PROCUREMENT PLAN (Textual Part) Project Country: Kyrgyz Republic information Full Project Name: Regional Economic Development Project (RED) Total Finance ($): USD 60,000,000 Project Number: P167428 Project Implementation agency Community Development and Investment Agency of the Kyrgyz Republic (ARIS) Date of the Procurement Plan February 5, 2020 Period covered by this Procurement September 2020 – December, 2026 Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), procurement under World Bank financed operations may be carried out in accordance with “Single-Stage Bidding” method set forth in the Public Procurement Law of the Kyrgyz Republic dated April 3, 2015 № 72 (the “PPL”) with amendments dated November 18, 2016 No. 182, December 10, 2016 No. 195, February 14, 2017 No. 25, May 30, 2017 No. 93, March 29, 2018 No. 32, January 11, 2019 No. 4, June 26, 2019 No. 76, provided that such arrangements continue to meet requirements of the paragraph 5.4 of the Procurement Regulations and the following conditions: • The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, Bank Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; • Bidding documents, including contract forms, acceptable to the Bank shall be used. Bidding documents shall include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social, health and safety (“ESHS”) risks and impacts. • The Bidding process shall not be cancelled solely on the reason that minimum bid price is larger than the amount allocated by procuring entity for the procurement. • There shall be no preference applied during procurement of goods and works. • Implementing agency shall have an option to publish procurement notice without disclosing cost estimate. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Other national procurement arrangements such as “Simplified Method” (Request for Quotation) may be applied on the same conditions stated above for procuring limited quantities of readily available off-the-shelf goods or simple civil works of small value. In addition, not less than three quotations shall be requested to ensure competition. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Kyrgyz Republic : Kyrgyz Republic Regional Economic Development Project PLAN General Information Country: Kyrgyz Republic 2021-03-03 Bank’s Approval Date of the Original Procurement Plan: 2023-06-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167428 GPN Date: 2020-09-16 Project Name: Kyrgyz Republic Regional Economic Development Project Loan / Credit No: IDA / 65580 Community Development and Investment Agency Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-W-RFQ-2021-1 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2023-07-2 ffice repair for Osh technical IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-06-10 2021-07-23 tions nvelope lementation 3 agricultural college unctions IDA-REDP-W-RFQ-2021-2 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2022-07-2 IDA / 65580 Post Open - National 0.00 2021-06-10 2021-07-23 ffice repair of Laboratory IST c Planning and Regulatory F tions nvelope lementation 3 A unctions IDA-REDP-W-RFQ-2021-3 / R Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2022-07-2 econstruction of driving field IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-06-10 2021-07-16 tions nvelope lementation 3 s for Osh technical agricultur unctions al college IDA-REDP-W-RFB-2021-4 / Pr Catalyzing Investments for T ovision of tourism services a Single Stage - One E Pending Imp 2023-09-1 IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National 0.00 2021-06-10 2021-06-10 2021-07-15 2021-08-05 2021-08-22 nd amenities (eg. rest stops) nvelope lementation 1 ent along the main circuits IDA-REDP-W-RFQ-2021-8 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2023-01-2 ffice repair for Osh technolog IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-12-17 2022-01-22 tions nvelope lementation 9 ical university unctions IDA-REDP-W-RFB-2021-6 / S uleiman-Too Museum and Co mplex upgrading and Uzgen Catalyzing Investments for T Open - Internationa Single Stage - Two E Pending Imp 2023-11-0 Museum and grounds upgrad IDA / 65580 ourism and Urban Developm Prior Request for Bids 0.00 2021-06-13 2021-06-18 2021-07-30 2021-10-12 2021-11-16 l nvelope lementation 6 ing (including infra, services, ent exhibition organization, mus eum site and visitor manage ment plan etc.) IDA-REDP-W-RFB-2021-7 / A Catalyzing Investments for T Single Stage - One E Pending Imp 2023-12-2 bshir-Ata: Kara-Shoro Park Ky IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National 0.00 2021-06-13 2021-06-13 2021-08-01 2021-08-22 2021-09-11 nvelope lementation 0 rgyz-Ata: infrastructure impr ent ovement IDA-REDP-W-RFQ-2022-9 / O Improving Regional Economi Request for Quota Single Stage - One E Pending Imp 2023-07-3 IDA / 65580 Post Open - National 0.00 2022-06-17 2022-07-30 ffice repair of Interdistrict La c Planning and Regulatory F tions nvelope lementation 0 boratories unctions IDA-REDP-W-RFB-2021-5 / " Osh City downtown and key and Uzgen City urban regen Catalyzing Investments for T Open - Internationa Single Stage - Two E 2023-11-0 eration (roads, parks and oth IDA / 65580 ourism and Urban Developm Prior Request for Bids 0.00 Canceled 2021-06-13 2021-06-18 2021-07-30 2021-10-12 2021-11-16 l nvelope 6 er public spaces, utilities, etc ent .) (roads, parks and other pu blic spaces, pedestrian bridges a cross river, utilities, etc.)" IDA-REDP-W-RFB-2022-14 / Catalyzing Investments for T Other (with fi Construction works: Tynchtyk Open - Internationa Single Stage - One E Pending Imp 2023-09-0 IDA / 65580 ourism and Urban Developm Post Request for Bids eld for expla 0.00 2022-11-15 2022-12-04 2023-01-03 2023-01-24 2023-03-05 park, park near the stadium, l nvelope lementation 1 ent nation) stadium, park bridge. IDA-REDP-W-RFB-2022-11 / I mprove and landscape the le Catalyzing Investments for T Other (with fi ft and right banks and shore Single Stage - One E 2024-04-2 IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National eld for expla 0.00 Canceled 2023-01-23 2023-01-27 2023-01-31 2023-03-02 2023-04-01 2023-04-23 strengthening works at the A nvelope 2 ent nation) k-Bura river in Osh city starti ng from Navoi street to Vakh apov street IDA-REDP-W-RFB-2022-11/1 / Procurement of works for wi Request for B dening the sidewalk with lan Catalyzing Investments for T ids - Small W Single Stage - One E Under Imple 2024-05-1 dscaping and improvement o IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National orks SPD (1 e 0.00 2023-01-31 2023-02-01 2023-02-05 2023-02-01 2023-03-19 2023-04-18 2023-05-23 nvelope mentation 7 f the coast of the Ak-Buura ri ent nvelope proc ver at the section of B. Nurm ess) atov and A. Navoi streets (on the part of Tileke-Batyr stree t) IDA-REDP-W-RFB-2022-10 / Catalyzing Investments for T Other (with fi Construction works: Open - Internationa Single Stage - One E 2023-04-0 IDA / 65580 ourism and Urban Developm Post Request for Bids eld for expla 0.00 Canceled 2022-06-17 2022-07-06 2022-08-05 2022-08-15 2022-10-05 Theater park, Toktogul theat l nvelope 3 ent nation) er and Navoi park. IDA-REDP-W-RFB-2023-1 / I mprovement of the territory Catalyzing Investments for T Other (with fi Single Stage - One E Pending Imp 2023-08-2 of the Osh National Drama T IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National eld for expla 0.00 2023-04-14 2023-04-19 2023-05-31 2023-06-30 2023-08-04 nvelope lementation 8 heater named