Dam Operational Improvement and Safety Project Phase 2 (DOISP 2) LOAN NO. P 8711 Procurement Plan Version No.: 1 Date: July 16, 2018 I. General Information 1. Project information: a. Country: Indonesia b. Recipient: Ministry of Finance (MOF) c. Project Name: Dam Operational Improvement and Safety Project Phase 2 d. Project Implementing Agency (PIA): (i) Directorate General of Water Resources – Ministry of Public Works and Housing 2. Bank’s No Objection Date of the Procurement Plan: a. Version 1: June 5, 2017 b. Version 2: November 10, 2017 c. Version 3: July 5, 2018 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: January 1, 2017 to December 31, 2018 II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procureme Ref. Bank’s Review Procurement Method nt Method No. Requirement Threshold 1. International Competitive ≥ $2,000,000 Each contract equal Bidding (Goods/IT System) to or above $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post 2. International Competitive ≥ review. Each contract equal Bidding (Non-consulting $10,000,000 to or above Services) $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post 3. National Competitive < $2,000,000 Each contract equal review. Bidding (Goods/IT System) to or above $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts 4. National Competitive < subject Each to post contract equal Bidding (Non-consulting review. $10,000,000 to or above Services) $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts 5. Shopping (Goods/IT < $ 100,000 subject No priorto post review System) review. (only post review). 6. Shopping (Small Works and < $ 200,000 No prior review Non-consulting Services) (only post review). 7. Direct Contracting (Small No Each contract equal Works, Goods and Non- procurement to or above consulting Services) method $1,500,000 threshold. equivalent shall be Subject to subject to Bank’s prior review. All justification other contracts for Direct subject to post Contracting review. as per para. 3.6 of the Justification for Procurementproposed use of Guidelines Direct Contracting method in any contract, regardless of value, shall be sent for the Bank’s 1. Pre-qualification: Not applicable. prior approval as part of the procurement plan. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable. 3. Reference to (if any) Project Operational/Procurement Manual: Not Applicable 4. Any Other Special Procurement Arrangements: (i) PIU may use its own forms of contract for goods/non-consulting services procured under shopping method, which have been reviewed and found acceptable by the Bank; (ii) The Bank may review technical aspects of procurement documents and other non-procurement matters (technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in questioned, if needed. 5. Summary of the Procurement Packages planned after project effectiveness (including those that are subject to retroactive financing and advance procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Comment No. on ed es c w s Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 1. Summary 2,222,22 1 No Prior of the ICB 2 (Goods/IT Systems) 2. Summary 3,310,80 9 No Post of the NCB 6 (Goods/IT Systems) 3. Summary [to be [to be No Post of the NCB updated, updated (Non- if any] , if any] consulting Services) 4. Summary 18,108,5 11 No Post of the NCB 26 (Works) 5. Summary 391,111 8 No Post of the Shopping (Goods) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packag Domesti Revie Comment No. on ed es c w s Cost Prefere by (US$ nce Bank million) (yes/no) (Prior / Post) 6. Summary [to be [to be No Post of the updated, updated Shopping if any] , if any] (Non- consulting Services) 7. Summary 481,481 3 No Post of the Shopping (Small Works) 8. Summary [to be [to be No Post of the updated updated Direct , if any] , if any] Contractin g (Goods/IT systems, Non- Consulting Services and Small Works) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement Ref. Selection Selection Method Bank’s Prior Review No. Method Threshold Requirement 1. QCBS (Firms) Applied to all Each contract equal to estimated value. No or above $500,000 threshold. equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. (Prior review from technical perspective of only the draft TOR 2. CQS (Firms) Only for estimated and No draft prior cost (only review contract value < $ estimate). post review). 300,000 as per paragraph 3.7 of the 3. Single Source Consultant No selection Guidelines. method Each contract equal to Selection of threshold. Subject to or above $500,000 Firms justification for Singe equivalent shall be Source Selection of subject to Bank’s prior firms as per para. 3.9 review. All other and 3.10 of the contracts subject to Consultant Guidelines. post review. (Prior review from technical perspective of only the draft TOR, Justification for use of Single Source Selection method and draft cost estimate, shall be sent for the Bank’s prior 4. Competitive No threshold. approval No as part prior review of the (only Selection of procurement post review), plan). unless Individual contract is equal to or Consultants above $200,000. (comparison of at least 3 CVs) (Prior review from technical perspective of only the draft TOR 5. Single Source No Threshold. and No draft prior cost (only review Selection of estimate). post review), unless Individual Subject to justification contract is equal to or Consultants for single source of above $200,000. individuals as per para. 5.4 of the (Prior review from Consultant Guidelines technical perspective of only the draft TOR, Justification for use of Single Source Selection method together with CV of the recommended candidate and draft cost estimate, shall be sent for the Bank’s 2. Shortlist comprising entirely of national consultants prior approval : Short as part of the procurement list of consultants for services (firms), estimated to cost less than $ 400,000 equivalent per contract, may comprise plan). entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Consultants may be hired under Indefinite Delivery Contract (IDCs) or Price Agreement as per paragraph 4.5 of the Consultant Guidelines. 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) 1. Summary (Time- 18,335,7 18 Prior of number Based/Lum 77 and of psump) Post contracts that will be let under QCBS 2. Summary (Time- 5,813,77 43 Post of number Based 8 of /Lump- contracts Sum) that will be let under other methods (QBS, FBS, LCS and CQS) 1 2 3 4 5 6 7 Ref Descripti Type of Estimat Packag Revie Commen . on of Assignme ed es/Posit w ts No. Assignme nts Cost ions by nts (US$ Bank million) (Prior / Post) 3. Summary (Time- 67,407 6 Post of number Based of /Lump- individual Sum) consultant contracts that will be let under competitiv e selection 4. Summary (Time- [to be [to be Post of number Based updated, updated, of /Lump- if any] if any] individual Sum) consultant contracts that will be let under single- source selection PROCUREMENT Indonesia : Dam Operational Improvement and Safety PLAN General Information Country: Indonesia 2018-09-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P096532 GPN Date: Project Name: Dam Operational Improvement and Safety Loan / Credit No: COFN / C1460 Directorate of Operation and Maintenance, Directorate General of Water Resources Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned RDC-CW-1 / Construction of Dam Operational Improvem Single Stage - One E 2020-03-0 Laboratory Building and Wor COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 724,444.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 nvelope 3 kshop at Balai Litbang BHGK udies SMT-CW-2 / Construction of Dam Operational Improvem Single Stage - One E 2020-03-0 Safety Measures and Support COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 370,370.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 nvelope 3 ing Facilities at Keuliling Dam udies SMT-CW-3 / Improvement of Dam Safety Institutional Imp Single Stage - One E 2020-03-0 COFN / C1460 Post Request for Bids Open - National 259,259.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 the Office of UPB BWS Suma rovement nvelope 3 tera I SMR-CW-3 / Rehabilitation of Dam Safety Institutional Imp Single Stage - One E 2020-03-2 DMU (Dam Management Unit COFN / C1460 Post Request for Bids Open - National 185,185.00 0.00 Canceled 2019-01-21 2019-02-10 2019-03-02 2019-03-10 2019-03-30 rovement nvelope 9 ) Building at BWS Sumatera I V Office CC-CW-1 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 1,481,481.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Gintung Dam ent and Safety Works and St nvelope 8 udies BSO-CW-3 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 2,222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Lalung Dam ent and Safety Works and St nvelope 8 udies BSO-CW-4 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 3,703,704.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Pacal Dam ent and Safety Works and St nvelope 8 udies BSO-CW-5 / Improvement an d Maintenance of the Dam Cr est, Instrumentataion, and Li Dam Operational Improvem Single Stage - One E 2020-09-0 ghting at Dawuhan Dam, and COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 2,222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 nvelope 8 Reinforcement of Dam Slope udies and Improvement of Hydrom echanical Gate at Gonggang Dam BSO-CW-6 / Improvement an d Maintenance of the Dam Cr Dam Operational Improvem est, Instrumentataion, Lightin Single Stage - One E 2020-03-0 COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 g, and Reinforcement of Dam nvelope 3 udies Slope and Improvement of H ydromechanical Gate at Prije tan Dam KLM-CW-2 / Reinforcement o Dam Operational Improvem Single Stage - One E 2020-02-2 COFN / C1460 Post Request for Bids Open - National 518,519.00 0.00 Canceled 2019-01-07 2019-01-14 2019-01-28 2019-02-04 2019-02-25 f Manggar Dam in Balikpapan ent and Safety Works and St nvelope 5 City udies KLM-CW-3 / Safety Measures Dam Operational Improvem Single Stage - One E 2019-04-0 COFN / C1460 Post Request for Bids Open - National 222,222.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 at Binalatung Dam, Tarakan ent and Safety Works and St nvelope 9 City udies KLM-CW-4 / Improvement of Dam Safety Institutional Imp Single Stage - One E 2020-03-0 the Office of UPB BWS Kalim COFN / C1460 Post Request for Bids Open - National 518,519.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 rovement nvelope 3 antan III, Samarinda City NTG-CW-1 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-09-0 COFN / C1460 Post Request for Bids Open - National 862,963.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Haikrit Dam ent and Safety Works and St nvelope 8 udies NTE-CW-5 / Installation of Fe Dam Operational Improvem Request for Quota Single Stage - One E 2020-03-0 COFN / C1460 Post Open - National 74,074.00 0.00 Canceled 2019-01-14 2019-03-04 nces at Batujai Dam Greenbe ent and Safety Works and St tions nvelope 3 lt udies NTG-CW-2 / Rehabilitation of Dam Operational Improvem Single Stage - One E 2020-03-0 COFN / C1460 Post Request for Bids Open - National 370,370.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-04 Haliwen Dam ent and Safety Works and St nvelope 3 udies BP-CW-3 / Hydromechanical Dam Operational Improvem Rehabilitation Works Palasari Single Stage - One E 2020-08-2 COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 936,981.00 0.00 Canceled 2018-12-28 2019-01-04 2019-01-25 2019-02-01 2019-02-22 , Grokgak, Telaga Tunjung da nvelope 9 udies n Benel Dams in Bali Provinc e PJE-CW-4 / Rehabilitation Po Dam Operational Improvem Single Stage - One E 2020-02-2 COFN / C1460 Post Request for Bids Open - National 455,556.00 0.00 Canceled 2018-12-28 2019-01-04 2019-01-25 2019-02-01 2019-02-22 nre-Ponre Dam ent and Safety Works and St nvelope 2 udies National Procure OP-CW-1 / Improvement of E ment Document - quipment/Operational Faciliti Dam Safety Institutional Imp Single Stage - One E Pending Imp 2021-11-2 COFN / C1460 Post Request for Bids Open - National 1 Envelope proce 433,333.00 0.00 2021-02-10 2021-02-15 2021-03-29 2021-04-28 2021-06-02 es for CDMU at Dit. of O&M, rovement nvelope lementation 9 ss (Non Bank-SPD DGWR (Phase IV) ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OP-GD-3 / Improvement of E Dam Operational Improvem quipment/Operational Faciliti Single Stage - One E Under Imple COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 222,222.00 0.00 2017-11-21 2019-06-27 2017-11-28 2017-12-21 2019-09-05 2017-12-28 2018-01-05 2018-05-05 es for Central Dam Monitorin nvelope mentation udies g Unit (CDMU) at Dit. of O&M , DGWR OP-GD-1 / Provision of BDSF Dam Operational Improvem Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 2,222,222.22 0.00 Canceled 2018-12-04 2018-12-09 2019-01-20 2019-02-19 2019-03-26 2019-09-22 (Basic Dam Safety Facilities) ent and Safety Works and St l nvelope udies RDC-GD-2 / Provision of Auto Dam Operational Improvem Single Stage - One E matization System for Hydro COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 173,741.00 0.00 Canceled 2019-01-22 2019-01-27 2019-02-17 2019-02-24 2019-03-02 2019-10-28 nvelope ulic Laboratory Equipment udies Page 1 BSO-GD-2 / Provision of Falic Dam Safety Institutional Imp Request for Quota Single Stage - One E COFN / C1460 Post Open - National 15,333.00 0.00 Canceled 2019-01-14 2019-03-04 2019-10-30 ities for UPB rovement tions nvelope NTG-GD-1 / Provision of Dam Dam Operational Improvem Single Stage - One E COFN / C1460 Post Request for Bids Open - National 148,148.00 0.00 Canceled 2019-01-07 2019-01-14 2019-02-04 2019-02-11 2019-03-03 2019-10-29 Monitoring Equipment ent and Safety Works and St nvelope udies BB-GD-2 / Provision of Dam Dam Safety Institutional Imp Request for Quota Single Stage - One E COFN / C1460 Post Open - National 7,407.00 0.00 Canceled 2019-03-18 2019-05-05 2019-11-01 Books rovement tions nvelope OP-GD-7 / Operational Impro Dam Operational Improvem Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 6,666,666.67 0.00 Canceled 2019-06-11 2020-04-10 2019-06-18 2020-06-29 2019-07-09 2019-07-16 2019-08-05 2021-07-25 vement of CDMU ent and Safety Works and St l nvelope udies OP-GD-4 / Provision of Opera Operation and Maintenance I Request for Quota Single Stage - One E tion and Maintenance of Dam COFN / C1460 mprovement and Capacity B Post Open - National 66,667.00 0.00 Signed 2019-06-17 2019-08-12 2020-02-08 tions nvelope facilities and infrastructure uilding OP-GD-5 / Improvement of E quipment/Operational Faciliti Dam Safety Institutional Imp Single Stage - One E COFN / C1460 Post Request for Bids Open - National 233,333.00 0.00 Signed 2019-06-12 2019-06-27 2019-06-17 2019-07-08 2019-09-05 2019-07-15 2019-09-23 2019-07-22 2020-03-18 es for Central Dam Monitorin rovement nvelope g Unit (CDMU),at Dit. of O&M , DGWR Stage II OP-GD-6 / Provision of Mean Dam Safety Institutional Imp Single Stage - One E s & Infrastructure Support for COFN / C1460 Post Request for Bids Open - National 333,333.00 345,474.72 Signed 2019-06-12 2019-06-27 2019-06-17 2019-07-08 2019-09-09 2019-07-15 2019-09-23 2019-07-23 2019-12-12 2020-03-19 rovement nvelope Activities OP Bendungan OP-GD-1A / Provision of BDS Dam Operational Improvem Single Stage - One E COFN / C1460 Prior Request for Bids Open - National 1,966,667.00 0.00 Canceled 2019-06-27 2019-09-26 2019-07-02 2019-09-27 2019-07-16 2019-07-23 2019-08-24 2020-08-23 F (Basic Dam Safety Facilities ent and Safety Works and St nvelope ) udies OP-GD-2 / Procurement of D am Monitoring Equipment, To pographic & Bathymetric Sur Dam Operational Improvem veys and Speed Boat Survey Single Stage - One E COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 710,433.00 807,136.78 Signed 2019-06-18 2019-06-27 2019-06-23 2019-08-04 2019-09-05 2019-09-03 2019-09-23 2019-10-08 2019-12-12 2020-04-05 s to support the implementat nvelope udies ion of dam monitoring in acc ordance with the objectives o f operation, maintenance and monitoring OP-GD-8 / Provision of Equip Reservoir Sedimentation Miti Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 1,933,333.33 0.00 Canceled 2020-03-30 2020-04-04 2020-05-16 2020-06-15 2020-07-20 2021-01-16 ment for Sedimentation Mitig gation l nvelope ation OP-GD-1B / Provision of BDS Dam Operational Improvem Single Stage - One E COFN / C1460 Prior Request for Bids Open - National 1,966,667.00 1,944,732.29 Signed 2020-03-02 2020-03-12 2020-03-07 2020-05-08 2020-04-18 2020-06-01 2020-05-18 2020-07-07 2020-06-22 2020-08-11 2020-12-19 F (Basic Dam Safety Facilities ent and Safety Works and St nvelope ) udies OP-GD-9 / Dam Asset Manag Operation and Maintenance I Single Stage - One E COFN / C1460 Post Request for Bids Open - National 333,333.00 0.00 Canceled 2020-04-06 2020-04-11 2020-05-23 2020-06-22 2020-07-27 2021-01-23 ement System mprovement and Capacity B nvelope uilding OP-GD-10 / Software for Sup Operation and Maintenance I Single Stage - One E COFN / C1460 Post Request for Bids Open - National 133,333.00 0.00 Signed 2020-04-06 2020-06-11 2020-04-11 2020-05-23 2020-07-03 2020-06-22 2020-07-22 2020-07-27 2021-01-23 porting CDMU mprovement and Capacity B nvelope uilding OP-GD-11 / Improvement of Dam Safety Institutional Imp Single Stage - One E Equipment /Operational Facili COFN / C1460 Post Request for Bids Open - National 1,333,333.00 0.00 Signed 2020-04-06 2020-05-29 2020-04-11 2020-05-23 2020-07-01 2020-06-22 2020-07-22 2020-07-27 2021-01-23 rovement nvelope ties for CDMU at Dit. of O&M, DGWR (Phase III) OP-GD-8A / Provision of Equi Reservoir Sedimentation Miti Single Stage - One E COFN / C1460 Prior Request for Bids Open - National 1,933,333.33 1,770,109.27 Signed 2020-05-11 2020-06-12 2020-05-16 2020-06-15 2020-06-27 2020-07-29 2020-07-27 2020-09-01 2020-08-31 2020-09-24 2021-02-27 pment for Sedimentation Miti gation nvelope gation OP-GD-7A / Operational Impr Dam Operational Improvem Open - Internationa Single Stage - One E COFN / C1460 Prior Request for Bids 6,666,666.67 0.00 Canceled 2020-09-15 2020-09-27 2020-09-20 2020-09-28 2020-11-01 2020-11-18 2020-12-01 2021-02-03 2021-01-05 2021-07-04 ovement of CDMU ent and Safety Works and St l nvelope udies OP-GD-12 / Software for Sup Operation and Maintenance I Single Stage - One E COFN / C1460 Post Request for Bids Open - National 200,000.00 0.00 Signed 2021-08-20 2021-08-31 2021-08-25 2021-10-06 2021-10-01 2021-11-05 2021-10-12 2021-12-10 2022-06-08 porting CDMU Phase II mprovement and Capacity B nvelope uilding OP-GD-13 / Provision of Dam Dam Safety Institutional Imp Single Stage - One E COFN / C1460 Post Request for Bids Open - National 266,667.00 0.00 Signed 2021-08-20 2022-01-11 2021-08-25 2021-10-06 2022-02-07 2021-11-05 2022-03-25 2021-12-10 2022-06-08 Monitoring Equipment rovement nvelope OP-GD-14 / Improvement of Dam Operational Improvem Equipment/Operational Facili Single Stage - One E COFN / C1460 ent and Safety Works and St Post Request for Bids Open - National 433,333.00 0.00 Signed 2021-10-31 2022-07-05 2021-11-05 2021-12-17 2022-07-29 2022-01-16 2022-08-15 2022-02-20 2022-08-19 ties for CDMU at Dit. of O&M, nvelope udies DGWR (Phase IV) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OP-NCS-1 / Mini-Series Movi Dam Safety Institutional Imp Single Stage - One E COFN / C1460 Post Request for Bids Open - National 266,667.00 0.00 Signed 2021-08-20 2021-08-30 2021-08-25 2021-10-06 2021-09-30 2021-11-05 2021-10-12 2021-12-10 2022-06-08 es of Dam Education rovement nvelope CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual OP-CS-1 / TA Consultancy Se Dam Operational Improvem rvices for Supporting the Cen Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 3,342,815.00 2,800,378.60 Signed 2017-09-13 2017-10-04 2017-11-17 2017-12-15 2018-01-14 2018-02-18 2018-11-16 2018-03-25 2018-11-02 2019-03-25 tral Project Management Unit Based Selection l udies of DOISP II (TA CPMU) OP-CS-2 / TA Consultancy Se Dam Operational Improvem rvices for Supporting the Imp Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 11,212,444.00 9,814,105.27 Signed 2017-09-13 2017-10-04 2017-11-17 2017-12-15 2018-01-14 2018-02-18 2018-12-14 2018-03-25 2018-11-30 2019-03-25 lementation Management an Based Selection l udies d Supervision of the DOISP II (TA CPIU) OP-CS-5 / Guidelines for Gov Dam Operational Improvem Quality And Cost- ement-owned Dam Managem COFN / C1460 ent and Safety Works and St Post Open - National 148,148.00 0.00 Signed 2018-12-31 2019-05-03 2019-01-07 2019-03-07 2019-09-05 2019-03-08 2019-09-27 2019-03-14 2019-10-06 2019-04-24 2019-11-06 2019-05-05 2020-05-04 Based Selection ent by Business Entity udies OP-CS-6 / Reservoir Inspecti Dam Operational Improvem Quality And Cost- on and Evaluation Dam Cate COFN / C1460 ent and Safety Works and St Post Open - National 233,233.00 0.00 Signed 2019-01-02 2019-04-29 2019-01-23 2019-03-07 2019-07-11 2019-03-08 2019-09-27 2019-03-15 2019-11-06 2019-04-01 2019-11-15 2019-04-15 2020-04-14 Based Selection gory Stage I udies Page 2 RDC-CS-2 / Supervision of La Dam Operational Improvem Quality And Cost- boratory and Workshop Build COFN / C1460 ent and Safety Works and St Post Open - National 16,296.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection ing of Balai Litbang BHGK udies SMT-CS-7 / Supervision of Im provement of UPB/ DMU (Da Dam Safety Institutional Imp Quality And Cost- COFN / C1460 Post Open - National 12,963.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 m Management Unit), in BWS rovement Based Selection Sumatera I, Phase I SMR-CS-10 / Supervision of Dam Safety Institutional Imp Quality And Cost- Rehabilitation of DMU Buildin COFN / C1460 Post Open - National 17,778.00 0.00 Canceled 2019-02-04 2019-02-09 2023-01-10 2023-02-07 2023-02-14 2023-03-18 2023-04-10 2024-04-09 rovement Based Selection g of BWS Sumatera IV SMR-CS-11 / DD of DMU Buil Dam Safety Institutional Imp Quality And Cost- ding Rehabilitation of BWS S COFN / C1460 Post Open - National 22,222.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-12-29 rovement Based Selection umatera IV and Heavy Mechi nery Workshop MSE-CS-4 / EAP Study of Wa Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 97,778.00 0.00 Canceled 2019-02-04 2019-02-09 2019-03-12 2019-04-09 2019-04-16 2019-05-18 2019-06-10 2019-10-08 y Jepara Dam ent and Safety Works and St Based Selection udies CC-CS-2 / Supervision on Gin Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 103,704.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 tung Dam Rehabilitation ent and Safety Works and St Based Selection udies CTR-CS-3A / Supervision of R Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 125,926.00 0.00 Canceled 2019-01-01 2019-01-20 2019-02-20 2019-03-20 2019-03-27 2019-04-28 2019-05-21 2020-05-20 ehabilitation Works of Cipanc ent and Safety Works and St Based Selection uh Dam udies BSO-CS-7 / Supervision for R Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 111,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 ehabilitation Works of Lalung ent and Safety Works and St Based Selection Dam udies BSO-CS-8 / Supervision for R Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 185,185.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 ehabilitation Works of Pacal ent and Safety Works and St Based Selection Dam udies BSO-CS-9 / Special Study for Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 222,222.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-10-30 Gonggang, Prijetan, and Pon ent and Safety Works and St Based Selection dok Dams udies BSO-CS-10 / Supervision on Rehabilitation and Maintenan ce of Crest, Instrumentation Dam Operational Improvem Quality And Cost- and Lighting of Dawuhan Da COFN / C1460 ent and Safety Works and St Post Open - National 111,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 Based Selection m, and Slope Reinforcement udies and Improvement of Hydrom echanical Gate of Gonggang Dam. BSO-CS-11 / Supervision on Rehabilitation and Maintenan Dam Operational Improvem ce of Crest, Instrumentation, Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 11,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Lighting and Slope Reinforce Based Selection udies ment and Improvement of Hy dromechanical Gate of Prijet an Dam. BSO-CS-12 / Detailed Desain of Rehabilitation and Moderni Dam Operational Improvem zation of Instrumentation an Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 200,000.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 d Hydromechanical at Dams i Based Selection udies n Bengawan Solo River Basin / Wilayah Sungai Bengawan Solo BSO-CS-13 / Special Study of Dam Operational Improvem Quality And Cost- Saradan Dam, Kab. Madiun J COFN / C1460 ent and Safety Works and St Post Open - National 200,000.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2019-11-04 Based Selection awa Tengah udies BSO-CS-16 / Preparation and Operation and Maintenance I Quality And Cost- Legalization Operation Permi COFN / C1460 mprovement and Capacity B Post Open - National 222,222.00 0.00 Canceled 2019-01-09 2019-01-14 2019-02-14 2019-03-14 2019-03-21 2019-04-22 2019-05-15 2020-02-09 Based Selection t of Gondang and Prijetan Da uilding ms BT-CS-2 / SID for Conservati Reservoir Sedimentation Miti Quality And Cost- on and Sedimentation Treat COFN / C1460 Post Open - National 148,148.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 gation Based Selection ment at Sengguruh Reservoir KLM-CS-8 / Supervision of Im Dam Operational Improvem Quality And Cost- provement of Manggar Dam, COFN / C1460 ent and Safety Works and St Post Open - National 14,815.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection Kota Balikpapan udies KLM-CS-9 / Supervision of Se Dam Operational Improvem Quality And Cost- faety Measures of Binalatung COFN / C1460 ent and Safety Works and St Post Open - National 7,407.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection Dam, Kota Tarakan udies KLM-CS-10 / Preparation of E Operation and Maintenance I Quality And Cost- AP / TRD for Lempake Dam, COFN / C1460 mprovement and Capacity B Post Open - National 59,259.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-10-30 Based Selection Kota Samarinda uilding KLM-CS-11 / Supervision of I Dam Safety Institutional Imp Quality And Cost- mprovement of UPB / DMU in COFN / C1460 Post Open - National 74,074.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 rovement Based Selection BWS Kalimantan IIII, Samarin da NTE-CS-8 / Spatial Arrangem Dam Operational Improvem Quality And Cost- ent for Batujai Reservoir and COFN / C1460 ent and Safety Works and St Post Open - National 74,074.