Public Disclosure Copy The World Bank Implementation Status & Results Report Turkiye Irrigation Modernization (P158418) Turkiye Irrigation Modernization (P158418) EUROPE AND CENTRAL ASIA | Turkiye | Water Global Practice | IBRD/IDA | Investment Project Financing | FY 2019 | Seq No: 11 | ARCHIVED on 29-Jun-2024 | ISR60786 | Implementing Agencies: Devlet Su İşleri (DSI), Republic of Turkey Key Dates Key Project Dates Bank Approval Date: 22-Jan-2019 Effectiveness Date: 30-May-2019 Planned Mid Term Review Date: 22-Aug-2022 Actual Mid-Term Review Date: 24-Oct-2022 Original Closing Date: 27-Feb-2026 Revised Closing Date: 27-Feb-2026 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the project is to improve irrigation delivery, through rehabilitation and modernization of distribution infrastructure in selected schemes, and through strengthening of capacity of WUAs. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1. Irrigation System Modernization:(Cost $249.00 M) Component 2. Innovation and Institutional Support:(Cost $2.00 M) Component 3. Project Management:(Cost $3.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The Project aims to improve irrigation delivery through rehabilitation and modernization of four schemes under Component 1 and strengthening capacity of Water User Associations (WUAs) under Component 2. Component 1 includes rehabilitation and modernization of four irrigation schemes, namely: Alasehir irrigation scheme in Manisa, Atabey irrigation scheme in Isparta, Eregli-Ivriz left bank irrigation scheme in Konya, and Uzunlu irrigation scheme in Yozgat. The Project activities under Component 2 includes (i) piloting a solar energy-based pumping of groundwater to irrigate an existing irrigation scheme in Bolvadin and (ii) support the implementation of the nationwide WUAs capacity building program to improve irrigation water management. Overall, the project has disbursed US$113.5 million. The work implementation progress for the four contracts has reached 48%. The construction work at Eregli Ivriz is complete. The work progress at Uzunlu is about 77.68% and is expected to be completed by December 2024. A new 6/29/2024 Page 1 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report Turkiye Irrigation Modernization (P158418) contractor is deployed for Alasehir irrigation scheme and the construction work is expected to resume in September/October, 2024; after the end of the irrigation season. For Atabey, the Specific Procurement Notice has been issued in June, 2024. Implementation of works and capacity building activities under GEF-funded Component 2 are progressing well. The work contract for Groundwater Stewardship Pilot which includes installation of solar panels to generate renewable energy is completed and is expected to be connected to the power network of Türkiye Electricity Distribution Inc. The development of SUTEM hardware is completed. A total 803 personnel from WUA’s, DSI General Directorate and Regional Directorates benefitted from the training program. The total irrigation service area planned to be improved was 50,764 hectares, of which 18,048 hectares are completed. Farmers report significant benefits due to improvements in irrigation reliability and adequacy of services including resilience to climate variability and change, reduction in production costs, increases in cropping intensity, increases in crop yield, and diversification towards high value crops. Overall, the emerging results show that the project contributed to sustaining the livelihoods of farmers, who were hitherto affected by water scarcity, which was exacerbated by climate change. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Moderate Moderate Macroeconomic Moderate Substantial Substantial Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Low Low Low Institutional Capacity for Implementation and Moderate Moderate Moderate Sustainability Fiduciary Moderate Moderate Moderate Environment and Social Substantial Substantial Substantial Stakeholders Substantial Moderate Moderate Other -- Low Low Overall Substantial Moderate Moderate Results PDO Indicators by Objectives / Outcomes Improve irrigation service delivery in selected schemes in Turkey IN01431146 ►Area provided with new/improved irrigation or drainage services (Hectare(Ha), Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 15,280.00 18,048.00 50,764.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 This indicator measures the total area of land provided with irrigation and drainage services under the Comments: project, including in (i) the area provided with new irrigation and drainage services, and (ii) the area provided with improved irrigation and drainage services, expressed in hectare (ha). IN01431148 6/29/2024 Page 2 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report Turkiye Irrigation Modernization (P158418) Area provided with new irrigation or drainage services (Hectare(Ha), Corporate Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 0.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 IN01431149 Area provided with improved irrigation or drainage services (Hectare(Ha), Corporate Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 15,280.00 18,048.00 50,764.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 IN01431150 ►Water users provided with improved irrigation service (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1,350.00 4,250.00 17,312.