PROCUREMENT PLAN (Textual Part) Project information: Regional Off Grid Electrification Project P- 160708 Project Implementation agency: ECOWAS Centre for Renewable Energy and Energy Efficiency (ECREEE) Date of the Procurement Plan: June 15, 2017 Period covered by this Procurement Plan: June 15, 2017 to June 30, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable PROCUREMENT Western and Central Africa : Regional Off-Grid Electricity Access Project PLAN General Information Country: Western and Central Africa 2017-07-31 Bank’s Approval Date of the Original Procurement Plan: 2023-07-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160708 GPN Date: Project Name: Regional Off-Grid Electricity Access Project Loan / Credit No: IDA / V0740, IDA / D7840 ECOWAS Commission Office of the Commissioner Energy and Mines Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ECREEE/GD/NS-01/17 / Procu Request for Quota Single Stage - One E IDA / V0740 Post Limited 25,000.00 0.00 Canceled 2017-06-24 2017-08-07 2017-08-14 rement of Furniture and Fitti tions nvelope ngs ECREEE/GD/NS-02/17 / Suppl Request for Quota Single Stage - One E IDA / V0740 Post Limited 25,000.00 0.00 Canceled 2017-06-24 2017-08-19 2018-02-15 y and Installation of Office tions nvelope ECREEE/GD/RFQ-01/17 / Pro Request for Quota Single Stage - One E IDA / V0740 Post Limited 23,000.00 0.00 Canceled 2017-06-12 2017-08-11 2017-09-25 curement of furniture and fitt tions nvelope ings (Praia) ECREEE/GD/ICB-01/18 / Sup ply, Installation, managemen Open - Internationa Single Stage - One E IDA / V0740 Post Request for Bids 250,000.00 0.00 Canceled 2018-09-03 2018-09-08 2018-10-20 2018-11-19 2018-12-24 2019-06-22 t, operation and maintenanc l nvelope e for solar equipments in Nig eria ECREEE/GD/ICB-02/18 / Sup ply, installation, managemen Open - Internationa Single Stage - One E IDA / V0740 Post Request for Bids 200,000.00 0.00 Canceled 2018-09-03 2018-09-08 2018-10-20 2018-11-19 2018-12-24 2019-06-22 t, operation and maintenanc l nvelope e for solar equipments Niger ECREEE/GD/RFQ-06/18 / Pro Request for Quota Single Stage - One E IDA / V0740 Post Limited 8,000.00 0.00 Canceled 2018-06-25 2018-08-20 2018-10-04 curement of Furniture and Fit tions nvelope tings (Praia) ECREEE/GD/RFQ-07/18 / Sup Request for Quota Single Stage - One E ply and Installation of Office IDA / V0740 Post Limited 51,000.00 0.00 Canceled 2018-06-25 2018-08-20 2018-10-04 tions nvelope Equipment (Praia) ECREEE/GD/RFQ-02/17 / Sup Request for Quota Single Stage - One E ply and Installation of Office IDA / V0740 Post Limited 12,000.00 0.00 Canceled 2017-06-14 2017-07-28 2017-09-15 tions nvelope Equipment (Praia) ECREEE/GD/RFQ-04/17 / Pro Request for Quota Single Stage - One E IDA / V0740 Post Limited 2,000.00 0.00 Canceled 2017-10-19 2017-11-09 2017-11-30 curement of furniture and fitt tions nvelope ings - Abuja ECREEE/GD/RFQ-03/17 / Sup Request for Quota Single Stage - One E ply and installation office equ IDA / V0740 Post Limited 10,000.00 0.00 Canceled 2017-06-14 2017-08-09 2018-02-05 tions nvelope ipment - Abuja ECREEE/GD/RFQ-08/18 / Sup Request for Quota Single Stage - One E ply and Installation of Office IDA / V0740 Post Limited 2,000.00 0.00 Canceled 2018-06-25 2018-08-20 2018-10-04 tions nvelope Equipment (Abuja) ECREEE/GD/RFQ-09/18 / Pro Request for Quota Single Stage - One E IDA / V0740 Post Limited 2,000.00 