Procurement Plan Colombia - Plan PAZcifico: WSS Infrastructure & Service Delivery Project P156239 I. General 1. Bank’s approval Date of the procurement Plan: Original 2016/08/29; Revision 2016/12/15 and 2017/4/19 2. Date of General Procurement Notice: Dec 13, 2016 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank will be marked in the procurement plan according to the level of risk of the agency 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P156239 issued by National Unit For The Management Of Disaster Risk – UNGRD 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 40.00 1 No Prior of the ICB (Works) Summary 54.00 09 No Post of the NCB (Works) Summary 1.00 1 No Post of the NCB (Goods) III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank will be marked in the procurement plan according to the level of risk of the agency 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_400,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 11.6 6 Post of number of contracts that will be let under QCBS Summary 1.6 5 Post CQS, of number LCBS of contracts that will be let under other methods July 9, 2010 PROCUREMENT Colombia : CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2016-12-15 Revised Plan Date(s): (comma delineated, leave blank if 2023-07-24 none) Project ID: P156239 GPN Date: 2016-12-13 Project Name: CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project Loan / Credit No: IBRD / 86490 National Unit for the Management of Disaster Risk Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PTSP-BIRF8649-002 / Acued Component 2. Water Supply ucto Tumaco, Nariño. Aducci and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 2019-06-0 IBRD / 86490 Posterior Open - National 2,973,324.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 on: suministro e instalacion d ements in the Municipality o s nvelope 4 e 5.5 km de tuberia en HD de f Tumaco 20" (1 de 4) PTSP-BIRF8649-003 / Acued ucto Tumaco, Nariño. Optimi zación PTAP Buchelly (incluy Component 2. Water Supply e: construccion empate con l and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 2019-06-0 IBRD / 86490 Posterior Open - National 1,547,966.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 a nueva aduccion de 20", co ements in the Municipality o s nvelope 4 nstruccion 4 modulos de des f Tumaco arenacion, mejoramiento sist ema dosificacion coagulante, construccion 4 modulos de fl oculacion. (2 de 4) PTSP-BIRF8649-004 / Acued ucto Tumaco, Nariño. Red m Component 2. Water Supply atriz continental: suministro and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 2019-06-0 IBRD / 86490 Posterior Open - National 822,003.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 e instalacion de 2229 metros ements in the Municipality o s nvelope 4 de tuberia HD y suministro e f Tumaco instalacion de macromedidor es. (3 de 4) PTSP-BIRF8649-005 / Acued Component 2. Water Supply ucto Tumaco, Nariño. Sumini and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 2019-06-0 stro e instalacion de 12331 IBRD / 86490 Posterior Open - National 1,519,053.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 ements in the Municipality o s nvelope 4 metros de redes de distribuci f Tumaco on de PVC RDE 21 (4 de 4) PTSP-BIRF8649-055 / CONST RUCCION DE 7.800 M DE AD UCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMP Component 2. Water Supply LIACION DE LA PTAP BUCHEL and Basic Sanitation Improv Solicitud de oferta Open - Internationa Single Stage - One E 2019-01-0 IBRD / 86490 Posterior 7,779,897.00 0.00 Cancelado 2017-08-25 2017-10-17 2017-08-30 2017-10-11 2018-03-14 2017-11-10 2018-06-08 2017-12-15 LI EN 50 LPS, CONSTRUCCIO ements in the Municipality o s l nvelope 9 N DE 2.231 M DE RED MATRI f Tumaco Z EN TUBERIA HD, CONSTRU CCION DE 15.298 M DE REDE S DE DISTRIBUCION EN TUBE RIA PVC-POI SEGUNDO Q PTSP-BIRF8649-045 / CONST RUCCION DE 5.500 M DE AD UCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMP Component 2. Water Supply LIACION DE LA PTAP BUCHEL and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 2018-09-1 IBRD / 86490 Posterior Open - National 6,862,347.00 0.00 Cancelado 2017-08-25 2017-08-30 2017-10-20 2017-10-11 2017-11-10 2017-12-15 LI EN 50 LPS, CONSTRUCCIO ements in the Municipality o s nvelope 1 N DE 2.231 M DE RED MATRI f Tumaco Z EN TUBERIA HD, CONSTRU CCION DE 15.298 M DE REDE S DE DISTRIBUCION EN TUBE RIA PVC - POI SEGUNDO QUI NQ PTSP-BIRF8649-018 / “Red M Component 2. Water Supply enor de  distribución de la zo and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 2020-05-1 IBRD / 86490 Posterior Open - National 1,724,138.00 0.00 Cancelado 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 na continental fase 2 en el M ements in the Municipality o s nvelope 3 unicipio de Tumaco, Departa f Tumaco mento de Nariño” PTSP-BIRF8649-017 / “Const Component 2. Water Supply rucción segunda fase de 20” and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 2019-05-1 en tubería de hierro dúctil pa IBRD / 86490 Posterior Open - National 1,436,782.00 0.00 Cancelado 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 ements in the Municipality o s nvelope 9 ra aducción, Municipio de Sa f Tumaco n Andrés de Tumaco, Depart amento de Nariño” PTSP-BIRF8649-014 / Constr Component 1. Water Supply Solicitud de oferta Single Stage - One E 2020-09-1 ucción del sistema definitivo IBRD / 86490 and Basic Sanitation Improv Posterior Open - National 1,353,180.00 0.00 Cancelado 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 s nvelope 0 de disposición final de residu ements in the Municipality o os. f Guapi PTSP-BIRF8649-013 / Constr Component 1. Water Supply Solicitud de oferta Single Stage - One E 12,865,288.0 2021-07-3 uccion del Sistema de Manej IBRD / 86490 and Basic Sanitation Improv Posterior Open - National 0.00 Cancelado 2018-04-02 2018-05-01 2018-06-12 2018-07-12 2018-08-16 s nvelope 0 1 o de las Aguas Residuales Ca ements in the Municipality o sco Urbano f Guapi PTSP-BIRF8649-019 / Constr Component 2. Water Supply Solicitud de oferta Single Stage - One E 2019-04-1 ucción nuevo relleno sanitari IBRD / 86490 and Basic Sanitation Improv Posterior Open - National 4,281,100.00 0.00 Cancelado 2018-07-01 2018-07-06 2018-08-17 2018-09-16 2018-10-21 s nvelope 9 o del municipio de Tumaco ements in the Municipality o f Tumaco PTSP-BIRF8649-074 / "OBRA S DE OPTIMIZACION Y AM PLIACION DEL SISTEMA DE Component 2. Water Supply ACUEDUCTO DEL DISTRIT and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 13,263,597.0 9,353,680.1 2020-11-2 IBRD / 86490 Posterior Open - National Firmado 2019-03-04 2019-03-07 2019-03-06 2019-04-03 2019-04-26 2019-05-03 2019-05-24 2019-06-07 2019-09-13 O ESPECIAL DE TUMACO FA ements in the Municipality o s nvelope 0 6 8 SE II, COMPONENTES PARA f Tumaco EL ABASTECIMIENTO A LOS SECTORES DE CONTINENTE E ISLA TUMACO". PTSP-BIRF8649-076 / "OBRA S DE OPTIMIZACION Y AMPLI Component 2. Water Supply ACION DEL SISTEMA DE ACU and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 5,357,696.2 2020-07-2 IBRD / 86490 Posterior Open - National 7,700,000.00 Firmado 2019-04-30 2019-06-07 2019-05-05 2019-06-04 2019-07-15 2019-06-29 2019-10-21 2019-08-03 2019-12-18 EDUCTO DEL DISTRITO ESPE ements in the Municipality o s nvelope 6 8 CIAL DE TUMACO FASE I, DEP f Tumaco ARTAMENTO DE NARIÑO, CO LOMBIA" PTSP-BIRF8649-064 / Constr ucción de 7.800 m de aducci ón tubería hd 20", optimizaci Component 2. Water Supply ón y ampliación PTAP Buchell and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 2020-04-1 i 50 lps, construcción de 2.23 IBRD / 86490 Posterior Open - National 7,733,591.00 0.00 Cancelado 2018-12-28 2019-01-02 2019-01-02 2019-02-13 2019-02-26 2019-03-15 2019-04-19 ements in the Municipality o s nvelope 3 1 m red matriz tubería hd, co f Tumaco nstruccion de 15.298 m rede s de distribución tubería pvc - poi segundo quinquenio del municipio de Tumaco Page 1 PTSP-BIRF8649-083 / “OPTIM IZACION Y AMPLIACION DEL Component 1. Water Supply SISTEMA DE ACUEDUCTO DE and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 3,118,398.3 2021-04-0 IBRD / 86490 Posterior Open - National 4,500,000.00 Firmado 2019-07-10 2019-08-30 2019-07-12 2019-10-01 2019-08-09 2019-10-28 2019-09-08 2020-03-27 2019-10-13 2017-12-19 LA CABECERA MUNICIPAL DE ements in the Municipality o s nvelope 0 5 GUAPI, DEPARTAMENTO DEL f Guapi CAUCA, COLOMBIA – ETAPA I ” PTSP-BIRF8649-100 / OBRAS DE OPTIMIZACIÓN Y AMPLIAC Component 2. Water Supply IÓN DEL SISTEMA DE ACUED and Basic Sanitation Improv Solicitud de oferta Single Stage - One E 2020-10-1 IBRD / 86490 Posterior Open - National 1,262,000.00 902,276.97 Firmado 2020-01-10 2020-01-17 2020-01-15 2020-02-14 2020-03-04 2020-03-10 2020-04-07 2020-04-14 2020-08-21 UCTO DEL DISTRITO ESPECIA ements in the Municipality o s nvelope 3 L DE TUMACO, DEPARTAMEN f Tumaco TO DE NARIÑO, COLOMBIA - FASE III ETAPA I Documento de Ad PTSP-BIRF8649-146 / Constr quisiciones con e Component 1. Water Supply ucción de la Fase II de acued nfoque nacional - and Basic Sanitation Improv Solicitud de oferta Single Stage - One E Ejecución p 2023-05-3 ucto GUAPI (técnico+ gestión IBRD / 86490 Posterior Open - National Proceso de un sob 3,080,000.00 0.00 2022-05-27 2022-05-29 2022-06-26 2022-07-26 2022-08-30 ements in the Municipality o s nvelope endiente 0 social+ambiental) - LICITACI re (No documento f Guapi ON PUBLICA NACIONAL - LPN estándar del Banc o) Documento de Ad PTSP-BIRF8649-147 / Constr quisiciones con e Component 1. Water Supply ucción de la Fase III de acued nfoque nacional - and Basic Sanitation Improv Solicitud de oferta Single Stage - One E Ejecución p 2023-04-2 ucto GUAPI (técnico+ gestión IBRD / 86490 Posterior Open - National Proceso de un sob 2,110,000.00 0.00 2022-05-27 2022-05-29 2022-06-26 2022-07-26 2022-08-30 ements in the Municipality o s nvelope endiente 8 social+ambiental) - LICITACI re (No documento f Guapi ON PUBLICA NACIONAL - LPN estándar del Banc o) Documento de Ad Component 1. Water Supply quisiciones con e PTSP-BIRF8649-152 / Constr and Basic Sanitation Improv Solicitud de oferta Single Stage - One E nfoque nacional - Ejecución p 2023-08-0 ucción obras cierre botadero IBRD / 86490 Posterior Open - National 557,000.00 0.00 2022-04-29 2022-05-01 2022-05-29 2022-06-28 2022-08-02 ements in the Municipality o s nvelope Proceso de un sob endiente 2 barrio El Olimpico GUAPI f Guapi re (No documento estándar del Banc o) Documento de Ad Component 2. Water Supply quisiciones con e PTSP-BIRF8649-153 / Constr and Basic Sanitation Improv Solicitud de oferta Single Stage - One E nfoque nacional - Ejecución p 2023-08-2 ucción de obra Fase 3 etapa IBRD / 86490 Posterior Open - National 9,950,000.00 0.00 2022-01-20 2022-01-22 2022-02-19 2022-03-21 2022-04-25 ements in the Municipality o s nvelope Proceso de un sob endiente 5 2 (PTAP) f Tumaco re (No