PROCUREMENT PLAN Project information: Country: The People’s Republic of China Project name: World Bank loan China Plastic Waste Reduction Project- Chongqing sub-project P-number: P174267 Project Implementation agency: Chongqing Municipal PMO Chongqing Environment Sanitation Group Wulong District Construction Investment Group Co., Ltd. Chongqing Nanzhou Urban Management Co. Ltd, Date of the Procurement Plan: May 14, 2021 Period covered by this Procurement Plan: 2021-2026 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” dated November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. A. The Bank’s Standard Procurement Documents (SPDs): The Bank’s SPDs shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. B. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures (Tendering and Bidding Law of the Peoples’ Republic of China, i.e. TBL promulgated by its Order No. 21 dated August 30, 1999 and the Implementation Regulations of the TBL promulgated by its State Council Order No. 613 dated November 30, 2011 and any amendments thereof) may be used with the following conditions to meet the requirements for open competitive procurement of paragraph 5.4 of the Procurement Regulations: a. All procurement notices shall be published in a national newspaper of wide circulation, or on a widely-used website / electronic portal with free access. b. A minimum of twenty (20) business days shall be given to Bidders between the date of such advertisement (or the date of availability of procurement documents, whichever is later and the deadline for the submission of bids). The advertisement and procurement documents shall specify the deadline for the submission of bids. Potential Bidders shall be allowed to inspect and purchase procurement documents at any time prior to the deadline for the submission of bids. c. Any Bidder/Consultant should be eligible to participate in a procurement process and to be awarded a Bank-financed contract as defined in paragraphs 3.21, 3.22 and 3.23 of the Procurement Regulations. d. Bidders/Consultants shall be allowed to submit bids/proposals by mail or in person. Bidders/consultants shall not be mandatory required to be present at the bid/proposal opening session. e. Bidders should not be required to register as a condition for inspecting or purchasing procurement documents, submitting its bid or receiving contract award. A winner Bidder, shall be given reasonable opportunity of registering (if required) before contract signing without any let or hindrance. Bidding shall not be restricted to any class of contractors. f. The winning bidder shall not be required, as a condition of award, to reduce its bid price No contract negotiation shall be permitted unless agreed in the procurement plan. g. No bid may be rejected solely on the basis that the bid price exceeds any cost estimate. Rejection of all bids or re-bidding shall not be allowed solely because the number of bids is less than three (3). Rebidding shall not take place without any sound justification. h. The Bank’s procurement documents for approaching the national market or any procurement document acceptable to the Bank shall be used. All procurement documents must require that bidders/consultants present a signed acceptance at the time of bidding or submitting a proposal, to be incorporated in any resulting contract, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i. The procurement documents shall disclose the newspaper and / or the electronic means in which the information on contract award shall be published. j. The contract award notification shall identify: (a) name and address of the Borrower’s Project Implementing Unit, (b) name and reference number of the contract being awarded and the selection method used (c) names of all Bidders/Consultants that submitted bids/proposals and their prices as read out at the bid opening meeting and as evaluated (d) names of all Bidders/ Consultants whose