0.00 Canceled 2018-06-25 2018-08-20 2018-10-04 curement of Furniture and Fit tions nvelope tings (Accra) ECREEE/GD/RFQ-10/18 / Sup Request for Quota Single Stage - One E ply and Installation of Office IDA / V0740 Post Limited 7,000.00 0.00 Canceled 2018-06-25 2018-08-20 2018-10-04 tions nvelope Equipment (Accra) ECREEE/GD/RFQ-05/17 / Sup Request for Quota Single Stage - One E ply and Installation of Office IDA / V0740 Post Limited 3,000.00 0.00 Canceled 2017-09-27 2017-11-20 2017-12-29 tions nvelope Equipment - Accra NG-ECOWAS-OCEM-289308- Request for Quota Single Stage - One E GO-RFQ / Supply and deliver IDA / D7840 1A: Enabling Environment Post Limited 80,000.00 65,827.50 Signed 2022-05-20 2022-04-26 2022-07-15 2022-08-22 2022-09-13 tions nvelope y of IT Equipment NG-ECOWAS-OCEM-289315- Request for Quota Single Stage - One E GO-RFQ / Supply and deliver IDA / D7840 1A: Enabling Environment Post Limited 30,000.00 17,712.92 Completed 2022-04-30 2022-04-26 2022-06-25 2022-08-28 2022-08-24 2022-09-30 tions nvelope y of Office furniture NG-ECOWAS-OCEM-294904- Request for Quota Single Stage - One E GO-RFQ / Acquisition of com IDA / D7840 1A: Enabling Environment Post Limited 15,000.00 0.00 Signed 2022-07-06 2022-06-30 2022-08-31 2022-12-02 2022-10-30 tions nvelope munication tools for ROGEAP Project NG-ECOWAS-OCEM-294913- Request for Quota Single Stage - One E GO-RFQ / Car rental for the R IDA / D7840 1A: Enabling Environment Post Limited 11,000.00 0.00 Signed 2022-08-19 2022-11-11 2022-10-14 2023-05-09 2023-10-14 tions nvelope OGEAP project NG-ECOWAS-OCEM-319403- GO-DIR / Acquisition of additi IDA / D7840 1A: Enabling Environment Post Direct Selection Direct - National 6,000.00 0.00 Signed 2022-11-30 2022-11-16 2022-12-05 2022-11-22 2023-01-19 2023-03-10 2023-02-18 onal IT equipment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ECREEE/CON/QCBS-01/17 / R EGIONAL OFF-GRID SOLAR M Quality And Cost- Open - Internationa IDA / V0740 1A: Enabling Environment Prior 1,900,000.00 652,873.00 Signed 2017-06-15 2017-07-06 2017-08-19 2017-09-04 2017-09-16 2017-10-20 2017-10-16 2017-12-06 2017-11-20 2018-07-13 2017-12-25 2018-03-16 2018-07-23 ARKET ASSESSMENT AND PRI Based Selection l VATE SECTOR SUPPORT FACI LITY DESIGN ECREEE/CON/CQS-03/17 / TA Consultant Qualifi Open - Internationa for entrepreneurs' projects re IDA / V0740 Prior 100,000.00 0.00 Canceled 2017-08-25 2018-02-22 2017-09-15 2018-02-23 2017-10-29 2018-08-15 2017-11-28 2018-01-02 2018-07-31 cation Selection l fining to bankable stage ECREEE/CON/CQS-01/17 / TA Consultant Qualifi Open - Internationa to prepare draft regional dire IDA / V0740 1A: Enabling Environment Prior 75,000.00 84,592.16 Signed 2017-06-30 2017-11-14 2017-07-21 2017-09-03 2018-04-08 2017-10-03 2018-11-28 2017-11-07 2018-09-03 2018-07-05 cation Selection l ctive/ policy on quality specifi cations for SHS ECREEE/CON/CQS-02/17 / Pr ovision of Technical Support Consultant Qualifi Open - Internationa IDA / V0740 Prior 180,000.00 0.00 Canceled 2017-10-27 2018-02-11 2017-11-17 2017-12-31 2018-01-30 2018-03-06 2018-07-24 on to countries on enabling e cation Selection l nvironment's improvement ECREEE/CON/CQS-04/18 / Id entification and analysis of a Consultant Qualifi Open - Internationa network of organizations with IDA / V0740 1A: Enabling Environment Prior 100,000.00 0.00 Canceled 2018-07-02 2018-08-20 2018-07-23 