after S. Ibraim ent nation) ov located on the street. Kur manzhan-Datka IDA-REDP-W-RFB-2023-2 / R Catalyzing Investments for T Other (with fi econstruction of the central s Single Stage - One E Pending Imp 2023-09-1 IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National eld for expla 0.00 2023-04-21 2023-04-26 2023-06-07 2023-07-07 2023-08-11 quare of Osh city on Lenin St nvelope lementation 6 ent nation) reet No. 220/2 in MTU No. 2 Sulaiman-Too IDA-REDP-W-RFB-2023-3 / R epair of the existing building of the summer theater name Catalyzing Investments for T Other (with fi d after T. Satylganov with th Single Stage - One E Pending Imp 2024-02-0 IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National eld for expla 0.00 2023-04-21 2023-04-26 2023-06-07 2023-07-07 2023-08-11 e construction of a canopy fo nvelope lementation 7 ent nation) r the auditorium of the summ er theater at the address: Le nina str. b/n in MTU № 2 "Sul aiman-Too" Osh city IDA-REDP-W-RFB-2022-12 / Construction works: Zones b Catalyzing Investments for T Other (with fi Open - Internationa Single Stage - One E Pending Imp 2023-07-0 etween residential quarters / IDA / 65580 ourism and Urban Developm Post Request for Bids eld for expla 0.00 2022-09-15 2022-10-04 2022-10-24 2022-11-23 2023-01-03 l nvelope lementation 2 blocks, wall painting (mosaic) ent nation) , northern part of Lenin stree t. Page 1 IDA-REDP-W-RFB-2023-4 / R Catalyzing Investments for T Other (with fi econstruction of the park on Single Stage - One E Pending Imp 2024-08-2 IDA / 65580 ourism and Urban Developm Post Request for Bids Open - National eld for expla 0.00 2023-05-15 2023-05-20 2023-07-01 2023-07-31 2023-09-04 Sai Boyu Street b/n in MTU № nvelope lementation 9 ent nation) 2 "Sulaiman-Too" of Osh city IDA-REDP-RFB-WORKS-VC"A PPLE"-2023-1 / Rehabilitation Other (with fi Strengthening Agri-Food Sup Single Stage - Two E Pending Imp 2024-05-3 works for the leader of the V IDA / 65580 Post Request for Bids Open - National eld for expla 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 ply Chains and SMEs nvelope lementation 1 C "Apple" and for the benefic nation) iaries of the VC "Apple" (2 Lo ts) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-GOODS-RFQ-2020 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -1 / PCs for the office of infor IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2020-12-20 2021-02-16 2021-08-15 tions nvelope ementation mation market system unctions IDA-REDP-GOODS-RFQ-2021 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl IDA / 65580 Post Open - National 0.00 2021-12-15 2022-01-23 2022-04-23 -5 / Tractor with equipment c Planning and Regulatory F tions nvelope ementation unctions IDA-REDP-GOODS-RFQ-2022 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -11 / Special vehicle for testi IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-02-23 2022-04-23 2022-10-20 tions nvelope ementation ng points of expertise of crop unctions s IDA-REDP-GOODS-RFB-2022- 12 / Abshir-Ata, Kara-Shoro P ark, Kyrgyz-Ata: goods for to Catalyzing Investments for T Open - Internationa Single Stage - One E Pending Impl urist infrastructure upgrading IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-01-13 2022-01-18 2022-03-01 2022-03-31 2022-05-05 2023-04-30 l nvelope ementation and solid waste management ent improvements ; Trucks and b ins for Kyrgyz-Ata, Abshyr-At a, Karashoroo IDA-REDP-GOODS-RFB-2022- Improving Regional Economi 9 / Mechanization and electrif Single Stage - One E Pending Impl IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 2022-08-11 2022-08-11 2022-08-25 2022-08-28 2022-09-16 2022-12-15 ication of agriculture for Osh nvelope ementation unctions technical agricultural college IDA-REDP-GOODS-RFQ-2022 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -10 / Promotion materials for IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-06-26 2022-07-30 2022-11-06 tions nvelope ementation National Stakeholders platfor unctions m IDA-REDP-GOODS-RFB-2022- Catalyzing Investments for T 13 / Furniture, goods and exi Open - Internationa Single Stage - One E Pending Impl IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-08-10 2022-08-15 2022-09-26 2022-10-26 2022-11-30 2023-05-29 bition equipment for Suleimq l nvelope ementation ent n-Too and Uzgen museums IDA-REDP-GOODS-RFQ-2021 Improving Regional Economi Request for Quota Single Stage - One E Pending Impl -6 / Software for information IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-12-12 2022-01-20 2022-04-20 tions nvelope ementation market system unctions IDA-REDP-GOODS-RFB-2023- 18 / Purchase of goods (traini ng materials, printed materia Supporting Tourism and Rur Single Stage - Two E Pending Impl ls, etc.) for training in the hos IDA / 65580 al Development through Sm Post Request for Bids Open - National 0.00 2022-01-02 2022-01-07 2022-02-18 2022-05-03 2022-06-07 2022-12-04 nvelope ementation pitality industry for tour guid all Grants es, tour operators and mana gers / accommodation perso nnel. Technical support IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Single Stage - One E 15 / Goods for Implementatio IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 Canceled 2023-01-10 2023-01-17 2023-01-31 2023-02-21 2023-03-10 2023-09-06 nvelope n of acitivities suggested by t unctions he REDP IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Single Stage - One E 16 / Goods for regional onlin IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 Canceled 2023-01-10 2023-01-17 2023-01-31 2023-02-21 2023-03-10 2023-09-06 nvelope e platform development unctions IDA-REDP-GOODS-RFB-2021- Catalyzing Investments for T Open - Internationa Single Stage - One E 7 / Goods for Branding, mark IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 Canceled 2021-10-01 2021-10-06 2021-11-17 2021-12-17 2022-01-21 2022-04-21 l nvelope eting and promotion activitie ent s for Osh region IDA-REDP-GOODS-RFB-2022- 14 / Ensuring the product de Catalyzing Investments for T Open - Internationa Single Stage - One E velopment at the regional lev IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 Canceled 2022-03-10 2022-03-13 2022-04-24 2022-05-24 2022-06-28 2022-12-25 l nvelope el (fairs, exhibitions, PR, med ent ia campaigns, cultural events , forums) IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Single Stage - One E Pending Impl 20 / Goods for regional onlin IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 2023-01-10 2023-01-15 2023-02-04 2023-02-24 2023-03-10 2023-09-06 nvelope ementation e platform development unctions IDA-REDP-GOODS-RFB-2023- Improving Regional Economi Open - Internationa Single Stage - One E Pending Impl 19 / Goods for Implementatio IDA / 65580 c Planning and Regulatory F Post Request for Bids 0.00 2023-01-10 2023-01-15 2023-01-30 2023-02-14 2023-03-21 2023-09-17 l nvelope ementation n of acitivities suggested by t unctions he REDP IDA-REDP-GOODS-RFQ-2021 -4 / Printing of education mat erials on veterinary, artificial Improving Regional Economi Request for Quota Single Stage - One E Pending Impl insemination, mechanization IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-07-05 2022-08-13 2022-11-11 tions nvelope ementation and electrification of agricult unctions ure for Osh agricolledge and printing education materials f or Osh technological universi ty IDA-REDP-GOODS-RFB-2022- 15 / Ensuring the product de Catalyzing Investments for T Open - Internationa Single Stage - One E Pending