Procurement Plan (Textual Part) I. General 1. Project Information Country: Mozambique Project Name: Southern Africa Regional Trade Connectivity Project Project ID: P164847 2. Project Implementation Agency: MTC 3. Date of the Procurement Plan: May 12, 2020 4. Period Covered by this procurement plan: 24 Months II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. Bank’s Standard Procurement Documents: The Bank’s Standard Procurement Documents shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in as set forth in Mozambique Procurement Regulation, the Decree 5/2016 of March 8, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: There should be no mandatory requirements for inclusion of local experts and firms for the consulting assignments. 1 When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. In accordance with paragraph 5.4(c) and 5.5 of the Procurement Regulations, the request for bids/request for proposals/request for quotations document shall require that Bidders/Proposers submitting Bids/Proposals/quotations present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification : Not Applicable VI. Leased Assets: Not Applicable VII. Procurement of Second Hand Goods: Not Applicable VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each. (a) Goods: Not Applicable (b) Works: To be defined Domestic preference is not applicable for National Open Competitive Procurement IX. Hands-on Expanded Implementation Support (HEIS): Not Applicable X. Other Relevant Procurement Information: None XI. Procurement Prior Review Thresholds (US$ millions) Type of Procurement Substantial Risk Works (including turnkey, supply & 10 installation of plant and equipment, and PPP) 2 Goods, information technology and 2 non-consulting services Consultants: firms 1 Consultants: Individuals 0.3 Post Review: All contacts not subject to prior review shall be subject to post review. XII. Thresholds for Procurement Approaches and Method (US$ millions) Works Goods, IT and Non-consulting Shortlist of National Services Consultants Open Open Request Open Open Request Consulti Engineeri Internatio Nationa for Internatio Nation for ng ng & nal l Quotati nal al Quotati Services Construct on on ion ≥ < ≥ < Supervisi ≤ ≤ on 15 15 0.2 5 5 0.1 0.3 0.3 XIII. Summary of the procurement packages: (Planned for the first 18 months after project effectiveness): Category: {Indicate Goods, Civil Works, Non-Consultancy Services or Consultancy Services as appropriate, and replicate this table for all each of the four categories} Sr. Contra Estimate Revie Market Selectio Evalua Procure- Prequa Domesti Expect Expecte No ct d Cost w by Approac n -tion ment li- c ed date d date Descri (US$) Bank h Method Option Process ficatio Preferen of bid/ of p-tion (Prior/ (Open- (RFP, s (Single n ce propos Contrac Post) National RFB, (BAFO, stage- (Yes/ (Yes/No) al t / QCBS Rated single No) openin Signatu Limited etc.) Criteria envelope g re etc.) etc.) etc.) 1 Works 2 Goods and NCS Consul ting Service s 3 Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 4 contract, financially or in any other manner;2 (ii) to be a nominated3 sub- contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. 5 the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 6 PROCUREMENT Southern Africa : Southern Africa Trade and Connectivity Project PLAN General Information Country: Southern Africa 2022-01-11 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164847 GPN Date: 2022-06-07 Project Name: Southern Africa Trade and Connectivity Project Loan / Credit No: IDA / V3370, IDA / D8030 National Road Authority Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - 47A003041/CP/170/2021 / R Works (without pr ehabilitation and Maintenanc Strengthen Transport Infrast Open - Internationa Single Stage - One E equalification) SP 22,440,000.0 Pending Imp 2028-05-1 e of the Trade Connector R68 IDA / V3370 ructure to Improve Market A Prior Request for Bids 0.00 2023-05-03 2023-05-24 2023-07-13 2023-08-14 2023-10-05 l nvelope D - Applying contr 0 lementation 1 6/R687 between Nampula an ccess actor disqualificia d Corane in Nampula and Me tion conta Districts (50.6 km) Request for Bids - 47A003041/CP/171/2021 / R Works (without pr ehabilitation and Maintenanc Strengthen Transport Infrast Open - Internationa Single Stage - One E equalification) SP 13,750,000.0 Pending Imp 2028-05-1 e of the Trade Connector R69 IDA / V3370 ructure to Improve Market A Prior Request for Bids 0.00 2023-05-03 2023-05-24 2023-07-13 2023-08-14 2023-10-05 l nvelope D - Applying contr 0 lementation 1 6 between Rapale and Mecub ccess actor disqualificia uri in Rapale and Mecuburi Di tion stricts (55.0 km) 47A003041/CP/172/2021 / R ehabilitation and Maintenanc National Procure e of the Trade Connectors R1 Strengthen Transport Infrast ment Document - Open - Internationa Single Stage - One E Pending Imp 2028-05-1 156 between Namialo and Ia IDA / V3370 ructure to Improve Market A Post Request for Bids 1 Envelope proce 6,882,000.00 0.00 2023-05-03 2023-05-24 2023-07-13 2023-08-14 2023-10-05 l nvelope lementation 1 pala and R692/R1170 betwee ccess ss (Non Bank-SPD n Namiconha and Iapala in Ri ) baue, Meconta and Muecate Districts (93.1 km) Request for Bids - 47A003041/CP/173/2021 / R Works (without pr ehabilitation and Maintenanc Strengthen Transport Infrast Open - Internationa Single Stage - One E equalification) SP 29,480,000.0 Pending Imp 2028-05-1 e of the Trade Connector N36 IDA / V3370 ructure to Improve Market A Prior Request for Bids 0.00 2023-05-03 2023-05-24 2023-07-13 2023-08-14 2023-10-05 l nvelope D - Applying contr 0 lementation 1 0 between Cuamba and Meta ccess actor disqualificia rica in Cuamba and Metarica tion Districts (67.0 km) Request for Bids - 47A003041/CP/174/2021 / R Works (without pr ehabilitation and Maintenanc Strengthen Transport Infrast Open - Internationa Single Stage - One E equalification) SP 21,500,000.0 Pending Imp 2028-05-1 e of the Trade Connector R72 IDA / V3370 ructure to Improve Market A Prior Request for Bids 0.00 2023-05-03 2023-05-24 2023-07-13 2023-08-14 2023-10-05 l nvelope D - Applying contr 0 lementation 1 0 between Cuamba and Insa ccess actor disqualificia ca in Cuamba and Mecanhela tion s Districts (86.0 km) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 47A003041/CP/175/2021 / C onceptual Design, Supervisio n of the Rehabilitation and M Strengthen Transport Infrast aintenance of the Trade Con Quality And Cost- Open - Internationa Under Implement IDA / V3370 ructure to Improve Market A Prior 2,534,000.00 0.00 2022-01-17 2022-02-21 2022-02-17 2022-02-28 2022-04-18 2023-04-12 2022-06-23 2022-07-25 2022-09-13 2022-11-04 2028-06-05 nector R686/R687 between N Based Selection l ation ccess ampula and Corane and R69 6 between Rapale and Mecub uri in Nampula, Meconta, Rap ale and Mecuburi Districts (1 06 km) 47A003041/CP/176/2021 / C onceptual Design, Supervisio n of the Rehabilitation and M Strengthen Transport Infrast aintenace of the Trade Conn Quality And Cost- Open - Internationa IDA / V3370 ructure to Improve Market A Post 500,000.00 0.00 Canceled 2022-01-17 2022-02-15 2022-02-17 2022-04-18 2022-06-23 2022-07-25 2022-09-13 2022-11-04 2028-06-05 ectors R1156 between Nami Based Selection l ccess alo and Iapala and R692/R11 70 between Namiconha and I apala in Ribaue, Meconta an d Muecate Districts (93 km) 47A003041/CP/177/2021 / C onceptual Design, Supervisio n of the Rehabilitation and M Strengthen Transport Infrast aintenance of the Trade Con Quality And Cost- Open - Internationa Under Implement IDA / V3370 ructure to Improve Market A Prior 3,569,000.00 0.00 2022-01-17 2022-02-21 2022-02-17 2022-02-28 2022-04-18 2023-04-11 2022-06-23 2022-07-25 2022-09-13 2022-11-04 2028-06-05 nectors N360 between Cuam Based Selection l ation ccess ba and Metarica and R720 be tween Cuamba and Insaca in Cuamba, Metarica and Meca nhelas Districts (153 km) 47A003041/CP/16/2022 / Co nceptual Design, Supervision of the Rehabilitation and Mai Strengthen Transport Infrast ntenace of the Trade Connec Quality And Cost- Open - Internationa Under Implement IDA / D8030 ructure to Improve Market A Prior 2,000,000.00 0.00 2022-03-07 2022-03-15 2022-04-07 2022-03-24 2022-06-06 2023-04-11 2022-08-11 2022-09-12 2022-11-01 2022-12-23 2028-07-24 tors R1156 between Namialo Based Selection l ation ccess and Iapala and R692/R1170 between Namiconha and Iap ala in Ribaue, Meconta and M uecate Districts (93 km) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 47A003041/CP/26/2022 / Co Strengthen Transport Infrast nsultancy Services for Social Individual Consult IDA / D8030 ructure to Improve Market A Post Open 250,000.00 0.00 Canceled 2022-04-29 2022-04-28 2022-06-22 2022-07-13 2022-08-17 2027-08-16 Development Specialist for A ant Selection ccess NE, IP, Headquarter 47A003041/CP/78/2022 / Pro Strengthen Regional Coordin Individual Consult Under Implement IDA / D8030 Prior Open - National 17,500.00 0.00 2023-01-31 2023-01-31 2023-03-21 2023-04-11 2023-05-16 2025-05-15 curement Technician ation and Project Implement ant Selection ation ation 47A003041/CP/79/2022 / Pro Strengthen Regional Coordin Individual Consult Under Implement IDA / D8030 Prior Open - National 17,500.00 0.00 2023-01-31 2023-01-31 2023-03-21 2023-04-11 2023-05-16 2025-05-15 curement Technician ation and Project Implement ant Selection ation ation 47A003041/CP/10/2023 / Co Strengthen Transport Infrast nsultancy Services for Social Individual Consult Open - Internationa Under Implement IDA / D8030 ructure to Improve Market A Prior 300,000.00 0.00 2023-01-31 2023-03-07 2023-03-21 2023-04-11 2023-05-16 2027-05-15 Development Specialist for A ant Selection l ation ccess NE, IP, Headquarter 47A003041/CP/30/2022 / Saf Strengthen Transport Infrast Individual Consult IDA / D8030 Prior Open 300,000.00 0.00 Canceled 2022-05-31 2022-05-18 2022-08-02 2022-08-09 2022-08-23 2022-09-27 2025-09-11 ety Road Specialist ructure to Improve Market A ant Selection ccess Page 2 Summarized Procurement Plan I. GENERAL Project information: Borrower: Government of Lesotho Project Name: Smallholder Agricultural Development Project II Project ID No: P 165228 Grant No.: Project Implementing Agency: Ministry of Agriculture and Food Security Bank’s approval Date of the Procurement Plan: Sep, 2019 Date of General Procurement Notice: Period covered by this procurement plan: 18 months II. Goods and Works and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by IDA as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Procurement Methods and Prior Review Goods, Works and Non- Consulting Services Procurement Approaches and Methods (US$ Prior millions) Review Category Open Open Request for (US$ millions) International National Quotation (RfQ) Works ≥ 15 ≥7 <7 ≤ 0.2 Goods, IT, and non- ≥4 ≥1 <1 ≤ 0.1 consulting services 2. Reference to (if any) Project Operational/Procurement Manual: The Procurement Plan also forms part of the Project Implementation Manual approved on Sep 2019. 1 3. Procurement Packages with Methods and Time Schedule Procurement of Goods & Non-consulting Services Summary 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank US$ million (yes/no) (Prior / Post) Summary of the ICB 0.18 1 NIL Nil (Works) Summary of the NCB 4.9 4 NIL Nil NIL (Works) Summary of the ICB 0.2 1 NIL NIL NIL (Goods) Summary of the NCB 3.8 2 NIL NIL NIL (Goods) Summary of the RfQ 0.39 5 NIL Post Nil (Goods & Non- Consulting Services) Summary of the DC NIL NIL NIL NIL (Non-consulting services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in the Procurement Regulations for IPF Borrowers: Thresholds for Consultants Selection Methods and Prior Review Thresholds for Consultants Selection Methods and Prior Review for Consulting Services Category Prior Short List of National Consultants (US$ million) 2 Review Consulting Engineering and (US$ Services Construction Supervision millions) Consultants (Firms) ≥2 ≤ 0.1 ≤ 0.3 Individual Consultants ≥ 0.4 NA. NA. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of the Procurement Regulations for IPF Borrowers. 3. Terms of Reference (TOR) for all consultancy contracts as well as all direction selections, irrespective of the contract value, will be subject to prior review. 4. Any Other Special Selection Arrangements: N/A 5. Consultancy Assignments with Selection Methods and Time Procurement of Consulting Services Summary 1 2 3 4 5 6 Ref. No. Description of Estimated Package Review Comments Assignment Cost s by Bank (Prior / US$ million Post) Summary of 3.5 1 Post contracts through QCBS Summary of 1.33 8 Post NIL contracts through CQS 3 Summary of 1.67 10 Post NIL contracts through IC 4 PROCUREMENT Lesotho : Smallholder Agriculture Development Project - II PLAN General Information Country: Lesotho 2020-03-16 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2023-05-19 if none) Project ID: P165228 GPN Date: 2022-06-08 Project Name: Smallholder Agriculture Development Project - II Loan / Credit No: IDA / 64220 Ministry of Agriculture and Food Security Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process S Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Comple Description Component Review Type Method Amount (U ount (US$ and Recommendatio Signed Contract o. h cess (Y/N) isk ocument Type tatus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes tion S$) ) n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LS-MAFS-161387-CW-RFQ / Rehabilitation and refurbish Promoting Climate Smart A Request for Quot Open - Internation Single Stage - One 2022-01-2 ment of server rooms and s IDA / 64220 gricultural Practices and Ad Post 180,000.00 0.00 Canceled 2021-06-05 2021-07-31 ations al Envelope 7 upplementary premises for visory Services MIS and other measuring sta tions and testing labs LS-MAFS-161385-CW-RFQ / Project Management, Coord Request for Quot Single Stage - One 2022-01-2 IDA / 64220 Post Open - National 100,000.00 0.00 Canceled 2021-06-01 2021-07-27 Repair and refurbishment of ination and Monitoring and ations Envelope 3 PMU Office Evaluation LS-MAFS-161554-CW-RFB / Promoting Climate Smart A Construction of fertilizer ble Single Stage - One 1,200,000.0 2022-08-1 IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 0.00 Canceled 2021-10-28 2021-11-02 2021-12-14 2022-01-13 2022-02-17 nding facility including oper Envelope 0 6 visory Services ating expenses for the fist t hree years LS-MAFS-161552-CW-RFB / Rehabilitation of irrigation s Promoting Climate Smart A Request for Quot Single Stage - One 1,200,000.0 2023-06-1 ystems and on farm pipeline IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National ations (Non Bank 0.00 Signed 2022-08-22 2022-02-21 2022-08-27 2022-10-08 2022-03-17 2022-11-07 2022-06-08 2022-12-12 Envelope 0 0 s for selected sites in Mafete visory Services -SPD) ng,Mohale'shoek and Quthin g Districts LS-MAFS-161549-CW-RFB / Request for Bids Rehabilitation of irrigation s Promoting Climate Smart A Single Stage - One - Works (without 2,400,000.0 2022-11-0 ystems and on farm pipeline IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 0.00 Canceled 2022-01-16 2022-01-21 2022-03-04 2022-04-03 2022-05-08 Envelope prequalification) 0 4 s for the selected sites in ler visory Services SPD ibe,Berea ,Butha-Buthe and Maseru districts. Request for Quot LS-MAFS-193539-CW-RFQ / Promoting Climate Smart A Request for Quot Single Stage - One ations - Small Wo 2022-11-0 Rehabilitation of Irrigation s IDA / 64220 gricultural Practices and Ad Post Limited 200,000.00 0.00 Canceled 2022-03-12 2022-05-07 ations Envelope rks (Emergency) 3 chemes visory Services SPD -Competitive Request for Quot Project Management, Coord LS-MAFS-260903-CW-RFQ / Request for Quot Single Stage - One ations - Small Wo 2022-07-2 IDA / 64220 ination and Monitoring and Post Open - National 200,000.00 113,827.03 Signed 2021-12-05 2022-01-30 2022-01-29 Rehabilitation of PMU offices ations Envelope rks (Emergency) 9 Evaluation SPD -Competitive Request for Bids LS-MAFS-299508-CW-RFB / Promoting Climate Smart A Single Stage - One - Small Works SP 2023-04-2 Rehabilitation of Irrigation S IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 400,000.00 0.00 Signed 2022-06-17 2022-06-23 2022-06-22 2022-06-23 2022-08-03 2022-07-28 2022-09-02 2022-09-30 2022-10-07 Envelope D (1 envelope pr 8 chemes for Leribe and Moha visory Services ocess) leshoek Request for Bids LS-MAFS-340963-CW-RFB / Promoting Climate Smart A Single Stage - One - Works (without Under Impl 2023-12-0 Construction of irrigation sys IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 99,511.58 0.00 2023-02-17 2023-02-09 2023-02-22 2023-04-05 2023-05-05 2023-06-09 Envelope prequalification) ementation 6 tem for Ha Mashaka visory Services SPD Request for Bids LS-MAFS-340969-CW-RFB / Promoting Climate Smart A Single Stage - One - Small Works SP Under Impl 2023-12-0 Construction of irrigation sys IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 127,678.92 0.00 2023-02-17 2023-02-09 2023-02-22 2023-04-05 2023-05-05 2023-06-09 Envelope D (1 envelope pr ementation 6 tem for Ha Ts'iu Thaba-Tsek visory Services ocess) a LS-MAFS-340976-CW-RFB / I Request for Bids Promoting Climate Smart A nstallation/Construction of ir Single Stage - One - Plant SPD (with Under Impl 2023-12-0 IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 74,954.02 0.00 2023-02-17 2023-02-09 2023-02-22 2023-04-05 2023-05-05 2023-06-09 rigation system Mosaqane ir Envelope out prequalificati ementation 6 visory Services rigation scheme in Qachas n on) ek Request for Bids LS-MAFS-340978-CW-RFB / Promoting Climate Smart A Single Stage - One - Plant SPD (with Under Impl 2023-12-0 Construction /installation of IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 187,906.71 0.00 2023-02-17 2023-02-09 2023-02-22 2023-04-05 2023-05-05 2023-06-09 Envelope out prequalificati ementation 6 Lipohong irrigation scheme i visory Services on) n Berea Request for Bids LS-MAFS-340996-CW-RFB / Promoting Climate Smart A Single Stage - One - Works (without Under Impl 2023-12-0 Construction of of Makoabati IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 74,291.20 0.00 2023-02-17 2023-02-09 2023-02-22 2023-04-05 2023-05-05 2023-06-09 Envelope prequalification) ementation 6 ng Irrigation system in Mokh visory Services SPD otlong Request for Bids LS-MAFS-341001-CW-RFB / Promoting Climate Smart A Single Stage - One - Works (without Under Impl 2023-12-0 Construction of Matamolane IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 159,229.40 0.00 2023-02-17 2023-02-09 2023-02-22 2023-04-05 2023-05-05 2023-06-09 Envelope prequalification) ementation 6 Irrigation Scheme in Mafete visory Services SPD ng Request for Bids LS-MAFS-341007-CW-RFB / Promoting Climate Smart A Single Stage - One - Works (without Under Impl 2023-12-0 Construction of Pulane and IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 109,743.25 0.00 2023-02-17 2023-02-22 2023-04-05 2023-05-05 2023-06-09 Envelope prequalification) ementation 6 Makhetheng Irrigation sche visory Services SPD mes in Berea Request for Bids LS-MAFS-341011-CW-RFB / Promoting Climate Smart A Single Stage - One - Works (without Under Impl 2023-12-0 Construction of Ts'ila-Nts'o I IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 92,111.40 0.00 2023-02-17 2023-02-09 2023-02-22 2023-04-05 2023-05-05 2023-06-09 Envelope prequalification) ementation 6 rrigation Scheme in Mokhotl visory Services SPD ong GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MAFS-161018-GO-RFQ / Project Management, Coord Request for Quot Single Stage - One Procurement of computers a IDA / 64220 ination and Monitoring and Post Open - National 140,000.00 41,786.84 Signed 2020-05-05 2020-06-26 2020-08-11 2020-07-30 ations Envelope nd IT equipment for PMU Evaluation LS-MAFS-161231-GO-RFQ / Project Management, Coord Request for Quot Single Stage - One IDA / 64220 Post Open - National 495,000.00 154,097.44 Completed 2020-06-23 2020-08-18 2020-08-14 2021-02-14 2020-10-21 Procurement of eight vehicl ination and Monitoring and ations Envelope es Evaluation LS-MAFS-184018-NC-DIR / P rocurement of shade-nets,A Contingency Emergency Re UN Agencies (Dir IDA / 64220 Prior Direct 5,000,000.00 5,000,000.00 Signed 2020-07-16 2020-08-12 2020-07-21 2020-08-12 2020-08-25 2020-08-11 2021-02-21 gricultural inputs and Irrigati sponse Component ect) on Equipment for Farmers in ten districts of Lesotho. LS-MAFS-161251-GO-RFB / Promoting Climate Smart A Single Stage - One Procurement of IT technolog IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 200,000.00 0.00 Canceled 2021-01-07 2021-01-12 2021-02-23 2021-03-25 2021-04-29 2021-10-26 Envelope ies /software for soil service visory Services testing LS-MAFS-161233-GO-RFB / Procurement of inputs and s Improving Agricultural Com Single Stage - One IDA / 64220 Post Request for Bids Open - National 3,000,000.00 0.00 Canceled 2021-01-28 2021-02-02 2021-03-16 2021-04-15 2021-05-20 2021-11-16 upplementary goods for de mercialization and Nutrition Envelope monstration activities under all components LS-MAFS-193536-GO-RFQ / I Promoting Climate Smart A Request for Quot Single Stage - One rrigation equipment and ma IDA / 64220 gricultural Practices and Ad Post Limited 375,000.00 62,913.23 Signed 2021-05-09 2021-05-20 2021-06-27 2021-08-09 2021-07-28 ations Envelope terials visory Services Page 1 LS-MAFS-161229-GO-RFQ / Project Management, Coord Request for Quot Single Stage - One IDA / 64220 Post Open - National 50,000.00 6,436.25 Completed 2021-07-05 2021-08-30 2021-04-17 2022-02-26 2021-05-15 Procurement of office furnitu ination and Monitoring and ations Envelope re for PMU Evaluation LS-MAFS-161382-GO-RFQ / Improving Agricultural Com Request for Quot Open - Internation Single Stage - One Procurement of IT Technolog IDA / 64220 Post 100,000.00 0.00 Canceled 2021-06-30 2021-08-25 2022-02-21 mercialization and Nutrition ations al Envelope ies/software for digitalizing agriculture statistics LS-MAFS-161384-GO-RFQ / Promoting Climate Smart A Request for Quot Open - Internation Single Stage - One Procurement of IT technolog IDA / 64220 gricultural Practices and Ad Post 80,000.00 0.00 Canceled 2021-08-04 2021-09-29 2022-03-28 ations al Envelope ies/software for water meas visory Services uring stations LS-MAFS-225356-GO-RFQ / Project Management, Coord Request for Quot Single Stage - One Software and IT equipment f IDA / 64220 ination and Monitoring and Post Open - National 90,000.00 20,456.89 Signed 2021-03-23 2021-05-14 2021-04-17 2021-06-13 ations Envelope or PMU and Districts Evaluation LS-MAFS-253927-GO-RFQ / I Promoting Climate Smart A Request for Quot Single Stage - One rrigation Equipment for Tha IDA / 64220 gricultural Practices and Ad Post Limited 100,000.00 185,896.70 Terminated 2021-12-05 2022-02-11 2022-01-23 2022-04-26 2022-02-23 ations Envelope ba-Phatsoa Irrigation Schem visory Services e LS-MAFS-253924-GO-RFQ / I Project Management, Coord Request for Quot Single Stage - One IDA / 64220 Post Open - National 69,000.00 0.00 Canceled 2021-11-06 2021-12-28 2022-01-27 t Equipment and software ination and Monitoring and ations Envelope Evaluation LS-MAFS-161246-GO-RFQ / Project Management, Coord Request for Quot Single Stage - One Procurement of IT technolog IDA / 64220 ination and Monitoring and Post Open - National 20,000.00 0.00 Canceled 2020-09-02 2020-10-28 2021-04-26 ations Envelope ies/ software for information Evaluation systems LS-MAFS-302754-GO-RFB / Procurement of Irrigation Eq uipment for Thaba-Phatsoa ( Promoting Climate Smart A Single Stage - One Sprinklers, sprinklers stands, IDA / 64220 gricultural Practices and Ad Post Request for Bids Open - National 350,000.00 0.00 Signed 2022-07-24 2022-08-09 2022-08-08 2022-08-26 2022-09-23 2022-09-08 2022-12-03 2022-10-06 2023-01-06 2023-02-28 Envelope hydrants, valves,hydro-Mati visory Services c valves, reducers, coupling s, drag hoses, mainline pipe s, sub -maline,laterals, and i ntake pipes. LS-MAFS-340959-GO-RFQ / Promoting Climate Smart A Supply of irrigation material Request for Quot Single Stage - One Under Imple IDA / 64220 gricultural Practices and Ad Post Open - National 37,359.26 0.00 2023-02-22 2023-04-19 2023-10-16 s to support the constructio ations Envelope mentation visory Services n of irrigation system for Ha Mashaka LS-MAFS-340966-GO-RFQ / Promoting Climate Smart A Supply of irrigation equipme Request for Quot Single Stage - One Under Imple IDA / 64220 gricultural Practices and Ad Post Open - National 62,309.88 0.00 2023-02-22 2023-04-19 2023-10-16 nt to support construction of ations Envelope mentation visory Services irrigation system of Ha Tsiu Thaba Tseka LS-MAFS-340972-GO-RFQ / Promoting Climate Smart A Supply of irrigation equipme Request for Quot Single Stage - One Under Imple IDA / 64220 gricultural Practices and Ad Post Open - National 26,023.86 0.00 2023-02-22 2023-04-19 2023-10-16 nt and materials to support t ations Envelope mentation visory Services he construction of Mosaqan e irrigation scheme. LS-MAFS-340977-GO-RFQ / Promoting Climate Smart A supplies/equipment for supp Request for Quot Single Stage - One Under Imple IDA / 64220 gricultural Practices and Ad Post Open - National 31,969.32 0.00 2023-02-22 2023-04-19 2023-10-16 orting construction of LIPOH ations Envelope mentation visory Services ONG Irrigation scheme. LS-MAFS-340993-GO-RFQ / Promoting Climate Smart A Supply of irrigation equipme Request for Quot Single Stage - One Under Imple IDA / 64220 gricultural Practices and Ad Post Open - National 16,357.67 0.00 2023-02-22 2023-04-19 2023-10-16 nt & materials to support Ma ations Envelope mentation visory Services koabating Irrigation System in Mokhotlong LS-MAFS-340998-GO-RFQ / Promoting Climate Smart A Supply of Irrigation material Request for Quot Single Stage - One Under Imple IDA / 64220 gricultural Practices and Ad Post Open - National 31,653.02 0.00 2023-02-22 2023-04-19 2023-10-16 s for the support of Matamol ations Envelope mentation visory Services ane Irrigation Scheme in Maf eteng LS-MAFS-341004-GO-RFQ / Promoting Climate Smart A Supply of Irrigation material Request for Quot Single Stage - One Under Imple IDA / 64220 gricultural Practices and Ad Post Open - National 23,645.20 0.00 2023-02-22 2023-04-28 2023-04-19 2023-10-16 s to support Pulane and Mak ations Envelope mentation visory Services hetheng Irrigation scheme i n Berea LS-MAFS-341010-GO-RFQ / Promoting Climate Smart A Supply of Irrigation material Request for Quot Single Stage - One Under Imple IDA / 64220 gricultural Practices and Ad Post Open - National 11,816.42 0.00 2023-02-15 2023-04-12 2023-10-09 s to support Ts'ila-Nts'o Irrig ations Envelope mentation visory Services ation scheme Mokhotlong LS-MAFS-350117-GO-RFQ / Project Management, Coord Request for Quot Single Stage - One IDA / 64220 Post Limited 8,896.33 0.00 Completed 2023-03-20 2022-11-11 2023-05-15 2023-11-11 2023-01-18 Procurement of Laptops for ination and Monitoring and ations Envelope PMU Staff Evaluation LS-MAFS-350120-GO-RFQ / Project Management, Coord Request for Quot Single Stage - One IDA / 64220 Post Limited 35,642.00 0.00 Completed 2023-03-20 2023-01-23 2023-05-15 2023-11-11 Procurement of office cartrid ination and Monitoring and ations Envelope ges for PMU Evaluation LS-MAFS-369122-GO-RFQ / Project Management, Coord Request for Quot Single Stage - One Under Imple Procurement of Laptops and IDA / 64220 ination and Monitoring and Post Limited 21,904.00 0.00 2023-07-01 2023-05-17 2023-08-26 2024-02-22 ations Envelope mentation Projectors for SADP II Staff Evaluation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendatio Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes n for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MAFS-350094-NC-RFQ / Improving Agricultural Com Request for Quot Single Stage - One Conferencing service for les IDA / 64220 Post Limited 42,891.00 0.00 Completed 2023-03-20 2023-01-10 2023-05-15 2023-11-11 mercialization and Nutrition ations Envelope sons learnt to Farmers and S ADP II Technical staff LS-MAFS-350107-NC-RFQ / Promoting Climate Smart A Request for Quot Single Stage - One Conferencing service for Far IDA / 64220 gricultural Practices and Ad Post Limited 25,365.00 0.00 Completed 2023-03-20 2023-01-10 2023-05-15 2023-11-11 2023-02-21 ations Envelope mers and SADP II Technical visory Services staff on study tour LS-MAFS-350109-NC-RFQ / Promoting Climate Smart A Request for Quot Single Stage - One Matching Grants training of IDA / 64220 gricultural Practices and Ad Post Limited 8,920.30 0.00 Completed 2023-03-20 2022-11-10 2023-05-15 2023-11-11 ations Envelope service providers on report visory Services writing LS-MAFS-350115-NC-RFQ / Promoting Climate Smart A Matching Grants training of Request for Quot Single Stage - One IDA / 64220 gricultural Practices and Ad Post Limited 10,691.00 0.00 Completed 2023-03-20 2022-11-10 2023-05-15 2023-11-11 Service Providers on report ations Envelope visory Services writing in Quthing district LS-MAFS-350594-NC-RFQ / Promoting Climate Smart A Request for Quot Single Stage - One CSA Training for Extension s IDA / 64220 gricultural Practices and Ad Post Limited 26,965.42 0.00 Completed 2023-03-22 2023-01-23 2023-05-17 2023-11-13 2023-03-26 ations Envelope taff visory Services LS-MAFS-350596-NC-RFQ / Promoting Climate Smart A Request for Quot Single Stage - One CSA Training for extension s IDA / 64220 gricultural Practices and Ad Post Limited 13,269.38 0.00 Completed 2023-03-22 2023-02-03 2023-05-17 2023-11-13 2023-04-03 ations Envelope taff visory Services LS-MAFS-350599-NC-RFQ / Promoting Climate Smart A Request for Quot Single Stage - One Matching Grants workshop o IDA / 64220 gricultural Practices