2018-08-23 2018-09-05 2019-07-16 2018-10-05 2018-11-09 2019-05-08 cation Selection l existing capacity to support entrepreneurs and deliver m anagerial training programs. ECREEE/CON/QCBS-03/18 / R Quality And Cost- Open - Internationa IDA / V0740 1A: Enabling Environment Post 200,000.00 0.00 Canceled 2018-09-03 2018-09-24 2018-11-07 2018-12-05 2019-01-04 2019-02-08 2019-03-15 2020-03-14 isk Mitigation Facility Based Selection l ECREEE/CON/CQS-02/17 - I / PHASE I - Development of im plementation frameworks for private investment in the off- Consultant Qualifi Open - Internationa IDA / V0740 1A: Enabling Environment Prior 100,000.00 0.00 Canceled 2017-11-27 2018-04-19 2018-08-27 2019-04-16 2018-09-26 2018-10-31 2020-12-31 grid electrification of public i cation Selection l nstitutions and to promote pr oductive uses of electricity fr om standalone solar systems in Niger and Nigeria ECREEE/CON/QCBS-04/19 / T Quality And Cost- Open - Internationa A for entrepreneurs' projects IDA / V0740 1A: Enabling Environment Prior 230,000.00 0.00 Canceled 2019-12-08 2019-12-29 2020-02-11 2020-03-10 2020-04-09 2020-05-14 2020-06-18 2021-11-18 Based Selection l refining to bankable stage. ECREEE/CON/CQS-05/19 / Fe asibility Study for Capital Mar ket Funding of Standalone So Consultant Qualifi Open - Internationa IDA / V0740 1A: Enabling Environment Post 100,000.00 0.00 Canceled 2019-12-02 2019-12-23 2020-02-05 2020-03-06 2020-04-10 2021-01-13 lar Loans and Receivables in cation Selection l the UEMOA Region for the Re gional Off-grid Electrification Project (ROGEP) NG-ECOWAS-OCEM-235864- 1B: Entrepreneurship Techni Quality And Cost- Open - Internationa CS-CQS / Consultancy firm fo IDA / V0740 Prior 3,000,000.00 0.00 Canceled 2021-07-01 2021-07-22 2021-09-04 2021-10-02 2021-11-01 2021-12-06 2022-01-10 2023-01-10 cal Support Based Selection l r Project Fund Manager (PFM) NG-ECOWAS-OCEM-241386- 1B: Entrepreneurship Techni Quality And Cost- Open - Internationa CS-QCBS / Consultancy Firm f IDA / D7840 Prior 3,000,000.00 0.00 Canceled 2021-06-25 2021-06-28 2021-07-16 2021-08-29 2021-09-26 2021-10-26 2021-11-30 2022-01-04 2023-01-04 cal Support Based Selection l or Project Fund Manager (PF M) NG-ECOWAS-OCEM-246015- 1B: Entrepreneurship Techni Quality And Cost- Open - Internationa Under Implement CS-QCBS / Consultancy Firm f IDA / D7840 Prior 3,000,000.00 0.00 2021-07-28 2021-07-30 2021-08-20 2021-08-09 2021-10-03 2022-06-24 2021-10-31 2022-09-29 2021-11-30 2023-02-27 2022-01-04 2023-05-30 2022-02-08 2023-02-08 cal Support Based Selection l ation or Project Fund Manager (PF M) NG-ECOWAS-OCEM-294903- Least Cost Selecti Open - Internationa IDA / D7840 1A: Enabling Environment Post 60,000.00 0.00 Signed 2022-05-20 2022-06-21 2022-06-03 2022-09-28 2022-07-17 2022-12-07 2022-08-14 2023-01-18 2022-09-13 2023-02-08 2022-10-18 2023-03-23 2022-11-22 2023-05-05 2025-11-06 CS-LCS / Audit of ROGEAP pr on l oject NG-ECOWAS-OCEM-294910- CS-CQS / Recruitment of an a Consultant Qualifi IDA / D7840 1A: Enabling Environment Post Limited 35,000.00 0.00 Signed 2022-08-01 2022-06-21 2022-08-15 2022-11-28 2022-09-14 2023-01-31 2022-10-19 2023-05-09 2023-04-17 gency for the production of a cation Selection institutional video NG-ECOWAS-OCEM-312796- CS-CDS / Development and i Quality And Cost- Open - Internationa Under Implement mplementation of sustainabl IDA / D7840 1A: Enabling