documento estándar del Banc o) Documento de Ad Component 2. Water Supply quisiciones con e PTSP-BIRF8649-154 / Constr and Basic Sanitation Improv Solicitud de oferta Single Stage - One E nfoque nacional - Ejecución p 2023-09-2 ucción de obra Fase 4 E1 (ob IBRD / 86490 Posterior Open - National 4,820,000.00 0.00 2022-02-16 2022-02-18 2022-03-18 2022-04-17 2022-05-22 ements in the Municipality o s nvelope Proceso de un sob endiente 1 ras Morro) f Tumaco re (No documento estándar del Banc o) Documento de Ad Component 2. Water Supply quisiciones con e PTSP-BIRF8649-155 / Constr and Basic Sanitation Improv Solicitud de oferta Single Stage - One E nfoque nacional - 2023-09-2 ucción acueducto - Fase 4 E2 IBRD / 86490 Posterior Open - National 740,000.00 0.00 Cancelado 2022-02-16 2022-02-18 2022-03-18 2022-04-17 2022-05-22 ements in the Municipality o s nvelope Proceso de un sob 1 (Paso de aguas claras) f Tumaco re (No documento estándar del Banc o) Documento de Ad PTSP-BIRF8649-163 / Constr Component 1. Water Supply quisiciones con e ucción alcantarillado GUAPI - and Basic Sanitation Improv Solicitud de oferta Single Stage - One E nfoque nacional - 14,500,000.0 Ejecución p 2024-12-0 IBRD / 86490 Posterior Open - National 0.00 2023-01-10 2023-01-12 2023-02-09 2023-03-11 2023-04-15 implementación alcantarillad ements in the Municipality o s nvelope Proceso de un sob 0 endiente 3 o Condominial f Guapi re (No documento estándar del Banc o) Documento de Ad PTSP-BIRF8649-165 / Constr Component 2. Water Supply quisiciones con e ucción alcantarillado Tumaco and Basic Sanitation Improv Solicitud de oferta Single Stage - One E nfoque nacional - 14,800,000.0 Ejecución p 2024-07-1 (obras derivadas del ajuste al IBRD / 86490 Posterior Open - National 0.00 2023-02-10 2023-02-12 2023-03-12 2023-04-11 2023-05-16 ements in the Municipality o s nvelope Proceso de un sob 0 endiente 8 Plan Maestro de Alcantarillad f Tumaco re (No documento o) estándar del Banc o) Documento de Ad Component 2. Water Supply quisiciones con e PTSP-BIRF8649-166 / Constr and Basic Sanitation Improv Solicitud de oferta Single Stage - One E nfoque nacional - 14,800,000.0 Ejecución p 2024-01-0 ucción piloto alcantarillado C IBRD / 86490 Posterior Open - National 0.00 2022-09-30 2022-10-02 2022-10-30 2022-11-29 2023-01-03 ements in the Municipality o s nvelope Proceso de un sob 0 endiente 3 ondominial Tumaco f Tumaco re (No documento estándar del Banc o) Documento de Ad PTSP-BIRF8649-149 / Constr Component 1. Water Supply quisiciones con e ucción del centro de restaura and Basic Sanitation Improv Solicitud de oferta Single Stage - One E nfoque nacional - Ejecución p 2023-01-0 ción ambiental CRAU - LICITA IBRD / 86490 Posterior Open - National 430,000.00 0.00 2022-01-12 2022-01-17 2022-02-28 2022-03-30 2022-05-04 ements in the Municipality o s nvelope Proceso de un sob endiente 5 CION PUBLICA NACIONAL - LP f Guapi re (No documento N estándar del Banc o) PTSP-BIRF-8649-213 / Optimi zación y ampliación del siste ma de acueducto de la cabec Component 1. Water Supply Solicitud de Cotiz era urbana del municipio de and Basic Sanitation Improv Solicitud de cotiza Single Stage - One E ación (no docume Ejecución p 2024-03-2 IBRD / 86490 Posterior Open - National 1,370,571.00 0.00 2023-07-29 2023-09-23 Guapi departamento del Cau ements in the Municipality o ciones nvelope nto estándar del endiente 1 ca Etapa I: Terminación de o f Guapi Banco) bras en la captación, aducció n, tratamiento y almacenami ento de agua potable. PTSP-BIRF-8649-214 / Optimi zación y ampliación del siste Component 1. Water Supply Solicitud de Cotiz ma de acueducto de la cabec and Basic Sanitation Improv Solicitud de cotiza Single Stage - One E ación (no docume Ejecución p 2024-03-2 era urbana del municipio de IBRD / 86490 Posterior Open - National 2,535,625.00 0.00 2023-07-29 2023-09-23 ements in the Municipality o ciones nvelope nto estándar del endiente 1 Guapi Departamento del Cau f Guapi Banco) ca Etapa I: Terminación de O bras en las Redes de Distribu ción Sectores 1 y 2 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-092 / Adquisi ción de un (1) Vehículo Comp Component 2. Water Supply actador Para La Prestación D and Basic Sanitation Improv Solicitud de oferta Single Stage - One E IBRD / 86490 Posterior Open - National 154,000.00 102,817.39 Firmado 2019-10-28 2019-11-29 2019-11-06 2019-12-18 2020-01-21 2020-01-17 2020-03-30 2020-02-21 2020-07-22 2020-08-19 el Servicio Público De Aseo E ements in the Municipality o s nvelope n El Distrito De San Andrés D f Tumaco e Tumaco Departamento de Nariño PTSP-BIRF8649-094 / CARAC Component 3. Capacity Buil TERIZACIÓN DE AGUA CRUD ding and Institutional Streng A Y MEDICIÓN DE NIVEL ESTA Solicitud de cotiza Single Stage - One E IBRD / 86490 thening of Service Providers Posterior Open - National 13,800.00 11,563.31 Firmado 2019-11-02 2019-12-28 2021-01-28 2020-06-25 TICO EN LOS POZOS Ccgua- ciones nvelope in the Municipalities of Guap 01 - Ccgua-02, MUNICIPIO GU i and Tum aco API, DEPARTAMENTO CAUCA PTSP-BIRF8649-095 / SONDA Component 3. Capacity Buil DE NIVEL PARA MEDICIÓN DE ding and Institutional Streng Solicitud de cotiza Single Stage - One E NIVEL ESTATICO EN LOS PO IBRD / 86490 thening of Service Providers Posterior Open - National 5,200.00 2,240.94 Firmado 2019-11-02 2019-12-28 2020-11-13 2020-06-25 ciones nvelope ZOS Ccgua-01 - Ccgua-02, M in the Municipalities of Guap UNICIPIO GUAPI, DEPARTAME i and Tum aco NTO CAUCA Page 2 Component 3. Capacity Buil PTSP-BIRF8649-118 / Adquiri ding and Institutional Streng Solicitud de cotiza Single Stage - One E r motobombas y accesorios h IBRD / 86490 Posterior Open - National 81,226.00 44,630.67 Firmado 2020-07-13 2020-09-07 2020-11-04 2020-10-07 thening of Service Providers ciones nvelope idráulicos in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-119 / Adquiri ding and Institutional Streng Solicitud de cotiza Single Stage - One E r tanques para almacenamie IBRD / 86490 Posterior Open - National 90,263.00 140,822.49 Firmado 2020-07-13 2020-09-07 2020-12-10 2020-10-07 thening of Service Providers ciones nvelope nto de agua in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-120 / Adquiri ding and Institutional Streng Solicitud de cotiza Single Stage - One E IBRD / 86490 Posterior Open - National 16,197.00 17,599.95 Firmado 2020-07-13 2020-09-07 2020-11-06 2020-10-22 r moto cargueros thening of Service Providers ciones nvelope in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-121 / Adquiri ding and Institutional Streng Solicitud de cotiza Single Stage - One E IBRD / 86490 Posterior Open - National 12,009.00 56,225.83 Firmado 2020-07-13 2020-09-07 2020-11-12 2020-10-22 r filtros purificadores de agua thening of Service Providers ciones nvelope in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-122 / Adquiri ding and Institutional Streng Solicitud de cotiza Single Stage - One E r estructuras de soporte met IBRD / 86490 Posterior Open - National 38,541.00 44,630.67 Firmado 2020-07-13 2020-09-07 2020-11-20 2020-10-07 thening of Service Providers ciones nvelope álicas in the Municipalities of Guap i and Tum aco PTSP-BIRF8649-160 / Adquisi Component 2. Water Supply Solicitud de oferta Single Stage - One E ción de segundo vehículo co IBRD / 86490 and Basic Sanitation Improv Posterior Open - National 141,000.00 0.00 Cancelado 2022-01-31 2022-02-09 2022-03-23 2022-04-22 2022-05-27 2022-11-23 s nvelope mpactador ements in the Municipality o f Tumaco PTSP-BIRF8649-168 / Adquisi Component 2. Water Supply ción de equipos resultado de and Basic Sanitation Improv Solicitud de oferta Single Stage - One E IBRD / 86490 Posterior Open - National 1,037,000.00 0.00 Cancelado 2022-11-16 2022-11-21 2023-01-02 2023-02-01 2023-03-08 2023-12-29 la consultoría reingenieria Bu ements in the Municipality o s nvelope cheli (bulldozer + pajarita) f Tumaco PTSP-BIRF8649-182 / Adquiri r un (1) vehículo compactado Component 2. Water Supply r de residuos sólidos para la and Basic Sanitation Improv Solicitud de oferta Single Stage - One E Ejecución pe IBRD / 86490 Posterior Open - National 136,476.00 0.00 2022-07-06 2022-07-11 2022-08-22 2022-09-21 2022-10-26 2023-04-24 prestación del servicio públic ements in the Municipality o s nvelope ndiente o de aseo en el Distrito de Sa f Tumaco n Andrés de Tumaco – Nariño . NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-053 / Progra Component 1. Water Supply Solicitud de cotiza Single Stage - One E ma de monitoreo de aguas s IBRD / 86490 and Basic Sanitation Improv Posterior Limited 17,242.00 0.00 Cancelado 2017-12-27 2018-02-21 2018-05-22 ciones nvelope ub-superficiales ements in the Municipality o f Guapi PTSP-BIRF8649-078 / ADQUI SICIÓN EN MODALIDAD DE A Component 3. Capacity Buil RRENDAMIENTO DE UN SOFT ding and Institutional Streng WARE INTEGRAL QUE PERMIT Solicitud de cotiza Single Stage - One E IBRD / 86490 thening of Service Providers Posterior Open - National 86,210.00 0.00 Cancelado 2019-11-18 2020-01-16 2020-10-30 A A AGUAS DE TUMACO SA E ciones nvelope in the Municipalities of Guap SP, EJECUTAR EN FORMA EFI i and Tum aco CIENTE EL CONTROL DE LOS PROCESOS COMERCIALES, C ONTABLES Y FINANCIEROS" CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Water Supply PTSP-BIRF8649-015 / Consul Selección basada IBRD / 86490 and Basic Sanitation Improv Posterior Open - National 112,024.00 101,622.79 Firmado 2017-07-01 2017-10-02 2017-07-22 2017-10-02 2017-09-04 2017-11-07 2017-10-02 2018-01-19 2017-11-01 2018-02-07 2017-12-06 2018-02-15 2018-01-10 2018-02-25 2018-08-08 toría Restauración Urbana en calidad y costo ements in the Municipality o f Guapi PTSP-BIRF8649-021 / Asisten Component 3. Capacity Buil Selección basada cia fortalecimiento institucio ding and Institutional Streng IBRD / 86490 Posterior en calificaciones d Open - National 235,000.00 78,605.00 Firmado 2018-06-01 2018-05-17 2018-06-22 2018-08-05 2018-08-31 2018-09-04 2018-12-03 2018-10-09 2018-12-03 2020-09-28 nal Aguas de Tumaco en el a thening of Service Providers e consultores rea urbana in the Municipalities of Guap i and Tum aco Component 4. Project Manag PTSP-BIRF8649-043 / Auditor Selección basada IBRD / 86490 ement and Environmental a Posterior Open - National 450,000.00 0.00 Cancelado 2017-08-01 2017-09-01 2017-10-15 2017-11-12 2017-12-12 2018-01-16 2018-02-20 2019-02-15 ia Externa en calidad y costo nd Social Management PTSP-BIRF8649-001 / Interve Component 2. Water Supply ntoría integral para obras de and Basic Sanitation Improv Selección basada Open - Internationa IBRD / 86490 Previa 6,266,775.00 0.00 Cancelado 2016-12-14 2017-01-28 2016-12-16 2017-03-14 2017-04-13 2017-05-13 2017-06-12 2017-07-07 2023-07-06 acueducto, alcantarillado y r ements in the Municipality o en calidad y costo l esiduos sólidos en el Municipi f Tumaco o de