and Ad Post Limited 15,992.10 0.00 Completed 2023-03-22 2022-09-10 2023-05-17 2023-11-13 ations Envelope n Lessons Learnt visory Services Page 2 LS-MAFS-350602-NC-RFQ / Promoting Climate Smart A Request for Quot Single Stage - One Matching Grants workshop o IDA / 64220 gricultural Practices and Ad Post Limited 46,183.32 0.00 Completed 2023-03-22 2023-02-06 2023-05-17 2023-11-13 2022-10-09 ations Envelope n Lessons Learnt visory Services LS-MAFS-350605-NC-RFQ / Promoting Climate Smart A Request for Quot Single Stage - One Agri- Business training for fa IDA / 64220 gricultural Practices and Ad Post Limited 17,708.24 0.00 Completed 2023-03-22 2022-08-10 2023-05-17 2023-11-13 2023-04-03 ations Envelope rmers visory Services LS-MAFS-350610-NC-RFQ / Promoting Climate Smart A Request for Quot Single Stage - One Agribusiness Training for Far IDA / 64220 gricultural Practices and Ad Post Limited 21,041.20 0.00 Completed 2023-03-22 2022-07-10 2023-05-17 2023-11-13 ations Envelope mers visory Services CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) Notice equest for Proposals as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MAFS-161720-CS-QCBS / Promoting Climate Smart A Quality And Cost- Open - Internation Consulting services for adop IDA / 64220 gricultural Practices and Ad Post 350,000.00 0.00 Canceled 2021-05-20 2021-06-10 2021-07-24 2021-08-21 2021-09-20 2021-10-25 2021-11-29 2022-11-29 Based Selection al tion of conservation agricult visory Services ure and ISFM LS-MAFS-161777-CS-QCBS / National service providers fo Improving Agricultural Com Quality And Cost- IDA / 64220 Post Open - National 700,000.00 1,349,072.80 Signed 2020-12-07 2020-06-26 2020-12-28 2020-06-26 2021-02-10 2020-08-28 2021-03-10 2020-09-16 2021-04-09 2020-09-24 2021-05-14 2020-11-04 2021-06-18 2020-11-20 2022-06-18 r nutrition sensitive agricult mercialization and Nutrition Based Selection ure sub-component LS-MAFS-161765-CS-CQS / National service providers fo Improving Agricultural Com Consultant Qualifi IDA / 64220 Post Open - National 250,000.00 0.00 Canceled 2021-02-10 2021-03-03 2021-04-16 2021-05-16 2021-06-20 2021-12-17 r productive alliances and v mercialization and Nutrition cation Selection alue chain development (U mbrella advisor) LS-MAFS-161739-CS-CQS / Promoting Climate Smart A Consulting services for rapid Consultant Qualifi IDA / 64220 gricultural Practices and Ad Post Open - National 200,000.00 0.00 Canceled 2021-01-17 2021-02-07 2021-03-23 2021-04-22 2021-05-27 2021-11-23 assessment and design of th cation Selection visory Services e fertilizer blending facility LS-MAFS-161768-CS-QCBS / Improving Agricultural Com Quality And Cost- National service providers fo IDA / 64220 Post Open - National 400,000.00 0.00 Canceled 2021-02-09 2021-03-02 2021-04-15 2021-05-13 2021-06-12 2021-07-17 2021-08-21 2022-08-21 mercialization and Nutrition Based Selection r smallholder competitive m atching grants LS-MAFS-161786-CS-QCBS / Consulting services for asse Project Management, Coord Quality And Cost- Open - Internation ssment of environmental co IDA / 64220 ination and Monitoring and Post 350,000.00 0.00 Canceled 2021-03-30 2021-04-20 2021-06-03 2021-07-01 2021-07-31 2021-09-04 2021-10-09 2022-10-09 Based Selection al mpliance of the project activ Evaluation ities for all ten districts. LS-MAFS-161789-CS-CQS / Project Management, Coord Consultant Qualifi Consulting services for base IDA / 64220 ination and Monitoring and Post Open - National 250,000.00 240,363.73 Signed 2021-06-07 2021-04-26 2021-06-28 2021-04-30 2021-08-11 2021-07-21 2021-09-10 2021-09-22 2021-10-15 2021-09-28 2022-04-13 cation Selection line survey,MTR and final im Evaluation pact assessment LS-MAFS-161918-CS-CQS / Project Management, Coord Consulting Services for rapid Consultant Qualifi Open - Internation IDA / 64220 ination and Monitoring and Post 50,000.00 0.00 Canceled 2021-05-04 2021-05-25 2021-07-08 2021-08-07 2021-09-11 2022-03-10 assessment and design of s cation Selection al Evaluation oil information system LS-MAFS-161757-CS-QCBS / International service provide Improving Agricultural Com Quality And Cost- Open - Internation IDA / 64220 Post 1,250,000.00 0.00 Canceled 2021-06-30 2021-07-21 2021-09-03 2021-10-01 2021-10-31 2021-12-05 2022-01-09 2023-01-09 r for productive alliances an mercialization and Nutrition Based Selection al d value chain development LS-MAFS-246560-CS-CQS / Project Management, Coord Consultant Qualifi Monitoring Information Syst IDA / 64220 ination and Monitoring and Post Open - National 100,000.00 131,758.00 Signed 2021-11-26 2021-09-08 2021-12-17 2021-09-14 2022-01-30 2021-11-22 2022-03-01 2022-02-08 2022-04-05 2022-03-15 2022-10-02 cation Selection em for Monitoring & Evaluati Evaluation on LS-MAFS-161753-CS-CQS / Consulting services for prep Promoting Climate Smart A Consultant Qualifi aration of detailed design in IDA / 64220 gricultural Practices and Ad Post Open - National 200,000.00 0.00 Canceled 2022-02-24 2022-03-17 2022-04-30 2022-05-30 2022-07-04 2022-12-31 cation Selection selected irrigation schemes i visory Services ncluding author supervision in all ten disticts LS-MAFS-161746-CS-CQS / Promoting Climate Smart A Scoping study for digitizing Consultant Qualifi IDA / 64220 gricultural Practices and Ad Post Open - National 250,000.00 0.00 Canceled 2022-04-25 2022-05-16 2022-06-29 2022-07-29 2022-09-02 2023-03-01 Agriculture statistics and im cation Selection visory Services proving Market Information LS-MAFS-182453-CS-QCBS / International Service Provid Improving Agricultural Com Quality And Cost- Open - Internation IDA / 64220 Post 700,000.00 0.00 Canceled 2022-09-23 2022-10-14 2022-11-27 2022-12-25 2023-01-24 2023-02-28 2023-04-04 2024-04-03 ers for Agriculture commerci mercialization and Nutrition Based Selection al alization and Nutrition LS-MAFS-161717-CS-QCBS / Promoting Climate Smart A Consulting services for disse Quality And Cost- Open - Internation IDA / 64220 gricultural Practices and Ad Post 450,000.00 0.00 Canceled 2022-06-30 2022-07-21 2022-09-03 2022-10-01 2022-10-31 2022-12-05 2023-01-09 2024-01-09 rmination of climate smart a Based Selection al visory Services griculture technologies (FFS and ToT) LS-MAFS-161716-CS-CQS / Promoting Climate Smart A Consulting services for publi Consultant Qualifi IDA / 64220 gricultural Practices and Ad Post Open - National 150,000.00 0.00 Canceled 2020-04-26 2020-05-17 2020-06-30 2020-07-30 2020-09-03 2021-03-02 c awareness and social mob cation Selection visory Services ilization in all ten districts LS-MAFS-261207-CS-CQS / Promoting Climate Smart A Consultant Qualifi Agro Weather tools consulta IDA / 64220 gricultural Practices and Ad Post Open - National 71,429.00 0.00 Signed 2021-11-30 2022-03-03 2021-12-21 2022-03-06 2022-02-03 2022-05-03 2022-03-05 2022-09-06 2022-04-09 2022-10-06 cation Selection ncy visory Services LS-MAFS-282505-CS-CQS / Promoting Climate Smart A Consultant Qualifi Open - Internation Under Implement Market Information and Far IDA / 64220 gricultural Practices and Ad Post 168,750.00 0.00 2022-03-31 2022-05-17 2022-04-21 2022-05-30 2022-06-04 2022-08-26 2022-07-04 2022-08-08 2023-02-04 cation Selection al ation mers database system visory Services LS-MAFS-312358-CS-CQS / Improving Agricultural Com Consultant Qualifi IDA / 64220 Post Open - National 100,000.00 0.00 Canceled 2022-08-29 2022-08-30 2022-09-19 2022-11-18 2022-12-18 2023-01-22 2024-01-26 Youth Mentorship Consultan mercialization and Nutrition cation Selection cy LS-MAFS-354824-CS-CQS / Project Management, Coord Consultant Qualifi Under Implement Selection and Employment o IDA / 64220 ination and Monitoring and Post Open - National 189,596.01 0.00 2023-05-08 2023-05-26 2023-05-29 2023-07-12 2023-08-11 2023-09-15 2024-03-13 cation Selection ation f Project Financial Specialist Evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LS-MAFS-161814-CS-INDV / Project Management, Coord Individual Consult Climate Smart Agricultural O IDA / 64220 ination and Monitoring and Post Open 210,000.00 158,349.40 Signed 2020-09-21 2020-10-12 2020-11-09 2021-05-17 2020-11-30 2021-05-17 2021-01-04 2021-05-25 2023-03-31 ant Selection fficer based in PMU office Evaluation LS-MAFS-161819-CS-INDV / Project Management, Coord Individual Consult Water Resource Manageme IDA / 64220 ination and Monitoring and Post Open 210,000.00 114,499.47 Signed 2020-05-21 2020-03-29 2020-07-09 2020-06-26 2020-07-30 2020-07-15 2020-09-03 2020-10-09 2023-03-31 ant Selection nt Officer based in PMU offic Evaluation e Page 3 LS-MAFS-161834-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 0.00 Canceled 2020-07-10 2020-03-17 2020-08-28 2020-09-18 2020-10-23 2023-03-31 Nutrition Officer based in PM ination and Monitoring and ant Selection U office Evaluation LS-MAFS-161891-CS-INDV / Project Management, Coord Individual Consult Environmental and social saf IDA / 64220 ination and Monitoring and Post Open 210,000.00 112,669.25 Signed 2020-06-22 2020-03-19 2020-08-10 2020-08-28 2020-08-31 2020-09-03 2020-10-05 2020-10-09 2021-04-03 ant Selection eguards Officer Evaluation LS-MAFS-161894-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Direct 250,000.00 168,493.37 Completed 2020-03-06 2020-03-18 2020-03-16 2020-03-31 2020-04-06 2020-08-10 2020-05-11 2020-04-01 2023-03-31 2021-04-01 Project Director based in PM ination and Monitoring and ant Selection U Evaluation LS-MAFS-161897-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Direct 245,000.00 154,452.26 Signed 2020-03-06 2020-03-18 2020-03-16 2020-03-31 2020-04-06 2020-08-10 2020-05-11 2020-04-01 2023-03-31 Finance Manager based in P ination and Monitoring and ant Selection MU Evaluation LS-MAFS-161898-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Direct 240,000.00 0.00 Canceled 2020-03-06 2020-03-18 2020-03-16 2020-04-06 2020-05-11 2023-03-31 Procurement Manager base ination and Monitoring and ant Selection d in PMU Evaluation LS-MAFS-161900-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Direct 210,000.00 84,246.69 Signed 2020-03-06 2020-03-18 2020-03-16 2020-03-31 2020-04-06 2020-08-10 2020-05-11 2020-04-01 2023-03-31 Project Field Officer -Mohale' ination and Monitoring and ant Selection shoek Evaluation LS-MAFS-161903-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Direct 210,000.00 0.00 Canceled 2020-03-06 2020-03-18 2020-03-16 2020-04-06 2020-05-11 2023-03-31 Project Field Officer Quthing ination and Monitoring and ant Selection Evaluation LS-MAFS-161907-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Direct 210,000.00 0.00 Canceled 2020-03-06 2020-03-18 2020-03-16 2020-04-06 2020-05-11 2023-03-31 Project Field Officer Maseru ination and Monitoring and ant Selection Evaluation LS-MAFS-161925-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Direct 230,000.00 108,020.52 Terminated 2020-03-06 2020-03-18 2020-03-16 2020-08-10 2020-04-06 2020-08-10 2020-05-11 2020-04-01 2023-03-31 Competitive Grants Manager ination and Monitoring and ant Selection Evaluation LS-MAFS-161926-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 230,000.00 114,499.47 Signed 2020-03-31 2020-03-18 2020-05-19 2020-06-29 2020-06-09 2020-07-15 2020-07-14 2020-10-13 2023-03-31 Monitoring and Evaluation M ination and Monitoring and ant Selection anager Evaluation LS-MAFS-161927-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 90,394.32 Signed 2020-03-06 2020-03-19 2020-04-24 2020-06-26 2020-05-15 2020-07-15 2020-06-19 2020-10-09 2023-03-31 Accountant based in PMU ination and Monitoring and ant Selection Evaluation LS-MAFS-161929-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 91,013.09 Signed 2020-03-06 2020-03-17 2020-04-24 2020-07-13 2020-05-15 2020-07-27 2020-06-19 2020-10-13 2023-03-31 Project Field Officer Qacha's ination and Monitoring and ant Selection nek Evaluation LS-MAFS-161931-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 0.00 Canceled 2020-03-06 2020-03-18 2020-04-24 2020-05-15 2020-06-19 2023-03-31 Project Field Officer -Thaba - ination and Monitoring and ant Selection Tseka Evaluation LS-MAFS-161932-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 0.00 Canceled 2020-03-06 2020-03-18 2020-04-24 2020-05-15 2020-06-19 2023-03-31 Project Field Officer Butha -B ination and Monitoring and ant Selection uthe Evaluation LS-MAFS-161934-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 0.00 Canceled 2020-03-06 2020-03-19 2020-04-24 2020-05-15 2020-06-19 2023-03-31 Project Field Officer Leribe ination and Monitoring and ant Selection Evaluation LS-MAFS-161935-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 0.00 Canceled 2020-03-06 2020-03-18 2020-04-24 2020-05-15 2020-06-19 2023-03-31 Project Field Officer Berea ination and Monitoring and ant Selection Evaluation LS-MAFS-161937-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 0.00 Canceled 2020-03-06 2020-03-18 2020-04-24 2020-05-15 2020-06-19 2023-03-31 Project Field Officer Mafeten ination and Monitoring and ant Selection g Evaluation LS-MAFS-161940-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 91,013.09 Signed 2020-03-06 2020-03-18 2020-04-24 2020-07-13 2020-05-15 2020-07-27 2020-06-19 2020-10-15 2023-03-31 Project Field Officer Mokhotl ination and Monitoring and ant Selection ong Evaluation LS-MAFS-161914-CS-CDS / I Project Management, Coord IDA / 64220 Post Direct Selection Direct 304,000.00 193,342.00 Signed 2020-03-22 2020-05-08 2020-04-01 2020-06-03 2020-06-05 2020-07-30 2020-08-16 rrigation Master plan for Les ination and Monitoring and otho Evaluation LS-MAFS-166188-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Direct 240,000.00 156,345.49 Signed 2020-03-29 2020-03-30 2020-04-08 2020-03-31 2020-04-29 2020-08-10 2020-06-03 2020-04-01 2023-03-31 Procurement Manager base ination and Monitoring and ant Selection d in PMU Evaluation LS-MAFS-166192-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 91,013.09 Signed 2020-03-29 2020-03-30 2020-05-17 2020-07-13 2020-06-07 2020-07-27 2020-07-12 2020-10-10 2023-03-31 Project Field Officer -Leribe ination and Monitoring and ant Selection Evaluation LS-MAFS-166195-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 91,013.09 Signed 2020-03-29 2020-03-30 2020-05-17 2020-07-13 2020-06-07 2020-07-27 2020-07-12 2020-10-15 2023-03-31 Project Field Officer -Butha- ination and Monitoring and ant Selection Buthe Evaluation LS-MAFS-166197-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 91,013.09 Terminated 2020-03-29 2020-03-30 2020-05-17 2020-07-20 2020-06-07 2020-07-27 2020-07-12 2020-10-13 2023-03-31 Project Fiedl Officer -Thaba - ination and Monitoring and ant Selection Tseka Evaluation LS-MAFS-166200-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Direct 210,000.00 85,279.36 Signed 2020-03-29 2020-03-30 2020-04-08 2020-03-31 2020-04-29 2020-08-10 2020-06-03 2020-04-01 2023-03-31 Project FIeld Officer -Quthin ination and Monitoring and ant Selection g Evaluation LS-MAFS-166201-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 85,073.22 Signed 2020-03-29 2020-03-30 2020-05-17 2020-07-13 2020-06-07 2020-08-10 2020-07-12 2020-10-15 2023-03-31 Project Field Officer -Berea ination and Monitoring and ant Selection Evaluation LS-MAFS-166202-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 106,874.66 Signed 2020-03-29 2020-03-30 2020-05-17 2020-06-26 2020-06-07 2020-07-15 2020-07-12 2020-10-09 2023-03-31 Nutrition Officer based in PM ination and Monitoring and ant Selection U Evaluation LS-MAFS-166203-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 91,013.09 Signed 2020-03-29 2020-03-30 2020-05-17 2020-07-13 2020-06-07 2020-07-27 2020-07-12 2020-10-13 2023-03-31 Project Field Officer Mafeten ination and Monitoring and ant Selection g Evaluation LS-MAFS-166206-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Direct 210,000.00 85,279.36 Signed 2020-03-29 2020-03-30 2020-04-08 2020-03-31 2020-04-29 2020-08-10 2020-06-03 2020-04-01 2023-03-31 Project Field Officer -Maseru ination and Monitoring and ant Selection Evaluation LS-MAFS-172733-CS-INDV / Project Management, Coord Individual Consult Horizontal Alliance Manager IDA / 64220 ination and Monitoring and Post Open 210,000.00 158,480.81 Signed 2020-07-19 2020-07-14 2020-09-06 2021-05-05 2020-09-27 2021-05-10 2020-11-01 2021-05-12 2023-03-31 ant Selection based in PMU Evaluation LS-MAFS-172735-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 150,000.00 60,675.39 Signed 2020-06-01 2020-05-20 2020-07-20 2020-07-20 2020-08-10 2020-07-27 2020-09-14 2020-10-09 2023-02-11 Administrator Based in PMU ination and Monitoring and ant Selection Evaluation LS-MAFS-161809-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 180,000.00 130,801.77 Signed 2021-02-14 2020-10-08 2021-04-04 2020-11-24 2021-04-25 2020-12-08 2021-05-30 2020-11-28 2023-11-30 Assistant to Procurement Off ination and Monitoring and ant Selection icer Evaluation LS-MAFS-161805-CS-INDV / Project Management, Coord Individual Consult Assistant to Monitoring and IDA / 64220 ination and Monitoring and Post Open 180,000.00 140,871.83 Signed 2021-02-14 2020-10-08 2021-04-04 2021-05-05 2021-04-25 2021-05-10 2021-05-30 2021-05-15 2023-11-30 ant Selection Evaluation Officer Evaluation LS-MAFS-161821-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 147,151.99 Terminated 2021-02-14 2020-09-24 2021-04-04 2020-11-24 2021-04-25 2020-12-08 2021-05-30 2020-11-28 2023-12-14 IT/MIS Officer based in PMU ination and Monitoring and ant Selection office Evaluation LS-MAFS-193542-CS-INDV / Improving Agricultural Com Individual Consult Matching Grants Implement IDA / 64220 Post Open 14,250.00 11,225.44 Completed 2020-09-18 2020-09-14 2020-10-10 2020-10-23 2020-10-31 2020-11-04 2020-11-26 2020-11-07 2021-05-25 2021-04-02 mercialization and Nutrition ant Selection ation Advisor-Mokhotlong LS-MAFS-193544-CS-INDV / Improving Agricultural Com Individual Consult Matching Grants Implement IDA / 64220 Post Open 14,250.00 11,973.81 Completed 2020-09-18 2020-09-14 2020-10-10 2020-10-23 2020-10-31 2020-11-04 2020-11-26 2020-11-05 2021-05-25 2021-03-25 mercialization and Nutrition ant Selection ation Advisor - Thaba -Tseka LS-MAFS-193547-CS-INDV / Improving Agricultural Com Individual Consult Matching Grants Implement IDA / 64220 Post Open 14,250.00 11,225.44 Completed 2020-09-18 2020-09-14 2020-10-10 2020-10-23 2020-10-31 2020-11-04 2020-11-26 2020-11-06 2021-05-25 2021-04-14 mercialization and Nutrition ant Selection ation Advisor-Qachasnek Page 4 LS-MAFS-193548-CS-INDV / Project Management, Coord Individual Consult Architecture and Structural IDA / 64220 ination and Monitoring and Post Limited 24,000.00 19,832.65 Signed 2020-10-22 2020-09-29 2020-10-27 2020-10-08 2020-11-17 2020-10-20 2020-12-22 2020-10-28 2021-06-20 ant Selection design Consultant Evaluation LS-MAFS-193553-CS-CDS / Project Management, Coord Social and Environmental Sa IDA / 64220 ination and Monitoring and Post Direct Selection Direct 29,100.00 30,780.00 Completed 2020-09-25 2021-02-22 2020-10-05 2021-03-02 2020-12-09 2020-10-24 2021-06-07 2020-12-19 feguard Specialist Evaluation LS-MAFS-193554-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-14 2020-11-27 2020-12-14 2021-01-01 2020-12-29 2021-06-30 Technical Reviewer for Mokh mercialization and Nutrition ant Selection otlong LS-MAFS-193556-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 0.00 Canceled 2020-09-18 2020-09-14 2020-11-06 2020-11-27 2021-01-01 2021-06-30 Technical Reviewer - Mokhot mercialization and Nutrition ant Selection long 2 LS-MAFS-193557-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 0.00 Canceled 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-14 2021-01-01 2021-06-30 Technical Reviewer -Mokhotl mercialization and Nutrition ant Selection ong 3 LS-MAFS-193558-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 0.00 Canceled 2020-09-18 2020-09-14 2020-11-06 2020-11-27 2021-01-01 2021-06-30 Technical Reviewer Mokhotl mercialization and Nutrition ant Selection ong 4 LS-MAFS-193559-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-14 2021-01-01 2020-12-30 2021-06-30 Technical Reviewer -Mokhotl mercialization and Nutrition ant Selection ong 5 LS-MAFS-193560-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-14 2021-01-01 2020-12-30 2021-06-30 Technical Reviewer -Mokhotl mercialization and Nutrition ant Selection ong 6 LS-MAFS-193561-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 0.00 Canceled 2020-09-18 2020-09-14 2020-11-06 2020-12-14 2020-11-27 2020-12-14 2021-01-01 2021-06-30 Technical Reviewer -Qachas mercialization and Nutrition ant Selection nek 1 LS-MAFS-193562-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-14 2021-01-01 2020-12-23 2021-06-30 Technical Reviewer -Qachas mercialization and Nutrition ant Selection nek 2 LS-MAFS-193563-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-14 2020-11-27 2020-12-14 2021-01-01 2020-12-30 2021-06-30 Technical Reviewer -Qachas mercialization and Nutrition ant Selection nek 3 LS-MAFS-193564-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-14 2021-01-01 2020-12-30 2021-06-30 Technical Reviewer -Qachas mercialization and Nutrition ant Selection nek 4 LS-MAFS-193567-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-14 2021-01-01 2020-12-29 2021-06-30 Technical Reviewer -Thaba-t mercialization and Nutrition ant Selection seka 1 LS-MAFS-193569-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-14 2021-01-01 2020-12-29 2021-06-30 Technical Reviewer -Thaba T mercialization and Nutrition ant Selection seka 3 LS-MAFS-193570-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-15 2021-01-01 2021-02-09 2021-06-30 Technical Reviewer 2 mercialization and Nutrition ant Selection LS-MAFS-193572-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 0.00 Canceled 2020-09-18 2020-09-14 2020-11-06 2020-11-27 2021-01-01 2021-06-30 Technical Reviewer -Thaba- mercialization and Nutrition ant Selection Tseka 4 LS-MAFS-193574-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 0.00 Canceled 2020-09-18 2020-09-14 2020-11-06 2020-11-27 2021-01-01 2021-06-30 Technical Reviewer -Thaba- mercialization and Nutrition ant Selection Tseka 5 LS-MAFS-193576-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-14 2021-01-01 2020-12-29 2021-06-30 Technical Reviewer -Thaba- mercialization and Nutrition ant Selection Tseka 6 LS-MAFS-193577-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-14 2021-01-01 2020-12-29 2021-06-30 Technical Reviewer -Thaba- mercialization and Nutrition ant Selection Tseka 7 LS-MAFS-193578-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 0.00 Canceled 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-14 2021-01-01 2021-06-30 Technical Reviewer -Qachas mercialization and Nutrition ant Selection nek 5 LS-MAFS-193580-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 50.00 Signed 2020-09-18 2020-09-14 2020-11-06 2020-12-10 2020-11-27 2020-12-14 2021-01-01 2020-12-29 2021-06-30 Technical Reviewer -Qachas mercialization and Nutrition ant Selection nek 6 LS-MAFS-193582-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 4,750.00 0.00 Canceled 2020-09-18 2020-09-14 2020-11-06 2020-12-14 2020-11-27 2020-12-15 2021-01-01 2021-06-30 Technical Reviewer -Mokhotl mercialization and Nutrition ant Selection ong 7 LS-MAFS-193583-CS-INDV / Improving Agricultural Com Individual Consult Service Providers to Grantee IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-18 2020-09-27 2020-11-06 2021-05-17 2020-11-27 2021-06-22 2021-01-01 2021-07-06 2021-06-30 mercialization and Nutrition ant Selection s - Mokhotlong 1 LS-MAFS-193585-CS-INDV / Improving Agricultural Com Individual Consult Service Providers to Grantee IDA / 64220 Post Open 2,000.00 3,509.07 Signed 2020-09-18 2020-09-27 2020-11-06 2021-05-17 2020-11-27 2021-06-22 2021-01-01 2021-07-07 2021-06-30 mercialization and Nutrition ant Selection s -Mokhotlong 2 LS-MAFS-193587-CS-INDV / Improving Agricultural Com Individual Consult Service Providers to Grantee IDA / 64220 Post Open 2,000.00 2,816.01 Signed 2020-09-18 2020-09-27 2020-11-06 2021-11-29 2020-11-27 2021-06-23 2021-01-01 2021-11-30 2021-06-30 mercialization and Nutrition ant Selection s -Mokhotlong 3 LS-MAFS-193588-CS-INDV / Improving Agricultural Com Individual Consult Service Providers to Grantee IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-18 2020-09-27 2020-11-06 2021-05-17 2020-11-27 2021-07-09 2021-01-01 2021-07-06 2021-06-30 mercialization and Nutrition ant Selection s -Mokhotlong 4 LS-MAFS-193594-CS-INDV / Improving Agricultural Com Individual Consult Service Provider to Grantees IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-18 2020-09-27 2020-11-06 2021-05-17 2020-11-27 2021-07-09 2021-01-01 2021-07-14 2021-06-30 mercialization and Nutrition ant Selection Mokhotlong 5 LS-MAFS-193595-CS-INDV / Improving Agricultural Com Individual Consult Service Providers to Grantee IDA / 64220 Post Open 2,000.00 3,380.94 Signed 2020-09-18 2020-09-27 2020-11-06 2021-05-17 2020-11-27 2021-07-20 2021-01-01 2021-10-30 2021-06-30 mercialization and Nutrition ant Selection s -Mokhotlong 6 LS-MAFS-193597-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,451.85 Signed 2020-09-18 2020-09-27 2020-11-06 2021-05-20 2020-11-27 2021-07-20 2021-01-01 2021-07-03 2021-06-30 Service Providers to Grantee mercialization and Nutrition ant Selection s7 LS-MAFS-193599-CS-INDV / Improving Agricultural Com Individual Consult Service Providers to Grantee IDA / 64220 Post Open 2,000.00 3,520.01 Signed 2020-09-18 2020-09-27 2020-11-06 2021-05-21 2020-11-27 2021-06-25 2021-01-01 2021-07-06 2021-06-30 mercialization and Nutrition ant Selection s -Mokhotlong 8 LS-MAFS-194429-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,451.85 Signed 2020-09-21 2020-09-27 2020-10-24 2021-05-06 2020-11-14 2021-07-20 2020-12-19 2021-07-03 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194430-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,451.85 Signed 2020-09-21 2020-09-27 2020-10-24 2021-05-18 2020-11-14 2021-06-25 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194431-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-21 2020-09-27 2020-10-24 2021-05-06 2020-11-14 2021-07-09 2020-12-19 2021-07-14 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194433-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 0.00 Canceled 2020-09-21 2020-09-17 2020-10-24 2021-05-06 2020-11-14 2021-07-21 2020-12-19 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194434-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,520.01 Signed 2020-09-21 2020-09-17 2020-10-24 2021-05-06 2020-11-14 2021-06-24 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194435-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 2,798.86 Signed 2020-09-21 2020-09-17 2020-10-24 2021-05-06 2020-11-14 2021-07-08 2020-12-19 2021-07-21 2021-06-17 Service Provider for Grantee mercialization and Nutrition ant Selection s Page 5 LS-MAFS-194436-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 2,761.48 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-20 2020-12-19 2021-07-03 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194438-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,438.79 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-09 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194439-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,520.01 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-21 2020-11-14 2021-06-24 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194440-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,438.79 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-09 2020-12-19 2021-07-17 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194441-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,438.79 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-20 2020-12-19 2021-07-03 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194442-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 0.00 Canceled 2020-09-21 2020-09-24 2020-10-24 2021-11-09 2020-11-14 2021-07-09 2020-12-19 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194444-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,481.88 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194445-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,498.57 Signed 2020-09-21 2020-09-17 2020-10-24 2021-05-06 2020-11-14 2021-07-08 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194446-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,498.57 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194448-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-17 2020-11-14 2021-07-09 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194449-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,481.88 Terminated 2020-09-21 2020-09-27 2020-10-24 2021-10-20 2020-11-14 2021-07-08 2020-12-19 2021-07-21 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194451-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,451.85 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-20 2020-12-19 2021-07-03 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194454-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,498.57 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194456-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-09 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194457-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-09 2020-12-19 2021-08-10 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194458-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,498.57 Signed 2020-09-21 2020-09-17 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-06 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194459-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,481.88 