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection Dam, Pulau Lombok udies NTE-CS-11 / Desain of UPB O Dam Operational Improvem Quality And Cost- ffice Rehabilitation, BWS Nus COFN / C1460 ent and Safety Works and St Post Open - National 11,111.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection a Tenggara I udies NTG-CS-4 / Supervision of Re Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 44,444.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-11-12 habilitation Haikrit and Haliw ent and Safety Works and St Based Selection en Dams udies SMT-CS-6 / UKL / UPL Study Dam Operational Improvem of Roads and Connecting Bri Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 77,778.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-05-02 dges, and Supervision of Keul Based Selection udies iling Dam Safety Mesures Co nstruction BB-CS-3 / Study of Hydrogeo Dam Operational Improvem Quality And Cost- logical Influence on Dam Con COFN / C1460 ent and Safety Works and St Post Open - National 92,593.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection struction Plans udies BB-CS-4 / Evaluation of Stud Dam Operational Improvem Quality And Cost- y on Approval of Dam Design COFN / C1460 ent and Safety Works and St Post Open - National 87,037.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 Based Selection on Dam Rehabilitation Imple udies mentation Page 3 BB-CS-5 / Guidelines of Seis Dam Safety Institutional Imp Quality And Cost- COFN / C1460 Post Open - National 100,000.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-12-29 mic Hazard Assessmet rovement Based Selection BB-CS-6 / Guidelines of Sism Dam Safety Institutional Imp Quality And Cost- COFN / C1460 Post Open - National 103,704.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2019-12-29 ic Hazard Analysis rovement Based Selection BB-CS-7 / Guidelines of Dyna Dam Safety Institutional Imp Quality And Cost- mic Analysis of Embankment COFN / C1460 Post Open - National 92,593.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 rovement Based Selection Type Dams) BB-CS-8 / Organize Inventor Dam Safety Institutional Imp Quality And Cost- y, Registration, and Clarificat COFN / C1460 Post Open - National 104,148.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-01-03 rovement Based Selection ion of Dam Hazard OP-CS-4 / Guidelines for Det Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 111,111.00 0.00 Signed 2018-10-17 2019-01-24 2018-11-07 2019-03-13 2019-03-11 2019-04-10 2019-02-21 2019-05-10 2019-04-29 2019-06-14 2019-05-16 2019-07-19 2020-07-18 ermining The Reservoir Bord ent and Safety Works and St Based Selection er Line udies CTR-CS-7 / DED, LARAP and Dam Operational Improvem Quality And Cost- Environment Permit for Capa COFN / C1460 ent and Safety Works and St Post Open - National 259,259.00 0.00 Canceled 2019-01-02 2019-01-07 2019-02-07 2019-03-07 2019-03-14 2019-04-15 2019-05-08 2020-05-07 Based Selection city Development of Cikemba udies ng River CMC-CS-2 / Preparation and Dam Operational Improvem Legalization Operation Permi Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 1,037,037.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 t of Darma, Malahayu, Situp Based Selection l udies atok snd Situ Bolang Dams PMJ-CS-6 / Preparation and L egalization Operation Permit Dam Operational Improvem Quality And Cost- Open - Internationa of Dams in Pemali River Basi COFN / C1460 ent and Safety Works and St Prior 888,889.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2021-10-10 Based Selection l n (Lodan, Panohan, Banyuku udies wung, Klego, Kedung Ombo a nd Cacaban) PMJ-CS-7 / Preparation and L Dam Operational Improvem egalization Operation Permit Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Prior 1,037,037.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2021-10-10 of Dams in Pemali Comal Riv Based Selection l udies er Basin (Simo, Penjalin, Gre neng and Tempuran) SRO-CS-4 / SID of Sedimenta tion Control and Managemen Dam Operational Improvem t at Sermo and Wadas Lintan Quality And Cost- Open - Internationa COFN / C1460 ent and Safety Works and St Post 407,407.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-08-06 g Dams, and Zoning Arrange Based Selection l udies ment in the Area of Sermo, S empor and Wadas Lintang D ams SRO-CS-5 / Preparation and Dam Operational Improvem Quality And Cost- Open - Internationa Legalization of Operation Per COFN / C1460 ent and Safety Works and St Post 466,667.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection l mit for Wadaslintang and Se udies mporDams BSO-CS-14 / Preparation and Operation and Maintenance I Legalization Operation Permi Quality And Cost- Open - Internationa COFN / C1460 mprovement and Capacity B Prior 518,519.00 0.00 Canceled 2019-03-20 2019-04-08 2019-05-09 2019-06-06 2019-06-13 2019-07-14 2019-08-07 2020-08-06 t of Song Putri, Parangjoho, N Based Selection l uilding awangan, Cengklik, Delingan , and Ketro Dams BSO-CS-17 / SID Sedimentati Reservoir Sedimentation Miti Quality And Cost- Open - Internationa on Coveservation of 6 Reserv COFN / C1460 Post 355,556.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 gation Based Selection l oir and UKL+UPL BT-CS-1 / Preparation and Le galization Operation Permits Dam Operational Improvem Quality And Cost- Open - Internationa (Kd. Sengon, Sumber Kepuh, COFN / C1460 ent and Safety Works and St Prior 1,111,111.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection l Klampis, Sengguruh, Selorejo udies , and Bening Dams) NTE-CS-9 / Preparation and L egalization of Operation Per Dam Operational Improvem Quality And Cost- Open - Internationa mit of Dams in Lombok Islan COFN / C1460 ent and Safety Works and St Prior 518,519.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-10-10 Based Selection l d Stage II (Pengga, Telaga L udies ebur, Tibu Kuning, dan Jerow aru) NTE-CS-10 / Preparation and Legalization of Operation Per Dam Operational Improvem Quality And Cost- Open - Internationa mit of Dams in Sumbawa Isla COFN / C1460 ent and Safety Works and St Prior 592,593.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2021-10-10 Based Selection l nd Stage II (Sumi, Batu Bulan udies , Olat Rawa, Ncera, Gapit dan Laju) MSE-CS-3 / Preparation and Dam Operational Improvem Quality And Cost- Open - Internationa Legalization Operation Permi COFN / C1460 ent and Safety Works and St Post 355,556.00 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-03 2019-08-02 2019-09-06 2019-10-11 2020-08-06 Based Selection l t of Way Jepara and Way Rar udies em Dams BP-CS-4 / Supervision for Re Dam Operational Improvem storation of Hydromechanical Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 40,466.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-11-07 at Palasari, Grokgak, Telaga Based Selection udies Tunjung and Benel Dams di P rovinsi Bali PJE-CS-9 / Supervision of Re Dam Operational Improvem Quality And Cost- habilitation and Remedial Wo COFN / C1460 ent and Safety Works and St Post Open - National 44,444.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-11-07 Based Selection rks of Kalola and Bili-Bili Dam udies s PJE-CS-8 / Supervision of Re Dam Operational Improvem Quality And Cost- COFN / C1460 Post Open - National 14,815.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-05-02 habilitation Works of Ponre-P ent and Safety Works and St Based Selection onre Dam udies PJE-CS-10 / Detailed Desain Dam Operational Improvem and UKL/UPL Study for Conve Quality And Cost- COFN / C1460 ent and Safety Works and St Post Open - National 185,185.00 0.00 Canceled 2018-12-28 2019-01-02 2019-02-02 2019-03-02 2019-03-09 2019-04-10 2019-05-03 2020-01-28 rvation Building at upstream Based Selection udies of Kalola, Salomekko snd Pon re-Ponre Dams OP-CS-7 / Reservoir Inspecti Dam Operational Improvem Quality And Cost- on and Evaluation Dam Cate COFN / C1460 ent and Safety Works and St Post Open - National 210,000.00 0.00 Under Review 2019-06-11 2020-04-13 2019-06-18 2019-07-19 2019-08-16 2019-08-23 2019-09-23 2019-10-17 2020-10-16 Based Selection gory Stage II udies OP - CS - 8 / Dam Asset Man Operation and Maintenance I Quality And Cost- Open - Internationa COFN / C1460 Post 333,333.00 0.00 Under Review 2020-06-24 2020-08-06 2020-07-15 2020-08-28 2020-09-25 2020-10-25 2020-11-29 2021-01-03 2022-01-03 agement System mprovement and Capacity B Based Selection l uilding OP-CS-9 / Study of Dam Mon Dam Safety Institutional Imp Quality And Cost- Open - Internationa Pending Impleme itoring using Interferometric COFN / C1460 Post 333,333.00 0.00 2021-08-20 2021-09-10 2021-10-24 2021-11-21 2021-12-21 2022-01-25 2022-03-01 2023-03-01 rovement Based Selection l ntation Syntetic Radar (InSAR) OP-CS-9A / Study of Dam Mo Dam Operational Improvem Quality And Cost- nitoring using Interferometric COFN / C1460 ent and Safety Works and St Post Open - National 298,970.00 0.00 Under Review 2021-10-27 2022-01-20 2021-11-17 2021-12-31 2022-01-28 2022-02-27 2022-04-03 2022-05-08 2023-05-08 Based Selection Syntetic Radar (InSAR) udies Page 4 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 PROCUREMENT PLAN (Textual Part) Project information: Country: Federal Democratic Republic of Ethiopia De-Risking, Inclusion and Value Enhancement of Pastoral Economies (DRIVE) in the Horn of Africa Project, Project ID No. P176517 Project Implementation agency: Ministry of Agriculture and Ministry of trade and Regional Integration Date of the Procurement Plan: July 14, 2022 Period covered by this Procurement Plan: July 2022 to Dec 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (Fourth Edition, November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement and Property Administration Proclamation No. 649/2009, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works is not applicable for those contracts identified in the Procurement Plan tables] Other Relevant Procurement Information. Not Applicable PROCUREMENT Eastern and Southern Africa : De-risking, inclusion and value enhancement of pastoral economies in the Horn of Africa PLAN General Information Country: Eastern and Southern Africa 2022-10-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176517 GPN Date: 2022-08-24 Project Name: De-risking, inclusion and value enhancement of pastoral economies in the Horn of Africa Loan / Credit No: IDA / E0380 Ministry of Agriculture- Ethiopia Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-ETH-311250-GO-RF Livestock Value Chains and Open - Internationa Single Stage - One E Under Imple IDA / E0380 Post Request for Bids 800,000.00 0.00 2022-11-30 2023-01-31 2022-12-05 2023-02-16 2022-12-20 2023-03-15 2023-02-18 2023-05-31 2023-03-25 2023-09-21 B / Procurement of 21 Vehicl Trade Facilitation l nvelope mentation es NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOA-ETH-311207-CS-QC BS / Trade Logistics Economi Livestock Value Chains and Quality And Cost- Open - Internationa Under Implement c Feasibility Study for the tra IDA / E0380 Post 500,000.00 0.00 2022-09-20 2022-10-13 2022-10-20 2023-01-23 2022-12-09 2023-01-08 2023-02-17 2023-04-08 2023-05-13 2023-11-09 Trade Facilitation Based Selection l ation de route from Mille to Djibout i, Jigjiga to Djibouti and Jigjig a to Berbera ports ET-MOA-ETH-321413-CS-LCS Livestock Value Chains and Least Cost Selecti Pending Impleme IDA / E0380 Post Open - National 30,000.00 0.00 2023-03-31 2023-03-31 2023-04-14 2023-05-14 2023-06-13 2023-07-18 2023-08-22 2025-08-21 / Hiring External Financial Au Trade Facilitation on ntation dit ET-MOA-ETH-311206-CS-QC BS / Recruitment of Consulta nt to assess capacity gaps an Livestock Value Chains and Quality And Cost- Under Implement d propose interventions in rel IDA / E0380 Post Open - National 100,000.00 0.00 2022-11-30 2023-01-23 2022-12-25 2023-01-25 2023-03-10 2023-04-09 2023-05-24 2023-08-07 2023-09-27 2024-03-25 Trade Facilitation Based Selection ation ation to testing, certification and inspection services, trac eability system, export abatt oirs and export quarantine sy stem ET-MOA-ETH-321384-CS-QC BS / Feasibility study for a re Livestock Value Chains and Quality And Cost- Pending Impleme IDA / E0380 Post Open - National 100,000.00 0.00 2023-02-28 2023-03-25 2023-06-08 2023-07-08 2023-08-22 2023-11-05 2023-12-26 2024-03-25 st point at Bole airport for ex Trade Facilitation Based Selection ntation port of sheep and goats thro ugh cargo ET-MOA-ETH-321391-CS-QC BS / Conducting studies to str Livestock Value Chains and Quality And Cost- Pending Impleme IDA / E0380 Post Open - National 100,000.00 0.00 2023-04-24 2023-05-19 2023-08-02 2023-09-01 2023-10-16 2023-12-30 2024-02-19 2024-08-17 engthen linkages between pa Trade Facilitation Based Selection ntation storalists and live animal exp orters/abattoirs INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 Partial Risk Sharing Facility in Energy Efficiency PROCUREMENT PLAN I. General 1. Project information: • Project Name: Partial Risk Sharing Facility in Energy Efficiency • Country: India • Project Code: P128921 2. Bank’s approval Date of the procurement Plan Draft Procurement Plan dated November 13, 2014 Revision 0 agreed by the Bank on November 13, 2014 3. Implementing Agencies: Small Industries Development Bank of India (SIDBI) and Energy Efficiency Services Limited (EESL) 4. Period covered by this procurement plan: 18 months 5. Risk Rating for the Implementing Agency: Moderate 6. Original Procurement Risk Rating for the Project: Moderate 7. Current Procurement Risk Rating for the Project: Moderate II. Non-consulting services and Goods. 