Tumaco. PTSP-BIRF8649-049 / Interve Component 2. Water Supply ntoria integral para obras de and Basic Sanitation Improv Selección basada Open - Internationa IBRD / 86490 Previa 5,762,334.24 4,364,033.42 Firmado 2017-12-20 2017-12-21 2018-01-12 2017-12-21 2018-02-25 2018-05-28 2018-03-25 2018-09-11 2018-04-24 2019-03-27 2018-05-29 2019-08-10 2018-07-03 2019-09-13 2022-07-02 acueducto y alcantarillado y ements in the Municipality o en calidad y costo l residuos sòlidos en el Munici f Tumaco pio de Tumaco PTSP-BIRF8649-062 / REALIZ AR LOS ESTUDIOS Y DISEÑOS PARA LA PLANTA DE TRATAM Component 1. Water Supply IENTO AGUAS RESIDUALES D and Basic Sanitation Improv Selección basada IBRD / 86490 Posterior Open - National 259,310.00 0.00 Cancelado 2018-06-15 2018-09-04 2018-07-06 2018-08-19 2018-09-16 2018-10-01 2018-10-19 2018-11-13 2019-06-11 EL MUNICIPIO DE GUAPI, DEP ements in the Municipality o en calidad y costo ARTAMENTO DEL CAUCA, EN f Guapi EL MARCO DEL FONDO PARA EL DESARROLLO DEL PLAN T ODOS SOMOS PAZCÍFICO PTSP-BIRF8649-041 / Asisten Component 3. Capacity Buil Selección basada cia fortalecimiento institucio ding and Institutional Streng IBRD / 86490 Posterior en calificaciones d Open - National 235,000.00 0.00 Cancelado 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2020-09-28 nal Aguas de Tumaco (para e thening of Service Providers e consultores l piloto de la politica en el are in the Municipalities of Guap a rural) i and Tum aco PTSP-BIRF8649-022 / Imple Component 4. Project Manag Selección basada mentacion del Plan de Inform IBRD / 86490 ement and Environmental a Posterior Open - National 400,000.00 0.00 Cancelado 2017-11-01 2018-09-13 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2018-11-09 en el menor costo acion, Comunicacion y Partici nd Social Management pacion PTSP-BIRF8649-016 / Interve Component 1. Water Supply ntoria Obras Alcantarillado, A and Basic Sanitation Improv Selección basada IBRD / 86490 Previa Open - National 2,333,451.00 0.00 Cancelado 2018-05-21 2018-06-11 2018-07-25 2018-08-22 2018-09-21 2018-10-26 2018-11-30 2019-11-30 cueducto y Residuos Solidos ements in the Municipality o en calidad y costo en Municipio de Guapi f Guapi Page 3 PTSP-BIRF8649-082 / Interve ntoría técnica, administrativa Component 1. Water Supply , financiera, legal, ambiental and Basic Sanitation Improv Selección basada Open - Internationa y social para los estudios, dis IBRD / 86490 Previa 2,900,000.00 1,741,709.58 Firmado 2019-07-10 2019-07-17 2019-08-02 2019-08-12 2019-09-15 2020-02-17 2019-10-13 2020-05-21 2019-11-12 2020-07-22 2019-12-17 2020-09-29 2020-01-21 2020-10-16 2024-01-20 ements in the Municipality o en calidad y costo l eños y obras de los sistemas f Guapi de acueducto y alcantarillado y proyectos de residuos sólid os del municipio de Guapi. PTSP-BIRF8649-096 / ACOMP Component 3. Capacity Buil AÑAR A EMGUAPI S.A.S. ESP ding and Institutional Streng EN LA OPERACIÓN DE LOS SE Selección basada IBRD / 86490 thening of Service Providers Posterior Open - National 662,000.00 377,390.55 Firmado 2019-10-31 2020-05-28 2019-11-21 2020-01-04 2020-07-24 2020-02-01 2020-09-22 2020-03-02 2020-10-29 2020-04-06 2020-11-23 2020-05-11 2021-03-04 2021-04-06 RVICIOS PÚBLICOS DE ACUE en calidad y costo in the Municipalities of Guap DUCTO, ALCANTARILLADO Y i and Tum aco ASEO Y ESTRUCTURACIÓN D EL SERVICIO PUBICOS DE AS EO. PTSP-BIRF8649-097 / Desarr ollar la Interventoría técnica, Component 3. Capacity Buil operativa, administrativa, co ding and Institutional Streng Selección basada mercial, financiera, contable, IBRD / 86490 thening of Service Providers Posterior Open - National 215,000.00 111,207.81 Firmado 2019-10-31 2020-01-28 2019-11-21 2020-01-04 2020-01-28 2020-02-01 2020-07-15 2020-03-02 2020-10-09 2020-04-06 2020-11-09 2020-05-11 2021-01-28 2021-05-11 en calidad y costo ambiental, social y jurídica al in the Municipalities of Guap proyecto de acompañamient i and Tum aco o a la empresa E guapi S.A. E SP. En el municipio de Guapi – Cauca. PTSP-BIRF8649-077 / INTERV ENTORÍA TÉCNICA, ADMINIST RATIVA, FINANCIERA, CONTA Component 3. Capacity Buil BLE, AMBIENTAL, SOCIAL Y JU ding and Institutional Streng Selección basada RÍDICA PARA LA "CONSULTO IBRD / 86490 thening of Service Providers Posterior Open - National 211,800.00 0.00 Cancelado 2019-04-30 2019-10-01 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 en calidad y costo RÍA DE ACOMPAÑAMIENTO E in the Municipalities of Guap N LA OPERACIÓN DE LOS SER i and Tum aco VICIOS PÚBLICOS DE ACUED UCTO, ALCANTARILLADO Y A SEO PARA EMGUAPI SAS ESP PTSP-BIRF8649-079 / FORTA Component 3. Capacity Buil LECIMIENTO Y ACOMPAÑAMI ding and Institutional Streng ENTO EN LA OPERACIÓN DE Selección basada IBRD / 86490 thening of Service Providers Posterior Open - National 1,380,000.00 0.00 Cancelado 2019-04-30 2019-10-01 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 LOS SERVICIOS PÚBLICOS DE en calidad y costo in the Municipalities of Guap ACUEDUCTO, ALCANTARILLA i and Tum aco DO Y ASEO DEL OPERADOR DE GUAPI - FASE I, II Y III PTSP-BIRF8649-056 / Consul Component 1. Water Supply toría de Diseño de la Planta d and Basic Sanitation Improv Selección basada e Tratamiento de Aguas de R IBRD / 86490 Posterior Open - National 141,300.00 0.00 Cancelado 2018-05-02 2019-09-27 2018-05-23 2018-07-06 2018-08-03 2018-09-02 2018-10-07 2018-11-11 2019-11-11 ements in the Municipality o en calidad y costo esiduales para el Sistema de f Guapi Alcantarillado del Municipio d e Guapi Component 3. Capacity Buil PTSP-BIRF8649-020 / Asegur ding and Institutional Streng Selección basada amiento en la prestación de l IBRD / 86490 Posterior Open - National 1,800,000.00 0.00 Cancelado 2018-06-01 2019-09-27 2018-06-22 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 thening of Service Providers en calidad y costo os servicios públicos Guapi. in the Municipalities of Guap i and Tum aco PTSP-BIRF8649-112 / Auditor ía a los Estados Financieros d Component 4. Project Manag Selección basada e Propósito Especial de Proye IBRD / 86490 ement and Environmental a Posterior Open - National 31,050.00 0.00 Cancelado 2020-05-15 2020-05-14 2020-06-05 2020-07-19 2020-08-16 2020-09-15 2020-10-20 2020-11-24 2021-04-23 en el menor costo ctos Financiados por el Banc nd Social Management o Mundial a través de présta mos PTSP-BIRF8649-137 / Consul toría para realizar el ajuste y complementación a los estud Component 1. Water Supply Selección basada ios y diseños de las Etapas II and Basic Sanitation Improv IBRD / 86490 Posterior en calificaciones d Open - National 77,860.00 109,528.65 Firmado 2021-04-29 2021-05-10 2021-05-20 2021-06-18 2021-07-21 2021-07-08 2021-08-10 2021-08-12 2022-03-06 2021-12-12 y III del proyecto denominad ements in the Municipality o e consultores o “OPTIMIZACIÓN Y AMPLIACI f Guapi ÓN DEL SISTEMA DE ACUEDU CTO DE LA CABECERA MUNIC IPAL DE GUAPI, CAUCA”. PTSP-BIRF8649-142 / ESTRU CTURACIÓN DE UN NUEVO E Component 3. Capacity Buil SQUEMA DE PRESTACIÓN DE ding and Institutional Streng Selección basada LOS SERVICIOS PÚBLICOS DE IBRD / 86490 thening of Service Providers Posterior Open - National 334,200.00 0.00 En ejecución 2021-09-28 2021-09-29 2021-10-19 2021-11-17 2021-12-15 2021-12-30 2022-01-28 2022-03-04 2023-02-02 en calidad y costo ACUEDUCTO Y ALCANTARILL in the Municipalities of Guap ADO EN EL MUNICIPIO DE SA i and Tum aco N ANDRÉS DE TUMACO, DEP ARTAMENTO DE NARIÑO PTSP-BIRF8649-156 / Consul Component 2. Water Supply toria de ajustes de estudios y and Basic Sanitation Improv Selección basada Ejecución pendien IBRD / 86490 Posterior Open - National 360,000.00 0.00 2022-01-20 2022-02-10 2022-03-11 2022-04-08 2022-04-23 2022-05-08 2022-06-12 2023-02-15 diseños Plan Maestro de alca ements in the Municipality o en calidad y costo te ntarillado TUMACO f Tumaco PTSP-BIRF8649-164 / Servici Component 3. Capacity Buil os resultado de consultoría d ding and Institutional Streng Selección basada Ejecución pendien IBRD / 86490 Posterior Open - National 1,700,000.00 0.00 2022-02-24 2022-03-17 2022-04-10 2022-05-08 2022-05-23 2022-06-17 2022-07-22 2023-07-22 e fortalecimiento instituciona thening of Service Providers en calidad y costo te l y el tema de aprovechamie in the Municipalities of Guap nto i and Tum aco PTSP-BIRF8649-167 / Consul Component 2. Water Supply Selección basada Open - Internationa toria de estudios y diseños n IBRD / 86490 and Basic Sanitation Improv Posterior 489,000.00 0.00 Cancelado 2022-06-15 2022-07-06 2022-08-19 2022-09-16 2022-10-16 2022-11-20 2022-12-25 2023-12-25 en calidad y costo l uevo relleno sanitario ements in the Municipality o f Tumaco PTSP-BIRF8649-161 / Ejecuci Component 3. Capacity Buil ón - Fase II. Acompañamient ding and Institutional Streng o en la recepción y operación Selección basada Open - Internationa Ejecución pendien IBRD / 86490 thening of Service Providers Posterior 461,000.00 0.00 2022-02-16 2022-03-09 2022-04-22 2022-05-20 2022-06-19 2022-07-24 2022-08-28 2023-08-28 de las obras de acueducto, al en calidad y costo l te in the Municipalities of Guap cantarillado. Diseño, estructu i and Tum aco ración e implementación de l a operación del SPA PTSP-BIRF8649-159 / Consul Component 2. Water Supply Selección basada toría para inclusión social de IBRD / 86490 and Basic Sanitation Improv Posterior en calificaciones d Open - National 213,000.00 0.00 Cancelado 2022-04-27 2022-05-18 2022-07-01 2022-07-31 2022-09-04 2023-06-04 recicladores ements in the Municipality o e consultores f Tumaco PTSP-BIRF8649-158 / Consul Component 2. Water Supply Selección basada toría de estudios y diseños M IBRD / 86490 and Basic Sanitation Improv Posterior en calificaciones d Open - National 285,000.00 0.00 Cancelado 2022-01-20 2022-02-10 2022-02-25 2022-03-12 2022-04-16 2022-10-20 ineria Bucheli TUMACO ements in the Municipality o e consultores f Tumaco PTSP-BIRF8649-151 / Consul Component 1. Water Supply Selección basada Ejecución pendien toría de estudios y diseños ci IBRD / 86490 and Basic Sanitation Improv Posterior en calificaciones d Open - National 245,000.00 0.00 2022-03-16 2022-04-06 2022-05-05 2022-05-25 2022-06-27 2023-02-27 te erre botadero barrio El Olimp ements in the Municipality o e consultores ico GUAPI f Guapi PTSP-BIRF8649-150 / Consul Component 1. Water Supply Selección basada toría para aprovechamiento IBRD / 86490 and Basic Sanitation Improv Posterior en calificaciones d Open - National 278,000.00 0.00 En ejecución 2022-01-17 2022-02-21 2022-02-07 2022-03-08 2022-03-28 2022-04-30 2023-01-31 de residuos orgánicos ements in the Municipality o e consultores f Guapi PTSP-BIRF8649-157 / Consul Component 2. Water Supply Selección basada toria de diseños de ingenierí and Basic Sanitation Improv Ejecución pendien IBRD / 86490 Posterior en calificaciones d Open - National 155,000.00 0.00 2022-02-17 2022-03-10 