PROCUREMENT PLAN (Textual Part) Project information: Romania Safer, Inclusive and Sustainable Schools Project (P175308) Project Implementation agency: Ministry of Education through Project Management Unit Date of the Procurement Plan: January 31, 2022 Period covered by this Procurement Plan: February 15, 2022- June 30, 2027 Preamble Applicable procurement arrangements: Procurement under the Project will be carried out in accordance with the World Bank Procurement Regulations for IPF Borrowers: Procurement in Investment Project Financing of Goods, Works, Non-Consulting and Consulting Services (Fourth Edition, November 2020), (hereinafter referred to as “Procurement Regulations”), and with the latest “Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants”. In accordance with paragraph 5.9 of the “Procurement Regulations the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. As part of project preparations and negotiations, it has been agreed that the Bank’s Standard Procurement Documents or other documents agreed with the Bank will be used for procurement with national market approach. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets- Not Applicable Procurement of Second-Hand Goods- Not Applicable Other procurement arrangements: The project provides for a Contingent Emergency Response Component (CERC) which is an ex-ante mechanism available to the Government for rapid access to financing to respond to an eligible crisis or emergency. Procurement arrangements under CERC will be streamlined and will be described in the Project Procurement Strategy for Development and CERC Annex to the Project Operations Manual to be developed by the PMU. Thresholds: Procurement Types, Method and Prior Review Thresholds Type of Method Threshold Prior Review Procurement (US$, millions) Threshold Works (including Open International > All contracts more Turnkey, Supply & 20 than US$10 million Installation of Plant equivalent and equipment, Open National < 20 and PPP) National Request for Quotation < 0.2 Goods, Information Open International > 2 All contracts more technology and than US$2 million Non-Consulting Open National < 2 equivalent Services National Request for Quotation < 0.1 Consulting firms Selection Based on All contracts more Consultants’ than US$1 million Qualifications < 0.3 equivalent Least Cost Selection and Fixed Budget Selection - in justified cases Quality- and Cost- based Selection and Quality-based Selection - in all other packages National market approach (As per paragraph 7.25 of the Procurement Regulations) < 0.5 Consulting - No threshold All contracts more individuals than US$300,000 equivalent Direct selection No threshold With prior agreement based on justification: • For goods/works/non- consulting services: As per paragraphs 6.8– 6.10 of the Procurement Regulations. • For consultants: As per paragraphs 7.13–7.15 of the Procurement Regulations. Note: The above thresholds are for the initial 18-month implementation period. Based on the procurement performance of the Project, these thresholds may be subsequently modified. PROCUREMENT Romania : Romania Safer, Inclusive and Sustainable Schools PLAN General Information Country: Romania Bank’s Approval Date of the Original Procurement Plan: 2022-01-31 Revised Plan Date(s): (comma delineated, leave blank if 2023-07-25 none) Project ID: P175308 GPN Date: 2022-02-03 Project Name: Romania Safer, Inclusive and Sustainable Schools Loan / Credit No: IBRD / 92360 Ministry of Education -School