bids/proposals were rejected either as nonresponsive or as not meeting qualification criteria or were not evaluated, with the reasons therefor and (e) the name of the successful Bidder/Consultant, the final contract price, the contract duration and a summary of its scope. k. The Borrower shall implement an effective complaint mechanism allowing bidders or consultants to complain, and have their complaints handled and responded in a timely manner. Procurement documents should indicate the complaint mechanism procedure and provide the professional title and address of the officials to whom such protests should be sent. l. The Bank shall be allowed to review procurement documentation and activities related to the activities included in the procurement plan. C. Other national procurement arrangements: When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. D. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing is not applicable for those contracts identified in the Procurement Plan tables. E. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations is not applicable. F. Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations: Goods: Domestic Preference is applicable for those contracts identified in the Procurement Plan tables. Works: Domestic Preference is not applicable for those contracts identified in the Procurement Plan tables. G. Other Relevant Procurement Information: Prior Review Threshold: The thresholds of procurement methods and the requirements for the Bank’s prior review are shown in Table1. Table1. Thresholds for Procurement Methods and Prior Review Expenditure Contract Value Procurement Prior Review Category Threshold (US$) Method Threshold (US$) 1. Civil works ≥40,000,000 International Open All contracts Competitive Procurement (International + Open) National Open ≥ 500k to Competitive All contracts ≥15 <40,000,000 Procurement million (National + Open) Request for <500,000 N/A Quotations All contracts ≥15 Any value Direct Selection million International Open Competitive ≥10,000,000 Procurement All contracts (International + Open) National Open 2. Goods/Non- ≥ 500k to Competitive All contracts ≥4 consulting services <10,000,000 Procurement million (National + Open) Request for <500,000 N/A Quotations All contracts ≥4 Any value Direct Selection million Currency Unit = Chinese Yuan (CNY) US$1.00 = CNY 6.5 Procurement Packages with Methods and Time Schedule: Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN PIU 1: Chongqing Environment and Sanitation Group (ESG) Jieshi secondary sorting & transfer station expansion - Road, 8839m2; Civil Engineering greening, ESG- Open, 2021-09- 2021-11- 2021- 1 Works 100% for kitchen waste 18835m2; station 3280 504.6 RFB Post 12 No   W-1 National 20 01 12-01 separation wall (with gate), workshop, parking 966m lot and general layout Recyclables sorting unit, Jieshi secondary 14400m2; 1# sorting & transfer storage, 2700m2; station expansion - 2# storage, Recyclable sorting 1600m2; ESG- workshop, Open, 2023-08- 2023-10- 2023- 2 Works 100% wastewater 5112 786.5 RFB Post 24 No   W-2 warehouse, National 20 01 12-01 reclamation and equipment reuse system, infrastructure and 200m2 other ancillary plant base facilities preparing and processing Xiajiaba secondary sorting & transfer station expansion – Move and rebuild ESG- Civil Engineering Open, 2021-09- 2021-11- 2021- 3 Works 100% open channel RFB Post 12 No   W-3 for kitchen waste 1452 223.38 National 20 01 12-01 inside the station sorting workshop, parking lot and general layout Xiajiaba secondary sorting & transfer road, 12500m2; greening, ESG- station expansion Open, 2023-09- 2023-10- 2023- 4 Works 100% Civil Engineering 8400m2  5248 807.4 RFB Post 24 No   W-4 National 20 01 12-01 wall/fence (with Bidding for high gates), 850m; value recycling workshop, Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN sanitation vehicle maintenance base, return water system, etc. Warehouse, 