PROCUREMENT PLAN Project information: Angola Commercial Agriculture Development Project P159052 Project Implementation Agency: Ministry of Agriculture (MINAGRI) – Office of Studies, Planning and Statistics (GEPE) Date of the Procurement Plan: March 22, 2017 Period covered by this Procurement Plan: March 22, 2017 to March 22, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. “National procurement legislation and applicable conditions under review by the Bank” When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. 1 Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works), Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information. “Not Applicable” 2 PROCUREMENT Angola : Angola Commercial Agriculture Development Project (PDAC) PLAN General Information Country: Angola 2017-03-06 Bank’s Approval Date of the Original Procurement Plan: 2024-07-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159052 GPN Date: 2021-09-15 Project Name: Angola Commercial Agriculture Development Project (PDAC) Loan / Credit No: IBRD / P4860, / , IBRD / 88660, COFN / C1580 Ministry of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 002/W/CADP/18 / Maintenan Infrastructure for Production Single Stage - One E 2022-05-0 COFN / C1580 Post Request for Bids Open - National 956,655.00 0.00 Canceled 2021-07-18 2021-07-23 2021-09-03 2021-10-03 2021-11-07 ce of rural roads (1st and 2n and Marketing nvelope 6 d yr) Request for Bids - 007/W/CADP/20 / Rehabilitat Works (without pr Infrastructure for Production Single Stage - One E 2023-06-1 ion of Irrigation infrastructure COFN / C1580 Post Request for Bids Open - National equalification) SP 6,500,000.00 0.00 Canceled 2022-02-21 2022-03-07 2022-04-11 2022-05-11 2022-06-15 and Marketing nvelope 5 (Lot 2) D - Applying contr actor disqualificia tion Request for Bids - 004/W/CADP/20 / Rehabilitat Works (without pr ion and Maintenance rural ro Infrastructure for Production Single Stage - One E equalification) SP 2023-02-2 COFN / C1580 Post Request for Bids Open - National 9,000,000.00 0.00 Canceled 2022-02-02 2022-02-16 2022-03-23 2022-04-27 2022-05-28 ads - (Works Phase 1 - Lot 3) and Marketing nvelope D - Applying contr 2 Kuanza Sul - 50 km actor disqualificia tion Request for Bids - 001/W/CADP/18 / Rehabilitat Works (without pr ion and Maintenance rural ro Infrastructure for Production Open - Internationa Single Stage - One E equalification) SP 10,000,000.0 2026-04-2 COFN / C1580 Prior Request for Bids 0.00 Canceled 2022-04-05 2022-04-19 2022-05-17 2022-06-21 2022-07-26 ads - (Works Phase 1- Lot 2) and Marketing l nvelope D - Applying contr 0 1 Kuanza Norte (50 km) actor disqualificia tion Request for Bids - 005/W/CADP/20 / Rehabilitat Works (without pr ion and Maintenance rural ro Infrastructure for Production Single Stage - One E 2023-07-3 COFN / C1580 Post Request for Bids Open - National equalification) SP 9,500,000.00 0.00 Canceled 2022-07-10 2022-07-24 2022-08-28 2022-10-02 2022-11-02 ads - (Works Phase 1- Lot1) and Marketing nvelope 0 D - Applying contr Malange - 50 km actor disqualificia tion Request for Bids - 003/W/CADP/18 / Rehabilitat Works (without pr Infrastructure for Production Single Stage - One E 2023-07-1 ion of Irrigation infrastructure COFN / C1580 Post Request for Bids Open - National equalification) SP 5,000,000.00 0.00 Canceled 2022-03-22 2022-04-05 2022-05-10 2022-06-14 2022-07-15 and Marketing nvelope 5 Kwanza Norte (Lot 1) D - Applying contr actor disqualificia tion C 189/CS/CADP-22 / Contrac Request for Bids - tor for the rehabilitation work Infrastructure for Production Open - Internationa Single Stage - One E Small Works SPD 2022-12-2 COFN / C1580 Post Request for Bids 8,500,000.00 0.00 Signed 2022-03-11 2022-05-30 2022-03-16 2022-06-02 2022-04-27 2022-08-05 2022-05-27 2022-09-05 2022-07-01 2023-05-19 of the irrigated perimeter of and Marketing l nvelope (1 envelope proce 8 Cacala and Korea in Kwanza ss) Norte C 251/W/CADP-22 / Construc Request for Bids - tion of the basic structure an Promotion and Support for A Single Stage - One E Small Works SPD 2023-07-0 COFN / C1580 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-09-18 2022-09-23 2022-11-04 2022-12-04 2023-01-08 d equipping of the potato gre gribusiness Development nvelope (1 envelope proce 7 enhouses in chianga ss) C 247/W/CADP-22 / Rehabilit Request for Bids - ation works of priorized rural Infrastructure for Production Open - Internationa Single Stage - One E Works (without pr 2023-08-1 COFN / C1580 Post Request for Bids 9,600,000.00 0.00 Canceled 2022-10-30 2022-11-04 2022-12-16 2023-01-15 2023-02-19 roads in the provinces of Mal and Marketing l nvelope equalification) SP 8 anje, Cuanza Norte and Cuan D za Sul Request for Bids - C 243/W/CADP-22 / Rehabilit Infrastructure for Production Single Stage - One E Small Works SPD 2023-08-1 ation Works of Small and Me COFN / C1580 Post Request for Bids Open - National 5,000,000.00 0.00 Canceled 2022-10-23 2022-10-28 2022-12-09 2023-01-08 2023-02-12 and Marketing nvelope (1 envelope proce 1 dium Perimeters. Cauá. Cuan ss) za Sul C 245/W/CADP-22 / Rehabilit Request for Bids - ation works of rural roads of Infrastructure for Production Open - Internationa Single Stage - Two E Works (without pr 2023-08-2 COFN / C1580 Post Request for Bids 8,400,000.00 0.00 Canceled 2022-09-18 2022-09-23 2022-11-04 2023-01-17 2023-02-21 access to the perimeters of B and Marketing l nvelope equalification) SP 0 om Jesus, Mucoso, Cacala, Ko D rea, and Cauá Request for Bids - C 286/W/CADP-22 / Construc Promotion and Support for A Single Stage - One E Small Works SPD 2023-06-1 tion of the structure and equi COFN / C1580 Post Request for Bids Open - National 700,000.00 0.00 Signed 2022-08-22 2022-10-10 2022-08-27 2022-10-10 2022-10-08 2022-11-21 2022-11-07 2022-12-22 2022-12-12 2023-06-22 gribusiness Development nvelope (1 envelope proce 0 ping of the potato greenhose ss) s in Chianga Request for Bids - C 288/W/CADP-22 / Construc Promotion and Support for A Single Stage - One E Small Works SPD 2023-06-1 tion of storage, office and pa COFN / C1580 Post Request for Bids Open - National 550,000.00 0.00 Signed 2022-08-30 2023-01-23 2022-09-04 2023-01-24 2022-10-16 2023-03-09 2022-11-15 2023-04-27 2022-12-20 2023-07-14 gribusiness Development nvelope (1 envelope proce 8 vilion for filling bags in Cuanz ss) a Norte Request for Bids - C 291/W/CADP-22 / Rehabilit Promotion and Support for A Single Stage - One E Small Works SPD 2023-06-2 ation of the infrastructures of COFN / C1580 Post Request for Bids Open - National 1,700,000.00 0.00 Canceled 2022-09-08 2022-09-13 2022-10-25 2022-11-24 2022-12-29 gribusiness Development nvelope (1 envelope proce 7 the LAU social support labora ss) tory in Malanje Request for Bids - 229A/W3/CADP/23 / Rehabili Promotion and Support for A Single Stage - One E Small Works SPD 2025-04-2 COFN / C1580 Post Request for Bids Open - National 900,000.00 0.00 Signed 2023-12-31 2023-10-31 2024-01-05 2023-10-31 2024-02-16 2023-12-15 2024-03-17 2024-03-05 2024-04-21 2024-03-27 tation of poultry rearing infra gribusiness Development nvelope (1 envelope proce 1 structure ss) 231A/W3/CADP/23 / Rehabili Request for Bids - tation and equipping of the b Promotion and Support for A Single Stage - One E Small Works SPD 2024-11-1 COFN / C1580 Post Request for Bids Open - National 300,000.00 0.00 Canceled 2024-01-31 2024-02-05 2024-03-18 2024-04-17 2024-05-22 romatology laboratory of the gribusiness Development nvelope (1 envelope proce 8 IIV in Santo António ss) 232A/W3/CADP/23 / Constru Request for Quota Promotion and Support for A Request for Quota Single Stage - One E 2024-08-2 ction of chicken sheds with 1 COFN / C1580 Post Limited tions (Non Bank-S 200,000.00 0.00 Signed 2024-01-05 2023-12-22 2024-03-01 2024-05-09 gribusiness Development tions nvelope 8 2 aisles and a rearing area PD) Request for Bids - C 231/W/CADP-22 / Rehabilit Promotion and Support for A Open - Internationa Single Stage - One E Small Works SPD 2023-04-0 ation Adaptation of an area o COFN / C1580 Post Request for Bids 600,000.00 0.00 Canceled 2022-06-19 2022-06-24 2022-08-05 2022-09-04 2022-10-09 gribusiness Development l nvelope (1 envelope proce 7 f ​(8*12)m2 for a bromatology ss) laboratory Request for Bids - C 229/W/CADP-22 / Rehabilit Promotion and Support for A Single Stage - One E Small Works SPD 2023-03-2 COFN / C1580 Post Request for Bids Open - National 238,000.00 0.00 Canceled 2022-06-05 2022-06-10 2022-07-22 2022-08-21 2022-09-25 ation of poultry rearing infras gribusiness Development nvelope (1 envelope proce 4 tructure ss) Request for Bids - C 230/W/CADP-22 / Rehabilit Promotion and Support for A Single Stage - One E Small Works SPD 2023-08-1 COFN / C1580 Post Request for Bids Open - National 585,000.00 0.00 Canceled 2022-10-30 2022-11-04 2022-12-16 2023-01-15 2023-02-19 ation of Social Support Infras gribusiness Development nvelope (1 envelope proce 8 tructures ss) 332/W3/CADP/23 / Rehabilit Request for Quota ation and restructuring works Promotion and Support for A Request for Quota Single Stage - One E Under Imple 2025-05-3 IBRD / 88660 Post Limited tions (Non Bank-S 100,000.00 0.00 2024-04-05 2024-02-21 2024-05-31 of the plumbing system in Bu gribusiness Development tions nvelope mentation 1 PD) ildings 1 and 2 of MINAGRIF Request for Bids - 334/W2/CADP/23 / Design a Promotion and Support for A Single Stage - One E Small Works SPD Under Imple 2025-06-2 nd Construction of electrical i IBRD / 88660 Post Request for Bids Open - National 2,666,916.82 0.00 2024-03-31 2024-05-07 2024-04-05 2024-05-07 2024-05-17 2024-07-05 2024-06-16 2024-07-21 gribusiness Development nvelope (1 envelope proce mentation 6 nfrastructures for Cacala, Cor ss) ea and Caua Page 1 325/W3/CADP/23 / Construct Request for Quota Promotion and Support for A Request for Quota Single Stage - One E 2024-10-2 ion of Base Structure for Pota IBRD / 88660 Post Limited tions (Non Bank-S 300,000.00 0.00 Signed 2024-03-05 2024-01-23 2024-04-30 2024-05-15 gribusiness Development tions nvelope 7 to Greenhouse Equipment in PD) Chianga Request for Bids - 243A/W2/CADP-23 / Rehabili Infrastructure for Production Open - Internationa Single Stage - One E Works (without pr 12,000,000.0 2026-10-1 COFN / C1580 Prior Request for Bids 0.00 Canceled 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 tation works on the Perimete and Marketing l nvelope equalification) SP 0 9 r of Cauá D 006A/W2/CADP/23 / Design Request for Bids - and Construction of electrical Infrastructure for Production Open - Internationa Single Stage - One E Works (without pr 18,600,000.0 2025-06-2 IBRD / 88660 Prior Request for Bids 0.00 Canceled 2024-02-29 2024-03-05 2024-04-16 2024-05-16 2024-06-20 connections - Kwanza Norte, and Marketing l nvelope equalification) SP 0 0 Kwanza Sul and Malange D 006/W/CADP/20 / Works of el ectrical connections, includin Infrastructure for Production Open - Internationa Single Stage - One E 15,000,000.0 2022-08-3 IBRD / 88660 Prior Request for Bids 0.00 Canceled 2021-11-11 2021-11-16 2021-12-28 2022-01-27 2022-03-03 g Design - Kwanza Norte, Kw and Marketing l nvelope 0 0 anza Sul and Malange Request for Bids - 008/W/CADP/20 / Rehabilitat Works (without pr Infrastructure for Production Single Stage - One E 2023-07-2 ion of Irrigation infrastructure COFN / C1580 Post Request for Bids Open - National equalification) SP 7,000,000.00 0.00 Canceled 2022-03-31 2022-04-14 2022-05-19 2022-06-23 2022-07-28 and Marketing nvelope 8 (Lot 3) D - Applying contr actor disqualificia Request tion for Bids - 322/W2/CADP/23 / Design a Infrastructure for Production Open - Internationa Single Stage - One E Works (without pr 15,560,995.0 2025-06-2 COFN / C1580 Prior Request for Bids 0.00 Canceled 2024-02-29 2024-03-05 2024-04-16 2024-05-16 2024-06-20 nd Rehabilitation of Perimete and Marketing l nvelope equalification) SP 0 0 r in Sumbe D Request for Bids - 243B/W2/CADP-24 / Rehabili Infrastructure for Production Open - Internationa Single Stage - Two E Works (without pr 12,000,000.0 Under Imple 2026-03-0 COFN / C1580 Prior Request for Bids 0.00 2024-03-20 2024-05-22 2024-03-20 2024-06-05 2024-05-29 2024-08-11 2024-09-15 tation works on the Perimete and Marketing l nvelope equalification) SP 0 mentation 9 r of Cauá D Request for Bids - 342/W3/CADP-24 / Review of Promotion and Support for A Single Stage - One E Small Works SPD Pending Imp 2026-03-0 the IIV Drinking Water Distrib COFN / C1580 Post Request for Bids Open - National 700,000.00 0.00 2024-04-30 2024-04-30 2024-07-09 2024-08-08 2024-09-12 gribusiness Development nvelope (1 envelope proce lementation 6 ution System in Huambo ss) 346/W3/CADP-24 / Rehabilit Request for Bids - ation of a Dam, including Sup Promotion and Support for A Single Stage - One E Small Works SPD Under Imple 2026-03-2 ply and Installation of a Syste COFN / C1580 Post Request for Bids Open - National 350,000.00 0.00 2024-05-21 2024-05-15 2024-05-21 2024-05-15 2024-07-30 2024-06-27 2024-08-29 2024-10-03 gribusiness Development nvelope (1 envelope proce mentation 7 m for Collection, Adduction a ss) nd Pivot Irrigation, at the IIA Experimental Station - Cela Request for Bids - 347/W1/CADP/24 / Santa Cla Promotion and Support for A Single Stage - One E Small Works SPD Pending Imp 2026-04-1 ra (Cunene) and Luvu (Zaire) IBRD / 88660 Post Request for Bids Open - National 380,000.00 0.00 2024-06-10 2024-06-10 2024-08-19 2024-09-18 2024-10-23 gribusiness Development nvelope (1 envelope proce lementation 6 Seed Control and Certificatio ss) n Post (Lot 1 & 2) 332A/W3/CADP/24 / Rehabili Request for Quota tation and restructuring work Promotion and Support for A Request for Quota Single Stage - One E Pending Imp 2025-03-2 IBRD / 88660 Post Limited - National tions (Non Bank-S 100,000.00 0.00 2024-07-31 2024-09-25 s of the plumbing system in gribusiness Development tions nvelope lementation 4 PD) Buildings 1 and 2 of MINAGRI F 348/W3/CADP-24 / Design a nd Construction of Medium V Request for Quota Promotion and Support for A Request for Quota Single Stage - One E Pending Imp 2025-03-2 oltage Electrical Infrastructur COFN / C1580 Post Limited - National tions (Non Bank-S 75,000.00 0.00 2024-07-31 2024-09-25 gribusiness Development tions nvelope lementation 4 es in the province of Huambo PD) , including repair of the inter nal low voltage network. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 001/GD/ACDP/17 / Supply of Project Management, Monito Request for Quota Single Stage - One E / Post Open - National 180,000.00 0.00 Canceled 2017-03-18 2017-04-22 2017-07-21 Vehicles (3) ring and Evaluation tions nvelope 007/GD/ACDP/17 / Supply of Project Management, Monito UN Agencies (Dire vehicles for the Project Imple IBRD / P4860 Prior Direct 180,000.00 102,941.35 Completed 2017-10-16 2017-10-13 2017-10-21 2017-11-02 2017-11-25 2017-11-25 2018-05-24 2018-04-07 ring and Evaluation ct) mentation Unit 002/GD/ACDP/17 / Supply of Project Management, Monito Request for Quota Single Stage - One E IBRD / P4860 Post Limited 50,000.00 22,626.49 Completed 2017-11-27 2017-12-07 2018-01-01 2018-03-12 2018-01-08 2018-09-25 IT equipment for PIU Office in ring and Evaluation tions nvelope Luanda 005/GD/ACDP/17 / Renovatio Project Management, Monito Request for Quota Single Stage - One E IBRD / P4860 Post Open - National 15,000.00 13,214.11 Completed 2017-11-06 2017-12-08 2017-12-18 2018-01-24 2017-12-25 2018-03-26 n of PIU office ring and Evaluation tions nvelope 003/GD/ACDP/17 / Supply of Project Management, Monito Request for Quota Single Stage - One E IBRD / P4860 Post Open - National 70,000.00 26,780.96 Completed 2017-11-25 2017-12-08 2018-01-20 2018-03-22 2018-02-10 2018-09-27 Office Furniture for PIU Offic ring and Evaluation tions nvelope e in Luanda 004/GD/ACDP/17 / Supply of Project Management, Monito Request for Quota Single Stage - One E IBRD / P4860 Post Open - National 15,000.00 19,462.35 Completed 2018-05-11 2018-06-15 2019-01-29 2018-06-22 2019-08-05 Accountant Software for the ring and Evaluation tions nvelope Project 006/GD/CADP/18 / Supply of Project Management, Monito UN Agencies (Dire IBRD / 88660 Post Direct 80,000.00 0.00 Canceled 2019-02-04 2019-09-11 2019-02-09 2019-09-11 2019-03-16 2019-09-12 Vehicles (3) ring and Evaluation ct) 002/GD/ACDP/18 / Supply of Project Management, Monito Request for Quota Single Stage - One E IBRD / P4860 Post Open - National 5,000.00 0.00 Canceled 2017-11-25 2017-12-30 2018-01-06 TC equipment for PIU ring and Evaluation tions nvelope 007/GD/CADP/18 / Supply of Project Management, Monito Request for Quota Single Stage - One E IBRD / 88660 Post Limited 65,000.00 29,221.33 Completed 2019-02-09 2019-03-20 2019-04-06 2019-06-23 2019-10-03 2019-08-01 IT equipment for PIU ring and Evaluation tions nvelope 009/GD/CADP/18 / Supply of Project Management, Monito Request for Quota Single Stage - One E IBRD / 88660 Post Limited 75,000.00 17,250.93 Completed 2019-01-30 2019-03-20 2019-03-27 2019-05-12 2019-09-23 2019-08-04 Office Furniture for PIU Offic ring and Evaluation tions nvelope e 074/CS/CADP/19 / Portable I Institutional Strengthening a Single Stage - One E T Equipment for field collecti COFN / C1580 nd Improved Business Enviro Post Request for Bids Open - National 800,000.00 611,543.73 Completed 2019-09-13 2019-10-29 2019-09-18 2019-10-29 2019-10-30 2019-11-29 2019-11-29 2020-04-08 2020-01-03 2020-06-18 2020-07-01 2020-10-04 nvelope on of primary information (Ta nment blets) 013/GD/CADP/20 / Office Eq Project Management, Monito IBRD / 88660 Post Direct Selection Direct 25,000.00 14,597.54 Completed 2020-04-30 2020-04-03 2020-05-05 2020-04-07 2020-06-03 2020-05-12 2020-08-02 2020-05-25 uipment for PIU/GEPE ring and Evaluation 012/GD/CADP/20 / Supply of Project Management, Monito Request for Quota Single Stage - One E IBRD / 88660 Post Limited 100,000.00 131,409.57 Completed 2020-05-05 2020-04-08 2020-06-30 2020-06-08 2020-10-28 2020-07-06 Vehicles (3) ring and Evaluation tions nvelope 084/CS/CADP/20 / Rehabilita Institutional Strengthening a Single Stage - One E tion of the communication ne COFN / C1580 nd Improved Business Enviro Post Request for Bids Open - National 537,000.00 0.00 Canceled 2020-02-21 2020-02-26 2020-04-08 2020-05-08 2020-06-12 2020-12-09 nvelope twork for Business intelligen nment ce GEPE 008/GD/CADP/18 / Supply of Project Management, Monito Request for Quota Single Stage - One E IBRD / 88660 Post Limited 10,000.00 0.00 Canceled 2021-07-14 2021-09-08 2022-03-07 TC equipment for PIU ring and Evaluation tions nvelope Page 2 105/G/CADP/21 / Vehicles to Institutional Strengthening a Request for Quota Single Stage - One E support GEPE on Statistic Dat COFN / C1580 nd Improved Business Enviro Post Limited 105,000.00 120,849.03 Completed 2021-05-31 2021-05-24 2021-07-14 2021-09-02 2021-09-12 2021-10-13 tions nvelope a collection nment 116/G/CADP/21 / Purchase of Two Vehicles (truck 4x4) to s Project Management, Monito Request for Quota Single Stage - One E COFN / C1580 Post Limited 130,000.00 0.00 Canceled 2021-10-29 2021-12-20 2022-04-19 upport FGC with Business Pla ring and Evaluation tions nvelope n implementation 117/G/CADP/21 / Laptops an d related IT equipment to su Project Management, Monito Request for Quota Single Stage - One E COFN / C1580 Post Limited 50,000.00 0.00 Canceled 2021-10-27 2021-10-25 2021-12-14 2022-04-13 pport CADP and FGC with Bu ring and Evaluation tions nvelope siness Plan implementation C 117/GD/CADP/21 / Purchas Institutional Strengthening a e of one Vehicles (truck 4x4) Request for Quota Single Stage - One E IBRD / 88660 nd Improved Business Enviro Post Limited 75,000.00 61,691.93 Signed 2021-12-20 2021-12-23 2022-02-14 2022-02-05 2022-08-13 to support the implementati tions nvelope nment on of the strategy 118/GD/CADP/22 / Laptops a nd related IT equipment to s Project Management, Monito Request for Quota Single Stage - One E COFN / C1580 Post Limited 50,000.00 85,160.85 Completed 2022-01-19 2022-01-12 2022-03-16 2022-04-03 2022-09-12 2022-08-13 upport CADP and FGC with B ring and Evaluation tions nvelope usiness Plan implementation 119/GD/CADP/22 / Purchase of Two Vehicles (truck 4x4) t Project Management, Monito Request for Quota Single Stage - One E COFN / C1580 Post Limited 130,000.00 148,833.85 Completed 2022-01-19 2022-01-18 2022-03-16 2022-03-28 2022-09-12 2022-05-10 o support FGC with Business ring and Evaluation tions nvelope Plan implementation C 121/G/CADP-22 / IT Equip Institutional Strengthening a Request for Quota Single Stage - One E COFN / C1580 Post Limited 50,000.00 0.00 Canceled 2022-03-09 2022-05-04 2022-10-31 ment for the Provicial Repres nd Improved Business Enviro tions nvelope entatives nment C 157G/CADP-22 / Procurem Project Management, Monito Single Stage - One E ent of agricultural machinery COFN / C1580 Post Request for Bids Open - National 318,000.00 0.00 Canceled 2022-03-11 2022-03-16 2022-04-27 2022-05-27 2022-07-01 2022-12-28 ring and Evaluation nvelope and equipment for INCA 122/G/CADP-22 / Purchase o Institutional Strengthening a Request for Quota Single Stage - One E f 4 vehicles (truck 4X4) to su COFN / C1580 nd Improved Business Enviro Post Limited 147,000.00 162,769.86 Completed 2022-03-30 2022-04-11 2022-05-25 2022-05-24 2022-11-21 2022-06-16 tions nvelope pport field specialists nment C 226/G/CADP-22 / Machines Project Management, Monito Single Stage - One E and Equipment for the Harm COFN / C1580 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2022-06-05 2022-06-10 2022-07-22 2022-08-21 2022-09-25 2023-03-24 ring and Evaluation nvelope onized Strategy C 227/G/CADP-22 / Reagents Promotion and Support for A Open - Internationa Single Stage - One E for laboratories and soils for t COFN / C1580 Prior Request for Bids 15,000,000.00 0.00 Canceled 2022-07-03 2022-07-08 2022-08-19 2022-09-18 2022-10-23 2023-04-21 gribusiness Development l nvelope he Harmonized Strategy C 228/G/CADP-22 / Glasswar Promotion and Support for A Open - Internationa Single Stage - One E e for Laboratories and Soils f COFN / C1580 Prior Request for Bids 13,300,000.00 0.00 Canceled 2022-07-03 2022-07-08 2022-08-19 2022-09-18 2022-10-23 2023-04-21 gribusiness Development l nvelope or the Harmonized Strategy C 233/G/CADP-22 / Acquisiti Promotion and Support for A Request for Quota Single Stage - One E on of installation of a mecha COFN / C1580 Post Limited 140,000.00 0.00 Canceled 2022-07-29 2022-09-23 2023-03-22 gribusiness Development tions nvelope nized sprinkler irrigation syst em C 237/G/CADP-22 / Greenho use installation: Greenhouse with 50x10x4 m2 (length x w Promotion and Support for A Single Stage - One E COFN / C1580 Post Request for Bids Open - National 335,000.00 0.00 Canceled 2022-07-24 2022-07-29 2022-09-09 2022-10-09 2022-11-13 2023-05-12 idth x height): 20 trays per b gribusiness Development nvelope ed: 42 beds per greenhouse: 63 tubes per tray (52920 tub es per greenhouse) C 238/G/CADP-22 / Acquisiti Promotion and Support for A Request for Quota Single Stage - One E on of office equipment and tr COFN / C1580 Post Limited 190,000.00 38,042.04 Completed 2022-07-01 2022-06-16 2022-08-26 2022-08-07 2023-02-22 2022-09-27 gribusiness Development tions nvelope aining support material for IN CA, IIA and IIV C 128/G/CADP-23 / Procurem Project Management, Monito Request for Quota Single Stage - One E COFN / C1580 Post Limited 120,000.00 44,301.17 Signed 2022-06-10 2022-07-25 2022-08-05 2022-07-21 2023-02-01 ent of IT Equipment for PIU's ring and Evaluation tions nvelope C 236/G/CADP-22 / Purchase Institutional Strengthening a Request for Quota Single Stage - One E of tree vehicles (truck 4X4) f COFN / C1580 nd Improved Business Enviro Post Limited 180,000.00 171,783.50 Completed 2022-05-27 2022-05-26 2022-07-22 2022-07-22 2023-01-18 2022-08-12 tions nvelope or provincial representatives nment C 127/G/CADP-22 / Procurem Institutional Strengthening a ent of 12 vehicles (4x4) for  COFN / C1580 nd Improved Business Enviro Post Direct Selection Direct 600,000.00 319,050.50 Signed 2022-06-26 2022-05-17 2022-07-01 2022-05-17 2022-08-05 2022-06-13 2023-02-01 Regional PIUs nment C 125/G/CADP-22 / Agricultu Promotion and Support for A Single Stage - One E ral Equipment for the Harmo COFN / C1580 Post Request for Bids Open - National 550,000.00 0.00 Canceled 2022-07-24 2022-07-29 2022-09-09 2022-10-09 2022-11-13 2023-05-12 gribusiness Development nvelope nized Strategy C 232/G/CADP-22 / Acquisiti Promotion and Support for A Single Stage - One E on of genetic material for gra COFN / C1580 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2022-07-31 2022-08-05 2022-09-16 2022-10-16 2022-11-20 2023-05-19 gribusiness Development nvelope ins (corn, beans, and soybea ns) C 234/G/CADP-22 / Impleme ntation of a drinking water co Promotion and Support for A Single Stage - One E COFN / C1580 Post Request for Bids Open - National 260,000.00 0.00 Canceled 2022-07-24 2022-07-29 2022-09-09 2022-10-09 2022-11-13 2023-05-12 llection system at the chiang gribusiness Development nvelope a station to support the prod uction of mini tubers C 271/G/CADP-22 / Procurem Project Management, Monito Single Stage - One E ent of 6 vehicles and accesso COFN / C1580 Post Request for Bids Open - National 1,000,000.00 0.00 Terminated 2022-07-19 2023-02-03 2022-07-24 2023-02-03 2022-09-04 2023-04-10 2022-10-04 2023-05-19 2022-11-08 2023-06-30 2023-05-07 ring and Evaluation nvelope ries for the harmonized strat egy C 270/G/CADP-22 / Glasswar Project Management, Monito Single Stage - One E e for Laboratories and Soils f COFN / C1580 Post Request for Bids Open - National 200,000.00 0.00 Completed 2022-07-18 2022-07-27 2022-07-23 2022-07-27 2022-09-03 2022-09-06 2022-10-03 2022-10-19 2022-11-07 2022-11-23 2023-05-06 2023-05-04 ring and Evaluation nvelope or the Harmonized Strategy C 269/G/CADP-22 / Procurem ent of phytosanitary laborato Project Management, Monito Single Stage - One E COFN / C1580 Post Request for Bids Open - National 350,000.00 0.00 Completed 2022-07-20 2022-08-09 2022-07-25 2022-08-09 2022-09-05 2022-09-19 2022-10-05 2022-12-14 2022-11-09 2023-02-26 2023-05-08 2024-04-02 ry equipment, reagents and c ring and Evaluation nvelope onsumables for the Harmoniz ed Strategy. C 287/G/CADP-22 / Implanta tion of rooting tunnel, nurseri Promotion and Support for A Open - Internationa Single Stage - One E es, clonal, garden, tests and COFN / C1580 Post Request for Bids 1,200,000.00 0.00 Canceled 2022-09-05 2022-09-27 2022-09-10 2022-09-27 2022-10-22 2022-09-06 2022-11-21 2022-12-26 2023-06-24 gribusiness Development l nvelope collection of cofee clones for INCA and respective irrigatio n system. Page 3 C 290/G/CADP-22 / Adequan cy and equipping of the seed laboratory,coffee quality anal Promotion and Support for A Open - Internationa Single Stage - One E COFN / C1580 Prior Request for Bids 2,100,000.00 0.00 Canceled 2022-09-08 2022-09-13 2022-10-25 2022-11-24 2022-12-29 2023-06-27 ysis laboratory in chianga, a gribusiness Development l nvelope nd equipment of the bromato logy laboratory in LAU Malanj e 309/G/3/CADP-22 / Network Institutional Strengthening a Open - Internationa Single Stage - One E IBRD / 88660 Prior Request for Bids 1,500,000.00 0.00 Signed 2022-10-31 2022-11-14 2022-11-05 2022-11-14 2022-12-17 2022-12-23 2023-01-16 2023-01-25 2023-02-20 2023-05-03 2024-02-20 Communication and Databas nd Improved Business Enviro l nvelope e nment 237A/G/CADP-22 / Procurem Promotion and Support for A Single Stage - One E ent and installation of a gree COFN / C1580 Post Request for Bids Open - National 335,000.00 0.00 Signed 2023-01-02 2023-01-17 2023-01-07 2023-07-13 2023-02-18 2023-08-29 2023-03-20 2023-09-28 2023-04-24 2023-10-26 2023-10-21 gribusiness Development nvelope nhouse for INCA 290A/G/CADP-22 / Acquisitio n and installation of equipme nt for the coffee quality labor Promotion and Support for A Open - Internationa Single Stage - One E atories in Cuanza Norte; of m COFN / C1580 Post Request for Bids 1,620,000.00 0.00 Canceled 2023-01-31 2023-02-05 2023-03-19 2023-04-18 2023-05-23 2024-05-22 gribusiness Development l nvelope aize seed analysis in Chianga -Huambo; and tube trays for clone greenhouses in Cuanza Norte. 