1 a) Procurement Methods and Thresholds Categor Method of Procurement Threshold (USD Equivalent) y Goods International Competitive Bidding > 3,000,000 and (ICB) Non- Limited International Bidding (LIB) wherever agreed by Bank consulta National Competitive Bidding Up to 3,000,000 (with NCB nt (NCB) conditions) services Shopping Up to 100,000 Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) As per paragraph 3.14 of Services Guidelines Force Account As per paragraph 3.9 of Guidelines Framework Agreement (FA) As per paragraph 3.6 of Guidelines Procurement from United Nations As per paragraph 3.10 of (UN) Agencies Guidelines Performance Based Procurement As per paragraph 3.16 of Guidelines 1 b) Prior Review Threshold Goods: All contracts more than USD 6 million equivalent Non-Consultant Services and IT systems: All contracts more than USD 6 million equivalent In addition, the justifications for all contracts to be issued using LIB or direct contracting shall be subject to prior review. First framework agreement will be subject to prior review irrespective of value. For prior review contracts, the amendments for increasing the cost or extension of time beyond 15% of original value shall also be subject to Bank’s prior review. 2. Pre-qualification – Not envisaged 3. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s “Guidelines: Procurement of goods, works and non-consulting services under IBRD loans and IDA credits & grants by World Bank borrowers” dated January 2011 (as updated in July 2014). 4. Any Other Special Procurement Arrangements: NCB will be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines and the following provisions: i. Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding; ii. Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; iii. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State; iv. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; v. Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/ Employer) vi. Re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank vii. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; viii. Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures. Such contracts will be acceptable however for any procurement under the Shopping procedures; ix. Two or three envelope system will not be used (except when using e-Procurement system assessed and agreed by the Bank) Other agreed provisions are: • Any discount received from the bidders after bid submission deadline will not be considered either during the bid evaluation or the contract award. • Domestic preference will be applicable for ICB procurement of Goods as per Appendix 2 of the Procurement Guidelines. • Bids received from foreign bidders will not be rejected under NCB. 5. Procurement Packages with Methods and Time Schedule – As per STEP. III. Selection of Consultants 1 a) Selection Methods and Thresholds Category Method of Procurement Threshold (USD Equivalent) Consultants’ Selection Based on Up to 300,000 Services Consultants’ Qualifications (CQS)/Least-Cost Selection (LCS) Single-Source Selection As per paragraphs 3.9-3.11 of (SSS) Guidelines Individuals As per Section V of Guidelines Particular Types of As per paragraphs 3.15-3.21 of Consultants Guidelines Quality- and Cost-Based for all other cases Selection (QCBS)/ Quality- Based Selection (QBS)/ Selection under a Fixed Budget (FBS) 1 b) Prior Review Threshold Consultancy Services: > US$ 4 Million equivalent for firms; and > US$ 500,000 equivalent for individuals In addition, the justifications for all contracts to be issued on the basis of single-source selection will be subject to prior review. For prior review contracts, the amendments for increasing the cost or extension of time beyond 15% of original value shall also be subject to Bank’s prior review. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: The evaluation committees will have external experts, as and when required, apart from in-house experts. 4. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s “Guidelines: Selection and employment of consultants under IBRD loans and IDA credits & grants by World Bank borrowers” dated January 2011 (as updated in July 2014). 5. Consultancy Assignments with Selection Methods and Time Schedule – As per STEP. PROCUREMENT India : Partial Risk Sharing Facility in Energy Efficiency PLAN General Information Country: India 2016-08-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P128921 GPN Date: Project Name: Partial Risk Sharing Facility in Energy Efficiency Loan / Credit No: TF / 19308 Small Industries Development Bank of India Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-256556-GO-RFQ / L aptops 10 nos, Printer (Desk) 2. Component 2: Technical Request for Quota Single Stage - One E 2 nos. and Printer (Office) 1 n TF / 19308 assistance and capacity buil Post Limited 35,000.00 17,687.36 Completed 2021-10-20 2021-11-09 2021-12-15 2021-12-16 2022-01-14 2021-12-29 tions nvelope o are proposed to be procure ding d for the PMU Staff working a t PEA SIDBI. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-346774-NC-RFB / Hi 2. Component 2: Technical Single Stage - Two E Pending Impl ring of agency for Developm TF / 19308 assistance and capacity buil Post Request for Bids Open - National 22,000.00 0.00 2023-03-10 2023-03-22 2023-05-03 2023-07-16 2023-08-20 2026-03-31 nvelope ementation ent and Maintenance of PRSF ding website IN-SIDBI-346782-NC-RFB / Hi ring a CA Firm for Maintenan 2. Component 2: Technical Single Stage - Two E Pending Impl ce of Books of Accounts and TF / 19308 assistance and capacity buil Post Request for Bids Open - National 32,000.00 0.00 2023-03-17 2023-03-29 2023-05-10 2023-07-23 2023-08-27 2025-03-31 nvelope ementation providing administrative and ding record keeping Services und er PRSF IN-SIDBI-346806-NC-RFB / Hi ring an agency for performin 2. Component 2: Technical g Measurement & Verificatio Single Stage - Two E Pending Impl TF / 19308 assistance and capacity buil Post Request for Bids Open - National 91,000.00 0.00 2023-03-02 2023-03-07 2023-04-18 2023-07-01 2023-08-05 2024-02-01 n (M&V) activities including E nvelope ementation ding nvironment & Social Safegua rd (E&SS) aspects under PRS F CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-151148-CS-CQS / M arketing and Promotion of PR 2. Component 2: Technical SF Facility and its Results thr Consultant Qualifi TF / 19308 assistance and capacity buil Post Open - National 45,000.00 0.00 Canceled 2020-01-30 2020-01-17 2020-02-09 2020-06-03 2020-02-29 2020-08-04 2020-03-10 2020-03-30 2020-09-26 ough Products such as Audio cation Selection ding Video Documentary Film, Mul timedia Presentations and bo oklets/pamphlets IN-SIDBI-155422-CS-QCBS / 2. Component 2: Technical Quality And Cost- Zone 1: Hiring of an agency f TF / 19308 assistance and capacity buil Post Open - National 150,000.00 0.00 Canceled 2020-02-10 2020-01-24 2020-03-09 2020-05-20 2020-04-16 2020-07-21 2020-05-16 2020-06-05 2020-07-18 2020-08-27 2021-08-27 Based Selection or generating pipeline in Zon ding e 1 States IN-SIDBI-155429-CS-QCBS / 2. Component 2: Technical Quality And Cost- Zone 2: Hiring of an agency f TF / 19308 assistance and capacity buil Post Open - National 150,000.00 0.00 Canceled 2020-02-10 2020-01-24 2020-03-09 2020-05-20 2020-04-16 2020-07-21 2020-05-16 2020-06-05 2020-07-18 2020-08-27 2021-08-27 Based Selection or pipeline generation in Zon ding e 2 States. IN-SIDBI-100763-CS-CDS / D esign & Development of Stan dard Product viz. Techno-Fin 2. Component 2: Technical ancial Analysis Tool for evalu Consultant Qualifi TF / 19308 assistance and capacity buil Post Open - National 70,000.00 0.00 Canceled 2020-05-22 2020-05-22 2020-06-12 2020-06-03 2020-07-26 2020-08-04 2020-08-25 2020-09-29 2020-11-22 ation of Energy Efficiency pro cation Selection ding jects by Participating Financi al Institutions (PFIs) and gen eration of pipelines for issuan ce of guarantee under PRSF Project IN-SIDBI-185402-CS-QBS / Z 2. Component 2: Technical one 1: Hiring of an agency fo Quality Based Sel TF / 19308 assistance and capacity buil Post Open - National 150,000.00 141,016.13 Completed 2020-08-17 2020-01-24 2020-09-07 2020-10-21 2020-08-27 2020-11-18 2020-11-04 2020-12-18 2020-12-30 2021-01-17 2021-02-25 2021-02-21 2021-04-07 2022-02-21 2022-04-06 r Generating pipeline of sub- ection ding projects under PRSF Project IN-SIDBI-185407-CS-QBS / Z 2. Component 2: Technical one 2: Hiring of an agency fo Quality Based Sel TF / 19308 assistance and capacity buil Post Open - National 150,000.00 119,329.08 Completed 2020-08-20 2020-01-24 2020-09-10 2020-10-24 2020-08-27 2020-11-21 2020-11-04 2020-12-21 2020-12-30 2021-01-20 2021-02-25 2021-02-24 2021-04-07 2022-02-24 2022-04-06 r Generating pipeline of sub- ection ding projects under PRSF Project IN-SIDBI-196292-CS-QCBS / Hiring of an agency for devel 2. Component 2: Technical oping Marketing and Promoti Quality And Cost- TF / 19308 assistance and capacity buil Post Open - National 95,000.00 33,590.06 Completed 2020-10-05 2020-10-16 2020-10-26 2020-11-09 2020-12-09 2020-12-30 2021-01-06 2021-03-03 2021-02-05 2021-04-01 2021-03-12 2021-05-12 2021-04-16 2021-07-14 2021-09-13 2022-03-01 on products such as Audio Vi Based Selection ding deo Film, Multimedia Present ations and Booklets covering PRSF Project. IN-SIDBI-874-CS-QCBS / PRS 2. Component 2: Technical Quality And Cost- F 13. Impact Assessment / Ev TF / 19308 assistance and capacity buil Post Open - National 100,000.00 0.00 Canceled 2017-08-01 2017-08-22 2017-10-05 2017-11-02 2017-12-02 2018-01-06 2018-02-10 2019-02-10 Based Selection aluation Study (Mid-Term & F ding inal) Page 1 IN-SIDBI-196300-CS-QCBS / Design & Development of Sta ndard Product viz. Techno-Fi 2. Component 2: Technical nancial Analysis Tool for eval Quality And Cost- TF / 19308 assistance and capacity buil Post Open - National 130,000.00 0.00 Canceled 2020-10-05 2020-03-11 2020-10-26 2020-11-09 2020-12-09 2020-12-30 2021-01-06 2021-02-05 2021-03-12 2021-04-16 2022-10-13 uation of Energy Efficiency pr Based Selection ding ojects by Participating Financ ial Institutions (PFIs) and gen eration of pipelines for issuan ce of guarantee under PRSF Project. IN-SIDBI-177161-CS-CQS / SI DBI is seeking the services of a reputed consulting agency 2. Component 2: Technical to assist SIDBI and EESL in D Consultant Qualifi TF / 19308 assistance and capacity buil Post Open - National 155,000.00 0.00 Canceled 2020-06-05 2020-07-05 2020-08-19 2020-09-18 2020-11-02 2021-11-02 esign and Development of Ec cation Selection ding osystem including document ations for Super ESCO Dema nd Aggregation Model and Is suance of Guarantees under PRSF Project. IN-SIDBI-229449-CS-QCBS / Legal agency for Developme nt of Standard ESPC Agreem 2. Component 2: Technical Quality And Cost- ents and other documents fo TF / 19308 assistance and capacity buil Post Open - National 85,000.00 0.00 Canceled 2021-04-26 2021-05-24 2021-05-26 2021-05-28 2021-07-09 2021-08-06 2021-09-05 2021-10-19 2021-11-30 2022-05-29 Based Selection r Energy Efficiency sub-proje ding ct implemented through Sup er ESCO Demand Aggregatio n Model IN-SIDBI-875-CS-QCBS / Hirin 2. Component 2: Technical Quality And Cost- g of Measurement & Verificat TF / 19308 assistance and capacity buil Post Open - National 220,000.00 0.00 Canceled 2017-04-01 2021-05-24 2017-04-22 2021-05-28 2017-06-05 2021-07-19 2017-07-03 2017-08-02 2017-09-06 2017-10-11 2018-10-11 Based Selection ion Agency (MVA) under PRS ding F project INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-SIDBI-878-CS-INDV / PRSF Component 1: Partial risk sh Individual Consult 16 (A). Hiring of Office Mana TF / 19308 Post Open - National 300,000.00 0.00 Canceled 2017-03-01 2017-04-19 2017-05-10 2017-06-14 2018-06-13 aring facility ant Selection ger / Office Executive IN-SIDBI-870-CS-CDS / PRSF- 2. Component 2: Technical 1. Marketing of PRSF scheme TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 12,698.58 Completed 2016-08-29 2016-08-29 2016-09-08 2017-01-23 2016-11-12 2017-02-03 2018-11-11 2018-06-15 - Awareness workshops inclu ding ding sponsoring the event / p rogram IN-SIDBI-872-CS-CDS / PRSF- 2. Component 2: Technical TF / 19308 Post Direct Selection Direct 100,000.00 11,215.32 Completed 2019-01-31 2015-02-23 2019-02-10 2015-03-19 2019-04-16 2015-04-01 2019-10-13 2015-09-24 5. Hiring of Legal Firm assistance and capacity buil ding IN-SIDBI-86268-CS-INDV / PR Component 1: Partial risk sh Pending Impleme SF 16C. Hiring of Expert Oper TF / 19308 Post Direct Selection Direct 17,600.00 0.00 2018-11-19 2018-11-29 2019-01-08 2020-01-08 aring facility ntation ations under the PRSF projec t. IN-SIDBI-92321-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 98,151.27 Completed 2018-12-21 2019-01-08 2018-12-31 2018-12-07 2019-01-23 2019-03-30 2020-01-23 2020-02-11 on for Building Sector. ding IN-SIDBI-92322-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 98,248.36 Completed 2018-12-21 2019-01-08 2018-12-31 2018-12-07 