PROCUREMENT PLAN (Textual Part) Project information: Republic of Marshall Islands Sustainable Energy Development Project P160096 & P163699 Project Implementation agency: PREP2 PMU, Division of International Development Assistance-Ministry of Finance (DIDA-MOF), and SPC-Pacific Community Date of the Procurement Plan: May 10, 2018 Period covered by this Procurement Plan: May 1, 2018 to Nov 30, 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Code of 1988, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The procurement is open to all eligible firms from any country; 2. The request for bids/request for proposals document shall require the Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting signed contracts, confirming application of, and compliance with, the Bank's Anti- Corruption Guidelines, including without limitation the Bank's right to sanction and the Bank's inspection and audit rights; 3. Publication of contract award information; 4. Rights for the Bank to review procurement documentation and activities; and 5. An effective complaints mechanism. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Work) Goods: is not applicable; Works: is not applicable. PROCUREMENT Marshall Islands : Pacific Resilience Project II under the Pacific Resilience Program PLAN General Information Country: Marshall Islands 2018-10-21 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160096 GPN Date: 2018-06-19 Project Name: Pacific Resilience Project II under the Pacific Resilience Program Loan / Credit No: IDA / D1830, IDA / V0410 Project Implementation Unit, PREP II Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MH-PREP II-PIU-83439-CW-R Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E 2020-07-1 FB / NDMO Building Refurbish IDA / D1830 trengthening, Early Warning Post 750,000.00 0.00 Canceled 2019-11-23 2020-01-18 tions l nvelope 6 ment and Preparedness MH-PREP II-PIU-81920-CW-R Component 2: Strengthening Request for Propo Open - Internationa 35,312,500.0 2023-10-2 IDA / D1830 Prior Multi Stage 0.00 Canceled 2020-12-31 2021-01-05 2021-03-16 2021-06-28 2021-08-02 FP / Coastal Protection Works Coastal Resilience sals l 0 1 MH-PREP II-PIU-119118-CW- Component 1: Institutional S RFQ / Support for NDMO Stre Open - Internationa Single Stage - One E 2021-06-2 IDA / D1830 trengthening, Early Warning Prior Request for Bids 1,050,000.00 0.00 Canceled 2020-09-06 2020-09-11 2020-10-23 2020-11-22 2020-12-27 ngthening as per NDMO Roa l nvelope 5 and Preparedness dmap including NDMO Refurb ishment Works. MH-PREP II-PIU-252921-GO- Component 1: Institutional S RFQ / Support for NDMO Stre Request for Quota Single Stage - One E Other (with field f Under Imple 2024-02-1 IDA / D1830 trengthening, Early Warning Post Open - National 400,000.00 0.00 2023-06-21 2023-08-16 ngthening as per NDMO Roa tions nvelope or explanation) mentation 2 and Preparedness dmap including NDMO Refurb ishment Works MH-PREP II-PIU-356432-CW- Component 1: Institutional S DIR / Installation and Commis Other (with field f Under Imple 2023-11-1 IDA / D1830 trengthening, Early Warning Prior Direct Selection Direct - National 2,300,000.00 0.00 2023-04-13 2023-04-17 2023-04-18 2023-05-01 2023-05-23 sioning of the Emergency Co or explanation) mentation 9 and Preparedness mmunications Network and A ssociated Trainings Request for Bids - MH-PREP II-PIU-239881-CW- Component 2: Strengthening Open - Internationa Single Stage - Two E 36,987,473.0 2024-02-0 IDA / D1830 Prior Request for Bids Works SPD (after 0.00 Canceled 2021-12-01 2022-05-20 2022-02-16 2022-02-16 2021-12-06 2022-07-13 2022-04-27 2022-07-10 2022-08-14 RFB / Coastal Protection Wor Coastal Resilience l nvelope 0 5 prequalification) ks Request for Bids - MH-PREP II-PIU-364075-CW- Works (without pr Component 2: Strengthening Open - Internationa Single Stage - Two E 60,520,000.0 Pending Imp 2027-11-1 RFB / Coastal Protection Wor IDA / D1830 Prior Request for Bids equalification) SP 0.00 2023-06-27 2023-06-29 2023-10-01 2024-05-15 Coastal Resilience l nvelope 0 lementation 5 ks D - Applying contr actor disqualificia tion GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-83438-GO-RF Component 4: Project and Pr Request for Quota Single Stage - One E Q / Office Equipment includin IDA / D1830 Post Open - National 61,000.00 0.00 Canceled 2019-08-05 2019-09-30 2020-03-28 ogram Management tions nvelope g Computers MH-PREP II-PIU-252918-GO- Component 4: Project and Pr Request for Quota Single Stage - One E RFQ / Office Equipment inclu IDA / D1830 Post Open - National 61,000.00 0.00 Signed 2021-10-05 2021-11-03 2021-11-30 2022-05-29 ogram Management tions nvelope ding Computers MH-PREP II-PIU-252920-GO- Component 1: Institutional S RFQ / Supply of IT equipment Request for Quota Single Stage - One E IDA / D1830 trengthening, Early Warning Post Open - National 50,000.00 39,155.87 Signed 2021-10-20 2021-11-11 2021-12-15 2022-07-15 2022-06-13 , outdoor equipment & office tions nvelope and Preparedness furniture under the NDMO Ro admap MH-PREP II-PIU-163821-GO- Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 40,000.00 0.00 Canceled 2020-05-05 2020-06-30 2020-12-27 RFB / Project Vehicle ogram Management tions nvelope MH-PREP II-PIU-301507-GO- Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 50,000.00 0.00 Signed 2022-07-20 2023-03-02 2022-09-14 2023-03-13 RFQ / Project Vehicle Resubm ogram Management tions nvelope ission MH-PREP II-PIU-83436-GO-RF Component 1: Institutional S Open - Internationa Single Stage - One E Q / Emergency Communicati IDA / D1830 trengthening, Early Warning Prior Request for Bids 1,100,000.00 0.00 Canceled 2022-01-03 2022-01-08 2022-02-19 2022-03-21 2022-04-25 2022-10-22 l nvelope on Equipment Supply & Com and Preparedness mission MH-PREP II-PIU-347314-GO- Component 1: Institutional S Request for Quota Single Stage - One E RFQ / VHF Emergency Comm IDA / D1830 trengthening, Early Warning Prior Limited 218,400.00 0.00 Signed 2023-03-12 2023-04-17 2023-05-07 2023-06-20 2023-11-03 tions nvelope unications Equipment Supply and Preparedness MH-PREP II-PIU-348605-GO- Component 4: Project and Pr Request for Quota Single Stage - One E Under Imple IDA / D1830 Post Open - National 10,000.00 0.00 2023-03-18 2023-05-13 2023-11-09 RFQ / Supply of Office Furnitu ogram Management tions nvelope mentation re for PIU MH-PREP II-PIU-342614-GO- Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E RFQ / IT Equipment to Suppo IDA / V0410 trengthening, Early Warning Post 48,700.00 0.00 Signed 2023-03-05 2023-03-27 2023-04-30 2023-10-27 tions l nvelope rt NDMO and Preparedness MH-PREP II-PIU-345824-GO- Component 1: Institutional S Request for Quota Open - Internationa Single Stage - One E RFQ / Non-IT Equipment Sup IDA / V0410 trengthening, Early Warning Post 9,900.00 0.00 Signed 2023-03-17 2023-04-09 2023-05-12 2023-11-08 tions l nvelope port to NDMO and Preparedness MH-PREP II-PIU-355664-GO- Component 1: Institutional S Request for Quota Single Stage - One E Under Imple RFQ / HF Communication Equ IDA / D1830 trengthening, Early Warning Prior Limited 666,550.00 0.00 2023-04-24 2023-04-17 2023-06-19 2023-12-16 tions nvelope mentation ipment for Support to EC Roa and Preparedness dmap MH-PREP II-PIU-361450-GO- Component 1: Institutional S RFQ / Procurement of masts Request for Quota Open - Internationa Single Stage - One E IDA / D1830 trengthening, Early Warning Post 235,000.00 0.00 Signed 2023-05-24 2023-05-17 2023-07-19 2024-01-15 and antennas in support of th tions l nvelope and Preparedness e Emergency Communication s Network NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 MH-PREP II-PIU-81923-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 40,000.00 0.00 Canceled 2019-09-07 2019-11-02 2020-01-31 Q / M and E Satisfaction Surv ogram Management tions nvelope ey MH-PREP II-PIU-81925-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 150,000.00 26,050.00 Signed 2019-07-05 2019-08-30 2021-10-06 2019-10-29 Q / PIU IT Support ogram Management tions nvelope MH-PREP II-PIU-81924-NC-RF Component 4: Project and Pr Request for Quota Single Stage - One E IDA / D1830 Post Open - National 20,000.00 0.00 Canceled 2019-10-05 2019-11-30 2019-12-30 Q / Translation Services ogram Management tions nvelope MH-PREP II-PIU-81919-NC-RF Component 2: Strengthening Request for Quota Open - Internationa Single Stage - One E IDA / D1830 Post 250,000.00 0.00 Canceled 2020-04-05 2020-05-31 2020-11-27 Q / UXO Removal Services Coastal Resilience tions l nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-83435-CS-QC Component 2: Strengthening Quality And Cost- Open - Internationa BS / Coastal Engineering Desi IDA / D1830 Prior 3,210,000.00 2,897,518.50 Signed 2018-10-30 2019-01-14 2018-11-20 2019-01-30 2019-01-03 2019-11-05 2019-01-31 2020-02-17 2019-03-02 2020-04-06 2019-04-06 2020-09-07 2019-05-11 2020-10-25 2021-04-30 Coastal Resilience Based Selection l gn & Supervision Firm MH-PREP II-PIU-81918-CS-UN Component 1: Institutional S UN Agencies (Dire / Community DRM and Emerg IDA / D1830 trengthening, Early Warning Prior Direct 500,000.00 500,000.00 Signed 2020-01-09 2021-06-06 2021-12-29 ct) ency Communications Traini and Preparedness ng (IOM-UN) Component 1: Institutional S MH-PREP II-PIU-81916-CS-CQ Consultant Qualifi Open - Internationa IDA / D1830 trengthening, Early Warning Post 190,000.00 0.00 Canceled 2018-11-30 2018-12-21 2019-02-03 2018-11-06 2019-03-05 2019-04-09 2019-08-07 S / NDMO Building Design cation Selection l and Preparedness MH-PREP II-PIU-119121-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / NDMO Structural Analysi IDA / D1830 trengthening, Early Warning Post 190,000.00 0.00 Canceled 2019-06-30 2019-07-21 2019-09-03 2019-10-03 2019-11-07 2020-05-05 cation Selection l s and Refurbishment Design and Preparedness MH-PREP II-PIU-163827-CS-C Component 1: Institutional S Consultant Qualifi QS / NAP Community Consult IDA / D1830 trengthening, Early Warning Prior Limited 500,000.00 0.00 Under Review 2020-05-05 2021-04-11 2020-05-19 2021-09-21 2020-06-18 2022-04-19 2020-07-23 2021-01-19 cation Selection ation and Preparedness MH-PREP II-PIU-110299-CS-C Component 4: Project and Pr Consultant Qualifi IDA / D1830 Post Limited 300,000.00 218,501.11 Signed 2020-04-16 2021-05-31 2020-04-30 2021-09-29 2020-05-30 2022-05-27 2020-07-04 2022-07-26 2020-12-31 QS / Communications and Me ogram Management cation Selection dia Firm MH-PREP II-PIU-217361-CS-Q CBS / Design of New NDMO Component 1: Institutional S Quality And Cost- Open - Internationa Warehouse and Office Accom IDA / D1830 trengthening, Early Warning Prior 550,000.00 0.00 Signed 2021-02-05 2021-09-16 2021-02-26 2021-11-30 2021-04-11 2022-05-01 2021-05-09 2022-06-23 2021-06-08 2022-09-27 2021-07-13 2023-02-12 2021-08-17 2023-03-29 2022-08-17 Based Selection l modation and Structural Anal and Preparedness ysis of the Existing NDMO Bui lding MH-PREP II-PIU-163844-CS-Q Component 1: Institutional S Quality And Cost- Open - Internationa CBS / Vulnerability and Planni IDA / D1830 trengthening, Early Warning Prior 600,000.00 0.00 Canceled 2020-03-17 2020-04-07 2020-05-21 2020-06-18 2020-07-18 2020-08-22 2020-09-26 2021-09-26 Based Selection l ng Consultancy Firm and Preparedness MH-PREP II-PIU-303510-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / Vulnerability and Planni IDA / D1830 trengthening, Early Warning Prior 500,000.00 0.00 Signed 2022-07-24 2022-07-30 2022-08-14 2022-09-06 2022-09-27 2022-11-09 2022-10-27 2023-04-02 2022-12-01 2023-05-30 cation Selection l ng Consultancy Firm and Preparedness MH-PREP II-PIU-163825-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / Community Vulnerability IDA / D1830 trengthening, Early Warning Post 250,000.00 0.00 Canceled 2020-05-03 2020-05-24 2020-07-07 2020-08-06 2020-09-10 2021-03-09 cation Selection l Mapping and Training and Preparedness MH-PREP II-PIU-163847-CS-C Component 1: Institutional S Consultant Qualifi Open - Internationa QS / Climate Financing Techn IDA / D1830 trengthening, Early Warning Post 200,000.00 0.00 Canceled 2023-06-01 2023-06-22 2023-08-05 2023-09-04 2023-10-09 2024-04-06 cation Selection l ical Assistance and Preparedness INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MH-PREP II-PIU-81917-CS-CD Component 2: Strengthening S / Coastal Vulnerability Asse IDA / D1830 Prior Direct Selection Direct 500,000.00 592,782.00 Signed 2019-04-04 2019-10-02 2019-04-14 2019-12-10 2019-06-18 2020-03-21 2020-01-10 Coastal Resilience ssment Firm MH-PREP II-PIU-81834-CS-IN Component 1: Institutional S Individual Consult DV / Emergency Communicat IDA / D1830 trengthening, Early Warning Post Open 120,000.00 64,425.00 Terminated 2019-04-30 2019-06-14 2019-06-18 2019-09-19 2019-07-09 2019-11-01 2019-08-13 2019-11-21 2020-06-08 ant Selection ion Specialist and Preparedness MH-PREP II-PIU-81915-CS-CD Component 2: Strengthening IDA / D1830 Prior Direct Selection Direct 50,000.00 0.00 Canceled 2018-11-16 2018-11-26 2019-01-30 2022-11-10 S / Coastal Design Adviser Coastal Resilience Component 1: Institutional S MH-PREP II-PIU-81927-CS-IN Individual Consult IDA / D1830 trengthening, Early Warning Post Open 480,000.00 0.00 Canceled 2018-10-15 2018-12-03 2018-12-24 2019-01-28 2021-01-17 DV / DRM and CCA Adviser ant Selection and Preparedness MH-PREP II-PIU-81928-CS-IN Component 1: Institutional S Individual Consult DV / Disaster and Climate Ris IDA / D1830 trengthening, Early Warning Post Open 202,500.00 0.00 Canceled 2018-10-15 2018-12-03 2018-12-24 2019-01-28 2021-01-17 ant Selection k Governance Adviser and Preparedness MH-PREP II-PIU-81926-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Limited 180,000.00 0.00 Canceled 2018-12-28 2019-01-02 2019-01-23 2019-02-27 2019-08-26 DV / Ebeye Project Represent Coastal Resilience ant Selection ative Component 1: Institutional S MH-PREP II-PIU-109655-CS-I Individual Consult IDA / D1830 trengthening, Early Warning Prior Open 324,000.00 648,000.00 Signed 2018-05-01 2018-01-03 2018-06-19 2018-08-24 2018-07-10 2018-09-27 2018-08-24 2018-10-01 2020-12-31 NDV / DRM&CCA Adviser ant Selection and Preparedness MH-PREP II-PIU-109653-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Prior Open 720,000.00 790,313.00 Signed 2017-02-14 2016-11-30 2017-03-28 2017-03-24 2017-04-20 2017-05-01 2017-05-01 2017-05-02 2020-05-14 NDV / Project Manager ogram Management ant Selection MH-PREP II-PIU-109656-CS-I Component 2: Strengthening Individual Consult IDA / D1830 Post Open 80,280.00 80,280.00 Completed 2018-04-18 2018-05-31 2018-06-06 2018-05-24 2018-06-27 2018-05-24 2018-07-31 2018-08-04 2020-07-01 2020-01-13 NDV / Ebeye Project Represe Coastal Resilience ant Selection ntative MH-PREP II-PIU-109654-CS-I Component 1: Institutional S Individual Consult NDV / Disaster and Climate R IDA / D1830 trengthening, Early Warning Prior Open 206,750.00 602,200.00 Signed 2018-04-01 2018-02-01 2018-05-20 2019-08-06 2018-06-10 2018-09-14 2018-07-13 2018-09-16 2020-08-31 ant Selection isk Governance Adviser and Preparedness Page 2 MH-PREP II-PIU-81838-CS-IN Component 4: Project and Pr Individual Consult DV / Communications & Medi IDA / D1830 Prior Open 240,000.00 0.00 Canceled 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2021-03-04 ogram Management ant Selection a Specialist MH-PREP II-PIU-110300-CS-I Component 1: Institutional S Individual Consult NDV / Strategic Emergency C IDA / D1830 trengthening, Early Warning Post Open 80,000.00 135,100.00 Signed 2019-07-30 2019-06-14 2019-09-17 2019-09-19 2019-10-08 2019-11-01 2019-11-12 2019-11-25 2020-05-10 2022-07-08 ant Selection ommunications Adviser and Preparedness MH-PREP II-PIU-81832-CS-IN Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 30,000.00 0.00 Canceled 2020-03-01 2020-04-19 2020-05-10 2020-06-14 2020-08-13 DV / Mid-term Reviewer ogram Management ant Selection MH-PREP II-PIU-81841-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 150,000.00 0.00 Canceled 2019-09-30 2020-02-18 2019-11-18 2019-12-09 2020-01-13 2020-07-11 DV / Value Engineering Coastal Resilience ant Selection MH-PREP II-PIU-137152-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Prior Open 480,000.00 13,022.00 Terminated 2020-05-16 2020-02-17 2020-07-04 2020-05-14 2020-07-25 2020-08-02 2020-08-29 2020-08-11 2021-02-25 NDV / Project Manager Post 2 ogram Management ant Selection 020 MH-PREP II-PIU-109652-CS-I Component 2: Strengthening Individual Consult IDA / D1830 Post Open 470,000.00 470,000.00 Signed 2017-10-25 2017-10-31 2017-11-01 2017-11-07 2017-11-19 2017-11-15 2017-12-20 2018-01-10 2020-01-31 NDV / Original Civil Engineeri Coastal Resilience ant Selection ng Advisor MH-PREP II-PIU-160075-CS-C Component 2: Strengthening IDA / D1830 Post Direct Selection Direct 150,000.00 154,975.00 Signed 2020-02-19 2020-03-05 2020-02-24 2020-04-17 2020-04-29 2020-06-21 2021-10-31 DS / Value Engineering Firm Coastal Resilience MH-PREP II-PIU-110298-CS-I Component 4: Project and Pr Individual Consult NDV / Local Communications IDA / D1830 Post Open 230,000.00 112,879.67 Terminated 2020-03-19 2020-05-19 2020-05-07 2020-09-14 2020-05-28 2020-10-15 2020-07-02 2020-11-08 2020-12-29 ogram Management ant Selection and M & E Officer MH-PREP II-PIU-81835-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 80,000.00 0.00 Canceled 2020-04-01 2020-05-20 2020-06-10 2020-07-15 2021-07-10 DV / Work Probity Assurance Coastal Resilience ant Selection Provider Component 1: Institutional S MH-PREP II-PIU-163845-CS-I Individual Consult IDA / D1830 trengthening, Early Warning Post Open 100,000.00 0.00 Canceled 2020-05-02 2021-03-23 2020-06-20 2020-07-11 2020-08-15 2021-02-11 NDV / NAP Coordinator ant Selection and Preparedness MH-PREP II-PIU-163848-CS-I Component 1: Institutional S Individual Consult NDV / Donor Coordination Te IDA / D1830 trengthening, Early Warning Prior Open 400,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 ant Selection chnical Assistance and Preparedness MH-PREP II-PIU-137154-CS-I Component 2: Strengthening Individual Consult NDV / Ebeye Project Represe IDA / D1830 Post Limited 100,000.00 0.00 Canceled 2020-07-01 2020-07-06 2020-07-27 2020-08-31 2021-02-27 Coastal Resilience ant Selection ntative Post 2020 MH-PREP II-PIU-81837-CS-IN Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 180,000.00 0.00 Canceled 2019-07-30 2019-09-23 2019-09-17 2019-10-08 2019-11-12 2023-07-22 DV / Project Officer ogram Management ant Selection MH-PREP II-PIU-135263-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 190,000.00 0.00 Canceled 2019-09-27 2019-12-02 2019-11-15 2019-12-06 2020-01-10 2020-07-08 NDV / Implementation Suppo ogram Management ant Selection rt Specialist MH-PREP II-PIU-119120-CS-I Component 1: Institutional S Individual Consult NDV / Civil Engineering Advis IDA / D1830 trengthening, Early Warning Prior Open 470,000.00 0.00 Canceled 2019-08-19 2020-02-10 2019-10-07 2019-10-28 2019-12-02 2020-05-30 ant Selection er and Preparedness MH-PREP II-PIU-165685-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 255,000.00 70,000.00 Signed 2020-04-17 2019-12-16 2020-06-05 2020-06-09 2020-06-26 2020-06-09 2020-07-31 2020-06-10 2021-01-27 NDV / Project Officer ogram Management ant Selection MH-PREP II-PIU-165691-CS-I Component 4: Project and Pr Individual Consult IDA / D1830 Post Open 305,000.00 180,000.00 Terminated 2019-12-15 2019-12-01 2020-02-02 2020-01-09 2020-02-23 2020-02-01 2020-03-29 2020-02-15 2020-09-25 NDV / Implementation Suppo ogram Management ant Selection rt Specialist MH-PREP II-PIU-165694-CS-I Component 1: Institutional S Individual Consult NDV / Civil Engineering Advis IDA / D1830 trengthening, Early Warning Prior Open 770,000.00 734,375.00 Signed 2020-03-23 2020-05-06 2020-05-11 2020-04-24 2020-06-01 2020-07-27 2020-07-06 2020-08-05 2021-01-02 ant Selection er and Preparedness MH-PREP II-PIU-163846-CS-I Component 1: Institutional S Individual Consult NDV / Climate Change Adapt IDA / D1830 trengthening, Early Warning Prior Open 300,000.00 303,000.00 Terminated 2020-05-02 2020-05-06 2020-06-20 2020-07-09 2020-07-11 2020-08-11 2020-08-15 2020-08-19 2021-02-11 ant Selection ation Specialist and Preparedness MH-PREP II-PIU-202148-CS-C Component 4: Project and Pr IDA / D1830 Prior Direct Selection Direct 480,000.00 442,000.00 Signed 2020-10-30 2020-11-20 2020-11-03 2020-12-01 2020-11-06 2021-01-12 2022-11-05 DS / PREP II Project Manager ogram Management 2021 MH-PREP II-PIU-205222-CS-C Component 4: Project and Pr DS / Project Management Su IDA / D1830 Prior Direct Selection Direct 86,820.00 82,200.00 Signed 2020-11-20 2020-12-22 2020-11-30 2021-02-09 2020-12-15 2021-03-10 2021-06-13 ogram Management pport Specialist Component 1: Institutional S MH-PREP II-PIU-234808-CS-C IDA / D1830 trengthening, Early Warning Post Direct Selection Direct 100,000.00 83,625.00 Signed 2021-05-22 2021-07-01 2021-06-01 2021-08-23 2021-08-05 2021-09-06 2022-02-01 DS / NAP Coordinator and Preparedness MH-PREP II-PIU-246795-CS-I Component 1: Institutional S Individual Consult NDV / Disaster and Climate R IDA / D1830 trengthening, Early Warning Prior Open 400,000.00 0.00 Signed 2021-08-09 2021-10-11 2021-09-27 2022-03-30 2021-10-18 2022-04-23 2021-11-22 2023-05-21 2022-05-21 ant Selection esilience Donor Coordination and Preparedness Adviser Component 1: Institutional S MH-PREP II-PIU-81836-CS-IN Individual Consult IDA / D1830 trengthening, Early Warning Post Open 60,000.00 0.00 Signed 2019-04-28 2022-06-23 2019-06-16 2023-02-19 2019-07-07 2023-02-19 2019-08-11 2019-11-09 DV / DRM Legislative Drafter ant Selection and Preparedness MH-PREP II-PIU-228529-CS-I Component 1: Institutional S Individual Consult NDV / Donor Coordination Te IDA / D1830 trengthening, Early Warning Prior Direct 400,000.00 0.00 Canceled 2021-04-30 2021-08-16 2021-05-10 2021-05-31 2021-07-05 2022-01-01 ant Selection chnical Assistance and Preparedness MH-PREP II-PIU-257808-CS-I Component 4: Project and Pr Individual Consult NDV / Implementation Suppo IDA / D1830 Post Open 190,000.00 0.00 Signed 2021-10-31 2022-02-03 2021-12-19 2022-11-10 2022-01-09 2022-07-13 2022-02-13 2022-08-12 ogram Management ant Selection rt Specialist 2022 MH-PREP II-PIU-81840-CS-IN Component 2: Strengthening Individual Consult IDA / D1830 Post Open 120,000.00 0.00 Canceled 2019-11-30 2020-01-18 2020-02-08 2020-03-14 2020-09-10 DV / Contracts Disputes Boar Coastal Resilience ant Selection d Member MH-PREP II-PIU-301513-CS-I Component 1: Institutional S NDV / Senior Emergency Co Individual Consult IDA / V0410 trengthening, Early Warning Post Direct 80,000.00 0.00 Signed 2022-07-08 2022-07-14 2022-07-18 2022-08-11 2022-08-08 2022-08-16 2022-09-12 2023-03-11 mmunications Network Com ant Selection and Preparedness missioning Specialist MH-PREP II-PIU-137153-CS-I Component 1: Institutional S Individual Consult NDV / DRM&CCA Adviser pos IDA / D1830 trengthening, Early Warning Prior Open 324,000.00 0.00 Canceled 2021-01-01 2021-02-19 2021-03-12 2021-04-16 2021-10-13 ant Selection t 2020 and Preparedness Page 3 MH-PREP II-PIU-327141-CS-C Component 1: Institutional S Direct - Internation DS / Climate Change Adaptat IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 Canceled 2022-11-23 2022-12-02 2022-12-03 2022-12-20 2023-02-06 2023-08-05 al ion Specialist 2023 and Preparedness MH-PREP II-PIU-301516-CS-I Component 1: Institutional S NDV / Junior Emergency Com Individual Consult IDA / D1830 trengthening, Early Warning Post Open 50,000.00 0.00 Canceled 2022-10-01 2022-11-19 2022-12-10 2023-01-14 2023-07-13 munications Network Commi ant Selection and Preparedness ssioning Specialist MH-PREP II-PIU-347593-CS-I Component 4: Project and Pr Individual Consult NDV / Communication and M IDA / D1830 Post Open - National 30,000.00 0.00 Canceled 2023-03-07 2023-02-13 2023-04-25 2023-05-02 2023-05-16 2023-06-20 2023-12-17 ogram Management ant Selection onitoring & Evaluations Offic er MH-PREP II-PIU-81831-CS-IN Component 1: Institutional S Individual Consult Open - Internationa DV / Change Management Ad IDA / D1830 trengthening, Early Warning Prior 480,000.00 0.00 Canceled 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2021-03-04 ant Selection l visor and Preparedness MH-PREP II-PIU-327137-CS-C Component 1: Institutional S DS / Disaster and Climate Re Direct - Internation IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 Canceled 2022-11-23 2022-12-02 2022-12-03 2022-12-19 2023-02-06 2023-08-05 silience Donor Coordination A al and Preparedness dviser (DCR-DCA) 2023 MH-PREP II-PIU-327141-CS-C Component 1: Institutional S Direct - Internation DS-2 / Climate Change Adapt IDA / D1830 trengthening, Early Warning Post Direct Selection 210,000.00 0.00 Signed 2023-03-16 2023-01-17 2023-03-26 2023-01-17 2023-05-30 2023-11-26 al ation Specialist 2023 and Preparedness MH-PREP II-PIU-362384-CS-I Component 4: Project and Pr Individual Consult Under Implement IDA / D1830 Post Open - National 20,000.00 0.00 2023-05-26 2023-05-19 2023-07-14 2023-08-04 2023-09-08 2024-03-06 NDV / Project Officer 2023 ogram Management ant Selection ation MH-PREP II-PIU-362549-CS-I Component 4: Project and Pr Individual Consult Open - Internationa Under Implement IDA / D1830 Post 60,000.00 0.00 2023-05-26 2023-05-19 2023-07-14 2023-08-04 2023-09-08 2024-03-06 NDV / Financial Management ogram Management ant Selection l ation Specialist MH-PREP II-PIU-81839-CS-IN Component 4: Project and Pr Individual Consult Open - Internationa Pending Impleme IDA / D1830 Post 30,000.00 0.00 2023-09-01 2023-10-20 2023-11-10 2023-12-15 2024-06-12 DV / End Term Reviewer ogram Management ant Selection l ntation MH-PREP II-PIU-365763-CS-I Component 1: Institutional S NDV / Junior Emergency Com Individual Consult Open - Internationa Under Implement IDA / D1830 trengthening, Early Warning Post 84,000.00 0.00 2023-06-16 2023-06-20 2023-08-04 2023-08-25 2023-09-29 2024-03-27 munications Network Commi ant Selection l ation and Preparedness ssioning Specialist Page 4 PROCUREMENT PLAN (Textual Part) Project information: [Mongolia] [COVID-19 emergency response and health system preparedness project] [P-173779] Project Implementation agency: [Ministry of Health] Date of the Procurement Plan: [25 March 2020] Period covered by this Procurement Plan: [Apr-Jun 2020] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” dated July 2016 (Revised in November 2017 and August 2018) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Law on Public Procurement of Goods, Works and Services, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not applicable (most if the Goods are not manufactured in country); Works: Not applicable (no works planned under this Project). Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Under HIES the Project will receive the bank-facilitated procurement (BFP). BFP activities will include the following: 1. Conduct extensive market engagement and survey to identify available stock of the agreed list of critical medical consumables and equipment needed under this COVID10 response project (attached) in the quantities therein specified; 2. Assist [the Implementing Entity] in (i) negotiating prices, delivery terms, and other contract conditions with identified suppliers; 3. Draft final award letters and/or contracts adapted to specific market conditions, on a fit-for-purpose basis and ensuring consistency with Bank’s procurement framework; 4. Provide additional hands-on support in contracting to outsource logistics. Other HEIS activities are as follows: 5. Draft technical requirements and specifications, as requested by the [Implementing Entity; 6. Assist [the Implementing Entity] in drafting procurement documents; and 7. Provide advice on evaluation procedures, participate as observers during negotiations, by only clarifying matters of the Bank Procurement Regulations. Other Relevant Procurement Information. Given the nature of the Project, the procurement approach shall prioritize fast track emergency procurement for the required goods, works and services that include the following measures: - Direct Contracting and/or Limited Competition with identified manufacturers of equipment; - Use of CQS, RFQ or National Open/Limited Competitive procurement procedures as appropriate and agreed with the Bank in the Procurement Plan. - Considering existing framework agreements with international agencies like UNICEF, WHO, UNOPS and other UN agencies for procurement of medicines, medical supplies and commodity equipment for emergency requirements where the terms offered are more beneficial (such as delivery times); - Increasing advance payments to 40% when supported by an advance payment guarantee; - Waiving the conditions for bid securities and replacing them with Bid Securing Declarations; - Maximizing the use of direct payments to foreign suppliers; - Allowing submission of bids using emails in encrypted files where it is not feasible to receive bids in hardcopy. All procurements under this project will be subject to Post Review (there will be no Prior Review). Thresholds for fast track emergency procurement under the Project are: - Increased threshold for goods for shopping of US$500,000; - Increased threshold for National Procurement of U$1,000,000 and reduced bidding time to 7-14 days; - Use of CQS rather than QCBS for larger contract below (should read ‘above’?) US$500,000. PROCUREMENT Mongolia : MONGOLIA COVID-19 EMERGENCY RESPONSE AND HEALTH SYSTEM PREPAREDNESS PROJECT PLAN General Information Country: Mongolia 2020-04-27 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173799 GPN Date: 2021-08-03 Project Name: MONGOLIA COVID-19 EMERGENCY RESPONSE AND HEALTH SYSTEM PREPAREDNESS PROJECT Loan / Credit No: IDA / 65940, IBRD / 90820, IDA / 68330 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MN-MOH-212439-CW-UN / B Component 2: Strengthening UN Agencies (Dire 2,057,664.0 2022-01-3 uilding Capacity for COVID-1 IDA / 65940 Health Care Delivery Capacit Prior Direct Signed 2021-01-06 2021-01-15 2021-01-06 2021-01-16 2021-01-16 2021-01-19 ct) 0 1 9 Vaccine Infrastructure y GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MN-MOH-169104-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 0.00 Canceled 2020-04-17 2020-04-22 2020-05-06 2020-06-17 1.6. Oxygen equipment Health Care Delivery Capacit y MN-MOH-169366-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 0.00 Canceled 2020-04-20 2020-04-25 2020-05-09 2020-06-20 1.7. Laboratory equipment a Health Care Delivery Capacit nd tests y MN-MOH-169092-GO-DIR / 2. Component 2: Strengthening 1.1. VENTILATORS, CPAP AN IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 6,864,425.00 Signed 2020-04-17 2020-06-19 2020-04-22 2020-06-22 2020-05-06 2020-08-04 2020-06-17 D ACCESSORIES y MN-MOH-169095-GO-DIR / 2. 1.2. AUTOMATIC SUCTION PU MP, AUTOMATIC SYRINGE PU Component 2: Strengthening MP, EXAMINATION LIGHT, VEI IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 242,956.76 Signed 2020-04-17 2020-06-05 2020-04-22 2020-06-01 2020-05-06 2020-10-15 2020-06-17 N DETECTOR, DIGITAL DISTA y NCE THERMOMETER, LARYNG OSCOPE, HANDHELD VIDEO L ARYNGOSOPE, FINGER TYPE PULSOXIMETER MN-MOH-173769-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-05-14 2020-05-22 2020-06-19 .1.3. CORPSE REFRIGERATOR Health Care Delivery Capacit tions nvelope S y MN-MOH-173770-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-10-18 .1.4. ECMO MACHINE Health Care Delivery Capacit tions nvelope y MN-MOH-173773-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-06-18 .1.5. CRRT, HEMODIALYSIS E Health Care Delivery Capacit tions nvelope QUIPMENT y MN-MOH-173780-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-06-18 .1.12. REAL TIME PCR EQUIP Health Care Delivery Capacit tions nvelope MENT y MN-MOH-173776-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.8. MULTIFUNCTIONAL HOS IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-06-18 tions nvelope PITAL BEDS y MN-MOH-169371-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 0.00 Canceled 2020-08-23 2020-08-30 2020-09-20 2020-10-20 1.a.1. Ventilator accessories Health Care Delivery Capacit y MN-MOH-173777-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-06-18 .1.9. CRITICAL CARE CRASH Health Care Delivery Capacit tions nvelope CARTS y MN-MOH-173777-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-08-30 2020-09-27 2020-11-08 2.1.9. CRITICAL CARE CRUSH Health Care Delivery Capacit tions nvelope CARTS y MN-MOH-180288-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 707,294.48 Signed 2020-09-28 2020-05-28 2020-10-05 2020-05-28 2020-10-24 2020-08-25 2020-12-05 1.b.1. DIAGNOSTIC EQUIPME Health Care Delivery Capacit NT y MN-MOH-180319-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 0.00 Canceled 2020-09-14 2020-09-21 2020-10-10 2020-12-05 1.d.6. NEUROLOGICAL ICU E Health Care Delivery Capacit QUIPMENT y MN-MOH-180308-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 948,815.00 Signed 2020-09-14 2020-12-02 2020-09-25 2020-12-02 2020-10-16 2021-05-29 2020-11-27 1.c.1. MEDICAL EQUIPMENT Health Care Delivery Capacit y MN-MOH-180316-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 659,064.00 Signed 2020-09-14 2020-12-01 2020-09-21 2021-01-20 2020-10-10 2021-02-25 2020-12-05 1.d.1. ICU MEDICAL EQUIPME Health Care Delivery Capacit NT y MN-MOH-180321-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 408,195.67 Signed 2020-09-21 2020-10-10 2020-12-12 2020-11-21 .1.d.3. ENDOSCOPY EQUIPME Health Care Delivery Capacit tions nvelope NT y MN-MOH-173778-GO-RFQ / 2 .1.10. REANIMATION EQUIPM Component 2: Strengthening Request for Quota Single Stage - One E ENT (PATIENT MONITORS, DE IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-05-14 2020-05-21 2020-06-18 tions nvelope FIBRILLATORS, OXYGEN CON y CENTRATOR, ANESTHESIA M ACHINES) MN-MOH-173778-GO-RFQ-2 / 2.1.10. REANIMATION EQUIP Component 2: Strengthening Request for Quota Single Stage - One E MENT (PATIENT MONITOR, D IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-08-30 2020-09-27 2020-11-08 tions nvelope EFIBRILLATOR, ECG, OXYGEN y CONCENTRATOR, HIGH FLOW OXYGEN DEVICE) MN-MOH-169373-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 1,269,370.00 Signed 2020-04-20 2020-10-12 2020-04-25 2020-10-09 2020-05-09 2020-12-03 2020-05-30 2.3. N95 masks, PPE Health Care Delivery Capacit y Page 1 MN-MOH-173775-GO-RFQ / 2 .1.7. LABORATORY EQUIPME Component 2: Strengthening NT (AUTOMATED AUTOCLAVE Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-08-30 2020-09-27 2020-11-26 , CO2 INCUBATOR, BIO-SAFE tions nvelope y TY LEVEL 2 CABINET, BENCH TOP CENTRIFUGE, TABLETOP CENTRIFUGE) MN-MOH-173781-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-10-12 2020-11-09 2020-12-21 .1.16. ENDOSCOPY DISINFEC Health Care Delivery Capacit tions nvelope TING UNIT y MN-MOH-173774-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-08-30 2020-09-27 2020-11-08 .1.6. OXYGEN REGULATING E Health Care Delivery Capacit tions nvelope QUIPMENT y MN-MOH-169101-GO-DIR / 2. Component 2: Strengthening 1.14. SPECIFIC LABORATORY IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-08-30 2020-09-04 2020-09-18 2020-11-17 TESTS FOR ZOONOSIS CENTE y R, 25 TYPES MN-MOH-180426-GO-RFQ / 3 Component 3: Implementati Request for Quota Single Stage - One E .5. IT equipment for PIU speci IDA / 65940 on management and Monito Post Limited 19,429.74 Completed 2020-09-06 2020-09-17 2020-10-11 2020-10-01 2020-11-10 2020-12-16 tions nvelope alists ring and Evaluation MN-MOH-169368-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 0.00 Canceled 2020-04-20 2020-04-25 2020-05-09 2020-06-20 1.13. PCR TESTS AND KITS Health Care Delivery Capacit y MN-MOH-173779-GO-RFQ / 2 Component 2: Strengthening .1.11. ISOLATION EQUIPMENT Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-08-30 2020-09-27 2020-11-08 (NEGATIVE PRESSURE ISOLA tions nvelope y TION CHAMBER WITH STRET CHER) MN-MOH-169370-GO-DIR / 2. Component 2: Strengthening 1.15. PCR EXTRACTION KITS IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-08-23 2020-08-30 2020-09-20 2020-11-01 AND SUPPLIES y MN-MOH-169367-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 0.00 Canceled 2020-08-23 2020-08-30 2020-09-20 2020-11-01 2.1.8. INFUSION SETS AND S Health Care Delivery Capacit YRINGES y MN-MOH-180318-GO-DIR / 2. Component 2: Strengthening 1.d.5. EMERGENCY AND ICU IDA / 65940 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-09-14 2020-09-21 2020-10-17 2020-12-12 PREPAREDNESS EQUIPMENT y MN-MOH-180291-GO-DIR / 2. Component 2: Strengthening 1.b.2. SURGICAL AND INTENS IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-09-14 2020-09-21 2020-10-19 2020-11-30 IVE CARE EQUIPMENT y MN-MOH-169369-GO-DIR / 2. Component 2: Strengthening 2.1. INTERFERON ALPHA 2B IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-09-14 2020-09-21 2020-10-12 2020-11-11 NASAL SPRAY y MN-MOH-169102-GO-DIR / 2. Component 2: Strengthening 2.1.2. BACTERIAL LYSATE OM IDA / 65940 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-09-14 2020-09-21 2020-10-12 2020-11-23 -85 BRONCHOMUNAL y MN-MOH-173782-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.17. OXYGEN CYLINDER FIL IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-10-05 2020-11-02 2021-01-31 tions nvelope LING SYSTEM, OXYGEN GAS y PLANT COMBINED MN-MOH-188110-GO-RFB / 2 Component 2: Strengthening Single Stage - One E IBRD / 90820 Post Request for Bids Open - National 0.00 Canceled 2020-08-30 2020-09-18 2020-09-13 2020-09-27 2020-10-06 2020-10-11 2020-11-08 2021-01-07 .1.1.2 General medical equip Health Care Delivery Capacit nvelope ment y MN-MOH-173769-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 2.1.3. CORPSE REFRIGERATO Health Care Delivery Capacit tions nvelope RS y MN-MOH-173770-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 2.1.4. ECMO MACHINE Health Care Delivery Capacit tions nvelope y MN-MOH-173773-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.5. CRRT, HEMODIALYSIS IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 tions nvelope EQUIPMENT y MN-MOH-173774-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.6. OXYGEN REGULATING IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 tions nvelope EQUIPMENT y MN-MOH-173775-GO-RFQ-2 / 2.1.7. LABORATORY EQUIPME Component 2: Strengthening NT (AUTOMATED AUTOCLAVE Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 , CO2 INCUBATOR, BIO-SAFE tions nvelope y TY LEVEL 2 CABINET, BENCH TOP CENTRIFUGE, TABLETOP CENTRIFUGE) MN-MOH-173777-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 2.1.9. CRITICAL CARE CRUSH Health Care Delivery Capacit tions nvelope CARTS y MN-MOH-173778-GO-RFQ-3 / Component 2: Strengthening 2.1.10. REANIMATION EQUIP Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 MENT (PATIENT MONITOR, D tions nvelope y EFIBRILLATOR, ECG, OXYGEN CONCENTRATOR) MN-MOH-173779-GO-RFQ-2 / Component 2: Strengthening 2.1.11. ISOLATION EQUIPMEN Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 T (NEGATIVE PRESSURE ISOL tions nvelope y ATION CHAMBER WITH STRE TCHER) MN-MOH-173780-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 2.1.12. REAL TIME PCR EQUIP Health Care Delivery Capacit tions nvelope MENT y MN-MOH-173781-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.16. ENDOSCOPY DISINFE IBRD / 90820 Health Care Delivery Capacit Post Limited 0.00 Canceled 2020-08-25 2020-10-06 2020-12-05 tions nvelope CTING UNIT y MN-MOH-173782-GO-DIR / 2. Component 2: Strengthening 1.17. OXYGEN CYLINDER FILL IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-08-23 2020-08-30 2020-10-11 2020-12-10 ING SYSTEM, OXYGEN GAS P y LANT COMBINED MN-MOH-169372-GO-DIR / 2. Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 0.00 Canceled 2020-08-23 2020-08-30 2020-09-27 2020-10-27 2.2. PPE (EXAMINATION GLO Health Care Delivery Capacit VES) y Page 2 MN-MOH-169371-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 0.00 Canceled 2020-09-18 2020-10-23 2021-01-21 .1.1.1. Ventilator accessories Health Care Delivery Capacit tions nvelope y MN-MOH-173778-GO-RFQ-4 / 2.1.10. REANIMATION EQUIP Component 2: Strengthening Request for Quota Single Stage - One E MENT (PATIENT MONITOR, D IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-09-18 2020-10-23 2021-01-21 tions nvelope EFIBRILLATOR, ECG, OXYGEN y CONCENTRATOR, HIGH FLOW OXYGEN DEVICE) MN-MOH-173769-GO-RFQ-4 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 104,258.87 Signed 2020-09-18 2020-10-23 2020-10-27 2021-01-21 2.1.3. CORPSE REFRIGERATO Health Care Delivery Capacit tions nvelope RS y MN-MOH-173770-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 201,169.47 Signed 2020-09-18 2020-10-23 2020-11-07 2021-01-21 2.1.4. ECMO MACHINE Health Care Delivery Capacit tions nvelope y MN-MOH-173773-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.5. CRRT, HEMODIALYSIS IBRD / 90820 Health Care Delivery Capacit Post Open - National 459,343.26 Signed 2020-09-18 2020-10-23 2020-11-07 2021-01-21 tions nvelope EQUIPMENT y MN-MOH-173774-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.6. OXYGEN REGULATING IBRD / 90820 Health Care Delivery Capacit Post Open - National 25,307.28 Signed 2020-09-18 2020-10-23 2020-12-25 2021-01-21 tions nvelope EQUIPMENT (CYLINDERS, INH y APERS) MN-MOH-173775-GO-RFQ-3 / 2.1.7. LABORATORY EQUIPME Component 2: Strengthening NT (AUTOMATED AUTOCLAVE Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Open - National 34,586.59 Completed 2020-09-18 2020-10-23 2020-11-11 2021-01-21 2021-06-29 , CO2 INCUBATOR, BIO-SAFE tions nvelope y TY LEVEL 2 CABINET, BENCH TOP CENTRIFUGE, TABLETOP CENTRIFUGE) MN-MOH-173781-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.16. ENDOSCOPY DISINFE IBRD / 90820 Health Care Delivery Capacit Post Open - National 78,547.58 Signed 2020-09-18 2020-10-23 2020-12-09 2021-01-21 tions nvelope CTING UNIT y MN-MOH-173780-GO-RFQ-3 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 171,931.20 Signed 2020-09-18 2020-10-23 2020-11-07 2021-01-21 2.1.12. REAL TIME PCR EQUIP Health Care Delivery Capacit tions nvelope MENT y MN-MOH-169368-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2020-09-18 2020-10-23 2021-01-21 .1.13. PCR TESTS AND KITS Health Care Delivery Capacit tions nvelope y MN-MOH-169101-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.14. SPECIFIC LABORATORY IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-09-18 2020-10-23 2021-01-21 tions nvelope TESTS FOR ZOONOTIC CENTE y R, 25 TYPES MN-MOH-173777-GO-RFQ-4 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 272,884.03 Signed 2020-09-18 2020-10-23 2020-10-29 2021-01-21 2.1.9. CRITICAL CARE CRUSH Health Care Delivery Capacit tions nvelope CARTS y MN-MOH-173779-GO-RFQ-3 / Component 2: Strengthening 2.1.11. ISOLATION EQUIPMEN Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Open - National 129,790.51 Signed 2020-09-18 2020-10-23 2020-12-09 2021-01-21 T (NEGATIVE PRESSURE ISOL tions nvelope y ATION CHAMBER WITH STRE TCHER) MN-MOH-173782-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E 2.1.17. OXYGEN CYLINDER FI IBRD / 90820 Health Care Delivery Capacit Post Open - National 360,090.49 Signed 2020-09-18 2020-10-23 2020-12-09 2021-01-21 tions nvelope LLING SYSTEM, OXYGEN GAS y PLANT MN-MOH-169370-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.15. PCR EXTRACTION KITS IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-09-18 2020-10-23 2021-01-21 tions nvelope AND SUPPLIES y MN-MOH-198939-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 94,166.02 Signed 2020-10-18 2020-11-15 2020-12-12 2020-12-15 .1.d.7. PENDANT SYSTEM Health Care Delivery Capacit tions nvelope y MN-MOH-180318-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 148,921.03 Signed 2020-10-18 2020-11-15 2020-12-12 2020-12-15 .1.d.5. ICU EMERGENCY EQUI Health Care Delivery Capacit tions nvelope PMENT y MN-MOH-180319-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 0.00 Canceled 2020-10-18 2020-11-15 2020-12-15 .1.d.6. ICU HOSPITAL EQUIPM Health Care Delivery Capacit tions nvelope ENT y MN-MOH-198949-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.d.8. IMAGING DIAGNOSTIC IDA / 65940 Health Care Delivery Capacit Post Open - National 52,211.69 Signed 2020-10-18 2020-11-15 2020-12-12 2020-12-15 tions nvelope EQUIPMENT y MN-MOH-201930-GO-DIR / 2. 1.b. ULTRASOUND MACHINES , ECG, PATIENT MONITORS, D Component 2: Strengthening EFIBRILATORS, SYRINGE AND IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 733,605.00 Signed 2020-10-28 2020-10-09 2020-11-11 2020-10-20 2020-12-16 2020-11-25 2021-01-27 INFUSION PUMPS, OXYGEN C y ONCENTRATOR, HEMATOLOG Y AND BLOOD ANALYZERS, NEONATAL CPAP MN-MOH-180298-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 197,321.48 Signed 2020-11-05 2020-12-10 2021-01-19 2021-02-08 .1.b.6. ULTRASOUND 3D/4D Health Care Delivery Capacit tions nvelope MACHINE y MN-MOH-180293-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 0.00 Canceled 2020-06-22 2020-06-29 2020-07-18 2020-09-12 1.b.4. LABORATORY EQUIPME Health Care Delivery Capacit NT y MN-MOH-201965-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. GYNECOLOGY AND OBS IBRD / 90820 Health Care Delivery Capacit Post Open - National 77,644.41 Signed 2020-11-23 2020-12-28 2021-06-16 2021-02-26 tions nvelope TETRICS INSTRUMENTS SET y MN-MOH-201974-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. WASHING, EXTRACTING IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2020-11-23 2020-12-28 2021-02-26 tions nvelope EQUIPMENT y MN-MOH-212442-GO-DIR / C Component 2: Strengthening OVID-19 ANTIGEN TESTS @$ IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2021-01-22 2021-01-29 2021-02-19 2021-04-20 4.95 PER UNIT (INCLUSIVE OF y FREIGHT COST) MN-MOH-201966-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 303,359.67 Signed 2021-01-27 2021-03-03 2021-05-25 2021-05-02 .1.b. ENDOSCOPY, LAPARASC Health Care Delivery Capacit tions nvelope OPY y MN-MOH-213325-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 25,313.29 Completed 2021-01-27 2021-03-03 2021-05-28 2021-05-02 2022-08-21 .1.b. Low temperature steriliz Health Care Delivery Capacit tions nvelope er y Page 3 MN-MOH-180291-GO-RFQ / 2 Component 2: Strengthening .1.b. STATIONERY XRAY MAC Request for Quota Single Stage - One E IBRD / 90820 Health Care Delivery Capacit Post Open - National 323,763.66 Signed 2021-01-27 2021-03-03 2021-01-29 2021-05-02 HINE, FLUOROGRAPHY UNIT, tions nvelope y XRAY PACS VIEWER MN-MOH-201925-GO-DIR / 2. Component 2: Strengthening 1.b. COMPUTER TOMOGRAPH IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2020-10-28 2020-11-11 2020-12-16 2021-01-27 Y MACHINE, 64 SLICES y MN-MOH-201925-GO-RFB / 2 Component 2: Strengthening Single Stage - One E IBRD / 90820 Post Request for Bids Open - National 667,479.51 Signed 2021-01-20 2021-01-13 2021-01-27 2021-02-10 2021-02-02 2021-02-24 2021-02-10 2021-03-10 2021-02-24 2021-09-06 .1.b Computer tomography Health Care Delivery Capacit nvelope 64 slice y MN-MOH-201967-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 42,530.29 Signed 2021-01-27 2021-03-03 2021-02-24 2021-05-02 .1.b. Cardiotocography, Fetal Health Care Delivery Capacit tions nvelope Doppler y MN-MOH-201968-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 159,748.69 Signed 2021-01-27 2021-03-03 2021-02-24 2021-05-02 .1.b. ANAESTHESIA EQUIPME Health Care Delivery Capacit tions nvelope NT y MN-MOH-180299-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 140,337.96 Signed 2021-01-27 2021-02-22 2021-02-24 2021-04-05 .1.b.7. PATHOLOGICAL EQUIP Health Care Delivery Capacit tions nvelope MENT y MN-MOH-201975-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. Delivery bed and nursin IBRD / 90820 Health Care Delivery Capacit Post Open - National 199,528.92 Signed 2021-01-27 2021-03-03 2021-02-24 2021-05-02 tions nvelope g equipment y MN-MOH-213362-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 8,716.95 Signed 2021-01-27 2021-03-03 2021-02-24 2021-04-17 .1.b Blood analyzer, automati Health Care Delivery Capacit tions nvelope c y MN-MOH-180301-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 65940 Post Open - National 0.00 2020-06-29 2020-08-01 2020-09-12 .1.b.8. COMPUTER, SERVER H Health Care Delivery Capacit tions nvelope mentation ARDWARE y MN-MOH-180302-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 46,620.21 Signed 2020-06-29 2020-07-18 2020-12-11 2020-08-29 .1.b.9. HOSPITAL KITCHEN EQ Health Care Delivery Capacit tions nvelope UIPMENT y MN-MOH-201974-GO-DIR / 2. Component 2: Strengthening IBRD / 90820 Post Direct Selection Direct 129,993.91 Signed 2020-12-09 2020-11-21 2020-12-14 2020-11-18 2021-01-02 2020-12-24 2021-02-01 1.b. WASHING, CLEANING EQ Health Care Delivery Capacit UIPMENT y MN-MOH-201878-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2021-01-27 2021-03-03 2021-04-02 .1.b. HOSPITAL ARCHIVING E Health Care Delivery Capacit tions nvelope QUIPMENT y MN-MOH-201977-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 24,811.09 Signed 2021-01-27 2021-03-03 2021-05-25 2021-04-17 .1.b. MEDICAL MEASURING E Health Care Delivery Capacit tions nvelope QUIPMENT y MN-MOH-180295-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b.5. STERILIZATION AND W IBRD / 90820 Health Care Delivery Capacit Post Open - National 133,098.96 Signed 2020-06-29 2020-07-18 2021-01-29 2020-08-29 tions nvelope ASHING EQUIPMENT y MN-MOH-180293-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 318,621.66 Signed 2020-11-06 2020-12-11 2021-01-29 2021-02-09 .1.b. LABORATORY EQUIPME Health Care Delivery Capacit tions nvelope NT y MN-MOH-180294-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2021-01-27 2021-02-15 2021-03-29 .1.b.3. REHABILITATION EQUI Health Care Delivery Capacit tions nvelope PMENT y MN-MOH-201970-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 42,764.63 Signed 2021-01-27 2021-03-03 2021-05-25 2021-05-02 .1.b. NEONATAL CARE EQUIP Health Care Delivery Capacit tions nvelope MENT y MN-MOH-201972-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. ELECTROSURGICAL UNI IBRD / 90820 Health Care Delivery Capacit Post Open - National 47,611.65 Signed 2021-01-27 2021-03-03 2021-05-25 2021-05-02 tions nvelope TS, AUTOMATIC SUCTION PU y MPS MN-MOH-201880-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. Electroencephalogram, IBRD / 90820 Health Care Delivery Capacit Post Open - National 34,109.04 Signed 2021-01-27 2021-03-03 2021-05-25 2021-04-02 tions nvelope holter monitor, spirometer y MN-MOH-201933-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.b. Neonatal phototherapy, IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2021-01-27 2021-03-03 2021-04-14 tions nvelope warmer, incubator, y MN-MOH-201877-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 229,267.77 Signed 2020-11-23 2020-12-28 2020-12-17 2021-02-11 .1.b. HOSPITAL OFFICE FURNI Health Care Delivery Capacit tions nvelope TURE y MN-MOH-201978-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IBRD / 90820 Post Open - National 0.00 2021-01-27 2021-03-03 2021-05-02 .1.a. Vaccine Syringe, safety Health Care Delivery Capacit tions nvelope ementation box y MN-MOH-216269-GO-UN / D ue to emergency case, vacci Component 2: Strengthening ne cold chain equipment will UN Agencies (Dire IBRD / 90820 Health Care Delivery Capacit Prior Direct 2,900,000.00 Signed 2021-01-27 2021-02-06 2021-02-01 2021-02-07 2021-03-08 2021-02-13 2021-09-04 supply directly from UNICEF s ct) y hopping list. Therefore, UNIC EF would be WB direct contra cter. MN-MOH-180320-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 221,181.57 Completed 2021-03-04 2021-03-23 2021-02-15 2021-05-04 2021-04-28 .1.d.2. EMERGENCY EQUIPME Health Care Delivery Capacit tions nvelope NT y MN-MOH-180322-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 110,559.24 Signed 2021-03-04 2021-03-23 2021-02-11 2021-05-04 .1.d.6. NEUROLOGICAL ICU E Health Care Delivery Capacit tions nvelope QUIPMENT y MN-MOH-180304-GO-RFQ / 2 Component 2: Strengthening .1.c.2. Aquapheresis apparat Request for Quota Single Stage - One E Under Imple IDA / 65940 Health Care Delivery Capacit Post Open - National 0.00 2021-03-17 2021-04-10 2021-05-22 us, CRRT, Hemodialisys wate tions nvelope mentation y r apparatus, Double water di stiller MN-MOH-180306-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.c.23. Surgical microscope, IDA / 65940 Health Care Delivery Capacit Post Open - National 227,704.03 Completed 2021-03-17 2021-04-05 2021-07-26 2021-05-17 2021-12-31 tions nvelope Viterctomy, phacomachine y MN-MOH-169369-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 414,940.00 Signed 2021-03-17 2021-04-26 2021-06-16 2021-07-25 .1.c.3 Endoscopic ultrasound Health Care Delivery Capacit tions nvelope set y MN-MOH-169102-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 0.00 Canceled 2021-03-17 2021-04-28 2021-07-27 .1.c.4. Laboratory equipment Health Care Delivery Capacit tions nvelope y MN-MOH-169367-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl .1.c.6 Nursing examination e IDA / 65940 Health Care Delivery Capacit Post Open - National 0.00 2021-03-23 2021-05-04 2021-08-02 tions nvelope ementation quipment y Page 4 MN-MOH-169372-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 0.00 Canceled 2021-03-23 2021-05-04 2021-08-02 .1.c.7. Bipap, CPAP, high flow Health Care Delivery Capacit tions nvelope y MN-MOH-221838-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 0.00 Canceled 2021-04-04 2021-06-07 2021-08-06 .1.c.9. Post operation care ap Health Care Delivery Capacit tions nvelope pliances y MN-MOH-221841-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.c.11. Endoscopy diagnosti IDA / 65940 Health Care Delivery Capacit Post Open - National 108,391.41 Signed 2021-03-29 2021-05-18 2021-06-16 2021-07-17 tions nvelope c set with accessories y MN-M0H-221844-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 65940 Post Open - National 0.00 2021-04-06 2021-06-13 2021-08-12 .1.c.12. Surgery equipment Health Care Delivery Capacit tions nvelope mentation y MN-MOH-221845-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 57,863.62 Signed 2021-04-02 2021-06-04 2021-04-16 2021-08-03 .1.c.13. Patient monitoring s Health Care Delivery Capacit tions nvelope ystem y MN-MOH-221847-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-04-06 2021-06-13 2021-06-19 .1.c.14. Ultrasound diagnosti Health Care Delivery Capacit tions nvelope ementation c unit y MN-M0H-221849-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-04-04 2021-06-13 2021-06-19 .1.c.15. Neuromonitoring equ Health Care Delivery Capacit tions nvelope ementation ipment y MN-MOH-221853-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 65940 Post Open - National 115,354.63 Signed 2021-03-28 2021-06-06 2021-07-23 2021-08-05 .1.c.17. ENT diagnostic unit Health Care Delivery Capacit tions nvelope y MN-MOH-221855-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-04-05 2021-06-14 2021-08-13 .1.c.18. Ankle arthroscopic su Health Care Delivery Capacit tions nvelope ementation rgery set y MN-MOOH-221858-GO-RFQ / Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl 2.1.c.19. Tissue cassette writ IDA / 65940 Health Care Delivery Capacit Post Open - National 0.00 2021-04-05 2021-06-14 2021-07-29 tions nvelope ementation er and Histology equipment y MN-MOH-221859-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-04-05 2021-06-14 2021-08-13 .1.c.20. Drug packing equipm Health Care Delivery Capacit tions nvelope ementation ent y MN-MOH-221860-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl .1.c.21. Medical equipment t IDA / 65940 Health Care Delivery Capacit Post Open - National 0.00 2021-04-13 2021-06-22 2021-08-21 tions nvelope ementation esting devices y MN-MOH-221861-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-04-21 2021-06-30 2021-12-27 .1.c.22. Ambulance car Health Care Delivery Capacit tions nvelope ementation y MN-MOH-180310-GO-DIR / B Component 2: Strengthening IDA / 65940 Post Direct Selection Direct 78,540.00 Signed 2020-06-29 2020-11-25 2020-07-06 2020-11-27 2020-07-25 2020-12-24 2020-09-19 FP contract... patient bed Health Care Delivery Capacit y MN-MOH-221850-GO-RFQ / 2 Component 2: Strengthening Single Stage - One E Under Imple IDA / 65940 Post Request for Bids Open - National 0.00 2021-03-31 2021-05-12 2021-04-05 2021-05-17 2021-06-16 2021-07-21 2021-09-19 .1.c.16. Surgery set Health Care Delivery Capacit nvelope mentation y MN-M0H-221840-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E .1.c.10. Endoscopy washer, s IDA / 65940 Health Care Delivery Capacit Post Open - National 24,603.92 Signed 2021-03-30 2021-06-01 2021-04-16 2021-07-31 tions nvelope terilization case y MN-MOH-181224-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-03-30 2021-06-01 2021-07-31 .1.c.8. Physio and therapy de Health Care Delivery Capacit tions nvelope ementation vices y MN-MOH-169371-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 135,230.63 Signed 2021-03-18 2021-04-22 2021-05-25 2021-07-21 2.1.1.1. Ventilator accessorie Health Care Delivery Capacit tions nvelope s y MN-MOH-188110-GO-RFB-2 / Component 2: Strengthening 2.1.1.2 General medical equi IBRD / 90820 Health Care Delivery Capacit Post Request for Bids 468,161.62 Signed 2021-03-11 2021-02-09 2021-03-18 2021-04-01 2021-03-12 2021-04-22 2021-05-03 2021-05-06 2021-05-25 2021-08-04 pment (re-announcement) y MN-MOH-169102-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 65940 Post Open - National 0.00 2021-05-08 2021-06-19 2021-09-17 2.1.c.4. Laboratory equipmen Health Care Delivery Capacit tions nvelope ementation t y MN-MOH-169372-GO-RFQ-2 / 2.1.c.7. Teaching hospital BiPap machine Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl Mini ventilator /CPAP/ IDA / 65940 Health Care Delivery Capacit Post Open - National 0.00 2021-05-24 2021-07-05 2021-10-03 tions nvelope ementation Mechanical Ventilator for MRI y system High flow nasal canula MN-MOH-235531-GO-DIR / R Component 2: Strengthening T-PCR and RNA Extraction Kit IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 0.00 Canceled 2021-05-21 2021-05-21 2021-05-28 2021-06-18 2021-08-17 For COVID -19 Control and Pr y evention MN-MOH-236935-GO-DIR / 2. Component 2: Strengthening 1.a.RT-PCR and Extraction kit IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 264,199.32 Completed 2021-05-28 2021-05-28 2021-05-31 2021-05-28 2021-06-15 2021-06-04 2021-07-15 2021-06-11 s for COVID-19 Control and P y revention MN-MOH-236938-GO-DIR / 2. Component 2: Strengthening 1.a. RT-PCR test kits for COVI IBRD / 90820 Health Care Delivery Capacit Post Direct Selection Direct 120,305.05 Signed 2021-05-28 2021-05-27 2021-05-31 2021-05-28 2021-06-15 2021-06-04 2021-07-20 D-19 Control and Prevention y MN-MOH-180427-GO-RFQ / 3 Component 3: Implementati Request for Quota Single Stage - One E .6. Furniture for PIU specialist IDA / 65940 on management and Monito Post Limited 0.00 Canceled 2020-08-30 2020-10-04 2020-11-03 tions nvelope s ring and Evaluation MN-MOH-247241-GO-RFQ / 1 Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl .2.1.B.5. COVID19 VACCINE E IDA / 68330 OVID-19 Prevention and Res Post Open - National 0.00 2021-08-31 2021-10-10 2022-01-31 tions nvelope ementation FFICIENCY STUDY EQUIPMEN ponse T AND SUPPLIES MN-MOH-180294-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 44,122.16 Signed 2021-08-18 2021-09-29 2021-09-26 2021-11-28 2.1.b.3.Rehabilitation equipm Health Care Delivery Capacit tions nvelope ent y MN-MOH-201878-GO-RFQ-2 / Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Canceled 2021-08-18 2021-09-29 2021-11-28 2.1.b.Hospital archiving equi Health Care Delivery Capacit tions nvelope pment y MN-MOH-253569-GO-RFQ / 2 Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 162,106.56 Signed 2021-09-27 2021-10-25 2021-11-06 2021-12-24 .2.3.2. PULSE OXIMETERS, FI Health Care Delivery Capacit tions nvelope NGER TIP y MN-MOH-262038-GO-DIR / 2. Component 2: Strengthening 2.2.1. COVID-19 VACCINES (2 IDA / 68330 Health Care Delivery Capacit Prior Direct Selection Direct 4,500,000.00 Completed 2021-11-08 2021-11-25 2021-11-15 2021-12-21 2021-12-14 2021-03-19 2022-01-13 2022-06-02 ND CONTRACT) y Page 5 MN-MOH-239597-GO-DIR / 2. Component 2: Strengthening IDA / 68330 Prior Direct Selection Direct 26,000,000.00 Completed 2021-06-15 2021-11-25 2021-06-22 2021-12-21 2021-09-15 2022-03-19 2021-10-15 2022-06-02 2.2.1. COVID-19 VACCINES Health Care Delivery Capacit y MN-MOH-331981-GO-DIR / C Component 2: Strengthening Direct - Internation Under Imple IDA / 68330 Prior Direct Selection 0.00 2022-12-18 2023-05-05 2022-12-19 2022-12-21 2022-12-22 OVID-19 VACCINES Health Care Delivery Capacit al mentation y MN-MOH-332103-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E ackage 1 - Continuous renal r IDA / 68330 Health Care Delivery Capacit Post Open - National 0.00 Signed 2022-12-20 2022-12-20 2023-02-24 2023-07-04 tions nvelope eplacement therapy y MN-MOH-332108-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E ackage 7 - Diagnostic and tr IDA / 68330 Health Care Delivery Capacit Post Open - National 0.00 Signed 2022-12-20 2022-12-19 2023-02-24 2023-07-04 tions nvelope eatment equipment y MN-MOH-332110-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IBRD / 90820 Post Open - National 0.00 2022-12-16 2023-01-19 2023-02-28 2023-07-08 ackage 8 - Rehabilitation equ Health Care Delivery Capacit tions nvelope ementation ipment y MN-MOH-332112-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Signed 2022-12-20 2022-12-20 2023-02-24 2023-07-04 ackage 9 - Surgery hand tool Health Care Delivery Capacit tions nvelope set y MN-MOH-332116-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Signed 2022-12-20 2023-02-24 2023-07-04 ackage 10 - Surgical equipm Health Care Delivery Capacit tions nvelope ent y MN-MOH-332117-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E ackage 11 - Biomedical equip IBRD / 90820 Health Care Delivery Capacit Post Open - National 0.00 Signed 2022-12-20 2022-12-20 2023-02-24 2023-07-04 tions nvelope ment inspection analyzator y MN-MOH-332121-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Signed 2022-12-20 2022-12-20 2023-02-24 2023-07-04 ackage 13 - Endoscope set Health Care Delivery Capacit tions nvelope y MN-MOH-332125-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E IBRD / 90820 Post Open - National 0.00 Signed 2022-12-20 2022-12-20 2023-02-24 2023-07-04 ackage 14 - Radiology equip Health Care Delivery Capacit tions nvelope ment y G01 / Package 9. Neonatal tr Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 eatment equipment Health Care Delivery Capacit tions nvelope y G02 / Package 23. Archiving Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 shelves Health Care Delivery Capacit tions nvelope y G03 / Package 6. Stretcher, Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 Therapeutic normothermic sy Health Care Delivery Capacit tions nvelope stem y G05 / Package 3 - Laborator Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 y equipment Health Care Delivery Capacit tions nvelope y G06 / Package 4 - Pathology Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 equipment Health Care Delivery Capacit tions nvelope y G07 / Package 15 - Anestesi Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 a surgical equipment Health Care Delivery Capacit tions nvelope y G08 / Package 16 - IT equip Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Signed 2023-01-31 2023-03-16 2023-08-03 ment Health Care Delivery Capacit tions nvelope y G09 / Autoclave for sterilizat Component 2: Strengthening Single Stage - One E IDA / 68330 Post Request for Bids Open - National 0.00 Signed 2023-01-18 2022-12-27 2023-01-18 2023-02-03 2023-02-03 2023-03-05 2023-04-03 2023-04-09 2023-08-17 ion of medical waste Health Care Delivery Capacit nvelope y MN-MOH-332105-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E ackage 5 - Automatic tablet / IDA / 68330 Health Care Delivery Capacit Post Open - National 0.00 Canceled 2022-12-20 2022-12-20 2023-02-24 2023-07-04 tions nvelope capsule machine y MN-MOH-332107-GO-RFQ / P Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Canceled 2022-12-20 2022-12-20 2023-02-24 2023-07-04 ackage 6 - Neurology equip Health Care Delivery Capacit tions nvelope ment y G04 / Package 2 - Intensive Component 2: Strengthening Request for Quota Single Stage - One E IDA / 68330 Post Open - National 0.00 Canceled 2023-01-31 2023-03-16 2023-08-03 care equipment Health Care Delivery Capacit tions nvelope y G10 / Supply and Delivery of Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 68330 Post Open - National 0.00 2023-04-20 2023-06-20 2024-01-26 ambulance cars Health Care Delivery Capacit tions nvelope mentation y G11 / Package 5 - Automatic Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 68330 Post Open - National 0.00 2023-04-20 2023-06-17 2023-10-15 tablet / capsule machine Health Care Delivery Capacit tions nvelope mentation y G12 / Package 6 - Neurolog Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 68330 Post Open - National 0.00 2023-04-20 2023-06-17 2023-09-20 y equipment Health Care Delivery Capacit tions nvelope mentation y G13 / Package 2 - Intensive Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 68330 Post Open - National 0.00 2023-04-20 2023-07-01 2023-07-12 care equipment Health Care Delivery Capacit tions nvelope mentation y NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MN-MOH-208524-NC-DIR / 2. Component 2: Strengthening Customs Clearance and Local IDA / 65940 Health Care Delivery Capacit Post Direct Selection Direct 82,089.59 Signed 2020-12-10 2020-11-18 2020-12-13 2020-12-18 2020-12-22 2020-12-25 2021-12-22 Freight Forwarding Services y CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Implementati MN-MOH-180428-CS-CQS / 3 Consultant Qualifi Pending Impleme IDA / 65940 on management and Monito Post Open - National 0.00 2020-09-28 2020-10-05 2020-10-19 2020-10-19 2020-11-02 2020-12-02 .7. Project baseline survey cation Selection ntation ring and Evaluation MN-MOH-181206-CS-CQS / 1 .1.3. Prepare and publish the Component 1: Emergency C Consultant Qualifi Information, Education, and IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-27 2020-10-04 2020-10-11 2020-10-23 2020-11-22 cation Selection Communication (IEC) materia ponse ls, TV promo, and info graphi c content Page 6 MN-MOH-181213-CS-CQS / 1 .1.8. Compose song and vide Component 1: Emergency C o movie against the COVID-1 Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-28 2020-10-05 2020-10-12 2020-10-26 2020-11-25 9 infection under the "Let us cation Selection ponse prevent infection together!" slogan and broadcast widely MN-MOH-181218-CS-CQS / 1 .1.16. Produce a video conte Component 1: Emergency C Consultant Qualifi nt to support social morale in IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-13 2020-09-20 2020-09-27 2020-10-09 2020-11-08 cation Selection cooperation with Mongolian S ponse tate Academic Drama Theate r MN-MOH-181210-CS-CQS / 1 Component 1: Emergency C .1.7. Prepare educational TV Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-10-04 2020-10-11 2020-10-18 2020-10-30 2020-11-29 programme with scientific an cation Selection ponse d cognitive content MN-MOH-181211-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.9. Produce a documentary IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-10-04 2020-10-11 2020-10-18 2020-10-30 2020-11-29 cation Selection film on COVID-19 infection ponse MN-MOH-181220-CS-CQS / 1 Component 1: Emergency C .2.3. Conduct the coronaviru Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-13 2020-09-20 2020-09-27 2020-10-09 2020-11-08 s infection survey (CIS) recor cation Selection ponse ds and incident monitoring re search MN-MOH-181222-CS-CQS / 1 Component 1: Emergency C .2.4. Develop mathematical Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-27 2020-10-04 2020-10-11 2020-10-23 2020-11-22 modelling of the coronavirus cation Selection ponse infection, influenza, and seas onal influenza MN-MOH-181204-CS-CQS / 1 Component 1: Emergency C .1.2. Develop and implement Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-07 2020-09-14 2020-09-21 2020-10-03 2020-11-02 the communications strategy cation Selection ponse during the coronavirus outbr eak MN-MOH-181215-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.11. Produce TV talk show s IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-27 2020-10-04 2020-10-11 2020-10-23 2020-11-22 cation Selection eries dedicated to youth ponse MN-MOH-181216-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.12. Obtain COVID-19 dedic IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-13 2020-09-20 2020-09-27 2020-10-09 2020-11-08 cation Selection ated air-time on TV channel ponse MN-MOH-181208-CS-CQS / 1 Component 1: Emergency C .1.5. Develop and distribute t Consultant Qualifi IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-28 2020-10-05 2020-10-12 2020-10-24 2020-11-23 he Information, Education, an cation Selection ponse d Communication (IEC) mate rials MN-MOH-181203-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.17. Produce song and vide IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-28 2020-10-05 2020-10-12 2020-10-24 2020-11-23 cation Selection o clip to promote work of doc ponse tors MN-MOH-181209-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.6. Disseminate information IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-28 2020-10-05 2020-10-12 2020-10-26 2020-11-25 cation Selection via public media outlets and ponse social media MN-MOH-181217-CS-CQS / 1 Component 1: Emergency C Consultant Qualifi .1.13. Place banner on the ho IDA / 65940 OVID-19 Prevention and Res Post Limited 0.00 Canceled 2020-09-07 2020-09-14 2020-09-21 2020-10-05 2020-11-04 cation Selection me page of the cable TVs ponse INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MN-MOH-168717-CS-INDV / Component 3: Implementati Individual Consult 3.1. Medical Equipment Speci IDA / 65940 on management and Monito Post Direct 22,294.66 Signed 2020-04-20 2020-05-19 2020-04-30 2020-06-03 2020-05-03 2020-08-05 2020-05-10 2020-08-06 2022-05-31 ant Selection alist/Engineer ring and Evaluation MN-MOH-168720-CS-INDV / Component 3: Implementati Individual Consult 3.2. Risk Communication and IDA / 65940 on management and Monito Post Direct 0.00 Canceled 2020-04-20 2020-05-19 2020-04-30 2020-06-03 2020-05-03 2020-05-10 2022-05-31 ant Selection Community Involvement Spe ring and Evaluation cialist Component 3: Implementati MN-MOH-168721-CS-INDV / Individual Consult IDA / 65940 on management and Monito Post Direct 0.00 Canceled 2020-04-20 2020-05-19 2020-04-30 2020-06-03 2020-05-03 2020-05-10 2022-05-31 3.3. Procurement Specialist ant Selection ring and Evaluation MN-MOH-168722-CS-INDV / Component 3: Implementati Individual Consult 3.4. Environmental and Occu IDA / 65940 on management and Monito Post Direct 0.00 Canceled 2020-04-20 2020-05-19 2020-04-30 2020-06-03 2020-05-03 2020-05-10 2022-05-31 ant Selection pational Health Specialist ring and Evaluation MN-MOH-185586-CS-INDV / Component 3: Implementati Individual Consult 3.2. Risk Communication and IDA / 65940 on management and Monito Post Open 0.00 Canceled 2020-08-06 2020-05-29 2020-09-03 2020-09-17 2020-10-01 2022-05-31 ant Selection Community Involvement Spe ring and Evaluation cialist Component 3: Implementati MN-MOH-185589-CS-INDV / Individual Consult IDA / 65940 on management and Monito Post Open 0.00 Canceled 2020-08-06 2020-05-23 2020-09-03 2020-09-17 2020-10-01 2022-05-31 3.3. Procurement Specialist ant Selection ring and Evaluation MN-MOH-185590-CS-INDV / Component 3: Implementati Individual Consult 3.4. Environmental and Occu IDA / 65940 on management and Monito Post Open 18,924.22 Signed 2020-08-06 2020-06-03 2020-09-03 2020-10-05 2020-09-17 2021-03-01 2020-10-01 2021-02-06 2022-05-31 ant Selection pational Health Specialist ring and Evaluation MN-MOH-185586-CS-INDV-2 Component 3: Implementati Individual Consult / 3.2. Risk Communication an IDA / 65940 on management and Monito Post Open 33,491.81 Completed 2020-10-16 2020-05-29 2020-11-13 2020-12-14 2020-11-20 2021-03-09 2020-12-01 2021-10-08 2022-10-31 2022-01-01 ant Selection d Community Involvement S ring and Evaluation pecialist Component 3: Implementati MN-MOH-185589-CS-INDV-2 Individual Consult IDA / 65940 on management and Monito Post 0.00 Canceled 2020-10-20 2020-05-26 2020-11-17 2020-11-24 2020-12-08 2022-10-31 / 3.3. Procurement specialist ant Selection ring and Evaluation Component 3: Implementati MN-MOH-218295-CS-CDS / 3 IDA / 65940 on management and Monito Prior Direct Selection Direct 0.00 Canceled 2021-02-10 2021-02-09 2021-02-20 2021-04-26 2021-10-23 .3. Procurement Specialist ring and Evaluation Component 3: Implementati MN-MOH-218862-CS-INDV / Individual Consult IDA / 65940 on management and Monito Prior Direct 14,642.68 Completed 2021-02-10 2021-02-10 2021-02-20 2021-02-11 2021-03-13 2021-03-30 2021-04-17 2021-08-25 2021-10-14 2022-01-01 3.3 Procurement specialist ant Selection ring and Evaluation Page 7 MN-MOH-232717-CS-INDV / Component 3: Implementati Individual Consult 3.6.Monitoring and Evaluatio IDA / 68330 on management and Monito Post Open 7,318.65 Completed 2021-05-17 2021-05-11 2021-06-19 2021-06-02 2021-06-26 2021-06-02 2021-07-17 2021-09-09 2023-03-31 2022-01-12 ant Selection n Specialist ring and Evaluation MN-MOH-232716-CS-INDV / Component 3: Implementati Individual Consult 3.5. Contract management s IDA / 68330 on management and Monito Post Open 7,824.72 Completed 2021-05-17 2021-05-11 2021-06-19 2021-06-07 2021-06-26 2021-05-28 2021-07-17 2021-06-08 2023-03-31 2021-12-01 ant Selection pecialist (local consultant) ring and Evaluation Component 3: Implementati MN-MOH-232722-CS-INDV / Individual Consult IDA / 68330 on management and Monito Post Open 0.00 Canceled 2021-05-17 2021-05-11 2021-06-19 2021-06-26 2021-07-17 2023-03-31 3.7. Vaccine Specialist ant Selection ring and Evaluation MN-MOH-180421-CS-CDS / 1 .3.13. Organize on-job traini Component 1: Emergency C ng among the traditional me IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 Canceled 2020-10-05 2020-10-12 2020-11-07 2020-12-05 dicine doctors, on epidemiolo ponse gy prevention and monitorin g measures MN-MOH-180424-CS-CDS / 1 .3.21. Organize clinical waste Component 1: Emergency C management specifically, bo IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 Canceled 2020-10-05 2020-10-12 2020-11-07 2020-12-05 dy transportation, storage, a ponse nd sanitation, and cremation training MN-MOH-180423-CS-CDS / 1 .3.15. Organize training on e Component 1: Emergency C arly detection of the complic IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 Canceled 2020-10-05 2020-10-12 2020-11-07 2020-12-05 ations of coronavirus infectio ponse n and mandatory treatment procedures for doctors of int ernal medicine MN-MOH-180422-CS-CDS / 1 .3.14. Strengthen laboratory operations and services capa Component 1: Emergency C bility by developing the bio- IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 Canceled 2020-10-05 2020-10-12 2020-11-07 2020-12-05 hazardous material and bio s ponse ubstances transportation reg ulation, on job training of CO VID-19 virus analysis, develo p manuals for specimen colle ction MN-MOH-247236-CS-CDS / 1 Component 1: Emergency C .1.1.A.1. COVID19 PREVENTI Under Implement IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 2021-08-13 2021-07-06 2021-08-27 2021-09-24 2022-12-17 ON AND TRANING ACTIVITIES ation ponse BY NATIONAL CENTER FOR P UBLIC HEALTH MN-MOH-247238-CS-CDS / 1 Component 1: Emergency C .2.2.A.3. COVID19 PREVENTI Under Implement IDA / 65940 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 2021-08-09 2021-05-31 2021-08-23 2021-09-13 2022-12-31 ON TRANING ACTIVITIES BY C ation ponse ENTER FOR HEALTH DEVELO PMENT MN-MOH-247239-CS-CDS / 1 Component 1: Emergency C .2.1.B.5. COVID19 VACCINE E Under Implement IDA / 68330 OVID-19 Prevention and Res Post Direct Selection Direct 0.00 2021-08-09 2021-07-24 2021-08-30 2021-10-04 2022-07-31 FFICIENCY STUDY BY MONGO ation ponse LIAN NATIONAL UNIVERSITY OF MEDICAL SCIENCES MN-MOH-232722-CS-INDV-2 Component 1: Emergency C Individual Consult / 1.1.1.B.15. PUBLIC HEALTH IDA / 68330 OVID-19 Prevention and Res Post Open 0.00 Canceled 2021-09-22 2021-09-21 2021-10-18 2021-10-23 2021-11-06 2022-11-06 ant Selection LOCAL CONSULTANT ponse MN-MOH-254589-CS-INDV / Component 1: Emergency C Individual Consult 1.3.3.A.3. FACILITY HEALTH A IDA / 65940 OVID-19 Prevention and Res Post Open 14,030.11 Signed 2021-09-22 2021-09-22 2021-10-25 2022-05-05 2021-10-30 2022-05-05 2021-11-13 2022-05-25 2022-11-13 ant Selection ND SAFETY LOCAL CONSULT ponse ANT MN-MOH-272427-CS-INDV / Component 1: Emergency C Individual Consult IDA / 65940 Post Direct 0.00 Canceled 2022-01-10 2022-02-11 2022-01-16 2022-01-19 2022-02-11 2022-08-10 1.1.1.B.15. Public health loca OVID-19 Prevention and Res ant Selection l consultant ponse Component 3: Implementati MN-MOH-272428-CS-INDV / Individual Consult IDA / 65940 on management and Monito Prior Open 0.00 Canceled 2022-01-17 2022-03-07 2022-03-28 2022-05-02 2022-10-29 procurement specialist ant Selection ring and Evaluation Component 3: Implementati MN-MOH-272668-CS-INDV / Individual Consult IDA / 65940 on management and Monito Prior Limited 0.00 Canceled 2022-01-17 2022-01-17 2022-01-22 2022-01-21 2022-02-12 2022-02-06 2022-03-19 2022-09-15 procurement specialist ant Selection ring and Evaluation MN-MOH-272670-CS-INDV / Component 3: Implementati Individual Consult Monitoring and Evaluation Sp IDA / 65940 on management and Monito Post Open 9,775.72 Terminated 2022-01-29 2022-01-04 2022-02-14 2022-01-21 2022-02-15 2022-03-18 2022-03-16 2022-03-28 2023-04-30 ant Selection ecialist ring and Evaluation Component 3: Implementati MN-MOH-272671-CS-INDV / Individual Consult IDA / 65940 on management and Monito Post Open 9,877.93 Terminated 2022-01-29 2022-01-04 2022-02-14 2022-01-21 2022-02-15 2022-01-01 2022-03-16 2022-04-30 2023-04-30 Project Assistant ant Selection ring and Evaluation MN-MOH-272672-CS-INDV / Component 3: Implementati Individual Consult Risk Communication and Co IDA / 65940 on management and Monito Post Open 10,248.84 Terminated 2022-01-29 2022-01-04 2022-02-14 2022-01-21 2022-02-15 2022-02-01 2022-03-16 2022-04-30 2023-04-30 ant Selection mmunity Engagement Specia ring and Evaluation list MN-MOH-272674-CS-INDV / Component 3: Implementati Individual Consult Financial Management Speci IDA / 65940 on management and Monito Prior Open 0.00 Canceled 2022-03-28 2022-04-06 2022-04-14 2022-04-15 2022-04-18 2022-10-15 ant Selection alist ring and Evaluation MN-MOH-292429-CS-INDV / Component 1: Emergency C Individual Consult Project Coordinator for Comp IDA / 68330 OVID-19 Prevention and Res Post Open 10,317.12 Terminated 2022-04-28 2022-04-28 2022-05-18 2022-06-08 2022-05-23 2022-06-08 2022-05-30 2022-06-22 2023-02-24 ant Selection onent 1 / National Training S ponse pecialist MN-MOH-292853-CS-INDV / Component 1: Emergency C Individual Consult IDA / 68330 Post Open 0.00 Canceled 2022-04-28 2022-05-05 2022-05-18 2022-06-27 2022-05-20 2022-05-24 2023-02-18 PUBLIC HEALTH LOCAL CONS OVID-19 Prevention and Res ant Selection ULTANT ponse MN-MOH-294627-CS-INDV / Component 3: Implementati Individual Consult Financial Management Speci IDA / 65940 on management and Monito Post Open 0.00 Signed 2022-05-11 2022-05-11 2022-06-03 2022-06-17 2022-06-06 2022-06-17 2022-06-10 2023-03-31 ant Selection alist ring and Evaluation Component 3: Implementati MN-MOH-272669-CS-INDV / Individual Consult IDA / 65940 on management and Monito Post Direct 0.00 Canceled 2022-01-29 2022-02-07 2022-02-13 2021-11-25 2022-02-14 2022-02-16 2023-04-30 Project Coordinator ant Selection ring and Evaluation MN-MOH-288910-CS-INDV / Component 2: Strengthening Individual Consult NATIONAL MEDICAL EQUIPME IDA / 65940 Health Care Delivery Capacit Post Open 0.00 Canceled 2022-04-15 2022-04-15 2022-05-03 2022-05-05 2022-05-07 2023-01-17 ant Selection NT SPECIALIST/ENGINEERING y CONSULTANT Component 3: Implementati MN-MOH-272673-CS-INDV / Individual Consult IDA / 65940 on management and Monito Post Open 0.00 Canceled 2022-03-22 2022-03-23 2022-04-09 2022-05-31 2022-04-10 2022-04-14 2022-10-11 Procurement Specialist ant Selection ring and Evaluation Page 8 MN-MOH-313589-CS-INDV / Component 1: Emergency C Individual Consult Project Coordinator for Comp IDA / 68330 OVID-19 Prevention and Res Post Open - National 11,467.88 Signed 2022-09-02 2022-09-01 2022-09-15 2022-09-01 2022-09-15 2022-09-02 2022-09-15 2022-09-06 2023-03-31 ant Selection onent 1 / National Training S ponse pecialist MN-MOH-288910-CS-INDV-2 Component 2: Strengthening Individual Consult / National Medical Equipment IDA / 68330 Health Care Delivery Capacit Post Open - National 10,820.64 Signed 2022-09-02 2022-09-01 2022-09-17 2022-09-02 2022-09-18 2022-09-02 2022-09-19 2022-09-15 2023-03-31 ant Selection Specialist / Engineering Cons y ultant MN-MOH-315239-CS-CDS / C REATING AN ENABLING ENVI Component 1: Emergency C RONMENT FOR ONE HEALTH Pending Impleme IDA / 68330 OVID-19 Prevention and Res Post Direct Selection Direct - National 0.00 2022-09-11 2022-09-13 2022-09-18 2023-08-14 CONCEPT IN MONGOLIA SING ntation ponse LE SOURCE CONTRACT WITH NATIONAL CENTER FOR ZOO NOTIC DISEASES Component 3: Implementati MN-MOH-317985-CS-INDV / Individual Consult Under Implement IDA / 68330 on management and Monito Post Open - National 0.00 2022-09-27 2022-10-10 2022-10-15 2022-10-17 2022-10-19 2023-03-31 Project Driver / Courier ant Selection ation ring and Evaluation MN-MOH-325523-CS-INDV / Component 1: Emergency C RISK COMMUNICATION AND Individual Consult Under Implement IBRD / 90820 OVID-19 Prevention and Res Post Open - National 0.00 2022-11-08 2022-12-26 2022-11-28 2022-11-30 2022-12-04 2023-12-31 COMMUNITY ENGAGEMENT S ant Selection ation ponse PECIALIST OF THE PROJECT I MPLEMENTATION UNIT MN-MOH-332130-CS-INDV / Component 3: Implementati Individual Consult Under Implement NATIONAL MONITORING AND IBRD / 90820 on management and Monito Post Open - National 0.00 2022-12-20 2022-12-20 2023-01-23 2023-01-26 2023-01-26 2023-09-10 ant Selection ation EVALUATION CONSULTANT ring and Evaluation MN-MOH-333001-CS-INDV / Component 3: Implementati Individual Consult PIU Monitoring and Evaluatio IBRD / 90820 on management and Monito Post Open - National 0.00 Canceled 2022-12-21 2023-01-20 2023-01-25 2023-01-27 2023-12-31 ant Selection n Specsialist ring and Evaluation CS02 / CREATING AN ENABLI Component 1: Emergency C NG ENVIRONMENT FOR ONE IDA / 68330 OVID-19 Prevention and Res Post Direct Selection Direct - National 0.00 Under Review 2023-05-31 2023-05-24 2023-06-02 2023-06-06 2023-12-31 HEALTH CONCEPT IN MONGO ponse LIA CS03 / IMPROVING HEALTHC Component 1: Emergency C Under Implement IDA / 68330 Post Direct Selection Direct - National 0.00 2023-05-31 2023-05-24 2023-06-04 2023-06-13 2024-02-08 ARE WASTE MANAGEMENT OVID-19 Prevention and Res ation ponse Page 9 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Desert Locust Response Project, P173702 Project Implementation agency: Ministry of Agriculture, Ethiopia Date of the Procurement Plan: April 6, 2012 Period covered by this Procurement Plan: April 2020 to March 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. cable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Since the project is an emergency response project the provisions of Procurement in Situations of Urgent Need of Assistance shall apply. PROCUREMENT Eastern and Southern Africa : Emergency Locust Response Program PLAN General Information Country: Eastern and Southern Africa 2022-10-20 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173702 GPN Date: 2020-12-03 Project Name: Emergency Locust Response Program Loan / Credit No: IDA / 66480 Isiolo County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-ISIOLO COUNTY-320739- Request for Quota CW-RFQ / Rehabilitation of La Livelihoods Protection and R Request for Quota Single Stage - One E Pending Imp 2023-02-1 IDA / 66480 Post Limited tions (Non Bank-S 82,680.00 0.00 2022-10-21 2022-11-18 ffe Borehole at Sericho Ward. ehabilitation tions nvelope lementation 6 PD) GPS coordinates: N0489997, E0155618 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-ISIOLO COUNTY-325132- GO-RFQ / Procurement of em ergency livestock supplemen Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl tary feeds in Sericho Ward, I IDA / 66480 Post Limited 87,053.90 0.00 2022-11-21 2022-12-16 2023-03-16 ehabilitation tions nvelope ementation siolo County. Coordinates: Latitude 1.12942 N 1*7'45.92 4 longitude 39.11108 E 38*6'3 KE-ISIOLO COUNTY-03/2022/ 9.894 2023-GO-RFQ / Procurement of Assorted certified Livelihoods Protection and R Pending Impl IDA / 66480 Post Direct Selection Direct - National 36,710.72 0.00 2023-05-18 2023-05-23 2023-06-13 2023-09-11 Seeds for farmers - County w ehabilitation ementation ide- Garbatulla, Merti and Isiolo s ub Counties. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-ISIOLO COUNTY-325126- GO-RFQ / Water trucking serv Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66480 Post Limited 81,766.14 0.00 2022-11-21 2022-12-23 2023-03-23 ices to alleviate human and li ehabilitation tions nvelope ementation vestock suffering as a result of drought. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Cher Marc, Nous avons examiné le projet de plan de passation des marchés pour le projet susmentionné, soumis à la Banque le 2019/09/01. Sur la base des informations fournies, la Banque n'a pas d'objection à ce que les activités marquées «cleared» dans le plan de passation des marchés (PPM). Après la publication du PPM, vous pouvez commencer la mise en œuvre de ces activités. Les PPMs traités par le système seront automatiquement publiés sur le site Web externe de la Banque mondiale dès réception de la déclaration de non-objection de la Banque et seront archivés sous le numéro de version indiqué ci-dessus. Bien cordialement + merci pour vos efforts, Jan Friedrich Kappen Spécialiste Principal en Energie PROCUREMENT Madagascar : Madagascar - Least-Cost Electricity Access Development Project - LEAD PLAN General Information Country: Madagascar 2019-11-07 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163870 GPN Date: Project Name: Madagascar - Least-Cost Electricity Access Development Project - LEAD Loan / Credit No: IDA / 63730 JIRAMA LEAD Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-JIRAMA LEAD-241233-G O-RFB / V0121C Densification des réseaux de distribution - Open - Internationa Single Stage - One E IDA / 63730 Grid Electrification Post Request for Bids 1,000,000.00 0.00 Signed 2021-06-28 2021-07-27 2021-07-03 2021-09-09 2021-08-14 2021-09-10 2021-09-13 2022-01-27 2021-10-18 2022-02-15 Fourniture des équipements l nvelope pour l’installation de 5000 br anchements sociaux (sans le s compteurs) MG-JIRAMA LEAD-241294-G O-RFB / V0321C Densification Open - Internationa Single Stage - One E et extension des réseaux de IDA / 63730 Grid Electrification Post Request for Bids 800,000.00 0.00 Canceled 2021-06-28 2021-08-19 2021-07-03 2021-08-19 2021-08-14 2021-10-04 2021-09-13 2022-02-08 2021-10-18 2022-02-15 l nvelope distribution : Fourniture maté riel de sécurité, appareil de mesure et outillage MG-JIRAMA LEAD-241299-G Single Stage - One E O-RFB / V0421C Fourniture d IDA / 63730 Grid Electrification Post Request for Bids Open - National 200,000.00 259,803.16 Signed 2021-06-28 2021-08-19 2021-07-03 2021-08-19 2021-08-14 2021-09-20 2021-09-13 2022-01-28 2021-10-18 2022-03-22 2022-02-15 nvelope e matériels informatiques MG-JIRAMA LEAD-244494-G O-RFQ / I0121A - Fournitures Technical Assistance and Pro Request for Quota Single Stage - One E IDA / 63730 Post Open - National 20,000.00 0.00 Signed 2021-07-24 2021-08-20 2021-09-18 2022-03-17 d'équipements informatiques ject Implementation Support tions nvelope pour l'unité de gestion du pro jet MG-JIRAMA LEAD-170532-G O-DIR / I0120C - Achat de 07 Technical Assistance and Pro licences du logiciel Power Fa IDA / 63730 Post Direct Selection Direct 20,000.00 0.00 Canceled 2020-06-02 2020-09-01 2020-06-07 2019-09-23 2020-07-12 2021-01-08 ject Implementation Support ctory avec contrat de mainte nance inclu pour une durée d e 03 ans MG-JIRAMA LEAD-244507-G O-RFB / A0121C - Fourniture de matériels roulants réparti e en 5 lots: Lot n°1: 20 Véhicules pick up Technical Assistance and Pro Open - Internationa Single Stage - One E IDA / 63730 Prior Request for Bids 2,800,000.00 0.00 Canceled 2021-09-14 2021-09-19 2021-10-31 2021-11-21 2021-12-26 2022-06-24 4x4 double cabine; ject Implementation Support l nvelope Lot n°2: 40 Camionnettes H D65 4X2 (plateau ridelle); Lot n°3: 5 Camions grues; Lot n°4: 2 Camions Plateaux ; Lot n°5: 7 Camions Nacelles, MG-JIRAMA LEAD-241292-G O-RFB / D0322C - Fourniture Open - Internationa Single Stage - One E IDA / 63730 Grid Electrification Post Request for Bids 1,840,000.00 1,556,789.98 Signed 2022-03-14 2022-03-24 2022-03-15 2022-04-05 2022-04-29 2022-05-16 2022-05-11 2022-05-16 2022-06-10 2022-08-05 2023-01-06 des kits de matériels pour 20 l nvelope 000 branchements sociaux MG-JIRAMA LEAD-283165-G O-RFB / D0222C - Fourniture Open - Internationa Single Stage - One E de 195 000 compteurs prép IDA / 63730 Grid Electrification Prior Request for Bids 6,640,000.00 0.00 Signed 2022-03-16 2022-06-21 2022-03-17 2022-07-18 2022-05-02 2022-09-01 2022-05-14 2023-01-12 2022-06-13 2022-12-10 l nvelope aiement et équipements de t est du laboratoire (en 2 lots) MG-JIRAMA LEAD-283176-G O-RFB / A0121C - Fourniture des moyens roulants en 4 lot Open - Internationa Single Stage - One E IDA / 63730 Grid Electrification Prior Request for Bids 2,500,000.00 0.00 Signed 2022-03-17 2022-06-24 2022-03-18 2022-07-18 2022-05-02 2022-08-23 2022-05-14 2023-01-12 2022-06-17 2023-06-02 2022-12-14 2023-06-02 s : 13 Véhicules 4x4 cabines, l nvelope 50 Camionnettes, 6 camions grues et 5 Camions plateaux MG-JIRAMA LEAD-283181-G Open - Internationa Single Stage - One E O-RFB / D0822C - Fourniture IDA / 63730 Grid Electrification Post Request for Bids 1,650,000.00 0.00 Signed 2022-03-18 2022-03-31 2022-03-19 2022-04-06 2022-05-03 2022-05-23 2022-05-11 2022-07-07 2022-06-13 2023-02-08 l nvelope des matériels de réseau élect rique MG-JIRAMA LEAD-241307-G O-RFB / D0122C (EPC) - Four Open - Internationa Single Stage - One E niture et installation en 6 Lot IDA / 63730 Grid Electrification Prior Request for Bids 20,060,000.00 0.00 Signed 2021-07-26 2022-07-06 2021-07-31 2023-01-10 2021-09-11 2022-10-27 2021-10-11 2023-02-21 2021-11-15 2023-06-01 2022-05-14 l nvelope s des kits de matériels pour 170 000 branchements socia ux en deux tranches MG-JIRAMA LEAD-283321-G O-RFB / D0722C (EPC) - Four niture et installation en 6 Lot Open - Internationa Single Stage - One E IDA / 63730 Grid Electrification Prior Request for Bids 23,200,000.00 0.00 Signed 2022-03-24 2022-07-06 2022-03-25 2022-07-24 2022-05-09 2022-10-28 2022-05-24 2023-04-02 2022-06-28 2023-06-23 2023-02-23 s des matériels de réseaux é l nvelope lectriques, poteaux et access oires pour 400 activités d'ext ension MG-JIRAMA LEAD-287326-G Under Imple O-DIR / D1322C FOURNITURE IDA / 63730 Grid Electrification Post Direct Selection Direct 700,000.00 0.00 2022-04-01 2022-06-03 2022-04-16 2022-06-05 2022-10-03 mentation DE 5000 COMPTEURS COMM UNICANTS MG-JIRAMA LEAD-283291-G Single Stage - One E Under Imple O-RFB / D0522C - Fourniture IDA / 63730 Grid Electrification Post Request for Bids Open - National 180,000.00 0.00 2022-03-23 2022-04-26 2022-03-24 2022-05-06 2022-03-28 2022-06-10 2022-04-09 2022-05-14 2022-11-10 nvelope mentation des matériaux de constructio n en 8 Lots MG-JIRAMA LEAD-283289-G Single Stage - One E O-RFB / D0422C - Fourniture IDA / 63730 Grid Electrification Post Request for Bids Open - National 630,000.00 0.00 Canceled 2022-03-21 2022-04-21 2022-03-22 2022-04-27 2022-05-06 2022-06-14 2022-05-18 2022-06-21 2022-12-18 nvelope de 5094 poteaux béton en u n seul Lot Page 1 MG-JIRAMA LEAD-305932-G O-RFB / D0522C - Fourniture Single Stage - One E Under Imple IDA / 63730 Grid Electrification Post Request for Bids Open - National 180,000.00 0.00 2022-08-09 2022-08-25 2022-08-14 2022-09-02 2022-09-28 2022-10-14 2022-10-10 2022-11-01 2023-04-30 des matériaux de constructio nvelope mentation n en 8 Lots (Relance) MG-JIRAMA LEAD-305937-G Request for Quota Single Stage - One E Pending Impl O-RFQ / P0122C - Services de IDA / 63730 Grid Electrification Post Open - National 1,000.00 0.00 2022-08-14 2022-10-09 2023-04-07 tions nvelope ementation 20 impressions de plans au f ormat A0 MG-JIRAMA LEAD-319194-G Single Stage - One E Under Imple O-RFB / D0422C - Fourniture IDA / 63730 Grid Electrification Post Request for Bids Open - National 1,900,000.00 0.00 2022-04-15 2022-04-26 2022-04-20 2022-10-16 2022-06-01 2022-06-14 2022-07-01 2022-10-17 2022-08-05 2023-02-01 nvelope mentation de 5094 poteaux béton en u n seul Lot MG-JIRAMA LEAD-340594-G O-RFB / D0922C Fourniture d Open - Internationa Single Stage - One E Pending Impl e 5000 Compteurs intelligent IDA / 63730 Grid Electrification Post Request for Bids 1,950,000.00 0.00 2023-04-03 2023-04-12 2023-05-27 2023-06-26 2023-07-31 2024-01-27 l nvelope ementation s et Acquisition et Mise en Se rvice d'une plateforme pour t ous Compteurs Intelligents MG-JIRAMA LEAD-350802-G O-RFB / D0123C Fourniture, I nstallation et mise en service Open - Internationa Single Stage - One E Pending Impl IDA / 63730 Grid Electrification Post Request for Bids 1,950,000.00 0.00 2023-06-21 2023-06-26 2023-08-07 2023-08-28 2023-10-02 2024-04-19 de raccordement électrique d l nvelope ementation es CSB et Centres Hospitalier s à partir des réseaux de la JI RAMA MG-JIRAMA LEAD-365709-G O-RFB / A0123C Acquisition d Single Stage - One E Pending Impl IDA / 63730 Grid Electrification Post Request for Bids Open - National 300,000.00 0.00 2023-06-14 2023-06-19 2023-07-31 2023-08-30 2023-10-04 2024-01-02 es moyens roulants : 2 voitur nvelope ementation es 4 x 4 et 50 motos MG-JIRAMA LEAD-365773-G O-RFB / V0123C Acquisition d Single Stage - One E Pending Impl IDA / 63730 Grid Electrification Post Request for Bids Open - National 150,000.00 0.00 2023-06-21 2023-06-26 2023-07-26 2023-08-10 2023-09-09 2023-11-08 es équipements informatique nvelope ementation s ordinateurs et imprimantes MG-JIRAMA LEAD-366144-G O-RFQ / V0223C ACQUISITIO Request for Quota Single Stage - One E Pending Impl IDA / 63730 Grid Electrification Post Open - National 50,000.00 0.00 2023-06-24 2023-09-10 2023-11-09 N DES MATERIELS DE BUREA tions nvelope ementation UX POUR LE SERVICE BU MG-JIRAMA LEAD-365712-G Single Stage - One E Pending Impl O-RFB / D0223C Acquisition d IDA / 63730 Grid Electrification Post Request for Bids Open - National 300,000.00 0.00 2023-06-14 2023-06-19 2023-07-31 2023-08-30 2023-10-04 2024-01-02 nvelope ementation es équipements de sécurité e t outillages NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-JIRAMA LEAD-283295-NC Request for Quota Single Stage - One E -RFQ / D0622C - Recrutemen IDA / 63730 Grid Electrification Post Open - National 70,000.00 0.00 Canceled 2022-03-15 2022-04-19 2022-05-09 2023-01-04 tions nvelope t de main d’œuvre temporair e en 8 Lots MG-JIRAMA LEAD-305925-NC -RFQ / D0622C - Recrutemen Request for Quota Single Stage - One E Under Imple IDA / 63730 Grid Electrification Post Open - National 120,000.00 0.00 2022-07-30 2022-09-02 2022-09-14 2023-05-12 t de main d’œuvre temporair tions nvelope mentation e en 8 Lots (Relance) MG-JIRAMA LEAD-318061-NC -DIR / SERVICE DE MIGRATIO Technical Assistance and Pro Direct - Internation Under Imple IDA / 63730 Post Direct Selection 10,000.00 0.00 2022-09-26 2022-09-28 2022-10-01 2022-09-28 2022-10-08 2022-10-22 N DE LA PLATEFORME ZTE A ject Implementation Support al mentation LA NOUVELLE ARCHITECTUR E SIG/SIG JIRAMA MG-JIRAMA LEAD-356618-NC -RFQ / X0423C Location d'un Pending Impl IDA / 63730 Grid Electrification Post Direct Selection Direct - National 75,000.00 0.00 2023-06-14 2023-06-19 2023-07-01 2024-07-31 bureau et équipement de bur ementation eau pour le PIÙ PAGOSE et L EAD JIRAMA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-JIRAMA LEAD-140248-CS -INDV / ASSISTANCE A LA MA Technical Assistance and Pro Quality And Cost- Open - Internationa IDA / 63730 Prior 4,000,000.00 4,794,525.54 Signed 2019-10-14 2019-11-11 2019-10-15 2019-12-04 2019-10-31 2020-06-03 2019-12-16 2020-08-14 2019-12-24 2020-10-01 2020-01-08 2021-02-14 2020-01-28 2021-03-16 2022-01-27 ITRISE D'OUVRAGE (Etude, C ject Implementation Support Based Selection l ontrôle et Supervision) (X011 9C) MG-JIRAMA LEAD-208711-CS -QCBS / ÉTUDES ENVIRONNE Technical Assistance and Pro Quality And Cost- Open - Internationa MENTALES ET SOCIALES REQ IDA / 63730 Post 220,000.00 224,274.66 Signed 2020-12-17 2020-12-16 2020-12-24 2021-05-21 2021-01-28 2021-06-22 2021-02-25 2021-07-22 2021-03-11 2021-08-09 2021-03-25 2021-08-26 2021-04-22 2021-10-14 2021-10-19 ject Implementation Support Based Selection l UISES POUR LES ACTIVITÉS D E LA SOUS- COMPOSANTE 1b DU PROJET MG-JIRAMA LEAD-232195-CS Consultant Qualifi -CQS / Service d'un Consulta IDA / 63730 Grid Electrification Post Limited 100,000.00 436,000.00 Signed 2021-04-29 2021-05-19 2021-05-13 2021-06-24 2021-06-12 2022-02-03 2021-07-17 2022-02-23 2021-12-24 cation Selection nt pour Compteur en cascad e V0121C MG-JIRAMA LEAD-298026-CS -CQS / X0122C - OPTIMA BUS INESS & BRANCHEMENTS MO Technical Assistance and Pro Consultant Qualifi Under Implement IDA / 63730 Post Limited 239,000.00 0.00 2022-06-09 2022-08-25 2022-06-16 2022-07-16 2022-08-13 2023-01-21 RA : Recrutement d’une Age ject Implementation Support cation Selection ation nce de communication pour l a mise en œuvre du Plan de Communication MG-JIRAMA LEAD-350822-CS Technical Assistance and Pro Consultant Qualifi Open - Internationa Pending Impleme -CQS / X0123C Service de Co IDA / 63730 Post 100,000.00 0.00 2023-03-24 2023-04-14 2023-05-13 2023-05-28 2023-06-21 2023-08-20 ject Implementation Support cation Selection l ntation nsultants pour l'Audit de MAT SELAKA (JdE) MG-JIRAMA LEAD-366138-CS -CQS / X0523C CABINET DE P ROFESSIONNEL DES COMPTA BLES CHARGE D'ASSURER LA Consultant Qualifi Pending Impleme IDA / 63730 Grid Electrification Post Open - National 350,000.00 0.00 2023-06-21 2023-07-12 2023-08-02 2023-08-09 2023-08-23 2024-09-19 GESTION FINANCIERE cation Selection ntation POUR LES PROJETS PAGOSE ET LEAD JUSQU'A LA CLOTUR E DES PROJETS Page 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-JIRAMA LEAD-182997-CS -CDS / SERVICE DE CONSULT ANT INDIVIDUEL POUR ASSIS Technical Assistance and Pro Individual Consult IDA / 63730 Post Limited 15,000.00 0.00 Canceled 2020-08-07 2020-08-12 2020-09-02 2020-10-07 2021-04-05 TER LA DIRECTION GÉNÉRAL ject Implementation Support ant Selection E DE LA JIRAMA POUR LES FO NCTIONS AU POSTE DU CONT RÔLEUR DE GESTION 1 MG-JIRAMA LEAD-182998-CS -CDS / SERVICE DE CONSULT ANT INDIVIDUEL POUR ASSIS Technical Assistance and Pro Individual Consult IDA / 63730 Post Limited 15,000.00 0.00 Canceled 2020-08-07 2020-08-12 2020-09-02 2020-10-07 2021-04-05 TER LA DIRECTION GÉNÉRAL ject Implementation Support ant Selection E DE LA JIRAMA POUR LES FO NCTIONS AU POSTE DU CONT RÔLEUR DE GESTION 2 MG-JIRAMA LEAD-246789-CS -INDV / X0321C - Recruteme Technical Assistance and Pro Individual Consult nt d'un Spécialiste en Gestio IDA / 63730 Post Open 17,500.00 16,677.23 Signed 2021-09-24 2021-10-18 2021-10-28 2022-01-28 2021-11-04 2022-05-17 2021-11-26 2022-05-31 2022-11-26 ject Implementation Support ant Selection n Financière pour appuyer l'é quipe de l'AGEX de la JIRAMA MG-JIRAMA LEAD-258678-CS -INDV / X0521C - Recruteme Technical Assistance and Pro Individual Consult Under Implement nt d'un Responsable de la Pa IDA / 63730 Prior Direct 17,000.00 0.00 2021-10-19 2021-10-21 2021-10-25 2021-11-17 2022-05-16 ject Implementation Support ant Selection ation ssation des Marchés pour le projet LEAD et PAGOSE MG-JIRAMA LEAD-295777-CS -INDV / Consultant individuel Technical Assistance and Pro Individual Consult Under Implement IDA / 63730 Post Direct 12,000.00 0.00 2022-05-23 2022-03-26 2022-06-02 2022-06-23 2022-07-28 2023-07-28 Comptable de Projets PAGOS ject Implementation Support ant Selection ation E et LEAD au sein de l'AGEX de la JIRAMA MG-JIRAMA LEAD-276238-CS -INDV / Coordonnateur de Pro Technical Assistance and Pro Individual Consult IDA / 63730 Post Direct 30,200.00 0.00 Canceled 2022-02-09 2022-02-11 2022-02-13 2022-02-20 2023-02-20 jets PAGOSE et LEAD au sein ject Implementation Support ant Selection de l'AGEX de la JIRAMA MG-JIRAMA LEAD-307906-CS -INDV / X0322C - Service de Technical Assistance and Pro Individual Consult Under Implement IDA / 63730 Post Direct - National 12,750.00 0.00 2022-08-09 2022-08-09 2022-08-19 2022-09-09 2022-10-14 2023-04-12 Consultant Individuel pour la ject Implementation Support ant Selection ation Coordination des Projets PAG OSE et LEAD MG-JIRAMA LEAD-304435-CS Technical Assistance and Pro Individual Consult Under Implement -INDV / X0422C - Recruteme IDA / 63730 Post Open - National 8,000.00 0.00 2022-08-09 2022-08-18 2022-09-27 2022-10-18 2022-11-22 2024-06-28 ject Implementation Support ant Selection ation nt d'un assistant en passatio n de marché MG-JIRAMA LEAD-304440-CS -INDV / X0522C - Recruteme Technical Assistance and Pro Individual Consult Under Implement IDA / 63730 Post Open - National 17,000.00 0.00 2022-08-09 2022-08-25 2022-09-27 2022-10-18 2022-11-22 2024-06-28 nt d'un consultant Responsa ject Implementation Support ant Selection ation ble de Passation de Marchés MG-JIRAMA LEAD-340591-CS -INDV / X0622C Service de C Technical Assistance and Pro Individual Consult Pending Impleme IDA / 63730 Post Direct - National 40,000.00 0.00 2023-02-10 2023-02-14 2023-02-17 2023-02-28 2024-07-01 onsultant individuel Coordon ject Implementation Support ant Selection ntation nateur de Projets PAGOSE et LEAD MG-JIRAMA LEAD-350775-CS -CDS / X0323C Service de Co Technical Assistance and Pro Pending Impleme nsultant individuel pour Com IDA / 63730 Post Direct Selection Direct - National 17,000.00 0.00 2023-03-20 2023-03-21 2023-03-22 2024-06-30 ject Implementation Support ntation ptable des projets PAGOSE et LEAD au sein de l'AGEX JIRA MA de ces projets MG-JIRAMA LEAD-367136-CS -INDV / X0623C SERVICE DE Individual Consult IDA / 63730 Grid Electrification Prior Open - National 15,000.00 0.00 Under Review 2023-06-30 2023-08-12 2023-08-19 2023-09-09 2024-07-31 CONSULTANT INDIVIDUEL D' ant Selection ASSISTANT EN PASSATION D E MARCHE Page 3 SUMMARY O F PROCUREMENT PLAN Project Preparation Advancement (PPA) Project information: Harmonizing and Improving Statistics in West Africa Project -P169265 Project Implementation agency: Liberia Institute of Statistics and Geo- Information Services (LISGIS) Date of the Procurement Plan: February 3, 2020 Period covered by this Procurement Plan: 3rd February to 31st July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 1, 2016), revised in November 2017, and August 2018 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Concessions Act, 2010 of the Republic of Liberia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a). Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Thresholds*, Procurement Arrangements, and Prior Review (The table below depicts the Thresholds and Procurement Methods to be used under the Regional Project for Statistics Thresholds*, Procurement Methods, and Prior Review Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] All contracts at or above USD Open Competition 5,000,000 are subject to International Market 1 Works C ≥ 5,000,000 Approach and Direct international advertising and the use of the Bank’s SPDs (or other Contracting documents agreed with the Contract (C) Value Expenditure Procurement Contracts Subject to No Threshold* [eq. Category Method Prior Review /[eq. US$] USD] Bank). Open Competition National Market 200,000 < C < 5,000,000 None Approach C ≤ 200,000 RfQ None All contracts at or above USD Open Competition 500,000 are subject to International Market international advertising and the C ≥ 500,000 Approach and Direct use of the Bank’s SPDs (or other Goods, IT and Contracting documents agreed with the 2 non-consulting Bank). services Open Competition 100,000 < C < 500,000 National Market None Approach C ≤ 100,000 RfQ None All contracts at or above USD 100,000 are subject to for international advertising and the C < 100,000 Consulting Services use of the Bank’s SPDs (or other National documents agreed with the shortlist for Bank). 3 selection of All contracts at or above USD consultant firms for 200,000 are subject to Engineering and international advertising and the C ≤ 200,000 Construction use of the Bank’s SPDs (or other Supervision documents agreed with the Bank). Selection of All values ≥ 100,000 4 Individual All Approaches consultants Training, This line activity is not subject to Workshops, Based on approved Procurement Review However, 5 Study Tours All Values Annual Work Plan & each of the activities will be Budgets (AWPB) by TTL cleared with the TTL prior to its implementation. (Special procurement arrangements like direct contracting, use of SOEs, UN Agencies, third party monitors, local NGOs, Force Account, servants needs, results based arrangements. It is not expected that there will be need for prequalification in the procurement arrangements under this Regional Project *These thresholds are for the purposes of the initial procurement plan for the PPA and for first 18 months. The thresholds will be revised periodically based on re- assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the packages of works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The LISGIS Project Management Team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: b) PROCUREMENT PLAN Works There are no works under the Project Preparation Advance Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequ Nation Revie Expecte Expecte Comment No. (Description) Cost Method alifica al w d bid d s US$ tion Prefer by opening Contrac (yes/n ence Bank date t o) (yes/n (Prior Signatu o) / Post) re Date 1 Procurement of 4 12,100 laptops, 3 No. all- in-1 printers, Limited, RFQ No No Post 28 Feb 4 Mar office desks, a 20 20 projector, metal filing cabinet, and stationery and supplies for project management Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Description of Estimate Selection Review Expecte Expected Expected Comments No. Assignment d Method/ by Bank d date Contract Completi Cost in Arrangem (Prior / of Signatur on US$ ent Post) proposal e Date submissi Date on 1. Recruitment of a Consultant to draft and validate 10,000 INDV Post 16 Mar 10 Apr 23 Apr ToR to be curricula of the 20 20 20 submitted to IDA Statistics degree & for Review and No CEST Program at Objection. the UL 2. Recruitment of a ToR, performance Financial evaluation, draft Management contract and Officer for Project DS Prior 10 Feb 21 Feb 31 Aug minutes of Management 20 20 20 contract negotiation to be submitted to IDA for Review and No 15,600 Objection. 3. ToR, performance evaluation, draft Recruitment of a contract and Procurement DS Prior 10 Feb 21 Feb 31 Aug minutes of Specialist for 20 20 20 contract Project 18,000 negotiation to be Management submitted to IDA for Review and No Objection. Training and Workshop (Training & Workshop activities are subject to TTL clearance). Estimat Estimated Expected Ref. Training, workshop and ed Cost Duration Training/workshop No. study tours in (Days) Date (US$) Conduct of validation 54,000 workshop and TOT for the GP Feb. 20 to March 1. on the design of 13 2020 questionnaires and enumeration training manual Workshop for cartographic 150,000 Feb. 24 to March 2. field staff training 16 2020 Workshop for enumeration 113,900 3. mapping training April 15, 2020 Study Tours to regional 32,000 countries for first-hand experience on regional March to April 4. harmonization of data 2020 collection, management and communication Workshops on current 50,000 administrative data across 5. April to July 2020 MACs and LISGIS regional offices Workshop to strengthen and 35,000 6. develop institutional capacity April to July 2020 of NSO Workshops for steering 40,000 7. committee on Administrative April to July 2020 Data Workshop for Project 10,000 Steering/Technical 8. Committees for annual work February 2020 plan preparation, review and validation GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan by the TTL. The beneficiaries, after the training, will be requested to submit a brief report indicating what skills have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operational Costs: These are expenditures incurred by the Recipient to finance: (i) communication technology (including, without limitation, internet and telephone; (ii) per diem and travel expenses of the operational staff performing their responsibilities under the Project; (iii) fuel and vehicle maintenance; (iv) maintenance of equipment; (v) photocopies and publications; (viii) bank commissions; and (ix) utilities and office supplies as defined in the FA. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Western and Central Africa : Harmonizing and Improving Statistics in West Africa PLAN General Information Country: Western and Central Africa 2021-02-15 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169265 GPN Date: 2021-05-19 Project Name: Harmonizing and Improving Statistics in West Africa Loan / Credit No: IDA / 65750, IDA / 65770 National Institute of Statistics - Cote d'Ivoire Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Regional component: Harmo CI-INS COTE D'IVOIRE-21420 nization, Data Collection, Qu 7-CW-RFB / Câblage réseau ( Single Stage - One E 2021-11-1 IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 268,000.00 0.00 Canceled 2021-01-25 2021-01-30 2021-03-13 2021-04-12 2021-05-17 câblage informatique, couran nvelope 3 ation and Use of Core Social t ondulé et revêtement mur) and Economic Statistics CI-INS COTE D'IVOIRE-21419 Regional component: Harmo National Procure 9-CW-RFQ / Travaux et amén nization, Data Collection, Qu ment Document - agement (Acquisition et insta Request for Quota Single Stage - One E 2022-12-0 IDA / 65750 ality Improvement, Dissemin Post Limited 1 Envelope proce 110,000.00 0.00 Canceled 2022-04-11 2022-06-06 llation de Split, Revêtement tions nvelope 3 ation and Use of Core Social ss (Non Bank-SPD murs, cloisonnement, extensi and Economic Statistics ) on du câblage électrique et r éseau, travaux divers...) CI-INS COTE D'IVOIRE-27353 Country-Specific Component Request for Quota 9-CW-RFQ / Travaux de réha : Improving and modernizing Request for Quota Single Stage - One E Under Imple 2022-10-2 IDA / 65770 Post Limited tions (Non Bank-S 100,000.00 0.00 2022-07-05 2022-08-30 bilitation et d'aménagement physical and statistical infra tions nvelope mentation 9 PD) du bâtiment siège de l'UCP structure CI-INS COTE D'IVOIRE-27354 Country-Specific Component Request for Quota 0-CW-RFQ / Travaux de réha : Improving and modernizing Request for Quota Single Stage - One E Pending Imp 2022-10-1 IDA / 65770 Post Limited tions (Non Bank-S 100,000.00 0.00 2022-08-09 2022-10-04 bilitation et d'aménagement physical and statistical infra tions nvelope lementation 0 PD) du bâtiment pour le Centre d structure e cartographie CI-INS COTE D'IVOIRE-30845 Country-Specific Component Request for Quota 1-CW-RFQ / Travaux de clois : Improving and modernizing Request for Quota Single Stage - One E tions - Small Work Pending Imp 2022-12-2 IDA / 65770 Post Limited 180,000.00 0.00 2022-09-19 2022-11-14 onnement et d'aménagemen physical and statistical infra tions nvelope s (Emergency) SP lementation 9 t des nouveaux bureaux de l' structure D -Competitive INS CI-INS COTE D'IVOIRE-30845 3-CW-RFQ / Travaux de fourn Country-Specific Component Request for Quota iture et installation de bâtim : Improving and modernizing Request for Quota Single Stage - One E tions - Small Work Pending Imp 2022-11-2 ent préfabriqués pour le site IDA / 65770 Post Limited 180,000.00 0.00 2022-09-17 2022-10-07 physical and statistical infra tions nvelope s (Emergency) SP lementation 1 de relocalisation de l'INS (infi structure D -Competitive rmerie, local imprimerie et lo cal de maintenance informati que etc.) CI-INS COTE D'IVOIRE-30845 Request for Quota 6-CW-RFQ / Travaux d'install Project Management and Mo Request for Quota Single Stage - One E Pending Imp 2022-12-2 IDA / 65770 Post Limited tions (Non Bank-S 110,000.00 0.00 2022-09-18 2022-11-13 ation de bureau en préfabriq nitoring and Evaluation tions nvelope lementation 8 PD) ués dans les locaux de l'UCP- PHAS CI-INS COTE D'IVOIRE-35012 Country-Specific Component 1-CW-RFQ / Travaux de mise Request for Quota : Improving and modernizing Request for Quota Single Stage - One E Pending Imp 2023-12-3 en place de bâtiments préfab IDA / 65770 Post Limited tions (Non Bank-S 190,000.00 0.00 2023-05-09 2023-07-04 physical and statistical infra tions nvelope lementation 1 riqués et aménagement du c PD) structure entre d’appel de l’INS CI-INS COTE D'IVOIRE-35198 Regional component: Harmo Request for Quota 6-CW-RFQ / Travaux d'aména nization, Data Collection, Qu Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-12-1 gement des bureaux du Rece IDA / 65770 ality Improvement, Dissemin Post Limited 150,000.00 0.00 2023-04-25 2023-06-20 tions nvelope s (Emergency) SP lementation 7 nsement Général des Entrepr ation and Use of Core Social D -Competitive ises et Etablissements de Côt and Economic Statistics e d'Ivoire (RGEE-CI) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-INS COTE D'IVOIRE-27353 5-GO-RFQ / Fourniture et inst Project Management and Mo Request for Quota Single Stage - One E Under Imple allation d'équipements infor IDA / 65770 Post Limited 90,000.00 0.00 2022-02-07 2022-06-10 2022-04-04 2022-10-01 nitoring and Evaluation tions nvelope mentation matiques (Ordinateurs, serve urs, imprimantes etc.) pour l' UCP-PHAS CI-INS COTE D'IVOIRE-27353 Country-Specific Component 6-GO-RFQ / Fourniture et inst : Improving and modernizing Request for Quota Single Stage - One E Pending Impl allation de matériels de bure IDA / 65770 Post Limited 90,000.00 0.00 2022-03-01 2022-04-26 2022-10-23 physical and statistical infra tions nvelope ementation au (Copieurs, vidéos projecte structure urs etc.) pour l'UCP et le cent re de cartographie CI-INS COTE D'IVOIRE-27354 Country-Specific Component 4-GO-RFQ / Fourniture et inst : Improving and modernizing Request for Quota Single Stage - One E Pending Impl allation d'un système de visi IDA / 65770 Post Limited 30,000.00 0.00 2022-03-28 2022-05-23 2022-11-19 physical and statistical infra tions nvelope ementation oconférence pour l'UCP-PHAS structure et le centre de cartographie CI-INS COTE D'IVOIRE-27354 5-GO-RFQ / Fourniture et inst Project Management and Mo Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 30,000.00 0.00 2022-04-18 2022-06-13 2022-12-10 allation de GPS pour les véhi nitoring and Evaluation tions nvelope ementation cules acquis dans le cadre du Projet PHAS CI-INS COTE D'IVOIRE-21423 Regional component: Harmo 2-GO-RFQ / Acquisition d’ouv nization, Data Collection, Qu Request for Quota Single Stage - One E Under Imple rages pour renouveler le fon IDA / 65750 ality Improvement, Dissemin Post Limited 12,000.00 0.00 2022-04-06 2022-06-01 2022-11-28 tions nvelope mentation ds documentaire de la bibliot ation and Use of Core Social hèque de l’ENSEA and Economic Statistics CI-INS COTE D'IVOIRE-27353 3-GO-RFQ / Acquisition de Fo Project Management and Mo Request for Quota Single Stage - One E Pending Impl urnitures de bureau (rame, ki IDA / 65770 Post Limited 60,000.00 0.00 2022-04-05 2022-05-31 2023-05-31 nitoring and Evaluation tions nvelope ementation ts, stylo…) pour l'UCP et dive rs ateliers et enquêtes Page 1 CI-INS COTE D'IVOIRE-27352 Country-Specific Component 1-GO-RFQ / Fourniture et inst : Improving and modernizing Request for Quota Single Stage - One E Pending Impl allation de matériels informat IDA / 65770 Post Limited 75,000.00 0.00 2022-04-17 2022-06-12 2022-07-27 physical and statistical infra tions nvelope ementation iques pour le fonctionnement structure du centre de cartographie CI-INS COTE D'IVOIRE-27352 Country-Specific Component Request for Quota Single Stage - One E Pending Impl 2-GO-RFQ / Fourniture et inst IDA / 65770 : Improving and modernizing Post Limited 70,000.00 0.00 2022-03-29 2022-05-24 2022-06-23 tions nvelope ementation allation de mobiliers de bure physical and statistical infra au pour l'UCP structure CI-INS COTE D'IVOIRE-21421 Regional component: Harmo 1-GO-RFB / Acquisition de LO nization, Data Collection, Qu Single Stage - One E GICIELS (VISUAL BASIC 2019 IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 783,484.00 0.00 Canceled 2021-02-25 2021-03-02 2021-04-13 2021-05-13 2021-06-17 2021-12-14 nvelope Entreprise, MS SQLSERVER 2 ation and Use of Core Social 019, STATA 16/PM 32, IBM SP and Economic Statistics SS 26 et anti virus) Regional component: Harmo CI-INS COTE D'IVOIRE-21423 nization, Data Collection, Qu 0-GO-RFQ / Acquisition de Ph Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 49,000.00 0.00 Canceled 2021-01-27 2021-03-24 2021-09-20 otocopieurs de grande capaci tions nvelope ation and Use of Core Social té and Economic Statistics CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 7-GO-RFB / Acquisition d’équi nization, Data Collection, Qu Single Stage - One E pements (serveurs physiques IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 221,930.00 0.00 Canceled 2021-02-22 2021-02-27 2021-04-10 2021-05-10 2021-06-14 2021-12-11 nvelope , disques de sauvegardes, ap ation and Use of Core Social plications, etc.) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21421 nization, Data Collection, Qu 3-GO-RFB / Acquisition de mo Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 279,800.00 0.00 Canceled 2021-02-18 2021-02-23 2021-04-06 2021-05-06 2021-06-10 2021-12-07 biliers de bureau pour l'Unité nvelope ation and Use of Core Social de Coordination du Projet and Economic Statistics CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 2-GO-RFB / Acquisition de Fo nization, Data Collection, Qu Single Stage - One E urnitures de bureau (rame, ki IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 139,326.00 0.00 Canceled 2021-02-26 2021-03-03 2021-04-14 2021-05-14 2021-06-18 2021-12-15 nvelope ts, stylo…), pour le fonctionn ation and Use of Core Social ement de l'UCP et la collecte and Economic Statistics des données Regional component: Harmo CI-INS COTE D'IVOIRE-21422 nization, Data Collection, Qu 4-GO-RFB / Acquisition de co Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 189,502.00 0.00 Canceled 2021-02-24 2021-03-01 2021-04-12 2021-05-12 2021-06-16 2021-12-13 nsommables informatiques ( nvelope ation and Use of Core Social encre, cartouches, etc…) and Economic Statistics CI-INS COTE D'IVOIRE-27351 Project Management and Mo Request for Quota Single Stage - One E Under Imple 8-GO-RFQ / Acquisition de tro IDA / 65770 Post Limited 190,000.00 0.00 2022-05-31 2022-09-06 2022-07-15 2022-08-14 nitoring and Evaluation tions nvelope mentation is (03) Véhicules pour les bes oins de l'UCP CI-INS COTE D'IVOIRE-27352 9-GO-RFB / Fourniture et inst allation de Matériels Informat Country-Specific Component iques, logiciels, consommabl : Improving and modernizing Single Stage - One E Under Imple IDA / 65770 Post Request for Bids Open - National 500,000.00 0.00 2022-05-25 2023-04-28 2022-05-30 2023-05-05 2022-07-11 2022-08-10 2022-09-14 2023-09-14 es et matériels de bureau po physical and statistical infra nvelope mentation ur la réalisation des enquête structure s (Indice d'Accessibilité, refo nte du site web, enquête prix , ENSEA, enquête marge de t ransport) CI-INS COTE D'IVOIRE-27352 5-GO-DIR / Acquisition de Car burant pour la mise en œuvr Project Management and Mo Request for Quota Single Stage - One E IDA / 65770 Post Limited 90,000.00 0.00 Canceled 2022-04-11 2022-06-06 2022-12-03 e des activités du projet (car nitoring and Evaluation tions nvelope burant pour les véhicules de l 'UCP, pour les enquêtes enqu êtes et ateliers) CI-INS COTE D'IVOIRE-29236 Country-Specific Component 4-GO-DIR / Acquisition de car : Improving and modernizing Pending Impl burant pour les véhicules de l IDA / 65770 Post Direct Selection Direct 120,000.00 0.00 2022-05-18 2022-05-23 2022-06-27 2023-06-27 physical and statistical infra ementation 'UCP et pour les ateliers et e structure nquêtes dans le cadre de la mise en œuvre du Projet CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 9-GO-RFB / Acquisition d'ond nization, Data Collection, Qu Single Stage - One E uleurs pour les Directions rég IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 148,400.00 0.00 Canceled 2021-02-26 2021-03-03 2021-04-14 2021-05-14 2021-06-18 2021-12-15 nvelope ionales et le centre de cartog ation and Use of Core Social raphie (20 onduleurs de 6 KV and Economic Statistics A et 1 onduleur de 30 KVA) CI-INS COTE D'IVOIRE-21423 3-GO-RFB / Acquisition de ser Regional component: Harmo veurs de calcul statistique, li nization, Data Collection, Qu Single Stage - One E cences, logiciels service clou IDA / 65750 ality Improvement, Dissemin Post Request for Bids Open - National 255,000.00 0.00 Canceled 2021-03-10 2021-03-15 2021-04-26 2021-05-26 2021-06-30 2021-12-27 nvelope d et équipements informatiq ation and Use of Core Social ues pour améliorer les capaci and Economic Statistics tés de calcul des étudiants et des chercheurs pour l'ENSEA CI-INS COTE D'IVOIRE-24506 Regional component: Harmo 5-GO-RFQ / ACHAT DE FOUR nization, Data Collection, Qu NITURES DE BUREAUX (Kits d Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 157.00 0.00 Canceled 2021-08-01 2021-09-26 2022-03-25 e formation (cahier 200 page tions nvelope ation and Use of Core Social s, stylo, crayon, gomme, che and Economic Statistics mise cartonnée) et Carton de rames)/EHCVM-NSU Regional component: Harmo CI-INS COTE D'IVOIRE-24508 nization, Data Collection, Qu 5-GO-RFQ / Achat de carbura Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 3,500.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 nt (Coordonnateur, Equipe te tions nvelope ation and Use of Core Social chnique) /EHCVM-NSU and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21423 nization, Data Collection, Qu 1-GO-RFQ / Acquisition de sc Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 40,000.00 0.00 Canceled 2022-03-28 2022-05-23 2022-11-19 anner professionnel A0 pour l tions nvelope ation and Use of Core Social e Centre de cartographie and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-24507 nization, Data Collection, Qu 3-GO-RFQ / Achat de cartouc Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 160.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 he d'encre pour imprimante / tions nvelope ation and Use of Core Social EHCVM NSU and Economic Statistics CI-INS COTE D'IVOIRE-27353 Country-Specific Component 2-GO-RFB / Acquisition de 30 : Improving and modernizing Open - Internationa Single Stage - One E véhicules pour la réalisation IDA / 65770 Post Request for Bids 1,800,000.00 0.00 Signed 2022-06-30 2022-07-07 2022-07-05 2022-11-19 2022-08-16 2022-08-23 2022-09-15 2022-09-06 2022-10-20 2023-04-18 physical and statistical infra l nvelope des enquêtes et recensemen structure ts dans le cadre du Projet Page 2 CI-INS COTE D'IVOIRE-21422 Regional component: Harmo 5-GO-RFQ / Achat de produits nization, Data Collection, Qu Request for Quota Single Stage - One E pharmaceutiques (kits pour l IDA / 65750 ality Improvement, Dissemin Post Limited 11,658.00 0.00 Canceled 2022-04-11 2022-06-06 2022-12-03 tions nvelope es agents de collecte sur le t ation and Use of Core Social errain) and Economic Statistics CI-INS COTE D'IVOIRE-27353 1-GO-RFQ / Fourniture et inst Project Management and Mo Request for Quota Single Stage - One E Pending Impl allation d'un système de vidé IDA / 65770 Post Limited 20,000.00 0.00 2022-07-04 2022-08-29 2022-11-27 nitoring and Evaluation tions nvelope ementation osurveillance et de sécurité p our les locaux de l'UCP-PHAS CI-INS COTE D'IVOIRE-24507 Regional component: Harmo 8-GO-RFQ / Achat de KITS sa nization, Data Collection, Qu nitaires (paquet de gants, Ge Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 675.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 l hydroalcoolique flacon (30 tions nvelope ation and Use of Core Social ml + 450ml + 30ml), Paquet and Economic Statistics de 50 Cache-nez )/EHCVM-NS U CI-INS COTE D'IVOIRE-24507 5-GO-RFQ / Acquisition de m Regional component: Harmo atériels de terrain ( Pèse alim nization, Data Collection, Qu ent, Peson électronique (affic Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 5,470.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 hage numérique), Toile de co tions nvelope ation and Use of Core Social uleur blanche (4 mètres), Pile and Economic Statistics s pour pèse aliment, Imperm éables, Imperméables, Sac à dos, chargeur portable)/EHC VM-NSU Regional component: Harmo CI-INS COTE D'IVOIRE-24508 nization, Data Collection, Qu 9-GO-RFQ / Achat de produits Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 540.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 pharmaceutiques dans le cad tions nvelope ation and Use of Core Social re des EHCVM-NSU and Economic Statistics CI-INS COTE D'IVOIRE-27352 Country-Specific Component 3-GO-RFQ / Fourniture et inst : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 75,000.00 0.00 2022-07-05 2022-08-30 2022-09-29 allation de mobiliers de bure physical and statistical infra tions nvelope ementation au pour le centre de cartogra structure phie CI-INS COTE D'IVOIRE-27353 Country-Specific Component 7-GO-RFQ / Acquisition de co : Improving and modernizing Request for Quota Single Stage - One E Under Imple nsommables informatiques ( IDA / 65770 Post Limited 60,000.00 0.00 2022-08-01 2022-08-05 2022-09-26 2023-03-25 physical and statistical infra tions nvelope mentation encre, toners etc.) pour le fo structure nctionnement de l'UCP et le c entre de cartographie CI-INS COTE D'IVOIRE-27352 7-GO-RFQ / Acquisition d'équi Country-Specific Component pements techniques, de com : Improving and modernizing Request for Quota Single Stage - One E Pending Impl munication et petit électrom IDA / 65770 Post Limited 50,000.00 0.00 2022-07-04 2022-08-29 2022-10-08 physical and statistical infra tions nvelope ementation énager (coffres-forts, télévise structure urs, téléphones portables, réf rigérateurs, machines à café, relieuses) pour l'UCP CI-INS COTE D'IVOIRE-29806 0-GO-DIR / Acquisition d'un lo Project Management and Mo Pending Impl IDA / 65770 Post Direct Selection Direct 30,000.00 0.00 2022-07-15 2022-07-20 2022-08-24 2023-02-20 giciel de gestion comptable e nitoring and Evaluation ementation t financière (TOMPRO) pour l' UCP-PHAS CI-INS COTE D'IVOIRE-30846 2-GO-RFQ / Fourniture et inst Country-Specific Component allation d'enseigne lumineus : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 30,000.00 0.00 2022-09-18 2022-11-13 2022-12-13 e, panneau directionnels et s physical and statistical infra tions nvelope ementation ystème de signalétique pour structure les bâtiments et bureaux du Projet CI-INS COTE D'IVOIRE-30846 6-GO-RFQ / Fourniture d'impr Country-Specific Component imés et gadgets promotionne : Improving and modernizing Request for Quota Single Stage - One E Pending Impl ls pour l'unité de coordinatio IDA / 65770 Post Limited 50,000.00 0.00 2022-09-17 2022-11-12 2022-11-22 physical and statistical infra tions nvelope ementation n du projet et la mise en œuv structure re des activités du projet (blo c-notes, tee-shirt, kakémono s, agenda etc.) CI-INS COTE D'IVOIRE-30846 Country-Specific Component 8-GO-RFQ / Acquisition de cin : Improving and modernizing Request for Quota Single Stage - One E Pending Impl quante-six (56) ordinateurs p IDA / 65770 Post Limited 90,000.00 0.00 2022-09-11 2022-11-06 2022-12-21 physical and statistical infra tions nvelope ementation ortables pour les 56 jeunes p structure rofessionnels recrutés dans l e cadre du PHAS CI-INS COTE D'IVOIRE-30847 0-GO-RFQ / Acquisition de m Country-Specific Component atériels informatiques compl : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 90,000.00 0.00 2022-09-13 2022-11-08 2022-12-23 émentaires pour le centre d'i physical and statistical infra tions nvelope ementation nnovation cartographique, ce structure ntre ce calcul et le centre d'a nalyse économique CI-INS COTE D'IVOIRE-32347 Country-Specific Component 7-GO-DIR / Acquisition d'un lo : Improving and modernizing Pending Impl IDA / 65770 Post Direct Selection Direct - National 40,000.00 0.00 2023-01-31 2023-02-05 2023-03-12 2023-09-08 giciel de type ARCGIS pour l'I physical and statistical infra ementation nstitut National de la Statisti structure que CI-INS COTE D'IVOIRE-32347 Country-Specific Component 9-GO-RFB / Fourniture et Mis : Improving and modernizing Single Stage - One E Under Imple IDA / 65770 Post Request for Bids Open - National 200,000.00 0.00 2023-01-31 2023-01-11 2023-02-05 2023-02-10 2023-03-19 2023-02-23 2023-04-18 2023-03-24 2023-05-23 2023-11-19 e en service d'un centre d'ap physical and statistical infra nvelope mentation pel pour l'Institut National de structure s Statistiques CI-INS COTE D'IVOIRE-33226 Country-Specific Component 2-GO-RFQ / Fourniture de logi : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 60,000.00 0.00 2023-03-05 2023-04-30 2023-10-27 ciel prioritaire (STATA, SPSS, physical and statistical infra tions nvelope ementation EVIEWS, …) pour l'INS et le structure Centre de Cartographie CI-INS COTE D'IVOIRE-33254 3-GO-RFQ / Acquisition de m Country-Specific Component obiliers de bureau pour l'opér : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 80,000.00 0.00 2023-09-05 2023-10-31 2024-04-28 ationnalisation du Conseil Na physical and statistical infra tions nvelope ementation tional de la Statistique (CNSt structure at) et l'Autorité Nationale de l a Statistique Publique (ANSP) CI-INS COTE D'IVOIRE-33255 Country-Specific Component 0-GO-RFQ / Acquisition de se : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 47,000.00 0.00 2023-02-06 2023-04-03 2023-09-30 pt (07) drones + Batterie de physical and statistical infra tions nvelope ementation rechange pour le centre de c structure artographie Page 3 CI-INS COTE D'IVOIRE-33255 Country-Specific Component 1-GO-RFQ / Fourniture de ma : Improving and modernizing Request for Quota Single Stage - One E Pending Impl tériels et mise en place de sa IDA / 65770 Post Limited 90,000.00 0.00 2023-05-01 2023-06-26 2023-12-23 physical and statistical infra tions nvelope ementation lles multimédia dans les dire structure ctions régionales de l'INS CI-INS COTE D'IVOIRE-33255 Country-Specific Component 3-GO-RFB / Acquisition de 67 : Improving and modernizing Single Stage - One E Pending Impl 0 engins à deux roues et cas IDA / 65770 Post Request for Bids Open - National 504,000.00 0.00 2023-03-29 2023-04-03 2023-05-15 2023-06-14 2023-07-19 2024-01-15 physical and statistical infra nvelope ementation ques en appui aux activités d structure e recensement agricole CI-INS COTE D'IVOIRE-33255 Country-Specific Component 7-GO-RFQ / Travaux d'aména : Improving and modernizing Request for Quota Single Stage - One E Pending Impl gement intérieur des locaux IDA / 65770 Post Limited 190,000.00 0.00 2023-01-29 2023-03-26 2023-09-22 physical and statistical infra tions nvelope ementation de l'UC-PHAS (aménagement structure salles de réunion, bureaux, s alles de conférence) etc. CI-INS COTE D'IVOIRE-33257 Country-Specific Component 5-GO-RFQ / Acquisition de Mo : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 90,000.00 0.00 2023-03-05 2023-04-30 2023-10-27 biliers de Bureau complémen physical and statistical infra tions nvelope ementation taires pour l'UC-PHAS structure CI-INS COTE D'IVOIRE-33252 Country-Specific Component Request for Quota Single Stage - One E Pending Impl 4-GO-RFQ / Acquisition de de IDA / 65770 : Improving and modernizing Post Limited 200,000.00 0.00 2023-05-22 2023-07-17 2024-01-13 tions nvelope ementation ux (02) cars pour l'INS physical and statistical infra structure CI-INS COTE D'IVOIRE-35003 Country-Specific Component 3-GO-RFQ / Acquisition de m : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 90,000.00 0.00 2023-05-03 2023-06-28 2023-12-25 obiliers de bureau (tables, fa physical and statistical infra tions nvelope ementation uteuils etc.) pour le centre d’ structure appels de l’INS CI-INS COTE D'IVOIRE-35014 Country-Specific Component 3-GO-RFQ / Acquisition de Ma : Improving and modernizing Request for Quota Single Stage - One E Pending Impl tériels Informatiques en souti IDA / 65770 Post Limited 90,000.00 0.00 2023-04-11 2023-06-06 2023-12-03 physical and statistical infra tions nvelope ementation en aux activités de l’Institut structure National de la Statistique (IN S) CI-INS COTE D'IVOIRE-35014 Country-Specific Component 6-GO-RFQ / Achats de matéri : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 200,000.00 0.00 2023-05-09 2023-07-04 2023-12-31 els roulants (120) Motos et c physical and statistical infra tions nvelope ementation asques pour le corps des age structure nts enquêteurs CI-INS COTE D'IVOIRE-35014 7-GO-RFQ / Acquisition d'équi Country-Specific Component pements techniques (Tables l : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 75,000.00 0.00 2023-05-03 2023-06-28 2023-12-25 umineuses, loupes etc.) pour physical and statistical infra tions nvelope ementation la cartothèque physique de l’ structure Institut National de la Statisti que (INS) CI-INS COTE D'IVOIRE-35014 Country-Specific Component 8-GO-RFQ / Acquisition de dix : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 480,000.00 0.00 2023-04-30 2023-06-25 2023-12-22 (10) véhicules pour la mise e physical and statistical infra tions nvelope ementation n œuvre du recensement agr structure icole CI-INS COTE D'IVOIRE-35014 Country-Specific Component 9-GO-RFQ / Acquisition de m : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 90,000.00 0.00 2023-06-05 2023-07-31 2024-01-27 atériels informatiques pour le physical and statistical infra tions nvelope ementation recensement agricole structure CI-INS COTE D'IVOIRE-35015 Country-Specific Component 2-GO-RFQ / Acquisition de m : Improving and modernizing Request for Quota Single Stage - One E Pending Impl obiliers de bureau pour les n IDA / 65770 Post Limited 90,000.00 0.00 2023-05-03 2023-06-28 2023-12-25 physical and statistical infra tions nvelope ementation ouveaux bureaux de l’Institut structure National de la Statistique (IN S) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-INS COTE D'IVOIRE-27350 Country-Specific Component 7-NC-RFQ / Recrutement d'un : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 50,000.00 0.00 2022-02-05 2022-04-02 2023-04-02 Prestaire pour le gardiennag physical and statistical infra tions nvelope ementation e des locaux du Projet et du structure centre de cartographie CI-INS COTE D'IVOIRE-27351 1-NC-RFQ / Recrutement d'un Country-Specific Component Prestataire pour la fourniture : Improving and modernizing Request for Quota Single Stage - One E Pending Impl de police d'assurances malad IDA / 65770 Post Limited 80,000.00 0.00 2022-03-13 2022-05-08 2023-05-08 physical and statistical infra tions nvelope ementation ie, individuelle accident tous structure risques véhicules et Multirisq ue professionnelle pour les v éhicules et les bâtiments du projet CI-INS COTE D'IVOIRE-21456 Regional component: Harmo 3-NC-RFQ / Recrutement d'un nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl prestataire pour l'entretien d IDA / 65750 ality Improvement, Dissemin Post Limited 40,000.00 0.00 2022-04-03 2022-05-29 2022-11-25 tions nvelope ementation es locaux de l'UCP PHAS et d ation and Use of Core Social u centre de cartographie and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21451 nization, Data Collection, Qu 0-NC-RFQ / Confection Kaké Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 20,088.00 0.00 Canceled 2021-03-20 2021-05-15 2021-11-11 mono, Location diverses, Ser tions nvelope ation and Use of Core Social vice divers and Economic Statistics CI-INS COTE D'IVOIRE-24527 Regional component: Harmo 2-NC-RFQ / ONNEXION INTER nization, Data Collection, Qu Request for Quota Single Stage - One E NET (formation agents, sortie IDA / 65750 ality Improvement, Dissemin Post Limited 888.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 tions nvelope terrain, coordonnateur, super ation and Use of Core Social viseur, Headquater et collect and Economic Statistics e)/EHCVM-NSU CI-INS COTE D'IVOIRE-24527 Regional component: Harmo 3-NC-RFQ / REPRODUCTION nization, Data Collection, Qu Request for Quota Single Stage - One E DES OUTILS DE FORMATION ( IDA / 65750 ality Improvement, Dissemin Post Limited 891.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 tions nvelope questionnaire, manuel, librair ation and Use of Core Social ie photo, etc.) et Badges /EH and Economic Statistics CVM NSU Page 4 CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 5-NC-RFQ / Reprographie des nization, Data Collection, Qu Request for Quota Single Stage - One E documents des projets (RECE IDA / 65750 ality Improvement, Dissemin Post Limited 52,000.00 0.00 Canceled 2022-04-25 2022-06-20 2022-12-17 tions nvelope NSEMENT, REPERTOIRE, EAI, ation and Use of Core Social IHPC, IPS) and Economic Statistics CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 8-NC-RFQ / Reprographie des nization, Data Collection, Qu Request for Quota Single Stage - One E documents des projets (ANN IDA / 65750 ality Improvement, Dissemin Post Limited 12,460.00 0.00 Canceled 2022-04-05 2022-05-31 2022-11-27 tions nvelope UAIRE, REEA, ENQUETE PRO ation and Use of Core Social DUCTION ET PRIX) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21446 nization, Data Collection, Qu Request for Quota Single Stage - One E 8-NC-RFQ / Réparation de vé IDA / 65750 ality Improvement, Dissemin Post Limited 99,920.00 0.00 Canceled 2021-04-04 2021-05-30 2021-11-26 tions nvelope hicules ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-24526 nization, Data Collection, Qu 9-NC-RFQ / LOCATION DE SA Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 800.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 LLE DE FORMATION AGENTS/ tions nvelope ation and Use of Core Social EHCVM -NSU and Economic Statistics CI-INS COTE D'IVOIRE-24527 Regional component: Harmo 0-NC-RFQ / FRAIS DE COMMU nization, Data Collection, Qu Request for Quota Single Stage - One E NICATION (coordonnateur, éq IDA / 65750 ality Improvement, Dissemin Post Limited 560.00 0.00 Canceled 2021-07-28 2021-09-22 2022-03-21 tions nvelope uipes technique et collecte / ation and Use of Core Social EHCVM-NSU and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21446 nization, Data Collection, Qu Request for Quota Single Stage - One E 2-NC-RFQ / Location motos p IDA / 65750 ality Improvement, Dissemin Post Limited 16,800.00 0.00 Canceled 2021-01-30 2021-03-27 2021-09-23 tions nvelope our la collecte sur le terrain ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21456 Regional component: Harmo 6-NC-RFQ / Reprographie des nization, Data Collection, Qu documents des projets (PAAS Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 6,726.00 0.00 Canceled 2022-03-28 2022-05-23 2022-11-19 , RAAS, PLATEFORME, REFON tions nvelope ation and Use of Core Social TE, ETUDE SNDS, RENFORCE and Economic Statistics MENT DE SITE PRODUCTION UTILISATEURS) Regional component: Harmo CI-INS COTE D'IVOIRE-21456 nization, Data Collection, Qu Request for Quota Single Stage - One E 9-NC-RFQ / Reprographie des IDA / 65750 ality Improvement, Dissemin Post Limited 8,126.00 0.00 Canceled 2022-04-24 2022-06-19 2022-12-16 tions nvelope documents ENSESI ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21447 nization, Data Collection, Qu 8-NC-RFQ / Acquisition de car IDA / 65750 ality Improvement, Dissemin Post Direct Selection Direct 40,000.00 0.00 Canceled 2021-01-28 2021-02-02 2021-03-09 2021-09-05 tes (traitement et production ation and Use of Core Social ) / CNTIG and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21453 nization, Data Collection, Qu 7-NC-DIR / Service autorisati IDA / 65750 ality Improvement, Dissemin Post Direct Selection Direct 65,000.00 0.00 Canceled 2022-03-30 2022-04-04 2022-05-09 2022-11-05 on de collecte de données gé ation and Use of Core Social ospatiales (ANAC) and Economic Statistics CI-INS COTE D'IVOIRE-21446 Regional component: Harmo 9-NC-RFQ / Recrutement d'un nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl prestataire pour l'assurances IDA / 65750 ality Improvement, Dissemin Post Limited 72,000.00 0.00 2022-06-06 2022-08-01 2023-01-28 tions nvelope ementation des trente (30) véhicules pou ation and Use of Core Social r les enquêtes et recenseme and Economic Statistics nts dans le cadre du projet Regional component: Harmo CI-INS COTE D'IVOIRE-21450 nization, Data Collection, Qu 8-NC-RFQ / Acquisition d'un S Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 6,000.00 0.00 Canceled 2022-04-19 2022-06-14 2022-12-11 ervice de VIDEO SURVEILLAN tions nvelope ation and Use of Core Social CE and Economic Statistics CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 1-NC-RFQ / Reprographie des nization, Data Collection, Qu Request for Quota Single Stage - One E documents des projets (C. CA IDA / 65750 ality Improvement, Dissemin Post Limited 1,500.00 0.00 Canceled 2022-04-23 2022-06-18 2022-12-15 tions nvelope RTO-CALL CENTER -UGP-REF ation and Use of Core Social ORME 1&2-CNStat) and Economic Statistics CI-INS COTE D'IVOIRE-27350 9-NC-RFQ / Recrutement d'un Country-Specific Component prestataire pour le câblage r : Improving and modernizing Request for Quota Single Stage - One E Under Imple IDA / 65770 Post Limited 50,000.00 0.00 2022-06-21 2022-07-20 2022-08-16 2022-09-30 éseau informatique, téléphon physical and statistical infra tions nvelope mentation ique, internet et pose de com structure binés téléphoniques des loca ux de l'UCP-PHAS CI-INS COTE D'IVOIRE-21457 Regional component: Harmo 3-NC-RFQ / Reprographie des nization, Data Collection, Qu Request for Quota Single Stage - One E documents des projets (LIAS IDA / 65750 ality Improvement, Dissemin Post Limited 8,490.00 0.00 Canceled 2022-05-01 2022-06-26 2022-12-23 tions nvelope SE, CR, CEA, SANTE, ICF, CE, ation and Use of Core Social MARGE) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21456 nization, Data Collection, Qu Request for Quota Single Stage - One E 8-NC-RFQ / Reprographie des IDA / 65750 ality Improvement, Dissemin Post Limited 7,257.00 0.00 Canceled 2022-03-22 2022-05-17 2022-11-13 tions nvelope documents RGPH 2020 ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21447 0-NC-RFQ / Recrutement d'un prestataire pour la fourniture Regional component: Harmo de police d'Assurances dom nization, Data Collection, Qu Request for Quota Single Stage - One E Pending Impl mage des agents de collecte IDA / 65750 ality Improvement, Dissemin Post Limited 26,627.00 0.00 2022-06-20 2022-08-15 2023-02-11 tions nvelope ementation dans le cadre des recenseme ation and Use of Core Social nts et enquêtes financés par and Economic Statistics le PHAS (recensement génér al des entreprises, enquête e mploi, recensements agricole s) CI-INS COTE D'IVOIRE-27350 4-NC-RFB / Recrutement d'un Country-Specific Component prestataire pour la location d : Improving and modernizing Request for Quota Single Stage - One E Under Imple e véhicules en appoint dans l IDA / 65770 Post Limited 30,000.00 0.00 2022-06-11 2022-06-15 2022-07-23 2023-01-19 physical and statistical infra tions nvelope mentation e cadre des enquêtes et inter structure ventions du projet (enquête pilote pour le recensement g énéral des entreprises). Page 5 Regional component: Harmo CI-INS COTE D'IVOIRE-24526 nization, Data Collection, Qu 7-NC-RFQ / Location de véhic Request for Quota Single Stage - One E IDA / 65750 ality Improvement, Dissemin Post Limited 7,200.00 0.00 Canceled 2021-08-02 2021-09-27 2022-03-26 ules de type 4x4 - Mission de tions nvelope ation and Use of Core Social supervision /EHCVM-NSU and Economic Statistics CI-INS COTE D'IVOIRE-27350 5-NC-RFQ / Recrutement d'un Country-Specific Component prestataire pour le câblage r : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 80,000.00 0.00 2022-09-26 2022-11-21 2023-01-05 éseau téléphonique, internet physical and statistical infra tions nvelope ementation et pose de combinés télépho structure niques des locaux du centre de cartographie CI-INS COTE D'IVOIRE-30974 Country-Specific Component 0-NC-RFQ / Recrutement d'un : Improving and modernizing Pending Impl prestataire pour les services IDA / 65770 Post Direct Selection Direct - National 20,000.00 0.00 2022-09-05 2022-09-10 2022-10-15 2023-04-13 physical and statistical infra ementation de gardiennage des locaux d structure u centre de cartographie CI-INS COTE D'IVOIRE-30974 Country-Specific Component 4-NC-DIR / Recrutement d'un : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 18,000.00 0.00 2022-12-05 2023-01-30 2023-07-29 prestataire pour l'entretien d physical and statistical infra tions nvelope ementation es locaux du centre de carto structure graphie CI-INS COTE D'IVOIRE-32364 Country-Specific Component 6-NC-DIR / Recrutement d'un : Improving and modernizing Pending Impl prestataire pour l'entretien d IDA / 65770 Post Direct Selection Direct - National 200,000.00 0.00 2022-12-01 2022-12-06 2023-01-10 2023-07-09 physical and statistical infra ementation es véhicules acquis par le Pro structure jet pour les enquêtes CI-INS COTE D'IVOIRE-33252 6-NC-RFQ / Recrutement d'un Project Management and Mo Request for Quota Single Stage - One E Pending Impl Prestataire pour la gestion de IDA / 65770 Post Limited 20,000.00 0.00 2023-02-13 2023-04-10 2023-10-07 nitoring and Evaluation tions nvelope ementation s transfert mobile money des agents dans le cadre des acti vités du Projet CI-INS COTE D'IVOIRE-33257 Country-Specific Component 4-NC-RFQ / Recrutement d'un : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 60,000.00 0.00 2023-04-05 2023-05-31 2023-11-27 prestataire pour la mise en pl physical and statistical infra tions nvelope ementation ace d'un système d'archivag structure e électronique CI-INS COTE D'IVOIRE-32365 Country-Specific Component 1-NC-DIR / Recrutement d'un : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 30,000.00 0.00 2023-04-08 2023-06-03 2023-11-30 Prestataire pour l'entretien d physical and statistical infra tions nvelope ementation es copieurs de l'UCP structure CI-INS COTE D'IVOIRE-35010 4-NC-RFQ / Recrutement d'un Country-Specific Component prestataire pour le Câblage r : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 90,000.00 0.00 2023-05-03 2023-06-28 2023-12-25 éseau, informatique et téléph physical and statistical infra tions nvelope ementation onique pour le centre d’appel structure de l’Institut National de la St atistique (INS) CI-INS COTE D'IVOIRE-35011 Country-Specific Component 1-NC-RFQ / Recrutement d’u : Improving and modernizing Request for Quota Single Stage - One E Pending Impl n Prestataire pour l’entretien IDA / 65770 Post Limited 30,000.00 0.00 2023-05-09 2023-07-04 2023-12-31 physical and statistical infra tions nvelope ementation des locaux des trois (03) Cen structure tres (Cartographie, Appel et CAE) CI-INS COTE D'IVOIRE-35015 Country-Specific Component 0-NC-DIR / Convention avec l’ : Improving and modernizing Pending Impl Institut National de la Statisti IDA / 65770 Prior Direct Selection Direct - National 2,000,000.00 0.00 2023-05-02 2023-05-07 2023-06-11 2023-12-08 physical and statistical infra ementation que (INS) pour la mise en œu structure vre de l’enquête Budget Con sommation CI-INS COTE D'IVOIRE-35015 Country-Specific Component 3-NC-RFQ / Recrutement d'un : Improving and modernizing Pending Impl IDA / 65770 Post Direct Selection Direct - National 30,000.00 0.00 2023-04-14 2023-04-19 2023-05-24 2023-11-20 Prestataire pour l'entretien d physical and statistical infra ementation es locaux de l’UC PHAS structure CI-INS COTE D'IVOIRE-35028 Country-Specific Component 3-NC-RFQ / Recrutement d’u : Improving and modernizing Request for Quota Single Stage - One E Pending Impl n prestataire pour l’impressio IDA / 65770 Post Limited 30,000.00 0.00 2023-05-06 2023-07-01 2023-12-28 physical and statistical infra tions nvelope ementation n des documents et rapports structure dans le cadre des activités d u Projet CI-INS COTE D'IVOIRE-35029 Regional component: Harmo 1-NC-DIR / Convention avec l’ nization, Data Collection, Qu Pending Impl Institut National de la Statisti IDA / 65770 ality Improvement, Dissemin Post Direct Selection Direct - National 1,000,000.00 0.00 2023-04-27 2023-05-02 2023-06-06 2023-12-03 ementation que (INS) pour la mise en œ ation and Use of Core Social uvre de l’enquête emploi and Economic Statistics CI-INS COTE D'IVOIRE-35015 1-NC-DIR / Convention avec l’ Country-Specific Component Institut National de la Statisti : Improving and modernizing Pending Impl IDA / 65770 Prior Direct Selection Direct - National 4,000,000.00 0.00 2023-06-06 2023-06-11 2023-07-16 2024-07-15 que (INS) pour la mise en œu physical and statistical infra ementation vre du Recensement Général structure des entreprises et établissem ents de côte d’Ivoire (RGEECI ) CI-INS COTE D'IVOIRE-35013 Regional component: Harmo 8-NC-DIR / Convention avec l’ nization, Data Collection, Qu Pending Impl INS pour la mise en place du IDA / 65770 ality Improvement, Dissemin Prior Direct Selection Direct - National 3,000,000.00 0.00 2023-06-01 2023-06-06 2023-07-11 2024-01-07 ementation corps des agents enquêteurs ation and Use of Core Social sur une durée de deux ans et and Economic Statistics demi CI-INS COTE D'IVOIRE-35014 Country-Specific Component 1-NC-DIR / Recrutement d’un : Improving and modernizing Request for Quota Single Stage - One E Pending Impl IDA / 65770 Post Limited 30,000.00 0.00 2023-05-30 2023-07-25 2024-01-21 Prestataire pour le gardienna physical and statistical infra tions nvelope ementation ge des locaux de l’UCP structure CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CI-INS COTE D'IVOIRE-21458 3-CS-QCBS / Recrutement d'u Regional component: Harmo ne firme de Consultants pour nization, Data Collection, Qu Consultant Qualifi Under Implement le renforcement des capacité IDA / 65750 ality Improvement, Dissemin Post Limited 100,000.00 0.00 2021-03-15 2022-05-17 2021-03-29 2021-04-28 2021-06-02 2021-11-29 cation Selection ation s des techniciens (Formation ation and Use of Core Social en Big Data et tout autre for and Economic Statistics mation technique compléme ntaire) Page 6 CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 3-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi Pending Impleme n cabinet pour l'installation e IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 2021-02-05 2021-02-19 2021-03-21 2021-04-25 2021-10-22 cation Selection ntation t la maintenance d'une appli ation and Use of Core Social cation pour le Call Center and Economic Statistics CI-INS COTE D'IVOIRE-21487 Regional component: Harmo 1-CS-CQS / Recrutement d’un nization, Data Collection, Qu Quality And Cost- Open - Internationa e firme pour accompagner la IDA / 65750 ality Improvement, Dissemin Post 72,000.00 0.00 Under Review 2021-03-15 2022-02-08 2021-04-05 2021-05-19 2021-06-16 2021-07-16 2021-08-20 2021-09-24 2022-09-24 Based Selection l mise en œuvre de la formati ation and Use of Core Social on à distance and Economic Statistics CI-INS COTE D'IVOIRE-27349 0-CS-QCBS / Recrutement d'u Country-Specific Component ne firme pour l'audit des fond : Improving and modernizing Quality And Cost- Pending Impleme IDA / 65770 Post Open - National 50,000.00 0.00 2022-02-01 2022-02-22 2022-03-18 2022-04-15 2022-05-15 2022-06-19 2022-07-24 2022-10-22 s de la Banque Mondiale dan physical and statistical infra Based Selection ntation s le cadre du Recensement G structure énéral de la Population et de l'Habitat (RGPH) CI-INS COTE D'IVOIRE-27349 Country-Specific Component 8-CS-QCBS / Recrutement d'u : Improving and modernizing Quality And Cost- Open - Internationa Under Implement IDA / 65770 Post 150,000.00 0.00 2022-02-16 2022-03-09 2022-03-09 2022-04-06 2022-04-22 2022-05-20 2022-06-19 2022-07-24 2022-08-28 2023-08-28 n cabinet pour la mise en pla physical and statistical infra Based Selection l ation ce d'un modèle macro écono structure métrique CI-INS COTE D'IVOIRE-21487 Regional component: Harmo 0-CS-QCBS / Recrutement d’ nization, Data Collection, Qu une firme chargée d’accomp Quality And Cost- Under Implement IDA / 65750 ality Improvement, Dissemin Post Open - National 70,000.00 0.00 2022-04-07 2022-05-17 2022-04-28 2022-06-27 2022-06-11 2022-07-09 2022-08-08 2022-09-12 2022-10-17 2023-10-17 agner l’ENSEA dans le dévelo Based Selection ation ation and Use of Core Social ppement de certificats profes and Economic Statistics sionnels dans le cadre de la f ormation continue Regional component: Harmo CI-INS COTE D'IVOIRE-21460 nization, Data Collection, Qu 6-CS-QCBS / Recrutement Ca Least Cost Selecti Pending Impleme IDA / 65750 ality Improvement, Dissemin Post Open - National 10,000.00 0.00 2022-03-30 2022-04-20 2022-06-03 2022-07-01 2022-07-31 2022-09-04 2022-10-09 2023-04-07 binet d'Audit des comptes de on ntation ation and Use of Core Social gestion du Projet and Economic Statistics CI-INS COTE D'IVOIRE-21488 Regional component: Harmo 9-CS-CQS / Recrutement d’un nization, Data Collection, Qu Consultant Qualifi Cabinet de consultants pour l IDA / 65750 ality Improvement, Dissemin Post Limited 10,300.00 0.00 Canceled 2021-06-30 2021-07-14 2021-08-13 2021-09-17 2022-03-16 cation Selection a réalisation de l'Enquête Sol ation and Use of Core Social de opinions Immobiliers and Economic Statistics CI-INS COTE D'IVOIRE-21458 Regional component: Harmo 6-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi n Cabinet de conception de s IDA / 65750 ality Improvement, Dissemin Post Limited 40,000.00 0.00 Canceled 2021-02-12 2021-02-26 2021-03-28 2021-05-02 2021-10-29 cation Selection ite dans le cadre de la refont ation and Use of Core Social e du site internet de l'INS and Economic Statistics CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 2-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi n cabinet pour la réalisation IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 Canceled 2022-04-27 2022-05-11 2022-06-10 2022-07-15 2023-01-11 cation Selection de la 2ème étude spécifique ation and Use of Core Social sur les réformes institutionne and Economic Statistics lles de l'INS CI-INS COTE D'IVOIRE-21461 7-CS-QCBS / Assistance cons Regional component: Harmo eil d'un opérateur (Faire l’étu nization, Data Collection, Qu Consultant Qualifi de par l’inventaire des conne IDA / 65750 ality Improvement, Dissemin Post Limited 10,000.00 0.00 Canceled 2022-03-31 2022-04-14 2022-05-14 2022-06-18 2022-12-15 cation Selection xions Internet et des équipe ation and Use of Core Social ments informatiques d’interc and Economic Statistics onnexion existant pour les sit es à interconnecter) CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 1-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi n cabinet pour la réalisation IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 Canceled 2022-04-06 2022-04-20 2022-05-20 2022-06-24 2022-12-21 cation Selection de la 1ère étude spécifique s ation and Use of Core Social ur les réformes institutionnell and Economic Statistics es de l'INS CI-INS COTE D'IVOIRE-21458 Regional component: Harmo 7-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi n cabinet pour la réalisation IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 Canceled 2022-04-28 2022-05-12 2022-06-11 2022-07-16 2023-01-12 cation Selection de l'étude sur la SNDS 2017- ation and Use of Core Social 2021 and Economic Statistics CI-INS COTE D'IVOIRE-21488 Regional component: Harmo 6-CS-CQS / Recrutement d’un nization, Data Collection, Qu Consultant Qualifi Cabinet de consultants pour l IDA / 65750 ality Improvement, Dissemin Post Limited 10,300.00 0.00 Canceled 2022-02-24 2022-03-10 2022-04-09 2022-05-14 2022-11-10 cation Selection a réalisation de l'Enquête Sol ation and Use of Core Social de opinions Transport and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 9-CS-QCBS / Recrutement d'u nization, Data Collection, Qu Consultant Qualifi n Cabinet pour l'élaboration IDA / 65750 ality Improvement, Dissemin Post Limited 30,000.00 0.00 Canceled 2021-02-10 2021-02-24 2021-03-26 2021-04-30 2021-10-27 cation Selection du Manuel de procédures du ation and Use of Core Social Projet and Economic Statistics CI-INS COTE D'IVOIRE-30975 6-CS-QCBS / Recrutement d'u Country-Specific Component ne firme pour la mise en plac : Improving and modernizing Quality And Cost- Open - Internationa IDA / 65770 Post 150,000.00 0.00 Under Review 2022-09-28 2022-10-18 2022-10-19 2022-12-02 2022-12-30 2023-01-29 2023-03-05 2023-04-09 2024-04-08 e d’un modèle de prévisions physical and statistical infra Based Selection l macroéconomiques trimestri structure elles (macrotrim) pour la côt e d’ivoire CI-INS COTE D'IVOIRE-32271 Country-Specific Component 2-CS-CQS / Recrutement d’un : Improving and modernizing Consultant Qualifi Under Implement e firme pour un accompagne IDA / 65770 Post Open - National 75,000.00 0.00 2022-11-30 2023-01-31 2022-12-21 2023-05-05 2023-02-03 2023-03-05 2023-04-09 2023-10-06 physical and statistical infra cation Selection ation ment technique dans le cadr structure e de la mise en place du cent re d’appels CI-INS COTE D'IVOIRE-30215 4-CS-QCBS / Recrutement d'u ne firme pour la Mise en plac Country-Specific Component e d’un modèle d’équilibre gé : Improving and modernizing Quality And Cost- Open - Internationa IDA / 65770 Post 100,000.00 0.00 Under Review 2022-11-30 2023-04-05 2022-12-21 2023-02-03 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2024-06-10 néral calculable statique et d physical and statistical infra Based Selection l ynamique (MEGC) et d’un mo structure dèle d’équilibre général stoc hastique dynamique (DGSE) pour la Côte d’ivoire CI-INS COTE D'IVOIRE-33225 Country-Specific Component 6-CS-QBS / Recrutement d'un : Improving and modernizing Quality Based Sel Open - Internationa Pending Impleme IDA / 65770 Post 158,000.00 0.00 2023-02-02 2023-02-23 2023-04-08 2023-05-06 2023-06-05 2023-07-05 2023-08-09 2024-08-08 cabinet pour la mise en place physical and statistical infra ection l ntation d'un modèle d'équilibre géné structure ral calculable Page 7 CI-INS COTE D'IVOIRE-33225 Country-Specific Component 7-CS-QBS / Recrutement d'un : Improving and modernizing Quality Based Sel Open - Internationa e firme pour la mise en place IDA / 65770 Post 103,000.00 0.00 Under Review 2023-03-01 2023-04-05 2023-03-22 2023-05-05 2023-06-02 2023-07-02 2023-08-01 2023-09-05 2024-09-04 physical and statistical infra ection l d'un modèle DSGE (Dynamic structure Stochastic General Equilibriu m) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu 3-CS-INDV / Recrutement Sp Individual Consult Under Implement IDA / 65750 ality Improvement, Dissemin Post Open 48,000.00 0.00 2021-02-03 2021-03-29 2021-03-24 2021-09-03 2021-04-14 2021-05-19 2021-11-15 écialiste en Passation de Mar ant Selection ation ation and Use of Core Social chés du Projet and Economic Statistics CI-INS COTE D'IVOIRE-21461 Regional component: Harmo 5-CS-INDV / Recrutement d’u nization, Data Collection, Qu n consultant chargé de l’ani Individual Consult Under Implement IDA / 65750 ality Improvement, Dissemin Post Open 10,000.00 0.00 2021-03-15 2022-05-17 2021-05-03 2021-05-24 2021-06-28 2021-12-25 mation du pôle de recherche ant Selection ation ation and Use of Core Social et de développement des co and Economic Statistics mpétences en statistique et r essources numériques Regional component: Harmo CI-INS COTE D'IVOIRE-21488 nization, Data Collection, Qu 4-CS-INDV / Recrutement d'u Individual Consult Under Implement IDA / 65750 ality Improvement, Dissemin Post Limited 15,744.00 0.00 2021-05-14 2022-03-23 2021-05-19 2021-06-09 2021-07-14 2022-01-10 n consultant Formateur en te ant Selection ation ation and Use of Core Social chnique de Prévision and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21489 nization, Data Collection, Qu 0-CS-INDV / Recrutement d'u Individual Consult Pending Impleme IDA / 65750 ality Improvement, Dissemin Post Limited 40,000.00 0.00 2021-03-15 2021-03-20 2021-04-10 2021-05-15 2021-11-11 n consultant dans le cadre de ant Selection ntation ation and Use of Core Social l'activité IPS ICA and Economic Statistics CI-INS COTE D'IVOIRE-21490 Regional component: Harmo 2-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult Pending Impleme n Expert pour la production d IDA / 65750 ality Improvement, Dissemin Post Limited 8,800.00 0.00 2021-03-15 2021-03-20 2021-04-10 2021-05-15 2021-11-11 ant Selection ntation es Statistiques du Commerce ation and Use of Core Social Extérieur and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-22840 nization, Data Collection, Qu Individual Consult 2-CS-INDV / Recrutement du IDA / 65750 ality Improvement, Dissemin Post Open 72,000.00 3,085.31 Signed 2021-04-17 2021-05-27 2021-06-05 2021-09-01 2021-06-26 2021-10-08 2021-07-31 2021-11-06 2022-01-27 ant Selection Coordonnateur du Projet ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-22840 nization, Data Collection, Qu 5-CS-INDV / Recrutement du Individual Consult IDA / 65750 ality Improvement, Dissemin Post Open 48,000.00 0.00 Under Review 2021-04-12 2021-05-27 2021-05-31 2022-01-14 2021-06-21 2021-07-26 2022-01-22 Spécialiste en gestion financi ant Selection ation and Use of Core Social ère et décaissement (RAF) and Economic Statistics CI-INS COTE D'IVOIRE-26140 3-CS-CDS / Convention avec l ’INS relative au recrutement Regional component: Harmo du personnel de collecte et d nization, Data Collection, Qu ’un opérateur de paiement m IDA / 65750 ality Improvement, Dissemin Prior Direct Selection Direct 12,216,000.00 0.00 Canceled 2021-11-05 2021-11-15 2022-01-19 2022-07-18 obile pour le paiement des p ation and Use of Core Social erdiems du personnel de coll and Economic Statistics ecte dans le cadre du Recens ement Général de la Populati on et de l’Habitat 2021-10-21 (RGPH 2021) CI-INS COTE D'IVOIRE-26235 9-CS-CDS / Convention avec l ’INS relative au recrutement Regional component: Harmo du personnel de collecte et d nization, Data Collection, Qu ’un opérateur de paiement m IDA / 65750 ality Improvement, Dissemin Prior Direct Selection Direct 16,483,740.00 0.00 Under Review 2021-11-10 2021-11-12 2021-11-20 2021-11-15 2022-01-24 2022-07-23 obile pour le paiement des p ation and Use of Core Social erdiems du personnel de coll and Economic Statistics ecte dans le cadre du recens ement Général de la Populati on et de l’Habitat 2021-10-21 (RGPH 2021) CI-INS COTE D'IVOIRE-27334 Country-Specific Component Individual Consult Under Implement 6-CS-INDV / Recruter 20 Adjo IDA / 65770 : Improving and modernizing Post Open 25,000.00 0.00 2022-02-07 2022-05-12 2022-03-08 2022-03-18 2022-04-04 2023-04-04 ant Selection ation ints Techniques de la Statisti physical and statistical infra que structure CI-INS COTE D'IVOIRE-27334 Country-Specific Component Individual Consult Under Implement 7-CS-INDV / Recrutement de IDA / 65770 : Improving and modernizing Post Open 36,000.00 0.00 2022-02-07 2022-05-12 2022-03-13 2022-03-14 2022-04-03 2023-04-03 ant Selection ation trois (03) géomaticiens physical and statistical infra structure CI-INS COTE D'IVOIRE-27349 Country-Specific Component 2-CS-INDV / recrutement d'u : Improving and modernizing Individual Consult Under Implement n consultant international sta IDA / 65770 Post Open 30,000.00 0.00 2022-02-17 2022-11-07 2022-04-07 2022-04-28 2022-06-02 2022-08-31 physical and statistical infra ant Selection ation tisticien agricole spécialisé e structure n sondage et analyse de don nées CI-INS COTE D'IVOIRE-27349 4-CS-INDV / Recrutement d’u Country-Specific Component n consultant individuel pour l : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open 50,000.00 0.00 2022-02-10 2022-05-17 2022-03-31 2022-04-21 2022-05-26 2022-08-24 ’élaboration des textes juridi physical and statistical infra ant Selection ation ques associes a la création d’ structure une fondation liée a l’ENSEA CI-INS COTE D'IVOIRE-27349 Country-Specific Component 6-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme n Consultant Individuel pour l IDA / 65770 Post Open 36,000.00 0.00 2022-02-10 2022-03-31 2022-04-21 2022-05-26 2022-08-24 physical and statistical infra ant Selection ntation 'élaboration d'un nouveau dé structure cret sur le fonctionnement d e l'ENSEA CI-INS COTE D'IVOIRE-27355 5-CS-INDV / Recrutement d’u Project Management and Mo Individual Consult Under Implement n consultant pour les études IDA / 65770 Post Limited 10,000.00 0.00 2022-02-01 2022-02-21 2022-02-06 2022-02-27 2022-04-03 2022-04-18 nitoring and Evaluation ant Selection ation de réhabilitation/configuratio n des bureaux du Projet et d u centre de cartographie CI-INS COTE D'IVOIRE-21485 Regional component: Harmo 5-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult Under Implement quinze (15) Ingénieurs Statist IDA / 65750 ality Improvement, Dissemin Post Open 267,505.00 0.00 2022-04-06 2022-05-12 2022-05-25 2022-06-15 2022-07-20 2023-01-16 ant Selection ation iciens Economistes pour le re ation and Use of Core Social nforcement des capacités tec and Economic Statistics hnique de l'INS Page 8 Regional component: Harmo CI-INS COTE D'IVOIRE-21460 nization, Data Collection, Qu 8-CS-INDV / Recrutement Co Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 14,400.00 0.00 Canceled 2021-02-08 2021-02-13 2021-03-06 2021-04-10 2021-10-07 nducteur de véhicule adminis ant Selection ation and Use of Core Social tratif du Projet and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21460 nization, Data Collection, Qu Individual Consult 7-CS-INDV / Recrutement Ag IDA / 65750 ality Improvement, Dissemin Post Limited 16,800.00 0.00 Canceled 2021-02-08 2021-02-13 2021-03-06 2021-04-10 2021-10-07 ant Selection ent de liaison du Projet ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu Individual Consult 8-CS-INDV / Recrutement Log IDA / 65750 ality Improvement, Dissemin Post Open 24,000.00 0.00 Canceled 2021-02-05 2021-03-26 2021-04-16 2021-05-21 2021-11-17 ant Selection isticien du Projet ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21489 Regional component: Harmo 2-CS-CDS / Mise en place d'u nization, Data Collection, Qu n Système d'Information Géo IDA / 65750 ality Improvement, Dissemin Post Direct Selection Direct 200,000.00 0.00 Canceled 2021-01-29 2021-02-08 2021-04-14 2021-10-11 graphique pour le recenseme ation and Use of Core Social nt des entreprises (CNTIG) and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu Individual Consult 9-CS-INDV / Recrutement Ass IDA / 65750 ality Improvement, Dissemin Post Open 24,000.00 0.00 Canceled 2021-02-05 2021-03-26 2021-04-16 2021-05-21 2021-11-17 ant Selection istante de Direction du Projet ation and Use of Core Social and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-22840 nization, Data Collection, Qu 6-CS-INDV / Recrutement du Individual Consult IDA / 65750 ality Improvement, Dissemin Post Open 48,000.00 0.00 Canceled 2021-04-12 2021-05-27 2021-05-31 2021-06-21 2021-07-26 2022-01-22 Spécialiste en Suivi Evaluatio ant Selection ation and Use of Core Social n du Projet and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21488 nization, Data Collection, Qu 3-CS-INDV / Recrutement d’u Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 16,000.00 0.00 Canceled 2021-03-15 2021-03-20 2021-04-10 2021-05-15 2021-11-11 n consultant Formation Conjo ant Selection ation and Use of Core Social ncture and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21489 nization, Data Collection, Qu 7-CS-INDV / Recrutement d'e Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 16,000.00 0.00 Canceled 2021-02-19 2021-02-24 2021-03-17 2021-04-21 2021-10-18 xpert-comptable auprès d'un ant Selection ation and Use of Core Social cabinet comptable and Economic Statistics CI-INS COTE D'IVOIRE-21489 Regional component: Harmo 6-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult ux (02) experts informaticien IDA / 65750 ality Improvement, Dissemin Post Limited 56,330.00 0.00 Canceled 2021-01-29 2021-02-03 2021-02-24 2021-03-31 2021-09-27 ant Selection s pour les travaux de liasses ation and Use of Core Social auprès d'un cabinet informati and Economic Statistics que CI-INS COTE D'IVOIRE-21489 Regional component: Harmo 8-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult consultants pour la productio IDA / 65750 ality Improvement, Dissemin Post Limited 26,000.00 0.00 Canceled 2021-04-19 2021-04-24 2021-05-15 2021-06-19 2021-12-16 ant Selection n des comptes satellites de l ation and Use of Core Social a Santé and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21459 nization, Data Collection, Qu Individual Consult 7-CS-INDV / Recrutement Co IDA / 65750 ality Improvement, Dissemin Post Open 24,000.00 0.00 Canceled 2021-02-04 2021-03-25 2021-04-15 2021-05-20 2021-11-16 ant Selection mptable du Projet ation and Use of Core Social and Economic Statistics CI-INS COTE D'IVOIRE-21490 Regional component: Harmo 1-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult Consultants pour la productio IDA / 65750 ality Improvement, Dissemin Post Limited 16,000.00 0.00 Canceled 2021-06-18 2021-06-23 2021-07-14 2021-08-18 2022-02-14 ant Selection n des comptes Economiques ation and Use of Core Social de l'agriculture and Economic Statistics CI-INS COTE D'IVOIRE-21490 Regional component: Harmo 3-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult n Informaticien programmeur IDA / 65750 ality Improvement, Dissemin Post Limited 10,000.00 0.00 Canceled 2021-03-25 2021-03-30 2021-04-20 2021-05-25 2021-11-21 ant Selection pour la production des statist ation and Use of Core Social iques du Commerce Extérieu and Economic Statistics r Regional component: Harmo CI-INS COTE D'IVOIRE-21490 nization, Data Collection, Qu 4-CS-INDV / Recrutement d'u Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 Canceled 2021-02-15 2021-02-20 2021-03-13 2021-04-17 2021-10-14 n consultant à long terme en ant Selection ation and Use of Core Social Comptabilité National and Economic Statistics Regional component: Harmo CI-INS COTE D'IVOIRE-21490 nization, Data Collection, Qu 5-CS-INDV / Recrutement d’u Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 35,000.00 0.00 Canceled 2021-02-15 2021-02-20 2021-03-13 2021-04-17 2021-10-14 n consultant à long terme en ant Selection ation and Use of Core Social Statistique d'Entreprises and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 1-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult n Consultant Expertise équip IDA / 65750 ality Improvement, Dissemin Post Limited 12,000.00 0.00 Canceled 2021-02-15 2021-02-20 2021-03-13 2021-04-17 2021-10-14 ant Selection e technique pour l'indice d'ac ation and Use of Core Social cessibilité and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 5-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult n Consultant en organisation IDA / 65750 ality Improvement, Dissemin Post Open 12,000.00 0.00 Canceled 2021-02-08 2021-03-29 2021-04-19 2021-05-24 2021-11-20 ant Selection statistique dans le cadre de l ation and Use of Core Social a refonte du site internet de l and Economic Statistics 'INS Regional component: Harmo CI-INS COTE D'IVOIRE-21487 nization, Data Collection, Qu 3-CS-CQS / Recrutement de c Individual Consult IDA / 65750 ality Improvement, Dissemin Post Limited 4,000.00 0.00 Canceled 2022-04-05 2022-04-10 2022-05-01 2022-06-05 2022-12-02 onsultant Enquête Producteu ant Selection ation and Use of Core Social r de l'agriculture and Economic Statistics CI-INS COTE D'IVOIRE-27349 Country-Specific Component 1-CS-INDV / Recrutement d’u : Improving and modernizing Individual Consult n consultant international inf IDA / 65770 Post Open 30,000.00 0.00 Canceled 2022-02-08 2022-03-29 2022-04-19 2022-05-24 2022-08-22 physical and statistical infra ant Selection ormaticien spécialisé en trait structure ement informatique des rece nsements et enquêtes Page 9 CI-INS COTE D'IVOIRE-21486 Regional component: Harmo 5-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult Pending Impleme n Webmaster pour le centre IDA / 65750 ality Improvement, Dissemin Post Open 36,000.00 0.00 2022-07-28 2022-09-15 2022-10-06 2022-11-10 2023-05-09 ant Selection ntation de traitement des travaux ca ation and Use of Core Social rtographiques et la refonte d and Economic Statistics u site internet de l'INS CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 4-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult n Webmaster dans le cadre d IDA / 65750 ality Improvement, Dissemin Post Open 5,000.00 0.00 Canceled 2021-02-08 2021-03-29 2021-04-19 2021-05-24 2021-11-20 ant Selection e la refonte du site internet d ation and Use of Core Social e l'INS and Economic Statistics CI-INS COTE D'IVOIRE-21460 Regional component: Harmo 3-CS-INDV / Recrutement d'u nization, Data Collection, Qu Individual Consult n Webmaster pour le centre IDA / 65750 ality Improvement, Dissemin Post Limited 16,800.00 0.00 Canceled 2022-05-30 2022-06-04 2022-06-25 2022-07-30 2023-01-26 ant Selection de traitement des travaux ca ation and Use of Core Social rtographiques and Economic Statistics CI-INS COTE D'IVOIRE-21486 Regional component: Harmo 3-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult douze (12) Adjoints Techniqu IDA / 65750 ality Improvement, Dissemin Post Open 250,734.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-01-10 ant Selection es des statistiques pour le re ation and Use of Core Social nforcement des capacités tec and Economic Statistics hniques de l'INS CI-INS COTE D'IVOIRE-21486 Regional component: Harmo 2-CS-INDV / Recrutement de nization, Data Collection, Qu Individual Consult dix (10) ingénieurs des trava IDA / 65750 ality Improvement, Dissemin Post Open 260,539.00 0.00 Canceled 2021-02-11 2021-04-01 2021-04-22 2021-05-27 2021-11-23 ant Selection ux statistiques pour le renfor ation and Use of Core Social cement des capacités techni and Economic Statistics ques de l'INS CI-INS COTE D'IVOIRE-29798 Regional component: Harmo 4-CS-INDV / RECRUTEMENT D nization, Data Collection, Qu Individual Consult E SEIZE (16) INGENIEURS DE IDA / 65770 ality Improvement, Dissemin Post Open 300,000.00 0.00 Under Review 2022-07-20 2022-06-16 2022-09-07 2022-09-28 2022-11-02 2023-05-01 ant Selection S TRAVAUX STATISTIQUES (IT ation and Use of Core Social S), and Economic Statistics CI-INS COTE D'IVOIRE-29798 5-CS-INDV / RECRUTEMENT D Country-Specific Component E 02 INGENIEURS INFORMATI : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open 48,000.00 0.00 2022-07-15 2022-06-16 2022-09-02 2022-09-23 2022-10-28 2023-04-26 CIENS (DEVELOPPEUR D’APP physical and statistical infra ant Selection ation LICATIONS ET WEBMASTER) structure dans le cadre du programme des jeunes professionnels CI-INS COTE D'IVOIRE-29806 2-CS-CDS / Recrutement d'un Cabinet d'audit comptable et Project Management and Mo IDA / 65770 Post Direct Selection Direct 10,000.00 0.00 Under Review 2022-06-21 2022-06-15 2022-07-01 2022-09-04 2023-03-03 financier pour la réalisation d nitoring and Evaluation e l'audit comptable et financi er de l'exercice 2021 du PHA S CI-INS COTE D'IVOIRE-30850 4-CS-INDV / Recrutement d'u Country-Specific Component n consultant pour l'élaboratio : Improving and modernizing Individual Consult Under Implement n des plans d'aménagements IDA / 65770 Post Limited 25,000.00 0.00 2022-09-09 2022-12-19 2022-09-14 2022-09-19 2022-10-31 2023-04-29 physical and statistical infra ant Selection ation et la supervision des travaux structure d'aménagement des nouvea ux bâtiments de l'INS et du c entre de cartographie CI-INS COTE D'IVOIRE-32272 2-CS-INDV / Recrutement d'u Country-Specific Component n consultant individuel pour l' : Improving and modernizing Individual Consult Pending Impleme IDA / 65770 Post Limited 20,000.00 0.00 2022-11-30 2022-12-05 2022-12-26 2023-01-30 2023-07-29 élaboration des cahiers de ch physical and statistical infra ant Selection ntation arges et la maitrise d'œuvre structure des travaux d'aménagement des différents centres CI-INS COTE D'IVOIRE-30847 4-CS-INDV / Recrutement de Country-Specific Component deux (02) Consultants superv : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 48,000.00 0.00 2022-11-30 2022-12-28 2023-01-18 2023-02-08 2023-03-15 2023-09-11 iseurs pour la mise en place physical and statistical infra ant Selection ation des centres d'appel, centre d structure 'innovation cartographique et centre de calcul CI-INS COTE D'IVOIRE-30851 8-CS-INDV / Recrutement d’u Country-Specific Component n Consultant pour l'Actualisat : Improving and modernizing Individual Consult Pending Impleme ion des analyses approfondie IDA / 65770 Post Limited 10,000.00 0.00 2022-12-02 2022-12-07 2022-12-28 2023-02-01 2023-07-31 physical and statistical infra ant Selection ntation s de l’EHCVM 2018 et de la D structure ynamique de la pauvreté ent re 1993 et 2018 en Côte d’Iv oire CI-INS COTE D'IVOIRE-30849 Country-Specific Component 1-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Under Implement deux (02) consultants cartoth IDA / 65770 Post Limited 40,000.00 0.00 2022-12-01 2022-12-28 2022-12-06 2022-12-27 2023-01-31 2023-07-30 physical and statistical infra ant Selection ation écaires pour la mise en place structure du centre de cartographie CI-INS COTE D'IVOIRE-30850 Country-Specific Component 1-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Under Implement quarante (40) téléopérateurs IDA / 65770 Post Open - National 180,000.00 0.00 2023-01-31 2022-12-28 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infra ant Selection ation pour la mise en place et le fo structure nctionnement du centre d'ap pel CI-INS COTE D'IVOIRE-32364 Country-Specific Component 8-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Under Implement quinze (15) consultants lecte IDA / 65770 Post Open - National 50,000.00 0.00 2023-01-31 2022-12-27 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infra ant Selection ation urs pour la relecture et la vali structure dation des rapports d’analys e CI-INS COTE D'IVOIRE-30847 5-CS-INDV / Recrutement d'u Country-Specific Component n Consultant Ingénieur en rés : Improving and modernizing Individual Consult Pending Impleme eau, sécurité et système d'in IDA / 65770 Post Open - National 36,000.00 0.00 2023-01-31 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infra ant Selection ntation formation pour la mise en pla structure ce et l'opérationnalisation du centre d'appel pour la collect e des données de l'INS CI-INS COTE D'IVOIRE-30849 6-CS-INDV / Recrutement d'u Country-Specific Component n Consultant expert en sécuri : Improving and modernizing Individual Consult IDA / 65770 Post Open - National 30,000.00 0.00 Under Review 2023-01-31 2023-06-20 2023-03-21 2023-04-11 2023-05-16 2023-11-12 té et réseau pour la mise en physical and statistical infra ant Selection place des centres d'appel, de structure calcul et d'innovation cartogr aphique CI-INS COTE D'IVOIRE-30849 Country-Specific Component 8-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 36,000.00 0.00 2023-01-19 2022-12-28 2023-03-09 2023-03-30 2023-05-04 2023-10-31 n Consultant Project Manage physical and statistical infra ant Selection ation ment Officer pour l'INS structure Page 10 CI-INS COTE D'IVOIRE-30851 Country-Specific Component 3-CS-CDS / Actualisation des : Improving and modernizing Pending Impleme IDA / 65770 Post Direct Selection Direct - National 20,000.00 0.00 2022-11-30 2022-12-10 2023-02-13 2023-08-12 analyses approfondies de l’E physical and statistical infra ntation HCVM 2018 par l’équipe de r structure echerche de l’ENSEA CI-INS COTE D'IVOIRE-30849 4-CS-INDV / Recrutement d'u Country-Specific Component n Consultant Chargé des opé : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 24,000.00 0.00 2023-01-31 2022-12-28 2023-03-21 2023-04-11 2023-05-16 2023-11-12 rations pour le centre d'innov physical and statistical infra ant Selection ation ation cartographique, d'analy structure se économique et du centre de calcul CI-INS COTE D'IVOIRE-32270 Country-Specific Component 9-CS-CDS / FORMATION DES : Improving and modernizing Under Implement IDA / 65770 Post Direct Selection Direct - National 45,000.00 0.00 2023-01-31 2023-01-20 2023-02-10 2023-04-16 2023-10-13 TELE OPERATEURS AUX TEC physical and statistical infra ation HNIQUES DE COLLECTE DE D structure ONNEES CI-INS COTE D'IVOIRE-32364 9-CS-INDV / Recrutement de Country-Specific Component quinze (15) consultants analy : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 180,000.00 0.00 2023-01-31 2022-12-27 2023-03-21 2023-04-11 2023-05-16 2023-11-12 stes pour la relecture et la va physical and statistical infra ant Selection ation lidation des rapports d’analy structure se thématique du Recensem ent de la Population 2021 CI-INS COTE D'IVOIRE-33224 Country-Specific Component 6-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Open - Internationa Pending Impleme n Consultant pour la mise en IDA / 65770 Post 30,000.00 0.00 2023-01-31 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infra ant Selection l ntation place d'un dispositif de collec structure te de données sur l'emploi CI-INS COTE D'IVOIRE-33225 Country-Specific Component 1-CS-INDV / Recrutement d’u : Improving and modernizing Individual Consult Under Implement n consultant individuel infor IDA / 65770 Post Open - National 40,000.00 0.00 2023-01-31 2022-12-27 2023-03-21 2023-04-11 2023-05-16 2023-11-12 physical and statistical infra ant Selection ation maticien spécialisé en traite structure ment informatique des recen sements et enquêtes CI-INS COTE D'IVOIRE-33225 Country-Specific Component 2-CS-INDV / Recrutement d’u : Improving and modernizing Individual Consult Pending Impleme n consultant individuel en ap IDA / 65770 Post Open - National 35,000.00 0.00 2023-03-01 2023-04-19 2023-05-10 2023-06-14 2023-12-11 physical and statistical infra ant Selection ntation pui au Calcul des Indices des structure valeurs unitaires (IVU) et des termes de l’échange (TE) CI-INS COTE D'IVOIRE-33225 Country-Specific Component 9-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme IDA / 65770 Post Limited 12,000.00 0.00 2023-03-28 2023-04-02 2023-04-23 2023-05-28 2023-11-24 n Consultant formateur en Te physical and statistical infra ant Selection ntation chniques d'Analyses conjonct structure urelles CI-INS COTE D'IVOIRE-33226 Country-Specific Component 3-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme IDA / 65770 Post Limited 10,000.00 0.00 2023-02-28 2023-03-05 2023-03-26 2023-04-30 2023-10-27 n agent d'anonymisation et l physical and statistical infra ant Selection ntation abellisation des données structure CI-INS COTE D'IVOIRE-33226 Country-Specific Component 5-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme n consultant individuel pour IDA / 65770 Post Limited 15,000.00 0.00 2023-02-22 2023-02-27 2023-03-20 2023-04-24 2023-10-21 physical and statistical infra ant Selection ntation élaboreration d'un Projet de structure Décret portant tarification de s produits statistiques CI-INS COTE D'IVOIRE-33226 6-CS-INDV / Recrutement d'u Country-Specific Component n consultant individuel pour : Improving and modernizing Individual Consult Pending Impleme élaboreration d'un Projet de IDA / 65770 Post Limited 15,000.00 0.00 2023-02-28 2023-03-05 2023-03-26 2023-04-30 2023-10-27 physical and statistical infra ant Selection ntation décret fixant les modalités d structure e communication des fichiers administratifs aux administra tions du SSN CI-INS COTE D'IVOIRE-33226 7-CS-INDV / Recrutement d'u Country-Specific Component n consultant individuel pour l' : Improving and modernizing Individual Consult Pending Impleme élaboraration d'un Projet de IDA / 65770 Post Limited 15,000.00 0.00 2023-03-30 2023-04-04 2023-04-25 2023-05-30 2023-11-26 physical and statistical infra ant Selection ntation Décret fixant les modalités d’ structure attribution du visa pour les e nquêtes et recensements eff ectués par les organes du SS N CI-INS COTE D'IVOIRE-33226 9-CS-INDV / Recrutement de Country-Specific Component dix (10) Ingénieurs statisticie : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 142,000.00 0.00 2023-07-31 2023-01-06 2023-09-18 2023-10-09 2023-11-13 2024-05-11 ns économistes dans le cadre physical and statistical infra ant Selection ation de la seconde cohorte du pro structure gramme des jeunes professio nnels CI-INS COTE D'IVOIRE-33227 1-CS-INDV / Recrutement de Country-Specific Component dix (10) Ingénieurs des Trava : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 200,000.00 0.00 2023-07-31 2023-01-06 2023-09-18 2023-10-09 2023-11-13 2024-05-11 ux Statistiques (ITS) dans le physical and statistical infra ant Selection ation cadre de la seconde cohorte structure du programme des jeunes pr ofessionnels CI-INS COTE D'IVOIRE-33227 2-CS-INDV / Recrutement de Country-Specific Component quatorze adjoint technique d : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 142,000.00 0.00 2023-07-31 2023-01-06 2023-09-18 2023-10-09 2023-11-13 2024-05-11 e la statistique dans le cadre physical and statistical infra ant Selection ation de la seconde cohorte du pro structure gramme des jeunes professio nnels CI-INS COTE D'IVOIRE-33253 Country-Specific Component 0-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme IDA / 65770 Post Limited 10,000.00 0.00 2023-02-28 2023-03-05 2023-03-26 2023-04-30 2023-10-27 n Consultant en appui à la pr physical and statistical infra ant Selection ntation oduction des comptes sectori structure els et satellites CI-INS COTE D'IVOIRE-33253 Country-Specific Component 3-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme n Consultant Programmeur e IDA / 65770 Post Open - National 15,000.00 0.00 2023-02-28 2023-04-18 2023-05-09 2023-06-13 2023-12-10 physical and statistical infra ant Selection ntation n appui aux activités d'exten structure sion et d'amélioration des co mptes nationaux annuels CI-INS COTE D'IVOIRE-33741 Country-Specific Component 3-CS-INDV / RECRUTEMENT D : Improving and modernizing Individual Consult ES TRENTE-TROIS ANALYSTE IDA / 65770 Post Open - National 165,000.00 0.00 Under Review 2023-03-01 2023-02-20 2023-04-19 2023-05-10 2023-06-14 2023-12-11 physical and statistical infra ant Selection S (CONSULTANTS) POUR LA structure REALISATION DES MONOGRA PHIES REGIONALES Page 11 CI-INS COTE D'IVOIRE-33254 Country-Specific Component 6-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Pending Impleme n consultant juriste pour la c IDA / 65770 Post Open - National 27,000.00 0.00 2023-05-31 2023-07-19 2023-08-09 2023-09-13 2024-03-11 physical and statistical infra ant Selection ntation onsolidation de la loi de 2013 structure et de la loi modifiée de 2020 relatives au SSN CI-INS COTE D'IVOIRE-33226 Country-Specific Component 0-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Under Implement IDA / 65770 Post Open - National 61,000.00 0.00 2023-03-15 2023-03-10 2023-05-03 2023-05-24 2023-06-28 2023-12-25 trois consultants data scienti physical and statistical infra ant Selection ation st au profit de l'INS structure CI-INS COTE D'IVOIRE-33255 5-GO-RFQ / Recrutement de Country-Specific Component deux (2) consultants pour l’él : Improving and modernizing Individual Consult Pending Impleme aboration des feuilles de mis IDA / 65770 Post Open - National 31,000.00 0.00 2023-04-06 2023-05-25 2023-06-15 2023-07-20 2024-01-16 physical and statistical infra ant Selection ntation e en place du Système d’Info structure rmation Statistique (SIS) de d eux (2) Services Statistiques Ministériels (SSM) CI-INS COTE D'IVOIRE-33227 Country-Specific Component 3-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Pending Impleme trois (03) démographes dans IDA / 65770 Post Open - National 66,000.00 0.00 2023-07-31 2023-09-18 2023-10-09 2023-11-13 2024-05-11 physical and statistical infra ant Selection ntation le cadre de la seconde cohort structure e du programme des jeunes professionnels CI-INS COTE D'IVOIRE-33254 Country-Specific Component 8-CS-INDV / Recrutement de : Improving and modernizing Individual Consult Pending Impleme deux (02) consultants pour l' IDA / 65770 Post Open - National 29,000.00 0.00 2023-04-13 2023-06-01 2023-06-22 2023-07-27 2024-01-23 physical and statistical infra ant Selection ntation animation d’un laboratoire d’ structure Innovation numérique en Sta tistique Appliquée CI-INS COTE D'IVOIRE-34926 Country-Specific Component 1-CS-INDV / Recrutement d'u : Improving and modernizing Individual Consult Under Implement n Ingénieur Informaticien spé IDA / 65770 Post Limited 20,000.00 0.00 2023-06-01 2023-06-22 2023-06-06 2023-06-27 2023-08-01 2024-01-28 physical and statistical infra ant Selection ation cialiste en réseau, sécurité et structure système d’information CI-INS COTE D'IVOIRE-35891 Regional component: Harmo 3-CS-CDS / Formation du cor nization, Data Collection, Qu Pending Impleme ps des agents enquêteurs au IDA / 65770 ality Improvement, Dissemin Post Direct Selection Direct - National 45,000.00 0.00 2023-06-01 2023-06-11 2023-08-15 2024-02-11 ntation x techniques de collecte de d ation and Use of Core Social onnées par l'ENSEA and Economic Statistics Page 12 18-MONTH PROCUREMENT PLAN Project information: Nigeria Rural Access And Agricultural Marketing Project (RAAMP) - P163353 Project Implementation Agencies: Federal Ministry of Agriculture and Rural Development and State Project Implementation Units (SPIUs) Date of the Procurement Plan: September 18, 2019 Period covered by this Procurement Plan: February 2019 to July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selecti Market on Evaluation Approa Review Metho Options Expected ch Prequal- Domestic Expected by Estimat d (Most date of Sr. Contract (Open- ification Preferenc date of Bank ed Cost (RFP, Advantageou bid/ No Description Nation (Yes/ e Contract (Prior/ (US$) RFB, s Bid, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated Criteria opening Limited DS etc.) etc.) etc.) Procurement of Air Conditioners 2 Limited Lowest March. 1 Post 24,600 RFQ No No Feb. 2020 Horse power Evaluated Cost 2020 (Split Unit) (Goods) Procurement of Steel File cabinets, Lowest March. 2 Spiral Binding Post 12,600 Limited RFQ Evaluated Cost No No Feb. 2020 2020 Machines and Consumables (Goods) Procurement of External hard disk + software packages Lowest March. 3 (licensed MS Post 12,300 Limited RFQ Evaluated Cost No No 2020 April. 2020 Office, Autocads, Antivirus, Converter etc) (Goods) Procurement of Laptops and Lowest March. 4 Post 100,000 Limited RFQ No No May. 2020 Tablets Evaluated Cost 2020 (Goods) Procurement Lowest March. 5 Post 22,400 Limited RFQ No No April. 2020 of Evaluated Cost 2020 Photocopying Machines (Goods) Medium Sized Lowest March. 6 Refrigerators Post 10,800 Limited RFQ Evaluated Cost No No 2020 April. 2020 (Goods) Procurement of Safety Equipment (Boots, Lowest 7 Post 39,000 Limited RFQ No No June. 2020 July, 2020 Helmets, Evaluated Cost Reflective Jackets etc.) (Goods) Construction Measuring Manual Wheel Lowest August. 8 Post 6,500 Limited RFQ No No July 2020 (Surveyor’s Evaluated Cost 2020 Wheel) (Goods) Roads Maintenance Equipment for Community based road maintenance (30 Nos tipping tricycles and other Open- 1,235,0 Lowest 9 equipment Post Nationa RFB No No Sept. 2020 Dec. 2020 00 Evaluated Cost such roads l signs and; cutlasses, wheelbarrows, hand rammer, digger, helmet, watering cans, reflective jacket, long shovel, nose cover, boots etc) (Goods) Procurement of Office Equipment, Printers, Open- Digital Lowest August. 10 Post 420,000 Nationa RFB No No June. 2020 Cameras & Evaluated Cost 2020 l Sundry Communicatio n devices (Goods) Purchase of Open- Project 2,940,0 Lowest March. 11 Prior Nationa RFB No No May. 2020 Vehicles 00 Evaluated Cost 2020 l (Goods) Server, Network System and other Open- Lowest equipment & Post 150,000 Nationa RFB Evaluated Cost No No Feb. 2020 May. 2020 accessories for l NiRTIMS and CosMos (Goods) Design and Construction of 200km of Rural Roads Open- 134,000 Rated Criteria (13 Prior Interna RFP No No Jun. 2020 Dec. 2020 ,000.00 and Cost Contracts of tional US$10.3 Million each) (Works) Construction/E stablishment Open – of Agro- 2,000,0 Lowest March. Post Nationa RFB No No July. 2021 Logistics 00 Evaluated Cost 2021 l centers/hubs at strategic locations (Multiple contracts) (Works) Construction /Rehabilitation of 10 Nos. Rural Bridges Open- 8,000,0 Lowest March. & Large Post Nationa RFB No No July. 2022 00 Evaluated Cost 2021 culverts (US$ l 0.6 M each Package) (Works) Local Community Group (LCG) and micro- enterprises maintenance Open- 14,000, Lowest of pilot roads Post Nationa RFB No No April. 2020 June.2020 000 Evaluated Cost (Multiple l Contracts in 13 States - US$ 0.002/year) (Works) II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Offshore & Onshore training and Workshops for Open- March. 1 the 13 states (Multiple Post 5,200,000 CQS No May. 2020 National 2020 contracts not to exceed US$ 0.1 M) (Consultancy) Consultancy Services for Detailed assessment, preliminary engineering design, ESIA, Procurement Support for Rural roads and Bridges; Road and 25,390,00 Open- 2 Bridge Supervision Prior QCBS Yes June. 2020 Nov. 2020 0 International Consultancy; Assessment of project security risk and mitigation (Multiple contracts spread in different locations) (Consultancy) Consultancy Services for design, procurement and supervision for Agro- Open- 3 logistics centers (Multiple Post 6,500,000 QCBS Yes Sep. 2020 Dec. 2020 International contracts spread in different locations) (Consultancy) Consultancy Services for the establishment of state Open- March. August. 4 road fund, and Post 5,665,000 QCBS Yes National 2020 2020 establishment of state rural access roads administration (Multiple contracts at 13 states) (Consultancy) Consultancy services on the development and operationalization of the Nigeria Rural Transport Infrastructure Management System (NiRTIMS) for sustainable road asset; Planning and Open- 5 Post 5,860,000 QCBS Yes Feb. 2020 July. 2020 implementation of the National routine maintenance system, spot improvement, periodic maintenance for rural roads. (Multiple contracts at 13 states) (Consultancy) Technical assistance consultancy services for the provision of technical advice (TA) to enhance the performance of agro- logistics centers (to ensure effective utilization of the facilities at the agro- Open- National March. 6 logistics centers); Post 4,975,000 QCBS Yes July. 2020 provision of TA and 2020 implements to farm level post-harvest agro-logistics activities and enhance the engagement of women and unemployed youth. (Multiple contracts at 13 states) (Consultancy) Consultancy services support for coordination of Open- 7 Post 2,442,000 CQS No Feb. 2020 April. 2020 project implementation at National Federal and State Levels (Multiple contracts at 13 states) (Consultancy) Consultancy services on Impact Evaluation, Baseline Data Collection, Comprehensive Technical Audit, Consultancy support for the development and Open- March. 8 operationalization of the Post 5,325,000 QCBS Yes July.2020 National 2020 smartphone-based construction site monitoring system (CoSMoS) (Multiple contracts at 13 states) (Consultancy) Consultancy support for the development and monitoring of Grievance Redress Mechanism and Gender-Based Violence; Development of road safety manual and training Open- 9 Post 1,843,000 CQS No April.2020 June. 2020 at the state level; National establishment/strengtheni ng the state traffic management agencies; road safety audit. (Multiple contracts at 13 states) (Consultancy) Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Rural Access and Agricultural Marketing Project PLAN General Information Country: Nigeria 2023-02-10 Bank’s Approval Date of the Original Procurement Plan: 2023-06-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163353 GPN Date: Project Name: Nigeria Rural Access and Agricultural Marketing Project Loan / Credit No: IDA / 65190 Ekiti RAAMP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - NG-EKITI RAAMP-331057-CW Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-06-2 -RFB / Construction of 40KM IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 6,400,000.00 0.00 2023-09-06 2023-09-11 2023-10-23 2023-11-22 2023-12-27 nvelope (1 envelope proce lementation 4 Rural Roads Upgrading ance Enhancement and Sect ss) or Reform NG-EKITI RAAMP-331060-CW Component B. Asset Manage Request for Bids - -RFB / Construction of 100 Li ment, Agro-logistics Perform Single Stage - One E Small Works SPD Pending Imp 2024-06-2 IDA / 65190 Post Request for Bids Open - National 1,200,000.00 0.00 2023-09-05 2023-09-10 2023-10-22 2023-11-21 2023-12-26 near meters cross Drainage ance Enhancement and Sect nvelope (1 envelope proce lementation 3 Structures(Culverts/Bridges) or Reform ss) on rural Roads Request for Bids - NG-EKITI RAAMP-336060-CW Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-05-0 -RFB / Physical improvement IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 2,000,000.00 0.00 2023-07-21 2023-07-26 2023-09-06 2023-10-06 2023-11-10 nvelope (1 envelope proce lementation 8 of Agro logistics centres ance Enhancement and Sect ss) or Reform Request for Bids - NG-EKITI RAAMP-331058-CW Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-07-0 -RFB / Construction of Backl IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 4,000,000.00 0.00 2023-09-13 2023-09-23 2023-11-04 2023-12-04 2024-01-08 nvelope (1 envelope proce lementation 6 og Maintenance/rehabilitatio ance Enhancement and Sect ss) n of Roads or Reform NG-EKITI RAAMP-331059-CW Request for Bids - -RFB / Spot Improvement of Component A. Improvement Single Stage - One E Small Works SPD Pending Imp 2024-06-2 Rural Roads and Constructio IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 7,875,000.00 0.00 2023-09-05 2023-09-10 2023-10-22 2023-11-21 2023-12-26 nvelope (1 envelope proce lementation 3 n of linear meters Cross Drai Infrastructure ss) nage Structures on Rural Roa ds GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EKITI RAAMP-331062-GO Component B. Asset Manage Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of 2Nos IDA / 65190 ment, Agro-logistics Perform Post Limited 170,000.00 0.00 2023-02-27 2023-04-24 2023-10-21 tions nvelope ementation Operating Project Vehicle ance Enhancement and Sect or Reform NG-EKITI RAAMP-331084-GO -RFQ / Procurement of Lapto ps, Desktops, Printers/Fax, U Component C. Institutional D Request for Quota Single Stage - One E Under Imple PS and peripherals, Heavy du IDA / 65190 evelopment, Project Manage Post Limited 80,000.00 0.00 2023-01-30 2023-03-27 2023-09-23 tions nvelope mentation ty photocopiers,scanners, pr ment and Risk Mitigation ojectors,internet installation, Video Camera, photo Printer, consumables etc NG-EKITI RAAMP-331151-GO Component C. Institutional D Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of a 30K IDA / 65190 evelopment, Project Manage Post Limited 40,000.00 0.00 2023-04-08 2023-06-03 2023-11-30 tions nvelope ementation VA Generator ment and Risk Mitigation NG-EKITI RAAMP-331245-GO Component C. Institutional D Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of Data C IDA / 65190 evelopment, Project Manage Post Limited 10,000.00 0.00 2023-03-11 2023-05-06 2023-11-02 tions nvelope ementation ollection Gadgets for NIRTIM ment and Risk Mitigation S and CoSMos NG-EKITI RAAMP-332720-GO -RFQ / Procurement of Safeg uard equipment(PPEs, First ai Component C. Institutional D Request for Quota Single Stage - One E Pending Impl d kits, Environmental Monitor IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-03-13 2023-05-08 2023-11-04 tions nvelope ementation ing and tracking Equipment, i ment and Risk Mitigation n-situ air quality kits, noise m eter, Ph meter, Caution tapes , Measuring tapes etc NG-EKITI RAAMP-331080-GO -RFQ / Procurement of Office Component C. Institutional D Request for Quota Single Stage - One E Pending Impl Furniture and Equipment, Shr IDA / 65190 evelopment, Project Manage Post Limited 50,000.00 0.00 2023-03-01 2023-04-26 2023-10-23 tions nvelope ementation edder Machines, Licence Soft ment and Risk Mitigation ware and Official Website NG-EKITI RAAMP-366086-GO Component C. Institutional D Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of Promo IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-07-28 2023-09-22 2024-03-20 tions nvelope ementation tional Materials ment and Risk Mitigation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EKITI RAAMP-330902-CS- CQS / Consultancy Services f Component B. Asset Manage or design and Supervision of ment, Agro-logistics Perform Consultant Qualifi Under Implement IDA / 65190 Post Open - National 300,000.00 0.00 2023-03-06 2023-03-22 2023-03-27 2023-05-10 2023-06-09 2023-07-14 2024-01-10 Rural Roads Spot Improveme ance Enhancement and Sect cation Selection ation nt and Construction of Linea or Reform r meters Cross Drainage Stru ctures on Rural Roads Page 1 NG-EKITI RAAMP-330921-CS- QCBS / Consultancy Service f Component A. Improvement Quality And Cost- Under Implement or Design and Supervision of IDA / 65190 of Rural Access and Trading Post Open - National 400,000.00 0.00 2023-02-13 2023-03-22 2023-03-06 2023-04-19 2023-05-17 2023-06-16 2023-07-21 2023-08-25 2024-08-24 Based Selection ation 2-3Nos Agro-Logistics centre Infrastructure s Physical improvement NG-EKITI RAAMP-330811-CS- Component A. Improvement QCBS / Consultancy service f Quality And Cost- Open - Internationa Under Implement IDA / 65190 of Rural Access and Trading Post 450,000.00 0.00 2023-01-30 2023-03-22 2023-02-20 2023-04-05 2023-05-03 2023-06-02 2023-07-07 2023-08-11 2024-08-10 or the design and Supervisio Based Selection l ation Infrastructure n of Road upgrading NG-EKITI RAAMP-336058-CS- Component B. Asset Manage CQS / Consultancy Service fo ment, Agro-logistics Perform Consultant Qualifi Under Implement IDA / 65190 Post Open - National 300,000.00 0.00 2023-04-17 2023-03-22 2023-05-08 2023-04-27 2023-06-21 2023-07-21 2023-08-25 2024-02-21 r Design and Supervision of ance Enhancement and Sect cation Selection ation Rural Roads Backlog Mainten or Reform ance/Rehabilitation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-EKITI RAAMP-331054-CS- Component C. Institutional D Individual Consult Under Implement INDV / Consultancy Service f IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-02-13 2023-03-08 2023-02-18 2023-03-11 2023-04-15 2024-04-14 ant Selection ation or the engagement of a Secu ment and Risk Mitigation rity Specialist NG-EKITI RAAMP-331055-CS- Component C. Institutional D INDV / Consultancy Services f Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-06-14 2023-06-19 2023-07-10 2023-08-14 2024-02-10 or the Engagement of a Geog ant Selection ntation ment and Risk Mitigation raphic Information System S pecialist NG-EKITI RAAMP-331053-CS- Component C. Institutional D INDV / Consultancy Services f Individual Consult Under Implement IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-04-04 2023-04-09 2023-04-30 2023-06-04 2024-05-13 or the Engagement of an Infr ant Selection ation ment and Risk Mitigation astructure Engineering Speci alist NG-EKITI RAAMP-361869-CS- Component C. Institutional D INDV / Consultancy Service f Individual Consult Under Implement IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-06-19 2023-06-24 2023-07-15 2023-08-19 2024-02-15 or the Engagement of a Tec ant Selection ation ment and Risk Mitigation hnical Assistance(TA) for Envi ronmental Safeguard NG-EKITI RAAMP-366291-CS- Component C. Institutional D INDV / Consultancy Service f Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-07-28 2023-08-02 2023-08-23 2023-09-27 2024-03-25 or the Engagement of a Proc ant Selection ntation ment and Risk Mitigation urement (TA)Specialist NG-EKITI RAAMP-366466-CS- Component C. Institutional D INDV / Consultancy Service f Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-08-03 2023-08-08 2023-08-29 2023-10-03 2024-03-31 or the Engagement of a Soci ant Selection ntation ment and Risk Mitigation al Safeguard (TA)Specialist NG-EKITI RAAMP-331056-CS- Component C. Institutional D Individual Consult Pending Impleme INDV / Consultancy Services f IDA / 65190 evelopment, Project Manage Post Limited 20,000.00 0.00 2023-10-19 2023-10-24 2023-11-14 2023-12-19 2024-06-16 ant Selection ntation or the engagement of a Data ment and Risk Mitigation Entry Specialist Page 2 PROCUREMENT PLAN (Textual Part) Project information: Country: Bolivia Project name: Bolivia Urban Resilience Project P-number: P165861 Project Implementation Agencies: Municipality of Santa Cruz (GAMSC) and Municipality of La Paz (GAMLP) Date of the Procurement Plan: September 09, 2021 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, dated July 2016, revised November 2017 and August 2018” (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures acceptable for the Bank by the may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not Applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations may be Applicable. Other Relevant Procurement Information. Procurement activities will be undertaken by GAMSC for Part 1 and 3.1; and by the GAMLP for Parts 2 and 3.2. Procurement of Goods, Works and Non-Consulting Services. According the Project Procurement Strategy for Development (PPSD), the open international competitive bidding approach should be applied when the Procurement Plan establishes it, while for small contracts the open national competitive bidding approach is supported by the availability of bidders in the local market. For Works and Gods the Borrower is able to specify detailed requirements to which bidders respond by offering bids; the Request for Bids or the Request for Quotations would be the selection methods for these contracts. Procurement of Consulting Services. Technical Assistance, designs, supervision services, and other studies: Considering that these will be small and medium magnitude contracts, the suitable market approach would be an open competition in the international or national market or direct market approach, while the Quality-Cost- Based Selection or Direct Selection (when a sole firm with needed capabilities is identified and justified) would be the selection methods. Project implementation support personnel. Individuals contracted to support project implementation (project staff), other than individual consulting positions identified in the Legal Agreement, may be selected by the Borrower according to their personnel hiring procedures for such activities, as reviewed and found acceptable by the Bank and described in the POMs. Individual consultants. Individual consultants will be selected for an assignment for which: (i) a team of experts is not required; (ii) no additional office support is required; and (iii) the experience and qualifications of the individual are of paramount requirement. The evaluation shall be based on the relevant qualifications and experience of the individual consultant in accordance with provision of paragraphs 7.34 to 7.39 of the Procurement Regulations. PROCUREMENT Bolivia : Bolivia Urban Resilience PLAN General Information Country: Bolivia 2021-09-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165861 GPN Date: 2021-08-12 Project Name: Bolivia Urban Resilience Loan / Credit No: IDA / 65170 Municipal Autonomous Government of Santa Cruz Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SMOP LPI 001 2021 / Obras Request for Bids - de construccion del canal em Resilient Infrastructure and Open - Internationa Single Stage - One E Small Works SPD 22,188,412.0 2024-10-0 isario 8vo Anillo suroeste y m IDA / 65170 Urban Upgrading in Santa Cr Prior Request for Bids 0.00 Canceled 2021-11-15 2021-11-20 2022-01-04 2022-02-03 2022-03-10 l nvelope (1 envelope proce 0 3 ejoramiento del espacio publi uz ss) co. Incluye salvaguardas soci ales y ambientales SMOP LPI 002-2022 / Constr Request for Bids - Resilient Infrastructure and ucción Canal Emisario 8vo An Open - Internationa Single Stage - One E Small Works SPD 23,294,667.3 2025-01-0 IDA / 65170 Urban Upgrading in Santa Cr Prior Request for Bids 0.00 Signed 2022-02-14 2022-04-08 2022-02-19 2022-06-03 2022-04-05 2022-06-13 2022-05-05 2022-10-13 2022-06-09 illo Sur Oeste y Mejoramiento l nvelope (1 envelope proce 4 2 uz de Espacio Público ss) National Procure SMOP UT COT 001/2022 / Ma ment Document - Request for Quota Single Stage - One E Under Imple 2022-12-2 ntenimiento de Espacio Públi IDA / 65170 Project Management Post Open - National 1 Envelope proce 120,000.00 0.00 2022-09-27 2022-11-22 tions nvelope mentation 2 co con Urbanismo Táctico en ss (Non Bank-SPD la Zona Central ) SES COT 001 2022 / Obras d Resilient Infrastructure and Request for Quota Request for Quota Single Stage - One E 2022-10-1 e Regeneracion Urbana. Pilot IDA / 65170 Urban Upgrading in Santa Cr Post Open - National tions (Non Bank-S 120,000.00 0.00 Canceled 2022-02-20 2022-04-17 tions nvelope 4 o de Urbanismo Tactico uz PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DPI COT 003 2021 / Utiles d Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 10,000.00 0.00 Canceled 2021-10-23 2021-12-18 2022-02-01 e escritorio tions nvelope DPI COT 002 2021 / Adquisic Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 16,961.00 0.00 Canceled 2021-10-23 2021-12-18 2022-02-01 ión de Muebles y Enseres tions nvelope DPI COT 001 2021 / Adquisci on de equipos de computacio Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 45,950.00 0.00 Canceled 2021-10-23 2021-12-23 2022-02-06 n, scanner, fotocopiadora, im tions nvelope presoras y proyectores DPI COT 002 2022 / Adquisic ión de: Computadoras de esc ritorio, Impresora de plotter, Single Stage - One E IDA / 65170 Project Management Post Request for Bids Open - National 82,492.71 0.00 Completed 2022-06-10 2022-07-13 2022-06-25 2022-07-13 2022-07-16 2022-08-11 2022-08-03 2022-08-29 2022-09-29 2022-10-29 2022-11-22 Computadoras portátiles, Pro nvelope yector multimedia, fotocopia doras, Impresoras de inyecci ón de tinta. DPI COT 001 2022 / Adquisic Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 32,912.39 0.00 Completed 2022-07-22 2022-09-22 2022-11-06 2022-12-12 ión de Equipos de Oficina y M tions nvelope uebles DPI COT 006 2021 / Adquisi Resilient Infrastructure and Request for Quota Single Stage - One E IDA / 65170 Post Open - National 10,500.00 0.00 Canceled 2021-11-27 2022-01-22 2022-03-08 cion de 1 Dron Urban Upgrading in Santa Cr tions nvelope uz DPI COT 004 2021 / Adquisic ion de Equipos de comunicac Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 2,620.00 0.00 Canceled 2021-10-30 2021-12-25 2022-02-08 ión, GPS, distanciador, radios tions nvelope walkie talkie, telefonos inala mbricos DPI SDO BS 001 2022 / Adqu isicion de Equipos de comuni Single Stage - One E IDA / 65170 Project Management Post Request for Bids Open - National 51,841.11 0.00 Completed 2022-08-15 2022-10-11 2022-08-30 2022-09-20 2022-11-10 2022-10-08 2022-11-06 2022-11-07 2022-12-07 2023-02-10 cación, Mobile phones, Digita nvelope l cameras, Televisions y Audi o visual technology DPI SDO BS 002 2022 / Adqu Single Stage - One E isiciones de Dos Vehiculos, u IDA / 65170 Project Management Post Request for Bids Open - National 66,427.76 0.00 Canceled 2022-09-05 2022-09-10 2022-10-01 2022-10-19 2022-11-17 2022-12-17 nvelope na camioneta y una camione ta DPI LPN 001 2021 / Adquisic Single Stage - One E ion de 2 Vehiculos 1 Vagonet IDA / 65170 Project Management Post Request for Bids Open - National 75,802.00 0.00 Canceled 2021-11-01 2021-11-06 2021-12-04 2022-01-03 2022-02-07 2022-03-24 nvelope a 4x4 y 1 Camioneta 4x4 DPI COT 003 2022 / Calzado Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 7,653.00 0.00 Canceled 2022-02-06 2022-04-08 2022-05-23 s tions nvelope DPI COT 002 2022 / Prendas Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 12,755.00 0.00 Canceled 2022-02-06 2022-04-03 2022-05-18 de vestir tions nvelope DPI-SD-001 / Adquisicion de Under Imple IDA / 65170 Project Management Post Direct Selection Direct - National 7,200.00 0.00 2022-12-19 2022-12-16 2022-12-24 2023-05-09 2023-01-28 2023-02-27 un Software Contable mentation DPI COT 003 2022 / ADQUISI Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 9,397.00 0.00 Canceled 2022-09-17 2022-11-12 2022-12-12 CIÓN DE UTILES DE ESCRITO tions nvelope RIO Y PAPEL DPI SDO BS 003 / Adquisició Single Stage - One E Pending Impl IDA / 65170 Project Management Post Request for Bids Open - National 182,653.00 0.00 2023-06-07 2023-06-12 2023-07-24 2023-08-23 2023-09-27 2023-11-26 n de (4) Cuatro Vehículos livi nvelope ementation anos DPI COT 005 / Adquisición d Request for Quota Single Stage - One E Pending Impl IDA / 65170 Project Management Post Open - National 19,000.00 0.00 2023-04-14 2023-06-22 2023-07-07 e Útiles de Escritorio y Papel tions nvelope ementation DPI COT 004 / Adquisición D Request for Quota Single Stage - One E Pending Impl e Prendas De Vestir y Calzad IDA / 65170 Project Management Post Open - National 4,500.00 0.00 2023-10-07 2023-12-16 2023-12-31 tions nvelope ementation os de seguridad Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DPI COT 005 2021 / Seguro Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 3,207.00 0.00 Canceled 2021-11-20 2022-01-15 2025-06-30 automotor tions nvelope DPI COT 001 2022 / Publicid Request for Quota Single Stage - One E IDA / 65170 Project Management Post Open - National 14,577.00 0.00 Canceled 2022-02-06 2022-04-03 2025-06-30 ad tions nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SMOP CONS 002 2021 / Serv Resilient Infrastructure and icios Consultoria especializad Quality And Cost- IDA / 65170 Urban Upgrading in Santa Cr Post Open - National 174,710.00 0.00 Canceled 2021-11-15 2021-12-06 2022-01-19 2022-02-16 2022-03-18 2022-04-22 2022-05-27 2024-09-30 a fiscalizacion de obras Sec. Based Selection uz Mcpal. Obras Publicas SMOP CONS 001 2021 / Serv icios Consultoría especializad a en Supervisión de las Obra Resilient Infrastructure and Quality And Cost- Open - Internationa s Civiles Ambientales y Social IDA / 65170 Urban Upgrading in Santa Cr Post 926,023.00 0.00 Canceled 2021-11-01 2021-11-11 2021-11-22 2022-01-05 2022-02-19 2022-03-21 2022-04-25 2022-05-30 2024-10-17 Based Selection l es. uz Obras de Construcción del Ca nal Emisario 8vo. Anillo sur-o este y mejoramiento del esp acio público SMOP LPI 001-2022 / Servici os Consultoría especializada para Supervisión de las Obra Resilient Infrastructure and Quality And Cost- Open - Internationa s Civiles, Ambientales y Soci IDA / 65170 Urban Upgrading in Santa Cr Post 722,568.75 0.00 Signed 2022-02-08 2022-02-10 2022-03-01 2022-03-28 2022-04-14 2022-06-06 2022-05-12 2022-07-20 2022-06-11 2022-08-31 2022-07-16 2022-09-30 2022-08-20 2023-08-20 Based Selection l ales. Construcción del Canal uz Emisario 8vo. Anillo sur-oeste y mejoramiento del espacio p úblico DPI CP 002 2022 / Consultorí a por producto para la elabor ación a diseño final del estud Quality And Cost- IDA / 65170 Project Management Post Open - National 150,000.00 0.00 Canceled 2022-09-26 2022-12-13 2022-10-17 2022-11-30 2022-12-28 2023-01-27 2023-03-03 2023-04-07 2024-04-06 io de Diseño Técnico de Prein Based Selection versión del proyecto Constru cción de Obra de Regeneraci ón Urbana Zona Central DPI CP 001 2022 / Consultorí a por producto para la elabor ación del Plan Integral de Ma Quality And Cost- Open - Internationa nejo de Parques Urbanos - PE IDA / 65170 Project Management Post 200,000.00 0.00 Canceled 2022-08-31 2022-12-13 2022-09-21 2022-11-04 2022-12-16 2023-01-15 2023-02-19 2023-03-26 2024-03-25 Based Selection l M: Proyecto del Parque Lineal Ecológico Metropolitano de S anta Cruz y su Plan Integral d e Manejo SMTT CP 001-2022 / Consult oría para la elaboración del P Quality And Cost- Open - Internationa Under Implement lan Maestro de Transporte N IDA / 65170 Project Management Post 500,000.00 0.00 2022-09-28 2022-12-29 2022-10-19 2023-01-24 2022-11-19 2023-03-30 2022-12-30 2023-05-25 2023-01-20 2023-02-24 2023-03-31 2024-03-30 Based Selection l ation o Motorizado y Proyecto de la Red de Ciclovías Ecológicas, Sustentables y Resilientes DPI SCC 001 / Consultoría pa Consultant Qualifi Under Implement ra el diseño e implementació IDA / 65170 Project Management Post Limited 58,000.00 0.00 2022-11-30 2022-12-01 2022-12-14 2022-12-21 2023-01-13 2023-02-11 2023-05-12 cation Selection ation n de Estrategia Comunicacio nal DPI CONS 002 / Consultoria para la Elaboracion del Plan I Quality And Cost- Open - Internationa Under Implement ntegral de Manejo de Parque IDA / 65170 Project Management Post 200,000.00 0.00 2023-01-10 2023-01-18 2023-01-31 2023-02-24 2023-03-16 2023-04-30 2023-05-30 2023-07-04 2023-08-08 2024-08-02 Based Selection l ation s Urbanos - PEM, Direccion d e Planificacion Integral, SEMP LAD DPI CONS 004 / Servicio de c onsultoría para auditoría fina nciera por el periodo compre Least Cost Selecti Under Implement ndido entre el 10 de marzo al IDA / 65170 Project Management Post Open - National 100,000.00 0.00 2023-03-27 2023-03-27 2023-03-27 2023-04-04 2023-05-17 2023-06-06 2023-07-10 2023-08-10 2024-02-26 on ation 31 de diciembre del 2021; 1º de enero al 31 de diciembre de 2022 y 1º de enero al 31 de diciembre de 2023 DPI CONS 001 2022 / Audito Least Cost Selecti IDA / 65170 Project Management Post Open - National 100,000.00 0.00 Canceled 2022-12-15 2022-09-12 2023-01-05 2023-02-18 2023-03-18 2023-04-17 2023-05-22 2023-06-26 2023-12-23 ria Externa Gestiones 2021 - on 2022 DPI CONS 003 / Consultoria para la Elaboracion de diseño final de Estudio Diseño Técni Quality And Cost- co de Preinversión del proyec IDA / 65170 Project Management Post Open - National 150,000.00 0.00 Under Review 2023-06-02 2023-06-27 2023-06-23 2023-08-06 2023-09-17 2023-10-17 2023-11-21 2023-12-26 2024-03-25 Based Selection to Construccion de la Obra R egeneracion Urbana Zona Ce ntral, Direccion de Planificaci on Integral, SEMPLAD INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DPI CI 001 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Social ant Selection DPI CI 002 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Ambiental ant Selection DPI CI 003 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a en Monitoreo ant Selection DPI CI 004 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Financiero ant Selection DPI CI 005 2021 / Especialist Individual Consult IDA / 65170 Project Management Prior Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-20 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a en Adquisiciones ant Selection Page 2 DPI CI 006 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Legal ant Selection DPI CI 007 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Comunicador ant Selection DPI CI 008 2021 / Especialist Individual Consult IDA / 65170 Project Management Post Open 116,790.