321/G4/CADP-23 / Purchase Project Management, Monito Single Stage - One E of 6 vehicles to support the i COFN / C1580 Post Request for Bids Open - National 600,000.00 0.00 Signed 2023-03-31 2023-01-30 2023-04-05 2023-01-31 2023-05-17 2023-03-10 2023-06-16 2023-03-30 2023-07-21 2023-05-05 2024-07-20 ring and Evaluation nvelope mplementation of mechanis ms 235A/G3/CADP-23 / Impleme Promotion and Support for A Single Stage - One E ntation of cold storage cham IBRD / 88660 Post Request for Bids Open - National 370,000.00 0.00 Signed 2023-03-31 2023-01-19 2023-04-05 2023-01-19 2023-05-17 2023-02-28 2023-06-16 2023-03-14 2023-07-21 2023-04-22 2024-07-20 gribusiness Development nvelope bers for mini tubers. 290B/G3/CADP-23 / Acquisiti on and installation of coffee Promotion and Support for A Single Stage - One E quality analysis equipment; a COFN / C1580 Post Request for Bids Open - National 1,400,000.00 0.00 Signed 2023-04-30 2023-01-24 2023-05-05 2023-01-25 2023-06-16 2023-03-10 2023-07-16 2023-04-11 2023-08-20 2023-06-27 2024-08-19 gribusiness Development nvelope nd trays and tubes for INCA c offee clone greenhouses 271A/G3/CADP/23 / Procure Project Management, Monito Single Stage - One E ment of 6 vehicles and acces COFN / C1580 Post Request for Bids Open - National 1,400,000.00 0.00 Signed 2023-10-31 2023-08-30 2023-11-05 2023-08-29 2023-12-17 2023-10-17 2024-01-16 2023-11-07 2024-02-20 2024-01-26 2024-08-18 ring and Evaluation nvelope sories for the harmonized str ategy 287B/G3/CADP/23 / Procure Institutional Strengthening a Single Stage - One E ment and installation of irrig COFN / C1580 nd Improved Business Enviro Post Request for Bids Open - National 550,000.00 0.00 Signed 2023-12-31 2023-09-07 2024-01-05 2023-09-07 2024-02-16 2023-10-25 2024-03-17 2023-11-16 2024-04-21 2023-12-12 2024-10-18 nvelope ation system for INCA nment 291A/G3/CADP/23 / Procure ment and installation of equi Promotion and Support for A Single Stage - One E Under Imple COFN / C1580 Post Request for Bids Open - National 500,000.00 0.00 2023-12-31 2024-02-19 2024-01-05 2024-02-19 2024-02-16 2024-03-17 2024-04-21 2024-10-18 pment for the IIV bromatolog gribusiness Development nvelope mentation y laboratory in Santo António 292/G3/CADP/23 / Procurem ent of reagents and consuma Project Management, Monito Request for Quota Single Stage - One E Under Imple COFN / C1580 Post Limited 100,000.00 0.00 2024-01-05 2024-04-16 2024-03-01 2024-08-28 bles for the IIV bromatology l ring and Evaluation tions nvelope mentation aboratory in Santo António 287A/G/3/CADP-22 / Acquisit Institutional Strengthening a Open - Internationa Single Stage - One E ion of Irrigation System for th COFN / C1580 nd Improved Business Enviro Post Request for Bids 1,100,000.00 0.00 Canceled 2022-12-21 2022-11-16 2022-12-26 2022-11-16 2023-02-06 2023-03-08 2023-04-12 2023-10-09 l nvelope e Coffee Study Center in Cua nment nza Norte C 235/G/CADP-22 / Impleme Promotion and Support for A Single Stage - One E ntation of cold storage cham COFN / C1580 Post Request for Bids Open - National 260,000.00 0.00 Canceled 2022-07-03 2022-10-10 2022-07-08 2022-10-10 2022-08-19 2022-09-18 2022-10-23 2023-04-21 gribusiness Development nvelope bers and 120 kva generator f or mini tubers 336/G1/CADP/23 / Installatio Promotion and Support for A Single Stage - One E Under Imple n and equipping of seed cont IBRD / 88660 Post Request for Bids Open - National 845,655.00 0.00 2024-03-31 2024-05-14 2024-04-05 2024-05-14 2024-05-17 2024-07-04 2024-06-16 2024-07-21 2024-08-26 gribusiness Development nvelope mentation rol and certification centers 339/G3/CADP/23 / Implemen Promotion and Support for A Request for Quota Single Stage - One E Under Imple tation of Cold Storage Chamb IBRD / 88660 Post Limited 375,000.00 0.00 2024-03-05 2023-12-15 2024-04-30 2024-10-27 gribusiness Development tions nvelope mentation ers for Mini Tubers 308/G/3/CADP-22 / Purchase Promotion and Support for A Single Stage - One E of irrigation systems for INCA IBRD / 88660 Post Request for Bids Open - National 1,050,000.00 0.00 Canceled 2022-11-30 2022-12-05 2023-01-16 2023-02-15 2023-03-22 2024-03-21 gribusiness Development nvelope - Harmonized Strategy C 160/G/CADP-22 / Acquisiti Promotion and Support for A Request for Quota Single Stage - One E on and installation of irrigatio COFN / C1580 Post Limited 115,000.00 0.00 Canceled 2022-03-15 2022-05-10 2022-11-06 gribusiness Development tions nvelope n system for IIA 243/G3/CADP-24 / Acquisitio n of Reagents for Biofertilizer Promotion and Support for A Single Stage - One E Under Imple COFN / C1580 Post Request for Bids Open - National 300,000.00 0.00 2024-04-30 2024-05-30 2024-04-30 2024-05-30 2024-07-09 2024-07-12 2024-08-08 2024-09-12 2026-03-06 analysis and reagents for IIA gribusiness Development nvelope mentation Soil Laboratories in Chianga. 344/G3/CADP-24 / Equipping the Bromatology Laboratory Promotion and Support for A Single Stage - One E Pending Impl COFN / C1580 Post Request for Bids Open - National 350,000.00 0.00 2024-04-30 2024-04-30 2024-07-09 2024-08-08 2024-09-12 2026-03-06 and IIV support infrastructure gribusiness Development nvelope ementation in Santo António 345/G3/CADP-24 / Acquisitio n and installation of Metrolog Promotion and Support for A Single Stage - One E Under Imple ical stations and Acquisition COFN / C1580 Post Request for Bids Open - National 350,000.00 0.00 2024-04-30 2024-05-02 2024-04-30 2024-05-02 2024-07-09 2024-08-08 2024-09-12 2026-03-06 gribusiness Development nvelope mentation and installation of Military Ca terpillar Traps, within the sco pe of the Harmonized Strateg y. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 090/CS/CADP/20 / Business I Institutional Strengthening a Open - Internationa Single Stage - One E ntelligence and rehabilitation COFN / C1580 nd Improved Business Enviro Post Request for Bids 1,200,000.00 1,498,136.00 Signed 2020-05-04 2020-10-29 2020-05-09 2021-01-19 2020-06-20 2021-02-03 2020-07-20 2021-05-11 2020-08-24 2021-06-26 2021-08-24 l nvelope of the communication networ nment k for GEPE C 224/CS/CADP-22 / Enginee ring Studies and Projects for the Realization of Small Irriga Infrastructure for Production Open - Internationa Single Stage - One E tion Systems for PDAC Benefi COFN / C1580 Prior Request for Bids 3,100,000.00 0.00 Canceled 2022-10-23 2022-10-28 2022-12-09 2023-01-08 2023-02-12 2023-08-11 and Marketing l nvelope ciaries in the Provinces of MA LANJE, CUANZA NORTE, CUA NZA SUL, HUAMBO, BIÉ and HUÍLA Page 4 324/CS4/CADP/23 / Selection of Human Resources Compan Project Management, Monito y to recruit Interns in Public IBRD / 88660 Post Direct Selection Direct - National 30,000.00 0.00 Signed 2023-12-31 2023-09-27 2024-01-05 2023-08-11 2024-02-09 2023-09-28 2024-06-08 ring and Evaluation Contracting for Projects Fina nced by the World Bank in An gola 331/NC3/CADP/23 / Hosting Promotion and Support for A Request for Quota Single Stage - One E service and public launch of t IBRD / 88660 Post Limited 100,000.00 0.00 Canceled 2024-04-05 2024-05-31 2024-11-27 gribusiness Development tions nvelope he MINAGRIF Portal CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 010/CS/ACDP/16 / Consultan cy to support value chain ana lysis/development for Poultry Promotion and Support for A Quality And Cost- Open - Internationa & Eggs, Corn and Soy, and C IBRD / P4860 Prior 500,000.00 159,585.00 Completed 2017-03-13 2017-04-03 2017-08-22 2017-04-19 2017-12-08 2017-04-24 2017-12-08 2017-05-15 2018-01-12 2017-06-03 2018-03-07 2017-06-13 2018-03-22 2017-12-20 2018-12-26 gribusiness Development Based Selection l offee VCs. This would include studies, strategy developme nt, stakeohlder mobilization, build capacity at MINAGRI. 013/CS/ACDP/17 / Consultan Promotion and Support for A Consultant Qualifi Open - Internationa t to develop environmental st IBRD / P4860 Post 150,000.00 156,310.00 Completed 2017-03-20 2017-05-15 2017-04-03 2017-05-01 2017-06-19 2017-05-08 2017-07-03 2017-05-29 2017-08-01 2017-07-28 2018-05-19 gribusiness Development cation Selection l udies and related safeguard i nstruments 009/CS/ACDP/17 / Consultan Promotion and Support for A Consultant Qualifi Open - Internationa t to develop Social Safeguard / Post 120,000.00 0.00 Canceled 2017-03-20 2017-05-15 2017-04-03 2017-05-01 2017-06-19 2017-05-08 2017-05-29 2017-07-28 gribusiness Development cation Selection l studies and related Instrume nts 060/CS/CADP/18 / External A Project Management, Monito Least Cost Selecti Open - Internationa IBRD / 88660 Prior 200,000.00 87,865.50 Signed 2018-09-24 2018-09-26 2018-10-15 2018-10-07 2018-11-19 2019-03-05 2018-12-17 2019-06-21 2019-01-16 2019-09-23 2019-02-13 2019-10-15 2019-03-13 2019-12-01 2019-09-09 udit for PIU (first 3 years) ring and Evaluation on l 061/CS/CADP/18 / Survey of Infrastructure for Production Quality And Cost- Open - Internationa IBRD / 88660 Post 350,000.00 249,434.61 Signed 2018-10-29 2018-12-27 2018-11-19 2019-02-06 2019-01-02 2019-04-24 2019-01-30 2019-07-31 2019-03-01 2019-07-02 2019-04-05 2019-08-05 2019-05-10 2019-09-19 2020-05-09 supporting infrastructure Pha and Marketing Based Selection l se 2 052/CS/CADP/18 / TECHNICA L SERVICES PROVIDERS TO S Promotion and Support for A Quality And Cost- Open - Internationa UPPORT PROJECT INTERVENT IBRD / 88660 Prior 1,000,000.00 13,096,125.93 Signed 2019-01-31 2019-07-23 2019-02-21 2019-08-13 2019-04-06 2019-11-21 2019-05-04 2020-01-17 2019-06-03 2020-02-12 2019-07-08 2021-08-27 2019-08-12 2020-07-05 2020-08-11 gribusiness Development Based Selection l IONS FOR BUSINESS PLANS I MPLEMENTATION (TSP 1.1) 072/CS/CADP/19 / TECHNICA Institutional Strengthening a L SERVICES PROVIDERS TO S Quality And Cost- Open - Internationa IBRD / 88660 nd Improved Business Enviro Post 120,000.00 0.00 Canceled 2019-07-26 2019-07-14 2019-08-16 2019-09-29 2019-10-27 2019-11-26 2019-12-31 2020-02-04 2021-02-03 UPPORT THE SUB-COMPONE Based Selection l nment NT OF VALUE CHAIN STRATE GY DEVELOPMENT 070/CS/CADP/19 / Participat Infrastructure for Production Quality And Cost- Open - Internationa ory process for identification IBRD / 88660 Post 120,000.00 0.00 Canceled 2019-07-23 2019-07-15 2019-08-13 2019-09-26 2019-10-24 2019-11-23 2019-12-28 2020-02-01 2021-01-31 and Marketing Based Selection l of irrigation schemes 071/CS/CADP/19 / Feasibility Infrastructure for Production Quality And Cost- Open - Internationa study on rehabilitation of sm IBRD / 88660 Prior 120,000.00 550,032.08 Signed 2019-07-23 2019-10-29 2019-08-13 2019-10-29 2019-09-26 2020-02-18 2019-10-24 2020-04-30 2019-11-23 2020-06-08 2019-12-28 2020-08-04 2020-02-01 2020-10-23 2021-01-31 and Marketing Based Selection l all and medium-sized irrigate d perimeters 073/CS/CADP/19 / Technical Feasibility Study (TFS) Prepar Institutional Strengthening a atory Assistance for the desi UN Agencies (Dire COFN / C1580 nd Improved Business Enviro Prior Direct 494,000.00 493,810.00 Signed 2019-11-16 2020-09-26 2020-07-13 gn of a strategy to develop a ct) nment nd implement a unique syste m for international trade in A ngola 077/CS/CADP/19 / Technical Studies including environme Infrastructure for Production Quality And Cost- Open - Internationa COFN / C1580 Post 300,000.00 0.00 Canceled 2020-03-15 2020-04-05 2020-05-19 2020-06-16 2020-07-16 2020-08-20 2020-09-24 2021-09-24 ntal and social impact assess and Marketing Based Selection l ment for rural roads 064/CS/CADP/18 / TA on geo spatial mapping, feasibility, d Infrastructure for Production Quality And Cost- Open - Internationa IBRD / 88660 Prior 900,000.00 0.00 Canceled 2019-01-31 2019-04-22 2019-02-21 2019-05-01 2019-04-06 2019-09-07 2019-05-04 2019-10-11 2019-06-03 2019-11-14 2019-07-08 2019-08-12 2020-08-11 emand and cost studies for r and Marketing Based Selection l ural electrifications 087/CS/CADP/20 / Technical Services Providers to support Promotion and Support for A Quality Based Sel Open - Internationa COFN / C1580 Prior 400,000.00 1,022,684.00 Signed 2020-04-15 2020-04-11 2020-05-06 2020-04-14 2020-06-19 2020-07-24 2020-07-17 2020-10-08 2020-08-16 2020-11-30 2020-09-15 2021-03-03 2020-10-20 