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194461-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 2,761.48 Signed 2020-09-21 2020-09-27 2020-10-24 2021-05-06 2020-11-14 2021-07-20 2020-12-19 2021-07-08 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194462-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,498.57 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-21 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194463-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,481.88 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-09 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194464-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-09 2020-12-19 2021-07-17 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194465-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,520.01 Signed 2020-09-21 2020-09-17 2020-10-24 2021-05-14 2020-11-14 2021-06-24 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194467-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,498.57 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-06 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194468-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,451.85 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-20 2020-12-19 2021-07-06 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194469-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,481.88 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-06 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194470-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 0.00 Canceled 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194471-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,498.57 Terminated 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-09 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194472-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,520.01 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-21 2020-11-14 2021-06-24 2020-12-19 2021-07-09 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194473-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,438.79 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-20 2020-12-19 2021-07-03 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194474-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,520.01 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-20 2020-11-14 2021-06-22 2020-12-19 2021-07-03 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194475-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-07 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194477-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,451.85 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-17 2020-11-14 2021-07-09 2020-12-19 2021-07-07 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194479-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,438.79 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-06 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194480-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,438.79 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-20 2020-12-19 2021-07-03 2021-06-17 Service Providers for grante mercialization and Nutrition ant Selection es LS-MAFS-194481-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-17 2020-11-14 2021-07-09 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194482-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,498.57 Signed 2020-09-21 2020-09-17 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-06 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194483-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,498.57 Signed 2020-09-21 2020-09-27 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-06 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194485-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,451.85 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-20 2020-12-19 2021-07-03 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s Page 6 LS-MAFS-194487-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-09 2020-12-19 2021-07-06 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194488-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 2,798.86 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-21 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194489-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-09 2020-12-19 2021-07-06 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194490-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-17 2020-11-14 2021-07-09 2020-12-19 2021-07-14 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194491-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,451.85 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-20 2020-12-19 2021-07-03 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194493-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,502.92 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-06 2020-11-14 2021-07-09 2020-12-19 2021-07-06 2021-06-17 Service Providers to Grantee mercialization and Nutrition ant Selection s LS-MAFS-194495-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,451.85 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-20 2020-12-19 2021-07-06 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es LS-MAFS-194496-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 2,000.00 3,481.88 Signed 2020-09-21 2020-09-24 2020-10-24 2021-05-14 2020-11-14 2021-07-08 2020-12-19 2021-07-09 2021-06-17 Service Providers for Grante mercialization and Nutrition ant Selection es Promoting Climate Smart A LS-MAFS-199571-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 31,250.00 0.00 Canceled 2020-10-30 2020-10-19 2020-12-18 2021-01-08 2021-02-12 2021-04-30 Irrigation policy for Lesotho ant Selection visory Services LS-MAFS-161916-CS-INDV / Project Management, Coord Individual Consult Monitoring and Evaluation In IDA / 64220 ination and Monitoring and Post Open 50,000.00 0.00 Canceled 2021-11-25 2021-03-09 2022-01-13 2022-02-03 2022-03-10 2022-09-06 ant Selection ternational Consultant for M Evaluation &E design LS-MAFS-222604-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Prior Open 250,000.00 0.00 Canceled 2021-03-04 2021-03-12 2021-04-15 2021-05-06 2021-06-10 2021-12-07 Project Director for SADP II ination and Monitoring and ant Selection Evaluation LS-MAFS-234327-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 250,000.00 221,283.88 Signed 2021-06-01 2021-06-07 2021-07-15 2021-11-02 2021-08-05 2021-11-23 2021-09-09 2021-11-30 2022-03-08 Project Director for SADPII ination and Monitoring and ant Selection Evaluation LS-MAFS-241199-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Signed 2021-07-09 2021-06-30 2021-08-27 2021-10-25 2021-09-17 2021-11-23 2021-10-22 2022-01-18 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241201-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-10-25 2021-09-17 2021-11-25 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241203-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-09 2021-06-30 2021-08-27 2021-10-25 2021-09-17 2021-12-02 2021-10-22 2022-01-15 2023-05-31 2022-01-15 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241205-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-09 2021-06-29 2021-08-27 2021-11-23 2021-09-17 2021-11-23 2021-10-22 2022-01-11 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241207-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-09 2021-06-29 2021-08-27 2021-11-02 2021-09-17 2021-12-02 2021-10-22 2022-01-04 2023-05-31 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241209-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-29 2021-08-27 2021-10-26 2021-09-17 2021-11-23 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241212-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-25 2021-10-22 2022-01-18 2023-05-31 2022-01-21 Service Providers mercialization and Nutrition ant Selection LS-MAFS-241215-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-11-02 2021-09-17 2021-12-03 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241218-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-11-02 2021-09-17 2021-11-23 2021-10-22 2022-01-11 2023-05-31 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241221-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-11-02 2021-09-17 2021-11-23 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241223-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-09 2021-06-30 2021-08-27 2021-11-11 2021-09-17 2021-11-23 2021-10-22 2021-12-18 2023-05-31 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241226-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-23 2021-10-22 2022-01-12 2023-05-31 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241230-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-09-17 2021-10-22 2023-05-31 Service Providers mercialization and Nutrition ant Selection LS-MAFS-241232-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-09 2021-06-30 2021-08-27 2021-10-25 2021-09-17 2021-11-23 2021-10-22 2022-01-08 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241234-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-11-25 2021-09-17 2021-11-25 2021-10-22 2022-01-13 2023-05-31 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241237-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-09 2021-06-30 2021-08-27 2021-11-02 2021-09-17 2021-12-03 2021-10-22 2022-01-04 2023-05-31 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241239-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-10-25 2021-09-17 2021-12-02 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241242-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.12 Completed 2021-07-09 2021-06-30 2021-08-27 2021-12-02 2021-09-17 2021-12-03 2021-10-22 2022-01-05 2023-05-31 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241244-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241246-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-09 2021-06-29 2021-08-27 2021-11-02 2021-09-17 2021-12-02 2021-10-22 2022-01-05 2023-05-31 2022-01-13 Service Providers mercialization and Nutrition ant Selection LS-MAFS-241250-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-23 2021-10-22 2022-01-11 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241253-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-23 2021-10-22 2022-01-11 2023-05-31 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241254-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-11-09 2021-09-17 2021-12-03 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241256-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 95.12 Completed 2021-07-09 2021-06-30 2021-08-27 2021-11-02 2021-09-17 2021-12-02 2021-10-22 2022-01-05 2023-05-31 2022-01-13 Service Providers mercialization and Nutrition ant Selection LS-MAFS-241257-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-11-02 2021-09-17 2021-11-23 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241258-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-25 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection Page 7 LS-MAFS-241259-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-25 2021-10-22 2022-01-18 2023-05-31 2022-01-29 Service Providers mercialization and Nutrition ant Selection LS-MAFS-241260-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-09-17 2021-10-22 2023-05-31 Service Providers mercialization and Nutrition ant Selection LS-MAFS-241261-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-25 2021-10-22 2022-01-14 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241262-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-10-25 2021-09-17 2021-11-23 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241263-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-23 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241265-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-09 2021-06-30 2021-08-27 2021-11-02 2021-09-17 2021-11-23 2021-10-22 2021-12-09 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241266-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-12-02 2021-10-22 2022-01-14 2023-05-31 2022-01-14 Service Providers mercialization and Nutrition ant Selection LS-MAFS-241267-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-09 2021-06-30 2021-08-27 2021-11-02 2021-09-17 2021-12-02 2021-10-22 2022-01-06 2023-05-31 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241268-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-10-25 2021-09-17 2021-11-23 2021-10-22 2021-12-08 2023-05-31 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241269-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-09 2021-06-30 2021-08-27 2021-11-02 2021-09-17 2021-12-03 2021-10-22 2022-01-08 2023-05-31 2022-01-13 Service Providers mercialization and Nutrition ant Selection LS-MAFS-241270-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Signed 2021-07-09 2021-06-30 2021-08-27 2021-10-25 2021-09-17 2021-11-25 2021-10-22 2022-01-11 2023-05-31 Service Providers mercialization and Nutrition ant Selection LS-MAFS-241271-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-09 2021-06-30 2021-08-27 2021-11-11 2021-09-17 2021-12-03 2021-10-22 2022-01-06 2023-05-31 2022-02-11 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241273-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-25 2021-10-22 2022-01-14 2023-05-31 2022-01-14 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241274-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-29 2021-08-27 2021-10-26 2021-09-17 2021-11-25 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241275-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-23 2021-10-22 2022-01-11 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241277-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Signed 2021-07-09 2021-06-30 2021-08-27 2021-11-11 2021-09-17 2021-12-03 2021-10-22 2022-01-11 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241278-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-23 2021-10-22 2021-12-18 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241279-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Signed 2021-07-09 2021-06-30 2021-08-27 2021-11-02 2021-09-17 2021-12-03 2021-10-22 2021-12-04 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241280-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-23 2021-10-22 2023-05-31 Service Providers mercialization and Nutrition ant Selection LS-MAFS-241281-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-11-25 2021-09-17 2021-11-25 2021-10-22 2022-01-11 2023-05-31 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241287-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-12-02 2021-09-17 2021-12-02 2021-10-22 2022-01-14 2023-05-31 2022-01-14 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241288-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-11-25 2021-10-22 2022-01-14 2023-05-31 2022-01-14 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241289-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-09 2021-06-30 2021-08-27 2021-10-26 2021-09-17 2021-12-02 2021-10-22 2022-01-14 2023-05-31 2022-01-14 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241290-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-09-17 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241762-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-02 2021-06-30 2021-08-20 2021-09-10 2021-10-15 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241764-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-02 2021-06-30 2021-08-20 2021-11-02 2021-09-10 2021-11-23 2021-10-15 2022-01-15 2023-05-24 2022-01-15 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241765-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-02 2021-06-30 2021-08-20 2021-11-11 2021-09-10 2021-12-02 2021-10-15 2022-01-06 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241766-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-02 2021-06-30 2021-08-20 2021-10-25 2021-09-10 2021-11-25 2021-10-15 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241767-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-02-15 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241769-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 95.12 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-25 2021-09-10 2021-11-25 2021-10-15 2022-02-23 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241773-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 95.12 Completed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-18 2023-05-24 2022-01-29 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241774-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-02 2021-06-30 2021-08-20 2021-10-25 2021-09-10 2021-11-25 2021-10-15 2022-01-12 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241775-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-02 2021-06-30 2021-08-20 2021-11-09 2021-09-10 2021-12-02 2021-10-15 2022-01-08 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241778-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-12-02 2021-10-15 2022-01-14 2023-05-24 2022-01-14 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241779-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-11 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241781-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-19 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241782-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-18 2023-05-24 2022-01-29 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241790-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-02 2021-06-30 2021-08-20 2021-11-02 2021-09-10 2021-12-03 2021-10-15 2022-01-29 2023-05-24 2022-01-29 Service Provider mercialization and Nutrition ant Selection Page 8 LS-MAFS-241791-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Signed 2021-07-02 2021-06-30 2021-08-20 2021-11-02 2021-09-10 2021-11-23 2021-10-15 2022-01-11 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241793-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-19 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241794-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-02 2021-06-30 2021-08-20 2021-10-25 2021-09-10 2021-10-15 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241796-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-02 2021-06-30 2021-08-20 2021-10-25 2021-09-10 2021-11-25 2021-10-15 2022-01-11 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241797-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-18 2023-05-24 2022-01-29 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241799-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Signed 2021-07-02 2021-06-30 2021-08-20 2021-11-02 2021-09-10 2021-11-23 2021-10-15 2022-01-22 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241800-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-23 2021-10-15 2022-01-06 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241801-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241802-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-02 2021-06-30 2021-08-20 2021-11-25 2021-09-10 2021-11-25 2021-10-15 2022-01-08 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241803-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-02 2021-06-30 2021-08-20 2021-10-25 2021-09-10 2021-11-23 2021-10-15 2021-12-18 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241806-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-02-15 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241807-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Signed 2021-07-02 2021-06-30 2021-08-20 2021-11-09 2021-09-10 2021-12-02 2021-10-15 2022-01-05 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241808-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-02-25 2023-05-24 2022-02-25 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241810-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-02 2021-06-30 2021-08-20 2021-11-02 2021-09-10 2021-11-23 2021-10-15 2022-01-14 2023-05-24 2022-01-21 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241811-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-19 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241812-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241813-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-20 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241814-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-25 2021-09-10 2021-11-23 2021-10-15 2021-12-08 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241816-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Completed 2021-07-02 2021-06-30 2021-08-20 2021-11-02 2021-09-10 2021-11-23 2021-10-15 2022-01-11 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241818-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-18 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241819-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-12-02 2021-10-15 2022-01-27 2023-05-24 2022-01-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241820-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-19 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241821-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-02 2021-06-30 2021-08-20 2021-11-09 2021-09-10 2021-12-03 2021-10-15 2021-01-08 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241822-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 95.12 Completed 2021-07-02 2021-06-30 2021-08-20 2021-11-11 2021-09-10 2021-12-02 2021-10-15 2022-01-11 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241823-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 95.12 Completed 2021-07-02 2021-06-30 2021-08-20 2021-12-09 2021-09-10 2021-12-09 2021-10-15 2022-01-08 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241824-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-19 2023-05-24 Service provider mercialization and Nutrition ant Selection LS-MAFS-241826-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-18 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241827-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-02 2021-06-30 2021-08-20 2021-11-02 2021-09-10 2021-12-02 2021-10-15 2022-01-06 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241829-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-26 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241831-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.64 Completed 2021-07-02 2021-06-30 2021-08-20 2021-11-02 2021-09-10 2021-12-02 2021-10-15 2022-01-07 2023-05-24 2022-01-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241832-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.96 Signed 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-11-25 2021-10-15 2022-01-19 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251323-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-11-19 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251492-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-01 2022-02-12 2022-08-11 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251493-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251494-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-16 2022-07-15 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251495-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251496-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251497-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection Page 9 LS-MAFS-251498-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-11-24 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251504-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251509-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251510-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service provider mercialization and Nutrition ant Selection LS-MAFS-251512-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251513-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251515-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251516-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2022-01-03 2021-12-10 2022-01-03 2022-01-14 2022-07-13 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251517-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251518-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 95.21 Completed 2021-09-17 2021-09-07 2021-12-01 2021-12-09 2021-12-10 2021-12-09 2022-01-28 2022-02-10 2022-07-27 2022-02-19 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251520-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-09 2021-12-10 2021-12-09 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251521-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-29 2021-12-10 2021-12-29 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251523-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-29 2021-12-10 2021-12-29 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251524-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 94.05 Signed 2021-09-17 2021-09-07 2021-12-01 2022-01-03 2021-12-10 2022-01-03 2022-01-28 2022-01-15 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251525-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-29 2021-12-10 2021-12-29 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251526-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 3,170.58 Signed 2021-09-17 2021-09-07 2021-12-01 2021-12-09 2021-12-10 2021-12-09 2022-01-28 2022-01-12 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-251528-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 3,170.58 Signed 2021-09-17 2021-09-07 2021-12-01 2021-12-09 2021-12-10 2021-12-09 2022-01-28 2022-01-12 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-252203-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-07-27 Service provider mercialization and Nutrition ant Selection LS-MAFS-252204-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 95.21 Completed 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-10 2021-12-29 2022-01-28 2022-01-14 2022-07-27 2022-01-15 Service Provider mercialization and Nutrition ant Selection LS-MAFS-252205-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-10 2021-12-29 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-252207-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-10 2021-12-29 2022-01-28 2022-02-10 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-252209-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-10 2021-12-29 2022-01-28 2022-01-12 2022-07-27 Service Provider mercialization and Nutrition ant Selection Promoting Climate Smart A LS-MAFS-252211-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2021-12-30 2021-12-10 2021-12-30 2022-01-28 2022-07-27 Service Provider ant Selection visory Services LS-MAFS-252212-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2022-01-04 2021-12-10 2022-01-04 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection Promoting Climate Smart A LS-MAFS-252213-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Completed 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-10 2021-12-29 2022-01-28 2022-02-15 2022-07-27 2022-03-01 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252218-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.12 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-09 2021-12-10 2021-12-09 2022-01-28 2022-01-13 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252219-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252222-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-10 2021-12-29 2022-01-28 2022-01-18 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252227-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.75 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-30 2021-12-10 2021-12-30 2022-01-28 2022-02-11 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252254-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Signed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-10 2022-01-03 2022-01-28 2022-02-10 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252258-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.75 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-30 2021-12-10 2021-12-30 2022-01-28 2022-02-17 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252264-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2021-12-30 2021-12-10 2021-12-30 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252286-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.12 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-09 2021-12-10 2021-12-09 2022-01-28 2022-05-05 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252287-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.12 Completed 2021-09-17 2021-09-14 2021-12-01 2021-12-09 2021-12-10 2021-12-09 2022-01-28 2022-03-02 2022-07-27 2022-03-03 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252288-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.75 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-30 2021-12-22 2021-12-30 2022-01-28 2022-02-16 2022-07-27 Service Provider ant Selection visory Services Page 10 Promoting Climate Smart A LS-MAFS-252290-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-14 2021-12-01 2021-12-09 2021-12-22 2021-12-09 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252293-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-03-02 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252295-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252297-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.75 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-30 2021-12-22 2021-12-30 2022-01-28 2022-02-11 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252298-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-01-15 2022-07-27 service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252301-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-02-12 