Impl velopment at the regional lev IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-03-10 2022-03-15 2022-04-24 2022-05-24 2022-06-26 2022-12-25 l nvelope ementation el (fairs, exhibitions, PR, med ent ia campaigns, cultural events , forums). IDA-REDP-GOODS-RFQ-2022 Catalyzing Investments for T -17 / Handouts for participant Request for Quota Single Stage - One E IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2022-09-13 2022-09-28 2022-10-28 s of the Regional Tourism For tions nvelope ent um "Sustainable Tourism De velopment Together" IDA-REDP-PP-GOODS-RFQ-20 23-1/1 / Apple tree seedlings Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-26 2023-03-10 for "Apple" Productive Partne ply Chains and SMEs tions nvelope rship : Golden Delicious (M9 r ootstock) Page 2 IDA-REDP-PP-GOODS-RFQ-20 23-1/3 / Apple tree seedlings Strengthening Agri-Food Sup Request for Quota Single Stage - One E for "Apple" Productive Partne IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-08-22 ply Chains and SMEs tions nvelope rship : Red Chif (MM 106 root stock),Red Chif (M9 rootstock ), Gala Must (M9 rootstock) IDA-REDP-PP-GOODS-RFQ-20 23-1/4 / Apple trees seedling Strengthening Agri-Food Sup Request for Quota Single Stage - One E s for "Apple" Productive Par IDA / 65580 Post Open - National 0.00 Canceled 2023-02-10 2023-03-09 2023-09-05 ply Chains and SMEs tions nvelope tnership for IE Boydonov S. a nd СHС "Baglan": Gala (M9 r ootstock) IDA-REDP-PP-GOODS-RFQ-20 23-2/1 / Cherry tree seedling for "Acoustic fruit and vegeta Strengthening Agri-Food Sup Request for Quota Single Stage - One E ble freezing" Product Partner IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-08-22 ply Chains and SMEs tions nvelope ship: Cordia (Maxma 14 roots tock), Valovaya 3 (cherry ro otstock), Regina (Maxma 14 r ootstock) IDA-REDP-PP-GOODS-RFQ-20 23-2/3 / Pear tree seedlings f or "Acoustic fruit and vegeta Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-03-10 ble freezing" Product Partner ply Chains and SMEs tions nvelope ship: Santa Maria (ВА 29 Po llinator), Carmen (ВА 29 Polli nator),Williams (ВА 29 Pollina tor) IDA-REDP-PP-GOODS-RFQ-20 23-2/4 / Seedlings of remont Strengthening Agri-Food Sup Request for Quota Single Stage - One E ant strawberries for "Acousti IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-08-22 ply Chains and SMEs tions nvelope c fruit and vegetable freezing " Product Partnership: Clery, Black Prince IDA-REDP-PP-GOODS-RFQ-20 23-1/5 / Apple trees seedling Strengthening Agri-Food Sup Request for Quota Single Stage - One E s for "Apple" Productive Par IDA / 65580 Post Open - National 0.00 Canceled 2023-02-10 2023-03-09 2023-09-05 ply Chains and SMEs tions nvelope tnership for "Termez" Agricu ltural Production Cooperative : Gala (M9 rootstock) IDA-REDP-PP-GOODS-RFQ-20 23-1/2 / Cherry tree seedling Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-03-10 s for "Apple" Productive Part ply Chains and SMEs tions nvelope nership : Regina, Cordia (Max ma 14 rootstock) IDA-REDP-PP-GOODS-RFQ-20 23-1/6 / Apple tree seedlings Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-03-10 for "Apple" Productive Partn ply Chains and SMEs tions nvelope ership for LLC "Agrocomplex ": Gala (M9 rootstock) IDA-REDP-PP-GOODS-RFQ-20 23-2/5 / Seedlings for "Acous Strengthening Agri-Food Sup Request for Quota Single Stage - One E tic fruit and vegetable freezin IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-08-22 ply Chains and SMEs tions nvelope g" Product Partnership of Plu m Leto and Raspberry Polka IDA-REDP-PP-GOODS-RFQ-20 23-1/7 / Apple tree seedlings Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-02-06 2023-03-01 2023-03-10 for "Apple" Productive Partne ply Chains and SMEs tions nvelope rship : Golden Delicious (M9 r ootstock) IDA-REDP-PP-GOODS-RFQ-20 23-1/8 / Apple tree seedlings Strengthening Agri-Food Sup Request for Quota Single Stage - One E for "Apple" Productive Partn IDA / 65580 Post Open - National 0.00 Canceled 2023-02-06 2023-03-01 2023-03-10 ply Chains and SMEs tions nvelope ership for LLC "Agrocomplex ": Red Chif (M9 rootstock) IDA-REDP-GOODS-RFB-2022- Catalyzing Investments for T Open - Internationa Single Stage - One E Pending Impl 17 / Goods for Branding,mark IDA / 65580 ourism and Urban Developm Post Request for Bids 0.00 2022-01-23 2022-01-28 2022-03-11 2022-04-10 2022-05-15 2022-11-11 l nvelope ementation eting and promotion activitie ent s for Osh region IDA-REDP-GOODS-RFQ-2021 -3 / Printing of materials for d evelopment of information m Improving Regional Economi arket system and for MinAgri, Request for Quota Single Stage - One E Pending Impl IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-07-22 2022-08-30 2022-11-28 Osh obl administration and 7 tions nvelope ementation unctions laborotories, market fairs, 6 border control points, soil agr ochemical map and its e-cad astre and 7 centers IDA-REDP-GOODS-RFB-2021- 2 / Laboratory equipment (for 7 sampling points for laborat ory testing, for 7 border cont Improving Regional Economi Open - Internationa Single Stage - Two E Pending Impl rol points, for 2 phytosanitar IDA / 65580 c Planning and Regulatory F Prior Request for Bids 0.00 2021-12-12 2021-12-17 2022-01-28 2022-04-12 2022-05-17 2022-11-13 l nvelope ementation y laboratories under GosStan unctions dard, food kaboratory (Sanep idnadzor), Venerinary Service and CoCommerse and small f ood laboratories etc... IDA-REDP-GOODS-RFB-2023- 10 / Laboratory equipment fo r laboratories of veterinary di Improving Regional Economi Single Stage - One E Pending Impl agnostics and examination, d IDA / 65580 c Planning and Regulatory F Post Request for Bids Open - National 0.00 2023-04-28 2023-05-03 2023-06-14 2023-07-14 2023-08-18 2024-02-14 nvelope ementation isease prevention and state s unctions anitary and epidemiological s upervision, standardization a nd metrology IDA-REDP-GOODS-RFB-2022- 8 / Office equipment, furnitur e for laboratory (ISTA) for on Improving Regional Economi testing points of expertise of Open - Internationa Single Stage - One E Pending Impl IDA / 65580 c Planning and Regulatory F Post Request for Bids 0.00 2022-02-23 2022-02-28 2022-04-11 2022-05-11 2022-06-15 2022-12-12 crops; Office equipment, furn l nvelope ementation unctions iture for 7 sampling points fo r laboratory testing; Office eq uipment, furniture for 7 bord er control points and etc. IDA-REDP-GOODS-RFQ-2023 -9 / Household equipment an d diesel generator for laborat Improving Regional Economi Request for Quota Single Stage - One E Pending Impl ories of veterinary diagnostic IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2023-05-03 2023-06-28 2023-12-25 tions nvelope ementation s and examination, disease p unctions revention and state sanitary and epidemiological supervis ion, standardization and metr ology Page 3 IDA-REDP-GOODS-RFQ-2023 -7 / Office equipment for labo ratories of veterinary diagnos Implementation Support and Request for Quota Single Stage - One E Pending Impl tics and examination, diseas IDA / 65580 Post Open - National 0.00 2023-05-16 2023-07-11 2024-01-07 Monitoring and Evaluation tions nvelope ementation e prevention and state sanita ry and epidemiological super vision, standardization and m etrology IDA-REDP-GOODS-RFQ-2023 -8 / Office furniture for labora tories of veterinary diagnosti Improving Regional Economi Request for Quota Single Stage - One E Pending Impl cs and examination, disease IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2023-05-16 