2021-03-31 2022-10-20 Financial Sector intervention gribusiness Development ection l for partial credit guarantees 069/CS/CADP/19 / Technical Services Providers to support Promotion and Support for A Quality And Cost- Open - Internationa IBRD / 88660 Post 200,000.00 0.00 Canceled 2019-07-14 2019-07-15 2019-08-04 2019-09-17 2019-10-15 2019-11-14 2019-12-19 2020-01-23 2021-01-22 Financial Sector intervention gribusiness Development Based Selection l for partial credit guarantees (TSP 1.2) 093/CS/CADP/20 / Priorizatio Infrastructure for Production Quality And Cost- Open - Internationa n Studies and Design for Mal COFN / C1580 Prior 837,000.00 576,294.43 Signed 2020-09-18 2020-09-21 2020-10-09 2020-10-26 2020-11-22 2021-03-05 2020-12-20 2021-05-13 2021-01-19 2021-09-23 2021-02-23 2022-03-18 2021-03-30 2022-04-22 2021-09-26 and Marketing Based Selection l anje, Cuanza Norte and Cuan za Sul 094/CS/CADP/20 / Innovative Infrastructure for Production Quality And Cost- Open - Internationa Management Systems for Irri COFN / C1580 Post 200,000.00 157,225.00 Signed 2020-10-11 2020-09-20 2020-11-01 2020-10-05 2020-12-15 2020-11-27 2021-01-12 2021-01-19 2021-02-11 2021-02-26 2021-03-18 2021-05-31 2021-04-22 2021-07-05 2021-08-20 and Marketing Based Selection l gated Perimeters 085/CS/CADP/20 / Environm ental and social assessment Infrastructure for Production Quality And Cost- IBRD / 88660 Post Open - National 80,000.00 0.00 Canceled 2020-05-22 2020-06-12 2020-07-26 2020-08-23 2020-09-22 2020-10-27 2020-12-01 2021-12-01 studies for electrical connecti and Marketing Based Selection on works - Kwanza Norte, Kw anza Sul, Malange 075/CS/CADP/19-2 / Particip Infrastructure for Production Quality And Cost- Open - Internationa atory process for identificatio COFN / C1580 Post 120,000.00 0.00 Canceled 2020-02-28 2019-11-06 2020-03-20 2020-05-03 2020-05-31 2020-06-30 2020-08-04 2020-09-08 2021-09-08 and Marketing Based Selection l n of irrigation schemes 035/CS/CADP/18 / Consultan cy Design Review and Works Infrastructure for Production Quality And Cost- Open - Internationa COFN / C1580 Post 350,000.00 0.00 Canceled 2020-03-30 2020-03-13 2020-04-20 2020-06-03 2020-07-01 2020-07-31 2020-09-04 2020-10-09 2021-10-09 Supervision including E&S Sa and Marketing Based Selection l feguards, PHASE 1 Kwanza N orte 076/CS/CADP/20 / Consultan cy Design Review and Works Infrastructure for Production Quality And Cost- Open - Internationa COFN / C1580 Post 350,000.00 0.00 Canceled 2020-03-27 2020-03-13 2020-04-17 2020-05-31 2020-06-28 2020-07-28 2020-09-01 2020-10-06 2021-10-06 Supervision, including E&S S and Marketing Based Selection l afeguards, PHASE 1 Kwanza Sul Page 5 078/CS/CADP/19 / Consultan cy Design Review and Works Infrastructure for Production Quality And Cost- Open - Internationa COFN / C1580 Post 350,000.00 0.00 Canceled 2020-03-30 2020-03-11 2020-04-20 2020-06-03 2020-07-01 2020-07-31 2020-09-04 2020-10-09 2021-10-09 Supervision, including E&S S and Marketing Based Selection l afeguards, PHASE 1 Malange 051/CS/CADP/18 / Business I Institutional Strengthening a Quality And Cost- Open - Internationa COFN / C1580 Prior 850,000.00 0.00 Canceled 2020-02-28 2020-03-20 2020-05-03 2020-05-31 2020-06-30 2020-08-04 2020-09-08 2021-09-08 ntelligence for GEPE nd Improved Business Enviro Based Selection l nment 017/CS/ACDP/16 / Project Ba Project Management, Monito Quality And Cost- Open - Internationa COFN / C1580 Post 300,000.00 0.00 Canceled 2020-03-06 2020-09-10 2020-03-27 2020-04-24 2020-04-29 2020-05-14 2020-06-03 2020-06-13 2020-09-11 seline Survey ring and Evaluation Based Selection l 088/CS/CADP/20 / TECHNICA L SERVICES PROVIDERS TO S Institutional Strengthening a Quality And Cost- Open - Internationa UPPORT THE SUB-COMPONE COFN / C1580 nd Improved Business Enviro Post 500,000.00 497,900.00 Signed 2021-04-16 2021-04-19 2021-05-01 2021-04-29 2021-06-01 2021-08-31 2021-06-29 2021-10-11 2021-07-20 2021-11-24 2021-08-20 2021-12-24 2021-09-09 2022-01-29 2023-08-30 Based Selection l NT ON PUBLIC-PRIVATE DIAL nment OGUE ON VALUE CHAIN STRA TEGY DEVELOPMENT 036/CS/CADP/19 / Supervisio n of Works for Rehabilitation Infrastructure for Production Quality And Cost- Open - Internationa COFN / C1580 Post 800,000.00 0.00 Signed 2021-10-22 2021-10-05 2021-11-05 2022-01-17 2021-11-22 2022-04-20 2021-12-22 2022-06-01 2022-01-06 2022-07-15 2022-01-31 2022-08-02 2022-02-20 2022-09-05 2023-02-20 of Small and Medium Irrigate and Marketing Based Selection l d Perimeters Kwanza Norte ( Lot 1) C 190/CS/CADP-22 / Supervi sion of the Rehabilitation Wo Infrastructure for Production Quality And Cost- Open - Internationa COFN / C1580 Post 850,000.00 0.00 Canceled 2022-03-04 2022-03-25 2022-05-08 2022-06-05 2022-07-05 2022-08-09 2022-09-13 2023-09-13 rks of the Irrigated Perimeter and Marketing Based Selection l s of Cacala and Korea in Kwa nza Norte C 204/CS/CADP-22 / Consult ancy to support the creation Institutional Strengthening a Quality And Cost- of a quality policy and a legis COFN / C1580 nd Improved Business Enviro Post Open - National 150,000.00 0.00 Canceled 2022-03-07 2022-05-25 2022-03-28 2022-05-11 2022-06-08 2022-07-08 2022-08-12 2022-09-16 2023-09-16 Based Selection lative package for the reform nment ulation of the National Qualit y System (SNQ) C 220/CS/CADP-22 / Consulti Institutional Strengthening a ng services for the elaboratio Quality And Cost- Open - Internationa COFN / C1580 nd Improved Business Enviro Post 640,000.00 0.00 Terminated 2022-03-07 2022-06-15 2022-03-28 2022-06-22 2022-05-11 2022-11-16 2022-06-08 2023-02-06 2022-07-08 2023-03-28 2022-08-12 2023-04-19 2022-09-16 2023-06-21 2023-09-16 n of the Revision of the Basic Based Selection l nment Law on Agrarian Developmen t C 208CS/CADP-22 / Study - E Institutional Strengthening a laboration of the Update of t Quality And Cost- Open - Internationa COFN / C1580 nd Improved Business Enviro Prior 2,950,000.00 0.00 Canceled 2022-03-07 2022-03-28 2022-05-11 2022-06-08 2022-07-08 2022-08-12 2022-09-16 2023-09-16 he Zoning Characterization a Based Selection l nment nd of the Phoclimatic of Ango la C 197/CS/CADP-22 / External Project Management, Monito Least Cost Selecti COFN / C1580 Post Open - National 90,000.00 0.00 Signed 2022-03-03 2022-04-08 2022-03-24 2022-04-19 2022-05-07 2022-07-08 2022-06-04 2022-08-19 2022-07-04 2022-10-03 2022-08-08 2022-10-25 2022-09-12 2022-12-22 2023-03-11 Audit 2022-2024 ring and Evaluation on C 219/CS/CADP-22 / Consult Project Management, Monito Quality And Cost- ancy for the preparation of st COFN / C1580 Post Open - National 300,000.00 0.00 Canceled 2022-03-07 2022-05-25 2022-03-28 2022-05-11 2022-06-08 2022-07-08 2022-08-12 2022-09-16 2023-09-16 ring and Evaluation Based Selection udies on competitiveness an d productivity C 244/CS/CADP-22 / Supervi sion of the rehabilitation wor Infrastructure for Production Quality And Cost- ks of rural roads of access to COFN / C1580 Post Open - National 840,000.00 0.00 Canceled 2022-09-18 2022-10-09 2022-11-22 2022-12-20 2023-01-19 2023-02-23 2023-03-30 2024-03-29 and Marketing Based Selection the perimeters of Bom Jesus, Mucoso, Cacala, Coreia 1, an d Cauá C 246/CS/CADP-22 / Supervi sion of the rehabilitation wor Infrastructure for Production Quality And Cost- Open - Internationa ks of priorized rural roads in t COFN / C1580 Post 850,000.00 0.00 Canceled 2022-10-23 2022-09-19 2022-11-13 2022-12-27 2023-01-24 2023-02-23 2023-03-30 2023-05-04 2024-05-03 and Marketing Based Selection l he provinces of Malanje, Cua nza Norte and Cuanza Sul C 256/CS/CADP-22 / Study o Promotion and Support for A Quality And Cost- n agricultural competitivenes COFN / C1580 Post Open - National 300,000.00 0.00 Canceled 2022-06-26 2022-07-17 2022-08-30 2022-09-27 2022-10-27 2022-12-01 2023-01-05 2024-01-05 gribusiness Development Based Selection s and productivity C 252/CS/CADP-22 / Selectio Institutional Strengthening a Consultant Qualifi n of Consultant firm to under COFN / C1580 nd Improved Business Enviro Post Open - National 150,000.00 0.00 Canceled 2022-06-15 2022-05-27 2022-07-06 2022-08-16 2022-08-19 2022-09-18 2022-10-23 2023-04-21 cation Selection take the Project Baseline Sur nment vey (Mosap III) 110/CS/CADP/21 / Technical Institutional Strengthening a Assistance for review and up Quality And Cost- COFN / C1580 nd Improved Business Enviro Post Open - National 210,000.00 0.00 Canceled 2021-04-11 2021-10-12 2021-04-26 2021-05-27 2022-05-09 2021-06-24 2022-06-27 2021-07-15 2022-07-21 2021-08-15 2021-09-04 2022-09-04 date of the Mid-Term Plan of Based Selection nment the Agrarian Sector (year 20 22 -2027) 103/CS/CADP/21 / Technical Institutional Strengthening a Assistance on revision of the Quality And Cost- Open - Internationa COFN / C1580 nd Improved Business Enviro Post 400,000.00 0.00 Canceled 2021-10-15 2021-10-12 2021-10-30 2021-11-30 2021-12-28 2022-01-27 2022-03-08 2022-03-28 2023-03-28 Basic Law of Agrarian Develo Based Selection l nment pment (Law No. 15/05 of 7 D ecember) C 225/C/CADP-22 / Priorizati on and Engineering Studies f Infrastructure for Production Quality And Cost- Open - Internationa or the rehabilitation of rural r COFN / C1580 Prior 6,000,000.00 0.00 Canceled 2022-08-21 2022-09-11 2022-10-25 2022-11-22 2022-12-22 2023-01-26 2023-03-02 2024-03-01 and Marketing Based Selection l oads in the provinces of Mala nje Cuanza Norte, Cuanza Sul , Huambo, Bié and Huila C 241/C/CADP-22 / Feaseabil ity and Engineering Studies f or the Reahabilitation of 20 Infrastructure for Production Quality And Cost- COFN / C1580 Prior Open - National 2,400,000.00 0.00 Canceled 2022-08-21 2022-09-11 2022-10-25 2022-11-22 2022-12-22 2023-01-26 2023-03-02 2024-03-01 00ha (in each Province ) of ir and Marketing Based Selection rigated Schemes on Provinc es of Huíla, Bié, Huambo, Cu anza Norte and Cuanza Sul 305/CS/3/CADP/22 / Technic Institutional Strengthening a al Assistance for review and Quality And Cost- COFN / C1580 nd Improved Business Enviro Post Open - National 600,000.00 0.00 Canceled 2022-09-20 2022-09-13 2022-10-11 2022-09-20 2022-11-24 2022-12-22 2023-01-21 2023-02-25 2023-04-01 2024-03-31 update of the Mid-Term Plan Based Selection nment of the Agrarian Sector (year 2022 -2027) 306/C/2/CADP-22 / Feaseabil ity and Engineering Studies f or the Reahabilitation of 200 Infrastructure for Production Quality And Cost- COFN / C1580 Prior Open - National 2,400,000.00 0.00 Canceled 2022-09-20 2022-10-20 2022-10-11 2022-11-24 2022-12-22 2023-01-21 2023-02-25 2023-04-01 2024-03-31 0ha (in each Province ) of irri and Marketing Based Selection gated Schemes on Provinces of Huíla, Bié, Huambo, Cuanz a Norte and Cuanza Sul 307/C/2/CADP-22 / Priorizati on and Engineering Studies f Infrastructure for Production Quality And Cost- Open - Internationa or the rehabilitation of rural r COFN / C1580 Prior 6,000,000.00 0.00 Canceled 2022-09-20 2022-09-19 2022-10-11 2022-11-24 2022-12-22 2023-01-21 2023-02-25 2023-04-01 2024-03-31 and Marketing Based Selection l oads in the provinces of Mala nje Cuanza Norte, Cuanza Sul , Huambo, Bié and Huila Page 6 002/CS/3/MOSAP3-22 / Cons ultancy Services for Technica Institutional Strengthening a Quality And Cost- Open - Internationa l Field Operator for the Trans IBRD / 88660 nd Improved Business Enviro Prior 1,200,000.00 0.00 Canceled 2022-11-30 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2025-05-31 Based Selection l formation Project of Family F nment arming of Angola (MOSAP 3) 003/CS/3/MOSAP3-22 / Cons Institutional Strengthening a ultancy Services for Rural Ext Quality And Cost- Open - Internationa IBRD / 88660 nd Improved Business Enviro Post 600,000.00 0.00 Canceled 2022-11-30 2022-10-26 2022-12-21 2022-11-01 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2025-05-31 ension, Technical Assistance Based Selection l nment and Institutionalization of the Approach for ECA 004/CS/3/MOSAP3-22 / Cons Institutional Strengthening a Quality And Cost- Open - Internationa ulting Services for the Functi COFN / C1580 nd Improved Business Enviro Prior 1,012,500.00 0.00 Canceled 2022-11-30 2022-10-26 2022-12-21 2022-11-14 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2026-06-10 Based Selection l onal Literacy of the Beneficia nment ries 306A/CS/2/CADP-22 / Feasibi lity and Engineering Studies f or the Rehabilitation of 1500 Infrastructure for Production Quality And Cost- Open - Internationa Under Implement COFN / C1580 Prior 1,120,050.00 0.00 2022-12-31 2022-10-25 2023-01-21 2022-11-28 2023-03-06 2023-03-27 2023-04-03 2023-05-26 2023-05-03 2023-08-23 2023-06-07 2024-06-05 2023-07-12 2024-07-11 ha (in each Province ) of irrig and Marketing Based Selection l ation ated Schemes on Provinces o f Cuanza Sul, Huambo, Bié, H uíla and Lunda Sul 242A/CS2/CADP/23 / Supervi Infrastructure for Production Quality And Cost- Open - Internationa sion of Works for Rehabilitati COFN / C1580 Prior 1,440,000.00 0.00 Under Review 2024-01-31 2024-02-07 2024-02-21 2024-02-22 2024-04-05 2024-05-23 2024-05-03 2024-07-10 2024-06-02 2024-07-07 2024-08-11 2025-08-11 and Marketing Based Selection l on of Small and Medium Peri meters of Cauá 323/CS2/CADP/23 / Design C Infrastructure for Production Quality And Cost- Open - Internationa Pending Impleme hecking and Works Supervisi COFN / C1580 Prior 1,794,000.00 0.00 2024-01-31 2024-02-21 2024-04-05 2024-05-03 2024-06-02 2024-07-07 2024-08-11 2025-08-11 and Marketing Based Selection l ntation on of perimeter in