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252303-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-14 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252304-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Completed 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-01-14 2022-07-27 2022-01-15 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252306-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252307-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.40 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-10 2021-12-22 2021-12-10 2022-01-28 2022-03-03 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252308-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.12 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-09 2021-12-22 2021-12-09 2022-01-28 2022-01-29 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252311-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-02-15 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252312-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-14 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-01-18 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252313-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.12 Completed 2021-09-17 2021-09-15 2021-12-01 2021-12-08 2021-12-22 2021-12-08 2022-01-28 2022-02-18 2022-07-27 2022-02-18 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252314-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Signed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-02-10 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252317-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-02-10 2022-07-27 service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252318-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Signed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-01-18 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252319-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Signed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-01-18 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252320-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.12 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-08 2021-12-22 2022-01-28 2022-02-18 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252321-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252463-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.12 Completed 2021-09-17 2021-09-15 2021-12-01 2021-12-08 2021-12-22 2021-12-08 2022-01-28 2022-02-18 2022-07-27 2022-02-19 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252466-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.12 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-09 2021-12-22 2021-12-09 2022-01-28 2022-01-12 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252469-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Signed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-01-18 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252491-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252497-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Signed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-01-19 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252499-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2021-12-08 2021-12-22 2021-12-08 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252500-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Completed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-02-11 2022-07-27 2022-02-11 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252502-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.12 Completed 2021-09-17 2021-09-15 2021-12-01 2021-12-08 2021-12-22 2021-12-08 2022-01-28 2022-02-12 2022-07-27 2022-02-22 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252503-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Signed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-02-19 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252517-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.06 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-30 2021-12-22 2021-12-30 2022-01-28 2022-02-19 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252518-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-01-15 2022-07-27 Service Provider ant Selection visory Services Page 11 Promoting Climate Smart A LS-MAFS-252520-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Completed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-01-18 2022-07-27 2022-01-20 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252526-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Completed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-01-26 2022-07-27 2022-01-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252529-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2022-01-04 2021-12-22 2022-01-04 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252530-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252532-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-17 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-02-15 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252534-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.06 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-30 2021-12-22 2021-12-30 2022-01-28 2022-02-19 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252535-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-02-12 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252536-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2021-12-08 2021-12-22 2021-12-08 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252537-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.12 Completed 2021-09-17 2021-09-17 2021-12-01 2021-12-08 2021-12-22 2021-12-08 2022-01-28 2022-02-18 2022-07-27 2022-02-19 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252538-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Signed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-01-14 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252539-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-02-15 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252541-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-02-15 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252542-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252544-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2021-12-30 2021-12-22 2021-12-30 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252545-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Signed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-02-23 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252546-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.12 Completed 2021-09-17 2021-09-15 2021-12-01 2021-12-08 2021-12-22 2021-12-08 2022-01-28 2022-02-18 2022-07-27 2022-02-18 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252548-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.06 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-30 2021-12-22 2021-12-30 2022-01-28 2022-02-19 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252549-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2021-12-09 2021-12-22 2021-12-09 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252550-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Completed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-01-25 2022-07-27 2022-01-25 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252552-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252554-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Signed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-02-11 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252555-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Completed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-01-15 2022-07-27 2022-01-15 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252557-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2021-12-08 2021-12-22 2021-12-08 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252558-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252560-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-01-18 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252562-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 95.21 Signed 2021-09-17 2021-09-15 2021-12-01 2021-12-29 2021-12-22 2021-12-29 2022-01-28 2022-02-15 2022-07-27 Service Provider ant Selection visory Services Promoting Climate Smart A LS-MAFS-252564-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 94.05 Completed 2021-09-17 2021-09-15 2021-12-01 2022-01-03 2021-12-22 2022-01-03 2022-01-28 2022-01-19 2022-07-27 2022-01-19 Service Provider ant Selection visory Services LS-MAFS-161922-CS-INDV / Project Management, Coord Consulting services for esta Individual Consult IDA / 64220 ination and Monitoring and Post Open 30,000.00 0.00 Canceled 2022-10-23 2022-12-11 2023-01-01 2023-02-05 2023-08-04 blishing and implementation ant Selection Evaluation of project grievance redress mechanism LS-MAFS-241825-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-02 2021-06-30 2021-08-20 2021-09-10 2021-10-15 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241828-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-02 2021-06-30 2021-08-20 2021-10-26 2021-09-10 2021-10-15 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241830-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-02 2021-06-30 2021-08-20 2021-09-10 2021-10-15 2023-05-24 Service Provider mercialization and Nutrition ant Selection Page 12 LS-MAFS-241243-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-09 2021-06-30 2021-08-27 2021-09-17 2021-10-22 2023-05-31 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241804-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-02 2021-06-30 2021-08-20 2021-09-10 2021-10-15 2023-05-24 Service Provider mercialization and Nutrition ant Selection LS-MAFS-241833-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-07-02 2021-06-30 2021-08-20 2021-09-10 2021-10-15 2023-05-24 Service Providers mercialization and Nutrition ant Selection Promoting Climate Smart A LS-MAFS-252519-CS-INDV / Individual Consult IDA / 64220 gricultural Practices and Ad Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-15 2021-12-01 2021-12-22 2022-01-28 2022-07-27 Service Provider ant Selection visory Services LS-MAFS-251530-CS-INDV / Improving Agricultural Com Individual Consult IDA / 64220 Post Open 3,000.00 0.00 Canceled 2021-09-17 2021-09-07 2021-12-01 2021-12-10 2022-01-28 2022-07-27 Service Provider mercialization and Nutrition ant Selection LS-MAFS-275548-CS-CDS / Improving Agricultural Com Service Provider for Matchin IDA / 64220 Post Direct Selection Direct 3,000.00 99.67 Signed 2022-02-14 2022-03-07 2022-02-24 2022-03-15 2022-04-30 2022-03-04 2022-05-31 mercialization and Nutrition g Grants Beneficiaries LS-MAFS-275563-CS-CDS / Improving Agricultural Com Service Provider for Matchin IDA / 64220 Post Direct Selection Direct 3,000.00 0.00 Canceled 2022-02-14 2022-03-07 2022-02-24 2022-03-15 2022-04-30 2022-05-31 mercialization and Nutrition g Grants Beneficiaries LS-MAFS-263241-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Matc IDA / 64220 Post Open 3,000.00 1,500.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-16 2022-02-07 2022-03-16 2022-03-14 2022-01-08 2022-09-10 2022-01-14 mercialization and Nutrition ant Selection hing grants Applications LS-MAFS-263245-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-16 2022-02-07 2022-03-16 2022-03-14 2022-01-07 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263255-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-21 2022-02-07 2022-03-21 2022-03-14 2022-01-08 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-267861-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 129,495.55 Signed 2021-12-17 2022-02-21 2022-02-04 2022-02-25 2022-02-25 2022-03-02 2022-04-01 2022-03-04 2022-09-28 Project Field Officer for Mok ination and Monitoring and ant Selection hotlong Evaluation LS-MAFS-267862-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 129,495.55 Signed 2021-12-17 2022-02-21 2022-02-04 2022-02-25 2022-02-25 2022-03-02 2022-04-01 2022-03-08 2022-09-28 Project Field Officer Quthing ination and Monitoring and ant Selection Evaluation LS-MAFS-263263-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-03 2022-02-07 2022-03-03 2022-03-14 2022-01-07 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-275545-CS-CDS / Improving Agricultural Com Service Provider for Matchin IDA / 64220 Post Direct Selection Direct 3,000.00 99.67 Signed 2022-02-14 2022-03-07 2022-02-24 2022-03-15 2022-04-30 2022-03-22 2022-05-31 mercialization and Nutrition g Grants beneficiaries LS-MAFS-275547-CS-CDS / Improving Agricultural Com Service Provider for Matchin IDA / 64220 Post Direct Selection Direct 3,000.00 99.67 Signed 2022-02-14 2022-03-07 2022-02-24 2022-03-15 2022-04-30 2022-03-12 2022-05-31 mercialization and Nutrition g Grants Beneficiaries LS-MAFS-275549-CS-CDS / Improving Agricultural Com Service Provider for Matchin IDA / 64220 Post Direct Selection Direct 3,000.00 99.67 Signed 2022-02-14 2022-03-07 2022-02-24 2022-03-15 2022-04-30 2022-03-04 2022-05-31 mercialization and Nutrition g Grants Beneficiaries LS-MAFS-263243-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-16 2022-02-07 2022-03-16 2022-03-14 2022-01-11 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants Applications LS-MAFS-263244-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-16 2022-02-07 2022-03-16 2022-03-14 2022-03-17 2022-09-10 2022-05-19 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263246-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-21 2022-02-07 2022-03-21 2022-03-14 2022-03-22 2022-09-10 2022-05-19 mercialization and Nutrition ant Selection ing grants Applications LS-MAFS-263248-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-21 2022-02-07 2022-03-21 2022-03-14 2022-01-04 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263249-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-08 2022-01-17 2022-03-16 2022-02-07 2022-03-16 2022-03-14 2022-01-07 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263250-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-21 2022-02-07 2022-03-21 2022-03-14 2022-03-07 2022-09-10 2022-05-19 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263253-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-21 2022-02-07 2022-03-21 2022-03-14 2022-01-11 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263254-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-21 2022-02-07 2022-03-21 2022-03-14 2022-03-08 2022-09-10 2022-05-19 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263256-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-21 2022-02-07 2022-03-21 2022-03-14 2022-03-08 2022-09-10 2022-05-19 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263257-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-21 2022-02-07 2022-03-21 2022-03-14 2021-12-08 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263258-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-21 2022-02-07 2022-03-21 2022-03-14 2022-01-08 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263259-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-04-05 2022-02-07 2022-04-05 2022-03-14 2022-01-08 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263261-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-21 2022-02-07 2022-03-21 2022-03-14 2022-01-07 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants applications LS-MAFS-263262-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-03 2022-02-07 2022-03-03 2022-03-14 2022-01-08 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grant applications LS-MAFS-263265-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-03 2022-02-07 2022-03-03 2022-03-14 2022-01-08 2022-09-10 2022-01-13 mercialization and Nutrition ant Selection ing grants applications Page 13 LS-MAFS-275552-CS-CDS / Improving Agricultural Com Service Provider for Matchin IDA / 64220 Post Direct Selection Direct 3,000.00 99.67 Signed 2022-02-14 2022-03-07 2022-02-24 2022-03-15 2022-04-30 2022-03-23 2022-05-31 mercialization and Nutrition g grants Beneficiaries LS-MAFS-275560-CS-CDS / Improving Agricultural Com Service Provider for Matchin IDA / 64220 Post Direct Selection Direct 3,000.00 99.10 Signed 2022-02-14 2022-03-07 2022-02-24 2022-03-15 2022-04-30 2022-03-17 2022-05-31 mercialization and Nutrition g grants Beneficiaries LS-MAFS-275561-CS-CDS / Improving Agricultural Com Service Provider for Matchin IDA / 64220 Post Direct Selection Direct 3,000.00 99.10 Signed 2022-02-14 2022-03-07 2022-02-24 2022-03-15 2022-04-30 2022-03-24 2022-05-31 mercialization and Nutrition g Grants Beneficiaries LS-MAFS-275544-CS-CDS / Improving Agricultural Com Service Provider for Matchin IDA / 64220 Post Direct Selection Direct 3,000.00 99.67 Signed 2022-02-14 2022-03-02 2022-02-24 2022-03-15 2022-04-30 2022-03-18 2022-05-31 mercialization and Nutrition g Grants Beneficiaries LS-MAFS-275556-CS-CDS / Improving Agricultural Com Service Provider for Matchin IDA / 64220 Post Direct Selection Direct 3,000.00 0.00 Canceled 2022-02-14 2022-03-07 2022-02-24 2022-03-15 2022-04-30 2022-05-31 mercialization and Nutrition g Grants Beneficiaries LS-MAFS-263239-CS-INDV / Promoting Climate Smart A Individual Consult Development of Training Ma IDA / 64220 gricultural Practices and Ad Post Open 43,000.00 67,169.42 Signed 2021-11-18 2022-02-25 2022-01-06 2022-03-21 2022-01-27 2022-03-21 2022-03-03 2022-04-09 2022-08-30 ant Selection nual for Climate-Smart Agric visory Services ulture LS-MAFS-263240-CS-INDV / Improving Agricultural Com Individual Consult Technical Reviewer of Match IDA / 64220 Post Open 3,000.00 50.00 Completed 2021-11-18 2022-02-22 2022-01-17 2022-03-16 2022-02-07 2022-03-16 2022-03-14 2022-03-08 2022-09-10 2022-05-19 mercialization and Nutrition ant Selection ing Grant Applications LS-MAFS-275551-CS-CDS / Improving Agricultural Com Service Provider for Matchin IDA / 64220 Post Direct Selection Direct 3,000.00 99.67 Signed 2022-02-14 2022-03-07 2022-02-24 2022-03-15 2022-04-30 2022-03-22 2022-05-31 mercialization and Nutrition g grants Beneficiaries LS-MAFS-261212-CS-INDV / Promoting Climate Smart A Individual Consult Design and supervision of n IDA / 64220 gricultural Practices and Ad Post Open 67,000.00 149,020.00 Signed 2021-11-30 2022-02-08 2022-01-18 2022-04-07 2022-02-08 2022-04-11 2022-03-15 2022-04-13 2022-09-11 ant Selection ew irrigation schemes visory Services LS-MAFS-261214-CS-INDV / Promoting Climate Smart A Individual Consult Capacity building of Water U IDA / 64220 gricultural Practices and Ad Post Open 94,040.00 54,946.05 Signed 2021-11-30 2022-02-25 2022-01-18 2022-04-07 2022-02-08 2022-04-07 2022-03-15 2022-04-23 2022-09-11 ant Selection sers Association Consultanc visory Services y LS-MAFS-259038-CS-CDS / Improving Agricultural Com IDA / 64220 Post Direct Selection Direct 87,000.00 1,300,000.00 Signed 2022-02-20 2022-02-17 2022-03-02 2022-03-08 2022-05-06 2022-06-14 2022-11-02 NGO -Service Provide mercialization and Nutrition LS-MAFS-275554-CS-CDS / Improving Agricultural Com Service Provider for matchin IDA / 64220 Post Direct Selection Direct 3,000.00 99.10 Signed 2022-02-14 2022-03-07 2022-02-24 2022-03-15 2022-04-30 2022-03-23 2022-05-31 mercialization and Nutrition g Grants Beneficiaries LS-MAFS-161893-CS-INDV / Project Management, Coord Individual Consult Pending Impleme IDA / 64220 Post Open 180,000.00 0.00 2023-04-21 2023-06-09 2023-06-30 2023-08-04 2026-01-31 Irrigation Engineer based in ination and Monitoring and ant Selection ntation PMU office Evaluation LS-MAFS-282002-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 152,259.76 Signed 2022-03-21 2022-03-04 2022-05-09 2022-05-17 2022-05-30 2022-06-06 2022-07-04 2022-06-01 2022-12-31 Matching grants Specialist ination and Monitoring and ant Selection Evaluation LS-MAFS-299316-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 210,000.00 0.00 Signed 2022-06-17 2022-06-14 2022-08-05 2022-08-31 2022-08-26 2022-10-20 2022-09-30 2025-10-31 PMU Information Technology ination and Monitoring and ant Selection Manager Evaluation LS-MAFS-299326-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 95,000.00 0.00 Signed 2022-06-17 2022-06-14 2022-08-05 2022-08-24 2022-08-26 2022-09-20 2022-09-30 2025-10-31 Project Field Officer for Thab ination and Monitoring and ant Selection a-Tseka Evaluation LS-MAFS-303097-CS-INDV / Project Management, Coord Individual Consult IDA / 64220 Post Open 227,000.00 0.00 Signed 2022-07-14 2022-07-08 2022-09-26 2022-09-23 2022-10-17 2022-09-28 2022-11-21 2024-10-31 Procurement Specialist for P ination and Monitoring and ant Selection MU Evaluation LS-MAFS-312375-CS-INDV / Project Management, Coord Knowledge Management or Individual Consult IDA / 64220 ination and Monitoring and Post Open - National 210,000.00 0.00 Signed 2022-08-31 2022-08-29 2022-10-19 2022-11-28 2022-11-09 2022-12-01 2022-12-14 2025-07-27 Communication Specialist - ant Selection Evaluation Permanent staff member LS-MAFS-328093-CS-INDV / Youth Mentorship programe Promoting Climate Smart A Individual Consult Under Implement e consultancy to provide tec IDA / 64220 gricultural Practices and Ad Post Open - National 6,666.67 0.00 2022-11-23 2023-02-23 2023-01-11 2023-02-27 2023-02-01 2023-05-05 2023-03-08 2023-09-04 ant Selection ation hnical expertise to SADP in t visory Services he matching grant departm ent. LS-MAFS-340934-CS-INDV / Project Management, Coord Engagement of individual co Individual Consult Under Implement IDA / 64220 ination and Monitoring and Post Open - National 85,860.31 0.00 2023-02-10 2023-02-09 2023-03-31 2023-04-21 2023-05-26 2023-11-22 nsultant to preform Project F ant Selection ation Evaluation ield Officers duties in Berea District LS-MAFS-341552-CS-INDV / Project Management, Coord Individual Consult Under Implement Engagement of Monitoring a IDA / 64220 ination and Monitoring and Post Open - National 96,446.70 0.00 2023-02-17 2023-02-22 2023-04-07 2023-04-28 2023-06-02 2023-11-29 ant Selection ation nd Evaluation Specialist Evaluation LS-MAFS-355401-CS-INDV / Project Management, Coord Individual Consult Under Implement Individual consultancy for se IDA / 64220 ination and Monitoring and Post Open - National 85,000.00 0.00 2023-05-08 2023-05-26 2023-06-26 2023-07-17 2023-08-21 2024-02-17 ant Selection ation rvices of project field officer Evaluation Maseru LS-MAFS-362298-CS-INDV / Promoting Climate Smart A Individual Consult Under Implement EMPLOYMENT OF MATCHING IDA / 64220 gricultural Practices and Ad Post Open - National 119,248.50 0.00 2023-05-26 2023-05-23 2023-07-14 2023-08-04 2023-09-08 2024-03-06 ant Selection ation GRANTS OFFICER visory Services LS-MAFS-362309-CS-INDV / Promoting Climate Smart A Individual Consult Under Implement Engagement of data clerk fo IDA / 64220 gricultural Practices and Ad Post Open - National 86,100.00 0.00 2023-05-31 2023-05-26 2023-07-19 2023-08-09 2023-09-13 2024-03-11 ant Selection ation r Matching Grants departme visory Services nt LS-MAFS-362312-CS-INDV / Promoting Climate Smart A Individual Consult Under Implement Engagement of Data Clerk f IDA / 64220 gricultural Practices and Ad Post Open - National 86,100.00 0.00 2023-05-31 2023-05-26 2023-07-19 2023-08-09 2023-09-13 2024-03-11 ant Selection ation or Matching Grants departm visory Services ent LS-MAFS-368220-CS-CDS / Project Management, Coord Pending Impleme Engagement of Individual C IDA / 64220 ination and Monitoring and Post Direct Selection Direct - National 7,987.40 0.00 2023-06-23 2023-07-03 2023-09-06 2024-03-04 ntation onsultant to review PIM Evaluation Page 14 PROCUREMENT PLAN (Textual Part) Project information: Country: Guyana Project Name: Guyana Strengthening Human Capital through Education Project (GHCP) Project Number: P177741 Project Implementation agency: Ministry of Education Date of the Procurement Plan: September 21, 2022 Period covered by this Procurement Plan: September 21, 2022, to September 20, 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Act of 2003 and regulations, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables]; Works: is not applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Guyana : Guyana Strengthening Human Capital through Education Project PLAN General Information Country: Guyana 2022-09-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177741 GPN Date: Project Name: Guyana Strengthening Human Capital through Education Project Loan / Credit No: IDA / 71330 Ministry of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Improve Servi GY-MOE-312412-GO-RFB / Pr ce Delivery and Enhance the Single Stage - One E Under Imple IDA / 71330 Post Request for Bids Open - National 278,927.00 0.00 2022-09-12 2023-02-13 2022-09-14 2023-02-22 2022-10-26 2023-03-14 2022-11-25 2022-12-16 2023-03-16 ocurement of Textbooks Learning Environment at the nvelope mentation Secondary Level Component 1: Improve Servi GY-MOE-303409-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Post Direct Selection 1,186,000.00 0.00 2022-09-12 2022-11-11 2022-09-20 2023-02-07 2022-10-31 2023-01-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level Component 1: Improve Servi GY-MOE-303375-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Post Direct Selection 343,246.00 0.00 2022-07-13 2022-11-11 2022-07-21 2023-02-07 2022-08-31 2022-11-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level Component 1: Improve Servi GY-MOE-303402-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Post Direct Selection 644,400.00 0.00 2022-09-12 2022-11-11 2022-09-20 2023-02-07 2022-10-31 2023-01-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level Component 1: Improve Servi GY-MOE-303405-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Prior Direct Selection 4,277,600.00 0.00 2022-09-12 2022-11-14 2022-09-20 2023-02-09 2022-10-31 2023-01-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level Component 1: Improve Servi GY-MOE-303401-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Post Direct Selection 757,427.00 0.00 2022-09-12 2022-11-11 2022-09-20 2023-02-07 2022-10-31 2023-01-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level Component 1: Improve Servi GY-MOE-303410-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Post Direct Selection 510,400.00 0.00 2022-09-12 2022-11-11 2022-09-20 2023-02-07 2022-10-31 2023-01-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level GY-MOE-361539-GO-RFQ / O Component 4: Project Manag Request for Quota Single Stage - One E IDA / 71330 Post Limited 4,000.00 0.00 Canceled 2023-05-28 2023-07-12 2023-08-11 ffice Furniture ement and Monitoring and E tions nvelope valuation GY-MOE-360008-GO-RFQ / O Component 4: Project Manag Request for Quota Single Stage - One E Under Imple IDA / 71330 Post Limited 10,000.00 0.00 2023-05-30 2023-05-31 2023-06-24 2023-07-24 ffice Equipment ement and Monitoring and E tions nvelope mentation valuation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY-MOE-329249-CS-QCBS / Component 2: Strengthen Sk Consultant Qualifi Open - Internationa Under Implement Tracer Study of TVET Gradua IDA / 71330 ills Development and Techni Post 300,000.00 0.00 2023-01-03 2022-12-01 2023-01-24 2023-01-12 2023-02-21 2023-03-13 2023-04-27 2023-10-24 cation Selection l ation tes cal and Vocational Training GY-MOE-329251-CS-QCBS / Component 2: Strengthen Sk Consultant Qualifi Open - Internationa Under Implement National Skills Audit Consulta IDA / 71330 ills Development and Techni Post 150,000.00 0.00 2023-01-03 2022-12-01 2023-01-24 2023-01-12 2023-02-08 2023-02-28 2023-04-14 2023-10-11 cation Selection l ation ncy cal and Vocational Training INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY-MOE-317475-CS-INDV / P Component 4: Project Manag Individual Consult IDA / 71330 Post Open - National 71,691.00 0.00 Canceled 2022-11-01 2022-09-29 2022-12-20 2022-12-23 2023-01-10 2024-01-10 roject Coordinator ement and Monitoring and E ant Selection valuation GY-MOE-343185-CS-INDV / P Component 4: Project Manag Individual Consult IDA / 71330 Post Open - National 47,100.00 0.00 Signed 2023-02-26 2023-02-27 2023-03-21 2023-05-11 2023-03-24 2023-05-11 2023-04-02 2024-04-01 roject Engineer ement and Monitoring and E ant Selection valuation GY-MOE-343188-CS-INDV / Component 4: Project Manag Individual Consult IDA / 71330 Post Open - National 31,400.00 0.00 Signed 2023-02-26 2023-02-27 2023-03-30 2023-05-04 2023-03-31 2023-05-10 2023-05-01 2024-04-30 Monitoring & Evaluation Offic ement and Monitoring and E ant Selection er valuation GY-MOE-343179-CS-CDS / Pr Component 4: Project Manag Individual Consult IDA / 71330 Post Direct - National 6,000.00 0.00 Signed 2023-02-22 2023-02-25 2023-02-24 2023-03-22 2023-02-26 2023-03-24 2023-02-28 2023-08-31 ocurement Officer (shared) ement and Monitoring and E ant Selection valuation Page 1 GY-MOE-343183-CS-CDS / Fi Component 4: Project Manag Individual Consult IDA / 71330 Post Direct - National 6,000.00 0.00 Signed 2023-02-22 2023-02-27 2023-02-24 2023-03-24 2023-02-26 2023-03-24 2023-02-28 2023-09-30 nance Officer (shared) ement and Monitoring and E ant Selection valuation GY-MOE-346230-CS-INDV / P Component 4: Project Manag Individual Consult IDA / 71330 Post Direct - National 71,691.00 0.00 Signed 2023-03-01 2023-03-10 2023-03-04 2023-03-14 2023-03-06 2023-03-16 2023-03-31 2024-03-30 roject Coordinator ement and Monitoring and E ant Selection valuation GY-MOE-346231-CS-INDV / S Component 4: Project Manag Individual Consult IDA / 71330 Post Direct - National 6,000.00 0.00 Signed 2023-03-01 2023-03-12 2023-03-05 2023-05-24 