2023-07-11 2024-01-07 tions nvelope ementation prevention and state sanitary unctions and epidemiological supervis ion, standardization and metr ology IDA-REDP-GOODS-RFB-2023- Strengthening Agri-Food Sup Single Stage - Two E Pending Impl 11 / Purchasing of cattle for v IDA / 65580 Post Request for Bids Open - National 0.00 2023-05-11 2023-05-16 2023-06-27 2023-09-09 2023-10-14 2024-04-11 ply Chains and SMEs nvelope ementation alue chain "Milk" IDA-REDP-PP-GOODS-RFQ-20 23-2/2 / Apple tree seedlings for "Acoustic fruit and vegeta ble freezing" Product Partner Strengthening Agri-Food Sup Request for Quota Single Stage - One E IDA / 65580 Post Open - National 0.00 Canceled 2023-01-27 2023-02-23 2023-03-10 ship:Golden Delicious (MM10 ply Chains and SMEs tions nvelope 6 rootstock), Gala (MM106 r ootstock), Red Chif (MM106 r ootstock), Super Chif (M9 ro otstock) Fudji IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-4 / Fertilizer for Value IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope Chain "Apple" IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-5 / Seeds for Value Ch IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope ai "Vegetables and Fruits" IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-6 / Equipment for Valu IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope e Chai"Vegetables and Fruits " IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-7 / Drip irrigation syste IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope m for Value Chain "Vegetable s and Fruits" IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-8 / reservoir for Value IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope Chain "Vegetables and Fruits " IDA-REDP-AFSC-GOODS-RFQ Strengthening Agri-Food Sup Request for Quota Single Stage - One E -2023-9 / pumps for Value Ch IDA / 65580 Post Open - National 0.00 Canceled 2023-06-05 2023-07-31 2024-01-27 ply Chains and SMEs tions nvelope ain "Vegetables and Fruits" IDA-REDP-GOODS-RFQ-2023 Strengthening Agri-Food Sup Request for Quota Single Stage - One E -10 / Purchasing of equipmen IDA / 65580 Post Open - National 0.00 Canceled 2023-05-03 2023-06-28 2023-08-27 ply Chains and SMEs tions nvelope t for value chain "Milk" IDA-REDP-GOODS-RFB-2023- 12 / Purchasing of equipment Strengthening Agri-Food Sup Single Stage - One E IDA / 65580 Post Request for Bids Open - National 0.00 Canceled 2023-04-28 2023-04-28 2023-05-03 2023-06-14 2023-05-26 2023-07-14 2023-08-18 2023-08-19 for the leader of value chain ply Chains and SMEs nvelope "Milk" for "Alaiku Organics" L td. IDA-REDP-GOODS-RFQ-2023 Strengthening Agri-Food Sup Request for Quota Single Stage - One E Pending Impl -10/RT1 / Purchasing of equip IDA / 65580 Post Open - National 0.00 2023-06-21 2023-08-16 2024-02-12 ply Chains and SMEs tions nvelope ementation ment for value chain "Milk" IDA-REDP-GOODS-RFB-2023- 12/RT1 / Purchasing of equip Strengthening Agri-Food Sup Single Stage - Two E Pending Impl IDA / 65580 Post Request for Bids Open - National 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 2024-05-31 ment for the leader of value- ply Chains and SMEs nvelope ementation chain "Milk" for "Alaikum Org anics" Ltd. IDA-REDP-RFQ-GOODS-VC-V F/A-2023-1 / Procurement of Strengthening Agri-Food Sup Request for Quota Single Stage - One E Pending Impl goods for the beneficiaries of IDA / 65580 Post Open - National 0.00 2023-07-05 2023-08-30 2024-02-26 ply Chains and SMEs tions nvelope ementation the Apple VC and for LLC Tur an Group Leader Vegetables and Fruits (2 Lots) IDA-REDP-RFB-GOODS-VC-A- Strengthening Agri-Food Sup Single Stage - Two E Pending Impl 2023-2 / Supply of plastic co IDA / 65580 Post Request for Bids Open - National 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 2024-05-31 ply Chains and SMEs nvelope ementation ntainers for Leader of VC App le IDA-REDP-RFQ-GOODS-VC-V F-2023-3 / Supply of cargo el Strengthening Agri-Food Sup Request for Quota Single Stage - One E Pending Impl IDA / 65580 Post Open - National 0.00 2023-07-05 2023-08-30 2024-02-26 evator of LLC Turan Group fo ply Chains and SMEs tions nvelope ementation r Leader of VC Vegetables an d Fruits IDA-REDP-RFB-GOODS-VC-V F-2023-3 / Supply of equipme Strengthening Agri-Food Sup Single Stage - Two E Pending Impl IDA / 65580 Post Request for Bids Open - National 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 2024-05-31 nt for LLC Turan Group of Lea ply Chains and SMEs nvelope ementation der of VC Vegetables and Fru its (2 Lots) IDA-REDP-RFB-GOODS-VC-V F/A-2023-4 / Supply of metal Strengthening Agri-Food Sup Request for Quota Single Stage - One E Pending Impl ware and reinforced concrete IDA / 65580 Post Open - National 0.00 2023-07-05 2023-08-30 2024-02-26 ply Chains and SMEs tions nvelope ementation poles for beneficiaries for VC Vegetables and Fruits and Ap ple (2 Lots) IDA-REDP-RFB-GOODS-VC-F V/A-2023-5 / Supply of drip ir Strengthening Agri-Food Sup Single Stage - Two E Pending Impl IDA / 65580 Post Request for Bids Open - National 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 2024-05-31 rigation systems for benefici ply Chains and SMEs nvelope ementation aries for VC Apple and Veget ables and Fruits (5 Lots) IDA-REDP-RFQ-GOODS- VC-V F/A-2023-6 / Supply of fertiliz Strengthening Agri-Food Sup Request for Quota Single Stage - One E Pending Impl IDA / 65580 Post Open - National 0.00 2023-07-05 2023-08-30 2024-02-26 ers and seeds for beneficiarie ply Chains and SMEs tions nvelope ementation s for VC Apple and Vegetable s and Fruits (2 Lots) IDA-REDP-RFB-GOODS-VC-V F/A-2023-7 / Supply of equip Strengthening Agri-Food Sup Single Stage - Two E Pending Impl IDA / 65580 Post Request for Bids Open - National 0.00 2023-06-30 2023-07-05 2023-08-16 2023-10-29 2023-12-03 2024-05-31 ment for beneficiaries for VC ply Chains and SMEs nvelope ementation Apple and Vegetables and Fr uits (3 Lots) Page 4 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-NS-2022-5 / Acco mmodation for participants Catalyzing Investments for T Request for Quota Single Stage - One E Pending Impl of International scientific and IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2022-10-08 2022-12-03 2023-06-01 tions nvelope ementation practical conference on Geot ent ourism and prospects of the geopark in the Osh region CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-CS-CQS-2021-1 / R Improving Regional Economi Consultant Qualifi Pending Impleme egional development platfor IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-01-25 2021-01-31 2021-03-16 2021-04-15 2021-05-20 2021-08-18 cation Selection ntation m implementation unctions IDA-REDP-CS-CQS-2021-5 / S urvey on agribusiness value Strengthening Agri-Food Sup Consultant Qualifi IDA / 65580 Post Open - National 52,594.80 Signed 2021-06-29 2021-05-06 2021-06-30 2021-05-18 2021-07-18 2022-04-12 2021-08-17 2022-04-12 2021-10-15 2022-04-14 2022-01-13 chain. Survey on diagnostic s ply Chains and SMEs cation Selection tudies. Consulting company for survey IDA-REDP-CS-LCS-2021-1 / P Implementation Support and Least Cost Selecti Open - Internationa IDA / 65580 Post 0.00 Canceled 2021-10-15 2021-11-05 2021-12-19 2022-01-16 2022-02-15 2022-03-22 2022-04-26 2026-08-23 roject audit (financial audit) Monitoring and Evaluation on l IDA-REDP-CS-QCBS-2021-10 / Сonsulting company for M& E to conduct a baseline surve Implementation Support and Quality And Cost- Open - Internationa Pending Impleme y, focus group interviews, etc IDA / 65580 Prior 0.00 