Sumbe 310/CS/3/CADP-22 / Consulti ng services for the elaboratio n of environmental and socia Institutional Strengthening a l safeguards instruments wit Consultant Qualifi COFN / C1580 nd Improved Business Enviro Post Limited 261,000.00 0.00 Canceled 2022-11-01 2022-10-23 2022-11-15 2022-12-15 2022-12-15 2023-01-19 2023-07-18 hin the scope of the lowest c cation Selection nment ost geospatial electrification project for the last mile exte nsion of the network in the pr ovinces of Cuanza Norte 311/CS/3/CADP-22 / Consulti ng services for the elaboratio n of environmental and socia Institutional Strengthening a l safeguards instruments wit Consultant Qualifi COFN / C1580 nd Improved Business Enviro Post Limited 261,000.00 0.00 Canceled 2022-11-01 2022-10-23 2022-11-15 2022-12-15 2022-12-15 2023-01-19 2023-07-18 hin the scope of the lowest c cation Selection nment ost geospatial electrification project for the last mile exte nsion of the network in the pr ovinces of Cuanza Sul 312/CS/3/CADP-22 / Consulti ng services for the elaboratio n of environmental and socia Institutional Strengthening a l safeguards instruments wit Consultant Qualifi COFN / C1580 nd Improved Business Enviro Post Limited 261,000.00 0.00 Canceled 2022-11-01 2022-10-23 2022-11-15 2022-12-15 2022-12-15 2023-01-19 2023-07-18 hin the scope of the lowest c cation Selection nment ost geospatial electrification project for the last mile exte nsion of the network in the pr ovinces of Malanje 313/CS/3/CADP-22 / Study fo Institutional Strengthening a r Updating the Agro-Ecologic Quality And Cost- Open - Internationa IBRD / 88660 nd Improved Business Enviro Prior 1,000,000.00 0.00 Canceled 2022-12-31 2022-11-09 2023-01-21 2022-11-28 2023-03-06 2023-04-03 2023-05-03 2023-06-07 2023-07-12 2024-08-10 al Characterization of Angola Based Selection l nment Region 1 – Cabinda, Zaire, Ui ge, Bengo and Luanda 314/CS/3/CADP-22 / Study fo r Updating the Agro-Ecologic Institutional Strengthening a Quality And Cost- Open - Internationa al Characterization of Angola IBRD / 88660 nd Improved Business Enviro Prior 1,000,000.00 0.00 Canceled 2022-12-31 2022-11-09 2023-01-21 2022-11-28 2023-03-06 2023-04-03 2023-05-03 2023-06-07 2023-07-12 2024-08-10 Based Selection l Region 2 – Cuanza Norte, Cu nment anza Sul, Malanje, Huambo a nd Bié 315/CS/3/CADP-22 / Study fo Institutional Strengthening a r Updating the Agro-Ecologic Quality And Cost- Open - Internationa IBRD / 88660 nd Improved Business Enviro Prior 1,000,000.00 0.00 Canceled 2022-12-31 2022-11-09 2023-01-21 2022-11-26 2023-03-06 2023-04-03 2023-05-03 2023-06-07 2023-07-12 2024-08-10 al Characterization of Angola Based Selection l nment Region 3 – Benguela, Huíla, N amibe and Cunene C 242/CS/CADP-22 / Supervi sion of Works for Rehabilitati Infrastructure for Production Quality And Cost- COFN / C1580 Post Open - National 500,000.00 0.00 Canceled 2022-09-18 2022-10-09 2022-11-22 2022-12-20 2023-01-19 2023-02-23 2023-03-30 2024-03-29 on of Small and Medium Peri and Marketing Based Selection meters of Cuanza Sul (Lot 3) 328/CS3/CADP/23 / Consulti Infrastructure for Production Quality And Cost- Open - Internationa ng service for updating PLANI IBRD / 88660 Prior 1,373,916.97 0.00 Canceled 2024-04-30 2024-04-16 2024-05-21 2024-07-04 2024-08-01 2024-08-31 2024-10-05 2024-11-09 2025-11-09 and Marketing Based Selection l RRIGA and preparing executi ve projects 337/CS2/CADP/23 / Studies o f Small Irrigation Systems up Promotion and Support for A Quality And Cost- Open - Internationa Under Implement to 5ha, in the Provinces of Cu IBRD / 88660 Prior 1,813,091.91 0.00 2024-04-30 2024-01-18 2024-05-21 2024-02-02 2024-07-04 2024-05-07 2024-08-01 2024-07-03 2024-08-31 2024-10-05 2024-11-09 2025-12-14 gribusiness Development Based Selection l ation anza Norte, Cuanza Sul, Mala nje, Bié, Huíla and Huambo 333/CS2/CADP/23 / Consulta ncy service for the preparatio Promotion and Support for A Quality And Cost- Open - Internationa Under Implement IBRD / 88660 Post 820,589.79 0.00 2024-06-30 2024-01-26 2024-07-21 2024-02-02 2024-09-03 2024-05-02 2024-10-01 2024-07-02 2024-10-31 2024-12-05 2025-01-09 2026-01-09 n of ESIAS for electrification gribusiness Development Based Selection l ation of the perimeters of Cacala, Corea and Caua 335/CS2/CADP/23 / Consulta ncy service for Design Verific Infrastructure for Production Quality And Cost- Open - Internationa Under Implement ation and Supervision of Elec IBRD / 88660 Post 625,442.34 0.00 2024-03-31 2024-03-20 2024-04-21 2024-03-25 2024-06-04 2024-07-02 2024-08-01 2024-09-05 2024-10-10 2025-10-10 and Marketing Based Selection l ation trification Works in the Cacal a, Corea and Caua perimeter s 327/CS4/CADP/23 / External Project Management, Monito Least Cost Selecti Open - Internationa IBRD / 88660 Post 300,000.00 0.00 Signed 2024-02-29 2023-12-01 2024-03-15 2023-12-06 2024-04-13 2024-01-14 2024-05-11 2024-02-27 2024-06-10 2024-03-20 2024-07-15 2024-04-23 2024-08-19 2024-06-10 2025-08-19 Audit 2022-2024 ring and Evaluation on l C 272/C/CADP-22 / Engineeri ng Studies and Projects for th Infrastructure for Production Quality And Cost- e Realization of Small Irrigati COFN / C1580 Post Open - National 393,000.00 0.00 Canceled 2022-07-28 2022-07-27 2022-08-18 2022-10-06 2022-10-01 2023-01-06 2022-10-29 2023-03-07 2022-11-28 2023-03-31 2023-01-02 2023-02-06 2024-02-06 and Marketing Based Selection on Systems for PDAC Benefic iaries, in the Province of Bié C 275/C/CADP-22 / Engineeri ng Studies and Projects for th Infrastructure for Production Quality And Cost- e Realization of Small Irrigati COFN / C1580 Post Open - National 393,000.00 0.00 Canceled 2022-07-28 2022-07-27 2022-08-18 2022-10-06 2022-10-01 2023-01-06 2022-10-29 2023-03-07 2022-11-28 2023-03-31 2023-01-02 2023-02-06 2024-02-06 and Marketing Based Selection on Systems for PDAC Benefic iaries, in the Province of Mala nje Page 7 C 276/C/CADP-22 / Engineeri ng Studies and Projects for th Infrastructure for Production Quality And Cost- e Realization of Small Irrigati COFN / C1580 Post Open - National 393,000.00 0.00 Canceled 2022-07-28 2022-07-27 2022-08-18 2022-10-06 2022-10-01 2023-01-06 2022-10-29 2023-03-07 2022-11-28 2023-03-31 2023-01-02 2023-02-06 2024-02-06 and Marketing Based Selection on Systems for PDAC Benefic iaries, in the Province of Cua nza Norte C 277/C/CADP-22 / Engineeri ng Studies and Projects for th Infrastructure for Production Quality And Cost- e Realization of Small Irrigati COFN / C1580 Post Open - National 393,000.00 0.00 Canceled 2022-07-28 2022-07-27 2022-08-18 2022-10-06 2022-10-01 2022-10-29 2022-11-28 2023-01-02 2023-02-06 2024-02-06 and Marketing Based Selection on Systems for PDAC Benefic iaries, in the Province of Cua nza Sul C 278/C/CADP-22 / Engineeri ng Studies and Projects for th Infrastructure for Production Quality And Cost- e Realization of Small Irrigati COFN / C1580 Post Open - National 393,000.00 0.00 Canceled 2022-07-28 2022-10-04 2022-08-18 2022-10-06 2022-10-01 2023-01-06 2022-10-29 2023-03-07 2022-11-28 2023-04-13 2023-01-02 2023-04-26 2023-02-06 2024-02-06 and Marketing Based Selection on Systems for PDAC Benefic iaries, in the Province of Hua mbo C 279/C/CADP-22 / Engineeri ng Studies and Projects for th Infrastructure for Production Quality And Cost- e Realization of Small Irrigati COFN / C1580 Post Open - National 393,000.00 0.00 Canceled 2022-07-28 2022-09-22 2022-08-18 2022-10-06 2022-10-01 2022-10-29 2022-11-28 2023-01-02 2023-02-06 2024-02-06 and Marketing Based Selection on Systems for PDAC Benefic iaries, in the Province of Huil a 316/CS/3/CADP-22 / Study fo r Updating the Agro-Ecologic Institutional Strengthening a Quality And Cost- Open - Internationa al Characterization of Angola IBRD / 88660 nd Improved Business Enviro Prior 1,000,000.00 0.00 Canceled 2022-12-31 2022-11-09 2023-01-21 2022-11-26 2023-03-06 2023-04-03 2023-05-03 2023-06-07 2023-07-12 2024-08-10 Based Selection l Region 4 – Lunda Norte, Lund nment a Sul, Moxico and Cuando Cu bango 050/CS/CADP/21 / Technical Institutional Strengthening a Quality And Cost- Open - Internationa Assistance for the completio COFN / C1580 nd Improved Business Enviro Prior 1,000,000.00 0.00 Canceled 2021-05-14 2021-08-13 2021-05-29 2021-08-23 2021-06-29 2022-03-01 2021-07-27 2022-04-22 2021-08-17 2022-08-24 2021-09-17 2022-10-19 2021-10-18 2023-10-18 Based Selection l n and implementation of PLA nment NIRRIGA 101/CS/CADP/20 / Consultan Project Management, Monito Quality And Cost- Open - Internationa cy Services for Monitoring an IBRD / 88660 Prior 800,000.00 0.00 Canceled 2021-01-29 2021-01-27 2021-02-19 2021-02-03 2021-04-04 2021-09-03 2021-05-02 2021-10-13 2021-06-01 2021-07-06 2021-08-10 2025-08-09 ring and Evaluation Based Selection l d Evaluation of the CADP 053/CS/CADP/18 / Technical Institutional Strengthening a assistance for capacity buildi Quality And Cost- Open - Internationa COFN / C1580 nd Improved Business Enviro Prior 500,000.00 0.00 Canceled 2022-03-31 2022-04-15 2022-05-16 2022-06-13 2022-07-04 2022-08-04 2022-08-24 2023-08-24 ng in research and developm Based Selection l nment ent (to support the 3 inst: IN CA, IIA, IIV) 099/CS/CADP/20 / Supervisio Infrastructure for Production Quality And Cost- Open - Internationa COFN / C1580 Post 850,000.00 0.00 Canceled 2021-10-15 2021-10-30 2021-11-30 2021-12-28 2022-01-18 2022-02-18 2022-03-10 2023-03-10 n for Works PHASE 1 Malang and Marketing Based Selection l e (Lot 1) 080/CS/CADP/20 / Technical Institutional Strengthening a Quality And Cost- Service Provider (TSP) Weat COFN / C1580 nd Improved Business Enviro Post Open - National 250,000.00 0.00 Canceled 2022-04-29 2022-05-14 2022-06-14 2022-07-12 2022-08-02 2022-09-02 2022-09-22 2023-03-21 Based Selection her index-based crop insuran nment ce studies C 221/CS/CADP-22 / Consult Institutional Strengthening a ancy services for the Nationa Quality And Cost- COFN / C1580 nd Improved Business Enviro Post Open - National 300,000.00 0.00 Canceled 2022-03-07 2022-03-28 2022-05-11 2022-06-08 2022-07-08 2022-08-12 2022-09-16 2023-09-16 l Registry of Agricultural Tran Based Selection nment sformation (RNTA) 079/CS/CADP/20 / Supervisio n for Works of electrical con Infrastructure for Production Quality And Cost- Open - Internationa IBRD / 88660 Prior 1,250,000.00 0.00 Canceled 2022-01-10 2022-01-25 2022-02-25 2022-03-25 2022-04-15 2022-05-16 2022-06-05 2023-06-05 nections, including design re and Marketing Based Selection l vision in Kwanza Norte, Kwa nza Sul and Malange 098/CS/CADP/20 / Supervisio Infrastructure for Production Quality And Cost- Open - Internationa COFN / C1580 Post 850,000.00 0.00 Canceled 2022-04-18 2022-05-03 2022-06-03 2022-07-01 2022-07-22 2022-08-22 2022-09-11 2023-06-08 n for Works PHASE 1 Kwanza and Marketing Based Selection l Sul (Lot 3) C 210/CS/CADP-22 / Consult Institutional Strengthening a Quality And Cost- Open - Internationa ancy for the strengthening of COFN / C1580 nd Improved Business Enviro Prior 1,500,000.00 0.00 Canceled 2022-03-07 2022-03-28 2022-05-11 2022-06-08 2022-07-08 2022-08-12 2022-09-16 2023-09-16 Based Selection l a National Food Security syst nment em C 205/CS/CADP-22 / Consulti Institutional Strengthening a ng services for the implemen Quality And Cost- COFN / C1580 nd Improved Business Enviro Post Open - National 500,000.00 0.00 Canceled 2022-03-17 2022-04-07 2022-05-21 2022-06-18 2022-07-18 2022-08-22 2022-09-26 2023-09-26 tation of the Monitoring and Based Selection nment Monitoring Unit of Projects Fi nanced by Multilaterals 095/CS/CADP/20 / Supervisio Infrastructure for Production Quality And Cost- Open - Internationa n for rehabilitation of Irrigatio COFN / C1580 Post 800,000.00 0.00 Canceled 2022-01-12 2022-01-27 2022-02-27 2022-03-27 2022-04-17 2022-05-18 2022-06-07 2023-06-07 and Marketing Based Selection l n infrastructure (Lot 2) 079A/CS2/CADP/23 / Design Checking and Supervision for Infrastructure for Production Quality And Cost- Open - Internationa IBRD / 88660 Prior 2,000,000.00 0.00 Canceled 2024-02-29 2024-03-21 2024-05-04 2024-06-01 2024-07-01 2024-08-05 2024-09-09 2025-09-09 Works of electrical connectio and Marketing Based Selection l ns - Kwanza Norte, Kwanza S ul and Malange C 273/CS/CADP-22 / Comput Institutional Strengthening a er System for the National Re Consultant Qualifi COFN / C1580 nd Improved Business Enviro Post Open - National 120,000.00 0.00 Canceled 2022-07-20 2022-08-30 2022-08-10 2022-09-07 2022-09-23 2022-10-23 2022-11-27 2023-05-26 gistry of Agricultural Produce cation Selection nment rs (RNPA) MOSAP III 097/CS/CADP/20 / Supervisio Infrastructure for Production Quality And Cost- Open - Internationa n for Works PHASE 1 Kwanza COFN / C1580 Post 850,000.00 0.00 Canceled 2022-04-22 2021-09-13 2022-05-07 2022-06-07 2022-07-05 2022-07-26 2022-08-26 2022-09-15 2023-06-12 and Marketing Based Selection l Norte (Lot 2) 054/CS/CADP/18 / Technical Project Management, Monito Quality And Cost- Open - Internationa assistance for the investment COFN / C1580 Post 500,000.00 0.00 Canceled 2021-12-10 2021-12-31 2022-02-13 2022-03-13 2022-04-12 2022-05-17 2022-06-21 2023-06-21 ring and Evaluation Based Selection l committee 096/CS/CADP/20 / Supervisio Infrastructure for Production Quality And Cost- Open - Internationa n for rehabilitation of Irrigatio COFN / C1580 Post 800,000.00 0.00 Canceled 2022-02-20 2022-03-07 2022-04-07 2022-05-05 2022-05-26 2022-06-26 2022-07-16 2023-07-16 and Marketing Based Selection l n infrastructure (Lot 3) 329/CS3/CADP/24 / Provision of services within the framew ork of the Reinforcement of A Promotion and Support for A Quality And Cost- Under Implement COFN / C1580 Post Open - National 430,000.00 0.00 2024-03-15 2024-05-28 2024-04-05 2024-06-03 2024-05-19 2024-06-16 2024-07-16 2024-08-20 2024-09-24 2025-09-24 gricultural Statistics - Agricult gribusiness Development Based Selection ation ural and Forestry Production Surveys, 1st and 2nd Season, in the period 2024-2025. 