PROCUREMENT PLAN (Textual Part) Project information: Pakistan: SINDH EARLY LEARNING ENHANCEMENT THROUGH CLASSROOM TRANSFORMATION (P172834) Project Implementation agency: REFORM SUPPORT UNIT, EDUCATION & LITERACY DEPT., GOVT. OF SINDH Date of the Procurement Plan: January 12, 2022 Period covered by this Procurement Plan: January 2022- June 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017, August 2018 and November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in respective Public Procurement Rules, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or prospective bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works); Goods: is not applicable, Works: is not applicable. Letter of Acceptance of the World Bank’s Anticorruption Guidelines and Sanctions Framework1 Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines2 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; 1[Drafting note: This document shall be signed by bidders/proposers/consultants and submitted as part of their bids/proposals. In addition, this document shall be signed by the winning bidder/consultant and incorporated as part of the contract.] 2Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;3 (ii) to be a nominated4 sub-contractor, sub-consultant, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect5 all accounts, records, and other documents relating to 3 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification or initial selection), expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 4A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the bidding document) is one which has been: (i) included by the bidder in its pre-qualification or initial selection application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 5Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact- finding activities undertaken by the Bank or persons appointed by the Bank to address specific the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Proposer/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Proposer/ Consultant: Title of the person signing the Letter: matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Pakistan : Sindh Early Learning Enhancement through Classroom Transformation PLAN General Information Country: Pakistan 2022-01-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172834 GPN Date: 2022-01-27 Project Name: Sindh Early Learning Enhancement through Classroom Transformation Loan / Credit No: TF / B6208, IDA / 69730 Reform Support Unit, Education & Literacy Dept., Govt. of Sindh Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-RSU-SINDH-365306-CW-R FQ / Hiring of contractor to e Monitoring and evaluation a Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-02-1 TF / B6208 Post Open - National 48,780.00 0.00 2023-06-21 2023-08-16 xecute small works to remod nd project management tions nvelope or explanation) lementation 2 el and establish office space GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-RSU-SINDH-324868-GO-R Developing an effective and Request for Quota Single Stage - One E FQ / Shopping of the IT Equip IDA / 69730 Post Open - National 32,040.00 0.00 Signed 2022-11-12 2022-12-14 2022-12-26 2023-01-25 safe learning environment tions nvelope ments for PMIU Staff PK-RSU-SINDH-324869-GO-R Developing an effective and Request for Quota Single Stage - One E IDA / 69730 Post Open - National 25,119.00 0.00 Signed 2022-11-12 2023-01-30 2022-12-30 2023-01-29 FQ / Shopping of Furniture fo safe learning environment tions nvelope r PMIU PK-RSU-SINDH-324943-GO-R Developing an effective and Request for Quota Single Stage - One E IDA / 69730 Post Open - National 25,692.00 0.00 Signed 2022-11-09 2022-12-22 2023-01-21 FQ / Shopping of Machinery's safe learning environment tions nvelope for PMIU PK-RSU-SINDH-365274-GO-R Improving system capacity f Request for Quota Single Stage - One E Pending Impl FQ / Procurement of Servers TF / B6208 or better school leadership a Post Open - National 17,421.00 0.00 2023-06-26 2023-08-21 2023-09-20 tions nvelope ementation (quantities-02) nd management support PK-RSU-SINDH-365308-GO-R Monitoring and evaluation a Request for Quota Single Stage - One E Pending Impl FQ / Procurement of Laptops TF / B6208 Post Open - National 8,995.00 0.00 2023-06-26 2023-08-21 2023-11-19 nd project management tions nvelope ementation and printers (LOT NO 1) PK-RSU-SINDH-365305-GO-R FQ / Procurement of Vehicle Monitoring and evaluation a Request for Quota Single Stage - One E Under Imple TF / B6208 Post Limited 33,449.00 0.00 2023-06-26 2023-08-21 2024-02-17 s (LOT NO 2) nd project management tions nvelope mentation Category of Vehicles: Cars PK-RSU-SINDH-365325-GO-R Monitoring and evaluation a Request for Quota Single Stage - One E Pending Impl FQ / Procurement of Electric TF / B6208 Post Open - National 8,303.00 0.00 2023-06-26 2023-08-21 2023-11-19 nd project management tions nvelope ementation Appliances (LOT NO 3) PK-RSU-SINDH-365301-GO-R FQ / Procurement of Vehicles Monitoring and evaluation a Request for Quota Single Stage - One E Under Imple TF / B6208 Post Limited 87,587.00 0.00 2023-06-26 2023-08-21 2024-02-17 (LOT NO 1) nd project management tions nvelope mentation Category of the vehicles: car s PK-RSU-SINDH-365319-GO-R Monitoring and evaluation a Request for Quota Single Stage - One E Pending Impl FQ / Procurement of Furnitur TF / B6208 Post Open - National 17,073.00 0.00 2023-06-26 2023-08-21 2023-11-19 nd project management tions nvelope ementation e (LOT NO 2) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-RSU-SINDH-319496-CS-Q CBS / Hiring of Consultancy fi Developing an effective and Quality And Cost- Open - Internationa Under Implement TF / B6208 Prior 2,676,886.00 0.00 2022-10-21 2022-10-21 2022-10-30 2022-10-24 2022-12-14 2023-05-16 2023-01-30 2023-03-01 2023-03-31 2023-04-24 2026-10-22 rm for the design and supervi safe learning environment Based Selection l ation sion of Civil Work PK-RSU-SINDH-365256-CS-C Improving system capacity f QS / Hiring of Consultancy fir Consultant Qualifi TF / B6208 or better school leadership a Post Open - National 260,000.00 0.00 Under Review 2023-06-20 2023-06-22 2023-07-11 2023-08-15 2023-09-14 2023-10-19 2024-06-15 m for the Early Grade Readin cation Selection nd management support g Assessment (EGRA) Baselin e Survey PK-RSU-SINDH-365266-CS-C QS / Hiring of Technical Assis Improving system capacity f Consultant Qualifi tance (TA) Firm for capacity TF / B6208 or better school leadership a Post Open - National 250,198.00 0.00 Under Review 2023-06-23 2023-06-22 2023-07-03 2023-08-07 2023-08-31 2023-10-05 2025-03-28 cation Selection building of school leadership nd management support and local education Manage ment INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-RSU-SINDH-270660-CS-IN Monitoring and evaluation a Individual Consult DV / Hiring of Financial Mana TF / B6208 Post Open 20,410.00 0.00 Terminated 2021-12-31 2021-12-20 2022-02-18 2022-09-07 2022-03-11 2022-09-13 2022-04-15 2023-04-15 nd project management ant Selection gement Specialist Page 1 PK-RSU-SINDH-270905-CS-IN DV / Terms of Reference for Monitoring and evaluation a Individual Consult TF / B6208 Post Open 20,410.00 0.00 Signed 2021-12-31 2021-12-20 2022-02-18 2023-01-19 2022-03-11 2022-09-05 2022-04-15 2023-04-15 Hiring of Procurement and Co nd project management ant Selection ntract Specialist (Consultant) PK-RSU-SINDH-270910-CS-IN Monitoring and evaluation a Individual Consult DV / Hiring of Environment, C TF / B6208 Post Open 13,607.00 0.00 Signed 2021-12-31 2021-12-20 2022-02-18 2022-08-16 2022-03-11 2022-09-13 2022-04-15 2023-04-15 nd project management ant Selection ommunity Health and Safety Specialist PK-RSU-SINDH-270912-CS-IN Monitoring and evaluation a Individual Consult Under Implement DV / TORs for Hiring of Gend TF / B6208 Post Open 13,607.00 0.00 2021-12-31 2021-12-20 2022-02-18 2022-03-11 2022-04-15 2023-04-15 nd project management ant Selection ation er Specialist PK-RSU-SINDH-270914-CS-IN Monitoring and evaluation a Individual Consult DV / TORs for Hiring of Social TF / B6208 Post Open 13,607.00 0.00 Signed 2021-12-31 2021-12-20 2022-02-18 2022-05-20 2022-03-11 2022-09-13 2022-04-15 2023-04-15 nd project management ant Selection Safeguard Consultant PK-RSU-SINDH-299355-CS-IN Monitoring and evaluation a Individual Consult DV / Hiring of Consultant PMI TF / B6208 Post Open - National 17,815.00 0.00 Canceled 2022-06-10 2022-09-15 2022-07-29 2022-08-19 2022-09-23 2023-09-23 nd project management ant Selection U-Civil Work: Lead Project En gineer PK-RSU-SINDH-299349-CS-IN Monitoring and evaluation a Individual Consult DV / Hiring of PMIU-Socio-Em TF / B6208 Post Open - National 10,400.00 0.00 Signed 2022-06-10 2022-09-15 2022-07-29 2023-04-05 2022-08-19 2023-04-05 2022-09-23 2023-09-23 nd project management ant Selection otional Support (SES) Special ist PK-RSU-SINDH-299350-CS-IN Monitoring and evaluation a Individual Consult DV / Hiring of PMIU- Assistant TF / B6208 Post Open - National 5,940.00 0.00 Signed 2022-06-10 2022-10-19 2022-07-29 2023-02-07 2022-08-19 2023-02-07 2022-09-23 2023-09-23 nd project management ant Selection CPD Specialist-Literacy PK-RSU-SINDH-299351-CS-IN Monitoring and evaluation a Individual Consult DV / Hiring of PMIU- Item Ban TF / B6208 Post Open - National 10,400.00 0.00 Signed 2022-06-10 2022-09-15 2022-07-29 2022-12-14 2022-08-19 2023-02-07 2022-09-23 2023-09-23 nd project management ant Selection k Manager PK-RSU-SINDH-299358-CS-IN Monitoring and evaluation a Individual Consult TF / B6208 Post Open - National 17,815.00 0.00 Signed 2022-06-10 2022-09-15 2022-07-29 2023-03-27 2022-08-19 2023-04-03 2022-09-23 2023-09-23 DV / Hiring of PMIU- M&E Sp nd project management ant Selection ecialist PK-RSU-SINDH-299344-CS-IN Monitoring and evaluation a Individual Consult DV / Hiring of PMIU- Continuo TF / B6208 Post Open - National 14,850.00 0.00 Signed 2022-06-10 2022-10-19 2022-07-29 2023-04-04 2022-08-19 2023-05-02 2022-09-23 2023-09-23 nd project management ant Selection us Professional Development Specialist - PK-RSU-SINDH-299330-CS-IN DV / Hiring of PMIU-Continuo Monitoring and evaluation a Individual Consult Under Implement TF / B6208 Post Open - National 14,850.00 0.00 2022-06-10 2022-10-19 2022-07-29 2022-08-19 2022-09-23 2023-09-23 us Professional Development nd project management ant Selection ation Specialist (STEDA) PK-RSU-SINDH-299356-CS-IN DV / Hiring of PMIU-Student A Monitoring and evaluation a Individual Consult TF / B6208 Post Open - National 10,400.00 0.00 Signed 2022-06-10 2022-09-15 2022-07-29 2023-02-07 2022-08-19 2023-02-07 2022-09-23 2023-09-23 ttendance Monitoring and Re nd project management ant Selection dress Specialist PK-RSU-SINDH-299357-CS-IN Monitoring and evaluation a Individual Consult TF / B6208 Post Open - National 11,875.00 0.00 Signed 2022-06-10 2022-09-15 2022-07-29 2023-05-11 2022-08-19 2023-05-11 2022-09-23 2023-09-23 DV / Hiring of PMIU-Manager nd project management ant Selection MIS PK-RSU-SINDH-315931-CS-IN Monitoring and evaluation a Individual Consult DV / PMIU-Labour Manageme TF / B6208 Post Open - National 5,085.00 0.00 Canceled 2022-09-19 2022-10-19 2022-10-17 2022-10-24 2022-11-07 2022-12-07 nd project management ant Selection nt Specialist PK-RSU-SINDH-315951-CS-IN Improving system capacity f Individual Consult DV / Hiring of PMIU-Assessme TF / B6208 or better school leadership a Post Open - National 15,572.00 0.00 Signed 2022-09-19 2022-10-19 2022-10-23 2023-02-27 2022-11-13 2023-02-27 2022-12-09 2023-12-09 ant Selection nt Specialist nd management support PK-RSU-SINDH-321849-CS-IN Monitoring and evaluation a Individual Consult DV / Hiring of Lead Project En TF / B6208 Post Limited 17,815.00 0.00 Completed 2022-10-20 2022-10-19 2022-10-27 2022-11-03 2022-11-02 2022-11-03 2022-11-04 2023-11-04 2023-11-26 nd project management ant Selection gineer for Civil Work (PMIU-S ELECT) PK-RSU-SINDH-322603-CS-IN DV / Hiring of Individual Cons Developing an effective and Individual Consult TF / B6208 Post Limited 5,085.00 0.00 Signed 2022-10-24 2022-10-27 2022-10-28 2022-12-15 2022-11-02 2022-11-30 2022-11-21 2022-12-21 ultant for Labour Manageme safe learning environment ant Selection nt Procedure Specialist PK-RSU-SINDH-331435-CS-IN Improving system capacity f Individual Consult Under Implement DV / Hiring of Continuous Pro IDA / 69730 or better school leadership a Post Open - National 16,301.00 0.00 2022-12-15 2022-12-05 2023-01-11 2023-02-01 2023-02-12 2024-02-12 ant Selection ation fessional Development Speci nd management support alist (PITE) PK-RSU-SINDH-331441-CS-IN Developing an effective and Individual Consult Under Implement IDA / 69730 Post Open - National 16,301.00 0.00 2022-12-15 2022-12-26 2023-01-11 2023-02-01 2023-02-17 2024-02-17 DV / Hiring of Project Enginee safe learning environment ant Selection ation r PK-RSU-SINDH-333910-CS-IN Monitoring and evaluation a Individual Consult DV / Hiring of Financial Mana TF / B6208 Post Limited 20,410.00 0.00 Canceled 2023-01-02 2023-01-05 2023-01-10 2023-01-19 2023-01-31 2023-01-13 2023-03-07 2024-03-06 nd project management ant Selection gement Specialist PK-RSU-SINDH-363792-CS-IN Monitoring and evaluation a Individual Consult DV / Hiring of Financial Mana TF / B6208 Prior Open - National 18,551.00 0.00 Under Review 2023-05-28 2023-06-05 2023-07-07 2023-07-28 2023-09-01 2024-08-31 nd project management ant Selection gement Specialist (FMS) PK-RSU-SINDH-365251-CS-IN Improving system capacity f Individual Consult DV / Hiring of Software Engin TF / B6208 or better school leadership a Post Open - National 12,804.00 0.00 Under Review 2023-06-15 2023-06-14 2023-08-03 2023-08-24 2023-09-28 2024-09-27 ant Selection eer nd management support Page 2 Plan de Passation de marchés I. Généralités 1. L'information sur le projet : Pays : Madagascar ; Emprunteur : République de Madagascar ; Nom de projet : Deuxième Projet de Gouvernance des Pêches et de Croissance Partagée du Sud-ouest de l’Océan Indien (SWIOFish2) Numéro du Crédit : P153370 Agence d’exécution du Projet : 2. Date d’approbation du Plan de passation de marchés par la Banque : 01 Février 2018 ; Révision : 09 Août 2018 ; 3. Date de notification du Plan Général de Passation de marchés : - ; 4. Période couverte par le Plan de Passation de marchés : Année 2018 II. Biens et Travaux et Services hors consultants 1. Seuil de Revue préalable : Les décisions de passation de marchés sujet aux revues préalables de la Banque comme indiqué dans le paragraphe 3.1 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) et sur la base de l'évaluation de la capacité de l'agence d’exécution : Méthode de Passation de Seuil de revue Commentaires marchés à priori 1. AOI – Ouvert ou Restreint (Biens) 2 000 000 Les montants 2. AON (Biens) 2 000 000 estimatifs des 3. AOI (Travaux) 10 000 000 marchés prévus 4. AON (Travaux) 10 000 000 sont au-dessous 5. AOI (Services) 2 000 000 des seuils. 6. UN -UNOPS (Biens) 2 000 000 Niveau de risque : 7. ED (Biens/Travaux) 2 000 000 « SUBSTANTIEL » 2. Pré-qualification (selon les dispositions des paragraphes 6.19 à 6.24 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable. 3. Procédures proposées pour les composantes CDD (selon le paragraphe. 6.52 et 6.53 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable 4. Référence (s’il y en a) au Manuel d’exécution du projet / Manuel de Passation de marchés : Non Applicable 5. Tout autre arrangement spécial en passation de marchés : Non Applicable. 6. Allotissement de fournitures avec méthodes et calendrier : [Enumérer d’abord les allotissements qui nécessitent la revue préalable de la Banque, ensuite les autres allotissements] 1 2 3 4 5 6 7 8 9 Réf. Description Contrat Coût Approche/Méth Pré- Préféren Revue de la Date Commentair No estimatif ode de qualificati ce Banque (à prévue es sélection on national priori / à d’ouverture Oui / Non e posteriori) des Oui / Non soumission s MG- Matériels roulants (46Voitures : PM 1DSP – 2CEDP – 3SG – 3DGRHP 3 070 000 UNOPS Non Non Oui 01/07/2018 01/1 – 3RGPDD – 4ASH – 1USTA – 8 5CSP – 22 DRRHP – 2UGP) MG- PM Matériels roulants (20motos ; Non Non 59 000 UNOPS Non 01/07/2018 02/1 2USTA – 16UGL – 2UGP) 8 Matériels et équipement Informatiques (48 Ordinateurs de bureau – 45 Ordinateurs portables – 27 Onduleurs – Non Non Non MG- 4Stabilisateurs – 29Imprimantes PM AON/UNOP multifonctions – 52 Imprimantes 433 910 30/09/2018 03/1 S laser noir – 11Imprimantes laser 8 couleur – 29Photocopieuses – 10Vidéoprojecteurs – 10Appareils photo – 11GPS – 1Caméra – 32 Tablettes MG- PM Matériels et mobiliers de bureau Non Non Non 162 200 AON 30/09/2018 04/1 : 1DCI – 2USTA –8 UGL - 1UGP 8 MG- Commented [JM1]: 29 170 dans PPM d’aout PM Fournitures et articles de Non Non Non Commented [u2R2]: Omission de la ligne 47 170 DC 01/12/2018 05/1 bureau 4.1.3.2.1 de l’UGP d’un montant de 18.000USD 8 sur le PTBA 2018 MG- PM Non Non Non Consommables informatiques 73 170 DC 30/09/2018 06/1 8 MG- Kits d'équipements pour les PM enquêteurs (sac de couchage, Non Non Non 17 500 DC 15/10/2018 07/1 tente, torche, bottes, 8 imperméable) MG- Non Non Non Achat téléphone mobile pour la PM collecte de données au niveau 5 250 DC 01/12/2018 08/1 national 8 MG- Non Non Non Matériels d'échantillonnage PM (Blouse, gant, balance, pied a 1 000 DC 30/09/2018 09/1 coulisse…) 8 MG- Non Non Non Acquisition et installation d’un PM logiciel de suivi automatique 150 000 AON 01/12/2018 10/1 des captures (ERS); 8 MG- Non Non Non Dotation et moyens PM d'équipement pour les 48 000 DC 30/10/2018 11/1 membres du CSC 8 MG- Non Non Non PM Matériels de l'électrification 9 000 DC 30/10/2018 12/1 hors grille 8 MG- Non Non Non PM Equipements et outils de pêche 120 000 AON 01/10/2018 13/1 8 MG- Non Non Non Commented [JM3]: 115 000 dans PPM d’aout Outillage d'entretien d'engin et PM Commented [u4R4]: Après vérification du d'embarcation de pêche pour 60 000 AON 01/12/2018 14/1 PTBA Ligne 3.2.1.1.32 : il est prévu :12 lots à usage communautaire 8 5.000USD l’unité Appui à la mise à disposition Non Non Non MG- des équipements de base pour PM la sécurité des pêcheurs et de 165 000 AON 01/12/2018 15/1 leurs embarcations en mer 8 (gilet, miroir… pour la période transitoire) MG- Non Non Non PM Outils de valorisation 80 000 DC 01/12/2018 16/1 8 MG- Petits matériels de valorisation 80 000 DC Non Non Non 01/12/2018 PM 17/1 8 MG- Non Non Non Commented [JM5]: Combien de boites sont PM prévues ? Achat boites à plaintes 3 950 DC 30/09/2018 18/1 Commented [u6R6]: 79 boites à plaintes 8 suivant la ligne 3.2.3.4.4 du PTBA 2018 MG- Non Non Non PM Outillage pour les pépinières et 19 000 DC 01/12/2018 19/1 les reboisements (brouette,….) 8 MG- Non Non Non Renforcement de l'unité de PM gestion communautaire en 10 000 DC 01/12/2018 20/1 biens et équipements 8 MG- Acquisition, installation et test Non Non Non PM des biens et équipements 240 000 AON 01/12/2018 21/1 relatifs aux technologies hors 8 grille MG- Non Non Non PM Petit outillage et fournitures 417 DC 30/10/2018 22/1 d’atelier (unité) 8 MG- Non Non Non Construction des bureaux des 2 PM PIE de l'ASH en province : 60 000 DC 30/09/2018 23/1 Antsiranana et Morondava 8 Carénages du navire de Non Non Non MG- surveillance «Atsantsa », PM remplacement des appareils de 181 000 AON 30/08/2018 24/1 navigation/accessoires et pièces 8 de rechanges des moteurs auxiliaires MG- Non Non Non PM Carénage du navire de 76 000 DC 30/10/2018 25/1 surveillance "Telonify" 8 MG- Non Non Non PM Constructions pour les six (06) 420 000 AON 30/09/2018 26/1 DRRHP et huit (08) CIRRHP 8 MG- Non Non Non PM Construction de petits 350 000 AON 30/11/2018 27/1 débarcadères type ponton 8 Installation d'unités de Non Non Non fabriques de glace/chambres MG- froides fonctionnant avec des PM énergies renouvelables et 320 000 AON 30/11/2018 28/1 respectant l’environnement 8 pour maintenir la chaine de froid des produits halieutiques dès leur débarquement MG- Non Non Non PM Construction d'infrastructures 360 000 AON 01/12/2018 29/1 communautaires /communales 8 MG- Non Non Non Infrastructures d'électrification PM hors grille dans les 1 250 000 AON 01/12/2018 30/1 communautés pilotes 8 MG- Non Non Non PM Construction de bureau de 60 000 DC 30/07/2018 31/1 l'UGP centrale 8 7.858.197 TOTAL Biens – Equipements et Travaux III. Sélection de consultants 1. Seuil de Revue Préalable : Décisions de sélection sujet à la revue préalable de la Banque comme indiqué dans le paragraphe 3 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) : Méthode de sélection Seuil de Commentaires revue à priori 1. Méthode compétitive (firmes) 1 000 000 Les montants 2. Entente directe (firmes) 1 000 000 estimatifs des 3. Méthode compétitive (Consultant individuel) 300 000 contrats prévus sont 4. Entente directe (Consultant individuel) 300 000 au-dessous des seuils. Niveau de risque : « SUBSTANTIEL » 2. Liste restreinte composée entièrement de consultants nationaux : Liste restreinte de consultants pour prestations de services, estimés à moins de USD 150 000 par contrat, peut comporter entièrement des consultants nationaux selon les dispositions du paragraphe 7.25 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016). 3. Tout autre arrangement spécial de Sélection de consultants : Non applicable 4. Tâches de consultation avec des méthodes de sélection et calendrier Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Etude et analyse diagnostiques des MG-PM stratégies du secteur et des anciens 75 000 CI NON 01/05/2018 32/18 plans directeurs et élaboration du nouveau plan directeur Mise à jour de la Stratégie Nationale de MG-PM l’Aquaculture (Consultant national + 30 000 CI NON 30/08/2018 33/18 Réunions (1 consultation, 1 validation) Etude sur les procédures MG-PM administratives régissant l’accès aux 70 000 CI NON 30/07/2018 34/18 ressources et examen des options et recommandations (6 outils de gestion) Elaboration de la stratégie d'adaptation MG-PM du secteur pêche face au changement 10 000 CI NON 01/09/2018 35/18 climatique Amélioration de la base de données pour la déclaration des produits de la Commented [JM8]: Est-ce que l augmentation MG-PM pêche régionale (Base de données- 10 000 CI NON 30/08/2018 de 35 000 à 58 500 justifié par l’ajout de la 36/18 Tableau de bord-Système d'Information partie CFTP non prévue au PPM d’aout. Pêche : basé sur le Web, consultant) Commented [u9R9]: Faisant suite aux Amélioration de la base de données instructions de l’Equipe PPM de la BM, on a MG-PM pour les pêcheries industrielles 10 000 CI NON 30/09/2018 regroupée les études techniques et les études 37/18 Impacts pour l’OEPA régional et central – CFTP (consultant) Etude technique et étude d'impact et Enceinte Fénerive Est suivant les lignes du PTBA suivantes ; 2.1.2.3.6 – 2.1.2.3.7 – 2.1.2.5.2 environnemental et social de Etude groupée – 2.1.2.5.3 – 2.3.2.1.1 – 2.3.2.2.1.2 – 3.2.1.1.3 et MG-PM l'extension ou construction du bureau MG-PM 38-39-40- 3.2.1.1.4 58 500 SFQC NON 30/10/2018 92/18 régional et central de l’OEPA, de 41-55-56-62- réhabilitation du CFTP , Clôture de 63/18 Commented [JM7]: Est-ce que les études techniquesenv. Pour l’enceinte de la DRRHP de l’enceinte DRRHP Fenerive Fenerive ne pourrait pas être plutôt ajouter à la PA65 ? Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Elaboration stratégie nationale de MG-PM recherches halieutiques (1 Consultant 50 000 CI NON 30/07/2018 42/18 international et 3 consultants nationaux) MG-PM Etude sur les mesures de gestion des 30 000 CI NON 30/07/2018 43/18 poulpes Avis scientifique pour la gestion des MG-PM pêcheries de langoustes, dans les sites 30 000 CI NON 30/07/2018 44/18 prioritaires Développement des points de référence MG-PM opérationnels pour la gestion de la 75 000 CI NON 30/07/2018 45/18 pêche crevettière Révision du système de suivi de la MG-PM pêche crevettière traditionnelle (PCT) 86 000 SFQC NON 30/07/2018 46/18 et élargissement à toutes les zones de pêche MG-PM Révision par les pairs des modèles 86 000 SFQC NON 30/07/2018 47/18 d'évaluation des stocks de crevettes Étude technique sur la stratégie de NON Commented [JM10]: 60 000 dans le PPM MG-PM surveillance et sur le fonctionnement 15 000 SFQC 30/07/2018 d’aout 49/18 du CSP Commented [u11R11]: Après vérification du Frais d'équipage durant les travaux de NON PTBA 2018 ligne 2.2.2.1.1, pour 2018 on a prévu MG-PM carénages (vivres+ indemnités + 25 000 CI 01/08/2018 01 étude pour 15.000USD le coût unitaire 50/18 carburants) MG-PM Assistance technique pour le suivi des 26 000 CI NON 30/09/2018 51/18 travaux de carénage de l'Atsantsa MG-PM NON Rédaction d’un plan national de lutte 52/18 52 000 CI 30/07/2018 contre la pêche INN Extension de l’ERS vers la flotte NON MG-PM nationale (Etude / subvention/ cout 50 000 CI 30/10/2018 53/18 interne CSP) Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Etude et élaboration de mécanisme NON MG-PM structurel de plateforme de cogestion 50 000 CI 30/07/2018 54/18 des filières prioritaires (crabes, poulpes, langoustes, holothuries, crevettes) Études techniques et études d’impact SFQC NON Commented [JM13]: 50 000 dans le PPM environnemental et social pour la Etude groupée d’aout PA 65 Construction des Bureaux de six (06) 70 000 30/07/2018 MG-PM 57-58-85– Commented [u14R14]: Cette ligne regroupe DRRHP et neuf (09) CirRHP et d’un local 86/18 les études MG-PM 57-58-85 et 85 du PPM d’Août, pour bureau de l’UGP réf PTBA 2018 : 2.3.2.1.3 – 2.3.2.1.4 – 4.1.4.1.1 Etude sur l'identification des 180 000 SFQC NON et 4.1.4.1.2 bénéficiaires, du montant et des Commented [u12]: Après vérification PTBA modalités de transfert financier et sur Etude groupée 2018 lignes 2.3.2.1.3 et 2.3.2.1.4 c’est 08 MG-PM la détermination du montant minimal MG-PM 59-18 et 93/18 30/04/2018 de filet social pour les pêcheurs/acteurs MG-PM 60-18 filières affectés par les mesures de gestion MG-PM Recensement et identification des 20 000 CI NON 30/05/2018 61/18 bénéficiaires chaque année Etude sur l'amélioration des SFQC NON MG-PM embarcations existantes à partir des 270 000 01/11/2018 64/18 matériaux locaux bon marché et existants pour chaque ZUP Etude sur l'identification de techniques NON MG-PM modernes de pêche et de fabrication 60 000 SFQC 30/07/2018 65/18 d'engins de pêche adaptés pour chaque ZUP Prestataire formateur en construction 30 000 CI NON MG-PM et entretien des embarcations de pêche 30/11/2018 66/18 (par an) Prestataire formateur en construction 30 000 CI NON MG-PM et entretien des engins de pêche (par 30/08/2018 67/18 an) Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions Etude sur le circuit de 90 000 SFQC NON MG-PM commercialisation des produits des 30/03/2018 68/18 pêches par ZUP MG-PM ""Etude sur les accidents en mer de la 90 000 SFQC NON 30/04/2018 69/18 pêche à petite échelle""" ""Développement du système de SFQC NON MG-PM valorisation des produits halieutiques 60 000 30/03/2018 70/18 adaptées pour chaque ZUP""" " Étude de marché pour les produits de SFQC MG-PM pêche valorisés dans chaque région 90 000 NON 30/04/2018 71/18 ultra prioritaire (1 étude par région)" MG-PM Prestataire formateur en technique de CI NON 75 000 30/03/2018 72/18 valorisation (par an) MG-PM Prestataire formateur en technique CI NON 25 000 28/02/2018 73/18 commerciale (par an) MG-PM "Analyse des besoins en activités SFQC NON 74/18 alternatives adaptées pour chaque ZUP 210 000 30/05/2018 (exécutée par AGEX)" Evaluation des impacts socio- SFQC NON MG-PM économiques de la mise pratique des 90 000 30/09/2018 75/18 activités alternatives MG-PM Elaboration des Plans d'Action aux 60 000 CI NON 28/02/2018 76/18 restrictions de Ressources (PARAR) Détermination des outils financiers de NON PA40 gestion des revenus issus des filières et 60 000 CI activités alternatives MG – PM Cabinet d’étude ou d’une ONG pour 600 000 SFQC NON 117/18 assurer les missions de l’AGEX (PAP 01/06/2018 MELAKY) Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions MG – PM Cabinet d’étude ou d’une ONG pour 600 000 SFQC NON 117/18 assurer les missions de l’AGEX (PAP 01/06/2018 BATAN) MG – PM Cabinet d’étude ou d’une ONG pour 600 000 SFQC NON 117/18 assurer les missions de l’AGEX (PAP 01/06/2018 Baie d’Antongil) Elaboration de plan de formation des CI NON élus et acteurs communaux MG-PM (Fokontany, Mairie,…) pour la gestion 18 000 01/06/2018 77/18 et la pérennisation des infrastructures de pêches