and University Network Rehabilitation Project Management Unit Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure RO-ME-SUNRPMU-270308-C ment Document - Integrated Investments in Sc Single Stage - One E Pending Imp 2024-10-0 W-RFB / Construction works f IBRD / 92360 Post Request for Bids Open - National 1 Envelope proce 1,227,504.52 0.00 2023-05-15 2023-05-20 2023-06-19 2023-07-19 2023-08-12 hool Infrastructure nvelope lementation 5 or 1 school in Vaslui County ss (Non Bank-SPD ) National Procure RO-ME-SUNRPMU-270309-C ment Document - Integrated Investments in Sc Single Stage - One E Pending Imp 2023-09-2 W-RFB / Construction works f IBRD / 92360 Post Request for Bids Open - National 1 Envelope proce 2,541,453.01 0.00 2023-05-15 2023-05-20 2023-06-19 2023-07-19 2023-08-12 hool Infrastructure nvelope lementation 1 or 1 school (monument) in V ss (Non Bank-SPD aslui County ) National Procure RO-ME-SUNRPMU-270307-C ment Document - Integrated Investments in Sc Single Stage - One E Pending Imp 2025-02-0 W-RFB / Construction works f IBRD / 92360 Post Request for Bids Open - National 1 Envelope proce 3,682,513.55 0.00 2023-09-15 2023-09-20 2023-10-20 2023-11-19 2023-12-13 hool Infrastructure nvelope lementation 5 or 3 schools in Bucharest Mu ss (Non Bank-SPD nicipality ) National Procure RO-ME-SUNRPMU-270306-C ment Document - Integrated Investments in Sc Single Stage - One E Pending Imp 2025-02-0 W-RFB / Construction works f IBRD / 92360 Post Request for Bids Open - National 1 Envelope proce 6,137,522.58 0.00 2023-09-15 2023-09-20 2023-10-20 2023-11-19 2023-12-13 hool Infrastructure nvelope lementation 5 or 5 schools situated in Ilfov ss (Non Bank-SPD County ) National Procure RO-ME-SUNRPMU-270305-C ment Document - Integrated Investments in Sc Single Stage - One E Pending Imp 2024-10-0 W-RFB / Construction works f IBRD / 92360 Post Request for Bids Open - National 1 Envelope proce 3,682,513.55 0.00 2023-05-15 2023-05-20 2023-06-19 2023-07-19 2023-08-12 hool Infrastructure nvelope lementation 5 or 3 schools situated in Iasi C ss (Non Bank-SPD ounty ) National Procure RO-ME-SUNRPMU-270301-C ment Document - W-RFB / Construction works f Integrated Investments in Sc Single Stage - One E Pending Imp 2024-10-0 IBRD / 92360 Post Request for Bids Open - National 1 Envelope proce 3,682,513.55 0.00 2023-05-15 2023-05-20 2023-06-19 2023-07-19 2023-08-12 or 3 schools situated in Galat hool Infrastructure nvelope lementation 5 ss (Non Bank-SPD i and Vrancea County ) National Procure RO-ME-SUNRPMU-270302-C ment Document - W-RFB / Construction works f Integrated Investments in Sc Single Stage - One E Pending Imp 2025-02-0 IBRD / 92360 Post Request for Bids Open - National 1 Envelope proce 4,910,018.06 0.00 2023-09-15 2023-09-20 2023-10-20 2023-11-19 2023-12-13 or 4 schools situated in Giurg hool Infrastructure nvelope lementation 5 ss (Non Bank-SPD iu and Teleorman County ) National Procure RO-ME-SUNRPMU-270304-C ment Document - Integrated Investments in Sc Single Stage - One E Pending Imp 2024-10-0 W-RFB / Construction works f IBRD / 92360 Post Request for Bids Open - National 1 Envelope proce 3,682,513.55 0.00 2023-05-15 2023-05-20 2023-06-19 2023-07-19 2023-08-12 hool Infrastructure nvelope lementation 5 or 3 schools situated in Iasi C ss (Non Bank-SPD ounty ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RO-ME-SUNRPMU-275410-G Single Stage - One E IBRD / 92360 Project Management Post Request for Bids Open - National 148,750.00 0.00 Canceled 2022-04-15 2022-04-20 