2019-01-23 2019-02-12 2020-01-18 2020-02-11 on for Industries sector. ding IN-SIDBI-92325-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 98,170.52 Completed 2018-12-28 2019-01-08 2019-01-07 2018-12-18 2019-01-27 2019-04-02 2020-01-27 2020-02-19 on for Municipalities. ding IN-SIDBI-92326-CS-CDS / Hiri 2. Component 2: Technical Individual Consult TF / 19308 Post Direct 65,000.00 64,152.00 Terminated 2019-01-14 2019-01-10 2019-01-27 2018-12-04 2019-02-06 2019-02-11 2019-03-03 2020-02-19 2020-03-02 ng of Chief Technical Speciali assistance and capacity buil ant Selection st ding IN-SIDBI-80059-CS-CDS / PR 2. Component 2: Technical SF 5B - External Audit of the TF / 19308 assistance and capacity buil Post Direct Selection Direct 897.00 844.29 Completed 2019-01-11 2018-11-01 2019-01-21 2018-10-01 2019-03-27 2018-11-05 2020-03-26 2019-01-14 PRSF project (FY 2017-18). ding IN-SIDBI-99536-CS-INDV / Hi Component 1: Partial risk sh Individual Consult TF / 19308 Post Open - National 100,000.00 60,500.11 Terminated 2019-02-07 2019-04-05 2019-03-13 2016-09-29 2019-03-23 2016-09-29 2019-04-08 2017-01-10 2021-04-07 ring of Lead Technical Expert aring facility ant Selection . IN-SIDBI-100747-CS-INDV / H Component 1: Partial risk sh Individual Consult TF / 19308 Post Open - National 100,000.00 72,488.13 Terminated 2019-02-14 2019-04-05 2019-03-20 2016-03-09 2019-03-30 2016-04-25 2019-04-15 2016-04-27 2021-05-04 iring of Senior Technical Exp aring facility ant Selection ert IN-SIDBI-100749-CS-CDS / Hi 2. Component 2: Technical ring of CA firm for maintenan TF / 19308 assistance and capacity buil Post Direct Selection Direct 10,000.00 8,418.91 Completed 2019-02-14 2016-01-01 2019-02-18 2016-02-02 2019-02-27 2016-02-22 2020-03-03 2019-02-21 ce of Books of Accounts and ding Providing Secretarial /Admini strative Services. IN-SIDBI-129278-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 55,000.00 44,630.64 Terminated 2019-09-02 2019-08-23 2019-10-10 2019-10-23 2019-10-20 2019-10-23 2019-11-05 2019-11-26 2021-11-04 iring of Technical Expert assistance and capacity buil ant Selection ding IN-SIDBI-129277-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 65,000.00 51,877.11 Signed 2019-09-02 2019-08-23 2019-10-10 2019-10-21 2019-10-20 2019-10-23 2019-11-05 2019-12-03 2021-11-04 iring of Procurement and Ad assistance and capacity buil ant Selection min Expert ding IN-SIDBI-151134-CS-INDV / H 2. Component 2: Technical Individual Consult IRING OF ENVIRONMENT AND TF / 19308 assistance and capacity buil Post Open - National 85,000.00 34,080.60 Signed 2020-02-07 2020-01-20 2020-03-26 2020-08-19 2020-04-10 2020-08-19 2020-05-13 2020-09-24 2022-05-13 ant Selection SOCIAL SAFEGUARD EXPERT ding IN-SIDBI-129275-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 60,000.00 50,583.52 Terminated 2019-09-02 2019-08-23 2019-10-10 2019-10-23 2019-10-20 2019-10-23 2019-11-05 2019-11-30 2021-11-04 iring of Experts Operations assistance and capacity buil ant Selection ding IN-SIDBI-129274-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 90,000.00 84,100.71 Signed 2019-09-02 2019-08-23 2019-10-10 2019-10-14 2019-10-20 2019-11-05 2020-01-07 2021-11-04 iring of Lead Technical Exper assistance and capacity buil ant Selection t ding IN-SIDBI-129243-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 151,000.00 218,024.05 Terminated 2019-09-02 2019-08-23 2019-10-10 2019-10-23 2019-10-20 2019-10-23 2019-11-05 2019-10-25 2021-11-04 iring of Chief Technical Speci assistance and capacity buil ant Selection alist. ding IN-SIDBI-1009-CS-INDV / PRS Component 1: Partial risk sh Individual Consult F 16A. Hiring of Technical Ex TF / 19308 Post Open 300,000.00 0.00 Canceled 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2018-06-12 aring facility ant Selection perts (Environment) IN-SIDBI-92330-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-01-11 2019-01-24 2019-01-26 2019-04-02 2019-09-29 on in selected 10 clusters (Zo ding ne:1) Page 2 IN-SIDBI-92332-CS-CDS / ES 2. Component 2: Technical CO projects pipeline generati TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2019-01-11 2019-01-24 2019-01-26 2019-04-02 2019-09-29 on in selected 10 clusters (Zo ding ne:2) IN-SIDBI-225805-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open 72,000.00 73,113.83 Signed 2021-03-30 2021-04-06 2021-07-03 2021-05-18 2021-07-23 2021-06-23 2021-09-11 2021-07-16 2023-09-11 iring of Senior Technical Exp assistance and capacity buil ant Selection ert ding IN-SIDBI-225807-CS-INDV / H 2. Component 2: Technical Individual Consult iring of Environment & Social TF / 19308 assistance and capacity buil Post Open 85,000.00 73,113.83 Signed 2021-03-30 2021-04-06 2021-07-03 2021-05-18 2021-07-23 2021-06-23 2021-09-11 2021-07-16 2023-09-11 ant Selection Safeguard Expert ding IN-SIDBI-1012-CS-CDS / PRS 2. Component 2: Technical F-8A. Training of PFIs - Condu TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2018-04-02 2018-04-12 2018-06-16 2019-06-15 cting Classroom Training ding IN-SIDBI-871-CS-CDS / PRSF- 2. Component 2: Technical 3. Development of appraisal / TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2016-09-30 2016-10-10 2016-12-14 2017-06-12 due diligence tool for PFIs ding IN-SIDBI-1006-CS-CDS / PRS 2. Component 2: Technical F- 1A. Marketing of PRSF sch TF / 19308 assistance and capacity buil Post Direct Selection Direct 50,000.00 0.00 Canceled 2019-04-01 2019-04-11 2019-06-15 2020-06-14 eme - Awareness workshops ding including sponsoring the eve nt / program IN-SIDBI-80070-CS-CDS / PR 2. Component 2: Technical SF - 5C - Internal Financial Au TF / 19308 assistance and capacity buil Post Direct Selection Direct 1,860.00 0.00 Canceled 2018-11-19 2018-11-29 2019-02-02 2020-02-02 dit and Operational Audit for ding PRSF (FY 2018-19). IN-SIDBI-129280-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 40,000.00 0.00 Canceled 2019-09-02 2019-08-23 2019-10-10 2019-10-14 2019-10-20 2019-11-05 2021-11-04 iring of Technical Executive assistance and capacity buil ant Selection ding IN-SIDBI-876-CS-INDV / PRSF 2. Component 2: Technical Individual Consult TF / 19308 Post Open - National 200,000.00 0.00 Canceled 2016-09-01 2016-10-20 2016-11-10 2016-12-15 2017-12-14 -6. Hiring of Chief Technical S assistance and capacity buil ant Selection pecialist ding IN-SIDBI-1014-CS-CDS / PRS 2. Component 2: Technical F-8 C. Training of PFIs - Cond TF / 19308 assistance and capacity buil Post Direct Selection Direct 66,000.00 0.00 Canceled 2021-04-01 2021-04-11 2021-06-15 2022-06-14 ucting Classroom Training ding IN-SIDBI-1013-CS-CDS / PRS 2. Component 2: Technical F-8 B. Training of PFIs - Cond TF / 19308 assistance and capacity buil Post Direct Selection Direct 66,000.00 0.00 Canceled 2020-04-02 2020-04-12 2020-06-16 2021-06-15 ucting Classroom Training ding IN-SIDBI-1011-CS-INDV / PRS Component 1: Partial risk sh Individual Consult TF / 19308 Post Open 200,000.00 0.00 Canceled 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2018-06-12 F 16 B. Hiring of Technical Ex aring facility ant Selection perts IN-SIDBI-877-CS-INDV / PRSF Component 1: Partial risk sh Individual Consult 16. Hiring of Technical Expert TF / 19308 Post Open - National 300,000.00 0.00 Canceled 2017-02-28 2017-04-18 2017-05-09 2017-06-13 2018-06-12 aring facility ant Selection s (Energy) IN-SIDBI-151152-CS-CQS / In 2. Component 2: Technical ternational Conference on im TF / 19308 assistance and capacity buil Post Direct Selection Direct 40,000.00 0.00 Canceled 2019-12-20 2020-01-19 2020-02-13 2020-08-11 plementation of Energy Effici ding ency Projects through ESCO mode IN-SIDBI-225801-CS-INDV / H 2. Component 2: Technical Individual Consult TF / 19308 Post Open 60,000.00 0.00 Canceled 2021-03-30 2021-04-06 2021-07-03 2021-06-14 2021-07-23 2021-09-11 2023-09-11 iring of Expert Operations assistance and capacity buil ant Selection ding IN-SIDBI-873-CS-CDS / PRSF- 2. Component 2: Technical 8. Training of PFIs - Conducti TF / 19308 assistance and capacity buil Post Direct Selection Direct 100,000.00 0.00 Canceled 2016-08-31 2016-09-16 2016-09-10 2016-11-14 2017-11-13 ng Classroom Training ding IN-SIDBI-1008-CS-CDS / PRS 2. Component 2: Technical TF / 19308 Post Direct Selection Direct 50,000.00 0.00 Canceled 2021-04-01 2021-04-11 2021-06-15 2021-12-12 F-5A. Hiring of Legal Firm assistance and capacity buil ding IN-SIDBI-251297-CS-CDS / Hi 2. Component 2: Technical ring of CA firm for maintenan TF / 19308 assistance and capacity buil Post Direct Selection Direct 40,000.00 0.00 Under Review 2021-09-05 2019-02-15 2021-09-09 2021-09-18 2024-09-17 ce of Books of Accounts and ding Providing Secretarial / Admini strative Services. IN-SIDBI-273146-CS-CDS / Hi ring of Legal agency for Deve lopment of Standard Energy 2. Component 2: Technical Saving Performance Contract Under Implement TF / 19308 assistance and capacity buil Post Direct Selection Direct 60,000.00 0.00 2022-02-01 2021-04-02 2022-02-11 2022-04-17 2022-09-14 Agreements and other docu ation ding ments for Energy Efficiency s ub-project implemented thro ugh Super ESCO based Dema nd Aggregation Model IN-SIDBI-297288-CS-INDV / P 2. Component 2: Technical Individual Consult Under Implement TF / 19308 Post Open - National 55,000.00 0.00 2022-06-01 2022-06-06 2022-07-16 2022-07-26 2022-08-20 2023-08-20 rocurement & Admin Expert assistance and capacity buil ant Selection ation Hiring ding IN-SIDBI-305836-CS-INDV / S eeking to hire the services of 5 nos. of Technical Officers, o 2. Component 2: Technical Individual Consult Under Implement n contract basis, to undertak TF / 19308 assistance and capacity buil Post Open - National 90,000.00 0.00 2022-07-25 2022-08-01 2022-09-08 2022-09-18 2022-10-13 2023-10-13 ant Selection ation e several tasks related to de ding veloping the market of energ y services Officers under PRS F Project IN-SIDBI-364598-CS-INDV / H 2. Component 2: Technical Individual Consult Pending Impleme iring 06 Experts / Consultants TF / 19308 assistance and capacity buil Post Open - National 225,000.00 0.00 2023-06-07 2023-07-26 2023-08-16 2023-09-20 2024-03-18 ant Selection ntation Under PRSF Scheme ding Page 3 PROCUREMENT PLAN (Textual Part) Project information: [Ghana] [Ghana Productive Safety Net Project 2 (GPSNP 2) [P-175588] Project Implementation agency: [Ministry of Gender, Children and Social Protection (MoGCSP) and Ministry of Local Government, Decentralisation and Rural Development (MLGDRD) Date of the Procurement Plan: [26/02/2021] Period covered by this Procurement Plan: [01 July 2021 – 31 December 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement Act, 2003 (Act 663) which was amended in 2016 by the Public Procurement (Amendment) Act, 2016, (Act 914), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 56 (1) Tenders shall be opened (a) at the time specified in the tender documents as the deadline for the submission of tenders or at the deadline specified in any extension of the deadline; and (b) at the place and in accordance with the procedures specified the tender documents. (2) The time for opening of the tenders shall be the same as the deadline for the receipt of the tenders or promptly after that deadline. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. Procedures for CDD components: Community Driven Development (CDD) activities are works activities, which are carried out directly by communities. Procurement of Materials Procurement of materials for the activities would be done through the procurement method limited- open. The activities to be carried out: i. Issuance of Request for quotation (at least 3 bidders); ii. Submission and opening of bids for bidders; iii. Evaluation of bids iv. Issuance of Acceptance Letters; v. Signing of Contracts Selection of Community Members Selection of communities to participate in the CDD activities shall be done through direct selection procurement method. Agreement is then signed between the Implementation Agencies (Municipals and District Assemblies) to cover the duration of the activity. PROCUREMENT Ghana : Ghana Productive Safety Net Project 2 PLAN General Information Country: Ghana 2021-03-01 Bank’s Approval Date of the Original Procurement Plan: 2023-05-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175588 GPN Date: Project Name: Ghana Productive Safety Net Project 2 Loan / Credit No: IDA / 68590 MINISTRY OF LOCAL GOVERNMENT AND RURAL DEVELOPMENT - RCU Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GH-MLGRD-RCU-334785-CW Request for Quota -RFQ / Rehabilitation of Abon Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 IDA / 68590 Post Open - National 72,000.00 0.00 2023-03-05 2023-04-30 gokrom -Tiabante - Owusukr Program tions nvelope s (Emergency) SP lementation 9 om Feeder Road (5.50km) D -Competitive Request for Quota GH-MLGRD-RCU-334788-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Yabe IDA / 68590 Post Open - National 70,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 neagya - Kwamekuma Feede D -Competitive r Road (3.50km) GH-MLGRD-RCU-334790-CW Request for Quota -RFQ / Rehabilitation of Sunk Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 wa -Tenso-Onwe-Dinkyini Fee Program tions nvelope s (Emergency) SP lementation 8 der Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-334791-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Derm IDA / 68590 Post Open - National 33,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 a - Monta Feeder Road (2.50 D -Competitive km) GH-MLGRD-RCU-334792-CW Request for Quota -RFQ / Rehabilitation of New Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 23,500.00 0.00 2023-03-05 2023-04-09 Bosankro - Akuraadadaa-Man Program tions nvelope s (Emergency) SP mentation 8 hutem Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-334793-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Drom IDA / 68590 Post Open - National 69,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ankuma -Fakawa Feeder Roa D -Competitive d (4.50km) GH-MLGRD-RCU-334794-CW Request for Quota -RFQ / Rehabilitation of Nkwa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 48,000.00 0.00 2023-03-05 2023-04-09 nta Farm Jnc.