2022-03-25 2022-04-09 2022-05-14 2022-09-15 a y proyecto social alcantarill ements in the Municipality o te e consultores ado condominial Tumaco f Tumaco Page 4 PTSP-BIRF8649-162 / Ejecuci Component 3. Capacity Buil ón - Fase III. Acompañamient ding and Institutional Streng Selección basada Ejecución pendien o en el diseño e implementac IBRD / 86490 thening of Service Providers Posterior en calificaciones d Open - National 248,000.00 0.00 2023-01-18 2023-02-08 2023-03-24 2023-04-23 2023-05-28 2023-10-28 te ión del sistema de seguimien in the Municipalities of Guap e consultores to y monitoreo de la operació i and Tum aco n PTSP-BIRF8649-169 / INTERV ENTORÍA PARA LA CONSULTO RÍA QUE TIENE COMO OBJET Component 3. Capacity Buil O LA “ESTRUCTURACIÓN DE ding and Institutional Streng Selección basada UN NUEVO ESQUEMA DE PRE IBRD / 86490 thening of Service Providers Posterior en calificaciones d Open - National 78,000.00 0.00 En ejecución 2022-01-21 2022-02-04 2022-02-11 2022-03-12 2022-04-01 2022-05-06 2023-05-05 STACIÓN DE LOS SERVICIOS in the Municipalities of Guap e consultores PÚBLICOS DE ACUEDUCTO Y i and Tum aco ALCANTARILLADO EN EL MU NICIPIO DE SAN ANDRÉS DE TUMACO, DEPARTAMENTO D E NARIÑO”. PTSP-BIRF8649-170 / REALIZ AR LOS ESTUDIOS PARA LA C ONCEPCIÓN DE UN SISTEMA CONDOMINIAL Component 1. Water Supply DE ALCANTARILLADO SANITA and Basic Sanitation Improv Selección basada Open - Internationa IBRD / 86490 Posterior 408,000.00 0.00 En ejecución 2022-02-14 2022-02-09 2022-03-07 2022-02-17 2022-04-05 2022-05-03 2022-05-18 2022-06-22 2022-07-27 2023-03-24 RIO Y DISEÑO DE PROYECTO ements in the Municipality o en calidad y costo l S BÁSICOS PARA SU f Guapi IMPLEMENTACIÓN EN LA CAB ECERA MUNICIPAL DE GUAPI, DEPARTAMENTO DEL CAUCA. PTSP-BIRF8649-183 / Realiza r la actualización y ajuste del Estudio de evaluación de imp Component 2. Water Supply Selección basada acto ambiental y social EIAS and Basic Sanitation Improv IBRD / 86490 Posterior en calificaciones d Open - National 61,352.00 0.00 En ejecución 2022-07-11 2022-07-15 2022-08-01 2022-09-14 2022-10-14 2022-11-18 2023-05-17 para la optimización del relle ements in the Municipality o e consultores no sanitario de Tumaco de ac f Tumaco uerdo con lo requerido por la s salvaguardas ambientales y sociales de Banco Mundial. PTSP-BIRF8649-143 / CONSU LTORÍA PARA REALIZAR LA A CTUALIZACIÓN, AJUSTE Y CO MPLEMENTACIÓN DE LOS ES Component 1. Water Supply TUDIOS Y DISEÑOS EXISTENT and Basic Sanitation Improv Selección basada IBRD / 86490 Posterior Open - National 363,000.00 0.00 Cancelado 2021-10-18 2021-11-08 2021-12-22 2022-01-19 2022-02-18 2022-03-25 2022-04-29 2023-01-04 ES DE ALCANTARILLADO SAN ements in the Municipality o en calidad y costo ITARIO Y REALIZAR LOS ESTU f Guapi DIOS PARA LA CONCEPCIÓN DE UN SISTEMA CONDOMINIA L DE ALCANTARILLADO SANI TARIO Y DISEÑO DE PROYECT OS PTSP-BIRF8649-148 / Consul toría de ajuste y complement Component 1. Water Supply ación del plan maestro de alc and Basic Sanitation Improv Selección basada IBRD / 86490 Posterior Open - National 359,000.00 0.00 Cancelado 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-05-30 antarillado + diseños de inge ements in the Municipality o en calidad y costo niería + proyecto social alca f Guapi ntarillado condominial Guapi INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-010 / Apoyar el componente social, en el D epartamento del Cauca en la Component 4. Project Manag implementaciòn y ejecuciòn IBRD / 86490 ement and Environmental a Posterior Individual Open 21,450.78 16,386.55 Finalizado 2017-05-11 2017-08-16 2017-06-05 2017-06-15 2017-09-06 2017-07-05 2017-09-18 2018-07-05 2018-09-17 del FDPTSP que adelanta co nd Social Management mo entidad ejecutora la Unid ad Nacional para la Gestiòn d el Riesgo de Desastres. PTSP-BIRF8649-009 / Liderar el componente social, en la i mplementación y ejecución d Component 4. Project Manag el Fondo para el Desarrollo d IBRD / 86490 ement and Environmental a Posterior Individual Open 82,299.37 62,869.64 Finalizado 2017-05-11 2017-08-28 2017-06-11 2017-06-21 2017-09-18 2018-07-01 2017-09-18 2018-12-28 2018-09-18 el Plan Todos Somos Pazcífic nd Social Management o que adelanta como entidad ejecutora la Unidad Nacional para la Gestión del Riesgo de Desastres. PTSP-BIRF8649-007 / Brindar apoyo al FTSP que adelanta c omo entidad ejecutora la Uni dad Nacional para la Gestión Component 4. Project Manag del Riesgo de Desastres, en l IBRD / 86490 ement and Environmental a Posterior Individual Open 48,873.76 36,452.16 Firmado 2017-06-01 2017-05-22 2017-06-16 2017-07-01 2017-06-19 2017-07-21 2017-06-29 2018-07-21 a viabilización de proyectos d nd Social Management el componente de Agua y Sa neamiento Básico, ante el Mi nisterio de Vivienda, Ciudad y Territorio - MVCT PTSP-BIRF8649-006 / Brindar apoyo al FTSP en la coordina ción de las acciones y activid Component 4. Project Manag ades al interior del MVCT rela IBRD / 86490 ement and Environmental a Posterior Individual Open 56,033.61 40,456.30 Firmado 2017-06-01 2018-04-18 2017-06-16 2017-06-21 2018-05-03 2017-07-02 2018-05-18 2018-07-02 cionadas con el crédito para nd Social Management dar respuesta a los requerimi entos de la Banca Multilatera l y las entidades del gobierno nacional PTSP-BIRF8649-008 / Apoyar el componente social, en el D epartamento de Nariño en la implementación y ejecución Component 4. Project Manag del Fondo para el Desarrollo IBRD / 86490 ement and Environmental a Posterior Individual Open 21,450.78 1,660.60 Firmado 2017-05-18 2017-08-22 2017-06-11 2017-06-26 2017-09-12 2017-07-16 2018-04-03 2018-07-16 del Plan Todos Somos Pazcífi nd Social Management co que adelanta como entida d ejecutora la Unidad Nacion al para la Gestión del Riesgo de Desastres. Component 4. Project Manag PTSP-BIRF8649-024 / Apoyo IBRD / 86490 ement and Environmental a Posterior Individual Open 17,908.97 12,960.77 Finalizado 2017-05-16 2017-03-22 2017-07-04 2017-07-25 2017-05-19 2017-08-29 2017-05-19 2018-02-25 2018-05-18 Administrativo (nivel técnico) nd Social Management Component 4. Project Manag PTSP-BIRF8649-028 / Lider d IBRD / 86490 ement and Environmental a Posterior Individual Direct 99,507.79 63,711.53 Finalizado 2017-03-01 2017-03-01 2017-03-11 2017-04-01 2017-03-06 2017-05-06 2017-03-18 2017-11-02 2018-03-17 e Adquisiciones nd Social Management Component 4. Project Manag PTSP-BIRF8649-029 / Especi IBRD / 86490 ement and Environmental a Posterior Individual Open 70,938.36 48,197.86 Finalizado 2017-04-01 2017-03-20 2017-05-20 2017-03-22 2017-06-10 2017-04-03 2017-07-15 2017-04-06 2018-01-11 2018-04-05 alista Adquisiciones nd Social Management Page 5 Component 4. Project Manag PTSP-BIRF8649-033 / Lider A IBRD / 86490 ement and Environmental a Posterior Individual Direct 93,771.65 61,167.00 Firmado 2017-04-01 2017-03-22 2017-04-11 2017-03-24 2017-05-02 2017-03-28 2017-06-06 2017-04-06 2017-12-03 mbiental nd Social Management Component 4. Project Manag PTSP-BIRF8649-034 / Especi IBRD / 86490 ement and Environmental a Posterior Individual Open 56,458.32 36,452.16 Finalizado 2017-06-01 2017-08-01 2017-07-20 2017-08-08 2017-08-10 2017-08-15 2017-09-14 2017-04-04 2018-03-13 2018-04-03 alista ambiental nd Social Management Component 4. Project Manag PTSP-BIRF8649-035 / Lider C IBRD / 86490 ement and Environmental a Posterior Individual Direct 99,507.79 61,167.00 Firmado 2017-03-01 2017-03-02 2017-03-11 2017-04-01 2017-03-13 2017-05-06 2017-03-18 2017-11-02 omponente Agua nd Social Management Component 4. Project Manag PTSP-BIRF8649-036 / Especi IBRD / 86490 ement and Environmental a Posterior Individual Direct 63,844.53 41,645.62 Firmado 2017-04-01 2017-03-17 2017-04-11 2017-05-02 2017-03-22 2017-06-06 2018-04-05 2017-12-03 alista Proyectos Agua nd Social Management Component 4. Project Manag PTSP-BIRF8649-037 / Especi IBRD / 86490 ement and Environmental a Posterior Individual Open 56,033.61 36,452.16 Firmado 2017-06-01 2017-11-01 2017-07-20 2017-08-10 2017-11-20 2017-09-14 2017-11-22 2018-03-13 alista Proyectos RSU nd Social Management Component 4. Project Manag PTSP-BIRF8649-038 / Ingenie IBRD / 86490 ement and Environmental a Posterior Individual Open 35,053.71 16,386.55 Finalizado 2017-06-01 2017-07-19 2017-07-20 2017-08-10 2017-08-15 2017-09-14 2017-08-31 2018-03-13 2018-08-30 ro de apoyo (Agua Tumaco) nd Social Management Component 4. Project Manag PTSP-BIRF8649-039 / Ingenie IBRD / 86490 ement and Environmental a Posterior Individual Open 35,053.71 19,500.00 Finalizado 2017-06-01 2017-12-12 2017-07-20 2017-08-10 2018-01-03 2017-09-14 2017-09-27 2018-03-13 2018-09-26 ro de apoyo ( Agua Guapi) nd Social Management Component 4. Project Manag PTSP-BIRF8649-040 / Apoyo IBRD / 86490 ement and Environmental a Posterior Individual Open 16,742.07 12,960.77 Finalizado 2017-06-01 2017-06-28 2017-07-20 2017-09-12 2017-08-10 2017-09-18 2017-09-14 2017-09-22 2018-03-13 2018-09-21 Administrativo (lideres) nd Social Management PTSP-BIRF8649-023 / Coordi Component 4. Project Manag nación General - LUZ AMAND IBRD / 86490 ement and Environmental a Posterior Individual Direct 116,664.30 71,591.30 Firmado 2017-03-01 2017-03-08 2017-03-11 2017-03-16 2017-04-01 2017-03-10 2017-05-06 2017-03-18 2017-11-02 A PULIDO nd Social Management PTSP-BIRF8649-026 / Lider Fi Component 4. Project Manag nanciero - CLAUDIA AGUDEL IBRD / 86490 ement and Environmental a Posterior Individual Direct 99,507.79 63,711.53 Finalizado 2017-03-01 2017-02-15 2017-03-11 2017-04-01 2017-03-08 2017-05-06 2017-03-18 2017-11-02 2018-03-17 O SEDANO - Por continuidad nd Social Management de Servicios PTSP-BIRF8649-031 / Lider d Component 4. Project Manag e Planeación y Seguimiento - IBRD / 86490 ement and Environmental a Posterior Individual Direct 99,507.79 61,063.18 Firmado 2017-03-01 2017-03-08 2017-03-11 2017-03-10 2017-04-01 2017-03-13 2017-05-06 2017-03-18 2017-11-02 JUAN DE DIOS CISNEROS - - P nd Social Management or continuidad de Servicios PTSP-BIRF8649-032 / Especi Component 4. Project Manag alista Planeación y Seguimie IBRD / 86490 ement and Environmental a Posterior Individual Direct 67,749.98 41,574.93 Firmado 2017-03-01 2017-03-08 2017-03-11 2017-03-16 2017-04-01 2017-03-22 2017-05-06 2017-04-02 2017-11-02 nto - JULIAN ANDRES VALBUE nd Social Management NA - Por continuidad de Servi cios PTSP-BIRF8649-025 / Asisten Component 4. Project Manag te Financiero y Administrativ IBRD / 86490 ement and Environmental a Posterior Individual Direct 37,173.93 0.00 Cancelado 2017-07-03 2017-07-13 2017-08-03 2017-09-07 2018-09-02 o - BEATRIZ PARRA - Continui nd Social Management dad de Servicios PTSP-BIRF8649-048 / Tulio f Component 4. Project Manag uentes Especialista en Adqui IBRD / 86490 ement and Environmental a Posterior Individual Direct 49,242.00 46,194.37 Firmado 2017-11-02 2017-10-23 2017-11-07 2017-10-12 