2023-03-07 2023-05-24 2023-04-02 2024-04-01 ocial Specialist (Part-time) ement and Monitoring and E ant Selection valuation GY-MOE-355798-CS-INDV / F Component 4: Project Manag Individual Consult Under Implement IDA / 71330 Post Open - National 24,000.00 0.00 2023-04-20 2023-04-16 2023-05-30 2023-06-04 2023-06-19 2024-06-18 inance Assistant ement and Monitoring and E ant Selection ation valuation GY-MOE-355800-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / 71330 Post Open - National 24,000.00 0.00 2023-04-20 2023-04-16 2023-05-30 2023-06-04 2023-06-19 2024-06-18 rocurement Assistant ement and Monitoring and E ant Selection ation valuation GY-MOE-355814-CS-CDS / E Component 4: Project Manag Under Implement IDA / 71330 Post Direct Selection Direct - National 8,000.00 0.00 2023-05-23 2023-05-22 2023-06-09 2023-06-29 2024-06-28 nvironmental Specialist (Part ement and Monitoring and E ation Time) valuation Component 1: Improve Servi GY-MOE-361519-CS-CDS / Sc ce Delivery and Enhance the Under Implement IDA / 71330 Post Direct Selection Direct - National 35,000.00 0.00 2023-05-18 2023-06-09 2023-05-28 2023-06-14 2023-10-12 hool Facility Plan Learning Environment at the ation Secondary Level GY-MOE-365697-CS-INDV / D Component 4: Project Manag Individual Consult Under Implement IDA / 71330 Post Open - National 150,000.00 0.00 2023-06-11 2023-06-14 2023-07-20 2023-07-21 2023-08-07 2024-08-06 evelopment of TVET Policy ement and Monitoring and E ant Selection ation valuation Page 2 Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [This is the first procurement plan) 2. Date of General Procurement Notice: April 25, 2017 3. Period covered by this procurement plan: September 2016 to June 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) NA 3. ICB (Works) Above US$ 7 million All 4. NCB (Works) NA 5. ICB and LIB (Non-Consultant Above US$ 1,500,000 All Services) 6 NCB (Non-Consultant Services) NA [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [CDD project implementation Manual to be issued by DRDIP PIU, MoANR for Bank approval) 4. Reference to (if any) Project Operational/Procurement Manual: DRDIP Procurement Manual to be issued by DRDIP PIU. 5. Any Other Special Procurement Arrangements: NA 6. Summary of the Procurement Packages planned during the first 18 July 9, 2010 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary NA NA NA NA of the ICB (Works) Summary 6.69 4 No Prior of the ICB (Goods) Summary 3.8 9 No Post All of the NCB (Works) Summary 14.70 14 No Post All of the NCB (Goods) Summary NA NA NA NA of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Commentes Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA July 9, 2010 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 0.35 2 Prior of number of contracts that will be let under QCBS Summary 1.4 38 Post LCS/ IC of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Eastern and Southern Africa : Development Response to Displacement Impacts Project in the HoA PLAN General Information Country: Eastern and Southern Africa 2017-10-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152822 GPN Date: Project Name: Development Response to Displacement Impacts Project in the HoA Loan / Credit No: IDA / 58330, IDA / 58210, IDA / 66660 Agence Djiboutienne de Development Social Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned COMP1/T1/2017 / Travaux d' Social and Economic Service Single Stage - One E 2018-12-0 extension de 5 salles de Lycé IDA / 58330 Post Request for Bids Open - National 325,070.00 375,984.42 Signed 2018-02-10 2018-09-24 2018-02-17 2018-03-31 2018-11-07 2018-04-30 2018-12-04 2018-06-04 2018-12-14 s and Infrastructure nvelope 1 e et réhabilitation du dortoir à Obock COMP1/T3/2017 / Travaux d Social and Economic Service Single Stage - One E 2018-09-1 IDA / 58330 Post Request for Bids Open - National 450,704.00 0.00 Canceled 2017-11-20 2017-11-27 2018-01-08 2018-02-07 2018-03-14 e raccordement pecherie d'O s and Infrastructure nvelope 0 bock COMP1/T8/2017 / constructi Social and Economic Service Request for Quota Single Stage - One E 2018-11-0 on de locaux communautaire IDA / 58330 Post Limited 101,408.00 95,992.16 Signed 2018-03-17 2018-10-22 2018-05-12 2019-01-14 s and Infrastructure tions nvelope 8 /communautaire à Ali addé COMP1/T9/2017 / Réhabilitat Social and Economic Service Request for Quota Single Stage - One E 2018-10-1 ion du local communautaire ( IDA / 58330 Post Limited 40,000.00 33,579.56 Signed 2018-02-17 2018-10-22 2018-04-14 2019-01-14 s and Infrastructure tions nvelope 1 UNFD) à Holl-Holl DJ-ADDS-29135-CW-RFB / Tr Social and Economic Service Single Stage - One E 2018-06-0 avaux extention du centre de IDA / 58330 Post Request for Bids Open - National 399,493.00 264,611.20 Signed 2017-10-31 2017-05-29 2017-11-05 2017-12-05 2017-07-16 2018-02-08 2017-09-11 s and Infrastructure nvelope 8 santé à Obock DJ-ADDS-29136-CW-RFB / re habilitation/ extention du cen Social and Economic Service Single Stage - One E 2018-08-0 IDA / 58330 Post Request for Bids Open - National 436,620.00 60,014.06 Signed 2017-10-31 2017-05-29 2017-11-05 2017-12-05 2017-07-09 2018-01-04 2017-08-08 2018-02-08 2017-09-11 tre de santé Ali addé et Hol H s and Infrastructure nvelope 7 ol en 2 lots séparés DJ-ADDS-29129-CW-DIR / Tr Social and Economic Service 1,188,375.0 2019-04-2 avaux d'extension Résau/ Ele IDA / 58330 Prior Direct Selection Direct 1,188,371.09 Signed 2017-09-19 2019-05-14 2017-10-04 2020-09-23 2017-10-27 2017-12-22 s and Infrastructure 0 5 ctricité d'Obock et Holl-Holl 004/2017/TVX/IDA-PRDDCA/ ADDS / avenant n°1 au marc Social and Economic Service 210,936,565. 2019-09-2 IDA / 58330 Prior Direct Selection Direct 0.00 Canceled 2019-02-21 2019-02-26 2019-04-02 hé des travaux d'électrificati s and Infrastructure 00 9 on Holhol et extension résea u electrique d'Obock COMP1/T5/2017 / F+P et rac cordement des installations é Social and Economic Service Single Stage - One E 2018-05-1 lectriques des logements, lo IDA / 58330 Post Request for Bids Open - National 241,392.00 324,046.72 Signed 2017-10-31 2018-03-29 2017-11-07 2017-12-07 2018-05-02 2018-01-06 2018-06-20 2018-02-10 2018-06-26 s and Infrastructure nvelope 1 caux commerciaux et établis sements publics à Holl-Holl COMP4/T1/2019 / Travaux d Project Management, and M Single Stage - One E 2020-06-2 IDA / 58330 Post Request for Bids Open - National 185,915.00 143,370.91 Signed 2019-09-08 2019-10-21 2019-09-13 2019-10-25 2019-12-11 2019-11-24 2020-01-27 2019-12-29 2020-02-03 e construction d'une salle d'a onitoring and Evaluation nvelope 6 rchives COMP1/T7/2017 / Travaux d Social and Economic Service Single Stage - One E 2020-06-2 e construction d'une piste en IDA / 58330 Post Request for Bids Open - National 662,423.00 851,773.84 Signed 2019-09-08 2018-11-01 2019-09-13 2021-01-19 2019-10-25 2019-03-06 2019-11-24 2019-04-10 2019-12-29 2019-08-18 s and Infrastructure nvelope 6 pierres taillées (voiries Oboc k) COMP1/T6/2017 / Travaux d e construction de logements Social and Economic Service Single Stage - One E 2018-05-0 IDA / 58330 Post Request for Bids Open - National 1,616,902.00 53,413.47 Signed 2017-10-31 2018-10-15 2017-11-05 2017-12-05 2018-12-06 2018-01-04 2018-12-30 2018-02-08 2019-01-14 de fonction et réhabilitation s and Infrastructure nvelope 9 de l’école primaire et collège de Holl Holl. COMP2/T2/2017 / rénovation Social and Economic Service Request for Quota Single Stage - One E 2018-06-2 et renforcement de perimetr IDA / 58330 Post Limited 186,183.00 0.00 Canceled 2017-11-01 2017-12-27 s and Infrastructure tions nvelope 5 es existants pour Holhol COMP2/T3/2017 / rénovation et renforcement de perimetr Social and Economic Service Request for Quota Single Stage - One E 2018-06-2 IDA / 58330 Post Limited 149,000.00 0.00 Canceled 2017-11-01 2017-12-27 es existants d'où 5 reservoirs s and Infrastructure tions nvelope 5 , 5 puits, 5 champs solaires pour Ali Addé COMP1/T1/2019 / Travaux d Social and Economic Service 2020-04-1 e réhabilitation et d'extensio IDA / 58330 Post Direct Selection Direct 87,417.00 87,159.13 Signed 2019-09-08 2019-08-06 2019-09-13 2019-08-13 2019-10-18 2019-08-29 s and Infrastructure 5 n du Centre de Santé de Holl Holl.. COMP1/T7/2019 / Travaux d e rénovation d'électricité pou Social and Economic Service Request for Quota Single Stage - One E 2020-06-2 IDA / 58330 Post Limited 13,000.00 12,299.96 Signed 2019-11-02 2019-10-15 2019-12-28 2019-11-06 r la salle d'urgence et salle d' s and Infrastructure tions nvelope 5 hospitalisation du CMH d'Obo ck COMP1/T5/TVX/2019 / Rénov Social and Economic Service Single Stage - One E 2020-09-0 IDA / 58330 Post Request for Bids Open - National 107,042.00 102,232.86 Signed 2019-11-19 2019-11-10 2019-11-24 2020-08-24 2020-01-05 2020-01-29 2020-02-04 2020-03-08 2020-03-10 2020-03-13 ation des locaux de l'UNFD à s and Infrastructure nvelope 6 Obock COMPT1/T3/2010 / travaux d e raccordement de nouveaux forages, réalisation de condui Social and Economic Service 1,335,723.2 2020-06-1 IDA / 58330 Post Direct Selection Direct 1,339,674.00 Signed 2020-02-04 2020-02-19 2020-02-09 2015-11-01 2020-03-15 2020-06-11 te d'adduction d'eau et chan s and Infrastructure 8 3 gements des conduites vétus tes de distribution d'eau à Ob ock COMP1/T5/2019 / Travaux d Social and Economic Service Single Stage - One E 2021-07-3 e rénovation des locaux de l' IDA / 58330 Post Request for Bids Open - National 107,042.00 102,232.86 Signed 2020-10-11 2019-11-21 2020-10-16 2020-11-15 2020-11-27 2019-12-25 2020-12-27 2020-03-18 2021-01-31 2020-03-21 s and Infrastructure nvelope 0 UNFD à Obock COMP1/T3/2019 / Réalisation à Obock des travaux de racc ordement de 05 forages, de Social and Economic Service 1,335,723.2 2020-04-1 changement de la conduite p IDA / 58330 Post Direct Selection Direct 1,339,674.00 Signed 2019-09-08 2019-10-19 2019-09-13 2019-10-14 2019-10-18 2020-07-06 s and Infrastructure 8 5 rincipale reliant les forages au réservoir existant de la vil le et de changement d'une p artie vetuste du réseau de di stribution Page 1 COMPT1/T7/2019 / Fournitur e +Pose et raccordement des Social and Economic Service Request for Quota Single Stage - One E 2020-07-0 installations électriques des IDA / 58330 Post Open - National 164,380.00 146,159.28 Signed 2020-02-09 2020-11-15 2020-04-05 2020-07-24 s and Infrastructure tions nvelope 4 logements, mis en conformit é de 200 logements à obock COMP1/T1/2021 / Fourniture Social and Economic Service 2021-10-0 +Pose d'un reservoir d'eau p IDA / 58330 Post Direct Selection Direct 11,493.00 11,459.07 Completed 2021-02-24 2021-02-14 2021-03-01 2021-03-18 2021-04-05 2021-05-12 s and Infrastructure 2 our le local communautaire d 'Ali addé COMP1/TX1/2021 / Réhabilit Social and Economic Service Single Stage - One E 2021-12-1 ation d’un hangar et de deux IDA / 58330 Post Request for Bids Open - National 84,507.00 45,049.86 Signed 2021-03-01 2021-08-11 2021-03-06 2021-04-17 2021-12-08 2021-05-17 2022-01-19 2021-06-21 2022-04-11 s and Infrastructure nvelope 8 stocks à Ali-Sabieh pour le M ASS COMP1/TX2/2021 / Travaux d’Extension pavillon matérnit Social and Economic Service Single Stage - One E 2021-12-1 IDA / 58330 Post Request for Bids Open - National 140,845.00 198,660.35 Signed 2021-03-01 2020-10-05 2021-03-06 2021-04-17 2020-12-10 2021-05-17 2020-12-09 2021-06-21 2020-12-18 é + réhabilitation couloir bloc s and Infrastructure nvelope 8 opératoire a Obock CPMP1/TX3/2021 / Construct Social and Economic Service Single Stage - One E Under Imple 2021-12-1 ion de deux casernes de pom IDA / 58330 Post Request for Bids Open - National 1,070,423.00 0.00 2021-03-01 2021-10-03 2021-03-06 2021-04-17 2021-05-17 2021-06-21 s and Infrastructure nvelope mentation 8 piers (Ali sabieh et obock ) COMP1/TX4/2021 / Construct Social and Economic Service Single Stage - One E Under Imple 2021-12-1 IDA / 58330 Post Request for Bids Open - National 112,676.00 0.00 2021-03-01 2021-10-03 2021-03-06 2021-04-17 2021-12-08 2021-05-17 2022-01-19 2021-06-21 ion d'un hangar à Obock s and Infrastructure nvelope mentation 8 COMP1/TX5/2021 / Travaux Social and Economic Service Single Stage - One E 2021-12-1 d'extension du centre de san IDA / 58330 Post Request for Bids Open - National 219,718.00 250,693.22 Signed 2021-03-01 2020-12-15 2021-03-06 2021-04-17 2021-01-20 2021-05-17 2021-03-01 2021-06-21 2021-03-18 s and Infrastructure nvelope 8 té de HOLHOL COMP2/TX3/2021 / Réhabilit Sustainable Environmental Single Stage - One E 2021-12-1 IDA / 58330 Post Request for Bids Open - National 662,873.00 246,399.78 Signed 2021-03-01 2021-03-04 2021-03-06 2021-04-17 2021-04-07 2021-05-17 2021-05-30 2021-06-21 2021-06-21 ation des périmètres existant Management nvelope 8 s COMP2/TX4/2021 / Création Sustainable Environmental Single Stage - One E 2021-12-1 IDA / 58330 Post Request for Bids Open - National 342,257.00 0.00 Canceled 2021-03-01 2021-03-06 2021-04-17 2021-05-17 2021-06-21 de nouveaux périmètres Management nvelope 8 COMP1/TX6/2021 / Réhabilit Social and Economic Service Single Stage - One E 2021-12-1 IDA / 58330 Post Request for Bids Open - National 200,000.00 461,024.97 Signed 2021-03-01 2021-05-06 2021-03-06 2021-04-17 2021-07-14 2021-05-17 2021-08-11 2021-06-21 2021-08-16 ation d’un parc (obock) s and Infrastructure nvelope 8 COMP1/T6/2019 / petits trav Social and Economic Service Request for Quota Single Stage - One E 2020-07-1 aux de raccordement eau et IDA / 58330 Post Limited 30,000.00 0.00 Canceled 2019-11-25 2020-01-20 s and Infrastructure tions nvelope 8 électricité pour la pêcherie.. COMP7/T1/2020 / Travaux d Social and Economic Service Single Stage - One E 2022-01-0 e réhabilitation de la cloture IDA / 58330 Post Request for Bids Open - National 235,070.00 87,442.79 Signed 2021-03-17 2020-06-04 2021-03-22 2021-05-30 2021-05-03 2020-07-15 2021-06-02 2020-08-11 2021-07-07 2020-08-27 s and Infrastructure nvelope 3 de l'école primaire d'Obock COMP2/T4/2020 / Travaux d’ Sustainable Environmental Open - Internationa Single Stage - One E 2021-10-2 extension de la centrale solai IDA / 58330 Post Request for Bids 3,500,000.00 0.00 Canceled 2021-01-03 2020-10-25 2021-01-07 2021-01-14 2021-02-18 2021-04-01 2021-03-20 2021-04-24 Management l nvelope 1 re et du réseau de ALI ADDE DJIBOUTI COMP1/TX10/2021 / TRAVAU Request for Quota Social and Economic Service Request for Quota Single Stage - One E 2022-08-1 X DE CONSTRUCTION DES SA IDA / 58330 Post Limited tions (Non Bank-S 27,000.00 27,466.37 Completed 2021-12-21 2021-06-03 2022-02-15 2021-07-14 s and Infrastructure tions nvelope 4 NITAIRES POUR LE COLLEGE PD) DE HOLHOL Request for Bids - COMP2/TX3/2021HH / TRAV Social and Economic Service Single Stage - One E Small Works SPD 2022-11-0 AUX DE REHABILITATION DES IDA / 58330 Post Request for Bids Open - National 149,000.00 296,508.33 Signed 2022-01-17 2021-03-04 2022-01-22 2022-03-05 2021-04-21 2022-04-04 2021-06-02 2022-05-09 2021-06-21 s and Infrastructure nvelope (1 envelope proce 5 PERIMETRES EXISTANTS POU ss) R HOLHOL Request for Bids - COMP2TX1/2022 / TRAVAUX Sustainable Environmental Open - Internationa Single Stage - One E Works French Civi Under Imple 2022-12-1 D’EXTENSION DE LA CENTRA IDA / 58330 Prior Request for Bids 3,500,000.00 0.00 2022-03-02 2022-04-06 2022-03-07 2022-04-18 2022-05-25 2022-05-18 2022-08-04 2022-06-22 Management l nvelope l Law (French) SP mentation 9 LE ET DU RESEAU D’ALI ADD D E Request for Bids - COMP2/TX4/2021BIS / TRAV Sustainable Environmental Single Stage - One E Works French Civi 2022-10-0 AUX DE CONSTRUCTION DE IDA / 58330 Post Request for Bids Open - National 342,257.00 0.00 Canceled 2021-12-16 2021-12-21 2022-02-01 2022-03-03 2022-04-07 Management nvelope l Law (French) SP 4 NOUVEAUX PERIMETRES AGR D ICOLS COMP2/T1/2017 / rénovation et renforcement de perimetr Social and Economic Service Request for Quota Single Stage - One E 2018-06-2 IDA / 58330 Post Limited 135,211.00 0.00 Canceled 2017-11-01 2017-12-27 es existants d'où 5 reservoirs s and Infrastructure tions nvelope 5 , 5 puits , 5 champs solaires pour Obock Request for Bids - COMP3/TX1/ADD2023 / Mise Single Stage - One E Small Works SPD Pending Imp 2024-02-2 en place d'une usine de fabri IDA / 66660 Livelihoods Program Post Request for Bids Open - National 200,000.00 0.00 2023-05-10 2023-05-15 2023-06-26 2023-07-26 2023-08-30 nvelope (1 envelope proce lementation 6 cation de thon ss) COMP2/TX6/2023 / Construct ion d'un reservoir de 30 M3 Social and Economic Service Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-11-2 IDA / 66660 Post Limited 15,775.00 0.00 2023-06-19 2023-07-31 et d'un puits de 12 M de prof s and Infrastructure tions nvelope or explanation) lementation 8 ondeur pour la ferme semenc ière COMP2/TX7/2023 / Travaux de construction d'une cloture Social and Economic Service Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-11-2 IDA / 66660 Post Limited 27,200.00 0.00 2023-06-19 2023-07-31 de 2500 M2, terrassement et s and Infrastructure tions nvelope or explanation) lementation 8 équipements pour la ferme s emencière Request for Bids - COMP2/TX2 / Réhabilitation Sustainable Environmental Single Stage - One E Small Works SPD 2024-02-1 des forages pour les périmètr IDA / 66660 Post Request for Bids Open - National 350,000.00 0.00 Canceled 2023-04-30 2023-05-05 2023-06-16 2023-07-16 2023-08-20 Management nvelope (1 envelope proce 6 es agricoles, citernes enterré ss) es, puits (Obock) COMP II/TX3/2023 ADD / Con struction de citernes enterré Social and Economic Service Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-10-3 es dans la localité de SOUWA IDA / 66660 Post Limited 22,535.00 0.00 2023-06-20 2023-08-01 s and Infrastructure tions nvelope or explanation) lementation 0 LI dans le cadre des réhabilit ation des périmètres agricols à Obock COMP II TX6/2023ADD / Con struction de citernes enterré Social and Economic Service Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-10-3 IDA / 66660 Post Limited 22,535.00 0.00 2023-06-20 2023-08-01 es dans la localité de WAYBO s and Infrastructure tions nvelope or explanation) lementation 0 L dans le cadre des périmètr es agricols a Obock COMP II/TX7/2023ADD / Con struction de 2 reservoirs de 4 Social and Economic Service Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-10-3 IDA / 66660 Post Limited 33,802.00 0.00 2023-06-20 2023-08-01 0M3 à ILISOLA et SOUBLALI d s and Infrastructure tions nvelope or explanation) lementation 0 ans le cadre des périmètres agricols à Obock COMP II /TX8/2023ADD / Pla Sustainable Environmental Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-10-3 IDA / 66660 Post Limited 27,605.00 0.00 2023-06-20 2023-08-01 ntation d'arbres dans la vile Management tions nvelope or explanation) lementation 0 d'Obock Page 2 COMP2/TX2/ADD2023 / Trav Request for Bids - aux d'amenagement hydro-a Sustainable Environmental Single Stage - One E Small Works SPD Pending Imp 2023-12-1 IDA / 66660 Post Request for Bids Open - National 45,950.00 0.00 2023-06-25 2023-06-30 2023-07-30 2023-08-14 2023-09-11 gricol du terrain à ASSAMO (l Management nvelope (1 envelope proce lementation 0 ocal technique * stockage) ss) Request for Bids - COMP3/TX1/2021 / Construct Single Stage - One E Small Works SPD Pending Imp 2023-07-3 ion d"un marché communaut IDA / 66660 Livelihoods Program Post Request for Bids Open - National 250,000.00 0.00 2022-10-12 2022-10-17 2022-11-28 2022-12-28 2023-02-01 nvelope (1 envelope proce lementation 1 aire a Obock ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP1/F2/2017 / achat de M atériels informatique pour le Social and Economic Service Request for Quota Single Stage - One E IDA / 58330 Post Limited 30,000.00 137,081.90 Signed 2017-10-07 2019-03-29 2017-12-02 2018-06-01 2018-05-31 s lycées bénéficiaires pour le s and Infrastructure tions nvelope compte de l'Education Inform atique COMP1/F4/2017 / equipeme Social and Economic Service nts médicaux et Mobiliers po IDA / 58330 Prior Direct Selection Direct 1,305,900.00 650,947.00 Signed 2017-10-20 2018-05-31 2017-10-20 2020-06-24 2017-12-01 2018-02-08 2018-05-30 s and Infrastructure ur Obock,Ali Addé et Hol Hol COMP2/F2/2017 / achat de matériels pour périmetres ex Social and Economic Service Single Stage - One E IDA / 58330 Post Request for Bids Open - National 166,667.00 67,316.40 Signed 2017-10-05 2017-11-16 2017-10-12 2017-11-23 2017-12-27 2017-12-23 2018-01-09 2018-01-27 2018-01-24 2018-07-26 istants d'où motopompes, br s and Infrastructure nvelope ouettes... pour Obock COMP4/F1/2017 / acquisition Social and Economic Service Single Stage - One E d'une pick up et de 2 voiture IDA / 58330 Post Request for Bids Open - National 124,213.00 142,010.26 Signed 2017-10-02 2017-04-13 2017-10-09 2017-11-20 2017-05-14 2017-12-20 2017-05-18 2018-01-24 2017-06-18 2018-07-23 s and Infrastructure nvelope s 4X4. HARD TOP COMP4/F2/2017 / acquisition Social and Economic Service Request for Quota Single Stage - One E IDA / 58330 Post Limited 30,000.00 28,970.66 Signed 2017-10-09 2017-08-16 2017-12-04 2017-09-12 2018-06-02 de tablettes pour l'enquete s and Infrastructure tions nvelope COMP4/F4/2017 / acquisition Social and Economic Service Single Stage - One E Pending Impl d' équipement pour le centre IDA / 58330 Post Request for Bids Open - National 84,507.00 0.00 2017-10-03 2017-10-10 2017-11-21 2017-12-21 2018-01-25 2018-07-24 s and Infrastructure nvelope ementation de formation de l'ONARS COMP1/F3/2017 / achat de M Social and Economic Service Single Stage - One E atériels de SVT et Physique p IDA / 58330 Post Request for Bids Open - National 135,201.00 91,577.55 Signed 2017-10-31 2019-10-16 2017-11-05 2017-12-05 2019-11-20 2018-01-04 2020-01-29 2018-02-08 2020-06-08 2018-04-09 s and Infrastructure nvelope our le Ministère de l'Educatio on Nationale COMP2/F3/2017 / achat de matériels pour périmetres ex Social and Economic Service Open - Internationa Single Stage - One E IDA / 58330 Post Request for Bids 333,334.00 129,599.81 Signed 2017-10-31 2017-11-16 2017-11-07 2017-12-19 2017-12-27 2018-01-18 2018-01-09 2018-02-22 2018-01-24 2018-06-22 istants d'où motopompes, br s and Infrastructure l nvelope ouettes... pour Ali Addé et Ho lHol COMP3/F1BIS/2017 / Acquisi Social and Economic Service Request for Quota Single Stage - One E IDA / 58330 Post Limited 20,000.00 20,109.35 Signed 2017-11-05 2017-06-26 2017-12-31 2017-07-12 2018-01-20 tion de kits culinaires pour le s and Infrastructure tions nvelope s GEA COMP3/F1/2017 / acquisition de matériels et consommabl Social and Economic Service Single Stage - One E IDA / 58330 Post Request for Bids Open - National 180,000.00 26,209.81 Signed 2017-10-31 2019-03-19 2017-11-05 2017-12-05 2019-04-02 2018-01-04 2019-04-08 2018-02-08 2019-04-10 2018-04-09 es pour les groupements de f s and Infrastructure nvelope emmes et jeunes COMP4/F3/2017 / acquisition Social and Economic Service Request for Quota Single Stage - One E de logiciel pour l'analyse des IDA / 58330 Post Limited 25,000.00 24,926.28 Signed 2017-11-17 2018-04-07 2018-01-12 2018-02-22 2018-07-11 s and Infrastructure tions nvelope données des enquetes COMP1/F1/2017 / Equipeme nts chauds et Froid pour les l Social and Economic Service Open - Internationa Single Stage - One E ycés techniques d' Ali Sabie IDA / 58330 Post Request for Bids 428,391.00 392,650.91 Signed 2017-10-05 2018-03-29 2017-10-12 2017-11-23 2018-05-02 2017-12-23 2018-06-04 2018-01-27 2018-06-11 2018-07-26 s and Infrastructure l nvelope h et Obock pour le Ministère de l' Education Nationale COMP1/F4/2019 / acquisition Project Management, and M Single Stage - One E de chambres froides positive IDA / 58330 Post Request for Bids Open - National 123,944.00 78,248.74 Signed 2019-09-08 2019-06-20 2019-09-13 2019-10-25 2019-08-07 2019-11-24 2019-09-17 2019-12-29 2019-10-03 2020-06-26 onitoring and Evaluation nvelope s pour la pecherie COMP1/F5/2019 / Acquisition Regional Support for Coordin Single Stage - One E de boutres, et autres matéri IDA / 58330 ation, Capacity and Knowled Post Request for Bids Open - National 275,000.00 0.00 Canceled 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 nvelope els etc.. pour les pecheurs d' ge obock COMP1/F6/2019 / Acquisition Regional Support for Coordin Single Stage - One E d'équipements pours les dor IDA / 58330 ation, Capacity and Knowled Post Request for Bids Open - National 56,338.00 24,152.51 Signed 2019-09-08 2019-09-23 2019-09-13 2019-10-25 2019-10-06 2019-11-24 2019-10-10 2019-12-29 2019-10-14 2020-06-26 nvelope toirs et réfectoires d'Obock ge COMP1/F2/2019 / Acquisition Regional Support for Coordin Single Stage - One E d'équipements pour l'UNFD à IDA / 58330 ation, Capacity and Knowled Post Request for Bids Open - National 99,000.00 77,028.25 Signed 2019-09-08 2020-07-05 2019-09-13 2019-10-25 2020-07-23 2019-11-24 2020-07-23 2019-12-29 2021-02-22 2020-06-26 nvelope Holhol, Ali addé et Obock ge COMP1/F2/2017 / achat de M Social and Economic Service Single Stage - One E atériels informatique pour les IDA / 58330 Post Request for Bids Open - National 169,000.00 0.00 Canceled 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 s and Infrastructure nvelope lycées bénéficiaires/ Educati on COMP1/F5/2017 / acquisition Social and Economic Service de 10 200 foyers améliorés p IDA / 58330 Prior Direct Selection Direct 229,859.00 183,345.08 Signed 2019-11-15 2020-06-18 2019-11-20 2020-06-24 2019-12-16 2020-01-09 2020-03-15 s and Infrastructure our les 3 sites COMP1/F1/2020 / acquisition Regional Support for Coordin d'équipements et matériels IDA / 58330 ation, Capacity and Knowled Post Direct Selection Direct 650,374.00 650,734.00 Signed 2020-10-07 2020-05-26 2020-10-12 2020-10-01 2020-11-16 2020-11-13 2021-05-15 médicaux pour la CAMME. ge COMP1/F1/2021 / Achat four Regional Support for Coordin Single Stage - One E Pending Impl nitures pour la caserne pom IDA / 58330 ation, Capacity and Knowled Post Request for Bids Open - National 214,085.00 0.00 2021-03-16 2021-03-21 2021-05-02 2021-06-01 2021-07-06 2022-01-02 nvelope ementation pier ALI SABIEH et OBOCK ge COMP1/F2/2021 / Achat de F Regional Support for Coordin Single Stage - One E ournitures et équipements co IDA / 58330 ation, Capacity and Knowled Post Request for Bids Open - National 84,995.00 127,813.08 Signed 2021-03-16 2021-03-18 2021-03-21 2021-05-02 2021-07-14 2021-06-01 2021-08-11 2021-07-06 2021-08-16 2022-01-02 nvelope llèges de Ali Addeh ge COMP1/F3/2021 / Achat de F Regional Support for Coordin Single Stage - One E IDA / 58330 Post Request for Bids Open - National 85,000.00 35,591.88 Signed 2021-03-16 2021-03-18 2021-03-21 2021-05-02 2021-08-11 2021-06-01 2021-08-29 2021-07-06 2021-10-13 2022-01-02 ournitures et équipements ly ation, Capacity and Knowled nvelope cée d’Obock ge Page 3 COMP1/F4/2021 / Acquisition Project Management, and M Single Stage - One E de matériels SVT pour le mini IDA / 58210 Post Request for Bids Open - National 270,423.00 383,875.99 Signed 2021-03-16 2021-03-18 2021-03-21 2021-05-02 2021-08-11 2021-06-01 2021-09-15 2021-07-06 2021-10-13 2022-01-02 onitoring and Evaluation nvelope stère de l’éducation COMP4/F4/2021 / Achat de f ournitures pour l'Atelier pour Regional Support for Coordin Request for Quota Single Stage - One E Pending Impl communication des résultats IDA / 58330 ation, Capacity and Knowled Post Limited 16,901.00 0.00 2021-03-21 2021-05-16 2021-11-12 tions nvelope ementation des enquêtes avec les parten ge aires (conseil régional, préfec ture, BM…) COMP4/F3/2021 / Achat de f Project Management, and M Single Stage - One E ournitures et matériels infor IDA / 58330 Post Request for Bids Open - National 45,070.00 0.00 Canceled 2021-03-16 2021-08-08 2021-03-21 2021-05-02 2021-09-01 2021-06-01 2021-07-06 2022-01-02 onitoring and Evaluation nvelope matiques pour la DPSE COMP4/F5/2021 / ACQUISITI Regional Support for Coordin ON D'EQUIPEMENTS ADIOVIS Request for Quota Single Stage - One E IDA / 58330 ation, Capacity and Knowled Post Limited 27,000.00 26,956.89 Signed 2021-12-21 2021-04-06 2022-02-15 2021-07-16 2022-08-14 UEL POUR LE SERVICE COM tions nvelope ge MUNICATION DU PROJET COMP1/F1/2019 / Acquisition Project Management, and M Single Stage - One E d'équipements pour le collèg IDA / 58330 Post Request for Bids Open - National 54,995.00 0.00 Canceled 2019-09-08 2019-09-13 2019-10-25 2019-11-24 2019-12-29 2020-06-26 onitoring and Evaluation nvelope e de Alli Addé (tables, chaise s,...) COMP1/F5/2019 BIS / ACQUI Sustainable Environmental Single Stage - One E SITION DE BOUTRES ET AUTR IDA / 58330 Post Request for Bids Open - National 275,000.00 0.00 Canceled 2021-12-16 2021-12-21 2022-02-01 2022-03-03 2022-04-07 2022-10-04 Management nvelope ES MATERIELS POUR LES PEC HEURS D'OBOCK COMP1/F5/2021 / Achat de F Regional Support for Coordin ourniture des équipements m Pending Impl IDA / 58330 ation, Capacity and Knowled Post Direct Selection Direct - National 170,000.00 0.00 2022-10-30 2022-11-04 2022-12-09 2023-06-07 édicaux MS pour le pavillon ementation ge maternité du CMH d’Obock e t extention de hollholl COMP4/F4/2022 / Achat de Regional Support for Coordin Request for Quota Single Stage - One E matériel de bureau pour la Di IDA / 58330 ation, Capacity and Knowled Post Limited 18,600.00 0.00 Completed 2022-12-27 2022-06-08 2023-02-21 2023-08-20 2022-09-14 tions nvelope rection de l'ADDS ge COMP4/F5/2022 / achat d'éq Regional Support for Coordin Request for Quota Single Stage - One E IDA / 58330 Post Limited 23,000.00 0.00 Completed 2022-12-27 2022-08-22 2023-02-21 2023-08-20 2022-12-18 uipement de bureau pour la ation, Capacity and Knowled tions nvelope Direction ge COMP4/F2/2021 / Acquisition Project Management, and M Single Stage - One E Pending Impl d'un camion de