1776m2; bulky wastes crushing plant, 875m2; Zouma secondary Raw material sorting & transfer storage, 2400m2  station expansion - plastic granulation 2021-09- 2021-11- 2021- kitchen waste plant, 4800m2; ESG- Open, 20 01 12-01 5 Works 100% treatment system, pyrolytic oxidation 5809 893.7 RFB Post 14 No   W-5 National warehouse, large plant of plastic, crushing workshop 11400m2 tank and other civil zone, 648m2; works wastewater treatment unit, 340m2; textile wastes recycling unit, 3600m2 Luoqi low-value recyclables recycling base - Civil works (waste plastics raw materials storehouse, plastic Foam glass granulation manufacture 2021-09- 2021-11- 2021- ESG- workshop, plastic plant, 3600m2; Open, 20 01 12-01 6 Works 100% 9635 1482.3 RFB Post 12 No   W-6 oil cracking glass pre- National workshop, waste processing plant, spinning recycling 924m2 workshop, glass pretreatment workshop, foam glass production workshop and other civil works) Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Urban ship (floating) waste Land area, collection and 6200m2; treatment facilities excavated - Civil earthwork, woks(highway to 841.5m3; tack ESG- Open, 2022-07- 2022-09- 2022- 7 Works 100% riverside, road, filled earthwork, 8364 1286.8 RFB Post 12 No   W-7 National 20 01 12-01 approach bridge, 32430m3; road area, harbor excavated basin, slope earthwork of yard protection, dock basin, ancillary works, 6945.95m3 etc.) Urban ship (floating) waste Collection and collection and transportation treatment facilities ESG-G- system (16 Open, 2023-08- 2023-10- 2023- 8 Goods 100% – collection and 300 46.2 RFQ Post 24 No   1 forklifts16, 2 National 20 01 12-01 transfer equipment loaders 2; 2 (16 forklifts, 2 transfer carts) loaders and 2 transfer trucks) Jieshi secondary sorting & transfer station expansion – Phase II- ‘Two Wastewater ESG-G- network reclamation and Open, 2023-08- 2023-10- 2023- 9 Goods 100% 4631 712.5 RFB Prior 24 No   2 integration’ reuse system National 20 01 12-01 equipment (PP / PE, inside the Base pet, pet reuse water system and supporting system) Jieshi secondary 1. washing tower sorting & transfer of dedusting and ESG-G- station expansion – deodorizing Open, 2023-08- 2023-10- 2023- 10 Goods 100% 1250 192.3 RFB Post 24 No   3 Phase II- system; 2. National 20 01 12-01 deodorization Photocatalytic equipment oxidation unit;3. blowers 4. Plant Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN liquid atomizing system and hydraulic control system; 5. Spray dedusting system; 6. air supply system and axial flow fan Xiajiaba secondary sorting & transfer station expansion – Phase I-main Compactor equipment system, automatic (compactor, system, discharge ESG-G- automatic control Open, 2021-09- 2021-11- 2021- 11 Goods 100% chute for various 3400 523.1 RFB Prior 12 No   4 system, steel National 20 01 12-01 kinds of wastes; structure platform, lifting system and discharge chute, 20 shaped steels waste transfer containers, 10 31- ton transfer vehicles, etc.) Xiajiaba secondary sorting & transfer ESG-G- VI national Open, 2021-09- 2021-11- 2021- 12 Goods 100% station expansion – 270 41.5 RFQ Post 12 No   5 Phase I- standard National 20 01 12-01 6 tractors Xiajiaba secondary sorting & transfer ESG-G- VI national Open, 2021-09- 2021-11- 2021- 13 Goods 100% station expansion – 90 13.8 RFQ Post 12 No   6 standard National 20 01 12-01 Phase I-Six semitrailers Xiajiaba secondary collection and ESG-G- sorting & transfer Open, 2023-09- 2023-10- 2023- 14 Goods 100% station expansion – transportation 450 69.2 RFB Post 24 No   7 National 01 01 12-01 system 16 Phase II Collection forklifts16, 2 and transfer (16 Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN forklifts, 2 loaders, loaders, 5 transfer 5 transfer vehicles, trucks  etc.) 1two-screw conveyer 2Whole bottle pre- washing Xiajiaba secondary machine 3 Color sorting & transfer sorter of whole station expansion – bottle 4. Output Phase II - Two belt conveyor (no ESG-G- network PET bottle) 5. Open, 2023-08- 2023-10- 2023- 15 Goods 100% 5381 827.8 RFB Prior 24 No   8 integration’ Output belt National 20 01 12-01 equipment (PP / PE, conveyor pet, pet reuse (varicolored PET water system and bottle) 6. supporting system) Transparent PET plates washing line; 7. Cleaning line of color PET bottle. 