PROCUREMENT PLAN (Textual Part) Project information: STRENGTHENING PERU'S NATIONAL SCIENCE, TECHNOLOGY AND INNOVATION SYSTEM (P176297) Project Implementation agency: NATIONAL PROGRAM FOR SCIENTIFIC RESEARCH AND ADVANCED STUDIES (PROCIENCIA) Date of the Procurement Plan: 01/18/2023 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Peru : STRENGTHENING PERU'S NATIONAL SCIENCE, TECHNOLOGY AND INNOVATION SYSTEM PLAN General Information Country: Peru 2023-01-18 Bank’s Approval Date of the Original Procurement Plan: 2023-07-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176297 GPN Date: 2022-12-30 Project Name: STRENGTHENING PERU'S NATIONAL SCIENCE, TECHNOLOGY AND INNOVATION SYSTEM Loan / Credit No: IBRD / 93340 National Program for Scientific Research and Advanced Studies Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PROCIENCIA-339687-GO- RFQ / Adquisición de mobiliar io para oficinas del Proyecto 4. Project Management and Solicitud de cotiza Single Stage - One E Ejecución pe “Mejoramiento y Ampliación IBRD / 93340 Posterior Open - National 50,000.00 0.00 2023-07-08 2023-08-27 2023-09-26 Monitoring & Evaluation ciones nvelope ndiente de los Servicios de CTI para f ortalecer el Sistema Nacional de Ciencia, Tecnología e Inno vación”. PE-PROCIENCIA-334146-GO- RFB / Adquisición de Bienes p ara Equipamiento Tecnológic 1: Strengthening SINACTI’s i Solicitud de oferta Single Stage - One E Ejecución pe o para el Proyecto: Mejorami IBRD / 93340 nstitutions and governance t Posterior Open - National 821,105.00 0.00 2023-07-03 2023-07-06 2023-08-17 2023-09-06 2023-10-07 2024-02-04 s nvelope ndiente ento y ampliación de los serv o bolster innovation in Peru icios de CTI para fortalecer el Sistema Nacional de Ciencia, Tecnología e Innovación PE-PROCIENCIA-337438-GO- 1: Strengthening SINACTI’s i RFB / Adquisición de licencias Solicitud de oferta Single Stage - One E Ejecución pe IBRD / 93340 nstitutions and governance t Posterior Open - National 158,291.00 0.00 2023-08-01 2023-08-06 2023-09-17 2023-10-17 2023-11-21 2023-12-21 informáticas de herramientas s nvelope ndiente o bolster innovation in Peru necesarias para la gestión de l Proyecto PE-PROCIENCIA-352355-GO- RFQ / Adquisición de equipo 4. Project Management and Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 93340 Posterior Open - National 77,600.00 0.00 2023-06-28 2023-08-17 2023-09-16 de computo para el equipo i Monitoring & Evaluation ciones nvelope ndiente mplementador del Proyecto NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PROCIENCIA-333995-NC- RFB / Servicio de alquiler de i nfraestructura en nube - Proy 1: Strengthening SINACTI’s i Solicitud de oferta Single Stage - One E Ejecución pe ecto Mejoramiento y ampliaci IBRD / 93340 nstitutions and governance t Posterior Open - National 476,146.00 0.00 2023-04-03 2023-04-08 2023-05-23 2023-06-06 2023-07-24 2026-07-23 s nvelope ndiente ón de los servicios de CTI par o bolster innovation in Peru a fortalecer el Sistema Nacio nal de Ciencia, Tecnología e I nnovación PE-PROCIENCIA-334001-NC- 1: Strengthening SINACTI’s i Adquisición direct Direct - Internation DIR / Suscripción a base de d IBRD / 93340 nstitutions and governance t Posterior 120,000.00 0.00 Cancelado 2023-03-01 2023-03-06 2023-05-10 2026-05-09 a al atos de referencias bibliográf o bolster innovation in Peru icas y citas PE-PROCIENCIA-335374-NC- DIR / Servicio de alquiler de o ficina para el Proyecto Mejor 4. Project Management and Adquisición direct IBRD / 93340 Posterior Direct - National 459,470.00 0.00 En ejecución 2023-04-01 2023-07-07 2023-04-06 2023-07-10 2023-05-11 2026-04-25 amiento y ampliación de los Monitoring & Evaluation a servicios de CTI para fortalec er el Sistema Nacional de Cie ncia, Tecnología e Innovación PE-PROCIENCIA-334000-NC- 1: Strengthening SINACTI’s i RFB / Suscripción de recursos Solicitud de oferta Open - Internationa Single Stage - One E IBRD / 93340 nstitutions and governance t Previa 3,607,035.00 0.00 Cancelado 2023-04-03 2023-04-08 2023-05-20 2023-06-19 2023-07-24 2026-07-23 de información de texto com s l nvelope o bolster innovation in Peru pleto con editor PE-PROCIENCIA-334005-NC- 4. Project Management and Solicitud de cotiza Single Stage - One E Ejecución pe RFQ / Servicio de correo elect IBRD / 93340 Posterior Open - National 42,211.00 0.00 2023-08-06 2023-10-01 2024-09-30 Monitoring & Evaluation ciones nvelope ndiente rónico para el Proyecto PE-PROCIENCIA-352954-NC- 1: Strengthening SINACTI’s i RFB / Servicio de suscripción Solicitud de oferta Open - Internationa Single Stage - One E IBRD / 93340 nstitutions and governance t Posterior 340,000.00 0.00 Cancelado 2023-04-21 2023-04-22 2023-06-06 2023-06-20 2023-08-01 2025-07-31 a base de datos de referenci s l nvelope o bolster innovation in Peru as bibliográficas y citas PE-PROCIENCIA-353049-NC- RFQ / Servicio de publicación de avisos en diarios para el P 4. Project Management and Solicitud de cotiza Single Stage - One E Ejecución pe royecto “Mejoramiento y Am IBRD / 93340 Posterior Open - National 50,000.00 0.00 2023-04-12 2023-05-28 2024-05-27 Monitoring & Evaluation ciones nvelope ndiente pliación de los Servicios de C TI para fortalecer el Sistema Nacional de Ciencia, Tecnolo gía e Innovación” PE-PROCIENCIA-358440-NC- 1: Strengthening SINACTI’s i Adquisición direct Direct - Internation DIR / Suscripción Nacional de IBRD / 93340 nstitutions and governance t Previa 4,009,946.00 0.00 En ejecución 2023-05-09 2023-05-02 2023-05-29 2023-05-04 2023-07-04 2025-07-03 a al Recursos de información de o bolster innovation in Peru Texto Completo PE-PROCIENCIA-361882-NC- RFQ / Servicio de agenciamie 4. Project Management and Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 93340 Posterior Open - National 30,000.00 0.00 2023-07-05 2023-08-20 2024-08-19 nto de pasajes aéreos a nivel Monitoring & Evaluation ciones nvelope ndiente nacional para el Proyecto Page 1 PE-PROCIENCIA-338461-NC- RFQ / Servicio de mejoramie nto y adecuación de instalaci ones para las Oficinas del Pro 4. Project Management and Solicitud de cotiza Single Stage - One E Ejecución pe IBRD / 93340 Posterior Open - National 50,000.00 0.00 2023-07-05 2023-08-24 2023-10-23 yecto Mejoramiento y amplia Monitoring & Evaluation ciones nvelope ndiente ción de los servicios de CTI p ara fortalecer el Sistema Naci onal de Ciencia, Tecnología e Innovación PE-PROCIENCIA-339685-NC- RFQ / Contratación de servici 4. Project Management and Solicitud de cotiza Single Stage - One E Ejecución pe o de cableado estructurado d IBRD / 93340 Posterior Open - National 50,000.00 0.00 2023-07-05 2023-08-24 2023-10-23 Monitoring & Evaluation ciones nvelope ndiente e red de datos y eléctrico par a Oficinas del Proyecto PE-PROCIENCIA-373216-NC- RFQ / Servicio de levantamie 1: Strengthening SINACTI’s i Solicitud de cotiza Single Stage - One E Ejecución pe nto y procesamiento de dato IBRD / 93340 nstitutions and governance t Posterior Open - National 72,236.00 0.00 2023-08-12 2023-10-12 2024-04-09 ciones nvelope ndiente s de la encuesta de eficiencia o bolster innovation in Peru de gasto público en CTI CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PROCIENCIA-334143-CS-L CS / Auditoria Externa para el Proyecto Mejoramiento y am 4. Project Management and Selección basada IBRD / 93340 Posterior Open - National 85,427.00 0.00 Bajo Revision 2023-06-01 2023-07-17 2023-06-22 2023-08-05 2023-09-02 2023-10-02 2023-11-06 2023-12-11 2026-12-10 pliación de los servicios de C Monitoring & Evaluation en el menor costo TI para fortalecer el Sistema Nacional de Ciencia, Tecnolo gía e Innovación PE-PROCIENCIA-334361-CS-L 1: Strengthening SINACTI’s i Selección basada Ejecución pendien CS / Servicio de control de ca IBRD / 93340 nstitutions and governance t Posterior Open - National 213,065.33 0.00 2023-04-01 2023-04-22 2023-05-25 2023-06-22 2023-07-22 2023-09-06 2023-10-27 2025-12-05 en el menor costo te lidad de software o bolster innovation in Peru PE-PROCIENCIA-334358-CS- 1: Strengthening SINACTI’s i Selección basada CQS / Servicio para elaborar Ejecución pendien IBRD / 93340 nstitutions and governance t Posterior en calificaciones d Open - National 11,871.86 0.00 2023-05-01 2023-05-22 2023-07-21 2023-08-20 2023-09-24 2024-01-22 un estudio de vigilancia tecn te o bolster innovation in Peru e consultores ológica en biotecnología agro alimentaria PE-PROCIENCIA-334346-CS- CQS / Servicio para elaborar 1: Strengthening SINACTI’s i Selección basada Ejecución pendien un estudio de vigilancia tecn IBRD / 93340 nstitutions and governance t Posterior en calificaciones d Open - National 11,871.86 0.00 2023-05-01 2023-05-22 2023-07-26 2023-08-25 2023-10-05 2024-02-02 te ológica en Tecnologías emer o bolster innovation in Peru e consultores gentes y disruptivas para SM ART CITIES PE-PROCIENCIA-334364-CS- 3. Strengthening Industry-ac CQS / Desarrollo de metodolo ademia linkages to accelerat Selección basada Ejecución pendien gías para priorizar tecnología IBRD / 93340 e technology transfer and sc Posterior en calificaciones d Open - National 62,814.07 0.00 2023-04-01 2023-04-22 2023-06-21 2023-07-21 2023-09-10 2024-03-08 te s con potencial de financiami ience-based business innova e consultores ento y con alto impacto tion PE-PROCIENCIA-334345-CS- 3. Strengthening Industry-ac CQS / Servicio de preevaluaci ademia linkages to accelerat Selección basada Ejecución pendien ón de proyectos financiados IBRD / 93340 e technology transfer and sc Posterior en calificaciones d Open - National 75,376.88 0.00 2023-05-01 2023-05-22 2023-07-21 2023-08-20 2023-10-10 2024-04-07 te por CONCYTEC y acompaña ience-based business innova e consultores miento para financiamiento tion PE-PROCIENCIA-334360-CS- CQS / Servicio de elaboración de la linea base del Proyecto Selección basada 4. Project Management and Mejoramiento y ampliación d IBRD / 93340 Posterior en calificaciones d Open - National 100,502.51 0.00 Cancelado 2023-06-01 2023-06-22 2023-08-21 2023-09-20 2023-10-31 2024-04-28 Monitoring & Evaluation e los servicios de CTI para for e consultores talecer el Sistema Nacional d e Ciencia, Tecnología e Innov ación PE-PROCIENCIA-334332-CS- CQS / Desarrollo del módulo Selección basada 4. Project Management and de vinculación con usuarios d IBRD / 93340 Posterior en calificaciones d Open - National 87,939.70 0.00 En ejecución 2023-04-01 2023-06-22 2023-04-22 2023-06-05 2023-06-25 2023-07-19 2024-01-15 Monitoring & Evaluation e fondos concursables (Plataf e consultores orma de Gestión de Fondos) PE-PROCIENCIA-334341-CS- CQS / Servicio de desarrollo 2. Capacity development for Selección basada del análisis de demanda de s Ejecución pendien IBRD / 93340 the generation of knowledge Posterior en calificaciones d Open - National 50,251.26 0.00 2023-08-01 2023-08-22 2023-10-26 2023-11-15 2023-12-26 2024-06-23 ectores productivos para el d te in Strategic Areas e consultores esarrollo de proyectos de inv estigación en áreas estratégi cas PE-PROCIENCIA-334308-CS- 1: Strengthening SINACTI’s i Selección basada Ejecución pendien CQS / Implementación de her IBRD / 93340 nstitutions and governance t Posterior en calificaciones d Open - National 179,899.00 0.00 2023-08-01 2023-08-22 2023-10-21 2023-11-20 2023-12-25 2024-03-24 te