2022-10-10 2022-10-31 2022-12-14 2023-01-11 2023-02-10 2023-03-17 2023-04-21 2024-04-20 Monitoring and Evaluation Based Selection l ntation . collect quantitive and qualit ative data through the projec t and then at closing provide the summary with the impact results IDA-REDP-CS-QCBS-2021-4 / Consulting company for feasi Improving Regional Economi bilty studies for SPS investm Quality And Cost- Open - Internationa IDA / 65580 c Planning and Regulatory F Post 158,295.00 Signed 2021-07-17 2021-05-01 2021-08-07 2021-05-18 2021-09-20 2021-08-25 2021-10-18 2021-09-23 2021-11-17 2022-02-08 2021-12-22 2022-02-24 2022-01-26 2022-04-01 2022-07-25 ents and design of technical Based Selection l unctions specifications for equipment of laboratories, centers and p oints IDA-REDP-CS-CQS-2021-25 / Catalyzing Investments for T Consultant Qualifi Regional Tourism Strategy C IDA / 65580 ourism and Urban Developm Post Open - National 90,744.99 Signed 2021-10-27 2021-09-22 2021-11-17 2021-12-31 2022-05-11 2022-01-30 2022-05-11 2022-03-06 2022-05-12 2022-09-02 cation Selection onsultant for Osh Oblast ent IDA-REDP-CS-QCBS-2021-11 / Consulting company to iden Strengthening Agri-Food Sup Quality And Cost- Open - Internationa tify specific supply chain acto IDA / 65580 Post 0.00 Canceled 2021-07-23 2021-07-28 2021-09-01 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2022-04-09 ply Chains and SMEs Based Selection l rs for participation and the c ompetitive selection of sub-p rojects IDA-REDP-CS-QCBS-2021-1 / Training in hospitality industr Catalyzing Investments for T Quality And Cost- Open - Internationa y for tour guides, tour operat IDA / 65580 ourism and Urban Developm Prior 0.00 Canceled 2021-08-25 2021-09-15 2021-10-29 2021-11-26 2021-12-26 2022-01-30 2022-03-06 2023-03-06 Based Selection l ors and accomodation mana ent gers/staff; Technical support in business planning IDA-REDP-CS-CQS-2021-27 / Consulting company providin Strengthening Agri-Food Sup Consultant Qualifi Pending Impleme g training and advice to mem IDA / 65580 Post Open - National 0.00 2022-04-04 2022-04-25 2022-06-08 2022-07-08 2022-08-12 2023-02-08 ply Chains and SMEs cation Selection ntation bers of productive partnershi ps for productivity, quality, m arketing and sales ARIS-AUDIT-LCS-2021-1 / Au Implementation Support and Least Cost Selecti Open - Internationa Under Implement IDA / 65580 Post 0.00 2021-09-01 2021-09-13 2021-09-15 2021-09-24 2021-10-13 2021-10-20 2021-10-27 2021-11-10 2021-12-08 2024-12-07 dit (financial audit) Monitoring and Evaluation on l ation IDA-REDP-CS-QCBS-2021-5 / Implementation Support and Quality And Cost- Open - Internationa Company for Preparation of f IDA / 65580 Prior 0.00 Canceled 2021-05-20 2021-06-10 2021-07-24 2021-08-21 2021-09-20 2021-10-25 2021-11-29 2022-11-29 Monitoring and Evaluation Based Selection l uture projects IDA-REDP-CS-CQS-2021-20 / Conducting an information ca mpaign, social mobilization a Strengthening Agri-Food Sup Consultant Qualifi nd diagnostic study in order t IDA / 65580 Post Open - National 0.00 Canceled 2021-09-20 2021-09-16 2021-10-11 2021-11-24 2021-12-24 2022-01-28 2022-07-27 ply Chains and SMEs cation Selection o build value chains and crea te productive partnerships in Osh oblast and Osh city and t heir further development IDA-REDP-CS-CQS-2021-22 / Conducting an information ca mpaign, social mobilization a Strengthening Agri-Food Sup Consultant Qualifi nd diagnostic study in order t IDA / 65580 Post Open - National 288,773.33 Signed 2021-12-20 2021-10-29 2022-01-10 2022-02-23 2022-04-19 2022-03-25 2022-04-19 2022-04-29 2022-04-20 2024-04-18 ply Chains and SMEs cation Selection o build value chains and crea te productive partnerships in Osh oblast and Osh city and t heir further development IDA-REDP-CS-QCBS-2021-3 / Support to department of To Improving Regional Economi Quality And Cost- Open - Internationa urism and regional/local touri IDA / 65580 c Planning and Regulatory F Prior 0.00 Canceled 2021-06-20 2021-07-11 2021-08-24 2021-09-21 2021-10-21 2021-11-25 2021-12-30 2022-05-29 Based Selection l sm agencies for improved st unctions atistics and data collection IDA-REDP-CS-CQS-2021-21 / Training in hospitality industr Supporting Tourism and Rur Consultant Qualifi y for tour guides, tour operat IDA / 65580 al Development through Sm Post Open - National 0.00 Canceled 2021-09-27 2021-10-18 2021-12-01 2021-12-31 2022-02-04 2022-08-03 cation Selection ors and accomodation mana all Grants gers/staff; Technical support in business planning IDA-REDP-CS-QCBS-2021-2 / Comprehensive assessment Catalyzing Investments for T of SulaimanToo and Uzgen m Quality And Cost- Open - Internationa IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2021-08-25 2021-10-22 2021-09-15 2021-10-29 2021-11-26 2021-12-26 2022-01-30 2022-03-06 2023-08-28 useums complexes Detailed Based Selection l ent designs and Construction Su pervision for SulaimanToo an d the Uzgen Museum IDA-REDP-CS-CQS-2021-3 / Improving Regional Economi Consultant Qualifi Open - Internationa Development of Visitors Man IDA / 65580 c Planning and Regulatory F Post 0.00 Canceled 2021-06-29 2021-07-20 2021-09-02 2021-10-02 2021-11-06 2022-02-04 cation Selection l agement Plans for Suleiman unctions Too and Uzgen Page 5 IDA-REDP-CS-CQS-2021-2 / Improving Regional Economi Development of Visitors Man Consultant Qualifi IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 Canceled 2021-06-17 2021-06-23 2021-08-06 2021-09-05 2021-10-10 2022-01-08 agement Plans for Kyrgyz-At cation Selection unctions a, Abshyr-Ata, Karashoroo IDA-REDP-CS-CQS-2021-24 / Consulting company for the p reparation of the regional ec onomic development progra Strengthening Agri-Food Sup Consultant Qualifi IDA / 65580 Post Open - National 0.00 Canceled 2021-09-26 2021-10-22 2021-10-17 2021-11-30 2021-12-30 2022-02-03 2022-08-02 m of osh oblast and economi ply Chains and SMEs cation Selection c development program of os h city under the implementat ion of the regional economic development project IDA-REDP-CS-CQS-2021-7 / Desing for tourism site touri Catalyzing Investments for T Consultant Qualifi sm services and amenities (e IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2021-06-29 2021-10-22 2021-07-06 2021-08-19 2021-09-30 2021-10-12 2022-07-14 cation Selection g Desing Abshir-Ata: Kara-Sh ent oro Park Kyrgyz-Ata: infrastr ucture improvement) IDA-REDP-CS-QCBS-2021-15 / Support to department of T Catalyzing Investments for T Quality And Cost- Open - Internationa Pending Impleme ourism and regional/local tou IDA / 65580 ourism and Urban Developm Post 0.00 2022-01-11 2022-02-01 2022-03-17 2022-04-14 2022-05-14 2022-06-18 2022-07-23 2023-07-23 Based Selection l ntation rism agencies for improved s ent tatistics and data collection IDA-REDP-CS-CQS-2021-9 / T Catalyzing Investments for T Consultant Qualifi Open - Internationa IDA / 65580 Post 0.00 Canceled 2021-06-29 2021-07-20 2021-09-02 2021-10-02 2021-11-06 2022-03-06 echnical audit ourism and Urban Developm cation Selection l ent IDA-REDP-CS-QCBS-2021-6 / Catalyzing Investments for T Quality And Cost- Open - Internationa Osh City Construction Superv IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2021-07-23 2021-08-13 2021-09-05 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2023-12-30 Based Selection l ision Services ent IDA-REDP-CS-CQS-2021-6 / P Catalyzing Investments for T reparation of detailed design Consultant Qualifi IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2021-06-29 