1 washing tower of dedusting and deodorizing system,  2 Xiajiaba secondary Photocatalytic sorting & transfer oxidation unit  2023-09- 2023-10- 2023- station expansion – 3blowers 4. Plant ESG-G- Open, 01 01 12-01 16 Goods 100% Phase II - liquid atomizing 1792 275.7 RFB Post 12 No   9 National system and deodorization hydraulic control equipment system;  6. Spray dedusting system; 7. air supply system and axial flow fan Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Xiajiaba secondary sorting & transfer ESG-G- station expansion – Photometric Open, 2021-09- 2021-11- 2021- 17 Goods 100% 448 68.9 RFB Post 12 No   10 Phase II - equipment National 20 01 12-01 photovoltaic system equipment Zouma secondary 2021-09- 2021-11- 2021- ESG-G- sorting & transfer VI national Open, 20 01 12-01 18 Goods 100% 2286 351.7 NBF Post 14 No   11 station expansion - standard National Phase I-41 tractors Zouma secondary sorting & transfer 2021-09- 2021-11- 2021- ESG-G- VI national Open, 20 01 12-01 19 Goods 100% station expansion - 615 94.6 RFB Post 14 No   12 standard National Phase I-41 semi- trailers Zouma secondary sorting & transfer 2021-09- 2021-11- 2021- ESG-G- Refuse transfer Open, 20 01 12-01 20 Goods 100% station expansion - 1679 258.3 RFB Post 14 No   13 container National Phase I-73 transfer containers Zouma secondary sorting & transfer 2021-09- 2021-11- 2021- ESG-G- Electric forklifts Open, 20 01 12-01 21 Goods 100% station expansion - 368 56.6 RFB Post 14 No   14  2T  National Phase II-2T electric forklift Luoqi low-value 1 single shaft recyclables shredder; 2 2021-09- 2021-11- 2021- ESG-G- recycling base- butterfly screw Open, 20 01 12-01 22 Goods 100% 1015 156.2 RFB Post 14 No   15 plastic cleaning mud press; 3 National and granulation crusher  4 equipment granulators Complete set of 2021-09- 2021-11- 2021- Luoqi low-value ESG-G- optical separation Open, 20 01 12-01 23 Goods 100% recyclables 572 88.0 RFB Post 12 No   16 equipment; National recycling base- broken glass waste glass zigzag screening Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN pretreatment machine; Eddy equipment current separator; injection screw air compressor; relaxation vibrating screen; natural gas burner Luoqi low-value recyclables 2021-09- 2021-11- 2021- ESG-G- Foam glass Open, 20 01 12-01 24 Goods 100% recycling base- 1650 253.8 RFB Post 12 No   17 production National Foam glass production Photometric sorter; Air pressure device; Co rotating Luoqi low-value parallel two-way recyclables screw extruder; 2021-09- 2021-11- 2021- ESG-G- recycling base- Biaxial shear Open, 20 01 12-01 25 Goods 100% 1802.5 277.3 RFB Post 12 No   18 waste textile crusher; National recycling pelletizer; equipment Loosening machine; carding machine; acupuncture machine 1. automatic compression box; 2. Steel mesh Urban ship framework plastic (floating) waste composite pipe; 3. collection and 2021-09- 2021-11- 2021- Steel mesh ESG-G- treatment facilities Open, 20 01 12-01 26 Goods 100% framework plastic 946 145.5 RFB Post 12 No   19 -mechanical National composite pipe; 4. equipment (oil spill Plastic coated storage tanks and composite steel garbage cans) pipe; 5. plastic coated composite steel pipe Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Information 2022-09- 2022-11- 2022- ESG-G- ESG Information system related Open, 20 01 12-01 27 Goods 100% 4858 747.4 RFB Prior 12 No   20 system equipment and National components, etc. Liquid chromatography, inductively coupled plasma 2022-09- 2022-11- 2022- ESG Monitoring and atomic mass ESG-G- Open, 20 01 12-01 28 Goods 100% Experimental spectrometry, 762 117.2 