2022-05-20 2022-06-09 2022-07-03 2022-12-30 O-RFB / PMU vehicles nvelope RO-ME-SUNRPMU-275407-G Request for Quota Single Stage - One E Pending Impl IBRD / 92360 Project Management Post Open - National 10,375.00 0.00 2023-03-03 2023-04-13 2023-06-12 O-RFQ / Office furniture for P tions nvelope ementation MU RO-ME-SUNRPMU-275408-G Request for Quota Single Stage - One E IBRD / 92360 Project Management Post Open - National 99,000.00 0.00 Completed 2023-03-28 2023-05-05 2023-04-26 2023-08-03 O-RFB / IT equipment for PM tions nvelope U RO-ME-SUNRPMU-276159-G Single Stage - One E Pending Impl O-RFB / Development of an I IBRD / 92360 Project Management Post Request for Bids Open - National 576,293.20 0.00 2023-12-04 2023-12-09 2024-01-08 2024-01-23 2024-02-16 2024-08-14 nvelope ementation nformatic system RO-ME-SUNRPMU-268777-G O-RFB / Procurement of Tem Integrated Investments in Sc Single Stage - One E IBRD / 92360 Post Request for Bids Open - National 749,180.00 0.00 Canceled 2023-07-03 2023-07-03 2023-08-02 2023-08-17 2023-09-14 2023-12-13 porary Facilities - mobile clas hool Infrastructure nvelope srooms for students G/SISSP/RFQ/01/2022 / 2 Ve Request for Quota Single Stage - One E Pending Impl IBRD / 92360 Project Management Post Open - National 59,500.00 0.00 2023-06-03 2023-07-15 2024-01-11 hicles for PMU staff tions nvelope ementation G/SISSP/RFB/03/2023 / Procu Integrated Investments in Sc Open - Internationa Single Stage - One E Pending Impl rement of Temporary Faciliti IBRD / 92360 Prior Request for Bids 9,000,000.00 0.00 2023-07-28 2023-08-02 2023-09-13 2023-10-13 2023-11-06 2024-10-31 hool Infrastructure l nvelope ementation es - mobile classrooms for st udents NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RO-ME-SUNRPMU-275411-N Request for Quota Single Stage - One E Under Imple IBRD / 92360 Project Management Post Open - National 16,350.00 0.00 2023-07-13 2023-09-01 2027-05-31 C-RFQ / Translation services tions nvelope mentation CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RO-ME-SUNRPMU-269979-C S-QCBS / Consultancy service Integrated Investments in Sc Quality And Cost- IBRD / 92360 Post Open - National 352,345.66 0.00 Signed 2022-02-15 2022-03-16 2022-03-08 2022-04-03 2022-07-25 2022-05-01 2022-09-30 2022-05-16 2022-11-28 2022-05-21 2023-01-27 2022-06-18 2023-02-14 2023-11-10 s for A&E design for 2 school hool Infrastructure Based Selection s situated in Vaslui County Page 1 RO-ME-SUNRPMU-269973-C S-QCBS / Consultancy service Integrated Investments in Sc Quality And Cost- IBRD / 92360 Post Open - National 294,601.08 0.00 Signed 2022-02-16 2022-03-14 2022-03-09 2022-04-04 2022-07-22 2022-05-02 2022-09-19 2022-05-17 2022-12-16 2022-05-22 2023-01-27 2022-06-19 2023-02-14 2023-11-11 s for A&E design for 3 school hool Infrastructure Based Selection s situated in Iasi County RO-ME-SUNRPMU-269978-C S-QCBS / Consultancy service Integrated Investments in Sc Quality And Cost- IBRD / 92360 Post Open - National 294,601.08 0.00 Canceled 2022-02-16 2022-03-14 2022-03-09 2022-04-04 2022-05-02 2022-05-17 2022-05-22 2022-06-19 2023-11-11 s for A&E design for 3 school hool Infrastructure Based Selection s situated in Bucharest Munic ipality RO-ME-SUNRPMU-269970-C S-QCBS / Consultancy service Integrated Investments in Sc Quality And Cost- IBRD / 92360 Post Open - National 294,601.08 0.00 Signed 2022-02-16 2022-03-14 2022-03-09 2022-04-04 2022-07-22 2022-05-02 2022-09-19 2022-05-17 2022-12-09 2022-05-22 2023-01-27 2022-06-19 2023-02-14 