et communautaires MG-PM Elaboration du plan stratégique de CI NON 80 000 30/01/2018 78/18 développement local (PCD et PLD) Etat de lieux des petites infrastructures CI NON MG-PM de pêches et identifications des besoins 79/18 60 000 01/04/2018 des communautés cibles en petites infrastructures de pêche Etude de faisabilité technique des NON constructions d'infrastructures de pêche (APS & APD) (33 débarcadères, 8 MG-PM marchés couverts, 70 salles réunion et 550 000 SFQC 01/08/2018 80/18 hangars d'entretien des embarcations, 28 fabriques de glace) MG-PM Etude d'impact environnemental et 275 000 SFQC NON 01/08/2018 81/18 social Préparation du plan local NON Ligne d’activité à Commented [JM15]: Pas de montant? MG-PM d'électrification communautaire : étude CI 01/03/2018 retirer dans ce Commented [u16R16]: Omission de montant 82/18 et rapports PPM dans le PTBA réf 3.3.3.1.3 – Après consultation Gestion et mise en œuvre : évaluation NON de RC3, le type de coût CS est changé en OP car MG-PM cette activité fait partie d’objet de convention de la mise en place de l'électrification 15 000 CI 01/12/2018 83/18 avec l’ADER. De ce fait, cette ligne ne fera plus hors grille partie des études dans le PPM 2018 Réf. Description des missions Coût Approche/Méthode de Revue de la Date prévue Commentaires No. estimatif sélection Banque (à de priori / à soumission posteriori) des propositions MG-PM Gestion et mise en œuvre : Suivi 40 000 CI NON 15/10/2018 84/18 évaluation des bases de données MG-PM Enquête de situation de référence des SFQC NON 50 000 30/07/2018 87/18 bénéficiaires MG-PM Audit externe des comptes du Projet 15 000 SMC NON 01/12/2018 88/18 MG-PM Elaboration d'une stratégie du plan de CI NON 10 000 30/09/2018 89/18 communication du projet SWIOFish2 MG-PM Mise en place du site internet du projet CI NON 2 000 30/09/2018 90/18 SWIOFish2 MG-PM CI NON Assistance technique - maintenance 500 30/09/2018 91/18 TOTAL Consultances 5.264.000 IV. Activités de renforcement de capacités de l’Agence d’exécution avec calendrier 1. Dans cette section, les activités de renforcement de capacité acceptées (quelques articles pourraient être des recommandations de CPAR) sont énumérées avec le calendrier No. Résultats escomptés / Description Coût Durée Date de Commentaire de l’activité estimatif estimative début s (jours) MG-FO Ateliers nationaux pour la 12.000 01-18 validation des textes d'application avec CRDA MG-FO Formation SLC (technique de 18.000 02-18 négociation, leadership etc.) MG-FO Tenir un atelier national relatif à 7.500 03-18 la communication de la nouvelle loi portant Code de la Pêche et de l'Aquaculture à Madagascar MG-FO Atelier national de préparation de 3.000 02 04-18 l'élaboration du nouveau plan directeur MG-FO Atelier national de validation du 6.000 01 05-18 plan directeur MG-FO Visite d'échange d'expérience en 40.000 06-18 matière de technique de production et d'exploitation aquacole marine (ex: grouper sp, algue marine, crabe) MG-FO Formation provinciale sur 27.000 07-18 nouvelles procédures de marquage, de délivrance des cartes pêcheurs et mareyeurs MG-FO Formation des cadres supérieurs 123.000 08-18 (6+6) dans la collecte des données et statistiques de pêche (formation FAO/ISSEA) MG-FO Formation des 10 enquêteurs en 2.000 09-18 méthodologie de collecte de données par téléphone mobile pour les 2 ZUP (DIANA et Analanjirofo; soit 5 enquêteurs/région) MG-FO Formation de 05 cadres 25.000 10-18 supérieurs dans l'analyse des données MG-FO Formation de 05 cadres 25.000 11-18 supérieurs en IT MG-FO Participation à des réunions et 10.000 12-18 ateliers régionaux per diem et hôtel et frais d'avion MG-FO Renforcement des 13-18 capacités des personnels 15.000 techniques de l'OEPA (économie des ressources naturelles et économie des pêches) MG-FO Ateliers régionaux sur la 36.000 14-18 stratégie nationale (pour les 6 ex- provinces) MG-FO Atelier national sur la stratégie 3.000 15-18 nationale MG-FO Formations et voyages d’échange 100.000 16-18 d’expérience et de la bonne pratique (renforcement des capacités, Ateliers de restitution et de validation des travaux de consultance, coûts des voyages, frais de participations, indemnités…) MG-FO Renforcement de capacité des 50.250 17-18 agents chercheurs (formations extérieures) MG-FO Participation à des forums de 52.500 18-18 recherche MG-FO Formation de l'équipe (média, 15.000 19-18 audio-visuel, design, PAO, site web, prog. éducatifs) MG-FO Renforcement de capacité des 5.000 20-18 membres du bureau de coordination pêche environnement (environnement pêche et mer) MG-FO Organisation des réunions 46.000 21-18 semestrielles MG-FO Formation en QMS d’une Autorité 14.300 22-18 Compétente par formateur international pour renforcement de capacités en Audit interne d’une Autorité compétente (Maitrise des documents et des enregistrements) MG-FO Formation en Informatique & 23-18 Base de données : Avec 24.000 formateur national : Informatique (bureautique et programmation) / Utilisation & gestion de base de données MG-FO Linguistique : Avec formateur 15.140 24-18 national : Anglais / Chinois MG-FO Formation en Aquaculture : Avec 22.640 25-18 formateur international : Technique d’élevage et gestion de risque / Méthode de contrôle appliquée dans divers système d’aquaculture (Diana 3 personnes; Melaky 7; Central 2) MG-FO Formation en système de 26-18 Biosécurité : Avec formateur 22.640 international : Biosécurité appliquée aux animaux aquatiques (Diana 3 personnes; Melaky 7; Central 2) MG-FO Formation en Système de 22.640 27-18 management de la QHSE Sanitaire : Avec formateur international : Hygiène et pré requis au niveau des établissements / Normes ISO sur la sécurité sanitaire des aliments / HACCP / Evaluation & analyse des risques MG-FO Formation en Gestion des crises : 28-18 Avec formateur international : 22.640 RASFF MG-FO Formation en Système de 20.200 29-18 certification : Avec formateur international : TRACES MG-FO Formation en Accord International 22.640 30-18 : Avec formateur international : Accord SPS&OMC MG-FO Formation en Science & 22.640 31-18 Technologie : Avec formateur international : Microbiologie des aliments et de l’eau / Toxicologie appliquées aux produits de la mer / Science & Technologie des aliments MG-FO Formation en Technique 2.830 32-18 d’analyse : Avec formateur national : Technique d’analyse de détection des maladies aquatiques MG-FO Formatio 22.640 33-18 n en Technique d’analyse et Technique d’échantillonnage : Avec formateur international MG-FO Formation en Administration : 34-18 Avec formateur national : 15.64 Formation en officier de police 0 judiciaire MG-FO Formation en Administration : 2.840 35-18 Avec formateur national : Procédures Banque Mondiale (Passation de marché, suivi- évaluation MG-FO Formation en QMS d’une Autorité 24.000 36-18 Compétente : Avec formateur international : Structuration et management Qualité d’une Autorité Compétente (ISO 17020) MG-FO Formation en Aquaculture : Avec 37-18 formateur international : 40.000 Aquaculture & environnement MG-FO Formation en Contrôles officiels : 38-18 Avec formateur international : 32.000 Echange d’expérience par jumelage régionale MG-FO Formation en Système de 39-18 management de la QHSE 8.000 Sanitaire : Avec formateur international : Audit de laboratoire selon ISO 17025 MG-FO Formation en Technique 8000 40-18 d’analyse : Avec formateur international : Technique d’analyse officielle MG-FO Formation en Technique 41-18 d’analyse : Avec formateur 8.000 international : Métrologie MG-FO Participation aux réunions et 134.000 42-18 groupes de travail CTOI et ORP MG-FO Réunion nationale (50 personnes 43-18 de 2 jours) de concertation sur la 6.000 pêche aux requins, oiseaux de mer, tortues MG-FO Participation aux réunions 100.500 44-18 régionales pour les termes minimaux des accords de pêche MG-FO Réunions de consultation 6.000 45-18 nationales sur la préparation des Mesures de conservation et de gestion (pour 6 réunions par an) MG- Formation sur l'identification des 8.500 FO46-18 espèces thonières et les techniques d'échantillonnage au débarquement MG-FO Formation sur la gestion des 8.500 47-18 données MG-FO Atelier de validation de nouveaux 75.000 48-18 PAP MG-FO Visite d'échange et d'expérience 31.000 49-18 sur l'utilisation du logiciel ERS MG-FO Formation du personnel à 60.600 50-18 l’utilisation et à l’exploitation de cet outil. MG-FO Renforcement de capacité et 51-18 formation des membres des CSC 24.000 MG-FO Ateliers de lancement régionaux 30.000 52-18 sur les plateformes de cogestion (crabes, poulpes, langoustes, holothuries, crevettes) dans les régions MG-FO Formations et remise à niveau au 112.500 53-18 niveau national des cadres MG-FO Formations et remise à niveau 100.000 54-18 des cadres à l'extérieur MG-FO Atelier de restitution de l'étude 55-18 sur l'identification des 20.000 bénéficiaires, du montant et des modalités de transfert financier et du filet social MG-FO Ateliers de validation des 3.000 56-18 référentiels (diplôme, certificat, attestation) MG-FO Formation des techniques 60.000 57-18 modernes de pêche MG-FO Formation en construction 60.000 58-18 et entretien d'engin de pêche MG-FO Formation sur les techniques 60.000 59-18 commerciales des produits des pêches MG-FO Atelier de restitution de l'étude 20.000 60-18 sur l'accidentologie MG-FO Visite d'échange dans le cadre de 90.000 61-18 la sécurité en mer et de la professionnalisation (Philippine, …) MG-FO Ateliers de validation régionale 62-18 (03) et nationale (01) de l'étude 16.000 diagnostic des techniques de valorisation MG-FO Voyage de partage d’expérience 63-18 dans les régions ou pays voisins, 90.000 où la formation et l’appui en valorisation ont été effectives et ont apporté des effets positifs MG-FO Formation des personnes dans la 64-18 communauté de pêcheurs (pêcheurs, femmes de pêcheur, jeunes sans emploi) en 72.000 techniques de valorisation (15 personnes formées par village) MG-FO Formation des acteurs pratiquant 72.000 65-18 les techniques de valorisation sur la gestion des activités commerciales, la prospection des marchés, les techniques de négociation et le marketing et conditionnement MG-FO Voyages d’échange d’expérience 16.000 66-18 pour les acteurs formés et ayant pratiqué la commercialisation au niveau d’un district littoral accompagnés des agents de la CirRHP/DRRHP/MRHP (1 par année par district) (50 acteurs par voyage) MG-FO Ateliers de restitution régionaux 67-18 et des ateliers de validation 24.000 nationale de l'étude diagnostic des besoins en activités alternatives MG-FO Voyages d’échange d’expérience 45.000 68-18 dans des pays semblables à Madagascar pour les bénéficiaires (Afrique australe, régions de la COI et en Asie) MG-FO Prestation à la formation des 50.000 69-18 cibles en activités alternatives MG-FO Formation des techniciens de 9.000 70-18 l’Administration (DRRHP et CirRHP) et l’UGL sur les techniques et le système de suivi de ces techniques (par région) MG-FO Formation des pêcheurs, femmes 480.000 15 71-18 de pêcheurs et jeunes dans les villages de pêcheurs en techniques de production appropriées pour chaque type d’activité alternative choisi (15j*8000) MG-FO Formation des pêcheurs, femmes 05 72-18 de pêcheurs et jeunes sans 100.000 emploi en techniques d’aquaculture (5 jours) MG-FO Formation et d'échange 90.000 73-18 d'expérience à l'étranger dans le cadre de l'aquaculture (algoculture, pisciculture, crabiculture,…) MG-FO Formation des acteurs pratiquant 80.000 04 74-18 les activités alternatives sur la gestion des activités commerciales, la prospection des marchés, les techniques de négociation et le marketing et conditionnement (4 jours) MG-FO Visites de la vitrine/ ferme école 72.000 75-18 pour les acteurs formés MG-FO Orientation des pêcheurs dans la 1.600 02 76-18 valorisation de leur biodiversité et les former en guide touristique MG-FO Sélection et formation des PF au 12.000 77-18 fonctionnement du MDGP MG-FO Ateliers de validation régionale 16.000 78-18 (03) et nationale (01) MG-FO Visite d’échange d’expérience 32.000 79-18 nationale (1 voyage par an par district) MG-FO Voyage de partage d’expérience 45.000 80-18 à l’étranger (01 voyage par an) MG-FO Séminaire/atelier international 70.000 81-18 (02 voyages par an) MG-FO Formation de courte durée à 45.000 82-18 l’étranger (01 voyage par an) MG-FO Réunions de sensibilisation et de 192.000 03 83-18 formation en éducation financière des petits pêcheurs et aquaculteurs à petite échelle (200 villages de pêcheurs) MG-FO Réunions de sensibilisation pour 64.000 01 84-18 la constitution en organisation appropriée des bénéficiaires du projet (200 villages de pêcheurs) MG-FO Promotion des services financiers 48.000 85-18 adéquats et adaptés à chaque zone d’intervention à travers des sensibilisations MG-FO Renforcement de capacité des 150.000 86-18 cadres et élus au niveau local MG-FO Renforcement de capacité des 9.000 87-18 UGL MG-FO Ateliers régionaux (03) et national 16.000 88-18 de validation MG-FO Atelier de réception locale de 4.000 89-18 l’infrastructure construite MG-FO Partage d'expérience à l'étranger 45.000 90-18 (2 missions par an) dans le cadre de la gestion communautaire des infrastructures de pêche MG-FO Formation des groupements de 8.000 91-18 pêcheurs pour être dans des comités de gestion et formation sur la gestion des infrastructures MG-FO Formation des groupements de 36.000 92-18 pêcheurs pour être dans des comités de gestion et formation sur la gestion des infrastructures MG-FO Formation des communautés 55.800 93-18 pilote sur les procédures réglementaires dans le cadre de l'électrification hors grille MG-FO Formation des communautés 90.000 94-18 pilotes à l'usage et à la gestion de l'électrification hors grille MG-FO Engagement communautaire 75.000 95-18 (IEC) dans le cadre de l'électrification hors grille MG-FO Gestion et mise en œuvre : 27.900 96-18 diffusion de connaissances MG-FO Participation à des ateliers de 10.000 97-18 partage MG-FO Formation modulaire spécifique 20.250 98-18 (langues, communication, informatique, …) MG-FO Formation modulaire (Gestion de 120.000 99-18 projet, suivi et évaluation, sauvegarde environnementale, techniques de négociations, SIG, …) MG-FO Formation de l'équipe (média, 37.500 100-18 audio-visuel, design, PAO, site web, prog. éducatifs) MG-FO Formation sur les procédures de 22.500 101-18 la Banque mondiale MG-FO Organisation des ateliers 17.000 102-18 MG-FO Formation relative à l'utilisation 11.400 103-18 de logiciel SE MG-FO Renforcement de capacité des 104-18 UGL sur le SE 7.500 MG-FO Atelier participatif de Suivi 105-18 Evaluation avec UGP- UGL- 3.000 MRHP-AGEX TOTAL Renforcement de capacité 4.396.730 PROCUREMENT Southern Africa : Second South West Indian Ocean Fisheries Governance and Shared Growth Project - Madagascar PLAN General Information Country: Southern Africa Bank’s Approval Date of the Original Procurement Plan: 2017-04-06 Revised Plan Date(s): (comma delineated, leave blank 2023-05-22 if none) Project ID: P153370 GPN Date: Project Name: Second South West Indian Ocean Fisheries Governance and Shared Growth Project - Madagascar Loan / Credit No: IDA / Q9790, IDA / 59870, IDA / D1720, IDA / V0500, TF / A4588 MINISTRY OF HALIEUTIC RESSOURCES AND FISHERIES Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl Description Component Review Type Method Document Ty Amount ( mount (U t and Recommendati Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) S$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MG-MRHP-28163-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2017-09-3 2017-10-2 2017-12-0 2018-02-2 2018-04-0 2018-10- MG-PM-11 / Carénages du n IDA / D1720 g capacities for priority fish Post Request for Bids 76,000.00 0.00 Canceled al Envelope 0 1 5 4 7 04 avire de surveillance «Teloni eries management fy », MG-MRHP-28164-CW-RFB// Component 3. Strengthenin MG-PM-12 / Construction d'i g capacities for engaging in Single Stage - Two 2017-11-3 2017-12-2 2018-02-0 2018-04-2 2018-06-0 2018-12- IDA / 59870 Post Request for Bids Open - National 200,000.00 0.00 Canceled nfrastructures communautai alternative fishing practices Envelope 0 1 4 6 7 04 res /communales and livelihoods activities MG-MRHP-28634-CW-RFB// MG-PM-105 / Carénages du Component 2. Strengthenin navire de surveillance «Atsa Open - Internation Single Stage - Two 2018-02-2 2019-01-2 2018-03-1 2018-04-2 2018-08-0 2018-09-1 2019-03- IDA / D1720 g capacities for priority fish Post Request for Bids 181,000.00 0.00 Canceled ntsa », remplacement des a al Envelope 8 8 4 8 2 3 12 eries management ppareils de navigation/accés soires et pièces de rechange s desmoteurs auxiliaires Component 3. Strengthenin MG-MRHP-28642-CW-RFB// g capacities for engaging in Single Stage - Two 2018-06-2 2018-07-1 2018-08-2 2018-11-1 2018-12-2 2019-06- MG-PM-107 / Rehabilitation IDA / 59870 Post Request for Bids Open - National 50,000.00 0.00 Canceled alternative fishing practices Envelope 9 3 7 6 8 26 du CFTP Nosy be and livelihoods activities MG-MRHP-28648-CW-RFB// Component 3. Strengthenin MG-PM-110 / Infrastructures g capacities for engaging in Single Stage - One 1,250,000.0 2018-04-3 2018-05-1 2018-06-2 2018-09-2 2019-03- IDA / V0500 Post Request for Bids Open - National 0.00 Canceled d'électrification hors grille d alternative fishing practices Envelope 0 0 4 5 0 19 ans les communautés pilote and livelihoods activities s MG-MRHP-100097-CW-RFQ Component 2. Strengthenin Request for Quot Single Stage - One 2019-02-1 2018-07-2 2019-04-1 2018-09-1 2019-10- / Carénages du navire de su IDA / D1720 g capacities for priority fish Post Limited 76,000.00 101,079.93 Completed ations Envelope 7 3 4 7 11 rveillance «Telonify » eries management MG-MRHP-28432-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06- MG-PM-101 / Extension ou c IDA / 59870 g capacities for priority fish Post Request for Bids 60,000.00 0.00 Canceled al Envelope 1 5 9 8 0 27 onstruction du bureau régio eries management nal OEPA : 03 MG-MRHP-28436-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2019-07-1 2019-07-2 2019-09-1 2019-12-0 2020-01-1 2020-07- MG-PM-102 / Construction d IDA / 59870 g capacities for priority fish Post Request for Bids 40,000.00 0.00 Canceled al Envelope 5 9 2 2 3 11 u bâtiment central de l'OEPA eries management : 01 MG-MRHP-28438-CW-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06- MG-PM-103 / Mise en place IDA / 59870 g capacities for priority fish Post Request for Bids 100,000.00 0.00 Canceled al Envelope 1 5 9 8 0 27 d'infrastructure pour centre eries management de recherche CEDP MG-MRHP-119316-CW-RFB / Component 2. Strengthenin Construction bureaux USTA Single Stage - One 2019-08-0 2019-08-0 2019-09-1 2019-10-1 2019-11-2 2020-05- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 46,000.00 0.00 Canceled au niveau des antennes (Ma Envelope 1 6 7 7 1 19 eries management hajanga et Toamasina) : 02 MG-MRHP-96947-CW-RFQ B IS / Carénages du navire de Component 2. Strengthenin surveillance «Atsantsa », re Request for Quot Single Stage - One 2019-07-0 2019-02-1 2019-09-2 2019-07-1 2020-03- IDA / D1720 g capacities for priority fish Post Limited 350,000.00 309,641.94 Completed mplacement des appareils d ations Envelope 7 1 6 2 24 eries management e navigation/accessoires et pièces de rechanges des mo teurs auxiliaires MG-MRHP-119317-CW-RFB / Component 2. Strengthenin Single Stage - One 2019-07-1 2019-07-2 2019-08-3 2019-09-3 2019-11-0 2020-05- Constructions pour les six (0 IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 420,000.00 0.00 Canceled Envelope 5 0 1 0 4 02 6) DRRHP et huit (08) CIRR eries management HP MG-MRHP-28643-CW-RFB// Component 3. Strengthenin MG-PM-108 / Construction d g capacities for engaging in Single Stage - Two 2019-08-0 2019-08-1 2019-09-2 2019-12-1 2020-01-3 2020-07- IDA / 59870 Post Request for Bids Open - National 350,000.00 0.00 Canceled e petites débarcadères type alternative fishing practices Envelope 1 5 9 9 0 28 ponton and livelihoods activities MG-MRHP-119318-CW-RFB / Travaux de construction et d Component 2. Strengthenin Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-0 2020-03-2 2020-08-2 2021-08- e la réhabilitation de l’ancie IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 130,900.00 126,080.50 Signed Envelope 5 8 0 1 3 2 9 8 0 25 n bureau-logement du DRRH eries management P Analanjorofo – Region Anal anjorofo MG-MRHP-119318BIS1-CW- Component 2. Strengthenin RFB / Travaux de constructio Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-0 2020-03-2 2020-07-0 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 58,400.00 89,364.09 Signed n d'un nouveau bureau-loge Envelope 5 8 0 1 4 2 9 8 4 25 eries management ment du DRRHP Anosy - Rég ion Anosy MG-MRHP-119318BIS2-CW- Component 2. Strengthenin RFB / Travaux de réhabilitati Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-0 2020-03-2 2020-06-2 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 62,700.00 95,221.17 Signed on du bureau de la CIRRHP Envelope 5 8 0 1 4 2 9 8 4 25 eries management Maroantsetra- District Maroa ntsetra MG-MRHP-119318BIS4-CW- Component 2. Strengthenin RFB / Travaux de constructio Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-06-1 2020-03-2 2020-08-1 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 58,600.00 43,216.11 Signed n d'un nouveau bureau-loge Envelope 5 8 0 1 5 2 2 8 8 25 eries management ment ASH Morondava - Régi on Menabe MG-MRHP-28640-CW-RFB// Component 2. Strengthenin Single Stage - Two 2018-06-1 2018-06-2 2018-08-1 2018-11-0 2018-12-1 2019-06- MG-PM-106 / Constructions IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 180,000.00 0.00 Canceled Envelope 5 9 3 2 4 12 pour les six ( 06) DRRHP et eries management huit (08 )CIRRHP MG-MRHP-170956-CW-DIR / Component 2. Strengthenin 2020-05-0 2020-06-1 2020-05-2 2020-06-1 2020-07-1 2020-09-2 2021-12- Travaux de construction du IDA / 59870 g capacities for priority fish Post Direct Selection Direct 76,500.00 95,680.97 Signed 8 1 2 2 0 2 07 DRRHP Androy - Région And eries management roy MG-MRHP-170965-CW-DIR / Component 2. Strengthenin Travaux de réhabilitation du 2020-05-0 2020-06-1 2020-05-2 2020-06-1 2020-07-1 2021-03-1 2021-12- IDA / 59870 g capacities for priority fish Post Direct Selection Direct 71,000.00 71,774.44 Signed bureau-logement du DRRHP 8 1 2 2 7 8 14 eries management Melaky - Région Melaky MG-MRHP-119318BIS5-CW- Component 2. Strengthenin RFB / Travaux de réhabilitati Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-03-2 2021-08- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 71,000.00 0.00 Canceled on du bureau-logement du Envelope 5 8 0 1 6 2 8 25 eries management DRRHP Melaky - Région Mel aky MG-MRHP-119318BIS3-CW- Component 2. Strengthenin Single Stage - One 2019-07-1 2019-06-1 2019-07-2 2019-08-3 2019-07-2 2020-02-2 2020-03-2 2021-08- RFB / Travaux de constructio IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 76,500.00 0.00 Canceled Envelope 5 8 0 1 5 2 8 25 n du DRRHP Androy - Région eries management Androy MG-MRHP-28165-CW-RFB-B Component 4. Project mana Single Stage - One Terminate 2019-06-1 2019-06-1 2019-07-0 2019-08-1 2019-07-2 2019-09-1 2019-12-1 2019-10-2 2020-01-1 2021-03- IS // MG-PM-13 / Constructio IDA / 59870 Post Request for Bids Open - National 90,375.00 74,306.94 gement and coordination Envelope d 7 7 8 9 3 8 7 3 8 21 n de bureau de l'UGP central e MG-MRHP-28165-CW-RFB// Component 4. Project mana Single Stage - Two 2019-07-0 2019-06-1 2019-07-2 2019-07-1 2019-09-0 2019-07-2 2019-11-2 2020-01-0 2020-07- MG-PM-13 / Construction de IDA / 59870 Post Request for Bids Open - National 60,000.00 0.00 Canceled gement and coordination Envelope 1 7 2 8 5 3 5 6 04 bureau de l'UGP centrale MG-MRHP-203600-CW-RFB / Travaux de construction d'u Component 2. Strengthenin Single Stage - One 2020-11-2 2020-12-0 2020-12-1 2020-12-1 2021-01-0 2021-01-0 2021-02-0 2021-03-3 2021-03-1 2021-05-1 2021-07- n bureau de Circonscription IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 61,500.00 59,640.48 Signed Envelope 0 9 0 2 9 8 8 0 5 5 13 de l'Agriculture, de l'Elevage eries management et de la Pêche ( CirAEP) à A mbanja MG-MRHP-96947-CW-RFQ / Carénage du navire de surv Component 2. Strengthenin eillance "Atsantsa", remplac Request for Quot Single Stage - One 2019-03-0 2019-02-1 2019-05-2 2019-11- IDA / D1720 g capacities for priority fish Post Limited 181,000.00 0.00 Canceled ement des appareils de navi ations Envelope 8 1 8 24 eries management gation/ accessoires et pièce s de rechanges des moteurs auxiliaires. MG-MRHP-256406-CW-RFB / Request for Bids TRAVAUX DE CONSTRUCTIO Component 2. Strengthenin Single Stage - One - Works French C 2021-11-1 2021-12-0 2021-11-2 2021-12-0 2021-12-2 2022-01-0 2022-01-2 2022-01-2 2022-02-2 2022-03-1 2022-07- N D’UN BATIMENT ADMINIST IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 178,400.00 163,531.57 Signed Envelope ivil Law (French) 6 1 1 7 1 7 0 4 4 4 24 RATIF ASH TOLIARA - District eries management SPD Toliara Région ATSIMO AND REFANA MG-MRHP-262336-CW-RFQ Request for Quot Component 4. Project mana Request for Quot Single Stage - One Under Impl 2021-12-2 2023-01-1 2022-02-2 2022-08- / Construction de bureau de IDA / 59870 Post Open - National ations (Non Bank 90,375.00 0.00 gement and coordination ations Envelope ementation 0 0 1 20 l'UGP centrale (Relance) -SPD) MG-MRHP-119319-CW-RFB / Installation d'unités de fabri ques de glace/chambres froi Component 3. Strengthenin Request for Bids des fonctionnant avec des é g capacities for engaging in Single Stage - One - Works French C 2022-03-0 2022-03-0 2022-04-0 2022-05-0 2022-06-1 2022-12- IDA / 59870 Post Request for Bids Open - National 320,000.00 0.00 Canceled nergies renouvelables et res alternative fishing practices Envelope ivil Law (French) 2 7 6 6 0 07 pectant l’environnement po and livelihoods activities SPD ur maintenir la chaîne de fro id des produits halieutiques dès leur débarquement : 04 MG-MRHP-119321-CW-RFB / Construction de hangars ave c des matériaux locaux pour Component 3. Strengthenin entretenir les moteurs, les e g capacities for engaging in Single Stage - One 2021-08-0 2021-08-1 2021-09-2 2021-10-2 2021-11-2 2022-05- IDA / 59870 Post Request for Bids Open - National 240,000.00 0.00 Canceled mbarcations et des engins d alternative fishing practices Envelope 6 1 2 2 6 25 e pêche autorisés et d'une b and livelihoods activities ase de réunion, sensibilisati on et de structuration des ut ilisateurs petites infrastructu res de pêche : 08 MG-MRHP-28645-CW-RFB// Component 3. Strengthenin Request for Bids Pending Im MG-PM-109 / Construction d' g capacities for engaging in Single Stage - Two - Small Works SP 2022-08-0 2022-08-1 2022-09-2 2022-12-1 2023-01-3 2023-07- IDA / 59870 Post Request for Bids Open - National 600,000.00 0.00 plementati infrastructures communauta alternative fishing practices Envelope D (1 envelope pr 1 5 9 9 0 29 on ires /communales : 60 and livelihoods activities ocess) MG-MRHP-119320-CW-RFB / Component 3. Strengthenin Request for Bids Pending Im Construction de marchés co g capacities for engaging in Single Stage - One - Small Works SP 2022-05-0 2022-05-0 2022-06-1 2022-07-1 2022-08-2 2023-02- IDA / 59870 Post Request for Bids Open - National 300,000.00 0.00 plementati uverts aux produits halieutiq alternative fishing practices Envelope D (1 envelope pr 3 8 9 9 3 19 on ues : 10 and livelihoods activities ocess) MG-MRHP-119324-CW-RFB / Component 3. Strengthenin Request for Bids Pending Im Infrastructures d'électrificati g capacities for engaging in Single Stage - One - Small Works SP 2022-04-3 2022-05-0 2022-06-1 2022-07-1 2022-08-2 2023-02- TF / A4588 Post Request for Bids Open - National 300,000.00 0.00 plementati on hors grille dans les comm alternative fishing practices Envelope D (1 envelope pr 0 5 6 6 0 16 on unautés pilotes : 10 and livelihoods activities ocess) MG-MRHP-28632-CW-RFB// Component 2. Strengthenin MG-PM-104 / Construction d Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-12-0 2020-01-1 2020-07- IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 60,000.00 0.00 Canceled es bureaux des 2 PIE de l'AS Envelope 1 5 9 3 4 12 eries management H en province : Antsiranana et Morondava Request for Bids MG-MRHP-127603-CW-RFB / Component 2. Strengthenin Pending Im Single Stage - One - Small Works SP 2022-07-0 2022-07-2 2022-09-0 2022-10-0 2022-11-0 2023-05- Construction