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 a Infraestructura Resiliente ant Selection DPI CI 009 2021 / Profesiona Individual Consult IDA / 65170 Project Management Post Open 63,289.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 l A Asistente Administrativo ant Selection Individual Consult DPI CI 010 2021 / Chofer A IDA / 65170 Project Management Post Open 37,854.00 0.00 Canceled 2021-10-01 2021-09-15 2021-11-19 2021-12-10 2022-01-14 2025-06-30 ant Selection DPI CI 001 2022 / Profesiona Individual Consult IDA / 65170 Project Management Post Open 63,289.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l A Contador Auditor Analista ant Selection Contable DPI CI 002 2022 / Profesiona Individual Consult IDA / 65170 Project Management Post Open 63,289.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l A Analista Presupuestario ant Selection DPI CI 003 2022 / Profesiona Individual Consult IDA / 65170 Project Management Prior Open 63,289.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l A Analista en Adquisiciones ant Selection 1 DPI CI 004 2022 / Profesiona Individual Consult IDA / 65170 Project Management Post Open 57,149.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 l B Asistente Legal ant Selection DPI CI 005 2022 / Asistente Individual Consult IDA / 65170 Project Management Post Open 51,464.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 A en Archivo ant Selection Individual Consult DPI CI 006 2022 / Chofer A IDA / 65170 Project Management Post Open 37,854.00 0.00 Canceled 2022-02-01 2022-03-22 2022-04-12 2022-05-17 2025-06-30 ant Selection SMOP CI 001-2022 / Fiscal d Resilient Infrastructure and Individual Consult e Obra para el canal emisario IDA / 65170 Urban Upgrading in Santa Cr Post Open 45,450.44 0.00 Signed 2022-02-08 2022-10-24 2022-03-29 2022-10-26 2022-04-19 2022-11-30 2022-05-24 2022-11-20 ant Selection 8vo. Anillo sur-oeste uz SMOP CI 002-2022 / Fiscal A Resilient Infrastructure and Individual Consult mbiental para el canal emisa IDA / 65170 Urban Upgrading in Santa Cr Post Open 45,450.44 0.00 Signed 2022-02-08 2022-10-24 2022-03-29 2022-10-26 2022-04-19 2022-11-09 2022-05-24 2022-11-20 ant Selection rio 8vo. Anillo sur-oeste uz SMOP CI 003-2022 / Fiscal S Resilient Infrastructure and Individual Consult ocial para el canal emisario 8 IDA / 65170 Urban Upgrading in Santa Cr Post Open 45,450.44 0.00 Signed 2022-02-08 2022-10-24 2022-03-29 2022-10-26 2022-04-19 2022-11-30 2022-05-24 2022-11-20 ant Selection vo. Anillo sur-oeste uz DPI CI 008-2022 / Consultor Individual Consult de línea Especialista en Infra IDA / 65170 Project Management Post Open 116,790.00 16,573.91 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-15 2025-11-10 ant Selection estructura Resiliente DPI CI 005-2022 / Consultor Individual Consult IDA / 65170 Project Management Prior Open 116,790.00 0.00 Signed 2022-02-11 2022-02-14 2022-04-01 2022-03-13 2022-04-22 2022-12-09 2022-05-27 2025-11-10 de línea Especialista en Adqu ant Selection isiciones DPI CI 001-2022 / Consultor Individual Consult de línea Especialista en Salva IDA / 65170 Project Management Post Open 116,790.00 16,573.91 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 ant Selection guarda Social DPI CI 004-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 116,790.00 16,549.83 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 de línea Especialista Financie ant Selection ro DPI CI 007-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 116,790.00 16,573.91 Completed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 2023-01-14 de línea Especialista Comuni ant Selection cador DPI CI 006-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 116,790.00 16,573.91 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 de línea Especialista Legal ant Selection DPI CI 003-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 116,790.00 16,549.83 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 de línea Especialista en Moni ant Selection toreo DPI CI 014-2022 / Consultor Individual Consult Under Implement IDA / 65170 Project Management Post Open 37,854.00 0.00 2022-02-11 2023-06-08 2022-06-17 2022-07-08 2022-08-12 2026-01-26 de línea Chofer A ant Selection ation DPI CI 002-2022 / Consultor Individual Consult de línea Especialista en Salva IDA / 65170 Project Management Post Open 116,790.00 16,549.83 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 ant Selection guarda Ambiental DPI CI 009-2022 / Consultor Individual Consult de línea Profesional A – Asist IDA / 65170 Project Management Post Open 63,288.00 8,994.49 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-11-10 ant Selection ente Administrativo DPI CI 010-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 63,288.00 8,968.37 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-07-10 de línea Profesional A - Analis ant Selection ta Contable DPI CI 011-2022 / Consultor Individual Consult de línea Profesional A - Analis IDA / 65170 Project Management Post Open 63,288.00 8,981.41 Completed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-04 2022-05-27 2022-04-24 2025-07-10 2022-09-08 ant Selection ta Presupuestario DPI CI 012-2022 / Consultor Individual Consult de línea Profesional A - Analis IDA / 65170 Project Management Post Open 63,288.00 8,968.37 Completed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-07 2022-05-27 2022-04-24 2025-07-10 ant Selection ta de Procesos de Adquisicio nes DPI CI 013-2022 / Consultor Individual Consult IDA / 65170 Project Management Post Open 57,149.00 8,110.08 Signed 2022-02-11 2022-02-11 2022-04-01 2022-04-01 2022-04-22 2022-04-05 2022-05-27 2022-04-24 2025-07-10 de línea Profesional B – Técni ant Selection co Legal SES CI 002 2022 / Consultor Resilient Infrastructure and especialista Fiscal de Obras d Individual Consult IDA / 65170 Urban Upgrading in Santa Cr Post Open 10,700.00 0.00 Canceled 2022-02-07 2022-03-28 2022-04-18 2022-05-23 2022-11-19 e Regeneracion Urbana. Pilot ant Selection uz o de Urbanismo Tactico SMOP UT CI 002-2022 / Cons ultor de linea Fiscal de Obra Individual Consult Under Implement IDA / 65170 Project Management Post Open - National 6,060.06 0.00 2022-09-22 2023-05-10 2022-11-05 2022-11-26 2022-12-27 2023-06-25 para el Mantenimiento de Es ant Selection ation pacio Público con Urbanismo Táctico Zona Central Page 3 SMOP UT CI 001-2022 / Cons ultor de linea Supervisor de o Individual Consult Under Implement bra para el Mantenimiento d IDA / 65170 Project Management Post Open - National 6,060.06 0.00 2022-09-22 2023-05-10 2022-11-05 2022-11-26 2022-12-27 2023-06-25 ant Selection ation e Espacio Público con Urbani smo Táctico Zona Central SES CI 001 2022 / Consultor especialista Supervisor de la Individual Consult IDA / 65170 Project Management Post Open 10,700.00 0.00 Canceled 2022-02-07 2022-03-28 2022-04-18 2022-05-23 2022-11-19 Obras de Regeneracion Urba ant Selection na. Piloto de Urbanismo Tacti co SMOP UT CP 001-2022 / Con sultor por producto para la cr eación de trabajos de pintura Under Implement IDA / 65170 Project Management Post Direct Selection Direct - National 9,475.22 0.00 2022-09-22 2022-10-10 2022-10-02 2023-05-31 2022-12-06 2023-03-06 mural para el Mantenimiento ation de Espacio Público con Urban ismo Táctico Zona Central pa ra la Pascana de la Recova SMOP UT CP 002 2022 / Con sultor por producto para la cr eación de trabajos de pintura Under Implement IDA / 65170 Project Management Post Direct Selection Direct - National 2,478.13 0.00 2022-09-22 2022-08-19 2022-10-02 2023-05-31 2022-12-06 2023-03-06 mural para el Mantenimiento ation de Espacio Público con Urban ismo Táctico Zona Central pa ra la Zona Hospitalaria SMOP UT CP 003 2022 / Con sultor por producto para la cr eación de trabajos de pintura Under Implement IDA / 65170 Project Management Post Direct Selection Direct - National 947.52 0.00 2022-09-01 2023-05-10 2022-09-11 2023-05-31 2022-11-15 2023-05-14 mural para el Mantenimiento ation de Espacio Público con Urban ismo Táctico Zona Central pa ra el Rincon de la Cruz DPI CI 015 / Consultor de Lin Individual Consult Under Implement IDA / 65170 Project Management Post Open - National 31,645.00 0.00 2023-04-10 2023-05-19 2023-05-23 2023-06-13 2023-07-08 2025-06-13 ea Profesional A - Analista Pr ant Selection ation esupuestario DPI CI 016 / Consultor de Lin Individual Consult Under Implement ea Profesional A - Analista de IDA / 65170 Project Management Post Open - National 31,645.00 0.00 2023-04-10 2023-05-19 2023-05-23 2023-06-13 2023-07-08 2025-06-13 ant Selection ation Procesos de Adquisiciones DPI CI 018 / Consultor de Lin Individual Consult Under Implement ea Profesional B - Personal d IDA / 65170 Project Management Post Open - National 28,575.00 0.00 2023-04-10 2023-05-19 2023-05-24 2023-06-07 2023-07-08 2025-06-13 ant Selection ation e Apoyo - Archivo DPI CI 017 / Consultor de Lin Resilient Infrastructure and Individual Consult IDA / 65170 Post Open - National 58,395.00 0.00 Under Review 2023-06-15 2023-06-27 2023-07-29 2023-08-12 2023-09-12 2025-06-30 ea Especialista Comunicador Urban Upgrading in Santa Cr ant Selection uz DPI CI 019 / Consultor de lín Individual Consult IDA / 65170 Project Management Post Open - National 58,395.00 0.00 Under Review 2023-06-15 2023-06-07 2023-07-28 2023-08-18 2023-09-12 2025-06-30 ea Especialista Legal ant Selection Page 4 PROCUREMENT PLAN Project information: Lebanon – Emergency Social Safety Net Project – P173367 Project Implementation agency: Presidency of Council of Ministers Date of the Procurement Plan: August 18th, 2021 Period covered by this Procurement Plan: August 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international and national competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Lebanon : LEBANON EMERGENCY CRISIS AND COVID-19 RESPONSE SOCIAL SAFETY NET PROJECT PLAN General Information Country: Lebanon 2021-08-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173367 GPN Date: 2021-10-28 Project Name: LEBANON EMERGENCY CRISIS AND COVID-19 RESPONSE SOCIAL SAFETY NET PROJECT Loan / Credit No: IBRD / 91980 Presidency of the Council of Ministers Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-PCM-277681-GO-RFQ / Pr ovision and Installation of Ha Enhanced Social Safety Nets Request for Quota Single Stage - One E IBRD / 91980 Post Open - National 0.00 Signed 2022-02-16 2022-04-13 2022-10-10 rdware for ID Cards Departm Program Delivery tions nvelope ent for the Ministry of Interior and Municipalities LB-PCM-292749-GO-RFQ / Pr ovision and Installation of Ha Enhanced Social Safety Nets Request for Quota Single Stage - One E IBRD / 91980 Post Open - National 0.00 Signed 2022-05-03 2022-06-28 2022-12-25 rdware and Software for the Program Delivery tions nvelope Ministry of Education and Hig her Education LB-PCM-292755-GO-RFQ / Pr Enhanced Social Safety Nets Request for Quota Single Stage - One E ovision and Installation of IT IBRD / 91980 Post Open - National 0.00 Completed 2022-05-03 2022-06-28 2022-12-25 2022-08-12 Program Delivery tions nvelope equipment for the Central Ma nagement Unit LB-PCM-364780-GO-RFQ / Pr Enhanced Social Safety Nets Request for Quota Single Stage - One E Under Imple ovision and Installation of IT IBRD / 91980 Post Open - National 0.00 2023-06-11 2023-08-06 2024-02-02 Program Delivery tions nvelope mentation equipment for the Ministry of Social Affairs NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-PCM-248944-NC-DIR / Ver Enhanced Social Safety Nets IBRD / 91980 Prior Direct Selection Direct 3,787,416.00 Signed 2021-08-18 2021-08-23 2021-08-23 2021-08-30 2021-09-27 2021-12-16 2022-03-26 ification of Household Program Delivery LB-PCM-259665-NC-DIR / Pro Provision of Cash Transfer fo vision of cash transfer for ho IBRD / 91980 Prior Direct Selection Direct 241,491,025.00 Signed 2021-10-25 2021-11-11 2021-10-30 2021-11-29 2021-12-04 2022-03-21 2022-06-02 r Basic Income Support me basic income support and students at risk CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-PCM-251364-CS-QCBS / T Enhanced Social Safety Nets Quality And Cost- Open - Internationa IBRD / 91980 Prior 0.00 Canceled 2021-09-01 2021-09-05 2021-09-22 2021-11-05 2021-12-03 2022-01-02 2022-02-06 2022-03-13 2023-03-13 hird Party Monitoring Agent Program Delivery Based Selection l LB-PCM-259792-CS-CQS / Th Enhanced Social Safety Nets Consultant Qualifi Open - Internationa IBRD / 91980 Prior 0.00 Canceled 2021-10-26 2021-10-26 2021-11-16 2021-11-11 2021-12-30 2022-02-22 2022-01-29 2022-03-05 2022-09-01 ird Party Monitoring Agent (T Program Delivery cation Selection l PMA) LB-PCM-309236-CS-CQS / Ex ternal Auditor for Lebanon E Enhanced Social Safety Nets Consultant Qualifi Under Implement IBRD / 91980 Post Open - National 0.00 2022-10-04 2022-11-01 2022-10-25 2022-12-16 2022-12-08 2023-01-07 2023-02-11 2023-08-10 mergency Crisis and COVID-1 Program Delivery cation Selection ation 9 Response Social Safety Net Project LB-PCM-295749-CS-QCBS / T Enhanced Social Safety Nets Quality And Cost- Open - Internationa Under Implement IBRD / 91980 Prior 0.00 2021-09-01 2022-12-07 2021-09-22 2021-11-05 2023-03-27 2021-12-03 2022-01-02 2022-02-06 2022-03-13 2023-03-13 hird-Party Monitoring Agent Program Delivery Based Selection l ation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LB-PCM-251006-CS-CDS / Ad Enhanced Social Safety Nets Under Implement ministration and Operation of IBRD / 91980 Post Direct Selection Direct 0.00 2021-08-30 2021-09-03 2021-09-09 2021-11-13 2022-05-12 Program Delivery ation Ration Card Call Center LB-PCM-251004-CS-CDS / De Enhanced Social Safety Nets velopment and Management IBRD / 91980 Prior Direct Selection Direct 783,010.00 Signed 2021-08-30 2021-10-17 2021-09-09 2021-10-20 2021-11-13 2021-12-11 2022-05-12 Program Delivery of Intake and Registration Pla tform Enhanced Social Safety Nets IC001 / Procurement Officer IBRD / 91980 Post Direct Selection Direct 36,600.00 Signed 2021-10-25 2021-10-25 2021-10-25 2021-10-25 2021-10-25 2021-11-04 2022-10-31 Program Delivery Enhanced Social Safety Nets Individual Consult IC002 / Financial Officer IBRD / 91980 Post Open 36,000.00 Signed 2021-11-26 2021-11-29 2022-01-14 2022-03-07 2022-02-04 2022-03-07 2022-03-11 2022-03-20 2022-09-07 Program Delivery ant Selection IC005 / MOSA ESSN Coordin Enhanced Social Safety Nets Individual Consult IBRD / 91980 Post Open 0.00 Canceled 2022-01-07 2022-02-25 2022-03-18 2022-04-22 2022-10-19 ator Program Delivery ant Selection LB-PCM-270451-CS-CDS / Pr Enhanced Social Safety Nets IBRD / 91980 Post Direct Selection Direct 107,637.60 Signed 2022-01-07 2021-12-21 2022-01-17 2021-12-22 2022-03-23 2022-04-22 2022-09-19 ovision of Information Securit Program Delivery y Services Enhanced Social Safety Nets Individual Consult IC004 / Project Director IBRD / 91980 Post Direct 48,000.00 Signed 2021-12-22 2021-11-30 2022-01-01 2021-11-30 2022-01-22 2021-12-01 2022-02-26 2021-12-13 2022-08-25 Program Delivery ant Selection Page 1 IC003 / Social Safeguards Of Enhanced Social Safety Nets Individual Consult IBRD / 91980 Post Open 30,000.00 Signed 2021-12-22 2022-01-10 2022-02-09 2022-03-04 2022-03-02 2022-03-07 2022-04-06 2022-03-20 2022-10-03 ficer-Full time Program Delivery ant Selection IC006 / Monitoring and Evalu Enhanced Social Safety Nets Individual Consult Under Implement IBRD / 91980 Post Open 0.00 2022-01-19 2022-01-19 2022-03-09 2022-03-30 2022-05-04 2022-10-31 ation Officer Program Delivery ant Selection ation IC007 / Focal Point/Monitorin Enhanced Social Safety Nets Individual Consult g and Evaluation Officer-Mini IBRD / 91980 Post Open 0.00 Canceled 2022-04-14 2022-04-27 2022-06-02 2022-06-23 2022-07-28 2023-01-24 Program Delivery ant Selection stry of Education and Higher Education IC008 / Focal Point/Monitorin g and Evaluation Officer und Enhanced Social Safety Nets Individual Consult IBRD / 91980 Post Limited 0.00 Signed 2022-10-04 2022-08-19 2022-10-09 2022-09-21 2022-10-30 2022-10-03 2022-12-04 2023-06-02 er the Ministry of Education a Program Delivery ant Selection nd Higher Education IC010 / Junior Software Deve Enhanced Social Safety Nets Individual Consult Pending Impleme loper-The Ministry of Educati IBRD / 91980 Post Limited 0.00 2022-10-04 2022-10-09 2022-10-30 2022-12-04 2023-06-02 Program Delivery ant Selection ntation on and Higher Education IC009 / Senior Software Dev Enhanced Social Safety Nets Individual Consult eloper-The Ministry of Educat IBRD / 91980 Post Limited 0.00 Canceled 2022-10-04 2022-10-09 2022-10-30 2022-12-04 2023-06-02 Program Delivery ant Selection ion and Higher Education IC012 / Senior Software Dev Contingent Emergency Resp Individual Consult Under Implement eloper for the Ministry of Edu IBRD / 91980 Post Open - National 0.00 2022-11-09 2022-11-17 2022-12-28 2023-01-18 2023-02-22 2023-08-21 onse Component (CERC) ant Selection ation cation and Higher Education IC011 / Database Admin-The Enhanced Social Safety Nets Individual Consult Under Implement Ministry of Education and Hig IBRD / 91980 Post Open - National 0.00 2022-11-17 2022-11-21 2023-01-05 2023-01-26 2023-03-02 2023-08-29 Program Delivery ant Selection ation her Education IC013 / ESSN Coordinator-Mi Contingent Emergency Resp Individual Consult IBRD / 91980 Post Limited 0.00 Signed 2022-11-17 2022-12-07 2022-11-22 2023-03-20 2022-12-13 2023-04-12 2023-01-17 2023-07-16 nistry of Social Affairs onse Component (CERC) ant Selection IC014 / MOSA Communicatio Enhanced Social Safety Nets Individual Consult IBRD / 91980 Post Direct - National 0.00 Signed 2022-12-07 2022-12-09 2022-12-17 2022-12-15 2023-01-07 2022-12-15 2023-02-11 2023-08-10 ns Officer Program Delivery ant Selection Page 2 Plan de Passation de marchés I. Généralités 1. L'information sur le projet : Pays : Madagascar ; Emprunteur : République de Madagascar ; Nom de projet : Deuxième Projet de Gouvernance des Pêches et de Croissance Partagée du Sud-ouest de l’Océan Indien (SWIOFish2) Numéro du Crédit : P153370 Agence d’exécution du Projet : 2. Date d’approbation du Plan de passation de marchés par la Banque : 01 Février 2018 ; Révision : 09 Août 2018 ; 3. Date de notification du Plan Général de Passation de marchés : - ; 4. Période couverte par le Plan de Passation de marchés : Année 2018 II. Biens et Travaux et Services hors consultants 1. Seuil de Revue préalable : Les décisions de passation de marchés sujet aux revues préalables de la Banque comme indiqué dans le paragraphe 3.1 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) et sur la base de l'évaluation de la capacité de l'agence d’exécution : Méthode de Passation de Seuil de revue Commentaires marchés à priori 1. AOI – Ouvert ou Restreint (Biens) 2 000 000 Les montants 2. AON (Biens) 2 000 000 estimatifs des 3. AOI (Travaux) 10 000 000 marchés prévus 4. AON (Travaux) 10 000 000 sont au-dessous 5. AOI (Services) 2 000 000 des seuils. 6. UN -UNOPS (Biens) 2 000 000 Niveau de risque : 7. ED (Biens/Travaux) 2 000 000 « SUBSTANTIEL » 2. Pré-qualification (selon les dispositions des paragraphes 6.19 à 6.24 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable. 3. Procédures proposées pour les composantes CDD (selon le paragraphe. 6.52 et 6.53 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable 4. Référence (s’il y en a) au Manuel d’exécution du projet / Manuel de Passation de marchés : Non Applicable 5. Tout autre arrangement spécial en passation de marchés : Non Applicable. 6. Allotissement de fournitures avec méthodes et calendrier : [Enumérer d’abord les allotissements qui nécessitent la revue préalable de la Banque, ensuite les autres allotissements] 1 2 3 4 5 6 7 8 9 Réf. Description Contrat Coût Approche/Méth Pré- Préféren Revue de la Date Commentair No estimatif ode de qualificati ce Banque (à prévue es sélection on national priori / à d’ouverture Oui / Non e posteriori) des Oui / Non soumission s MG- Matériels roulants (46Voitures : PM 1DSP – 2CEDP – 3SG – 3DGRHP 3 070 000 UNOPS Non Non Oui 01/07/2018 01/1 – 3RGPDD – 4ASH – 1USTA – 8 5CSP – 22 DRRHP – 2UGP) MG- PM Matériels roulants (20motos ; Non Non 59 000 UNOPS Non 01/07/2018 02/1 2USTA – 16UGL – 2UGP) 8 Matériels et équipement Informatiques (48 Ordinateurs de bureau – 45 Ordinateurs portables – 27 Onduleurs – Non Non Non MG- 4Stabilisateurs – 29Imprimantes PM AON/UNOP multifonctions – 52 Imprimantes 433 910 30/09/2018 03/1 S laser noir – 11Imprimantes laser 8 couleur – 29Photocopieuses – 10Vidéoprojecteurs – 10Appareils photo – 11GPS – 1Caméra – 32 Tablettes MG- PM Matériels et mobiliers de bureau Non Non Non 162 200 AON 30/09/2018 04/1 : 1DCI – 2USTA –8 UGL - 1UGP 8 MG- Commented [JM1]: 29 170 dans PPM d’aout PM Fournitures et articles de Non Non Non Commented [u2R2]: Omission de la ligne 47 170 DC 01/12/2018 05/1 bureau 4.1.3.2.1 de l’UGP d’un montant de 18.000USD 8 sur le PTBA 2018 MG- PM Non Non Non Consommables informatiques 73 170 DC 30/09/2018 06/1 8 MG- Kits d'équipements pour les PM enquêteurs (sac de couchage, Non Non Non 17 500 DC 15/10/2018 07/1 tente, torche, bottes, 8 imperméable) MG- Non Non Non Achat téléphone mobile pour la PM collecte de données au niveau 5 250 DC 01/12/2018 08/1 national 8 MG- Non Non Non Matériels d'échantillonnage PM (Blouse, gant, balance, pied a 1 000 DC 30/09/2018 09/1 coulisse…) 8 MG- Non Non Non Acquisition et installation d’un PM logiciel de suivi automatique 150 000 AON 01/12/2018 10/1 des captures (ERS); 8 MG- Non Non Non Dotation et moyens PM d'équipement pour les 48 000 DC 30/10/2018 11/1 membres du CSC 8 MG- Non Non Non PM Matériels de l'électrification 9 000 DC 30/10/2018 12/1 hors grille 8 MG- Non Non Non PM Equipements et outils de pêche 120 000 AON 01/10/2018 13/1 8 MG- Non Non Non Commented [JM3]: 115 000 dans PPM d’aout Outillage d'entretien d'engin et PM Commented [u4R4]: Après vérification du d'embarcation de pêche pour 60 000 AON 01/12/2018 14/1 PTBA Ligne 3.2.1.1.32 : il est prévu :12 lots à usage communautaire 8 5.000USD l’unité Appui à la mise à disposition Non Non Non MG- des équipements de base pour PM la sécurité des pêcheurs et de 165 000 AON 01/12/2018 15/1 leurs embarcations en mer 8 (gilet, miroir… pour la période transitoire) MG- Non Non Non PM Outils de valorisation 80 000 DC 01/12/2018 16/1 8 MG- Petits matériels de valorisation 80 000 DC Non Non Non 01/12/2018 PM 17/1 8 MG- Non Non Non Commented [JM5]: Combien de boites sont PM prévues ? Achat boites à plaintes 3 950 DC 30/09/2018 18/1 Commented [u6R6]: 79 boites à plaintes 8 suivant la ligne 3.2.3.4.4 du PTBA 2018 MG- Non Non Non PM Outillage pour les pépinières et 19 000 DC 01/12/2018 19/1 les reboisements (brouette,….) 8 MG- Non Non Non Renforcement de l'unité de PM gestion communautaire en 10 000 DC 01/12/2018 20/1 biens et équipements 8 MG- Acquisition, installation et test Non Non Non PM des biens et équipements 240 000 AON 01/12/2018 21/1 relatifs aux technologies hors 8 grille MG- Non Non Non PM Petit outillage et fournitures 417 DC 30/10/2018 22/1 d’atelier (unité) 8 MG- Non Non Non Construction des bureaux des 2 PM PIE de l'ASH en province : 60 000 DC 30/09/2018 23/1 Antsiranana et Morondava 8 Carénages du navire de Non Non Non MG- surveillance «Atsantsa », PM remplacement des appareils de 181 000 AON 30/08/2018 24/1 navigation/accessoires et pièces 8 de rechanges des moteurs auxiliaires MG- Non Non Non PM Carénage du navire de 76 000 DC 30/10/2018 25/1 surveillance "Telonify" 8 MG- Non Non Non PM Constructions pour les six (06) 420 000 AON 30/09/2018 26/1 DRRHP et huit (08) CIRRHP 8 MG- Non Non Non PM Construction de petits 350 000 AON 30/11/2018 27/1 débarcadères type ponton 8 Installation d'unités de Non Non Non fabriques de glace/chambres MG- froides fonctionnant avec des PM énergies renouvelables et 320 000 AON 30/11/2018 28/1 respectant l’environnement 8 pour maintenir la chaine de froid des produits halieutiques dès leur débarquement MG- Non Non Non PM Construction d'infrastructures 360 000 AON 01/12/2018 29/1 communautaires /communales 8 MG- Non Non Non Infrastructures d'électrification PM hors grille dans les 1 250 000 AON 01/12/2018 30/1 communautés pilotes 8 MG- Non Non Non PM Construction de bureau de 60 000 DC 30/07/2018 31/1 l'UGP centrale 8 7.858.197 TOTAL Biens – Equipements et Travaux III. Sélection de consultants 1. Seuil de Revue Préalable : Décisions de sélection sujet à la revue préalable de la Banque comme indiqué dans le paragraphe 3 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) : Méthode de sélection Seuil de Commentaires revue à priori 1. Méthode compétitive (firmes) 1 000 000 Les montants 2. Entente directe (firmes) 1 000 000 estimatifs des 3. Méthode compétitive (Consultant individuel) 300 000 contrats prévus sont 4. Entente directe (Consultant individuel) 300 000 au-dessous des seuils. Niveau de risque : « SUBSTANTIEL » 2. Liste restreinte composée entièrement de consultants nationaux : Liste restreinte de consultants pour prestations de services, estimés à moins de USD 150 000 par contrat, peut comporter entièrement des consultants nationaux selon les dispositions du paragraphe 7.25 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016). 3. Tout autre arrangement spécial de Sélection de consultants : Non applicable 4. Tâches de consultation avec des méthodes de sélection et calendrier Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Etude et analyse diagnostiques des MG-PM stratégies du secteur et des anciens 75 000 CI NON 01/05/2018 32/18 plans directeurs et élaboration du nouveau plan directeur Mise à jour de la Stratégie Nationale de MG-PM l’Aquaculture (Consultant national + 30 000 CI NON 30/08/2018 33/18 Réunions (1 consultation, 1 validation) Etude sur les procédures MG-PM administratives régissant l’accès aux 70 000 CI NON 30/07/2018 34/18 ressources et examen des options et recommandations (6 outils de gestion) Elaboration de la stratégie d'adaptation MG-PM du secteur pêche face au changement 10 000 CI NON 01/09/2018 35/18 climatique Amélioration de la base de données pour la déclaration des produits de la Commented [JM8]: Est-ce que l augmentation MG-PM pêche régionale (Base de données- 10 000 CI NON 30/08/2018 de 35 000 à 58 500 justifié par l’ajout de la 36/18 Tableau de bord-Système d'Information partie CFTP non prévue au PPM d’aout. Pêche : basé sur le Web, consultant) Commented [u9R9]: Faisant suite aux Amélioration de la base de données instructions de l’Equipe PPM de la BM, on a MG-PM pour les pêcheries industrielles 10 000 CI NON 30/09/2018 regroupée les études techniques et les études 37/18 Impacts pour l’OEPA régional et central – CFTP (consultant) Etude technique et étude d'impact et Enceinte Fénerive Est suivant les lignes du PTBA suivantes ; 2.1.2.3.6 – 2.1.2.3.7 – 2.1.2.5.2 environnemental et social de Etude groupée – 2.1.2.5.3 – 2.3.2.1.1 – 2.3.2.2.1.2 – 3.2.1.1.3 et MG-PM l'extension ou construction du bureau MG-PM 38-39-40- 3.2.1.1.4 58 500 SFQC NON 30/10/2018 92/18 régional et central de l’OEPA, de 41-55-56-62- réhabilitation du CFTP , Clôture de 63/18 Commented [JM7]: Est-ce que les études techniquesenv. Pour l’enceinte de la DRRHP de l’enceinte DRRHP Fenerive Fenerive ne pourrait pas être plutôt ajouter à la PA65 ? Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Elaboration stratégie nationale de MG-PM recherches halieutiques (1 Consultant 50 000 CI NON 30/07/2018 42/18 international et 3 consultants nationaux) MG-PM Etude sur les mesures de gestion des 30 000 CI NON 30/07/2018 43/18 poulpes Avis scientifique pour la gestion des MG-PM pêcheries de langoustes, dans les sites 30 000 CI NON 30/07/2018 44/18 prioritaires Développement des points de référence MG-PM opérationnels pour la gestion de la 75 000 CI NON 30/07/2018 45/18 pêche crevettière Révision du système de suivi de la MG-PM pêche crevettière traditionnelle (PCT) 86 000 SFQC NON 30/07/2018 46/18 et élargissement à toutes les zones de pêche MG-PM Révision par les pairs des modèles 86 000 SFQC NON 30/07/2018 47/18 d'évaluation des stocks de crevettes Étude technique sur la stratégie de NON Commented [JM10]: 60 000 dans le PPM MG-PM surveillance et sur le fonctionnement 15 000 SFQC 30/07/2018 d’aout 49/18 du CSP Commented [u11R11]: Après vérification du Frais d'équipage durant les travaux de NON PTBA 2018 ligne 2.2.2.1.1, pour 2018 on a prévu MG-PM carénages (vivres+ indemnités + 25 000 CI 01/08/2018 01 étude pour 15.000USD le coût unitaire 50/18 carburants) MG-PM Assistance technique pour le suivi des 26 000 CI NON 30/09/2018 51/18 travaux de carénage de l'Atsantsa MG-PM NON Rédaction d’un plan national de lutte 52/18 52 000 CI 30/07/2018 contre la pêche INN Extension de l’ERS vers la flotte NON MG-PM nationale (Etude / subvention/ cout 50 000 CI 30/10/2018 53/18 interne CSP) Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Etude et élaboration de mécanisme NON MG-PM structurel de plateforme de cogestion 50 000 CI 30/07/2018 54/18 des filières prioritaires (crabes, poulpes, langoustes, holothuries, crevettes) Études techniques et études d’impact SFQC NON Commented [JM13]: 50 000 dans le PPM environnemental et social pour la Etude groupée d’aout PA 65 Construction des Bureaux de six (06) 70 000 30/07/2018 MG-PM 57-58-85– Commented [u14R14]: Cette ligne regroupe DRRHP et neuf (09) CirRHP et d’un local 86/18 les études MG-PM 57-58-85 et 85 du PPM d’Août, pour bureau de l’UGP réf PTBA 2018 : 2.3.2.1.3 – 2.3.2.1.4 – 4.1.4.1.1 Etude sur l'identification des 180 000 SFQC NON et 4.1.4.1.2 bénéficiaires, du montant et des Commented [u12]: Après vérification PTBA modalités de transfert financier et sur Etude groupée 2018 lignes 2.3.2.1.3 et 2.3.2.1.4 c’est 08 MG-PM la détermination du montant minimal MG-PM 59-18 et 93/18 30/04/2018 de filet social pour les pêcheurs/acteurs MG-PM 60-18 filières affectés par les mesures de gestion MG-PM Recensement et identification des 20 000 CI NON 30/05/2018 61/18 bénéficiaires chaque année Etude sur l'amélioration des SFQC NON MG-PM embarcations existantes à partir des 270 000 01/11/2018 64/18 matériaux locaux bon marché et existants pour chaque ZUP Etude sur l'identification de techniques NON MG-PM modernes de pêche et de fabrication 60 000 SFQC 30/07/2018 65/18 d'engins de pêche adaptés pour chaque ZUP Prestataire formateur en construction 30 000 CI NON MG-PM et entretien des embarcations de pêche 30/11/2018 66/18 (par an) Prestataire formateur en construction 30 000 CI NON MG-PM et entretien des engins de pêche (par 30/08/2018 67/18 an) Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Etude sur le circuit de 90 000 SFQC NON MG-PM commercialisation des produits des 30/03/2018 68/18 pêches par ZUP MG-PM ""Etude sur les accidents en mer de la 90 000 SFQC NON 30/04/2018 69/18 pêche à petite échelle""" ""Développement du système de SFQC NON MG-PM valorisation des produits halieutiques 60 000 30/03/2018 70/18 adaptées pour chaque ZUP""" " Étude de marché pour les produits de SFQC MG-PM pêche valorisés dans chaque région 90 000 NON 30/04/2018 71/18 ultra prioritaire (1 étude par région)" MG-PM Prestataire formateur en technique de CI NON 75 000 30/03/2018 72/18 valorisation (par an) MG-PM Prestataire formateur en technique CI NON 25 000 28/02/2018 73/18 commerciale (par an) MG-PM "Analyse des besoins en activités SFQC NON 74/18 alternatives adaptées pour chaque ZUP 210 000 30/05/2018 (exécutée par AGEX)" Evaluation des impacts socio- SFQC NON MG-PM économiques de la mise pratique des 90 000 30/09/2018 75/18 activités alternatives MG-PM Elaboration des Plans d'Action aux 60 000 CI NON 28/02/2018 76/18 restrictions de Ressources (PARAR) Détermination des outils financiers de NON PA40 gestion des revenus issus des filières et 60 000 CI activités alternatives MG – PM Cabinet d’étude ou d’une ONG pour 600 000 SFQC NON 117/18 assurer les missions de l’AGEX (PAP 01/06/2018 MELAKY) Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions MG – PM Cabinet d’étude ou d’une ONG pour 600 000 SFQC NON 117/18 assurer les missions de l’AGEX (PAP 01/06/2018 BATAN) MG – PM Cabinet d’étude ou d’une ONG pour 600 000 SFQC NON 117/18 assurer les missions de l’AGEX (PAP 01/06/2018 Baie d’Antongil) Elaboration de plan de formation des CI NON élus et acteurs communaux MG-PM (Fokontany, Mairie,…) pour la gestion 18 000 01/06/2018 77/18 et la pérennisation des infrastructures de pêches et communautaires MG-PM Elaboration du plan stratégique de CI NON 80 000 30/01/2018 78/18 développement local (PCD et PLD) Etat de lieux des petites infrastructures CI NON MG-PM de pêches et identifications des besoins 79/18 60 000 01/04/2018 des communautés cibles en petites infrastructures de pêche Etude de faisabilité technique des NON constructions d'infrastructures de pêche (APS & APD) (33 débarcadères, 8 MG-PM marchés couverts, 70 salles réunion et 550 000 SFQC 01/08/2018 80/18 hangars d'entretien des embarcations, 28 fabriques de glace) MG-PM Etude d'impact environnemental et 275 000 SFQC NON 01/08/2018 81/18 social Préparation du plan local NON Ligne d’activité à Commented [JM15]: Pas de montant? MG-PM d'électrification communautaire : étude CI 01/03/2018 retirer dans ce Commented [u16R16]: Omission de montant 82/18 et rapports PPM dans le PTBA réf 3.3.3.1.3 – Après consultation Gestion et mise en œuvre : évaluation NON de RC3, le type de coût CS est changé en OP car MG-PM cette activité fait partie d’objet de convention de la mise en place de l'électrification 15 000 CI 01/12/2018 83/18 avec l’ADER. De ce fait, cette ligne ne fera plus hors grille partie des études dans le PPM 2018 Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions MG-PM Gestion et mise en œuvre : Suivi 40 000 CI NON 15/10/2018 84/18 évaluation des bases de données MG-PM Enquête de situation de référence des SFQC NON 50 000 30/07/2018 87/18 bénéficiaires MG-PM Audit externe des comptes du Projet 15 000 SMC NON 01/12/2018 88/18 MG-PM Elaboration d'une stratégie du plan de CI NON 10 000 30/09/2018 89/18 communication du projet SWIOFish2 MG-PM Mise en place du site internet du projet CI NON 2 000 30/09/2018 90/18 SWIOFish2 MG-PM CI NON Assistance technique - maintenance 500 30/09/2018 91/18 TOTAL Consultances 5.264.000 IV. Activités de renforcement de capacités de l’Agence d’exécution avec calendrier 1. Dans cette section, les activités de renforcement de capacité acceptées (quelques articles pourraient être des recommandations de CPAR) sont énumérées avec le calendrier No. Résultats escomptés / Description Coût Durée Date de Commentaire de l’activité estimatif estimative début s (jours) MG-FO Ateliers nationaux pour la 12.000 01-18 validation des textes d'application avec CRDA MG-FO Formation SLC (technique de 18.000 02-18 négociation, leadership etc.) MG-FO Tenir un atelier national relatif à 7.500 03-18 la communication de la nouvelle loi portant Code de la Pêche et de l'Aquaculture à Madagascar MG-FO Atelier national de préparation de 3.000 02 04-18 l'élaboration du nouveau plan directeur MG-FO Atelier national de validation du 6.000 01 05-18 plan directeur MG-FO Visite d'échange d'expérience en 40.000 06-18 matière de technique de production et d'exploitation aquacole marine (ex: grouper sp, algue marine, crabe) MG-FO Formation provinciale sur 27.000 07-18 nouvelles procédures de marquage, de délivrance des cartes pêcheurs et mareyeurs MG-FO Formation des cadres supérieurs 123.000 08-18 (6+6) dans la collecte des données et statistiques de pêche (formation FAO/ISSEA) MG-FO Formation des 10 enquêteurs en 2.000 09-18 méthodologie de collecte de données par téléphone mobile pour les 2 ZUP (DIANA et Analanjirofo; soit 5 enquêteurs/région) MG-FO Formation de 05 cadres 25.000 10-18 supérieurs dans l'analyse des données MG-FO Formation de 05 cadres 25.000 11-18 supérieurs en IT MG-FO Participation à des réunions et 10.000 12-18 ateliers régionaux per diem et hôtel et frais d'avion MG-FO Renforcement des 13-18 capacités des personnels 15.000 techniques de l'OEPA (économie des ressources naturelles et économie des pêches) MG-FO Ateliers régionaux sur la 36.000 14-18 stratégie nationale (pour les 6 ex- provinces) MG-FO Atelier national sur la stratégie 3.000 15-18 nationale MG-FO Formations et voyages d’échange 100.000 16-18 d’expérience et de la bonne pratique (renforcement des capacités, Ateliers de restitution et de validation des travaux de consultance, coûts des voyages, frais de participations, indemnités…) MG-FO Renforcement de capacité des 50.250 17-18 agents chercheurs (formations extérieures) MG-FO Participation à des forums de 52.500 18-18 recherche MG-FO Formation de l'équipe (média, 15.000 19-18 audio-visuel, design, PAO, site web, prog. éducatifs) MG-FO Renforcement de capacité des 5.000 20-18 membres du bureau de coordination pêche environnement (environnement pêche et mer) MG-FO Organisation des réunions 46.000 21-18 semestrielles MG-FO Formation en QMS d’une Autorité 14.300 22-18 Compétente par formateur international pour renforcement de capacités en Audit interne d’une Autorité compétente (Maitrise des documents et des enregistrements) MG-FO Formation en Informatique & 23-18 Base de données : Avec 24.000 formateur national : Informatique (bureautique et programmation) / Utilisation & gestion de base de données MG-FO Linguistique : Avec formateur 15.140 24-18 national : Anglais / Chinois MG-FO Formation en Aquaculture : Avec 22.640 25-18 formateur international : Technique d’élevage et gestion de risque / Méthode de contrôle appliquée dans divers système d’aquaculture (Diana 3 personnes; Melaky 7; Central 2) MG-FO Formation en système de 26-18 Biosécurité : Avec formateur 22.640 international : Biosécurité appliquée aux animaux aquatiques (Diana 3 personnes; Melaky 7; Central 2) MG-FO Formation en Système de 22.640 27-18 management de la QHSE Sanitaire : Avec formateur international : Hygiène et pré requis au niveau des établissements / Normes ISO sur la sécurité sanitaire des aliments / HACCP / Evaluation & analyse des risques MG-FO Formation en Gestion des crises : 28-18 Avec formateur international : 22.640 RASFF MG-FO Formation en Système de 20.200 29-18 certification : Avec formateur international : TRACES MG-FO Formation en Accord International 22.640 30-18 : Avec formateur international : Accord SPS&OMC MG-FO Formation en Science & 22.640 31-18 Technologie : Avec formateur international : Microbiologie des aliments et de l’eau / Toxicologie appliquées aux produits de la mer / Science & Technologie des aliments MG-FO Formation en Technique 2.830 32-18 d’analyse : Avec formateur national : Technique d’analyse de détection des maladies aquatiques MG-FO Formatio 22.640 33-18 n en Technique d’analyse et Technique d’échantillonnage : Avec formateur international MG-FO Formation en Administration : 34-18 Avec formateur national : 15.64 Formation en officier de police 0 judiciaire MG-FO Formation en Administration : 2.840 35-18 Avec formateur national : Procédures Banque Mondiale (Passation de marché, suivi- évaluation MG-FO Formation en QMS d’une Autorité 24.000 36-18 Compétente : Avec formateur international : Structuration et management Qualité d’une Autorité Compétente (ISO 17020) MG-FO Formation en Aquaculture : Avec 37-18 formateur international : 40.000 Aquaculture & environnement MG-FO Formation en Contrôles officiels : 38-18 Avec formateur international : 32.000 Echange d’expérience par jumelage régionale MG-FO Formation en Système de 39-18 management de la QHSE 8.000 Sanitaire : Avec formateur international : Audit de laboratoire selon ISO 17025 MG-FO Formation en Technique 8000 40-18 d’analyse : Avec formateur international : Technique d’analyse officielle MG-FO Formation en Technique 41-18 d’analyse : Avec formateur 8.000 international : Métrologie MG-FO Participation aux réunions et 134.000 42-18 groupes de travail CTOI et ORP MG-FO Réunion nationale (50 personnes 43-18 de 2 jours) de concertation sur la 6.000 pêche aux requins, oiseaux de mer, tortues MG-FO Participation aux réunions 100.500 44-18 régionales pour les termes minimaux des accords de pêche MG-FO Réunions de consultation 6.000 45-18 nationales sur la préparation des Mesures de conservation et de gestion (pour 6 réunions par an) MG- Formation sur l'identification des 8.500 FO46-18 espèces thonières et les techniques d'échantillonnage au débarquement MG-FO Formation sur la gestion des 8.500 47-18 données MG-FO Atelier de validation de nouveaux 75.000 48-18 PAP MG-FO Visite d'échange et d'expérience 31.000 49-18 sur l'utilisation du logiciel ERS MG-FO Formation du personnel à 60.600 50-18 l’utilisation et à l’exploitation de cet outil. MG-FO Renforcement de capacité et 51-18 formation des membres des CSC 24.000 MG-FO Ateliers de lancement régionaux 30.000 52-18 sur les plateformes de cogestion (crabes, poulpes, langoustes, holothuries, crevettes) dans les régions MG-FO Formations et remise à niveau au 112.500 53-18 niveau national des cadres MG-FO Formations et remise à niveau 100.000 54-18 des cadres à l'extérieur MG-FO Atelier de restitution de l'étude 55-18 sur l'identification des 20.000 bénéficiaires, du montant et des modalités de transfert financier et du filet social MG-FO Ateliers de validation des 3.000 56-18 référentiels (diplôme, certificat, attestation) MG-FO Formation des techniques 60.000 57-18 modernes de pêche MG-FO Formation en construction 60.000 58-18 et entretien d'engin de pêche MG-FO Formation sur les techniques 60.000 59-18 commerciales des produits des pêches MG-FO Atelier de restitution de l'étude 20.000 60-18 sur l'accidentologie MG-FO Visite d'échange dans le cadre de 90.000 61-18 la sécurité en mer et de la professionnalisation (Philippine, …) MG-FO Ateliers de validation régionale 62-18 (03) et nationale (01) de l'étude 16.000 diagnostic des techniques de valorisation MG-FO Voyage de partage d’expérience 63-18 dans les régions ou pays voisins, 90.000 où la formation et l’appui en valorisation ont été effectives et ont apporté des effets positifs MG-FO Formation des personnes dans la 64-18 communauté de pêcheurs (pêcheurs, femmes de pêcheur, jeunes sans emploi) en 72.000 techniques de valorisation (15 personnes formées par village) MG-FO Formation des acteurs pratiquant 72.000 65-18 les techniques de valorisation sur la gestion des activités commerciales, la prospection des marchés, les techniques de négociation et le marketing et conditionnement MG-FO Voyages d’échange d’expérience 16.000 66-18 pour les acteurs formés et ayant pratiqué la commercialisation au niveau d’un district littoral accompagnés des agents de la CirRHP/DRRHP/MRHP (1 par année par district) (50 acteurs par voyage) MG-FO Ateliers de restitution régionaux 67-18 et des ateliers de validation 24.000 nationale de l'étude diagnostic des besoins en activités alternatives MG-FO Voyages d’échange d’expérience 45.000 68-18 dans des pays semblables à Madagascar pour les bénéficiaires (Afrique australe, régions de la COI et en Asie) MG-FO Prestation à la formation des 50.000 69-18 cibles en activités alternatives MG-FO Formation des techniciens de 9.000 70-18 l’Administration (DRRHP et CirRHP) et l’UGL sur les techniques et le système de suivi de ces techniques (par région) MG-FO Formation des pêcheurs, femmes 480.000 15 71-18 de pêcheurs et jeunes dans les villages de pêcheurs en techniques de production appropriées pour chaque type d’activité alternative choisi (15j*8000) MG-FO Formation des pêcheurs, femmes 05 72-18 de pêcheurs et jeunes sans 100.000 emploi en techniques d’aquaculture (5 jours) MG-FO Formation et d'échange 90.000 73-18 d'expérience à l'étranger dans le cadre de l'aquaculture (algoculture, pisciculture, crabiculture,…) MG-FO Formation des acteurs pratiquant 80.000 04 74-18 les activités alternatives sur la gestion des activités commerciales, la prospection des marchés, les techniques de négociation et le marketing et conditionnement (4 jours) MG-FO Visites de la vitrine/ ferme école 72.000 75-18 pour les acteurs formés MG-FO Orientation des pêcheurs dans la 1.600 02 76-18 valorisation de leur biodiversité et les former en guide touristique MG-FO Sélection et formation des PF au 12.000 77-18 fonctionnement du MDGP MG-FO Ateliers de validation régionale 16.000 78-18 (03) et nationale (01) MG-FO Visite d’échange d’expérience 32.000 79-18 nationale (1 voyage par an par district) MG-FO Voyage de partage d’expérience 45.000 80-18 à l’étranger (01 voyage par an) MG-FO Séminaire/atelier international 70.000 81-18 (02 voyages par an) MG-FO Formation de courte durée à 45.000 82-18 l’étranger (01 voyage par an) MG-FO Réunions de sensibilisation et de 192.000 03 83-18 formation en éducation financière des petits pêcheurs et aquaculteurs à petite échelle (200 villages de pêcheurs) MG-FO Réunions de sensibilisation pour 64.000 01 84-18 la constitution en organisation appropriée des bénéficiaires du projet (200 villages de pêcheurs) MG-FO Promotion des services financiers 48.000 85-18 adéquats et adaptés à chaque zone d’intervention à travers des sensibilisations MG-FO Renforcement de capacité des 150.000 86-18 cadres et élus au niveau local MG-FO Renforcement de capacité des 9.000 87-18 UGL MG-FO Ateliers régionaux (03) et national 16.000 88-18 de validation MG-FO Atelier de réception locale de 4.000 89-18 l’infrastructure construite MG-FO Partage d'expérience à l'étranger 45.000 90-18 (2 missions par an) dans le cadre de la gestion communautaire des infrastructures de pêche MG-FO Formation des groupements de 8.000 91-18 pêcheurs pour être dans des comités de gestion et formation sur la gestion des infrastructures MG-FO Formation des groupements de 36.000 92-18 pêcheurs pour être dans des comités de gestion et formation sur la gestion des infrastructures MG-FO Formation des communautés 55.800 93-18 pilote sur les procédures réglementaires dans le cadre de l'électrification hors grille MG-FO Formation des communautés 90.000 94-18 pilotes à l'usage et à la gestion de l'électrification hors grille MG-FO Engagement communautaire 75.000 95-18 (IEC) dans le cadre de l'électrification hors grille MG-FO Gestion et mise en œuvre : 27.900 96-18 diffusion de connaissances MG-FO Participation à des ateliers de 10.000 97-18 partage MG-FO Formation modulaire spécifique 20.250 98-18 (langues, communication, informatique, …) MG-FO Formation modulaire (Gestion de 120.000 99-18 projet, suivi et évaluation, sauvegarde environnementale, techniques de négociations, SIG, …) MG-FO Formation de l'équipe (média, 37.500 100-18 audio-visuel, design, PAO, site web, prog. éducatifs) MG-FO Formation sur les procédures de 22.500 101-18 la Banque mondiale MG-FO Organisation des ateliers 17.000 102-18 MG-FO Formation relative à l'utilisation 11.400 103-18 de logiciel SE MG-FO Renforcement de capacité des 104-18 UGL sur le SE 7.500 MG-FO Atelier participatif de Suivi 105-18 Evaluation avec UGP- UGL- 3.000 MRHP-AGEX TOTAL Renforcement de capacité 4.396.730 PROCUREMENT Southern Africa : Second South West Indian Ocean Fisheries Governance and Shared Growth Project - Madagascar PLAN General Information Country: Southern Africa Bank’s Approval Date of the Original Procurement Plan: 2017-04-06 Revised Plan Date(s): (comma delineated, leave blank 2023-06-05 if none) Project ID: P153370 GPN Date: Project Name: Second South West Indian Ocean Fisheries Governance and Shared Growth Project - Madagascar Loan / Credit No: IDA / Q9790, IDA / 59870, IDA / D1720, IDA / V0500, TF / A4588 MINISTRY OF HALIEUTIC RESSOURCES AND FISHERIES Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl Description Component Review Type Method Document Ty Amount ( mount (U t and Recommendati Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) S$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MG-MRHP-28163-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2017-09-3 2017-10-2 2017-12-0 2018-02-2 2018-04-0 2018-10- MG-PM-11 / Carénages du n IDA / D1720 g capacities for priority fish Post Request for Bids 76,000.00 0.00 Canceled al Envelope 0 1 5 4 7 04 avire de surveillance «Teloni eries management fy », MG-MRHP-28164-CW-RFB// Component 3. Strengthenin MG-PM-12 / Construction d'i g capacities for engaging in Single Stage - Two 2017-11-3 2017-12-2 2018-02-0 2018-04-2 2018-06-0 2018-12- IDA / 59870 Post Request for Bids Open - National 200,000.00 0.00 Canceled nfrastructures communautai alternative fishing practices Envelope 0 1 4 6 7 04 res /communales and livelihoods activities MG-MRHP-28634-CW-RFB// MG-PM-105 / Carénages du Component 2. Strengthenin navire de surveillance «Atsa Open - Internation Single Stage - Two 2018-02-2 2019-01-2 2018-03-1 2018-04-2 2018-08-0 2018-09-1 2019-03- IDA / D1720 g capacities for priority fish Post Request for Bids 181,000.00 0.00 Canceled ntsa », remplacement des a al Envelope 8 8 4 8 2 3 12 eries management ppareils de navigation/accés soires et pièces de rechange s desmoteurs auxiliaires Component 3. Strengthenin MG-MRHP-28642-CW-RFB// g capacities for engaging in Single Stage - Two 2018-06-2 2018-07-1 2018-08-2 2018-11-1 2018-12-2 2019-06- MG-PM-107 / Rehabilitation IDA / 59870 Post Request for Bids Open - National 50,000.00 0.00 Canceled alternative fishing practices Envelope 9 3 7 6 8 26 du CFTP Nosy be and livelihoods activities MG-MRHP-28648-CW-RFB// Component 3. Strengthenin MG-PM-110 / Infrastructures g capacities for engaging in Single Stage - One 1,250,000.0 2018-04-3 2018-05-1 2018-06-2 2018-09-2 2019-03- IDA / V0500 Post Request for Bids Open - National 0.00 Canceled d'électrification hors grille d alternative fishing practices Envelope 0 0 4 5 0 19 ans les communautés pilote and livelihoods activities s MG-MRHP-100097-CW-RFQ Component 2. Strengthenin Request for Quot Single Stage - One 2019-02-1 2018-07-2 2019-04-1 2018-09-1 2019-10- / Carénages du navire de su IDA / D1720 g capacities for priority fish Post Limited 76,000.00 101,079.93 Completed ations Envelope 7 3 4 7 11 rveillance «Telonify » eries management MG-MRHP-28432-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06- MG-PM-101 / Extension ou c IDA / 59870 g capacities for priority fish Post Request for Bids 60,000.00 0.00 Canceled al Envelope 1 5 9 8 0 27 onstruction du bureau régio eries management nal OEPA : 03 MG-MRHP-28436-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2019-07-1 2019-07-2 2019-09-1 2019-12-0 2020-01-1 2020-07- MG-PM-102 / Construction d IDA / 59870 g capacities for priority fish Post Request for Bids 40,000.00 0.00 Canceled al Envelope 5 9 2 2 3 11 u bâtiment central de l'OEPA eries management : 01 MG-MRHP-28438-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06- MG-PM-103 / Mise en place IDA / 59870 g capacities for priority fish Post Request for Bids 100,000.00 0.00 Canceled al Envelope 1 5 9 8 0 27 d'infrastructure pour centre eries management de recherche CEDP MG-MRHP-119316-CW-RFB / Component 2. Strengthenin Construction bureaux USTA Single Stage - One 2019-08-0 2019-08-0 2019-09-1 2019-10-1 2019-11-2 2020-05- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 46,000.00 0.00 Canceled au niveau des antennes (Ma Envelope 1 6 7 7 1 19 eries management hajanga et Toamasina) : 02 MG-MRHP-96947-CW-RFQ B IS / Carénages du navire de Component 2. Strengthenin surveillance «Atsantsa », re Request for Quot Single Stage - One 2019-07-0 2019-02-1 2019-09-2 2019-07-1 2020-03- IDA / D1720 g capacities for priority fish Post Limited 350,000.00 309,641.94 Completed mplacement des appareils d ations Envelope 7 1 6 2 24 eries management e navigation/accessoires et pièces de rechanges des mo teurs auxiliaires MG-MRHP-119317-CW-RFB / Component 2. Strengthenin Single Stage - One 2019-07-1 2019-07-2 2019-08-3 2019-09-3 2019-11-0 2020-05- Constructions pour les six (0 IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 420,000.00 0.00 Canceled Envelope 5 0 1 0 4 02 6) DRRHP et huit (08) CIRR eries management HP MG-MRHP-28643-CW-RFB// Component 3. Strengthenin MG-PM-108 / Construction d g capacities for engaging in Single Stage - Two 2019-08-0 2019-08-1 2019-09-2 2019-12-1 2020-01-3 2020-07- IDA / 59870 Post Request for Bids Open - National 350,000.00 0.00 Canceled e petites débarcadères type alternative fishing practices Envelope 1 5 9 9 0 28 ponton and livelihoods activities MG-MRHP-119318-CW-RFB / Travaux de construction et d Component 2. Strengthenin Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-0 2020-03-2 2020-08-2 2021-08- e la réhabilitation de l’ancie IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 130,900.00 126,080.50 Signed Envelope 5 8 0 1 3 2 9 8 0 25 n bureau-logement du DRRH eries management P Analanjorofo – Region Anal anjorofo MG-MRHP-119318BIS1-CW- Component 2. Strengthenin RFB / Travaux de constructio Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-0 2020-03-2 2020-07-0 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 58,400.00 89,364.09 Signed n d'un nouveau bureau-loge Envelope 5 8 0 1 4 2 9 8 4 25 eries management ment du DRRHP Anosy - Rég ion Anosy MG-MRHP-119318BIS2-CW- Component 2. Strengthenin RFB / Travaux de réhabilitati Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-0 2020-03-2 2020-06-2 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 62,700.00 95,221.17 Signed on du bureau de la CIRRHP Envelope 5 8 0 1 4 2 9 8 4 25 eries management Maroantsetra- District Maroa ntsetra MG-MRHP-119318BIS4-CW- Component 2. Strengthenin RFB / Travaux de constructio Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-1 2020-03-2 2020-08-1 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 58,600.00 43,216.11 Signed n d'un nouveau bureau-loge Envelope 5 8 0 1 5 2 2 8 8 25 eries management ment ASH Morondava - Régi on Menabe MG-MRHP-28640-CW-RFB// Component 2. Strengthenin Single Stage - Two 2018-06-1 2018-06-2 2018-08-1 2018-11-0 2018-12-1 2019-06- MG-PM-106 / Constructions IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 180,000.00 0.00 Canceled Envelope 5 9 3 2 4 12 pour les six ( 06) DRRHP et eries management huit (08 )CIRRHP MG-MRHP-170956-CW-DIR / Component 2. Strengthenin 2020-05-0 2020-06-1 2020-05-2 2020-06-1 2020-07-1 2020-09-2 2021-12- Travaux de construction du IDA / 59870 g capacities for priority fish Post Direct Selection Direct 76,500.00 95,680.97 Signed 8 1 2 2 0 2 07 DRRHP Androy - Région And eries management roy MG-MRHP-170965-CW-DIR / Component 2. Strengthenin Travaux de réhabilitation du 2020-05-0 2020-06-1 2020-05-2 2020-06-1 2020-07-1 2021-03-1 2021-12- IDA / 59870 g capacities for priority fish Post Direct Selection Direct 71,000.00 71,774.44 Signed bureau-logement du DRRHP 8 1 2 2 7 8 14 eries management Melaky - Région Melaky MG-MRHP-119318BIS5-CW- Component 2. Strengthenin RFB / Travaux de réhabilitati Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-03-2 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 71,000.00 0.00 Canceled on du bureau-logement du Envelope 5 8 0 1 6 2 8 25 eries management DRRHP Melaky - Région Mel aky MG-MRHP-119318BIS3-CW- Component 2. Strengthenin Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-03-2 2021-08- RFB / Travaux de constructio IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 76,500.00 0.00 Canceled Envelope 5 8 0 1 5 2 8 25 n du DRRHP Androy - Région eries management Androy MG-MRHP-28165-CW-RFB-B Component 4. Project mana Single Stage - One Terminate 2019-06-1 2019-06-1 2019-07-0 2019-08-1 2019-07-2 2019-09-1 2019-12-1 2019-10-2 2020-01-1 2021-03- IS // MG-PM-13 / Constructio IDA / 59870 Post Request for Bids Open - National 90,375.00 74,306.94 gement and coordination Envelope d 7 7 8 9 3 8 7 3 8 21 n de bureau de l'UGP central e MG-MRHP-28165-CW-RFB// Component 4. Project mana Single Stage - Two 2019-07-0 2019-06-1 2019-07-2 2019-07-1 2019-09-0 2019-07-2 2019-11-2 2020-01-0 2020-07- MG-PM-13 / Construction de IDA / 59870 Post Request for Bids Open - National 60,000.00 0.00 Canceled gement and coordination Envelope 1 7 2 8 5 3 5 6 04 bureau de l'UGP centrale MG-MRHP-203600-CW-RFB / Travaux de construction d'u Component 2. Strengthenin Single Stage - One 2020-11-2 2020-12-0 2020-12-1 2020-12-1 2021-01-0 2021-01-0 2021-02-0 2021-03-3 2021-03-1 2021-05-1 2021-07- n bureau de Circonscription IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 61,500.00 59,640.48 Signed Envelope 0 9 0 2 9 8 8 0 5 5 13 de l'Agriculture, de l'Elevage eries management et de la Pêche ( CirAEP) à A mbanja MG-MRHP-96947-CW-RFQ / Carénage du navire de surv Component 2. Strengthenin eillance "Atsantsa", remplac Request for Quot Single Stage - One 2019-03-0 2019-02-1 2019-05-2 2019-11- IDA / D1720 g capacities for priority fish Post Limited 181,000.00 0.00 Canceled ement des appareils de navi ations Envelope 8 1 8 24 eries management gation/ accessoires et pièce s de rechanges des moteurs auxiliaires. MG-MRHP-256406-CW-RFB / Request for Bids TRAVAUX DE CONSTRUCTIO Component 2. Strengthenin Single Stage - One - Works French C 2021-11-1 2021-12-0 2021-11-2 2021-12-0 2021-12-2 2022-01-0 2022-01-2 2022-01-2 2022-02-2 2022-03-1 2022-07- N D’UN BATIMENT ADMINIST IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 178,400.00 163,531.57 Signed Envelope ivil Law (French) 6 1 1 7 1 7 0 4 4 4 24 RATIF ASH TOLIARA - District eries management SPD Toliara Région ATSIMO AND REFANA MG-MRHP-262336-CW-RFQ Request for Quot Component 4. Project mana Request for Quot Single Stage - One Under Impl 2021-12-2 2023-01-1 2022-02-2 2022-08- / Construction de bureau de IDA / 59870 Post Open - National ations (Non Bank 90,375.00 0.00 gement and coordination ations Envelope ementation 0 0 1 20 l'UGP centrale (Relance) -SPD) MG-MRHP-119319-CW-RFB / Installation d'unités de fabri ques de glace/chambres froi Component 3. Strengthenin Request for Bids des fonctionnant avec des é g capacities for engaging in Single Stage - One - Works French C 2022-03-0 2022-03-0 2022-04-0 2022-05-0 2022-06-1 2022-12- IDA / 59870 Post Request for Bids Open - National 320,000.00 0.00 Canceled nergies renouvelables et res alternative fishing practices Envelope ivil Law (French) 2 7 6 6 0 07 pectant l’environnement po and livelihoods activities SPD ur maintenir la chaîne de fro id des produits halieutiques dès leur débarquement : 04 MG-MRHP-119321-CW-RFB / Construction de hangars ave c des matériaux locaux pour Component 3. Strengthenin entretenir les moteurs, les e g capacities for engaging in Single Stage - One 2021-08-0 2021-08-1 2021-09-2 2021-10-2 2021-11-2 2022-05- IDA / 59870 Post Request for Bids Open - National 240,000.00 0.00 Canceled mbarcations et des engins d alternative fishing practices Envelope 6 1 2 2 6 25 e pêche autorisés et d'une b and livelihoods activities ase de réunion, sensibilisati on et de structuration des ut ilisateurs petites infrastructu res de pêche : 08 MG-MRHP-28645-CW-RFB// Component 3. Strengthenin Request for Bids Pending Im MG-PM-109 / Construction d' g capacities for engaging in Single Stage - Two - Small Works SP 2022-08-0 2022-08-1 2022-09-2 2022-12-1 2023-01-3 2023-07- IDA / 59870 Post Request for Bids Open - National 600,000.00 0.00 plementati infrastructures communauta alternative fishing practices Envelope D (1 envelope pr 1 5 9 9 0 29 on ires /communales : 60 and livelihoods activities ocess) MG-MRHP-119320-CW-RFB / Component 3. Strengthenin Request for Bids Pending Im Construction de marchés co g capacities for engaging in Single Stage - One - Small Works SP 2022-05-0 2022-05-0 2022-06-1 2022-07-1 2022-08-2 2023-02- IDA / 59870 Post Request for Bids Open - National 300,000.00 0.00 plementati uverts aux produits halieutiq alternative fishing practices Envelope D (1 envelope pr 3 8 9 9 3 19 on ues : 10 and livelihoods activities ocess) MG-MRHP-119324-CW-RFB / Component 3. Strengthenin Request for Bids Pending Im Infrastructures d'électrificati g capacities for engaging in Single Stage - One - Small Works SP 2022-04-3 2022-05-0 2022-06-1 2022-07-1 2022-08-2 2023-02- TF / A4588 Post Request for Bids Open - National 300,000.00 0.00 plementati on hors grille dans les comm alternative fishing practices Envelope D (1 envelope pr 0 5 6 6 0 16 on unautés pilotes : 10 and livelihoods activities ocess) MG-MRHP-28632-CW-RFB// Component 2. Strengthenin MG-PM-104 / Construction d Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-12-0 2020-01-1 2020-07- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 60,000.00 0.00 Canceled es bureaux des 2 PIE de l'AS Envelope 1 5 9 3 4 12 eries management H en province : Antsiranana et Morondava Request for Bids MG-MRHP-127603-CW-RFB / Component 2. Strengthenin Pending Im Single Stage - One - Small Works SP 2022-07-0 2022-07-2 2022-09-0 2022-10-0 2022-11-0 2023-05- Construction du siège de l'A IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 60,000.00 0.00 plementati Envelope D (1 envelope pr 1 2 2 2 6 05 SH centrale sis à Antananari eries management on ocess) vo Page 1 MG-MRHP-292931-CW-RFB / Construction des bâtiments Component 3. Strengthenin Request for Bids du kiosque de pré-électrifica g capacities for engaging in Single Stage - One - Small Works SP Under Impl 2022-05-1 2022-05-1 2022-05-1 2022-05-1 2022-06-1 2022-06-2 2022-07-1 2022-07-1 2022-08-2 2022-12- IDA / 59870 Post Request for Bids Open - National 347,450.00 0.00 tion et du «Complexe-pêche alternative fishing practices Envelope D (1 envelope pr ementation 2 2 7 6 6 0 6 5 0 18 » dans les villages de Fontsi and livelihoods activities ocess) maro et Rantohely, Région A nalanjirofo répartis en 2 lots MG-MRHP-296929-CW-RFB / Constructions des Bureaux a dministratifs de l’Autorité Sa Request for Bids nitaire Halieutique (ASH) da Component 2. Strengthenin Single Stage - One - Works French C Under Impl 2022-06-1 2022-06-1 2022-06-2 2022-06-2 2022-07-2 2022-08-1 2022-09-2 2023-02- ns la Région Vatovavy Fitovi IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 362,500.00 0.00 Envelope ivil Law (French) ementation 5 7 0 0 0 9 3 20 nany, District Manakara, Co eries management SPD mmune Manakara, Village M angarivotra et au District de Mananjary, Commune Mana njary, Village Marofinaritra ( 2 Lots) MG-MRHP-297986-CW-RFB / TRAVAUX DE CONSTRUCTIO Component 3. Strengthenin Request for Bids N DES BATIMENTS DU KIOS g capacities for engaging in Single Stage - One - Works French C 2,745,000.0 Under Impl 2022-06-1 2022-10-0 2022-06-2 2022-10-1 2022-07-2 2022-08-2 2022-09-2 2023-02- QUE DE PRE-ELECTRIFICATI IDA / 59870 Post Request for Bids Open - National 0.00 alternative fishing practices Envelope ivil Law (French) 0 ementation 6 7 1 0 1 0 4 21 ON ET DU « COMPLEXE-PEC and livelihoods activities SPD HE » DANS LE DISTRICT D’A MBILOBE, ET DANS LE DISTR ICT DE NOSY BE REPARTIS E N HUIT (08) LOTS MG-MRHP-307513-CW-RFB- Component 3. Strengthenin Request for Bids BIS / Travaux de constructio Pending Im g capacities for engaging in Single Stage - One - Works French C 2022-09-2 2022-10-0 2022-11-0 2022-12-0 2023-01-0 2023-05- n du bâtiment de Kiosque et IDA / 59870 Post Request for Bids Open - National 558,200.00 0.00 plementati alternative fishing practices Envelope ivil Law (French) 9 4 3 3 7 07 du complexe pêche Aniribe on and livelihoods activities SPD Mananara-Nord et Antoraka Maroantsetra répartis en 2 l ots MG-MRHP-320141-CW-RFB / Construction de Bâtiment ab Component 3. Strengthenin Request for Bids ritant la machine à glace rep g capacities for engaging in Single Stage - One - Works French C Under Impl 2022-10-2 2022-11-3 2022-10-2 2022-12-0 2022-11-2 2022-12-2 2023-01-2 2023-05- artis en 5 Lots dans les villa IDA / 59870 Post Request for Bids Open - National 601,000.00 0.00 alternative fishing practices Envelope ivil Law (French) ementation 1 0 6 6 5 5 9 29 ges d’Antanambao Mandrisy and livelihoods activities SPD , Hoalampano, Tampolo, Fah ambahy, Itanjona dans le dis trict de Mananara nord) MG-MRHP-320162-CW-RFB / TRAVAUX DE CONSTRUCTIO Component 3. Strengthenin Request for Bids N DES BATIMENTS DU KIOS g capacities for engaging in Single Stage - One - Works French C Under Impl 2022-10-2 2022-11-2 2022-10-2 2022-12-0 2022-11-2 2022-12-2 2023-01-2 2023-05- IDA / 59870 Post Request for Bids Open - National 852,900.00 0.00 QUE DE PRE-ELECTRIFICATI alternative fishing practices Envelope ivil Law (French) ementation 1 8 6 9 5 5 9 29 ON ET DU « COMPLEXE-PEC and livelihoods activities SPD HE » DANS LE DISTRICT D’A MBANJA REPARTIS EN TROIS (03) LOTS MG-MRHP-320156-CW-RFB / Travaux de construction des Component 3. Strengthenin Request for Bids bâtiments du kiosque de pré g capacities for engaging in Single Stage - One - Works French C Under Impl 2022-10-2 2022-10-2 2022-10-2 2022-10-3 2022-11-2 2022-11-2 2022-12-2 2023-01-2 2023-06- -électrification et du « Comp IDA / 59870 Post Request for Bids Open - National 622,000.00 0.00 alternative fishing practices Envelope ivil Law (French) ementation 1 7 6 1 5 8 5 9 28 lexe-pêche » dans les villag and livelihoods activities SPD es d'Ambalahonko et Ampas imandoro district de Maintir ano repartis en 2 lots MG-MRHP-320151-CW-RFB / Request for Bids CONSTRUCTIONS DES BURE Component 2. Strengthenin Pending Im Single Stage - One - Works French C 2022-10-2 2022-10-2 2022-11-2 2022-12-2 2023-01-2 2023-05- AUX ADMINISTRATIFS DE L'A IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 975,000.00 0.00 plementati Envelope ivil Law (French) 1 6 5 5 9 29 SH ET DE DESP (Ex-OEPA) A eries management on SPD NTANANARIVO repartis en 2 Lots MG-MRHP-332561-CW-RFB / Travaux de construction des Request for Bids Bureaux de la circonscriptio Component 2. Strengthenin Pending Im Single Stage - One - Works French C 2023-01-1 2023-01-1 2023-02-1 2023-03-1 2023-04-2 2023-08- n en charge de la pèche et d IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 708,427.00 0.00 plementati Envelope ivil Law (French) 0 5 4 6 0 18 e l’économie bleu et l’anten eries management on SPD ne du centre de la surveillan ce des pêches à Maintirano, Région Melaky MG-MRHP-337958-CW-RFB / Component 3. Strengthenin Request for Bids Construction de Bâtiment ab g capacities for engaging in Single Stage - One - Small Works SP Under Impl 2023-01-2 2023-02-0 2023-02-0 2023-02-0 2023-03-0 2023-03-1 2023-03-2 2023-07- ritant la chambre froide dan IDA / 59870 Post Request for Bids Open - National 410,000.00 0.00 alternative fishing practices Envelope D (1 envelope pr ementation 7 3 1 6 3 3 3 21 s le village de RANTABE dan and livelihoods activities ocess) s le district de MAROANTSET RA, Région ANALANJIROFO MG-MRHP-337965-CW-RFB / Component 3. Strengthenin Request for Bids CONSTRUCTION DES DEUX ( Pending Im g capacities for engaging in Single Stage - One - Works French C 2023-01-3 2023-02-0 2023-03-0 2023-03-1 2023-03-2 2023-07- 02) MARCHES COUVERTS D IDA / 59870 Post Request for Bids Open - National 250,000.00 0.00 plementati alternative fishing practices Envelope ivil Law (French) 1 5 7 7 5 23 ANS LE DISTRICT DE MANAN on and livelihoods activities SPD ARA NORD REPARTIE EN DE UX (02) LOTS Request for Bids MG-MRHP-262336-BIS-CW- Component 4. Project mana Single Stage - One - Works French C Under Impl 2023-01-2 2023-01-1 2023-02-0 2023-02-0 2023-03-0 2023-03-1 2023-03-2 2023-07- RFQ / Construction de burea IDA / 59870 Post Request for Bids Open - National 90,375.00 0.00 gement and coordination Envelope ivil Law (French) ementation 9 0 3 8 5 5 3 21 u de l’UGP centrale (Relance SPD ) MG-MRHP-340927-CW-RFB / Travaux de construction des Component 3. Strengthenin Request for Bids bâtiments du kiosque de pré Pending Im g capacities for engaging in Single Stage - One - Works French C 2023-02-1 2023-02-1 2023-03-2 2023-04-1 2023-04-2 2023-08- électrification et du "Comple IDA / 59870 Post Request for Bids Open - National 222,300.00 0.00 plementati alternative fishing practices Envelope ivil Law (French) 4 9 1 1 8 26 xe pêche" dans le village d' on and livelihoods activities SPD Andranonabo, Commune Anj iabe ambony, District d'Amb ilobe (RELANCE) MG-MRHP-344175-CW-RFB / Request for Bids Travaux de construction des Component 2. Strengthenin Single Stage - One - Small Works SP 1,352,000.0 Under Impl 2023-02-2 2023-03-1 2023-03-0 2023-03-1 2023-03-3 2023-04-1 2023-04-1 2023-08- bâtiments Administratifs du IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 0.00 Envelope D (1 envelope pr 0 ementation 4 1 1 5 1 0 4 12 MPEB dans les régions de D eries management ocess) IANA- MELAKY- ANOSY repar tie en 04 lots MG-MRHP-344184-CW-RFB / Request for Bids Travaux de construction des Component 2. Strengthenin Single Stage - One - Works French C Under Impl 2023-02-2 2023-03-1 2023-03-0 2023-04-1 2023-03-3 2023-04-1 2023-04-1 2023-08- bâtiments Administratifs du IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 620,000.00 0.00 Envelope ivil Law (French) ementation 4 1 1 1 1 0 4 12 MPEB dans les régions de B eries management SPD OENY et ATSIMO ANTSINANA NA repartie en 02 lots MG-MRHP-344311-CW-DIR / Travaux additionnels de con Component 2. Strengthenin Request for Quot Pending Im struction du bureau, de Han 2023-04-0 2023-04-2 2023-05-0 2023-08- TF / A4588 g capacities for priority fish Post Direct Selection Direct - National ations (Non Bank 230,000.00 0.00 plementati gar pour la vedette de la bri 7 7 3 31 eries management -SPD) on gade du CSP Analanjirofo, et mise en place d’un point d’eau autonome par Entrepr ise FITALIA Request for Bids MG-MRHP-127600-CW-RFB / Component 2. Strengthenin Pending Im Single Stage - One - Small Works SP 2023-05-0 2023-05-0 2023-06-0 2023-06-2 2023-07-1 2023-09- Renforcement du CDA - Con IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 36,850.00 0.00 plementati Envelope D (1 envelope pr 2 7 6 7 1 29 struction puits et réhabilitati eries management on ocess) on clôture CDA MG-MRHP-337960-CW-RFB / Travaux de construction des Component 3. Strengthenin Request for Bids bâtiments abritant la machi g capacities for engaging in Single Stage - One - Small Works SP Under Impl 2023-05-0 2023-05-0 2023-05-0 2023-05-0 2023-06-0 2023-06-1 2023-07-0 2023-09- ne à glace dans les villages IDA / 59870 Post Request for Bids Open - National 357,400.00 0.00 alternative fishing practices Envelope D (1 envelope pr ementation 3 3 3 9 2 6 7 29 de Maintimbato, Mahasoa, A and livelihoods activities ocess) mbodipaka, Masindrano da ns le district de Maroantsetr a repartis en 4 lots MG-MRHP-337959-CW-RFB / Component 3. Strengthenin Request for Bids Travaux de construction des g capacities for engaging in Single Stage - One - Works French C Under Impl 2023-04-2 2023-04-2 2023-04-2 2023-05-2 2023-05-2 2023-06-1 2023-07-1 2023-09- bâtiments abritant la machi IDA / 59870 Post Request for Bids Open - National 198,000.00 0.00 alternative fishing practices Envelope ivil Law (French) ementation 9 8 9 2 9 2 0 29 ne à glace et magasin de st and livelihoods activities SPD ockage dans le district de N osy be répartis en 2 lots GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) atus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-28121-GO-UN// M Component 2. Strengthenin UN Agencies (Dir 2017-09-3 2017-10-2 2017-12-2 2018-06-2 G-PM-01 / Matériels et équip IDA / 59870 g capacities for priority fish Post Direct 315,310.00 0.00 Canceled ect) 0 1 3 1 ements informatiques et bur eries management eautiques MG-MRHP-28129-GO-RFB// Component 2. Strengthenin MG-PM-02 / Kits d'équipeme Open - Internation Single Stage - Two 2017-10-1 2017-11-0 2017-12-1 2018-03-0 2018-04-1 2018-10-1 IDA / D1720 g capacities for priority fish Post Request for Bids 17,500.00 0.00 Canceled nts pour les enquêteurs (sa al Envelope 5 5 7 8 9 6 eries management c de couchage, tente, torche , bottes, impermeable) MG-MRHP-28136-GO-UN//M Component 2. Strengthenin UN Agencies (Dir Pending Imp 2017-09-3 2017-10-2 2017-12-2 2018-06-2 G-PM-03 / Acquisition de Vé IDA / 59870 g capacities for priority fish Post Direct 1,830,000.00 0.00 ect) lementation 0 1 3 1 hicule eries management MG-MRHP-28157-GO-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2017-10-3 2017-11-2 2018-01-0 2018-03-2 2018-05-0 2018-11-0 MG-PM-05 / Acquisition de fo IDA / 59870 g capacities for priority fish Post Request for Bids 29,170.00 0.00 Canceled al Envelope 0 0 4 6 7 3 urnitures et articles de bure eries management au MG-MRHP-28158-GO-UN//M Component 2. Strengthenin UN Agencies (Dir Pending Imp 2017-09-3 2017-10-2 2017-12-2 2018-06-2 G-PM-06 / Acquisition de Mot IDA / 59870 g capacities for priority fish Post Direct 59,000.00 0.00 ect) lementation 0 1 3 1 o eries management MG-MRHP-28159-GO-UN//M Component 2. Strengthenin UN Agencies (Dir 2017-10-1 2017-11-0 2018-01-0 2018-07-0 G-PM-07 / Acquisition de Dro IDA / D1720 g capacities for priority fish Post Direct 5,000.00 0.00 Canceled ect) 6 6 8 7 ne pour surveillance et contr eries management ôle MG-MRHP-28160-GO-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2017-10-3 2017-11-2 2018-01-0 2018-03-2 2018-05-0 2018-11-0 MG-PM-08 / Acquisition de M IDA / 59870 g capacities for priority fish Post Request for Bids 120,000.00 0.00 Canceled al Envelope 0 0 4 6 7 3 atériels et Mobiliers de bure eries management au MG-MRHP-28161-GO-RFB// MG-PM-09 / Appui à la mise Component 3. Strengthenin à disposition des équipemen g capacities for engaging in Open - Internation Single Stage - Two 2017-11-1 2017-12-0 2018-01-2 2018-04-1 2018-05-2 2018-11-1 IDA / 59870 Post Request for Bids 65,000.00 0.00 Canceled ts de base pour la sécurité d alternative fishing practices al Envelope 5 6 0 1 3 9 es pêcheurs et de leurs emb and livelihoods activities arcations en mer (gilet, miro ir... pour la période transitoir e) MG-MRHP-28162-GO-RFB// Component 2. Strengthenin Single Stage - One 2017-11-1 2017-12-0 2018-01-2 2018-02-1 2018-04-0 2018-09-2 MG-PM-10 / Acquisition de C IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 25,170.00 0.00 Canceled Envelope 5 6 0 9 2 9 onsommables informatiques eries management (Lot) MG-MRHP-28397-GO-RFB// Component 2. Strengthenin MG-MP-89 / Acquisition et in Open - Internation Single Stage - Two 2018-06-1 2018-06-2 2018-08-1 2018-11-0 2018-12-1 2019-06-1 IDA / D1720 g capacities for priority fish Post Request for Bids 150,000.00 0.00 Canceled stallation d'un logiciel de sui al Envelope 5 9 3 2 4 2 eries management vi automatique des captures (ERS) MG-MRHP-28401-GO-RFB// Component 3. Strengthenin MG-PM-90 / Matériels de bur g capacities for engaging in Open - Internation Single Stage - Two 2018-06-1 2018-06-2 2018-08-1 2018-11-0 2018-12-1 2019-06-1 eau du CFTP (06 lots compo IDA / 59870 Post Request for Bids 6,000.00 0.00 Canceled alternative fishing practices al Envelope 5 9 3 2 4 2 sés de table de bureau, chai and livelihoods activities se de bureau, chaise visiteu se et armoire ) MG-MRHP-28406-GO-RFB// MG-PM-93 / Acquisition des Component 3. Strengthenin équipements de base pour l g capacities for engaging in Open - Internation Single Stage - Two 2018-01-3 2018-02-1 2018-03-3 2018-06-1 2018-07-3 2019-01-2 IDA / 59870 Post Request for Bids 100,000.00 0.00 Canceled a sécurité des pêcheurs et d alternative fishing practices al Envelope 0 3 0 9 1 7 e leurs embarcations en mer and livelihoods activities (gilet, miroir... pour la périod e transitoire) MG-MRHP-28415-GO-RFB// Component 3. Strengthenin MG-PM-96 / Acquisition d'out g capacities for engaging in Single Stage - Two 2018-03-3 2018-04-1 2018-05-2 2018-08-1 2018-09-2 2019-03-2 IDA / 59870 Post Request for Bids Open - National 19,000.00 0.00 Canceled illage pour les pépinières et alternative fishing practices Envelope 0 3 8 7 8 7 les reboisements (brouette,. and livelihoods activities ...) Page 2 MG-MRHP-28431-GO-RFB// MG-PM-100 / Acquisition de Component 3. Strengthenin mobiliers de bureau pour Ge g capacities for engaging in Single Stage - Two 2018-05-1 2018-05-2 2018-07-1 2018-10-0 2018-11-1 2019-05-1 stion et mise en œuvre : (0 IDA / V0500 Post Request for Bids Open - National 40,000.00 0.00 Canceled alternative fishing practices Envelope 5 9 3 2 3 2 3 lots composés de 01 table and livelihoods activities de bureau, 01 chaise de bur eau, 02 chaises visiteurs et 01 armoire de rangement se mi vitré ) MG-MRHP-23399-GO-UN / A Component 2. Strengthenin UN Agencies (Dir 2017-08-1 2017-09-0 2017-11-0 2018-05-0 chat de lot de Matériel infor IDA / Q9790 g capacities for priority fish Post Direct 201,660.00 0.00 Canceled ect) 5 5 7 6 matique (Année 2017) eries management Component 3. Strengthenin MG-MRHP-85764-GO-RFQ // g capacities for engaging in Request for Quot Single Stage - One 2018-12-1 2019-04-1 2019-10-1 MG-PM 18/18 / Achat de 79 IDA / 59870 Post Limited 3,950.00 0.00 Canceled alternative fishing practices ations Envelope 5 4 1 boites à plaintes and livelihoods activities MG-MRHP-28404-GO-RFB// Component 3. Strengthenin MG-PM-91 / Acquisition d'éq g capacities for engaging in Open - Internation Single Stage - Two 2019-07-1 2019-07-3 2019-09-1 2019-12-0 2020-01-1 2020-07-1 IDA / 59870 Post Request for Bids 320,000.00 0.00 Canceled uipements et outils de pêch alternative fishing practices al Envelope 6 0 3 3 4 2 e and livelihoods activities MG-MRHP-28405-GO-RFB// Component 3. Strengthenin MG-PM-92 / Acquisition d'out g capacities for engaging in Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06-2 IDA / 59870 Post Request for Bids 185,000.00 0.00 Canceled illage d'entretien d'engin et alternative fishing practices al Envelope 1 5 9 8 0 7 d'embarcation de pêche pou and livelihoods activities r usage communautaire MG-MRHP-119305-GO-RFQ / Component 3. Strengthenin Appui à l'acquisition de mat g capacities for engaging in Request for Quot Single Stage - One 2019-07-0 2019-08-3 2020-02-2 IDA / 59870 Post Limited 100,000.00 0.00 Canceled ériels de sécurité aux pêche alternative fishing practices ations Envelope 6 1 7 urs et communauté de pêch and livelihoods activities eurs : 2000 Component 3. Strengthenin MG-MRHP-28410-GO-RFB// g capacities for engaging in Open - Internation Single Stage - Two 2018-05-1 2018-05-2 2018-07-1 2018-10-0 2018-11-1 2019-05-1 MG-PM-94 / Acquisition d'out IDA / 59870 Post Request for Bids 80,000.00 0.00 Canceled alternative fishing practices al Envelope 5 9 3 2 3 2 ils de valorisation and livelihoods activities MG-MRHP-28411-GO-RFB// Component 3. Strengthenin MG-PM-95 / Acquisition des g capacities for engaging in Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06-2 IDA / 59870 Post Request for Bids 80,000.00 0.00 Canceled petits matériels de valorisati alternative fishing practices al Envelope 1 5 9 8 0 7 on and livelihoods activities Component 3. Strengthenin MG-MRHP-119309-GO-RFQ / g capacities for engaging in Request for Quot Single Stage - One 2019-06-2 2019-08-1 2019-07-1 2020-02-1 2019-08-1 IDA / 59870 Post Open - National 5,250.00 7,885.75 Completed Achat boites à plaintes : 105 alternative fishing practices ations Envelope 3 8 6 4 4 and livelihoods activities Component 3. Strengthenin MG-MRHP-119311-GO-RFQ / g capacities for engaging in Request for Quot Single Stage - One 2019-07-2 2019-10-0 2019-09-1 2020-01-1 2020-03-1 2020-02-0 Achat puce et téléphone por IDA / 59870 Post Limited 5,250.00 11,213.00 Completed alternative fishing practices ations Envelope 0 9 4 1 2 1 table : 105 and livelihoods activities MG-MRHP-28121-GO-UN// M Component 2. Strengthenin Request for Prop Single Stage - One 2019-07-3 2019-09-1 2019-08-2 2019-10-0 2019-10-0 2019-11-0 2019-11-0 2020-04-1 2019-12-1 2020-06-1 2020-06-1 2020-09-2 G-PM-01-2 / Matériels inform IDA / 59870 g capacities for priority fish Post Open - National 156,370.00 141,053.48 Completed osals Envelope 1 4 1 9 2 8 1 5 3 0 0 8 atiques 2019 eries management MG-MRHP-86177-GO-RFQ// Component 2. Strengthenin MG-PM 08/18 / Achat téléph Request for Quot Single Stage - One 2019-08-2 2019-07-2 2020-01-0 2019-09-0 2020-07-0 2019-09-2 IDA / V0500 g capacities for priority fish Post Limited 10,500.00 10,073.72 Completed one mobile pour la collecte ations Envelope 4 4 6 4 4 5 eries management de données au niveau natio nal MG-MRHP-28160-GO-RFB// Component 2. Strengthenin Request for Quot Single Stage - One 2019-07-2 2019-08-2 2019-09-1 2019-09-0 2020-03-1 2019-09-1 MG-PM-08-2 / Matériels et m IDA / 59870 g capacities for priority fish Post Limited 33,200.00 19,057.68 Completed ations Envelope 0 9 4 5 2 0 obiliers de bureau 2019 eries management MG-MRHP-28161-GO-RFB// MG-PM-09-2 / Appui à la mis Component 3. Strengthenin e à disposition des équipem g capacities for engaging in Single Stage - One 2019-07-1 2019-09-1 2019-07-2 2019-10-0 2019-08-3 2019-11-0 2019-09-3 2019-11-0 2020-05-0 ents de base pour la sécurit IDA / 59870 Post Request for Bids Open - National 330,000.00 0.00 Canceled alternative fishing practices Envelope 5 6 0 9 1 8 0 4 2 é des pêcheurs et de leurs e and livelihoods activities mbarcations en mer (gilet, miroir… pour la période tran sitoire) : 3300 MG-MRHP-28161 BIS-GO-RF Component 3. Strengthenin B // MG-PM-09-2 / Acquisitio g capacities for engaging in Single Stage - One 2019-12-2 2019-12-3 2019-12-2 2019-12-3 2020-01-2 2020-01-3 2020-02-1 2020-04-0 2020-03-0 2020-04-2 2020-06-0 n de 3300 kits de sécurité e IDA / 59870 Post Request for Bids Open - National 330,000.00 106,992.01 Signed alternative fishing practices Envelope 0 1 7 1 6 1 6 7 4 8 2 n mer pour les petits pêcheu and livelihoods activities rs (gilet, miroir… pour la pér iode transitoire) MG-MRHP-160447-GO-RFQ / Component 2. Strengthenin Fourniture des plaques d'im Request for Quot Single Stage - One 2020-03-1 2020-08-2 2020-04-1 2020-11-0 2020-05-1 2020-12-1 IDA / 59870 g capacities for priority fish Post Limited 100,000.00 18,218.09 Completed matriculations des pirogues ations Envelope 1 5 5 4 5 8 eries management (lot unique et indivisible) MG-MRHP-161268-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2020-02-2 2020-02-1 2020-03-0 2020-03-0 2020-03-1 Fourniture des carnets d'exp IDA / 59870 g capacities for priority fish Post Limited 8,400.00 8,166.14 Signed ations Envelope 7 8 6 5 3 édition des produits halieuti eries management ques MG-MRHP-127597-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2020-09-1 2020-12-1 2021-06-0 200 équipements et outils d IDA / 59870 g capacities for priority fish Post Limited 40,000.00 0.00 ations Envelope lementation 1 1 9 e pêches eries management MG-MRHP-119304-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2020-08-0 2020-09-2 2021-03-2 Matériels de l'électrification IDA / 59870 g capacities for priority fish Post Limited 9,000.00 0.00 ations Envelope lementation 4 9 8 hors grille : 03 eries management MG-MRHP-119300BIS-GO-R Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2019-06-0 2019-08-2 2020-02-2 FQ / Acquisition d'une Vedet TF / A4588 g capacities for priority fish Post Limited 100,000.00 0.00 ations Envelope lementation 8 6 2 te pour appui CSP eries management Component 3. Strengthenin MG-MRHP-85764 BIS-GO-RF g capacities for engaging in Request for Quot Single Stage - One 2020-05-1 2020-05-0 2020-07-0 2020-06-1 2020-08-0 Q / Achat de 155 boites à pl IDA / 59870 Post Limited 12,000.00 11,910.86 Signed alternative fishing practices ations Envelope 3 8 8 0 7 aintes pour l'exercice 2020 and livelihoods activities MG-MRHP-174399-GO-RFQ / Component 3. Strengthenin Acquisition de 160 téléphon g capacities for engaging in Request for Quot Single Stage - One Under Imple 2020-05-3 2020-06-0 2020-07-2 2020-08-2 IDA / 59870 Post Limited 15,000.00 0.00 es mobiles pour le Mécanis alternative fishing practices ations Envelope mentation 1 3 6 5 me De Gestion des Plaintes and livelihoods activities (MDGP) / Exercice 2020 MG-MRHP-119314-GO-RFQ / Component 3. Strengthenin Achat de vedette pour la mi g capacities for engaging in Request for Quot Single Stage - One 2020-07-2 2020-09-1 2021-03-1 IDA / 59870 Post Limited 80,000.00 0.00 Canceled se en œuvre des activités d alternative fishing practices ations Envelope 0 4 3 ans la région Melaky :1 and livelihoods activities MG-MRHP-119300-GO-RFB / Acquisition de Cinq (05) Ved ettes pour CSP réparties en deux (02) lots: Component 2. Strengthenin - Lot 01: Acquisition de 03 V Single Stage - One 2020-04-1 2020-04-2 2020-06-0 2020-07-0 2020-08-0 2021-02-0 TF / A4588 g capacities for priority fish Post Request for Bids Open - National 321,500.00 0.00 Canceled edettes pour appuyer le CSP Envelope 5 0 1 1 5 1 eries management pour les nouvelles antennes au niveau des ZUP; - Lot 02: Acquisition de 02 v edettes rapides semi-rigides pour patrouilleurs MG-MRHP-119300BIS1-GO- RFB / Acquisition des vedett es réparties en 02 Lots : Component 2. Strengthenin Single Stage - One Under Imple 2020-06-1 2020-06-1 2020-06-1 2020-06-1 2020-07-1 2020-08-1 2020-09-1 2020-12-1 • Lot1 : 07 vedettes coque IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 551,500.00 0.00 Envelope mentation 5 2 6 9 6 5 9 8 s rigides ; eries management • Lot2 : 02 vedettes rapid es semi-rigides. MG-MRHP-28415-GO-RFB // Component 3. Strengthenin MG-PM-96 BIS / Outillage po g capacities for engaging in Request for Quot Single Stage - One 2020-04-2 2020-06-1 2020-12-1 IDA / 59870 Post Limited 19,000.00 0.00 Canceled ur les pépinières et les reboi alternative fishing practices ations Envelope 0 5 2 sements (brouette,….) : 19 and livelihoods activities MG-MRHP-14629-GO-RFQ// Component 2. Strengthenin Request for Quot Single Stage - One 2020-09-2 2021-03-2 2020-11-1 2021-04-1 2020-12-1 PA 2 / PA2: Acquisition d'un l IDA / Q9790 g capacities for priority fish Post Limited 11,000.00 4,352.99 Signed ations Envelope 9 6 7 6 7 ot de matériels de formation eries management et d'enquête MG-MRHP-119240-GO-RFB / Component 2. Strengthenin Renforcement du Centre de Single Stage - Two 2020-07-3 2020-08-0 2020-09-1 2020-11-2 2021-01-0 2021-07-0 IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 580,000.00 0.00 Canceled Développement de l'Aquacul Envelope 0 4 5 8 2 1 eries management ture (CDA) -Equipement der echerche MG-MRHP-188316-GO-RFB / Component 3. Strengthenin Fourniture et livraison de 11 g capacities for engaging in Open - Internation Single Stage - One 2020-08-1 2020-08-2 2020-08-1 2020-08-2 2020-09-2 2020-10-2 2020-10-1 2020-11-1 2020-11-1 2021-01-1 2021-01-1 IDA / 59870 Post Request for Bids 1,170,000.00 432,020.22 Signed .700 lots d'équipements de alternative fishing practices al Envelope 4 6 5 6 9 0 4 3 1 9 0 base pour la sécurité en mer and livelihoods activities MG-MRHP-192172-GO-RFQ / Achat de 15.000 Caches bou Component 4. Project mana Request for Quot Single Stage - One 2020-09-2 2020-11-1 2021-05-1 IDA / 59870 Post Limited 11,500.00 0.00 Canceled che avec logo SWIOFish2 po gement and coordination ations Envelope 2 7 6 ur les trois (03) UGL's et l'U GP du projet SWIOFish2 MG-MRHP-119300 RELANCE -GO-RFB / Acquisition des ve Component 2. Strengthenin Single Stage - One Under Imple 2021-01-1 2021-02-1 2021-01-2 2021-02-1 2021-03-0 2021-03-2 2021-04-0 2021-05-1 2021-11-0 dettes réparties en 02 Lots : IDA / 59870 g capacities for priority fish Post Request for Bids Limited 551,500.00 0.00 Envelope mentation 9 5 4 6 7 2 6 1 7 • Lot1 : 07 vedettes coques eries management rigides ; • Lot2 : 02 vedettes rapides semi-rigides. MG-MRHP-218714-GO-RFB / Component 2. Strengthenin Single Stage - One 2021-03-0 2021-03-3 2021-03-0 2021-04-0 2021-04-0 2021-05-0 2021-05-0 2021-07-1 2021-06-0 2021-11-0 2021-08-2 Acquisition des matériels inf IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 316,100.00 402,663.35 Signed Envelope 1 0 6 6 5 3 5 6 9 6 3 ormatiques 2020 et 2021 eries management MG-MRHP-119306-GO-RFQ / Component 3. Strengthenin Appui en biens et équipeme g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2021-03-1 2021-05-0 2021-11-0 nts des groupements formel IDA / 59870 Post Limited 6,400.00 0.00 alternative fishing practices ations Envelope lementation 4 9 5 s: 32/ répartis en 2 Lots: Lot and livelihoods activities 1: Glacières; Lot 2: Couteau x MG-MRHP-203606-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2021-03-2 2021-05-2 2021-04-2 2021-07-1 2021-05-0 Acquisitions des téléphones IDA / 59870 g capacities for priority fish Post Open - National 19,200.00 17,632.53 Completed ations Envelope 0 9 0 3 1 mobiles pour l'UGP- SRPA et eries management RPA MG-MRHP-222323-GO-RFQ / Component 2. Strengthenin Acquisition d'une vedette et Request for Quot Single Stage - One Pending Imp 2021-04-0 2021-06-2 2021-09-0 IDA / 59870 g capacities for priority fish Post Limited 45,000.00 0.00 des autres équipements pou ations Envelope lementation 5 3 6 eries management r la prospections de nouvell e zone de pêche MG-MRHP-216847-GO-RFB / Component 3. Strengthenin Achat, installation et mainte g capacities for engaging in Open - Internation Single Stage - One 2021-04-1 2021-03-3 2021-04-2 2021-03-3 2021-06-0 2021-05-1 2021-06-2 2021-09-1 2021-07-3 2021-10-2 2022-01-2 IDA / 59870 Post Request for Bids 1,615,000.00 1,541,854.13 Signed nance d'équipements photo alternative fishing practices al Envelope 5 0 0 1 4 7 5 3 0 3 6 voltaïque pour 20 kiosques and livelihoods activities multiservices MG-MRHP-224078-GO-RFB / Component 3. Strengthenin Achat, installation et mainte g capacities for engaging in Open - Internation Single Stage - One 2021-04-1 2021-03-3 2021-04-2 2021-03-3 2021-06-0 2021-05-1 2021-07-0 2021-07-1 2021-08-0 2021-10-1 2022-02-0 IDA / 59870 Post Request for Bids 990,300.00 873,533.21 Signed nance d'équipements frigorif alternative fishing practices al Envelope 5 0 0 1 4 8 4 2 8 6 4 iques et de glace pour 20 ki and livelihoods activities osques multiservices MG-MRHP-227238-GO-RFB / Component 3. Strengthenin Fourniture et livraison des é g capacities for engaging in Open - Internation Single Stage - One 2021-05-1 2021-05-1 2021-05-2 2021-05-1 2021-07-0 2021-07-1 2021-07-3 2021-11-3 2021-09-0 2022-01-1 2022-03-0 IDA / 59870 Post Request for Bids 1,200,000.00 780,301.00 Signed quipements de base pour la alternative fishing practices al Envelope 5 7 0 8 1 9 1 0 4 7 3 sécurité en mer pour l'anné and livelihoods activities e 2021 et 2022 MG-MRHP-231608-GO-RFB / Component 2. Strengthenin Open - Internation Single Stage - One 2021-05-1 2022-05-1 2021-05-1 2022-05-1 2021-06-3 2022-06-3 2021-07-3 2022-09-1 2021-09-0 2022-03-0 Matériels et équipements po IDA / V0500 g capacities for priority fish Post Request for Bids 680,000.00 0.00 Signed al Envelope 4 0 9 6 0 0 0 3 3 2 ur laboratoire CEDP-CDA et eries management USTA Page 3 MG-MRHP-119240 BIS-GO-R Component 2. Strengthenin FB / Renforcement du Centr Single Stage - One 2021-03-2 2021-03-3 2021-04-3 2021-05-3 2021-07-0 2021-10-0 IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 580,000.00 0.00 Canceled e de Développement de l'Aq Envelope 6 1 0 0 4 2 eries management uaculture (CDA) -Equipemen t de recherche MG-MRHP-28156-GO-UN//-M Component 2. Strengthenin UN Agencies (Dir 2020-11-0 2020-11-2 2021-01-2 2021-07-2 G-PM-04 / Matériels et équip IDA / 59870 g capacities for priority fish Post Direct 50,000.00 0.00 Canceled ect) 2 3 5 4 ements pour laboratoire CE eries management DP MG-MRHP-232523-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2021-05-2 2021-07-2 2021-10-0 Acquisition d'une vedette fri IDA / 59870 g capacities for priority fish Post Limited 73,000.00 0.00 ations Envelope lementation 5 0 3 gorifique CDPHM eries management MG-MRHP-231602-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2021-05-2 2021-07-2 2022-01-1 Acquisition de Drones pour IDA / D1720 g capacities for priority fish Post Limited 26,000.00 0.00 ations Envelope lementation 5 0 6 CSC, formation et service ap eries management rès vente MG-MRHP-232525-GO-RFQ / Component 2. Strengthenin Acquisition des matériels ro Request for Quot Single Stage - One Pending Imp 2021-05-2 2021-07-2 2021-10-1 IDA / 59870 g capacities for priority fish Post Open - National 86,000.00 0.00 ulants ( 02 camions Frigorifi ations Envelope lementation 6 1 9 eries management ques de capacité 5 tonnes) pour les sites du CDPHM MG-MRHP-232534-GO-RFQ / Component 4. Project mana Request for Quot Single Stage - One 2021-05-2 2021-12-0 2021-07-2 2022-03-1 2022-01-1 Acquisition et installation d' IDA / Q9790 Post Open - National 50,000.00 20,955.96 Signed gement and coordination ations Envelope 5 9 0 2 6 un logiciel de suivi évaluatio n MG-MRHP-119295-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2021-03-1 2021-05-1 2021-11-0 Achat de Lot d'équipements IDA / 59870 g capacities for priority fish Post Limited 10,000.00 0.00 Canceled ations Envelope 5 0 6 pour laboratoire USTA eries management MG-MRHP-119300 RELANCE Component 2. Strengthenin LOT2-GO-RFB / Acquisition d Single Stage - One 2021-11-3 2021-12-1 2021-12-0 2021-12-2 2021-12-3 2022-03-1 2022-01-3 2022-03-0 2022-06-0 TF / A4588 g capacities for priority fish Post Request for Bids Open - National 170,000.00 0.00 Canceled e 02 vedettes rapides semi-r Envelope 0 7 1 1 1 0 0 6 4 eries management igides pour CSP (Relance Lot 2) MG-MRHP-262317-GO-RFQ / Component 2. Strengthenin Acquisition des matériels inf Request for Quot Single Stage - One 2021-12-0 2021-12-0 2022-01-3 2022-04-3 IDA / 59870 g capacities for priority fish Post Open - National 93,600.00 0.00 Canceled ormatiques 2020 et 2021 (re ations Envelope 5 9 0 0 eries management lance lot 8: tablettes) MG-MRHP-284470-GO-RFQ / Component 2. Strengthenin Single Stage - One Under Imple 2022-04-1 2022-05-0 2022-04-2 2022-05-3 2022-06-0 2022-07-0 2022-08-0 2023-02-0 Acquisition mobiliers de bur IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 427,553.00 0.00 Envelope mentation 5 6 0 0 1 1 5 1 eau pour les bureaux admini eries management stratifs 2022-2023 Component 3. Strengthenin MG-MRHP-28421-GO-RFB// g capacities for engaging in Single Stage - One Pending Imp 2020-09-1 2020-09-2 2020-11-0 2020-12-0 2021-01-0 2021-07-0 MG-PM-99 / Acquisition des IDA / V0500 Post Request for Bids Open - National 500,000.00 0.00 alternative fishing practices Envelope lementation 7 2 3 3 7 6 kits de panneaux solaires and livelihoods activities MG-MRHP-119315-GO-RFQ / Component 3. Strengthenin Renforcement de l'unité de g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-05-0 2022-06-3 2022-12-2 IDA / 59870 Post Limited 55,000.00 0.00 gestion communautaire en b alternative fishing practices ations Envelope lementation 5 0 7 iens et équipements : 22 and livelihoods activities MG-MRHP-289660-GO-RFQ / Component 3. Strengthenin Équipements et outils de for g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-04-2 2022-06-1 2022-12-1 IDA / 59870 Post Open - National 100,000.00 0.00 mation de technique de pêc alternative fishing practices ations Envelope lementation 3 8 5 he: palangre and livelihoods activities MG-MRHP-289646-GO-RFQ / Component 3. Strengthenin Equipement pour la commer g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-04-2 2022-06-1 2022-12-1 IDA / 59870 Post Open - National 40,000.00 0.00 cialisation des produits de p alternative fishing practices ations Envelope lementation 1 6 3 êche and livelihoods activities MG-MRHP-231589-GO-RFQ / Component 2. Strengthenin Acquisition de 20 tablettes Request for Quot Single Stage - One Pending Imp 2022-07-0 2022-08-3 2022-10-3 IDA / V0500 g capacities for priority fish Post Open - National 37,000.00 0.00 marinisées pour le Centre d ations Envelope lementation 6 1 0 eries management e Surveillance de Pêche MG-MRHP-119303-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2022-11-0 2023-01-0 2023-06-3 Dotation et moyens d'équip TF / A4588 g capacities for priority fish Post Limited 48,000.00 0.00 ations Envelope lementation 6 1 0 ement pour les membres du eries management CSC : 24 MG-MRHP-119300_2ÈME RE Component 2. Strengthenin LANCE LOT2-GO-RFB / Acqui Open - Internation Single Stage - One Under Imple 2022-05-3 2022-05-2 2022-06-0 2022-05-2 2022-07-1 2022-07-1 2022-08-0 2022-09-1 2022-12-1 TF / A4588 g capacities for priority fish Post Request for Bids 170,000.00 0.00 sition de 02 vedettes rapide al Envelope mentation 0 3 4 5 9 1 9 3 2 eries management s semi-rigides pour CSP MG-MRHP-262317-GO-RFQ- 2ÈME RELANCE / ACQUISITI Component 2. Strengthenin ON DES TABLETTES POUR C Request for Quot Single Stage - One Pending Imp 2022-06-0 2022-07-1 2022-09-1 IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 ENTRE DE SURVEILLANCE D ations Envelope lementation 4 6 4 eries management E PÊCHE, STATISTIQUE ET 1 3 RÉGIONS CÔTIÈRES DE L’U GP SWIOFISH2 MG-MRHP-296825-GO-RFQ / Component 2. Strengthenin Acquisition des smartphones Request for Quot Single Stage - One 2022-06-1 2022-10-2 2022-08-0 2022-09-0 TF / A4588 g capacities for priority fish Post Open - National 30,000.00 0.00 Signed pour la collecte des données ations Envelope 3 7 8 7 eries management pour le Service d'Etude MPE B MG-MRHP-119299-GO-RFQ / Matériels d'échantillonnages Component 2. Strengthenin Request for Quot Single Stage - One Under Imple 2022-06-2 2023-04-1 2022-08-1 2022-08-2 pour Services d'Etudes (Ex- TF / A4588 g capacities for priority fish Post Open - National 40,000.00 0.00 ations Envelope mentation 1 2 6 2 USTA) et Enquêteurs pour St eries management atistique et Kit d'Inspection pour CSP MG-MRHP-256429-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2021-10-2 2021-12-0 2021-12-1 2022-01-1 Acquisition de 20 VTT pour l TF / A4588 g capacities for priority fish Post Open - National 6,000.00 0.00 Canceled ations Envelope 3 9 8 7 es antennes USTA eries management MG-MRHP-307043-GO-RFB / Fourniture, Installation, Mise en service et Maintenance d Component 3. Strengthenin e vingt-six (26) infrastructur g capacities for engaging in Open - Internation Single Stage - One Under Imple 2022-09-2 2022-10-3 2022-10-0 2022-10-3 2022-11-1 2022-12-1 2023-01-1 2023-07-1 IDA / 59870 Post Request for Bids 1,100,000.00 0.00 es frigorifiques dans les loca alternative fishing practices al Envelope mentation 9 1 4 1 5 5 9 8 lités de pêcheurs dans les Z and livelihoods activities ones Ultra Prioritaires (ZUP) sur deux (02) régions de MA DAGASCAR : ANALANJIROFO - DIANA MG-MRHP-307036-GO-RFB / Fourniture, Installation, Mise en service et Maintenance d Component 3. Strengthenin e vingt-six (26) infrastructur g capacities for engaging in Open - Internation Single Stage - One Under Imple 2022-09-2 2022-10-2 2022-10-0 2022-10-3 2022-11-1 2022-12-1 2022-12-1 2023-01-1 2023-07-1 IDA / 59870 Post Request for Bids 1,800,000.00 0.00 es énergétiques dans les loc alternative fishing practices al Envelope mentation 9 7 4 1 5 4 5 9 8 alités de pêcheurs dans les and livelihoods activities Zones Ultra Prioritaires (ZUP ) sur deux (02) régions de M ADAGASCAR : ANALANJIROF O - DIANA MG-MRHP-329768-GO-RFQ / Component 3. Strengthenin Acquisition matériels de co g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-12-1 2023-02-0 2023-08-0 IDA / 59870 Post Open - National 5,000.00 0.00 mmunication de la météo m alternative fishing practices ations Envelope lementation 5 9 8 arine: Panneau SAP - Téléph and livelihoods activities one solaire - radio VHF MG-MRHP-329336-GO-RFB / Outil et équipement de valor Component 3. Strengthenin isation et commercialisation g capacities for engaging in Single Stage - One Under Imple 2023-01-1 2023-02-0 2023-01-1 2023-02-0 2023-02-1 2023-03-1 2023-04-2 2023-07-1 IDA / 59870 Post Request for Bids Open - National 500,000.00 0.00 compose de 400 bicyclette à alternative fishing practices Envelope mentation 0 3 5 8 4 6 0 9 grande roue, 250 Glacière 5 and livelihoods activities 0litres et 150 bac ajouré 70li tre MG-MRHP-256423-GO-DIR / Component 2. Strengthenin 2022-05-0 2022-05-1 2022-06-1 2022-10-1 Acquisition de 33 motos 5 TF / A4588 g capacities for priority fish Post Direct Selection Direct 70,000.00 0.00 Canceled 6 1 5 3 motos eries management MG-MRHP-332050-GO-RFB / Acquisition des matériels ro Component 2. Strengthenin Single Stage - One Under Imple 2023-01-1 2023-02-0 2023-01-1 2023-02-0 2023-02-1 2023-03-0 2023-04-1 2023-07-1 ulants répartis en 2 Lots: IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 495,000.00 0.00 Envelope mentation 0 3 5 6 4 7 1 0 • Lot 01: 05 véhicules 4*4 eries management • Lot 02: 45 motos MG-MRHP-338246-GO-RFB / Component 2. Strengthenin Open - Internation Single Stage - One Under Imple 2023-02-0 2023-02-1 2023-02-0 2023-02-1 2023-03-1 2023-03-1 2023-03-1 2023-05-2 2023-03-2 2023-07-2 Acquisition de matériels info IDA / 59870 g capacities for priority fish Post Request for Bids 490,000.00 0.00 al Envelope mentation 3 0 8 3 0 3 5 5 5 3 rmatiques 2022 et 2023 eries management MG-MRHP-331442-GO-RFB / La fourniture, Livraison, Inst allation et Mise en service d Component 3. Strengthenin e 200 lampadaires solaires g capacities for engaging in Single Stage - One Under Imple 2023-01-1 2023-02-1 2023-01-1 2023-02-1 2023-02-1 2023-03-0 2023-03-1 2023-08-0 IDA / 59870 Post Request for Bids Open - National 140,000.00 0.00 dans les localités des Zones alternative fishing practices Envelope mentation 0 1 5 3 4 1 1 8 Ultra Prioritaires des pêcheu and livelihoods activities rs dans (03) trois Régions à Madagascar : MELAKY - DIA NA - ANALANJIROFO MG-MRHP-338964-GO-DIR / Component 3. Strengthenin Equipement et d'outils de pê g capacities for engaging in Under Imple 2023-01-3 2023-02-2 2023-02-0 2023-02-2 2023-02-2 2023-07-2 che: 20.000 kits composés d IDA / 59870 Post Direct Selection Direct - National 436,800.00 0.00 alternative fishing practices mentation 1 4 5 4 4 4 e palmes réglable, masque and livelihoods activities de plongé, tuba et sac de tr ansport MG-MRHP-338245-GO-RFB / Component 3. Strengthenin Outils de valorisation compo g capacities for engaging in Single Stage - One Under Imple 2023-02-0 2023-02-1 2023-02-0 2023-02-1 2023-03-1 2023-03-1 2023-03-1 2023-03-2 2023-03-2 2023-04-0 IDA / 59870 Post Request for Bids Open - National 650,000.00 0.00 sé de 325 broyeurs à disque alternative fishing practices Envelope mentation 3 0 8 3 0 3 5 8 5 3 , à percussion et de 125 pell and livelihoods activities etiseur à pédale MG-MRHP-338984-GO-RFB / La fourniture, Livraison, Inst allation et Mise en service d Component 3. Strengthenin e 20 kits de congélateurs sol g capacities for engaging in Single Stage - One Under Imple 2023-01-3 2023-02-1 2023-02-0 2023-02-1 2023-03-0 2023-03-1 2023-03-2 2023-08-2 IDA / 59870 Post Request for Bids Open - National 50,000.00 0.00 aires dans les localités des Z alternative fishing practices Envelope mentation 1 1 2 3 4 4 9 6 ones Ultra Prioritaires des p and livelihoods activities êcheurs dans (03) trois Régi ons à Madagascar , Region MELAKY - DIANA - ANALANJI ROFO MG-MRHP-346374-GO-RFQ / Component 3. Strengthenin Acquisition de 500 téléphon g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2023-03-1 2023-04-3 2023-06-2 IDA / 59870 Post Open - National 100,000.00 0.00 es solaires et 300 radios VH alternative fishing practices ations Envelope lementation 9 0 9 F and livelihoods activities MG-MRHP-346378-GO-DIR / Fourniture et installation, Fo rmation des points focaux et Component 3. Strengthenin accompagnement pour la mi g capacities for engaging in Under Imple 2023-03-1 2023-03-1 2023-03-1 2023-03-1 2023-04-1 2023-08-1 IDA / 59870 Post Direct Selection Direct - National 1,975,000.00 0.00 se en service de 3000 pann alternative fishing practices mentation 4 4 9 4 6 4 eaux agrometeorologique d and livelihoods activities e type MITAO FORECAST (pa nneaux SAP) dans les 14 rég ions côtières de Madagascar MG-MRHP-355024-GO-RFB / Component 3. Strengthenin Acquisition d'équipements p g capacities for engaging in Open - Internation Single Stage - One Pending Imp 2023-05-1 2023-05-2 2023-07-0 2023-07-1 2023-07-2 2023-09-2 our la mise en œuvre de l'Ac IDA / 59870 Post Request for Bids 1,920,000.00 0.00 alternative fishing practices al Envelope lementation 6 1 5 5 7 9 tivité Génératrice des Reven and livelihoods activities us ( AGR) pour les pêcheurs. Component 3. Strengthenin MG-MRHP-361766-GO-DIR / g capacities for engaging in Pending Imp 2023-05-1 2023-05-2 2023-06-1 2023-08-2 Acquisition des divers matér IDA / 59870 Post Direct Selection Direct - National 900,000.00 0.00 alternative fishing practices lementation 8 8 2 6 iels de pêches and livelihoods activities MG-MRHP-362169-GO-RFB / Component 3. Strengthenin Acquisition et installation de g capacities for engaging in Single Stage - One Pending Imp 2023-05-2 2023-05-3 2023-06-2 2023-07-0 2023-07-1 2023-09-0 s matériels et équipements IDA / 59870 Post Request for Bids Open - National 290,000.00 0.00 alternative fishing practices Envelope lementation 5 0 9 4 1 9 pour le fonctionnement des i and livelihoods activities nfrastructures construites Page 4 MG-MRHP-362172-GO-RFB / Component 3. Strengthenin Renforcement de l'unité de g capacities for engaging in Single Stage - One Pending Imp 2023-05-2 2023-05-3 2023-06-2 2023-07-0 2023-07-1 2023-09-0 IDA / 59870 Post Request for Bids Open - National 300,000.00 0.00 gestion communautaire en b alternative fishing practices Envelope lementation 5 0 9 4 1 9 iens et équipements; and livelihoods activities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) atus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-151759-NC-RFB / Component 2. Strengthenin Open - Internation Single Stage - One 2020-01-0 2020-01-2 2020-01-1 2020-01-2 2020-02-2 2020-03-1 2020-02-2 2020-06-1 2020-03-2 2020-11-2 2020-05-2 Analyse PC de l'eau de traite IDA / 59870 g capacities for priority fish Post Request for Bids 110,000.00 186,954.22 Signed al Envelope 6 9 1 9 5 6 6 5 2 6 1 ment ou de production (lot eries management N°1) MG-MRHP-151759BIS1-NC- Component 2. Strengthenin RFQ / Analyses officielles po Request for Quot Single Stage - One Pending Imp 2019-08-1 2019-10-2 2019-12-2 IDA / 59870 g capacities for priority fish Post Limited 100,000.00 0.00 ur le compte de l'Autorité Sa ations Envelope lementation 0 8 7 eries management nitaire Halieutique (ASH) rép artie en 9 Lots MG-MRHP-192432-NC-RFB / Analyses officielles relatives au contrôle de la qualité phy sico-chimique des eaux de tr Component 2. Strengthenin Open - Internation Single Stage - One Under Imple 2020-09-2 2021-10-1 2020-09-2 2021-10-1 2020-11-1 2021-12-0 2020-12-0 2021-01-0 2021-04-0 aitement et de production et IDA / 59870 g capacities for priority fish Post Request for Bids 309,750.00 0.00 al Envelope mentation 2 3 7 3 1 7 2 2 2 des résidus chimiques et co eries management ntaminants dans les produit s de la pêche et d’aquacultu re, conformément aux plans de surveillance nationaux 2 02 MG-MRHP-192435-NC-DIR / Analyses officielles relatives à la Recherche de Vibrio pot Component 2. Strengthenin entiellement entéropathogè Pending Imp 2020-09-2 2020-09-2 2020-11-2 2021-02-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 7,860.00 0.00 nes dans les produits de la p lementation 2 7 5 3 eries management êche et d’aquaculture (crust acées : crabes et crevettes), conformément aux plans de surveillance nationaux 2020 MG-MRHP-196025-NC-DIR / Component 2. Strengthenin Diagnostic des maladies des Pending Imp 2020-10-0 2020-10-3 2020-11-2 2020-12-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 47,000.00 0.00 crustacés dans le cadre de l lementation 9 0 6 1 eries management a réalisation du Plan de Surv eillance 2020 MG-MRHP-231600-NC-DIR / Component 2. Strengthenin Acquisition et installation d' Under Imple 2021-05-2 2021-05-2 2021-07-1 2022-07-1 IDA / V0500 g capacities for priority fish Post Direct Selection Direct 37,000.00 0.00 équipement des deux Patro mentation 0 5 4 4 eries management uilleurs (Atsantsa et Telonify ) à bord des navires MG-MRHP-231592-NC-DIR / Extension de l’application d Component 2. Strengthenin 2021-05-2 2021-05-2 2021-05-2 2021-06-1 2021-07-1 2021-10-2 2022-07-1 u système ERS du Centre de IDA / V0500 g capacities for priority fish Post Direct Selection Direct 36,600.00 47,559.62 Signed 0 7 5 4 4 2 4 Surveillance des Pêches de eries management Madagascar aux navires nati onaux et étrangers hors-UE MG-MRHP-289369-NC-DIR / Analyse officielle en laborat Component 2. Strengthenin oire de dosage des substan Under Imple 2022-04-1 2022-04-2 2022-04-1 2022-04-2 2022-05-2 2022-11-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 30,000.00 0.00 ces interdites et résidus mé mentation 2 1 7 5 2 8 eries management dicamenteux et de dosage de résidus de pes ticides MG-MRHP-295994-NC-RFQ / ACHEMINEMENT DES PRELE VEMENTS DE PRODUITS DE LA PECHE POUR ANALYSES Component 2. Strengthenin OFFICIELLES DANS LE CADR Request for Quot Single Stage - One Pending Imp 2022-05-3 2022-07-2 2023-01-2 IDA / 59870 g capacities for priority fish Post Open - National 51,000.00 0.00 E DE LA REALISATION DES P ations Envelope lementation 0 5 1 eries management LANS DE SURVEILLANCE SA NITAIRES 2020 & 2021 DE L’ AUTORITE SANITAIRE HALIE UTIQUE JUSQU’AUX LABORA TOIRES ACCREDITES INTERN ATIONAUX RETENUS. Component 3. Strengthenin MG-MRHP-REG2022-NC-RFQ g capacities for engaging in Request for Quot Single Stage - One 2022-05-3 2022-05-3 2022-06-0 2022-06-0 2022-06-2 / Dédouanement de 20000 k IDA / 59870 Post Limited 100,000.00 93,478.02 Signed alternative fishing practices ations Envelope 1 1 6 8 1 it de sécurté en mer and livelihoods activities MG-MRHP-296834-NC-RFP / Firme pour la réparation des Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2022-06-2 2022-08-1 2023-02-1 imprimantes photocopieurs, IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 ations Envelope lementation 1 6 2 scanners, dupli copieurs,mat eries management ériels informatique et électr onique MG-MRHP-REG2020-NC-RFQ Component 4. Project mana Request for Quot Single Stage - One 2020-11-0 2020-11-0 2020-11-1 2020-11-2 2021-11-1 / Hébergement mail professi IDA / 59870 Post Limited 13,800.00 13,793.14 Signed gement and coordination ations Envelope 6 6 9 0 9 onnel du projet SWIOFish2 MG-MRHP-308415-NC-RFQ / Prestation de service en Age Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2022-11-0 2022-12-3 2023-06-2 nce de Voyage ( Billet d'avio IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 ations Envelope lementation 5 1 9 n) pour les voyages à l'étran eries management ger - Contrat Cadre Multi at tributaire de 12 mois- MG-MRHP-337984-NC-DIR / Component 2. Strengthenin Direct - Internatio Pending Imp 2023-01-2 2023-02-0 2023-03-0 2023-05-3 Support et Maintenance de l IDA / D1720 g capacities for priority fish Post Direct Selection 50,000.00 0.00 nal lementation 7 1 2 1 'application THEMIS-VMS pa eries management r CLS CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Interes Request for Proposal Opening of Technical Evaluation of Techni Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s t Notice s as Issued Proposals / Minutes cal Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-14498-CS-QCBS// PA-13 / PA 13: Mise à jour de Component 2. Strengthenin Quality And Cost- Open - Internation 2017-05-3 2017-07-2 2017-09-1 2017-09-1 2017-09-2 2017-10-2 2018-10-2 la Stratégie d'aquaculture et IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2017-05-16 Based Selection al 0 8 1 3 2 0 0 élaboration de plan de dével eries management oppement des 03 filières aq uaculture MG-MRHP-14951-CS-LCS//P A65 / PA 65: Etudes techniq ues : - Clôture de l'enceinte DRRH Component 2. Strengthenin P Fénérive Least Cost Select Open - Internation 2017-12-1 2017-05-3 2017-07-2 2018-03-1 2017-08-2 2018-04-1 2017-08-2 2018-04-2 2017-09-1 2018-05-0 2017-10-0 2018-07-0 2018-04-0 2019-07-2 IDA / Q9790 g capacities for priority fish Post 35,000.00 25,756.66 Completed 2017-05-17 - Construction des Bureaux ion al 9 1 2 9 1 7 8 4 1 7 9 3 7 4 eries management de 06 DRRHP - Extension de l'ASH à Antsir anana et Morondava - Construction local pour bur eau UGP MG-MRHP-23760-CS-QCBS// MG-PM-117 / Recrutement d' Component 3. Strengthenin un Cabinet d'étude ou d'une g capacities for engaging in Quality And Cost- 2017-10-3 2017-10-0 2018-08-2 2017-12-1 2018-09-1 2018-01-0 2019-02-0 2018-02-0 2019-07-0 2018-03-2 2019-08-1 2018-05-0 2019-09-2 2020-04-3 ONG pour assurer les missio IDA / Q9790 Prior Open - National 600,000.00 677,965.07 Signed 2017-09-14 alternative fishing practices Based Selection 0 5 9 0 8 7 7 6 8 0 6 1 4 0 ns de l'AGEX pour l'appui à l and livelihoods activities a mise en œuvre du Plan d'A ménagement des Pêcheries de la Baie d'Antongil MG-MRHP-27282-CS-QCBS// Component 2. Strengthenin Quality And Cost- Open - Internation 2017-09-2 2017-11-2 2017-12-2 2017-08-0 2018-01-2 2018-02-2 2018-04-0 2019-04-0 PA61 / Appui à la mise en pl IDA / Q9790 g capacities for priority fish Prior 500,000.00 0.00 Canceled 2017-09-07 Based Selection al 8 6 4 4 3 7 3 3 ace des outils d'aménageme eries management nt des pêches MG-MRHP-28166-CS-QCBS// Component 2. Strengthenin Quality And Cost- Open - Internation 2018-01-0 2018-03-1 2018-04-0 2018-05-2 2018-07-0 2018-08-1 2019-08-1 MG-PM-14 / Recueil et analy IDA / D1720 g capacities for priority fish Post 25,000.00 0.00 Canceled 2017-12-15 Based Selection al 5 2 9 4 5 6 6 se des informations de base eries management avant-projet MG-MRHP-28168-CS-QCBS// Component 2. Strengthenin MG-PM-16 / Collecte des don Quality And Cost- Open - Internation Pending Implem 2018-01-0 2018-03-1 2018-04-0 2018-05-2 2018-07-0 2018-08-1 2019-08-1 IDA / D1720 g capacities for priority fish Post 20,000.00 0.00 2017-12-15 nées au niveau des régions Based Selection al entation 5 2 9 4 5 6 6 eries management prioritaires (Artfish) MG-MRHP-28170-CS-CQS// MG-PM-18 / Identification de s besoins en formation et él Component 2. Strengthenin Consultant Qualif Open - Internation 2018-01-1 2018-03-1 2018-04-1 2018-05-3 2018-11-2 aboration du plan de formati IDA / 59870 g capacities for priority fish Post 20,000.00 0.00 Canceled 2017-12-22 ication Selection al 2 9 8 0 6 on des agents de l'administr eries management ation (y compris Inventaire et contact des centres de fo rmation locaux et extérieurs ) MG-MRHP-28171-CS-CQS// MG-PM-19 / Etude sur l'ident ification et recensement des Component 3. Strengthenin bénéficiaires chaque année, g capacities for engaging in Consultant Qualif Open - Internation 2017-10-2 2017-12-0 2018-02-1 2019-05-3 2018-03-2 2019-09-0 2018-05-0 2019-09-1 2018-11-0 2020-11-0 IDA / 59870 Post 200,000.00 159,792.61 Completed 2017-11-15 du montant et des modalité alternative fishing practices ication Selection al 4 6 0 1 7 6 8 8 4 2 s de transfert financier, du and livelihoods activities montant minimal de filet soc ial pour les pêcheurs/acteur s filières affectés par les me sures de gestion MG-MRHP-28174-CS-CQS// Component 3. Strengthenin MG-PM-22 / Étude sur le circ g capacities for engaging in Consultant Qualif Open - Internation 2019-06-1 2017-12-2 2018-02-2 2018-04-1 2018-05-2 2018-11-1 IDA / 59870 Post 90,000.00 0.00 Canceled 2017-11-30 uit de commercialisation des alternative fishing practices ication Selection al 7 1 5 1 3 9 produits des pêches and livelihoods activities MG-MRHP-28175-CS-CQS// MG-PM-23 / Étude et enquêt e sur l'état des lieux des acc Component 3. Strengthenin idents en mer de la petite p g capacities for engaging in Consultant Qualif Open - Internation 2019-02-2 2017-12-2 2018-02-2 2019-02-2 2018-04-1 2019-06-1 2018-05-2 2019-06-1 2018-11-1 êche et aux éventuelles mes IDA / 59870 Post 120,000.00 50,244.29 Signed 2017-11-30 alternative fishing practices ication Selection al 6 1 5 6 1 4 3 4 9 ures déjà prises/analyse de and livelihoods activities s accidentologies/aspect inst itutionnel sur les responsabil ités de la petite pêche/ à titr e provisoire proposer les éq uipements MG-MRHP-28319-CS-QCBS// Component 3. Strengthenin MG-PM-25 / Diagnostic des b g capacities for engaging in Quality And Cost- Open - Internation 2019-03-1 2018-01-0 2018-03-1 2018-04-0 2018-05-2 2018-07-0 2018-08-1 2019-08-1 esoins en activités alternativ IDA / 59870 Post 150,000.00 0.00 Canceled 2017-12-15 alternative fishing practices Based Selection al 5 5 2 9 4 5 6 6 es adaptées pour chaque ré and livelihoods activities gion ultra prioritaire (exécut ée par AGEX) MG-MRHP-28322-CS-QCBS// Component 3. Strengthenin MG-PM-27 / Détermination d g capacities for engaging in Quality And Cost- Open - Internation 2017-01-2 2017-11-2 2018-01-2 2017-09-0 2018-02-2 2017-10-1 2018-04-0 2017-10-1 2018-05-2 2018-08-0 2018-07-0 2018-09-2 2019-07-0 2019-07-2 IDA / 59870 Post 60,000.00 66,260.37 Completed 2017-10-30 es outils financiers d'appui a alternative fishing practices Based Selection al 4 0 5 6 2 0 8 0 0 8 1 5 1 3 ux filières et activités altern and livelihoods activities atives MG-MRHP-28323-CS-CQS// Component 3. Strengthenin MG-PM-28 / Étude sur l'amél g capacities for engaging in Consultant Qualif Open - Internation 2017-11-0 2018-01-1 2018-02-2 2018-04-0 2018-10-0 IDA / 59870 Post 60,000.00 0.00 Canceled 2017-10-16 ioration des conditions de vi alternative fishing practices ication Selection al 6 1 5 8 5 e sociale des communautés and livelihoods activities de pêcheur MG-MRHP-28330-CS-QCBS// MG-PM-31 / État de lieux des Component 3. Strengthenin petites infrastructures de pê g capacities for engaging in Quality And Cost- Open - Internation 2019-04-0 2017-11-2 2019-04-1 2018-01-2 2019-06-0 2018-02-2 2019-07-1 2018-04-0 2019-07-1 2018-05-2 2019-09-1 2018-07-0 2019-10-1 2019-07-0 2020-11-0 IDA / 59870 Post 120,000.00 113,351.50 Completed 2017-10-30 ches et les besoins des com alternative fishing practices Based Selection al 4 0 5 5 6 2 7 8 8 0 3 1 0 1 3 munautés cibles en petites i and livelihoods activities nfrastructures de pêche et c ommunautaires MG-MRHP-28333-CS-QCBS// Component 3. Strengthenin MG-PM-32 / Étude des besoi g capacities for engaging in Quality And Cost- Open - Internation 2017-11-2 2018-01-2 2018-02-2 2018-04-0 2018-05-2 2018-07-0 2019-07-0 IDA / 59870 Post 200,000.00 0.00 Canceled 2017-10-30 ns communautaires (une ét alternative fishing practices Based Selection al 0 5 2 8 0 1 1 ude par district) and livelihoods activities Page 5 MG-MRHP-28336-CS-CQS// Component 3. Strengthenin MG-PM-33 / Préparation du p g capacities for engaging in Consultant Qualif Open - Internation 2017-11-2 2018-01-2 2018-03-1 2018-04-2 2018-10-1 IDA / 59870 Post 60,000.00 0.00 Canceled 2017-10-30 lan local d'électrification co alternative fishing practices ication Selection al 0 5 1 2 9 mmunautaire : étude et rap and livelihoods activities ports MG-MRHP-28342-CS-CQS// MG-PM-39 / Études techniqu Component 4. Project mana Consultant Qualif 2017-11-2 2018-01-2 2018-03-1 2018-04-2 2018-10-1 IDA / 59870 Post Open - National 13,500.00 0.00 Canceled 2017-10-30 es pour la construction d'un gement and coordination ication Selection 0 5 1 2 9 local pour bureau UGP MG-MRHP-28343-CS-LCS//M G-PM-40 / Études d'impacts Component 4. Project mana Least Cost Select Open - Internation 2018-01-0 2018-03-1 2018-04-0 2018-05-0 2018-06-2 2018-08-0 2019-01-2 IDA / 59870 Post 10,000.00 0.00 Canceled 2017-12-15 environnementales et social gement and coordination ion al 5 2 9 9 0 1 8 es pour la construction d'un local pour bureau UGP MG-MRHP-27288-CS-QCBS// Component 2. Strengthenin PA62 / Appui à la mise en œ Quality And Cost- Open - Internation 2016-09-0 2017-09-2 2017-11-1 2017-06-0 2017-12-0 2017-07-1 2018-01-0 2017-08-0 2018-02-1 2017-10-2 2018-03-1 2018-05-0 2019-03-1 2019-07-1 IDA / Q9790 g capacities for priority fish Post 255,000.00 234,182.87 Completed 2017-09-07 uvre du plan d'amélioration Based Selection al 6 8 1 6 9 7 8 4 2 0 9 2 9 6 eries management de la pêcherie crevettière MG-MRHP-28654-CS-CQS// MG-PM-113 / Mise à jour de l Component 2. Strengthenin Consultant Qualif 2018-02-2 2018-04-2 2018-06-1 2018-07-2 2019-01-2 a Stratégie Nationale de l'Aq IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-02-01 ication Selection 2 9 3 5 1 uaculture (Consultant natio eries management nal + Réunions (1 consultati on, 1 validation) MG-MRHP-28656-CS-CQS// MG-PM-114 / Étude sur les p Component 2. Strengthenin rocédures administratives ré Consultant Qualif 2018-02-2 2018-04-2 2018-06-1 2018-07-2 2019-01-1 IDA / 59870 g capacities for priority fish Post Open - National 50,000.00 0.00 Canceled 2018-01-30 gissant l'accès aux ressourc ication Selection 0 7 1 3 9 eries management es et examen des options et recommandations (6 outils d e gestion) MG-MRHP-28657-CS-CQS// Component 2. Strengthenin MG-PM-115 / Diagnostic du Consultant Qualif 2018-06-2 2018-08-2 2018-10-1 2018-11-2 2019-05-2 IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-06-01 secteur dans le domaine fin ication Selection 2 7 1 2 1 eries management ancier local, régional, intern ational MG-MRHP-28659-CS-CQS// Component 2. Strengthenin MG-PM-116 / Élaboration de Consultant Qualif 2018-02-2 2018-04-2 2018-05-2 2018-07-0 2019-01-0 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-01-30 la stratégie d'adaptation du ication Selection 0 7 7 8 4 eries management secteur pêche face au chan gement climatique MG-MRHP-28661-CS-CQS// Component 2. Strengthenin Consultant Qualif 2018-06-2 2018-08-2 2018-09-2 2018-11-0 2019-05-0 MG-PM-118 / Recueil et anal IDA / D1720 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-06-01 ication Selection 2 7 6 7 6 yse des informations de bas eries management e avant-projet MG-MRHP-28663-CS-CQS// MG-PM-119 / Développemen Component 2. Strengthenin t et mise en œuvre du systè Consultant Qualif 2018-04-2 2018-06-0 2018-07-0 2018-08-1 2019-02-0 IDA / D1720 g capacities for priority fish Post Open - National 5,000.00 0.00 Canceled 2018-04-02 me de collecte de données p ication Selection 3 6 6 0 6 eries management our les pêcheries traditionne lles, y compris une stratégie d'échantillonnage approprié e MG-MRHP-28665-CS-CQS// Component 2. Strengthenin MG-PM-120 / Collecte des do Consultant Qualif 2018-03-2 2018-05-0 2018-06-0 2018-07-0 2019-01-0 IDA / D1720 g capacities for priority fish Post Open - National 35,000.00 0.00 Canceled 2018-03-01 nnées au niveau des régions ication Selection 2 5 4 9 5 eries management prioritaires (Artfish) MG-MRHP-28668-CS-CQS// Component 2. Strengthenin Consultant Qualif 2018-02-2 2018-04-0 2018-05-0 2018-06-1 2018-12-0 MG-PM-121 / Mise à jour de l IDA / D1720 g capacities for priority fish Post Open - National 50,000.00 0.00 Canceled 2018-02-01 ication Selection 2 7 7 1 8 'Enquête Cadre Nationale eries management MG-MRHP-28669-CS-CQS// Component 2. Strengthenin MG-PM-122 / Développemen Consultant Qualif 2018-03-0 2018-04-2 2018-05-2 2018-06-2 2018-12-2 IDA / D1720 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-02-15 t et mise en œuvre de la col ication Selection 8 1 1 5 2 eries management lecte de données pour les pr oduits post-capture MG-MRHP-28679-CS-CQS// Component 2. Strengthenin MG-PM-126 / Développemen Consultant Qualif 2018-09-2 2018-11-0 2018-12-0 2019-01-1 2019-07-1 IDA / D1720 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-09-03 t d'un système d'information ication Selection 4 7 7 1 0 eries management halieutique modulaire MG-MRHP-28682-CS-CQS// Component 2. Strengthenin Consultant Qualif 2018-05-2 2018-07-0 2018-08-0 2018-09-0 2019-03-0 MG-PM-127 / Suivi du systè IDA / D1720 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-04-30 ication Selection 1 4 3 7 6 me d'information halieutiqu eries management e modulaire MG-MRHP-28686-CS-CQS// Component 2. Strengthenin MG-PM-129 / Étude d'impact Consultant Qualif 2018-06-0 2018-07-1 2018-08-1 2018-09-2 2019-03-2 IDA / 59870 g capacities for priority fish Post Open - National 66,000.00 0.00 Canceled 2018-05-15 environnemental et social d ication Selection 5 9 8 2 1 eries management e l'extension ou de la constr uction MG-MRHP-28687-CS-QCBS// Component 2. Strengthenin Quality And Cost- Open - Internation 2018-04-0 2018-06-1 2018-07-0 2018-08-0 2018-09-1 2018-10-3 2019-10-3 MG-PM-130 / Élaboration str IDA / 59870 g capacities for priority fish Post 50,000.00 0.00 Canceled 2018-03-15 Based Selection al 5 0 8 7 8 0 0 atégie nationale de recherch eries management es halieutiques MG-MRHP-28690-CS-CQS// Component 2. Strengthenin Consultant Qualif Open - Internation 2018-07-0 2018-08-1 2018-09-1 2018-10-2 2019-04-2 MG-PM-134 / Etude sur les IDA / 59870 g capacities for priority fish Post 30,000.00 0.00 Canceled 2018-06-15 ication Selection al 6 9 8 3 1 mesures de gestion des pou eries management lpes MG-MRHP-28691-CS-QCBS// Component 2. Strengthenin MG-PM-135 / Avis scientifiqu Quality And Cost- Open - Internation 2018-07-2 2018-09-2 2018-10-2 2018-11-2 2019-01-0 2019-02-0 2020-02-0 IDA / 59870 g capacities for priority fish Post 30,000.00 0.00 Canceled 2018-06-29 e pour la gestion des pêcher Based Selection al 0 4 2 1 2 6 6 eries management ies de langoustes, dans les sites prioritaires MG-MRHP-28693-CS-QCBS// MG-PM-137 / Révision du sys Component 2. Strengthenin Quality And Cost- Open - Internation 2018-02-0 2018-04-1 2018-05-1 2018-06-0 2018-07-2 2018-08-2 2019-08-2 tème de suivi de la pêche cr IDA / 59870 g capacities for priority fish Post 75,000.00 0.00 Canceled 2018-01-15 Based Selection al 5 2 0 9 1 5 5 evettière traditionnelle (PCT eries management ) et élargissement à toutes l es zones de pêche MG-MRHP-28694-CS-CQS// Component 2. Strengthenin MG-PM-138 / Révision par le Consultant Qualif Open - Internation 2018-02-2 2018-04-0 2018-05-0 2018-06-1 2018-12-0 IDA / 59870 g capacities for priority fish Post 75,000.00 0.00 Canceled 2018-02-01 s pairs des modèles d'évalu ication Selection al 2 7 7 1 8 eries management ation des stock de crevettes MG-MRHP-28695-CS-CQS// Component 2. Strengthenin MG-PM-139 / Etat des lieux e Consultant Qualif Open - Internation 2018-06-2 2018-08-0 2018-09-0 2018-10-0 2019-04-0 IDA / 59870 g capacities for priority fish Post 10,000.00 0.00 Canceled 2018-05-30 t évaluation des besoins du ication Selection al 0 3 2 7 5 eries management Ministère en moyens et équi pements MG-MRHP-28703-CS-QCBS// MG-PM-145 / Élaboration du Component 2. Strengthenin Quality And Cost- 2018-02-2 2018-04-2 2018-05-1 2018-07-0 2018-08-0 2018-09-1 2019-09-1 plan d'action national sur les IDA / 59870 g capacities for priority fish Post Open - National 60,000.00 0.00 Canceled 2018-01-30 Based Selection 0 0 8 2 6 0 0 requins, les oiseaux de mer, eries management les tortues mrines, (résolutio n CTOI) MG-MRHP-28706-CS-QCBS// Component 2. Strengthenin Quality And Cost- 2018-10-0 2018-12-1 2019-01-1 2019-02-2 2019-03-3 2019-05-0 2020-05-0 MG-PM-149 / Étude sur l'am IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 Canceled 2018-09-17 Based Selection 8 3 0 4 1 5 4 élioration du protocole stand eries management ard de pêche MG-MRHP-28707-CS-CQS// MG-PM-150 / Étude sur l'éval Component 2. Strengthenin Consultant Qualif 2018-10-0 2018-11-2 2018-12-2 2019-01-2 2019-07-2 uation des impacts des diffé IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-09-17 ication Selection 8 1 1 5 4 rents engins (palangres, filet eries management s, ...) sur les espèces menac ées (requins, tortues, ...) MG-MRHP-28709-CS-CQS// Component 2. Strengthenin MG-PM-128 / Étude techniqu Consultant Qualif 2018-03-0 2018-04-2 2018-05-2 2018-06-2 2018-12-2 IDA / 59870 g capacities for priority fish Post Open - National 67,500.00 0.00 Canceled 2018-02-15 e de l'extension ou construc ication Selection 8 1 1 5 2 eries management tion du bureau régional MG-MRHP-28713-CS-QCBS// Component 2. Strengthenin MG-PM-155 / Études techniq Quality And Cost- 2018-02-2 2018-04-2 2018-05-2 2018-07-0 2018-08-2 2018-10-0 2019-10-0 IDA / D1720 g capacities for priority fish Post Open - National 60,000.00 0.00 Canceled 2018-01-30 ues sur la stratégie de surve Based Selection 0 7 5 9 0 1 1 eries management illance et sur le fonctionnem ent du CSP MG-MRHP-28728-CS-CQS// Component 2. Strengthenin Consultant Qualif Open - Internation 2018-02-2 2018-04-2 2018-06-1 2018-07-2 2019-01-1 MG-PM-156 / Rédaction d'un IDA / 59870 g capacities for priority fish Post 15,000.00 0.00 Canceled 2018-01-30 ication Selection al 0 7 1 3 9 plan national de lutte contre eries management la pêche INN MG-MRHP-28732-CS-CQS// MG-PM-158 / Etude et élabor Component 2. Strengthenin ation de mécanisme structur Consultant Qualif Open - Internation 2018-02-2 2018-04-1 2018-05-1 2018-06-2 2018-12-2 IDA / 59870 g capacities for priority fish Post 50,000.00 0.00 Canceled 2018-01-30 el de plateforme de cogestio ication Selection al 0 2 2 3 0 eries management n des filières prioritaires (cra bes, poulpes, langoustes, ho lothuries, crevettes) MG-MRHP-28733-CS-QCBS// Component 2. Strengthenin Quality And Cost- 2018-03-0 2018-05-1 2018-06-1 2018-07-2 2018-09-0 2018-10-1 2019-10-1 MG-PM-163 / Suivi-évaluatio IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-02-15 Based Selection 8 3 0 5 5 7 7 n des formations et recyclag eries management es réalisés MG-MRHP-28747-CS-QCBS// Component 3. Strengthenin MG-PM-172 / Mise en place g capacities for engaging in Quality And Cost- Open - Internation 2018-08-2 2018-10-2 2018-11-2 2019-01-0 2019-02-1 2019-03-3 2020-03-3 IDA / 59870 Post 25,000.00 0.00 Canceled 2018-07-30 d'une règlementation de bas alternative fishing practices Based Selection al 0 5 2 6 7 1 0 e concernant la sécurité en and livelihoods activities mer de la petite pêche MG-MRHP-28748-CS-QCBS// Component 3. Strengthenin MG-PM-173 / " Étude de mar g capacities for engaging in Quality And Cost- Open - Internation 2018-04-2 2018-06-2 2018-07-2 2018-09-0 2018-10-1 2018-11-2 2019-11-2 ché pour les produits de pêc IDA / 59870 Post 90,000.00 0.00 Canceled 2018-03-30 alternative fishing practices Based Selection al 0 5 3 6 8 9 9 he valorisés dans chaque ré and livelihoods activities gion ultra prioritaire " MG-MRHP-28763-CS-QCBS// Component 3. Strengthenin MG-PM-185 / Gestion et mis g capacities for engaging in Quality And Cost- Open - Internation 2018-11-2 2019-01-1 2019-02-1 2019-04-0 2019-05-0 2019-06-1 2020-06-0 IDA / V0500 Post 40,000.00 0.00 Canceled 2018-10-30 e en œuvre : Suivi évaluatio alternative fishing practices Based Selection al 0 8 5 1 6 0 9 n des bases de données and livelihoods activities MG-MRHP-28766-CS-LCS//M Component 4. Project mana Least Cost Select Open - Internation 2018-02-2 2018-04-0 2018-05-0 2018-06-0 2018-07-0 2018-08-1 2019-02-0 G-PM-189 / Audit externe de IDA / 59870 Post 15,000.00 0.00 Canceled 2018-01-30 gement and coordination ion al 0 5 3 2 7 1 7 s comptes du Projet MG-MRHP-14953-CS-LCS//P Component 2. Strengthenin Least Cost Select Open - Internation 2018-03-2 2018-05-1 2018-05-2 2018-05-2 2018-06-1 2018-07-1 2019-01-1 A67 / PA 67: Recensement d IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2018-03-15 ion al 9 3 0 7 7 5 1 es données au niveau des ré eries management gions prioritaires MG-MRHP-14945-CS-CQS//P Component 2. Strengthenin Consultant Qualif Open - Internation 2018-01-0 2018-03-1 2018-04-2 2018-06-0 2018-12-0 A 15 / PA 15: Recueillir et an IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2017-12-15 ication Selection al 5 2 6 7 4 alyser des informations de b eries management ase avant-projet MG-MRHP-86202-CS-QCBS// PA61 / Recrutement d'une fi Component 2. Strengthenin Quality And Cost- Open - Internation 2016-09-2 2018-12-2 2019-02-1 2017-06-0 2019-03-2 2017-07-1 2019-04-1 2017-08-0 2019-06-1 2018-07-0 2019-08-1 2018-10-1 2020-08-1 rme afin d'appuyer la mise e IDA / 59870 g capacities for priority fish Post 262,000.00 317,899.36 Terminated 2018-11-20 Based Selection al 0 0 8 6 0 7 9 4 8 5 7 2 6 n place d'outils d'aménage eries management ment des pêcheries à Mada gascar MG-MRHP-86206-CS-LCS//M Component 4. Project mana Least Cost Select Open - Internation 2019-02-0 2018-12-3 2019-03-1 2019-02-1 2019-04-2 2019-03-1 2019-06-1 2019-03-2 2019-08-2 2019-03-2 2019-11-1 2019-04-1 2020-05-0 2021-04-2 G-PM 88/18 / Audit externe IDA / 59870 Post 45,000.00 14,382.71 Completed 2018-11-30 gement and coordination ion al 5 0 5 5 9 5 3 1 7 6 0 6 8 1 des comptes du Projet 2018- 2019-2020 MG-MRHP-119249-CS-QCBS Component 3. Strengthenin / Etude technique et étude d g capacities for engaging in Quality And Cost- 2019-08-0 2019-10-3 2019-12-1 2020-01-1 2020-03-2 2020-06-1 2021-06-1 IDA / 59870 Post Open - National 20,000.00 0.00 Canceled 2019-07-03 'Impact Environnemental Ré alternative fishing practices Based Selection 2 1 5 4 9 2 2 habilitation du CFPT and livelihoods activities MG-MRHP-28674-CS-QCBS// MG-PM-125 / Développemen Component 2. Strengthenin Quality And Cost- 2019-08-2 2019-11-1 2019-12-1 2020-01-1 2020-03-1 2020-05-1 2021-05-1 t de la base de données pou IDA / 59870 g capacities for priority fish Post Open - National 46,000.00 0.00 Canceled 2019-07-30 Based Selection 9 2 2 1 1 0 0 r la pêche traditionnelle MA eries management RITIME et CONTINENTALE (c onsultant) Page 6 MG-MRHP-28755-CS-QCBS// MG-PM-177 / Élaboration de Component 3. Strengthenin s Plans d'Action aux restricti g capacities for engaging in Quality And Cost- Open - Internation 2019-08-2 2019-09-0 2019-08-3 2019-11-0 2020-01-2 2019-12-0 2020-02-2 2019-12-3 2020-04-0 2020-02-0 2020-04-1 2020-03-1 2021-02-0 2021-03-1 IDA / 59870 Post 270,000.00 408,313.76 Signed 2019-08-15 ons de Ressources (PARAR)/ alternative fishing practices Based Selection al 2 5 0 3 9 1 8 1 7 4 3 0 6 0 Diagnostic des besoins en a and livelihoods activities ctivités alternatives adaptée s à chaque région ultra prior itaire (AGR) MG-MRHP-105669-CS-QCBS Component 3. Strengthenin / Recrutement d'agence de g capacities for engaging in Quality And Cost- 2019-02-0 2019-09-2 2019-11-0 2019-05-0 2019-12-0 2019-06-1 2020-01-0 2019-06-1 2020-02-0 2019-06-2 2020-03-1 2019-07-1 2021-03-1 2019-09-1 communication pour la conc IDA / 59870 Post Open - National 33,750.00 21,553.74 Completed 2019-09-02 alternative fishing practices Based Selection 7 3 6 2 4 2 3 2 7 1 3 6 3 7 eption et production des sup and livelihoods activities ports de communications rel atifs au MDGP MG-MRHP-28174-CS-QCBS / Etude sur le circuit de comm Component 3. Strengthenin ercialisation des produits de g capacities for engaging in Quality And Cost- Open - Internation 2019-06-1 2019-09-2 2019-11-0 2019-10-0 2019-12-0 2019-11-1 2020-01-0 2020-01-1 2020-02-0 2020-02-0 2020-03-1 2020-06-0 2021-03-1 2021-05-1 IDA / 59870 Post 130,000.00 100,145.61 Completed 2019-09-02 s pêches frais et identificatio alternative fishing practices Based Selection al 8 3 6 9 4 1 3 3 7 3 3 6 3 3 n des techniques de transfor and livelihoods activities mation adaptées pour chaqu e ZUP MG-MRHP-19124-CS-QCBS PA48 / Etablissement de la S Component 4. Project mana Quality And Cost- Open - Internation 2017-08-0 2017-07-1 2017-09-0 2017-08-3 2017-09-2 2017-10-2 2017-12-0 2018-01-0 2019-01-0 ituation de référence du Cad IDA / Q9790 Post 75,000.00 0.00 Canceled 2017-06-27 gement and coordination Based Selection al 1 8 6 1 8 8 2 6 6 re de résultats et développe ment d'un système de gesti on de projet MG-MRHP-28701-CS-QCBS// Component 2. Strengthenin MG-PM-144 / Étude pour la d Quality And Cost- 2018-05-0 2018-07-0 2018-08-0 2018-09-1 2018-10-2 2018-11-2 2019-11-2 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-04-16 éfinition des termes de référ Based Selection 7 5 2 6 1 5 5 eries management ences du Service de Gestion de la Pêche Thonière MG-MRHP-28759-CS-QCBS// Component 3. Strengthenin MG-PM-182 / Préparation du g capacities for engaging in Quality And Cost- Open - Internation 2018-04-2 2018-06-1 2018-07-1 2018-08-3 2018-10-0 2018-11-0 2019-11-0 IDA / V0500 Post 251,100.00 0.00 Canceled 2018-03-30 plan local d'électrification co alternative fishing practices Based Selection al 0 8 6 0 4 8 8 mmunautaire : prestations i and livelihoods activities nternationales MG-MRHP-28753-CS-QCBS// Component 3. Strengthenin MG-PM-176 / Évaluation des g capacities for engaging in Quality And Cost- Open - Internation 2018-10-0 2018-12-0 2018-12-3 2019-01-3 2019-03-0 2019-04-1 2020-04-0 IDA / 59870 Post 90,000.00 0.00 Canceled 2018-09-14 impacts socio-économiques alternative fishing practices Based Selection al 5 3 1 0 6 0 9 de la mise pratique des acti and livelihoods activities vités alternatives MG-MRHP-28741-CS-QCBS// Component 3. Strengthenin MG-PM-168 / Étude sur l'ide g capacities for engaging in Quality And Cost- Open - Internation 2019-11-1 2020-01-2 2021-04-2 2021-06-1 2021-08-1 2021-09-2 2022-09-2 ntification de techniques mo IDA / 59870 Post 100,000.00 0.00 Canceled 2019-09-30 alternative fishing practices Based Selection al 4 8 8 2 1 2 2 dernes de pêche et de fabric and livelihoods activities ation d'engins de pêche ada ptés pour chaque ZUP MG-MRHP-14947-CS-QCBS// PA63 / PA 63: Elaboration de Component 2. Strengthenin Quality And Cost- Open - Internation 2017-05-3 2017-07-2 2017-08-0 2017-08-1 2017-09-0 2017-09-3 2018-09-3 s plans d'action nationaux s IDA / Q9790 g capacities for priority fish Prior 60,000.00 0.00 Canceled 2017-05-17 Based Selection al 1 9 5 2 2 0 0 ur les requins, les oiseaux d eries management e mer et les tortues marines (résolutions CTOI) MG-MRHP-28746-CS-QCBS// MG-PM-171 / Identification d e matériels de sécurité adap Component 3. Strengthenin tés aux différentes catégorie g capacities for engaging in Quality And Cost- Open - Internation 2018-04-2 2018-06-2 2018-07-2 2018-09-0 2018-10-1 2018-11-2 2019-11-2 IDA / 59870 Post 180,000.00 0.00 Canceled 2018-03-30 s d'embarcation et de navig alternative fishing practices Based Selection al 0 5 3 6 8 9 9 ation, stratégie de mis à dis and livelihoods activities position des équipements, d' organisation de secours et l a diffusion des informations météorologiques MG-MRHP-28761-CS-QCBS// Component 3. Strengthenin MG-PM-183 / Préparation du g capacities for engaging in Quality And Cost- Open - Internation 2018-04-0 2018-06-0 2018-07-0 2018-08-1 2018-09-1 2018-10-2 2019-10-2 IDA / V0500 Post 33,800.00 0.00 Canceled 2018-03-15 plan local d'électrification co alternative fishing practices Based Selection al 5 3 1 5 9 4 4 mmunautaire : prestations n and livelihoods activities ationales MG-MRHP-127605-CS-CQS / Component 2. Strengthenin Consultant Qualif Open - Internation 2019-10-0 2019-12-0 2020-01-0 2020-02-2 2020-08-2 Etude sur les accidents en IDA / 59870 g capacities for priority fish Post 90,000.00 0.00 Canceled 2019-09-06 ication Selection al 6 5 4 4 2 mer de la pêche à petite éch eries management elle MG-MRHP-28697-CS-CQS// MG-PM-140 / Étude sur l'ada Component 2. Strengthenin Consultant Qualif Open - Internation 2018-05-2 2018-07-0 2018-08-0 2018-09-0 2019-03-0 ptation des missions et attri IDA / 59870 g capacities for priority fish Post 10,000.00 0.00 Canceled 2018-04-30 ication Selection al 1 4 3 7 6 butions du MRHP par rappor eries management t au défi du développement rural MG-MRHP-23763-CS-QCBS// MG-PM-117 / Recrutement d' Component 3. Strengthenin un Cabinet d'étude ou d'une g capacities for engaging in Quality And Cost- 2017-10-3 2017-10-0 2017-12-0 2017-12-1 2018-09-1 2018-01-0 2019-02-0 2018-02-0 2018-03-2 2018-05-0 2020-04-3 ONG pour assurer les missio IDA / Q9790 Prior Open - National 600,000.00 0.00 Canceled 2017-09-14 alternative fishing practices Based Selection 0 5 1 0 8 7 7 6 0 1 0 ns de l'AGEX pour l'appui à l and livelihoods activities a mise en œuvre du Plan d'A ménagement Concerté des Pêcheries de la Région Mela ky MG-MRHP-23508-CS-QCBS// MG-MP-117 / Recrutement d e Cabinet d'étude ou d'une Component 3. Strengthenin ONG pour assurer les missio g capacities for engaging in Quality And Cost- 2017-10-3 2017-10-0 2018-08-2 2017-12-1 2018-09-1 2018-01-0 2019-02-0 2018-02-0 2019-09-0 2018-03-2 2018-05-0 2020-04-3 ns de l'AGEX pour l'appui à l IDA / Q9790 Prior Open - National 600,000.00 0.00 Canceled 2017-09-14 alternative fishing practices Based Selection 0 5 9 0 8 7 7 6 5 0 1 0 a mise en œuvre du Plan d'A and livelihoods activities ménagement des Pêcheries des Baies d'Ampasindava, d e Tsimipaika, d'Ambaro, et l' archipel de Nosy Be (BATAN ) MG-MRHP-23508-CS-BQS / Recrutement d'une agence Component 3. Strengthenin d'exécution pour l'appui à la g capacities for engaging in Quality Based Sel 2020-01-0 2017-10-0 2020-01-0 2017-11-1 2020-01-2 2017-12-1 2019-02-0 2018-01-1 2020-02-1 2018-02-1 2020-04-1 2018-03-2 2020-05-0 2019-03-2 mise en œuvre du Plan d'Am IDA / Q9790 Prior Open - National 1,600,000.00 1,517,925.94 Signed 2017-09-14 alternative fishing practices ection 7 5 9 8 3 6 7 5 1 4 4 1 9 1 énagement des Pêcheries d and livelihoods activities es Baies d'Ampasindava, de Tsimipaika, d'Ambaro, et l « archipel de Nosy Be (BATAN ) MG-MRHP-23763-CS-BQS / Component 3. Strengthenin Recrutement d'une agence g capacities for engaging in Quality Based Sel 2019-12-1 2017-10-0 2020-01-0 2017-11-1 2020-01-2 2017-12-1 2019-02-0 2018-01-1 2020-02-1 2018-02-1 2020-05-2 2018-03-2 2020-06-1 2021-03-2 d'exécution pour l'appui à la IDA / Q9790 Prior Open - National 900,000.00 647,158.90 Signed 2017-09-14 alternative fishing practices ection 8 5 9 8 3 6 7 5 1 4 0 1 6 0 mise en œuvre du Plan d'Am and livelihoods activities énagement Concerté des Pê cheries de la Région Melaky MG-MRHP-150365-CS-CQS / RECRUTEMENT D'UN CONSU LTANT NATIONAL POUR LE R ENFORCEMENT DE CAPACIT Component 2. Strengthenin Consultant Qualif Under Implemen 2020-03-1 2019-12-3 2020-09-1 2020-01-2 2020-03-0 2020-03-2 2020-05-2 E DU PERSONNEL DE L’AUT IDA / 59870 g capacities for priority fish Post Open - National 15,140.00 0.00 2019-12-24 ication Selection tation 1 1 4 8 8 2 1 ORITE SANITAIRE HALIEUTIQ eries management UE PAR UNE FORMATION EN LINGUISTIQUE (ANGLAIS / CHINOIS) AU NIV EAU NATIONAL (2.1.7.2.04) MG-MRHP-28740BIS-CS-QC BS // MG-PM-167 / Etude sur Component 3. Strengthenin l'amélioration des embarcati g capacities for engaging in Quality And Cost- Under Implemen 2020-02-2 2020-03-0 2020-03-1 2020-04-1 2020-05-1 2020-06-0 2020-07-0 2020-07-1 2021-03-2 IDA / 59870 Post Open - National 90,000.00 0.00 2020-02-25 ons existantes à partir des alternative fishing practices Based Selection tation 7 3 8 6 6 6 4 8 5 matériaux locaux bon march and livelihoods activities é et existants pour chaque Z UP (3.2.1.1.12) MG-MRHP-28740-CS-QCBS// Component 3. Strengthenin MG-PM-167 / Étude sur l'am g capacities for engaging in Quality And Cost- Open - Internation 2019-08-1 2018-05-2 2019-08-1 2018-07-2 2018-08-2 2018-10-0 2018-11-1 2018-12-3 2019-12-3 élioration des embarcations IDA / 59870 Post 60,000.00 0.00 Canceled 2018-04-30 alternative fishing practices Based Selection al 1 1 9 6 3 7 8 0 0 existantes à partir des maté and livelihoods activities riaux locaux bon marché et existants MG-MRHP-86203BIS-CS-QC BS / Recrutement d'une Fir me pour Appui à la Mise à jo ur de la Stratégie Nationale Component 2. Strengthenin Quality And Cost- Under Implemen 2020-02-2 2020-03-0 2020-03-0 2020-04-1 2020-05-1 2020-06-0 2020-07-1 2020-07-2 2020-12-1 pour le Développement de l’ IDA / 59870 g capacities for priority fish Post Open - National 50,000.00 0.00 2020-02-28 Based Selection tation 5 6 7 9 9 9 4 8 5 Aquaculture à Madagascar ( eries management SNDAM) et Elaboration des P lans de Développement des trois (3) filières « d’algocultu re, d’holothuriculture et de c rabicultu MG-MRHP-119284-CS-QCBS / Recrutement d'un BE pour Etudes techniques, étude d’i Component 3. Strengthenin mpact environnemental et s g capacities for engaging in Quality And Cost- Open - Internation 2020-03-1 2020-03-2 2020-03-1 2020-05-1 2020-06-1 2020-06-0 2020-07-1 2020-06-3 2020-08-1 2020-08-0 2020-11-0 2020-08-2 2021-03-1 2022-03-2 ocial et contrôle et surveilla TF / A4588 Post 44,000.00 56,927.90 Signed 2020-03-06 alternative fishing practices Based Selection al 0 7 8 0 6 9 6 0 3 4 5 5 8 8 nce des travaux pour la con and livelihoods activities struction des bâtiments du k iosque de pré-électrification et du « Complexe-pêche » d ans 2 villages à Mananara N ord MG-MRHP-86203-CS-QCBS// PA13 / Mise à jour de la Stra Component 2. Strengthenin Quality And Cost- Open - Internation 2020-02-0 2019-08-3 2019-11-1 2019-12-2 2020-02-1 2020-04-1 2020-06-1 2021-06-1 tégie Nationale de l’Aquacul IDA / 59870 g capacities for priority fish Post 30,000.00 0.00 Canceled 2019-07-31 Based Selection al 4 0 3 8 1 1 0 0 ture (Consultant national + eries management Réunions (1 consultation, 1 validation) MG-MRHP-14952-CS-LCS//P A66 / PA 66: Etudes d'Impac t environnemental et Socail : - Clôture de l'enceinte DRRH Component 2. Strengthenin Consultant Qualif Open - Internation 2017-07-1 2017-08-3 2017-09-3 2017-11-0 2018-05-0 P Fénérive IDA / Q9790 g capacities for priority fish Post 35,000.00 0.00 Canceled 2017-06-27 ication Selection al 8 1 0 4 3 - Construction des Bureaux eries management de 06 DRRHP - Extension de l'ASH à Antsir anana et Morondava - Construction local pour bur eau UGP MG-MRHP-168222-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-07-1 2020-08-1 2020-09-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 9 8 2 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH à Manakara et Mananjary MG-MRHP-168223-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-08-1 2020-07-1 2020-09-1 2020-08-1 2020-12-1 2020-09-2 2021-10-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 7 9 7 8 6 2 5 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH-OEPA à An tananarivo MG-MRHP-168224-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-07-1 2020-08-1 2020-09-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 9 8 2 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH-USTA-SRPA à Majunga MG-MRHP-168226-CS-QCBS / Recrutement d'un BE pour Component 2. Strengthenin la réalisation des études tec Quality And Cost- 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-08-2 2020-07-1 2020-09-2 2020-08-1 2020-12-1 2020-09-2 2021-02-0 2020-10-2 2021-03-1 2021-05-3 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 15,378.80 Signed 2020-04-17 hniques- du PGES et du cont Based Selection 5 8 7 1 0 9 8 8 8 2 1 7 8 0 eries management rôle et surveillance des cons tructions des bureaux admin istratifs de l'ASH à Toliara MG-MRHP-168227-CS-QCBS / Recrutement d'un BE pour Component 2. Strengthenin la réalisation des études tec Quality And Cost- 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-08-1 2020-07-1 2020-09-1 2020-08-1 2021-02-1 2020-09-2 2021-06-2 2020-10-2 2021-09-3 2021-05-3 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 25,713.74 Signed 2020-04-17 hniques- du PGES et du cont Based Selection 5 8 7 1 4 9 4 8 6 2 3 7 0 0 eries management rôle et surveillance des cons tructions des bureaux admin istratifs de l'ASH à Fort-Dau phin Page 7 MG-MRHP-168225-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-07-1 2020-08-1 2020-09-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 9 8 2 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH-SRPA-OEPA à Diégo Suarez MG-MRHP-169196-CS-QCBS / RECRUTEMENT D’UNE FIRM E EN CHARGE DE L’ELABOR Component 3. Strengthenin ATION DES PCD ET PDF DE g capacities for engaging in Quality And Cost- 2020-05-0 2020-05-2 2020-05-1 2020-07-0 2020-10-2 2020-08-0 2020-12-0 2020-08-3 2021-04-2 2020-10-0 2021-06-0 2020-11-0 2021-09-0 2021-09-0 S COMMUNES POUR LES 3 Z IDA / 59870 Post Open - National 300,000.00 157,999.04 Signed 2020-04-30 alternative fishing practices Based Selection 4 1 6 4 0 1 2 1 6 5 2 9 9 5 UPs ET REPARTIE EN TROIS and livelihoods activities LOTS: Lot 1: ZUP BA, Lot 2: ZUP BATAN Lot 3: ZUP MELAKY MG-MRHP-170094-CS-CQS / Recrutement d’un consultan Component 2. Strengthenin Consultant Qualif 2020-05-1 2020-05-2 2020-05-1 2020-06-2 2021-05-1 2020-07-2 2021-12-1 2020-08-2 2022-02-0 2021-02-2 t chargé de la traduction et IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 74,211.00 Signed 2020-04-30 ication Selection 4 1 6 5 9 5 6 9 5 5 de la synthèse des documen eries management ts du français et anglais au malagasy officiel MG-MRHP-170870-CS-QCBS / Recrutement d'une firme p Component 2. Strengthenin Quality And Cost- Under Implemen 2020-05-0 2020-05-2 2020-05-1 2020-07-0 2020-08-0 2020-09-0 2020-10-0 2020-11-1 2022-02-1 our l’élaboration du Plan d’A IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 0.00 2020-05-04 Based Selection tation 4 5 6 8 5 4 9 3 1 ménagement des Pêcheries eries management de la Région ATSIMO ATSINA NANA MG-MRHP-174365-CS-QCBS / Recrutement d'un Institut de Recherche ou d'une Firm Component 2. Strengthenin Quality And Cost- 2020-05-2 2020-06-1 2020-06-0 2020-07-3 2020-10-2 2020-08-2 2020-12-0 2020-09-2 2021-01-2 2020-10-3 2021-03-0 2020-12-0 2021-04-1 2022-02-2 e pour appuyer le Centre d’ IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 338,974.11 Signed 2020-05-26 Based Selection 0 6 6 0 0 7 2 6 9 1 4 5 5 8 Etude et de Développement eries management des Pêches (CEDP) dans l’ét ude des stocks Halieutiques (Cinq filières Prioritaires) MG-MRHP-181840-CS-QCBS Component 3. Strengthenin / RECRUTEMENT D’UNE FIRM g capacities for engaging in Quality And Cost- Under Implemen 2020-06-3 2020-07-1 2020-07-1 2020-08-1 2020-09-1 2020-10-0 2020-11-1 2020-12-1 2021-12-1 E POUR LA FORMATION DES IDA / 59870 Post Open - National 50,000.00 0.00 2020-07-02 alternative fishing practices Based Selection tation 0 2 6 6 5 6 0 5 5 GROUPEMENTS DE PÊCHEU and livelihoods activities RS SUR LES TECHNIQUES C OMMERCIALES MG-MRHP-182950-CS-CQS / Recrutement d'agence de co Component 3. Strengthenin mmunication pour la concep g capacities for engaging in Consultant Qualif 2020-08-1 2020-08-0 2020-08-2 2020-09-1 2021-10-0 2020-10-1 2022-03-3 2020-11-2 2022-04-1 2021-05-2 tion et production des suppo IDA / 59870 Post Open - National 25,000.00 61,842.50 Signed 2020-07-14 alternative fishing practices ication Selection 3 4 6 7 5 7 0 1 4 0 rts de communications relati and livelihoods activities fs au MDGP 2020 et pour la mise en oeuvre du plan de c ommunication du projet SWI Ofish2 MG-MRHP-181871-CS-QCBS / Recrutement d’ONG pour l a conservation et la restaura Component 3. Strengthenin tion des forêts de mangrove g capacities for engaging in Quality And Cost- 2020-10-0 2020-07-3 2020-10-2 2020-09-1 2021-05-2 2020-10-1 2022-01-1 2020-11-0 2022-04-0 2020-12-0 2022-10-1 2020-12-2 2021-12-2 IDA / 59870 Prior Open - National 3,000,000.00 0.00 Signed 2020-07-21 , et la protection de récifs co alternative fishing practices Based Selection 7 1 1 3 5 3 3 3 7 8 3 9 9 ralliens et d’herbiers marins and livelihoods activities dans des zones riches en ha bitats naturels côtiers et ma rins de Madagascar, répartis en 6 Lots MG-MRHP-183755-CS-QCBS / Recrutement d'une firme p our la réalisation d’une enqu Component 4. Project mana Quality And Cost- 2020-07-2 2020-08-0 2020-08-0 2020-09-1 2020-10-1 2020-10-1 2020-11-1 2020-11-0 2020-12-0 2020-12-0 2021-02-1 2020-12-2 2021-03-3 2021-03-1 IDA / 59870 Post Open - National 75,000.00 79,586.86 Signed 2020-07-17 ête de satisfaction des béné gement and coordination Based Selection 2 7 7 1 3 1 3 1 3 6 5 0 1 0 ficiaires du projet et les me mbres de la communauté de s pêcheurs MG-MRHP-28698-CS-CQS// Component 2. Strengthenin Consultant Qualif 2020-07-2 2020-09-0 2020-10-0 2020-11-0 2021-05-0 MG-PM-141 / Assistant techn IDA / 59870 g capacities for priority fish Post Open - National 24,000.00 0.00 Canceled 2020-06-30 ication Selection 1 3 3 7 6 ique pour UGP eries management MG-MRHP-183758-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- 2020-09-0 2020-09-1 2020-09-1 2020-10-2 2020-11-2 2020-11-2 2021-01-1 2020-12-1 2021-02-0 2021-01-1 2021-03-0 2021-02-2 2021-04-3 2021-10-1 IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 86,424.70 Signed 2020-08-27 our étudier la mise en place Based Selection 1 7 0 2 7 1 1 2 2 6 9 0 0 8 eries management des ZEA pêche et aquacultu re MG-MRHP-28689-CS-CQS// MG-PM-133 / Appui du centr Component 2. Strengthenin Consultant Qualif Open - Internation 2020-08-3 2020-11-1 2020-12-2 2021-03-1 2021-09-0 e de recherche par deux (02 IDA / 59870 g capacities for priority fish Post 150,000.00 0.00 Canceled 2020-07-31 ication Selection al 0 3 8 3 9 ) experts internationaux pou eries management r les évaluations de stocks d e 5 filières prioritaires MG-MRHP-190077-CS-CQS / Recrutement d'un cabinet d' Component 2. Strengthenin Consultant Qualif 2020-09-1 2020-09-2 2020-09-2 2020-11-0 2021-03-1 2020-12-0 2021-05-1 2021-01-0 2022-05-1 2021-03-0 étude pour effectuer une ét IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 50,426.00 Signed 2020-08-31 ication Selection 1 1 3 4 1 4 4 8 1 9 ude de faisabilité de l'éclose eries management rie en holothuries à Ambanj a MG-MRHP-28671-CS-QCBS// MG-PM-123 / Amélioration d e la base de données pour l Component 2. Strengthenin Quality And Cost- 2018-01-2 2018-03-3 2018-04-2 2018-05-2 2018-07-0 2018-08-1 2019-08-1 a déclaration des produits d IDA / D1720 g capacities for priority fish Post Open - National 20,000.00 0.00 Canceled 2018-01-02 Based Selection 3 0 7 7 8 9 9 e la pêche régionale (Base d eries management e données-Tableau de bord- Système d'Information Pêch e :basé sur le Web, consulta nt) MG-MRHP-198557-CS-QCBS / Recrutement des BE pour Component 3. Strengthenin réaliser les études techniqu g capacities for engaging in Quality And Cost- 2020-10-1 2020-11-0 2020-12-2 2021-04-0 2021-01-1 2021-11-0 2021-02-1 2021-05-1 2021-03-2 2021-07-1 2021-04-2 2021-11-0 2021-11-2 es et EIES de la construction TF / A4588 Post Open - National 130,000.00 108,278.08 Signed 2020-10-16 alternative fishing practices Based Selection 9 6 0 1 9 3 8 4 5 6 9 5 5 des bâtiments de pré-électri and livelihoods activities fication hors grille et comple xe pêche au niveau BATAN et Aniribe (BA) répartis en 4 Lots MG-MRHP-199272-CS-CQS / Recrutement d'un BE études Component 2. Strengthenin Consultant Qualif Under Implemen 2020-10-1 2020-11-0 2020-12-1 2021-03-1 2021-01-1 2021-02-1 2021-09-0 techniques- EIES et contrôle IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-10-19 ication Selection tation 9 9 3 1 2 6 4 et surveillance des travaux eries management à la mise en place d'écloseri e_Ambanja MG-MRHP-203599-CS-CQS / Recrutement d’une firme po ur la conception et le dévelo ppement de site web pour l’ Component 2. Strengthenin Consultant Qualif 2020-11-2 2020-12-1 2020-11-2 2021-01-1 2021-03-2 2021-02-1 2021-06-0 2021-03-2 2021-09-2 2021-05-1 Observatoire Economique d IDA / Q9790 g capacities for priority fish Post Open - National 45,000.00 76,667.73 Signed 2020-11-20 ication Selection 1 1 6 5 3 4 8 1 5 0 e la Pêche et de l’Aquacultur eries management e (OEPA), pour le Centre d’E tudes et de Développement des Pêches (CEDP) et pour l’ Unité Statistique Thonière d’ Antsiran MG-MRHP-208296-CS-CQS / Recrutement d'un BE études techniques, EIES et C&S des Component 3. Strengthenin travaux pour la construction g capacities for engaging in Consultant Qualif 2021-01-1 2021-01-1 2021-01-1 2021-02-1 2021-03-2 2021-03-1 2021-06-1 2021-04-2 2021-09-1 2021-11-1 TF / A4588 Post Open - National 20,000.00 36,890.00 Signed 2020-12-21 des bâtiments du kiosque d alternative fishing practices ication Selection 2 1 9 4 6 6 0 0 4 6 e pré-électrification et du « and livelihoods activities Complexe-pêche » dans les villages d’Ambalahonko et A mpasimandroro district de M aintirano MG-MRHP-208303-CS-QCBS / Recrutement des BE pour r Component 3. Strengthenin éaliser les études technique g capacities for engaging in Quality And Cost- 2021-01-1 2021-01-1 2021-01-1 2021-02-2 2021-03-3 2021-03-2 2021-04-3 2021-04-2 2021-05-2 2021-05-3 2021-07-1 2021-07-0 2022-09-2 2022-01-3 IDA / 59870 Post Open - National 180,000.00 146,654.22 Signed 2020-12-21 s, PGES et et contrôle et sur alternative fishing practices Based Selection 2 1 9 4 1 6 0 5 5 0 9 4 2 0 veillance des travaux de con and livelihoods activities struction des petites infrast ructures de pêches répartis en 6 lots MG-MRHP-208305-CS-CQS / Component 2. Strengthenin Recrutement d'un BE pour l Consultant Qualif 2021-01-1 2021-01-1 2021-01-1 2021-02-2 2021-03-2 2021-03-2 2021-06-1 2021-04-3 2021-09-2 2021-09-2 IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 25,708.56 Signed 2020-12-21 e contrôle et surveillance de ication Selection 2 1 9 4 3 6 0 0 8 7 eries management s travaux des DRAEP à Andr oy, Anosy MG-MRHP-208306-CS-CQS / Component 2. Strengthenin Recrutement d'un BE pour l Consultant Qualif 2021-01-1 2021-01-1 2021-01-1 2021-02-2 2021-03-2 2021-03-2 2021-10-0 2021-04-3 2021-10-2 2021-09-2 IDA / 59870 g capacities for priority fish Post Open - National 8,000.00 15,062.89 Signed 2020-12-21 e contrôle et la surveillance ication Selection 2 1 9 4 3 6 4 0 1 7 eries management des travaux du DRAEP à Mai ntirano MG-MRHP-214299-CS-QCBS / Recrutement d’une firme p Component 2. Strengthenin Quality And Cost- 2021-01-2 2021-02-1 2021-02-0 2021-03-0 2021-03-3 2021-03-3 2021-04-3 2021-04-2 2021-05-1 2021-05-2 2021-06-0 2021-06-3 2021-09-1 2022-09-2 our l’élaboration du Plan d’A IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 137,749.52 Signed 2021-01-29 Based Selection 8 3 4 1 0 1 0 1 4 6 7 0 4 3 ménagement des Pêcheries eries management (PAP) de la Région ANDROY MG-MRHP-216848-CS-CQS / Recrutement d'un BE pour ET, élaboration du PGES et C Component 3. Strengthenin &S relative à la construction g capacities for engaging in Consultant Qualif Under Implemen 2021-02-2 2021-03-1 2021-03-0 2021-04-1 2021-05-1 2021-06-1 2022-02-0 IDA / 59870 Post Open - National 33,000.00 0.00 2021-02-17 du bureau de la Circonscripti alternative fishing practices ication Selection tation 4 0 9 3 3 7 2 on en charge de la pêche et and livelihoods activities de l’Aquaculture et l’l’anten ne du Centre de Surveillanc e des Pêches (CSP) à Maintir ano MG-MRHP-218699-CS-CQS / Component 2. Strengthenin Recrutement d’une firme po Consultant Qualif Under Implemen 2021-02-2 2021-03-0 2021-03-0 2021-04-2 2021-05-2 2021-06-2 2021-10-2 IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 2021-02-15 ur Etude des impacts du CO ication Selection tation 3 8 2 1 1 5 3 eries management VID19 sur la pêche à Madag ascar MG-MRHP-222309-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif 2021-03-1 2021-03-3 2021-03-2 2021-05-1 2021-04-2 2021-06-1 2021-05-2 2021-07-1 2021-09-1 2021-09-0 ur réaliser un diagnostic inst IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 13,920.80 Signed 2021-03-17 ication Selection 4 1 6 4 1 3 8 8 4 1 itutionnel et organisationnel eries management de la mise en oeuvre du proj et SWIOFish2 MG-MRHP-222313-CS-QCBS / Recrutement d’une firme e n charge de l’identification d Component 3. Strengthenin es plans de pérennisation in g capacities for engaging in Quality And Cost- Under Implemen 2022-01-1 2021-04-0 2022-01-1 2021-05-2 2022-03-1 2021-06-2 2022-05-0 2021-07-2 2022-05-2 2021-08-2 2022-06-0 2021-09-2 2022-01-2 IDA / 59870 Post Open - National 90,000.00 0.00 2021-03-24 cluant un plan de gestion et alternative fishing practices Based Selection tation 2 7 7 1 7 0 3 0 4 4 3 8 6 un plan d’affaire des petites and livelihoods activities infrastructures de pêche et complexes pêches dans les zones ultra prioritaires BATA N, BA et MELAKY MG-MRHP-224627-CS-CQS / Component 2. Strengthenin Recrutement firme pour pro Consultant Qualif Under Implemen 2021-03-3 2021-04-2 2021-04-1 2021-06-0 2021-07-0 2021-08-0 2022-02-0 IDA / 59870 g capacities for priority fish Post Open - National 115,000.00 0.00 2021-03-30 spection nouvelles zones de ication Selection tation 0 0 5 3 3 7 3 eries management pêche langoustes MG-MRHP-223841-CS-CQS / Cabinet pour le recrutement Component 2. Strengthenin Consultant Qualif 2021-05-0 2021-04-2 2021-06-0 2021-09-2 2021-07-0 2021-12-2 2021-08-0 2022-03-2 2021-10-0 de 75 enquêteurs pour le dé IDA / Q9790 g capacities for priority fish Post Open - National 40,000.00 23,150.53 Signed 2021-03-31 ication Selection 1 1 4 9 4 3 8 2 7 ploiement d'OPENARTFISH d eries management ans 5 régions côtières MG-MRHP-222316-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- Under Implemen 2021-04-2 2021-06-0 2021-07-0 2021-08-0 2021-09-0 2021-10-1 2022-04-1 IDA / 59870 g capacities for priority fish Prior Open - National 1,250,000.00 0.00 2021-03-31 our l'Appui au développeme Based Selection tation 1 4 4 3 7 2 0 eries management nt de l’économie bleue à Ma dagascar MG-MRHP-227234-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2021-04-0 2021-04-2 2021-06-1 2021-07-1 2021-08-1 2022-02-1 ur la mise à jour de la straté IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 2021-04-07 ication Selection tation 9 8 1 1 5 1 gie Nationale de la Bonne G eries management ouvernance de la Pêche Mar itime MG-MRHP-229422-CS-QCBS Component 2. Strengthenin Quality And Cost- Under Implemen 2021-05-1 2021-05-2 2021-10-1 2021-06-2 2022-03-0 2021-07-2 2022-04-1 2021-08-1 2022-05-3 2021-09-2 2022-07-2 2021-10-2 2023-01-2 / Recrutement des firmes po IDA / 59870 g capacities for priority fish Post Open - National 700,000.00 0.00 2021-05-14 Based Selection tation 8 9 4 8 2 8 1 8 0 2 0 7 0 ur l'élaboration des PAP régi eries management onaux Page 8 MG-MRHP-28730-CS-CQS// Component 2. Strengthenin Consultant Qualif Open - Internation 2021-07-2 2021-09-0 2021-10-0 2021-11-0 2022-05-0 MG-PM-157 / Étude pour l'ex IDA / 59870 g capacities for priority fish Post 50,000.00 0.00 Canceled 2021-07-01 ication Selection al 2 4 4 8 7 tension de l'ERS vers la flott eries management e nationale MG-MRHP-231603-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2021-06-0 2021-06-0 2021-10-1 2021-07-1 2022-01-0 2021-08-1 2022-05-0 2021-09-2 2021-12-2 ur réaliser une étude diagno IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2021-05-14 ication Selection tation 9 4 4 8 7 7 2 1 0 stique des besoins en renfor eries management cement des capacités DGPA et UGP SWIOFish2 MG-MRHP-231604-CS-LCS / Component 4. Project mana Least Cost Select 2021-06-1 2021-07-2 2021-08-2 2021-09-2 2021-10-2 2021-11-2 2022-01-2 Recrutement d'audit pour le IDA / Q9790 Post Open - National 32,500.00 0.00 Canceled 2021-05-20 gement and coordination ion 0 4 1 0 5 9 8 Centre de Surveillance de P êche MG-MRHP-232532-CS-LCS / Recrutement d'un cabinet d' Component 4. Project mana Least Cost Select 2021-07-1 2021-06-1 2021-07-2 2021-09-2 2021-08-2 2021-10-2 2021-09-2 2021-11-1 2021-10-2 2022-01-2 2021-11-2 2022-02-2 2023-09-2 IDA / 59870 Post Open - National 50,000.00 20,442.04 Signed 2021-05-20 audit externe des comptes d gement and coordination ion 5 0 4 3 1 5 0 2 5 6 9 4 9 u Projet 2021-2022 et 2023 MG-MRHP-236858-CS-CQS / Component 2. Strengthenin Recrutement d'un BE pour l Consultant Qualif Under Implemen 2021-08-0 2021-07-1 2021-10-1 2021-08-2 2021-11-2 2021-09-2 2022-05-3 2021-10-3 2022-04-2 TF / A4588 g capacities for priority fish Post Open - National 30,000.00 0.00 2021-06-30 es études technique et contr ication Selection tation 6 4 4 7 6 6 1 1 9 eries management ôle et surveillance du Burea u CSP à Toliara MG-MRHP-239019-CS-CQS / Recrutement d'un BE ET- PG Component 2. Strengthenin ES et C&S relative à la con Consultant Qualif Under Implemen 2021-08-0 2021-07-1 2021-10-1 2021-08-1 2021-09-1 2021-10-2 2022-06-0 IDA / 59870 g capacities for priority fish Post Open - National 37,000.00 0.00 2021-06-30 struction du bureau de la Cir ication Selection tation 6 4 4 7 6 1 8 eries management conscription en charge de la pêche et de l’Aquaculture à Besalampy. MG-MRHP-28755BIS-CS-QC BS // MG-PM-177 / Élaboratio Component 3. Strengthenin n des plans d'action aux rest g capacities for engaging in Quality And Cost- 2019-08-3 2020-01-2 2020-02-2 2020-04-0 2020-04-1 2021-02-0 2021-10-0 rictions de ressources (PARA IDA / 59870 Post Open - National 875,300.00 0.00 Canceled 2019-08-22 alternative fishing practices Based Selection 0 9 8 7 3 9 7 R) / Diagnostic des besoins and livelihoods activities en activités alternatives ada ptées à chaque région ultra prioritaire (AGR) MG-MRHP-150349-CS-CQS / Recrutement de consultant national pour assurer le renf Component 2. Strengthenin orcement de capacité des a Consultant Qualif Pending Implem 2022-01-1 2022-02-0 2022-03-2 2022-04-0 2022-04-2 IDA / 59870 g capacities for priority fish Post Open - National 1,500.00 0.00 2022-01-04 gents de l’administration de ication Selection entation 1 8 0 3 4 eries management s pêches et des responsable s des textes administratifs e n leadership et Gestion axés sur les résultats (2.1.1.1.04) MG-MRHP-14959-CS-CQS / Component 3. Strengthenin Mise en place d’une règleme g capacities for engaging in Consultant Qualif Open - Internation 2021-11-1 2022-01-2 2022-03-1 2022-05-1 2022-11-0 IDA / 59870 Post 60,000.00 0.00 Canceled 2021-09-30 ntation de base concernant l alternative fishing practices ication Selection al 4 8 4 3 9 a sécurité en mer de la petit and livelihoods activities e pêche MG-MRHP-263393-CS-CQS / Recrutement des BE pour ré Component 3. Strengthenin aliser les études techniques, g capacities for engaging in Consultant Qualif 2021-12-1 2021-12-1 2021-12-2 2022-01-2 2022-03-1 2022-02-2 2022-06-0 2022-04-0 2022-07-2 2022-09-2 IDA / 59870 Post Open - National 77,000.00 98,415.82 Signed 2021-11-23 PGES et contrôle et surveilla alternative fishing practices ication Selection 5 4 1 7 7 6 9 2 0 9 nce des travaux de construc and livelihoods activities tion des petites infrastructur es de pêches (relance lot 1 et 5) MG-MRHP-264080-CS-CQS / Recrutement des BE pour é Component 3. Strengthenin tudes techniques, PGES et C g capacities for engaging in Consultant Qualif 2021-12-1 2021-12-2 2021-12-2 2022-01-2 2022-03-1 2022-02-2 2022-06-0 2022-03-3 2022-07-2 2022-10-1 IDA / 59870 Post Open - National 84,000.00 111,436.73 Signed 2021-11-30 ontrôle et surveillance des tr alternative fishing practices ication Selection 5 1 1 4 7 3 9 0 0 6 avaux de construction des b and livelihoods activities âtiments abritant les chamb res froide repartis en 3 lots MG-MRHP-288108-CS-CQS / Component 2. Strengthenin Mise à jour l’enquête cadre Consultant Qualif Under Implemen 2022-04-1 2022-05-0 2022-05-0 2022-06-1 2022-08-0 2022-07-1 2022-11-1 2022-08-1 2023-02-1 IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 2022-04-11 nationale 2012-2013 sur la ication Selection tation 8 2 3 5 5 5 8 9 5 eries management petite pêche maritime et la pêche continentale MG-MRHP-232529-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- Open - Internation 2022-01-2 2021-06-1 2021-07-2 2021-08-2 2021-09-2 2021-10-2 2021-11-2 2022-11-2 IDA / 59870 g capacities for priority fish Prior 2,000,000.00 0.00 Canceled 2021-05-20 our le développement de la Based Selection al 3 0 4 1 0 5 9 9 eries management planification spatiale mariti me PSM à Madagascar MG-MRHP-232529 BIS-CS-Q CBS / Recrutement d'une fir Component 2. Strengthenin Quality And Cost- Open - Internation Under Implemen 2022-04-2 2022-05-1 2022-04-2 2022-06-2 2022-07-2 2022-08-2 2022-09-2 2022-10-3 2023-10-3 me pour le développement IDA / 59870 g capacities for priority fish Post 600,000.00 0.00 2022-04-20 Based Selection al tation 5 1 8 4 2 1 5 0 0 de la planification spatiale eries management maritime PSM à Madagascar MG-MRHP-239018-CS-CQS / Recrutement d’une firme po Component 2. Strengthenin ur élaborer et mettre à jour l Consultant Qualif 2021-10-1 2021-10-0 2021-12-2 2021-11-1 2021-12-1 2021-12-2 2022-05-0 IDA / 59870 g capacities for priority fish Post Open - National 56,000.00 0.00 Canceled 2021-09-22 es textes d’application de la ication Selection 9 6 1 0 0 4 3 eries management nouvelle loi portant Code de la Pêche et de l'Aquaculture à Madagascar MG-MRHP-28757-CS-QCBS// Component 3. Strengthenin MG-PM-179 / Étude de faisa g capacities for engaging in Quality And Cost- Open - Internation 2021-10-3 2022-01-1 2022-02-2 2022-04-1 2022-06-1 2022-08-1 2023-08-1 bilité technique des constru IDA / 59870 Post 795,000.00 0.00 Canceled 2021-10-01 alternative fishing practices Based Selection al 1 4 8 4 3 2 2 ctions d'infrastructures de p and livelihoods activities êche(APS & APD) (33 débarc adères, 8 marchés couverts) MG-MRHP-252969-CS-CQS / Component 3. Strengthenin Recrutement d'une firme po g capacities for engaging in Consultant Qualif 2021-10-1 2021-11-1 2021-12-1 2022-01-0 2022-12-2 IDA / 59870 Post Open - National 100,000.00 0.00 Canceled 2021-09-30 ur la promotion de transfert alternative fishing practices ication Selection 4 8 8 1 7 financier pour les 03 ZUP. and livelihoods activities MG-MRHP-218708-CS-QCBS Component 3. Strengthenin / Recrutement d’une firme g capacities for engaging in Quality And Cost- Pending Implem 2022-05-1 2022-06-1 2022-07-1 2022-08-0 2022-09-1 2022-10-1 2023-02-1 en charge de l’élaboration d’ IDA / 59870 Post Open - National 100,000.00 0.00 2022-05-10 alternative fishing practices Based Selection entation 5 9 9 9 3 8 5 un plan de formation/renforc and livelihoods activities ement de capacités des élus et des acteurs MG-MRHP-198566-CS-QCBS / Recrutement des BE pour é Component 3. Strengthenin tudes techniques- PGES et c g capacities for engaging in Quality And Cost- 2020-11-1 2020-12-2 2021-01-2 2021-02-2 2021-04-0 2021-05-0 2021-12-0 IDA / 59870 Post Open - National 240,000.00 0.00 Canceled 2020-10-23 ontrôle et surveillance des tr alternative fishing practices Based Selection 3 7 6 5 1 6 2 avaux des petites infrastruct and livelihoods activities ures de pêches pour les 3 Z ups répartis en 8 Lots. MG-MRHP-239018-CS-CQS- 2 / Recrutement d'une firme Component 2. Strengthenin pour élaborer et mettre à jo Consultant Qualif Under Implemen 2022-05-1 2022-05-0 2022-05-1 2022-06-0 2022-07-0 2022-07-2 2022-11-2 IDA / 59870 g capacities for priority fish Post Open - National 56,000.00 0.00 2022-04-18 ur les textes d'application d ication Selection tation 0 2 6 6 6 0 7 eries management e la nouvelle loi portant Cod e de la Pêche et de l'Aquacu lture à Madagascar. MG-MRHP-14951-CS-QCBS / PA 65: Etudes techniques : - Clôture de l'enceinte DRRHP Component 2. Strengthenin Fénérive - Construction des Quality And Cost- 2019-08-1 2019-09-2 2019-10-2 2019-11-2 2019-12-3 2020-02-0 2021-02-0 IDA / Q9790 g capacities for priority fish Post Open - National 35,000.00 0.00 Canceled 2019-07-26 Bureaux de 06 DRRHP - Exte Based Selection 6 9 7 6 1 4 3 eries management nsion de l'ASH à Antsiranana et Morondava - Construction local pour bureau UGP et 0 8 CirRHP (APS/APD) MG-MRHP-285789-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif 2022-04-1 2022-06-0 2022-07-0 2022-08-0 2023-02-0 ur mettre à jour l’enquête c IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 Canceled 2022-03-28 ication Selection 8 1 1 5 1 adre nationale 2012-2013 s eries management ur la petite pêche maritime et la pêche continentale MG-MRHP-150366-CS-CQS / RECRUTEMENT D'UN CONSU Component 2. Strengthenin LTANT NATIONAL POUR LA F Consultant Qualif 2021-07-3 2021-08-2 2021-10-0 2021-10-2 2021-12-1 IDA / 59870 g capacities for priority fish Post Open - National 15,000.00 0.00 Canceled 2021-07-23 ORMATION ET RENFORCEME ication Selection 0 7 6 0 9 eries management NT DE CAPACITE DE L’EQUIP E EN COMMUNICATION (2.1. 4.1.05) MG-MRHP-150361-CS-CQS / RECRUTEMENT D'UN CONSU LTANT NATIONAL POUR LE R Component 2. Strengthenin ENFORCEMENT DE CAPACIT Consultant Qualif Pending Implem 2022-11-0 2022-12-0 2023-01-1 2023-01-2 2023-03-3 IDA / 59870 g capacities for priority fish Post Open - National 8,000.00 0.00 2022-11-01 E DU PERSONNEL DE L’AUT ication Selection entation 8 6 5 9 0 eries management ORITE SANITAIRE HALIEUTIQ UE EN INFORMATIQUE (BUR EAUTIQUE ET PROGRAMMAT ION) AU NIVEAU NATIONAL ( 2.1.7.2.02) MG-MRHP-298214-CS-CQS / Recrutement d’une firme ch Component 3. Strengthenin argée de l’appui à la promot g capacities for engaging in Consultant Qualif Under Implemen 2022-06-1 2022-07-1 2022-08-1 2022-09-1 2022-10-0 2023-09-2 IDA / 59870 Post Open - National 70,000.00 0.00 2022-06-30 ion des produits halieutique alternative fishing practices ication Selection tation 5 4 8 7 1 6 s valorisés au niveau des ZU and livelihoods activities P sur le marché national/inte rnational MG-MRHP-304395-CS-CQS / Recrutement d’une firme po Component 3. Strengthenin ur l’étude de faisabilité de m g capacities for engaging in Consultant Qualif Under Implemen 2022-07-2 2022-08-1 2022-10-0 2022-11-0 2022-12-0 2023-03-0 IDA / 59870 Post Open - National 60,000.00 0.00 2022-07-29 ise en place d’unités de pro alternative fishing practices ication Selection tation 2 9 2 1 6 6 duction artisanale de conser and livelihoods activities ves de sardines à BATAN et BA MG-MRHP-304402-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- Open - Internation Under Implemen 2022-08-0 2022-08-1 2022-08-2 2022-10-0 2022-10-3 2022-11-2 2023-01-0 2023-02-0 2023-08-0 IDA / 59870 g capacities for priority fish Post 205,000.00 0.00 2022-07-29 our la lise en place des outil Based Selection al tation 3 9 2 2 0 9 3 7 6 eries management s d'aménagement des pêch eries à Madagascar MG-MRHP-307091-CS-CQS / Component 2. Strengthenin Evaluation des emplois direc Consultant Qualif Under Implemen 2022-09-1 2022-09-0 2022-10-0 2022-10-1 2022-11-1 2022-12-2 2023-06-1 IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2022-08-12 ts et indirects issus de la pet ication Selection tation 5 2 7 6 5 0 8 eries management ite pêche au niveau des 03 ZUP du Projet MG-MRHP-307110-CS-CQS / Elaboration de Cartographie Component 2. Strengthenin Consultant Qualif Under Implemen 2022-09-1 2022-09-0 2022-10-3 2022-10-1 2022-11-1 2022-12-2 2023-06-1 détaillée pour le développe IDA / 59870 g capacities for priority fish Post Open - National 150,000.00 0.00 2022-08-12 ication Selection tation 5 2 1 6 5 0 8 ment de l’holothuriculture, l eries management a crabiculture, l’algoculture et l’aquaculture continental e. MG-MRHP-307200-CS-CQS / Recrutement d’une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2022-09-1 2022-08-3 2022-10-2 2022-10-0 2022-11-0 2022-12-0 2023-06-1 ur la mise en place d’un site IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2022-08-09 ication Selection tation 5 0 7 4 3 8 6 web dynamique du Ministèr eries management e de la Pêche et de l’Écono mie Bleue MG-MRHP-306851-CS-CQS / Etude technique, l'élaboratio Component 2. Strengthenin Consultant Qualif Under Implemen 2022-11-2 2022-10-2 2022-12-1 2022-12-0 2023-01-0 2023-02-0 2023-08-0 n du PGES , contrôle et surv IDA / 59870 g capacities for priority fish Post Open - National 60,000.00 0.00 2022-09-29 ication Selection tation 4 0 5 3 2 6 5 eillance des travaux de cons eries management truction de l'antenne CDPH M à Besalampy MG-MRHP-306857-CS-CQS / Component 3. Strengthenin Etude techniques élaboratio g capacities for engaging in Consultant Qualif Under Implemen 2022-11-2 2022-10-1 2022-12-1 2022-12-0 2023-01-0 2023-02-0 2023-08-0 n PGES et Contrôle & surveil IDA / 59870 Post Open - National 35,000.00 0.00 2022-09-28 alternative fishing practices ication Selection tation 4 9 6 2 1 5 4 lance de la Construction déb and livelihoods activities arcadère à Ankazomborona MG-MRHP-320120-CS-CQS / Component 3. Strengthenin Recrutement d'une associati g capacities for engaging in Consultant Qualif Under Implemen 2022-10-2 2022-10-2 2022-10-3 2022-11-1 2022-12-0 2022-12-1 2023-09-2 on pour l’étude et la mise en IDA / 59870 Post Open - National 40,000.00 0.00 2022-10-21 alternative fishing practices ication Selection tation 7 2 1 9 3 7 9 place d’habitats artificiels d and livelihoods activities ans quatre zones côtières Page 9 MG-MRHP-320122-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2022-10-2 2022-11-0 2022-12-0 2022-12-0 2023-01-0 2023-01-2 2023-05-2 ur l'élaboration de la Politiqu IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 0.00 2022-10-21 ication Selection tation 5 4 6 9 8 9 9 e Nationale intégrée de la G eries management ouvernance de l'Océan à Ma dagascar MG-MRHP-355022-CS-CQS / Component 3. Strengthenin Recrutement d’une ONG po g capacities for engaging in Consultant Qualif Under Implemen 2023-05-0 2023-04-2 2023-05-2 2023-05-1 2023-05-2 2023-05-3 2023-08-2 IDA / 59870 Post Open - National 250,000.00 0.00 2023-04-09 ur la mise en œuvre des Acti alternative fishing practices ication Selection tation 9 4 3 9 4 1 9 vités Alternatives (PARAR/A and livelihoods activities GR) MG-MRHP-239021-CS-CQS / Component 4. Project mana Consultant Qualif Under Implemen 2023-05-2 2023-05-2 2023-05-2 2023-06-0 2023-07-0 2023-07-2 2023-09-2 Recrutement firme pour l'év IDA / 59870 Post Open - National 75,000.00 0.00 2023-05-10 gement and coordination ication Selection tation 3 4 5 7 7 1 9 aluation finale du projet SWI OFish2 MG-MRHP-239020-CS-CQS / Component 2. Strengthenin Recrutement d'une firme po Consultant Qualif Under Implemen 2023-05-0 2023-05-2 2023-05-2 2023-06-2 2023-07-1 2023-07-2 2023-09-2 IDA / 59870 g capacities for priority fish Post Open - National 25,000.00 0.00 2023-05-10 ur l'élaboration de manuel d ication Selection tation 9 4 2 8 2 6 4 eries management e l'audit interne du MPEB MG-MRHP-362176-CS-CQS / Renforcement de capacité d Component 3. Strengthenin u comité de gestion des infr g capacities for engaging in Consultant Qualif Under Implemen 2023-06-1 2023-07-2 2023-08-0 2023-08-1 2023-09-1 IDA / 59870 Post Open - National 270,000.00 0.00 2023-05-26 astructures sur la gestion de alternative fishing practices ication Selection tation 6 1 5 5 4 s infrastructures et appui à l' and livelihoods activities opérationnalisation des petit es infrastructures; Component 3. Strengthenin MG-MRHP-363621-CS-CQS / g capacities for engaging in Consultant Qualif Under Implemen 2023-06-0 2023-06-1 2023-06-1 2023-06-2 2023-07-1 2023-07-2 2023-09-1 Formation sur la fabrication IDA / 59870 Post Open - National 30,000.00 0.00 2023-05-30 alternative fishing practices ication Selection tation 6 4 4 4 4 1 9 des pirogues and livelihoods activities MG-MRHP-4770-CS-CQS / C onception d'un système de c Component 2. Strengthenin Consultant Qualif Open - Internation 2017-02-2 2017-04-0 2017-05-0 2017-06-1 2017-12-0 ollecte de données pour les IDA / Q9790 g capacities for priority fish Post 10,000.00 0.00 Canceled 2017-02-01 ication Selection al 2 7 7 1 8 pêcheries traditionnelles, y eries management compris une stratégie d'éch antillonnage appropriée MG-MRHP-4769-CS-CQS / Mi Component 2. Strengthenin se à jour de la Stratégie d'a Consultant Qualif Open - Internation 2017-02-2 2017-04-0 2017-05-0 2017-06-1 2017-12-0 IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2017-02-01 quaculture et élaboration de ication Selection al 2 7 7 1 8 eries management plan de développement des 03 filières aquaculture INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-23395-CS-INDV// PA75 / Recrutement d'un (0 Component 4. Project mana Individual Consul 2017-08-0 2017-09-2 2017-09-2 2017-10-1 2017-10-0 2017-11-2 2017-10-0 2018-05-2 2019-04-0 1) Spécialiste en Passation d IDA / Q9790 Post Open 15,600.00 15,412.69 Completed 2017-08-02 gement and coordination tant Selection 3 0 1 1 2 2 3 1 1 es Marchés en appui à l'équi pe de passation des marché s de l'UGP SWIOFish2. MG-MRHP-28176-CS-INDV// MG-PM-24 / Diagnostic des t echniques de valorisation pr Component 3. Strengthenin atiquées à Madagascar et le g capacities for engaging in Individual Consul 2018-02-1 2018-03-1 2018-04-1 2018-10-0 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2017-11-30 s bonnes pratique en Afriqu alternative fishing practices tant Selection 8 8 0 7 e et identifier les besoins en and livelihoods activities technique de valorisation de s produits halieutiques de ch aque région ultra prioritaire MG-MRHP-28321-CS-INDV// Component 3. Strengthenin MG-PM-26 / Évaluation du ni g capacities for engaging in Individual Consul 2018-01-1 2018-01-3 2018-03-1 2018-09-1 IDA / D1720 Post Open 90,000.00 0.00 Canceled 2017-10-30 veau de vulnérabilité des m alternative fishing practices tant Selection 0 1 4 0 énages bénéficiaires and livelihoods activities MG-MRHP-28328-CS-INDV// Component 3. Strengthenin MG-PM-30 / Élaboration du p g capacities for engaging in Individual Consul 2018-01-2 2018-02-1 2018-03-2 2018-09-2 IDA / 59870 Post Open 10,500.00 0.00 Canceled 2017-10-30 lan stratégique de développ alternative fishing practices tant Selection 5 5 9 5 ement local (PCD et PLD) and livelihoods activities MG-MRHP-28338-CS-INDV// Component 4. Project mana Individual Consul 2017-12-2 2018-01-1 2018-02-2 2018-08-2 MG-PM-35 / Assistants coord IDA / 59870 Post Open 20,800.00 0.00 Canceled 2017-10-16 gement and coordination tant Selection 0 0 1 0 inateurs locaux UGL MG-MRHP-28344-CS-INDV// MG-PM-41 / Élaboration d'un Component 4. Project mana Individual Consul 2018-02-2 2018-03-1 2018-04-2 2018-10-2 IDA / 59870 Post Open 10,000.00 0.00 Canceled 2017-12-15 e stratégie du plan de comm gement and coordination tant Selection 5 8 9 6 unication du projet SWIOFis h2 MG-MRHP-28345-CS-INDV// Component 4. Project mana Individual Consul 2018-01-2 2018-02-1 2018-03-3 2018-09-2 MG-PM-42 / Mise en place d IDA / 59870 Post Open 2,000.00 0.00 Canceled 2017-11-15 gement and coordination tant Selection 6 6 0 6 u site internet du projet SWI OFish2 MG-MRHP-28346-CS-INDV// Component 4. Project mana Individual Consul 2018-02-1 2018-03-1 2018-04-2 2018-10-1 MG-PM-43 / Mission de couv IDA / 59870 Post Open 1,000.00 0.00 Canceled 2017-12-15 gement and coordination tant Selection 8 1 2 9 erture des autres activités d e communication MG-MRHP-27289-CS-INDV// Component 2. Strengthenin PA27 / Évaluation et dévelop Individual Consul 2015-09-0 2017-10-2 2017-11-1 2016-11-0 2017-12-2 2017-11-1 2018-06-1 2018-08-3 IDA / Q9790 g capacities for priority fish Post Open 50,000.00 35,963.63 Completed 2017-09-07 pement de la recherche hali tant Selection 9 6 6 1 1 4 9 0 eries management eutique (pour les 5 filières p rioritaires MG-MRHP-28651-CS-INDV// Component 2. Strengthenin Individual Consul 2018-09-0 2018-09-2 2018-11-0 2019-05-0 MG-PM-111 / Assistance Tec IDA / 59870 g capacities for priority fish Post Open 10,000.00 0.00 Canceled 2018-07-02 tant Selection 5 6 7 6 hnique juridique pour le SLC eries management MG-MRHP-28653-CS-INDV// MG-PM-112 / Étude et analy Component 2. Strengthenin se diagnostiques des stratég Individual Consul 2018-04-0 2018-04-2 2018-06-0 2018-12-0 IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-01-30 ies du secteur et des ancien tant Selection 5 6 7 4 eries management s plans directeurs et élabora tion du nouveau plan directe ur MG-MRHP-28692-CS-INDV// Component 2. Strengthenin MG-PM-136 / Développemen Individual Consul 2018-05-0 2018-05-2 2018-06-3 2018-12-2 IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-03-01 t des points de référence op tant Selection 5 6 0 7 eries management érationnels pour la gestion d e la pêche crevettière MG-MRHP-28704-CS-INDV// Component 2. Strengthenin Individual Consul 2018-08-0 2018-08-2 2018-09-3 2019-03-2 MG-PM-148 / Audit techniqu IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-06-01 tant Selection 5 6 0 9 e et financier de la pêche au eries management x thons MG-MRHP-28744-CS-INDV// Component 3. Strengthenin MG-PM-169 / Prestataire for g capacities for engaging in Individual Consul 2019-01-0 2019-01-2 2019-03-0 2019-08-2 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2018-11-01 mateur en construction et e alternative fishing practices tant Selection 5 6 2 9 ntretien des embarcations and livelihoods activities MG-MRHP-28751-CS-INDV// Component 3. Strengthenin MG-PM-174 / Prestataire for g capacities for engaging in Individual Consul 2018-08-1 2018-09-0 2018-10-1 2019-04-1 IDA / 59870 Post Open 75,000.00 0.00 Canceled 2018-06-15 mateur en technique de val alternative fishing practices tant Selection 9 9 4 2 orisation and livelihoods activities MG-MRHP-28752-CS-INDV// Component 3. Strengthenin MG-PM-175 / Prestataire for g capacities for engaging in Individual Consul 2018-09-1 2018-10-0 2018-11-1 2019-05-1 IDA / 59870 Post Open 25,000.00 0.00 Canceled 2018-06-29 mateur en technique comm alternative fishing practices tant Selection 7 8 2 1 erciale and livelihoods activities MG-MRHP-28758-CS-INDV// MG-PM-181 / Étude d'impact Component 3. Strengthenin environnemental et social d g capacities for engaging in Individual Consul 2018-07-1 2018-08-0 2018-09-1 2019-03-1 IDA / 59870 Post Open 90,000.00 0.00 Canceled 2018-05-30 es constructions d'infrastruc alternative fishing practices tant Selection 8 8 2 1 tures de pêche(APS & APD) ( and livelihoods activities 33 débarcadères, 8 marchés couverts) MG-MRHP-28762-CS-INDV// Component 3. Strengthenin MG-PM-184 / Gestion et mis g capacities for engaging in Individual Consul 2018-07-1 2018-08-0 2018-09-1 2019-03-1 IDA / V0500 Post Open 15,000.00 0.00 Canceled 2018-05-30 e en œuvre : évaluation de l alternative fishing practices tant Selection 8 8 2 1 a mise en place de l'électrifi and livelihoods activities cation hors grille MG-MRHP-28765-CS-INDV// Component 4. Project mana Individual Consul 2018-11-1 2018-12-1 2019-01-1 2019-07-1 MG-PM-188 / Responsable P IDA / 59870 Post Open 7,800.00 0.00 Canceled 2018-10-01 gement and coordination tant Selection 9 0 4 3 assation de marché MG-MRHP-28769-CS-INDV// MG-PM-191 / Mission de cou Component 4. Project mana Individual Consul 2018-04-1 2018-05-1 2018-06-1 2018-12-1 IDA / 59870 Post Open 1,000.00 0.00 Canceled 2018-03-01 verture des autres activités gement and coordination tant Selection 9 0 4 1 de communication MG-MRHP-28770-CS-INDV// Component 4. Project mana Individual Consul 2018-04-1 2018-05-0 2018-06-1 2018-12-1 MG-PM-192 / Réalisation du IDA / 59870 Post Open 8,000.00 0.00 Canceled 2018-02-28 gement and coordination tant Selection 8 9 3 0 Bulletin trimestriel SWIOFish 2 MG-MRHP-14956-CS-INDV// 70 / PA 70: Etude sur l'adapt Component 2. Strengthenin Individual Consul 2018-02-1 2018-02-2 2018-04-0 2018-10-0 ation des missions et attribu IDA / Q9790 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2017-11-30 tant Selection 0 4 7 4 tions du MRHP par rapport a eries management ux défis du développement r ural MG-MRHP-14959-CS-INDV// Component 3. Strengthenin PA71 / PA 71: Mise en place g capacities for engaging in Individual Consul 2018-07-2 2018-08-0 2018-09-2 2019-03-1 IDA / Q9790 Post Open 1,000.00 0.00 Canceled 2018-05-31 d'une règlementation de bas alternative fishing practices tant Selection 6 9 0 9 e concernant la sécurité en and livelihoods activities mer de la petite pêche MG-MRHP-14955-CS-INDV// Component 2. Strengthenin 69 / PA 69: Elaboration du S Individual Consul 2018-06-2 2018-07-1 2018-08-1 2019-02-1 IDA / Q9790 g capacities for priority fish Post Open 8,000.00 0.00 Canceled 2018-05-15 chéma d'aménagement aqu tant Selection 6 0 4 0 eries management acole national (algues, crab es, holothurie etc) MG-MRHP-14954-CS-INDV// PA68 / PA 68: Conception d' Component 2. Strengthenin Individual Consul 2018-02-0 2018-02-1 2018-03-2 2018-09-2 un système de collecte de d IDA / Q9790 g capacities for priority fish Post Open 10,000.00 0.00 Canceled 2017-12-30 tant Selection 3 7 4 0 onnées pour les pêcheries tr eries management aditionnelles, y compris une stratégie MG-MRHP-14497-CS-INDV// PA-42 / PA 42: Etude sur les Component 2. Strengthenin Individual Consul 2017-07-0 2017-07-1 2017-08-1 2018-02-1 FFOM et mesures nécessaire IDA / Q9790 g capacities for priority fish Post Open 25,000.00 0.00 Canceled 2017-05-29 tant Selection 3 0 4 0 s pour le développement de eries management la pêche nationale et attirer la flotte étrangère MG-MRHP-14950-CS-INDV// PA64 / PA 64: Etude sur les Component 2. Strengthenin besoins en formation, en Eq Individual Consul 2017-07-0 2017-07-1 2017-08-0 2018-02-0 IDA / Q9790 g capacities for priority fish Prior Open 20,000.00 0.00 Canceled 2017-05-29 uipements et immobiliers de tant Selection 3 0 7 3 eries management l'Administration (Central et DRRHP) Plans de formation et d'investissement MG-MRHP-14948-CS-INDV// Component 2. Strengthenin PA21 / PA 21: Etude de faisa Individual Consul 2018-06-2 2018-07-0 2018-07-3 2019-01-2 IDA / Q9790 g capacities for priority fish Post Open 20,000.00 0.00 Canceled 2018-05-15 bilité du projet d'Ecole Natio tant Selection 6 3 1 7 eries management nale Halieutique, les besoins en formation Page 10 MG-MRHP-28167-CS-QCBS// MG-PM-15 / Développement Component 2. Strengthenin et mise en œuvre du systèm Individual Consul 2018-03-1 2018-04-0 2018-05-1 2018-11-1 IDA / D1720 g capacities for priority fish Post Open 5,000.00 0.00 Canceled 2017-12-15 e de collecte de données po tant Selection 2 2 4 0 eries management ur les pêcheries traditionnell es, y compris une stratégie d'échantillonnage approprié e MG-MRHP-28339-CS-CQS// Component 4. Project mana Individual Consul 2017-08-2 2017-12-0 2018-01-2 2017-12-2 2018-01-2 2018-02-0 2018-02-1 2018-07-3 MG-PM-37 / Recrutement d'u IDA / 59870 Post Open 4,000.00 23,250.53 Signed 2017-10-19 gement and coordination tant Selection 4 7 3 8 3 1 7 1 n Chef Comptable MG-MRHP-28711-CS-QCBS// MG-PM-153 / Étude de prosp Component 2. Strengthenin Individual Consul 2018-12-0 2018-12-2 2019-02-0 2019-08-0 ection des lieux d'implantati IDA / 59870 g capacities for priority fish Post Open 1,500.00 0.00 Canceled 2018-10-01 tant Selection 5 6 6 5 on des deux antennes regio eries management nales de l'USTA (Majunga, T amatave) MG-MRHP-28712-CS-QCBS// Component 2. Strengthenin Individual Consul 2019-02-1 2019-03-0 2019-04-1 2019-10-0 MG-PM-154 / Étude de mise IDA / 59870 g capacities for priority fish Post Open 1,500.00 0.00 Canceled 2018-12-03 tant Selection 3 6 0 7 en place des antennes régio eries management nales MG-MRHP-33990-CS-INDV// Component 2. Strengthenin Individual Consul 2018-01-2 2018-02-1 2018-03-2 2018-09-2 MG-PM 68 / Assistance tech IDA / D1720 g capacities for priority fish Post Open 26,000.00 0.00 Canceled 2017-11-02 tant Selection 1 1 5 1 nique pour le suivi des trava eries management ux de carénage MG-MRHP-86203-CS-INDV// Component 2. Strengthenin Individual Consul 2019-01-3 2019-03-0 2019-04-2 2019-07-0 2020-01-0 PA13 / Mise à jour de la Stra IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-11-22 tant Selection 1 7 1 5 1 tégie Nationale de l'Aquacul eries management ture MG-MRHP-86204-CS-INDV / Component 2. Strengthenin Recrutement d'un consultan Individual Consul 2018-12-1 2019-03-1 2019-02-2 2019-04-1 2019-02-2 2019-06-2 2018-12-2 2019-12-2 2020-04-0 IDA / D1720 g capacities for priority fish Post Open 55,000.00 39,810.58 Completed 2018-11-26 t pour convertir OPENARTFIS tant Selection 7 1 6 0 6 4 6 1 2 eries management H dans une base de donnée s basée sur le We MG-MRHP-86205-CS-INDV// Component 2. Strengthenin MG-PM 51/18 / Assistance te Individual Consul 2018-08-1 2019-03-0 2018-10-2 2019-04-0 2018-11-0 2019-06-2 2018-11-1 2019-12-1 IDA / D1720 g capacities for priority fish Post Open 26,000.00 24,252.91 Signed 2018-11-22 chnique pour le suivi des tra tant Selection 0 7 3 6 8 0 3 7 eries management vaux de carénage de l'Atsan tsa MG-MRHP-105669-CS-INDV Component 3. Strengthenin / Recrutement d'agence de g capacities for engaging in Individual Consul 2019-03-2 2019-04-2 2019-04-3 2019-05-2 2019-11-2 communication pour la conc IDA / 59870 Post Open 5,625.00 0.00 Canceled 2019-03-12 alternative fishing practices tant Selection 0 3 0 8 4 eption et production des sup and livelihoods activities ports de communications rel atifs au MDGP MG-MRHP-119243-CS-INDV / Assistance technique pour Component 2. Strengthenin Individual Consul 2019-08-0 2019-11-2 2020-01-1 2020-03-2 2020-09-2 la coordination génerale des IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2019-08-15 tant Selection 9 8 2 7 3 activités durant l'élaboration eries management du PAP Atsimo Atsinanana MG-MRHP-119244-CS-INDV / Etude sur l'analyse de prob Component 2. Strengthenin Individual Consul 2019-08-0 2020-01-2 2020-01-1 2020-03-1 2020-02-2 2020-05-1 2020-03-0 2020-11-0 lématiques liées à la pratiqu IDA / D1720 g capacities for priority fish Post Open 20,000.00 10,846.29 Signed 2019-10-15 tant Selection 2 8 7 3 1 2 9 8 e courante des sennes de pl eries management age dans la Baie d’ Antongil MG-MRHP-119261-CS-INDV Component 3. Strengthenin / Prestataire formateur en c g capacities for engaging in Individual Consul 2019-12-2 2020-01-2 2020-03-2 2020-09-2 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2019-09-15 onstruction et entretien des alternative fishing practices tant Selection 9 8 8 4 engins de pêche and livelihoods activities Component 3. Strengthenin MG-MRHP-119286-CS-INDV g capacities for engaging in Individual Consul 2019-12-1 2020-01-1 2020-03-2 2020-09-2 / Consultance et appui à la c IDA / 59870 Post Open 45,900.00 0.00 Canceled 2019-08-30 alternative fishing practices tant Selection 3 2 7 3 omposante 3 and livelihoods activities MG-MRHP-119288-CS-INDV Component 4. Project mana Individual Consul 2019-08-2 2019-10-2 2019-10-2 2019-11-2 2019-11-1 2020-01-1 2019-11-2 2020-07-1 / Consultance et appui à la IDA / 59870 Post Open 15,300.00 11,155.20 Terminated 2019-07-31 gement and coordination tant Selection 8 9 2 8 2 8 6 6 composante 4 MG-MRHP-119289-CS-CDS / Component 4. Project mana 2019-07-2 2019-08-1 2019-08-0 2019-11-1 2019-08-1 2020-05-1 IDA / 59870 Post Direct Selection Direct 20,400.00 32,788.66 Signed 2019-07-15 Responsable Administratif et gement and coordination 9 9 8 7 6 5 Financier MG-MRHP-119291-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2019-10-1 2019-10-2 2019-11-2 2020-01-1 2020-07-1 IDA / 59870 Post Open 4,200.00 0.00 2019-07-31 / Personnel d'appui : Secréta gement and coordination tant Selection tation 0 9 8 8 6 ire MG-MRHP-28341-CS-CQS// Component 4. Project mana Individual Consul 2017-08-2 2019-09-0 2018-01-2 2019-09-2 2018-01-2 2019-10-2 2018-03-0 2020-04-2 MG-PM-38 / Recrutement de IDA / 59870 Post Open 24,000.00 47,399.30 Signed 2019-07-15 gement and coordination tant Selection 4 2 2 3 3 8 6 5 deux (02) Comptables MG-MRHP-119292-CS-INDV Component 4. Project mana Individual Consul Pending Implem 2019-07-2 2019-08-1 2019-09-1 2020-03-1 / Personnel d'appui (Femme IDA / 59870 Post Limited 1,320.00 0.00 2019-07-15 gement and coordination tant Selection entation 0 0 4 2 de ménage et gardien) MG-MRHP-119293-CS-INDV Component 4. Project mana Individual Consul Pending Implem 2019-07-2 2019-08-1 2019-09-1 2020-03-1 IDA / 59870 Post Limited 25,200.00 0.00 2019-07-15 / Personnel d'appui : Chauffe gement and coordination tant Selection entation 0 0 4 2 ur MG-MRHP-28673-CS-INDV// Component 2. Strengthenin MG-PM-124 / Amélioration d Individual Consul 2019-09-0 2019-09-2 2019-10-3 2020-04-2 IDA / D1720 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2019-07-01 e la base de données pour l tant Selection 4 5 0 7 eries management es pêcheries industrielles MG-MRHP-23395-CS-INDV// SPM / Frais de personnel du projet : recrutement d'un (0 Component 4. Project mana Individual Consul 2019-08-0 2019-09-1 2019-10-0 2019-10-0 2019-10-1 2019-11-0 2019-10-2 2020-05-0 IDA / 59870 Post Open 88,400.00 14,322.53 Signed 2019-07-26 1) Spécialiste en Passation d gement and coordination tant Selection 1 3 4 4 5 8 1 6 es Marchés en appui à l'équi pe de passation des marché s de l'UGP SWIOFish2. MG-MRHP-119243BIS-CS-IN DV / Recrutement d’un cons ultant individuel pour l’assis Component 2. Strengthenin Individual Consul 2019-08-2 2019-12-1 2019-10-2 2020-01-2 2019-11-2 2020-04-1 2019-12-0 2020-10-0 tance technique de l’Admini IDA / 59870 g capacities for priority fish Post Open 35,000.00 89,509.64 Signed 2019-08-15 tant Selection 2 3 2 7 7 1 2 8 stration en charge de la Pêc eries management he et de l’Aquaculture et de l’UGP du Projet SWIOFish2 d ans le cadre de la Cogestion MG-MRHP-123343-CS-INDV / Développer la base de don nées intégrée des pêches de Component 2. Strengthenin Madagascar et le registre de Individual Consul 2019-08-2 2019-11-0 2019-10-2 2019-11-2 2020-02-1 2020-01-0 2020-02-2 2020-07-0 IDA / D1720 g capacities for priority fish Post Open 50,000.00 38,851.99 Signed 2019-09-02 s pêcheurs et embarcations tant Selection 2 6 2 7 9 8 0 6 eries management dans une base de donnée b asé sur le Web (lignes des é tudes regroupées: 2.1.2.1.1 3 - 2.1.2.1.13.1 - 2.1.2.1.13. 2) MG-MRHP-28764-CS-INDV// Component 4. Project mana Individual Consul 2018-11-1 2018-12-1 2019-01-1 2019-07-1 MG-PM-187 / Assistants coor IDA / 59870 Post Open 62,400.00 0.00 Canceled 2018-10-01 gement and coordination tant Selection 9 0 4 3 dinateurs locaux UGL MG-MRHP-28735-CS-INDV// Component 3. Strengthenin MG-PM-164 / Recensement g capacities for engaging in Individual Consul 2018-05-0 2018-05-2 2018-06-2 2018-12-2 IDA / 59870 Post Open 20,000.00 0.00 Canceled 2018-02-28 et identification des bénéfici alternative fishing practices tant Selection 4 5 9 6 aires chaque année and livelihoods activities MG-MRHP-127608-CS-INDV Component 4. Project mana Individual Consul 2019-12-2 2020-01-2 2020-03-1 2020-09-0 IDA / 59870 Post Open 1,500.00 0.00 Canceled 2019-09-23 / Assistance technique - mai gement and coordination tant Selection 2 1 2 8 ntenance MG-MRHP-28926-CS-INDV// Component 4. Project mana Individual Consul 2018-03-2 2018-04-1 2018-05-1 2018-11-1 MG-PM-17 / Évaluation seme IDA / 59870 Post Open 3,500.00 0.00 Canceled 2018-01-15 gement and coordination tant Selection 1 1 6 2 strielle du projet MG-MRHP-127606-CS-INDV Component 2. Strengthenin Individual Consul 2019-12-1 2020-01-1 2020-03-0 2020-09-0 / Etude diagnostic sur la pêc IDA / 59870 g capacities for priority fish Post Open 20,000.00 0.00 Canceled 2019-09-18 tant Selection 7 6 7 3 herie crevettière à Madagas eries management car MG-MRHP-141087-CS-INDV Component 4. Project mana Individual Consul 2019-10-2 2019-11-2 2019-12-1 2019-11-2 2019-12-1 2019-11-2 2019-12-1 2022-11-2 / Recrutement d’un Chef Co IDA / 59870 Post Open 39,000.00 22,844.93 Signed 2019-10-31 gement and coordination tant Selection 8 1 1 3 3 7 9 6 mptable (CC) au sein de l’U GP MG-MRHP-141088-CS-INDV Component 4. Project mana Individual Consul 2019-10-2 2019-11-2 2019-12-0 2019-11-2 2019-12-1 2019-11-2 2019-12-1 2022-11-2 IDA / 59870 Post Open 24,000.00 17,668.00 Terminated 2019-10-31 / Recrutement d'un comptab gement and coordination tant Selection 8 1 9 3 3 7 8 6 le MG-MRHP-146229-CS-INDV / Recrutement d’un consulta Component 2. Strengthenin nt national pour animer l’ate Individual Consul 2019-10-1 2019-11-2 2019-10-2 2019-12-0 2019-11-1 2019-12-2 2019-12-0 2020-01-0 IDA / 59870 g capacities for priority fish Post Limited 2,800.00 2,496.64 Signed 2019-11-21 lier national relatif à la com tant Selection 4 6 3 1 3 2 5 5 eries management munication de la nouvelle loi portant Code de la Pêche et de l'Aquaculture à Madagas car MG-MRHP-146231-CS-INDV / Recrutement d’un Assistan t Technique pour les constru Component 4. Project mana Individual Consul 2019-12-0 2019-12-1 2020-01-1 2019-12-2 2020-01-2 2019-12-2 2020-01-2 2022-12-2 IDA / 59870 Post Open 25,000.00 25,491.34 Signed 2019-11-21 ctions et réhabilitations d’ in gement and coordination tant Selection 6 5 7 5 4 9 5 8 frastructures de pêche, com munautaires et administrati ves MG-MRHP-119287-CS-CDS / Component 4. Project mana 2019-10-2 2020-02-1 2020-08-0 Contrôle et surveillance de l IDA / 59870 Post Direct Selection Direct 12,000.00 0.00 Canceled 2019-08-30 gement and coordination 9 1 9 a construction de bureau de l'UGP centrale MG-MRHP-149046-CS-CDS / RECRUTEMENT DE CONSULT ANT NATIONAL POUR ASSUR Component 2. Strengthenin 2019-12-2 2020-01-0 2020-05-1 2020-01-2 2020-09-0 2020-02-0 ER LE RENFORCEMENT DE C IDA / 59870 g capacities for priority fish Post Direct Selection Direct 6,290.00 7,739.85 Signed 2019-12-30 6 5 4 0 5 4 APACITES DES BIOLOGISTES eries management DU CDA DANS LE DOMAINE DE L’AQUACULTURE MARINE ET DULCAQUICOLE (2.1.1.3. 