2023-11-11 s for A&E design for 3 school hool Infrastructure Based Selection s situated in Iasi County RO-ME-SUNRPMU-276090-C S-CQS / Consultancy services Integrated Investments in Sc Consultant Qualifi IBRD / 92360 Post Open - National 15,833.66 0.00 Canceled 2022-02-15 2022-03-08 2022-03-18 2022-04-02 2022-04-26 2022-06-25 technical surveys for 1 scho hool Infrastructure cation Selection ol located in Vaslui County RO-ME-SUNRPMU-311545-C S-QCBS / Consultancy service Integrated Investments in Sc Quality And Cost- s for A&E design for School n IBRD / 92360 Post Open - National 98,200.36 0.00 Canceled 2022-08-24 2022-08-24 2022-09-14 2022-09-24 2022-11-08 2022-12-08 2022-12-13 2023-01-10 2024-06-03 hool Infrastructure Based Selection o 167 situated in Bucharest Municipality package S/SISSP /QCBS/08/2022 RO-ME-SUNRPMU-326020-C S-QCBS / Consultancy service s for A&E design for School n Integrated Investments in Sc Quality And Cost- IBRD / 92360 Post Open - National 196,400.72 0.00 Canceled 2022-11-15 2022-11-14 2022-12-06 2022-12-16 2023-01-30 2023-03-01 2023-03-06 2023-04-03 2024-08-25 o 168 (9 Alizeului Street and hool Infrastructure Based Selection 7 Giulesti Street) situated in Bucharest Municipality packa ge S/SISSP/QCBS/09/2022 RO-ME-SUNRPMU-270289-C S-CQS / Consultancy services Integrated Investments in Sc Consultant Qualifi Pending Impleme IBRD / 92360 Post Open - National 75,082.36 0.00 2023-05-15 2023-05-30 2023-06-18 2023-06-23 2023-07-17 2024-09-09 for site supervision for 2 scho hool Infrastructure cation Selection ntation ols situated in Vaslui County RO-ME-SUNRPMU-270288-C S-CQS / Consultancy services Integrated Investments in Sc Consultant Qualifi Pending Impleme IBRD / 92360 Post Open - National 112,623.54 0.00 2023-05-15 2023-05-30 2023-06-18 2023-06-23 2023-07-17 2024-09-09 for site supervision for 3 scho hool Infrastructure cation Selection ntation ols situated in Bucharest Mun icipality RO-ME-SUNRPMU-270287-C S-CQS / Consultancy services Integrated Investments in Sc Consultant Qualifi Pending Impleme IBRD / 92360 Post Open - National 187,705.90 0.00 2023-09-15 2023-09-30 2023-10-19 2023-10-24 2023-11-17 2025-01-10 for site supervision for 5 scho hool Infrastructure cation Selection ntation ols situated in Ilfov County RO-ME-SUNRPMU-270286-C S-CQS / Consultancy services Integrated Investments in Sc Consultant Qualifi Pending Impleme IBRD / 92360 Post Open - National 112,623.54 0.00 2023-05-15 2023-05-30 2023-06-18 2023-06-23 2023-07-17 2024-09-09 for site supervision for 3 scho hool Infrastructure cation Selection ntation ols situated in Iasi County RO-ME-SUNRPMU-270284-C S-CQS / Consultancy services Integrated Investments in Sc Consultant Qualifi Pending Impleme IBRD / 92360 Post Open - National 112,623.54 0.00 2023-05-15 2023-05-30 2023-06-18 2023-06-23 2023-07-17 2024-09-09 for site supervision for 3 scho hool Infrastructure cation Selection ntation ols situated in Iasi County RO-ME-SUNRPMU-270282-C S-CQS / Consultancy services Integrated Investments in Sc Consultant Qualifi Pending Impleme IBRD / 92360 Post Open - National 150,164.72 0.00 2023-09-15 2023-09-30 2023-10-19 2023-10-24 2023-11-17 2025-01-10 for site supervision for 4 scho hool Infrastructure cation Selection ntation ols situated in Giurgiu and Te leorman County RO-ME-SUNRPMU-270012-C S-CQS / Consultancy services Integrated Investments in Sc Consultant Qualifi Pending Impleme IBRD / 92360 Post Open - National 112,623.54 0.00 2023-09-15 2023-09-30 2023-10-19 2023-10-24 