RFB Post 12 No   21 National Center residual carbon determination of oil and other laboratory equipment PIU 2: Wulong Dev Investment Group (WL) Construction of Wulong district municipal solid Construction of waste transfer Wulong District station project, WL-W- Open, 2022-09- 2022/10/ 2022/11/ 1 Works 100% Municipal Solid including 3821 588 RFB Post 24 No   1 National 01 11 10 Waste Transfer construction, Station installation, general drawing, equipment procurement Construction of Wulong District West Area MSW Construction of Transfer Station domestic garbage WL-W- Project, including Open, 2023-09- 2023-11- 2023/12/ 2 Works 100% transfer station in 3749 577 RFB Post 18 No   2 construction, National 01 01 1 the west of Wulong installation, District general drawing and equipment procurement Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Construction of Wulong District MSW collection and transfer system and Construction of intelligent domestic garbage dispatch center collection and project, including WL-W- Open, 2022-02- 2022-04- 3 Works 100% transfer system construction 1656 255 RFB Post 2022/5/1 24 No   3 National 01 01 and command and project, dispatch center in decoration Wulong District project, installation project, general drawing project and equipment procurement Wulong District MSW Landfill closure, including Wulong District civil engineering, WL-W- Municipal Solid installation Open, 2022-02- 2022-04- 2022- 4 Works 100% 2310 355 RFB Post 12 No   4 Waste Landfill engineering, National 01 01 05-01 closure general drawing engineering and equipment engineering Construction of Wulong district kitchen waste harmless disposal Construction of plant project, harmless disposal including WL-W- Open, 2023-07- 2023-09- 2023/9/3 5 Works 100% plant for kitchen construction 3737 575 RFB Post 24 No   5 National 01 01 0 waste in Wulong project, District installation project, general drawing project, equipment procurement Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Purchase garbage Wulong District sorting collection household garbage WL-G- bucket, intelligent Open, 2021-10- 2021-12- 2022- 6 goods 100% collection system 1512 233 RFB Post 18 No   1 buried sorting National 01 01 01-05 equipment collection box and procurement other equipment Wulong District Buy machine WL-G- MSW Transfer sweeper, garbage Open, 2021-10- 2021-12- 2022- 7 goods 100% 2174 334 RFB Post 18 No   2 System Equipment truck and other National 01 01 01-05 Purchase equipment PIU3: Chongqing Nanzhou Urban Management Service Co Ltd (QJ) Construction of Qijiang District waste secondary transfer station project, including Construction of construction secondary refuse Open, 2021-12- 2022-1- 2022-2- 1 QJ-W-1 Works 100% engineering, 5769 888 RFB Post 9 No   transfer station in National 1 11 11 installation Qijiang District engineering, general layout engineering, equipment procurement The construction of Yongxin waste transfer station includes construction Construction of engineering, Open, 2021-10- 2021-12- 2022-1- 2 QJ-W-2 Works 100% Yongxin refuse 881 136 RFB Post 9 No   installation National 1 11 11 transfer station engineering, general layout engineering and equipment procurement Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Construction of Hengshan, Yongcheng and Construction of Guofu waste waste transfer transfer stations, stations in Open, 2021-12- 2022-1- 2022-2- 3 QJ-W-3 Works 100% including 2661 409 RFB Post 9 No   Hengshan, National 1 11 11 construction, Yongcheng and installation, Guofu general layout and equipment procurement The construction of Shihao, Anshan, and Qushui refuse Construction of transfer stations Shihao, Anshan, Open, 2021-12- 2022-1- 2022-2- 4 QJ-W-4 Works 100% includes 2854 439 RFB Post 9 No   and Qushui refuse National 1 11 11 construction, transfer station installation, general layout, and equipment procurement The construction of Qijiang large waste dismantling station includes