stock alimen IDA / 66660 Post Request for Bids Open - National 78,873.00 0.00 2023-04-05 2023-04-10 2023-05-22 2023-06-21 2023-07-26 2024-01-22 onitoring and Evaluation nvelope ementation taire pour l’ONARS COMP2/F6/2023 / Achat de f Sustainable Environmental Request for Quota Single Stage - One E Pending Impl ournitures consommables (o IDA / 66660 Post Limited 5,000.00 0.00 2023-05-13 2023-07-08 2024-01-04 Management tions nvelope ementation nduleur) pour la centrale sola ire COMP4/F1/2022 / Achat de f Project Management, and M Single Stage - One E Pending Impl ournitures et matériels infor IDA / 58330 Post Request for Bids Open - National 36,000.00 0.00 2022-01-17 2022-01-22 2022-03-05 2022-04-04 2022-05-09 2022-11-05 onitoring and Evaluation nvelope ementation matiques pour la DPSE COMP3/F1/ADD2023 / Achat Request for Quota Single Stage - One E Pending Impl de matériel de quincaillerie p IDA / 66660 Livelihoods Program Post Limited 16,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 tions nvelope ementation our les moulins pour les sites COMP3/F2/ADD2023 / Acquis Request for Quota Single Stage - One E Pending Impl ition de tableaux et étiquette IDA / 66660 Livelihoods Program Post Limited 10,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 tions nvelope ementation s pour les 2 régions COMP3/F6/ADD2023 / Achat Request for Quota Single Stage - One E Pending Impl de matériels informatiques et IDA / 66660 Livelihoods Program Post Limited 6,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 tions nvelope ementation bureautiques COMP3/F7/ADD2023 / Achat Social and Economic Service Request for Quota Single Stage - One E Pending Impl consommables Matières pre IDA / 66660 Post Limited 50,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 s and Infrastructure tions nvelope ementation mières pour le moulin et livr aison sur site COMP3/F8/ADD2023 / Achat de consommables pour la ge Request for Quota Single Stage - One E Pending Impl IDA / 66660 Livelihoods Program Post Limited 7,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 stion des moulins (congélate tions nvelope ementation urs; climatiseurs) pour les 2 r égions COMP I /F7/2023ADD / Achat de pompes immergées et é Social and Economic Service Request for Quota Single Stage - One E Pending Impl IDA / 66660 Post Limited 45,050.00 0.00 2023-06-20 2023-08-01 2023-10-30 quipements solaires dans le s and Infrastructure tions nvelope ementation cadre de la réhabilitation des périmètres agricols COMP3/F5/ADD2023 / Achat, Direct - Internation Pending Impl installation et formation pour IDA / 66660 Livelihoods Program Post Direct Selection 200,000.00 0.00 2023-06-25 2023-06-30 2023-07-28 2023-11-25 al ementation deux moulins à grain (obock et Ali adde) COMP3/F9/ADD2023 / Achat Single Stage - One E Pending Impl IDA / 66660 Livelihoods Program Post Request for Bids Limited 60,000.00 0.00 2023-06-25 2023-06-30 2023-07-30 2023-08-14 2023-09-11 2023-12-10 et pose de kits solaires pour nvelope ementation Ali addé COMP4/F1/2021 / Achat /ada Regional Support for Coordin Single Stage - One E Pending Impl ptation d’un logiciel intégré p IDA / 66660 ation, Capacity and Knowled Post Request for Bids Open - National 209,000.00 0.00 2023-03-27 2023-04-01 2023-05-13 2023-06-12 2023-07-10 2023-11-07 nvelope ementation our l’ONARS ge COMP1/F1/ADD2023 / Achat d'équipements médicaux MS Social and Economic Service Pending Impl IDA / 58330 Post Direct Selection Direct - National 134,000.00 0.00 2023-03-31 2023-04-05 2023-05-10 2023-11-06 pour le pavillon maternité du s and Infrastructure ementation CMH d'Obock et extension de Holhol NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP4/NCS1/2019 / séminai re Management de projets et Project Management, and M Pending Impl programmes par indicateurs, IDA / 58330 Post Direct Selection Direct 12,435.00 0.00 2019-09-08 2019-09-13 2019-10-18 2020-04-15 onitoring and Evaluation ementation résultats et tableaux de bord Page 4 COMP4/NCS2/2019 / Formati on: cycle FI05 intitulé "La pas sation et l'exécution des mar Project Management, and M Pending Impl chés selon les nouvelles proc IDA / 58330 Post Direct Selection Direct 15,000.00 0.00 2019-09-08 2019-09-13 2019-10-18 2020-04-15 onitoring and Evaluation ementation édures nationales et des baill eurs (Banque Mondiale, Banq ue Africaine de Développeme nt, Union Européenne...)" COMP4/CSC3/2019 / Formati on de la responsable gestion Project Management, and M Pending Impl financière en gestion adminis IDA / 58330 Post Direct Selection Direct 15,000.00 0.00 2019-09-24 2019-09-29 2019-11-03 2020-05-01 onitoring and Evaluation ementation trative et financière, la clôtur e et l'audit des programmes et projets COMP4/NCS4/2019 / formati on du chef de projet en " pré Project Management, and M Pending Impl paration ala certification en IDA / 58330 Post Direct Selection Direct 15,171.00 0.00 2019-11-17 2019-11-22 2019-12-27 2019-12-30 onitoring and Evaluation ementation gestion de projet PMP (projec t Managment professionnal) COMP3/F3/ADD2023 / Achat Request for Quota Single Stage - One E Pending Impl IDA / 66660 Livelihoods Program Post Limited 6,000.00 0.00 2023-06-04 2023-07-30 2024-01-26 et pose d'étagères métalliqu tions nvelope ementation es COMP3/C11/2023ADD / LAB Pending Impl ORATOIRE D'ANALYSE ALIME IDA / 66660 Livelihoods Program Post Direct Selection Direct - National 10,000.00 0.00 2023-06-06 2023-06-11 2023-07-25 2023-10-10 ementation NTAIRE ( LANAA) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP1/C1/2017 / Recrutem ent d'un Bureau d'Etudes et de supervision pour les trava Social and Economic Service Quality And Cost- IDA / 58330 Post Open - National 252,234.00 332,425.00 Signed 2017-10-02 2017-07-26 2017-10-23 2017-12-06 2018-01-08 2018-01-03 2018-01-31 2018-02-02 2018-03-07 2018-03-09 2018-04-04 2018-04-13 2018-04-06 2019-04-13 ux d'extension, construction, s and Infrastructure Based Selection réhabilitation des établissem ents scolaires , le local comm unautaire COMP1/C2/2017 / Recrutem ent d'un Bureau d'Etudes po Social and Economic Service Consultant Qualifi ur la supervision des travaux IDA / 58330 Post Open - National 83,611.00 83,364.44 Signed 2017-10-02 2017-07-13 2017-10-23 2017-12-06 2017-11-05 2018-01-05 2017-11-13 2018-02-09 2017-11-22 2018-08-08 s and Infrastructure cation Selection d'extension de centres de sa nté pour obock, ali addé et H ol hol COMP1/C3/2017 / Récrutem ent d'un consultant individue l pour les études et la superv Social and Economic Service Consultant Qualifi IDA / 58330 Post Open - National 30,000.00 23,276.23 Signed 2017-10-30 2018-03-11 2017-11-20 2018-01-03 2018-08-29 2018-02-02 2018-09-19 2018-03-09 2018-10-11 2018-09-05 ision les travaux d'installatio s and Infrastructure cation Selection ns dans les logements, locau x commerciaux et établissem ent publics à Holl-Holl COMP1/C4/2017 / Recrutem Social and Economic Service Consultant Qualifi ent d'un bureau d'etudes pou IDA / 58330 Post Open - National 45,070.00 0.00 Canceled 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 s and Infrastructure cation Selection r raccordement Pecherie (Ob ock) COMP1/C5/2017 / Recrutem ent d'un BE pour les travaux Social and Economic Service Quality And Cost- de forrage de Hol hol et Ali A IDA / 58330 Post Open - National 188,732.00 0.00 Canceled 2017-12-15 2018-01-05 2018-02-18 2018-03-18 2018-04-17 2018-05-22 2018-06-26 2019-06-26 s and Infrastructure Based Selection ddé et du reseau d'adductio n d'eau à Obock et Holl-Holl COMP2/C1/2017 / Recrutem ent d'un bureau d'etudes pou Social and Economic Service Consultant Qualifi IDA / 58330 Post Open - National 40,564.00 0.00 Canceled 2017-10-05 2017-10-26 2017-12-09 2018-01-08 2018-02-12 2018-08-11 r la la rénovation et renforce s and Infrastructure cation Selection ment des perimetres existant s COMP2/C2/2017 / Recrutem ent d'un bureau d'etudes pou Social and Economic Service Quality And Cost- IDA / 58330 Post Open - National 152,369.00 228,500.00 Completed 2017-10-02 2018-07-12 2017-10-23 2017-12-06 2018-08-29 2018-01-03 2018-10-24 2018-02-02 2018-12-26 2018-03-09 2019-01-09 2018-04-13 2019-01-24 2019-04-13 2020-10-28 r l'extension de la centrale so s and Infrastructure Based Selection laire et le forage d'Ali-Addé COMP4/C10/2017 / recrutem Social and Economic Service Least Cost Selecti IDA / 58330 Post Open - National 10,000.00 18,351.36 Signed 2017-10-02 2017-09-13 2017-10-23 2017-12-06 2017-12-24 2018-01-03 2018-02-21 2018-02-02 2018-04-02 2018-03-09 2018-04-09 2018-04-13 2018-04-17 2018-10-10 ent d 'un cabinet pour l'Audit s and Infrastructure on Financier COMP4/C11/2017 / Recrute ment d'un consultant pour la Social and Economic Service Consultant Qualifi IDA / 58330 Post Open - National 8,000.00 7,976.41 Signed 2017-10-02 2017-08-20 2017-10-23 2017-12-06 2017-10-04 2018-01-05 2017-10-16 2018-02-09 2017-10-16 2018-08-08 collecte de donnée administr s and Infrastructure cation Selection atives de toutes les infrastru ctures sociales de base COMP1/C2/2019 / Recrutem ent d'un cabinet pour l'étude Social and Economic Service Quality And Cost- IDA / 58330 Post Open - National 30,000.00 0.00 Canceled 2019-09-23 2019-10-14 2019-11-27 2019-12-25 2020-01-24 2020-02-28 2020-04-03 2021-04-03 topographique de l'adduction s and Infrastructure Based Selection d'eau potable a partir d'Ali sa bieh COMP1/C5/2017 / Recrutem ent d'un BE pour les travaux Social and Economic Service Quality And Cost- Open - Internationa IDA / 58330 Post 500,000.00 442,290.00 Completed 2020-02-20 2020-01-09 2020-03-12 2020-08-16 2020-04-25 2020-09-09 2020-05-23 2021-06-02 2020-06-22 2021-05-30 2020-07-27 2021-06-30 2020-08-31 2021-07-15 2021-08-31 2021-10-25 de raccordements de Hol hol s and Infrastructure Based Selection l et Ali Addé au reservoir d'ea u d'Ali-Sabieh COMP4/C4/2021 / recruteme Regional Support for Coordin Least Cost Selecti nt d'un cabinet d'audit financ IDA / 58330 ation, Capacity and Knowled Post Open - National 67,606.00 36,912.52 Signed 2021-02-28 2021-02-14 2021-03-21 2021-05-04 2021-04-26 2021-06-01 2021-06-30 2021-07-01 2021-07-28 2021-08-05 2021-08-11 2021-09-09 2021-08-18 2022-03-08 on ier pour les exercices 2020/2 ge 021/2022 COMP1/C1SUP/2021 / LE RE CRUTEMENT D'UN BUREAU D E CONTROLE POUR LES TRAV Social and Economic Service Consultant Qualifi IDA / 58330 Post Open - National 100,000.00 442,290.00 Signed 2021-04-18 2021-04-25 2021-04-28 2021-06-02 2021-05-22 2021-07-07 2021-06-21 2021-07-11 2021-07-26 2021-07-15 2022-01-22 AUX D'EXTENSION/CONSTRU s and Infrastructure cation Selection CTION/REHABILITATION D'ALI -ADDE, HOLL-HOLL ET D'OBO CK COMP4/C1/2022 / Recrutem Regional Support for Coordin ent d'un bureau d'études inte Consultant Qualifi Open - Internationa Under Implement IDA / 58330 ation, Capacity and Knowled Post 85,000.00 0.00 2022-09-29 2022-10-11 2022-10-20 2022-10-11 2022-12-03 2023-01-02 2023-02-06 2023-08-05 rnational pour la rédaction d' cation Selection l ation ge un manuel administratif et fi nancier pour l'ONARS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Page 5 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual COMP4/C1/2017 / coordinate Social and Economic Service Individual Consult IDA / 58330 Post Open 30,000.00 142,079.81 Signed 2017-10-02 2016-10-25 2017-11-20 2017-03-02 2017-12-11 2017-03-02 2018-01-15 2017-04-02 2018-07-14 ur de projet s and Infrastructure ant Selection COMP4/C2/2017 / recruteme Social and Economic Service Individual Consult IDA / 58330 Post Open 24,000.00 109,675.64 Signed 2017-10-02 2016-10-25 2017-11-20 2017-05-30 2017-12-11 2017-06-01 2018-01-15 2017-06-02 2018-07-14 nt d'ingénieur en Infrastructu s and Infrastructure ant Selection res COMP4/C3/2017 / recruteme Social and Economic Service Individual Consult nt de 4 techniciens supérieur IDA / 58330 Post Open 62,400.00 15,554.00 Signed 2017-10-02 2017-03-20 2017-11-20 2017-05-03 2017-12-11 2017-05-07 2018-01-15 2017-08-16 2018-07-14 s and Infrastructure ant Selection s pour les régions et Djibouti ville COMP4/C5/2017 / recruteme Social and Economic Service Individual Consult nt d'un spécialiste en sauveg IDA / 58330 Post Open 24,000.00 116,588.52 Signed 2017-10-02 2016-11-08 2017-11-20 2017-02-14 2017-12-11 2017-02-23 2018-01-15 2017-03-15 2018-07-14 s and Infrastructure ant Selection ardes environnementales et sociales COMP4/C6/2017 / recruteme Social and Economic Service Individual Consult IDA / 58330 Post Open 24,000.00 91,728.71 Signed 2017-10-02 2016-11-08 2017-11-20 2016-02-14 2017-12-11 2017-02-23 2018-01-15 2017-03-02 2018-07-14 nt d'un responsable Suivi eva s and Infrastructure ant Selection luation COMP4/C7/2017 / recruteme Social and Economic Service Individual Consult IDA / 58330 Post Open 24,000.00 113,663.84 Signed 2017-10-02 2016-11-15 2017-11-20 2017-02-19 2017-12-11 2017-02-20 2018-01-15 2017-04-01 2018-07-14 nt d'un comptable s and Infrastructure ant Selection COMP4/C8/2017 / recruteme Social and Economic Service Individual Consult IDA / 58330 Post Open 12,000.00 13,161.08 Signed 2017-11-05 2019-05-01 2017-12-24 2019-06-16 2018-01-14 2019-06-16 2018-02-18 2019-05-01 2018-08-17 nt d'un assistant de projet s and Infrastructure ant Selection COMP4/C9/2017 / recruteme Social and Economic Service Individual Consult nt d'un spécialiste Passation IDA / 58330 Post Open 24,000.00 47,858.46 Signed 2017-10-05 2018-01-08 2017-11-23 2018-03-21 2017-12-14 2018-03-21 2018-01-18 2018-03-25 2018-07-17 s and Infrastructure ant Selection des marchés COMP4/C12/2017 / Enquette Social and Economic Service Under Implement sur les migrants à Balbala et IDA / 58330 Prior Direct Selection Direct 71,967.00 0.00 2017-10-02 2021-03-18 2017-10-07 2017-08-30 2017-11-11 2018-05-10 s and Infrastructure ation à Djibouti-Ville COMP4/C16/2017 / Récrute ment d'un expert internation Social and Economic Service Individual Consult IDA / 58330 Post Open 30,000.00 31,252.91 Signed 2017-10-02 2017-09-14 2017-11-20 2018-03-29 2017-12-11 2018-04-08 2018-01-15 2018-05-25 2018-07-14 al pour la préparation de la s s and Infrastructure ant Selection tratégie de l'ONARS COMP4/C17/2017 / Récrute ment d'un consultant individ Social and Economic Service Individual Consult IDA / 58330 Post Open 11,268.00 10,967.56 Signed 2017-10-02 2017-09-14 2017-11-20 2018-03-12 2017-12-11 2018-04-08 2018-01-15 2018-04-18 2018-07-14 uel pour l'appui de l'expert e s and Infrastructure ant Selection n charge de la préparation d e la stratégie de l'ONARS COMP4/C17/2017_1 / recrute Social and Economic Service Individual Consult ment d'un expert internation IDA / 58330 Post Open 85,000.00 0.00 Canceled 2017-11-15 2017-09-18 2018-01-03 2018-01-24 2018-02-28 2018-08-27 s and Infrastructure ant Selection al en manuel de procédures ONARS COMP4/C4/2017 / recruteme Social and Economic Service Individual Consult IDA / 58330 Post Open 24,000.00 71,787.69 Signed 2017-10-02 2016-11-08 2017-11-20 2017-02-16 2017-12-11 2017-02-13 2018-01-15 2017-03-02 2019-01-15 nt d'un spécialiste en agricult s and Infrastructure ant Selection ure COMP4/C13/2017 / recrutem Social and Economic Service Individual Consult Pending Impleme ent d'un consultant pour l'en IDA / 58330 Post Open 29,734.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2018-10-27 s and Infrastructure ant Selection ntation quête quantitative ménage COMP4/C14/2017 / recrutem ent d'un consultant pour l'en Social and Economic Service Individual Consult Pending Impleme IDA / 58330 Post Open 26,133.00 0.00 2018-01-25 2018-03-15 2018-04-05 2018-05-10 2018-11-06 quête quantitative jeunes fe s and Infrastructure ant Selection ntation mmes et périmètres agro pas toraux COMP4/C16/2017 / Recrute Social and Economic Service Individual Consult ment d'un consultant pour l'e IDA / 58330 Post Limited 34,000.00 4,237.47 Signed 2018-03-14 2019-02-18 2018-03-19 2019-02-18 2018-04-09 2019-03-20 2018-05-14 2019-04-21 2018-06-28 s and Infrastructure ant Selection nquête de suivi des indicateu rs DJ-ADDS-54279-CS-INDV / re crutement d'un consultantpo Social and Economic Service Individual Consult Pending Impleme IDA / 58330 Post Limited 20,000.00 0.00 2017-10-05 2017-10-10 2017-10-31 2017-12-05 2018-06-03 ur la sensibilisation,étude de s and Infrastructure ant Selection ntation marchés, mise a jour du listin g COMP4/C17/2017_2 / recrute Social and Economic Service Individual Consult Pending Impleme ment d'un consultant pour l'e IDA / 58330 Post Limited 80,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-06-29 s and Infrastructure ant Selection ntation nquete de référence 40000 / recrutement d'un co Social and Economic Service Individual Consult IDA / 58330 Post Limited 40,000.00 0.00 Canceled 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-11-11 nsultant pour la communicati s and Infrastructure ant Selection on COMP3/C1/2017 / recruteme Social and Economic Service Individual Consult Pending Impleme nt d'un consultant pour l'anal IDA / 58330 Post Limited 20,000.00 0.00 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-11-11 s and Infrastructure ant Selection ntation yse complémentaire de l'en quete 022/2018/CO/IDA-PRDDCA/A DDS / recrutement d'une cha IDA / 58330 Livelihoods Program Post Direct Selection Direct 8,400.00 28,615.37 Signed 2019-01-16 2018-12-04 2019-01-26 2019-01-20 2019-04-01 2019-01-21 2019-09-28 rgée des GEA pour la rgion O BOCK 023/2018/CO/IDA-PRDDCA/A DDS / recrutement d'une cha IDA / 58330 Livelihoods Program Post Direct Selection Direct 8,400.00 25,125.69 Signed 2019-01-16 2018-12-04 2019-01-26 2019-01-20 2019-04-01 2019-01-21 2019-09-28 rgée des GEA pour la région d'Ali sabieh 024/2018/CO/IDA-PRDDCA/A DDS / Recrutement d'une fac IDA / 58330 Livelihoods Program Post Direct Selection Direct 7,200.00 29,911.54 Signed 2019-01-30 2018-01-01 2019-02-09 2019-02-06 2019-04-15 2018-03-02 2019-10-12 ilitatrice du programme de m oyens de subsistance des jeu nes. 004/2019/CO/IDA-PRDDCA/A DDS / Recrutement d'un facili tateur à Holl-Holl pour le Re Project Management, and M IDA / 58330 Post Direct Selection Direct 7,200.00 22,732.77 Signed 2019-02-05 2018-01-01 2019-02-15 2019-01-27 2019-04-21 2019-02-06 2019-10-18 nforcement de capacités des onitoring and Evaluation jeunes et pour la Préparation au concours de Microprojets 005/2019/CO/IDA-PRDDCA/A DDS / Recrutement d'une fac ilitatrice à Holl-Holl pour le R Project Management, and M IDA / 58330 Post Direct Selection Direct 7,200.00 30,270.52 Signed 2019-02-05 2018-01-01 2019-02-15 2019-01-27 2019-04-21 2019-02-06 2019-10-18 enforcement de capacités de onitoring and Evaluation s jeunes et pour la Préparatio n au concours de Microprojet s. Page 6 006/2019/CO/IDA-PRDDCA/A DDS / Recrutement d'une fac ilitatrice à Holl-Holl pour le R Project Management, and M IDA / 58330 Post Direct Selection Direct 7,200.00 30,118.86 Signed 2019-02-05 2018-01-01 2019-02-15 2019-01-27 2019-04-21 2019-02-07 2019-10-18 enforcement de capacités de onitoring and Evaluation s jeunes et pour la Préparatio n au concours de Microprojet s. 007/2019/CO/IDA-PRDDCA/A DDS / Recrutement d’un facil itateur à Ali-Addeh pour le R Project Management, and M IDA / 58330 Post Direct Selection Direct 7,200.00 22,732.77 Signed 2019-02-05 2019-01-01 2019-02-15 2019-02-06 2019-04-21 2019-02-07 2019-10-18 enforcement de capacités de onitoring and Evaluation s jeunes et pour la Préparatio n au concours de Microprojet s. 020/2019/CO/IDA-PRDDCA/A DDS / recrutement d'un cons Project Management, and M Pending Impleme IDA / 58330 Post Direct Selection Direct 4,250.00 0.00 2019-04-02 2019-04-12 2019-06-16 2019-12-13 ultant pour l'actualisation de onitoring and Evaluation ntation s indicateurs DRIPDIP COMP4/C19/2019 / recrutem Project Management, and M Individual Consult ent d'un consultant pour la re IDA / 58330 Post Open 15,000.00 23,000.00 Signed 2019-07-15 2019-06-09 2019-09-02 2019-07-18 2019-09-23 2019-07-29 2019-10-28 2019-07-31 2020-04-25 onitoring and Evaluation ant Selection vue mi-parcours COMP4/C20/2019 / recrutem Project Management, and M ent d'un coordinateur pour la IDA / 58330 Post Direct Selection Direct 30,000.00 103,693.33 Signed 2019-07-15 2019-06-01 2019-07-25 2019-04-24 2019-09-28 2019-05-02 2020-03-26 onitoring and Evaluation composante III COMP4/C21/2019 / recrutem Project Management, and M Under Implement IDA / 58330 Post Direct Selection Direct 24,000.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 ent d'un expert micro entrep onitoring and Evaluation ation rise COMP4/C22/2019 / recrutem Project Management, and M Under Implement ent d'une assistante pour le c IDA / 58330 Post Direct Selection Direct 13,200.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 onitoring and Evaluation ation oordinateur du projet COMP4/C23/2019 / recrutem Project Management, and M Under Implement ent d'une assistante pour le c IDA / 58330 Post Direct Selection Direct 13,200.00 0.00 2019-07-15 2019-06-01 2019-07-25 2019-09-28 2020-03-26 onitoring and Evaluation ation oordinateur de la composant e III COMP4/C24/2019 / recrutem Project Management, and M ent d'une facilitatrice commu IDA / 58330 Post Direct Selection Direct 4,733.00 20,041.84 Signed 2019-07-15 2019-07-15 2019-07-25 2019-06-16 2019-09-28 2019-05-02 2020-03-26 onitoring and Evaluation nautaire des femmes à Holh ol COMP4/C25/2019 / recrutem Project Management, and M ent d'une facilitatrice commu IDA / 58330 Post Direct Selection Direct 6,915.00 25,424.80 Signed 2019-07-15 2019-07-15 2019-07-25 2019-06-16 2019-09-28 2019-05-02 2020-03-26 onitoring and Evaluation nautaire pour les femmes à o bock COMP4/C26/2019 / recrutem Project Management, and M ent d'une facilitatrice commu IDA / 58330 Post Direct Selection Direct 6,915.00 20,041.84 Signed 2019-07-15 2019-07-15 2019-07-25 2019-06-16 2019-09-28 2019-05-02 2020-03-26 onitoring and Evaluation nautaire pour les femmes a Obock COMP4/C27/2019 / recrutem Project Management, and M ent d'une facilitatrice commu IDA / 58330 Post Direct Selection Direct 6,915.00 20,041.84 Signed 2019-07-15 2019-06-01 2019-07-25 2019-06-16 2019-09-28 2019-05-02 2020-03-26 onitoring and Evaluation nautaire pour les femmes a Obock COMP4/C28/2019 / recrutem Project Management, and M ent d'une facilitatrice commu IDA / 58330 Post Direct Selection Direct 6,915.00 20,041.84 Signed 2019-07-15 2019-07-15 2019-07-25 2019-06-16 2019-09-28 2019-05-02 2020-03-26 onitoring and Evaluation nautaire pour les femmes a Obock COMP1/C1/2019 / Recrutem Regional Support for Coordin Individual Consult ent d'un consultant pour l'étu IDA / 58330 ation, Capacity and Knowled Post Limited 32,000.00 27,850.03 Signed 2019-11-12 2019-09-23 2019-11-17 2019-04-29 2019-12-08 2019-09-24 2020-01-12 2019-09-27 2020-02-26 ant Selection de topographique dédiée a la ge DHR... COMP3/C4/2019 / recruteme Project Management, and M Individual Consult nt d'un spécialiste en dévelo IDA / 58330 Post Limited 15,000.00 0.00 Canceled 2019-11-26 2019-10-09 2019-12-01 2019-12-22 2020-01-26 2020-01-30 onitoring and Evaluation ant Selection ppement agropastorale COMP3/C3/2019 / Recrutem ent de deux consultant hydro Project Management, and M Individual Consult laugue et énergeticien pour l IDA / 58330 Post Limited 30,000.00 59,823.08 Signed 2019-11-12 2019-10-15 2019-11-17 2019-10-29 2019-12-08 2020-04-29 2020-01-12 2020-07-01 2020-02-26 onitoring and Evaluation ant Selection a la renovation/renforcemen t des perimetres existants COMPR1/C2/2019 / Recrute ment d'un consultant individ Social and Economic Service Individual Consult uel pour la supervision les tra IDA / 58330 Post Limited 27,000.00 26,400.79 Signed 2020-02-05 2020-02-24 2020-02-10 2020-03-23 2020-03-02 2020-03-25 2020-04-06 2020-06-02 2020-06-05 s and Infrastructure ant Selection vaux d'installations dans les l ogements et mis en conformi té de 200 logment à obock COMP1/C1/2020 / recruteme nt du BE d'études assurant la continuité du contrôle des tra Social and Economic Service IDA / 58330 Post Direct Selection Direct 121,025.00 0.00 Canceled 2020-08-24 2020-03-12 2020-09-03 2020-11-07 2021-05-06 vaux de construction et réha s and Infrastructure bilitation (ecole, local commu nautaire, maison de fonction, route pierres taillées...) COMP4/C11/2019 / Mise a jo Regional Support for Coordin IDA / 58330 Post Direct Selection Direct 94,000.00 117,075.91 Signed 2019-09-08 2020-11-07 2019-09-18 2019-09-20 2019-11-22 2020-05-26 2020-05-20 ur du logiciel de gestion du ation, Capacity and Knowled projet ge COMP1/C2/2020 / Recrutem Regional Support for Coordin ent d'un consultant ingénieur IDA / 58330 ation, Capacity and Knowled Post Direct Selection Direct 24,000.00 23,929.23 Signed 2020-12-22 2020-12-11 2021-01-01 2020-12-15 2021-03-07 2021-01-29 2021-09-03 en HYDRAULIQUE ge COMP1/C3/2020 / Recrutem Regional Support for Coordin ent d'un consultant Ingénieur IDA / 58330 ation, Capacity and Knowled Post Direct Selection Direct 24,000.00 23,929.23 Signed 2020-12-22 2020-12-11 2021-01-01 2020-12-15 2021-03-07 2021-01-25 2021-09-03 en Genie Civil ge COMP3/C2/2020 / recruteme nt d'un expert en micro entre IDA / 58330 Livelihoods Program Post Direct Selection Direct 24,000.00 18,146.33 Signed 2020-12-22 2020-10-22 2021-01-01 2020-09-27 2021-03-07 2020-11-02 2021-09-03 prise pour la composante III COMP3/C3/2020 / recruteme nt d'une assistante pour la co IDA / 58330 Livelihoods Program Post Direct Selection Direct 13,200.00 15,354.59 Signed 2020-12-22 2020-10-22 2021-01-01 2020-09-27 2021-03-07 2020-11-02 2021-09-03 mposante III COMP3/C1/2020 / recruteme Project Management, and M nt d'un coordinateur pour la IDA / 58330 Post Direct Selection Direct 30,000.00 27,917.43 Signed 2020-12-22 2020-10-22 2021-01-01 2020-09-27 2021-03-07 2020-11-02 2021-09-03 onitoring and Evaluation composante III Page 7 COMP3/C2/2017 / recruteme Regional Support for Coordin nt d'une facilitatrice pour le p Individual Consult Under Implement IDA / 58330 ation, Capacity and Knowled Post Limited 7,200.00 0.00 2021-02-09 2018-01-01 2021-02-14 2021-03-07 2021-04-11 2021-10-08 rogramme de moyens de sub ant Selection ation ge sistances a Obock COMP1/C3/2017 / Recrutem ent d'un consultant individue l pour la supervision les trava Social and Economic Service Individual Consult IDA / 58330 Post Limited 30,000.00 0.00 Canceled 2021-02-24 2018-06-07 2021-03-01 2021-03-22 2021-04-26 2021-10-23 ux d'installations dans les log s and Infrastructure ant Selection ements, locaux commerciaux et établissement publics à Ho ll-Holl et daasbiyo COMP4/C7/2021 / Recrutem ent d’un consultant pour une Project Management, and M Individual Consult IDA / 58330 Post Limited 14,080.00 14,042.98 Signed 2021-03-16 2021-05-17 2021-03-21 2021-08-17 2021-04-11 2021-08-17 2021-05-16 2021-09-14 2021-11-12 seconde enquête de suivi pr onitoring and Evaluation ant Selection évue pour 2021 (en septem bre) COMP4/C9/2021 / Recrutem ent d’un consultant pour l’en Project Management, and M Individual Consult quête qualitativequi complét IDA / 58330 Post Limited 11,268.00 11,234.38 Signed 2021-03-16 2021-05-17 2021-03-21 2021-08-17 2021-04-11 2021-09-13 2021-05-16 2021-09-17 2021-11-12 onitoring and Evaluation ant Selection era les données quantitatives recueillies durant l’année (m ai 2021) COMP3/C1/2021 / Recrutem Individual Consult ent d'un consultant pour la C IDA / 58330 Livelihoods Program Post Limited 149,000.00 16,851.57 Signed 2021-03-16 2021-07-12 2021-03-21 2021-07-12 2021-04-11 2021-10-04 2021-05-16 2021-10-21 2021-11-12 ant Selection réation/organisation/formatio n de GEAs COMP3/C3/2021 / recruteme nt d'un nouveau facilitateur p IDA / 58330 Livelihoods Program Post Direct Selection Direct 8,400.00 14,586.91 Signed 2021-03-23 2020-02-17 2021-04-02 2021-03-17 2021-06-06 2021-05-02 2021-12-03 our les formations jeunes à l' entreprenariat au chef lieu d' Obock COMP4/C6/2021 / Recrutem ent d’un consultant pour une Project Management, and M Individual Consult IDA / 58330 Post Limited 14,080.00 11,234.38 Completed 2021-05-03 2021-05-17 2021-05-08 2021-07-29 2021-05-29 2021-08-17 2021-07-03 2021-09-13 2021-12-30 2022-02-24 premiere enquête de suivi pr onitoring and Evaluation ant Selection évue pour mai 2021. COMPP1/C6/2021 / RECRUTE MENT D’UN BEPOUR LES SUP Social and Economic Service IDA / 58330 Post Direct Selection Direct 27,605.00 27,927.69 Signed 2021-10-24 2021-06-30 2021-11-03 2021-07-07 2022-01-07 2021-10-28 2022-07-06 ERVISIONS DE TRAVAUX DU s and Infrastructure CENTRE DE SANTE HOLHOL COMP4/C15/2017 / recrutem Social and Economic Service Individual Consult ent d'un consultant pour l'en IDA / 58330 Post Open - National 50,000.00 26,000.00 Signed 2022-02-20 2018-05-06 2022-04-10 2018-01-30 2022-05-01 2019-01-30 2022-06-05 2019-01-31 2022-12-02 s and Infrastructure ant Selection quete qualitatif (focus group e) .. 