du siège de l'A IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 60,000.00 0.00 plementati Envelope D (1 envelope pr 1 2 2 2 6 05 SH centrale sis à Antananari eries management on ocess) vo Page 1 MG-MRHP-292931-CW-RFB / Construction des bâtiments Component 3. Strengthenin Request for Bids du kiosque de pré-électrifica g capacities for engaging in Single Stage - One - Small Works SP Under Impl 2022-05-1 2022-05-1 2022-05-1 2022-05-1 2022-06-1 2022-06-2 2022-07-1 2022-07-1 2022-08-2 2022-12- IDA / 59870 Post Request for Bids Open - National 347,450.00 0.00 tion et du «Complexe-pêche alternative fishing practices Envelope D (1 envelope pr ementation 2 2 7 6 6 0 6 5 0 18 » dans les villages de Fontsi and livelihoods activities ocess) maro et Rantohely, Région A nalanjirofo répartis en 2 lots MG-MRHP-296929-CW-RFB / Constructions des Bureaux a dministratifs de l’Autorité Sa Request for Bids nitaire Halieutique (ASH) da Component 2. Strengthenin Single Stage - One - Works French C Under Impl 2022-06-1 2022-06-1 2022-06-2 2022-06-2 2022-07-2 2022-08-1 2022-09-2 2023-02- ns la Région Vatovavy Fitovi IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 362,500.00 0.00 Envelope ivil Law (French) ementation 5 7 0 0 0 9 3 20 nany, District Manakara, Co eries management SPD mmune Manakara, Village M angarivotra et au District de Mananjary, Commune Mana njary, Village Marofinaritra ( 2 Lots) MG-MRHP-297986-CW-RFB / TRAVAUX DE CONSTRUCTIO Component 3. Strengthenin Request for Bids N DES BATIMENTS DU KIOS g capacities for engaging in Single Stage - One - Works French C 2,745,000.0 Under Impl 2022-06-1 2022-10-0 2022-06-2 2022-10-1 2022-07-2 2022-08-2 2022-09-2 2023-02- QUE DE PRE-ELECTRIFICATI IDA / 59870 Post Request for Bids Open - National 0.00 alternative fishing practices Envelope ivil Law (French) 0 ementation 6 7 1 0 1 0 4 21 ON ET DU « COMPLEXE-PEC and livelihoods activities SPD HE » DANS LE DISTRICT D’A MBILOBE, ET DANS LE DISTR ICT DE NOSY BE REPARTIS E N HUIT (08) LOTS MG-MRHP-307513-CW-RFB- Component 3. Strengthenin Request for Bids BIS / Travaux de constructio Pending Im g capacities for engaging in Single Stage - One - Works French C 2022-09-2 2022-10-0 2022-11-0 2022-12-0 2023-01-0 2023-05- n du bâtiment de Kiosque et IDA / 59870 Post Request for Bids Open - National 558,200.00 0.00 plementati alternative fishing practices Envelope ivil Law (French) 9 4 3 3 7 07 du complexe pêche Aniribe on and livelihoods activities SPD Mananara-Nord et Antoraka Maroantsetra répartis en 2 l ots MG-MRHP-320141-CW-RFB / Construction de Bâtiment ab Component 3. Strengthenin Request for Bids ritant la machine à glace rep g capacities for engaging in Single Stage - One - Works French C Under Impl 2022-10-2 2022-11-3 2022-10-2 2022-12-0 2022-11-2 2022-12-2 2023-01-2 2023-05- artis en 5 Lots dans les villa IDA / 59870 Post Request for Bids Open - National 601,000.00 0.00 alternative fishing practices Envelope ivil Law (French) ementation 1 0 6 6 5 5 9 29 ges d’Antanambao Mandrisy and livelihoods activities SPD , Hoalampano, Tampolo, Fah ambahy, Itanjona dans le dis trict de Mananara nord) MG-MRHP-320162-CW-RFB / TRAVAUX DE CONSTRUCTIO Component 3. Strengthenin Request for Bids N DES BATIMENTS DU KIOS g capacities for engaging in Single Stage - One - Works French C Under Impl 2022-10-2 2022-11-2 2022-10-2 2022-12-0 2022-11-2 2022-12-2 2023-01-2 2023-05- IDA / 59870 Post Request for Bids Open - National 852,900.00 0.00 QUE DE PRE-ELECTRIFICATI alternative fishing practices Envelope ivil Law (French) ementation 1 8 6 9 5 5 9 29 ON ET DU « COMPLEXE-PEC and livelihoods activities SPD HE » DANS LE DISTRICT D’A MBANJA REPARTIS EN TROIS (03) LOTS MG-MRHP-320156-CW-RFB / Travaux de construction des Component 3. Strengthenin Request for Bids bâtiments du kiosque de pré g capacities for engaging in Single Stage - One - Works French C Under Impl 2022-10-2 2022-10-2 2022-10-2 2022-10-3 2022-11-2 2022-11-2 2022-12-2 2023-01-2 2023-06- -électrification et du « Comp IDA / 59870 Post Request for Bids Open - National 622,000.00 0.00 alternative fishing practices Envelope ivil Law (French) ementation 1 7 6 1 5 8 5 9 28 lexe-pêche » dans les villag and livelihoods activities SPD es d'Ambalahonko et Ampas imandoro district de Maintir ano repartis en 2 lots MG-MRHP-320151-CW-RFB / Request for Bids CONSTRUCTIONS DES BURE Component 2. Strengthenin Pending Im Single Stage - One - Works French C 2022-10-2 2022-10-2 2022-11-2 2022-12-2 2023-01-2 2023-05- AUX ADMINISTRATIFS DE L'A IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 975,000.00 0.00 plementati Envelope ivil Law (French) 1 6 5 5 9 29 SH ET DE DESP (Ex-OEPA) A eries management on SPD NTANANARIVO repartis en 2 Lots MG-MRHP-332561-CW-RFB / Travaux de construction des Request for Bids Bureaux de la circonscriptio Component 2. Strengthenin Pending Im Single Stage - One - Works French C 2023-01-1 2023-01-1 2023-02-1 2023-03-1 2023-04-2 2023-08- n en charge de la pèche et d IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 708,427.00 0.00 plementati Envelope ivil Law (French) 0 5 4 6 0 18 e l’économie bleu et l’anten eries management on SPD ne du centre de la surveillan ce des pêches à Maintirano, Région Melaky MG-MRHP-337958-CW-RFB / Component 3. Strengthenin Request for Bids Construction de Bâtiment ab g capacities for engaging in Single Stage - One - Small Works SP Under Impl 2023-01-2 2023-02-0 2023-02-0 2023-02-0 2023-03-0 2023-03-1 2023-03-2 2023-07- ritant la chambre froide dan IDA / 59870 Post Request for Bids Open - National 410,000.00 0.00 alternative fishing practices Envelope D (1 envelope pr ementation 7 3 1 6 3 3 3 21 s le village de RANTABE dan and livelihoods activities ocess) s le district de MAROANTSET RA, Région ANALANJIROFO MG-MRHP-337965-CW-RFB / Component 3. Strengthenin Request for Bids CONSTRUCTION DES DEUX ( Pending Im g capacities for engaging in Single Stage - One - Works French C 2023-01-3 2023-02-0 2023-03-0 2023-03-1 2023-03-2 2023-07- 02) MARCHES COUVERTS D IDA / 59870 Post Request for Bids Open - National 250,000.00 0.00 plementati alternative fishing practices Envelope ivil Law (French) 1 5 7 7 5 23 ANS LE DISTRICT DE MANAN on and livelihoods activities SPD ARA NORD REPARTIE EN DE UX (02) LOTS Request for Bids MG-MRHP-262336-BIS-CW- Component 4. Project mana Single Stage - One - Works French C Under Impl 2023-01-2 2023-01-1 2023-02-0 2023-02-0 2023-03-0 2023-03-1 2023-03-2 2023-07- RFQ / Construction de burea IDA / 59870 Post Request for Bids Open - National 90,375.00 0.00 gement and coordination Envelope ivil Law (French) ementation 9 0 3 8 5 5 3 21 u de l’UGP centrale (Relance SPD ) MG-MRHP-340927-CW-RFB / Travaux de construction des Component 3. Strengthenin Request for Bids bâtiments du kiosque de pré Pending Im g capacities for engaging in Single Stage - One - Works French C 2023-02-1 2023-02-1 2023-03-2 2023-04-1 2023-04-2 2023-08- électrification et du "Comple IDA / 59870 Post Request for Bids Open - National 222,300.00 0.00 plementati alternative fishing practices Envelope ivil Law (French) 4 9 1 1 8 26 xe pêche" dans le village d' on and livelihoods activities SPD Andranonabo, Commune Anj iabe ambony, District d'Amb ilobe (RELANCE) MG-MRHP-344175-CW-RFB / Request for Bids Travaux de construction des Component 2. Strengthenin Single Stage - One - Small Works SP 1,352,000.0 Under Impl 2023-02-2 2023-03-1 2023-03-0 2023-03-1 2023-03-3 2023-04-1 2023-04-1 2023-08- bâtiments Administratifs du IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 0.00 Envelope D (1 envelope pr 0 ementation 4 1 1 5 1 0 4 12 MPEB dans les régions de D eries management ocess) IANA- MELAKY- ANOSY repar tie en 04 lots MG-MRHP-344184-CW-RFB / Request for Bids Travaux de construction des Component 2. Strengthenin Single Stage - One - Works French C Under Impl 2023-02-2 2023-03-1 2023-03-0 2023-04-1 2023-03-3 2023-04-1 2023-04-1 2023-08- bâtiments Administratifs du IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 620,000.00 0.00 Envelope ivil Law (French) ementation 4 1 1 1 1 0 4 12 MPEB dans les régions de B eries management SPD OENY et ATSIMO ANTSINANA NA repartie en 02 lots MG-MRHP-344311-CW-DIR / Travaux additionnels de con Component 2. Strengthenin Request for Quot Pending Im struction du bureau, de Han 2023-04-0 2023-04-2 2023-05-0 2023-08- TF / A4588 g capacities for priority fish Post Direct Selection Direct - National ations (Non Bank 230,000.00 0.00 plementati gar pour la vedette de la bri 7 7 3 31 eries management -SPD) on gade du CSP Analanjirofo, et mise en place d’un point d’eau autonome par Entrepr ise FITALIA Request for Bids MG-MRHP-127600-CW-RFB / Component 2. Strengthenin Pending Im Single Stage - One - Small Works SP 2023-05-0 2023-05-0 2023-06-0 2023-06-2 2023-07-1 2023-09- Renforcement du CDA - Con IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 36,850.00 0.00 plementati Envelope D (1 envelope pr 2 7 6 7 1 29 struction puits et réhabilitati eries management on ocess) on clôture CDA MG-MRHP-337960-CW-RFB / Travaux de construction des Component 3. Strengthenin Request for Bids bâtiments abritant la machi g capacities for engaging in Single Stage - One - Small Works SP Under Impl 2023-05-0 2023-05-0 2023-05-0 2023-05-0 2023-06-0 2023-06-1 2023-07-0 2023-09- ne à glace dans les villages IDA / 59870 Post Request for Bids Open - National 357,400.00 0.00 alternative fishing practices Envelope D (1 envelope pr ementation 3 3 3 9 2 6 7 29 de Maintimbato, Mahasoa, A and livelihoods activities ocess) mbodipaka, Masindrano da ns le district de Maroantsetr a repartis en 4 lots MG-MRHP-337959-CW-RFB / Component 3. Strengthenin Request for Bids Travaux de construction des g capacities for engaging in Single Stage - One - Works French C Under Impl 2023-04-2 2023-04-2 2023-04-2 2023-05-2 2023-05-2 2023-06-1 2023-07-1 2023-09- bâtiments abritant la machi IDA / 59870 Post Request for Bids Open - National 198,000.00 0.00 alternative fishing practices Envelope ivil Law (French) ementation 9 8 9 2 9 2 0 29 ne à glace et magasin de st and livelihoods activities SPD ockage dans le district de N osy be répartis en 2 lots GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) atus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-28121-GO-UN// M Component 2. Strengthenin UN Agencies (Dir 2017-09-3 2017-10-2 2017-12-2 2018-06-2 G-PM-01 / Matériels et équip IDA / 59870 g capacities for priority fish Post Direct 315,310.00 0.00 Canceled ect) 0 1 3 1 ements informatiques et bur eries management eautiques MG-MRHP-28129-GO-RFB// Component 2. Strengthenin MG-PM-02 / Kits d'équipeme Open - Internation Single Stage - Two 2017-10-1 2017-11-0 2017-12-1 2018-03-0 2018-04-1 2018-10-1 IDA / D1720 g capacities for priority fish Post Request for Bids 17,500.00 0.00 Canceled nts pour les enquêteurs (sa al Envelope 5 5 7 8 9 6 eries management c de couchage, tente, torche , bottes, impermeable) MG-MRHP-28136-GO-UN//M Component 2. Strengthenin UN Agencies (Dir Pending Imp 2017-09-3 2017-10-2 2017-12-2 2018-06-2 G-PM-03 / Acquisition de Vé IDA / 59870 g capacities for priority fish Post Direct 1,830,000.00 0.00 ect) lementation 0 1 3 1 hicule eries management MG-MRHP-28157-GO-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2017-10-3 2017-11-2 2018-01-0 2018-03-2 2018-05-0 2018-11-0 MG-PM-05 / Acquisition de fo IDA / 59870 g capacities for priority fish Post Request for Bids 29,170.00 0.00 Canceled al Envelope 0 0 4 6 7 3 urnitures et articles de bure eries management au MG-MRHP-28158-GO-UN//M Component 2. Strengthenin UN Agencies (Dir Pending Imp 2017-09-3 2017-10-2 2017-12-2 2018-06-2 G-PM-06 / Acquisition de Mot IDA / 59870 g capacities for priority fish Post Direct 59,000.00 0.00 ect) lementation 0 1 3 1 o eries management MG-MRHP-28159-GO-UN//M Component 2. Strengthenin UN Agencies (Dir 2017-10-1 2017-11-0 2018-01-0 2018-07-0 G-PM-07 / Acquisition de Dro IDA / D1720 g capacities for priority fish Post Direct 5,000.00 0.00 Canceled ect) 6 6 8 7 ne pour surveillance et contr eries management ôle MG-MRHP-28160-GO-RFB// Component 2. Strengthenin Open - Internation Single Stage - Two 2017-10-3 2017-11-2 2018-01-0 2018-03-2 2018-05-0 2018-11-0 MG-PM-08 / Acquisition de M IDA / 59870 g capacities for priority fish Post Request for Bids 120,000.00 0.00 Canceled al Envelope 0 0 4 6 7 3 atériels et Mobiliers de bure eries management au MG-MRHP-28161-GO-RFB// MG-PM-09 / Appui à la mise Component 3. Strengthenin à disposition des équipemen g capacities for engaging in Open - Internation Single Stage - Two 2017-11-1 2017-12-0 2018-01-2 2018-04-1 2018-05-2 2018-11-1 IDA / 59870 Post Request for Bids 65,000.00 0.00 Canceled ts de base pour la sécurité d alternative fishing practices al Envelope 5 6 0 1 3 9 es pêcheurs et de leurs emb and livelihoods activities arcations en mer (gilet, miro ir... pour la période transitoir e) MG-MRHP-28162-GO-RFB// Component 2. Strengthenin Single Stage - One 2017-11-1 2017-12-0 2018-01-2 2018-02-1 2018-04-0 2018-09-2 MG-PM-10 / Acquisition de C IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 25,170.00 0.00 Canceled Envelope 5 6 0 9 2 9 onsommables informatiques eries management (Lot) MG-MRHP-28397-GO-RFB// Component 2. Strengthenin MG-MP-89 / Acquisition et in Open - Internation Single Stage - Two 2018-06-1 2018-06-2 2018-08-1 2018-11-0 2018-12-1 2019-06-1 IDA / D1720 g capacities for priority fish Post Request for Bids 150,000.00 0.00 Canceled stallation d'un logiciel de sui al Envelope 5 9 3 2 4 2 eries management vi automatique des captures (ERS) MG-MRHP-28401-GO-RFB// Component 3. Strengthenin MG-PM-90 / Matériels de bur g capacities for engaging in Open - Internation Single Stage - Two 2018-06-1 2018-06-2 2018-08-1 2018-11-0 2018-12-1 2019-06-1 eau du CFTP (06 lots compo IDA / 59870 Post Request for Bids 6,000.00 0.00 Canceled alternative fishing practices al Envelope 5 9 3 2 4 2 sés de table de bureau, chai and livelihoods activities se de bureau, chaise visiteu se et armoire ) MG-MRHP-28406-GO-RFB// MG-PM-93 / Acquisition des Component 3. Strengthenin équipements de base pour l g capacities for engaging in Open - Internation Single Stage - Two 2018-01-3 2018-02-1 2018-03-3 2018-06-1 2018-07-3 2019-01-2 IDA / 59870 Post Request for Bids 100,000.00 0.00 Canceled a sécurité des pêcheurs et d alternative fishing practices al Envelope 0 3 0 9 1 7 e leurs embarcations en mer and livelihoods activities (gilet, miroir... pour la périod e transitoire) MG-MRHP-28415-GO-RFB// Component 3. Strengthenin MG-PM-96 / Acquisition d'out g capacities for engaging in Single Stage - Two 2018-03-3 2018-04-1 2018-05-2 2018-08-1 2018-09-2 2019-03-2 IDA / 59870 Post Request for Bids Open - National 19,000.00 0.00 Canceled illage pour les pépinières et alternative fishing practices Envelope 0 3 8 7 8 7 les reboisements (brouette,. and livelihoods activities ...) Page 2 MG-MRHP-28431-GO-RFB// MG-PM-100 / Acquisition de Component 3. Strengthenin mobiliers de bureau pour Ge g capacities for engaging in Single Stage - Two 2018-05-1 2018-05-2 2018-07-1 2018-10-0 2018-11-1 2019-05-1 stion et mise en œuvre : (0 IDA / V0500 Post Request for Bids Open - National 40,000.00 0.00 Canceled alternative fishing practices Envelope 5 9 3 2 3 2 3 lots composés de 01 table and livelihoods activities de bureau, 01 chaise de bur eau, 02 chaises visiteurs et 01 armoire de rangement se mi vitré ) MG-MRHP-23399-GO-UN / A Component 2. Strengthenin UN Agencies (Dir 2017-08-1 2017-09-0 2017-11-0 2018-05-0 chat de lot de Matériel infor IDA / Q9790 g capacities for priority fish Post Direct 201,660.00 0.00 Canceled ect) 5 5 7 6 matique (Année 2017) eries management Component 3. Strengthenin MG-MRHP-85764-GO-RFQ // g capacities for engaging in Request for Quot Single Stage - One 2018-12-1 2019-04-1 2019-10-1 MG-PM 18/18 / Achat de 79 IDA / 59870 Post Limited 3,950.00 0.00 Canceled alternative fishing practices ations Envelope 5 4 1 boites à plaintes and livelihoods activities MG-MRHP-28404-GO-RFB// Component 3. Strengthenin MG-PM-91 / Acquisition d'éq g capacities for engaging in Open - Internation Single Stage - Two 2019-07-1 2019-07-3 2019-09-1 2019-12-0 2020-01-1 2020-07-1 IDA / 59870 Post Request for Bids 320,000.00 0.00 Canceled uipements et outils de pêch alternative fishing practices al Envelope 6 0 3 3 4 2 e and livelihoods activities MG-MRHP-28405-GO-RFB// Component 3. Strengthenin MG-PM-92 / Acquisition d'out g capacities for engaging in Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06-2 IDA / 59870 Post Request for Bids 185,000.00 0.00 Canceled illage d'entretien d'engin et alternative fishing practices al Envelope 1 5 9 8 0 7 d'embarcation de pêche pou and livelihoods activities r usage communautaire MG-MRHP-119305-GO-RFQ / Component 3. Strengthenin Appui à l'acquisition de mat g capacities for engaging in Request for Quot Single Stage - One 2019-07-0 2019-08-3 2020-02-2 IDA / 59870 Post Limited 100,000.00 0.00 Canceled ériels de sécurité aux pêche alternative fishing practices ations Envelope 6 1 7 urs et communauté de pêch and livelihoods activities eurs : 2000 Component 3. Strengthenin MG-MRHP-28410-GO-RFB// g capacities for engaging in Open - Internation Single Stage - Two 2018-05-1 2018-05-2 2018-07-1 2018-10-0 2018-11-1 2019-05-1 MG-PM-94 / Acquisition d'out IDA / 59870 Post Request for Bids 80,000.00 0.00 Canceled alternative fishing practices al Envelope 5 9 3 2 3 2 ils de valorisation and livelihoods activities MG-MRHP-28411-GO-RFB// Component 3. Strengthenin MG-PM-95 / Acquisition des g capacities for engaging in Open - Internation Single Stage - Two 2019-07-0 2019-07-1 2019-08-2 2019-11-1 2019-12-3 2020-06-2 IDA / 59870 Post Request for Bids 80,000.00 0.00 Canceled petits matériels de valorisati alternative fishing practices al Envelope 1 5 9 8 0 7 on and livelihoods activities Component 3. Strengthenin MG-MRHP-119309-GO-RFQ / g capacities for engaging in Request for Quot Single Stage - One 2019-06-2 2019-08-1 2019-07-1 2020-02-1 2019-08-1 IDA / 59870 Post Open - National 5,250.00 7,885.75 Completed Achat boites à plaintes : 105 alternative fishing practices ations Envelope 3 8 6 4 4 and livelihoods activities Component 3. Strengthenin MG-MRHP-119311-GO-RFQ / g capacities for engaging in Request for Quot Single Stage - One 2019-07-2 2019-10-0 2019-09-1 2020-01-1 2020-03-1 2020-02-0 Achat puce et téléphone por IDA / 59870 Post Limited 5,250.00 11,213.00 Completed alternative fishing practices ations Envelope 0 9 4 1 2 1 table : 105 and livelihoods activities MG-MRHP-28121-GO-UN// M Component 2. Strengthenin Request for Prop Single Stage - One 2019-07-3 2019-09-1 2019-08-2 2019-10-0 2019-10-0 2019-11-0 2019-11-0 2020-04-1 2019-12-1 2020-06-1 2020-06-1 2020-09-2 G-PM-01-2 / Matériels inform IDA / 59870 g capacities for priority fish Post Open - National 156,370.00 141,053.48 Completed osals Envelope 1 4 1 9 2 8 1 5 3 0 0 8 atiques 2019 eries management MG-MRHP-86177-GO-RFQ// Component 2. Strengthenin MG-PM 08/18 / Achat téléph Request for Quot Single Stage - One 2019-08-2 2019-07-2 2020-01-0 2019-09-0 2020-07-0 2019-09-2 IDA / V0500 g capacities for priority fish Post Limited 10,500.00 10,073.72 Completed one mobile pour la collecte ations Envelope 4 4 6 4 4 5 eries management de données au niveau natio nal MG-MRHP-28160-GO-RFB// Component 2. Strengthenin Request for Quot Single Stage - One 2019-07-2 2019-08-2 2019-09-1 2019-09-0 2020-03-1 2019-09-1 MG-PM-08-2 / Matériels et m IDA / 59870 g capacities for priority fish Post Limited 33,200.00 19,057.68 Completed ations Envelope 0 9 4 5 2 0 obiliers de bureau 2019 eries management MG-MRHP-28161-GO-RFB// MG-PM-09-2 / Appui à la mis Component 3. Strengthenin e à disposition des équipem g capacities for engaging in Single Stage - One 2019-07-1 2019-09-1 2019-07-2 2019-10-0 2019-08-3 2019-11-0 2019-09-3 2019-11-0 2020-05-0 ents de base pour la sécurit IDA / 59870 Post Request for Bids Open - National 330,000.00 0.00 Canceled alternative fishing practices Envelope 5 6 0 9 1 8 0 4 2 é des pêcheurs et de leurs e and livelihoods activities mbarcations en mer (gilet, miroir… pour la période tran sitoire) : 3300 MG-MRHP-28161 BIS-GO-RF Component 3. Strengthenin B // MG-PM-09-2 / Acquisitio g capacities for engaging in Single Stage - One 2019-12-2 2019-12-3 2019-12-2 2019-12-3 2020-01-2 2020-01-3 2020-02-1 2020-04-0 2020-03-0 2020-04-2 2020-06-0 n de 3300 kits de sécurité e IDA / 59870 Post Request for Bids Open - National 330,000.00 106,992.01 Signed alternative fishing practices Envelope 0 1 7 1 6 1 6 7 4 8 2 n mer pour les petits pêcheu and livelihoods activities rs (gilet, miroir… pour la pér iode transitoire) MG-MRHP-160447-GO-RFQ / Component 2. Strengthenin Fourniture des plaques d'im Request for Quot Single Stage - One 2020-03-1 2020-08-2 2020-04-1 2020-11-0 2020-05-1 2020-12-1 IDA / 59870 g capacities for priority fish Post Limited 100,000.00 18,218.09 Completed matriculations des pirogues ations Envelope 1 5 5 4 5 8 eries management (lot unique et indivisible) MG-MRHP-161268-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2020-02-2 2020-02-1 2020-03-0 2020-03-0 2020-03-1 Fourniture des carnets d'exp IDA / 59870 g capacities for priority fish Post Limited 8,400.00 8,166.14 Signed ations Envelope 7 8 6 5 3 édition des produits halieuti eries management ques MG-MRHP-127597-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2020-09-1 2020-12-1 2021-06-0 200 équipements et outils d IDA / 59870 g capacities for priority fish Post Limited 40,000.00 0.00 ations Envelope lementation 1 1 9 e pêches eries management MG-MRHP-119304-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2020-08-0 2020-09-2 2021-03-2 Matériels de l'électrification IDA / 59870 g capacities for priority fish Post Limited 9,000.00 0.00 ations Envelope lementation 4 9 8 hors grille : 03 eries management MG-MRHP-119300BIS-GO-R Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2019-06-0 2019-08-2 2020-02-2 FQ / Acquisition d'une Vedet TF / A4588 g capacities for priority fish Post Limited 100,000.00 0.00 ations Envelope lementation 8 6 2 te pour appui CSP eries management Component 3. Strengthenin MG-MRHP-85764 BIS-GO-RF g capacities for engaging in Request for Quot Single Stage - One 2020-05-1 2020-05-0 2020-07-0 2020-06-1 2020-08-0 Q / Achat de 155 boites à pl IDA / 59870 Post Limited 12,000.00 11,910.86 Signed alternative fishing practices ations Envelope 3 8 8 0 7 aintes pour l'exercice 2020 and livelihoods activities MG-MRHP-174399-GO-RFQ / Component 3. Strengthenin Acquisition de 160 téléphon g capacities for engaging in Request for Quot Single Stage - One Under Imple 2020-05-3 2020-06-0 2020-07-2 2020-08-2 IDA / 59870 Post Limited 15,000.00 0.00 es mobiles pour le Mécanis alternative fishing practices ations Envelope mentation 1 3 6 5 me De Gestion des Plaintes and livelihoods activities (MDGP) / Exercice 2020 MG-MRHP-119314-GO-RFQ / Component 3. Strengthenin Achat de vedette pour la mi g capacities for engaging in Request for Quot Single Stage - One 2020-07-2 2020-09-1 2021-03-1 IDA / 59870 Post Limited 80,000.00 0.00 Canceled se en œuvre des activités d alternative fishing practices ations Envelope 0 4 3 ans la région Melaky :1 and livelihoods activities MG-MRHP-119300-GO-RFB / Acquisition de Cinq (05) Ved ettes pour CSP réparties en deux (02) lots: Component 2. Strengthenin - Lot 01: Acquisition de 03 V Single Stage - One 2020-04-1 2020-04-2 2020-06-0 2020-07-0 2020-08-0 2021-02-0 TF / A4588 g capacities for priority fish Post Request for Bids Open - National 321,500.00 0.00 Canceled edettes pour appuyer le CSP Envelope 5 0 1 1 5 1 eries management pour les nouvelles antennes au niveau des ZUP; - Lot 02: Acquisition de 02 v edettes rapides semi-rigides pour patrouilleurs MG-MRHP-119300BIS1-GO- RFB / Acquisition des vedett es réparties en 02 Lots : Component 2. Strengthenin Single Stage - One Under Imple 2020-06-1 2020-06-1 2020-06-1 2020-06-1 2020-07-1 2020-08-1 2020-09-1 2020-12-1 • Lot1 : 07 vedettes coque IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 551,500.00 0.00 Envelope mentation 5 2 6 9 6 5 9 8 s rigides ; eries management • Lot2 : 02 vedettes rapid es semi-rigides. MG-MRHP-28415-GO-RFB // Component 3. Strengthenin MG-PM-96 BIS / Outillage po g capacities for engaging in Request for Quot Single Stage - One 2020-04-2 2020-06-1 2020-12-1 IDA / 59870 Post Limited 19,000.00 0.00 Canceled ur les pépinières et les reboi alternative fishing practices ations Envelope 0 5 2 sements (brouette,….) : 19 and livelihoods activities MG-MRHP-14629-GO-RFQ// Component 2. Strengthenin Request for Quot Single Stage - One 2020-09-2 2021-03-2 2020-11-1 2021-04-1 2020-12-1 PA 2 / PA2: Acquisition d'un l IDA / Q9790 g capacities for priority fish Post Limited 11,000.00 4,352.99 Signed ations Envelope 9 6 7 6 7 ot de matériels de formation eries management et d'enquête MG-MRHP-119240-GO-RFB / Component 2. Strengthenin Renforcement du Centre de Single Stage - Two 2020-07-3 2020-08-0 2020-09-1 2020-11-2 2021-01-0 2021-07-0 IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 580,000.00 0.00 Canceled Développement de l'Aquacul Envelope 0 4 5 8 2 1 eries management ture (CDA) -Equipement der echerche MG-MRHP-188316-GO-RFB / Component 3. Strengthenin Fourniture et livraison de 11 g capacities for engaging in Open - Internation Single Stage - One 2020-08-1 2020-08-2 2020-08-1 2020-08-2 2020-09-2 2020-10-2 2020-10-1 2020-11-1 2020-11-1 2021-01-1 2021-01-1 IDA / 59870 Post Request for Bids 1,170,000.00 432,020.22 Signed .700 lots d'équipements de alternative fishing practices al Envelope 4 6 5 6 9 0 4 3 1 9 0 base pour la sécurité en mer and livelihoods activities MG-MRHP-192172-GO-RFQ / Achat de 15.000 Caches bou Component 4. Project mana Request for Quot Single Stage - One 2020-09-2 2020-11-1 2021-05-1 IDA / 59870 Post Limited 11,500.00 0.00 Canceled che avec logo SWIOFish2 po gement and coordination ations Envelope 2 7 6 ur les trois (03) UGL's et l'U GP du projet SWIOFish2 MG-MRHP-119300 RELANCE -GO-RFB / Acquisition des ve Component 2. Strengthenin Single Stage - One Under Imple 2021-01-1 2021-02-1 2021-01-2 2021-02-1 2021-03-0 2021-03-2 2021-04-0 2021-05-1 2021-11-0 dettes réparties en 02 Lots : IDA / 59870 g capacities for priority fish Post Request for Bids Limited 551,500.00 0.00 Envelope mentation 9 5 4 6 7 2 6 1 7 • Lot1 : 07 vedettes coques eries management rigides ; • Lot2 : 02 vedettes rapides semi-rigides. MG-MRHP-218714-GO-RFB / Component 2. Strengthenin Single Stage - One 2021-03-0 2021-03-3 2021-03-0 2021-04-0 2021-04-0 2021-05-0 2021-05-0 2021-07-1 2021-06-0 2021-11-0 2021-08-2 Acquisition des matériels inf IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 316,100.00 402,663.35 Signed Envelope 1 0 6 6 5 3 5 6 9 6 3 ormatiques 2020 et 2021 eries management MG-MRHP-119306-GO-RFQ / Component 3. Strengthenin Appui en biens et équipeme g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2021-03-1 2021-05-0 2021-11-0 nts des groupements formel IDA / 59870 Post Limited 6,400.00 0.00 alternative fishing practices ations Envelope lementation 4 9 5 s: 32/ répartis en 2 Lots: Lot and livelihoods activities 1: Glacières; Lot 2: Couteau x MG-MRHP-203606-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2021-03-2 2021-05-2 2021-04-2 2021-07-1 2021-05-0 Acquisitions des téléphones IDA / 59870 g capacities for priority fish Post Open - National 19,200.00 17,632.53 Completed ations Envelope 0 9 0 3 1 mobiles pour l'UGP- SRPA et eries management RPA MG-MRHP-222323-GO-RFQ / Component 2. Strengthenin Acquisition d'une vedette et Request for Quot Single Stage - One Pending Imp 2021-04-0 2021-06-2 2021-09-0 IDA / 59870 g capacities for priority fish Post Limited 45,000.00 0.00 des autres équipements pou ations Envelope lementation 5 3 6 eries management r la prospections de nouvell e zone de pêche MG-MRHP-216847-GO-RFB / Component 3. Strengthenin Achat, installation et mainte g capacities for engaging in Open - Internation Single Stage - One 2021-04-1 2021-03-3 2021-04-2 2021-03-3 2021-06-0 2021-05-1 2021-06-2 2021-09-1 2021-07-3 2021-10-2 2022-01-2 IDA / 59870 Post Request for Bids 1,615,000.00 1,541,854.13 Signed nance d'équipements photo alternative fishing practices al Envelope 5 0 0 1 4 7 5 3 0 3 6 voltaïque pour 20 kiosques and livelihoods activities multiservices MG-MRHP-224078-GO-RFB / Component 3. Strengthenin Achat, installation