03) MG-MRHP-160293-CS-INDV / Recrutement d'un consulta Component 2. Strengthenin Individual Consul 2020-02-2 2020-03-3 2020-06-1 2020-04-0 2020-09-1 2020-04-2 2020-11-2 2020-08-1 nt pour l'élaboration de proc IDA / 59870 g capacities for priority fish Post Open 15,000.00 86,190.00 Signed 2020-02-27 tant Selection 5 0 8 9 5 3 6 1 édure de délivrance des cart eries management es pêcheurs et d'immatricul ation des pirogues MG-MRHP-160452-CS-INDV Component 2. Strengthenin / Recrutement d’un Assistan Individual Consul 2020-03-0 2020-04-1 2020-07-0 2020-05-1 2020-08-1 2020-05-2 2020-08-1 2022-05-2 IDA / D1720 g capacities for priority fish Post Open 85,000.00 15,207.52 Signed 2020-03-10 t technique pour l’ Appui au tant Selection 6 9 1 0 7 4 9 4 eries management renforcement des capacités opérationnelles du CSP MG-MRHP-160443-CS-CDS / Component 2. Strengthenin Recrutement d'Institut de Fo Under Implemen 2020-03-0 2020-03-1 2020-04-1 2020-04-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 3,000.00 0.00 2020-03-09 rmation en technique d'anal tation 1 9 7 7 eries management yse de détection de maladie aquatique MG-MRHP-161605-CS-INDV / Recrutement d'un consulta Component 4. Project mana Individual Consul 2020-03-0 2020-04-2 2020-05-2 2020-05-1 2020-06-2 2020-05-2 2020-06-2 2020-09-2 nt individuel pour la réalisati IDA / 59870 Post Open 100,000.00 34,272.29 Signed 2020-03-13 gement and coordination tant Selection 2 7 6 1 2 5 4 2 on de l’évaluation à mi-parc ours des objectifs du projet SWIOFish2 MG-MRHP-161625-CS-CDS / Component 2. Strengthenin Recrutement d'un BE pour l 2020-03-2 2020-03-2 2020-05-2 2020-05-3 2020-11-0 2021-10-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 12,600.00 22,582.18 Signed 2020-03-16 e contrôle et la surveillance 0 6 6 0 6 7 eries management des travaux du CIRAEP Mar oantsetra Page 11 MG-MRHP-159186-CS-CDS / Component 3. Strengthenin Recrutement d'une Associati g capacities for engaging in 2020-04-1 2020-04-1 2020-05-1 2020-05-0 2020-08-1 2021-10-3 on/ONG pour la promotion d IDA / 59870 Post Direct Selection Direct 90,000.00 90,332.42 Signed 2020-03-31 alternative fishing practices 6 0 5 1 9 1 e l'approche Groupe d'Eparg and livelihoods activities ne Communautaire (GEC) Zo ne BATAN (3.2.5.1.02.1) MG-MRHP-165352-CS-CDS / Component 3. Strengthenin Recrutement d'une Associati g capacities for engaging in 2020-04-1 2020-04-1 2020-09-1 2020-05-0 2021-01-1 2021-11-0 on / ONG pour la promotion IDA / 59870 Post Direct Selection Direct 90,000.00 80,997.01 Signed 2020-04-01 alternative fishing practices 6 1 8 2 4 1 de l'approche Groupe d'Epar and livelihoods activities gne Communautaire (GEC) Zone MELAKY (3.2.5.1.02.1) MG-MRHP-165351-CS-CDS / Component 3. Strengthenin Recrutement d'une Associati g capacities for engaging in 2020-04-1 2020-04-2 2020-07-2 2020-05-1 2020-10-0 2021-11-1 on / ONG pour la promotion IDA / 59870 Post Direct Selection Direct 90,000.00 75,162.11 Signed 2020-04-10 alternative fishing practices 6 0 4 1 9 0 de l'approche Groupe d'Epar and livelihoods activities gne Communautaire (GEC) Zone BA (3.2.5.1.02.1) MG-MRHP-167265-CS-CDS / Acquisition et maintenance Component 4. Project mana 2020-04-0 2020-04-2 2020-04-1 2020-06-2 2020-05-1 2020-12-2 d'un Logiciel Informatisé de IDA / 59870 Post Direct Selection Direct 50,000.00 40,829.47 Signed 2020-04-10 gement and coordination 7 0 6 4 2 1 Gestion Administrative, Com ptable, Budgétaire et Financ ière pour le Projet SWIOFish 2 MG-MRHP-119242-CS-INDV Component 2. Strengthenin / Elaboration du plan de dév Individual Consul 2019-11-1 2019-12-1 2020-02-1 2020-08-1 IDA / 59870 g capacities for priority fish Post Open 20,000.00 0.00 Canceled 2019-08-01 eloppement des 3 filières aq tant Selection 4 4 2 0 eries management uaculture (algue,holothurie, crabe) MG-MRHP-149438-CS-INDV / Recrutement d'un Consulta nt individuel pour la facilitati Component 2. Strengthenin on des ateliers de sensibilisa Individual Consul 2020-04-1 2020-06-2 2020-05-2 2020-07-0 2020-09-0 2020-07-1 2020-10-0 2020-09-1 IDA / 59870 g capacities for priority fish Post Limited 3,000.00 8,439.82 Signed 2020-06-19 tion régionale au niveau des tant Selection 6 5 7 2 8 6 8 4 eries management 13 régions côtières, relatifs à la communication de la no uvelle loi portant Code de la Pêche et de l'Aquaculture à Madagascar MG-MRHP-119286-CS-INDV- 2 / Recrutement d’un Consul Component 3. Strengthenin tant individuel pour l’appui t g capacities for engaging in Individual Consul 2020-04-2 2020-06-0 2020-07-2 2020-06-2 2020-08-1 2020-07-0 2020-08-2 2021-07-0 TF / A4588 Post Open 85,000.00 26,683.05 Signed 2020-04-24 echnique à la mise en œuvr alternative fishing practices tant Selection 1 6 4 0 4 4 7 4 e de l’électrification hors gril and livelihoods activities le dans le cadre du projet S WIOFish2 MG-MRHP-28756-CS-INDV// Component 3. Strengthenin MG-PM-178 / Élaboration du g capacities for engaging in Individual Consul 2019-11-0 2019-12-1 2020-01-2 2020-03-2 2020-09-2 IDA / 59870 Post Open 300,000.00 0.00 Canceled 2019-08-30 plan stratégique de dévelop alternative fishing practices tant Selection 5 3 7 7 3 pement local (PCD et PLD) and livelihoods activities MG-MRHP-170896-CS-INDV / Recrutement d'un Consulta Component 2. Strengthenin Individual Consul Under Implemen 2020-05-2 2020-07-0 2020-07-2 2020-09-0 2021-09-0 nt pour la mise en place de IDA / D1720 g capacities for priority fish Post Open 30,000.00 0.00 2020-05-04 tant Selection tation 4 8 9 9 9 Base Des Données et la con eries management ception d'un logiciel de colle cte de données_OEPA MG-MRHP-119288BIS-CS-IN DV / Recrutement d'un resp Component 4. Project mana Individual Consul 2019-08-2 2020-03-2 2020-03-2 2020-04-1 2020-04-1 2020-04-2 2020-04-1 2021-04-2 IDA / 59870 Post 15,000.00 13,822.38 Signed 2019-08-19 onsable en communication gement and coordination tant Selection 8 0 0 7 7 0 8 0 2 de l'UGP SWIOfish2 MG-MRHP-170881-CS-INDV Component 2. Strengthenin / Recrutement d’un consulta Individual Consul 2020-05-1 2020-06-2 2020-09-1 2020-07-1 2020-10-0 2020-08-1 2020-10-2 2021-08-1 IDA / 59870 g capacities for priority fish Post Open 15,000.00 13,828.32 Signed 2020-05-04 nt individuel spécialiste de l tant Selection 3 2 6 3 9 7 0 7 eries management a petite pêche au sein de l’U GP du Projet SWIOFish2 MG-MRHP-170887-CS-INDV / Recrutement d’un consulta Component 3. Strengthenin nt individuel spécialiste du d g capacities for engaging in Individual Consul Under Implemen 2020-05-1 2020-07-0 2020-07-2 2020-08-2 2021-08-2 IDA / 59870 Post Open 15,000.00 0.00 2020-05-15 éveloppement des chaines d alternative fishing practices tant Selection tation 4 3 4 8 8 e valeur de la petite pêche a and livelihoods activities u sein de l’UGP du Projet SW IOFish2 MG-MRHP-173507-CS-INDV Component 2. Strengthenin / Recrutement de consultant Individual Consul Under Implemen 2020-05-1 2020-06-2 2020-06-2 2020-07-1 2020-07-2 IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 2020-05-20 Individuel pour la formation tant Selection tation 4 2 9 9 9 eries management en technique d'approche et animation rurale MG-MRHP-173508-CS-INDV Component 2. Strengthenin / Recrutement de consultant Individual Consul Under Implemen 2020-05-1 2020-07-1 2020-08-0 2020-09-0 2020-09-1 IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 2020-05-20 Individuel pour formation en tant Selection tation 4 7 7 5 5 eries management technique de négociation et leadership MG-MRHP-119245 BIS1-CS- CDS / Recrutement d'un BE Component 2. Strengthenin pour le Contrôle et surveilla 2019-07-2 2019-08-1 2019-08-1 2019-11-1 2020-03-1 2021-04-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 56,000.00 51,918.79 Signed 2019-07-24 nce des travaux de construc 4 4 4 2 8 0 eries management tion de l'UGP SWIOFish2 Nan isana, DRRHP Analanjirojo et ASH Morondava MG-MRHP-119245-CS-CDS / Component 2. Strengthenin Contrôle et surveillance des 2019-07-2 2019-10-1 2019-08-1 2020-01-1 2020-07-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 84,000.00 0.00 Canceled 2019-08-01 travaux de constructions po 4 5 4 3 1 eries management ur les six (06) DRRHP et h uit (08) CIRRHP MG-MRHP-172004-CS-INDV / Recrutement d’un consulta Component 2. Strengthenin nt individuel pour l’appui tec Individual Consul 2020-05-2 2020-07-1 2020-08-0 2020-08-0 2020-09-0 2020-09-0 2020-10-0 2023-09-0 IDA / 59870 g capacities for priority fish Post Open 50,000.00 13,512.58 Terminated 2020-05-26 hnique à la mise en œuvre d tant Selection 0 4 7 4 1 8 9 8 eries management es activités d’aquaculture d ans le cadre du projet SWIO Fish2 MG-MRHP-28341 BIS 2-CS-I Component 4. Project mana Individual Consul 2019-02-1 2019-03-1 2019-03-0 2019-03-2 2019-03-0 2019-03-3 2019-03-1 2020-03-2 NDV / Recrutement d'un Co IDA / 59870 Post Open 12,000.00 9,065.16 Terminated 2019-02-18 gement and coordination tant Selection 8 2 6 2 7 0 2 9 mptable remplaçant en 201 9 MG-MRHP-179481-CS-INDV Component 3. Strengthenin / Recrutement d’un formate g capacities for engaging in Individual Consul Under Implemen 2020-06-1 2020-07-3 2020-08-2 2020-09-0 2020-11-3 IDA / 59870 Post Open 50,000.00 0.00 2020-06-18 ur sur la technique de pêche alternative fishing practices tant Selection tation 9 0 0 1 0 moderne and livelihoods activities MG-MRHP-179501-CS-INDV Component 2. Strengthenin / RECRUTEMENT D’UN CONS Individual Consul Under Implemen 2020-07-0 2020-08-0 2020-08-2 2020-09-1 2021-03-1 IDA / 59870 g capacities for priority fish Post Open 10,000.00 0.00 2020-06-19 ULTANT SPÉCIALISTE EN SYS tant Selection tation 7 7 8 1 0 eries management TEME D’INFORMATION GEO GRAPHIQUE (SIG) MG-MRHP-179518-CS-CDS / Recrutement d'une firme po Component 2. Strengthenin 2020-06-2 2020-07-0 2020-07-2 2020-07-2 2020-10-0 2020-08-0 2020-10-2 ur assurer le renforcement d IDA / 59870 g capacities for priority fish Post Direct Selection Direct 10,000.00 23,550.98 Completed 2020-06-22 4 9 2 4 2 8 4 es capacités des agents de l eries management a DGPA à l'IHSM en algocult ure et holothuriculture MG-MRHP-182966-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul Under Implemen 2020-07-2 2020-09-0 2020-09-2 2020-10-3 2023-10-3 IDA / 59870 g capacities for priority fish Post Open 23,400.00 0.00 2020-07-17 nt INDIVIDUEL pour Respons tant Selection tation 2 4 5 0 0 eries management able Local de la composante 2 à Nosy be MG-MRHP-182961-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul 2020-07-2 2020-09-0 2020-10-0 2020-09-2 2020-10-1 2020-10-3 2020-10-2 2023-10-3 IDA / 59870 g capacities for priority fish Post Open 23,400.00 6,449.18 Signed 2020-07-17 nt individuel pour Responsa tant Selection 2 4 7 5 3 0 0 0 eries management ble Local de la composante 2 à Maintirano MG-MRHP-105671-CS-INDV Component 3. Strengthenin / Mise en place, Formation, g capacities for engaging in Individual Consul 2019-03-2 2019-05-1 2019-05-2 2019-07-0 2019-12-2 IDA / 59870 Post Open 60,000.00 0.00 Canceled 2019-03-12 Maintenance et Entretien du alternative fishing practices tant Selection 0 4 8 2 9 système en ligne ou platefor and livelihoods activities me MG-MRHP-119245 BIS2-CS- CDS / Recrutement d'un BE Component 2. Strengthenin 2019-07-2 2020-10-2 2019-08-1 2021-01-2 2021-05-1 2022-06-2 pour le Contrôle et surveilla IDA / 59870 g capacities for priority fish Post Direct Selection Direct 34,500.00 13,383.27 Signed 2020-10-05 4 6 4 4 5 3 nce des travaux de construc eries management tion des CIRRHP Ambanja, A mbilobe, MG-MRHP-119248-CS-INDV Component 2. Strengthenin Individual Consul 2019-11-0 2019-10-1 2019-11-1 2020-01-2 2020-07-2 / Consultance et appui à la IDA / 59870 g capacities for priority fish Post Open 30,600.00 0.00 Canceled 2019-07-01 tant Selection 5 4 3 7 5 composante 2 eries management MG-MRHP-119241-CS-INDV / Assistance juridique pour a Component 2. Strengthenin Individual Consul 2019-08-1 2019-10-3 2019-11-2 2020-01-2 2020-07-2 ppuyer à l’homologation du IDA / 59870 g capacities for priority fish Post Open 10,000.00 0.00 Canceled 2019-08-01 tant Selection 9 0 9 8 6 Dinabe régissant la gestion l eries management ocale des pêcheries au nive au de la Baie d'Antongil MG-MRHP-148888-CS-INDV / Recrutement d’un consulta nt national pour assurer le r Component 2. Strengthenin enforcement de capacité de Individual Consul Pending Implem 2020-09-3 2020-10-0 2020-10-1 2020-10-3 IDA / 59870 g capacities for priority fish Post Limited 1,000.00 0.00 2020-09-24 s agents de l’administration tant Selection entation 0 7 7 1 eries management des pêches et des responsa bles des textes administratif s en technique d'approche e t d’animation rurale (2.1.1.1 .04) MG-MRHP-189680-CS-INDV / Recrutement d'un (e) secré Component 4. Project mana Individual Consul 2020-10-0 2020-10-1 2020-10-2 2023-10-2 IDA / 59870 Post Open 15,000.00 0.00 Canceled 2020-09-15 taire en passation des marc gement and coordination tant Selection 9 9 3 3 hés du projet SWIOFish2 MG-MRHP-160194-CS-INDV / Recrutement d'un assistan Component 4. Project mana Individual Consul 2020-02-2 2020-03-2 2020-04-0 2020-04-0 2023-04-0 IDA / 59870 Post Open 20,000.00 0.00 Canceled 2020-02-27 t en passation des marchés gement and coordination tant Selection 5 2 1 5 5 de l'UGP-SWIOFish2 MG-MRHP-197771-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2020-10-2 2020-11-1 2021-01-3 2020-11-2 2021-02-0 2020-12-0 2021-02-2 2023-09-0 IDA / 59870 Post Open 21,000.00 6,389.81 Signed 2020-10-13 nt individuel Assistant en Pa gement and coordination tant Selection 0 6 0 2 1 3 7 3 ssation des Marchés de l'UG P SWIOFish2 MG-MRHP-197821-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2020-10-1 2020-10-2 2021-05-0 2020-11-0 2021-05-0 2020-11-2 2021-05-1 2023-09-2 IDA / 59870 Post Limited 11,900.00 3,071.04 Signed 2020-10-13 nt individuel Secrétaire de la gement and coordination tant Selection 3 3 5 6 7 2 1 1 Passation des Marchés de l' UGP SWIOFish2 MG-MRHP-197817-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2020-11-1 2020-11-1 2021-03-0 2020-11-2 2021-03-0 2020-12-0 2021-03-0 2023-09-0 IDA / 59870 Post Open 21,000.00 11,362.85 Signed 2020-10-13 nt individuel Gestionnaire de gement and coordination tant Selection 6 6 2 2 4 5 9 5 contrats de l'UGP SWIOFish2 MG-MRHP-203594-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul Under Implemen 2020-11-2 2021-01-0 2021-01-2 2021-02-0 2024-02-0 IDA / 59870 g capacities for priority fish Post Open 23,400.00 0.00 2020-11-20 nt individuel pour Responsa tant Selection tation 1 1 2 5 5 eries management ble Local de la composante 2 à Mananara Nord MG-MRHP-203595-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul Under Implemen 2020-11-2 2021-01-0 2021-01-2 2021-02-0 2024-02-0 IDA / 59870 g capacities for priority fish Post Open 23,400.00 0.00 2020-11-20 nt individuel pour Responsa tant Selection tation 1 1 2 5 5 eries management ble Local de la composante 2 à Maroantsetra MG-MRHP-203596-CS-INDV Component 3. Strengthenin / Recrutement d'un consulta g capacities for engaging in Individual Consul 2020-11-2 2020-11-2 2021-01-1 2020-12-1 2021-01-1 2021-01-2 2021-01-2 2023-09-2 IDA / 59870 Post Limited 23,400.00 6,449.18 Signed 2020-11-20 nt individuel pour Responsa alternative fishing practices tant Selection 1 5 4 6 5 0 1 3 ble Local de la Composante and livelihoods activities 3 à Maintirano Page 12 MG-MRHP-203597-CS-INDV Component 3. Strengthenin / Recrutement des consultan g capacities for engaging in Individual Consul Under Implemen 2020-11-2 2021-01-0 2021-01-2 2021-02-1 2023-09-2 ts individuels pour Responsa IDA / 59870 Post Open 46,800.00 0.00 2020-11-20 alternative fishing practices tant Selection tation 1 1 2 2 3 ble Local de la Composante and livelihoods activities 3 à Maroantsetra et Nosy Be MG-MRHP-28348-CS-INDV/ Component 4. Project mana Individual Consul Pending Implem 2021-08-0 2021-08-2 2021-10-0 2022-04-0 MG-PM-44 / Réalisation du B IDA / 59870 Post Open 8,000.00 0.00 2021-06-03 gement and coordination tant Selection entation 7 8 9 7 ulletin trimestriel SWIOFish2 MG-MRHP-223821-CS-CDS / Recrutement d'un BE pour ET, PGES, C&S de travaux d e construction de la clôture Component 2. Strengthenin 2021-03-1 2021-03-2 2021-03-2 2021-05-3 2021-09-2 2021-07-2 de l’enceinte et mise en pla IDA / 59870 g capacities for priority fish Post Direct Selection Direct 40,000.00 15,938.40 Signed 2021-03-16 4 6 6 0 8 9 ce d’un point d’eau autono eries management me du bureau de la CirAEP Maroantsetra, construction du Hangar et bureau de la brigade CSP Analanjirofo MG-MRHP-223828-CS-INDV / Recrutement d’un troisièm Component 4. Project mana Individual Consul Under Implemen 2021-03-2 2021-04-2 2021-04-2 2021-04-2 2023-09-2 IDA / 59870 Post Open 15,600.00 0.00 2021-03-30 e Comptable pour l’Unité de gement and coordination tant Selection tation 6 0 2 6 9 Gestion du Projet SWIOFish2 MG-MRHP-227230-CS-INDV Component 4. Project mana Individual Consul 2021-04-0 2021-05-2 2021-09-1 2021-06-1 2021-11-1 2021-07-2 2021-11-2 2021-10-1 / Recrutement d'un SIGiste a IDA / 59870 Post Open 15,000.00 15,563.24 Signed 2021-04-07 gement and coordination tant Selection 9 6 0 6 9 1 7 9 u niveau de l'UGP SWIOFish 2 MG-MRHP-229415-CS-CDS / Recrutement d'un responsa Component 4. Project mana Under Implemen 2021-05-2 2021-04-2 2021-05-1 2023-09-2 IDA / 59870 Post Direct Selection 52,600.00 0.00 2021-04-22 ble en passation des marché gement and coordination tation 3 8 5 9 s du projet SWIOFish2 MG-MRHP-229418-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2021-10-2 2021-04-2 2022-03-0 2021-05-0 2022-03-1 2021-05-1 2022-03-2 2023-09-2 IDA / 59870 Post Limited 52,000.00 7,736.16 Signed 2021-04-22 nt individuel Gestionnaire de gement and coordination tant Selection 0 9 8 6 1 5 3 9 contrats de l'UGP SWIOFish2 (2021) MG-MRHP-161616-CS-CDS / Recrutement d'un BE pour l Component 2. Strengthenin 2020-03-2 2020-03-2 2020-05-2 2020-05-2 2021-10-2 e contrôle et surveillance de IDA / 59870 g capacities for priority fish Post Direct Selection Direct 41,500.00 0.00 Canceled 2020-03-12 0 2 6 6 3 s travaux des DRAEP à Andr eries management oy, Anosy et Atsimo Atsinan ana MG-MRHP-161621-CS-CDS / Recrutement d'un BE pour l Component 2. Strengthenin 2020-03-2 2020-03-2 2020-05-2 2020-05-2 2021-10-2 e contrôle et la surveillance IDA / 59870 g capacities for priority fish Post Direct Selection Direct 51,000.00 0.00 Canceled 2020-03-13 0 3 6 7 4 des travaux du DRAEP et CI eries management RAEP à Maintirano, des CIRA EP à Besalampy et à Masoar ivo MG-MRHP-231606-CS-INDV / Recrutement consultant in Component 2. Strengthenin Individual Consul 2021-05-0 2021-07-0 2021-06-2 2021-07-2 2021-10-0 2021-09-0 2021-11-0 2022-09-0 dividuel pour développemen IDA / D1720 g capacities for priority fish Post Open 15,000.00 47,116.80 Signed 2021-05-20 tant Selection 7 8 3 9 8 2 5 2 t de Base des Donnés du Ce eries management ntre de Surveillance Pêche ( CSP) MG-MRHP-236864-CS-INDV / Recrutement d’un Consulta nt individuel pour effectuer Component 2. Strengthenin Individual Consul Under Implemen 2021-08-0 2021-08-1 2021-09-0 2021-10-1 2021-12-1 la mise à jour du Plan d’Acti TF / A4588 g capacities for priority fish Post Open 100,000.00 0.00 2021-06-30 tant Selection tation 6 8 8 3 2 on National de lutte contre l eries management a pêche Illicite Non Déclarée et Non Réglementée (PAN IN N) de Madagascar MG-MRHP-119285-CS-CDS / Component 3. Strengthenin Contrôles et surveillances d g capacities for engaging in 2022-01-2 2022-05-1 2022-11-1 IDA / 59870 Post Direct Selection Direct 60,000.00 0.00 Canceled 2021-11-30 es infrastructures d'électrific alternative fishing practices 9 4 0 ation hors grille dans les co and livelihoods activities mmunautés pilotes MG-MRHP-119281-CS-CDS / Component 2. Strengthenin Contrôle et surveillance des 2021-06-2 2021-10-2 2022-04-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 60,000.00 0.00 Canceled 2021-04-30 constructions de marchés co 9 7 5 eries management uverts aux produits halieutiq ues Component 3. Strengthenin MG-MRHP-252968-CS-INDV g capacities for engaging in Individual Consul 2021-10-1 2021-11-3 2021-10-2 2021-12-2 2021-11-0 2022-01-2 2021-11-1 2023-01-2 / Recrutement d’un Assistan IDA / 59870 Post Open 15,000.00 6,796.71 Signed 2021-10-11 alternative fishing practices tant Selection 2 0 2 1 3 5 7 5 t Technique Foncier and livelihoods activities MG-MRHP-256410-CS-INDV Component 4. Project mana Individual Consul 2021-12-2 2021-11-0 2022-02-2 2021-11-1 2022-03-0 2021-11-2 2022-03-0 2023-09-2 / Recrutement d'un comptab IDA / 59870 Post Open 24,000.00 8,042.13 Signed 2021-10-18 gement and coordination tant Selection 0 8 5 5 1 4 8 9 le 2021 (Remplacement co mptable 2) MG-MRHP-285250-CS-CDS / Component 2. Strengthenin Analyse des problématiques Under Implemen 2022-04-1 2022-04-1 2022-06-0 2022-06-1 2022-12-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 20,000.00 0.00 2022-04-05 liées à l’utilisation des senn tation 5 5 2 9 6 eries management es de plage dans la baie d’A ntongil MG-MRHP-289654-CS-INDV / Responsable Local de la Co Component 3. Strengthenin mposante 3 (RLC3) « Appui g capacities for engaging in Individual Consul Pending Implem 2022-05-3 2022-06-2 2022-07-1 2025-02-1 à l’adhésion des populations IDA / 59870 Post Open 22,000.00 0.00 2022-04-18 alternative fishing practices tant Selection entation 0 0 1 8 cibles à la gestion durable d and livelihoods activities es pêcheries cibles/Promotio n des activités alternatives » dans les Districts de Maro antsetra MG-MRHP-252785-CS-INDV / Recrutement d'un Respons Component 4. Project mana Individual Consul 2021-09-1 2021-10-1 2021-10-2 2021-11-0 2023-09-3 IDA / 59870 Post Open 32,400.00 0.00 Canceled 2021-09-23 able Administratif et Financi gement and coordination tant Selection 5 3 3 6 0 er pour le Projet SWIOFish2 ( 2021) MG-MRHP-119282-CS-CDS / Contrôle et surveillance des constructions de hangars av Component 3. Strengthenin ec des materiaux locaux po g capacities for engaging in 2022-01-1 2022-05-1 2022-11-0 ur entretenir les moteurs, le IDA / 59870 Post Direct Selection Direct 48,000.00 0.00 Canceled 2021-11-12 alternative fishing practices 1 1 7 s embarcations et des engin and livelihoods activities s de pêche autorisés et d'un e base de réunion, sensibilis ation et de structuration des utilisateurs petites infrastru MG-MRHP-119283-CS-CDS / Component 3. Strengthenin Contrôles et surveillances d g capacities for engaging in 2022-01-1 2022-04-2 2022-10-2 IDA / 59870 Post Direct Selection Direct 120,000.00 0.00 Canceled 2021-11-12 es constructions d'infrastruc alternative fishing practices 1 6 3 tures communautaires /com and livelihoods activities munales MG-MRHP-119280-CS-CDS / Component 3. Strengthenin Contrôle et surveillance des g capacities for engaging in 2022-01-2 2022-04-2 2022-10-2 IDA / 59870 Post Direct Selection Direct 70,000.00 0.00 Canceled 2021-11-12 constructions de petites déb alternative fishing practices 6 6 3 arcadères type ponton and livelihoods activities MG-MRHP-28325-CS-INDV// Component 3. Strengthenin MG-PM-29 / Élaboration de p g capacities for engaging in Individual Consul 2022-11-1 2022-12-1 2023-02-1 2023-08-1 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2022-09-02 lan de formation des cadres alternative fishing practices tant Selection 7 7 5 4 et élus au niveau local and livelihoods activities MG-MRHP-189660-CS-INDV / Recrutement d'un consulta Component 2. Strengthenin nt individuel pour le renforc Individual Consul Pending Implem 2022-08-0 2022-08-2 2022-09-1 2022-09-2 IDA / 59870 g capacities for priority fish Post Open 4,000.00 0.00 2022-07-01 ement de capacités de l'équ tant Selection entation 6 7 0 2 eries management ipe du service personnel du secteur pêche et aquacultur e en gestion des ressources humaines MG-MRHP-190572-CS-INDV / Recrutement d'un consulta nt individuel pour le renforc Component 2. Strengthenin ement de capacités des age Individual Consul Pending Implem 2022-10-0 2022-10-2 2022-11-1 2022-12-0 IDA / 59870 g capacities for priority fish Post Open 4,000.00 0.00 2022-09-01 nts de l'administration en dé tant Selection entation 7 8 1 8 eries management veloppement d'application web sous HTML, CSS et Java Script et pratique de dévelo ppement en WEBDEV MG-MRHP-292939-CS-INDV / Assistant Technique 2 pour Component 4. Project mana Individual Consul Under Implemen 2022-06-1 2022-06-0 2022-06-1 2022-06-1 2025-06-1 les constructions et réhabilit IDA / 59870 Post Open 25,000.00 0.00 2022-05-09 gement and coordination tant Selection tation 0 2 2 6 5 ations d'infrastructures de p êche, communautaires et ad ministratives MG-MRHP-280897-CS-CDS / Mise à jour des études techn iques relatives à la construct ion du bureau administratif Component 2. Strengthenin Under Implemen 2022-06-0 2022-05-1 2022-06-0 2022-07-2 2023-01-1 de l’UGP SWIOFish2 Nanisan IDA / 59870 g capacities for priority fish Post Direct Selection Direct 26,000.00 0.00 2022-05-06 tation 2 6 8 0 6 a et Contrôle et surveillance eries management de la construction du nouve au bureau logement et de la réhabilitation du bureau log ement existant Farafangana MG-MRHP-297266-CS-INDV / Recrutement d'un consulta Component 2. Strengthenin nt pour la création d'un site Individual Consul 2022-07-1 2022-08-0 2022-09-1 2022-08-2 2022-10-0 2022-09-0 2022-12-0 IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 Signed 2022-06-10 web de design et de base de tant Selection 3 5 2 6 7 9 8 eries management données pour la gestion des autorisations et des licences des pêches MG-MRHP-298184-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2022-06-2 2022-08-0 2022-08-2 2022-09-2 2023-09-2 / Recrutement d'un comptab IDA / 59870 Post Open 24,000.00 0.00 2022-06-16 gement and coordination tant Selection tation 4 4 5 9 9 le 3 remplaçant MG-MRHP-298211-CS-CDS / Recrutement d’une organisa tion non-gouvernementale p Component 3. Strengthenin our la promotion des groupe g capacities for engaging in Under Implemen 2022-06-1 2022-06-2 2022-07-1 2023-07-1 s d’épargne communautaire IDA / 59870 Post Direct Selection Direct 90,000.00 0.00 2022-06-17 alternative fishing practices tation 0 7 8 8 (GEC) au niveau des district and livelihoods activities s de Farafangana et Vangain drano - regions Atsimo Atsin anana et des districts d’Amb ovombe, Tsihombe et Beloh a - région And MG-MRHP-296823-CS-INDV / Recrutement d'un Assista Component 4. Project mana Individual Consul 2022-08-1 2023-02-1 IDA / 59870 Post Open 25,000.00 0.00 Canceled nt Technique national au Mi gement and coordination tant Selection 7 3 nistère de la Pêche et de l'E conomie Bleue (MPEB) MG-MRHP-296823-CS-INDV_ 2 / Recrutement d'un Assist Component 4. Project mana Individual Consul 2022-06-2 2022-08-1 2022-07-1 2022-09-0 2022-07-1 2022-10-1 2022-08-0 2023-04-1 IDA / 59870 Post Open 25,000.00 7,215.66 Signed 2022-06-30 ant Technique national au M gement and coordination tant Selection 9 8 3 8 9 3 2 1 inistère de la Pêche et de l'E conomie Bleue (MPEB) MG-MRHP-303933-CS-CDS / Recrutement d'un formateur Component 3. Strengthenin relatif au renforcement de c g capacities for engaging in Direct - Internatio Under Implemen 2022-07-2 2022-08-0 2022-10-0 2023-08-0 IDA / 59870 Post Direct Selection 500,000.00 0.00 2022-07-22 apacité sur les techniques d alternative fishing practices nal tation 1 1 5 1 e fumage des produits halie and livelihoods activities utiques et construction de fu moirs FTT MG-MRHP-231604-CS-INDV / Recrutement d’un Consulta Component 2. Strengthenin nt Individuel pour effectuer Individual Consul 2022-07-2 2022-09-0 2022-10-1 2022-09-3 2022-11-1 2022-11-0 2023-09-2 TF / A4588 g capacities for priority fish Post Open - National 32,500.00 0.00 Signed 2022-07-22 un Audit des activités de Sur tant Selection 2 9 8 0 0 4 9 eries management veillance, réalisées par le Ce ntre de Surveillance des Pêc hes (CSP) de Madagascar. Page 13 MG-MRHP-304398-CS-CDS / Recrutement d'un consultan Component 2. Strengthenin Under Implemen 2022-07-2 2022-08-0 2022-07-2 2022-10-0 2023-09-2 t pour la modification tablea TF / A4588 g capacities for priority fish Post Direct Selection Direct - National 20,000.00 0.00 2022-07-22 tation 1 1 5 5 9 u de bord et création de mo eries management dules dans le SIP et OPENAR TFISH MG-MRHP-308538-CS-CDS / Renouvellement des contrat Component 3. Strengthenin s de prestation des organisa g capacities for engaging in 2022-09-2 2022-08-2 2022-09-2 2022-11-0 2023-05-0 tions non-gouvernementales IDA / 59870 Post Direct Selection Direct - National 180,000.00 0.00 Signed 2022-08-19 alternative fishing practices 7 9 9 2 1 pour la promotion des group and livelihoods activities es d’épargne communautair e (GEC) au niveau des ZUP MELAKY et BAIE d’ANTONGIL MG-MRHP-308722-CS-CDS / Renouvellement des contrat Component 3. Strengthenin s de prestation des organisa g capacities for engaging in Under Implemen 2022-09-2 2022-08-2 2022-09-2 2022-10-3 2023-04-2 IDA / 59870 Post Direct Selection Direct - National 90,000.00 0.00 2022-08-17 tions non-gouvernementales alternative fishing practices tation 7 7 9 1 9 pour la promotion des group and livelihoods activities es d’épargne communautair e (GEC) au niveau des ZUP BATAN MG-MRHP-320114-CS-INDV Component 3. Strengthenin / Recrutement d'un Assistan g capacities for engaging in Individual Consul 2022-10-2 2022-11-0 2023-01-1 2022-11-1 2023-01-1 2022-12-1 2023-08-1 IDA / 59870 Post Open - National 20,000.00 0.00 Signed 2022-10-14 t spécialiste sauvegarde env alternative fishing practices tant Selection 4 9 1 0 3 4 6 ironnemental et social and livelihoods activities MG-MRHP-334021-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2023-01-3 2023-02-1 2023-02-2 2023-03-1 2023-09-2 IDA / 59870 Post Open - National 16,000.00 0.00 2023-01-10 / Recrutement d'un 4ème co gement and coordination tant Selection tation 0 2 6 2 9 mptable MG-MRHP-336492-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2023-01-3 2023-02-2 2023-03-1 2023-04-0 2023-09-2 / Recrutement d'un Chef Co IDA / 59870 Post Open - National 8,000.00 0.00 2023-01-30 gement and coordination tant Selection tation 0 5 1 1 9 mptable (CC) au sein de l'U GP 2023 MG-MRHP-336490-CS-CDS / Recrutement d'un Responsa Component 4. Project mana 2023-02-1 2023-02-2 2023-02-2 2023-03-0 2023-10-1 IDA / 59870 Post Direct Selection Direct - National 15,000.00 0.00 Signed 2023-02-15 ble Administratif et Financie gement and coordination 7 0 4 3 5 r au sein de l'UGP 2023 MG-MRHP-299084-CS-INDV / Recrutement d'un Assista Component 4. Project mana Individual Consul 2022-06-2 2022-08-1 2022-09-0 2022-10-1 2023-04-1 nt Technique international IDA / 59870 Post Open 35,000.00 0.00 Canceled 2022-06-30 gement and coordination tant Selection 9 8 8 3 1 au Ministère de la Pêche et de l'Economie Bleue (MPEB) MG-MRHP-5189-CS-INDV / E Component 2. Strengthenin tude sur l'adaptation des mi Individual Consul 2017-04-0 2017-04-2 2017-05-3 2017-11-2 IDA / Q9790 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2017-02-15 ssions et attributions du MR tant Selection 5 6 1 7 eries management HP par rapport aux défis du développement rural Page 14 LESOTHO COMPETITIVENESS AND FINANCIAL INCLUSION (CAFI) PROJECT Project Procurement Strategy Development (PPSD) (Short form of PPSD) Implementing Agency: Ministry of Trade & Industry MARCH 2022 1|Page Common Abbreviations and Defined Terms This Section explains the common terms and abbreviations used in this Document. Defined terms are written using capital letters. Abbreviation / Full terminology / definition term ASYCUDA A computerised customs management system which covers most foreign Trade procedures Bank IBRD and/or IDA (whether acting on its account or in its capacity as administrator of trust funds provided by other donors). Borrower A borrower or recipient of Investment Project Financing (IPF) and any other entity involved in the implementation of a project financed by IPF, in this case, the GoL. Complaint A procurement-related complaint as described in Paragraphs 3.26 to 3.31 and Annex III, Procurement- related Complaints of the Procurement Regulations. ESRI Company that provides GIS systems in Africa and around the globe (Environmental Systems Research Institute) EXPERIAN Credit Scoring system and Credit Infrastructure system Goods A category of procurement that includes commodities, raw material, machinery, equipment, vehicles, Plant, and related services such as transportation, insurance, installation, commissioning, training, and initial maintenance, G2B Government to Business Initial Selection The shortlisting process is used prior to inviting (IS) requests for Proposals in the procurement of Goods, Works, or Non-consulting Services. Investment The Bank’s financing of investment Projects that aim Project to promote poverty reduction and sustainable Financing (IPF) development. IPF supports Projects with defined development objectives, activities, and results, and disburses the proceeds of Bank financing against specific eligible expenditures. LERIMA Lesotho Electronic Registry Interest of Moveable Assets Non--consulting Services, which are not Consulting Services. Non- Services: consulting Services are normally bid and contracted on the basis of performance of measurable outputs, and for which performance standards can be clearly identified and consistently applied. Examples include drilling, aerial photography, satellite imagery, mapping, and similar operations. 2|Page Abbreviation / Full terminology / definition term SWOT (Strengths, Weaknesses, Opportunity and Threats) is an analysis tool for supporting assessment of each of these factors. PARADIGM A company that deals with Moveable Asset Registry Prequalification The shortlisting process can be, used prior to inviting requests for Bids in the procurement of Goods, Works or Non-Consulting Services. Procurement Procurement approach is the overall design of “fit Approach for purpose” procurement to award contracts that deliver the Project Development Objectives and Value for Money. This includes Procurement Arrangements, procurement risk management, contract strategy, market engagement, requirements drafting and contract management (where appropriate). Procurement Procurement arrangements are the combination of Arrangements Selection Methods and Market Approaches. Procurement The Borrower’s Procurement Plan for IPF Projects, as Plan referred to in Paragraphs 4.4 and 4.5 of the Procurement Regulations, and incorporated by reference in the Legal Agreement. Procurement The process that starts with the identification of a Process need and continues through planning, preparation of specifications/ requirements, budget considerations, selection, contract award, and contract management. It ends on the last day of the warranty period. Procurement The “World Bank Procurement Regulations for IPF Regulations Borrowers”. Project A Project-level strategy document, prepared by the Procurement Borrower, that describes how procurement in IPF Strategy for operations will support the development objectives Development of the Project and deliver Value for Money (VFM). (PPSD) UNCTAD United Nations Conference on Trade and Development 3|Page Table of Contents CHAPTER 1 ...........................................................................................................5 1.0 PROJECT OVERVIEW ...............................................................................5 1.1 Project Description ................................................................................6 1.2 Project Development Objectives .........................................................8 1.3 Results Indicators ..................................................................................8 1.4 High Level Statement of Requirement ...............................................9 CHAPTER 2 ...........................................................................................................9 2.0 OVERVIEW OF COUNTRY, BORROWER AND MARKET PLACE .9 2.1 Operational Context ..............................................................................9 2.2 Assessment of Borrower Capability and Project Implementation Unit (PIU) ........................................................................................................15 2.3 Project Procurement Structure .........................................................19 2.4 Market Analysis ....................................................................................20 CHAPTER 3 .........................................................................................................23 3.0 PROJECT PROCUREMENT RISK ANALYSIS .........................................23 CHAPTER 4 .........................................................................................................29 4.0 STAKEHOLDER ANALYSIS ...................................................................29 CHAPTER 5 .........................................................................................................31 5.0 PROCUREMENT OBJECTIVES ...............................................................31 CHAPTER 6 .........................................................................................................32 6.0 PROCUREMENT APPROACH OPTIONS AND RECOMMENDATIONS .32 CHAPTER 7 .........................................................................................................39 7.0 SUMMARY OF PPSD TO SUPPORT THE PREPARATION OF THE PAD BY THE BANK ..................................................................................................39 CHAPTER 8 .........................................................................................................40 8.0 PROCUREMENT PLAN FOR THE FIRST 18 MONTHS .........................40 4|Page CHAPTER 1 1.0 PROJECT OVERVIEW Competitiveness and Financial Inclusion (CAFI), aims to provide more opportunities for women in the private sector through the following interventions: (i) focusing on women owned MSMEs for rapid disbursements during shocks. Women-owned MSMEs are particularly vulnerable to climatic shocks and require targeted support. Research in Lesotho has shown that shocks disproportionately increase the work burden of women, who, in addition to being more likely to be self-employed or employed in the informal sector, are also tasked with walking long distances to collect water for their families in droughts, growing/providing food, covering educational costs/needs, and generally sustaining the family. In rural areas, men are more likely to leave their villages in search of alternate income sources, thereby giving women the full burden of family caretaking. Thus, when climatic shocks occur, a loss of income for the self-employed women can have large and catastrophic effects on families and communities, emphasizing the need for rapid support to women-owned MSMEs; (ii) focusing on women-owned start-ups and women-owned MSMEs to assist them in launching businesses, adopting new digital technologies, and improving managerial practices. This supports gender transformation within the MSME space. The proposed project has adopted a selective approach by targeting interventions that link closely to business expansion and resilience and job creation, specifically those related to supporting entrepreneurship, MSMEs, and high potential value chains. The proposed interventions are targeted at increasing financial inclusion and resilience as well as strengthening the support for MSMEs and entrepreneurship along the high potential value chains. Under increasing financial inclusion and resilience, the proposed interventions focus on strengthening the delivery of G2B services, increasing access to finance for MSMEs with a focus on ensuring the 5|Page inclusion of women- owned MSMEs and enhancing the resilience of the business sector from climate and other shocks. Support for MSMEs and entrepreneurship is focused on enhancing the scope and quality of business support services, access to early-stage finance and improving the overall competitiveness and climate resilience of horticulture and export manufacturing value chains. Based on the experience of the PSCED and PSCEDII projects, institutional, legal, and regulatory reforms pertaining to access to finance, investment policy and business environment reforms, while critical for overall competitiveness, have proven challenging and unnecessarily prolonged. These reforms will be supported through a parallel technical advisory support program. The project interventions proposed therefore target market and coordination failures through direct support to entrepreneurs and firms while leveraging private sector service delivery capacity to augment limited public sector capacity. Although the tourism value chain has not been explicitly targeted, entrepreneurs and existing MSMEs in the sector will be able to fully benefit from the project interventions. Country: Kingdom of Lesotho Full Project Competitiveness and Financial Inclusion Project Name: Total Finance 55,000,000. ($): Project ID P175783 Number: 1.1 Project Description The purpose of this project is to increase access to business support services and financial products targeted at MSMEs and entrepreneurs, especially women and youth. The project has three components that will support the Government’s efforts to expand the private sector in Lesotho. 6|Page • Component 1 will enhance financial inclusion by strengthening the delivery of efficient and reliable government-to-business (G2B) digital services to facilitate the establishment and operation of new businesses and reduce the time and cost of regulatory compliance which in turn will enhance access to finance and the competitiveness of MSMEs. It will also provide support for firms to be more resilient to shocks from climate, pandemics, and other natural disasters. The component will include activities that support (i) optimizing the outcomes of investments in G2B digital systems and processes made under the PSCEDII project, to strengthen inter-operability, efficiency, and impactful service delivery for businesses, particularly those receiving support under Component 2, (ii) improving financial access through upgrading the security and reliability of credit infrastructure and expanding access to digital financial services, and (iii) instruments to expand financial resilience for businesses to cope with disasters and other shocks to the economy. These instruments will be particularly beneficial to the private sector. The component will finance technical assistance, goods, training and capacity building programs, and recurrent expenditures, including operating costs. • Component 2 aims to strengthen the nascent entrepreneurial ecosystem and access to early-stage finance for startups and youth owned businesses, support the digitization of MSMEs, and facilitate private investment in high-potential value-chains including encourage upgrading of skills and adoption of sustainable production practices by businesses to enhance productivity and green growth. The component will include activities that support (i) establishing an Entrepreneurship Hub and Seed Financing Facility to increase the quality and scope of integrated startup business support services and increase access to early-stage financing, (ii) scaling the current Lesotho Enterprise Assistance Program (LEAP) focusing on supporting MSMEs to adopt digital technologies that allow them to transact in the digital economy and upgrade their capabilities, and (iii) facilitating investment into productive value chains that are linked to 7|Page local MSMEs. The component will finance technical assistance, goods, training, recurring expenditures including operating costs, grants, and investments in a “seed financing facility.” • Component 3 will provide support for the management and implementation of project-associated activities. Activities to be financed include salaries of project management unit (PMU) staff/consultants in areas of project management, project coordination, fiduciary specialists (e.g., procurement, financial management), monitoring and evaluation (M&E) specialist, a dedicated environment, and social safeguards (E&S) specialist, project communication, and citizen engagement. This component will also cover modest office equipment and independent audits and learning/training for the PMU and beneficiary agencies, through the official closing date of the project. It is expected that all consultant terms of reference (TORs) will clearly stipulate knowledge transfer and hands on training to ministry staff. Special attention will be devoted to promoting equal participation of women in all decision- making bodies under the project and contributing to tackling barriers in recruitment, retention, and promotion. 1.2 Project Development Objectives The project development objective (PDO) is to increase access to business support services and financial products targeted at MSMEs and entrepreneurs, especially women and youth. The proposed project supports results in two areas: (i) Improving financial inclusion and resilience through improvements in government to business services, government supported financial products that increase MSME creation, growth, and resilience to climatic and other shocks; and 8|Page (ii) Direct support for entrepreneurship and MSMEs to increase start-up creation and growth and the capabilities of MSMEs to grow and participate in the value chains of high potential export industries. 1.3 Results Indicators The project’s achievement of the PDO will be measured via the following key results indicators: 1. Number of enterprises benefitting from private sector initiatives of the program (Of which are women-owned, of which are youth-owned); 2. Value of financing (seed funding, grants, partial credit guarantee, MSME resilience funds) accessed by enterprises through the program (Of which are women-owned); 3. Percentage of enterprises supported by the program with increased revenue (Of which are women-owned, of which are youth-owned); and 4. Percentage of enterprises supported by the program with increased employment (Of which are women-owned, of which are youth-owned. 9|Page There are also indicative intermediate indicators which will be used to measure the performance of the project, and these are: • Firms benefiting from private sector initiatives (CRI, Number) (Of which are women-owned, and of which are youth-owned). • Percent change in the number of enterprises accessing supported G2B systems; • Number of key G2B systems upgraded with the support from the program; • Percentage of women-owned enterprises recorded as being creditworthy in the credit bureau; • Number of additional enterprises covered by the partial credit guarantee (PCG) scheme; • Number of MSMEs registered for coverage in MSME Resilience Fund database; • Number of startups and innovative SMEs supported through entrepreneurship hub support programs; • Number of startups and innovative SMEs supported through entrepreneurship hub support programs of which are women-owned; • Number of enterprises accessing early-stage finance; • Number of entrepreneurship hub and LEAP program supported enterprises that adopted new digital technologies; • Number of LEAP fund supported enterprises with 25% or greater increase in revenues one year after grant support; and • Number of supported enterprises in targeted value chains with increased value of exports. 1.4 High Level Statement of Requirement The implementation of the Competitiveness and Financial Inclusion Project requires procurement of consulting and non-consulting services, goods, and works under the project components. Consulting services will be needed to provide capacity building and technical advisory services as well as 10 | P a g e management assistance to both PMU and beneficiary agencies. Procurement of consulting services will be needed to enhance G2B digital services to more effectively serve MSMEs, access to financial services, strengthening the resilience of MSMEs to Climatic Disasters and shock scaling-up support for Entrepreneurship and MSME’s and expanding SME participation in high potential value chains. Procurement of works will be needed to support the refurbishment of Mahobong Incubation Hub as well as partitioning of PMU office. Procurement of goods will be needed to provide ICT equipment to support implementation of Component 1 system upgrades including the business registration and licensing system at OBFC, the LRA customs system, the MCC construction permitting system to mention a few. Table 1 below provides a summary of the estimated costs of procurement package per component, works, good and consulting services included. 11 | P a g e TABLE 1: Proposed Procurement Contract Summary PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE Sub-Component 1.1 - Enhancing Government to Business Digital Services UNCTAD is uniquely and exceptionally qualified to upgrade business registration and licensing system at OBFC as it was originally developed by them. It is also the case that the tasks represent a natural continuation of previous work carried out by a consultant, where continuity in the technical approach, experience Upgrade of the acquired, and continued professional liability of the same business Consultant may make continuation with the initial registration and Consultant preferable to a new competition. The licensing system 880 Direct Selection performance of UNCTAD has been satisfactory in the 1.1.1 at OBFC 000.00 (UNCTAD) previous assignment(s); UNCTAD is uniquely and exceptionally qualified to upgrade LRA customs system as it was originally designed and developed by them. Upgrade of the It is also the case that the tasks represent a natural LRA customs continuation of previous work carried out by a consultant, system, based on Direct Selection where continuity in the technical approach, experience UNCTAD`s (UNCTAD)ASYC acquired, and continued professional liability of the same ASYCUDA World 1 000 UDA World Consultant may make continuation with the initial 1.1.2 System 000.00 System Consultant preferable to a new competition. The 1|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD performance of UNCTAD has been satisfactory in the previous assignment(s); Only ESRI is qualified and has experience of exceptional worth for the upgrade of the LAA land registry system as they designed and developed the system. It is also the case that the system is proprietary where continuity in the technical approach, experience acquired, and continued professional liability of the same Consultant may make direct selection of the system developer Upgrade of the Consultant preferable to a new competition. The LAA land registry 1 000 Direct Selection performance of ESRI has been satisfactory in the previous 1.1.3 system 000.00 (ESRI) assignment(s); Design and Appropriate method for medium and high complexity development of assignment. Competitive approach is required to achieve the G2B quality and value for money interoperability 1 600 QCBS - 1.1.4 framework 000.00 International Design and The method is appropriate as this is a large firm consultant development of a assignment with cost above $ 300 000.00. Competitive G2B payment 1 500 QCBS - approach is required to achieve quality and value for money 1.1.5 gateway 000.00 International 5 980 000.00 Sub-Component 1.2 - Improving Access to Financial Services Upgrade of the Only EXPERIAN is qualified and has experience of credit exceptional worth for the upgrade of the credit infrastructure infrastructure system as they designed and developed the system. The system that 200 Direct Selection task represents a natural continuation of previous work 1.2.1 facilitates access 000.00 (EXPERIAN) carried out by a consultant, where continuity in the technical 2|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD to business approach, experience acquired, and continued professional financing liability of the same consultant may make continuation with the initial consultant preferable to a new competition The performance of EXPERIAN has been satisfactory in the previous assignments Only EXPERIAN is qualified and has experience of exceptional worth for the development of the credit scoring system as they designed the system. The task represents a natural continuation of previous work carried out by a consultant, where continuity in the technical approach, Development of experience acquired, and continued professional liability of credit scoring the same consultant may make continuation with the initial system to consultant preferable to a new competition The performance enhance the of EXPERIAN has been satisfactory in the previous utility of credit 600 Direct Selection assignments 1.2.2 reporting 000.00 (EXPERIAN) Only Paradigm is qualified and has experience of exceptional worth for the upgrade of the LERIMA movable asset registry as they designed and developed the system. The task represents a natural continuation of previous work carried out by a consultant, where continuity in the technical approach, experience acquired, and continued professional liability of the same consultant may make continuation with the initial consultant preferable to a new competition. The Upgrade of performance of LERIMA has been satisfactory in the previous LERIMA movable 200 Direct Selection assignments 1.2.3 asset registry 000.00 (Paradigm) Development of Appropriate method for medium and high complexity New financial 500 QCBS - assignment. Competitive approach is required to achieve 1.2.4 products to 000.00 International quality and value for money 3|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD promote market innovation Capacity building This is a small assignment of which preparing and evaluating of financial competitive proposals is not justified institutions and MSME`s to utilise asset-based 1.2.5 lending 50 000.00 CQS- National TA to Postbank This is a small assignment of which preparing and evaluating for development competitive proposals is not justified of business case for agricultural value chain finance, including market assessment and financing 150 CQS- 1.2.6 methodology 000.00 International Design and This is a small assignment of which preparing and evaluating implementation competitive proposals is not justified of a management information system (MIS) to support value- 200 CQS- 1.2.7 chain financing 000.00 International Review and This is a low value assignment with less than six months improve governance, institutional and 1.2.8 operational 50 000.00 IC- National 4|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD features of the L- PCG Develop a This is a small assignment of which preparing and evaluating business case competitive proposals is not justified and financial model for portfolio 150 CQS- 1.2.9 guarantees 000.00 International Design and Appropriate method for large firm consultant assignment implement the over US$ 300 000.00. Competitive approach is required to portfolio achieve quality and value for money guarantee scheme including development of supporting documentation 2,000 QCBS- 1.2.10 and systems 000.00 International 100 This is a small assignment of which preparing and evaluating 1.2.11 Capacity building 000.00 CQS-National competitive proposals is not justified 2 800 000.00 Sub-Component 1.3 – Strengthening the Resilience of MSMEs to Climatic Shocks TA on disaster Appropriate method for such high value and complex risk financing assignment. Competitive approach is required to achieve including drafting quality and value for money of National Disaster Risk Finance Policy for 750 QCBS- 1.3.1 MoF 000.00 International 5|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD Design and Appropriate method for less complex assignments. This is a development a small assignment of which preparing and evaluating database for competitive proposals is not justified informal MSMEs and integrate the database into the existing business 300 QCBS- 1.3.2 registry 000.00 International TA on design and Appropriate method for less complex assignments. This is a procurement of small assignment of which preparing and evaluating sovereign competitive proposals is not justified insurance backstop and co- financing of insurance 150 CQS- 1.3.3 premiums 000.00 International Draft regulations This is a low value assignment with less than six months to govern the duration operational activities of the existing MoF Contingency 1.3.4 Fund 75 000.00 IC - National 1,275, 000.00 COMPONENT 2: SCALING SUPPORT FOR ENTREPRENEURSHIP AND MSMES Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility 6|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD Procure a private Appropriate method for high value and complex assignment. operator to Competitive approach is required to achieve quality and support the value for money establishment of a sustainable Entrepreneurship Hub within the Tourism Information Craft 500 QCBS- 2.1.1 Centre 000.00 International Design and Appropriate method for less complex assignments. development of Preparing and evaluating competitive proposals is not an incubation 150 CQS- justified 2.1.2 support program 000.00 International Facilitate the This is a low value assignment with less than six months integration of the duration Lesotho Start-up Community within a wider regional Entrepreneurship 2.1.3 ecosystem 50 000.00 IC- National Procure a private Appropriate method for less complex assignments. operator to Preparing and evaluating competitive proposals is not establish and justified manage a seed financing facility and an associated acceleration 250 CQS- 2.1.4 program 000.00 International 7|Page PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES JUSTIFICATIONS FOR THE PROPOSED SELECTION DESCRIPTION ESTIMAT PROPOSED METHOD COMPON OF THE ED COST SELECTION ENT ASSIGNMENT ($) METHOD 950 000.00 Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program Procure private Appropriate method for less complex assignments. sector service Preparing and evaluating competitive proposals is not providers to justified augment the delivery capacity 300 2.2.1 of LEAP PMU 000.00 QCBS-National Sub-Component 2.3 - Expanding SME Participation in High Potential Value Chains TA to set up a QCBS Appropriate method for high value and complex assignment. Horticulture 350 International Competitive approach is required to achieve quality and 2.3.1 Incubation Hub 000.00 Selection value for money PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE Sub-Component 1.1 - Enhancing Government to Business Digital Services 8|Page PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD Efficient method for procuring limited quantities of readily ICT equipment for upgrade of the business Request For available off-the- 1.1.1 registration and licensing system at OBFC 70 000.00 Quotations shelf goods Medium value and local availability. The user will be able to specify detailed requirements to which bidders may respond in offering bids. ICT equipment for Upgrade of the LRA customs Value for money system, based on UNCTAD`s ASYCUDA World National will also be 1.1.2 System 150 000.00 Competitive Bidding achieved. Efficient method for procuring limited quantities ICT equipment for Upgrade of the LAA land registry of readily system and the MCC construction permitting Request For available off-the- 1.1.3 system 100 000.00 Quotations shelf goods Medium value and local availability. National The user will be 1.1.4 ICT equipment for G2B interoperability 200 000.00 Competitive Bidding able to specify 9|Page PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD detailed requirements to which bidders may respond in offering bids. Value for money will also be achieved. 520 000.00 Sub-Component 1.2 - Improving Access to Financial Services Efficient method for procuring limited quantities ICT equipment for upgrade of the credit of readily infrastructure system that facilitates access to Request for available off-the- 1.2.1 business financing 100 000.00 Quotations shelf goods Efficient method for procuring limited quantities ICT equipment for upgrade of LERIMA movable of readily assets and integration of data from motor vehicle Request for available off-the- 1.2.3 and company registries 100 000.00 Quotations shelf goods Efficient method for procuring limited quantities of readily ICT equipment to support implementation of MIS Request for available off-the- 1.2.4 for Lesotho Post bank value-chain financing 100 000.00 Quotations shelf goods 10 | P a g e PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD Efficient method for procuring limited quantities of readily Request for available off-the- 1.2.5 ICT equipment to support L-PCG 100 000.00 Quotations shelf goods 400 000.00 Sub-Component 1.3 – Strengthening the Resilience of MSMEs to Climatic Shocks COMPONENT 2: SCALING SUPPORT FOR ENTREPRENEURSHIP AND MSMES Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility Medium value and local availability. The user will be able to specify detailed requirements to which bidders may respond in offering bids. Value for money Procure equipment and furniture for the National will also be 2.1.1 Entrepreneurship Hub 300 000.00 Competitive Bidding achieved. Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program Efficient method for procuring Request for limited quantities Procure ICT equipment and furniture 70 000.00 Quotations of readily 11 | P a g e PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD available off-the- shelf goods Sub-Component 2.3 - Expanding SME Participation in High Potential Value Chains Medium value and local availability. The user will be able to specify detailed requirements to which bidders may respond in offering bids. Value for money Procure ICT equipment and furniture for National will also be 2.3.1 Horticulture Incubation Hub 300 000.00 Competitive Bidding achieved. COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT Efficient method for procuring limited quantities of readily Request for available off-the- 3.1.1 ICT equipment and furniture for PMU 100 000.00 Quotations shelf goods Medium value and local availability. The user will be National able to specify 3.1.2 Procure vehicles for PMU and Vehicle 150 000.00 Competitive Bidding detailed 12 | P a g e PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD requirements to which bidders may respond in offering bids. Value for money will also be achieved. PROCURMENT PLAN TEMPLATE FOR SELECTION OF WORKS COMPON ESTIMATED PROCUREMENT ENT DESCRIPTION OF THE ASSIGNMENT COST ($) METHOD Sub-Component 2.3 - Expanding SME Participation in high Potential Value Chain Medium value and local availability. The user will be able to specify detailed requirements to which bidders may respond in offering bids. Value for money National will also be 2.3.1 Refurbishment of the Horticulture Incubation Hub 250 000.00 Competitive Bidding achieved. COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT 13 | P a g e PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS JUSTIFICATION S FOR THE ESTIMATED PROPOSED COMPON COST ($) PROCUREMENT SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD Efficient method for procuring limited quantities of readily Request for available off-the- 3.1.1 Partitioning of New PMU office space 50 000.00 Quotations shelf goods 14 | P a g e CHAPTER 2 2.0 OVERVIEW OF COUNTRY, BORROWER AND MARKET PLACE 2.1 Operational Context This section provides an overview of the context in which the project will be implemented and the conditions under which the procurement process will take place. It is essentially based on a simplified Governance, Economic, Sustainability and Technological (GEST analysis as suggested in the procurement guidance: Project Procurement Strategy for Development Short Form Guidance (World Bank:2017). 2.1.1 Governance Aspects Lesotho’s private sector is largely concentrated in two sectors – mining and textiles/apparel manufacturing – and economic diversification has proven challenging due to a lack of competitiveness. The two sectors account for 84 percent of all formal sector employment and over two-thirds of all exports. Both sectors have experienced challenges in recent years. Textile and apparel exports have been declining due to competitiveness challenges and Kenya has overtaken Lesotho as the leading apparel exporter to the United States under the African Growth and Opportunity Act (AGOA). Total employment in the export manufacturing sector dropped from a peak of 43,500 in February 2020 to a low of 31,000 in April 2020 before rebounding to 39,000 in September 2020.1 It was reported that an additional 6,000 workers had been laid off in 2021. Job losses in the textile/manufacturing sector have had a significant impact on women and on widening gender gaps in labour market outcomes in Lesotho. Women comprise 80 percent of the approximately 40,000 textile workers in Lesotho and an increasing 1 LNDC survey of 64 firms in eight industrial estates, November 2020; most of these factory workers are women 15 | P a g e proportion of those who migrate to South Africa for jobs in the textile industry.2 The pandemic has exposed the underlying challenges that are stifling the export competitiveness of the manufacturing sector as well as exposing the vulnerable position of women workers in the sector, who suffer from occupation segregation across the entire spectrum of labour market opportunities occupying lower-skilled jobs compared to men, even in sectors such as manufacturing where they predominate. Lesotho’s mining sector is entirely dependent on diamond exports which have faced declining demand in recent years. Lesotho’s business environment is still weak despite recent reforms, with political instability, tax rates and practices of the informal sector emerging as the top three constraints for firms. The Second National Strategic Development Plan (NSPD II) (2019-2023) identified an “uncompetitive business environment” as one of the key binding constraints on the growth of private enterprises, adversely affecting both FDI and local micro, small, and medium enterprises (MSMEs). Recent reforms include new legislation for business registration and licensing and secured lending as well as starting adoption of digital systems and procedures in trade facilitation, land administration, and construction permits, all supported under the World Bank’s Second Private Sector Competitiveness and Economic Diversification Project (PSCED2), which closes in June 2022. However, weak regulations and inadequate institutional capacity hinder the effective implementation of these reforms necessary for meaningful impact. Lesotho’s ranking in the Global Competitiveness Index dropped from 123 to 131 out of 141 countries (from 2014 to 2019), and the Logistics Performance Index ranking also dropped from 133 to 139. In the most recent Enterprise Survey, the top constraints faced by firms are (in order of severity): (i) political instability, (ii) tax rates, (iii) practices of the informal sector, (iv) access to finance, (v) crime, (vi) theft and disorder, (vii) access to land, (viii) electricity (power supply), (ix) corruption (x) tax administration, and (xi) customs and trade 2 Botea, Compernolle, and Chakravarty 2018 16 | P a g e regulations.3 These challenges have manifested in different ways. For example, insolvency takes 2.6 years with a recovery rate of 28 cents per dollar compared to 2 years and 43 cents of recovery for the rest of the SACU region4 and the onerous licensing regulations have left local wool and mohair farmers with just one broker through whom they can sell their production. 3 World Bank Enterprise Survey, 2016 4 IMF Data 17 | P a g e 2.1.2 Economic Aspects Despite being a lower-middle income country, Lesotho experiences persistently high levels of unemployment, informality, inequality, and poverty, which have been further exacerbated by the Covid-19 pandemic. GDP growth has steadily worsened over the past decade, from a peak of 6.3 percent in 2012 to -11.1 percent in 2020, resulting in a 12 percent decline in GDP per capita from 2016 to 2020 Lesotho’s poor economic performance has been the result of compounding factors including declining revenues from the Southern African Customs Union (SACU)5, recurrent climate related shocks that have drained fiscal resources6, a high public sector wage bill that has inhibited spending on development objectives, and contraction of key economic sectors (manufacturing and tourism) due to the Covid-19 pandemic. Unemployment is at 22.5 percent7, and while the poverty rate in Lesotho fell from 56.6% to 49.7% between 2002 and 2017, economic vulnerability persists with more than 75% of the population either poor or vulnerable to poverty, driven in large part by exposure to climatic shocks. Declines in remittances due to Covid-19 related border restrictions have further exacerbated poverty. Although income and other measures of inequality have fallen, Lesotho remains one of the most unequal countries in the world.8 Overall, Lesotho’s economic and social development is not commensurate with the country’s lower- middle-income-status.9 The public sector has a disproportionate role in the economy, crowding out private participation and resulting in a weak and largely informal private sector. The government has been the main driver of economic activity, with public spending accounting for 60 percent of GDP and with public sector 5 SACU revenues fell from 30% of GDP in FY2012/13 to 17.7% of GDP in FY2017/18 and are expected to decline further to 15.2% of GDP in FY 2019/20. 6 The average annual cost of disaster response is estimated at US$19.3 million, or 1.6 percent of the total budget expenditure in the 2019/20 fiscal year. 7 22.5 percent unemployment (strict definition) or 38.3 percent (expanded definition) in 2019. Systematic Country Diagnostic. World Bank (Forthcoming) 8 Lesotho Poverty Assessment. World Bank (2019). 9 IMF Article IV Consultation (2019) 18 | P a g e investment levels averaging around 29 percent of GDP since 2010, both figures amongst the highest in the world. The government’s contribution to GDP now far exceeds that of the textile and apparel industry, which is the largest private sector industry in Lesotho. Lesotho’s public sector wage bill (as a percentage of GDP) is one of the highest in the world and has crowded out private sector employment. Public sector workers earn an average monthly salary that is approximately seven times higher than the minimum wage of a skilled worker in the textile sector.10 The recent Mid-Term Budget Review projects the compensation of employees to account for 45.9 percent of total government expenditures for 2020/21. Core inflation, which excludes the CPI suppliers with extreme price changes, however, decelerated from 4.2 percent in June 2021 to 3.9 percent in July 2021. The decline was broad-based but major contributors were food and non-alcoholic beverages, transport, housing, water, electricity, gas and other fuels and alcohol and tobacco components. The disinflation during the review period reflected declining international food prices due to better cereal production from the United States and Argentina and cancelled grain import orders from China. In addition, the exchange rate appreciation of South African Rand against the US. Dollar contributed to falling domestic prices, amid favourable harvest conditions, domestic availability of grain and limited food import demand. (Central Bank of Lesotho Monthly Economic Review (July 2021). 2.1.3 Sustainability Aspects Sustainable procurement is a process which incorporates sustainability considerations throughout the procurement process in order to achieve optimal value for money in delivering development objectives. (Sustainable Procurement an introduction for practitioners to sustainable procurement in World Bank IPF projects November 2016). The United Nations Environment Programme (UNEP) defines Sustainable Public Procurement 10 Lesotho Poverty Assessment. World Bank (2019) 19 | P a g e (SPP) as “a process whereby organisations meet their needs for goods, services, works and utilities in a way that achieves value for money on a whole life basis in terms of generating benefits not only to the organisation, but also to society and the economy, whilst minimising damage to the environment” (United Nations Environment Programme, 2015). The project is supporting broad reforms on financial inclusion and the private sector. Such efforts are meant to strengthen access to finance, create jobs, and support export-led growth. Sustainability will be supported through three main avenues, system-level interventions, infrastructure development, and skills development/capacity building. a) System-level Interventions will Promote Structural Reform. System-level interventions include investments to enhance the interoperability of government IT systems that facilitate private sector activity, implementation of a government payment gateway to support G2B digital payments, investments to strengthen credit infrastructure, and the establishment of a private sector window within the contingency fund and procurement of sovereign insurance (which will be co-financed on a sliding basis, so the cost is increasingly transferred to the budget over the life of the project). b) Establishment of Infrastructure: The project will support the establishment of a sustainable entrepreneurship hub, seed financing facility, infrastructure for the horticulture incubator program. This infrastructure will exceed the life of the project, enabling activities to continue. c) Technical Assistance will Build Skills Amongst the Workforce and Government Capacity. Technical assistance will be provided to the Government to address deficiencies and build interoperability and strengthen disaster risk financing. For the workforce, skills development initiatives will build technical, supervisory and management capacity in high potential sectors and capacity of MSMEs 20 | P a g e and entrepreneurs. Building capacity at the government level will enable line ministries and agencies to continue project activities after the completion of the project. Skills development is intended to equip the workforce with the skills required at the labour market, thereby enabling them to find employment. 2.1.4 Technological Aspects Digital transformation can foster economic growth, reduce poverty, increase productivity and create jobs. However, its potential in underutilised in Lesotho. Whereas good progress has been made in improving digital infrastructure, adoption and use of digital technology is lagging. Around two thirds of the population are not regularly using the internet, pointing to a wide digital divide. As a result, the ability of the government to take advantage of the internet connectivity and digital channels of service delivery for COVID-19response is limited. Adoption and use of digital technology should be accelerated to meet the needs under the pandemic, but also for long-term recovery and development. In 2018, approximately two-thirds of the population were not using the internet regularly even though 97 percent of the population was covered by a 3G network and 72 percent by the 4G network signal. Lesotho ranked 133 on the 2017 ITU ICT Development Index, behind South Africa (92), Botswana (105) and Namibia (118). This ranking was driven by limited use of, and demand placed on the extensive broadband infrastructure. Digital public platforms such as digital ID systems and digital financial services are key for improving efficiency, quality and inclusiveness of the public and private services. Though several G2B services have been developed and adopted with success, the government may need to consider adopting more coordinated and strategic approach towards advancing digital government. Investments in technology may need to be put on shared interoperable infrastructure and services that can be leveraged across various government entities. Legal and regulatory gaps especially concerning cybersecurity, electronic transactions and e-commerce should be fixed. A road map for adopting electronic payments across all government services 21 | P a g e should be developed and the digital financial services market further enhanced. Lesotho is characterised with private sector that makes limited use of digital technologies. In the private sector, digital technology can change the way economies of scale are achieved, particularly through e-commerce and digital payments. The digital economy may provide the better matching of buyers and sellers in a competitive marketplace. The digital economy offers potential for enhanced service delivery in the public sector, but the Lesotho government’s efforts in this field appear fragmented and slow moving. Improved digital infrastructure can only achieve the desired transformational impact if combined with a capable public sector, investments in digital skills and literacy, increased access to digital financial services, and ramped up support for digital start-ups and existing businesses. Though Lesotho is characterised with weak business environment induced by weak government regulations and policies and inadequate institutional capacity to support implementation of reforms that curtail the weak environment, the success of the PSECDP II in implementing reforms supporting private sector development is an indication of the willingness of the country to eliminate these constraints and enhance its rating. The environment within which the CAFI project will be implement is deemed favourable and pose no potential risk that may affect the efficiency and the effectiveness of the project implementation. As mentioned above, the low level of inflation and stable exchange rate will support efficient procurement of both goods and services that would create value for money. Nevertheless, the project encompasses enormous digital transformation that may call for project implementing agencies to prepare accurate technical specifications to ensure relevant purchase of equipment and technology to meet the project development objectives. “World Bank. 2020. Lesotho Digital Economy Diagnostic. World Bank, Washington, DC. © World Bank. https://openknowledge.worldbank.org/handle/10986/33881 License: CC BY 3.0 IGO.” 22 | P a g e 2.2 Assessment of Borrower Capability and Project Implementation Unit (PIU) The Project governance is an “oversight function that is aligned with the organization's governance model and encompasses the project life cycle,” this is according to A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition (Project Management Institute, 2013, p. 34). There are two critical elements in this statement that need to be emphasised: • Alignment with organization's governance: There needs to be an understanding of the project's environment to ensure that there is a right fit with the established Project's governance. This alignment is a crucial factor and has been considered when defining (1) the project governance framework, (2) roles and responsibilities and (3) stakeholder engagement and communication. The project governance structure is similar to the one used in the implementation of PSCEDP II, which has proven to be effective. The PSCEDP II structure has maintained constant flow of information from the Project Management Unit to all key stakeholders. The proposal is therefore to adopt a strengthened version of the PSCEDP II governance structure (to match the project size) as it ensures that all key stakeholders that are critical for the successful implementation of the project are represented; The Department of Planning under the Ministry of Trade and Industry (MTI) will remain the implementing agency for the CAFI project as MTI already has extensive experience in implementing WB-financed projects. Critical to the governance structure are the following: a) Project Steering Committee 23 | P a g e The Steering Committee will provide advice, ensures delivery of the project outputs and the achievement of project outcomes. The committee is responsible for policy decisions to support the project approvals and implementations, review project progress and facilitates for implementation by the PIUs. The steering committee helps to steer the project through from start to completion. The committee: • Reports to the stakeholders. • Consists of representatives of key Stakeholder Ministries (Trade and Industry, Finance, Development Planning, Agriculture and Food Security, Tourism, Environment and Culture etc.), relevant State- Owned Enterprises (Lesotho National Development Corporation, Basotho Enterprise Development Corporation and Lesotho Tourism Development Corporation), Maseru City Council and critical regulators (Central Bank of Lesotho, Land Administration Authority and Lesotho Revenue Authority); • Reports to GoL (Ministry of Finance, Ministry of Trade and Industry and others) and WB on project implementation status; • Coordinate other ministries around project implementation; • The Principal Secretary of the Ministry of Trade and Industry shall chair the Steering Committee; and • The Steering Committee receives reports from the Project Manager. b) Client/Contracting Authorities • The contracting authority is the Ministry of Trade and Industry. • Signs all contracts with private entities to implement the project (works, services, goods); • Authorise payments to all private entities that have been contracted. • Report to GoL (Ministry of Finance and others) and WB on project implementation status; and • Coordinate other ministries around project implementation. 24 | P a g e c) Project Management Unit (PMU)/ Project Implementation Unit • As the frontline actor, PIU plans, executes, monitors, administers and manages the project representing the project implementing agency (MTI); • Reporting to the Ministry of Trade and Industry and Stakeholder in the format agreed with the Ministry of Development Planning; • Establish financial accounting and control systems and ensure accurate and timely report submissions and funds flow from WB and onwards to the implementing agencies. Financial status and forecast, disbursements; • Procurement and contracting of private entities; • All contracts management (works, services, goods); • Supervise, coordinate and monitor the work of PIUs for implementation of project activities; and • Contribute to institutional analysis if necessary and requested. c) Project Manager (PM) The Project Manager is responsible for the day-to-day implementation of the project through performing the following: • Reporting to MTI and the Steering Committee; • Financial status and forecast, disbursements; • Procurement and contracting of private entities; • Manage Human Resources of the Project; • Oversee contracts negotiations; • Manage the assets of the project; • All contracts management (works, services, goods); • Physical monitoring of works (technical, E&S etc…); and • All other duties as stipulated in the Terms of Reference. A further assessment of the Procurement Capability within the Ministry of Trade and Industry (PMU) has been done. The Ministry through the PMU/PIU 25 | P a g e has over the past fifteen years successfully implemented similar projects including: a) The First Private Sector Competitiveness and Economic Diversification Project (PSCEDP I) b) The Second Private Competitiveness and Economic Diversification Project (PSCEDP II) and c) PSCEDP II - Additional Financing (on-going). Procurement Risk Assessment: The procurement risk assessment has taken into considerations the Strengths, Weaknesses, Opportunities and Threats of the operational context of the implementing agencies. The project will be implemented by the same Project Management Unit (PMU) that is currently implementing the World Bank financed Second Private Sector Competitiveness and Economic Diversification Project (PSCEDP II) under MTI. The PSCEDP II PMU has a good track record of many years and has established project implementation capacity as well as working relationships with key agencies and Ministries across the Government. The PSCEDP II is ending in June 2022 thereby allowing the PMU to be available and ready for CAFI project implementation from the outset of the project. The PMU will be responsible for all fiduciary aspects of the project including FM and procurement activities. The MTI and its PMU, having prior experience of working on PSCED and PSCED II projects, are expected to implement the project smoothly. However, the fact that there will be more project beneficiaries under each component and subcomponent, could pose coordination risk due to the complexity of the project. Based on the existing procurement capacity within the MTI/PMU and taking into consideration one additional Procurement Officer to be recruited by the Project the procurement risk is rated Moderate. This rating has also considered the fact that the current project does not have any IPF component involving complex or high value contracts. It is also expected that all the procurement activities envisaged under the new project (CAFI) will be simple and small value contracts. Taking all these circumstances into consideration, the four major capacity limitations or risks identified at the moment are: (i) lack of prior experience of implementing IPF procurement procedures; (ii) coordination challenge as implementation of components and subcomponents involve many beneficiaries; (ii) Implementation capacity 26 | P a g e gap within the different beneficiaries and (iii) lack of practices on good contracts implementation management. 2.3 Project Procurement Unit Structure The Procurement Unit within the Project Management Unit (PMU) is staffed with qualified procurement professionals i.e. The Procurement Manager holds MSc Degree in Supply Chain Management with more than ten (10) years’ experience in procurement, while the Procurement Officer has bachelor’s degree in economics with seven years’ experience. TABLE 2: PIU Procurement Staff Supply Chain Staff Experience working on Bank Position Qualificati Experienc financed Projects ons e procurement Procurem MSc in Over 10 The Procurement Manager has ent Supply years’ held a senior procurement Manager Chain, BA experience management positions since Degree in in 2017. She managed and Business procureme administered procurement Administrati nt. services under the Lesotho on, government’s capital projects Chartered and donor funded projects Institute of including AfDB and World Bank Procuremen supported projects. t and Supply (Professiona l Diploma Level 6) Procurem BA Over 7 The Procurement Officer has over ent Economics years’ 7 years’ experience working on Officer and experience GoL capital projects that are Chartered in supported by development Institute of procureme partners including AfDB and the Procuremen nt. World Bank. In addition, the t and Supply officer has worked as a (Diploma, Procurement Officer for the level 4) World Bank financed PSCEDP since 2021. 27 | P a g e 2.4 Market Analysis The objective of market research and analysis is to develop a good understanding of the market sectors that have been identified as having the potential to bid for the goods, services, and/or works required by the Project. This is to ensure the eventual Procurement Approach maximizes the likelihood of the right suppliers participating, and the right supplier being selected thereby minimizing failed procurement processes due to no bids, or the wrong types of bids. Supplier Preferencing identifies the approaches suppliers use based on their segmentation of customers. The table below provides a view of a supplier’s likely approach to the project in each category. 28 | P a g e TABLE 3: Supplier Preferencing Model SUPPLIER PREFERENCING MODEL Relative Supply value of Account positioning Compon the Attractiven ent Description of the assignment Business ess COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE ($20.25 MILLION) Sub-Component 1.1: Enhancing Government to Business Digital Services ($ 6.5 million) 1.1.1 Upgrade of the business registration and licensing system at OBFC High High core Upgrade of the LRA customs system, based on UNCTAD`s ASYCUDA core 1.1.2 World System High High Upgrade of the LAA land registry system and the MCC construction core 1.1.3 permitting system High High 1.1.4 Design and development of the G2B interoperability framework Low High Developmental 1.1.5 Design and development of a G2B payment gateway Low High Developmental Sub-Component 1.2: Improving Access to Financial Services ($ 3.0 million) Upgrade of the credit infrastructure system that facilitates access to Developmental 1.2.1 business financing low High Development of credit scoring system to enhance the utility of credit Core 1.2.2 reporting High High 1.2.3 Upgrade of LERIMA movable asset registry High High Core 1.2.4 Development of New financial products to promote market innovation Low High Developmental Capacity building of financial institutions and MSME`s to utilise asset- Core 1.2.5 based lending High High TA to Postbank for development of business case for agricultural value Core chain finance, including market assessment and financing 1.2.6 methodology High High Design and implementation of a management information system (MIS) Developmental 1.2.7 to support value-chain financing Low High 29 | P a g e Review and improve governance, institutional and operational features Core 1.2.8 of the L-PCG High High 1.2.9 Develop a business case and financial model for portfolio guarantees High High Core Design and implement the portfolio guarantee scheme including Core 1.2.10 development of supporting documentation and systems High High 1.2.11 Capacity building High High Core Sub-Component 1.3 – Strengthening the Resilience of MSMEs to Climatic Shocks ($ 10.75 million ) TA on disaster risk financing including drafting of National Disaster Risk Core 1.3.1 Finance Policy for MoF High High Design and development a database for informal MSMEs and integrate Developmental 1.3.2 the database into the existing business registry Low High TA on design and procurement of sovereign insurance backstop and Developmental 1.3.3 co-financing of insurance premiums Low High Draft regulations to govern the operational activities of the existing Core 1.3.4 MoF Contingency Fund High High COMPONENT 2: SCALING SUPPORT FOR ENTREPRENEURSHIP AND MSMES ($ 29.5 MILLION) Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility (12.5 million) Procure a private operator to support the establishment of a Core sustainable Entrepreneurship Hub within the Tourism Information Craft 2.1.1 Centre High High 2.1.2 Design and development of an incubation support program High High Core Facilitate the integration of the Lesotho Start-up Community within a Core 2.1.3 wider regional Entrepreneurship ecosystem High High Procure a private operator to establish and manage a seed financing Core 2.1.4 facility and an associated acceleration program High High Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program ($ 5.0 million) Procure private sector service providers to augment the delivery Developmental 2.2.1 capacity of LEAP PMU Low High Sub-Component 2.3 - Expanding SME Participation in high potential Value Chains ($ 12 million) 2.3.1 TA to set up a Horticulture Incubation Hub Low High Developmental 30 | P a g e Summary of Procurement Market Analysis for the Project: Considering the local, Regional, and international market situations and the nature and value of the procurement activities under this project, the market risk is low and favourable. Conducting further detail market research for other innovative market approaches and selection methods is not proportional. Therefore, the default selection methods are fit-for-purpose as indicated in table 6, Chapter 6 of this PPSD. 31 | P a g e 32 | P a g e CHAPTER 3 3.0 PROJECT PROCUREMENT RISK ANALYSIS TABLE 4: Project Procurement implementation capacity (MoTI) Risk Analysis Risk Probability Impact Risk Rating Description of Mitigation of Measure occurrence (Major, (High, (Very likely, minor, Substantial, likely, unlikely, negligible, or Moderate, Low or not not or Not applicable) applicable) Applicable) 1. Accountability for Procurement Unlikely Major Moderate (2) Prepare and adopt a Project Decisions Procurement Manual (PPM), that identifies lines of responsibilities. 2. Internal Manuals and Clarity of Unlikely Minor Moderate (3) Develop a project the Procurement Process procurement manual that is comprehensive and easy to follow and should be accessible to all procurement staff. 3. Record Keeping & Document All procurement documents Management Systems Unlikely Minor Moderate (2) will be kept in procurement office with contract register manual and should be accessible to all procurement staff. 4. Procurement Planning Likely Major High (4) Prepare and adopt a project operation manual (POM), including a chapter on procurement comprising of 33 | P a g e Risk Probability Impact Risk Rating Description of Mitigation of Measure occurrence (Major, (High, (Very likely, minor, Substantial, likely, unlikely, negligible, or Moderate, Low or not not or Not applicable) applicable) Applicable) clear rules, step by step procedures and responsibility, timeline requirements for procurement activities. All Procurement assignment should be uploaded in STEP. 5. Bidding documents, qualification/ Likely Minor Substantial (3) Follow Bank’s Procurement shortlisting/ evaluation criteria templates. Standard bidding documents, evaluation forms and evaluation criteria should be availed and provided in the bidding document. 6. Staffing Unlikely Major Moderate (2) Recruitment of qualified and experienced staff and require staff involved in procurement to declare their interest and sign a declaration form. 7. Advertisement, Pre-bid/proposal Unlikely Minor Moderate (2) Ensure that all adverts, pre Conference and Bid/Proposal bid/proposal conference and Submission bid/proposal submissions should follow the banks procurement procedures and regulations. 34 | P a g e Risk Probability Impact Risk Rating Description of Mitigation of Measure occurrence (Major, (High, (Very likely, minor, Substantial, likely, unlikely, negligible, or Moderate, Low or not not or Not applicable) applicable) Applicable) 8. Evaluation and Award of contract Unlikely Major Moderate (2) Recruit qualified technical evaluation team and follow the bank`s procurement procedure. 9. Review of Procurement Decisions Unlikely Major Moderate (2) Establish a procurement and Resolution of Complaints complaint handling mechanism consistent with the Government Procurement Rules and Regulations and in line with the World Bank`s requirements. 10. Contract Management and Likely Minor Substantial (3) Develop a contract Administration management strategy and contract management plan 11. Procurement Oversight Unlikely Major Moderate (2) Procurement audits should be carried out regularly. 12. Procurement functional Unit Unlikely Major Moderate (2) Recruit qualified performance procurement staff with experience in implementation of World Bank financed project procurement. Overall Project Procurement Risk 28/12 =2.3 ~~ (2) = Moderate rating 35 | P a g e Note: The risk ratings in fourth column of the above table are determined using the following formulation: Probability of Impact Risk Rating Occurrence Likely or Equal Major High Likelihood Likely or Equal Minor Substantial Likelihood Likely or Equal Negligible Moderate Likelihood Unlikely Major Moderate Unlikely Minor Moderate Unlikely Negligible Low Not applicable Not Applicable Not Applicable 36 | P a g e Procurement Risk Mitigation Measures: The MTI will have overall responsibility of procurement under the project. Based on the above preliminary procurement implementation risks identification, the mitigation measures may also include: (i) provision of reorientation/training to the PMU on Bank’s procurement procedures and contract management, including use of STEP platform; (ii) putting in place simple, but efficient, procurement and contract management mechanism (tracking system);(iii) Develop Project Operational Manual/Project Procurement Strategy for Development (PPSD) that would assist the practitioners on procurement routines and (iv) strengthen the PMU based on the needs of the new project. More frequent World Bank implementation support missions with the aim of providing closer support and monitoring the performance of PMU and its Procurement team’s performance would also add value. Record Keeping: All records pertaining to award of tenders, including bid notification, register pertaining to sale and receipt of bids, bid opening minutes, bid evaluation reports and all correspondence pertaining to bid evaluation, communication sent to/with the World Bank in the process, bid securities, and approval of invitation/evaluation of bids by the management would be retained by the Procurement Unit and also uploaded in the STEP for Post ante review and independent procurement audit, as necessary. Operational Context, SWOT Analysis: According to CIPS (2012) Strengths, weaknesses, opportunities, and threats (SWOT) analysis is a technique of corporate appraisal, used to assess the internal resources of an organisation (or function or project) to cope with and/or capitalise on factors in the external environment in which it operates. This tool will be used to assess the PMU’s capability. A summary of the strengths, weaknesses, opportunities, and threats regarding the capacity of the PMU is presented as follows: 37 | P a g e 38 | P a g e STRENGTHS The Project Management Unit (PMU) has extensive experience in executing projects funded by the World Bank and the African Development Bank (AfDB) and has both tangible and non-tangible resources to execute projects. The unit already has some human capital with relevant skills set to execute the project and the Project Manager has successfully managed the PSCEDP I and PSCEDP II and PSCEDP II – Additional Financing. The Project Manager is supported by an experienced competent fiduciary management team that has more than 10 years’ experience. The project also has experience in stakeholder and private sector engagements and administration of matching grants. The PMU already has office space, furniture and ICT equipment which are in good condition to start the new project. The responsible Ministry also has prior operational experience in implementation of World Bank financed projects. WEAKNESSES The procurement staff lacks operational capacity to administer procurement of multiple packages at the same time in a timely manner. The operational capacity is limited by under-staffing of the Procurement Unit. OPPORTUNITIES The Project has tools and systems in place that enables procurement to be carried out effectively, efficiently, and economically. All procurements under the project will be carried out in accordance with the World Bank’s Procurement Regulations for Investment Project Financing Recipient’s- Procurement in investment Project Financing Goods, Works, Non-Consulting and Consulting services. The project will also be subject to the guidelines on preventing and combating fraud and corruption in projects Financed by IBRD Loans and IDA Credit and grants. The Systematic Tracking Exchange Procurement (STEP) system will be used to track all procurement planning, execution, and contract management. The PMU will also recruit additional procurement staff to strengthen the capacity of the Procurement Unit. 39 | P a g e THREATS The main threat is political instability, which may hider implementation of important policies and regulations. The governing coalition remains fragile with considerable risk of frequent change in administration during project implementation. Political instability can also deter new international investors and experienced service providers. Limited availability of service providers can in turn delay procurement processes and may lead to selection of inexperienced consultants. Strength: Weakness 5. PIU’s Prior experience of similar • Limited manpower/staff projects implementation for increased works 6. Well-functioning PMU having • Lack of experience on necessary facilities and complex contracts motivated team procurement and 7. Availability of tested and well- contracts implementation functioning working procedures management and well-defined responsibility • Lack of business matrix performance standard Opportunities Threats • Technical support and training • Political instability opportunities from the • Weak local/national Development partners (world market Bank & others). • Application and use of good practice standard procurement documents of the development partners (World Bank) including use of STEP for tracking procurement transactions. 40 | P a g e • Availability of providers in the region, like SA. Key Risks Identified from operational context and agency capacity: i. MoTI-PIU institutional performance capacity limitations. ii. Inadequate local market. iii. Political instability and weak macro-economic performance 41 | P a g e CHAPTER 4 4.0 STAKEHOLDER ANALYSIS The table below presents analysis of key stakeholders responsible for implementation of various components of the project towards achievement of the Project Development Objective: TABLE 5: Stakeholder Analysis STAKEHOLDER MANAGEMENT PLAN Interest in Stakeholder Name the Stakeholder Objectives from the Stake Holder Management Project11 Procurement Approach R A C I World Bank - - - Y • To ensure that project procurement in C compliance with procurement objectives. Consult and Keep informed and comply Ministry of Trade and Y Y Y Y • MTI is the implementing agency MTI is responsible and accountable Industry and should be consulted and informed Maseru City Council - - Y Y • Project Implementing agency for upgrade MCC is consulted and informed of the construction permitting system Basotho Enterprise - - Y Y • Stakeholder in the implementation of BEDCO is consulted and informed Development Corporation subcomponent 2.1 and 2.2 of the project. (BEDCO) 11 Responsible, Accountable, Consulted, Informed 42 | P a g e STAKEHOLDER MANAGEMENT PLAN Interest in Stakeholder Name the Stakeholder Objectives from the Stake Holder Management Project11 Procurement Approach R A C I Lesotho Revenue - - Y Y • Stakeholder in the implementation of LRA is consulted and informed Authority (LRA) subcomponent 1.1 and 1.2 and 1.3 of the projects. One Stop Business - - Y Y • Stakeholder in the implementation of OBFC is consulted and informed Facilitation Centre (OBFC) subcomponent 1.1. Ministry of Small Business - - Y Y • Stakeholder in the implementation of MSBDC is consulted and informed Development and subcomponent 1.3, 2.1 and 2.2 of the Cooperatives project. Prime Minister’s Delivery - - Y Y • Stakeholder in the implementation of PMDU is consulted and informed Unit (PMDU) component 3 Ministry of Labour and - - Y Y • Stakeholder in the implementation of MoLE is consulted and informed Employment subcomponent 2.3. Ministry of Public Works - - Y Y • Stakeholder in the implementation of MPW is consulted and informed subcomponent 2.3. Ministry of Transport - - Y Y • Stakeholder in the implementation of MoT is consulted and informed subcomponent 2.3. Lesotho National - - Y Y • Stakeholder in the implementation of LNDC is consulted and informed Development Corporation subcomponent 2.3. (LNDC) Central Bank of Lesotho - - Y Y Stakeholder in the implementation of CBL is consulted and informed (CBL) subcomponent 1.2 and 1.3 of the project. National University of - - Y Y • Stakeholder in the implementation of MUL is consulted and informed Lesotho (NUL) subcomponent 2.3. 43 | P a g e CHAPTER 5 5.0 PROCUREMENT OBJECTIVES Based on the Strategic Analysis, Risk Assessment and Stakeholder Analysis, the five key Procurement Objectives that if achieved, would help support the delivery of the Project Development Objective are as follows: • Packaging based on market analysis to aim for an average of 8 bidders’ participation in each bid. • Foster competition to enhance achievement of VfM by familiarizing the vendors with the SBDs for international approach to market through vendor conferences and pre-bid meetings and site visits, and suitably modifying and customizing the bidding documents and conditions such as qualification requirements and application of bid securities with the objectives receiving competitive bid prices which are within approximately 15% of client’s cost estimate. • Implementation of works and services in time to ensure that 95 percent of bids are awarded without extending bid validity and that rebid in not more than 5 percent cases, for all procurements. • Awarding contracts to qualified, experienced, capable bidders so that 90 percent of contracts are executed within original allotted time; and • Contracts are completed with not more than 15 percent cost overruns by carrying out robust design at bidding stage. 44 | P a g e CHAPTER 6 6.0 PROCUREMENT APPROACH OPTIONS AND RECOMMENDATIONS This procurement strategy/approach is designed based on the project requirements, technical solutions, and market information, institutional capacity and experience of the Ministry of trade and Industry (MoTI). The Market approach and selection method proposed for each package has taken into considerations values, complexities, local market capacity and institutional experiences of MoTI to achieve better Value for Money (VfM) while supporting the project achievement of objectives its objectives. The project has no high value and complex contract packages as such. However, the PPSD has focused on separate packages for consultancy services and works using both international and national approach to markets with the objectives of fostering competitions to enable the PIU get best of what the market can offer. For certain unique packages, where open competition may not be the best-fit approach, Direct Selection (DS) has been proposed with clear justifications on why DS is found to be fit-for-purpose as against the default open competitive market approaches. The following activities are proposed for Direct Selection market approach for the reasons as indicated in the below table: Package/contract Reason why non-competitive market approach is Name of Proposed appropriate and departing from the preferred and supplier/consultant default competitive methods 45 | P a g e Consultancy Services for UNCTAD is uniquely and exceptionally qualified to upgrade UNCTAD is an eligible design and upgrade of the business registration and licensing system at OBFC as it firm under Bank’s business registration and was originally developed by them. It is also the case that financed projects. It is a the tasks represent a natural continuation of previous UN Agency based in East licensing system at OBFC work carried out by a consultant, where continuity in the and Southern Africa; technical approach, experience acquired, and continued professional liability of the same Consultant may make continuation with the initial Consultant preferable to a new competition. The performance of UNCTAD has been satisfactory in the previous assignment(s); Consultancy Services for design UNCTAD is uniquely and exceptionally qualified to upgrade UNCTAD is an eligible LRA customs system as it was originally designed and and upgrading of the LRA customs firm under Bank’s developed by them. The task represents a natural system, based on UNCTAD`s continuation of previous work carried out by a consultant, financed projects. It is a where continuity in the technical approach, experience ASYCUDA World System UN Agency based in East acquired, and continued professional liability of the same consultant may make continuation with the initial and Southern Africa; consultant preferable to a new competition The performance of UNCTAD has been satisfactory in the previous assignments Consultancy Service for Design Only ESRI is qualified and has experience of exceptional ESRI is an eligible firm worth for the upgrade of the LAA land registry system as and upgrading of the LAA land they designed and developed the system. The task under Bank’s financed registry system represents a natural continuation of previous work carried projects. It out by a consultant, where continuity in the technical approach, experience acquired, and continued professional is a South African liability of the same consultant may make continuation with company based in the initial consultant preferable to a new competition The 46 | P a g e performance of esri has been satisfactory in the previous Midrand 1685, Cnr New assignments Road. Consultancy Services for Only EXPERIAN is qualified and has experience of EXPERIAN is an eligible exceptional worth for the upgrade of the credit Design and upgrading of the infrastructure system as they designed and developed the firm under bank’s credit infrastructure system system. The task represents a natural continuation of financed projects. It is a previous work carried out by a consultant, where continuity that facilitates access to in the technical approach, experience acquired, and South African company continued professional liability of the same consultant may based in Stellenbosch, business financing make continuation with the initial consultant preferable to a new competition The performance of EXPERIAN has been Experian House, 3 satisfactory in the previous assignments Neutron Avenue, Techno PARK. Consultancy Services for Only Paradigm is qualified and has experience of PARADIGM is an eligible exceptional worth for the upgrade of the LERIMA movable Design and Upgrading of asset registry as they designed and developed the system. firm under bank’s LERIMA movable asset registry The task represents a natural continuation of previous work financed projects. It is a carried out by a consultant, where continuity in the technical approach, experience acquired, and continued company based in United professional liability of the same consultant may make States, New York. continuation with the initial consultant preferable to a new competition The performance of PARADIGM has been satisfactory in the previous assignments For works packages where designs have been completed and the client’s requirements are well defined, the selection methods would be RFB or RFQs, based on the package’s values. For works where there are conceptual designs and innovation can be introduced by the providers, the selection method will be RFP. The RFP method will also be used 47 | P a g e for selection of consultants. The selection method for supply and installation of software and hardware, as schedules of requirements and specifications are precisely defined by the ministry, the selection method will be RFBs. The table below presents the project market approach and procurement methods for consultancy services, procurement of goods and works. TABLE 6: Procurement Approach and Recommendation PROCURMENT PLAN FOR SELECTION OF CONSULTANCY SERVICES DESCRIPTION OF PROCURE CONTRA JUSTIFICATION FOR THE ESTIMATED COMPON THE MARKET MENT CT RECOMMENDED SELECTION COST ($) ENT ASSIGNMENT APPROACH METHOD TYPE METHOD COMPONENT 1 : ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE Sub-Component 1.1 - Enhancing Government to Business Digital Services Upgrade of the UNCTAD is a UN Agency based in East business and Southern Africa; It is uniquely and 1.1.1 registration and 800 000.00 Direct exceptionally qualified to upgrade 48 | P a g e licensing system DS Lump business registration and licensing at OBFC Sum system at OBFC as it was originally developed by them. Upgrade of the UNCTAD is a UN Agency based in East LRA customs and Southern Africa. It is uniquely and system, based on DS exceptionally qualified to upgrade UNCTAD`s Lump LRA customs system as it was ASYCUDA World Sum originally designed and developed by 1.1.2 System 1 000 000.00 Direct them. ESRI is a South African company based in Midrand 1685, Cnr New DS Lump Road. It is qualified and has Sum experience of exceptional worth for Upgrade of the the upgrade of the LAA land registry LAA land registry system as they designed and 1.1.3 system 1 000 000.00 Direct developed the system. Design and Appropriate method for high value development of QCBS Lump and complex assignment. the G2B Sum Competitive approach is required to interoperability achieve quality and value for money 1.1.4 framework 1 600 000.00 International Appropriate method for high value and complex assignment. Design and Competitive approach is required to development of a QCBS achieve quality and value for money G2B payment Lump 1.1.5 gateway 1 500 000.00 International Sum 5 980 000.00 Sub-Component 1.2 - Improving Access to Financial Services Upgrade of the Lump credit Sum EXPERIAN is a South African company infrastructure based in Stellenbosch, Experian 1.2.1 system that 200 000.00 Direct DS House, 3 Neutron Avenue, Techno 49 | P a g e facilitates access PARK. It is qualified and has to business experience of exceptional worth for financing the upgrade of the credit infrastructure system as they designed and developed the system. Lump EXPERIAN is a South African company Sum based in Stellenbosch, Experian House, 3 Neutron Avenue, Techno PARK. It is qualified and has Development of DS experience of exceptional worth for credit scoring the development of the credit scoring system to enhance system as they designed the system the utility of credit 1.2.2 reporting 600 000.00 Direct Lump Paradigm is a company based in Sum United States, New York. It is qualified and has experience of exceptional worth for the upgrade of the LERIMA DS movable asset registry as they Upgrade of LERIMA designed and developed the system movable asset 1.2.3 registry 200 000.00 Direct Development of Lump Appropriate method for high value New financial Sum and complex assignment. products to Competitive approach is required to promote market achieve quality and value for money 1.2.4 innovation 500 000.00 International QCBS Capacity building Schedule Appropriate method for less of financial of complex assignments. Preparing and institutions and CQS Rates/Ti evaluating competitive proposals is MSME`s to utilise me- not justified asset-based Based 1.2.5 lending 50 000.00 National 50 | P a g e TA to Postbank for Schedule Appropriate method for less complex development of of assignments. Preparing and business case for Rates/Ti evaluating competitive proposals is agricultural value me- not justified chain finance, Based including market assessment and CQS financing 1.2.6 methodology 150 000.00 International Design and Lump Appropriate method for less complex implementation of Sum assignments. Preparing and a management evaluating competitive proposals is information not justified system (MIS) to support value- CQS 1.2.7 chain financing 200 000.00 International Review and Lump Low value assignment with a duration improve Sum less than six months governance, institutional and operational IC features of the L- 1.2.8 PCG 50 000.00 National Develop a Lump Appropriate method for less complex business case and Sum assignments. Preparing and financial model for evaluating competitive proposals is portfolio CQS not justified 1.2.9 guarantees 150 000.00 International Design and Lump Appropriate method for high value implement the QCBS Sum and complex assignment. portfolio Competitive approach is required to guarantee scheme achieve quality and value for money including development of 1.2.10 supporting 2,000,000.00 International 51 | P a g e documentation and systems Schedule Appropriate method for less complex of assignments. Preparing and CQS Rates/Ti evaluating competitive proposals is me- not justified 1.2.11 Capacity building 100 000.00 National Based 2 800 000.00 Sub-Component 1.3 – Strengthening the Resilience of MSMEs to Climatic Shocks TA on disaster risk Lump Appropriate method for high value financing including Sum and complex assignment. drafting of Competitive approach is required to National Disaster achieve quality and value for money Risk Finance Policy QCBS 1.3.1 for MoF 750 000.00 International Design and Lump Appropriate method for less complex development a Sum assignments. Preparing and database for evaluating competitive proposals is informal MSMEs not justified and integrate the database into the existing business QCBS 1.3.2 registry 300 000.00 International TA on design and Lump Appropriate method for less complex procurement of Sum assignments. Preparing and sovereign evaluating competitive proposals is insurance not justified backstop and co- financing of CQS insurance 1.3.3 premiums 150 000.00 International Draft regulations Lump Low value assignment with a duration 1.3.4 to govern the 75 000.00 National Sum less than six months 52 | P a g e operational activities of the IC existing MoF Contingency Fund 1 275 000.00 COMPONENT 2: SCALING SUPPORT FOR ENTREPRENEURSHIP AND MSMES ($ 29.5 MILLION) Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility Procure a private Schedule Appropriate method for high value operator to of and complex assignment. support the Rates/Ti Competitive approach is required to establishment of a me- achieve quality and value for money sustainable Based Entrepreneurship Hub within the Tourism QCBS Information Craft 2.1.1 Centre 500 000.00 International Design and Lump Appropriate method for less complex development of an Sum assignments. Preparing and incubation support evaluating competitive proposals is 2.1.2 program 150 000.00 International CQS not justified Facilitate the Schedule Low value assignment with a duration integration of the of less than six months Lesotho Start-up Rates/Ti Community within me- a wider regional Based Entrepreneurship 2.1.3 ecosystem 50 000.00 National IC Procure a private Schedule Appropriate method for less complex operator to of assignments. Preparing and 2.1.4 establish and 250 000.00 International Rates/Ti 53 | P a g e manage a seed me- evaluating competitive proposals is financing facility CQS Based not justified and an associated acceleration program 950 000.00 Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program Procure private Schedule Appropriate method for less complex sector service of assignments. Preparing and providers to Rates/Ti evaluating competitive proposals is augment the me- not justified delivery capacity QCBS Based 2.2.1 of LEAP PMU 300 000.00 International Sub-Component 2.3 - Expanding SME Participation in high potential Value Chains Lump Appropriate method for high value Sum and complex assignment. TA to set up a Competitive approach is required to Horticulture achieve quality and value for money 2.3.1 Incubation Hub 350 000.00 International QCBS 54 | P a g e PROCURMENT PLAN TEMPLATE FOR SELECTION OF GOODS CONTRA JUSTIFICATION CT TYPE S FOR THE ESTIMATED PROCUREM RECOMMENDE COST ($) COMPON ENT D SELECTION ENT DESCRIPTION OF THE ASSIGNMENT METHOD METHOD COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE Sub-Component 1.1 Enhancing Government to Business Digital Services Conforman Efficient method ce for procuring /Traditional limited quantities ICT equipment for upgrade of the business Request For of readily available 1.1.1 registration and licensing system at OBFC 70 000.00 Quotations off-the-shelf goods Conforman Medium value and ce local availability. /Traditional The user will be able to specify detailed requirements to which bidders may respond in offering ICT equipment for Upgrade of the LRA customs National bids. Value for system, based on UNCTAD`s ASYCUDA World Competitive money will also be 1.1.2 System 150 000.00 Bidding achieved. Conforman Efficient method ce for procuring /Traditional limited quantities ICT equipment for Upgrade of the LAA land Request For of readily available 1.1.3 registry system. 100 000.00 Quotations off-the-shelf goods 55 | P a g e Conforman Medium value and ce local availability. /Traditional The user will be able to specify detailed requirements to which bidders may respond in offering National bids. Value for Competitive money will also be 1.1.4 ICT equipment for G2B interoperability 200 000.00 Bidding achieved. 520 000.00 Sub-Component 1.2 - Improving Access to Financial Services Conforman Efficient method ce for procuring ICT equipment for upgrade of the credit /Traditional limited quantities infrastructure system that facilitates access to Request for of readily available 1.2.1 business financing 100 000.00 Quotations off-the-shelf goods Conforman Efficient method ce for procuring ICT equipment for upgrade of LERIMA movable /Traditional limited quantities assets and integration of data from motor Request for of readily available 1.2.3 vehicle and company registries 100 000.00 Quotations off-the-shelf goods Conforman Efficient method ce for procuring ICT equipment to support implementation of /Traditional limited quantities MIS for Lesotho Post bank value-chain Request for of readily available 1.2.6 financing 100 000.00 Quotations off-the-shelf goods Conforman Efficient method ce for procuring /Traditional limited quantities Request for of readily available 1.2.7 ICT equipment to support L-PCG 100 000.00 Quotations off-the-shelf goods 400 000.00 56 | P a g e Sub-Component 1.3 – Strengthening the Resilience of MSMEs to Climatic Shocks COMPONENT 2: SCALING SUPPORT FOR ENTREPRENEURSHIP AND MSMES Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility Conforman Medium value and ce local availability. /Traditional The user will be able to specify detailed requirements to which bidders may respond in offering National bids. Value for Procure equipment and furniture for the Competitive money will also be 2.1.1 Entrepreneurship Hub 300 000.00 Bidding achieved. Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program Conforman Medium value and ce local availability. /Traditional The user will be able to specify detailed requirements to which bidders may respond in offering bids. Value for Request for money will also be Procure ICT equipment and furniture 70 000.00 Quotations achieved. Sub-Component 2.3 - Expanding SME Participation in high Potential Value Chains Conforman Medium value and ce local availability. National /Traditional The user will be Procure ICT equipment and furniture for Competitive able to specify 2.3.1 Horticulture Incubation Hub 300 000.00 Bidding detailed 57 | P a g e requirements to which bidders may respond in offering bids. Value for money will also be achieved. COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT Conforman Efficient method ce for procuring /Traditional limited quantities Request for of readily available 3.1.1 ICT equipment and furniture for PMU 100 000.00 Quotations off-the-shelf goods Conforman Medium value and ce local availability. /Traditional The user will be able to specify detailed requirements to which bidders may respond in offering National bids. Value for Competitive money will also be 3.1.2 Procure vehicles for PMU and Vehicle 150 000.00 Bidding achieved. PROCURMENT PLAN TEMPLATE FOR SELECTION OF WORKS Estimated Procuremen Component Description of the assignment Cost ($) t Method Sub-Component 2.3 - Expanding SME Participation in high Potential Value Chain Conforman Medium value and National ce local availability. Refurbishment of the Horticulture Competitive /Traditional The user will be 2.3.1 Incubation Hub 250 000.00 Bidding able to specify 58 | P a g e detailed requirements to which bidders may respond in offering bids. Value for money will also be achieved. COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT Conforman Efficient method ce for procuring /Traditional limited quantities Request for of readily available 3.1.1 Partitioning of New PMU office space 50 000.00 Quotations off-the-shelf goods 59 | P a g e CHAPTER 7 7.0 SUMMARY OF PPSD TO SUPPORT THE PREPARATION OF THE PAD BY THE BANK The recommended procurement approach, which is expected to inform the Project Appraisal Document (PAD) is stated in the summary above. The rationale for this approach is primarily based on packaging that is suitable for each procurement package. 60 | P a g e CHAPTER 8 8.0 PROCUREMENT PLAN FOR THE FIRST 18 MONTHS TABLE 8: Procurement Plan for Goods, Works & Non-Consultancy Services 1 2 3 4 5 6 7 8 9 10 11 Expected Expected Expected Expected Expected contract contract Contract Estimat Procurem Prequalif (Prio Bid Bid- contract commence completio Ref. No. Descriptio ed Cost ent ication r/ Floating Opening award ment date n date n (US$’00 Method (yes/no) Post Date Date date 0) ) COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE ($20.25 MILLION) Sub-Component 1.1 - Enhancing Government to Business Digital Services ($520 000.00) CAF/WB/GO/2 ICT 70 RfQ NO Post 5 Jan 23 15 Feb 23 29 March 1 April 23 17 May 23 7 equipment 23 for upgrade of the business registration and licensing system at OBFC CAF/WB/GO/2 ICT 150 NCB NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 8 equipment 61 | P a g e for Upgrade of the LRA customs system, based on UNCTAD`s ASYCUDA World System CAF/WB/GO/2 ICT 100 RFQ NO Post 6 Oct 22 6 Nov 22 18 Nov 22 25 Nov 22 6 Jan 23 9 equipment for Upgrade of the LAA land registry system and the MCC constructio n permitting system CAF/WB/GO/3 ICT 200 NCB NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 0 equipment for G2B interoperabi lity Sub-Component 1.2 Improving Access to Financial Services CAF/WB/GO/ ICT 100 RfQ NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 31 equipment for upgrade 62 | P a g e of the credit infrastructur e system that facilitates access to business financing CAF/WB/GO/ ICT 100 RfQ NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 32 equipment for upgrade of LERIMA movable assets and integration of data from motor vehicle and company registries CAF/WB/GO/ ICT 100 RfQ NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 33 equipment to support implementati on of MIS for Lesotho Post bank value- chain financing CAF/WB/GO/ ICT 100 RfQ NO Post 10 Aug 23 15 Sept 23 29 Sept 23 2 Oct 23 17 Nov 23 34 equipment 63 | P a g e to support L- PCG Sub-Component 2.1 - Establishing an Entrepreneurship Hub and Seed Financing Facility CAF/WB/GO/ Procure 300 NCB NO Post 11 Aug 22 15 Sept 22 29 Sept 22 2 Oct 22 17 Nov 22 35 equipment and furniture for the Entrepreneu rship Hub Sub-Component 2.2 - Scaling Up of the Lesotho Enterprise Assistance Program CAF/WB/GO/ Procure ICT 70 RfQ NO Post 3 Feb 23 2 March 16 March 31 March 23 12 May 23 36 equipment 23 23 and furniture Sub-Component 2.3 - Expanding SME Participation in high Potential Value Chains Procure ICT 300 NCB NO Post 10 Aug 23 15 Sept 29 Sept 23 2 Oct 23 17 Nov 23 CAF/WB/GO/ equipment 23 37 and furniture for Horticulture Incubation Hub COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT CAF/WB/GO/ ICT 100 RfQ NO Post 10 Oct 23 15 Nov 23 29 Nov 23 2 Dec 23 17 Dec 23 38 Equipment and furniture for PMU CAF/WB/GO/ Procure 150 NCB NO Post 10 Jun 23 15 July 23 2 Aug 23 2 Aug 23 15 Sept 23 39 vehicles for PMU and Vehicle 64 | P a g e PROCUREMENT PLAN FOR SELECTION OF WORKS Sub-Component 2.3 - Expanding SME Participation in high Potential Value Chain CAF/WB/WS/ Refurbishme 250 NCB NO Post 10 Aug 23 15 Sept 2 Oct 23 2 Oct 23 17 Nov 23 40 nt of the 23 Horticulture Incubation Hub COMPONENT 3: PROJECT MANAGEMENT IMPLEMENTATION SUPPORT CAF/WB/WS/ Partitioning 50 RfQ NO Post 10 July 23 15 Aug 23 2 Aug 23 2 Aug 23 17 Aug 23 41 of New PMU office space PROCURMENT PLAN FOR CONSULTING SERVICES Expected Expected Expect Expected Expected assignment contract Contract Estimat Procurem Prior Review ed Technical Assignme commence completio Ref. No. Description ed Cost ent Shortlisti by REoI Proposal nt award ment date n date (US$’00 Method ng Financi (SPN s date 0) yes/no) ng date) Opening Agency date (Prior / Post) COMPONENT 1: ENHANCING G2B DIGITAL SERVICES AND STRENGTHENING PRIVATE SECTOR RESILIENCE ($20.25 MILLION) Sub-Component 1.1 - Enhancing Government to Business Digital Services ($520 000.00) CAF/WB/CS/0 Upgrade of 800 Direct NO Prior - 1 Nov 22 Nov 29 Nov 2022 31 May 1 the business 2022 2022 2023 Registration and Licensing system at OBFC 65 | P a g e CAF/WB/CS/0 Upgrade of 1 000 Direct NO Prior - 1 Nov 22 Nov 29 Nov 2022 31 May 2 the LRA 2022 022 2023 customs system, based on UNCTAD`s ASYCUDA World System CAF/WB/CS/0 Upgrade of 1 000 Direct NO Prior - 1 Nov 22 Nov 29 Nov 2022 31 May 3 the LAA land 2022 022 2023 registry system CAF/WB/CS/0 Design and 1 600 QCBS Yes Prior 9 Jan 2023 6 Feb 23 27 Feb 28 Feb 23 31 August 4 development 2023 2023 of G2B interoperabil ity Sub-Component 1.2- Improving Access to Financial Services CAF/WB/CS/0 Upgrade of 200 Direct NO Post - 1 Nov 22 Nov 22 Nov 2022 31 May 5 the credit 2022 2022 2023 infrastructure system that facilitates access to business financing CAF/WB/CS/0 Development 600 QCBS Yes Prior 9 Jan 2023 6 Feb 27 Feb 28 Feb 2023 31 Aug 6 of credit 2023 2023 2023 scoring system to 66 | P a g e enhance the utility of credit reporting CAF/WB/CS/0 Upgrade of 200 Direct - Post 1 Nov 22 Nov 22 Nov 29 Nov 2022 31 May 7 LERIMA 2022 2022 2022 2023 movable assets and integration of data from motor vehicle and company registries CAF/WB/CS/0 Capacity 50 IC Yes Post 9 Jan 23 6 Feb 23 27 Feb 23 28 Feb 23 31 Aug 8 Building of 2023 financial institutions and MSME`s to utilise asset-based lending CAF/WB/CS/0 TA to Post 150 CQS Yes Post 9 Jan 23 6 Feb 23 27 Feb 23 28 Feb 23 31 Aug 9 Bank for 2023 development of business case for agricultural value chain finance, including market assessment 67 | P a g e and financing methodology CAF/WB/CS/1 Design and 200 CQS Yes Post 23 Jan 20 Feb 13 March 20 March 29 Sept 0 implementati 2023 2023 2023 2023 2023 on of a management information system (MIS) to support value-chain financing CAF/WB/CS/1 Review and 50 IC Yes Post 23 Jan 20 Feb 13 March 20 March 29 Sept 1 improve 2023 2023 2023 2023 2023 governance, institutional and operational features of the L-PCG CAF/WB/CS/1 Develop a 150 CQS Yes Post 23 Jan 20 Feb 13 March 20 March 20 March 2 business 2023 2023 2023 2023 2023 case and financial model for portfolio guarantees CAF/WB/CS/1 Design and 2000 QCBS Yes Prior 23 Jan 20 Feb 13 March 20 March 20 March 3 implement 2023 2023 2023 2023 2023 the portfolio guarantee scheme including development of supporting documentati 68 | P a g e on and systems CAF/WB/CS/1 Capacity 100 CQS Yes Post 23 Jan 20 Feb 13 March 20 March 20 March 4 Building 2023 2023 2023 2023 2023 Sub-Component 1.3: Strengthening the Resilience of MSMEs to Climatic Shocks CAF/WB/CS/1 TA on 750 QCBS Yes Prior 23 Jan 20 Feb 13 Mar 20 Mar 29 Sept 5 disaster risk 2023 2023 2023 2023 financing including drafting of National Disaster Risk Finance Policy for MoF CAF/WB/CS/1 Design and 300 QCBS Yes Post 23 Jan 20 Feb 13 Mar 20 Mar 2023 29 Sept 6 development 2023 2023 2023 2023 of a database for informal MSMEs and integrate the database into the existing business registry CAF/WB/CS/1 TA on design 150 CQS Yes Post 23 Jan 20 Feb 13 Mar 20 Mar 2023 29 Sept 7 and 2023 2023 2023 2023 procurement of sovereign insurance backstop and co- 69 | P a g e financing of insurance premiums CAF/WB/CS/1 Draft 75 CQS Yes Post 23 Jan 20 Feb 13 Mar 20 Mar 29 Sept 8 regulations 2023 2023 2023 2023 to govern the operational activities of the existing MoF Contingency Fund Sub-Component 2.1- Establishing an Entrepreneurship Hub and Seed Financing Facility CAF/WB/CS/1 Procure a 500 QCBS Yes Prior 9 Jan 3 Feb 27 Feb 28 Feb 2023 31 Aug 23 9 private 2023 2023 2023 Sector operator to support establishmen t of a sustainable entrepreneur ship Hub within the Tourism Information centre CAF/WB/CS/2 Design and 150 CQS Yes Post 23 Jan 20 Feb 13 Mar 20 Mar 29 Sept 0 development 2023 2023 2023 2023 of an incubation support program 70 | P a g e CAF/WB/CS/2 Facilitate the 50 IC Yes Post 23 Jan 20 Feb 13 Mar 20 Mar 29 Sept 1 integration of 2023 2023 2023 2023 the Lesotho Start-up Community within a wider regional Entrepreneur ship ecosystem CAF/WB/CS/2 Procure a 250 CQS Yes Post 9 Jan 3 Feb 27 Feb 28 Feb 2023 31 Aug 23 2 private 2023 2023 2023 operator to establish and manage a seed financing facility and an associated acceleration program Procure a 300 QCBS Yes Post 9 Jan 2023 6 Feb 27 Feb 28 Feb 2023 31 May CAF/WB/CS/2 private 2023 2023 2023 3 sector service provider to augment the delivery capacity of LEAP PMU Sub-Component 2.3-Expanding SME Participation in High Potential Value Chains 71 | P a g e CAF/WB/CS/2 TA to set a 350 CQBS Yes Post 10 Oct 23 15 Nov 23 29 Nov 23 2 Dec 23 17 Dec 23 4 Horticulture Incubation Hub 9. Contract Management Plan (CMP) As the project at hand (CAFI) doesn’t involve any high value and complex contract, the Contract Management Plan (CMP) being outlined below may not need to be applied fully. However, the basic ones that would help the CMU manage its contracts (Works, Goods, Non-Consultancy Services or Consultancy services) with better efficiency to achieve its intended objectives may be adopted. The primary objective of any CMP is achievement of designed quality, agreed delivery timelines and perform within the contract ceiling amount. Assuring sustainability objectives in terms of environmental, social, and economic compliance are also sustainability dimension to be achieved through appropriate and proportional CMP. The Key contract management tools are all around establishing clear communication lines and having defined roles and responsibilities in the contract implementations. Each contractual parties defined accountability and Decision-making process must be communicated to the other party. The below templates may be used as found fit to each contract context. Sample Contract Management Plan 1.CONTACTS, ROLES AND RESPONSIBILITIES Roles and Organization Name and Title Contact Information (email, tel, address) Responsibilities PE Contract Manager Contractor Contractor’s representative: Consultant Engineer 72 | P a g e 2.COMMUNICATION AND REPORTING PROCEDURE Communication Procedures Communication Objective Format Frequency Audience Owner Type Contractual Notices Descriptions Objective Contract Frequency/ From to Reference Timing Contractor’s documents Descriptions Objective Contract Reference 73 | P a g e Reporting Requirement and Procedure No. Contract Ref. Due date/ Recipients Responsibilities Required Action Clause frequency [Progress [Monthly] Report] [ESHS Progress [Monthly] reports] [ESHS [immediately after immediate occurrence of event reports] Test results Issues Escalation Procedure Nature of Level of Responsible Response Type of issue Issue review body time Low or Routine Medium High Critical 3.KEY CONTRACTUAL PROVISIONS 74 | P a g e No. Description Contract Responsible Remark Risks reference 1. Care and Procuring 2 copies issued Supply of Entity to contractor Documents 2. Delayed Procuring Time extension Drawings or Entity cost compensation Instructions 3. Right of Access Procuring Give right of to the Site Entity access within time stated in data sheet. 4. 4.CONTRACTUAL MILESTONES AND DELIVERABLES Contract Start End Activity / Milestone Responsible Remark Reference date date Submit work Contractor schedule Foundation work for Contractor Critical path section… Complete structure Contractor for … Pilot testing for … 5.KEY PERFORMANCE INDICATORS (to MEASURE PERFORMANCE AND OUTCOMES) No. Deliverable KPI Performance Test Verification Remark target 1. 2. 3. 75 | P a g e 6.UNDERPERFORMANCE/DEFAULT CONTRACTUAL ACTIONS No. Description of Responsible Applicable Actions Remark underperformance contractual to be provision/s taken 1. 2. 3. 7.CHANGE MANAGEMENT PROCESS No. Change Type of Responsible Required Review/ Contract Status initiated change Action Approval Amendment by Process Requirement 1. Procuring Change in Procuring Inform Entity authority of Entity Contractor the of any Engineer change 2. Procuring Change in Engineer Entity scope of work 3. 8.INSURANCE Contract Amount / Information Required Required Expiry No Type of Insurance Ref. Limit of Date date liability 1. 2. 3. 9.GUARANTEES AND SECURITIES 76 | P a g e Type of Contrac Amount / Expir Information Required Require No Guarantee / t Ref. Limit of y d Date Security liability date 1. [Advance Payment Guarantee] 2. [Performance Security] 3. [ESHS Performance Security] 4. [Retention Guarantee] 77 | P a g e 10.PAYMENT PLAN /PROCEDURES N Type of Whe Documents Required Process Verification Approvals o Payment n/ time process . freq uenc y 1 Advance Once Advance payment . payment Guarantee 2 Interim Ever Interim payment . payments y certificates, timesheets, mont proof of incurred h expenditure, shipping documents etc. 3 Interest Dela . payments yed pay ment s 4 Price - . adjustme nt 5 Claims/ As Contractors . Compens need ation ed 6 Final . Payment 11.RECORDS MANAGMENT No. Type of Record Owner Responsible Action Remark required 1. [Contract documents and any amendments/] 78 | P a g e No. Type of Record Owner Responsible Action Remark required 2. Insurance details 3. [change orders] 4. [notices] 5. [Payment Documents, including documents on application of price adjustment if any] 6. Minutes of contract related meetings 7. [Progress Reports] 8. [immediate Reports on ESHS, if applicable] 9. [Test Results] 10. [Guarantees, warranty/defect liability and Securities] 11. Documents related to any suspension or termination 12.KEY STAKEHOLDERS ENGAGEMENT PLAN No. Stakeholder Format Frequency Remark 1. 2. 3. 13.CONTRACT CLOSURE PROCEDURES No. Activity Responsible Remark 1. 2. 3. 14.PRICE ADJUSTMENT PROCEDURES 79 | P a g e No. Activity Responsible Remark 1. e.g., verification of indices 2. 3. 15.INTERFACE MANAGEMENT No. Activity Responsible Remark 1. 2. 3. 80 | P a g e PROCUREMENT Lesotho : Lesotho Competitiveness and Financial Inclusion Project PLAN General Information Country: Lesotho 2022-10-06 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175783 GPN Date: Project Name: Lesotho Competitiveness and Financial Inclusion Project Loan / Credit No: IDA / 71690 Ministry of Trade and Industry Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota LS-MTI-369383-CW-RFQ / Re Scaling Support for Entrepre Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-2 furbishment of Horticulture I IDA / 71690 Post Limited 130,000.00 0.00 2023-08-05 2023-09-30 neurship and MSMEs tions nvelope s (Emergency) SP lementation 8 ncubation Hub D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-334917-GO-RFQ / Su Project Management and Im Request for Quota Single Stage - One E pply and Delivery of Three (3 IDA / 71690 Post Limited 20,000.00 0.00 Canceled 2023-01-11 2023-01-04 2023-03-08 2023-09-04 plementation Support tions nvelope ) colour printers for Project M anagement Unit LS-MTI-347213-GO-RFQ / Su Project Management and Im Request for Quota Single Stage - One E pply and delivery of 3 colour IDA / 71690 Post Limited 11,000.00 0.00 Canceled 2023-03-08 2023-05-03 2023-10-30 plementation Support tions nvelope printers for the project mana gement unit NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-344493-NC-DIR / Eng agement of Comnet (PTY)Ltd Project Management and Im IDA / 71690 Post Direct Selection Direct - National 13,000.00 0.00 Signed 2023-02-21 2023-02-01 2023-02-26 2023-02-01 2023-04-02 2023-09-29 for provision of ICT equipmen plementation Support t maintenance and repair LS-MTI-344436-NC-RFQ / Pro vision of Office Space for Ent Scaling Support for Entrepre Single Stage - One E IDA / 71690 Post Request for Bids Limited 204,564.00 0.00 Canceled 2023-03-07 2023-03-12 2023-04-23 2023-05-23 2023-06-27 2023-12-24 repreneurship Hub and Seed neurship and MSMEs nvelope Financing Facility for 3 years LS-MTI-353680-NC-RFQ / Pro vision of office space for the Scaling Support for Entrepre Request for Quota Single Stage - One E IDA / 71690 Post Limited 137,000.00 0.00 Signed 2023-04-03 2023-02-06 2023-05-29 2023-11-25 Entrepreneurship Hub and Se neurship and MSMEs tions nvelope ed Financing Facility for 24 M onths LS-MTI-355099-NC-DIR / Pro vision of Lesotho National Sin Enhancing Financial Inclusio Direct - Internation IDA / 71690 Post Direct Selection 83,000.00 0.00 Signed 2023-04-06 2023-04-11 2023-04-21 2023-04-11 2023-06-02 2023-11-29 gle Window (LNSW) Cloud Ho n and Resilience of MSMEs al sting Services for 12 Months CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-326389-CS-CQS / Eng Project Management and Im Consultant Qualifi Under Implement agement of a Communicatio IDA / 71690 Post Open - National 30,000.00 0.00 2022-11-14 2022-11-01 2022-12-05 2022-11-23 2023-01-18 2023-03-01 2023-02-17 2023-03-24 2023-09-20 plementation Support cation Selection ation ns Firm to support CAFI LS-MTI-327844-CS-CQS / Des Scaling Support for Entrepre Consultant Qualifi Under Implement IDA / 71690 Post Open - National 50,000.00 0.00 2022-11-22 2023-01-03 2022-12-13 2023-01-20 2023-01-26 2023-03-01 2023-02-25 2023-04-01 2023-09-28 ign and Development of LEAP neurship and MSMEs cation Selection ation Website LS-MTI-327989-CS-CQS / De Enhancing Financial Inclusio Consultant Qualifi Open - Internationa velopment of New Financial P IDA / 71690 Post 80,000.00 0.00 Canceled 2022-11-23 2022-12-14 2023-01-27 2023-02-26 2023-04-02 2023-09-29 n and Resilience of MSMEs cation Selection l roducts for Post Bank LS-MTI-327991-CS-CQS / Str Enhancing Financial Inclusio Consultant Qualifi Open - Internationa engthening the Credit Infrast IDA / 71690 Post 100,000.00 0.00 Canceled 2022-11-23 2022-12-01 2022-12-14 2023-01-12 2023-01-27 2023-02-26 2023-04-02 2023-09-29 n and Resilience of MSMEs cation Selection l ructure System for Central B ank LS-MTI-327996-CS-CQS / Eng Scaling Support for Entrepre Consultant Qualifi agement of Technical Adviso IDA / 71690 Post Limited 100,000.00 0.00 Canceled 2022-11-30 2022-12-01 2022-12-14 2023-01-13 2023-02-17 2023-08-16 neurship and MSMEs cation Selection r for MTI/BDT re-organization INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MTI-317459-CS-CDS / Pro vision of Consultancy service Scaling Support for Entrepre Direct - Internation Under Implement s by ILO "Lesotho Textiles an IDA / 71690 Prior Direct Selection 4,300,000.00 0.00 2022-09-23 2022-11-08 2022-10-03 2022-12-07 2023-06-05 neurship and MSMEs al ation d clothing Global Value Chain Technical Assistance Progra m LS-MTI-319844-CS-INDV / Co Scaling Support for Entrepre Individual Consult Open - Internationa nsultancy for Entrepreneursh IDA / 71690 Post 240,000.00 0.00 Signed 2022-10-06 2022-10-12 2022-11-24 2023-02-01 2022-12-15 2023-01-31 2023-01-19 2023-07-18 neurship and MSMEs ant Selection l ip Hub Manager for 24 month s Page 1 LS-MTI-319846-CS-CDS / Eng Project Management and Im agement of a Project Manage IDA / 71690 Post Direct Selection Direct - National 698,489.63 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support r for the CAFI Project for a Pe riod of 6 years LS-MTI-319870-CS-CDS / Eng Project Management and Im agement of the Finance Man IDA / 71690 Post Direct Selection Direct - National 396,742.55 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support ager for 6 years LS-MTI-319914-CS-CDS / Eng Project Management and Im agement of the Project Accou IDA / 71690 Post Direct Selection Direct - National 194,535.04 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support ntant for 6 years LS-MTI-319862-CS-CDS / Eng Project Management and Im agement of the Deputy Proje IDA / 71690 Post Direct Selection Direct - National 457,658.37 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support ct Manager for 6 years LS-MTI-319940-CS-CDS / Eng Project Management and Im agement of the Procurement IDA / 71690 Post Direct Selection Direct - National 32,982.39 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support Officer for 12 Months LS-MTI-319942-CS-CDS / Eng Project Management and Im agement of the Receptionist/ IDA / 71690 Post Direct Selection Direct - National 21,433.28 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support IT Support for 12 Months LS-MTI-319881-CS-CDS / Eng Project Management and Im agement of the Entrepreneur IDA / 71690 Post Direct Selection Direct - National 320,662.11 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support ship Manager for the period o f 6 years LS-MTI-319921-CS-CDS / Eng Project Management and Im agement of the Office Assista IDA / 71690 Post Direct Selection Direct - National 37,410.61 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support nt for 6 years LS-MTI-319951-CS-CDS / Eng Project Management and Im agement of the Project Accou IDA / 71690 Post Direct Selection Direct - National 32,982.39 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support ntant for 12 Months LS-MTI-319937-CS-CDS / Eng Project Management and Im agement of the Administrativ IDA / 71690 Post Direct Selection Direct - National 33,087.41 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support e Secretary for 12 Months LS-MTI-319890-CS-CDS / Eng Project Management and Im agement of the Procurement IDA / 71690 Post Direct Selection Direct - National 48,862.00 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support Manager for 1 year LS-MTI-319947-CS-CDS / Eng Project Management and Im agement of the LEAP Officer f IDA / 71690 Post Direct Selection Direct - National 30,539.25 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support or 12 Months LS-MTI-319948-CS-CDS / Eng Project Management and Im agement of the Project Drive IDA / 71690 Post Direct Selection Direct - National 53,443.69 0.00 Signed 2022-10-17 2022-11-01 2022-10-27 2022-11-01 2022-12-31 2023-06-29 plementation Support r for 6 years LS-MTI-326558-CS-INDV / En Project Management and Im Individual Consult Under Implement gagement of the LEAP Officer IDA / 71690 Post Open - National 30,539.25 0.00 2022-11-15 2022-11-22 2023-01-03 2023-01-24 2023-02-28 2023-08-27 plementation Support ant Selection ation 2 for the Project for 1 year LS-MTI-326560-CS-INDV / En gagement of the Monitoring Project Management and Im Individual Consult IDA / 71690 Post Open - National 55,000.00 0.00 Canceled 2022-11-15 2022-11-22 2023-01-03 2023-01-24 2023-02-28 2023-08-27 and Evaluation Specialist for plementation Support ant Selection CAFI Project for 1 year LS-MTI-326562-CS-INDV / En gagement of the Social and E Project Management and Im Individual Consult IDA / 71690 Post Open - National 55,000.00 0.00 Signed 2022-11-15 2022-11-22 2023-01-03 2023-01-13 2023-01-24 2023-01-31 2023-02-28 2023-08-27 nvironmental Safeguards Spe plementation Support ant Selection cialist for CAFI Project for 1 y ear LS-MTI-326566-CS-INDV / En Project Management and Im Individual Consult gagement of Deputy Project IDA / 71690 Post Open - National 76,000.00 0.00 Signed 2022-11-15 2022-11-22 2023-01-03 2023-01-27 2023-01-24 2023-01-23 2023-02-28 2023-08-27 plementation Support ant Selection Manager Operations for CAFI Project for 1 year LS-MTI-326568-CS-INDV / En Project Management and Im Individual Consult gagement of the Executive A IDA / 71690 Post Open - National 33,087.41 0.00 Canceled 2022-11-15 2022-11-22 2023-01-03 2023-01-31 2023-01-24 2023-02-28 2023-08-27 plementation Support ant Selection ssistant for CAFI Project for 1 year LS-MTI-326594-CS-INDV / En Enhancing Financial Inclusio Individual Consult gagement of MSME Resilienc IDA / 71690 Post Open - National 52,000.00 0.00 Canceled 2022-11-15 2022-11-22 2023-01-03 2023-03-10 2023-01-24 2023-03-15 2023-02-28 2023-08-27 n and Resilience of MSMEs ant Selection e Coordinator for 1 year LS-MTI-327692-CS-INDV / En Enhancing Financial Inclusio Individual Consult Open - Internationa gagement of Trade Facilitatio IDA / 71690 Post 100,000.00 0.00 Signed 2022-11-22 2023-01-03 2023-01-10 2023-01-18 2023-01-31 2023-01-23 2023-03-07 2023-09-03 n and Resilience of MSMEs ant Selection l n Expert for 18 Months LS-MTI-330598-CS-INDV / En Scaling Support for Entrepre Individual Consult gagement of the Horticulture IDA / 71690 Post Open - National 52,000.00 0.00 Signed 2022-12-07 2022-12-01 2023-01-25 2023-03-16 2023-02-15 2023-03-15 2023-03-22 2023-09-18 neurship and MSMEs ant Selection Coordinator for a period of 1 2 Months LS-MTI-330602-CS-INDV / En Scaling Support for Entrepre Individual Consult Under Implement gagement of Incubation Hub IDA / 71690 Post Open - National 52,000.00 0.00 2022-12-07 2022-12-01 2023-01-25 2023-02-15 2023-03-22 2023-09-18 neurship and MSMEs ant Selection ation Manager for 12 Months LS-MTI-331150-CS-CDS / Eng agement of Horticulture Infra Scaling Support for Entrepre IDA / 71690 Post Direct Selection Direct - National 7,000.00 0.00 Signed 2022-12-12 2022-12-01 2022-12-22 2023-01-02 2023-02-25 2023-08-24 structure Technician 2 for a p neurship and MSMEs eriod of 12 Months. LS-MTI-331153-CS-CDS / Eng Scaling Support for Entrepre agement of Horticulture Infra IDA / 71690 Post Direct Selection Direct - National 7,000.00 0.00 Signed 2022-12-12 2022-12-01 2022-12-22 2023-01-02 2023-02-25 2023-08-24 neurship and MSMEs structure Technician 1 for 12 Months LS-MTI-331168-CS-CDS / Eng Scaling Support for Entrepre agement of Horticulture Tech IDA / 71690 Post Direct Selection Direct - National 32,000.00 0.00 Signed 2022-12-12 2023-01-03 2022-12-22 2023-01-02 2023-02-25 2023-08-24 neurship and MSMEs nical Field Manager for 12 Mo nths LS-MTI-331185-CS-CDS / Eng Scaling Support for Entrepre agement of the Horticulture IDA / 71690 Post Direct Selection Direct - National 50,000.00 0.00 Canceled 2022-12-12 2022-12-01 2022-12-22 2023-02-25 2023-08-24 neurship and MSMEs Field Technical Advisor for 12 Months Page 2 LS-MTI-334909-CS-INDV / En Scaling Support for Entrepre Individual Consult gagement of Horticulture Tec IDA / 71690 Post Open - National 28,000.00 0.00 Signed 2023-01-12 2023-01-09 2023-03-02 2023-03-01 2023-03-23 2023-03-15 2023-04-27 2023-10-24 neurship and MSMEs ant Selection hnical Advisor for 12 Months LS-MTI-344470-CS-CDS / Inst Project Management and Im Direct - Internation allation of Financial Manage IDA / 71690 Post Direct Selection 40,000.00 0.00 Signed 2023-02-21 2023-02-01 2023-03-03 2023-01-31 2023-05-07 2023-11-03 plementation Support al ment System, TOMPRO LS-MTI-356459-CS-INDV / En Project Management and Im Individual Consult Under Implement gagement of MSME Resilienc IDA / 71690 Post Open - National 45,000.00 0.00 2023-04-17 2023-04-12 2023-06-05 2023-06-26 2023-07-31 2024-01-27 plementation Support ant Selection ation e Coordinator for 12 months LS-MTI-360353-CS-CDS / Eng Scaling Support for Entrepre Direct - Internation agement of Textile and Appa IDA / 71690 Post Direct Selection 150,000.00 0.00 Signed 2023-05-08 2023-05-05 2023-05-18 2023-05-09 2023-07-22 2024-01-18 neurship and MSMEs al rel Senior Advisor for 24 Mon ths LS-MTI-364387-CS-INDV / En gagement of Senior Expert to Enhancing Financial Inclusio Individual Consult Open - Internationa Under Implement IDA / 71690 Post 100,000.00 0.00 2023-06-06 2023-06-09 2023-07-25 2023-08-15 2023-09-19 2024-03-17 review and reform Credit Gu n and Resilience of MSMEs ant Selection l ation arantee Scheme for 45 days LS-MTI-366101-CS-INDV / En gagement of Deputy Progra Scaling Support for Entrepre Individual Consult Under Implement mme Manager-Entrepreneurs IDA / 71690 Post Open - National 94,000.00 0.00 2023-06-30 2023-06-09 2023-08-18 2023-09-08 2023-10-13 2024-04-10 neurship and MSMEs ant Selection ation hip Hub and Seed Financing Facility for a period of 24 Mo nths LS-MTI-366106-CS-INDV / En gagement of the Grants Adm Scaling Support for Entrepre Individual Consult Under Implement inistrator for Entrepreneurshi IDA / 71690 Post Open - National 40,000.00 0.00 2023-06-30 2023-06-09 2023-08-18 2023-09-08 2023-10-13 2024-04-10 neurship and MSMEs ant Selection ation p Hub and Seed Financing Fa cility for a period of 24 Month s LS-MTI-366112-CS-INDV / En gagement of the Executive A Scaling Support for Entrepre Individual Consult Under Implement ssistant for Entrepreneurship IDA / 71690 Post Open - National 40,000.00 0.00 2023-06-30 2023-06-09 2023-08-18 2023-09-08 2023-10-13 2024-04-10 neurship and MSMEs ant Selection ation Hub and Seed Financing Facil ity for a period of 24 Months LS-MTI-366363-CS-INDV / En gagement of the Financial Se Enhancing Financial Inclusio Individual Consult Open - Internationa Under Implement IDA / 71690 Post 45,000.00 0.00 2023-06-30 2023-06-13 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ctor Specialist for Strengthen n and Resilience of MSMEs ant Selection l ation ing the Credit Infrastructure System for 12 Weeks LS-MTI-367031-CS-INDV / En gagement of a legal Consulta Enhancing Financial Inclusio Individual Consult Under Implement nt for Central Bank to suppor IDA / 71690 Post Open - National 40,000.00 0.00 2023-06-30 2023-06-15 2023-08-18 2023-09-08 2023-10-13 2024-04-10 n and Resilience of MSMEs ant Selection ation t the strengthening of the Cr edit Infrastructure System for 12 weeks Page 3 18-MONTH PROCUREMENT PLAN Project information: Nigeria Rural Access And Agricultural Marketing Project (RAAMP) - P163353 Project Implementation Agencies: Federal Ministry of Agriculture and Rural Development and State Project Implementation Units (SPIUs) Date of the Procurement Plan: September 18, 2019 Period covered by this Procurement Plan: February 2019 to July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selecti Market on Evaluation Approa Review Metho Options Expected ch Prequal- Domestic Expected by Estimat d (Most date of Sr. Contract (Open- ification Preferenc date of Bank ed Cost (RFP, Advantageou bid/ No Description Nation (Yes/ e Contract (Prior/ (US$) RFB, s Bid, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated Criteria opening Limited DS etc.) etc.) etc.) Procurement of Air Conditioners 2 Limited Lowest March. 1 Post 24,600 RFQ No No Feb. 2020 Horse power Evaluated Cost 2020 (Split Unit) (Goods) Procurement of Steel File cabinets, Lowest March. 2 Spiral Binding Post 12,600 Limited RFQ Evaluated Cost No No Feb. 2020 2020 Machines and Consumables (Goods) Procurement of External hard disk + software packages Lowest March. 3 (licensed MS Post 12,300 Limited RFQ Evaluated Cost No No 2020 April. 2020 Office, Autocads, Antivirus, Converter etc) (Goods) Procurement of Laptops and Lowest March. 4 Post 100,000 Limited RFQ No No May. 2020 Tablets Evaluated Cost 2020 (Goods) Procurement Lowest March. 5 Post 22,400 Limited RFQ No No April. 2020 of Evaluated Cost 2020 Photocopying Machines (Goods) Medium Sized Lowest March. 6 Refrigerators Post 10,800 Limited RFQ Evaluated Cost No No 2020 April. 2020 (Goods) Procurement of Safety Equipment (Boots, Lowest 7 Post 39,000 Limited RFQ No No June. 2020 July, 2020 Helmets, Evaluated Cost Reflective Jackets etc.) (Goods) Construction Measuring Manual Wheel Lowest August. 8 Post 6,500 Limited RFQ No No July 2020 (Surveyor’s Evaluated Cost 2020 Wheel) (Goods) Roads Maintenance Equipment for Community based road maintenance (30 Nos tipping tricycles and other Open- 1,235,0 Lowest 9 equipment Post Nationa RFB No No Sept. 2020 Dec. 2020 00 Evaluated Cost such roads l signs and; cutlasses, wheelbarrows, hand rammer, digger, helmet, watering cans, reflective jacket, long shovel, nose cover, boots etc) (Goods) Procurement of Office Equipment, Printers, Open- Digital Lowest August. 10 Post 420,000 Nationa RFB No No June. 2020 Cameras & Evaluated Cost 2020 l Sundry Communicatio n devices (Goods) Purchase of Open- Project 2,940,0 Lowest March. 11 Prior Nationa RFB No No May. 2020 Vehicles 00 Evaluated Cost 2020 l (Goods) Server, Network System and other Open- Lowest equipment & Post 150,000 Nationa RFB Evaluated Cost No No Feb. 2020 May. 2020 accessories for l NiRTIMS and CosMos (Goods) Design and Construction of 200km of Rural Roads Open- 134,000 Rated Criteria (13 Prior Interna RFP No No Jun. 2020 Dec. 2020 ,000.00 and Cost Contracts of tional US$10.3 Million each) (Works) Construction/E stablishment Open – of Agro- 2,000,0 Lowest March. Post Nationa RFB No No July. 2021 Logistics 00 Evaluated Cost 2021 l centers/hubs at strategic locations (Multiple contracts) (Works) Construction /Rehabilitation of 10 Nos. Rural Bridges Open- 8,000,0 Lowest March. & Large Post Nationa RFB No No July. 2022 00 Evaluated Cost 2021 culverts (US$ l 0.6 M each Package) (Works) Local Community Group (LCG) and micro- enterprises maintenance Open- 14,000, Lowest of pilot roads Post Nationa RFB No No April. 2020 June.2020 000 Evaluated Cost (Multiple l Contracts in 13 States - US$ 0.002/year) (Works) II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Offshore & Onshore training and Workshops for Open- March. 1 the 13 states (Multiple Post 5,200,000 CQS No May. 2020 National 2020 contracts not to exceed US$ 0.1 M) (Consultancy) Consultancy Services for Detailed assessment, preliminary engineering design, ESIA, Procurement Support for Rural roads and Bridges; Road and 25,390,00 Open- 2 Bridge Supervision Prior QCBS Yes June. 2020 Nov. 2020 0 International Consultancy; Assessment of project security risk and mitigation (Multiple contracts spread in different locations) (Consultancy) Consultancy Services for design, procurement and supervision for Agro- Open- 3 logistics centers (Multiple Post 6,500,000 QCBS Yes Sep. 2020 Dec. 2020 International contracts spread in different locations) (Consultancy) Consultancy Services for the establishment of state Open- March. August. 4 road fund, and Post 5,665,000 QCBS Yes National 2020 2020 establishment of state rural access roads administration (Multiple contracts at 13 states) (Consultancy) Consultancy services on the development and operationalization of the Nigeria Rural Transport Infrastructure Management System (NiRTIMS) for sustainable road asset; Planning and Open- 5 Post 5,860,000 QCBS Yes Feb. 2020 July. 2020 implementation of the National routine maintenance system, spot improvement, periodic maintenance for rural roads. (Multiple contracts at 13 states) (Consultancy) Technical assistance consultancy services for the provision of technical advice (TA) to enhance the performance of agro- logistics centers (to ensure effective utilization of the facilities at the agro- Open- National March. 6 logistics centers); Post 4,975,000 QCBS Yes July. 2020 provision of TA and 2020 implements to farm level post-harvest agro-logistics activities and enhance the engagement of women and unemployed youth. (Multiple contracts at 13 states) (Consultancy) Consultancy services support for coordination of Open- 7 Post 2,442,000 CQS No Feb. 2020 April. 2020 project implementation at National Federal and State Levels (Multiple contracts at 13 states) (Consultancy) Consultancy services on Impact Evaluation, Baseline Data Collection, Comprehensive Technical Audit, Consultancy support for the development and Open- March. 8 operationalization of the Post 5,325,000 QCBS Yes July.2020 National 2020 smartphone-based construction site monitoring system (CoSMoS) (Multiple contracts at 13 states) (Consultancy) Consultancy support for the development and monitoring of Grievance Redress Mechanism and Gender-Based Violence; Development of road safety manual and training Open- 9 Post 1,843,000 CQS No April.2020 June. 2020 at the state level; National establishment/strengtheni ng the state traffic management agencies; road safety audit. (Multiple contracts at 13 states) (Consultancy) Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Rural Access and Agricultural Marketing Project PLAN General Information Country: Nigeria 2021-04-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163353 GPN Date: Project Name: Nigeria Rural Access and Agricultural Marketing Project Loan / Credit No: IDA / 65190 AKWA IBOM RAAMP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-AKWA IBOM RAAMP-230 Request for Bids - Component A. Improvement 755-CW-RFB / Construction o Single Stage - One E Small Works SPD Pending Imp 2024-04-1 IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 900,000.00 0.00 2022-09-28 2022-10-03 2022-11-14 2022-12-14 2023-01-18 f 100 meters Cross - Drainag nvelope (1 envelope proce lementation 2 Infrastructure e Structures (Culverts/Bridge ss) s) on Rural Roads Request for Bids - NG-AKWA IBOM RAAMP-280 Component A. Improvement Single Stage - One E Small Works SPD Under Imple 2023-06-3 436-CW-RFB / Upgrading/ Co IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 600,000.00 0.00 2022-07-04 2022-10-25 2022-07-25 2022-12-16 2022-07-27 2022-11-22 2022-08-26 2022-09-23 nvelope (1 envelope proce mentation 0 nstruction of 11km of priority Infrastructure ss) pilot Road NG-AKWA IBOM RAAMP-280 Request for Bids - Component A. Improvement 438-CW-RFB / Physical impro Single Stage - One E Small Works SPD Pending Imp 2024-06-2 IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 1,000,000.00 0.00 2022-09-19 2022-10-10 2022-10-12 2022-11-11 2022-12-09 vement of about 2 nos. Agro- nvelope (1 envelope proce lementation 6 Infrastructure logistics Centers (ALCs) ss) Request for Bids - NG-AKWA IBOM RAAMP-230 Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-01-0 747-CW-RFB / Spot Improve IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 5,000,000.00 0.00 2022-07-26 2022-08-16 2022-08-18 2022-09-08 2022-10-13 nvelope (1 envelope proce lementation 6 ment of about 225 km Rural ance Enhancement and Sect ss) Roads or Reform Request for Bids - NG-AKWA IBOM RAAMP-280 Component A. Improvement Single Stage - One E Small Works SPD Pending Imp 2024-06-1 431-CW-RFB / Rural Roads up IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 2,000,000.00 0.00 2022-09-29 2022-10-20 2022-10-22 2022-11-21 2022-12-19 nvelope (1 envelope proce lementation 1 grading of about 40km Infrastructure ss) Request for Bids - NG-AKWA IBOM RAAMP-230 Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-04-0 673-CW-RFB / Backlog Maint IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 2,500,000.00 0.00 2022-09-27 2022-10-02 2022-11-13 2022-12-13 2023-01-10 nvelope (1 envelope proce lementation 4 enance/Rehabilitation of 100 ance Enhancement and Sect ss) km Rural Roads or Reform GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 299-GO-RFQ / Purchase of off IDA / 65190 evelopment, Project Manage Post Limited 50,000.00 0.00 2022-06-07 2022-07-12 2022-08-11 tions nvelope ementation ice furniture and equipment ment and Risk Mitigation NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Under Imple 389-GO-RFQ / Purchase of 1 IDA / 65190 evelopment, Project Manage Post Limited 33,000.00 0.00 2022-05-23 2022-08-30 2022-06-27 2022-07-27 tions nvelope mentation no. 30 KVA Generators ment and Risk Mitigation NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 590-GO-RFQ / Purchase of pr IDA / 65190 evelopment, Project Manage Post Limited 50,000.00 0.00 2022-06-27 2022-08-01 2022-08-31 tions nvelope ementation omotional materials (Flip Cha ment and Risk Mitigation rt, Memo etc.) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 280-GO-RFQ / Purchase of 2n IDA / 65190 evelopment, Project Manage Post Limited 150,000.00 0.00 2022-06-13 2022-07-25 2022-08-24 tions nvelope ementation os. of operating project vehic ment and Risk Mitigation les NG-AKWA IBOM RAAMP-230 339-GO-RFQ / Purchase of 15 nos. laptops, 10nos, Desktop Component C. Institutional D Request for Quota Single Stage - One E Pending Impl s, 10nos Printers/Fax, 2Nos H IDA / 65190 evelopment, Project Manage Post Limited 80,000.00 0.00 2022-06-20 2022-07-25 2022-08-24 tions nvelope ementation eavy Duty Photocopiers 10No ment and Risk Mitigation s Scanners, 1 nos Projector, I nternet Installation, Air Condi tioners, and Consumables NG-AKWA IBOM RAAMP-230 409-GO-RFQ / Purchase of Sa feguard equipment (PPEs, fir Component C. Institutional D st aid kits, environmental mo Request for Quota Single Stage - One E Pending Impl IDA / 65190 evelopment, Project Manage Post Limited 80,000.00 0.00 2022-07-02 2022-08-13 2022-09-12 nitoring and tracking equipm tions nvelope ementation ment and Risk Mitigation ent including in-situ air qualit y kits, noise meter, PH meter , caution tapes, measuring ta pes, camera, GPS etc.) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 391-GO-RFQ / Purchase of da IDA / 65190 evelopment, Project Manage Post Limited 10,000.00 0.00 2022-04-08 2022-05-20 2022-07-04 tions nvelope ementation ta Collection Gadgets (6Nos) ment and Risk Mitigation AKS/RAAMP/RFQ/O1/23 / Pro Component C. Institutional D Request for Quota Single Stage - One E Pending Impl curement of office stationerie IDA / 65190 evelopment, Project Manage Post Limited 10,000.00 0.00 2023-07-17 2023-08-24 2023-09-07 tions nvelope ementation s and Consumables for AKS R ment and Risk Mitigation AAMP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 NG-AKWA IBOM RAAMP-280 293-CS-QCBS / Consultancy S Component A. Improvement ervices for Design and Super Quality And Cost- Open - Internationa Under Implement IDA / 65190 of Rural Access and Trading Post 430,000.00 0.00 2022-03-09 2022-06-09 2022-04-08 2022-08-17 2022-05-06 2022-10-06 2022-06-03 2022-11-17 2022-07-03 2022-12-15 2022-08-07 2022-09-11 2024-11-29 vision of 160 km Rural Road Based Selection l ation Infrastructure Upgrading (Design & Build; N on-Design & Build contracts) NG-AKWA IBOM RAAMP-230 440-CS-CQS / Consultancy se rvices for Design and Supervi Component B. Asset Manage sion of Backlog Maintenance, ment, Agro-logistics Perform Consultant Qualifi IDA / 65190 Post Open - National 365,000.00 0.00 Canceled 2021-05-10 2021-05-17 2021-06-23 2021-07-07 2021-08-04 2023-12-22 Spot Improvement, Performa ance Enhancement and Sect cation Selection nce Based Maintenance Cont or Reform ract (PBMC) and Cross-draina ge Structures (bridges/ culve rts) in Akwa Ibom State NG-AKWA IBOM RAAMP-280 Component A. Improvement 333-CS-CQS / Consultancy se Consultant Qualifi Under Implement IDA / 65190 of Rural Access and Trading Post Open - National 120,000.00 0.00 2022-03-20 2022-03-08 2022-04-10 2022-05-19 2022-05-08 2022-08-09 2022-06-07 2022-09-07 2022-07-12 2023-05-08 rvices for the Design review cation Selection ation Infrastructure and Supervision of 11 Km of priority Pilot road NG-AKWA IBOM RAAMP-280 337-CS-QCBS / Consultancy S Component A. Improvement Quality And Cost- Open - Internationa Under Implement ervices for Design and Super IDA / 65190 of Rural Access and Trading Post 395,000.00 0.00 2022-03-20 2022-03-09 2022-04-19 2022-12-24 2022-06-14 2023-02-03 2022-06-28 2022-07-19 2022-08-09 2022-09-06 2024-11-14 Based Selection l ation vision of physical improveme Infrastructure nt of 5 to 6 nos. Agro-logistic s Centers (ALCs) NG-AKWA IBOM RAAMP-230 412-CS-CQS / Consultancy Se Component A. Improvement rvices for Design and Supervi Consultant Qualifi IDA / 65190 of Rural Access and Trading Post Open - National 350,000.00 0.00 Canceled 2021-09-06 2021-09-13 2021-10-20 2021-11-03 2021-12-01 2024-06-18 sion of Rural Road Upgrading cation Selection Infrastructure (Design & Build) and Improve ment of Agro-Logistics Hubs ( ALHs) in Akwa Ibom State. NG-AKWA IBOM RAAMP-282 Component B. Asset Manage 705-CS-CQS / Consultancy Se ment, Agro-logistics Perform Consultant Qualifi Under Implement rvices for Design and Supervi IDA / 65190 Post Open - National 180,000.00 0.00 2022-03-20 2022-06-09 2022-04-10 2022-06-08 2022-05-15 2022-08-31 2022-05-29 2022-10-13 2022-06-26 2023-06-21 ance Enhancement and Sect cation Selection ation sion of Backlog maintenance/ or Reform Réhabilitation of roads (125K M) NG-AKWA IBOM RAAMP-282 708-CS-CQS / Consultancy Se Component B. Asset Manage rvices for Design and Supervi ment, Agro-logistics Perform Consultant Qualifi Under Implement IDA / 65190 Post Open - National 200,000.00 0.00 2022-03-28 2022-03-08 2022-04-18 2022-06-08 2022-05-23 2022-08-30 2022-06-06 2022-10-21 2022-07-04 2023-06-29 sion of Spot Improvement (3 ance Enhancement and Sect cation Selection ation 00KM) and construction of 50 or Reform linear meter Cross-drainage s tructures (bridges/culverts) NG-AKWA IBOM RAAMP-280 320-CS-CQS / Consultancy se rvices for Design and Supervi Component B. Asset Manage sion of Backlog Maintenance/ ment, Agro-logistics Perform Consultant Qualifi IDA / 65190 Post Open - National 212,000.00 0.00 Canceled 2022-03-01 2022-03-22 2022-04-19 2022-05-03 2022-05-31 2023-05-26 Rehabilitation (125km), Spot ance Enhancement and Sect cation Selection Improvement (300km), and c or Reform onstruction of 50 linear mete r Cross-drainage Structures ( bridges/culverts) AKS/RAAMP/ESMP/CQS/01/2 3 / Consultancy Services for preparation of ESMP for Rural Component C. Institutional D Consultant Qualifi Pending Impleme Roads (Upgrading of Rural Ro IDA / 65190 evelopment, Project Manage Post Limited 120,000.00 0.00 2023-07-12 2023-07-26 2023-08-16 2023-09-11 2024-09-10 cation Selection ntation ads, Spot Improvement, Cros ment and Risk Mitigation s-drainage structure, and Ba cklog Maintenance/Rehabilita tion) for AKS RAAMP AKS/RAAMP/RAP/CQS/02/23 / Consultancy Services for pre Component C. Institutional D paration of RAP for Rural Roa Consultant Qualifi Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 120,000.00 0.00 2023-07-12 2023-07-26 2023-08-16 2023-09-11 2024-09-10 ds (Upgrading of Rural Roads cation Selection ntation ment and Risk Mitigation , Spot Improvement, Cross-dr ainage structure, and Backlo g Maintenance/Rehabilitation ) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-AKWA IBOM RAAMP-280 Component C. Institutional D 394-CS-INDV / Consultancy S Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Signed 2022-03-07 2022-04-05 2022-03-28 2022-06-14 2022-04-04 2022-07-25 2022-04-18 2023-04-13 ervices for the engagement o ant Selection ment and Risk Mitigation f TA on Security Specialist NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult 466-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 40,000.00 0.00 Canceled 2022-06-08 2022-06-29 2022-07-13 2022-08-03 2023-08-03 ant Selection f Technical Assistant (Gender ment and Risk Mitigation Based Violent) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult 504-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-06-16 2022-07-07 2022-07-21 2022-08-11 2023-08-11 ant Selection f Technical Assistant (Social ment and Risk Mitigation Safeguard) NG-AKWA IBOM RAAMP-230 Component C. Institutional D 522-CS-INDV / Engagement o Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-06-23 2022-07-14 2022-07-28 2022-08-18 2023-08-18 f Technical Assistant (Environ ant Selection ment and Risk Mitigation mental Safeguard) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult 533-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-06-30 2022-07-21 2022-08-04 2022-08-25 2023-08-25 ant Selection f Technical Assistant (Procure ment and Risk Mitigation ment) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult Under Implement 538-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2022-07-08 2022-05-25 2022-07-29 2022-05-10 2022-08-12 2022-07-12 2022-09-02 2023-09-02 ant Selection ation f Technical Assistant (Infrastr ment and Risk Mitigation ucture) NG-AKWA IBOM RAAMP-280 406-CS-INDV / Consultancy S Component C. Institutional D Individual Consult Under Implement ervices for engagement of Te IDA / 65190 evelopment, Project Manage Post Open 25,000.00 0.00 2022-07-18 2021-06-25 2022-08-22 2021-08-13 2022-08-29 2021-08-16 2022-09-12 2023-09-12 ant Selection ation chnical Assistant (TA) for Dat ment and Risk Mitigation a Entry Specialist (DES) NG-AKWA IBOM RAAMP-280 398-CS-INDV / Consultancy S Component C. Institutional D Individual Consult Under Implement ervices for engagement of TA IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 2022-07-26 2021-06-25 2022-08-02 2021-07-16 2022-08-16 2022-09-06 2023-09-01 ant Selection ation for Geographic Information S ment and Risk Mitigation ystem (GIS) Specialist Page 2 NG-AKWA IBOM RAAMP-313 481-CS-CDS / CONSULTANCY SERVICE FOR UPDATING OF E NVIRONMENTAL AND SOCIAL Component C. Institutional D Under Implement MANAGEMENT PLAN (ESMP) F IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-12 2022-09-15 2022-09-26 2022-10-31 2023-04-29 ation OR 11KM OWOT UTA – NUNG ment and Risk Mitigation OKU EKERE – AFAHA UDOE E YOP – EDEOBOM UTUAT MAR KET JUNCTION ROAD IN NSIT IBOM & IBESIKPO ASUTAN IN AKWA STATE NG-AKWA IBOM RAAMP-313 511-CS-CDS / CONSULTANCY SERVICES FOR UPDATING OF RESETTLEMENT ACTION PLA Component C. Institutional D Under Implement N (RAP) FOR 11KM OWOT UT IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-19 2022-09-15 2022-10-03 2022-11-07 2023-05-06 ation A – NUNG OKU EKERE – AFAH ment and Risk Mitigation A UDOE EYOP – EDEOBOM UT UAT MARKET JUNCTION ROA D IN NSIT IBOM & IBESIKPO A SUTAN IN AKWA STATE NG-AKWA IBOM RAAMP-313 965-CS-CDS / CONSULTANCY SERVICE FOR THE PREPARATI ON OF ENVIRONMENTAL AND Component C. Institutional D Under Implement SOCIAL MANAGEMENT PLAN ( IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-21 2022-09-15 2022-10-05 2022-11-09 2023-05-08 ation ESMP) FOR 11.127KM NSIE – ment and Risk Mitigation UTINE – OTIEKE OFFI – URUTI NG AKS-RAAMP PILOT ROAD I N OKOBO LGA AS PART OF P RIORITY ROADS IN AKWA IBO M. NG-AKWA IBOM RAAMP-313 968-CS-CDS / CONSULTANCY SERVICES FOR THE PREPARA Component C. Institutional D TION OF RESETTLEMENT ACT Under Implement IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-26 2022-09-15 2022-10-10 2022-11-14 2023-05-13 ION PLAN (RAP) FOR 11.127K ation ment and Risk Mitigation M NSIE – UTINE – OTIEKE OFF I – URUTING AKS-RAAMP PILO T ROAD IN OKOBO LGA AS PA RT OF PRIORITY ROADS IN AK WA IBOM. NG-AKWA IBOM RAAMP-322 Component C. Institutional D Individual Consult Under Implement 098-CS-INDV / ENGAGEMENT IDA / 65190 evelopment, Project Manage Prior Limited 40,000.00 0.00 2022-10-31 2022-11-01 2022-11-14 2023-02-28 2022-11-28 2023-06-01 2022-12-12 2024-12-01 ant Selection ation OF PROCUREMENT SPECIALIS ment and Risk Mitigation T NG-AKWA IBOM RAAMP-350 642-CS-INDV / Consultancy S ervice for the Preparation of Environmental and Social Ma Component C. Institutional D Individual Consult Pending Impleme nagement Plan (ESMP) and R IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 2023-04-05 2023-04-19 2023-05-03 2023-05-24 2024-05-23 ant Selection ntation AP For 11.127km Nsie – Utine ment and Risk Mitigation – Otieke Offi – Uruting Aks-RA AMP Pilot Road in Okobo LGA s as Part of Priority Roads in Akwa Ibom State. NG-AKWA IBOM RAAMP-347 Component C. Institutional D Individual Consult 731-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2023-03-15 2023-04-18 2023-04-05 2023-04-19 2023-05-10 2024-05-09 ant Selection f Technical Assistant (Social ment and Risk Mitigation Safeguard) NG-AKWA IBOM RAAMP-347 Component C. Institutional D 741-CS-INDV / Engagement o Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2023-03-26 2023-03-20 2023-04-16 2023-04-30 2023-05-21 2024-05-20 f Technical Assistant (Environ ant Selection ment and Risk Mitigation mental Safeguard) NG-AKWA IBOM RAAMP-347 Component C. Institutional D 738-CS-INDV / Engagement o Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2023-03-20 2023-04-10 2023-04-24 2023-05-15 2024-05-14 f Technical Assistant (Environ ant Selection ment and Risk Mitigation mental Safeguard) AKS/RAAMP/ES/INDV/01/23 / Component C. Institutional D Consultancy Service for the E Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2023-08-01 2023-08-15 2023-08-29 2023-10-03 2024-03-01 ngagement of TA Environme ant Selection ntation ment and Risk Mitigation nt to support SPIU NG-AKWA IBOM RAAMP-350 636-CS-INDV / Consultancy S ervice for updating of Enviro nmental and Social Manage Component C. Institutional D Individual Consult Pending Impleme ment Plan (ESMP) and RAP fo IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 2023-03-27 2023-04-10 2023-04-24 2023-05-22 2024-05-21 ant Selection ntation r 11km Owot Uta – Nung Oku ment and Risk Mitigation Ekere – Afaha Udoe Eyop – E de obom Utuat Market Juncti on Road in Nsit Ibom & Ibesik po Asutan LGAs in Akwa Stat e AKS/RAAMP/SS/INDV/02/23 / Component C. Institutional D Consultancy Services for Eng Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2023-07-13 2023-07-27 2023-08-10 2023-08-31 2024-01-28 agement of TA Social Safegu ant Selection ntation ment and Risk Mitigation ard to support SPIU Page 3 PROCUREMENT PLAN Project information: ENHANCING WATERWAY CONNECTIVITY AND WATER SERVICE PROVISION IN COLOMBIA’S PLAN PAZCIFICO Region Project P156880 Project Implementation agency: 1. NATIONAL UNIT FOR THE MANAGEMENT OF DISASTER RISK / UNIDAD NACIONAL DE GESTION DEL RIESGO DE DESASTRES Date of the Procurement Plan: 10/22/2019 Period covered by this Procurement Plan: 10/22/2019 – 12/15/2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the documents previously approved with the Bank will be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is not applicable; Works: Is not applicable PROCUREMENT Colombia : Enhancing Waterway Connectivity and Water Service Provision in Colombia’s Plan Pazcifico PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2019-12-12 Revised Plan Date(s): (comma delineated, leave blank if2023-06-05 none) Project ID: P156880 GPN Date: 2019-12-09 Project Name: Enhancing Waterway Connectivity and Water Service Provision in Colombia’s Plan Pazcifico Loan / Credit No: IBRD / 87980 National Unit for the Management of Disaster Risk Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PTSP-BIRF8798-003 / Constr Improving Water Supply and Single Stage - One E 2020-10-3 ucción acueducto Francisco P IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 3,967,526.00 0.00 Canceled 2020-01-13 2020-01-18 2020-02-29 2020-03-30 2020-05-04 nvelope 1 izarro pating municipalities Improving Water Supply and PTSP-BIRF8798-005 / Constr Single Stage - One E 2020-11-1 IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 4,046,127.00 0.00 Canceled 2020-01-27 2020-02-01 2020-03-14 2020-04-13 2020-05-18 ucción acueducto Timbiquí nvelope 4 pating municipalities PTSP-BIRF8798-006 / Constr Improving Water Supply and Single Stage - One E 2020-11-0 ucción alcantarillado municip IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 3,760,945.00 0.00 Canceled 2020-01-20 2020-01-25 2020-03-07 2020-04-06 2020-05-11 nvelope 7 io seleccionado pating municipalities PTSP-BIRF8798-007 / Mante nimiento de las instalaciones Improving Waterway Transp Single Stage - One E 2020-11-1 portuarias y equipos de Seña IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 962,000.00 0.00 Canceled 2020-01-27 2020-02-01 2020-03-14 2020-04-13 2020-05-18 nvelope 4 lización y Seguridad durante ities el periodo de ejecución de la s obras PTSP-BIRF8798-0060 / Const Improving Waterway Transp Single Stage - One E 2021-07-1 rucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1,336,814.00 0.00 Canceled 2020-08-15 2020-08-28 2020-08-20 2020-09-18 2020-10-15 2020-10-06 2020-11-21 nvelope 9 portuario del municipio de La ities Tola (Nariño) National Procure PTSP-BIRF8798-090 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-08-1 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2022-09-28 2022-10-03 2022-11-14 2022-12-14 2023-01-18 nvelope lementation 8 portuario No. 1 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-091 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-10-2 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2022-11-03 2022-11-08 2022-12-20 2023-01-19 2023-02-23 nvelope lementation 3 portuario No. 2 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-092 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-12-1 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2022-12-22 2022-12-27 2023-02-07 2023-03-09 2023-04-13 nvelope lementation 1 portuario No. 3 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-094 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-12-0 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 nvelope lementation 4 portuario No. 4 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-095 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-12-0 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2022-12-12 2022-12-17 2023-01-28 2023-02-27 2023-04-03 nvelope lementation 1 portuario No. 5 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-096 / Constr Improving Waterway Transp ment Document - Single Stage - One E Pending Imp 2023-12-2 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2023-01-05 2023-01-10 2023-02-21 2023-03-23 2023-04-27 nvelope lementation 5 portuario No. 6 ities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-098 / Obras Improving Water Supply and ment Document - Single Stage - One E Pending Imp 2023-05-2 de optimización del acueduct IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 1 Envelope proce 2,900,000.00 0.00 2022-02-02 2022-02-07 2022-03-21 2022-04-20 2022-05-25 nvelope lementation 5 o de Timbiquí pating municipalities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-099 / Obras Improving Water Supply and ment Document - Single Stage - One E Pending Imp 2023-07-0 de optimización del acueduct IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 1 Envelope proce 2,900,000.00 0.00 2022-03-17 2022-03-22 2022-05-03 2022-06-02 2022-07-07 nvelope lementation 7 o de Francisco Pizarro pating municipalities ss (Non Bank-SPD ) National Procure Improving Water Supply and ment Document - PTSP-BIRF8798-100 / Obra al Single Stage - One E Pending Imp 2024-06-1 IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 1 Envelope proce 3,200,000.00 0.00 2022-10-21 2022-10-26 2022-12-07 2023-01-06 2023-02-10 cantarillado de Timbiquí nvelope lementation 0 pating municipalities ss (Non Bank-SPD ) National Procure PTSP-BIRF8798-101 / Obra al Improving Water Supply and ment Document - Single Stage - One E Pending Imp 2024-06-1 cantarillado de Francisco Piza IBRD / 87980 Sanitation Services in partici Post Request for Bids Open - National 1 Envelope proce 3,200,000.00 0.00 2022-10-21 2022-10-26 2022-12-07 2023-01-06 2023-02-10 nvelope lementation 0 rro pating municipalities ss (Non Bank-SPD ) PTSP-BIRF-8798-125 / Optimi zación y ampliación del siste ma de acueducto de la cabec Improving Water Supply and Request for Quota Request for Quota Single Stage - One E Under Imple 2023-07-0 era urbana del municipio de IBRD / 87980 Sanitation Services in partici Post Open - National tions (Non Bank-S 1,031,264.00 0.00 2022-11-12 2023-01-07 tions nvelope mentation 6 Timbiquí Departamento del C pating municipalities PD) auca: Obras en la captación, aducción, tratamiento y alma cenamiento de agua potable. PTSP-BIRF-8798-130 / Optimi zación y ampliación del siste Improving Water Supply and ma de acueducto de la cabec Request for Quota Single Stage - One E Other (with field f Under Imple 2023-07-0 IBRD / 87980 Sanitation Services in partici Post Open - National 1,755,560.00 0.00 2022-11-15 2023-01-10 era urbana del municipio de tions nvelope or explanation) mentation 9 pating municipalities Timbiquí Departamento del C auca: Obras en la red de dist ribución. National Procure PTSP-BIRF8798-088 / Constr Improving Waterway Transp ment Document - Single Stage - One E 2023-09-0 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 1 Envelope proce 2,761,617.00 0.00 Canceled 2022-08-15 2022-12-06 2022-08-20 2022-10-01 2023-01-26 2022-10-31 2022-12-05 nvelope 1 portuario del municipio de La ities ss (Non Bank-SPD Tola (Nariño) ) PTSP-BIRF8798-140 / Constr Improving Waterway Transp Single Stage - One E Other (with field f Pending Imp 2024-01-1 ucción del muelle y terminal IBRD / 87980 ort in participating municipal Post Request for Bids Open - National 2,761,618.84 0.00 2023-03-29 2023-04-03 2023-05-15 2023-06-14 2023-07-19 nvelope or explanation) lementation 5 portuario del municipio de La ities Tola (Nariño). GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Capacity Building and Institu PTSP-BIRF8798-0052 / Adqui tional Strengthening for wat Request for Quota Single Stage - One E rir motobombas y accesorios IBRD / 87980 erway transport operators a Post Open - National 198,804.00 187,812.81 Signed 2020-07-13 2020-09-07 2020-11-15 2020-10-07 tions nvelope hidráulicos nd water supply and sanitati on service providers in parti cipating municipalities Capacity Building and Institu PTSP-BIRF8798-0053 / Adqui tional Strengthening for wat Request for Quota Single Stage - One E rir tanques para almacenami IBRD / 87980 erway transport operators a Post Open - National 246,330.00 19,321.73 Signed 2020-07-13 2020-09-07 2020-11-21 2020-10-07 tions nvelope ento de agua nd water supply and sanitati on service providers in parti cipating municipalities Capacity Building and Institu PTSP-BIRF8798-0056 / Adqui tional Strengthening for wat Request for Quota Single Stage - One E rir filtros purificadores de ag IBRD / 87980 erway transport operators a Post Open - National 100,274.00 51,899.67 Signed 2020-07-13 2020-09-07 2020-11-12 2020-10-22 tions nvelope ua nd water supply and sanitati on service providers in parti cipating municipalities Capacity Building and Institu PTSP-BIRF8798-0054 / Adqui tional Strengthening for wat Request for Quota Single Stage - One E rir plantas de tratamiento de IBRD / 87980 erway transport operators a Post Open - National 140,278.00 120,485.00 Signed 2020-07-13 2020-09-07 2020-10-31 2020-11-06 tions nvelope agua potable portátiles nd water supply and sanitati on service providers in parti cipating municipalities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8798-117 / Prestar los servicios logísticos integr Capacity Building and Institu ales para la correcta ejecució tional Strengthening for wat n del Convenio de Cooperaci erway transport operators a Request for Quota Single Stage - One E Under Imple IBRD / 87980 Post Open - National 166,050.00 0.00 2022-08-27 2022-10-22 2023-05-20 ón No. 57833-PTSP-017-2022 nd water supply and sanitati tions nvelope mentation suscrito entre la Dirección Ge on service providers in parti neral Marítima (MDN – DIMAR cipating municipalities ), el Servicio Nacional de Apr endizaje (SENA) y el FTSP. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8798-010 / Interve Improving Waterway Transp ntoría de la Ejecución de Obr Quality And Cost- Open - Internationa IBRD / 87980 ort in participating municipal Post 1,326,080.00 0.00 Canceled 2020-01-27 2020-02-17 2020-04-01 2020-04-29 2020-05-29 2020-07-03 2020-08-07 2021-08-07 as de muelles, Obras de Señ Based Selection l ities alización y Seguridad en Nav egación PTSP-BIRF8798-011 / Imple Project Management and En Consultant Qualifi mentación del plan de inform IBRD / 87980 vironmental and Social Mana Post Open - National 100,000.00 0.00 Canceled 2020-02-03 2020-02-24 2020-04-08 2020-05-08 2020-06-12 2020-12-09 cation Selection ación, comunicación y partici gement pación PTSP-BIRF8798-012 / Actuali Improving Water Supply and Consultant Qualifi zacion de estudios Acueduct IBRD / 87980 Sanitation Services in partici Post Open - National 74,600.00 0.00 Canceled 2020-01-27 2020-02-17 2020-04-01 2020-05-01 2020-06-05 2020-12-02 cation Selection o Francisco Pizarro pating municipalities PTSP-BIRF8798-014 / Interve Improving Water Supply and Least Cost Selecti ntoria Obras Alcantarillado Fr IBRD / 87980 Sanitation Services in partici Post Open - National 275,138.00 0.00 Canceled 2020-01-13 2020-02-03 2020-03-18 2020-04-15 2020-05-15 2020-06-19 2020-07-24 2021-01-20 on ancisco Pizarro pating municipalities PTSP-BIRF8798-015 / Actuali Improving Water Supply and Least Cost Selecti zacion de estudios Alcantarill IBRD / 87980 Sanitation Services in partici Post Open - National 275,138.00 0.00 Canceled 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 on ado Francisco Pizarro pating municipalities PTSP-BIRF8798-017 / Interve Improving Water Supply and Least Cost Selecti ntoría obras Acueducto Timbi IBRD / 87980 Sanitation Services in partici Post Open - National 323,690.00 0.00 Canceled 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 on quí pating municipalities PTSP-BIRF8798-018 / Actuali Improving Water Supply and Least Cost Selecti zacion de estudios Alcantarill IBRD / 87980 Sanitation Services in partici Post Open - National 302,814.00 0.00 Canceled 2020-01-20 2020-02-10 2020-03-25 2020-04-22 2020-05-22 2020-06-26 2020-07-31 2021-01-27 on ado Timbiquí pating municipalities PTSP-BIRF8798-019 / Interve Improving Water Supply and Least Cost Selecti ntoría obras Alcantarillado Ti IBRD / 87980 Sanitation Services in partici Post Open - National 275,285.00 0.00 Canceled 2020-01-27 2020-02-17 2020-04-01 2020-04-29 2020-05-29 2020-07-03 2020-08-07 2021-02-03 on mbiquí pating municipalities Capacity Building and Institu tional Strengthening for wat PTSP-BIRF8798-020 / Fortale Quality And Cost- Open - Internationa IBRD / 87980 erway transport operators a Post 700,000.00 0.00 Canceled 2020-02-17 2020-03-09 2020-04-22 2020-05-20 2020-06-19 2020-07-24 2020-08-28 2021-08-28 cimiento institucional Based Selection l nd water supply and sanitati on service providers in parti cipating municipalities PTSP-BIRF8798-021 / Actuali Capacity Building and Institu zacion de planes maestros d tional Strengthening for wat Quality And Cost- Open - Internationa e acueducto para Olaya Herr IBRD / 87980 erway transport operators a Post 900,000.00 0.00 Canceled 2020-02-24 2020-03-16 2020-04-29 2020-05-27 2020-06-26 2020-07-31 2020-09-04 2021-09-04 Based Selection l era, La Tola, Mosquera, Franc nd water supply and sanitati isco Pizarro, Lopez de Micay on service providers in parti and Santa Barbara de Iscuan cipating municipalities de PTSP-BIRF8798-022 / Interve Improving Water Supply and Consultant Qualifi ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Post Open - National 5,425.00 0.00 Canceled 2020-01-27 2020-02-17 2020-04-01 2020-05-01 2020-06-05 2020-12-02 cation Selection os Acueducto Francisco Pizar pating municipalities ro PTSP-BIRF8798-023 / Interve Improving Water Supply and Consultant Qualifi ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Post Open - National 8,447.00 0.00 Canceled 2020-01-20 2020-02-10 2020-03-25 2020-04-24 2020-05-29 2020-11-25 cation Selection os Acueducto Timbiquí pating municipalities PTSP-BIRF8798-024 / Interve Improving Water Supply and Consultant Qualifi ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Post Open - National 22,011.00 0.00 Canceled 2020-02-03 2020-02-24 2020-04-08 2020-05-08 2020-06-12 2020-12-09 cation Selection os Alcantarillado Francisco pi pating municipalities zarro PTSP-BIRF8798-025 / Interve Improving Water Supply and Consultant Qualifi ntoría Actualizacion de estudi IBRD / 87980 Sanitation Services in partici Post Open - National 24,225.00 0.00 Canceled 2020-02-10 2020-03-02 2020-04-15 2020-05-15 2020-06-19 2020-12-16 cation Selection os Alcantarillado Timbiquí pating municipalities PTSP-BIRF8798-026 / Evalua Project Management and En Quality And Cost- IBRD / 87980 Post Open - National 174,000.00 0.00 Canceled 2021-02-22 2021-03-15 2021-04-28 2021-05-26 2021-06-25 2021-07-30 2021-09-03 2022-09-03 ción de medio término y final vironmental and Social Mana Based Selection gement Page 2 PTSP-BIRF8798-008 / Estudio Improving Waterway Transp Quality And Cost- Open - Internationa s y Diseños definitivos para l IBRD / 87980 ort in participating municipal Prior 1,169,532.00 925,315.06 Signed 2020-05-19 2020-06-15 2020-06-09 2020-07-08 2020-07-08 2020-09-21 2020-08-05 2020-11-20 2020-08-20 2021-01-29 2020-09-24 2021-06-01 2020-10-18 2021-10-09 2021-10-18 Based Selection l os muelles y señalización ities PTSP-BIRF8798-009 / Interve Improving Waterway Transp Consultant Qualifi ntoría de Estudios de muelles IBRD / 87980 ort in participating municipal Post Open - National 350,763.00 0.00 Canceled 2020-05-19 2020-06-24 2020-06-09 2020-07-23 2020-08-22 2020-10-05 2021-10-05 cation Selection y estudios de señalización ities PTSP-BIRF8798-0009 / Interv Improving Waterway Transp Quality And Cost- entoría de Estudios y Diseños IBRD / 87980 ort in participating municipal Post Open - National 350,763.00 191,593.71 Signed 2020-07-07 2020-07-06 2020-07-28 2020-09-10 2020-09-10 2020-10-08 2020-11-09 2020-11-07 2021-01-29 2020-12-12 2021-02-22 2021-01-16 2021-10-09 2022-01-16 Based Selection de Muelles y señalización ities PTSP-BIRF8798-0058 / Interv entoría técnica, administrativ Improving Waterway Transp a, financiera, legal, ambienta Quality And Cost- IBRD / 87980 ort in participating municipal Post Open - National 230,726.00 0.00 Canceled 2020-07-21 2020-07-18 2020-08-11 2020-09-24 2020-10-22 2020-11-21 2020-12-26 2021-01-30 2021-10-27 l y social de la construcción d Based Selection ities el muelle y terminal portuari o en el municipio de La Tola ( Nariño) PTSP-BIRF8798-0059 / Cons ultoría para la estructuración Capacity Building and Institu del modelo de administració tional Strengthening for wat n, operación y mantenimient erway transport operators a Consultant Qualifi IBRD / 87980 Post Open - National 101,414.00 71,457.54 Signed 2020-07-21 2020-07-18 2020-08-11 2020-09-24 2020-10-06 2020-10-24 2022-01-18 2020-11-28 2022-01-19 2021-05-27 o de los terminales portuario nd water supply and sanitati cation Selection s fluviales de los municipios on service providers in parti del Pacífico sur de Colombia, cipating municipalities con aplicación piloto en el m unicipio de La Tola (Nariño). PTSP-BIRF8798-0057 / Actua Improving Water Supply and lización, ajuste y complemen Consultant Qualifi IBRD / 87980 Sanitation Services in partici Post Open - National 100,013.00 129,170.81 Signed 2020-09-30 2020-10-21 2020-10-15 2020-11-22 2021-02-16 2020-12-07 2021-06-10 2021-01-11 2021-06-11 2021-07-10 tación de los estudios y diseñ cation Selection pating municipalities os acueducto Francisco Pizar ro PTSP-BIRF8798-072 / CONSU LTORÍA PARA LA ELABORACI ÓN DE LOS ESTUDIOS Y DISE Improving Water Supply and Consultant Qualifi Under Implement ÑOS DEL SISTEMA DE ALCAN IBRD / 87980 Sanitation Services in partici Post Open - National 172,700.00 0.00 2021-03-24 2021-05-06 2021-04-08 2021-05-16 2021-05-31 2021-07-05 2022-03-02 cation Selection ation TARILLADO DE LA CABECERA pating municipalities URBANA DEL MUNICIPIO DE T IMBIQUÍ, DEPARTAMENTO DE L CAUCA PTSP-BIRF8798-073 / CONSU LTORÍA PARA LA ELABORACI ÓN DE LOS ESTUDIOS Y DISE Improving Water Supply and Consultant Qualifi Under Implement ÑOS DEL SISTEMA DE ALCAN IBRD / 87980 Sanitation Services in partici Post Open - National 184,250.00 0.00 2021-03-24 2021-05-20 2021-04-08 2021-05-16 2021-05-31 2021-07-05 2022-03-02 cation Selection ation TARILLADO DE LA CABECERA pating municipalities URBANA DEL MUNICIPIO DE F RANCISCO PIZARRO, DEPART AMENTO DE NARIÑO PTSP-BIRF8798-074 / PREST AR LOS SERVICIOS DE INTER VENTORÍA (SUPERVISIÓN) TÉ CNICA, ADMINISTRATIVA, FIN Improving Water Supply and ANCIERA, LEGAL, AMBIENTAL Quality And Cost- IBRD / 87980 Sanitation Services in partici Post Open - National 93,030.00 0.00 Canceled 2021-03-24 2021-04-14 2021-05-18 2021-05-23 2021-06-07 2021-06-22 2021-07-18 2022-04-22 Y SOCIAL PARA LOS ESTUDIO Based Selection pating municipalities S Y DISEÑOS DE LOS SISTEM AS DE ALCANTARILLADO DE LOS MUNICIPIOS DE TIMBIQUÍ , DEPARTAMENTO DEL CAUC A, Y FRANCISCO PIZARRO, D PTSP-BIRF8798-078 / Prestar los servicios de interventoría (supervisión) técnica, admini Improving Water Supply and strativa, financiera, legal, am Quality And Cost- IBRD / 87980 Sanitation Services in partici Post Open - National 46,512.00 0.00 Canceled 2021-05-13 2021-06-03 2021-07-07 2021-07-12 2021-07-27 2021-08-11 2021-09-06 2022-06-11 biental y social para los estu Based Selection pating municipalities dios y diseños del sistema de alcantarillado en los municipi os del pacifico sur de los dep artamentos de cauca y nariñ o. PTSP-BIRF8798-080 / PREST AR LOS SERVICIOS DE INTER VENTORÍA (SUPERVISIÓN) TÉ CNICA, ADMINISTRATIVA, FIN Improving Water Supply and ANCIERA, LEGAL, AMBIENTAL Consultant Qualifi Under Implement IBRD / 87980 Sanitation Services in partici Post Open - National 60,550.00 0.00 2021-05-25 2021-06-09 2021-06-09 2021-07-19 2021-10-01 2021-08-03 2021-10-28 2021-09-01 2022-05-29 Y SOCIAL PARA LOS ESTUDIO cation Selection ation pating municipalities S Y DISEÑOS DE LOS SISTEM AS DE ALCANTARILLADO DE LOS MUNICIPIOS DE TIMBIQUÍ , DTO DEL CAUCA, Y FRANCIS CO PIZARRO DTO NARIÑO. PTSP-BIRF8798-082 / PREST AR LOS SERVICIOS DE INTER VENTORÍA (SUPERVISIÓN) TÉ CNICA, ADMINISTRATIVA, FIN Improving Water Supply and ANCIERA, LEGAL, AMBIENTAL Quality And Cost- Open - Internationa Under Implement IBRD / 87980 Sanitation Services in partici Prior 1,640,447.00 0.00 2021-07-12 2021-10-04 2021-07-16 2021-12-07 2021-08-14 2022-04-06 2021-09-27 2022-06-17 2021-10-12 2022-09-16 2021-11-16 2023-04-21 2021-12-10 2023-12-15 , SOCIAL Y DE SEGURIDAD Y Based Selection l ation pating municipalities SALUD EN EL TRABAJO PARA LOS ESTUDIOS, DISEÑOS Y O BRAS DE LOS SISTEMAS DE A CUEDUCTO Y ALCANTARILLA DO EN LOS MUNICIPIOS DEL PTSP-BIRF8798-089 / Interve ntoría técnica, administrativa Improving Waterway Transp , financiera, legal, ambiental Quality And Cost- Open - Internationa Under Implement IBRD / 87980 ort in participating municipal Post 430,000.00 0.00 2022-03-16 2022-04-23 2022-04-06 2022-05-20 2022-06-17 2022-07-17 2022-08-21 2022-09-25 2023-07-25 y social de la construcción de Based Selection l ation ities l muelle y terminal portuario en el municipio de La Tola (N ariño) PTSP-BIRF8798-093 / Interve ntoría técnica, administrativa Improving Waterway Transp Quality And Cost- Open - Internationa Pending Impleme , financiera, legal, ambiental IBRD / 87980 ort in participating municipal Post 950,000.00 0.00 2022-10-12 2022-11-02 2022-12-16 2023-01-13 2023-02-12 2023-03-19 2023-04-23 2024-02-23 Based Selection l ntation y social de la construcción de ities l muelle y terminal portuario 1, 2 y 3 PTSP-BIRF8798-097 / Interve ntoría técnica, administrativa Improving Waterway Transp Quality And Cost- Open - Internationa Pending Impleme , financiera, legal, ambiental IBRD / 87980 ort in participating municipal Post 950,000.00 0.00 2023-01-05 2023-01-26 2023-03-11 2023-04-08 2023-05-08 2023-06-12 2023-07-17 2024-05-17 Based Selection l ntation y social de la construcción de ities l muelle y terminal portuario 4, 5 y 6 PTSP-BIRF8798-102 / Estruct Capacity Building and Institu uración del esquema de pres tional Strengthening for wat Quality And Cost- tación de los servicios públic IBRD / 87980 erway transport operators a Post Open - National 380,000.00 0.00 Canceled 2022-03-17 2022-04-07 2022-05-21 2022-06-18 2022-07-18 2022-08-22 2022-09-26 2023-07-26 Based Selection os de acueducto, alcantarilla nd water supply and sanitati do \ aseo en Timbiquí on service providers in parti cipating municipalities Page 3 PTSP-BIRF8798-111 / ESTRU Capacity Building and Institu CTURACIÓN DEL ESQUEMA D tional Strengthening for wat E PRESTACIÓN DE LOS SERVI erway transport operators a Consultant Qualifi Under Implement CIOS PÚBLICOS DE ACUEDUC IBRD / 87980 Post Open - National 285,000.00 0.00 2022-04-27 2022-08-01 2022-05-18 2022-07-01 2022-07-31 2022-09-04 2023-07-01 nd water supply and sanitati cation Selection ation TO, ALCANTARILLADO Y ASE on service providers in parti O EN EL MUNICIPIO DE TIMBI cipating municipalities QUÍ, DEPARTAMENTO DEL CA UCA PTSP-BIRF8798-119 / INTERV ENTORÍA integral técnica, ad ministrativa, financiera, cont Capacity Building and Institu able, ambiental, social y juríd tional Strengthening for wat ica a la consultoría que tiene erway transport operators a Consultant Qualifi Pending Impleme IBRD / 87980 Post Open - National 61,786.00 0.00 2022-08-30 2022-09-19 2022-10-17 2022-11-16 2022-12-21 2023-06-19 como nd water supply and sanitati cation Selection ntation objeto la “ESTRUCTURACIÓN on service providers in parti DEL ESQUEMA DE PRESTACI cipating municipalities ÓN DE LOS SERVICIOS PÚBLI COS DE ACUEDUCTO, ALCAN TARILLADO Y ASEO TIMBIQUI " PTSP-BIRF- 8798-133 / Interv entoría técnica, administrativ a, financiera, legal, ambienta Improving Waterway Transp l y social de los estudios y dis Quality And Cost- Open - Internationa Pending Impleme IBRD / 87980 ort in participating municipal Post 114,205.00 0.00 2023-01-27 2023-02-06 2023-03-22 2023-04-19 2023-05-19 2023-06-23 2023-07-28 2024-07-27 eños finales para la construc Based Selection l ntation ities ción, rehabilitación y mejora miento de la infraestructura de muelles e instalaciones po rtuarias; y para la implement ación de la INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8798-001 / Líder d Project Management and En Individual Consult IBRD / 87980 Post Open 23,598.00 18,126.11 Signed 2019-11-25 2020-01-02 2019-12-04 2021-01-08 2019-12-05 2021-01-28 2019-12-15 2020-02-08 2020-04-13 e Conectividad de Transporte vironmental and Social Mana ant Selection gement PTSP-BIRF8798-028 / Especi Project Management and En Individual Consult IBRD / 87980 Post Limited 17,032.00 0.00 Canceled 2020-01-27 2020-01-28 2020-02-01 2020-02-08 2020-03-07 2020-07-05 alista Ambiental vironmental and Social Mana ant Selection gement PTSP-BIRF8798-029 / Enlace Project Management and En Individual Consult IBRD / 87980 Post Open 7,759.00 0.00 Canceled 2020-01-27 2020-01-28 2020-03-16 2020-03-23 2020-04-20 2020-08-18 Social de Conectividad de Tr vironmental and Social Mana ant Selection ansporte gement PTSP-BIRF8798-030 / Enlace Project Management and En Individual Consult IBRD / 87980 Post Open 7,759.00 0.00 Canceled 2020-01-27 2020-01-28 2020-03-16 2020-03-23 2020-04-20 2020-08-18 Social de Conectividad de Tr vironmental and Social Mana ant Selection ansporte gement PTSP-BIRF8798-031 / Apoyo Project Management and En Técnico del Componente de Individual Consult IBRD / 87980 vironmental and Social Mana Post Limited 7,759.00 0.00 Canceled 2020-01-31 2020-01-31 2020-02-05 2020-02-15 2020-03-06 2020-07-04 Conectividad de Transporte y ant Selection gement Provisión de Agua PTSP-BIRF8798-032 / Apoyo Project Management and En Técnico del Componente de Individual Consult IBRD / 87980 vironmental and Social Mana Post Limited 7,759.00 0.00 Canceled 2020-01-31 2020-01-31 2020-02-05 2020-02-15 2020-03-10 2020-07-08 Conectividad de Transporte y ant Selection gement Provisión de Agua PTSP-BIRF8798-033 / Especi Project Management and En Individual Consult IBRD / 87980 Post Limited 17,032.00 10,993.59 Signed 2020-01-31 2020-01-31 2020-02-05 2020-02-05 2020-02-15 2020-02-14 2020-03-10 2020-05-27 2020-07-08 alista de Conectividad de Tra vironmental and Social Mana ant Selection nsporte gement PTSP-BIRF8798-034 / Viabiliz Project Management and En Individual Consult IBRD / 87980 Post Limited 17,032.00 10,993.59 Signed 2020-01-31 2020-01-31 2020-02-05 2020-03-16 2020-02-15 2020-04-15 2020-03-10 2020-05-27 2020-07-08 ador de Proyectos ante INVIA vironmental and Social Mana ant Selection S gement PTSP-BIRF8798-035 / Especi Project Management and En alista en Agua y Saneamient Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 17,302.00 39,247.38 Signed 2020-02-26 2020-03-11 2020-03-04 2020-03-23 2020-03-09 2020-07-16 2020-03-19 2020-07-22 2020-07-17 o Básico - Recontratación JAI ant Selection gement RO ALBERTO PÉREZ GÓMEZ PTSP-BIRF8798-036 / Directo Project Management and En ra Ejecutiva / Coordinadora d Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 17,596.00 67,107.66 Signed 2020-02-26 2020-02-26 2020-03-07 2020-03-06 2020-03-12 2020-03-10 2020-03-22 2020-03-19 2021-03-21 el Proyecto FTSP - Recontrata ant Selection gement ción LUZ AMANDA PULIDO PTSP-BIRF8798-037 / Líder A Project Management and En Individual Consult mbiental - Recontratación RU IBRD / 87980 vironmental and Social Mana Post Limited 15,009.00 57,644.82 Signed 2020-02-27 2020-03-11 2020-03-03 2020-03-16 2020-03-08 2020-03-12 2020-03-18 2020-03-19 2021-03-17 ant Selection TH ALEJANDRA CATACOLI JIM gement ENEZ PTSP-BIRF8798-038 / Líder Fi Project Management and En Individual Consult nanciera - Recontratación CL IBRD / 87980 vironmental and Social Mana Post Direct 15,009.00 57,242.20 Signed 2020-02-26 2020-02-26 2020-03-07 2020-03-06 2020-03-12 2020-03-16 2020-03-22 2020-03-19 2021-03-21 ant Selection AUDIA AGUDELO SEDANO gement PTSP-BIRF8798-039 / Líder d Project Management and En Individual Consult e Adquisiciones - Recontrata IBRD / 87980 vironmental and Social Mana Post Direct 15,009.00 57,242.20 Signed 2020-02-26 2020-02-26 2020-03-07 2020-03-05 2020-03-12 2020-03-11 2020-03-22 2020-03-19 2021-03-21 ant Selection ción ELKIN ADOLFO PINILLA C gement AÑÓN PTSP-BIRF8798-040 / Líder d Project Management and En Individual Consult e Seguridad - Recontratación IBRD / 87980 vironmental and Social Mana Post Direct 15,009.00 57,242.09 Signed 2020-02-26 2022-03-11 2020-03-07 2020-03-06 2020-03-12 2020-03-11 2020-03-22 2020-03-22 2021-03-21 ant Selection WILSON LAVERDE FLÓREZ gement PTSP-BIRF8798-041 / Especi Project Management and En Individual Consult alista Financiera - Recontrata IBRD / 87980 vironmental and Social Mana Post Direct 11,355.00 43,304.24 Signed 2020-02-26 2020-02-26 2020-03-07 2020-03-10 2020-03-12 2020-03-12 2020-03-22 2020-03-19 2021-03-21 ant Selection ción SANDRA LORENA PEÑA gement PTSP-BIRF8798-042 / Líder C Project Management and En omponente Agua y Saneamie Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 37,523.00 57,644.82 Signed 2020-03-24 2020-04-01 2020-04-03 2020-04-07 2020-04-08 2020-04-01 2020-04-18 2020-04-07 2021-04-18 nto Básico - Recontratación F ant Selection gement ABIOLA IGUARAN ARAUJO PTSP-BIRF8798-043 / Líder S Project Management and En Individual Consult ocial - Recontratación KELLY IBRD / 87980 vironmental and Social Mana Post Direct 15,009.00 57,666.59 Signed 2020-04-06 2020-04-06 2020-04-16 2020-04-06 2020-04-21 2020-04-10 2020-05-01 2020-04-24 2021-04-30 ant Selection LORENA RUIZ GARCIA gement PTSP-BIRF8798-044 / Especi Project Management and En alista de Adquisiciones BM - Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 56,773.00 43,625.30 Signed 2020-04-16 2020-02-14 2020-04-26 2020-04-10 2020-05-01 2020-04-15 2020-05-11 2020-05-05 2021-05-10 Recontratación JOHN MAURIC ant Selection gement IO OTALVARO CORTES PTSP-BIRF8798-045 / Actuali zación, Ajustes y Complemen Improving Water Supply and Pending Impleme to de los Diseños para la Opti IBRD / 87980 Sanitation Services in partici Post Direct Selection Direct 69,865.00 0.00 2020-05-07 2020-05-17 2020-06-06 2020-09-19 ntation mización y Ampliación del Ac pating municipalities ueducto del Municipio de Tim biquí - Cauca Page 4 PTSP-BIRF8798-046 / Especi Project Management and En Individual Consult IBRD / 87980 Post Limited 11,355.00 0.00 Canceled 2020-05-07 2020-05-07 2020-05-12 2020-06-02 2020-07-07 2021-01-03 alista de Planeación y Segui vironmental and Social Mana ant Selection miento gement PTSP-BIRF8798-047 / Líder d Project Management and En Individual Consult e Conectividad - Recontrataci IBRD / 87980 vironmental and Social Mana Post Direct 75,046.00 57,644.82 Signed 2020-05-14 2020-06-12 2020-05-24 2020-05-22 2020-05-29 2020-06-04 2020-06-08 2020-06-09 2021-06-07 ant Selection ón DIEGO FERNANDO DUQUE gement BASTIDAS PTSP-BIRF8798-052 / Líder d Project Management and En Individual Consult Pending Impleme IBRD / 87980 Post Limited 15,009.00 0.00 2020-06-24 2020-07-04 2020-07-09 2020-07-19 2021-07-18 e Planeación y Seguimiento vironmental and Social Mana ant Selection ntation gement PTSP-BIRF8798-048 / Interve ntoría de Estudios y Diseños Improving Water Supply and Individual Consult Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Post Direct 13,932.00 12,466.75 Signed 2020-06-12 2020-07-09 2020-06-22 2020-07-15 2020-07-02 2020-07-27 2020-07-17 2020-08-27 2021-07-16 ant Selection e Timbiquí y Francisco Pizarr pating municipalities o - Director de Interventoría PTSP-BIRF8798-049 / Interve ntoría de Estudios y Diseños Improving Water Supply and Individual Consult Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Post Direct 4,917.00 4,509.25 Signed 2020-06-12 2020-07-09 2020-06-22 2020-07-15 2020-07-02 2020-07-27 2020-07-17 2020-08-27 2021-07-16 ant Selection e Timbiquí y Francisco Pizarr pating municipalities o - Especialista Electromecán ico PTSP-BIRF8798-050 / Interve ntoría de Estudios y Diseños Improving Water Supply and Individual Consult Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Post Direct 8,072.00 7,294.38 Signed 2020-06-12 2020-07-09 2020-06-22 2020-07-15 2020-07-02 2020-07-27 2020-07-17 2020-08-27 2021-07-16 ant Selection e Timbiquí y Francisco Pizarr pating municipalities o - Especialista Estructural PTSP-BIRF8798-051 / interve ntoría de Estudios y Diseños Improving Water Supply and Individual Consult Acueducto y Alcantarillado d IBRD / 87980 Sanitation Services in partici Post Direct 5,818.00 5,263.20 Signed 2020-06-04 2020-07-09 2020-06-14 2020-07-15 2020-06-24 2020-07-24 2020-07-09 2020-08-27 2021-07-08 ant Selection e Timbiquí y Francisco Pizarr pating municipalities o - Especialista Geotécnia PTSP-BIRF8798-061 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP Project Management and En ECIAL Y ASEGURAMIENTO RA IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct 10,200.00 20,172.50 Signed 2020-10-19 2020-11-05 2020-11-08 2020-11-19 2021-01-08 2021-02-20 2021-07-07 ZONABLE SOBRE LOS PROCE gement SOS DE ADQUISICIONES DEL PROYECTO/PROGRAMA FINA NCIADO POR EL BID Y EL BAN CO MUNDIAL A TRAVÉS DE P RÉSTAMOS PTSP-BIRF8798-062 / Directo Project Management and En ra Ejecutiva / Coordinadora d Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 12,900.00 62,078.79 Signed 2021-02-26 2021-03-15 2021-03-08 2021-03-15 2021-03-13 2021-03-13 2021-03-18 2021-03-19 2022-03-17 el Proyecto FTSP - Recontrata ant Selection gement ción LUZ AMANDA PULIDO PTSP-BIRF8798-063 / Líder C Project Management and En omponente Agua y Saneamie Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 27,500.00 52,952.63 Signed 2021-03-01 2021-03-15 2021-03-11 2021-03-15 2021-03-16 2021-03-16 2021-04-08 2021-04-09 2022-04-07 nto Básico - Recontratación F ant Selection gement ABIOLA IGUARAN ARAUJO PTSP-BIRF8798-064 / Líder d Project Management and En Individual Consult e Adquisiciones - Recontrata IBRD / 87980 vironmental and Social Mana Post Direct 11,000.00 52,952.63 Signed 2021-02-26 2021-03-15 2021-03-08 2021-03-15 2021-03-13 2021-03-16 2021-03-18 2021-03-19 2022-03-17 ant Selection ción ELKIN ADOLFO PINILLA C gement AÑÓN PTSP-BIRF8798-065 / Líder Fi Project Management and En Individual Consult nanciera - Recontratación CL IBRD / 87980 vironmental and Social Mana Post Direct 11,000.00 52,952.63 Signed 2021-02-26 2021-03-15 2021-03-08 2021-03-15 2021-03-13 2021-03-13 2021-03-18 2021-03-19 2022-03-17 ant Selection AUDIA AGUDELO SEDANO gement PTSP-BIRF8798-066 / Líder S Project Management and En Individual Consult ocial - Recontratación KELLY IBRD / 87980 vironmental and Social Mana Post Direct 11,000.00 52,952.63 Signed 2021-03-19 2021-03-15 2021-03-29 2021-03-29 2021-04-03 2021-04-03 2021-04-23 2021-04-24 2022-04-22 ant Selection LORENA RUIZ GARCIA gement PTSP-BIRF8798-067 / Líder d Project Management and En Individual Consult e Seguridad - Recontratación IBRD / 87980 vironmental and Social Mana Post Direct 11,000.00 52,952.63 Signed 2021-02-26 2021-03-15 2021-03-08 2021-03-18 2021-03-13 2021-03-18 2021-03-22 2021-03-24 2022-03-21 ant Selection WILSON LAVERDE FLÓREZ gement PTSP-BIRF8798-068 / Contra tación Líder Ambiental para l a ejecución y cumplimiento d Project Management and En e los Marcos de Gestión Ambi IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct 5,496.00 26,476.31 Signed 2021-03-08 2021-03-15 2021-03-09 2021-03-15 2021-03-22 2021-03-24 2021-09-21 ental adoptados para la ejec gement ución del Fondo para el desar rollo del Plan Todos Somos P AZcífico - Fernando Rey PTSP-BIRF8649-070 / Especi Project Management and En Individual Consult alista Financiera - Recontrata IBRD / 87980 vironmental and Social Mana Post Direct 8,315.00 40,059.14 Signed 2021-03-08 2021-03-15 2021-03-09 2021-03-15 2021-03-14 2021-03-16 2021-03-18 2021-03-19 2022-03-17 ant Selection ción Sandra Lorena Peña gement PTSP-BIRF8649-069 / Especi Project Management and En alista de Adquisiciones - Cont IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct 20,079.00 40,059.14 Signed 2021-03-08 2021-03-15 2021-03-09 2021-03-15 2021-03-15 2021-03-17 2022-03-14 ratación Tulio José Fuentes gement PTSP-BIRF8649-071 / Especi alista de Planeación y Segui miento. - Brindar apoyo profe Project Management and En Individual Consult sional en la gestión de planifi IBRD / 87980 vironmental and Social Mana Post Open 10,394.00 18,200.98 Signed 2021-03-11 2021-03-15 2021-03-16 2021-03-22 2021-03-17 2021-03-18 2021-03-25 2021-03-27 2021-09-24 ant Selection cación, monitoreo y seguimie gement nto a las actividades del Fon do para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8798-075 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Project Management and En mplementación y ejecución d IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct 5,496.00 0.00 Canceled 2021-04-14 2021-04-19 2021-05-17 2021-11-16 e los componentes de Capaci gement dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico - Jorge Silva PTSP-BIRF8798-076 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Project Management and En mplementación y ejecución d Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 5,496.00 26,476.31 Signed 2021-04-15 2021-04-19 2021-04-22 2021-04-22 2021-04-23 2021-04-23 2021-05-17 2021-05-12 2021-11-16 e los componentes de Capaci ant Selection gement dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico para el desarrollo de l Plan Todos Somos PAZcífico - Jorge Silva. PTSP-BIRF8798-077 / Especi Project Management and En alista de Adquisiciones - Rec Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 8,315.00 40,059.14 Signed 2021-04-22 2021-04-26 2021-04-24 2021-04-26 2021-04-26 2021-04-26 2021-05-04 2021-05-07 2022-05-03 ontratación JOHN MAURICIO ant Selection gement OTÁLVARO CORTÉS Page 5 PTSP-BIRF8798-079 / Líder d Project Management and En Individual Consult e Conectividad - Recontrataci IBRD / 87980 vironmental and Social Mana Post Direct 54,958.00 52,952.63 Signed 2021-05-18 2021-05-26 2021-05-20 2021-05-26 2021-05-24 2021-05-24 2021-06-08 2021-06-09 2022-06-07 ant Selection ón DIEGO FERNANDO DUQUE gement BASTIDAS PTSP-BIRF8798-081 / Líder d Project Management and En Individual Consult e Planeación y Seguimiento IBRD / 87980 vironmental and Social Mana Post Direct 10,992.00 52,952.63 Signed 2021-06-09 2021-06-10 2021-06-19 2021-06-19 2021-06-24 2021-06-24 2021-06-30 2021-07-01 2022-06-29 ant Selection - Recontratación Joan Natalie gement Garzón PTSP-BIRF8798-083 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP ECIAL Y ASEGURAMIENTO Project Management and En RAZONABLE SOBRE LOS PRO IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct 21,808.00 19,036.57 Signed 2021-09-06 2021-09-15 2021-09-26 2021-10-04 2021-12-23 2022-02-01 2022-06-21 CESOS DE ADQUISICIONES D gement EL PROYECTO/PROGRAMA FI NANCIADO POR EL BID Y EL B ANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8798-084 / Líder A Project Management and En Individual Consult mbiental FTSP - Recontrataci IBRD / 87980 vironmental and Social Mana Post Direct 5,935.00 26,476.31 Signed 2021-09-09 2021-09-09 2021-09-09 2021-09-09 2021-09-20 2021-09-20 2021-09-23 2021-09-24 2022-03-22 ant Selection ón Fernando Rey gement PTSP-BIRF8798-085 / Especi Project Management and En alista de Planeación y Segui Individual Consult IBRD / 87980 vironmental and Social Mana Post Direct 22,425.00 40,059.14 Signed 2021-09-09 2021-09-09 2021-09-17 2021-09-17 2021-09-17 2021-09-17 2021-09-27 2021-09-29 2022-09-26 miento FTSP - Recontratación ant Selection gement Natalia García Medina Capacity Building and Institu PTSP-BIRF8798-086 / Líder d tional Strengthening for wat e Fortalecimiento Institucion Individual Consult IBRD / 87980 erway transport operators a Post Direct 11,870.00 52,952.63 Signed 2021-10-19 2021-10-20 2021-10-19 2021-10-20 2021-10-26 2021-10-26 2021-11-11 2021-11-12 2022-11-10 al - Recontratación Jorge Ern ant Selection nd water supply and sanitati esto Silva on service providers in parti cipating municipalities PTSP-BIRF8798-087 / Líder S Project Management and En Individual Consult IBRD / 87980 Post Open 14,837.00 24,066.33 Signed 2021-10-27 2021-10-27 2021-11-30 2022-02-22 2021-12-03 2022-02-25 2021-12-22 2022-04-10 2022-06-19 ocial FTSP vironmental and Social Mana ant Selection gement PTSP-BIRF8798-103 / Realiza r la evaluación de medio tér mino del proyecto “Mejora de Project Management and En la Conectividad y de la Provis Individual Consult Under Implement IBRD / 87980 vironmental and Social Mana Post Limited 12,545.00 0.00 2022-03-10 2022-03-01 2022-03-15 2022-04-05 2022-05-10 2022-08-11 ión de Agua en el Marco del ant Selection ation gement Plan PAZcífico” en cumplimie nto de las condiciones establ ecidas en el Contrato de Prés tamo BIRF N° 8798-CO. PTSP-BIRF8798-104 / Recont Improving Water Supply and Individual Consult ratación Líder de Agua BM - F IBRD / 87980 Sanitation Services in partici Post Direct 31,342.00 57,727.68 Signed 2022-03-04 2022-03-04 2022-03-14 2022-03-04 2022-03-19 2022-03-09 2022-04-08 2022-04-10 2023-04-07 ant Selection abiola del Rosario Iguarán pating municipalities PTSP-BIRF8798-106 / Recont Project Management and En Individual Consult ratación Líder de Adquisicion IBRD / 87980 vironmental and Social Mana Post Direct 12,537.00 52,952.63 Signed 2022-03-04 2022-03-04 2022-03-14 2022-03-14 2022-03-14 2022-03-14 2022-03-18 2022-03-28 2023-03-17 ant Selection es - Élkin Pinilla gement PTSP-BIRF8798-107 / Recont Project Management and En Individual Consult ratación Líder Financiera - Cl IBRD / 87980 vironmental and Social Mana Post Direct 12,537.00 52,952.63 Signed 2022-03-04 2022-03-04 2022-03-14 2022-03-14 2022-03-16 2022-03-16 2022-03-18 2022-03-19 2023-03-17 ant Selection audia Agudelo gement PTSP-BIRF8798-108 / Recont Project Management and En Individual Consult IBRD / 87980 Post Direct 6,269.00 26,476.31 Signed 2022-03-04 2022-03-04 2022-03-09 2022-03-09 2022-03-15 2022-03-15 2022-03-23 2022-03-24 2022-09-22 ratación Líder Ambiental - Fe vironmental and Social Mana ant Selection rnando Rey gement PTSP-BIRF8798-110 / Recont Project Management and En Individual Consult Under Implement ratación Especialista Financie IBRD / 87980 vironmental and Social Mana Post Direct 9,484.00 0.00 2022-03-04 2022-03-04 2022-03-05 2022-03-10 2022-03-18 2023-03-17 ant Selection ation ra - Sandra Lorena Peña gement PTSP-BIRF8798-105 / Recont Project Management and En Individual Consult ratación Directora Ejecutiva- IBRD / 87980 vironmental and Social Mana Post Direct 14,698.00 62,078.79 Signed 2022-03-04 2022-03-04 2022-03-14 2022-03-14 2022-03-15 2022-03-14 2022-03-18 2022-03-19 2023-03-17 ant Selection Coordinadora General - Luz A gement manda Pulido PTSP-BIRF8798-109 / Recont Project Management and En Individual Consult ratación Especialista de Adqu IBRD / 87980 vironmental and Social Mana Post Direct 23,711.00 43,671.56 Signed 2022-03-10 2022-03-04 2022-03-20 2022-03-20 2022-03-20 2022-03-07 2022-03-26 2022-03-17 2023-03-25 ant Selection isiciones - Tulio José Fuentes gement PTSP-BIRF8798-112 / Recont Project Management and En Individual Consult Under Implement ratación Líder de Seguridad - IBRD / 87980 vironmental and Social Mana Post Direct 5,935.00 0.00 2022-04-26 2022-05-05 2022-05-02 2022-05-02 2022-05-04 2022-05-05 2022-11-04 ant Selection ation Wilson Laverde gement PTSP-BIRF8798-113 / Liderar los procesos de adquisicione s que adelanta la Unidad Nac ional para la Gestión del Ries Project Management and En Individual Consult Under Implement go de Desastres como entida IBRD / 87980 vironmental and Social Mana Post Limited 11,870.00 0.00 2022-05-23 2022-05-23 2022-05-28 2022-06-15 2022-06-02 2022-06-17 2023-06-16 ant Selection ation d ejecutora del Fondo para el gement Desarrollo del Plan Todos So mos PAZcífico, según las Polí ticas, normas y regulaciones del BID y Banco M. PTSP-BIRF8798-114 / Liderar la planificación, estructuració Capacity Building and Institu n, seguimiento y gestión de l tional Strengthening for wat os proyectos de Conectividad erway transport operators a Individual Consult Under Implement de Transporte que hagan par IBRD / 87980 Post Direct 60,000.00 0.00 2022-05-27 2022-05-26 2022-05-29 2022-06-02 2022-06-07 2023-06-06 nd water supply and sanitati ant Selection ation te del préstamo BIRF 8798 - on service providers in parti CO, ejecutado por la Unidad cipating municipalities Nacional para la Gestión del Riesgo de Desastres como en tidad ejecutora. PTSP-BIRF8798-115 / Liderar la planificación, monitoreo, s eguimiento y gestión de los p réstamos del BID y el Banco Project Management and En Individual Consult Pending Impleme Mundial, ejecutados por la U IBRD / 87980 vironmental and Social Mana Post Direct 11,870.00 0.00 2022-06-16 2022-06-17 2022-06-24 2022-06-29 2023-06-29 ant Selection ntation nidad Nacional para la Gestió gement n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo del Plan Todos Somos Pazc PTSP-BIRF8798-116 / Brindar apoyo profesional como Espe cialista de Adquisiciones en l Project Management and En os procesos que adelanta la Individual Consult Under Implement IBRD / 87980 vironmental and Social Mana Post Limited 20,979.00 0.00 2022-07-11 2022-07-19 2022-07-16 2022-08-06 2022-09-10 2023-03-09 Unidad Nacional para la Gesti ant Selection ation gement ón del Riesgo de Desastres c omo entidad ejecutora del Fo ndo para el Desarrollo del Pla n Todos Somos PAZcífico. Page 6 PTSP-BIRF8798-118 / Especi Project Management and En alista de Planeación y Segui Individual Consult Pending Impleme IBRD / 87980 vironmental and Social Mana Post Direct - National 20,979.00 0.00 2022-08-30 2022-08-30 2022-09-28 2022-09-28 2023-09-27 miento FTSP - Recontratación ant Selection ntation gement Natalia García Medina PTSP-BIRF8798-120 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Project Management and En Individual Consult Pending Impleme el marco de los prestamos de IBRD / 87980 vironmental and Social Mana Post Direct - National 5,546.00 0.00 2022-09-19 2022-09-29 2022-10-20 2022-10-28 2023-04-26 ant Selection ntation l BIRF y el Banco Mundial, eje gement cutados por la Unidad Nacion al para la Gestión del Riesgo Desastres como entidad ejec utora del Fondo. PTSP-BIRF8798-121 / Coordi nar la implementación y sup ervisión de los préstamos del Project Management and En BID y el Banco Mundial, ejecu Individual Consult IBRD / 87980 vironmental and Social Mana Post Open - National 13,004.00 0.00 Canceled 2022-09-23 2022-09-19 2022-10-15 2022-10-17 2022-11-21 2023-05-20 tados por la Unidad Nacional ant Selection gement para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico PTSP-BIRF-8798-122 / Presta r los servicios jurídicos como especialista para los proceso s de adquisiciones del Fondo Project Management and En Individual Consult Pending Impleme para el Desarrollo del Plan To IBRD / 87980 vironmental and Social Mana Post Open - National 8,392.00 0.00 2022-10-03 2022-11-21 2022-12-12 2023-01-16 2023-07-15 ant Selection ntation dos Somos PAZcífico que ade gement lanta como entidad ejecutora la Uni-dad Nacional para la G estión del Riesgo de Desastr es, en el marco d PTSP-BIRF-8798-123 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP Project Management and En ECIAL Y ASEGURAMIENTO RA Pending Impleme IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct - National 21,217.00 0.00 2022-10-10 2022-10-16 2023-01-09 2023-05-09 ZONABLE SOBRE LOS PROCE ntation gement SOS DE ADQUISICIONES DEL PROYECTO/PROGRAMA FINA NCIADO POR EL BID Y EL BAN CO MUNDIAL A TRAVÉS DE P RÉSTAMOS PTSP-BIRF-8798-124 / Coordi nar la implementación y sup ervisión de los préstamos del Project Management and En BID y el Banco Mundial, ejecu Individual Consult Under Implement IBRD / 87980 vironmental and Social Mana Post Limited 13,004.00 0.00 2022-10-10 2022-10-07 2022-10-15 2022-09-27 2022-11-05 2022-12-10 2023-06-08 tados por la Unidad Nacional ant Selection ation gement para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico PTSP-BIRF-8798-126 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Project Management and En Individual Consult Pending Impleme l Banco Mundial ejecutados p IBRD / 87980 vironmental and Social Mana Post Direct - National 5,826.00 0.00 2022-11-07 2022-11-17 2022-12-08 2023-01-12 2023-07-11 ant Selection ntation or la Unidad Nacional para la gement Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PTSP-BIRF-8798-127 / Lidera r la planificación, estructurac Capacity Building and Institu ión, seguimiento y gestión de tional Strengthening for wat los proyectos de Capacidad y erway transport operators a Individual Consult Pending Impleme Fortalecimiento Institucional IBRD / 87980 Post Direct - National 2,773.00 0.00 2022-11-11 2022-11-16 2022-12-07 2023-01-11 2023-07-10 nd water supply and sanitati ant Selection ntation que hagan parte de los prést on service providers in parti amos del BID y el Banco Mun cipating municipalities dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Desa PTSP-BIRF-8798-128 / Lidera r los procesos de adquisicion es que adelanta la Unidad Na cional para la Gestión del Rie Project Management and En Individual Consult Under Implement sgo de Desastres como entid IBRD / 87980 vironmental and Social Mana Post Open - National 11,092.00 0.00 2022-11-11 2022-09-15 2022-12-20 2022-11-23 2023-01-10 2022-12-19 2023-02-14 2023-08-13 ant Selection ation ad ejecutora del Fondo para gement el Desarrollo del Plan Todos Somos PAZcífico, según las P olíticas, normas y regulacion es del BID y el Banc PTSP-BIRF-8798-129 / Lidera r las actividades relacionad as con protocolos y herrami Project Management and En entas de seguridad, para miti Pending Impleme IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct - National 2,773.00 0.00 2022-11-08 2022-11-16 2023-01-20 2023-07-19 gar las posibles amenazas o ntation gement riesgos en la ejecución de los proyectos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, q ue ejecuta la PTSP-BIRF-8798-131 / Brinda r apoyo profesional como esp ecialista de planeación, moni toreo, seguimiento y gestión Project Management and En Individual Consult Pending Impleme de los préstamos del Banco IBRD / 87980 vironmental and Social Mana Post Direct - National 23,731.00 0.00 2023-01-27 2023-02-01 2023-02-22 2023-03-29 2023-09-25 ant Selection ntation Mundial, ejecutados por la U gement nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo d PTSP-BIRF8798-132 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Project Management and En Pending Impleme el marco de los préstamos de IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct - National 12,548.00 0.00 2023-01-27 2023-02-01 2023-04-07 2023-10-04 ntation l BID y el Banco Mundial, ejec gement utados por la Unidad Naciona l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo PTSP-BIRF-8798-134 / Realiz ar apoyo como profesional es pecializado en los procesos c ontractuales y relaciones jurí Project Management and En Individual Consult Pending Impleme dico negociales del Fondo pa IBRD / 87980 vironmental and Social Mana Post Limited 9,493.00 0.00 2023-02-06 2023-02-11 2023-03-04 2023-04-08 2023-10-05 ant Selection ntation ra el Desarrollo del Plan Todo gement s Somos PAZcífico - FTSP, cu ya entidad ejecutora es la Un idad Nacional para la Gestión del Riesgo de Des Page 7 PTSP-BIRF-8798-135 / TDR E specialista Financiera en la g estión presupuestal y financi era de los préstamos del BID Project Management and En Individual Consult Pending Impleme y el Banco Mundial, ejecutad IBRD / 87980 vironmental and Social Mana Post Direct - National 9,493.