002/COMP2/2022 / Recrute ment d'un Bureau de contrôl Sustainable Environmental IDA / 58330 Post Direct Selection Direct - National 156,000.00 0.00 Signed 2022-11-13 2022-11-06 2022-11-23 2022-10-10 2023-01-27 2023-07-26 e des travaux d'extension et Management le réseau électrique de la cen trale solaire d'Ali Addé COMP4/C5/2022 / recruteme Regional Support for Coordin IDA / 58330 Post Direct Selection Direct - National 23,600.00 0.00 Under Review 2022-12-22 2021-12-20 2023-01-01 2023-03-07 2023-09-03 nt d'un spécialiste en Suivi E ation, Capacity and Knowled valuation ge COMP4/C11/2021 / Recrute ment d’un consultant pour ef Project Management, and M Individual Consult Pending Impleme IDA / 66660 Post Limited 10,000.00 0.00 2023-07-02 2023-07-07 2023-07-28 2023-09-01 2024-02-28 fectuer une évaluation en im onitoring and Evaluation ant Selection ntation age pour l’ensemble du proje t COMP3/C1/ADD2023 / Recru Individual Consult Pending Impleme tement d'un consultant pour IDA / 66660 Livelihoods Program Post Limited 11,831.00 0.00 2023-05-20 2023-05-25 2023-06-15 2023-07-20 2024-01-16 ant Selection ntation la mise en place d'un systèm e de facturation COMP4/C2/2017 / expert int Project Management, and M Individual Consult ernational en manuel de proc IDA / 58330 Post Limited 85,000.00 0.00 Canceled 2020-02-04 2022-07-25 2020-02-09 2020-03-01 2020-04-05 2020-07-04 onitoring and Evaluation ant Selection édures /ONARS (3) COMP3/C2/2021 / Recrutem Individual Consult et d'un consultant pour le Co IDA / 58330 Livelihoods Program Post Limited 9,420.00 0.00 Canceled 2021-03-16 2021-03-21 2021-04-11 2021-05-16 2021-11-12 ant Selection ncours de plan d’affaires COMP4/C10/2021 / recrutem ent d'un consultant pour com Project Management, and M Individual Consult Pending Impleme IDA / 66660 Post Limited 10,000.00 0.00 2023-09-03 2023-09-08 2023-09-29 2023-11-03 2024-05-01 muniquer avec les partenaire onitoring and Evaluation ant Selection ntation s sur les différentes données COMP4/C8/2021 / recruteme nt d'un consultant pour réalis Project Management, and M Individual Consult Pending Impleme IDA / 66660 Post Limited 14,085.00 0.00 2023-04-20 2023-04-25 2023-05-16 2023-06-20 2023-12-17 e une enquête de suivi prévu onitoring and Evaluation ant Selection ntation pour 2023 (en juin 2023) COMP4/C13/2021 / recrutem ent d'un consultant pour réali Sustainable Environmental Individual Consult Pending Impleme IDA / 66660 Post Limited 25,000.00 0.00 2023-04-10 2023-04-15 2023-05-06 2023-06-10 2023-12-07 ser une étude de satisfaction Management ant Selection ntation du projet parent pour les 3 si tes du projet COMP4/C8/2023 / recruteme Regional Support for Coordin nt d'un consultant en charge Individual Consult Under Implement IDA / 66660 ation, Capacity and Knowled Post Limited 80,000.00 0.00 2023-04-02 2023-06-08 2023-04-07 2023-04-28 2023-06-02 2023-11-29 de la rédaction du rapport d' ant Selection ation ge évaluation/achèvement de pr ojet COMP3/C2/2023 / Expert po Direct - Internation Pending Impleme ur le developpement de l'unit IDA / 66660 Livelihoods Program Post Direct Selection 30,000.00 0.00 2023-04-02 2023-04-12 2023-06-01 2023-11-28 al ntation é de production du Thon COMP2/C10/2023 / recrutem Sustainable Environmental Individual Consult Pending Impleme ent d'un consultant pour la fa IDA / 66660 Post Limited 30,000.00 0.00 2023-05-08 2023-05-13 2023-06-03 2023-07-08 2024-01-04 Management ant Selection ntation cturation de la centrale solair e COMP4/C11/2023ADD / Recr Project Management, and M Pending Impleme utement d'un cabinet d'audit IDA / 66660 Post Direct Selection Direct - National 15,000.00 0.00 2023-06-06 2023-06-16 2023-07-29 2023-12-09 onitoring and Evaluation ntation pour l'année 2023 COMP3/C2/ADD2023 / Recru tement d'un Expert pour le d Direct - Internation Pending Impleme IDA / 66660 Livelihoods Program Post Direct Selection 30,000.00 0.00 2023-06-25 2023-07-05 2023-07-20 2023-11-17 eveloppement de l'unité de p al ntation roduction du Thon COMP4/C1/ADD2023 / AUDIT Project Management, and M Pending Impleme IDA / 66660 Post Direct Selection Direct - National 27,149.00 0.00 2023-03-06 2023-03-16 2023-04-17 2023-07-16 2023 onitoring and Evaluation ntation Page 8 COMP4/C12/2021 / Recrutee mnt d'un consultant pour réa liser l’enquête d’impact du pr Project Management, and M Individual Consult Pending Impleme IDA / 66660 Post Limited 50,000.00 0.00 2023-03-27 2023-04-01 2023-04-22 2023-05-27 2023-11-23 ojet parent dont l’achèvemen onitoring and Evaluation ant Selection ntation t est prévu le 31 décembre 2 023 (plus rapport d’achèvem ent du PP et PA) Page 9 PROCUREMENT PLAN (Textual Part) Project information: Burundi - Great Lakes Trade Facilitation and Integration Project] (P174814) Project Implementation agency: Burundi-Ministry of Finance, Budget and Privatization Date of the Procurement Plan: November 8, 2021 Period covered by this Procurement Plan: December 2017 – December 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the country procurement handbook, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. - The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. - Rights for the Bank to review procurement documentation and activities. - An effective complaints mechanism. - Maintenance of records of the Procurement Process When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables : Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is Not Applicable Works: is not Applicable PROCUREMENT Eastern and Southern Africa : Great Lakes Trade Facilitation and Integration Project PLAN General Information Country: Eastern and Southern Africa 2018-07-23 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174814 GPN Date: Project Name: Great Lakes Trade Facilitation and Integration Project Loan / Credit No: IDA / V1000, IDA / V3250, IDA / V0960, IDA / V3940, IDA / E0700, IDA / E0710 Burundi-Ministry of Finance, Budget and Privatization Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BI-BI-MOF-71885-CW-DIR / A Component 1. Improving Poli Under Imple 2019-01-1 dduction d'eau au poste front IDA / V1000 cy and Regulatory Environm Prior Direct Selection Direct 28,600.00 0.00 2018-07-27 2018-08-01 2018-09-18 mentation 7 ière de Gatumba (Interventio ent for cross border trade n rapide) BI-BI-MOF-71888-CW-RFQ / Improving core trade infrastr Aménagement des Latrines e Request for Quota Single Stage - One E 2019-01-0 IDA / V1000 ucture and facilities in the b Post Limited 11,000.00 10,186.24 Completed 2018-08-11 2018-08-10 2018-10-02 2018-09-06 t douches au port de Rumon tions nvelope 4 order areas ge (Intervention urgente) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-BI-MOF-170418-GO-RFQ / Implementation support, Co Request for Quota Single Stage - One E Acquisition des équipements IDA / V3250 mmunication, Monitoring, an Post Limited 50,000.00 16,881.67 Signed 2020-07-25 2022-02-22 2020-09-19 2022-01-25 2020-10-30 tions nvelope de bureau (mobilier et photo d Evaluation copieuse) BI-BI-MOF-170426-GO-RFQ / Implementation support, Co Request for Quota Single Stage - One E Acquisition du matériel infor IDA / V3250 mmunication, Monitoring, an Post Limited 30,000.00 42,446.89 Completed 2020-07-12 2020-10-12 2020-08-28 2021-01-20 2020-10-09 2021-06-08 tions nvelope matique pour l'UGP d Evaluation BI-BI-MOF-170423-GO-RFB / Implementation support, Co Acquisition de Trois véhicules Single Stage - One E IDA / V3250 mmunication, Monitoring, an Post Request for Bids Open - National 250,000.00 0.00 Canceled 2020-07-15 2020-07-20 2020-08-31 2020-09-15 2020-10-09 2020-12-01 (One station wagon 4*4 et de nvelope d Evaluation ux camionnettes) BI-BI-MOF-319184-GO-RFB / Component 4: Supporting Im Single Stage - One E Pending Impl Acquisition des équipements IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 50,000.00 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-06-15 nvelope ementation mobiliers pour l'UGP and Evaluation BI-BI-MOF-319187-GO-RFB / Component 4: Supporting Im Single Stage - One E Pending Impl Acquisition du matériel infor IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 100,000.00 0.00 2022-12-15 2022-12-20 2023-01-31 2023-03-02 2023-04-06 2023-06-30 nvelope ementation matique pour l'UGP and Evaluation BI-BI-MOF-319182-GO-RFB / Component 4: Supporting Im Acquisition de 4 véhicules (1 Single Stage - One E IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 350,000.00 0.00 Canceled 2022-11-15 2022-11-20 2023-01-01 2023-01-20 2023-02-17 2023-04-21 jeep station wagon ou équiva nvelope and Evaluation lent + 3 pick up) BI-BI-MOF-355350-GO-DIR / Acquisition de 4 véhicules (1 Component 4: Supporting Im Direct - Internation Under Imple station wagon 4X4 et 3 cami IDA / E0700 plementation and Monitoring Post Direct Selection 300,000.00 0.00 2023-04-21 2023-06-02 2023-05-02 2023-03-25 2023-05-23 2023-11-19 al mentation onnettes double cabine 4X4) and Evaluation auprès de l'agence des Natio ns Unies UNOPS BI-BI-MOF-357226-GO-RFB / Component 4: Supporting Im Open - Internationa Single Stage - One E Pending Impl Acquisition d'un système de IDA / E0700 plementation and Monitoring Post Request for Bids 60,000.00 0.00 2023-04-28 2023-05-03 2023-06-14 2023-06-21 2023-07-26 2023-10-27 l nvelope ementation vidéoconférence and Evaluation BI-BI-MOF-360294-GO-RFB / Component 4: Supporting Im Single Stage - One E Pending Impl Acquisition de 14 batteries d' IDA / E0700 plementation and Monitoring Post Request for Bids Open - National 20,000.00 0.00 2023-05-19 2023-05-24 2023-07-05 2023-08-04 2023-09-08 2023-12-15 nvelope ementation un système de back-up élect and Evaluation rique BI-BI-MOF-367786-GO-RFQ / Component 4: Supporting Im Request for Quota Single Stage - One E Pending Impl Acquisition du mobilier de bu IDA / E0700 plementation and Monitoring Post Limited 10,000.00 0.00 2023-07-05 2023-08-16 2023-10-20 tions nvelope ementation reau and Evaluation BI-BI-MOF-367788-GO-RFQ / Component 4: Supporting Im Request for Quota Single Stage - One E Pending Impl Acquisition du matériel infor IDA / E0700 plementation and Monitoring Post Limited 15,000.00 0.00 2023-07-10 2023-08-21 2023-10-27 tions nvelope ementation matique pour l'UGP and Evaluation BI-BI-MOF-367790-GO-RFQ / Component 4: Supporting Im Request for Quota Single Stage - One E Pending Impl Acquisition des climatiseurs IDA / E0700 plementation and Monitoring Post Limited 18,000.00 0.00 2023-07-16 2023-08-25 2023-11-30 tions nvelope ementation de remplacement and Evaluation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DMI/010/PFCGL-II/2018 / Con Improving core trade infrastr ception détaillée nécessaire Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 200,000.00 187,605.23 Completed 2018-04-20 2018-04-16 2018-06-15 2018-09-13 2018-07-22 2018-07-05 2018-08-23 2018-09-28 2018-09-15 2018-10-05 2018-10-20 2018-10-23 2018-11-10 2018-02-15 2019-02-11 2019-11-06 pour le site du projet de cons Based Selection l order areas truction du Port de Rumonge BI-BI-MOF-65618-CS-QCBS / Improving core trade infrastr Conception détaillée nécessa Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 200,000.00 0.00 Canceled 2018-07-05 2018-07-26 2018-08-31 2018-10-03 2018-10-19 2018-11-16 2018-12-07 2019-02-07 ire pour les sites du poste fro Based Selection l order areas ntalier et du marché frontalie r de Gatumba Page 1 BI-BI-MOF-65723-CS-QCBS / Improving core trade infrastr Conception des infrastructur Quality And Cost- IDA / V1000 ucture and facilities in the b Post Open - National 60,000.00 0.00 Canceled 2018-07-15 2018-08-10 2018-09-10 2018-10-15 2018-10-31 2018-11-21 2018-12-05 2019-03-05 es provisoires aux postes fro Based Selection order areas ntaliers de Gatumba et au po rt de Rumonge BI-BI-MOF-71876-CS-QCBS / Improving core trade infrastr Conception détaillée nécessa Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 80,000.00 118,150.00 Completed 2018-08-20 2018-11-19 2018-09-10 2018-11-20 2018-10-15 2019-01-24 2018-11-27 2019-01-15 2018-12-14 2019-01-25 2019-01-18 2019-04-15 2019-02-22 2020-08-20 2019-05-27 2021-07-05 ire pour les sites du poste fro Based Selection l order areas ntière de Gatumba BI-BI-MOF-71879-CS-QCBS / Improving core trade infrastr Quality And Cost- Conception détaillée nécessa IDA / V1000 ucture and facilities in the b Post Open - National 43,130.00 8,504.99 Completed 2018-08-23 2018-09-07 2018-09-13 2018-09-12 2018-10-19 2018-11-08 2018-11-23 2019-01-15 2018-12-10 2019-10-28 2019-01-14 2019-10-28 2019-02-11 2019-03-20 2019-05-13 2020-04-22 Based Selection ire pour le marché frontalier order areas de Gatumba BI-BI-MOF-96822-CS-LCS / A Implementation support, Co udit comptable et financier d Least Cost Selecti Open - Internationa IDA / V1000 mmunication, Monitoring, an Post 25,000.00 13,684.46 Completed 2019-01-28 2019-02-22 2019-02-18 2019-05-20 2019-04-03 2019-10-30 2019-05-01 2019-10-30 2019-05-31 2019-10-30 2019-07-05 2022-02-19 2019-08-09 2019-11-19 2020-02-05 2019-12-06 u PFCGL-II de la période allan on l d Evaluation t du 07/08/2017 au 30/06/20 19 BI-BI-MOF-102626-CS-QCBS / Recrutement d'une firme de Improving core trade infrastr consultants pour le contrôle Quality And Cost- Open - Internationa IDA / V1000 ucture and facilities in the b Post 100,000.00 0.00 Canceled 2019-03-14 2019-04-04 2019-05-17 2019-07-04 2019-07-19 2019-08-16 2019-10-08 2020-10-07 et la surveillance des travaux Based Selection l order areas de construction du port de R umonge et provision de servi ces connexes BI-BI-MOF-203512-CS-CQS / Recrutement d'un bureau en charge de l'élaboration de l'é Improving core trade infrastr tude technique pour l'aména Consultant Qualifi Open - Internationa IDA / V3250 ucture and facilities in the b Post 80,000.00 0.00 Canceled 2020-12-01 2020-12-08 2021-01-14 2021-01-29 2021-02-11 2021-05-11 gement et le bitumage de la cation Selection l order areas RP 108: RN4(PK 14 + 8)/Gatu mba-Vuggizo/Frontière RDC ( 8km)+Etude d'Impact Enviro nnemental et Social (EIES) BI-BI-MOF-203525-CS-CQS / Improving core trade infrastr Etude de faisabilité sur les ch Consultant Qualifi Open - Internationa IDA / V3250 ucture and facilities in the b Post 200,000.00 0.00 Canceled 2020-12-15 2020-12-22 2021-02-04 2021-02-18 2021-03-04 2021-05-19 aînes de valeur des produits cation Selection l order areas agricoles, de pêche et de frui ts BI-BI-MOF-203488-CS-CQS / Etude pour la construction du Improving core trade infrastr marché transfrontalier de Ru Consultant Qualifi IDA / V3250 ucture and facilities in the b Post 50,000.00 0.00 Canceled 2020-11-27 2020-12-10 2021-01-23 2021-02-10 2021-03-17 2021-05-25 monge (incluant l'étude de re cation Selection order areas ntabilité et Etude d'Impact E nironnemental et Social (EIES )) BI-BI-MOF-204468-CS-QCBS / Recrutement d'un cabinet p Implementation of policy an our la réalisation de l'audit o d procedural reforms and ca pérationnel des administratio Quality And Cost- Open - Internationa IDA / V3250 pacity building to facilitate c Post 150,000.00 0.00 Canceled 2020-12-21 2021-01-04 2021-02-03 2021-03-11 2021-03-30 2021-05-04 2021-05-31 2021-10-14 ns des services des frontière Based Selection l ross-border trade in goods a s: étude sur l'efficacité et l'ef nd servic es ficience institutionnelle des a dministrations des services d es frontières BI-BI-MOF-207626-CS-CQS / Component 1. Improving Poli Etude pour la constructiondu Consultant Qualifi Pending Impleme IDA / V3250 cy and Regulatory Environm Post Open - National 40,000.00 0.00 2021-03-08 2021-03-15 2021-04-28 2021-05-28 2021-06-11 2021-09-30 marché transfrontalier de Ru cation Selection ntation ent for cross border trade monge incluant l'étude de re ntabilité BI-BI-MOF-207711-CS-CQS / Etude technique pour l'amén Component 1. Improving Poli Consultant Qualifi Open - Internationa Under Implement agement et le bitumage de l IDA / V3250 cy and Regulatory Environm Post 55,000.00 0.00 2020-12-09 2021-01-27 2020-12-14 2021-02-15 2021-01-20 2022-02-21 2021-02-05 2021-02-15 2021-05-28 cation Selection l ation a RP 108: RN4 (PK14 + 8)Gat ent for cross border trade umba-Vugizo/frontière BI-BI-MOF-207744-CS-CQS / Recrutement d'un cabinet po Implementation of policy an ur la réalisation de l'audit op d procedural reforms and ca érationnel des administration Consultant Qualifi Open - Internationa IDA / V3250 pacity building to facilitate c Post 150,000.00 108,130.00 Signed 2021-01-15 2020-12-21 2021-01-29 2021-03-15 2021-03-14 2022-02-17 2021-04-13 2022-02-17 2021-05-04 2021-12-03 2021-10-31 s des services des frontières cation Selection l ross-border trade in goods a : étude sur l'efficacité et l'effi nd servic es cience institutionnelle des ad ministrations des services de s frontières BI-BI-MOF-207751-CS-CQS / Improving core trade infrastr Etude de faisabilité sur les ch Consultant Qualifi Open - Internationa IDA / V3250 ucture and facilities in the b Post 200,000.00 0.00 Canceled 2020-12-15 2020-12-21 2020-12-22 2021-01-26 2021-02-04 2022-02-18 2021-03-06 2021-03-19 2021-06-18 aînes de valeurs des produits cation Selection l order areas agricoles, de pêche et de frui ts BI-BI-MOF-221288-CS-LCS / Implementation support, Co Audit comptable et financier Least Cost Selecti Open - Internationa IDA / V0960 mmunication, Monitoring, an Post 20,000.00 6,074.00 Completed 2021-03-02 2021-03-01 2021-03-23 2021-05-10 2021-05-06 2022-02-15 2021-06-03 2022-02-15 2021-07-03 2022-02-21 2021-08-07 2022-02-21 2021-10-15 2021-12-07 2021-12-15 2021-12-25 du projet pour la période alla on l d Evaluation nt du 01/07/2020 au 30/06/2 021 BI-BI-MOF-290037-CS-QCBS Component 3: Supporting Co / Recrutement d'un coonsulta Quality And Cost- Open - Internationa Under Implement IDA / V3250 mmercialization of Selected Post 200,000.00 0.00 2022-04-14 2022-04-13 2022-04-20 2022-07-12 2022-05-20 2023-03-22 2022-06-17 2022-07-11 2022-08-15 2022-09-19 2022-12-30 nt chargé de l'étude de l"état Based Selection l ation Cross-border Value Chains des lieux des chaînes de vale ur de l'agribusiness BI-BI-MOF-303406-CS-QCBS / Recrutement d'un consultan Component 3: Supporting Co t chargé de l'élaboration du Quality And Cost- Open - Internationa IDA / V3940 mmercialization of Selected Post 100,000.00 0.00 Canceled 2022-08-19 2022-10-04 2022-09-09 2022-10-23 2022-11-20 2022-12-20 2023-01-24 2023-02-28 2023-04-26 manuel de gestion des subve Based Selection l Cross-border Value Chains ntions aux associations et co opératives des commerçants dans le cadre du PFCIGL BI-BI-MOF-319236-CS-QCBS / Recrutement d'un bureau p our l'élaboration d'une étude Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement IDA / E0700 Post 200,000.00 0.00 2022-11-02 2023-01-13 2022-11-09 2023-04-07 2022-12-23 2023-01-20 2023-02-10 2023-03-03 2023-03-31 2023-07-14 technique pour l'aménageme e Trade Infrastructure Based Selection l ation nt et modernisation des infra structures du poste frontière de Vugizo-Kiliba BI-BI-MOF-207635-CS-CQS / Component 1. Improving Poli Etude pour l'aménagement e Consultant Qualifi Open - Internationa IDA / V3250 cy and Regulatory Environm Post 40,000.00 0.00 Canceled 2020-12-11 2020-12-22 2020-12-18 2021-01-26 2021-01-22 2021-02-21 2021-03-05 2021-05-17 t la modernisation du poste-f cation Selection l ent for cross border trade rontière Vugizo-Kiliba Page 2 BI-BI-MOF-203504-CS-CQS / Recrutement d'un bureau ch argé de l'élaboration de l'étu Improving core trade infrastr Consultant Qualifi de pour l'aménagement et m IDA / V3250 ucture and facilities in the b Post Open - National 60,000.00 0.00 Canceled 2020-11-18 2020-11-25 2021-01-08 2021-02-07 2021-02-19 2021-04-26 cation Selection odernisation poste-frontière order areas Vugizo-Kiliba + Etude d'Imp act Environnemental et Socia l (EIES) BI-BI-MOF-335979-CS-QCBS / Recrutement d'un bureau d' un bureau pour la réalisation Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement de la réalisation d'une étude IDA / E0700 Post 100,000.00 0.00 2023-01-20 2023-04-04 2023-01-25 2023-06-05 2023-02-17 2023-04-03 2023-04-14 2023-05-12 2023-06-09 2023-09-15 e Trade Infrastructure Based Selection l ation de rentabilité économique et l'adaptation de l'étude techni que pour la construction du marché transfrontalier de Ga tumba BI-BI-MOF-335987-CS-QCBS / Recrutement d'un bureau p Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement our la surveillance/contrôle d IDA / E0700 Post 700,000.00 0.00 2023-01-20 2023-01-18 2023-01-27 2023-04-05 2023-02-17 2023-04-04 2023-04-14 2023-05-05 2023-05-29 2024-05-28 e Trade Infrastructure Based Selection l ation es travaux de construction d u poste frontière de Gatumb a-Kavimvira BI-BI-MOF-335989-CS-QCBS / Recrutement d'un bureau p our la surveillance/contrôle d Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement es travaux de construction d IDA / E0700 Post 1,800,000.00 0.00 2023-01-24 2023-01-19 2023-01-31 2023-02-23 2023-02-21 2023-04-05 2023-04-19 2023-05-05 2023-05-31 2026-05-29 e Trade Infrastructure Based Selection l ation u port de Rumonge et provisi on de services connexes y co mpris l'actualisation des étud es techniques BI-BI-MOF-338261-CS-QCBS / Recrutement d'un bureau c hargé de l'élaboration de l'ét Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement IDA / E0710 Post 200,000.00 0.00 2023-02-15 2023-01-25 2023-02-21 2023-03-30 2023-03-30 2023-05-10 2023-05-26 2023-06-30 2023-07-21 2023-10-30 ude technique d'aménageme e Trade Infrastructure Based Selection l ation nt et de bitumage de la RP 1 08: RN 4/Gatumba - Vugizo/fr ontière RDC (8 km) BI-BI-MOF-338268-CS-QCBS / Recrutement d'une firme ch Component 3: Supporting Co Quality And Cost- Open - Internationa Under Implement argée de la gestion du méca IDA / E0700 mmercialization of Selected Post 300,000.00 0.00 2023-02-20 2023-03-13 2023-02-27 2023-03-30 2023-04-05 2023-05-12 2023-05-26 2023-06-30 2023-07-21 2025-07-18 Based Selection l ation nisme de subventions aus as Cross-border Value Chains sociations et coopératives de commerçants BI-BI-MOF-357217-CS-QCBS / Recrutement d'un bureau d' Component 2: Improving Cor Quality And Cost- Open - Internationa Under Implement étude pour l'aménagement e IDA / E0700 Post 400,000.00 0.00 2023-04-24 2023-04-26 2023-04-26 2023-06-12 2023-06-02 2023-07-07 2023-07-28 2023-08-25 2023-09-22 2023-12-29 e Trade Infrastructure Based Selection l ation t modernisation des postes fr ontières de Buganda et Mpar ambo BI-BI-MOF-362749-CS-QCBS / Recrutement d'une ONG po Component 4: Supporting Im Quality And Cost- Open - Internationa Under Implement ur la mise en oeuvre des PAR IDA / E0700 plementation and Monitoring Post 100,000.00 0.00 2023-05-31 2023-05-29 2023-06-07 2023-07-14 2023-08-11 2023-08-25 2023-09-22 2023-10-20 2024-06-28 Based Selection l ation du port de Rumonge et du po and Evaluation ste frontière de Gatumba BI-BI-MOF-365295-CS-QCBS / Recrutement d'un bureau c hargé de l'étude d'aménage Component 2: Improving Cor Quality And Cost- Open - Internationa IDA / E0700 Post 200,000.00 0.00 Under Review 2023-06-12 2023-06-19 2023-06-20 2023-08-03 2023-08-31 2023-09-22 2023-10-20 2023-11-17 2024-02-28 ment et de bitumage des voi e Trade Infrastructure Based Selection l es d'accès aux postes frontiè res de Buganda et Mparamb o BI-BI-MOF-367793-CS-LCS / Component 4: Supporting Im Least Cost Selecti Recrutement d'un cabinet d' IDA / E0700 plementation and Monitoring Post Open - National 15,000.00 0.00 Under Review 2023-06-30 2023-06-27 2023-07-10 2023-08-16 2023-08-23 2023-09-08 2023-09-29 2023-10-27 2024-10-26 on audit interne du projet and Evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DMI/002/PFCGL-II/2017 / Ela boration du Cadre de Politiqu e des Peuples Autochtones ( Improving core trade infrastr Individual Consult Pending Impleme CPPA), du Plan en faveur des IDA / V1000 ucture and facilities in the b Post Open 30,000.00 0.00 2017-12-11 2018-01-20 2018-02-06 2018-02-09 2018-03-18 ant Selection ntation populations autochtones (PP order areas A) du Cadre de Politique de R éinstallation (CPR) pour les a ctivitésdu Projet GLTFP BI-BI-MOF-65639-CS-INDV / Improving core trade infrastr Individual Consult IDA / V1000 Post Open 50,000.00 0.00 Canceled 2018-07-27 2018-09-05 2018-09-19 2018-10-04 2018-12-18 Etude sur la logistique et le tr ucture and facilities in the b ant Selection ansport order areas BI-BI-MOF-65645-CS-INDV / Implementation of policy an Enquête auprès des commer d procedural reforms and ca Individual Consult çants des associations profes IDA / V1000 pacity building to facilitate c Post Open 60,000.00 0.00 Canceled 2018-08-05 2018-09-12 2018-09-26 2018-10-10 2019-01-10 ant Selection sionnelles et évaluation des ross-border trade in goods a besoins pour le renforcement nd servic es des capacités BI-BI-MOF-71086-CS-INDV / Implementation support, Co Individual Consult Pending Impleme Consultant Expert en Sauveg IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-07-24 2018-10-28 2018-11-20 2018-11-23 2019-05-19 ant Selection ntation ardes Environnementales et d Evaluation Sociales BI-BI-MOF-71104-CS-INDV / Improving core trade infrastr Elaboration du Cadre de Gest Individual Consult Pending Impleme IDA / V1000 ucture and facilities in the b Post Open 16,210.00 0.00 2018-07-24 2018-08-31 2018-09-24 2018-09-25 2018-11-01 ion Environnementale et Soci ant Selection ntation order areas ale (CGES) du Projet GLTFP DMI/006/PFCGL-II/2018 / Con Implementation support, Co Individual Consult Pending Impleme sultant Responsable en Suivi- IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-07-24 2018-09-16 2018-12-02 2018-12-03 2019-12-02 ant Selection ntation Evaluation d Evaluation DMI/004/PFCGL-II/2018 / Con Implementation support, Co Individual Consult Under Implement sultant Expert en Facilitation IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-01-26 2018-01-25 2018-05-25 2018-05-25 2018-05-28 2019-05-27 ant Selection ation du Commerce d Evaluation BI-BI-MOF-65604-CS-INDV / Implementation support, Co Individual Consult Pending Impleme Consultant Responsable Adm IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-06-07 2018-07-10 2018-07-17 2018-07-23 2019-07-22 ant Selection ntation inistratif et Financier d Evaluation DMI/003/PFCGL-II/2018 / Con Implementation support, Co Individual Consult sultant Coordinateur du proje IDA / V1000 mmunication, Monitoring, an Post Open 48,000.00 0.00 Under Review 2018-01-26 2018-01-19 2018-05-10 2018-05-10 2018-05-14 2019-05-13 ant Selection t d Evaluation Page 3 DMI/007/PFCGL-II/2018 / Con Implementation support, Co Individual Consult Pending Impleme sultant Responsable Passatio IDA / V1000 mmunication, Monitoring, an Post Open 40,800.00 0.00 2018-01-26 2018-05-25 2018-05-28 2018-05-28 2019-05-27 ant Selection ntation n des Marchés d Evaluation Implementation support, Co DMI/009/PFCGL-II/2018 / Con Individual Consult IDA / V1000 mmunication, Monitoring, an Post Open 24,000.00 0.00 Under Review 2018-01-26 2018-06-08 2018-06-05 2018-06-07 2018-07-01 2019-06-30 sultant Comptable du projet ant Selection d Evaluation BI-BI-MOF-65720-CS-INDV / Implementation of policy an Enumérateurs et Superviseur d procedural reforms and ca Individual Consult Under Implement s pour l'enquête de base et p IDA / V1000 pacity building to facilitate c Post Open 16,631.00 0.00 2018-06-27 2018-11-05 2018-08-06 2018-08-20 2018-08-31 2018-10-31 ant Selection ation our la collecte des données s ross-border trade in goods a ur le commerce transfrontali nd servic es er BI-BI-MOF-170399-CS-INDV / Recrutement d'un consultant Improving service delivery b Individual Consult pour réaliser l'identification e IDA / V3250 y agencies at the border/por Post Open 30,000.00 43,617.38 Completed 2020-08-25 2020-11-05 2020-10-13 2022-02-21 2020-11-03 2022-02-21 2020-12-08 2021-01-13 2021-02-13 2021-04-24 ant Selection t la cartographie des associat t and citizen engagement ions des commerçants transf rontaliers BI-BI-MOF-170412-CS-INDV / Implementation support, Co Recrutement d'un consultant Individual Consult Pending Impleme IDA / V3250 mmunication, Monitoring, an Post Open 20,000.00 0.00 2020-07-31 2020-09-18 2020-10-09 2020-11-13 2021-01-22 en charge de l'élaboration d' ant Selection ntation d Evaluation une stratégie de communicat ion du projet BI-BI-MOF-182061-CS-INDV / Implementation support, Co Individual Consult Under Implement Conception et réalisation du IDA / V3250 mmunication, Monitoring, an Post Open 20,000.00 0.00 2020-08-24 2023-02-21 2020-10-12 2020-11-02 2020-12-07 2021-01-29 ant Selection ation site web PFCGL-II d Evaluation BI-BI-MOF-182703-CS-CDS / Implementation support, Co Audit comptable et financier IDA / V3250 mmunication, Monitoring, an Post Direct Selection Direct 20,000.00 10,844.85 Completed 2020-08-04 2020-07-15 2020-08-14 2020-08-11 2020-10-09 2020-11-03 2020-11-30 2020-12-29 du projet (exercice de juillet d Evaluation 2019 à juin 2020) BI-BI-MOF-203519-CS-INDV / Improving core trade infrastr Individual Consult Recrutement d'un consultant IDA / V3250 ucture and facilities in the b Post Open 20,000.00 0.00 Canceled 2020-11-17 2020-12-29 2021-01-12 2021-02-09 2021-03-15 ant Selection pour la mise à jour du CGES order areas et du CPR BI-BI-MOF-207798-CS-INDV / Component 1. Improving Poli Individual Consult Under Implement Recrutement d'un expert en i IDA / V3250 cy and Regulatory Environm Post Open 40,000.00 0.00 2020-12-09 2020-12-18 2021-01-20 2022-01-06 2021-02-03 2022-01-11 2021-02-08 2022-01-31 ant Selection ation nfrastructures ent for cross border trade BI-BI-MOF-207950-CS-CDS / Entente Directe avec le Cons Improving core trade infrastr ultant Dr NIYONKURU Charles IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 15,000.00 0.00 Canceled 2020-12-10 2020-12-14 2020-12-24 2021-01-29 pour l'Elaboration du CGES + order areas Plan de Gestion des Pestes et Pesticides (PGPP) BI-BI-MOF-207964-CS-CDS / Entente Directe avec le Cons ultant CIMPAYE Joachim pour Improving core trade infrastr la Mise à jour des rapports d'I IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 10,000.00 0.00 Canceled 2020-12-12 2020-12-22 2021-01-06 2021-02-15 mpact Environnemental et S order areas ocial (EIES) pour la constructi on du Port de Rumonge et la construction du marché de G atumba BI-BI-MOF-207970-CS-CDS / Entente Directe avec le Cons Improving core trade infrastr ultant Dr MISAGO Aloispour l IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 10,000.00 0.00 Canceled 2020-12-18 2020-12-28 2021-01-13 2021-02-19 a Préparation du Plan dActio order areas n de Réinstallation (PAR) des Personnes affectées pour la c onstruction du Port de Rumo nge BI-BI-MOF-225823-CS-CDS / Entente Directe avec Monsie ur NDIKUMANA Denis pour l'a Improving core trade infrastr ctualisation/mise à jour des E IDA / V0960 ucture and facilities in the b Post Direct Selection