et mainte g capacities for engaging in Open - Internation Single Stage - One 2021-04-1 2021-03-3 2021-04-2 2021-03-3 2021-06-0 2021-05-1 2021-07-0 2021-07-1 2021-08-0 2021-10-1 2022-02-0 IDA / 59870 Post Request for Bids 990,300.00 873,533.21 Signed nance d'équipements frigorif alternative fishing practices al Envelope 5 0 0 1 4 8 4 2 8 6 4 iques et de glace pour 20 ki and livelihoods activities osques multiservices MG-MRHP-227238-GO-RFB / Component 3. Strengthenin Fourniture et livraison des é g capacities for engaging in Open - Internation Single Stage - One 2021-05-1 2021-05-1 2021-05-2 2021-05-1 2021-07-0 2021-07-1 2021-07-3 2021-11-3 2021-09-0 2022-01-1 2022-03-0 IDA / 59870 Post Request for Bids 1,200,000.00 780,301.00 Signed quipements de base pour la alternative fishing practices al Envelope 5 7 0 8 1 9 1 0 4 7 3 sécurité en mer pour l'anné and livelihoods activities e 2021 et 2022 MG-MRHP-231608-GO-RFB / Component 2. Strengthenin Open - Internation Single Stage - One 2021-05-1 2022-05-1 2021-05-1 2022-05-1 2021-06-3 2022-06-3 2021-07-3 2022-09-1 2021-09-0 2022-03-0 Matériels et équipements po IDA / V0500 g capacities for priority fish Post Request for Bids 680,000.00 0.00 Signed al Envelope 4 0 9 6 0 0 0 3 3 2 ur laboratoire CEDP-CDA et eries management USTA Page 3 MG-MRHP-119240 BIS-GO-R Component 2. Strengthenin FB / Renforcement du Centr Single Stage - One 2021-03-2 2021-03-3 2021-04-3 2021-05-3 2021-07-0 2021-10-0 IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 580,000.00 0.00 Canceled e de Développement de l'Aq Envelope 6 1 0 0 4 2 eries management uaculture (CDA) -Equipemen t de recherche MG-MRHP-28156-GO-UN//-M Component 2. Strengthenin UN Agencies (Dir 2020-11-0 2020-11-2 2021-01-2 2021-07-2 G-PM-04 / Matériels et équip IDA / 59870 g capacities for priority fish Post Direct 50,000.00 0.00 Canceled ect) 2 3 5 4 ements pour laboratoire CE eries management DP MG-MRHP-232523-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2021-05-2 2021-07-2 2021-10-0 Acquisition d'une vedette fri IDA / 59870 g capacities for priority fish Post Limited 73,000.00 0.00 ations Envelope lementation 5 0 3 gorifique CDPHM eries management MG-MRHP-231602-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2021-05-2 2021-07-2 2022-01-1 Acquisition de Drones pour IDA / D1720 g capacities for priority fish Post Limited 26,000.00 0.00 ations Envelope lementation 5 0 6 CSC, formation et service ap eries management rès vente MG-MRHP-232525-GO-RFQ / Component 2. Strengthenin Acquisition des matériels ro Request for Quot Single Stage - One Pending Imp 2021-05-2 2021-07-2 2021-10-1 IDA / 59870 g capacities for priority fish Post Open - National 86,000.00 0.00 ulants ( 02 camions Frigorifi ations Envelope lementation 6 1 9 eries management ques de capacité 5 tonnes) pour les sites du CDPHM MG-MRHP-232534-GO-RFQ / Component 4. Project mana Request for Quot Single Stage - One 2021-05-2 2021-12-0 2021-07-2 2022-03-1 2022-01-1 Acquisition et installation d' IDA / Q9790 Post Open - National 50,000.00 20,955.96 Signed gement and coordination ations Envelope 5 9 0 2 6 un logiciel de suivi évaluatio n MG-MRHP-119295-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2021-03-1 2021-05-1 2021-11-0 Achat de Lot d'équipements IDA / 59870 g capacities for priority fish Post Limited 10,000.00 0.00 Canceled ations Envelope 5 0 6 pour laboratoire USTA eries management MG-MRHP-119300 RELANCE Component 2. Strengthenin LOT2-GO-RFB / Acquisition d Single Stage - One 2021-11-3 2021-12-1 2021-12-0 2021-12-2 2021-12-3 2022-03-1 2022-01-3 2022-03-0 2022-06-0 TF / A4588 g capacities for priority fish Post Request for Bids Open - National 170,000.00 0.00 Canceled e 02 vedettes rapides semi-r Envelope 0 7 1 1 1 0 0 6 4 eries management igides pour CSP (Relance Lot 2) MG-MRHP-262317-GO-RFQ / Component 2. Strengthenin Acquisition des matériels inf Request for Quot Single Stage - One 2021-12-0 2021-12-0 2022-01-3 2022-04-3 IDA / 59870 g capacities for priority fish Post Open - National 93,600.00 0.00 Canceled ormatiques 2020 et 2021 (re ations Envelope 5 9 0 0 eries management lance lot 8: tablettes) MG-MRHP-284470-GO-RFQ / Component 2. Strengthenin Single Stage - One Under Imple 2022-04-1 2022-05-0 2022-04-2 2022-05-3 2022-06-0 2022-07-0 2022-08-0 2023-02-0 Acquisition mobiliers de bur IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 427,553.00 0.00 Envelope mentation 5 6 0 0 1 1 5 1 eau pour les bureaux admini eries management stratifs 2022-2023 Component 3. Strengthenin MG-MRHP-28421-GO-RFB// g capacities for engaging in Single Stage - One Pending Imp 2020-09-1 2020-09-2 2020-11-0 2020-12-0 2021-01-0 2021-07-0 MG-PM-99 / Acquisition des IDA / V0500 Post Request for Bids Open - National 500,000.00 0.00 alternative fishing practices Envelope lementation 7 2 3 3 7 6 kits de panneaux solaires and livelihoods activities MG-MRHP-119315-GO-RFQ / Component 3. Strengthenin Renforcement de l'unité de g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-05-0 2022-06-3 2022-12-2 IDA / 59870 Post Limited 55,000.00 0.00 gestion communautaire en b alternative fishing practices ations Envelope lementation 5 0 7 iens et équipements : 22 and livelihoods activities MG-MRHP-289660-GO-RFQ / Component 3. Strengthenin Équipements et outils de for g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-04-2 2022-06-1 2022-12-1 IDA / 59870 Post Open - National 100,000.00 0.00 mation de technique de pêc alternative fishing practices ations Envelope lementation 3 8 5 he: palangre and livelihoods activities MG-MRHP-289646-GO-RFQ / Component 3. Strengthenin Equipement pour la commer g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-04-2 2022-06-1 2022-12-1 IDA / 59870 Post Open - National 40,000.00 0.00 cialisation des produits de p alternative fishing practices ations Envelope lementation 1 6 3 êche and livelihoods activities MG-MRHP-231589-GO-RFQ / Component 2. Strengthenin Acquisition de 20 tablettes Request for Quot Single Stage - One Pending Imp 2022-07-0 2022-08-3 2022-10-3 IDA / V0500 g capacities for priority fish Post Open - National 37,000.00 0.00 marinisées pour le Centre d ations Envelope lementation 6 1 0 eries management e Surveillance de Pêche MG-MRHP-119303-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2022-11-0 2023-01-0 2023-06-3 Dotation et moyens d'équip TF / A4588 g capacities for priority fish Post Limited 48,000.00 0.00 ations Envelope lementation 6 1 0 ement pour les membres du eries management CSC : 24 MG-MRHP-119300_2ÈME RE Component 2. Strengthenin LANCE LOT2-GO-RFB / Acqui Open - Internation Single Stage - One Under Imple 2022-05-3 2022-05-2 2022-06-0 2022-05-2 2022-07-1 2022-07-1 2022-08-0 2022-09-1 2022-12-1 TF / A4588 g capacities for priority fish Post Request for Bids 170,000.00 0.00 sition de 02 vedettes rapide al Envelope mentation 0 3 4 5 9 1 9 3 2 eries management s semi-rigides pour CSP MG-MRHP-262317-GO-RFQ- 2ÈME RELANCE / ACQUISITI Component 2. Strengthenin ON DES TABLETTES POUR C Request for Quot Single Stage - One Pending Imp 2022-06-0 2022-07-1 2022-09-1 IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 ENTRE DE SURVEILLANCE D ations Envelope lementation 4 6 4 eries management E PÊCHE, STATISTIQUE ET 1 3 RÉGIONS CÔTIÈRES DE L’U GP SWIOFISH2 MG-MRHP-296825-GO-RFQ / Component 2. Strengthenin Acquisition des smartphones Request for Quot Single Stage - One 2022-06-1 2022-10-2 2022-08-0 2022-09-0 TF / A4588 g capacities for priority fish Post Open - National 30,000.00 0.00 Signed pour la collecte des données ations Envelope 3 7 8 7 eries management pour le Service d'Etude MPE B MG-MRHP-119299-GO-RFQ / Matériels d'échantillonnages Component 2. Strengthenin Request for Quot Single Stage - One Under Imple 2022-06-2 2023-04-1 2022-08-1 2022-08-2 pour Services d'Etudes (Ex- TF / A4588 g capacities for priority fish Post Open - National 40,000.00 0.00 ations Envelope mentation 1 2 6 2 USTA) et Enquêteurs pour St eries management atistique et Kit d'Inspection pour CSP MG-MRHP-256429-GO-RFQ / Component 2. Strengthenin Request for Quot Single Stage - One 2021-10-2 2021-12-0 2021-12-1 2022-01-1 Acquisition de 20 VTT pour l TF / A4588 g capacities for priority fish Post Open - National 6,000.00 0.00 Canceled ations Envelope 3 9 8 7 es antennes USTA eries management MG-MRHP-307043-GO-RFB / Fourniture, Installation, Mise en service et Maintenance d Component 3. Strengthenin e vingt-six (26) infrastructur g capacities for engaging in Open - Internation Single Stage - One Under Imple 2022-09-2 2022-10-3 2022-10-0 2022-10-3 2022-11-1 2022-12-1 2023-01-1 2023-07-1 IDA / 59870 Post Request for Bids 1,100,000.00 0.00 es frigorifiques dans les loca alternative fishing practices al Envelope mentation 9 1 4 1 5 5 9 8 lités de pêcheurs dans les Z and livelihoods activities ones Ultra Prioritaires (ZUP) sur deux (02) régions de MA DAGASCAR : ANALANJIROFO - DIANA MG-MRHP-307036-GO-RFB / Fourniture, Installation, Mise en service et Maintenance d Component 3. Strengthenin e vingt-six (26) infrastructur g capacities for engaging in Open - Internation Single Stage - One Under Imple 2022-09-2 2022-10-2 2022-10-0 2022-10-3 2022-11-1 2022-12-1 2022-12-1 2023-01-1 2023-07-1 IDA / 59870 Post Request for Bids 1,800,000.00 0.00 es énergétiques dans les loc alternative fishing practices al Envelope mentation 9 7 4 1 5 4 5 9 8 alités de pêcheurs dans les and livelihoods activities Zones Ultra Prioritaires (ZUP ) sur deux (02) régions de M ADAGASCAR : ANALANJIROF O - DIANA MG-MRHP-329768-GO-RFQ / Component 3. Strengthenin Acquisition matériels de co g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2022-12-1 2023-02-0 2023-08-0 IDA / 59870 Post Open - National 5,000.00 0.00 mmunication de la météo m alternative fishing practices ations Envelope lementation 5 9 8 arine: Panneau SAP - Téléph and livelihoods activities one solaire - radio VHF MG-MRHP-329336-GO-RFB / Outil et équipement de valor Component 3. Strengthenin isation et commercialisation g capacities for engaging in Single Stage - One Under Imple 2023-01-1 2023-02-0 2023-01-1 2023-02-0 2023-02-1 2023-03-1 2023-04-2 2023-07-1 IDA / 59870 Post Request for Bids Open - National 500,000.00 0.00 compose de 400 bicyclette à alternative fishing practices Envelope mentation 0 3 5 8 4 6 0 9 grande roue, 250 Glacière 5 and livelihoods activities 0litres et 150 bac ajouré 70li tre MG-MRHP-256423-GO-DIR / Component 2. Strengthenin 2022-05-0 2022-05-1 2022-06-1 2022-10-1 Acquisition de 33 motos 5 TF / A4588 g capacities for priority fish Post Direct Selection Direct 70,000.00 0.00 Canceled 6 1 5 3 motos eries management MG-MRHP-332050-GO-RFB / Acquisition des matériels ro Component 2. Strengthenin Single Stage - One Under Imple 2023-01-1 2023-02-0 2023-01-1 2023-02-0 2023-02-1 2023-03-0 2023-04-1 2023-07-1 ulants répartis en 2 Lots: IDA / 59870 g capacities for priority fish Post Request for Bids Open - National 495,000.00 0.00 Envelope mentation 0 3 5 6 4 7 1 0 • Lot 01: 05 véhicules 4*4 eries management • Lot 02: 45 motos MG-MRHP-338246-GO-RFB / Component 2. Strengthenin Open - Internation Single Stage - One Under Imple 2023-02-0 2023-02-1 2023-02-0 2023-02-1 2023-03-1 2023-03-1 2023-03-1 2023-05-2 2023-03-2 2023-07-2 Acquisition de matériels info IDA / 59870 g capacities for priority fish Post Request for Bids 490,000.00 0.00 al Envelope mentation 3 0 8 3 0 3 5 5 5 3 rmatiques 2022 et 2023 eries management MG-MRHP-331442-GO-RFB / La fourniture, Livraison, Inst allation et Mise en service d Component 3. Strengthenin e 200 lampadaires solaires g capacities for engaging in Single Stage - One Under Imple 2023-01-1 2023-02-1 2023-01-1 2023-02-1 2023-02-1 2023-03-0 2023-03-1 2023-08-0 IDA / 59870 Post Request for Bids Open - National 140,000.00 0.00 dans les localités des Zones alternative fishing practices Envelope mentation 0 1 5 3 4 1 1 8 Ultra Prioritaires des pêcheu and livelihoods activities rs dans (03) trois Régions à Madagascar : MELAKY - DIA NA - ANALANJIROFO MG-MRHP-338964-GO-DIR / Component 3. Strengthenin Equipement et d'outils de pê g capacities for engaging in Under Imple 2023-01-3 2023-02-2 2023-02-0 2023-02-2 2023-02-2 2023-07-2 che: 20.000 kits composés d IDA / 59870 Post Direct Selection Direct - National 436,800.00 0.00 alternative fishing practices mentation 1 4 5 4 4 4 e palmes réglable, masque and livelihoods activities de plongé, tuba et sac de tr ansport MG-MRHP-338245-GO-RFB / Component 3. Strengthenin Outils de valorisation compo g capacities for engaging in Single Stage - One Under Imple 2023-02-0 2023-02-1 2023-02-0 2023-02-1 2023-03-1 2023-03-1 2023-03-1 2023-03-2 2023-03-2 2023-04-0 IDA / 59870 Post Request for Bids Open - National 650,000.00 0.00 sé de 325 broyeurs à disque alternative fishing practices Envelope mentation 3 0 8 3 0 3 5 8 5 3 , à percussion et de 125 pell and livelihoods activities etiseur à pédale MG-MRHP-338984-GO-RFB / La fourniture, Livraison, Inst allation et Mise en service d Component 3. Strengthenin e 20 kits de congélateurs sol g capacities for engaging in Single Stage - One Under Imple 2023-01-3 2023-02-1 2023-02-0 2023-02-1 2023-03-0 2023-03-1 2023-03-2 2023-08-2 IDA / 59870 Post Request for Bids Open - National 50,000.00 0.00 aires dans les localités des Z alternative fishing practices Envelope mentation 1 1 2 3 4 4 9 6 ones Ultra Prioritaires des p and livelihoods activities êcheurs dans (03) trois Régi ons à Madagascar , Region MELAKY - DIANA - ANALANJI ROFO MG-MRHP-346374-GO-RFQ / Component 3. Strengthenin Acquisition de 500 téléphon g capacities for engaging in Request for Quot Single Stage - One Pending Imp 2023-03-1 2023-04-3 2023-06-2 IDA / 59870 Post Open - National 100,000.00 0.00 es solaires et 300 radios VH alternative fishing practices ations Envelope lementation 9 0 9 F and livelihoods activities MG-MRHP-346378-GO-DIR / Fourniture et installation, Fo rmation des points focaux et Component 3. Strengthenin accompagnement pour la mi g capacities for engaging in Under Imple 2023-03-1 2023-03-1 2023-03-1 2023-03-1 2023-04-1 2023-08-1 IDA / 59870 Post Direct Selection Direct - National 1,975,000.00 0.00 se en service de 3000 pann alternative fishing practices mentation 4 4 9 4 6 4 eaux agrometeorologique d and livelihoods activities e type MITAO FORECAST (pa nneaux SAP) dans les 14 rég ions côtières de Madagascar MG-MRHP-355024-GO-RFB / Component 3. Strengthenin Acquisition d'équipements p g capacities for engaging in Open - Internation Single Stage - One Pending Imp 2023-05-1 2023-05-2 2023-07-0 2023-07-1 2023-07-2 2023-09-2 our la mise en œuvre de l'Ac IDA / 59870 Post Request for Bids 1,920,000.00 0.00 alternative fishing practices al Envelope lementation 6 1 5 5 7 9 tivité Génératrice des Reven and livelihoods activities us ( AGR) pour les pêcheurs. Component 3. Strengthenin MG-MRHP-361766-GO-DIR / g capacities for engaging in Pending Imp 2023-05-1 2023-05-2 2023-06-1 2023-08-2 Acquisition des divers matér IDA / 59870 Post Direct Selection Direct - National 900,000.00 0.00 alternative fishing practices lementation 8 8 2 6 iels de pêches and livelihoods activities MG-MRHP-362169-GO-RFB / Component 3. Strengthenin Acquisition et installation de g capacities for engaging in Single Stage - One Pending Imp 2023-05-2 2023-05-3 2023-06-2 2023-07-0 2023-07-1 2023-09-0 s matériels et équipements IDA / 59870 Post Request for Bids Open - National 290,000.00 0.00 alternative fishing practices Envelope lementation 5 0 9 4 1 9 pour le fonctionnement des i and livelihoods activities nfrastructures construites Page 4 MG-MRHP-362172-GO-RFB / Component 3. Strengthenin Renforcement de l'unité de g capacities for engaging in Single Stage - One Pending Imp 2023-05-2 2023-05-3 2023-06-2 2023-07-0 2023-07-1 2023-09-0 IDA / 59870 Post Request for Bids Open - National 300,000.00 0.00 gestion communautaire en b alternative fishing practices Envelope lementation 5 0 9 4 1 9 iens et équipements; and livelihoods activities NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process St Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) atus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-151759-NC-RFB / Component 2. Strengthenin Open - Internation Single Stage - One 2020-01-0 2020-01-2 2020-01-1 2020-01-2 2020-02-2 2020-03-1 2020-02-2 2020-06-1 2020-03-2 2020-11-2 2020-05-2 Analyse PC de l'eau de traite IDA / 59870 g capacities for priority fish Post Request for Bids 110,000.00 186,954.22 Signed al Envelope 6 9 1 9 5 6 6 5 2 6 1 ment ou de production (lot eries management N°1) MG-MRHP-151759BIS1-NC- Component 2. Strengthenin RFQ / Analyses officielles po Request for Quot Single Stage - One Pending Imp 2019-08-1 2019-10-2 2019-12-2 IDA / 59870 g capacities for priority fish Post Limited 100,000.00 0.00 ur le compte de l'Autorité Sa ations Envelope lementation 0 8 7 eries management nitaire Halieutique (ASH) rép artie en 9 Lots MG-MRHP-192432-NC-RFB / Analyses officielles relatives au contrôle de la qualité phy sico-chimique des eaux de tr Component 2. Strengthenin Open - Internation Single Stage - One Under Imple 2020-09-2 2021-10-1 2020-09-2 2021-10-1 2020-11-1 2021-12-0 2020-12-0 2021-01-0 2021-04-0 aitement et de production et IDA / 59870 g capacities for priority fish Post Request for Bids 309,750.00 0.00 al Envelope mentation 2 3 7 3 1 7 2 2 2 des résidus chimiques et co eries management ntaminants dans les produit s de la pêche et d’aquacultu re, conformément aux plans de surveillance nationaux 2 02 MG-MRHP-192435-NC-DIR / Analyses officielles relatives à la Recherche de Vibrio pot Component 2. Strengthenin entiellement entéropathogè Pending Imp 2020-09-2 2020-09-2 2020-11-2 2021-02-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 7,860.00 0.00 nes dans les produits de la p lementation 2 7 5 3 eries management êche et d’aquaculture (crust acées : crabes et crevettes), conformément aux plans de surveillance nationaux 2020 MG-MRHP-196025-NC-DIR / Component 2. Strengthenin Diagnostic des maladies des Pending Imp 2020-10-0 2020-10-3 2020-11-2 2020-12-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 47,000.00 0.00 crustacés dans le cadre de l lementation 9 0 6 1 eries management a réalisation du Plan de Surv eillance 2020 MG-MRHP-231600-NC-DIR / Component 2. Strengthenin Acquisition et installation d' Under Imple 2021-05-2 2021-05-2 2021-07-1 2022-07-1 IDA / V0500 g capacities for priority fish Post Direct Selection Direct 37,000.00 0.00 équipement des deux Patro mentation 0 5 4 4 eries management uilleurs (Atsantsa et Telonify )   à bord des navires MG-MRHP-231592-NC-DIR / Extension de l’application d Component 2. Strengthenin 2021-05-2 2021-05-2 2021-05-2 2021-06-1 2021-07-1 2021-10-2 2022-07-1 u système ERS du Centre de IDA / V0500 g capacities for priority fish Post Direct Selection Direct 36,600.00 47,559.62 Signed 0 7 5 4 4 2 4 Surveillance des Pêches de eries management Madagascar aux navires nati onaux et étrangers hors-UE MG-MRHP-289369-NC-DIR / Analyse officielle en laborat Component 2. Strengthenin oire de dosage des substan Under Imple 2022-04-1 2022-04-2 2022-04-1 2022-04-2 2022-05-2 2022-11-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 30,000.00 0.00 ces interdites et résidus mé mentation 2 1 7 5 2 8 eries management dicamenteux et de dosage de résidus de pes ticides MG-MRHP-295994-NC-RFQ / ACHEMINEMENT DES PRELE VEMENTS DE PRODUITS DE LA PECHE POUR ANALYSES Component 2. Strengthenin OFFICIELLES DANS LE CADR Request for Quot Single Stage - One Pending Imp 2022-05-3 2022-07-2 2023-01-2 IDA / 59870 g capacities for priority fish Post Open - National 51,000.00 0.00 E DE LA REALISATION DES P ations Envelope lementation 0 5 1 eries management LANS DE SURVEILLANCE SA NITAIRES 2020 & 2021 DE L’ AUTORITE SANITAIRE HALIE UTIQUE JUSQU’AUX LABORA TOIRES ACCREDITES INTERN ATIONAUX RETENUS. Component 3. Strengthenin MG-MRHP-REG2022-NC-RFQ g capacities for engaging in Request for Quot Single Stage - One 2022-05-3 2022-05-3 2022-06-0 2022-06-0 2022-06-2 / Dédouanement de 20000 k IDA / 59870 Post Limited 100,000.00 93,478.02 Signed alternative fishing practices ations Envelope 1 1 6 8 1 it de sécurté en mer and livelihoods activities MG-MRHP-296834-NC-RFP / Firme pour la réparation des Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2022-06-2 2022-08-1 2023-02-1 imprimantes photocopieurs, IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 ations Envelope lementation 1 6 2 scanners, dupli copieurs,mat eries management ériels informatique et électr onique MG-MRHP-REG2020-NC-RFQ Component 4. Project mana Request for Quot Single Stage - One 2020-11-0 2020-11-0 2020-11-1 2020-11-2 2021-11-1 / Hébergement mail professi IDA / 59870 Post Limited 13,800.00 13,793.14 Signed gement and coordination ations Envelope 6 6 9 0 9 onnel du projet SWIOFish2 MG-MRHP-308415-NC-RFQ / Prestation de service en Age Component 2. Strengthenin Request for Quot Single Stage - One Pending Imp 2022-11-0 2022-12-3 2023-06-2 nce de Voyage ( Billet d'avio IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 ations Envelope lementation 5 1 9 n) pour les voyages à l'étran eries management ger - Contrat Cadre Multi at tributaire de 12 mois- MG-MRHP-337984-NC-DIR / Component 2. Strengthenin Direct - Internatio Pending Imp 2023-01-2 2023-02-0 2023-03-0 2023-05-3 Support et Maintenance de l IDA / D1720 g capacities for priority fish Post Direct Selection 50,000.00 0.00 nal lementation 7 1 2 1 'application THEMIS-VMS pa eries management r CLS CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Interes Request for Proposal Opening of Technical Evaluation of Techni Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s t Notice s as Issued Proposals / Minutes cal Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-14498-CS-QCBS// PA-13 / PA 13: Mise à jour de Component 2. Strengthenin Quality And Cost- Open - Internation 2017-05-3 2017-07-2 2017-09-1 2017-09-1 2017-09-2 2017-10-2 2018-10-2 la Stratégie d'aquaculture et IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2017-05-16 Based Selection al 0 8 1 3 2 0 0 élaboration de plan de dével eries management oppement des 03 filières aq uaculture MG-MRHP-14951-CS-LCS//P A65 / PA 65: Etudes techniq ues : - Clôture de l'enceinte DRRH Component 2. Strengthenin P Fénérive Least Cost Select Open - Internation 2017-12-1 2017-05-3 2017-07-2 2018-03-1 2017-08-2 2018-04-1 2017-08-2 2018-04-2 2017-09-1 2018-05-0 2017-10-0 2018-07-0 2018-04-0 2019-07-2 IDA / Q9790 g capacities for priority fish Post 35,000.00 25,756.66 Completed 2017-05-17 - Construction des Bureaux ion al 9 1 2 9 1 7 8 4 1 7 9 3 7 4 eries management de 06 DRRHP - Extension de l'ASH à Antsir anana et Morondava - Construction local pour bur eau UGP MG-MRHP-23760-CS-QCBS// MG-PM-117 / Recrutement d' Component 3. Strengthenin un Cabinet d'étude ou d'une g capacities for engaging in Quality And Cost- 2017-10-3 2017-10-0 2018-08-2 2017-12-1 2018-09-1 2018-01-0 2019-02-0 2018-02-0 2019-07-0 2018-03-2 2019-08-1 2018-05-0 2019-09-2 2020-04-3 ONG pour assurer les missio IDA / Q9790 Prior Open - National 600,000.00 677,965.07 Signed 2017-09-14 alternative fishing practices Based Selection 0 5 9 0 8 7 7 6 8 0 6 1 4 0 ns de l'AGEX pour l'appui à l and livelihoods activities a mise en œuvre du Plan d'A ménagement des Pêcheries de la Baie d'Antongil MG-MRHP-27282-CS-QCBS// Component 2. Strengthenin Quality And Cost- Open - Internation 2017-09-2 2017-11-2 2017-12-2 2017-08-0 2018-01-2 2018-02-2 2018-04-0 2019-04-0 PA61 / Appui à la mise en pl IDA / Q9790 g capacities for priority fish Prior 500,000.00 0.00 Canceled 2017-09-07 Based Selection al 8 6 4 4 3 7 3 3 ace des outils d'aménageme eries management nt des pêches MG-MRHP-28166-CS-QCBS// Component 2. Strengthenin Quality And Cost- Open - Internation 2018-01-0 2018-03-1 2018-04-0 2018-05-2 2018-07-0 2018-08-1 2019-08-1 MG-PM-14 / Recueil et analy IDA / D1720 g capacities for priority fish Post 25,000.00 0.00 Canceled 2017-12-15 Based Selection al 5 2 9 4 5 6 6 se des informations de base eries management avant-projet MG-MRHP-28168-CS-QCBS// Component 2. Strengthenin MG-PM-16 / Collecte des don Quality And Cost- Open - Internation Pending Implem 2018-01-0 2018-03-1 2018-04-0 2018-05-2 2018-07-0 2018-08-1 2019-08-1 IDA / D1720 g capacities for priority fish Post 20,000.00 0.00 2017-12-15 nées au niveau des régions Based Selection al entation 5 2 9 4 5 6 6 eries management prioritaires (Artfish) MG-MRHP-28170-CS-CQS// MG-PM-18 / Identification de s besoins en formation et él Component 2. Strengthenin Consultant Qualif Open - Internation 2018-01-1 2018-03-1 2018-04-1 2018-05-3 2018-11-2 aboration du plan de formati IDA / 59870 g capacities for priority fish Post 20,000.00 0.00 Canceled 2017-12-22 ication Selection al 2 9 8 0 6 on des agents de l'administr eries management ation (y compris Inventaire et contact des centres de fo rmation locaux et extérieurs ) MG-MRHP-28171-CS-CQS// MG-PM-19 / Etude sur l'ident ification et recensement des Component 3. Strengthenin bénéficiaires chaque année, g capacities for engaging in Consultant Qualif Open - Internation 2017-10-2 2017-12-0 2018-02-1 2019-05-3 2018-03-2 2019-09-0 2018-05-0 2019-09-1 2018-11-0 2020-11-0 IDA / 59870 Post 200,000.00 159,792.61 Completed 2017-11-15 du montant et des modalité alternative fishing practices ication Selection al 4 6 0 1 7 6 8 8 4 2 s de transfert financier, du and livelihoods activities montant minimal de filet soc ial pour les pêcheurs/acteur s filières affectés par les me sures de gestion MG-MRHP-28174-CS-CQS// Component 3. Strengthenin MG-PM-22 / Étude sur le circ g capacities for engaging in Consultant Qualif Open - Internation 2019-06-1 2017-12-2 2018-02-2 2018-04-1 2018-05-2 2018-11-1 IDA / 59870 Post 90,000.00 0.00 Canceled 2017-11-30 uit de commercialisation des alternative fishing practices ication Selection al 7 1 5 1 3 9 produits des pêches and livelihoods activities MG-MRHP-28175-CS-CQS// MG-PM-23 / Étude et enquêt e sur l'état des lieux des acc Component 3. Strengthenin idents en mer de la petite p g capacities for engaging in Consultant Qualif Open - Internation 2019-02-2 2017-12-2 2018-02-2 2019-02-2 2018-04-1 2019-06-1 2018-05-2 2019-06-1 2018-11-1 êche et aux éventuelles mes IDA / 59870 Post 120,000.00 50,244.29 Signed 2017-11-30 alternative fishing practices ication Selection al 6 1 5 6 1 4 3 4 9 ures déjà prises/analyse de and livelihoods activities s accidentologies/aspect inst itutionnel sur les responsabil ités de la petite pêche/ à titr e provisoire proposer les éq uipements MG-MRHP-28319-CS-QCBS// Component 3. Strengthenin MG-PM-25 / Diagnostic des b g capacities for engaging in Quality And Cost- Open - Internation 2019-03-1 2018-01-0 2018-03-1 2018-04-0 2018-05-2 2018-07-0 2018-08-1 2019-08-1 esoins en activités alternativ IDA / 59870 Post 150,000.00 0.00 Canceled 2017-12-15 alternative fishing practices Based Selection al 5 5 2 9 4 5 6 6 es adaptées pour chaque ré and livelihoods activities gion ultra prioritaire (exécut ée par AGEX) MG-MRHP-28322-CS-QCBS// Component 3. Strengthenin MG-PM-27 / Détermination d g capacities for engaging in Quality And Cost- Open - Internation 2017-01-2 2017-11-2 2018-01-2 2017-09-0 2018-02-2 2017-10-1 2018-04-0 2017-10-1 2018-05-2 2018-08-0 2018-07-0 2018-09-2 2019-07-0 2019-07-2 IDA / 59870 Post 60,000.00 66,260.37 Completed 2017-10-30 es outils financiers d'appui a alternative fishing practices Based Selection al 4 0 5 6 2 0 8 0 0 8 1 5 1 3 ux filières et activités altern and livelihoods activities atives MG-MRHP-28323-CS-CQS// Component 3. Strengthenin MG-PM-28 / Étude sur l'amél g capacities for engaging in Consultant Qualif Open - Internation 2017-11-0 2018-01-1 2018-02-2 2018-04-0 2018-10-0 IDA / 59870 Post 60,000.00 0.00 Canceled 2017-10-16 ioration des conditions de vi alternative fishing practices ication Selection al 6 1 5 8 5 e sociale des communautés and livelihoods activities de pêcheur MG-MRHP-28330-CS-QCBS// MG-PM-31 / État de lieux des Component 3. Strengthenin petites infrastructures de pê g capacities for engaging in Quality And Cost- Open - Internation 2019-04-0 2017-11-2 2019-04-1 2018-01-2 2019-06-0 2018-02-2 2019-07-1 2018-04-0 2019-07-1 2018-05-2 2019-09-1 2018-07-0 2019-10-1 2019-07-0 2020-11-0 IDA / 59870 Post 120,000.00 113,351.50 Completed 2017-10-30 ches et les besoins des com alternative fishing practices Based Selection al 4 0 5 5 6 2 7 8 8 