ramientas de soporte al gobi o bolster innovation in Peru e consultores erno de datos PE-PROCIENCIA-334302-CS- 1: Strengthening SINACTI’s i Selección basada CQS / Servicio de diseño e im Ejecución pendien IBRD / 93340 nstitutions and governance t Posterior en calificaciones d Open - National 150,754.00 0.00 2023-04-01 2023-04-22 2023-06-05 2023-07-05 2023-08-09 2024-02-05 plementación del proceso de te o bolster innovation in Peru e consultores mesa de ayuda. PE-PROCIENCIA-347908-CS- CQS / Desarrollo de propuest 1: Strengthening SINACTI’s i Selección basada a de arreglos normativos par Ejecución pendien IBRD / 93340 nstitutions and governance t Posterior en calificaciones d Open - National 100,503.00 0.00 2023-08-01 2023-08-15 2023-10-09 2023-10-23 2023-11-20 2024-05-18 a la implementación de los p te o bolster innovation in Peru e consultores rocesos de licenciamiento y a creditación de programas de posgrado PE-PROCIENCIA-334307-CS- 1: Strengthening SINACTI’s i Selección basada CQS / Servicio de diseño e im Ejecución pendien IBRD / 93340 nstitutions and governance t Posterior en calificaciones d Open - National 30,151.00 0.00 2023-08-01 2023-08-22 2023-10-05 2023-11-04 2023-12-09 2024-06-06 plementación de la línea de p te o bolster innovation in Peru e consultores roducción de microformas PE-PROCIENCIA-334340-CS- 1: Strengthening SINACTI’s i Selección basada CQS / Servicio de diseño de a Ejecución pendien IBRD / 93340 nstitutions and governance t Posterior en calificaciones d Open - National 92,964.82 0.00 2023-12-01 2023-12-22 2024-02-10 2024-03-11 2024-04-15 2024-10-12 rreglo institucional para desa te o bolster innovation in Peru e consultores rrollar red de sostenibilidad PE-PROCIENCIA-334347-CS- CQS / Desarrollo del módulo 1: Strengthening SINACTI’s i Selección basada Ejecución pendien de gestión de evaluadores co IBRD / 93340 nstitutions and governance t Posterior en calificaciones d Open - National 62,814.07 0.00 2023-09-01 2023-09-22 2023-11-05 2023-11-25 2023-12-19 2025-01-12 te n enfoque regional – Latinoa o bolster innovation in Peru e consultores mérica (Plataforma de Gestió n de Fondos) Page 2 PE-PROCIENCIA-334365-CS- CQS / Servicio de programa d 1: Strengthening SINACTI’s i Selección basada Ejecución pendien e capacitación especializada IBRD / 93340 nstitutions and governance t Posterior en calificaciones d Open - National 251,256.28 0.00 2023-10-02 2023-10-23 2023-12-06 2023-12-21 2024-01-10 2024-11-05 te para el fortalecimiento de ca o bolster innovation in Peru e consultores pacidades en gestión y opera ción de laboratorios PE-PROCIENCIA-334348-CS-L 1: Strengthening SINACTI’s i CS / Servicio para levantamie Selección basada Ejecución pendien IBRD / 93340 nstitutions and governance t Posterior Open - National 75,376.88 0.00 2023-11-01 2023-11-22 2024-01-05 2024-01-12 2024-01-22 2024-02-08 2024-03-03 2024-08-30 nto de información sobre gru en el menor costo te o bolster innovation in Peru pos, líneas y áreas de investi gación PE-PROCIENCIA-347915-CS- 1: Strengthening SINACTI’s i QCBS / Servicio para el desar Selección basada Ejecución pendien IBRD / 93340 nstitutions and governance t Posterior Open - National 201,005.00 0.00 2023-07-03 2023-07-24 2023-08-28 2023-10-17 2023-10-31 2023-12-14 2024-01-27 2025-01-26 rollo de diagnóstico y estado en calidad y costo te o bolster innovation in Peru del arte para programas de p osgrado PE-PROCIENCIA-335076-CS- QCBS / Servicio para la siste 1: Strengthening SINACTI’s i matización de procesos admi Selección basada Open - Internationa Ejecución pendien IBRD / 93340 nstitutions and governance t Posterior 482,412.00 0.00 2023-08-01 2023-08-22 2023-09-26 2023-11-15 2023-11-29 2024-01-12 2024-02-09 2025-02-08 nistrativos y misionales, de g en calidad y costo l te o bolster innovation in Peru estión documental, e implem entación de herramientas de optimización de procesos PE-PROCIENCIA-334352-CS- 3. Strengthening Industry-ac QCBS / Consultoría para defi ademia linkages to accelerat Selección basada Open - Internationa Ejecución pendien IBRD / 93340 Previa 1,130,653.00 0.00 2023-10-02 2023-10-23 2023-11-27 2024-01-16 2024-01-30 2024-03-14 2024-04-18 2024-08-16 nición de modelo de Oficina e technology transfer and sc en calidad y costo l te de Transferencia Tecnológica ience-based business innova y capacitaciones tion PE-PROCIENCIA-337449-CS- 1: Strengthening SINACTI’s i Selección basada Ejecución pendien QCBS / Consultoría para la im IBRD / 93340 nstitutions and governance t Posterior Open - National 188,944.72 0.00 2023-09-01 2023-09-22 2023-12-01 2023-12-06 2023-12-20 2024-01-20 2024-02-24 2027-02-23 en calidad y costo te plementación de funcionalida o bolster innovation in Peru des de PerúCris PE-PROCIENCIA-334344-CS- 3. Strengthening Industry-ac QCBS / Capacitación, acompa ademia linkages to accelerat ñamiento y asistencia técnic Selección basada Open - Internationa IBRD / 93340 e technology transfer and sc Posterior 829,145.36 0.00 En ejecución 2023-07-03 2023-07-20 2023-07-24 2023-08-28 2023-10-17 2023-10-31 2023-12-14 2024-01-07 2025-01-06 a para la formulación e identi en calidad y costo l ience-based business innova ficación de las iniciativas de tion vinculación academia industr ia INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PE-PROCIENCIA-334889-CS- 4. Project Management and CDS / Asistente Coordinación IBRD / 93340 Posterior Individual Direct - National 21,105.53 0.00 Firmado 2023-02-17 2023-03-07 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2023-03-31 2024-03-23 Monitoring & Evaluation Administrativa 1 PE-PROCIENCIA-334895-CS- 4. Project Management and CDS / Analista en Soporte y S IBRD / 93340 Posterior Individual Direct - National 33,166.00 0.00 En ejecución 2023-02-17 2023-03-23 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation eguimiento Subvenciones PE-PROCIENCIA-335025-CS-I 4. Project Management and NDV / Analista en Tecnología IBRD / 93340 Posterior Individual Limited 24,121.00 0.00 En ejecución 2023-03-01 2023-06-09 2023-03-06 2023-03-21 2023-04-14 2024-04-13 Monitoring & Evaluation de la Información 1 PE-PROCIENCIA-335027-CS-I 4. Project Management and NDV / Analista en Tecnología IBRD / 93340 Posterior Individual Limited 24,121.00 0.00 En ejecución 2023-03-01 2023-06-09 2023-03-06 2023-03-21 2023-04-14 2024-04-13 Monitoring & Evaluation de la Información 2 PE-PROCIENCIA-334618-CS-I 1: Strengthening SINACTI’s i NDV / Apoyo de recopilación, IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 48,241.20 0.00 En ejecución 2023-03-15 2023-03-06 2023-04-08 2023-05-17 2023-04-18 2023-05-17 2023-05-12 2024-05-11 calidad y procesamiento de d o bolster innovation in Peru atos - PerúCris PE-PROCIENCIA-334619-CS-I 1: Strengthening SINACTI’s i NDV / Especialista para la ge IBRD / 93340 nstitutions and governance t Posterior Individual Limited 21,105.53 0.00 En ejecución 2023-03-01 2023-03-06 2023-03-06 2023-03-21 2023-04-14 2024-04-13 stión de implementación de i o bolster innovation in Peru nteroperabilidad PE-PROCIENCIA-334620-CS-I 1: Strengthening SINACTI’s i NDV / Soporte administrativo IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 21,105.53 0.00 En ejecución 2023-03-15 2023-03-06 2023-04-08 2023-04-18 2023-05-12 2024-05-11 para gestión administrativa o bolster innovation in Peru PE-PROCIENCIA-334795-CS-I 1: Strengthening SINACTI’s i NDV / Experto en gestión de IBRD / 93340 nstitutions and governance t Posterior Individual Limited 39,195.98 0.00 En ejecución 2023-03-01 2023-04-14 2023-03-06 2023-03-21 2023-04-14 2024-04-13 organismos de investigación o bolster innovation in Peru PE-PROCIENCIA-334800-CS-I 1: Strengthening SINACTI’s i NDV / Experto en gestión y r IBRD / 93340 nstitutions and governance t Posterior Individual Limited 30,150.75 0.00 En ejecución 2023-03-01 2023-04-20 2023-03-06 2023-03-21 2023-04-14 2024-04-13 egulación o bolster innovation in Peru PE-PROCIENCIA-334801-CS- 1: Strengthening SINACTI’s i CDS / Soporte administrativo IBRD / 93340 nstitutions and governance t Posterior Individual Direct - National 21,105.53 0.00 En ejecución 2023-02-17 2023-02-01 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 para gestión administrativa - o bolster innovation in Peru Componente I PE-PROCIENCIA-334799-CS- 1: Strengthening SINACTI’s i Direct - Internation CDS / Consultoría para el Est IBRD / 93340 nstitutions and governance t Posterior Individual 50,251.26 0.00 En ejecución 2023-04-03 2023-04-10 2023-04-13 2023-07-17 2023-04-23 2023-05-08 2023-11-04 al udio de Eficiencia del Gasto P o bolster innovation in Peru úblico en CTI PE-PROCIENCIA-334802-CS-I 1: Strengthening SINACTI’s i NDV / Experto en gestión y a IBRD / 93340 nstitutions and governance t Posterior Individual Limited 39,195.98 0.00 En ejecución 2023-03-01 2023-04-20 2023-03-06 2023-03-21 2023-04-14 2024-04-13 rticulación de CTI o bolster innovation in Peru PE-PROCIENCIA-334804-CS-I 1: Strengthening SINACTI’s i Ejecución pendien NDV / Monitor Financiero par IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 12,060.30 0.00 2023-06-01 2023-06-25 2023-07-05 2023-07-29 2024-01-25 te a supervisión - Redes de inve o bolster innovation in Peru stigación PE-PROCIENCIA-334805-CS-I 2. Capacity development for Ejecución pendien NDV / Monitores Técnicos par IBRD / 93340 the generation of knowledge Posterior Individual Open - National 60,301.51 0.00 2023-06-01 2023-06-25 2023-07-05 2023-07-29 2024-01-25 te a supervisión in Strategic Areas PE-PROCIENCIA-334809-CS-I 2. Capacity development for NDV / Servicio de análisis de IBRD / 93340 the generation of knowledge Posterior Individual Limited 16,582.91 0.00 En ejecución 2023-03-01 2023-04-20 2023-03-06 2023-03-21 2023-04-14 2024-04-13 datos - Programa de Doctora in Strategic Areas do PE-PROCIENCIA-334808-CS-I 2. Capacity development for NDV / Experto en programas IBRD / 93340 the generation of knowledge Posterior Individual Limited 39,195.98 0.00 Cancelado 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 de postgrado de investigació in Strategic Areas n Page 3 3. Strengthening Industry-ac PE-PROCIENCIA-334821-CS-I ademia linkages to accelerat IBRD / 93340 Posterior Individual Limited 16,582.91 0.00 En ejecución 2023-03-01 2023-05-05 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Apoyo Comunicacional e technology transfer and sc ience-based business innova tion 3. Strengthening Industry-ac PE-PROCIENCIA-334823-CS-I ademia linkages to accelerat NDV / Servicio en análisis de IBRD / 93340 Posterior Individual Open - National 16,582.91 0.00 En ejecución 2023-03-15 2023-07-18 2023-04-08 2023-04-18 2023-05-12 2024-05-11 e technology transfer and sc datos ience-based business innova tion 3. Strengthening Industry-ac PE-PROCIENCIA-334838-CS-I ademia linkages to accelerat IBRD / 93340 Posterior Individual Limited 39,195.98 0.00 En ejecución 2023-03-01 2023-04-20 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Experto en innovación e technology transfer and sc ience-based business innova tion PE-PROCIENCIA-334845-CS- CDS / Coordinador Adjunto p ara el Proyecto “Mejoramient 4. Project Management and IBRD / 93340 Posterior Individual Direct - National 60,301.51 0.00 En ejecución 2023-02-17 2023-03-02 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 