2017-11-08 2017-10-20 2017-11-10 2017-11-10 2018-11-09 siciones 2 nd Social Management Component 4. Project Manag PTSP-BIRF8649-046 / Especi IBRD / 86490 ement and Environmental a Posterior Individual Open 49,242.00 0.00 Cancelado 2017-10-31 2017-11-06 2017-11-09 2017-11-13 2018-11-13 alista Adquisiciones 2 nd Social Management Component 3. Capacity Buil PTSP-BIRF8649-044 / Especi ding and Institutional Streng alista Fortalecimiento Instituc IBRD / 86490 Posterior Individual Open 49,242.00 47,560.97 Firmado 2017-08-18 2017-10-12 2017-09-01 2017-11-10 2017-09-03 2017-12-20 2017-09-17 2017-12-30 2018-09-12 thening of Service Providers ional in the Municipalities of Guap i and Tum aco PTSP-BIRF8649-51 / IEH GRU CON-Realizar los estudios y d iseños de los proyectos priori Component 2. Water Supply zados para la optimización y and Basic Sanitation Improv Selección directa ampliación del sistema de ac IBRD / 86490 Posterior Direct 792,345.00 708,875.23 Firmado 2017-12-18 2018-02-20 2017-12-31 2018-02-21 2018-01-15 2018-02-25 2019-01-10 ements in the Municipality o de consultores ueducto del municipio de Tu f Tumaco maco, departamento de Nari ño, en el marco del Fondo pa ra el Desarrollo del Plan Todo s Somos PAZcífico Component 4. Project Manag PTSP-BIRF8649-054 / KPMG- Selección directa IBRD / 86490 ement and Environmental a Posterior Direct 35,000.00 69,291.56 Firmado 2017-12-29 2018-04-04 2018-01-08 2018-04-05 2018-03-14 2018-04-13 2018-09-10 AUDITORIA EXTERNA de consultores nd Social Management PTSP-BIRF8649-057 / Antoni Component 1. Water Supply o Nieto - Director de Interven IBRD / 86490 and Basic Sanitation Improv Posterior Individual Direct 26,897.00 25,232.22 Firmado 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-19 2018-11-03 torìa ements in the Municipality o f Guapi PTSP-BIRF8649-058 / Ramiro Component 1. Water Supply Gutierrez. Especialista Electr IBRD / 86490 and Basic Sanitation Improv Posterior Individual Direct 6,771.00 6,351.73 Firmado 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-17 2018-11-03 o-mecànico de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-060 / Alvaro Component 1. Water Supply Bravo - Especialista Geotecni IBRD / 86490 and Basic Sanitation Improv Posterior Individual Direct 9,233.00 8,661.44 Firmado 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-17 2018-11-03 sta de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-059 / Eduard Component 1. Water Supply o Gòmez - Especialista Estruc IBRD / 86490 and Basic Sanitation Improv Posterior Individual Direct 9,233.00 0.00 Cancelado 2018-04-26 2018-04-27 2018-05-02 2018-05-07 2018-11-03 tural de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-061 / FERNA Component 1. Water Supply NDO VARGAS RODRÍGUEZ. E IBRD / 86490 and Basic Sanitation Improv Posterior Individual Direct 9,233.00 8,661.44 Firmado 2018-05-07 2018-05-04 2018-05-08 2018-05-11 2018-05-13 2018-06-08 2018-06-12 2018-06-08 2018-12-09 specialista Estructural de Int ements in the Municipality o erventoria. f Guapi PTSP-BIRF8649-011 / Apoyar el componente social, en el D epartamento del Chocò, en la Component 4. Project Manag implementaciòn y ejecuciòn IBRD / 86490 ement and Environmental a Posterior Individual Open 27,082.76 0.00 Cancelado 2017-04-07 2017-08-22 2017-05-02 2017-05-12 2017-06-01 2018-06-01 del FDPTSP que adelanta co nd Social Management mo entidad ejecutora la Unid ad Nacional para la Gestiòn d el Riesgo de Desastres. Page 6 PTSP-BIRF8649-012 / Apoyar el componente social, en el D epartamento del Valle en la i Component 4. Project Manag mplementaciòn y ejecuciòn d IBRD / 86490 ement and Environmental a Posterior Individual Open 27,082.76 0.00 Cancelado 2017-04-07 2017-05-02 2017-05-12 2017-06-01 2018-06-01 el FDPTSP que adelanta com nd Social Management o entidad ejecutora la Unidad Nacional para la Gestiòn del Riesgo de Desastres. Component 4. Project Manag PTSP-BIRF8649-030 / Apoyo IBRD / 86490 ement and Environmental a Posterior Individual Open 26,159.48 0.00 Cancelado 2017-06-30 2017-07-21 2017-07-23 2017-07-27 2018-07-22 en adquisiciones nd Social Management PTSP-BIRF8649-042 / Asisten Component 4. Project Manag te Financiero y Administrativ IBRD / 86490 ement and Environmental a Posterior Individual Open 37,173.93 0.00 Cancelado 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-06-06 o nd Social Management CO-UNGRD-87418-CS-INDV / Brindar apoyo jurídico en la g estión predial y catastral de l Component 1. Water Supply os bienes inmuebles que sea and Basic Sanitation Improv n necesarios para la viabiliza IBRD / 86490 Posterior Individual Open 7,763.00 7,763.00 Firmado 2018-11-30 2018-11-28 2019-01-18 2019-02-08 2019-02-05 2019-03-15 2019-02-05 2019-09-11 ements in the Municipality o ción de los proyectos que se f Guapi ejecutan en el marco del Fon do para el Desarrollo del Plan Todos Somos Pazcífico, que a delanta como entidad PTSP-BIRF8649-063 / Liderar el componente de Agua y Sa neamiento Básico, en la impl Component 4. Project Manag ementación y ejecución del F IBRD / 86490 ement and Environmental a Posterior Individual Open 34,200.00 34,200.00 Firmado 2018-12-26 2019-02-18 2019-02-13 2019-03-06 2019-04-04 2019-04-10 2019-04-08 2019-10-07 ondo para el Desarrollo del Pl nd Social Management an Todos Somos Pazcífico qu e adelanta como entidad eje cutora la Unidad Nacional pa ra la Gestión del Riesgo de D esastres. PTSP-BIRF8649-072 / Especi Component 4. Project Manag alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Posterior Individual Direct 53,560.00 26,780.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-15 2019-03-18 2019-03-18 2020-03-12 ontratación Pilar Valero nd Social Management PTSP-BIRF8649-073 / Especi Component 4. Project Manag alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Posterior Individual Direct 53,560.00 53,560.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-15 2019-03-15 2020-03-09 ontratación Tulio Fuentes nd Social Management PTSP-BIRF8649-075 / Especi Component 4. Project Manag alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Posterior Individual Direct 53,560.00 26,780.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-15 2019-03-18 2019-03-18 2020-03-12 ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-069 / Líder d Component 4. Project Manag e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-18 2020-03-12 ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-065 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d IBRD / 86490 ement and Environmental a Posterior Individual Direct 83,000.00 41,500.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 el Proyecto FTSP - Recontrata nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-067 / Líder A Component 4. Project Manag mbiental - Recontratación Al IBRD / 86490 ement and Environmental a Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 ejandra Catacoli nd Social Management PTSP-BIRF8649-068 / Líder Fi Component 4. Project Manag nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-02-25 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 udia Agudelo nd Social Management PTSP-BIRF8649-066 / Líder d Component 4. Project Manag e Planeación y Seguimiento - IBRD / 86490 ement and Environmental a Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-15 2020-03-12 Luis Ignacio Alfonso nd Social Management PTSP-BIRF8649-070 / Líder S Component 4. Project Manag ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Posterior Individual Direct 23,600.00 11,800.00 Firmado 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-18 2019-07-17 uiz nd Social Management PTSP-BIRF8649-080 / Especi Component 4. Project Manag alista Social para la Evaluaci IBRD / 86490 ement and Environmental a Posterior Individual Open 13,140.00 0.00 Cancelado 2019-04-12 2019-07-16 2019-04-29 2019-05-10 2019-05-20 2019-07-30 ón Social de los municipios d nd Social Management e Tumaco (Nariño) y Guapi ( Cauca) PTSP-BIRF8649-084 / Electro Mecanico - Realizar apoyo a l a Interventoría Integral de lo Component 1. Water Supply s contratos de Estudios y Dis and Basic Sanitation Improv IBRD / 86490 Posterior Individual Open 16,000.00 9,050.40 Firmado 2019-07-10 2019-06-21 2019-08-28 2019-09-27 2019-09-18 2019-09-25 2019-10-23 2019-10-01 2020-04-20 eños como interventor en los ements in the Municipality o aspectos eléctricos y mecáni f Guapi cos de los proyectos de prein versión priorizados en el com ponente de Agua y Saneamie nto Básico. PTSP-BIRF8649-081 / Direcci ón de Interventoría Integral d Component 1. Water Supply e Estudios y Diseños de los p and Basic Sanitation Improv IBRD / 86490 Posterior Individual Open 27,000.00 12,926.59 Firmado 2019-06-25 2019-07-26 2019-08-13 2019-09-10 2019-09-03 2019-10-01 2019-10-08 2019-10-12 2020-04-05 royectos de preinversión prio ements in the Municipality o rizados en el componente de f Guapi Agua y Saneamiento Básico en el marco del préstamo BIR F. Component 4. Project Manag PTSP-BIRF8649-085 / Líder d IBRD / 86490 ement and Environmental a Posterior Individual Open 20,000.00 25,517.85 Firmado 2019-06-21 2019-07-29 2019-08-09 2019-09-24 2019-08-30 2019-09-02 2019-10-04 2019-09-07 2020-04-01 e Seguridad FTSP nd Social Management PTSP-BIRF8649-086 / Líder S Component 4. Project Manag ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Posterior Individual Direct 47,200.00 39,330.50 Firmado 2019-07-11 2019-07-15 2019-07-12 2019-07-23 2019-07-12 2019-08-22 2019-07-18 2019-08-23 2020-03-17 uiz nd Social Management PTSP-BIRF8649-089 / Topogr afo - Prestación de servicios profesionales para la realizac Component 1. Water Supply ión de levantamientos topogr and Basic Sanitation Improv áficos requeridos para el san IBRD / 86490 Posterior Individual Open 13,800.00 9,943.53 Firmado 2019-08-26 2019-08-22 2019-10-14 2019-09-19 2019-11-04 2019-10-18 2019-12-09 2019-10-24 2020-03-08 ements in the Municipality o eamiento de los predios requ f Guapi eridos para la ejecución de lo s proyectos del Fondo para el Desarrollo del Plan Todos So mos PAZcífico. Page 7 PTSP-BIRF8649-090 / Catastr al - Brindar apoyo técnico cat astral y de avalúos en la gest Component 1. Water Supply ión predial de los bienes inm and Basic Sanitation Improv IBRD / 86490 Posterior Individual Open 27,600.00 8,438.74 Firmado 2019-08-26 2019-08-30 2019-10-14 2019-10-01 2019-11-04 2019-10-25 2019-12-09 2019-11-06 2020-06-08 uebles que sean necesarios p ements in the Municipality o ara la viabilización de los pro f Guapi yectos que se ejecutan en el marco del Fondo para el Des arrollo del Plan Todos Somos PAZcífico. PTSP-BIRF8649-091 / Apoyo jurídico en las gestiones juríd Component 1. Water Supply icas y administrativas que se and Basic Sanitation Improv requiera adelantar dentro del IBRD / 86490 Posterior Individual Open 16,000.00 12,098.26 Firmado 2019-08-26 2020-04-08 2019-10-14 2020-04-10 