2021-07-04 2021-08-17 2021-09-28 2021-10-10 2022-01-13 packages for Osh and Uzgen cation Selection ent Design packages IDA-REDP-CS-CQS-2021-8 / T echnical supervision for touri Catalyzing Investments for T Consultant Qualifi sm sites (infrastructure impr IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2021-06-29 2021-07-06 2021-08-19 2021-09-30 2021-10-17 2022-04-15 cation Selection ovement: Abshir-Ata, park Ka ent ra-Shoro, Kyrgyz-Ata) IDA-REDP-CS-CQS-2021-13 / Catalyzing Investments for T DED: Zones between residen Consultant Qualifi Pending Impleme IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2021-11-21 2021-12-12 2022-01-25 2022-02-24 2022-03-31 2022-09-27 tial quarters/blocks, wall pain cation Selection ntation ent ting (mosaic), the northern p art of Lenin Street. IDA-REDP-CS-QCBS-2021-14 / DED: Development of feasib Catalyzing Investments for T Quality And Cost- Open - Internationa Under Implement ility study and DED of infrastr IDA / 65580 ourism and Urban Developm Post 0.00 2021-11-30 2022-07-12 2021-12-05 2022-07-29 2021-12-15 2021-12-30 2022-01-09 2022-01-29 2022-02-25 2023-02-25 Based Selection l ation ucture of Sulaiman-Too comp ent lex and Uzgen historical and architectural complex IDA-REDP-CS-CQS-2021-28 / Consulting company for prep Improving Regional Economi Consultant Qualifi aration of a regional economi IDA / 65580 c Planning and Regulatory F Post Open - National 148,095.79 Signed 2021-11-26 2021-12-02 2021-12-06 2021-12-26 2022-05-11 2021-12-31 2022-05-11 2022-01-26 2022-05-12 2022-07-25 cation Selection c development program for t unctions he Osh oblast and Osh city IDA-REDP-CS-CQS-2021-11 / Catalyzing Investments for T Detailed design packages an Consultant Qualifi IDA / 65580 ourism and Urban Developm Post Open - National 49,479.16 Signed 2021-11-30 2022-03-04 2021-12-21 2022-02-03 2022-04-12 2022-03-05 2022-06-01 2022-04-29 2022-06-08 2022-07-28 d author supervision for the s cation Selection ent elected facilities in the city of Osh IDA-REDP-CS-CQS-2021-15 / Detailed design packages for Catalyzing Investments for T : City Park of Culture and Lei Consultant Qualifi IDA / 65580 ourism and Urban Developm Post Open - National 50,868.60 Signed 2021-11-21 2022-03-02 2021-12-12 2022-01-25 2022-04-05 2022-02-24 2022-06-01 2022-03-31 2022-06-08 2022-09-27 sure "Tynchtyk" named after cation Selection ent N. Aznabakieva, park near th e city stadium, city stadium a nd park bridge IDA-REDP-CS-CQS-2021-17 / Design services and author s Catalyzing Investments for T Consultant Qualifi upervision for Kara-Shoro an IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2021-11-28 2022-03-18 2021-12-19 2022-03-29 2022-02-01 2022-07-22 2022-03-03 2022-08-22 2022-04-07 2022-10-04 cation Selection d Kyrgyz-Ata national parks a ent nd Abshir-Ata Waterfall IDA-REDP-CS-CQS-2021-12 / Catalyzing Investments for T Consultant Qualifi IDA / 65580 Post Open - National 0.00 Canceled 2021-11-21 2021-12-12 2022-01-25 2022-02-24 2022-03-31 2022-09-27 DED: coastal zone of the Ak- ourism and Urban Developm cation Selection Buura river ent IDA-REDP-CS-QCBS-2021-13 Supporting Tourism and Rur / Consulting company for the Quality And Cost- Open - Internationa IDA / 65580 al Development through Sm Post 0.00 Signed 2022-05-08 2022-05-11 2022-05-18 2022-06-07 2022-07-22 2022-06-17 2022-08-23 2022-06-27 2022-09-13 2022-07-17 2022-09-27 2022-08-11 2025-02-18 preparation and implementat Based Selection l all Grants ion of the Small Grants Progr am IDA-REDP-CS-CQS-2021-31 / Selection of consulting comp any for assessment of the sol Implementation Support and Consultant Qualifi IDA / 65580 Post Open - National 0.00 Canceled 2022-03-01 2022-03-04 2022-03-22 2022-05-05 2022-06-04 2022-07-09 2023-01-05 id waste management syste Monitoring and Evaluation cation Selection ms in selected towns and the identification of priority secto r investments IDA-REDP-CS-CQS-2021-31- RT / Selection of consulting c ompany for assessment of th Implementation Support and Consultant Qualifi Open - Internationa IDA / 65580 Post 35,578.71 Signed 2022-06-17 2022-06-17 2022-07-08 2022-08-21 2022-07-07 2022-09-20 2022-08-02 2022-10-25 2022-08-09 2023-04-23 e solid waste management s Monitoring and Evaluation cation Selection l ystems in selected towns an d the identification of priority sector investments IDA-REDP-CS-CQS-2021-23 / Consulting Services for the pr eparation of a Tourism Mana gement Plan for Catalyzing Investments for T Consultant Qualifi Open - Internationa the Sulaiman-Too and Uzgen IDA / 65580 ourism and Urban Developm Post 0.00 Signed 2022-07-25 2022-07-27 2022-08-15 2022-08-01 2022-09-18 2022-10-20 2022-10-18 2022-12-16 2022-11-15 2023-09-08 cation Selection l Historical and Architectural C ent omplexes; Interior Design an d Exhibition Plan for the Sulai man-Too Cave Museum; and Recommendation for enlistin g Uzgen Histo IDA-REDP-CS-QCBS-2021-12 Implementation Support and Quality And Cost- Open - Internationa Pending Impleme / Company for Preparation of IDA / 65580 Prior 0.00 2024-02-05 2024-02-26 2024-04-10 2024-05-08 2024-06-07 2024-07-12 2024-08-16 2025-02-12 Monitoring and Evaluation Based Selection l ntation future projects Page 6 IDA-REDP-CS-QCBS-2021-7 / Catalyzing Investments for T Quality And Cost- Open - Internationa Tech supervision SulaimanT IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2021-07-23 2022-08-05 2021-08-07 2021-09-05 2021-10-03 2021-10-23 2021-11-13 2021-12-10 2023-12-30 Based Selection l oo and the Uzgen Museum ent IDA-REDP-CS-QCBS-2021-7. / Technical Supervision of Civil Catalyzing Investments for T Quality And Cost- Open - Internationa Works at the Sulaiman-Too a IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2022-08-22 2022-08-24 2022-09-12 2022-08-29 2022-10-26 2023-04-01 2022-11-23 2023-04-01 2022-12-23 2023-04-01 2023-01-27 2023-04-01 2023-03-03 2024-03-02 Based Selection l nd Uzgen Historical and Archi ent tectural Complexes IDA-REDP-CS-CQS-2021-14 / Catalyzing Investments for T Consultant Qualifi Pending Impleme DED: road networks (5 street IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2021-11-21 2021-12-12 2022-01-25 2022-02-24 2022-03-31 2022-09-27 cation Selection ntation s) and extension of Dostuk p ent ark IDA-REDP-CS-CQS-2021-19 / Preparation of Design Estima te Documentation (DED) pac Catalyzing Investments for T kages for the construction of Consultant Qualifi IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Signed 2022-10-10 2022-10-13 2022-10-31 2022-10-28 2022-12-14 2023-03-07 2023-01-13 2023-03-07 2023-02-17 2023-08-16 an access road, installation o cation Selection ent f transformer substation, pow er transmission line within Pu blic-Private Cooperation Prog ram of RED-1 IDA-REDP-CS-CQS-2021-18 / Catalyzing Investments for T Consultant Qualifi Technical Supervision of Civil IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2022-06-20 2022-06-13 2022-07-11 2022-07-21 2022-08-24 2022-09-23 2022-11-07 2024-07-05 cation Selection Works under the RED-1 ent IDA-REDP-CS-CQS-2021-26 / Consulting Services for the pr Catalyzing Investments for T Consultant Qualifi Under Implement eparation of Management Pla IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2021-12-01 2022-10-05 2021-12-11 2022-10-11 2021-12-28 2022-01-07 2022-02-10 2022-08-09 cation Selection ation ns for the State Nature Parks ent Kara-Shoro, Kyrgyz-Ata and waterfall Abshir-Ata IDA-REDP-CS-CQS-2021-18- Catalyzing Investments for T Consultant Qualifi