construction Construction of engineering, Open, 2022-10- 2022- 5 QJ-W-5 Works 100% large waste 756 116 RFB Post 2022-9-1 9 No   installation National 11 11-11 dismantling station engineering, general layout engineering and equipment procurement Civil engineering of Civil engineering domestic waste Open, 2022-8- 2022-9- 6 QJ-W-6 Works 100% of waste sorting 1267 195 RFB Post 2022-7-1 9 No   sorting collection National 11 11 collection point point Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Procurement of Procurement of Open, 2022-10- 2022-11- 2022- 7 QJ-G-1 Goods 100% 1910 294 RFB Post 3 No   waste sorting bins waste sorting bins National 1 11 12-11 Domestic waste Procurement of classification domestic waste Open, 2022-10- 2022-11- 2022- 8 QJ-G-2 Goods 100% information classification 243 37 RFQ Post 3 No   National 1 11 12-11 platform information procurement platform Reconstruction and Purchase and expansion of the installation of new Open, 2022-8- 2022-9- 9 QJ-G-3 Goods 100% original garbage equipment in 1184 182 RFB Post 2022-7-1 6 No   National 11 11 collection station in garbage collection 30 towns station Prior Review Threshold: The thresholds of procurement methods and the requirements for the Bank’s prior review are shown in Table2 according to the Procurement Regulations dated November 2020. Table 2. Thresholds for Procurement Methods and Prior Review Contract Expenditure Value Procurement Prior Review Category Threshold Method Threshold (US$) (US$) QCBS/QBS/LCS/FB ≥300,000 All contracts ≥2 S million <300,000 FBS, LCS, CQS Direct Selection All contracts ≥1 for firms million Consultant Services Selection of All contracts Individual ≥400,000 Consultant Direct Selection for All contacts ≥ individuels 400,000 Notes: QCBS: Quality- and Cost-Based DS: Direct Selection Selection IC: Individual Consultant QBS: Quality-Based Selection selection FBS: Fixed Budget Selection N/A: Not Applicable LCS: Least Cost Selection CQS: Consultants’ Qualifications-based Selection Currency Unit = Chinese Yuan (CNY) US$1.00 = CNY 6.5 Procurement Packages with Methods and Time Schedule: Revi Estima ew Expecte Expect Sour Contra Estimat ted Selecti d Date Contra Procure ce of Procurem by ed Bid ct Advance S/ Ref. ed Cost Cost on WB of ct ment Fund Contract Name Main Activities ent Openi Period Contract Remarks N No. (CNY: (USD: Metho Publicat Signin Category s Method (Prio ng (Mont ing 10,000) 10,000 d r/ ion of g Date (WB) Date h) ) SPN Post) PIU 1: Chongqing Environment and Sanitation Group (ESG) Make research and study to propose Research on the fiscal policy ESG-T- Consulting 100 and tax incentive policy recommendations Open, 2022- 2022- 1 75 11.5 CQS Post 2022-9-1 36 No   1 services % of low value recyclables for fiscal and tax National 10-11 11-11 in Chongqing incentive of low value recyclables in Chongqing Research and Study to propose policy Research on the system recommendation for ESG-T- Consulting 100 of charge-by-quantity charging system Open, 2021-12- 2022- 2022- 2 75 11.5 CQS Post 48 No   2 services % for household solid based on quantity of National 01 01-11 01-31 wastes wastes yield for household solid wastes Make research and studies to propose analytical results on Research on new green various materials, materials, new technologies, ESG-T- Consulting 100 Open, 2023-12- 2024- 2024- 3 technology, new processes and 75 11.5 CQS Post 36 No   3 services % National 01 01-11 02-01 process and new equipment of equipment of plastics plastics; and to propose recommendation inventories. Study on Preparation Research and study and accelerated to development a ESG-T- Consulting 100 degradation of heat Open, 2021-12- 2022- 2022- 4 new kind of 75 11.5 CQS Post 48 No   4 services % resistant polylactide National 01 01-11 02-11 polylactide for lunch based disposable lunch box products box Revi Estima ew Expecte Expect Sour Contra Estimat ted Selecti by d Date Contra Procure ce of Procurem ed Bid ct