Environment Post 500,000.00 0.00 2022-11-30 2022-11-16 2022-12-21 2023-03-13 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2023-12-08 Based Selection l ation e business and financing mo dels for the electrification of public rural health centers NG-ECOWAS-OCEM-336818- Consultant Qualifi Under Implement CS-CQS / Recruitment of a tr IDA / D7840 1A: Enabling Environment Post Open - National 50,000.00 0.00 2023-01-31 2023-01-27 2023-02-21 2023-02-17 2023-04-06 2023-05-06 2023-06-10 2024-06-09 cation Selection ation anslation and interpreting co mpany ECREEE/CON/QCBS-02/17 / F Quality And Cost- Open - Internationa IDA / V0740 1A: Enabling Environment Post 100,000.00 0.00 Canceled 2018-03-26 2019-04-30 2018-04-16 2019-05-24 2018-05-30 2018-06-27 2018-07-27 2018-08-31 2018-10-05 2018-11-24 inancial audit Based Selection l ECREEE/CON/CQS-02/17-II / PHASE II- TA for specific supp Consultant Qualifi Open - Internationa IDA / V0740 1A: Enabling Environment Post 100,000.00 0.00 Canceled 2018-08-15 2018-08-22 2018-09-05 2018-08-28 2018-10-19 2018-11-18 2018-12-23 2019-08-23 ort to countries on enabling e cation Selection l nvironment's improvment INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ECREEE/CON/IC-02/17 / TA t Individual Consult o assist in fieldwork, supevisi IDA / V0740 Post Limited 20,000.00 0.00 Canceled 2017-07-14 2017-07-19 2017-08-09 2017-09-13 2018-06-10 ant Selection on and monitoring of pilot pr ojects in Niger ECREEE/CON/IC-03/17 / TA t Individual Consult o assist in fieldwork, supervis IDA / V0740 Post Limited 20,000.00 0.00 Canceled 2017-07-13 2017-07-18 2017-08-08 2017-09-12 2018-05-10 ant Selection ion and monitoring of pilot pr ojects in Nigeria ECREEE/CON/IC-01/18 / Proje Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 11,500.00 0.00 Canceled 2017-12-19 2017-12-24 2018-01-14 2018-02-18 2018-08-17 ct Administrative Assistant ant Selection ECREEE/CON/IC-03/18 / Proje Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 13,500.00 0.00 Canceled 2017-12-19 2017-12-24 2018-01-14 2018-02-18 2018-08-17 ct Communication Officer ant Selection Page 2 ECREEE/CON/IC-02/18 / Proje Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 20,000.00 0.00 Canceled 2017-12-19 2017-12-24 2018-01-14 2018-02-18 2018-08-17 ct Administration Officer ant Selection ECREEE/CON/IC-05/18 / Proje Individual Consult IDA / V0740 1A: Enabling Environment Post Open 22,750.00 0.00 Canceled 2017-12-19 2018-02-06 2018-02-27 2018-04-03 2018-09-30 ct Finance expert ant Selection ECREEE/CON/IC-04/18 / Coor Individual Consult dinator Of Private Support Fa IDA / V0740 1A: Enabling Environment Post Limited 32,500.00 0.00 Canceled 2017-12-19 2017-12-24 2018-01-14 2018-03-19 2018-09-15 ant Selection cility Sector ECREEE/CON/IC-06/18 / Proje Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 10,000.00 0.00 Canceled 2017-12-19 2017-12-24 2018-01-14 2018-03-19 2018-09-15 ct IT Assistant ant Selection ECREEE/CON/IC-09/18 / Proje Individual Consult IDA / V0740 1A: Enabling Environment Post Direct 110,500.00 0.00 Canceled 2017-05-02 2017-05-12 2017-05-15 2017-05-29 2018-08-31 ct Coordinator ant Selection ECREEE/CON/IC-19/18 / Proje Individual Consult IDA / V0740 1A: Enabling Environment Post Open 12,500.00 0.00 Canceled 2018-03-16 2018-06-22 2018-07-13 2018-07-27 2018-12-31 ct Accountant Assistant ant Selection ECREEE/CON/IC-07/18 / Proje Individual