328A/CS/CADP/24 / Consulti Infrastructure for Production Quality And Cost- Open - Internationa Under Implement ng service for updating PLANI IBRD / 88660 Post 850,000.00 0.00 2024-05-10 2024-05-27 2024-05-31 2024-05-30 2024-07-14 2024-08-11 2024-09-10 2024-10-15 2024-11-19 2025-11-19 and Marketing Based Selection l ation RRIGA and preparing executi ve projects Page 8 328B/CS/CADP/24 / Preparati on of Engineering Projects for the Implementation of Irrigati Infrastructure for Production Quality And Cost- Open - Internationa Under Implement IBRD / 88660 Post 950,000.00 0.00 2024-05-10 2024-06-12 2024-05-31 2024-06-13 2024-07-14 2024-08-11 2024-09-10 2024-10-15 2024-11-19 2025-11-19 on Systems in the Irrigated P and Marketing Based Selection l ation erimeters of Lussol in Waba ( Huíla) and Hortas do Giraúl / Bero (Namibe) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 002/CS/ACDP/16 / Procurem Project Management, Monito Individual Consult IBRD / P4860 Prior Open 130,000.00 817,829.44 Signed 2017-03-06 2017-08-29 2017-04-04 2017-09-08 2017-04-05 2017-09-28 2017-04-20 2017-10-04 2018-04-20 ent specialist ring and Evaluation ant Selection 014/CS/ACDP/16 / Consultan t to undertake analysis of infr Promotion and Support for A astructure current status as IBRD / P4860 Post Direct Selection Direct 100,000.00 299,133.85 Completed 2017-03-13 2017-03-23 2017-05-20 2017-09-25 2017-06-19 2018-05-20 gribusiness Development well as other services for the betterment of the value chai ns 003/CS/ACDP/16 / Agribusin Project Management, Monito Individual Consult IBRD / P4860 Prior Open 150,000.00 278,174.02 Terminated 2017-11-13 2018-05-17 2017-12-16 2017-12-23 2018-10-01 2018-01-13 2018-11-07 2019-01-13 ess and Value Chain Analysis ring and Evaluation ant Selection Specialist 016/CS/ACDP/16 / Consultan Project Management, Monito Individual Consult IBRD / P4860 Post Open 70,000.00 45,200.00 Completed 2017-12-18 2018-04-13 2018-02-05 2018-04-16 2018-02-26 2018-05-02 2018-03-08 2018-05-22 2018-06-06 2019-08-18 t to develop the project's ma ring and Evaluation ant Selection nual 004/CS/ACDP/16 / Finance m Project Management, Monito Individual Consult IBRD / P4860 Prior Open 130,000.00 343,662.13 Signed 2017-10-30 2017-10-04 2017-11-28 2017-12-12 2018-01-31 2018-01-09 2018-02-28 2019-01-09 anagement specialist ring and Evaluation ant Selection 023/CS/ACDP/17 / Contractin Project Management, Monito Individual Consult g of an Environmental Safeg IBRD / P4860 Prior Open 70,000.00 389,271.24 Signed 2018-01-15 2017-11-30 2018-03-05 2018-05-08 2018-03-26 2018-05-08 2018-04-30 2018-07-11 2019-04-30 ring and Evaluation ant Selection uards Specialist 007/CS/ACDP/16 / Project ac Project Management, Monito Individual Consult IBRD / P4860 Post Open 90,000.00 0.00 Canceled 2018-01-15 2017-11-07 2018-03-05 2018-03-19 2018-04-07 2019-04-07 countant ring and Evaluation ant Selection 025/CS/ACDP/18 / Consultan cy services for the elaboratio Promotion and Support for A Individual Consult IBRD / P4860 Post Open 90,000.00 0.00 Canceled 2017-06-25 2017-06-05 2017-07-19 2017-08-28 2017-07-24 2017-08-03 2018-01-30 n of a Diagnosis of Land Uses gribusiness Development ant Selection and Rights in the Project Impl ementation Area 025/CS/CADP/17 / DIAGNOS Promotion and Support for A Individual Consult TIC REVIEW OF LAND RIGHTS IBRD / P4860 Prior Open 90,000.00 80,000.00 Completed 2017-11-20 2017-11-22 2017-12-12 2017-12-04 2017-12-15 2018-01-24 2018-01-10 2018-02-19 2018-07-09 2019-01-06 gribusiness Development ant Selection AND LAND USES IN THE PROJ ECT AREA 005/CS/ACDP/16 / Junior Pro Project Management, Monito Individual Consult IBRD / P4860 Prior Open 70,000.00 243,044.75 Signed 2018-05-07 2018-05-29 2018-06-05 2018-09-10 2018-06-19 2018-09-27 2018-07-10 2018-10-16 2019-07-10 curement Officer 1 ring and Evaluation ant Selection 026/CS/CADP/17 / Consultan Project Management, Monito Individual Consult IBRD / P4860 Post Open 30,000.00 0.00 Canceled 2018-01-29 2018-03-19 2018-04-09 2018-05-14 2018-11-10 cy to prepare the project ma ring and Evaluation ant Selection nuals 034/CS/CADP/18 / Project Ac Project Management, Monito Individual Consult IBRD / P4860 Post Open 70,000.00 165,897.79 Signed 2018-06-04 2018-05-17 2018-07-03 2018-07-12 2018-07-13 2018-07-17 2018-08-12 2018-08-18 2019-02-08 countant ring and Evaluation ant Selection 006/CS/ACDP/16 / Assistant Project Management, Monito Individual Consult IBRD / P4860 Post Open 75,000.00 0.00 Canceled 2017-03-06 2017-04-04 2017-04-18 2017-05-16 2018-05-16 Financial Management ring and Evaluation ant Selection 028/CS/CADP/18 / Matching Project Management, Monito Individual Consult IBRD / 88660 Prior Open 150,000.00 385,664.22 Signed 2019-01-15 2019-01-23 2019-03-05 2019-07-15 2019-03-26 2019-07-25 2019-04-30 2019-08-15 2019-10-27 Grant Manager ring and Evaluation ant Selection 032/CS/CADP/18 / Matching Project Management, Monito Individual Consult IBRD / 88660 Post Open 70,000.00 133,645.35 Signed 2019-01-15 2019-02-11 2019-03-05 2019-11-05 2019-03-26 2019-11-13 2019-04-30 2019-12-01 2019-10-27 Grant Specialist ring and Evaluation ant Selection 033/CS/CADP/18 / Junior Fina Project Management, Monito Individual Consult IBRD / 88660 Post Open 70,000.00 308,671.17 Signed 2019-01-15 2018-12-06 2019-03-05 2019-04-25 2019-03-26 2019-05-07 2019-04-30 2019-05-26 2019-10-27 ncial Management officer ring and Evaluation ant Selection 031/CS/CADP/18 / Matching Project Management, Monito Individual Consult IBRD / 88660 Post Open 70,000.00 230,661.87 Signed 2019-01-18 2018-11-29 2019-03-08 2019-07-15 2019-03-29 2019-07-26 2019-05-03 2019-09-24 2019-10-30 grant accountant ring and Evaluation ant Selection 058/CS/CADP/18 / Monitorin Project Management, Monito Individual Consult IBRD / 88660 Post Open 70,000.00 132,150.00 Signed 2018-12-28 2019-02-11 2019-02-15 2019-10-28 2019-03-08 2019-11-08 2019-04-12 2019-12-03 2019-10-09 g and Evaluation specialist ring and Evaluation ant Selection 057/CS/CADP/18 / Provincial Project Management, Monito Individual Consult IBRD / 88660 Post Open 40,000.00 73,335.82 Signed 2019-01-09 2019-04-22 2019-02-27 2019-12-24 2019-03-20 2020-01-23 2019-04-24 2020-01-25 2019-10-21 Representative 3 ring and Evaluation ant Selection 056/CS/CADP/18 / Provincial Project Management, Monito Individual Consult IBRD / 88660 Post Open 40,000.00 108,321.20 Signed 2019-01-09 2019-04-22 2019-02-27 2019-11-13 2019-03-20 2019-11-15 2019-04-24 2019-11-12 2019-10-21 Representative 2 ring and Evaluation ant Selection 055/CS/CADP/18 / Provincial Project Management, Monito Individual Consult IBRD / 88660 Post Open 40,000.00 73,335.82 Signed 2019-01-09 2019-04-15 2019-02-27 2019-11-13 2019-03-20 2019-11-14 2019-04-24 2019-11-12 2019-10-21 Representative 1 ring and Evaluation ant Selection 043/CS/CADP/18 / Communi Project Management, Monito Individual Consult IBRD / 88660 Prior Open 70,000.00 291,821.33 Signed 2019-01-11 2019-02-26 2019-03-01 2019-04-30 2019-03-22 2019-05-29 2019-04-26 2019-06-17 2019-10-23 cation specialist ring and Evaluation ant Selection 044/CS/CADP/18 / Senior Infr Project Management, Monito Individual Consult IBRD / 88660 Prior Open 150,000.00 309,372.24 Signed 2018-12-28 2019-02-11 2019-02-15 2019-04-22 2019-03-08 2019-06-24 2019-04-12 2019-06-24 2019-10-09 astructure specialist ring and Evaluation ant Selection 045/CS/CADP/18 / Project Co Project Management, Monito Individual Consult IBRD / 88660 Post Open 18,000.00 17,934.06 Signed 2019-01-24 2019-05-16 2019-03-14 2020-01-09 2019-04-04 2020-01-20 2019-05-09 2020-02-05 2019-11-05 ordinator's Assistant ring and Evaluation ant Selection 063/CS/CADP/18 / Expert for Institutional Strengthening a Individual Consult Data collection and analysis t IBRD / 88660 nd Improved Business Enviro Post Open 90,000.00 275,673.48 Signed 2019-01-31 2019-11-08 2019-03-21 2020-02-18 2019-04-11 2020-02-21 2019-05-16 2020-03-12 2019-11-12 ant Selection o support GEPE nment 066/CS/CADP/18 / Administr Project Management, Monito Individual Consult IBRD / 88660 Post Open 30,000.00 101,014.54 Signed 2019-02-08 2019-02-11 2019-03-29 2019-06-18 2019-04-19 2019-06-21 2019-05-24 2019-07-16 2019-11-20 ative/Office Assistant ring and Evaluation ant Selection 062/CS/CADP/18 / Internal A Project Management, Monito Individual Consult IBRD / 88660 Post Open 90,000.00 61,754.00 Signed 2018-12-14 2018-11-29 2019-02-01 2019-04-30 2019-02-22 2019-06-07 2019-03-29 2019-06-27 2019-09-25 udit for PIU ring and Evaluation ant Selection 067/CS/CADP/19 / External A Project Management, Monito IBRD / 88660 Post Direct Selection Direct 40,000.00 30,000.00 Completed 2019-04-30 2019-04-29 2019-05-10 2019-05-08 2019-06-13 2019-05-24 2019-09-11 2019-09-17 udit for PIU (First Year) ring and Evaluation Page 9 068/CS/CADP/19 / Technical Institutional Strengthening a Individual Consult support for agriculture policy IBRD / 88660 nd Improved Business Enviro Post Open 80,000.00 132,780.67 Signed 2019-05-10 2019-05-31 2019-06-28 2020-01-23 2019-07-19 2020-02-19 2019-08-23 2020-08-20 2020-08-17 ant Selection set up and analysis for GEPE/ nment MINAGRIF 082/CS/CADP/19 / Internal A Project Management, Monito Individual Consult COFN / C1580 Post Limited 90,000.00 261,986.86 Signed 2019-12-27 2020-01-09 2020-01-03 2020-01-08 2020-01-24 2020-02-28 2020-02-28 2020-03-18 2020-03-02 udit for PIU ring and Evaluation ant Selection 042/CS/CADP/18 / IT Speciali Project Management, Monito Individual Consult IBRD / 88660 Post Open 70,000.00 0.00 Canceled 2019-07-25 2019-09-12 2019-10-03 2019-11-07 2020-05-05 st ring and Evaluation ant Selection 065/CS/CADP/18 / Expert to Institutional Strengthening a Individual Consult provide TA on commissioning IBRD / 88660 nd Improved Business Enviro Post Open 97,500.00 0.00 Canceled 2019-02-11 2019-04-01 2019-04-22 2019-05-27 2020-05-26 ant Selection studies related to institutiona nment l support 020/CS/ACDP/17 / Contractin Project Management, Monito Individual Consult IBRD / 88660 Post Open 30,000.00 0.00 Canceled 2019-03-27 2019-05-15 2019-06-05 2019-07-10 2020-07-09 g of a Land governance/socia ring and Evaluation ant Selection l Assistant 081/CS/CADP/20 / M&E Spec Project Management, Monito Individual Consult COFN / C1580 Post Limited 90,000.00 102,673.80 Signed 2020-02-17 2020-02-17 2020-02-22 2020-03-03 2020-03-14 2020-07-28 2020-04-18 2020-08-11 2021-04-13 ialist ring and Evaluation ant Selection 030/CS/CADP/18 / Junior Agri Project Management, Monito Individual Consult business and Value Chain An COFN / C1580 Post Open 70,000.00 54,936.90 Signed 2020-04-24 2020-06-22 2020-06-12 2020-10-07 2020-07-03 2020-10-14 2020-08-07 2020-11-20 2021-08-02 ring and Evaluation ant Selection alysis Specialist 048/CS/CADP/18 / Impact ev Project Management, Monito Individual Consult COFN / C1580 Post Open 50,000.00 0.00 Canceled 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 aluation specialist ring and Evaluation ant Selection 021/CS/ACDP/17 / Contractin Project Management, Monito Individual Consult g of a Value chain developm COFN / C1580 Post Open 70,000.00 0.00 Canceled 2020-02-28 2020-04-17 2020-05-08 2020-06-12 2021-06-12 ring and Evaluation ant Selection ent/competitiveness expert 089/CS/CADP/20 / Project Ac Project Management, Monito Individual Consult IBRD / 88660 Post Limited 90,000.00 224,578.41 Signed 2020-04-15 2020-04-09 2020-04-20 2020-05-05 2020-05-11 2020-06-09 2020-06-15 2020-06-29 2021-06-10 countant ring and Evaluation ant Selection 024/CS/ACDP/17 / Contractin Project Management, Monito Individual Consult COFN / C1580 Post Open 70,000.00 115,508.02 Signed 2020-10-08 2020-08-07 2020-11-26 2020-11-09 2020-12-17 2020-11-17 2021-01-21 2020-12-10 2022-01-21 g of a Social Safeguards Spec ring and Evaluation ant Selection ialist 091/CS/CADP/20 / Technical Institutional Strengthening a Service Provider (TSP) Devel COFN / C1580 nd Improved Business Enviro Post Direct Selection Direct 300,000.00 298,962.00 Signed 2020-07-07 2020-06-11 2020-07-17 2020-07-03 2020-09-20 2020-09-26 2021-09-15 oping a risk financing tool for nment agriculture and food security 092/CS/CADP/20 / LEAST-CO ST GEOSPATIAL ELECTRIFICA Infrastructure for Production TION OPTIONS ANALYSIS FOR IBRD / 88660 Post Direct Selection Direct 300,000.00 361,837.00 Signed 2020-07-01 2020-06-15 2020-07-22 2020-06-21 2020-08-15 2020-08-12 2021-02-11 and Marketing LAST-MILE EXTENSION OF GR ID IN THE PROJECT AREA (Par tial Study) 086/CS/CADP/20 / Technical Infrastructure for Production Individual Consult Studies for environmental an COFN / C1580 Post Open 90,000.00 0.00 Canceled 2020-03-23 2020-03-11 2020-05-11 2020-06-01 2020-07-06 2020-11-03 and Marketing ant Selection d social impact assessment f or rural roads 083/CS/CADP/20 / Assistant/J Project Management, Monito Individual Consult COFN / C1580 Post Open 70,000.00 149,719.20 Signed 2020-10-16 2021-03-04 2020-12-04 2021-06-01 2020-12-25 2021-06-03 2021-01-29 2021-07-05 2022-01-24 unior M&E Specialist ring and Evaluation ant Selection 100/CS/CADP/21 / Project Co Project Management, Monito COFN / C1580 Prior Direct Selection Direct 191,700.00 385,026.74 Signed 2021-02-26 2021-02-26 2021-03-13 2021-03-04 2021-04-01 2021-02-20 2022-03-27 ordinator ring and Evaluation 106/CS/CADP/21 / Assistant f Project Management, Monito Individual Consult COFN / C1580 Post Limited 32,117.00 62,085.56 Signed 2021-04-09 2021-04-14 2021-04-19 2021-05-06 2021-05-04 2021-08-02 2021-05-24 2021-08-31 2022-05-24 or the Project Coordinator ring and Evaluation ant Selection 107/CS/CADP/21 / Matching Project Management, Monito Individual Consult COFN / C1580 Post Limited 90,000.00 180,000.00 Signed 2021-04-16 2021-04-30 2021-04-26 2021-05-06 2021-05-11 2021-06-21 2021-05-31 2021-07-20 2022-05-31 Grant Manager ring and Evaluation ant Selection 108/CS/CADP/21 / Monitorin Project Management, Monito Individual Consult g and Evaluation Specialist fo COFN / C1580 Post Limited 77,000.00 77,005.31 Signed 2021-04-13 2021-04-19 2021-04-23 2021-04-28 2021-05-08 2021-06-11 2021-05-28 2021-07-13 2022-05-28 ring and Evaluation ant Selection r the Project and is closing. 