2023-11-17 2025-01-10 for site supervision for 3 scho hool Infrastructure cation Selection ntation ols situated in Galati and Vra ncea County RO-ME-SUNRPMU-275415-C S-QCBS / Consultancy service Quality And Cost- Pending Impleme s (business analysis) for pro IBRD / 92360 Project Management Post Open - National 144,073.30 0.00 2023-05-22 2023-06-12 2023-07-02 2023-08-01 2023-08-16 2023-08-22 2023-09-15 2023-12-14 Based Selection ntation viding technical requirement s of a Informatic system RO-ME-SUNRPMU-276128-C S-QCBS / Services for campai Integrated Investments in Sc Quality And Cost- Open - Internationa Pending Impleme IBRD / 92360 Post 695,874.04 0.00 2023-05-05 2023-05-26 2023-06-20 2023-07-18 2023-08-02 2023-08-17 2023-09-10 2024-09-09 gns, awareness and commun hool Infrastructure Based Selection l ntation ications materials RO-ME-SUNRPMU-275412-C Consultant Qualifi IBRD / 92360 Project Management Post Open - National 129,665.97 0.00 Signed 2023-03-15 2023-03-13 2023-03-30 2023-03-16 2023-04-18 2023-05-22 2023-05-18 2023-05-22 2023-06-11 2023-06-07 2027-06-30 S-CQS / Audit services cation Selection RO-ME-SUNRPMU-341721-C S-QCBS / Consultancy service Integrated Investments in Sc Quality And Cost- Open - Internationa Under Implement s for A&E design for 2 school IBRD / 92360 Post 937,809.60 0.00 2023-02-15 2023-06-15 2023-03-02 2023-07-19 2023-03-08 2023-04-07 2023-04-22 2023-04-27 2023-05-25 2024-10-16 hool Infrastructure Based Selection l ation s (3 buildings) situated in Bu charest Municipality package S/SISSP/QCBS/03/2023 RO-ME-SUNRPMU-343428-C S-QCBS / Consultancy service s for A&E design for 12 schoo Integrated Investments in Sc Quality And Cost- Open - Internationa Under Implement IBRD / 92360 Prior 2,035,356.00 0.00 2023-02-24 2023-03-03 2023-03-16 2023-03-09 2023-03-26 2023-06-30 2023-05-10 2023-05-30 2023-06-04 2023-07-02 2024-11-23 ls situated in Galati, Vrancea, hool Infrastructure Based Selection l ation Giurgiu, Teleorman and Ilfov County package S/SISSP/QCB S/01/2023 RO-ME-SUNRPMU-269975-C S-QCBS / Consultancy service Integrated Investments in Sc Quality And Cost- IBRD / 92360 Post Open - National 491,001.81 0.00 Canceled 2022-02-15 2022-03-14 2022-03-08 2022-04-03 2022-07-25 2022-05-01 2022-09-08 2022-05-16 2022-12-16 2022-05-21 2022-06-18 2023-11-10 s for A&E design for 5schools hool Infrastructure Based Selection situated in Ilfov County RO-ME-SUNRPMU-269962-C S-QCBS / Consultancy service Integrated Investments in Sc Quality And Cost- IBRD / 92360 Post Open - National 392,801.45 0.00 Canceled 2022-02-15 2022-03-14 2022-03-08 2022-04-03 2022-07-25 2022-05-01 2022-09-06 2022-05-16 2022-11-23 2022-05-21 2022-06-18 2023-11-10 s for A&E design for 4 school hool Infrastructure Based Selection s situated in Giurgiu and Tele orman County RO-ME-SUNRPMU-268762-C S-QCBS / Consultancy service Integrated Investments in Sc Quality And Cost- IBRD / 92360 Post Open - National 294,601.08 0.00 Canceled 2022-02-16 2022-03-14 2022-03-09 2022-04-04 2022-07-20 2022-05-02 2022-09-05 2022-05-17 2022-11-14 2022-05-22 2022-06-19 2023-11-11 s for A&E design for 3 school hool Infrastructure Based Selection s situated in Galati and Vranc ea County INDIVIDUAL CONSULTANTS Page 2 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RO-ME-SUNRPMU-270317-C Individual Consult Under Implement S-INDV / Individual consultan IBRD / 92360 Project Management Post Open 77,799.58 0.00 2023-08-01 2022-03-23 2023-08-31 2023-09-10 2023-10-04 2025-03-27 ant Selection ation t