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation os por la Unidad Nacional par gement a la Gestión del Riesgo de De sastres como entidad ejecuto ra del Fondo para el Desarrol lo del Plan Todos S PTSP-BIRF-8798-136 / Lidera r la gestión presupuestal y fi nanciera de los préstamos de Project Management and En l BID y el Banco Mundial, ejec Individual Consult Pending Impleme IBRD / 87980 vironmental and Social Mana Post Direct - National 12,548.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 utados por la Unidad Naciona ant Selection ntation gement l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo para el De sarrollo del Plan Todos Somo s PAZcífico. PTSP-BIRF-8798-137 / Lidera r las actividades relacionadas con protocolos y herramienta s de seguridad, para mitigar l Project Management and En as posibles amenazas o riesg IBRD / 87980 vironmental and Social Mana Post Direct Selection Direct - National 12,548.00 0.00 Under Review 2023-03-13 2023-03-23 2023-03-22 2023-05-26 2023-11-22 os en la ejecución de los proy gement ectos que se desarrollan en e l marco de los préstamos del BID y el Banco Mundial, que ejecuta la Unida PTSP-BIRF-8798-139 / Lidera r la planificación, estructurac ión, seguimiento y gestión de los proyectos de Capacidad y Improving Waterway Transp Individual Consult Pending Impleme Fortalecimiento Institucional IBRD / 87980 ort in participating municipal Post Direct - National 12,548.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation que hagan parte de los prést ities amos del BID y el Banco Mun dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Desa PTSP-BIRF-8798-141 / Presta r los servicios juridicos como especialista al Ordenador del Gasto, en los procesos de ad Project Management and En Individual Consult Pending Impleme quisiciones, así como en las IBRD / 87980 vironmental and Social Mana Post Direct - National 7,977.00 0.00 2023-04-11 2023-04-21 2023-05-12 2023-06-16 2023-12-13 ant Selection ntation actividades inherentes a la ej gement ecución de los proyectos que se desarrollan en el marco d e los prestamos del BID y el Banco Mundial.. PTSP-BIRF-8798-142 / Lidera r la planificación,estructuraci ón, seguimiento y gestión de los proyectos de Agua y Sane Improving Water Supply and Individual Consult Pending Impleme amiento Básico que hagan p IBRD / 87980 Sanitation Services in partici Post Direct - National 15,684.00 0.00 2023-04-11 2023-04-21 2023-05-12 2023-06-16 2023-12-13 ant Selection ntation arte de los préstamos del Ba pating municipalities nco Mundial 8649 CO y 8798 CO, ejecutados por la Unidad Nacional para la Gestión del Riesgo de Desastres. PTSP-BIRF-8798-143 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Project Management and En Individual Consult Under Implement l Banco Mundial ejecutados p IBRD / 87980 vironmental and Social Mana Post Limited 31,370.00 0.00 2023-05-05 2023-05-11 2023-05-10 2023-05-31 2023-07-05 2024-01-01 ant Selection ation or la Unidad Nacional para la gement Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PTSP-BIRF-8798-138 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Project Management and En Individual Consult l Banco Mundial ejecutados p IBRD / 87980 vironmental and Social Mana Post Limited 15,685.00 0.00 Canceled 2023-03-13 2023-04-04 2023-03-17 2023-04-07 2023-05-12 2023-11-08 ant Selection or la Unidad Nacional para la gement Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PTSP-BIRF-8798-145 / Lidera r la planificación, monitoreo, seguimiento y gestión de los Project Management and En préstamos del BID y el Banco Individual Consult Under Implement IBRD / 87980 vironmental and Social Mana Post Direct - National 12,548.00 0.00 2023-05-26 2023-05-25 2023-06-05 2023-06-26 2023-07-31 2024-01-27 Mundial, ejecutados por la U ant Selection ation gement nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del FTS P. NATALIE GARZON PSTP-BIRF-8798-146 / Brinda r acompañamiento técnico pr ofesional ambiental en la ges Project Management and En tión de los Planes de Manejo Individual Consult IBRD / 87980 vironmental and Social Mana Post Limited 5,307.00 0.00 Under Review 2023-05-26 2023-05-25 2023-05-31 2023-06-21 2023-07-26 2024-01-22 Ambiental y Estudios de Imp ant Selection gement acto Ambiental de los proyec tos que se desarrollen en el marco del PTSP, que adelant a como entidad ejecutora la UNGRD PTSP-BIRF-8798-147 / Lidera r la planificación, estructurac ión, seguimiento y gestión de Improving Waterway Transp Individual Consult Under Implement los proyectos de Conectivida IBRD / 87980 ort in participating municipal Post Direct - National 31,370.00 0.00 2023-05-26 2023-05-30 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation d de Transporte que hagan p ities arte del préstamo BIRF 8798 - CO, ejecutado por la UNGR D como entidad ejecutora del FTSP PTSP-BIRF-8798-148 / Brinda r apoyo profesional como Esp ecialista de Adquisiciones del préstamo 8798-CO en los pro Project Management and En Individual Consult Under Implement cesos que adelanta la Unidad IBRD / 87980 vironmental and Social Mana Prior Limited 47,463.00 0.00 2023-05-26 2023-06-07 2023-05-31 2023-06-21 2023-07-26 2024-01-22 ant Selection ation Nacional para la Gestión del gement Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico. Page 8 PTSP-BIRF-8798-149 / Presta r los servicios de acompaña miento integral y exclusivo al Ordenador del Gasto del FTS Project Management and En Individual Consult Pending Impleme P, en las actividades inherent IBRD / 87980 vironmental and Social Mana Post Limited 11,866.00 0.00 2023-06-02 2023-06-07 2023-06-28 2023-08-02 2024-01-29 ant Selection ntation es a la ejecución de los proye gement ctos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, que ejecuta la UNGRD. PTSP-BIRF-8798-150 / Coordi nar y dirigir la implementació n y supervisión de los présta mos del BID y el Banco Mund Project Management and En Individual Consult Pending Impleme ial, ejecutados por la Unidad IBRD / 87980 vironmental and Social Mana Post Direct - National 8,581.00 0.00 2023-06-02 2023-06-12 2023-07-03 2023-08-07 2024-02-03 ant Selection ntation Nacional para la Gestión del gement Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico. PTSP-BIRF-8798-152 / LÍDER Improving Water Supply and COMPONENTE AGUA Y SANE Individual Consult Pending Impleme IBRD / 87980 Sanitation Services in partici Post Open - National 62,739.00 0.00 2023-06-09 2023-07-28 2023-08-18 2023-09-22 2024-03-20 AMIENTO BÁSICO (FRANCISC ant Selection ntation pating municipalities O PZARRO - TIMBIQUI) PTSP-BIRF-8798-153 / Brinda r apoyo profesional como Esp ecialista de Adquisiciones del préstamo 8798-CO en los pro Project Management and En Individual Consult Pending Impleme cesos que adelanta la Unidad IBRD / 87980 vironmental and Social Mana Post Open - National 47,463.00 0.00 2023-06-13 2023-08-01 2023-08-22 2023-09-26 2024-03-24 ant Selection ntation Nacional para la Gestión del gement Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico. Page 9 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Improving Healthcare Services in Somalia ("Damal Caafimaad") Project c. Project Number: P172031 d. Total Finance: USD 100 million 2. Project Implementation Agency: Ministry of Health 3. Date of Project Plan: May, 2021 4. Period Covered by this Procurement: June 2021- May 2022 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017, August 2018 and November 2020 and ) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second-hand Goods: Not Applicable VII. Domestic Preference: Not Applicable VIII. Hands on Expanded Implementation Support (HEIS): Not applicable 1 IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US millions) Based on the risks identified above, the following procurement arrangements are proposed: a) Approach to Market: Based on previous experience and available local market, the following threshold will be used of open national/international and RFQ bidding (all figures in million USD) Table 1.2: Thresholds for procurement approaches and methods Procurement Methods (US millions)–Goods, Works, and Non- Consulting Services Open Open Request for Direct Category Internatio National Quotation Selection nal (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 All Values Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 All Values consultin g services Thresholds for Procurement Approaches and Methods (US, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants n.a. n.a. Direct Selection Consultants (Firms) All Values All Values Individual Consultants All Values All Values 2 XI. Table Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) S.N Contract Title, Description Estimat Revi Market Selec Evaluation Expect Date of o and Category ed Cost ew Approach tion Options (BAFO ed date contrac (US$) by (Open- Meth Rated Criteria of t award Ban National/ od etc.) bid/pro k Limited (RFP, posal etc.) RFB, openin RFQ g GOODS G1 FGS HMIS office 20,000 Prior Limited RFQ Most 27-Sep- 31-Oct- electronics/equipment advantageous Bid 21 21 G2 FMS HMIS office 40,000 Prior Limited RFQ Most 27-Oct- 30-Nov- electronics/equipment advantageous Bid 21 21 G3 HMIS reporting forms, printing 40,000 Prior Limited RFQ Most 26-Jan- 01-Mar- costs advantageous Bid 22 22 Sub-total 1 60,000 S.N Contract Title, Description and Estimate Revi Market Metho Expect Date of o Category d Cost ew Approach d ed date contract (US$) by (Open- (QCBS, of award Bank National/ LCBCS, bid/pro Limited etc.) QBS, posal DS openin g CONSULTANCY SERVICES C1 PCIU Senior Project Coordinator 91,680 Prior Open INDV 28-Jun- 01-Aug- International 21 21 C2 PCIU Legal Advisor (Part-time) 40,000 Prior Open National INDV 28-Jun- 01-Aug- 21 21 1 S.N Contract Title, Description and Estimate Revi Market Metho Expect Date of o Category d Cost ew Approach d ed date contract (US$) by (Open- (QCBS, of award Bank National/ LCBCS, bid/pro Limited etc.) QBS, posal DS openin g C3 PCIU Security Advisor 80,000 Prior Open INDV 28-Jun- 01-Aug- International 21 21 C4 PCIU Communications Specialist 43,488 Prior Open National INDV 28-Jun- 01-Aug- 21 21 C5 PCIU Environmental Specialist 43,488 Prior Open National INDV 28-Jun- 01-Aug- 21 21 C6 PCIU Procurement Specialist 100,000 Prior Open INDV 26-Feb- 01-Apr-22 International 22 C7 PCIU PFM Specialist 100,000 Prior Open INDV 26-Feb- 01-Apr-22 International 22 C8 PCIU GBV Specialist 43,488 Prior Open National INDV 19-Jul- 22-Aug- 21 21 C9 PCIU Social Specialist 52,800 Prior Open National INDV 28-Jun- 01-Aug- 21 21 C10 PMT Project Manager (PL) 48,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C11 PMT Environmental Specialist (PL) 16,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C12 PMT Social/ GBV Specialist (PL) 32,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C13 PMT Project Manager (SWS) 48,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C14 PMT Environmental Specialist (SWS) 16,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 2 S.N Contract Title, Description and Estimate Revi Market Metho Expect Date of o Category d Cost ew Approach d ed date contract (US$) by (Open- (QCBS, of award Bank National/ LCBCS, bid/pro Limited etc.) QBS, posal DS openin g C15 PMT Social/ GBV Specialist (SWS) 32,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C16 PMT Project Manager (HSS) 48,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C17 PMT Environmental Specialist (HSS) 16,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C18 PMT Social/ GBV Specialist (HSS) 32,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C19 PMT Project Manager (GAL) 48,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C20 PMT Project Manager (JUB) 48,000 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C21 FGS MoH HMIS specialist 43,488 Prior Open National INDV 18-Sep- 22-Oct-21 21 C22 FMS MoH HMIS specialist (PL) 32,000 Prior Open National INDV 19-Oct- 22-Nov- 21 21 C23 FMS MoH HMIS specialist (SWS) 24,000 Prior Open National INDV 19-Oct- 22-Nov- 21 21 C24 FMS MoH HMIS specialist (HSS) 24,000 Prior Open National INDV 19-Oct- 22-Nov- 21 21 C25 FMS MoH HMIS specialist (GAL) 24,000 Prior Open National INDV 19-Oct- 22-Nov- 21 21 C26 FMS MoH HMIS specialist (JUB) 24,000 Prior Open National INDV 19-Oct- 22-Nov- 21 21 3 S.N Contract Title, Description and Estimate Revi Market Metho Expect Date of o Category d Cost ew Approach d ed date contract (US$) by (Open- (QCBS, of award Bank National/ LCBCS, bid/pro Limited etc.) QBS, posal DS openin g C27 HMIS TA (firm) 400,000 Prior Open QCBS 28-Nov- 01-Jan-22 International 21 C28 PCIU Contract management specialist 43,488 Prior Open National INDV 28-Jun- 01-Aug- (3no.) 21 21 C29 PCIU M&E specialist 43,488 Prior Open National INDV 28-Jun- 01-Aug- 21 21 C30 HMIS expert in the HMIS Unit 43,488 Prior Open National INDV 18-Sep- 22-Oct-21 21 C31 Contract management TA (firm) 100,000 Prior Open QCBS 19-Oct- 22-Nov- International 21 21 C32 Regional-level health staff in 5 regions 16,000 Prior Open National INDV 19-Oct- 22-Nov- (5no.) 21 21 C33 Health financing/RMET specialist 43,488 Prior Open National INDV 19-Aug- 22-Sep- 21 21 C34 Public Private Partnerships (PPP) 43,488 Prior Open National INDV 19-Oct- 22-Nov- Specialist 21 21 C35 Security Assessment (Firm) 300,000 Prior Open QCBS 19-Aug- 22-Sep- International 21 21 C36 Third-party monitoring contract 1,250,000 Prior Open QCBS 15-Aug- 15-Sep- International 21 21 C37 Service delivery contract (Nugaal, PL) 4,000,000 Prior Open QCBS 15-Aug- 15-Sep- International 21 21 C38 Service delivery contract (Bay, SWS) 4,000,000 Prior Open QCBS 15-Aug- 15-Sep- International 21 21 4 S.N Contract Title, Description and Estimate Revi Market Metho Expect Date of o Category d Cost ew Approach d ed date contract (US$) by (Open- (QCBS, of award Bank National/ LCBCS,bid/pro Limited etc.) QBS, posal DS openin g C39 Service delivery contract (Bakool, SWS) 4,000,000 Prior Open QCBS 15-Aug- 15-Sep- International 21 21 C40 Service delivery contract (Hiraan, 4,000,000 Prior Open QCBS 15-Aug- 15-Sep- Hirshabelle) International 21 21 C41 Service delivery contract (M.Shabelle, 1,500,000 Prior Open QCBS 15-Aug- 15-Sep- Hirshabelle)* International 21 21 Sub-Total 2 20,933,8 72 GRAND TOTAL 20,993,8 72 5 PROCUREMENT Somalia : Improving Healthcare Services in Somalia Project (“Damal Caafimaad”) PLAN General Information Country: Somalia 2021-06-30 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172031 GPN Date: 2021-09-30 Project Name: Improving Healthcare Services in Somalia Project (“Damal Caafimaad”) Loan / Credit No: / , IDA / D8620, TF / B5820 Federal Government of Somalia Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOH-FGS-043-GO-RFQ / Component 3: Project mana Request for Quota Single Stage - One E Under Imple Procurement of Office Equip IDA / D8620 gement, knowledge manage Prior Limited 35,000.00 0.00 2023-01-07 2023-06-14 2023-02-16 2023-04-17 tions nvelope mentation ment for the PCIU ment and learning SO-MOH-FGS-0058-GO-RFQ / Component 3: Project mana Request for Quota Single Stage - One E Under Revie Damal Caafimaad - Office Fur IDA / D8620 gement, knowledge manage Prior Limited 49,000.00 0.00 2023-06-18 2023-07-28 2024-01-24 tions nvelope w niture for PCIU ment and learning NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Expanding th SO-MOH-FGS-036-NC-DIR / P e coverage of high-impact h rovision of Security Risk Asse IDA / D8620 Prior Direct Selection Direct 500,000.00 0.00 Canceled 2021-11-01 2021-11-06 2021-12-21 2022-12-21 ealth and nutrition services i ssment Services n select geographic areas SO-MOH-FGS-043-NC-RFB / Component 1: Expanding th Delivering the Essential Pack e coverage of high-impact h Open - Internationa Single Stage - One E Under Imple IDA / D8620 Prior Request for Bids 12,000,000.00 0.00 2022-12-23 2022-12-30 2022-12-28 2023-01-06 2023-02-08 2023-02-12 2023-03-10 2023-05-27 2023-04-14 2025-04-13 age of Health Services in Nug ealth and nutrition services i l nvelope mentation al Region - Puntland State of n select geographic areas Somalia SO-MOH-FGS-044-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Open - Internationa Single Stage - One E Under Imple IDA / D8620 Prior Request for Bids 12,000,000.00 0.00 2022-12-23 2022-12-30 2022-12-28 2023-01-18 2023-02-08 2023-02-20 2023-03-10 2023-05-27 2023-04-14 2025-04-13 of Health Services in Hiiraan ealth and nutrition services i l nvelope mentation Region - Hirshabelle State of n select geographic areas Somalia SO-MOH-FGS-045-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Open - Internationa Single Stage - One E Under Imple IDA / D8620 Prior Request for Bids 4,500,000.00 0.00 2022-12-23 2022-12-30 2022-12-28 2023-01-16 2023-02-08 2023-02-18 2023-03-10 2023-05-27 2023-04-14 2025-04-13 of Health Services in Middle ealth and nutrition services i l nvelope mentation Shabelle Region - Hirshabelle n select geographic areas State of Somalia SO-MOH-FGS-046-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Open - Internationa Single Stage - One E IDA / D8620 Prior Request for Bids 12,000,000.00 0.00 Canceled 2022-12-23 2022-12-30 2022-12-28 2023-01-06 2023-02-08 2023-02-12 2023-03-10 2023-04-14 2025-04-13 of Health Services in Bay Reg ealth and nutrition services i l nvelope ion - South West State of So n select geographic areas malia SO-MOH-FGS-047-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Open - Internationa Single Stage - One E IDA / D8620 Prior Request for Bids 12,000,000.00 0.00 Canceled 2022-12-23 2022-12-30 2022-12-28 2023-01-06 2023-02-08 2023-02-12 2023-03-10 2023-04-14 2025-04-13 of Health Services in Bakool ealth and nutrition services i l nvelope Region - South West State of n select geographic areas Somalia SO-MOH-FGS-0054-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Single Stage - One E Under Imple IDA / D8620 Prior Request for Bids Limited 15,000,000.00 0.00 2023-06-02 2023-06-12 2023-06-18 2023-06-15 2023-06-21 2023-07-06 2023-07-25 2025-05-30 of Health Services in Bay Reg ealth and nutrition services i nvelope mentation ion n select geographic areas SO-MOH-FGS-0055-NC-RFB / Component 1: Expanding th Delivery of Essential Package e coverage of high-impact h Single Stage - One E Under Imple IDA / D8620 Prior Request for Bids Limited 15,000,000.00 0.00 2023-06-02 2023-06-12 2023-06-18 2023-06-15 2023-06-20 2023-07-05 2023-07-24 2025-05-30 of Health Services in Bakool ealth and nutrition services i nvelope mentation Region n select geographic areas CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Expanding th SO-MOH-FGS-014-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Under Implement Provision of Third Party Monit IDA / D8620 Prior 5,000,000.00 0.00 2021-09-28 2022-02-09 2021-10-08 2022-03-14 2021-10-27 2023-06-14 2021-11-24 2021-11-29 2021-12-14 2022-01-04 2023-01-04 ealth and nutrition services i Based Selection l ation oring Services n select geographic areas Component 1: Expanding th SO-MOH-FGS-013-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Provision of Security Assess IDA / D8620 Prior 500,000.00 0.00 Canceled 2021-09-28 2021-10-08 2021-10-27 2021-11-24 2021-11-29 2021-12-14 2022-01-04 2023-01-04 ealth and nutrition services i Based Selection l ment Services n select geographic areas Component 1: Expanding th SO-MOH-FGS-017-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Service delivery contract (Ba IDA / D8620 Prior 12,000,000.00 0.00 Canceled 2021-10-01 2022-02-09 2021-10-11 2021-10-31 2021-11-28 2021-12-03 2021-12-18 2022-01-08 2025-01-07 ealth and nutrition services i Based Selection l kool, South West State) n select geographic areas Component 1: Expanding th SO-MOH-FGS-015-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Service delivery contract (Nu IDA / D8620 Prior 12,000,000.00 0.00 Canceled 2021-10-01 2022-02-22 2021-10-11 2022-03-10 2021-10-31 2021-11-28 2021-12-03 2021-12-18 2022-01-08 2025-01-07 ealth and nutrition services i Based Selection l gaal, Puntland) n select geographic areas Page 1 Component 1: Expanding th SO-MOH-FGS-018-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Service delivery contract (Hir IDA / D8620 Prior 12,000,000.00 0.00 Canceled 2021-10-01 2022-02-22 2021-10-11 2022-03-10 2021-10-31 2021-11-28 2021-12-03 2021-12-18 2022-01-08 2025-01-07 ealth and nutrition services i Based Selection l aan, Hirshabelle) n select geographic areas Component 1: Expanding th SO-MOH-FGS-016-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Service delivery contract (Ba IDA / D8620 Prior 12,000,000.00 0.00 Canceled 2021-10-01 2022-02-22 2021-10-11 2022-03-10 2021-10-31 2021-11-28 2021-12-03 2021-12-18 2022-01-08 2025-01-07 ealth and nutrition services i Based Selection l y, South West State) n select geographic areas Component 1: Expanding th SO-MOH-FGS-019-CS-QCBS / e coverage of high-impact h Quality And Cost- Open - Internationa Service delivery contract (M. IDA / D8620 Prior 4,500,000.00 0.00 Canceled 2021-10-01 2022-02-22 2021-10-11 2022-03-10 2021-10-31 2021-11-28 2021-12-03 2021-12-18 2022-01-08 2025-01-07 ealth and nutrition services i Based Selection l Shabelle, Hirshabelle) n select geographic areas INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Project mana SO-MOH-FGS-0002-CS-INDV Individual Consult / gement, knowledge manage Prior Open 40,000.00 0.00 Signed 2021-07-01 2021-07-27 2021-08-19 2021-10-31 2021-09-09 2021-12-13 2021-10-14 2022-10-13 / PCIU Legal Advisor ant Selection ment and learning SO-MOH-FGS-0004-CS-INDV Component 3: Project mana Individual Consult / PIU Communications Specia IDA / D8620 gement, knowledge manage Prior Open 43,488.00 51,000.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-12-21 2021-09-18 2022-02-09 2021-10-23 2022-02-24 2022-10-22 ant Selection list ment and learning SO-MOH-FGS-0008-CS-INDV Component 3: Project mana Individual Consult / PCIU Contract Management IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-11-03 2021-09-18 2021-12-09 2021-10-23 2021-12-28 2022-10-22 ant Selection Specialist no. 01 ment and learning Component 3: Project mana SO-MOH-FGS-0010-CS-INDV Individual Consult IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-12-21 2021-09-18 2022-01-14 2021-10-23 2022-01-28 2022-10-22 / PCIU- HMIS Specialist ant Selection ment and learning SO-MOH-FGS-0011-CS-INDV Component 3: Project mana Individual Consult / PCIU- Contract Management IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-12-09 2021-09-18 2021-12-24 2021-10-23 2022-01-11 2022-10-22 ant Selection Specialist No. 2 ment and learning Component 3: Project mana SO-MOH-FGS-0009-CS-INDV Individual Consult IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-11-20 2021-09-18 2021-12-09 2021-10-23 2021-12-28 2022-10-22 / PCIU M&E Specialist ant Selection ment and learning Component 3: Project mana SO-MOH-FGS-0003-CS-INDV Individual Consult IDA / D8620 gement, knowledge manage Prior Open 80,000.00 54,360.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-10-31 2021-09-18 2021-12-08 2021-10-23 2021-12-28 2022-10-22 / PCIU Security Advisor ant Selection ment and learning SO-MOH-FGS-0001-CS-INDV Component 3: Project mana Individual Consult / PCIU Senior Programme Co IDA / D8620 gement, knowledge manage Prior Open 91,680.00 93,980.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-10-20 2021-09-18 2021-12-06 2021-10-23 2022-01-01 2022-10-22 ant Selection ordinator ment and learning SO-MOH-FGS-0007-CS-INDV Component 3: Project mana Individual Consult / PCIU Social Safeguards Spe IDA / D8620 gement, knowledge manage Prior Open 52,800.00 51,000.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-11-03 2021-09-18 2021-12-08 2021-10-23 2021-12-28 2022-10-22 ant Selection cialist ment and learning SO-MOH-FGS-0005-CS-INDV Component 3: Project mana Individual Consult / PCIU Environmental Safegu IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-11-18 2021-09-18 2021-12-21 2021-10-23 2021-12-28 2022-10-22 ant Selection ards Specialist ment and learning Component 3: Project mana SO-MOH-FGS-0006-CS-INDV Individual Consult IDA / D8620 gement, knowledge manage Prior Open 43,488.00 51,000.00 Signed 2021-07-10 2021-07-21 2021-08-28 2021-11-02 2021-09-18 2021-12-07 2021-10-23 2021-12-28 2022-10-22 / PCIU- GBV Specialist ant Selection ment and learning SO-MOH-FGS-0012-CS-INDV Component 3: Project mana Individual Consult / PCIU- Contract Management IDA / D8620 gement, knowledge manage Prior Open 43,488.00 49,920.00 Signed 2021-07-10 2021-07-16 2021-08-28 2021-12-07 2021-09-18 2021-12-24 2021-10-23 2022-01-11 2022-10-22 ant Selection Specialist No. 3 ment and learning SO-MOH-FGS-020-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Project Manager (Puntla IDA / D8620 gement, knowledge manage Prior Open 48,000.00 0.00 2021-09-21 2021-11-04 2021-10-17 2022-09-06 2021-10-31 2022-10-18 2021-11-24 2022-11-23 ant Selection ation nd) ment and learning SO-MOH-FGS-022-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Social/ GBV Specialist ( IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 2021-09-21 2021-10-05 2021-10-17 2022-09-06 2021-10-31 2022-12-22 2021-11-24 2022-11-23 ant Selection ation Puntland) ment and learning SO-MOH-FGS-024-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Project Manager (South IDA / D8620 gement, knowledge manage Prior Open 48,000.00 0.00 2021-09-21 2021-11-04 2021-10-17 2022-11-26 2021-10-31 2022-12-30 2021-11-24 2022-11-23 ant Selection ation West State) ment and learning SO-MOH-FGS-026-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Social/ GBV Specialist ( IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 2021-09-21 2021-10-05 2021-10-17 2022-10-17 2021-10-31 2022-12-22 2021-11-24 2022-11-23 ant Selection ation South West State) ment and learning SO-MOH-FGS-028-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Project Manager (Hirsha IDA / D8620 gement, knowledge manage Prior Open 48,000.00 0.00 2021-09-21 2021-11-04 2021-10-17 2022-08-23 2021-10-31 2022-10-18 2021-11-24 2022-11-23 ant Selection ation belle) ment and learning SO-MOH-FGS-030-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Social/ GBV Specialist ( IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 2021-09-21 2021-10-05 2021-10-17 2022-10-06 2021-10-31 2022-10-28 2021-11-24 2022-11-23 ant Selection ation Hirshabelle) ment and learning SO-MOH-FGS-032-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Project Manager (Galmu IDA / D8620 gement, knowledge manage Prior Open 48,000.00 0.00 2021-09-21 2021-11-04 2021-10-17 2022-07-31 2021-10-31 2022-10-18 2021-11-24 2022-11-23 ant Selection ation dug) ment and learning SO-MOH-FGS-034-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Project Manager (Jubbal IDA / D8620 gement, knowledge manage Prior Open 48,000.00 0.00 2021-09-21 2021-11-04 2021-10-17 2022-09-06 2021-10-31 2022-10-18 2021-11-24 2022-11-23 ant Selection ation and) ment and learning SO-MOH-FGS-021-CS-INDV / Component 3: Project mana Individual Consult Under Implement PMT Environmental Specialist IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 2021-09-21 2021-10-05 2021-10-17 2022-09-06 2021-10-31 2022-10-18 2021-11-24 2022-11-23 ant Selection ation (Puntland) ment and learning SO-MOH-FGS-031-CS-INDV / Component 2: Strengthening Individual Consult Under Implement FMS MoH HMIS specialist (Hir IDA / D8620 Government’s stewardship t Prior Open 24,000.00 0.00 2021-09-27 2022-01-06 2021-10-23 2022-10-02 2021-11-06 2022-10-28 2021-11-30 2022-11-29 ant Selection ation shabelle) o enhance service delivery Page 2 SO-MOH-FGS-029-CS-INDV / Component 3: Project mana Individual Consult PMT Environmental Specialist IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 Signed 2021-09-21 2021-10-05 2021-10-17 2022-10-02 2021-10-31 2022-11-15 2021-11-24 2022-11-23 ant Selection (Hirshabelle) ment and learning SO-MOH-FGS-023-CS-INDV / Component 2: Strengthening Individual Consult Under Implement FMS MoH HMIS specialist (Pu IDA / D8620 Government’s stewardship t Prior Open 32,000.00 0.00 2021-09-27 2022-01-06 2021-10-23 2022-09-06 2021-11-06 2022-12-22 2021-11-30 2022-11-29 ant Selection ation ntland) o enhance service delivery SO-MOH-FGS-027-CS-INDV / Component 2: Strengthening Individual Consult Under Implement FMS MoH HMIS specialist (So IDA / D8620 Government’s stewardship t Prior Open 24,000.00 0.00 2021-09-27 2022-01-06 2021-10-23 2022-11-24 2021-11-06 2022-12-24 2021-11-30 2022-11-29 ant Selection ation uth West State) o enhance service delivery SO-MOH-FGS-025-CS-INDV / Component 3: Project mana Individual Consult PMT Environmental Specialist IDA / D8620 gement, knowledge manage Prior Open 32,000.00 0.00 Canceled 2021-09-24 2021-10-05 2021-10-20 2022-11-23 2021-11-03 2021-11-27 2022-11-26 ant Selection (South West State) ment and learning SO-MOH-FGS-033-CS-INDV / Component 2: Strengthening Individual Consult Under Implement FMS MoH HMIS specialist (Gal IDA / D8620 Government’s stewardship t Prior Open 24,000.00 0.00 2021-09-27 2022-01-06 2021-10-23 2022-07-31 2021-11-06 2022-10-18 2021-11-30 2022-11-29 ant Selection ation mudug) o enhance service delivery SO-MOH-FGS-035-CS-INDV / Component 2: Strengthening Individual Consult Under Implement FMS MoH HMIS specialist (Jub IDA / D8620 Government’s stewardship t Prior Open 24,000.00 0.00 2021-09-27 2022-01-06 2021-10-23 2022-10-02 2021-11-06 2022-10-29 2021-11-30 2022-11-29 ant Selection ation baland) o enhance service delivery SO-MOH-FGS-037-CS-INDV / Component 2: Strengthening Individual Consult FGS Health Financing Special IDA / D8620 Government’s stewardship t Prior Open 43,488.00 49,920.00 Signed 2021-11-05 2021-11-04 2021-12-24 2022-06-30 2022-01-14 2022-08-01 2022-02-18 2022-08-16 2023-02-17 ant Selection ist o enhance service delivery Component 1: Expanding th SO-MOH-FGS-037-CS-CDS / P e coverage of high-impact h rovision of Security Risk Asse IDA / D8620 Prior Direct Selection Direct 900,000.00 927,000.00 Signed 2021-11-30 2021-12-06 2021-12-10 2022-01-11 2022-02-13 2022-08-23 2022-08-12 ealth and nutrition services i ssment Services n select geographic areas SO-MOH-FGS-038-CS-INDV / Component 3: Project mana Individual Consult Under Implement Senior Contract Management IDA / D8620 gement, knowledge manage Prior Open 182,000.00 0.00 2022-07-04 2022-08-31 2022-08-22 2022-09-01 2022-10-06 2023-10-05 ant Selection ation Technical Advisor ment and learning SO-MOH-FGS-0040-CS-INDV Component 3: Project mana Individual Consult / Procurement Specialist No. IDA / D8620 gement, knowledge manage Prior Open - National 51,000.00 0.00 Canceled 2022-09-08 2022-10-27 2022-11-17 2022-12-22 2023-12-22 ant Selection 2 ment and learning SO-MOH-FGS-039-CS-INDV / Component 2: Strengthening Individual Consult Under Implement Health Financing Specialist N IDA / D8620 Government’s stewardship t Prior Direct - National 51,000.00 0.00 2022-09-07 2022-12-30 2022-09-17 2023-01-10 2022-09-27 2023-01-12 2022-10-28 2023-10-28 ant Selection ation o. 2 o enhance service delivery SO-MOH-FGS-041-CS-INDV / Component 3: Project mana Individual Consult Direct - Internation Under Implement Public Financial Management IDA / D8620 gement, knowledge manage Prior 190,000.00 0.00 2022-11-25 2022-12-04 2022-12-07 2022-12-21 2022-12-12 2022-12-27 2022-12-31 2023-12-31 ant Selection al ation (PFM) Specialist ment and learning Component 2: Strengthening SO-MOH-FGS-042-CS-INDV / Individual Consult Direct - Internation Under Implement IDA / D8620 Government’s stewardship t Prior 190,000.00 0.00 2022-11-25 2022-12-06 2022-12-06 2022-12-19 2022-12-11 2023-01-05 2022-12-31 2023-12-31 Procurement Specialist ant Selection al ation o enhance service delivery Component 2: Strengthening SO-MOH-FGS-048-CS-INDV / Individual Consult Under Implement TF / B5820 Government’s stewardship t Prior Limited 51,000.00 0.00 2023-01-18 2023-02-10 2023-01-23 2023-04-02 2023-02-13 2023-06-08 2023-03-20 2024-03-19 HMIS-ICT Specialist ant Selection ation o enhance service delivery SO-MOH-FGS-050-CS-INDV / Component 3: Project mana Individual Consult PMT Environmental Specialist IDA / D8620 gement, knowledge manage Prior Open - National 46,200.00 0.00 Under Review 2023-04-05 2023-05-08 2023-05-14 2023-06-04 2023-07-02 2024-07-01 ant Selection -South West State- (Readvert ment and learning ised) SO-MOH-FGS-051-CS-INDV / Component 2: Strengthening Individual Consult Under Implement Public Private Partnership Sp IDA / D8620 Government’s stewardship t Prior Open - National 55,000.00 0.00 2023-04-05 2023-06-08 2023-05-14 2023-06-04 2023-07-09 2024-07-08 ant Selection ation ecialist o enhance service delivery SO-MOH-FGS-049-CS-INDV / Component 2: Strengthening Individual Consult Open - Internationa Under Implement HMIS International Consultan TF / B5820 Government’s stewardship t Prior 190,000.00 0.00 2023-04-05 2023-05-24 2023-06-14 2023-07-19 2024-07-18 ant Selection l ation t o enhance service delivery Component 3: Project mana SO-MOH-FGS-052-CS-INDV / Individual Consult Under Implement IDA / D8620 gement, knowledge manage Prior Open - National 52,200.00 0.00 2023-06-05 2023-06-06 2023-07-14 2023-08-04 2023-09-08 2024-09-07 PMT Project Manager (BRA) ant Selection ation ment and learning Component 3: Project mana SO-MOH-FGS-053-CS-INDV / Individual Consult Under Implement IDA / D8620 gement, knowledge manage Prior Open - National 46,000.00 0.00 2023-06-05 2023-06-06 2023-07-14 2023-08-04 2023-09-08 2024-09-07 PMT HMIS Specialist (BRA) ant Selection ation ment and learning Component 3: Project mana SO-MOH-FGS-0056-CS-INDV Individual Consult Open - Internationa Under Implement IDA / D8620 gement, knowledge manage Prior 190,000.00 0.00 2023-06-02 2023-06-12 2023-07-11 2023-07-21 2023-08-09 2024-08-08 / Procurement Specialist ant Selection l ation ment and learning SO-MOH-FGS-0057-CS-INDV Component 3: Project mana Individual Consult Under Implement / PCIU Social Safeguard Speci IDA / D8620 gement, knowledge manage Prior Open - National 54,000.00 0.00 2023-06-02 2023-06-06 2023-07-11 2023-07-21 2023-08-09 2024-08-08 ant Selection ation alist ment and learning Page 3 PROCUREMENT PLAN (Textual Part) Project information: Papua New Guinea (PNG), PNG COVID-19 Emergency Response Project, P-173834 Project Implementation agency: National Department of Health (NDoH) Date of the Procurement Plan: April 3, 2020 Period covered by this Procurement Plan: April 3 2020 – to April 2, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Not Applicable. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable; Works: Not Applicable PROCUREMENT Papua New Guinea : Papua New Guinea COVID-19 Emergency Response Project PLAN General Information Country: Papua New Guinea 2020-04-14 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173834 GPN Date: 2020-04-21 Project Name: Papua New Guinea COVID-19 Emergency Response Project Loan / Credit No: / , IDA / 66140, IDA / 67850 National Department of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-168433-GO-RFQ / Managing Implementation a Request for Quota Single Stage - One E / Post Limited 10,000.00 0.00 Canceled 2020-05-02 2020-05-27 2020-11-23 IT Equipment for the PCU nd Monitoring & Evaluation tions nvelope PG-NDOH-168430-GO-UN / D irect Selection of UNOPS for " delivery of outputs", includin Health Systems Strengtheni UN Agencies (Dire g but not limited to: modular IDA / 66140 Post Direct 10,490,139.00 10,490,139.00 Signed 2020-04-17 2020-04-13 2020-04-22 2020-04-16 2020-05-07 2020-04-25 2023-04-30 ng ct) isolation facilities, medical eq uipment and other medical c onsumables, and specimen tr ansportation PG-NDOH-338787-GO-RFQ / Managing Implementation a Request for Quota Single Stage - One E IDA / 67850 Post Limited 7,000.00 0.00 Canceled 2023-02-08 2023-04-05 2023-10-02 Laptops nd Monitoring & Evaluation tions nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-168432-NC-UN / D irect Selection UNICEF for "d elivery of outputs", including Preparedness for COVID-19 UN Agencies (Dire but not limited to: delivering IDA / 66140 Post Direct 8,233,861.00 8,294,910.77 Signed 2020-04-17 2020-04-13 2020-04-22 2020-04-17 2020-05-06 2020-05-01 2023-04-09 Containment and Mitigation ct) diagnostic as well as social b ehavioral change communica tions training (inc related logi stics), and some goods (such as PPE). CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-NDOH-168421-CS-INDV / Managing Implementation a Individual Consult Financial Management Speci / Post Limited 216,000.00 0.00 Canceled 2020-05-04 2020-06-18 2020-05-09 2020-05-30 2020-06-19 2023-04-30 nd Monitoring & Evaluation ant Selection alist (part time) PG-NDOH-168424-CS-INDV / Managing Implementation a Individual Consult Monitoring & Evaluation Spec / Post Limited 180,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-05-30 2020-06-19 2023-04-30 nd Monitoring & Evaluation ant Selection ialist (part time) PG-NDOH-168425-CS-INDV / Managing Implementation a Individual Consult International Procurement Sp IDA / 66140 Post Direct 180,000.00 123,885.00 Completed 2020-04-24 2020-06-26 2020-05-04 2020-06-29 2020-05-14 2020-06-29 2020-05-24 2020-10-26 2023-04-30 nd Monitoring & Evaluation ant Selection ecialist (part time) PG-NDOH-168426-CS-INDV / Managing Implementation a Individual Consult International Environmental IDA / 66140 Post Limited 120,000.00 120,064.60 Completed 2020-05-15 2020-04-17 2020-05-20 2020-04-21 2020-06-10 2020-06-01 2020-06-30 2021-06-09 2023-04-15 nd Monitoring & Evaluation ant Selection and Social Safeguards Specia list (part time) PG-NDOH-168423-CS-INDV / Managing Implementation a Individual Consult Environmental Safeguard Sp IDA / 66140 Post Limited 180,000.00 0.00 Canceled 2020-05-04 2020-05-09 2020-05-30 2020-06-19 2023-04-30 nd Monitoring & Evaluation ant Selection ecialist (part time) PG-NDOH-176430-CS-INDV / Environmental, Social, Health Managing Implementation a Individual Consult IDA / 66140 Post Limited 180,000.00 114,961.45 Completed 2020-06-09 2020-06-01 2020-06-14 2020-06-16 2020-07-05 2020-07-17 2020-08-09 2020-06-29 2022-05-31 , Safety and Community Eng nd Monitoring & Evaluation ant Selection agement Specialist PG-NDOH-193728-CS-INDV / Managing Implementation a Individual Consult IDA / 66140 Post Open 200,000.00 299,689.60 Signed 2020-09-14 2020-09-20 2020-10-17 2022-02-17 2020-10-22 2022-03-07 2020-11-01 2022-05-10 2022-11-01 2023-05-03 Deputy Project Coordinator nd Monitoring & Evaluation ant Selection PG-NDOH-303681-CS-INDV / Managing Implementation a Individual Consult Direct - Internation IDA / 66140 Post 80,000.00 0.00 Canceled 2022-07-18 2022-07-28 2022-08-18 2022-08-28 2023-04-30 Financial Management Speci nd Monitoring & Evaluation ant Selection al alist PG-NDOH-308745-CS-INDV / Managing Implementation a Individual Consult IDA / 66140 Post Limited 36,000.00 0.00 Completed 2022-08-17 2022-08-23 2022-08-27 2022-10-26 2022-09-06 2023-01-10 2022-09-16 2023-05-05 Environmental Assessment S nd Monitoring & Evaluation ant Selection pecialist PG-NDOH-365532-CS-CDS / I Managing Implementation a Direct - Internation Under Implement IDA / 66140 Post Direct Selection 219,126.41 0.00 2023-06-07 2023-06-08 2023-06-17 2023-08-21 2024-02-17 nternational Procurement Sp nd Monitoring & Evaluation al ation ecialist Page 1 PG-NDOH-366185-CS-INDV / Managing Implementation a Individual Consult Under Implement Environmental, Social, and H IDA / 66140 Post Direct - National 70,000.00 0.00 2023-06-16 2023-06-17 2023-06-26 2023-07-17 2023-08-21 2024-10-31 nd Monitoring & Evaluation ant Selection ation ealth and Safety (ESHS) Spec ialist PG-NDOH-367257-CS-INDV / Managing Implementation a Individual Consult Direct - Internation Under Implement IDA / 66140 Prior 737,710.55 0.00 2023-06-23 2023-06-22 2023-07-03 2023-06-26 2023-07-23 2023-06-28 2023-08-11 2024-10-31 Project Coordinator nd Monitoring & Evaluation ant Selection al ation Page 2 TOGO PLAN DE PASSATION DES MARCHES SI PROJET : PROJET D’AMELIORATION DE LA QUALITE ET DE L’EQUITE DE L’EDUCATION DE BASE(PAQEEB) No d’identification du projet [P172674] PLAN DE PASSATION DE MARCHES SIMPLIFIE VERSION N° 1 I. GENERAL 1. Informations sur le Projet Emprunteur : République Togolaise Ministère : Ministère des enseignements primaire, Responsable secondaire, technique et de l’artisanat Nom du Projet : PROJET D’AMELIORATION DE LA QUALITE ET DE L’EQUITE DE L’EDUCATION DE BASE Identification : P172674 IDA N° Accord de Crédit/Accord de Don No… Structure chargée Unité de coordination du projet de la mise en œuvre du projet 2. Date d’approbation par la Banque du plan de passation de marchés : 3. Date de publication de l’Avis Général de Passation des Marchés : [A insérer plus tard 4. Période couverte par la Plan de Passation des Marchés : [A insérer dès à présent]…………… 5. Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System) : Substantiel Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Novembre 2020) (“Règlement de Passation des Marchés”), le Système 2 électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la loi No 2009-013 du 30 juin 2009 relative aux Marchés Publics et Délégation de Service Public, le Décret Nº 2009-277/PR du 11 novembre 2009 portant Code des Marchés Publics et Délégation de Service Public, et les textes d’application y afférents, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : • Le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/les proposants présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection et l’audit ; • Le droit de la Banque d’examiner le dossier et les activités de passation des marchés. 3 Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés ne s’applique pas. Seuils pour approches et méthodes de passation des marchés – Travaux, Fournitures, et Services non-consultant ; Approches et méthode de passation des marchés (US$) Catégorie Ouverte Ouverte Demande de Internationale Nationale cotation (DC) (AOI) (AON) Travaux ≥ 5 000 000 <5 000 000 ≤ 200 000 Fournitures et Services ≥ 500 000 <500 000 ≤ 100 000 non-consultant 4 II. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Montants estimatifs des contrats en Catégories de marchés Observations millions de dollars américains Travaux (incluant clé à main, Fourniture et Installation, et les >= 10 Partenariat Public - Privé -PPP) Biens, Système d’Information et de Services autres que les Services >= 2 intellectuels Travaux (incluant clé à main, Fourniture et Installation, et les >= 10 Les justifications de Contrats à Partenariat Public - l’entente directe passer par Privé -PPP) devront être jointes entente Biens, Système et approuvées avec directe d’Information et de PPM Services autres que >= 2 les Services intellectuels 2. Pré qualification : Sans objet. 3. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre- valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). Liste des marchés avec les méthodes de passation et les dates de mise en œuvre : Travaux 1 2 3 4 5 6 7 8 9 Revue de Méthode Date de Comment Ref. la Re Coût de lanceme aires/Fin Com Approche du Banque f. Description estimatif passatio nt de la de pos marché (a priori/a N° (US$) n des procédu prestatio ante posteriori marchés re ns ) Activités à l’étape projet Coût total en US$ 6 Fournitures et services autres que les services de consultants 1 2 3 4 5 6 7 8 9 Revue de Métho la Date de Ref. de de Commenta Coût Banque lancemen Ref. Com passati Approche du ires/Fin de Description estimatif (a t de la N° posa on des marché prestation (US$) priori/a procédur nte march s posterior e és i) Activités à l’étape projet Coût total en US$ III. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés Décisions de sélection sujette à la revue préalable de la Banque comme indiqué dans Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Seuils de revue a priori Méthode de Montants estimatifs des sélection/Catégories Observations contrats en millions de de marchés dollars américains Méthode compétitive/Firmes de >= 1 consultants Entente Les justifications pour directe/firmes de >= 1 l’entente directe consultants devront être jointes et 7 Entente approuvées avec le directe/Consultants >= 0.3 PPM individuel Méthode Compétitive (Comparaison de CVs) >= 0.3 / Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales : La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux en conformité avec les dispositions des Règlement de Passation des marchés., et l’Emprunteur ne procède pas à une publication dans UNDB. 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultant est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission ; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels telles des situations d’urgence en conformité au Règlement de Passation des marchés. Marchés de Services de Consultants 1. 2. 3. 4. 5. 6. 7. 8. 9. Revue de la Date de Ref Ref. Coût Méthode Banque lancemen Commentaires Approche . Composa Description des missions estimatif de (a t de la /Fin de du marché N° nte (US$) sélection priori/a procédur prestations posterio e ri) Activités à l’étape projet Coût total en US$ Lexique des Sigles et Abréviations PPM : Plan de Passation des Marchés AOI : Appel d’Offres International AON : Appel d’Offres National DC : Demande de Cotations SQC Sélection fondée sur les Qualifications des : Consultants SMC : Sélection au Moindre Coût CI : Consultant Individuel ED : Sélection Directe ou Entente Directe A Revue a posteriori : posteriori A Priori : Revue a priori PPM : Plan de Passation des Marchés DNCMP Direction Nationale de Contrôle des : Marchés Publics ARMP : Autorité de Régulation des Marchés Publics PROCUREMENT Togo : Togo, Improving Quality and Equity of Basic Education Project PLAN General Information Country: Togo 2022-04-12 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172674 GPN Date: 2022-03-20 Project Name: Togo, Improving Quality and Equity of Basic Education Project Loan / Credit No: IDA / D9010, TF / B6287 Project Coordination Unit - PAQEEB Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned TG-PCU-PAQEEB-356614-CW Component 1: Improving Qu Request for Quota -RFQ / Travaux de réfection d Request for Quota Single Stage - One E Pending Imp 2023-10-3 IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 313,540.00 0.00 2023-05-30 2023-08-01 es Ecoles Normales de Forma tions nvelope lementation 0 ng PD) tion des Professeurs d’Ecoles (ENFPE) de Notsè TG-PCU-PAQEEB-348838-CW National Procure -RFB / Travaux de réfection d Component 1: Improving Qu ment Document - Request for Quota Single Stage - One E Pending Imp 2023-11-0 es Ecoles Normales de Forma IDA / D9010 ality of Teaching and Learni Post Limited 1 Envelope proce 335,195.00 0.00 2023-05-30 2023-08-08 tions nvelope lementation 6 tion des Professeurs d’Ecoles ng ss (Non Bank-SPD (ENFPE) de Dapaong et de M ) ango TG-PCU-PAQEEB-356605-CW Component 1: Improving Qu Request for Quota -RFQ / Travaux de réfection d Request for Quota Single Stage - One E Pending Imp 2023-08-1 IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 248,450.00 0.00 2023-05-30 2023-08-01 es Ecoles Normales de Forma tions nvelope lementation 0 ng PD) tion des Professeurs d’Ecoles (ENFPE) d'Adéta TG-PCU-PAQEEB-356608-CW Component 1: Improving Qu Request for Quota -RFQ / Travaux de réfection d Request for Quota Single Stage - One E Pending Imp 2023-10-3 IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 257,770.00 0.00 2023-05-30 2023-08-01 es Ecoles Normales de Forma tions nvelope lementation 0 ng PD) tion des Professeurs d’Ecoles (ENFPE) de Tabligbo TG-PCU-PAQEEB-356613-CW -RFQ / Travaux de réfection d Component 1: Improving Qu Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-3 es Ecoles Normales de Forma IDA / D9010 ality of Teaching and Learni Post Limited tions (Non Bank-S 252,895.00 0.00 2023-05-30 2023-08-01 tions nvelope lementation 0 tion des Professeurs d’Ecoles ng PD) (ENFPE) de Sotouboua GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285558-GO -RFB / Acquisition de tablette Component 3: Strengthening s pour les DRE, inspections (i Single Stage - One E IDA / D9010 system management and re Post Request for Bids Open - National 340,000.00 0.00 Signed 2022-06-15 2022-06-20 2022-06-20 2022-07-20 2022-07-19 2022-09-03 2022-09-13 2022-10-15 2023-01-13 nspecteurs, conseillers, char nvelope silience gés de statistique) et aux ca dres des directions centrales et de l'UCP-PAQEEB TG-PCU-PAQEEB-285564-GO -RFB / Acquisition de matériel Component 3: Strengthening Single Stage - One E informatique (vidéo projecte IDA / D9010 system management and re Post Request for Bids Open - National 180,000.00 0.00 Signed 2022-06-15 2022-07-27 2022-06-20 2022-07-20 2022-08-26 2022-09-03 2022-10-05 2023-04-23 2023-07-22 nvelope ur, PC portable) aux inspectio silience ns et DRE, cellule genre, et a ux directions centrales TG-PCU-PAQEEB-285546-GO -RFQ / Acquisition de matérie Component 3: Strengthening Single Stage - One E ls informatiques pour la mise IDA / D9010 system management and re Post Request for Bids Open - National 400,000.00 0.00 Signed 2022-06-15 2022-08-04 2022-06-20 2022-07-20 2022-12-05 2022-09-03 2023-02-15 2022-10-08 2023-02-05 nvelope en place d'une plateforme d' silience enseignement en ligne TG-PCU-PAQEEB-296639-GO -RFQ / Acquisition d'équipem ents (MICROPHONE FILAIRE, Component 2: Improve equit LECTEUR DVD EXTERNE, ÉCO able access to basic educati Request for Quota Single Stage - One E UTEURS INTRA-AURICULAIRE IDA / D9010 Post Limited 40,000.00 0.00 Canceled 2022-06-20 2022-07-29 2022-08-23 2022-11-21 on (primary and lower-secon tions nvelope S, MICRO SANS FIL, KIT ACCE dary) SSOIRES POUR MICROPHONE S, etc.…) pour la salle de pro duction de la plateforme d'en seignement en ligne TG-PCU-PAQEEB-296770-GO -RFQ / Acquisition du matérie Component 1: Improving Qu Request for Quota Single Stage - One E l informatique pour le compt IDA / D9010 ality of Teaching and Learni Post Limited 80,000.00 0.00 Signed 2022-06-15 2022-09-19 2022-08-18 2022-11-16 tions nvelope e de l’INSE, l’ENS d’Atakpam ng é et la Fast de l’Université de Kara TG-PCU-PAQEEB-285554-GO Component 3: Strengthening Open - Internationa Single Stage - One E -RFB / Acquisition de 24 véhi IDA / D9010 system management and re Post Request for Bids 1,056,000.00 0.00 Signed 2022-09-15 2022-10-21 2022-09-20 2022-10-21 2022-11-01 2022-12-01 2022-12-01 2023-02-13 2023-01-31 2023-05-01 l nvelope cules PICKUP pour les inspect silience ions TG-PCU-PAQEEB-328197-GO -RFB / Acquisition d'équipem ents (MICROPHONE FILAIRE, Component 2: Improve equit LECTEUR DVD EXTERNE, ÉCO able access to basic educati Single Stage - One E Under Imple UTEURS INTRA-AURICULAIRE IDA / D9010 Post Request for Bids Open - National 160,000.00 0.00 2022-12-15 2022-12-20 2022-12-20 2023-01-19 2023-01-23 2023-02-27 2023-03-08 on (primary and lower-secon nvelope mentation S, MICRO SANS FIL, KIT ACCE dary) SSOIRES POUR MICROPHONE S, etc.…) pour la salle de pro duction de la plateforme d'en seignement en ligne TG-PCU-PAQEEB-348484-GO -RFB / Acquisition de tablette s pour le personnel d'encadr Component 1: Improving Qu Open - Internationa Single Stage - One E Pending Impl ement, les élèves professeur IDA / D9010 ality of Teaching and Learni Post Request for Bids 1,279,990.00 0.00 2023-03-27 2023-04-03 2023-05-15 2023-06-14 2023-07-26 2023-10-24 l nvelope ementation s d'écoles et les élèves du pri ng maire pour la phase pilote de la numérisation des apprenti ssages au primaire Page 1 TG-PCU-PAQEEB-348501-GO -RFB / Acquisition de matériel s informatiques pour les élèv Component 1: Improving Qu Open - Internationa Single Stage - One E Under Imple es inspecteurs et les conseill IDA / D9010 ality of Teaching and Learni Post Request for Bids 564,560.00 0.00 2023-04-05 2023-05-26 2023-04-12 2023-05-26 2023-05-24 2023-06-23 2023-08-04 2023-08-13 l nvelope mentation ers pédagogiques, pour la Dir ng ection de l'Enseignement Sec ondaire Général (DESG), pou r le CNDP-TICE et l'ENEAS. TG-PCU-PAQEEB-307487-GO Component 3: Strengthening -RFQ / Acquisition d'un véhic Request for Quota Single Stage - One E IDA / D9010 system management and re Post Limited 50,000.00 0.00 Canceled 2022-12-10 2023-01-12 2023-02-12 2023-04-13 ule station wagon pour l'Unit tions nvelope silience é de Coordination du Projet TG-PCU-PAQEEB-353825-GO -RFQ / Acquisition de deux vé Component 3: Strengthening hicules station wagon pour l' Request for Quota Single Stage - One E Under Imple IDA / D9010 system management and re Post Limited 100,000.00 0.00 2023-05-25 2023-06-06 2023-08-03 2023-09-02 unité de coordination du proj tions nvelope mentation silience et et de la Direction de la Pla nification de statistiques et d e suivi-évaluation TG-PCU-PAQEEB-353828-GO Component 2: Improve equit -RFQ / Acquisition et installati able access to basic educati Request for Quota Single Stage - One E Pending Impl IDA / D9010 Post Limited 60,000.00 0.00 2023-05-30 2023-08-15 2023-10-14 on de dispositifs de visioconf on (primary and lower-secon tions nvelope ementation érence dans les 6 ENFPE et l dary) a DPIP TG-PCU-PAQEEB-354335-GO Component 1: Improving Qu Request for Quota Single Stage - One E -RFQ / Acquisition de matérie IDA / D9010 ality of Teaching and Learni Post Limited 17,500.00 0.00 Canceled 2023-04-25 2023-06-20 2023-07-20 tions nvelope l de géométrie au profit des ng ENFPE TG-PCU-PAQEEB-363225-GO -RFB / Acquisition et distribut Component 1: Improving Qu Open - Internationa Single Stage - One E Pending Impl ion des manuels et guides sc TF / B6287 ality of Teaching and Learni Prior Request for Bids 5,000,000.00 0.00 2023-06-05 2023-06-10 2023-07-22 2023-08-21 2023-10-02 2023-12-31 l nvelope ementation olaires pour les préscolaires ng section 1 et 2, et des cours p réparatoires 1 et 2 TG-PCU-PAQEEB-367783-GO Component 1: Improving Qu Request for Quota Single Stage - One E Pending Impl -RFQ / Acquisition de matérie IDA / D9010 ality of Teaching and Learni Post Limited 17,500.00 0.00 2023-07-05 2023-09-06 2024-01-04 tions nvelope ementation l de géométrie au profit des ng ENFPE NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285027-NC- Component 1: Improving Qu Request for Quota Single Stage - One E Pending Impl RFQ / Reproduction des guid TF / B6287 ality of Teaching and Learni Post Limited 17,000.00 0.00 2022-05-30 2022-08-17 2022-10-16 tions nvelope ementation es de cours pour la formation ng des enseignants TG-PCU-PAQEEB-285496-NC- Component 3: Strengthening Request for Quota Single Stage - One E Under Imple RFQ / Reproduction des guid IDA / D9010 system management and re Post Limited 50,000.00 0.00 2022-07-25 2022-07-18 2022-09-19 2023-03-18 tions nvelope mentation es illustrés pour les formatio silience ns FGB TG-PCU-PAQEEB-285005-NC- Component 1: Improving Qu RFQ / Impression des module Request for Quota Single Stage - One E IDA / D9010 ality of Teaching and Learni Post Limited 40,000.00 0.00 Canceled 2022-05-21 2022-07-29 2022-08-08 2022-10-07 s de formation en français et tions nvelope ng en mathématiques du CE2 TG-PCU-PAQEEB-285050-NC- RFQ / Impression du guide si Component 1: Improving Qu mplifié/circulaire de gestion Request for Quota Single Stage - One E IDA / D9010 ality of Teaching and Learni Post Limited 39,500.00 0.00 Signed 2022-07-05 2022-09-01 2022-09-29 2022-11-28 de la subvention et des regis tions nvelope ng tres de gestion aux inspectio ns (IEPP/IESG) et aux DRE po ur le suivi-accompagnement TG-PCU-PAQEEB-285058-NC- RFQ / Reproduction des regis Component 1: Improving Qu Request for Quota Single Stage - One E tres de la tenue de la compt IDA / D9010 ality of Teaching and Learni Post Limited 13,600.00 0.00 Signed 2022-06-25 2022-09-01 2022-09-19 2022-11-18 tions nvelope abilité aux COGEPs /COGERE ng S et aux inspections/DRE TG-PCU-PAQEEB-285547-NC- Component 3: Strengthening RFQ / Assurance maladie-indi Request for Quota Single Stage - One E IDA / D9010 system management and re Post Limited 50,000.00 0.00 Signed 2022-09-20 2022-09-27 2022-11-29 2023-11-29 viduel accident et décès UCP tions nvelope silience -PAQEEB pour une période d e deux (02) ans TG-PCU-PAQEEB-285414-NC- DIR / Acquisition d'un module Component 3: Strengthening supplémentaire de schoolfee IDA / D9010 system management and re Post Direct Selection Direct - National 30,000.00 0.00 Signed 2022-10-18 2022-08-26 2022-10-23 2022-09-05 2022-12-27 2023-03-27 s pour la gestion des dotatio silience ns aux écoles et formation d es chefs sections finance des inspections TG-PCU-PAQEEB-328196-NC- Component 1: Improving Qu RFB / Impression des module Single Stage - One E Under Imple IDA / D9010 ality of Teaching and Learni Post Request for Bids Open - National 160,000.00 0.00 2022-12-15 2022-12-27 2022-12-20 2023-01-19 2023-01-26 2023-03-05 2023-04-09 2023-06-08 s de formation en français et nvelope mentation ng en mathématiques du CE2 TG-PCU-PAQEEB-329090-NC- RFQ / Reproduction et distrib ution des manuels scolaires a ux élèves de préscolaires sec Component 1: Improving Qu Request for Quota Single Stage - One E Under Imple tion 1 et 2, et des cours prép IDA / D9010 ality of Teaching and Learni Prior Limited 5,000,000.00 0.00 2023-01-15 2023-01-13 2023-03-12 2023-04-26 tions nvelope mentation aratoires 1 et 2 en deux lots : ng Lot 1 : préscolaires section 1 et préscolaires 2, Lot 2 : CP1 et CP2 TG-PCU-PAQEEB-348855-NC- RFB / Impression des plans d étaillés de cours pour les ens eignants volontaires, des mo Component 1: Improving Qu Single Stage - One E dules de formation sur l'éval TF / B6287 ality of Teaching and Learni Post Request for Bids Open - National 120,000.00 0.00 Canceled 2023-07-25 2023-07-30 2023-08-29 2023-09-28 2023-11-09 2024-01-08 nvelope uation en APC, reproduction ng des guides de cours pour la f ormation des enseignants et Impression du manuel sur la santé scolaire (SH). TG-PCU-PAQEEB-348503-NC- RFB / Assurances tous risque Component 3: Strengthening Request for Quota Single Stage - One E Under Imple s pour les 24 véhicules pick-u IDA / D9010 system management and re Post Limited 84,000.00 0.00 2023-04-25 2023-05-16 2023-06-27 2024-06-21 tions nvelope mentation p pour les inspections pour u silience ne durée d'une année. Page 2 TG-PCU-PAQEEB-368706-NC- RFQ / Impression des plans d Component 1: Improving Qu Request for Quota Single Stage - One E Pending Impl étaillés de cours pour les ens IDA / D9010 ality of Teaching and Learni Post Limited 60,000.00 0.00 2023-07-18 2023-09-19 2023-11-18 tions nvelope ementation eignants volontaires et des ng modules de formation sur l'é valuation en APC. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285037-CS- Component 1: Improving Qu QCBS / Recrutement d'un édi Quality And Cost- Open - Internationa IDA / D9010 ality of Teaching and Learni Post 300,000.00 0.00 Signed 2022-04-15 2022-06-15 2022-05-06 2022-07-27 2022-06-12 2022-10-25 2022-07-27 2022-11-23 2022-09-10 2022-12-19 2022-10-24 2023-02-14 2022-11-28 2023-05-27 teur pour l'édition des manu Based Selection l ng els et guides du CM1 TG-PCU-PAQEEB-285500-CS- Component 3: Strengthening Quality And Cost- Open - Internationa QCBS / Recrutement d'un Ag IDA / D9010 system management and re Post 400,000.00 0.00 Signed 2022-04-04 2022-07-06 2022-04-18 2022-07-11 2022-05-25 2022-10-19 2022-07-09 2022-11-22 2022-08-23 2022-12-16 2022-09-27 2023-03-30 2022-11-08 2026-10-08 Based Selection l ent Vérificateur Indépendant silience TG-PCU-PAQEEB-285503-CS- Component 3: Strengthening LCS / Recrutement de l'Audit Least Cost Selecti IDA / D9010 system management and re Post Open - National 90,000.00 0.00 Signed 2022-04-15 2022-05-17 2022-05-06 2022-06-12 2022-09-13 2022-07-12 2022-10-12 2022-08-11 2022-11-07 2022-09-08 2022-11-23 2022-10-20 2025-10-19 eur Externe pour les exercice on silience s 2022,2023 et 2024 TG-PCU-PAQEEB-285045-CS- Component 1: Improving Qu CQS / Recrutement d'un édit Consultant Qualifi Open - Internationa IDA / D9010 ality of Teaching and Learni Post 200,000.00 0.00 Signed 2022-06-20 2022-08-10 2022-07-11 2022-08-22 2022-08-28 2022-11-02 2022-09-27 2023-01-05 2022-11-01 2023-04-30 eur pour l'édition des manue cation Selection l ng ls de technologie ( 6ème, 5è me, 4ème, 3ème) TG-PCU-PAQEEB-348826-CS- CQS / Recrutement d'un cons Component 3: Strengthening ultant pour la réalisation de l' Consultant Qualifi Open - Internationa Pending Impleme IDA / D9010 system management and re Post 100,000.00 0.00 2023-05-25 2023-06-08 2023-07-22 2023-08-21 2023-10-02 2023-12-01 enquête sur la transition des cation Selection l ntation silience jeunes diplômés de l'enseign ement supérieur et des EFFP vers la vie active TG-PCU-PAQEEB-348827-CS- Component 3: Strengthening CQS / Recrutement d'un cabi Consultant Qualifi IDA / D9010 system management and re Post Open - National 90,000.00 0.00 Under Review 2023-04-20 2023-04-25 2023-05-04 2023-06-17 2023-07-17 2023-08-28 2023-10-27 net pour l'évaluation des acq cation Selection silience uis scolaires EGMA et EGRA TG-PCU-PAQEEB-348824-CS- Component 3: Strengthening Quality And Cost- Open - Internationa CQS / Recrutement d'un cabi IDA / D9010 system management and re Post 260,000.00 0.00 Canceled 2023-05-15 2023-06-05 2023-07-19 2023-07-23 2023-08-22 2023-10-03 2023-11-14 2023-12-14 Based Selection l net pour la réalisation de l'en silience quête SDI TG-PCU-PAQEEB-361288-CS- CDS / Recrutement d'un cabi Component 3: Strengthening net en formation en gestion Consultant Qualifi Open - Internationa Pending Impleme IDA / D9010 system management and re Post 100,000.00 0.00 2023-06-30 2023-07-14 2023-08-18 2023-09-08 2023-10-13 2024-10-07 a la base (FGB) pour appuyer cation Selection l ntation silience la DPSSE dans la mise en œu vre de l’approche communau taire INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-PCU-PAQEEB-285070-CS- INDV / Recrutement d'un con sultant pour faire l'Etat des li Component 2: Improve equit eux et identification des beso able access to basic educati Individual Consult ins en ressources humaines TF / B6287 Post Open 20,000.00 0.00 Signed 2022-07-20 2022-06-15 2022-09-07 2022-09-26 2022-09-10 2022-10-19 2022-10-22 2022-12-21 on (primary and lower-secon ant Selection et équipement pour le bon fo dary) nctionnement de la cellule ge nre et élaborer une stratégie nationale d’intégration du ge nre dans la planification TG-PCU-PAQEEB-285497-CS- CDS / Recrutement d'un cons ultant par entente directe po Component 3: Strengthening ur la poursuite de l'élaboratio IDA / D9010 system management and re Post Direct Selection Direct 35,600.00 0.00 Signed 2022-09-20 2022-07-20 2022-10-02 2022-07-20 2022-12-06 2023-01-20 n du document de politique n silience ationale d'offre de service d'i nformation et d'orientation s colaires et professionnelles. TG-PCU-PAQEEB-285083-CS- Component 2: Improve equit CDS / Sélection par entente d able access to basic educati IDA / D9010 Post Direct Selection Direct 280,000.00 0.00 Signed 2022-05-20 2022-07-20 2022-05-30 2022-07-20 2022-08-10 2022-11-08 ire de l'IIPE pour l' opérationn on (primary and lower-secon alisation du système de la ca dary) rte scolaire TG-PCU-PAQEEB-285402-CS- CDS / Recrutement d'un cons ultant individuel pour l'élabor Component 3: Strengthening Individual Consult ation du schéma directeur su IDA / D9010 system management and re Post Open 22,000.00 0.00 Signed 2022-06-30 2022-07-13 2022-08-18 2022-10-05 2022-09-17 2022-10-26 2022-10-22 2022-12-21 ant Selection r la mise en œuvre de la for silience mation initiale et continue de les acteurs du système éduc atif TG-PCU-PAQEEB-285412-CS- CDS / Recrutement d'un cons ultant national (coache) pour Component 3: Strengthening Individual Consult accompagner l'équipe des dé IDA / D9010 system management and re Post Open 18,000.00 0.00 Signed 2022-06-15 2022-07-13 2022-08-03 2022-09-15 2022-09-02 2022-10-21 2022-10-07 2023-04-05 ant Selection veloppeurs d'une plateforme silience unique de gestion des notes des élèves de tous les établis sements scolaires TG-PCU-PAQEEB-285409-CS- CDS / Recrutement d'un cons Component 3: Strengthening ultant StatEduc expert SIGE IDA / D9010 system management and re Post Direct Selection Direct - National 40,000.00 0.00 Signed 2022-09-15 2022-09-26 2022-09-25 2022-09-26 2022-11-29 2023-02-27 par entente directe pour l'op silience timisation du du Système d'I nformation de Gestion de l'E ducation (SIGE) TG-PCU-PAQEEB-285020-CS- Component 1: Improving Qu INDV / Recrutement d'un con Individual Consult TF / B6287 ality of Teaching and Learni Post Open 40,000.00 0.00 Canceled 2022-04-15 2022-06-03 2022-07-03 2022-08-07 2022-11-05 sultant pour la mise en œuvr ant Selection ng e de l'outil TEACH Page 3 TG-PCU-PAQEEB-285031-CS- Component 1: Improving Qu INDV / Recrutement d'un con Individual Consult TF / B6287 ality of Teaching and Learni Post Open 30,000.00 0.00 Canceled 2022-05-10 2022-06-28 2022-07-28 2022-09-01 2022-10-31 sultant individuel pour l'élab ant Selection ng oration de la politique des m anuels scolaires TG-PCU-PAQEEB-307500-CS- CDS / Recrutement d'un cabi Component 1: Improving Qu Direct - Internation net par entente directe pour l TF / B6287 ality of Teaching and Learni Post Direct Selection 30,000.00 0.00 Signed 2022-09-15 2022-10-05 2022-09-25 2022-10-07 2022-11-29 2023-01-28 al 'élaboration de la politique d ng es manuels scolaires TG-PCU-PAQEEB-307562-CS- INDV / Recrutement d'un con sultant individuel internation Component 3: Strengthening Individual Consult Open - Internationa Under Implement al en formation en gestion a l IDA / D9010 system management and re Post 50,000.00 0.00 2022-12-05 2022-12-26 2023-01-23 2023-02-22 2023-03-29 2023-06-27 ant Selection l ation a base (FGB) pour appuyer la silience DPSSE dans la mise en œuvr e de l’approche communauta ire TG-PCU-PAQEEB-328193-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant individuel national en Individual Consult Under Implement IDA / D9010 system management and re Post Open - National 50,000.00 0.00 2022-12-15 2022-12-26 2023-02-02 2023-03-04 2023-04-08 2023-10-05 formation en gestion a la bas ant Selection ation silience e (FGB) pour appuyer la DPS SE dans la mise en œuvre de l’approche communautaire TG-PCU-PAQEEB-348831-CS- INDV / Recrutement d'un con Component 3: Strengthening Individual Consult sultant individuel pour la nu IDA / D9010 system management and re Post Open - National 50,000.00 0.00 Under Review 2023-05-25 2023-04-25 2023-07-13 2023-08-03 2023-09-14 2023-10-14 ant Selection mérisation des nouveaux out silience ils de gestion : ETP, IRRP, TIS E, MAGEV, CC TG-PCU-PAQEEB-348841-CS- INDV / Recrutement d'un con Component 1: Improving Qu sultant en ingénierie pédago Individual Consult TF / B6287 ality of Teaching and Learni Post Open - National 16,000.00 0.00 Under Review 2023-05-25 2023-06-16 2023-07-13 2023-08-03 2023-09-14 2023-11-13 gique auprès de la DRH de la ant Selection ng DESG et de la DEPP dans le c adre de la reforme curriculair e TG-PCU-PAQEEB-296779-CS- INDV / Recrutement d’un con Component 3: Strengthening sultant individuel pour la mis Individual Consult IDA / D9010 system management and re Post Open 40,000.00 0.00 Canceled 2022-07-15 2022-07-25 2022-09-02 2022-10-13 2022-10-02 2022-11-06 2023-02-04 e en œuvre des recommanda ant Selection silience tions du rapport de l’évaluati on du pilotage sectoriel de l’ éducation au Togo TG-PCU-PAQEEB-354394-CS- INDV / Recrutement d’un con Component 3: Strengthening Individual Consult sultant pour la formation des IDA / D9010 system management and re Post Direct - National 4,250.00 0.00 Canceled 2023-04-17 2023-04-27 2023-05-18 2023-06-22 2023-07-02 ant Selection cadres de l’ENEAS sur les mé silience thodes quantitatives des don nées TG-PCU-PAQEEB-354341-CS- INDV / Recrutement d’un con Component 3: Strengthening sultant pour la formation des Individual Consult Direct - Internation IDA / D9010 system management and re Post 7,000.00 0.00 Canceled 2023-04-13 2023-04-23 2023-05-14 2023-06-18 2023-06-28 cadres de l’ENEAS sur le pilot ant Selection al silience age et gestion des évaluation s à large échelle internationa le et nationale. TG-PCU-PAQEEB-285499-CS- INDV / Recrutement d'un con Component 3: Strengthening Individual Consult sultant individuel pour le Dia IDA / D9010 system management and re Post Open 30,000.00 0.00 Canceled 2022-06-15 2022-07-19 2022-08-03 2022-09-02 2022-10-14 2022-12-13 ant Selection gnostic institutionnel du syst silience ème national d'évaluation de s apprentissages (SNEA) TG-PCU-PAQEEB-285498-CS- Component 3: Strengthening CDS / Recrutement d'un cons Individual Consult IDA / D9010 system management and re Post Open 30,000.00 0.00 Canceled 2022-06-10 2022-07-29 2022-08-28 2022-10-02 2023-03-31 ultant individuel en ingénieri ant Selection silience e pédagogique auprès de la DF et de la DEPP TG-PCU-PAQEEB-285504-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant pour l'Etude de faisab Individual Consult IDA / D9010 system management and re Post Open 30,000.00 0.00 Canceled 2022-05-30 2022-08-03 2022-08-24 2022-10-05 2022-12-04 ilité pour usage de l'instrume ant Selection silience nt PPP en Education pour la c onstruction d'infrastructures scolaires TG-PCU-PAQEEB-367785-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant individuel pour appuy Individual Consult Pending Impleme IDA / D9010 system management and re Post Open - National 36,000.00 0.00 2023-06-30 2023-08-09 2023-09-08 2023-10-13 2023-12-12 er l'équipe nationale d'évalua ant Selection ntation silience tion des acquis scolaires (EN EAS) pour la réalisation de l'e nquête SDI TG-PCU-PAQEEB-367787-CS- INDV / Recrutement d'un con Component 3: Strengthening sultant individuel pour appuy Individual Consult Pending Impleme IDA / D9010 system management and re Post Open - National 30,000.00 0.00 2023-06-30 2023-08-09 2023-09-08 2023-10-13 2023-12-12 er l'équipe nationale d'évalua ant Selection ntation silience tion des acquis scolaires (EN EAS) pour l'évaluation des ac quis scolaires EGMA et EGRA TG-PCU-PAQEEB-368690-CS- CDS / Recrutement de L’ONG Component 2: Improve equit PLAN INTERNATIONAL TOGO able access to basic educati Pending Impleme pour appuyer la cellule genre TF / B6287 Post Direct Selection Direct - National 24,000.00 0.00 2023-07-10 2023-07-20 2023-09-23 2024-09-17 on (primary and lower-secon ntation dans la réalisation des activit dary) és de promotion de la scolari sation des filles dans le cadre de la mise en œuvre du PAQ EEB Page 4 PROCUREMENT PLAN (Textual Part) Project information: Accelerating and Strengthening Skills for Economic Transformation Project) (ASSET), P167506 Project Implementation agency: Directorate of Technical Education (DTE), Technical and Madrasah Education Division (TMED), Ministry of Education (MoE) Date of the Procurement Plan: March 23, 2022 Period covered by this Procurement Plan: March 2022 to March 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (dated July 2016, revised November 2017, August 2018 and November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules 2008, as amended in August 2009) , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions : a) e-GP system of the country for national competitive bidding (NCB) shall be followed using Standard/Model Procurement documents satisfactory to the Bank b) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; c) Bids should be submitted and opened in public in one location immediately after the deadline for submission; d) Lottery in award of contracts shall not be allowed; e) Bidders’ qualification/experience requirement shall be mandatory f) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. Procurement Responsibility: Bangladesh Bureau of Statistics (BBS) is the implementing agency (IA) who will be responsible for all procurements. Procurement Threshold Bank-financed all contracts at or above the thresholds set out in the below table 1 are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) High Substant Modera Low Type of procurement risk ial risk te risk risk Works (including turnkey, supply & installation of plant and equipment, 5 10 15 20 and PPP) Goods, information technology and 1.5 2 4 6 non-consulting services Consultants: firms 0.5 1 2 4 Consultants: individuals 0.2 0.3 0.4 0.5 Irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: a. procurement processes involving contract negotiations as, described in paragraphs 6.34-36 of Section VI of the Procurement Regulation for Borrowers; b. competitive dialogue; c. sustainable procurement; and d. best and final offer. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract, including all taxes and duties payable under the contract. PROCUREMENT Bangladesh : Accelerating and Strengthening Skills for Economic Transformation PLAN General Information Country: Bangladesh 2022-04-03 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167506 GPN Date: 2022-04-18 Project Name: Accelerating and Strengthening Skills for Economic Transformation Loan / Credit No: IDA / 68740 Technical and Madrasah Education Division Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure Component 3: Capacity Dev ment Document - BD-TMED-317150-CW-RFB / elopment, Project Managem Single Stage - One E Under Imple 2023-11-0 IDA / 68740 Post Request for Bids Open - National 1 Envelope proce 174,400.00 0.00 2023-02-28 2023-03-23 2023-03-21 2023-03-27 2023-05-02 2023-04-18 2023-07-01 2023-08-05 Office refurbishment of DTE ent, Social Marketing and M nvelope mentation 3 ss (Non Bank-SPD onitoring & Evaluation ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-TMED-286889-GO-RFB / Component 3: Capacity Dev Procurement of Desktop Com elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 66,176.47 0.00 Signed 2022-04-05 2022-05-24 2022-04-10 2022-05-22 2022-06-13 2022-06-21 2022-07-03 2022-07-26 2023-01-22 puter, UPS, Laptop Computer ent, Social Marketing and M nvelope , Photocopier, Printer,Scanne onitoring & Evaluation r, DSLR Camera,etc BD-TMED-317151-GO-RFB / Component 1: Transforming Establishment of Internet & T Formal Skills Development f Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 17,450.00 0.00 2022-10-10 2022-10-25 2022-11-04 2022-12-04 2023-01-08 2023-07-07 elecom Network of the Projec or Future of Work, Inclusiven nvelope ementation t Office ess, and Resilience BD-TMED-317152-GO-RFB / Component 3: Capacity Dev Supply & installation of Offic elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 16,280.00 0.00 Signed 2022-10-10 2022-11-30 2022-10-15 2022-11-26 2022-12-15 2022-12-26 2023-01-08 2023-01-30 2023-03-01 e Equipment (Photocopier, Pr ent, Social Marketing and M nvelope inter & Scanner) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317153-GO-RFB / elopment, Project Managem Single Stage - One E Pending Impl Supply and installation of PA IDA / 68740 Post Request for Bids Open - National 11,630.00 0.00 2022-10-11 2022-10-16 2022-11-27 2022-12-27 2023-01-31 2023-03-02 ent, Social Marketing and M nvelope ementation and multimedia system onitoring & Evaluation G2B / Supply and Installatio Component 3: Capacity Dev n of Laptop, Intercom System elopment, Project Managem Single Stage - One E Under Imple IDA / 68740 Post Request for Bids Open - National 32,500.00 0.00 2023-05-21 2023-06-12 2023-05-26 2023-06-12 2023-06-16 2023-07-31 2023-09-04 2023-12-03 and LAN for PMU including all ent, Social Marketing and M nvelope mentation accessories onitoring & Evaluation Component 3: Capacity Dev G5A / Supply of Furniture an elopment, Project Managem Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 232,550.00 0.00 2023-05-21 2023-05-26 2023-06-16 2023-07-31 2023-09-04 2024-01-02 d Fixtures for PMU office ent, Social Marketing and M nvelope ementation onitoring & Evaluation Component 3: Capacity Dev G11A / Supply of Computer elopment, Project Managem Request for Quota Single Stage - One E Under Imple IDA / 68740 Post Open - National 2,325.00 0.00 2023-05-26 2023-06-19 2023-06-22 2023-07-13 Consumables ent, Social Marketing and M tions nvelope mentation onitoring & Evaluation Component 3: Capacity Dev G15A / Supply of Stationarie elopment, Project Managem Request for Quota Single Stage - One E Pending Impl IDA / 68740 Post Open - National 1,400.00 0.00 2023-06-02 2023-06-29 2023-07-20 s for PMU office ent, Social Marketing and M tions nvelope ementation onitoring & Evaluation G57 / Supply of Materials for Component 1: Transforming Seminar, Workshops and Con Formal Skills Development f Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 232,550.00 0.00 2023-05-28 2023-06-02 2023-06-30 2023-07-30 2023-09-10 2025-09-09 ferences under framework co or Future of Work, Inclusiven nvelope ementation ntract ess, and Resilience G59 / Supply of Project Mana Component 3: Capacity Dev gement Information System elopment, Project Managem Single Stage - One E Under Imple IDA / 68740 Post Request for Bids Open - National 286,000.00 0.00 2023-05-28 2023-05-18 2023-06-02 2023-05-21 2023-06-04 2023-06-21 2023-08-03 2023-09-07 2023-12-06 Software with 04 year opera ent, Social Marketing and M nvelope mentation tional and maintenance supp onitoring & Evaluation ort Component 3: Capacity Dev BD-TMED-286891-GO-RFB / elopment, Project Managem Single Stage - One E Supply of Accounts and other IDA / 68740 Post Request for Bids Open - National 12,941.18 0.00 Canceled 2022-05-03 2022-05-08 2022-06-19 2022-07-19 2022-08-23 2023-02-19 ent, Social Marketing and M nvelope Software onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286890-GO-RFB / elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 35,294.12 0.00 Canceled 2022-04-12 2022-04-17 2022-05-29 2022-06-28 2022-08-02 2023-01-29 Supply of furniture for PMU ent, Social Marketing and M nvelope onitoring & Evaluation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Transforming NCS1A / Selection of Event Formal Skills Development f Single Stage - One E Pending Impl Management firm for Semina IDA / 68740 Post Request for Bids Open - National 55,800.00 0.00 2023-05-28 2023-06-02 2023-06-30 2023-08-29 2023-10-03 2024-03-31 or Future of Work, Inclusiven nvelope ementation rs and Workshops ess, and Resilience CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 BD-TMED-286611-CS-QCBS / Selection of firm/ institution f Component 1: Transforming or organizing seminars and w Formal Skills Development f Quality And Cost- orkshops for TTIs (1), Partner IDA / 68740 Post Open - National 228,235.29 0.00 Canceled 2022-04-03 2022-04-24 2022-06-07 2022-07-05 2022-08-04 2022-09-08 2022-10-13 2023-10-13 or Future of Work, Inclusiven Based Selection organizations (1), RPL for em ess, and Resilience ployers and workers (2) and DTE (1), project launching ce remony (1) BD-TMED-286628-CS-QCBS / Component 3: Capacity Dev Selection of Consultant for R elopment, Project Managem Quality And Cost- apid Assessment and follow- IDA / 68740 Post Open - National 117,647.06 0.00 Canceled 2022-04-20 2022-05-11 2022-06-24 2022-07-22 2022-08-21 2022-09-25 2022-10-30 2023-10-30 ent, Social Marketing and M Based Selection up on Diploma Students by D onitoring & Evaluation TE (1), Demand and Gap Ana lysis by BTEB (1) Component 3: Capacity Dev BD-TMED-286635-CS-QCBS / elopment, Project Managem Quality And Cost- Survey and Studies by BMET IDA / 68740 Post Open - National 235,294.12 0.00 Canceled 2022-04-27 2022-05-18 2022-07-01 2022-07-29 2022-08-28 2022-10-02 2022-11-06 2023-11-06 ent, Social Marketing and M Based Selection (2), NSDA (1), DTE (1) onitoring & Evaluation BD-TMED-286641-CS-FBS / S Component 3: Capacity Dev election of Consultant for TV elopment, Project Managem Fixed Budget Sele Pending Impleme IDA / 68740 Post Open - National 29,411.76 0.00 2022-04-10 2022-05-01 2022-06-14 2022-07-12 2022-08-11 2022-09-15 2022-10-20 2023-10-20 C production (1), Radio Ad pr ent, Social Marketing and M ction ntation oduction (2) onitoring & Evaluation BD-TMED-286888-CS-QCBS / Component 3: Capacity Dev Selection of Consulting Firm f elopment, Project Managem Quality And Cost- IDA / 68740 Post Open - National 174,117.65 0.00 Canceled 2022-04-24 2022-05-15 2022-06-28 2022-07-26 2022-08-25 2022-09-29 2022-11-03 2023-11-03 or Competency Standard Dev ent, Social Marketing and M Based Selection elopment for BTEB (12), BME onitoring & Evaluation T (40), S51 / Selection of Consultant for Demand and Gap Analysi Component 3: Capacity Dev s under BTEB: Analyzing the elopment, Project Managem Consultant Qualifi Skills and Competency Gaps IDA / 68740 Post Open - National 58,000.00 0.00 Under Review 2023-03-01 2023-03-23 2023-03-22 2023-05-05 2023-06-23 2023-08-04 2024-01-31 ent, Social Marketing and M cation Selection of the Selected Diploma in En onitoring & Evaluation gineering Courses Running U nder the Bangladesh Technic al Education Board S55A / Selection of Consulta nt for Survey and Studies un Component 3: Capacity Dev der BTEB on Analyzing Weak elopment, Project Managem Quality And Cost- IDA / 68740 Post Open - National 93,000.00 0.00 Under Review 2023-03-01 2023-03-23 2023-03-22 2023-05-05 2023-06-30 2023-07-30 2023-09-03 2023-10-15 2024-04-12 nesses, Prospects, and Effect ent, Social Marketing and M Based Selection iveness of Industrial Attachm onitoring & Evaluation ent of Diploma in Engineerin g Courses Running S59A / Selection of Consultin Component 3: Capacity Dev g firm for Surveys and Studie elopment, Project Managem Consultant Qualifi IDA / 68740 Post Open - National 58,000.00 0.00 Under Review 2023-03-07 2023-03-23 2023-03-28 2023-05-11 2023-06-22 2023-08-03 2024-01-30 s under NSDA (Sector: Creati ent, Social Marketing and M cation Selection ve Media) onitoring & Evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Capacity Dev BD-TMED-286652-CS-INDV / elopment, Project Managem Individual Consult Selection of Financial Manag IDA / 68740 Prior Open 352,941.18 0.00 Signed 2022-04-03 2022-04-18 2022-05-22 2022-09-21 2022-06-12 2022-10-24 2022-07-17 2023-01-13 ent, Social Marketing and M ant Selection ement Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286655-CS-INDV / elopment, Project Managem Individual Consult Selection of Junior Financial IDA / 68740 Post Open 197,647.06 0.00 Signed 2022-04-03 2022-04-16 2022-05-22 2023-02-23 2022-06-12 2023-02-23 2022-07-17 2023-01-13 ent, Social Marketing and M ant Selection Management Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286658-CS-INDV / elopment, Project Managem Individual Consult Selection of Procurement Spe IDA / 68740 Prior Open 364,705.88 0.00 Signed 2022-04-04 2022-04-17 2022-05-23 2022-09-21 2022-06-13 2022-10-27 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection cialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286660-CS-INDV / elopment, Project Managem Individual Consult Selection of Junior Procureme IDA / 68740 Prior Open 218,823.53 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2023-02-23 2022-06-13 2023-03-28 2022-07-18 2023-05-02 2023-01-14 ent, Social Marketing and M ant Selection nt Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286661-CS-INDV / elopment, Project Managem Individual Consult Selection of IDG Managemen IDA / 68740 Prior Open 317,647.06 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2022-09-21 2022-06-13 2022-10-25 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection t Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286883-CS-INDV / elopment, Project Managem Individual Consult Selection of ICT and MIS Spec IDA / 68740 Prior Open 282,352.94 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2022-09-21 2022-06-13 2022-10-25 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection ialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286885-CS-INDV / elopment, Project Managem Individual Consult Under Implement Selection of E&S safeguard S IDA / 68740 Prior Open 235,294.12 0.00 2022-04-28 2022-08-07 2022-06-16 2022-07-07 2022-08-11 2023-02-07 ent, Social Marketing and M ant Selection ation pecialist (1) onitoring & Evaluation BD-TMED-316744-CS-INDV / Component 3: Capacity Dev Selection of TVET & Industry elopment, Project Managem Individual Consult Under Implement IDA / 68740 Prior Open - National 310,000.00 0.00 2022-09-27 2022-11-07 2022-11-15 2022-12-06 2023-01-10 2025-01-09 Development Management S ent, Social Marketing and M ant Selection ation pecialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286886-CS-INDV / elopment, Project Managem Individual Consult Pending Impleme Selection of Short Term Tech IDA / 68740 Prior Open - National 350,000.00 0.00 2022-09-27 2022-11-15 2022-12-06 2023-01-10 2023-07-09 ent, Social Marketing and M ant Selection ntation nical Specialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317145-CS-INDV / elopment, Project Managem Individual Consult Selection of Monitoring & Eva IDA / 68740 Prior Open - National 590,000.00 0.00 Under Review 2022-09-30 2022-11-07 2022-11-18 2022-12-09 2023-01-13 2025-01-12 ent, Social Marketing and M ant Selection luation Specialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317147-CS-INDV / elopment, Project Managem Individual Consult Selection of Skills Training Sp IDA / 68740 Prior Open - National 310,000.00 0.00 Under Review 2022-10-05 2022-11-07 2022-11-23 2022-12-14 2023-01-18 2025-01-07 ent, Social Marketing and M ant Selection ecialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317148-CS-INDV / elopment, Project Managem Individual Consult Under Implement Selection of Communication IDA / 68740 Prior Open - National 310,000.00 0.00 2022-10-05 2022-11-07 2022-11-23 2022-12-14 2023-01-18 2025-01-17 ent, Social Marketing and M ant Selection ation Speciaist onitoring & Evaluation Page 2 Component 3: Capacity Dev S39B / Selection of IDG Spec elopment, Project Managem Individual Consult IDA / 68740 Post Limited 34,800.00 0.00 Under Review 2023-06-08 2023-06-06 2023-06-13 2023-07-04 2023-08-15 2024-02-11 ialist (Health) ent, Social Marketing and M ant Selection onitoring & Evaluation Page 3 PROCUREMENT PLAN (Textual Part) Project information: Mozambique – Mozambique: Access to Finance & Economic Opportunities Project – P178658 Project Implementation agency: Ministry of Economy and Finance Date of the Procurement Plan: March 20, 2023 Period covered by this Procurement Plan: from March 22, 2023 to August 31, 2024 (18 months) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Decree 79/ 2022 of 30th December 2022 (in replacement of Decree 5/2016), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. PROCUREMENT Mozambique : Access to Finance & Economic Opportunities Project – Mais Oportunidades PLAN General Information Country: Mozambique 2023-03-22 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178658 GPN Date: Project Name: Access to Finance & Economic Opportunities Project – Mais Oportunidades Loan / Credit No: / , IDA / 72780 Ministry of Economy and Finance - DNT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-MEF-DNT-350986-CS-IND Component 1. Promote acce Individual Consult Open - Internationa Under Implement V / Credit Guarantee Fund M / ss and usage of financial ser Post 200,000.00 0.00 2023-03-31 2023-03-22 2023-06-12 2023-07-03 2023-08-21 2028-08-19 ant Selection l ation anager vices for MSMEs MZ-MEF-DNT-351009-CS-IND Component 1. Promote acce Individual Consult Under Implement V / Risk and Compliance Man / ss and usage of financial ser Post Open - National 150,000.00 0.00 2023-04-14 2023-03-23 2023-07-06 2023-08-05 2023-09-23 2026-09-22 ant Selection ation ager vices for MSMEs MZ-MEF-DNT-351014-CS-IND Component 1. Promote acce Individual Consult Under Implement V / Credit Risk and Operation / ss and usage of financial ser Post Open - National 120,000.00 0.00 2023-04-21 2023-03-23 2023-07-13 2023-08-12 2023-09-30 2026-09-29 ant Selection ation s Manager vices for MSMEs MZ-MEF-DNT-364905-CS-IND Component 3. Project mana Individual Consult Pending Impleme IDA / 72780 Post Open - National 86,400.00 0.00 2023-07-20 2023-10-21 2023-11-25 2024-01-20 2026-01-19 V / Financial Services Speciali gement ant Selection ntation st Component 1. Promote acce MZ-MEF-DNT-364907-CS-IND Individual Consult Pending Impleme IDA / 72780 ss and usage of financial ser Post Open - National 120,000.00 0.00 2023-07-21 2023-10-22 2023-11-21 2024-01-09 2026-01-08 V / Line of Credit Manager ant Selection ntation vices for MSMEs MZ-MEF-DNT-364920-CS-IND Component 3. Project mana Individual Consult Pending Impleme IDA / 72780 Prior Open - National 64,800.00 0.00 2023-07-31 2023-11-01 2023-12-06 2024-01-24 2026-01-23 V / Procurement Consultant gement ant Selection ntation MZ-MEF-DNT-364908-CS-IND Component 1. Promote acce V / Individual consulting servi Individual Consult Pending Impleme IDA / 72780 ss and usage of financial ser Post Open - National 120,000.00 0.00 2023-07-31 2023-11-01 2023-12-01 2024-01-19 2026-01-18 ces for Financial Inclusion Pro ant Selection ntation vices for MSMEs gramme Manager (micro-savi ngs) MZ-MEF-DNT-364917-CS-IND V / Individual consulting servi Component 3. Project mana Individual Consult IDA / 72780 Post Open - National 75,600.00 0.00 Under Review 2023-08-30 2023-12-11 2024-01-10 2024-02-28 2026-02-27 ces for Social Specialist with gement ant Selection health and safety experience MZ-MEF-DNT-364910-CS-IND V / Individual consulting servi Component 3. Project mana Individual Consult Pending Impleme IDA / 72780 Post Open - National 75,600.00 0.00 2023-08-18 2023-11-19 2023-12-19 2024-02-06 2026-02-05 ces for Social Specialist with gement ant Selection ntation experience in resettlement Page 1 PROCUREMENT PLAN (Textual Part) Project information: [country]Congo Democratic Republic, EMERGENCY EQUITY AND SYSTEM STRENGTHENING IN EDUCATION PROJECT [Project name] [P-number] Project Implementation agency: [insert legal name] Date of the Procurement Plan: [insert date] Period covered by this Procurement Plan: [insert from – to period] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Congo, Democratic Republic of : DR Congo Emergency Equity and System Strengthening in Education PLAN General Information Country: Congo, Democratic Republic of 2020-08-11 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172341 GPN Date: Project Name: DR Congo Emergency Equity and System Strengthening in Education Loan / Credit No: IDA / 66920 Permanent Secretariat for Support and Coordination of the Education Sector Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-SPACE-214168-CW-RFQ / Travaux d'aménagement des Component 3: Strengthening Request for Quota Single Stage - One E 2021-04-2 IDA / 66920 Post Limited 52,613.00 Signed 2021-01-22 2021-01-05 2021-03-10 2021-02-19 bureaux pour l'Equipe de Coo Systems for Results tions nvelope 4 rdination du Projet (ECP) du P rojet PERSE Request for ZR-SPACE-272628-CW-RFQ / Quotations - TRAVAUX D'AMENAGEMENT Component 3: Strengthening Request for Quota Single Stage - One E Small Works 2022-09-0 IDA / 66920 Post Limited 0.00 Signed 2022-01-16 2022-08-18 2022-03-13 DE 6 CONTAINERS EN BUREA Systems for Results tions nvelope (Emergency) 9 UX POUR LE PROJET PERSE SPD -Compet itive Request for ZR-SPACE-296497-CW-RFQ / Quotations - Travaux d'aménagement des Component 3: Strengthening Request for Quota Single Stage - One E Small Works 2023-01-2 IDA / 66920 Post Limited 0.00 Signed 2022-06-06 2022-08-18 2022-08-01 douze (12) bureaux en faveu Systems for Results tions nvelope (Emergency) 8 r des Directions d'appui MEP SPD -Compet ST itive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-SPACE-209748-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Fourniture des supports de c IDA / 66920 Post Limited 69,950.00 Signed 2020-12-15 2020-12-04 2021-01-28 2021-01-21 2021-02-27 Systems for Results tions nvelope ommunication pour le PERSE ZR-SPACE-209751-GO-RFQ / Fourniture et installation des Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 45,800.00 Completed 2020-12-15 2020-12-04 2021-01-10 2021-01-21 2021-02-09 2021-04-01 équipements vidéo conféren Systems for Results tions nvelope ce pour l'UCP PERSE ZR-SPACE-209756-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Acquisition de deux véhicule IDA / 66920 Post Limited 94,450.00 Completed 2020-12-15 2020-12-15 2021-01-05 2021-03-24 2021-02-04 2021-09-17 Systems for Results tions nvelope s utilitaires pour l'UCP PERSE ZR-SPACE-229255-GO-RFQ / ACQUISITION MOBILIER DE B Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 94,415.00 Completed 2021-04-19 2021-04-15 2021-06-14 2021-05-11 2021-12-11 UREAU POUR L'EQUIPE DE C Systems for Results tions nvelope OORDINATION (ECP) DU PROJ ET PERSE A KINSHASA ZR-SPACE-229266-GO-RFQ / ACQUISITION EQUIPEMENTS I Component 3: Strengthening Request for Quota Single Stage - One E NFORMATIQUES POUR L'EQU IDA / 66920 Post Limited 94,060.00 Completed 2021-04-19 2021-04-15 2021-06-14 2021-05-11 2021-12-11 2021-06-25 Systems for Results tions nvelope IPE DE COORDINATION DU P ROJET PERSE A KINSHASA ZR-SPACE-237602-GO-RFQ / ACQUISITION DES FOURNITU RES DE BUREAU ET CONSOM Component 3: Strengthening Request for Quota Single Stage - One E MABLES INFORMATIQUES PO IDA / 66920 Post Limited 52,533.83 Completed 2021-06-06 2021-07-26 2021-08-01 2021-08-14 2022-01-28 Systems for Results tions nvelope UR L'EQUIPE DE COORDINATI ON DU PROJET (ECP) PERSE P OUR 3 MOIS ( JUILLET -AOUT- SEPTEMBRE 2021) ZR-SPACE-248721-GO-RFP / Component 3: Strengthening Request for Quota Single Stage - One E Impression du code de bonne IDA / 66920 Post Limited 103,550.00 Completed 2021-09-19 2021-08-23 2021-11-07 2021-09-14 2022-02-05 2022-01-15 Systems for Results tions nvelope conduite (Acte d'engagemen t) ZR-SPACE-252528-GO-RFB / Component 3: Strengthening Single Stage - One E Under Imple ACQUISITION DE 11 VEHICUL IDA / 66920 Post Request for Bids Open - National 0.00 2021-09-08 2021-11-01 2021-09-13 2021-10-25 2021-11-24 2021-12-29 2022-06-27 Systems for Results nvelope mentation ES DE TERRAIN POUR LE PRO JET PERSE ZR-SPACE-256454-GO-RFQ / ACQUISITION DE MOBILIER D E BUREAU POUR L'EQUIPE DE Component 3: Strengthening Request for Quota Single Stage - One E COORDINATION DU PROJET P IDA / 66920 Post Limited 60,600.00 Completed 2021-10-09 2021-09-27 2021-12-04 2021-10-23 2022-06-02 2021-12-05 Systems for Results tions nvelope ERSE (ECP EN PROVINCE : KA NANGA, MBUJI-MAYI, TSHIKAP A, KABINDA, MATADI, BANDU NDU VILLE ZR-SPACE-259196-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E FOURNITURE DES SUPPORTS IDA / 66920 Post Limited 98,550.00 Completed 2021-10-26 2021-10-21 2021-12-21 2021-12-16 2022-06-19 2022-02-15 Systems for Results tions nvelope DE COMMUNICATION POUR L E PROJET PERSE ZR-SPACE-261260-GO-RFB / Component 3: Strengthening Single Stage - One E IMPRESSION DU CODE DE BO IDA / 66920 Post Request for Bids Open - National 0.00 Completed 2021-11-02 2022-03-30 2021-11-07 2021-12-19 2022-05-03 2022-01-18 2022-06-10 2022-02-22 2022-08-21 2022-11-03 Systems for Results nvelope NNE CONDUITE ZR-SPACE-272906-GO-RFQ / ACQUISITION D'UN SYSTEME Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl ELECTRONIQUE DE POINTAG IDA / 66920 Post Limited 0.00 2022-01-18 2022-03-15 2022-09-11 Systems for Results tions nvelope ementation E DE PRESENCE DU PERSON NEL DU PROJET PERSE ZR-SPACE-272911-GO-RFQ / ACQUISITION DES FOURNITU Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Signed 2022-01-18 2022-04-08 2022-03-15 2022-09-11 RES DE BUREAU ET PETITS M Systems for Results tions nvelope ATERIELS POUR LE PROJET PE RSE ZR-SPACE-272912-GO-RFQ / ACQUISITION DES CONSOMM Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Signed 2022-01-18 2022-04-08 2022-03-15 2022-09-11 ABLES INFORMATIQUES POU Systems for Results tions nvelope R LE PROJET PERSE Page 1 ZR-SPACE-272914-GO-RFQ / ACQUISITION DU MATERIEL E Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl T LOCATION D'UNE BANDE P IDA / 66920 Post Limited 0.00 2022-01-18 2022-03-15 2022-09-11 Systems for Results tions nvelope ementation ASSANTE POUR L'ABONNEME NT INTERNET DES BUREAUX DU PROJET PERSE ZR-SPACE-256601-GO-RFQ / ACQUISITION ET INSTALLATI Component 3: Strengthening Request for Quota Single Stage - One E ON D'UN GROUPE ELECTROG IDA / 66920 Post Limited 34,200.00 Completed 2021-10-10 2021-10-06 2021-12-05 2021-10-26 2022-06-03 2021-11-02 Systems for Results tions nvelope ENE DE 100 KVA POUR LE PR OJET PERSE A KINSHASA ZR-SPACE-296501-GO-RFQ / Acquisition d'Ordinateurs por tables (Laptops), imprimante Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Completed 2022-06-14 2022-06-01 2022-08-09 2023-02-05 s en couleurs et les Rétroproj Systems for Results tions nvelope ecteurs vidéo en faveur des Directions d'appui du MEPST ZR-SPACE-296503-GO-RFQ / Acquisition des mobiliers et c Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-06-19 2022-08-14 2023-02-10 limatisation des bureaux des Systems for Results tions nvelope ementation Directions d'appui du MEPST ZR-SPACE-300083-GO-RFB / ACQUISITION DES MOTOS AU Component 3: Strengthening Single Stage - One E IDA / 66920 Post Request for Bids Open - National 0.00 Signed 2022-09-16 2022-08-19 2022-09-21 2022-11-02 2022-09-22 2022-12-02 2022-10-14 2023-01-06 2023-07-05 PROFIT DES SOUS-DIVISIONS Systems for Results nvelope PROVINCIALES CIBLEES PAR LE PERSE ZR-SPACE-300092-GO-RFB / ACQUISITION DE CANOTS RA Component 3: Strengthening Single Stage - One E Pending Impl IDA / 66920 Post Request for Bids Open - National 0.00 2022-08-22 2022-08-27 2022-10-08 2022-11-07 2022-12-12 2023-06-10 PIDES AU PROFIT DES 2 SOU Systems for Results nvelope ementation S DIVISIONS LACUTSRES ZR-SPACE-300098-GO-RFB / ACQUISITION DES KITS INFOR Component 3: Strengthening Single Stage - One E MATIQUES (LAP TOP ET IMPR IDA / 66920 Post Request for Bids Open - National 0.00 Signed 2022-09-15 2022-08-18 2022-09-20 2022-11-01 2022-09-20 2022-12-01 2022-10-12 2023-01-05 2023-07-04 Systems for Results nvelope OMANTES) AU PROFIT DES DI VISIONS PROVINCIALES CIBL EES PAR LE PERSE ZR-SPACE-305596-GO-RFB / ACQUISITION DE MATERIEL I Component 3: Strengthening Open - Internationa Single Stage - One E Under Imple IDA / 66920 Prior Request for Bids 0.00 2022-08-16 2022-10-20 2022-08-21 2022-11-23 2022-10-02 2023-01-10 2022-11-01 2022-12-06 2023-06-04 NFORMATIQUE POUR LES DIF Systems for Results l nvelope mentation FERENTES DIRECTIONS DU M EPST ZR-SPACE-305616-GO-RFQ / PRODUCTION DES SUPPORTS Component 3: Strengthening Request for Quota Single Stage - One E Under Imple IDA / 66920 Post Limited 0.00 2022-07-27 2022-10-13 2022-09-21 2023-03-20 DE FIN D'ANNEE (AGENDAS, Systems for Results tions nvelope mentation CALENDRIERS ET AUTRES GA DGET) ZR-SPACE-305621-GO-RFQ / PRODUCTION DES SUPPORTS Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Completed 2022-07-27 2022-08-18 2022-09-21 2023-03-20 2023-02-27 DE VULGARISATION DU NUM Systems for Results tions nvelope ERO VERT 178 ZR-SPACE-305623-GO-RFQ / PRODUCTION DES FEUILLETS Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Signed 2022-08-31 2022-09-22 2022-10-26 2023-04-24 DE SENSIBIISATION SUR LE M Systems for Results tions nvelope ECANISME DE GESTION DES PLAINTES ZR-SPACE-305626-GO-RFQ / IMPRESSION DES SUPPORTS Component 3: Strengthening Request for Quota Single Stage - One E IDA / 66920 Post Limited 0.00 Signed 2022-08-29 2022-08-18 2022-10-24 2023-04-22 DE VISIBILITE DU PROJET/RE Systems for Results tions nvelope NOUVELLEMENT STOCK ZR-SPACE-305631-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl PRODUCTION ET MULTIPLICA IDA / 66920 Post Limited 0.00 2022-07-27 2022-09-21 2023-03-20 Systems for Results tions nvelope ementation TION DES MODULES DE FOR MATION ZR-SPACE-305634-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E PRODUCTION DES SUPPORTS IDA / 66920 Post Limited 0.00 Completed 2022-08-20 2022-09-13 2022-10-11 2023-04-09 2022-11-07 Systems for Results tions nvelope DE SENSIBILISATION DIFORE ZR-SPACE-305636-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IMPRESSION DU MODULE MG IDA / 66920 Post Limited 0.00 2022-07-27 2022-09-21 2023-03-20 Systems for Results tions nvelope ementation P EN 15 000 EXEMPLAIRES (I LD4) ZR-SPACE-305637-GO-RFQ / IMPRESSION DU MANUEL DE Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-07-27 2022-09-21 2023-03-20 PROCEDURE DE GESTION DE Systems for Results tions nvelope ementation S FRAIS DE FONCTIONNEMEN T ZR-SPACE-305638-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IMPRESSION DE MANUEL DE IDA / 66920 Post Limited 0.00 2022-07-27 2022-09-21 2023-03-20 Systems for Results tions nvelope ementation FORMATION DE COGES ZR-SPACE-305640-GO-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-07-27 2022-09-21 2023-03-20 IMPRESSION BUDGET CITOYE Systems for Results tions nvelope ementation N ZR-SPACE-329759-GO-RFQ / ACQUISITION DE 10 GROUPE Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl S ELECTROGENES POUR LES IDA / 66920 Post Limited 0.00 2022-12-17 2023-02-11 2023-08-10 Systems for Results tions nvelope ementation BUREAUX PERSE EN PROVIN CES (10KVA), FRAIS D'INSTAL LATION ET ACCESSOIRES ZR-SPACE-358640-GO-DIR / Contractualisation avec la fir me GMSP-COM pour l'acquisit Component 3: Strengthening Under Imple IDA / 66920 Post Direct Selection Direct - National 0.00 2023-04-26 2023-04-25 2023-05-01 2023-04-24 2023-06-05 2023-12-02 ion des cartes SIM VPN et forf Systems for Results mentation ait connexion pour la collecte des données dans les 10 Pro vinces ciblées par le PERSE ZR-SPACE-358644-GO-DIR / Contractualisation avec la fir Component 3: Strengthening Under Imple me LIFT TECH COMPANY pou IDA / 66920 Post Direct Selection Direct - National 0.00 2023-04-26 2023-04-25 2023-05-01 2023-04-24 2023-06-05 2023-12-02 Systems for Results mentation r l'acquisition de 1000 Tablet tes pour la collecte des donn ées scolaires 2022-2023 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Page 2 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-SPACE-227692-NC-DIR / Acquisition du logiciel TOMPR Component 3: Strengthening Pending Impl IDA / 66920 Post Direct Selection Direct 0.00 2021-09-14 2021-09-19 2021-10-24 2021-11-23 O pour la gestion comptable Systems for Results ementation du projet PERSE : TOMATE ZR-SPACE-272910-NC-RFB / RECRUTEMENT D'UN PRESTA TAIRE EN QUALITE D'UNE AG Component 3: Strengthening Single Stage - One E Pending Impl IDA / 66920 Post Request for Bids Open - National 0.00 2022-01-13 2022-01-18 2022-03-01 2022-03-31 2022-05-05 2022-11-01 ENCE DE VOYAGE POUR L'AC Systems for Results nvelope ementation QUISITION DES TITRES DE VO YAGE AINSI QUE LES FORMAL ITES Y RELATIVES ZR-SPACE-272913-NC-RFQ / RECRUTEMENT D'UN CABINE T EN CHARGE DE L'ENTRETIE Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-01-18 2022-03-15 2022-09-11 N ET MAINTENANCE DU MAT Systems for Results tions nvelope ementation ERIEL INFORMATIQUE, PLOM BERIE ET CLIMATISATION PO UR LE PROJET PERSE ZR-SPACE-305975-NC-RFQ / Contrat avec un assureur ma Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-07-30 2022-09-24 2023-03-23 ladie pour la prise en charge Systems for Results tions nvelope ementation des soins médicaux des mem bres de l'ECP PERSE ZR-SPACE-314511-NC-RFQ / RECRUTEMENT D'UNE SOCIE Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl IDA / 66920 Post Limited 0.00 2022-09-25 2022-11-20 2023-05-19 TE DE GARDIENNAGE POUR L Systems for Results tions nvelope ementation ES BUREAUX DU PERSE A KIN SHASA ZR-SPACE-326748-NC-RFQ / Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl PRODUCTION D'UN FILM DE S IDA / 66920 Post Limited 0.00 2022-11-30 2023-01-25 2023-07-24 Systems for Results tions nvelope ementation ENSIBILISATION AUX VBG/EA S/HS ET MGP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-SPACE-187618-CS-CQS / Component 3: Strengthening Consultant Qualifi Pending Impleme Sélection de la firme pour la IDA / 66920 Post Open - National 0.00 2021-02-09 2021-03-02 2021-04-15 2021-05-15 2021-06-19 2023-06-09 Systems for Results cation Selection ntation revue du Plan de Travail Ann uel (PTA) ZR-SPACE-191896-CS-CQS / Sélection du Cabinet pour le Component 3: Strengthening Consultant Qualifi IDA / 66920 Post Open - National 96,825.08 Completed 2020-09-15 2020-09-28 2020-10-06 2020-11-03 2020-11-02 2020-11-10 2020-12-09 2020-12-01 2021-01-14 2021-01-30 2021-10-15 recrutement du personnel clé Systems for Results cation Selection de l'équipe de gestion du pro jet ZR-SPACE-198450-CS-CQS / Sélection du Cabinet Firme l' Component 3: Strengthening Consultant Qualifi Audit externe du Programme IDA / 66920 Post Limited 106,350.00 Signed 2020-10-08 2020-10-06 2020-10-22 2020-11-02 2020-10-29 2020-11-12 2020-11-19 2020-11-19 2020-12-19 Systems for Results cation Selection des Dépenses Eligibles (EEP) au 30 novembre 2020 ZR-SPACE-187535-CS-UN / S élection de l'Agence des Nati Component 3: Strengthening UN Agencies (Dire ons Unies pour la mise en œ IDA / 66920 Prior Direct 15,000,000.00 Signed 2020-11-03 2021-01-12 2020-11-10 Systems for Results ct) uvre du programme pilote " é coles sécurisées et inclusives " : UNFPA ZR-SPACE-221809-CS-QCBS / Cabinet d'Assistance Techni Component 3: Strengthening Quality And Cost- Open - Internationa Under Implement que pour appuyer la mise en IDA / 66920 Post 0.00 2021-03-05 2021-03-23 2021-03-19 2021-06-25 2021-04-16 2021-05-14 2021-05-28 2021-06-25 2021-07-30 2022-07-30 Systems for Results Based Selection l ation oeuvre de l'ILD 5 et les activ ités de la Composante 3.2 lié es au MGP et l'EC ZR-SPACE-223392-CS-QCBS / Sélection du Cabinet d'assis tance technique chargé d'ap Component 3: Strengthening Quality And Cost- Open - Internationa Under Implement IDA / 66920 Post 0.00 2021-03-10 2021-03-23 2021-03-31 2021-06-25 2021-04-28 2021-05-26 2021-06-25 2021-07-30 2021-09-03 2022-09-03 puyer les activités liées aux I Systems for Results Based Selection l ation LD 2,3,6 et 7 et de renforcer les Directions responsables d e ces ILD ZR-SPACE-221808-CS-QCBS / Sélection du Cabinet / ONG d'Assistance technique pour Component 3: Strengthening Consultant Qualifi Open - Internationa Under Implement appuyer les activités suivant IDA / 66920 Post 0.00 2021-03-22 2021-03-29 2021-04-12 2021-04-08 2021-05-26 2021-06-19 2021-06-09 2021-11-10 2021-07-14 2022-01-10 Systems for Results cation Selection l ation es de la Composante 3.1: ren forcer le SIGE et entreprendr e une revue fonctionnelle de la DIGE. ZR-SPACE-226130-CS-QBS / Sélection du Cabinet / ONG d Component 3: Strengthening Quality Based Sel Open - Internationa Under Implement 'Assistance technique pour le IDA / 66920 Post 0.00 2021-04-01 2021-04-01 2021-04-22 2021-04-07 2021-06-05 2021-07-07 2021-07-03 2021-08-02 2021-09-01 2021-10-06 2022-10-06 Systems for Results ection l ation s activités de Communication ( y compris vis-à-vis du MGP) ZR-SPACE-241434-CS-QCBS / Sélection d'un Cabinet pour la formation, sensibilisation e Component 3: Strengthening Quality And Cost- Open - Internationa Under Implement IDA / 66920 Post 0.00 2021-06-29 2021-08-05 2021-07-20 2021-08-09 2021-08-17 2021-09-14 2021-09-15 2021-10-13 2021-11-17 2023-11-07 t suivi sur les Violences Basé Systems for Results Based Selection l ation es sur le Genre (VBG) au nive au des Points Focaux MGP/ P ERSE ZR-SPACE-187608-CS-QCBS / Sélection des firmes pour la Component 3: Strengthening Quality And Cost- Open - Internationa réalisation des reformes du s IDA / 66920 Prior 0.00 Canceled 2020-08-31 2020-09-21 2020-11-04 2020-12-02 2021-01-01 2021-02-05 2021-03-12 2023-03-02 Systems for Results Based Selection l ystème d'enseignement prim aire et l'amélioration de la go uvernance ZR-SPACE-241554-CS-QCBS / Sélection du Consultant Fir me chargé (i) de la Vérificati Component 3: Strengthening Quality And Cost- Under Implement on des indicateurs Liés au Dé IDA / 66920 Post Open - National 0.00 2021-06-29 2021-08-02 2021-07-20 2021-08-09 2021-08-04 2021-09-01 2021-09-15 2021-10-13 2021-11-10 2022-11-10 Systems for Results Based Selection ation caissements, (ii) de l'audit de s Dépenses Eligibles au Progr amme (DEP) et (iii) de l'audit financier des comptes du pro jet ZR-SPACE-187612-CS-QCBS / Sélection de la firme pour la vérification des Indicateurs Li Component 3: Strengthening Quality And Cost- Open - Internationa IDA / 66920 Prior 0.00 Canceled 2020-09-10 2020-10-01 2020-11-14 2020-12-12 2021-01-11 2021-02-15 2021-03-22 2024-03-21 és aux Décaissements ( ILD) Systems for Results Based Selection l et de l'Audit externe du Progr amme des Dépenses Eligible s (EEP) et du SECOPE Page 3 ZR-SPACE-221810-CS-QCBS / Un Cabinet d'Assistance Tec Component 3: Strengthening Quality And Cost- Open - Internationa IDA / 66920 Post 0.00 Canceled 2021-03-05 2021-04-01 2021-03-19 2021-04-08 2021-04-16 2021-05-14 2021-05-28 2021-06-25 2021-07-23 2022-07-23 hnique pour le suivi par des t Systems for Results Based Selection l iers des autres assistances te chniques ZR-SPACE-246958-CS-CQS / Component 3: Strengthening Consultant Qualifi Under Implement ASSISTANCE TECHNIQUE PO IDA / 66920 Post Open - National 0.00 2021-08-12 2021-08-05 2021-08-26 2021-10-09 2021-10-23 2021-11-27 2022-05-26 Systems for Results cation Selection ation UR L'EVALUATION SOCIALE D U PROJET PERSE ZR-SPACE-296511-CS-QCBS / Recrutement d'un Consulta nt cabinet en soutien de la C Component 1: Enabling Free Quality And Cost- Open - Internationa Pending Impleme omposante 1 (LDs2&3), de la IDA / 66920 Prior 0.00 2022-06-06 2022-06-27 2022-08-10 2022-09-07 2022-10-07 2022-11-11 2022-12-16 2023-12-16 Access for All Based Selection l ntation Composante 2 5ILDs 6&7) et de la Composante 3.1 (Elabo ration et contrôle du budget ) pour le Projet PERSE ZR-SPACE-296505-CS-CQS / Recrutement d'un Consultant Cabinet chargé d'Assistance Technique en soutien à la for Component 3: Strengthening Consultant Qualifi Under Implement mation des COGES, à la Com IDA / 66920 Prior Limited 0.00 2022-06-02 2022-07-25 2022-06-16 2022-07-16 2022-08-20 2023-02-16 Systems for Results cation Selection ation posante3.2 (Engagement des Citoyens et Mécanisme de G estion des Plaintes) et de la Composante 3.1 (Elaboration et contrôle du budget) ZR-SPACE-305078-CS-QCBS / Recrutement d'un consultan t Cabinet d'Assistance Techni que chargé d'appuyer, dans l Component 3: Strengthening Quality And Cost- Under Implement IDA / 66920 Prior Open - National 0.00 2022-08-05 2022-08-26 2022-10-09 2022-11-06 2022-12-06 2023-01-10 2023-02-14 2024-02-14 e cadre du projet PERSE, la r Systems for Results Based Selection ation ationalisation des écoles, bur eaux gestionnaires et service s du MEPST ainsi que du proc essus de leur création ZR-SPACE-305103-CS-QCBS / Recrutement d'un Consulta nt Cabinet d'Assistance Tech nique chargé d'appuyer le M Component 3: Strengthening Quality And Cost- Under Implement IDA / 66920 Prior Open - National 0.00 2022-08-08 2022-08-29 2022-10-12 2022-11-09 2022-12-09 2023-01-13 2023-02-17 2024-02-17 EPST dans la mise en place d Systems for Results Based Selection ation 'un nouveau système de recr utement, transparent, objecti f et basé sur l'équité, d'ensei gnants et Directeurs d'école primaire ZR-SPACE-307961-CS-QCBS / RECRUTEMENT D'UN CABIN Component 3: Strengthening Quality And Cost- Under Implement ET D'AUDIT COMPTABLE ET F IDA / 66920 Post Open - National 0.00 2022-09-05 2022-12-15 2022-09-26 2022-11-09 2022-12-07 2023-01-06 2023-02-10 2023-03-17 2024-03-16 Systems for Results Based Selection ation INANCIER DU PERSE, EXERCI CES 2022,2023 ET 2024 ZR-SPACE-326745-CS-CQS / RECRUTEMENT D’UN CONSU LTANT (FIRME) CHARGE (I) D E L’ELABORATION DU RAPPO Component 3: Strengthening Consultant Qualifi Under Implement IDA / 66920 Post Open - National 0.00 2022-11-21 2023-02-14 2022-12-12 2023-01-25 2023-02-24 2023-03-31 2023-09-27 RT DE CERTIFICATION DE L’A Systems for Results cation Selection ation TTEINTE DE L’INDICATEUR LI E AU DECAISSEMENT (ILD) ET (II) DE L’AUDIT DES DEPENSE S ELIGIBLES AU PROGRAMME (DEP) ZR-SPACE-359741-CS-QCBS / RECRUTEMENT D'UN CONS ULTANT (FIRME) CHARGE (I) DE L'ELABORATION DU RAPP Component 3: Strengthening Quality And Cost- Pending Impleme IDA / 66920 Post Open - National 0.00 2023-05-08 2023-05-29 2023-07-12 2023-08-09 2023-09-08 2023-10-13 2023-11-17 2024-11-16 ORT DE CERTIFICATION DE L' Systems for Results Based Selection ntation ATTEINTE DE L'INDICATEUR L IE AU DECAISSEMENT (ILD) E T (II) DE L'AUDIT DES DEPEN SES ELIGIBLES AU PROGRAM ME (DEP) ZR-SPACE-359742-CS-QCBS / Sélection du Prestataire Tier s chargé du suivi des activité Component 3: Strengthening Quality And Cost- IDA / 66920 Post Open - National 0.00 Under Review 2023-05-15 2023-06-05 2023-06-05 2023-07-19 2023-08-16 2023-09-15 2023-10-20 2023-11-24 2024-11-23 s de renforcement des capaci Systems for Results Based Selection tés dans le cadre de la mise en oeuvre du projet PERSE INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-SPACE-187600-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Sélection des consultants ( 2) IDA / 66920 Post Open 0.00 2020-09-07 2020-09-28 2020-10-26 2021-08-11 2020-11-16 2021-08-16 2020-12-21 2022-12-11 Systems for Results ant Selection ation chargés du suivi de l'engage ment citoyen ZR-SPACE-187601-CS-INDV / Sélection des consultants nat ionaux ( 10) au niveau provin Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Open 0.00 2020-09-15 2020-09-17 2020-11-03 2020-11-24 2020-12-29 2022-12-19 cial pour la supervision, le so Systems for Results ant Selection ation utien et le suivi des reformes du projet : plusieurs petits m archés ZR-SPACE-187573-CS-INDV / Sélection du spécialiste resp Component 3: Strengthening Individual Consult onsable pour appuyer le renf IDA / 66920 Post Open 0.00 Signed 2020-09-10 2020-09-28 2020-10-29 2021-08-11 2020-11-19 2021-08-16 2020-12-24 2022-12-14 Systems for Results ant Selection orcement des réseaux d'écol es et Bureaux gestionnaires ZR-SPACE-187592-CS-INDV / Component 3: Strengthening Individual Consult Sélection du Spécialiste char IDA / 66920 Post Open 0.00 Signed 2020-09-14 2020-09-28 2020-11-02 2021-06-23 2020-11-23 2021-08-15 2020-12-28 2022-12-18 Systems for Results ant Selection gé du suivi-évaluation du pro jet ZR-SPACE-187590-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Sélection du Spécialiste en s IDA / 66920 Post Open 0.00 2020-09-15 2020-09-30 2020-11-03 2020-11-24 2020-12-29 2022-12-19 Systems for Results ant Selection ation auvegardes sociales ZR-SPACE-187548-CS-INDV / Component 3: Strengthening Individual Consult Sélection du Coordonnateur IDA / 66920 Post Open 0.00 Signed 2020-09-14 2020-09-17 2020-11-02 2021-06-07 2020-11-16 2021-08-12 2020-12-14 2022-12-04 Systems for Results ant Selection adjoint du projet PERSE ZR-SPACE-187555-CS-INDV / Sélection d'un Consultant int Component 3: Strengthening Individual Consult Under Implement ernational pour appuyer les s IDA / 66920 Post Open 0.00 2020-09-10 2020-09-28 2020-10-29 2020-11-12 2020-12-17 2021-02-27 Systems for Results ant Selection ation ystèmes d'information et de paiement des salaires Page 4 ZR-SPACE-187561-CS-INDV / Sélection du spécialiste resp Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Open 0.00 2020-09-13 2021-02-05 2020-11-01 2020-11-22 2020-12-27 2022-12-17 onsable pour le recrutement Systems for Results ant Selection ation basé sur le mérite ZR-SPACE-187576-CS-INDV / Sélection d'un Consultant int Component 3: Strengthening Individual Consult Pending Impleme IDA / 66920 Post Open 0.00 2020-09-17 2020-11-05 2020-11-19 2020-12-24 2022-12-14 ernational pour la gestion fin Systems for Results ant Selection ntation ancière du projet ZR-SPACE-187579-CS-INDV / Sélection du Consultant natio Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Open 0.00 2020-09-15 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2022-12-19 nal spécialiste en gestion fin Systems for Results ant Selection ation ancière du projet ZR-SPACE-187580-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Sélection du Spécialiste en P IDA / 66920 Post Open 0.00 2020-09-10 2021-01-26 2020-10-29 2020-11-12 2020-12-17 2022-12-07 Systems for Results ant Selection ation assation des marchés ZR-SPACE-187582-CS-INDV / Component 3: Strengthening Individual Consult Sélection du Spécialiste char IDA / 66920 Post Open 0.00 Signed 2020-09-15 2020-09-28 2020-11-03 2021-08-11 2020-11-24 2021-08-16 2020-12-29 2022-12-19 Systems for Results ant Selection gé des sauvegardes environn ementales ZR-SPACE-187575-CS-INDV / Sélection du spécialiste resp Component 3: Strengthening Individual Consult IDA / 66920 Post Open 0.00 Signed 2020-09-14 2020-12-17 2020-11-02 2022-08-11 2020-11-23 2021-08-16 2020-12-28 2022-12-18 onsable pour appuyer la gest Systems for Results ant Selection ion des finances publiques ZR-SPACE-187620-CS-CDS / Component 3: Strengthening Sélection du Coordonnateur IDA / 66920 Post Direct Selection Direct 7,500.00 Signed 2020-09-10 2020-10-16 2020-09-20 2021-01-03 2020-11-01 2021-01-09 2022-10-22 Systems for Results du Projet : Prof Valère MUNS YA ZR-SPACE-209760-CS-CDS / Component 3: Strengthening Sélection chargée de Passati IDA / 66920 Post Direct Selection Direct 7,500.00 Signed 2020-12-14 2021-02-10 2020-12-18 2020-12-30 2020-12-29 2021-01-06 2021-06-27 Systems for Results on des Marchés : Fleur SHWE KA ZR-SPACE-216049-CS-CDS / Sélection du Consultant Spéc Component 3: Strengthening IDA / 66920 Post Direct Selection Direct 27,000.00 Signed 2021-01-26 2021-02-10 2021-02-05 2020-12-30 2021-02-26 2021-01-06 2021-08-25 ialiste en Communication de Systems for Results l'ECP PERSE: Mme BIBICHE M ODJAKA ZR-SPACE-216061-CS-CDS / Component 3: Strengthening Sélection du Spécialiste en V IDA / 66920 Post Direct Selection Direct 36,000.00 Signed 2021-01-26 2021-02-10 2021-02-05 2020-12-30 2021-03-05 2021-01-06 2021-09-01 Systems for Results BG : Jeanine Gabrielle NGUN GU ZR-SPACE-221812-CS-CDS / Sélection du Consultant Princ ipal ( avec son équipe de 4 e Component 3: Strengthening xperts) pour la conduite des IDA / 66920 Post Direct Selection Direct 93,500.00 Completed 2021-03-08 2021-03-10 2021-03-18 2021-03-15 2021-04-08 2021-03-30 2021-07-07 2021-10-15 Systems for Results opérations de géolocalisation des écoles primaires dans le cadre du PERSE : Roger VIBIL A ZR-SPACE-221817-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Assistant ponctuel logisticien IDA / 66920 Post Direct 0.00 2021-02-25 2021-02-26 2021-03-07 2021-03-12 2021-03-22 2021-06-20 Systems for Results ant Selection ation : ARLY MANGELELE BOKOMB E ZR-SPACE-223393-CS-INDV / Consultant Architecte chargé de mener les études pour la r Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2021-03-10 2021-01-20 2021-03-15 2021-04-05 2021-05-03 2021-08-01 éhabilitation des bureaux du Systems for Results ant Selection ation SPACE qui serviront des bure aux définitifs pour le projet P ERSE ZR-SPACE-223394-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Sélection du Comptable pour IDA / 66920 Post Open 0.00 2021-03-10 2021-03-23 2021-04-28 2021-05-19 2021-06-23 2021-12-20 Systems for Results ant Selection ation le projet PERSE ZR-SPACE-221823-CS-CDS / Recrutement du Prestataire p Component 3: Strengthening IDA / 66920 Post Direct Selection Direct 830,726.00 Signed 2021-03-21 2021-03-03 2021-03-31 2021-03-25 2021-04-29 2021-07-08 2021-10-26 our le Développement de l'ap Systems for Results plication ALLO ECOLE : INFOS ET ZR-SPACE-231137-CS-INDV / RENOUVELLEMENT CONTRAT Component 3: Strengthening Individual Consult CHARGEE DE PASSATION DE IDA / 66920 Post Direct 0.00 Signed 2021-04-22 2021-03-20 2021-05-02 2021-03-26 2021-05-23 2021-03-30 2021-06-27 2022-06-27 Systems for Results ant Selection S MARCHES MADAME FLEUR SHWEKA (12 MOIS) ZR-SPACE-234473-CS-INDV / Sélection du Consultant char gé de l'élaboration du Plan d Component 3: Strengthening Individual Consult Under Implement e Gestion Environnemental e IDA / 66920 Post Limited 0.00 2021-06-30 2021-08-05 2021-07-05 2021-07-19 2021-08-09 2021-10-08 Systems for Results ant Selection ation t Social Générique (PGES) po ur le projet PERSE ( Le volet Social étant prépondérant da ns le cadre de ce marché) ZR-SPACE-241555-CS-INDV / Renouvellement du Contrat d Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Direct 0.00 2021-06-27 2021-05-27 2021-07-07 2021-07-14 2021-07-28 2022-07-28 e la Chargée de logistique- A Systems for Results ant Selection ation RLLY MANGELELE ( pour 12 mois) ZR-SPACE-187591-CS-INDV / Sélection du Spécialiste dans Component 3: Strengthening Individual Consult IDA / 66920 Post Open 0.00 Canceled 2020-09-09 2020-10-28 2020-11-18 2020-12-23 2022-12-13 la gestion des Violences Basé Systems for Results ant Selection es sur le Genre ( VBG) ZR-SPACE-248688-CS-INDV / Component 3: Strengthening Individual Consult Under Implement Sélection spécialiste en plani IDA / 66920 Post Open 0.00 2021-08-17 2020-09-17 2021-10-05 2021-10-26 2021-11-30 2022-11-30 Systems for Results ant Selection ation fication et vérification du proj et PERSE ZR-SPACE-248700-CS-INDV / Component 3: Strengthening Individual Consult Sélection Expert en communi IDA / 66920 Post Open 0.00 Signed 2021-08-17 2021-08-17 2021-10-05 2021-07-23 2021-10-26 2021-07-23 2021-11-30 2022-05-29 Systems for Results ant Selection cation Projet PERSE ZR-SPACE-249050-CS-INDV / Sélection d'un Spécialiste de Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2021-09-14 2020-11-26 2021-09-19 2021-10-03 2021-10-24 2022-10-24 s Systèmes d’information de Systems for Results ant Selection ation gestion de l’éducation et du paiement (SIGEP) Page 5 ZR-SPACE-241557-CS-CDS / Sélection du Prestataire Tiers chargé du suivi des activités Component 3: Strengthening Pending Impleme IDA / 66920 Post Direct Selection Direct 0.00 2021-09-14 2021-09-24 2021-11-12 2022-11-12 de renforcement des capacit Systems for Results ntation és dans le cadre de la mise e n oeuvre du projet PERSE : O NG CORDAID ZR-SPACE-231135-CS-INDV / RENOUVELLEMENT CONTRAT Component 3: Strengthening Individual Consult Under Implement SPECIALISTE EN VIOLENCES IDA / 66920 Post Direct 0.00 2021-06-30 2021-03-01 2021-07-10 2021-07-31 2021-09-04 2023-08-25 Systems for Results ant Selection ation BASEES SUR LE GENRE : MA DAME JEANINE NGUNGU KWA TE (12 MOIS) ZR-SPACE-261331-CS-INDV / Component 3: Strengthening Individual Consult Under Implement SELECTION CAISSIER(RE) PO IDA / 66920 Post Open 0.00 2021-11-03 2022-02-10 2021-12-22 2022-01-12 2022-02-16 2022-08-15 Systems for Results ant Selection ation UR LE PROJET PERSE ZR-SPACE-261334-CS-INDV / Component 3: Strengthening Individual Consult Under Implement SELECTION D'UN(E) ASSISTA IDA / 66920 Post Open 0.00 2021-11-03 2022-02-10 2021-12-22 2022-01-12 2022-02-16 2022-08-15 Systems for Results ant Selection ation NT(E) ADMINISTRATIF POUR L E PROJET PERSE ZR-SPACE-261338-CS-INDV / SELECTION D'UN(E) ASSISTA Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Open 0.00 2021-11-03 2022-02-10 2021-12-22 2022-01-12 2022-02-16 2022-08-15 NT(E) AU PROGRAMME POUR Systems for Results ant Selection ation LE PROJET PERSE ZR-SPACE-262236-CS-INDV / SELECTION DES CHAUFFEUR Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2021-11-16 2022-02-10 2021-11-21 2021-12-12 2022-01-16 2022-07-15 S POUR LE PROJET PERSE A K Systems for Results ant Selection ation INSHASA (5 CONTRATS POUR 12 MOIS) ZR-SPACE-272626-CS-INDV / RECRUTEMENT D'UN CONSUL Component 3: Strengthening Individual Consult Pending Impleme TANT INDIVIDUEL EN QUALIT IDA / 66920 Post Open 0.00 2022-01-11 2022-03-01 2022-03-22 2022-04-26 2022-10-23 Systems for Results ant Selection ntation E DE SUPERVISEUR PROVINCI AL BASE A KINSHASA ZR-SPACE-262238-CS-INDV / SELECTION DES ASSISTANTS Component 3: Strengthening Individual Consult Under Implement ADMINISTRATIFS ET FINANCI IDA / 66920 Post Open 0.00 2021-11-16 2022-03-09 2022-01-04 2022-01-25 2022-03-01 2022-08-28 Systems for Results ant Selection ation ERS (10 CONTRATS) POUR LE PROJET PERSE EN PROVINCE (12 MOIS) ZR-SPACE-284618-CS-CDS / CONTRACTUALISATION AVEC LE CABINET PriceWatherHous eCoopers POUR LA VERIFICA TION DES INDICATEURS LIES Component 3: Strengthening Under Implement IDA / 66920 Prior Direct Selection Direct 0.00 2022-03-15 2022-03-18 2022-03-25 2022-03-19 2022-05-29 2022-11-25 AUX DECAISSEMENTS (ILD) E Systems for Results ation T L'AUDIT DES DEPENSES ELI GIBLES AU PROGRAMME (DE P) DANS LES PROVINCES DU KWILU, KONGO CENTRAL, KI NSHASA, LOMAMI, KASAÏ ORI ENTAL ZR-SPACE-284619-CS-CDS / CONTRACTUALISATION AVEC LE CABINET MGI STRONG NK V POUR L'AUDIT FINANCIER Component 3: Strengthening Under Implement DES COMPTES DU PROJET PO IDA / 66920 Post Direct Selection Direct 0.00 2022-03-15 2022-03-18 2022-03-25 2022-03-21 2022-05-29 2022-11-25 Systems for Results ation UR LES 3 EXERCICES SUIVAN TS: (1) JUIN 2020 AU 31 DEC EMBRE 2020; (2) 01 JANVIER 2021 AU 31 DECEMBRE 2021 ; (3) 01 JANVIER 22 AU 31 DE CEMBRE 2022 ZR-SPACE-284617-CS-CDS / CONTRACTUALISATION AVEC LE CABINET COFIMA POUR LA VERIFICATION DES INDICATE Component 3: Strengthening Under Implement URS LIES AUX DECAISSEMEN IDA / 66920 Prior Direct Selection Direct 0.00 2022-03-15 2022-03-18 2022-03-25 2022-03-19 2022-05-29 2022-11-25 Systems for Results ation TS (ILD) ET L'AUDIT DES DEP ENSES ELIGIBLES AU PROGR AMME (DEP) DANS LES PROVI NCES DU NORD-KIVU, SUD-KI VU, ITURI, KASAÏ, kASAÏ CENT RAL ZR-SPACE-286586-CS-CDS / RENOUVELLEMENT CONTRAT Component 3: Strengthening Under Implement CHARGEE DE PASSATION DE IDA / 66920 Post Direct Selection Direct 0.00 2022-05-20 2022-03-28 2022-05-30 2022-08-03 2023-01-30 Systems for Results ation S MARCHES DU PROJET PERS E MADAME FLEUR SHWEKA ( 12 MOIS) ZR-SPACE-295474-CS-INDV / Recrutement d'un Consultant individuel pour l'accompagne ment de la cellule du Projet d Component 3: Strengthening Individual Consult Under Implement ans l'évaluation et coordinati IDA / 66920 Post Limited 0.00 2022-05-20 2022-07-20 2022-05-25 2022-06-15 2022-07-20 2023-01-16 Systems for Results ant Selection ation on des travaux réalisés par le s cabinets chargés de l'audit des Dépenses DEP et du cont rôle des indicateurs de réalis ation ILD/RLD ZR-SPACE-300402-CS-INDV / RECRUTEMENT D'UN ASSIST Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2022-09-09 2022-08-31 2022-09-14 2022-10-05 2022-11-09 2023-05-08 ANT TECHNIQUE PROVINCIAL Systems for Results ant Selection ation BASE A KINSHASA ZR-SPACE-303555-CS-CDS / CONSULTANT PONCTUEL PO Component 3: Strengthening Under Implement UR UN APPUI TECHNIIQUE A L IDA / 66920 Post Direct Selection Direct - National 0.00 2022-08-11 2022-07-29 2022-08-21 2022-10-25 2023-04-23 Systems for Results ation A PASSATION DES MARCHES DU PROJET PERSE ( Mr LAURE NT TSHIMBIYE) ZR-SPACE-304959-CS-CDS / Renouvellement du contrat d Component 3: Strengthening Under Implement IDA / 66920 Post Direct Selection Direct - National 0.00 2022-07-19 2022-07-28 2022-07-29 2022-10-02 2023-03-31 e la chargée de la logistique Systems for Results ation (Madame Arlly MANGELELE) pour 12 mois ZR-SPACE-304955-CS-INDV / Recrutement de 10 chauffeur Component 3: Strengthening Individual Consult Pending Impleme IDA / 66920 Post Limited 0.00 2022-07-19 2022-07-24 2022-08-14 2022-09-18 2023-03-17 s pour les véhicules des ante Systems for Results ant Selection ntation nnes provinciales du Projet ZR-SPACE-300117-CS-INDV / Component 3: Strengthening Individual Consult Under Implement RECRUTEMENT DU SPECIALIS IDA / 66920 Post Limited 0.00 2022-08-26 2022-09-13 2022-08-31 2022-09-21 2022-10-26 2023-04-24 Systems for Results ant Selection ation TE PROVINCIAL POUR LE NOR D-KIVU Page 6 ZR-SPACE-314053-CS-INDV / RECRUTEMENT D’UN(E) ASSI STANT(E) SPECIALISTE EN VI Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2022-09-19 2022-12-20 2022-09-24 2022-10-15 2022-11-19 2023-05-18 OLENCES BASEES SUR LE GE Systems for Results ant Selection ation NRE AU SEIN DE L’EQUIPE DE CO ORDINATION DU PROJET ZR-SPACE-326740-CS-CDS / CONTRACTUALISATION AVEC LE CABINET PWC POUR LA MI SSION D'AUDIT DES DEPENS Component 3: Strengthening Pending Impleme ES ELIGIBLES AU PROGRAMM IDA / 66920 Post Direct Selection Direct - National 0.00 2022-11-21 2022-12-01 2023-02-04 2023-08-03 Systems for Results ntation E (DEP) POUR LA PERIODE A LLANT DU 1ER JANVIER AU 3 1 DECEMBRE 2022 ET VERIFI CATION DE L'INDICATEUR LIE AU DECAISSEMENT (ILD 5.2) ZR-SPACE-326743-CS-CDS / CONTRACTUALISATION AVEC LE CABINET COFIMA POUR LA MISSION D'AUDIT DES DEPE Component 3: Strengthening Pending Impleme NSES ELIGIBLES AU PROGRA IDA / 66920 Post Direct Selection Direct - National 0.00 2022-11-21 2022-12-01 2023-02-04 2023-08-03 Systems for Results ntation MME (DEP) POUR LA PERIOD E ALLANT DU 1ER JANVIER A U 31 DECEMBRE 2022 ET VE RIFICATION DE L'INDICATEUR LIE AU DECAISSEMENT (ILD 5 .2) ZR-SPACE-327666-CS-INDV / RECRUTEMENT D'UN ASSIST Component 3: Strengthening Individual Consult Under Implement IDA / 66920 Post Limited 0.00 2022-11-28 2022-12-20 2022-12-03 2022-12-24 2023-01-28 2023-07-27 ANT ADMINISTRATIF ET FINA Systems for Results ant Selection ation NCIER POUR LE KONGO CENT RAL ZR-SPACE-336148-CS-INDV / Component 3: Strengthening Individual Consult Under Implement RECRUTEMENT DU COORDO IDA / 66920 Post Open - National 0.00 2023-02-01 2023-02-22 2023-03-22 2023-04-12 2023-05-17 2023-11-13 Systems for Results ant Selection ation NNATEUR ADJOINT DU PERSE ZR-SPACE-343004-CS-CDS / CONTRACTUALISATION AVEC Component 3: Strengthening Pending Impleme IDA / 66920 Post Direct Selection Direct - National 0.00 2023-02-28 2023-03-10 2023-05-14 2023-11-10 LA FIRME INFOSET POUR L'E Systems for Results ntation XTENSION DU CENTRE D'APP EL ALLO-ECOLE Page 7 PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western and Central Africa : West Africa Coastal Areas Resilience Investment Project PLAN General Information Country: Western and Central Africa 2018-02-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience Investment Project Loan / Credit No: IDA / V1150, IDA / D2860, IDA / 62130, TF / A7130, TF / A7131 Ministry of Environnement/Directorate of Environment Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 39 / Aménagement de burea Component 4: National Coor Single Stage - One E 2019-02-2 ux pour l’unité de gestion du IDA / V1150 Post Request for Bids Open - National 90,000.00 81,133.59 Terminated 2018-05-07 2018-04-06 2018-05-12 2018-06-23 2018-05-07 2018-07-23 2018-05-26 2018-08-27 2018-08-29 dination nvelope 3 projet WACA 59 / Travaux d'aménagemen t du R+1 des bureaux pour l' UGP, Construction du mur de séparation, d'un parking pour Component 4: National Coor Single Stage - One E 2020-04-1 IDA / D2860 Post Request for Bids Open - National 190,000.00 0.00 Canceled 2019-06-27 2019-07-02 2019-08-13 2019-09-12 2019-10-17 10 voitures, un poste d'héber dination nvelope 4 gement (des compteurs et d u groupe électrogène) et am énagement de la cour (aires de circulation et jardin) 85 / Travaux d’aménagemen t de la cour du Ministère de l' Component 2: Strengthening Request for Quota Single Stage - One E 2021-01-1 environnement, du développ IDA / D2860 the Policy and Institutional F Post Limited 105,000.00 126,079.40 Signed 2020-05-19 2020-04-24 2020-07-14 2020-08-29 tions nvelope 0 ement durable et de la prote ramework ction de la nature - en un (01 ) lot 114 / Travaux de constructio n de la clôture de la direction Component 4: National Coor Request for Quota Single Stage - One E 2020-12-0 IDA / D2860 Post Open - National 70,000.00 55,047.27 Signed 2020-07-14 2020-09-08 2022-02-19 régionale des forestiers de la dination tions nvelope 8 réserve de Togodo Nord à AT AKPAME 88 / Travaux d'aménagemen Component 4: National Coor Request for Quota Single Stage - One E 2021-03-0 t du R+1 des bureaux pour l' IDA / D2860 Post Limited 152,728.00 0.00 Signed 2020-07-12 2020-07-16 2020-09-06 dination tions nvelope 5 UGP WACA ResIP, en lot uniq ue 104 / Travaux de protection Component 3: Strengthening d’urgence de la côte par la te 2021-02-1 IDA / D2860 National Physical and Social Post Direct Selection Direct 909,090.90 899,211.65 Signed 2020-07-08 2020-07-03 2020-07-13 2020-08-19 2020-08-17 2020-09-18 chnique de juxtaposition de p 3 Investments uits en fûs granulitique. TG-WACA TOGO-204668-CW Component 3: Strengthening Request for Quota Single Stage - One E 2021-04-1 -RFQ / Construction de deux ( TF / A7131 National Physical and Social Post Limited 30,000.00 0.00 Canceled 2021-01-20 2021-03-18 tions nvelope 7 02) bâtiments à TOGODO Investments TG-WACA TOGO-204671-CW Component 3: Strengthening -RFQ / Travaux de constructi Request for Quota Single Stage - One E 2021-09-1 TF / A7130 National Physical and Social Post Limited 60,000.00 0.00 Canceled 2021-01-25 2021-03-22 on de deux (02) étangs et de tions nvelope 8 Investments deux (02) forages à TOGODO 92 / Travaux de construction Component 2: Strengthening Request for Quota Single Stage - One E 2021-02-2 IDA / D2860 Post Limited 106,000.00 0.00 Canceled 2020-07-01 2020-08-26 du siège de l'ANGE the Policy and Institutional F tions nvelope 2 ramework TG-WACA TOGO-239069-CW National Procure -RFQ / Travaux d'aménagem Component 2: Strengthening ment Document - ent (réhabilitation) de la salle Request for Quota Single Stage - One E 2022-02-1 IDA / D2860 the Policy and Institutional F Post Limited 1 Envelope proce 30,000.00 0.00 Signed 2021-09-20 2022-04-26 2021-11-15 de vidéo conférence du progr tions nvelope 3 ramework ss (Non Bank-SPD amme de licence en océano ) graphie de l'université de Kar a TG-WACA TOGO-239044-CW National Procure -RFB / TRAVAUX DE CONSTR Component 3: Strengthening ment Document - Single Stage - One E 2022-07-2 UCTION DES UNITES DE TRA IDA / D2860 National Physical and Social Post Request for Bids Open - National 1 Envelope proce 937,389.00 653,009.74 Signed 2021-10-15 2021-08-09 2021-10-20 2021-11-19 2021-11-02 2021-12-19 2021-11-13 2022-01-23 2022-03-29 nvelope 2 NSFORMATIONS DANS LES A Investments ss (Non Bank-SPD GR PILOTES EN SEPT (07) LO ) TS TG-WACA TOGO-255574-CW -RFB / TRAVAUX DE CONSTR UCTION ET DE REHABILITATI National Procure ON DE CABINES DE TOILETT Component 3: Strengthening ment Document - Single Stage - One E 2022-06-0 ES EQUIPES DE DISPOSITIFS IDA / D2860 National Physical and Social Post Request for Bids Open - National 1 Envelope proce 177,273.00 192,765.13 Signed 2021-10-29 2021-08-09 2021-11-03 2021-12-03 2021-11-03 2022-01-02 2021-11-14 2022-02-06 2022-05-07 nvelope 6 DE LAVE-MAIN DANS LES EC Investments ss (Non Bank-SPD OLES, ET DE CONSTRUCTION ) DE TOILETTES ECOSAN DANS LES MENAGES DE LA COMMU NE DES LACS 1( en 04 lots) TG-WACA TOGO-222964-CW National Procure -RFQ / renforcement (travaux Component 3: Strengthening ment Document - Request for Quota Single Stage - One E 2022-07-2 de réhabilitation) du poste se IDA / D2860 National Physical and Social Post Open - National 1 Envelope proce 109,000.00 0.00 Canceled 2021-11-02 2022-01-25 tions nvelope 4 cours d'urgence (PSR) du cor Investments ss (Non Bank-SPD ps des sapeurs - pompiers de ) la Région de Lomé Nord TG-WACA TOGO-239057-CW National Procure -RFB / construction de trois ( Component 2: Strengthening ment Document - 03) postes de relais forestier Single Stage - One E 2022-06-0 TF / A7130 the Policy and Institutional F Post Request for Bids Open - National 1 Envelope proce 90,000.00 0.00 Canceled 2021-10-25 2021-10-30 2021-11-29 2021-12-29 2022-02-02 s équipés de panneaux solair nvelope 2 ramework ss (Non Bank-SPD es et de forages à motricité h ) umaine dans le complexe d’a ires protégées de Togodo. Request for Bids - TG-WACA TOGO-239048-CW Component 2: Strengthening Single Stage - One E Small Works SPD 2022-07-0 -RFB / Réhabilitation de la br TF / A7130 the Policy and Institutional F Post Request for Bids Open - National 100,000.00 0.00 Canceled 2021-10-29 2021-11-03 2021-12-03 2022-01-02 2022-02-06 nvelope (1 envelope proce 6 igade de Togodo Nord ramework ss) National Procure TG-WACA TOGO-255877-CW Component 3: Strengthening ment Document - Request for Quota Single Stage - One E 2022-07-2 -RFQ / Réhabilitation de la bri TF / A7130 National Physical and Social Post Limited 1 Envelope proce 100,000.00 105,469.51 Signed 2021-12-05 2021-11-10 2022-01-30 2022-04-16 tions nvelope 9 gade de Togodo Nord Investments ss (Non Bank-SPD ) TG-WACA TOGO-255863-CW National Procure -RFQ / renforcement (travaux Component 3: Strengthening ment Document - Request for Quota Single Stage - One E 2022-05-1 de réhabilitation) du poste se IDA / D2860 National Physical and Social Post Limited 1 Envelope proce 109,000.00 93,880.49 Signed 2021-11-20 2021-11-10 2022-01-15 2022-04-16 tions nvelope 5 cours d'urgence (PSR) du cor Investments ss (Non Bank-SPD ps des sapeurs - pompiers de ) la Région de Lomé Nord Page 1 TG-WACA TOGO-255873-CW National Procure -RFQ / construction de trois ( Component 3: Strengthening ment Document - Request for Quota Single Stage - One E Under Imple 2022-07-1 03) postes de relais forestier TF / A7130 National Physical and Social Post Limited 1 Envelope proce 90,000.00 0.00 2021-11-24 2022-04-14 2022-01-19 tions nvelope mentation 8 s équipés de panneaux solair Investments ss (Non Bank-SPD es dans le complexe d’aires ) protégées de Togodo. TG-WACA TOGO-238677-CW National Procure -RFB / Construction de toilett Component 3: Strengthening ment Document - Single Stage - One E 2022-03-1 e dans les ménages (12 lots) IDA / D2860 National Physical and Social Post Request for Bids Open - National 1 Envelope proce 177,273.00 0.00 Canceled 2021-08-03 2021-08-08 2021-09-07 2021-10-07 2021-11-11 nvelope 1 et dans les écoles en six (06) Investments ss (Non Bank-SPD lots soit en 18 lots au total ) TG-WACA TOGO-204666-CW Component 3: Strengthening Single Stage - One E 2021-08-1 -RFB / Réhabilitation de 90 k TF / A7130 National Physical and Social Post Request for Bids Open - National 210,606.00 0.00 Canceled 2021-01-06 2021-01-11 2021-02-10 2021-03-12 2021-04-16 nvelope 4 m de piste, 7 ponceaux et 15 Investments radiers à Togodo National Procure TG-WACA TOGO-276081-CW ment Document - Component 4: National Coor Request for Quota Single Stage - One E Under Imple 2023-03-0 -RFQ / Aménagement de la c IDA / D2860 Post Limited 1 Envelope proce 54,546.00 0.00 2022-07-11 2022-07-18 2022-09-05 dination tions nvelope mentation 4 our et d'un parking de l'UGP ss (Non Bank-SPD WACA ResIP ) TG-WACA TOGO-238692-CW National Procure -RFB / Construction de forage Component 3: Strengthening ment Document - (dans les préfectures de Yoto Single Stage - One E 2023-04-0 IDA / D2860 National Physical and Social Post Request for Bids Open - National 1 Envelope proce 231,090.00 0.00 Signed 2022-08-31 2021-08-18 2022-09-05 2022-10-05 2022-04-21 2022-11-04 2022-09-02 2022-12-09 , Bas-Mono, Lacs, Vo, Avé, Zi nvelope 8 Investments ss (Non Bank-SPD o et Golfe) pour les sous-proj ) ets communautaire en cinq ( 05) lots TG-WACA TOGO-262261-CW Component 3: Strengthening Request for Quota -RFQ / construction et équipe Request for Quota Single Stage - One E Pending Imp 2022-11-2 TF / A7130 National Physical and Social Post Limited tions (Non Bank-S 20,000.00 0.00 2022-08-29 2022-10-24 ment de trois forages dans le tions nvelope lementation 3 Investments PD) complexe forestier de Togod o TG-WACA TOGO-290356-CW -RFQ / TRAVAUX DE CURAGE Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-05-2 DE LA MARE A TOMETY KOND TF / A7130 National Physical and Social Post Limited tions (Non Bank-S 128,000.00 0.00 2022-10-05 2022-11-30 tions nvelope lementation 9 JI ET DE CONSTRUCTION DE Investments PD) DEUX 02 ETANGS DANS LA F ORET TG-WACA TOGO-290370-CW Request for Quota Component 4: National Coor Request for Quota Single Stage - One E Pending Imp 2023-05-2 -RFQ / Travaux d'extension R IDA / D2860 Post Limited tions (Non Bank-S 150,000.00 0.00 2022-10-03 2022-11-28 dination tions nvelope lementation 7 +2 du Bâtiment de la Coordi PD) nation nationale TG-WACA TOGO-265124-CW Request for Bids - Component 3: Strengthening -RFB / Réhabilitation de pist Single Stage - One E Works French Civi 2023-06-1 TF / A7130 National Physical and Social Post Request for Bids Open - National 1,145,500.00 0.00 Signed 2022-08-24 2022-08-29 2022-08-29 2022-10-10 2022-09-21 2022-11-09 2022-10-07 2022-12-14 e, construction de ponceaux nvelope l Law (French) SP 2 Investments et radiers à Togodo D TG-WACA TOGO-306588-CW Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E 2023-03-3 -RFQ / Construction de la Brig IDA / D2860 National Physical and Social Post Limited tions (Non Bank-S 120,000.00 0.00 Signed 2022-10-05 2022-10-11 2022-11-30 tions nvelope 0 ades Forestières de Togodo S Investments PD) ud TG-WACA TOGO-313426-CW Request for Bids - -RFB / TRAVAUX DE CURAGE Component 3: Strengthening Open - Internationa Single Stage - One E Works (without pr Under Imple 2023-04-1 MÉCANIQUE ET DE RESTAUR IDA / 62130 National Physical and Social Post Request for Bids 7,289,738.00 0.00 2022-11-30 2022-10-24 2022-12-05 2022-11-07 2023-01-16 2022-12-22 2023-02-15 2023-03-02 2023-03-23 l nvelope equalification) SP mentation 9 ATION DES ECOSYSTEMES A Investments D SSOCIES DU CHENAL DE GBA GA TG-WACA TOGO-313517-CW Component 3: Strengthening Request for Quota Request for Quota Single Stage - One E Under Imple 2023-06-2 -DIR / TRAVAUX DE RÉHABILI IDA / 62130 National Physical and Social Post Limited tions (Non Bank-S 72,000.00 0.00 2022-11-02 2022-09-27 2022-12-28 tions nvelope mentation 6 TATION DE L'EPP AGBODRAF Investments PD) O National Procure TG-WACA TOGO-276078-CW Component 2: Strengthening ment Document - Request for Quota Single Stage - One E Under Imple 2023-02-0 -RFB / construction de la dire TF / A7130 the Policy and Institutional F Post Limited 1 Envelope proce 145,455.00 0.00 2022-06-13 2022-08-08 tions nvelope mentation 4 ctions préfectorale de Vo ramework ss (Non Bank-SPD ) TG-WACA TOGO-355573-CW -RFQ / achèvement des trava Request for Quota Component 4: National Coor Request for Quota Single Stage - One E Pending Imp 2024-01-2 ux de clôture de la direction r IDA / D2860 Post Limited tions (Non Bank-S 60,000.00 0.00 2023-06-04 2023-07-30 dination tions nvelope lementation 6 égionale de l'environnement PD) et des ressources forestières plateaux TG-WACA TOGO-355341-CW Component 3: Strengthening Request for Quota -RFQ / PRÉPARATION DU SOL Request for Quota Single Stage - One E Under Imple 2023-08-2 TF / A7130 National Physical and Social Post Limited tions (Non Bank-S 150,000.00 0.00 2023-05-29 2023-07-24 ET LABOUR MÉCANIQUE POU tions nvelope mentation 3 Investments PD) R LE REBOISEMENT PAR L'OD EF ET LA MAIRIE Vo3 Request for Quota TG-WACA TOGO-364034-CW Component 3: Strengthening Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-11-2 -RFQ / ENLÈVEMENT DE FUTS IDA / 62130 National Physical and Social Post Limited 126,000.00 0.00 2023-08-05 2023-09-30 tions nvelope s (Emergency) SP lementation 9 EN BÉTON NON ARME A ADIS Investments D -Competitive SEM GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 35 / Acquisition de matériels Component 4: National Coor Request for Quota Single Stage - One E IDA / V1150 Post Limited 15,000.00 0.00 Canceled 2018-05-13 2018-07-08 2019-01-04 informatiques dination tions nvelope 37 / Acquisition du mobilier Component 4: National Coor Request for Quota Single Stage - One E IDA / V1150 Post Limited 25,000.00 23,847.22 Signed 2018-07-17 2018-09-03 2018-09-11 2018-10-25 2019-03-10 de bureau pour la coordinatio dination tions nvelope n du projet 34 / Achat de fournitures de bureau, matériels de bureau et matériels d'entretien de b ureau en 03 lots. Component 4: National Coor Request for Quota Single Stage - One E Lot 1 fournitures de bureau ( IDA / V1150 Post Limited 10,000.00 7,637.09 Signed 2018-02-03 2018-02-16 2018-03-31 2018-08-08 2018-09-27 dination tions nvelope papiers rames, bics,..) Lot 2 matériels de bureau (re liure) et Lot 3 matériels d'entretien d e bureau (gel désinfectant, ... ). 35 BIS / Acquisition de fourni tures informatiques et de ma tériels informatiques en 02 lo ts : Lot 1 fournitures informat Component 4: National Coor Request for Quota Single Stage - One E IDA / V1150 Post Limited 27,000.00 26,469.61 Signed 2018-01-09 2018-01-11 2018-03-06 2018-08-08 2018-09-02 iques (cartouches d'encre, an dination tions nvelope tivirus, disques durs) et Lot 2 matériels informatiques (or dinateurs de bureau, ordinat eurs portables, scanners ..) Page 2 41BIS / Le matériel roulant s era composé comme suit : Lo t 1: 2 pick-up 4x4 double cab Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Limited 294,000.00 113,114.60 Signed 2019-04-20 2019-10-10 2019-06-15 2020-05-27 2019-12-12 ine tropicalisés pour les missi dination tions nvelope ons de terrain, Lot2: 01 stati on wagon , Lot3: 01 mini bus. 65 / Acquisition de matériel r Component 4: National Coor Request for Quota Single Stage - One E oulant (moto) pour les 7 CPD TF / A7130 Post Limited 40,000.00 0.00 Canceled 2019-07-01 2019-08-26 2020-02-22 dination tions nvelope D et le coursier de l'UGP 66 / Acquisition de GPS pour Component 4: National Coor Request for Quota Single Stage - One E les CPDD (07) et l'unité de ge TF / A7130 Post Limited 20,000.00 0.00 Signed 2019-07-02 2019-09-10 2019-08-27 2020-02-23 dination tions nvelope stion du projet (5) soit au tot al 12 GPS 58 / Acquisition de matériel et fourniture informatique po ur le projet (Ordinateur burea u +portable en poste de trav, Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Limited 50,000.00 0.00 Canceled 2019-06-16 2019-08-11 2020-02-07 copieur, imprimante couleur, dination tions nvelope blanc noir, clé USB multi copi eur, disque dure, vidéo proje cteur, onduleurs, modem pou r connexion Wifi, camera... 74 / Acquisition de 2 véhicul Component 2: Strengthening Request for Quota Single Stage - One E es de terrain pour l'Agence N IDA / D2860 the Policy and Institutional F Post Limited 85,000.00 0.00 Canceled 2019-06-26 2019-08-21 2020-02-17 tions nvelope ationale de Gestion de l'Envir ramework onnement 98 / Production des supports Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Open - National 36,364.00 16,660.05 Signed 2020-04-14 2020-06-09 2021-05-15 2020-12-06 de communications - un lot dination tions nvelope 83 / Acquisition de matériel et fourniture informatique, et Component 2: Strengthening matériels bureautique pour l Single Stage - One E IDA / D2860 the Policy and Institutional F Post Request for Bids Open - National 473,091.00 229,876.88 Signed 2020-06-25 2020-07-23 2020-06-30 2020-08-11 2020-09-25 2020-09-10 2020-10-26 2020-10-15 2021-04-24 2021-01-15 es CPDD, l'ANGE,Direction de nvelope ramework l'Environnement, Economie B leue et l'UGP WACA - Lot uni que 107 / Acquisition de matériel Component 2: Strengthening UN Agencies (Dire s roulants pour le Haut Conse IDA / D2860 the Policy and Institutional F Post Direct 232,727.00 0.00 Canceled 2020-06-02 2020-06-07 2020-07-12 2020-09-30 ct) il pour la Mer, l’ANGE et l’UG ramework P WACA ResIP 84BIS / Acquisition de matéri Component 2: Strengthening UN Agencies (Dire els roulants (engins TP) pour IDA / D2860 the Policy and Institutional F Post Direct 531,000.00 0.00 Canceled 2020-06-02 2020-06-07 2020-07-12 2020-11-12 ct) la Mairie d’Aného – lot uniqu ramework e 81 / Acquisition de matériels Component 2: Strengthening Request for Quota Single Stage - One E roulants pour le développem IDA / D2860 the Policy and Institutional F Post Limited 187,272.73 0.00 Canceled 2020-04-13 2020-06-08 2020-12-05 tions nvelope ent de l'économie bleue et l' ramework ANGE - 02 Lots 109 / Acquisition de trois (03 Component 4: National Coor Request for Quota Single Stage - One E ) téléphones portables pour l’ IDA / D2860 Post Limited 2,190.00 3,558.26 Signed 2020-08-16 2020-09-08 2020-10-11 2020-09-15 2020-10-27 dination tions nvelope UGP WACA ResIP 118 / Acquisition de mobilier Component 2: Strengthening Request for Quota Single Stage - One E de bureau pour l'ANGE et l'Ec IDA / D2860 the Policy and Institutional F Post Limited 36,364.00 6,936.87 Signed 2020-10-05 2021-05-18 2020-11-30 2022-02-01 2021-01-28 tions nvelope onomie Bleue ramework 120 / Acquisition de technol ogie des systèmes aériens sa Component 2: Strengthening ns pilotes (drone, logiciels, d Request for Quota Single Stage - One E IDA / D2860 the Policy and Institutional F Post Limited 70,000.00 0.00 Signed 2020-10-05 2021-06-28 2020-11-30 2021-03-01 e matériel et fourniture infor tions nvelope ramework matiques, Formations) pour l a production d'une cartograp hie 2D et 3D de gestion de la côte TG-WACA TOGO-211741-GO- Component 2: Strengthening UN / Acquisition de matériel r UN Agencies (Dire IDA / D2860 the Policy and Institutional F Post Direct 836,049.00 1,310,421.00 Signed 2020-10-15 2020-06-02 2020-10-16 2020-11-25 2020-11-22 2020-12-12 2021-02-20 oulant pour la coordination e ct) ramework t les partenaires TG-WACA TOGO-222191-GO- RFQ / Achat de véhicule Stati Component 2: Strengthening Request for Quota Single Stage - One E on WAGON pour le Ministère IDA / 62130 the Policy and Institutional F Post Limited 60,000.00 52,272.60 Signed 2021-05-25 2021-06-11 2021-07-20 2022-02-01 2021-08-19 tions nvelope de la Protection côtière, de la ramework Pêche et de l'Economie Mariti me TG-WACA TOGO-223503-GO- Component 2: Strengthening RFQ / Equipements de suivi e Request for Quota Single Stage - One E TF / A7130 the Policy and Institutional F Post Limited 18,182.00 0.00 Signed 2021-07-05 2022-04-28 2021-08-30 2021-09-29 t surveillance pour les comm tions nvelope ramework unautés locales (30 tablettes ) TG-WACA TOGO-232179-GO- RFQ / Acquisition de matériel pour la vidéoconférence pour Component 4: National Coor Request for Quota Single Stage - One E IDA / 62130 Post Limited 97,273.00 35,295.12 Signed 2021-07-20 2021-06-29 2021-09-14 2022-03-29 2021-10-14 la salle de réunion de l'UGP (l dination tions nvelope ot1) et pour la faculté de géo graphie de l'université de Kar a (lot2) TG-WACA TOGO-249718-GO- RFQ / ACQUISITION DE MOBIL Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Limited 50,000.00 42,374.50 Signed 2021-10-05 2021-09-07 2021-11-30 2022-02-01 2021-12-30 IER DE BUREAU POUR L'UNIT dination tions nvelope E DE COORDINATION NATION ALE TG-WACA TOGO-223620-GO- RFQ / acquisition de matériel Component 2: Strengthening Single Stage - One E Under Imple et équipement de laboratoire IDA / D2860 the Policy and Institutional F Post Request for Bids Open - National 110,000.00 0.00 2021-11-15 2021-10-01 2021-11-20 2021-12-20 2021-11-16 2022-01-19 2021-12-29 2022-02-23 2022-05-24 nvelope mentation pour les départements de gé ramework ographie des universités de L omé et Kara TG-WACA TOGO-265102-GO- Component 4: National Coor Request for Quota Single Stage - One E Under Imple RFQ / Fourniture et installatio IDA / D2860 Post Limited 54,000.00 0.00 2022-06-01 2022-02-25 2022-07-27 2023-01-23 dination tions nvelope mentation n de groupe électrogène TG-WACA TOGO-276063-GO- Component 3: Strengthening RFB / Acquisition et installati Open - Internationa Single Stage - One E Pending Impl IDA / D2860 National Physical and Social Post Request for Bids 650,000.00 0.00 2022-09-30 2022-10-05 2022-11-16 2022-12-16 2023-01-20 2023-07-19 on d'un centre de contrôle et l nvelope ementation Investments d'une station météorologique marine TG-WACA TOGO-276061-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de matériel IDA / D2860 National Physical and Social Post Limited 100,000.00 0.00 2022-06-28 2022-08-31 2023-02-27 tions nvelope ementation de collecte des données par l Investments es institutions Page 3 TG-WACA TOGO-260437-GO- RFB / FOURNITURE ET INSTAL LATION DE MINI CENTRALES SOLAIRES AVEC RESEAU ELE Component 3: Strengthening CTRIQUE, DE PLATEFORMES Single Stage - One E TF / A7130 National Physical and Social Post Request for Bids Open - National 218,000.00 0.00 Signed 2022-07-28 2022-01-31 2022-08-02 2022-09-01 2022-04-20 2022-10-01 2022-08-12 2022-11-05 2023-03-05 MULTIFONCTIONNELLES ALIM nvelope Investments ENTEES PAR LA CENTRALE S OLAIRE ET DES KITS DE LAMP ADAIRES AUTONOMES EN 04 LOTS DANS 04 LOCALITES (A damé, Afito, Godjinmé et Nya massiva) TG-WACA TOGO-223532-GO- RFQ / Acquisition d'équipeme nt pour la mise en place d'un Component 2: Strengthening e base de données de gestio Request for Quota Single Stage - One E IDA / D2860 the Policy and Institutional F Post Limited 95,454.00 0.00 Signed 2022-10-05 2022-04-26 2022-11-30 2023-02-28 n des ouvrages côtiers (serve tions nvelope ramework ur, ordinateurs portables, dis que durs externe, appareil p hoto professionnel, etc...) et des ordinateurs portables TG-WACA TOGO-292672-GO- RFQ / Acquisition d'équipeme nts complémentaires de prod Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl uction des plants et d'expéri TF / A7130 the Policy and Institutional F Post Limited 54,000.00 0.00 2022-09-05 2022-10-31 2022-11-30 tions nvelope ementation mentation pour le centre se ramework mencier de Davié (Ombrière, Humidi-mètre ,PH-mètre, Mél angeur de terreau) TG-WACA TOGO-292843-GO- Component 3: Strengthening Request for Quota Single Stage - One E Under Imple RFQ / Achat d'un porte-char IDA / D2860 National Physical and Social Post Limited 70,000.00 0.00 2022-07-25 2022-06-08 2022-09-19 2023-03-18 tions nvelope mentation pour la commune Lacs1 Investments TG-WACA TOGO-306594-GO- Component 2: Strengthening Single Stage - One E Pending Impl RFB / Acquisition des équipe IDA / D2860 the Policy and Institutional F Post Request for Bids Open - National 360,000.00 0.00 2022-09-30 2022-10-05 2022-11-04 2022-12-04 2023-01-08 2023-01-20 nvelope ementation ments du studio (Météo médi ramework a) TG-WACA TOGO-313510-GO- Component 3: Strengthening RFQ / Fourniture et pose de p Request for Quota Single Stage - One E IDA / 62130 National Physical and Social Post Limited 18,000.00 0.00 Signed 2022-11-05 2022-08-24 2022-12-31 2023-06-29 anneaux de signalisation sur tions nvelope Investments les sites de travaux de prote ction côtière TG-WACA TOGO-326628-GO- RFQ / Acquisition des équipe Component 3: Strengthening ments de maraichage (Bande Request for Quota Single Stage - One E Pending Impl TF / A7130 National Physical and Social Post Limited 130,000.00 0.00 2022-12-20 2023-02-14 2023-08-13 s perforées, motopompe et a tions nvelope ementation Investments ccessoires, Pulvérisateur élec trique rechargeable etc..) TG-WACA TOGO-313451-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / ACHAT DE TRACTEUR P IDA / D2860 National Physical and Social Post Limited 40,000.00 0.00 2023-02-20 2023-04-17 2023-10-14 tions nvelope ementation OUR LA COMMUNE LAC 1 Investments TG-WACA TOGO-308000-GO- Component 2: Strengthening Request for Quota Single Stage - One E Under Imple TF / A7130 Post Limited 150,000.00 0.00 2023-02-20 2023-02-22 2023-04-17 2023-10-14 RFQ / Acquisition d'un camio the Policy and Institutional F tions nvelope mentation n fourgon ramework TG-WACA TOGO-346896-GO- Component 3: Strengthening RFB / Acquisition des équipe Single Stage - One E Under Imple IDA / D2860 National Physical and Social Post Request for Bids Open - National 566,273.00 0.00 2023-04-24 2023-05-16 2023-04-29 2023-05-29 2023-06-28 2023-08-02 2024-02-28 ments de transformation en nvelope mentation Investments sept (07) lots pour les 7 AGR TG-WACA TOGO-355426-GO- Component 3: Strengthening RFQ / acquisition de plants p Request for Quota Single Stage - One E Pending Impl TF / A7130 National Physical and Social Post Limited 140,000.00 0.00 2023-05-20 2023-07-15 2024-01-11 our le reboisement par ODEF tions nvelope ementation Investments et les mairies des préfecture s des Lacs et Vo 97 / Réalisation des films do Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Open - National 27,909.00 0.00 Canceled 2020-05-27 2020-07-22 2021-01-18 cumentaires dination tions nvelope 93 / Fournitures de bureau p Component 4: National Coor Request for Quota Single Stage - One E our l'UGP ( Accord cadre attri TF / A7130 Post Open 20,000.00 0.00 Canceled 2020-04-20 2020-06-15 2020-12-12 dination tions nvelope bution par article) TG-WACA TOGO-223544-GO- Component 2: Strengthening RFQ / Edition et vulgarisation Request for Quota Single Stage - One E IDA / D2860 the Policy and Institutional F Post Limited 5,544.00 0.00 Canceled 2021-05-31 2021-07-26 2021-08-25 du guide d'intégration de l'éc tions nvelope ramework onomie bleu dans les docum ents de planification TG-WACA TOGO-234936-GO- Component 2: Strengthening Request for Quota Single Stage - One E TF / A7130 Post Limited 5,000.00 0.00 Canceled 2021-08-04 2021-09-29 2021-11-28 RFQ / achat de deux (02) dro the Policy and Institutional F tions nvelope nes ramework TG-WACA TOGO-365276-GO- Component 3: Strengthening RFQ / Acquisition de plants p Request for Quota Single Stage - One E Pending Impl TF / A7130 National Physical and Social Post Limited 50,000.00 0.00 2023-08-05 2023-09-30 2024-03-28 our l'ODEF (Tectona grandis, tions nvelope ementation Investments Gmelina arborea, Khaya sene galensis etc..) TG-WACA TOGO-365279-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / acquisition de plants p TF / A7130 National Physical and Social Post Limited 6,000.00 0.00 2023-08-05 2023-09-30 2024-03-28 tions nvelope ementation our la commune des Lacs 1 Investments TG-WACA TOGO-365283-GO- RFQ / achat de plants pour la Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl commune Lacs 2 (Khaya sen TF / A7130 National Physical and Social Post Limited 5,900.00 0.00 2023-08-05 2023-09-30 2024-03-28 tions nvelope ementation egalensis, Sena ciamea Gmel Investments ina arborea et autres essenc es naturelles) TG-WACA TOGO-365292-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de plants p TF / A7130 National Physical and Social Post Limited 6,200.00 0.00 2023-08-13 2023-10-08 2024-04-05 tions nvelope ementation our la mairie Lacs 3 Investments TG-WACA TOGO-365294-GO- RFQ / achat de plants pour la Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl mairie Vo 1 (Khaya senegale TF / A7130 National Physical and Social Post Limited 18,000.00 0.00 2023-08-09 2023-10-04 2024-04-01 tions nvelope ementation nsis, Sena ciamea Gmelina ar Investments borea et autres essences nat urelles) TG-WACA TOGO-365296-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / acquisition de plants p TF / A7130 National Physical and Social Post Limited 17,000.00 0.00 2023-08-13 2023-10-08 2024-04-05 tions nvelope ementation our la mairie Vo 3 Investments TG-WACA TOGO-365299-GO- Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl RFQ / achat de plants pour la TF / A7130 National Physical and Social Post Limited 6,000.00 0.00 2023-08-13 2023-10-08 2024-04-05 tions nvelope ementation mairie Vo 2 Investments Page 4 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 36 / Edition du plan d'investi ssement et du document d'a Component 4: National Coor Request for Quota Single Stage - One E IDA / V1150 Post Limited 18,000.00 20,365.63 Signed 2018-02-21 2018-02-16 2018-04-18 2018-08-01 2018-10-15 nalyse du cadre juridique inst dination tions nvelope itutionnel de gestion intégrée du littoral 38 / Paramétrage du logiciel Component 4: National Coor de gestion financière du PGIC IDA / V1150 Post Direct Selection Direct 13,000.00 12,538.87 Signed 2018-07-05 2018-11-14 2018-07-10 2018-11-14 2018-08-14 2019-08-29 2019-02-10 dination T pour le projet WACA 52 / Recrutement d'un servic Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Limited 4,000.00 0.00 Signed 2019-06-29 2020-06-08 2019-08-24 2020-02-20 e d'entretien dination tions nvelope 77 / Police d'assurance pour Component 4: National Coor Request for Quota Single Stage - One E le personnel recruté par le pr IDA / D2860 Post Limited 20,000.00 12,512.77 Signed 2019-11-25 2019-09-10 2020-01-20 2020-04-08 2020-07-18 dination tions nvelope ojet WACA ResIP 17 BIS / Mise en place d'un s ystème informatisé de suivi d Component 4: National Coor Single Stage - One E IDA / D2860 Post Request for Bids Open - National 40,000.00 0.00 Canceled 2019-02-20 2019-05-08 2019-02-25 2019-04-08 2019-05-08 2019-06-12 2019-12-09 u projet (acquisition, installat dination nvelope ion et formation des utilisate urs) 119 / Service de gardiennag Component 4: National Coor Request for Quota Single Stage - One E IDA / D2860 Post Limited 8,182.00 8,602.22 Signed 2020-08-17 2020-09-09 2020-10-12 2021-04-24 2021-10-09 e des bureaux de l'UGP dination tions nvelope TG-WACA TOGO-364035-NC- Component 4: National Coor Request for Quota Single Stage - One E Pending Impl RFQ / Entretien et maintenan IDA / D2860 Post Limited 24,000.00 0.00 2023-09-04 2023-10-30 2023-12-05 dination tions nvelope ementation ce de climatiseur CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 14 / Etude de faisabilité tech Component 3: Strengthening Quality And Cost- Open - Internationa nique de la protection côtière IDA / V1150 National Physical and Social Prior 2,000,000.00 0.00 Canceled 2018-02-06 2018-02-27 2018-04-12 2018-05-10 2018-06-09 2018-07-14 2018-08-18 2019-08-18 Based Selection l du segment transfrontalier B Investments énin-Togo 15 / Etude d'Impact Environ Component 2: Strengthening nemental et Social (EIES) de l Quality And Cost- Open - Internationa IDA / V1150 the Policy and Institutional F Post 320,000.00 0.00 Canceled 2018-02-08 2018-03-01 2018-04-14 2018-05-12 2018-06-11 2018-07-16 2018-08-20 2019-08-20 a protection côtière du segm Based Selection l ramework ent transfrontalier Bénin-Tog o 19 / Etude d'Impact Environ nemental et Social (EIES) pou Component 2: Strengthening Consultant Qualifi r le curage mécanique du ch IDA / V1150 the Policy and Institutional F Post Open - National 200,000.00 0.00 Canceled 2018-09-25 2018-10-16 2018-11-29 2018-12-29 2019-02-02 2019-08-01 cation Selection enal Gbaga et de restauratio ramework n de ces écosystèmes associ és 46 / Evaluation du coût de la Component 2: Strengthening dégradation historique de la Consultant Qualifi IDA / D2860 the Policy and Institutional F Post Open - National 130,000.00 149,746.25 Signed 2019-01-17 2019-05-22 2019-02-07 2019-07-08 2019-03-23 2019-11-28 2019-04-22 2020-12-22 2019-05-27 2021-04-24 2019-11-23 côte y compris la vulnérabilit cation Selection ramework é des communautés côtières 42BIS / Etude de faisabilité t echnique de l'installation d'u Component 3: Strengthening Quality And Cost- Open - Internationa ne vanne au niveau du pont IDA / D2860 National Physical and Social Prior 650,000.00 0.00 Canceled 2019-03-05 2019-03-26 2019-05-09 2019-06-06 2019-07-06 2019-08-10 2019-09-14 2020-09-13 Based Selection l de la lagune d'Aného et l'étu Investments de hydrodynamique du systè me fluvio-lagunaire 43 / Etude approfondie de fa Component 3: Strengthening Quality And Cost- Open - Internationa isabilité du traitement des bo IDA / 62130 National Physical and Social Prior 600,000.00 0.00 Canceled 2019-03-12 2019-04-02 2019-05-16 2019-06-13 2019-07-13 2019-08-17 2019-09-21 2020-09-20 Based Selection l ues de phosphates rejetées e Investments n mer 44 / Elaboration du plan spat Component 4: National Coor Quality And Cost- Open - Internationa IDA / D2860 Post 250,000.00 0.00 Canceled 2019-02-11 2019-03-04 2019-04-17 2019-05-15 2019-06-14 2019-07-19 2019-08-23 2020-08-22 ial marin et côtier dination Based Selection l 45 / Evaluation du capital na Component 2: Strengthening Quality And Cost- Open - Internationa IDA / D2860 Post 300,000.00 0.00 Canceled 2019-02-12 2019-03-05 2019-04-18 2019-05-16 2019-06-15 2019-07-20 2019-08-24 2020-08-23 turel de la zone côtière the Policy and Institutional F Based Selection l ramework 49 / Audits financiers et com Component 4: National Coor Least Cost Selecti ptables du projet - exercices IDA / D2860 Post Open - National 45,000.00 24,687.83 Signed 2019-02-11 2019-04-18 2019-03-04 2019-07-08 2019-04-17 2019-10-10 2019-05-15 2020-02-06 2019-06-14 2020-03-11 2019-07-19 2020-05-19 2019-08-23 2020-06-30 2020-02-19 dination on 2017, 2018 et 2019 3 BIS / Etudes de faisabilité t echniques de dragage et de Component 3: Strengthening stabilisation des berges de la Quality And Cost- Open - Internationa IDA / D2860 National Physical and Social Post 250,000.00 1,061,119.41 Signed 2018-10-04 2018-05-18 2018-10-25 2018-12-08 2019-08-28 2019-01-05 2019-10-10 2019-02-04 2019-10-25 2019-03-11 2019-12-13 2019-04-15 2020-08-27 2020-04-14 lagune et du lac Togo, et pou Based Selection l Investments r la Construction et le curage de caniveau, de bassin d'ora ge, de retenue d'eau 48 / Etude d'Impact Environ nemental et Social (EIES) pou Component 3: Strengthening Consultant Qualifi r le curage mécanique du ch TF / A7130 National Physical and Social Post Open - National 100,000.00 0.00 Canceled 2018-12-28 2019-01-03 2019-01-18 2019-03-03 2019-04-02 2019-05-07 2019-11-03 cation Selection enal Gbaga et de restauratio Investments n de ces écosystèmes associ és 47B / Etude de faisabilité tec Component 3: Strengthening hnique pour le curage mécan Quality And Cost- Open - Internationa TF / A7130 National Physical and Social Prior 600,000.00 554,086.35 Signed 2019-04-26 2019-04-18 2019-05-17 2019-07-23 2019-06-30 2020-10-17 2019-07-28 2020-10-26 2019-08-27 2021-01-14 2019-10-01 2021-04-13 2019-11-05 2021-06-19 2020-11-04 ique du chenal de Gbaga et d Based Selection l Investments e la restauration de ces écos ystèmes associés 47 / Etude de faisabilité tech Component 3: Strengthening nique du curage mécanique Quality And Cost- Open - Internationa TF / A7130 National Physical and Social Post 300,000.00 0.00 Canceled 2018-12-28 2019-01-03 2019-01-18 2019-03-03 2019-03-31 2019-04-30 2019-06-04 2019-07-09 2020-07-08 du chenal Gbaga et de resta Based Selection l Investments uration de ces écosystèmes associés 48B / Etude d'Impact Enviro nnemental et Social (EIES) po Component 3: Strengthening Consultant Qualifi Open - Internationa Under Implement ur le curage mécanique du c TF / A7130 National Physical and Social Post 200,000.00 0.00 2019-04-26 2019-04-17 2019-05-17 2019-06-30 2019-08-13 2019-07-30 2021-02-26 2019-09-03 2020-03-01 cation Selection l ation henal Gbaga et de restaurati Investments on de ces écosystèmes assoc iés Page 5 40 / Surveillance et contrôle Component 4: National Coor Consultant Qualifi des travaux d'aménagement IDA / V1150 Post Open - National 18,000.00 0.00 Canceled 2018-07-11 2018-08-01 2018-09-14 2018-10-14 2018-11-18 2019-05-17 dination cation Selection des bureaux du Projet WACA 62 / Élaboration du plan d'a Component 3: Strengthening ménagement participatif et d Consultant Qualifi Open - Internationa TF / A7130 National Physical and Social Post 140,000.00 154,345.80 Signed 2019-08-28 2020-01-07 2019-09-18 2020-06-26 2019-11-01 2020-10-26 2019-12-01 2021-02-09 2020-01-05 2021-04-24 2020-07-03 es outils de gestion de la forê cation Selection l Investments t communautaire d'Avévé 63 / Elaboration du plan d'a Component 3: Strengthening ménagement participatif et d Consultant Qualifi Open - Internationa TF / A7130 National Physical and Social Post 150,000.00 154,345.80 Signed 2019-08-28 2020-01-07 2019-09-18 2020-06-26 2019-11-01 2020-10-15 2019-12-01 2021-02-09 2020-01-05 2021-04-24 2020-07-03 es outils de gestion de la forê cation Selection l Investments t communautaire de Kodjo-G ati 60 / Recrutement d'une stru cture ( centre de formation) Component 3: Strengthening pour la formation et l'accomp Consultant Qualifi TF / A7130 National Physical and Social Post Open - National 55,000.00 244,722.82 Signed 2019-08-28 2019-08-21 2019-09-18 2019-11-01 2020-05-05 2019-12-01 2020-06-10 2020-01-05 2021-06-04 2020-07-03 agnement des acteurs comm cation Selection Investments unautaires sur les bonnes pr atiques en gestion durable d es terres. 82 / Etude sur la situation de s plantes envahissantes, des Component 3: Strengthening Consultant Qualifi Open - Internationa modèles de gestion et de val TF / A7130 National Physical and Social Post 80,000.00 0.00 Signed 2019-12-30 2020-03-30 2020-01-20 2022-04-28 2020-03-04 2022-10-20 2020-04-03 2022-11-28 2020-05-08 2020-11-04 cation Selection l orisation dans la sous-région Investments et les applications possibles dans la zone du projet 40 C / Surveillance et contrôl e des travaux d'aménageme nt du R + 1 des bureaux de l' Component 4: National Coor Consultant Qualifi UGP, Construction du mur de IDA / D2860 Post Open - National 20,000.00 0.00 Canceled 2019-08-28 2019-09-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 dination cation Selection séparation, d'un parking pour 10 voitures, d'un poste d'ach at et d'un aménagement de cour. 105 / Recrutement d'un cabi net pour l'actualisation de l'é tude de faisabilité technique Component 3: Strengthening du projet d'assainissement d Quality And Cost- Open - Internationa IDA / D2860 National Physical and Social Post 120,000.00 111,390.00 Signed 2020-06-30 2020-09-16 2020-07-21 2021-01-20 2020-09-03 2021-04-15 2020-10-01 2021-07-02 2020-10-31 2021-07-28 2020-12-05 2021-08-19 2021-01-09 2022-02-01 2022-01-09 es eaux usées à la plage de L Based Selection l Investments omé, réhabilitation du réseau embryonnaire d'assainissem ent collectif des eaux usées de la ville de Lomé au Togo 121 / Recrutement d'un cabi net pour le contrôle et surveil Component 3: Strengthening lance des travaux d’urgence Consultant Qualifi IDA / D2860 National Physical and Social Post Limited 910.00 90,871.35 Signed 2020-08-07 2020-08-09 2020-08-21 2020-08-25 2020-09-20 2020-11-10 2020-10-25 2021-02-02 2021-02-24 de protection contre l’érosion cation Selection Investments côtière des habitations vulné rables sur le littoral togolais allant de Gbodjomé à Agbodr afo. TG-WACA TOGO-223531-CS- CQS / Etude de faisabilité te Component 2: Strengthening Consultant Qualifi chnique pour la création et l' IDA / D2860 the Policy and Institutional F Post Open - National 92,000.00 0.00 Canceled 2021-06-30 2021-07-21 2021-09-03 2021-10-03 2021-11-07 2022-05-06 cation Selection opérationnalisation de l'obse ramework rvatoire national sur le littora l 78 / Assistance technique et Component 2: Strengthening Consultant Qualifi TF / A7130 Post Open - National 220,982.00 0.00 Canceled 2020-01-14 2020-01-15 2020-02-04 2020-03-19 2020-04-18 2020-05-23 2020-11-19 contrôle des activités commu the Policy and Institutional F cation Selection nautaires ramework 113 / Etude d'avant projet d étaillé (APD) pour la construc Component 4: National Coor Consultant Qualifi tion de la nouvelle direction r IDA / D2860 Post Open - National 40,000.00 0.00 Canceled 2020-07-27 2020-08-17 2020-09-30 2020-10-30 2020-12-04 2021-06-02 dination cation Selection égionale des forestiers de la réserve de faune de Togodo Nord à Atakpamé TG-WACA TOGO-276324-CS- Component 4: National Coor Least Cost Selecti Pending Impleme LCS / audit externe 2023 et IDA / D2860 Post Open - National 20,000.00 0.00 2022-08-16 2022-09-06 2022-10-20 2022-11-17 2022-12-17 2023-01-21 2023-02-25 2023-03-27 dination on ntation clôture du projet TG-WACA TOGO-276160-CS- Component 3: Strengthening QBS / Informatisation du syst Consultant Qualifi Open - Internationa Pending Impleme TF / A7130 National Physical and Social Post 100,000.00 0.00 2022-09-30 2022-10-21 2022-12-04 2023-01-03 2023-02-07 2023-08-06 ème de suivi-évaluation du M cation Selection l ntation Investments ERF: Extension du logiciel Ru che au ministère TG-WACA TOGO-276156-CS- Component 2: Strengthening QBS / Recrutement d'un cabi Consultant Qualifi Open - Internationa TF / A7130 the Policy and Institutional F Post 100,000.00 0.00 Signed 2022-07-29 2022-05-11 2022-08-19 2022-07-27 2022-10-02 2022-09-15 2022-11-01 2022-11-02 2022-12-06 2023-06-04 net pour la formation des ag cation Selection l ramework ents du MEMPPC sur la prote ction côtière TG-WACA TOGO-224375-CS- Component 3: Strengthening CDS / Etude de faisabilité tec Quality And Cost- Open - Internationa Under Implement IDA / 62130 National Physical and Social Post 380,000.00 0.00 2022-09-28 2023-03-14 2022-10-19 2022-12-02 2022-06-06 2022-12-30 2022-06-17 2023-01-29 2022-06-02 2023-03-05 2022-06-20 2023-04-09 2024-04-08 hnique de la mise en place d' Based Selection l ation Investments un bypass au port autonome de Lomé TG-WACA TOGO-276177-CS- Component 3: Strengthening QBS / Mise en valeur de quat Quality And Cost- Open - Internationa Under Implement IDA / 62130 National Physical and Social Post 363,637.00 0.00 2022-09-30 2023-05-01 2022-10-21 2023-05-04 2022-12-04 2023-01-01 2023-01-31 2023-03-07 2023-04-11 2024-04-10 re zones prioritaires du Sché Based Selection l ation Investments ma d’aménagement du Littor al (SDAL) TG-WACA TOGO-222420-CS- CQS / Elaboration de la carte Component 2: Strengthening Consultant Qualifi de vulnérabilité de la côte to TF / A7130 the Policy and Institutional F Post Open - National 54,545.00 0.00 Canceled 2022-08-24 2022-09-14 2022-10-28 2022-11-27 2023-01-01 2023-04-01 cation Selection golaise face aux menaces de ramework pollution par les hydrocarbur es (ABC) TG-WACA TOGO-308002-CS- CQS / Elaboration de la carte Component 2: Strengthening Consultant Qualifi Open - Internationa Under Implement de vulnérabilité de la côte to TF / A7130 the Policy and Institutional F Post 100,000.00 0.00 2022-10-20 2023-01-24 2022-11-10 2023-03-24 2022-12-24 2023-01-23 2023-02-27 2023-08-26 cation Selection l ation golaise face aux menaces de ramework pollution par les hydrocarbur es (ABC) TG-WACA TOGO-313433-CS- Component 3: Strengthening CQS / CONTRÔLE DES TRAVA Consultant Qualifi Open - Internationa Under Implement IDA / 62130 National Physical and Social Post 990,000.00 0.00 2022-10-20 2022-09-29 2022-11-10 2022-12-13 2022-12-24 2023-01-23 2023-02-27 2023-12-24 UX DE CURAGE MÉCANIQUE cation Selection l ation Investments DU CHENAL DE GBAGA TG-WACA TOGO-339841-CS- Component 2: Strengthening Quality And Cost- CQS / Étude architecturale de IDA / D2860 the Policy and Institutional F Post Open - National 120,000.00 0.00 Under Review 2023-04-24 2023-05-15 2023-06-28 2023-07-26 2023-08-25 2023-09-29 2023-11-03 2024-11-02 Based Selection la construction du siège de l' ramework ANGE Page 6 TG-WACA TOGO-276163-CS- QBS / Appui à la mise en œu Component 3: Strengthening vre du plan d'investissement Consultant Qualifi Open - Internationa IDA / D2860 National Physical and Social Post 100,000.00 0.00 Canceled 2022-09-30 2022-10-21 2022-12-04 2023-01-03 2023-02-07 2023-08-06 des CDN 2030 du Togo pour l cation Selection l Investments 'élaboration d'une stratégie d e développement sobre en c arbone et résilience au CC TG-WACA TOGO-223546-CS- Component 2: Strengthening Consultant Qualifi CQS / Elaboration du plan sp IDA / D2860 the Policy and Institutional F Post Open - National 32,000.00 0.00 Canceled 2022-09-26 2022-10-17 2022-11-30 2022-12-30 2023-02-03 2023-06-03 cation Selection atial marin et côtier ramework INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1 / Elaboration du Cadre de Component 2: Strengthening Individual Consult Gestion Environnementale et IDA / V1150 the Policy and Institutional F Post Limited 27,500.00 23,893.15 Signed 2017-07-18 2017-06-22 2017-07-23 2017-09-07 2018-01-29 2017-09-28 2018-03-05 2017-11-29 2018-07-17 ant Selection Sociale (CGES) ramework 2 / Elaboration du Cadre de Component 2: Strengthening Individual Consult IDA / V1150 Post Limited 24,000.00 20,223.92 Signed 2017-06-22 2017-06-22 2017-08-24 2017-09-07 2017-09-29 2017-09-29 2017-11-29 2017-11-29 2018-01-12 Politique de Réinstallation (C the Policy and Institutional F ant Selection PR) ramework 4 / Etude d'impact environne Component 2: Strengthening mental et social des dragage Individual Consult IDA / V1150 the Policy and Institutional F Post Limited 18,000.00 0.00 Signed 2017-11-12 2017-11-12 2018-01-27 2018-01-22 2018-02-17 2018-05-31 2018-03-24 2018-04-24 s et de la construction des ou ant Selection ramework vrages de lutte contre les ino ndations 13 / Elaboration de la straté Component 4: National Coor IDA / V1150 Post Direct Selection Direct 14,000.00 13,130.33 Signed 2017-12-12 2017-12-12 2017-12-22 2017-12-22 2018-02-09 2018-08-29 2018-03-29 gie de passation des marché dination s (PPSD) 6 / Recrutement d'un spécial Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 iste en passation des marché dination ant Selection s 8 / Recrutement d'un spécial Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 iste en suivi-évaluation dination ant Selection 9 / Recrutement d'un spécial Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 iste en sauvegarde sociale dination ant Selection 10 / Recrutement d'un spéci Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 aliste en communication dination ant Selection 9 BIS / Recrutement d'un sp Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Signed 2018-04-26 2018-05-18 2018-06-14 2019-01-25 2018-07-05 2019-05-14 2018-08-09 2019-02-05 écialiste en sauvegarde socia dination ant Selection le 10 BIS / Recrutement d'un s Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Signed 2018-06-03 2018-02-18 2018-07-22 2019-04-11 2018-08-12 2019-05-20 2018-09-16 2019-03-15 pécialiste en communication dination ant Selection 7 / Recrutement d'un ingéni Component 4: National Coor Individual Consult IDA / V1150 Post Open 28,000.00 0.00 Signed 2018-05-17 2018-08-13 2018-07-05 2018-07-26 2019-04-15 2018-08-30 2019-02-26 eur génie civil (génie côtier) dination ant Selection 27 / Recrutement d'un audit Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Signed 2018-05-24 2019-02-03 2018-07-12 2019-06-25 2018-08-02 2022-02-22 2018-09-06 2019-03-05 eur interne du projet dination ant Selection 11 / Recrutement de secréta Component 4: National Coor Individual Consult IDA / V1150 Post Open 12,000.00 0.00 Canceled 2018-02-20 2018-04-10 2018-05-01 2018-06-05 2018-12-02 ire caissière dination ant Selection 7 / Recrutement d'un ingéni Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-02-06 2018-03-27 2018-04-17 2018-05-22 2018-11-18 eur génie civil (génie côtier) dination ant Selection 3 / Réalisation d'études tech Component 3: Strengthening Individual Consult niques d'ouvrages de lutte co IDA / V1150 National Physical and Social Post Limited 53,000.00 0.00 Canceled 2017-11-08 2017-11-13 2018-03-26 2018-04-30 2018-10-27 ant Selection ntre les inondations Investments 12 / Recrutement d'un Assist Component 4: National Coor Individual Consult IDA / V1150 Post Limited 30,000.00 0.00 Canceled 2017-11-08 2017-11-13 2017-12-04 2018-01-08 2018-07-07 ant technique au projet dination ant Selection 25 / Recrutement d'un assist Component 4: National Coor Individual Consult IDA / V1150 Post Open 10,000.00 0.00 Canceled 2018-04-26 2018-06-14 2018-07-05 2018-08-09 2019-02-05 ant en passation des marché dination ant Selection s 24 BIS / Recrutement d'un s Component 4: National Coor Individual Consult IDA / D2860 Post Open 24,000.00 0.00 Signed 2018-08-29 2018-09-18 2018-11-02 2018-11-23 2019-02-25 2018-12-28 2019-06-26 pécialiste en gestion financiè dination ant Selection re 24 / Recrutement d'un assist Component 4: National Coor Individual Consult IDA / V1150 Post Open 10,000.00 0.00 Canceled 2018-08-29 2018-10-31 2018-11-21 2018-12-26 2019-06-24 ant au spécialiste en gestion dination ant Selection financière 6 BIS / Recrutement d'un sp Component 4: National Coor Individual Consult IDA / D2860 Post Open 24,000.00 37,051.31 Signed 2018-08-27 2018-10-31 2019-02-15 2018-11-21 2019-08-19 2018-12-26 2019-08-09 2019-06-24 écialiste en passation des ma dination ant Selection rchés 69 / Actualisation des manu Component 2: Strengthening Individual Consult IDA / D2860 Post Open 13,000.00 13,023.07 Signed 2019-06-17 2019-06-07 2019-08-05 2020-11-17 2019-08-26 2020-11-23 2019-09-30 2021-04-24 2020-03-28 els de procédure de l'ANGE the Policy and Institutional F ant Selection ramework 67 / Élaboration du plan de d éveloppement des Ressource Component 2: Strengthening Individual Consult s Humaines du Ministère de l' TF / A7130 the Policy and Institutional F Post Open 15,000.00 0.00 Canceled 2019-06-19 2019-06-17 2019-08-07 2019-08-28 2019-10-02 2020-03-30 ant Selection Environnement, du Développ ramework ement Durable et de la Prote ction de la Nature 64 / Appui à l'analyse institu tionnelle du Ministère de l'En vironnement, du Développe Component 2: Strengthening Individual Consult ment Durable et de la Protec TF / A7130 the Policy and Institutional F Post Open 15,000.00 16,668.25 Signed 2019-06-19 2019-06-07 2019-08-07 2020-11-17 2019-08-28 2020-11-23 2019-10-02 2021-04-24 2020-03-30 ant Selection tion de la Nature relative à la ramework mise en œuvre des conventio ns internationales signées pa r le Togo Component 3: Strengthening 68 / Élaboration du cadre fo Individual Consult TF / A7130 National Physical and Social Post Open 24,000.00 18,403.19 Signed 2019-06-17 2019-06-07 2019-08-05 2019-11-04 2019-08-26 2019-02-07 2019-09-30 2020-08-18 2020-03-28 nctionnel (procédural) ant Selection Investments Page 7 40B / Surveillance contrôle d es Travaux d'aménagement du R+1 des bureaux pour l'U GP, Construction du mur de s Component 4: National Coor Individual Consult IDA / V1150 Post Open 9,000.00 0.00 Canceled 2019-06-20 2019-08-08 2019-08-29 2019-10-03 2020-03-31 éparation, d'un parking pour dination ant Selection 10 voitures, un poste d'héber gement (des compteurs et d u groupe électrogène) et am énagement de la cour 61 / Élaboration des textes d Component 2: Strengthening Individual Consult IDA / D2860 Post Open 20,000.00 22,801.19 Signed 2019-06-20 2019-06-07 2019-08-08 2020-12-18 2019-08-29 2021-01-04 2019-10-03 2021-04-24 2020-03-31 'application de la loi sur le litt the Policy and Institutional F ant Selection oral ramework 53 / Recrutement d'un (01) c Component 4: National Coor Individual Consult IDA / D2860 Post Open 3,500.00 4,603.46 Signed 2019-06-26 2019-08-21 2019-08-14 2020-05-13 2019-09-04 2020-09-03 2019-10-09 2020-09-22 2020-04-06 oursier dination ant Selection 55 / Recrutement de deux (2 Component 4: National Coor Individual Consult IDA / D2860 Post Open 9,000.00 20,845.12 Signed 2019-07-12 2019-08-21 2019-08-30 2020-06-02 2019-09-20 2020-07-15 2019-10-25 2020-09-22 2020-04-22 ) chauffeurs de permis catég dination ant Selection orie B 54 / Recrutement d'un (01) c Component 4: National Coor Individual Consult IDA / D2860 Post Open 5,500.00 0.00 Canceled 2019-08-22 2019-08-21 2019-10-10 2019-10-31 2019-12-05 2020-06-02 hauffeur de permis catégorie dination ant Selection C 75 / Recrutement d'un Coord Component 4: National Coor Individual Consult IDA / D2860 Post Open 33,000.00 40,385.61 Signed 2019-08-19 2019-08-20 2019-10-07 2020-03-04 2019-10-28 2020-03-11 2019-12-02 2020-05-27 2020-05-30 onnateur du projet WACA Re dination ant Selection sIP 75BIS / Recrutement de coor Component 4: National Coor Individual Consult IDA / D2860 Post Open 33,000.00 40,486.37 Signed 2019-11-20 2019-11-08 2019-12-23 2020-03-13 2020-01-06 2020-03-25 2020-02-10 2020-05-27 2020-08-08 donnateur pour le projet WA dination ant Selection CA ResIP 91 / Recrutement d'un secré Component 4: National Coor Individual Consult taire administratif pour l'UGP IDA / D2860 Post Open 12,000.00 694.31 Signed 2020-04-09 2020-07-30 2020-05-28 2021-03-15 2020-06-18 2021-05-10 2020-07-23 2021-06-16 2021-01-19 dination ant Selection WACAResIP 89 / Recrutement de consult ant individuel environnement Component 2: Strengthening aliste pour le contrôles des tr Individual Consult TF / A7130 the Policy and Institutional F Post Open 11,136.00 0.00 Canceled 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 avaux d'aménagement de la ant Selection ramework cour du MEDDPN et des bure aux de l'UGP (RDC et R+1) 20 / Recrutement d'un spéci Component 4: National Coor Individual Consult IDA / V1150 Post Open 24,000.00 0.00 Canceled 2018-06-03 2018-07-22 2019-06-25 2018-08-12 2018-09-16 2019-03-15 aliste en développement insti dination ant Selection tutionnel 111 / Recrutement d'un exp Component 4: National Coor Individual Consult ert en passation de marché p IDA / D2860 Post Open 28,500.00 34,987.56 Signed 2020-05-29 2020-05-25 2020-07-17 2020-07-23 2020-08-07 2020-10-02 2020-09-11 2020-11-21 2021-09-10 dination ant Selection our le projet WACA ResIP 115 / Recrutement d'un audi Component 4: National Coor Individual Consult IDA / D2860 Post Open 17,455.00 0.00 Canceled 2020-06-03 2020-07-22 2020-08-12 2020-09-16 2021-11-30 teur interne pour le projet W dination ant Selection ACA ResIP 101 / Recrutement de consul tant individuel génie électro Component 2: Strengthening mécanique pour le contrôle d Individual Consult IDA / D2860 the Policy and Institutional F Post Open 6,200.00 15,039.77 Signed 2020-07-10 2020-06-16 2020-08-28 2020-09-23 2020-09-18 2021-03-24 2020-10-23 2021-04-24 2021-06-23 es travaux d'aménagement d ant Selection ramework u cadre de travail de l'ANGE et du bâtiment R+1 de l'UGP WACA ResiP 90 / Recrutement d’un secré taire pour la passation de ma Component 4: National Coor Individual Consult IDA / D2860 Post Open 12,000.00 11,146.14 Signed 2020-06-30 2020-08-11 2020-08-18 2021-03-15 2020-09-08 2021-05-10 2020-10-13 2021-06-16 2021-04-11 rché et la gestion financière dination ant Selection du projet WACA ResIP 117 / Recrutement d'un spéc Component 4: National Coor Individual Consult ialiste en communication pou IDA / D2860 Post Open 24,000.00 0.00 Canceled 2020-08-12 2020-09-30 2020-10-21 2020-11-25 2021-11-24 dination ant Selection r le projet WACA ResIP 122 / Mise en place d'un sys Component 2: Strengthening tème automatisé de gestion Individual Consult TF / A7130 the Policy and Institutional F Post Open 15,000.00 30,789.27 Signed 2020-09-30 2021-03-29 2020-11-18 2021-06-28 2020-12-09 2021-08-19 2021-01-13 2021-10-15 2021-04-12 des ressources humaines et f ant Selection ramework inancières du MEDDPN TG-WACA TOGO-204714-CS- Component 3: Strengthening INDV / élaboration d'un plan Individual Consult TF / A7130 National Physical and Social Post Limited 20,000.00 25,170.94 Signed 2021-01-28 2020-12-30 2021-02-12 2021-02-04 2021-03-05 2021-06-17 2021-04-09 2021-08-04 2021-05-09 d'aménagement et de gestio ant Selection Investments n de la forêt classée d'Assév é 99 / Recrutement d'un consu ltant pour la réalisation d'un Component 3: Strengthening Individual Consult plan d'action de réinstallatio IDA / D2860 National Physical and Social Post Open 22,000.00 0.00 Canceled 2020-04-10 2020-05-29 2020-06-19 2020-07-24 2021-01-20 ant Selection n du dragage et stabilisation Investments des berges de la lagune et d u lac Togo 95 / Recrutement d'un consu Component 3: Strengthening ltant pour la realisation d'un Individual Consult TF / A7130 National Physical and Social Post Open 9,091.00 0.00 Canceled 2020-04-09 2020-04-14 2020-05-28 2020-06-18 2020-07-23 2021-01-19 plan d'action de réinstallatio ant Selection Investments n du complexe d'aires protég ées de TOGODO 102 / Recrutement de consul tant individuel environnemen Component 2: Strengthening Individual Consult taliste pour le contrôle des tr IDA / D2860 the Policy and Institutional F Post Open 2,727.00 0.00 Canceled 2020-04-09 2020-05-28 2020-06-18 2020-07-23 2021-01-19 ant Selection avaux d'aménagement du ca ramework dre de travail de l'ANGE 94 / Recrutement de consult ant individuel génie civil pour Component 2: Strengthening Individual Consult le contrôle des travaux IDA / D2860 the Policy and Institutional F Post Open 4,136.00 0.00 Canceled 2020-06-30 2020-08-18 2020-09-08 2020-10-13 2021-05-12 ant Selection d'aménagement du cadre de ramework travail de l'ANGE 86 / Recrutement de consult ant individuel génie civil pour Component 2: Strengthening Individual Consult le contrôles des travaux d'a TF / A7130 the Policy and Institutional F Post Open 18,182.00 0.00 Canceled 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 ant Selection ménagement de la cour du ramework MEDDPN et des bureaux de l' UGP (RDC et R+1) 80 / Etude d'impact environn Component 3: Strengthening Individual Consult ementale et sociale du compl TF / A7130 National Physical and Social Post Open 18,182.00 0.00 Canceled 2020-03-19 2020-03-30 2020-05-07 2020-05-28 2020-07-02 2020-12-29 ant Selection exe d'aires protégées de TO Investments GODO TG-WACA TOGO-222909-CS- Component 4: National Coor Individual Consult INDV / Elaboration du rapport IDA / D2860 Post Open 46,000.00 35,376.04 Signed 2021-04-15 2021-03-29 2021-06-03 2021-08-04 2021-06-24 2021-08-16 2021-07-29 2021-09-30 2021-08-28 dination ant Selection d'évaluation à mi-parcours Page 8 TG-WACA TOGO-222896-CS- Component 4: National Coor Individual Consult INDV / SELECTION D’UN EXPE IDA / D2860 Post Open 38,000.00 123.63 Signed 2021-06-18 2021-06-01 2021-08-06 2021-09-03 2021-08-27 2021-09-03 2021-10-01 2022-03-29 2022-10-01 dination ant Selection RT OCEANOGRAPHE – LITTOR ALISTE TG-WACA TOGO-222891-CS- Component 2: Strengthening Individual Consult INDV / Elaboration du plan sp IDA / D2860 the Policy and Institutional F Post Open 32,000.00 0.00 Canceled 2021-05-20 2021-07-08 2021-07-29 2021-09-02 2021-10-02 ant Selection atial marin et côtier ramework 51 / Appui à la mise en place Component 2: Strengthening Individual Consult IDA / D2860 Post Open 30,000.00 0.00 Canceled 2019-02-04 2019-06-05 2019-03-25 2019-04-15 2019-05-20 2019-11-16 du MRV de la zone côtière the Policy and Institutional F ant Selection ramework TG-WACA TOGO-238696-CS- INDV / Recrutement d'un spé Component 4: National Coor Individual Consult IDA / D2860 Post Open 27,000.00 0.00 Under Review 2021-07-14 2021-06-07 2021-09-01 2021-09-22 2021-10-27 2022-10-22 cialiste en développement de dination ant Selection s sous-projet communautaire et AGR pilote TG-WACA TOGO-240809-CS- INDV / RECRUTEMENT D’UN Component 4: National Coor Individual Consult IDA / D2860 Post Limited 17,455.00 16,663.49 Signed 2021-07-30 2021-06-02 2021-08-04 2021-06-10 2021-08-25 2021-08-12 2021-09-29 2021-10-09 2021-11-04 ASSISTANT A LA MISE EN ŒU dination ant Selection VRE DES ACTIVITES GENERA TRICES DE REVENUS TG-WACA TOGO-240217-CS- INDV / ELABORATION DU PLA Component 3: Strengthening N D’ACTION POUR LA RESTRI Individual Consult TF / A7130 National Physical and Social Post Open 54,545.00 40,571.91 Signed 2021-09-30 2021-08-06 2021-11-18 2022-03-15 2021-12-09 2022-04-22 2022-01-13 2022-06-16 2022-04-13 CTION D’ACCES AUX RESSOU ant Selection Investments RCES DES ECOSYSTEMES FO RESTIERS DE LA ZONE LITTO RALE DU TOGO 87 / Recrutement de consult ant individuel génie electro- Component 2: Strengthening mécanique pour le contrôles Individual Consult TF / A7130 the Policy and Institutional F Post Open 18,182.00 0.00 Canceled 2020-04-15 2020-06-03 2020-06-24 2020-07-29 2021-01-25 des travaux d'aménagement ant Selection ramework de la cour du MEDDPN et de s bureaux de l'UGP (RDC et R +1) TG-WACA TOGO-260449-CS- INDV / recrutement d'un cons Component 3: Strengthening ultant individuel pour l'appui Individual Consult TF / A7130 National Physical and Social Post Open 35,000.00 0.00 Under Review 2022-08-23 2022-03-17 2022-10-11 2022-11-01 2022-12-06 2023-06-04 à l’aménagement des périmè ant Selection Investments tres maraichers de 04 sous p rojets communautaires TG-WACA TOGO-260444-CS- INDV / IDENTIFICATION, ELAB ORATION DES SPECIFICATION Component 3: Strengthening Individual Consult Pending Impleme S TECHNIQUES ET DETERMIN TF / A7130 National Physical and Social Post Open 27,000.00 0.00 2022-07-26 2022-08-31 2022-09-21 2022-10-26 2022-11-25 ant Selection ntation ATION DES COÛTS DES EQUI Investments PEMENTS POUR LE DEVELOP PEMENT DES FILIERES AGRIC OLES TG-WACA TOGO-222416-CS- Component 2: Strengthening Individual Consult Under Implement INDV / Etude pour la mise en IDA / D2860 the Policy and Institutional F Post Open 30,000.00 0.00 2022-08-24 2022-01-26 2022-10-13 2022-11-03 2022-12-08 2023-01-07 ant Selection ation place du MRV de la zone côti ramework ère TG-WACA TOGO-299627-CS- Component 2: Strengthening Individual Consult INDV / RÉALISATION D’UNE IDA / D2860 the Policy and Institutional F Post Open 45,000.00 0.00 Signed 2022-07-27 2022-06-06 2022-09-14 2022-10-12 2022-10-05 2022-12-23 2022-11-09 2023-05-08 ant Selection WEB CARTOGRAPHIE DU PRO ramework JET WACA ResIP TG-WACA TOGO-306645-CS- Component 3: Strengthening CDS / Actualisation de l'étud Direct - Internation IDA / 62130 National Physical and Social Post Direct Selection 110,000.00 0.00 Signed 2022-09-30 2022-09-13 2022-10-10 2022-09-14 2022-12-05 2023-02-03 e de faisabilité technique de l al Investments a protection côtière: tronçon Agbodrafo-Gbodjomé TG-WACA TOGO-306628-CS- CDS / Actualisation de l'étud Component 3: Strengthening Direct - Internation e d'impact environnemental IDA / 62130 National Physical and Social Post Direct Selection 120,000.00 0.00 Signed 2022-09-30 2022-09-28 2022-10-10 2022-09-12 2022-12-05 2023-03-05 al et social du tronçon Agbodraf Investments o-Gbodjomé et élaboration d u PAR TG-WACA TOGO-332877-CS- INDV / ELABORATION DE L’A DDENDUM AU PLAN D’ACTIO Component 3: Strengthening NS DE RÉINSTALLATION (PAR Individual Consult Pending Impleme IDA / 62130 National Physical and Social Post Limited 30,000.00 0.00 2023-01-24 2023-01-29 2023-02-19 2023-03-26 2023-09-22 ) DES PERSONNES AFFECTÉE ant Selection ntation Investments S DANS LE CADRE DES TRAV AUX DE PROTECTION DU SEG MENT DE CÔTE SITUE ENTRE AGBODRAFO ET ANEHO TG-WACA TOGO-223541-CS- INDV / Actualisation du plan Component 2: Strengthening Individual Consult d’action pour le développem IDA / D2860 the Policy and Institutional F Post Open - National 27,273.00 0.00 Signed 2021-05-28 2022-05-09 2021-07-16 2022-12-23 2021-08-06 2022-12-23 2021-09-10 2021-10-10 ant Selection ent et l’adaptation aux chang ramework ements climatiques du littora l togolais TG-WACA TOGO-346060-CS- Component 2: Strengthening INDV / REALISATION DE L'ET Individual Consult Under Implement TF / A7130 the Policy and Institutional F Post Open - National 13,000.00 0.00 2023-05-30 2023-05-02 2023-07-18 2023-08-08 2023-09-12 2024-03-10 UDE DE SATISFACTION DES B ant Selection ation ramework ENEFICAIRES DU PROJET WA CA ResIP TG-WACA TOGO-355432-CS- Component 3: Strengthening INDV / élaboration d'une stra Individual Consult Under Implement IDA / D2860 National Physical and Social Post Open - National 60,000.00 0.00 2023-05-15 2022-10-10 2023-07-03 2023-07-24 2023-08-28 2024-02-24 tégie de développement sobr ant Selection ation Investments e en carbone et résilience au CC TG-WACA TOGO-356038-CS- Component 3: Strengthening INDV / Réalisation de l'EIES si Individual Consult Pending Impleme IDA / 62130 National Physical and Social Post Limited 30,000.00 0.00 2023-05-30 2023-06-04 2023-06-25 2023-07-30 2024-01-26 mplifié des activités du sous ant Selection ntation Investments projet d'AGR pilote noix de C oco 50 / Etude pour la mise en pl ace du système national d'inf Component 2: Strengthening ormations côtières (Définitio Individual Consult IDA / D2860 the Policy and Institutional F Post Open 70,000.00 0.00 Canceled 2019-04-02 2019-06-05 2019-05-21 2019-06-11 2019-07-16 2020-01-12 n et harmonisation des stand ant Selection ramework ards de collecte, traitement e t diffusion de données pour l' observatoire) 106 / Recrutement d'un cons ultant pour la réalisation de l' EIES du projet d'assainissem Component 3: Strengthening Individual Consult ent des eaux usées à la plag IDA / D2860 National Physical and Social Post Open 50,000.00 0.00 Canceled 2020-06-02 2020-11-11 2020-07-21 2020-08-11 2020-09-15 2021-01-15 ant Selection e de Lomé, réhabilitation du r Investments éseau embryonnaire d'assain issement collectif des eaux u sées de la ville de Lomé-Tog o Page 9 TG-WACA TOGO-276167-CS- Component 2: Strengthening INDV / Appui à la révision de Individual Consult IDA / D2860 the Policy and Institutional F Post Open 20,000.00 0.00 Canceled 2022-07-15 2022-09-02 2022-09-23 2022-10-28 2023-04-26 la loi cadre sur l'environnem ant Selection ramework ent et l'élaboration de ses te xtes d'application Page 10 PROCUREMENT PLAN (Textual Part) Project information: Caribbean Region, Caribbean Digital Transformation Program, P171528 Project Implementation agency: Organisation of Eastern Caribbean States (OECS) Date of the Procurement Plan: November 11, 2020. Period covered by this Procurement Plan: The whole project life. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: The implementing agency is not a national state; hence, there is not a national market and there are no national procurement regulations. This notwithstanding, the implementing agency’s procurement procedures (OECS Procurement Manual Revised June 2016) were found acceptable to the Bank and therefore they may be applied for the Procurement of Works, Goods and Non-consulting Services below the mandatory thresholds for international competition (as specified in the Procurement Plan tables in STEP). These procurements should be in accordance with paragraph 5.3, 5.4 and 5.5 of the Procurement Regulations.. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: not applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – not applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: not applicable; Works: not applicable Other Relevant Procurement Information: The Implementing Agency will proceed with advance contracting in the amount of not exceeding SDR1,180,000.- (US$1.600,000.- equivalent) in accordance with the provisions of paragraph 5.1 – 5.2 of the Procurement Regulations. PROCUREMENT Caribbean : Caribbean Digital Transformation Project PLAN General Information Country: Caribbean 2021-03-24 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P171528 GPN Date: 2021-10-11 Project Name: Caribbean Digital Transformation Project Loan / Credit No: IDA / 66820 Department of Public Service Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU_CARDTP_W_RFQ_1 / Sit Digital Government Infrastru Other (with fi e preparation and civil works Request for Quota Single Stage - One E 2022-12-1 IDA / 66820 cture, Platforms and Service Post Open - National eld for expla 0.00 Canceled 2022-07-20 2022-09-14 for foundation of the 40ft con tions nvelope 3 s nation) tainer to establish a Containe rized Datacenter. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU_CARDTP_G_RFB_10 / Te Digital Skills and Technology Open - Internationa Single Stage - One E Pending Impl chnology Adoption and Innov IDA / 66820 Post Request for Bids 0.00 2023-02-02 2023-02-07 2023-03-21 2023-04-20 2023-05-25 2023-11-21 Adoption l nvelope ementation ation (Balance) SLU_CARDTP_G_RFB_8 / Bulk disbursements digitization to support the upgrading of fina Digital Government Infrastru Open - Internationa Single Stage - One E Pending Impl ncial infrastructure (payment IDA / 66820 cture, Platforms and Service Post Request for Bids 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-10-03 l nvelope ementation settlement), operational cons s iderations, policy modificatio ns, and monitoring and evalu ation SLU_CARDTP_G_RFB_3 / Proc urement of digital devices an Digital Government Infrastru d associated digital content t Open - Internationa Single Stage - One E IDA / 66820 cture, Platforms and Service Post Request for Bids 0.00 Canceled 2021-10-25 2021-10-11 2021-10-28 2021-11-27 2021-12-27 2022-01-16 2022-04-16 o access among Grade 6 and l nvelope s Form 1 for remote learning b y students, SALCC & Civil Se rvants SLU_CARDTP_G_RFB_3R / Pr ocurement of digital devices Digital Government Infrastru and associated digital conten Single Stage - One E IDA / 66820 cture, Platforms and Service Post Request for Bids Open - National 1,843,845.32 Signed 2021-10-11 2021-10-16 2021-11-27 2021-11-10 2021-12-27 2022-01-17 2022-03-27 2022-03-31 2022-06-25 t to access among Grade 6 a nvelope s nd Form 1 for remote learnin g by students, SALCC & Civil Servant SLU_CARDTP_G_RFB_5 / Sup Digital Enabling Environmen Open - Internationa Single Stage - One E ply and Installation of Cybers IDA / 66820 Post Request for Bids 0.00 Canceled 2022-06-30 2022-07-05 2022-08-16 2022-09-15 2022-10-20 2023-04-18 t l nvelope ecurity System SLU_CARDTP_G_RFB_1 / Pha se 1: Supply, Refurbishment and Retrofitting of a 40ft con tainer to establish a Containe Digital Government Infrastru Open - Internationa Single Stage - One E Pending Impl rized Datacenter to host a Di IDA / 66820 cture, Platforms and Service Post Request for Bids 0.00 2023-04-15 2023-04-20 2023-06-01 2023-07-01 2023-08-05 2024-02-01 l nvelope ementation giGov Platform, through a Tu s rnkey solution. Phase 2: Supply and Installat ion of Equipment to establish a Containerized Datacenter SLU_CARDTP_G_RFQ_7 / Upg Digital Skills and Technology Request for Quota Open - Internationa Single Stage - One E Under Imple rading of approximately 20 C IDA / 66820 Post 0.00 2022-12-20 2023-02-08 2023-03-29 2023-07-27 Adoption tions l nvelope mentation lassrooms to smart classroo ms SLU_CARDTP_G_RFB_4 / Soft Digital Skills and Technology Open - Internationa Single Stage - One E Pending Impl ware Development Platform t IDA / 66820 Post Request for Bids 0.00 2023-09-15 2023-09-20 2023-10-20 2023-11-19 2023-12-24 2024-06-21 Adoption l nvelope ementation o facilitate Virtual Learning SLU_CARDTP_G_RFB_7 / Sup Digital Government Infrastru Open - Internationa Single Stage - One E Pending Impl ply and Installation of Health IDA / 66820 cture, Platforms and Service Post Request for Bids 0.00 2023-09-19 2023-09-24 2023-11-05 2023-12-05 2024-01-09 2024-07-07 l nvelope ementation Surveillance and Tracking Sy s stem LC-DPS-326309-GO-RFB / Su Digital Skills and Technology Open - Internationa Single Stage - One E Pending Impl pply and Installation of SALC IDA / 66820 Post Request for Bids 0.00 2022-12-16 2022-12-21 2023-02-01 2023-03-03 2023-04-07 2023-10-04 Adoption l nvelope ementation C Innovation Lab SLU_CARDTP_G_RFB_12 / Di Digital Government Infrastru gital infrastructure strengthe Open - Internationa Single Stage - One E IDA / 66820 cture, Platforms and Service Prior Request for Bids 0.00 Canceled 2022-09-02 2022-09-07 2022-10-19 2022-11-18 2022-12-23 2023-06-21 ning and Continuity of Gover l nvelope s nment Operations (Balance) SLU_CARDTP_G_RFB_6 / Cyb Digital Enabling Environmen Open - Internationa Single Stage - One E ersecurity, Data Protection a IDA / 66820 Post Request for Bids 0.00 Canceled 2022-06-30 2022-07-05 2022-08-16 2022-09-15 2022-10-20 2023-04-18 t l nvelope nd Privacy (Balance) LC-DPS-326899-GO-RFB / Pr Digital Government Infrastru Open - Internationa Single Stage - One E Pending Impl ocurement of an e-Land Regi IDA / 66820 cture, Platforms and Service Post Request for Bids 0.00 2023-06-13 2023-06-18 2023-07-30 2023-08-29 2023-10-03 2024-03-31 l nvelope ementation stry System s LC-DPS-336825-GO-DIR / Pur chase of Microsoft Office 201 Digital Government Infrastru 6 for installation on the four IDA / 66820 cture, Platforms and Service Post Direct Selection Direct - National 0.00 Canceled 2023-01-31 2023-05-24 2023-02-05 2023-02-10 2023-03-12 2023-09-08 hundred and Fifty (450) Lapt s ops purchased for Public Ser vants LC-DPS-365681-GO-RFQ / Pu rchase of Microsoft Office 20 Digital Government Infrastru Request for Quota Single Stage - One E Under Imple 21 for installation on the four IDA / 66820 cture, Platforms and Service Post Limited 0.00 2023-04-25 2023-06-20 2023-09-18 tions nvelope mentation hundred and Fifty (450) Lapt s ops purchased for Public Ser vants NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU_CARDTP_G_RFB_9 / Ref Digital Skills and Technology Open - Internationa Single Stage - One E Pending Impl IDA / 66820 Post Request for Bids 0.00 2023-11-17 2023-11-22 2024-01-03 2024-02-02 2024-03-08 2024-09-04 urbishment of co-working sp Adoption l nvelope ementation ace SLU_CARDTP_G_RFQ_6 / Adv ertising Support for the Roll-o Digital Skills and Technology Request for Quota Single Stage - One E IDA / 66820 Post Open - National 0.00 Canceled 2022-03-02 2022-04-27 2022-06-26 ut of the IT Adoption and Pro Adoption tions nvelope ductivity measurement tool f or SME's CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU_CARDTP_CS_RFQ_8 / Se Digital Government Infrastru Consultant Qualifi Open - Internationa Pending Impleme ctor-specific Digital Transfor IDA / 66820 cture, Platforms and Service Post 0.00 2022-12-01 2022-12-22 2023-02-04 2023-03-06 2023-04-10 2023-10-07 cation Selection l ntation mation Strategy s SLU_CARDTP_C_IC_13 / Deliv Digital Skills and Technology Quality And Cost- Open - Internationa Pending Impleme IDA / 66820 Prior 0.00 2023-02-07 2023-02-28 2023-04-13 2023-05-11 2023-06-10 2023-07-15 2023-08-19 2024-08-18 ery of Workforce-Ready Digit Adoption Based Selection l ntation al Skills LC-DPS-326299-CS-QCBS / C onsultancy Services for the E Digital Enabling Environmen Quality And Cost- Open - Internationa Pending Impleme IDA / 66820 Prior 0.00 2023-01-09 2023-01-30 2023-03-15 2023-04-12 2023-05-12 2023-06-16 2023-07-21 2024-07-20 stablishment of a National CE t Based Selection l ntation RT and Supporting Systems LC-DPS-326303-CS-CQS / Co Digital Government Infrastru nsultancy Services for the de Consultant Qualifi Open - Internationa Pending Impleme IDA / 66820 cture, Platforms and Service Post 0.00 2023-01-09 2023-01-30 2023-03-15 2023-04-14 2023-05-19 2023-11-15 velopment of Standards for t cation Selection l ntation s he Government of Saint Luci a LC-DPS-326307-CS-CQS / Im Digital Government Infrastru Consultant Qualifi Open - Internationa Pending Impleme plementation of Open Data P IDA / 66820 cture, Platforms and Service Post 0.00 2023-01-22 2023-02-12 2023-03-28 2023-04-27 2023-06-01 2023-11-28 cation Selection l ntation rogramme s SLU_CARDTP_C_IC_16 / Digit Digital Government Infrastru al Government strategy, stan Quality And Cost- Open - Internationa IDA / 66820 cture, Platforms and Service Post 0.00 Canceled 2022-11-15 2022-12-06 2023-01-19 2023-02-16 2023-03-18 2023-04-22 2023-05-27 2024-05-26 dards, business continuity an Based Selection l s d protocols (Balance) SLU_CARDTP_C_IC_12 / Supp ort for an internship/apprenti ceship program to facilitate j Digital Skills and Technology Quality And Cost- Open - Internationa ob placements of participant IDA / 66820 Post 0.00 Canceled 2022-11-15 2022-12-06 2023-01-19 2023-02-16 2023-03-18 2023-04-22 2023-05-27 2023-11-23 Adoption Based Selection l s of the digital skills program s (under Subcomponent 3.1) including provision of Interns hip Stipends for participants LC-DPS-337263-CS-CQS / Co Digital Government Infrastru nsultancy for undertaking an Consultant Qualifi Under Implement IDA / 66820 cture, Platforms and Service Post Open - National 0.00 2023-02-06 2023-02-01 2023-02-27 2023-04-12 2023-05-12 2023-06-16 2023-09-14 d Inventory of Computer Equi cation Selection ation s pment for the Government o f Saint Lucia LC-DPS-337889-CS-QCBS / C Project Implementation Sup Quality And Cost- Open - Internationa onsultancy Services for Imple IDA / 66820 Post 0.00 Canceled 2023-02-24 2023-03-17 2023-04-30 2023-05-28 2023-06-27 2023-08-01 2023-09-05 2024-09-04 port Based Selection l mentation and Technical Sup port LC-DPS-326302-CS-CQS / Co Digital Government Infrastru nsultancy for the developme Consultant Qualifi Open - Internationa Pending Impleme IDA / 66820 cture, Platforms and Service Post 0.00 2023-03-31 2023-04-21 2023-06-04 2023-07-04 2023-08-08 2024-02-04 nt of the Business Continuity cation Selection l ntation s and Cloud Infrastructure for t he GOSL LC-DPS-345278-CS-CQS / Co nsultancy Services for the De Digital Government Infrastru Consultant Qualifi Open - Internationa Under Implement velopment of the National Br IDA / 66820 cture, Platforms and Service Post 0.00 2023-03-08 2023-06-05 2023-04-10 2023-05-24 2023-07-24 2023-08-18 2024-02-24 cation Selection l ation oadband Policy, Strategy & A s ction Plan for the Government of Saint Lucia LC-DPS-346401-CS-QCBS / C onsultancy Services for the S Digital Government Infrastru upport with the Development Quality And Cost- Open - Internationa Under Implement IDA / 66820 cture, Platforms and Service Post 0.00 2023-06-02 2023-04-17 2023-06-23 2023-05-15 2023-08-06 2023-09-03 2023-10-03 2023-11-07 2023-12-12 2025-06-12 of Technical Requirements a Based Selection l ation s nd Implementation of the e-L and Registry Information Sys tem LC-DPS-362369-CS-QCBS / C onsultancy Services for an Im Project Implementation Sup Quality And Cost- Open - Internationa Under Implement plementation Support & Tech IDA / 66820 Post 0.00 2023-05-26 2023-06-06 2023-06-16 2023-07-30 2023-08-27 2023-09-26 2023-10-31 2023-12-05 2026-06-08 port Based Selection l ation nical Advisory Firm for the Pr oject Implementation Unit INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SLU_CARDTP_G_RFB_11 / Su pport for development of an I Digital Skills and Technology Individual Consult Pending Impleme IDA / 66820 Post Open 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-30 2023-09-26 T adoption and productivity Adoption ant Selection ntation measurement tool for SMEs ( Balance years 2-5) SLU_CARDTP_C_IC-1 / Drafti ng of Legislation for Digital P ayments, Digital Identificatio Digital Enabling Environmen Individual Consult Pending Impleme IDA / 66820 Post Open 0.00 2022-09-23 2022-11-11 2022-12-02 2023-01-06 2023-09-23 n, as well as amending existi t ant Selection ntation ng Finance Act to include Thi rd Party Transactions for Tra de Facilitation LC-DPS-208504-CS-INDV / Pr Project Implementation Sup Individual Consult IDA / 66820 Post Open 0.00 Canceled 2021-03-24 2021-09-27 2021-04-08 2021-04-13 2021-04-23 2026-04-22 ocurement Specialist port ant Selection LC-DPS-208502-CS-INDV / Pr Project Implementation Sup Individual Consult IDA / 66820 Post Open 0.00 Canceled 2021-03-22 2020-08-21 2021-04-06 2021-04-11 2021-04-21 2026-04-20 oject Manager port ant Selection LC-DPS-208501-CS-INDV / Pr Project Implementation Sup Individual Consult IDA / 66820 Post Open 0.00 Canceled 2021-03-22 2020-09-24 2021-05-10 2021-05-31 2021-07-05 2022-01-01 oject Manager port ant Selection Page 2 LC-DPS-208503-CS-INDV / Pr Project Implementation Sup Individual Consult IDA / 66820 Post Open 0.00 Canceled 2021-03-24 2020-08-21 2021-05-12 2021-06-02 2021-07-07 2022-01-03 ocurement Specialist port ant Selection SLU_CARDTP_C_IC_18 / Fina Project Implementation Sup Individual Consult IDA / 66820 Post Open 108,000.00 Signed 2022-03-13 2022-03-21 2022-04-21 2022-06-08 2022-05-12 2022-06-09 2022-05-31 2022-06-25 2025-05-30 nce Officer port ant Selection SLU_CARDTP_C_IC_2 / Techn Digital Government Infrastru ical Consultant to support th Individual Consult IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2022-05-27 2022-06-29 2022-07-20 2022-08-24 2022-09-24 e development of the TOR fo ant Selection s r the Broadband Policy and S trategy SLU_CARDTP_C_IC_4 / Techn ical Consultant to support th Digital Government Infrastru Individual Consult e development of the TOR fo IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2022-07-29 2022-08-31 2022-09-21 2022-10-26 2022-11-26 ant Selection r the Development of a Conti s nuity Plan for the GOSL LC-DPS-326059-CS-INDV / A Project Implementation Sup Individual Consult IDA / 66820 Post Open - National 0.00 Canceled 2022-11-27 2022-12-05 2023-01-05 2023-01-26 2023-03-02 2026-03-01 dministrative Assistant port ant Selection LC-DPS-326060-CS-INDV / Tr Project Implementation Sup Individual Consult Open - Internationa IDA / 66820 Post 0.00 Signed 2022-12-01 2022-12-05 2023-01-09 2023-04-25 2023-01-30 2023-04-26 2023-03-06 2026-03-05 aining Officer port ant Selection l LC-DPS-326062-CS-INDV / E Project Implementation Sup Individual Consult Under Implement IDA / 66820 Post Open - National 0.00 2023-01-03 2023-02-13 2023-02-11 2023-03-04 2023-04-08 2023-10-05 nvironmental and Social Offic port ant Selection ation er LC-DPS-326298-CS-INDV / R Digital Government Infrastru Individual Consult Open - Internationa Pending Impleme eclassification and Job Evalua IDA / 66820 cture, Platforms and Service Post 0.00 2023-01-23 2023-03-03 2023-03-24 2023-04-28 2023-10-25 ant Selection l ntation tion of ICT Positions within G s OSL SLU_CARDTP_C_IC_14 / Deve Digital Enabling Environmen Individual Consult lopment of CERT National CE IDA / 66820 Post Open 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-01-10 t ant Selection RT Roadmap SLU_CARDTP_C_IC_15 / Supp ort for CERT human capacity Digital Enabling Environmen Individual Consult IDA / 66820 Prior Open 0.00 Canceled 2022-04-01 2022-05-20 2022-06-10 2022-07-15 2023-01-11 including support for hiring of t ant Selection CERT manager and analysts; SLU_CARDTP_CS_RFQ_7 / Su Digital Enabling Environmen Individual Consult pport for Development of Nat IDA / 66820 Prior Open 0.00 Canceled 2022-09-16 2022-11-04 2022-11-25 2022-12-30 2023-06-28 t ant Selection ional Cybersecurity Capabilit y LC-DPS-326300-CS-INDV / C Digital Government Infrastru onsultancy Services for the D Individual Consult Open - Internationa IDA / 66820 cture, Platforms and Service Post 0.00 Canceled 2022-12-01 2023-01-19 2023-02-09 2023-03-16 2023-09-12 evelopment of the Broadban ant Selection l s d Policy and Strategy SLU_CARDTP_C_IC_5 / Consu Digital Government Infrastru ltancy Services for the Devel Individual Consult IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2022-03-01 2022-04-19 2022-05-10 2022-06-14 2022-12-26 opment of a Business Contin ant Selection s uity Plan for the GOSL SLU_CARDTP_C_IC_6 / Consu ltancy Services for the Prepar ation of Detailed Specificatio ns for Turnkey Solution for a Digital Government Infrastru Individual Consult containerized Datacenter to IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2021-10-20 2021-12-27 2021-12-08 2021-12-29 2022-02-02 2022-04-23 ant Selection host the DigiGov platform an s d associated data and servic es, and backup centralized G overnment data hosted by th e GITS and Govt Depts LC-DPS-326304-CS-INDV / C onsultancy Services for the P Digital Government Infrastru Individual Consult Open - Internationa Under Implement reparation of Detailed Specifi IDA / 66820 cture, Platforms and Service Post 0.00 2022-12-29 2023-01-24 2023-02-16 2023-03-09 2023-04-13 2023-10-10 ant Selection l ation cations for Turnkey Solution f s or a containerized Datacente r SLU_CARDTP_C_IC_9 / Procur ement of Teacher Training of Digital Skills and Technology Individual Consult digital devices and associate IDA / 66820 Post Open 0.00 Canceled 2022-06-24 2022-08-12 2022-09-02 2022-10-07 2023-02-04 Adoption ant Selection d digital content to access a mong vulnerable groups and remote learning by students LC-DPS-326308-CS-INDV / C Digital Skills and Technology Individual Consult Under Implement onsultancy to M&E Services f IDA / 66820 Post Open - National 0.00 2023-01-23 2023-04-06 2023-03-13 2023-04-03 2023-05-08 2023-11-04 Adoption ant Selection ation or Training Activities SLU_CARDTP_C_IC_8 / Delive ry of Training in accordance with Training Plan to support Digital Government Infrastru Individual Consult Open - Internationa Pending Impleme technical capacity developm IDA / 66820 cture, Platforms and Service Post 0.00 2023-03-30 2023-05-18 2023-06-08 2023-07-13 2023-11-20 ant Selection l ntation ent of GITS and Public Sector s Modernization Unit, CARDTP PIU Staff, ICT staff and other s as relevant SLU_CARDTP_C_IC_3 / Consu Digital Government Infrastru ltancy Services for the Devel Individual Consult IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2022-03-15 2021-12-27 2022-05-03 2022-05-24 2022-06-28 2023-01-09 opment of the Broadband Pol ant Selection s icy and Strategy SLU_CARDTP_C_IC_17 / Proje Project Implementation Sup Individual Consult IDA / 66820 Prior Open 0.00 Canceled 2022-09-15 2022-11-03 2022-11-24 2022-12-29 2026-06-12 ct Implementation Support port ant Selection SLU_CARDTP_C_IC_10 / Train ing Programme - Enhancing Business Productivity as part Digital Skills and Technology Individual Consult IDA / 66820 Post Open 0.00 Canceled 2022-06-24 2022-08-12 2022-09-02 2022-10-07 2022-12-21 of Protool Capacity Building A Adoption ant Selection pproach (3 Cohorts of 20 per sons per session over a 5 da y training period each) SLU_CARDTP_C_IC_7 / Under take Training and Awareness Assessment and prepare Trai Digital Government Infrastru Individual Consult ning Plan to support technica IDA / 66820 cture, Platforms and Service Post Open 0.00 Canceled 2022-08-25 2022-04-25 2022-10-13 2022-11-03 2022-12-08 2023-02-26 ant Selection l capacity development of GI s TS and Public Sector Moderni zation Unit, CARDTP PIU Staff , ICT staff and others as rele vant SLU_CARDTP_C_IC_11 / Capa Digital Government Infrastru Individual Consult city building of public sector I IDA / 66820 cture, Platforms and Service Prior Open 0.00 Canceled 2022-07-17 2022-09-04 2022-09-25 2022-10-30 2023-04-28 ant Selection T professionals and civil serv s ants Page 3 LC-DPS-208506-CS-INDV / Pr Project Implementation Sup Individual Consult IDA / 66820 Post Open - National 0.00 Signed 2021-04-19 2021-06-07 2021-02-16 2021-06-28 2021-04-14 2021-08-02 2022-01-29 ocurement Specialist port ant Selection LC-DPS-208505-CS-INDV / Pr Project Implementation Sup Individual Consult Open - Internationa IDA / 66820 Post 0.00 Signed 2021-04-19 2021-06-07 2021-02-16 2021-06-28 2021-04-14 2021-08-02 2022-01-29 oject Coordinator port ant Selection l LC-DPS-326635-CS-CDS / Su Digital Skills and Technology IDA / 66820 Post Direct Selection Direct - National 0.00 Canceled 2022-12-01 2022-12-05 2022-12-11 2023-02-14 2023-08-13 pport for Pro-Tool TrainingPro Adoption gramme Page 4 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Somalia Crisis Recovery Project c. Project Number: P173315 d. Total Finance: USD 137.5 Million 2. Project Implementation Agency: Ministry of Finance, FGS 3. Date of Project Plan: July 2020 4. Period Covered by this Procurement: July-2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Procurement Methods (US$ millions)–Goods, Works, and Non- Consulting Services Category Open Open Request for International National Quotation (RfQ) Works ≥ 5.0 <5.0 ≤ 0.2 Goods, IT, and non- ≥ 0.5 <0.5 ≤ 0.1 consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Short List of National Consultants Consulting Engineering and Services Construction Supervision Consultants (Firms) ≤ 0.1 ≤ 0.2 Individual Consultants n.a. n.a. 2 Consulting Services Re Contract Estimated Review Market Selecti Shortli Expected Expected f Description Cost (US$) by Bank Approach on sting Date of Date of No (Prior/Po (Open- Metho (Yes/N Bid Contract . st) National/ d o) Proposal Signatur Limited (QCBS Opening e etc.) , LCBCS , QBS, DS Social Development 70,200.00 July 16, C1 Prior Limited INDV N/A July 11, 2020 Specialist 2020 Agreement for Delivery of Outputs: Provision of Desert Locust Control, Emergency Support to 10,000,000. Direct Un July 16, C2 affected 00 Prior N/A July 9, 2020 Contracting Agency 2020 communities, and Re- establish the Desert Locust Surveillance and Control System. 10,070,20 Total 0.00 3 4 PROCUREMENT Somalia : Somalia Crisis Recovery Project PLAN General Information Country: Somalia 2020-07-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173315 GPN Date: Project Name: Somalia Crisis Recovery Project Loan / Credit No: IDA / D6300, IDA / D8730 Federal Government of Somalia Ministry of Finance Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-188762-CW-RFB / R ehabilitation and Reconstruct Component 2: Medium-Ter Open - Internationa Single Stage - One E Pending Imp 2021-12-1 IDA / D6300 Prior Request for Bids 0.00 2021-02-28 2021-03-05 2021-04-16 2021-05-16 2021-06-20 ion in Open River Breakages m Flood Recovery l nvelope lementation 7 along Jubba and Shabelle bas in SO-MOF-188768-CW-RFB / R Component 2: Medium-Ter Open - Internationa Single Stage - One E Pending Imp 2021-12-1 ehabilitation of flood relief ca IDA / D6300 Prior Request for Bids 0.00 2021-02-28 2021-03-05 2021-04-16 2021-05-16 2021-06-20 m Flood Recovery l nvelope lementation 7 nals of shabelle and Jubba Ri vers SO-MOF-228020-CW-RFQ / R ehabilitation of River Embank Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 ments (7 Sites) in Beledweyn IDA / D6300 Prior Limited 198,109.19 Signed 2021-04-14 2021-05-10 2021-06-09 2021-05-21 m Flood Recovery tions nvelope 6 District – Somalia (Lot-1) SO-MOF-228024-CW-RFQ / R EHABILITATION OF BELEDWE Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 YNE/BUNDOWEY N/KAWANKA IDA / D6300 Prior Limited 164,868.31 Signed 2021-04-14 2021-04-26 2021-06-09 2021-04-30 m Flood Recovery tions nvelope 6 /BUULADA RIVER EMBANKME NT IN BELEDWEYN DISTRICT – SOMALIA (Lot-2) SO-MOF-228026-CW-RFQ / R EHABILITATION OF BELEDWE Component 2: Medium-Ter Request for Quota Single Stage - One E 2021-12-0 YNE/XAWO IDA / D6300 Prior Limited 90,134.76 Signed 2021-04-14 2021-04-29 2021-06-09 2021-05-06 m Flood Recovery tions nvelope 6 TAKO/HORSEED RIVER EMBA NKMENT IN BELEDWEYN DIST RICT – SOMALIA (Lot-3) SO-MOF-229815-CW-RFQ / B Request for ATCH-2 (Beledwyne): REHABI Quotations - LITATION BELEDWEYN/ BULO Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 -KAHIN B-1 (RIGHT) AND BAL IDA / D6300 Prior Limited 159,147.00 Signed 2021-05-05 2021-05-17 2021-06-30 2021-05-21 m Flood Recovery tions nvelope (Emergency) 7 ADWEYN/BULO-KAHIN A-1 (RI SPD -Compet GHT) RIVER EMBANKMENT IN itive BELEDWEYN DISTRICT – SOM ALIA (C4) SO-MOF-229841-CW-RFQ / B Request for ATCH-2 (Beledwyne): REHABI Quotations - LITATION OF CEELKA TOWFIQ Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 (BEERTA HUSEEN DHEERE) A IDA / D6300 Prior Limited 62,680.00 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-21 m Flood Recovery tions nvelope (Emergency) 5 ND HELO KILIYO TO HOODLE SPD -Compet Y RIVER EMBANKMENT IN BE itive LEDWEYN DISTRICT – SOMALI A (C5) SO-MOF-229843-CW-RFQ / B atch-2 (Beledwyne): REHABIL Request for ITATION OF BELEDWEYN/DHA Quotations - RKEYNTA 1, BELEDWEYN/DH Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 181,262.94 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-21 ARKEYNTA 2, BELEDWEYN/S m Flood Recovery tions nvelope (Emergency) 5 HINIILE 1, AND BALADWEYN/ SPD -Compet SHINIILE 2 RIVER EMBANKME itive NT IN BELEDWEYN DISTRICT – SOMALIA (C7) SO-MOF-229844-CW-RFQ / B atch-2 (Beledwyn): REHABILI Request for TATION OF BELEDWEYNE/ DO Quotations - OLOGAAL (BEERTA CIILOW) Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 239,419.76 Signed 2021-05-03 2021-05-17 2021-06-28 2021-05-21 (LEFT), BELEDWEYNE/XUBEE m Flood Recovery tions nvelope (Emergency) 5 Y 2, BELEDWEYNE/ XUBEEY 3 SPD -Compet AND BEBELEDWEYNE/XUBEE itive Y 4 RIVER EMBANKMENT IN B ELEDWEYN DISTRICT – SOMA LIA (C8) SO-MOF-229845-CW-RFQ / B Request for atch-2 (Beledwyn): REHABILI Quotations - TATION OF BELEDWEYNE/XU Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 155,960.80 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-11 BEEY 6 AND BELEDWEYNE / m Flood Recovery tions nvelope (Emergency) 5 XUBEEY 8 RIVER EMBANKME SPD -Compet NT IN BELEDWEYN DISTRICT itive – SOMALIA (C9) SO-MOF-229846-CW-RFQ / B atch-2 (Beledwyn): REHABILI TATION OF DAMALAW/XURIY Request for E1, / SIIGAALOW/ KALIAGA Y Quotations - UUSUF A, BELEDWEYNE/ SIIG Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 172,386.28 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-11 AALOW / KALIAGA YUUSUF B, m Flood Recovery tions nvelope (Emergency) 5 BELEDWEYN/BEERATA MOHA SPD -Compet MED SALAAD 1, AND BELED itive WEYN/BEERATA MOHAMED S ALAAD 2 RIVER EMBANKMEN T IN BELEDWEYN DISTRICT –( C10) SO-MOF-229847-CW-RFQ / B atch-2 (Beledwyn): REHABILI TATION OF BELEDWEYNE/CE Request for ELKA TAWFIIQ/ BEERTA HUSE Quotations - EN DHEERE1, BELEDWEYNE/ Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 IDA / D6300 Prior Limited 153,159.44 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-11 LAANTA HILAAC/KALIGA ABDI m Flood Recovery tions nvelope (Emergency) 5 GARAAD, BELEDWEYNE/ BER SPD -Compet DAHA/RADERKA/HILO BARDO itive 1AND BELEDWEYNE/ BERDA HA/RADERKA/HILO BARDO 2 RIVER EMBANKMENT ( C11) SO-MOF-229848-CW-RFQ / B Request for atch-2 (Beledwyn): REHABILI Quotations - TATION OF BLEDWEYNE/HAA Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 WOTAKOBALADWEYN-4 (LEF IDA / D6300 Prior Limited 152,241.50 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-11 m Flood Recovery tions nvelope (Emergency) 5 T) AND BELEDWEYNE/BILIS D SPD -Compet IID 2 RIVER EMBANKMENT IN itive BELEDWEYN DISTRICT – SOM ALIA (C12) Page 1 SO-MOF-229849-CW-RFQ / B Request for atch-2 (Beledwyn): REHABILI Quotations - TATION OF BELEDWEYN/ QO Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 OQANE, BELELDWAYN/XAWO IDA / D6300 Prior Limited 161,580.00 Signed 2021-05-03 2021-06-06 2021-06-28 2021-06-11 m Flood Recovery tions nvelope (Emergency) 5 TAKO, /BELEDWEYN/BILISDII SPD -Compet D 1 RIVER EMBANKMENT IN B itive ELEDWEYN DISTRICT – SOMA LIA (C13) Request for SO-MOF-229852-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-2 IDA / D6300 Prior Limited 170,543.80 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-19 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/Magadley 2) - C2 SPD -Compet itive Request for SO-MOF-229853-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-2 IDA / D6300 Prior Limited 150,315.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-19 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/gafaay 1) - C3 SPD -Compet itive Request for SO-MOF-229857-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E 2022-01-2 IDA / D6300 Prior Limited Small Works 96,958.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-19 n of River Embankments (Jow m Flood Recovery tions nvelope 7 (Emergency) har/Sabuun) - C7 SPD -Compet itive Request for SO-MOF-229860-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-2 IDA / D6300 Prior Limited 140,354.00 Signed 2021-06-05 2021-05-10 2021-07-31 2021-05-19 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/Buulo haji) - C10 SPD -Compet itive SO-MOF-229842-CW-RFQ / B Request for ATCH-2 (Beledwyne): REHABI Quotations - LITATION OF BALADWEYN/BU Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 ULO KAHIN 2, BALADWEYN /B IDA / D6300 Prior Limited 198,329.46 Signed 2021-05-15 2021-06-07 2021-07-10 2021-06-18 m Flood Recovery tions nvelope (Emergency) 6 UULO KAHIN 3 AND BALADW SPD -Compet EYN/BUULO KAHIN 4RIVER E itive MBANKMENT IN BELEDWEYN DISTRICT – SOMALIA (C6) Request for SO-MOF-229854-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 IDA / D6300 Prior Limited 162,610.60 Signed 2021-05-16 2021-06-14 2021-07-11 2021-06-18 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/gafaay 2) - C4 SPD -Compet itive Request for SO-MOF-229856-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 IDA / D6300 Prior Limited 172,125.85 Signed 2021-05-15 2021-06-14 2021-07-10 2021-06-20 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 6 har/Geedo Barkan 2 & Buulo SPD -Compet Ahmed) C6 itive Request for SO-MOF-229855-CW-RFQ / B Quotations - atch-1 (Jowhar): Rehabilitatio Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-01-0 IDA / D6300 Prior Limited 185,812.00 Signed 2021-05-16 2021-06-14 2021-07-11 2021-06-20 n of River Embankments (Jow m Flood Recovery tions nvelope (Emergency) 7 har/Geedo Barkan 1) - C5 SPD -Compet itive Request for B SO-MOF-235315-CW-RFB / S ids - Small W Component 5: Contingent Single Stage - One E 2022-05-1 upply and Installation of Sola IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-07-31 2021-08-05 2021-09-16 2021-10-16 2021-11-20 Emergency Response nvelope 9 r panels to hospitals (Martini nvelope proc & Banadir) ess) Request for SO-MOF-229850-CW-RFQ / B Quotations - atch-2 (Beledwyn): REHABILI Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2021-12-2 TATION OF BELEDWEYN/HOO IDA / D6300 Prior Limited 0.00 Canceled 2021-05-03 2021-06-28 m Flood Recovery tions nvelope (Emergency) 5 DLEY RIVER EMBANKMENT IN SPD -Compet BELEDWEYN DISTRICT – SOM itive ALIA (C4) Request for SO-MOF-238412-CW-RFQ / B Quotations - ardhere: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-02-2 IDA / D6300 Prior Limited 0.00 2021-07-05 2021-10-19 2021-08-30 er Embankments Shimbiro ea m Flood Recovery tions nvelope (Emergency) mentation 6 st, Baardhere District – Soma SPD -Compet lia (C1) itive Request for SO-MOF-238415-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 156,525.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-08 ver Embankments Bandar 2, m Flood Recovery tions nvelope (Emergency) 6 Baardhere District – Somalia SPD -Compet (C2) itive Request for SO-MOF-238416-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 151,605.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-08 ver Embankments Bandar 3, m Flood Recovery tions nvelope (Emergency) 6 Baardhere District – Somalia SPD -Compet (C3) itive Request for SO-MOF-238417-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-02-2 ver Embankments Hilo banee IDA / D6300 Prior Limited 0.00 2021-07-05 2021-10-19 2021-08-30 m Flood Recovery tions nvelope (Emergency) mentation 6 d 1 and Hilo baneed 2, Baard SPD -Compet here District – Somalia (C4) itive Request for SO-MOF-238418-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 152,534.20 Signed 2021-07-05 2021-10-19 2021-08-30 2022-03-08 ver Embankments Hilo banee m Flood Recovery tions nvelope (Emergency) 6 d 3, Baardhere District – Som SPD -Compet alia (C5) itive Request for SO-MOF-238419-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Prior Limited 177,395.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-08 ver Embankments Hilo banee m Flood Recovery tions nvelope (Emergency) 6 d 6, Baardhere District – Som SPD -Compet alia (C6) itive Request for SO-MOF-238421-CW-RFQ / B Quotations - aardhere: Rehabilitation of Ri Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 ver Embankments Bandar 1, IDA / D6300 Prior Limited 136,540.00 Signed 2021-07-05 2021-10-27 2021-08-30 2022-03-08 m Flood Recovery tions nvelope (Emergency) 6 Bulo cesan 1 and Bulo-cesan SPD -Compet 2, Baardhere District – Somal itive ia (C7) Request for SO-MOF-235264-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Daaf bari 1 in m Flood Recovery tions nvelope (Emergency) 6 Agooye District – Somalia (C1 SPD -Compet 1) itive Request for SO-MOF-235233-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-0 IDA / D6300 Post Limited 0.00 Canceled 2021-07-15 2021-09-09 Embankments (3 Sites) in Af m Flood Recovery tions nvelope (Emergency) 8 goye district – Somalia (C1) SPD -Compet itive Request for SO-MOF-235235-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-0 IDA / D6300 Post Limited 0.00 Canceled 2021-07-15 2021-09-09 Embankments Beerta Kuwayt m Flood Recovery tions nvelope (Emergency) 8 1 in Afgoye District – Somalia SPD -Compet (C2) itive Page 2 Request for SO-MOF-235267-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 Embankments Ceelka cartan/ IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 m Flood Recovery tions nvelope (Emergency) 6 farta baabaa hasan1 in Afgoo SPD -Compet ye District – Somalia (C13) itive Request for SO-MOF-235272-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Raqayle 1 in A m Flood Recovery tions nvelope (Emergency) 6 fgooye District – Somalia (C1 SPD -Compet 5) itive Request for SO-MOF-235278-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Damalay1 in A m Flood Recovery tions nvelope (Emergency) 6 fgooye District – Somalia (C1 SPD -Compet 7) itive Request for SO-MOF-235281-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Dhagax tuurk m Flood Recovery tions nvelope (Emergency) 6 a 1 in Afgooye District – Som SPD -Compet alia (C19) itive Request for SO-MOF-235283-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Baalguri in Af m Flood Recovery tions nvelope (Emergency) 6 gooye District – Somalia (C21 SPD -Compet ) itive Request for SO-MOF-235284-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankments Beerta imaara m Flood Recovery tions nvelope (Emergency) 6 adka 1 in Afgooye District – S SPD -Compet omalia (C22) itive Request for SO-MOF-235288-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-02-2 IDA / D6300 Post Limited 0.00 Canceled 2021-07-05 2021-08-30 Embankment (1 Site) in Afgo m Flood Recovery tions nvelope (Emergency) 6 ye District – Somalia (C24) SPD -Compet itive SO-MOF-238422-CW-RFQ / D ollow: Procurement of: Qansa Request for xlay,Qansaxlay/Beerta Aadan Quotations - Modoobe 1, Qansaxlay/Beert Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 a Aadan Modoobe 2, Dollow/ m Flood Recovery tions nvelope (Emergency) 9 Qansaxlay/Beerta osman Abd SPD -Compet ikadir1, Dollow/ Qansaxlay/B itive eerta osman Abdikadir2. In J ubba-land Somalia (C1) Request for SO-MOF-238426-CW-RFQ / D Quotations - ollow: Procurement of Lot2 i Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 n Dollow/ Cambaha/ Dhuma IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 dhumay1/ Dhumadhumay2 D SPD -Compet huudhhumy 3 of Jubaland - S itive omalia (C2) SO-MOF-238428-CW-RFQ / D Request for ollow: Procurement of: [Five Quotations - villages Dollow/Una/Beerta Z Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 akaria Abdirashid1, Dollow/U m Flood Recovery tions nvelope (Emergency) 9 na/Beerta Zakaria Abdirashid SPD -Compet 2 district Jubaland state of So itive malia. (C3) Request for SO-MOF-238430-CW-RFQ / D Quotations - ollow: Procurement of: Five v Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 illages in Dollow/Una/Hilo, Un IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 a/Beerta Abdi dool and Una/B SPD -Compet eerta Abdikawi mohamed (C itive 4) Request for SO-MOF-238431-CW-RFQ / D Quotations - ollow: Procurement of: Dollo Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 w/Suul Guduud/Abdiyo Abdi m Flood Recovery tions nvelope (Emergency) 9 Baale, Suul Guduud/mohame SPD -Compet d Abdullahi (C5) itive Request for SO-MOF-238432-CW-RFQ / D Quotations - ollow: Procurement of: [Suulg Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 udud/Ali sharif , Quracleey/K IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 eli Dahir, Suulgudud/Adam Ib SPD -Compet rahim] in Dollow Juba land So itive malia. (C6) SO-MOF-257503-CW-RFB / Jo Request for B whar Batch 2 Works: Rehabili ids - Small W tation of River Embankment Component 2: Medium-Ter Single Stage - One E 2022-08-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-10-30 2021-11-04 2021-12-16 2022-01-15 2022-02-19 at Magadley 1, Muriyaale, Gu m Flood Recovery nvelope 8 nvelope proc maray and Mareeray 1 (3 LO ess) TS) in Jowhar, Hirshabelle Sta te. Request for SO-MOF-255371-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 2 site in Afgoye District, Lo SPD -Compet wer Shabelle Region - (C6) itive Request for SO-MOF-255309-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 Embankments at Aytiro 1 an IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 d Dhagaxtuurka 2 sites in Af SPD -Compet goye District, Lower Shabelle itive Region - (C1) Request for SO-MOF-255347-CW-RFQ / A Quotations - fgooye: Rehabilitation of Rive Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 r Embankment at Baalguri 2 IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 site in Afgoye District, Lower SPD -Compet Shabelle Region - (C2) itive Request for SO-MOF-255357-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 Embankment and Canal Intak IDA / D6300 Post Limited 0.00 Canceled 2021-10-19 2021-12-14 m Flood Recovery tions nvelope (Emergency) 2 e at Beerta Imaaraadka 1 in SPD -Compet Afgoye District, Lower Shabel itive le Region - (C3) SO-MOF-255367-CW-RFQ / A Request for fgoye: Rehabilitation of River Quotations - Embankment & Canal Intake Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 Chamber at Beerta Imaaraad m Flood Recovery tions nvelope (Emergency) 4 ka 2 site in Afgoye District, L SPD -Compet ower Shabelle Region - (C4) itive Page 3 Request for SO-MOF-255369-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 1 site in Afgoye District, Lo SPD -Compet wer Shabelle Region - (C5) itive Request for SO-MOF-255372-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 3 site in Afgoye District, Lo SPD -Compet wer Shabelle Region - (C7) itive Request for SO-MOF-255373-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 4 in Afgoye District, Lower SPD -Compet Shabelle Region - (C8) itive Request for SO-MOF-255374-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 5 in Afgoye District, Lower SPD -Compet Shabelle Region - (C9) itive Request for SO-MOF-255375-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Kuwa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 yt 6 in Afgoye District, Lower SPD -Compet Shabelle Region - (C10) itive Request for B SO-MOF-262209-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-10-0 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-12-15 2022-05-26 2021-12-20 2022-06-05 2022-01-31 2022-07-31 2022-03-02 2022-04-06 ments at Dhagaxtuurka 2 an m Flood Recovery nvelope 3 nvelope proc d Aytiro 1 (2 Sites) in Afgoye ess) District, SWS State Request for SO-MOF-262214-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 Embankment at Baalguri 2 si m Flood Recovery tions nvelope (Emergency) 3 te in Afgoye District, Lower S SPD -Compet habelle Region (C2) itive Request for SO-MOF-262215-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Imaa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 raakda 1 in Afgoye District, L SPD -Compet ower Shabelle Region (C3) itive Request for SO-MOF-262216-CW-RFQ / A Quotations - fgoye: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Beerta Imaa IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 m Flood Recovery tions nvelope (Emergency) 3 raadka 2 in Afgoye District, L SPD -Compet ower Shabelle Region (C4) itive Request for SO-MOF-257752-CW-RFQ / D Quotations - ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-2 IDA / D6300 Post Limited 0.00 Canceled 2021-11-04 2021-12-30 Embankment at Qansaxlay Si m Flood Recovery tions nvelope (Emergency) 8 te In Dollow District, Gedo Re SPD -Compet gion (Lot 1) itive Request for B SO-MOF-262226-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-10-0 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-12-15 2022-05-26 2021-12-20 2022-06-05 2022-01-31 2022-03-02 2022-04-06 ment (five sites) in Dollow Di m Flood Recovery nvelope 3 nvelope proc strict, Gedo Region - (2 Lots) ess) SO-MOF-257753-CW-RFQ / D Request for ollow: Rehabilitation of River Quotations - Embankment at Qansaxlay ( Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-08-1 IDA / D6300 Prior Limited 0.00 2021-12-20 2022-03-07 2022-02-14 Beerta Aden madobe1,2 and m Flood Recovery tions nvelope (Emergency) mentation 3 Beerta osman Abdikadir1,2) i SPD -Compet n Dollow District, Gedo Regio itive n (C2) SO-MOF-257760-CW-RFQ / D Request for ollow: Rehabiliation of River Quotations - Embankment at Buulo Qaloo Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2023-05-11 c (Mohamed Qase 1,2,3 and m Flood Recovery tions nvelope (Emergency) 3 Dollow/Iskudaraha Ahmed Ali SPD -Compet Qeyr) in Dollow District, Ged itive o Region (C9) Request for SO-MOF-257758-CW-RFQ / D Quotations - ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 Embankment at Sulguduud ( IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 2023-05-11 m Flood Recovery tions nvelope (Emergency) 3 Ali Sharif, Adan Ibrahim, Abdi SPD -Compet rashid, and Hassan) in Dollo itive w District, Gedo Region - (C7 ) Request for SO-MOF-257759-CW-RFQ / D Quotations - ollow: Rehabilitation of River Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-2 IDA / D6300 Post Limited 0.00 Canceled 2021-11-04 2021-12-30 Embankment at Sulguduud N m Flood Recovery tions nvelope (Emergency) 8 asteh in Dollow District, Gedo SPD -Compet Region (Lot 8) itive Request for B SO-MOF-257755-CW-RFB / R ids - Small W ehbilitation of River embank Component 2: Medium-Ter Single Stage - One E 2022-09-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-11-30 2022-05-26 2021-12-05 2022-06-05 2022-01-16 2022-02-15 2022-03-22 ment (5 sites) in Dollow distri m Flood Recovery nvelope 8 nvelope proc ct, Jubaland (2 Lots) ess) Request for B SO-MOF-257754-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-09-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2021-11-30 2022-06-06 2021-12-05 2022-06-10 2022-01-16 2022-02-15 2022-03-22 ments (4 sites) in Dollow Dist m Flood Recovery nvelope 8 nvelope proc rict, Jubaland State (2 Lots) ess) Request for SO-MOF-256788-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works Under Imple 2022-08-1 IDA / D6300 Prior Limited 0.00 2021-12-20 2022-03-24 2022-02-14 mbankment at Boyle farm 1 i m Flood Recovery tions nvelope (Emergency) mentation 3 n Luuq District, Gedo Region SPD -Compet - (C1) itive Request for SO-MOF-256790-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-2 IDA / D6300 Post Limited 0.00 Canceled 2021-10-30 2021-12-25 mbankment at Bacaad Weyn m Flood Recovery tions nvelope (Emergency) 3 1&2 in Luuq District, Gedo Re SPD -Compet gion - (C2) itive Request for SO-MOF-256791-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-24 2022-02-14 2023-03-21 mbankment at Bacaadlay Far m Flood Recovery tions nvelope (Emergency) 3 m 3 in Luuq District, Gedo Re SPD -Compet gion - (C3) itive Page 4 Request for SO-MOF-256792-CW-RFQ / L Quotations - uuq: Rehabilitation of River E Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Canceled 2021-12-20 2022-02-14 mbankment at Bacaadlay Far m Flood Recovery tions nvelope (Emergency) 3 m 4 in Luuq District, Gedo Re SPD -Compet gion - (C4) itive SO-MOF-255593-CW-RFQ / K Request for ismayo: Rehabilitation of Riv Quotations - er Embankments at Goobwey Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 n (Farta school ka, Fargeelee IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 y, Farta Garoonka and Masha SPD -Compet qo 1 & 2) and Qamqam (Maq itive ara'as 1, 2 & 3) in Kismayo T own, Jubba-land state - (C1) Request for SO-MOF-262246-CW-RFQ / K Quotations - ismayo: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 er Embankment In Kismayo T m Flood Recovery tions nvelope (Emergency) 3 own, Jubaland State (C1) SPD -Compet itive Request for SO-MOF-255595-CW-RFQ / K Quotations - ismayo: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-06-1 er Embankment at Yoontoow IDA / D6300 Post Limited 0.00 Canceled 2021-10-21 2021-12-16 m Flood Recovery tions nvelope (Emergency) 4 (Mayakondo & Shubiiro sites) SPD -Compet in Kismayo town, Jubba-land itive state (C2) Request for SO-MOF-262247-CW-RFQ / K Quotations - ismayo: Rehabilitation of Riv Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-08-1 IDA / D6300 Prior Limited 0.00 Signed 2021-12-20 2022-03-07 2022-02-14 er Embankment in Kismayo T m Flood Recovery tions nvelope (Emergency) 3 own, Jubaland State (C2) SPD -Compet itive Request for SO-MOF-238433-CW-RFQ / D Quotations - ollaw: Procurement of: [Five Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-2 villages in dollaw Suulgudud/ IDA / D6300 Post Limited 0.00 Canceled 2021-08-05 2021-09-30 m Flood Recovery tions nvelope (Emergency) 9 Ali sharif, Quracleey/Keli Dahi SPD -Compet r district Jubaland state of So itive malia. (C7) SO-MOF-235230-CW-RFQ / B Request for atch-3 (Beledwyn): Rehabilita Quotations - tion of Masonry Retaining Wa Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-0 ll (in Hilo Bardo, Horseed, Bal IDA / D6300 Post Limited 0.00 Canceled 2021-07-15 2021-09-09 m Flood Recovery tions nvelope (Emergency) 8 adweyn 1, Ibrahim Farm & D SPD -Compet onsubagle 5 Villages)for Floo itive d Protection in Beledweyn Di strict – Somalia (C15) Request for SO-MOF-235875-CW-RFQ / R Quotations - ehabilitation of Beledweyn/H Component 2: Medium-Ter Request for Quota Single Stage - One E Small Works 2022-03-1 IDA / D6300 Post Limited 0.00 Canceled 2021-07-20 2021-09-14 oodley River Embankment in m Flood Recovery tions nvelope (Emergency) 3 Beledweyn District – Somalia SPD -Compet (C14). itive SO-MOF-266544-CW-RFB / R Request for B ehabilitation of River Embank ids - Small W Component 2: Medium-Ter Single Stage - One E 2023-01-1 ment at Magadley 1, Muriyaa IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-08-06 2022-06-16 2022-07-21 m Flood Recovery nvelope 7 le, nvelope proc Gumaray and Mareeray 1 (3 ess) LOTS) in Jowhar, Hirshabelle State Request for B SO-MOF-262257-CW-RFB / R ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E 2023-01-1 ehabilitation of Far Libaax Ro IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-07-07 2022-06-16 2022-07-21 m Flood Recovery l nvelope 7 ad (phase-I) in Beledwayne, nvelope proc Hirshabelle State ess) SO-MOF-262258-CW-RFB / L Request for B ot 1: Rehabilitation of Habala ids - Small W Component 2: Medium-Ter Single Stage - One E 2023-01-1 Adey MCH in Bardhere Distric IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-06-16 2022-07-21 m Flood Recovery nvelope 7 t nvelope proc Lot 2: Rehabilitation of Horse ess) ed Health Facility in Berdere District SO-MOF-262259-CW-RFB / L Request for B ot 1: Rehabilitation of Sigaalo ids - Small W w MCH in Beldewyne District Component 2: Medium-Ter Single Stage - One E 2023-01-1 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-03-31 2022-05-26 2022-04-05 2022-06-05 2022-05-17 2022-07-05 2022-06-16 2022-07-21 Lot 2: Rehabilitation of Haaw m Flood Recovery nvelope 7 nvelope proc o Taako Health Facility in Bal ess) edweyn District Request for B SO-MOF-276917-CW-RFB / R ids - Small W ehabilitation of 5 sites ( Kalu Component 2: Medium-Ter Single Stage - One E Under Imple 2022-12-0 IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-02-20 2022-03-14 2022-02-25 2022-03-16 2022-04-08 2022-03-26 2022-05-08 2022-04-26 2022-06-12 undi 1 &2, Garaash and Moky m Flood Recovery nvelope mentation 9 nvelope proc o 1& 3) in Jowhar District ess) Request for SO-MOF-277130-CW-RFQ / C Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2022-11-2 onstruction of two rooms to h IDA / D6300 Prior Limited 0.00 2022-04-05 2022-05-31 Emergency Response tions nvelope Non Bank-SP lementation 7 ouse Oxygen plants in Baido D) a and Kismayo Request for SO-MOF-295717-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-08 2022-09-02 Emergency Response tions nvelope Non Bank-SP lementation 1 rehouse for the State of Jubal D) and Request for SO-MOF-295721-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-08 2022-09-02 Emergency Response tions nvelope Non Bank-SP lementation 1 rehouse for the State of Sout D) hwest Request for SO-MOF-295723-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-09 2022-09-03 Emergency Response tions nvelope Non Bank-SP lementation 2 rehouse for the State of Gal D) mudug Request for SO-MOF-295724-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-0 ehabilitation of a medical wa IDA / D6300 Prior Limited 0.00 2022-07-09 2022-09-03 Emergency Response tions nvelope Non Bank-SP lementation 2 rehouse for the State of Hirsh D) abelle Request for SO-MOF-295727-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-2 ehabilitation of Medical Natio IDA / D6300 Prior Limited 0.00 2022-08-05 2022-09-30 Emergency Response tions nvelope Non Bank-SP lementation 9 nal warehouse in Mogadishu D) SO-MOF-295726-CW-RFQ / R Request for ehabilitation of Medical ware Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-2 IDA / D6300 Prior Limited 0.00 2022-08-05 2022-09-30 house for Banadir regional ad Emergency Response tions nvelope Non Bank-SP lementation 9 ministration (BRA) D) Request for SO-MOF-295719-CW-RFQ / R Component 5: Contingent Request for Quota Single Stage - One E Quotations ( Pending Imp 2023-03-2 ehabilitation of Medical ware IDA / D6300 Prior Limited 0.00 2022-08-05 2022-09-30 Emergency Response tions nvelope Non Bank-SP lementation 9 house in Puntland State D) Request for B SO-MOF-307801-CW-RFB / R ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-06-1 ehabilitation of river embank IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-08-31 2022-08-25 2022-09-05 2022-09-02 2022-10-17 2022-09-29 2022-11-16 2022-12-15 2022-12-21 m Flood Recovery nvelope mentation 9 ment (3 sites) in Luuq district nvelope proc , Jubaland State ess) Page 5 Request for B SO-MOF-307802-CW-RFB / R ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-06-1 ehabilitation of Belethawa's IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-08-31 2022-09-13 2022-09-05 2022-09-14 2022-10-17 2022-10-17 2022-11-16 2023-02-14 2022-12-21 m Flood Recovery l nvelope mentation 9 Dolow (2.9Km) and Elwaq (1. nvelope proc 9Km) Roads ess) Request for B SO-MOF-307803-CW-RFB / R ids - Small W ehabilitation of Hudur Main R Component 2: Medium-Ter Open - Internationa Single Stage - One E 2023-06-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 Canceled 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 oad (2.5 kilometers) and Blim m Flood Recovery l nvelope 9 nvelope proc aqasi Road (3.9 kilometers) i ess) n Hudur Request for B SO-MOF-316762-CW-RFB / R ids - Small W ehabilitation of Hudur Main R Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-07-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-09-30 2022-10-04 2022-10-05 2022-11-16 2022-11-16 2022-12-17 2022-12-16 2023-03-07 2023-01-20 oad (2.5Km) and Blimaqasi R m Flood Recovery l nvelope mentation 9 nvelope proc oad (3.9Km) in Hudur district ess) , South West State Request for B SO-MOF-316766-CW-RFB / R ids - Small W ehabilitation of Dhulu Ale (3. Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-07-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-09-30 2022-11-08 2022-10-05 2022-11-15 2022-11-16 2022-12-20 2022-12-16 2023-05-23 2023-01-20 5Km), Dolow (1.25Km) and B m Flood Recovery l nvelope mentation 9 nvelope proc oiya Road (4.0Km) in Luuq, Ju ess) baland State SO-MOF-316767-CW-RFB / R Request for B e-construction of Kulmis Mat ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-08-0 ernal and Child Health (MCH) IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-10-15 2022-11-08 2022-10-20 2022-11-15 2022-12-01 2022-12-19 2022-12-31 2023-01-31 2023-02-04 m Flood Recovery l nvelope mentation 3 Facility in Jowhar District -Hir nvelope proc shabelle State, Somalia. ess) SO-MOF-316794-CW-RFB / R Request for B e-construction of Shidley Mat Component 3: Longer-Ter ids - Small W Open - Internationa Single Stage - One E Under Imple 2023-08-0 ernal and Child Health (MCH) IDA / D6300 m Disaster Risk Preparednes Prior Request for Bids orks SPD (1 e 0.00 2022-10-15 2022-11-08 2022-10-20 2022-11-15 2022-12-01 2022-12-15 2022-12-31 2023-03-14 2023-02-04 l nvelope mentation 3 Facility in Hudur District - So s nvelope proc uth West State, Somalia. ess) Request for B SO-MOF-319819-CW-RFB / R ids - Small W ehabilitation of Far Libaax Ro Component 2: Medium-Ter Single Stage - One E Under Imple 2023-08-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-10-31 2022-11-15 2022-11-05 2023-01-17 2022-12-17 2022-11-26 2023-01-16 2023-01-31 2023-02-20 ad (2 km) in Beledweyne, Hir m Flood Recovery nvelope mentation 9 nvelope proc shabelle State of Somalia ess) SO-MOF-319822-CW-RFB / R Request for B e-Construction of Habala Ade ids - Small W y Maternal and Child Health ( Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-27 2023-02-15 2023-03-06 2023-03-22 MCH) Facility and Re-Constru m Flood Recovery nvelope mentation 8 nvelope proc ction Horseed Healthcare Fac ess) ility, Bardere District, Jubbala nd State, Somalia SO-MOF-319827-CW-RFB / R Request for B e-construction of Sigaalow M ids - Small W aternal and Child Health (MC Component 2: Medium-Ter Single Stage - One E Under Imple 2023-08-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-10-31 2022-11-15 2022-11-05 2022-12-21 2022-12-17 2022-11-27 2023-01-16 2023-03-06 2023-02-20 H) Facility and Haawa Taako m Flood Recovery nvelope mentation 9 nvelope proc Healthcare (HF) Facility in Be ess) ledweyne District, Hirshabell e State SO-MOF-319829-CW-RFB / R Request for B ehabilitation of river embank ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-08-1 ments at Dhagaxtuurka 2 (21 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-10-31 2022-11-15 2022-11-05 2022-12-14 2022-12-17 2022-11-24 2023-01-16 2023-02-07 2023-02-20 m Flood Recovery nvelope mentation 9 0m) and Aytiro 1 (200m) Site nvelope proc s in Afgoye District, Southwe ess) st State of Somalia. SO-MOF-319831-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover Request for B ing the following sites: ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-16 2022-12-05 2022-12-14 2023-01-16 2022-11-23 2023-02-15 2023-03-06 2023-03-22 - Lot-1: Dollow/Una (Qansa m Flood Recovery nvelope mentation 8 nvelope proc xlay (276m). ess) - Lot-2: Dollow/Una/ (Beert a Zakaria Abdirashid1 & 2 (2 05.5m) SO-MOF-319832-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover Request for B ing the following sites: ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-23 2023-02-15 2023-03-06 2023-03-22 - LOT 1: Dollow/Sulguduud m Flood Recovery nvelope mentation 8 nvelope proc (Mudeey Ali 1,2&3 (349m) an ess) d; - LOT 2: Dollow Sulguduud/ Nasteh (196m) SO-MOF-319835-CW-RFB / R ehabilitation of river embank ment in Dollow District, cover Request for B ing the following two sites: ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 - Lot-1: Dollow/Una (Beerta IDA / D6300 m Flood Recovery Prior Request for Bids Limited nvelope orks SPD (1 e 0.00 mentation 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-23 2023-02-15 2023-01-31 2023-03-22 8 Abdikawi Mohamed, Beerta A nvelope proc bdi dool, and Hillo (360.2m) ess) and; - Lot-2: Doolaw/Sulguduud (Husein Ibrahim 1&2 (466m) SO-MOF-319837-CW-RFB / R ehabilitation of river embank ment sites in Jowhar District, Hirshabelle State of Somalia, Request for B consisting of the following 3 l ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-1 ots IDA / D6300 Prior Request for Bids Limited orks SPD (1 e 0.00 2022-11-30 2022-11-15 2022-12-05 2022-12-21 2023-01-16 2022-11-24 2023-02-15 2023-03-06 2023-03-22 m Flood Recovery nvelope mentation 8 nvelope proc Lot 1 - Jowhar/Magadley 1 (3 ess) 30m) Lot 2 - Jowhar/Muryaale & Gu mareey (460m) Lot 3- Jowhar/Mareerey 1 & Mareerey 2 (450m) Request for B SO-MOF-262240-CW-RFB / R ids - Small W ehabilitation of River Embank Component 2: Medium-Ter Single Stage - One E 2022-11-1 IDA / D6300 Post Request for Bids Open - National orks SPD (1 e 0.00 Canceled 2022-01-31 2022-02-05 2022-03-19 2022-04-18 2022-05-23 ment Bacaadlay Farm 1, 2 & m Flood Recovery nvelope 9 nvelope proc 4 in Luuq District, Gedo Regi ess) on. Request for B SO-MOF-328327-CW-RFB / R ids - Small W Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-09-1 e-habilitation of Imbresso Ro IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-12-01 2022-12-14 2022-12-06 2023-01-11 2023-01-17 2023-02-07 2023-02-16 2023-05-31 2023-03-23 m Flood Recovery l nvelope mentation 9 ad (8.4Km) in Barawe, South nvelope proc West State ess) SO-MOF-328329-CW-RFB / R Request for B e-construction of Malkariyey ids - Small W Component 2: Medium-Ter Single Stage - One E Under Imple 2023-09-2 Maternal and Child Health (M IDA / D6300 Prior Request for Bids Open - National orks SPD (1 e 0.00 2022-12-05 2022-12-14 2022-12-10 2023-01-11 2023-01-21 2023-02-06 2023-02-20 2023-04-26 2023-03-27 m Flood Recovery nvelope mentation 3 CH) Facility Belet Hawo Distri nvelope proc ct Jubbaland State, Somalia ess) Page 6 Request for B SO-MOF-328797-CW-RFB / R ids - Small W e-construction of Bulobarde Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-10-0 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-12-20 2023-01-11 2022-12-25 2023-01-17 2023-02-05 2023-02-22 2023-03-07 2023-04-20 2023-04-11 Cholera Unit Healthcare Facil m Flood Recovery l nvelope mentation 8 nvelope proc ity in Bulobarde District Hirsh ess) abelle State, Somalia Request for B SO-MOF-333065-CW-RFB / R ids - Small W e-construction of Barawe TB Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Imple 2023-10-1 IDA / D6300 Prior Request for Bids orks SPD (1 e 0.00 2022-12-31 2023-01-11 2023-01-05 2023-01-17 2023-02-16 2023-02-16 2023-03-18 2023-04-20 2023-04-22 Unit Healthcare Facility, in Ba m Flood Recovery l nvelope mentation 9 nvelope proc rawe District, South West Sta ess) te, Somalia. Request for B SO-MOF-331714-CW-RFB / R ids - Small W e-construction of Barawe TB Component 2: Medium-Ter Open - Internationa Single Stage - One E 2023-10-1 IDA / D6300 Post Request for Bids orks SPD (1 e 0.00 Canceled 2022-12-31 2023-01-05 2023-02-16 2023-03-18 2023-04-22 Unit Healthcare Facility, Bara m Flood Recovery l nvelope 9 nvelope proc we District, South West State ess) , Somalia. Request for SO-MOF-352047-CW-RFQ / R Quotations - ehabilitation of river embank Component 2: Medium-Ter Request for Quota Single Stage - One E Under Imple 2023-12-2 IDA / D8730 Prior Limited Small Works 0.00 2023-05-05 2023-05-03 2023-06-30 ment site (Moyko 3) in Jowha m Flood Recovery tions nvelope mentation 7 (Emergency) r District. SPD -Compet itive Request for B SO-MOF-358679-CW-RFB / R ids - Small W ehabilitation of Two Canals ( Component 2: Medium-Ter Open - Internationa Single Stage - One E Under Revie 2024-03-1 IDA / D8730 Prior Request for Bids orks SPD (1 e 0.00 2023-05-31 2023-06-28 2023-06-05 2023-07-17 2023-08-16 2023-09-20 Xanshoore and Aslubta) in Jo m Flood Recovery l nvelope w 8 nvelope proc whar District, Hirshabelle Sta ess) te of Somalia GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-214333-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E IDA / D6300 Prior Limited 84,861.70 Signed 2021-04-05 2021-07-14 2021-05-31 2021-07-25 2021-11-27 ocurement of 2 Vehicle for PI ement tions nvelope U SO-MOF-214334-GO-RFQ / Fi Component 4: Project Manag Request for Quota Single Stage - One E Under Imple IDA / D6300 Prior Limited 0.00 2021-04-05 2021-04-26 2021-05-31 2021-11-27 ttings and furniture for PIU Of ement tions nvelope mentation fice SO-MOF-230645-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Under Imple ocurement of IT equipment f IDA / D6300 Prior Limited 0.00 2021-05-06 2021-07-12 2021-07-01 2021-12-28 ement tions nvelope mentation or PIU Office SO-MOF-235305-GO-RFB / Pr ocurement of Locally made cl Component 5: Contingent Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids Open - National 0.00 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 oth face masks for the gener Emergency Response nvelope ementation al public (schools, mosques, etc) SO-MOF-235307-GO-RFB / Pr Component 5: Contingent Single Stage - One E Pending Impl ocure Hygiene supplies (Clor IDA / D6300 Prior Request for Bids Open - National 0.00 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 Emergency Response nvelope ementation ox, soaps, disinfectants, han d sanitizers etc) SO-MOF-235309-GO-DIR / Pr ocurement, commissioning a Component 5: Contingent nd installation of two oxygen IDA / D6300 Prior Direct Selection Direct 0.00 Canceled 2021-06-30 2021-07-05 2021-08-09 2022-02-05 Emergency Response plants for Southwest and Jub aland States of Somalia SO-MOF-235310-GO-RFB / Pr ocurement of Continuous su Component 5: Contingent Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids Open - National 0.00 2021-06-30 2021-07-05 2021-08-16 2021-09-15 2021-10-20 2022-04-18 pply of oxygen to hospitals to Emergency Response nvelope ementation be used for Covid-19 patients SO-MOF-233802-GO-RFQ / B atch-2 (Beledwyn): REHABILI Component 2: Medium-Ter Request for Quota Single Stage - One E TATION OF BELEDWEYN/HOO IDA / D6300 Prior Limited 0.00 Canceled 2021-05-16 2021-07-11 2022-01-07 m Flood Recovery tions nvelope DLEY RIVER EMBANKMENT IN BELEDWEYN DISTRICT – SOM ALIA (C14) SO-MOF-238495-GO-RFQ / Pr ocurement, commissioning a Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids 0.00 2021-07-15 2021-07-20 2021-08-31 2021-09-30 2021-11-04 2022-05-03 nd installation of One oxygen Emergency Response l nvelope ementation plant for Banadir SO-MOF-242309-GO-RFB / Pr ocurement, commissioning a Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids 0.00 2021-07-20 2021-07-25 2021-09-05 2021-10-05 2021-11-09 2022-05-08 nd installation of 2 oxygen pl Emergency Response l nvelope ementation ants for Southwest and Jubal and States of Somalia SO-MOF-247166-GO-RFB / S upply, delivery, installation, c ommissioning and maintenan Component 5: Contingent Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids Open - National 0.00 2021-08-15 2021-08-20 2021-10-01 2021-10-31 2021-12-05 2022-06-03 ce of solar systems to Martini Emergency Response nvelope ementation Hospital, Banadir Hospital, N ational Laboratory and Minist ry of Health SO-MOF-273751-GO-RFQ / P Component 4: Project Manag Request for Quota Single Stage - One E Under Imple urchase of IT equipment for S IDA / D6300 Prior Limited 0.00 2022-04-05 2022-03-03 2022-05-31 2022-11-27 ement tions nvelope mentation tate project teams (3 Lots) SO-MOF-273756-GO-RFQ / P Component 4: Project Manag Request for Quota Single Stage - One E Under Imple urchase of office furniture for IDA / D6300 Prior Limited 0.00 2022-04-05 2022-03-03 2022-05-31 2022-11-27 ement tions nvelope mentation State project teams (3 Lots) SO-MOF-235291-GO-RFQ / Pr ocurement of Medical grade Component 5: Contingent Request for Quota Single Stage - One E IDA / D6300 Post Limited 0.00 Canceled 2021-07-20 2021-09-14 2022-03-13 masks for health care worker Emergency Response tions nvelope s at hospitals and health facil ities SO-MOF-235311-GO-RFB / Pr ocurement of Essential Covid Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl IDA / D6300 Prior Request for Bids 0.00 2022-03-31 2022-04-05 2022-05-17 2022-06-16 2022-07-21 2023-01-17 -19 medicines and kits, labor Emergency Response l nvelope ementation atory reagents and other ess entials countrywide SO-MOF-295728-GO-RFQ / Pr Component 5: Contingent Request for Quota Single Stage - One E Pending Impl ocurement of a vehicle for th IDA / D6300 Prior Limited 0.00 2022-07-09 2022-09-03 2023-03-02 Emergency Response tions nvelope ementation e FMOH to transport Medical Supplies. SO-MOF-304013-GO-RFB / Pr ocurement and installation of Component 5: Contingent Open - Internationa Single Stage - One E Pending Impl additional solar panels (comp IDA / D8730 Prior Request for Bids 0.00 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 2023-06-19 Emergency Response l nvelope ementation lete with spare parts) at the COVID-19 Health Facilities in Mogadishu and FMS Page 7 SO-MOF-304000-GO-RFB / Pr Component 5: Contingent Open - Internationa Single Stage - One E Under Imple ocurement of Lab & medical IDA / D8730 Prior Request for Bids 0.00 2022-08-31 2022-09-05 2022-10-17 2022-11-16 2022-12-21 2023-06-19 Emergency Response l nvelope mentation equipment for Federal & FMS Health Ministries SO-MOF-328332-GO-DIR / Pr Component 3: Longer-Ter ocurement of Hydrological an Direct - Internation Under Revie IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection 0.00 2022-12-10 2022-12-29 2022-12-15 2023-04-14 2023-01-19 2023-07-18 d hydraulic modeling and Flo al w s od Early Warning System soft ware package SO-MOF-346330-GO-RFQ / Pr Component 4: Project Manag Request for Quota Single Stage - One E Under Imple ocurement of office furniture IDA / D6300 Prior Limited 0.00 2023-04-05 2023-05-15 2023-05-31 2023-11-27 ement tions nvelope mentation for Hirshabelle and Jubaland SPT offices SO-MOF-357130-GO-RFB / Pr Component 6: Anticipatory a Open - Internationa Single Stage - One E Under Imple ocurement of Refrigerated tr IDA / D6300 nd Recovery Support for Add Prior Request for Bids 0.00 2023-06-30 2023-05-15 2023-07-05 2023-05-23 2023-08-16 2023-09-15 2023-10-20 2024-04-17 l nvelope mentation ucks for fishing associations ressing Food Insecurity SO-MOF-357133-GO-RFB / Pr Component 6: Anticipatory a Open - Internationa Single Stage - One E Under Imple ocurement of Mobile refriger IDA / D6300 nd Recovery Support for Add Prior Request for Bids 0.00 2023-06-30 2023-05-17 2023-07-05 2023-05-19 2023-08-16 2023-09-15 2023-10-20 2024-04-17 l nvelope mentation ated fish kiosks ressing Food Insecurity SO-MOF-359405-GO-RFQ / Pr Component 3: Longer-Ter Request for Quota Single Stage - One E Pending Impl ocurement of Office Furniture IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-05 2023-07-31 2024-01-27 tions nvelope ementation and Equipment for NEOC s SO-MOF-359413-GO-RFB / Pr Component 3: Longer-Ter Single Stage - One E Pending Impl IDA / D8730 Prior Request for Bids Open - National 0.00 2023-05-31 2023-06-05 2023-07-17 2023-08-16 2023-09-20 2024-03-18 ocurement of Vehicles for NE m Disaster Risk Preparednes nvelope ementation OC s NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-174236-NC-UN / Agr eement for Delivery of Outpu ts: Provision of Desert Locust Component 1: Immediate UN Agencies (Dire Control, Emergency Support IDA / D6300 Basic Services and Livelihoo Prior Direct 41,156,567.00 Signed 2020-07-09 2020-07-10 2020-07-14 2020-07-10 2020-08-18 2020-07-28 2021-02-14 ct) to affected communities, and d Support Re-establish the Desert Locu st Surveillance and Control S ystem. SO-MOF-190204-NC-DIR / No n-consulting Service contract with the INGO- Building Resil Component 1: Immediate ience Communities in Somali IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 14,142,000.00 Signed 2020-12-31 2020-10-28 2021-01-05 2021-02-24 2021-02-09 2022-01-24 2021-08-08 a (BRC for the implementatio d Support n of Immediate basic service s and livelihood support for e arly recovery SO-MOF-217511-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire OUTPUTS WITH UNICEF: SOM IDA / D6300 Prior Direct 0.00 Canceled 2021-03-15 2021-03-20 2021-04-24 2021-10-21 Emergency Response ct) ALIA COVID-19 OUTBREAK RE SPONSE UNDER SOMALIA CRI SIS RESPONSE SO-MOF-223676-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire IDA / D6300 Prior Direct 871,500.00 Signed 2021-04-30 2021-04-07 2021-05-05 2021-04-12 2021-06-09 2021-08-01 2021-12-06 OUTPUTS WITH IOM- SOMALI Emergency Response ct) A COVID-19 RESPONSE UNDE R SCRP SO-MOF-223678-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire IDA / D6300 Prior Direct 8,175,120.00 Signed 2021-04-30 2021-04-07 2021-05-05 2021-04-12 2021-06-09 2021-04-25 2021-12-06 OUTPUTS WITH WHO - SOMA Emergency Response ct) LIA COVID-19 RESPONSE UN DER SCRP PROJECT SO-MOF-223679-NC-DIR / Ag reement with SomRep consor Component 1: Immediate tia for the provision of Early IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 10,681,000.00 Signed 2021-04-30 2021-04-12 2021-05-05 2021-04-29 2021-06-09 2022-06-30 2021-12-06 Recovery Support to The Floo d Support d Affected Communities in Hi rshabelle, Jubaland And Sout hwest SO-MOF-223686-NC-DIR / Ag reement with NEXUS Consort Component 1: Immediate ia for the provision of early r IDA / D6300 Basic Services and Livelihoo Prior Direct Selection Direct 0.00 Canceled 2021-05-31 2021-08-05 2021-06-05 2021-07-10 2022-01-06 ecovery Support to The Flood d Support Affected Communities in Hirs habelle, Jubaland And South west States of Somalia SO-MOF-226047-NC-UN / AG REEMENT FOR DELIVERY OF Component 5: Contingent UN Agencies (Dire OUTPUTS WITH UNICEF: SOM IDA / D6300 Prior Direct 4,416,509.11 Signed 2021-03-31 2021-03-23 2021-04-05 2021-04-01 2021-05-10 2021-04-13 2021-11-06 Emergency Response ct) ALIA COVID-19 OUTBREAK RE SPONSE UNDER SOMALIA CRI SIS RESPONSE SO-MOF-328356-NC-DIR / Str Component 3: Longer-Ter engthening medical emergen Direct - Internation Under Imple IDA / D8730 m Disaster Risk Preparednes Prior Direct Selection 0.00 2022-12-01 2023-01-02 2022-12-06 2023-02-27 2023-01-10 2023-07-09 cy services including intensiv al mentation s e care units for Federal & Sta te referral hospitals SO-MOF-333084-NC-DIR / Ca Component 3: Longer-Ter Direct - Internation Under Imple pacity Building of Somalia Se IDA / D8730 m Disaster Risk Preparednes Prior Direct Selection 0.00 2023-02-28 2023-04-14 2023-03-05 2023-05-17 2023-04-09 2023-10-06 al mentation ed Systems Recovery Initiati s ve (SSRI) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-183832-CS-CDS / Te chnical assistance agency for Component 4: Project Manag UN Agencies (Dire IDA / D6300 Prior Direct 4,437,254.00 Signed 2020-08-28 2020-09-15 2022-08-28 the provision of Project Mana ement ct) gement Support SO-MOF-187653-CS-QCBS / Component 4: Project Manag Least Cost Selecti Open - Internationa SCRP Project Audit and Indep IDA / D6300 Prior 406,932.40 Signed 2020-10-31 2020-11-05 2020-11-21 2020-11-19 2021-01-04 2021-02-24 2021-02-01 2021-04-03 2021-03-03 2021-06-28 2021-04-07 2021-09-30 2021-05-12 2021-11-17 2021-11-08 ement on l endent Verification Agent IVA Page 8 SO-MOF-188776-CS-UN / De Component 2: Medium-Ter UN Agencies (Dire velopment of Designs & Supe IDA / D6300 Prior Direct 0.00 Canceled 2020-11-09 2021-05-08 m Flood Recovery ct) rvision of Construction Works SO-MOF-318290-CS-QCBS / Component 3: Longer-Ter Consultancy service to stren Quality And Cost- Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2022-11-30 2022-11-28 2022-12-21 2022-12-14 2023-02-03 2023-05-04 2023-03-03 2023-04-02 2023-05-07 2023-06-11 2024-06-10 gthen Hydromet service diss Based Selection ation s emination and community en gagement SO-MOF-328349-CS-FBS / Co Component 3: Longer-Ter Fixed Budget Sele nsultancy Service for Strengt IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 Under Review 2022-12-10 2022-12-14 2022-12-31 2023-03-09 2023-02-13 2023-03-13 2023-04-12 2023-05-17 2023-06-21 2024-06-20 ction hening Hydro-Met and Hazar s d Monitoring SO-MOF-328353-CS-FBS / Co Component 3: Longer-Ter nsultancy Service to Strength Fixed Budget Sele IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 Under Review 2022-12-10 2022-12-14 2022-12-31 2023-01-11 2023-02-13 2023-03-13 2023-04-12 2023-05-17 2023-06-21 2024-06-20 en Hydromet Service Dissemi ction s nation and Community Enga gement SO-MOF-333116-CS-CQS / C onsultancy Services for the d Component 3: Longer-Ter evelopment of a Basin Diagn Quality And Cost- Open - Internationa IDA / D8730 m Disaster Risk Preparednes Prior 0.00 Under Review 2023-03-31 2023-03-13 2023-04-21 2023-04-14 2023-06-04 2023-07-02 2023-08-01 2023-09-05 2023-10-10 2024-10-09 ostic and a Strategic Action P Based Selection l s lan for the Juba Basin, Somali a, and preparation of prioritiz ed action projects SO-MOF-346332-CS-LCS / Pr Component 3: Longer-Ter ovision of Consulting Service Consultant Qualifi IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 Canceled 2023-03-31 2023-03-15 2023-04-14 2023-05-14 2023-06-18 2023-12-15 s for Mogadishu's Water Secu cation Selection s rity Diagnostic Study SO-MOF-347690-CS-QCBS / Component 6: Anticipatory a Consulting Service - Capacity Quality And Cost- Open - Internationa Under Implement IDA / D8730 nd Recovery Support for Add Prior 0.00 2023-03-31 2023-05-19 2023-04-21 2023-05-31 2023-06-04 2023-07-02 2023-08-01 2023-09-05 2023-10-10 2024-10-09 Assessment of Federal and S Based Selection l ation ressing Food Insecurity tate level Ministries of Agricu lture and Irrigation SO-MOF-348357-CS-CQS / P Component 3: Longer-Ter ublic Private Engagement (PP Consultant Qualifi Pending Impleme IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-03-31 2023-04-14 2023-05-14 2023-06-18 2023-12-15 E) to strengthen Hydro-mete cation Selection ntation s orological services SO-MOF-352038-CS-CQS / C Component 3: Longer-Ter onsulting Services - Assessm Consultant Qualifi Under Implement IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-04-30 2023-05-14 2023-06-13 2023-07-18 2024-01-14 ent & Delivery of Design & C cation Selection ation s ost Estimation for Eight Regi onal Hospitals SO-MOF-358654-CS-CQS / T Component 3: Longer-Ter echnical assistance to suppor Consultant Qualifi Under Implement IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-16 2023-06-14 2023-07-14 2023-08-18 2024-02-14 t Mogadishu's Water Security cation Selection ation s Diagnostic Study SO-MOF-358661-CS-QCBS / Component 3: Longer-Ter Provision of Consulting Servic Quality And Cost- Pending Impleme IDA / D8730 m Disaster Risk Preparednes Prior Open - National 0.00 2023-07-31 2023-08-21 2023-10-04 2023-11-01 2023-12-01 2024-01-05 2024-02-09 2025-02-08 es for Mogadishu's Water Sec Based Selection ntation s urity Diagnostic Study INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-183841-CS-INDV / H Component 5: Contingent Individual Consult ealth/COVID19 Response Faci IDA / D6300 Prior Limited 120,000.00 Signed 2020-08-20 2020-08-19 2020-08-27 2020-12-12 2020-09-01 2021-01-07 2020-09-04 2021-01-18 2021-06-01 Emergency Response ant Selection litation Consultant SO-MOF-186983-CS-CDS / Fo Component 3: Longer-Ter recasting, Aid Tracking Syste IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 769,060.00 Signed 2020-08-31 2020-11-16 2020-09-10 2020-12-19 2020-11-14 2021-03-29 2021-05-13 m & Needs Assessment to Int s egrate COVID-19 Country Wi de efforts SO-MOF-184256-CS-INDV / R Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 227,880.00 Signed 2020-08-17 2020-09-03 2020-08-22 2020-10-07 2020-09-12 2020-10-09 2020-10-17 2020-10-11 2021-04-15 ecovery Planning Specialist ement ant Selection SO-MOF-183833-CS-QCBS / Component 4: Project Manag Security Risk Management C IDA / D6300 Prior Direct Selection Direct 1,581,419.71 Signed 2020-10-31 2020-09-04 2020-11-10 2020-09-23 2021-01-14 2021-01-09 2021-07-13 ement onsulting Services SO-MOF-183838-CS-INDV / Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 140,400.00 Completed 2020-08-15 2020-09-03 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-09-24 2021-04-18 2021-12-17 Monitoring & Evaluation Spec ement ant Selection ialist SO-MOF-183836-CS-INDV / F Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 213,780.00 Signed 2020-08-15 2020-09-04 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-09-27 2021-04-18 inancial Management Special ement ant Selection ist SO-MOF-183837-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 213,780.00 Signed 2020-08-15 2020-09-03 2020-08-20 2020-09-09 2020-09-10 2020-09-17 2020-10-15 2020-09-27 2021-04-13 roject Engineer ement ant Selection SO-MOF-183834-CS-CDS / Pr Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 334,440.00 Terminated 2020-08-15 2020-09-03 2020-08-25 2020-09-01 2020-09-15 2020-09-17 2020-10-20 2020-09-27 2021-04-18 oject Coordinator ement ant Selection SO-MOF-183835-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 222,420.00 Signed 2020-08-15 2020-09-04 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-09-27 2021-04-18 rocurement Specialist ement ant Selection SO-MOF-183839-CS-INDV / E Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 70,200.00 Signed 2020-08-15 2020-09-03 2020-08-25 2020-09-09 2020-09-15 2020-09-17 2020-10-20 2020-09-25 2021-04-18 nvironmental Safeguard Spe ement ant Selection cialist SO-MOF-183157-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 0.00 Canceled 2020-07-09 2020-07-09 2020-07-14 2020-08-04 2020-09-08 2021-03-07 ocial Development Specialist ement ant Selection SO-MOF-187526-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 0.00 Canceled 2020-08-15 2020-08-20 2020-09-10 2020-10-15 2021-04-13 ocial Development Specialist ement ant Selection SO-MOF-190535-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 140,400.00 Signed 2020-10-31 2020-10-05 2020-11-05 2020-12-09 2020-11-26 2020-12-15 2020-12-31 2020-12-20 2021-06-29 takeholder Engagement Spec ement ant Selection ialist SO-MOF-190539-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 65,035.00 Terminated 2020-10-31 2020-10-05 2020-11-05 2021-02-25 2020-11-26 2021-03-01 2020-12-31 2021-03-02 2021-06-29 roject Administrative Officer ement ant Selection Page 9 SO-MOF-190541-CS-INDV / T Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 105,600.00 Signed 2020-12-31 2020-11-05 2021-01-05 2020-11-16 2021-01-26 2020-11-20 2021-03-02 2020-12-07 2021-08-29 oll-free Hotline Operator (GR ement ant Selection M) SO-MOF-190545-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 52,800.00 Completed 2020-11-30 2020-10-05 2020-12-05 2021-03-22 2020-12-26 2021-04-21 2021-01-30 2021-05-19 2021-07-29 2022-05-19 roject Security Officer ement ant Selection SO-MOF-190709-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 229,320.00 Signed 2020-08-31 2020-10-05 2020-09-05 2020-08-18 2020-09-26 2020-10-08 2020-10-31 2020-09-05 2021-04-29 ocial Development Specialist ement ant Selection SO-MOF-196562-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 0.00 Signed 2020-11-15 2020-11-16 2021-01-03 2022-03-03 2021-01-24 2022-03-14 2021-02-28 2023-03-21 2021-08-27 ement ant Selection er, Hirshabelle State Project Team SO-MOF-196565-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 82,200.00 Signed 2020-12-15 2020-11-16 2021-02-02 2021-05-17 2021-02-23 2021-06-07 2021-03-30 2021-06-08 2021-09-26 ement ant Selection er, Southwest State Project T eam SO-MOF-196570-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 82,200.00 Signed 2020-11-15 2020-11-16 2021-01-03 2021-05-17 2021-01-24 2021-06-06 2021-02-28 2021-06-08 2021-08-27 roject Engineer, Southwest St ement ant Selection ate SO-MOF-196571-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 40,320.00 Signed 2020-12-15 2020-11-16 2021-02-02 2022-01-09 2021-02-23 2022-01-19 2021-03-30 2022-02-06 2021-09-26 roject Engineer, Hirshabelle S ement ant Selection tate SO-MOF-196572-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 102,120.00 Signed 2020-11-15 2020-11-16 2021-01-03 2021-05-19 2021-01-24 2021-06-06 2021-02-28 2021-06-08 2021-08-27 roject Coordinator, Southwes ement ant Selection t SPT SO-MOF-196574-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 49,920.00 Signed 2020-12-15 2020-11-16 2021-02-02 2022-01-09 2021-02-23 2022-01-19 2021-03-30 2022-02-06 2021-09-26 roject Coordinator, Hirshabell ement ant Selection e SPT SO-MOF-197348-CS-INDV / G Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 105,600.00 Signed 2020-10-31 2020-11-16 2020-11-05 2021-02-07 2020-11-26 2021-02-12 2020-12-31 2021-02-16 2021-06-29 BV Officer ement ant Selection SO-MOF-196560-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental Safeguard Offic IDA / D6300 Prior Open 0.00 Canceled 2020-12-31 2020-11-25 2021-02-18 2021-03-11 2021-04-15 2021-10-12 ement ant Selection er, Jubalad SPT SO-MOF-196555-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 0.00 Signed 2020-12-31 2020-11-25 2021-02-18 2022-03-17 2021-03-11 2022-03-23 2021-04-15 2023-04-15 2021-10-12 roject Coordinator, Jubaland ement ant Selection State SPT SO-MOF-196556-CS-INDV / P Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 0.00 Signed 2020-12-31 2020-11-25 2021-02-18 2022-03-17 2021-03-11 2022-03-23 2021-04-15 2023-04-16 2021-10-12 roject Engineer, Jubaland SPT ement ant Selection SO-MOF-196568-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 82,200.00 Signed 2020-12-15 2020-11-25 2021-02-02 2021-05-17 2021-02-23 2021-06-06 2021-03-30 2021-06-08 2021-09-26 ement ant Selection er, Southwest SPT SO-MOF-196567-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 40,320.00 Signed 2020-12-31 2020-11-30 2021-02-18 2022-01-09 2021-03-11 2022-01-19 2021-04-15 2022-02-06 2021-10-12 ement ant Selection er, Hirshabelle SPT SO-MOF-196558-CS-INDV / A Component 4: Project Manag Individual Consult dministration & Finance Offic IDA / D6300 Prior Open 0.00 Canceled 2020-12-31 2020-11-30 2021-02-18 2021-03-11 2021-04-15 2021-10-12 ement ant Selection er, Jubaland SPT SO-MOF-210970-CS-INDV / Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 140,400.00 Signed 2021-01-31 2021-02-10 2021-02-05 2021-03-04 2021-02-26 2021-03-17 2021-04-02 2021-03-30 2021-09-29 MOH Senior Coordinator for S m Disaster Risk Preparednes ant Selection CRP Project s SO-MOF-214330-CS-INDV / F Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 118,560.00 Signed 2021-02-28 2021-02-09 2021-03-05 2021-05-10 2021-03-26 2021-06-06 2021-04-30 2021-03-21 2021-10-27 inancial Specialist, MOH m Disaster Risk Preparednes ant Selection s SO-MOF-214331-CS-INDV / Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Limited 77,400.00 Signed 2021-03-01 2021-03-15 2021-03-06 2021-03-04 2021-03-27 2021-03-18 2021-05-01 2021-03-24 2021-10-28 MOH Communication Officer m Disaster Risk Preparednes ant Selection s SO-MOF-210968-CS-INDV / Component 5: Contingent Individual Consult MOH COVID-19 RESPONSE & IDA / D6300 Prior Limited 139,617.75 Signed 2021-03-31 2021-03-15 2021-04-05 2021-03-04 2021-04-26 2021-03-18 2021-05-31 2021-03-21 2021-11-27 Emergency Response ant Selection RECOVERY COORDINATOR SO-MOF-217509-CS-INDV / S Component 4: Project Manag Individual Consult IDA / D6300 Prior Direct 164,040.00 Signed 2021-04-30 2021-04-16 2021-05-10 2021-05-17 2021-05-31 2021-06-07 2021-07-05 2021-06-08 2022-01-01 CRP Operations Manager ement ant Selection SO-MOF-190538-CS-INDV / C Component 4: Project Manag Individual Consult IDA / D6300 Prior Limited 0.00 Canceled 2020-10-31 2020-10-05 2020-11-05 2020-11-26 2020-12-31 2021-06-29 ommunication Specialist ement ant Selection SO-MOF-229866-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open 0.00 2021-04-30 2021-05-21 2021-06-18 2021-07-09 2021-08-13 2022-02-09 IU Communications Specialist ement ant Selection ation SO-MOF-239607-CS-CDS / A GREEMENT FOR DELIVERY OF Component 4: Project Manag IDA / D6300 Prior Direct Selection Direct 0.00 Canceled 2021-07-01 2021-07-11 2021-09-14 2022-03-13 OUTPUTS WITH UNOPS: TECH ement NICAL STUDIES & DESIGN SO-MOF-188776-CS-UN-2 / P Component 2: Medium-Ter Under Implement rovision of Design and Super IDA / D6300 Prior Direct Selection Direct 0.00 2021-08-15 2021-08-25 2021-10-29 2022-04-27 m Flood Recovery ation vision of Flood and Irrigation System with FAO SO-MOF-256503-CS-INDV / E Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open 0.00 2021-10-20 2021-10-22 2021-12-08 2022-03-24 2021-12-29 2022-03-29 2022-02-02 2022-08-01 nvironmental Safeguard Spe ement ant Selection ation cialist SO-MOF-260028-CS-CDS / Pr ovision of Technical Studies a Component 4: Project Manag Under Implement IDA / D6300 Prior Direct Selection Direct 0.00 2021-11-05 2022-01-20 2021-11-15 2022-01-19 2022-07-18 nd Design Services as part of ement ation the Somalia Crisis Recovery Project SO-MOF-273757-CS-INDV / Component 4: Project Manag Individual Consult IDA / D6300 Prior Open 0.00 Signed 2022-02-28 2022-02-07 2022-04-18 2022-06-07 2022-05-09 2022-06-13 2022-06-13 2023-06-09 2022-12-10 Monitoring and Evaluation Sp ement ant Selection ecialist SO-MOF-277118-CS-CDS / Te Component 3: Longer-Ter chnical Advisor for National E Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 0.00 2022-03-31 2022-03-30 2022-04-10 2022-04-13 2022-06-14 2022-12-11 mergency Operation Centre ( ation s NEOC), Office of the Prime Mi nster SO-MOF-277127-CS-CDS / C Component 3: Longer-Ter ommunication Consultant, N IDA / D6300 m Disaster Risk Preparednes Prior Direct Selection Direct 0.00 Signed 2022-03-31 2022-03-30 2022-04-10 2022-04-13 2022-06-14 2022-12-11 ational Emergency Operation s Centre (NEOC) - Office of the Prime Minster Page 10 SO-MOF-276900-CS-CDS / C Component 5: Contingent Under Implement ERC Coordinator for Banadir IDA / D6300 Prior Direct Selection Direct 0.00 2022-03-31 2022-04-05 2022-04-10 2022-04-13 2022-06-14 2022-12-11 Emergency Response ation Regional Administration (BRA ) SO-MOF-276905-CS-CDS / C Component 5: Contingent Under Implement ERC Finance Specialist for Ba IDA / D6300 Prior Direct Selection Direct 0.00 2022-03-31 2022-04-05 2022-04-10 2022-04-13 2022-06-14 2022-12-11 Emergency Response ation ndir Regional Administration SO-MOF-307794-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Limited 0.00 2022-08-31 2022-08-25 2022-09-05 2022-12-06 2022-09-26 2023-02-22 2022-10-31 2023-04-29 roject Security Officer ement ant Selection ation SO-MOF-307795-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Open - National 0.00 2022-08-31 2022-08-25 2022-10-19 2023-02-25 2022-11-09 2023-05-11 2022-12-14 2023-06-12 roject Admin Officer ement ant Selection ation SO-MOF-307796-CS-INDV / E Component 4: Project Manag Individual Consult Under Implement nvironmental and Social Safe IDA / D6300 Prior Open - National 0.00 2022-08-31 2022-09-19 2022-10-19 2023-04-27 2022-11-09 2023-05-11 2022-12-14 2023-06-12 ement ant Selection ation guard Officer, Jubaland SPT SO-MOF-307798-CS-INDV / Component 4: Project Manag Individual Consult Under Implement Monitoring and evaluation off IDA / D6300 Prior Open - National 0.00 2022-08-31 2022-09-26 2022-10-19 2023-02-15 2022-11-09 2023-05-11 2022-12-14 2023-06-12 ement ant Selection ation icer, Jubaland SPT SO-MOF-316799-CS-CDS / C Component 4: Project Manag Under Implement ontract Management and Pro IDA / D6300 Prior Direct Selection Direct - National 0.00 2022-11-30 2022-10-12 2022-12-10 2022-10-22 2023-02-13 2023-08-12 ement ation curement Specialist, PIU SO-MOF-322581-CS-INDV / D Component 3: Longer-Ter rought Management Advisor Individual Consult Under Implement IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2022-10-31 2022-11-08 2022-11-05 2023-01-25 2022-11-26 2023-03-13 2022-12-31 2023-06-29 for the office of Somalia spec ant Selection ation s ial envoy for drought respons e SO-MOF-322582-CS-INDV / R esource Mobilization and Don Component 3: Longer-Ter Individual Consult Under Implement or Relations Advisor for the o IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2022-10-31 2022-11-08 2022-11-05 2023-01-25 2022-11-26 2023-03-07 2022-12-31 2023-06-29 ant Selection ation ffice of Somalia’s special env s oy for drought response SO-MOF-328720-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D8730 Prior Limited 0.00 2022-12-10 2022-12-14 2022-12-15 2023-03-01 2023-01-05 2023-06-14 2023-02-09 2023-08-08 rocurement officer, PIU ement ant Selection ation SO-MOF-328721-CS-INDV / F Component 4: Project Manag Individual Consult Under Implement IDA / D8730 Prior Limited 0.00 2022-12-10 2022-12-14 2022-12-15 2023-03-01 2023-01-05 2023-06-12 2023-02-09 2023-08-08 inance Officer, PIU ement ant Selection ation SO-MOF-333068-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / D8730 Prior Limited 0.00 2022-12-31 2023-01-17 2023-01-05 2023-01-26 2023-03-02 2023-08-29 IU Communication Officer ement ant Selection ation SO-MOF-333073-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D8730 Prior Open - National 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 nesthetics/Intensivist Consult m Disaster Risk Preparednes ant Selection ation ant s SO-MOF-333077-CS-INDV / B Component 3: Longer-Ter Individual Consult Under Implement lood Bank Technologist for R IDA / D8730 m Disaster Risk Preparednes Prior Open - National 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection ation egional Referral Hospitals s SO-MOF-333079-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement IDA / D8730 Prior Open - National 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 mergency Medicine Consulta m Disaster Risk Preparednes ant Selection ation nt s SO-MOF-333082-CS-INDV / Component 3: Longer-Ter Individual Consult Under Implement Medical Laboratory Consulta IDA / D8730 m Disaster Risk Preparednes Prior Open - National 0.00 2022-12-31 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection ation nt for Regional Referral Hospi s tals SO-MOF-331702-CS-INDV / C Component 4: Project Manag Individual Consult IDA / D8730 Post Limited 0.00 Canceled 2022-12-29 2023-01-03 2023-01-24 2023-02-28 2023-08-27 ommunication Officer, PIU ement ant Selection SO-MOF-333083-CS-INDV / I Component 3: Longer-Ter Individual Consult ntegration and Organizationa IDA / D8730 m Disaster Risk Preparednes Post Open - National 0.00 Canceled 2022-12-31 2023-02-13 2023-02-18 2023-03-11 2023-04-15 2023-10-12 ant Selection l Development Consultant for s NEOC/SODMA SO-MOF-344251-CS-INDV / F Component 4: Project Manag Individual Consult Under Implement IDA / D6300 Prior Direct - National 0.00 2023-02-25 2023-03-10 2023-03-07 2023-03-14 2023-03-28 2023-03-20 2023-05-02 2023-10-29 inancial Management Special ement ant Selection ation ist SO-MOF-344255-CS-INDV / I Component 3: Longer-Ter Individual Consult Under Implement ntegration and Organizationa IDA / D8730 m Disaster Risk Preparednes Prior Limited 0.00 2023-02-28 2023-04-10 2023-03-05 2023-03-26 2023-04-30 2023-10-27 ant Selection ation l Consultant for NEOC/SODM s A SO-MOF-350971-CS-CDS / C ONSULTING SERVICES TO SU Component 4: Project Manag Direct - Internation IDA / D6300 Prior Direct Selection 0.00 Under Review 2023-04-30 2023-06-08 2023-05-10 2023-06-17 2023-07-14 2024-01-10 PPORT THE SCRP PROJECT WI ement al TH SECURITY RISK MANAGEM ENT SO-MOF-357102-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-11 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Banadir Hospital, Benadi s r Region SO-MOF-357104-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-11 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Martini Hospital, Benadir s Region SO-MOF-357112-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-17 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Hirshabelle State of Som s alia SO-MOF-357113-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt – Jubbaland State of Somal s ia SO-MOF-357115-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-05-31 2023-05-17 2023-06-05 2023-06-26 2023-07-31 2024-01-27 ant Selection ation nt – Government of Somalila s nd SO-MOF-357116-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt – Galmudug State of Soma s lia SO-MOF-357117-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-05-17 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation nt - Southwest State of Soma s lia Page 11 SO-MOF-357119-CS-INDV / E Component 3: Longer-Ter Individual Consult Under Implement mergency Medicine Consulta IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-07-31 2023-05-17 2023-08-05 2023-08-26 2023-09-30 2024-03-28 ant Selection ation nt – Puntland State of Somali s a SO-MOF-328359-CS-INDV / S Component 3: Longer-Ter Individual Consult enior Health Emergency Prep IDA / D8730 m Disaster Risk Preparednes Post Direct - National 0.00 Canceled 2022-12-10 2023-01-17 2022-12-20 2023-01-10 2023-02-14 2023-08-13 ant Selection aredness & Response Adviso s r SO-MOF-357121-CS-INDV / S Component 3: Longer-Ter Individual Consult Under Implement enior Health emergency prep IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2023-06-30 2023-05-15 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ant Selection ation aredness and Response Advi s sor SO-MOF-357128-CS-INDV / S Component 3: Longer-Ter enior Medical Technical Advis Individual Consult IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 Under Review 2023-05-31 2023-05-15 2023-07-19 2023-08-09 2023-09-13 2024-03-11 or for the Ministry of Health ant Selection s & Human Services SO-MOF-362318-CS-INDV / V Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Limited 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ector Control Advisor m Disaster Risk Preparednes ant Selection ation s SO-MOF-362320-CS-INDV / A Component 3: Longer-Ter Individual Consult Under Implement IDA / D6300 Prior Limited 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 nimal Health Advisor m Disaster Risk Preparednes ant Selection ation s SO-MOF-362323-CS-INDV / F Component 3: Longer-Ter Individual Consult Under Implement ield Coordinator, Vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation ol for Southwest State s SO-MOF-362418-CS-INDV / F Component 3: Longer-Ter Individual Consult Under Implement ield Coordinator, vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-06-30 2023-07-05 2023-07-26 2023-08-30 2024-02-26 ant Selection ation ol in Jubaland State s SO-MOF-362421-CS-INDV / F Component 3: Longer-Ter Individual Consult Under Implement ield Coordinator, vector contr IDA / D6300 m Disaster Risk Preparednes Prior Limited 0.00 2023-07-31 2023-08-05 2023-08-26 2023-09-30 2024-03-28 ant Selection ation ol in Hirshabelle State s SO-MOF-362428-CS-INDV / C Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 apacity building specialist, N m Disaster Risk Preparednes ant Selection EOC s SO-MOF-362432-CS-INDV / I Component 3: Longer-Ter Individual Consult nformation management spe IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ant Selection cialist, NEOC s SO-MOF-362434-CS-INDV / N Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 EOC Coordinator m Disaster Risk Preparednes ant Selection s SO-MOF-362438-CS-INDV / N Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 EOC Deputy Coordinator m Disaster Risk Preparednes ant Selection s SO-MOF-362440-CS-INDV / D Component 3: Longer-Ter Individual Consult Pending Impleme isaster Risk Management (DR IDA / D6300 m Disaster Risk Preparednes Prior Open - National 0.00 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ant Selection ntation M) specialist s SO-MOF-366795-CS-INDV / O Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 perations Manager, NEOC m Disaster Risk Preparednes ant Selection s SO-MOF-366797-CS-INDV / P Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 olicy & Planning Advisor, NE m Disaster Risk Preparednes ant Selection OC s SO-MOF-366804-CS-INDV / P Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 rocurement & Logistics Office m Disaster Risk Preparednes ant Selection r, NEOC s SO-MOF-366805-CS-INDV / Li Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-21 2023-08-09 2023-08-30 2023-10-04 2024-04-01 aison Officer, NEOC m Disaster Risk Preparednes ant Selection s SO-MOF-366806-CS-INDV / P Component 3: Longer-Ter Individual Consult IDA / D6300 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 lanning Officer, NEOC m Disaster Risk Preparednes ant Selection s SO-MOF-366808-CS-INDV / E Component 4: Project Manag Individual Consult nvironmental & Safeguard Sp IDA / D8730 Prior Open - National 0.00 Under Review 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 ement ant Selection ecialist, PIU Page 12 REPUBLIQUE DE CENTRAFRIQUE Projet d’Amélioration des Services d’Eau et d’Electricité (PASEEL) P162245 « Numéro du crédit ou du Don » PLAN SIMPLIFIE DE PASSATION DES MARCHES (VERSION 15 JUILLET 2017) Information sur le Projet : République Centrafricaine - Projet Eau & Energie – P162245 Agence d’exécution du Projet : Sous – traitant Coordination du Projet Transit et Transit en zone CEMAC Date du plan de passation des marchés : 16 Mai 2017 Période couverte par ce plan de passation des marchés : Juin 2017 à Mai 2018 I. PRÉAMBULE Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Page 1 of 11 Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées par la Loi n°08.017 portant Code des Marchés Publics et Délégations de Service Publics en République Centrafricaine, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés : « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés : « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés. Travaux ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés. Autres informations pertinentes sur la passation des marchés Indiquer toute autre information pertinente relative aux procédures de passation, telle que par exemple l’utilisation de procédures de participation communautaire au développement (CDD), de l’utilisation de procédures pour un besoin urgent d’assistance ou de faible capacité, etc. Page 2 of 11 II. TRAVAUX, FOURNITURES ET SERVICES NON INTELLECTUELS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis au contrôle de la passation des marchés, tel que prévu dans l’annexe II du "Règlement de Passation des pour les Emprunteurs sollicitant de la Banque mondiale le Financement de Projets d’Investissement (FPI)’’. Méthodes de Seuils de Examen par la Catégorie passation Option de marchés revue en Banque des marchés USD ≥ Tous les contrats Appel Internationale 5.000.000 d’Offres < Le premier Nationale Travaux 5.000.000 contrat Demande de Aucun Internationale/Nati cotations <200.000 onale (DC) ≥ Tous les contrats Fournitures Appel Internationale 500.000 et services d’Offres < Le premier autres que Nationale 500.000 contrat services de Demande de Internationale/Nati Aucun consultant <100.000 cotations onale 2. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : TRAVAUX (US$ équivalent) FOURNITURES (US$ équivalent) Demande Demande Appel d’offres de Appel d’offres de Cotations Cotations Internatio National International/Na Internatio National International/Nat nal tional nal ional < ≥ ≥ <500.00 5.000.00 < 200,000 < 100,000 5,000.000 500.000 0 0 3. Référence (s’il y en a) au Manuel d’exécution du projet/Manuel de Passation des Marchés : Manuel des Procédures Administrative, Financière et Comptable. 4. Autres arrangements spécifiques pour la passation des marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur de USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers) ; Page 3 of 11 5. Autres modalités nationales de passation des marchés : En conformité avec le paragraphe 5.5 du "Règlement de Passation des pour les Emprunteurs sollicitant de la Banque mondiale le Financement de Projets d’Investissement (FPI)’’, les autres modalités nationales de passation des marchés (autres que sous forme d’appel d’offres/a propositions national ouvert) qui pourraient être appliquées par l’Emprunteur (appel d’offres limite/restreint, demande de prix/consultation des fournisseurs, entente directe) doivent être conformes avec les Principes Fondamentaux de passation des marchés de la Banque et garantir que les Directives de lutte contre la corruption, son cadre de sanctions et les recours contractuels vises dans l’Accord Juridique s’appliquent. Page 4 of 11 6. Liste des marchés avec les méthodes de passation et les dates de mise en œuvre Fournitures, Travaux et Services autres que services de consultants 1 2 3 4 5 6 7 8 9 Date Pré Revue de Comment Ré Méthode Préférenc prévue Coût qualific la Banque aires / Fin f. passatio e de Description estimatif ation (à priori / de No n des nationale l’ouvertu (US$) (oui/no à prestation . marchés (oui/non) re des n) posteriori) s offres Acquisition du matériel informatique pour assistant comptable, assistant en passation des A 1 50,000 DC NON NON 31/10/17 marchés, expert suivi- posteriori évaluation, expert technique, et expert environnemental et social Frais de fonctionnement et de 2 logistique jusqu’à la 50,000 DC NON NON A posteriori 31/10/17 mise en œuvre du Projet Page 5 of 11 Coût total en US$ 100,000 Page 6 of 11 III. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujet au contrôle de la passation des marchés, tel que prévu dans l’annexe II du "Règlement de Passation des pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)’’. Seuils Méthodes de de Examen par Catégorie sélection revue la Banque en USD SFQC ; SFQ ; ≥ Tous les Services de SBCD ; SMC ; CQ 200.000 contrats Consultant (firmes) ≥ Tous les SED 100.000 contrats ≥ Tous les SED Consultants 100.000 contrats Individuels Comparaison de ≥ Tous les CVs) 200.000 contrats 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 200,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux selon les dispositions du paragraphe 7.25 du "Règlement de Passation des pour les Emprunteurs sollicitant de la Banque mondiale le Financement de Projets d’Investissement (FPI)’’. 3. Autres arrangements spécifiques pour la Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels prévus au paragraphe 7.12 du "Règlement de Passation des pour les Emprunteurs sollicitant de la Banque mondiale le Financement de Projets d’Investissement (FPI) ". Page 7 of 11 4. Liste des Consultations, avec les méthodes de sélection et le calendrier de mise œuvre 1 2 3 4 5 6 7 Revue Date de la Coût Méthod prévue de Ref Banque Commentaires/ estimatif e de soumissio . Description des Missions (à priori Fin de ($EU) 1$ = sélectio n des No. /à prestations 600 FCFA n propositio posterio ns ri) Etude détaillée des travaux hydrauliques devant être 1 250,000 QC A priori 15/10/17 réalisées à Bangui et Berberati (SODECA) + contrôle des travaux Audit énergétique des A 2 infrastructures hydrauliques de la 50,000 CI 31/10/17 posteriori SODECA Le bureau d’études CONCEPT SA a été recruté par le Ministère dans le cadre du projet BADEA pour réaliser Etudes APS, APD et DAO pour les les études à travaux hydrauliques à réaliser 3 200,000 ED A priori 31/10/17 Bambari. Il est dans Bambari + contrôle des proposé de faire un travaux avenant au contrat de ce BE qui intervient déjà à Bambari pour un projet complémentaire. Page 8 of 11 1 2 3 4 5 6 7 Revue Date de la Coût Méthod prévue de Ref Banque Commentaires/ estimatif e de soumissio . Description des Missions (à priori Fin de ($EU) 1$ = sélectio n des No. /à prestations 600 FCFA n propositio posterio ns ri) Réalisation d’un Plan de Sécurité A 4 60,000 CI 15/10/17 du barrage de Boali posteriori Réalisation du Manuel A 5 30,000 CI 15/10/17 d’exécution du projet posteriori Réalisation des Etudes d’Impact Environnementales et Sociales (EIES), y compris les Plans de A 6 150,000 QC 31/10/17 Gestion Environnemental et posteriori Social (PGES), et les PARs – Eau et Energie, à Bambari Réalisation des Etudes d’Impact Environnementales et Sociales (EIES), y compris les Plans de A 7 130,000 QC 31/10/17 Gestion Environnemental et posteriori Social (PGES), et les PARs – Eau et Energie, à Berberati Réalisation des Etudes d’Impact Environnementales et Sociales (EIES), y compris les Plans de 8 210,000 QC A priori 31/10/17 Gestion Environnemental et Social (PGES), et les PARs – Eau et Energie à Bangui Page 9 of 11 1 2 3 4 5 6 7 Revue Date de la Coût Méthod prévue de Ref Banque Commentaires/ estimatif e de soumissio . Description des Missions (à priori Fin de ($EU) 1$ = sélectio n des No. /à prestations 600 FCFA n propositio posterio ns ri) Diagnostic opérationnel et APS des installations de génération et distribution de l’ENERCA dans six 9 230,000 QC A priori 15/11/17 villes secondaires (Berberati, Ndélé, Bria, Kaga-Bandoro, Bangassou et Sibut) Diagnostic opérationnel, APS + A 10 niveau APD/DAO et contrôle des 100,000 QC 31/10/17 posteriori travaux à Bambari, volet énergie Diagnostic opérationnel/Etat des A 11 lieux des installations de 100,000 CI 30/10/17 posteriori distribution de l’ENERCA à Bangui A 12 Elaboration du PPSD 30,000 CI 15/10/17 posteriori A 13 Audit financier du PPSD 20,000 QC 31/01/18 posteriori Recrutement d’un Assistant 14 20,000 CI A priori 15/10/17 comptable Assistant en passation des 15 20,000 CI A priori 15/10/17 marchés 16 Expert en suivi-évaluation 20,000 CI A priori 15/10/17 17 Expert environnement 20,000 CI A priori 15/10/17 Page 10 of 11 1 2 3 4 5 6 7 Revue Date de la Coût Méthod prévue de Ref Banque Commentaires/ estimatif e de soumissio . Description des Missions (à priori Fin de ($EU) 1$ = sélectio n des No. /à prestations 600 FCFA n propositio posterio ns ri) 18 Expert en développement Social 20,000 CI A priori 15/10/17 19 Expert technique énergie 20,000 CI A priori 15/10/17 20 Expert technique eau 20,000 CI A priori 15/10/17 Coût total en US$ 1,700,000 Lexique des Sigles et Abréviations AO : Appel d’Offres Ouvert SMC : Sélection au Moindre Coût DC : Demande de Cotations CI : Consultant Individuel SFQC : Sélection Fondée sur la Qualité et le Coût A posteriori : Revue à posteriori SFQ : Sélection Fondée sur la Qualité A Priori : Revue à priori QC : Sélection fondée sur les Qualifications des PPM : Plan de Passation des Marchés Consultants SED : Sélection par Entente Directe Page 11 of 11 PROCUREMENT Central African Republic : Water and Electricity Upgrading Project PLAN General Information Country: Central African Republic 2017-11-10 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162245 GPN Date: Project Name: Water and Electricity Upgrading Project Loan / Credit No: IDA / D2690, / , IDA / V1340 Water and Electricity Upgrading Project Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PASEEL/045/CW/RFB/19 / Be rberati AEP-Travaux de réhab Single Stage - One E 1,703,778.0 2020-05-1 ilitation des infrastructures d IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National Signed 2019-07-25 2019-10-23 2019-07-30 2019-10-23 2019-09-10 2019-11-22 2019-10-10 2020-03-02 2019-11-14 2020-06-08 nvelope 9 2 es infrastructures d'alimenta tion en eau dans la ville de B erberati PASEEL/053/CW/RFB/19 / Ea u Bangui-Travaux de réhabili Single Stage - One E 2020-08-3 IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National 0.00 Canceled 2019-11-13 2019-11-18 2019-12-30 2020-01-29 2020-03-04 tation des infrastructures d'al nvelope 1 imentation en eau potable de la ville de Bangui. PASEEL/056/CW/RFB/19 / Re bobinage-Travaux de rebobin Single Stage - One E 1,343,699.6 2020-09-0 IDA / D2690 Energy Infrastructure Post Request for Bids Open - National Signed 2019-11-18 2019-12-19 2019-11-23 2020-01-04 2020-03-05 2020-02-03 2020-03-06 2020-03-09 2020-10-24 age des alternateurs des Gro nvelope 9 5 upes G2, G3, G4 et G5 de Bo ali 1 PASEEL/052/CW/RFB / Eau B ambari-Travaux de réhabilita Single Stage - One E 2,028,639.2 2020-09-0 IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National Signed 2019-11-22 2020-01-15 2019-11-27 2020-01-08 2020-02-17 2020-02-07 2020-03-25 2020-03-13 2020-08-30 tion des infrastructures d'ali nvelope 3 9 mentation en eau potable de la ville de Bambari PASEEL/054/CW/RFB/19 / En ergie de 2 villes-Travaux de r Single Stage - One E 1,939,143.7 2020-09-2 éhabilitation et d'amélioratio IDA / D2690 Energy Infrastructure Prior Request for Bids Open - National Signed 2019-12-03 2020-01-22 2019-12-08 2020-02-06 2020-01-19 2020-04-03 2020-02-18 2020-06-15 2020-03-24 2020-08-27 nvelope 5 0 n de l'alimentation en électri cité dans les villes de Bamba ri et Berberati PASEEL/065/CW/RFB/20 / Ce ntrales hybrides-Construction Open - Internationa Single Stage - One E 2,365,433.3 2021-05-0 des ouvrages de production IDA / D2690 Energy Infrastructure Post Request for Bids Signed 2020-07-15 2020-07-13 2020-07-20 2020-07-24 2020-08-31 2020-09-18 2020-09-30 2020-10-26 2020-11-04 2021-04-11 l nvelope 5 3 de centrales hybrides (solaire PV-Diesel) dans les villes de Bambari et Berberati. PASEEL/078/CW/RFQ/21 / Dé Other (with fi molition Bambari-Travaux de Technical Support to Water Request for Quota Single Stage - One E 2022-05-1 2021-10 IDA / D2690 Post Limited eld for expla 5,691.55 Completed 2021-09-25 2021-09-02 2021-11-20 2021-10-07 démolition et de nettoyage d and Energy Sectors tions nvelope 9 -17 nation) u site de l'ENERCA à Bambari . PASEEL/079/CW/RFQ/21 / Dé Other (with fi molition Berberati-Travaux d Technical Support to Water Request for Quota Single Stage - One E 2022-05-1 2021-11 IDA / D2690 Post Limited eld for expla 19,878.23 Completed 2021-09-21 2021-09-02 2021-11-16 2021-10-08 e démolition, abattage d'arbr and Energy Sectors tions nvelope 5 -05 nation) es et nettoyage du site de l'E NERCA à Berberati. Request for PASEEL/0097/CW/DIR/23 / R Quotations - éalisation de forages-Travau Technical Support to Water Small Works Under Imple 2023-11-2 x de réalisation et d'équipem IDA / D2690 Post Direct Selection Direct - National 0.00 2023-04-18 2023-05-09 2023-04-23 2023-05-10 2023-05-28 and Energy Sectors (Emergency) mentation 4 ents de 2 forages y compris SPD -Non Co un forage témoin à Berberati. mpetitive PASEEL/097/CW/RFQ/22 / Ré alisation de forages-Travaux Other (with fi Technical Support to Water Request for Quota Single Stage - One E 2023-06-0 de réalisation et d'équipeme IDA / D2690 Post Limited eld for expla 0.00 Canceled 2022-10-10 2022-12-05 and Energy Sectors tions nvelope 3 nts de 2 forages y compris u nation) n forage témoin à Berberati. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CF- PASEEL-38235-GO-RFQ / Acquisition du matériel infor matique pour les experts (Pa Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Limited 30,074.23 Completed 2017-12-31 2018-06-29 2018-02-25 2019-03-23 2018-08-24 2019-04-30 ssation des Marchés, Compta and Energy Sectors tions nvelope ble, Suivi-évaluation et exper t environnemental et social) PASEEL-20-IND-18 / Acquisiti on des moyens roulants - Ac Technical Support to Water Request for Quota Single Stage - One E hat des véhicules (2 double c IDA / D2690 Post Limited 190,572.56 Completed 2018-04-30 2018-04-20 2018-06-25 2018-05-29 2018-12-22 2018-07-24 and Energy Sectors tions nvelope abine, une berline) et 10 mot os pour la supervision des a ctivités du Projet PASEEL/O21/FOUR/DC/18 / C Request for Quota Single Stage - One E arburant-Acquisition de carb IDA / D2690 Water Supply Infrastructure Post Limited 101,955.32 Completed 2018-08-20 2019-07-15 2018-10-15 2019-03-16 2019-04-13 2020-11-21 tions nvelope urant pour la SODECA PASEEL/O23/FOUR/AOI/18 / Branchements sociaux-Acqui Open - Internationa Single Stage - One E IDA / D2690 Water Supply Infrastructure Post Request for Bids 1,180,710.11 Completed 2018-12-07 2020-02-03 2018-12-12 2019-01-23 2019-03-21 2019-02-22 2019-05-16 2019-03-29 2020-07-28 2019-09-25 2021-07-02 sition d'équipements d'exten l nvelope sion et de branchements soci aux pour la SODECA. PASEEL/22/FOUR/DC/18 / Pro duits chimiques-Acquisition d Request for Quota Single Stage - One E IDA / D2690 Water Supply Infrastructure Post Open - National 0.00 Canceled 2019-01-19 2019-03-16 2019-09-12 e consommables (produits ch tions nvelope imiques) pour la SODECA PASEEL/033/FOUR/CF/18 / D étection fuite-Acquisition d'é Request for Quota Single Stage - One E IDA / D2690 Water Supply Infrastructure Post Limited 23,148.34 Completed 2019-02-04 2021-04-01 2019-04-01 2021-10-12 2019-09-28 2022-07-20 quipements de détection de f tions nvelope uite sur le réseau de distribut ion de la SODECA Page 1 PASEEL/O22/FOUR/AON/18 / Single Stage - One E Produits chimiques-Acquisitio IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National 0.00 Canceled 2018-11-29 2018-12-04 2019-01-15 2019-02-14 2019-03-21 2019-09-17 nvelope n de consommables pour la S ODECA PASEEL/035/FOUR/DC/18 / El Request for Quota Single Stage - One E ectropompes - Fourniture d'é IDA / D2690 Water Supply Infrastructure Post Limited 0.00 Canceled 2019-01-12 2019-03-09 2019-09-05 tions nvelope lectropompes à la SODECA PASEEL/038/FOUR/DIR/19 / E lectropompes de captage: Fo Contingent Emergency Resp IDA / D2690 Post Direct Selection Direct 473,708.04 Signed 2019-05-16 2019-09-07 2019-05-21 2019-09-07 2019-06-25 2019-07-16 2019-12-22 urniture d'électropompes de onse captage d'eau brute à la SOD ECA PASEEL/040/FOUR/DIR/19 / E lectropompes de refoulement Contingent Emergency Resp - Fourniture et installation d' IDA / D2690 Post Direct Selection Direct 203,227.14 Signed 2019-05-16 2019-11-19 2019-05-21 2019-11-25 2019-06-25 2019-10-18 2019-12-22 onse électropompes de refouleme nt d'eau vers les réservoirs R 2, R3 et R4 à la SODECA. PASEEL/022/FOUR/RFB/19 / Single Stage - One E Produits chimiques - Fournitu IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National 201,207.87 Completed 2019-05-27 2019-07-25 2019-06-01 2019-07-13 2019-09-03 2019-08-12 2020-02-27 2019-09-16 2019-10-20 2020-03-14 2020-01-20 nvelope re de produits chimiques à la SODECA PASEEL/19/GO/RFB/19 / Bloc Single Stage - One E de réserve-Acquisition de Tra IDA / D2690 Energy Infrastructure Post Request for Bids Open - National 85,523.75 Completed 2019-11-05 2019-11-21 2019-11-10 2019-12-16 2019-12-22 2019-12-20 2020-01-21 2020-01-03 2020-02-25 2020-04-09 2020-08-23 2020-10-23 nvelope nsformateurs de Puissance PASEEL/055/GO/RFQ/19 / Tra Request for Quota Open - Internationa Single Stage - One E nsformateur-Acquisition de tr IDA / D2690 Energy Infrastructure Post 0.00 Canceled 2019-11-05 2019-12-31 2020-06-28 tions l nvelope ansformateurs de courant. PASEEL/057/GO/RFQ/19 / Pet its outillages-Acquisition de p Request for Quota Single Stage - One E Under Imple IDA / D2690 Water Supply Infrastructure Post Limited 0.00 2019-11-18 2019-11-20 2020-01-13 2020-07-11 etits outillages pour les instal tions nvelope mentation lations des électropompes fo urnies à la SODECA. PASEEL/058/GO/DIR/19 / Mat ériels informatiques-Acquisiti Technical Support to Water on de matériels informatique IDA / D2690 Post Direct Selection Direct 43,017.59 Completed 2019-10-31 2021-01-20 2019-11-05 2021-04-06 2019-12-10 2021-05-06 2020-06-07 2021-06-01 and Energy Sectors s pour certains cadres Minist ériels acteurs du Projet PASSEEL/049/GO/RFB/19 / C ompteurs-Acquisition de com pteurs à prépaiement et com Open - Internationa Single Stage - One E IDA / D2690 Energy Infrastructure Prior Request for Bids 872,468.94 Completed 2019-11-26 2020-01-06 2019-12-01 2020-01-16 2020-01-12 2020-03-31 2020-02-11 2020-05-15 2020-03-17 2020-06-13 2020-09-13 2021-12-05 municants pour l'amélioratio l nvelope n des performances commer ciales de l'ENERCA à BANGUI PASEEL/50/GO/RFB/19 / Rem Single Stage - One E placement cellules-Acquisitio IDA / D2690 Energy Infrastructure Prior Request for Bids Open - National 318,725.00 Completed 2019-11-29 2019-12-27 2019-12-04 2020-04-22 2020-01-15 2020-03-06 2020-02-14 2020-04-27 2020-03-20 2020-07-10 2020-09-16 2021-05-15 nvelope n des équipements de postes HTA/BT PASEEL/059/GO/RFQ/19 / Elé ments armoires-Fournitures Request for Quota Single Stage - One E Under Imple des éléments d'armoires de c IDA / D2690 Water Supply Infrastructure Post Limited 0.00 2020-01-04 2020-02-20 2020-02-29 2020-08-27 tions nvelope mentation ommande des électropompe s de refoulement d'eau. PASEEL/067/GO/DIR/21 / Acq uisition du logiciel de gestion Technical Support to Water IDA / D2690 Post Direct Selection Direct 17,742.81 Signed 2021-02-01 2021-04-27 2021-02-06 2021-04-30 2021-03-13 2021-06-26 2021-09-09 financière TOM2PRO et la for and Energy Sectors mation des utilisateurs. PASEEL/71/GO/DIR/21 / Carb urant ENERCA-Acquisition de Technical Support to Water IDA / D2690 Post Direct Selection Direct 0.00 Canceled 2021-04-30 2021-05-05 2021-06-09 2021-12-06 carburant et mise à dispositi and Energy Sectors on de l'ENERCA et certains H ôpitaux PASEEL/072/GO/RFQ/21 / Ma tériels branchements-Acquisi Request for Quota Single Stage - One E tion de matériels informatiqu IDA / D2690 Water Supply Infrastructure Post Limited 7,637.28 Completed 2021-06-01 2021-06-01 2021-07-27 2021-08-18 2022-01-23 2021-09-08 tions nvelope es et équipements de collect e pour la mise en œuvre des branchements sociaux. PASEEL/074/GO/RFQ/21 / Eq uipements branchements-Ac Request for Quota Single Stage - One E quisition d'outillage et d'équi IDA / D2690 Water Supply Infrastructure Post Limited 7,852.30 Completed 2021-05-31 2021-05-31 2021-07-26 2021-08-18 2022-01-22 2021-08-28 tions nvelope pements de chantier pour la mise en œuvre des branche ments sociaux PASEEL/075/GO/RFB/21 / Vé hicules branchements sociau Single Stage - One E x-Acquisitions de matériels r IDA / D2690 Water Supply Infrastructure Post Request for Bids Open - National 98,006.81 Completed 2021-05-31 2021-06-03 2021-06-05 2021-06-17 2021-07-17 2021-07-21 2021-08-16 2021-07-23 2021-09-20 2021-09-01 2022-03-19 2021-10-15 nvelope oulants pour la mise en œuvr e des branchements sociaux. PASEEL/077/GO/RFB/21 / Tra Single Stage - One E nsfo Courant-Acquisition de t IDA / D2690 Energy Infrastructure Post Request for Bids Open - National 140,919.92 Signed 2021-09-21 2021-09-20 2021-09-26 2021-09-23 2021-11-07 2021-10-26 2021-12-07 2021-11-24 2022-01-11 2022-02-08 2022-07-10 nvelope ransformateurs de courant à l'ENERCA. PASEEL/082/GO/RFQ/21 / Br anchements sociaux-Acquisit Request for Quota Single Stage - One E IDA / D2690 Water Supply Infrastructure Post Limited 12,815.41 Completed 2021-10-16 2021-10-11 2021-12-11 2021-11-25 2022-06-09 2021-12-22 ion de supports de communic tions nvelope ation pour les activités de br anchements sociaux. PASEEL/085/RFQ/21 / Fournit Technical Support to Water Request for Quota Single Stage - One E ure bureau-Acquisition de fou IDA / D2690 Post Limited 8,726.29 Completed 2021-10-17 2022-01-25 2021-12-12 2022-03-22 2022-06-10 2022-04-30 and Energy Sectors tions nvelope rnitures de bureaux PASEE/086/GO/RFQ/21 / Bra nchements électriques-Achat Technical Support to Water Request for Quota Single Stage - One E de matériels de branchement IDA / V1340 Post Limited 67,212.76 Completed 2021-12-22 2021-12-22 2022-02-16 2022-03-22 2022-08-15 2022-06-23 and Energy Sectors tions nvelope s électriques à Bambari et Be rberati par l'ENERCA. PASEEL/080/GO/RFB/21 / Gr oupe 1250 KVA-Acquisition e Technical Support to Water Single Stage - One E t installation d'un groupe éle IDA / D2690 Post Request for Bids Open - National 0.00 Canceled 2021-09-20 2021-09-17 2021-09-25 2021-09-21 2021-11-06 2021-11-18 2021-12-06 2022-01-10 2022-07-09 and Energy Sectors nvelope ctrogène de 1250 KVA à la st ation de traitement de la SO DECA à Bangui. Page 2 PASEEL/087/GO/CDS/21 / GA LATE-Mise à jour du logiciel d Technical Support to Water IDA / V1340 Post Direct Selection Direct 0.00 Signed 2021-12-27 2021-12-22 2022-01-01 2023-03-16 2022-02-05 2022-08-04 e gestion (GALATE) de la clie and Energy Sectors ntèle de la SODECA. PASEEL/088/GO/RFQ/21 / Gr Technical Support to Water Single Stage - One E oupe 650 kva-Achat d'un gro IDA / V1340 Post Request for Bids Open - National 109,580.00 Signed 2021-12-27 2021-12-21 2022-01-01 2021-12-23 2022-02-12 2022-01-28 2022-03-14 2022-02-07 2022-04-18 2022-03-22 2022-10-15 and Energy Sectors nvelope upe électrogène de 650 KVA à la SODECA. PASEEL/092/GO/DIR/22 / Gro upe SODECA-Acquisition d'un Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 48,771.52 Completed 2022-07-14 2022-07-19 2022-07-19 2022-07-19 2022-08-23 2022-07-20 2023-02-19 2022-07-27 groupe électrogène de 100 K and Energy Sectors VA à la SODECA, Agence de BERBERATI PASEEL/091/GO/RFQ/22 / Ac quisition de matériels et équi Technical Support to Water Single Stage - One E pements pour la mise en plac IDA / D2690 Post Request for Bids Open - National 0.00 Canceled 2022-03-14 2022-03-21 2022-03-19 2022-03-22 2022-04-30 2022-05-30 2022-07-04 2022-12-31 and Energy Sectors nvelope e du Système d'Information Géographique (SIG) de la SO DECA. PASEEL/093/GO/RFQ/22 / Ma tériels SIG-Acquisition de mat Technical Support to Water Single Stage - One E Under Imple ériels et équipements pour la IDA / D2690 Post Request for Bids Open - National 0.00 2022-09-27 2022-09-27 2022-10-02 2022-10-11 2022-11-13 2022-12-13 2023-01-17 2023-07-16 and Energy Sectors nvelope mentation mise en place du Système d'I nformation Géographique (SI G) de la SODECA. PASEEL/090/GO/RFQ/22 / Ac quisition de matériels et équi Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Open - National 0.00 Signed 2022-03-12 2022-05-07 2022-11-03 pements pour la mise à jour and Energy Sectors tions nvelope du progiciel GALATE de la SO DECA. PASEEL/098/GO/RFQ/22 / Co mpteurs eau-Acquisition de 5 Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Limited 0.00 Canceled 2022-10-08 2022-12-03 2023-06-01 00 compteurs d'eau en maté and Energy Sectors tions nvelope riau plastic pour la SODECA. PASEEL/099/GO/DIR/22 / Tub es Galva-Acquisition de 600 t Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 0.00 Completed 2022-09-26 2022-10-10 2022-10-01 2022-10-18 2022-11-05 2023-05-04 2022-12-31 ubes Galva de 6 mètres linéa and Energy Sectors ires y compris les coudes. PASEEL/095/GO/CDS/22 / Vé hicules distribution-Acquisitio n de matériels roulants pour l Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 0.00 Signed 2022-10-17 2022-10-10 2022-10-23 2022-10-21 2022-11-27 2023-05-26 a mise en œuvre de la distrib and Energy Sectors ution d'électricité dans les vil les de Bambari et Berberati PASEEL/100/GO/RFQ/22 / Div ers outillages-Acquisition de Technical Support to Water Request for Quota Single Stage - One E divers outillages pour les acti IDA / D2690 Post Limited 0.00 Completed 2022-12-03 2022-12-06 2023-01-28 2023-07-27 2023-01-16 and Energy Sectors tions nvelope vités de branchements socia ux de la SODECA à Bambari et Berberati. PASEEL/0101/GO/RFQ/22 / M atériels informatiques-Acquis ition de matériels et équipem Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Limited 0.00 Canceled 2022-12-04 2023-01-29 2023-07-28 ents informatiques pour les a and Energy Sectors tions nvelope ctivités de branchements soc iaux de la SODECA à Bambari et Berberati. PASEEL/102/GO/RFQ/22 / Co mpteurs eau-Acquisition de 2 Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Limited 0.00 Completed 2022-12-05 2022-12-07 2023-01-30 2023-07-29 2023-02-05 500 compteurs d'eau en mat and Energy Sectors tions nvelope ériau plastic pour la SODECA PASEEL/104/GO/DIR/22 / Mat ériels roulants - Acquisition d e 2 véhicules pour les branch IDA / D2690 Water Supply Infrastructure Post Direct Selection Direct - National 0.00 Signed 2022-12-15 2022-12-13 2022-12-20 2022-12-13 2023-01-24 2023-07-23 ements sociaux et 2 motos p our appuyer les service régio naux Eau-Energie à Bambari et Berberati. PASEEL/105/GO/RFQ/22 / Sor ties HTA - Acquisition de mat ériels pour la reprise des sort Request for Quota Single Stage - One E ies HTA des départs du résea IDA / D2690 Energy Infrastructure Post Open - National 0.00 Signed 2022-12-21 2023-02-15 2023-08-14 tions nvelope u de Berberati et lampadaire s solaires pour l'éclairage de sécurité au pourtour des cha mps solaires à Bambari et Be rberati PASEEL/107/GO/RFQ/22 / Ac quisition ordinateurs - Acquis ition de 8 ordinateurs et 4 im Technical Support to Water Request for Quota Single Stage - One E IDA / D2690 Post Open - National 0.00 Signed 2022-12-17 2023-02-11 2023-08-10 primantes pour appuyer les d and Energy Sectors tions nvelope irections régionales Eau/Ener gie de Bambari et Berberati p our les collectes de données PASEEL/103/GO/RFQ/22 / Ré paration conduite - Acquisitio Single Stage - One E n des matériels pour la répar IDA / D2690 Water Supply Infrastructure Post Request for Bids Limited 0.00 Signed 2022-12-19 2022-12-26 2022-12-24 2023-01-06 2023-02-04 2023-02-06 2023-03-06 2023-02-16 2023-04-10 2023-10-07 nvelope ation des conduites de distrib ution d'eau à Bambari. PASEEL/106/GO/RFQ/22 / Ma tériels branchements - Acqui Single Stage - One E sition de complément de mat IDA / D2690 Energy Infrastructure Post Request for Bids Limited 0.00 Signed 2022-12-19 2022-12-26 2022-12-24 2023-01-06 2023-02-04 2023-02-06 2023-03-06 2023-02-16 2023-04-10 2023-10-07 nvelope ériels de branchements pour Bangui, Bambari et Berberati . PASEEL/0108/GO/DIR/22 / Ac quisition et pose de matériels et équipements de plomberie Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 0.00 Signed 2022-12-19 2022-12-14 2022-12-24 2022-12-14 2023-01-28 2023-07-27 pour le renforcement du syst and Energy Sectors ème d'alimentation en eau d es sanitaires des locaux de l' UGP. PASEEL/101/GO/DIR/22 / Mat ériels informatiques - Acquisi tion de matériels et équipem Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 0.00 Completed 2022-12-26 2022-12-26 2022-12-31 2022-12-26 2023-02-04 2023-08-03 2023-02-01 ents informatiques pour les a and Energy Sectors ctivités de branchements soc iaux de la SODECA à Bambari et Berberati. Page 3 PASEEL/110/GO/CDS/23 / Ca rbure centres SODECA - Acqu Pending Impl IDA / D2690 Water Supply Infrastructure Post Direct Selection Direct - National 0.00 2023-02-23 2023-02-28 2023-04-04 2023-10-01 isition de carburant pour les ementation centres de Berberati et Bamb ari de la SODECA PASEEL/109/GO/RFQ/23 / Ma tériels extensions - Acquisitio Request for Quota Single Stage - One E IDA / D2690 Water Supply Infrastructure Post Limited 0.00 Signed 2023-03-29 2023-03-24 2023-05-24 2023-11-20 n de matériels d'extension et tions nvelope de raccordement des Bornes Fontaines PASEEL/111/GO/CDS/23 / Co nsommables SODECA provin IDA / D2690 Water Supply Infrastructure Post Direct Selection Direct - National 0.00 Canceled 2023-02-21 2023-02-26 2023-04-02 2023-09-29 ces - Acquisition des consom mables pour SODECA Berber ati et Bambari NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PASEEL/114/NC/DIR/23 / SO DECA Bambari-Achemineme Technical Support to Water Under Imple nt de matériels de réparation IDA / D2690 Post Direct Selection Direct - National 0.00 2023-04-24 2023-05-11 2023-04-29 2023-05-10 2023-06-03 2023-11-30 and Energy Sectors mentation des conduites de distribution d’eau au centre d’exploitatio n de SODECA de Bambari PASEEL/115/NC/DIR/23 / Mat ériels KBF-Acheminement de matériels d’extension et de r Technical Support to Water Pending Impl IDA / D2690 Post Direct Selection Direct - National 0.00 2023-05-09 2023-05-14 2023-06-18 2023-12-15 accordements des bornes fon and Energy Sectors ementation taines sur le réseau de distri bution de la SODECA à Bamb ari. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-6 / Réalisation des Et udes d'Impact Environnemen tal et Social (EIES), y compris Technical Support to Water Consultant Qualifi Open - Internationa les Plans de Gestion Environn / Post 0.00 Canceled 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 and Energy Sectors cation Selection l ementale et Sociale (PGES) e t les Plans d'Action de Réinst allation du Projet Eau et Ener gie à Bambari CS-REF-7 / Réalisation des Et udes d'Impact Environnemen tal et Social (EIES) y compris Technical Support to Water Consultant Qualifi Open - Internationa / Post 0.00 Canceled 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 les Plans de Gestion Environn and Energy Sectors cation Selection l ementale et Sociale (PGES) e t les PARS du Projet eau et é nergie dans la ville de Berber ati CS-REF-8 / Réalisation des EI Technical Support to Water Consultant Qualifi Open - Internationa Under Implement ES, PGES et PARS - Eau et En IDA / D2690 Prior 0.00 2017-11-30 2017-12-21 2018-01-29 2018-02-03 2018-03-27 2018-03-05 2018-04-09 2018-10-06 and Energy Sectors cation Selection l ation ergie à Bangui CS-REF-9 / Diagnostic opérat ionnel APS des installations d e génération et distribution d Consultant Qualifi Open - Internationa / Energy Infrastructure Post 0.00 Canceled 2018-01-05 2018-01-26 2018-03-11 2018-04-10 2018-05-15 2018-11-11 e l'ENERCA dans six villes se cation Selection l condaires ( Ndele, Bria, Kaga -Bandoro, Bangassou et Sibu t) CS-REF-10 / Diagnostic opér ationnel APS, APD et DAO ain Consultant Qualifi Open - Internationa / Energy Infrastructure Post 0.00 Signed 2018-01-10 2018-07-24 2018-01-31 2018-08-02 2018-03-16 2018-11-28 2018-04-15 2019-03-13 2018-05-20 2018-11-16 si que contrôle des travaux à cation Selection l Bambari et Berberati, volet é nergie CS-REF-12 / Audit financier e Technical Support to Water Least Cost Selecti Open - Internationa IDA / V1340 Prior 0.00 Canceled 2018-01-25 2018-02-15 2018-03-31 2018-04-28 2018-05-28 2018-07-02 2018-08-06 2019-02-02 xterne du PPA and Energy Sectors on l PASEEL/02/CS/QC/18 / Bang ui-Berberati étude hydro/ Co Consultant Qualifi Open - Internationa IDA / D2690 Water Supply Infrastructure Prior 548,339.01 Signed 2017-12-20 2018-07-18 2018-01-10 2018-02-23 2018-11-02 2018-03-25 2018-11-27 2018-04-29 2018-12-13 2018-10-26 nsultant pour étude détaillée cation Selection l et contrôle des travaux hydr auliques. CS-REF-2 / Recrutement d'u n consultant pour étude déta Consultant Qualifi Open - Internationa illée des travaux hydraulique / Water Supply Infrastructure Prior 0.00 Canceled 2017-12-20 2018-01-10 2018-02-14 2018-02-23 2018-03-25 2018-04-29 2018-10-26 cation Selection l s devant être réalisées à Ban gui et Berberati et contrôle d es travaux PASEEL/O24/CS/QC/18 / Etud es Bambari/Berberati-Recrut ement d'un Consultant/Firme chargé de la réalisation des é Consultant Qualifi Open - Internationa tudes APS, APD, élaboration IDA / D2690 Energy Infrastructure Prior 0.00 Canceled 2018-08-22 2018-09-12 2018-10-26 2018-11-25 2018-12-30 2019-06-28 cation Selection l du DAO, surveillance et contr ôle des travaux de réhabilitat ion et d'amélioration de l'ali mentation en électricité à Ba mbari et Berberati PASEEL/28/CS/QC/18 / EIES - Technical Support to Water Consultant Qualifi Open - Internationa Berberati: EIES-PGES-PAR du IDA / V1340 Post 95,061.24 Signed 2018-01-15 2018-10-12 2018-02-05 2018-03-21 2018-04-13 2018-04-20 2018-07-23 2018-05-25 2018-07-24 2018-11-21 and Energy Sectors cation Selection l PASEEL pour la ville de Berbe rati. PASEEL/29/SC/QC/18 / EIES Technical Support to Water Consultant Qualifi Open - Internationa BAMBARI-EIES-PGES-PAR du IDA / V1340 Post 112,148.82 Signed 2018-01-15 2018-10-12 2018-02-05 2018-03-21 2018-04-13 2018-04-20 2018-07-19 2018-05-25 2018-07-29 2018-11-21 and Energy Sectors cation Selection l PASEEL pour la ville de BAMB ARI. PASEEL/032/CS/SFQC/18 / Et udes dans 6 villes-Recruteme nt d'un consultant/Firme pou Technical Support to Water Quality And Cost- Open - Internationa r la réalisation des études te IDA / D2690 Prior 593,295.00 Signed 2019-02-20 2019-01-23 2019-03-13 2019-04-17 2019-04-26 2020-03-19 2019-05-24 2020-07-21 2019-06-23 2020-10-21 2019-07-28 2021-06-29 2019-09-01 2021-07-13 2020-08-31 and Energy Sectors Based Selection l chniques de faisabilité et Ava nt-Projet Sommaire, volet ea u et énergie dans six (6) ville s secondaires de la RCA. Page 4 PASEEL/035/CS/QC/19 / Elect Quality Based Sel Open - Internationa rification rurale-Politique d'él IDA / D2690 Energy Infrastructure Post 0.00 Canceled 2019-03-15 2019-04-05 2021-06-01 2019-05-19 2019-06-16 2019-07-16 2019-08-15 2019-09-19 2020-09-18 ection l ectrification rurale et plan d'i nvestissement PASEEL/036/CS/SFQC/19 / Pl an Directeur-Recrutement d' un Consultant/Firme pour l'él Quality And Cost- Open - Internationa aboration d'un Plan Directeur IDA / D2690 Energy Infrastructure Post 519,397.52 Signed 2019-03-11 2019-03-20 2019-04-01 2019-05-15 2019-10-01 2019-06-12 2020-05-15 2019-07-12 2020-05-20 2019-08-16 2020-05-20 2019-09-20 2020-11-14 2020-09-19 Based Selection l et d'un Programme d'Investis sement pour l'électrification nationale de la République C entrafricaine CS-REF-012 / Audit-externe- Recrutement d'un Auditeur e Technical Support to Water Quality And Cost- Open - Internationa IDA / D2690 Prior 0.00 Canceled 2019-03-18 2020-11-12 2019-04-08 2019-05-22 2019-06-19 2019-07-19 2019-08-23 2019-09-27 2020-09-26 xterne pour réaliser l'audit d and Energy Sectors Based Selection l es comptes financiers du Proj et CS-REF-0012 / Audit externe -Recrutement d'un Auditeur Technical Support to Water Quality Based Sel Open - Internationa Under Implement IDA / D2690 Prior 0.00 2019-04-03 2019-03-29 2019-04-24 2019-06-07 2019-04-15 2019-07-05 2019-05-20 2019-08-04 2022-09-11 2019-09-03 2019-10-08 2020-10-07 externe pour réaliser l'audit and Energy Sectors ection l ation des comptes financiers du pr ojet PASEEL/047/CS/QC/19 / Mise Technical Support to Water Consultant Qualifi à jour-Mise à jour de la straté IDA / D2690 Post Open - National 138,401.96 Signed 2019-07-31 2019-09-13 2019-08-21 2019-09-17 2019-10-04 2021-07-13 2019-11-03 2021-09-15 2019-12-08 2021-09-29 2020-06-05 and Energy Sectors cation Selection gie du secteur énergétique PASEEL/048/CS/QCBS/19 / A udit externe 19 - Recrutemen t d'un Consultant/Firme pour Technical Support to Water Quality And Cost- Open - Internationa Under Implement IDA / D2690 Prior 0.00 2019-11-15 2019-12-16 2019-12-06 2020-03-19 2020-01-19 2020-02-16 2020-03-17 2020-04-21 2020-05-26 2021-05-26 la réalisation de l'audit financ and Energy Sectors Based Selection l ation ier et comptable du PASEEL e t PURACEL pour l'exercice 20 19, 2020 et 2021 PASEEL/069/SC/QC/21 / Recr utement d'un Consultant/Fir Technical Support to Water Consultant Qualifi me pour appui aux activités IDA / D2690 Post Limited 22,029.03 Signed 2021-03-25 2021-05-14 2021-04-08 2021-06-01 2021-05-08 2021-08-17 2021-06-12 2021-08-27 2021-12-09 and Energy Sectors cation Selection de communication relatives a ux branchements sociaux. PASEEL/062/CS/QCBS/20 / A udit ENERCA SODECA-Audit fi nancier et comptable de l'EN Technical Support to Water Quality And Cost- Open - Internationa IDA / D2690 Prior 0.00 Canceled 2020-03-09 2020-11-19 2020-03-30 2020-11-23 2020-05-13 2020-06-10 2020-07-10 2020-08-14 2020-09-18 2021-09-18 ERCA et de la SODECA et les and Energy Sectors Based Selection l évaluations indépendantes d es exercices 2016, 2017 et 2 018. PASEEL/00062/CS/LCS/20 / A udit ENERCA SODECA-Audit fi nancier et comptable de l'EN Least Cost Selecti Open - Internationa IDA / D2690 Energy Infrastructure Post 97,306.09 Signed 2020-11-19 2020-11-19 2020-12-10 2021-01-23 2021-02-19 2021-02-20 2021-04-09 2021-03-22 2021-05-03 2021-04-26 2021-05-05 2021-05-31 2021-05-07 2021-11-27 ERCA et de la SODECA et les on l évaluations indépendantes d es exercices 2016, 2017 et 2 018. PASEEL/046/CS/SFQC/19 / C ode d'électrification-Révision Technical Support to Water Quality And Cost- IDA / D2690 Post Open - National 0.00 Canceled 2019-08-02 2019-09-07 2019-08-23 2019-10-06 2019-11-03 2019-12-03 2020-01-07 2020-02-11 2021-02-10 du Code d'électrification et r and Energy Sectors Based Selection édaction des décrets d'applic ation. PASEEL/031/CS/SFQC/18 / As sistance Technique-Recrute Technical Support to Water Quality And Cost- Open - Internationa IDA / D2690 Post 0.00 Canceled 2019-02-15 2019-03-08 2019-04-21 2019-05-19 2019-06-18 2019-07-23 2019-08-27 2020-08-26 ment d'un consultant/Firme p and Energy Sectors Based Selection l our l'Assistance Technique à la SODECA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-1 / Recrutement d'u n consultant chargé de l'élab Technical Support to Water IDA / D2690 Prior Direct Selection Direct 0.00 Under Review 2017-09-30 2018-01-23 2017-10-19 2017-10-04 2017-10-25 2017-11-24 oration du PPSD des Projets P and Energy Sectors ASEEL et PURACEL CS-REF-3 / Recrutement d'u n consultant pour études APS , APD et DAO des travaux hy / Water Supply Infrastructure Prior Direct Selection Direct 0.00 Canceled 2017-12-10 2017-12-20 2018-04-20 2018-02-23 2018-08-22 drauliques à réaliser et contr ôle des travaux dans la ville de Bambari CS-REF-15 / Recrutement d' Technical Support to Water Individual Consult Under Implement IDA / V1340 Post Open 0.00 2018-01-31 2020-09-10 2018-03-21 2018-04-11 2018-05-16 2018-11-12 un Expert en Suivi-évaluation and Energy Sectors ant Selection ation SGF-PASEEL-CS-INDV-16 / S Technical Support to Water Individual Consult GF - Recrutement d'un compt IDA / D2690 Prior Limited 0.00 Canceled 2017-11-10 2017-11-15 2017-12-06 2018-01-10 2018-07-09 and Energy Sectors ant Selection able du Projet PASEEL PASEEL-CS-INDV-15 / EPM-P Technical Support to Water Individual Consult ASEEL-Recrutement d'un Exp IDA / D2690 Prior Limited 3,160.64 Signed 2017-11-12 2017-11-17 2017-12-08 2018-05-05 2018-01-12 2018-05-14 2018-07-11 and Energy Sectors ant Selection ert en Passation des Marchés CS-REF-13 / Recrutement d' Technical Support to Water Individual Consult un comptable, responsable d IDA / V1340 Prior Limited 1,535.77 Signed 2018-01-25 2018-01-30 2018-02-20 2018-03-21 2018-03-27 2018-04-06 2018-09-23 and Energy Sectors ant Selection e gestion fiduciaire du projet PASEEL-18-IND-18 / Expert E nvironnement-Recrutement d Technical Support to Water Individual Consult IDA / D2690 Post Limited 1,714.06 Signed 2018-05-15 2017-10-04 2018-05-20 2020-10-27 2018-06-10 2018-04-13 2018-07-15 2019-04-18 2019-01-11 'un consultant, expert en sau and Energy Sectors ant Selection vegarde environnementale d u Projet PASEEL. PASEEL-19-IND-18 / Expert s ociale - Recrutement d'un co Technical Support to Water Individual Consult IDA / D2690 Post Limited 0.00 Canceled 2018-05-10 2018-05-15 2018-06-05 2018-07-10 2019-01-06 nsultant individuel, expert en and Energy Sectors ant Selection sauvegarde sociale du Projet PASEEL/O25/CS/IND/18 / Rés ilience Boali-Recrutement d'u n consultant chargé de la réd Individual Consult action des spécifications tech IDA / D2690 Energy Infrastructure Post Open 141,700.48 Signed 2018-09-05 2020-02-15 2018-10-24 2019-03-05 2018-11-14 2020-03-07 2018-12-19 2019-03-22 2019-06-17 ant Selection niques pour la fourniture et i nstallation des équipements de la sous-composante "Résil ience de Boali". Page 5 PASEEL/O26/CS/IND/18 / Co mpteurs prépaiement-Recrut ement d'un consultant charg é de la rédaction des spécific Individual Consult IDA / D2690 Energy Infrastructure Post Open 32,300.00 Signed 2018-09-13 2018-08-28 2018-11-01 2019-03-12 2018-11-22 2019-03-20 2018-12-27 2019-03-22 2019-06-25 ations techniques des compt ant Selection eurs à prépaiement et comm uniquant pour l'amélioration des performances commerci ales de l'ENERCA à Bangui. PASEEL/030/CS/IND/18 / Aud it énergétique-Recrutement d'un consultant individuel po Individual Consult IDA / D2690 Water Supply Infrastructure Post Open 54,236.70 Signed 2018-11-15 2018-08-28 2019-01-03 2019-09-02 2019-01-24 2019-09-02 2019-02-28 2019-10-23 2019-08-27 ur la réalisation de l'audit én ant Selection ergétique des infrastructures hydrauliques de la SODECA. PASEEL-0019-IND-18 / Exper Technical Support to Water Individual Consult t Social-Recrutement d'un Ex IDA / D2690 Post Open 16,477.67 Signed 2018-06-03 2020-02-28 2018-07-22 2018-08-06 2018-08-12 2018-09-25 2018-09-16 2018-12-04 2019-03-15 and Energy Sectors ant Selection pert en sauvegardes sociales PASEEL/034/CS/CDS/18 / Par amétrage Tompro-Recrutem Technical Support to Water Individual Consult IDA / D2690 Post Direct 23,580.49 Completed 2018-11-19 2018-12-19 2018-11-29 2019-04-11 2018-12-20 2019-04-16 2019-01-24 2019-04-17 2019-07-23 2019-05-27 ent d'un consultant individue and Energy Sectors ant Selection l pour le paramétrage des pr ojets sur Tompro. CS-REF-11 / Diagnostic opér ationnel/Etat des lieux des in Individual Consult IDA / D2690 Energy Infrastructure Post Open 0.00 Canceled 2019-02-28 2019-04-18 2019-05-09 2019-06-13 2019-12-10 stallations de distribution de ant Selection l'ENERCA à Bangui CS-REF-5 / Etude de réalisati Individual Consult on d'un plan de sécurité du b IDA / D2690 Energy Infrastructure Post Limited 80,150.00 Signed 2019-03-15 2019-02-08 2019-03-20 2019-03-15 2019-04-10 2019-05-02 2020-07-03 2019-05-11 2020-12-30 ant Selection arrage de Boali PASEEL/037/SC/SED/19 / Co ntrat Comptable-Renouvelle Technical Support to Water IDA / D2690 Prior Direct Selection Direct 1,712.76 Signed 2019-04-16 2019-05-08 2019-04-26 2019-06-30 2019-05-10 2019-12-27 ment de contrat du Comptabl and Energy Sectors e du PASEEL et du PURACEL PASEEL/043/CS/ED/19 / Reno uvellement du contrat de l'Ex Technical Support to Water IDA / D2690 Post Direct Selection Direct 38.22 Signed 2019-05-15 2019-05-29 2019-05-25 2019-05-29 2019-07-29 2019-06-09 2020-01-25 pert en Passation des Marché and Energy Sectors s des Projets PASEEL et PURA CEL PASEEL/044/CS/INDV/19 / SI G-Recrutement d'un consulta nt individuel chargé de réalis Technical Support to Water Individual Consult IDA / D2690 Post Open 45,387.60 Signed 2019-06-13 2021-08-27 2019-08-01 2021-11-22 2019-08-22 2021-12-13 2019-09-26 2021-12-28 2020-03-24 er les études pour la mise en and Energy Sectors ant Selection place d'u système d'informati on géographique de la SODE CA PASEEL/060/CS/INDV/19 / Ex pert Social-Renouvellement d Technical Support to Water IDA / D2690 Post Direct Selection Direct 19,825.08 Signed 2019-12-30 2020-01-07 2020-01-09 2020-01-17 2020-03-14 2020-01-17 2020-09-10 u contrat de l'Expert en Sauv and Energy Sectors egardes Sociales PASEEL/061/CS/INDV/19 / Ex pert environnement-Renouve Technical Support to Water IDA / D2690 Post Direct Selection Direct 28,071.11 Signed 2020-01-08 2020-01-16 2020-01-18 2020-02-28 2020-03-23 2020-05-06 2020-09-19 llement du contrat de l'Exper and Energy Sectors t en Sauvegardes Environne mentales PASEEL/063/CS/INDV/20 / Co Technical Support to Water mptable-Renouvellement du IDA / D2690 Post Direct Selection Direct 1,871.30 Signed 2020-03-10 2020-04-17 2020-03-20 2020-04-22 2020-05-24 2020-04-30 2020-11-20 and Energy Sectors contrat du Comptable PASEE L/PURACEL PASSEL/064/CS/INDV/20 / SP M Renouvellement-Renouvell Technical Support to Water IDA / D2690 Post Direct Selection Direct 0.00 Signed 2020-06-15 2020-06-29 2020-06-25 2020-05-29 2020-08-29 2021-02-25 ement du contrat du Spéciali and Energy Sectors ste en Passation des Marchés PASEEL/066/CS/IND/20 / Soci Technical Support to Water Individual Consult al-Renouvellement du Contra IDA / D2690 Post Direct 29,047.36 Signed 2020-09-30 2020-09-16 2020-10-10 2020-09-04 2020-10-31 2020-12-04 2020-12-05 2020-12-10 2021-06-03 and Energy Sectors ant Selection t de l'Expert en Sauvegardes Sociales PASEEL/067/CS/INDV/20 / Re lecture-Recrutement d'un Co Technical Support to Water Individual Consult nsultant individuel chargé de IDA / D2690 Post Direct 0.00 Canceled 2020-10-21 2020-10-22 2020-10-31 2020-11-21 2020-12-26 2021-06-24 and Energy Sectors ant Selection la relecture et finalisation de s rapports EIES des villes de Bambari et Berberati. PASEEL/068/CS/INDV/21 / Av Technical Support to Water Individual Consult enant 3-Renouvellement du IDA / D2690 Post Direct 30,595.49 Signed 2021-02-16 2021-04-01 2021-02-26 2021-05-27 2021-03-19 2021-06-09 2021-04-23 2021-06-19 2021-10-20 and Energy Sectors ant Selection Contrat du Comptable du PA SEEL/PURACEL PASEEL/069/CS/INDV/21 / Av enant 2- renouvellement du Technical Support to Water Individual Consult IDA / D2690 Post Direct 28,410.10 Signed 2021-02-18 2021-03-01 2021-02-28 2021-05-27 2021-03-21 2021-06-10 2021-04-25 2021-06-19 2021-10-22 Contrat de l'Expert en Sauve and Energy Sectors ant Selection gardes Environnementales. PASEEL/073/CS/DIR/21 / Ave nant3 SPM-Renouvellement d Technical Support to Water IDA / D2690 Post Direct Selection Direct 43,158.96 Signed 2021-05-31 2021-06-14 2021-06-10 2021-06-07 2021-08-14 2021-06-10 2022-02-10 u contrat du Spécialiste en P and Energy Sectors assation des Marchés second du PURACEL/PASEEL PASEEL/076/CS/INDV/21 / Ev aluation mi parcours-Recrute ment d'un Consultant Individ Technical Support to Water Individual Consult IDA / D2690 Post Limited 42,814.85 Signed 2021-06-21 2021-05-28 2021-06-26 2021-08-06 2021-07-17 2021-09-06 2021-08-21 2021-09-08 2022-02-17 uel chargé de l'évaluation à and Energy Sectors ant Selection mi parcours du Projet d'Améli oration des Services d'Eau et d'Electricité (PASEEL). PASEEL/081/CS/INDV/21 / Co ntrat SGF-Renouvellement du Technical Support to Water contrat n°0266/20/MTPER/DI IDA / D2690 Post Direct Selection Direct 138,375.90 Signed 2021-09-20 2021-08-19 2021-09-30 2021-09-07 2021-12-04 2021-10-30 2022-06-02 and Energy Sectors RCAB/CUGP/PASEEL-PURACE L, Prestations de Spécialiste en Gestion Financière PASEEL/083/CS/CDS/21 / Exp ert Energie-Renouvellement du contrat n°0217/18/MTPER/ Technical Support to Water IDA / D2690 Post Direct Selection Direct 197,521.30 Signed 2021-11-22 2020-11-30 2021-12-02 2021-12-07 2022-02-05 2022-01-20 2022-08-04 DIRCAB/CUG/PASEEL-PURACE and Energy Sectors L, prestations d'Expert en En ergie (NERGUIDIMA Mathurin ) Page 6 PASEEL/084/CS/CDS/21 / Exp ert Social-Renouvellement du contrat n°0192/18/MTPER/DI Technical Support to Water IDA / D2690 Post Direct Selection Direct 28,318.56 Signed 2021-11-19 2020-09-23 2021-11-29 2021-11-24 2022-02-02 2022-02-24 2022-08-01 RCAB/CUG -/PASEEL–PURACE and Energy Sectors L, prestation d'Expert en sau vegardes sociales du PASEEL /PURACEL PASEEL/089/CS/INDV/21 / Re vue code-Révision du code d' Technical Support to Water Individual Consult IDA / V1340 Post Open 0.00 Signed 2021-12-27 2021-12-21 2022-02-14 2022-03-07 2022-03-07 2022-12-14 2022-04-11 2022-10-08 électricité et rédaction des d and Energy Sectors ant Selection écrets d'application. PASEEL/094/SC/INDV/22 / Co ntrôle Bambari-Recrutement par entente pour la surveillan Technical Support to Water IDA / D2690 Post Direct Selection Direct - National 0.00 Signed 2022-09-27 2022-10-14 2022-10-07 2022-10-18 2022-12-11 2023-06-09 ce et contrôle des travaux de and Energy Sectors réhabilitation des infrastruct ures d’alimentation en eau p otable de la ville de Bambari. PASEEL/95/SC/INDV/22 / Con trôle Berberati-Recrutement par entente directe d'un cons Technical Support to Water ultant individuel pour la supe IDA / D2690 Post Direct Selection Direct - National 0.00 Signed 2022-09-30 2022-10-14 2022-10-10 2022-10-18 2022-12-14 2023-06-12 and Energy Sectors rvision et contrôle des travau x de Réhabilitation des infras tructures d’alimentation en e au potable de la ville de Berb erati. CS-REF-03 / MOC AEP Bamb ari-Recrutement d'un consult ant pour études APS, APD et Direct - Internation IDA / D2690 Water Supply Infrastructure Post Direct Selection 0.00 Signed 2017-12-10 2018-04-24 2017-12-20 2018-04-20 2018-02-23 2018-08-22 DAO des travaux hydraulique al s à réaliser et contrôle des tr avaux dans la ville de Bamba ri PASEEL/CS/CDS/22 / Concep tion 2 forages-Recrutement d 'un consultant individuel char Technical Support to Water Direct - Internation IDA / D2690 Post Direct Selection 0.00 Signed 2022-11-28 2022-11-24 2022-12-08 2022-11-29 2023-02-11 2023-08-10 gé de réaliser les études et c and Energy Sectors al onception de deux forages p our le compte de la SODECA à Beberati. PASEEL/112/CS/CDS/23 / Au dit technique-Recrutement d’ un Consultant Individuel char gé de l’Audit de l’exécution d Technical Support to Water Direct - Internation Under Implement u marché des Travaux de réh IDA / D2690 Post Direct Selection 0.00 2023-04-17 2023-04-10 2023-04-27 2023-07-01 2023-12-28 and Energy Sectors al ation abilitation, de construction et d’équipement des infrastruct ures d’eau potable dans la vil le de BAMBARI confiés à l’Ent reprise SK BATIMENT. PASEEL/0113/CS/CDS/23 / A udit SK-Recrutement d’un Co nsultant Individuel chargé de l’Audit de l’exécution des ma Technical Support to Water Direct - Internation Under Implement rchés de Travaux de réhabilit IDA / D2690 Post Direct Selection 0.00 2023-04-17 2023-04-10 2023-04-27 2023-07-01 2023-12-28 and Energy Sectors al ation ation, de construction et d’éq uipement des infrastructures d’eau potable dans la ville de BERBERATI confiés à l’Entrep rise SK BATIMENT. Page 7 Plan de Passation des marchés du Projet d’Appui aux Communautés dépendantes de la Forêt (DGM-DRC) P149049 (TF0A0924). I. Général 1. Date d’élaboration : 8 février 2016 2. Date d’approbation par la Banque du Plan de Passation des Marches : 8 février 2016 - Version négociée 3. Date de l’Avis Général de Passation des marchés: 4. Période couverte par ce Plan : Janvier à Décembre 2016 5. Risque passation des marchés : Substantiel II. Biens et Travaux et services autres que ceux de consultants. 1. Seuil de revue préalable: au-dessus duquel le processus de passation des marchés fait l’objet d’une revue préalable de la Banque mondiale tel que décrit dans l’annexe 1 des Directives pour l’acquisition de biens et de services autres que ceux de consultants. Nature des Méthode de passation Valeur seuil Contrats soumis à dépenses de marchés du marché examen préalable de $EU l’IDA 1. Travaux Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 Demande de cotation – < 200.000 Aucun comparaison d’au moins 3 offres 2. AON ˂1 000.000 Tout contrat supérieur ou Fournitures égal à US$500 000 et services Consultation de < 100.000 Aucun assimilés Fournisseurs Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 N.B. : Toutes les justifications du recours à l’entente directe incluant le montant estimé du contrat sont à soumettre à la revue préalable de la Banque. 2. Liste globale des contrats d’équipement devant être financés sur le don de préparation et le projet. Date Réf. Cout Méthode Préfére prévue Commentai Description Revue No. estimés$ de nce pour res 1 Passatio nationa (Prior / l’ouvertur n des le Post) e des marchés (oui/no offres n) Acquisition de cinq 1 motos de brousse 12.000 CF Non Post 15/06/16 et 32 vélos Service informatique de configuration de 2 15/05/16 logiciels 5,000 CF Non Post spécialisés de comptabilité Assurance du 3 matériel roulant 15/06/16 2,000 ED Non Post (pour 3 ans) Contrat ouvert – tarif Impression et préférentiels duplication des négociés documents du 4 20,000 1/12/16 pour les projet, du Code AC Non Post prestations Forestier et des attendues décrets durant l’année CF= Consultations de Fournisseurs AC = Accord Cadre III. Sélection de Consultants 1. Seuil de revue préalable: au-dessus duquel le processus de sélection fait l’objet d’une revue préalable de la Banque mondiale tel que décrit dans l’annexe 1 des Directives pour la sélection et l’emploi de consultants. Nature de Méthode de Valeur seuil du Contrats soumis à examen dépenses passation de contrat préalable marchés $EU Consultan ≥ 200.000 Tout contrat supérieur ou ts égal à US$ 500 000 Firmes < 200.000 Aucun QC Tout montant Tout contrat supérieur ou égal à US$ 100 000 Entente directe 2 Consultan Tout montant Tout contrat supérieur ou ts Consultant égal à Individuel individuel 200 000 US$ s Entente directe Tout montant Tout contrat supérieur ou égal à US$ 100 000 Tous les TDRs, quelle que soit la valeur du contrat, sont soumis à examen préalable. Toutes les justifications du recours à l’entente directe incluant le montant estimé du contrat sont soumis à l’examen préalable de la Banque. QC = Qualifications du Consultant 2. Listes restreintes comprenant uniquement des candidats nationaux: Les listes restreintes pour les contrats de consultants estimées à un coût inférieur à $100,000 pour les services ordinaires et $200,000 pour les contrats de supervision peuvent être entièrement composées de consultants nationaux, suivant les dispositions du Paragraphe 2.7 des Directives pour l’emploi des Consultants. 1 2 3 4 5 6 7 8 Examen Date Ref. Description Montant Préalable prévue Date Commentaires No. Méthod estimé ou à pour prévue e de ($.US) postériori l’ouvertu pour sélectio par la re des attributio n Banque offres n Opérateur spécialisé Pour les 3 pour le suivi des premières plaintes, 1 ED 200,000 Priori 15/07/16 15/08/16 années – consultation Composante 3b - permanente des REPALEF communautés Réalisation pour 2 chaque APAC de la 1 seule sélection cartographie avec 5 lots de QC 225,000 Post 15/08/16 15/09/16 participative, du 45,000 USD – plan de gestion et du Composante 2b PARAR Opérateur spécialisé Pour 3 ans – 3 QC 45,000 Post 1/03/16 1/04/16 sur la question des Composante 1a – 3 droits fonciers des PA Etudes pour dégager des options susceptibles de 4 renseigner la CI 5,000 Post 15/08/16 15/09/16 Composante 1a réforme foncière sur l'accès des PA à la terre Opérateur spécialisé pour créer des Pour 3 ans - 5 lobbies pour QC 45,000 Post 1/03/16 1/04/16 Composante 1a l'adoption de la loi sur les PA Opérateur spécialisé pour l'appui à la gestion Pour 3 ans - 6 QC 45,000 Post 1/03/16 1/04/16 communautaire de Composante 1a l'affectation des terres (APAC) Opérateurs pour Les lots seront l'alphabétisation des définis après le PACL impliqués dans diagnostic la gestion du projet institutionnel et les former à la initial pour 7 QC 40,000 Post 15/08/16 15/09/16 gestion et à la petite identifier les comptabilité (tenue opérateurs du livre de caisse, locaux et les gestion des entrées besoins - et des sorties, etc) Composante 1b Consultant appui Conservation Communautaire 8 CI 5,000 Post 15/2/16 10/03/16 pour le bilan des expériences existantes Contrat 3 ans 9 Expert Sauvegardes CI 70,000 Post 15/07/16 15/08/16 renouvelable - Composante 3a Appui pour la finalisation - Rédaction du Manuel 10 CI 5,000 Post 1/03/16 1/04/16 pour la mise en de mise en œuvre vigueur - Composante 3a Pour 3 ans - 11 Auditeur externe SMC 45,000 Post 15/07/16 15/08/16 Composante 3a En vue de la Expert technique revue à mi- 12 CI 30,000 Post 15/11/16 15/12/16 indépendant parcours - Composante 3b 4 5 PROCUREMENT Congo, Democratic Republic of : Forest Dependent Communities Support Project PLAN General Information Country: Congo, Democratic Republic of 2018-09-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P149049 GPN Date: Project Name: Forest Dependent Communities Support Project Loan / Credit No: TF / A0924, TF / A5550 CARITAS CONGO Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CARITAS-125539-GO-RF Component 3 - Increase the Q / 40 téléphones (+4) Andro capacity to implement the IP Request for Quota Single Stage - One E TF / A0924 Post Limited 15,600.00 6,783.00 Signed 2019-08-05 2019-10-29 2019-09-30 2020-03-14 2020-03-28 id pour le suivi des indicateur LC development activities a tions nvelope s avec KOBO. nd consolidate feedback NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CARITAS-83598-NC-RFQ / Contrat - Cadre avec Imprim Component 1 - Reinforce the eurs (plusieurs lots) pour mo participation of the IPLC in fo Request for Quota Single Stage - One E Pending Impl TF / A0924 Post Limited 60,000.00 0.00 2018-11-05 2018-12-31 2019-06-29 dules d'alphabétisation , cod rest and land management tions nvelope ementation e forestier, textes sur le fonci processes related to REDD+ er (40000 documents de taill es diverses) ZR-CARITAS-122739-CS-CDS Component 1 - Reinforce the / Transport et distribution de participation of the IPLC in fo Request for Quota Single Stage - One E Pending Impl s modules dans les territoires TF / A0924 Post Limited 8,000.00 0.00 2019-07-31 2019-09-25 2020-03-23 rest and land management tions nvelope ementation avec AEN ( consultations de processes related to REDD+ trois transporteurs pour dem ande des prixà ZR-CARITAS-83603-NC-RFQ / Component 1 - Reinforce the Transport des documents po participation of the IPLC in fo Request for Quota Single Stage - One E TF / A0924 Post Limited 3,000.00 0.00 Canceled 2018-11-05 2018-12-31 2019-06-29 ur Kisangani, Mbujimayi, Go rest and land management tions nvelope ma, Kanange, Inongo et Mba processes related to REDD+ ndaka ZR-CARITAS-175242-NC-RFQ / Sélection d'un prestataire p Component 2 - Support com Request for Quota Single Stage - One E our la reproduction des docu TF / A0924 munity-based sustainable fo Post Limited 12,750.00 0.00 Canceled 2020-07-25 2020-09-19 2021-03-18 tions nvelope ments sur le foncier, foresteri rest and land management e communautaire et amenag ement du territoire CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 - Increase the ZR-CARITAS-66039-CS-CDS / capacity to implement the IP Consultant Qualifi Recrutement point focal INO TF / A0924 Post Open - National 18,000.00 0.00 Signed 2018-09-13 2018-09-13 2018-09-18 2023-06-01 2018-10-07 2023-06-05 2018-10-17 2023-06-09 2018-10-27 2019-04-25 LC development activities a cation Selection NGO nd consolidate feedback ZR-CARITAS-241037-CS-QCB Component 3 - Increase the S / Recrutement d'un Cabinet capacity to implement the IP Consultant Qualifi TF / A0924 Post Open - National 6,000.00 8,260.00 Signed 2021-07-14 2021-07-15 2021-07-17 2021-09-10 2021-07-24 2021-07-27 2021-07-29 2021-07-30 2021-08-08 2021-08-11 2021-09-07 d'Audit pour Auditer les Etats LC development activities a cation Selection financiers du Projet DGM exe nd consolidate feedback rcice 2020 ZR-CARITAS-49120-CS-CDS / Component 3 - Increase the CAUDITEC - Recrutement d'u capacity to implement the IP Quality And Cost- n Auditeur externe pour la c TF / A0924 Post Open - National 40,000.00 0.00 Canceled 2018-10-31 2018-10-31 2018-11-21 2019-01-04 2019-02-01 2019-03-03 2019-04-07 2019-05-12 2020-05-11 LC development activities a Based Selection ertification des comptes de l nd consolidate feedback a DGM pour les comptables 2 016, 2017 et 2018 ZR-CARITAS-280030-CS-QCB Component 3 - Increase the S / Recrutement d'un auditeu capacity to implement the IP Quality And Cost- r externe pour la reddition de TF / A0924 Post Open - National 40,000.00 0.00 Signed 2022-03-07 2023-06-12 2022-03-28 2023-06-22 2022-05-11 2023-06-20 2022-06-08 2023-06-20 2022-07-08 2023-06-20 2022-08-12 2023-06-20 2022-09-16 2023-09-16 LC development activities a Based Selection s comptes du projet DGM exe nd consolidate feedback rcices 2016, 2017 et 2018 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3 - Increase the ZR-CARITAS-66157-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 22,500.00 0.00 Canceled 2018-10-31 2019-10-01 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF Sauvegardes KISANGANI LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66158-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 9,000.00 0.00 Signed 2018-10-31 2019-10-01 2018-12-19 2023-06-05 2019-01-09 2023-06-07 2019-02-13 2019-08-12 PF Sauvegardes GOMA LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66159CS-CDS / capacity to implement the IP Individual Consult Under Implement TF / A0924 Post Open 13,500.00 0.00 2018-10-31 2018-10-31 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF Sauvegardes KANANGA LC development activities a ant Selection ation nd consolidate feedback Page 1 Component 3 - Increase the ZR-CARITAS-66159-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 22,500.00 0.00 Signed 2018-10-31 2019-10-01 2018-12-19 2023-06-04 2019-01-09 2023-06-06 2019-02-13 2019-08-12 PF Sauvegardes MBUJIMAYI LC development activities a ant Selection nd consolidate feedback Component 3 - Increase the ZR-CARITAS-83607-CS-INDV capacity to implement the IP Individual Consult Under Implement TF / A0924 Post Open 72,000.00 0.00 2018-10-25 2018-10-25 2018-12-13 2019-01-03 2019-02-07 2019-08-06 / Expert Sauvegardes LC development activities a ant Selection ation nd consolidate feedback Component 3 - Increase the ZR-CARITAS-66156-CS-CDS / capacity to implement the IP Individual Consult TF / A0924 Post Open 18,000.00 0.00 Canceled 2018-10-31 2018-12-19 2019-01-09 2019-02-13 2019-08-12 PF sauvegardes INONGO LC development activities a ant Selection nd consolidate feedback ZR-CARITAS-122805-CS-CDS Component 1 - Reinforce the / Salaire expert sauvegarde e participation of the IPLC in fo Individual Consult nv. et sociale et mission suivi TF / A0924 Post Limited 126,000.00 0.00 Canceled 2019-08-08 2019-08-13 2019-09-03 2019-10-08 2020-04-05 rest and land management ant Selection sauvegarde (respect des cad processes related to REDD+ res de gestion environnemen tale et sociale ZR-CARITAS-62547-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as BUKAVU sur l'Alphabétisat TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-22 2020-07-24 2020-07-02 2020-08-03 2020-09-05 2020-08-14 2021-03-04 rest and land management ion Dio BUKAVU, Territoire de processes related to REDD+ KALEHE . Component 1 - Reinforce the ZR-CARITAS-49616-CS-CDS / participation of the IPLC in fo Alphabétisation Dio KANANG TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2019-07-16 2020-07-24 2019-07-26 2020-08-03 2019-09-29 2020-08-25 2020-03-27 rest and land management A, Territoire de DIMBELENGE processes related to REDD+ ZR-CARITAS-62538-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de MWEKA pour l' TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-22 2020-07-24 2020-07-02 2020-08-03 2020-09-05 2020-08-21 2021-03-04 rest and land management éducation de base et l'alphab processes related to REDD+ étisation territoire MWEKA ZR-CARITAS-62540-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese d'INONGO, territoi TF / A0924 Post Direct Selection Direct 18,000.00 18,000.00 Signed 2020-06-25 2020-07-24 2020-07-05 2020-08-06 2020-09-08 2020-08-11 2021-03-07 rest and land management re de KIRI, OSWE et INONGO processes related to REDD+ pour l'éducation de base et l' alphabétisation . ZR-CARITAS-62543-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese d'ISANGI, territoir TF / A0924 Post Direct Selection Direct 12,000.00 12,000.00 Signed 2020-07-20 2020-07-24 2020-07-30 2020-07-27 2020-10-03 2020-08-11 2021-04-01 rest and land management e de YAHUMA et OPALA pour processes related to REDD+ l'éducation de base et l'alpha bétisation ZR-CARITAS-62546-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-07-31 2020-07-24 2020-08-10 2020-08-06 2020-10-14 2020-08-12 2021-04-12 as diocese de MBANDAKA BI rest and land management KORO, territoire de BIKORO processes related to REDD+ Component 1 - Reinforce the ZR-CARITAS-83577-CS-CDS / participation of the IPLC in fo Alphabétisation Dio WAMBA - TF / A0924 Post Direct Selection Direct 12,000.00 12,000.00 Signed 2020-06-26 2020-07-24 2020-07-06 2020-08-03 2020-09-09 2020-08-11 2021-03-08 rest and land management MAMBASA ET BAFWASENDE processes related to REDD+ ZR-CARITAS-175241-CS-CDS Component 3 - Increase the / Renouvelement de contrat capacity to implement the IP avec REPALEF avec les opéra TF / A0924 Post Direct Selection Direct 120,950.00 0.00 Signed 2020-07-27 2016-07-01 2020-08-06 2016-07-11 2020-10-10 2021-04-08 LC development activities a teurs pour le suivi de satifact nd consolidate feedback ion et gestion des plainte 20 20 2022 ZR-CARITAS-62460-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de KABINDA pour TF / A0924 Post Direct Selection Direct 18,000.00 18,000.00 Signed 2020-06-17 2021-03-17 2020-06-27 2020-07-27 2020-09-15 2020-08-21 2021-03-14 rest and land management l'alphabétisation , Territoire K processes related to REDD+ ABINDA, LUBAO et LUSAMBO ZR-CARITAS-185697-CS-CDS / Contractualisation avec l'O NG FONDATION NSELALA pou Component 2 - Support com r valorisation des initiatives l TF / A0924 munity-based sustainable fo Post Direct Selection Direct 61,000.00 61,000.00 Signed 2020-08-10 2021-03-18 2020-08-20 2020-08-24 2020-09-15 2020-11-11 2021-03-14 ocales des plantations d'arbr rest and land management es dans le secteur entre LUK ENI - LOKORO , Territoire de 0shwe ZR-CARITAS-185700-CS-CDS / Contractualisation avec l'O Component 2 - Support com NG EQUIPE MIKA pour la valo TF / A0924 munity-based sustainable fo Post Direct Selection Direct 61,000.00 66,077.00 Signed 2020-08-10 2021-03-18 2020-08-20 2020-08-24 2020-09-15 2020-11-03 2021-03-14 risation des initiatives locales rest and land management des plantations d'arbres dans le secteur de Penzwa, Territo ire de Kiri ZR-CARITAS-175248-CS-CDS / Renouvelement de contrat Component 1 - Reinforce the avec LINAPYCO pour la Colle participation of the IPLC in fo Under Implement TF / A0924 Post Direct Selection Direct 120,000.00 0.00 2020-07-13 2020-07-13 2020-07-23 2020-07-23 2020-09-26 2021-03-25 cte des données sur les terre rest and land management ation s des PA pour la reconnaissa processes related to REDD+ nce légale et la sécurisation des terres ZR-CARITAS-62535-CS-CDS / Contractualisation avec Carit Component 1 - Reinforce the as diocese de MUJIMAYI , terri participation of the IPLC in fo toire de LUPATAPATA Les Les TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-06-29 2021-03-17 2020-07-09 2020-07-27 2020-09-15 2020-08-21 2021-03-14 rest and land management justificatifs techniques ( note processes related to REDD+ s méthodologiques et cv des alphabétiseurs vous parviend rons par mail. ZR-CARITAS-185701-CS-CDS / Contractualisation avec le C entre National d'appui au Dé veloppement et à la participa Component 2 - Support com tion populaire (CENEDEP) po TF / A0924 munity-based sustainable fo Post Direct Selection Direct 66,000.00 0.00 Canceled 2020-08-10 2020-08-20 2020-09-15 2021-03-14 ur l'amélioration des capacit rest and land management és de 280 ménages PA et CO LO à planter et entretenir les arbres de la forêt MOBOKON DA secteur INONGO ZR-CARITAS-62464-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de KOLE pour l'éd TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-21 2021-03-16 2020-10-01 2020-07-27 2021-11-22 2020-08-21 2022-02-20 rest and land management ucation de base et l'alphabéti processes related to REDD+ sation des PA et COLO Territo ire de DEKESE Page 2 ZR-CARITAS-189907-CS-CDS Component 1 - Reinforce the / Contractualisation avec l'O participation of the IPLC in fo NG CENADEP pour l'élevage TF / A0924 Post Direct Selection Direct 65,000.00 65,416.00 Signed 2020-09-21 2021-03-18 2020-10-01 2020-08-26 2020-12-05 2020-11-06 2021-06-03 rest and land management des porcs à MOMBOKONDA, processes related to REDD+ dans le Territoire d’INONGO ZR-CARITAS-185690-CS-CDS / Contractualisation avec l'O NG Programme d'intégration Component 1 - Reinforce the et du développement des pe participation of the IPLC in fo uples pygmées (PIDP) pour l' TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Signed 2020-09-15 2020-09-08 2020-09-25 2021-09-18 2020-10-21 2021-04-19 rest and land management éducation de base et l'alphab processes related to REDD+ étisation aux peuples autoch tones (PA ) et aux communa utés locales (COLO) pour le T erritoire de Walikale. ZR-CARITAS-62537-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-15 2021-03-17 2020-09-25 2020-07-27 2020-12-09 2020-08-21 2021-06-07 as de KISANGANI pour l'éduc rest and land management ation de base et l'alphabétisa processes related to REDD+ tion ZR-CARITAS-62539-CS-CDS / Component 1 - Reinforce the Contractualisation avec Carit participation of the IPLC in fo as diocese de TSHUMBE pour TF / A0924 Post Direct Selection Direct 6,000.00 6,000.00 Signed 2020-09-15 2020-07-10 2020-09-25 2020-07-27 2020-10-28 2020-08-21 2021-04-26 rest and land management l'éducation de base et l'alpha processes related to REDD+ bétisation Territoire de LUBE FU ZR-CARITAS-154570-CS-CDS Component 2 - Support com / Contractualisation avec AN TF / A0924 munity-based sustainable fo Post Direct Selection Direct 80,000.00 0.00 Canceled 2020-07-21 2020-07-31 2020-10-04 2021-04-02 APAC pour l'organisation de r rest and land management éunions avec les peules auto chtones ZR-CARITAS-175245-CS-CDS / Avenant avec ANAPAC pour Component 2 - Support com suivi des dossiers de deman TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,000.00 0.00 Canceled 2020-07-27 2020-08-06 2020-10-10 2021-04-08 de auprès du Ministère de l'e rest and land management nvironnement et du Gouvern ement ZR-CARITAS-175244-CS-CDS / Renouvellement contrat AN APAC pour organiser des ass Component 2 - Support com emblées communautaires et TF / A0924 munity-based sustainable fo Post Direct Selection Direct 285,000.00 0.00 Canceled 2020-07-21 2020-07-21 2020-07-31 2020-07-31 2020-10-04 2021-04-02 réunions consultatives, d'ide rest and land management ntification, prospection des si tes à : Walikale, Bikoro et fin alisation dossier Mweka, Kiri et Mambasa ZR-CARITAS-196411-CS-CDS Component 1 - Reinforce the / Contractualisation avec DG participation of the IPLC in fo PA pour Suivi des loi au Parle TF / A0924 Post Direct Selection Direct 25,500.00 0.00 Signed 2020-09-28 2020-09-28 2020-10-08 2020-09-08 2020-12-12 2021-06-10 rest and land management ment et lutte contre la discri processes related to REDD+ mination pour les PA ZR-CARITAS-62578-CS-CDS / DIPED: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Walikale dans l'identificatio TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 n des idées des microprojets rest and land management et des Opérateurs locaux d'a ppui aux communautés -Com posante 2.a.1 - Consultant ZR-CARITAS-62576-CS-CDS / UEFA: Opérateur pour accom pagner les communautés de Component 2 - Support com Kalehe dans l'identification d TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 es idées des microprojets et rest and land management des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-49316-CS-CDS / CAIF- Opérateur pour accom Component 2 - Support com pagner les communautés (m TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2018-03-01 2018-03-11 2018-05-15 2018-11-11 icroprojets et des Opérateurs rest and land management locaux d'appui aux communa utés Lubao et Lubefu ZR-CARITAS-62579-CS-CDS / FECOFA: Opérateur pour acc ompagner les communautés Component 2 - Support com de Kabinda et Lusambo dans TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 l'identification des idées des rest and land management microprojets et des Opérateu rs locaux d'appui aux commu nautés -Composante 2.a.1 - Consultant ZR-CARITAS-62575-CS-CDS / GTF: Opérateur pour accomp agner les communautés de Y Component 2 - Support com ahuma et Opala dans l'identif TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 ication des idées des micropr rest and land management ojets et des Opérateurs locau x d'appui aux communautés -Composante 2.a.1 - Consult ant ZR-CARITAS-62572-CS-CDS / EPAP/RDC: Opérateur pour a ccompagner les communaut Component 2 - Support com és de Lupatapata et Dimbele TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,350.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 nge dans l'identification des i rest and land management dées des microprojets et des Opérateurs locaux d'appui au x communautés -Composant e 2.a.1 - Consultant ZR-CARITAS-62582-CS-CDS / APSVR:Opérateur pour acco mpagner les communautés d Component 2 - Support com e Mweka et Dekese dans l'id TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,700.00 0.00 Canceled 2018-05-14 2019-10-30 2018-05-24 2018-07-28 2019-01-24 entification des idées des mi rest and land management croprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-62581-CS-CDS / OCEAN: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Banalia, Bafwasende et Ma TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,950.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 mbasa dans l'identification d rest and land management es idées des microprojets et des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant Page 3 ZR-CARITAS-49123-CS-CDS / Consultant Kasongo Kabusa Component 2 - Support com Raphael, chargé d'identificati TF / A0924 munity-based sustainable fo Post Direct Selection Direct 8,000.00 0.00 Canceled 2018-02-05 2018-02-15 2018-04-21 2018-10-18 on des expériences de mise rest and land management en œuvre des microprojets c ommunautaires ZR-CARITAS-125538-CS-CDS Component 1 - Reinforce the / Contrat REPEQ identificatio participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 10,000.00 0.00 Canceled 2019-08-31 2019-09-10 2019-11-14 2020-05-12 n des besoins en renforceme rest and land management nt des capacités processes related to REDD+ ZR-CARITAS-62580-CS-CDS / DIPY: Opérateur pour accom pagner les communautés d'I Component 2 - Support com nongo et Oshwe dans l'identi TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2018-05-14 2018-05-24 2018-07-28 2019-01-24 fication des idées des microp rest and land management rojets et des Opérateurs loca ux d'appui aux communautés -Composante 2.a.1 - Consult ant ZR-CARITAS-49610-CS-CDS / -CIDB: Opérateur d'identificat Component 2 - Support com ion des micros projets et ON TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,600.00 0.00 Canceled 2018-03-01 2018-03-11 2018-05-15 2018-11-11 G locales ( Bikoro et Kiri) AN rest and land management O obtenu 25/09/2017 Component 1 - Reinforce the ZR-CARITAS-122741-CS-CDS participation of the IPLC in fo Individual Consult / Evaluation à mis parcours s TF / A0924 Post Limited 17,500.00 0.00 Canceled 2019-08-10 2019-08-15 2019-09-05 2019-10-10 2020-04-07 rest and land management ant Selection uivi processes related to REDD+ ZR-CARITAS-253078-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de M participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Under Review 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 BANDAKA pour l'éducation d rest and land management e base et l'alphabétisation, T processes related to REDD+ erritoire de BIKORO composa nte 1b ZR-CARITAS-253085-CS-CDS / Renouvellement avec ANAP AC pour appui à l'élaboration des cartes des droits et d'aff Component 2 - Support com ectation des terres, plans de TF / A0924 munity-based sustainable fo Post Direct Selection Direct 113,500.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 sondage, Dépôt des dossiers rest and land management de demande de CFCL, Enquê te de vacance des terres, Ob tention de CFCL à Mweka, Bi ko, Walikale. composante 2b ZR-CARITAS-253091-CS-CDS Component 3 - Increase the / Renouvellement de Contrat capacity to implement the IP avec REPALEF pour le suivi d TF / A0924 Post Direct Selection Direct 40,500.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 LC development activities a e satisfaction et gestion des nd consolidate feedback plaintes. composante 3b ZR-CARITAS-253093-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec (CENADEP) pour l'améli participation of the IPLC in fo oration des capacités de 280 TF / A0924 Post Direct Selection Direct 38,045.00 0.00 Signed 2021-12-08 2022-02-28 2021-12-18 2022-03-10 2022-02-21 2022-06-21 rest and land management ménages PA et COLO à plant processes related to REDD+ er et entretenir les arbres de la forêt MOBOKONDA secteur INONGO. composante 2a ZR-CARITAS-253094-CS-CDS / Renouvellement contrat av ec l'ONG ADGRN pour le pro Component 2 - Support com jet de plantation d’arbres su TF / A0924 munity-based sustainable fo Post Direct Selection Direct 71,250.00 73,773.50 Signed 2021-12-08 2021-12-06 2021-12-18 2022-01-31 2022-02-21 2022-01-25 2022-03-05 r 45 ha et de promotion de l’ rest and land management élevage et de l'apiculture da ns les villages de Milela, Toko meka et Tshintu mwanza, Te rritoire de Lupatapata. comp osante 2a ZR-CARITAS-253072-CS-CDS / Renouvellement contrat Ca ritas diocésaine Kabinda po Component 1 - Reinforce the ur le projet d'appui à la prote participation of the IPLC in fo ction du forestière par l'agro TF / A0924 Post Direct Selection Direct 73,960.00 0.00 Signed 2021-12-08 2022-01-14 2021-12-18 2022-01-31 2022-03-08 2022-07-06 rest and land management foresterie et en faveur des p processes related to REDD+ euples autochtones pour les villages de Tulimbi, Ebaala et Kashoko, Territoire de Kabind a composante 2a ZR-CARITAS-253097-CS-CDS / Renouvellement de contrat Component 2 - Support com avec l'ONG SPFA pour le proj TF / A0924 munity-based sustainable fo Post Direct Selection Direct 22,680.00 0.00 Signed 2021-09-30 2021-09-30 2021-10-10 2021-10-10 2021-12-14 2022-04-13 et d'appui à l'agroforesterie e rest and land management t à la pisciculture dans les vill ages Moboyo, Mboli et Iyand a, dans le Territoire de Bikor o ZR-CARITAS-253098-CS-CDS / Renouvellement contrat UE Component 2 - Support com FA projet d'amélioration des TF / A0924 munity-based sustainable fo Post Direct Selection Direct 48,760.00 0.00 Signed 2021-12-08 2021-07-01 2021-12-18 2023-01-01 2022-02-21 2022-06-21 écosystèmes forestiers avec l rest and land management a plantation d'arbres de 17 g roupements du Territoire de Kalehe, composante 2b ZR-CARITAS-253067-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine Kisa participation of the IPLC in fo ngani pour donner l'Educatio TF / A0924 Post Direct Selection Direct 3,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-03-03 2022-07-01 rest and land management n de base et alphabétisation processes related to REDD+ aux PA et Communautés loca les Territoire BANALIA comp osante 1b ZR-CARITAS-253086-CS-CDS / Renouvellement de contrat avec l'ONG FONDATION NSEL Component 2 - Support com ALA pour valorisation des init TF / A0924 munity-based sustainable fo Post Direct Selection Direct 30,761.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2022-02-07 2022-01-13 2022-05-13 iatives locales des plantation rest and land management s d'arbres dans le secteur en tre LUKENI - LOKORO, Territoi re de 0shwe. composante 2a ZR-CARITAS-253090-CS-CDS / Renouvellement de Contrat Component 1 - Reinforce the avec LINAPYCO pour la Colle participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 61,790.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-02-21 2022-06-21 cte des données sur les terre rest and land management s des PA pour la reconnaissa processes related to REDD+ nce légale et la sécurisation des terres. composante 1a Page 4 ZR-CARITAS-253096-CS-CDS / Renouvellement Contrat av ec l'ONG Programme d'intég Component 1 - Reinforce the ration et du développement participation of the IPLC in fo des peuples pygmées (PIDP) TF / A0924 Post Direct Selection Direct 42,300.00 0.00 Signed 2021-12-08 2016-07-01 2021-12-18 2022-12-09 2022-02-21 2022-06-21 rest and land management pour le projet d'amélioration processes related to REDD+ des capacités de production agropastorale des ménages autochtones pygmées dans l e Territoire de Walikale. com pos 2a ZR-CARITAS-253099-CS-CDS / Renouvellement contrat DG Component 1 - Reinforce the PA pour soutien à la finalisati participation of the IPLC in fo on de 4 concessions : Bondo, TF / A0924 Post Direct Selection Direct 106,636.00 0.00 Signed 2021-09-30 2017-07-17 2021-10-10 2017-07-27 2021-12-14 2022-04-13 rest and land management Kombe, Mitshia, Tongonwena processes related to REDD+ forestières des communauté s locales de TSHIEFU / Territo ire de Dimbelenge. composa nte 2b ZR-CARITAS-253095-CS-CDS / Contractualisation avec CA RITAS Kabinda pour le pro d Component 2 - Support com 'appui à la protection du cou TF / A0924 munity-based sustainable fo Post Direct Selection Direct 71,359.00 0.00 Signed 2022-01-27 2022-01-27 2022-02-06 2022-02-18 2022-04-12 2022-08-10 ver forestier par l'agroforeste rest and land management rie, la porciculture et la picic ulture en faveur des peuples autochtones des villages d'E baala et Kangulube, Territoir e de Lubao. c 2a ZR-CARITAS-253087-CS-CDS / Renouvellement de contrat avec l'ONG EQUIPE MIKA pou Component 2 - Support com r la valorisation des initiative TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,500.00 0.00 Signed 2021-12-08 2021-12-08 2021-12-18 2021-12-18 2022-01-13 2022-05-13 s locales des plantations d'ar rest and land management bres dans le secteur de Penz wa, Territoire de Kiri. compos ante 2a ZR-CARITAS-280706-CS-CDS / CAIF- Opérateur pour acco Component 2 - Support com mpagner les communautés ( TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 microprojets et des Opérateu rest and land management rs locaux d'appui aux commu nautés Lubao et Lubefu ZR-CARITAS-280677-CS-CDS / EPAP/RDC: Opérateur pour accompagner les communau Component 2 - Support com tés de Lupatapata et Dimbel TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 enge dans l'identification des rest and land management idées des microprojets et des Opérateurs locaux d'appui au x communautés -Composant e 2.a.1 - Consultant ZR-CARITAS-280720-CS-CDS / Recrutement d'un opérateu r spécialisé, chargé d'organis er des assemblées communa Component 2 - Support com utaires et d'accompagner les TF / A0924 munity-based sustainable fo Post Direct Selection Direct 80,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 PA et communautés locales d rest and land management ans le processus de la reconn aissance formelle de leur con cession forestière et de leurs aires de conservation ZR-CARITAS-280674-CS-CDS / APSVR: Opérateur pour acc ompagner les communautés Component 2 - Support com de Mweka et Dekese dans l'i TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 dentification des idées des m rest and land management icroprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-280683-CS-CDS / OCEAN: Opérateur pour acc ompagner les communautés Component 2 - Support com de Banalia, Bafwasende et M TF / A0924 munity-based sustainable fo Post Direct Selection Direct 12,950.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 ambasa dans l'identification rest and land management des idées des microprojets et des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-280711-CS-CDS / DIPY: Opérateur pour acco mpagner les communautés d Component 2 - Support com 'Inongo et Oshwe dans l'ident TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 ification des idées des micro rest and land management projets et des Opérateurs loc aux d'appui aux communaut és -Composante 2.a.1 – Cons ultant ZR-CARITAS-281043-CS-CDS / Avenant avec ANAPAC pour Component 2 - Support com suivi des dossiers de demand TF / A0924 munity-based sustainable fo Post Direct Selection Direct 27,000.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-12-07 2022-06-24 2022-12-21 e auprès du Ministère de l'en rest and land management vironnement et du Gouverne ment ZR-CARITAS-280020-CS-CDS Component 2 - Support com / Identification des idées des TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-24 2022-12-21 micro-projets dans le territoir rest and land management e de Walikale ZR-CARITAS-280023-CS-CDS / UEFA: Opérateur pour acco mpagner les communautés d Component 2 - Support com e Kalehe dans l'identification TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,800.00 0.00 Signed 2022-04-10 2022-04-10 2022-04-20 2022-04-20 2022-06-10 2022-12-07 des idées des microprojets et rest and land management des Opérateurs locaux d'app ui aux communautés -Compo sante 2.a.1 - Consultant ZR-CARITAS-280659-CS-CDS / FECOFA: Opérateur pour ac compagner les communauté Component 2 - Support com s de Kabinda et Lusambo à l'i TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Signed 2022-04-10 2022-04-20 2022-04-20 2022-10-12 2022-06-24 2022-12-21 dentification des idées des m rest and land management icroprojets et des Opérateurs locaux d'appui aux communa utés -Composante 2.a.1 - Co nsultant ZR-CARITAS-280688-CS-CDS / Contrat REPEQ renforcemen Component 1 - Reinforce the t des capacités dans le cadre participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 5,000.00 0.00 Signed 2022-04-10 2023-04-10 2022-04-20 2023-06-18 2022-06-24 2022-12-21 du plan d’action pour le déve rest and land management loppement et la promotion d processes related to REDD+ es droits des peuples autocht ones en RDC Page 5 Component 1 - Reinforce the ZR-CARITAS-280724-CS-CDS participation of the IPLC in fo / Evaluation externe à mi-par TF / A0924 Post Direct Selection Direct 20,000.00 0.00 Signed 2022-04-10 2023-06-12 2022-04-20 2023-06-18 2022-06-24 2022-12-21 rest and land management cours du projet PACDF processes related to REDD+ ZR-CARITAS-286914-CS-CDS / GTF: Opérateur pour accom pagner les communautés de Component 2 - Support com Yahuma et Opala dans l'ident Under Implement TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 2022-04-10 2023-06-12 2022-04-20 2023-06-18 2022-06-24 2022-12-21 ification des idées des micro ation rest and land management projets et des Opérateurs loc aux d'appui aux communaut és -Composante 2.a.1 – Cons ultant Component 1 - Reinforce the ZR-CARITAS-279788-CS-CQS participation of the IPLC in fo / Contractualisation avec le c TF / A0924 Post Direct Selection Direct 30,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 rest and land management onsultant DGPA processes related to REDD+ ZR-CARITAS-281039-CS-CDS / ANAPAC: accompagner les PA et les COLO dans le proce ssus de la reconnaissance for Component 2 - Support com melle de leurs concessions fo TF / A0924 munity-based sustainable fo Post Direct Selection Direct 250,000.00 0.00 Signed 2022-05-20 2022-05-20 2022-05-30 2022-05-30 2022-08-03 2023-01-30 restières et des aires de cons rest and land management ervation et patrimoine autoc htone et communautaires da ns les sites de Walikale, Bikor o, Kiri, Mambasa et Mweka ZR-CARITAS-280041-CS-CDS / FECOFA: Opérateur pour ac compagner les communauté Component 2 - Support com s de Kabinda et Lusambo dan TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,800.00 0.00 Canceled 2022-04-10 2022-04-10 2022-04-20 2022-06-24 2022-12-21 s l'identification des idées de rest and land management s microprojets et des Opérat eurs locaux d'appui aux com munautés -Composante 2.a.1 - Consultant ZR-CARITAS-281031-CS-CDS / Renouvèlement de contrat Component 1 - Reinforce the avec LINAPYCO pour la Collec participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 120,000.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 te des données sur les terres rest and land management des PA pour la reconnaissanc processes related to REDD+ e légale et la sécurisation de s terres ZR-CARITAS-253083-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de M participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 WEKA pour l'éducation de ba rest and land management se et l'alphabétisation, Territ processes related to REDD+ oire MWEKA composante 1b ZR-CARITAS-300093-CS-CQS / POINT FOCAL: Suivi rapproc Component 2 - Support com Individual Consult Under Implement hé environnemental et social TF / A0924 munity-based sustainable fo Post Direct 3,000.00 0.00 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection ation des activités des microprojet rest and land management s dans le territoire de Walikal e ZR-CARITAS-300099-CS-CQS / POINT FOCAL: Suivi rapproc Component 2 - Support com Individual Consult hé environnemental et social TF / A0924 munity-based sustainable fo Post Direct 3,000.00 0.00 Canceled 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection des activités des microprojet rest and land management s dans le territoire de Kahele ZR-CARITAS-300107-CS-CQS / POINT FOCAL: Suivi rapproc hé environnemental et social Component 2 - Support com Individual Consult Under Implement des activités à Mbuji-Mayi da TF / A0924 munity-based sustainable fo Post Direct 9,000.00 0.00 2022-06-30 2022-10-11 2022-07-10 2022-07-31 2022-09-04 2023-03-03 ant Selection ation ns les territoires de Lupatapa rest and land management ta (Tshintumuanza, Tokomek a et Milela), Kabinda (Ebala - Tulimbi) et Lubao (Kangulube ) ZR-CARITAS-319901-CS-CDS Component 3 - Increase the / ADDEC: Recrutement d'une capacity to implement the IP ONG d'appui à la mise en œu TF / A5550 Post Direct Selection Direct - National 99,373.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 LC development activities a vre de microprojet à Kabala, nd consolidate feedback dans le territoire de Dimbele nge ZR-CARITAS-319916-CS-CDS / UNION POUR LE DEVELOPPE MENT DES MINORITES EKON Component 2 - Support com DA: Recrutement d'une ONG TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 108,749.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-22 2022-12-25 2023-06-23 d'appui à la mise en œuvre d rest and land management e microprojet à MPANGOLA, dans le territoire de LUSAMB O ZR-CARITAS-319961-CS-CDS / FODI: Recrutement d'une O Component 2 - Support com NG d'appui à la mise en œuv TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 104,749.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-20 2022-10-21 2022-12-24 2023-06-22 re de microprojet dans le vill rest and land management age d'Itunga, territoire de Lu befu ZR-CARITAS-319986-CS-CDS / PCF: Recrutement d'une ON Component 1 - Reinforce the G d'appui à la mise en œuvre participation of the IPLC in fo TF / A5550 Post Direct Selection Direct - National 96,509.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 de microprojet à MANGBAUT rest and land management U, KILONDE, et BANANA GITE processes related to REDD+ dans le territoire de MAMBAS A ZR-CARITAS-319996-CS-CDS / CARITAS KABINDA: Recrute Component 2 - Support com ment d'une structure d'appui TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 72,509.00 0.00 Canceled 2022-10-11 2022-10-11 2022-10-21 2022-12-25 2023-06-23 à la mise en œuvre de micro rest and land management projet à TSHINTU MWANZA, MILELA et TOKOMEKA dans le territoire de LUPATAPATA ZR-CARITAS-320000-CS-CDS / ACODELPY: Recrutement d' Component 2 - Support com une ONG d'appui à la mise e TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 99,948.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-11 2022-12-25 2023-06-23 n œuvre de microprojet à BI rest and land management MELI, dans le territoire de BA FWASENDE Page 6 ZR-CARITAS-300080-CS-CDS / LIMA: Promotion des initiati ves de restauration de la forê t, développement des alterna Component 2 - Support com tives économiques compensa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 111,383.50 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 toires aux efforts de la forêt rest and land management et contribution à la cohésion sociale entre les PA et les CO LO à Bomili dans le territoire de Bafwasende. Com 2a ZR-CARITAS-300070-CS-CDS / CARITAS ISANGI: Contributi on à la réduction de la pressi on sur la forêt par l'améliorat Component 2 - Support com ion de la production, commer TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 116,220.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-12-12 2022-12-25 2023-06-23 cialisation du riz, du manioc, rest and land management du miel et l'artisanat en fave ur des PA et des COLO à Yalo nde et Yasamola dans le terri toire de Yahuma. C 2a ZR-CARITAS-300059-CS-CDS / CARITAS ISANGI: Contributi on à la restauration de la for Component 2 - Support com êt, la croissance économique TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 83,056.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-21 2022-12-25 2023-06-23 de 150 ménages cibles et en rest and land management même temps à l'encouragem ent de la cohésion sociale de s PA et CL à Lieke Lesole dan s le territoire d'Opala. Compo sante 2a ZR-CARITAS-300115-CS-CDS / LIMA: Promotion des initiati ves de restauration de la forê t, développement des alterna Component 2 - Support com tives économiques compensa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 111,383.50 0.00 Canceled 2022-10-11 2022-10-21 2022-12-25 2023-06-23 toires aux efforts de la forêt rest and land management et contribution à la cohésion sociale entre les PA et les CO LO à Bangbo dans le territoir e de Banalia. Comp 2a ZR-CARITAS-280716-CS-CDS / Consultant Kasongo Kabusa Component 2 - Support com Individual Consult Raphael, Chargé d’identificat TF / A0924 munity-based sustainable fo Post Direct - National 8,000.00 0.00 Signed 2022-10-11 2022-10-11 2022-10-21 2022-10-22 2022-11-11 2022-11-11 2022-12-16 2023-06-14 ant Selection ion des expériences de mise rest and land management en œuvre des microprojets c ommunautaires ZR-CARITAS-320534-CS-CDS / CARITAS KOLE: Recrutemen Component 2 - Support com t d'une ONG d'appui à la mis TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 99,603.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-12-26 2023-06-24 e en œuvre de microprojet à rest and land management ITUNGA dans le territoire de DEKESE. Comp 2a ZR-CARITAS-320537-CS-CDS / CEDAP: Recrutement d'une ONG locale pour la mise en œuvre du projet de restaurat Component 2 - Support com ion de la foret d'Itungampen TF / A5550 munity-based sustainable fo Post Direct Selection Direct - National 105,094.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-12-26 2023-06-24 de à travers la plantation d'a rest and land management rbres et le développement de s alternatives économiques pour lutter contre la dégrada tion de la foret. Comp 2a ZR-CARITAS-320542-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com nt d'un consultant pour le sui Individual Consult TF / A5550 munity-based sustainable fo Post Direct - National 5,200.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 vi environnemental et social ant Selection rest and land management dans les territoires de BAFW ASENDE, YAHUMA, OPALA et BANALIA ZR-CARITAS-320547-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 1,000.00 0.00 Signed 2022-10-11 2022-11-21 2022-10-21 2022-11-26 2022-11-11 2022-12-17 2022-12-16 2023-06-14 ant Selection vi environnemental et social rest and land management dans le territoire de MAMBAS A ZR-CARITAS-320549-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 4,200.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 ant Selection vi environnemental et social rest and land management dans les territoires de MWEK A, DEKESE et DIMBELENGE ZR-CARITAS-320552-CS-IND V / POINT FOCAL: Recruteme Component 2 - Support com Individual Consult nt d'un consultant pour le sui TF / A5550 munity-based sustainable fo Post Direct - National 3,400.00 0.00 Signed 2022-10-12 2022-11-21 2022-10-22 2022-12-01 2022-11-12 2022-12-22 2022-12-17 2023-06-15 ant Selection vi environnemental et social rest and land management dans les territoires de LUSAM BO ET LUBEFU ZR-CARITAS-253070-CS-CDS / Renouvellement contrat Car Component 1 - Reinforce the itas Mbujimayi pour donner l' participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 5,400.00 0.00 Canceled 2021-12-08 2021-07-08 2021-12-18 2022-02-24 2022-06-24 éducation de base et alphab rest and land management étisation aux PA et communa processes related to REDD+ utés locales territoire de LUP ATAPATA composante 1b ZR-CARITAS-253063-CS-CDS / Renouvellement contrat av Component 1 - Reinforce the ec Caritas diocèse Kananga p participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-02-21 2022-06-21 our l'Education de base des P rest and land management A et communautés locales Te processes related to REDD+ rritoire de Dimbelenge comp 1b ZR-CARITAS-253084-CS-CDS Component 1 - Reinforce the / Renouvellement contrat av participation of the IPLC in fo ec Caritas diocésaine de WA TF / A0924 Post Direct Selection Direct 12,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-02-21 2022-06-21 rest and land management MBA Alphabétisation Dio WA processes related to REDD+ MBA - MAMBASA ET BAFWAS ENDE composante 1b ZR-CARITAS-253082-CS-CDS Component 1 - Reinforce the / Renouvellement de contrat participation of the IPLC in fo avec Caritas BUKAVU sur l'Al TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2020-09-22 2022-02-21 2022-06-21 rest and land management phabétisation Dio BUKAVU, T processes related to REDD+ erritoire de KALEHE composa nte 1b ZR-CARITAS-253089-CS-CDS Component 1 - Reinforce the / Renouvellement de Contrat participation of the IPLC in fo avec DGPA pour Suivi des loi TF / A0924 Post Direct Selection Direct 30,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 rest and land management au Parlement et lutte contre l processes related to REDD+ a discrimination pour les PA. composante 1a Page 7 ZR-CARITAS-280035-CS-CDS / CAIF- Opérateur pour acco Component 2 - Support com mpagner les communautés à TF / A0924 munity-based sustainable fo Post Direct Selection Direct 9,900.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 l’identification des micro-proj rest and land management ets pour les territoires de Lub ao et Lubefu ZR-CARITAS-253092-CS-CDS / Renouvellement de Contrat avec l'ONG Programme d'inté Component 1 - Reinforce the gration et du développement participation of the IPLC in fo des peuples pygmées (PIDP) TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-01-13 2022-05-13 rest and land management pour l'éducation de base et l' processes related to REDD+ alphabétisation aux peuples autochtones (PA ) et aux com munautés locales (COLO) po ur le Territoire de Walikale. c 1b ZR-CARITAS-253073-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de d participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-05-31 2022-09-28 e KOLE pour l'éducation de b rest and land management ase et l'alphabétisation des P processes related to REDD+ A et COLO Territoire de DEKE SE composante 1b ZR-CARITAS-253088-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocèse d'ISANG participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 12,000.00 0.00 Canceled 2021-12-08 2021-12-27 2021-12-18 2022-01-15 2022-02-21 2022-06-21 I, territoire de YAHUMA et OP rest and land management ALA pour l'éducation de bas processes related to REDD+ e et l'alphabétisation. compo sante 1b ZR-CARITAS-280699-CS-CDS / Identification des idées des Component 2 - Support com microprojets et des organisat TF / A0924 munity-based sustainable fo Post Direct Selection Direct 5,900.00 0.00 Canceled 2022-04-10 2022-04-20 2022-06-24 2022-12-21 ions et site d'implémentation rest and land management du microprojet à Walikale ZR-CARITAS-253081-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine de K participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-03-08 2022-07-06 ABINDA pour l'alphabétisatio rest and land management n , Territoire KABINDA, LUBA processes related to REDD+ O et LUSAMBO composante 1 b ZR-CARITAS-294564-CS-CQS Component 3 - Increase the / Recrutement d'un auditeur capacity to implement the IP Individual Consult externe pour la révision du m TF / A0924 Post Direct 3,000.00 0.00 Canceled 2022-06-24 2022-10-11 2022-07-04 2022-07-25 2022-08-29 2023-02-25 LC development activities a ant Selection anuel des procédures admini nd consolidate feedback stratives et financières du pr ojet PACDF ZR-CARITAS-242600-CS-IND Component 3 - Increase the V / Recrutement d'un consult capacity to implement the IP Individual Consult ant individuel pour la révisio TF / A0924 Post Limited 4,000.00 0.00 Canceled 2021-07-30 2021-08-04 2021-08-25 2021-09-29 2021-11-13 LC development activities a ant Selection n du manuel des procédures nd consolidate feedback administratives et financière s du projet PCDF ZR-CARITAS-362380-CS-CDS Component 3 - Increase the / Recrutement d'un Consulta capacity to implement the IP Individual Consult Direct - Internation nt International pour l'évalua TF / A0924 Post 10,000.00 0.00 Canceled 2023-05-30 2023-05-30 2023-06-09 2023-06-04 2023-06-30 2023-08-04 2024-01-31 LC development activities a ant Selection al tion final et la rédaction du r nd consolidate feedback apport d'achèvement du pro jet ZR-CARITAS-362377-CS-CDS Component 3 - Increase the / Recrutement d'un Consulta capacity to implement the IP Individual Consult nt National pour l'appui à l'év TF / A0924 Post Direct - National 10,000.00 0.00 Signed 2023-05-30 2023-05-30 2023-06-09 2023-06-04 2023-06-30 2023-06-25 2023-08-04 2024-01-31 LC development activities a ant Selection aluation finale et à la rédacti nd consolidate feedback on du rapport d'achèvement du projet ZR-CARITAS-253079-CS-CDS / Renouvellement de contrat Component 1 - Reinforce the avec Caritas diocésaine d'IN participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 18,000.00 0.00 Canceled 2021-12-08 2020-09-08 2021-12-18 2022-02-21 2022-06-21 ONGO, territoire de KIRI, OS rest and land management WE et INONGO pour l'éducat processes related to REDD+ ion de base et l'alphabétisati on. composante 1b ZR-CARITAS-253068-CS-CDS / Renouvellement contrat av Component 1 - Reinforce the ec Caritas diocésaine TSHUM participation of the IPLC in fo TF / A0924 Post Direct Selection Direct 6,000.00 0.00 Canceled 2021-12-08 2021-12-08 2021-12-18 2022-01-20 2022-05-20 BE pour Education de Base et rest and land management Alphabétisation aux PA et co processes related to REDD+ mmunautés locales territoire de LUBEFU composante 1b ZR-CARITAS-365668-CS-CDS / CIDB: Identification des idée Component 2 - Support com s des microprojets communa TF / A0924 munity-based sustainable fo Post Direct Selection Direct - National 9,800.00 0.00 Signed 2023-06-06 2023-06-12 2023-06-16 2023-06-18 2023-08-20 2024-02-16 utaires et des opérateurs loc rest and land management aux d'appui aux communaut és à Bikoro-Kiri ZR-CARITAS-365674-NC-DIR / OSAPY: Appuyer l'élaboratio n des cartes des terroirs com Component 1 - Reinforce the munautaires et des plans d'a participation of the IPLC in fo Under Implement TF / A0924 Post Direct Selection Direct - National 150,000.00 0.00 2023-06-12 2023-06-25 2023-06-22 2023-06-29 2023-08-26 2024-02-22 ménagement et de gestion si rest and land management ation mplifiée des concessions fore processes related to REDD+ stières des COLO et des aires de patrimoine ou aires de co nservation des PA et des COL O Page 8 PROCUREMENT PLAN (Textual Part) Project information: Sindh Flood Emergency Rehabilitation Project (P179981) Project Implementation agency(ies): (i) Sindh Planning & Development Department (ii) Sindh Irrigation Department Date of the Procurement Plan: December 2022 Period covered by this Procurement Plan: June 30 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in public procurement rules such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is not allowed Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Sindh Flood Emergency Rehabilitation Project PLAN General Information Country: Pakistan 2023-01-17 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P179981 GPN Date: 2023-01-19 Project Name: Sindh Flood Emergency Rehabilitation Project Loan / Credit No: IDA / 72500 Province of Sindh Irrigation Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-POSID-336211-CW-RFB / Rehabilitation/ Construction Single Stage - One E Other (with field f Under Imple 2024-03-1 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 5,681,818.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 of Additional Outfall Regulato nvelope or explanation) mentation 1 r Along Ochitto Outfall Drain and Leading Channel. PK-POSID-336212-CW-RFB / Single Stage - One E Other (with field f Pending Imp 2024-03-1 Rehabilitation of Main East Br IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 1,006,738.00 0.00 2023-01-13 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) lementation 1 anch Nawabshah. PK-POSID-336213-CW-RFB / Single Stage - One E Other (with field f Under Imple 2024-03-1 Rehabilitation of Shikarpur Br IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 258,748.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) mentation 1 . Drain system. PK-POSID-336214-CW-RFB / Rehabilitation of Pharho Esca Single Stage - One E Other (with field f Under Imple 2024-03-1 pe from RD 0+000 to 30+00 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 139,273.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) mentation 1 0 Both Sides in KhairpurGam bo Sub Division of Nasir Divis ion. PK-POSID-336215-CW-RFB / Raising and Rehabilitation (E arthwork) along Oderolal Esc Single Stage - One E Other (with field f Under Imple 2024-03-1 ape from RD 0+000 to 71+0 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 2,250,000.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 nvelope or explanation) mentation 1 00 NIP Side i/c installation of new gates to increase capaci ty of water to enable escape discharge in Indus River. PK-POSID-336216-CW-RFB / Single Stage - One E Other (with field f 2024-03-1 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 652,658.00 0.00 Canceled 2023-01-13 2023-01-13 2023-01-24 2023-02-23 2023-03-13 Rehabilitation of Karampur Ri nvelope or explanation) 1 ng Bund. PK-POSID-336217-CW-RFB / Single Stage - One E Other (with field f Under Imple 2024-03-1 IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 1,590,120.00 0.00 2023-01-13 2022-12-19 2023-01-13 2023-01-24 2023-02-23 2023-03-13 Rehabilitation of Suprio Bund nvelope or explanation) mentation 1 . PK-POSID-336218-CW-RFB / Package No. 1 Lot No. 1 Floo d Detention Dam Lat-01 (DD/ Single Stage - One E Other (with field f 2024-03-1 W-L01 along LatNai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,586,543.00 0.00 Signed 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-02-20 2023-03-20 nvelope or explanation) 8 Lot No.2 Floo d Detention Dam Lat-02 (DD/ W-L02 along LatNai). PK-POSID-336219-CW-RFB / Package No. 2 Lot No. 1 Floo d Detention Dam Lat-03 (DD/ Single Stage - One E Other (with field f 2024-03-1 W-L03 along LatNai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,919,065.00 0.00 Signed 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-02-20 2023-03-20 nvelope or explanation) 8 Lot No. 2 Flo od Detention Dam Lat-04 (D D/W-L04 along LatNai). PK-POSID-336220-CW-RFB / Single Stage - One E Other (with field f 2024-03-1 Package No.3 Flood Detentio IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 4,597,684.00 0.00 Signed 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-02-20 2023-03-20 nvelope or explanation) 8 n Dam Mole-02 (DD/W-M2 al ong Mole Nai). PK-POSID-336221-CW-RFB / Package No. 4 Lot No. 1 Floo d Detention Dam Mole-03 (D Single Stage - One E Other (with field f 2024-03-1 D/W-M3 along Mole Nai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,993,696.00 0.00 Signed 2023-01-13 2022-12-26 2023-01-13 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-03-07 2023-03-20 nvelope or explanation) 8 Lot No. 2 Floo d Detention Dam Mole-04 (D D/W-M4 along Mole Nai). PK-POSID-336223-CW-RFB / Package No. 5 Lot No. 1 Floo d Detention Dam Mole-05 (D Single Stage - One E Other (with field f 2024-03-1 D/W-M5 along Mole Nai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 8,779,468.00 0.00 Signed 2023-01-14 2022-12-26 2023-01-14 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-02-20 2023-03-20 nvelope or explanation) 8 Lot No. 2 Floo d Detention Dam Mole-06 (D D/W-M6 along Mole Nai). PK-POSID-336225-CW-RFB / Package No. 6 Lot No.1 Floo d Detention Dam Mole-07 (D Single Stage - One E Other (with field f 2024-03-1 D/W-M7 along Mole Nai). IDA / 72500 Infrastructure Rehabilitation Post Request for Bids Open - National 7,608,233.00 0.00 Signed 2023-01-14 2022-12-26 2023-01-14 2023-01-25 2023-01-31 2023-01-31 2023-03-02 2023-03-07 2023-03-20 nvelope or explanation) 8 Lot No. 2 Flo od Detention Dam Mole -08 ( DD/W-M8 along Mole Nai). PK-POSID-336067-CW-DIR / Other (with field f 2023-04-2 Rehabilitation OF Manchar C IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,251,592.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 ONTAINING BUND (RD 0+000 TO 27+000 ). PK-POSID-336093-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF DANISTA IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,682,097.00 0.00 Signed 2023-01-13 2022-11-14 2023-01-13 2022-11-15 2023-01-21 or explanation) 1 R CANAL (RD 0+000 TO 27+ 440). PK-POSID-336083-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF DHORO IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,427,760.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 PURAN RD 176+400 to 210+ 000. PK-POSID-336069-CW-DIR / REHABILITATION OF MANCHA Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,483,243.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 R CONTAINING BUND (RD 54 or explanation) 1 +000 TO 77+000 ). Page 1 PK-POSID-336074-CW-DIR / Other (with field f 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,543,288.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 or explanation) 1 380+000 to RD 445+000). PK-POSID-336077-CW-DIR / Rehabilitation of FP Bund (RD Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,748,317.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 490+000 to RD 502+000 & R or explanation) 1 D 263+000 to RD 220+000). PK-POSID-336079-CW-DIR / Other (with field f 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,492,892.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 or explanation) 1 220+000 to RD 169+000). PK-POSID-336085-CW-DIR / REHABILITATION OF DHORO Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,318,122.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 PURAN RD 210+000 TO 222 or explanation) 1 +130 AND MAIN DRAIN RD 2 12+300 TO 217+600. PK-POSID-336075-CW-DIR / Other (with field f 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,604,680.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 445+000 to RD 490+000). PK-POSID-335890-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 635,481.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 or explanation) 9 of Breach along Saifullah Ma gsi Branch. PK-POSID-335912-CW-DIR / Other (with field f 2023-02-1 Plugging, Strengthening Rest IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 930,558.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 or explanation) 9 oration and Rehabilitation of Dhamrah Wah. PK-POSID-335914-CW-DIR / Replacement / Supply and In stallation of Motor Pump (10 Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,074,545.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 0 H.P) Including All Accessori or explanation) 0 es Along Ghaar, Shahmeer, Mehar, Mashori, K.N.Shah, Mi ro Khan and Agani Pumping Stations. PK-POSID-335916-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 977,477.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 of Breach along Main Nara V or explanation) 9 alley (MNV) Drain at RD 280. PK-POSID-335928-CW-DIR / Other (with field f Under Imple 2023-02-1 Closing of cuts alog Rohri Mai IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 469,559.00 0.00 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 or explanation) mentation 9 n Canal, Moro Division. PK-POSID-335933-CW-DIR / Plugging And Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,022,523.00 0.00 Signed 2023-01-12 2022-10-28 2023-01-12 2022-10-31 2023-01-20 Of Relief Cut Along Johi Branc or explanation) 9 h Along Rd 80 To Rd 86 And Rd 95 To Rd 98. PK-POSID-335862-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 226,695.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 or explanation) 9 of Breach along FP Bund alon g 169+000. PK-POSID-335917-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 309,602.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 of Breach along Main Nara V or explanation) 9 alley (MNV) Drain at RD 330. PK-POSID-335893-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 407,933.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 of Breaches / Cuts Along Gha or explanation) 9 r Main Drain & Leading Chan nel. PK-POSID-335905-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 782,058.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 or explanation) 9 of Breaches / Cuts Along Miro Khan Main Drain. PK-POSID-335919-CW-DIR / Plugging, Strengthening and Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 346,364.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 Stone Pitching of Breach alon or explanation) 9 g Superio Bund RD 12. PK-POSID-335920-CW-DIR / Plugging, Strengthening and Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 249,294.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 Stone Pitching of Breach alon or explanation) 9 g Superio Bund RD 28. PK-POSID-336089-CW-DIR / REMODELING AND REHABILIT Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 6,486,130.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 ATION OF ARAL HEAD REGUL or explanation) 1 ATOR (MC RD 0+000). PK-POSID-336087-CW-DIR / REHABILITATION OF OUTFALL Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,482,485.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 STRUCTURE AT RD 210+000 or explanation) 1 OF DHORO PURAN. PK-POSID-336070-CW-DIR / REHABILITATION OF MANCHA Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,542,517.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 R CONTAINING BUND (RD 77 or explanation) 1 +000 TO 100+000). PK-POSID-336071-CW-DIR / Other (with field f 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,475,187.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 160+000 to RD 210+000). PK-POSID-335923-CW-DIR / Plugging, Strengthening and Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 60,393.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 Stone Pitching of Breach alon or explanation) 9 g Superio Bund RD 42. PK-POSID-336091-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF LEFT AR IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,156,718.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 or explanation) 1 AL BUND RD 0+000 TO RD 1 9+000. PK-POSID-335931-CW-DIR / Other (with field f 2023-02-1 Repair of Rain Damages of S IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,397,355.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 or explanation) 9 mall Dams Under Small Dam s Organization. Page 2 PK-POSID-335855-CW-DIR / Plugging, Strengthening & St Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 219,056.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 one Pitching of Relief Cut Lar or explanation) 9 kana Sehwan Bund along Mil e 95/6. PK-POSID-336080-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF DHORO IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,250,317.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 PURAN RD 110+000 TO 143 +330. PK-POSID-335851-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,249,943.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 of Relief Cut along Manchar or explanation) 9 Containing Bund at RD 52+0 00. PK-POSID-335854-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,133,842.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 of Breach along Main Nara V or explanation) 9 aley (MNV) Drain at RD 8+06 8. PK-POSID-335887-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 180,708.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 or explanation) 9 of Breach along FP Bund alon g RD 476+000. PK-POSID-336081-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF DHORO IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,491,000.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 or explanation) 1 PURAN RD 143+330 TO 176 +400. PK-POSID-335925-CW-DIR / Plugging, Strengthening and Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 189,836.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 Stone Pitching of Breach alon or explanation) 9 g Superio Bund RD 52. PK-POSID-335929-CW-DIR / Other (with field f 2023-02-1 Repair of Rain Damages Sma IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,912,465.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 or explanation) 9 ll Dams Under Sindh Resilien ce Project (SRP). PK-POSID-335898-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 493,189.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 of Breaches Along K.N Shah or explanation) 9 Main Drain & Leading Chann el. PK-POSID-335927-CW-DIR / Plugging, Strengthening and Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 44,676.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 Stone Pitching of Breach alon or explanation) 9 g Superio Bund RD 82. PK-POSID-335858-CW-DIR / Plugging, Strengthening & St Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 906,846.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 one Pitching of Relief Cut Lar or explanation) 9 kana Sehwan Bund along Mil e 97/2. PK-POSID-335873-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,452,498.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 or explanation) 9 of Breach along FP Bund alon g RD 340+000. PK-POSID-335915-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 802,253.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 of Breach along Main Nara V or explanation) 9 alley (MNV) Drain at RD 210. PK-POSID-335821-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,135,696.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 of Relief Cut along Manchar or explanation) 9 Containing Bund at RD 14+0 00. PK-POSID-335903-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 385,539.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 of Breaches / Cuts Along Sha or explanation) 9 hdad Kot Branch Drain. PK-POSID-336068-CW-DIR / REHABILITATION OF MANCHA Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,538,878.00 0.00 Signed 2023-01-13 2022-10-21 2023-01-13 2022-10-24 2023-01-21 R CONTAINING BUND (RD 27 or explanation) 1 +000 TO 54+000 ). PK-POSID-336072-CW-DIR / Other (with field f 2023-04-2 Rehabilitation of FP Bund (RD IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,524,135.00 0.00 Signed 2023-01-13 2022-10-28 2023-01-13 2022-10-31 2023-01-21 or explanation) 1 325+000 to RD 380+000). PK-POSID-336094-CW-DIR / Other (with field f 2023-04-2 REHABILITATION OF DANISTA IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,633,010.00 0.00 Signed 2023-01-13 2022-11-14 2023-01-13 2022-11-15 2023-01-21 or explanation) 1 R CANAL (RD 27+440 TO 56 +434). PK-POSID-335860-CW-DIR / Plugging, Strengthening & St Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,231,284.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 one Pitching of Relief Cut Lar or explanation) 9 kana Sehwan Bund along Mil e 99/3. PK-POSID-335909-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,075,286.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 or explanation) 9 of Breach Along F.P Bund Rd 432. PK-POSID-335932-CW-DIR / Repair of Gaj Diversion Bund Other (with field f 2023-02-1 ledge and stone apron from IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,342,347.00 0.00 Signed 2023-01-12 2022-10-14 2023-01-12 2022-10-17 2023-01-20 or explanation) 9 RD 3-11, Repair of Gaj Divers ion Bund stone apron from R D 15-32.5. PK-POSID-335867-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 552,124.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 or explanation) 9 of Breach along FP Bund alon g RD 215+000. PK-POSID-335853-CW-DIR / Plugging and Strengthening Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,361,326.00 0.00 Signed 2023-01-12 2022-09-26 2023-01-12 2022-09-28 2023-01-20 of Breach along Main Nara V or explanation) 9 aley (MNV) Drain at RD 2+31 8. PK-POSID-335908-CW-DIR / Other (with field f 2023-02-1 Plugging and Strengthening IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,747,581.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 or explanation) 9 of Breaches Along Indus Link Drain. Page 3 PK-POSID-336092-CW-DIR / REMODELING AND REHABILIT Other (with field f 2023-04-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,469,384.00 0.00 Signed 2023-01-13 2022-11-14 2023-01-13 2022-11-15 2023-01-21 ATION OF ARAL WAH (RD 1+ or explanation) 1 250 TO RD 0+000 & RD 0+0 00 TO 14+000). PK-POSID-336095-CW-DIR / Remodeling and Rehabilitatio Other (with field f 2023-04-2 n of Danister Tail Regulator a IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 2,745,403.00 0.00 Signed 2023-01-13 2022-11-14 2023-01-13 2022-11-15 2023-01-21 or explanation) 1 nd Regulator for 10 Phats (Mi nors) Danister Canal (Civil W orks). PK-POSID-343948-CW-DIR / Other (with field f 2023-05-2 Rehabilitation Of Old Water IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 173,193.00 0.00 Signed 2023-02-20 2022-12-07 2023-02-20 2022-12-09 2023-02-28 or explanation) 9 Way In Desert Area Of Khairp ur. Request for Quota PK-POSID-341482-CW-RFQ / Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-12-1 Rehabilitation of Talpur Wad IDA / 72500 Infrastructure Rehabilitation Post Limited 530,161.00 0.00 2023-02-24 2023-03-17 tions nvelope s (Emergency) SP mentation 2 a Pumping Station And Water D -Competitive Carrier Drain. PK-POSID-341480-CW-RFQ / Request for Quota Rehabilitation of Syphon at A Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Limited 294,021.00 0.00 2023-02-24 2023-03-17 li Bahar Branch And Rehabilit tions nvelope s (Emergency) SP mentation 2 ation of Syphon at Kubri Mino D -Competitive r. Request for Quota PK-POSID-341483-CW-RFQ / Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-12-1 Rehabilitation of G & F Pumpi IDA / 72500 Infrastructure Rehabilitation Post Limited 752,713.00 0.00 2023-02-24 2023-03-17 tions nvelope s (Emergency) SP mentation 2 ng Station. D -Competitive Request for Quota PK-POSID-341485-CW-RFQ / Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-12-1 Rehabilitation of Karampur Ri IDA / 72500 Infrastructure Rehabilitation Post Limited 527,885.00 0.00 2023-02-24 2023-03-17 tions nvelope s (Emergency) SP mentation 2 ng Bund. D -Competitive PK-POSID-335901-CW-DIR / Other (with field f 2023-02-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 337,811.00 0.00 Signed 2023-01-12 2022-10-05 2023-01-12 2022-10-07 2023-01-20 Rehabilitation Of Mehar Main or explanation) 9 Drain. PK-POSID-348241-CW-DIR / Rehabilitation of F.P Bund (R Other (with field f 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,507,304.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 D 0+000 to RD 20+000 & RD or explanation) 2 75+000 to RD 160+000). PK-POSID-348243-CW-DIR / Other (with field f 2023-12-1 Rehabilitation of F.P Bund (R IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,533,536.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 or explanation) 2 D 210+000 to RD 265+000). PK-POSID-348244-CW-DIR / Other (with field f 2023-12-1 Rehabilitation of F.P Bund (R IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,506,334.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 or explanation) 2 D 265+000 to RD 325+000). PK-POSID-348246-CW-DIR / Rehabilitation of Gates in Ara Other (with field f 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,361,791.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 l Head Regulator, Dainster Ta or explanation) 2 il Regulator and 10 Phats (Mi nors) Regulators. PK-POSID-348248-CW-DIR / Rehabilitation of Retaining W Other (with field f 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 4,976,266.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 all (3 RDs) along Danistar Ca or explanation) 2 nal (Bubak/Miani Town). PK-POSID-348251-CW-DIR / Other (with field f 2023-12-1 Rehabilitation of Irrigation W IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 3,348,712.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 or explanation) 2 orks on Johi Branch. PK-POSID-348254-CW-DIR / Remodeling of Shaheed Bena Other (with field f 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 5,891,955.