2019-11-04 2020-04-16 2019-12-09 2020-04-24 2020-06-08 ements in the Municipality o proceso de saneamiento, adq f Guapi uisición predial y reasentami ento de población, a través d e las modalidades de enajen ación PTSP-BIRF8649-088 / Gestor Component 1. Water Supply a Predial - Recontratación NI IBRD / 86490 and Basic Sanitation Improv Posterior Individual Direct 27,600.00 10,207.20 Firmado 2019-08-30 2019-09-02 2019-09-06 2019-12-09 2019-09-06 2020-01-31 2019-09-13 2020-02-01 2020-03-12 NFA LUCIA SANTANA ESCOBA ements in the Municipality o R. f Guapi Component 4. Project Manag PTSP-BIRF8649-027 / Especi IBRD / 86490 ement and Environmental a Posterior Individual Open 63,844.53 0.00 Cancelado 2017-04-01 2017-04-11 2017-05-20 2017-06-10 2017-07-15 2018-01-11 alista Financiero nd Social Management PTSP-BIRF8649-093 / JOHN O Component 4. Project Manag TALVARO CORTES - Especiali IBRD / 86490 ement and Environmental a Posterior Individual Direct 18,000.00 11,102.00 Firmado 2019-11-15 2019-11-25 2019-11-22 2020-01-02 2019-11-22 2020-01-02 2019-11-26 2020-01-03 2020-05-24 sta de Adquisiciones nd Social Management PTSP-BIRF8649-099 / Líder d Component 4. Project Manag e Planeación - JOAN NATALIE IBRD / 86490 ement and Environmental a Posterior Individual Direct 17,700.00 25,806.54 Firmado 2019-11-15 2019-11-25 2019-11-22 2019-12-05 2019-11-22 2019-12-19 2019-11-26 2019-12-28 2020-05-24 GARZON nd Social Management PTSP-BIRF8649-101 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d IBRD / 86490 ement and Environmental a Posterior Individual Direct 26,400.00 64,142.90 Firmado 2020-02-24 2020-03-03 2020-03-02 2020-03-09 2020-03-02 2020-03-12 2020-03-18 2020-03-19 2021-03-17 el Proyecto FTSP - Recontrata nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-102 / Líder A Component 4. Project Manag mbiental - Recontratación Al IBRD / 86490 ement and Environmental a Posterior Individual Direct 22,520.00 54,713.29 Firmado 2020-02-24 2020-03-03 2020-03-02 2020-03-10 2020-03-02 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ejandra Catacoli nd Social Management PTSP-BIRF8649-103 / Líder Fi Component 4. Project Manag nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Posterior Individual Direct 22,520.00 54,127.85 Firmado 2020-02-24 2020-03-03 2020-03-02 2020-03-10 2020-03-02 2020-03-12 2020-03-18 2020-03-19 2021-03-17 udia Agudelo nd Social Management PTSP-BIRF8649-104 / Líder d Component 4. Project Manag e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Posterior Individual Direct 22,520.00 54,713.29 Firmado 2020-02-24 2020-03-03 2020-03-02 2020-03-09 2020-03-02 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-105 / Líder d Component 4. Project Manag e Seguridad FTSP - WILSON L IBRD / 86490 ement and Environmental a Posterior Individual Direct 22,520.00 16,685.59 Firmado 2020-02-24 2020-03-02 2020-03-02 2020-03-04 2020-03-02 2020-03-11 2020-03-06 2020-03-24 2021-03-05 AVERDE FLÓREZ nd Social Management PTSP-BIRF8649-106 / Especi Component 4. Project Manag alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Posterior Individual Direct 17,050.00 41,402.62 Firmado 2020-02-25 2020-03-03 2020-03-03 2020-03-09 2020-03-03 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-107 / Especi Component 4. Project Manag alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Posterior Individual Direct 56,800.00 41,391.10 Firmado 2020-02-25 2020-03-03 2020-03-03 2020-03-09 2020-03-03 2020-03-12 2020-03-16 2020-03-17 2021-03-15 ontratación Tulio Jose Fuente nd Social Management s PTSP-BIRF8649-108 / Líder C Component 4. Project Manag omponente Agua y Saneamie IBRD / 86490 ement and Environmental a Posterior Individual Direct 37,523.00 53,829.69 Firmado 2020-03-24 2020-03-24 2020-03-28 2020-03-30 2020-04-01 2020-03-31 2020-04-07 2020-04-09 2021-04-07 nto Básico - Recontratación F nd Social Management ABIOLA IGUARAN ARAUJO PTSP-BIRF8649-110 / Liderar el componente social, en la i mplementación y ejecución d e los proyectos de agua, san Component 4. Project Manag eamiento y energía del Fond IBRD / 86490 ement and Environmental a Posterior Individual Direct 22,520.00 16,685.59 Firmado 2020-04-14 2020-04-15 2020-04-15 2020-04-03 2020-04-15 2020-04-20 2020-04-23 2020-04-24 2021-04-22 o para el Desarrollo del Plan nd Social Management Todos Somos PAZcífico finan ciados por la Banca Multilate ral que adelanta como entida d ejecutora la Unidad PTSP-BIRF8649-087 / Especi Component 4. Project Manag alista Social para la Evaluaci IBRD / 86490 ement and Environmental a Posterior Individual Open 13,140.00 0.00 Cancelado 2019-08-23 2019-08-30 2019-09-09 2019-09-27 2019-09-20 2019-09-30 2019-12-29 ón Social de los municipios d nd Social Management e Tumaco (Nariño) y Guapi ( Cauca) Component 4. Project Manag PTSP-BIRF8649-098 / KPMG- Selección directa IBRD / 86490 ement and Environmental a Posterior Direct 34,500.00 0.00 Cancelado 2019-11-25 2019-12-02 2019-11-30 2020-02-03 2020-08-01 AUDITORIA EXTERNA de consultores nd Social Management PTSP-BIRF8649-111 / “Realiz ar Los Estudios Y Diseños Par Component 1. Water Supply a La Construcción, Operación and Basic Sanitation Improv Selección directa , Clausura Y Post Clausura De IBRD / 86490 Posterior Direct 7,350.00 89,848.30 Firmado 2020-05-15 2020-05-14 2020-05-20 2020-06-12 2020-08-02 2020-12-17 2021-01-02 ements in the Municipality o de consultores l Centro De Restauración Am f Guapi biental Urbano – CRAU Del M unicipio De Guapi, Departam ento Del Cauca” PTSP-BIRF8649-113 / Especi alista de Planeación y Segui miento. - Brindar apoyo profe Component 4. Project Manag sional en la gestión de planifi IBRD / 86490 ement and Environmental a Posterior Individual Open 17,050.00 42,576.52 Firmado 2020-05-14 2020-05-22 2020-06-03 2020-05-25 2020-06-18 2021-05-27 2020-08-01 2021-05-28 2021-08-01 cación, monitoreo y seguimie nd Social Management nto a las actividades del Fon do para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8649-114 / Realiza r la evaluación de medio tér mino del PROYECTO DE INFR AESTRUCTURA PARA EL SUMI Component 4. Project Manag NISTRO DE AGUA Y SANEAMI IBRD / 86490 ement and Environmental a Posterior Individual Open 15,870.00 11,192.26 Firmado 2020-05-20 2020-05-20 2020-06-14 2020-06-30 2020-06-29 2020-07-15 2020-07-10 2020-08-16 2020-11-07 ENTO BÁSICO & PROVISIÓN nd Social Management DE SERVICIOS, en cumplimie nto de las condiciones establ ecidas en el Contrato de Prés tamo N° 8649-CO. Page 8 PTSP-BIRF8649-115 / Liderar la planificación, gestión, mon itoreo y seguimiento de las di ferentes herramientas de ges Component 4. Project Manag tión IBRD / 86490 ement and Environmental a Posterior Individual Open 22,520.00 0.00 Cancelado 2020-06-24 2020-06-22 2020-07-05 2020-07-25 2020-08-10 2021-08-10 establecidas para el cumplim nd Social Management iento de las metas y objetivo s del Fondo para el Desarroll o del Plan Todos Somos PAZcífico que a delanta como entidad ejecut PTSP-BIRF8649-116 / Auditor ora ía a los Estados Financieros d Component 4. Project Manag Selección directa e Propósito Especial de Proye IBRD / 86490 ement and Environmental a Posterior Direct 31,050.00 23,247.90 Firmado 2020-06-26 2020-06-22 2020-07-06 2020-07-01 2020-08-20 2020-09-26 2020-11-18 de consultores ctos Financiados por el Banc nd Social Management o Mundial a través de présta mos. PTSP-BIRF8649-117 / Liderar la planificación, gestión, mon itoreo y seguimiento de las di ferentes herramientas de ges Component 4. Project Manag tión establecidas para el cum IBRD / 86490 ement and Environmental a Posterior Individual Limited 22,520.00 56,302.02 Firmado 2020-06-23 2020-06-22 2020-06-28 2020-06-19 2020-07-08 2020-06-23 2020-07-28 2020-07-01 2021-07-28 plimiento de las metas y obje nd Social Management tivos del Fondo para el Desar rollo del Plan Todos Somos P AZcífico que adelanta como entidad ejecutora PTSP-BIRF8649-123 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP ECIAL Y ASEGURAMIENTO Component 4. Project Manag Selección directa RAZONABLE SOBRE LOS PRO IBRD / 86490 ement and Environmental a Posterior Direct 26,600.00 23,668.95 Firmado 2020-10-19 2020-11-05 2020-11-08 2020-11-19 2021-01-07 2021-02-20 2021-07-06 de consultores CESOS DE ADQUISICIONES D nd Social Management EL PROYECTO/PROGRAMA FI NANCIADO POR EL BID Y EL B ANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8649-124 / Líder C Component 4. Project Manag omponente Agua y Saneamie IBRD / 86490 ement and Environmental a Posterior Individual Direct 27,500.00 56,506.60 Firmado 2021-02-23 2021-02-25 2021-02-27 2021-04-07 2021-03-03 2021-04-07 2021-04-08 2021-04-09 2022-04-08 nto Básico - Recontratación F nd Social Management ABIOLA IGUARAN ARAUJO PTSP-BIRF8649-125 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d IBRD / 86490 ement and Environmental a Posterior Individual Direct 19,330.00 66,005.44 Firmado 2021-02-24 2021-02-25 2021-03-03 2021-03-17 2021-03-03 2021-03-16 2021-03-18 2021-03-19 2022-03-18 el Proyecto FTSP - Recontrata nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-126 / Líder d Component 4. Project Manag e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Posterior Individual Direct 16,500.00 56,090.91 Firmado 2021-02-24 2021-02-25 2021-03-03 2021-03-17 2021-03-03 2021-02-17 2021-03-18 2021-03-20 2022-03-17 ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-127 / Líder Fi Component 4. Project Manag nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Posterior Individual Direct 16,500.00 56,280.26 Firmado 2021-02-24 2021-02-25 2021-03-03 2021-03-16 2021-03-03 2021-03-12 2021-03-18 2021-03-19 2022-03-17 udia Agudelo nd Social Management PTSP-BIRF8649-128 / Líder S Component 4. Project Manag ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Posterior Individual Direct 16,500.00 56,643.71 Firmado 2021-02-24 2021-02-25 2021-02-25 2021-04-22 2021-02-25 2021-04-22 2021-04-23 2021-04-24 2022-04-22 uiz nd Social Management PTSP-BIRF8649-129 / Líder d Component 4. Project Manag e Seguridad FTSP -Recontrat IBRD / 86490 ement and Environmental a Posterior Individual Direct 16,500.00 56,090.91 Firmado 2021-02-24 2021-02-25 2021-03-03 2021-03-22 2021-03-03 2021-02-22 2021-03-22 2021-03-24 2022-03-21 ación WILSON LAVERDE FLÓ nd Social Management REZ PTSP-BIRF8649-130 / Especi Component 4. Project Manag alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Posterior Individual Direct 12,473.00 42,851.48 Firmado 2021-03-03 2021-03-15 2021-03-10 2021-03-17 2021-03-10 2021-03-17 2021-03-18 2021-03-19 2022-03-17 ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-132 / Especi Component 4. Project Manag alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Posterior Individual Direct 20,788.00 42,433.29 Firmado 2021-03-03 2021-03-15 2021-03-10 2021-03-12 2021-03-10 2021-03-15 2021-03-15 2021-03-19 2022-03-14 ontratación Tulio Jose Fuente nd