o y Ampliación de los servicio Monitoring & Evaluation s de CTI para fortalecer el Sis tema Nacional de Ciencia, Te cnología e Innovación” PE-PROCIENCIA-334848-CS- 4. Project Management and CDS / Coordinador de Segui IBRD / 93340 Posterior Individual Direct - National 51,256.28 0.00 En ejecución 2023-02-17 2023-03-02 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation miento y Monitoreo PE-PROCIENCIA-334850-CS- 4. Project Management and CDS / Asistente Administrativ IBRD / 93340 Posterior Individual Direct - National 21,105.53 0.00 Firmado 2023-02-17 2023-03-02 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2023-03-31 2024-03-23 Monitoring & Evaluation o para la Coordinación Adjunt a PE-PROCIENCIA-334853-CS-I 4. Project Management and NDV / Asistente Administrativ IBRD / 93340 Posterior Individual Open - National 15,075.38 0.00 En ejecución 2023-10-02 2023-05-05 2023-10-26 2023-11-05 2023-11-29 2024-11-28 Monitoring & Evaluation o en Archivo PE-PROCIENCIA-339636-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Open - National 39,195.98 0.00 En ejecución 2023-03-15 2023-03-17 2023-04-08 2023-04-18 2023-05-12 2024-05-11 NDV / Coordinador de Compo Monitoring & Evaluation nente 1 PE-PROCIENCIA-334857-CS- 4. Project Management and IBRD / 93340 Posterior Individual Direct - National 39,195.98 0.00 En ejecución 2023-02-17 2023-03-23 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Coordinador de Compo Monitoring & Evaluation nente 2 PE-PROCIENCIA-334859-CS-I 4. Project Management and NDV / Coordinador de Compo IBRD / 93340 Posterior Individual Limited 39,195.98 0.00 En ejecución 2023-03-01 2023-03-17 2023-03-06 2023-03-24 2023-03-21 2023-04-21 2023-04-14 2024-04-13 Monitoring & Evaluation nente 3 - Personal Clave PE-PROCIENCIA-334869-CS- 4. Project Management and IBRD / 93340 Posterior Individual Direct - National 39,195.98 0.00 En ejecución 2023-02-17 2023-03-02 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 CDS / Especialista Socio Amb Monitoring & Evaluation iental PE-PROCIENCIA-334879-CS- 4. Project Management and IBRD / 93340 Posterior Individual Direct - National 30,150.75 0.00 En ejecución 2023-02-17 2023-03-02 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 CDS / Analista Ambiental Monitoring & Evaluation PE-PROCIENCIA-334883-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Open - National 30,150.75 0.00 En ejecución 2023-03-15 2023-03-02 2023-04-08 2023-04-18 2023-05-12 2024-05-11 NDV / Analista Social y de Gé Monitoring & Evaluation nero PE-PROCIENCIA-334884-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Open - National 33,165.83 0.00 En ejecución 2023-03-15 2023-03-15 2023-04-08 2023-05-12 2023-04-18 2023-05-17 2023-05-12 2024-05-11 NDV / Especialista en Comuni Monitoring & Evaluation caciones PE-PROCIENCIA-334885-CS- 4. Project Management and IBRD / 93340 Posterior Individual Direct - National 30,150.75 0.00 En ejecución 2023-02-17 2023-03-15 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Analista de Comunicaci Monitoring & Evaluation ones PE-PROCIENCIA-334886-CS- 4. Project Management and IBRD / 93340 Posterior Individual Direct - National 39,195.98 0.00 En ejecución 2023-02-17 2023-03-07 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 CDS / Especialista en Diseño Monitoring & Evaluation PE-PROCIENCIA-334890-CS- 4. Project Management and CDS / Asistente Administrativ IBRD / 93340 Posterior Individual Direct - National 21,105.53 0.00 En ejecución 2023-02-17 2023-03-07 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation o - Unidad Gestión de Concur sos PE-PROCIENCIA-334891-CS-I 4. Project Management and NDV / Especialista en Evalua IBRD / 93340 Posterior Individual Open - National 39,195.98 0.00 En ejecución 2023-03-15 2023-04-14 2023-04-08 2023-04-18 2023-05-12 2024-05-11 Monitoring & Evaluation ción de Beneficiarios PE-PROCIENCIA-334893-CS- 4. Project Management and CDS / Especialista en Soporte IBRD / 93340 Posterior Individual Direct - National 39,195.98 0.00 Cancelado 2023-02-17 2023-03-23 2023-02-27 2023-03-09 2023-03-24 2024-03-23 Monitoring & Evaluation y Seguimiento Subvenciones PE-PROCIENCIA-334989-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Limited 39,195.98 0.00 En ejecución 2023-03-01 2023-05-30 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Especialista en Vincula Monitoring & Evaluation ción PE-PROCIENCIA-335075-CS-I 4. Project Management and NDV / Asistente Técnico - Uni IBRD / 93340 Posterior Individual Open - National 21,105.53 0.00 En ejecución 2023-03-15 2023-05-30 2023-04-08 2023-04-18 2023-05-12 2024-05-11 Monitoring & Evaluation dad de Vinculación PE-PROCIENCIA-334992-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Open - National 33,165.83 0.00 En ejecución 2023-03-15 2023-03-07 2023-04-08 2023-04-17 2023-04-18 2023-04-17 2023-05-12 2024-05-11 NDV / Analista Legal Monitoring & Evaluation PE-PROCIENCIA-334993-CS- 4. Project Management and CDS / Especialista en Planific IBRD / 93340 Posterior Individual Direct - National 42,211.06 0.00 En ejecución 2023-02-17 2023-03-01 2023-02-27 2023-03-09 2023-03-24 2024-03-23 Monitoring & Evaluation ación y Presupuesto PE-PROCIENCIA-334996-CS-I 4. Project Management and Ejecución pendien NDV / Especialista en Seguim IBRD / 93340 Posterior Individual Open - National 39,195.98 0.00 2023-10-02 2023-10-26 2023-11-05 2023-11-29 2024-11-28 Monitoring & Evaluation te iento y Monitoreo PE-PROCIENCIA-334998-CS- 4. Project Management and CDS / Analista de Seguimient IBRD / 93340 Posterior Individual Direct - National 30,150.75 0.00 En ejecución 2023-02-17 2023-03-02 2023-02-27 2023-03-09 2023-03-24 