Under Implement RT / Technical Supervision of IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2022-10-03 2022-10-04 2022-10-24 2022-10-06 2022-12-07 2023-01-12 2023-01-06 2023-02-15 2023-02-10 2026-05-25 cation Selection ation Civil Works under the RED-1 ent IDA-REDP-CS-QCBS-2021-8 / Catalyzing Investments for T Company for Branding,marke Quality And Cost- Open - Internationa Pending Impleme IDA / 65580 ourism and Urban Developm Post 0.00 2023-07-23 2023-07-28 2023-09-13 2023-10-03 2023-10-23 2023-11-13 2023-12-10 2024-08-04 ting and promotion activities Based Selection l ntation ent for Osh region IDA-REDP-CS-CQS-2022-28 / Selection of a consulting com pany for the provision of trai Strengthening Agri-Food Sup Consultant Qualifi Under Implement IDA / 65580 Post Open - National 0.00 2022-11-17 2023-05-23 2022-12-08 2023-05-26 2023-01-21 2023-02-20 2023-03-27 2023-09-23 ning consultancy service to t ply Chains and SMEs cation Selection ation he participants of the Produc tive Partnership of Osh Oblas t and Osh City IDA-REDP-CS-CQS-2021-17- RT / Consulting Company for Catalyzing Investments for T Feasibility Studies, Design Se Consultant Qualifi Under Implement IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2023-03-03 2023-03-24 2023-03-24 2023-04-08 2023-05-07 2023-06-06 2023-07-11 2024-03-07 rvices and Author Supervisio cation Selection ation ent n for Kara-Shoro and Kyrgyz- Ata National Parks and Abshi r-Ata Waterfall IDA-REDP-CS-CQS-2021-4 / Consulting company to cond Strengthening Agri-Food Sup Consultant Qualifi Pending Impleme IDA / 65580 Post Open - National 0.00 2021-06-29 2021-07-04 2021-08-17 2021-09-28 2021-10-15 2023-10-05 uct market studies. Methodol ply Chains and SMEs cation Selection ntation ogy for National Stakeholders Platform IDA-REDP-CS-CQS-2023-1 / Improving Regional Economi Consulting company for the d Consultant Qualifi Under Implement IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2023-03-24 2023-03-31 2023-04-14 2023-04-08 2023-05-28 2023-06-27 2023-08-01 2024-01-28 evelopment of detailed desig cation Selection ation unctions n for facilities in Osh region a nd Osh city IDA-REDP-CS-CQS-2021-10 / Consulting company for Deve lopment of design document ation and supervision of repa Improving Regional Economi Consultant Qualifi Pending Impleme ir of the office of Osh technic IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2021-12-20 2021-12-25 2022-02-07 2022-03-21 2022-04-02 2022-10-18 cation Selection ntation al agriculture college, (includi unctions ng driving fields) and office o f Osh technological university , warehouses of seed farms a nd plemzavod etc... IDA-REDP-CS-QCBS-2021-7- RT / Technical Supervision of Catalyzing Investments for T Quality And Cost- Open - Internationa Under Implement Civil Works at the Sulaiman-T IDA / 65580 ourism and Urban Developm Post 0.00 2023-04-14 2023-04-10 2023-05-05 2023-04-28 2023-06-18 2023-07-16 2023-08-15 2023-09-19 2023-10-24 2024-10-18 Based Selection l ation oo and Uzgen Historical and ent Architectural Complexes IDA-REDP-CS-CQS-2023-33 / For Consultancy Services to Catalyzing Investments for T Consultant Qualifi Under Implement deliver a Capacity Building Pr IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2023-04-28 2023-05-02 2023-05-19 2023-05-13 2023-07-02 2023-08-01 2023-09-05 2024-03-03 cation Selection ation ogram for the Tourism Sector ent Stakeholders in the Osh Regi on IDA-REDP-CS-CQS-2023-34 / Tourism Product developmen Catalyzing Investments for T Consultant Qualifi Pending Impleme t at the regional level (fairs, IDA / 65580 ourism and Urban Developm Post Open - National 0.00 2023-05-29 2023-06-19 2023-08-02 2023-09-01 2023-10-06 2024-04-03 cation Selection ntation exhibitions, PR, media campa ent igns, cultural events, forums) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-REDP-CS-IC-2021-11 / Lo Improving Regional Economi Individual Consult Pending Impleme cal consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2021-12-21 2022-01-23 2022-02-25 2022-03-22 2023-03-17 ant Selection ntation gal acts for exports 3 unctions IDA-REDP-CS-IC-2021-12 / Lo Improving Regional Economi Individual Consult Pending Impleme cal consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2021-12-21 2022-01-23 2022-01-25 2022-03-26 2023-03-21 ant Selection ntation gal acts for exports 4 unctions IDA-REDP-CS-IC-2021-13 / C Improving Regional Economi onsultant for Development of Individual Consult Pending Impleme IDA / 65580 c Planning and Regulatory F Post Open 0.00 2021-12-21 2022-01-23 2022-01-25 2022-03-26 2023-03-21 legal documents of 7 samplin ant Selection ntation unctions g points for laboratory testin g Page 7 IDA-REDP-CS-IC-2021-4 / Co Improving Regional Economi nsultant for Development of Individual Consult Pending Impleme IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 education materials for Osh t ant Selection ntation unctions echnical agricultural college and Osh university IDA-REDP-CS-IC-2021-8 / Int Improving Regional Economi Individual Consult Pending Impleme ernational consultant for revi IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 ant Selection ntation ew of legal acts for exports unctions IDA-REDP-CS-IC-2021-10 / Lo Improving Regional Economi Individual Consult Pending Impleme cal consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 ant Selection ntation gal acts for exports 2 unctions IDA-REDP-CS-IC-2021-9 / Loc Improving Regional Economi Individual Consult Pending Impleme al consultant for review of le IDA / 65580 c Planning and Regulatory F Post Open 0.00 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2021-05-01 ant Selection ntation gal acts for exports 1 unctions IDA-REDP-CS-IC-2021-20 / C Supporting Tourism and Rur onsultant to provide support Individual Consult IDA / 65580 al Development through Sm Post Open 16,421.51 Signed 2021-10-21 2021-08-19 2021-12-09 2022-04-15 2021-12-30 2022-04-15 2022-02-03 2022-04-16 2022-08-02 to ARIS with Small Grants Pro ant Selection all Grants gram and Public and Private Cooperation initiative IDA-REDP-CS-IC-2021-1 / Co Improving Regional Economi Individual Consult nsultant for Regional Econom IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 ant Selection ic Development Plan for Osh unctions region IDA-REDP-CS-IC-2021-2 / Co Improving Regional Economi Individual Consult nsultant for Development of t IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2021-09-27 2021-05-18 2021-10-27 2021-11-01 2021-12-31 2022-12-26 ant Selection he Regional tourism strategy unctions for Osh region IDA-REDP-CS-IC-2021-21 / Fo r the Consultancy to provide Implementation Support and Individual Consult IDA / 65580 Post Open 0.00 Canceled 2021-12-12 2021-10-07 2022-01-30 2022-02-20 2022-03-27 2022-09-23 support to ARIS with Social Is Monitoring and Evaluation ant Selection sues for RED Project IDA-REDP-CS-IC-2021-22 / Fo r the Consultancy to provide Implementation Support and Individual Consult IDA / 65580 Post Limited 7,055.99 Signed 2021-12-12 2021-10-12 2021-12-26 2022-04-04 2022-02-20 2022-04-04 2022-03-27 2022-04-06 2022-09-23 support to ARIS with Social Is Monitoring and Evaluation ant Selection sues for RED Project IDA-REDP-CS-IC-2021-19 / C onsultants for the developme Strengthening Agri-Food Sup Individual Consult nt of business plans and proj IDA / 65580 Post Open 0.00 Canceled 2021-10-29 2021-12-17 2022-01-07 2022-02-11 2022-08-10 ply Chains and SMEs ant Selection ect proposals at the stages