109/CS/CADP/21 / IT Speciali Project Management, Monito Individual Consult COFN / C1580 Post Open 64,500.00 129,000.06 Signed 2021-04-18 2021-08-10 2021-06-02 2021-10-07 2021-06-17 2021-10-20 2021-07-07 2021-11-03 2022-07-07 st for the project ring and Evaluation ant Selection 022/CS/ACDP/17 / Contractin Project Management, Monito Individual Consult COFN / C1580 Post Open 50,000.00 0.00 Canceled 2022-04-22 2022-06-10 2022-07-01 2022-08-05 2023-08-05 g of a Junior Agribusiness Ex ring and Evaluation ant Selection pert 112/CS/CADP/21 / Junior Agri Project Management, Monito Individual Consult business and Value Chain An COFN / C1580 Post Limited 38,500.00 38,503.20 Signed 2021-04-13 2021-05-05 2021-04-18 2021-05-31 2021-05-09 2021-07-20 2021-06-13 2021-08-27 2022-06-13 ring and Evaluation ant Selection alysis Specialist (new strateg y) 111/CS/CADP/21 / Agronomi Institutional Strengthening a Individual Consult st Researcher (Specialist in a COFN / C1580 nd Improved Business Enviro Post Limited 40,000.00 40,000.00 Signed 2021-04-21 2021-04-27 2021-04-26 2021-07-14 2021-05-17 2021-08-18 2021-06-21 2021-08-22 2021-09-19 ant Selection gricultural research) nment 102/CS/CADP/21 / Agribusin Project Management, Monito Individual Consult IBRD / 88660 Post Direct 16,000.00 0.00 Canceled 2021-04-23 2021-04-21 2021-05-10 2021-05-17 2021-05-31 2022-05-31 ess and Value Chain Analysis ring and Evaluation ant Selection Specialist 113/CS/CADP/21 / Environm Project Management, Monito Individual Consult COFN / C1580 Post Open 70,000.00 0.00 Canceled 2021-07-21 2021-07-23 2021-08-25 2021-09-21 2021-09-09 2021-09-29 2022-09-29 ental Safeguards Specialist ring and Evaluation ant Selection 114/CS/CADP/21 / Agribusin Project Management, Monito Individual Consult COFN / C1580 Post Direct 64,000.00 128,000.04 Signed 2021-07-13 2021-07-23 2021-07-30 2021-07-28 2021-08-02 2021-07-28 2021-08-15 2021-08-10 2022-08-15 ess and Value Chain Analysis ring and Evaluation ant Selection Specialist 047/CS/CADP/18 / Junior Pro Project Management, Monito Individual Consult COFN / C1580 Prior Open 70,000.00 70,000.08 Signed 2021-07-18 2021-08-05 2021-08-26 2021-10-26 2021-09-05 2021-10-29 2021-09-25 2021-11-23 2022-09-25 curement Officer 2 ring and Evaluation ant Selection 115/CS/CADP/21 / Junior Pro Project Management, Monito Individual Consult COFN / C1580 Prior Open 70,000.00 0.00 Canceled 2021-09-07 2021-09-13 2021-10-16 2021-12-06 2021-10-26 2021-11-19 2022-11-14 curement Officer ring and Evaluation ant Selection 019/CS/ACDP/17 / Contractin Project Management, Monito Individual Consult COFN / C1580 Post Open 50,000.00 0.00 Canceled 2021-09-13 2021-10-12 2021-10-22 2021-12-06 2021-10-27 2021-11-13 2022-11-13 g of a Land Administration sp ring and Evaluation ant Selection ecialist 104/CS/CADP/21 / Consultan Institutional Strengthening a cy to support the registration Individual Consult COFN / C1580 nd Improved Business Enviro Post Open 150,000.00 0.00 Canceled 2021-07-30 2021-09-07 2021-09-17 2021-10-07 2022-04-05 and legalization of land of po ant Selection nment tential beneficiaries Page 10 118/CS/CADP/21 / Contractin Project Management, Monito Individual Consult g of new Environmental Safe COFN / C1580 Post Direct 70,000.00 70,000.00 Signed 2021-10-25 2021-10-26 2021-11-06 2021-10-28 2021-11-16 2021-11-08 2021-12-06 2021-12-04 2022-12-01 ring and Evaluation ant Selection guards Specialist 119/CS/CADP/21 / Junior Con Project Management, Monito Individual Consult sultant to support the Provin COFN / C1580 Post Open 18,000.00 18,000.00 Terminated 2021-11-03 2021-11-18 2021-12-13 2022-01-21 2021-12-27 2022-01-26 2022-01-20 2022-02-13 2023-01-15 ring and Evaluation ant Selection cial Representative of Cuanz a Norte 120/CS/CADP/21 / Junior Con Project Management, Monito Individual Consult sultant to support the Provin COFN / C1580 Post Open 18,000.00 18,000.00 Signed 2021-11-03 2021-11-18 2021-12-13 2022-01-20 2021-12-27 2022-01-24 2022-01-20 2022-02-11 2023-01-15 ring and Evaluation ant Selection cial Representative of Cuanz a Sul 121/CS/CADP/21 / Junior Con Project Management, Monito Individual Consult sultant to support the Provin COFN / C1580 Post Open 18,000.00 18,000.00 Signed 2021-11-03 2021-11-18 2021-12-13 2022-01-25 2021-12-27 2022-01-31 2022-01-20 2022-02-16 2023-01-15 ring and Evaluation ant Selection cial Representative of Malan ge 122/CS/CADP/21 / Individual Project Management, Monito Individual Consult Consultant to conduct the Mi COFN / C1580 Post Direct 75,000.00 48,851.00 Signed 2021-10-25 2021-11-10 2021-11-04 2021-11-16 2021-11-09 2021-11-18 2021-11-19 2021-11-23 2022-02-17 ring and Evaluation ant Selection d-Term Evaluation of the Proj ect CADP 123/CS/CADP/21 / Agronomi st Researcher to support the Institutional Strengthening a Individual Consult PIU to monitor the implement COFN / C1580 nd Improved Business Enviro Post Direct 90,000.00 90,000.00 Signed 2021-10-26 2021-11-10 2021-11-05 2021-11-15 2021-11-15 2021-11-25 2021-11-27 2021-12-11 2022-11-22 ant Selection ation of the Harmonized Stra nment tegy under SubComponent 3. 2 C 132/CS/CADP/21 / Procure Institutional Strengthening a Individual Consult IBRD / 88660 Prior Open 166,836.00 0.00 Canceled 2021-12-09 2022-01-27 2022-02-17 2022-03-24 2022-09-20 ment Specialist nd Improved Business Enviro ant Selection nment C 130/CS/CADP/21 / Project Institutional Strengthening a Individual Consult IBRD / 88660 Post Limited 192,513.36 0.00 Canceled 2021-12-09 2021-12-31 2021-12-14 2022-01-04 2022-02-08 2022-08-07 Coordinator nd Improved Business Enviro ant Selection nment C 131/CS/CADP/21 / Financia Institutional Strengthening a Individual Consult IBRD / 88660 Post Limited 107,009.55 102,673.80 Signed 2021-12-09 2021-12-13 2021-12-14 2021-12-29 2022-01-04 2022-02-24 2022-02-08 2022-03-12 2022-08-07 l Management Specialist nd Improved Business Enviro ant Selection nment C 133/CS/CADP/21 / Senior S Institutional Strengthening a Individual Consult IBRD / 88660 Post Limited 48,000.06 102,673.80 Signed 2021-12-09 2021-12-10 2021-12-14 2021-12-29 2022-01-04 2022-01-06 2022-02-08 2022-01-11 2022-08-07 pecialist for Agriculture/agrib nd Improved Business Enviro ant Selection usiness nment C136/CS/CADP/21 / Senior E Institutional Strengthening a Individual Consult IBRD / 88660 Post Limited 105,882.21 102,673.80 Signed 2021-12-09 2021-12-10 2021-12-14 2021-12-24 2022-01-04 2021-12-29 2022-02-08 2022-01-03 2022-08-07 ngineer Specialized in Irrigati nd Improved Business Enviro ant Selection on nment C 135/CS/CADP/21 / Senior L Institutional Strengthening a Individual Consult IBRD / 88660 Post Limited 52,500.15 102,673.80 Signed 2021-12-09 2021-12-10 2021-12-14 2021-12-21 2022-01-04 2021-12-24 2022-02-08 2021-12-29 2022-08-07 ivestock Specialist nd Improved Business Enviro ant Selection nment C 137/CS/CADP/21 / Monitori Institutional Strengthening a Individual Consult IBRD / 88660 Post Limited 57,753.99 102,673.80 Signed 2021-12-09 2021-12-13 2021-12-14 2022-04-01 2022-01-04 2022-04-08 2022-02-08 2022-04-12 2022-08-07 ng and Evaluation Specialist nd Improved Business Enviro ant Selection nment C 138/CS/CADP/21-129 / Soc Institutional Strengthening a Individual Consult IBRD / 88660 Post Limited 70,000.00 102,673.80 Signed 2021-12-13 2021-12-14 2021-12-18 2021-12-24 2022-01-08 2022-01-03 2022-02-12 2022-01-08 2022-08-11 ial and Gender Safeguards S nd Improved Business Enviro ant Selection pecialist nment C 139/CS/CADP/21 / Senior P Institutional Strengthening a Individual Consult IBRD / 88660 Prior Open 166,836.00 128,342.25 Signed 2021-12-13 2021-12-15 2022-01-31 2022-04-11 2022-02-21 2022-09-01 2022-03-28 2022-09-23 2022-09-24 rocurement Specialist nd Improved Business Enviro ant Selection nment C 140/CS/CADP/21 / ENVIRO Institutional Strengthening a Individual Consult IBRD / 88660 Post Limited 70,000.00 102,673.80 Signed 2021-12-15 2021-12-29 2021-12-20 2022-01-14 2022-01-10 2022-01-14 2022-02-14 2022-01-19 2022-08-13 NMENTAL SAFEGUARDS SPEC nd Improved Business Enviro ant Selection IALIST nment C 141/CS/CADP/21-132 / Juni Project Management, Monito Individual Consult COFN / C1580 Post Open 70,000.17 83,422.46 Signed 2022-01-04 2022-01-05 2022-02-22 2022-02-22 2022-03-15 2022-02-24 2022-04-19 2022-03-12 2022-10-16 or Procurement Officer 3 ring and Evaluation ant Selection C 142/CS/CADP/21-132 / Lan Project Management, Monito Individual Consult COFN / C1580 Post Open 70,000.00 77,005.35 Signed 2022-01-05 2022-01-05 2022-02-23 2022-02-23 2022-03-16 2022-02-24 2022-04-20 2022-03-01 2022-10-17 d Administration Specialist ring and Evaluation ant Selection C 128/CS/CADP/21 / PREPAR ATION OF THE MANAGEMENT Institutional Strengthening a FRAMEWORK OF INDIGENOU Individual Consult IBRD / 88660 nd Improved Business Enviro Post Limited 60,000.00 0.00 Canceled 2021-12-09 2021-12-10 2021-12-14 2022-01-04 2022-02-08 2022-08-07 S PEOPLES/LOCAL COMMUNI ant Selection nment TIES HISTORICALLY DISADVA NTAGED TRADITIONALS OF S UB-SAHARAN AFRICA C 129/CS/CADP/21 / ENVIRO Institutional Strengthening a Individual Consult IBRD / 88660 Post Limited 70,000.00 0.00 Canceled 2021-12-09 2021-12-10 2021-12-14 2022-01-04 2022-02-08 2022-08-07 NMENTAL SAFEGUARDS SPEC nd Improved Business Enviro ant Selection IALIST nment C 143/CS/CADP/21-133 / EN Institutional Strengthening a COFN / C1580 Post Direct Selection Direct 60,000.00 71,310.53 Signed 2022-01-20 2022-01-28 2022-01-30 2021-12-01 2022-04-05 2022-02-17 2022-10-02 VIRONMENTAL SAFEGUARDS nd Improved Business Enviro SPECIALIST nment C 147/CS/CADP/22 / Speciali Institutional Strengthening a Individual Consult COFN / C1580 Post Limited 75,000.00 0.00 Canceled 2022-01-28 2022-01-28 2022-02-02 2022-02-23 2022-03-30 2022-09-26 st in Agriculture Policy nd Improved Business Enviro ant Selection nment C 181/CS/CADP-22 / Environ Project Management, Monito Individual Consult COFN / C1580 Post Limited 38,502.67 38,502.67 Signed 2022-02-15 2022-03-17 2022-02-20 2022-04-14 2022-03-13 2022-04-21 2022-04-17 2022-04-30 2022-10-14 mental Safeguards Assistant ring and Evaluation ant Selection C 187/CS/CADP-22 / PROJEC Project Management, Monito Individual Consult COFN / C1580 Post Limited 70,000.00 77,005.35 Signed 2022-02-22 2022-02-23 2022-02-27 2022-03-31 2022-03-20 2022-04-07 2022-04-24 2022-04-25 2022-10-21 T DIRECTOR'S ASSISTANT ring and Evaluation ant Selection C 198/CS/CADP-22 / Account Project Management, Monito Individual Consult COFN / C1580 Post Open 55,000.00 44,919.79 Signed 2022-03-03 2022-03-17 2022-04-21 2022-04-29 2022-05-12 2022-05-04 2022-06-16 2022-05-11 2022-12-13 ing Assistant ring and Evaluation ant Selection C 199/CS/CADP-22 / Matchin Promotion and Support for A Individual Consult COFN / C1580 Post Open 74,000.00 57,754.01 Signed 2022-03-03 2022-03-15 2022-04-21 2022-04-25 2022-05-12 2022-04-27 2022-06-16 2022-05-04 2022-12-13 g-Grants Accountant gribusiness Development ant Selection C 200/CS/CADP-22 / Matchin Promotion and Support for A Individual Consult COFN / C1580 Post Open 129,000.00 83,422.46 Signed 2022-03-03 2022-03-18 2022-04-21 2022-05-05 2022-05-12 2022-05-10 2022-06-16 2022-05-18 2022-12-13 g-Grants Specialist gribusiness Development ant Selection C 206/CS/CADP-22 / Social S Project Management, Monito Individual Consult COFN / C1580 Post Limited 39,000.00 38,502.67 Signed 2022-03-03 2022-03-25 2022-03-08 2022-04-14 2022-03-29 2022-05-19 2022-05-03 2022-05-27 2022-10-30 afeguards Assistant ring and Evaluation ant Selection C 211/CS/CADP-22 / Provinci Project Management, Monito Individual Consult COFN / C1580 Post Open 44,000.00 0.00 Canceled 2022-03-03 2022-03-15 2022-04-21 2022-04-29 2022-05-12 2022-06-16 2022-12-13 al Representative - Huila ring and Evaluation ant Selection C 212/CS/CADP-22 / Provinci Project Management, Monito Individual Consult COFN / C1580 Post Open 44,000.00 34,986.10 Signed 2022-03-03 2022-03-15 2022-04-21 2022-04-29 2022-05-12 2022-05-04 2022-06-16 2022-05-16 2022-12-13 al Representative - Huambo ring and Evaluation ant Selection C 213/CS/CADP-22 / Provinci Project Management, Monito Individual Consult COFN / C1580 Post Open 44,000.00 34,986.10 Signed 2022-03-03 2022-03-15 2022-04-21 2022-04-29 2022-05-12 2022-05-04 2022-06-16 2022-05-17 2022-12-13 al Representative - BIÉ ring and Evaluation ant Selection Page 11 C 202/CS/CADP-22 / Part-tim Institutional Strengthening a Individual Consult COFN / C1580 Prior Direct 50,000.00 33,009.63 Signed 2022-03-03 2022-03-15 2022-03-13 2022-03-29 2022-04-03 2022-04-10 2022-05-08 2022-04-15 2022-11-04 e Procurement Specialist nd Improved Business Enviro ant Selection nment C 203/CS/CADP-22 / Procure Project Management, Monito Individual Consult COFN / C1580 Prior Open 36,000.00 38,502.67 Signed 2022-03-03 2022-03-28 2022-04-21 2022-05-18 2022-05-12 2022-05-24 2022-06-16 2022-06-11 2022-12-13 ment Assistant ring and Evaluation ant Selection C 208/CS/CADP-22 / Junior Pr Project Management, Monito Individual Consult ocurement Officer to Support COFN / C1580 Prior Open 74,000.00 38,502.67 Signed 2022-03-04 2022-04-19 2022-04-22 2022-07-07 2022-05-13 2022-07-20 2022-06-17 2022-08-08 2022-12-14 ring and Evaluation ant Selection the component 3.2 harmoniz ed strategy C 209/CS/CADP-22 / Account Project Management, Monito Individual Consult ant to support the Harmonize COFN / C1580 Post Open 70,000.00 57,754.01 Signed 2022-03-04 2022-04-12 2022-04-22 2022-05-19 2022-05-13 2022-05-23 2022-06-17 2022-05-31 2022-12-14 ring and Evaluation ant Selection d Strategy - sub-component 3.2 C 218/CS/CADP-22 / Procure Project Management, Monito Individual Consult COFN / C1580 Prior Open 166,863.00 128,342.25 Signed 2022-03-04 2022-03-28 2022-04-22 2022-06-24 2022-05-13 2022-07-10 2022-06-17 2022-08-06 2022-12-14 ment Specialist for PDAC ring and Evaluation ant Selection C 214/CS/CADP-22 / Junior C Project Management, Monito Individual Consult onsultant to support the Prov COFN / C1580 Post Open 30,000.00 18,000.00 Signed 2022-03-07 2022-04-08 2022-04-25 2022-05-19 2022-05-16 2022-05-20 2022-06-20 2022-05-27 2022-12-17 ring and Evaluation ant Selection incial Representative of Huila C 215/CS/CADP-22 / Junior C Project Management, Monito Individual Consult onsultant to support the Prov COFN / C1580 Post Open 30,000.00 18,000.00 Signed 2022-03-07 2022-04-08 2022-04-25 2022-04-17 2022-05-16 2022-05-19 2022-06-20 2022-05-23 2022-12-17 ring and Evaluation ant Selection incial Representative of Hua mbo C 216/CS/CADP-22 / Junior C Project Management, Monito Individual Consult onsultant to support the Prov COFN / C1580 Post Open 30,000.00 18,000.00 Terminated 2022-03-07 2022-04-08 2022-04-25 2022-05-19 2022-05-16 2022-05-24 2022-06-20 2022-05-31 2022-12-17 ring and Evaluation ant Selection incial Representative of Bié C 207/CS/CADP/21 / Project Institutional Strengthening a Individual Consult COFN / C1580 Post Direct 192,513.36 192,513.37 Signed 2022-03-15 2022-03-17 2022-03-25 2022-03-22 2022-04-15 2022-03-22 2022-05-20 2022-03-26 2022-11-16 Coordinator (Mosap3) nd Improved Business Enviro ant Selection nment C 222/CS/CADP-22 / Consult Institutional Strengthening a Individual Consult ant for the Preparation of the COFN / C1580 nd Improved Business Enviro Post Direct 50,000.00 70,659.09 Signed 2022-03-17 2022-04-01 2022-03-27 2022-04-08 2022-04-17 2022-04-07 2022-05-22 2022-04-15 2022-11-18 ant Selection Mosap3 Operations Manual ( nment MOP) C 223/CS/CADP/22 / Consult Project Management, Monito Individual Consult ancy for the Development of COFN / C1580 Post Limited 70,000.00 0.00 Signed 2022-03-24 2022-05-13 2022-03-29 2022-11-06 2022-04-19 2022-05-30 2022-05-24 2022-06-16 2022-11-20 ring and Evaluation ant Selection a Gender Strategy C 253/CS/CADP-22 / IT Tech Institutional Strengthening a Individual Consult COFN / C1580 Post Open 65,000.00 51,336.90 Signed 2022-05-22 2022-06-08 2022-07-10 2022-08-23 2022-07-31 2022-08-29 2022-09-04 2022-09-23 2023-03-03 nician to Support MOSAP III P nd Improved Business Enviro ant Selection IU nment C 250/CS/CADP-22 / Technic Promotion and Support for A al Assistance for the study on COFN / C1580 Prior Direct Selection Direct 1,230,000.00 0.00 Canceled 2022-06-15 2022-09-20 2022-06-25 2022-10-04 2022-08-29 2023-02-25 gribusiness Development food safety (FAO) C 257/CS/CADP-22 / Consult Project Management, Monito Individual Consult ancy for the preparation of st COFN / C1580 Prior Open 300,000.00 0.00 Signed 2022-06-03 2022-06-02 2022-07-22 2022-09-21 2022-08-12 2022-10-26 2022-09-16 2022-12-06 2023-03-15 ring and Evaluation ant Selection udies on competitiveness an d productivity C 258/CS/CADP-22 / Consult ancy to support the creation Institutional Strengthening a Individual Consult of a quality policy and a legis COFN / C1580 nd Improved Business Enviro Post Open 150,000.00 0.00 Signed 2022-06-03 2022-06-01 2022-07-22 2022-08-09 2022-08-12 2022-09-09 2022-09-16 2022-10-10 2023-03-15 ant Selection lative package for the reform nment ulation of the National Qualit y System (SNQ) C 259/CS/CADP-22 / Provinci Project Management, Monito Individual Consult COFN / C1580 Post Open 44,000.00 44,000.00 Signed 2022-06-20 2022-06-22 2022-08-08 2022-08-09 2022-08-29 2022-08-12 2022-10-03 2022-08-19 2023-04-01 al Representative - Huila ring and Evaluation ant Selection C 263/CS/CADP-22 / Junior Pr Institutional Strengthening a Individual Consult COFN / C1580 Prior Open 90,000.00 0.00 Canceled 2022-07-20 2022-10-26 2022-09-07 2022-09-28 2022-11-02 2023-05-01 ocurement Officer For MOSA nd Improved Business Enviro ant Selection P III Project nment C 264/CS/CADP/22 / Junior C Project Management, Monito Individual Consult onsultant to support the Prov COFN / C1580 Post Open 30,000.00 0.00 Signed 2022-07-05 2022-06-30 2022-08-23 2022-09-05 2022-09-13 2022-09-14 2022-10-18 2022-10-08 2023-04-16 ring and Evaluation ant Selection incial Representative of Huila C 274/CS/CADP-22 / Consult Institutional Strengthening a Direct - Internation ante for elaboration of the M COFN / C1580 nd Improved Business Enviro Post Direct Selection 80,000.00 0.00 Signed 2022-07-27 2022-07-27 2022-08-06 2022-07-29 2022-10-10 2022-08-25 2023-04-08 al OP and others ManualS for M nment OSAP III 303/CS/CADP/22 / Monitorin Institutional Strengthening a Individual Consult g and Evaluation Specialist fo COFN / C1580 nd Improved Business Enviro Post Open - National 103,000.00 0.00 Signed 2022-08-25 2022-09-05 2022-10-13 2022-12-08 2022-11-03 2022-12-07 2022-12-08 2022-12-31 2023-06-06 ant Selection r the Project and is closing. nment 304/CS/CADP/22 / Matching Institutional Strengthening a Individual Consult COFN / C1580 Post Open - National 85,000.00 0.00 Signed 2022-08-25 2022-09-05 2022-10-13 2023-01-06 2022-11-03 2023-01-10 2022-12-08 2023-02-10 2023-06-06 grant accountant nd Improved Business Enviro ant Selection nment 302/CS/CADP/22 / Senior Agr Project Management, Monito COFN / C1580 Post Direct Selection Direct - National 104,000.00 0.00 Signed 2022-09-12 2022-09-12 2022-09-22 2022-09-19 2022-11-26 2022-06-17 2023-05-25 ibusiness Specialist ring and Evaluation 001/CS/3/MOSAP3-22 / Speci Institutional Strengthening a alist in Field School and Rural Individual Consult IBRD / 88660 nd Improved Business Enviro Post Limited 102,674.00 0.00 Canceled 2022-11-30 2022-10-26 2022-12-05 2022-12-26 2023-01-19 2024-01-19 Extension for the Family Far ant Selection nment ming Transformation Project (MOSAP3) 005/CS/3/MOSAP3-22 / Junio Institutional Strengthening a Individual Consult r Specialist in Gender Based COFN / C1580 nd Improved Business Enviro Post Open - National 64,200.00 0.00 Canceled 2022-11-30 2022-10-26 2023-01-18 2023-02-08 2023-03-15 2024-03-14 ant Selection Violence (VBG) nment 215A/CS/4/CADP-22 / Junior Project Management, Monito Individual Consult Consultant to support the Pro COFN / C1580 Post Open - National 30,000.00 0.00 Signed 2022-12-19 2022-11-17 2023-02-06 2023-02-01 2023-02-27 2023-02-06 2023-04-03 2023-03-05 2024-04-02 ring and Evaluation ant Selection vincial Representative of Hua mbo 032A/CS4/CADP/22 / Matchin Project Management, Monito Individual Consult IBRD / 88660 Post Open - National 70,000.00 0.00 Signed 2023-02-28 2022-12-30 2023-04-18 2023-03-20 2023-05-09 2023-03-24 2023-06-13 2023-04-18 2024-06-12 g Grant Specialist ring and Evaluation ant Selection 044A/CS4/CADP/22 / Senior I Project Management, Monito Individual Consult Open - Internationa IBRD / 88660 Post 128,345.00 0.00 Canceled 2023-02-28 2023-04-18 2023-05-09 2023-06-13 2024-06-12 nfrastructure specialist ring and Evaluation ant Selection l 317/CS4/CADP-23 / Senior In Project Management, Monito Individual Consult IBRD / 88660 Post Direct - National 102,673.80 0.00 Signed 2023-03-31 2023-01-16 2023-04-10 2023-01-24 2023-05-01 2023-01-27 2023-06-05 2023-02-09 2024-06-04 frastructure specialist ring and Evaluation ant Selection 318/CS4/CADP-23 / Junior Inf Project Management, Monito Individual Consult IBRD / 88660 Post Direct - National 38,502.65 0.00 Signed 2023-03-31 2023-01-16 2023-04-10 2023-01-24 2023-05-01 2023-01-27 2023-06-05 2023-02-09 2024-06-04 rastructure specialist ring and Evaluation ant Selection Page 12 319/CS4/CADP-23 / Senior Irr Project Management, Monito Individual Consult IBRD / 88660 Post Direct - National 102,673.80 0.00 Signed 2023-03-31 2023-01-16 2023-04-10 2023-01-24 2023-05-01 2023-01-27 2023-06-05 2023-02-09 2024-06-04 igation Specialist ring and Evaluation ant Selection 320/CS4/CADP-23 / Junior Irri Project Management, Monito Individual Consult IBRD / 88660 Post Direct - National 38,502.65 0.00 Signed 2023-03-31 2023-01-16 2023-04-10 2023-01-24 2023-05-01 2023-01-27 2023-06-05 2023-02-09 2024-06-04 gation Specialist ring and Evaluation ant Selection 043A/CS4/CADP-23 / Commu Project Management, Monito Individual Consult Open - Internationa IBRD / 88660 Post 89,839.57 0.00 Signed 2023-04-23 2023-04-17 2023-06-11 2023-05-26 2023-07-02 2023-05-29 2023-08-06 2023-06-22 2024-08-05 nication Specialist ring and Evaluation ant Selection l 326/CS4/CADP/23 / Finance Project Management, Monito Individual Consult IBRD / 88660 Post Open - National 137,062.25 0.00 Signed 2024-02-29 2023-12-21 2024-04-18 2024-05-09 2024-05-09 2024-05-09 2024-06-13 2024-05-23 2025-06-13 Management Specialist ring and Evaluation ant Selection C 144/CS/CADP/21-134 / PRE PARATION OF THE MANAGEM Institutional Strengthening a ENT FRAMEWORK OF INDIGE COFN / C1580 nd Improved Business Enviro Post Direct Selection Direct 70,000.00 0.00 Canceled 2022-01-20 2022-01-28 2022-01-30 2022-04-05 2022-10-02 NOUS PEOPLES/LOCAL COMM nment UNITIES HISTORICALLY DISA DVANTAGED TRADITIONALS OF SUB-SAHARAN AFRICA C 134/CS/CADP/21 / Junior S Institutional Strengthening a Individual Consult IBRD / 88660 Post Limited 56,144.61 0.00 Canceled 2021-12-09 2021-12-14 2022-01-04 2022-02-08 2022-08-07 pecialist from Field Schools nd Improved Business Enviro ant Selection nment 340/CS4/CADP-24 / Environ Institutional Strengthening a Individual Consult Under Implement COFN / C1580 Post Open - National 80,000.00 0.00 2024-03-22 2024-06-11 2024-05-10 2024-05-31 2024-07-05 2025-01-01 mental Safeguards Specialist nd Improved Business Enviro ant Selection ation nment 341/CS4/CADP-24 / Specialis Institutional Strengthening a Individual Consult Under Implement COFN / C1580 Post Open - National 80,000.00 0.00 2024-03-22 2024-06-11 2024-05-10 2024-05-31 2024-07-05 2025-01-01 t in Social Safeguards nd Improved Business Enviro ant Selection ation nment 033A/CS/CADP/24 / Junior Fi Project Management, Monito Individual Consult Under Implement IBRD / 88660 Post Open - National 70,000.00 0.00 2024-05-06 2024-05-24 2024-06-24 2024-07-19 2024-07-15 2024-07-22 2024-08-19 2025-02-15 nancial Management Officer ring and Evaluation ant Selection ation 2 216A/CS/CADP/24 / Junior Co Project Management, Monito Individual Consult Under Implement nsultant to support the Provi COFN / C1580 Post Open - National 18,000.00 0.00 2024-05-06 2024-05-28 2024-06-24 2024-07-08 2024-07-15 2024-07-09 2024-08-19 2025-02-15 ring and Evaluation ant Selection ation ncial Representative of Bié 119A/CS/CADP/24 / Junior Co Project Management, Monito Individual Consult Under Implement nsultant to support the Provi COFN / C1580 Post Open - National 18,000.00 0.00 2024-05-06 2024-05-28 2024-06-24 2024-06-26 2024-07-15 2024-07-01 2024-08-19 2025-02-15 ring and Evaluation ant Selection ation ncial Representative of Cuan za Norte 218A/CS/CADP/24 / Procure Project Management, Monito Individual Consult Under Implement COFN / C1580 Prior Direct - National 140,000.00 0.00 2024-06-28 2024-06-29 2024-07-08 2024-07-15 2024-07-29 2024-07-29 2024-09-02 2025-03-01 ment Specialist for PDAC ring and Evaluation ant Selection ation 141A/CS/CADP/24 / Junior Pr Project Management, Monito Individual Consult COFN / C1580 Prior Limited - National 90,000.00 0.00 Under Review 2024-06-28 2024-06-29 2024-07-03 2024-07-01 2024-07-24 2024-08-28 2025-02-24 ocurement Officer ring and Evaluation ant Selection 141B/CS/CADP/24 / Junior Pr Project Management, Monito Individual Consult COFN / C1580 Prior Limited - National 90,000.00 0.00 Under Review 2024-06-28 2024-06-29 2024-07-03 2024-07-01 2024-07-24 2024-08-28 2025-02-24 ocurement Officer ring and Evaluation ant Selection C 181A/CS/CADP-24 / Enviro Project Management, Monito Individual Consult Pending Impleme COFN / C1580 Post Open - National 40,000.00 0.00 2024-07-26 2024-09-13 2024-10-04 2024-11-08 2025-05-07 nmental Safeguards Assistan ring and Evaluation ant Selection ntation t 083A/CS/CADP/24 / Monitori Project Management, Monito Individual Consult Pending Impleme COFN / C1580 Post Open - National 70,000.00 0.00 2024-07-26 2024-09-13 2024-10-04 2024-11-08 2025-05-07 ng and Evaluation Assistant ring and Evaluation ant Selection ntation Page 13