2024-03-23 Monitoring & Evaluation o y Monitoreo PE-PROCIENCIA-335000-CS- CDS / Especialista de Implem 4. Project Management and IBRD / 93340 Posterior Individual Direct - National 28,643.22 0.00 En ejecución 2023-02-17 2023-03-01 2023-02-27 2023-03-09 2023-03-24 2024-03-23 entación, Gestión y Monitore Monitoring & Evaluation o de Intervenciones PE-PROCIENCIA-335001-CS- 4. Project Management and CDS / Especialista en Soporte IBRD / 93340 Posterior Individual Direct - National 24,120.60 0.00 En ejecución 2023-02-17 2023-03-01 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation de Gestión Administrativa PE-PROCIENCIA-335002-CS- 4. Project Management and CDS / Especialista Técnico pa IBRD / 93340 Posterior Individual Direct - National 39,195.98 0.00 En ejecución 2023-02-17 2023-03-01 2023-02-27 2023-03-14 2023-03-09 2023-03-23 2023-03-24 2024-03-23 Monitoring & Evaluation ra implementación de proyec tos de CTI Page 4 PE-PROCIENCIA-335003-CS-I 4. Project Management and IBRD / 93340 Previa Individual Open - National 45,226.13 0.00 En ejecución 2023-03-15 2023-03-02 2023-04-08 2023-04-24 2023-04-18 2023-04-27 2023-05-12 2024-05-11 NDV / Especialista en Adquisi Monitoring & Evaluation ciones PE-PROCIENCIA-335005-CS-I 4. Project Management and NDV / Especialista en Adquisi IBRD / 93340 Previa Individual Open - National 39,195.98 0.00 Cancelado 2023-03-15 2023-03-02 2023-04-08 2023-04-18 2023-05-12 2024-05-11 Monitoring & Evaluation ciones - Subproyectos PE-PROCIENCIA-335007-CS-I 4. Project Management and NDV / Asistente Administrativ IBRD / 93340 Previa Individual Limited 21,105.53 0.00 En ejecución 2023-03-01 2023-03-07 2023-03-06 2023-04-24 2023-03-21 2023-05-19 2023-04-14 2024-04-13 Monitoring & Evaluation o - Adquisiciones PE-PROCIENCIA-335008-CS- 4. Project Management and IBRD / 93340 Previa Individual Direct - National 30,151.00 0.00 En ejecución 2023-02-17 2023-03-08 2023-02-27 2023-03-14 2023-03-09 2023-04-24 2023-03-24 2024-03-23 CDS / Analista en Adquisicion Monitoring & Evaluation es 1 PE-PROCIENCIA-335011-CS- 4. Project Management and IBRD / 93340 Posterior Individual Direct - National 42,211.06 0.00 En ejecución 2023-02-17 2023-03-15 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Especialista en Tesorer Monitoring & Evaluation ía PE-PROCIENCIA-335012-CS- 4. Project Management and IBRD / 93340 Posterior Individual Direct - National 27,135.68 0.00 En ejecución 2023-02-17 2023-03-15 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Analista en Tesorería Monitoring & Evaluation PE-PROCIENCIA-335019-CS- 4. Project Management and IBRD / 93340 Posterior Individual Direct - National 27,135.68 0.00 En ejecución 2023-02-17 2023-03-17 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Analista de Contabilida Monitoring & Evaluation d PE-PROCIENCIA-335021-CS-I 4. Project Management and NDV / Especialista en Tecnol IBRD / 93340 Posterior Individual Open - National 39,195.98 0.00 En ejecución 2023-03-15 2023-06-09 2023-04-08 2023-04-18 2023-05-12 2024-05-11 Monitoring & Evaluation ogía de la Información PE-PROCIENCIA-335023-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Limited 21,105.53 0.00 Cancelado 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Analista Técnico SIGA - Monitoring & Evaluation SIAF PE-PROCIENCIA-335029-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Limited 30,150.75 0.00 En ejecución 2023-03-01 2023-03-06 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Profesional Ejecución C Monitoring & Evaluation ontractual PE-PROCIENCIA-335032-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Limited 21,105.53 0.00 En ejecución 2023-03-01 2023-03-06 2023-03-06 2023-04-26 2023-03-21 2023-04-14 2024-04-13 NDV / Analista Ejecución Con Monitoring & Evaluation tractual PE-PROCIENCIA-335010-CS-I 4. Project Management and IBRD / 93340 Previa Individual Limited 30,151.00 0.00 Cancelado 2023-03-01 2023-03-07 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Analista en Adquisicion Monitoring & Evaluation es 3 PE-PROCIENCIA-335009-CS-I 4. Project Management and IBRD / 93340 Previa Individual Limited 30,151.00 0.00 Cancelado 2023-03-01 2023-03-08 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Analista en Adquisicion Monitoring & Evaluation es 2 PE-PROCIENCIA-337642-CS-I 2. Capacity development for NDV / Especialista en I+D - N IBRD / 93340 the generation of knowledge Posterior Individual Limited 30,151.00 0.00 En ejecución 2023-03-01 2023-04-14 2023-03-06 2023-03-21 2023-04-14 2024-04-13 ecesidades de Áreas Estratég in Strategic Areas icas PE-PROCIENCIA-347874-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Open - National 42,211.00 0.00 En ejecución 2023-03-22 2023-03-10 2023-04-20 2023-04-16 2023-04-25 2023-04-17 2023-05-19 2024-05-18 NDV / Especialista Legal Monitoring & Evaluation PE-PROCIENCIA-347875-CS-I 1: Strengthening SINACTI’s i NDV / Experto en diseño de p IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 30,151.00 0.00 En ejecución 2023-03-22 2023-04-20 2023-04-20 2023-04-30 2023-05-24 2024-05-23 olíticas publicas de CTI o bolster innovation in Peru PE-PROCIENCIA-347877-CS-I 2. Capacity development for NDV / Especialista en Fortale IBRD / 93340 the generation of knowledge Posterior Individual Open - National 30,150.25 0.00 En ejecución 2023-03-22 2023-04-20 2023-04-20 2023-04-30 2023-05-24 2024-05-23 cimiento de Capital Físico - F in Strategic Areas ortalecimiento de Laboratori os 3. Strengthening Industry-ac PE-PROCIENCIA-347881-CS-I ademia linkages to accelerat NDV / Experto en Transferen IBRD / 93340 Posterior Individual Open - National 39,196.00 0.00 En ejecución 2023-03-22 