PROCUREMENT PLAN Project information: Republic of Uzbekistan Ferghana Valley Enterprise Development Project Project Implementation agency: Agency for Implementation of Projects in the Field of Agroindustry and Food Security (Agroindustry and Food Security Agency - UZAIFSA) Date of the Procurement Plan: February 13, 2019 Period covered by this Procurement Plan: First two years of project implementation (April 2019 – April 2021) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Provisions of PD No.3857 being in line with Public Procurement Law No. 472 dated April 9, 2018 such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Uzbekistan : Ferghana Valley Rural Enterprise Development Project PLAN General Information Country: Uzbekistan Bank’s Approval Date of the Original Procurement Plan: 2022-10-12 Revised Plan Date(s): (comma delineated, leave blank if 2023-07-28 none) Project ID: P166305 GPN Date: Project Name: Ferghana Valley Rural Enterprise Development Project Loan / Credit No: IBRD / 89380 International Center for Agri-Food Development under the Ministry of Agriculture of Uzbekistan Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FVRED/RFQ/14 / Supply of co mputer equipment for State Component 2: Access to Fin Request for Quota Single Stage - One E IBRD / 89380 Post Open - National 180,000.00 0.00 Canceled 2022-11-04 2022-11-14 2022-12-30 2023-06-28 Fund for Support of Entrepre ance tions nvelope neurship Activities FVRED/RFQ/14-RB / Supply o f computer equipment for Sta Component 2: Access to Fin Request for Quota Single Stage - One E IBRD / 89380 Post Open - National 180,000.00 0.00 Canceled 2023-02-05 2023-04-02 2023-09-29 te Fund for Support of Entrep ance tions nvelope reneurship Activities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FVRED/RFQ/15 / Organizatio n of foreign internships for e mployees of the Ministry of I Component 1: Enterprise De Request for Quota Single Stage - One E Under Imple IBRD / 89380 Post Open - National 100,000.00 0.00 2023-03-05 2023-04-30 2023-10-27 nnovative Development invol velopment tions nvelope mentation ved in coordinating the imple mentation of start-up project s FVRED/RFQ/16 / Organizatio n International study tour for Component 2: Access to Fin Request for Quota Single Stage - One E IBRD / 89380 Post Open - National 100,000.00 0.00 Canceled 2023-02-17 2023-04-14 2023-10-11 State Fund for Support of Ent ance tions nvelope repreneurship Activities CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FVED/CQS/05 / Baseline surv Component 3: Project Manag Consultant Qualifi IBRD / 89380 Post Open - National 30,000.00 0.00 Canceled 2021-07-14 2021-08-04 2021-09-17 2021-10-17 2021-11-21 2022-05-20 ey under FVREDP ement and Coordination cation Selection FVREDP/CQS/07 / Moderniza tion of "Tadbirkor" software f Component 2: Access to Fin Consultant Qualifi Under Implement IBRD / 89380 Post Open - National 80,000.00 0.00 2022-09-10 2022-08-25 2022-10-01 2022-11-14 2022-12-14 2023-01-18 2023-07-17 or State fund for support of e ance cation Selection ation ntrepreneurship activities FVED/LCS/02 / Project audit f Component 3: Project Manag Least Cost Selecti Under Implement IBRD / 89380 Post Open - National 45,000.00 0.00 2022-11-18 2022-12-22 2022-12-09 2023-01-22 2023-01-17 2023-02-19 2023-01-09 2023-03-21 2023-01-12 2023-04-25 2023-01-25 2023-05-30 2023-11-26 or 3 financial years ement and Coordination on ation FVRED/CQS/08 / Developme nt of an information system f Component 1: Enterprise De Consultant Qualifi Under Implement IBRD / 89380 Post Open - National 110,000.00 0.00 2023-02-15 2023-02-02 2023-03-08 2023-04-21 2023-04-28 2023-05-21 2023-05-16 2023-06-25 2023-12-22 or office work for employees velopment cation Selection ation of regional business incubato rs FVRED/CQS/05 / Mid-term im Component 3: Project Manag Consultant Qualifi Under Implement IBRD / 89380 Post Open - National 30,000.00 0.00 2022-08-16 2023-02-10 2022-09-06 2022-10-20 2022-11-19 2022-12-24 2023-06-22 pact evaluation study under ement and Coordination cation Selection ation FVREDP FVED/CQS/17 / Study trip to Component 2: Access to Fin Consultant Qualifi Pending Impleme Hungary for the State Fund f IBRD / 89380 Post Open - National 65,000.00 0.00 2023-07-31 2023-08-21 2023-10-04 2023-11-03 2023-12-08 2024-06-05 ance cation Selection ntation or Entrepreneurship INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FVRED/IC/07 / Preparation of pre-procurement documents Component 3: Project Manag Individual Consult for the project, including doc IBRD / 89380 Post Open - National 10,000.00 0.00 Canceled 2023-02-17 2023-04-07 2023-04-28 2023-06-02 2023-11-29 ement and Coordination ant Selection uments on the areas of envir onmental protection and prot ective measures FVED/IC/18 / Technical cons Component 1: Enterprise De Individual Consult Under Implement ultant for support and ease t IBRD / 89380 Post Open - National 15,000.00 0.00 2023-07-31 2023-07-28 2023-09-18 2023-10-09 2023-11-13 2024-05-11 velopment ant Selection ation he tasks of Project's Compon ent 1 Coordinator Page 1