0 3 1 0 1 3 munautés cibles en petites i and livelihoods activities nfrastructures de pêche et c ommunautaires MG-MRHP-28333-CS-QCBS// Component 3. Strengthenin MG-PM-32 / Étude des besoi g capacities for engaging in Quality And Cost- Open - Internation 2017-11-2 2018-01-2 2018-02-2 2018-04-0 2018-05-2 2018-07-0 2019-07-0 IDA / 59870 Post 200,000.00 0.00 Canceled 2017-10-30 ns communautaires (une ét alternative fishing practices Based Selection al 0 5 2 8 0 1 1 ude par district) and livelihoods activities Page 5 MG-MRHP-28336-CS-CQS// Component 3. Strengthenin MG-PM-33 / Préparation du p g capacities for engaging in Consultant Qualif Open - Internation 2017-11-2 2018-01-2 2018-03-1 2018-04-2 2018-10-1 IDA / 59870 Post 60,000.00 0.00 Canceled 2017-10-30 lan local d'électrification co alternative fishing practices ication Selection al 0 5 1 2 9 mmunautaire : étude et rap and livelihoods activities ports MG-MRHP-28342-CS-CQS// MG-PM-39 / Études techniqu Component 4. Project mana Consultant Qualif 2017-11-2 2018-01-2 2018-03-1 2018-04-2 2018-10-1 IDA / 59870 Post Open - National 13,500.00 0.00 Canceled 2017-10-30 es pour la construction d'un gement and coordination ication Selection 0 5 1 2 9 local pour bureau UGP MG-MRHP-28343-CS-LCS//M G-PM-40 / Études d'impacts Component 4. Project mana Least Cost Select Open - Internation 2018-01-0 2018-03-1 2018-04-0 2018-05-0 2018-06-2 2018-08-0 2019-01-2 IDA / 59870 Post 10,000.00 0.00 Canceled 2017-12-15 environnementales et social gement and coordination ion al 5 2 9 9 0 1 8 es pour la construction d'un local pour bureau UGP MG-MRHP-27288-CS-QCBS// Component 2. Strengthenin PA62 / Appui à la mise en œ Quality And Cost- Open - Internation 2016-09-0 2017-09-2 2017-11-1 2017-06-0 2017-12-0 2017-07-1 2018-01-0 2017-08-0 2018-02-1 2017-10-2 2018-03-1 2018-05-0 2019-03-1 2019-07-1 IDA / Q9790 g capacities for priority fish Post 255,000.00 234,182.87 Completed 2017-09-07 uvre du plan d'amélioration Based Selection al 6 8 1 6 9 7 8 4 2 0 9 2 9 6 eries management de la pêcherie crevettière MG-MRHP-28654-CS-CQS// MG-PM-113 / Mise à jour de l Component 2. Strengthenin Consultant Qualif 2018-02-2 2018-04-2 2018-06-1 2018-07-2 2019-01-2 a Stratégie Nationale de l'Aq IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-02-01 ication Selection 2 9 3 5 1 uaculture (Consultant natio eries management nal + Réunions (1 consultati on, 1 validation) MG-MRHP-28656-CS-CQS// MG-PM-114 / Étude sur les p Component 2. Strengthenin rocédures administratives ré Consultant Qualif 2018-02-2 2018-04-2 2018-06-1 2018-07-2 2019-01-1 IDA / 59870 g capacities for priority fish Post Open - National 50,000.00 0.00 Canceled 2018-01-30 gissant l'accès aux ressourc ication Selection 0 7 1 3 9 eries management es et examen des options et recommandations (6 outils d e gestion) MG-MRHP-28657-CS-CQS// Component 2. Strengthenin MG-PM-115 / Diagnostic du Consultant Qualif 2018-06-2 2018-08-2 2018-10-1 2018-11-2 2019-05-2 IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-06-01 secteur dans le domaine fin ication Selection 2 7 1 2 1 eries management ancier local, régional, intern ational MG-MRHP-28659-CS-CQS// Component 2. Strengthenin MG-PM-116 / Élaboration de Consultant Qualif 2018-02-2 2018-04-2 2018-05-2 2018-07-0 2019-01-0 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-01-30 la stratégie d'adaptation du ication Selection 0 7 7 8 4 eries management secteur pêche face au chan gement climatique MG-MRHP-28661-CS-CQS// Component 2. Strengthenin Consultant Qualif 2018-06-2 2018-08-2 2018-09-2 2018-11-0 2019-05-0 MG-PM-118 / Recueil et anal IDA / D1720 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-06-01 ication Selection 2 7 6 7 6 yse des informations de bas eries management e avant-projet MG-MRHP-28663-CS-CQS// MG-PM-119 / Développemen Component 2. Strengthenin t et mise en œuvre du systè Consultant Qualif 2018-04-2 2018-06-0 2018-07-0 2018-08-1 2019-02-0 IDA / D1720 g capacities for priority fish Post Open - National 5,000.00 0.00 Canceled 2018-04-02 me de collecte de données p ication Selection 3 6 6 0 6 eries management our les pêcheries traditionne lles, y compris une stratégie d'échantillonnage approprié e MG-MRHP-28665-CS-CQS// Component 2. Strengthenin MG-PM-120 / Collecte des do Consultant Qualif 2018-03-2 2018-05-0 2018-06-0 2018-07-0 2019-01-0 IDA / D1720 g capacities for priority fish Post Open - National 35,000.00 0.00 Canceled 2018-03-01 nnées au niveau des régions ication Selection 2 5 4 9 5 eries management prioritaires (Artfish) MG-MRHP-28668-CS-CQS// Component 2. Strengthenin Consultant Qualif 2018-02-2 2018-04-0 2018-05-0 2018-06-1 2018-12-0 MG-PM-121 / Mise à jour de l IDA / D1720 g capacities for priority fish Post Open - National 50,000.00 0.00 Canceled 2018-02-01 ication Selection 2 7 7 1 8 'Enquête Cadre Nationale eries management MG-MRHP-28669-CS-CQS// Component 2. Strengthenin MG-PM-122 / Développemen Consultant Qualif 2018-03-0 2018-04-2 2018-05-2 2018-06-2 2018-12-2 IDA / D1720 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-02-15 t et mise en œuvre de la col ication Selection 8 1 1 5 2 eries management lecte de données pour les pr oduits post-capture MG-MRHP-28679-CS-CQS// Component 2. Strengthenin MG-PM-126 / Développemen Consultant Qualif 2018-09-2 2018-11-0 2018-12-0 2019-01-1 2019-07-1 IDA / D1720 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-09-03 t d'un système d'information ication Selection 4 7 7 1 0 eries management halieutique modulaire MG-MRHP-28682-CS-CQS// Component 2. Strengthenin Consultant Qualif 2018-05-2 2018-07-0 2018-08-0 2018-09-0 2019-03-0 MG-PM-127 / Suivi du systè IDA / D1720 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-04-30 ication Selection 1 4 3 7 6 me d'information halieutiqu eries management e modulaire MG-MRHP-28686-CS-CQS// Component 2. Strengthenin MG-PM-129 / Étude d'impact Consultant Qualif 2018-06-0 2018-07-1 2018-08-1 2018-09-2 2019-03-2 IDA / 59870 g capacities for priority fish Post Open - National 66,000.00 0.00 Canceled 2018-05-15 environnemental et social d ication Selection 5 9 8 2 1 eries management e l'extension ou de la constr uction MG-MRHP-28687-CS-QCBS// Component 2. Strengthenin Quality And Cost- Open - Internation 2018-04-0 2018-06-1 2018-07-0 2018-08-0 2018-09-1 2018-10-3 2019-10-3 MG-PM-130 / Élaboration str IDA / 59870 g capacities for priority fish Post 50,000.00 0.00 Canceled 2018-03-15 Based Selection al 5 0 8 7 8 0 0 atégie nationale de recherch eries management es halieutiques MG-MRHP-28690-CS-CQS// Component 2. Strengthenin Consultant Qualif Open - Internation 2018-07-0 2018-08-1 2018-09-1 2018-10-2 2019-04-2 MG-PM-134 / Etude sur les IDA / 59870 g capacities for priority fish Post 30,000.00 0.00 Canceled 2018-06-15 ication Selection al 6 9 8 3 1 mesures de gestion des pou eries management lpes MG-MRHP-28691-CS-QCBS// Component 2. Strengthenin MG-PM-135 / Avis scientifiqu Quality And Cost- Open - Internation 2018-07-2 2018-09-2 2018-10-2 2018-11-2 2019-01-0 2019-02-0 2020-02-0 IDA / 59870 g capacities for priority fish Post 30,000.00 0.00 Canceled 2018-06-29 e pour la gestion des pêcher Based Selection al 0 4 2 1 2 6 6 eries management ies de langoustes, dans les sites prioritaires MG-MRHP-28693-CS-QCBS// MG-PM-137 / Révision du sys Component 2. Strengthenin Quality And Cost- Open - Internation 2018-02-0 2018-04-1 2018-05-1 2018-06-0 2018-07-2 2018-08-2 2019-08-2 tème de suivi de la pêche cr IDA / 59870 g capacities for priority fish Post 75,000.00 0.00 Canceled 2018-01-15 Based Selection al 5 2 0 9 1 5 5 evettière traditionnelle (PCT eries management ) et élargissement à toutes l es zones de pêche MG-MRHP-28694-CS-CQS// Component 2. Strengthenin MG-PM-138 / Révision par le Consultant Qualif Open - Internation 2018-02-2 2018-04-0 2018-05-0 2018-06-1 2018-12-0 IDA / 59870 g capacities for priority fish Post 75,000.00 0.00 Canceled 2018-02-01 s pairs des modèles d'évalu ication Selection al 2 7 7 1 8 eries management ation des stock de crevettes MG-MRHP-28695-CS-CQS// Component 2. Strengthenin MG-PM-139 / Etat des lieux e Consultant Qualif Open - Internation 2018-06-2 2018-08-0 2018-09-0 2018-10-0 2019-04-0 IDA / 59870 g capacities for priority fish Post 10,000.00 0.00 Canceled 2018-05-30 t évaluation des besoins du ication Selection al 0 3 2 7 5 eries management Ministère en moyens et équi pements MG-MRHP-28703-CS-QCBS// MG-PM-145 / Élaboration du Component 2. Strengthenin Quality And Cost- 2018-02-2 2018-04-2 2018-05-1 2018-07-0 2018-08-0 2018-09-1 2019-09-1 plan d'action national sur les IDA / 59870 g capacities for priority fish Post Open - National 60,000.00 0.00 Canceled 2018-01-30 Based Selection 0 0 8 2 6 0 0 requins, les oiseaux de mer, eries management les tortues mrines, (résolutio n CTOI) MG-MRHP-28706-CS-QCBS// Component 2. Strengthenin Quality And Cost- 2018-10-0 2018-12-1 2019-01-1 2019-02-2 2019-03-3 2019-05-0 2020-05-0 MG-PM-149 / Étude sur l'am IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 Canceled 2018-09-17 Based Selection 8 3 0 4 1 5 4 élioration du protocole stand eries management ard de pêche MG-MRHP-28707-CS-CQS// MG-PM-150 / Étude sur l'éval Component 2. Strengthenin Consultant Qualif 2018-10-0 2018-11-2 2018-12-2 2019-01-2 2019-07-2 uation des impacts des diffé IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 Canceled 2018-09-17 ication Selection 8 1 1 5 4 rents engins (palangres, filet eries management s, ...) sur les espèces menac ées (requins, tortues, ...) MG-MRHP-28709-CS-CQS// Component 2. Strengthenin MG-PM-128 / Étude techniqu Consultant Qualif 2018-03-0 2018-04-2 2018-05-2 2018-06-2 2018-12-2 IDA / 59870 g capacities for priority fish Post Open - National 67,500.00 0.00 Canceled 2018-02-15 e de l'extension ou construc ication Selection 8 1 1 5 2 eries management tion du bureau régional MG-MRHP-28713-CS-QCBS// Component 2. Strengthenin MG-PM-155 / Études techniq Quality And Cost- 2018-02-2 2018-04-2 2018-05-2 2018-07-0 2018-08-2 2018-10-0 2019-10-0 IDA / D1720 g capacities for priority fish Post Open - National 60,000.00 0.00 Canceled 2018-01-30 ues sur la stratégie de surve Based Selection 0 7 5 9 0 1 1 eries management illance et sur le fonctionnem ent du CSP MG-MRHP-28728-CS-CQS// Component 2. Strengthenin Consultant Qualif Open - Internation 2018-02-2 2018-04-2 2018-06-1 2018-07-2 2019-01-1 MG-PM-156 / Rédaction d'un IDA / 59870 g capacities for priority fish Post 15,000.00 0.00 Canceled 2018-01-30 ication Selection al 0 7 1 3 9 plan national de lutte contre eries management la pêche INN MG-MRHP-28732-CS-CQS// MG-PM-158 / Etude et élabor Component 2. Strengthenin ation de mécanisme structur Consultant Qualif Open - Internation 2018-02-2 2018-04-1 2018-05-1 2018-06-2 2018-12-2 IDA / 59870 g capacities for priority fish Post 50,000.00 0.00 Canceled 2018-01-30 el de plateforme de cogestio ication Selection al 0 2 2 3 0 eries management n des filières prioritaires (cra bes, poulpes, langoustes, ho lothuries, crevettes) MG-MRHP-28733-CS-QCBS// Component 2. Strengthenin Quality And Cost- 2018-03-0 2018-05-1 2018-06-1 2018-07-2 2018-09-0 2018-10-1 2019-10-1 MG-PM-163 / Suivi-évaluatio IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-02-15 Based Selection 8 3 0 5 5 7 7 n des formations et recyclag eries management es réalisés MG-MRHP-28747-CS-QCBS// Component 3. Strengthenin MG-PM-172 / Mise en place g capacities for engaging in Quality And Cost- Open - Internation 2018-08-2 2018-10-2 2018-11-2 2019-01-0 2019-02-1 2019-03-3 2020-03-3 IDA / 59870 Post 25,000.00 0.00 Canceled 2018-07-30 d'une règlementation de bas alternative fishing practices Based Selection al 0 5 2 6 7 1 0 e concernant la sécurité en and livelihoods activities mer de la petite pêche MG-MRHP-28748-CS-QCBS// Component 3. Strengthenin MG-PM-173 / " Étude de mar g capacities for engaging in Quality And Cost- Open - Internation 2018-04-2 2018-06-2 2018-07-2 2018-09-0 2018-10-1 2018-11-2 2019-11-2 ché pour les produits de pêc IDA / 59870 Post 90,000.00 0.00 Canceled 2018-03-30 alternative fishing practices Based Selection al 0 5 3 6 8 9 9 he valorisés dans chaque ré and livelihoods activities gion ultra prioritaire " MG-MRHP-28763-CS-QCBS// Component 3. Strengthenin MG-PM-185 / Gestion et mis g capacities for engaging in Quality And Cost- Open - Internation 2018-11-2 2019-01-1 2019-02-1 2019-04-0 2019-05-0 2019-06-1 2020-06-0 IDA / V0500 Post 40,000.00 0.00 Canceled 2018-10-30 e en œuvre : Suivi évaluatio alternative fishing practices Based Selection al 0 8 5 1 6 0 9 n des bases de données and livelihoods activities MG-MRHP-28766-CS-LCS//M Component 4. Project mana Least Cost Select Open - Internation 2018-02-2 2018-04-0 2018-05-0 2018-06-0 2018-07-0 2018-08-1 2019-02-0 G-PM-189 / Audit externe de IDA / 59870 Post 15,000.00 0.00 Canceled 2018-01-30 gement and coordination ion al 0 5 3 2 7 1 7 s comptes du Projet MG-MRHP-14953-CS-LCS//P Component 2. Strengthenin Least Cost Select Open - Internation 2018-03-2 2018-05-1 2018-05-2 2018-05-2 2018-06-1 2018-07-1 2019-01-1 A67 / PA 67: Recensement d IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2018-03-15 ion al 9 3 0 7 7 5 1 es données au niveau des ré eries management gions prioritaires MG-MRHP-14945-CS-CQS//P Component 2. Strengthenin Consultant Qualif Open - Internation 2018-01-0 2018-03-1 2018-04-2 2018-06-0 2018-12-0 A 15 / PA 15: Recueillir et an IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2017-12-15 ication Selection al 5 2 6 7 4 alyser des informations de b eries management ase avant-projet MG-MRHP-86202-CS-QCBS// PA61 / Recrutement d'une fi Component 2. Strengthenin Quality And Cost- Open - Internation 2016-09-2 2018-12-2 2019-02-1 2017-06-0 2019-03-2 2017-07-1 2019-04-1 2017-08-0 2019-06-1 2018-07-0 2019-08-1 2018-10-1 2020-08-1 rme afin d'appuyer la mise e IDA / 59870 g capacities for priority fish Post 262,000.00 317,899.36 Terminated 2018-11-20 Based Selection al 0 0 8 6 0 7 9 4 8 5 7 2 6 n place d'outils d'aménage eries management ment des pêcheries à Mada gascar MG-MRHP-86206-CS-LCS//M Component 4. Project mana Least Cost Select Open - Internation 2019-02-0 2018-12-3 2019-03-1 2019-02-1 2019-04-2 2019-03-1 2019-06-1 2019-03-2 2019-08-2 2019-03-2 2019-11-1 2019-04-1 2020-05-0 2021-04-2 G-PM 88/18 / Audit externe IDA / 59870 Post 45,000.00 14,382.71 Completed 2018-11-30 gement and coordination ion al 5 0 5 5 9 5 3 1 7 6 0 6 8 1 des comptes du Projet 2018- 2019-2020 MG-MRHP-119249-CS-QCBS Component 3. Strengthenin / Etude technique et étude d g capacities for engaging in Quality And Cost- 2019-08-0 2019-10-3 2019-12-1 2020-01-1 2020-03-2 2020-06-1 2021-06-1 IDA / 59870 Post Open - National 20,000.00 0.00 Canceled 2019-07-03 'Impact Environnemental Ré alternative fishing practices Based Selection 2 1 5 4 9 2 2 habilitation du CFPT and livelihoods activities MG-MRHP-28674-CS-QCBS// MG-PM-125 / Développemen Component 2. Strengthenin Quality And Cost- 2019-08-2 2019-11-1 2019-12-1 2020-01-1 2020-03-1 2020-05-1 2021-05-1 t de la base de données pou IDA / 59870 g capacities for priority fish Post Open - National 46,000.00 0.00 Canceled 2019-07-30 Based Selection 9 2 2 1 1 0 0 r la pêche traditionnelle MA eries management RITIME et CONTINENTALE (c onsultant) Page 6 MG-MRHP-28755-CS-QCBS// MG-PM-177 / Élaboration de Component 3. Strengthenin s Plans d'Action aux restricti g capacities for engaging in Quality And Cost- Open - Internation 2019-08-2 2019-09-0 2019-08-3 2019-11-0 2020-01-2 2019-12-0 2020-02-2 2019-12-3 2020-04-0 2020-02-0 2020-04-1 2020-03-1 2021-02-0 2021-03-1 IDA / 59870 Post 270,000.00 408,313.76 Signed 2019-08-15 ons de Ressources (PARAR)/ alternative fishing practices Based Selection al 2 5 0 3 9 1 8 1 7 4 3 0 6 0 Diagnostic des besoins en a and livelihoods activities ctivités alternatives adaptée s à chaque région ultra prior itaire (AGR) MG-MRHP-105669-CS-QCBS Component 3. Strengthenin / Recrutement d'agence de g capacities for engaging in Quality And Cost- 2019-02-0 2019-09-2 2019-11-0 2019-05-0 2019-12-0 2019-06-1 2020-01-0 2019-06-1 2020-02-0 2019-06-2 2020-03-1 2019-07-1 2021-03-1 2019-09-1 communication pour la conc IDA / 59870 Post Open - National 33,750.00 21,553.74 Completed 2019-09-02 alternative fishing practices Based Selection 7 3 6 2 4 2 3 2 7 1 3 6 3 7 eption et production des sup and livelihoods activities ports de communications rel atifs au MDGP MG-MRHP-28174-CS-QCBS / Etude sur le circuit de comm Component 3. Strengthenin ercialisation des produits de g capacities for engaging in Quality And Cost- Open - Internation 2019-06-1 2019-09-2 2019-11-0 2019-10-0 2019-12-0 2019-11-1 2020-01-0 2020-01-1 2020-02-0 2020-02-0 2020-03-1 2020-06-0 2021-03-1 2021-05-1 IDA / 59870 Post 130,000.00 100,145.61 Completed 2019-09-02 s pêches frais et identificatio alternative fishing practices Based Selection al 8 3 6 9 4 1 3 3 7 3 3 6 3 3 n des techniques de transfor and livelihoods activities mation adaptées pour chaqu e ZUP MG-MRHP-19124-CS-QCBS PA48 / Etablissement de la S Component 4. Project mana Quality And Cost- Open - Internation 2017-08-0 2017-07-1 2017-09-0 2017-08-3 2017-09-2 2017-10-2 2017-12-0 2018-01-0 2019-01-0 ituation de référence du Cad IDA / Q9790 Post 75,000.00 0.00 Canceled 2017-06-27 gement and coordination Based Selection al 1 8 6 1 8 8 2 6 6 re de résultats et développe ment d'un système de gesti on de projet MG-MRHP-28701-CS-QCBS// Component 2. Strengthenin MG-PM-144 / Étude pour la d Quality And Cost- 2018-05-0 2018-07-0 2018-08-0 2018-09-1 2018-10-2 2018-11-2 2019-11-2 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 0.00 Canceled 2018-04-16 éfinition des termes de référ Based Selection 7 5 2 6 1 5 5 eries management ences du Service de Gestion de la Pêche Thonière MG-MRHP-28759-CS-QCBS// Component 3. Strengthenin MG-PM-182 / Préparation du g capacities for engaging in Quality And Cost- Open - Internation 2018-04-2 2018-06-1 2018-07-1 2018-08-3 2018-10-0 2018-11-0 2019-11-0 IDA / V0500 Post 251,100.00 0.00 Canceled 2018-03-30 plan local d'électrification co alternative fishing practices Based Selection al 0 8 6 0 4 8 8 mmunautaire : prestations i and livelihoods activities nternationales MG-MRHP-28753-CS-QCBS// Component 3. Strengthenin MG-PM-176 / Évaluation des g capacities for engaging in Quality And Cost- Open - Internation 2018-10-0 2018-12-0 2018-12-3 2019-01-3 2019-03-0 2019-04-1 2020-04-0 IDA / 59870 Post 90,000.00 0.00 Canceled 2018-09-14 impacts socio-économiques alternative fishing practices Based Selection al 5 3 1 0 6 0 9 de la mise pratique des acti and livelihoods activities vités alternatives MG-MRHP-28741-CS-QCBS// Component 3. Strengthenin MG-PM-168 / Étude sur l'ide g capacities for engaging in Quality And Cost- Open - Internation 2019-11-1 2020-01-2 2021-04-2 2021-06-1 2021-08-1 2021-09-2 2022-09-2 ntification de techniques mo IDA / 59870 Post 100,000.00 0.00 Canceled 2019-09-30 alternative fishing practices Based Selection al 4 8 8 2 1 2 2 dernes de pêche et de fabric and livelihoods activities ation d'engins de pêche ada ptés pour chaque ZUP MG-MRHP-14947-CS-QCBS// PA63 / PA 63: Elaboration de Component 2. Strengthenin Quality And Cost- Open - Internation 2017-05-3 2017-07-2 2017-08-0 2017-08-1 2017-09-0 2017-09-3 2018-09-3 s plans d'action nationaux s IDA / Q9790 g capacities for priority fish Prior 60,000.00 0.00 Canceled 2017-05-17 Based Selection al 1 9 5 2 2 0 0 ur les requins, les oiseaux d eries management e mer et les tortues marines (résolutions CTOI) MG-MRHP-28746-CS-QCBS// MG-PM-171 / Identification d e matériels de sécurité adap Component 3. Strengthenin tés aux différentes catégorie g capacities for engaging in Quality And Cost- Open - Internation 2018-04-2 2018-06-2 2018-07-2 2018-09-0 2018-10-1 2018-11-2 2019-11-2 IDA / 59870 Post 180,000.00 0.00 Canceled 2018-03-30 s d'embarcation et de navig alternative fishing practices Based Selection al 0 5 3 6 8 9 9 ation, stratégie de mis à dis and livelihoods activities position des équipements, d' organisation de secours et l a diffusion des informations météorologiques MG-MRHP-28761-CS-QCBS// Component 3. Strengthenin MG-PM-183 / Préparation du g capacities for engaging in Quality And Cost- Open - Internation 2018-04-0 2018-06-0 2018-07-0 2018-08-1 2018-09-1 2018-10-2 2019-10-2 IDA / V0500 Post 33,800.00 0.00 Canceled 2018-03-15 plan local d'électrification co alternative fishing practices Based Selection al 5 3 1 5 9 4 4 mmunautaire : prestations n and livelihoods activities ationales MG-MRHP-127605-CS-CQS / Component 2. Strengthenin Consultant Qualif Open - Internation 2019-10-0 2019-12-0 2020-01-0 2020-02-2 2020-08-2 Etude sur les accidents en IDA / 59870 g capacities for priority fish Post 90,000.00 0.00 Canceled 2019-09-06 ication Selection al 6 5 4 4 2 mer de la pêche à petite éch eries management elle MG-MRHP-28697-CS-CQS// MG-PM-140 / Étude sur l'ada Component 2. Strengthenin Consultant Qualif Open - Internation 2018-05-2 2018-07-0 2018-08-0 2018-09-0 2019-03-0 ptation des missions et attri IDA / 59870 g capacities for priority fish Post 10,000.00 0.00 Canceled 2018-04-30 ication Selection al 1 4 3 7 6 butions du MRHP par rappor eries management t au défi du développement rural MG-MRHP-23763-CS-QCBS// MG-PM-117 / Recrutement d' Component 3. Strengthenin un Cabinet d'étude ou d'une g capacities for engaging in Quality And Cost- 2017-10-3 2017-10-0 2017-12-0 2017-12-1 2018-09-1 2018-01-0 2019-02-0 2018-02-0 2018-03-2 2018-05-0 2020-04-3 ONG pour assurer les missio IDA / Q9790 Prior Open - National 600,000.00 0.00 Canceled 2017-09-14 alternative fishing practices Based Selection 0 5 1 0 8 7 7 6 0 1 0 ns de l'AGEX pour l'appui à l and livelihoods activities a mise en œuvre du Plan d'A ménagement Concerté des Pêcheries de la Région Mela ky MG-MRHP-23508-CS-QCBS// MG-MP-117 / Recrutement d e Cabinet d'étude ou d'une Component 3. Strengthenin ONG pour assurer les missio g capacities for engaging in Quality And Cost- 2017-10-3 2017-10-0 2018-08-2 2017-12-1 2018-09-1 2018-01-0 2019-02-0 2018-02-0 2019-09-0 2018-03-2 2018-05-0 2020-04-3 ns de l'AGEX pour l'appui à l IDA / Q9790 Prior Open - National 600,000.00 0.00 Canceled 2017-09-14 alternative fishing practices Based Selection 0 5 9 0 8 7 7 6 5 0 1 0 a mise en œuvre du Plan d'A and livelihoods activities ménagement des Pêcheries des Baies d'Ampasindava, d e Tsimipaika, d'Ambaro, et l' archipel de Nosy Be (BATAN ) MG-MRHP-23508-CS-BQS / Recrutement d'une agence Component 3. Strengthenin d'exécution pour l'appui à la g capacities for engaging in Quality Based Sel 2020-01-0 2017-10-0 2020-01-0 2017-11-1 2020-01-2 2017-12-1 2019-02-0 2018-01-1 2020-02-1 2018-02-1 2020-04-1 2018-03-2 2020-05-0 2019-03-2 mise en œuvre du Plan d'Am IDA / Q9790 Prior Open - National 1,600,000.00 1,517,925.94 Signed 2017-09-14 alternative fishing practices ection 7 5 9 8 3 6 7 5 1 4 4 1 9 1 énagement des Pêcheries d and livelihoods activities es Baies d'Ampasindava, de Tsimipaika, d'Ambaro, et l « archipel de Nosy Be (BATAN ) MG-MRHP-23763-CS-BQS / Component 3. Strengthenin Recrutement d'une agence g capacities for engaging in Quality Based Sel 2019-12-1 2017-10-0 2020-01-0 2017-11-1 2020-01-2 2017-12-1 2019-02-0 2018-01-1 2020-02-1 2018-02-1 2020-05-2 2018-03-2 2020-06-1 2021-03-2 d'exécution pour l'appui à la IDA / Q9790 Prior Open - National 900,000.00 647,158.90 Signed 2017-09-14 alternative fishing practices ection 8 5 9 8 3 6 7 5 1 4 0 1 6 0 mise en œuvre du Plan d'Am and livelihoods activities énagement Concerté des Pê cheries de la Région Melaky MG-MRHP-150365-CS-CQS / RECRUTEMENT D'UN CONSU LTANT NATIONAL POUR LE R ENFORCEMENT DE CAPACIT Component 2. Strengthenin Consultant Qualif Under Implemen 2020-03-1 2019-12-3 2020-09-1 2020-01-2 2020-03-0 2020-03-2 2020-05-2 E DU PERSONNEL DE L’AUT IDA / 59870 g capacities for priority fish Post Open - National 15,140.00 0.00 2019-12-24 ication Selection tation 1 1 4 8 8 2 1 ORITE SANITAIRE HALIEUTIQ eries management UE PAR UNE FORMATION EN LINGUISTIQUE (ANGLAIS / CHINOIS) AU NIV EAU NATIONAL (2.1.7.2.04) MG-MRHP-28740BIS-CS-QC BS // MG-PM-167 / Etude sur Component 3. Strengthenin l'amélioration des embarcati g capacities for engaging in Quality And Cost- Under Implemen 2020-02-2 2020-03-0 2020-03-1 2020-04-1 2020-05-1 2020-06-0 2020-07-0 2020-07-1 2021-03-2 IDA / 59870 Post Open - National 90,000.00 0.00 2020-02-25 ons existantes à partir des alternative fishing practices Based Selection tation 7 3 8 6 6 6 4 8 5 matériaux locaux bon march and livelihoods activities é et existants pour chaque Z UP (3.2.1.1.12) MG-MRHP-28740-CS-QCBS// Component 3. Strengthenin MG-PM-167 / Étude sur l'am g capacities for engaging in Quality And Cost- Open - Internation 2019-08-1 2018-05-2 2019-08-1 2018-07-2 2018-08-2 2018-10-0 2018-11-1 2018-12-3 2019-12-3 élioration des embarcations IDA / 59870 Post 60,000.00 0.00 Canceled 2018-04-30 alternative fishing practices Based Selection al 1 1 9 6 3 7 8 0 0 existantes à partir des maté and livelihoods activities riaux locaux bon marché et existants MG-MRHP-86203BIS-CS-QC BS / Recrutement d'une Fir me pour Appui à la Mise à jo ur de la Stratégie Nationale Component 2. Strengthenin Quality And Cost- Under Implemen 2020-02-2 2020-03-0 2020-03-0 2020-04-1 2020-05-1 2020-06-0 2020-07-1 2020-07-2 2020-12-1 pour le Développement de l’ IDA / 59870 g capacities for priority fish Post Open - National 50,000.00 0.00 2020-02-28 Based Selection tation 5 6 7 9 9 9 4 8 5 Aquaculture à Madagascar ( eries management SNDAM) et Elaboration des P lans de Développement des trois (3) filières « d’algocultu re, d’holothuriculture et de c rabicultu MG-MRHP-119284-CS-QCBS / Recrutement d'un BE pour Etudes techniques, étude d’i Component 3. Strengthenin mpact environnemental et s g capacities for engaging in Quality And Cost- Open - Internation 2020-03-1 2020-03-2 2020-03-1 2020-05-1 2020-06-1 2020-06-0 2020-07-1 2020-06-3 2020-08-1 2020-08-0 2020-11-0 2020-08-2 2021-03-1 2022-03-2 ocial et contrôle et surveilla TF / A4588 Post 44,000.00 56,927.90 Signed 2020-03-06 alternative fishing practices Based Selection al 0 7 8 0 6 9 6 0 3 4 5 5 8 8 nce des travaux pour la con and livelihoods activities struction des bâtiments du k iosque de pré-électrification et du « Complexe-pêche » d ans 2 villages à Mananara N ord MG-MRHP-86203-CS-QCBS// PA13 / Mise à jour de la Stra Component 2. Strengthenin Quality And Cost- Open - Internation 2020-02-0 2019-08-3 2019-11-1 2019-12-2 2020-02-1 2020-04-1 2020-06-1 2021-06-1 tégie Nationale de l’Aquacul IDA / 59870 g capacities for priority fish Post 30,000.00 0.00 Canceled 2019-07-31 Based Selection al 4 0 3 8 1 1 0 0 ture (Consultant national + eries management Réunions (1 consultation, 1 validation) MG-MRHP-14952-CS-LCS//P A66 / PA 66: Etudes d'Impac t environnemental et Socail : - Clôture de l'enceinte DRRH Component 2. Strengthenin Consultant Qualif Open - Internation 2017-07-1 2017-08-3 2017-09-3 2017-11-0 2018-05-0 P Fénérive IDA / Q9790 g capacities for priority fish Post 35,000.00 0.00 Canceled 2017-06-27 ication Selection al 8 1 0 4 3 - Construction des Bureaux eries management de 06 DRRHP - Extension de l'ASH à Antsir anana et Morondava - Construction local pour bur eau UGP MG-MRHP-168222-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-07-1 2020-08-1 2020-09-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 9 8 2 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH à Manakara et Mananjary MG-MRHP-168223-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-08-1 2020-07-1 2020-09-1 2020-08-1 2020-12-1 2020-09-2 2021-10-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 7 9 7 8 6 2 5 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH-OEPA à An tananarivo MG-MRHP-168224-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-07-1 2020-08-1 2020-09-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 9 8 2 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH-USTA-SRPA à Majunga MG-MRHP-168226-CS-QCBS / Recrutement d'un BE pour Component 2. Strengthenin la réalisation des études tec Quality And Cost- 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-08-2 2020-07-1 2020-09-2 2020-08-1 2020-12-1 2020-09-2 2021-02-0 2020-10-2 2021-03-1 2021-05-3 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 15,378.80 Signed 2020-04-17 hniques- du PGES et du cont Based Selection 5 8 7 1 0 9 8 8 8 2 1 7 8 0 eries management rôle et surveillance des cons