o f selection of productive part nerships IDA-REDP-CS-IC-2021-24 / C Catalyzing Investments for T onsulting for conducting rese Individual Consult Pending Impleme IDA / 65580 ourism and Urban Developm Post Open 0.00 2021-11-30 2021-12-25 2022-01-04 2022-01-20 2022-04-20 arch on tourism statistics an ant Selection ntation ent d developing recommendatio ns for impoving IDA-REDP-CS-IC-2021-6 / Loc Improving Regional Economi al consultant for for MinAgri, Individual Consult IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2020-11-25 2020-12-25 2020-12-30 2021-02-28 2022-02-23 Osh oblast administration an ant Selection unctions d other stakeholders 1 IDA-REDP-CS-IC-2021-7 / Loc Improving Regional Economi al consultant for for MinAgri, Individual Consult IDA / 65580 c Planning and Regulatory F Post Open 0.00 Canceled 2020-12-21 2021-01-20 2021-01-25 2021-03-26 2022-03-21 Osh oblast administration an ant Selection unctions d other stakeholders 2 IDA-REDP-CS-IC-2021-25 / C onsultant - trainer for capacit y building of specialists of go Improving Regional Economi vernment bodies and process Individual Consult IDA / 65580 c Planning and Regulatory F Post Open 1,627.02 Signed 2021-12-05 2021-11-25 2022-01-23 2022-04-05 2022-02-13 2022-04-03 2022-03-20 2022-04-14 2022-09-16 ing enterprises on food safet ant Selection unctions y in accordance with internat ional food quality and safety standards (ISO 9001, ISO 220 00, FSSC 22000). IDA-REDP-CS-IC-2021-26 / C onsultant-trainer for capacity building of specialists of gove rnment bodies and agricultur Improving Regional Economi Individual Consult al producers on ensuring the IDA / 65580 c Planning and Regulatory F Post Open 1,627.02 Signed 2021-12-05 2021-11-25 2022-01-23 2022-04-01 2022-02-13 2022-04-01 2022-03-20 2022-04-06 2022-09-16 ant Selection safety of agricultural producti unctions on in accordance with intern ational standards (GLOBAL G .A.P., Organic, ISO 14000, etc .) for domestic mar IDA-REDP-CS-CQS-2021-30 / Implementation Support and Individual Consult Pending Impleme IDA / 65580 Post Open 0.00 2023-05-05 2023-06-23 2023-07-14 2023-08-18 2024-02-14 Technical audit Monitoring and Evaluation ant Selection ntation IDA-REDP-CS-IC-2021-31 / S Implementation Support and Individual Consult election of institutional devel IDA / 65580 Post Limited 9,490.78 Signed 2021-12-05 2021-12-08 2021-12-10 2022-04-05 2021-12-31 2022-04-05 2022-02-04 2022-04-07 2022-08-03 Monitoring and Evaluation ant Selection opment consultant IDA-REDP-CS-IC-2021-27 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult IDA / 65580 Post Open 0.00 Canceled 2021-12-27 2022-02-14 2022-03-07 2022-04-11 2023-10-03 luation of business plans and ply Chains and SMEs ant Selection Sub-project proposals IDA-REDP-CS-IC-2021-32 / C Catalyzing Investments for T Individual Consult Under Implement onsultant to develop a websit IDA / 65580 ourism and Urban Developm Post Open 0.00 2022-04-28 2022-05-13 2022-06-16 2022-07-07 2022-08-11 2023-02-07 ant Selection ation e of the Public-Private Coope ent ration Program IDA-REDP-CS-IC-2021-14 / C onsultant-trainer on capacity building of employees of the Ministry of Agriculture of the Strengthening Agri-Food Sup Individual Consult Under Implement Kyrgyz Republic, specialists o IDA / 65580 Post Open 0.00 2022-05-25 2022-06-06 2022-07-13 2022-08-03 2022-09-07 2023-03-06 ply Chains and SMEs ant Selection ation f the Regional Economic Dev elopment Project of Osh obla st and Osh city, ARIS and the Agribusiness Competitivenes s Center on building a IDA-REDP-CS-IC-2021-5 / Int Improving Regional Economi ernational consultant for Min Individual Consult Pending Impleme IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2022-07-22 2022-09-09 2022-09-30 2022-11-04 2023-05-03 Agri, Osh oblast administrati ant Selection ntation unctions on and other stakeholders Page 8 IDA-REDP-CS-IC-2021-28 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult Under Implement IDA / 65580 Post Open - National 0.00 2022-10-06 2022-10-04 2022-11-24 2022-11-02 2022-12-15 2022-11-02 2023-01-19 2023-07-18 luation of business plans and ply Chains and SMEs ant Selection ation Sub-project proposals IDA-REDP-CS-IC-2022-33 / C Catalyzing Investments for T Individual Consult onsultancy services of an int IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2022-11-14 2022-10-31 2023-01-02 2023-01-23 2023-02-27 2023-08-26 ant Selection ernational expert in the field ent of museology IDA-REDP-CS-IC-2022-34 / C Catalyzing Investments for T Individual Consult onsultancy services of an int IDA / 65580 ourism and Urban Developm Post Open - National 0.00 Canceled 2022-11-14 2022-10-31 2023-01-02 2023-01-23 2023-02-27 2023-08-26 ant Selection ernational World Heritage ex ent pert IDA-REDP-CS-IC-2022-34/1 / Catalyzing Investments for T Individual Consult Open - Internationa Under Implement Consultancy services of an in IDA / 65580 ourism and Urban Developm Post 0.00 2022-11-14 2022-11-23 2023-01-02 2023-01-23 2023-02-27 2023-05-28 ant Selection l ation ternational World Heritage ex ent pert IDA-REDP-CS-IC-2021-29 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult Under Implement IDA / 65580 Post Open - National 0.00 2023-03-24 2023-03-24 2023-05-12 2023-06-02 2023-07-07 2024-01-03 luation of business plans and ply Chains and SMEs ant Selection ation Sub-project proposals IDA-REDP-CS-IC-2023-3 / Cre Strengthening Agri-Food Sup Individual Consult Under Implement dit specialist for evaluation of IDA / 65580 Post Open - National 0.00 2023-03-24 2023-03-25 2023-05-12 2023-06-02 2023-07-07 2024-01-03 ply Chains and SMEs ant Selection ation credit documentation of VC p articipants IDA-REDP-CS-IC-2021-30 / In dependent consultant on eva Strengthening Agri-Food Sup Individual Consult Under Implement IDA / 65580 Post Open - National 0.00 2023-03-31 2023-03-24 2023-05-19 2023-06-09 2023-07-14 2024-01-10 luation of business plans and ply Chains and SMEs ant Selection ation Sub-project proposals IDA-REDP-CS-IC-2023-2 / Sh Improving Regional Economi Individual Consult Under Implement ort-term individual consultan IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2023-03-31 2023-03-25 2023-05-19 2023-06-09 2023-07-14 2024-01-10 ant Selection ation t for laboratory equipment unctions IDA-REDP-CS-IC-2021-3 / Co Improving Regional Economi Individual Consult Under Implement nsultant for sowtfare desing IDA / 65580 c Planning and Regulatory F Post Open - National 0.00 2020-11-25 2023-04-19 2020-12-25 2020-12-30 2021-02-28 2022-02-23 ant Selection ation and on-job training unctions IDA-REDP-CS-IC-2022-33/1/T R1 / Consultancy services of Strengthening Agri-Food Sup Individual Consult Pending Impleme IDA / 65580 Post Open - National 0.00 2023-06-16 2023-08-04 2023-08-25 2023-09-29 2024-03-27 an international expert in the ply Chains and SMEs ant Selection ntation field of museology IDA-REDP-CS-IC-2022-33/1 / Catalyzing Investments for T Individual Consult Open - Internationa Consultancy services of an in IDA / 65580 ourism and Urban Developm Post 0.00 Canceled 2022-11-14 2022-11-23 2023-01-02 2023-04-06 2023-01-23 2023-02-27 2023-05-28 ant Selection l ternational expert in the field ent of museology IDA-REDP-CS-IC-2023-4 / Co Strengthening Agri-Food Sup Individual Consult Pending Impleme nsultant to develop a Procure IDA / 65580 Post Open - National 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ply Chains and SMEs ant Selection ntation ment Manual on Productive P artnerships Page 9