-Hiawoanwu Fe Program tions nvelope s (Emergency) SP lementation 8 eder Road (4.2km) D -Competitive Request for Quota GH-MLGRD-RCU-336045-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Abes IDA / 68590 Post Open - National 44,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ewa-Databi Feeder Road (4.4 D -Competitive km) Request for Quota GH-MLGRD-RCU-336046-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bons IDA / 68590 Post Open - National 54,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ukrom Jnc.-Adense Feeder Ro D -Competitive ad (5.0km) Request for Quota GH-MLGRD-RCU-336047-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Srent IDA / 68590 Post Open - National 36,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 iantia-Abrofoa Feeder Road ( D -Competitive 2.50km) GH-MLGRD-RCU-336049-CW Request for Quota -RFQ / Rehabilitation of Yebo Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 67,500.00 0.00 2023-03-05 2023-04-09 ah Apatam - Nsuguasua Feed Program tions nvelope s (Emergency) SP mentation 8 er Road (5.70km) D -Competitive GH-MLGRD-RCU-336050-CW Request for Quota -RFQ / Rehabilitation of Ayaa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 kwa Junction-Bebeduaso Fee Program tions nvelope s (Emergency) SP lementation 8 der Road(4.50km) D -Competitive GH-MLGRD-RCU-336051-CW Request for Quota -RFQ / Rehabilitation of Mang Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 51,000.00 0.00 2023-03-05 2023-04-09 oase Jnc -Akyease - Mpentua Program tions nvelope s (Emergency) SP mentation 8 se Feeder Road (4.0km) D -Competitive GH-MLGRD-RCU-336052-CW Request for Quota -RFQ / Rehabilitation of Hani- Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 64,400.00 0.00 2023-03-05 2023-04-09 Proposed Tourist Site (Gbeho Program tions nvelope s (Emergency) SP mentation 8 ) Feeder Road (3.50km) D -Competitive Request for Quota GH-MLGRD-RCU-336053-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Mire IDA / 68590 Post Open - National 83,800.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 mano -Berekumkroaso Feede D -Competitive r Road (5.50km) GH-MLGRD-RCU-336054-CW Request for Quota -RFQ / Rehabilitation of Nwoa Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 69,000.00 0.00 2023-03-05 2023-04-09 se - Seiduakuraa - Aboabo Fe Program tions nvelope s (Emergency) SP mentation 8 eder Road (4.80km) D -Competitive Request for Quota GH-MLGRD-RCU-336055-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Sikaa IDA / 68590 Post Open - National 58,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 -Wansamkuraa Feeder Road D -Competitive (5.0km) Request for Quota GH-MLGRD-RCU-336330-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Akru IDA / 68590 Post Open - National 56,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ma - Bobrobo Feeder Road (3 D -Competitive .80km) Request for Quota GH-MLGRD-RCU-336331-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation Of Kobe IDA / 68590 Post Open - National 80,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 da No. 1 - Kobeda No. 2 Feed D -Competitive er Road (5.80km) Request for Quota GH-MLGRD-RCU-336336-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bami IDA / 68590 Post Open - National 70,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ra - Asantanso Feeder Road ( D -Competitive 5.70km) Request for Quota GH-MLGRD-RCU-336341-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tawia IDA / 68590 Post Open - National 53,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kwaa-Annan Feeder Road (3. D -Competitive 1km) Page 1 Request for Quota GH-MLGRD-RCU-336342-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Enyis IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 am - Takyiman Feeder Road ( D -Competitive 3.5km) Request for Quota GH-MLGRD-RCU-336343-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Yaw IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Duodo-Kobiso Feeder Road ( D -Competitive 3.9km) Request for Quota GH-MLGRD-RCU-336344-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kwab IDA / 68590 Post Open - National 51,100.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 oadi No.2-Aboso Jnc. Feeder D -Competitive Road (4.7km) GH-MLGRD-RCU-336345-CW Request for Quota -RFQ / Rehabilitation of Sema Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 75,000.00 0.00 2023-03-05 2023-04-09 nhyia-Kyeame Kissi-Kyemfre Program tions nvelope s (Emergency) SP mentation 8 Feeder Road (10.60km) D -Competitive GH-MLGRD-RCU-336346-CW Request for Quota -RFQ / Rehabilitation of Mota Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 46,000.00 0.00 2023-03-05 2023-04-09 Afarikrom-Nkwaakwaasem F Program tions nvelope s (Emergency) SP mentation 8 eeder Road (2.4km) D -Competitive Request for Quota GH-MLGRD-RCU-336347-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Agog IDA / 68590 Post Open - National 62,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 o-Okyerekrom Feeder Road ( D -Competitive 3.1km) Request for Quota GH-MLGRD-RCU-336348-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Akrus IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 u Jnc.-Asekeso Feeder Road ( D -Competitive 3.64km) Request for Quota GH-MLGRD-RCU-336349-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Wate IDA / 68590 Post Open - National 29,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 r Works Jnc.-Muerter Feeder D -Competitive Road (1.5km) Request for Quota GH-MLGRD-RCU-336350-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dave IDA / 68590 Post Open - National 41,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 -Gbleve Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-336352-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Adze IDA / 68590 Post Open - National 66,400.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kofe Jnc.-Adzekofe Feeder Ro D -Competitive ad (3.95km) Request for Quota GH-MLGRD-RCU-336354-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tsrib IDA / 68590 Post Open - National 62,400.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ormi-Kesenyemito Feeder Ro D -Competitive ad (4.2km) Request for Quota GH-MLGRD-RCU-336355-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation Of Kped IDA / 68590 Post Open - National 44,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ze Tordze-Anagokope Feeder D -Competitive Road (1.8km) Request for Quota GH-MLGRD-RCU-336356-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Duku IDA / 68590 Post Open - National 77,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ma Tsrukpe-Zanukope Feede D -Competitive r Road (4.6km) Request for Quota GH-MLGRD-RCU-336549-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 7 Earth Dam at Adaklu Torda D -Competitive GH-MLGRD-RCU-336551-CW Request for Quota -RFQ / Rehabilitation of Korsi Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 36,000.00 0.00 2023-03-05 2023-04-09 ve Jnc.-Cashew Plantation Sit Program tions nvelope s (Emergency) SP mentation 8 e Feeder Road (2.0km) D -Competitive Request for Quota GH-MLGRD-RCU-336555-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Ladu IDA / 68590 Post Open - National 60,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 mdo-Nalogni-Tindando Feede D -Competitive r Road 5.00km Request for Quota GH-MLGRD-RCU-336557-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2023-10-2 -RFQ / Construction of Paralle IDA / 68590 Post Open - National 50,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 7 l Drain at Wulensi Dam D -Competitive Request for Quota GH-MLGRD-RCU-336559-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Mpah IDA / 68590 Post Open - National 27,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 a-Chukonto Feeder Road (2.0 D -Competitive 0 km) Request for Quota GH-MLGRD-RCU-336561-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Naku IDA / 68590 Post Open - National 81,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 nga Jnt - Nakunga Feeder Ro D -Competitive ad (5.0km) Request for Quota GH-MLGRD-RCU-336562-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gbanl IDA / 68590 Post Open - National 84,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ua - Ditani Feeder Road (6.5k D -Competitive m) Request for Quota GH-MLGRD-RCU-336564-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kumoayili D -Competitive Request for Quota GH-MLGRD-RCU-336566-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Bagli IDA / 68590 Post Open - National 51,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 - Bagkurli Feeder Road (3.5k D -Competitive m) Request for Quota GH-MLGRD-RCU-336567-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Nant IDA / 68590 Post Open - National 76,700.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 on - Yapalsi Feeder Road (4. D -Competitive 8km) Request for Quota GH-MLGRD-RCU-336569-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Nach IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 amba No. 2 - Tatale Feeder D -Competitive Road (5.2km) Request for Quota GH-MLGRD-RCU-336570-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 55,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Nanton Kurugu D -Competitive Request for Quota GH-MLGRD-RCU-336581-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gork IDA / 68590 Post Open - National 61,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ugani- Natindo Feeder Road ( D -Competitive 5.0km) Page 2 Request for Quota GH-MLGRD-RCU-336584-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 92,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kuyuli D -Competitive Request for Quota GH-MLGRD-RCU-336585-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam At Kpalgigbeni D -Competitive Request for Quota GH-MLGRD-RCU-336588-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 Earth Dam at Kuyuli D -Competitive Request for Quota GH-MLGRD-RCU-336589-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 55,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Nanton Kurugu D -Competitive Request for Quota GH-MLGRD-RCU-336590-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 91,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Buegmal D -Competitive Request for Quota GH-MLGRD-RCU-336591-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dika- IDA / 68590 Post Open - National 60,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Ahamansu Feeder Roads (4.0 D -Competitive km) Ph2 Request for Quota GH-MLGRD-RCU-336592-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kachi IDA / 68590 Post Open - National 44,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 nke-Lugnuldo Feeder Road 2. D -Competitive 60 Km GH-MLGRD-RCU-336593-CW Request for Quota -RFQ / Rehabilitation of Pechi Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 65,000.00 0.00 2023-03-05 2023-04-09 Akura Jnt. - Ahiamankyene F Program tions nvelope s (Emergency) SP mentation 8 eeder Road (5.0km D -Competitive Request for Quota GH-MLGRD-RCU-336594-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Tsafo IDA / 68590 Post Open - National 71,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 kura Jnc. - Tsafokura Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-336595-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Grubi IDA / 68590 Post Open - National 58,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 - Akaniem Feeder Road (4.0 D -Competitive km) GH-MLGRD-RCU-336596-CW Request for Quota -RFQ / Rehabilitation of Mam Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 IDA / 68590 Post Open - National 49,000.00 0.00 2023-03-05 2023-04-09 a Kura- Hundokope Feeder R Program tions nvelope s (Emergency) SP mentation 8 oad(3.0km) Phase 2 D -Competitive Request for Quota GH-MLGRD-RCU-336597-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kito- IDA / 68590 Post Open - National 48,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Kito Nkwanta Feeder Road 4. D -Competitive 6km Request for Quota GH-MLGRD-RCU-336598-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Fuu. - IDA / 68590 Post Open - National 83,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 Takpli Feeder Road (6.7km) D -Competitive Request for Quota GH-MLGRD-RCU-336600-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Bonb IDA / 68590 Post Open - National 29,000.00 0.00 2023-03-05 2023-03-14 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ontey Jnc - Bonbontey Feeder D -Competitive (1.50km) Request for Quota GH-MLGRD-RCU-336601-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Noko IDA / 68590 Post Open - National 48,500.00 0.00 2023-03-05 2023-03-15 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 yiri - Samariyiri Feeder Road D -Competitive (2.50km) Request for Quota GH-MLGRD-RCU-336602-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation Of Mank IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 arigu-Sakpala-Kpatarigu Fee D -Competitive der Road (4.5km) Request for Quota GH-MLGRD-RCU-336604-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Kagb IDA / 68590 Post Open - National 85,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 al Small Earth Dam D -Competitive Request for Quota GH-MLGRD-RCU-336616-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Moyir IDA / 68590 Post Open - National 77,800.00 0.00 2023-03-05 2023-03-15 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 i - Konzokala Feeder Road (4. D -Competitive 5km) Request for Quota GH-MLGRD-RCU-336636-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kont IDA / 68590 Post Open - National 77,400.