2023-05-05 2023-04-20 2023-04-30 2023-05-24 2024-05-23 e technology transfer and sc cia de Tecnología ience-based business innova tion PE-PROCIENCIA-347883-CS-I 3. Strengthening Industry-ac NDV / Profesional en gestión ademia linkages to accelerat IBRD / 93340 Posterior Individual Open - National 30,151.00 0.00 En ejecución 2023-03-22 2023-04-14 2023-04-20 2023-04-30 2023-05-24 2024-05-23 de la innovación y transferen e technology transfer and sc cia de tecnología ience-based business innova tion PE-PROCIENCIA-347884-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Open - National 42,211.00 0.00 En ejecución 2023-03-22 2023-03-10 2023-04-25 2023-04-17 2023-05-05 2023-04-17 2023-05-29 2024-05-28 NDV / Especialista Financiero Monitoring & Evaluation PE-PROCIENCIA-334991-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Limited 42,211.06 0.00 Cancelado 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 NDV / Especialista Legal Monitoring & Evaluation PE-PROCIENCIA-334796-CS-I 1: Strengthening SINACTI’s i NDV / Experto en Diseño de IBRD / 93340 nstitutions and governance t Posterior Individual Limited 30,150.75 0.00 Cancelado 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 políticas publicas de CTI o bolster innovation in Peru PE-PROCIENCIA-334816-CS-I 2. Capacity development for NDV / Especialista en Fortale IBRD / 93340 the generation of knowledge Posterior Individual Limited 30,150.75 0.00 Cancelado 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 cimiento de Capital Físico - F in Strategic Areas ortalecimiento de laboratorio s 3. Strengthening Industry-ac PE-PROCIENCIA-334833-CS-I ademia linkages to accelerat NDV / Experto en transferenc IBRD / 93340 Posterior Individual Limited 39,195.98 0.00 Cancelado 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 e technology transfer and sc ia de tecnología ience-based business innova tion PE-PROCIENCIA-334835-CS-I 3. Strengthening Industry-ac NDV / Profesional en gestión ademia linkages to accelerat IBRD / 93340 Posterior Individual Limited 30,150.75 0.00 Cancelado 2023-03-01 2023-03-06 2023-03-21 2023-04-14 2024-04-13 de la innovación y transferen e technology transfer and sc cia de tecnología ience-based business innova tion PE-PROCIENCIA-335013-CS- 4. Project Management and IBRD / 93340 Posterior Individual Direct - National 42,211.06 0.00 Cancelado 2023-02-17 2023-02-27 2023-03-09 2023-03-24 2024-03-23 CDS / Especialista Financiero Monitoring & Evaluation PE-PROCIENCIA-352364-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Limited 21,106.00 0.00 En ejecución 2023-04-20 2023-04-14 2023-04-25 2023-05-10 2023-06-03 2024-06-02 NDV / Apoyo Técnico en SIGA Monitoring & Evaluation - SIAF PE-PROCIENCIA-357990-CS- 4. Project Management and Selección directa IBRD / 93340 Posterior Direct - National 33,166.00 0.00 Cancelado 2023-05-08 2023-05-15 2023-05-18 2023-06-12 2024-06-11 CDS / Analista en Adquisicion Monitoring & Evaluation de consultores es 2 PE-PROCIENCIA-357991-CS- 4. Project Management and Selección directa IBRD / 93340 Previa Direct - National 33,166.00 0.00 En ejecución 2023-05-08 2023-05-19 2023-05-18 2023-06-20 2023-06-12 2024-06-11 CDS / Analista en Adquisicion Monitoring & Evaluation de consultores es 3 Page 5 PE-PROCIENCIA-334995-CS-I 4. Project Management and NDV / Analista en Planeamie IBRD / 93340 Posterior Individual Open - National 36,180.90 0.00 En ejecución 2023-03-15 2023-05-15 2023-04-08 2023-04-18 2023-05-12 2024-05-11 Monitoring & Evaluation nto y Presupuesto Sénior PE-PROCIENCIA-361886-CS-I 2. Capacity development for NDV / Experto en programas IBRD / 93340 the generation of knowledge Posterior Individual Limited 39,196.00 0.00 En ejecución 2023-07-03 2023-06-09 2023-07-08 2023-07-23 2023-08-16 2024-08-15 de postgrado de investigació in Strategic Areas n 1: Strengthening SINACTI’s i PE-PROCIENCIA-334624-CS-I IBRD / 93340 nstitutions and governance t Posterior Individual Limited 18,844.22 0.00 En ejecución 2023-07-03 2023-06-09 2023-07-08 2023-07-23 2023-08-16 2024-08-15 NDV / Especialista en testing o bolster innovation in Peru PE-PROCIENCIA-334888-CS-I 4. Project Management and Ejecución pendien IBRD / 93340 Posterior Individual Open - National 30,150.75 0.00 2023-07-03 2023-07-27 2023-08-06 2023-08-30 2024-08-29 NDV / Analista de Diseño Monitoring & Evaluation te PE-PROCIENCIA-334623-CS-I 1: Strengthening SINACTI’s i Ejecución pendien NDV / Especialista en desarro IBRD / 93340 nstitutions and governance t Posterior Individual Limited 60,301.50 0.00 2023-07-03 2023-07-08 2023-07-23 2023-08-16 2024-08-15 te llo de software - PerúCris o bolster innovation in Peru PE-PROCIENCIA-334988-CS-I 4. Project Management and Ejecución pendien NDV / Asistente Técnico para IBRD / 93340 Posterior Individual Open - National 21,105.53 0.00 2023-07-03 2023-07-27 2023-08-06 2023-08-30 2024-08-29 Monitoring & Evaluation te la Unidad de Vinculación PE-PROCIENCIA-334994-CS-I 4. Project Management and Ejecución pendien NDV / Asistente Administrativ IBRD / 93340 Posterior Individual Open - National 21,105.53 0.00 2023-07-03 2023-07-27 2023-08-06 2023-08-30 2024-08-29 Monitoring & Evaluation te o - Coordinación Administrati va 2 PE-PROCIENCIA-335015-CS-I 4. Project Management and Ejecución pendien NDV / Asistente Administrativ IBRD / 93340 Posterior Individual Open - National 21,105.53 0.00 2023-07-03 2023-07-27 2023-08-06 2023-08-30 2024-08-29 Monitoring & Evaluation te o - Coordinación Administrati va 3 PE-PROCIENCIA-334615-CS-I 1: Strengthening SINACTI’s i Ejecución pendien NDV / Apoyo Técnico en mes IBRD / 93340 nstitutions and governance t Posterior Individual