Social Management s PTSP-BIRF8649-131 / Contra tación Líder Ambiental para l a ejecución y cumplimiento d Component 4. Project Manag Selección directa e los Marcos de Gestión Ambi IBRD / 86490 ement and Environmental a Posterior Direct 8,244.00 28,045.46 Firmado 2021-03-03 2021-03-05 2021-03-11 2021-03-05 2021-03-18 2021-03-17 2021-09-17 de consultores ental adoptados para la ejec nd Social Management ución del Fondo para el desar rollo del Plan Todos Somos P AZcífico - Fernando Rey PTSP-BIRF8649-133 / Especi alista de Planeación y Segui miento. - Brindar apoyo profe Component 4. Project Manag sional en la gestión de planifi IBRD / 86490 ement and Environmental a Posterior Individual Open 10,394.00 17,829.14 Firmado 2021-03-11 2021-03-15 2021-03-16 2021-03-24 2021-03-17 2021-03-24 2021-03-25 2021-03-27 2022-09-24 cación, monitoreo y seguimie nd Social Management nto a las actividades del Fon do para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8649-134 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Component 4. Project Manag Selección directa mplementación y ejecución d IBRD / 86490 ement and Environmental a Posterior Direct 8,244.00 0.00 Cancelado 2021-04-14 2021-04-24 2021-05-17 2021-11-16 de consultores e los componentes de Capaci nd Social Management dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico - Jorge Silva PTSP-BIRF8649-135 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Component 4. Project Manag mplementación y ejecución d IBRD / 86490 ement and Environmental a Posterior Individual Direct 8,244.00 28,321.85 Firmado 2021-04-15 2021-04-19 2021-04-23 2021-04-14 2021-04-26 2021-05-07 2021-05-17 2021-05-12 2021-11-16 e los componentes de Capaci nd Social Management dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico para el desarrollo de l Plan Todos Somos PAZcífico - Jorge Silva. PTSP-BIRF8649-136 / Especi Component 4. Project Manag alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Posterior Individual Direct 12,473.00 42,851.48 Firmado 2021-04-22 2021-04-22 2021-04-26 2021-05-26 2021-04-26 2021-05-04 2021-05-04 2021-05-07 2022-05-03 ontratación JOHN MAURICIO nd Social Management OTÁLVARO CORTÉS PTSP-BIRF8649-138 / Líder d Component 4. Project Manag e Planeación - JOAN NATALIE IBRD / 86490 ement and Environmental a Posterior Individual Direct 16,490.00 56,643.71 Firmado 2021-06-04 2021-06-11 2021-06-11 2021-06-22 2021-06-11 2021-06-23 2021-06-30 2021-07-01 2022-06-29 GARZON nd Social Management Page 9 PTSP-BIRF8649-139 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP ECIAL Y ASEGURAMIENTO Component 4. Project Manag Selección directa RAZONABLE SOBRE LOS PRO IBRD / 86490 ement and Environmental a Posterior Direct 26,238.00 21,580.38 Firmado 2021-09-06 2021-09-15 2021-09-26 2021-10-04 2021-12-22 2022-02-03 2022-07-29 de consultores CESOS DE ADQUISICIONES D nd Social Management EL PROYECTO/PROGRAMA FI NANCIADO POR EL BID Y EL B ANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8649-140 / Líder A Component 4. Project Manag mbiental FTSP - Recontrataci IBRD / 86490 ement and Environmental a Posterior Individual Direct 8,902.00 27,880.05 Firmado 2021-09-09 2021-09-09 2021-09-09 2021-09-10 2021-09-20 2021-09-20 2021-09-23 2021-09-24 2022-03-22 ón Fernando Rey nd Social Management PTSP-BIRF8649-141 / Especi Component 4. Project Manag alista de Planeación y Segui IBRD / 86490 ement and Environmental a Posterior Individual Direct 22,425.00 41,939.36 Firmado 2021-09-09 2021-09-09 2021-09-17 2021-09-16 2021-09-17 2021-09-20 2021-09-27 2021-09-29 2022-09-26 miento FTSP - Recontratación nd Social Management Natalia García Medina PTSP-BIRF8649-144 / Líder d Component 3. Capacity Buil e Fortalecimiento Institucion ding and Institutional Streng IBRD / 86490 Posterior Individual Direct 17,805.00 55,760.11 Firmado 2021-10-19 2021-10-19 2021-10-19 2021-10-19 2021-10-26 2021-10-26 2021-11-11 2021-11-12 2022-11-10 al - Recontratación Jorge Silv thening of Service Providers a in the Municipalities of Guap i and Tum aco Component 4. Project Manag PTSP-BIRF8649-145 / Líder S IBRD / 86490 ement and Environmental a Posterior Individual Open 14,837.00 24,051.50 Firmado 2021-10-27 2021-10-27 2021-11-30 2022-03-16 2021-12-03 2022-03-17 2021-12-20 2022-04-10 2022-06-19 ocial FTSP nd Social Management PTSP-BIRF8649-171 / Líder d Component 1. Water Supply e Agua BM - Recontratación F IBRD / 86490 and Basic Sanitation Improv Posterior Individual Direct 31,342.00 57,727.68 Firmado 2022-03-04 2022-03-04 2022-03-04 2022-03-04 2022-03-24 2022-03-09 2022-04-08 2022-04-11 2023-04-07 abiola del Rosario Iguarán ements in the Municipality o f Guapi PTSP-BIRF8649-176 / Recont Component 4. Project Manag ratación Especialista de Adqu IBRD / 86490 ement and Environmental a Posterior Individual Direct 23,711.00 43,671.56 Firmado 2022-03-04 2022-03-04 2022-03-09 2022-03-04 2022-03-09 2022-03-04 2022-03-16 2022-03-19 2023-03-15 isiciones - Tulio José Fuentes nd Social Management PTSP-BIRF8649-172 / Recont Component 4. Project Manag ratación Directora Ejecutiva- IBRD / 86490 ement and Environmental a Posterior Individual Direct 22,046.00 62,078.79 Firmado 2022-03-04 2022-03-04 2022-03-11 2022-03-11 2022-03-11 2022-03-11 2022-03-18 2022-03-19 2023-03-17 Coordinadora General - Luz A nd Social Management manada Pulido PTSP-BIRF8649-173 / Recont Component 4. Project Manag ratación Líder de Adquisicion IBRD / 86490 ement and Environmental a Posterior Individual Direct 18,805.00 52,952.63 Firmado 2022-03-04 2022-03-04 2022-03-11 2022-03-11 2022-03-11 2022-03-11 2022-03-18 2022-03-21 2023-03-17 es - Élkin Pinilla nd Social Management PTSP-BIRF8649-174 / Recont Component 4. Project Manag ratación Líder Financiera - Cl IBRD / 86490 ement and Environmental a Posterior Individual Direct 18,805.00 53,292.14 Firmado 2022-03-04 2022-03-04 2022-03-11 2022-03-04 2022-03-11 2022-04-11 2022-03-18 2022-03-19 2023-03-17 audia Agudelo nd Social Management PTSP-BIRF8649-175 / Recont Component 4. Project Manag ratación Líder Ambiental - Fe IBRD / 86490 ement and Environmental a Posterior Individual Direct 9,403.00 26,646.07 Firmado 2022-03-04 2022-03-04 2022-03-04 2022-03-04 2022-03-15 2022-03-15 2022-03-23 2022-03-24 2022-09-22 rnando Rey nd Social Management PTSP-BIRF8649-177 / Recont Component 4. Project Manag ratación Especialista Financie IBRD / 86490 ement and Environmental a Posterior Individual Direct 14,226.00 40,315.98 Firmado 2022-03-04 2022-03-04 2022-03-11 2022-03-04 2022-03-11 2022-03-11 2022-03-18 2022-03-19 2023-03-17 ra - Lorena Peña nd Social Management PTSP-BIRF8649-178 / Recont Component 4. Project Manag ratación Líder de Seguridad - IBRD / 86490 ement and Environmental a Posterior Individual Direct 8,910.00 0.00 En ejecución 2022-04-26 2022-05-05 2022-05-02 2022-04-26 2022-05-02 2022-05-05 2022-11-04 Wilson Laverde nd Social Management PTSP-BIRF8649-180 / Liderar los procesos de adquisicione s que adelanta la Unidad Nac ional para la Gestión del Ries Component 4. Project Manag go de Desastres como entida IBRD / 86490 ement and Environmental a Posterior Individual Limited 17,900.00 0.00 Cancelado 2022-05-23 2022-05-27 2022-05-28 2022-06-15 2022-06-02 2022-06-17 2023-06-16 d ejecutora del Fondo para el nd Social Management Desarrollo del Plan Todos So mos PAZcífico, según las Polí ticas, normas y regulaciones del BID y Banco M. PTSP-BIRF8649-181 / Liderar la planificación, monitoreo, s eguimiento y gestión de los p réstamos del BID y el Banco Component 4. Project Manag Ejecución pendien Mundial, ejecutados por la U IBRD / 86490 ement and Environmental a Posterior Individual Direct 17,805.00 0.00 2022-06-16 2022-06-17 2022-06-24 2022-06-29 2023-06-29 te nidad Nacional para la Gestió nd Social Management n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo del Plan Todos Somos FTSP PTSP-BIRF8649-184 / Brindar apoyo profesional como Espe cialista de Adquisiciones en l Component 4. Project Manag os procesos que adelanta la IBRD / 86490 ement and Environmental a Posterior Individual Limited 20,979.00 0.00 En ejecución 2022-07-11 2022-07-19 2022-07-16 2022-08-06 2022-09-10 2023-03-09 Unidad Nacional para la Gesti nd Social Management ón del Riesgo de Desastres c omo entidad ejecutora del Fo ndo para el Desarrollo del Pla n Todos Somos PAZcífico. PTSP-BIRF8649-185 / Especi Component 4. Project Manag alista de Planeación y Segui IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 20,979.00 0.00 En ejecución 2022-08-30 2022-08-30 2022-08-30 2022-09-28 2022-09-28 2023-09-27 miento FTSP - Recontratación nd Social Management Natalia García Medina PTSP-BIRF8649-186 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Component 4. Project Manag Ejecución pendien el marco de los préstamos de IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 8,319.00 0.00 2022-09-19 2022-09-19 2022-10-07 2022-10-28 2023-04-26 te l BID y el Banco Mundial, ejec nd Social Management utados por la Unidad Naciona l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo PTSP-BIRF8649-187 / Coordi nar la implementación y sup ervisión de los préstamos del Component 4. Project Manag BID y el Banco Mundial, ejecu IBRD / 86490 ement and Environmental a Posterior Individual Open - National 19,506.00 0.00 Cancelado 2022-09-23 2022-09-20 2022-10-15 2022-10-17 2022-11-21 2023-05-20 tados por la Unidad Nacional nd Social Management para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico Page 10 PTSP-BIRF-8649-188 / Presta r los servicios jurídicos como especialista para los proceso s de adquisiciones del Fondo Component 4. Project Manag Ejecución pendien para el Desarrollo del Plan To IBRD / 86490 ement and Environmental a Posterior Individual Open - National 12,587.00 0.00 2022-10-10 2022-11-28 2022-12-19 2023-01-23 2023-10-23 te dos Somos PAZcífico que ade nd Social Management lanta como entidad ejecutora la Uni-dad Nacional para la G estión del Riesgo de Desastr es, en el marco PTSP-BIRF-8649-189 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP Component 4. Project Manag ECIAL Y ASEGURAMIENTO RA Selección directa Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Direct - National 28,410.00 0.00 2022-10-10 2022-10-16 2023-01-09 2023-05-05 ZONABLE SOBRE LOS PROCE de consultores te nd Social Management SOS DE ADQUISICIONES DEL PROYECTO/PROGRAMA FINA NCIADO POR EL BID Y EL BAN CO MUNDIAL A TRAVÉS DE P RÉSTAMOS - PTSP-BIRF-8649-190 / Coordi nar la implementación y sup ervisión de los préstamos del Component 4. Project Manag BID y el Banco Mundial, ejecu IBRD / 86490 ement and Environmental a Posterior Individual Limited 19,506.00 0.00 En ejecución 2022-10-14 2022-10-07 2022-10-19 2022-09-27 2022-11-09 2022-12-14 2023-06-12 tados por la Unidad Nacional nd Social Management para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico PTSP-BIRF-8649-191 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Component 