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 wiri - Chachaa Feeder Road ( D -Competitive 3.5km) Request for Quota GH-MLGRD-RCU-336637-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Kohu IDA / 68590 Post Open - National 77,800.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 o - Pina Feeder Road (4.7km) D -Competitive Request for Quota GH-MLGRD-RCU-336640-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 85,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 Earth Dam at Boo D -Competitive Request for Quota GH-MLGRD-RCU-336641-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Furo - IDA / 68590 Post Open - National 42,100.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Gbier Feeder Road (2.5km) D -Competitive Request for Quota GH-MLGRD-RCU-336644-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Goli - IDA / 68590 Post Open - National 64,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 Kaabogu Feeder Road (3.35k D -Competitive m) Request for Quota GH-MLGRD-RCU-336648-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Domi IDA / 68590 Post Open - National 36,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ngye - Nabugangn Feeder Ro D -Competitive ad (2.2km) Request for Quota GH-MLGRD-RCU-336649-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Guo IDA / 68590 Post Open - National 43,400.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 mwaane - Hayore Feeder Ro D -Competitive ad (2.5km) Request for Quota GH-MLGRD-RCU-336652-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Puze IDA / 68590 Post Open - National 78,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ne-Boo Feeder Road (6.6km) D -Competitive Page 3 Request for Quota GH-MLGRD-RCU-336656-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-0 -RFQ / Rehabilitation of Dorn IDA / 68590 Post Open - National 98,000.00 0.00 2023-03-05 2023-03-16 2023-04-09 Program tions nvelope s (Emergency) SP mentation 8 ye - Dorkyire Feeder Road (5. D -Competitive 0km) Request for Quota GH-MLGRD-RCU-337227-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Wiidi- IDA / 68590 Post Open - National 76,900.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 Kukanga-Buzunde Feeder Ro D -Competitive ad (5.8km) Request for Quota GH-MLGRD-RCU-337229-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gund IDA / 68590 Post Open - National 76,200.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ago- Gbango-Kansogo Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-337232-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Samb IDA / 68590 Post Open - National 80,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 oliga-Agatuse Feeder Road (3 D -Competitive .7km) Request for Quota GH-MLGRD-RCU-337234-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Nayo IDA / 68590 Post Open - National 75,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ko No. 2 - Gore Clinic Feeder D -Competitive Road (5.5km) Request for Quota GH-MLGRD-RCU-337235-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Aniisi IDA / 68590 Post Open - National 58,500.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 - Belimpiisi Feeder Road (3.5 D -Competitive km) Request for Quota GH-MLGRD-RCU-337236-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Sana IDA / 68590 Post Open - National 87,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 biisi -Kabre - Akulyor Feeder D -Competitive Road (5.0km) GH-MLGRD-RCU-337237-CW Request for Quota -RFQ / Rehabilitation of Akuy Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-09 elingo - Tingre -Wegurigo Fee Program tions nvelope s (Emergency) SP lementation 8 der Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-337238-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Donin IDA / 68590 Post Open - National 68,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ga - Banyangsa Feeder Road D -Competitive (4.0km) Request for Quota GH-MLGRD-RCU-337239-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gban IDA / 68590 Post Open - National 84,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 koni - Nanjong No. 2 Feeder D -Competitive Road (6.9km) Request for Quota GH-MLGRD-RCU-337240-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Natur IDA / 68590 Post Open - National 77,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 i -Tichangu Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-337242-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Natur IDA / 68590 Post Open - National 65,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 i Junc- Naturi Feeder Road (3. D -Competitive 4km) Request for Quota GH-MLGRD-RCU-337243-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Gam IDA / 68590 Post Open - National 84,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 baga - Zimasa Feeder Road ( D -Competitive 5.0km) Request for Quota GH-MLGRD-RCU-337244-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Song IDA / 68590 Post Open - National 81,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 o-Songure Feeder Road (5.0k D -Competitive m) Request for Quota GH-MLGRD-RCU-337246-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Farfa IDA / 68590 Post Open - National 83,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 r- Walkman Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-337247-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Jade IDA / 68590 Post Open - National 86,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ma-Buyinga Feeder Road (5. D -Competitive 4km) Request for Quota GH-MLGRD-RCU-337249-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Kulsa IDA / 68590 Post Open - National 51,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 lboug - Zanlerigu Feeder Ro D -Competitive ad (2.1 Km) GH-MLGRD-RCU-337250-CW Request for Quota -RFQ / Rehabilitation of Zopel Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 IDA / 68590 Post Open - National 71,000.00 0.00 2023-03-05 2023-04-09 iga - Dagliga Basic School Fe Program tions nvelope s (Emergency) SP lementation 8 eder Road (4.0km) D -Competitive Request for Quota GH-MLGRD-RCU-337251-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Ajeng IDA / 68590 Post Open - National 71,300.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 o Natinga- Tesnatinga Feede D -Competitive r Road (4.3km) Request for Quota GH-MLGRD-RCU-337252-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Pwal IDA / 68590 Post Open - National 58,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ugu-Manpelugu Feeder Road D -Competitive (3.5km) Request for Quota GH-MLGRD-RCU-337253-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Wink IDA / 68590 Post Open - National 66,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ongo-Dapore Feeder Road (4. D -Competitive 0km) Request for Quota GH-MLGRD-RCU-337254-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-0 -RFQ / Rehabilitation of Imigr IDA / 68590 Post Open - National 79,100.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP lementation 8 ation Junc- Tafakwan Feeder D -Competitive Road (5.0km) Request for Quota GH-MLGRD-RCU-337256-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 24,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 arth Dam at Nayorku D -Competitive Request for Quota GH-MLGRD-RCU-337257-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 79,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 arth Dam at Agargo D -Competitive Request for Quota GH-MLGRD-RCU-337258-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 22,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 9 arth Dam at Mangor D -Competitive Request for Quota GH-MLGRD-RCU-337260-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-04-2 -RFQ / Completion of Small E IDA / 68590 Post Open - National 68,500.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 9 arth Dam at Namongo D -Competitive Page 4 Request for Quota GH-MLGRD-RCU-336599-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 127,000.00 0.00 2023-03-05 2023-03-15 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Sornyo D -Competitive Request for Quota GH-MLGRD-RCU-336619-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 137,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dapuoha D -Competitive Request for Quota GH-MLGRD-RCU-337262-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 111,000.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dagubaa D -Competitive Request for Quota GH-MLGRD-RCU-337261-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 170,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Dagbigu D -Competitive Request for Quota GH-MLGRD-RCU-336651-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 111,400.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Bakwalla D -Competitive Request for Quota GH-MLGRD-RCU-336617-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 170,800.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Nakpala D -Competitive Request for Quota GH-MLGRD-RCU-336642-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 102,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Gbankor D -Competitive Request for Quota GH-MLGRD-RCU-336657-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 128,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Janbob D -Competitive Request for Quota GH-MLGRD-RCU-336639-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 176,500.00 0.00 2023-03-05 2023-04-30 Program tions nvelope s (Emergency) SP lementation 1 Earth Dam at Hachagagan D -Competitive Request for Quota GH-MLGRD-RCU-336618-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation Of Smal IDA / 68590 Post Open - National 132,600.00 0.00 2023-03-05 2023-03-15 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 l Earth Dam at Saapari D -Competitive Request for Quota GH-MLGRD-RCU-336653-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 174,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Nyentie D -Competitive Request for Quota GH-MLGRD-RCU-336654-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 148,000.00 0.00 2023-03-05 2023-03-16 2023-04-30 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Sogla D -Competitive GH-MLGRD-RCU-334786-CW Request for Quota -RFQ / Rehabilitation of Amo Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-12-3 IDA / 68590 Post Open - National 64,000.00 0.00 2023-03-05 2023-04-30 maso -Ninkyeama - Sentaso Program tions nvelope s (Emergency) SP lementation 1 Feeder Road (5.20km) D -Competitive Request for Quota GH-MLGRD-RCU-336334-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2024-12-3 -RFQ / Rehabilitation of Kofi IDA / 68590 Post Open - National 92,000.00 0.00 2023-03-05 2023-04-09 Program tions nvelope s (Emergency) SP mentation 1 Djankrom - Kakraka Feeder R D -Competitive oad(6.30km) GH-MLGRD-RCU-337255-CW Request for Quota -RFQ / Rehabilitation of Bimb Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2025-01-3 IDA / 68590 Post Open - National 83,400.00 0.00 2023-04-05 2023-05-10 ago-Gbingbalanchet Phase 1 Program tions nvelope s (Emergency) SP lementation 1 Feeder Road (5.0km) D -Competitive Request for Quota GH-MLGRD-RCU-341117-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-02-1 -RFQ / Rehabilitation of Nako IDA / 68590 Post Open - National 113,500.00 0.00 2023-04-05 2023-05-31 Program tions nvelope s (Emergency) SP mentation 1 re - Kpongu Feeder Road (5.0 D -Competitive km) Request for Quota GH-MLGRD-RCU-341120-CW Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Under Imple 2025-02-1 -RFQ / Rehabilitation of Small IDA / 68590 Post Open - National 132,000.00 0.00 2023-04-05 2023-05-31 Program tions nvelope s (Emergency) SP mentation 1 Earth Dam at Bokpieriyiri D -Competitive GH-MLGRD-RCU-365594-CW -RFQ / Construction of On-sit e Creches and Temporary Toi lets for CCMI Nurseries and Pl Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 antations for Builsa South, B IDA / 68590 Post Open - National tions (Non Bank-S 32,000.