Advance S/ Ref. ed Cost Cost on WB of ct ment Fund Contract Name Main Activities ent Openi Period Contract Remarks N No. (CNY: (USD: Metho Publicat Signin Category s Method (Prio ng (Mont ing 10,000) 10,000 d r/ ion of g Date (WB) Date h) ) SPN Post) Make studies to propose paths and Implementation path draft technical and technical guidelines guidelines for ESG-T- Consulting 100 for comprehensive Open, 2021-09- 2021- 2021- 5 comprehensive 100 15.4 CQS Post 24 No   5 services % utilization of domestic National 20 11-01 12-01 utilization of waste (plastic) domestic waste resources in Chongqing (plastic) resources in Chongqing Public awareness by media, advertisement, and door-to-door publicity to various Publicity and training units (communities, ESG-T- 100 for capacity building institutions and so Trainin 6 Training 200 30.8 N/A N/A N/A N/A N/A 72 No   6 % MSW segregation and on); training of g/SOE recycling - city proper relevant personnel, to strengthen the capacity for ensuring the MSW front-end segregation in city proper PIU 2: Wulong Dev Investment Group (WL) Public awareness by media, advertisement, and door-to-door Publicity and training publicity to various 100 for capacity building Trainin 1 WL-T-1 Training units (communities, 400 61 N/A N/A N/A N/A N/A 72 No   % MSW segregation and g/SOE institutions and so recycling - Wulong on); training of relevant personnel, to strengthen the capacity for ensuring the MSW front-end Revi Estima ew Expecte Expect Sour Contra Estimat ted Selecti by d Date Contra Procure ce of Procurem ed Bid ct Advance S/ Ref. ed Cost Cost on WB of ct ment Fund Contract Name Main Activities ent Openi Period Contract Remarks N No. (CNY: (USD: Metho Publicat Signin Category s Method (Prio ng (Mont ing 10,000) 10,000 d r/ ion of g Date (WB) Date h) ) SPN Post) segregation in Wulong District Research and study; policy work; Improvement of information system Open, Consulting 100 agricultural mulching to improve the 2021- 2021- 2 WL-T-2 300 46 QCBS Internation Post 2021-9-1 72 No   services % film recycling and reuse agricultural mulching 10-11 11-11 al system - Wulong film recycling and reuse system in Wulong District Research and study; policy work; Qijiang Integrated information system Open, Consulting 100 Urban-rural MSW 2021- 2021- 3 WL-T-3 to improve the 352 54 QCBS Internation Post 2021-9-1 72 No   services % management system 10-11 11-11 integrated urban- al Improvement rural management system in Wulong Research on whole Research and study process information to propose a set of Consulting 100 Open, 2021- 2021- 4 WL-T-4 management system of methods for whole- 75 12 CQS Post 2021-9-1 72 No   services % National 10-11 11-11 MSW (including plastic process information wastes) system construction Make research and study to propose Study on the system policy and mechanism of recommendations Consulting 100 recycling and utilization for the system and Open, 2021- 2021- 5 WL-T-5 75 12 CQS Post 2021-9-1 72 No   services % of plastic pesticide mechanism of National 10-11 11-11 packaging waste in recycling and Chongqing utilization of plastic pesticide packaging waste in Chongqing Subto         1202 185                   tal Revi Estima ew Expecte Expect Sour Contra Estimat ted Selecti by d Date Contra Procure ce of Procurem ed Bid ct Advance S/ Ref. ed Cost Cost on WB of ct ment Fund Contract Name Main Activities ent Openi Period Contract Remarks N No. (CNY: (USD: Metho Publicat Signin Category s Method (Prio ng (Mont ing 10,000) 10,000 d r/ ion of g Date (WB) Date h) ) SPN Post) PIU3: Chongqing Nanzhou Urban Management Service Co Ltd (QJ) Public awareness by media, advertisement, and door-to-door publicity to various Publicity and training units (communities, 100 for capacity building institutions and so Trainin 1 QJ-T-1 Training 600 92 N/A N/A N/A N/A N/A 72 No   % MSW segregation and on); training of g/SOE recycling - Qijiang relevant personnel, to strengthen