Limited 12,060.30 0.00 2023-07-03 2023-07-08 2023-07-23 2023-08-16 2024-08-15 te a de ayuda o bolster innovation in Peru PE-PROCIENCIA-334810-CS-I 2. Capacity development for Ejecución pendien NDV / Monitores senior - bec IBRD / 93340 the generation of knowledge Posterior Individual Open - National 265,326.63 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 te as in Strategic Areas PE-PROCIENCIA-334814-CS-I 2. Capacity development for NDV / Monitor Financiero par Ejecución pendien IBRD / 93340 the generation of knowledge Posterior Individual Open - National 24,120.60 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 a supervisión - Fortalecimient te in Strategic Areas o de laboratorios 3. Strengthening Industry-ac PE-PROCIENCIA-334840-CS-I ademia linkages to accelerat Ejecución pendien NDV / Monitores Técnicos par IBRD / 93340 Posterior Individual Open - National 241,206.03 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 e technology transfer and sc te a supervisión ience-based business innova tion PE-PROCIENCIA-334616-CS-I 1: Strengthening SINACTI’s i Ejecución pendien NDV / Coordinación de proye IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 36,180.90 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 te ctos de transformación digita o bolster innovation in Peru l PE-PROCIENCIA-334813-CS-I 2. Capacity development for Ejecución pendien NDV / Monitor Técnico para s IBRD / 93340 the generation of knowledge Posterior Individual Open - National 30,150.75 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 te upervisión - Fortalecimiento in Strategic Areas de laboratorios PE-PROCIENCIA-334819-CS-I 3. Strengthening Industry-ac NDV / Consultores para brind ademia linkages to accelerat Ejecución pendien ar apoyo y seguimiento a los IBRD / 93340 e technology transfer and sc Posterior Individual Open - National 84,422.11 0.00 2023-09-01 2023-09-25 2023-10-05 2023-10-29 2024-10-28 te equipos de gestión de iniciati ience-based business innova vas de vinculación academia tion industria 3. Strengthening Industry-ac PE-PROCIENCIA-334842-CS-I ademia linkages to accelerat Ejecución pendien NDV / Monitores Financieros IBRD / 93340 Posterior Individual Open - National 192,964.82 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 e technology transfer and sc te para supervisión ience-based business innova tion PE-PROCIENCIA-334892-CS-I 4. Project Management and IBRD / 93340 Posterior Individual Open - National 30,150.75 0.00 En ejecución 2023-07-03 2023-06-21 2023-07-27 2023-08-06 2023-08-30 2024-08-29 NDV / Analista de Evaluación Monitoring & Evaluation PE-PROCIENCIA-334803-CS-I 1: Strengthening SINACTI’s i Ejecución pendien NDV / Monitor Técnico para s IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 15,075.38 0.00 2023-09-01 2023-09-25 2023-10-05 2023-10-29 2024-04-26 te upervisión - Redes de investi o bolster innovation in Peru gación PE-PROCIENCIA-334622-CS-I 1: Strengthening SINACTI’s i NDV / Coordinador en imple Ejecución pendien IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 37,688.44 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 mentación y operación de inf te o bolster innovation in Peru raestructura AWS PE-PROCIENCIA-334807-CS-I 2. Capacity development for Ejecución pendien NDV / Monitores Financieros IBRD / 93340 the generation of knowledge Posterior Individual Open - National 24,120.60 0.00 2023-08-01 2023-08-25 2023-09-04 2023-09-28 2024-09-27 te para supervisión in Strategic Areas PE-PROCIENCIA-335018-CS-I 4. Project Management and Ejecución pendien IBRD / 93340 Posterior Individual Open - National 27,135.68 0.00 2023-12-01 2023-12-25 2024-01-04 2024-01-28 2025-01-27 NDV / Analista de Finanzas Monitoring & Evaluation te PE-PROCIENCIA-364431-CS-I 1: Strengthening SINACTI’s i NDV / Servicio de identificaci IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 25,126.00 0.00 En ejecución 2023-07-03 2023-06-27 2023-08-01 2023-08-11 2023-08-26 2023-11-24 ón, análisis y propuesta meto o bolster innovation in Peru dológica para la priorización de cadenas de valor PE-PROCIENCIA-369588-CS-I 4. Project Management and Ejecución pendien NDV / Especialista en Adquisi IBRD / 93340 Previa Individual Limited 39,200.00 0.00 2023-07-10 2023-07-15 2023-08-05 2023-08-17 2024-08-11 Monitoring & Evaluation te ciones - Subproyectos PE-PROCIENCIA-373212-CS-I 1: Strengthening SINACTI’s i Ejecución pendien NDV / Especialista para la ge IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 21,105.53 0.00 2023-08-07 2023-08-31 2023-09-05 2023-09-16 2024-09-15 te stión de implementación de i o bolster innovation in Peru nteroperabilidad PE-PROCIENCIA-373217-CS-I 1: Strengthening SINACTI’s i NDV / Apoyo en Recopilación, Ejecución pendien IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 9,648.00 0.00 2023-08-14 2023-09-07 2023-09-17 2023-10-02 2024-10-01 Procesamiento y Registro de te o bolster innovation in Peru Información en CTI PE-PROCIENCIA-334621-CS-I 1: Strengthening SINACTI’s i NDV / Especialista en soporte IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 30,150.76 0.00 Cancelado 2023-03-15 2023-03-06 2023-04-08 2023-05-17 2023-04-18 2023-05-12 2024-05-11 funcional y técnico para los d o bolster innovation in Peru irectorios y plataformas de C TI Page 6 PE-PROCIENCIA-373219-CS-I 1: Strengthening SINACTI’s i NDV / Apoyo en soporte funci Ejecución pendien IBRD / 93340 nstitutions and governance t Posterior Individual Open - National 30,150.76 0.00 2023-08-14 2023-09-12 2023-09-22 2023-10-05 2024-10-04 onal y técnico para los direct te o bolster innovation in Peru orios y plataformas de CTI Page 7