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 uilsa North Municipal, Bongo, PD) Talensi, Nabdam, Bawku Wes t , Binduri, Bawku Municipal, Pusiga, Tempane and Garu Districts by the UERCC GH-MLGRD-RCU-365602-CW -RFQ / Construction of Fencin g for CCMI Nurseries and Pla Request for Quota ntations sites (119.3 Ha) for Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 IDA / 68590 Post Open - National tions (Non Bank-S 131,664.00 0.00 2023-07-02 2023-08-27 Builsa South, Builsa North Mu Program tions nvelope lementation 3 PD) nicipal, Bongo, Talensi, Nabd am, Bawku West ,Binduri, Ba wku Municipal, Pusiga, Temp ane and Garu Districts by th e UERCC. GH-MLGRD-RCU-365610-CW -RFQ / Construction of Boreh oles for CCMI Nurseries and P lantations for Builsa South, B Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 uilsa North Municipal, Bongo, IDA / 68590 Post Open - National tions (Non Bank-S 50,909.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 Talensi, Nabdam, Bawku Wes PD) t, Bawku Municipal, Binduri, Garu, Pusiga, Tempane, Bunk prugu, East mamprusi, and o ther Districts in UERCC. GH-MLGRD-RCU-365627-CW -RFQ / Construction of On-sit e Creches & Temporary Toile Request for Quota ts for CCMI Nurseries and Pla Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 IDA / 68590 Post Open - National tions (Non Bank-S 12,273.00 0.00 2023-07-02 2023-08-27 ntations for Mamprugu Moag Program tions nvelope lementation 3 PD) duri, East Mamprusi Municipa l, Bunkpurugu-Nakpanduri an d Yunyoo-Nasuan Districts by the NERCC Page 5 GH-MLGRD-RCU-365630-CW -RFQ / Construction of Fence for CCMI Nurseries and Plant Request for Quota Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-02-2 ations for Mamprugu Moagdu IDA / 68590 Post Open - National tions (Non Bank-S 4,727.00 0.00 2023-07-02 2023-08-27 Program tions nvelope lementation 3 ri, East Mamprusi Municipal, PD) Bunkpurugu - Nakpanduri an d Yunyoo-Nasuan Districts by the NERCC GH-MLGRD-RCU-364275-GO- RFQ / Supply of materials for Request for Quota concrete works for the rehabi Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Imp 2024-01-2 IDA / 68590 Post Open - National tions (Non Bank-S 17,497.00 0.00 2023-06-25 2023-08-01 litation of 10ha degraded co Program tions nvelope lementation 8 PD) mmunal land and developme nt of watershed, facility at Ns esresu - concrete works GH-MLGRD-RCU-365584-CW Request for Quota -RFQ / Construction of 3 No. Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-2 Ancillary structures (On - site IDA / 68590 Post Open - National 4,910.00 0.00 2023-07-02 2023-08-27 Program tions nvelope s (Emergency) SP lementation 3 Creche and Temporary toilet) D -Competitive at Liati Soba and Ve Deme in Afadzato District GH-MLGRD-RCU-367456-CW -RFQ / Construction of on-site Request for Quota Creches and Temporary Toile Labor-Intensive Public Works Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-02-2 t for Kpandai, Gushegu, Nanu IDA / 68590 Post Open - National 29,444.00 0.00 2023-07-01 2023-08-26 Program tions nvelope s (Emergency) SP lementation 2 mba South, Saboba Tatale - D -Competitive Sanguli, Zabzugu, Karaga, Mi on and Nanton District Asse mblies. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-220729-GO- RFB / Procurement of 500 No Productive Inclusion Progra Single Stage - One E IDA / 68590 Post Request for Bids Open - National 300,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-17 2022-08-12 2022-11-21 2023-02-19 . tablets with Biometric Scan m nvelope ners for LIPW and PI Activitie s GH-MLGRD-RCU-286190-GO- RFB / Supply and Delivery of Labor-Intensive Public Works Single Stage - One E 294 All-Terrain Motorbikes fo IDA / 68590 Post Request for Bids Open - National 420,000.00 0.00 Completed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-03-25 Program nvelope r Labour Intensive Public Wor ks (LIPW) and Productive Incl usion (PI) Monitoring Activitie s GH-MLGRD-RCU-220725-GO- RFB / Supply and Delivery of 7No. Photocopiers, 175 0No. Productive Inclusion Progra Single Stage - One E Printers, 175 Scanners, 5 Des IDA / 68590 Post Request for Bids Open - National 885,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-02-23 m nvelope ktops, 195 No. Laptops, 5 No. Projectors, 6 Digital Cameras and 5 No. Commercial Drone s GH-MLGRD-RCU-220726-GO- Project Management, Coordi RFB / Procurement of 8No. 4 Single Stage - One E IDA / 68590 nation, and Institutional Stre Post Request for Bids Open - National 650,000.00 0.00 Signed 2022-07-22 2022-07-08 2022-07-27 2022-07-23 2022-09-07 2022-08-16 2022-10-21 2022-08-12 2022-11-25 2023-02-23 X4 Vehicles for LIPW and PI M nvelope ngthening onitoring and Supervision GH-MLGRD-RCU-264274-GO- RFQ / Supply and Delivery of Labor-Intensive Public Works Request for Quota Single Stage - One E 400 Bags of Polyclonal Cashe IDA / 68590 Post Limited 70,000.00 0.00 Signed 2023-02-15 2022-03-28 2023-04-12 2023-06-11 Program tions nvelope w Seeds for LIPW activities in the 34 Southern Districts. GH-MLGRD-RCU-272643-GO- RFQ / Supply and Delivery of Labor-Intensive Public Works Request for Quota Single Stage - One E IDA / 68590 Post Limited 50,000.00 0.00 Completed 2023-02-22 2022-03-28 2023-04-19 2023-06-18 4Million Units of Polypots (Pol Program tions nvelope y bags) for Nursery Activities under LIPW GH-MLGRD-RCU-341125-GO- Labor-Intensive Public Works Request for Quota Single Stage - One E RFQ / Supply and Delivery of IDA / 68590 Post Open - National 85,000.00 0.00 Completed 2023-03-01 2023-04-26 2023-10-23 Program tions nvelope 7,000 Wellington Boots for LI PW Activities GH-MLGRD-RCU-341122-GO- RFB / Supply and Delivery of Productive Inclusion Progra Single Stage - One E Pending Impl 1 (One) Server to Host GMIS IDA / 68590 Post Request for Bids Open - National 90,000.00 0.00 2023-03-31 2023-04-05 2023-05-17 2023-06-16 2023-07-21 2024-01-17 m nvelope ementation PRO, E-DASH, PI System Appl ication Software and Data Ba se GH-MLGRD-RCU-365616-GO- RFQ / Procurement of Signag e and Transparency Account ability Boards for CCMI Nurse Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl ries and Plantations for Buils IDA / 68590 Post Open - National 7,727.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation a South, Builsa North Municip al, Bongo, Talensi, Nabdam, Bawku West, Bawku Municip al, Binduri, Garu, Pusiga, Te mpane, and other Districts in EURCC GH-MLGRD-RCU-365618-GO- RFQ / Procurement of Tools, Equipment & PPEs for CCMI N Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl urseries and Plantations for IDA / 68590 Post Open - National 5,338.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation Mamprugu Moagduri, East M amprusi Municipal, Bunkpuru gu - Nakpanduri and Yunyoo - Nasuan Districts by the NER CC GH-MLGRD-RCU-365573-GO- RFQ / Procurement of Tools, Equipment, and Materials for Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl the establishment of coconut IDA / 68590 Post Open - National 31,000.00 0.00 2023-07-02 2023-08-27 2024-02-23 Program tions nvelope ementation plantation, including nursery at Liati Soba and establishme nt of oil palm plantation at V e Deme in Afadzato South Di strict. GH-MLGRD-RCU-365587-GO- RFQ / Procurement of Tools, Equipment & PPEs for CCMI N urseries and Plantations for B Labor-Intensive Public Works Request for Quota Single Stage - One E Pending Impl IDA / 68590 Post Open - National 22,404.00 0.00 2023-07-03 2023-08-28 2024-02-24 uilsa South, Builsa North, Bon Program tions nvelope ementation go, Talensi, Nabdam, Bawku West, Bawku Mun, Pusiga, Te mpani, Garu, Binduri, District s by the UERCC. Page 6 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-322569-NC- RFB / Procurement of Service Productive Inclusion Progra Open - Internationa Single Stage - One E Under Imple IDA / 68590 Prior Request for Bids 4,000,000.00 0.00 2022-10-31 2022-10-25 2022-11-05 2022-10-26 2022-12-17 2022-08-19 2023-01-16 2022-11-14 2023-02-20 2025-12-31 Provider for LEAP, LIPW and P m l nvelope mentation I E-Payment Service GH-MLGRD-RCU-220724-NC- RFB / Procurement of Service Productive Inclusion Progra Open - Internationa Single Stage - Two E IDA / 68590 Prior Request for Bids 4,000,000.00 0.00 Canceled 2022-05-16 2022-06-22 2022-05-21 2022-07-14 2022-07-02 2022-08-19 2022-09-14 2022-10-19 2025-12-31 Provider for LEAP, LIPW and P m l nvelope I E-Payment Service CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-341523-CS- Project Management, Coordi CQS / Selection of Consultant Consultant Qualifi IDA / 68590 nation, and Institutional Stre Post Open - National 40,000.00 0.00 Under Review 2023-02-28 2023-02-27 2023-03-04 2023-03-29 2023-04-05 2023-04-19 2023-05-30 to undertake Independent Pr cation Selection ngthening ocurement Audit of Project a ctivities for 2022 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-MLGRD-RCU-363850-CS- CDS / Selection of Consultant Labor-Intensive Public Works Pending Impleme to undertake impact Evaluati IDA / 68590 Prior Direct Selection Direct - National 250,000.00 0.00 2023-06-26 2023-07-28 2023-09-01 2025-09-26 Program ntation on of the Labour-Intensive Pu blic Works Component. Page 7 PROCUREMENT PLAN (Textual Part) Project information: Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT (P173989) Project Implementation agency: MOH – Ministry of Health Date of the Procurement Plan: June 30th, 2020 Period covered by this Procurement Plan: From July 2020 to December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the national procurement legislation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: The corresponding Procurement Documents must be acceptable to the World Bank. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations and the corresponding Procurement Documents must be acceptable to the World Bank. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: “Not Applicable”; Works: “Not Applicable” Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is “Not Applicable” Other Relevant Procurement Information. Since the Project triggers Paragraph 12 of the IPF Policy, which relates to Projects in Situations of Urgent Need of Assistance or Capacity Constraints, the GoRTT and the Bank have agreed that the MOH would directly engage PAHO/WHO to source all PPEs, pharmaceuticals, medical supplies, equipment and vaccines the Project needs to respond the COVID-19 pandemic, given PAHO/WHO’s rapid mobilization on the ground and expertise in responding emergency situations like the current one. When entering into a contract with PAHO/WHO, the MOH will use a standard form of agreement previously negotiated and approved by the Bank. PROCUREMENT Trinidad and Tobago : Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT PLAN General Information Country: Trinidad and Tobago 2021-05-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173989 GPN Date: 2021-05-10 Project Name: Republic of Trinidad and Tobago: COVID-19 EMERGENCY RESPONSE PROJECT Loan / Credit No: IBRD / 91570 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-232028-GO-RFB / Pr ocurement/supply of COVID- Emergency Response to CO IBRD / 91570 Prior Direct Selection Direct 11,617,613.85 0.00 Signed 2021-05-16 2021-05-20 2021-05-23 2021-06-01 2021-06-27 2022-06-22 19 related PPEs, pharmaceuti VID-19 cals, medical supplies and eq uipments TT-MOH-343910-GO-RFQ / P Project Management and Mo Request for Quota Single Stage - One E IBRD / 91570 Post Limited 18,680.00 0.00 Signed 2023-02-22 2022-12-28 2023-04-19 2023-10-16 urchasing of ICT Equipment f nitoring tions nvelope or the PIU TT-MOH-348518-GO-DIR / Pu Support to COVID-19 Vaccin Direct - Internation Under Revie IBRD / 91570 Prior Direct Selection 7,500,000.00 0.00 2023-03-09 2023-03-14 2023-04-18 2023-10-15 rchasing of COVID-19 Vaccin ation Campaign al w es TT-MOH-348548-GO-DIR / Pu Support to COVID-19 Vaccin Direct - Internation Under Revie IBRD / 91570 Prior Direct Selection 173,432.00 0.00 2023-03-09 2023-03-14 2023-04-18 2023-10-15 rchasing of COVID-19 vaccin ation Campaign al w es TT-MOH-348554-GO-DIR / Th Project Management and Mo e purchasing of SAGE 50 Acc IBRD / 91570 Post Direct Selection Direct - National 4,412.00 0.00 Signed 2023-03-09 2023-03-17 2023-03-14 2023-03-03 2023-04-18 2023-10-15 nitoring ounting Software for the PIU Team NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-365711-CS-LCS / Fi nancial Audit Services for the COVID 19 Emergency Respo Project Management and Mo Least Cost Selecti Under Implement IBRD / 91570 Post Open - National 60,000.00 0.00 2023-06-06 2023-05-25 2023-06-27 2023-08-10 2023-09-07 2023-10-07 2023-11-11 2023-12-16 2024-06-13 nse Project for the periods M nitoring on ation arch 15, 2021 to September 30, 2023, October 1, 2023 to June 30, 2024. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TT-MOH-IC-1 / PIU Project Ma Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-08 2021-08-28 2022-02-24 2022-04-14 2023-04-14 nager nitoring ant Selection TT-MOH-IC-3 / PIU Financial Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-09 2021-08-28 2022-02-24 2022-04-14 2023-04-14 Management Officer nitoring ant Selection TT-MOH-IC-4 / PIU Environm Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-08-09 2021-08-28 2022-02-24 2022-04-14 2023-04-14 ental and Social Specialist nitoring ant Selection TT-MOH-IC-2 / PIU Procurem Project Management and Mo Individual Consult IBRD / 91570 Post Limited 39,000.00 0.00 Under Review 2021-03-01 2022-10-20 2021-08-28 2022-02-24 2022-04-14 2023-04-14 ent Officer nitoring ant Selection Page 1