the capacity for ensuring the MSW front-end segregation in Qijiang District Research and study; policy work; Qijiang Integrated information system Open, Consulting 100 Urban-rural MSW to improve the 2021- 2021- 2 QJ-T-2 266 41 QCBS Internation Post 2021-9-1 72 No   services % management system integrated urban- 10-11 11-11 al Improvement rural management system in Qijiang District Consulting Improvement of Research and study; Open, 100 2021- 2021- 3 QJ-T-3 services, agricultural film policy work; 400 62 QCBS Internation Post 2021-9-1 72 No   % 10-11 11-11 training recycling capacity information system al Study on the management system of Research and study; Consulting 100 Open, 2021- 2021- 4 QJ-T-4 rural waste agricultural policy work; 75 12 CQS post 2021-9-1 72 No   services % National 10-11 11-11 film recycling and information system resource utilization Study on MSW Make research and Consulting 100 study to propose Open, 2021- 2021- 5 QJ-T-5 segregation system in 75 12 CQS post 2021-9-1 72 No   services % National 10-11 11-11 Chongqing policy recommendations Revi Estima ew Expecte Expect Sour Contra Estimat ted Selecti by d Date Contra Procure ce of Procurem ed Bid ct Advance S/ Ref. ed Cost Cost on WB of ct ment Fund Contract Name Main Activities ent Openi Period Contract Remarks N No. (CNY: (USD: Metho Publicat Signin Category s Method (Prio ng (Mont ing 10,000) 10,000 d r/ ion of g Date (WB) Date h) ) SPN Post) for MSW segregation system in Chongqing CPMO contract management, financial management and audit, environment Open, Consulting 100 Project management 2021- 2021- 1 PM-T-1 management, 2259 347.54 QCBS internation Prior 2021-9-1 72 No services % consulting service 10-11 11-11 technical design & al BD review, including project performance evaluation & results of promotion Construction Construction Open, Consulting 100 supervision 2021- 2021- 2 PM-T-2 supervision consulting 3000 461.59 QCBS internation Prior 2021-9-1 72 No services % consulting service 10-11 11-11 service al Municipality for all projects level comprehens Social assessment, Social assessment, Consulting 100 Open, 2021- 2021- ive 3 PM-T-3 resettlement external resettlement 100 15.38 CQS Post 2021-9-1 72 No services % National 10-11 11-11 arrangemen monitoring external monitoring t Incremental Operating Costs for CQPMO, Wulong PMO and Qijiang PMO, PIUs & Training and workshops for plastic Incremental Operating 100 wastes reduction to Trainin 4 PM-T-4 Training Costs (Training, 200 30.77 N/A N/A N/A N/A N/A 72 No % enhance the g/SOE Workshops, Etc.) institutional capacity in the Districts for implementing municipal solid wastes sorting and management PROCUREMENT China : China Plastic Waste Reduction Project PLAN General Information Country: China 2023-03-16 Bank’s Approval Date of the Original Procurement Plan: 2023-07-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174267 GPN Date: 2021-07-23 Project Name: China Plastic Waste Reduction Project Loan / Credit No: IBRD / 92640 Chongqing Plastic Waste Reduction project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CN-CHONGQING-(PM-T-1)-Q CBS / contract management,f inancial management and au Component 1 National Polici Quality And Cost- Open - Internationa dit, environment manageme IBRD / 92640 es and Institution Strengthe Prior 2,950,000.00 0.00 Under Review 2023-03-10 2023-04-02 2023-03-31 2023-04-29 2023-05-27 2023-06-11 2023-07-16 2023-08-20 2029-03-31 Based Selection l nt, technical design & BD rev ning iew,including project perform ance evaluation &results of p romotion PM-T-3 / External monitoring Component 1 National Polici Quality And Cost- and evaluation of social perfo IBRD / 92640 es and Institution Strengthe Post Open - National 215,000.00 0.00 Canceled 2023-05-15 2023-06-05 2023-07-19 2023-08-16 2023-09-15 2023-10-20 2023-11-24 2024-11-23 Based Selection rmance consulting services ning INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1