tructions des bureaux admin istratifs de l'ASH à Toliara MG-MRHP-168227-CS-QCBS / Recrutement d'un BE pour Component 2. Strengthenin la réalisation des études tec Quality And Cost- 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-08-1 2020-07-1 2020-09-1 2020-08-1 2021-02-1 2020-09-2 2021-06-2 2020-10-2 2021-09-3 2021-05-3 IDA / 59870 g capacities for priority fish Post Open - National 10,000.00 25,713.74 Signed 2020-04-17 hniques- du PGES et du cont Based Selection 5 8 7 1 4 9 4 8 6 2 3 7 0 0 eries management rôle et surveillance des cons tructions des bureaux admin istratifs de l'ASH à Fort-Dau phin Page 7 MG-MRHP-168225-CS-QCBS / Recrutement d'un BE pour la réalisation des études tec Component 2. Strengthenin Quality And Cost- Under Implemen 2020-04-1 2020-05-0 2020-04-2 2020-06-2 2020-07-1 2020-08-1 2020-09-2 2020-10-2 2021-05-3 hniques- du PGES et du cont IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 2020-04-17 Based Selection tation 5 8 7 1 9 8 2 7 0 rôle et surveillance des cons eries management tructions des bureaux admin istratifs de l'ASH-SRPA-OEPA à Diégo Suarez MG-MRHP-169196-CS-QCBS / RECRUTEMENT D’UNE FIRM E EN CHARGE DE L’ELABOR Component 3. Strengthenin ATION DES PCD ET PDF DE g capacities for engaging in Quality And Cost- 2020-05-0 2020-05-2 2020-05-1 2020-07-0 2020-10-2 2020-08-0 2020-12-0 2020-08-3 2021-04-2 2020-10-0 2021-06-0 2020-11-0 2021-09-0 2021-09-0 S COMMUNES POUR LES 3 Z IDA / 59870 Post Open - National 300,000.00 157,999.04 Signed 2020-04-30 alternative fishing practices Based Selection 4 1 6 4 0 1 2 1 6 5 2 9 9 5 UPs ET REPARTIE EN TROIS and livelihoods activities LOTS: Lot 1: ZUP BA, Lot 2: ZUP BATAN Lot 3: ZUP MELAKY MG-MRHP-170094-CS-CQS / Recrutement d’un consultan Component 2. Strengthenin Consultant Qualif 2020-05-1 2020-05-2 2020-05-1 2020-06-2 2021-05-1 2020-07-2 2021-12-1 2020-08-2 2022-02-0 2021-02-2 t chargé de la traduction et IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 74,211.00 Signed 2020-04-30 ication Selection 4 1 6 5 9 5 6 9 5 5 de la synthèse des documen eries management ts du français et anglais au malagasy officiel MG-MRHP-170870-CS-QCBS / Recrutement d'une firme p Component 2. Strengthenin Quality And Cost- Under Implemen 2020-05-0 2020-05-2 2020-05-1 2020-07-0 2020-08-0 2020-09-0 2020-10-0 2020-11-1 2022-02-1 our l’élaboration du Plan d’A IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 0.00 2020-05-04 Based Selection tation 4 5 6 8 5 4 9 3 1 ménagement des Pêcheries eries management de la Région ATSIMO ATSINA NANA MG-MRHP-174365-CS-QCBS / Recrutement d'un Institut de Recherche ou d'une Firm Component 2. Strengthenin Quality And Cost- 2020-05-2 2020-06-1 2020-06-0 2020-07-3 2020-10-2 2020-08-2 2020-12-0 2020-09-2 2021-01-2 2020-10-3 2021-03-0 2020-12-0 2021-04-1 2022-02-2 e pour appuyer le Centre d’ IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 338,974.11 Signed 2020-05-26 Based Selection 0 6 6 0 0 7 2 6 9 1 4 5 5 8 Etude et de Développement eries management des Pêches (CEDP) dans l’ét ude des stocks Halieutiques (Cinq filières Prioritaires) MG-MRHP-181840-CS-QCBS Component 3. Strengthenin / RECRUTEMENT D’UNE FIRM g capacities for engaging in Quality And Cost- Under Implemen 2020-06-3 2020-07-1 2020-07-1 2020-08-1 2020-09-1 2020-10-0 2020-11-1 2020-12-1 2021-12-1 E POUR LA FORMATION DES IDA / 59870 Post Open - National 50,000.00 0.00 2020-07-02 alternative fishing practices Based Selection tation 0 2 6 6 5 6 0 5 5 GROUPEMENTS DE PÊCHEU and livelihoods activities RS SUR LES TECHNIQUES C OMMERCIALES MG-MRHP-182950-CS-CQS / Recrutement d'agence de co Component 3. Strengthenin mmunication pour la concep g capacities for engaging in Consultant Qualif 2020-08-1 2020-08-0 2020-08-2 2020-09-1 2021-10-0 2020-10-1 2022-03-3 2020-11-2 2022-04-1 2021-05-2 tion et production des suppo IDA / 59870 Post Open - National 25,000.00 61,842.50 Signed 2020-07-14 alternative fishing practices ication Selection 3 4 6 7 5 7 0 1 4 0 rts de communications relati and livelihoods activities fs au MDGP 2020 et pour la mise en oeuvre du plan de c ommunication du projet SWI Ofish2 MG-MRHP-181871-CS-QCBS / Recrutement d’ONG pour l a conservation et la restaura Component 3. Strengthenin tion des forêts de mangrove g capacities for engaging in Quality And Cost- 2020-10-0 2020-07-3 2020-10-2 2020-09-1 2021-05-2 2020-10-1 2022-01-1 2020-11-0 2022-04-0 2020-12-0 2022-10-1 2020-12-2 2021-12-2 IDA / 59870 Prior Open - National 3,000,000.00 0.00 Signed 2020-07-21 , et la protection de récifs co alternative fishing practices Based Selection 7 1 1 3 5 3 3 3 7 8 3 9 9 ralliens et d’herbiers marins and livelihoods activities dans des zones riches en ha bitats naturels côtiers et ma rins de Madagascar, répartis en 6 Lots MG-MRHP-183755-CS-QCBS / Recrutement d'une firme p our la réalisation d’une enqu Component 4. Project mana Quality And Cost- 2020-07-2 2020-08-0 2020-08-0 2020-09-1 2020-10-1 2020-10-1 2020-11-1 2020-11-0 2020-12-0 2020-12-0 2021-02-1 2020-12-2 2021-03-3 2021-03-1 IDA / 59870 Post Open - National 75,000.00 79,586.86 Signed 2020-07-17 ête de satisfaction des béné gement and coordination Based Selection 2 7 7 1 3 1 3 1 3 6 5 0 1 0 ficiaires du projet et les me mbres de la communauté de s pêcheurs MG-MRHP-28698-CS-CQS// Component 2. Strengthenin Consultant Qualif 2020-07-2 2020-09-0 2020-10-0 2020-11-0 2021-05-0 MG-PM-141 / Assistant techn IDA / 59870 g capacities for priority fish Post Open - National 24,000.00 0.00 Canceled 2020-06-30 ication Selection 1 3 3 7 6 ique pour UGP eries management MG-MRHP-183758-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- 2020-09-0 2020-09-1 2020-09-1 2020-10-2 2020-11-2 2020-11-2 2021-01-1 2020-12-1 2021-02-0 2021-01-1 2021-03-0 2021-02-2 2021-04-3 2021-10-1 IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 86,424.70 Signed 2020-08-27 our étudier la mise en place Based Selection 1 7 0 2 7 1 1 2 2 6 9 0 0 8 eries management des ZEA pêche et aquacultu re MG-MRHP-28689-CS-CQS// MG-PM-133 / Appui du centr Component 2. Strengthenin Consultant Qualif Open - Internation 2020-08-3 2020-11-1 2020-12-2 2021-03-1 2021-09-0 e de recherche par deux (02 IDA / 59870 g capacities for priority fish Post 150,000.00 0.00 Canceled 2020-07-31 ication Selection al 0 3 8 3 9 ) experts internationaux pou eries management r les évaluations de stocks d e 5 filières prioritaires MG-MRHP-190077-CS-CQS / Recrutement d'un cabinet d' Component 2. Strengthenin Consultant Qualif 2020-09-1 2020-09-2 2020-09-2 2020-11-0 2021-03-1 2020-12-0 2021-05-1 2021-01-0 2022-05-1 2021-03-0 étude pour effectuer une ét IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 50,426.00 Signed 2020-08-31 ication Selection 1 1 3 4 1 4 4 8 1 9 ude de faisabilité de l'éclose eries management rie en holothuries à Ambanj a MG-MRHP-28671-CS-QCBS// MG-PM-123 / Amélioration d e la base de données pour l Component 2. Strengthenin Quality And Cost- 2018-01-2 2018-03-3 2018-04-2 2018-05-2 2018-07-0 2018-08-1 2019-08-1 a déclaration des produits d IDA / D1720 g capacities for priority fish Post Open - National 20,000.00 0.00 Canceled 2018-01-02 Based Selection 3 0 7 7 8 9 9 e la pêche régionale (Base d eries management e données-Tableau de bord- Système d'Information Pêch e :basé sur le Web, consulta nt) MG-MRHP-198557-CS-QCBS / Recrutement des BE pour Component 3. Strengthenin réaliser les études techniqu g capacities for engaging in Quality And Cost- 2020-10-1 2020-11-0 2020-12-2 2021-04-0 2021-01-1 2021-11-0 2021-02-1 2021-05-1 2021-03-2 2021-07-1 2021-04-2 2021-11-0 2021-11-2 es et EIES de la construction TF / A4588 Post Open - National 130,000.00 108,278.08 Signed 2020-10-16 alternative fishing practices Based Selection 9 6 0 1 9 3 8 4 5 6 9 5 5 des bâtiments de pré-électri and livelihoods activities fication hors grille et comple xe pêche au niveau BATAN et Aniribe (BA) répartis en 4 Lots MG-MRHP-199272-CS-CQS / Recrutement d'un BE études Component 2. Strengthenin Consultant Qualif Under Implemen 2020-10-1 2020-11-0 2020-12-1 2021-03-1 2021-01-1 2021-02-1 2021-09-0 techniques- EIES et contrôle IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2020-10-19 ication Selection tation 9 9 3 1 2 6 4 et surveillance des travaux eries management à la mise en place d'écloseri e_Ambanja MG-MRHP-203599-CS-CQS / Recrutement d’une firme po ur la conception et le dévelo ppement de site web pour l’ Component 2. Strengthenin Consultant Qualif 2020-11-2 2020-12-1 2020-11-2 2021-01-1 2021-03-2 2021-02-1 2021-06-0 2021-03-2 2021-09-2 2021-05-1 Observatoire Economique d IDA / Q9790 g capacities for priority fish Post Open - National 45,000.00 76,667.73 Signed 2020-11-20 ication Selection 1 1 6 5 3 4 8 1 5 0 e la Pêche et de l’Aquacultur eries management e (OEPA), pour le Centre d’E tudes et de Développement des Pêches (CEDP) et pour l’ Unité Statistique Thonière d’ Antsiran MG-MRHP-208296-CS-CQS / Recrutement d'un BE études techniques, EIES et C&S des Component 3. Strengthenin travaux pour la construction g capacities for engaging in Consultant Qualif 2021-01-1 2021-01-1 2021-01-1 2021-02-1 2021-03-2 2021-03-1 2021-06-1 2021-04-2 2021-09-1 2021-11-1 TF / A4588 Post Open - National 20,000.00 36,890.00 Signed 2020-12-21 des bâtiments du kiosque d alternative fishing practices ication Selection 2 1 9 4 6 6 0 0 4 6 e pré-électrification et du « and livelihoods activities Complexe-pêche » dans les villages d’Ambalahonko et A mpasimandroro district de M aintirano MG-MRHP-208303-CS-QCBS / Recrutement des BE pour r Component 3. Strengthenin éaliser les études technique g capacities for engaging in Quality And Cost- 2021-01-1 2021-01-1 2021-01-1 2021-02-2 2021-03-3 2021-03-2 2021-04-3 2021-04-2 2021-05-2 2021-05-3 2021-07-1 2021-07-0 2022-09-2 2022-01-3 IDA / 59870 Post Open - National 180,000.00 146,654.22 Signed 2020-12-21 s, PGES et et contrôle et sur alternative fishing practices Based Selection 2 1 9 4 1 6 0 5 5 0 9 4 2 0 veillance des travaux de con and livelihoods activities struction des petites infrast ructures de pêches répartis en 6 lots MG-MRHP-208305-CS-CQS / Component 2. Strengthenin Recrutement d'un BE pour l Consultant Qualif 2021-01-1 2021-01-1 2021-01-1 2021-02-2 2021-03-2 2021-03-2 2021-06-1 2021-04-3 2021-09-2 2021-09-2 IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 25,708.56 Signed 2020-12-21 e contrôle et surveillance de ication Selection 2 1 9 4 3 6 0 0 8 7 eries management s travaux des DRAEP à Andr oy, Anosy MG-MRHP-208306-CS-CQS / Component 2. Strengthenin Recrutement d'un BE pour l Consultant Qualif 2021-01-1 2021-01-1 2021-01-1 2021-02-2 2021-03-2 2021-03-2 2021-10-0 2021-04-3 2021-10-2 2021-09-2 IDA / 59870 g capacities for priority fish Post Open - National 8,000.00 15,062.89 Signed 2020-12-21 e contrôle et la surveillance ication Selection 2 1 9 4 3 6 4 0 1 7 eries management des travaux du DRAEP à Mai ntirano MG-MRHP-214299-CS-QCBS / Recrutement d’une firme p Component 2. Strengthenin Quality And Cost- 2021-01-2 2021-02-1 2021-02-0 2021-03-0 2021-03-3 2021-03-3 2021-04-3 2021-04-2 2021-05-1 2021-05-2 2021-06-0 2021-06-3 2021-09-1 2022-09-2 our l’élaboration du Plan d’A IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 137,749.52 Signed 2021-01-29 Based Selection 8 3 4 1 0 1 0 1 4 6 7 0 4 3 ménagement des Pêcheries eries management (PAP) de la Région ANDROY MG-MRHP-216848-CS-CQS / Recrutement d'un BE pour ET, élaboration du PGES et C Component 3. Strengthenin &S relative à la construction g capacities for engaging in Consultant Qualif Under Implemen 2021-02-2 2021-03-1 2021-03-0 2021-04-1 2021-05-1 2021-06-1 2022-02-0 IDA / 59870 Post Open - National 33,000.00 0.00 2021-02-17 du bureau de la Circonscripti alternative fishing practices ication Selection tation 4 0 9 3 3 7 2 on en charge de la pêche et and livelihoods activities de l’Aquaculture et l’l’anten ne du Centre de Surveillanc e des Pêches (CSP) à Maintir ano MG-MRHP-218699-CS-CQS / Component 2. Strengthenin Recrutement d’une firme po Consultant Qualif Under Implemen 2021-02-2 2021-03-0 2021-03-0 2021-04-2 2021-05-2 2021-06-2 2021-10-2 IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 2021-02-15 ur Etude des impacts du CO ication Selection tation 3 8 2 1 1 5 3 eries management VID19 sur la pêche à Madag ascar MG-MRHP-222309-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif 2021-03-1 2021-03-3 2021-03-2 2021-05-1 2021-04-2 2021-06-1 2021-05-2 2021-07-1 2021-09-1 2021-09-0 ur réaliser un diagnostic inst IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 13,920.80 Signed 2021-03-17 ication Selection 4 1 6 4 1 3 8 8 4 1 itutionnel et organisationnel eries management de la mise en oeuvre du proj et SWIOFish2 MG-MRHP-222313-CS-QCBS / Recrutement d’une firme e n charge de l’identification d Component 3. Strengthenin es plans de pérennisation in g capacities for engaging in Quality And Cost- Under Implemen 2022-01-1 2021-04-0 2022-01-1 2021-05-2 2022-03-1 2021-06-2 2022-05-0 2021-07-2 2022-05-2 2021-08-2 2022-06-0 2021-09-2 2022-01-2 IDA / 59870 Post Open - National 90,000.00 0.00 2021-03-24 cluant un plan de gestion et alternative fishing practices Based Selection tation 2 7 7 1 7 0 3 0 4 4 3 8 6 un plan d’affaire des petites and livelihoods activities infrastructures de pêche et complexes pêches dans les zones ultra prioritaires BATA N, BA et MELAKY MG-MRHP-224627-CS-CQS / Component 2. Strengthenin Recrutement firme pour pro Consultant Qualif Under Implemen 2021-03-3 2021-04-2 2021-04-1 2021-06-0 2021-07-0 2021-08-0 2022-02-0 IDA / 59870 g capacities for priority fish Post Open - National 115,000.00 0.00 2021-03-30 spection nouvelles zones de ication Selection tation 0 0 5 3 3 7 3 eries management pêche langoustes MG-MRHP-223841-CS-CQS / Cabinet pour le recrutement Component 2. Strengthenin Consultant Qualif 2021-05-0 2021-04-2 2021-06-0 2021-09-2 2021-07-0 2021-12-2 2021-08-0 2022-03-2 2021-10-0 de 75 enquêteurs pour le dé IDA / Q9790 g capacities for priority fish Post Open - National 40,000.00 23,150.53 Signed 2021-03-31 ication Selection 1 1 4 9 4 3 8 2 7 ploiement d'OPENARTFISH d eries management ans 5 régions côtières MG-MRHP-222316-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- Under Implemen 2021-04-2 2021-06-0 2021-07-0 2021-08-0 2021-09-0 2021-10-1 2022-04-1 IDA / 59870 g capacities for priority fish Prior Open - National 1,250,000.00 0.00 2021-03-31 our l'Appui au développeme Based Selection tation 1 4 4 3 7 2 0 eries management nt de l’économie bleue à Ma dagascar MG-MRHP-227234-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2021-04-0 2021-04-2 2021-06-1 2021-07-1 2021-08-1 2022-02-1 ur la mise à jour de la straté IDA / 59870 g capacities for priority fish Post Open - National 30,000.00 0.00 2021-04-07 ication Selection tation 9 8 1 1 5 1 gie Nationale de la Bonne G eries management ouvernance de la Pêche Mar itime MG-MRHP-229422-CS-QCBS Component 2. Strengthenin Quality And Cost- Under Implemen 2021-05-1 2021-05-2 2021-10-1 2021-06-2 2022-03-0 2021-07-2 2022-04-1 2021-08-1 2022-05-3 2021-09-2 2022-07-2 2021-10-2 2023-01-2 / Recrutement des firmes po IDA / 59870 g capacities for priority fish Post Open - National 700,000.00 0.00 2021-05-14 Based Selection tation 8 9 4 8 2 8 1 8 0 2 0 7 0 ur l'élaboration des PAP régi eries management onaux Page 8 MG-MRHP-28730-CS-CQS// Component 2. Strengthenin Consultant Qualif Open - Internation 2021-07-2 2021-09-0 2021-10-0 2021-11-0 2022-05-0 MG-PM-157 / Étude pour l'ex IDA / 59870 g capacities for priority fish Post 50,000.00 0.00 Canceled 2021-07-01 ication Selection al 2 4 4 8 7 tension de l'ERS vers la flott eries management e nationale MG-MRHP-231603-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2021-06-0 2021-06-0 2021-10-1 2021-07-1 2022-01-0 2021-08-1 2022-05-0 2021-09-2 2021-12-2 ur réaliser une étude diagno IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2021-05-14 ication Selection tation 9 4 4 8 7 7 2 1 0 stique des besoins en renfor eries management cement des capacités DGPA et UGP SWIOFish2 MG-MRHP-231604-CS-LCS / Component 4. Project mana Least Cost Select 2021-06-1 2021-07-2 2021-08-2 2021-09-2 2021-10-2 2021-11-2 2022-01-2 Recrutement d'audit pour le IDA / Q9790 Post Open - National 32,500.00 0.00 Canceled 2021-05-20 gement and coordination ion 0 4 1 0 5 9 8 Centre de Surveillance de P êche MG-MRHP-232532-CS-LCS / Recrutement d'un cabinet d' Component 4. Project mana Least Cost Select 2021-07-1 2021-06-1 2021-07-2 2021-09-2 2021-08-2 2021-10-2 2021-09-2 2021-11-1 2021-10-2 2022-01-2 2021-11-2 2022-02-2 2023-09-2 IDA / 59870 Post Open - National 50,000.00 20,442.04 Signed 2021-05-20 audit externe des comptes d gement and coordination ion 5 0 4 3 1 5 0 2 5 6 9 4 9 u Projet 2021-2022 et 2023 MG-MRHP-236858-CS-CQS / Component 2. Strengthenin Recrutement d'un BE pour l Consultant Qualif Under Implemen 2021-08-0 2021-07-1 2021-10-1 2021-08-2 2021-11-2 2021-09-2 2022-05-3 2021-10-3 2022-04-2 TF / A4588 g capacities for priority fish Post Open - National 30,000.00 0.00 2021-06-30 es études technique et contr ication Selection tation 6 4 4 7 6 6 1 1 9 eries management ôle et surveillance du Burea u CSP à Toliara MG-MRHP-239019-CS-CQS / Recrutement d'un BE ET- PG Component 2. Strengthenin ES et C&S relative à la con Consultant Qualif Under Implemen 2021-08-0 2021-07-1 2021-10-1 2021-08-1 2021-09-1 2021-10-2 2022-06-0 IDA / 59870 g capacities for priority fish Post Open - National 37,000.00 0.00 2021-06-30 struction du bureau de la Cir ication Selection tation 6 4 4 7 6 1 8 eries management conscription en charge de la pêche et de l’Aquaculture à Besalampy. MG-MRHP-28755BIS-CS-QC BS // MG-PM-177 / Élaboratio Component 3. Strengthenin n des plans d'action aux rest g capacities for engaging in Quality And Cost- 2019-08-3 2020-01-2 2020-02-2 2020-04-0 2020-04-1 2021-02-0 2021-10-0 rictions de ressources (PARA IDA / 59870 Post Open - National 875,300.00 0.00 Canceled 2019-08-22 alternative fishing practices Based Selection 0 9 8 7 3 9 7 R) / Diagnostic des besoins and livelihoods activities en activités alternatives ada ptées à chaque région ultra prioritaire (AGR) MG-MRHP-150349-CS-CQS / Recrutement de consultant national pour assurer le renf Component 2. Strengthenin orcement de capacité des a Consultant Qualif Pending Implem 2022-01-1 2022-02-0 2022-03-2 2022-04-0 2022-04-2 IDA / 59870 g capacities for priority fish Post Open - National 1,500.00 0.00 2022-01-04 gents de l’administration de ication Selection entation 1 8 0 3 4 eries management s pêches et des responsable s des textes administratifs e n leadership et Gestion axés sur les résultats (2.1.1.1.04) MG-MRHP-14959-CS-CQS / Component 3. Strengthenin Mise en place d’une règleme g capacities for engaging in Consultant Qualif Open - Internation 2021-11-1 2022-01-2 2022-03-1 2022-05-1 2022-11-0 IDA / 59870 Post 60,000.00 0.00 Canceled 2021-09-30 ntation de base concernant l alternative fishing practices ication Selection al 4 8 4 3 9 a sécurité en mer de la petit and livelihoods activities e pêche MG-MRHP-263393-CS-CQS / Recrutement des BE pour ré Component 3. Strengthenin aliser les études techniques, g capacities for engaging in Consultant Qualif 2021-12-1 2021-12-1 2021-12-2 2022-01-2 2022-03-1 2022-02-2 2022-06-0 2022-04-0 2022-07-2 2022-09-2 IDA / 59870 Post Open - National 77,000.00 98,415.82 Signed 2021-11-23 PGES et contrôle et surveilla alternative fishing practices ication Selection 5 4 1 7 7 6 9 2 0 9 nce des travaux de construc and livelihoods activities tion des petites infrastructur es de pêches (relance lot 1 et 5) MG-MRHP-264080-CS-CQS / Recrutement des BE pour é Component 3. Strengthenin tudes techniques, PGES et C g capacities for engaging in Consultant Qualif 2021-12-1 2021-12-2 2021-12-2 2022-01-2 2022-03-1 2022-02-2 2022-06-0 2022-03-3 2022-07-2 2022-10-1 IDA / 59870 Post Open - National 84,000.00 111,436.73 Signed 2021-11-30 ontrôle et surveillance des tr alternative fishing practices ication Selection 5 1 1 4 7 3 9 0 0 6 avaux de construction des b and livelihoods activities âtiments abritant les chamb res froide repartis en 3 lots MG-MRHP-288108-CS-CQS / Component 2. Strengthenin Mise à jour l’enquête cadre Consultant Qualif Under Implemen 2022-04-1 2022-05-0 2022-05-0 2022-06-1 2022-08-0 2022-07-1 2022-11-1 2022-08-1 2023-02-1 IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 2022-04-11 nationale 2012-2013 sur la ication Selection tation 8 2 3 5 5 5 8 9 5 eries management petite pêche maritime et la pêche continentale MG-MRHP-232529-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- Open - Internation 2022-01-2 2021-06-1 2021-07-2 2021-08-2 2021-09-2 2021-10-2 2021-11-2 2022-11-2 IDA / 59870 g capacities for priority fish Prior 2,000,000.00 0.00 Canceled 2021-05-20 our le développement de la Based Selection al 3 0 4 1 0 5 9 9 eries management planification spatiale mariti me PSM à Madagascar MG-MRHP-232529 BIS-CS-Q CBS / Recrutement d'une fir Component 2. Strengthenin Quality And Cost- Open - Internation Under Implemen 2022-04-2 2022-05-1 2022-04-2 2022-06-2 2022-07-2 2022-08-2 2022-09-2 2022-10-3 2023-10-3 me pour le développement IDA / 59870 g capacities for priority fish Post 600,000.00 0.00 2022-04-20 Based Selection al tation 5 1 8 4 2 1 5 0 0 de la planification spatiale eries management maritime PSM à Madagascar MG-MRHP-239018-CS-CQS / Recrutement d’une firme po Component 2. Strengthenin ur élaborer et mettre à jour l Consultant Qualif 2021-10-1 2021-10-0 2021-12-2 2021-11-1 2021-12-1 2021-12-2 2022-05-0 IDA / 59870 g capacities for priority fish Post Open - National 56,000.00 0.00 Canceled 2021-09-22 es textes d’application de la ication Selection 9 6 1 0 0 4 3 eries management nouvelle loi portant Code de la Pêche et de l'Aquaculture à Madagascar MG-MRHP-28757-CS-QCBS// Component 3. Strengthenin MG-PM-179 / Étude de faisa g capacities for engaging in Quality And Cost- Open - Internation 2021-10-3 2022-01-1 2022-02-2 2022-04-1 2022-06-1 2022-08-1 2023-08-1 bilité technique des constru IDA / 59870 Post 795,000.00 0.00 Canceled 2021-10-01 alternative fishing practices Based Selection al 1 4 8 4 3 2 2 ctions d'infrastructures de p and livelihoods activities êche(APS & APD) (33 débarc adères, 8 marchés couverts) MG-MRHP-252969-CS-CQS / Component 3. Strengthenin Recrutement d'une firme po g capacities for engaging in Consultant Qualif 2021-10-1 2021-11-1 2021-12-1 2022-01-0 2022-12-2 IDA / 59870 Post Open - National 100,000.00 0.00 Canceled 2021-09-30 ur la promotion de transfert alternative fishing practices ication Selection 4 8 8 1 7 financier pour les 03 ZUP. and livelihoods activities MG-MRHP-218708-CS-QCBS Component 3. Strengthenin / Recrutement d’une firme g capacities for engaging in Quality And Cost- Pending Implem 2022-05-1 2022-06-1 2022-07-1 2022-08-0 2022-09-1 2022-10-1 2023-02-1 en charge de l’élaboration d’ IDA / 59870 Post Open - National 100,000.00 0.00 2022-05-10 alternative fishing practices Based Selection entation 5 9 9 9 3 8 5 un plan de formation/renforc and livelihoods activities ement de capacités des élus et des acteurs MG-MRHP-198566-CS-QCBS / Recrutement des BE pour é Component 3. Strengthenin tudes techniques- PGES et c g capacities for engaging in Quality And Cost- 2020-11-1 2020-12-2 2021-01-2 2021-02-2 2021-04-0 2021-05-0 2021-12-0 IDA / 59870 Post Open - National 240,000.00 0.00 Canceled 2020-10-23 ontrôle et surveillance des tr alternative fishing practices Based Selection 3 7 6 5 1 6 2 avaux des petites infrastruct and livelihoods activities ures de pêches pour les 3 Z ups répartis en 8 Lots. MG-MRHP-239018-CS-CQS- 2 / Recrutement d'une firme Component 2. Strengthenin pour élaborer et mettre à jo Consultant Qualif Under Implemen 2022-05-1 2022-05-0 2022-05-1 2022-06-0 2022-07-0 2022-07-2 2022-11-2 IDA / 59870 g capacities for priority fish Post Open - National 56,000.00 0.00 2022-04-18 ur les textes d'application d ication Selection tation 0 2 6 6 6 0 7 eries management e la nouvelle loi portant Cod e de la Pêche et de l'Aquacu lture à Madagascar. MG-MRHP-14951-CS-QCBS / PA 65: Etudes techniques : - Clôture de l'enceinte DRRHP Component 2. Strengthenin Fénérive - Construction des Quality And Cost- 2019-08-1 2019-09-2 2019-10-2 2019-11-2 2019-12-3 2020-02-0 2021-02-0 IDA / Q9790 g capacities for priority fish Post Open - National 35,000.00 0.00 Canceled 2019-07-26 Bureaux de 06 DRRHP - Exte Based Selection 6 9 7 6 1 4 3 eries management nsion de l'ASH à Antsiranana et Morondava - Construction local pour bureau UGP et 0 8 CirRHP (APS/APD) MG-MRHP-285789-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif 2022-04-1 2022-06-0 2022-07-0 2022-08-0 2023-02-0 ur mettre à jour l’enquête c IDA / 59870 g capacities for priority fish Post Open - National 100,000.00 0.00 Canceled 2022-03-28 ication Selection 8 1 1 5 1 adre nationale 2012-2013 s eries management ur la petite pêche maritime et la pêche continentale MG-MRHP-150366-CS-CQS / RECRUTEMENT D'UN CONSU Component 2. Strengthenin LTANT NATIONAL POUR LA F Consultant Qualif 2021-07-3 2021-08-2 2021-10-0 2021-10-2 2021-12-1 IDA / 59870 g capacities for priority fish Post Open - National 15,000.00 0.00 Canceled 2021-07-23 ORMATION ET RENFORCEME ication Selection 0 7 6 0 9 eries management NT DE CAPACITE DE L’EQUIP E EN COMMUNICATION (2.1. 