Consult IDA / V0740 1A: Enabling Environment Post Open 37,500.00 0.00 Canceled 2018-01-08 2018-02-18 2018-02-21 2018-03-19 2018-09-15 ct (impact) Evaluation Expert ant Selection ECREEE/CON/IC-10/18 / Tech Individual Consult IDA / V0740 1A: Enabling Environment Post Direct 105,000.00 0.00 Canceled 2017-05-02 2017-05-11 2017-05-19 2017-05-22 2017-11-18 nical Coordinator ant Selection ECREEE/CON/IC-12/18 / Tech Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 84,500.00 0.00 Canceled 2017-05-02 2017-05-07 2017-05-18 2017-05-22 2017-11-18 nical Specialist - Area 3 ant Selection ECREEE/CON/IC-08/18 / Gen Individual Consult IDA / V0740 1A: Enabling Environment Post Open 10,500.00 0.00 Canceled 2018-01-08 2018-02-22 2018-02-22 2018-04-19 2018-10-16 der Expert ant Selection ECREEE/CON/IC-11/18 / Fina Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 84,500.00 0.00 Canceled 2017-05-01 2017-05-15 2017-05-17 2017-05-22 2017-11-18 ncial Management Specialist ant Selection ECREEE/CON/IC-17/18 / Proje Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 39,000.00 0.00 Canceled 2017-06-09 2017-06-09 2017-06-30 2017-07-25 2018-01-21 ct GIS Specialist ant Selection ECREEE/CON/IC-15/18 / Proje Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 39,000.00 0.00 Canceled 2017-05-31 2017-06-09 2017-06-30 2017-07-14 2018-01-10 ct Accountant ant Selection ECREEE/CON/IC-16/18 / Adm Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 30,000.00 0.00 Canceled 2017-08-18 2017-08-23 2017-09-13 2017-10-19 2018-04-17 inistrative Officer - Abuja ant Selection ECREEE/CON/IC-13/18 / Tech Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 84,500.00 0.00 Canceled 2017-05-02 2017-05-07 2017-05-18 2017-05-22 2017-11-18 nical Specialist - Area 2 ant Selection ECREEE/CON/IC-14/18 / Tech Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 84,500.00 0.00 Canceled 2017-05-02 2017-05-07 2017-05-28 2017-06-02 2017-11-29 nical Specialist - Area 1 ant Selection ECREEE/CON/IC-18/18 / Proc Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 17,000.00 0.00 Canceled 2017-09-11 2017-09-16 2017-09-18 2017-11-08 2018-07-31 urement Specialist ant Selection ECREEE/CON/IC-20/19 COOR Individual Consult DINATOR ROGEP / PROJECT C IDA / V0740 1A: Enabling Environment Prior Open 110,500.00 0.00 Canceled 2019-05-31 2019-06-26 2019-06-29 2019-07-04 2021-07-04 ant Selection OORDINATOR OF ROGEP ECREEE/CON/IC-21/19 / TEC Individual Consult IDA / V0740 1A: Enabling Environment Prior Open 105,000.00 0.00 Canceled 2019-05-31 2019-06-26 2019-06-29 2019-07-04 2021-07-04 HNICAL COORDINATOR FOR ant Selection ROGEP ECREEE/CON/IC-22/19 / ADVI Individual Consult SOR TO THE COMMISSIONER IDA / V0740 1A: Enabling Environment Prior Open 96,000.00 0.00 Canceled 2019-05-31 2019-06-26 2019-06-29 2019-07-04 2021-07-04 ant Selection ENERGY AND MINES ECREEE/CON/IC-24/19 / TEC Individual Consult IDA / V0740 1A: Enabling Environment Prior Open 156,000.00 0.00 Canceled 2019-12-02 2020-01-16 2020-01-20 2020-02-10 2020-03-16 2022-03-09 HNICAL SPECIALIST for AREA ant Selection 2 ECREEE/CON/IC-25/19 / FINA Individual Consult IDA / V0740 1A: Enabling Environment Prior Open 156,000.00 0.00 Canceled 2019-12-02 2020-01-16 2020-01-20 2020-02-10 2020-03-16 2022-03-03 NCE EXPERT FOR ROGEP ant Selection ECREEE/CON/IC-23/19 / Enga gement of a Consultant to pr ospect for Commercial Finan Individual Consult IDA / V0740 