4. Project Manag Ejecución pendien l Banco Mundial ejecutados p IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 5,826.00 0.00 2022-11-07 2022-11-17 2022-12-08 2023-01-12 2023-07-11 te or la Unidad Nacional para la nd Social Management Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PTSP-BIRF-8649-192 / Lidera r la planificación, estructurac ión, seguimiento y gestión de Component 3. Capacity Buil los proyectos de Capacidad y ding and Institutional Streng Ejecución pendien Fortalecimiento Institucional IBRD / 86490 thening of Service Providers Posterior Individual Direct - National 4,160.00 0.00 2022-11-11 2022-11-16 2022-12-07 2023-01-11 2023-07-10 te que hagan parte de los prést in the Municipalities of Guap amos del BID y el Banco Mun i and Tum aco dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Des PTSP-BIRF-8649-193 / Lidera r los procesos de adquisicion es que adelanta la Unidad Na cional para la Gestión del Rie Component 4. Project Manag sgo de Desastres como entid IBRD / 86490 ement and Environmental a Posterior Individual Open - National 16,639.00 0.00 Firmado 2022-11-11 2022-11-18 2022-12-19 2022-11-23 2023-01-09 2022-12-19 2023-02-13 2022-12-21 2023-08-12 ad ejecutora del Fondo para nd Social Management el Desarrollo del Plan Todos Somos PAZcífico, según las P olíticas, normas y regulacion es del BID y el Banc PTSP-BIRF-8649-194 / Lidera r las actividades relacionad as con protocolos y herrami Component 4. Project Manag entas de seguridad, para miti Selección directa Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Direct - National 4,160.00 0.00 2022-11-10 2022-11-19 2023-01-23 2023-07-22 gar las posibles amenazas o de consultores te nd Social Management riesgos en la ejecución de los proyectos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, q ue ejecuta la PTSP-BIRF8649-194 / Brindar apoyo profesional como espe cialista de planeación, monit oreo, seguimiento y gestión Component 4. Project Manag Ejecución pendien de los préstamos del Banco IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 23,731.00 0.00 2023-01-27 2023-02-01 2023-02-22 2023-03-29 2023-09-25 te Mundial, ejecutados por la U nd Social Management nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo d PTSP-BIRF8649-195 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Component 4. Project Manag Ejecución pendien el marco de los préstamos de IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 18,822.00 0.00 2023-01-27 2023-02-01 2023-02-22 2023-03-29 2023-09-25 te l BID y el Banco Mundial, ejec nd Social Management utados por la Unidad Naciona l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo PTSP-BIRF-8649-195 / Realiz ar apoyo como profesional es pecializado en los procesos c ontractuales y relaciones jurí Component 4. Project Manag Ejecución pendien dico negociales del Fondo pa IBRD / 86490 ement and Environmental a Posterior Individual Limited 14,239.00 0.00 2023-02-06 2023-02-11 2023-03-04 2023-04-08 2023-10-05 te ra el Desarrollo del Plan Todo nd Social Management s Somos PAZcífico - FTSP, cu ya entidad ejecutora es la Un idad Nacional para la Gestión del Riesgo de Des PTSP-BIRF-8649-196 / Brinda r apoyo profesional como Esp ecialista de Adquisiciones del préstamo 8649-CO en los pro Component 4. Project Manag Ejecución pendien cesos que adelanta la Unidad IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 39,885.00 0.00 2023-02-22 2023-03-04 2023-03-25 2023-04-29 2023-10-26 te Nacional para la Gestión del nd Social Management Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico, s PTSP-BIRF-8649-199 / Lidera r las actividades relacionadas con protocolos y herramienta s de seguridad, para mitigar l Component 4. Project Manag Selección directa as posibles amenazas o riesg IBRD / 86490 ement and Environmental a Posterior Direct - National 18,822.00 0.00 En ejecución 2023-03-13 2023-03-22 2023-03-22 2023-05-26 2023-11-22 de consultores os en la ejecución de los proy nd Social Management ectos que se desarrollan en e l marco de los préstamos del BID y el Banco Mundial, que ejecuta la Unida Page 11 PTSP-BIRF-8649-197 / TDR - Especialista Financiera en la gestión presupuestal y financ iera de los préstamos del BID Component 4. Project Manag Ejecución pendien y el Banco Mundial, ejecutad IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 14,239.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 te os por la Unidad Nacional par nd Social Management a la Gestión del Riesgo de De sastres como entidad ejecuto ra del Fondo para el Desarrol lo del Plan Todos PTSP-BIRF-8649-198 / TDR- L iderar la gestión presupuesta l y financiera de los préstamo s del BID y el Banco Mundial, Component 4. Project Manag Ejecución pendien ejecutados por la Unidad Nac IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 18,822.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 te ional para la Gestión del Ries nd Social Management go de Desastres como entida d ejecutora del Fondo para el Desarrollo del Plan Todos So mos PAZcífico. PTSP-BIRF-8649-201 / Lidera r la planificación, estructurac ión, seguimiento y gestión de Component 3. Capacity Buil los proyectos de Capacidad y ding and Institutional Streng Ejecución pendien Fortalecimiento Institucional IBRD / 86490 thening of Service Providers Posterior Individual Direct - National 18,822.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 te que hagan parte de los prést in the Municipalities of Guap amos del BID y el Banco Mun i and Tum aco dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Desa PTSP- BIRF-8649-200 / Lider ar el componente social de lo s proyectos que se generen e n el marco de los préstamos Component 4. Project Manag del Banco Mundial ejecutado IBRD / 86490 ement and Environmental a Posterior Individual Limited 15,685.00 0.00 Cancelado 2023-03-13 2023-04-04 2023-03-17 2023-04-07 2023-05-12 2023-11-08 s por la Unidad Nacional para nd Social Management la Gestión del Riesgo de Des astres como entidad ejecutor a del Fondo para el Desarroll o del Plan Todos Somos PTSP-BIRF-8649-202 / Presta r los servicios juridicos como especialista al Ordenador del Gasto, en los procesos de ad Component 4. Project Manag Ejecución pendien quisiciones, así como en las IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 11,965.00 0.00 2023-04-04 2023-04-14 2023-05-05 2023-06-09 2023-12-06 te actividades inherentes a la ej nd Social Management ecución de los proyectos que se desarrollan en el marco d e los prestamos del BID y el Banco Mundial.. PTSP-BIRF-8649-204 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Component 4. Project Manag l Banco Mundial ejecutados p IBRD / 86490 ement and Environmental a Posterior Individual Limited 31,370.00 0.00 En ejecución 2023-05-05 2023-05-11 2023-05-19 2023-05-16 2023-06-09 2023-07-14 2024-01-10 or la Unidad Nacional para la nd Social Management Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PSTP-BIRF-8649-206 / Lidera r la planificación, monitoreo, seguimiento y gestión de los Component 4. Project Manag préstamos del BID y el Banco IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 18,822.00 0.00 En ejecución 2023-05-15 2023-05-25 2023-05-25 2023-06-15 2023-07-20 2024-01-16 Mundial, ejecutados por la U nd Social Management nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del FTS P PTSP-BIRF-8649-203 / Lidera r la planificación,estructuraci ón, seguimiento y gestión de Component 1. Water Supply los proyectos de Agua y Sane and Basic Sanitation Improv amiento Básico que hagan p IBRD / 86490 Posterior Individual Direct - National 15,684.00 0.00 Cancelado 2023-04-04 2023-04-14 2023-05-05 2023-06-09 2023-12-06 ements in the Municipality o arte de los préstamos del Ba f Guapi nco Mundial 8649 CO y 8798 CO, ejecutados por la Unidad Nacional para la Gestión del Riesgo de Desastres... PTSP-BIRF-8649-205 / Brinda r acompañamiento técnico pr ofesional ambiental en la ges Component 4. Project Manag tión de los Planes de Manejo IBRD / 86490 ement and Environmental a Posterior Individual Limited 17,438.00 0.00 En ejecución 2023-05-15 2023-05-25 2023-05-20 2023-06-10 2023-07-15 2024-01-11 Ambiental y Estudios de Imp nd Social Management acto Ambiental de los proyec tos que se desarrollen en el marco del PTSP, que adelant a como entidad ejecutora de la UNGRD PTSP-BIRF-8649-208 / Presta r los servicios de acompaña miento integral y exclusivo al Ordenador del Gasto del FTS Component 4. Project Manag P, en las actividades inherent IBRD / 86490 ement and Environmental a Posterior Individual Limited 11,866.00 0.00 Cancelado 2023-06-02 2023-06-07 2023-06-28 2023-08-02 2024-01-29 es a la ejecución de los proye nd Social Management ctos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, que ejecuta la UNGRD. PTSP-BIRF-8649-209 / Coordi nar y dirigir la implementació n y supervisión de los présta mos del BID y el Banco Mund Component 4. Project Manag ial, ejecutados por la Unidad IBRD / 86490 ement and Environmental a Posterior Individual Direct - National 12,872.00 0.00 En ejecución 2023-06-02 2023-07-11 2023-06-12 2023-07-03 2023-08-07 2024-02-03 Nacional para la Gestión del nd Social Management Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico PTSP-BIRF-8649-212 / Actual ización, ajuste y complement Component 2. Water Supply ación de estudios y diseños d and Basic Sanitation Improv Selección directa IBRD / 86490 Posterior Direct - National 133,327.00 0.00 En ejecución 2023-06-09 2023-06-23 2023-06-19 2023-08-23 2024-02-19 e la nueva línea de aducción ements in the Municipality o de consultores del sistema de acueducto del f Tumaco distrito especial de Tumaco d epartamento de Nariño. PTSP-BIRF-8649-211 / LÍDER AGUA Y SANEAMIENTO BÁSIC Component 1. Water Supply O (TUMACO - GUAPI) - Liderar and Basic Sanitation Improv Ejecución pendien IBRD / 86490 Posterior Individual Open - National 62,739.00 0.00 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 la planificación, estructuració ements in the Municipality o te n, seguimiento y gestión de l f Guapi os proyectos de Agua y Sane amiento Básico Page 12 PTSP-BIRF-8649-210 / Lidera r la planificación, seguimient o y gestión ambiental de los proyectos que se adelanten e Component 4. Project Manag n el marco de los préstamos IBRD / 86490 ement and Environmental a Posterior Individual Open - National 18,822.00 0.00 Cancelado 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 del BID y el Banco Mundial, e nd Social Management jecutados por la Unidad Naci onal para la Gestión del Ries go de Desastres como entida d ejecutora del FTSP Component 4. Project Manag PTSP-BIRF-8649-215 / Líder Ejecución pendien IBRD / 86490 ement and Environmental a Posterior Individual Limited 15,917.00 0.00 2023-07-27 2023-08-01 2023-08-22 2023-09-26 2024-03-24 Ambiental te nd Social Management Page 13