4.1.05) MG-MRHP-150361-CS-CQS / RECRUTEMENT D'UN CONSU LTANT NATIONAL POUR LE R Component 2. Strengthenin ENFORCEMENT DE CAPACIT Consultant Qualif Pending Implem 2022-11-0 2022-12-0 2023-01-1 2023-01-2 2023-03-3 IDA / 59870 g capacities for priority fish Post Open - National 8,000.00 0.00 2022-11-01 E DU PERSONNEL DE L’AUT ication Selection entation 8 6 5 9 0 eries management ORITE SANITAIRE HALIEUTIQ UE EN INFORMATIQUE (BUR EAUTIQUE ET PROGRAMMAT ION) AU NIVEAU NATIONAL ( 2.1.7.2.02) MG-MRHP-298214-CS-CQS / Recrutement d’une firme ch Component 3. Strengthenin argée de l’appui à la promot g capacities for engaging in Consultant Qualif Under Implemen 2022-06-1 2022-07-1 2022-08-1 2022-09-1 2022-10-0 2023-09-2 IDA / 59870 Post Open - National 70,000.00 0.00 2022-06-30 ion des produits halieutique alternative fishing practices ication Selection tation 5 4 8 7 1 6 s valorisés au niveau des ZU and livelihoods activities P sur le marché national/inte rnational MG-MRHP-304395-CS-CQS / Recrutement d’une firme po Component 3. Strengthenin ur l’étude de faisabilité de m g capacities for engaging in Consultant Qualif Under Implemen 2022-07-2 2022-08-1 2022-10-0 2022-11-0 2022-12-0 2023-03-0 IDA / 59870 Post Open - National 60,000.00 0.00 2022-07-29 ise en place d’unités de pro alternative fishing practices ication Selection tation 2 9 2 1 6 6 duction artisanale de conser and livelihoods activities ves de sardines à BATAN et BA MG-MRHP-304402-CS-QCBS Component 2. Strengthenin / Recrutement d'une firme p Quality And Cost- Open - Internation Under Implemen 2022-08-0 2022-08-1 2022-08-2 2022-10-0 2022-10-3 2022-11-2 2023-01-0 2023-02-0 2023-08-0 IDA / 59870 g capacities for priority fish Post 205,000.00 0.00 2022-07-29 our la lise en place des outil Based Selection al tation 3 9 2 2 0 9 3 7 6 eries management s d'aménagement des pêch eries à Madagascar MG-MRHP-307091-CS-CQS / Component 2. Strengthenin Evaluation des emplois direc Consultant Qualif Under Implemen 2022-09-1 2022-09-0 2022-10-0 2022-10-1 2022-11-1 2022-12-2 2023-06-1 IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2022-08-12 ts et indirects issus de la pet ication Selection tation 5 2 7 6 5 0 8 eries management ite pêche au niveau des 03 ZUP du Projet MG-MRHP-307110-CS-CQS / Elaboration de Cartographie Component 2. Strengthenin Consultant Qualif Under Implemen 2022-09-1 2022-09-0 2022-10-3 2022-10-1 2022-11-1 2022-12-2 2023-06-1 détaillée pour le développe IDA / 59870 g capacities for priority fish Post Open - National 150,000.00 0.00 2022-08-12 ication Selection tation 5 2 1 6 5 0 8 ment de l’holothuriculture, l eries management a crabiculture, l’algoculture et l’aquaculture continental e. MG-MRHP-307200-CS-CQS / Recrutement d’une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2022-09-1 2022-08-3 2022-10-2 2022-10-0 2022-11-0 2022-12-0 2023-06-1 ur la mise en place d’un site IDA / 59870 g capacities for priority fish Post Open - National 20,000.00 0.00 2022-08-09 ication Selection tation 5 0 7 4 3 8 6 web dynamique du Ministèr eries management e de la Pêche et de l’Écono mie Bleue MG-MRHP-306851-CS-CQS / Etude technique, l'élaboratio Component 2. Strengthenin Consultant Qualif Under Implemen 2022-11-2 2022-10-2 2022-12-1 2022-12-0 2023-01-0 2023-02-0 2023-08-0 n du PGES , contrôle et surv IDA / 59870 g capacities for priority fish Post Open - National 60,000.00 0.00 2022-09-29 ication Selection tation 4 0 5 3 2 6 5 eillance des travaux de cons eries management truction de l'antenne CDPH M à Besalampy MG-MRHP-306857-CS-CQS / Component 3. Strengthenin Etude techniques élaboratio g capacities for engaging in Consultant Qualif Under Implemen 2022-11-2 2022-10-1 2022-12-1 2022-12-0 2023-01-0 2023-02-0 2023-08-0 n PGES et Contrôle & surveil IDA / 59870 Post Open - National 35,000.00 0.00 2022-09-28 alternative fishing practices ication Selection tation 4 9 6 2 1 5 4 lance de la Construction déb and livelihoods activities arcadère à Ankazomborona MG-MRHP-320120-CS-CQS / Component 3. Strengthenin Recrutement d'une associati g capacities for engaging in Consultant Qualif Under Implemen 2022-10-2 2022-10-2 2022-10-3 2022-11-1 2022-12-0 2022-12-1 2023-09-2 on pour l’étude et la mise en IDA / 59870 Post Open - National 40,000.00 0.00 2022-10-21 alternative fishing practices ication Selection tation 7 2 1 9 3 7 9 place d’habitats artificiels d and livelihoods activities ans quatre zones côtières Page 9 MG-MRHP-320122-CS-CQS / Recrutement d'une firme po Component 2. Strengthenin Consultant Qualif Under Implemen 2022-10-2 2022-11-0 2022-12-0 2022-12-0 2023-01-0 2023-01-2 2023-05-2 ur l'élaboration de la Politiqu IDA / 59870 g capacities for priority fish Post Open - National 75,000.00 0.00 2022-10-21 ication Selection tation 5 4 6 9 8 9 9 e Nationale intégrée de la G eries management ouvernance de l'Océan à Ma dagascar MG-MRHP-355022-CS-CQS / Component 3. Strengthenin Recrutement d’une ONG po g capacities for engaging in Consultant Qualif Under Implemen 2023-05-0 2023-04-2 2023-05-2 2023-05-1 2023-05-2 2023-05-3 2023-08-2 IDA / 59870 Post Open - National 250,000.00 0.00 2023-04-09 ur la mise en œuvre des Acti alternative fishing practices ication Selection tation 9 4 3 9 4 1 9 vités Alternatives (PARAR/A and livelihoods activities GR) MG-MRHP-239021-CS-CQS / Component 4. Project mana Consultant Qualif Under Implemen 2023-05-2 2023-05-2 2023-05-2 2023-06-0 2023-07-0 2023-07-2 2023-09-2 Recrutement firme pour l'év IDA / 59870 Post Open - National 75,000.00 0.00 2023-05-10 gement and coordination ication Selection tation 3 4 5 7 7 1 9 aluation finale du projet SWI OFish2 MG-MRHP-239020-CS-CQS / Component 2. Strengthenin Recrutement d'une firme po Consultant Qualif Under Implemen 2023-05-0 2023-05-2 2023-05-2 2023-06-2 2023-07-1 2023-07-2 2023-09-2 IDA / 59870 g capacities for priority fish Post Open - National 25,000.00 0.00 2023-05-10 ur l'élaboration de manuel d ication Selection tation 9 4 2 8 2 6 4 eries management e l'audit interne du MPEB MG-MRHP-362176-CS-CQS / Renforcement de capacité d Component 3. Strengthenin u comité de gestion des infr g capacities for engaging in Consultant Qualif Under Implemen 2023-06-1 2023-07-2 2023-08-0 2023-08-1 2023-09-1 IDA / 59870 Post Open - National 270,000.00 0.00 2023-05-26 astructures sur la gestion de alternative fishing practices ication Selection tation 6 1 5 5 4 s infrastructures et appui à l' and livelihoods activities opérationnalisation des petit es infrastructures; Component 3. Strengthenin MG-MRHP-363621-CS-CQS / g capacities for engaging in Consultant Qualif Under Implemen 2023-06-0 2023-06-1 2023-06-1 2023-06-2 2023-07-1 2023-07-2 2023-09-1 Formation sur la fabrication IDA / 59870 Post Open - National 30,000.00 0.00 2023-05-30 alternative fishing practices ication Selection tation 6 4 4 4 4 1 9 des pirogues and livelihoods activities MG-MRHP-4770-CS-CQS / C onception d'un système de c Component 2. Strengthenin Consultant Qualif Open - Internation 2017-02-2 2017-04-0 2017-05-0 2017-06-1 2017-12-0 ollecte de données pour les IDA / Q9790 g capacities for priority fish Post 10,000.00 0.00 Canceled 2017-02-01 ication Selection al 2 7 7 1 8 pêcheries traditionnelles, y eries management compris une stratégie d'éch antillonnage appropriée MG-MRHP-4769-CS-CQS / Mi Component 2. Strengthenin se à jour de la Stratégie d'a Consultant Qualif Open - Internation 2017-02-2 2017-04-0 2017-05-0 2017-06-1 2017-12-0 IDA / Q9790 g capacities for priority fish Post 75,000.00 0.00 Canceled 2017-02-01 quaculture et élaboration de ication Selection al 2 7 7 1 8 eries management plan de développement des 03 filières aquaculture INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MG-MRHP-23395-CS-INDV// PA75 / Recrutement d'un (0 Component 4. Project mana Individual Consul 2017-08-0 2017-09-2 2017-09-2 2017-10-1 2017-10-0 2017-11-2 2017-10-0 2018-05-2 2019-04-0 1) Spécialiste en Passation d IDA / Q9790 Post Open 15,600.00 15,412.69 Completed 2017-08-02 gement and coordination tant Selection 3 0 1 1 2 2 3 1 1 es Marchés en appui à l'équi pe de passation des marché s de l'UGP SWIOFish2. MG-MRHP-28176-CS-INDV// MG-PM-24 / Diagnostic des t echniques de valorisation pr Component 3. Strengthenin atiquées à Madagascar et le g capacities for engaging in Individual Consul 2018-02-1 2018-03-1 2018-04-1 2018-10-0 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2017-11-30 s bonnes pratique en Afriqu alternative fishing practices tant Selection 8 8 0 7 e et identifier les besoins en and livelihoods activities technique de valorisation de s produits halieutiques de ch aque région ultra prioritaire MG-MRHP-28321-CS-INDV// Component 3. Strengthenin MG-PM-26 / Évaluation du ni g capacities for engaging in Individual Consul 2018-01-1 2018-01-3 2018-03-1 2018-09-1 IDA / D1720 Post Open 90,000.00 0.00 Canceled 2017-10-30 veau de vulnérabilité des m alternative fishing practices tant Selection 0 1 4 0 énages bénéficiaires and livelihoods activities MG-MRHP-28328-CS-INDV// Component 3. Strengthenin MG-PM-30 / Élaboration du p g capacities for engaging in Individual Consul 2018-01-2 2018-02-1 2018-03-2 2018-09-2 IDA / 59870 Post Open 10,500.00 0.00 Canceled 2017-10-30 lan stratégique de développ alternative fishing practices tant Selection 5 5 9 5 ement local (PCD et PLD) and livelihoods activities MG-MRHP-28338-CS-INDV// Component 4. Project mana Individual Consul 2017-12-2 2018-01-1 2018-02-2 2018-08-2 MG-PM-35 / Assistants coord IDA / 59870 Post Open 20,800.00 0.00 Canceled 2017-10-16 gement and coordination tant Selection 0 0 1 0 inateurs locaux UGL MG-MRHP-28344-CS-INDV// MG-PM-41 / Élaboration d'un Component 4. Project mana Individual Consul 2018-02-2 2018-03-1 2018-04-2 2018-10-2 IDA / 59870 Post Open 10,000.00 0.00 Canceled 2017-12-15 e stratégie du plan de comm gement and coordination tant Selection 5 8 9 6 unication du projet SWIOFis h2 MG-MRHP-28345-CS-INDV// Component 4. Project mana Individual Consul 2018-01-2 2018-02-1 2018-03-3 2018-09-2 MG-PM-42 / Mise en place d IDA / 59870 Post Open 2,000.00 0.00 Canceled 2017-11-15 gement and coordination tant Selection 6 6 0 6 u site internet du projet SWI OFish2 MG-MRHP-28346-CS-INDV// Component 4. Project mana Individual Consul 2018-02-1 2018-03-1 2018-04-2 2018-10-1 MG-PM-43 / Mission de couv IDA / 59870 Post Open 1,000.00 0.00 Canceled 2017-12-15 gement and coordination tant Selection 8 1 2 9 erture des autres activités d e communication MG-MRHP-27289-CS-INDV// Component 2. Strengthenin PA27 / Évaluation et dévelop Individual Consul 2015-09-0 2017-10-2 2017-11-1 2016-11-0 2017-12-2 2017-11-1 2018-06-1 2018-08-3 IDA / Q9790 g capacities for priority fish Post Open 50,000.00 35,963.63 Completed 2017-09-07 pement de la recherche hali tant Selection 9 6 6 1 1 4 9 0 eries management eutique (pour les 5 filières p rioritaires MG-MRHP-28651-CS-INDV// Component 2. Strengthenin Individual Consul 2018-09-0 2018-09-2 2018-11-0 2019-05-0 MG-PM-111 / Assistance Tec IDA / 59870 g capacities for priority fish Post Open 10,000.00 0.00 Canceled 2018-07-02 tant Selection 5 6 7 6 hnique juridique pour le SLC eries management MG-MRHP-28653-CS-INDV// MG-PM-112 / Étude et analy Component 2. Strengthenin se diagnostiques des stratég Individual Consul 2018-04-0 2018-04-2 2018-06-0 2018-12-0 IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-01-30 ies du secteur et des ancien tant Selection 5 6 7 4 eries management s plans directeurs et élabora tion du nouveau plan directe ur MG-MRHP-28692-CS-INDV// Component 2. Strengthenin MG-PM-136 / Développemen Individual Consul 2018-05-0 2018-05-2 2018-06-3 2018-12-2 IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-03-01 t des points de référence op tant Selection 5 6 0 7 eries management érationnels pour la gestion d e la pêche crevettière MG-MRHP-28704-CS-INDV// Component 2. Strengthenin Individual Consul 2018-08-0 2018-08-2 2018-09-3 2019-03-2 MG-PM-148 / Audit techniqu IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-06-01 tant Selection 5 6 0 9 e et financier de la pêche au eries management x thons MG-MRHP-28744-CS-INDV// Component 3. Strengthenin MG-PM-169 / Prestataire for g capacities for engaging in Individual Consul 2019-01-0 2019-01-2 2019-03-0 2019-08-2 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2018-11-01 mateur en construction et e alternative fishing practices tant Selection 5 6 2 9 ntretien des embarcations and livelihoods activities MG-MRHP-28751-CS-INDV// Component 3. Strengthenin MG-PM-174 / Prestataire for g capacities for engaging in Individual Consul 2018-08-1 2018-09-0 2018-10-1 2019-04-1 IDA / 59870 Post Open 75,000.00 0.00 Canceled 2018-06-15 mateur en technique de val alternative fishing practices tant Selection 9 9 4 2 orisation and livelihoods activities MG-MRHP-28752-CS-INDV// Component 3. Strengthenin MG-PM-175 / Prestataire for g capacities for engaging in Individual Consul 2018-09-1 2018-10-0 2018-11-1 2019-05-1 IDA / 59870 Post Open 25,000.00 0.00 Canceled 2018-06-29 mateur en technique comm alternative fishing practices tant Selection 7 8 2 1 erciale and livelihoods activities MG-MRHP-28758-CS-INDV// MG-PM-181 / Étude d'impact Component 3. Strengthenin environnemental et social d g capacities for engaging in Individual Consul 2018-07-1 2018-08-0 2018-09-1 2019-03-1 IDA / 59870 Post Open 90,000.00 0.00 Canceled 2018-05-30 es constructions d'infrastruc alternative fishing practices tant Selection 8 8 2 1 tures de pêche(APS & APD) ( and livelihoods activities 33 débarcadères, 8 marchés couverts) MG-MRHP-28762-CS-INDV// Component 3. Strengthenin MG-PM-184 / Gestion et mis g capacities for engaging in Individual Consul 2018-07-1 2018-08-0 2018-09-1 2019-03-1 IDA / V0500 Post Open 15,000.00 0.00 Canceled 2018-05-30 e en œuvre : évaluation de l alternative fishing practices tant Selection 8 8 2 1 a mise en place de l'électrifi and livelihoods activities cation hors grille MG-MRHP-28765-CS-INDV// Component 4. Project mana Individual Consul 2018-11-1 2018-12-1 2019-01-1 2019-07-1 MG-PM-188 / Responsable P IDA / 59870 Post Open 7,800.00 0.00 Canceled 2018-10-01 gement and coordination tant Selection 9 0 4 3 assation de marché MG-MRHP-28769-CS-INDV// MG-PM-191 / Mission de cou Component 4. Project mana Individual Consul 2018-04-1 2018-05-1 2018-06-1 2018-12-1 IDA / 59870 Post Open 1,000.00 0.00 Canceled 2018-03-01 verture des autres activités gement and coordination tant Selection 9 0 4 1 de communication MG-MRHP-28770-CS-INDV// Component 4. Project mana Individual Consul 2018-04-1 2018-05-0 2018-06-1 2018-12-1 MG-PM-192 / Réalisation du IDA / 59870 Post Open 8,000.00 0.00 Canceled 2018-02-28 gement and coordination tant Selection 8 9 3 0 Bulletin trimestriel SWIOFish 2 MG-MRHP-14956-CS-INDV// 70 / PA 70: Etude sur l'adapt Component 2. Strengthenin Individual Consul 2018-02-1 2018-02-2 2018-04-0 2018-10-0 ation des missions et attribu IDA / Q9790 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2017-11-30 tant Selection 0 4 7 4 tions du MRHP par rapport a eries management ux défis du développement r ural MG-MRHP-14959-CS-INDV// Component 3. Strengthenin PA71 / PA 71: Mise en place g capacities for engaging in Individual Consul 2018-07-2 2018-08-0 2018-09-2 2019-03-1 IDA / Q9790 Post Open 1,000.00 0.00 Canceled 2018-05-31 d'une règlementation de bas alternative fishing practices tant Selection 6 9 0 9 e concernant la sécurité en and livelihoods activities mer de la petite pêche MG-MRHP-14955-CS-INDV// Component 2. Strengthenin 69 / PA 69: Elaboration du S Individual Consul 2018-06-2 2018-07-1 2018-08-1 2019-02-1 IDA / Q9790 g capacities for priority fish Post Open 8,000.00 0.00 Canceled 2018-05-15 chéma d'aménagement aqu tant Selection 6 0 4 0 eries management acole national (algues, crab es, holothurie etc) MG-MRHP-14954-CS-INDV// PA68 / PA 68: Conception d' Component 2. Strengthenin Individual Consul 2018-02-0 2018-02-1 2018-03-2 2018-09-2 un système de collecte de d IDA / Q9790 g capacities for priority fish Post Open 10,000.00 0.00 Canceled 2017-12-30 tant Selection 3 7 4 0 onnées pour les pêcheries tr eries management aditionnelles, y compris une stratégie MG-MRHP-14497-CS-INDV// PA-42 / PA 42: Etude sur les Component 2. Strengthenin Individual Consul 2017-07-0 2017-07-1 2017-08-1 2018-02-1 FFOM et mesures nécessaire IDA / Q9790 g capacities for priority fish Post Open 25,000.00 0.00 Canceled 2017-05-29 tant Selection 3 0 4 0 s pour le développement de eries management la pêche nationale et attirer la flotte étrangère MG-MRHP-14950-CS-INDV// PA64 / PA 64: Etude sur les Component 2. Strengthenin besoins en formation, en Eq Individual Consul 2017-07-0 2017-07-1 2017-08-0 2018-02-0 IDA / Q9790 g capacities for priority fish Prior Open 20,000.00 0.00 Canceled 2017-05-29 uipements et immobiliers de tant Selection 3 0 7 3 eries management l'Administration (Central et DRRHP) Plans de formation et d'investissement MG-MRHP-14948-CS-INDV// Component 2. Strengthenin PA21 / PA 21: Etude de faisa Individual Consul 2018-06-2 2018-07-0 2018-07-3 2019-01-2 IDA / Q9790 g capacities for priority fish Post Open 20,000.00 0.00 Canceled 2018-05-15 bilité du projet d'Ecole Natio tant Selection 6 3 1 7 eries management nale Halieutique, les besoins en formation Page 10 MG-MRHP-28167-CS-QCBS// MG-PM-15 / Développement Component 2. Strengthenin et mise en œuvre du systèm Individual Consul 2018-03-1 2018-04-0 2018-05-1 2018-11-1 IDA / D1720 g capacities for priority fish Post Open 5,000.00 0.00 Canceled 2017-12-15 e de collecte de données po tant Selection 2 2 4 0 eries management ur les pêcheries traditionnell es, y compris une stratégie d'échantillonnage approprié e MG-MRHP-28339-CS-CQS// Component 4. Project mana Individual Consul 2017-08-2 2017-12-0 2018-01-2 2017-12-2 2018-01-2 2018-02-0 2018-02-1 2018-07-3 MG-PM-37 / Recrutement d'u IDA / 59870 Post Open 4,000.00 23,250.53 Signed 2017-10-19 gement and coordination tant Selection 4 7 3 8 3 1 7 1 n Chef Comptable MG-MRHP-28711-CS-QCBS// MG-PM-153 / Étude de prosp Component 2. Strengthenin Individual Consul 2018-12-0 2018-12-2 2019-02-0 2019-08-0 ection des lieux d'implantati IDA / 59870 g capacities for priority fish Post Open 1,500.00 0.00 Canceled 2018-10-01 tant Selection 5 6 6 5 on des deux antennes regio eries management nales de l'USTA (Majunga, T amatave) MG-MRHP-28712-CS-QCBS// Component 2. Strengthenin Individual Consul 2019-02-1 2019-03-0 2019-04-1 2019-10-0 MG-PM-154 / Étude de mise IDA / 59870 g capacities for priority fish Post Open 1,500.00 0.00 Canceled 2018-12-03 tant Selection 3 6 0 7 en place des antennes régio eries management nales MG-MRHP-33990-CS-INDV// Component 2. Strengthenin Individual Consul 2018-01-2 2018-02-1 2018-03-2 2018-09-2 MG-PM 68 / Assistance tech IDA / D1720 g capacities for priority fish Post Open 26,000.00 0.00 Canceled 2017-11-02 tant Selection 1 1 5 1 nique pour le suivi des trava eries management ux de carénage MG-MRHP-86203-CS-INDV// Component 2. Strengthenin Individual Consul 2019-01-3 2019-03-0 2019-04-2 2019-07-0 2020-01-0 PA13 / Mise à jour de la Stra IDA / 59870 g capacities for priority fish Post Open 30,000.00 0.00 Canceled 2018-11-22 tant Selection 1 7 1 5 1 tégie Nationale de l'Aquacul eries management ture MG-MRHP-86204-CS-INDV / Component 2. Strengthenin Recrutement d'un consultan Individual Consul 2018-12-1 2019-03-1 2019-02-2 2019-04-1 2019-02-2 2019-06-2 2018-12-2 2019-12-2 2020-04-0 IDA / D1720 g capacities for priority fish Post Open 55,000.00 39,810.58 Completed 2018-11-26 t pour convertir OPENARTFIS tant Selection 7 1 6 0 6 4 6 1 2 eries management H dans une base de donnée s basée sur le We MG-MRHP-86205-CS-INDV// Component 2. Strengthenin MG-PM 51/18 / Assistance te Individual Consul 2018-08-1 2019-03-0 2018-10-2 2019-04-0 2018-11-0 2019-06-2 2018-11-1 2019-12-1 IDA / D1720 g capacities for priority fish Post Open 26,000.00 24,252.91 Signed 2018-11-22 chnique pour le suivi des tra tant Selection 0 7 3 6 8 0 3 7 eries management vaux de carénage de l'Atsan tsa MG-MRHP-105669-CS-INDV Component 3. Strengthenin / Recrutement d'agence de g capacities for engaging in Individual Consul 2019-03-2 2019-04-2 2019-04-3 2019-05-2 2019-11-2 communication pour la conc IDA / 59870 Post Open 5,625.00 0.00 Canceled 2019-03-12 alternative fishing practices tant Selection 0 3 0 8 4 eption et production des sup and livelihoods activities ports de communications rel atifs au MDGP MG-MRHP-119243-CS-INDV / Assistance technique pour Component 2. Strengthenin Individual Consul 2019-08-0 2019-11-2 2020-01-1 2020-03-2 2020-09-2 la coordination génerale des IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2019-08-15 tant Selection 9 8 2 7 3 activités durant l'élaboration eries management du PAP Atsimo Atsinanana MG-MRHP-119244-CS-INDV / Etude sur l'analyse de prob Component 2. Strengthenin Individual Consul 2019-08-0 2020-01-2 2020-01-1 2020-03-1 2020-02-2 2020-05-1 2020-03-0 2020-11-0 lématiques liées à la pratiqu IDA / D1720 g capacities for priority fish Post Open 20,000.00 10,846.29 Signed 2019-10-15 tant Selection 2 8 7 3 1 2 9 8 e courante des sennes de pl eries management age dans la Baie d’ Antongil MG-MRHP-119261-CS-INDV Component 3. Strengthenin / Prestataire formateur en c g capacities for engaging in Individual Consul 2019-12-2 2020-01-2 2020-03-2 2020-09-2 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2019-09-15 onstruction et entretien des alternative fishing practices tant Selection 9 8 8 4 engins de pêche and livelihoods activities Component 3. Strengthenin MG-MRHP-119286-CS-INDV g capacities for engaging in Individual Consul 2019-12-1 2020-01-1 2020-03-2 2020-09-2 / Consultance et appui à la c IDA / 59870 Post Open 45,900.00 0.00 Canceled 2019-08-30 alternative fishing practices tant Selection 3 2 7 3 omposante 3 and livelihoods activities MG-MRHP-119288-CS-INDV Component 4. Project mana Individual Consul 2019-08-2 2019-10-2 2019-10-2 2019-11-2 2019-11-1 2020-01-1 2019-11-2 2020-07-1 / Consultance et appui à la IDA / 59870 Post Open 15,300.00 11,155.20 Terminated 2019-07-31 gement and coordination tant Selection 8 9 2 8 2 8 6 6 composante 4 MG-MRHP-119289-CS-CDS / Component 4. Project mana 2019-07-2 2019-08-1 2019-08-0 2019-11-1 2019-08-1 2020-05-1 IDA / 59870 Post Direct Selection Direct 20,400.00 32,788.66 Signed 2019-07-15 Responsable Administratif et gement and coordination 9 9 8 7 6 5 Financier MG-MRHP-119291-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2019-10-1 2019-10-2 2019-11-2 2020-01-1 2020-07-1 IDA / 59870 Post Open 4,200.00 0.00 2019-07-31 / Personnel d'appui : Secréta gement and coordination tant Selection tation 0 9 8 8 6 ire MG-MRHP-28341-CS-CQS// Component 4. Project mana Individual Consul 2017-08-2 2019-09-0 2018-01-2 2019-09-2 2018-01-2 2019-10-2 2018-03-0 2020-04-2 MG-PM-38 / Recrutement de IDA / 59870 Post Open 24,000.00 47,399.30 Signed 2019-07-15 gement and coordination tant Selection 4 2 2 3 3 8 6 5 deux (02) Comptables MG-MRHP-119292-CS-INDV Component 4. Project mana Individual Consul Pending Implem 2019-07-2 2019-08-1 2019-09-1 2020-03-1 / Personnel d'appui (Femme IDA / 59870 Post Limited 1,320.00 0.00 2019-07-15 gement and coordination tant Selection entation 0 0 4 2 de ménage et gardien) MG-MRHP-119293-CS-INDV Component 4. Project mana Individual Consul Pending Implem 2019-07-2 2019-08-1 2019-09-1 2020-03-1 IDA / 59870 Post Limited 25,200.00 0.00 2019-07-15 / Personnel d'appui : Chauffe gement and coordination tant Selection entation 0 0 4 2 ur MG-MRHP-28673-CS-INDV// Component 2. Strengthenin MG-PM-124 / Amélioration d Individual Consul 2019-09-0 2019-09-2 2019-10-3 2020-04-2 IDA / D1720 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2019-07-01 e la base de données pour l tant Selection 4 5 0 7 eries management es pêcheries industrielles MG-MRHP-23395-CS-INDV// SPM / Frais de personnel du projet : recrutement d'un (0 Component 4. Project mana Individual Consul 2019-08-0 2019-09-1 2019-10-0 2019-10-0 2019-10-1 2019-11-0 2019-10-2 2020-05-0 IDA / 59870 Post Open 88,400.00 14,322.53 Signed 2019-07-26 1) Spécialiste en Passation d gement and coordination tant Selection 1 3 4 4 5 8 1 6 es Marchés en appui à l'équi pe de passation des marché s de l'UGP SWIOFish2. MG-MRHP-119243BIS-CS-IN DV / Recrutement d’un cons ultant individuel pour l’assis Component 2. Strengthenin Individual Consul 2019-08-2 2019-12-1 2019-10-2 2020-01-2 2019-11-2 2020-04-1 2019-12-0 2020-10-0 tance technique de l’Admini IDA / 59870 g capacities for priority fish Post Open 35,000.00 89,509.64 Signed 2019-08-15 tant Selection 2 3 2 7 7 1 2 8 stration en charge de la Pêc eries management he et de l’Aquaculture et de l’UGP du Projet SWIOFish2 d ans le cadre de la Cogestion MG-MRHP-123343-CS-INDV / Développer la base de don nées intégrée des pêches de Component 2. Strengthenin Madagascar et le registre de Individual Consul 2019-08-2 2019-11-0 2019-10-2 2019-11-2 2020-02-1 2020-01-0 2020-02-2 2020-07-0 IDA / D1720 g capacities for priority fish Post Open 50,000.00 38,851.99 Signed 2019-09-02 s pêcheurs et embarcations tant Selection 2 6 2 7 9 8 0 6 eries management dans une base de donnée b asé sur le Web (lignes des é tudes regroupées: 2.1.2.1.1 3 - 2.1.2.1.13.1 - 2.1.2.1.13. 2) MG-MRHP-28764-CS-INDV// Component 4. Project mana Individual Consul 2018-11-1 2018-12-1 2019-01-1 2019-07-1 MG-PM-187 / Assistants coor IDA / 59870 Post Open 62,400.00 0.00 Canceled 2018-10-01 gement and coordination tant Selection 9 0 4 3 dinateurs locaux UGL MG-MRHP-28735-CS-INDV// Component 3. Strengthenin MG-PM-164 / Recensement g capacities for engaging in Individual Consul 2018-05-0 2018-05-2 2018-06-2 2018-12-2 IDA / 59870 Post Open 20,000.00 0.00 Canceled 2018-02-28 et identification des bénéfici alternative fishing practices tant Selection 4 5 9 6 aires chaque année and livelihoods activities MG-MRHP-127608-CS-INDV Component 4. Project mana Individual Consul 2019-12-2 2020-01-2 2020-03-1 2020-09-0 IDA / 59870 Post Open 1,500.00 0.00 Canceled 2019-09-23 / Assistance technique - mai gement and coordination tant Selection 2 1 2 8 ntenance MG-MRHP-28926-CS-INDV// Component 4. Project mana Individual Consul 2018-03-2 2018-04-1 2018-05-1 2018-11-1 MG-PM-17 / Évaluation seme IDA / 59870 Post Open 3,500.00 0.00 Canceled 2018-01-15 gement and coordination tant Selection 1 1 6 2 strielle du projet MG-MRHP-127606-CS-INDV Component 2. Strengthenin Individual Consul 2019-12-1 2020-01-1 2020-03-0 2020-09-0 / Etude diagnostic sur la pêc IDA / 59870 g capacities for priority fish Post Open 20,000.00 0.00 Canceled 2019-09-18 tant Selection 7 6 7 3 herie crevettière à Madagas eries management car MG-MRHP-141087-CS-INDV Component 4. Project mana Individual Consul 2019-10-2 2019-11-2 2019-12-1 2019-11-2 2019-12-1 2019-11-2 2019-12-1 2022-11-2 / Recrutement d’un Chef Co IDA / 59870 Post Open 39,000.00 22,844.93 Signed 2019-10-31 gement and coordination tant Selection 8 1 1 3 3 7 9 6 mptable (CC) au sein de l’U GP MG-MRHP-141088-CS-INDV Component 4. Project mana Individual Consul 2019-10-2 2019-11-2 2019-12-0 2019-11-2 2019-12-1 2019-11-2 2019-12-1 2022-11-2 IDA / 59870 Post Open 24,000.00 17,668.00 Terminated 2019-10-31 / Recrutement d'un comptab gement and coordination tant Selection 8 1 9 3 3 7 8 6 le MG-MRHP-146229-CS-INDV / Recrutement d’un consulta Component 2. Strengthenin nt national pour animer l’ate Individual Consul 2019-10-1 2019-11-2 2019-10-2 2019-12-0 2019-11-1 2019-12-2 2019-12-0 2020-01-0 IDA / 59870 g capacities for priority fish Post Limited 2,800.00 2,496.64 Signed 2019-11-21 lier national relatif à la com tant Selection 4 6 3 1 3 2 5 5 eries management munication de la nouvelle loi portant Code de la Pêche et de l'Aquaculture à Madagas car MG-MRHP-146231-CS-INDV / Recrutement d’un Assistan t Technique pour les constru Component 4. Project mana Individual Consul 2019-12-0 2019-12-1 2020-01-1 2019-12-2 2020-01-2 2019-12-2 2020-01-2 2022-12-2 IDA / 59870 Post Open 25,000.00 25,491.34 Signed 2019-11-21 ctions et réhabilitations d’ in gement and coordination tant Selection 6 5 7 5 4 9 5 8 frastructures de pêche, com munautaires et administrati ves MG-MRHP-119287-CS-CDS / Component 4. Project mana 2019-10-2 2020-02-1 2020-08-0 Contrôle et surveillance de l IDA / 59870 Post Direct Selection Direct 12,000.00 0.00 Canceled 2019-08-30 gement and coordination 9 1 9 a construction de bureau de l'UGP centrale MG-MRHP-149046-CS-CDS / RECRUTEMENT DE CONSULT ANT NATIONAL POUR ASSUR Component 2. Strengthenin 2019-12-2 2020-01-0 2020-05-1 2020-01-2 2020-09-0 2020-02-0 ER LE RENFORCEMENT DE C IDA / 59870 g capacities for priority fish Post Direct Selection Direct 6,290.00 7,739.85 Signed 2019-12-30 6 5 4 0 5 4 APACITES DES BIOLOGISTES eries management DU CDA DANS LE DOMAINE DE L’AQUACULTURE MARINE ET DULCAQUICOLE (2.1.1.3. 