1A: Enabling Environment Post Limited 65,500.00 0.00 Canceled 2019-11-29 2019-12-04 2019-12-25 2020-01-29 2021-01-27 cial Institutions to access Cre ant Selection dit Lines from BOAD for the R egional Off-grid Electrificatio n Project (ROGEP) NG-ECOWAS-OCEM-235792- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 Individual Consul IDA / V0740 Post Limited 95,000.00 0.00 Canceled 2021-07-01 2021-07-06 2021-07-27 2021-08-31 2022-02-27 cal Support ant Selection tant as Financial Managemen t Expert NG-ECOWAS-OCEM-241360- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 individual consul IDA / D7840 Post Limited 95,000.00 109,500.00 Signed 2021-06-24 2021-04-12 2021-06-29 2021-04-12 2021-07-20 2021-10-18 2021-08-24 2021-12-30 2022-08-19 cal Support ant Selection tant as Financial Managemen t Specialist NG-ECOWAS-OCEM-235778- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 Individual Consul IDA / V0740 Post Limited 43,000.00 0.00 Canceled 2021-07-01 2021-07-06 2021-07-27 2021-08-31 2022-02-27 cal Support ant Selection tant as Administrative Assist ant NG-ECOWAS-OCEM-241361- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 individual consul IDA / D7840 Post Limited 43,000.00 100,000.00 Signed 2021-06-25 2021-04-12 2021-06-30 2021-04-12 2021-07-21 2021-12-08 2021-08-25 2022-04-09 2022-08-20 cal Support ant Selection tant as Administrative Assist ant NG-ECOWAS-OCEM-235859- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 Individual Consul IDA / V0740 Post Limited 95,000.00 0.00 Canceled 2021-07-01 2021-07-06 2021-07-27 2021-08-31 2022-02-27 cal Support ant Selection tant as Procurement Speciali st NG-ECOWAS-OCEM-241368- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 individual Consul IDA / D7840 Post Limited 95,000.00 108,000.00 Signed 2021-06-25 2021-04-12 2021-06-30 2021-04-12 2021-07-21 2021-10-14 2021-08-25 2021-12-09 2022-08-20 cal Support ant Selection tant as Procurement Speciali st NG-ECOWAS-OCEM-235782- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 individual Consul IDA / V0740 Post Limited 81,500.00 0.00 Canceled 2021-07-01 2021-07-06 2021-07-27 2021-08-31 2022-02-27 cal Support ant Selection tant as Communication Offic er Page 3 NG-ECOWAS-OCEM-241369- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 individual consul IDA / D7840 Post Limited 81,500.00 81,500.00 Signed 2021-06-25 2021-04-12 2021-06-30 2021-11-10 2021-07-21 2021-11-17 2021-08-25 2021-12-09 2022-08-20 cal Support ant Selection tant as Communication Offic er NG-ECOWAS-OCEM-235794- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 Individual Consul IDA / V0740 Post Limited 95,000.00 0.00 Canceled 2021-07-01 2021-07-06 2021-07-27 2021-08-31 2022-02-27 cal Support ant Selection tant as Monitoring and Evalu ation Officer NG-ECOWAS-OCEM-241370- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 individual consul IDA / D7840 Post Limited 95,000.00 95,000.00 Signed 2021-06-25 2021-04-12 2021-06-30 2021-04-12 2021-07-21 2021-11-17 2021-08-25 2022-03-10 2022-08-20 cal Support ant Selection tant as Monitoring and Evalu ation Officer NG-ECOWAS-OCEM-235861- CS-INDV / I Individual Consult 1B: Entrepreneurship Techni Individual Consult IDA / V0740 Post Limited 108,000.00 0.00 Canceled 2021-07-01 2021-07-06 2021-07-27 2021-08-31 2022-02-27 ant as Senior Advisor to Com cal Support ant Selection missioner, Energy and Mines