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 This refers to the number of farmers receiving pressurized irrigation water delivery through the Comments: modernization activities financed by the project. IN01431151 Female water users provided with improved irrigation service (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 250.00 415.00 519.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 IN01431152 ►Increase in irrigation efficiency (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 This refers to the increase in irrigation efficiency realized by the reduction of conveyance losses. Values Comments: and targets refer to efficiency increase, in absolute percentage points from baseline, averaged over project schemes. Strengthen the institutional capacity of Water User Associations. IN01431147 ►Water User Associations (WUAs) regularly reporting on water use data (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 181.00 181.00 378.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 6/29/2024 Page 3 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report Turkiye Irrigation Modernization (P158418) This refers to the number of WUAs which are actively collecting and uploading water management data in Comments: the SUTEM MIS Intermediate Results Indicators by Components Component 1. Irrigation Systems Modernization IN01431153 ►Length of modernized irrigation network (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 694.54 718.00 1,521.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 This refers to the length of primary, secondary and tertiary pressurized irrigation network financed by the Comments: project. IN01431155 ►Annual WUA consultations conducted and results discussed via DSI’s communication channels (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 252.00 50.00 245.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 This refers to the formal consultations with WUAs organized by DSI before and during the construction period as well as during the implementation period. The four selected schemes correspond to 5 WUAs Comments: and DSI will conduct 7 consultations per year with each WUA. Results of the annual WUA consultations, including women consultations, will be shared with the water users via DSI’s communication channels. IN01431158 Annual WUA consultations specifically conducted with women (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 20.00 20.00 35.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 IN01431159 Percentage of women participants in consultations reporting increased awareness of WUA's activities and project investments (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 9.80 40.00 90.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 IN01431160 ►Percent of grievances addressed within stipulated timeframe (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 89.19 96.00 80.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 6/29/2024 Page 4 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report Turkiye Irrigation Modernization (P158418) Baseline data will be determined by DSI and then the annual progress will be entered accordingly. The Comments: indicator refers to grievances addressed within stipulated timeframes(tbc)/total number of grievances filed. Component 2: Innovation and Institutional Support IN01431154 ►WUAs trained in the use of SUTEM MIS (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 181.00 378.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 This refers to the number of WUAs which have received the equipment and trainings needed for using the Comments: SUTEM MIS. IN01431156 ►Share of renewable energy used for Bolvadin irrigation (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 78.00 69.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 This refers to the share of solar energy generated for irrigation in Bolvadin Groundwater Stewardship Pilot Comments: being used to cover the electricity needs for the operation of the irrigation system in Bolvadin. IN01431157 ►Reduction in Groundwater Withdrawal by Bolvadin Cooperative (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 16.00 Date 22-Jan-2019 04-Dec-2023 07-Jun-2024 27-Feb-2026 Comments: This indicator monitors the reduction in groundwater withdrawal by the Bolvadin Cooperative. Performance-Based Conditions Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P158418 IBRD-89190 Effective USD 252.00 252.00 0.00 111.36 135.54 45% P158418 TF-A9363 Closed USD 2.00 0.00 2.00 0.00 0.00 0% P167363 TF-B0863 Effective USD 2.00 2.00 0.00 1.83 0.17 92% 6/29/2024 Page 5 of 6 Public Disclosure Copy The World Bank Implementation Status & Results Report Turkiye Irrigation Modernization (P158418) Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P158418 IBRD-89190 Effective 22-Jan-2019 15-Feb-2019 30-May-2019 27-Feb-2026 27-Feb-2026 P158418 TF-A9363 Closed 04-Feb-2019 04-Feb-2019 30-May-2019 27-Feb-2026 03-Jul-2019 P167363 TF-B0863 Effective 04-Feb-2019 04-Feb-2019 30-May-2019 27-Feb-2026 27-Feb-2026 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) P167363-GEF Turkey Irrigation Modernization ,P181624-Additional Financing: Türkiye Irrigation Modernization Project 6/29/2024 Page 6 of 6