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 zirabad Stormwater Drain (R or explanation) 2 D 0+000 to 16+556). PK-POSID-348257-CW-DIR / Remodeling of Shaheed Bena Other (with field f 2023-12-1 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 5,558,022.00 0.00 Signed 2023-03-09 2022-12-07 2023-03-09 2022-12-09 2023-03-17 zirabad Stormwater Drain (R or explanation) 2 D 13+320+ to RD 26+223). PK-POSID-356470-CW-DIR / Construction of new T-head S pur along Ruk loop bund mile 0/0+200, 04 Nos. Stone Stud Other (with field f 10,393,757.0 2024-01-2 s, providing stone pitching, st IDA / 72500 Infrastructure Rehabilitation Prior Direct Selection Direct - National 0.00 Signed 2023-04-14 2023-04-17 2023-04-14 2023-04-26 2023-04-27 2023-06-09 or explanation) 0 2 one apron along Rukh loop b und mile 0/0 to 0/5 and Ghu mra loop bund mile 4/6 & pro viding stone pitching and apr on at remaining portions. PK-POSID-356505-CW-DIR / Rehabilitation/Re-Constructio Other (with field f 2024-01-2 IDA / 72500 Infrastructure Rehabilitation Post Direct Selection Direct - National 1,957,566.00 0.00 Signed 2023-04-14 2023-04-14 2023-04-14 2023-04-14 2023-04-27 n of Regulator Mile 44th of D or explanation) 2 esert Canal. Damaged during floods 2022. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-POSID-353032-GO-RFQ / Project Management and Op Request for Quota Single Stage - One E IDA / 72500 Post Limited 107,410.00 0.00 Signed 2023-04-03 2023-04-03 2023-04-25 2023-10-22 Procurement of Vehicles. erational Costs tions nvelope PK-POSID-364645-GO-RFQ / Project Management and Op Request for Quota Single Stage - One E Under Imple Procurement of IT Equipment IDA / 72500 Post Limited 14,000.00 0.00 2023-06-01 2023-06-02 2023-06-08 2023-07-08 erational Costs tions nvelope mentation for Office use. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 4 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-POSID-342908-CS-QCBS / Institutional Strengthening f Forensic Analysis of 2022 Flo Quality And Cost- Open - Internationa IDA / 72500 or Resilience and Technical Prior 1,500,000.00 0.00 Under Review 2023-02-16 2023-02-20 2023-04-06 2023-05-11 2023-06-10 2023-06-27 2023-07-07 2024-07-06 ods and Mitigation Options o Based Selection l Assistance n the Right Bank of Indus. PK-POSID-364945-CS-CQS / Project Management and Op Consultant Qualifi Under Implement IDA / 72500 Post Limited 75,000.00 0.00 2023-06-02 2023-06-08 2023-06-12 2023-06-19 2023-06-26 2026-06-25 The Hiring of Internal Audit Fi erational Costs cation Selection ation rm. PK-POSID-364947-CS-CQS / Environmental and Social Saf Project Management and Op Consultant Qualifi eguard Management Implem IDA / 72500 Post Limited 100,000.00 0.00 Under Review 2023-06-02 2023-06-08 2023-06-12 2023-06-19 2023-06-26 2024-03-22 erational Costs cation Selection entation and Monitoring Of R ehabilitation of Dhoro Puran Works. PK-POSID-366420-CS-QCBS / Institutional Strengthening f Hiring of Consultancy Service Quality And Cost- Open - Internationa Pending Impleme IDA / 72500 or Resilience and Technical Prior 1,200,000.00 0.00 2023-06-12 2023-06-19 2023-08-18 2023-09-15 2023-09-29 2023-11-03 2023-12-01 2024-11-30 s for Designing Flood Detenti Based Selection l ntation Assistance on Weirs and Flood Affected Embankments. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-POSID-344014-CS-CDS / Institutional Strengthening f Development & Integration o Direct - Internation IDA / 72500 or Resilience and Technical Post Direct Selection 949,373.00 0.00 Signed 2023-02-20 2023-03-05 2023-03-01 2023-03-15 2023-04-04 2024-04-02 f Kirthar Model and Operatio al Assistance ns & Maintenance of Data Ce nter. PK-POSID-346415-CS-INDV / Project Management and Op Individual Consult The Hiring of Project Director IDA / 72500 Post Open - National 101,533.00 0.00 Signed 2023-03-01 2023-03-17 2023-03-29 2023-06-02 2023-04-03 2023-06-02 2023-04-12 2025-04-09 erational Costs ant Selection (Market Based). PK-POSID-349520-CS-INDV / Project Management and Op Individual Consult The Hiring of Gender Speciali IDA / 72500 Post Open - National 12,915.00 0.00 Signed 2023-03-14 2022-11-20 2023-04-06 2022-12-16 2023-04-07 2022-12-26 2023-04-13 2024-04-11 erational Costs ant Selection st for SFERP. PK-POSID-349526-CS-INDV / Project Management and Op Individual Consult The Hiring of Environment Co IDA / 72500 Post Open - National 12,915.00 0.00 Signed 2023-03-14 2022-11-20 2023-04-06 2022-12-16 2023-04-07 2022-12-26 2023-04-13 2024-04-11 erational Costs ant Selection nsultant for SFERP. PK-POSID-349551-CS-INDV / Project Management and Op Individual Consult The Hiring of Social Safeguar IDA / 72500 Post Open - National 12,915.00 0.00 Signed 2023-03-14 2022-11-20 2023-04-06 2022-12-16 2023-04-07 2022-12-26 2023-04-13 2024-04-11 erational Costs ant Selection d Consultant for SFERP. Page 5 18 MONTHS PROCUREMENT PLAN- (FINES) I. General 1.Project information Country: Malawi Project Name: Financial Inclusion and Entrepreneurship Scaling (FINES) Project ID: P168577 2.Project Implementation Agency: Reserve Bank of Malawi 3.Date of the Procurement Plan: January 2020 4.Period covered by this Procurement Plan: March 2020 to December 2021 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Disposal of Public Assets Act, 2017 of the Republic of Malawi, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit Page 1 of 8 rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable for those contracts identified in the Procurement Plan tables; Works: Not Applicable for those contracts identified in the Procurement Plan tables. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable. Other Relevant Procurement Information: - (a) Procurement Approach and Prior Review Thresholds: The Procurement Arrangements as indicated in the below table will be used. The thresholds for the Bank’s prior review requirements are also provided in the table: Prior-review Thresholds for Procurement Methods Thresholds Procurem Substanti Works Goods, IT & Non-Consulting Shortlist of National ent al Services Consultants Type Risk ($`000) Works 10,000 Open Request Request Internatio for Engineerin Open Open for nal or Quotatio Open g& Nation Nationa Quotatio Consulting n or internatio Constructio al or l or n or Services ICB National nal or ICB n NCB NCB National ($'000) ($'000 Shoppin ($'000) Supervision ($'000) ($'000) Shopping g ($'000) ($'000) ($'000) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultan 1,000 ts (Firms) 7,000 7,000 200 1,000 1,000 100 200 300 Individual 300 Consultan ts Page 2 of 8 *These prior review thresholds are for the purposes of the initial procurement plan for the first 18 months. The thresholds will be revised periodically based on re-assessment of risks. All contracts not subject to prior review will be post-reviewed. Prequalification. Not expected for the works/goods packages in the procurement plan. Proposed Procedures for CDD Components: Not Applicable Reference to (if any) Project Operational/Procurement Manual: The Ministry of Agriculture Irrigation and Water Development team will prepare Procurement manuals. The Procurement Plan will also form part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Page 3 of 8 Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: b) PROCUREMENT PLAN Works 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequalifica Domestic Review Expected bid Expected Comme No. Method/ tion Preferen opening date Contract nts (Description) Cost Arrangement (yes/no) ce by Bank Signature (yes/no) Date US$ million (Prior / Post) 1. Minor works for 200,000.00 Open, National, Post No Post September 11, October maintenance of PIU offices RFB 2020 16, 2020 Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procurement Prequalific Domestic Review Expected bid Expected Comme No. (Description) Cost Method/ ation Preferenc by Bank opening date Contract nts US$ million Arrangement (yes/no) e (Prior / Signature (yes/no) Post) Date 1. Procurement of 8 motor 550,000.00 Open National, Post No Post Sept 11, 2020 Nov 16, 2020 vehicles RFB 2. Procurement of office 500,000.00 Open National, Post No Post August 07, 2020 August 31, furniture, ICT equipment RFB 2020 and system upgrades 3. Procurement of an ICT 300,000.00 Open National, Post No Post February 15, March 30, system for proper stress RFB 2021 2021 testing by the Reserve Bank’s Supervision Department 4. Procurement of a 150,000.00 Open National, Post No Post February 15, March 30, surveillance system for the RFB 2021 2021 securities market 5. Procurement of an 100,000.00 Open National, Post No Post February 15, March 30, integrated risk RFB 2021 2021 management system for Deposit Insurance Scheme (DIS) Page 4 of 8 Consultancy Services 1 2 3 4 5 6 7 8 Ref. No. Description of Assignment Estimated Selection Review Expected date Expected Comment Cost Method/ by Bank of proposal Contract s US$ Arrangement (Prior / submission Signature Post) Date IDA 1. Consulting services to carry out annual external 150,000.00 Open National LCS Post August 30, 2021 Sept 20, 2021 audits 2. Consulting services to carry out Baseline surveys 200,000.00 Open International Post September 11, October 16, 2020 QCBS 2020 3. Consulting services to collect and consolidate data 200,000.00 Open International Post February 15, March 30, 2021 on MSMEs on a national level to support the creation QCBS 2021 of a national database on MSMEs 4. Consulting services to Develop legal, regulatory and 200,000.00 Open International Post February 15, March 30, 2021 supervision frameworks for consumer protection; QCBS 2021 and digital finance products 5. Consulting service to support MAIIC 100,000 Open, National Post September 11, October 16, 2020 QCBS 2020 6. Consulting service to support RBM administration of 100,000 Open, National Post February 15, March 30, 2021 LOCs to PFIs, and provide support for onboarding of QCBS 2021 MFIs to the MFI Hub 7. Consulting service to support capacity building at 100,000 Open, National Post February 15, March 30, 2021 the Malawi Registration Bureau CQS 2021 8. Consulting service to conduct BDS Service activities 1,000,000 Open, International Prior September 11, October 16, 2020 QCBS 2020 9. Consulting Service to support and build capacity at 200,000 Open International Post September 11, October 16, 2020 SMEDI QCBS 2020 10. Consulting service to support improvement of 150,000 Open, National Post September 11, October 16, 2020 policy, legal and regulatory environment at the RBM, QCBS 2020 MoITT, and MoFEPD. 11. Hiring of Procurement Specialist 392,000.00 Open National Prior Review 12. Hiring of a Financial Management Specialist 392,000.00 Open National Prior Review 13. Environmental and Social Risk Management 300,000.00 Open National Prior Specialist Review 14. Hiring of M&E Specialist 250,000.00 Open National Post Review Page 5 of 8 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub- consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross- debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, Page 6 of 8 to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Page 7 of 8 Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: Page 8 of 8 PROCUREMENT Malawi : Financial Inclusion and Entrepreneurship Scaling Project PLAN General Information Country: Malawi 2020-12-14 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P168577 GPN Date: 2022-08-25 Project Name: Financial Inclusion and Entrepreneurship Scaling Project Loan / Credit No: IDA / 67460 Reserve Bank of Malawi Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-RBM-223957-GO-DIR / PI U Accounting Software Packa Project Implementation Sup IDA / 67460 Post Direct Selection Direct 60,000.00 60,250.00 Signed 2021-03-22 2021-09-01 2021-03-27 2021-09-01 2021-05-11 2021-09-07 2025-09-30 ge- Licences, support & main port tenance, Installation MW-RBM-223977-GO-RFB / P Enhancing the Enabling Envi rocurement for improving of ronment for Supporting the IDA / 67460 Post Request for Bids 350,000.00 0.00 Canceled 2021-04-09 2021-04-14 2021-05-26 2021-06-25 2021-07-30 2025-10-18 a surveillance system for the Financial Inclusion and Grow securities market to ensure th of Entrepreneurs orderly markets, MW-RBM-223956-GO-RFB / P Project Implementation Sup IDA / 67460 Post Request for Bids 600,000.00 564,693.80 Signed 2021-05-21 2021-07-08 2021-05-26 2021-08-06 2021-07-07 2021-09-09 2021-08-06 2021-10-07 2021-09-10 2022-07-04 2025-11-29 rocurement of 9 motor vehicl port es MW-RBM-223965-GO-RFB / P Project Implementation Sup Single Stage - One E IDA / 67460 Post Request for Bids Open - National 350,000.00 0.00 Canceled 2021-07-11 2021-07-16 2021-08-27 2021-09-26 2021-10-31 2025-09-30 rocurement of ICT equipment port nvelope MW-RBM-223961-GO-RFB / P Liquidity Enhancement for M Open - Internationa Single Stage - One E rocurement Integrated Mana IDA / 67460 Post Request for Bids 1,230,000.00 0.00 Canceled 2021-07-25 2021-07-30 2021-09-10 2021-10-10 2021-11-14 2025-09-30 SMEs l nvelope gement Information System f or MAIIC MW-RBM-223972-GO-DIR / P Enhancing the Enabling Envi rocurement of enhancement ronment for Supporting the IDA / 67460 Prior Direct Selection Direct 1,500,000.00 0.00 Canceled 2021-05-28 2021-06-02 2021-07-17 2025-12-06 software on National Switch t Financial Inclusion and Grow o support Electronic payment th of Entrepreneurs s MW-RBM-236762-GO-DIR / PI U Accounting Software Packa Project Implementation Sup IDA / 67460 Post Direct Selection Direct 60,000.00 0.00 Canceled 2021-06-22 2021-06-24 2021-06-27 2021-08-19 2021-08-01 2025-09-25 ge- Licenses, Support and Ma port intenance Installation RBM/FINES/002/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 3,800.00 3,431.62 Completed 2021-04-12 2021-04-12 2021-04-28 2021-04-29 2021-05-13 2021-05-14 ment of Office desks port tions nvelope RBM/FINES/003/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 5,000.00 2,107.14 Completed 2021-04-12 2021-04-12 2021-04-28 2021-04-29 2021-05-13 2021-05-14 ment of Office chairs port tions nvelope RBM/FINES/004/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 1,700.00 1,050.00 Completed 2021-03-11 2021-03-11 2021-04-18 2021-04-29 2021-05-28 2021-05-14 ment of Projector and Screen port tions nvelope RBM/FINES/005/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 18,000.00 18,256.98 Completed 2021-02-09 2021-02-09 2021-04-28 2021-04-29 2021-05-13 2021-05-14 ment of Color Photo Copier port tions nvelope RBM/FINES/006/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 4,000.00 2,355.87 Completed 2021-04-19 2021-04-19 2021-04-28 2021-05-15 2021-05-10 2021-05-15 ment of Mobile Phones port tions nvelope RBM/FINES/007/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 4,000.00 3,000.00 Completed 2021-04-09 2021-04-09 2021-04-28 2021-04-29 2021-05-13 2021-05-14 ment of Filling Cabinet port tions nvelope RBM/FINES/008/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 2,000.00 706.76 Completed 2021-02-17 2021-02-17 2021-04-28 2021-04-29 2021-05-13 2021-04-29 ment of Binding Machine port tions nvelope RBM/FINES/009/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 44,000.00 32,061.26 Completed 2020-12-28 2020-12-28 2021-04-28 2021-04-29 2021-05-10 2021-05-11 ment of Laptops port tions nvelope RBM/FINES/010/GO / Procure Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 1,200.00 1,022.86 Completed 2021-04-23 2021-04-23 2021-04-28 2021-04-29 2021-05-13 2021-05-14 ment of Bar Fridge port tions nvelope MW-RBM-250746-GO-RFP / P rocurement of an Integrated Liquidity Enhancement for M Request for Propo Open - Internationa Management Information Sys IDA / 67460 Post 1,230,000.00 0.00 Canceled 2021-09-03 2021-11-19 2021-11-19 2021-09-08 2022-01-28 2022-07-02 2022-08-06 2024-01-28 SMEs sals l tem for Malawi Agricultural a nd Industrial Investment Cor poration Plc (MAIIC) MW-RBM-223955-GO-RFB / P Project Implementation Sup Single Stage - One E IDA / 67460 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2021-06-18 2021-06-23 2021-08-04 2021-09-03 2021-10-08 2025-09-25 rocurement of office furnitur port nvelope e MW-RBM-223981-GO-RFB / P Project Implementation Sup Single Stage - One E IDA / 67460 Post Request for Bids Open - National 50,000.00 0.00 Canceled 2021-06-22 2021-06-27 2021-08-08 2021-09-07 2021-10-12 2025-09-25 rocurement -system upgrade port nvelope s MW-RBM-264980-GO-RFQ / Liquidity Enhancement for M Request for Quota Single Stage - One E Supply and delivery of ICT Eq IDA / 67460 Post Limited 34,000.00 87,050.45 Completed 2022-01-01 2022-01-12 2022-02-26 2022-02-19 2022-04-27 2022-04-30 SMEs tions nvelope uipment for MoF and MoI (dat abase) MW-RBM-265216-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Supply and delivery of 2022 IDA / 67460 Post Limited 4,000.00 1,926.45 Signed 2022-01-01 2021-12-07 2022-02-19 2022-01-07 2022-04-20 port tions nvelope calendars, diaries and busine ss cards MW-RBM-265219-GO-DIR / D Enhancing the Enabling Envi esign, supply and delivery of ronment for Supporting the IDA / 67460 Post Direct Selection Direct 30,000.00 39,028.36 Signed 2021-12-20 2021-12-06 2021-12-25 2021-12-06 2022-02-05 2021-12-30 2022-08-04 5000 ATM debit cards for MFI Financial Inclusion and Grow Hub th of Entrepreneurs Page 1 MW-RBM-267217-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 28,000.00 30,622.25 Completed 2021-12-18 2021-12-22 2022-02-12 2022-01-11 2022-08-11 2022-01-15 Server port tions nvelope MW-RBM-278501-GO-RFB / Design, Supply, Installation a nd Commissioning of Integrat Liquidity Enhancement for M Open - Internationa Single Stage - One E IDA / 67460 Post Request for Bids 1,230,000.00 0.00 Signed 2022-02-28 2022-02-15 2022-03-05 2022-02-17 2022-04-16 2022-04-14 2022-05-16 2022-06-08 2022-06-20 2025-07-31 ed Management System for SMEs l nvelope Malawi Agricultural and Indus trial Investment Corporation (MAIIC) MW-RBM-289686-GO-RFQ / Enhancing the Enabling Envi Supply and delivery of ICT Eq ronment for Supporting the Request for Quota Single Stage - One E IDA / 67460 Post Limited 70,000.00 61,456.90 Completed 2022-05-14 2022-04-19 2022-07-09 2022-06-10 2022-09-07 2022-07-14 uipment for MFI Hub and Dep Financial Inclusion and Grow tions nvelope artment of Registrar General th of Entrepreneurs MW-RBM-236760-GO-RFB / S Enhancing the Enabling Envi upply, Installation and Comm ronment for Supporting the Single Stage - One E issioning of an Automated M IDA / 67460 Post Request for Bids Open - National 350,000.00 0.00 Signed 2022-05-27 2022-06-09 2022-06-01 2022-06-10 2022-07-13 2022-08-04 2022-08-12 2022-09-30 2022-09-16 2023-03-15 Financial Inclusion and Grow nvelope arket Trading Surveillance Sy th of Entrepreneurs stem for Reserve Bank of Mal awi MW-RBM-298572-GO-RFQ / Enhancing the Enabling Envi Design and printing of broch ronment for Supporting the Request for Quota Single Stage - One E IDA / 67460 Post Limited 8,000.00 0.00 Signed 2022-07-30 2022-07-07 2022-09-24 2023-03-23 ures and flyers for Pension A Financial Inclusion and Grow tions nvelope wareness th of Entrepreneurs MW-RBM-303991-GO-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Supply and delivery of One ( IDA / 67460 Post Limited 100,000.00 0.00 Signed 2022-09-24 2022-08-03 2022-11-19 2023-05-18 port tions nvelope 1) Station Wagon SUV MW-RBM-318976-GO-RFB / S upply and Delivery of Procur Scaling Entrepreneurship an Single Stage - One E IDA / 67460 Post Request for Bids Open - National 200,000.00 0.00 Signed 2022-12-01 2022-10-28 2022-12-06 2022-10-31 2023-01-17 2022-11-10 2023-02-16 2022-12-09 2023-03-23 2023-05-22 ement of ICT Equipment for S d Building Firm Capabilities nvelope MEDI Head Office and Region al Offices. MW-RBM-322622-GO-DIR / S Enhancing the Enabling Envi upply, Installation and Comm ronment for Supporting the Direct - Internation Under Imple IDA / 67460 Post Direct Selection 1,500,000.00 0.00 2022-12-01 2022-10-24 2022-12-06 2022-11-01 2023-01-24 2023-04-24 issioning of National E-paym Financial Inclusion and Grow al mentation ent Gateway th of Entrepreneurs MW-RBM-318969-GO-RFB / S Enhancing the Enabling Envi upply, Installation and Comm ronment for Supporting the Single Stage - One E issioning of a Mobile Trading IDA / 67460 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2023-01-02 2022-11-18 2023-01-16 2022-11-18 2023-02-27 2023-01-10 2023-03-29 2023-01-18 2023-05-19 2023-11-15 Financial Inclusion and Grow nvelope Platform for the Malawi Stock th of Entrepreneurs Exchange Automated Tradin g System. MW-RBM-325735-GO-RFQ / P rinting and delivery of 500 co Scaling Entrepreneurship an Request for Quota Single Stage - One E IDA / 67460 Post Limited 5,000.00 0.00 Signed 2023-01-16 2022-11-18 2023-03-27 2023-05-26 pies of MSME policy documen d Building Firm Capabilities tions nvelope t for Ministry of Trade and In dustry MW-RBM-332182-GO-RFQ / Enhancing the Enabling Envi Supply and delivery of Tablet ronment for Supporting the Request for Quota Single Stage - One E IDA / 67460 Post Limited 20,000.00 0.00 Signed 2023-03-20 2023-02-27 2023-06-29 2023-12-26 s for Complaints Handling an Financial Inclusion and Grow tions nvelope d Financial literacy. th of Entrepreneurs MW-RBM-358971-GO-RFQ / Enhancing the Enabling Envi Designing, supply and deliver ronment for Supporting the Request for Quota Single Stage - One E Under Imple y of IEC materials (Roll up ba IDA / 67460 Post Limited 20,000.00 0.00 2023-06-19 2023-05-26 2023-08-07 2023-10-06 Financial Inclusion and Grow tions nvelope mentation nners, Golf shirts, Caps, Clot th of Entrepreneurs h, Billboards, Backdrop bann er, Brochures) MW-RBM-364667-GO-DIR / D Project Implementation Sup Pending Impl esigning and printing of bran IDA / 67460 Post Direct Selection Direct - National 9,205.00 0.00 2023-08-31 2023-09-05 2023-10-10 2024-04-07 port ementation ded cloth wrapper for FInES P roject MW-RBM-364671-GO-RFQ / P Enhancing the Enabling Envi rocurement of ICT Equipment ronment for Supporting the Request for Quota Single Stage - One E Under Imple (1Desktop and 2 scanner/pri IDA / 67460 Post Limited 5,714.00 0.00 2023-09-04 2023-10-30 2023-12-29 Financial Inclusion and Grow tions nvelope mentation nters) for Pension and Financ th of Entrepreneurs ial Sector Policy Division, Min istry of Finance MW-RBM-366379-GO-RFQ / Enhancing the Enabling Envi Supply, installation and confi ronment for Supporting the Request for Quota Single Stage - One E Pending Impl guration of network firewall d IDA / 67460 Post Limited 20,000.00 0.00 2023-08-28 2023-10-26 2024-01-24 Financial Inclusion and Grow tions nvelope ementation evice for IFMIS interface with th of Entrepreneurs Natswitch on e-payment gate way NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-RBM-265206-NC-RFQ / Project Implementation Sup Request for Quota Single Stage - One E Migration of email platform t IDA / 67460 Post Limited 5,000.00 25,000.00 Signed 2021-12-25 2021-12-06 2022-02-12 2022-02-11 2022-04-13 port tions nvelope o Microsoft 365 MW-RBM-298557-NC-RFQ / P Enhancing the Enabling Envi roduction of FInES and Pensi ronment for Supporting the Request for Quota Single Stage - One E IDA / 67460 Post Limited 45,000.00 0.00 Signed 2022-09-24 2022-08-03 2022-11-19 2023-01-18 on Awareness Materials (Jingl Financial Inclusion and Grow tions nvelope es and Comedies) th of Entrepreneurs MW-RBM-303998-NC-RFQ / Project Implementation Sup Request for Quota Single Stage - One E IDA / 67460 Post Limited 1,000.00 633.26 Signed 2022-10-01 2022-08-03 2022-11-26 2022-08-25 2023-01-25 Design of FInES Project logo port tions nvelope MW-RBM-358976-NC-RFQ / P Enhancing the Enabling Envi roduction and airing of anima ronment for Supporting the Request for Quota Single Stage - One E Under Imple IDA / 67460 Post Limited 10,000.00 0.00 2023-07-03 2023-05-19 2023-08-28 2024-02-24 ted videos, video documenta Financial Inclusion and Grow tions nvelope mentation ries, radio and video jingles a th of Entrepreneurs nd adverts MW-RBM-358985-NC-DIR / S Enhancing the Enabling Envi upply and installation of toll-f ronment for Supporting the Under Imple IDA / 67460 Post Direct Selection Direct - National 7,000.00 0.00 2023-06-12 2023-06-09 2023-06-26 2023-06-19 2023-08-14 2024-02-10 ree lines for Financial Consu Financial Inclusion and Grow mentation mer Complaints Handling th of Entrepreneurs MW-RBM-364664-NC-RFQ / P Enhancing the Enabling Envi roduction and airing of TV an ronment for Supporting the Request for Quota Single Stage - One E Under Imple IDA / 67460 Post Limited 7,725.00 0.00 2023-08-14 2023-06-02 2023-10-09 2023-11-08 d Radio messages on launch Financial Inclusion and Grow tions nvelope mentation of Incubation by Malawi Stoc th of Entrepreneurs k Exchange Page 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-RBM-223959-CS-QCBS / Consultancy and advisory ser Liquidity Enhancement for M Quality And Cost- Open - Internationa vices to support managemen IDA / 67460 Post 470,000.00 0.00 Canceled 2021-05-28 2021-06-18 2021-08-01 2021-08-29 2021-09-28 2021-11-02 2021-12-07 2025-11-12 SMEs Based Selection l t in capital raising and projec t preparation for MAIIC. MW-RBM-253006-CS-LCS / C Liquidity Enhancement for M Least Cost Selecti Open - Internationa onsultancy services to suppo IDA / 67460 Post 170,000.00 0.00 Canceled 2021-10-04 2021-10-25 2021-12-08 2022-01-05 2022-02-04 2022-03-11 2022-04-15 2025-09-25 SMEs on l rt management in project pre paration MW-RBM-256859-CS-CQS / C onsulting Services to identify Liquidity Enhancement for M Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 SMEs cation Selection that can access concessional loans from MAIIC Package 2 MW-RBM-256870-CS-CQS / C onsulting Services to identify Project Implementation Sup Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 port cation Selection that can access concessional loans from MAIIC Package 1 MW-RBM-256867-CS-CQS / C onsulting Services to identify Liquidity Enhancement for M Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 SMEs cation Selection that can access concessional loans from MAIIC Package 3 MW-RBM-256872-CS-CQS / C onsulting Services to identify Liquidity Enhancement for M Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 SMEs cation Selection that can access concessional loans from MAIIC Package 4 MW-RBM-256875-CS-CQS / C onsulting Services to identify Liquidity Enhancement for M Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 SMEs cation Selection that can access concessional loans from MAIIC Package 5 MW-RBM-256863-CS-CQS / C onsulting Services to identify Liquidity Enhancement for M Consultant Qualifi innovative firms with projects IDA / 67460 Post Open - National 166,666.67 0.00 Canceled 2021-10-25 2021-10-11 2021-11-08 2021-10-13 2021-12-22 2022-01-21 2022-02-25 2024-12-31 SMEs cation Selection that can access concessional loans from MAIIC Package 6 MW-RBM-259352-CS-CQS / C onsultancy Service for Trans Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 100,000.00 0.00 Canceled 2021-11-01 2021-10-27 2021-11-22 2021-10-28 2022-01-05 2021-11-30 2022-02-04 2022-03-11 2025-09-25 action Advisory Services for SMEs cation Selection Capital Raising for MAIIC Pac kage 1 MW-RBM-259279-CS-CQS / C onsultancy Service for Trans Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 100,000.00 247,250.00 Signed 2021-11-01 2021-10-27 2021-11-22 2021-10-28 2022-01-05 2021-11-30 2022-02-04 2022-02-15 2022-03-11 2022-04-30 2025-09-25 action Advisory Services for SMEs cation Selection Capital Raising for MAIIC Pac kage 3 MW-RBM-259367-CS-CQS / C Project Implementation Sup Consultant Qualifi onsultancy services for Exter IDA / 67460 Post Open - National 45,000.00 23,985.62 Signed 2021-11-01 2021-10-28 2021-11-22 2021-11-23 2022-01-05 2022-01-06 2022-02-04 2022-02-02 2022-03-11 2022-03-01 2025-09-25 port cation Selection nal Audit Review for PIU MW-RBM-259365-CS-CQS / C Liquidity Enhancement for M Consultant Qualifi onsultancy services for Legal IDA / 67460 Post Open - National 50,000.00 0.00 Canceled 2021-11-01 2021-11-23 2021-11-22 2022-01-11 2022-01-05 2022-02-04 2022-03-11 2025-09-25 SMEs cation Selection Services in respect of MAIIC's Capital raising MW-RBM-259363-CS-CQS / C onsultancy Services on the d Project Implementation Sup Consultant Qualifi IDA / 67460 Post Open - National 180,000.00 99,892.39 Signed 2021-11-01 2021-12-16 2021-11-22 2022-02-28 2022-01-05 2022-04-01 2022-02-04 2022-05-05 2022-03-11 2022-08-01 2025-09-25 evelopment of the Project Ma port cation Selection nagement Information Syste m MW-RBM-259364-CS-CQS / C Project Implementation Sup Consultant Qualifi onsultancy services for Basel IDA / 67460 Post Open - National 200,000.00 227,505.10 Signed 2021-11-01 2022-01-19 2021-11-22 2022-01-28 2022-01-05 2022-03-04 2022-02-04 2022-03-30 2022-03-11 2022-04-30 2025-09-25 port cation Selection ine Survey MW-RBM-253010-CS-QCBS / Liquidity Enhancement for M Quality And Cost- Open - Internationa Consultancy services to sup IDA / 67460 Post 250,000.00 0.00 Canceled 2021-10-04 2021-10-25 2021-12-08 2022-01-05 2022-02-04 2022-03-11 2022-04-15 2025-09-25 SMEs Based Selection l port management in capital r aising MW-RBM-223948-CS-CQS / C onsulting service for Biller an Liquidity Enhancement for M Consultant Qualifi d Card System Intergration a IDA / 67460 Post Open - National 176,000.00 0.00 Canceled 2021-05-28 2021-06-18 2021-08-01 2021-08-31 2021-10-05 2025-12-06 SMEs cation Selection nd capacity building to suppo rt onboarding of MFIs to the MFI Hub MW-RBM-240966-CS-QCBS / Technical Assistance in busin ess development and suppor Scaling Entrepreneurship an Quality And Cost- Open - Internationa t services to entrepreneurs t IDA / 67460 Prior 3,500,000.00 0.00 Canceled 2021-06-25 2021-08-10 2021-07-16 2021-08-29 2021-09-26 2021-10-26 2021-11-30 2022-01-04 2025-01-03 d Building Firm Capabilities Based Selection l o develop the right business models, skills, networks, and to access financial services a nd markets. MW-RBM-264974-CS-QCBS / Consultancy Services for Pro vision of Business Developm Scaling Entrepreneurship an Quality And Cost- Open - Internationa IDA / 67460 Prior 3,000,000.00 0.00 Canceled 2021-12-27 2022-01-17 2022-03-02 2022-04-01 2022-05-01 2022-06-05 2022-07-10 2025-07-09 ent Services to deliver capaci d Building Firm Capabilities Based Selection l ty building training program t o firms defined under subco mponent 2.1 MW-RBM-265225-CS-CQS / P Enhancing the Enabling Envi rovision of consultancy servic ronment for Supporting the Consultant Qualifi IDA / 67460 Post Open - National 20,000.00 22,067.37 Completed 2021-12-20 2021-12-07 2022-01-10 2021-12-16 2022-02-23 2022-01-21 2022-03-25 2022-03-08 2022-04-29 2022-04-22 2022-05-29 2022-10-07 es to conduct systems audit f Financial Inclusion and Grow cation Selection or MFI Hub th of Entrepreneurs MW-RBM-270547-CS-CQS / C ONSULTING SERVICES TO IDE Liquidity Enhancement for M Consultant Qualifi NTIFY INNOVATIVE FIRMS WI IDA / 67460 Post Open - National 166,666.67 118,423.37 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-02-09 2022-03-24 2022-03-10 2022-04-28 2022-05-21 2025-03-03 SMEs cation Selection TH PROJECTS THAT CAN ACC ESS CONCESSIONAL LOANS F ROM MAIIC PACKAGE 1 Page 3 MW-RBM-256872-CS-CQS-2 / CONSULTING SERVICES TO I Liquidity Enhancement for M Consultant Qualifi DENTIFY INNOVATIVE FIRMS IDA / 67460 Post Open - National 166,666.67 130,809.55 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-02-09 2022-03-24 2022-03-10 2022-04-28 2022-05-21 2025-03-03 SMEs cation Selection WITH PROJECTS THAT CAN A CCESS CONCESSIONAL LOAN S FROM MAIIC PACKAGE 2 MW-RBM-270552-CS-CQS / C ONSULTING SERVICES TO IDE Liquidity Enhancement for M Consultant Qualifi NTIFY INNOVATIVE FIRMS WI IDA / 67460 Post Open - National 166,666.67 130,809.55 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-02-09 2022-03-24 2022-03-10 2022-04-28 2022-05-21 2025-03-03 SMEs cation Selection TH PROJECTS THAT CAN ACC ESS CONCESSIONAL LOANS F ROM MAIIC PACKAGE 3 MW-RBM-270553-CS-CQS / C ONSULTING SERVICES TO IDE Liquidity Enhancement for M Consultant Qualifi NTIFY INNOVATIVE FIRMS WI IDA / 67460 Post Open - National 166,666.67 130,809.55 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-02-09 2022-03-24 2022-03-10 2022-04-28 2022-05-21 2025-03-03 SMEs cation Selection TH PROJECTS THAT CAN ACC ESS CONCESSIONAL LOANS F ROM MAIIC PACKAGE 4 MW-RBM-270557-CS-CQS / C ONSULTING SERVICES TO IDE Liquidity Enhancement for M Consultant Qualifi NTIFY INNOVATIVE FIRMS WI IDA / 67460 Post Open - National 166,666.67 0.00 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-04-27 2022-03-24 2022-10-07 2022-04-28 2025-03-03 SMEs cation Selection TH PROJECTS THAT CAN ACC ESS CONCESSIONAL LOANS F ROM MAIIC PACKAGE 5 MW-RBM-270558-CS-CQS / C ONSULTING SERVICES TO IDE Project Implementation Sup Consultant Qualifi NTIFY INNOVATIVE FIRMS WI IDA / 67460 Post Open - National 166,666.67 130,809.55 Signed 2021-12-26 2022-01-05 2022-01-09 2022-01-10 2022-02-22 2022-02-09 2022-03-24 2022-03-10 2022-04-28 2022-05-21 2025-03-03 port cation Selection TH PROJECTS THAT CAN ACC ESS CONCESSIONAL LOANS F ROM MAIIC PACKAGE 6 MW-RBM-272572-CS-QCBS / Consultancy Services for Pro vision of Business Developm Scaling Entrepreneurship an Quality And Cost- Open - Internationa IDA / 67460 Prior 3,300,000.00 0.00 Signed 2022-02-14 2022-01-27 2022-03-07 2022-02-04 2022-04-20 2022-05-16 2022-05-20 2022-06-30 2022-06-19 2022-08-24 2022-07-24 2022-10-20 2022-08-28 2025-08-29 ent Services to deliver capaci d Building Firm Capabilities Based Selection l ty building training program t o firms defined under subco mponent 2.1 MW-RBM-272889-CS-CQS / C onsultancy Services to Establ ish a Baseline for Capacity B Scaling Entrepreneurship an Consultant Qualifi Open - Internationa uilding and Access to Financi IDA / 67460 Post 200,000.00 0.00 Signed 2022-02-14 2022-02-08 2022-03-07 2022-02-17 2022-04-20 2022-04-01 2022-05-20 2022-05-05 2022-06-24 2022-11-21 d Building Firm Capabilities cation Selection l al Services for Small and Med ium Enterprises (SMEs) Partic ipating in Firm Capability Trai ning Under Sub-Component 2 .1 MW-RBM-303996-CS-CQS / C Enhancing the Enabling Envi onsultancy to conduct follow- ronment for Supporting the Consultant Qualifi IDA / 67460 Post Open - National 130,000.00 0.00 Signed 2022-09-30 2022-08-24 2022-10-21 2022-09-11 2022-12-04 2022-10-31 2023-01-03 2022-11-28 2023-02-07 2023-07-07 up household survey on Mala Financial Inclusion and Grow cation Selection wi financial capability and Co th of Entrepreneurs nsumer Protection MW-RBM-313226-CS-CQS / P rovision of Consulting service s to design, develop and com mission a user-friendly and r Project Implementation Sup Consultant Qualifi IDA / 67460 Post Open - National 8,000.00 0.00 Signed 2022-11-14 2022-09-16 2022-12-05 2023-01-18 2022-10-20 2023-02-17 2023-03-28 2023-03-24 2023-06-22 esponsive Content Managem port cation Selection ent System (CMS) or website which shall provide a platfor m to all stakeholders to easil y access all material on FInE S Project MW-RBM-259365-CS-CQS-2 / CONSULTANCY SERVICES FO R PROVISION OF LEGAL SERV Liquidity Enhancement for M Consultant Qualifi ICES IN RESPECT OF MALAWI IDA / 67460 Post Open - National 50,000.00 0.00 Canceled 2022-03-28 2022-05-12 2022-04-18 2022-05-17 2022-06-01 2022-07-09 2022-07-01 2022-08-05 2023-02-01 SMEs cation Selection AGRICULTURAL AND INDUST RIAL INVESTMENT CORPORA TION PLC (MAIIC) CAPITAL RA ISING MW-RBM-324785-CS-CQS / C onsulting Services to Provide Capacity Building Programm Scaling Entrepreneurship an Consultant Qualifi e for SMEDI Staff in Financial IDA / 67460 Post Open - National 50,000.00 0.00 Signed 2022-12-26 2022-12-02 2023-01-16 2022-12-06 2023-03-08 2023-01-10 2023-04-07 2023-02-03 2023-05-18 2023-08-16 d Building Firm Capabilities cation Selection and Business Advisory Servic es and Programme Design fo r Micro, Small and Medium E nterprises MW-RBM-327297-CS-CQS / C onsulting Services to identify innovative firms with projects Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 190,000.00 0.00 Signed 2023-01-23 2022-11-23 2023-02-13 2022-12-16 2023-03-29 2023-02-07 2023-04-28 2023-03-19 2023-06-02 2025-07-31 that can access concessional SMEs cation Selection loans from MAIIC (Business in cubators, hubs and accelerat ors) Package 1 MW-RBM-327298-CS-CQS / C onsulting Services to identify innovative firms with projects Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 190,000.00 0.00 Signed 2023-01-23 2022-11-23 2023-02-13 2022-12-16 2023-03-29 2023-02-07 2023-04-28 2023-03-28 2023-06-02 2025-07-31 that can access concessional SMEs cation Selection loans from MAIIC (Business in cubators, hubs and accelerat ors) Package 2 MW-RBM-327299-CS-CQS / C onsulting Services to identify innovative firms with projects Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 190,000.00 0.00 Canceled 2023-01-31 2022-11-23 2023-02-21 2022-12-16 2023-04-06 2023-02-07 2023-05-06 2023-06-10 2025-08-08 that can access concessional SMEs cation Selection loans from MAIIC (Business in cubators, hubs and accelerat ors) Package 3 MW-RBM-327300-CS-CQS / C onsulting Services to identify innovative firms with projects Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 190,000.00 0.00 Canceled 2023-01-23 2022-11-23 2023-02-13 2022-12-16 2023-03-29 2023-02-07 2023-04-28 2023-06-02 2025-07-31 that can access concessional SMEs cation Selection loans from MAIIC (Business in cubators, hubs and accelerat ors) Package 4 MW-RBM-259354-CS-CQS / C onsultancy Service for Trans Liquidity Enhancement for M Consultant Qualifi IDA / 67460 Post Open - National 100,000.00 0.00 Canceled 2021-11-01 2021-10-27 2021-11-22 2021-10-28 2022-01-05 2021-11-30 2022-02-04 2022-03-11 2025-09-25 action Advisory Services for SMEs cation Selection Capital Raising for MAIIC Pac kage 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 MW-RBM-209099-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Prior Open 392,000.00 60,832.03 Terminated 2020-12-14 2020-12-17 2021-02-09 2021-05-20 2021-02-23 2021-08-23 2021-03-16 2021-06-22 2025-09-30 Procurement Specialist port ant Selection MW-RBM-209097-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Prior Open 392,000.00 116,541.90 Signed 2020-12-14 2021-01-07 2021-02-09 2021-05-25 2021-02-23 2021-08-22 2021-03-16 2021-06-11 2025-09-30 Financial Management Speci port ant Selection alist MW-RBM-209089-CS-INDV / Project Implementation Sup Individual Consult Environmental and Social Ris IDA / 67460 Prior Open 392,000.00 88,958.02 Terminated 2020-12-14 2021-01-06 2021-02-09 2021-05-25 2021-02-23 2021-09-09 2021-03-16 2021-06-18 2025-09-30 port ant Selection k Management Specialist MW-RBM-216945-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Post Open 250,000.00 4,576.64 Terminated 2021-02-28 2021-02-02 2021-04-18 2021-06-01 2021-05-09 2021-06-02 2021-06-13 2021-07-13 2025-09-30 Monitoring and Evaluation Sp port ant Selection ecialist MW-RBM-223978-CS-INDV / Hiring of Micro Small &Mediu Project Implementation Sup Individual Consult IDA / 67460 Post Open 250,000.00 43,847.68 Signed 2021-03-22 2021-03-29 2021-05-10 2021-07-27 2021-05-31 2021-09-01 2021-07-05 2021-09-03 2025-09-30 m Enterprises (Business Dev port ant Selection elopment) Specialist MW-RBM-223963-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Post Open 250,000.00 67,306.89 Terminated 2021-03-22 2021-03-29 2021-05-10 2021-06-25 2021-05-31 2021-09-01 2021-07-05 2021-09-03 2025-09-30 Hiring of Financial Sector Spe port ant Selection cialist MW-RBM-241105-CS-INDV / Consultancy Services to scop e the status of SMEDI, identif Scaling Entrepreneurship an Individual Consult IDA / 67460 Post Open 14,060.00 0.00 Canceled 2021-06-25 2021-06-27 2021-08-13 2021-09-03 2021-10-08 2022-01-06 y its capacity development n d Building Firm Capabilities ant Selection eeds and recommend priority capacity development action s MW-RBM-241101-CS-INDV / Project Implementation Sup Individual Consult Hiring of a Business Develop IDA / 67460 Post Open 250,000.00 0.00 Canceled 2021-06-25 2021-06-28 2021-08-13 2021-09-03 2021-10-08 2022-04-06 port ant Selection ment Services Specialist MW-RBM-251839-CS-INDV / Consultant to scope the statu Scaling Entrepreneurship an Individual Consult s of SMEDI, identify its capaci IDA / 67460 Post Open 30,000.00 28,104.45 Completed 2021-09-03 2021-08-09 2021-10-22 2021-12-06 2021-11-12 2021-12-07 2021-12-17 2021-12-21 2022-06-15 d Building Firm Capabilities ant Selection ty development needs and re commend priority capacity d evelopment actions MW-RBM-258339-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Prior Open 250,000.00 61,502.76 Signed 2021-10-18 2021-11-07 2021-12-06 2022-01-25 2021-12-27 2022-02-10 2022-01-31 2022-02-13 2025-09-25 Financial Sector Specialist port ant Selection MW-RBM-209099-CS-INDV.. / Project Implementation Sup Individual Consult IDA / 67460 Prior Open 392,000.00 60,501.37 Signed 2020-12-15 2021-11-17 2021-02-02 2021-08-27 2021-10-22 2022-01-19 2021-11-07 2021-12-18 2025-09-25 Procurement Specialist port ant Selection MW-RBM-209099-CS-INDV. / Project Implementation Sup Individual Consult IDA / 67460 Post Open 392,000.00 0.00 Canceled 2020-12-15 2020-12-15 2021-10-10 2021-10-31 2021-12-05 2025-09-25 Procurement Specialist port ant Selection MW-RBM-264972-CS-INDV / Enhancing the Enabling Envi Consultancy to review activiti ronment for Supporting the Individual Consult IDA / 67460 Post Open 14,458.00 15,000.00 Signed 2021-12-20 2021-12-07 2022-01-28 2022-02-09 2022-02-11 2022-03-11 2022-03-18 2022-04-09 2022-04-17 es planned for the developm Financial Inclusion and Grow ant Selection ent of payment gateway in M th of Entrepreneurs alawi MW-RBM-265208-CS-INDV / Consultancy Services to supp ort National Economic Empo Liquidity Enhancement for M Individual Consult IDA / 67460 Post Open 100,000.00 41,828.93 Completed 2021-12-27 2021-12-06 2022-02-14 2022-01-21 2022-03-07 2022-03-10 2022-04-11 2022-04-04 2022-06-10 werment Fund (NEEF) to stre SMEs ant Selection ngthen their credit portfolio management systems and pr ocedures MW-RBM-209089-CS-INDV. / Project Implementation Sup Individual Consult Environmental and Social Ris IDA / 67460 Prior Open 392,000.00 61,502.76 Signed 2021-12-13 2021-01-06 2022-01-31 2022-01-05 2022-02-21 2022-02-10 2022-03-28 2022-03-12 2025-09-25 port ant Selection k Management Specialist MW-RBM-272092-CS-INDV / Project Implementation Sup Individual Consult Financial Services Developm IDA / 67460 Post Open 250,000.00 60,527.57 Signed 2022-01-31 2022-01-10 2022-03-21 2022-03-01 2022-04-11 2022-03-07 2022-05-16 2022-04-02 2025-09-30 port ant Selection ent Specialist MW-RBM-272077-CS-INDV / Enhancing the Enabling Envi Consultancy to develop a Nat ronment for Supporting the Individual Consult IDA / 67460 Post Open 168,000.00 0.00 Canceled 2022-02-07 2022-01-13 2022-03-28 2022-04-18 2022-05-23 2022-09-20 ional Database for Micro, Sm Financial Inclusion and Grow ant Selection all and Medium Enterprises ( th of Entrepreneurs MSMEs) MW-RBM-272561-CS-INDV / Consultancy to develop a Co Project Implementation Sup Individual Consult mmunication Strategy for the IDA / 67460 Post Open 15,000.00 26,989.25 Signed 2022-02-07 2022-01-13 2022-03-28 2022-02-18 2022-04-18 2022-03-09 2022-05-23 2022-04-22 2022-07-22 port ant Selection Financial Inclusion and Entre preneurship Scaling (FInES) P roject MW-RBM-216945-CS-INDV.. / Project Implementation Sup Individual Consult IDA / 67460 Prior Open 392,000.00 52,077.89 Signed 2022-03-01 2022-02-23 2022-04-19 2022-01-31 2022-05-10 2022-03-11 2022-06-14 2022-03-27 2025-09-25 Monitoring and Evaluation Sp port ant Selection ecialist MW-RBM-278507-CS-INDV / Enhancing the Enabling Envi Consultancy to design a Nati ronment for Supporting the Individual Consult IDA / 67460 Post Open 30,000.00 24,277.56 Signed 2022-02-28 2022-02-17 2022-04-18 2022-04-01 2022-05-09 2022-05-05 2022-06-13 2022-07-28 2022-08-12 onal Database for Micro, Sma Financial Inclusion and Grow ant Selection ll and Medium Enterprises ( th of Entrepreneurs MSMEs) in Malawi MW-RBM-313225-CS-INDV / Project Implementation Sup Individual Consult IDA / 67460 Post Open - National 55,000.00 0.00 Signed 2022-11-07 2022-09-07 2022-12-26 2022-11-22 2023-01-16 2022-12-23 2023-02-20 2024-12-31 Communication Officer for FI port ant Selection nES Project MW-RBM-313237-CS-INDV / Consultancy Services to Iden tify, propose action plan and Liquidity Enhancement for M Individual Consult IDA / 67460 Post Limited 50,000.00 0.00 Signed 2022-11-14 2022-09-22 2022-11-19 2022-09-30 2022-12-10 2022-11-04 2023-01-14 2023-03-10 train financial institutions in i SMEs ant Selection ncreasing access to finance t o MSMEs and farmer coopera tives MW-RBM-313243-CS-INDV / Enhancing the Enabling Envi Consultancy Services for Aut ronment for Supporting the Individual Consult Open - Internationa omation and Enhancement of IDA / 67460 Post 100,000.00 0.00 Canceled 2022-11-30 2022-09-07 2023-01-18 2023-02-08 2023-03-15 2024-03-31 Financial Inclusion and Grow ant Selection l the Complaints Handling and th of Entrepreneurs Management Information Sys tem MW-RBM-313241-CS-INDV / Consultancy Services for Cap acity Building Program for S Scaling Entrepreneurship an Individual Consult IDA / 67460 Post Limited 50,000.00 0.00 Canceled 2022-12-12 2022-09-16 2022-12-17 2022-09-27 2023-01-07 2022-11-01 2023-02-11 2023-03-04 MEDI Staff in Entrepreneurshi d Building Firm Capabilities ant Selection p Development, Business Dia gnostics and Advisory; and C urriculum Development Page 5 MW-RBM-318989-CS-INDV / Enhancing the Enabling Envi Consultancy Services to Stud ronment for Supporting the Individual Consult IDA / 67460 Post Open - National 26,956.00 0.00 Signed 2022-12-19 2022-10-07 2023-02-06 2022-11-22 2023-02-27 2022-11-25 2023-04-03 2023-07-02 y the Cost of Financial Servic Financial Inclusion and Grow ant Selection es in Malawi th of Entrepreneurs MW-RBM-313243-CS-INDV. / Enhancing the Enabling Envi Consultancy Services for Aut ronment for Supporting the Individual Consult Open - Internationa omation and Enhancement of IDA / 67460 Post 100,000.00 0.00 Signed 2022-11-30 2022-10-13 2023-01-18 2022-12-15 2023-02-08 2022-12-19 2023-03-15 2024-03-31 Financial Inclusion and Grow ant Selection l the Complaints Handling and th of Entrepreneurs Management Information Sys tem MW-RBM-313246-CS-INDV / Enhancing the Enabling Envi Consultancy Services for Dev ronment for Supporting the Individual Consult Open - Internationa elopment of a Directive on Fi IDA / 67460 Post 93,000.00 0.00 Canceled 2022-12-05 2022-09-07 2023-01-23 2023-02-13 2023-03-20 2023-09-16 Financial Inclusion and Grow ant Selection l nancial Consumer Protection th of Entrepreneurs for Users of Digital Financial Services MW-RBM-327295-CS-INDV / Consultancy for Capacity Buil ding Programme for SMEDI S Scaling Entrepreneurship an Individual Consult IDA / 67460 Post Open - National 50,000.00 0.00 Signed 2023-01-02 2022-11-23 2023-03-01 2023-01-18 2023-03-22 2023-01-20 2023-04-26 2023-07-25 taff in Entrepreneurship Deve d Building Firm Capabilities ant Selection lopment, Business Diagnostic s and Advisory; and Curriculu m Development MW-RBM-332176-CS-CDS / P rovision of External Audit Ser Project Implementation Sup IDA / 67460 Post Direct Selection Direct - National 45,000.00 0.00 Signed 2023-02-13 2023-01-17 2023-03-29 2023-01-20 2023-06-02 2023-12-31 vices for FInES Project for the port year ended 2022 MW-RBM-364181-CS-INDV / Consultancy Services for dev elopment of Online Training Scaling Entrepreneurship an Individual Consult Under Implement IDA / 67460 Post Open - National 49,547.00 0.00 2023-07-28 2023-06-02 2023-09-15 2023-10-06 2023-11-10 2024-03-09 and Marketing Portals, Mobil d Building Firm Capabilities ant Selection ation e and USSD Applications for s upport of Micro, Small and M edium Enterprises Page 6 PROCUREMENT PLAN (Textual Part) Project information: Greater Accra Resilient Integrated Development (GARID) Project- [P-164330] Project Implementation agency: Ministry of Works and Housing Date of the Procurement Plan: March 28, 2018 Period covered by this Procurement Plan: January to December, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [Ghana Public Procurement Act 663, amended with Act 914 ], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. a. Open advertising of the procurement opportunity at the national level; b. The procurement is open to eligible firms from any country; c. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. Publication of contract award information; f. Rights for the Bank to review procurement documentation and activities; g. An effective complaints mechanism; and h. Maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. N/A Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables N/A Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables]; Works: is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. . PROCUREMENT Ghana : Greater Accra Resilient and Integrated Development Project PLAN General Information Country: Ghana 2019-02-27 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164330 GPN Date: Project Name: Greater Accra Resilient and Integrated Development Project Loan / Credit No: IDA / V1450, IDA / 64100 Ministry of Local Government Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Participatory GH-MLG-RESILIANCE-159390 Upgrading of Targeted Flood Request for Quota Single Stage - One E -GO-RFQ / Procurement of 2N IDA / 64100 Post Limited 46,000.00 0.00 Canceled 2020-03-01 2020-04-26 2020-07-25 Prone Low-income Communi tions nvelope o. Vehicles ties and Local Government S upport GH-MLG-RESILIANCE-159389 Component 3: Participatory -GO-RFQ / Procurement of 2N Upgrading of Targeted Flood Request for Quota Single Stage - One E IDA / 64100 Post Limited 3,000.00 9,487.78 Signed 2020-08-15 2020-09-07 2020-10-10 2021-02-25 2021-01-08 o Laptops, 1 No Printers, inte Prone Low-income Communi tions nvelope rnet modem, External Hard D ties and Local Government S rives upport GH-MLG-RESILIANCE-159392 Component 3: Participatory -GO-RFQ / Procurement of off Upgrading of Targeted Flood Request for Quota Single Stage - One E IDA / 64100 Post Limited 1,200.00 0.00 Canceled 2020-03-01 2020-09-07 2020-04-26 2020-07-25 ice furniture - 1 Desk and 1 s Prone Low-income Communi tions nvelope wivel chair ties and Local Government S upport GH-MLG-RESILIANCE-220955 Component 3: Participatory -GO-RFQ / Procure 3 No. Lapt Upgrading of Targeted Flood Request for Quota Single Stage - One E IDA / 64100 Post Limited 8,000.00 6,779.26 Completed 2021-06-26 2021-08-04 2021-08-21 2021-08-25 2021-09-20 2021-11-10 ops, Printer, Scanner and Ext Prone Low-income Communi tions nvelope ernal Hard Drive ties and Local Government S upport GH-MLG-RESILIANCE-220965 Component 3: Participatory -GO-RFQ / Procure office Tabl Upgrading of Targeted Flood Request for Quota Single Stage - One E IDA / 64100 Post Limited 4,200.00 2,623.85 Completed 2021-06-26 2021-08-24 2021-08-21 2021-09-09 2021-09-20 2021-11-10 e, Swivel Chair and File Cabin Prone Low-income Communi tions nvelope et ties and Local Government S upport Component 3: Participatory GH-MLG-RESILIANCE-282273 Upgrading of Targeted Flood Request for Quota Single Stage - One E -GO-RFQ / Procurement of 3N IDA / 64100 Post Limited 8,000.00 0.00 Signed 2022-05-28 2022-06-21 2022-07-23 2022-08-27 Prone Low-income Communi tions nvelope o. Laptops and a Printer ties and Local Government S upport GH-MLG-RESILIANCE-347032 Component 3: Participatory -GO-RFB / Procure Multipurpo Upgrading of Targeted Flood se Drones for the Physical Pla Single Stage - One E Under Imple IDA / 64100 Prone Low-income Communi Post Request for Bids Open - National 665,000.00 0.00 2023-05-15 2023-05-25 2023-05-20 2023-05-30 2023-06-19 2023-07-10 2023-08-07 2023-11-05 nning Departments of GARID nvelope mentation ties and Local Government S MMAs, LUSPA Headquarters a upport nd Greater Accra Regional Co ordinating Council (GARCC) GH-MLG-RESILIANCE-159391 -GO-RFQ / Printing of 200 cop Component 3: Participatory ies of O&M Manuals, 30 copie Upgrading of Targeted Flood Request for Quota Single Stage - One E Pending Impl s of Participating Agreement IDA / 64100 Prone Low-income Communi Post Limited 21,500.00 0.00 2023-06-18 2023-08-13 2023-09-12 tions nvelope ementation Document for Participating M ties and Local Government S MAs & Partners and 250 copi upport es of ICMC Management Fra mework and Guidelines. Component 3: Participatory GH-MLG-RESILIANCE-347029 Upgrading of Targeted Flood Request for Quota Single Stage - One E Pending Impl -GO-RFQ / Procure 2No. Proje IDA / 64100 Post Limited 3,000.00 0.00 2023-05-20 2023-07-15 2023-09-09 Prone Low-income Communi tions nvelope ementation ctors and 2No. Laptops ties and Local Government S upport NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLG-RESILIANCE-103417 Component 3: Participatory -CS-QCBS / Flood utility asses Upgrading of Targeted Flood Quality And Cost- IDA / V1450 Post Open - National 194,250.00 0.00 Canceled 2021-03-18 2021-04-08 2021-05-22 2021-06-19 2021-07-19 2021-08-23 2021-09-27 2023-09-27 sment and Support for JDPA/ Prone Low-income Communi Based Selection B LI development, sensitizati ties and Local Government S on, capacity building upport GH-MLG-RESILIANCE-182102 Component 3: Participatory -CS-QCBS / Consultancy Servi Upgrading of Targeted Flood Quality And Cost- ces for the Establishment an IDA / 64100 Prone Low-income Communi Post Open - National 120,000.00 118,000.00 Signed 2020-08-25 2021-02-15 2020-09-15 2020-10-29 2021-09-14 2020-11-26 2021-10-22 2020-12-26 2021-11-23 2021-01-30 2021-12-14 2021-03-06 2022-03-31 2022-03-06 Based Selection d Operationalisation of the In ties and Local Government S ter-jurisdictional Coordinatio upport n Management Framework GH-MLG-RESILIANCE-159398 Component 3: Participatory -CS-LCS / Preparation of O & Upgrading of Targeted Flood Least Cost Selecti M Plan and Manuals, Implem IDA / 64100 Prone Low-income Communi Post Open - National 80,000.00 170,000.00 Signed 2020-04-15 2020-12-10 2020-05-06 2020-06-19 2021-06-22 2020-07-17 2021-07-22 2020-08-16 2021-10-13 2020-09-20 2021-10-28 2020-10-25 2021-12-27 2021-04-23 on entation Guidelines for delive ties and Local Government S ry of O & M Grants to GARID upport MAs GH-MLG-RESILIANCE-198806 Component 3: Participatory -CS-QCBS / Consultancy Servi Upgrading of Targeted Flood Quality And Cost- Open - Internationa ces for the Preparation of Joi IDA / 64100 Prone Low-income Communi Prior 2,100,000.00 0.00 Canceled 2020-11-06 2021-03-18 2020-11-27 2021-07-16 2021-01-10 2022-01-04 2021-02-07 2022-02-15 2021-03-09 2021-04-13 2021-05-18 2023-05-08 Based Selection l nt Basin Management Plan fo ties and Local Government S r the Odaw Drainage Basin. upport Page 1 GH-MLG-RESILIANCE-182100 Component 3: Participatory -CS-QCBS / Consultancy Servi Upgrading of Targeted Flood Quality And Cost- Open - Internationa Under Implement IDA / 64100 Prior 1,400,000.00 0.00 2021-04-22 2021-05-13 2021-06-26 2021-07-24 2021-08-23 2021-09-27 2021-11-01 2022-11-01 ces for the Preparation of Ge Prone Low-income Communi Based Selection l ation ospatial Asset Management P ties and Local Government S lan. upport GH-MLG-RESILIANCE-292975 Component 3: Participatory -CS-FBS / Consultancy Servic Upgrading of Targeted Flood Fixed Budget Sele Under Implement IDA / 64100 Post Open - National 200,000.00 0.00 2022-05-19 2022-05-26 2022-06-09 2022-08-15 2022-07-14 2022-11-09 2022-08-13 2023-01-05 2022-08-27 2023-01-25 2022-10-01 2022-10-22 2023-10-22 es for the Preparation of Geo Prone Low-income Communi ction ation spatial Management Assets P ties and Local Government S latform upport GH-MLG-RESILIANCE-325992 Component 3: Participatory -CS-QCBS / Consultancy Servi Upgrading of Targeted Flood Quality And Cost- Open - Internationa Pending Impleme IDA / 64100 Prior 1,000,000.00 0.00 2023-06-07 2023-06-28 2023-08-11 2023-09-08 2023-10-08 2023-11-12 2023-12-17 2024-07-25 ces for the Development of a Prone Low-income Communi Based Selection l ntation n Integrated Odaw Basin Man ties and Local Government S agement Plan upport INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLG-RESILIANCE-159394 Component 3: Participatory -CS-INDV / Consultancy Servi Upgrading of Targeted Flood Individual Consult ces for the Preparation of Joi IDA / 64100 Prone Low-income Communi Post Open 50,000.00 0.00 Canceled 2020-08-20 2020-10-01 2020-10-08 2020-10-29 2020-12-03 2021-06-01 ant Selection nt Basin Management Plan fo ties and Local Government S r the Odaw Drainage Basin. upport Page 2 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-04 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Migori County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-MIGORI COUNTY-138559- Project Coordination and Ma Single Stage - One E 34,565,500.0 Pending Imp 2020-08-0 IDA / 59000 Prior Request for Bids Open - National 0.00 2019-10-16 2019-10-21 2019-12-02 2020-01-01 2020-02-05 CW-RFB / Good for the grant i nagement nvelope 0 lementation 3 ssuance KE-MIGORI COUNTY-154147- CW-RFB / CONSTRUCTION W ORKS FOR LOWER KUJA IRRI Supporting County Communi Single Stage - One E Pending Imp 2020-07-0 IDA / 59000 Post Request for Bids Open - National 700,000.00 0.00 2020-01-17 2020-01-22 2020-03-04 2020-04-03 2020-05-08 GATION DEVELOPMENT PROJ ty-Led Development nvelope lementation 7 ECT BLOCK 2.1 UNDER MULTI COMMUNITY PROJECT; COMP ONENT 3 KE-MIGORI COUNTY-218291- CW-RFB / GIRIBE LANDSCAPE RESTORATION AND EARTH D Supporting County Communi Single Stage - One E Under Imple 2021-08-3 AM REHABILITATION. THIS WI IDA / 59000 Post Request for Bids Open - National 355,868.00 0.00 2021-02-10 2022-12-15 2021-02-15 2021-03-29 2021-05-03 2021-04-28 2021-06-02 ty-Led Development nvelope mentation 1 LL CREATE SUSTAINABLE AG RICULTURAL PRODUCTION A ND AVAILABILITY OF WATER FOR COMMUNITY USE. KE-MIGORI COUNTY-221343- CW-RFB / SIABAI LANDSCAPE RESTORATION AND EARTH D AM REHABILITATION PROJECT Supporting County Communi Single Stage - One E Under Imple 2021-09-1 WILL CREATE SUSTAINABLE IDA / 59000 Post Request for Bids Open - National 399,912.03 0.00 2021-02-25 2021-03-12 2021-03-02 2021-04-13 2021-05-03 2021-05-13 2021-06-17 ty-Led Development nvelope mentation 5 AGRICULTURAL PRODUCTION AND AVAILABILITY OF WATER FOR COMMUNITY USE THROU GH CLIMATE SMART AGRICUL TURE TECHNOLOGIES. KE-MIGORI COUNTY-148815- Project Coordination and Ma Request for Quota Single Stage - One E 2020-08-0 IDA / 59000 Post Limited 13,000.00 22,595.43 Completed 2019-12-12 2018-05-30 2020-02-06 2018-06-30 CW-RFQ / CPCU OFFICE REFU nagement tions nvelope 4 RBISHMENT KE-MIGORI COUNTY-230006- Request for Bids - CW-RFB / ROKERE/ KOMAKAR Supporting County Communi Single Stage - One E Works (without pr Under Imple 2022-02-1 IDA / 59000 Post Request for Bids Open - National 322,026.20 0.00 2021-04-20 2021-04-28 2021-07-06 2021-05-27 2021-07-06 2021-04-28 2021-04-25 2022-12-08 2021-09-14 2021-05-19 2021-10-14 2021-11-18 A LANDSCAPE RESTORATION ty-Led Development nvelope equalification) SP mentation 6 AND EARTH DAM REHABILITA D TION PROJECT KE-MIGORI COUNTY-230011- Request for Bids - CW-RFB / THE OTATI LANDSC Supporting County Communi Single Stage - One E Works (without pr Under Imple 2022-02-1 IDA / 59000 Post Request for Bids Open - National 423,909.95 0.00 2021-04-20 2021-04-30 2021-07-06 2021-05-27 2021-07-06 2021-04-28 2021-04-25 2021-09-14 2021-05-19 2021-10-14 2021-05-27 2021-11-18 APE RESTORATION AND EAR ty-Led Development nvelope equalification) SP mentation 6 TH DAM REHABILITATION PR D OJECT KE-MIGORI COUNTY-138553- Project Coordination and Ma Single Stage - One E 13,333,333.0 2020-08-1 CW-RFB / Refurbishment of N IDA / 59000 Prior Request for Bids Open - National 0.00 Canceled 2019-10-30 2019-11-04 2019-12-16 2020-01-15 2020-02-19 nagement nvelope 0 7 ARIGP offices GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MIGORI COUNTY-138546- Project Coordination and Ma Single Stage - One E GO-RFB / Motor cycle procure IDA / 59000 Post Request for Bids Open - National 100,000.00 769.82 Completed 2019-10-03 2019-10-04 2019-10-08 2019-10-04 2019-11-19 2019-10-04 2019-12-19 2019-10-04 2020-01-23 2019-10-04 2020-02-22 2020-09-10 nagement nvelope ment for 20 ward officers. KE-MIGORI COUNTY-148812- Project Coordination and Ma Request for Quota Single Stage - One E Pending Impl GO-RFQ / PURCHASE OF OFFI IDA / 59000 Post Limited 10,000.00 0.00 2019-12-12 2020-02-06 2020-08-04 nagement tions nvelope ementation CE CABINETS FOR CDDCs KE-MIGORI COUNTY-148814- Project Coordination and Ma Request for Quota Single Stage - One E Under Imple GO-RFQ / PURCHASE OF OFFI IDA / 59000 Post Limited 10,360.00 0.00 2019-12-12 2018-05-30 2020-02-06 2020-08-04 nagement tions nvelope mentation CE FURNITURE FOR CPCU KE-MIGORI COUNTY-148820- GO-RFQ / PROCUREMENT OF Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 41,456.00 30,773.47 Completed 2020-01-22 2020-06-05 2020-03-18 2020-06-27 2020-05-17 2020-09-26 SOIL TESTING AND WATER C ty-Led Development tions nvelope ONSERVATION TOOLS KE-MIGORI COUNTY-191573- GO-RFQ / SUPPLY DELIVERY AND INSTALLATION OF IP BA Project Coordination and Ma Request for Quota Single Stage - One E SED TELECONFERENCING SY IDA / 59000 Post Limited 85,000.00 58,380.64 Completed 2020-09-14 2020-10-30 2020-11-11 2020-11-27 2020-12-11 2021-02-26 nagement tions nvelope STEM, FIRE WALL AND NETW ORK ROUTER AND INSTALL I NTERNET CONNECTION IN T HE CPCU OFFICES IN MIGORI COUNTY KE-MIGORI COUNTY-363774- GO-RFQ / PROCUREMENT OF Supporting Community-Driv Request for Quota Single Stage - One E Pending Impl IDA / 59000 Post Limited 23,741.10 0.00 2023-06-14 2023-08-09 2023-11-07 CDDCs AND FPOs SACCOs C en Development tions nvelope ementation OMPUTERS AND PRINTERS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MIGORI COUNTY-164389- CS-CQS / PROVISION OF CON SULTANCY SERVICES ON PRI Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-03-16 2020-09-10 2020-04-06 2022-12-05 2020-05-20 2020-07-24 2020-06-19 2021-03-01 2020-07-24 2021-08-28 MARY PRODUCTION (TIMPS), en Development cation Selection ation VALUE ADDITION AND LINKA GE TO MARKET IN APICULTUR E VALUE CHAIN KE-MIGORI COUNTY-164403- CS-CQS / PROVISION OF CON SULTANCY SERVICES ON PRI Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-03-16 2020-09-10 2020-04-06 2022-12-06 2020-05-20 2020-07-24 2020-06-19 2021-03-01 2020-07-24 2021-08-28 MARY PRODUCTION (TIMPS), en Development cation Selection ation VALUE ADDITION AND LINKA GE TO MARKET IN LOCAL CHI CKEN VALUE CHAIN KE-MIGORI COUNTY-164414- CS-CQS / PROVISION OF CON SULTANCY SERVICES ON PRI Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-03-16 2020-09-10 2020-04-06 2022-12-06 2020-05-20 2021-02-18 2020-06-19 2021-03-01 2020-07-24 2021-08-28 MARY PRODUCTION (TIMPS), en Development cation Selection ation VALUE ADDITION AND LINKA GE TO MARKET IN SWEET PO TATOES VALUE CHAIN KE-MIGORI COUNTY-164420- CS-CQS / PROVISION OF CON SULTANCY SERVICES ON PRI Supporting Community-Driv Consultant Qualifi Under Implement IDA / 59000 Post Open - National 50,000.00 0.00 2020-03-16 2020-09-10 2020-04-06 2022-12-06 2020-05-20 2020-07-24 2020-06-19 2021-03-01 2020-07-24 2021-08-28 MARY PRODUCTION (TIMPS), en Development cation Selection ation VALUE ADDITION AND LINKA GE TO MARKET IN DAIRY CO W MILK VALUE CHAIN INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: Pakistan Punjab Rural Sustainable Water Supply and Sanitation Project (P169071) Project Implementation agency: Local Government Department Date of the Procurement Plan: April 15, 2022 Period covered by this Procurement Plan: April 2022- December 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Rules 2004 Revised 2020, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Punjab Rural Sustainable Water Supply and Sanitation Project PLAN General Information Country: Pakistan 2022-04-15 Bank’s Approval Date of the Original Procurement Plan: 2023-06-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169071 GPN Date: 2021-04-22 Project Name: Punjab Rural Sustainable Water Supply and Sanitation Project Loan / Credit No: IBRD / 92670, IDA / 69250 Local Government and Community Development Department, Government of Punjab Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure PK-LG& CD-289259-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-10-1 / Pilot Scheme Provision of W IBRD / 92670 Post Request for Bids Open - National 1 Envelope proce 2,000,000.00 0.00 2023-01-02 2023-01-07 2023-02-18 2023-03-20 2023-04-24 Infrastructure Development nvelope lementation 5 ater supply & Sanitation (Nor ss (Non Bank-SPD th) / W ) National Procure PK-LG& CD-289261-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-10-1 / Pilot Scheme Provision of W IBRD / 92670 Post Request for Bids Open - National 1 Envelope proce 2,000,000.00 0.00 2023-01-05 2023-01-10 2023-02-21 2023-03-23 2023-04-27 Infrastructure Development nvelope lementation 8 ater supply & Sanitation (Cen ss (Non Bank-SPD tral) / W ) National Procure PK-LG& CD-289264-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-10-1 / Pilot Scheme Provision of W IBRD / 92670 Post Request for Bids Open - National 1 Envelope proce 2,000,000.00 0.00 2023-01-06 2023-01-11 2023-02-22 2023-03-24 2023-04-28 Infrastructure Development nvelope lementation 9 ater Supply & Sanitation (Sou ss (Non Bank-SPD th ) / W ) Request for Quota PK-LG& CD-315561-GO-RFQ Water Supply and Sanitation Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-05-1 / Rehabilitation of Water Sup IBRD / 92670 Post Open - National 330,000.00 0.00 2022-10-05 2022-11-14 Infrastructure Development tions nvelope s (Emergency) SP lementation 3 ply Schemes D -Competitive National Procure PK-LG& CD-349521-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 3,200,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 Infrastructure Development nvelope mentation 1 of Priority Villages Central-I ( ss (Non Bank-SPD Tehsil Bhowana) ) National Procure PK-LG& CD-349557-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,800,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 Infrastructure Development nvelope mentation 1 of Priority Villages Central-II ( ss (Non Bank-SPD Tehsil Pakpattan) ) National Procure PK-LG& CD-349583-CW-RFB ment Document - / Procurement of Civil Works Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,100,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 of Priority Villages South-I (T Infrastructure Development nvelope mentation 1 ss (Non Bank-SPD ehsil Bahawalnagar) ) National Procure PK-LG& CD-349597-CW-RFB ment Document - / Procurement of Civil Works Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,000,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 of Priority Villages South-I (T Infrastructure Development nvelope mentation 1 ss (Non Bank-SPD ehsil Khairpur Tamewali) ) National Procure PK-LG& CD-349608-CW-RFB ment Document - / Procurement of Civil Works Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,200,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 of Priority Villages South-II (T Infrastructure Development nvelope mentation 1 ss (Non Bank-SPD ehsil Kahror Pakka) ) National Procure PK-LG& CD-349614-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E 2024-03-2 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 Canceled 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 Infrastructure Development nvelope 1 of Priority Villages South-III (T ss (Non Bank-SPD ehsil Liaqatpur) ) National Procure PK-LG& CD-349619-CW-RFB ment Document - / Procurement of Civil Works Water Supply and Sanitation Single Stage - One E Under Imple 2024-03-2 IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,500,000.00 0.00 2023-03-20 2023-04-03 2023-03-24 2023-04-03 2023-04-14 2023-05-02 2023-04-24 2023-05-26 of Priority Villages North (Teh Infrastructure Development nvelope mentation 1 ss (Non Bank-SPD sil Kallar Kahar and Kot Momi ) n) National Procure PK-LG& CD-359416-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-05-0 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 3,300,000.00 0.00 2023-05-04 2023-05-07 2023-05-08 2023-05-08 2023-05-29 2023-05-30 2023-06-08 2023-07-10 Infrastructure Development nvelope mentation 5 of Priority Villages (Tehsil Bh ss (Non Bank-SPD awana 02) ) National Procure PK-LG& CD-359417-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-05-0 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 3,600,000.00 0.00 2023-05-04 2023-05-04 2023-05-08 2023-05-08 2023-05-29 2023-05-30 2023-06-08 2023-07-10 Infrastructure Development nvelope mentation 5 of Priority Villages (Khairpur ss (Non Bank-SPD Tamewali 02) ) National Procure PK-LG& CD-359419-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-05-0 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 4,200,000.00 0.00 2023-05-04 2023-05-04 2023-05-08 2023-05-08 2023-05-29 2023-05-30 2023-06-08 2023-07-10 Infrastructure Development nvelope mentation 5 of Priority Villages (Tehsil Ka ss (Non Bank-SPD hror Pakka 02) ) National Procure PK-LG& CD-359420-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-05-0 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 7,600,000.00 0.00 2023-05-04 2023-05-04 2023-05-08 2023-05-08 2023-05-29 2023-05-30 2023-06-08 2023-07-10 Infrastructure Development nvelope mentation 5 of Priority Villages (Tehsil Lia ss (Non Bank-SPD quatpur 02) ) National Procure PK-LG& CD-359421-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-05-0 / Procurement of Civil Works IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 5,200,000.00 0.00 2023-05-04 2023-05-04 2023-05-08 2023-05-08 2023-05-29 2023-05-30 2023-06-08 2023-07-10 Infrastructure Development nvelope mentation 5 of Priority Villages (Tehsil Kot ss (Non Bank-SPD Momin 02) ) National Procure PK-LG& CD-366683-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,250,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-20 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-I, Tehsil Ahmedpur Si ss (Non Bank-SPD al (APS-01) ) National Procure PK-LG& CD-366693-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,510,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-20 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-I, Tehsil Ahmedpur Si ss (Non Bank-SPD al (APS-02) ) National Procure PK-LG& CD-366694-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,050,000.00 0.00 Canceled 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope 5 South-III, Tehsil Rojhan (ROJ- ss (Non Bank-SPD 01) ) National Procure PK-LG& CD-366695-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 600,000.00 0.00 Canceled 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope 5 South-III, Tehsil Rojhan (ROJ- ss (Non Bank-SPD 02) ) National Procure PK-LG& CD-366696-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 960,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 South-III, Tehsil Rojhan (ROJ- ss (Non Bank-SPD 03) ) National Procure PK-LG& CD-366697-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,360,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 South-III, Tehsil Liaquatpur (L ss (Non Bank-SPD QR-01) ) Page 1 National Procure PK-LG& CD-366698-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,500,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 South-I, Tehsil Bahawalnagar ss (Non Bank-SPD (BWN-02) ) National Procure PK-LG& CD-366699-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,050,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 South-I, Tehsil Bahawalnagar ss (Non Bank-SPD (BWN-03) ) National Procure PK-LG& CD-366701-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,750,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 South-I, Tehsil Bahawalnagar ss (Non Bank-SPD (BWN-04) ) National Procure PK-LG& CD-366702-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,200,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 South-I, Tehsil Bahawalnagar ss (Non Bank-SPD (BWN-05) ) National Procure PK-LG& CD-366704-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,600,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 South-II, Tehsil Shujaabad (SJ ss (Non Bank-SPD D-01) ) National Procure PK-LG& CD-366706-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,700,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 South-II, Tehsil Shujaabad (SJ ss (Non Bank-SPD D-02) ) National Procure PK-LG& CD-366707-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,900,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 South-II, Tehsil Shujaabad (SJ ss (Non Bank-SPD D-03) ) National Procure PK-LG& CD-366708-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,350,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 South-II, Tehsil Shujaabad (SJ ss (Non Bank-SPD D-04) ) National Procure PK-LG& CD-366711-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Pending Imp 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 750,000.00 0.00 2023-06-14 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope lementation 5 North, Tehsil Noorpur Thal (N ss (Non Bank-SPD PT-01) ) National Procure PK-LG& CD-366713-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,850,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 North, Tehsil Isa Khel (ISK-01 ss (Non Bank-SPD ) ) National Procure PK-LG& CD-366715-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,150,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 North, Tehsil Isa Khel (ISK-02 ss (Non Bank-SPD ) ) National Procure PK-LG& CD-366716-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,250,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 North, Tehsil Isa Khel (ISK-03 ss (Non Bank-SPD ) ) National Procure PK-LG& CD-366717-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,900,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-II, Tehsil Pakpattan (P ss (Non Bank-SPD KN-02) ) National Procure PK-LG& CD-366718-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,500,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-II, Tehsil Pakpattan (P ss (Non Bank-SPD KN-03) ) National Procure PK-LG& CD-366719-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,200,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-II, Tehsil Pakpattan (P ss (Non Bank-SPD KN-04) ) National Procure PK-LG& CD-366720-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 1,650,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-II, Tehsil Pakpattan (P ss (Non Bank-SPD KN-05) ) National Procure PK-LG& CD-366721-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 700,000.00 0.00 2023-06-14 2023-06-15 2023-06-18 2023-06-18 2023-07-09 2023-07-19 2023-08-30 Infrastructure Development nvelope mentation 5 Central-II, Tehsil Pakpattan (P ss (Non Bank-SPD KN-06) ) National Procure PK-LG& CD-366916-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 950,000.00 0.00 2023-06-15 2023-06-15 2023-06-19 2023-06-18 2023-07-10 2023-07-20 2023-08-31 Infrastructure Development nvelope mentation 6 South-III, Tehsil Rojhan (ROJ- ss (Non Bank-SPD 02) ) National Procure PK-LG& CD-366917-CW-RFB ment Document - Water Supply and Sanitation Single Stage - One E Under Imple 2024-06-2 / Procurement of Civil Works, IDA / 69250 Post Request for Bids Open - National 1 Envelope proce 2,860,000.00 0.00 2023-06-15 2023-06-15 2023-06-19 2023-06-18 2023-07-10 2023-07-20 2023-08-31 Infrastructure Development nvelope mentation 6 South-III, Tehsil Rojhan (ROJ- ss (Non Bank-SPD 01) ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-LG& CD-289353-GO-RFQ Request for Quota Single Stage - One E Pending Impl IBRD / 92670 Project Management Post Open - National 80,000.00 0.00 2022-05-07 2022-06-11 2022-09-09 / Procurement of Office Equip tions nvelope ementation ment/G PK-LG& CD-289354-GO-RFQ Request for Quota Single Stage - One E Pending Impl IBRD / 92670 Project Management Post Open - National 100,000.00 0.00 2022-05-09 2022-06-09 2022-08-08 / Procurement of Office Furni tions nvelope ementation ture /G PK-LG& CD-289355-GO-RFQ Request for Quota Single Stage - One E Pending Impl IBRD / 92670 Project Management Post Open - National 400,000.00 0.00 2022-05-13 2022-06-17 2022-12-14 / Procurement of Operational tions nvelope ementation Vehicles PK-LG& CD-289352-GO-RFB Single Stage - One E Pending Impl IBRD / 92670 Project Management Post Request for Bids Open - National 200,000.00 0.00 2022-04-29 2022-05-04 2022-05-25 2022-05-30 2022-06-13 2022-09-11 / Procurement of IT Equipme nvelope ementation nt /G PK-LG& CD-315566-GO-RFQ Service Delivery Improveme Request for Quota Single Stage - One E IBRD / 92670 Post Open - National 12,100.00 0.00 Signed 2022-09-24 2023-05-23 2022-10-09 2022-11-08 / Package-V: Chlorine Tablets nt tions nvelope PK-LG& CD-315555-GO-RFQ Service Delivery Improveme Request for Quota Single Stage - One E / Procurement of double cabi IDA / 69250 Post Open - National 110,000.00 0.00 Signed 2022-09-24 2023-05-24 2022-10-08 2022-12-07 nt tions nvelope n 4x4 vehicles PK-LG& CD-315558-GO-RFQ Service Delivery Improveme Request for Quota Single Stage - One E Pending Impl IDA / 69250 Post Open - National 85,000.00 0.00 2022-09-26 2022-10-10 2022-11-24 / Procurement of Equipment nt tions nvelope ementation Page 2 PK-LG& CD-316170-GO-DIR / Service Delivery Improveme Under Imple IDA / 69250 Post Direct Selection Direct - National 1,450,000.00 0.00 2022-09-16 2022-11-01 2022-09-21 2022-11-10 2022-09-30 2023-01-28 Procurement of Heavy Machi nt mentation nery PK-LG& CD-316171-GO-RFQ Water Supply and Sanitation Request for Quota Single Stage - One E Pending Impl / Procurement of Water Filtra IDA / 69250 Prior Open - National 2,100,000.00 0.00 2022-09-24 2022-10-09 2022-12-08 Infrastructure Development tions nvelope ementation tion Systems PK-LG& CD-316174-GO-RFQ Service Delivery Improveme Request for Quota Single Stage - One E IDA / 69250 Post Open - National 90,000.00 0.00 Signed 2022-09-27 2023-05-23 2022-10-10 2022-10-11 / Procurement of Generators nt tions nvelope PK-LG& CD-289345-GO-RFB / Design, Supply and Installat Single Stage - One E Under Imple IBRD / 92670 Project Management Prior Request for Bids Open - National 3,000,000.00 0.00 2022-09-15 2022-09-20 2022-11-01 2022-12-01 2023-01-05 2024-06-28 ion of Enterprise Resource Pl nvelope mentation anning [ERP] and Manageme nt Information System PK-LG& CD-317580-GO-RFQ / Procurement of Goods for R Request for Quota Single Stage - One E Under Imple IDA / 69250 Project Management Post Open - National 96,000.00 0.00 2022-10-29 2022-11-28 2023-03-28 enovation of PRSC Head Offic tions nvelope mentation e and Miscellaneous Item PK-LG& CD-325075-GO-RFQ Request for Quota Single Stage - One E Under Imple / procurement of Office Furni IDA / 69250 Project Management Post Open - National 85,000.00 0.00 2022-11-15 2023-05-27 2022-12-07 2023-02-05 tions nvelope mentation ture for PRMSC Tehsil Offices PK-LG& CD-325076-GO-RFQ Request for Quota Single Stage - One E Under Imple / Procurement of General Offi IDA / 69250 Project Management Post Open - National 50,000.00 0.00 2022-11-17 2023-05-27 2022-12-14 2023-01-13 tions nvelope mentation ce Equipment PK-LG& CD-325074-GO-RFQ Request for Quota Single Stage - One E Pending Impl / Procurement of Printing and IDA / 69250 Project Management Post Open - National 85,000.00 0.00 2022-11-17 2022-12-15 2022-12-24 tions nvelope ementation Miscellaneous IT Equipment PK-LG& CD-315548-GO-DIR / Service Delivery Improveme Under Imple IDA / 69250 Post Direct Selection Direct - National 1,100,000.00 0.00 2022-09-14 2022-11-01 2022-09-19 2022-11-10 2022-10-05 2022-11-19 Procurement of Sucker & Jett nt mentation er Unit PK-LG& CD-331360-GO-RFB / Procurement of Laptops & D Single Stage - One E IDA / 69250 Project Management Post Request for Bids Open - National 210,000.00 0.00 Signed 2022-12-13 2023-01-23 2022-12-16 2023-05-23 2023-01-13 2023-02-20 2023-01-14 2023-03-16 2023-02-05 2023-08-04 esktops for PRMSC Head Offi nvelope ce & Tehsil Offices PK-LG& CD-300945-GO-RFQ Request for Quota Single Stage - One E Under Imple / Office Fixtures & Portable In IBRD / 92670 Project Management Post Open - National 60,000.00 0.00 2022-06-24 2022-06-28 2022-06-30 tions nvelope mentation stallations and Miscellaneous office Items PK-LG& CD-351779-GO-RFQ Request for Quota Single Stage - One E Under Imple / Installation of Monitoring an IDA / 69250 Project Management Post Open - National 60,000.00 0.00 2023-04-06 2023-04-12 2023-05-21 2023-06-20 tions nvelope mentation d Vehicle Tracking System PK-LG& CD-359711-GO-RFB / Installation, Commissioning Water Supply and Sanitation Single Stage - One E Pending Impl and Testing for Solarization o IDA / 69250 Post Request for Bids Open - National 1,000,000.00 0.00 2023-05-10 2023-05-12 2023-06-02 2023-06-07 2023-07-03 2023-10-31 Infrastructure Development nvelope ementation f Water Supply and Sewerag e Schemes under PRSWSSP P hase-I (70 Villages) PK-LG& CD-362800-GO-RFB / Installation, Commissioning Water Supply and Sanitation Single Stage - One E Pending Impl and Testing for Solarization o IDA / 69250 Post Request for Bids Open - National 1,800,000.00 0.00 2023-05-22 2023-05-27 2023-06-17 2023-06-22 2023-07-18 2023-11-15 Infrastructure Development nvelope ementation f Water Supply and Sewerag e Schemes under PRSWSSP P hase-I (70 Villages) Part-II NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-LG& CD-332020-NC-DIR / Service Delivery Improveme Under Imple Water & Waste Water Quality IDA / 69250 Prior Direct Selection Direct - National 3,000,000.00 0.00 2023-03-15 2023-02-24 2023-03-20 2023-04-07 2023-04-24 2028-04-22 nt mentation Monitoring PK-LG& CD-289231-NC-RFB / Procurement of the Services Behavior Change and Capaci Single Stage - One E of Implementation Partners f IBRD / 92670 Prior Request for Bids Open - National 3,500,000.00 0.00 Canceled 2022-12-02 2022-12-07 2023-01-18 2023-02-17 2023-03-24 2028-06-30 ty Development nvelope or Behavioral Change Comm unications & Capacity Buildin g (South)/NCS PK-LG& CD-289205-NC-RFB / Procurement of the Services Behavior Change and Capaci Single Stage - One E of Implementation Partners f IBRD / 92670 Prior Request for Bids Open - National 3,500,000.00 0.00 Canceled 2022-12-02 2022-12-07 2023-01-18 2023-02-17 2023-03-24 2023-10-02 ty Development nvelope or Behavioural Change Com munications & Capacity Build ing (Central)/NCS PK-LG& CD-289107-NC-RFB / Procurement of the Services Behavior Change and Capaci Single Stage - One E of Implementation Partners f IBRD / 92670 Prior Request for Bids Open - National 3,500,000.00 0.00 Canceled 2022-12-02 2022-12-07 2023-01-18 2023-02-17 2023-03-24 2028-06-30 ty Development nvelope or Behavioural Change Com munications & Capacity Build ing (North)/NCS PK-LG& CD-316926-NC-RFB / Behavior Change and Capaci Single Stage - One E Under Imple Behavior Change and Capaci IBRD / 92670 Prior Request for Bids Open - National 3,500,000.00 0.00 2022-12-26 2023-02-26 2022-12-31 2023-03-02 2023-02-05 2023-04-07 2023-02-20 2023-05-16 2023-03-20 2025-03-19 ty Development nvelope mentation ty Development Program PK-LG& CD-332746-NC-RFB / Procurement of the Services Behavior Change and Capaci Single Stage - One E Pending Impl of Implementation Partners f IDA / 69250 Prior Request for Bids Open - National 9,000,000.00 0.00 2023-07-20 2023-07-25 2023-09-05 2023-10-05 2023-11-09 2026-11-13 ty Development nvelope ementation or Behavioral Change Comm unications & Capacity Buildin g (Multiple Lots) PK-LG& CD-332015-NC-RFB / Single Stage - One E Impact Evaluation of PRSWSS IDA / 69250 Project Management Post Request for Bids Open - National 1,200,000.00 0.00 Canceled 2023-01-26 2023-01-31 2023-02-28 2023-03-15 2023-04-06 2025-05-25 nvelope P (Baseline and Midline) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 PK-LG& CD-289348-CS-QCBS Water Supply and Sanitation Quality And Cost- Pending Impleme / TPV (TPV (baseline, midline IBRD / 92670 Prior Open - National 1,500,000.00 0.00 2022-09-30 2022-10-21 2022-12-04 2023-01-01 2023-01-31 2023-03-07 2023-04-11 2028-06-30 Infrastructure Development Based Selection ntation and end line)/CS PK-LG& CD-289968-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-04-25 2022-06-27 2022-05-16 2023-05-24 2022-06-06 2022-08-12 2022-06-13 2022-09-23 2022-07-11 2023-04-07 Infrastructure Development cation Selection , Design and Supervision Sou th PK-LG& CD-289097-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-04-26 2022-06-27 2022-05-17 2023-05-23 2022-06-07 2022-08-01 2022-07-07 2022-10-24 2022-08-11 2023-05-08 Infrastructure Development cation Selection , Design and Supervision Cen tral /CS PK-LG& CD-289966-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-04-18 2022-06-27 2022-05-09 2023-05-23 2022-05-30 2022-08-12 2022-06-29 2022-09-23 2022-08-03 2023-04-30 Infrastructure Development cation Selection , Design and Supervision Nor th/CS PK-LG& CD-292584-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-05-10 2022-06-27 2022-05-31 2023-05-23 2022-06-21 2022-08-12 2022-07-21 2022-09-23 2022-08-11 2023-05-08 Infrastructure Development cation Selection , Design and Supervision Nor th- A/CS PK-LG& CD-292585-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-05-11 2022-06-27 2022-06-01 2023-05-23 2022-06-22 2022-08-12 2022-07-22 2022-09-23 2022-08-12 2023-05-09 Infrastructure Development cation Selection , Design and Supervision Cen tral - A /CS PK-LG& CD-292587-CS-CQS / Water Supply and Sanitation Consultant Qualifi Pilot Services for Engineering IBRD / 92670 Post Open - National 300,000.00 0.00 Signed 2022-05-12 2022-06-27 2022-06-02 2023-05-23 2022-06-23 2022-08-01 2022-07-23 2022-09-23 2022-08-13 2023-05-10 Infrastructure Development cation Selection , Design and Supervision Sou th-A /CS PK-LG& CD-289349-CS-QCBS Quality And Cost- IBRD / 92670 Project Management Prior Open - National 1,000,000.00 0.00 Canceled 2022-07-05 2022-07-26 2022-09-08 2022-10-06 2022-11-05 2022-12-10 2023-01-14 2028-06-30 / Internal Audit Firm/CS Based Selection PK-LG& CD-289099-CS-CQS / Procurement of Services for Water Supply and Sanitation Consultant Qualifi IBRD / 92670 Post Open - National 300,000.00 0.00 Canceled 2022-05-06 2022-05-27 2022-06-17 2022-06-24 2022-07-08 2023-01-04 Development of Punjab BCC Infrastructure Development cation Selection WASH Strategy PK-LG& CD-333387-CS-QCBS Quality And Cost- IDA / 69250 Project Management Post Open - National 400,000.00 0.00 Canceled 2026-03-12 2026-04-02 2026-05-16 2026-06-13 2026-07-13 2026-08-17 2026-09-21 2027-09-21 / Impact Evaluation Firm/ End Based Selection line PK-LG& CD-334176-CS-CQS / Water Supply and Sanitation Consultant Qualifi Procurement for hiring of Fir IDA / 69250 Post Open - National 250,000.00 0.00 Signed 2023-01-04 2023-01-09 2023-01-19 2023-02-27 2023-02-02 2023-03-30 2023-02-09 2023-04-12 2023-02-23 2024-02-23 Infrastructure Development cation Selection m for Tariff Appraisal Study f or PRSWSSP PK-LG& CD-346557-CS-CQS / Consultant Qualifi Consultancy Services for Co IDA / 69250 Project Management Post Open - National 100,000.00 0.00 Under Review 2023-03-07 2023-06-22 2023-03-28 2023-04-11 2023-05-11 2023-05-25 2024-05-24 cation Selection mmunication/PR/Marketing of PRSWSSP PK-LG& CD-289246-CS-QCBS Water Supply and Sanitation Quality And Cost- Under Implement / Services for Engineering, D IBRD / 92670 Prior Open - National 3,500,000.00 0.00 2023-04-14 2023-05-16 2023-05-05 2023-06-17 2023-05-27 2023-06-24 2023-07-09 2023-07-31 2023-08-22 2028-08-25 Infrastructure Development Based Selection ation esign and Supervision North / CS PK-LG& CD-289251-CS-QCBS Water Supply and Sanitation Quality And Cost- Under Implement / Services for Engineering, D IBRD / 92670 Prior Open - National 3,750,000.00 0.00 2023-04-14 2023-05-16 2023-05-05 2023-06-17 2023-05-27 2023-06-24 2023-07-09 2023-07-31 2023-08-22 2028-08-23 Infrastructure Development Based Selection ation esign and Supervision Centra l /CS PK-LG& CD-289253-CS-QCBS Water Supply and Sanitation Quality And Cost- Under Implement / Services for Engineering, D IBRD / 92670 Prior Open - National 3,000,000.00 0.00 2023-04-14 2023-05-16 2023-05-05 2023-06-17 2023-05-27 2023-06-24 2023-07-09 2023-07-31 2023-08-22 2028-08-21 Infrastructure Development Based Selection ation esign and Supervision South- I /CS PK-LG& CD-353899-CS-QCBS Water Supply and Sanitation Quality And Cost- Under Implement / Services for Engineering, D IBRD / 92670 Prior Open - National 3,500,000.00 0.00 2023-04-14 2023-05-16 2023-05-05 2023-06-17 2023-05-27 2023-06-24 2023-07-09 2023-07-31 2023-08-22 2028-08-25 Infrastructure Development Based Selection ation esign and Supervision South- II /CS PK-LG& CD-353901-CS-QCBS Water Supply and Sanitation Quality And Cost- Under Implement / Services for Engineering, D IBRD / 92670 Prior Open - National 3,500,000.00 0.00 2023-04-14 2023-05-16 2023-05-05 2023-06-17 2023-05-27 2023-06-24 2023-07-09 2023-07-31 2023-08-22 2028-08-25 Infrastructure Development Based Selection ation esign and Supervision South- III /CS PK-LG& CD-359704-CS-LCS / Least Cost Selecti Consultancy Services for Imp IDA / 69250 Project Management Prior Open - National 3,600,000.00 0.00 Canceled 2023-05-10 2023-05-19 2023-05-31 2023-05-26 2023-06-17 2023-07-15 2023-07-22 2023-08-03 2023-08-31 2028-01-17 on act Evaluation of PRSWSSP PK-LG& CD-364852-CS-QCBS Quality And Cost- Under Implement IDA / 69250 Project Management Prior Open - National 3,600,000.00 0.00 2023-06-06 2023-06-09 2023-06-27 2023-06-24 2023-07-14 2023-08-11 2023-08-21 2023-09-05 2023-09-29 2028-02-15 / Impact Evaluation of PRSWS Based Selection ation SP INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-LG& CD-316922-CS-INDV Individual Consult IDA / 69250 Project Management Post Open - National 30,000.00 0.00 Under Review 2022-09-26 2022-09-15 2022-10-22 2022-10-29 2022-11-08 2023-11-08 / MIS System Architect ant Selection PK-LG& CD-316924-CS-INDV Individual Consult IDA / 69250 Project Management Post Open - National 25,000.00 0.00 Under Review 2022-09-27 2022-09-15 2022-10-23 2022-10-28 2022-11-07 2023-11-07 / Principal Technology Adviso ant Selection r (ERP) PK-LG& CD-289361-CS-INDV Individual Consult IBRD / 92670 Project Management Post Open 250,000.00 0.00 Canceled 2022-05-03 2022-06-07 2022-06-14 2022-06-21 2028-06-30 / Safeguard Specialist /IC ant Selection PK-LG& CD-289357-CS-INDV / Procurement Specialist /IC/ Individual Consult IBRD / 92670 Project Management Post Open 250,000.00 0.00 Canceled 2022-04-30 2022-06-04 2022-06-11 2022-06-18 2028-06-30 Sr. Procurement & Contract S ant Selection pecialist PK-LG& CD-325078-CS-INDV Individual Consult / Individual Consultant for Ba IDA / 69250 Project Management Post Open - National 20,000.00 0.00 Canceled 2022-11-16 2022-11-30 2022-12-28 2023-01-05 2023-07-04 ant Selection seline, Midline and Endline S urvey PK-LG& CD-289359-CS-INDV Individual Consult IBRD / 92670 Project Management Post Open 250,000.00 0.00 Canceled 2022-07-07 2022-08-11 2022-08-18 2022-08-25 2028-06-30 / M& E Specialist/IC ant Selection PK-LG& CD-289356-CS-INDV Individual Consult IBRD / 92670 Project Management Prior Open 300,000.00 0.00 Canceled 2022-04-30 2022-06-04 2022-06-11 2022-06-18 2028-06-30 / Project Coordinator /IC ant Selection PK-LG& CD-289360-CS-INDV Individual Consult IBRD / 92670 Project Management Post Open 250,000.00 0.00 Canceled 2022-05-10 2022-06-14 2022-06-21 2022-06-28 2028-06-30 / Environmental specialist/IC ant Selection Page 4 PK-LG& CD-289358-CS-INDV Individual Consult IBRD / 92670 Project Management Post Open 250,000.00 0.00 Canceled 2022-05-03 2022-06-07 2022-06-14 2022-06-21 2028-06-30 / Financial Management Spec ant Selection ialist /IC PK-LG& CD-332736-CS-INDV Individual Consult IDA / 69250 Project Management Post Limited 13,000.00 0.00 Signed 2022-12-23 2023-04-03 2022-12-24 2023-03-20 2022-12-26 2023-04-10 2023-01-14 2023-04-14 / Procurement Specialist ant Selection PK-LG& CD-332737-CS-INDV Individual Consult Pending Impleme IDA / 69250 Project Management Post Limited 12,000.00 0.00 2022-12-23 2022-12-25 2022-12-28 2023-01-07 2023-04-07 / Contract Management Spec ant Selection ntation ialist PK-LG& CD-332740-CS-INDV Individual Consult IDA / 69250 Project Management Post Limited 20,000.00 0.00 Signed 2022-12-25 2023-03-27 2022-12-27 2023-03-01 2023-01-17 2023-03-31 2023-02-21 2023-08-20 / Legal Expert ant Selection PK-LG& CD-362799-CS-INDV Water Supply and Sanitation Individual Consult Under Implement / Engineering Design Review IDA / 69250 Post Limited 10,000.00 0.00 2023-05-22 2023-06-20 2023-05-25 2023-05-30 2023-06-09 2023-10-07 Infrastructure Development ant Selection ation Consultant for 200 Villages Page 5 Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by <mention name of PIU> 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other July 9, 2010 methods July 9, 2010 PROCUREMENT Tanzania : Citizen-Centric Judicial Modernization and Justice Service Delivery PLAN General Information Country: Tanzania 2016-08-05 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155759 GPN Date: 2022-06-09 Project Name: Citizen-Centric Judicial Modernization and Justice Service Delivery Loan / Credit No: IDA / 57780, IDA / 70580 Judiciary of Tanzania Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-18206-CW- Component 2: Skills Develop DIR / Construction of training 2018-03-0 2020-01 IDA / 57780 ment, Inspection and Perfor Prior Direct Selection Direct 35,175.53 Completed 2017-07-14 2017-06-29 2017-07-19 2017-08-22 2017-09-06 2017-08-24 room at Kisutu Residence Ma 5 -22 mance Management gistrate Court location in Dar es Salaam TZ-JUDICIARY TZ-118965-C W-RFB / Construction of Integ rated Justice Centers (IJCs) in Component 3: Access to Just Open - Internationa Single Stage - One E 22,309,086. 2020-04-1 IDA / 57780 Prior Request for Bids Signed 2019-06-28 2019-07-31 2019-07-03 2019-08-01 2019-08-14 2019-09-20 2019-09-13 2019-12-04 2019-10-18 2020-01-11 Six Selected Locations of Mw ice and Public Trust l nvelope 76 5 anza, Morogoro, Arusha, Dod oma and Dar es Salaam-Six L ots TZ-JUDICIARY TZ-211158-C W-RFB / Construction of Subo Component 3: Access to Just Single Stage - One E 7,950,439.8 2021-09-0 IDA / 57780 Prior Request for Bids Open - National Signed 2020-12-28 2021-02-04 2021-01-04 2021-02-11 2021-02-08 2021-03-23 2021-02-28 2021-08-24 2021-04-04 2021-09-11 rdinate Courts in twenty five( ice and Public Trust nvelope 1 1 25) Selected Locations aroun d Tanzania. TZ-JUDICIARY TZ-364564-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Four Selected Locations of Si nvelope proc ngida, Simiyu, Geita and Pem ess) ba-Four Lots TZ-JUDICIARY TZ-364566-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Five Selected Locations of Ka nvelope proc tavi, Songwe, Njombe, Mtwar ess) a and Songea-Five Lots TZ-JUDICIARY TZ-364568-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Five Selected Locations of Pw nvelope proc ani, Tanga, Moshi, Manyara a ess) nd Lindi-Five Lots TZ-JUDICIARY TZ-9217-CW-D IR / Construction of ten (10) c Component 3: Access to Just 2017-11-1 ourthouses for subordinate c IDA / 57780 Prior Direct Selection Direct 0.00 Canceled 2017-04-10 2017-04-15 2017-05-20 ice and Public Trust 6 ourts Primary Court and Trai ning room at Kisutu RMs Cou rt. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-4371-GO-R Component 1: Governance, Request for Quota Single Stage - One E FQ / Design, Editing and Print IDA / 57780 Organization and Systems D Post Limited 40,909.50 Completed 2016-12-18 2016-12-05 2017-02-12 2017-01-24 2017-08-11 2017-02-08 tions nvelope ing of Strategic plan, Brochur evelopment es TZ-JUDICIARY TZ-9220-GO-R Component 1: Governance, Single Stage - One E FB / Supply of IT Equipment f IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-07-15 2017-07-20 2017-08-31 2017-09-30 2017-11-04 2018-05-03 nvelope or registries & DJSIE evelopment TZ-JUDICIARY TZ-30083-GO- Component 2: Skills Develop RFQ / Procurement of office f Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 32,612.45 Completed 2017-09-30 2017-10-04 2017-11-05 2017-11-25 2018-05-04 2018-01-23 acilities for training center at tions nvelope mance Management Kisutu Resident Magistrate C ourt-Dar es salaam TZ-JUDICIARY TZ-30400-GO- RFQ / Procurement of office v Component 2: Skills Develop Request for Quota Single Stage - One E ideo conference facilities for IDA / 57780 ment, Inspection and Perfor Post Limited 83,134.05 Completed 2017-10-03 2017-10-05 2017-11-28 2017-10-31 2018-05-27 2018-04-16 tions nvelope training center at Kisutu resi mance Management dent magistrate court-Dar es salaam. TZ-JUDICIARY TZ-30103-GO- Component 2: Skills Develop RFQ / Procurement of IT equi Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 77,394.71 Completed 2017-10-04 2017-10-12 2017-11-09 2017-11-14 2018-05-08 2018-05-16 pment for training center at tions nvelope mance Management Kisutu Resident Magistrate C ourt- Dar es Salaam. TZ-JUDICIARY TZ-37777-GO- RFQ / Supply, Installation and Component 1: Governance, Commissioning of Furniture, Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 91,246.04 Completed 2017-11-27 2017-11-28 2018-01-08 2018-01-19 2018-02-05 2018-04-06 LAN, CCTV camera and Bio-m tions nvelope evelopment etric Door Access System for Retooling of Judiciary Deliver y Unit Office. TZ-JUDICIARY TZ-40300-GO- RFB / Supply, Installation, Te Component 1: Governance, st and Commissioning of Vid Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 594,512.13 Completed 2017-12-21 2018-01-11 2017-12-26 2018-01-25 2018-02-09 2018-02-24 2018-03-21 2018-03-31 2018-05-15 2018-09-27 2019-06-18 eo Conferencing facilities, Au nvelope evelopment dio Visual and Recording equ ipment at four selected Court s TZ-JUDICIARY TZ-64942-GO- Component 1: Governance, Request for Quota Single Stage - One E RFQ / Procurement of ICT eq IDA / 57780 Organization and Systems D Post Limited 95,937.33 Completed 2018-06-16 2018-06-14 2018-08-11 2018-08-07 2019-02-07 2018-09-21 tions nvelope uipment for new directorates evelopment TZ-JUDICIARY TZ-64971-GO- Component 1: Governance, Request for Quota Single Stage - One E RFQ / Procurement of furnitur IDA / 57780 Organization and Systems D Post Limited 71,421.54 Completed 2018-06-16 2018-06-14 2018-08-11 2018-07-17 2019-02-07 2018-11-23 tions nvelope e for new directorates evelopment Page 1 TZ-JUDICIARY TZ-67572-GO- Component 3: Access to Just Single Stage - One E RFB / Procurement of furnitur IDA / 57780 Prior Request for Bids Open - National 1,785,846.11 Completed 2018-07-25 2019-01-09 2018-07-30 2019-01-29 2018-09-10 2019-02-28 2018-10-10 2019-05-15 2018-11-14 2019-07-02 2019-05-13 2023-02-18 ice and Public Trust nvelope e for eighteen (18) new court buildings. TZ-JUDICIARY TZ-87170-GO- Component 2: Skills Develop UN Agencies (Dire UN / Procurement of 57 moto IDA / 57780 ment, Inspection and Perfor Prior Direct 1,701,529.79 Completed 2018-11-30 2018-12-05 2019-01-16 2019-01-28 2019-07-15 2019-06-30 ct) r vehicles mance Management TZ-JUDICIARY TZ-62259-GO- Component 2: Skills Develop Open - Internationa Single Stage - One E RFB / Procurement of 57 mot IDA / 57780 ment, Inspection and Perfor Prior Request for Bids 0.00 Canceled 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 2019-03-20 l nvelope or vehicles mance Management TZ-JUDICIARY TZ-91934-GO- RFB / Supply, Installation, Te sting and Commissioning of L Component 3: Access to Just Single Stage - One E ocal Area Network and other IDA / 57780 Post Request for Bids Open - National 592,972.08 Completed 2018-12-28 2019-04-25 2019-01-02 2019-01-30 2019-07-12 2019-03-01 2019-08-19 2019-04-05 2019-11-20 2019-10-02 2020-07-26 ice and Public Trust nvelope ICT equipment for Moderniza tion of ICT Infrastructure to T wenty Three (23) New Court s Buildings. TZ-JUDICIARY TZ-107689-GO -DIR / SUPPLY AND INSTALLA TION OF NETWORK/FIBER CO Component 1: Governance, NNECTIVITY AND PROVISION IDA / 57780 Organization and Systems D Prior Direct Selection Direct 1,814,257.31 Signed 2019-04-01 2019-04-24 2019-04-06 2019-05-22 2019-05-11 2019-07-29 2019-11-07 OF DATA AND INTERNET SER evelopment VICES TO HIGH COURTS, REG IONAL MAGISTRATES AND DI STRICT COURTS BUILDINGS C OUNTRYWIDE. TZ-JUDICIARY TZ-110239-GO Component 2: Skills Develop -RFQ / PROCUREMENT OF PR Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 42,683.08 Completed 2019-04-20 2019-05-02 2019-06-15 2019-06-17 2019-12-12 2019-10-28 OTECTIVE ACCESSORIES FOR tions nvelope mance Management THE 57 PROCURED MOTOR V EHICLES. TZ-JUDICIARY TZ-113691-GO Component 1: Governance, -RFB / Procurement of Gadge Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 219,227.79 Completed 2019-05-10 2019-05-10 2019-05-15 2019-06-26 2019-06-14 2019-07-26 2019-07-23 2019-08-30 2019-08-02 2020-02-26 2020-01-30 ts (POS) for utilization of GeP nvelope evelopment G government system TZ-JUDICIARY TZ-118395-GO Component 1: Governance, -RFQ / Procurement of Stand Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 26,526.32 Completed 2019-06-26 2019-06-20 2019-08-21 2019-09-24 2020-02-17 2020-01-19 by Generator for High Court- tions nvelope evelopment Commercial Division TZ-JUDICIARY TZ-120930-GO Component 2: Skills Develop -RFQ / Procurement of ICT eq Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 22,480.99 Completed 2019-07-06 2019-07-22 2019-08-31 2019-08-30 2020-02-27 2019-10-31 uipment and furniture for Co tions nvelope mance Management urt brokers and advocate sec tion TZ-JUDICIARY TZ-144324-GO Component 3: Access to Just Request for Quota Single Stage - One E -RFQ / PROCUREMENT OF ICT IDA / 57780 Post Limited 8,221.98 Completed 2019-11-19 2019-12-06 2020-01-14 2020-04-01 2020-07-12 2020-06-25 ice and Public Trust tions nvelope EQUIPMENT FOR LEGAL AID UNIT - MOCLA TZ-JUDICIARY TZ-159885-GO Component 1: Governance, -UN / Procurement of ICT equ UN Agencies (Dire IDA / 57780 Organization and Systems D Prior Direct 1,370,192.72 Completed 2020-02-25 2020-05-18 2020-03-01 2020-05-19 2020-04-19 2020-05-16 2020-10-16 2020-10-13 pment for registries, Court of ct) evelopment Appeal and centres. TZ-JUDICIARY TZ-168252-GO Component 1: Governance, -DIR / Supply of ICT equipme IDA / 57780 Organization and Systems D Post Direct Selection Direct 268,181.31 Completed 2020-04-15 2020-04-15 2020-04-17 2020-04-15 2020-04-20 2020-04-18 2020-04-25 2021-05-09 nt to facilitate e-court service evelopment s as a response measures ag ainst COVID-19 TZ-JUDICIARY TZ-178077-GO -RFB / Procurement of furnitu Component 3: Access to Just Single Stage - One E re for six Integrated Justice C IDA / 57780 Prior Request for Bids Open - National 3,069,984.39 Completed 2020-06-26 2020-06-29 2020-07-01 2020-06-30 2020-08-12 2020-07-28 2020-09-11 2020-08-20 2020-10-16 2020-10-28 2021-04-14 2021-12-18 ice and Public Trust nvelope enters located in Mwanza, Ar usha,Morogoro,Dodoma, Tem eke and Kinondoni. TZ-JUDICIARY TZ-180768-GO -RFB / SUPPLY, INSTALLATIO N AND CONFIGURATION OF Component 1: Governance, Single Stage - One E MICROSOFT OFFICE PROFESS IDA / 57780 Organization and Systems D Post Request for Bids Open - National 650,286.94 Completed 2020-06-26 2020-07-16 2020-07-01 2020-07-17 2020-07-22 2020-08-03 2020-07-29 2020-09-01 2020-08-10 2020-11-21 2020-09-07 2020-12-24 nvelope IONAL 2019 FOR 1388 LAPTO evelopment PS AND 14 DESKTOPS FOR M AGISTRATES AND COURT OF APPEAL REGISTRIES TZ-JUDICIARY TZ-180771-GO -RFQ / PROCUREMENT OF SC Component 3: Access to Just Request for Quota Single Stage - One E ANNERS FOR TWO INTERGRA IDA / 57780 Post Limited 27,451.65 Completed 2020-08-04 2020-06-25 2020-09-13 2020-12-05 2020-09-22 2021-05-20 ice and Public Trust tions nvelope TED JUSTICE CENTRES (IJCS) LOCATED IN MOROGORO AN D TEMEKE DAR ES SALAAM. TZ-JUDICIARY TZ-180773-GO -UN / PROCUREMENT OF ICT Component 3: Access to Just UN Agencies (Dire EQUIPMENT FOR TWO INTER IDA / 57780 Post Direct 27,451.65 Completed 2020-07-01 2020-07-21 2020-07-06 2020-07-22 2020-08-10 2020-12-05 2020-12-08 2021-09-15 ice and Public Trust ct) GRATED JUSTICE CENTRES (IJ CS) LOCATED IN MOROGORO AND TEMEKE DAR ES SALAA M. TZ-JUDICIARY TZ-182131-GO Component 1: Governance, -RFQ / Supply and Installation Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 4,764.07 Completed 2020-07-03 2020-07-08 2020-07-10 2020-08-23 2021-01-06 2020-10-27 of plumbing materials and fit tions nvelope evelopment tings at new JDU Offices-Haki House TZ-JUDICIARY TZ-182133-GO Component 1: Governance, -RFQ / Supply and Installation Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 7,534.44 Completed 2020-07-02 2020-07-08 2020-07-10 2020-08-29 2021-01-06 2020-09-01 of LAN,CCTV, security door s tions nvelope evelopment ystem and telephones at JDU offices-Haki House TZ-JUDICIARY TZ-182134-GO -RFQ / Supply and installation Component 1: Governance, of office partitioning material Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 51,159.33 Completed 2020-07-02 2020-07-09 2020-07-10 2020-10-03 2021-01-06 2021-01-26 s and dismantal , packing an tions nvelope evelopment d re-instllation of Office facilit ies from Rita tower and PPF T ower to HAKI House. TZ-JUDICIARY TZ-182136-GO Component 1: Governance, Request for Quota Single Stage - One E -RFQ / Supply and Installation IDA / 57780 Organization and Systems D Post Limited 9,799.74 Completed 2020-07-02 2020-07-08 2020-07-10 2020-08-20 2021-01-06 2020-12-01 tions nvelope of Air Conditions at JDU Offic evelopment es -Haki House TZ-JUDICIARY TZ-188551-GO -RFQ / Supply, Installation, te Component 3: Access to Just Request for Quota Single Stage - One E sting and comissioning of LA IDA / 57780 Post Limited 23,461.52 Completed 2020-08-26 2020-08-23 2020-10-02 2020-11-17 2020-12-01 2021-04-15 ice and Public Trust tions nvelope N at Office of Attorney Gene ral in Dar es Salaam and Dod oma. Page 2 TZ-JUDICIARY TZ-211164-GO Component 1: Governance, Request for Quota Single Stage - One E -RFQ / Procurement of ICT Fa IDA / 57780 Organization and Systems D Post Limited 21,195.18 Completed 2021-01-02 2020-12-31 2021-02-03 2021-03-18 2021-04-04 2021-06-25 tions nvelope cilities for Kigamboni " Paper evelopment less Court" TZ-JUDICIARY TZ-221783-GO -RFB / Procurement of ICT eq Component 3: Access to Just Single Stage - One E uipment for Six Integrated Ju IDA / 57780 Post Request for Bids Open - National 560,528.31 Completed 2021-03-01 2021-08-04 2021-03-06 2021-08-04 2021-04-05 2021-08-27 2021-04-30 2020-08-30 2021-05-24 2021-09-22 2021-09-21 2021-12-08 ice and Public Trust nvelope stice Centers(IJCs) in Arusha, Mwanza, Dodoma, Morogoro, Kinondoni, and Temeke. TZ-JUDICIARY TZ-260890-GO -RFB / Procurement of furnitu re for eighteen(18) Subordin ate Courts located at Kaliua, Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2021-11-12 2021-11-29 2021-11-17 2021-11-29 2021-12-15 2021-12-20 2021-12-29 2021-12-27 2022-01-12 2022-05-12 Uvinza, Buhigwe, Kakonko, B ice and Public Trust nvelope utiama, Rorya, Itilima, Buseg a, Songwe, Tanganyika, Mbo gwe, Nyang’wale , Kyerwa, M isenyi, Gairo, Mvomero, Kilo mbero and Mkinga. TZ-JUDICIARY TZ-260892-GO -RFB / Supply, Installation, Te st and Commissioning of ICT equipment for eighteen(18) S Component 3: Access to Just Single Stage - One E ubordinate Courts located at IDA / 57780 Post Request for Bids Open - National 659,497.68 Completed 2021-11-12 2021-11-29 2021-11-17 2021-11-29 2021-12-15 2021-12-20 2021-12-29 2021-12-20 2022-01-12 2022-03-12 2022-05-12 2022-10-19 ice and Public Trust nvelope Kaliua, Uvinza, Buhigwe, Kak onko, Butiama, Rorya, Itilima , Busega, Songwe, Tanganyik a, Mbogwe, Nyang’wale , Kye rwa, Misenyi, Gairo, Mvomer o, Kilom TZ-JUDICIARY TZ-271298-GO -RFB / PROCUREMENT OF FU RNITURE FOR EIGHTEEN(18) SUBORDINATE COURTS LOCA TED AT KALIUA, UVINZA, BUH Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 1,257,889.98 Signed 2022-01-03 2022-01-05 2022-01-05 2022-01-05 2022-01-26 2022-01-26 2022-02-02 2022-02-07 2022-02-16 2022-05-07 2022-05-17 IGWE, KAKONKO, BUTIAMA, R ice and Public Trust nvelope ORYA, ITILIMA, BUSEGA, SON GWE, TANGANYIKA, MBOGW E, NYANG’WALE , KYERWA, M ISENYI, GAIRO, MVOMERO, KI LOMBERO AND MKINGA-(RE ADVERTISED) TZ-JUDICIARY TZ-293025-GO Component 3: Access to Just Single Stage - One E -RFB / Procurement of ICT eq IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2022-05-04 2022-05-09 2022-06-06 2022-06-16 2022-06-30 2022-08-29 ice and Public Trust nvelope uipment for Judiciary Media C enter TZ-JUDICIARY TZ-295320-GO Component 1: Governance, -DIR / Procurement of 18 Mot Under Imple IDA / 57780 Organization and Systems D Post Direct Selection Direct 0.00 2022-05-27 2022-08-03 2022-06-01 2022-08-03 2022-06-29 2022-12-01 or vehicles to support IJCs an mentation evelopment d project operations. TZ-JUDICIARY TZ-295322-GO Component 3: Access to Just Single Stage - One E -RFB / Procurement of ICT eq IDA / 57780 Post Request for Bids Limited 393,494.83 Completed 2022-05-16 2022-05-09 2022-05-17 2022-05-10 2022-05-31 2022-05-21 2022-06-02 2022-06-02 2022-06-11 2022-06-24 2022-06-25 2022-12-11 ice and Public Trust nvelope uipment for Judiciary Media C enter TZ-JUDICIARY TZ-320431-GO Component 1: Governance, -RFQ / Procurement of Archiv Request for Quota Single Stage - One E Under Imple IDA / 57780 Organization and Systems D Post Limited 0.00 2022-10-29 2022-12-29 2022-12-24 2023-06-22 e Boxes, File Cover and Stati tions nvelope mentation evelopment onery for Decongestion Exerc ise TZ-JUDICIARY TZ-320580-GO Component 1: Governance, -DIR / PROCUREMENT OF 83 Direct - Internation IDA / 57780 Organization and Systems D Prior Direct Selection 0.00 Signed 2022-11-30 2023-01-24 2022-12-05 2023-02-01 2023-01-09 2023-03-24 2023-07-08 MOTOR VEHICLES TO SUPPO al evelopment RT THE JUDICIAL REFORM AG ENDA TZ-JUDICIARY TZ-322583-GO -RFB / PROCUREMENT OF ICT Component 1: Governance, Single Stage - One E Under Imple EQUIPMENT FOR THE ATTOR IDA / 57780 Organization and Systems D Post Request for Bids Open - National 0.00 2022-11-11 2022-11-28 2022-11-16 2022-12-22 2022-12-19 2022-12-29 2023-01-23 2023-01-31 2023-05-31 nvelope mentation NEY GENERAL'S OFFICE & DI evelopment GITIZATION OF COURT RECO RDS. TZ-JUDICIARY TZ-320428-GO Component 3: Access to Just Single Stage - One E Under Imple -RFB / Procurement of Six Mo IDA / 57780 Prior Request for Bids Open - National 0.00 2022-11-11 2023-02-03 2022-11-16 2023-02-08 2022-12-22 2023-03-31 2022-12-27 2023-06-01 2023-01-15 2023-11-11 ice and Public Trust nvelope mentation bile Court Vehicles TZ-JUDICIARY TZ-330899-GO -RFB / Supply, installation, te Component 1: Governance, Single Stage - One E Under Imple st, configuration and Commis IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-01-06 2023-01-30 2023-01-16 2023-01-31 2023-02-21 2023-03-10 2023-03-07 2023-03-25 2023-03-28 2023-07-26 nvelope mentation sioning of audio virtual recor evelopment ding equipment for eight IJCs and three high court centers. TZ-JUDICIARY TZ-338611-GO -RFB / Supply, installation , c Component 1: Governance, Single Stage - One E Under Imple onfiguration, testing and com IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-02-10 2023-02-15 2023-02-15 2023-02-15 2023-03-23 2023-03-16 2023-04-22 2023-03-17 2023-05-27 2023-08-25 nvelope mentation missioning of ICT equipment evelopment for establishment of Judiciary Virtual Situation Room. TZ-JUDICIARY TZ-340099-GO -RFB / Procurement of heavy Component 1: Governance, Single Stage - One E Under Imple duty scanners and other ICT IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-03-08 2023-02-08 2023-03-17 2023-02-08 2023-04-22 2023-03-02 2023-05-22 2023-03-06 2023-06-26 2023-09-24 nvelope mentation equipment for digitization of evelopment court records and supporting JDU's procurement functions. TZ-JUDICIARY TZ-347075-GO -RFB / Supply, Installation, te sting, and commissioning of Component 3: Access to Just Single Stage - One E Under Imple Video Conferencing facilities IDA / 70580 Post Request for Bids Open - National 0.00 2023-03-14 2023-04-14 2023-03-19 2023-04-14 2023-04-30 2023-05-15 2023-05-30 2023-05-24 2023-07-04 2023-10-02 ice and Public Trust nvelope mentation for Prisons and other ICT facil ities to capacitate the estate management unit of the Judi ciary of Tanzania. TZ-JUDICIARY TZ-359592-GO Component 1: Governance, Request for Quota Single Stage - One E Under Imple -RFQ / Supply of protective a IDA / 57780 Organization and Systems D Post Limited 0.00 2023-05-15 2023-05-09 2023-06-15 2023-07-15 tions nvelope mentation ccessories for 18 motor vehic evelopment les. TZ-JUDICIARY TZ-364570-GO Component 1: Governance, -RFQ / Procurement of ICT eq Request for Quota Single Stage - One E Under Imple IDA / 70580 Organization and Systems D Post Limited 0.00 2023-06-11 2023-08-06 2024-02-02 uipment to support the imple tions nvelope mentation evelopment mentation and oversight of t he project. TZ-JUDICIARY TZ-9233-GO-R Component 2: Skills Develop FQ / Procurement of Furnitur Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 58,108.56 Completed 2017-07-03 2017-11-10 2017-08-28 2017-12-14 2018-02-24 2018-04-05 e for training rooms at High tions nvelope mance Management Court DSM & Kisutu RMs Cou rt Page 3 TZ-JUDICIARY TZ-9227-GO-R FB / Supply, installation and c Component 1: Governance, Single Stage - One E ommission of Video Conferen IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-05-22 2017-09-11 2017-05-27 2017-07-08 2017-08-07 2017-09-11 2018-03-10 nvelope cing Equipment, audio visual evelopment and recording equipment for four selected courts. TZ-JUDICIARY TZ-9218-GO-R Component 3: Access to Just Single Stage - One E FB / Supply of Two (2) Mobile IDA / 57780 Prior Request for Bids Open - National 415,669.47 Completed 2017-04-13 2017-10-09 2017-04-18 2017-05-30 2017-11-15 2017-06-29 2017-12-22 2017-08-03 2018-01-19 2018-01-30 2019-02-01 ice and Public Trust nvelope Courts Van TZ-JUDICIARY TZ-9356-GO-R Component 1: Governance, FB / Procurement of IT hardw Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 235,523.50 Completed 2017-03-09 2017-01-26 2017-03-14 2017-04-25 2017-02-16 2017-05-25 2017-04-22 2017-06-29 2017-03-23 2017-12-26 2017-09-15 are and general software for nvelope evelopment Integrated Justice Centre at Mbeya. TZ-JUDICIARY TZ-585-GO-RF Component 1: Governance, Request for Quota Single Stage - One E Q / Supply of office consuma IDA / 57780 Organization and Systems D Post Limited 27,167.14 Completed 2016-08-17 2016-08-17 2016-10-12 2016-10-07 2017-04-10 2016-11-08 tions nvelope bles evelopment TZ-JUDICIARY TZ-9382-GO-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Supply of Documentary IDA / 57780 Post Limited 11,233.54 Completed 2017-03-21 2017-02-02 2017-05-16 2017-01-28 2017-11-12 2017-05-02 ice and Public Trust tions nvelope about information on Judiciar y constructions. TZ-JUDICIARY TZ-9361-GO-R FB / Procurement of furniture Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2017-06-13 2017-06-18 2017-07-30 2017-08-29 2017-10-03 2018-04-01 for registries & Mbeya Integr ice and Public Trust nvelope ated Justice Centre. TZ-JUDICIARY TZ-9237-GO-R Component 1: Governance, FB / Procurement of training I Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 0.00 Canceled 2017-03-28 2017-04-02 2017-05-14 2017-06-13 2017-07-18 2018-01-14 T facilities for High Court DS nvelope evelopment M & Kisutu RMs Court. TZ-JUDICIARY TZ-9364-GO-R Component 1: Governance, FQ / Procurement of IT hardw Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 78,159.26 Completed 2017-03-20 2017-03-22 2017-05-15 2017-05-04 2017-11-11 2017-06-30 are and general software for tions nvelope evelopment a medium size Integrated Jus tice Centre at Kibaha TZ-JUDICIARY TZ-9239-GO-R FB / Procurement of standb Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 133,805.01 Completed 2017-04-28 2017-08-02 2017-05-03 2017-06-14 2017-09-19 2017-07-14 2017-10-03 2017-08-18 2017-11-23 2018-02-14 2018-06-19 y generators for High Court ice and Public Trust nvelope DSM, JDU & Kisutu RMs Court TZ-JUDICIARY TZ-9222-GO-R Component 1: Governance, Single Stage - One E FB / Installation and partition IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-04-26 2017-05-01 2017-06-12 2017-07-12 2017-08-16 2018-02-12 nvelope of pre fabrication storage for evelopment selected courts. TZ-JUDICIARY TZ-9389-GO-R Component 1: Governance, FB / Supply of LAN materials, Single Stage - One E IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-01-24 2018-02-28 2018-08-27 installation and commission i nvelope evelopment n High courts, Resident and d istrict courts. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-39836-NC- RFB / Provision of Service for Component 3: Access to Just Single Stage - One E Design, Editing and Printing IDA / 57780 Prior Request for Bids Open - National 0.00 Canceled 2017-12-15 2017-12-08 2017-12-20 2018-01-17 2018-01-15 2018-02-16 2018-03-05 2018-03-23 2018-09-19 ice and Public Trust nvelope of Various Legal Documents under Framework Contract. TZ-JUDICIARY TZ-52317-NC- RFQ / Provision of event man Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 93,400.36 Completed 2018-03-13 2018-03-23 2018-05-08 2018-05-02 2018-11-04 2018-06-11 agement, documentary and li ice and Public Trust tions nvelope ve coverage services for law week. TZ-JUDICIARY TZ-55449-NC- RFQ / Production of awarenes Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 53,002.21 Completed 2018-04-01 2018-03-19 2018-05-27 2018-05-03 2018-11-23 2018-05-18 s program of ongoing judiciar ice and Public Trust tions nvelope y reforms to the public. TZ-JUDICIARY TZ-67402-NC- RFQ / Provision of event man Component 3: Access to Just Request for Quota Single Stage - One E agement service and printing IDA / 57780 Post Limited 19,723.02 Completed 2018-06-25 2018-06-22 2018-07-07 2018-07-13 2019-01-03 2018-07-23 ice and Public Trust tions nvelope of various exhibition material s for sabasaba 2018. TZ-JUDICIARY TZ-91933-NC- RFQ / Provision of Event Man Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 97,646.03 Completed 2018-12-22 2019-01-03 2019-01-27 2019-01-29 2019-07-26 2019-03-28 agement and Printing Service ice and Public Trust tions nvelope s for Law Week 2019. TZ-JUDICIARY TZ-122947-NC -RFQ / Provision of event ma Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 23,220.09 Completed 2019-07-21 2019-06-03 2019-08-10 2019-06-25 2019-08-24 2019-12-03 nagement service and printin ice and Public Trust tions nvelope g of various exhibition materi als TZ-JUDICIARY TZ-146943-NC -RFQ / Provision of printing s Component 2: Skills Develop Request for Quota Single Stage - One E ervice for guideline manuals IDA / 57780 ment, Inspection and Perfor Post Limited 12,051.60 Completed 2019-12-13 2019-12-02 2020-02-07 2020-01-28 2020-08-05 2020-03-14 tions nvelope for Judicial Ethics Committee, mance Management Judiciary training policy and t raining programs. TZ-JUDICIARY TZ-151993-NC -RFQ / Provision of Event Man Component 3: Access to Just Request for Quota Single Stage - One E agement: Hiring of Tents, Ch IDA / 57780 Post Limited 82,237.59 Completed 2020-01-15 2019-12-06 2020-03-11 2020-01-28 2020-09-07 2020-03-18 ice and Public Trust tions nvelope airs, Tables, Mobile Toilet an d Printing Services for Law W eek 2020 TZ-JUDICIARY TZ-159179-NC -RFB / ONLINE PUBLICATION OF COURT DECISIONS (REPO Component 1: Governance, Single Stage - One E RTED AND UNREPORTED LA IDA / 57780 Organization and Systems D Post Request for Bids Open - National 335,025.26 Completed 2020-02-23 2020-02-18 2020-02-28 2020-03-16 2020-04-10 2020-04-16 2020-05-10 2020-04-26 2020-06-14 2020-06-07 2020-12-11 2022-04-30 nvelope W REPORTS), PRINTING OF L evelopment AW REPORTS AND INDEX OF LEGISLATION AND SUB LEGIS LATION FROM THE YEAR 196 1-2020 Page 4 TZ-JUDICIARY TZ-180775-NC Component 1: Governance, -RFQ / PROCUREMENT OF SE Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 98,517.15 Completed 2020-07-08 2020-07-08 2020-08-10 2020-09-23 2020-11-08 2021-03-20 RVICE FOR EDITING, DESIGN tions nvelope evelopment AND PRINTING OF VARIOUS J UDICIARY DOCUMENTS. TZ-JUDICIARY TZ-298032-NC -RFQ / Provision of Non-Cons Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 16,353.54 Signed 2022-06-10 2022-06-05 2022-07-08 2022-07-15 2022-07-22 ultancy service-Filming and d ice and Public Trust tions nvelope eveloping documentaries abo ut project activities TZ-JUDICIARY TZ-325875-NC -RFQ / PROVISION OF EVENT S MANAGEMENT SERVICES (H IRING TENTS, TABLE, CHAIRS , GENERATORS, PA SYSTEM, Component 3: Access to Just Request for Quota Single Stage - One E Under Imple IDA / 70580 Post Limited 0.00 2022-11-23 2022-11-28 2022-12-21 2023-02-19 CARPET,MOBILE TOILET, DEC ice and Public Trust tions nvelope mentation ORATION, EXHIBITION BOOT H, MARQUEE, AND SUPPLY O F PROMOTIONAL MATERIALS) FOR OPENING CEREMONY AN D 6 DAYS LAW WEEK 2023 TZ-JUDICIARY TZ-9393-NC-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Printing and supply of m IDA / 57780 Post Limited 80,911.34 Completed 2017-03-14 2017-01-02 2017-05-09 2017-01-28 2017-11-05 2017-03-28 ice and Public Trust tions nvelope aterials for Law week. TZ-JUDICIARY TZ-9397-NC-R FQ / Draw printing and fixing Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 0.00 Canceled 2017-03-28 2017-05-23 2017-11-19 of Signs / display boards for s ice and Public Trust tions nvelope elected court buildings. TZ-JUDICIARY TZ-9395-NC-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Design and printing of Ju IDA / 57780 Post Limited 63,673.97 Completed 2017-03-14 2016-12-28 2017-05-09 2017-01-24 2017-11-05 2017-03-23 ice and Public Trust tions nvelope diciary Calendar and diaries TZ-JUDICIARY TZ-9392-NC-R Component 3: Access to Just Single Stage - One E FB / Printing of different mat IDA / 57780 Prior Request for Bids Open - National 0.00 Canceled 2017-04-28 2017-12-08 2017-05-03 2017-06-14 2017-07-14 2017-08-18 2018-02-14 ice and Public Trust nvelope erials( Framework Contract) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-9448-CS-Q CBS / Consultancy for design Component 1: Governance, Quality And Cost- and supervision of LAN instal IDA / 57780 Organization and Systems D Prior Open - National 0.00 Canceled 2017-04-25 2017-10-09 2017-05-16 2017-12-08 2017-06-29 2018-02-26 2017-07-27 2018-03-30 2017-08-26 2018-05-21 2017-09-30 2017-11-04 2018-11-04 Based Selection lation in Selected High Court, evelopment Resident and District Courts TZ-JUDICIARY TZ-44715-CS- QCBS / CONSULTANCY SERVI CES FOR FEASIBILITY STUDY/I Component 1: Governance, Quality And Cost- Open - Internationa MPLEMENTATION PLAN/PROC IDA / 57780 Organization and Systems D Prior 513,542.79 Completed 2018-01-26 2018-02-16 2018-01-22 2018-04-01 2018-03-29 2018-04-29 2018-04-30 2018-05-29 2018-07-06 2018-07-03 2018-10-03 2018-08-07 2018-11-29 2019-08-07 2021-03-05 Based Selection l UREMENT, DEVELOPMENT AN evelopment D IMPLEMENTATION SUPPOR T FOR E-JUDICIARY SERVICES FOR THE JUDICIARY OF TANZ ANIA TZ-JUDICIARY TZ-50144-CS- QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa e 1) and (Ii) Supervise the Co IDA / 57780 Prior 452,799.20 Signed 2018-02-26 2018-03-18 2018-03-19 2018-03-27 2018-05-02 2018-06-18 2018-05-30 2018-07-27 2018-06-29 2018-10-03 2018-08-03 2018-11-27 2018-09-07 2018-12-16 2019-09-07 ice and Public Trust Based Selection l nstruction Work for the Propo sed Integrated Justice Centre (IJC) Court Buildings which wi ll be Built in Six Selected Loc ations of Mwanza, Morogoro TZ-JUDICIARY TZ-50194-CS- QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa IDA / 57780 Prior 0.00 Canceled 2018-02-26 2018-03-18 2018-03-19 2018-04-12 2018-05-02 2018-06-18 2018-05-30 2018-06-29 2018-08-03 2018-09-07 2019-09-07 e 1) and (Ii) Supervise the Co ice and Public Trust Based Selection l nstruction Work for Small Co urthouses which will be Built in at least 10 Selected Locati ons in Tanzania (Phase 2) TZ-JUDICIARY TZ-113326-CS -QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa IDA / 57780 Prior 310,611.59 Signed 2019-05-08 2019-07-27 2019-05-22 2019-07-31 2019-07-05 2019-12-28 2019-08-02 2020-01-10 2019-08-16 2020-02-18 2019-09-06 2020-03-13 2019-09-23 2020-04-01 2020-09-22 e 1) and (II) Supervise the Co ice and Public Trust Based Selection l nstruction Work for Small Co urthouses which will be Buil t in at Least 27 Selected Loca tions in Tanzania (Phase 2). TZ-JUDICIARY TZ-291807-CS -CQS / CONSULTANCY SERVI CES FOR PREPARATION OF A N ENVIRONMENTAL AND SOC IAL IMPACT ASSESSMENT FO Component 3: Access to Just Consultant Qualifi IDA / 57780 Post Open - National 295,190.27 Signed 2022-04-26 2022-04-24 2022-05-10 2022-05-19 2022-05-25 2022-07-01 2022-06-24 2022-07-25 2022-07-15 2022-08-06 2022-10-13 R THE PROPOSED CONSTRUC ice and Public Trust cation Selection TION PROJECTS IN TANZANIA MAINLAND UNDER THE CITIZ EN-CENTRIC JUDICIAL MODER NIZATION AND JUSTICE SERVI CE DELIVERY PROJECT.(AF) TZ-JUDICIARY TZ-320375-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-26 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least Eleven (1 1) Selected Locations in Tanz ania. 1st Package TZ-JUDICIARY TZ-320379-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-01-18 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-26 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least nine (09) Selected Locations in Tanzani a. 2nd Package Page 5 TZ-JUDICIARY TZ-320381-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-21 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least nine (09) Selected Locations in Tanzani a. 3rd Package TZ-JUDICIARY TZ-320383-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least eleven (1 1) Selected Locations in Tanz ania. 4th Package TZ-JUDICIARY TZ-320388-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Under Implement IDA / 57780 Post Open - National 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection ation uction Work for the Proposed Small Courthouses which will be Built in at least four (4) Se lected Locations in Tanzania. 5th Package TZ-JUDICIARY TZ-320391-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least six (6) Sel ected Locations in Tanzania. 6th Package TZ-JUDICIARY TZ-320393-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least ten (10) S elected Locations in Tanzania . 7th Package TZ-JUDICIARY TZ-320396-CS -QCBS / Consultancy Service for Supervision of Constructi on Work for the Proposed Int Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-08 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 egrated Justice Centre (IJC) C ice and Public Trust Based Selection l ation ourt Buildings which will be b uilt in four (4) Selected regio ns of Singida, Geita, Simiyu a nd Manyara. 1st Package. TZ-JUDICIARY TZ-320398-CS -QCBS / Consultancy Service for Supervision of Constructi on Work for the Proposed Int Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 egrated Justice Centre (IJC) C ice and Public Trust Based Selection l ation ourt Buildings which will be b uilt in three (3) Selected regi ons of Katavi, Songwe, and N jombe. 3rd Package. TZ-JUDICIARY TZ-320400-CS -QCBS / Consultancy Service for Supervision of Constructi Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement on Work for the Proposed Int IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 ice and Public Trust Based Selection l ation egrated Justice Centre (IJC) C ourt Buildings which will be b uilt in Two (2) Selected regio ns of Lindi and Pwani. 2nd Pa ckage TZ-JUDICIARY TZ-365265-CS -QCBS / Consultancy services Component 1: Governance, Quality And Cost- for conducting impact assess IDA / 70580 Organization and Systems D Post Open - National 0.00 Under Review 2023-06-23 2023-07-14 2023-07-28 2023-09-02 2023-09-09 2023-09-30 2023-10-21 2024-02-18 Based Selection ments on simplified laws and evelopment rules of procedure. TZ-JUDICIARY TZ-9183-CS-C QS / Consultancy service to c onduct environmental and so Component 3: Access to Just Consultant Qualifi IDA / 57780 Post Open - National 110,103.09 Completed 2017-03-08 2016-09-06 2017-03-29 2017-05-12 2016-10-25 2017-06-11 2017-02-09 2017-07-16 2017-03-10 2018-01-12 2018-04-27 cial impact assessments for t ice and Public Trust cation Selection he Citizen-Centric Judicial Mo dernization and Justice Servic e Delivery Project. TZ-JUDICIARY TZ-9399-CS-C Component 2: Skills Develop QS / Consultancy service to D Consultant Qualifi IDA / 57780 ment, Inspection and Perfor Post Open - National 0.00 Canceled 2017-07-17 2017-08-07 2017-09-20 2017-10-20 2017-11-24 2018-05-23 evelop continuous training pr cation Selection mance Management ogram and facilitate legal trai ning TZ-JUDICIARY TZ-9438-CS-Q Component 1: Governance, CBS / Consultancy Services t Quality And Cost- IDA / 57780 Organization and Systems D Prior Open - National 0.00 Canceled 2017-05-10 2017-05-31 2017-07-14 2017-08-11 2017-09-10 2017-10-15 2017-11-19 2018-11-19 o design and introduce E-jud Based Selection evelopment gment, e-payment & E- notifi cation TZ-JUDICIARY TZ-9420-CS-Q Component 1: Governance, Quality And Cost- CBS / Consultancy service to IDA / 57780 Organization and Systems D Post Open - National 100,710.87 Completed 2017-04-19 2016-03-30 2017-05-10 2017-06-23 2016-12-23 2017-07-21 2017-01-30 2017-08-20 2017-03-30 2017-09-24 2017-05-04 2017-10-29 2017-06-08 2018-10-29 2019-01-31 Based Selection undertake Court mapping co evelopment untry wide INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-25713-CS-I Component 1: Governance, Individual Consult NDV / Procurement Specialist IDA / 57780 Organization and Systems D Post Limited 179,040.00 Completed 2017-08-28 2017-08-28 2017-09-02 2017-08-31 2017-09-23 2017-09-06 2017-10-28 2017-09-26 2018-04-26 2020-05-20 ant Selection to support Project team evelopment TZ-JUDICIARY TZ-42554-CS-I NDV / Provision of consultanc Component 3: Access to Just Individual Consult IDA / 57780 Post Limited 67,200.00 Completed 2018-01-15 2017-11-21 2018-01-20 2018-01-23 2018-02-10 2018-02-12 2018-03-17 2018-03-29 2018-09-13 2019-03-28 y for Information and Commu ice and Public Trust ant Selection nication services Page 6 TZ-JUDICIARY TZ-42596-CS-I Component 1: Governance, NDV / Consultancy services f Individual Consult IDA / 57780 Organization and Systems D Post Limited 68,100.00 Completed 2018-01-18 2017-11-21 2018-01-23 2018-01-18 2018-02-13 2018-02-12 2018-03-20 2018-05-07 2018-09-16 2019-06-26 or preparation of Human Res ant Selection evelopment ource planning guideline for J udiciary of Tanzania. TZ-JUDICIARY TZ-42602-CS-I NDV / Provision of consultanc y services for development o Component 3: Access to Just Individual Consult IDA / 57780 Post Limited 31,581.00 Terminated 2018-01-15 2017-12-30 2018-01-20 2018-01-21 2018-02-10 2018-02-15 2018-03-17 2018-05-07 2018-09-13 f database systems for judge ice and Public Trust ant Selection ment, Advocates and Court B rokers and database for proje ct M & E tools based on BRN. TZ-JUDICIARY TZ-9406-CS-C DS / Consultancy service for supervision of the constructio Component 3: Access to Just IDA / 57780 Prior Direct Selection Direct 0.00 Canceled 2017-04-02 2017-04-12 2017-06-16 2017-12-13 n of ten (10) courthouses for ice and Public Trust subordinate court Primary Co urt and training room at Kisu tu RMs Court. TZ-JUDICIARY TZ-54811-CS-I Component 1: Governance, NDV / Individual Consultancy Individual Consult IDA / 57780 Organization and Systems D Post Limited 22,980.00 Completed 2018-03-26 2018-03-26 2018-03-31 2018-07-02 2018-04-21 2018-08-21 2018-05-26 2018-11-07 2018-11-22 2019-10-04 service for establishment an ant Selection evelopment d development of a compute rized e-Library system TZ-JUDICIARY TZ-138788-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 66,998.08 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-21 2020-01-25 2020-06-18 2022-03-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN M WANZA, Plot 768 Block. A at North Buswelu. TZ-JUDICIARY TZ-140323-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 31,688.28 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2020-01-04 2020-01-25 2020-07-02 2021-02-15 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN M OROGORO,, Plot 430 Block. G at Kihonda. TZ-JUDICIARY TZ-140325-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 47,647.74 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-07 2020-01-25 2020-06-04 2021-09-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN AR USHA, Plot No 123. Block I Sit uated at Corridor I in Arusha City. TZ-JUDICIARY TZ-140327-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 46,979.73 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-21 2020-01-25 2020-06-18 2021-09-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN D ODOMA, Plot No. 4 Block C at NCC Link. TZ-JUDICIARY TZ-140332-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 53,505.92 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-02-06 2019-12-07 2020-01-25 2020-06-04 2021-07-31 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) in DA R ES SALAAM, Plot No. 38 Blo ck No. 20 at Kinondoni Munic ipal. TZ-JUDICIARY TZ-140334-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 48,306.60 Signed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-07 2020-01-25 2020-06-04 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN DA R ES SALAAM, Plot No 2025 B lock D at Temeke. TZ-JUDICIARY TZ-152928-CS -INDV / INDIVIDUAL EXPERT T Component 1: Governance, O CONDUCT AN ECONOMIC A Individual Consult IDA / 57780 Organization and Systems D Post Limited 8,182.54 Completed 2020-01-24 2020-02-11 2020-01-29 2020-02-12 2020-02-19 2020-02-14 2020-03-25 2020-03-04 2020-09-21 2021-01-01 NALYSIS OF CITIZEN-CENTRIC ant Selection evelopment JUDICIAL MODERNIZATION A ND JUSTICE SERVICE DELIVE RY PROJECT TZ-JUDICIARY TZ-291818-CS Component 1: Governance, -INDV / Procurement and Con Individual Consult IDA / 57780 Organization and Systems D Prior Open 67,925.09 Signed 2022-04-26 2022-05-06 2022-05-22 2022-07-09 2022-05-27 2022-08-26 2022-06-13 2022-09-02 2023-06-08 tract Management Expert to ant Selection evelopment support the project team. TZ-JUDICIARY TZ-294037-CS -INDV / INDIVIDUAL CONSULT Component 1: Governance, ANT (CIVIL ENGINEER) FOR T Individual Consult IDA / 57780 Organization and Systems D Post Limited 30,875.04 Signed 2022-05-13 2022-05-15 2022-05-18 2022-06-27 2022-06-08 2022-08-24 2022-06-29 2022-09-05 2023-06-29 HE CITIZEN-CENTRIC JUDICIA ant Selection evelopment L MODERNIZATION AND JUST ICE SERVICE DELIVERY PROJE CT. TZ-JUDICIARY TZ-295323-CS -CDS / CONSULTANCY SERVI CE TO UPDATE THE DESIGN ( Component 3: Access to Just Under Implement IDA / 57780 Post Direct Selection Direct 0.00 2022-05-20 2022-05-30 2022-06-08 2022-08-25 2022-06-22 2022-08-23 REDESIGN) OF EXISTING DRA ice and Public Trust ation WINGS FOR THE PROPOSED 12 INTEGRATED JUSTICE CEN TRE (IJCs). TZ-JUDICIARY TZ-306644-CS -CDS / Consultancy service t Component 3: Access to Just Under Implement IDA / 57780 Post Direct Selection Direct - National 0.00 2022-07-31 2022-08-01 2022-08-19 2022-08-17 2022-08-31 2023-02-27 o conduct court users’ satisfa ice and Public Trust ation ction survey 2022 TZ-JUDICIARY TZ-364600-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Songea. TZ-JUDICIARY TZ-364607-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Lindi. TZ-JUDICIARY TZ-364593-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Njombe. Page 7 TZ-JUDICIARY TZ-364576-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Simiyu TZ-JUDICIARY TZ-364587-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Katavi TZ-JUDICIARY TZ-364590-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Songwe TZ-JUDICIARY TZ-364605-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Moshi. TZ-JUDICIARY TZ-364583-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Pemba. TZ-JUDICIARY TZ-364597-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Mtwara TZ-JUDICIARY TZ-364602-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Pwani. TZ-JUDICIARY TZ-364604-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Tanga. TZ-JUDICIARY TZ-364581-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Geita. TZ-JUDICIARY TZ-364606-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Manyara. TZ-JUDICIARY TZ-364574-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 Under Review 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection pervision of construction of i ntegrated justice centre (IJC) in Singida TZ-JUDICIARY TZ-9441-CS-IN DV / Consultancy to review ju Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-04-24 2017-06-12 2017-07-03 2017-08-07 2018-02-03 stice chain, identify gaps in t ice and Public Trust ant Selection erms of policy, strategy, refo rm or performance TZ-JUDICIARY TZ-9445-CS-IN Component 3: Access to Just Individual Consult DV / Consultancy to prepare IDA / 57780 Post Open 0.00 Canceled 2017-04-24 2017-06-12 2017-07-03 2017-08-07 2018-02-03 ice and Public Trust ant Selection special program on legal aid with MoCLA TZ-JUDICIARY TZ-9410-CS-C Component 3: Access to Just DS / Consultancy service for IDA / 57780 Post Direct Selection Direct 121,856.63 Completed 2017-03-29 2019-01-18 2017-04-08 2019-04-17 2017-06-12 2019-06-27 2017-12-09 2019-09-27 ice and Public Trust Court User Survey. TZ-JUDICIARY TZ-9433-CS-IN Component 1: Governance, Individual Consult DV / Procurement of IT Speci IDA / 57780 Organization and Systems D Post Open 0.00 Canceled 2017-04-17 2017-06-05 2017-06-26 2017-07-31 2018-01-27 ant Selection alist to support Project team evelopment TZ-JUDICIARY TZ-9422-CS-IN Component 1: Governance, Individual Consult DV / Procurement Specialist t IDA / 57780 Organization and Systems D Post Open 0.00 Canceled 2017-03-09 2017-02-02 2017-04-27 2017-05-11 2017-05-18 2017-06-22 2017-12-19 ant Selection o Support Project Team evelopment TZ-JUDICIARY TZ-9431-CS-IN DV / Consultancy service to s Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-05-12 2017-06-30 2017-07-21 2017-08-25 2018-02-21 upport the development of A ice and Public Trust ant Selection DR and backlog reduction pr ogram TZ-JUDICIARY TZ-9440-CS-IN DV / Consultancy Services to Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-07-18 2017-09-05 2017-09-26 2017-10-31 2018-04-29 introduce Online interactive c ice and Public Trust ant Selection omplaints platform Page 8 PROCUREMENT PLAN (Textual Part) Project information: Burundi - Great Lakes Trade Facilitation and Integration Project] (P174814) Project Implementation agency: Burundi-Ministry of Finance, Budget and Privatization Date of the Procurement Plan: November 8, 2021 Period covered by this Procurement Plan: December 2017 – December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the country procurement handbook, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. - The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. - Rights for the Bank to review procurement documentation and activities. - An effective complaints mechanism. - Maintenance of records of the Procurement Process When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables : Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is Not Applicable Works: is not Applicable PROCUREMENT Eastern and Southern Africa : Great Lakes Trade Facilitation and Integration Project PLAN General Information Country: Eastern and Southern Africa 2018-07-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174814 GPN Date: Project Name: Great Lakes Trade Facilitation and Integration Project Loan / Credit No: IDA / V1000, IDA / V3250, IDA / V0960, IDA / V3940, IDA / E0700, IDA / E0710 Burundi-Ministry of Finance, Budget and Privatization Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BI-BI-MOF-71885-CW-DIR / A Component 1. Improving Poli Under Imple 2019-01-1 dduction d'eau au poste front IDA / V1000 cy and Regulatory Environm Prior Direct Selection Direct 28,600.00 0.00 2018-07-27 2018-08-01 2018-09-18 mentation 7 ière de Gatumba (Interventio ent for cross border trade n rapide) BI-BI-MOF-71888-CW-RFQ / Improving core trade infrastr Aménagement des Latrines e Request for Quota Single Stage - One E 2019-01-0 IDA / V1000 ucture and facilities in the b Post Limited 11,000.00 10,186.24 Completed 2018-08-11 2018-08-10 2018-10-02 2018-09-06 t douches au port de Rumon tions nvelope 4 order areas ge (Intervention urgente) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-BI-MOF-170418-GO-RFQ / Implementation support, Co Request for Quota Single Stage - One E Acquisition des équipements IDA / V3250 mmunication, Monitoring, an Post Limited 50,000.00 16,881.67 Signed 2020-07-25 2022-02-22 2020-09-19 2022-01-25 2020-10-30 tions nvelope de bureau (mobilier et photo d Evaluation copieuse) BI-BI-MOF-170426-GO-RFQ / Implementation support, Co Request for Quota Single Stage - One E Acquisition du matériel infor IDA / V3250 mmunication, Monitoring, an Post Limited 30,000.00 42,446.89 Completed 2020-07-12 2020-10-12 2020-08-28 2021-01-20 2020-10-09 2021-06-08 tions nvelope matique pour l'UGP d Evaluation BI-BI-MOF-170423-GO-RFB / Implementation support, Co Acquisition de Trois véhicules Single Stage - One E IDA / V3250 mmunication, Monitoring, an Post Request for Bids Open - National 250,000.00 0.00 Canceled 2020-07-15 2020-07-20 2020-08-31 2020-09-15 2020-10-09 2020-12-01 (One station wagon 4*4 et de nvelope d Evaluation ux camionnettes) BI-BI-MOF-319184-GO-RFB / Component 4: Supporting Im Single Stage - One E Pending Impl Acquisition des équipements IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 50,000.00 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-06-15 nvelope ementation mobiliers pour l'UGP and Evaluation BI-BI-MOF-319187-GO-RFB / Component 4: Supporting Im Single Stage - One E Pending Impl Acquisition du matériel infor IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 100,000.00 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-06-30 nvelope ementation matique pour l'UGP and Evaluation BI-BI-MOF-319182-GO-RFB / Component 4: Supporting Im Acquisition de 4 véhicules (1 Single Stage - One E IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 350,000.00 0.00 Canceled 2022-11-15 2022-11-20 2023-01-01 2023-01-20 2023-02-17 2023-04-21 jeep station wagon ou équiva nvelope and Evaluation lent + 3 pick up) BI-BI-MOF-355350-GO-DIR / Acquisition de 4 véhicules (1 Component 4: Supporting Im Direct - Internation Under Imple station wagon 4X4 et 3 cami IDA / E0700 plementation and Monitoring Post Direct Selection 300,000.00 0.00 2023-04-21 2023-06-02 2023-05-02 2023-03-25 2023-05-23 2023-11-19 al mentation onnettes double cabine 4X4) and Evaluation auprès de l'agence des Natio ns Unies UNOPS BI-BI-MOF-357226-GO-RFB / Component 4: Supporting Im Open - Internationa Single Stage - One E Pending Impl Acquisition d'un système de IDA / E0700 plementation and Monitoring Post Request for Bids 60,000.00 0.00 2023-04-28 2023-05-03 2023-06-14 2023-06-21 2023-07-26 2023-10-27 l nvelope ementation vidéoconférence and Evaluation BI-BI-MOF-360294-GO-RFB / Component 4: Supporting Im Single Stage - One E Pending Impl Acquisition de 14 batteries d' IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 20,000.00 0.00 2023-05-19 2023-05-24 2023-07-05 2023-08-04 2023-09-08 2023-12-15 nvelope ementation un système de back-up élect and Evaluation rique BI-BI-MOF-367786-GO-RFQ / Component 4: Supporting Im Request for Quota Single Stage - One E Pending Impl Acquisition du mobilier de bu IDA / E0700 plementation and Monitoring Post Limited 10,000.00 0.00 2023-07-05 2023-08-16 2023-10-20 tions nvelope ementation reau and Evaluation BI-BI-MOF-367788-GO-RFQ / Component 4: Supporting Im Request for Quota Single Stage - One E Pending Impl Acquisition du matériel infor IDA / E0700 plementation and Monitoring Post Limited 15,000.00 0.00 2023-07-10 2023-08-21 2023-10-27 tions nvelope ementation matique pour l'UGP and Evaluation BI-BI-MOF-367790-GO-RFQ / Component 4: Supporting Im Request for Quota Single Stage - One E Pending Impl Acquisition des climatiseurs IDA / E0700 plementation and Monitoring Post Limited 18,000.00 0.00 2023-07-16 2023-08-25 2023-11-30 tions nvelope ementation de remplacement and Evaluation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DMI/010/PFCGL-II/2018 / Con Improving core trade infrastr ception détaillée nécessaire Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 200,000.00 187,605.23 Completed 2018-04-20 2018-04-16 2018-06-15 2018-09-13 2018-07-22 2018-07-05 2018-08-23 2018-09-28 2018-09-15 2018-10-05 2018-10-20 2018-10-23 2018-11-10 2018-02-15 2019-02-11 2019-11-06 pour le site du projet de cons Based Selection l order areas truction du Port de Rumonge BI-BI-MOF-65618-CS-QCBS / Improving core trade infrastr Conception détaillée nécessa Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 200,000.00 0.00 Canceled 2018-07-05 2018-07-26 2018-08-31 2018-10-03 2018-10-19 2018-11-16 2018-12-07 2019-02-07 ire pour les sites du poste fro Based Selection l order areas ntalier et du marché frontalie r de Gatumba Page 1 BI-BI-MOF-65723-CS-QCBS / Improving core trade infrastr Conception des infrastructur Quality And Cost- IDA / V1000 ucture and facilities in the b Post Open - National 60,000.00 0.00 Canceled 2018-07-15 2018-08-10 2018-09-10 2018-10-15 2018-10-31 2018-11-21 2018-12-05 2019-03-05 es provisoires aux postes fro Based Selection order areas ntaliers de Gatumba et au po rt de Rumonge BI-BI-MOF-71876-CS-QCBS / Improving core trade infrastr Conception détaillée nécessa Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 80,000.00 118,150.00 Completed 2018-08-20 2018-11-19 2018-09-10 2018-11-20 2018-10-15 2019-01-24 2018-11-27 2019-01-15 2018-12-14 2019-01-25 2019-01-18 2019-04-15 2019-02-22 2020-08-20 2019-05-27 2021-07-05 ire pour les sites du poste fro Based Selection l order areas ntière de Gatumba BI-BI-MOF-71879-CS-QCBS / Improving core trade infrastr Quality And Cost- Conception détaillée nécessa IDA / V1000 ucture and facilities in the b Post Open - National 43,130.00 8,504.99 Completed 2018-08-23 2018-09-07 2018-09-13 2018-09-12 2018-10-19 2018-11-08 2018-11-23 2019-01-15 2018-12-10 2019-10-28 2019-01-14 2019-10-28 2019-02-11 2019-03-20 2019-05-13 2020-04-22 Based Selection ire pour le marché frontalier order areas de Gatumba BI-BI-MOF-96822-CS-LCS / A Implementation support, Co udit comptable et financier d Least Cost Selecti Open - Internationa IDA / V1000 mmunication, Monitoring, an Post 25,000.00 13,684.46 Completed 2019-01-28 2019-02-22 2019-02-18 2019-05-20 2019-04-03 2019-10-30 2019-05-01 2019-10-30 2019-05-31 2019-10-30 2019-07-05 2022-02-19 2019-08-09 2019-11-19 2020-02-05 2019-12-06 u PFCGL-II de la période allan on l d Evaluation t du 07/08/2017 au 30/06/20 19 BI-BI-MOF-102626-CS-QCBS / Recrutement d'une firme de Improving core trade infrastr consultants pour le contrôle Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 100,000.00 0.00 Canceled 2019-03-14 2019-04-04 2019-05-17 2019-07-04 2019-07-19 2019-08-16 2019-10-08 2020-10-07 et la surveillance des travaux Based Selection l order areas de construction du port de R umonge et provision de servi ces connexes BI-BI-MOF-203512-CS-CQS / Recrutement d'un bureau en charge de l'élaboration de l'é Improving core trade infrastr tude technique pour l'aména Consultant Qualifi Open - Internationa IDA / V3250 ucture and facilities in the b Post 80,000.00 0.00 Canceled 2020-12-01 2020-12-08 2021-01-14 2021-01-29 2021-02-11 2021-05-11 gement et le bitumage de la cation Selection l order areas RP 108: RN4(PK 14 + 8)/Gatu mba-Vuggizo/Frontière RDC ( 8km)+Etude d'Impact Enviro nnemental et Social (EIES) BI-BI-MOF-203525-CS-CQS / Improving core trade infrastr Etude de faisabilité sur les ch Consultant Qualifi Open - Internationa IDA / V3250 ucture and facilities in the b Post 200,000.00 0.00 Canceled 2020-12-15 2020-12-22 2021-02-04 2021-02-18 2021-03-04 2021-05-19 aînes de valeur des produits cation Selection l order areas agricoles, de pêche et de frui ts BI-BI-MOF-203488-CS-CQS / Etude pour la construction du Improving core trade infrastr marché transfrontalier de Ru Consultant Qualifi IDA / V3250 ucture and facilities in the b Post 50,000.00 0.00 Canceled 2020-11-27 2020-12-10 2021-01-23 2021-02-10 2021-03-17 2021-05-25 monge (incluant l'étude de re cation Selection order areas ntabilité et Etude d'Impact E nironnemental et Social (EIES )) BI-BI-MOF-204468-CS-QCBS / Recrutement d'un cabinet p Implementation of policy an our la réalisation de l'audit o d procedural reforms and ca pérationnel des administratio Quality And Cost- Open - Internationa IDA / V3250 pacity building to facilitate c Post 150,000.00 0.00 Canceled 2020-12-21 2021-01-04 2021-02-03 2021-03-11 2021-03-30 2021-05-04 2021-05-31 2021-10-14 ns des services des frontière Based Selection l ross-border trade in goods a s: étude sur l'efficacité et l'ef nd servic es ficience institutionnelle des a dministrations des services d es frontières BI-BI-MOF-207626-CS-CQS / Component 1. Improving Poli Etude pour la constructiondu Consultant Qualifi Pending Impleme IDA / V3250 cy and Regulatory Environm Post Open - National 40,000.00 0.00 2021-03-08 2021-03-15 2021-04-28 2021-05-28 2021-06-11 2021-09-30 marché transfrontalier de Ru cation Selection ntation ent for cross border trade monge incluant l'étude de re ntabilité BI-BI-MOF-207711-CS-CQS / Etude technique pour l'amén Component 1. Improving Poli Consultant Qualifi Open - Internationa Under Implement agement et le bitumage de l IDA / V3250 cy and Regulatory Environm Post 55,000.00 0.00 2020-12-09 2021-01-27 2020-12-14 2021-02-15 2021-01-20 2022-02-21 2021-02-05 2021-02-15 2021-05-28 cation Selection l ation a RP 108: RN4 (PK14 + 8)Gat ent for cross border trade umba-Vugizo/frontière BI-BI-MOF-207744-CS-CQS / Recrutement d'un cabinet po Implementation of policy an ur la réalisation de l'audit op d procedural reforms and ca érationnel des administration Consultant Qualifi Open - Internationa IDA / V3250 pacity building to facilitate c Post 150,000.00 108,130.00 Signed 2021-01-15 2020-12-21 2021-01-29 2021-03-15 2021-03-14 2022-02-17 2021-04-13 2022-02-17 2021-05-04 2021-12-03 2021-10-31 s des services des frontières cation Selection l ross-border trade in goods a : étude sur l'efficacité et l'effi nd servic es cience institutionnelle des ad ministrations des services de s frontières BI-BI-MOF-207751-CS-CQS / Improving core trade infrastr Etude de faisabilité sur les ch Consultant Qualifi Open - Internationa IDA / V3250 ucture and facilities in the b Post 200,000.00 0.00 Canceled 2020-12-15 2020-12-21 2020-12-22 2021-01-26 2021-02-04 2022-02-18 2021-03-06 2021-03-19 2021-06-18 aînes de valeurs des produits cation Selection l order areas agricoles, de pêche et de frui ts BI-BI-MOF-221288-CS-LCS / Implementation support, Co Audit comptable et financier Least Cost Selecti Open - Internationa IDA / V0960 mmunication, Monitoring, an Post 20,000.00 6,074.00 Completed 2021-03-02 2021-03-01 2021-03-23 2021-05-10 2021-05-06 2022-02-15 2021-06-03 2022-02-15 2021-07-03 2022-02-21 2021-08-07 2022-02-21 2021-10-15 2021-12-07 2021-12-15 2021-12-25 du projet pour la période alla on l d Evaluation nt du 01/07/2020 au 30/06/2 021 BI-BI-MOF-290037-CS-QCBS Component 3: Supporting Co / Recrutement d'un coonsulta Quality And Cost- Open - Internationa Under Implement IDA / V3250 mmercialization of Selected Post 200,000.00 0.00 2022-04-14 2022-04-13 2022-04-20 2022-07-12 2022-05-20 2023-03-22 2022-06-17 2022-07-11 2022-08-15 2022-09-19 2022-12-30 nt chargé de l'étude de l"état Based Selection l ation Cross-border Value Chains des lieux des chaînes de vale ur de l'agribusiness BI-BI-MOF-303406-CS-QCBS / Recrutement d'un consultan Component 3: Supporting Co t chargé de l'élaboration du Quality And Cost- Open - Internationa IDA / V3940 mmercialization of Selected Post 100,000.00 0.00 Canceled 2022-08-19 2022-10-04 2022-09-09 2022-10-23 2022-11-20 2022-12-20 2023-01-24 2023-02-28 2023-04-26 manuel de gestion des subve Based Selection l Cross-border Value Chains ntions aux associations et co opératives des commerçants dans le cadre du PFCIGL BI-BI-MOF-319236-CS-QCBS / Recrutement d'un bureau p our l'élaboration d'une étude Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement IDA / E0700 Post 200,000.00 0.00 2022-11-02 2023-01-13 2022-11-09 2023-04-07 2022-12-23 2023-01-20 2023-02-10 2023-03-03 2023-03-31 2023-07-14 technique pour l'aménageme e Trade Infrastructure Based Selection l ation nt et modernisation des infra structures du poste frontière de Vugizo-Kiliba BI-BI-MOF-207635-CS-CQS / Component 1. Improving Poli Etude pour l'aménagement e Consultant Qualifi Open - Internationa IDA / V3250 cy and Regulatory Environm Post 40,000.00 0.00 Canceled 2020-12-11 2020-12-22 2020-12-18 2021-01-26 2021-01-22 2021-02-21 2021-03-05 2021-05-17 t la modernisation du poste-f cation Selection l ent for cross border trade rontière Vugizo-Kiliba Page 2 BI-BI-MOF-203504-CS-CQS / Recrutement d'un bureau ch argé de l'élaboration de l'étu Improving core trade infrastr Consultant Qualifi de pour l'aménagement et m IDA / V3250 ucture and facilities in the b Post Open - National 60,000.00 0.00 Canceled 2020-11-18 2020-11-25 2021-01-08 2021-02-07 2021-02-19 2021-04-26 cation Selection odernisation poste-frontière order areas Vugizo-Kiliba + Etude d'Imp act Environnemental et Socia l (EIES) BI-BI-MOF-335979-CS-QCBS / Recrutement d'un bureau d' un bureau pour la réalisation Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement de la réalisation d'une étude IDA / E0700 Post 100,000.00 0.00 2023-01-20 2023-04-04 2023-01-25 2023-06-05 2023-02-17 2023-04-03 2023-04-14 2023-05-12 2023-06-09 2023-09-15 e Trade Infrastructure Based Selection l ation de rentabilité économique et l'adaptation de l'étude techni que pour la construction du marché transfrontalier de Ga tumba BI-BI-MOF-335987-CS-QCBS / Recrutement d'un bureau p Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement our la surveillance/contrôle d IDA / E0700 Post 700,000.00 0.00 2023-01-20 2023-01-18 2023-01-27 2023-04-05 2023-02-17 2023-04-04 2023-04-14 2023-05-05 2023-05-29 2024-05-28 e Trade Infrastructure Based Selection l ation es travaux de construction d u poste frontière de Gatumb a-Kavimvira BI-BI-MOF-335989-CS-QCBS / Recrutement d'un bureau p our la surveillance/contrôle d Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement es travaux de construction d IDA / E0700 Post 1,800,000.00 0.00 2023-01-24 2023-01-19 2023-01-31 2023-02-23 2023-02-21 2023-04-05 2023-04-19 2023-05-05 2023-05-31 2026-05-29 e Trade Infrastructure Based Selection l ation u port de Rumonge et provisi on de services connexes y co mpris l'actualisation des étud es techniques BI-BI-MOF-338261-CS-QCBS / Recrutement d'un bureau c hargé de l'élaboration de l'ét Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement IDA / E0710 Post 200,000.00 0.00 2023-02-15 2023-01-25 2023-02-21 2023-03-30 2023-03-30 2023-05-10 2023-05-26 2023-06-30 2023-07-21 2023-10-30 ude technique d'aménageme e Trade Infrastructure Based Selection l ation nt et de bitumage de la RP 1 08: RN 4/Gatumba - Vugizo/fr ontière RDC (8 km) BI-BI-MOF-338268-CS-QCBS / Recrutement d'une firme ch Component 3: Supporting Co Quality And Cost- Open - Internationa Under Implement argée de la gestion du méca IDA / E0700 mmercialization of Selected Post 300,000.00 0.00 2023-02-20 2023-03-13 2023-02-27 2023-03-30 2023-04-05 2023-05-12 2023-05-26 2023-06-30 2023-07-21 2025-07-18 Based Selection l ation nisme de subventions aus as Cross-border Value Chains sociations et coopératives de commerçants BI-BI-MOF-357217-CS-QCBS / Recrutement d'un bureau d' Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement étude pour l'aménagement e IDA / E0700 Post 400,000.00 0.00 2023-04-24 2023-04-26 2023-04-26 2023-06-12 2023-06-02 2023-07-07 2023-07-28 2023-08-25 2023-09-22 2023-12-29 e Trade Infrastructure Based Selection l ation t modernisation des postes fr ontières de Buganda et Mpar ambo BI-BI-MOF-362749-CS-QCBS / Recrutement d'une ONG po Component 4: Supporting Im Quality And Cost- Open - Internationa Under Implement ur la mise en oeuvre des PAR IDA / E0700 plementation and Monitoring Post 100,000.00 0.00 2023-05-31 2023-05-29 2023-06-07 2023-07-14 2023-08-11 2023-08-25 2023-09-22 2023-10-20 2024-06-28 Based Selection l ation du port de Rumonge et du po and Evaluation ste frontière de Gatumba BI-BI-MOF-365295-CS-QCBS / Recrutement d'un bureau c hargé de l'étude d'aménage Component 2: Improving Cor Quality And Cost- Open - Internationa IDA / E0700 Post 200,000.00 0.00 Under Review 2023-06-12 2023-06-19 2023-06-20 2023-08-03 2023-08-31 2023-09-22 2023-10-20 2023-11-17 2024-02-28 ment et de bitumage des voi e Trade Infrastructure Based Selection l es d'accès aux postes frontiè res de Buganda et Mparamb o BI-BI-MOF-367793-CS-LCS / Component 4: Supporting Im Least Cost Selecti Recrutement d'un cabinet d' IDA / E0700 plementation and Monitoring Post Open - National 15,000.00 0.00 Under Review 2023-06-30 2023-06-27 2023-07-10 2023-08-16 2023-08-23 2023-09-08 2023-09-29 2023-10-27 2024-10-26 on audit interne du projet and Evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DMI/002/PFCGL-II/2017 / Ela boration du Cadre de Politiqu e des Peuples Autochtones ( Improving core trade infrastr Individual Consult Pending Impleme CPPA), du Plan en faveur des IDA / V1000 ucture and facilities in the b Post Open 30,000.00 0.00 2017-12-11 2018-01-20 2018-02-06 2018-02-09 2018-03-18 ant Selection ntation populations autochtones (PP order areas A) du Cadre de Politique de R éinstallation (CPR) pour les a ctivitésdu Projet GLTFP BI-BI-MOF-65639-CS-INDV / Improving core trade infrastr Individual Consult IDA / V1000 Post Open 50,000.00 0.00 Canceled 2018-07-27 2018-09-05 2018-09-19 2018-10-04 2018-12-18 Etude sur la logistique et le tr ucture and facilities in the b ant Selection ansport order areas BI-BI-MOF-65645-CS-INDV / Implementation of policy an Enquête auprès des commer d procedural reforms and ca Individual Consult çants des associations profes IDA / V1000 pacity building to facilitate c Post Open 60,000.00 0.00 Canceled 2018-08-05 2018-09-12 2018-09-26 2018-10-10 2019-01-10 ant Selection sionnelles et évaluation des ross-border trade in goods a besoins pour le renforcement nd servic es des capacités BI-BI-MOF-71086-CS-INDV / Implementation support, Co Individual Consult Pending Impleme Consultant Expert en Sauveg IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-07-24 2018-10-28 2018-11-20 2018-11-23 2019-05-19 ant Selection ntation ardes Environnementales et d Evaluation Sociales BI-BI-MOF-71104-CS-INDV / Improving core trade infrastr Elaboration du Cadre de Gest Individual Consult Pending Impleme IDA / V1000 ucture and facilities in the b Post Open 16,210.00 0.00 2018-07-24 2018-08-31 2018-09-24 2018-09-25 2018-11-01 ion Environnementale et Soci ant Selection ntation order areas ale (CGES) du Projet GLTFP DMI/006/PFCGL-II/2018 / Con Implementation support, Co Individual Consult Pending Impleme sultant Responsable en Suivi- IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-07-24 2018-09-16 2018-12-02 2018-12-03 2019-12-02 ant Selection ntation Evaluation d Evaluation DMI/004/PFCGL-II/2018 / Con Implementation support, Co Individual Consult Under Implement sultant Expert en Facilitation IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-01-26 2018-01-25 2018-05-25 2018-05-25 2018-05-28 2019-05-27 ant Selection ation du Commerce d Evaluation BI-BI-MOF-65604-CS-INDV / Implementation support, Co Individual Consult Pending Impleme Consultant Responsable Adm IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-06-07 2018-07-10 2018-07-17 2018-07-23 2019-07-22 ant Selection ntation inistratif et Financier d Evaluation DMI/003/PFCGL-II/2018 / Con Implementation support, Co Individual Consult sultant Coordinateur du proje IDA / V1000 mmunication, Monitoring, an Post Open 48,000.00 0.00 Under Review 2018-01-26 2018-01-19 2018-05-10 2018-05-10 2018-05-14 2019-05-13 ant Selection t d Evaluation Page 3 DMI/007/PFCGL-II/2018 / Con Implementation support, Co Individual Consult Pending Impleme sultant Responsable Passatio IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-01-26 2018-05-25 2018-05-28 2018-05-28 2019-05-27 ant Selection ntation n des Marchés d Evaluation Implementation support, Co DMI/009/PFCGL-II/2018 / Con Individual Consult IDA / V1000 mmunication, Monitoring, an Post Open 24,000.00 0.00 Under Review 2018-01-26 2018-06-08 2018-06-05 2018-06-07 2018-07-01 2019-06-30 sultant Comptable du projet ant Selection d Evaluation BI-BI-MOF-65720-CS-INDV / Implementation of policy an Enumérateurs et Superviseur d procedural reforms and ca Individual Consult Under Implement s pour l'enquête de base et p IDA / V1000 pacity building to facilitate c Post Open 16,631.00 0.00 2018-06-27 2018-11-05 2018-08-06 2018-08-20 2018-08-31 2018-10-31 ant Selection ation our la collecte des données s ross-border trade in goods a ur le commerce transfrontali nd servic es er BI-BI-MOF-170399-CS-INDV / Recrutement d'un consultant Improving service delivery b Individual Consult pour réaliser l'identification e IDA / V3250 y agencies at the border/por Post Open 30,000.00 43,617.38 Completed 2020-08-25 2020-11-05 2020-10-13 2022-02-21 2020-11-03 2022-02-21 2020-12-08 2021-01-13 2021-02-13 2021-04-24 ant Selection t la cartographie des associat t and citizen engagement ions des commerçants transf rontaliers BI-BI-MOF-170412-CS-INDV / Implementation support, Co Recrutement d'un consultant Individual Consult Pending Impleme IDA / V3250 mmunication, Monitoring, an Post Open 20,000.00 0.00 2020-07-31 2020-09-18 2020-10-09 2020-11-13 2021-01-22 en charge de l'élaboration d' ant Selection ntation d Evaluation une stratégie de communicat ion du projet BI-BI-MOF-182061-CS-INDV / Implementation support, Co Individual Consult Under Implement Conception et réalisation du IDA / V3250 mmunication, Monitoring, an Post Open 20,000.00 0.00 2020-08-24 2023-02-21 2020-10-12 2020-11-02 2020-12-07 2021-01-29 ant Selection ation site web PFCGL-II d Evaluation BI-BI-MOF-182703-CS-CDS / Implementation support, Co Audit comptable et financier IDA / V3250 mmunication, Monitoring, an Post Direct Selection Direct 20,000.00 10,844.85 Completed 2020-08-04 2020-07-15 2020-08-14 2020-08-11 2020-10-09 2020-11-03 2020-11-30 2020-12-29 du projet (exercice de juillet d Evaluation 2019 à juin 2020) BI-BI-MOF-203519-CS-INDV / Improving core trade infrastr Individual Consult Recrutement d'un consultant IDA / V3250 ucture and facilities in the b Post Open 20,000.00 0.00 Canceled 2020-11-17 2020-12-29 2021-01-12 2021-02-09 2021-03-15 ant Selection pour la mise à jour du CGES order areas et du CPR BI-BI-MOF-207798-CS-INDV / Component 1. Improving Poli Individual Consult Under Implement Recrutement d'un expert en i IDA / V3250 cy and Regulatory Environm Post Open 40,000.00 0.00 2020-12-09 2020-12-18 2021-01-20 2022-01-06 2021-02-03 2022-01-11 2021-02-08 2022-01-31 ant Selection ation nfrastructures ent for cross border trade BI-BI-MOF-207950-CS-CDS / Entente Directe avec le Cons Improving core trade infrastr ultant Dr NIYONKURU Charles IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 15,000.00 0.00 Canceled 2020-12-10 2020-12-14 2020-12-24 2021-01-29 pour l'Elaboration du CGES + order areas Plan de Gestion des Pestes et Pesticides (PGPP) BI-BI-MOF-207964-CS-CDS / Entente Directe avec le Cons ultant CIMPAYE Joachim pour Improving core trade infrastr la Mise à jour des rapports d'I IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 10,000.00 0.00 Canceled 2020-12-12 2020-12-22 2021-01-06 2021-02-15 mpact Environnemental et S order areas ocial (EIES) pour la constructi on du Port de Rumonge et la construction du marché de G atumba BI-BI-MOF-207970-CS-CDS / Entente Directe avec le Cons Improving core trade infrastr ultant Dr MISAGO Aloispour l IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 10,000.00 0.00 Canceled 2020-12-18 2020-12-28 2021-01-13 2021-02-19 a Préparation du Plan dActio order areas n de Réinstallation (PAR) des Personnes affectées pour la c onstruction du Port de Rumo nge BI-BI-MOF-225823-CS-CDS / Entente Directe avec Monsie ur NDIKUMANA Denis pour l'a Improving core trade infrastr ctualisation/mise à jour des E IDA / V0960 ucture and facilities in the b Post Direct Selection Direct 10,000.00 9,834.66 Completed 2021-03-24 2021-03-24 2021-03-26 2021-03-25 2021-04-02 2021-03-31 2021-05-03 2021-10-20 IES du sous-projet de constru order areas ction du port de Rumonge et celui de construction du mar ché transfrontalier de Gatum ba BI-BI-MOF-239602-CS-CDS / Implementation support, Co Entente Directe avec le bure IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 79,400.00 70,447.09 Signed 2021-06-22 2021-06-17 2021-07-02 2022-02-15 2021-07-30 2021-10-06 2022-01-14 au GETA pour pour l'élaborat d Evaluation ion du CGES du PFCIGL BI-BI-MOF-207962-CS-CDS / Entente Directe avec le Cons ultant BARAKAMFITIYE Tharci Improving core trade infrastr sse pour l'Elaboration du Cad IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 15,000.00 0.00 Canceled 2020-12-11 2020-12-21 2021-01-12 2021-02-16 re de Politique de Réinstallati order areas on (CPR) + Cadre de Planifica tion en faveur des Peuples A utochtones (CPPA) BI-BI-MOF-246029-CS-CDS / Implementation support, Co Entente directe avec Madam IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 26,000.00 33,246.84 Signed 2021-07-30 2021-07-28 2021-08-09 2021-09-03 2021-10-13 2021-05-12 2021-11-01 e Clotilde NIZIGAMA, Coordo d Evaluation nnateur du projet pour l'Actu alisation du contrat BI-BI-MOF-246032-CS-CDS / Entente directe avec Mr BAT Implementation support, Co UNGWANAYO Léonidas, Resp IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 21,600.00 30,476.27 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-02 2021-10-13 2021-07-27 2022-04-30 onsable Administratif et Fina d Evaluation ncier pour l'Actualisation du contrat BI-BI-MOF-246034-CS-CDS / Entente directe avec Monsie Implementation support, Co ur Cyprien BARAMBONERANY IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 24,700.00 27,710.10 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-02 2021-10-13 2021-05-29 2022-04-30 E, Responsable de la Passati d Evaluation on des Marchés pour l'actuali sation du contrat BI-BI-MOF-246037-CS-CDS / Entente directe avec Mr BIRE Implementation support, Co HANISENGE Adophe, Expert IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 24,800.00 30,224.40 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-03 2021-10-13 2021-05-29 2022-04-30 en Facilitation du Commerce d Evaluation et Secteur Privé pour l'actuali sation du contrat BI-BI-MOF-246040-CS-CDS / Entente directe avec Madam Implementation support, Co e KABURA Marie Rose, Respo IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 19,800.00 27,705.70 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-03 2021-10-13 2021-07-21 2022-04-30 nsable des Sauvegardes envi d Evaluation ronnementales pour l'actuali sation du contrat BI-BI-MOF-246044-CS-CDS / Implementation support, Co Entente directe avec Mr Césa IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 19,800.00 27,705.70 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-02 2021-10-13 2021-06-08 2022-04-30 r Abel MAYELE pour l'actualis d Evaluation ation du contrat Page 4 BI-BI-MOF-246046-CS-CDS / Implementation support, Co Entente directe avec Madam IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 17,700.00 16,623.42 Signed 2021-07-30 2021-07-28 2021-08-09 2021-09-03 2021-10-13 2021-07-01 2022-04-30 e NIYOKINDI Consolée pour l' d Evaluation actualisation du contrat BI-BI-MOF-253433-CS-INDV / Implementation support, Co Individual Consult Réalisation d'une enquête de IDA / V0960 mmunication, Monitoring, an Post Open 45,000.00 41,703.71 Signed 2021-09-17 2021-09-17 2021-10-29 2022-02-15 2021-11-05 2022-02-15 2021-11-16 2021-12-16 2022-05-15 ant Selection base dans la zone du PFCIGL d Evaluation BI-BI-MOF-257902-CS-INDV / Entente Directe avec Monsie ur Denis NDIKUMANA pour l'É Component 2: Improving Cor Individual Consult laboration du PAR pour la co IDA / V3250 Post Direct 12,000.00 14,557.51 Signed 2021-10-25 2021-11-22 2021-11-04 2022-02-01 2021-11-15 2022-02-01 2021-11-21 2021-12-14 2021-12-31 e Trade Infrastructure ant Selection nstruction du port de Rumon ge et l’actualisation du PAR p our le poste frontière de Gat umba BI-BI-MOF-262743-CS-CDS / Entente Directe avec la firme CHEMAS pour l'élaboration d Component 2: Improving Cor e l'EIES/PGES et du PAR de la IDA / V3250 Post Direct Selection Direct 420,000.00 0.00 Canceled 2021-11-15 2021-11-19 2022-01-14 2022-02-28 e Trade Infrastructure RN3, projet pilote TNM, du Bo ulevard NDADAYE et du Cont ournement Ouest de Bujumb ura pour le PRT BI-BI-MOF-262749-CS-CDS / Entente Directe avec la firme CHEMAS pour l'assistance te chnique en sauvegardes envi Component 2: Improving Cor ronnementales et sociales et IDA / V3250 Post Direct Selection Direct 300,000.00 0.00 Canceled 2021-11-15 2021-11-21 2022-01-05 2022-03-15 e Trade Infrastructure la préparation des dossiers d u Cadre Environnemental et Social pour PRT et le contrô le qualité des documents de sauvegarde du PFCIGL BI-BI-MOF-303392-CS-CDS / Entente Directe avec Mr NIVY Component 4: Supporting Im Under Implement INTIZO Scarie pour l'élaborati IDA / V3940 plementation and Monitoring Post Direct Selection Direct 50,000.00 0.00 2022-07-13 2022-08-11 2022-07-23 2022-10-18 2022-08-30 2022-10-29 ation on des manuels de procédur and Evaluation es et d'execution du Projet BI-BI-MOF-303396-CS-INDV / Component 2: Improving Cor Individual Consult Pending Impleme Etude de rentabilité du marc IDA / V3940 Post Open 50,000.00 0.00 2022-08-15 2022-10-03 2022-10-24 2022-11-28 2023-01-27 e Trade Infrastructure ant Selection ntation hé transfrontalier de Gatumb a BI-BI-MOF-303470-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un spécialiste IDA / V3940 plementation and Monitoring Post Open 3,500.00 0.00 2022-07-29 2022-08-24 2022-09-16 2022-10-07 2022-11-11 2023-02-10 ant Selection ation en communication and Evaluation BI-BI-MOF-303472-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un spécialiste IDA / V3940 plementation and Monitoring Post Open 4,000.00 0.00 2022-08-04 2022-09-12 2022-09-22 2022-10-13 2022-11-17 2023-02-16 ant Selection ation en VBG and Evaluation BI-BI-MOF-303474-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un spécialiste IDA / V3940 plementation and Monitoring Post Open 4,000.00 0.00 2022-08-10 2022-09-06 2022-09-28 2022-10-19 2022-11-23 2023-02-22 ant Selection ation en Développement social and Evaluation BI-BI-MOF-304400-CS-INDV / Actualisation de l'étude d'im Component 4: Supporting Im pact environnemental et soci Individual Consult Under Implement IDA / V3250 plementation and Monitoring Post Open - National 15,000.00 0.00 2022-07-19 2022-08-09 2022-09-06 2022-09-27 2022-11-01 2022-12-06 al (EIES) pour la construction ant Selection ation and Evaluation et modernisation du poste fr ontière de Gatumba-Kavimvir a BI-BI-MOF-312567-CS-CDS / Component 4: Supporting Im Entente Directe avec le cabin Direct - Internation Under Implement IDA / V3250 plementation and Monitoring Post Direct Selection 15,000.00 0.00 2022-09-06 2022-09-19 2022-09-16 2022-10-14 2022-11-11 2022-12-15 et pour l'audit comptable et f al ation and Evaluation inancier exercice de juillet 20 21 à juin 2022 BI-BI-MOF-319230-CS-INDV / Recrutement d'un Consultant pour l'élaboration d'une étud Component 1. Improving Poli e sur les natures et causes d Individual Consult Pending Impleme IDA / E0700 cy and Regulatory Environm Post Open - National 30,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-16 2023-05-30 es conflits entre les administr ant Selection ntation ent for cross border trade ations des frontières et les co mmerçants, entre les service s ou entre les commerçants au niveau des frontières ciblé es du projet BI-BI-MOF-319247-CS-INDV / Réalisation de l'Etude d'Impa ct Environnemental et Social Component 2: Improving Cor Individual Consult Pending Impleme IDA / E0700 Post Open - National 25,000.00 0.00 2023-04-20 2023-06-08 2023-06-22 2023-07-13 2023-09-22 (EIES) des travaux d'aménag e Trade Infrastructure ant Selection ntation ement et modernisation des i nfrastructures du poste fronti ère de Vugizo-Kiliba BI-BI-MOF-319248-CS-INDV / Recrutement d'un consultant pour la préparation du plan d Component 2: Improving Cor Individual Consult Pending Impleme 'action de réinstallation des t IDA / E0700 Post Open - National 30,000.00 0.00 2023-04-27 2023-06-08 2023-06-22 2023-07-13 2023-09-29 e Trade Infrastructure ant Selection ntation ravaux d'aménagement et m odernisation des infrastructur es du poste frontière de Vugi zo-Kiliba BI-BI-MOF-335993-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un assistant e IDA / E0700 plementation and Monitoring Post Open - National 36,000.00 0.00 2023-01-18 2023-01-19 2023-02-15 2023-03-08 2023-03-30 2024-03-29 ant Selection ation n passation des marchés and Evaluation BI-BI-MOF-335996-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un assistant c IDA / E0700 plementation and Monitoring Post Open - National 36,000.00 0.00 2023-01-26 2023-01-30 2023-03-01 2023-03-15 2023-04-05 2024-04-04 ant Selection ation omptable and Evaluation BI-BI-MOF-344280-CS-QCBS Component 4: Supporting Im / Recrutement d'un bureau p Individual Consult Open - Internationa IDA / E0700 plementation and Monitoring Post 100,000.00 0.00 Canceled 2023-03-31 2023-04-03 2023-05-03 2023-05-24 2023-06-21 2023-09-29 our effectuer un audit techni ant Selection l and Evaluation que du Bureau Burundais de Normalisation (BBN) BI-BI-MOF-353142-CS-INDV / Recrutement d'un consultant Component 2: Improving Cor Individual Consult Under Implement individuel pour la conception IDA / E0700 Post Open - National 20,000.00 0.00 2023-03-31 2023-04-03 2023-05-03 2023-05-17 2023-06-16 2023-08-16 e Trade Infrastructure ant Selection ation des infrastructures provisoire s aux postes frontières de Bu ganda et Mparambo Page 5 BI-BI-MOF-360296-CS-CDS / Entente Directe avec le cabin Component 4: Supporting Im Direct - Internation Under Implement et ABC pour l'audit comptabl IDA / E0700 plementation and Monitoring Post Direct Selection 15,000.00 0.00 2023-05-12 2023-05-20 2023-05-22 2023-05-29 2023-07-26 2023-11-15 al ation e et financier de l'exercice de and Evaluation juillet 2022 à juin 2023 BI-BI-MOF-364126-CS-INDV / RECRUTEMENT D'UN CONSUL TANT CHARGE D'EFFECTUER Component 3: Supporting Co UN AUDIT TECHNIQUE ET INS Individual Consult Open - Internationa IDA / E0700 mmercialization of Selected Post 100,000.00 0.00 Under Review 2023-06-05 2023-06-05 2023-07-17 2023-07-31 2023-09-04 2023-11-17 TITUTIONNEL DU BUREAU BU ant Selection l Cross-border Value Chains RUNDAIS DE NORMALISATIO N ET CONTROLE DE LA QUALI TE (BBN) EN MATIERE DE CE RTIFICATION BI-BI-MOF-365300-CS-INDV / Component 4: Supporting Im Recrutement d'un consultant Individual Consult Pending Impleme IDA / E0700 plementation and Monitoring Post Open - National 25,000.00 0.00 2023-07-20 2023-08-31 2023-09-14 2023-10-19 2023-12-15 pour l'élaboration du plan de ant Selection ntation and Evaluation gestion de la biodiversité Page 6 Procurement Plan I. General 1. Project Information Country : Kenya Recipient : Republic of Kenya Project Name : National Agriculture and Rural Inclusive Growth Loan Credit No. : IDA 59000 2. Date of General Procurement Notice : 9th February 2018 3. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services 1. Thresholds for the Method of Procurement: Method of Procurement Thresholds for Method (US$ equivalent) Open International (Goods) Equal to or more than 3 million Open National ( Goods) – Open < $3 million Tender as per PPDA 2015 RFQ (Goods) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Open International (Works) Equal to or more than 15 million Open National (Works) - Open Less than 15 million Tender as per PPDA 2015 RFQ (works) Less than 20,000 or as stipulated in Kenya Procurement Regulations 2017 Method of Procurement Thresholds for Method (US$ equivalent) Open International (Non-consulting Equal to or More than 3 million Services) Open National (Non-consulting Less than 3 million Services) - Open Tender as per PPDA 2015 Direct Contracting No threshold; meet requirements of Bank’s Procurement Regulations Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection (Project Procurement Risk Rating is “High”): (a) Goods, information technology and Non-consulting Services: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1.5 million (b) Works (including turnkey, supply & installation of plant and equipment and PPP); First procurement under the project irrespective of value and all procurements estimated to cost more than USD 5 million and The prior review thresholds will be reviewed during the implementation of the project and modified, based on the risk assessment. 2. For contracts subject to prior review, the Borrower shall seek the Bank’s no objection before agreeing to: a. an extension of the stipulated time for execution of a contract that has an impact on the planned completion of the project; b. any material modification of the scope of the Works, Goods, Non- consulting services or Consulting Services, or other significant changes to the terms and conditions of the contract; c. any variation order or contract amendment (except in cases of extreme urgency), including due to extension of time, that singly or combined with all previous variation orders or amendments, increases the original contract amount by more than 15% (fifteen percent); or d. the proposed termination of the contract. The Borrower / IA shall provide a copy of all amendments to the contract to the Bank for its records. 3. Prequalification Not Applicable Domestic Preference. The provision of domestic preference shall be applied in the procurement of goods following international market approach in accordance with Annex VI of the Regulations. Domestic preference shall not apply in the procurement of works. 4. Reference to Standard Procurement Documents Bank’s Standard RFB Goods and RFP Consulting Services dated July 2016 will be used as a base and incorporating suitable modifications and the same would be agreed with the Bank subject international competition. 5. Any Other Special Procurement Arrangements A. Procurement approach under CDD Approach by Communities: Applicable if stipulated in the PAD. B. When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2017 may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality aspects. 6. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Selection methods of procurement of Consultants' Services (Firms): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Quality and Cost Based As per requirements of para 7.3 of the Selection (QCBS) Regulations Quality Based Selection As per requirements of para 7.8 to 7.10 (QBS) of the Regulations Selection based on a Fixed As per requirements of para 7.4 and 7.5 of the Budget (FBS) Regulations Selection Based on Least As per requirements of para 7.6 and 7.7 of the Cost Basis (LCS) Regulations Selection based on As per requirements of para 7.11 and 7.12 of Consultant’s Qualification the Regulations (CQ) Direct Must meet the requirements of Para 7.13 to 7.15 of the Regulations, and with prior agreement in PP with the Bank. The short list may consist of all National consultants in case the estimated cost is less than USD 300,000 Procurement methods for Selection of Individual Consultants (IC): The Approved Selection Methods as reflected in the Section VII of the procurement regulations Method of Procurement Thresholds for Methods Open Competitive As per requirements of para 7.36 and 7.37 of Selection the Regulations Limited Competitive As per requirements of para 7.38 of the Selection Regulations Direct Must meet the requirements of Para 7.39 of the Regulations, and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Regulations Prior Review Thresholds: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. The following would be subject to Prior review of the Bank regardless of the Method of selection: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 0.5 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.2 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. PROCUREMENT Kenya : National Agricultural and Rural Inclusive Growth Project PLAN General Information Country: Kenya 2019-10-04 Bank’s Approval Date of the Original Procurement Plan: 2023-06-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153349 GPN Date: 2018-02-09 Project Name: National Agricultural and Rural Inclusive Growth Project Loan / Credit No: IDA / 59000 Kisii County Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-KISII COUNTY-140174-CW Project Coordination and Ma Request for Quota Single Stage - One E 2020-06-1 -RFQ / renovation works at A IDA / 59000 Post Limited 14,041.42 14,190.45 Completed 2019-10-19 2019-11-08 2019-12-14 2019-12-05 nagement tions nvelope 1 TC NARIGP offices KE-KISII COUNTY-167455-CW Supporting County Communi Single Stage - One E 2021-03-1 -RFB / proposed construction IDA / 59000 Post Request for Bids Open - National 1,000,000.00 850,110.00 Completed 2020-04-21 2020-04-28 2020-04-28 2020-09-15 2020-05-01 2020-09-15 2020-05-06 2020-06-05 2020-05-16 2020-07-18 ty-Led Development nvelope 2 of nyamache banana market KE-KISII COUNTY-216089-CW -RFQ / proposed construction Supporting County Communi Request for Quota Single Stage - One E 2021-06-0 IDA / 59000 Post Limited 57,504.25 0.00 Signed 2021-02-13 2022-07-01 2021-03-09 of watershed hotspot activiti ty-Led Development tions nvelope 7 es in Nyamesocho KE-KISII COUNTY-216087-CW Supporting County Communi Request for Quota Single Stage - One E 2021-06-0 -RFQ / proposed construction IDA / 59000 Post Limited 64,596.77 0.00 Signed 2021-02-13 2022-07-08 2021-03-05 ty-Led Development tions nvelope 3 of watershed hotspot activiti es in Nyakani KE-KISII COUNTY-320530-CW Request for Bids - Strengthening Producer Org -RFB / Proposed Construction Single Stage - One E Small Works SPD 2023-06-3 IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 370,278.54 0.00 Signed 2022-10-11 2022-10-17 2022-10-21 2022-12-15 2022-11-20 2022-11-11 2022-12-04 2022-11-18 2023-01-01 of Magena Vegetable Aggreg nvelope (1 envelope proce 0 Development ation & Marketing Centre ss) KE-KISII COUNTY-320531-CW Request for Bids - Strengthening Producer Org -RFB / Proposed Construction Single Stage - One E Small Works SPD 2023-06-3 IDA / 59000 anizations and Value Chain Post Request for Bids Open - National 370,278.54 0.00 Signed 2022-10-11 2022-10-17 2022-10-21 2022-12-15 2022-11-20 2022-11-11 2022-12-04 2022-11-18 2023-01-01 of Marani Vegetable Aggrega nvelope (1 envelope proce 0 Development tion & Marketing Centre ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KISII COUNTY-138534-GO Supporting County Communi Single Stage - One E IDA / 59000 Post Request for Bids Open - National 100,000.00 6,254.81 Completed 2019-10-03 2019-10-04 2019-10-05 2019-10-04 2019-11-04 2019-10-04 2019-11-18 2019-10-04 2019-12-23 2019-10-04 2020-01-22 2019-10-04 -RFB / procurement of motor ty-Led Development nvelope cycles KE-KISII COUNTY-144916-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / purchase of 20 cabine IDA / 59000 Post Limited 7,350.00 2,579.61 Completed 2019-12-25 2020-04-14 2020-01-16 2020-04-25 2020-01-31 2020-05-13 nagement tions nvelope ts for cddc and 1 executive t able for cessco KE-KISII COUNTY-144917-GO Supporting Community-Driv Request for Quota Single Stage - One E -RFQ / Agricultural Materials, IDA / 59000 Post Limited 40,220.00 37,067.28 Completed 2020-01-01 2020-06-03 2020-01-23 2020-07-01 2020-02-07 2020-12-24 en Development tions nvelope Supplies and Small Equipme nt KE-KISII COUNTY-148933-GO Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 10,000.00 7,376.67 Completed 2019-12-25 2020-04-20 2020-01-16 2020-05-01 2020-01-31 2020-06-20 -RFQ / Purchase of laptops nagement tions nvelope KE-KISII COUNTY-167453-GO Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 80,000.00 73,364.06 Completed 2020-04-28 2020-06-05 2020-05-17 2020-06-20 2020-06-16 2020-07-17 -RFB / purchase of motorcycl nagement tions nvelope es KE-KISII COUNTY-169149-GO -RFQ / procurement of install Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 63,000.00 69,555.28 Completed 2020-04-26 2020-05-05 2020-05-18 2020-05-15 2020-06-17 2020-08-21 ation and commissioning of I nagement tions nvelope P based audio-visual teleconf erence system KE-KISII COUNTY-173312-GO -RFQ / Supply and Installation Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 13,000.00 69,555.28 Completed 2020-05-15 2020-05-05 2020-05-30 2020-05-15 2020-06-29 2020-08-21 of Video Conferencing Equip nagement tions nvelope ment (IP network connectivit y, firewall and router) KE-KISII COUNTY-206421-GO Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 1,318.00 12,223.77 Completed 2020-12-05 2020-12-16 2020-12-19 2021-01-07 2021-01-18 2021-01-26 -RFQ / purchase of farm tools ty-Led Development tions nvelope KE-KISII COUNTY-206426-GO Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 36,360.00 16,351.23 Completed 2020-12-05 2020-12-16 2020-12-19 2020-12-30 2021-01-18 2021-02-03 -RFQ / purchase of agricultur ty-Led Development tions nvelope al items KE-KISII COUNTY-206430-GO Supporting County Communi Request for Quota Single Stage - One E -RFQ / procurement of publis IDA / 59000 Post Limited 4,000.00 3,594.18 Completed 2020-12-05 2020-12-16 2020-12-19 2020-12-29 2021-01-18 2021-04-27 ty-Led Development tions nvelope hing and printing materials KE-KISII COUNTY-206438-GO Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 4,000.00 3,639.74 Completed 2020-12-05 2020-12-16 2020-12-19 2020-12-30 2021-01-18 2021-01-16 -RFQ / purchase of phones ty-Led Development tions nvelope KE-KISII COUNTY-206429-GO Supporting County Communi Request for Quota Single Stage - One E IDA / 59000 Post Limited 825.00 767.44 Completed 2021-01-31 2020-12-16 2021-02-14 2020-12-31 2021-03-16 2021-01-29 -RFQ / purchase of roadshow ty-Led Development tions nvelope items KE-KISII COUNTY-276686-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / Purchase of smart pho IDA / 59000 Post Limited 2,000.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 nagement tions nvelope nes for County A.I service pro viders KE-KISII COUNTY-276688-GO Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 300.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 -RFQ / Purchase of speakers nagement tions nvelope KE-KISII COUNTY-276690-GO Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 2,228.00 0.00 Signed 2022-02-24 2022-06-08 2022-03-20 2022-04-19 -RFQ / Purchase of stickers a nagement tions nvelope nd reflectors Page 1 KE-KISII COUNTY-276692-GO -RFQ / procurement of Web-b Project Coordination and Ma Request for Quota Single Stage - One E ased Dashboard and Analytic IDA / 59000 Post Limited 8,000.00 0.00 Signed 2022-02-24 2022-07-14 2022-03-20 2022-04-19 nagement tions nvelope s Application plus Android Da ta Collection Application KE-KISII COUNTY-276697-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / procurement of Specia IDA / 59000 Post Limited 3,654.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 nagement tions nvelope lly designed Android Tablet KE-KISII COUNTY-276699-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / procurement of Smart IDA / 59000 Post Limited 6,786.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 nagement tions nvelope Digital Projector with Android OS KE-KISII COUNTY-276700-GO Project Coordination and Ma Request for Quota Single Stage - One E IDA / 59000 Post Limited 2,955.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 -RFQ / procurement of Ruka nagement tions nvelope device KE-KISII COUNTY-276703-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / procurement of Agripr IDA / 59000 Post Limited 9,396.00 0.00 Signed 2022-02-24 2022-07-01 2022-03-20 2022-04-19 nagement tions nvelope eneurs Digital platform Licen se KE-KISII COUNTY-276708-GO Project Coordination and Ma Request for Quota Single Stage - One E -RFQ / procurement of EQUIP IDA / 59000 Post Limited 12,000.00 0.00 Signed 2022-02-24 2022-06-08 2022-03-20 2022-04-19 nagement tions nvelope MENT & LINCENSING KE-KISII COUNTY-363805-GO -RFQ / Procurement of 3no d Supporting County Communi Request for Quota Single Stage - One E Under Imple IDA / 59000 Post Open - National 3,254.00 0.00 2023-06-02 2023-06-23 2023-07-23 esktop computers,backup an ty-Led Development tions nvelope mentation d printers for 3 saccos KE-KISII COUNTY-363826-GO Supporting Community-Driv Request for Quota Single Stage - One E Under Imple -RFQ / Procurement of Hass A IDA / 59000 Post Open - National 8,586.00 0.00 2023-06-05 2023-07-02 2023-08-01 en Development tions nvelope mentation vocado Seedlings KE-KISII COUNTY-363820-GO Project Coordination and Ma Under Imple -DIR / Procurement of soil dig IDA / 59000 Post Direct Selection Direct - National 7,549.00 0.00 2023-06-14 2023-06-13 2023-06-17 2023-06-12 2023-07-04 2023-08-03 nagement mentation ital testing kit (soil pal) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KISII COUNTY-171191-CS Supporting Community-Driv Consultant Qualifi -CQS / service provider for ba IDA / 59000 Post Open - National 50,000.00 23,154.47 Completed 2020-05-12 2020-08-17 2020-05-19 2020-06-09 2020-08-21 2020-06-12 2021-01-14 2020-06-26 2021-01-19 2021-12-28 2022-01-05 en Development cation Selection nana value chain KE-KISII COUNTY-171198-CS Supporting Community-Driv Consultant Qualifi -CQS / service provider for da IDA / 59000 Post Open - National 50,000.00 23,145.91 Completed 2020-05-12 2020-08-17 2020-05-19 2020-06-09 2020-08-21 2020-06-12 2021-01-10 2020-06-26 2021-01-19 2021-12-28 2022-01-05 en Development cation Selection iry (cow) value chain KE-KISII COUNTY-171199-CS Supporting Community-Driv Consultant Qualifi -CQS / service provider for lo IDA / 59000 Post Open - National 50,000.00 23,073.65 Completed 2020-05-12 2020-08-17 2020-05-19 2020-06-09 2020-08-21 2020-06-12 2021-01-10 2020-06-26 2021-01-19 2021-12-28 2022-01-05 en Development cation Selection cal vegetable value chain KE-KISII COUNTY-171200-CS Supporting Community-Driv Consultant Qualifi -CQS / service provider for ch IDA / 59000 Post Open - National 50,000.00 23,158.88 Completed 2020-05-12 2020-08-17 2020-05-19 2020-06-09 2020-08-21 2020-06-12 2021-01-10 2020-06-26 2021-01-19 2021-12-28 2022-01-05 en Development cation Selection icken value chain INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-KISII COUNTY-276269-CS -INDV / Procurement of consu Supporting Community-Driv Individual Consult IDA / 59000 Post Limited 26,408.45 0.00 Canceled 2022-02-02 2022-02-07 2022-02-28 2022-04-04 2022-10-01 ltancy services to support FI en Development ant Selection MG in selected Saccos Page 2 Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by <mention name of PIU> 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other July 9, 2010 methods July 9, 2010 PROCUREMENT Tanzania : Citizen-Centric Judicial Modernization and Justice Service Delivery PLAN General Information Country: Tanzania 2016-08-05 Bank’s Approval Date of the Original Procurement Plan: 2023-06-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155759 GPN Date: 2022-06-09 Project Name: Citizen-Centric Judicial Modernization and Justice Service Delivery Loan / Credit No: IDA / 57780, IDA / 70580 Judiciary of Tanzania Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-18206-CW- Component 2: Skills Develop DIR / Construction of training 2018-03-0 2020-01 IDA / 57780 ment, Inspection and Perfor Prior Direct Selection Direct 35,175.53 Completed 2017-07-14 2017-06-29 2017-07-19 2017-08-22 2017-09-06 2017-08-24 room at Kisutu Residence Ma 5 -22 mance Management gistrate Court location in Dar es Salaam TZ-JUDICIARY TZ-118965-C W-RFB / Construction of Integ rated Justice Centers (IJCs) in Component 3: Access to Just Open - Internationa Single Stage - One E 22,309,086. 2020-04-1 IDA / 57780 Prior Request for Bids Signed 2019-06-28 2019-07-31 2019-07-03 2019-08-01 2019-08-14 2019-09-20 2019-09-13 2019-12-04 2019-10-18 2020-01-11 Six Selected Locations of Mw ice and Public Trust l nvelope 76 5 anza, Morogoro, Arusha, Dod oma and Dar es Salaam-Six L ots TZ-JUDICIARY TZ-211158-C W-RFB / Construction of Subo Component 3: Access to Just Single Stage - One E 7,950,439.8 2021-09-0 IDA / 57780 Prior Request for Bids Open - National Signed 2020-12-28 2021-02-04 2021-01-04 2021-02-11 2021-02-08 2021-03-23 2021-02-28 2021-08-24 2021-04-04 2021-09-11 rdinate Courts in twenty five( ice and Public Trust nvelope 1 1 25) Selected Locations aroun d Tanzania. TZ-JUDICIARY TZ-364564-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Four Selected Locations of Si nvelope proc ngida, Simiyu, Geita and Pem ess) ba-Four Lots TZ-JUDICIARY TZ-364566-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Five Selected Locations of Ka nvelope proc tavi, Songwe, Njombe, Mtwar ess) a and Songea-Five Lots TZ-JUDICIARY TZ-364568-C Request for B W-RFB / Construction of Integ ids - Small W Component 3: Access to Just Open - Internationa Single Stage - One E Under Revie 2024-06-1 rated Justice Centers (IJCs) in IDA / 70580 Prior Request for Bids orks SPD (1 e 0.00 2023-06-06 2023-06-11 2023-07-23 2023-08-22 2023-09-12 ice and Public Trust l nvelope w 3 Five Selected Locations of Pw nvelope proc ani, Tanga, Moshi, Manyara a ess) nd Lindi-Five Lots TZ-JUDICIARY TZ-9217-CW-D IR / Construction of ten (10) c Component 3: Access to Just 2017-11-1 ourthouses for subordinate c IDA / 57780 Prior Direct Selection Direct 0.00 Canceled 2017-04-10 2017-04-15 2017-05-20 ice and Public Trust 6 ourts Primary Court and Trai ning room at Kisutu RMs Cou rt. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-4371-GO-R Component 1: Governance, Request for Quota Single Stage - One E FQ / Design, Editing and Print IDA / 57780 Organization and Systems D Post Limited 40,909.50 Completed 2016-12-18 2016-12-05 2017-02-12 2017-01-24 2017-08-11 2017-02-08 tions nvelope ing of Strategic plan, Brochur evelopment es TZ-JUDICIARY TZ-9220-GO-R Component 1: Governance, Single Stage - One E FB / Supply of IT Equipment f IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-07-15 2017-07-20 2017-08-31 2017-09-30 2017-11-04 2018-05-03 nvelope or registries & DJSIE evelopment TZ-JUDICIARY TZ-30083-GO- Component 2: Skills Develop RFQ / Procurement of office f Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 32,612.45 Completed 2017-09-30 2017-10-04 2017-11-05 2017-11-25 2018-05-04 2018-01-23 acilities for training center at tions nvelope mance Management Kisutu Resident Magistrate C ourt-Dar es salaam TZ-JUDICIARY TZ-30400-GO- RFQ / Procurement of office v Component 2: Skills Develop Request for Quota Single Stage - One E ideo conference facilities for IDA / 57780 ment, Inspection and Perfor Post Limited 83,134.05 Completed 2017-10-03 2017-10-05 2017-11-28 2017-10-31 2018-05-27 2018-04-16 tions nvelope training center at Kisutu resi mance Management dent magistrate court-Dar es salaam. TZ-JUDICIARY TZ-30103-GO- Component 2: Skills Develop RFQ / Procurement of IT equi Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 77,394.71 Completed 2017-10-04 2017-10-12 2017-11-09 2017-11-14 2018-05-08 2018-05-16 pment for training center at tions nvelope mance Management Kisutu Resident Magistrate C ourt- Dar es Salaam. TZ-JUDICIARY TZ-37777-GO- RFQ / Supply, Installation and Component 1: Governance, Commissioning of Furniture, Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 91,246.04 Completed 2017-11-27 2017-11-28 2018-01-08 2018-01-19 2018-02-05 2018-04-06 LAN, CCTV camera and Bio-m tions nvelope evelopment etric Door Access System for Retooling of Judiciary Deliver y Unit Office. TZ-JUDICIARY TZ-40300-GO- RFB / Supply, Installation, Te Component 1: Governance, st and Commissioning of Vid Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 594,512.13 Completed 2017-12-21 2018-01-11 2017-12-26 2018-01-25 2018-02-09 2018-02-24 2018-03-21 2018-03-31 2018-05-15 2018-09-27 2019-06-18 eo Conferencing facilities, Au nvelope evelopment dio Visual and Recording equ ipment at four selected Court s TZ-JUDICIARY TZ-64942-GO- Component 1: Governance, Request for Quota Single Stage - One E RFQ / Procurement of ICT eq IDA / 57780 Organization and Systems D Post Limited 95,937.33 Completed 2018-06-16 2018-06-14 2018-08-11 2018-08-07 2019-02-07 2018-09-21 tions nvelope uipment for new directorates evelopment TZ-JUDICIARY TZ-64971-GO- Component 1: Governance, Request for Quota Single Stage - One E RFQ / Procurement of furnitur IDA / 57780 Organization and Systems D Post Limited 71,421.54 Completed 2018-06-16 2018-06-14 2018-08-11 2018-07-17 2019-02-07 2018-11-23 tions nvelope e for new directorates evelopment Page 1 TZ-JUDICIARY TZ-67572-GO- Component 3: Access to Just Single Stage - One E RFB / Procurement of furnitur IDA / 57780 Prior Request for Bids Open - National 1,785,846.11 Completed 2018-07-25 2019-01-09 2018-07-30 2019-01-29 2018-09-10 2019-02-28 2018-10-10 2019-05-15 2018-11-14 2019-07-02 2019-05-13 2023-02-18 ice and Public Trust nvelope e for eighteen (18) new court buildings. TZ-JUDICIARY TZ-87170-GO- Component 2: Skills Develop UN Agencies (Dire UN / Procurement of 57 moto IDA / 57780 ment, Inspection and Perfor Prior Direct 1,701,529.79 Completed 2018-11-30 2018-12-05 2019-01-16 2019-01-28 2019-07-15 2019-06-30 ct) r vehicles mance Management TZ-JUDICIARY TZ-62259-GO- Component 2: Skills Develop Open - Internationa Single Stage - One E RFB / Procurement of 57 mot IDA / 57780 ment, Inspection and Perfor Prior Request for Bids 0.00 Canceled 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 2019-03-20 l nvelope or vehicles mance Management TZ-JUDICIARY TZ-91934-GO- RFB / Supply, Installation, Te sting and Commissioning of L Component 3: Access to Just Single Stage - One E ocal Area Network and other IDA / 57780 Post Request for Bids Open - National 592,972.08 Completed 2018-12-28 2019-04-25 2019-01-02 2019-01-30 2019-07-12 2019-03-01 2019-08-19 2019-04-05 2019-11-20 2019-10-02 2020-07-26 ice and Public Trust nvelope ICT equipment for Moderniza tion of ICT Infrastructure to T wenty Three (23) New Court s Buildings. TZ-JUDICIARY TZ-107689-GO -DIR / SUPPLY AND INSTALLA TION OF NETWORK/FIBER CO Component 1: Governance, NNECTIVITY AND PROVISION IDA / 57780 Organization and Systems D Prior Direct Selection Direct 1,814,257.31 Signed 2019-04-01 2019-04-24 2019-04-06 2019-05-22 2019-05-11 2019-07-29 2019-11-07 OF DATA AND INTERNET SER evelopment VICES TO HIGH COURTS, REG IONAL MAGISTRATES AND DI STRICT COURTS BUILDINGS C OUNTRYWIDE. TZ-JUDICIARY TZ-110239-GO Component 2: Skills Develop -RFQ / PROCUREMENT OF PR Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 42,683.08 Completed 2019-04-20 2019-05-02 2019-06-15 2019-06-17 2019-12-12 2019-10-28 OTECTIVE ACCESSORIES FOR tions nvelope mance Management THE 57 PROCURED MOTOR V EHICLES. TZ-JUDICIARY TZ-113691-GO Component 1: Governance, -RFB / Procurement of Gadge Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 219,227.79 Completed 2019-05-10 2019-05-10 2019-05-15 2019-06-26 2019-06-14 2019-07-26 2019-07-23 2019-08-30 2019-08-02 2020-02-26 2020-01-30 ts (POS) for utilization of GeP nvelope evelopment G government system TZ-JUDICIARY TZ-118395-GO Component 1: Governance, -RFQ / Procurement of Stand Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 26,526.32 Completed 2019-06-26 2019-06-20 2019-08-21 2019-09-24 2020-02-17 2020-01-19 by Generator for High Court- tions nvelope evelopment Commercial Division TZ-JUDICIARY TZ-120930-GO Component 2: Skills Develop -RFQ / Procurement of ICT eq Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 22,480.99 Completed 2019-07-06 2019-07-22 2019-08-31 2019-08-30 2020-02-27 2019-10-31 uipment and furniture for Co tions nvelope mance Management urt brokers and advocate sec tion TZ-JUDICIARY TZ-144324-GO Component 3: Access to Just Request for Quota Single Stage - One E -RFQ / PROCUREMENT OF ICT IDA / 57780 Post Limited 8,221.98 Completed 2019-11-19 2019-12-06 2020-01-14 2020-04-01 2020-07-12 2020-06-25 ice and Public Trust tions nvelope EQUIPMENT FOR LEGAL AID UNIT - MOCLA TZ-JUDICIARY TZ-159885-GO Component 1: Governance, -UN / Procurement of ICT equ UN Agencies (Dire IDA / 57780 Organization and Systems D Prior Direct 1,370,192.72 Completed 2020-02-25 2020-05-18 2020-03-01 2020-05-19 2020-04-19 2020-05-16 2020-10-16 2020-10-13 pment for registries, Court of ct) evelopment Appeal and centres. TZ-JUDICIARY TZ-168252-GO Component 1: Governance, -DIR / Supply of ICT equipme IDA / 57780 Organization and Systems D Post Direct Selection Direct 268,181.31 Completed 2020-04-15 2020-04-15 2020-04-17 2020-04-15 2020-04-20 2020-04-18 2020-04-25 2021-05-09 nt to facilitate e-court service evelopment s as a response measures ag ainst COVID-19 TZ-JUDICIARY TZ-178077-GO -RFB / Procurement of furnitu Component 3: Access to Just Single Stage - One E re for six Integrated Justice C IDA / 57780 Prior Request for Bids Open - National 3,069,984.39 Completed 2020-06-26 2020-06-29 2020-07-01 2020-06-30 2020-08-12 2020-07-28 2020-09-11 2020-08-20 2020-10-16 2020-10-28 2021-04-14 2021-12-18 ice and Public Trust nvelope enters located in Mwanza, Ar usha,Morogoro,Dodoma, Tem eke and Kinondoni. TZ-JUDICIARY TZ-180768-GO -RFB / SUPPLY, INSTALLATIO N AND CONFIGURATION OF Component 1: Governance, Single Stage - One E MICROSOFT OFFICE PROFESS IDA / 57780 Organization and Systems D Post Request for Bids Open - National 650,286.94 Completed 2020-06-26 2020-07-16 2020-07-01 2020-07-17 2020-07-22 2020-08-03 2020-07-29 2020-09-01 2020-08-10 2020-11-21 2020-09-07 2020-12-24 nvelope IONAL 2019 FOR 1388 LAPTO evelopment PS AND 14 DESKTOPS FOR M AGISTRATES AND COURT OF APPEAL REGISTRIES TZ-JUDICIARY TZ-180771-GO -RFQ / PROCUREMENT OF SC Component 3: Access to Just Request for Quota Single Stage - One E ANNERS FOR TWO INTERGRA IDA / 57780 Post Limited 27,451.65 Completed 2020-08-04 2020-06-25 2020-09-13 2020-12-05 2020-09-22 2021-05-20 ice and Public Trust tions nvelope TED JUSTICE CENTRES (IJCS) LOCATED IN MOROGORO AN D TEMEKE DAR ES SALAAM. TZ-JUDICIARY TZ-180773-GO -UN / PROCUREMENT OF ICT Component 3: Access to Just UN Agencies (Dire EQUIPMENT FOR TWO INTER IDA / 57780 Post Direct 27,451.65 Completed 2020-07-01 2020-07-21 2020-07-06 2020-07-22 2020-08-10 2020-12-05 2020-12-08 2021-09-15 ice and Public Trust ct) GRATED JUSTICE CENTRES (IJ CS) LOCATED IN MOROGORO AND TEMEKE DAR ES SALAA M. TZ-JUDICIARY TZ-182131-GO Component 1: Governance, -RFQ / Supply and Installation Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 4,764.07 Completed 2020-07-03 2020-07-08 2020-07-10 2020-08-23 2021-01-06 2020-10-27 of plumbing materials and fit tions nvelope evelopment tings at new JDU Offices-Haki House TZ-JUDICIARY TZ-182133-GO Component 1: Governance, -RFQ / Supply and Installation Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 7,534.44 Completed 2020-07-02 2020-07-08 2020-07-10 2020-08-29 2021-01-06 2020-09-01 of LAN,CCTV, security door s tions nvelope evelopment ystem and telephones at JDU offices-Haki House TZ-JUDICIARY TZ-182134-GO -RFQ / Supply and installation Component 1: Governance, of office partitioning material Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 51,159.33 Completed 2020-07-02 2020-07-09 2020-07-10 2020-10-03 2021-01-06 2021-01-26 s and dismantal , packing an tions nvelope evelopment d re-instllation of Office facilit ies from Rita tower and PPF T ower to HAKI House. TZ-JUDICIARY TZ-182136-GO Component 1: Governance, Request for Quota Single Stage - One E -RFQ / Supply and Installation IDA / 57780 Organization and Systems D Post Limited 9,799.74 Completed 2020-07-02 2020-07-08 2020-07-10 2020-08-20 2021-01-06 2020-12-01 tions nvelope of Air Conditions at JDU Offic evelopment es -Haki House TZ-JUDICIARY TZ-188551-GO -RFQ / Supply, Installation, te Component 3: Access to Just Request for Quota Single Stage - One E sting and comissioning of LA IDA / 57780 Post Limited 23,461.52 Completed 2020-08-26 2020-08-23 2020-10-02 2020-11-17 2020-12-01 2021-04-15 ice and Public Trust tions nvelope N at Office of Attorney Gene ral in Dar es Salaam and Dod oma. Page 2 TZ-JUDICIARY TZ-211164-GO Component 1: Governance, Request for Quota Single Stage - One E -RFQ / Procurement of ICT Fa IDA / 57780 Organization and Systems D Post Limited 21,195.18 Completed 2021-01-02 2020-12-31 2021-02-03 2021-03-18 2021-04-04 2021-06-25 tions nvelope cilities for Kigamboni " Paper evelopment less Court" TZ-JUDICIARY TZ-221783-GO -RFB / Procurement of ICT eq Component 3: Access to Just Single Stage - One E uipment for Six Integrated Ju IDA / 57780 Post Request for Bids Open - National 560,528.31 Completed 2021-03-01 2021-08-04 2021-03-06 2021-08-04 2021-04-05 2021-08-27 2021-04-30 2020-08-30 2021-05-24 2021-09-22 2021-09-21 2021-12-08 ice and Public Trust nvelope stice Centers(IJCs) in Arusha, Mwanza, Dodoma, Morogoro, Kinondoni, and Temeke. TZ-JUDICIARY TZ-260890-GO -RFB / Procurement of furnitu re for eighteen(18) Subordin ate Courts located at Kaliua, Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2021-11-12 2021-11-29 2021-11-17 2021-11-29 2021-12-15 2021-12-20 2021-12-29 2021-12-27 2022-01-12 2022-05-12 Uvinza, Buhigwe, Kakonko, B ice and Public Trust nvelope utiama, Rorya, Itilima, Buseg a, Songwe, Tanganyika, Mbo gwe, Nyang’wale , Kyerwa, M isenyi, Gairo, Mvomero, Kilo mbero and Mkinga. TZ-JUDICIARY TZ-260892-GO -RFB / Supply, Installation, Te st and Commissioning of ICT equipment for eighteen(18) S Component 3: Access to Just Single Stage - One E ubordinate Courts located at IDA / 57780 Post Request for Bids Open - National 659,497.68 Completed 2021-11-12 2021-11-29 2021-11-17 2021-11-29 2021-12-15 2021-12-20 2021-12-29 2021-12-20 2022-01-12 2022-03-12 2022-05-12 2022-10-19 ice and Public Trust nvelope Kaliua, Uvinza, Buhigwe, Kak onko, Butiama, Rorya, Itilima , Busega, Songwe, Tanganyik a, Mbogwe, Nyang’wale , Kye rwa, Misenyi, Gairo, Mvomer o, Kilom TZ-JUDICIARY TZ-271298-GO -RFB / PROCUREMENT OF FU RNITURE FOR EIGHTEEN(18) SUBORDINATE COURTS LOCA TED AT KALIUA, UVINZA, BUH Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 1,257,889.98 Signed 2022-01-03 2022-01-05 2022-01-05 2022-01-05 2022-01-26 2022-01-26 2022-02-02 2022-02-07 2022-02-16 2022-05-07 2022-05-17 IGWE, KAKONKO, BUTIAMA, R ice and Public Trust nvelope ORYA, ITILIMA, BUSEGA, SON GWE, TANGANYIKA, MBOGW E, NYANG’WALE , KYERWA, M ISENYI, GAIRO, MVOMERO, KI LOMBERO AND MKINGA-(RE ADVERTISED) TZ-JUDICIARY TZ-293025-GO Component 3: Access to Just Single Stage - One E -RFB / Procurement of ICT eq IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2022-05-04 2022-05-09 2022-06-06 2022-06-16 2022-06-30 2022-08-29 ice and Public Trust nvelope uipment for Judiciary Media C enter TZ-JUDICIARY TZ-295320-GO Component 1: Governance, -DIR / Procurement of 18 Mot Under Imple IDA / 57780 Organization and Systems D Post Direct Selection Direct 0.00 2022-05-27 2022-08-03 2022-06-01 2022-08-03 2022-06-29 2022-12-01 or vehicles to support IJCs an mentation evelopment d project operations. TZ-JUDICIARY TZ-295322-GO Component 3: Access to Just Single Stage - One E -RFB / Procurement of ICT eq IDA / 57780 Post Request for Bids Limited 393,494.83 Completed 2022-05-16 2022-05-09 2022-05-17 2022-05-10 2022-05-31 2022-05-21 2022-06-02 2022-06-02 2022-06-11 2022-06-24 2022-06-25 2022-12-11 ice and Public Trust nvelope uipment for Judiciary Media C enter TZ-JUDICIARY TZ-320431-GO Component 1: Governance, -RFQ / Procurement of Archiv Request for Quota Single Stage - One E Under Imple IDA / 57780 Organization and Systems D Post Limited 0.00 2022-10-29 2022-12-29 2022-12-24 2023-06-22 e Boxes, File Cover and Stati tions nvelope mentation evelopment onery for Decongestion Exerc ise TZ-JUDICIARY TZ-320580-GO Component 1: Governance, -DIR / PROCUREMENT OF 83 Direct - Internation IDA / 57780 Organization and Systems D Prior Direct Selection 0.00 Signed 2022-11-30 2023-01-24 2022-12-05 2023-02-01 2023-01-09 2023-03-24 2023-07-08 MOTOR VEHICLES TO SUPPO al evelopment RT THE JUDICIAL REFORM AG ENDA TZ-JUDICIARY TZ-322583-GO -RFB / PROCUREMENT OF ICT Component 1: Governance, Single Stage - One E Under Imple EQUIPMENT FOR THE ATTOR IDA / 57780 Organization and Systems D Post Request for Bids Open - National 0.00 2022-11-11 2022-11-28 2022-11-16 2022-12-22 2022-12-19 2022-12-29 2023-01-23 2023-01-31 2023-05-31 nvelope mentation NEY GENERAL'S OFFICE & DI evelopment GITIZATION OF COURT RECO RDS. TZ-JUDICIARY TZ-320428-GO Component 3: Access to Just Single Stage - One E Under Imple -RFB / Procurement of Six Mo IDA / 57780 Prior Request for Bids Open - National 0.00 2022-11-11 2023-02-03 2022-11-16 2023-02-08 2022-12-22 2023-03-31 2022-12-27 2023-06-01 2023-01-15 2023-11-11 ice and Public Trust nvelope mentation bile Court Vehicles TZ-JUDICIARY TZ-330899-GO -RFB / Supply, installation, te Component 1: Governance, Single Stage - One E Under Imple st, configuration and Commis IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-01-06 2023-01-30 2023-01-16 2023-01-31 2023-02-21 2023-03-10 2023-03-07 2023-03-25 2023-03-28 2023-07-26 nvelope mentation sioning of audio virtual recor evelopment ding equipment for eight IJCs and three high court centers. TZ-JUDICIARY TZ-338611-GO -RFB / Supply, installation , c Component 1: Governance, Single Stage - One E Under Imple onfiguration, testing and com IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-02-10 2023-02-15 2023-02-15 2023-02-15 2023-03-23 2023-03-16 2023-04-22 2023-03-17 2023-05-27 2023-08-25 nvelope mentation missioning of ICT equipment evelopment for establishment of Judiciary Virtual Situation Room. TZ-JUDICIARY TZ-340099-GO -RFB / Procurement of heavy Component 1: Governance, Single Stage - One E Under Imple duty scanners and other ICT IDA / 70580 Organization and Systems D Post Request for Bids Open - National 0.00 2023-03-08 2023-02-08 2023-03-17 2023-02-08 2023-04-22 2023-03-02 2023-05-22 2023-03-06 2023-06-26 2023-09-24 nvelope mentation equipment for digitization of evelopment court records and supporting JDU's procurement functions. TZ-JUDICIARY TZ-347075-GO -RFB / Supply, Installation, te sting, and commissioning of Component 3: Access to Just Single Stage - One E Under Imple Video Conferencing facilities IDA / 70580 Post Request for Bids Open - National 0.00 2023-03-14 2023-04-14 2023-03-19 2023-04-14 2023-04-30 2023-05-15 2023-05-30 2023-05-24 2023-07-04 2023-10-02 ice and Public Trust nvelope mentation for Prisons and other ICT facil ities to capacitate the estate management unit of the Judi ciary of Tanzania. TZ-JUDICIARY TZ-359592-GO Component 1: Governance, Request for Quota Single Stage - One E Under Imple -RFQ / Supply of protective a IDA / 57780 Organization and Systems D Post Limited 0.00 2023-05-15 2023-05-09 2023-06-15 2023-07-15 tions nvelope mentation ccessories for 18 motor vehic evelopment les. TZ-JUDICIARY TZ-364570-GO Component 1: Governance, -RFQ / Procurement of ICT eq Request for Quota Single Stage - One E Under Imple IDA / 70580 Organization and Systems D Post Limited 0.00 2023-06-11 2023-08-06 2024-02-02 uipment to support the imple tions nvelope mentation evelopment mentation and oversight of t he project. TZ-JUDICIARY TZ-9233-GO-R Component 2: Skills Develop FQ / Procurement of Furnitur Request for Quota Single Stage - One E IDA / 57780 ment, Inspection and Perfor Post Limited 58,108.56 Completed 2017-07-03 2017-11-10 2017-08-28 2017-12-14 2018-02-24 2018-04-05 e for training rooms at High tions nvelope mance Management Court DSM & Kisutu RMs Cou rt Page 3 TZ-JUDICIARY TZ-9227-GO-R FB / Supply, installation and c Component 1: Governance, Single Stage - One E ommission of Video Conferen IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-05-22 2017-09-11 2017-05-27 2017-07-08 2017-08-07 2017-09-11 2018-03-10 nvelope cing Equipment, audio visual evelopment and recording equipment for four selected courts. TZ-JUDICIARY TZ-9218-GO-R Component 3: Access to Just Single Stage - One E FB / Supply of Two (2) Mobile IDA / 57780 Prior Request for Bids Open - National 415,669.47 Completed 2017-04-13 2017-10-09 2017-04-18 2017-05-30 2017-11-15 2017-06-29 2017-12-22 2017-08-03 2018-01-19 2018-01-30 2019-02-01 ice and Public Trust nvelope Courts Van TZ-JUDICIARY TZ-9356-GO-R Component 1: Governance, FB / Procurement of IT hardw Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 235,523.50 Completed 2017-03-09 2017-01-26 2017-03-14 2017-04-25 2017-02-16 2017-05-25 2017-04-22 2017-06-29 2017-03-23 2017-12-26 2017-09-15 are and general software for nvelope evelopment Integrated Justice Centre at Mbeya. TZ-JUDICIARY TZ-585-GO-RF Component 1: Governance, Request for Quota Single Stage - One E Q / Supply of office consuma IDA / 57780 Organization and Systems D Post Limited 27,167.14 Completed 2016-08-17 2016-08-17 2016-10-12 2016-10-07 2017-04-10 2016-11-08 tions nvelope bles evelopment TZ-JUDICIARY TZ-9382-GO-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Supply of Documentary IDA / 57780 Post Limited 11,233.54 Completed 2017-03-21 2017-02-02 2017-05-16 2017-01-28 2017-11-12 2017-05-02 ice and Public Trust tions nvelope about information on Judiciar y constructions. TZ-JUDICIARY TZ-9361-GO-R FB / Procurement of furniture Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 0.00 Canceled 2017-06-13 2017-06-18 2017-07-30 2017-08-29 2017-10-03 2018-04-01 for registries & Mbeya Integr ice and Public Trust nvelope ated Justice Centre. TZ-JUDICIARY TZ-9237-GO-R Component 1: Governance, FB / Procurement of training I Single Stage - One E IDA / 57780 Organization and Systems D Post Request for Bids Open - National 0.00 Canceled 2017-03-28 2017-04-02 2017-05-14 2017-06-13 2017-07-18 2018-01-14 T facilities for High Court DS nvelope evelopment M & Kisutu RMs Court. TZ-JUDICIARY TZ-9364-GO-R Component 1: Governance, FQ / Procurement of IT hardw Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 78,159.26 Completed 2017-03-20 2017-03-22 2017-05-15 2017-05-04 2017-11-11 2017-06-30 are and general software for tions nvelope evelopment a medium size Integrated Jus tice Centre at Kibaha TZ-JUDICIARY TZ-9239-GO-R FB / Procurement of standb Component 3: Access to Just Single Stage - One E IDA / 57780 Post Request for Bids Open - National 133,805.01 Completed 2017-04-28 2017-08-02 2017-05-03 2017-06-14 2017-09-19 2017-07-14 2017-10-03 2017-08-18 2017-11-23 2018-02-14 2018-06-19 y generators for High Court ice and Public Trust nvelope DSM, JDU & Kisutu RMs Court TZ-JUDICIARY TZ-9222-GO-R Component 1: Governance, Single Stage - One E FB / Installation and partition IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-04-26 2017-05-01 2017-06-12 2017-07-12 2017-08-16 2018-02-12 nvelope of pre fabrication storage for evelopment selected courts. TZ-JUDICIARY TZ-9389-GO-R Component 1: Governance, FB / Supply of LAN materials, Single Stage - One E IDA / 57780 Organization and Systems D Prior Request for Bids Open - National 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-01-24 2018-02-28 2018-08-27 installation and commission i nvelope evelopment n High courts, Resident and d istrict courts. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-39836-NC- RFB / Provision of Service for Component 3: Access to Just Single Stage - One E Design, Editing and Printing IDA / 57780 Prior Request for Bids Open - National 0.00 Canceled 2017-12-15 2017-12-08 2017-12-20 2018-01-17 2018-01-15 2018-02-16 2018-03-05 2018-03-23 2018-09-19 ice and Public Trust nvelope of Various Legal Documents under Framework Contract. TZ-JUDICIARY TZ-52317-NC- RFQ / Provision of event man Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 93,400.36 Completed 2018-03-13 2018-03-23 2018-05-08 2018-05-02 2018-11-04 2018-06-11 agement, documentary and li ice and Public Trust tions nvelope ve coverage services for law week. TZ-JUDICIARY TZ-55449-NC- RFQ / Production of awarenes Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 53,002.21 Completed 2018-04-01 2018-03-19 2018-05-27 2018-05-03 2018-11-23 2018-05-18 s program of ongoing judiciar ice and Public Trust tions nvelope y reforms to the public. TZ-JUDICIARY TZ-67402-NC- RFQ / Provision of event man Component 3: Access to Just Request for Quota Single Stage - One E agement service and printing IDA / 57780 Post Limited 19,723.02 Completed 2018-06-25 2018-06-22 2018-07-07 2018-07-13 2019-01-03 2018-07-23 ice and Public Trust tions nvelope of various exhibition material s for sabasaba 2018. TZ-JUDICIARY TZ-91933-NC- RFQ / Provision of Event Man Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 97,646.03 Completed 2018-12-22 2019-01-03 2019-01-27 2019-01-29 2019-07-26 2019-03-28 agement and Printing Service ice and Public Trust tions nvelope s for Law Week 2019. TZ-JUDICIARY TZ-122947-NC -RFQ / Provision of event ma Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 23,220.09 Completed 2019-07-21 2019-06-03 2019-08-10 2019-06-25 2019-08-24 2019-12-03 nagement service and printin ice and Public Trust tions nvelope g of various exhibition materi als TZ-JUDICIARY TZ-146943-NC -RFQ / Provision of printing s Component 2: Skills Develop Request for Quota Single Stage - One E ervice for guideline manuals IDA / 57780 ment, Inspection and Perfor Post Limited 12,051.60 Completed 2019-12-13 2019-12-02 2020-02-07 2020-01-28 2020-08-05 2020-03-14 tions nvelope for Judicial Ethics Committee, mance Management Judiciary training policy and t raining programs. TZ-JUDICIARY TZ-151993-NC -RFQ / Provision of Event Man Component 3: Access to Just Request for Quota Single Stage - One E agement: Hiring of Tents, Ch IDA / 57780 Post Limited 82,237.59 Completed 2020-01-15 2019-12-06 2020-03-11 2020-01-28 2020-09-07 2020-03-18 ice and Public Trust tions nvelope airs, Tables, Mobile Toilet an d Printing Services for Law W eek 2020 TZ-JUDICIARY TZ-159179-NC -RFB / ONLINE PUBLICATION OF COURT DECISIONS (REPO Component 1: Governance, Single Stage - One E RTED AND UNREPORTED LA IDA / 57780 Organization and Systems D Post Request for Bids Open - National 335,025.26 Completed 2020-02-23 2020-02-18 2020-02-28 2020-03-16 2020-04-10 2020-04-16 2020-05-10 2020-04-26 2020-06-14 2020-06-07 2020-12-11 2022-04-30 nvelope W REPORTS), PRINTING OF L evelopment AW REPORTS AND INDEX OF LEGISLATION AND SUB LEGIS LATION FROM THE YEAR 196 1-2020 Page 4 TZ-JUDICIARY TZ-180775-NC Component 1: Governance, -RFQ / PROCUREMENT OF SE Request for Quota Single Stage - One E IDA / 57780 Organization and Systems D Post Limited 98,517.15 Completed 2020-07-08 2020-07-08 2020-08-10 2020-09-23 2020-11-08 2021-03-20 RVICE FOR EDITING, DESIGN tions nvelope evelopment AND PRINTING OF VARIOUS J UDICIARY DOCUMENTS. TZ-JUDICIARY TZ-298032-NC -RFQ / Provision of Non-Cons Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 16,353.54 Signed 2022-06-10 2022-06-05 2022-07-08 2022-07-15 2022-07-22 ultancy service-Filming and d ice and Public Trust tions nvelope eveloping documentaries abo ut project activities TZ-JUDICIARY TZ-325875-NC -RFQ / PROVISION OF EVENT S MANAGEMENT SERVICES (H IRING TENTS, TABLE, CHAIRS , GENERATORS, PA SYSTEM, Component 3: Access to Just Request for Quota Single Stage - One E Under Imple IDA / 70580 Post Limited 0.00 2022-11-23 2022-11-28 2022-12-21 2023-02-19 CARPET,MOBILE TOILET, DEC ice and Public Trust tions nvelope mentation ORATION, EXHIBITION BOOT H, MARQUEE, AND SUPPLY O F PROMOTIONAL MATERIALS) FOR OPENING CEREMONY AN D 6 DAYS LAW WEEK 2023 TZ-JUDICIARY TZ-9393-NC-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Printing and supply of m IDA / 57780 Post Limited 80,911.34 Completed 2017-03-14 2017-01-02 2017-05-09 2017-01-28 2017-11-05 2017-03-28 ice and Public Trust tions nvelope aterials for Law week. TZ-JUDICIARY TZ-9397-NC-R FQ / Draw printing and fixing Component 3: Access to Just Request for Quota Single Stage - One E IDA / 57780 Post Limited 0.00 Canceled 2017-03-28 2017-05-23 2017-11-19 of Signs / display boards for s ice and Public Trust tions nvelope elected court buildings. TZ-JUDICIARY TZ-9395-NC-R Component 3: Access to Just Request for Quota Single Stage - One E FQ / Design and printing of Ju IDA / 57780 Post Limited 63,673.97 Completed 2017-03-14 2016-12-28 2017-05-09 2017-01-24 2017-11-05 2017-03-23 ice and Public Trust tions nvelope diciary Calendar and diaries TZ-JUDICIARY TZ-9392-NC-R Component 3: Access to Just Single Stage - One E FB / Printing of different mat IDA / 57780 Prior Request for Bids Open - National 0.00 Canceled 2017-04-28 2017-12-08 2017-05-03 2017-06-14 2017-07-14 2017-08-18 2018-02-14 ice and Public Trust nvelope erials( Framework Contract) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-9448-CS-Q CBS / Consultancy for design Component 1: Governance, Quality And Cost- and supervision of LAN instal IDA / 57780 Organization and Systems D Prior Open - National 0.00 Canceled 2017-04-25 2017-10-09 2017-05-16 2017-12-08 2017-06-29 2018-02-26 2017-07-27 2018-03-30 2017-08-26 2018-05-21 2017-09-30 2017-11-04 2018-11-04 Based Selection lation in Selected High Court, evelopment Resident and District Courts TZ-JUDICIARY TZ-44715-CS- QCBS / CONSULTANCY SERVI CES FOR FEASIBILITY STUDY/I Component 1: Governance, Quality And Cost- Open - Internationa MPLEMENTATION PLAN/PROC IDA / 57780 Organization and Systems D Prior 513,542.79 Completed 2018-01-26 2018-02-16 2018-01-22 2018-04-01 2018-03-29 2018-04-29 2018-04-30 2018-05-29 2018-07-06 2018-07-03 2018-10-03 2018-08-07 2018-11-29 2019-08-07 2021-03-05 Based Selection l UREMENT, DEVELOPMENT AN evelopment D IMPLEMENTATION SUPPOR T FOR E-JUDICIARY SERVICES FOR THE JUDICIARY OF TANZ ANIA TZ-JUDICIARY TZ-50144-CS- QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa e 1) and (Ii) Supervise the Co IDA / 57780 Prior 452,799.20 Signed 2018-02-26 2018-03-18 2018-03-19 2018-03-27 2018-05-02 2018-06-18 2018-05-30 2018-07-27 2018-06-29 2018-10-03 2018-08-03 2018-11-27 2018-09-07 2018-12-16 2019-09-07 ice and Public Trust Based Selection l nstruction Work for the Propo sed Integrated Justice Centre (IJC) Court Buildings which wi ll be Built in Six Selected Loc ations of Mwanza, Morogoro TZ-JUDICIARY TZ-50194-CS- QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa IDA / 57780 Prior 0.00 Canceled 2018-02-26 2018-03-18 2018-03-19 2018-04-12 2018-05-02 2018-06-18 2018-05-30 2018-06-29 2018-08-03 2018-09-07 2019-09-07 e 1) and (Ii) Supervise the Co ice and Public Trust Based Selection l nstruction Work for Small Co urthouses which will be Built in at least 10 Selected Locati ons in Tanzania (Phase 2) TZ-JUDICIARY TZ-113326-CS -QCBS / Consultancy Services to (I) Update Design (Redesig n) of Existing Drawings (Phas Component 3: Access to Just Quality And Cost- Open - Internationa IDA / 57780 Prior 310,611.59 Signed 2019-05-08 2019-07-27 2019-05-22 2019-07-31 2019-07-05 2019-12-28 2019-08-02 2020-01-10 2019-08-16 2020-02-18 2019-09-06 2020-03-13 2019-09-23 2020-04-01 2020-09-22 e 1) and (II) Supervise the Co ice and Public Trust Based Selection l nstruction Work for Small Co urthouses which will be Buil t in at Least 27 Selected Loca tions in Tanzania (Phase 2). TZ-JUDICIARY TZ-291807-CS -CQS / CONSULTANCY SERVI CES FOR PREPARATION OF A N ENVIRONMENTAL AND SOC IAL IMPACT ASSESSMENT FO Component 3: Access to Just Consultant Qualifi IDA / 57780 Post Open - National 295,190.27 Signed 2022-04-26 2022-04-24 2022-05-10 2022-05-19 2022-05-25 2022-07-01 2022-06-24 2022-07-25 2022-07-15 2022-08-06 2022-10-13 R THE PROPOSED CONSTRUC ice and Public Trust cation Selection TION PROJECTS IN TANZANIA MAINLAND UNDER THE CITIZ EN-CENTRIC JUDICIAL MODER NIZATION AND JUSTICE SERVI CE DELIVERY PROJECT.(AF) TZ-JUDICIARY TZ-320375-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-26 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least Eleven (1 1) Selected Locations in Tanz ania. 1st Package TZ-JUDICIARY TZ-320379-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-01-18 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-26 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least nine (09) Selected Locations in Tanzani a. 2nd Package Page 5 TZ-JUDICIARY TZ-320381-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-21 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least nine (09) Selected Locations in Tanzani a. 3rd Package TZ-JUDICIARY TZ-320383-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement and; (II) Supervise the Constr IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least eleven (1 1) Selected Locations in Tanz ania. 4th Package TZ-JUDICIARY TZ-320388-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Under Implement IDA / 57780 Post Open - National 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection ation uction Work for the Proposed Small Courthouses which will be Built in at least four (4) Se lected Locations in Tanzania. 5th Package TZ-JUDICIARY TZ-320391-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-30 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-06-19 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at least six (6) Sel ected Locations in Tanzania. 6th Package TZ-JUDICIARY TZ-320393-CS -QCBS / Consultancy Services to (I) Update the Design (Red esign) of Existing Drawings, Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-03-13 and; (II) Supervise the Constr ice and Public Trust Based Selection l ation uction Work for the Proposed Small Courthouses which will be Built in at Least ten (10) S elected Locations in Tanzania . 7th Package TZ-JUDICIARY TZ-320396-CS -QCBS / Consultancy Service for Supervision of Constructi on Work for the Proposed Int Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-08 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 egrated Justice Centre (IJC) C ice and Public Trust Based Selection l ation ourt Buildings which will be b uilt in four (4) Selected regio ns of Singida, Geita, Simiyu a nd Manyara. 1st Package. TZ-JUDICIARY TZ-320398-CS -QCBS / Consultancy Service for Supervision of Constructi on Work for the Proposed Int Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 egrated Justice Centre (IJC) C ice and Public Trust Based Selection l ation ourt Buildings which will be b uilt in three (3) Selected regi ons of Katavi, Songwe, and N jombe. 3rd Package. TZ-JUDICIARY TZ-320400-CS -QCBS / Consultancy Service for Supervision of Constructi Component 3: Access to Just Quality And Cost- Open - Internationa Under Implement on Work for the Proposed Int IDA / 57780 Post 0.00 2022-10-21 2022-10-20 2022-11-04 2022-11-29 2022-11-14 2023-02-09 2022-12-20 2023-03-24 2022-12-25 2023-03-31 2023-01-04 2023-01-23 2025-05-12 ice and Public Trust Based Selection l ation egrated Justice Centre (IJC) C ourt Buildings which will be b uilt in Two (2) Selected regio ns of Lindi and Pwani. 2nd Pa ckage TZ-JUDICIARY TZ-365265-CS -QCBS / Consultancy services Component 1: Governance, Quality And Cost- for conducting impact assess IDA / 70580 Organization and Systems D Post Open - National 0.00 Under Review 2023-06-23 2023-07-14 2023-07-28 2023-09-02 2023-09-09 2023-09-30 2023-10-21 2024-02-18 Based Selection ments on simplified laws and evelopment rules of procedure. TZ-JUDICIARY TZ-9183-CS-C QS / Consultancy service to c onduct environmental and so Component 3: Access to Just Consultant Qualifi IDA / 57780 Post Open - National 110,103.09 Completed 2017-03-08 2016-09-06 2017-03-29 2017-05-12 2016-10-25 2017-06-11 2017-02-09 2017-07-16 2017-03-10 2018-01-12 2018-04-27 cial impact assessments for t ice and Public Trust cation Selection he Citizen-Centric Judicial Mo dernization and Justice Servic e Delivery Project. TZ-JUDICIARY TZ-9399-CS-C Component 2: Skills Develop QS / Consultancy service to D Consultant Qualifi IDA / 57780 ment, Inspection and Perfor Post Open - National 0.00 Canceled 2017-07-17 2017-08-07 2017-09-20 2017-10-20 2017-11-24 2018-05-23 evelop continuous training pr cation Selection mance Management ogram and facilitate legal trai ning TZ-JUDICIARY TZ-9438-CS-Q Component 1: Governance, CBS / Consultancy Services t Quality And Cost- IDA / 57780 Organization and Systems D Prior Open - National 0.00 Canceled 2017-05-10 2017-05-31 2017-07-14 2017-08-11 2017-09-10 2017-10-15 2017-11-19 2018-11-19 o design and introduce E-jud Based Selection evelopment gment, e-payment & E- notifi cation TZ-JUDICIARY TZ-9420-CS-Q Component 1: Governance, Quality And Cost- CBS / Consultancy service to IDA / 57780 Organization and Systems D Post Open - National 100,710.87 Completed 2017-04-19 2016-03-30 2017-05-10 2017-06-23 2016-12-23 2017-07-21 2017-01-30 2017-08-20 2017-03-30 2017-09-24 2017-05-04 2017-10-29 2017-06-08 2018-10-29 2019-01-31 Based Selection undertake Court mapping co evelopment untry wide INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-JUDICIARY TZ-25713-CS-I Component 1: Governance, Individual Consult NDV / Procurement Specialist IDA / 57780 Organization and Systems D Post Limited 179,040.00 Completed 2017-08-28 2017-08-28 2017-09-02 2017-08-31 2017-09-23 2017-09-06 2017-10-28 2017-09-26 2018-04-26 2020-05-20 ant Selection to support Project team evelopment TZ-JUDICIARY TZ-42554-CS-I NDV / Provision of consultanc Component 3: Access to Just Individual Consult IDA / 57780 Post Limited 67,200.00 Completed 2018-01-15 2017-11-21 2018-01-20 2018-01-23 2018-02-10 2018-02-12 2018-03-17 2018-03-29 2018-09-13 2019-03-28 y for Information and Commu ice and Public Trust ant Selection nication services Page 6 TZ-JUDICIARY TZ-42596-CS-I Component 1: Governance, NDV / Consultancy services f Individual Consult IDA / 57780 Organization and Systems D Post Limited 68,100.00 Completed 2018-01-18 2017-11-21 2018-01-23 2018-01-18 2018-02-13 2018-02-12 2018-03-20 2018-05-07 2018-09-16 2019-06-26 or preparation of Human Res ant Selection evelopment ource planning guideline for J udiciary of Tanzania. TZ-JUDICIARY TZ-42602-CS-I NDV / Provision of consultanc y services for development o Component 3: Access to Just Individual Consult IDA / 57780 Post Limited 31,581.00 Terminated 2018-01-15 2017-12-30 2018-01-20 2018-01-21 2018-02-10 2018-02-15 2018-03-17 2018-05-07 2018-09-13 f database systems for judge ice and Public Trust ant Selection ment, Advocates and Court B rokers and database for proje ct M & E tools based on BRN. TZ-JUDICIARY TZ-9406-CS-C DS / Consultancy service for supervision of the constructio Component 3: Access to Just IDA / 57780 Prior Direct Selection Direct 0.00 Canceled 2017-04-02 2017-04-12 2017-06-16 2017-12-13 n of ten (10) courthouses for ice and Public Trust subordinate court Primary Co urt and training room at Kisu tu RMs Court. TZ-JUDICIARY TZ-54811-CS-I Component 1: Governance, NDV / Individual Consultancy Individual Consult IDA / 57780 Organization and Systems D Post Limited 22,980.00 Completed 2018-03-26 2018-03-26 2018-03-31 2018-07-02 2018-04-21 2018-08-21 2018-05-26 2018-11-07 2018-11-22 2019-10-04 service for establishment an ant Selection evelopment d development of a compute rized e-Library system TZ-JUDICIARY TZ-138788-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 66,998.08 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-21 2020-01-25 2020-06-18 2022-03-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN M WANZA, Plot 768 Block. A at North Buswelu. TZ-JUDICIARY TZ-140323-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 31,688.28 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2020-01-04 2020-01-25 2020-07-02 2021-02-15 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN M OROGORO,, Plot 430 Block. G at Kihonda. TZ-JUDICIARY TZ-140325-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 47,647.74 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-07 2020-01-25 2020-06-04 2021-09-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN AR USHA, Plot No 123. Block I Sit uated at Corridor I in Arusha City. TZ-JUDICIARY TZ-140327-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 46,979.73 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-21 2020-01-25 2020-06-18 2021-09-01 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN D ODOMA, Plot No. 4 Block C at NCC Link. TZ-JUDICIARY TZ-140332-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 53,505.92 Completed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-02-06 2019-12-07 2020-01-25 2020-06-04 2021-07-31 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) in DA R ES SALAAM, Plot No. 38 Blo ck No. 20 at Kinondoni Munic ipal. TZ-JUDICIARY TZ-140334-CS -INDV / CLERK OF WORKS (Co Ws) FOR SUPERVISION OF CO Component 3: Access to Just Individual Consult IDA / 57780 Post Open 48,306.60 Signed 2019-10-21 2019-10-22 2019-11-16 2020-01-17 2019-11-23 2020-01-17 2019-12-07 2020-01-25 2020-06-04 NSTRUCTION OF INTEGRATE ice and Public Trust ant Selection D JUSTICE CENTRE (IJC) IN DA R ES SALAAM, Plot No 2025 B lock D at Temeke. TZ-JUDICIARY TZ-152928-CS -INDV / INDIVIDUAL EXPERT T Component 1: Governance, O CONDUCT AN ECONOMIC A Individual Consult IDA / 57780 Organization and Systems D Post Limited 8,182.54 Completed 2020-01-24 2020-02-11 2020-01-29 2020-02-12 2020-02-19 2020-02-14 2020-03-25 2020-03-04 2020-09-21 2021-01-01 NALYSIS OF CITIZEN-CENTRIC ant Selection evelopment JUDICIAL MODERNIZATION A ND JUSTICE SERVICE DELIVE RY PROJECT TZ-JUDICIARY TZ-291818-CS Component 1: Governance, -INDV / Procurement and Con Individual Consult IDA / 57780 Organization and Systems D Prior Open 67,925.09 Signed 2022-04-26 2022-05-06 2022-05-22 2022-07-09 2022-05-27 2022-08-26 2022-06-13 2022-09-02 2023-06-08 tract Management Expert to ant Selection evelopment support the project team. TZ-JUDICIARY TZ-294037-CS -INDV / INDIVIDUAL CONSULT Component 1: Governance, ANT (CIVIL ENGINEER) FOR T Individual Consult IDA / 57780 Organization and Systems D Post Limited 30,875.04 Signed 2022-05-13 2022-05-15 2022-05-18 2022-06-27 2022-06-08 2022-08-24 2022-06-29 2022-09-05 2023-06-29 HE CITIZEN-CENTRIC JUDICIA ant Selection evelopment L MODERNIZATION AND JUST ICE SERVICE DELIVERY PROJE CT. TZ-JUDICIARY TZ-295323-CS -CDS / CONSULTANCY SERVI CE TO UPDATE THE DESIGN ( Component 3: Access to Just Under Implement IDA / 57780 Post Direct Selection Direct 0.00 2022-05-20 2022-05-30 2022-06-08 2022-08-25 2022-06-22 2022-08-23 REDESIGN) OF EXISTING DRA ice and Public Trust ation WINGS FOR THE PROPOSED 12 INTEGRATED JUSTICE CEN TRE (IJCs). TZ-JUDICIARY TZ-306644-CS -CDS / Consultancy service t Component 3: Access to Just Under Implement IDA / 57780 Post Direct Selection Direct - National 0.00 2022-07-31 2022-08-01 2022-08-19 2022-08-17 2022-08-31 2023-02-27 o conduct court users’ satisfa ice and Public Trust ation ction survey 2022 TZ-JUDICIARY TZ-364600-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Songea. TZ-JUDICIARY TZ-364607-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Lindi. TZ-JUDICIARY TZ-364593-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Njombe. Page 7 TZ-JUDICIARY TZ-364576-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Simiyu TZ-JUDICIARY TZ-364587-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Katavi TZ-JUDICIARY TZ-364590-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Songwe TZ-JUDICIARY TZ-364605-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Moshi. TZ-JUDICIARY TZ-364583-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of i ntegrated justice centre (IJC) in Pemba. TZ-JUDICIARY TZ-364597-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Mtwara TZ-JUDICIARY TZ-364602-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Pwani. TZ-JUDICIARY TZ-364604-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Tanga. TZ-JUDICIARY TZ-364581-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of I ntegrated Justice Centre (IJC) in Geita. TZ-JUDICIARY TZ-364606-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Pending Impleme Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection ntation pervision of construction of t he Integrated Justice Centre ( IJC) in Manyara. TZ-JUDICIARY TZ-364574-CS -INDV / Individual Consultant- Component 3: Access to Just Individual Consult Clerk of Works (CoWs) for su IDA / 70580 Post Open - National 0.00 Under Review 2023-06-11 2023-07-30 2023-08-20 2023-09-10 2024-09-09 ice and Public Trust ant Selection pervision of construction of i ntegrated justice centre (IJC) in Singida TZ-JUDICIARY TZ-9441-CS-IN DV / Consultancy to review ju Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-04-24 2017-06-12 2017-07-03 2017-08-07 2018-02-03 stice chain, identify gaps in t ice and Public Trust ant Selection erms of policy, strategy, refo rm or performance TZ-JUDICIARY TZ-9445-CS-IN Component 3: Access to Just Individual Consult DV / Consultancy to prepare IDA / 57780 Post Open 0.00 Canceled 2017-04-24 2017-06-12 2017-07-03 2017-08-07 2018-02-03 ice and Public Trust ant Selection special program on legal aid with MoCLA TZ-JUDICIARY TZ-9410-CS-C Component 3: Access to Just DS / Consultancy service for IDA / 57780 Post Direct Selection Direct 121,856.63 Completed 2017-03-29 2019-01-18 2017-04-08 2019-04-17 2017-06-12 2019-06-27 2017-12-09 2019-09-27 ice and Public Trust Court User Survey. TZ-JUDICIARY TZ-9433-CS-IN Component 1: Governance, Individual Consult DV / Procurement of IT Speci IDA / 57780 Organization and Systems D Post Open 0.00 Canceled 2017-04-17 2017-06-05 2017-06-26 2017-07-31 2018-01-27 ant Selection alist to support Project team evelopment TZ-JUDICIARY TZ-9422-CS-IN Component 1: Governance, Individual Consult DV / Procurement Specialist t IDA / 57780 Organization and Systems D Post Open 0.00 Canceled 2017-03-09 2017-02-02 2017-04-27 2017-05-11 2017-05-18 2017-06-22 2017-12-19 ant Selection o Support Project Team evelopment TZ-JUDICIARY TZ-9431-CS-IN DV / Consultancy service to s Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-05-12 2017-06-30 2017-07-21 2017-08-25 2018-02-21 upport the development of A ice and Public Trust ant Selection DR and backlog reduction pr ogram TZ-JUDICIARY TZ-9440-CS-IN DV / Consultancy Services to Component 3: Access to Just Individual Consult IDA / 57780 Post Open 0.00 Canceled 2017-07-18 2017-09-05 2017-09-26 2017-10-31 2018-04-29 introduce Online interactive c ice and Public Trust ant Selection omplaints platform Page 8 PROCUREMENT PLAN (Textual Part) Project information: Proyecto de Respuesta de El Salvador ante el COVID 19 - P173872 Project Implementation agency: Ministerio de Salud Date of the Procurement Plan: 27 de Enero de 2021 Period covered by this Procurement Plan: Enero 2021 – Diciembre 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. PROCUREMENT El Salvador : El Salvador COVID-19 Emergency Response Project PLAN General Information Country: El Salvador 2021-06-10 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173872 GPN Date: 2022-01-24 Project Name: El Salvador COVID-19 Emergency Response Project Loan / Credit No: IBRD / 91000, IBRD / 92290, IBRD / 94290 Health Ministry Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned RECOVID-4-RFB-GO / Equipo, Component 1: Emergency C Open - Internationa Single Stage - One E 2022-02-1 cristalería, insumos y mobilia IBRD / 91000 OVID-19 response to preven Post Request for Bids 914,805.00 0.00 Canceled 2021-03-22 2021-04-15 2021-05-31 2021-07-20 2021-08-19 l nvelope 5 rio para Laboratorio de Biolo tion, detection and treatmen gía Molecular t RECOVID-63-RFQ-CW / Adec Component 1: Emergency C uación de infraestructura par Request for Quota OVID-19 response to preven Request for Quota Single Stage - One E 2022-09-2 a la sustitución del sistema d IBRD / 92290 Post Open - National tions (Non Bank-S 52,830.00 0.00 Signed 2022-04-18 2022-05-26 2022-06-27 tion, detection and treatmen tions nvelope 5 e generación de vapor Hospit PD) t al Nueva Concepción, Chalat enango RECOVID-53-RFB-CW / Remo delación y readecuación de o Component 1: Emergency C Request for Bids - bras eléctricas y electromecá OVID-19 response to preven Single Stage - One E Small Works SPD Pending Imp 2023-04-2 nicas de las instalaciones del IBRD / 92290 Post Request for Bids Open - National 3,900,000.00 0.00 2022-04-12 2022-04-15 2022-05-15 2022-06-14 2022-07-19 tion, detection and treatmen nvelope (1 envelope proce lementation 5 Almacén Regional de Salud d t ss) el área Metropolitana de San Salvador en el Centro Nacion al de Biológicos RECOVID-138-RFB-CW / Ade Component 1: Emergency C Request for Bids - cuación de Infraestructura pa OVID-19 response to preven Single Stage - One E Small Works SPD Under Imple 2023-06-2 IBRD / 92290 Post Request for Bids Open - National 186,040.00 0.00 2022-10-31 2023-01-25 2022-11-05 2023-03-08 2022-11-25 2023-03-07 2022-12-15 2023-05-18 2022-12-29 ra la Instalación de Cuarto Frí tion, detection and treatmen nvelope (1 envelope proce mentation 7 o de la Región Paracentral de t ss) Salud del MINSAL RECOVID-96-RFB-CW / Remo delación y readecuación de o Component 1: Emergency C Request for Bids - bras eléctricas y electromecá OVID-19 response to preven Open - Internationa Single Stage - One E Works (without pr 2023-11-1 nicas de las instalaciones del IBRD / 92290 Post Request for Bids 3,650,000.00 0.00 Canceled 2022-10-28 2022-11-02 2022-12-02 2022-12-30 2023-02-03 tion, detection and treatmen l nvelope equalification) SP 0 Almacén Regional de Salud d t D el Área Metropolitana de San Salvador en el Centro Nacion al de Biológicos. RECOVID-147-DIR-CW / Rem odelación y readecuación de Component 1: Emergency C obras eléctricas y electromec OVID-19 response to preven Other (with field f Under Imple 2023-11-0 ánicas de las instalaciones d IBRD / 92290 Post Direct Selection Direct - National 3,650,000.00 0.00 2022-12-09 2022-12-13 2022-12-14 2023-01-09 2023-01-12 tion, detection and treatmen or explanation) mentation 8 el Almacén Regional de Salu t d del Área Metropolitana de San Salvador en el Centro Na cional de Biológicos. RECOVID-159-RFB-CW / Rea Component 1: Emergency C decuación y Ampliación Unid OVID-19 response to preven Single Stage - One E Other (with field f 2023-12-0 IBRD / 92290 Post Request for Bids Open - National 833,267.69 0.00 Canceled 2023-01-20 2023-03-23 2023-01-25 2023-03-23 2023-02-24 2023-03-16 2023-04-11 ad de Pediatría Hospital Naci tion, detection and treatmen nvelope or explanation) 7 onal Zacamil, Dr. Juan José F t ernández RECOVID-175-RFB-CW / Rea Component 1: Emergency C Request for Bids - decuación y Ampliación Unid OVID-19 response to preven Single Stage - One E Small Works SPD Under Imple 2024-05-0 IBRD / 92290 Post Request for Bids Open - National 1,100,000.00 0.00 2023-06-02 2023-06-21 2023-06-07 2023-06-22 2023-07-07 2023-08-06 2023-09-04 ad de Pediatría Hospital Naci tion, detection and treatmen nvelope (1 envelope proce mentation 1 onal Zacamil, Dr. Juan José F t ss) ernández RECOVID-178-RFB-CW / Amp Component 1: Emergency C Request for Bids - liación de las áreas de Labor OVID-19 response to preven Single Stage - One E Small Works SPD Pending Imp 2024-01-2 atorios Clínicos de las Unidad IBRD / 92290 Post Request for Bids Open - National 150,000.00 0.00 2023-06-16 2023-06-21 2023-07-21 2023-08-18 2023-09-22 tion, detection and treatmen nvelope (1 envelope proce lementation 0 es de Salud de Dulce Nombre t ss) de María, Chalatenango y Ciu dad Barrios, San Miguel RECOVID-183-RFB-CW / Mejo Component 1: Emergency C Request for Bids - ras de la Unidad de Salud de OVID-19 response to preven Single Stage - One E Small Works SPD Pending Imp 2024-04-1 El Triunfo, Usulután a través IBRD / 92290 Post Request for Bids Open - National 235,000.00 0.00 2023-08-07 2023-08-12 2023-08-15 2023-09-14 2023-10-19 tion, detection and treatmen nvelope (1 envelope proce lementation 6 de la implementación del áre t ss) a de Laboratorio Clínico. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RECOVID-1-RFB-GO / Sumini Component 1: Emergency C stro, instalación y puesta en OVID-19 response to preven Open - Internationa Single Stage - One E marcha de equipos de unida IBRD / 91000 Prior Request for Bids 7,131,425.00 0.00 Signed 2021-08-23 2021-12-15 2021-09-13 2021-12-20 2021-10-28 2022-03-15 2021-11-27 2023-01-13 2022-01-25 2022-07-24 tion, detection and treatmen l nvelope d de radiología e imágenes di t agnósticas para el Hospital N acional El Salvador. RECOVID-10-RFQ-GO / Equip Component 1: Emergency C os de seguridad ocupacional OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 91000 Post Open - National 22,400.00 0.00 2021-09-17 2021-11-28 2022-02-26 para personal elaborando en tion, detection and treatmen tions nvelope ementation áreas de riesgo del Hospital t El Salvador RECOVID-5-RFQ-GO / Equipo Component 1: Emergency C Request for Quota Single Stage - One E y mobiliario clínico para Hosp IBRD / 91000 OVID-19 response to preven Post Open - National 62,625.00 0.00 Canceled 2021-10-27 2022-01-26 2022-04-26 tions nvelope ital El Salvador tion, detection and treatmen t Component 1: Emergency C RECOVID-6-RFQ-GO / Mobilia Request for Quota Single Stage - One E IBRD / 91000 OVID-19 response to preven Post Open - National 138,750.00 0.00 Canceled 2021-10-12 2022-01-12 2022-04-12 rio para Hospital El Salvador tions nvelope tion, detection and treatmen t RECOVID-27-RFQ-GO / Insu Component 2. Project Manag Request for Quota Single Stage - One E mos informáticos para funcio IBRD / 91000 Post Open - National 1,659.00 1,232.88 Signed 2021-08-06 2021-09-27 2021-10-12 2021-10-12 ement and Monitoring tions nvelope namiento de la UGP RECOVID-11-RFQ-GO / Equip Component 1: Emergency C Request for Quota Single Stage - One E o informático y mobiliario par IBRD / 91000 OVID-19 response to preven Post Open - National 8,000.00 8,556.51 Signed 2021-08-16 2021-10-05 2021-11-17 2021-11-19 tions nvelope a ejecución del proyecto tion, detection and treatmen t Page 1 RECOVID-7-RFQ-GO / Equipo Component 1: Emergency C s para el fortalecimiento de e OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl spacio de almacén para insu IBRD / 91000 Post Open - National 25,000.00 0.00 2022-01-25 2022-04-14 2022-05-29 tion, detection and treatmen tions nvelope ementation mos y medicamentos dentro t del Hospital El Salvador RECOVID-8-RFQ-GO / Equipo Component 1: Emergency C s para el fortalecimiento de e OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 91000 Post Open - National 30,000.00 0.00 2022-01-17 2022-04-04 2022-07-03 spacio de almacenamiento d tion, detection and treatmen tions nvelope ementation e desechos bioinfecciosos t RECOVID-9-RFQ-GO / Mobilia Component 1: Emergency C Request for Quota Single Stage - One E Pending Impl rio para las áreas de socializa IBRD / 91000 OVID-19 response to preven Post Open - National 25,000.00 0.00 2021-11-04 2022-01-11 2022-02-25 tions nvelope ementation ción y alimentación del perso tion, detection and treatmen nal t RECOVID-3-RFB-GO / Sumini Component 1: Emergency C stro, instalación y puesta en f OVID-19 response to preven Open - Internationa Single Stage - One E uncionamiento de equipos pa IBRD / 91000 Prior Request for Bids 2,442,500.00 1,296,504.90 Signed 2021-08-23 2021-12-15 2021-09-13 2021-12-20 2021-10-28 2022-03-03 2021-11-27 2022-06-15 2022-01-08 2022-09-03 2022-07-07 tion, detection and treatmen l nvelope ra la central de esterilización t del Hospital Nacional El Salva dor RECOVID-2-RFB-GO / Sumini Component 1: Emergency C stro, instalación y puesta en f OVID-19 response to preven Open - Internationa Single Stage - One E Under Imple uncionamiento de equipos de IBRD / 91000 Prior Request for Bids 2,535,000.00 0.00 2021-08-23 2022-03-10 2021-09-13 2022-03-17 2021-10-28 2022-05-30 2021-11-27 2022-10-25 2022-01-25 2022-07-24 tion, detection and treatmen l nvelope mentation la sala de angiógrafo y quiróf t ano general del Hospital Naci onal El Salvador RECOVID-32-DIR-GO / Adqui Component 1: Emergency C sición de medicamentos (Toc IBRD / 91000 OVID-19 response to preven Post Direct Selection Direct 1,216,656.00 1,216,656.00 Completed 2020-06-24 2020-06-24 2020-06-26 2020-06-26 2020-06-27 2020-06-28 2020-07-20 2020-07-21 ilizumab) tion, detection and treatmen t RECOVID-33-DIR-GO / Adqui Component 1: Emergency C sición de oxígeno medicinal lí IBRD / 91000 OVID-19 response to preven Post Direct Selection Direct 99,996.00 99,996.49 Completed 2020-07-31 2020-07-30 2020-07-31 2020-07-31 2020-08-01 2020-08-02 2020-09-04 2020-08-12 quido para el Hospital Nacion tion, detection and treatmen al El Salvador t RECOVID-34-DIR-GO / Adqui Component 1: Emergency C sición de medicamentos (Toc IBRD / 91000 OVID-19 response to preven Post Direct Selection Direct 1,569,568.00 1,569,568.00 Completed 2020-08-06 2020-08-06 2020-08-06 2020-08-06 2020-08-07 2020-08-08 2020-09-06 2020-08-22 ilizumab) tion, detection and treatmen t RECOVID-35-DIR-GO / Adqui Component 1: Emergency C sición de reactivos de laborat OVID-19 response to preven orio (set de extracción para IBRD / 91000 Post Direct Selection Direct 1,043,455.00 1,043,455.04 Completed 2020-08-07 2020-08-07 2020-08-12 2020-08-12 2020-08-13 2020-08-14 2020-11-11 2020-09-06 tion, detection and treatmen RNA/DNA viral y set de ampli t ficación de ácidos nucleicos RECOVID-36-DIR-GO / Adqui Component 1: Emergency C sición de oxígeno medicinal lí IBRD / 91000 OVID-19 response to preven Post Direct Selection Direct 99,996.00 99,996.49 Completed 2020-08-12 2020-08-13 2020-08-12 2020-08-12 2020-08-13 2020-08-14 2020-08-22 2020-08-23 quido para el Hospital Nacion tion, detection and treatmen al El Salvador t RECOVID-28-RFB-GO / Sumi Component 1: Emergency C nistro, instalación y puesta e OVID-19 response to preven Open - Internationa Single Stage - One E n marcha de equipo de Labor IBRD / 91000 Post Request for Bids 1,172,105.00 0.00 Signed 2022-01-07 2022-03-22 2022-01-14 2022-05-11 2022-02-28 2022-06-24 2022-03-30 2022-12-13 2022-05-04 2022-10-31 tion, detection and treatmen l nvelope atorio de Biología Molecular t para Hospital Nacional El Sal vador RECOVID-37-RFQ-GO / Equip o informático y audio para el Component 2. Project Manag Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 69,591.00 21,678.30 Signed 2022-01-26 2022-03-24 2022-06-23 2022-06-22 fortalecimiento del área de p ement and Monitoring tions nvelope romoción de la salud. RECOVID-38-RFQ-GO / Adqui Component 2. Project Manag Request for Quota Single Stage - One E sición de mobiliario de oficin IBRD / 92290 Post Open - National 20,670.00 9,596.11 Signed 2022-01-31 2022-03-28 2022-02-24 2022-04-27 ement and Monitoring tions nvelope a para dependencias del MIN SAL y UGPPI RECOVID-39-RFQ-GO / Papel Component 1: Emergency C ería para el fortalecimiento al OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 7,279.00 5,266.39 Signed 2022-02-01 2022-03-22 2022-05-16 2022-04-21 componente técnico y proces tion, detection and treatmen tions nvelope os en promoción de la salud t RECOVID-40-RFQ-GO / Mobili Component 1: Emergency C ario para el fortalecimiento al OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 23,130.00 16,519.00 Signed 2022-01-24 2022-04-07 2022-07-19 2022-06-06 componente técnico y proces tion, detection and treatmen tions nvelope os de promoción de la salud t RECOVID-49-DIR-GO / Vacun Component 1: Emergency C a contra SARS COV-2 inactiva IBRD / 92290 OVID-19 response to preven Prior Direct Selection Direct 20,000,000.00 0.00 Canceled 2021-04-23 2021-12-22 2021-04-23 2021-12-22 2021-04-26 2021-07-01 da CORONAVAC suspensión i tion, detection and treatmen nyectable t RECOVID-49-DIR-GO-2 / Vac Component 1: Emergency C una contra SARS COV-2 inact IBRD / 92290 OVID-19 response to preven Post Direct Selection Direct 20,000,000.00 30,000,000.00 Completed 2021-04-23 2021-12-03 2021-04-23 2021-12-10 2021-04-26 2021-03-11 2021-07-01 2021-07-02 ivada CORONAVAC suspensió tion, detection and treatmen n inyectable t Component 1: Emergency C RECOVID-54-DIR-GO / Equip IBRD / 91000 OVID-19 response to preven Post Direct Selection Direct 1,499,250.00 1,499,250.00 Completed 2020-07-06 2020-07-06 2020-07-07 2020-07-07 2020-07-08 2020-07-09 2020-09-06 2020-09-08 o de alto flujo de oxigeno tion, detection and treatmen t RECOVID-55-DIR-GO / Adqui Component 1: Emergency C sición de materiales de aseo OVID-19 response to preven personal para Regiones de S IBRD / 91000 Post Direct Selection Direct 102,812.00 115,711.88 Completed 2020-02-01 2020-02-03 2020-02-07 2020-02-07 2020-03-04 2020-03-05 2020-11-09 2020-03-27 tion, detection and treatmen alud y Hospitales Nacionales t para atender emergencia del Coronavirus. Component 1: Emergency C RECOVID-56-RFB-GO / Insum Single Stage - One E IBRD / 92290 OVID-19 response to preven Post Request for Bids Open - National 200,000.00 181,010.00 Signed 2022-03-31 2022-03-23 2022-04-05 2022-05-05 2022-06-19 2022-05-25 2022-06-08 2022-06-29 2022-07-17 2022-09-27 2022-08-20 os médicos de bioseguridad nvelope tion, detection and treatmen t RECOVID-57-RFB-GO / Sumi Component 1: Emergency C nistro de emisor Rayos X par OVID-19 response to preven IBRD / 92290 Post Direct Selection Direct 226,050.00 0.00 Canceled 2022-03-04 2022-03-11 2022-04-09 2022-05-09 a equipo de Tomografía para tion, detection and treatmen Hospitales Nacionales. t RECOVID-61-RFB-GO / Sumi nistro, instalación y puesta e n marcha de sistemas de: ex Component 1: Emergency C tracción de aire y aire acondi OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 329,509.00 0.00 Canceled 2022-04-04 2022-04-11 2022-05-11 2022-06-10 2022-07-08 2023-01-04 cionado de aplicación especi tion, detection and treatmen nvelope al (100% aire exterior) y recir t culado, para Hospital Nacion al General Zacamil "Dr. Juan J osé Fernández". Page 2 RECOVID-62-RFB-GO / Sumi Component 1: Emergency C nistro, instalación y puesta e OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 606,849.00 0.00 Signed 2022-04-11 2022-05-17 2022-04-18 2022-05-17 2022-05-18 2022-06-28 2022-06-17 2022-07-28 2022-07-22 2023-01-18 n marcha de equipo generad tion, detection and treatmen nvelope or de vapor, caldera 100 bhp t y periféricos. RECOVID-57-DIR-GO / Sumin Component 1: Emergency C istro de emisor Rayos X para IBRD / 92290 OVID-19 response to preven Post Direct Selection Direct 226,050.00 226,050.00 Signed 2022-03-28 2022-03-31 2022-04-04 2022-04-04 2022-04-25 2022-06-11 2022-05-10 equipo de Tomografía para H tion, detection and treatmen ospitales t RECOVID-65-RFQ-GO / Equip Component 1: Emergency C Request for Quota Single Stage - One E Under Imple o informático y software para IBRD / 92290 OVID-19 response to preven Post Open - National 30,000.00 0.00 2022-04-18 2022-06-06 2022-10-04 tions nvelope mentation el fortalecimiento de Epidemi tion, detection and treatmen ología MINSAL t RECOVID-66-RFQ-GO / Mater Component 1: Emergency C iales promocionales para ide OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 10,000.00 0.00 Signed 2022-04-19 2022-06-07 2022-07-07 ntificación del personal de ep tion, detection and treatmen tions nvelope idemiología de campo t RECOVID-67-RFQ-GO / Aires Component 1: Emergency C Request for Quota Single Stage - One E acondicionados para depend IBRD / 92290 OVID-19 response to preven Post Open - National 36,000.00 0.00 Canceled 2022-05-18 2022-07-13 2022-08-12 tions nvelope encias del MINSAL tion, detection and treatmen t RECOVID-68-RFQ-GO / Adqui Component 1: Emergency C sición de Mobiliario para el fo OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 6,711.00 0.00 Signed 2022-05-18 2022-07-06 2022-08-05 rtalecimiento de la Dirección tion, detection and treatmen tions nvelope de Promoción de Salud t RECOVID-69-RFQ-GO / Adqui Component 2. Project Manag Request for Quota Single Stage - One E sición de equipo de computo IBRD / 92290 Post Open - National 30,000.00 13,565.25 Signed 2022-05-13 2022-06-27 2022-07-21 2022-08-26 ement and Monitoring tions nvelope para ser utilizado en la UGP-P I RECOVID-71-RFW-GO / Insu Component 2. Project Manag Request for Quota Single Stage - One E mos Infromáticos para funcio IBRD / 92290 Post Open - National 2,000.00 0.00 Canceled 2022-05-07 2022-06-14 2022-06-29 ement and Monitoring tions nvelope namiento de UGP RECOVID-72-RFQ-NC / Contr atación de servicios de alime ntación y uso de instalacion Component 2. Project Manag Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 7,400.00 6,880.00 Signed 2022-05-16 2022-07-25 2022-07-29 2023-05-31 es para jornadas de socializa ement and Monitoring tions nvelope ción con partes interesadas, poblaciones vulnerables y for talecimiento y personal de sa lud. RECOVID-73-RFB-GO / Adqui Component 1: Emergency C sición de estantería industrial OVID-19 response to preven Single Stage - One E Pending Impl y equipo de carga para fortal IBRD / 92290 Post Request for Bids Open - National 190,000.00 0.00 2022-05-17 2022-05-23 2022-07-04 2022-08-03 2022-09-07 2023-02-04 tion, detection and treatmen nvelope ementation ecer la cadena de suministro t s con la mejora del almacén El Paraíso del MINSAL RECOVID-78-RFQ-GO / Adqui sición y Suministro de Insum Component 2. Project Manag Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 59,500.00 0.00 Signed 2022-06-20 2022-09-09 2022-08-18 2022-09-19 os para Establecimientos de ement and Monitoring tions nvelope Salud en el Marco de la Gesti ón Ambiental RECOVID-80-RFB-GO / Comp ra de frigoríficos para fortale Component 1: Emergency C cimiento de la cadena de frío OVID-19 response to preven Open - Internationa Single Stage - One E Under Imple IBRD / 92290 Post Request for Bids 1,200,000.00 0.00 2022-06-24 2023-01-10 2022-08-08 2023-01-18 2022-09-19 2023-03-02 2022-10-19 2023-06-07 2022-11-23 2023-03-23 del MINSAL para el almacena tion, detection and treatmen l nvelope mentation miento adecuado de vacunas t , con énfasis en la vacuna co ntar la COVID-19 RECOVID-81-DIR-GO / Adqui sición y Suministro de Repue stos como parte del servicio Component 1: Emergency C del mantenimiento preventiv OVID-19 response to preven o y correctivo de equipo de R IBRD / 92290 Post Direct Selection Direct 29,000.00 0.00 Signed 2022-06-24 2022-07-27 2022-07-01 2022-08-10 2022-08-05 2023-01-02 tion, detection and treatmen esonancia Magnética del Hos t pital Nacional Rosales y de la Fuente de Suministro Eléctric o UPS para el Hospital Nacion al General Neumología RECOVID-82-RFQ-GO / Adqui Component 1: Emergency C sición de Equipo informático OVID-19 response to preven Request for Quota Single Stage - One E Under Imple IBRD / 92290 Post Open - National 54,500.00 0.00 2022-07-20 2022-09-22 2022-12-21 y audio para el fortalecimient tion, detection and treatmen tions nvelope mentation o del área de promoción de l t a salud. RECOVID-41-RFB-GO / Sumi nistro, instalación y puesta e Component 1: Emergency C n marcha de planta generad OVID-19 response to preven Open - Internationa Single Stage - One E IBRD / 92290 Prior Request for Bids 5,000,000.00 0.00 Canceled 2022-01-31 2022-02-04 2022-03-21 2022-04-20 2022-06-03 2022-11-30 ora de oxígeno médico (PGO tion, detection and treatmen l nvelope M) para el sistema hospitalari t o del Ministerio de Salud de E l Salvador RECOVID-83-RFB-GO / SUMI NISTRO, INSTALACIÓN Y PUE Component 1: Emergency C STA EN FUNCIONAMIENTO DE OVID-19 response to preven Open - Internationa Single Stage - One E Under Imple IBRD / 92290 Post Request for Bids 867,100.00 0.00 2022-08-08 2022-10-04 2022-08-18 2022-10-05 2022-09-29 2022-11-15 2022-10-28 2023-01-16 2022-12-02 2023-05-01 LAVADORAS TERMODESINFE tion, detection and treatmen l nvelope mentation CTADORAS Y BAÑOS ULTRAS t ONICOS PARA HOSPITAL NAC IONAL EL SALVADOR. RECOVID-84-RFQ-GO / SUMI Component 1: Emergency C NISTRO, INSTALACIÓN Y PUE OVID-19 response to preven Request for Quota Single Stage - One E STA EN FUNCIONAMIENTO DE IBRD / 92290 Post Open - National 30,000.00 0.00 Signed 2022-08-08 2022-10-03 2023-03-02 tion, detection and treatmen tions nvelope MAQUINAS PARA CORTAR TE t LA PARA HOSPITAL NACIONA L EL SALVADOR. RECOVID-76-RFB-GO / SUMI Component 1: Emergency C NISTRO, INSTALACIÓN Y PUE OVID-19 response to preven Single Stage - One E STA EN FUNCIONAMIENTO DE IBRD / 92290 Post Request for Bids Open - National 121,500.00 0.00 Signed 2022-06-01 2022-08-29 2022-06-06 2022-10-07 2022-07-18 2022-10-07 2022-08-17 2023-01-18 2022-09-21 2022-12-20 tion, detection and treatmen nvelope EQUIPO DE ENDOSCOPIA PAR t A EL HOSPITAL NACIONAL RO SALES. RECOVID-87-RFB-GO / SUMI Component 1: Emergency C NISTRO, INSTALACIÓN Y PUE OVID-19 response to preven Open - Internationa Single Stage - One E Under Imple STA EN MARCHA DE EQUIPOS IBRD / 92290 Post Request for Bids 844,000.00 0.00 2022-09-02 2022-12-05 2022-09-19 2023-02-10 2022-10-31 2022-11-30 2023-01-04 2023-07-03 tion, detection and treatmen l nvelope mentation DE RAYOS "X" DIGITALES EN t HOSPITALES PRIORIZADOS RECOVID-88-DIR-GO / Adqui Component 1: Emergency C sición de Vacuna inactiva par OVID-19 response to preven Direct - Internation IBRD / 94290 Prior Direct Selection 15,600,000.00 35,600,000.00 Completed 2021-03-10 2022-08-15 2021-03-10 2022-08-16 2021-03-10 2021-03-11 2021-05-19 2021-05-20 a la profilaxis del SARS CoV-2 tion, detection and treatmen al SINOVAC original t Page 3 RECOVID-89-DIR-GO / Adqui Component 1: Emergency C sición de BNT 162, Vacuna A OVID-19 response to preven Direct - Internation RNm dirigida contra SARS Co IBRD / 94290 Prior Direct Selection 29,694,600.00 29,694,600.00 Completed 2021-05-07 2022-08-09 2021-05-07 2022-08-09 2021-05-25 2021-05-20 2022-03-04 2021-12-31 tion, detection and treatmen al V-2 para prevenir la infección t por COVID-19 en los seres hu manos RECOVID-90-DIR-GO / Adqui Component 1: Emergency C sición de vacuna para SARS- OVID-19 response to preven Direct - Internation IBRD / 94290 Prior Direct Selection 15,000,000.00 15,000,000.00 Completed 2021-05-07 2022-08-15 2021-05-15 2022-08-16 2021-06-17 2021-06-18 2021-07-23 2021-09-12 CoV-2 (VERO CELL) inactivad tion, detection and treatmen al a Vacuna COVID-19 (VERO C t ELL Inactivada) RECOVID-91-DIR-GO / Vacun Component 1: Emergency C Direct - Internation a contra SARS COV-2 inactiva IBRD / 94290 OVID-19 response to preven Prior Direct Selection 5,000,000.00 35,000,000.00 Completed 2021-04-23 2022-08-09 2021-04-23 2022-08-10 2021-04-26 2021-03-11 2021-07-01 2021-07-08 al da CORONAVAC suspensión i tion, detection and treatmen nyectable t RECOVID-75-RFB-GO / SUMI NISTRO, INSTALACIÓN Y PUE Component 1: Emergency C STA EN MARCHA DEL SISTEM OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 48,000.00 0.00 Canceled 2022-06-01 2022-06-06 2022-07-18 2022-08-17 2022-09-21 2023-01-19 A DE AIRE ACONDICIONADO tion, detection and treatmen nvelope Y VENTILACIÓN MECÁNICA, P t ARA EL LABORATORIO DE PA TOLOGÍA DEL HOSPITAL ROS ALES. RECOVID-92-RFQ-GO / Aires Component 1: Emergency C Request for Quota Single Stage - One E Acondicionados para depend IBRD / 92290 OVID-19 response to preven Post Open - National 9,500.00 0.00 Signed 2022-09-02 2022-11-02 2023-01-01 tions nvelope encias del MINSAL tion, detection and treatmen t RECOVID-86-RFQ-GO / SUMI Component 1: Emergency C NISTRO, INSTALACIÓN Y PUE OVID-19 response to preven Request for Quota Open - Internationa Single Stage - One E Under Imple STA EN MARCHA DE TOMOG IBRD / 92290 Post 1,350,000.00 0.00 2022-09-26 2022-11-21 2023-05-20 tion, detection and treatmen tions l nvelope mentation RAFO COMPUTARIZADO MUL t TICORTE PARA EL HOSPITAL NACIONAL DE LA MUJER RECOVID-85-RFQ-GO / SUMI NISTRO, INSTALACIÓN Y PUE STA EN MARCHA DE EQUIPOS Component 1: Emergency C DE UNIDAD DE RADIOLOGÍA OVID-19 response to preven Request for Quota Open - Internationa Single Stage - One E Under Imple IBRD / 92290 Prior 7,501,000.00 0.00 2022-09-26 2023-02-24 2022-11-21 2023-05-20 E IMÁGENES DIAGNÓSTICAS tion, detection and treatmen tions l nvelope mentation PARA EL HOSPITAL NACIONA t L ROSALES, HOSPITAL NACIO NAL ZACAMIL Y HOSPITAL NA CIONAL SAN RAFAEL RECOVID-95-RFB-GO / Sumi Component 1: Emergency C nistro, Instalación y Puesta e OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 200,000.00 0.00 Signed 2022-09-30 2022-11-24 2022-10-05 2023-01-30 2022-11-04 2023-01-12 2022-12-02 2023-02-23 2022-12-22 2023-05-21 n funcionamiento de Autocla tion, detection and treatmen nvelope ve para Hospital Nacional Sa t n Vicente RECOVID-97-RFB-GO / Adqui Component 1: Emergency C sición de estantería industrial OVID-19 response to preven Single Stage - One E Under Imple y equipo de carga para mejor IBRD / 92290 Post Request for Bids Open - National 250,000.00 0.00 2022-10-14 2022-11-28 2022-10-19 2022-12-05 2022-11-18 2023-01-04 2022-12-16 2023-02-03 2023-01-20 2023-06-19 tion, detection and treatmen nvelope mentation ar el almacenamiento en alm t acén el Paraíso del MINSAL. RECOVID-99-RFB-GO / Sumi Component 1: Emergency C nistro, Instalación y Puesta e OVID-19 response to preven Single Stage - One E Pending Impl IBRD / 92290 Post Request for Bids Open - National 100,000.00 0.00 2022-10-10 2022-10-17 2022-11-28 2022-12-28 2023-02-01 2023-08-30 n marcha de Curato Frío Regi tion, detection and treatmen nvelope ementation ón Central de Salud, Ministeri t o de Salud RECOVID-100-RFQ-GO / Aire Component 1: Emergency C s Acondicionados Dependenc OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 26,500.00 0.00 Signed 2022-11-02 2022-12-28 2023-02-11 ias del MINSAL: Dirección de tion, detection and treatmen tions nvelope Inmunizaciones y Centro Nac t ional de Biológicos RECOVID-101-RFB-GO / Sum inistro, Instalación y Puesta e Component 2. Project Manag Single Stage - One E Under Imple IBRD / 92290 Post Request for Bids Open - National 200,000.00 0.00 2022-10-31 2023-02-07 2022-11-07 2023-02-07 2022-12-19 2023-01-18 2023-02-22 2023-08-21 n Marcha de Paneles Solares ement and Monitoring nvelope mentation para Hospitales Priorizados, Ministerio de Salud RECOVID-DIR-102-GO / ADQ Component 1: Emergency C UISICIÓN DE CARRO PARA CU OVID-19 response to preven RACIONES PARA STABLECIMI IBRD / 94290 Post Direct Selection Direct - National 331,000.00 331,000.00 Signed 2021-01-12 2021-01-12 2021-03-02 2021-03-02 2021-04-06 2021-04-20 2021-10-03 tion, detection and treatmen ENTOS DE SALUD DE APLICA t CIÓN DE LA VACIUNA CONTR A COVID-19 RECOVID-DIR-103-GO / ADQ Component 1: Emergency C UISICION DE MEDICAMENTOS OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 1,867,320.00 1,867,320.00 Signed 2022-01-19 2021-11-22 2022-02-01 2022-02-01 2022-02-24 2022-03-08 2022-05-25 CASIMIRAB E INDIMIRAB PAR tion, detection and treatmen A EL TRATAMIENTO DE COVI t D 19 Component 1: Emergency C RECOVID-DIR-104-GO / ADQ IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 9,000.00 9,000.00 Completed 2021-01-11 2021-01-20 2021-02-04 2021-02-04 2021-03-10 2021-03-21 2021-12-31 2021-07-28 UISICIÓN DE EQUIPO MÉDICO tion, detection and treatmen t RECOVID-DIR-106-GO / ADQ Component 1: Emergency C UISICIÓN DE INSUMOS DE LA OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 1,685,635.84 1,685,635.84 Signed 2021-02-25 2021-03-02 2021-03-04 2021-03-04 2021-03-11 2021-03-16 2021-07-11 BORATORIO (SET DE AMPLIFI tion, detection and treatmen CACIÓN DE ÁCIDOS NUCLEIC t OS RT-PCR Y PCR) RECOVID-DIR-107-GO / ADQ Component 1: Emergency C UISICIÓN DE INSUMOS MEDIC IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 2,283,600.00 2,283,600.00 Signed 2021-03-05 2021-03-09 2021-03-22 2021-03-22 2021-04-20 2021-04-21 2021-05-31 OS (MASCARILLAS N95) tion, detection and treatmen t RECOVID-DIR-109-GO / ADQ Component 1: Emergency C UISICIÓN DE MEDICAMENTOS IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 73,730.00 73,730.00 Signed 2021-03-15 2021-03-19 2021-04-08 2021-04-08 2021-04-27 2021-04-28 2021-05-20 (ÁCIDO ACETILSALICILICO) tion, detection and treatmen t RECOVID-DIR-111-GO / ADQ UISICION DE SUMINISTROS (C Component 1: Emergency C INTAS Y CARTUCHOS PARA I OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 180,540.00 180,540.00 Signed 2021-03-18 2021-04-28 2021-05-19 2021-05-19 2021-06-15 2021-06-16 2021-12-31 MPRESORAS) PARA ESTABLE tion, detection and treatmen CIMIENTOS DE APLICACIÓN D t E LA VACUNA CONTRA EL SA RS-COVID-II RECOVID-DIR-112-GO / ADQ Component 1: Emergency C UISICIÓN DE SUMINISTROS D OVID-19 response to preven E OFICINA PARA ESTABLECIM IBRD / 94290 Post Direct Selection Direct - National 82,507.00 82,506.29 Signed 2021-03-18 2021-04-20 2021-05-21 2021-05-21 2021-06-25 2021-07-05 2021-12-31 tion, detection and treatmen IENTOS DE APLICACIÓN DE L t A VACUNA CONTRA EL SARS- COVID-II RECOVID-DIR-114-GO / ADQ Component 1: Emergency C UISICIÓN DE MOBILIARIO (CA OVID-19 response to preven NOPY) PARA ESTABLECIMIEN IBRD / 94290 Post Direct Selection Direct - National 296,510.00 296,510.00 Signed 2021-04-15 2021-04-20 2021-04-29 2021-04-29 2021-05-14 2021-05-15 2021-06-15 tion, detection and treatmen TOS DE APLICACIÓN DE LA V t ACUNA CONTRA EL SARS-CO VID-II Page 4 RECOVID-DIR-115-GO / ADQ Component 1: Emergency C UISICIÓN DE MEDICAMENTOS OVID-19 response to preven : TOCILIZUMAB 20 MG/ML CO IBRD / 94290 Post Direct Selection Direct - National 1,783,600.00 1,783,600.00 Signed 2021-04-26 2021-04-27 2021-05-20 2021-05-20 2021-07-01 2021-07-02 2021-09-20 tion, detection and treatmen NCENTRADO PARA LIQUIDO P t ARENTERAL PARA PERFUSIO N FRASCO VIAL 10 ML RECOVID-DIR-117-GO / MEDI Component 1: Emergency C O DE TRANSPORTE UNIVERS OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 177,800.00 177,800.00 Completed 2021-06-11 2021-06-23 2021-06-28 2021-06-28 2021-07-12 2021-07-22 2021-07-15 2021-09-15 AL PARA VIRUS, CON HISOPO tion, detection and treatmen INCORPORADO CAJA (50-100) t UNIDADES RECOVID-DIR-119-GO / SUMI Component 1: Emergency C NISTRO DE ALGODÓN HIDRO IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 225,990.00 225,990.00 Signed 2021-09-06 2021-09-06 2021-09-28 2021-09-28 2021-11-08 2021-11-20 2021-12-31 FILO ABSORBENTE EN LIBRA tion, detection and treatmen S t RECOVID-DIR-120-GO / ADQ Component 1: Emergency C UISICIÓN DE INSUMOS MEDIC OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 1,777,174.85 1,777,174.85 Signed 2021-09-16 2021-09-20 2021-09-27 2021-09-27 2021-11-26 2021-12-12 2021-12-31 OS PARA LA DIRECCIÓN NACI tion, detection and treatmen ONAL HOSPITALES t RECOVID-DIR-121-GO / ADQ Component 1: Emergency C UISICIÓN DE MEDICAMENTOS IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 748,587.53 748,587.61 Signed 2021-09-16 2021-09-21 2021-09-24 2021-09-24 2021-11-24 2021-12-06 2021-12-31 PARA LA DIRECCIÓN NACION tion, detection and treatmen AL HOSPITALES t RECOVID-DIR-122-GO / ADQ Component 1: Emergency C UISICIÓN DE CASIRIVIMAB E I OVID-19 response to preven MDEVIMAB 120 MG/ML CONC IBRD / 94290 Post Direct Selection Direct - National 1,867,320.00 1,867,320.00 Signed 2021-09-17 2021-09-17 2021-09-19 2021-09-14 2021-09-21 2021-09-26 2021-11-05 tion, detection and treatmen ENTRADO PARA LIQUIDO PAR t ENTERAL, FRASCO VIAL DE 6 A 20 ML SOLIDO, ORAL RECOVID-DIR-123-GO / ADQ Component 1: Emergency C UISICIÓN DE MEDICAMENTO IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 220,000.00 220,000.00 Signed 2021-10-06 2021-10-18 2021-11-29 2021-11-01 2021-12-01 2021-12-02 2021-12-31 EDOXABAN 60 MG tion, detection and treatmen t RECOVID-DIR-128-GO / OXIG Component 1: Emergency C ENO MEDICINAL PARA PACIE OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 3,919,020.00 3,919,020.00 Signed 2021-09-16 2021-09-17 2021-09-18 2021-09-18 2021-09-20 2021-09-21 2021-12-31 NTES CON COVID-19 HOSPIT tion, detection and treatmen AL NACIONAL EL SALVADOR t RECOVID-DIR-132-GO / PRO Component 1: Emergency C DUCCIÓN Y SUMINISTRO DE OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 58,375.80 0.00 Completed 2021-07-17 2021-07-23 2021-07-24 2021-07-24 2021-08-13 2021-09-01 2021-09-10 MOBILIARIO PARA ESTACION tion, detection and treatmen MOVIL DE VACUNACIÓN t RECOVID-DIR-134-GO / ADQ Component 1: Emergency C UISICION DE ACIDO ASCÓRBI IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 246,035.00 0.00 Completed 2021-11-03 2021-11-12 2021-11-17 2021-11-19 2021-12-23 2022-01-03 2022-05-20 CO PARA KIT COVID 19 (VITA tion, detection and treatmen MINA C) t RECOVID-135-RFQ-GO / ADQ UISICIÓN DE ARTÍCULOS DE L Component 2. Project Manag Request for Quota Single Stage - One E Under Imple IMPIEZA, ALIMENTACIÓN Y M IBRD / 92290 Post Open - National 2,210.00 0.00 2022-10-19 2022-12-01 2022-12-16 ement and Monitoring tions nvelope mentation ANIPULACIÓN DE ALIMENTOS PARA FUNCIONAMIENTO DE L A UGPPI RECOVID-64-RFB-GO / Sumi Component 1: Emergency C nistro, instalación y puesta e OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 315,000.00 0.00 Canceled 2022-04-19 2022-06-15 2022-04-26 2022-05-26 2022-07-27 2022-06-25 2022-07-30 2023-02-25 n marcha de cuarto frio Regi tion, detection and treatmen nvelope ón Paracentral de Salud, Mini t sterio de Salud RECOVID-DIR-140-GO / ADQ Component 1: Emergency C UISICIÓN DE MEDICAMENTOS IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 555,300.00 0.00 Signed 2022-01-07 2022-01-24 2022-02-01 2022-02-01 2022-02-24 2022-12-31 PARA KIT COVID 19 tion, detection and treatmen t RECOVID-DIR-143-GO / ADQ Component 1: Emergency C UISICION DE MEDICAMENTO IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 666,876.00 0.00 Completed 2021-10-08 2021-10-12 2021-10-18 2021-10-15 2021-11-25 2022-02-25 2022-02-07 PARA KIT COVID 19 tion, detection and treatmen t RECOVID-DIR-142-GO / ADQ Component 1: Emergency C UISICIÓN DE CUPONES DE C OVID-19 response to preven Single Stage - One E OMBUSTIBLE PARA ABASTECI IBRD / 94290 Post Request for Bids Open - National 90,250.00 0.00 Canceled 2021-04-29 2021-06-02 2021-05-09 2021-07-02 2021-07-12 2021-07-30 2021-12-31 tion, detection and treatmen nvelope MIENTO DE FLOTA DE VEHIC t ULOS DEL NIVEL SUPERIOR M INSAL RECOVID-DIR-145-GO / ADQ Component 1: Emergency C UISICIÓN DE CUPONES DE C OVID-19 response to preven OMBUSTIBLE PARA ABASTECI IBRD / 94290 Post Direct Selection Direct - National 90,250.00 0.00 Completed 2021-04-29 2021-06-02 2021-07-02 2021-07-02 2021-07-30 2021-12-31 tion, detection and treatmen MIENTO DE FLOTA DE VEHIC t ULOS DEL NIVEL SUPERIOR M INSAL RECOVID-146-RFQ-GO / Adq uisición de 7 boletos aéreos para la capacitación de siete Component 2. Project Manag Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 10,000.00 0.00 Canceled 2022-11-11 2022-11-16 2022-12-16 profesionales del Laboratorio ement and Monitoring tions nvelope Clínico Nacional de Salud Púb lica en secuenciación genómi ca del SARS-Cov-2. RECOVID-148-DIR-GO / SUMI NISTRO, INSTALACIÓN Y PUE Component 1: Emergency C STA EN FUNCIONAMIENTO DE OVID-19 response to preven Under Imple IBRD / 92290 Post Direct Selection Direct - National 29,000.00 0.00 2022-12-16 2023-01-04 2022-12-21 2023-01-06 2023-01-25 2023-05-25 VIDEO-ENDOSCOPIO Y MONIT tion, detection and treatmen mentation OR A COLOR 19", GRADO MÉ t DICO PARA EL HOSPITAL NAC IONAL ROSALES. RECOVID-75-RFQ-GO / SUMI NISTRO, INSTALACIÓN Y PUE Component 1: Emergency C STA EN MARCHA DEL SISTEM OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 48,000.00 0.00 Canceled 2022-08-24 2022-10-26 2023-02-23 A DE AIRE ACONDICIONADO tion, detection and treatmen tions nvelope Y VENTILACIÓN MECÁNICA, P t ARA EL LABORATORIO DE PA TOLOGÍA DEL HOSPITAL ROS ALES. RECOVID-149-RFQ-GO / SUM INISTRO, INSTALACIÓN Y PUE Component 1: Emergency C STA EN MARCHA DEL SISTEM OVID-19 response to preven Request for Quota Single Stage - One E A DE AIRE ACONDICIONADO IBRD / 92290 Post Open - National 48,000.00 0.00 Canceled 2023-01-18 2023-05-18 2023-03-11 2023-07-09 tion, detection and treatmen tions nvelope Y VENTILACIÓN MECÁNICA, P t ARA EL LABORATORIO DE PA TOLOGÍA DEL HOSPITAL ROS ALES. RECOVID-156-RFB-GO / Sum inistro, instalación y puesta e Component 1: Emergency C n marcha de Cabinas de bios OVID-19 response to preven Single Stage - One E Under Imple IBRD / 91000 Post Request for Bids Open - National 194,472.55 0.00 2023-01-27 2023-02-13 2023-02-01 2023-02-14 2023-03-03 2023-03-30 2023-03-23 2023-06-20 2023-04-20 2023-10-17 eguridad, Esterilizador y Sist tion, detection and treatmen nvelope mentation ema de ultrapurificación de a t gua para Hospital Nacional El Salvador. Page 5 RECOVID-157-RFQ-GO / Insu Component 2. Project Manag Request for Quota Single Stage - One E Under Imple mos informáticos para funcio IBRD / 92290 Post Open - National 2,865.00 0.00 2023-01-03 2023-02-20 2023-03-07 ement and Monitoring tions nvelope mentation namiento de la UGP RECOVID-158-RFB-GO / Sum Component 1: Emergency C Single Stage - One E Under Imple inistro de Torre de Video colo IBRD / 91000 OVID-19 response to preven Post Request for Bids Open - National 141,350.00 0.00 2023-01-13 2023-02-13 2023-01-18 2023-02-13 2023-02-17 2023-03-20 2023-04-18 2023-07-17 nvelope mentation noscopia para el Hospital Na tion, detection and treatmen cional Rosales t RECOVID-161-RFB-GO / Adq Component 1: Emergency C uisición de equipo informátic OVID-19 response to preven Single Stage - One E Pending Impl o para el fortalecimiento de l IBRD / 92290 Post Request for Bids Open - National 133,932.55 0.00 2023-02-15 2023-02-20 2023-03-22 2023-04-21 2023-05-23 2023-09-20 tion, detection and treatmen nvelope ementation a Dirección de Comunicación t Social e Institucional RECOVID-162-RFQ-GO / Sum Component 1: Emergency C inistro, Instalación y Puesta e OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 60,000.00 0.00 2023-02-20 2023-04-07 2023-08-05 n Funcionamiento de Baños tion, detection and treatmen tions nvelope ementation Ultrasónicas para HNES. t RECOVID-163-RFB-GO / Adq Component 1: Emergency C uisición de montacargas para OVID-19 response to preven Single Stage - One E Under Imple IBRD / 92290 Post Request for Bids Open - National 120,250.00 0.00 2023-02-15 2023-03-24 2023-02-20 2023-03-22 2023-04-16 2023-05-21 2023-09-18 mejorar el almacenamiento e tion, detection and treatmen nvelope mentation n almacén el Paraiso del MIN t SAL. RECOVID-139-RFB-GO / SUM Component 1: Emergency C INISTRO, INSTALACIÓN Y PUE OVID-19 response to preven Single Stage - One E STA EN MARCHA DE CUARTO IBRD / 92290 Post Request for Bids Open - National 139,265.00 0.00 Canceled 2022-10-28 2022-12-13 2022-11-02 2022-12-13 2022-11-25 2022-12-09 2022-12-29 2023-07-27 tion, detection and treatmen nvelope FRIO DE LA REGION PARACE t NTRAL DE SALUD DEL MINIST ERIO DE SALUD RECOVID-167-RFB-GO / Sum Component 1: Emergency C Single Stage - One E Under Imple inistro, Instalación y Puesta e IBRD / 92290 OVID-19 response to preven Post Request for Bids Open - National 139,265.00 0.00 2023-02-28 2023-03-31 2023-03-05 2023-03-31 2023-04-04 2023-04-24 2023-05-23 2023-11-19 nvelope mentation n Marcha de Cuarto Frío RPS tion, detection and treatmen del MINSAL t RECOVID-77-RFB-GO / Sumi Component 1: Emergency C nistro de Equipo e Instrumen OVID-19 response to preven Single Stage - One E IBRD / 92290 Post Request for Bids Open - National 170,000.00 0.00 Canceled 2022-08-31 2022-12-08 2022-09-14 2022-12-08 2022-10-15 2022-11-14 2022-12-06 2023-04-05 tal para Unidad de Oftalmolo tion, detection and treatmen nvelope gía de Hospital del Hospital N t acional Zacamil RECOVID-165-RFQ-GO / Sum Component 1: Emergency C inistro de Equipo para Unidad OVID-19 response to preven Request for Quota Single Stage - One E Under Imple IBRD / 92290 Post Open - National 40,000.00 0.00 2023-03-08 2023-05-18 2023-04-23 2023-08-21 de Oftalmología de Hospital tion, detection and treatmen tions nvelope mentation del Hospital Nacional Zacami t l RECOVID-166-RFQ-GO / Sum Component 1: Emergency C inistro de Instrumental para OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 150,000.00 0.00 2023-03-08 2023-04-27 2023-08-25 Unidad de Oftalmología de H tion, detection and treatmen tions nvelope ementation ospital del Hospital Nacional t Zacamil RECOVID-173-RFQ-GO / Adq Component 1: Emergency C uisición de Equipo Informátic OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 34,595.68 0.00 2023-05-24 2023-07-15 2023-11-12 o para el fortalecimiento de tion, detection and treatmen tions nvelope ementation Unidad de Promoción Vida Sa t na y Bienestar RECOVID-1-RFB-GO-BIS / Su Component 1: Emergency C ministro, instalación y puesta OVID-19 response to preven Open - Internationa Single Stage - One E en marcha de equipos de uni IBRD / 91000 Prior Request for Bids 8,349,609.18 0.00 Canceled 2021-08-23 2021-12-20 2022-03-15 2022-06-24 2022-10-24 2023-07-02 tion, detection and treatmen l nvelope dad de radiología e imágenes t diagnósticas para el Hospital Nacional El Salvador. RECOVID-179-RFQ-GO / Adq Component 1: Emergency C uisición y suministro de equi OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 32,000.00 0.00 2023-07-05 2023-08-30 2023-11-28 pos de aires acondicionados tion, detection and treatmen tions nvelope ementation en Establecimientos de Salud t priorizados. RECOVID-181-RFQ-GO / Adq uisición de impresores matric Component 2. Project Manag Request for Quota Single Stage - One E Pending Impl iales, software y accesorios i IBRD / 92290 Post Open - National 34,250.00 0.00 2023-06-28 2023-08-28 2023-11-26 ement and Monitoring tions nvelope ementation nformáticos para el fortaleci miento de la UGGPI y la Paga duría Institucional RECOVID-182-RFB-GO / Sum Component 1: Emergency C inistro, Instalación y Puesta e OVID-19 response to preven Single Stage - One E Pending Impl n Marcha de Equipo generad IBRD / 92290 Post Request for Bids Open - National 275,000.00 0.00 2023-07-14 2023-07-19 2023-08-18 2023-09-18 2023-10-13 2024-02-10 tion, detection and treatmen nvelope ementation or de vapor, caldera 80 VHP t y periféricos. Hospital Nacion al Zacamil. RECOVID-180-RFQ-GO / Adq Component 1: Emergency C uisición y suministro de piso OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 70,000.00 0.00 2023-07-05 2023-08-21 2023-11-19 de vinil en áreas de imagenol tion, detection and treatmen tions nvelope ementation ogía de Hospitales Nacionale t s priorizados. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RECOVID-13-RFQ-NC / Contr atación de servicios de agen Component 1: Emergency C cia de publicidad para produ OVID-19 response to preven Request for Quota Single Stage - One E IBRD / 91000 Post Open - National 500,000.00 400,000.00 Signed 2021-09-29 2022-01-10 2022-03-08 2022-07-09 cción y difusión de campañas tion, detection and treatmen tions nvelope de comunicación educativa, t para el combate de la pande mia contra el COVID-19. RECOVID-16-RFQ-NC / Servic io de rotulación que visibilice Component 1: Emergency C las recomendaciones y medi OVID-19 response to preven Request for Quota Single Stage - One E Pending Impl IBRD / 91000 Post Open - National 35,000.00 0.00 2021-11-11 2022-01-21 2022-03-07 das contenidas en los lineami tion, detection and treatmen tions nvelope ementation entos técnicos para la protec t ción del personal por la emer gencia del COVID-19 RECOVID-58-RFQ-NC / Servic io de arrendamiento de fotoc Component 2. Project Manag Request for Quota Single Stage - One E IBRD / 92290 Post Open - National 7,000.00 6,999.00 Signed 2022-03-23 2022-04-27 2022-05-15 2023-04-27 opiadora e impresiones para ement and Monitoring tions nvelope apoyar la Gestión de la UGPP I RECOVID-59-RFQ-NC / Servic Component 2. Project Manag Request for Quota Single Stage - One E ios de mantenimiento de equ IBRD / 92290 Post Open - National 15,000.00 4,320.00 Signed 2022-03-23 2022-04-27 2022-06-08 2023-04-27 ement and Monitoring tions nvelope ipos de aíres acondicionados Page 6 RECOVID-15-RFQ-NC / Contr Component 1: Emergency C atación de alimentación y loc OVID-19 response to preven Request for Quota Single Stage - One E al para el desarrollo de consu IBRD / 91000 Post Open - National 15,000.00 0.00 Canceled 2022-01-21 2022-03-30 2022-07-28 tion, detection and treatmen tions nvelope ltas de partes interesadas y t poblaciones vulnerables RECOVID-DIR-105-NC / SERV Component 1: Emergency C ICIO DE CALL CENTER PARA L IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 418,530.00 418,530.00 Signed 2021-02-02 2021-02-11 2021-02-12 2021-02-12 2021-02-15 2021-02-16 2021-03-05 LAMADAS DE CONTENCIÓN D tion, detection and treatmen E LA PANDEMIA t RECOVID-DIR-110-NC / SERV ICIO DE ALQUILER DE 40 CA Component 1: Emergency C MIONES FURGON PARA LA DI OVID-19 response to preven STRIBUCION DE SUMINISTRO IBRD / 94290 Post Direct Selection Direct - National 597,645.00 597,645.00 Signed 2021-03-11 2021-04-13 2021-04-16 2021-04-16 2021-05-17 2021-05-18 2021-12-31 tion, detection and treatmen S, TRASLADO DE MOBILIARIO t Y EQUIPO A LOS DIFERENTES CENTROS DE VACUNACIÓN Y OTROS. RECOVID-DIR-113-NC / SERV Component 1: Emergency C ICIO DE ALIMENTACION A DO OVID-19 response to preven MICILIO EN ZONA METROPOLI IBRD / 94290 Post Direct Selection Direct - National 96,884.24 96,884.24 Signed 2021-04-08 2021-04-09 2021-04-09 2021-04-09 2021-05-21 2021-05-22 2021-08-21 tion, detection and treatmen TANA PARA EL PERSONAL EN t LOS AUTOSERVICIOS DE VAC UNACION PARA COVID-19 RECOVID-DIR-116-NC / CON Component 1: Emergency C TRATACION DE SERVICIOS D OVID-19 response to preven E SANITIZACION DE UNIDADE IBRD / 94290 Post Direct Selection Direct - National 530,545.04 530,545.04 Signed 2021-04-07 2021-04-19 2021-04-19 2021-04-19 2021-04-30 2021-05-01 2021-12-31 tion, detection and treatmen S DE TRANSPORTE DERIVAD t OS PARA LA EMERGENCIA PO R COVID-19 RECOVID-DIR-118-NC / SERV ICIO DE ALIMENTACIÓN PARA Component 1: Emergency C EL PERSONAL DE SALUD DE L OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 194,929.00 474,722.08 Signed 2021-04-12 2021-06-16 2021-07-16 2021-07-16 2021-07-27 2021-08-06 2021-10-27 OS AUTOCENTROS DE VACU tion, detection and treatmen NACION Y EL MEGACENTRO t DE VACUNACION DEL HOSPIT AL EL SALVADOR RECOVID-DIR-124-NC / SERV ICIO DE ALIMENTACIÓN A DO Component 1: Emergency C MICILIO EN ZONA METROPOLI OVID-19 response to preven IBRD / 94290 Post Direct Selection Direct - National 148,918.60 148,918.60 Signed 2021-10-27 2021-11-11 2021-11-01 2021-10-11 2021-12-22 2021-12-23 2022-02-22 TANA, MEGACENTRO DE VAC tion, detection and treatmen UNACION Y CENTRO NACION t AL DE VACUNACION (CENABI ) RECOVID-DIR-125-NC / SERV Component 1: Emergency C ICIO DE CALL CENTER PARA IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 4,100,000.00 4,100,000.00 Signed 2021-09-03 2021-09-07 2021-09-08 2021-09-08 2021-09-16 2021-09-17 2021-12-31 EL SEM tion, detection and treatmen t RECOVID-DIR-126-NC / SERV Component 1: Emergency C ICIO DE CALL CENTER PARA OVID-19 response to preven SEGUIMIENTO DE CASOS SOS IBRD / 94290 Post Direct Selection Direct - National 1,064,361.32 1,064,361.22 Signed 2021-11-08 2021-11-10 2021-11-10 2021-11-10 2021-11-12 2021-11-29 2022-02-22 tion, detection and treatmen PECHOSOS Y CONFIRMADOS t POR COVID-19 A NIVEL NACI ONAL RECOVID-DIR-108-NC / CON Component 1: Emergency C TRATACIÓN DE SERVICIO DE OVID-19 response to preven CALL CENTER DE ATENCIÓN IBRD / 94290 Post Direct Selection Direct - National 1,064,361.32 1,064,361.32 Completed 2021-03-04 2021-03-12 2021-03-22 2021-03-19 2021-03-22 2021-04-01 2021-07-21 2021-09-05 tion, detection and treatmen DE LLAMADAS EN EL MARCO t DE LA CONTENCIÓN DE LA P ANDEMIA COVID-19 RECOVID-DIR-129-NC / SERV ICIO DE TRANSPORTE PARA Component 1: Emergency C LA DISTRIBUCION DE VACUN OVID-19 response to preven AS, EQUIPO DE VACUNACION IBRD / 94290 Post Direct Selection Direct - National 808,515.00 0.00 Completed 2021-01-05 2021-02-01 2021-02-03 2021-02-03 2021-02-11 2021-12-31 2021-11-07 tion, detection and treatmen , KITS MEDICOS, INSUMOS Y t PERSONAS A LAS DIFRENTES CENTROS DE VACUNACION Y OTROS PUNTOS GEOGRAFIC OS. RECOVID-DIR-130-NC / SERV Component 1: Emergency C ICIO DE LIMPIEZA DE BIOPRO OVID-19 response to preven TECCIÒN EN LOS ESTABLECI IBRD / 94290 Post Direct Selection Direct - National 1,283,599.32 0.00 Signed 2021-01-03 2021-03-01 2021-03-08 2021-03-08 2021-06-15 2021-12-31 tion, detection and treatmen MIENTOS DE LA RED NACION t AL DE HOSPITALES DEL MINS AL. RECOVID-DIR-131-NC / SERV ICIO DE TRANSPORTE PARA L Component 1: Emergency C A DISTRIBUCIÓN DE VACUNA OVID-19 response to preven S, EQUIPO DE VACUNACION, IBRD / 94290 Post Direct Selection Direct - National 2,997,144.00 0.00 Signed 2021-05-12 2021-05-17 2021-05-19 2021-05-19 2021-05-31 2021-10-01 tion, detection and treatmen KITS MEDICOS, INSUMOS Y P t ERSONAS A LOS DIFERENTES CENTROS DE VACUNACION Y OTROS PUNTOS GEOGRAFIC OS. RECOVID-DIR-133-NC / SERV Component 1: Emergency C ICIO DE LIMPIEZA DE BIOPRO IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 778,000.00 0.00 Completed 2021-08-12 2021-08-19 2021-10-22 2021-10-22 2021-12-10 2021-12-31 2022-06-06 TECCION tion, detection and treatmen t RECOVID-DIR-141-NC / LICE Component 1: Emergency C NCIA DE ALOJAMIENTO EN LA IBRD / 94290 OVID-19 response to preven Post Direct Selection Direct - National 196,892.30 0.00 Completed 2021-01-19 2021-02-02 2021-02-08 2021-02-02 2021-03-03 2022-03-03 2022-06-12 NUBE tion, detection and treatmen t RECOVID-17-RFQ-NC / Repro Component 1: Emergency C ducción de material educativ OVID-19 response to preven Request for Quota Single Stage - One E o para promover el sistema d IBRD / 91000 Post Open - National 55,000.00 0.00 Canceled 2022-01-19 2022-03-31 2022-06-29 tion, detection and treatmen tions nvelope e quejas y derechos de los us t uarios de los servicios RECOVID-150-RFQ-NC / Mont aje, Impresión y Reproducció n de Rotafolio Educativo sobr Component 2. Project Manag Request for Quota Single Stage - One E Under Imple IBRD / 92290 Post Open - National 55,000.00 0.00 2023-01-18 2023-03-11 2023-04-25 e la temática de Mecanismo ement and Monitoring tions nvelope mentation de Insatisfacciones, dirigido a la Población Usuaria de los S ervicios de Salud. RECOVID-168-RFQ-NC / Serv icio de arrendamiento de fot Component 2. Project Manag Request for Quota Single Stage - One E Under Imple IBRD / 92290 Post Open - National 10,000.00 0.00 2023-03-01 2023-04-18 2023-12-31 ocopiadora e impresiones pa ement and Monitoring tions nvelope mentation ra apoyar la Gestión de la UG PPI RECOVID-169-RFQ-NC / SER VICIOS DE ALIMENTACION Y USO DE INSTALACIONES EN ZONA METROPOLITANA DE S Component 2. Project Manag Request for Quota Single Stage - One E Under Imple AN SALVADOR, PARA JORNAD IBRD / 92290 Post Open - National 10,000.00 0.00 2023-04-03 2023-05-19 2023-09-30 ement and Monitoring tions nvelope mentation AS DE SOCIALIZACIÓN DE A VANCES Y FORTALECIMIENTO DE RECURSOS HUMANOS EN CUMPLIMIENTO AL MARCO D E GESTIÓN AMBIENTAL Y SO CIAL Page 7 RECOVID-176-RFQ-NC / CON TRATACIÓN DE AGENCIA DE VIAJES PARA EL SERVICIO DE EMISIÓN DE BOLETOS AÉREO S, TARJETAS DE SEGURO DE Component 2. Project Manag Request for Quota Single Stage - One E Pending Impl IBRD / 92290 Post Open - National 12,000.00 0.00 2023-05-29 2023-06-09 2023-06-30 ASISTENCIA AL VIAJERO CON ement and Monitoring tions nvelope ementation COBERTURA INTERNACIONAL , ALOJAMIENTO Y TRASLADO PARA PERSONAL DE LA UNID AD DE GESTIÓN DE PROGRA MAS Y PROYECTOS DE INVER SIÓN EN CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RECOVID-18-QCBS-CS / Serv icios de consultoría para sup Component 1: Emergency C ervisión externa de conexos OVID-19 response to preven Quality And Cost- IBRD / 91000 Post Open - National 150,000.00 0.00 Canceled 2021-02-08 2021-03-01 2021-03-30 2021-04-27 2021-05-12 2021-05-26 2021-06-09 2022-01-10 relacionados a la adecuación tion, detection and treatmen Based Selection de la infraestructura para la i t nstalación del equipo de res onancia magnética RECOVID-19-LCS-CS / Audito ría de estados financieros pa ra el periodo del 1 de enero a l 31 de diciembre 2021 del Pr Component 2. Project Manag Least Cost Selecti IBRD / 91000 Post Open - National 20,000.00 20,000.00 Signed 2022-01-13 2022-01-18 2022-01-13 2022-02-21 2022-01-28 2022-03-22 2022-02-02 2022-03-31 2022-02-07 2022-04-07 2022-02-15 2022-04-07 2022-02-28 2022-05-21 2022-05-31 oyecto de “Respuesta de Em ement and Monitoring on ergencia de El salvador ante el COVID-19” financiado por l os Contratos de Préstamo BI RF-9100-SV y BIRF-9229-SV RECOVID-93-CQS-CS / Contr atación de Auditoría de estad os financieros para el periodo del 1 de enero al 31 de dicie Component 2. Project Manag Consultant Qualifi Under Implement mbre 2022 del Proyecto de R IBRD / 92290 Post Open - National 40,000.00 0.00 2022-08-26 2022-10-04 2022-09-16 2022-10-31 2022-11-30 2023-01-04 2023-05-31 ement and Monitoring cation Selection ation espuesta de Emergencia de El salvador ante el COVID-19 ” financiado por los contratos de préstamo 9100-SV, 9229- SV y 9429-SV. RECOVID-20-LCS-CS / Audito Component 1: Emergency C Least Cost Selecti ria de los estados financieros IBRD / 91000 OVID-19 response to preven Post Open - National 23,000.00 0.00 Canceled 2022-10-10 2022-10-10 2022-11-09 2022-12-07 2022-12-21 2023-01-25 2023-02-22 2023-06-30 on correspondientes al año 202 tion, detection and treatmen 2 t RECOVID-174-CQS-CS / Audi toría de estados financieros p ara el periodo del 1 de enero al 31 de diciembre 2023 del Component 2. Project Manag Consultant Qualifi Under Implement Proyecto de “Respuesta de E IBRD / 92290 Post Open - National 40,000.00 0.00 2023-05-18 2023-06-13 2023-06-08 2023-08-03 2023-09-04 2023-10-10 2024-05-04 ement and Monitoring cation Selection ation mergencia de El salvador ant e el COVID-19” financiado po r los Contratos de Préstamo BIRF-9100-SV, BIRF-9229-SV y BIRF 9429-SV INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RECOVID-23-INDV-CS / Cons ultoría Individual de Especiali sta Social en Apoyo al cumpli Component 1: Emergency C miento del Marco de Gestión OVID-19 response to preven Individual Consult IBRD / 91000 Post Open 41,600.00 41,600.00 Terminated 2021-08-16 2021-07-27 2021-08-29 2021-09-09 2021-09-01 2021-09-22 2021-10-02 2021-10-11 2023-01-25 Social de los Proyectos ejecu tion, detection and treatmen ant Selection tados en la UGPPI con financi t amiento BIRF, con énfasis en el Proyecto “Respuesta de El Salvador ante el COVID-19 RECOVID-24-INDV-CS / Cons ultoría Individual de Especiali sta Ambiental en Apoyo al cu Component 1: Emergency C mplimiento del Marco de Ges OVID-19 response to preven Individual Consult IBRD / 91000 Post Open 41,600.00 41,600.00 Signed 2021-08-09 2021-08-26 2021-08-22 2021-10-06 2021-08-25 2021-10-06 2021-09-25 2021-11-04 2023-01-18 tión Ambiental de los Proyect tion, detection and treatmen ant Selection os ejecutados en la UGPPI co t n financiamiento BIRF, con é nfasis en el Proyecto “Respu esta de El Salvador ante el C OVID-19” RECOVID-29-IND-CS / Servici o de consultoría para la supe Component 1: Emergency C rvisión del proyecto “suminis OVID-19 response to preven Individual Consult Pending Impleme tro, instalación y puesta en f IBRD / 91000 Post Open 17,500.00 0.00 2021-08-31 2021-10-19 2021-11-09 2022-01-04 2022-07-31 tion, detection and treatmen ant Selection ntation uncionamiento de equipos de t la sala de angiógrafo y quiróf ano general del Hospital Naci onal El Salvador”. RECOVID-30-IND-CS / Servici o de consultoría para la supe Component 1: Emergency C rvisión del proyecto “suminis OVID-19 response to preven Individual Consult Pending Impleme tro, instalación y puesta en f IBRD / 91000 Post Open 17,500.00 0.00 2021-08-31 2021-10-19 2021-11-09 2022-01-04 2022-07-31 tion, detection and treatmen ant Selection ntation uncionamiento de equipos pa t ra la central de esterilización y equipos del Hospital Nacion al El Salvador”. RECOVID-31-IND-CS / Servici o de consultoría para la supe Component 1: Emergency C rvisión del proyecto “suminis OVID-19 response to preven Individual Consult Pending Impleme tro, instalación y puesta en IBRD / 91000 Post Open 24,000.00 0.00 2021-08-31 2021-10-19 2021-11-09 2022-01-04 2022-07-31 tion, detection and treatmen ant Selection ntation marcha de equipos de unida t d de radiología e imágenes di agnósticas para el Hospital N acional El Salvador Component 1: Emergency C RECOVID-22-INDV-CS / Espe Individual Consult IBRD / 91000 OVID-19 response to preven Post Open 52,500.00 0.00 Canceled 2021-02-15 2021-02-28 2021-03-03 2021-04-03 2022-12-31 cialista financiero ant Selection tion, detection and treatmen t RECOVID-21-INDV-CS / Cons Component 1: Emergency C ultor(a) para adquisiciones y OVID-19 response to preven Individual Consult contrataciones del proyecto IBRD / 91000 Prior Open 33,600.00 33,600.00 Signed 2021-08-28 2021-09-07 2021-09-14 2021-09-13 2021-09-17 2021-11-30 2021-10-05 2021-10-11 2022-10-05 tion, detection and treatmen ant Selection de respuesta de El Salvador t ante el COVID-19, y otros con financiamiento BIRF Page 8 RECOVID -46-INDV-CS / Serv icios de consultoría especiali Component 2. Project Manag Individual Consult Pending Impleme zada de ingeniería mecánica IBRD / 92290 Post Open 33,600.00 0.00 2022-01-07 2022-01-31 2022-02-04 2022-02-15 2023-02-15 ement and Monitoring ant Selection ntation en apoyo a la ejecución de lo s proyectos de infraestructur a RECOVID -47-INDV-CS / Serv icios de consultoría especiali Component 2. Project Manag Individual Consult Pending Impleme zada de ingeniería eléctrica e IBRD / 92290 Post Open 33,600.00 0.00 2022-01-07 2022-01-31 2022-02-04 2022-02-15 2023-02-15 ement and Monitoring ant Selection ntation n apoyo a la ejecución de los proyectos de infraestructura RECOVID -48-INDV-CS / Serv icios de consultoría especiali Component 2. Project Manag Individual Consult Pending Impleme zada de ingeniería hidrosanit IBRD / 92290 Post Open 33,600.00 0.00 2022-01-07 2022-01-31 2022-02-04 2022-02-15 2023-02-15 ement and Monitoring ant Selection ntation aria en apoyo a la ejecución de los proyectos de infraestr uctura RECOVID-42-CDS-CS / Consu ltoría en arquitectura y activi dades de dibujo técnico de in Component 2. Project Manag Individual Consult IBRD / 92290 Post Direct 27,600.00 27,600.00 Signed 2021-12-17 2022-01-03 2022-01-03 2022-01-07 2022-01-06 2022-01-18 2022-01-14 2022-02-07 2023-01-14 fraestructura financiados con ement and Monitoring ant Selection Unidad de Gestión de Progra mas y Proyectos De Inversión – UGPPI RECOVID-45-CDS-CS / Consu ltoría en arquitectura y activi dades de dibujo técnico de in Component 2. Project Manag Individual Consult IBRD / 92290 Post Direct 27,600.00 27,600.00 Signed 2021-12-17 2022-01-03 2022-01-03 2022-01-07 2022-01-06 2022-01-18 2022-01-14 2022-02-07 2023-01-14 fraestructura financiados con ement and Monitoring ant Selection Unidad de Gestión de Progra mas y Proyectos De Inversión – UGPPI RECOVID-43-CDS-CS / Consu ltoría en arquitectura y activi dades de dibujo técnico de in Component 2. Project Manag Individual Consult IBRD / 92290 Post Direct 27,600.00 27,600.00 Signed 2021-12-17 2022-01-03 2022-01-03 2022-01-07 2022-01-06 2022-01-18 2022-01-14 2022-02-07 2023-01-14 fraestructura financiados con ement and Monitoring ant Selection Unidad de Gestión de Progra mas y Proyectos De Inversión – UGPPI RECOVID-44-CDS-CS / Consu ltoría en arquitectura y activi dades de dibujo técnico de in Component 2. Project Manag Individual Consult IBRD / 92290 Post Direct 27,600.00 27,600.00 Signed 2021-12-17 2022-01-03 2022-01-03 2022-01-07 2022-01-06 2022-01-18 2022-01-14 2022-02-07 2023-01-14 fraestructura financiados con ement and Monitoring ant Selection Unidad de Gestión de Progra mas y Proyectos De Inversión – UGPPI RECOVID-50-INDV-CS / Cons ultoría individual para especi alista de adquisiciones y cont Component 2. Project Manag Individual Consult IBRD / 92290 Prior Open 39,200.00 33,600.00 Signed 2022-01-10 2022-03-10 2022-01-20 2022-04-21 2022-01-27 2022-04-25 2022-02-01 2022-05-07 2023-03-31 rataciones del proyecto de re ement and Monitoring ant Selection spuesta de El Salvador ante el COVID-19, y otros con fina nciamiento BIRF RECOVID-51-INDV-CS / Contr atación de consultores para f ormulación de carpetas técni Component 2. Project Manag Individual Consult IBRD / 92290 Post Open 120,000.00 0.00 Signed 2022-02-07 2022-06-13 2022-03-05 2022-09-01 2022-03-18 2022-09-02 2022-04-08 2022-07-07 cas para el mejoramiento del ement and Monitoring ant Selection sistema eléctrico de los hospi tales nacionales priorizados RECOVID-52-INDV-CS / Servi cios de consultoría par avalú Component 2. Project Manag Individual Consult os técnicos de los bienes inm IBRD / 92290 Post Open 100,000.00 75,000.00 Signed 2022-02-14 2022-03-17 2022-03-14 2022-06-07 2022-03-21 2022-06-07 2022-04-12 2022-06-24 2022-06-11 ement and Monitoring ant Selection uebles propiedad del Minister io de Salud en hospitales na cionales priorizados. RECOVID-60-RFQ-CS / Servic Component 2. Project Manag Individual Consult ios de consultoría de especial IBRD / 92290 Prior Open 36,000.00 0.00 Canceled 2022-03-21 2022-03-28 2022-04-18 2022-05-23 2023-05-23 ement and Monitoring ant Selection ista en adquisiciones para ap oyar la UGPPI RECOVID-60-IND-CS / Servici Component 2. Project Manag Individual Consult os de consultoría de especiali IBRD / 92290 Prior Open 36,000.00 33,600.00 Signed 2022-04-04 2022-05-24 2022-04-18 2022-06-13 2022-05-02 2022-06-30 2022-05-13 2022-07-14 2022-12-31 ement and Monitoring ant Selection sta en adquisiciones para ap oyar la UGPPI RECOVID-70-INDV-CS / Servi cios de consultoría para aval Component 2. Project Manag Individual Consult úos técnicos de los bienes in IBRD / 92290 Post Open 100,000.00 0.00 Signed 2022-04-28 2022-06-27 2022-05-30 2022-10-24 2022-06-09 2022-10-25 2022-07-06 2022-11-03 ement and Monitoring ant Selection muebles propiedad del Minist erio de Salud en Hospitales N acionales Priorizados RECOVID-94-CDS-CS / CONS ULTORÍA INDIVIDUAL PARA E SPECIALISTA EN ADQUISICIO Component 2. Project Manag NES Y CONTRATACIONES DEL IBRD / 92290 Post Direct Selection Direct - National 42,000.00 0.00 Signed 2022-09-09 2022-09-12 2022-09-18 2022-09-28 2022-09-30 2023-12-31 ement and Monitoring PROYECTO DE RESPUESTA D E EL SALVADOR ANTE EL CO VID-19, Y OTROS CON FINACI AMIENTO BIRF RECOVID-98-INDV-CS / Cons ultoría Individual de Especiali sta Social en Apoyo al Cumpli miento del Marco de Gestión Component 2. Project Manag Individual Consult Under Implement IBRD / 92290 Post Open - National 39,000.00 0.00 2022-09-16 2022-11-14 2022-09-30 2023-01-09 2022-10-10 2023-01-12 2022-10-24 2023-12-31 Social de los proyectos ejecu ement and Monitoring ant Selection ation tados en la UGPPI con financi amiento BIRF, con énfasis en el Proyecto "Respuesta de El Salvador ante el COVID-19" RECOVID-136-INDV-CS / CO NSULTORÍA INDIVIDUAL PAR A ESPECIALISTA EN ADQUISIC Component 2. Project Manag Individual Consult IONES Y CONTRATACIONES D IBRD / 92290 Prior Open - National 39,200.00 0.00 Canceled 2022-10-14 2022-10-29 2022-11-03 2022-11-17 2023-12-31 ement and Monitoring ant Selection EL PROYECTO DE RESPUESTA DE EL SALVADOR ANTE EL C OVID-19, Y OTROS CON FINA CIAMIENTO BIRF RECOVID-137-INDV-CS / SER VICIO DE CONSULTORÍA PAR Component 2. Project Manag Individual Consult A APOYO JURÍDICO EN UNIDA IBRD / 92290 Prior Open - National 39,200.00 0.00 Canceled 2022-10-14 2022-10-25 2022-10-27 2022-11-03 2022-11-17 2023-12-31 ement and Monitoring ant Selection D DE ADQUISICIONES Y CON TRATACIONES DE LA UGPPI Page 9 RECOVID-144-CDS-CS / CON SULTORÍA INDIVIDUAL PARA ESPECIALISTA EN ADQUISICI Component 2. Project Manag ONES Y CONTRATACIONES D IBRD / 92290 Prior Direct Selection Direct - National 39,200.00 0.00 Signed 2022-10-18 2022-10-21 2022-10-26 2022-11-03 2022-11-10 2023-12-31 ement and Monitoring EL PROYECTO DE RESPUESTA DE EL SALVADOR ANTE EL C OVID-19, Y OTROS CON FINA CIAMIENTO BIRF RECOVID-152-CDS-CS / SER VICIOS DE CONSULTORIA EN ARQUITECTURA Y ACTIVIDAD Component 2. Project Manag ES DE DIBUJO TECNICO DE IN IBRD / 92290 Post Direct Selection Direct - National 25,300.00 0.00 Signed 2022-12-23 2023-01-20 2023-01-09 2023-01-20 2023-01-25 2023-12-31 ement and Monitoring FRAESTRUCTURA FINANCIAD OS CON UNIDAD DE GESTION DE PROGRAMAS Y PROYECTO S DE INVERSION - UGPPI RECOVID-153-CDS-CS / SER VICIOS DE CONSULTORIA EN ARQUITECTURA Y ACTIVIDAD Component 2. Project Manag Under Implement ES DE DIBUJO TECNICO DE IN IBRD / 92290 Post Direct Selection Direct - National 25,300.00 0.00 2022-12-23 2023-01-10 2023-01-09 2023-01-20 2023-01-25 2023-12-31 ement and Monitoring ation FRAESTRUCTURA FINANCIAD OS CON UNIDAD DE GESTION DE PROGRAMAS Y PROYECTO S DE INVERSION - UGPPI RECOVID-154-CDS-CS / SER VICIOS DE CONSULTORIA EN ARQUITECTURA Y ACTIVIDAD Component 2. Project Manag Under Implement ES DE DIBUJO TECNICO DE IN IBRD / 92290 Post Direct Selection Direct - National 25,300.00 0.00 2022-12-23 2023-01-10 2023-01-09 2023-01-20 2023-01-25 2023-12-31 ement and Monitoring ation FRAESTRUCTURA FINANCIAD OS CON UNIDAD DE GESTION DE PROGRAMAS Y PROYECTO S DE INVERSION - UGPPI RECOVID-155-CDS-CS / SER VICIOS DE CONSULTORIA EN ARQUITECTURA Y ACTIVIDAD Component 2. Project Manag ES DE DIBUJO TECNICO DE IN IBRD / 92290 Post Direct Selection Direct - National 25,300.00 0.00 Signed 2022-12-23 2023-01-10 2023-01-09 2023-01-23 2023-01-25 2023-12-31 ement and Monitoring FRAESTRUCTURA FINANCIAD OS CON UNIDAD DE GESTION DE PROGRAMAS Y PROYECTO S DE INVERSION - UGPPI RECOVID-160-CDS-CS / Cons ultoría Individual de Especiali sta Ambiental en Apoyo al cu mplimiento del Marco de Ges Component 2. Project Manag IBRD / 92290 Post Direct Selection Direct - National 26,588.00 0.00 Signed 2023-01-31 2023-02-10 2023-02-10 2023-02-24 2023-02-25 2023-12-31 tión Ambiental de los Proyect ement and Monitoring os ejecutados en la UGPPI co n financiamiento BIRF, con é nfasis en el Proyecto “Respu esta de El Salvador ante el C OVID-19. RECOVID-164-INDV-CS / Ser vicios de Consultoría para Ap Component 2. Project Manag Individual Consult IBRD / 92290 Prior Open - National 28,000.00 0.00 Signed 2023-02-08 2023-02-07 2023-02-20 2023-02-21 2023-02-24 2023-02-23 2023-03-01 2023-12-31 oyo Jurídico en Unidad de Ad ement and Monitoring ant Selection quisiciones y Contartaciones de la UGPPI RECOVID-170-INDV-CS / Con tratación de servicios de con Component 2. Project Manag Individual Consult Pending Impleme sultoría individual para el fort IBRD / 92290 Post Open - National 45,000.00 0.00 2023-03-31 2023-05-04 2023-05-19 2023-06-13 2023-09-11 ement and Monitoring ant Selection ntation alecimiento de la Dirección d e Tecnologías de la Informaci ón y Comunicación RECOVID-171-CDS-CS / Cons ultoría Individual para Especi alista en Adquisiciones y Con Component 2. Project Manag IBRD / 92290 Prior Direct Selection Direct - National 22,774.00 0.00 Signed 2023-03-24 2023-04-13 2023-04-03 2023-04-17 2023-04-27 2023-12-31 tratación del Proyecto de Res ement and Monitoring puesta de El Salvador ante el COVID-19 y otros con financi amiento BIRF RECOVID-172-CDS-CS / Cons ultoría Individual para Especi alista en Adquisiciones y Con Component 2. Project Manag Under Implement IBRD / 92290 Prior Direct Selection Direct - National 16,530.00 0.00 2023-04-14 2023-04-13 2023-05-03 2023-05-15 2023-07-04 2023-12-31 tratación del Proyecto de Res ement and Monitoring ation puesta de El Salvador ante el COVID-19 y otros con financi amiento BIRF RECOVID-184-INDV-CS / Con tratación de Asistente Admini Component 2. Project Manag Individual Consult Pending Impleme IBRD / 92290 Post Open - National 5,000.00 0.00 2023-06-30 2023-07-25 2023-08-07 2023-08-18 2023-12-31 strativo para la coordinación ement and Monitoring ant Selection ntation del Área de Infraestructura y Equipo Page 10 PLAN DE PASSATION DE MARCHÉS Information sur le Projet : Emprunteur/Bénéficiaire République Togolaise Ministère Responsable Nom du Projet Identification P172769 Agence d’exécution du Projet : [A insérer] Date du plan de passation des marchés : [A indiquer] Période couverte par ce plan de passation des marchés : [A indiquer] Date d’approbation par la Banque du plan de passation de marchés : [A indiquer] Date de publication de l’Avis Général de Passation des Marchés : [A indiquer] Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System) : Elevé Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Novembre 2020) (“Règlement de Passation des Marchés”), le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la loi No. 2009-013 du 30 juin 2009 relative aux Marchés Publics et Délégation de Service Public, le Décret Nº 2009-277/PR du 11 novembre 2009 portant Code des Marchés Publics et Délégation de Service Public, et les textes d’application y afférents, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : - Le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/les proposants présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection e l’audit ; - Le droit de la Banque d’examiner le dossier et les activités de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés Travaux ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés ne s’applique pas. Autres informations pertinentes sur la passation des marchés : Néant I. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Juillet 2016, révisé en Novembre 2017. Catégories de marchés Montants Observations estimatifs des contrats en millions de dollars américains Travaux (incluant clé à main, Fourniture et Installation, et les >= 5 Partenariat Public - Privé -PPP) Biens, Système d’Information et de Services autres que les >= 1,5 Services intellectuels Contrats à Travaux passer par (incluant clé à >= 5 entente main, directe Fourniture et Les justifications de Installation, et l’entente directe les Partenariat devront être jointes et Public - Privé - approuvées avec PPM PPP) Biens, Système d’Information et de Services >= 1,5 autres que les Services intellectuels 2. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : FOURNITURES ET SERVICES AUTRE QUE LES SERVICES DE CONSULTANTS TRAVAUX (US$ équivalent) (US$ équivalent) AOI AON DC AOI AON DC < < 100.000 ≥5.000.000 <5.000.000 200.00 ≥500.000 <500.000 0 3. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). Liste de Marchés de Travaux, Fournitures, et Services autres que Consultant Date Type Méthode/ Montan de Comme d'Exa Modalité Appro t lance ntaire Réf. DESCRIP men de che de Estimat ment /Fin de No. TION par la passatio march if en de la prestat Banqu n des és US$ procé ions e marchés dure II. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujette à la revue préalable de la Banque comme indiqué dans Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Méthode de Seuils de revue a priori Observations sélection/Catégories de Montants estimatifs des marchés contrats en millions de dollars américains Méthode compétitive/Firmes de >= 0.5 consultants Entente directe/firmes de Les justifications pour consultants >= 0.5 l’entente directe devront être jointes et approuvées Entente avec le PPM directe/Consultants >= 0.2 individuel Méthode Compétitive >= 0.2 (Comparaison de CVs)/ Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux en conformité avec les dispositions des Règlements de Passation des marchés., et l’Emprunteur ne procède pas à une publication dans UNDB 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission ; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels telles des situations d’urgence en conformité au Règlement de Passation des marchés II- Liste de Marchés de Services de Consultants Date Méthod Comm Montan Type de Ré e de entair t d'Exam Approch lancem f. DESCRIPTION passati e/Fin Estimat en par e de ent de No DES MISSIONS on des des if en la Marché la . marché presta US$ Banque procéd s tions ure Lexique des Sigles et Abréviations ARMP Autorité de Régulation des Marchés Publics AOI Appel d’Offres International AON Appel d’Offres National A Revue a posteriori posteriori A Priori Revue a priori CI Consultant Individuel DC Demande de Cotations DNCMP Direction Nationale de Contrôle des Marchés Publics ED Sélection Directe ou Entente Directe PPM Plan de Passation des Marchés SFQ Sélection Fondée sur la Qualité SFQC Sélection Fondée sur la Qualité et le Coût SMC Sélection au Moindre Coût SQC Sélection fondée sur les Qualifications des Consultants PROCUREMENT Western and Central Africa : West Africa Food System Resilience Program (FSRP) PLAN General Information Country: Western and Central Africa 2022-08-09 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172769 GPN Date: Project Name: West Africa Food System Resilience Program (FSRP) Loan / Credit No: IDA / 69980, IDA / D9250 FOOD SYSTEM RESILIENCE PROGRAM - NIGER Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure NE-FRSP-NE-306233-CW-RF ment Document - Request for Quota Single Stage - One E 2023-01-3 Q / Travaux d'extension du si IDA / 69980 Project Management Post Limited 1 Envelope proce 121,951.00 0.00 Signed 2022-08-20 2022-09-22 2022-09-12 tions nvelope 0 ège de l’UGP PARIIS pour le c ss (Non Bank-SPD ompte du FSRP ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306159-GO-RFB Sustainability and adaptive c / Acquisition pour doter le CR Single Stage - One E IDA / 69980 apacity of the food system’s Post Request for Bids Open - National 313,589.00 0.00 Signed 2022-09-05 2022-12-12 2022-09-10 2022-12-13 2022-10-10 2023-01-16 2022-10-25 2023-01-27 2022-11-29 2023-03-29 S et les labos en équipement nvelope productive base s complémentaires clés NE-FRSP-NE-306190-GO-RFB Sustainability and adaptive c Single Stage - One E / Acquisition de semences (A IDA / 69980 apacity of the food system’s Post Request for Bids Open - National 143,728.00 0.00 Completed 2022-08-31 2022-10-07 2022-09-05 2022-10-10 2022-10-05 2022-11-02 2022-10-15 2022-11-23 2022-11-15 2022-12-30 2023-01-21 nvelope ppui en intrants agricoles) productive base NE-FRSP-NE-306228-GO-RFQ Request for Quota Single Stage - One E IDA / 69980 Project Management Post Limited 52,265.00 0.00 Completed 2022-10-25 2023-03-30 2022-11-21 2022-12-31 2023-04-16 / Acquisition de mobilier de b tions nvelope ureau NE-FRSP-NE-306961-GO-RFQ Request for Quota Single Stage - One E / Acquisition de matériel infor IDA / 69980 Project Management Post Limited 52,265.00 38,580.81 Completed 2022-08-15 2022-08-22 2022-08-31 2022-09-09 2022-10-15 2022-09-26 tions nvelope matique pour l'équipe FSRP NE-FRSP-NE-342474-GO-RFQ / Acquisition d'équipements c Digital advisory services for Request for Quota Single Stage - One E Pending Impl omplémentaires et mise en IDA / D9250 agriculture and food crisis pr Post Limited 52,632.00 0.00 2023-06-06 2023-06-14 2023-07-14 tions nvelope ementation marche de la station de réce evention and management ption des données satellitale s de la DGPIA et DGGR NE-FRSP-NE-342493-GO-RFQ Digital advisory services for / Equipement des structures, Request for Quota Single Stage - One E Pending Impl IDA / D9250 agriculture and food crisis pr Post Limited 17,545.00 0.00 2023-06-05 2023-06-13 2023-07-13 renforcement de la cellule gé tions nvelope ementation evention and management omatique par acquisition des drones. NE-FRSP-NE-342526-GO-RFQ / Acquisitions de Kits de com Digital advisory services for Request for Quota Single Stage - One E Pending Impl munication, d'information de IDA / D9250 agriculture and food crisis pr Post Limited 13,000.00 0.00 2023-04-05 2023-04-13 2023-04-30 tions nvelope ementation s impacts potentiels aux agro evention and management pasteurs et décideurs NE-FRSP-NE-342538-GO-RFQ Regional food market integr Request for Quota Single Stage - One E Pending Impl / Equipement des laboratoire IDA / D9250 Post Limited 43,333.00 0.00 2023-03-20 2023-03-28 2023-05-02 ation and trade tions nvelope ementation s (LABOCEL, DGPV, LANA, LT A et LNCCS) NE-FRSP-NE-342565-GO-RFQ Regional food market integr Request for Quota Single Stage - One E Pending Impl / Acquisition de matériel de c IDA / D9250 Post Limited 26,315.00 0.00 2023-04-15 2023-04-25 2023-05-10 ation and trade tions nvelope ementation ollecte des données NE-FRSP-NE-342578-GO-RFB Sustainability and adaptive c Single Stage - One E Under Imple / Appui en intrants des cultur IDA / D9250 apacity of the food system’s Post Request for Bids Open - National 221,053.00 0.00 2023-03-15 2023-03-24 2023-03-20 2023-03-31 2023-04-20 2023-04-27 2023-04-28 2023-05-27 2023-05-22 2023-06-26 nvelope mentation es pluviales (semences et en productive base grais) NE-FRSP-NE-342588-GO-RFB Single Stage - One E Under Imple IDA / D9250 Project Management Post Request for Bids Open - National 390,351.00 0.00 2023-03-15 2023-03-23 2023-03-20 2023-03-23 2023-04-19 2023-04-27 2023-04-28 2023-05-15 2023-05-25 2023-07-29 / Acquisition de matériel roul nvelope mentation ant NE-FRSP-NE-342590-GO-RFQ Request for Quota Single Stage - One E / Acquisition de Motos au pro IDA / D9250 Project Management Post Limited 13,160.00 0.00 Completed 2023-03-13 2023-03-01 2023-03-21 2023-03-31 2023-04-05 tions nvelope fit de l'UCP et les Régions NE-FRSP-NE-342591-GO-RFQ Request for Quota Single Stage - One E / Acquisition de Matériels info IDA / D9250 Project Management Post Limited 26,315.00 0.00 Completed 2023-03-03 2023-03-06 2023-03-10 2023-03-31 2023-04-05 tions nvelope rmatiques au profit de l'UCP NE-FRSP-NE-342499-GO-RFQ Digital advisory services for Request for Quota Single Stage - One E Pending Impl / Achats d'équipements infor IDA / D9250 agriculture and food crisis pr Post Limited 35,088.00 0.00 2023-05-07 2023-05-16 2023-05-31 tions nvelope ementation matiques (Ordinateurs et Tél evention and management éphones) NE-FRSP-NE-306204-GO-RFB / Acquisition de Matériels info Regional food market integr Single Stage - One E Pending Impl IDA / D9250 Post Request for Bids Open - National 122,807.00 0.00 2023-06-12 2023-06-17 2023-07-17 2023-07-27 2023-08-26 2023-10-10 rmatiques pour les structures ation and trade nvelope ementation et partenaires du FSRP NE-FRSP-NE-361809-GO-RFQ Sustainability and adaptive c / Acquisition de semences en Request for Quota Single Stage - One E IDA / D9250 apacity of the food system’s Post Limited 87,000.00 0.00 Completed 2023-05-29 2023-06-01 2023-06-09 2023-06-24 complément de quantités po tions nvelope productive base ur la campagne hivernale 20 23 NE-FRSP-NE-364001-GO-RFB / Fourniture et installation d' Regional food market integr Single Stage - One E Pending Impl un générateur d'azote liquid IDA / D9250 Post Request for Bids Open - National 280,700.00 0.00 2023-06-15 2023-06-22 2023-07-21 2023-07-31 2023-08-31 2023-11-30 ation and trade nvelope ementation e en appui aux unités de con servations de semences ani males NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306238-NC-DIR / Fourniture et installation du IDA / 69980 Project Management Post Direct Selection Direct - National 17,422.00 0.00 Signed 2022-08-30 2022-09-09 2022-09-04 2022-10-07 2022-09-23 2023-09-23 logiciel informatique et comp table TOM2PRO CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306060-CS-CQS / Recrutement consultant po Digital advisory services for Consultant Qualifi Pending Impleme ur l'évaluation des capacités IDA / 69980 agriculture and food crisis pr Post Open - National 43,554.00 0.00 2022-08-30 2022-09-20 2022-11-03 2022-12-03 2022-12-30 2023-02-28 cation Selection ntation techniques et les besoins en evention and management formation pour soutenir le PD O du FSRP NE-FRSP-NE-306174-CS-CQS Sustainability and adaptive c Consultant Qualifi / Recrutement des ONGs pou IDA / 69980 apacity of the food system’s Post Open - National 300,000.00 0.00 Signed 2022-08-20 2022-10-10 2022-09-10 2022-10-24 2022-10-24 2022-12-14 2022-11-23 2023-02-20 2022-12-28 2023-12-28 cation Selection r l'Elaboration d'un Plan GIP productive base NE-FRSP-NE-306184-CS-CQS Sustainability and adaptive c / Recrutement consultant po Consultant Qualifi Pending Impleme IDA / 69980 apacity of the food system’s Post Open - National 69,686.00 0.00 2022-08-25 2022-09-15 2022-10-25 2022-11-24 2022-12-16 2023-02-14 ur l’Élaboration des schémas cation Selection ntation productive base d’aménagements de bassin v ersant NE-FRSP-NE-306187-CS-CQS Consultant Qualifi Under Implement / Recrutement Consultant po IDA / 69980 Project Management Post Open - National 36,794.00 0.00 2022-09-05 2022-12-08 2022-09-20 2023-01-26 2022-10-11 2023-05-05 2022-10-26 2022-11-01 2022-12-16 cation Selection ation ur l’Etude de référence NE-FRSP-NE-306235-CS-QCB Quality And Cost- S / Recrutement d’un Consult IDA / 69980 Project Management Post Open - National 8,711.00 0.00 Signed 2022-08-30 2022-09-05 2022-09-20 2022-10-13 2022-10-31 2022-12-22 2022-11-30 2023-01-20 2022-12-09 2023-02-28 2022-12-21 2023-02-28 2023-01-25 2024-01-25 Based Selection ant pour l’Audit annuel du pr ojet NE-FRSP-NE-342601-CS-CQS / Recrutement d'un consultan Sustainability and adaptive c Consultant Qualifi Open - Internationa Pending Impleme t pour les études de faisabilit IDA / D9250 apacity of the food system’s Post 263,160.00 0.00 2023-04-10 2023-04-20 2023-05-30 2023-07-05 2023-07-27 2024-01-23 cation Selection l ntation é technique de l'aménageme productive base nt des petits périmètres irrig ués NE-FRSP-NE-342663-CS-QCB Sustainability and adaptive c S / Recrutement d'un consult Quality And Cost- Open - Internationa Pending Impleme IDA / D9250 apacity of the food system’s Post 352,632.00 0.00 2023-05-05 2023-05-26 2023-07-09 2023-08-06 2023-09-05 2023-10-10 2023-11-14 2024-11-13 ant chargé des étude techniq Based Selection l ntation productive base ues des seuils de correction NE-FRSP-NE-342655-CS-QCB S / Recrutement d'un consult Sustainability and adaptive c ant pour les études de faisab Quality And Cost- Open - Internationa IDA / D9250 apacity of the food system’s Post 307,000.00 0.00 Under Review 2023-04-15 2023-05-20 2023-05-02 2023-06-15 2023-07-17 2023-07-28 2023-08-18 2023-09-22 2023-12-31 ilité technique et contrôle de Based Selection l productive base s travaux d'une petite retenu e d'eau dans la région de Till abéry NE-FRSP-NE-361744-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 300,000.00 0.00 2023-05-22 2023-05-26 2023-06-12 2023-07-12 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Zinder NE-FRSP-NE-361758-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 300,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Tahoua NE-FRSP-NE-361797-CS-CQS Sustainability and adaptive c / Recrutement d'ONG pour l'é Consultant Qualifi Under Implement IDA / D9250 apacity of the food system’s Post Limited 200,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 laboration d'un Plan GIP (Ges cation Selection ation productive base tion Intégrée du Paysage) da ns la région de Diffa NE-FRSP-NE-361801-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 200,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Tillabéry NE-FRSP-NE-361866-CS-QCB S / Recrutement d’un cabinet pour l’étude de faisabilité (AP Sustainability and adaptive c Quality And Cost- Open - Internationa S/APD/EIES/DAO) et le contrôl IDA / D9250 apacity of the food system’s Post 307,000.00 0.00 Under Review 2023-05-22 2023-05-20 2023-06-12 2023-07-24 2023-08-21 2023-08-31 2023-09-08 2023-10-13 2024-10-12 Based Selection l e des travaux d’aménageme productive base nt des bas-fonds (seuils d’ép andage/petits barrages) dans les régions de Tahoua et INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306128-CS-IND Digital advisory services for Individual Consult Pending Impleme V / Recrutement consultant p IDA / 69980 agriculture and food crisis pr Post Limited 17,422.00 0.00 2022-08-15 2022-08-22 2022-09-05 2022-09-15 2022-11-14 ant Selection ntation our la mise à jour des param evention and management ètres d’analyse NE-FRSP-NE-306140-CS-IND V / Recrutement consultant p Digital advisory services for our identifier/répertorier les f Individual Consult IDA / 69980 agriculture and food crisis pr Post Limited 52,265.00 0.00 Signed 2022-10-10 2022-12-07 2022-10-31 2023-02-22 2022-11-15 2023-04-25 2022-11-16 2022-12-31 ournisseurs et évaluation des ant Selection evention and management besoins de services hydro m étéo, phyto, et agro météo (I ncluant le secteur privée) NE-FRSP-NE-306156-CS-IND V / Recrutement d'un prestat Digital advisory services for Individual Consult Pending Impleme aire pour l'identification des t IDA / 69980 agriculture and food crisis pr Post Limited 17,422.00 0.00 2022-09-15 2022-09-30 2022-10-12 2022-10-15 2022-11-29 ant Selection ntation ypes de services et des mod evention and management alités d'engagement du sect eur privé NE-FRSP-NE-306516-CS-CDS / Service de consultant pour l IDA / 69980 Project Management Post Direct Selection Direct - National 26,132.00 0.00 Completed 2022-08-15 2022-08-19 2022-08-22 2022-09-20 2022-09-07 2022-10-07 2023-03-23 e recrutement du personnel complémentaire du FSRP Page 2 NE-FRSP-NE-306199-CS-IND V / Recrutement d'un Consult Regional food market integr Individual Consult ant pour l’Identification des a IDA / 69980 Post Limited 10,180.00 0.00 Canceled 2022-09-26 2022-10-10 2022-10-31 2022-11-15 2022-12-30 ation and trade ant Selection cteurs dans les chaines de va leur de Niébé et Oignon NE-FRSP-NE-309010-CS-IND V / Recrutement d'un Consult Regional food market integr Individual Consult IDA / 69980 Post Limited 5,500.00 0.00 Canceled 2022-09-26 2022-10-10 2022-10-31 2022-11-01 2022-12-01 ant pour l’Identification des a ation and trade ant Selection cteurs dans la chaine de vale ur Bétail-viande-lait NE-FRSP-NE-342594-CS-IND V / Recrutement d’un Consult Individual Consult ant pour l' Elaboration d'un g IDA / D9250 Project Management Post Limited 17,545.00 0.00 Under Review 2023-02-20 2023-02-22 2023-02-28 2023-03-10 2023-03-13 2023-05-02 ant Selection uide simplifié de gestion fina ncière pour les partenaires NE-FRSP-NE-342595-CS-IND V / Recrutement d'un consult Sustainability and adaptive c Individual Consult Pending Impleme ant pour l'élaboration d'une c IDA / D9250 apacity of the food system’s Post Limited 17,545.00 0.00 2023-04-03 2023-04-13 2023-04-20 2023-04-21 2023-05-31 ant Selection ntation artographie des groupes vuln productive base érables et constitution des b ases de données NE-FRSP-NE-342596-CS-IND Sustainability and adaptive c V / Recrutement d'un consult Individual Consult Pending Impleme IDA / D9250 apacity of the food system’s Post Limited 26,667.00 0.00 2023-04-01 2023-04-10 2023-04-21 2023-04-25 2023-06-14 ant pour l'élaboration de 3 pl ant Selection ntation productive base ans d’aménagement des zon es humides Page 3 PROCUREMENT PLAN (Textual Part) Project information: Papua New Guinea (PNG), PNG Agriculture Commercialization and Diversification Strategy, P-166222 Project Implementation agency: Department of Agriculture and Livestock (DAL); Cocoa Board (CB); and Coffee Industry Corporation (CIC) Date of the Procurement Plan: February 13, 2020 Period covered by this Procurement Plan: February 2020 – to August 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Act 2018, No. 12 of 2018, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. National preferences Eligibility: Eligibility to participate in a procurement process for and to be awarded a Bank financed contract shall be as defined under paragraphs 3.21-3.23 of the Procurement Regulations; accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in the said paragraphs. Foreign bidders shall be eligible to participate in bidding under the same conditions as national bidders. No domestic preference shall be granted in bid evaluation on the basis of bidder’s nationality, origin of goods or services, and/or preferential programs. Registration of bidders as Registration of bidders: condition for bidding Registration shall not be used to assess bidders’ qualifications. A foreign bidder shall not be required to register as a condition for submitting its bid, and a foreign bidder recommended for contract award shall be given a reasonable opportunity to register, with the reasonable cooperation of the Recipient, prior to contract signing. Procurement documents Procurement Documents: Templates of procurement documents, including contract forms, acceptable to the Association shall be used for all procurement financed by the Project. Document Fees Bidding Document Fees: A fee for bidding documents if applied must be reasonable and is to be used to offset the actual costs associated with reproduction of large bidding documents and associated plans and drawings. It is not to be used to generate revenue, or to limit or restrict participation in procurement processes. Bidding document fees are not to be charged for the procurement of consulting services (firms and individual), non-consulting services, or goods. Fraud and Corruption Fraud and Corruption: The procurement documents shall require that bidders submitting bids present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. Negotiations and Cancellation of all bids: cancellation of All bids (or the sole bid if only one bid is procurement process received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank’s prior written concurrence. Complaints Handling Complaints Review Mechanism: The Recipient shall establish and implement an effective, fair and timely complaints review mechanism allowing bidders to complain and to have their complaints handled in a timely manner. Until an adequate complaints review mechanism (as assessed by the Bank) is established the Bank’s review mechanism as set out in the Procurement Regulations will apply. Contract Award Notice Publication of Contract Award Notice: For purposes of Article 36(5) of the Act, within one month from award, a notice of all procurement contract awards shall include, at a minimum as relevant and applicable for each procurement method (a) the name of each bidder that submitted a bid; (b) bid prices as read out at bid opening; (c) evaluated prices of each bid that was evaluated; (d) the names of bidders whose bids were either rejected as nonresponsive or not meeting qualification criteria, or not evaluated, with the reasons thereof; and (e) the name of the winning bidder, the final total contract price, as well as the duration and a summary of the scope of the contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The above captioned conditions also apply when approaching the international market. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable; Works: Not Applicable PROCUREMENT Papua New Guinea : PNG Agriculture Commercialization and Diversification Project PLAN General Information Country: Papua New Guinea 2021-07-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166222 GPN Date: 2020-12-12 Project Name: PNG Agriculture Commercialization and Diversification Project Loan / Credit No: IDA / 64660 Coffee Industry Corporation Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-CIC-321953-GO-RFQ / St andard Multi-Function Printer Institutional Capacity Buildin Request for Quota Single Stage - One E Under Imple , Scanner and Photocopier-un IDA / 64660 Post Limited 15,000.00 0.00 2022-12-26 2023-02-13 2023-01-17 2023-01-31 g tions nvelope mentation der component 1 for CIC's Co ffee Research Institute Librar y in Aiyura, EHP. PG-CIC-361661-GO-RFQ / Pu Institutional Capacity Buildin Request for Quota Single Stage - One E Under Imple rchase of Factory Machines-P IDA / 64660 Post Limited 87,000.00 0.00 2023-06-19 2023-06-07 2023-08-14 2024-08-08 g tions nvelope mentation anga, Sub-station (dry coffee mill) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PG-CIC-236458-CS-INDV / Pr Project Management and Mo Individual Consult IDA / 64660 Prior Open 540,000.00 0.00 Canceled 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 oject Manager, Coffee PMU nitoring and Evaluation ant Selection PG-CIC-236473-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Open 276,000.00 95,044.72 Signed 2021-06-01 2021-12-03 2021-07-20 2022-03-01 2021-08-10 2022-02-28 2021-09-14 2022-03-05 2022-03-13 nior Procurement Officer, Cof nitoring and Evaluation ant Selection fee PMU PG-CIC-236469-CS-INDV / M Project Management and Mo Individual Consult onitoring, Evaluation and Sur IDA / 64660 Post Open 220,000.00 92,404.62 Terminated 2021-06-01 2021-12-03 2021-07-20 2022-03-01 2021-08-10 2022-03-01 2021-09-14 2022-03-01 2022-03-13 nitoring and Evaluation ant Selection vey Officer (MESO) PG-CIC-236474-CS-INDV / Pr Individual Consult oductive Partnership Coordin IDA / 64660 Productive Partnerships Prior Open 360,000.00 0.00 Signed 2021-08-05 2022-01-05 2021-09-23 2022-07-28 2021-10-14 2023-03-14 2021-11-18 2023-05-21 2022-05-17 ant Selection ator, Coffee PMU PG-CIC-248926-CS-INDV / En Project Management and Mo Individual Consult IDA / 64660 Post Open 210,000.00 40,636.99 Signed 2021-08-18 2021-12-03 2021-10-06 2022-03-11 2021-10-27 2022-03-14 2021-12-01 2022-03-17 2022-05-30 vironmental and Social Office nitoring and Evaluation ant Selection r PG-CIC-260472-CS-INDV / Pr Project Management and Mo Individual Consult oject Manager, Coffee Project IDA / 64660 Prior Open 424,000.00 0.00 Signed 2021-10-29 2021-11-08 2021-12-17 2022-07-19 2022-01-07 2022-08-17 2022-02-11 2023-05-08 2022-08-10 nitoring and Evaluation ant Selection Management Unit PG-CIC-236468-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Prior Open 326,000.00 0.00 Canceled 2021-08-05 2021-09-23 2021-10-14 2021-11-18 2022-05-17 nior Finance Officer, Coffee P nitoring and Evaluation ant Selection MU PG-CIC-236481-CS-INDV / Se Individual Consult IDA / 64660 Agriculture Feeder Roads Prior Open 377,000.00 0.00 Canceled 2021-08-05 2021-09-23 2021-10-14 2021-11-18 2022-05-17 nior Engineer, Coffee PMU ant Selection PG-CIC-266769-CS-INDV / Co Individual Consult IDA / 64660 Agriculture Feeder Roads Post Open 295,000.00 0.00 Signed 2021-12-10 2022-11-24 2022-01-28 2023-05-22 2022-02-18 2023-06-12 2022-03-25 2025-12-04 ffee PMU Senior Engineer ant Selection PG-CIC-266768-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Open 240,000.00 86,607.73 Terminated 2021-12-13 2021-12-07 2022-02-09 2022-03-14 2022-03-02 2022-03-14 2022-04-06 2022-03-15 2025-12-16 nior Finance Officer, Coffee P nitoring and Evaluation ant Selection MU PG-CIC-288418-CS-INDV / M Project Management and Mo Individual Consult onitoring, Evaluation and Sur IDA / 64660 Post Limited 220,000.00 73,308.35 Terminated 2022-04-11 2022-04-07 2022-04-25 2022-04-12 2022-05-09 2022-04-22 2022-06-06 2022-04-21 2023-02-11 nitoring and Evaluation ant Selection vey Officer (MESO) PG-CIC-288419-CS-INDV / Se Project Management and Mo Individual Consult IDA / 64660 Post Limited 240,000.00 116,086.28 Signed 2022-04-11 2022-04-07 2022-04-16 2022-04-11 2022-04-30 2022-04-14 2022-05-28 2022-04-24 2023-02-02 nior Finance Officer, Coffee P nitoring and Evaluation ant Selection MU PG-CIC-289818-CS-INDV / Se Individual Consult IDA / 64660 Productive Partnerships Post Open 167,000.00 0.00 Terminated 2022-05-16 2022-05-16 2022-06-18 2022-09-30 2022-06-28 2022-09-30 2022-07-13 2023-01-09 nior Partnership Officer - East ant Selection ern Zone PG-CIC-289829-CS-INDV / Se Individual Consult IDA / 64660 Productive Partnerships Post Open 167,000.00 0.00 Signed 2022-05-16 2022-05-16 2022-06-14 2022-10-04 2022-06-24 2022-10-04 2022-07-09 2023-01-05 nior Partnership Officer - Wes ant Selection tern Zone Page 1 PG-CIC-290477-CS-INDV / Inf Project Management and Mo Individual Consult ormation Technology & Mana IDA / 64660 Post Open 170,520.00 0.00 Signed 2022-05-16 2022-05-16 2022-06-14 2022-10-27 2022-06-24 2022-10-27 2022-07-20 2023-01-16 nitoring and Evaluation ant Selection gement Information Systems Officer PG-CIC-289832-CS-INDV / Fi Project Management and Mo Individual Consult IDA / 64660 Post Open 97,440.00 0.00 Signed 2022-05-16 2022-05-20 2022-06-14 2022-10-05 2022-06-19 2022-10-05 2022-07-15 2023-01-11 nance and Administration Off nitoring and Evaluation ant Selection icer PG-CIC-307536-CS-INDV / M Project Management and Mo Individual Consult IDA / 64660 Post Open - National 220,000.00 0.00 Signed 2022-08-08 2022-08-15 2022-09-26 2022-11-03 2022-10-17 2022-10-03 2022-11-21 2025-12-25 onitoring, Evaluation and Sur nitoring and Evaluation ant Selection vey Officer PG-CIC-321943-CS-CDS / Co Institutional Capacity Buildin Direct - Internation nsultant-ToT Training for PNG IDA / 64660 Post Direct Selection 6,000.00 0.00 Signed 2022-12-12 2022-10-18 2022-12-27 2023-01-13 2023-02-07 2023-02-12 g al Coffee Extension Manuals PG-CIC-328546-CS-INDV / Pa Individual Consult Under Implement IDA / 64660 Productive Partnerships Post Open - National 91,350.00 0.00 2022-12-12 2022-11-22 2023-01-14 2023-01-19 2023-01-29 2025-01-18 rtnership Officer, Eastern Zo ant Selection ation ne. PG-CIC-328548-CS-INDV / Pa Individual Consult Under Implement IDA / 64660 Productive Partnerships Post Open - National 91,350.00 0.00 2022-12-12 2022-11-22 2023-01-05 2023-01-10 2023-01-29 2025-01-18 rtnership Officer, Western Zo ant Selection ation ne PG-CIC-328557-CS-INDV / Ad Project Management and Mo Individual Consult Under Implement IDA / 64660 Post Limited 42,630.00 0.00 2022-12-12 2022-11-25 2022-12-26 2022-12-31 2023-01-10 2023-03-23 ministration Officer, Western nitoring and Evaluation ant Selection ation Zone PG-CIC-328553-CS-INDV / Fi Project Management and Mo Individual Consult IDA / 64660 Post Open - National 85,260.00 0.00 Canceled 2022-12-12 2023-01-05 2023-01-10 2023-01-20 2025-01-09 nance & Admin Officer-Gorok nitoring and Evaluation ant Selection a PG-CIC-335414-CS-INDV / Fi Project Management and Mo Individual Consult Under Implement nance & Procurement Officer IDA / 64660 Post Open - National 84,877.00 0.00 2023-01-30 2023-01-20 2023-03-04 2023-03-09 2023-03-19 2025-03-18 nitoring and Evaluation ant Selection ation -Goroka/Panga PG-CIC-331087-CS-INDV / M Individual Consult SME Development Officer (Mi IDA / 64660 Productive Partnerships Post Open - National 125,283.00 0.00 Signed 2023-01-23 2023-01-23 2023-02-25 2023-06-16 2023-03-02 2023-06-16 2023-03-12 2025-12-26 ant Selection cro Small Medium Enterprise) PG-CIC-363589-CS-INDV / Se Project Management and Mo Individual Consult Under Implement nior Partnership Officer, East IDA / 64660 Post Limited 167,000.00 0.00 2023-05-30 2023-06-01 2023-06-04 2023-06-25 2023-07-30 2024-01-26 nitoring and Evaluation ant Selection ation ern Zone (Replacement) Page 2 PROCUREMENT PLAN (Textual Part) Project information: Mauritania, Western Africa Regional Digital Integration Program (WARDIP) [P176932] Project Implementation agency: Ministere de la Transition Numerique, de l’Innovation et de la Modernisation de l’Administration (MTNIMA) Date of the Procurement Plan: December 22, 2021 Period covered by this Procurement Plan: December 22, 2021 - November 30, 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in “le décret N° 2020-122 du 06 octobre 2020, modifiant et complétant certaines dispositions du décret N° 2017-126 du 02 novembre 2017, abrogeant et replaçant les dispositions des décrets d’applications de la loi N° 2010-044 du 22 juillet 2010”, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Other Relevant Procurement Information. PROCUREMENT Western and Central Africa : Western Africa Regional Digital Integration Program SOP1 PLAN General Information Country: Western and Central Africa 2023-06-01 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176932 GPN Date: Project Name: Western Africa Regional Digital Integration Program SOP1 Loan / Credit No: IDA / V4020 PCU Western Africa Regional Digital Integration Program Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WARDIP-F - 016-2023 / Mobil Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl iário de escritório para a Unid IDA / V4020 ement and Implementation Post Open - National 0.00 2023-06-26 2023-08-21 2024-02-17 tions nvelope ementation ade de Gestão Support WARDIP-F - 017-2023 / IT an Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl IDA / V4020 Post Open - National 0.00 2023-06-28 2023-08-23 2024-02-19 d Office Equipment ement and Implementation tions nvelope ementation Support WARDIP-F - 018-2023 / Stati Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl IDA / V4020 Post Open - National 0.00 2023-07-03 2023-08-28 2024-02-24 onary ement and Implementation tions nvelope ementation Support WARDIP-F - 019-2023 / Com Component 5. Project Manag Request for Quota Single Stage - One E Pending Impl munication Devices (telepho IDA / V4020 ement and Implementation Post Open - National 0.00 2023-07-04 2023-08-29 2024-02-25 tions nvelope ementation ne, router, etc) Support NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual WARDIP-C - 006-2023 / Lega Component 1. Enabling envi l analysis of missing /outdate Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-06-30 2023-07-21 2023-09-03 2023-10-01 2023-10-31 2023-12-05 2024-01-09 2025-01-08 d laws and regulations and re Based Selection l ntation nt of a continental SDM commendations for needed r eforms WARDIP-C - 007-2023 / Stud y of the national backbone: F Component 1. Enabling envi easibility (technical, financial Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-06-19 2023-07-10 2023-08-23 2023-09-20 2023-10-20 2023-11-24 2023-12-29 2024-12-28 and governance), preparatio Based Selection l ntation nt of a continental SDM n of tender documents (DAO) , monitoring and evaluation ( M&E). WARDIP-C - 008-2023 / Stud y of (i) redundancy of interna Component 1. Enabling envi tional connectivity, (ii) sale of Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-06-27 2023-07-18 2023-08-31 2023-09-28 2023-10-28 2023-12-02 2024-01-06 2025-01-05 excess capacity to neighbors Based Selection l ntation nt of a continental SDM , (iii) improvement of SCGB g overnance and (iv) improvem ent of FAU management WARDIP-C - 009-2023 / Feasi bility study for establishing a Component 3. Data Market Quality And Cost- Open - Internationa Under Implement n NREN and connecting it to t IDA / V4020 Development and Integratio Post 0.00 2023-07-15 2023-06-20 2023-08-05 2023-06-22 2023-09-18 2023-10-16 2023-11-15 2023-12-20 2024-01-24 2025-01-23 Based Selection l ation he Western and Central Afric n a Research and Education Ne twork (WACREN) WARDIP-C - 010-2023 / Stud y on government needs for a Security Operations Center ( Quality And Cost- Open - Internationa Under Implement SOC), Computer Emergency IDA / V4020 Component 6. CERC Post 0.00 2023-07-14 2023-06-20 2023-08-04 2023-06-22 2023-09-17 2023-10-15 2023-11-14 2023-12-19 2024-01-23 2025-01-22 Based Selection l ation Response Team (CERT) and n ational cloud, including a dat a sharing and infrastructure analysis and DAO WARDIP-C - 011-2023 / Gap analysis on (i) demand for di gital skills in the public and p Component 3. Data Market rivate sectors; (ii) current su Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 Development and Integratio Post 0.00 2023-07-17 2023-08-07 2023-09-20 2023-10-18 2023-11-17 2023-12-22 2024-01-26 2025-01-25 pply of digital skills in the pri Based Selection l ntation n vate sector and public sector ; and (iii) suggestions on how to expand or strengthen exis ting and future programs and courses t WARDIP-C - 012-2023 / Gap analysis of the entrepreneurs Component 4. Online Market Quality And Cost- Open - Internationa hip ecosystem and needs of IDA / V4020 Development and Integratio Post 0.00 Under Review 2023-07-12 2023-06-22 2023-08-02 2023-09-15 2023-10-13 2023-11-12 2023-12-17 2024-01-21 2025-01-20 Based Selection l digital entrepreneurs and rec n ommended actions (DAO) WARDIP-C - 013-2023 / Detai Component 3. Data Market led analysis of digital payme Quality And Cost- Open - Internationa IDA / V4020 Development and Integratio Post 0.00 Under Review 2023-07-30 2023-06-22 2023-08-20 2023-10-03 2023-10-31 2023-11-30 2024-01-04 2024-02-08 2025-02-07 nts and financial digital servi Based Selection l n ces infrastructure WARDIP-C - 014-2023 / Feasi bility study for the developm Component 2. Connectivity Quality And Cost- Open - Internationa ent of an interoperability fra IDA / V4020 Market Development and Int Post 0.00 Under Review 2023-07-31 2023-06-22 2023-08-21 2023-10-04 2023-11-01 2023-12-01 2024-01-05 2024-02-09 2025-02-08 Based Selection l mework and platform, as well egration as digitalization of the main public services and DAO Page 1 WARDIP-C - 015-2023 / Tech nical assistance to the Minist Component 1. Enabling envi ry of Transport and Communi Quality And Cost- Open - Internationa Pending Impleme IDA / V4020 ronment for the establishme Post 0.00 2023-07-24 2023-08-14 2023-09-27 2023-10-25 2023-11-24 2023-12-29 2024-02-02 2025-02-01 cations for the development Based Selection l ntation nt of a continental SDM of human and institutional ca pacity in terms of digital tran sformation. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT (P173989) Project Implementation agency: MOH – Ministry of Health Date of the Procurement Plan: June 30th, 2020 Period covered by this Procurement Plan: From July 2020 to December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the national procurement legislation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: The corresponding Procurement Documents must be acceptable to the World Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations and the corresponding Procurement Documents must be acceptable to the World Bank. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: “Not Applicable”; Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is “Not Applicable” Other Relevant Procurement Information. Since the Project triggers Paragraph 12 of the IPF Policy, which relates to Projects in Situations of Urgent Need of Assistance or Capacity Constraints, the GoRTT and the Bank have agreed that the MOH would directly engage PAHO/WHO to source all PPEs, pharmaceuticals, medical supplies, equipment and vaccines the Project needs to respond the COVID-19 pandemic, given PAHO/WHO’s rapid mobilization on the ground and expertise in responding emergency situations like the current one. When entering into a contract with PAHO/WHO, the MOH will use a standard form of agreement previously negotiated and approved by the Bank. PROCUREMENT Trinidad and Tobago : Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT PLAN General Information Country: Trinidad and Tobago 2021-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173989 GPN Date: 2021-05-10 Project Name: Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT Loan / Credit No: IBRD / 91570 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-232028-GO-RFB / Pr ocurement/supply of COVID- Emergency Response to CO IBRD / 91570 Prior Direct Selection Direct 11,617,613.85 0.00 Signed 2021-05-16 2021-05-20 2021-05-23 2021-06-01 2021-06-27 2022-06-22 19 related PPEs, pharmaceuti VID-19 cals, medical supplies and eq uipments TT-MOH-343910-GO-RFQ / P Project Management and Mo Request for Quota Single Stage - One E IBRD / 91570 Post Limited 18,680.00 0.00 Signed 2023-02-22 2022-12-28 2023-04-19 2023-10-16 urchasing of ICT Equipment f nitoring tions nvelope or the PIU TT-MOH-348518-GO-DIR / Pu Support to COVID-19 Vaccin Direct - Internation Under Revie IBRD / 91570 Prior Direct Selection 7,500,000.00 0.00 2023-03-09 2023-03-14 2023-04-18 2023-10-15 rchasing of COVID-19 Vaccin ation Campaign al w es TT-MOH-348548-GO-DIR / Pu Support to COVID-19 Vaccin Direct - Internation Under Revie IBRD / 91570 Prior Direct Selection 173,432.00 0.00 2023-03-09 2023-03-14 2023-04-18 2023-10-15 rchasing of COVID-19 vaccin ation Campaign al w es TT-MOH-348554-GO-DIR / Th Project Management and Mo e purchasing of SAGE 50 Acc IBRD / 91570 Post Direct Selection Direct - National 4,412.00 0.00 Signed 2023-03-09 2023-03-17 2023-03-14 2023-03-03 2023-04-18 2023-10-15 nitoring ounting Software for the PIU Team NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-365711-CS-LCS / Fi nancial Audit Services for the COVID 19 Emergency Respo Project Management and Mo Least Cost Selecti Under Implement IBRD / 91570 Post Open - National 60,000.00 0.00 2023-06-06 2023-05-25 2023-06-27 2023-08-10 2023-09-07 2023-10-07 2023-11-11 2023-12-16 2024-06-13 nse Project for the periods M nitoring on ation arch 15, 2021 to September 30, 2023, October 1, 2023 to June 30, 2024. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-IC-1 / PIU Project Ma Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-08 2021-08-28 2022-02-24 2022-04-14 2023-04-14 nager nitoring ant Selection TT-MOH-IC-3 / PIU Financial Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-09 2021-08-28 2022-02-24 2022-04-14 2023-04-14 Management Officer nitoring ant Selection TT-MOH-IC-4 / PIU Environm Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-09 2021-08-28 2022-02-24 2022-04-14 2023-04-14 ental and Social Specialist nitoring ant Selection TT-MOH-IC-2 / PIU Procurem Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-10-20 2021-08-28 2022-02-24 2022-04-14 2023-04-14 ent Officer nitoring ant Selection Page 1 PROCUREMENT PLAN (Textual Part) Project information: Pakistan Pandemic Response Effectiveness Project (P173796) Project Implementation agency: (i) Ministry of National Health Services, Regulations and Coordination; (ii) National Disaster Management Authority (iii) Benazir Income Support Programme and; (iv) Provincial EPI Cells Date of the Procurement Plan: April 13, 2020 Period covered by this Procurement Plan: April-2020 to June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Rules 2004, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. are applicable Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : PANDEMIC RESPONSE EFFECTIVENESS IN PAKISTAN PLAN General Information Country: Pakistan 2022-06-20 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173796 GPN Date: 2020-04-20 Project Name: PANDEMIC RESPONSE EFFECTIVENESS IN PAKISTAN Loan / Credit No: IDA / 65900 Ministry of Federal Education and Professional Training Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-MOFEPT-300476-GO-RFB / Procurement of relevant eq uipment for AIOU on lot-wise basis for transmission of DL c hannels. The categories are: Component 2. Mitigation of Open - Internationa Single Stage - One E 1. Earth Station Uplink & Ser IDA / 65900 Post Request for Bids 1,480,000.00 0.00 Canceled 2022-09-19 2023-02-23 2022-09-22 2023-02-26 2022-11-07 2023-03-17 2022-11-21 2022-11-25 2023-05-31 Disruptive Impacts l nvelope ver Development 2. Upgradation of Existing Fa cilities 3. Establishment of Studio 4. Post-Production Assets 3. Up PK-MOFEPT-327308-GO-RFB / Procurement of Handheld D Component 2. Mitigation of Single Stage - One E evices (Chromebooks) for stu IDA / 65900 Prior Request for Bids Open - National 3,250,000.00 0.00 Canceled 2022-12-12 2023-02-13 2022-12-16 2023-02-13 2023-01-17 2023-03-08 2023-01-27 2023-01-31 2023-06-30 Disruptive Impacts nvelope dents and teachers under Dis tance Learning initiatives of MOFEPT. PK-MOFEPT-327311-GO-RFB / Hiring of a firm to provide e Component 2. Mitigation of Single Stage - One E IDA / 65900 Prior Request for Bids Open - National 1,700,000.00 0.00 Canceled 2022-12-05 2023-03-10 2022-12-09 2023-04-03 2023-01-10 2023-04-17 2023-01-20 2023-01-31 2023-06-30 nd-to-end implementation of Disruptive Impacts nvelope "School on Wheels" activity. PK-MOFEPT-330116-GO-RFB / Establishment of 400 Smart Component 3. Implementati Classrooms in selected instit Single Stage - One E Under Imple IDA / 65900 on Management and Monitor Post Request for Bids Open - National 1,250,000.00 0.00 2022-12-16 2023-02-21 2022-12-19 2023-01-18 2023-04-10 2023-01-27 2023-05-08 2023-01-31 2023-06-30 utions of Islamabad Capital T nvelope mentation ing and Evaluation erritory (ICT), Azad, Jammu & Kashmir (AJK) and Gilgit-Balti stan (GB). PK-MOFEPT-330115-GO-RFB / Establishment of Virtual Tea Component 3. Implementati Single Stage - One E cher training platform for tea IDA / 65900 on Management and Monitor Post Request for Bids Open - National 975,000.00 0.00 Canceled 2022-12-15 2022-12-21 2023-01-20 2023-01-27 2023-01-31 2023-06-30 nvelope chers including development ing and Evaluation of a dedicated Mobile App an d Website PK-MOFEPT-332164-GO-DIR / Hiring of "PTCL" for develop ment of a dedicated Mobile A Component 3. Implementati Under Imple pp and Website as an e-learn IDA / 65900 on Management and Monitor Post Direct Selection Direct - National 650,000.00 0.00 2022-12-26 2023-01-20 2022-12-30 2023-03-06 2023-01-13 2023-06-30 mentation ing solution for teachers and ing and Evaluation students including Virtual Te acher training (VTT) platform and LMS. PK-MOFEPT-332166-GO-RFB Component 3. Implementati / Sourcing of Teachers' Traini Single Stage - One E Under Imple IDA / 65900 on Management and Monitor Post Request for Bids Open - National 190,000.00 0.00 2022-12-30 2023-02-16 2023-01-05 2023-01-26 2023-03-07 2023-02-10 2023-02-20 2023-05-31 ng Content for Virtual Teache nvelope mentation ing and Evaluation rs' Training (VTT) module PK-MOFEPT-335516-GO-RFQ Component 4. Contingent E / Refurbishment of Two Existi Request for Quota Single Stage - One E IDA / 65900 mergency Response Compo Post Open - National 65,000.00 0.00 Signed 2023-01-12 2023-02-01 2023-03-10 ng Buses at Federal Director tions nvelope nent ate of Education for Conversi on into Mobile Schools. PK-MOFEPT-344018-GO-RFB / Procurement of Distance Le Component 2. Mitigation of Single Stage - One E IDA / 65900 Prior Request for Bids Open - National 1,806,000.00 0.00 Canceled 2023-02-20 2023-02-23 2023-03-14 2023-03-21 2023-03-27 2023-06-30 arning Content for Grade KG Disruptive Impacts nvelope to Grade 12 under PREP. PK-MOFEPT-349937-GO-RFB / Procurement and Developm Component 2. Mitigation of Single Stage - One E Under Imple IDA / 65900 Prior Request for Bids Open - National 1,806,000.00 0.00 2023-03-17 2023-04-07 2023-03-21 2023-04-09 2023-04-11 2023-04-17 2023-04-21 2023-06-30 ent of Distance Learning Con Disruptive Impacts nvelope mentation tent for Grades KG-12 under PREP. PK-MOFEPT-355504-GO-RFB / Establishment of Television Channels on Turnkey Basis w ith Provisioning and Commiss Component 2. Mitigation of Single Stage - One E IDA / 65900 Prior Request for Bids Open - National 5,000,000.00 0.00 Canceled 2023-04-11 2023-04-17 2023-04-13 2023-04-17 2023-04-28 2023-05-04 2023-05-03 2023-05-08 2023-06-30 ioning of Hardware, Software Disruptive Impacts nvelope and Installation of All the Req uired Equipment, Accessories , Electrical & Access Controls at Allama Iqbal Open Univers ity (AIOU) PK-MOFEPT-362836-GO-DIR / Procurement of Chromeboo Component 2. Mitigation of Direct - Internation IDA / 65900 Prior Direct Selection 2,750,000.00 0.00 Canceled 2023-05-22 2023-05-28 2023-05-23 2023-06-01 2023-05-29 2023-06-30 ks for Supplies at School Lev Disruptive Impacts al el across Pakistan. PK-MOFEPT-366470-GO-RFB Component 4. Contingent E / Procurement of LED Screen Single Stage - One E Under Revie IDA / 65900 mergency Response Compo Prior Request for Bids Limited 2,666,667.00 0.00 2023-06-10 2023-06-13 2023-06-11 2023-06-16 2023-06-19 2023-06-20 2023-06-30 s for Federal Directorate of E nvelope w nent ducation (FDE) Schools PK-MOFEPT-366476-GO-RFB Component 4. Contingent E / Procurement of Laptops (lot Single Stage - One E Under Revie IDA / 65900 mergency Response Compo Prior Request for Bids Limited 3,312,781.00 0.00 2023-06-10 2023-06-13 2023-06-11 2023-06-16 2023-06-19 2023-06-20 2023-06-30 -1), Desktops (lot-2) and Clic nvelope w nent kers(lot-3) for FDE schools. Page 1 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-MOFEPT-326600-NC-RFB / Hiring of a Survey Firm for Component 2. Mitigation of Single Stage - One E IDA / 65900 Post Request for Bids Open - National 264,000.00 0.00 Signed 2022-11-21 2022-11-15 2022-11-21 2022-12-07 2022-12-07 2022-12-12 2023-01-04 2022-12-15 2023-03-31 Administration of Summative Disruptive Impacts nvelope Testing and Surveys in KPK P ublic Schools PK-MOFEPT-329384-NC-DIR / Component 4. Contingent E Engagement with PTV for Tra IDA / 65900 mergency Response Compo Post Direct Selection Direct - National 850,000.00 0.00 Signed 2022-12-01 2022-12-01 2022-12-02 2022-11-30 2022-12-05 2023-06-30 nsmission of "Tele School" nent PK-MOFEPT-344017-NC-RFQ Component 3. Implementati / Hiring of a firm to run a ded Request for Quota Single Stage - One E IDA / 65900 on Management and Monitor Post Open - National 74,600.00 0.00 Signed 2023-02-21 2023-02-28 2023-03-31 icated communication campa tions nvelope ing and Evaluation ign for launch of MoFEPT's Te leschool App. PK-MOFEPT-357389-NC-RFQ Component 3. Implementati Request for Quota Single Stage - One E / Communication & Dissemin IDA / 65900 on Management and Monitor Post Open - National 67,685.00 0.00 Signed 2023-05-02 2023-05-15 2023-06-30 tions nvelope ation Campaign under PREP. ing and Evaluation PK-MOFEPT-363615-NC-RFQ / Hiring of fIrm to provide logi Component 3. Implementati Request for Quota Single Stage - One E Under Imple stics, event management an IDA / 65900 on Management and Monitor Post Open - National 80,000.00 0.00 2023-05-26 2023-06-08 2023-06-30 tions nvelope mentation d communications services f ing and Evaluation or the "National Learning Co nference" CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-MOFEPT-325096-CS-CQS / Hiring of firm to supervise s Component 2. Mitigation of Consultant Qualifi ourcing and installation of rel IDA / 65900 Post Open - National 225,000.00 0.00 Signed 2022-11-04 2022-11-04 2022-11-24 2022-12-05 2022-12-15 2022-12-12 2023-01-04 2022-12-17 2023-06-30 Disruptive Impacts cation Selection evant equipment and facilitie s at AIOU for running 04 dedi cated channels. PK-MOFEPT-326076-CS-QCB Component 1. Emergency C S / Communications and Outr Quality And Cost- IDA / 65900 OVID-19 Preparedness and R Prior Open - National 1,650,000.00 0.00 Canceled 2022-11-11 2022-11-16 2022-11-30 2022-12-12 2023-04-06 2023-01-11 2023-03-27 2023-01-20 2023-04-12 2023-01-30 2023-01-31 2023-06-30 each Campaign under Pande Based Selection esponse mic Response Effectiveness P roject (PREP). PK-MOFEPT-326940-CS-CQS / Hiring of Consulting Service Component 3. Implementati Consultant Qualifi s for "Rapid Assessment and IDA / 65900 on Management and Monitor Post Open - National 60,000.00 0.00 Canceled 2022-12-05 2022-12-23 2023-01-06 2023-01-12 2023-01-16 2023-06-30 cation Selection Mapping" to provide learning ing and Evaluation about MoFEPT learning conti nuation activities PK-MOFEPT-326943-CS-QCB S / Procurement and develop Component 2. Mitigation of Quality And Cost- IDA / 65900 Prior Open - National 1,806,000.00 0.00 Canceled 2022-12-05 2022-12-23 2023-01-07 2023-02-07 2023-02-15 2023-02-23 2023-02-26 2023-06-30 ment of distance learning co Disruptive Impacts Based Selection ntent for Grade KG-Grade 12 under PREP. PK-MOFEPT-300484-CS-LCS / Hiring of firm to supervise so Component 2. Mitigation of Least Cost Selecti IDA / 65900 Post Open - National 225,000.00 0.00 Canceled 2022-09-15 2022-09-16 2022-10-06 2022-10-14 2022-10-17 2022-10-17 2022-10-17 2022-10-21 2023-06-30 urcing and installation of rele Disruptive Impacts on vant equipment and facilities at AIOU. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-MOFEPT-316197-CS-CDS / HIRING OF ALLAMA IQBAL O Component 3. Implementati PEN UNIVERSIT (AIOU) FOR S IDA / 65900 on Management and Monitor Post Direct Selection Direct - National 300,000.00 0.00 Signed 2022-09-16 2022-08-17 2022-09-21 2022-08-10 2022-09-27 2023-06-30 USTAINIBILITY OF DISTANCE ing and Evaluation LEARNING INITIATIVES INCLU DING TELE-SCHOOL. PK-MOFEPT-300488-CS-INDV Component 1. Emergency C Individual Consult IDA / 65900 Post Open 66,000.00 0.00 Canceled 2022-06-24 2022-07-01 2022-07-26 2022-07-28 2022-08-01 2023-06-30 / Hiring of "Project Director" OVID-19 Preparedness and R ant Selection esponse PK-MOFEPT-335676-CS-INDV Component 3. Implementati / Hiring of "Project Coordinati Individual Consult Under Implement IDA / 65900 on Management and Monitor Post Open - National 26,500.00 0.00 2023-01-12 2023-01-18 2023-01-27 2023-02-03 2023-01-30 2023-02-07 2023-01-31 2023-06-30 on Consultant" for Program C ant Selection ation ing and Evaluation oordination Unit, M/o FE & PT . Page 2 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Desert Locust Response Project, P173702 Project Implementation agency: Ministry of Agriculture, Ethiopia Date of the Procurement Plan: April 6, 2012 Period covered by this Procurement Plan: April 2020 to March 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable For national open competitive procurement the following requirement apply: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts; e. contracts with an appropriate allocation of responsibilities, risks, and liabilities; f. publication of contract award information; g. rights for the Bank to review procurement documentation and activities; h. an effective complaints mechanism; and i. maintenance of records of the Procurement Process. cable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Since the project is an emergency response project the provisions of Procurement in Situations of Urgent Need of Assistance shall apply. PROCUREMENT Eastern and Southern Africa : Emergency Locust Response Program PLAN General Information Country: Eastern and Southern Africa 2020-05-11 Bank’s Approval Date of the Original Procurement Plan: 2023-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173702 GPN Date: 2020-12-03 Project Name: Emergency Locust Response Program Loan / Credit No: IDA / 66480, IDA / 66510, IDA / D6360 Ministry of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Quota ET-MOA-325738-NC-RFQ / R Surveillance and Control Me Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-06-0 IDA / 66510 Post Limited 200,000.00 0.00 2023-03-23 2023-04-19 enovation of chemical store asures tions nvelope s (Emergency) SP lementation 3 D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-172079-GO-DIR / Fi Coordination and Early Warn IDA / 66480 Post Direct Selection Direct 450,000.00 1,056,832.73 Completed 2020-05-08 2020-07-10 2020-05-13 2020-05-27 2020-05-27 2020-08-18 2020-06-16 2021-12-25 eld Vehicles (Pickups) ing Preparedness ET-MOA-178452-GO-DIR / A Livelihoods Protection and R mhara feed purchase 318 qtl IDA / 66510 Post Direct Selection Direct 143,100.00 0.00 Canceled 2020-06-15 2020-06-20 2020-07-25 2020-07-30 ehabilitation s from Amhara Seed Enterpri se ET-MOA-184656-GO-DIR / Eq uipment for Desert Locust Re Surveillance and Control Me Under Revie IDA / 66510 Prior Direct Selection Direct 7,800,000.00 0.00 2020-07-19 2020-07-24 2020-08-12 2020-08-27 sponse Project (Knapsacks U asures w LV sprayers, PPE, Vehicle mo unted sprayers) ET-MOA-242623-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 143,100.00 0.00 2021-07-17 2021-08-14 2021-09-04 mhara Region, Seed for Anim ehabilitation tions nvelope ementation al Feed ET-MOA-248518-GO-RFQ / P Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl urchase of animal feed seed IDA / 66510 Post Limited 130,000.00 0.00 2021-08-30 2021-10-04 2021-11-03 ehabilitation tions nvelope ementation (Alfalfa and Sudan grass) ET-MOA-184728-GO-DIR / Dr Surveillance and Control Me Pending Impl IDA / 66510 Post Direct Selection Direct 50,000.00 0.00 2022-02-14 2022-02-19 2022-03-15 2022-03-28 ones for survey asures ementation ET-MOA-175937-GO-RFQ / Af Livelihoods Protection and R Pending Impl ar purchase of fertilizer 3088 IDA / 66510 Post Direct Selection Direct 200,720.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-03 ehabilitation ementation Qtl from EARC ET-MOA-175930-GO-RFQ / A mhara procurement of fertiliz Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 746,200.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-04 er 11480 Qtl from Amhara Se ehabilitation ementation ed Enterprise (ASE) ET-MOA-178443-GO-DIR / 14 Livelihoods Protection and R Pending Impl 35 Qtls of seed from Amhara IDA / 66510 Post Direct Selection Direct 154,980.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-04 ehabilitation ementation Seed Enterprise (ASE) ET-MOA-175925-GO-RFQ / Ti Livelihoods Protection and R Pending Impl gray region procurement of f IDA / 66510 Prior Direct Selection Direct 3,685,240.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-04 ehabilitation ementation ertilizer 56696 Qtls from EAR C ET-MOA-178446-GO-DIR / Or Livelihoods Protection and R Pending Impl omia Seed purchase 2455 Qtl IDA / 66510 Post Direct Selection Direct 265,140.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-01 ehabilitation ementation s from Oromia Seed Enterpris e (OSE) ET-MOA-178447-GO-DIR / SN Livelihoods Protection and R Pending Impl NP seed purchase 304 Qtls fr IDA / 66510 Post Direct Selection Direct 32,832.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-03-31 ehabilitation ementation om Southern Seed Enterprise (SSE) ET-MOA-178440-GO-DIR / Ti Livelihoods Protection and R Pending Impl gray seed purchase 7087 Qtl IDA / 66510 Post Direct Selection Direct 765,396.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-09-22 ehabilitation ementation s of Seed from EARC ET-MOA-178448-GO-DIR / Af Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 41,688.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-03 ar seed purchase 386 Qtls fro ehabilitation ementation m EARC ET-MOA-178449-GO-DIR / So Livelihoods Protection and R mali seed purchase 7,815 Qtl IDA / 66510 Post Direct Selection Direct 844,020.00 600,365.32 Completed 2022-02-14 2020-09-11 2022-02-19 2020-09-17 2022-03-26 2020-10-27 2022-04-05 2021-06-05 ehabilitation s from EARC ET-MOA-178450-GO-DIR / D Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 20,844.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-01 D seed purchase 193 qtls fro ehabilitation ementation m EARC ET-MOA-178453-GO-DIR / Or Livelihoods Protection and R Pending Impl omia feed seed purchase 160 IDA / 66510 Post Direct Selection Direct 720,000.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-09-22 ehabilitation ementation 0 qtls from Oromia seed ente rprise ET-MOA-178454-GO-DIR / SN Livelihoods Protection and R Under Imple NP feed seeds purchase 125 IDA / 66510 Post Direct Selection Direct 562,500.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-03 ehabilitation mentation 0 qtls from Southern seed en terprise (SSE) ET-MOA-178456-GO-DIR / Af Livelihoods Protection and R Pending Impl ar feed seeds purchase 2500 IDA / 66510 Post Direct Selection Direct 1,125,000.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-03 ehabilitation ementation qtls from EARC ET-MOA-178467-GO-DIR / So Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 1,080,000.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-03 mali feed seeds 2400 Qtls fro ehabilitation ementation m EARC ET-MOA-178468-GO-DIR / D Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 90,000.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-04 D feed seeds 200 qtls from E ehabilitation ementation ARC Page 1 ET-MOA-175934-GO-RFQ / D Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 100,360.00 0.00 2022-02-14 2022-02-19 2022-03-26 2022-04-04 D purchase of fertilizer 1544 ehabilitation ementation Qtl ET-MOA-175933-GO-RFQ / S Livelihoods Protection and R Under Imple IDA / 66510 Prior Direct Selection Direct 4,063,800.00 0.00 2022-02-11 2022-06-16 2022-02-16 2022-06-29 2022-03-23 2022-04-01 omali purchase of fertilizer 6 ehabilitation mentation 2520 Qtl ET-MOA-277931-GO-RFQ / O Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Prior Limited 2,782,000.00 0.00 2022-02-21 2022-04-18 2022-05-18 romia purchase of improved ehabilitation tions nvelope ementation seeds ET-MOA-277932-GO-DIR / Or omia- purchase of fertilizers f Livelihoods Protection and R Pending Impl IDA / 66510 Prior Direct Selection Direct 1,737,000.00 0.00 2022-02-16 2022-02-21 2022-03-28 2022-04-27 rom Ethiopian agricultural Bu ehabilitation ementation siness Corporation (EABC) ET-MOA-277933-GO-DIR / Af Livelihoods Protection and R Pending Impl ar- Purchase of fertilizers fro IDA / 66510 Post Direct Selection Direct 363,500.00 0.00 2022-02-15 2022-02-20 2022-03-27 2022-04-17 ehabilitation ementation m Ethiopian Agricultural Busi ness Corporation ET-MOA-277936-GO-RFQ / Af Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 244,500.00 0.00 2022-02-21 2022-04-18 2022-05-18 ar- Purchase of improved see ehabilitation tions nvelope ementation ds ET-MOA-277940-GO-RFQ / S Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 422,000.00 0.00 2022-02-21 2022-04-18 2022-05-09 NNP- Purchase of improved s ehabilitation tions nvelope ementation eeds ET-MOA-277943-GO-RFQ / S Livelihoods Protection and R Request for Quota Single Stage - One E IDA / 66510 Post Limited 687,000.00 0.00 Canceled 2022-02-21 2022-04-18 2022-05-18 omali- Purchase of improved ehabilitation tions nvelope seeds ET-MOA-277951-GO-RFQ / S Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 808,000.00 0.00 2022-02-21 2022-04-18 2022-05-18 omali- purchase of forage se ehabilitation tions nvelope ementation eds ET-MOA-277958-GO-RFQ / Di Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 120,700.00 0.00 2022-02-20 2022-04-17 2022-05-17 redawa- purchase of improve ehabilitation tions nvelope ementation d seeds ET-MOA-277962-GO-DIR / SN NP- purchase of fertilizers fro Livelihoods Protection and R IDA / 66510 Post Direct Selection Direct 608,000.00 0.00 Canceled 2022-02-15 2022-02-20 2022-03-27 2022-04-26 m Ethiopian Agricultural Busi ehabilitation ness Corporation ET-MOA-277964-GO-DIR / So mali- purchase of Fertilizer fr Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 1,030,000.00 0.00 2022-02-16 2022-02-21 2022-03-28 2022-04-18 om Ethiopian Agricultural Bu ehabilitation ementation siness Corporation ET-MOA-277965-GO-DIR / A mhara- Purchase of fertilizers Livelihoods Protection and R Pending Impl IDA / 66510 Prior Direct Selection Direct 2,810,000.00 0.00 2022-02-16 2022-02-21 2022-03-28 2022-04-27 from Ethiopian Agricultural B ehabilitation ementation usiness Corporation ET-MOA-277969-GO-DIR / Di Livelihoods Protection and R Pending Impl redawa- purchase of fertilizer IDA / 66510 Post Direct Selection Direct 182,300.00 0.00 2022-02-16 2022-02-21 2022-03-28 2022-09-24 ehabilitation ementation s from EABC ET-MOA-277971-GO-DIR / Ha Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct 91,500.00 0.00 2022-02-16 2022-02-21 2022-03-28 2022-04-27 rar purchase of fertilizer from ehabilitation ementation EABC ET-MOA-277974-GO-RFQ / H Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 60,400.00 0.00 2022-02-20 2022-04-17 2022-05-08 arar purchase of improved se ehabilitation tions nvelope ementation eds ET-MOA-286684-GO-DIR / pu Livelihoods Protection and R Pending Impl rchase of improved seeds fro IDA / 66510 Post Direct Selection Direct 687,000.00 0.00 2022-03-25 2022-03-30 2022-04-13 2022-04-28 ehabilitation ementation m Somali Seed Enterprise ET-MOA-308951-GO-RFQ / S Livelihoods Protection and R Single Stage - One E IDA / 66510 Post Request for Bids Open - National 608,000.00 0.00 Canceled 2022-08-18 2022-08-23 2022-09-07 2022-09-22 2022-10-13 2022-10-27 NNP Purchase of seeds ehabilitation nvelope ET-MOA-313528-GO-RFQ / T Livelihoods Protection and R Request for Quota Single Stage - One E Under Imple IDA / 66510 Post Limited 390,000.00 0.00 2022-09-11 2022-08-30 2022-10-09 2022-11-08 eff Seed for SNNP woredas ehabilitation tions nvelope mentation ET-MOA-313530-GO-RFQ / S Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 212,000.00 0.00 2022-09-12 2022-10-10 2022-11-09 weet potato seed ehabilitation tions nvelope ementation ET-MOA-318810-GO-RFQ / U Coordination and Early Warn Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 90,000.00 0.00 2022-10-08 2022-12-03 2023-01-02 niforms for scouts ing Preparedness tions nvelope ementation ET-MOA-318811-GO-RFQ / la Request for Quota Single Stage - One E Pending Impl IDA / 66510 Project Management Post Limited 17,500.00 0.00 2022-10-09 2022-12-04 2023-01-03 ptop computers tions nvelope ementation ET-MOA-323079-GO-DIR / A Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct - National 260,000.00 0.00 2022-10-28 2022-11-02 2022-12-07 2022-12-21 mhara Fertilizer ehabilitation ementation ET-MOA-323073-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 1,000,000.00 0.00 2022-10-30 2022-12-25 2023-01-24 mhara wheat improved seed ehabilitation tions nvelope ementation s ET-MOA-323076-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 380,000.00 0.00 2022-11-01 2022-12-27 2023-01-26 mhara Masho improved seed ehabilitation tions nvelope ementation s ET-MOA-323075-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 280,000.00 0.00 2022-11-01 2022-12-27 2023-01-26 mhara Sorghum improved se ehabilitation tions nvelope ementation eds ET-MOA-323074-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 600,000.00 0.00 2022-10-30 2022-12-25 2023-01-24 mhara Teff improved seeds ehabilitation tions nvelope ementation ET-MOA-325985-GO-DIR / Fe Livelihoods Protection and R IDA / 66510 Post Direct Selection Direct - National 490,000.00 0.00 Signed 2022-11-14 2022-10-24 2022-11-19 2022-12-12 2022-12-24 2023-01-23 rtilizer ehabilitation ET-MOA-325961-GO-RFQ / i Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 560,226.00 0.00 2022-11-19 2023-01-14 2023-02-13 mproved wheat seed ehabilitation tions nvelope ementation ET-MOA-325964-GO-RFQ / F Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 94,339.00 0.00 2022-11-19 2023-01-14 2023-02-13 orage seeds ehabilitation tions nvelope ementation ET-MOA-325966-GO-RFQ / Di Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 12,075.00 0.00 2022-11-20 2023-01-15 2023-02-14 redawa Forage seed ehabilitation tions nvelope ementation Page 2 ET-MOA-325982-GO-DIR / Di Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct - National 16,982.00 0.00 2022-11-15 2022-11-20 2022-12-25 2023-01-24 redawa procurement of Fert ehabilitation ementation ilizer ET-MOA-325983-GO-RFQ / Di Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 44,889.00 0.00 2022-11-23 2023-01-18 2023-02-17 redawa procurement of cere ehabilitation tions nvelope ementation als ET-MOA-328808-GO-RFQ / S Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 483,411.00 0.00 2022-12-05 2023-01-23 2023-02-22 omali improved seed (Maize ) ehabilitation tions nvelope ementation ET-MOA-328809-GO-RFQ / s Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 225,236.00 0.00 2022-12-05 2023-01-30 2023-03-01 omali improved forage seed ehabilitation tions nvelope ementation ET-MOA-328817-GO-RFQ / Af Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 135,406.00 0.00 2022-12-04 2023-01-29 2023-02-28 rar procurement of cereals ehabilitation tions nvelope ementation ET-MOA-328823-GO-RFQ / Af Livelihoods Protection and R Request for Quota Single Stage - One E IDA / 66510 Post Limited 94,340.00 0.00 Signed 2022-12-05 2022-12-06 2023-01-30 2023-03-01 ar improved forage seeds ehabilitation tions nvelope ET-MOA-328826-GO-DIR / pr Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct - National 66,037.00 0.00 2022-11-30 2022-12-05 2023-01-09 2023-02-08 ocurement of fertilizer ehabilitation ementation ET-MOA-328842-GO-RFQ / or Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 463,393.00 0.00 2022-12-04 2023-01-29 2023-02-28 omia improved forage seed ehabilitation tions nvelope ementation ET-MOA-328849-GO-DIR / Or Livelihoods Protection and R Pending Impl omia -procurement of Fertili IDA / 66510 Post Direct Selection Direct - National 686,788.00 0.00 2022-11-29 2022-12-04 2023-01-08 2023-02-07 ehabilitation ementation zer (NPS ,UREA) ET-MOA-328854-GO-RFQ / O Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 351,696.00 0.00 2022-12-05 2023-01-30 2023-03-01 romia procurement of impro ehabilitation tions nvelope ementation ved seed ET-MOA-333773-GO-RFQ / H Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 27,158.21 0.00 2023-01-04 2023-03-01 2023-03-31 arari -Forage seeds ehabilitation tions nvelope ementation ET-MOA-333776-GO-DIR / Ha Livelihoods Protection and R Pending Impl IDA / 66510 Post Direct Selection Direct - National 19,622.00 0.00 2022-12-29 2023-01-03 2023-02-07 2023-03-09 rari - procurement of fertilize ehabilitation ementation r ET-MOA-333777-GO-RFQ / H Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 27,164.00 0.00 2023-01-04 2023-03-01 2023-03-31 arari procurement of seeds ehabilitation tions nvelope ementation ET-MOA-333831-GO-RFQ / s Surveillance and Control Me Request for Quota Single Stage - One E Under Imple upply installation of electric b IDA / 66510 Post Limited 48,000.00 0.00 2023-01-04 2023-03-01 2023-03-31 asures tions nvelope mentation oard for data centre ET-MOA-335504-GO-RFQ / E Request for Quota Single Stage - One E quipment for DL Communicat IDA / 66510 Project Management Post Limited 78,200.00 0.00 Signed 2023-01-18 2023-01-18 2023-03-15 2023-04-14 tions nvelope ion (Audio Visual ) ET-MOA-311252-GO-RFB / E Coordination and Early Warn Request for Quota Single Stage - One E quipment for networking and IDA / 66510 Prior Limited 2,000,000.00 0.00 Canceled 2022-09-04 2022-10-16 2022-11-15 ing Preparedness tions nvelope Software management ET-MOA-337956-GO-RFB / E Coordination and Early Warn Open - Internationa Single Stage - One E Under Imple quipment for Networking and IDA / 66510 Prior Request for Bids 2,000,000.00 0.00 2023-01-27 2023-04-04 2023-02-01 2023-04-11 2023-03-15 2023-04-04 2023-04-21 2023-06-20 ing Preparedness l nvelope mentation software Management ET-MOA-175931-GO-RFQ / O Livelihoods Protection and R romia purchase of fertilizer 1 IDA / 66510 Post Direct Selection Direct 1,276,600.00 0.00 Canceled 2022-02-14 2022-02-19 2022-03-26 2022-04-01 ehabilitation 9640 Qtl from Oromia Seed E nterprise (OSE) ET-MOA-175932-GO-RFQ / S Livelihoods Protection and R NNP purchase of fertilizer 24 IDA / 66510 Post Direct Selection Direct 158,080.00 0.00 Canceled 2022-02-14 2022-02-19 2022-03-26 2022-04-05 ehabilitation 32 Qtl from SSE ET-MOA-277955-GO-RFQ / A Livelihoods Protection and R Request for Quota Single Stage - One E IDA / 66510 Prior Limited 1,865,000.00 0.00 Canceled 2022-02-21 2022-04-18 2022-05-18 mhara- purchase of improve ehabilitation tions nvelope d seeds ET-MOA-348001-GO-RFQ / pr Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 160,000.00 0.00 2023-03-17 2023-05-12 2023-05-27 ocurement of Urea fertilizer ehabilitation tions nvelope ementation ET-MOA-349034-GO-RFQ / pr Request for Quota Single Stage - One E Pending Impl IDA / 66510 Project Management Post Limited 99,500.00 0.00 2023-03-21 2023-05-16 2023-06-25 ocurement of office furniture tions nvelope ementation ET-MOA-318812-GO-RFQ / E arth ranger and tableaus soft Surveillance and Control Me Request for Quota Single Stage - One E IDA / 66510 Post Limited 35,000.00 0.00 Canceled 2022-10-15 2022-12-10 2023-01-09 ware for data analysis and fie asures tions nvelope ld operation tracking ET-MOA-328848-GO-RFQ / O Livelihoods Protection and R Request for Quota Single Stage - One E IDA / 66510 Post Limited 100.00 0.00 Canceled 2022-12-05 2023-01-30 2023-03-01 romia improved seed ehabilitation tions nvelope ET-MOA-199303-GO-DIR / 20 Surveillance and Control Me IDA / 66510 Post Direct Selection Direct 700,000.00 0.00 Canceled 2022-02-14 2022-02-19 2022-03-26 2022-05-10 Agricultural sprayer Drones asures ET-MOA-353878-GO-RFQ / R Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl hodes grass, Panicum grass IDA / 66510 Post Limited 920,000.00 0.00 2023-04-08 2023-05-13 2023-06-27 ehabilitation tions nvelope ementation and Sudan grass seeds ET-MOA-353882-GO-RFQ / L Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl ukinia, Sesbania, Tree Lucere IDA / 66510 Post Limited 900,000.00 0.00 2023-04-08 2023-05-13 2023-06-27 ehabilitation tions nvelope ementation ne and pigeon pea seeds ET-MOA-364542-GO-RFQ / O Livelihoods Protection and R Pending Impl romia procurement of fertili IDA / 66510 Prior Direct Selection Direct - National 2,094,230.00 0.00 2023-06-05 2023-06-10 2023-07-08 2023-08-07 ehabilitation ementation zer ( urea and UPS) ET-MOA-364548-GO-RFQ / or Livelihoods Protection and R Single Stage - One E Under Imple IDA / 66510 Prior Request for Bids Open - National 2,879,741.00 0.00 2023-06-06 2023-06-11 2023-07-11 2023-07-21 2023-08-18 2023-09-20 omia procurement of improv ehabilitation nvelope mentation ed seed ET-MOA-364555-GO-RFB / A Livelihoods Protection and R Single Stage - One E Pending Impl IDA / 66510 Post Request for Bids Open - National 322,652.00 0.00 2023-06-07 2023-06-12 2023-07-12 2023-07-13 2023-08-04 2023-09-03 mhara procurement of forag ehabilitation nvelope ementation e seed ET-MOA-364601-GO-RFB / S Livelihoods Protection and R Single Stage - One E Pending Impl IDA / 66510 Post Request for Bids Open - National 246,000.00 0.00 2023-06-06 2023-06-11 2023-07-11 2023-07-19 2023-07-28 2023-08-27 NNP procurement of forage s ehabilitation nvelope ementation eeds Page 3 ET-MOA-365284-GO-RFQ / Pr Surveillance and Control Me Request for Quota Single Stage - One E Pending Impl ocurement of tablets for DL d IDA / 66510 Post Limited 30,000.00 0.00 2023-06-12 2023-08-07 2023-09-06 asures tions nvelope ementation ata collection NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-181756-NC-DIR / Le Surveillance and Control Me Under Revie ase of Aircraft sprayer (4 airc IDA / 66510 Prior Direct Selection 5,600,000.00 0.00 2020-07-07 2020-07-12 2020-07-25 2021-01-21 asures w rafts) from Zemen Flights ser vice ET-MOA-199304-NC-DIR / Le Surveillance and Control Me Under Revie IDA / 66510 Prior Direct Selection Direct 4,500,000.00 0.00 2020-10-15 2020-10-20 2020-11-24 2021-02-22 ase of sprayer air crafts asures w ET-MOA-236964-NC-RFQ / C harter service to transport ba Surveillance and Control Me Request for Quota Single Stage - One E IDA / 66510 Post Limited 390,000.00 385,000.00 Completed 2021-06-05 2021-05-25 2021-07-17 2021-05-27 2021-08-06 2021-06-01 ck to South Africa after servic asures tions nvelope e contract of the Helicopters is completed. ET-MOA-237036-NC-RFQ / Tr Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl ansport contract to deliver th IDA / 66510 Post Limited 150,000.00 0.00 2021-06-05 2021-07-10 2021-08-09 ehabilitation tions nvelope ementation e "improved seeds" for the Ti gray regions. ET-MOA-238897-NC-RFQ / Tr ansport service for 11,584 qu Livelihoods Protection and R Request for Quota Single Stage - One E Pending Impl IDA / 66510 Post Limited 150,000.00 0.00 2021-06-16 2021-07-06 2021-07-21 intals of seed from Mekelle to ehabilitation tions nvelope ementation various woredas in Tigray reg ion ET-MOA-279746-NC-RFQ / le Surveillance and Control Me Request for Quota Single Stage - One E IDA / 66510 Prior Limited 3,000,000.00 0.00 Canceled 2022-03-01 2022-04-26 2022-10-23 ase of DL spray aircrafts asures tions nvelope ET-MOA-199300-NC-DIR / Le Surveillance and Control Me Pending Impl IDA / 66510 Post Direct Selection Direct 315,000.00 0.00 2020-10-19 2020-10-24 2020-11-28 2021-01-12 ase of four sprayer drones asures ementation ET-MOA-289953-NC-DIR / Le Surveillance and Control Me IDA / 66510 Post Direct Selection Direct 1,490,000.00 0.00 Completed 2022-04-15 2022-04-21 2022-04-20 2022-04-21 2022-05-11 2022-09-08 2022-07-22 ase of Sprayer aircraft asures ET-MOA-255670-GO-RFQ / D ocumentation and publicatio Request for Quota Single Stage - One E IDA / 66510 Project Management Post Limited 60,000.00 0.00 Canceled 2022-02-16 2022-04-13 2022-06-12 n service of DL situation in Et tions nvelope hiopia from 2019-2021 ET-MOA-311259-NC-DIR / Thi Direct - Internation IDA / 66510 Project Management Post Direct Selection 1,400,000.00 0.00 Canceled 2022-09-05 2022-09-10 2022-10-08 2023-04-06 rd Party Implementer service al fee ET-MOA-322588-NC-DIR / Se Direct - Internation IDA / D6360 Project Management Prior Direct Selection 2,400,000.00 0.00 Signed 2022-10-26 2022-10-20 2022-10-31 2022-10-24 2022-12-05 2023-11-30 rvice of Third Party Impleme al nter ET-MOA-348005-GO-DIR / Pr Surveillance and Control Me Direct - Internation Pending Impl ocurement of earth range sof IDA / 66510 Post Direct Selection 35,000.00 0.00 2023-03-20 2023-03-25 2023-04-10 2023-05-20 asures al ementation tware license CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-325698-CS-LCS / co Surveillance and Control Me Least Cost Selecti nsultancy service for design IDA / 66510 Post Open - National 90,000.00 0.00 Under Review 2022-12-08 2023-06-27 2022-12-22 2023-01-01 2023-01-29 2023-02-05 2023-02-13 2023-02-23 2023-03-16 asures on and supervise of renovation of chemical store INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-197751-CS-INDV / E Individual Consult mployment of Communicatio IDA / 66510 Project Management Post Open 48,000.00 0.00 Canceled 2020-10-15 2020-11-23 2020-12-08 2021-01-07 2022-01-06 ant Selection n specialist ET-MOA-199298-CS-INDV / E Individual Consult mployment of data manage IDA / 66510 Project Management Post Open 48,000.00 0.00 Canceled 2020-10-16 2020-11-25 2020-12-09 2020-12-28 2021-12-27 ant Selection ment specialist ET-MOA-197753-CS-INDV / E Individual Consult mployment of Pest Managem IDA / 66510 Project Management Post Open 48,000.00 0.00 Canceled 2020-10-14 2020-11-22 2020-12-10 2020-12-30 2021-12-29 ant Selection ent Specialist ET-MOA-197752-CS-INDV / E Individual Consult mployment of Environmental IDA / 66510 Project Management Post Open 48,000.00 0.00 Canceled 2020-10-13 2020-11-22 2020-12-13 2021-01-05 2022-01-04 ant Selection and Social Safeguards Specia list ET-MOA-197750-CS-INDV / E Individual Consult mployment of Monitoring, Ev IDA / 66510 Project Management Post Open 48,000.00 0.00 Canceled 2020-10-18 2020-11-27 2020-12-11 2021-01-06 2022-01-05 ant Selection aluation and Learning (MEAL) specialist ET-MOA-264667-CS-INDV / R Individual Consult Under Implement ecruitment of Pest Managem IDA / 66510 Project Management Post Open 10,000.00 0.00 2021-11-23 2021-06-10 2022-01-11 2022-02-01 2022-03-08 2022-09-04 ant Selection ation ent specialist ET-MOA-264678-CS-INDV / R Individual Consult Under Implement IDA / 66510 Project Management Post Open 10,000.00 0.00 2021-11-26 2021-06-10 2021-12-22 2021-12-29 2022-01-26 2023-01-26 ecruitment of M & E Specialis ant Selection ation t ET-MOA-261441-CS-INDV / E Individual Consult Under Implement mployment of Communicatio IDA / 66510 Project Management Post Open 10,000.00 0.00 2021-11-25 2020-11-05 2021-12-28 2022-01-04 2022-02-08 2023-02-08 ant Selection ation n specialist Page 4 ET-MOA-264675-CS-INDV / r Individual Consult Under Implement ecruitment of Environmental IDA / 66510 Project Management Post Open 10,000.00 0.00 2021-11-25 2021-06-10 2021-12-28 2022-01-18 2022-02-22 2023-02-22 ant Selection ation Safeguard Specialist Page 5 PLAN DE PASSATION DE MARCHÉS Information sur le Projet : Emprunteur/Bénéficiaire République Togolaise Ministère Responsable Nom du Projet Identification P172769 Agence d’exécution du Projet : [A insérer] Date du plan de passation des marchés : [A indiquer] Période couverte par ce plan de passation des marchés : [A indiquer] Date d’approbation par la Banque du plan de passation de marchés : [A indiquer] Date de publication de l’Avis Général de Passation des Marchés : [A indiquer] Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System) : Elevé Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Novembre 2020) (“Règlement de Passation des Marchés”), le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la loi No. 2009-013 du 30 juin 2009 relative aux Marchés Publics et Délégation de Service Public, le Décret Nº 2009-277/PR du 11 novembre 2009 portant Code des Marchés Publics et Délégation de Service Public, et les textes d’application y afférents, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : - Le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/les proposants présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection e l’audit ; - Le droit de la Banque d’examiner le dossier et les activités de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés Travaux ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés ne s’applique pas. Autres informations pertinentes sur la passation des marchés : Néant I. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Juillet 2016, révisé en Novembre 2017. Catégories de marchés Montants Observations estimatifs des contrats en millions de dollars américains Travaux (incluant clé à main, Fourniture et Installation, et les >= 5 Partenariat Public - Privé -PPP) Biens, Système d’Information et de Services autres que les >= 1,5 Services intellectuels Contrats à Travaux passer par (incluant clé à >= 5 entente main, directe Fourniture et Les justifications de Installation, et l’entente directe les Partenariat devront être jointes et Public - Privé - approuvées avec PPM PPP) Biens, Système d’Information et de Services >= 1,5 autres que les Services intellectuels 2. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : FOURNITURES ET SERVICES AUTRE QUE LES SERVICES DE CONSULTANTS TRAVAUX (US$ équivalent) (US$ équivalent) AOI AON DC AOI AON DC < < 100.000 ≥5.000.000 <5.000.000 200.00 ≥500.000 <500.000 0 3. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). Liste de Marchés de Travaux, Fournitures, et Services autres que Consultant Date Type Méthode/ Montan de Comme d'Exa Modalité Appro t lance ntaire Réf. DESCRIP men de che de Estimat ment /Fin de No. TION par la passatio march if en de la prestat Banqu n des és US$ procé ions e marchés dure II. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujette à la revue préalable de la Banque comme indiqué dans Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Méthode de Seuils de revue a priori Observations sélection/Catégories de Montants estimatifs des marchés contrats en millions de dollars américains Méthode compétitive/Firmes de >= 0.5 consultants Entente directe/firmes de Les justifications pour consultants >= 0.5 l’entente directe devront être jointes et approuvées Entente avec le PPM directe/Consultants >= 0.2 individuel Méthode Compétitive >= 0.2 (Comparaison de CVs)/ Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux en conformité avec les dispositions des Règlements de Passation des marchés., et l’Emprunteur ne procède pas à une publication dans UNDB 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission ; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels telles des situations d’urgence en conformité au Règlement de Passation des marchés II- Liste de Marchés de Services de Consultants Date Méthod Comm Montan Type de Ré e de entair t d'Exam Approch lancem f. DESCRIPTION passati e/Fin Estimat en par e de ent de No DES MISSIONS on des des if en la Marché la . marché presta US$ Banque procéd s tions ure Lexique des Sigles et Abréviations ARMP Autorité de Régulation des Marchés Publics AOI Appel d’Offres International AON Appel d’Offres National A Revue a posteriori posteriori A Priori Revue a priori CI Consultant Individuel DC Demande de Cotations DNCMP Direction Nationale de Contrôle des Marchés Publics ED Sélection Directe ou Entente Directe PPM Plan de Passation des Marchés SFQ Sélection Fondée sur la Qualité SFQC Sélection Fondée sur la Qualité et le Coût SMC Sélection au Moindre Coût SQC Sélection fondée sur les Qualifications des Consultants PROCUREMENT Western and Central Africa : West Africa Food System Resilience Program (FSRP) PLAN General Information Country: Western and Central Africa 2022-08-08 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172769 GPN Date: Project Name: West Africa Food System Resilience Program (FSRP) Loan / Credit No: IDA / D9220 COORDINATION OF WEST AFRICA FOOD SYSTEM RESILIENCE PROGRAM (TOGO) Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure TG-FSRP TOGO-306292-CW- ment Document - Request for Quota Single Stage - One E 2023-02-2 RFQ / Travaux de réhabilitati IDA / D9220 Project Management Post Limited 1 Envelope proce 54,545.00 0.00 Signed 2022-09-04 2022-09-13 2022-10-30 tions nvelope 7 on du bâtiment du projet FSR ss (Non Bank-SPD P-Togo ) National Procure TG-FSRP TOGO-315205-CW- Sustainability and adaptive c ment Document - Single Stage - One E Pending Imp 2023-04-2 RFB / Construction de deux ( IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 1 Envelope proce 109,000.00 0.00 2022-10-18 2022-10-25 2022-11-24 2022-12-24 2023-01-28 nvelope lementation 8 02) serres modernes sur une productive base ss (Non Bank-SPD station de l'ITRA ) TG-FSRP TOGO-337929-CW- RFB / Réalisation des forages Request for Bids - de suivi des ressources en ea Digital advisory services for Single Stage - One E Works (without pr Under Imple 2023-12-1 ux souterraines (piézomètres IDA / D9220 agriculture and food crisis pr Post Request for Bids Open - National 150,182.00 0.00 2023-03-03 2023-04-05 2023-03-13 2023-04-12 2023-05-05 2023-05-12 2023-05-11 2023-06-16 nvelope equalification) SP mentation 3 ) dans les formations aquifèr evention and management D es du socle au profit de la Dir ection des ressources en eau (DRE) TG-FSRP TOGO-337930-CW- RFB / Réhabilitation de sept ( Request for Bids - Sustainability and adaptive c 07) agences de l' institut de Single Stage - One E Works (without pr Pending Imp 2023-11-2 IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 707,000.00 0.00 2023-04-10 2023-04-17 2023-05-17 2023-06-01 2023-06-29 conseil et d'appui technique ( nvelope equalification) SP lementation 6 productive base ICAT) dans les régions de la D Kara, centrale, plateaux et m aritime (Marchés en 4 lots) TG-FSRP TOGO-338947-CW- National Procure RFB / Réhabilitation du local Sustainability and adaptive c ment Document - devant abriter les équipemen Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / D9220 apacity of the food system’s Post Open - National 1 Envelope proce 72,727.00 0.00 2023-04-20 2023-06-16 ts de conservation des resso tions nvelope lementation 4 productive base ss (Non Bank-SPD urces génétiques de l'Institut ) togolais de recherche agrono mique (ITRA) TG-FSRP TOGO-337928-CW- RFB / Réhabilitation de onze ( Request for Bids - Digital advisory services for 11) centres et stations agro Single Stage - One E Works (without pr Pending Imp 2023-12-1 IDA / D9220 agriculture and food crisis pr Post Request for Bids Open - National 938,000.00 0.00 2023-04-10 2023-04-25 2023-05-25 2023-06-09 2023-07-14 météorologiques de la directi nvelope equalification) SP lementation 1 evention and management on générale de la météorolog D ie nationale (DGMN) réparti e n quatre (04) lots. TG-FSRP TOGO-351037-CW- Request for Quota RFQ / Réhabilitation de deux Sustainability and adaptive c Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-09-0 (02) agences de l'institut de IDA / D9220 apacity of the food system’s Post Open - National 170,500.00 0.00 2023-04-17 2023-06-06 tions nvelope s (Emergency) SP mentation 4 conseil et d'appui technique ( productive base D -Competitive ICAT) dans la région des sava nes TG-FSRP TOGO-351042-CW- Request for Quota RFQ / Réhabilitation de trois ( Digital advisory services for Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-09-1 03) agence de l'Agence natio IDA / D9220 agriculture and food crisis pr Post Open - National 302,000.00 0.00 2023-04-17 2023-06-13 tions nvelope s (Emergency) SP lementation 1 nale de la météorologie (ANA evention and management D -Competitive MET) dans la région des sava nes. TG-FSRP TOGO-357134-CW- Request for Quota Sustainability and adaptive c RFQ / Aménagement de la vo Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-11-0 IDA / D9220 apacity of the food system’s Post Open - National 123,955.00 0.00 2023-06-02 2023-08-03 ix d'accès au complexe avico tions nvelope s (Emergency) SP lementation 1 productive base le de référence d'Avetonou D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-FSRP TOGO-305273-GO- Digital advisory services for Request for Quota Single Stage - One E RFQ / Acquisition de GPS au IDA / D9220 agriculture and food crisis pr Post Limited 14,545.00 0.00 Signed 2022-11-13 2022-09-05 2023-01-08 2023-05-08 tions nvelope profit des structures partenai evention and management res TG-FSRP TOGO-305828-GO- Digital advisory services for RFQ / Acquisition et installati Request for Quota Single Stage - One E IDA / D9220 agriculture and food crisis pr Post Limited 18,182.00 0.00 Signed 2022-10-29 2022-09-06 2022-12-24 2023-06-22 on de l'antenne de réception tions nvelope evention and management d'images satellitaires au profi t de la DGMN TG-FSRP TOGO-305833-GO- Digital advisory services for Request for Quota Single Stage - One E Pending Impl RFQ / Acquisition de smart p IDA / D9220 agriculture and food crisis pr Post Limited 12,727.00 0.00 2022-10-03 2022-11-28 2023-02-26 tions nvelope ementation hone pour le FAMEWS evention and management TG-FSRP TOGO-306008-GO- Digital advisory services for Request for Quota Single Stage - One E RFQ / Acquisition des pièges IDA / D9220 agriculture and food crisis pr Post Limited 12,727.00 0.00 Signed 2022-09-03 2022-08-31 2022-10-29 2023-01-27 tions nvelope à pheromone au profit de la evention and management DPV TG-FSRP TOGO-306094-GO- Sustainability and adaptive c RFQ / Acquisition de 2 drones Request for Quota Single Stage - One E IDA / D9220 apacity of the food system’s Post Limited 90,909.00 0.00 Signed 2022-09-03 2022-09-05 2022-10-29 2023-02-26 de phénotypage haut débit e tions nvelope productive base t de traitements phytosanitai res au profit de l'ITRA TG-FSRP TOGO-306286-GO- RFB / Acquisition des instrum Regional food market integr Single Stage - One E ents de mesure de températ IDA / D9220 Post Request for Bids Open - National 109,091.00 0.00 Signed 2022-08-18 2022-10-03 2022-08-23 2022-10-04 2022-11-04 2022-11-03 2022-12-07 2022-12-08 2023-04-07 ation and trade nvelope ure pour le laboratoire de mé trologie au profit de la HAUQ E (ATOMET, COTAG) TG-FSRP TOGO-306297-GO- RFQ / Acquisition des mobilie Request for Quota Single Stage - One E Under Imple IDA / D9220 Project Management Post Limited 36,364.00 0.00 2022-08-23 2022-12-22 2022-10-18 2022-11-17 rs et équipements pour la sal tions nvelope mentation le de reunion de la coordinati on du FSRP Page 1 TG-FSRP TOGO-305701-GO- Digital advisory services for RFQ / Achat de consommable Request for Quota Single Stage - One E Under Imple IDA / D9220 agriculture and food crisis pr Post Limited 18,182.00 0.00 2022-10-30 2022-12-25 2023-03-25 s pour les analyses au labora tions nvelope mentation evention and management toire des semences de Sotou boua TG-FSRP TOGO-306207-GO- Sustainability and adaptive c RFQ / Acquisition de vaccins I Request for Quota Single Stage - One E IDA / D9220 apacity of the food system’s Post Limited 87,273.00 0.00 Signed 2022-09-04 2022-10-19 2022-10-30 2023-01-28 TANEW pour la campagne de tions nvelope productive base vaccination de volailles (1 84 0 000 doses) TG-FSRP TOGO-306014-GO- Digital advisory services for RFQ / Acquisition de véhicule Direct - Internation IDA / D9220 agriculture and food crisis pr Post Direct Selection 872,727.00 0.00 Signed 2022-08-22 2022-10-28 2022-08-27 2022-08-23 2022-10-01 2022-12-30 s au profit des structures par al evention and management tenaires du FSRP - Togo TG-FSRP TOGO-306304-GO- RFQ / Achat de fournitures de Request for Quota Single Stage - One E Under Imple IDA / D9220 Project Management Post Limited 36,364.00 0.00 2022-08-28 2022-10-10 2022-10-16 2022-11-15 bureau et consomables infor tions nvelope mentation matiques au profit du FSRP TG-FSRP TOGO-306009-GO- RFQ / Acquisition de semenc Sustainability and adaptive c Request for Quota Single Stage - One E Under Imple es certifiées de cultures mar IDA / D9220 apacity of the food system’s Post Limited 136,364.00 0.00 2022-09-04 2022-11-02 2022-10-30 2022-12-29 tions nvelope mentation aichères au profit des produc productive base teurs de la région des savane s TG-FSRP TOGO-306015-GO- Digital advisory services for DIR / Acquisition des motos a Direct - Internation IDA / D9220 agriculture and food crisis pr Post Direct Selection 450,000.00 0.00 Signed 2022-08-25 2022-10-28 2022-08-30 2022-08-23 2022-10-04 2023-01-02 u profit des structures parten al evention and management aires du FSRP - Togo TG-FSRP TOGO-306007-GO- RFQ / Acquisition des équipe ments TIC (Serveur, imprima Digital advisory services for nte AO pour l'impression de Request for Quota Single Stage - One E IDA / D9220 agriculture and food crisis pr Post Limited 81,818.00 0.00 Signed 2022-09-04 2022-09-06 2022-10-30 2023-02-27 données sur des formats spé tions nvelope evention and management cifiques, ordinateurs de perfo rmances élevées, écrans inte ractifs) au profit de l'ANPC et de la DSID TG-FSRP TOGO-306331-GO- RFQ / Acquisition et installati Request for Quota Single Stage - One E Under Imple IDA / D9220 Project Management Post Limited 36,364.00 0.00 2022-09-04 2022-09-05 2022-10-23 2022-12-22 on d'un groupe electrogène a tions nvelope mentation u profit de la FSRP TG-FSRP TOGO-306302-GO- RFQ / Acquisiton du matériel Request for Quota Single Stage - One E Under Imple IDA / D9220 Project Management Post Limited 54,545.00 0.00 2022-08-31 2022-11-16 2022-10-26 2023-02-23 informatique au profit de la c tions nvelope mentation oordination du FSRP TG-FSRP TOGO-306288-GO- Regional food market integr Request for Quota Single Stage - One E Under Imple DIR / Acquérir les équipemen IDA / D9220 Post Limited 36,364.00 0.00 2022-09-12 2022-11-15 2022-11-07 2023-03-07 ation and trade tions nvelope mentation ts de métrologie au profit de la HAUQE TG-FSRP TOGO-306016-GO- Digital advisory services for RFB / Acquisition des matérie Single Stage - One E Under Imple IDA / D9220 agriculture and food crisis pr Post Request for Bids Open - National 490,909.00 0.00 2022-08-24 2021-10-05 2022-08-29 2022-09-28 2022-11-08 2022-10-28 2023-01-06 2022-12-02 2023-04-01 ls informatiques au profit de nvelope mentation evention and management s structures partenaires du F SRP - Togo TG-FSRP TOGO-306290-GO- RFQ / Acquisition des kits de Sustainability and adaptive c formation des femmes leader Request for Quota Single Stage - One E IDA / D9220 apacity of the food system’s Post Limited 10,909.00 0.00 Signed 2022-08-30 2022-08-31 2022-10-18 2022-11-17 s et des groupes organisés s tions nvelope productive base ur la transformation des alim ents à hautes valeurs nutritio nnelles TG-FSRP TOGO-306019-GO- DIR / Acquisition de vaccin p Sustainability and adaptive c Direct - Internation our la campagne de vaccinati IDA / D9220 apacity of the food system’s Post Direct Selection 47,273.00 0.00 Signed 2022-08-30 2022-09-08 2022-09-04 2022-08-23 2022-10-09 2023-01-07 al on du petit ruminant (500 00 productive base 0 doses de vaccins PPR) TG-FSRP TOGO-306285-GO- RFQ / Acquisition de matériel s et équipements de producti Sustainability and adaptive c on des essences forrestières Request for Quota Single Stage - One E IDA / D9220 apacity of the food system’s Post Limited 54,545.00 0.00 Signed 2022-09-11 2022-09-22 2022-11-06 2023-02-04 au profit des pépinéristes et tions nvelope productive base des équipements de collecte des produits forestiers non li geux (PFNL) au proft des coo pératives collectrices des PF NL. TG-FSRP TOGO-315078-GO- RFB / Acquisition de tracteurs Sustainability and adaptive c Open - Internationa Single Stage - One E Under Imple avec machines agricoles de IDA / D9220 apacity of the food system’s Post Request for Bids 545,455.00 0.00 2022-10-13 2022-10-17 2022-10-28 2022-10-20 2022-12-12 2022-12-02 2023-01-11 2023-01-16 2023-02-15 2023-06-15 l nvelope mentation motoculteurs et de trieuses c productive base alibreuses au profit de l’ITRA, l’ESA, l’ISMA et l’INFA TG-FSRP TOGO-315173-GO- RFB / Acquisition des équipe Sustainability and adaptive c ments pour l’analyse des rési Open - Internationa Single Stage - One E IDA / D9220 apacity of the food system’s Post Request for Bids 365,000.00 0.00 Signed 2022-10-14 2022-10-24 2022-10-29 2022-10-27 2022-12-13 2022-12-07 2023-01-12 2023-01-18 2023-02-16 2023-05-17 dus de médicaments vétérin l nvelope productive base aires et autres (laboratoire d e microbiologie, physico-chi mie, etc.) pour le compte de l 'ITRA TG-FSRP TOGO-315208-GO- RFB / Acquisition des équipe Sustainability and adaptive c ments des laboratoires de bi Open - Internationa Single Stage - One E IDA / D9220 apacity of the food system’s Post Request for Bids 364,000.00 0.00 Signed 2022-10-20 2022-11-17 2022-11-04 2022-11-17 2022-12-19 2023-01-06 2023-01-18 2023-01-23 2023-02-22 2023-06-22 osécurité, génétiques, entom l nvelope productive base ologie, microbiologie, chimie et phytopathologie au profit de l'ITRA TG-FSRP TOGO-318862-GO- Sustainability and adaptive c RFB / Acquisition des fertilisa Single Stage - One E Under Imple IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 90,000.00 0.00 2022-10-30 2022-11-14 2022-11-06 2022-11-21 2022-12-16 2022-12-21 2022-12-22 2023-01-25 2023-03-26 nts et des biopesticides au pr nvelope mentation productive base ofit des producteurs sur les Z AAP TG-FSRP TOGO-320854-GO- RFB / Acquisition des équipe Sustainability and adaptive c ments de transformation agri Open - Internationa Single Stage - One E Pending Impl IDA / D9220 apacity of the food system’s Post Request for Bids 909,100.00 0.00 2022-11-30 2022-12-21 2023-02-04 2023-03-06 2023-04-17 2023-10-14 cole (décortiqueuses, batteus l nvelope ementation productive base es-vanneuses de riz, décortiq ueuses-vanneuses de soja) d ans la région des savanes Page 2 TG-FSRP TOGO-320879-GO- RFB / Acquisition et installati Digital advisory services for on de dix (10) stations autom Open - Internationa Single Stage - One E Under Imple IDA / D9220 agriculture and food crisis pr Post Request for Bids 636,364.00 0.00 2022-11-10 2022-11-21 2022-11-25 2022-11-21 2023-01-09 2023-02-08 2023-03-16 2023-09-12 atiques avec télétransmissio l nvelope mentation evention and management n de mesures hydrologiques et autres équipements au pr ofit de la DRE TG-FSRP TOGO-320903-GO- RFB / Acquisition des équipe Digital advisory services for Open - Internationa Single Stage - One E ments de réétalonnage (mai IDA / D9220 agriculture and food crisis pr Post Request for Bids 727,273.00 0.00 Signed 2022-11-02 2022-11-14 2022-11-17 2022-11-17 2023-01-01 2023-01-06 2023-01-31 2023-02-15 2023-03-07 2023-08-04 l nvelope ntenance) et autres accessoi evention and management res au profit de la DGMN. TG-FSRP TOGO-318860-GO- Sustainability and adaptive c RFB / Acquisition des outils m Single Stage - One E IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 309,000.00 0.00 Signed 2022-10-30 2022-11-16 2022-11-14 2022-11-29 2022-12-02 2022-12-29 2022-12-22 2023-02-02 2023-03-19 araichers au profit des produ nvelope productive base cteurs sur les ZAAP TG-FSRP TOGO-320892-GO- RFB / Acquisition et installati Digital advisory services for Single Stage - One E on des équipements d’interc IDA / D9220 agriculture and food crisis pr Post Request for Bids Open - National 363,634.00 0.00 Signed 2022-11-22 2022-11-16 2022-12-07 2023-01-06 2022-12-20 2023-02-05 2022-12-30 2023-03-12 2023-07-10 nvelope onnexion des stations et cent evention and management re de contrôle de la DGMN TG-FSRP TOGO-320791-GO- Request for Quota Single Stage - One E RFQ / Acquisition de véhivule IDA / D9220 Project Management Post Limited 237,000.00 0.00 Signed 2022-10-28 2022-11-14 2022-12-01 2023-03-01 tions nvelope s au profit de la coordination du FSRP TG-FSRP TOGO-305934-GO- RFQ / Acquisition et installati on de 10 stations automatiqu Digital advisory services for Request for Quota Single Stage - One E es avec télétransmission de IDA / D9220 agriculture and food crisis pr Post Limited 40,000.00 0.00 Canceled 2022-09-07 2022-11-02 2023-03-02 tions nvelope mesures hydrologiques au pr evention and management ofit de la DRE et des équipe ments de réétalonnage au pr ofit de la DGMN. TG-FSRP TOGO-305702-GO- RFQ / Acquisition des équipe Digital advisory services for Request for Quota Single Stage - One E ments d'interconnexion des s IDA / D9220 agriculture and food crisis pr Post Limited 54,545.00 0.00 Canceled 2022-10-23 2022-12-18 2023-04-17 tions nvelope tations et centre de contrôle evention and management (15 stations et la DGMN: cent re de contrôle) TG-FSRP TOGO-306095-GO- Sustainability and adaptive c RFQ / Acquisition de 5 moiss Request for Quota Single Stage - One E IDA / D9220 apacity of the food system’s Post Limited 31,818.00 0.00 Canceled 2022-09-03 2022-08-31 2022-10-29 2023-02-26 onneuses batteuses au profit tions nvelope productive base des structures partenaires TG-FSRP TOGO-305830-GO- Digital advisory services for RFQ / Acquisition de postes p Request for Quota Single Stage - One E IDA / D9220 agriculture and food crisis pr Post Limited 90,909.00 0.00 Canceled 2022-10-10 2022-08-31 2022-12-05 2023-03-05 luvio classique complets ave tions nvelope evention and management c support au profit de la DGM N TG-FSRP TOGO-306287-GO- DIR / Acquisition des équipe Regional food market integr Direct - Internation ments de contrôle de qualité IDA / D9220 Post Direct Selection 327,273.00 0.00 Canceled 2022-08-29 2022-09-03 2022-10-08 2023-02-05 ation and trade al des produits (camion étalon) au profit de la HAUQE (ATOM ET, COTAG) TG-FSRP TOGO-337895-GO- RFB / Acquisition de moisson Sustainability and adaptive c Open - Internationa Single Stage - One E Under Imple neuses-batteuses et trieuses IDA / D9220 apacity of the food system’s Post Request for Bids 305,455.00 0.00 2023-02-23 2023-05-12 2023-03-10 2023-04-24 2023-05-24 2023-06-28 2023-10-26 l nvelope mentation calibreuses au profit des stru productive base ctures partenaires du FSRP TG-FSRP TOGO-337896-GO- Sustainability and adaptive c Open - Internationa Single Stage - One E Under Imple RFB / Acquisition des motocu IDA / D9220 apacity of the food system’s Post Request for Bids 418,182.00 0.00 2023-02-24 2023-05-15 2023-03-11 2023-05-17 2023-04-25 2023-05-25 2023-06-29 2023-10-27 l nvelope mentation lteurs au profit des producte productive base urs sur les ZAAP TG-FSRP TOGO-337900-GO- RFB / Acquisition des équipe ments de contrôle de qualité Regional food market integr Open - Internationa Single Stage - One E Under Imple IDA / D9220 Post Request for Bids 545,455.00 0.00 2023-02-26 2023-05-12 2023-03-13 2023-05-17 2023-04-27 2023-05-27 2023-07-01 2023-12-28 des produits (camion étalon) ation and trade l nvelope mentation au profit de la Haute Autorité pour la Qualité et l'Environne ment (HAUQE) TG-FSRP TOGO-337903-GO- Sustainability and adaptive c RFB / Acquisition des semenc Single Stage - One E Under Imple IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 363,636.00 0.00 2023-02-17 2023-02-14 2023-03-04 2023-03-25 2023-04-20 2023-04-09 2023-05-09 2023-05-08 2023-06-07 es certifiées de riz et de soj nvelope mentation productive base a au profit des producteurs TG-FSRP TOGO-337927-GO- RFQ / Acquisition et installati on de dix (10) sondes électri Digital advisory services for Request for Quota Single Stage - One E Under Imple ques à eau pour mesure du IDA / D9220 agriculture and food crisis pr Post Limited 21,455.00 0.00 2023-04-07 2023-04-06 2023-05-19 2023-07-18 tions nvelope mentation niveau d'eau dans dix (10) pi evention and management ézomètres dans le bassin ver sant de l'Oti au profit de la Di rection des ressources en ea u (DRE) TG-FSRP TOGO-337933-GO- RFQ / Acquisition des logiciel Digital advisory services for Request for Quota Single Stage - One E Pending Impl s (SimClim, BaRatinAGE et lo IDA / D9220 agriculture and food crisis pr Post Limited 61,818.00 0.00 2023-03-04 2023-04-25 2023-06-24 tions nvelope ementation giciel base de données hydro evention and management logique) et la formation à leu r l'utilisation TG-FSRP TOGO-338507-GO- Digital advisory services for RFB / Acquisition et installati Open - Internationa Single Stage - One E Pending Impl IDA / D9220 agriculture and food crisis pr Post Request for Bids 909,091.00 0.00 2023-03-15 2023-04-05 2023-05-20 2023-06-19 2023-07-31 2024-01-27 on de six (06) nouvelles stati l nvelope ementation evention and management ons agrométéorologie au pro fit de la DGMN TG-FSRP TOGO-338974-GO- Sustainability and adaptive c RFB / Mise en place de 05 sy Open - Internationa Single Stage - One E Pending Impl IDA / D9220 apacity of the food system’s Post Request for Bids 545,455.00 0.00 2023-04-28 2023-05-13 2023-06-27 2023-07-27 2023-09-06 2023-12-05 stèmes de micro-irrigation s l nvelope ementation productive base ur les ZAAP à aménager TG-FSRP TOGO-338058-GO- Sustainability and adaptive c RFB / Equipement de la banq Single Stage - One E Under Imple IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 174,545.00 0.00 2023-02-27 2023-03-08 2023-03-09 2023-04-08 2023-05-08 2023-05-25 2023-07-24 ue de gènes de l'Institut togo nvelope mentation productive base lais de recherche agronomiq ue (ITRA) TG-FSRP TOGO-337906-GO- Sustainability and adaptive c Direct - Internation DIR / Acquisition de l'engrais IDA / D9220 apacity of the food system’s Prior Direct Selection 20,000,000.00 0.00 Signed 2023-02-15 2023-02-21 2023-02-17 2023-02-21 2023-03-14 2023-04-13 al NPK15-15-15 en réponse à la productive base crise Page 3 TG-FSRP TOGO-351054-GO- RFQ / Acquisition de divers é Sustainability and adaptive c Request for Quota Single Stage - One E Pending Impl quipements d’élevage dans l IDA / D9220 apacity of the food system’s Post Open - National 50,000.00 0.00 2023-04-27 2023-06-19 2023-08-18 tions nvelope ementation e cadre du programme d'urg productive base ence dans la région des sava nes (PURS) TG-FSRP TOGO-357098-GO- RFB / Achat de couveuses de Sustainability and adaptive c Open - Internationa Single Stage - One E Pending Impl grandes capacités pour le co IDA / D9220 apacity of the food system’s Post Request for Bids 181,818.00 0.00 2023-05-19 2023-06-02 2023-07-17 2023-08-16 2023-09-20 2024-03-18 l nvelope ementation mplexe avicole de référence productive base d'Avetonou pour le compte d e l'ITRA TG-FSRP TOGO-357101-GO- Sustainability and adaptive c RFB / Acquisition et installati Open - Internationa Single Stage - One E Pending Impl IDA / D9220 apacity of the food system’s Post Request for Bids 472,727.00 0.00 2023-05-17 2023-05-31 2023-07-15 2023-08-14 2023-09-18 2023-12-17 on des kits d'irrigation au pr l nvelope ementation productive base ofit des producteurs de la rég ion des savanes TG-FSRP TOGO-358287-GO- Sustainability and adaptive c RFQ / Acquisition des poulets Request for Quota Single Stage - One E Under Imple IDA / D9220 apacity of the food system’s Post Limited 45,455.00 0.00 2023-06-01 2023-06-07 2023-07-20 2023-09-18 reproducteurs SASSO au prof tions nvelope mentation productive base it de l'ITRA (Ferme d'Avetono u) TG-FSRP TOGO-358276-GO- DIR / Acquisition des pièces d Digital advisory services for Direct - Internation Pending Impl e rechange et autres accesso IDA / D9220 agriculture and food crisis pr Post Direct Selection 1,090,909.00 0.00 2023-06-30 2023-07-05 2023-08-23 2024-02-19 al ementation ires pour la remise à niveau evention and management des stations météorologiques de l'ANAMET TG-FSRP TOGO-363533-GO- Sustainability and adaptive c RFB / Achat d'ingrédients pou Single Stage - One E Pending Impl IDA / D9220 apacity of the food system’s Post Request for Bids Open - National 181,818.00 0.00 2023-06-20 2023-07-04 2023-08-03 2023-08-18 2023-09-22 2024-09-21 r alimentation des volailles a nvelope ementation productive base u profit de l'ITRA (AVETONOU ) TG-FSRP TOGO-363538-GO- Sustainability and adaptive c RFB / Acquisition des équipe Open - Internationa Single Stage - One E Pending Impl IDA / D9220 apacity of the food system’s Post Request for Bids 318,181.00 0.00 2023-06-16 2023-06-30 2023-08-14 2023-09-13 2023-10-18 2024-04-15 ment d'analyse bromatologiq l nvelope ementation productive base ue rapide pour le compte de l 'ITRA (AVETONOU) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-FSRP TOGO-306337-GO- Request for Quota Single Stage - One E RFQ / Sélection d'une compa IDA / D9220 Project Management Post Limited 44,545.00 0.00 Signed 2022-08-29 2022-09-06 2022-10-24 2023-10-24 tions nvelope gnie d'assurance pour le pers onnel du projet TG-FSRP TOGO-306339-GO- Request for Quota Single Stage - One E RFQ / Service courant de gar IDA / D9220 Project Management Post Limited 21,818.00 0.00 Signed 2022-08-30 2022-09-06 2022-10-18 2024-10-17 tions nvelope diennage pour le FSRP TG-FSRP TOGO-305834-GO- RFQ / Sélection d’une firme p Digital advisory services for Request for Quota Single Stage - One E Under Imple our l’impression des cartes, d IDA / D9220 agriculture and food crisis pr Post Limited 72,727.00 0.00 2022-08-28 2022-11-08 2022-10-23 2023-10-23 tions nvelope mentation es bulletins d’information et evention and management d’alerte au profit de l’ANPC e t de la DGMN TG-FSRP TOGO-306351-NC- Request for Quota Single Stage - One E RFQ / Service courant d'une s IDA / D9220 Project Management Post Limited 18,182.00 0.00 Signed 2022-08-29 2022-09-05 2022-10-24 2024-10-23 tions nvelope ociété d'entretien pour le FS RP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-FSRP TOGO-305281-CS-L CS / Recrutement d'un audite Least Cost Selecti Under Implement ur externe pour l'audit financ IDA / D9220 Project Management Post Open - National 54,545.00 0.00 2022-08-31 2022-08-12 2022-09-21 2022-11-04 2022-12-02 2023-01-01 2023-02-05 2023-03-12 2023-06-10 on ation ier et comptable du projet FS RP (Exercice 2022, 2023, 202 4) TG-FSRP TOGO-306526-CS-I NDV / Selection d'un consulta Sustainability and adaptive c Quality And Cost- Open - Internationa Pending Impleme nt (cabinet) pour l'élaboratio IDA / D9220 apacity of the food system’s Post 109,091.00 0.00 2022-10-28 2022-11-18 2023-01-01 2023-01-29 2023-02-28 2023-04-04 2023-05-09 2023-08-07 Based Selection l ntation n du draft 1 de l'avant-projet productive base de loi portant régime foncier rural TG-FSRP TOGO-306602-CS-I NDV / Recrutement d'un cons Sustainability and adaptive c ultant pour l'étude environne Consultant Qualifi Pending Impleme IDA / D9220 apacity of the food system’s Post Limited 54,545.00 0.00 2022-09-20 2022-10-04 2022-11-03 2022-12-08 2023-03-08 mentale et sociale en vue de cation Selection ntation productive base l'aménagement de 5 ZAAP (5 00 ha) dans la région des sav anes TG-FSRP TOGO-315162-CS-C QS / Sélection d'un cabinet p Sustainability and adaptive c our l'étude de faisabilité tech Consultant Qualifi Pending Impleme IDA / D9220 apacity of the food system’s Post Limited 154,545.00 0.00 2022-10-25 2022-11-08 2022-12-08 2023-01-12 2023-06-11 nique et environnementale e cation Selection ntation productive base t sociale (APS, APD, EIES, DA O) pour la réhabilitation de 2 00 Km de pistes rurales TG-FSRP TOGO-320868-CS-L CS / Recrutement d’un consu Digital advisory services for Quality And Cost- Under Implement ltant (cabinet) pour la mise e IDA / D9220 agriculture and food crisis pr Post Open - National 36,364.00 0.00 2022-11-14 2022-10-27 2022-12-05 2023-01-18 2023-02-15 2023-03-17 2023-04-21 2023-05-26 2023-11-22 Based Selection ation n place de la base de donnée evention and management s nationales sur les catastrop hes agro climatiques TG-FSRP TOGO-338969-CS-I NDV / Recrutement d'un con sultant/cabinet pour les étud Sustainability and adaptive c Consultant Qualifi Pending Impleme es techniques, environnemen IDA / D9220 apacity of the food system’s Post Limited 90,909.00 0.00 2023-04-20 2023-04-30 2023-05-30 2023-07-05 2024-01-01 cation Selection ntation tales et sociales d'aménage productive base ment et réhabilitation des ret enues d'eau ( APS, APD, EIES ,DAO) Page 4 TG-FSRP TOGO-337941-CS-L CS / Recrutement d'un cabin Sustainability and adaptive c Quality And Cost- Under Implement et pour la surveillance et le c IDA / D9220 apacity of the food system’s Post Open - National 72,727.00 0.00 2023-04-10 2023-03-29 2023-04-24 2023-05-19 2023-06-03 2023-06-10 2023-06-24 2023-07-29 2024-01-25 Based Selection ation ontrôle de l'exécution des tra productive base vaux de réhabilitation de neu f (09) agences de l'ICAT TG-FSRP TOGO-337934-CS-L CS / Recrutement d'un cabin et pour la surveillance et le c ontrôle de l'exécution des tra Digital advisory services for Quality And Cost- Under Implement vaux de réhabilitation des ce IDA / D9220 agriculture and food crisis pr Post Open - National 90,909.00 0.00 2023-04-10 2023-04-10 2023-04-24 2023-05-19 2023-06-03 2023-06-10 2023-06-24 2023-07-25 2024-01-21 Based Selection ation ntres et stations météorologi evention and management ques de l'agence nationale d e la météorologie (ANAMET) dans 14 localités réparties da ns les 5 régions du TOGO TG-FSRP TOGO-357140-CS-Q CBS / Recrutement d'un cabi net pour la surveillance et le Sustainability and adaptive c contrôle de d'exécution des t Quality And Cost- Under Implement IDA / D9220 apacity of the food system’s Post Open - National 63,636.00 0.00 2023-05-08 2023-05-22 2023-06-17 2023-07-09 2023-08-08 2023-08-23 2023-09-14 2023-10-19 2024-04-16 ravaux d'aménagement du c Based Selection ation productive base omplexe avicole de référenc e d'Avetonou ainsi que de l'a ménagement de la voix d'acc ès au complexe TG-FSRP TOGO-363560-CS-Q CBS / Recrutement d'un cons ultant (cabinet) pour la mise Regional food market integr Quality And Cost- Under Implement IDA / D9220 Post Open - National 45,455.00 0.00 2023-06-21 2023-06-02 2023-08-05 2023-09-03 2023-10-01 2023-10-31 2023-12-05 2024-01-09 2024-03-09 en place d'un dispositif de ve ation and trade Based Selection ation ille informatique sur l'offre et la demande de marché au se in du CIFS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TG-FSRP TOGO-306507-CS-I NDV / Recrutement d'un spéc Regional food market integr Individual Consult Under Implement IDA / D9220 Post Open - National 36,364.00 0.00 2022-09-20 2022-11-08 2022-11-29 2023-01-03 2024-01-03 ialiste en gestion des instrum ation and trade ant Selection ation ents financiers et l'accès au marché TG-FSRP TOGO-306509-CS-I NDV / Recrutement d'un cons Digital advisory services for ultant pour l'élaboration d'un Individual Consult Under Implement IDA / D9220 agriculture and food crisis pr Post Open - National 18,182.00 0.00 2022-10-06 2022-10-12 2022-11-24 2022-12-15 2023-01-19 2023-07-18 e cartographie des acteurs in ant Selection ation evention and management tervenants dans la productio n des données météorologiq ues TG-FSRP TOGO-306515-CS-I NDV / Recrutement d'un cons ultant pour l'élaboration du d Digital advisory services for Individual Consult ocument sur la thématique R IDA / D9220 agriculture and food crisis pr Post Open - National 72,727.00 0.00 Signed 2022-09-15 2022-09-22 2022-11-03 2022-12-16 2022-11-24 2023-03-16 2022-12-29 2023-03-29 ant Selection RC en lien avec la résilience evention and management alimentaire et nutritionelle d ans les instruments de planifi cation du développement TG-FSRP TOGO-306552-CS-I NDV / Recrutement d'un cons ultant pour l'actualisation de s textes législatifs et régleme Regional food market integr Individual Consult IDA / D9220 Post Open - National 18,182.00 0.00 Signed 2022-11-25 2022-09-21 2023-01-13 2023-01-06 2023-02-03 2023-03-13 2023-03-10 2023-04-09 ntaires relatifs au stockage e ation and trade ant Selection t aux échanges commerciaux des produits alimentaires en lien avec les textes commun autaires et internationaux TG-FSRP TOGO-306557-CS-I NDV / Recrutement de chauff Individual Consult Under Implement IDA / D9220 Project Management Post Open - National 20,945.00 0.00 2022-08-22 2022-08-17 2022-10-10 2023-02-24 2022-10-31 2022-12-05 2023-12-05 eurs et de coursier au profit ant Selection ation de la Coordination du FSRP TG-FSRP TOGO-306554-CS-I NDV / Recrutement d'un cons ulant individuel pour le renfo Regional food market integr Individual Consult IDA / D9220 Post Limited 36,364.00 0.00 Signed 2022-09-15 2022-11-10 2022-09-20 2022-12-01 2022-10-11 2023-03-13 2022-11-15 2022-12-15 rcement des capacités des tr ation and trade ant Selection ois filières cibles (Riz, Sodja, Volailes) sur l'accès au marc hé dans le cadre de la ZELEC AF TG-FSRP TOGO-306521-CS-I Sustainability and adaptive c NDV / Recrutement d'un cons Individual Consult IDA / D9220 apacity of the food system’s Post Limited 36,364.00 0.00 Signed 2022-08-25 2022-09-21 2022-08-30 2022-10-21 2022-09-20 2023-04-04 2022-10-25 2022-12-24 utant pour l'élaboration de la ant Selection productive base stratégie de vulgarisation dig itale (e-extension) TG-FSRP TOGO-306513-CS-I NDV / Recrutement d'un cons Digital advisory services for Individual Consult ultant pour la mise en place IDA / D9220 agriculture and food crisis pr Post Open - National 18,182.00 0.00 Canceled 2022-08-30 2022-10-18 2022-11-08 2022-12-13 2023-03-13 ant Selection de la base de données nation evention and management ales sur les catastrophes agr o climatiques TG-FSRP TOGO-338956-CS-I NDV / Recrutement d'un cons utatnt pour le diagnostic des Digital advisory services for possibiltés d' intervention du Individual Consult Pending Impleme IDA / D9220 agriculture and food crisis pr Post Open - National 27,273.00 0.00 2023-03-17 2023-05-11 2023-06-01 2023-07-06 2023-09-04 secteur privé dans la product ant Selection ntation evention and management ion des données y compris l a stratégie de financement d e la production et d'accès au x données TG-FSRP TOGO-338958-CS-I NDV / Recrutement d'un cons Digital advisory services for ultant pour l'inventaire des p Individual Consult Pending Impleme IDA / D9220 agriculture and food crisis pr Post Open - National 18,182.00 0.00 2023-03-20 2023-05-14 2023-06-04 2023-07-09 2023-09-07 arties prenantes, y compris l ant Selection ntation evention and management es acteurs du secteur privée en matières de données et d e services HIA TG-FSRP TOGO-338960-CS-I NDV / Recrutement de consul Digital advisory services for tant pour l'elaboration d'un Individual Consult Under Implement IDA / D9220 agriculture and food crisis pr Post Open - National 14,545.00 0.00 2023-03-15 2023-03-15 2023-05-04 2023-05-25 2023-06-29 2023-08-28 manuel de méthodologie et d ant Selection ation evention and management es outils de collectes des prix des produits animaux et hali eutiques pour le SIM Page 5 TG-FSRP TOGO-338962-CS-I NDV / Recrutement d'un cons ultant pour la formation des Digital advisory services for Individual Consult Pending Impleme acteurs (DGMN, ANPC, DSID, IDA / D9220 agriculture and food crisis pr Post Open - National 36,364.00 0.00 2023-03-22 2023-05-11 2023-06-01 2023-07-06 2023-08-05 ant Selection ntation DPPSE)sur les logiciels de SI evention and management G/Cartographie, de télédétec tion, SimClim, Globalmapper …...) TG-FSRP TOGO-338965-CS-I NDV / Recrutement de consul Digital advisory services for Individual Consult Pending Impleme tant pour l'établissement de l IDA / D9220 agriculture and food crisis pr Post Open - National 72,727.00 0.00 2023-03-24 2023-05-08 2023-05-29 2023-07-03 2023-10-31 ant Selection ntation a cartographie des zones à ri evention and management sques (inondation, vent viole nt, éboulements etc) TG-FSRP TOGO-338967-CS-I NDV / Recrutement de consul Digital advisory services for tant pour la Conception de m Individual Consult Pending Impleme IDA / D9220 agriculture and food crisis pr Post Open - National 27,273.00 0.00 2023-03-30 2023-05-19 2023-06-09 2023-07-14 2023-09-12 odèle simplifie de prévision e ant Selection ntation evention and management t détermination des seuils d’ alerte aux inondations dans l es bassins fluviaux du Togo TG-FSRP TOGO-338968-CS-I NDV / Recrutement d'un cons Digital advisory services for Individual Consult Under Implement ultant pour l'opérationnalisati IDA / D9220 agriculture and food crisis pr Post Open - National 9,091.00 0.00 2023-03-28 2023-04-10 2023-05-17 2023-06-07 2023-07-12 2023-08-11 ant Selection ation on du système informatisé d evention and management e gestion de la traçabilité des semences TG-FSRP TOGO-338971-CS-I NDV / Recrutement d'un cons Regional food market integr Individual Consult Under Implement ultant pour la cartographiqu IDA / D9220 Post Open - National 45,455.00 0.00 2023-04-10 2023-05-23 2023-05-30 2023-06-20 2023-07-25 2023-09-08 ation and trade ant Selection ation e des zones de production bi ologiques et agroécologique à l'echelle nationale TG-FSRP TOGO-338975-CS-I NDV / Recrutement d'un con Digital advisory services for Individual Consult Pending Impleme sultant pour l'étude diagnosti IDA / D9220 agriculture and food crisis pr Post Open - National 18,182.00 0.00 2023-04-04 2023-05-24 2023-06-14 2023-07-15 2023-07-18 ant Selection ntation que, l'élaboration et la valid evention and management ation des textes réglementan t l'accès aux données TG-FSRP TOGO-338979-CS-I NDV / recrutement d'un cons Regional food market integr Individual Consult Open - Internationa Under Implement ultant international pour app IDA / D9220 Post 45,455.00 0.00 2023-03-08 2023-04-10 2023-04-27 2023-05-18 2023-06-22 2023-08-21 ation and trade ant Selection l ation uyer la certification de cents (100) produits agroalimentair es prioritaires togolais TG-FSRP TOGO-357122-CS-I NDV / Mise en place d’un dis Regional food market integr Individual Consult Under Implement IDA / D9220 Post Open - National 45,455.00 0.00 2023-05-08 2023-05-05 2023-06-20 2023-07-11 2023-08-15 2023-10-14 positif de collecte des besoin ation and trade ant Selection ation s en intrants au sein du CIFS TG-FSRP TOGO-357129-CS-I NDV / Recrutement d’un cons ultant pour l’identification, la Sustainability and adaptive c Individual Consult Under Implement caractérisation et la de limita IDA / D9220 apacity of the food system’s Post Open - National 45,455.00 0.00 2023-05-08 2023-05-05 2023-07-05 2023-07-26 2023-08-30 2023-10-29 ant Selection ation tion du paysage d’interventio productive base n pour la mise en œuvre de l’ approche gestion intégrée du paysage TG-FSRP TOGO-357111-CS-I NDV / Recrutement d'un cons ultant pour la mise en place Regional food market integr Individual Consult IDA / D9220 Post Open - National 45,455.00 0.00 Canceled 2023-05-08 2023-07-06 2023-07-27 2023-08-31 2023-10-30 d'un dispositif de veille infor ation and trade ant Selection matique sur l'offre et la dem ande de marché au sein du C IFS Page 6 PROCUREMENT PLAN General 1. Project Information a. Country: Federal Republic of Somalia b. Project Name: Somalia Capacity Advancement, Livelihoods and Entrepreneurship, through Digital Uplift Program (SCALED-UP) c. Project Number: P168115 d. Total Finance: USD 31 Million 2. Project Implementation Agency: Somalia Ministry of Finance 3. Date of Project Plan: January 31, 2019 4. Period Covered by this Procurement: May 2019 – November 2020 I. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. II. Bank’s Standard Procurement Document: The Bank’s standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified into Procurement Plan tables in STEP III. National Procurement Arrangements: Not applicable IV. Prequalification: Not applicable V. Leased Assets: Not Applicable VI. Procurement of Second hand Goods: Not Applicable VII. Domestic Preference: Not Applicable 1 VIII. Hands on Expanded Implementation Support (HEIS): Not Applicable IX. Other Relevant Procurement Information: Not Applicable X. Thresholds for Procurement Approaches and Method (US$ millions) Thresholds for Procurement Approaches and Methods (US$ millions)–Goods, Works, and Non-Consulting Services Category Prior Open Open Request for Review Internation National Quotation (US$ al (RfQ) millions) Works All ≥ 5.0 < 5.0 ≤ 0.2 Goods, IT, All ≥ 0.5 < 0.5 ≤ 0.1 and non- consulting services Thresholds for Procurement Approaches and Methods (US$, millions) – Consulting Services Category Prior Review Short List of National (US$, millions) Consultants Consulting Engineering Services and Construction Supervision Consultants all ≤0.1 ≤0.2 (Firms) Individual all N/A N/A Consultants 2 XI. Packages for Goods, Works and Non-Consulting Services (At Negotiations – to be entered in STEP) Pr Revi Procur Selecti eq ew Evaluati ement Dom Market on ual by on Proces estic Expecte Expecte Approac Metho ific Estimate Ban Options s Pref d date of d date of Ref. Contract h (Open- d ati d Cost k (BAFO (Single eren bid/ Contract No Description National/ (RFP, on (US$) (Pri Rated stage- ce proposal Signatur Limited RFB, (Ye or/ Criteria single (Yes opening e etc.) RFQ s/ Post etc.) envelo /No) etc.) No ) pe etc.) ) GOODS Data Center equipment and software including: Singe Open Lowest 30th Security systems and stage 1st Jan, G1 $500,000 Prior Internatio RFQ Evaluate N/A N/A March equipment, Fraud One - 2020 nal d Cost 2020 monitoring and Envelop detection system (NCA) Office Equipment Single (Laptops, Desktops, Lowest Open stage 30/Octob 30/Novem G2 Projector, Printers $160,000 Prior RFB Evaluate N/A N/A National One- er/2019 ber/2019 and accessories) d Cost Envelop (NCA and ID) Singe Lowest Purchase of vehicles Open stage 20/Novem 10/Januar $80,000 Prior RFQ Evaluate N/A N/A G3 (NCA and ID) National One - ber/2019 y/2020 d Cost Envelop 3 Pr Revi Procur Selecti eq ew Evaluati ement Dom Market on ual by on Proces estic Expecte Expecte Approac Metho ific Estimate Ban Options s Pref d date of d date of Ref. Contract h (Open- d ati d Cost k (BAFO (Single eren bid/ Contract No Description National/ (RFP, on (US$) (Pri Rated stage- ce proposal Signatur Limited RFB, (Ye or/ Criteria single (Yes opening e etc.) RFQ s/ Post etc.) envelo /No) etc.) No ) pe etc.) ) Single Office furniture Lowest Stage 30/Januar 30/Februa (Chairs, Tables) $80,000 Prior Limited RFQ Evaluate N/A N/A G4 One- y/2020 ry/2020 (NCA and ID) d Cost Envelop Fixed spectrum monitoring and management Single Lowest equipment, Open Stage 01/Jun/20 01/Jul/201 G5 $120,000 Prior RFB Evaluate N/A N/A Spectrum National One- 19 9 d Cost management and Envelop monitoring system (NCA) Procurement of a suitable software platform to meet the Single CBS regulatory Open- Lowest Stage 01/Januar 01/April/2 G9 reporting and 1,100,000 Prior Internatio RFB Evaluate N/A N/A One- y/2020 020 effective analysis of nal d Cost Envelop financial risks (RegTech) for Central Bank 4 Pr Revi Procur Selecti eq ew Evaluati ement Dom Market on ual by on Proces estic Expecte Expecte Approac Metho ific Estimate Ban Options s Pref d date of d date of Ref. Contract h (Open- d ati d Cost k (BAFO (Single eren bid/ Contract No Description National/ (RFP, on (US$) (Pri Rated stage- ce proposal Signatur Limited RFB, (Ye or/ Criteria single (Yes opening e etc.) RFQ s/ Post etc.) envelo /No) etc.) No ) pe etc.) ) Procurement of a suitable software platform to meet the Financial Reporting Center (FRC) Single Open- Lowest requirements for Stage 01/Januar 01//April/ G10 1,300,000 Prior Internatio RFB Evaluate N/A N/A effective analysis One- y/2019 2020 nal d Cost and investigation of Envelop suspected cases of money laundering or financing of terrorism (FRC) Laptops for the new Single consultants, Office Lowest Stage 1stJanuary 1st March G11 chairs and tables 30,000 Prior Limited RFQ Evaluate N/A N/A One- 2020 2020 (Project Management d Cost Envelop (FRC) $3,370,0 Total Goods 00 WORKS W1 N/A Total Works Non -Consulting Services 5 Pr Revi Procur Selecti eq ew Evaluati ement Dom Market on ual by on Proces estic Expecte Expecte Approac Metho ific Estimate Ban Options s Pref d date of d date of Ref. Contract h (Open- d ati d Cost k (BAFO (Single eren bid/ Contract No Description National/ (RFP, on (US$) (Pri Rated stage- ce proposal Signatur Limited RFB, (Ye or/ Criteria single (Yes opening e etc.) RFQ s/ Post etc.) envelo /No) etc.) No ) pe etc.) ) Total Non- Consultant Service Consulting Services Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Individual Consultant for Financial Sector Specialist(Fintech) C1 100,000 Prior Open INDV N/A 01/June/2019 30/July/2019 and focal point of CBS on Scaled-up- to support Central Bank Consultancy services to: i) draft secured Open - C2 300,000 Prior QCBS N/A 15/June/2019 15/August2019 transaction and International credit referencing law that 6 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS establishes a modern legal framework enabling efficient intermediation, and ii) draft regulations under a modern FIL, National Payment Systems Law and Insurance Law to support Central Bank Individual AML/CFT expert to support the planned 2021 Mutual Evaluation and Financial C3 Reporting Center 100,000 Prior Open INDV N/A 01/June/2019 30/July/2019 (FRC) organizational development and Focal point to Scaled-Up to support FRC 7 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Policy Advisor- Focal Point MPTT 100,000 C4 Prior Open INDV N/A 30/June 2019 20/August/2019 to Scaled up - NCA Consultancy services to provide ICT Sector Open – 09/Septembe C5 200,000 Prior CQS N/A 26/November2019 Strategy for International r/2019 Women in ICT (MPTT) - NCA Consultancy to provide ICT Sector Open – 09/October/2 30/December/201 C6 Strategy for 200,000 Prior CQS N/A International 019 9 Youth in ICT (MPTT) Consultancy to provide ICT Sector Strategy for Open – 15/Novembe C7 200,000 Prior CQS N/A 10/January/2020 ICT for the International r/2019 disabled (MPTT) - - NCA Consultancy to provide Regulatory Capacity Building 200,000 Open – 25/Novembe C8 Prior CQS N/A 26/January/2020 and Advisory International r/2019 Services on technical aspects including 8 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Spectrum Management including 4G spectrum allocation, and SIM card registry (NCA) Consultancy service to provide logistical, transport and travel support for Open – 15th January C9 public 100,000 Prior CQS N/A 1st March 2020 International 2020 consultations, workshops, seminars, and select meetings (NCA) Consultancy 20th January C10 services for 100,000 Prior Open INDV N/A 10th March 2020 2020 Regulation (NCA) Consultancy C11 services for 100,000 Prior Open INDV N/A 1st Feb 2020 15th March 2020 Licensing (NCA) Consultancy service for 15th Feb C12 100,000 Prior Open INDV N/A 30th March 2020 Interconnection 2020 (NCA) 9 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Consultancy 25th Feb C13 service for Mobile 100,000 Prior Open INDV N/A 10th April 2020 2020 Money (NCA) Consultancy service for SIM 1st March C14 100,000 Prior Open INDV N/A 20th April 2020 card registration 2020 (NCA) Consultancy 10th Sept C15 service for 100,000 Prior Open INDV N/A 10th Nov 2020 2020 Spectrum (NCA) Consultancy 20th March C16 service for 100,000 Prior Open INDV N/A 20th May 2020 2020 Numbering (NCA) Consultancy service for Sector 1st Sept t C17 100,000 Prior Open INDV N/A 1st Nov 2020 Economic Analysis 2020 (NCA) Services of a Senior Resident C18 Regulatory 100,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 Advisor to NCA (ITT) Services of a Licensing C19 60,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 Specialist to NCA (ITT) Services of a C20 60,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 Spectrum 10 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Specialist to NCA (ITT) Services of a C21 Finance Specialist 60,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 to NCA (ITT) Services of an Accounting C22 60,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 Specialist to NCA (ITT) Services of a Pricing and Cyber C23 60,000 Prior Open INDV N/A 01/Oct/2019 30/Nov/2019 Security Specialist to NCA (ITT) Digital Identification System C24 Consultant and 108,000 Prior Open INDV N/A 30/May/2019 01/July/2019 Focal Point for ID to Scaled-up Project Consultancy to support the development of a comprehensive Open – C25 450,000 Prior QCBS N/A 30/May/2019 01/August/2019 legal framework International for the digital ID system, including to address data 11 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS protection, privacy, and cybersecurity (Digital ID) Consultancy to provide Advisory Services and Capacity Building on technical aspects of the digital ID system, Open – C26 400,000 Prior QCBS N/A 01/June/2019 30/Aug/2019 incl. database International mgmt., registration, and credential issuance, and authentication (Digital ID) Consultancy to provide Capacity Building and Advisory Services on the Open – C27 operationalization 300,000 Prior QCBS N/A 30/June/2019 30/August2019 International of an ID authority (incl. governance arrangements, organizational structure, 12 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS business plan) (ID authority) Consultancy service to provide logistical, transport and travel support for public Open – C28 100,000 Prior CQS N/A 30/June/2019 30/August/2019 consultations, National workshops, seminars, trainings, and meetings (Digital ID) Consultancy to develop Grievance Redressal Mechanisms, Social Management Plan Open – 01/Septembe C29 to address 250,000 Prior CQS N/A 30/October/2019 National r/2019 ongoing risks of exclusion and risk of data protection, and to design Digital ID Outreach Strategy to women and 13 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS other vulnerable groups (Digital ID) Consultancy to integrate the use of digital IDs in the financial Open – 15/October2 C30 250,000 Prior CQS N/A 15/December2019 sector, including National 019 for KYC and payment systems (Digital ID) Services of a Project Coordinator to the Open – 20/October/2 20/December/201 C31 ID unit/authority 60,000 Prior INDV N/A National 019 9 (could also be under Comp 2 or 3) Services of a Technical ID Open - 30/Septembe 30/November/201 C32 Solutions 80,000 Prior INDV N/A International r/2019 9 Specialist to the ID unit/authority Services of an ID Information Open - 03/October 03/December/201 C33 Systems 80,000 Prior INDV N/A International /2019 9 Specialist to the ID unit/authority 14 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Services of a Financial Sector Specialist to the Open - 30/Septembe 03/November/201 C34 60,000 Prior INDV N/A ID unit (could also National r/2019 9 be under Comp 2 or 3) Services of a Communications and Grievance Open - 30/Septembe 03/November/201 C35 60,000 Prior INDV N/A Redressal National r/2019 9 Specialist to the ID unit Consultancy service to design and implement Citizen Open – 01/Sep/2019 01/Nov/2019 C36 600,000 Prior QCBS N/A Engagement and International Communications Campaign [Component 2.2] Consultancy service to implement ID Open – 01/Sep/2019 01/Nov 2019 C37 (mass) 2,400,000 Prior QCBS N/A International registration for 1 million residents [Component 2.2] Payment System Open – C38 162,000 Prior INDV 20/Aug/2019 30/October2019 Consultant to International 15 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS support interoperability of retail payment systems and mobile money services Individual consultancy services for digital registration Open – C39 100,000 Prior INDV N/A 30/Aug/2019 30/October/2019 services for International business at MoCI and Scaled-Up Focal Point PIU Personnel (PIU) Coordinator, Procurement Direct C40 Specialist and 396,000 Prior DIR N/A 15/May/2019 15/June/2020 Selection Financial Management Specialist) Monitoring Agent Open – 30/October/2 20/December/201 C41 300,000 Prior CQS N/A (PIU) International 019 9 Environmental and Social Open – C42 100,000 Prior INDV N/A 20/June/2019 30/August/2019 Safeguards International Consultant (PIU) 16 Selecti Market on Review by Approach Shortli Expected Estimate Method Expected Date Contract Bank (Open- sting Date of Bid Ref No. d Cost (QCBS, of Contract Description (Prior/Pos National/ (Yes/N Proposal (US$) LCBCS, Signature t) Limited o) Opening QBS, etc.) DS Monitoring and Open – C43 Evaluation 100,000 Prior INDV N/A 30/June/2019 01/August/2019 International Specialist Grievance Open – 30/Novembe C44 Redress Services 100,000 Prior INDV N/A 30/January/2020 International r/2019 Advisor (PIU) Investment Advisor for the Open – 30/October2 28/December/201 C45 100,000 Prior INDV N/A MSME Financing International 019 9 Facility (PIU) 9,256,00 Total Consulting 0 Services 12,626,0 Grand total 00 17 PROCUREMENT Somalia : Somalia Capacity Advancement, Livelihoods and Entrepreneurship, through Digital Uplift Project (SCALED-UP) PLAN General Information Country: Somalia Bank’s Approval Date of the Original Procurement Plan: 2019-04-24 Revised Plan Date(s): (comma delineated, leave blank if 2023-06-07 none) Project ID: P168115 GPN Date: Project Name: Somalia Capacity Advancement, Livelihoods and Entrepreneurship, through Digital Uplift Project (SCALED-UP) Loan / Credit No: IDA / D4330, TF / A9642, IDA / D8430, TF / B5774 Federal Republic of Somalia, Ministry of Finance, Office of the Director General Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-125939-GO-RFQ / IT Project Management and Co Request for Quota Single Stage - One E Under Imple IDA / D4330 Prior Limited 20,000.00 0.00 2019-08-12 2020-01-28 2019-10-07 2020-04-04 Equipment for Gargaara Offic ordination tions nvelope mentation e SO-MOF-125942-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Under Imple IDA / D4330 Prior Limited 20,000.00 0.00 2019-08-12 2019-12-12 2019-10-07 2020-04-04 ffice Furniture for Gargaara O ordination tions nvelope mentation ffice SO-MOF-133514-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 24,000.00 0.00 2019-09-17 2019-12-12 2019-11-12 2020-05-10 ffice Furniture for FRC ordination tions nvelope mentation SO-MOF-133517-GO-RFQ / IT Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 34,000.00 0.00 2019-09-16 2019-12-12 2019-11-11 2020-05-09 Equipment for FRC Office ordination tions nvelope mentation SO-MOF-147025-GO-RFQ / M Project Management and Co Request for Quota Single Stage - One E Under Imple IDA / D4330 Prior Limited 16,000.00 0.00 2019-12-01 2019-12-22 2020-01-05 2020-02-04 aterials to renovate Gargaara ordination tions nvelope mentation Office SO-MOF-157419-GO-RFQ / O Request for Quota Single Stage - One E Under Imple TF / A9642 Strengthening Institutions Prior Limited 18,000.00 0.00 2020-02-16 2020-02-28 2020-03-21 2020-05-20 ffice Renovation Materials for tions nvelope mentation FRC SO-MOF-147502-GO-RFQ / M Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 15,000.00 0.00 Canceled 2019-12-04 2020-01-07 2020-03-07 aterials to renovate FRC Offic tions nvelope e SO-MOF-158312-GO-RFQ / IT Project Management and Co Request for Quota Single Stage - One E Pending Impl TF / A9642 Post Limited 40,000.00 0.00 2020-02-16 2020-03-22 2020-05-21 Equipment for NCA ordination tions nvelope ementation SO-MOF-158311-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Pending Impl TF / A9642 Post Limited 30,000.00 0.00 2020-02-18 2020-03-25 2020-05-24 ffice Furniture for NCA ordination tions nvelope ementation SO-MOF-164727-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 36,000.00 0.00 2020-03-25 2020-05-13 2020-05-01 2020-06-19 ffice Vehicle for Gargaara ordination tions nvelope mentation SO-MOF-176028-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Pending Impl TF / A9642 Post Limited 15,000.00 0.00 2020-06-05 2020-07-12 2020-09-10 ffice Furniture for Switch Con ordination tions nvelope ementation sultants SO-MOF-176029-GO-RFQ / IT Project Management and Co Request for Quota Single Stage - One E Pending Impl Equipment for Switch Project TF / A9642 Post Limited 13,000.00 0.00 2020-06-05 2020-07-12 2020-09-10 ordination tions nvelope ementation Consultants SO-MOF-157412-GO-RFB / D esign, supply, installation, co Open - Internationa Single Stage - One E mmissioning and support of i TF / A9642 Strengthening Institutions Prior Request for Bids 500,000.00 0.00 Canceled 2020-02-13 2020-03-01 2020-02-18 2020-04-24 2020-03-31 2020-04-30 2020-06-04 2020-12-01 l nvelope nformation technology infras tructure ( Hardware and Soft ware) for goAML for FRC SO-MOF-182695-GO-RFB / D esign, supply, installation, co Open - Internationa Single Stage - One E mmissioning and support of i TF / A9642 Strengthening Institutions Prior Request for Bids 500,000.00 533,413.00 Signed 2020-06-30 2020-07-08 2020-07-05 2020-07-09 2020-08-16 2020-08-22 2020-09-15 2020-10-04 2020-10-20 2020-11-15 2021-06-17 l nvelope nformation technology infras tructure ( Hardware and Soft ware) for goAML for FRC SO-MOF-186149-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 20,000.00 0.00 2020-07-30 2020-08-07 2020-09-03 2020-09-07 ffice Furniture for State Attor ordination tions nvelope mentation ney General SO-MOF-186151-GO-RFQ / IT Project Management and Co Request for Quota Single Stage - One E Under Imple Equipment for Office of State TF / A9642 Prior Limited 10,000.00 0.00 2020-08-02 2020-08-20 2020-09-01 2020-10-11 ordination tions nvelope mentation Attorney General SO-MOF-194580-GO-DIR / "D esign, Supply, Installation, Co mmissioning and Support for Information Technology Infra structure (ITI) covering Telec TF / A9642 Strengthening Institutions Prior Direct Selection Direct 586,355.28 595,823.09 Signed 2020-09-18 2020-10-01 2020-09-23 2020-10-30 2020-09-28 2021-03-04 2021-03-27 ommunication Networks, Mo dular Data Centers and LAN Network Infrastructure Tender No.SO-MoF-2018-3-G O-RFB i SO-MOF-194583-GO-DIR / D esign, Supply, Installation, Co TF / A9642 Strengthening Institutions Prior Direct Selection Direct 1,016,620.00 1,016,620.00 Signed 2020-09-18 2020-10-01 2020-09-23 2020-11-08 2020-09-27 2021-07-21 2021-03-26 mmissioning and Support for “National Switch of Somalia” (NSS) SO-MOF-194584-GO-DIR / D esign, Supply, Installation, Co mmissioning and Support for TF / A9642 Strengthening Institutions Prior Direct Selection Direct 1,468,677.00 507,323.50 Signed 2020-09-18 2020-10-01 2020-09-23 2020-11-08 2020-09-29 2021-08-27 2021-03-28 an Automated Transfer Syste m + (ATS+) - “Somalia Trans action Automation and Repor ting System” (STARS) SO-MOF-195729-GO-RFQ / G Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 40,000.00 0.00 2020-09-27 2020-10-04 2020-10-25 2021-04-23 argaara Vehicle ordination tions nvelope mentation Page 1 SO-MOF-205114-GO-RFQ / IC Request for Quota Single Stage - One E T Equipment for Office of Sta TF / A9642 Strengthening Institutions Prior Limited 10,000.00 0.00 Terminated 2020-11-24 2020-12-23 2020-12-29 2021-02-22 2021-02-27 tions nvelope te Attorney General SO-MOF-205304-GO-RFQ / O Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 52,960.00 96,500.00 Signed 2020-11-25 2021-01-20 2020-12-22 2021-02-24 2021-02-20 ffice Renovation Materials for tions nvelope SPS Office SO-MOF-206419-GO-RFQ / H Request for Quota Single Stage - One E Under Imple ardware requirement for goA TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 2020-12-02 2021-01-02 2021-07-01 tions nvelope mentation ML Infrastructure for FRC SO-MOF-208281-GO-RFQ / IT Request for Quota Single Stage - One E Under Imple TF / A9642 Strengthening Institutions Prior Limited 8,000.00 0.00 2020-12-13 2020-12-14 2021-01-11 2021-03-12 I Network Monitoring Servers tions nvelope mentation for CBS SO-MOF-212376-GO-RFQ / IT Request for Quota Single Stage - One E Under Imple TF / A9642 Strengthening Institutions Prior Limited 29,100.00 0.00 2021-01-13 2021-02-16 2021-04-17 Equipment for Office of Switc tions nvelope mentation h Project. SO-MOF-212381-GO-RFQ / O Request for Quota Single Stage - One E Pending Impl TF / A9642 Strengthening Institutions Prior Limited 15,000.00 0.00 2021-01-13 2021-02-16 2021-04-17 ffice Furniture for Office of S tions nvelope ementation witch Project SO-MOF-215205-GO-DIR / Cl oud hosting, storages and So Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 90,000.00 86,925.45 Signed 2021-01-31 2021-02-11 2021-03-28 2021-03-02 2021-09-24 ftware Licenses Procurement tions nvelope for the Office of Accountant General SO-MOF-217738-GO-RFQ / IT Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 50,000.00 52,358.00 Signed 2021-02-11 2021-02-23 2021-03-14 2021-08-03 2021-05-13 Equipment for NCA Office tions nvelope SO-MOF-217739-GO-RFQ / O Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 40,000.00 46,175.00 Signed 2021-02-13 2021-02-23 2021-03-16 2021-05-05 2021-05-15 ffice Furniture for NCA Office tions nvelope SO-MOF-235209-GO-RFQ / IT Request for Quota Single Stage - One E Equipment for Ministry of Co TF / A9642 Strengthening Institutions Prior Limited 15,000.00 0.00 Terminated 2021-05-29 2021-10-15 2021-07-24 2022-02-28 2022-01-20 tions nvelope mmerce and Industry SO-MOF-235195-GO-RFQ / IT Request for Quota Single Stage - One E Under Imple Equipment for Office of State TF / A9642 Strengthening Institutions Prior Limited 10,000.00 0.00 2021-05-28 2021-06-08 2021-07-23 2022-01-19 tions nvelope mentation Attorney General SO-MOF-239372-GO-RFQ / IT Request for Quota Single Stage - One E Under Imple TF / A9642 Strengthening Institutions Prior Limited 29,000.00 0.00 2021-06-21 2021-06-28 2021-08-16 2022-02-12 Equipment for Switch Compa tions nvelope mentation ny Office SO-MOF-244698-GO-RFB / O Open - Internationa Single Stage - One E racle EBS Development & Su TF / A9642 Strengthening Institutions Prior Request for Bids 400,000.00 395,000.00 Signed 2021-07-26 2021-08-03 2021-07-31 2021-08-04 2021-09-11 2021-09-17 2021-10-11 2021-12-02 2021-11-15 2021-12-15 2022-11-15 l nvelope pport Maintenance for Centra l Bank SO-MOF-244700-GO-RFQ / IC Project Management and Co Request for Quota Single Stage - One E Pending Impl T Equipment for the Project I TF / A9642 Prior Limited 20,000.00 0.00 2021-08-02 2021-09-27 2022-03-26 ordination tions nvelope ementation mplementation Unit SO-MOF-248597-GO-RFQ / V Project Management and Co Request for Quota Single Stage - One E TF / A9642 Prior Limited 50,000.00 45,000.00 Signed 2021-08-25 2021-08-27 2021-10-02 2021-11-14 2022-03-31 ehicle for PIU Office ordination tions nvelope SO-MOF-248598-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Pending Impl TF / A9642 Prior Limited 20,000.00 0.00 2021-08-25 2021-10-02 2022-03-31 ffice Furniture of PIU ordination tions nvelope ementation SO-MOF-259560-GO-RFQ / V Enabling Financial and Digit Request for Quota Single Stage - One E ehicle for Gargaara Company IDA / D4330 Prior Limited 50,000.00 40,000.00 Signed 2021-10-30 2021-10-29 2021-12-06 2021-11-18 2022-06-04 al Services tions nvelope Limited Office SO-MOF-261494-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 20,000.00 0.00 2021-11-13 2021-11-12 2021-12-16 2022-06-14 ffice Furniture for PIU ordination tions nvelope mentation SO-MOF-261477-GO-RFQ / IC Request for Quota Single Stage - One E T Equipment for PIU Office an TF / A9642 Strengthening Institutions Prior Limited 93,000.00 94,468.00 Signed 2021-11-13 2021-11-12 2021-12-03 2021-12-21 2022-06-01 tions nvelope d for Office of Accountant Ge neral SO-MOF-261945-GO-RFQ / IC Enabling Financial and Digit Request for Quota Single Stage - One E Under Imple T Equipment for Gargaara Co IDA / D4330 Prior Limited 20,000.00 0.00 2021-11-15 2021-12-08 2021-12-23 2022-06-21 al Services tions nvelope mentation mpany Limited SO-MOF-266889-GO-RFQ / O Request for Quota Single Stage - One E Under Imple ffice Furniture for Ministry of TF / A9642 Strengthening Institutions Prior Limited 20,000.00 0.00 2021-12-12 2021-12-09 2022-02-06 2022-08-05 tions nvelope mentation Commerce and Industry SO-MOF-287355-GO-RFQ / IC Enabling Financial and Digit Request for Quota Single Stage - One E Under Imple T Equipment for Gargaara Co IDA / D4330 Prior Limited 20,000.00 0.00 2022-04-09 2022-04-12 2022-05-13 2022-11-09 al Services tions nvelope mentation mpany Limited SO-MOF-294240-GO-RFQ / IC Request for Quota Single Stage - One E Under Imple TF / B5774 Strengthening Institutions Prior Limited 25,000.00 0.00 2022-05-16 2023-03-09 2022-06-19 2022-12-16 T Equipment for FRC tions nvelope mentation SO-MOF-294242-GO-RFQ / O Request for Quota Single Stage - One E Under Imple TF / B5774 Strengthening Institutions Prior Limited 50,000.00 0.00 2022-05-16 2022-07-26 2022-06-19 2022-12-16 ffice Furniture for FRC tions nvelope mentation SO-MOF-299091-GO-RFB / C Under Imple ORE-BANKING TEMENOS T24 TF / B5774 Strengthening Institutions Prior Request for Bids Direct 350,000.00 0.00 2022-06-10 2022-06-21 2022-06-18 2022-06-27 2022-07-29 2023-07-29 mentation UPGRADE FOR CENTRAL BAN K SO-MOF-301667-GO-RFQ / Pr ovision and implementation Request for Quota Single Stage - One E TF / B5774 Strengthening Institutions Prior Limited 100,000.00 0.00 Canceled 2022-07-05 2022-08-15 2022-08-30 2023-02-26 of Splunk Enterprise security tions nvelope system for Central Bank. SO-MOF-343154-GO-RFQ / O Request for Quota Single Stage - One E Pending Impl TF / B5774 Strengthening Institutions Prior Limited 30,000.00 0.00 2023-02-26 2023-04-23 2023-07-02 ffice furniture for Gargaara tions nvelope ementation SO-MOF-345380-GO-RFQ / Pr ovision and implementation Request for Quota Single Stage - One E Under Imple TF / B5774 Strengthening Institutions Prior Limited 100,000.00 0.00 2023-03-05 2023-05-09 2023-04-30 2023-10-27 of Splunk Enterprise security tions nvelope mentation system for Central Bank SO-MOF-360532-GO-RFQ / IC Request for Quota Single Stage - One E Pending Impl TF / B5774 Strengthening Institutions Prior Limited 95,000.00 0.00 2023-05-23 2023-07-18 2023-09-16 T Equipment for NIRA tions nvelope ementation SO-MOF-360537-GO-RFQ / V Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 60,000.00 0.00 2023-05-31 2023-07-26 2023-09-24 ehicle for PIU ordination tions nvelope mentation Page 2 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-129803-NC-RFQ / Of Project Management and Co Request for Quota Single Stage - One E IDA / D4330 Prior Limited 44,000.00 205,440.00 Signed 2019-09-14 2020-02-10 2019-11-09 2020-02-23 2019-12-01 fice Rent for Gargaara Comp ordination tions nvelope any SO-MOF-145412-NC-RFQ / C omprehensive Brand Visual I Request for Quota Single Stage - One E Under Imple IDA / D4330 Strengthening Institutions Prior Limited 11,000.00 0.00 2019-11-22 2019-12-12 2019-12-20 2020-02-18 dentity & Development Servi tions nvelope mentation ce for Gargaara Company SO-MOF-176015-GO-RFQ / O Project Management and Co Request for Quota Single Stage - One E Pending Impl TF / A9642 Post Limited 50,000.00 0.00 2020-06-05 2020-07-31 2021-07-31 ffice Rent for Switch Compan ordination tions nvelope ementation y SO-MOF-189485-NC-DIR / Or acle Cloud Infrastructure for TF / A9642 Strengthening Institutions Prior Direct Selection Direct 500,000.00 416,350.00 Signed 2020-08-20 2020-08-25 2020-08-22 2020-10-15 2020-08-29 2020-11-10 2022-08-19 Somalia Stars Project for Cen tral Bank SO-MOF-192239-NC-DIR / T2 TF / A9642 Strengthening Institutions Prior Direct Selection Direct 60,000.00 296,712.50 Signed 2020-09-09 2020-09-16 2020-09-14 2020-10-26 2020-09-19 2020-12-25 2020-11-18 4 Integration to STARS for Ce ntral Bank SO-MOF-198928-NC-RFB / Or Single Stage - One E Under Imple TF / A9642 Strengthening Institutions Prior Request for Bids Limited 400,000.00 0.00 2020-10-12 2020-10-21 2020-10-17 2020-10-28 2020-11-28 2020-12-22 2020-12-10 2021-04-19 2021-01-05 2022-01-05 acle Partner for CBS nvelope mentation SO-MOF-221827-NC-RFQ / in Request for Quota Single Stage - One E TF / A9642 Strengthening Institutions Prior Limited 24,000.00 22,800.00 Signed 2021-03-04 2021-03-08 2021-04-10 2021-05-03 2022-04-10 ternet connection to MoCI tions nvelope SO-MOF-238583-NC-RFB / Or Single Stage - One E acle EBS Development & Sup TF / A9642 Strengthening Institutions Prior Request for Bids Open - National 400,000.00 0.00 Canceled 2021-06-13 2021-06-18 2021-07-30 2021-08-29 2021-10-03 2022-10-03 nvelope port Maintenance for Central Bank SO-MOF-239371-NC-RFQ / Tr anslations of the Radio Frequ Request for Quota Single Stage - One E Under Imple ency Spectrum Policy and th TF / A9642 Strengthening Institutions Prior Limited 30,000.00 0.00 2021-06-21 2021-06-28 2021-08-16 2022-02-12 tions nvelope mentation e Numbering Policy for Minist ry of Communication and Tec hnology SO-MOF-258720-NC-RFQ / Cl oud dedicated server hosting Project Management and Co Request for Quota Single Stage - One E Under Imple TF / A9642 Prior Limited 96,000.00 0.00 2021-10-31 2021-12-07 2022-06-05 and software license for ongo ordination tions nvelope mentation ing activities of Ministry of Fi nance Website SO-MOF-259985-NC-RFB / Or Open - Internationa Single Stage - One E Pending Impl acle Software Update License TF / A9642 Strengthening Institutions Prior Request for Bids 206,000.00 0.00 2021-11-01 2021-11-06 2021-12-18 2022-01-07 2022-01-24 2023-01-24 l nvelope ementation and Support to CBS SO-MOF-259987-NC-RFQ / T Request for Quota Single Stage - One E Under Imple emenos T24 R16 Cloud Base TF / A9642 Strengthening Institutions Prior Limited 50,000.00 0.00 2021-11-06 2021-11-03 2021-12-13 2022-06-11 tions nvelope mentation d Disaster Recover Solution f or CBS SO-MOF-259990-NC-RFQ / T Request for Quota Single Stage - One E Under Imple 24-SFMIS BULK Transactions TF / A9642 Strengthening Institutions Prior Limited 51,000.00 0.00 2021-11-06 2021-11-03 2021-12-14 2022-06-12 tions nvelope mentation Straight Through Processing (STP) for CBS SO-MOF-287352-NC-DIR / Or Under Imple acle Database Enterprise Edit TF / B5774 Strengthening Institutions Prior Direct Selection Direct 200,000.00 0.00 2022-04-01 2022-04-08 2022-04-06 2022-04-25 2022-04-12 2023-04-07 mentation ion - Processor Perpetual Full Use 6 Pieces SO-MOF-291779-NC-RFQ / S ecurity Aspect Regulatory Co Request for Quota Single Stage - One E Pending Impl TF / B5774 Strengthening Institutions Prior Limited 70,000.00 0.00 2022-04-30 2022-06-07 2023-06-07 mpliance for Somali Business tions nvelope ementation Registration and licensing sy stem SO-MOF-291776-NC-RFQ / A Request for Quota Single Stage - One E udit Software for the Central TF / B5774 Strengthening Institutions Post Limited 90,000.00 0.00 Canceled 2022-04-30 2022-05-30 2022-06-07 2023-06-07 tions nvelope Bank of Somalia (CBS) SO-MOF-304504-NC-RFQ / A Request for Quota Single Stage - One E Under Imple TF / B5774 Strengthening Institutions Prior Limited 90,000.00 0.00 2022-07-23 2022-08-15 2022-09-17 2023-03-16 udit Software for Central Ban tions nvelope mentation k SO-MOF-332568-NC-RFQ / S omali Business Registration a Enabling Financial and Digit Request for Quota Single Stage - One E Under Imple TF / B5774 Prior Limited 46,000.00 0.00 2023-01-31 2023-05-15 2023-03-28 2023-09-24 nd licensing system – Securit al Services tions nvelope mentation y Aspect Regulatory Complia nce report. SO-MOF-348481-NC-DIR / Tr Enabling Financial and Digit Under Imple IDA / D4330 Prior Direct Selection Direct - National 35,633.00 0.00 2023-03-09 2023-03-09 2023-03-10 2023-03-10 2023-03-31 2023-04-10 aining for local Bankers -Gaa al Services mentation rgara Co. SO-MOF-353236-NC-DIR / Of Project Management and Co fice Rent for National Identifi IDA / D4330 Prior Direct Selection Direct - National 84,000.00 0.00 Canceled 2023-03-31 2023-04-05 2023-04-05 2023-04-19 2023-05-10 2024-05-09 ordination cation and Registration Auth ority SO-MOF-353364-NC-DIR / Int Under Imple ernet connection to Business TF / A9642 Strengthening Institutions Prior Direct Selection Direct - National 26,400.00 0.00 2023-04-10 2023-04-18 2023-04-15 2023-05-03 2023-05-20 2024-05-19 mentation Registration System for MOCI SO-MOF-362310-NC-DIR / Of Under Imple TF / B5774 Strengthening Institutions Prior Direct Selection Direct - National 173,195.00 0.00 2023-05-20 2023-05-18 2023-05-25 2023-05-21 2023-06-22 2025-06-21 fice Rent for NIRA mentation SO-MOF-362876-NC-RFQ / Of Request for Quota Single Stage - One E Under Revie TF / B5774 Strengthening Institutions Prior Limited 56,000.00 0.00 2023-06-09 2023-08-04 2024-08-03 fice Rent for DPA tions nvelope w CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 SO-MOF-113751-CS-CQS / C onsultancy service to prepar e financial sustainability plan Project Management and Co Consultant Qualifi s for each supported agency IDA / D4330 Prior Open - National 250,000.00 0.00 Canceled 2019-05-28 2019-07-10 2019-06-18 2019-07-23 2019-08-01 2019-08-31 2019-10-05 2020-04-02 ordination cation Selection to assist with fiscal planning and sustainability of services delivered & institutional effec tiveness SO-MOF-128029-CS-CQS / C onsultancy Services To Provi Enabling Financial and Digit Consultant Qualifi IDA / D4330 Prior Open - National 200,000.00 102,629.20 Signed 2019-08-22 2019-09-03 2019-09-12 2019-09-11 2019-10-26 2019-12-04 2019-11-25 2020-03-17 2019-12-30 2020-03-20 2020-06-27 de Legal Advisory Services to al Services cation Selection Gargaara Company Limited SO-MOF-134869-CS-QCBS / Enabling Financial and Digit Quality And Cost- Open - Internationa Under Implement TF / A9642 Prior 500,000.00 0.00 2019-09-23 2019-09-25 2019-10-14 2019-10-04 2019-11-15 2019-12-22 2019-11-17 2020-02-24 2019-12-17 2020-05-01 2019-12-24 2020-01-28 2021-01-27 Digital ID Legal Framework S al Services Based Selection l ation upport SO-MOF-135542-CS-QCBS / Technical and Project Manag Enabling Financial and Digit Quality And Cost- Open - Internationa Under Implement TF / A9642 Prior 1,500,000.00 0.00 2019-09-26 2019-09-26 2019-10-17 2019-10-04 2019-11-30 2020-02-18 2019-12-02 2020-01-01 2020-01-09 2020-02-01 2021-01-31 ement Support for Somalia’s al Services Based Selection l ation Digital ID System SO-MOF-139425-CS-CQS / D ESIGN, DEVELOPMENT AND I MPLEMENTATION OF AN ELE CTONIC MANAGEMENT INFOR MATION SYSTEM FOR ACCOU Consultant Qualifi TF / A9642 Strengthening Institutions Prior Open - National 200,000.00 0.00 Canceled 2019-10-14 2019-11-08 2019-11-04 2019-12-15 2019-12-22 2020-01-15 2020-07-13 NTABLE DOCUMENTS (EMIS – cation Selection AD), AN ENTERPRISE ELECTR ONIC OFFICE AND DOCUMEN T MANAGEMENT SYSTEM (EO DMS) AND A CASH MANAGEM ENT SYSTEM/DATABASE FOR THE AG SO-MOF-150489-CS-QCBS / THE DESIGN, DEVELOPMENT AND IMPLEMENTATION OF A N ELECTONIC MANAGEMENT INFORMATION SYSTEM FOR A Quality And Cost- Open - Internationa TF / A9642 Strengthening Institutions Prior 300,000.00 394,546.50 Signed 2019-12-18 2020-01-13 2020-01-08 2020-01-26 2020-02-21 2020-06-03 2020-03-20 2020-07-01 2020-04-19 2020-09-07 2020-05-24 2020-09-23 2020-06-20 2020-09-25 2021-06-20 CCOUNTABLE DOCUMENTS ( Based Selection l EMIS – AD), AN ENTERPRISE ELECTRONIC OFFICE AND DO CUMENT MANAGEMENT SYST EM (EODMS) AND A CASH MA NAGEMENT SYSTEM/DATABA SE FOR THE AG Office SO-MOF-153721-CS-CQS / C onsultancy service to prepar e financial sustainability plan Project Management and Co Consultant Qualifi Open - Internationa s for each supported agency TF / A9642 Prior 250,000.00 73,912.80 Signed 2020-01-30 2020-02-02 2020-02-13 2020-02-02 2020-02-28 2020-08-19 2020-03-04 2020-09-23 2020-03-21 2020-09-25 2020-08-28 ordination cation Selection l to assist with fiscal planning and sustainability of services delivered & institutional effec tiveness SO-MOF-155916-CS-CQS / Gr ievance Redress Mechanisms Consultant Qualifi Open - Internationa TF / A9642 Strengthening Institutions Prior 90,000.00 88,966.25 Signed 2020-01-29 2020-01-28 2020-02-12 2020-02-06 2020-03-05 2020-09-01 2020-03-17 2021-02-03 2020-04-03 2021-03-15 2020-08-07 for the Digital ID System and cation Selection l the MSME Financing Facility SO-MOF-155917-CS-CQS / S ocial Impact Research & Dev Consultant Qualifi Open - Internationa elopment of an Inclusive Outr TF / A9642 Strengthening Institutions Prior 180,000.00 179,604.19 Signed 2020-01-31 2020-01-28 2020-02-14 2020-02-06 2020-03-21 2020-09-01 2020-03-26 2021-02-01 2020-04-12 2021-03-26 2020-12-06 cation Selection l each and Enrollment Strateg y for the Digital ID System SO-MOF-167633-CS-CQS / C onsultancy Services to Provid Consultant Qualifi Open - Internationa TF / A9642 Strengthening Institutions Prior 50,000.00 60,000.00 Signed 2020-04-07 2020-04-22 2020-04-21 2020-05-04 2020-05-22 2020-10-12 2020-05-27 2021-04-30 2020-06-14 2021-05-04 2021-06-14 e Financial Audit Services to cation Selection l Gargaara Company Limited SO-MOF-201605-CS-CQS / D EVELOPMENT OF AN ICT DIGI TAL INCLUSION POLICY AND Consultant Qualifi TF / A9642 Strengthening Institutions Prior Open - National 180,000.00 0.00 Canceled 2020-10-28 2020-11-16 2020-11-18 2020-12-10 2020-12-17 2021-03-23 2020-12-20 2021-01-03 2021-07-02 ACTION PLAN FOR ADVANCIN cation Selection G ACCESS TO ICT SERVICES F OR MARGINALIZED GROUPS FOR MPTT SO-MOF-204670-CS-CQS / C onsulting Services for CBS str Consultant Qualifi ongrooms on Design and Eng TF / A9642 Strengthening Institutions Prior Limited 60,000.00 74,160.00 Signed 2020-11-17 2020-12-01 2020-12-01 2020-12-28 2020-12-11 2021-05-06 2020-12-25 2021-05-28 2021-06-23 cation Selection ineering, Required by CBS St rongrooms & Incineration Fac ilities SO-MOF-205622-CS-CQS / C onsultancy Services to condu Consultant Qualifi Pending Impleme TF / A9642 Strengthening Institutions Post Open - National 90,000.00 0.00 2020-11-23 2020-12-14 2021-01-12 2021-01-17 2021-01-30 2022-01-30 ct Independent third-party as cation Selection ntation sessments of PFIs SO-MOF-205623-CS-CQS / E nterprise Information and Re Consultant Qualifi Pending Impleme TF / A9642 Strengthening Institutions Post Open - National 200,000.00 0.00 2020-11-23 2020-12-14 2021-01-12 2021-01-14 2021-01-28 2022-01-28 source Planning System for G cation Selection ntation argaara Company Limited SO-MOF-215903-CS-CQS / C onsultancy Services to Condu Enabling Financial and Digit Consultant Qualifi Open - Internationa Pending Impleme ct Independent Third-Party A IDA / D4330 Prior 150,000.00 0.00 2021-01-26 2021-02-09 2021-03-12 2021-03-24 2021-04-08 2022-04-08 al Services cation Selection l ntation ssessment of Financial Institu tions under the MSME Financi ng Facility SO-MOF-225550-CS-CQS / C Consultant Qualifi Open - Internationa onsulting Firm to Conduct AM TF / A9642 Strengthening Institutions Prior 60,000.00 0.00 Canceled 2021-03-21 2021-04-11 2021-05-25 2021-06-24 2021-07-29 2022-01-25 cation Selection l L/CFT Technical Compliance Analysis SO-MOF-228105-CS-CQS / C Consultant Qualifi Open - Internationa Under Implement onsulting Firm to Conduct AM TF / A9642 Strengthening Institutions Prior 100,000.00 0.00 2021-04-08 2021-05-03 2021-04-29 2021-05-24 2021-06-12 2021-10-21 2021-07-12 2023-01-15 2021-08-16 2022-02-12 cation Selection l ation L/CFT Technical Compliance Analysis SO-MOF-231332-CS-QCBS / Technical Advisory Services f Quality And Cost- Open - Internationa Under Implement TF / A9642 Strengthening Institutions Prior 500,000.00 0.00 2021-05-24 2021-07-22 2021-06-07 2021-09-15 2021-07-20 2021-12-23 2021-07-23 2022-01-18 2021-08-22 2022-03-01 2021-09-26 2022-10-06 2021-10-31 2022-10-31 or the development of a foun Based Selection l ation dational legal framework for the digital economy SO-MOF-261944-CS-CQS / In Consultant Qualifi dependent Verification Agent IDA / D8430 Strengthening Institutions Prior Open - National 250,000.00 0.00 Under Review 2021-11-10 2021-11-10 2021-11-24 2021-11-16 2021-12-27 2022-05-30 2021-12-30 2022-07-20 2022-01-16 2023-01-16 cation Selection for Central Bank Page 4 SO-MOF-272066-CS-CQS / D EVELOPMENT OF AN ICT DIGI TAL INCLUSION POLICY AND Consultant Qualifi Open - Internationa ACTION PLAN FOR ADVANCIN TF / A9642 Strengthening Institutions Prior 180,000.00 0.00 Canceled 2022-01-09 2022-01-23 2022-02-23 2022-02-27 2022-03-16 2022-09-12 cation Selection l G ACCESS TO ICT SERVICES F OR MARGINALIZED GROUPS FOR MINISTRY OF COMMUNIC ATION AND TECHNOLOGY SO-MOF-273546-CS-CQS / D EVELOPMENT OF AN ICT DIGI Consultant Qualifi Under Implement TAL INCLUSION POLICY AND TF / B5774 Strengthening Institutions Prior Open - National 230,000.00 0.00 2022-01-24 2022-01-31 2022-02-07 2022-02-03 2022-03-12 2023-01-30 2022-03-22 2023-04-28 2022-04-10 2022-10-07 cation Selection ation ACTION PLAN FOR ADVANCIN G ACCESS TO ICT SERVICES F OR MARGINALIZED GROUPS SO-MOF-276315-CS-CQS / C onsultancy to identify the de Enabling Financial and Digit Consultant Qualifi Under Implement IDA / D8430 Prior Open - National 140,000.00 0.00 2022-02-07 2022-02-03 2022-02-28 2022-02-06 2022-04-05 2022-06-21 2022-04-09 2022-09-19 2022-04-27 2022-10-24 mand for Business Developm al Services cation Selection ation ent Services (BDS) by MSMEs in Somalia SO-MOF-299092-CS-CQS / C Consultant Qualifi Under Implement onsultancy Services that pro TF / B5774 Strengthening Institutions Prior Open - National 144,000.00 0.00 2022-06-13 2022-07-26 2022-07-04 2022-08-14 2022-08-17 2023-04-07 2022-09-16 2022-10-21 2023-10-21 cation Selection ation vide IFRSs to Central Bank of Somalia SO-MOF-299099-CS-QCBS / Technical Advisory Services f or the Development of a Nati onal Cybersecurity Policy, Str Quality And Cost- Open - Internationa Under Implement ategy, Governance and Instit TF / B5774 Strengthening Institutions Prior 300,000.00 0.00 2022-06-13 2022-06-16 2022-07-04 2022-07-18 2022-08-17 2022-09-14 2022-10-14 2022-11-18 2022-12-23 2023-12-23 Based Selection l ation utional Structure as well as G uidelines for the Protection of Critical Information Infrastruc ture for Ministry of Communi cation & Technology SO-MOF-128027-CS-CQS / C onsultancy services for indep Enabling Financial and Digit Consultant Qualifi endent third-party assessme IDA / D4330 Post Open - National 250,000.00 0.00 Canceled 2019-08-23 2019-09-03 2019-09-13 2019-09-11 2019-10-27 2019-11-14 2019-11-26 2019-12-31 2020-06-28 al Services cation Selection nt of financial institution accr editation under the MSME Fin ancing Facility SO-MOF-345386-CS-CQS / C onsultancy Service for Techni Consultant Qualifi Open - Internationa TF / A9642 Strengthening Institutions Prior 100,000.00 0.00 Under Review 2023-03-02 2023-03-23 2023-05-06 2023-06-05 2023-07-10 2024-01-06 cal Assistance to Establish a cation Selection l Market Observatory- NCA SO-MOF-360637-CS-CQS / C onsultancy Services to Under Consultant Qualifi Open - Internationa Under Implement TF / B5774 Strengthening Institutions Prior 150,000.00 0.00 2023-05-28 2023-06-15 2023-06-18 2023-08-01 2023-08-31 2023-10-05 2024-01-03 take Assessment for establis cation Selection l ation hing National CERT at NCA SO-MOF-360536-CS-CQS / C onsultancy Services to Provid Enabling Financial and Digit Consultant Qualifi Under Implement IDA / D4330 Prior Limited 30,000.00 0.00 2023-05-21 2023-05-30 2023-06-04 2023-07-04 2023-08-08 2023-11-06 e Financial Audit Services to al Services cation Selection ation Gargaara Company Limited SO-MOF-362870-CS-CQS / D evelopment of DPA Strategic Plan, Budget and Financial S Enabling Financial and Digit Consultant Qualifi Open - Internationa Pending Impleme IDA / D4330 Prior 200,000.00 0.00 2023-06-05 2023-06-26 2023-08-09 2023-09-08 2023-10-13 2024-04-10 ustainability Plan; 5-year HR al Services cation Selection l ntation and Talent Plan; 5-year Capa city Building Plan for or the D PA SO-MOF-362874-CS-CQS / C onsultancy service for Develo Enabling Financial and Digit Consultant Qualifi Open - Internationa Pending Impleme TF / B5774 Prior 150,000.00 0.00 2023-06-05 2023-06-26 2023-08-09 2023-09-08 2023-10-13 2024-04-10 ping a communications strat al Services cation Selection l ntation egy/engagement strategy for DPA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SO-MOF-111310-CS-INDV / C Project Management and Co Individual Consult IDA / D4330 Prior Open 120,000.00 156,000.00 Signed 2019-04-27 2019-04-25 2019-05-31 2019-07-06 2019-06-15 2019-07-16 2019-07-12 2019-07-16 2020-01-08 hief Executive Officer( Garga ordination ant Selection ara) SO-MOF-113319-CS-INDV / G Project Management and Co Individual Consult IDA / D4330 Prior Open 77,000.00 338,760.00 Signed 2019-05-06 2019-05-06 2019-05-27 2019-07-15 2019-06-04 2019-07-16 2019-06-27 2019-07-17 2019-12-24 argaara Treasurer ordination ant Selection SO-MOF-113749-CS-INDV / E Project Management and Co Individual Consult nvironmental and Social Safe IDA / D4330 Prior Open 100,000.00 199,920.00 Signed 2019-05-28 2019-06-02 2019-07-16 2019-09-10 2019-08-06 2019-09-30 2019-09-10 2019-10-03 2020-09-11 ordination ant Selection guard Consultant SO-MOF-116571-CS-INDV / C Project Management and Co Individual Consult IDA / D4330 Prior Open 70,000.00 0.00 Canceled 2019-05-29 2019-05-31 2019-07-17 2019-08-07 2019-09-11 2020-03-09 ommunication Officer ordination ant Selection SO-MOF-118083-CS-INDV / P Individual Consult olicy Advisor-Ministry of Post IDA / D4330 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2019-06-10 2019-07-29 2019-08-19 2019-09-23 2020-03-21 ant Selection and Telecommunication Auth ority SO-MOF-118084-CS-INDV / C Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 194,040.00 Signed 2019-06-10 2019-10-08 2019-07-29 2020-05-09 2019-08-19 2020-05-27 2019-09-23 2020-05-30 2020-03-21 yber Security Specialist-NCA ant Selection SO-MOF-118086-CS-INDV / F Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 194,040.00 Signed 2019-06-10 2019-06-11 2019-07-29 2019-11-30 2019-08-19 2019-12-10 2019-09-23 2020-01-01 2020-03-21 inance and Accounting Exper ant Selection t-NCA SO-MOF-118091-CS-INDV / S Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 194,040.00 Signed 2019-06-10 2019-06-11 2019-07-29 2019-12-02 2019-08-19 2019-12-10 2019-09-23 2020-01-01 2020-03-21 pectrum Management Expert ant Selection -NCA SO-MOF-118092-CS-INDV / T Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 220,140.00 Signed 2019-06-10 2019-06-11 2019-07-29 2019-12-01 2019-08-19 2019-12-09 2019-09-23 2020-01-01 2020-03-21 eam Coordinator-NCA ant Selection SO-MOF-118093-CS-INDV / L Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 194,040.00 Signed 2019-06-10 2019-06-11 2019-07-29 2019-11-30 2019-08-19 2019-12-10 2019-09-23 2020-01-01 2020-03-21 egal and Regulatory Advisor ant Selection SO-MOF-118658-CS-INDV / P Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 72,000.00 Signed 2019-06-17 2019-06-13 2019-08-05 2019-12-02 2019-08-26 2019-12-10 2019-09-30 2019-12-16 2020-03-28 olicy Advisor-MPT ant Selection Page 5 SO-MOF-119553-CS-INDV / I T System Integrator – Integra Enabling Financial and Digit Individual Consult tion of the SFMIS with the CB IDA / D4330 Prior Open 80,000.00 0.00 Canceled 2019-06-20 2019-07-09 2019-07-23 2019-07-30 2019-08-10 2020-04-30 al Services ant Selection S Financial Systems and Oth er external Systems ( Office of Accountant General) SO-MOF-126312-CS-INDV / F Project Management and Co Individual Consult IDA / D4330 Prior Open 72,000.00 177,120.00 Signed 2019-08-11 2019-08-19 2019-09-29 2019-12-01 2019-10-09 2019-12-09 2019-10-24 2019-12-10 2020-08-30 inancial Institutions Analyst ordination ant Selection SO-MOF-132967-CS-INDV / T echnical assistant - Institutio Individual Consult nal development, Administra TF / A9642 Strengthening Institutions Prior Open 70,000.00 0.00 Canceled 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2020-08-31 ant Selection tion and Human resource ma nagement for the Office of Ac countant General SO-MOF-132969-CS-INDV / P Project Management and Co Individual Consult TF / A9642 Prior Direct 125,640.00 230,460.00 Signed 2019-09-09 2019-10-18 2019-09-19 2019-10-17 2019-10-10 2019-11-25 2019-11-14 2019-12-08 2021-08-10 rocurement Specialist-PIU ordination ant Selection SO-MOF-133522-CS-INDV / P Project Management and Co Individual Consult rocurement and Contract Ma TF / A9642 Prior Limited 70,000.00 0.00 Canceled 2019-09-13 2019-09-18 2019-10-09 2019-11-13 2020-09-30 ordination ant Selection nager-Payment System and Regtech SO-MOF-135080-CS-INDV / P Project Management and Co Individual Consult Under Implement rocurement and Contract Ma TF / A9642 Prior Limited 60,000.00 0.00 2019-09-24 2019-09-23 2019-09-29 2019-09-30 2019-10-18 2020-10-15 ordination ant Selection ation nagement Consultant SO-MOF-133524-CS-INDV / O Project Management and Co Individual Consult TF / A9642 Prior Open 60,000.00 0.00 Canceled 2019-09-13 2019-09-23 2019-11-01 2019-11-02 2019-11-10 2020-09-30 perations Officer for SCALED- ordination ant Selection UP SO-MOF-139422-CS-CDS / IT System Integrator – Integrati on of the SFMIS with the CBS TF / A9642 Strengthening Institutions Prior Direct Selection Direct 84,000.00 216,000.00 Signed 2019-10-13 2019-10-14 2019-10-23 2020-03-01 2019-11-09 2020-05-15 2020-10-01 Financial Systems and Other external Systems ( Office of Accountant General) SO-MOF-139423-CS-INDV / N Individual Consult TF / A9642 Strengthening Institutions Prior Open 36,000.00 145,220.00 Signed 2019-10-14 2019-11-06 2019-11-17 2020-03-19 2019-11-22 2021-09-05 2019-12-09 2021-09-20 2020-11-30 CA Focal Point ant Selection SO-MOF-139429-CS-INDV / T echnical assistant - Institutio Individual Consult TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2019-10-14 2019-11-08 2019-11-22 2019-12-04 2019-12-21 2020-12-22 nal development, Administra ant Selection tion and Human resource ma nagement SO-MOF-139430-CS-INDV / T Individual Consult echnical assistant – Treasury TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2019-10-14 2019-11-08 2019-11-08 2019-11-16 2019-12-04 2020-11-30 ant Selection and Payroll Management SO-MOF-139650-CS-INDV / T Individual Consult TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 Canceled 2019-10-15 2019-11-08 2019-11-18 2019-11-23 2019-12-08 2020-11-30 echnical assistant - Cash Man ant Selection agement SO-MOF-139652-CS-INDV / T Individual Consult echnical assistant - Internal c TF / A9642 Strengthening Institutions Prior Open 72,000.00 129,360.00 Signed 2019-10-15 2019-11-08 2019-11-15 2020-06-19 2019-11-20 2020-06-26 2019-12-08 2020-07-23 2020-11-30 ant Selection ontrols and compliance SO-MOF-144735-CS-CDS / Fi Project Management and Co TF / A9642 Prior Direct Selection Direct 80,000.00 230,460.00 Signed 2019-11-12 2019-12-11 2019-11-22 2020-01-15 2019-11-30 2020-02-03 2020-11-28 nancial Management Speciali ordination st- PIU SO-MOF-147501-CS-INDV / A Enabling Financial and Digit Individual Consult Under Implement dministrative Assistant for Di TF / A9642 Prior Open 40,000.00 0.00 2019-11-30 2020-06-22 2019-12-22 2019-12-26 2020-01-12 2020-12-31 al Services ant Selection ation gital ID Task Force SO-MOF-148232-CS-INDV / P Project Management and Co rocurement and Contract Ma TF / A9642 Prior Direct Selection Direct 60,000.00 278,775.00 Signed 2019-12-06 2019-12-04 2019-12-16 2019-12-11 2019-12-27 2020-01-03 2020-12-26 ordination nagement Consultant SO-MOF-148234-CS-CDS / Pr Project Management and Co TF / A9642 Prior Direct Selection Direct 63,000.00 194,040.00 Signed 2019-12-05 2020-01-26 2019-12-15 2020-02-12 2019-12-25 2020-05-16 2020-12-24 icing and Interconnection Ex ordination pert SO-MOF-150482-CS-INDV / T echnical Assistant-Public Sect Individual Consult TF / A9642 Strengthening Institutions Prior Open 60,000.00 194,040.00 Signed 2019-12-18 2020-01-09 2020-01-12 2020-06-19 2020-01-17 2020-06-26 2020-01-26 2020-07-12 2020-12-31 or Accounting and Reporting ant Selection for Office of Accountant Gen eral SO-MOF-132860-CS-INDV / A Enabling Financial and Digit Individual Consult dministrative Assistant for G IDA / D4330 Prior Open 40,000.00 0.00 Canceled 2019-09-09 2019-09-11 2019-10-28 2019-11-18 2019-12-23 2020-08-31 al Services ant Selection argaara Company Limited SO-MOF-154543-CS-INDV / A Project Management and Co Individual Consult TF / A9642 Prior Open 40,000.00 104,940.00 Signed 2020-01-24 2020-01-28 2020-02-16 2020-03-16 2020-02-24 2020-03-30 2020-03-08 2020-04-03 2021-03-08 dministrative Assistant for G ordination ant Selection argaara SO-MOF-155128-CS-INDV / S Individual Consult enior System Analyst for Offi TF / A9642 Strengthening Institutions Prior Open 70,000.00 0.00 Canceled 2020-01-24 2020-01-28 2020-02-19 2020-02-22 2020-03-06 2021-03-06 ant Selection ce of Accountant General SO-MOF-155131-CS-INDV / D Individual Consult atabase Administrator for Off TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2020-01-24 2020-01-28 2020-02-22 2020-02-27 2020-03-13 2021-03-13 ant Selection ice of Accountant General SO-MOF-155135-CS-INDV / S Individual Consult ystem Developer for Office of TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2020-01-24 2020-01-28 2020-02-10 2020-02-12 2020-02-26 2021-02-25 ant Selection Accountant General SO-MOF-139424-CS-CDS / Li TF / A9642 Strengthening Institutions Prior Direct Selection Direct 84,000.00 0.00 Canceled 2019-10-14 2019-10-14 2019-10-24 2019-11-10 2020-11-01 censing Expert SO-MOF-118090-CS-INDV / P Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2019-06-10 2019-06-11 2019-07-29 2019-08-19 2019-09-23 2020-03-21 ricing and Interconnection Ex ant Selection pert-NCA SO-MOF-118085-CS-INDV / Li Individual Consult IDA / D4330 Strengthening Institutions Prior Open 60,000.00 0.00 Canceled 2019-06-10 2019-06-11 2019-07-29 2019-08-19 2019-09-23 2020-03-21 censing Specialist-NCA ant Selection SO-MOF-155915-CS-CDS / Li TF / A9642 Strengthening Institutions Prior Direct Selection Direct 60,000.00 194,040.00 Signed 2020-01-29 2020-01-28 2020-02-08 2020-02-09 2020-02-17 2020-05-16 2021-02-16 censing Expert SO-MOF-153723-CS-INDV / C Project Management and Co Individual Consult TF / A9642 Prior Open 60,000.00 0.00 Canceled 2020-01-30 2020-02-28 2020-03-05 2020-03-21 2021-03-21 ommunication Specialist ordination ant Selection Page 6 SO-MOF-153788-CS-INDV / Enabling Financial and Digit Individual Consult Under Implement TF / A9642 Prior Open 120,000.00 0.00 2020-01-30 2020-02-23 2020-02-25 2020-03-13 2021-03-13 Managing Project Director- Di al Services ant Selection ation gital ID SO-MOF-157418-CS-INDV / A Individual Consult Under Implement dministration and Finance Co TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 2020-02-13 2020-02-23 2020-02-18 2020-02-22 2020-02-28 2021-02-27 ant Selection ation nsultant for FRC SO-MOF-157417-CS-INDV / R Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 2020-02-13 2020-02-23 2020-02-18 2020-02-22 2020-03-06 2021-03-06 egulatory Consultant for FRC ant Selection ation SO-MOF-163669-CS-INDV / F Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 40,000.00 0.00 2020-03-09 2020-04-01 2020-04-08 2020-08-05 2020-04-10 2020-08-19 2020-04-27 2021-04-27 ocal Point-FRC ant Selection ation SO-MOF-167102-CS-INDV / S Individual Consult TF / A9642 Strengthening Institutions Prior Limited 120,000.00 120,000.00 Signed 2020-04-03 2020-04-22 2020-04-08 2020-06-21 2020-04-12 2020-06-26 2020-04-29 2020-07-09 2020-08-27 trategic Advisor for Central B ant Selection ank SO-MOF-167208-CS-INDV / A Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 2020-04-04 2020-04-05 2020-04-09 2020-04-12 2020-04-29 2021-04-29 dministration and Finance Co ant Selection ation nsultant SO-MOF-167209-CS-INDV / R Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 2020-04-04 2020-04-05 2020-04-09 2020-05-06 2020-04-14 2020-05-28 2020-05-01 2021-05-01 egulatory Expert ant Selection ation SO-MOF-168266-CS-CDS / PI Project Management and Co TF / A9642 Prior Direct Selection Direct 111,480.00 0.00 Canceled 2020-04-13 2020-04-23 2020-04-30 2020-06-05 U Coordinator of SCALED-UP ordination SO-MOF-169310-CS-INDV / P Project Management and Co Individual Consult roject Director-Digital Identifi TF / A9642 Prior Limited 360,000.00 156,000.00 Signed 2020-04-22 2020-04-23 2020-04-27 2020-05-01 2020-05-01 2020-05-17 2020-05-17 2020-05-20 2021-05-17 ordination ant Selection cation Program SO-MOF-169477-CS-INDV / R Individual Consult Under Implement estructuring Project Manager TF / A9642 Strengthening Institutions Prior Open 84,000.00 0.00 2020-04-23 2020-05-01 2020-05-15 2020-05-18 2020-06-03 2021-06-03 ant Selection ation -Central Bank SO-MOF-171854-CS-INDV / L Individual Consult Under Implement egal drafting and translator f TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 2020-05-05 2020-06-23 2020-07-14 2020-08-18 2021-08-18 ant Selection ation or office of the Attorney Gen eral SO-MOF-172367-CS-INDV / P roject Consultant Finance an Individual Consult TF / A9642 Strengthening Institutions Prior Limited 48,000.00 118,560.00 Signed 2020-05-11 2020-06-08 2020-05-16 2020-09-01 2020-05-28 2020-09-07 2020-06-14 2020-09-14 2021-06-14 d Administration- Somalia Pa ant Selection yment Switch Project SO-MOF-172370-CS-INDV / P Individual Consult ROJECT CONSULTANT SWITC TF / A9642 Strengthening Institutions Prior Limited 60,000.00 118,560.00 Signed 2020-05-11 2020-06-08 2020-05-16 2020-07-28 2020-05-27 2020-09-01 2020-06-13 2020-09-18 2021-06-13 ant Selection H OPERATIONS SO-MOF-172373-CS-INDV / P ROJECT CONSULTANT, INFOR Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Limited 72,000.00 0.00 2020-05-12 2020-06-08 2020-05-17 2020-07-28 2020-05-30 2020-09-01 2020-06-16 2021-06-16 MATION TECHNOLOGY-SOMA ant Selection ation LIA PAYMENT SWITCH PROJE CT SO-MOF-176000-CS-CDS / B TF / A9642 Strengthening Institutions Prior Direct Selection Direct 500,000.00 500,510.00 Signed 2020-05-31 2020-06-23 2020-06-10 2020-08-27 2020-07-16 2020-09-17 2023-07-16 usiness Automation Registrat ion PhaseII SO-MOF-178403-CS-INDV / A Individual Consult TF / A9642 Strengthening Institutions Prior Limited 60,000.00 0.00 Canceled 2020-06-10 2020-06-15 2020-06-25 2020-07-12 2021-07-12 dmin/Finance Consultant for ant Selection FRC SO-MOF-175994-CS-INDV / N Individual Consult TF / A9642 Strengthening Institutions Prior Direct 80,000.00 210,000.00 Signed 2020-05-31 2020-09-03 2020-06-10 2020-09-14 2020-07-01 2020-09-23 2020-08-05 2020-10-04 2021-08-05 ational Risk Assessment Coor ant Selection dinator SO-MOF-178462-CS-INDV / S omali Legislative Drafting Ex Enabling Financial and Digit Individual Consult Under Implement TF / A9642 Prior Open 60,000.00 0.00 2020-06-10 2020-06-11 2020-07-09 2020-07-14 2020-07-30 2021-07-30 pert for the Digital ID Project al Services ant Selection ation for Office of State Attorney G eneral SO-MOF-179535-CS-INDV / A Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 2020-06-15 2020-06-26 2020-07-06 2020-09-01 2020-07-08 2020-10-04 2020-07-23 2021-07-23 dmin/Finance Consultant for ant Selection ation FRC SO-MOF-183387-CS-INDV / C Enabling Financial and Digit Individual Consult Under Implement hief Technology Officer (CTO) TF / A9642 Prior Open 77,400.00 0.00 2020-07-13 2020-07-22 2020-08-05 2020-08-07 2020-08-21 2021-08-21 al Services ant Selection ation for Digital ID Project SO-MOF-183388-CS-INDV / S Enabling Financial and Digit Individual Consult Under Implement enior Network and Security E TF / A9642 Prior Open 77,400.00 0.00 2020-07-13 2020-07-22 2020-08-06 2020-08-09 2020-08-24 2021-08-24 al Services ant Selection ation ngineer - (SNSE) for Digital I D Project SO-MOF-183390-CS-INDV / S Enabling Financial and Digit Individual Consult Under Implement enior Solutions Architect for TF / A9642 Prior Open 77,400.00 0.00 2020-07-13 2020-07-22 2020-08-10 2020-08-13 2020-08-27 2021-08-27 al Services ant Selection ation Digital ID Project SO-MOF-185120-CS-CDS / I Under Implement mplementation Project Mana TF / A9642 Strengthening Institutions Prior Direct Selection Direct 72,000.00 0.00 2020-07-24 2020-07-29 2020-08-03 2020-09-02 2020-08-08 2021-02-04 ation ger- Payment System SO-MOF-187101-CS-INDV / A dvisor - Business Registration Individual Consult TF / A9642 Strengthening Institutions Prior Open 60,000.00 59,280.00 Signed 2020-08-06 2020-09-14 2020-09-01 2021-04-20 2020-09-05 2021-04-26 2020-09-20 2021-05-18 2021-09-20 Services (BRS) Outreach and ant Selection MSME Engagement SO-MOF-187103-CS-INDV / I Individual Consult TF / A9642 Strengthening Institutions Prior Open 60,000.00 118,560.00 Signed 2020-08-07 2020-09-15 2020-09-02 2021-02-11 2020-09-05 2021-02-16 2020-09-21 2021-03-18 2021-09-21 CT Advisor for OSS and ICT In ant Selection frastructure SO-MOF-190091-CS-CDS / Le gal and Regulatory Expert for TF / A9642 Strengthening Institutions Prior Direct Selection Direct 67,770.00 180,720.00 Signed 2020-08-28 2020-09-15 2020-09-07 2020-09-29 2020-09-15 2020-10-06 2021-06-12 Central Bank SO-MOF-190093-CS-CDS / H uman Resource Management TF / A9642 Strengthening Institutions Prior Direct Selection Direct 87,480.00 174,960.00 Signed 2020-08-28 2020-09-15 2020-09-07 2020-09-29 2020-09-18 2020-11-13 2021-09-18 Principal Advisor SO-MOF-190096-CS-CDS / Pr oject Manager- Business Regi TF / A9642 Strengthening Institutions Prior Direct Selection Direct 52,650.00 175,500.00 Signed 2020-08-27 2020-09-18 2020-09-06 2020-09-29 2020-09-20 2020-10-05 2021-06-17 stration Automation SO-MOF-190098-CS-INDV / P Individual Consult TF / A9642 Strengthening Institutions Prior Open 80,000.00 0.00 Signed 2020-08-31 2020-09-07 2020-10-01 2021-09-11 2020-10-04 2021-09-20 2020-10-30 2021-10-30 IU Coordinator for SCALED-U ant Selection P Page 7 SO-MOF-190597-CS-INDV / R Individual Consult TF / A9642 Strengthening Institutions Prior Limited 80,000.00 97,480.00 Signed 2020-08-26 2020-09-07 2020-08-31 2020-10-05 2020-09-03 2020-11-23 2020-09-11 2020-11-23 2020-12-10 estructuring Project Manager ant Selection SO-MOF-193600-CS-INDV / I Individual Consult TF / A9642 Strengthening Institutions Prior Open 60,000.00 190,460.00 Terminated 2020-09-15 2020-09-16 2020-10-11 2020-11-16 2020-10-14 2020-11-25 2020-10-27 2020-11-26 2021-10-27 CT Consultant for Central Ba ant Selection nk SO-MOF-196195-CS-CDS / E Project Management and Co Under Implement TF / A9642 Prior Direct Selection Direct 50,000.00 0.00 2020-09-25 2020-10-05 2020-11-11 2021-05-10 nd SCORE Evaluation Consult ordination ation ant SO-MOF-199766-CS-CDS / Po Under Implement TF / A9642 Strengthening Institutions Prior Direct Selection Direct 40,000.00 0.00 2020-10-16 2020-10-15 2020-10-26 2020-10-21 2020-11-13 2021-05-12 licy Advisor for MPTT ation SO-MOF-199770-CS-INDV / C Individual Consult TF / A9642 Strengthening Institutions Prior Open 72,000.00 204,220.00 Signed 2020-10-17 2020-10-19 2020-11-20 2021-01-21 2020-11-22 2021-02-10 2020-12-07 2021-03-24 2021-12-07 ommunication Consultant ant Selection SO-MOF-201599-CS-CDS / LE GAL EXPERT TO CONDUCT ST AKEHOLDER CONSULTATION S ON FINANCIAL INSTITUTION S BILL, 2020, NATIONAL PAY TF / A9642 Strengthening Institutions Prior Direct Selection Direct 200,000.00 200,000.00 Signed 2020-10-27 2020-11-01 2020-11-06 2020-12-18 2020-11-15 2021-03-02 2021-11-15 MENT SYSTEM BILL, 2020 AN D INSURANCE BILL, 2020 & T O DEVELOP REGULATIONS O N OVERSIGHT OF THE NATIO NAL PAYMENT SYSTEM, REGU LATIONS ON THE OPERATION S OF THE SO-MOF-205624-CS-INDV / I Individual Consult Under Implement T Consultant for Somalia Pay TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2020-11-23 2020-12-14 2020-12-21 2020-12-24 2021-01-06 2022-01-06 ant Selection ation ment Switch Project SO-MOF-206189-CS-INDV / C onsultant to Develop of an e- Individual Consult TF / A9642 Strengthening Institutions Prior Open 90,000.00 90,000.00 Signed 2020-11-26 2020-12-09 2020-12-22 2021-05-29 2020-12-25 2021-06-15 2021-01-08 2021-06-26 2021-07-07 Government Strategy and Im ant Selection plementation Roadmap for M PTT SO-MOF-206191-CS-INDV / C Individual Consult Under Implement onsultant to conduct Human TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 2020-11-24 2020-12-01 2020-12-23 2021-03-30 2020-12-26 2021-04-21 2021-01-09 2021-07-08 ant Selection ation Capital Development Frame work for NCA SO-MOF-212383-CS-INDV / L Individual Consult Under Implement egal and Regulatory Expert t TF / A9642 Strengthening Institutions Prior Open 90,000.00 0.00 2021-01-08 2021-02-26 2021-03-02 2021-03-27 2022-03-27 ant Selection ation o Assist the MPTT SO-MOF-212387-CS-INDV / E Individual Consult Under Implement -Government Strategy Imple TF / A9642 Strengthening Institutions Prior Open 90,000.00 0.00 2021-01-08 2021-02-26 2021-03-03 2021-03-16 2022-04-04 ant Selection ation mentation Advisor SO-MOF-212389-CS-INDV / C Individual Consult Under Implement yber-security Policy Impleme TF / A9642 Strengthening Institutions Prior Open 90,000.00 0.00 2021-01-08 2021-02-11 2021-03-04 2021-03-20 2021-05-14 ant Selection ation ntation Advisor SO-MOF-215898-CS-INDV / C onsultant to Provide Pre- Pro curement and Project Imple Enabling Financial and Digit Individual Consult mentation Consultancy Servi IDA / D4330 Prior Open 90,000.00 55,000.00 Signed 2021-01-27 2021-01-28 2021-02-25 2021-05-06 2021-02-28 2021-05-24 2021-03-16 2021-05-27 2022-03-16 al Services ant Selection ces for the GARGAARA Finan cial Management and Reporti ng System and Supporting In frastructure SO-MOF-216261-CS-INDV / C Enabling Financial and Digit Individual Consult hief Executive Officer of Garg IDA / D4330 Prior Open 87,480.00 0.00 Signed 2021-01-28 2021-02-01 2021-03-03 2021-08-28 2021-03-08 2021-09-28 2021-03-22 2022-03-22 al Services ant Selection aara Company SO-MOF-218183-CS-INDV / S Project Management and Co Individual Consult ocial Development Specialist TF / A9642 Prior Open 87,000.00 143,580.00 Under Review 2021-02-09 2021-03-15 2021-03-10 2021-06-16 2021-03-13 2021-06-28 2021-03-28 2021-07-07 2022-03-28 ordination ant Selection for SCALED-UP PIU SO-MOF-218204-CS-INDV / I Individual Consult TF / A9642 Strengthening Institutions Prior Open 72,000.00 73,380.00 Terminated 2021-02-09 2021-02-15 2021-03-06 2021-04-15 2021-03-09 2021-05-05 2021-03-24 2021-05-30 2022-03-24 T Consultant for Switch Proje ant Selection ct SO-MOF-220162-CS-INDV / Project Management and Co Individual Consult Under Implement Monitoring and Evaluation Sp TF / A9642 Prior Open 72,000.00 0.00 2021-02-19 2021-03-08 2021-03-20 2021-03-22 2021-04-06 2022-04-06 ordination ant Selection ation ecialist for SCALED-UP Projec t SO-MOF-227745-CS-INDV / C Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 2021-04-06 2021-05-01 2021-05-10 2021-11-22 2021-05-13 2021-11-29 2021-05-30 2022-05-30 ommunication Consultant for ant Selection ation MoCI SO-MOF-227746-CS-INDV / B Individual Consult Under Implement usiness Planning and Policy A TF / A9642 Strengthening Institutions Prior Open 60,000.00 0.00 2021-04-06 2021-05-01 2021-05-06 2022-02-03 2021-05-07 2022-02-09 2021-05-22 2022-05-22 ant Selection ation dvisor for MoCI SO-MOF-228108-CS-INDV / Monitoring, Evaluation and L Enabling Financial and Digit Individual Consult IDA / D4330 Prior Open 60,000.00 0.00 Signed 2021-04-12 2021-06-08 2021-05-31 2022-02-17 2021-06-21 2022-03-01 2021-07-26 2023-04-16 2022-07-26 earning (ME&L) Consultant fo al Services ant Selection r Gargaara Company Limited SO-MOF-231333-CS-INDV / E Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2021-04-26 2021-07-27 2021-06-14 2021-07-05 2021-08-09 2022-08-09 mbedded Local Legal Advisor ant Selection ation SO-MOF-234389-CS-INDV / A Enabling Financial and Digit Individual Consult IDA / D4330 Prior Open 40,000.00 67,440.00 Terminated 2021-05-14 2021-06-08 2021-06-12 2022-05-17 2021-06-15 2022-05-27 2021-06-30 2022-06-20 2022-06-30 ccountant, Gargaara Compan al Services ant Selection y Limited SO-MOF-234391-CS-INDV / H Enabling Financial and Digit Individual Consult Pending Impleme ead of Finance, Gargaara Co IDA / D4330 Prior Open 60,000.00 0.00 2021-05-14 2021-06-12 2021-06-17 2021-07-03 2022-07-03 al Services ant Selection ntation mpany Limited SO-MOF-234398-CS-INDV / E nvironmental and Social Risk Enabling Financial and Digit Individual Consult IDA / D4330 Prior Open 60,000.00 0.00 Signed 2021-05-14 2021-06-08 2021-06-12 2022-03-03 2021-06-16 2022-03-21 2021-07-01 2023-04-16 2022-07-01 Management Officer, Gargaa al Services ant Selection ra Company Limited SO-MOF-238133-CS-INDV / G Project Management and Co Individual Consult Under Implement TF / A9642 Prior Open 60,000.00 0.00 2021-06-10 2021-07-22 2021-07-14 2021-09-29 2021-08-04 2021-10-13 2021-08-19 2022-08-19 ender Based Violence (GBV) ordination ant Selection ation Advisor Page 8 SO-MOF-244708-CS-INDV / I NTERNATIONAL CONSULTAN T TO CONDUCT A FEASIBILIT Enabling Financial and Digit Individual Consult Y STUDY FOR THE ESTABLISH IDA / D4330 Prior Open 30,000.00 42,000.00 Signed 2021-07-26 2021-07-27 2021-08-29 2022-02-16 2021-09-19 2022-03-01 2021-10-24 2022-03-21 2022-04-22 al Services ant Selection MENT OF A PARTIAL CREDIT GUARANTEE (PCG) SCHEME OR OTHER RISK SHARING ME CHANISM IN SOMALIA SO-MOF-244701-CS-INDV / Project Management and Co Individual Consult TF / A9642 Prior Open 87,000.00 0.00 Signed 2021-07-26 2021-07-26 2021-09-13 2021-10-03 2021-10-04 2021-10-27 2021-11-08 2023-04-24 2022-11-08 Monitoring and Evaluation Of ordination ant Selection ficer SO-MOF-245275-CS-CDS / C onsultancy Services To Provi Enabling Financial and Digit Under Implement IDA / D4330 Prior Direct Selection Direct 150,000.00 0.00 2021-07-27 2021-09-13 2021-08-06 2021-12-14 2021-08-18 2022-08-18 de Legal Advisory Services to al Services ation Gargaara Company Limited SO-MOF-245277-CS-INDV / P Project Management and Co Individual Consult Under Implement roject Assistant for SCALED-U TF / A9642 Prior Open 40,000.00 0.00 2021-07-27 2021-07-27 2021-08-30 2021-10-03 2021-08-31 2021-10-23 2021-09-12 2022-09-12 ordination ant Selection ation P Project PIU SO-MOF-245864-CS-CDS / Po Under Implement licy Advisor and Focal Point o TF / A9642 Strengthening Institutions Prior Direct Selection Direct 60,000.00 0.00 2021-08-02 2021-07-30 2021-08-12 2021-08-23 2021-08-19 2022-08-19 ation f SCALED-UP Project SO-MOF-246212-CS-INDV / e Individual Consult Under Implement -Government Strategy Devel TF / A9642 Strengthening Institutions Prior Open 90,000.00 0.00 2021-07-31 2021-08-16 2021-08-29 2021-11-24 2021-09-02 2021-12-08 2021-09-15 2022-09-15 ant Selection ation opment and Implementation Advisor SO-MOF-248595-CS-INDV / C Project Management and Co Individual Consult Under Implement TF / A9642 Prior Open 60,000.00 0.00 2021-08-20 2021-08-25 2021-09-11 2021-11-03 2021-09-14 2021-11-11 2021-10-01 2022-10-01 ommunication Consultant for ordination ant Selection ation PIU SO-MOF-253392-CS-CDS / C onsultancy service to prepar e financial sustainability plan Project Management and Co Under Implement s for Central Bank and Minist TF / A9642 Prior Direct Selection Direct 170,000.00 0.00 2021-09-17 2021-10-13 2021-10-20 2022-06-27 ordination ation ry of Commerce and Industry to assist with fiscal planning and sustainability of services delivered & institutional effec tiveness SO-MOF-253780-CS-CDS / E Project Management and Co Under Implement nvironmental and Social Safe TF / A9642 Prior Direct Selection Direct 87,000.00 0.00 2021-09-20 2021-09-29 2021-09-30 2021-10-03 2021-10-09 2022-10-09 ordination ation guard Consultant for SCALED -UP PIU SO-MOF-258660-CS-INDV / I Individual Consult Pending Impleme TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2021-10-26 2021-11-26 2021-11-29 2021-12-15 2022-12-15 CT Consultant for Switch Proj ant Selection ntation ect SO-MOF-256363-CS-INDV / I Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2021-10-29 2021-11-30 2021-11-24 2021-11-26 2021-12-13 2022-12-13 CT Consultant for SPS project ant Selection ation SO-MOF-266890-CS-INDV / E mbedded Local Legal Advisor Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open 60,000.00 0.00 2021-12-08 2021-12-21 2022-01-03 2022-01-05 2022-01-21 2023-01-21 for Ministry of Communicatio ant Selection ation n and Technology SO-MOF-266891-CS-INDV / F Individual Consult Under Implement inance and Administration Co TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2021-12-08 2022-02-14 2022-01-03 2023-02-27 2022-01-06 2023-03-15 2022-01-22 2023-01-22 ant Selection ation nsultant for FRC SO-MOF-266892-CS-INDV / E Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 40,000.00 0.00 2021-12-08 2022-01-06 2022-01-06 2022-04-09 2022-01-09 2022-04-24 2022-01-26 2023-01-26 xecutive Assistant for FRC ant Selection ation SO-MOF-272062-CS-INDV / R Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 90,000.00 0.00 2022-01-10 2022-02-23 2022-02-18 2023-02-28 2022-02-21 2023-03-26 2022-03-09 2023-03-09 egulatory Expert ant Selection ation SO-MOF-272063-CS-CDS / C onsulting Services for CBS str Pending Impleme ongrooms on Design and Eng TF / A9642 Strengthening Institutions Prior Direct Selection Direct 70,000.00 0.00 2022-01-10 2022-01-20 2022-01-29 2022-07-28 ntation ineering, Required by CBS St rongrooms & Incineration Fac ilities SO-MOF-273543-CS-INDV / T echnical Advisor on Cybersec Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open 87,000.00 0.00 2022-01-24 2022-02-06 2022-02-22 2022-10-12 2022-03-04 2022-10-31 2022-04-08 2023-04-08 urity for Ministry of Communi ant Selection ation cation and Technology SO-MOF-266895-CS-INDV / I nternational consultant to Co nduct a review of Institutiona Enabling Financial and Digit Individual Consult l Development Plan (IDP) exp TF / B5774 Post Open 100,000.00 0.00 Canceled 2021-12-08 2021-12-21 2022-01-26 2022-01-28 2022-02-16 2022-08-15 al Services ant Selection erience in the SCALED-UP pro ject and identify incentives o ptions to improve IDP owners hip and performance SO-MOF-281989-CS-INDV / C Enabling Financial and Digit Individual Consult Under Implement onsultant to develop Gargaar IDA / D4330 Prior Limited 14,000.00 0.00 2022-03-03 2022-03-21 2022-03-08 2022-03-14 2022-04-18 2022-10-15 al Services ant Selection ation a Company Profile and Annua l Report Writer SO-MOF-287354-CS-INDV / I Individual Consult Under Implement TF / A9642 Strengthening Institutions Prior Open 72,000.00 0.00 2022-04-04 2022-08-22 2022-05-03 2022-05-06 2022-05-23 2023-05-18 CT Consultant for Switch Proj ant Selection ation ect SO-MOF-295539-CS-CDS / Po licy Advisor/SCALED-UP Focal TF / B5774 Strengthening Institutions Prior Direct Selection Direct 100,000.00 0.00 Signed 2022-05-21 2022-06-02 2022-05-31 2022-06-07 2022-08-04 2023-05-30 2023-08-04 point for Ministry of Commun ication and Technology SO-MOF-297512-CS-INDV / P Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open 72,000.00 0.00 2022-05-31 2022-08-16 2022-07-19 2022-08-09 2022-09-13 2023-09-13 rocurement Expert for Centra ant Selection ation l Bank SO-MOF-299094-CS-CDS / SF TF / B5774 Strengthening Institutions Prior Direct Selection Direct 96,000.00 0.00 Signed 2022-06-13 2022-06-30 2022-06-23 2022-07-18 2022-08-27 2022-10-02 MIS TA SO-MOF-299095-CS-INDV / E mbedded Advisor for Data Pr Individual Consult TF / B5774 Strengthening Institutions Prior Open 87,000.00 0.00 Under Review 2022-06-13 2022-06-16 2022-08-01 2022-08-22 2022-09-26 2023-09-26 otection (Individual Consulta ant Selection nt) for Ministry of Communic ation and Technology SO-MOF-299596-CS-INDV / I Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open 87,000.00 0.00 2022-06-16 2022-07-20 2022-08-04 2022-08-25 2022-09-29 2023-09-29 CT Consultant for Central Ba ant Selection ation nk Page 9 SO-MOF-304330-CS-CDS / C onsultancy Services to Provid Enabling Financial and Digit Under Implement IDA / D8430 Prior Direct Selection Direct - National 30,000.00 0.00 2022-07-18 2022-09-30 2022-07-28 2022-11-01 2022-09-03 2023-03-02 e Financial Audit Services to al Services ation Gargaara Company Limited SO-MOF-304332-CS-CDS / M TF / B5774 Strengthening Institutions Prior Direct Selection Direct - National 120,000.00 0.00 Under Review 2022-07-18 2022-07-25 2022-07-28 2022-07-28 2022-08-26 2023-06-27 2023-08-26 utual Evaluation Coordinator for FRC SO-MOF-304335-CS-CDS / Le gal Advisor for Ministry of Co TF / B5774 Strengthening Institutions Prior Direct Selection Direct - National 60,000.00 0.00 Canceled 2022-07-18 2022-08-14 2022-07-28 2022-10-01 2023-10-01 mmerce and Industry SO-MOF-304503-CS-INDV / I ndividual Consultant Institutional Review and Rest Individual Consult Open - Internationa Under Implement ructuring of the Ministry of C TF / B5774 Strengthening Institutions Prior 100,000.00 0.00 2022-07-18 2022-07-26 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ant Selection l ation ommunications and Technolo gy, as well as development o f a dedicated Ministry 5-year Strategic Plan SO-MOF-304329-CS-INDV / A Enabling Financial and Digit Individual Consult Under Implement ccountant for Gargaara Com IDA / D8430 Prior Limited 70,000.00 0.00 2022-07-27 2022-10-05 2022-08-01 2022-07-28 2022-08-22 2022-10-17 2022-09-26 2023-09-26 al Services ant Selection ation pany Limited SO-MOF-305712-CS-INDV / P Project Management and Co Individual Consult Under Implement rocurement Specialist for PIU TF / A9642 Prior Open - National 80,000.00 0.00 2022-07-25 2022-07-26 2022-08-18 2022-09-22 2022-08-23 2022-10-06 2022-09-16 2023-09-16 ordination ant Selection ation - Ministry of Finance Somalia SO-MOF-319310-CS-CDS / Pr Project Management and Co Direct - Internation ocurement Consultant for PIU TF / A9642 Prior Direct Selection 150,000.00 0.00 Canceled 2022-10-04 2022-10-09 2022-10-31 2023-10-31 ordination al - International SO-MOF-320077-CS-CDS / Pr Project Management and Co Direct - Internation Under Implement ocurement Consultant PIU - I TF / A9642 Prior Direct Selection 150,000.00 0.00 2022-10-06 2022-10-11 2022-10-16 2022-10-13 2022-10-31 2023-10-31 ordination al ation nternational SO-MOF-320415-CS-INDV / R Individual Consult Open - Internationa Pending Impleme eserve Management (RM) an TF / A9642 Strengthening Institutions Prior 96,000.00 0.00 2022-10-13 2022-12-01 2022-12-11 2022-12-31 2023-12-31 ant Selection l ntation d Asset Allocations Consultan t. SO-MOF-323013-CS-INDV / L Individual Consult Open - Internationa Under Implement TF / B5774 Strengthening Institutions Prior 80,000.00 0.00 2023-01-12 2022-12-29 2023-02-16 2023-03-06 2023-04-14 2024-04-13 egal advisor ID ant Selection l ation SO-MOF-325815-CS-INDV / E Individual Consult Open - Internationa TF / B5774 Strengthening Institutions Prior 30,000.00 0.00 Canceled 2023-01-12 2022-12-27 2023-02-24 2023-03-09 2023-03-20 2023-09-16 mbedded Professional Transl ant Selection l ator. SO-MOF-332567-CS-INDV / C Enabling Financial and Digit Individual Consult Open - Internationa Pending Impleme TF / B5774 Prior 80,280.00 0.00 2023-01-24 2023-03-23 2023-04-13 2023-05-18 2023-11-14 ommunication consultant for al Services ant Selection l ntation CBS SO-MOF-340104-CS-INDV / l Enabling Financial and Digit Individual Consult Open - Internationa egal and policy advisor to mi TF / A9642 Prior 60,000.00 0.00 Under Review 2023-02-10 2023-02-13 2023-03-15 2023-03-22 2023-04-12 2024-04-06 al Services ant Selection l nistry of commerce and indu stry SO-MOF-342298-CS-INDV / C Individual Consult Open - Internationa Under Implement TF / A9642 Strengthening Institutions Prior 104,000.00 0.00 2023-02-18 2023-02-13 2023-04-08 2023-04-29 2023-06-03 2024-05-28 ommunication Consultant ant Selection l ation SO-MOF-343936-CS-INDV / S Individual Consult Pending Impleme tatistics Expert for Central Ba TF / A9642 Strengthening Institutions Prior Open - National 90,360.00 0.00 2023-02-22 2023-04-12 2023-05-03 2023-06-07 2024-06-06 ant Selection ntation nk of Somalia SO-MOF-345384-CS-INDV / I Individual Consult Under Implement CT Consultant – Somali Paym TF / B5774 Strengthening Institutions Prior Open - National 70,200.00 0.00 2023-02-28 2023-04-13 2023-04-18 2023-05-09 2023-06-13 2024-06-12 ant Selection ation ent Switch (SPS) SO-MOF-350222-CS-CDS / C onsulting Services for Techni Enabling Financial and Digit Under Implement cal support for an Electronic TF / A9642 Prior Direct Selection Direct - National 119,700.00 0.00 2023-04-03 2023-04-18 2023-04-13 2023-06-29 2023-06-17 2024-06-16 al Services ation Management Information Sy stem for (EMIS – AD) Account ant General office SO-MOF-353257-CS-INDV / s Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open - National 91,000.00 0.00 2023-03-30 2023-04-13 2023-05-18 2023-06-08 2023-07-13 2024-07-12 tatistics Expert for CBS ant Selection ation SO-MOF-353293-CS-INDV / F Individual Consult Open - Internationa Under Implement TF / B5774 Strengthening Institutions Prior 90,000.00 0.00 2023-03-30 2023-04-12 2023-05-18 2023-06-08 2023-07-13 2024-07-12 inancial Sector Expert - CBS ant Selection l ation SO-MOF-353315-CS-INDV / O Individual Consult Open - Internationa Under Implement rganization-wide Risk and Co TF / A9642 Strengthening Institutions Prior 102,000.00 0.00 2023-03-30 2023-04-05 2023-05-18 2023-06-08 2023-07-13 2024-07-12 ant Selection l ation mpliance Management Exper t for CBS SO-MOF-353961-CS-INDV / E Individual Consult Under Implement mbedded Professional Transl TF / B5774 Strengthening Institutions Prior Limited 30,000.00 0.00 2023-03-31 2023-04-18 2023-04-05 2023-06-07 2023-04-26 2023-05-31 2023-11-27 ant Selection ation ator for MOCT SO-MOF-360169-CS-INDV / C Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 76,800.00 0.00 2023-05-10 2023-06-28 2023-07-19 2023-08-23 2024-08-17 ommunications Specialist for ant Selection ntation NIRA SO-MOF-360524-CS-INDV / C Individual Consult Under Implement TF / B5774 Strengthening Institutions Prior Open - National 80,280.00 0.00 2023-05-15 2023-07-03 2023-07-24 2023-08-28 2024-08-22 ybersecurity Specialist for NI ant Selection ation RA SO-MOF-360525-CS-INDV / I Individual Consult Pending Impleme nstitutional Development Ad TF / B5774 Strengthening Institutions Prior Open - National 80,280.00 0.00 2023-05-15 2023-07-03 2023-07-24 2023-08-28 2024-08-22 ant Selection ntation visor for NIRA SO-MOF-360526-CS-INDV / N Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 80,280.00 0.00 2023-05-15 2023-07-03 2023-07-24 2023-08-28 2024-08-22 etwork Architect consultant f ant Selection ntation or NIRA SO-MOF-360528-CS-INDV / P Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 80,280.00 0.00 2023-05-15 2023-07-03 2023-07-24 2023-08-28 2024-08-22 olicy and strategy advisor for ant Selection ntation NIRA SO-MOF-360529-CS-INDV / S Individual Consult Pending Impleme oftware Development Special TF / B5774 Strengthening Institutions Prior Open - National 80,280.00 0.00 2023-05-18 2023-07-06 2023-07-27 2023-08-31 2024-08-25 ant Selection ntation ist for NIRA SO-MOF-360530-CS-INDV / S Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 87,480.00 0.00 2023-05-15 2023-07-03 2023-07-24 2023-08-28 2024-08-22 olutions Architect Advisor for ant Selection ntation NIRA Page 10 SO-MOF-362842-CS-INDV / F Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 59,280.00 0.00 2023-06-05 2023-07-24 2023-08-14 2023-09-18 2024-09-17 ocal Point and Coordination f ant Selection ntation or DPA SO-MOF-362845-CS-INDV / L Individual Consult Pending Impleme TF / B5774 Strengthening Institutions Prior Open - National 70,200.00 0.00 2023-06-05 2023-07-24 2023-08-14 2023-09-18 2024-09-12 egal Adviser for DPA ant Selection ntation SO-MOF-362846-CS-INDV / D Individual Consult Pending Impleme ata Protection - Technical Ex TF / B5774 Strengthening Institutions Prior Open - National 59,280.00 0.00 2023-05-25 2023-06-20 2023-07-11 2023-08-15 2024-08-09 ant Selection ntation pert for DPA SO-MOF-362869-CS-INDV / F Enabling Financial and Digit Individual Consult Under Implement IDA / D4330 Prior Open - National 59,280.00 0.00 2023-05-30 2023-07-18 2023-08-08 2023-09-12 2024-09-06 inancial Institution Analyst F al Services ant Selection ation or Gargaara Page 11 PROCUREMENT PLAN (Textual Part) Project information: P167958 - COMMUNITY PARTICIPATION IN HOW IS MY SCHOOL DOING PROJECT Project Implementation agency: World Vision Dominicana Date of the Procurement Plan: 03-08-2022 Period covered by this Procurement Plan: during project implementation Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not applicable Works: Not applicable PROCUREMENT Dominican Republic : COMMUNITY PARTICIPATION IN HOW IS MY SCHOOL DOING PROJECT PLAN General Information Country: Dominican Republic 2022-03-31 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167958 GPN Date: 2022-04-26 Project Name: COMMUNITY PARTICIPATION IN HOW IS MY SCHOOL DOING PROJECT Loan / Credit No: TF / B0840 How is my School Doing Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DO-CVME-258014-GO-RFQ / Monitoring, Evaluation and L Request for Quota Single Stage - One E Adquisición de Softwares (Po TF / B0840 earning, and Project Manage Post Limited 150.00 0.00 Canceled 2022-04-19 2022-06-14 2023-01-18 tions nvelope wer BI, Zoom etc.) ment DO-CVME-258020-GO-RFQ / Monitoring, Evaluation and L Request for Quota Single Stage - One E TF / B0840 Post Open - National 4,500.00 5,207.89 Completed 2022-05-05 2022-07-23 2022-06-30 2022-07-22 2022-12-27 2022-07-27 Adquisición de 3 Laptop. earning, and Project Manage tions nvelope ment DO-CVME-257960-GO-RFQ / Community participation in s Request for Quota Single Stage - One E Adquisición de Accesorios de TF / B0840 chool management through Post Open - National 2,500.00 0.00 Canceled 2022-04-24 2022-06-19 2022-12-16 tions nvelope computadoras y cámara de v CVME ideos para TV DO-CVME-258017-GO-RFQ / Community participation in s Request for Quota Single Stage - One E Adquisición de paquetes de i TF / B0840 chool management through Post Open - National 2,500.00 0.00 Canceled 2022-05-19 2022-07-14 2023-01-10 tions nvelope nternet para 30 Escuelas (rec CVME arga de 2 GB). DO-CVME-258016-GO-RFQ / Community participation in s Request for Quota Single Stage - One E Adquisición de 10 televisores TF / B0840 chool management through Post Open - National 3,000.00 0.00 Canceled 2022-05-05 2022-06-30 2022-12-27 tions nvelope Smart 40 pulgadas. CVME DO-CVME-257998-GO-RFQ / Community participation in s Servicio de impresión de Mat Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 2,500.00 2,464.30 Completed 2022-03-30 2022-08-02 2022-05-25 2022-08-13 2022-11-21 2022-08-26 erial didáctico para capacitac tions nvelope CVME iones en 60 escuelas. DO-CVME-258018-GO-RFQ / Solicitud de compra de mater iales de higiene (50 Alcohol d Community participation in s Request for Quota Single Stage - One E e 1500 ml, 50 gel antibacteri TF / B0840 chool management through Post Open - National 3,500.00 0.00 Canceled 2023-04-06 2023-06-01 2023-11-28 tions nvelope al de 10 ml, 500 mascarillas CVME quirúrgicas) para el desarroll o de actividades en comunid ades. DO-CVME-258002-GO-RFQ / Establishing a follow-up mec Servicio de Impresión de Mat hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 1,800.00 900.73 Completed 2022-03-30 2022-05-25 2022-05-10 2022-11-21 2022-05-31 eriales de visibilidad Afiches, the Ministry of Education thr tions nvelope Banners y díptico. ough CVME DO-CVME-285846-GO-RFQ / Adquisición de materiales ga Monitoring, Evaluation and L Request for Quota Single Stage - One E stables varios (lapiceros, libr TF / B0840 earning, and Project Manage Post Open - National 700.00 115.67 Completed 2022-04-04 2022-07-20 2022-05-30 2022-05-17 2022-11-26 2022-05-17 tions nvelope etas, folders etc.) para realiz ment ación de talleres en comunid ad educativa. DO-CVME-258024-GO-RFQ / Monitoring, Evaluation and L Request for Quota Single Stage - One E Plataforma (servidores virtua TF / B0840 earning, and Project Manage Post Open - National 16,235.00 0.00 Canceled 2022-04-19 2022-06-14 2022-12-11 tions nvelope les en la nube) ment DO-CVME-285844-GO-RFQ / Adquisición de Artículos pro mocionales Souvenir para las Monitoring, Evaluation and L Request for Quota Single Stage - One E APMAES Para celebración de TF / B0840 earning, and Project Manage Post Open - National 1,200.00 0.00 Canceled 2022-03-30 2022-05-25 2022-11-21 tions nvelope Dia de las APMAE" Polo-Shirt ment para los colaboradores integr antes de la comunidad educa tiva del proyecto. DO-CVME-256484-GO-RFQ / Community participation in s Adquisición de 60 Murales inf Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 3,000.00 0.00 Canceled 2022-04-05 2022-05-31 2022-11-27 ormativos para Centros educ tions nvelope CVME ativos, en Vinil adhesivo 20X 24. DO-CVME-257733-GO-RFQ / Community participation in s Servicio de Diseño e impresió Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 500.00 0.00 Canceled 2022-04-20 2022-06-15 2022-06-18 n de 60 Impresiones de Scor tions nvelope CVME e Card en Escuelas. DO-CVME-360032-GO-RFQ / Adquisición de materiales ga stables varios (lapiceros, libr Community participation in s etas, folders etc.) para realiz Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,000.00 0.00 Completed 2023-05-05 2023-06-13 2023-06-20 2023-05-25 ación de talleres en comunid tions nvelope CVME ad educativa y Adquisición d e 4 cajas plásticas para salva guardar las fuentes de verific ación del Proyecto. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DO-CVME-257943-NC-RFQ / Establishing a follow-up mec Diagramación y diseño de h hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 4,000.00 0.00 Canceled 2022-05-07 2022-07-02 2022-12-29 allazgo en la Evaluación de i the Ministry of Education thr tions nvelope mpacto del proyecto CVME. ough CVME Page 1 DO-CVME-257926-NC-RFQ / Diseño gráficos pedagógico d Community participation in s e los materiales de capacitac Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 2,200.00 0.00 Canceled 2022-10-20 2022-12-15 2023-06-13 ión (manuales, brochure, ban tions nvelope CVME ner ect.) Derivados de la gest ión y aprendizaje adaptivo de l proyecto. DO-CVME-258021-NC-RFQ / Community participation in s Request for Quota Single Stage - One E Servicio de producción de Vo TF / B0840 chool management through Post Open - National 2,000.00 0.00 Completed 2022-01-09 2022-07-28 2022-03-06 2022-09-02 2022-09-25 tions nvelope z en off para programa forma CVME tivo. DO-CVME-257954-GO-RFQ / Servicios de alimentos y rent Community participation in s Request for Quota Single Stage - One E a de espacio para realizar Co TF / B0840 chool management through Post Open - National 1,500.00 1,387.91 Completed 2022-04-27 2022-08-08 2022-06-22 2022-08-20 2022-12-19 2022-08-26 tions nvelope nmemoración del Día de la D CVME escentralización a nivel nacio nal, para 50 personas. DO-CVME-258000-GO-RFQ / Servicios de alimentos para r Monitoring, Evaluation and L ealizar "Foro Regional Ciudad Request for Quota Single Stage - One E TF / B0840 earning, and Project Manage Post Open - National 1,500.00 754.90 Completed 2022-04-06 2022-06-01 2022-04-30 2022-11-28 2022-05-07 anía Voz y Acción en Centros tions nvelope ment Educativos" en 28 Centros E ducativos de la zona Metropo litana, para 45 personas. DO-CVME-258028-GO-RFQ / Servicios de alimentos para r Community participation in s ealizar "Foro Regional Ciudad Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,200.00 1,043.92 Completed 2022-04-10 2022-07-20 2022-06-05 2022-04-29 2022-12-02 2022-04-29 anía Voz y Acción en Centros tions nvelope CVME Educativos" en 24 Centros Ed ucativos de la zona norte, pa ra 40 personas. DO-CVME-258350-NC-RFQ / Community participation in s Servicios de alimentos para r Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 500.00 767.42 Completed 2022-04-17 2022-07-22 2022-06-12 2022-05-21 2022-12-09 2022-05-24 ealizar Encuentro con Volunt tions nvelope CVME arios en la zona Metropolitan a, para 35 personas. DO-CVME-270877-NC-RFQ / Servicios de Alquiler de Trans porte privado con el recorrid Community participation in s Request for Quota Single Stage - One E o desde Santiago, La Vega y TF / B0840 chool management through Post Open - National 300.00 0.00 Canceled 2022-03-27 2022-05-22 2022-05-25 tions nvelope Bonao para participantes de CVME "Foro Regional Ciudadanía V oz y Acción en Centros Educa tivos" de la zona norte. DO-CVME-270850-NC-RFQ / Servicios de alimentos para r Community participation in s ealizar 5 talleres en 12 Centr Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 2,500.00 988.36 Completed 2022-04-19 2022-06-13 2022-06-14 2022-06-30 2023-01-18 2022-10-08 os Educativos en la Provincia tions nvelope CVME de Santiago para un total de 110 participantes por escuel a. DO-CVME-270875-NC-RFQ / Servicios de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar talleres Fase 2 CVA e TF / B0840 chool management through Post Open - National 35.54 0.00 Canceled 2022-04-06 2022-06-01 2022-11-28 tions nvelope n los 2 centros educativos en CVME Puerto Plata, zona norte. 5 p articipantes por escuelas. DO-CVME-270826-NC-RFQ / Servicios de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar 5 talleres en 4 Escuel TF / B0840 chool management through Post Open - National 800.00 250.87 Completed 2022-04-06 2022-06-13 2022-06-01 2022-06-21 2022-11-28 2022-06-21 tions nvelope as en la Villa Altagracia un to CVME tal de 65 participantes por es cuela. DO-CVME-270786-NC-RFQ / Servicios de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar 6 talleres en 4 Escuel TF / B0840 chool management through Post Open - National 800.00 476.32 Completed 2023-04-09 2022-06-13 2023-06-04 2022-06-30 2023-12-01 2022-10-08 tions nvelope a en Bonao un total de 110 p CVME articipantes por escuela. DO-CVME-270869-NC-RFQ / Servicios de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar 5 talleres en 2 Escuel TF / B0840 chool management through Post Open - National 350.00 448.97 Completed 2023-04-15 2022-06-13 2023-06-10 2022-06-27 2023-12-07 2022-10-09 tions nvelope a en La Provincia de Puerto P CVME lata un total de 110 participa ntes por escuela. DO-CVME-270852-NC-RFQ / Servicios de alimentos para r Community participation in s ealizar 5 talleres en 6 Centro Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,000.00 587.29 Completed 2023-04-15 2022-06-13 2023-06-10 2022-06-27 2023-12-07 2022-10-08 s Educativos en la Provincia tions nvelope CVME de La Vega para un total de 110 participantes por escuel a. DO-CVME-270805-NC-RFQ / Servicio de alimentos para re alizar Taller de formación con Community participation in s Request for Quota Single Stage - One E miembros de organismos de TF / B0840 chool management through Post Open - National 1,120.00 0.00 Completed 2022-04-06 2022-12-03 2022-06-01 2022-11-28 2022-12-10 tions nvelope participación escolar de 28 C CVME entros Educativos en el Gran Santo Domingo. 20 participa ntes por cada centro. DO-CVME-270881-NC-RFQ / Servicios de alimentos para r Community participation in s ealizar 4 talleres de la Fase 1 Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 3,400.00 0.00 Terminated 2022-04-19 2022-12-03 2022-06-14 2022-12-11 y 2 de CVA en los 28 centros tions nvelope CVME educativos en el Gran Santo Domingo. Un total de 90 part icipantes por escuela. DO-CVME-270837-NC-RFQ / Servicios de alimentos para r Community participation in s ealizar "Foro Regional Ciudad Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 700.00 0.00 Completed 2023-04-12 2022-10-26 2023-06-07 2023-12-04 2022-11-05 anía Voz y Acción en Centros tions nvelope CVME Educativos" en 8 Centros Edu cativos de San Cristóbal, par a 20 personas. DO-CVME-270863-NC-RFQ / Servicios de alimentos para r Community participation in s ealizar 5 talleres en 4 Centro Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,000.00 0.00 Completed 2022-04-06 2022-12-03 2022-06-01 2022-11-28 2022-11-30 s Educativos en la Provincia tions nvelope CVME de San Cristóbal para un tota l de 110 participantes por es cuela. DO-CVME-285916-NC-RFQ / Monitoring, Evaluation and L Servicio de Bordado de las C Request for Quota Single Stage - One E TF / B0840 earning, and Project Manage Post Open - National 80.00 0.00 Canceled 2021-03-25 2021-05-20 2021-11-16 amisas del Proyecto Mi Comu tions nvelope ment nidad Participa en CVME Page 2 DO-CVME-285910-NC-RFQ / Community participation in s Compra de Materiales Educat Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 70.00 0.00 Completed 2021-08-25 2021-10-20 2022-04-18 2021-09-05 ivos y gastables para utilizar tions nvelope CVME en encuentro con técnicos re gionales y distritales DO-CVME-285921-NC-RFQ / Servicio de alimentos y renta de local para celebrar la Jorn Community participation in s Request for Quota Single Stage - One E ada de capacitación del equi TF / B0840 chool management through Post Open - National 980.00 0.00 Completed 2021-08-07 2022-10-27 2021-10-02 2022-03-31 2022-11-14 tions nvelope po Vision Mundial, Técnicos R CVME egionales, Distritales y Direct ores de Centros Educativos Z ona Norte. DO-CVME-323688-NC-RFQ / Servicio de adquisición de m Community participation in s aterias educativos y gastable Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,500.00 0.00 Completed 2022-11-10 2022-11-25 2023-01-05 2023-07-04 2022-12-14 s para desarrollar encuentros tions nvelope CVME formativos con estudiantes, docentes y técnicos del MINE RD. DO-CVME-323689-NC-RFQ / Servicio de alimentos y renta de espacio para la celebració Establishing a follow-up mec n del Congreso Nacional de B hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Limited 6,000.00 0.00 Completed 2023-03-15 2023-03-01 2023-05-10 2023-11-06 2023-04-04 uenas Practicas de Participac the Ministry of Education thr tions nvelope ión Comunitaria en apoyo a l ough CVME a calidad educativa. Activida d de cierre del Proyecto. 100 personas. DO-CVME-323690-NC-RFQ / Monitoring, Evaluation and L Solicitud de materiales plega Request for Quota Single Stage - One E TF / B0840 earning, and Project Manage Post Open - National 2,500.00 0.00 Completed 2022-11-10 2022-12-09 2023-01-05 2023-07-04 2023-01-28 bles y portátiles para la impl tions nvelope ment ementación del Proyecto en campo. DO-CVME-323700-NC-RFQ / Servicio de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar jornada formativa con TF / B0840 chool management through Post Open - National 700.00 0.00 Completed 2022-11-10 2022-11-03 2023-01-05 2023-07-04 2022-11-16 tions nvelope Técnicos del MINERD en Sant CVME o Domingo Para 20 personas. Regional 10 DO-CVME-323692-NC-RFQ / Monitoring, Evaluation and L Servicio de impresión de mat Request for Quota Single Stage - One E TF / B0840 earning, and Project Manage Post Open - National 9,850.00 0.00 Completed 2022-11-10 2023-03-21 2023-01-05 2023-07-04 eriales formativos y de visibil tions nvelope ment idad del Proyecto DO-CVME-323691-NC-RFQ / Servicio de alimentos para 2 0 personas, actividad para d Community participation in s Request for Quota Single Stage - One E esarrollar Encuentro de revisi TF / B0840 chool management through Post Open - National 1,200.00 0.00 Completed 2022-11-25 2022-11-25 2023-01-20 2023-07-19 2022-12-10 tions nvelope ón del Protocolo de acción p CVME ara el seguimiento a los orga nismos de Participación Escol ar con Técnicos del MINERD. DO-CVME-323694-NC-RFQ / Community participation in s Servicio de diseño y diagram Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 4,300.00 0.00 Canceled 2022-11-25 2023-01-20 2023-07-19 ación de materiales formativ tions nvelope CVME os y de visibilidad del Proyec to DO-CVME-270878-NC-RFQ / Servicios de streaming para Establishing a follow-up mec Zoom y YouTube, Para celebr hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 5,000.00 0.00 Canceled 2023-01-06 2023-03-03 2023-08-30 ar el Congreso Nacional de B the Ministry of Education thr tions nvelope uenas Prácticas de Participac ough CVME ión Comunitaria en apoyo a l a calidad educativa. DO-CVME-258004-NC-RFQ / Servicio de alimentos para d Establishing a follow-up mec ar el Entrenamientos colabor hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 300.00 0.00 Canceled 2022-05-21 2022-11-07 2022-07-16 2023-01-12 ativos con IDEC y Comité de the Ministry of Education thr tions nvelope Veeduría para establecer vín ough CVME culos entre CVME, Plan Estrat égico y Pacto Educativo . DO-CVME-257730-GO-RFQ / Servicio de alimentos y renta Establishing a follow-up mec de espacio, Congreso Nacion hanism between schools and Request for Quota Single Stage - One E al de Buenas Practicas de Par TF / B0840 Post Open - National 1,500.00 0.00 Completed 2022-11-16 2022-11-04 2023-01-11 2023-07-10 2022-11-30 the Ministry of Education thr tions nvelope ticipación Comunitaria en ap ough CVME oyo a la calidad educativa, e n conmeración del mes de la familia. DO-CVME-285918-NC-RFQ / Monitoring, Evaluation and L Servicio de diseño e impresió Request for Quota Single Stage - One E TF / B0840 earning, and Project Manage Post Open - National 388.00 0.00 Completed 2020-07-11 2020-09-05 2021-03-04 2021-07-18 n 3 Banner tamano 31x80 PU tions nvelope ment LGS. Impresos a full color DO-CVME-285913-NC-RFQ / Establishing a follow-up mec Servicio de impresión de 50 c hanism between schools and Request for Quota Single Stage - One E opias a full color en papel Bo TF / B0840 Post Open - National 645.00 0.00 Completed 2021-05-01 2021-06-26 2021-12-23 2021-05-07 the Ministry of Education thr tions nvelope nd tamano 8/30 x11y encuar ough CVME denacion espiral a manual de encuestadores DO-CVME-257734-NC-RFQ / I Community participation in s Request for Quota Single Stage - One E mplementación de Plataform TF / B0840 chool management through Post Open - National 10,000.00 0.00 Canceled 2022-03-30 2022-07-29 2022-05-25 2022-11-21 tions nvelope a, creación de aula virtual de CVME estudio. DO-CVME-324459-NC-RFQ / I Community participation in s Request for Quota Single Stage - One E mplementación de Plataform TF / B0840 chool management through Post Open - National 20,000.00 0.00 Completed 2022-11-10 2022-12-08 2023-01-05 2023-07-04 2023-03-31 tions nvelope a, creación de aula virtual de CVME estudio. DO-CVME-258015-NC-RFQ / Establishing a follow-up mec Servicios de fotografia y vide hanism between schools and Request for Quota Single Stage - One E os para el Congreso Nacional TF / B0840 Post Open - National 715.00 0.00 Canceled 2022-03-30 2022-05-25 2022-11-21 the Ministry of Education thr tions nvelope de Buenas Practicas de Partic ough CVME ipación Comunitaria en apoy o a la calidad educativa. DO-CVME-285928-NC-RFQ / Community participation in s Servicio de alimentación par Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 208.00 0.00 Completed 2021-05-19 2021-07-14 2022-01-10 2021-05-31 a realizar jornadas en centro tions nvelope CVME s educativos zona metropolit ana DO-CVME-285920-NC-RFQ / Community participation in s Servicio de alimentación par Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 87.00 0.00 Canceled 2021-05-19 2021-07-14 2022-01-10 a realizar jornadas en centro tions nvelope CVME s educativos zona metropolit ana (Galleta) Page 3 DO-CVME-270866-NC-RFQ / Compra y servicio de bordad Monitoring, Evaluation and L Request for Quota Single Stage - One E o de camisas tipo Columbia, TF / B0840 earning, and Project Manage Post Open - National 2,000.00 0.00 Canceled 2022-04-04 2022-05-30 2022-11-26 tions nvelope mangas largas de colores ne ment gro, blanca y azul, con Logo del proyecto. DO-CVME-323697-NC-RFQ / Servicio de alimentos para r Community participation in s Request for Quota Single Stage - One E ealizar jornada formativa con TF / B0840 chool management through Post Open - National 700.00 0.00 Completed 2022-11-10 2022-12-03 2023-01-05 2023-07-04 2022-11-21 tions nvelope Tecnicos del MINERD en San CVME to Domingo Para 20 personas . Regional 15 DO-CVME-351268-NC-RFQ / Servicio de alimentos para so Establishing a follow-up mec cializar la sistematización de hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 700.00 0.00 Completed 2023-04-26 2023-06-30 2023-12-27 buenas prácticas en auditori the Ministry of Education thr tions nvelope a Social en centros educativo ough CVME s del Corredor Duarte. 20 per sonas. DO-CVME-352076-NC-RFQ / I mpresión del INFOGRAFICO 1 7x22 Cartonite 1 Cara. 100 ej Establishing a follow-up mec emplares. Impresión de las S hanism between schools and Request for Quota Single Stage - One E TF / B0840 Post Open - National 3,900.00 0.00 Canceled 2023-03-29 2023-05-24 2023-11-20 core Card de las 60 escuelas the Ministry of Education thr tions nvelope objetivos del Proyecto. A tod ough CVME o color 17X22. Impresión de 60 Murales de visibilidad de l as APMAE para 60 centros ed ucativos. DO-CVME-357699-NC-RFQ / Solicitud de refrigerio para re Community participation in s alizar Jornada formativo en t Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 1,000.00 0.00 Completed 2023-05-12 2023-05-10 2023-06-06 2023-06-20 2023-05-14 orno a la metodología Ciudan tions nvelope CVME ía, Voz y Acción con la comu nidad educativa de la escuel a Juan Pablo Pina, San Cristó bal. DO-CVME-359988-NC-RFQ / Encuentro de cierre del Proy ecto en la Zona Norte: Servic Community participation in s io de alimentos y renta de es Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 10,000.00 0.00 Completed 2023-05-12 2023-06-13 2023-06-18 pacio para la celebración del tions nvelope CVME cierre del proyecto y las entr egas de las Scoredcard (28x4 ) actividad para un estimado de 112 personas DO-CVME-359989-NC-RFQ / Encuentro de Cierre del Proy ecto en la Zona Metropolitan Community participation in s a: Servicio de alimentos y re Request for Quota Single Stage - One E TF / B0840 chool management through Post Open - National 15,000.00 0.00 Canceled 2023-05-12 2023-06-14 2023-06-19 nta de espacio para la celebr tions nvelope CVME ación del Cierre del Proyecto y las entregas de las Scoredc ard para un estimado de 14 0 personas DO-CVME-360025-GO-RFQ / Community participation in s Request for Quota Single Stage - One E TF / B0840 Post Open - National 10,000.00 0.00 Completed 2023-05-10 2023-06-10 2023-06-20 2023-06-20 Adquisición de Materiales ser chool management through tions nvelope igrafiados CVME DO-CVME-360015-NC-RFQ / I mpresión de Herramientas fo rmativas diseñadas o replica Establishing a follow-up mec das en el Marco del Proyecto hanism between schools and Request for Quota Single Stage - One E Mi Comunidad Participa en C TF / B0840 Post Open - National 21,390.00 0.00 Signed 2023-05-05 2023-05-26 2023-06-20 the Ministry of Education thr tions nvelope omo Va Mi Escuela e impresi ough CVME ón del Informe de la evaluaci ón del Proyecto, realizado en el formato del GPSA y murale s de visibilidad DO-CVME-364457-NC-RFQ / Establishing a follow-up mec Diseño, ilustración y diagram hanism between schools and Request for Quota Single Stage - One E Under Imple TF / B0840 Post Open - National 15,600.00 0.00 2023-06-04 2023-07-30 2024-01-26 ación de los materiales form the Ministry of Education thr tions nvelope mentation ativos y de visibilidad del pro ough CVME yecto. DO-CVME-365429-NC-RFQ / Solicitud de refrigerio para re alizar Encuentros del Cierre d Community participation in s Request for Quota Single Stage - One E Under Imple el Proyecto en Los 60 centros TF / B0840 chool management through Post Open - National 20,000.00 0.00 2023-06-06 2023-06-12 2023-06-12 tions nvelope mentation Educativos: CVME “Ciudadanía Voy y Acción For taleciendo la Participación Es colar y Comunitaria CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DO-CVME-258023-CS-CQS / Monitoring, Evaluation and L Consultant Qualifi TF / B0840 Post Open - National 9,000.00 0.00 Canceled 2023-04-03 2023-04-24 2023-06-07 2023-07-07 2023-08-11 2024-02-07 Auditoria Externa del proyect earning, and Project Manage cation Selection o. ment DO-CVME-285875-NC-RFQ / Establishing a follow-up mec Servicio de consultoría para l hanism between schools and Quality Based Sel Under Implement TF / B0840 Post Open - National 41,300.00 0.00 2021-04-19 2021-04-19 2021-05-10 2021-06-23 2021-04-14 2021-07-21 2021-04-14 2021-08-20 2021-04-08 2021-09-19 2021-04-16 2021-10-24 2022-10-24 evantamiento de Encuesta e the Ministry of Education thr ection ation n 180 centros educativos ough CVME DO-CVME-285906-CS-QBS / Monitoring, Evaluation and L Contratación de Firma De Au Quality Based Sel TF / B0840 earning, and Project Manage Post Open - National 5,610.00 0.00 Completed 2021-09-21 2021-05-17 2021-10-12 2021-11-25 2021-05-15 2021-12-23 2021-05-17 2022-01-22 2021-05-17 2022-02-21 2021-05-17 2022-03-28 2023-03-28 2022-07-29 ditores Para Visión Mundial In ection ment ternacional y Banco Mundial INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DO-CVME-257737-NC-RFQ / 2 Facilitadores para Jornada Community participation in s Individual Consult s formativas CVA Miembros d TF / B0840 chool management through Post Open 12,000.00 998.19 Completed 2022-04-01 2022-04-19 2022-05-20 2022-04-26 2022-06-10 2022-04-27 2022-07-15 2022-04-28 2023-01-11 2022-05-08 ant Selection e APMAEs, Técnicos Regional CVME es, Distritales y Directores de Centros Educativos. Page 4 DO-CVME-258398-CS-INDV / Monitoring, Evaluation and L Contratación de servicios de Individual Consult TF / B0840 earning, and Project Manage Post Open 50,342.47 0.00 Completed 2020-02-28 2020-01-20 2020-04-17 2020-02-18 2020-05-08 2020-03-24 2020-06-12 2020-12-09 2023-05-17 Consultoria para la eleboraci ant Selection ment ón de las Evaluaciones inter media y Final. DO-CVME-285869-CS-INDV / Community participation in s Servicio de consultoria para Individual Consult Under Implement TF / B0840 chool management through Post Open 5,478.00 0.00 2021-08-20 2021-04-12 2021-10-08 2021-03-31 2021-10-29 2021-05-05 2021-12-03 2022-06-01 el Desarrollo de capacitacion ant Selection ation CVME es en centros educativos DO-CVME-314908-CS-INDV / Servicio de consultoría indivi Community participation in s dual para facilitar fase 2 de l Individual Consult TF / B0840 chool management through Post Open - National 2,000.00 0.00 Canceled 2022-09-24 2022-10-26 2022-11-12 2022-12-03 2023-01-07 2023-07-06 a metodología ciudadanía, vo ant Selection CVME z y acción (CVA) a trabajar e n la zona norte de Santo Do mingo Este y Distrito Naciona l. DO-CVME-314910-CS-INDV / Desarrollar la fase 2 de CVA en 12 escuelas intervenidas Community participation in s Individual Consult por el Proyecto Mi Comunida TF / B0840 chool management through Post Open - National 3,000.00 0.00 Canceled 2022-09-24 2022-10-26 2022-11-12 2022-12-03 2023-01-07 2023-07-06 ant Selection d Participa en Como Va Mi Es CVME cuela, ubicadas en San Cristó bal, Villa Altagracia y Santo Domingo Oeste. DO-CVME-314911-CS-INDV / Desarrollar la fase 2 de CVA Community participation in s en 14 escuelas intervenidas Individual Consult TF / B0840 chool management through Post Open - National 3,500.00 0.00 Canceled 2022-09-24 2022-10-24 2022-11-12 2022-12-03 2023-01-07 2023-07-06 por el Proyecto Mi Comunida ant Selection CVME d Participa en Como Va Mi Es cuela, ubicadas en Bonao, La Vega, Santiago y Puerto Plat a DO-CVME-258019-CS-INDV / Establishing a follow-up mec Servicios de consultoría siste hanism between schools and Individual Consult TF / B0840 Post Open 15,000.00 0.00 Canceled 2022-07-01 2022-08-19 2022-09-09 2022-10-14 2023-04-12 matización de buenas practic the Ministry of Education thr ant Selection as en auditoria Social en cent ough CVME ros educativos. DO-CVME-357232-CS-CDS / Monitoring, Evaluation and L Under Implement TF / B0840 Post Direct Selection Direct - National 9,000.00 0.00 2023-04-21 2023-05-15 2023-05-01 2023-05-15 2023-07-05 2024-01-01 Auditoria externa del proyect earning, and Project Manage ation o ment DO-CVME-359985-CS-INDV / Servicio de consultoria para l a sistematizacion del proyect Establishing a follow-up mec o Mi Comunidad Participa en hanism between schools and Individual Consult Under Implement Como Va Mi Escuela (Buenas TF / B0840 Post Open - National 18,000.00 0.00 2023-05-05 2023-05-22 2023-05-25 2023-05-30 2023-06-13 2023-06-24 the Ministry of Education thr ant Selection ation Practicas) y Sistematizacion ough CVME y digitalizacion de datos cuali tativos y cuantitativos de 60 centros educativos ubicados en el corredor Duarte DO-CVME-360012-CS-INDV / Diseño de Murales de visibili dad de los Organismos de Pa Establishing a follow-up mec rticipación Escolar (Identifica hanism between schools and Individual Consult TF / B0840 Post Open - National 4,500.00 0.00 Canceled 2023-05-05 2023-06-20 2023-06-28 2023-07-07 2023-07-18 ndo los Roles y las funciones the Ministry of Education thr ant Selection de Cada uno) y Diagramació ough CVME n del Informe de la evaluació n del Proyecto, realizado en el formato del GPSA. DO-CVME-361876-CS-INDV / Servicio de Diseño, ilustració n y diagramación de las de S Establishing a follow-up mec core Card de las evaluacione hanism between schools and Individual Consult s de los estandares educativ TF / B0840 Post Open - National 7,000.00 0.00 Under Review 2023-05-16 2023-05-30 2023-05-23 2023-05-26 2023-05-31 2023-05-31 the Ministry of Education thr ant Selection os realizados durante la impl ough CVME ementacion del proyecto Mi Comunidad Participa en Com o Va Mi Escuela 60 escuelas. Full color 17X22. DO-CVME-362554-CS-INDV / PARA EL DISEÑO, ILUSTRACI Establishing a follow-up mec ÓN Y DIAGRAMACIÓN DE LOS hanism between schools and Individual Consult TF / B0840 Post Open - National 8,600.00 0.00 Canceled 2023-05-19 2023-05-29 2023-05-31 2023-06-09 2023-06-13 MATERIALES FORMATIVOS Y the Ministry of Education thr ant Selection DE VISIBILIDAD DEL PROYEC ough CVME TO MI COMUNIDAD PARTICIP A EN COMO VA MI ESCUELA Page 5 PROCUREMENT PLAN - Textual Part Project information: Sint Maarten Emergency Recovery Project (P167339) Project Implementation Agency: NRPB Date of the Procurement Plan: April 29, 2021 Period covered by this Procurement Plan: From April 2021 to March 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: Shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Legislation such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The Bank’s Anti- Corruption Guidelines and Sanctions Framework shall be incorporated into the national bidding documents by adding a page entitled “Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework”. 2. Contracts with an appropriate allocation of responsibilities, risks, and liabilities between the Borrower and the contractors/suppliers/consultants. 3. Rights for the Bank to review procurement documentation and activities. In accordance with the Procurement Regulations, each bidding document and contract shall include provisions stating the Bank's policy to sanction firms or individuals, found to have engaged in fraud and/or corruption as defined in the Procurement Regulations. In accordance with the Procurement Regulations, each bidding document and contract financed out of the proceeds of the Financing Agreement shall provide that bidders, suppliers, contractors and their subcontractors, agents, personnel, consultants, service providers, or suppliers shall permit the Bank to inspect all accounts, records and other documents relating to the bid submission and performance of the contract and to have said accounts and records audited by auditors appointed by the Bank. Acts intended to materially impede the exercise of the Bank's inspection and audit rights provided for in the Procurement Regulations constitute an obstructive practice as defined in the Regulations. 4. No bids shall be rejected solely because they fall below or exceed the estimated cost. All bids (including in the case when less than two bids are received) shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank's prior written concurrence. The Bidding Documents template to be used under “national open competitive procurement arrangements” are subject to prior written concurrence by the Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable. Procurement of Second-hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: not applicable Works: not applicable. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. Procurement in Situations of Urgent Need of Assistance or Capacity Constraints. PROCUREMENT PLAN Goods Notification Activity Draft Signed Review Procurement Evaluation of Intention Reference No. / In-Process Component Contract Contract Type Category Options of Award Description: Planned Planned Planned Restoring a community SX-NRPB- learning and 205571-GO-DIR / No cultural Post Goods Direct 2021/01/30 2021/02/13 2021/03/06 ICT Equipment environment, Project Management Consulting Services Draft Signed Negotiated Activity Contract Market Contract Reference No. In-Process Component Review Type Category Approach / Description: Planned Planned SX-NRPB- Restoring a 205590-CS- community CDS / ESS8 Consultant No learning and Post Direct 2021/03/26 2021/04/30 Cultural Services cultural Heritage environment Consultants SX-NRPB- 205594-CS- Rebuilding safe Consultant CDS / School No Prior Direct 2021/04/10 2021/05/15 schools Services and Library designs Individual Consultants Terms of Expression Signed Activity Reference of Interest Contract Reference In- Review Market Component Category No. / Process Type Approach Description: Planned Planned Planned SX-NRPB- 205589-CS- INDV / Consultant No Project Management Post Open 2021/03/04 2021/03/25 2021/06/24 MECYS Services Project Manager SX-NRPB- 205575-CS- Restoring a community INDV / learning and cultural Consultant Technical No Post Open 2021/01/04 2021/01/25 2021/04/26 environment,Project Services Assistant Management Project Engineer SX-NRPB- Restoring a community 205576-CS- learning and cultural Consultant INDV / No Post Open 2021/02/04 2021/02/25 2021/05/27 environment,Project Services Safeguards Management Specialist SX-NRPB- 205592-CS- Restoring a community INDV / Needs Consultant No learning and cultural Post Open 2021/02/04 2021/02/25 2021/05/27 Assessment Services environment for Inclusive Education SX-NRPB- 205415-CS- INDV / FRLP: Local Consultant to Restoring a community work on learning and cultural strategy and Consultant No environment,Strengthening Post Open 2021/01/04 2021/01/18 2021/04/19 Framework Services the Ministry’s Management for SXM Information System Cultural Heritage and other Learning Services SX-NRPB- 205561-CS- Consultant INDV / No Project Management Post Open 2021/01/04 2021/01/25 2021/04/26 Services Procurement Specialist SX-NRPB- 205593-CS- Strengthening the INDV / Consultant No Ministry’s Management Post Open 2021/03/01 2021/03/22 2021/06/21 Development Services Information System MIS framework PROCUREMENT St Maarten : Sint Maarten Emergency Recovery Project I PLAN General Information Country: St Maarten 2018-09-05 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167339 GPN Date: Project Name: Sint Maarten Emergency Recovery Project I Loan / Credit No: TF / A8079, TF / B5199 National Recovery Program Bureau Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned SX-NRPB-156576-CW-RFB / P Housing Repair and Public B Open - Internationa Single Stage - One E 2020-12-1 ublic Building Repairs: Educa TF / A8079 uildings Repair and Reconstr Prior Request for Bids 5,000,000.00 0.00 Canceled 2020-03-02 2020-03-07 2020-04-18 2020-05-18 2020-06-22 l nvelope 9 tion Facilities uction SX-NRPB-165115-CW-RFB / Housing Repair and Public B Single Stage - One E 2,418,911.5 2021-01-1 TF / A8079 Post Request for Bids Limited 1,000,000.00 Completed 2020-03-25 2020-04-16 2020-03-30 2020-04-16 2020-05-11 2020-05-07 2020-06-10 2020-06-01 2020-07-15 2020-07-10 Rehabilitation of Shelters uildings Repair and Reconstr nvelope 4 1 uction SX-NRPB-181992-CW-RFB / P Housing Repair and Public B Single Stage - One E 1,946,600.0 2021-05-0 TF / A8079 Prior Request for Bids Limited 1,500,000.00 Signed 2020-07-14 2020-08-10 2020-07-19 2020-11-03 2020-08-30 2020-09-11 2020-09-29 2020-11-12 2020-11-03 2021-01-19 riority School Repairs uildings Repair and Reconstr nvelope 0 2 uction SX-NRPB-183349-CW-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E 2021-03-0 SMHDF roof repairs, for retro TF / A8079 uildings Repair and Reconstr Post Limited 236,367.00 236,367.00 Signed 2020-07-13 2020-07-07 2020-09-07 2020-07-08 tions nvelope 6 active finance uction SX-NRPB-202289-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E 7,151,533.0 2021-08-2 Batch 2: Schools and F&A Bui TF / A8079 uildings Repair and Reconstr Post Request for Bids 4,750,000.00 Signed 2020-11-09 2021-04-27 2020-11-14 2021-05-10 2020-12-26 2021-07-06 2021-01-25 2021-10-01 2021-03-01 2021-12-21 l nvelope 0 8 lding Repairs uction SX-NRPB-202300-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E 5,471,564.0 2021-09-0 TF / A8079 Post Request for Bids 6,500,000.00 Signed 2020-11-16 2021-04-01 2020-11-21 2021-04-08 2021-01-02 2021-05-24 2021-02-01 2021-09-17 2021-03-08 2021-12-21 SMHDF Repairs Phase 2 uildings Repair and Reconstr l nvelope 0 4 uction SX-NRPB-202314-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E 2021-10-3 TF / A8079 Post Request for Bids 5,000,000.00 0.00 Canceled 2021-01-11 2021-08-31 2021-01-16 2021-08-31 2021-02-27 2021-11-09 2021-03-29 2022-01-14 2021-05-03 Batch 3: School Repairs uildings Repair and Reconstr l nvelope 0 uction Emergency measures for the SX-NRPB-202332-CW-RFB / Open - Internationa Single Stage - One E 3,779,342.0 2021-12-1 TF / A8079 recovery of disaster first res Post Request for Bids 5,000,000.00 Signed 2021-03-01 2021-08-23 2021-03-06 2021-08-23 2021-04-17 2021-10-05 2021-05-17 2021-11-05 2021-06-21 2022-01-11 GEBE Trenching Batch 1 l nvelope 0 8 ponders and preparedness f acilities SX-NRPB-208747-CW-DIR / Housing Repair and Public B 2021-07-1 Minor Repair Works to Home TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 27,772.18 28,065.55 Completed 2020-12-09 2020-12-01 2020-12-14 2020-12-01 2021-01-18 2021-01-07 7 s: Aluminum System uction Request for Bids - SX-NRPB-202315-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2022-12-1 TF / A8079 Post Request for Bids 4,500,000.00 0.00 2022-03-01 2022-03-06 2022-04-17 2022-05-17 2022-06-21 Expansion of the EOC Buildin uildings Repair and Reconstr l nvelope (1 envelope proce lementation 8 g uction ss) National Procure SX-NRPB-275606-CW-RFB / Housing Repair and Public B Single Stage - One E ment Document - 2023-02-1 Single Family Home Repairs TF / A8079 uildings Repair and Reconstr Post Request for Bids Open - National 3,000,000.00 0.00 Signed 2022-05-01 2022-06-15 2022-05-06 2022-06-16 2022-06-17 2022-08-10 2022-07-17 2022-09-28 2022-08-21 nvelope 1 Envelope proce 7 PHASE 3 uction ss (Non Bank-SPD ) Request for Bids - Emergency measures for the SX-NRPB-202333-CW-RFB / Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2022-12-1 TF / A8079 recovery of disaster first res Post Request for Bids 5,000,000.00 0.00 2022-03-01 2022-03-06 2022-04-17 2022-05-17 2022-06-21 GEBE Trenching Batch 2 l nvelope (1 envelope proce lementation 8 ponders and preparedness f ss) acilities National Procure SX-NRPB-278379-CW-RFB / P Housing Repair and Public B ment Document - rocurement of Repair and Re Open - Internationa Single Stage - One E 2022-12-0 TF / A8079 uildings Repair and Reconstr Post Request for Bids 1 Envelope proce 5,000,000.00 0.00 Signed 2022-02-14 2022-03-10 2022-02-19 2022-03-10 2022-04-02 2022-05-27 2022-05-02 2022-08-05 2022-06-06 habilitation Works for 13 SXM l nvelope 3 uction ss (Non Bank-SPD schools - relaunch ) Request for Quota SX-NRPB-278660-CW-DIR / Housing Repair and Public B 2022-09-2 TF / A8079 Post Direct Selection Direct tions (Non Bank-S 4,000.00 4,100.45 Signed 2022-02-15 2022-01-27 2022-02-20 2022-02-24 2022-03-27 2022-03-15 MAC High I.T Classroom Relo uildings Repair and Reconstr 3 PD) cation uction Request for Quota AN-NRPB-93655-CW-RFQ / M Housing Repair and Public B Request for Quota Single Stage - One E Under Imple 2020-01-2 TF / A8079 Post Open - National tions (Non Bank-S 500,000.00 0.00 2019-06-06 2019-08-01 inor Repairs to 26 Homes uildings Repair and Reconstr tions nvelope mentation 8 PD) uction Request for Quota AN-NRPB-93655A-CW-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E 2021-01-2 TF / A8079 Post Open - National tions (Non Bank-S 130,000.00 0.00 Signed 2020-06-06 2020-08-01 Minor Repairs to 3 Homes uildings Repair and Reconstr tions nvelope 8 PD) uction Request for Bids - SX-NRPB-357289-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-08-1 TF / B5199 Post Request for Bids 4,800,000.00 0.00 2023-04-30 2023-05-05 2023-06-16 2023-07-16 2023-08-20 Renovation of Gyms uildings Repair and Reconstr l nvelope (1 envelope proce lementation 9 uction ss) Request for Bids - SX-NRPB-357290-CW-RFB / Housing Repair and Public B Open - Internationa Single Stage - One E Small Works SPD Pending Imp 2024-08-1 TF / B5199 Post Request for Bids 3,100,000.00 0.00 2023-04-30 2023-05-05 2023-06-16 2023-07-16 2023-08-20 Renovation of Sports facilitie uildings Repair and Reconstr l nvelope (1 envelope proce lementation 9 s uction ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Emergency measures for the SX-NRPB-136740-GO-DIR / Fi TF / A8079 recovery of disaster first res Prior Direct Selection Direct 2,250,000.00 1,938,933.00 Signed 2019-10-01 2020-06-04 2019-10-01 2020-06-18 2019-11-05 2020-02-27 2020-05-03 re Trucks ponders and preparedness f acilities Emergency measures for the SX-NRPB-143339-GO-DIR / S TF / A8079 recovery of disaster first res Prior Direct Selection Direct 15,000.00 15,120.00 Signed 2019-10-29 2020-05-27 2019-11-03 2020-06-15 2019-12-08 2020-01-09 2020-06-05 afety Shoes Fire Department ponders and preparedness f acilities Emergency measures for the SX-NRPB-157539-GO-DIR / D TF / A8079 recovery of disaster first res Post Direct Selection Direct 20,000.00 17,690.00 Signed 2020-02-09 2020-02-04 2020-02-14 2020-03-19 2020-03-20 2020-03-28 2020-09-16 iesel Water Pumps ponders and preparedness f acilities Emergency measures for the SX-NRPB-160723-GO-DIR / A TF / A8079 recovery of disaster first res Post Direct Selection Direct 60,000.00 52,355.72 Signed 2020-02-20 2019-12-11 2020-02-25 2020-03-10 2020-03-31 2020-04-15 2020-09-27 mbulance: Spare Parts ponders and preparedness f acilities SX-NRPB-160730-GO-DIR / F Emergency measures for the D&AD: Additional Radios and TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 61,381.67 Signed 2020-02-20 2018-06-07 2020-02-25 2020-03-23 2020-03-31 2020-03-24 2020-09-27 Accessories ponders and preparedness f acilities Page 1 Emergency measures for the SX-NRPB-165436-GO-DIR / T TF / A8079 recovery of disaster first res Prior Direct Selection Direct 1,500,000.00 0.00 Canceled 2020-03-19 2020-06-04 2020-03-24 2020-06-18 2020-04-28 2020-10-25 ype II Ambulances ponders and preparedness f acilities Emergency measures for the SX-NRPB-167830-GO-DIR / P TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 100,213.14 Signed 2020-04-06 2020-03-05 2020-04-06 2020-04-06 2020-05-11 2020-04-22 2020-11-07 roPac Isolation Capsules ponders and preparedness f acilities Emergency measures for the AN-NRPB-76471-GO-RFB / G Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Prior Request for Bids 2,385,000.00 1,645,775.00 Signed 2020-05-18 2020-06-18 2020-05-23 2020-09-14 2020-07-04 2020-09-23 2020-08-03 2020-12-10 2020-09-07 2021-02-12 2021-03-06 eneral Vehicles l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-160728-GO-DIR / F TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 174,753.00 Signed 2020-02-20 2021-05-10 2020-02-25 2021-02-05 2020-03-31 2021-05-26 2020-09-27 D: Spare Parts ponders and preparedness f acilities Emergency measures for the SX-NRPB-160720-GO-DIR / S TF / A8079 recovery of disaster first res Prior Direct Selection Direct 170,000.00 0.00 Canceled 2020-02-20 2020-02-25 2020-03-31 2020-09-27 ubmersible Water Pumps ponders and preparedness f acilities Emergency measures for the SX-NRPB-185662-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 320,000.00 0.00 Canceled 2020-08-12 2020-10-07 2021-04-05 Crane Trucks (2) tions l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-202313-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 630,000.00 0.00 Canceled 2020-11-20 2021-03-04 2021-01-15 2021-07-14 Command Vehicles tions l nvelope ponders and preparedness f acilities SX-NRPB-213914-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 15,400.00 21,052.00 Signed 2021-01-15 2021-03-11 2021-01-20 2021-02-05 2021-02-24 2021-04-17 2021-08-23 r Parts 2 : Waziri Export ponders and preparedness f acilities SX-NRPB-213915-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 8,800.00 6,603.47 Signed 2021-01-15 2021-03-11 2021-01-20 2021-02-05 2021-02-24 2021-05-07 2021-08-23 r Parts 3: Saint-Martin Cars ponders and preparedness f acilities Emergency measures for the SX-NRPB-216605-GO-RFQ / T Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 90,000.00 0.00 Canceled 2021-02-03 2021-06-28 2021-03-31 2021-09-27 hirty Seater Bus (1) tions l nvelope ponders and preparedness f acilities SX-NRPB-218343-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 27,500.00 28,132.52 Signed 2021-02-09 2021-03-11 2021-02-14 2021-02-08 2021-03-21 2021-04-14 2021-09-17 r Parts Package 4: Motorworl ponders and preparedness f d acilities SX-NRPB-218364-GO-DIR / Si Emergency measures for the nt Maarten Fire Service Repai TF / A8079 recovery of disaster first res Post Direct Selection Direct 3,000.00 2,181.54 Signed 2021-02-09 2021-03-11 2021-02-14 2021-02-08 2021-03-21 2021-04-16 2021-09-17 r Parts package 5: Napa Auto ponders and preparedness f Parts SXM acilities SX-NRPB-220199-GO-DIR / T Emergency measures for the ype II Ambulances: Wheeled TF / A8079 recovery of disaster first res Prior Direct Selection Direct 1,500,000.00 1,146,956.00 Signed 2021-02-18 2021-02-18 2021-02-23 2021-02-18 2021-03-30 2021-03-02 2021-09-26 Coach/ REV Group ponders and preparedness f acilities Emergency measures for the SX-NRPB-216373-GO-RFQ / S Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 215,000.00 0.00 Canceled 2021-02-02 2021-04-12 2021-03-30 2021-09-26 upport Vehicles - Vans tions l nvelope ponders and preparedness f acilities SX-NRPB-221791-GO-DIR / C Emergency measures for the Pending Impl omputer Tablets and Protecti TF / A8079 recovery of disaster first res Post Direct Selection Direct 3,000.00 0.00 2021-02-27 2021-03-04 2021-04-08 2021-10-05 ementation ve Cases: Keijzer Computer S ponders and preparedness f ystems NV acilities Emergency measures for the SX-NRPB-239642-GO-RFQ / Request for Quota Single Stage - One E TF / A8079 recovery of disaster first res Post Limited 215,000.00 124,500.00 Signed 2021-06-22 2021-06-21 2021-08-17 2021-09-17 2022-02-13 Vans II tions nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-241317-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 486,500.00 0.00 Canceled 2021-07-02 2021-07-21 2021-08-27 2022-02-23 Command Vehicles II (7) tions l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-241320-GO-RFQ / Request for Quota Open - Internationa Single Stage - One E TF / A8079 recovery of disaster first res Post 142,500.00 0.00 Canceled 2021-07-02 2021-07-15 2021-08-27 2022-02-23 Command Pick-up Trucks (3) tions l nvelope ponders and preparedness f acilities Emergency measures for the SX-NRPB-202345-GO-RFQ / Request for Quota Single Stage - One E TF / A8079 recovery of disaster first res Post Open - National 35,000.00 0.00 Signed 2020-12-06 2021-01-31 2021-07-30 MDS Goods tions nvelope ponders and preparedness f acilities SX-NRPB-202327-GO-RFQ / Emergency measures for the Request for Quota Open - Internationa Single Stage - One E Pending Impl MDS Automatic Weather Stat TF / A8079 recovery of disaster first res Post 350,000.00 0.00 2022-06-06 2022-08-01 2023-01-28 tions l nvelope ementation ions and Tidal Gauges ponders and preparedness f acilities Emergency measures for the SX-NRPB-275366-GO-DIR / Fi TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 103,361.00 Signed 2022-02-01 2022-01-26 2022-02-06 2022-03-02 2022-03-13 2022-05-12 2022-09-09 re Suits - Viking ponders and preparedness f acilities SX-NRPB-284636-GO-RFB / F Emergency measures for the Open - Internationa Single Stage - One E Under Imple ire and Ambulance Vehicles ( TF / A8079 recovery of disaster first res Post Request for Bids 108,672.00 0.00 2022-03-21 2022-04-26 2022-03-26 2022-04-27 2022-05-07 2022-05-31 2022-06-06 2022-07-08 2022-07-11 2023-01-07 l nvelope mentation 12) ponders and preparedness f acilities Emergency measures for the SX-NRPB-284650-GO-RFB / V Open - Internationa Single Stage - One E Under Imple TF / A8079 recovery of disaster first res Post Request for Bids 200,000.00 0.00 2022-03-21 2022-07-14 2022-03-26 2022-07-19 2022-05-07 2022-10-04 2022-06-06 2022-11-16 2022-07-11 2023-01-07 ROMI Specialty Trucks l nvelope mentation ponders and preparedness f acilities SX-NRPB-288112-GO-DIR / M Emergency measures for the Pending Impl odular classrooms for tempor TF / A8079 recovery of disaster first res Post Direct Selection Direct 90,000.00 0.00 2022-04-05 2022-04-10 2022-05-15 2022-11-11 ementation ary relocation of classrooms ponders and preparedness f under repair acilities SX-NRPB-300150-GO-DIR / A Emergency measures for the mbulance Vehicle Warning Li TF / A8079 recovery of disaster first res Post Direct Selection Direct 4,000.00 0.00 Completed 2022-06-21 2022-07-01 2022-06-26 2022-07-01 2022-07-31 2023-01-27 2022-11-25 ghts & Siren ponders and preparedness f acilities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-160721-NC-DIR / E Housing Repair and Public B mergency Mold Assessment TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 150,000.00 8,082.00 Signed 2020-02-20 2020-02-21 2020-02-25 2020-02-17 2020-03-31 2020-02-22 2020-09-27 and Remediation Action Plan uction Page 2 SX-NRPB-232003-NC-DIR / R Housing Repair and Public B etroactive Lease Agreement: TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 4,200.00 5,400.00 Signed 2021-04-30 2021-04-09 2021-05-05 2020-12-04 2021-06-09 2021-05-20 2021-12-06 Simpson Bay Community Cen uction ter SX-NRPB-278661-NC-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E Pending Impl TF / A8079 Post Limited 6,000.00 0.00 2022-02-20 2022-04-17 2022-10-14 Dumpster Rental for 16 Scho uildings Repair and Reconstr tions nvelope ementation ols uction SX-NRPB-278700-NC-RFQ / Housing Repair and Public B Request for Quota Single Stage - One E TF / A8079 Post Limited 100,000.00 0.00 Signed 2022-02-20 2022-05-18 2022-04-17 2022-10-14 Moving Company for 16 Scho uildings Repair and Reconstr tions nvelope ols uction SX-NRPB-278672-NC-DIR / S Housing Repair and Public B ecurity Company Services for TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 30,000.00 0.00 Signed 2022-02-15 2022-02-11 2022-02-20 2022-02-23 2022-03-27 2022-09-23 MPC School uction SX-NRPB-278674-NC-RFQ / S Housing Repair and Public B Request for Quota Single Stage - One E torage Space/ Container Rent TF / A8079 uildings Repair and Reconstr Post Limited 130,000.00 57,995.00 Signed 2022-02-20 2022-06-13 2022-04-17 2022-08-10 2022-10-14 tions nvelope al for 16 Schools uction SX-NRPB-300184-NC-DIR / A Emergency measures for the mbulance Department Vehicl TF / A8079 recovery of disaster first res Post Direct Selection Direct 1,800.00 0.00 Completed 2022-06-21 2022-07-01 2022-06-26 2022-06-30 2022-07-31 2023-01-27 2022-12-02 e Branding and Striping ponders and preparedness f acilities SX-NRPB-311317-NC-DIR / M Housing Repair and Public B AC High Art Class Transporta TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 32,000.00 0.00 Signed 2022-08-29 2022-08-19 2022-09-03 2022-08-18 2022-10-08 2023-04-06 tion Services uction Emergency measures for the SX-NRPB-312693-NC-DIR / R TF / A8079 recovery of disaster first res Post Direct Selection Direct - National 10,000.00 0.00 Signed 2022-08-31 2022-08-15 2022-09-05 2022-09-07 2022-10-10 2023-04-08 ental for MAC CSE Art Studio ponders and preparedness f acilities SX-NRPB-328192-NC-DIR / S Housing Repair and Public B Pending Impl chools Moving Services Here TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 70,000.00 0.00 2021-02-25 2021-03-02 2021-04-06 2021-10-03 ementation and There Transport B.V uction SX-NRPB-328180-NC-DIR / A Housing Repair and Public B Pending Impl TF / A8079 Post Direct Selection Direct - National 5,000.00 0.00 2022-06-27 2022-07-02 2022-08-06 2023-02-02 rt Class Rental Silvia Carty uildings Repair and Reconstr ementation uction SX-NRPB-328195-NC-DIR / A Institutional Support for Rec Pending Impl dditional Structural Assessm TF / A8079 Post Direct Selection Direct - National 11,000.00 0.00 2021-02-21 2021-02-26 2021-04-02 2021-09-29 onstruction ementation ent and Design of 3 Schools I .C.E SX-NRPB-328194-NC-DIR / A Institutional Support for Rec Pending Impl dditional Structural Design a TF / A8079 Post Direct Selection Direct - National 2,432.00 0.00 2021-05-25 2021-05-30 2021-07-04 2021-12-31 onstruction ementation nd Assessment 3 Schools Pha se Two I.C.E SX-NRPB-328181-NC-DIR / S Housing Repair and Public B Pending Impl chools Security Services Haw TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 15,038.00 0.00 2021-04-28 2021-05-03 2021-06-07 2021-12-04 ementation keye Security Force uction SX-NRPB-328179-NC-DIR / S Housing Repair and Public B Pending Impl chools Transportation Servic TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct - National 4,500.00 0.00 2022-04-01 2022-04-06 2022-05-11 2022-11-07 ementation es Group Transnational Trans uction port Services SX-NRPB-328183-NC-DIR / Fi Emergency measures for the Pending Impl re Dept. Suit Sizing Camille S TF / A8079 recovery of disaster first res Post Direct Selection Direct - National 1,400.00 0.00 2020-10-09 2020-10-14 2020-11-18 2021-05-17 ementation ewing & Boutique ponders and preparedness f acilities SX-NRPB-328182-NC-DIR / Fi Emergency measures for the Under Imple re Dept. Suit Sizing Camille S TF / A8079 recovery of disaster first res Post Direct Selection Direct - National 2,700.00 0.00 2021-09-15 2020-10-09 2021-09-20 2020-10-09 2021-10-25 2022-04-23 mentation ewing & Boutique ponders and preparedness f acilities SX-NRPB-328191-NC-DIR / H Institutional Support for Rec Pending Impl TF / A8079 Post Direct Selection Direct - National 3,901.00 0.00 2021-06-01 2021-06-06 2021-07-11 2022-01-07 ome Assessment I.C.E house onstruction ementation Nr.8 SX-NRPB-328189-NC-DIR / C Institutional Support for Rec Pending Impl ombining Technical Files for TF / A8079 Post Direct Selection Direct - National 1,578.00 0.00 2021-07-07 2021-07-12 2021-08-16 2022-02-12 onstruction ementation Schools RFB 3 I.C.E SX-NRPB-327303-NC-DIR / P Emergency measures for the erforated Vinyl Sides for Amb TF / B5199 recovery of disaster first res Post Direct Selection Direct - National 500.00 0.00 Completed 2022-11-23 2022-11-17 2022-11-28 2022-12-07 2023-01-02 2023-07-01 2023-01-23 ulances ponders and preparedness f acilities SX-NRPB-347195-NC-RFQ / S Housing Repair and Public B Request for Quota Single Stage - One E Under Imple TF / B5199 Post Open - National 96,140.00 0.00 2023-03-18 2023-05-13 2024-08-13 ecurity Services for 13 Schoo uildings Repair and Reconstr tions nvelope mentation ls uction SX-NRPB-347196-NC-DIR / Tr Housing Repair and Public B Pending Impl TF / B5199 Post Direct Selection Direct - National 66,667.00 0.00 2023-03-13 2023-03-18 2023-04-22 2024-03-31 ansportation Services for 13 uildings Repair and Reconstr ementation Schools uction SX-NRPB-347197-NC-DIR / L Housing Repair and Public B ease Agreement with NIPA fo Pending Impl TF / B5199 uildings Repair and Reconstr Post Direct Selection Direct - National 9,943.19 0.00 2023-03-13 2023-03-18 2023-04-22 2023-07-22 r Kitchen & Restaurant faciliti ementation uction es for Sundial School Student s SX-NRPB-347198-NC-DIR / L Housing Repair and Public B ease Agreement with NIA for Pending Impl TF / B5199 uildings Repair and Reconstr Post Direct Selection Direct - National 5,805.00 0.00 2023-03-13 2023-03-18 2023-04-22 2023-07-22 Dance Studio facilities for Su ementation uction ndial School Students CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-132867-CS-LCS / A Institutional Support for Rec Least Cost Selecti TF / A8079 Prior Open - National 150,000.00 0.00 Canceled 2019-09-05 2019-09-26 2019-11-09 2019-12-07 2020-01-06 2020-02-10 2020-03-16 2020-09-12 udit Services NRPB onstruction on Institutional Support for Rec Least Cost Selecti ERP_C_015 / Audit services TF / A8079 Post Open - National 150,000.00 421,998.00 Signed 2019-09-05 2019-02-13 2019-09-26 2019-09-18 2019-11-09 2019-04-25 2019-12-07 2019-07-11 2020-01-06 2019-07-11 2020-02-10 2019-07-11 2020-03-16 2019-09-29 2020-09-12 onstruction on SX-NRPB-160722-CS-LCS / W Housing Repair and Public B Least Cost Selecti TF / A8079 Post Open - National 25,000.00 59,696.00 Signed 2019-11-06 2020-01-30 2019-11-27 2020-01-10 2020-01-30 2020-02-07 2020-03-25 2020-03-08 2020-03-25 2020-04-12 2020-03-25 2020-05-17 2020-04-24 2020-11-13 orks Verification Audit SMHD uildings Repair and Reconstr on F uction AN-IRC-NRPB-88561-CS-CQS Housing Repair and Public B Consultant Qualifi / SMHDF Technical Assessme TF / A8079 uildings Repair and Reconstr Post Open - National 250,000.00 207,300.00 Completed 2020-10-15 2019-01-03 2020-11-05 2020-11-17 2020-12-19 2019-01-24 2021-01-18 2019-09-27 2021-02-22 2019-10-01 2021-08-21 2020-04-09 cation Selection nt and Design for Phase 2 uction Page 3 AN-IRC-NRPB-109549-CS-QC Housing Repair and Public B Quality And Cost- BS / Technical Assessment Si TF / A8079 uildings Repair and Reconstr Post Open - National 500,000.00 522,461.00 Signed 2020-11-03 2019-07-10 2020-11-24 2021-08-04 2021-01-07 2019-04-22 2021-02-04 2019-04-22 2021-03-06 2019-04-22 2021-04-10 2019-07-11 2021-05-15 2019-07-16 2022-05-15 Based Selection ngle family Home Repairs 2 uction AN-NRPB-76431-CS-CQS / Su pervision Shelter Repairs Mai Institutional Support for Rec Consultant Qualifi n and Recovery Housing Rep TF / A8079 Post Open - National 100,000.00 402,811.88 Signed 2021-05-19 2019-02-11 2021-06-09 2022-03-08 2021-07-23 2019-03-22 2021-08-22 2019-08-12 2021-09-26 2019-08-16 2022-03-25 onstruction cation Selection air and Public Buildings Repai r and Reconstruction SX-NRPB-202330-CS-CQS / E Emergency measures for the Quality And Cost- Open - Internationa Pending Impleme mergency Cell Broadcast Sys TF / A8079 recovery of disaster first res Post 350,000.00 0.00 2022-06-01 2022-06-22 2022-08-05 2022-09-02 2022-10-02 2022-11-06 2022-12-11 2023-12-11 Based Selection l ntation tem ponders and preparedness f acilities SX-NRPB-298818-CS-LCS / N Institutional Support for Rec Least Cost Selecti Open - Internationa TF / A8079 Post 545,000.00 0.00 Signed 2022-06-14 2022-06-29 2022-07-05 2022-08-18 2022-07-05 2022-09-15 2022-08-15 2022-10-15 2022-09-29 2022-11-19 2022-09-29 2022-12-24 2023-06-22 RPB Financial Audit Services onstruction on l SX-NRPB-317497-CS-CQS / S Institutional Support for Rec Consultant Qualifi Open - Internationa TF / B5199 Post 20,000.00 0.00 Canceled 2022-09-23 2022-10-23 2022-11-07 2022-12-09 2023-01-08 2023-03-08 ecurity Assessment onstruction cation Selection l SX-NRPB-338215-CS-QCBS / Emergency measures for the Quality And Cost- Open - Internationa Under Implement Project Management Service TF / B5199 recovery of disaster first res Prior 3,000,000.00 0.00 2023-01-27 2023-04-12 2023-02-17 2023-05-17 2023-04-02 2023-04-30 2023-05-30 2023-07-04 2023-08-08 2024-12-02 Based Selection l ation s for ERP-1 ponders and preparedness f acilities SX-NRPB-352121-CS-CQS / P Housing Repair and Public B Consultant Qualifi Open - Internationa Pending Impleme TF / B5199 Post 150,000.00 0.00 2023-08-06 2023-08-27 2023-10-10 2023-11-09 2023-11-27 2024-11-26 reparation GEBE Investment uildings Repair and Reconstr cation Selection l ntation Plan uction INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SX-NRPB-124802-CS-INDV / Institutional Support for Rec Individual Consult PROJECT COORDINATOR– Sin TF / A8079 Post Open 180,000.00 267,983.36 Signed 2019-07-25 2019-07-25 2019-09-12 2019-10-18 2019-10-03 2019-11-25 2019-11-07 2020-05-30 2020-05-05 onstruction ant Selection t Maarten Digital Governmen t Project SX-NRPB-126135-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Prior Open 60,000.00 59,241.98 Signed 2019-08-03 2019-08-07 2019-09-21 2019-11-21 2019-10-12 2020-07-07 2019-11-16 2020-01-17 2020-05-14 Procurement Assistant Consu onstruction ant Selection ltant SX-NRPB-126138-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Prior Open 90,000.00 0.00 Canceled 2019-08-03 2019-08-07 2019-09-21 2019-10-12 2019-11-16 2020-05-14 Procurement Specialist Cons onstruction ant Selection ultant SX-NRPB-126137-CS-INDV / Institutional Support for Rec Individual Consult Portfolio and Accounting Offi TF / A8079 Post Open 180,000.00 0.00 Canceled 2019-08-03 2019-08-07 2019-09-21 2019-10-12 2019-11-16 2020-05-14 onstruction ant Selection cer for Small Enterprise Reco very Project SX-NRPB-126665-CS-CDS / I Institutional Support for Rec TF / A8079 Post Direct Selection Direct 14,000.00 12,150.00 Signed 2019-08-12 2019-09-01 2019-08-22 2019-08-08 2019-10-26 2019-09-01 2020-04-23 nterim Financial Managemen onstruction t Officer SX-NRPB-127209-CS-CDS / S Institutional Support for Rec TF / A8079 Post Direct Selection Direct 45,000.00 44,000.00 Signed 2019-08-14 2019-08-09 2019-08-24 2019-08-08 2019-10-28 2019-08-16 2020-04-25 takeholder Engagement Hom onstruction e Repairs SX-NRPB-128034-CS-INDV / J Institutional Support for Rec Individual Consult TF / A8079 Post Open 80,000.00 43,436.52 Terminated 2019-08-20 2019-08-23 2019-10-08 2019-10-18 2019-10-29 2019-11-12 2019-12-03 2019-11-16 2020-05-31 unior Communications Consu onstruction ant Selection ltant SX-NRPB-128036-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 40,000.00 27,000.00 Signed 2019-08-19 2019-08-22 2019-10-07 2019-11-19 2019-10-28 2019-11-26 2019-12-02 2019-11-27 2020-05-30 Financial Management Assist onstruction ant Selection ant SX-NRPB-129158-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 80,000.00 61,699.24 Signed 2019-08-26 2019-08-30 2019-10-14 2019-11-13 2019-11-04 2019-11-18 2019-12-09 2019-11-20 2020-06-06 Executive Assistant onstruction ant Selection SX-NRPB-129299-CS-INDV / J Institutional Support for Rec Individual Consult TF / A8079 Post Open 80,000.00 106,076.17 Signed 2019-08-30 2019-08-30 2019-10-18 2019-11-18 2019-11-08 2020-03-30 2019-12-13 2020-05-30 2020-06-10 r Environmental Safeguards onstruction ant Selection Specialist SX-NRPB-134548-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 25,000.00 0.00 Canceled 2019-09-16 2018-12-10 2019-11-04 2019-11-25 2019-12-30 2020-06-27 Communications Specialist onstruction ant Selection SX-NRPB-144180-CS-CDS / D Emergency measures for the esign Fire Department Renov TF / A8079 recovery of disaster first res Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-11-04 2021-05-03 2019-11-04 2020-01-08 2020-07-06 ation and Expansion ponders and preparedness f acilities SX-NRPB-146192-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 150,000.00 0.00 Canceled 2019-12-12 2019-12-12 2020-02-14 2020-03-06 2020-04-10 2020-10-07 Contract Manager onstruction ant Selection SX-NRPB-153308-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 150,000.00 108,000.00 Signed 2020-01-31 2020-01-24 2020-03-20 2020-06-11 2020-04-10 2020-06-24 2020-05-15 2020-06-25 2020-11-11 Project Manager Education Pr onstruction ant Selection oject SX-NRPB-154610-CS-CDS / Institutional Support for Rec Mission Project Manager Digit TF / A8079 Post Direct Selection Direct 8,000.00 7,250.00 Signed 2020-01-20 2020-01-21 2020-01-20 2019-10-18 2020-01-27 2020-01-24 2020-02-17 onstruction al Government SX-NRPB-155761-CS-INDV / Institutional Support for Rec Individual Consult Project Manager Enterprise R TF / A8079 Post Open 150,000.00 0.00 Canceled 2020-01-24 2020-03-13 2020-04-03 2020-05-08 2020-11-04 onstruction ant Selection ecovery Project SX-NRPB-156570-CS-CDS / P Institutional Support for Rec TF / A8079 Post Direct Selection Direct 320,000.00 0.00 Canceled 2020-01-29 2020-01-29 2020-05-03 2020-10-30 rocurement Consultant Servi onstruction ces SX-NRPB-146438-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Prior Open 150,000.00 0.00 Canceled 2019-11-20 2020-01-08 2020-01-29 2020-03-04 2020-08-31 Procurement Specialist Cons onstruction ant Selection ultant 2 SX-NRPB-156572-CS-CDS / P roject Manager ERP-1 Institutional Support for Rec This is a continuation of the c TF / A8079 Post Direct Selection Direct 185,000.00 184,500.00 Signed 2020-01-29 2020-03-10 2020-02-08 2020-03-10 2020-04-13 2020-03-26 2020-10-10 onstruction urrent contract. This contract will go into effect on April 1 - March 31 2021. SX-NRPB-146440-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Limited 50,000.00 57,975.00 Signed 2019-11-22 2019-11-27 2019-11-27 2020-01-20 2020-02-07 2020-03-09 2020-03-13 2020-03-13 2020-09-09 Activity Manager School Rep onstruction ant Selection airs SX-NRPB-159532-CS-CDS / N Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 200,000.00 49,262.46 Signed 2020-02-13 2021-02-02 2020-02-13 2020-02-13 2020-04-17 2020-02-13 2020-10-14 RPB Legal Services onstruction Page 4 SX-NRPB-161524-CS-CDS / A Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 8,000.00 0.00 2020-02-26 2020-03-07 2020-05-11 2020-11-07 irport Benchmark Study onstruction ntation SX-NRPB-165435-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 225,000.00 220,500.00 Signed 2020-03-19 2019-07-09 2020-03-29 2020-03-20 2020-06-02 2020-03-21 2020-11-29 ngineer onstruction SX-NRPB-166957-CS-CDS / P Institutional Support for Rec roject Coordinator Digital Go TF / A8079 Post Direct Selection Direct 16,000.00 40,000.00 Signed 2020-03-30 2019-12-01 2020-04-09 2020-04-02 2020-06-13 2020-04-10 2020-12-10 onstruction vernment INTERIM SX-NRPB-168099-CS-CDS / S Institutional Support for Rec TF / A8079 Post Direct Selection Direct 150,000.00 182,550.00 Signed 2020-04-08 2020-07-31 2020-04-18 2020-04-07 2020-06-22 2020-08-17 2020-12-19 ocial Safeguards Specialist onstruction SX-NRPB-168800-CS-CDS / D Institutional Support for Rec TF / A8079 Post Direct Selection Direct 120,000.00 177,000.00 Signed 2020-04-15 2020-04-14 2020-04-25 2020-05-04 2020-06-29 2020-05-05 2020-12-26 esign Rehabilitation of Shelte onstruction rs SX-NRPB-173096-CS-INDV / J Institutional Support for Rec Individual Consult TF / A8079 Post Open 60,000.00 89,982.21 Signed 2020-05-11 2019-10-01 2020-06-29 2020-05-15 2020-07-20 2020-06-19 2020-08-24 2020-06-23 2021-02-20 r Communication Officer 2 onstruction ant Selection SX-NRPB-167363-CS-CDS / Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 30,000.00 63,000.00 Signed 2020-04-02 2021-01-12 2020-04-12 2020-05-08 2020-06-16 2020-05-08 2020-12-13 MP: Procurement Consultant onstruction SX-NRPB-167376-CS-CDS / S Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 30,000.00 223,500.00 Signed 2020-04-02 2020-07-22 2020-04-12 2020-04-02 2020-06-16 2020-04-24 2020-12-13 I: Procurement Consultant onstruction SX-NRPB-186632-CS-CDS / T Housing Repair and Public B wenty Schools and F&A buildi TF / A8079 uildings Repair and Reconstr Prior Direct Selection Direct 820,600.00 790,190.00 Signed 2020-07-30 2020-08-19 2020-08-09 2020-05-19 2020-10-13 2020-09-01 2021-04-11 ng Design Consulting uction SX-NRPB-186392-CS-CDS / A Housing Repair and Public B sbestos Assessment Consulti TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 25,000.00 56,950.00 Signed 2020-07-29 2020-07-29 2020-08-08 2020-08-23 2020-10-12 2020-09-19 2021-04-10 ng Services ROBERTO DAVID uction OVICH SX-NRPB-189349-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 85,000.00 0.00 Canceled 2020-08-18 2019-11-14 2020-10-06 2020-10-27 2020-12-01 2021-05-30 HR Consultant onstruction ant Selection SX-NRPB-189691-CS-CDS / L Emergency measures for the and Negotiation for Link 6 Ro TF / A8079 recovery of disaster first res Prior Direct Selection Direct 50,000.00 0.00 Canceled 2020-08-20 2020-08-28 2020-08-30 2020-09-23 2020-11-03 2021-05-02 ad-Hubert Lopez HISMAR NV ponders and preparedness f acilities SX-NRPB-191068-CS-CDS / S Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 125,000.00 501,550.00 Signed 2020-08-28 2021-04-01 2020-09-07 2020-10-20 2020-11-11 2020-10-26 2021-05-10 GS Procurement Service onstruction SX-NRPB-196201-CS-CDS / F Institutional Support for Rec TF / A8079 Post Direct Selection Direct 30,000.00 0.00 Under Review 2020-09-25 2020-10-05 2020-12-09 2021-06-07 MO Consultant Home Based onstruction SX-NRPB-197284-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 180,000.00 181,250.00 Signed 2020-10-01 2020-12-12 2020-11-19 2020-05-18 2020-12-10 2020-06-01 2021-01-14 2021-01-12 2021-07-13 DL - Contract Manager onstruction ant Selection SX-NRPB-198813-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 150,000.00 0.00 Canceled 2020-10-15 2020-11-19 2020-12-03 2020-12-24 2021-01-28 2021-07-27 AR - Contract Manager onstruction ant Selection SX-NRPB-126986-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 85,690.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Lawyer onstruction ntation 1 SX-NRPB-126988-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 61,250.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Legal S onstruction ntation upport 1 SX-NRPB-126989-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 28,500.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Legal S onstruction ntation upport 2 SX-NRPB-126987-CS-CDS / C Institutional Support for Rec Pending Impleme TF / A8079 Post Direct Selection Direct 79,000.00 0.00 2019-08-16 2019-08-26 2019-10-30 2020-04-27 orporate Governance Lawyer onstruction ntation 2 SX-NRPB-199448-CS-CDS / C Institutional Support for Rec TF / A8079 Post Direct Selection Direct 23,750.00 23,684.00 Signed 2020-10-13 2020-11-19 2020-10-23 2020-02-06 2020-12-27 2020-10-29 2021-06-25 ontract Manager (DL) Home onstruction Based SX-NRPB-170435-CS-CDS / I Institutional Support for Rec nterim Environmental Safegu TF / A8079 Post Direct Selection Direct 20,000.00 21,720.00 Signed 2020-04-24 2019-09-02 2020-05-04 2019-11-18 2020-07-08 2020-05-08 2021-01-04 onstruction ards Specialist SX-NRPB-201640-CS-CDS / J Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 95,000.00 189,000.00 Signed 2020-10-26 2020-10-29 2020-11-05 2020-10-29 2021-01-09 2021-01-01 2021-07-08 B: Procurement Coordinator onstruction SX-NRPB-201789-CS-INDV / I Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Limited 25,000.00 0.00 2020-10-27 2020-10-27 2020-11-01 2020-11-22 2020-12-27 2021-06-25 nsurance Consultant onstruction ant Selection ation SX-NRPB-201788-CS-CDS / U Institutional Support for Rec TF / A8079 Post Direct Selection Direct 155,000.00 163,252.75 Signed 2020-10-27 2020-10-21 2020-11-06 2020-09-16 2021-01-10 2020-11-03 2021-07-09 B: Activity Manager Home Re onstruction pairs SX-NRPB-201795-CS-CDS / B Institutional Support for Rec TF / A8079 Post Direct Selection Direct 200,000.00 125,000.00 Signed 2020-10-27 2020-11-24 2020-11-06 2019-11-01 2021-01-10 2020-12-17 2021-07-09 B: ICT Helpdesk onstruction SX-NRPB-205755-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 50,000.00 50,000.00 Signed 2020-11-24 2020-11-20 2021-01-12 2021-03-04 2021-02-02 2021-03-04 2021-03-09 2021-05-20 2021-09-05 Copywriter onstruction ant Selection SX-NRPB-208921-CS-CDS / Institutional Support for Rec Mold Assessment Consultanc TF / A8079 Post Direct Selection Direct 50,000.00 141,910.00 Signed 2020-12-09 2020-12-07 2020-12-19 2020-12-03 2021-02-22 2021-01-15 2021-08-21 onstruction y: Farmer Environmental Gro up SX-NRPB-214549-CS-CDS / J Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 50,000.00 48,000.00 Signed 2021-01-18 2021-01-28 2021-01-28 2021-01-07 2021-04-03 2021-02-10 2021-09-30 A: Procurement Consultant onstruction SX-NRPB-215465-CS-CDS / A Housing Repair and Public B TF / A8079 Post Direct Selection Direct 200,000.00 218,842.20 Signed 2021-01-21 2021-01-20 2021-01-31 2021-01-21 2021-04-06 2021-02-16 2021-10-03 C: Project Manager Infrastruc uildings Repair and Reconstr ture uction SX-NRPB-211337-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 350,000.00 0.00 Canceled 2020-12-23 2021-01-02 2021-03-08 2021-09-04 ngineer onstruction SX-NRPB-231555-CS-INDV / J Emergency measures for the Individual Consult unior Environmental Speciali TF / A8079 recovery of disaster first res Post Open 60,000.00 70,200.00 Signed 2021-04-29 2021-05-18 2021-06-17 2021-09-06 2021-07-08 2021-09-30 2021-08-12 2021-10-01 2022-02-08 ant Selection st ponders and preparedness f acilities Page 5 SX-NRPB-232896-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 15,000.00 43,875.00 Signed 2021-05-03 2021-05-06 2021-06-21 2021-08-13 2021-07-12 2021-08-19 2021-08-16 2021-08-28 2022-02-12 HRM Consultant onstruction ant Selection SX-NRPB-236664-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 30,000.00 20,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-10-30 2022-03-09 Graphic Design Services onstruction ant Selection SX-NRPB-236668-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 30,000.00 35,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-11-04 2022-03-09 Video Production Services onstruction ant Selection SX-NRPB-236671-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 30,000.00 30,000.00 Signed 2021-05-28 2021-06-08 2021-07-16 2021-08-05 2021-08-06 2021-09-21 2021-09-10 2021-10-30 2022-03-09 Animation Services onstruction ant Selection SX-NRPB-239247-CS-CDS / S Institutional Support for Rec ocial Safeguards Consultant: TF / A8079 Post Direct Selection Direct 200,000.00 200,000.00 Signed 2021-06-14 2021-06-16 2021-06-24 2021-06-28 2021-08-28 2020-07-13 2022-02-24 onstruction Jo-Ann George SX-NRPB-240330-CS-CDS / Institutional Support for Rec TF / A8079 Post Direct Selection Direct 280,000.00 251,210.00 Signed 2021-06-18 2021-06-28 2021-06-20 2021-06-21 2021-06-23 2021-07-07 2023-05-31 MH: Project Manager EDMP onstruction SX-NRPB-241445-CS-CDS / D Emergency measures for the esign Fire Dept. Renovation a TF / A8079 recovery of disaster first res Post Direct Selection Direct 160,000.00 159,900.00 Signed 2021-06-28 2021-05-21 2021-07-08 2021-05-03 2021-09-11 2021-07-01 2022-03-10 nd Expansion: ICE ponders and preparedness f acilities SX-NRPB-242711-CS-CDS / P Institutional Support for Rec rocurement Coordinator: San TF / A8079 Post Direct Selection Direct 267,000.00 266,640.00 Signed 2021-07-11 2021-07-15 2021-07-21 2021-06-08 2021-09-24 2021-08-03 2022-03-23 onstruction tiago Ibarguen SX-NRPB-246966-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Prior Open 80,000.00 0.00 2021-09-17 2021-09-21 2021-11-05 2021-11-26 2021-12-31 2022-06-29 NRPB Procurement Assistant onstruction ant Selection ation SX-NRPB-252781-CS-CDS / P Institutional Support for Rec roject Funding Coordinator – TF / A8079 Post Direct Selection Direct 20,000.00 0.00 Canceled 2021-09-12 2021-09-08 2021-09-22 2021-11-26 2022-05-25 onstruction Housing Project SX-NRPB-253548-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 180,000.00 102,600.00 Signed 2021-09-17 2021-09-30 2021-11-05 2021-11-15 2021-11-26 2022-01-12 2021-12-31 2022-01-13 2022-06-29 DGTP Project Manager for DL onstruction ant Selection T SX-NRPB-254305-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Open 90,000.00 0.00 2021-09-24 2021-09-15 2021-11-12 2021-12-03 2022-01-07 2022-07-06 Program Management Assist onstruction ant Selection ation ant SX-NRPB-256482-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Open 90,000.00 0.00 2021-10-07 2021-10-05 2021-11-25 2021-12-16 2022-01-20 2022-07-19 Project Manager - Mental Hea onstruction ant Selection ation lth Project SX-NRPB-257387-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 60,000.00 58,800.00 Signed 2021-10-12 2021-10-08 2021-11-30 2022-01-27 2021-12-21 2022-04-06 2022-01-25 2022-04-07 2022-07-24 Executive Assistant II onstruction ant Selection SX-NRPB-257388-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 180,000.00 163,500.00 Signed 2021-10-12 2021-10-07 2021-11-30 2021-09-20 2021-12-21 2021-10-19 2022-01-25 2021-10-22 2022-07-24 Engineer II onstruction ant Selection SX-NRPB-257389-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 245,000.00 244,000.00 Signed 2021-10-12 2021-10-07 2021-11-30 2021-09-22 2021-12-21 2021-10-12 2022-01-25 2021-11-02 2022-07-24 Contract Manager II onstruction ant Selection SX-NRPB-257455-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 20,000.00 31,972.50 Signed 2021-10-12 2021-10-07 2021-10-22 2021-09-20 2021-12-26 2021-10-22 2022-06-24 ngineer II onstruction SX-NRPB-258195-CS-CDS / P Institutional Support for Rec TF / A8079 Prior Direct Selection Direct 40,000.00 82,400.00 Signed 2021-10-15 2021-10-19 2021-10-25 2021-10-20 2021-12-29 2021-11-02 2022-06-27 rocurement Consultant: Paol onstruction o Maculotti SX-NRPB-258246-CS-CDS / P Institutional Support for Rec roject Finance Specialist-Hou TF / A8079 Post Direct Selection Direct 20,000.00 23,240.00 Signed 2021-10-14 2021-10-13 2021-10-24 2021-10-14 2021-12-28 2021-10-15 2022-06-26 onstruction sing Project SX-NRPB-258918-CS-CDS / P Institutional Support for Rec TF / A8079 Post Direct Selection Direct 15,000.00 12,750.00 Signed 2021-10-22 2021-10-27 2021-11-01 2021-10-27 2022-01-05 2021-10-30 2022-07-04 roject Officer - Mental Health onstruction Project SX-NRPB-262565-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 130,000.00 140,000.00 Signed 2021-11-12 2021-11-08 2021-11-22 2021-10-20 2021-12-13 2021-12-04 2022-01-17 2021-12-13 2022-07-16 Procurement Consultant: Ms. onstruction ant Selection Jackson SX-NRPB-270528-CS-CDS / S Housing Repair and Public B TF / A8079 Post Direct Selection Direct 350,000.00 294,850.00 Signed 2021-12-24 2022-01-17 2022-01-03 2021-12-21 2022-03-09 2022-02-20 2022-09-05 chool Gyms Technical Assess uildings Repair and Reconstr ment uction SX-NRPB-272351-CS-CDS / P Institutional Support for Rec rocurement Consultant - Ho TF / A8079 Post Direct Selection Direct 72,090.00 72,090.00 Signed 2022-01-10 2022-01-14 2022-01-20 2022-01-18 2022-03-26 2022-01-22 2022-09-22 onstruction me Based : Paolo Maculotti SX-NRPB-272355-CS-CDS / P Institutional Support for Rec roject Manager EDMP: East W TF / A8079 Post Direct Selection Direct 165,000.00 174,000.00 Signed 2022-01-10 2022-01-07 2022-01-20 2022-01-05 2022-03-26 2022-02-25 2022-09-22 onstruction est Consultancy BV SX-NRPB-278264-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 250,000.00 295,050.00 Signed 2022-02-14 2022-03-01 2022-04-04 2022-04-18 2022-04-25 2022-05-16 2022-05-30 2022-05-17 2022-11-26 Senior Project Manager ERP1 onstruction ant Selection SX-NRPB-278699-CS-CDS / D Housing Repair and Public B esign of Fire Dept. Renovatio TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 171,124.00 152,075.25 Signed 2022-02-15 2022-03-24 2022-02-25 2022-03-14 2022-05-01 2022-03-31 2022-10-28 n and Expansion completion uction of deliverables SX-NRPB-281075-CS-CDS / C Institutional Support for Rec TF / A8079 Post Direct Selection Direct 180,000.00 181,250.00 Signed 2022-02-28 2022-03-11 2022-03-10 2022-01-14 2022-05-14 2022-03-31 2022-11-10 ontract Manager - D. Louis onstruction SX-NRPB-282293-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Open 245,000.00 0.00 2022-03-11 2022-03-03 2022-04-29 2022-05-20 2022-06-24 2022-12-21 Social Safeguards Specialist onstruction ant Selection ation SX-NRPB-280013-CS-CDS / E Institutional Support for Rec TF / A8079 Post Direct Selection Direct 125,000.00 112,370.00 Signed 2022-03-08 2022-03-14 2022-03-18 2022-03-04 2022-05-22 2022-03-16 2022-11-18 nvironmental Safeguards Spe onstruction cialist SX-NRPB-286353-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 52,500.00 150,480.00 Signed 2022-03-28 2022-03-21 2022-04-07 2022-03-23 2022-04-28 2022-03-23 2022-06-02 2022-04-06 2022-11-29 Senior Human Resources Con onstruction ant Selection sultant SX-NRPB-286729-CS-CDS / E Housing Repair and Public B Under Implement SS8 Cultural Heritage Mental TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 20,000.00 0.00 2022-03-30 2022-04-14 2022-04-09 2022-04-21 2022-06-13 2022-12-10 ation Health Project uction SX-NRPB-287284-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 105,000.00 103,106.00 Signed 2022-03-31 2022-05-24 2022-04-10 2022-05-31 2022-05-01 2022-05-31 2022-06-05 2022-06-02 2022-12-02 Activity Coordinator Home an onstruction ant Selection d Schools Page 6 SX-NRPB-288109-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / A8079 Post Direct 161,712.00 0.00 2022-04-05 2022-05-15 2022-04-15 2022-08-17 2022-05-06 2022-08-17 2022-06-10 2022-12-07 Social Safeguards Consultant onstruction ant Selection ation SX-NRPB-291870-CS-CDS / R Housing Repair and Public B eview of MET building design TF / A8079 uildings Repair and Reconstr Post Direct Selection Direct 7,400.00 6,688.00 Signed 2022-04-28 2022-05-04 2022-05-08 2022-04-13 2022-07-12 2022-05-10 2023-01-08 : Structural Integrity uction SX-NRPB-287287-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Direct 136,940.00 136,980.00 Signed 2022-05-04 2022-04-26 2022-05-14 2022-04-22 2022-06-04 2022-05-05 2022-07-09 2022-05-06 2023-01-05 Senior Advisor – Project Mana onstruction ant Selection gement SX-NRPB-294730-CS-INDV / Institutional Support for Rec Individual Consult Under Implement Medior Project Manager – Ho TF / A8079 Post Open 162,000.00 0.00 2022-05-17 2022-05-13 2022-07-05 2022-07-26 2022-08-30 2023-02-26 onstruction ant Selection ation using Project SX-NRPB-295647-CS-INDV / Institutional Support for Rec Individual Consult Communication Consultant - TF / A8079 Post Direct 63,250.00 63,000.00 Signed 2022-05-24 2022-05-16 2022-06-03 2022-06-30 2022-06-24 2022-06-30 2022-07-29 2022-07-01 2023-01-25 onstruction ant Selection Copywriter SX-NRPB-298841-CS-INDV / Institutional Support for Rec Individual Consult Communication and Commu TF / A8079 Post Direct 57,000.00 57,000.00 Signed 2022-06-10 2022-06-09 2022-06-20 2022-06-15 2022-07-11 2022-06-15 2022-08-15 2022-06-17 2023-02-11 onstruction ant Selection nity Outreach Consultant SX-NRPB-304252-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation PROJECT COORDINATOR - INF TF / A8079 Post 229,786.00 229,786.00 Signed 2022-07-21 2022-07-25 2022-07-31 2022-07-26 2022-08-21 2022-07-31 2022-09-25 2022-07-30 2024-03-25 onstruction ant Selection al RASTRUCTURE ERP-1 SX-NRPB-312698-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement Communications and Commu TF / A8079 Post 91,200.00 0.00 2022-08-31 2022-08-25 2022-10-19 2022-11-09 2022-12-14 2023-12-14 onstruction ant Selection l ation nity Outreach Consultant SX-NRPB-314853-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement Project Manager - St. Maarte TF / B5199 Post 270,000.00 0.00 2022-09-16 2022-09-20 2022-11-04 2022-11-25 2022-12-30 2024-06-30 onstruction ant Selection l ation n Wastewater Management P roject SX-NRPB-322083-CS-INDV / I Institutional Support for Rec Individual Consult Direct - Internation TF / B5199 Post 14,500.00 0.00 Signed 2022-10-21 2022-10-25 2022-10-31 2022-10-27 2022-11-21 2022-10-27 2022-12-26 2023-01-31 nterim Project coordinator W onstruction ant Selection al astewater SX-NRPB-325069-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation TF / B5199 Post 271,140.00 0.00 Signed 2022-11-15 2022-11-03 2022-11-25 2022-11-03 2022-12-16 2022-12-13 2023-01-20 2024-07-21 Head of Procurement - S.I onstruction ant Selection al SX-NRPB-326442-CS-INDV / J Institutional Support for Rec Individual Consult Pending Impleme TF / B5199 Post Open - National 90,000.00 0.00 2022-11-30 2023-01-18 2023-02-08 2023-03-15 2024-09-13 r. M&E Consultant onstruction ant Selection ntation SX-NRPB-326444-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Post 160,000.00 0.00 2022-11-28 2022-01-11 2022-12-08 2023-01-12 2022-12-29 2023-01-12 2023-01-16 2024-07-17 Program Advisor onstruction ant Selection al ation SX-NRPB-326641-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 260,000.00 0.00 2022-11-30 2023-01-11 2023-01-18 2023-02-08 2023-05-08 2024-11-06 Project Manager Housing onstruction ant Selection l ation SX-NRPB-333295-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 45,000.00 0.00 2022-12-23 2023-01-12 2023-02-10 2023-03-03 2023-04-07 2024-04-06 Financial Management Assist onstruction ant Selection l ation ant SX-NRPB-260433-CS-INDV / Institutional Support for Rec Individual Consult TF / A8079 Post Open 25,000.00 0.00 Canceled 2021-10-29 2021-12-17 2022-01-07 2022-02-11 2022-08-10 Sector Expert - Housing onstruction ant Selection SX-NRPB-342557-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 110,000.00 0.00 2023-02-17 2023-02-27 2023-04-07 2023-04-28 2023-06-02 2024-06-01 Project Officer ERP-1 onstruction ant Selection l ation SX-NRPB-342572-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa TF / B5199 Post 100,000.00 0.00 Canceled 2023-02-17 2023-02-27 2023-04-07 2023-04-28 2023-06-02 2024-06-01 Senior Advisor -Housing Proje onstruction ant Selection l ct SX-NRPB-347124-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Post 221,000.00 0.00 2023-03-05 2023-03-20 2023-03-15 2023-05-19 2023-04-05 2023-04-12 2023-05-10 2024-09-14 Coordinating Environmental onstruction ant Selection al ation Specialist SX-NRPB-347131-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 245,000.00 0.00 2023-03-05 2023-03-20 2023-04-23 2023-05-14 2023-06-18 2024-10-31 Social Specialist onstruction ant Selection l ation SX-NRPB-353790-CS-INDV / Institutional Support for Rec Individual Consult Under Implement TF / B5199 Post Direct - National 65,000.00 0.00 2023-04-05 2023-04-26 2023-04-15 2023-05-16 2023-05-06 2023-05-16 2023-06-10 2024-06-09 Executive Assistant Consulta onstruction ant Selection ation nt SX-NRPB-326436-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Post 165,000.00 0.00 2022-11-15 2023-05-23 2022-11-25 2022-12-16 2023-06-01 2024-12-31 Engineer ERP-1 - K.W onstruction ant Selection al ation SX-NRPB-363223-CS-INDV / Institutional Support for Rec Individual Consult TF / B5199 Post Direct - National 15,000.00 0.00 Under Review 2023-05-28 2023-05-23 2023-06-07 2023-06-28 2023-08-02 2023-10-02 Energy Specialist onstruction ant Selection SX-NRPB-364424-CS-INDV / Institutional Support for Rec Individual Consult Open - Internationa Under Implement TF / B5199 Post 100,000.00 0.00 2023-06-09 2023-05-31 2023-07-28 2023-08-18 2023-09-22 2024-09-21 Housing Sector Expert onstruction ant Selection l ation SX-NRPB-364743-CS-INDV / Institutional Support for Rec Individual Consult TF / B5199 Prior Direct - National 242,510.00 0.00 Signed 2023-06-01 2023-06-01 2023-06-11 2023-06-02 2023-07-02 2023-06-02 2023-08-06 2024-08-05 Procurement Consultant Ms. J onstruction ant Selection ackson II SX-NRPB-364744-CS-CDS / F Institutional Support for Rec Under Implement acilitator Performance Agree TF / B5199 Post Direct Selection Direct - National 60,000.00 0.00 2023-06-09 2023-06-22 2023-06-19 2023-06-19 2023-08-23 2024-05-22 onstruction ation ment Housing SX-NRPB-368036-CS-INDV / Institutional Support for Rec Individual Consult Direct - Internation Under Implement TF / B5199 Prior 153,900.00 0.00 2023-06-25 2023-06-22 2023-07-05 2023-06-13 2023-07-26 2023-06-26 2023-08-30 2024-08-29 Procurement Consultant Mr. onstruction ant Selection al ation Maculotti II Page 7 Summarized Procurement Plan I. GENERAL Project information: Borrower: CCARDESA Project Name: Agricultural Productivity Program for Southern Africa Project ID No: P164486 Grant No.: Project Implementing Agency: CCARDESA Bank’s approval Date of the Procurement Plan: February 13, 2019 Date of General Procurement Notice: Period covered by this procurement plan: February 13, 2019 to September 2020 II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in Appendix 1 to the Guidelines for Procurement: Thresholds for Procurement Methods and Prior Review Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ Prior millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 15 ≥7 < 0.2 ≤ 0.2 Goods, IT, and non- ≥6 ≥1 < 0.1 ≤ 0.1 consulting services 2. Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan also forms part of the Project Implementation Manual approved on May 2019. 1 3. Procurement Packages with Methods and Time Schedule Procurement of Goods & Non-consulting Services Summary 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of the ICB NIL NIL NIL NIL NIL (Works) Summary of the NCB NIL NIL NIL NIL NIL (Works) Summary of the ICB NIL NIL No NIL No major goods (Goods) Summary of the NCB NIL NIL NIL NIL NIL (Goods) Summary of the RfQ 0.03 6 No Post Request for (Goods & Non- Quotations Consulting Services) Summary of the DC 0.2million 2 No Post (Non-consulting services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines: Selection and Employment of Consultants: Thresholds for Consultants Selection Methods and Prior Review Thresholds for Consultants Selection Methods and Prior Review for Consulting Services Category Prior Short List of National Consultants (US$ million) 2 Review Consulting Engineering and (US$ Services Construction Supervision millions) Consultants (Firms) ≥4 ≤ 0.3 ≤ 0.3 Individual Consultants ≥ 0.5 NA. NA. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Guidelines: Selection and Employment of Consultants. 3. Terms of Reference (TOR) for all consultancy contracts as well as all single source selections, irrespective of the contract value, will be subject to prior review. 4. Any Other Special Selection Arrangements: N/A 5. Consultancy Assignments with Selection Methods and Time Procurement of Consulting Services Summary 1 2 3 4 5 6 Ref. No. Description of Estimated Package Review Comments Assignment Cost s by Bank (Prior / US$ million Post) Summary of NIL NIL NIL NIL contracts through CQS 3 Summary of 0.2 million 26 Post Individual Consultants (mostly contracts through peer reviewers) IC 4 PROCUREMENT Eastern and Southern Africa : Agricultural Productivity Program for Southern Africa - Angola & Lesotho PLAN General Information Country: Eastern and Southern Africa 2020-08-27 Bank’s Approval Date of the Original Procurement Plan: 2023-06-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164486 GPN Date: Project Name: Agricultural Productivity Program for Southern Africa - Angola & Lesotho Loan / Credit No: IBRD / 89170 Agronomic Research Institute Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - AO-IIA-188294-CW-RFP / Ref Strengthening the Institution Single Stage - One E Small Works SPD 2023-11-0 urbishment of the PIU Office IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 200,000.00 0.00 Canceled 2023-01-17 2023-01-22 2023-03-05 2023-04-04 2023-05-09 nvelope (1 envelope proce 5 and three premises in Chiang for Technology Adoption ss) a - Huambo Request for Bids - APPSA/W-001 / Construction Strengthening the Institution Open - Internationa Single Stage - One E Works (without pr Under Imple 2023-11-2 Works of the Cassava Region IBRD / 89170 al and Enabling Environment Post Request for Bids 5,000,000.00 0.00 2023-03-10 2023-04-19 2023-03-15 2023-04-25 2023-04-26 2023-04-27 2023-06-01 l nvelope equalification) SP mentation 8 al Leadership Center in Mala for Technology Adoption D nje. APPSA/W-002 / Fencing at th Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Under Imple 2023-10-1 e Agricultural Experimental S IBRD / 89170 al and Enabling Environment Post Limited 100,000.00 0.00 2023-02-25 2023-05-30 2023-04-22 tions nvelope or explanation) mentation 9 tations of Malanje for Technology Adoption APPSA/W-003 / Fencing at th Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Under Imple 2023-10-2 e Agricultural Experimental S IBRD / 89170 al and Enabling Environment Post Limited 70,000.00 0.00 2023-03-04 2023-05-30 2023-04-29 tions nvelope or explanation) mentation 6 tations of Chianga (Huambo) for Technology Adoption APPSA/W-005 / Fencing at th Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Under Imple 2023-10-2 e Agricultural Experimental S IBRD / 89170 al and Enabling Environment Post Limited 70,000.00 0.00 2023-03-01 2023-05-30 2023-04-26 tions nvelope or explanation) mentation 3 tations of Namibe for Technology Adoption Request for Bids - APPSA/W-006 / Rehabilitatio Strengthening the Institution Single Stage - One E Small Works SPD Under Imple 2023-12-1 n of the Malanje Agricultural IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 200,000.00 0.00 2023-02-28 2023-04-24 2023-03-05 2023-05-03 2023-04-16 2023-05-16 2023-06-20 nvelope (1 envelope proce mentation 7 Experimental Station for Technology Adoption ss) APPSA/W-008 / Construction Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-10-3 of a Warehouse at the Tomb IBRD / 89170 al and Enabling Environment Post Limited 15,000.00 0.00 2023-03-08 2023-05-03 tions nvelope or explanation) lementation 0 oco Agricultural Experimental for Technology Adoption Field (Zaire) APPSA/W-010 / Rehabilitatio Request for Bids - Strengthening the Institution n of three (3) Buildings of the Single Stage - One E Small Works SPD Under Imple 2023-12-2 IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 400,000.00 0.00 2023-03-06 2023-04-25 2023-03-11 2023-05-03 2023-04-22 2023-05-22 2023-06-26 Chianga (Huambo) and Buildi nvelope (1 envelope proce mentation 3 for Technology Adoption ng in Largo Cussy ss) APPSA/W-004 / Fencing at th Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-2 e Agricultural Experimental S IBRD / 89170 al and Enabling Environment Post Limited 40,000.00 0.00 2023-05-01 2023-06-26 tions nvelope or explanation) mentation 3 tations of Mazozo (Luanda) for Technology Adoption APPSA/W-007 / Rehabilitatio Strengthening the Institution n of the Tissue Culture Labor Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-12-2 IBRD / 89170 al and Enabling Environment Post Limited 50,000.00 0.00 2023-05-03 2023-06-28 atory at the Mazozo Agricultu tions nvelope or explanation) lementation 5 for Technology Adoption ral Experimental Station APPSA/W-009 / Construction Strengthening the Institution Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-12-2 of a Warehouse at the Ceilun IBRD / 89170 al and Enabling Environment Post Limited 15,000.00 0.00 2023-05-05 2023-06-30 tions nvelope or explanation) lementation 7 ga Agricultural Experimental for Technology Adoption Field (Bié) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-IIA-188196-GO-RFQ / Offi Technology Generation and Request for Quota Single Stage - One E ce supplies for R&D projects IBRD / 89170 Post Limited 30,000.00 0.00 Canceled 2020-10-11 2020-12-06 2021-06-04 Dissemination tions nvelope and PIU office AO-IIA-193891-GO-RFQ / Pur Strengthening the Institution chase ot three vehicles stati Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Limited 120,000.00 174,219.91 Completed 2020-11-08 2021-02-19 2021-01-03 2021-04-01 2021-07-02 2021-10-30 on wagon 13 seats for Experi tions nvelope for Technology Adoption mental Fields of Luso, Ceilun ga and Zaire AO-IIA-193765-GO-RFB / Pur Strengthening the Institution Single Stage - One E chase of tractors and implem IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 400,000.00 0.00 Canceled 2021-01-10 2021-01-15 2021-02-26 2021-03-28 2021-05-02 2021-10-29 nvelope ents for Malanje and Huambo for Technology Adoption (Chianga) AO-IIA-188275-GO-RFQ / Thr Strengthening the Institution Request for Quota Single Stage - One E ee sets video conference equ IBRD / 89170 al and Enabling Environment Post Limited 30,000.00 0.00 Canceled 2020-11-08 2021-01-03 2021-07-02 tions nvelope ipment for Technology Adoption AO-IIA-221338-GO-RFQ / Veh Project management, monit Request for Quota Single Stage - One E icles to Support the monitori IBRD / 89170 oring and evaluation, and re Post Limited 200,000.00 281,067.85 Completed 2021-03-09 2021-06-11 2021-05-04 2021-10-01 2021-10-31 2022-02-26 tions nvelope ng Missions gional coordination Strengthening the Institution AO-IIA-187417-GO-RFB / Pur Single Stage - One E IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 880,000.00 0.00 Canceled 2020-09-21 2020-09-26 2020-11-07 2020-12-07 2021-01-11 2021-07-10 chase of vehicles nvelope for Technology Adoption Strengthening the Institution AO-IIA-188183-GO-RFQ / Pur Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Limited 15,000.00 0.00 Canceled 2021-05-09 2021-07-04 2021-12-31 chase of 10 motorbikes tions nvelope for Technology Adoption Strengthening the Institution APPSA/G-013 / Procurement IBRD / 89170 al and Enabling Environment Post Direct Selection Direct 25,000.00 81,865.99 Signed 2022-01-10 2022-01-26 2022-01-15 2022-01-31 2022-02-19 2022-02-18 2022-08-18 of Motorbikes for Technology Adoption Strengthening the Institution APPSA/G-014 / Procurement IBRD / 89170 al and Enabling Environment Post Direct Selection Direct 500,000.00 535,515.88 Signed 2022-01-10 2021-12-10 2022-01-15 2022-02-07 2022-02-19 2022-03-15 2022-08-18 Tractors and Implements for Technology Adoption Page 1 APPSA/G-015 / Procurement Strengthening the Institution of Vehicles for PIU, IIA Resear IBRD / 89170 al and Enabling Environment Post Direct Selection Direct 750,000.00 804,217.70 Signed 2022-01-11 2022-01-05 2022-01-16 2022-02-07 2022-02-20 2022-03-05 2022-08-19 ch Programmes and Stations for Technology Adoption Project management, monit APPSA/G-016 / License Softw IBRD / 89170 oring and evaluation, and re Post Direct Selection Direct 30,000.00 16,459.31 Signed 2022-01-16 2022-01-26 2022-01-21 2022-01-26 2022-02-25 2022-02-01 2022-08-24 are Accounting TOMPRO gional coordination AO-IIA-188898-GO-RFQ / Aut Technology Generation and Request for Quota Single Stage - One E Under Imple omatic Weather Stations for IBRD / 89170 Post Limited 97,000.00 0.00 2021-01-17 2021-03-14 2021-09-10 Dissemination tions nvelope mentation Research and Field Stations APPSA/G-017 / IT Equipment Strengthening the Institution Single Stage - One E Under Imple for UIP and Subprojects Supp IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 300,000.00 0.00 2022-05-31 2022-05-26 2022-06-05 2022-05-27 2022-07-17 2022-07-08 2022-08-16 2022-09-20 2023-03-19 nvelope mentation ort for Technology Adoption AO-IIA-188210-GO-RFQ / Lab oratory supplies (essencial e Technology Generation and Request for Quota Single Stage - One E IBRD / 89170 Post Limited 70,000.00 0.00 Canceled 2021-01-15 2021-03-12 2021-09-08 quipment, reagens and other Dissemination tions nvelope lab consumables) APPSA/G-021 / Procurement Strengthening the Institution Single Stage - One E of 6 Vehicles to Intensify the IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 500,000.00 0.00 Signed 2022-06-26 2022-07-18 2022-07-01 2022-07-27 2022-08-12 2022-08-31 2022-09-11 2022-09-05 2022-10-16 2023-04-14 nvelope Activities of the Research Su for Technology Adoption b-projects Fields APPSA/G-022 / Procurement Strengthening the Institution Request for Quota Single Stage - One E of 15 Motorbikes and Access IBRD / 89170 al and Enabling Environment Post Open - National 150,000.00 0.00 Signed 2022-07-19 2022-06-23 2022-09-13 2023-03-12 tions nvelope ories for Technology Adoption Strengthening the Institution APPSA/G-025 / Procurement Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Limited 80,000.00 0.00 Signed 2022-08-01 2022-08-25 2022-09-26 2023-03-25 1 Vehicle for Supporting UIP tions nvelope for Technology Adoption Strengthening the Institution APPSA/G-023 / Procurement Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Open - National 150,000.00 0.00 Signed 2022-09-10 2022-10-13 2023-04-11 of 3 Tractors tions nvelope for Technology Adoption AO-IIA-187401-GO-RFQ / Pur Technology Generation and Single Stage - One E IBRD / 89170 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2021-01-18 2021-01-23 2021-03-06 2021-04-05 2021-05-10 2021-11-06 chase of IT equipments for R Dissemination nvelope &D Projects APPSA/G-032 / Procurement Technology Generation and Request for Quota Open - Internationa Single Stage - One E Under Imple IBRD / 89170 Post 100,000.00 0.00 2022-12-10 2023-04-01 2023-02-04 2023-08-03 of Laboratorial Reagents Dissemination tions l nvelope mentation Strengthening the Institution APPSA/G-018 / Procurement Single Stage - One E Under Imple IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 250,000.00 0.00 2023-01-15 2023-03-20 2023-01-20 2023-04-07 2023-03-03 2023-04-02 2023-05-07 2023-11-03 of Tractors and Implements I nvelope mentation for Technology Adoption APPSA/G-034 / Procurement Strengthening the Institution Request for Quota Single Stage - One E of Reagents, Equipment and IBRD / 89170 al and Enabling Environment Post Limited 120,000.00 0.00 Canceled 2022-11-05 2022-12-15 2023-06-13 tions nvelope other Laboratorial Consumab for Technology Adoption les I APPSA/G-033 / Procurement Strengthening the Institution Request for Quota Single Stage - One E Pending Impl of Irrigation System for Agric IBRD / 89170 al and Enabling Environment Post Limited 120,000.00 0.00 2023-01-22 2023-03-03 2023-08-30 tions nvelope ementation ultural Experimental Stations for Technology Adoption I APPSA/G-020 / Procurement Technology Generation and Request for Quota Open - Internationa Single Stage - One E Under Imple of Laboratory Equipment and IBRD / 89170 Post 150,000.00 0.00 2023-03-05 2023-04-01 2023-04-30 2023-10-27 Dissemination tions l nvelope mentation Consumables APPSA/G-26 / Lightning prot Strengthening the Institution ection equipment for UIP offi Request for Quota Single Stage - One E IBRD / 89170 al and Enabling Environment Post Limited 80,000.00 0.00 Canceled 2023-01-02 2023-02-27 2023-08-26 ces and Chianga Agricultural tions nvelope for Technology Adoption Experiment Station - Huambo APPSA/G-019 / Procurement Strengthening the Institution Request for Quota Single Stage - One E Pending Impl of 10 Freezers for the Conser IBRD / 89170 al and Enabling Environment Post Open - National 100,000.00 0.00 2023-08-05 2023-09-30 2024-03-28 tions nvelope ementation vation of Genetic Agricultural for Technology Adoption Material AO-IIA-193893-GO-RFQ / Pro Strengthening the Institution Single Stage - One E Pending Impl curement of Irrigation Syste IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 260,000.00 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 nvelope ementation m for Agricultural Experimen for Technology Adoption tal Stations AO-IIA-187641-GO-RFB / Pro Strengthening the Institution curement of Equipment and Single Stage - One E Pending Impl IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 400,000.00 0.00 2023-06-30 2023-07-05 2023-08-16 2023-09-15 2023-10-20 2024-04-17 Furniture for the Cassava Re nvelope ementation for Technology Adoption gional Leadership Center APPSA/G-027 / Procurement of 2 Refrigeration Chambers f Strengthening the Institution Request for Quota Single Stage - One E Pending Impl or Legume Seeds for the Agri IBRD / 89170 al and Enabling Environment Post Limited 110,000.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation cultural Experimental Station for Technology Adoption s of Mazozo and Chianga APPSA/G-043 / Procurement Technology Generation and Request for Quota Single Stage - One E Pending Impl IBRD / 89170 Post Limited 100,000.00 0.00 2023-07-01 2023-08-26 2024-02-22 of Fertilizer for Agricultural C Dissemination tions nvelope ementation ampaign APPSA/G-042 / Automatic W Technology Generation and Request for Quota Single Stage - One E Pending Impl IBRD / 89170 Post Limited 120,000.00 0.00 2023-07-04 2023-08-29 2024-02-25 eather Stations Dissemination tions nvelope ementation APPSA/G-045 / Procurement Technology Generation and Direct - Internation Under Imple 4 vehicles for High-Level Inte IBRD / 89170 Post Direct Selection 200,000.00 0.00 2023-06-29 2023-06-28 2023-07-04 2023-08-08 2024-02-04 Dissemination al mentation r-Ministerial missions to verif y Project Actions APPSA/G-044 / Procurement of 17 Generators for the Cass Technology Generation and Direct - Internation Pending Impl IBRD / 89170 Post Direct Selection 220,000.00 0.00 2023-06-29 2023-07-04 2023-08-08 2024-02-04 ava Regional Leadership Cen Dissemination al ementation ter and Agricultural Experime ntal Stations APPSA/G-041 / Procurement Technology Generation and Request for Quota Single Stage - One E Pending Impl of Solar Energy Equipment fo IBRD / 89170 Post Limited 115,000.00 0.00 2023-07-04 2023-08-29 2024-02-25 Dissemination tions nvelope ementation r Subproject NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 APPSA/S-002 / Repair Servic Strengthening the Institution Single Stage - One E es and Supply of Parts of Tra IBRD / 89170 al and Enabling Environment Post Request for Bids Open - National 300,000.00 0.00 Canceled 2022-06-30 2022-07-05 2022-08-16 2022-09-15 2022-10-20 2023-04-18 nvelope ctors for Experimental Agricu for Technology Adoption ltural Stations APPSA/S-003 / Website Desi Strengthening the Institution Request for Quota Single Stage - One E Pending Impl gn, Development and Manag IBRD / 89170 al and Enabling Environment Post Open - National 20,000.00 0.00 2022-12-27 2023-02-21 2023-08-20 tions nvelope ementation ement Services for the IIA an for Technology Adoption d APPSA APPSA/S-001 / Repair Servic Strengthening the Institution e and Supply of Parts for IIA IBRD / 89170 al and Enabling Environment Post Direct Selection Direct 300,000.00 0.00 Canceled 2022-05-26 2022-05-27 2022-05-31 2022-07-05 2023-01-01 Vehicles Within the scope of for Technology Adoption APPSA CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-IIA-259173-CS-QCBS / Pr Strengthening the Institution oject Design and Supervision Quality And Cost- Open - Internationa IBRD / 89170 al and Enabling Environment Post 540,000.00 0.00 Signed 2021-10-29 2022-01-21 2021-11-19 2022-04-18 2022-01-02 2022-06-13 2022-01-30 2022-07-22 2022-03-01 2022-06-29 2022-04-05 2022-08-16 2022-05-10 2023-05-10 of the Supervision of the Cas Based Selection l for Technology Adoption sava Regional Leadership Ce nter AO-IIA-267731-CS-QCBS / As Project management, monit Quality And Cost- sessment the Agriculture Res IBRD / 89170 oring and evaluation, and re Post Open - National 180,000.00 99,929.00 Signed 2021-12-19 2022-01-10 2022-01-09 2022-01-20 2022-02-22 2022-04-14 2022-03-22 2022-05-30 2022-04-21 2022-06-03 2022-05-26 2022-06-06 2022-06-30 2022-07-31 2023-06-30 Based Selection earch Baseline gional coordination Project management, monit APPSA/C-028 / External Audi Least Cost Selecti Open - Internationa Under Implement IBRD / 89170 oring and evaluation, and re Post 200,000.00 0.00 2022-01-13 2022-02-02 2022-02-03 2022-03-04 2022-03-19 2022-07-15 2022-04-16 2022-08-31 2022-05-16 2022-06-20 2022-07-25 2023-01-21 t on l ation gional coordination AO-IIA-188277-CS-INDV / Ra pid rual survey for assement of conditions to stregthen the Technology Generation and Consultant Qualifi the basic seed and vegetativ IBRD / 89170 Post Limited 60,000.00 0.00 Canceled 2022-09-01 2022-09-15 2022-10-15 2022-11-19 2023-05-18 Dissemination cation Selection e propagation materials fram ework under coordination of Chianga Research Station in the Central Plateau of Angola APPSA/C-023 / Consultancy f or the Development of Enviro Strengthening the Institution Consultant Qualifi nmental Impact Studies for t IBRD / 89170 al and Enabling Environment Post Open - National 100,000.00 0.00 Canceled 2022-06-20 2022-06-16 2022-07-11 2022-08-04 2022-09-03 2022-10-08 2023-04-06 cation Selection he Construction Work of the for Technology Adoption Cassava Regional Leadership Center - Malanje INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AO-IIA-187655-CS-INDV / Re Project management, monit Individual Consult cruitment of Procurement Sp IBRD / 89170 oring and evaluation, and re Prior Open 84,000.00 0.00 Canceled 2020-09-01 2021-01-15 2020-10-20 2021-07-16 2020-11-10 2020-12-15 2021-06-13 ant Selection ecialist gional coordination AO-IIA-187660-CS-INDV / Re Project management, monit Individual Consult cruitment of safeguards spec IBRD / 89170 oring and evaluation, and re Post Open 72,000.00 0.00 Canceled 2020-09-01 2020-10-09 2020-10-20 2021-07-01 2020-11-10 2021-07-09 2020-12-15 2021-06-13 ant Selection ialist gional coordination AO-IIA-187659-CS-INDV / Re Project management, monit Individual Consult cruitment of communication IBRD / 89170 oring and evaluation, and re Post Open 72,000.00 86,205.35 Signed 2020-09-01 2021-02-12 2020-10-20 2021-09-30 2020-11-10 2021-10-01 2020-12-15 2021-10-19 2021-06-13 ant Selection and information specialst gional coordination AO-IIA-187657-CS-INDV / Re Project management, monit Individual Consult cruitment of monitoring and IBRD / 89170 oring and evaluation, and re Post Open 84,000.00 111,873.80 Signed 2020-09-01 2020-10-09 2020-10-20 2021-04-28 2020-11-10 2021-05-24 2020-12-15 2021-06-08 2021-06-13 ant Selection evaluation specialist gional coordination AO-IIA-187647-CS-INDV / Re Project management, monit Individual Consult cruitment of the project coor IBRD / 89170 oring and evaluation, and re Post Open 96,000.00 0.00 Canceled 2020-09-01 2020-09-17 2020-10-20 2020-11-10 2020-12-15 2021-06-13 ant Selection dinator gional coordination Project management, monit AO-IIA-221339-CS-INDV / So Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 72,500.00 97,039.57 Signed 2021-03-10 2021-09-21 2021-04-28 2021-11-08 2021-05-19 2021-11-09 2021-06-23 2021-11-11 2021-12-20 cial Safeguards Specialist ant Selection gional coordination Project management, monit AO-IIA-187662-CS-INDV / Re Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 36,000.00 0.00 Canceled 2020-09-01 2020-10-09 2020-10-20 2020-11-10 2020-12-15 2021-06-13 cruitment of an accountant ant Selection gional coordination AO-IIA-187652-CS-INDV / Re Project management, monit Individual Consult cruitment of financial manag IBRD / 89170 oring and evaluation, and re Post Open 84,000.00 0.00 Canceled 2020-09-01 2020-10-09 2020-10-20 2020-11-10 2020-12-15 2021-06-13 ant Selection er gional coordination AO-IIA-239079-CS-INDV / Fin Project management, monit Individual Consult ancial Management Specialis IBRD / 89170 oring and evaluation, and re Post Open 140,000.00 150,376.47 Signed 2021-07-22 2021-07-27 2021-09-09 2021-09-27 2021-09-30 2021-09-29 2021-11-04 2021-10-09 2022-05-03 ant Selection t gional coordination Project management, monit AO-IIA-239084-CS-INDV / Ac Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 72,000.00 64,954.01 Signed 2021-07-22 2021-07-27 2021-09-09 2021-10-14 2021-09-30 2021-10-20 2021-11-04 2021-10-26 2022-05-03 countant ant Selection gional coordination Project management, monit AO-IIA-252339-CS-INDV / IT Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 45,000.00 33,285.56 Signed 2021-09-13 2021-10-05 2021-11-01 2022-02-08 2021-11-22 2022-03-24 2021-12-27 2022-04-27 2022-06-25 Specialist ant Selection gional coordination Project management, monit AO-IIA-252343-CS-INDV / Infr Individual Consult IBRD / 89170 oring and evaluation, and re Post Limited 74,000.00 34,485.56 Signed 2021-09-13 2021-10-21 2021-09-18 2022-01-14 2021-10-09 2022-03-24 2021-11-13 2022-04-27 2022-05-12 astructure Specialist ant Selection gional coordination AO-IIA-252344-CS-INDV / En Project management, monit Individual Consult vironmental Safeguards Spec IBRD / 89170 oring and evaluation, and re Post Open 74,000.00 98,039.57 Signed 2021-09-13 2021-09-29 2021-11-01 2021-07-01 2021-11-22 2021-10-19 2021-12-27 2021-10-21 2022-06-25 ant Selection ialist gional coordination AO-IIA-244838-CS-INDV / Fin Project management, monit Individual Consult ancial Management Consulta IBRD / 89170 oring and evaluation, and re Post Direct 60,000.00 0.00 Canceled 2021-07-23 2021-07-22 2021-08-02 2021-08-03 2021-08-23 2021-09-27 2022-03-26 ant Selection nt gional coordination Page 3 AO-IIA-252345-CS-INDV / Co nsultancy for Water Resource Strengthening the Institution Individual Consult s Assessment, Irrigation Cap IBRD / 89170 al and Enabling Environment Post Limited 60,000.00 0.00 Canceled 2021-09-27 2021-10-05 2021-10-02 2022-03-24 2021-10-23 2021-11-27 2022-05-26 ant Selection acity Review and Water Man for Technology Adoption agement Systems Proposals Project management, monit AO-IIA-254446-CS-INDV / Pro Individual Consult IBRD / 89170 oring and evaluation, and re Prior Open 176,000.00 156,793.58 Signed 2021-09-23 2021-10-12 2021-11-11 2021-12-02 2021-12-02 2021-12-08 2022-01-06 2021-12-20 2022-07-05 curement Specialist ant Selection gional coordination AO-IIA-218571-CS-INDV / Stu Strengthening the Institution Individual Consult dies on small scale irrigation IBRD / 89170 al and Enabling Environment Post Open 30,000.00 0.00 Canceled 2022-03-14 2022-05-02 2022-05-23 2022-06-27 2022-12-24 ant Selection schemes in Central Plateau o for Technology Adoption f Angola AO-IIA-188476-CS-INDV / Re Strengthening the Institution cruitment of a consultant for Individual Consult IBRD / 89170 al and Enabling Environment Post Limited 20,000.00 0.00 Canceled 2020-11-02 2020-11-06 2020-11-27 2021-01-01 2021-06-30 budget preparation and supe ant Selection for Technology Adoption rvision of rehabilitation works in Chianga RS Project management, monit AO-IIA-221336-CS-INDV / Pro Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 100,000.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2023-01-10 ject Manager ant Selection gional coordination Project management, monit APPSA/C-029 / Procurement Individual Consult Under Implement IBRD / 89170 oring and evaluation, and re Prior Open 72,000.00 0.00 2022-01-14 2022-02-24 2022-03-04 2022-03-25 2022-04-29 2022-10-26 Assistant ant Selection ation gional coordination Project management, monit APPSA/C-030 / Financial Assi Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 72,000.00 0.00 Signed 2022-01-14 2022-02-02 2022-03-04 2022-07-25 2022-03-25 2022-09-20 2022-04-29 2022-10-26 stant ant Selection gional coordination AO-IIA-193690-CS-INDV / Ass Strengthening the Institution Individual Consult essment the agriculture rese IBRD / 89170 al and Enabling Environment Post Open 50,000.00 0.00 Canceled 2020-11-03 2021-07-12 2020-12-22 2021-01-12 2021-02-16 2021-08-15 ant Selection ardh baseline for Technology Adoption AO-IIA-188286-CS-INDV / Ass Strengthening the Institution Individual Consult ess and design the IIA resear IBRD / 89170 al and Enabling Environment Post Open 45,000.00 0.00 Canceled 2022-06-30 2022-08-18 2022-09-08 2022-10-13 2023-04-11 ant Selection ch network investment for Technology Adoption APPSA/C-032 / Consultant fo Project management, monit Individual Consult Under Implement r Supporting the Installation, IBRD / 89170 oring and evaluation, and re Post Open 80,000.00 0.00 2022-05-13 2022-05-16 2022-07-01 2023-01-20 2022-07-22 2022-08-26 2023-02-22 ant Selection ation Operation and, Management gional coordination of DHIS2 Project management, monit APPSA/C-022 / Monitoring an Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 120,000.00 0.00 Signed 2022-06-13 2022-06-03 2022-08-01 2022-10-04 2022-08-22 2022-10-31 2022-09-26 2023-03-25 d Evaluation Specialist ant Selection gional coordination AO-IIA-188291-CS-INDV / Stu Strengthening the Institution Individual Consult dies on cassava value chain i IBRD / 89170 al and Enabling Environment Post Open 30,000.00 0.00 Canceled 2022-07-19 2022-09-06 2022-09-27 2022-11-01 2023-04-30 ant Selection n Angola for Technology Adoption Project management, monit AO-IIA-221337-CS-INDV / Ca Individual Consult IBRD / 89170 oring and evaluation, and re Post Open 80,000.00 0.00 Canceled 2022-05-31 2022-07-19 2022-08-09 2022-09-13 2023-03-12 ssava Consultant Specialist ant Selection gional coordination Project management, monit APPSA/C-025 / Procurement Individual Consult Under Implement IBRD / 89170 oring and evaluation, and re Prior Open - National 30,000.00 0.00 2022-11-03 2023-02-06 2022-12-22 2023-01-12 2023-02-16 2023-08-15 Assistant ant Selection ation gional coordination Project management, monit APPSA/IC-20 / Financial Man Individual Consult Under Implement IBRD / 89170 oring and evaluation, and re Post Open - National 140,000.00 0.00 2023-05-02 2023-05-02 2023-06-20 2023-07-11 2023-08-15 2024-02-11 agement Specialist I ant Selection ation gional coordination Project management, monit Individual Consult APPSA/C-027 / Internal Audit IBRD / 89170 oring and evaluation, and re Post Open 70,000.00 0.00 Canceled 2022-01-12 2022-04-19 2022-03-02 2022-03-23 2022-04-27 2022-10-24 ant Selection gional coordination Page 4 PROCUREMENT PLAN (Textual Part) Project information: Nigeria [SPESSE ][P169405] Project Implementation agency: National University Commission Date of the Procurement Plan: August 9, 2019 Period covered by this Procurement Plan: [August 9, 2019 – Jan 31, 2019] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Nigeria 2017 Procurement Act, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. None When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Goods: is not applicable Works: is not applicable Other Relevant Procurement Information. None PROCUREMENT Nigeria : Sustainable Procurement, Environmental and Social Standards Enhancement Project (SPESSE) PLAN General Information Country: Nigeria 2020-05-15 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169405 GPN Date: Project Name: Sustainable Procurement, Environmental and Social Standards Enhancement Project (SPESSE) Loan / Credit No: IDA / V2820 Federal Ministries of Women Affairs, Labour, Works and Housing Node Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 2020-05-1 934-CW-RFQ / Partitioning of IDA / V2820 stance and Support to imple Post Limited 10,000.00 0.00 Canceled 2020-03-15 2020-04-21 tions nvelope 2 Offices menting agencies NG-FMWA LAB &WORKS-239 Component I: Technical assi Request for Quota Request for Quota Single Stage - One E 2022-05-1 731-CW-RFQ / Maintenance o IDA / V2820 stance and Support to imple Post Limited tions (Non Bank-S 16,000.00 0.00 Canceled 2021-09-20 2021-11-15 tions nvelope 4 f office building. menting agencies PD) NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Request for Quota Single Stage - One E 2022-03-0 934-CW-RFQ-2 / Partitioning IDA / V2820 stance and Support to imple Post Limited tions (Non Bank-S 10,000.00 9,779.38 Completed 2022-01-09 2022-01-06 2022-02-15 2022-02-11 tions nvelope 8 of Offices menting agencies PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 880-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 25,000.00 24,088.82 Completed 2021-08-15 2021-12-15 2021-09-21 2022-01-29 2021-10-05 2022-03-03 tions nvelope f Office Furniture menting agencies NG-FMWA LAB &WORKS-239 Component I: Technical assi Request for Quota Single Stage - One E Pending Impl 639-GO-RFQ / Printing of Fina IDA / V2820 stance and Support to imple Post Limited 1,223.03 0.00 2021-08-30 2021-10-25 2022-04-23 tions nvelope ementation ncial documents menting agencies NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 897-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 8,450.00 8,278.82 Completed 2021-08-15 2021-12-15 2021-09-21 2022-02-09 2021-10-05 2022-04-14 tions nvelope f Inverters menting agencies NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 898-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 87,611.85 84,922.44 Signed 2021-08-15 2021-12-15 2021-09-21 2022-02-11 2021-10-12 tions nvelope f Project Vehicle, Registration menting agencies and Insurance NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 935-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 9,750.00 9,051.27 Completed 2021-08-15 2021-12-15 2021-09-21 2022-02-09 2021-10-12 2022-04-14 tions nvelope f Window Blinds & Internal D menting agencies ecorations NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E Pending Impl 895-GO-RFQ / NgREN Subscri IDA / V2820 stance and Support to imple Post Limited 120,000.00 0.00 2021-08-14 2021-09-20 2021-10-04 tions nvelope ementation ption and Equipment menting agencies NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 886-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 29,078.95 28,264.58 Completed 2021-08-20 2021-12-15 2021-09-26 2022-02-07 2021-10-10 2022-03-23 tions nvelope f Computers and Printers menting agencies NG-FMWA LAB &WORKS-164 Component I: Technical assi 007-GO-RFQ / Procurement o Request for Quota Single Stage - One E Under Imple IDA / V2820 stance and Support to imple Post Limited 34,750.00 0.00 2021-08-18 2021-12-15 2021-10-13 2022-04-11 f Sound Proof Diesel Generat tions nvelope mentation menting agencies or and its maintenance NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota 896-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post 15,000.00 0.00 Canceled 2020-03-10 2020-03-10 2020-03-10 tions f Video Conference Device menting agencies NG-FMWA LAB &WORKS-246 Component I: Technical assi Request for Quota Single Stage - One E 371-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 29,157.34 26,459.41 Completed 2021-09-18 2021-12-15 2021-10-09 2022-01-27 2021-10-23 2022-02-26 tions nvelope f Office Equipment menting agencies NG-FMWA LAB &WORKS-239 Component I: Technical assi Request for Quota Single Stage - One E 636-GO-RFQ / Office Accomm IDA / V2820 stance and Support to imple Post Limited 43,421.04 0.00 Canceled 2021-09-18 2021-11-13 2022-05-12 tions nvelope odation Rent (3 Years). menting agencies NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 896-GO-RFQ-2 / Procurement IDA / V2820 stance and Support to imple Post Limited 15,000.00 14,653.88 Completed 2022-01-09 2022-01-14 2022-03-06 2022-02-22 2022-09-02 2022-03-17 tions nvelope of Video Conference Device menting agencies NG-FMWA LAB &WORKS-163 Component I: Technical assi Under Imple 931-GO-DIR / Procurement of IDA / V2820 stance and Support to imple Post Direct Selection Direct 12,000.00 0.00 2022-03-07 2022-03-29 2022-03-12 2022-03-28 2022-04-18 mentation Accounting Software menting agencies NG-FMWA LAB &WORKS-361 Component I: Technical assi Request for Quota Single Stage - One E Pending Impl 426-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 32,000.00 0.00 2023-05-20 2023-06-26 2023-07-10 tions nvelope ementation f Local Area Network (LAN) menting agencies NG-FMWA LAB &WORKS-361 Component I: Technical assi Request for Quota Single Stage - One E Pending Impl 427-GO-RFQ / Procurement o IDA / V2820 stance and Support to imple Post Limited 35,000.00 0.00 2023-05-20 2023-06-26 2023-07-10 tions nvelope ementation f I.T. Tools menting agencies NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 916-NC-RFQ / Engagement of IDA / V2820 stance and Support to imple Post Limited 15,000.00 14,249.58 Signed 2021-08-14 2022-02-07 2021-09-20 2022-02-22 2022-09-19 tions nvelope Security Services firm menting agencies Page 1 NG-FMWA LAB &WORKS-163 Component I: Technical assi Request for Quota Single Stage - One E 928-NC-RFQ / Engagement of IDA / V2820 stance and Support to imple Post Limited 12,000.00 11,774.79 Signed 2021-08-17 2022-02-07 2021-09-23 2022-02-22 2022-09-22 tions nvelope Cleaning Services firm menting agencies CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMWA LAB &WORKS-281 956-CS-CQS / Engagement of Component I: Technical assi Consultant Qualifi Under Implement consultancy firm for the Dev IDA / V2820 stance and Support to imple Post Limited 100,000.00 0.00 2022-03-09 2023-02-22 2022-03-23 2022-04-22 2022-05-11 2022-11-07 cation Selection ation elopment of Professional pro menting agencies grammes for online certificati on NG-FMWA LAB &WORKS-281 933-CS-CQS / Engagement of Component I: Technical assi Consultant Qualifi consultancy firm to Develop IDA / V2820 stance and Support to imple Post Limited 80,000.00 0.00 Canceled 2022-03-09 2022-12-28 2022-03-23 2022-04-22 2022-05-11 2022-11-07 cation Selection Local Training content for S. menting agencies D., Labour & resettlement Se ctors in Nigeria NG-FMWA LAB &WORKS-344 247-CS-CQS / Engagement of Component I: Technical assi Consultant Qualifi consultancy firm to Develop IDA / V2820 stance and Support to imple Post Limited 80,000.00 0.00 Under Review 2023-02-27 2023-06-14 2023-03-13 2023-04-02 2023-04-21 2023-10-18 cation Selection Local Training content for S. menting agencies D., Labour & resettlement Se ctors in Nigeria NG-FMWA LAB &WORKS-364 465-CS-CQS / Engagement of Component I: Technical assi Consultant Qualifi Under Implement a consultancy firm for the De IDA / V2820 stance and Support to imple Post Limited 280,000.00 0.00 2023-05-31 2023-02-22 2023-06-14 2023-07-14 2023-08-02 2024-01-29 cation Selection ation velopment of Professional pr menting agencies ogrammes for the online cert ification portal INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FMWA LAB &WORKS-239 Component I: Technical assi Individual Consult 728-CS-INDV / Engagement o IDA / V2820 stance and Support to imple Post Limited 15,789.47 0.00 Signed 2021-09-14 2023-02-22 2021-09-19 2023-02-23 2021-10-10 2023-03-13 2021-11-14 2022-05-13 ant Selection f an ICT/LMS Specialist menting agencies NG-FMWA LAB &WORKS-357 Component I: Technical assi Individual Consult Under Implement 708-CS-INDV / Engagement o IDA / V2820 stance and Support to imple Post Limited 52,182.99 0.00 2023-04-19 2023-02-22 2023-04-24 2023-05-15 2023-06-19 2023-12-16 ant Selection ation f an ICT/LMS Specialist menting agencies NG-FMWA LAB &WORKS-361 Component I: Technical assi Individual Consult Pending Impleme 424-CS-INDV / Engagement o IDA / V2820 stance and Support to imple Post Limited 50,000.00 0.00 2023-05-15 2023-05-20 2023-06-10 2023-07-15 2024-07-09 ant Selection ntation f Certification Manager menting agencies NG-FMWA LAB &WORKS-361 Component I: Technical assi Individual Consult Pending Impleme 425-CS-INDV / Engagement o IDA / V2820 stance and Support to imple Post Limited 7,500.00 0.00 2023-05-15 2023-05-20 2023-06-10 2023-07-15 2023-10-13 ant Selection ntation f Strategy Document Consult menting agencies ant. NG-FMWA LAB &WORKS-362 Component I: Technical assi Individual Consult Under Implement 050-CS-INDV / Engagement o IDA / V2820 stance and Support to imple Post Limited 12,000.00 0.00 2023-05-22 2023-05-17 2023-05-27 2023-06-17 2023-07-22 2024-01-18 ant Selection ation f External Auditor menting agencies Page 2