for energy audits RO-ME-SUNRPMU-274024-C Individual Consult S-INDV / Individual consultan IBRD / 92360 Project Management Post Open 285,265.13 0.00 Signed 2022-02-15 2022-03-10 2022-04-01 2022-07-12 2022-04-11 2022-07-12 2022-05-05 2022-10-26 2027-06-01 ant Selection t for social services RO-ME-SUNRPMU-270318-C Individual Consult S-INDV / Individual consultan IBRD / 92360 Project Management Post Open 285,265.13 0.00 Signed 2022-02-15 2022-03-10 2022-04-01 2022-07-12 2022-04-11 2022-07-14 2022-05-05 2022-10-26 2027-06-01 ant Selection t for environmental services RO-ME-SUNRPMU-275405-C Individual Consult S-INDV / Consultant fo engag IBRD / 92360 Project Management Post Open 285,265.13 0.00 Signed 2022-02-15 2022-03-10 2022-04-01 2022-07-12 2022-04-11 2022-07-14 2022-05-05 2022-10-26 2027-06-01 ant Selection ement community services RO-ME-SUNRPMU-268527-C Individual Consult S-INDV / Individual consultan IBRD / 92360 Project Management Post Limited 285,265.13 0.00 Signed 2022-03-21 2022-03-25 2022-03-26 2022-07-12 2022-04-10 2022-07-14 2022-05-04 2022-10-27 2027-06-30 ant Selection t for financial services under the project RO-ME-SUNRPMU-270293-C Integrated Investments in Sc Individual Consult S-INDV / Consultancy service IBRD / 92360 Post Open 223,313.62 0.00 Signed 2022-03-21 2022-03-23 2022-04-20 2022-07-12 2022-04-30 2022-07-14 2022-05-24 2022-10-27 2027-06-30 hool Infrastructure ant Selection s for construction engineer e xpert RO-ME-SUNRPMU-270291-C Integrated Investments in Sc Individual Consult S-INDV / Consultancy service IBRD / 92360 Post Open 223,313.62 0.00 Signed 2022-03-21 2022-03-23 2022-04-19 2022-07-12 2022-04-29 2022-07-14 2022-05-23 2022-10-27 2027-06-30 hool Infrastructure ant Selection s for construction engineer e xpert RO-ME-SUNRPMU-270311-C Individual Consult S-INDV / Individual consultan IBRD / 92360 Project Management Post Open 77,799.58 0.00 Signed 2022-03-21 2022-03-23 2022-04-20 2022-07-12 2022-04-30 2022-07-14 2022-05-24 2022-10-27 2023-11-30 ant Selection t for architectural services RO-ME-SUNRPMU-270312-C Individual Consult S-INDV / Individual consultan IBRD / 92360 Project Management Post Open 77,799.58 0.00 Signed 2022-03-21 2022-03-23 2022-04-20 2022-07-12 2022-04-30 2022-07-14 2022-05-24 2022-10-27 2023-11-30 ant Selection t for construction engineerin g services RO-ME-SUNRPMU-270295-C Integrated Investments in Sc Individual Consult S-INDV / Consultancy service IBRD / 92360 Post Open 223,313.62 0.00 Signed 2022-03-21 2022-03-23 2022-04-19 2022-07-12 2022-04-29 2022-07-14 2022-05-23 2022-10-27 2027-06-30 hool Infrastructure ant Selection s for construction engineer e xpert RO-ME-SUNRPMU-270294-C S-INDV / Consultancy service Integrated Investments in Sc Individual Consult IBRD / 92360 Post Open - National 223,313.62 0.00 Signed 2022-02-15 2022-03-23 2022-07-12 2022-07-12 2022-07-14 2022-07-14 2022-10-26 2022-10-26 2027-06-30 s for construction engineer e hool Infrastructure ant Selection xpert (area coordinator) Area 2 RO-ME-SUNRPMU-270313-C Individual Consult S-INDV / Individual consultan IBRD / 92360 Project Management Post Open 77,799.58 0.00 Canceled 2022-03-21 2022-03-23 2022-04-20 2022-04-30 2022-05-24 2023-11-30 ant Selection t for electrical installations se rvices RO-ME-SUNRPMU-270315-C Individual Consult S-INDV / Individual consultan IBRD / 92360 Project Management Post Open 77,799.58 0.00 Canceled 2022-03-21 2022-03-23 2022-04-20 2022-04-30 2022-05-24 2023-11-30 ant Selection t for plumbing services Page 3