M&E - Contracting a firm for data collection to determine baseli Component 3: Project Imple Consultant Qualifi IDA / 71260 Post Open - National 30,000.00 0.00 Canceled 2023-12-08 2023-11-28 2023-12-29 2024-02-11 2024-03-12 2024-04-16 2024-10-13 ne for ´local tourism and oth mentation Support cation Selection er ocean-economy value chai n beneficiaries satisfied with the project interventions´ Page 2 47/RTBED/UGPE/2023 / Cont Component 1: Development racting Supervision/Inspectio of integrated and resilient to Quality And Cost- Open - Internationa IDA / 71260 Post 300,000.00 0.00 Canceled 2023-11-30 2024-04-18 2023-12-21 2024-02-03 2024-03-02 2024-04-01 2024-05-06 2024-06-10 2025-06-10 n Service for the Rehabilitati urism and blue economy infr Based Selection l on of Santa Maria pier and su astructure rrounding area - Sal 08/RTBED/UGPE/2022 / For t Component 1: Development he preparation of a detailed of integrated and resilient to Least Cost Selecti Open - Internationa Under Implement plan (DP) and execution proj IDA / 71260 Post 250,000.00 0.00 2023-11-30 2023-11-28 2023-12-21 2023-11-29 2024-02-03 2024-03-02 2024-04-01 2024-05-06 2024-06-10 2024-12-07 urism and blue economy infr on l ation ects for the requalification of astructure the coastal zone of tarrafal d e monte trigo - Santo Antão 38/RTBED/UGPE/2024 / Stud Component 1: Development y for the development of an of integrated and resilient to Consultant Qualifi Open - Internationa Under Implement IDA / 71260 Post 300,000.00 0.00 2024-01-19 2024-03-13 2024-02-09 2024-04-03 2024-03-24 2024-04-23 2024-05-28 2024-11-24 experience around on Turtle urism and blue economy infr cation Selection l ation conservation at S. Pedro – S. astructure Vicente 38/RTBED/UGPE/2023 / Stud Component 1: Development y for the development of an of integrated and resilient to Consultant Qualifi IDA / 71260 Post Open - National 300,000.00 0.00 Canceled 2023-10-20 2023-10-12 2023-11-10 2023-12-24 2024-01-23 2024-02-27 2024-08-25 experience around on Turtle urism and blue economy infr cation Selection conservation at S. Pedro – S. astructure Vicente Component 2: Enhancement 26/RTBED/UGPE/2024 / Impl of inclusive and sustainable Consultant Qualifi Under Implement ement gender mainstreamin IDA / 71260 Post Open - National 200,000.00 0.00 2024-02-20 2024-05-14 2024-03-12 2024-04-25 2024-05-25 2024-06-29 2024-12-26 management of tourism in a cation Selection ation g activities in tourism blue economy 47/RTBED/UGPE/2024 / Cont Component 1: Development racting Supervision/Inspectio of integrated and resilient to Consultant Qualifi Open - Internationa Under Implement IDA / 71260 Post 300,000.00 0.00 2024-04-30 2024-05-03 2024-05-21 2024-05-08 2024-07-04 2024-08-03 2024-09-07 2025-03-06 n Service for the Rehabilitati urism and blue economy infr cation Selection l ation on of Santa Maria pier and su astructure rrounding area - Sal 46/RTBED/UGPE/2024 / M&E - Contracting a firm for data collection to determine baseli Component 3: Project Imple Consultant Qualifi Under Implement IDA / 71260 Post Open - National 30,000.00 0.00 2024-06-10 2024-06-03 2024-07-01 2024-08-25 2024-09-29 2024-11-03 2025-05-02 ne for ´local tourism and oth mentation Support cation Selection ation er ocean-economy value chai n beneficiaries satisfied with the project interventions´ Component 2: Enhancement 51/RTBED/UGPE/2024 / Draft of inclusive and sustainable Quality And Cost- Open - Internationa Under Implement ing of Coastal Zone Plan S. Vi IDA / 71260 Post 200,000.00 0.00 2024-06-17 2024-06-13 2024-07-08 2024-07-12 2024-08-28 2024-10-02 2024-11-01 2024-12-06 2025-01-10 2026-01-10 management of tourism in a Based Selection l ation cente (POOC_M S. Vicente) blue economy 53/RTBED/UGPE/2024 / Cons Component 1: Development ultant services for additional of integrated and resilient to Consultant Qualifi Open - Internationa Pending Impleme IDA / 71260 Post 200,000.00 0.00 2024-08-09 2024-08-30 2024-10-13 2024-11-12 2024-12-17 2025-06-15 field ESIA studies in the cont urism and blue economy infr cation Selection l ntation ext of the Santa Maria Pier R astructure ehabilitation Project 56/RTBED/UGPE/2024 / Upgr ade of city´s museum – São Component 1: Development Vicente (ELABORAÇÃO DO P of integrated and resilient to Consultant Qualifi Open - Internationa Pending Impleme ROJETO MUSEUGRÁFICO DO IDA / 71260 Post 200,000.00 0.00 2024-07-31 2024-08-21 2024-10-04 2024-11-03 2024-12-08 2025-06-06 urism and blue economy infr cation Selection l ntation MUSEU DO MAR - MMAR astructure ILHA DE SÃO VICENTE – CAB O VERDE) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 04/RTBED/UGPE/2022 / Mark eting Specialist for ITCV - Indi Component 3: Project Imple Individual Consult IDA / 71260 Post Open 100,000.00 0.00 Signed 2022-06-23 2022-06-28 2022-08-11 2022-08-26 2022-09-01 2022-09-16 2022-10-06 2022-09-17 2023-04-04 vidual consultant to support t mentation Support ant Selection he Ministry of Tourism and Tr ansportation (MTT) 01/RTBED/UGPE/2022 / Proje ct Manager for Resilient Touri Component 3: Project Imple Individual Consult IDA / 71260 Post Direct 188,000.00 19,661.68 Signed 2022-06-30 2022-06-30 2022-07-10 2022-07-04 2022-07-31 2022-07-04 2022-09-04 2022-07-08 2023-03-03 sm and Blue Economy Devel mentation Support ant Selection opment in Cabo Verde 03/RTBED/UGPE/2022 / Plan ning and Tourism Specialist - Component 3: Project Imple Individual Consult IDA / 71260 Post Open 150,000.00 0.00 Signed 2022-07-08 2022-06-30 2022-08-26 2022-09-26 2022-09-16 2022-09-30 2022-10-21 2022-10-01 2023-04-19 Individual consultant to supp mentation Support ant Selection ort the Ministry of Tourism an d Transportation (MTT) Component 2: Enhancement 16/RTBED/UGPE/2022 / TA of of inclusive and sustainable Individual Consult a senior consultant for the Mi IDA / 71260 Post Open - National 102,000.00 0.00 Canceled 2022-11-30 2023-05-24 2023-01-18 2024-01-10 2023-02-08 2023-03-15 2023-09-11 management of tourism in a ant Selection nistry of Sea blue economy Component 2: Enhancement 17/RTBED/UGPE/2022 / TA of of inclusive and sustainable Individual Consult a junior consultant for the Mi IDA / 71260 Post Open - National 60,000.00 0.00 Signed 2022-11-30 2023-01-06 2023-01-18 2023-05-22 2023-02-08 2023-07-06 2023-03-15 2023-07-14 2023-09-11 management of tourism in a ant Selection nistry of Sea blue economy 19/RTBED/UGPE/2022 / Busi Component 2: Enhancement ness development support a of inclusive and sustainable Individual Consult IDA / 71260 Post Open - National 105,000.00 0.00 Canceled 2022-12-09 2023-01-02 2023-01-27 2023-02-17 2023-03-24 2023-09-20 nd access to finance to SMEs management of tourism in a ant Selection – Suppliers Development Pro blue economy gram 19/RTBED/UGPE/2022-2 / Bu Component 2: Enhancement siness development support of inclusive and sustainable Individual Consult Open - Internationa IDA / 71260 Post 105,000.00 0.00 Signed 2023-01-23 2023-01-19 2023-03-13 2023-04-19 2023-04-03 2023-06-02 2023-05-08 2023-07-03 2023-11-04 and access to finance to SME management of tourism in a ant Selection l s – Suppliers Development Pr blue economy ogram 21/RTBED/UGPE/2023 / Stre Component 2: Enhancement ngthen Tourism National Stat of inclusive and sustainable Individual Consult IDA / 71260 Post Limited 40,000.00 0.00 Signed 2023-02-10 2023-03-02 2023-02-15 2023-03-22 2023-03-08 2023-07-26 2023-04-12 2023-07-28 2023-10-09 istic System: TA to INE - Inter management of tourism in a ant Selection national Tourist Survey blue economy 28/RTBED/UGPE/2023 / Cont Component 2: Enhancement ratação de um consultor naci of inclusive and sustainable Individual Consult onal para elaborar proposta IDA / 71260 Post Open - National 15,000.00 0.00 Canceled 2023-03-27 2023-03-24 2023-05-15 2023-06-05 2023-07-10 2024-01-06 management of tourism in a ant Selection de regulamento da atividade blue economy de prestador de serviço de al ojamento complementar Page 3 27/RTBED/UGPE/2023 / Inter national individual consultan Component 2: Enhancement cy to support the ministry of of inclusive and sustainable Individual Consult Open - Internationa IDA / 71260 Post 25,000.00 0.00 Canceled 2023-03-27 2023-03-27 2023-05-15 2023-06-05 2023-07-10 2024-01-06 tourism to prepare proposal management of tourism in a ant Selection l of regulation for complement blue economy ary accommodation service p roviders 28/RTBED/UGPE/2023-2 / Co Component 2: Enhancement ntratação de um consultor na of inclusive and sustainable Individual Consult cional para elaborar proposta IDA / 71260 Post Limited 15,000.00 0.00 Signed 2023-06-15 2023-05-30 2023-06-20 2023-06-06 2023-07-11 2023-11-02 2023-08-15 2023-11-21 2024-02-11 management of tourism in a ant Selection de regulamento da atividade blue economy de prestador de serviço de al ojamento complementar 27/RTBED/UGPE/2023-2 / Int ernational individual consulta Component 2: Enhancement ncy to support the ministry o of inclusive and sustainable Individual Consult IDA / 71260 Post Limited 25,000.00 0.00 Canceled 2023-06-15 2023-05-30 2023-06-20 2023-06-06 2023-07-11 2023-08-15 2024-02-11 f tourism to prepare proposal management of tourism in a ant Selection of regulation for complement blue economy ary accommodation service p roviders Component 2: Enhancement 31/RTBED/UGPE/2023 / TA to of inclusive and sustainable Individual Consult EMAR – Training Program on TF / B8414 Post Limited 45,000.00 0.00 Canceled 2023-09-03 2023-09-27 2023-09-08 2023-10-05 2023-09-29 2023-11-03 2024-05-01 management of tourism in a ant Selection Fish Handling Best Practices blue economy 32/RTBED/UGPE/2023 / Cont ract a local consultant to assi Component 3: Project Imple Individual Consult st MTT in the implementation IDA / 72720 Post Open - National 80,000.00 0.00 Signed 2023-09-06 2023-08-28 2023-10-25 2023-12-15 2023-11-15 2024-01-17 2023-12-20 2024-01-23 2024-06-17 mentation Support ant Selection of tourism infrastructures pro jects in Santiago (Cidade Vel ha and Tarrafal). 22/RTBED/UGPE/2023 / TEC Component 1: Development HNICAL ASSISTANCE REGAR of integrated and resilient to Individual Consult Open - Internationa DING HIKING TRAIL MANAGE IDA / 71260 Post 50,000.00 0.00 Canceled 2023-09-29 2023-09-21 2023-11-17 2023-12-08 2024-01-12 2024-07-10 urism and blue economy infr ant Selection l MENT AND FEE STRUCTURE F astructure OR SANTO ANTÃO ISLAND 43/RTBED/UGPE/2023 / Cons Component 2: Enhancement ulting service to the Ministry of inclusive and sustainable Direct - Internation TF / B8414 Post Direct Selection 200,000.00 0.00 Signed 2023-10-31 2023-10-23 2023-11-10 2023-10-31 2024-01-14 2024-03-27 2024-07-12 of the Sea on Climate Chang management of tourism in a al e and Marine Fisheries blue economy 27/RTBED/UGPE/2023-3 / Int ernational individual consulta Component 2: Enhancement ncy to support the ministry o of inclusive and sustainable Individual Consult Under Implement IDA / 71260 Post Limited 25,000.00 0.00 2023-11-10 2023-11-13 2023-11-15 2023-11-17 2023-12-06 2024-01-10 2024-07-08 f tourism to prepare proposal management of tourism in a ant Selection ation of regulation for complement blue economy ary accommodation service p roviders. Component 2: Enhancement 26-RTBED-UGPE-2023 / Impl of inclusive and sustainable Individual Consult ement gender mainstreamin IDA / 71260 Post Open - National 200,000.00 0.00 Canceled 2023-02-20 2023-03-28 2023-04-10 2023-08-01 2023-05-01 2023-06-05 2023-12-02 management of tourism in a ant Selection g activities into tourism blue economy Component 2: Enhancement 48/RTBED/UGPE/2024 / New of inclusive and sustainable Direct - Internation Under Implement Brand Communication Materi IDA / 71260 Post Direct Selection 43,500.00 0.00 2024-02-08 2024-02-07 2024-02-18 2024-04-23 2024-10-20 management of tourism in a al ation al/Design and graphics blue economy 54/RTBED/UGPE/2024 / Cons ultant services to assess rese Component 1: Development ttlement needs and draft a c of integrated and resilient to Individual Consult Pending Impleme IDA / 71260 Post Open - National 80,000.00 0.00 2024-08-15 2024-10-03 2024-10-24 2024-11-28 2025-05-27 orresponding Resettlement A urism and blue economy infr ant Selection ntation ction Plan (RAP) within the co astructure ntext of the Santa Maria Pier Rehabilitation Project Component 2: Enhancement 55/RTBED/UGPE/2024 / TA to of inclusive and sustainable Individual Consult Open - Internationa Pending Impleme EMAR – Training Program on TF / B8414 Post 60,000.00 0.00 2024-08-30 2024-10-18 2024-11-08 2024-12-13 2025-06-11 management of tourism in a ant Selection l ntation Fish Handling Best Practices blue economy Page 4