NG-ECOWAS-OCEM-241376- CS-INDV / 1 individual consul 1B: Entrepreneurship Techni Individual Consult IDA / D7840 Post Limited 108,000.00 114,000.00 Signed 2021-06-25 2021-04-12 2021-06-30 2021-04-12 2021-07-21 2021-11-11 2021-08-25 2021-12-09 2022-08-20 tant as Senior Adviser to Co cal Support ant Selection mmissioner, Energy and Min es NG-ECOWAS-OCEM-235863- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 Individual Consul IDA / V0740 Post Limited 108,000.00 0.00 Canceled 2021-07-01 2021-07-06 2021-07-27 2021-08-31 2022-02-27 cal Support ant Selection tant as Senior Financial Expe rt (BOAD) NG-ECOWAS-OCEM-241379- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 individual Consul IDA / D7840 Post Limited 108,000.00 108,000.00 Signed 2021-06-25 2021-04-12 2021-06-30 2021-04-12 2021-07-21 2021-11-11 2021-08-25 2021-12-25 2022-08-20 cal Support ant Selection tant as Senior Financial Expe rt BOAD NG-ECOWAS-OCEM-235860- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 Individual Consul IDA / D7840 Post Limited 95,000.00 0.00 Signed 2021-06-28 2021-06-29 2021-07-03 2022-04-25 2021-07-24 2022-07-05 2021-08-28 2022-11-08 2022-08-23 cal Support ant Selection tant as Grievance Redress Of ficer NG-ECOWAS-OCEM-243108- 1B: Entrepreneurship Techni Individual Consult CS-INDV / 1 individual consul IDA / D7840 Post Limited 43,000.00 0.00 Canceled 2021-07-12 2021-04-12 2021-07-17 2021-08-07 2021-09-11 2022-09-06 cal Support ant Selection tant as Administrative Assist ant 2 NG-ECOWAS-OCEM-294906- CS-INDV / Recruitment of a c Individual Consult IDA / D7840 1A: Enabling Environment Post Limited 15,000.00 0.00 Signed 2022-07-01 2022-06-21 2022-07-06 2022-12-15 2022-07-27 2023-01-31 2022-08-31 2023-05-09 2022-11-29 onsultant for the creation of t ant Selection he ROGEAP project website NG-ECOWAS-OCEM-294921- CS-INDV / Recruitment of two consultants to support the pr Individual Consult Under Implement eparation and implementatio IDA / D7840 1A: Enabling Environment Post Limited 15,000.00 0.00 2022-06-30 2022-06-22 2022-07-05 2022-07-26 2022-08-30 2023-02-26 ant Selection ation n of the regional capacity bui lding workshop for the impro vement of the policy and reg ulatory framework NG-ECOWAS-OCEM-294912- Individual Consult CS-CQS / Recruitment of a tr IDA / D7840 1A: Enabling Environment Post Limited 25,000.00 0.00 Canceled 2022-08-14 2022-09-23 2022-08-19 2022-09-09 2022-10-14 2023-10-14 ant Selection anslator for the ROGEAP proj ect NG-ECOWAS-OCEM-302604- CS-INDV / Recruitment of an i Individual Consult Under Implement ndividual consultant in enviro IDA / D7840 1A: Enabling Environment Post Limited 25,000.00 0.00 2022-08-31 2022-09-29 2022-09-01 2023-01-19 2022-09-22 2022-10-27 2023-10-27 ant Selection ation nmental and social safeguard ing for the training of financi al institutions NG-ECOWAS-OCEM-344193- CS-INDV / Recruitment of Fin Individual Consult Under Implement IDA / D7840 1A: Enabling Environment Post Limited 192,000.00 0.00 2023-04-02 2023-04-05 2023-04-07 2023-04-28 2023-06-02 2025-06-01 ancial Management Specialis ant Selection ation t for ROGEAP Project NG-ECOWAS-OCEM-337495- Individual Consult Direct - Internation CS-INDV / Replacement of th IDA / D7840 1A: Enabling Environment Post 96,000.00 0.00 Canceled 2023-01-31 2023-01-27 2023-02-10 2023-02-06 2023-03-03 2023-04-07 2026-04-06 ant Selection al e Financial Management Spe cialist Page 4