03) MG-MRHP-160293-CS-INDV / Recrutement d'un consulta Component 2. Strengthenin Individual Consul 2020-02-2 2020-03-3 2020-06-1 2020-04-0 2020-09-1 2020-04-2 2020-11-2 2020-08-1 nt pour l'élaboration de proc IDA / 59870 g capacities for priority fish Post Open 15,000.00 86,190.00 Signed 2020-02-27 tant Selection 5 0 8 9 5 3 6 1 édure de délivrance des cart eries management es pêcheurs et d'immatricul ation des pirogues MG-MRHP-160452-CS-INDV Component 2. Strengthenin / Recrutement d’un Assistan Individual Consul 2020-03-0 2020-04-1 2020-07-0 2020-05-1 2020-08-1 2020-05-2 2020-08-1 2022-05-2 IDA / D1720 g capacities for priority fish Post Open 85,000.00 15,207.52 Signed 2020-03-10 t technique pour l’ Appui au tant Selection 6 9 1 0 7 4 9 4 eries management renforcement des capacités opérationnelles du CSP MG-MRHP-160443-CS-CDS / Component 2. Strengthenin Recrutement d'Institut de Fo Under Implemen 2020-03-0 2020-03-1 2020-04-1 2020-04-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 3,000.00 0.00 2020-03-09 rmation en technique d'anal tation 1 9 7 7 eries management yse de détection de maladie aquatique MG-MRHP-161605-CS-INDV / Recrutement d'un consulta Component 4. Project mana Individual Consul 2020-03-0 2020-04-2 2020-05-2 2020-05-1 2020-06-2 2020-05-2 2020-06-2 2020-09-2 nt individuel pour la réalisati IDA / 59870 Post Open 100,000.00 34,272.29 Signed 2020-03-13 gement and coordination tant Selection 2 7 6 1 2 5 4 2 on de l’évaluation à mi-parc ours des objectifs du projet SWIOFish2 MG-MRHP-161625-CS-CDS / Component 2. Strengthenin Recrutement d'un BE pour l 2020-03-2 2020-03-2 2020-05-2 2020-05-3 2020-11-0 2021-10-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 12,600.00 22,582.18 Signed 2020-03-16 e contrôle et la surveillance 0 6 6 0 6 7 eries management des travaux du CIRAEP Mar oantsetra Page 11 MG-MRHP-159186-CS-CDS / Component 3. Strengthenin Recrutement d'une Associati g capacities for engaging in 2020-04-1 2020-04-1 2020-05-1 2020-05-0 2020-08-1 2021-10-3 on/ONG pour la promotion d IDA / 59870 Post Direct Selection Direct 90,000.00 90,332.42 Signed 2020-03-31 alternative fishing practices 6 0 5 1 9 1 e l'approche Groupe d'Eparg and livelihoods activities ne Communautaire (GEC) Zo ne BATAN (3.2.5.1.02.1) MG-MRHP-165352-CS-CDS / Component 3. Strengthenin Recrutement d'une Associati g capacities for engaging in 2020-04-1 2020-04-1 2020-09-1 2020-05-0 2021-01-1 2021-11-0 on / ONG pour la promotion IDA / 59870 Post Direct Selection Direct 90,000.00 80,997.01 Signed 2020-04-01 alternative fishing practices 6 1 8 2 4 1 de l'approche Groupe d'Epar and livelihoods activities gne Communautaire (GEC) Zone MELAKY (3.2.5.1.02.1) MG-MRHP-165351-CS-CDS / Component 3. Strengthenin Recrutement d'une Associati g capacities for engaging in 2020-04-1 2020-04-2 2020-07-2 2020-05-1 2020-10-0 2021-11-1 on / ONG pour la promotion IDA / 59870 Post Direct Selection Direct 90,000.00 75,162.11 Signed 2020-04-10 alternative fishing practices 6 0 4 1 9 0 de l'approche Groupe d'Epar and livelihoods activities gne Communautaire (GEC) Zone BA (3.2.5.1.02.1) MG-MRHP-167265-CS-CDS / Acquisition et maintenance Component 4. Project mana 2020-04-0 2020-04-2 2020-04-1 2020-06-2 2020-05-1 2020-12-2 d'un Logiciel Informatisé de IDA / 59870 Post Direct Selection Direct 50,000.00 40,829.47 Signed 2020-04-10 gement and coordination 7 0 6 4 2 1 Gestion Administrative, Com ptable, Budgétaire et Financ ière pour le Projet SWIOFish 2 MG-MRHP-119242-CS-INDV Component 2. Strengthenin / Elaboration du plan de dév Individual Consul 2019-11-1 2019-12-1 2020-02-1 2020-08-1 IDA / 59870 g capacities for priority fish Post Open 20,000.00 0.00 Canceled 2019-08-01 eloppement des 3 filières aq tant Selection 4 4 2 0 eries management uaculture (algue,holothurie, crabe) MG-MRHP-149438-CS-INDV / Recrutement d'un Consulta nt individuel pour la facilitati Component 2. Strengthenin on des ateliers de sensibilisa Individual Consul 2020-04-1 2020-06-2 2020-05-2 2020-07-0 2020-09-0 2020-07-1 2020-10-0 2020-09-1 IDA / 59870 g capacities for priority fish Post Limited 3,000.00 8,439.82 Signed 2020-06-19 tion régionale au niveau des tant Selection 6 5 7 2 8 6 8 4 eries management 13 régions côtières, relatifs à la communication de la no uvelle loi portant Code de la Pêche et de l'Aquaculture à Madagascar MG-MRHP-119286-CS-INDV- 2 / Recrutement d’un Consul Component 3. Strengthenin tant individuel pour l’appui t g capacities for engaging in Individual Consul 2020-04-2 2020-06-0 2020-07-2 2020-06-2 2020-08-1 2020-07-0 2020-08-2 2021-07-0 TF / A4588 Post Open 85,000.00 26,683.05 Signed 2020-04-24 echnique à la mise en œuvr alternative fishing practices tant Selection 1 6 4 0 4 4 7 4 e de l’électrification hors gril and livelihoods activities le dans le cadre du projet S WIOFish2 MG-MRHP-28756-CS-INDV// Component 3. Strengthenin MG-PM-178 / Élaboration du g capacities for engaging in Individual Consul 2019-11-0 2019-12-1 2020-01-2 2020-03-2 2020-09-2 IDA / 59870 Post Open 300,000.00 0.00 Canceled 2019-08-30 plan stratégique de dévelop alternative fishing practices tant Selection 5 3 7 7 3 pement local (PCD et PLD) and livelihoods activities MG-MRHP-170896-CS-INDV / Recrutement d'un Consulta Component 2. Strengthenin Individual Consul Under Implemen 2020-05-2 2020-07-0 2020-07-2 2020-09-0 2021-09-0 nt pour la mise en place de IDA / D1720 g capacities for priority fish Post Open 30,000.00 0.00 2020-05-04 tant Selection tation 4 8 9 9 9 Base Des Données et la con eries management ception d'un logiciel de colle cte de données_OEPA MG-MRHP-119288BIS-CS-IN DV / Recrutement d'un resp Component 4. Project mana Individual Consul 2019-08-2 2020-03-2 2020-03-2 2020-04-1 2020-04-1 2020-04-2 2020-04-1 2021-04-2 IDA / 59870 Post 15,000.00 13,822.38 Signed 2019-08-19 onsable en communication gement and coordination tant Selection 8 0 0 7 7 0 8 0 2 de l'UGP SWIOfish2 MG-MRHP-170881-CS-INDV Component 2. Strengthenin / Recrutement d’un consulta Individual Consul 2020-05-1 2020-06-2 2020-09-1 2020-07-1 2020-10-0 2020-08-1 2020-10-2 2021-08-1 IDA / 59870 g capacities for priority fish Post Open 15,000.00 13,828.32 Signed 2020-05-04 nt individuel spécialiste de l tant Selection 3 2 6 3 9 7 0 7 eries management a petite pêche au sein de l’U GP du Projet SWIOFish2 MG-MRHP-170887-CS-INDV / Recrutement d’un consulta Component 3. Strengthenin nt individuel spécialiste du d g capacities for engaging in Individual Consul Under Implemen 2020-05-1 2020-07-0 2020-07-2 2020-08-2 2021-08-2 IDA / 59870 Post Open 15,000.00 0.00 2020-05-15 éveloppement des chaines d alternative fishing practices tant Selection tation 4 3 4 8 8 e valeur de la petite pêche a and livelihoods activities u sein de l’UGP du Projet SW IOFish2 MG-MRHP-173507-CS-INDV Component 2. Strengthenin / Recrutement de consultant Individual Consul Under Implemen 2020-05-1 2020-06-2 2020-06-2 2020-07-1 2020-07-2 IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 2020-05-20 Individuel pour la formation tant Selection tation 4 2 9 9 9 eries management en technique d'approche et animation rurale MG-MRHP-173508-CS-INDV Component 2. Strengthenin / Recrutement de consultant Individual Consul Under Implemen 2020-05-1 2020-07-1 2020-08-0 2020-09-0 2020-09-1 IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 2020-05-20 Individuel pour formation en tant Selection tation 4 7 7 5 5 eries management technique de négociation et leadership MG-MRHP-119245 BIS1-CS- CDS / Recrutement d'un BE Component 2. Strengthenin pour le Contrôle et surveilla 2019-07-2 2019-08-1 2019-08-1 2019-11-1 2020-03-1 2021-04-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 56,000.00 51,918.79 Signed 2019-07-24 nce des travaux de construc 4 4 4 2 8 0 eries management tion de l'UGP SWIOFish2 Nan isana, DRRHP Analanjirojo et ASH Morondava MG-MRHP-119245-CS-CDS / Component 2. Strengthenin Contrôle et surveillance des 2019-07-2 2019-10-1 2019-08-1 2020-01-1 2020-07-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 84,000.00 0.00 Canceled 2019-08-01 travaux de constructions po 4 5 4 3 1 eries management ur les six (06) DRRHP et h uit (08) CIRRHP MG-MRHP-172004-CS-INDV / Recrutement d’un consulta Component 2. Strengthenin nt individuel pour l’appui tec Individual Consul 2020-05-2 2020-07-1 2020-08-0 2020-08-0 2020-09-0 2020-09-0 2020-10-0 2023-09-0 IDA / 59870 g capacities for priority fish Post Open 50,000.00 13,512.58 Terminated 2020-05-26 hnique à la mise en œuvre d tant Selection 0 4 7 4 1 8 9 8 eries management es activités d’aquaculture d ans le cadre du projet SWIO Fish2 MG-MRHP-28341 BIS 2-CS-I Component 4. Project mana Individual Consul 2019-02-1 2019-03-1 2019-03-0 2019-03-2 2019-03-0 2019-03-3 2019-03-1 2020-03-2 NDV / Recrutement d'un Co IDA / 59870 Post Open 12,000.00 9,065.16 Terminated 2019-02-18 gement and coordination tant Selection 8 2 6 2 7 0 2 9 mptable remplaçant en 201 9 MG-MRHP-179481-CS-INDV Component 3. Strengthenin / Recrutement d’un formate g capacities for engaging in Individual Consul Under Implemen 2020-06-1 2020-07-3 2020-08-2 2020-09-0 2020-11-3 IDA / 59870 Post Open 50,000.00 0.00 2020-06-18 ur sur la technique de pêche alternative fishing practices tant Selection tation 9 0 0 1 0 moderne and livelihoods activities MG-MRHP-179501-CS-INDV Component 2. Strengthenin / RECRUTEMENT D’UN CONS Individual Consul Under Implemen 2020-07-0 2020-08-0 2020-08-2 2020-09-1 2021-03-1 IDA / 59870 g capacities for priority fish Post Open 10,000.00 0.00 2020-06-19 ULTANT SPÉCIALISTE EN SYS tant Selection tation 7 7 8 1 0 eries management TEME D’INFORMATION GEO GRAPHIQUE (SIG) MG-MRHP-179518-CS-CDS / Recrutement d'une firme po Component 2. Strengthenin 2020-06-2 2020-07-0 2020-07-2 2020-07-2 2020-10-0 2020-08-0 2020-10-2 ur assurer le renforcement d IDA / 59870 g capacities for priority fish Post Direct Selection Direct 10,000.00 23,550.98 Completed 2020-06-22 4 9 2 4 2 8 4 es capacités des agents de l eries management a DGPA à l'IHSM en algocult ure et holothuriculture MG-MRHP-182966-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul Under Implemen 2020-07-2 2020-09-0 2020-09-2 2020-10-3 2023-10-3 IDA / 59870 g capacities for priority fish Post Open 23,400.00 0.00 2020-07-17 nt INDIVIDUEL pour Respons tant Selection tation 2 4 5 0 0 eries management able Local de la composante 2 à Nosy be MG-MRHP-182961-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul 2020-07-2 2020-09-0 2020-10-0 2020-09-2 2020-10-1 2020-10-3 2020-10-2 2023-10-3 IDA / 59870 g capacities for priority fish Post Open 23,400.00 6,449.18 Signed 2020-07-17 nt individuel pour Responsa tant Selection 2 4 7 5 3 0 0 0 eries management ble Local de la composante 2 à Maintirano MG-MRHP-105671-CS-INDV Component 3. Strengthenin / Mise en place, Formation, g capacities for engaging in Individual Consul 2019-03-2 2019-05-1 2019-05-2 2019-07-0 2019-12-2 IDA / 59870 Post Open 60,000.00 0.00 Canceled 2019-03-12 Maintenance et Entretien du alternative fishing practices tant Selection 0 4 8 2 9 système en ligne ou platefor and livelihoods activities me MG-MRHP-119245 BIS2-CS- CDS / Recrutement d'un BE Component 2. Strengthenin 2019-07-2 2020-10-2 2019-08-1 2021-01-2 2021-05-1 2022-06-2 pour le Contrôle et surveilla IDA / 59870 g capacities for priority fish Post Direct Selection Direct 34,500.00 13,383.27 Signed 2020-10-05 4 6 4 4 5 3 nce des travaux de construc eries management tion des CIRRHP Ambanja, A mbilobe, MG-MRHP-119248-CS-INDV Component 2. Strengthenin Individual Consul 2019-11-0 2019-10-1 2019-11-1 2020-01-2 2020-07-2 / Consultance et appui à la IDA / 59870 g capacities for priority fish Post Open 30,600.00 0.00 Canceled 2019-07-01 tant Selection 5 4 3 7 5 composante 2 eries management MG-MRHP-119241-CS-INDV / Assistance juridique pour a Component 2. Strengthenin Individual Consul 2019-08-1 2019-10-3 2019-11-2 2020-01-2 2020-07-2 ppuyer à l’homologation du IDA / 59870 g capacities for priority fish Post Open 10,000.00 0.00 Canceled 2019-08-01 tant Selection 9 0 9 8 6 Dinabe régissant la gestion l eries management ocale des pêcheries au nive au de la Baie d'Antongil MG-MRHP-148888-CS-INDV / Recrutement d’un consulta nt national pour assurer le r Component 2. Strengthenin enforcement de capacité de Individual Consul Pending Implem 2020-09-3 2020-10-0 2020-10-1 2020-10-3 IDA / 59870 g capacities for priority fish Post Limited 1,000.00 0.00 2020-09-24 s agents de l’administration tant Selection entation 0 7 7 1 eries management des pêches et des responsa bles des textes administratif s en technique d'approche e t d’animation rurale (2.1.1.1 .04) MG-MRHP-189680-CS-INDV / Recrutement d'un (e) secré Component 4. Project mana Individual Consul 2020-10-0 2020-10-1 2020-10-2 2023-10-2 IDA / 59870 Post Open 15,000.00 0.00 Canceled 2020-09-15 taire en passation des marc gement and coordination tant Selection 9 9 3 3 hés du projet SWIOFish2 MG-MRHP-160194-CS-INDV / Recrutement d'un assistan Component 4. Project mana Individual Consul 2020-02-2 2020-03-2 2020-04-0 2020-04-0 2023-04-0 IDA / 59870 Post Open 20,000.00 0.00 Canceled 2020-02-27 t en passation des marchés gement and coordination tant Selection 5 2 1 5 5 de l'UGP-SWIOFish2 MG-MRHP-197771-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2020-10-2 2020-11-1 2021-01-3 2020-11-2 2021-02-0 2020-12-0 2021-02-2 2023-09-0 IDA / 59870 Post Open 21,000.00 6,389.81 Signed 2020-10-13 nt individuel Assistant en Pa gement and coordination tant Selection 0 6 0 2 1 3 7 3 ssation des Marchés de l'UG P SWIOFish2 MG-MRHP-197821-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2020-10-1 2020-10-2 2021-05-0 2020-11-0 2021-05-0 2020-11-2 2021-05-1 2023-09-2 IDA / 59870 Post Limited 11,900.00 3,071.04 Signed 2020-10-13 nt individuel Secrétaire de la gement and coordination tant Selection 3 3 5 6 7 2 1 1 Passation des Marchés de l' UGP SWIOFish2 MG-MRHP-197817-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2020-11-1 2020-11-1 2021-03-0 2020-11-2 2021-03-0 2020-12-0 2021-03-0 2023-09-0 IDA / 59870 Post Open 21,000.00 11,362.85 Signed 2020-10-13 nt individuel Gestionnaire de gement and coordination tant Selection 6 6 2 2 4 5 9 5 contrats de l'UGP SWIOFish2 MG-MRHP-203594-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul Under Implemen 2020-11-2 2021-01-0 2021-01-2 2021-02-0 2024-02-0 IDA / 59870 g capacities for priority fish Post Open 23,400.00 0.00 2020-11-20 nt individuel pour Responsa tant Selection tation 1 1 2 5 5 eries management ble Local de la composante 2 à Mananara Nord MG-MRHP-203595-CS-INDV Component 2. Strengthenin / Recrutement d'un consulta Individual Consul Under Implemen 2020-11-2 2021-01-0 2021-01-2 2021-02-0 2024-02-0 IDA / 59870 g capacities for priority fish Post Open 23,400.00 0.00 2020-11-20 nt individuel pour Responsa tant Selection tation 1 1 2 5 5 eries management ble Local de la composante 2 à Maroantsetra MG-MRHP-203596-CS-INDV Component 3. Strengthenin / Recrutement d'un consulta g capacities for engaging in Individual Consul 2020-11-2 2020-11-2 2021-01-1 2020-12-1 2021-01-1 2021-01-2 2021-01-2 2023-09-2 IDA / 59870 Post Limited 23,400.00 6,449.18 Signed 2020-11-20 nt individuel pour Responsa alternative fishing practices tant Selection 1 5 4 6 5 0 1 3 ble Local de la Composante and livelihoods activities 3 à Maintirano Page 12 MG-MRHP-203597-CS-INDV Component 3. Strengthenin / Recrutement des consultan g capacities for engaging in Individual Consul Under Implemen 2020-11-2 2021-01-0 2021-01-2 2021-02-1 2023-09-2 ts individuels pour Responsa IDA / 59870 Post Open 46,800.00 0.00 2020-11-20 alternative fishing practices tant Selection tation 1 1 2 2 3 ble Local de la Composante and livelihoods activities 3 à Maroantsetra et Nosy Be MG-MRHP-28348-CS-INDV/ Component 4. Project mana Individual Consul Pending Implem 2021-08-0 2021-08-2 2021-10-0 2022-04-0 MG-PM-44 / Réalisation du B IDA / 59870 Post Open 8,000.00 0.00 2021-06-03 gement and coordination tant Selection entation 7 8 9 7 ulletin trimestriel SWIOFish2 MG-MRHP-223821-CS-CDS / Recrutement d'un BE pour ET, PGES, C&S de travaux d e construction de la clôture Component 2. Strengthenin 2021-03-1 2021-03-2 2021-03-2 2021-05-3 2021-09-2 2021-07-2 de l’enceinte et mise en pla IDA / 59870 g capacities for priority fish Post Direct Selection Direct 40,000.00 15,938.40 Signed 2021-03-16 4 6 6 0 8 9 ce d’un point d’eau autono eries management me du bureau de la CirAEP Maroantsetra, construction du Hangar et bureau de la brigade CSP Analanjirofo MG-MRHP-223828-CS-INDV / Recrutement d’un troisièm Component 4. Project mana Individual Consul Under Implemen 2021-03-2 2021-04-2 2021-04-2 2021-04-2 2023-09-2 IDA / 59870 Post Open 15,600.00 0.00 2021-03-30 e Comptable pour l’Unité de gement and coordination tant Selection tation 6 0 2 6 9 Gestion du Projet SWIOFish2 MG-MRHP-227230-CS-INDV Component 4. Project mana Individual Consul 2021-04-0 2021-05-2 2021-09-1 2021-06-1 2021-11-1 2021-07-2 2021-11-2 2021-10-1 / Recrutement d'un SIGiste a IDA / 59870 Post Open 15,000.00 15,563.24 Signed 2021-04-07 gement and coordination tant Selection 9 6 0 6 9 1 7 9 u niveau de l'UGP SWIOFish 2 MG-MRHP-229415-CS-CDS / Recrutement d'un responsa Component 4. Project mana Under Implemen 2021-05-2 2021-04-2 2021-05-1 2023-09-2 IDA / 59870 Post Direct Selection 52,600.00 0.00 2021-04-22 ble en passation des marché gement and coordination tation 3 8 5 9 s du projet SWIOFish2 MG-MRHP-229418-CS-INDV / Recrutement d'un Consulta Component 4. Project mana Individual Consul 2021-10-2 2021-04-2 2022-03-0 2021-05-0 2022-03-1 2021-05-1 2022-03-2 2023-09-2 IDA / 59870 Post Limited 52,000.00 7,736.16 Signed 2021-04-22 nt individuel Gestionnaire de gement and coordination tant Selection 0 9 8 6 1 5 3 9 contrats de l'UGP SWIOFish2 (2021) MG-MRHP-161616-CS-CDS / Recrutement d'un BE pour l Component 2. Strengthenin 2020-03-2 2020-03-2 2020-05-2 2020-05-2 2021-10-2 e contrôle et surveillance de IDA / 59870 g capacities for priority fish Post Direct Selection Direct 41,500.00 0.00 Canceled 2020-03-12 0 2 6 6 3 s travaux des DRAEP à Andr eries management oy, Anosy et Atsimo Atsinan ana MG-MRHP-161621-CS-CDS / Recrutement d'un BE pour l Component 2. Strengthenin 2020-03-2 2020-03-2 2020-05-2 2020-05-2 2021-10-2 e contrôle et la surveillance IDA / 59870 g capacities for priority fish Post Direct Selection Direct 51,000.00 0.00 Canceled 2020-03-13 0 3 6 7 4 des travaux du DRAEP et CI eries management RAEP à Maintirano, des CIRA EP à Besalampy et à Masoar ivo MG-MRHP-231606-CS-INDV / Recrutement consultant in Component 2. Strengthenin Individual Consul 2021-05-0 2021-07-0 2021-06-2 2021-07-2 2021-10-0 2021-09-0 2021-11-0 2022-09-0 dividuel pour développemen IDA / D1720 g capacities for priority fish Post Open 15,000.00 47,116.80 Signed 2021-05-20 tant Selection 7 8 3 9 8 2 5 2 t de Base des Donnés du Ce eries management ntre de Surveillance Pêche ( CSP) MG-MRHP-236864-CS-INDV / Recrutement d’un Consulta nt individuel pour effectuer Component 2. Strengthenin Individual Consul Under Implemen 2021-08-0 2021-08-1 2021-09-0 2021-10-1 2021-12-1 la mise à jour du Plan d’Acti TF / A4588 g capacities for priority fish Post Open 100,000.00 0.00 2021-06-30 tant Selection tation 6 8 8 3 2 on National de lutte contre l eries management a pêche Illicite Non Déclarée et Non Réglementée (PAN IN N) de Madagascar MG-MRHP-119285-CS-CDS / Component 3. Strengthenin Contrôles et surveillances d g capacities for engaging in 2022-01-2 2022-05-1 2022-11-1 IDA / 59870 Post Direct Selection Direct 60,000.00 0.00 Canceled 2021-11-30 es infrastructures d'électrific alternative fishing practices 9 4 0 ation hors grille dans les co and livelihoods activities mmunautés pilotes MG-MRHP-119281-CS-CDS / Component 2. Strengthenin Contrôle et surveillance des 2021-06-2 2021-10-2 2022-04-2 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 60,000.00 0.00 Canceled 2021-04-30 constructions de marchés co 9 7 5 eries management uverts aux produits halieutiq ues Component 3. Strengthenin MG-MRHP-252968-CS-INDV g capacities for engaging in Individual Consul 2021-10-1 2021-11-3 2021-10-2 2021-12-2 2021-11-0 2022-01-2 2021-11-1 2023-01-2 / Recrutement d’un Assistan IDA / 59870 Post Open 15,000.00 6,796.71 Signed 2021-10-11 alternative fishing practices tant Selection 2 0 2 1 3 5 7 5 t Technique Foncier and livelihoods activities MG-MRHP-256410-CS-INDV Component 4. Project mana Individual Consul 2021-12-2 2021-11-0 2022-02-2 2021-11-1 2022-03-0 2021-11-2 2022-03-0 2023-09-2 / Recrutement d'un comptab IDA / 59870 Post Open 24,000.00 8,042.13 Signed 2021-10-18 gement and coordination tant Selection 0 8 5 5 1 4 8 9 le 2021 (Remplacement co mptable 2) MG-MRHP-285250-CS-CDS / Component 2. Strengthenin Analyse des problématiques Under Implemen 2022-04-1 2022-04-1 2022-06-0 2022-06-1 2022-12-1 IDA / 59870 g capacities for priority fish Post Direct Selection Direct 20,000.00 0.00 2022-04-05 liées à l’utilisation des senn tation 5 5 2 9 6 eries management es de plage dans la baie d’A ntongil MG-MRHP-289654-CS-INDV / Responsable Local de la Co Component 3. Strengthenin mposante 3 (RLC3) « Appui g capacities for engaging in Individual Consul Pending Implem 2022-05-3 2022-06-2 2022-07-1 2025-02-1 à l’adhésion des populations IDA / 59870 Post Open 22,000.00 0.00 2022-04-18 alternative fishing practices tant Selection entation 0 0 1 8 cibles à la gestion durable d and livelihoods activities es pêcheries cibles/Promotio n des activités alternatives » dans les Districts de Maro antsetra MG-MRHP-252785-CS-INDV / Recrutement d'un Respons Component 4. Project mana Individual Consul 2021-09-1 2021-10-1 2021-10-2 2021-11-0 2023-09-3 IDA / 59870 Post Open 32,400.00 0.00 Canceled 2021-09-23 able Administratif et Financi gement and coordination tant Selection 5 3 3 6 0 er pour le Projet SWIOFish2 ( 2021) MG-MRHP-119282-CS-CDS / Contrôle et surveillance des constructions de hangars av Component 3. Strengthenin ec des materiaux locaux po g capacities for engaging in 2022-01-1 2022-05-1 2022-11-0 ur entretenir les moteurs, le IDA / 59870 Post Direct Selection Direct 48,000.00 0.00 Canceled 2021-11-12 alternative fishing practices 1 1 7 s embarcations et des engin and livelihoods activities s de pêche autorisés et d'un e base de réunion, sensibilis ation et de structuration des utilisateurs petites infrastru MG-MRHP-119283-CS-CDS / Component 3. Strengthenin Contrôles et surveillances d g capacities for engaging in 2022-01-1 2022-04-2 2022-10-2 IDA / 59870 Post Direct Selection Direct 120,000.00 0.00 Canceled 2021-11-12 es constructions d'infrastruc alternative fishing practices 1 6 3 tures communautaires /com and livelihoods activities munales MG-MRHP-119280-CS-CDS / Component 3. Strengthenin Contrôle et surveillance des g capacities for engaging in 2022-01-2 2022-04-2 2022-10-2 IDA / 59870 Post Direct Selection Direct 70,000.00 0.00 Canceled 2021-11-12 constructions de petites déb alternative fishing practices 6 6 3 arcadères type ponton and livelihoods activities MG-MRHP-28325-CS-INDV// Component 3. Strengthenin MG-PM-29 / Élaboration de p g capacities for engaging in Individual Consul 2022-11-1 2022-12-1 2023-02-1 2023-08-1 IDA / 59870 Post Open 30,000.00 0.00 Canceled 2022-09-02 lan de formation des cadres alternative fishing practices tant Selection 7 7 5 4 et élus au niveau local and livelihoods activities MG-MRHP-189660-CS-INDV / Recrutement d'un consulta Component 2. Strengthenin nt individuel pour le renforc Individual Consul Pending Implem 2022-08-0 2022-08-2 2022-09-1 2022-09-2 IDA / 59870 g capacities for priority fish Post Open 4,000.00 0.00 2022-07-01 ement de capacités de l'équ tant Selection entation 6 7 0 2 eries management ipe du service personnel du secteur pêche et aquacultur e en gestion des ressources humaines MG-MRHP-190572-CS-INDV / Recrutement d'un consulta nt individuel pour le renforc Component 2. Strengthenin ement de capacités des age Individual Consul Pending Implem 2022-10-0 2022-10-2 2022-11-1 2022-12-0 IDA / 59870 g capacities for priority fish Post Open 4,000.00 0.00 2022-09-01 nts de l'administration en dé tant Selection entation 7 8 1 8 eries management veloppement d'application web sous HTML, CSS et Java Script et pratique de dévelo ppement en WEBDEV MG-MRHP-292939-CS-INDV / Assistant Technique 2 pour Component 4. Project mana Individual Consul Under Implemen 2022-06-1 2022-06-0 2022-06-1 2022-06-1 2025-06-1 les constructions et réhabilit IDA / 59870 Post Open 25,000.00 0.00 2022-05-09 gement and coordination tant Selection tation 0 2 2 6 5 ations d'infrastructures de p êche, communautaires et ad ministratives MG-MRHP-280897-CS-CDS / Mise à jour des études techn iques relatives à la construct ion du bureau administratif Component 2. Strengthenin Under Implemen 2022-06-0 2022-05-1 2022-06-0 2022-07-2 2023-01-1 de l’UGP SWIOFish2 Nanisan IDA / 59870 g capacities for priority fish Post Direct Selection Direct 26,000.00 0.00 2022-05-06 tation 2 6 8 0 6 a et Contrôle et surveillance eries management de la construction du nouve au bureau logement et de la réhabilitation du bureau log ement existant Farafangana MG-MRHP-297266-CS-INDV / Recrutement d'un consulta Component 2. Strengthenin nt pour la création d'un site Individual Consul 2022-07-1 2022-08-0 2022-09-1 2022-08-2 2022-10-0 2022-09-0 2022-12-0 IDA / 59870 g capacities for priority fish Post Open 15,000.00 0.00 Signed 2022-06-10 web de design et de base de tant Selection 3 5 2 6 7 9 8 eries management données pour la gestion des autorisations et des licences des pêches MG-MRHP-298184-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2022-06-2 2022-08-0 2022-08-2 2022-09-2 2023-09-2 / Recrutement d'un comptab IDA / 59870 Post Open 24,000.00 0.00 2022-06-16 gement and coordination tant Selection tation 4 4 5 9 9 le 3 remplaçant MG-MRHP-298211-CS-CDS / Recrutement d’une organisa tion non-gouvernementale p Component 3. Strengthenin our la promotion des groupe g capacities for engaging in Under Implemen 2022-06-1 2022-06-2 2022-07-1 2023-07-1 s d’épargne communautaire IDA / 59870 Post Direct Selection Direct 90,000.00 0.00 2022-06-17 alternative fishing practices tation 0 7 8 8 (GEC) au niveau des district and livelihoods activities s de Farafangana et Vangain drano - regions Atsimo Atsin anana et des districts d’Amb ovombe, Tsihombe et Beloh a - région And MG-MRHP-296823-CS-INDV / Recrutement d'un Assista Component 4. Project mana Individual Consul 2022-08-1 2023-02-1 IDA / 59870 Post Open 25,000.00 0.00 Canceled nt Technique national au Mi gement and coordination tant Selection 7 3 nistère de la Pêche et de l'E conomie Bleue (MPEB) MG-MRHP-296823-CS-INDV_ 2 / Recrutement d'un Assist Component 4. Project mana Individual Consul 2022-06-2 2022-08-1 2022-07-1 2022-09-0 2022-07-1 2022-10-1 2022-08-0 2023-04-1 IDA / 59870 Post Open 25,000.00 7,215.66 Signed 2022-06-30 ant Technique national au M gement and coordination tant Selection 9 8 3 8 9 3 2 1 inistère de la Pêche et de l'E conomie Bleue (MPEB) MG-MRHP-303933-CS-CDS / Recrutement d'un formateur Component 3. Strengthenin relatif au renforcement de c g capacities for engaging in Direct - Internatio Under Implemen 2022-07-2 2022-08-0 2022-10-0 2023-08-0 IDA / 59870 Post Direct Selection 500,000.00 0.00 2022-07-22 apacité sur les techniques d alternative fishing practices nal tation 1 1 5 1 e fumage des produits halie and livelihoods activities utiques et construction de fu moirs FTT MG-MRHP-231604-CS-INDV / Recrutement d’un Consulta Component 2. Strengthenin nt Individuel pour effectuer Individual Consul 2022-07-2 2022-09-0 2022-10-1 2022-09-3 2022-11-1 2022-11-0 2023-09-2 TF / A4588 g capacities for priority fish Post Open - National 32,500.00 0.00 Signed 2022-07-22 un Audit des activités de Sur tant Selection 2 9 8 0 0 4 9 eries management veillance, réalisées par le Ce ntre de Surveillance des Pêc hes (CSP) de Madagascar. Page 13 MG-MRHP-304398-CS-CDS / Recrutement d'un consultan Component 2. Strengthenin Under Implemen 2022-07-2 2022-08-0 2022-07-2 2022-10-0 2023-09-2 t pour la modification tablea TF / A4588 g capacities for priority fish Post Direct Selection Direct - National 20,000.00 0.00 2022-07-22 tation 1 1 5 5 9 u de bord et création de mo eries management dules dans le SIP et OPENAR TFISH MG-MRHP-308538-CS-CDS / Renouvellement des contrat Component 3. Strengthenin s de prestation des organisa g capacities for engaging in 2022-09-2 2022-08-2 2022-09-2 2022-11-0 2023-05-0 tions non-gouvernementales IDA / 59870 Post Direct Selection Direct - National 180,000.00 0.00 Signed 2022-08-19 alternative fishing practices 7 9 9 2 1 pour la promotion des group and livelihoods activities es d’épargne communautair e (GEC) au niveau des ZUP MELAKY et BAIE d’ANTONGIL MG-MRHP-308722-CS-CDS / Renouvellement des contrat Component 3. Strengthenin s de prestation des organisa g capacities for engaging in Under Implemen 2022-09-2 2022-08-2 2022-09-2 2022-10-3 2023-04-2 IDA / 59870 Post Direct Selection Direct - National 90,000.00 0.00 2022-08-17 tions non-gouvernementales alternative fishing practices tation 7 7 9 1 9 pour la promotion des group and livelihoods activities es d’épargne communautair e (GEC) au niveau des ZUP BATAN MG-MRHP-320114-CS-INDV Component 3. Strengthenin / Recrutement d'un Assistan g capacities for engaging in Individual Consul 2022-10-2 2022-11-0 2023-01-1 2022-11-1 2023-01-1 2022-12-1 2023-08-1 IDA / 59870 Post Open - National 20,000.00 0.00 Signed 2022-10-14 t spécialiste sauvegarde env alternative fishing practices tant Selection 4 9 1 0 3 4 6 ironnemental et social and livelihoods activities MG-MRHP-334021-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2023-01-3 2023-02-1 2023-02-2 2023-03-1 2023-09-2 IDA / 59870 Post Open - National 16,000.00 0.00 2023-01-10 / Recrutement d'un 4ème co gement and coordination tant Selection tation 0 2 6 2 9 mptable MG-MRHP-336492-CS-INDV Component 4. Project mana Individual Consul Under Implemen 2023-01-3 2023-02-2 2023-03-1 2023-04-0 2023-09-2 / Recrutement d'un Chef Co IDA / 59870 Post Open - National 8,000.00 0.00 2023-01-30 gement and coordination tant Selection tation 0 5 1 1 9 mptable (CC) au sein de l'U GP 2023 MG-MRHP-336490-CS-CDS / Recrutement d'un Responsa Component 4. Project mana 2023-02-1 2023-02-2 2023-02-2 2023-03-0 2023-10-1 IDA / 59870 Post Direct Selection Direct - National 15,000.00 0.00 Signed 2023-02-15 ble Administratif et Financie gement and coordination 7 0 4 3 5 r au sein de l'UGP 2023 MG-MRHP-299084-CS-INDV / Recrutement d'un Assista Component 4. Project mana Individual Consul 2022-06-2 2022-08-1 2022-09-0 2022-10-1 2023-04-1 nt Technique international IDA / 59870 Post Open 35,000.00 0.00 Canceled 2022-06-30 gement and coordination tant Selection 9 8 8 3 1 au Ministère de la Pêche et de l'Economie Bleue (MPEB) MG-MRHP-5189-CS-INDV / E Component 2. Strengthenin tude sur l'adaptation des mi Individual Consul 2017-04-0 2017-04-2 2017-05-3 2017-11-2 IDA / Q9790 g capacities for priority fish Post Open 15,000.00 0.00 Canceled 2017-02-15 ssions et attributions du MR tant Selection 5 6 1 7 eries management HP par rapport aux défis du développement rural Page 14