Direct 10,000.00 9,834.66 Completed 2021-03-24 2021-03-24 2021-03-26 2021-03-25 2021-04-02 2021-03-31 2021-05-03 2021-10-20 IES du sous-projet de constru order areas ction du port de Rumonge et celui de construction du mar ché transfrontalier de Gatum ba BI-BI-MOF-239602-CS-CDS / Implementation support, Co Entente Directe avec le bure IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 79,400.00 70,447.09 Signed 2021-06-22 2021-06-17 2021-07-02 2022-02-15 2021-07-30 2021-10-06 2022-01-14 au GETA pour pour l'élaborat d Evaluation ion du CGES du PFCIGL BI-BI-MOF-207962-CS-CDS / Entente Directe avec le Cons ultant BARAKAMFITIYE Tharci Improving core trade infrastr sse pour l'Elaboration du Cad IDA / V3250 ucture and facilities in the b Post Direct Selection Direct 15,000.00 0.00 Canceled 2020-12-11 2020-12-21 2021-01-12 2021-02-16 re de Politique de Réinstallati order areas on (CPR) + Cadre de Planifica tion en faveur des Peuples A utochtones (CPPA) BI-BI-MOF-246029-CS-CDS / Implementation support, Co Entente directe avec Madam IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 26,000.00 33,246.84 Signed 2021-07-30 2021-07-28 2021-08-09 2021-09-03 2021-10-13 2021-05-12 2021-11-01 e Clotilde NIZIGAMA, Coordo d Evaluation nnateur du projet pour l'Actu alisation du contrat BI-BI-MOF-246032-CS-CDS / Entente directe avec Mr BAT Implementation support, Co UNGWANAYO Léonidas, Resp IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 21,600.00 30,476.27 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-02 2021-10-13 2021-07-27 2022-04-30 onsable Administratif et Fina d Evaluation ncier pour l'Actualisation du contrat BI-BI-MOF-246034-CS-CDS / Entente directe avec Monsie Implementation support, Co ur Cyprien BARAMBONERANY IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 24,700.00 27,710.10 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-02 2021-10-13 2021-05-29 2022-04-30 E, Responsable de la Passati d Evaluation on des Marchés pour l'actuali sation du contrat BI-BI-MOF-246037-CS-CDS / Entente directe avec Mr BIRE Implementation support, Co HANISENGE Adophe, Expert IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 24,800.00 30,224.40 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-03 2021-10-13 2021-05-29 2022-04-30 en Facilitation du Commerce d Evaluation et Secteur Privé pour l'actuali sation du contrat BI-BI-MOF-246040-CS-CDS / Entente directe avec Madam Implementation support, Co e KABURA Marie Rose, Respo IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 19,800.00 27,705.70 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-03 2021-10-13 2021-07-21 2022-04-30 nsable des Sauvegardes envi d Evaluation ronnementales pour l'actuali sation du contrat BI-BI-MOF-246044-CS-CDS / Implementation support, Co Entente directe avec Mr Césa IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 19,800.00 27,705.70 Signed 2021-07-30 2021-07-29 2021-08-09 2021-09-02 2021-10-13 2021-06-08 2022-04-30 r Abel MAYELE pour l'actualis d Evaluation ation du contrat Page 4 BI-BI-MOF-246046-CS-CDS / Implementation support, Co Entente directe avec Madam IDA / V0960 mmunication, Monitoring, an Post Direct Selection Direct 17,700.00 16,623.42 Signed 2021-07-30 2021-07-28 2021-08-09 2021-09-03 2021-10-13 2021-07-01 2022-04-30 e NIYOKINDI Consolée pour l' d Evaluation actualisation du contrat BI-BI-MOF-253433-CS-INDV / Implementation support, Co Individual Consult Réalisation d'une enquête de IDA / V0960 mmunication, Monitoring, an Post Open 45,000.00 41,703.71 Signed 2021-09-17 2021-09-17 2021-10-29 2022-02-15 2021-11-05 2022-02-15 2021-11-16 2021-12-16 2022-05-15 ant Selection base dans la zone du PFCIGL d Evaluation BI-BI-MOF-257902-CS-INDV / Entente Directe avec Monsie ur Denis NDIKUMANA pour l'É Component 2: Improving Cor Individual Consult laboration du PAR pour la co IDA / V3250 Post Direct 12,000.00 14,557.51 Signed 2021-10-25 2021-11-22 2021-11-04 2022-02-01 2021-11-15 2022-02-01 2021-11-21 2021-12-14 2021-12-31 e Trade Infrastructure ant Selection nstruction du port de Rumon ge et l’actualisation du PAR p our le poste frontière de Gat umba BI-BI-MOF-262743-CS-CDS / Entente Directe avec la firme CHEMAS pour l'élaboration d Component 2: Improving Cor e l'EIES/PGES et du PAR de la IDA / V3250 Post Direct Selection Direct 420,000.00 0.00 Canceled 2021-11-15 2021-11-19 2022-01-14 2022-02-28 e Trade Infrastructure RN3, projet pilote TNM, du Bo ulevard NDADAYE et du Cont ournement Ouest de Bujumb ura pour le PRT BI-BI-MOF-262749-CS-CDS / Entente Directe avec la firme CHEMAS pour l'assistance te chnique en sauvegardes envi Component 2: Improving Cor ronnementales et sociales et IDA / V3250 Post Direct Selection Direct 300,000.00 0.00 Canceled 2021-11-15 2021-11-21 2022-01-05 2022-03-15 e Trade Infrastructure la préparation des dossiers d u Cadre Environnemental et Social pour PRT et le contrô le qualité des documents de sauvegarde du PFCIGL BI-BI-MOF-303392-CS-CDS / Entente Directe avec Mr NIVY Component 4: Supporting Im Under Implement INTIZO Scarie pour l'élaborati IDA / V3940 plementation and Monitoring Post Direct Selection Direct 50,000.00 0.00 2022-07-13 2022-08-11 2022-07-23 2022-10-18 2022-08-30 2022-10-29 ation on des manuels de procédur and Evaluation es et d'execution du Projet BI-BI-MOF-303396-CS-INDV / Component 2: Improving Cor Individual Consult Pending Impleme Etude de rentabilité du marc IDA / V3940 Post Open 50,000.00 0.00 2022-08-15 2022-10-03 2022-10-24 2022-11-28 2023-01-27 e Trade Infrastructure ant Selection ntation hé transfrontalier de Gatumb a BI-BI-MOF-303470-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un spécialiste IDA / V3940 plementation and Monitoring Post Open 3,500.00 0.00 2022-07-29 2022-08-24 2022-09-16 2022-10-07 2022-11-11 2023-02-10 ant Selection ation en communication and Evaluation BI-BI-MOF-303472-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un spécialiste IDA / V3940 plementation and Monitoring Post Open 4,000.00 0.00 2022-08-04 2022-09-12 2022-09-22 2022-10-13 2022-11-17 2023-02-16 ant Selection ation en VBG and Evaluation BI-BI-MOF-303474-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un spécialiste IDA / V3940 plementation and Monitoring Post Open 4,000.00 0.00 2022-08-10 2022-09-06 2022-09-28 2022-10-19 2022-11-23 2023-02-22 ant Selection ation en Développement social and Evaluation BI-BI-MOF-304400-CS-INDV / Actualisation de l'étude d'im Component 4: Supporting Im pact environnemental et soci Individual Consult Under Implement IDA / V3250 plementation and Monitoring Post Open - National 15,000.00 0.00 2022-07-19 2022-08-09 2022-09-06 2022-09-27 2022-11-01 2022-12-06 al (EIES) pour la construction ant Selection ation and Evaluation et modernisation du poste fr ontière de Gatumba-Kavimvir a BI-BI-MOF-312567-CS-CDS / Component 4: Supporting Im Entente Directe avec le cabin Direct - Internation Under Implement IDA / V3250 plementation and Monitoring Post Direct Selection 15,000.00 0.00 2022-09-06 2022-09-19 2022-09-16 2022-10-14 2022-11-11 2022-12-15 et pour l'audit comptable et f al ation and Evaluation inancier exercice de juillet 20 21 à juin 2022 BI-BI-MOF-319230-CS-INDV / Recrutement d'un Consultant pour l'élaboration d'une étud Component 1. Improving Poli e sur les natures et causes d Individual Consult Pending Impleme IDA / E0700 cy and Regulatory Environm Post Open - National 30,000.00 0.00 2022-12-15 2023-02-02 2023-02-23 2023-03-16 2023-05-30 es conflits entre les administr ant Selection ntation ent for cross border trade ations des frontières et les co mmerçants, entre les service s ou entre les commerçants au niveau des frontières ciblé es du projet BI-BI-MOF-319247-CS-INDV / Réalisation de l'Etude d'Impa ct Environnemental et Social Component 2: Improving Cor Individual Consult Pending Impleme IDA / E0700 Post Open - National 25,000.00 0.00 2023-04-20 2023-06-08 2023-06-22 2023-07-13 2023-09-22 (EIES) des travaux d'aménag e Trade Infrastructure ant Selection ntation ement et modernisation des i nfrastructures du poste fronti ère de Vugizo-Kiliba BI-BI-MOF-319248-CS-INDV / Recrutement d'un consultant pour la préparation du plan d Component 2: Improving Cor Individual Consult Pending Impleme 'action de réinstallation des t IDA / E0700 Post Open - National 30,000.00 0.00 2023-04-27 2023-06-08 2023-06-22 2023-07-13 2023-09-29 e Trade Infrastructure ant Selection ntation ravaux d'aménagement et m odernisation des infrastructur es du poste frontière de Vugi zo-Kiliba BI-BI-MOF-335993-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un assistant e IDA / E0700 plementation and Monitoring Post Open - National 36,000.00 0.00 2023-01-18 2023-01-19 2023-02-15 2023-03-08 2023-03-30 2024-03-29 ant Selection ation n passation des marchés and Evaluation BI-BI-MOF-335996-CS-INDV / Component 4: Supporting Im Individual Consult Under Implement Recrutement d'un assistant c IDA / E0700 plementation and Monitoring Post Open - National 36,000.00 0.00 2023-01-26 2023-01-30 2023-03-01 2023-03-15 2023-04-05 2024-04-04 ant Selection ation omptable and Evaluation BI-BI-MOF-344280-CS-QCBS Component 4: Supporting Im / Recrutement d'un bureau p Individual Consult Open - Internationa IDA / E0700 plementation and Monitoring Post 100,000.00 0.00 Canceled 2023-03-31 2023-04-03 2023-05-03 2023-05-24 2023-06-21 2023-09-29 our effectuer un audit techni ant Selection l and Evaluation que du Bureau Burundais de Normalisation (BBN) BI-BI-MOF-353142-CS-INDV / Recrutement d'un consultant Component 2: Improving Cor Individual Consult Under Implement individuel pour la conception IDA / E0700 Post Open - National 20,000.00 0.00 2023-03-31 2023-04-03 2023-05-03 2023-05-17 2023-06-16 2023-08-16 e Trade Infrastructure ant Selection ation des infrastructures provisoire s aux postes frontières de Bu ganda et Mparambo Page 5 BI-BI-MOF-360296-CS-CDS / Entente Directe avec le cabin Component 4: Supporting Im Direct - Internation Under Implement et ABC pour l'audit comptabl IDA / E0700 plementation and Monitoring Post Direct Selection 15,000.00 0.00 2023-05-12 2023-05-20 2023-05-22 2023-05-29 2023-07-26 2023-11-15 al ation e et financier de l'exercice de and Evaluation juillet 2022 à juin 2023 BI-BI-MOF-364126-CS-INDV / RECRUTEMENT D'UN CONSUL TANT CHARGE D'EFFECTUER Component 3: Supporting Co UN AUDIT TECHNIQUE ET INS Individual Consult Open - Internationa IDA / E0700 mmercialization of Selected Post 100,000.00 0.00 Under Review 2023-06-05 2023-06-05 2023-07-17 2023-07-31 2023-09-04 2023-11-17 TITUTIONNEL DU BUREAU BU ant Selection l Cross-border Value Chains RUNDAIS DE NORMALISATIO N ET CONTROLE DE LA QUALI TE (BBN) EN MATIERE DE CE RTIFICATION BI-BI-MOF-365300-CS-INDV / Component 4: Supporting Im Recrutement d'un consultant Individual Consult Pending Impleme IDA / E0700 plementation and Monitoring Post Open - National 25,000.00 0.00 2023-07-20 2023-08-31 2023-09-14 2023-10-19 2023-12-15 pour l'élaboration du plan de ant Selection ntation and Evaluation gestion de la biodiversité Page 6 PLAN DE PASSATION DE MARCHÉS (Texte) Information sur le Projet : Djibouti, Projet Intégré de Résorption des Bidonvilles (P162901) Agence d’exécution du Projet : Fonds de l’Habitat Date du plan de passation des marchés : 2 novembre 2017 Période couverte par ce plan de passation des marchés : 17 juillet 2017-31 décembre 2018 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la Loi n°53/AN/09/6ème L portant Nouveau Code des Marchés Publics, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés : « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux : ne s’applique pas PROCUREMENT Djibouti : Djibouti Integrated Slum Upgrading Project PLAN General Information Country: Djibouti 2017-11-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162901 GPN Date: Project Name: Djibouti Integrated Slum Upgrading Project Loan / Credit No: IDA / V0980, IDA / 63380, IDA / D7590 Habitat Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned DJ-FDH-68733-CW-RFB / Rec Participatory upgrading inve rutement d'une entreprise po Single Stage - One E 1,725,830.5 2019-05-2 IDA / V0980 stments in selected urban ar Post Request for Bids Open - National 1,500,000.00 Completed 2018-08-01 2018-11-23 2018-08-06 2018-09-17 2019-01-30 2018-10-17 2019-02-20 2018-11-21 2019-04-23 ur les travaux de constructio nvelope 1 0 eas n de la voie de désenclavem ent de Balbala ancien DJ-FDH-126388-CW-RFB / Tr Participatory upgrading inve avaux de démolition/reconstr Single Stage - One E 2019-12-1 IDA / 63380 stments in selected urban ar Post Request for Bids Limited 600,000.00 894,180.22 Signed 2019-08-15 2019-09-01 2019-08-20 2019-09-02 2019-09-10 2019-09-25 2019-09-25 2019-12-04 2019-10-16 2020-01-09 uction des biens physiques i nvelope 5 eas mpactés par la voie commer çante DJ-FDH-68740-CW-RFB / Rec rutement d'une entreprise po Participatory upgrading inve Single Stage - One E 2019-02-1 ur les travaux de reconstructi IDA / V0980 stments in selected urban ar Post Request for Bids Limited 70,000.00 0.00 Canceled 2018-08-01 2018-08-06 2018-09-17 2018-10-17 2018-11-21 nvelope 9 on des biens eas physiques impactés par la vo ie commercante DJ-FDH-126389-CW-RFB / Tr Participatory upgrading inve Open - Internationa Single Stage - One E 1,788,421.6 2020-11-1 avaux d'aménagement de la IDA / 63380 stments in selected urban ar Post Request for Bids 2,000,000.00 Signed 2020-01-30 2021-05-05 2020-02-04 2021-05-16 2020-03-17 2021-06-10 2020-04-16 2021-06-23 2020-05-21 2021-10-06 l nvelope 2 7 zone de récasement eas DJ-FDH-209424-CW-RFQ / Tr avaux d'aménagement des l Emergency response to COV Request for Quota Single Stage - One E 2021-07-0 ocaux de l'ARULoS pour resp IDA / 63380 Post Open - National 100,000.00 99,829.27 Signed 2021-01-08 2021-03-05 2021-05-27 ID-19 and to the floods tions nvelope 3 ecter la politique de préventi on et de la propagation du C ovid-19 DJ-FDH-209425-CW-RFQ / Tr Emergency response to COV Request for Quota Single Stage - One E 2021-05-2 avaux de construction d'un o IDA / 63380 Post Open - National 400,000.00 534,835.13 Signed 2020-12-26 2021-02-20 2021-05-27 ID-19 and to the floods tions nvelope 1 uvrage de drainage à Nassib DJ-FDH-239880-CW-DIR / Tra vaux d’électricité et d’éclaira Participatory upgrading inve Other (with field f 2022-02-0 ge public de la mailles 2 de l IDA / 63380 stments in selected urban ar Post Direct Selection Direct 600,700.00 599,655.84 Signed 2021-07-01 2021-07-04 2021-07-06 2021-09-29 2021-08-10 2022-02-17 or explanation) 6 a zone de relogement et de p eas révention de Balbala Sud Request for Bids - DJ-FDH-266465-CW-RFB / Tr Participatory upgrading inve Single Stage - One E Works (without pr 1,441,292.3 2022-07-2 avaux de voirie de Balbala a IDA / 63380 stments in selected urban ar Post Request for Bids Open - National 1,500,000.00 Signed 2021-10-04 2021-10-05 2021-10-09 2021-11-20 2021-11-17 2021-12-20 2021-11-24 2022-01-24 2022-03-11 nvelope equalification) SP 1 3 ncien: 2 voies en pierre taillé eas D es Request for Bids - DJ-FDH-301096-CW-RFB / Co Participatory upgrading inve Single Stage - One E Small Works SPD Under Imple 2023-08-1 nstruction d'un CDC et d'un t IDA / 63380 stments in selected urban ar Post Request for Bids Open - National 310,000.00 0.00 2022-06-29 2022-06-22 2022-07-04 2022-08-15 2022-09-14 2022-10-19 nvelope (1 envelope proce mentation 5 errain de sport à Balbala Anci eas ss) en DJ-FDH-353352-CW-RFB / Tr Request for Bids - Participatory upgrading inve avaux de construction des éq Single Stage - One E Works (without pr Under Imple 2024-07-1 IDA / 63380 stments in selected urban ar Post Request for Bids Open - National 335,000.00 0.00 2023-03-28 2023-05-03 2023-04-02 2023-05-14 2023-06-13 2023-07-18 uipements publics pour le qu nvelope equalification) SP mentation 7 eas artier 9 du Balbala ancien D GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-FDH-102334-GO-RFB / Ac Single Stage - One E quisition de deux véhicules Pi IDA / V0980 Project management Post Request for Bids Open - National 70,000.00 59,941.03 Completed 2019-02-21 2019-02-26 2019-03-26 2019-03-27 2019-04-16 2019-04-10 2019-05-21 2019-05-02 2019-06-20 2019-06-02 nvelope ck up pour la coordination et le suivi DJ-FDH-126354-GO-RFQ / Ac Request for Quota Single Stage - One E IDA / 63380 Project management Post Limited 30,000.00 27,805.88 Completed 2019-08-30 2019-09-09 2019-10-25 2019-10-20 2020-04-22 2019-11-20 hats de matériels informatiqu tions nvelope es DJ-FDH-126373-GO-RFQ / Ac Request for Quota Single Stage - One E IDA / 63380 Project management Post Limited 30,000.00 27,253.76 Completed 2019-08-30 2019-09-09 2019-10-25 2019-10-20 2020-04-22 2019-11-20 hats de mobiliers de bureaux tions nvelope DJ-FDH-126411-GO-RFQ / Ac Participatory upgrading inve quisition des équipements inf Request for Quota Single Stage - One E IDA / 63380 stments in selected urban ar Post Limited 12,000.00 27,962.83 Completed 2019-10-05 2022-04-19 2019-11-30 2022-07-05 2019-12-30 2022-07-27 ormatiques et des mobiliers tions nvelope eas pour l'Ingénierie Sociale DJ-FDH-34737-GO-RFQ / Ach Request for Quota Single Stage - One E at d'ordinateur et de mobilier IDA / V0980 Post Open - National 20,000.00 0.00 Canceled 2017-11-20 2018-01-15 2018-03-01 tions nvelope s de bureaux pour l'expert DJ-FDH-126409-GO-RFB / Ac Participatory upgrading inve quisition d'un véhicule pour l Request for Quota Single Stage - One E IDA / 63380 stments in selected urban ar Post Open - National 28,000.00 28,057.86 Completed 2019-09-14 2019-11-09 2020-01-08 2019-12-09 2020-02-24 a supervision et le déplacem tions nvelope eas ent de l'équipe de l'Ingénieri e Sociale DJ-FDH-202547-GO-RFQ / Ac Emergency response to COV Request for Quota Single Stage - One E quisition de matériaux de co IDA / 63380 Post Open - National 900,000.00 474,493.70 Signed 2020-11-13 2021-01-08 2021-10-11 2022-01-08 ID-19 and to the floods tions nvelope nstructions - Ciments et fer à béton DJ-FDH-202581-GO-RFQ / Ac Emergency response to COV Request for Quota Single Stage - One E quisition de matériaux de co IDA / 63380 Post Open - National 400,000.00 301,839.69 Signed 2020-11-13 2021-01-08 2021-07-28 2022-01-08 ID-19 and to the floods tions nvelope nstructions - Parpaings DJ-FDH-202582-GO-RFQ / Ac Emergency response to COV Request for Quota Single Stage - One E quisition de matériaux de co IDA / 63380 Post Open - National 300,000.00 291,588.33 Signed 2020-11-13 2021-01-08 2022-06-16 2022-01-08 ID-19 and to the floods tions nvelope nstructions - Menuiseries Page 1 DJ-FDH-202583-GO-RFQ / Ac Emergency response to COV Request for Quota Single Stage - One E quisition de matériaux de co IDA / 63380 Post Open - National 300,000.00 238,959.48 Signed 2020-11-13 2021-01-08 2021-07-28 2022-01-08 ID-19 and to the floods tions nvelope nstructions - Toiture et quinc ailleries DJ-FDH-216883-GO-RFB / Ac Support to the elaboration of quisitions des véhicules et de Single Stage - One E IDA / 63380 the ZSP strategic framework Post Request for Bids Open - National 285,000.00 277,854.30 Completed 2020-08-23 2020-08-24 2020-08-28 2020-10-09 2020-09-16 2020-11-08 2020-10-07 2020-12-13 2020-10-15 2021-02-11 2020-12-29 s engins de construction pour nvelope and investment plan la préfecture de Djibouti DJ-FDH-236685-GO-RFQ / Ac Support to the elaboration of Request for Quota Single Stage - One E quisition de matériels inform IDA / 63380 the ZSP strategic framework Post Open - National 30,000.00 49,890.34 Completed 2021-05-14 2021-07-09 2021-10-29 2021-09-07 2021-12-31 tions nvelope atiques pour le compte de la and investment plan DATUH DJ-FDH-239886-GO-RFB / Ac Single Stage - One E IDA / D7590 Project management Post Request for Bids Open - National 120,000.00 84,443.92 Completed 2021-07-01 2021-07-28 2021-07-06 2021-08-05 2021-08-25 2021-08-20 2021-09-01 2021-09-24 2021-09-28 2021-11-23 2021-10-06 quistion de véhicules nvelope DJ-FDH-266862-GO-RFB / Ac Support to the elaboration of Single Stage - One E quisitions de 3 vehicules pick IDA / D7590 the ZSP strategic framework Post Request for Bids Open - National 105,000.00 92,845.70 Completed 2021-09-01 2021-09-23 2021-09-06 2021-10-06 2021-10-27 2021-10-20 2021-11-03 2021-11-24 2021-11-19 2021-12-24 2021-12-27 nvelope up au profit de la DDCF and investment plan DJ-FDH-244881-GO-RFQ / Ac quisition et installation d'une Support to the elaboration of Single Stage - One E station CORS et les logiciels c IDA / 63380 the ZSP strategic framework Post Request for Bids Open - National 80,000.00 0.00 Canceled 2021-09-08 2021-09-05 2021-09-13 2021-10-13 2021-10-27 2021-10-28 2021-12-02 2022-03-02 nvelope orrespondants pour la Directi and investment plan on des Domaines et de la Co nservation Foncière DJ-FDH-244878-GO-RFQ / Ac Support to the elaboration of quisition de tablettes pour la Request for Quota Single Stage - One E IDA / D7590 the ZSP strategic framework Post Open - National 34,000.00 0.00 Canceled 2021-08-06 2021-10-01 2021-12-30 Direction des Domaines et de tions nvelope and investment plan la Conservation Foncière DJ-FDH-244876-GO-RFQ / Ac Support to the elaboration of quisition de GPS pour la Dire Single Stage - One E IDA / 63380 the ZSP strategic framework Post Request for Bids Open - National 85,000.00 0.00 Canceled 2021-09-08 2021-09-05 2021-09-13 2021-10-13 2021-10-27 2021-10-28 2021-12-02 2022-03-02 ction des Domaines et de la nvelope and investment plan Conservation Foncière DJ-FDH-297938-GO-RFQ / L’ ACQUISITION DE MATÉRIELS I Support to the elaboration of Request for Quota Single Stage - One E Under Imple NFORMATIQUE - HARDWARE IDA / D7590 the ZSP strategic framework Post Limited 45,000.00 0.00 2022-06-28 2022-06-15 2022-09-08 2022-12-07 tions nvelope mentation POUR LA DIRECTION DES DO and investment plan MAINES ET DE LA CONSERVA TION FONCIÈRE DJ-FDH-298543-GO-RFQ / L’ ACQUISITION DE MATÉRIELS I Support to the elaboration of Request for Quota Single Stage - One E Under Imple NFORMATIQUE - SOFTWARE IDA / D7590 the ZSP strategic framework Post Limited 35,000.00 0.00 2022-06-28 2022-06-15 2022-08-30 2022-11-28 tions nvelope mentation POUR LA DIRECTION DES DO and investment plan MAINES ET DE LA CONSERVA TION FONCIÈRE DJ-FDH-301104-GO-RFQ / Ac Support to the elaboration of quisition de matériels géodés Open - Internationa Single Stage - One E Under Imple IDA / D7590 the ZSP strategic framework Post Request for Bids 240,000.00 0.00 2022-07-13 2022-07-12 2022-07-18 2022-08-17 2022-08-29 2022-09-07 2022-09-05 2022-09-14 2022-10-10 2023-01-08 iques pour la Direction des D l nvelope mentation and investment plan omaines et de la Conservatio n foncière DJ-FDH-364031-GO-RFQ / Ac Participatory upgrading inve Single Stage - One E Pending Impl IDA / D7590 Post Request for Bids Open - National 70,000.00 0.00 2023-06-06 2023-06-11 2023-07-11 2023-07-26 2023-08-30 2023-10-29 quisition d'un véhicule pour l stments in selected urban ar nvelope ementation a MASS eas NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-FDH-35172-NC-RFQ / Acti Request for Quota Single Stage - One E vités et supports divers de co IDA / V0980 Post Limited 45,000.00 0.00 Canceled 2017-12-23 2018-02-17 2018-04-18 tions nvelope mmunication CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-FDH-34629-CS-QCBS / Re crutement d'un consultant po Quality And Cost- IDA / V0980 Post Open - National 80,000.00 0.00 Canceled 2017-12-20 2018-01-10 2018-02-23 2018-03-23 2018-04-22 2018-05-27 2018-07-01 2018-11-28 ur l'étude sur la gestion du fo Based Selection ncier urbain au service de l'h abitat DJ-FDH-34632-CS-QBS / Recr utement d'un consultant pou Quality Based Sel Open - Internationa IDA / V0980 Post 150,000.00 0.00 Canceled 2017-12-11 2018-01-01 2018-02-14 2018-03-14 2018-04-13 2018-05-13 2018-06-17 2018-09-15 r le recensement des populat ection l ions des quartiers DJ-FDH-34618-CS-CQS / Recr Least Cost Selecti IDA / V0980 Post Open - National 30,000.00 0.00 Canceled 2017-12-04 2017-12-25 2018-02-07 2018-03-07 2018-04-06 2018-05-11 2018-06-15 2018-07-30 utement d'un cabinet d'audit on externe DJ-FDH-51535-CS-LCS / Recr Least Cost Selecti IDA / V0980 Prior Open - National 30,000.00 0.00 Canceled 2018-02-27 2018-04-04 2018-03-20 2018-04-19 2018-05-03 2018-06-11 2018-05-31 2018-07-18 2018-06-30 2018-09-03 2018-08-04 2018-09-08 2019-06-20 utement d'un cabinet d'audit on externe DJ-FDH-55870-CS-QCBS / Re crutement d'un consultant po Support to the elaboration of Quality And Cost- Open - Internationa ur les études urbaines et tec IDA / V0980 the ZSP strategic framework Post 200,000.00 192,922.37 Signed 2018-04-24 2018-04-19 2018-05-15 2018-05-10 2018-06-28 2018-07-17 2018-07-26 2018-09-05 2018-08-25 2018-09-26 2018-09-29 2018-11-14 2018-11-03 2019-01-27 2019-09-04 Based Selection l hniques de la zone de reloge and investment plan ment et de prévention à Balb ala Sud DJ-FDH-56020-CS-QCBS / Re Support to the elaboration of crutement d'un consultant po Quality And Cost- Open - Internationa IDA / V0980 the ZSP strategic framework Post 250,000.00 240,000.00 Completed 2018-04-24 2018-04-19 2018-05-15 2018-05-10 2018-06-28 2018-07-17 2018-07-26 2018-09-12 2018-08-25 2018-09-26 2018-09-29 2018-11-14 2018-11-03 2019-01-27 2019-05-02 2020-01-27 ur l'étude de restructuration Based Selection l and investment plan du quartier de Balbala Ancie n DJ-FDH-68702-CS-QCBS / Re Support to the elaboration of crutement d'un cabinet char Quality And Cost- Open - Internationa IDA / V0980 the ZSP strategic framework Post 80,000.00 106,948.00 Completed 2018-07-09 2018-07-30 2018-09-12 2018-09-02 2018-10-10 2018-10-03 2018-11-09 2018-10-31 2018-12-14 2018-11-14 2019-01-18 2019-01-27 2019-04-18 2020-11-15 gé de l'élaboration du cadre i Based Selection l and investment plan nstitutionnel et organisationn el de l'ARULoS Page 2 DJ-FDH-68705-CS-QCBS / Re crutement d'un consultant po Participatory upgrading inve Quality And Cost- Open - Internationa ur l'élaboration d'un plan de IDA / V0980 stments in selected urban ar Post 300,000.00 288,208.21 Completed 2018-08-06 2018-09-12 2018-08-27 2018-11-05 2018-10-10 2018-12-13 2018-11-07 2019-01-30 2018-12-07 2019-03-20 2019-01-11 2019-04-17 2019-02-15 2019-07-24 2019-08-14 2020-12-31 Based Selection l développement urbain et pro eas grammes d'investissement p our Balbala Nord DJ-FDH-68706-CS-QCBS / Re crutement d'un consultant po Participatory upgrading inve Quality And Cost- ur le suivi et contrôle des tra IDA / V0980 stments in selected urban ar Post Open - National 120,000.00 489,997.38 Completed 2018-07-16 2018-12-06 2018-08-06 2018-09-19 2019-02-12 2018-10-17 2019-03-13 2018-11-16 2019-04-30 2018-12-21 2019-05-16 2019-01-25 2019-08-08 2019-07-24 2021-01-07 Based Selection vaux de la voie de désenclav eas ement de Balbala ancien DJ-FDH-68736-CS-QCBS / Re Participatory upgrading inve crutement d'un consultant po Quality And Cost- Open - Internationa IDA / V0980 stments in selected urban ar Post 120,000.00 0.00 Canceled 2018-09-03 2018-09-24 2018-11-07 2018-12-05 2019-01-04 2019-02-08 2019-03-15 2024-03-13 ur des services d'ingénierie s Based Selection l eas ociale du projet à Balbala anc ien DJ-FDH-94102-CS-LCS / Recr Least Cost Selecti IDA / V0980 Project management Post Open - National 30,000.00 13,500.00 Completed 2019-01-08 2018-04-04 2019-01-29 2019-03-14 2018-06-11 2019-04-11 2018-07-18 2019-05-11 2018-08-08 2019-06-15 2018-08-29 2019-07-20 2019-03-31 2019-09-21 2019-06-13 utement d'un cabinet d'audit on externe DJ-FDH-125271-CS-QCBS / R Participatory upgrading inve ecrutement d'un consultant p Quality And Cost- IDA / 63380 stments in selected urban ar Post Open - National 200,000.00 223,400.00 Signed 2019-11-11 2021-06-22 2019-12-02 2020-01-15 2021-08-12 2020-02-12 2021-09-01 2020-02-26 2021-09-08 2020-04-01 2021-09-22 2020-05-06 2021-10-14 2020-11-02 our la supervision des travau Based Selection eas x de la zone de recasement DJ-FDH-127998-CS-LCS / Rec Least Cost Selecti rutement d'un cabinet pour l' IDA / 63380 Project management Post Open - National 50,000.00 14,655.00 Completed 2019-09-09 2019-11-26 2019-09-30 2019-11-13 2020-01-15 2019-12-11 2020-02-19 2020-01-10 2020-04-15 2020-02-14 2020-06-10 2020-03-20 2020-08-11 2020-09-16 2021-07-08 on audit des états financiers du projet DJ-FDH-126380-CS-QCBS / R Support to the elaboration of ecrutement d'un consultant p Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 250,000.00 303,290.00 Completed 2019-11-04 2019-12-25 2019-11-25 2020-01-07 2020-01-08 2020-04-16 2020-02-05 2020-06-10 2020-03-06 2020-08-12 2020-04-10 2020-08-26 2020-05-15 2021-01-06 2021-01-10 2021-09-01 our l'élaboration d'une étude Based Selection l and investment plan pour la restructuration des p etits quartiers DJ-FDH-154476-CS-QCBS / R Support to the elaboration of ecrutement d'un consultant p Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 150,000.00 161,750.00 Completed 2020-01-26 2020-01-22 2020-02-16 2020-03-31 2020-04-16 2020-04-28 2020-05-27 2020-05-28 2020-07-22 2020-07-02 2020-08-12 2020-08-06 2020-10-20 2020-08-27 2021-11-01 our l'étude de restructuration Based Selection l and investment plan et d'alignement du quartier T ora-Dora DJ-FDH-154517-CS-QCBS / R Support to the elaboration of ecrutement d'un consultant p Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 100,000.00 158,197.57 Completed 2020-01-22 2020-01-22 2020-02-12 2020-03-27 2020-04-16 2020-04-24 2020-05-27 2020-05-24 2020-07-22 2020-06-28 2020-08-12 2020-08-02 2020-10-20 2021-01-29 2021-10-01 our l'étude de faisabilité du q Based Selection l and investment plan uartier de bâche à eau DJ-FDH-155166-CS-QCBS / R Participatory upgrading inve ecrutement d'un consultant Quality And Cost- Open - Internationa IDA / 63380 stments in selected urban ar Post 100,000.00 76,704.77 Completed 2020-04-13 2020-10-01 2020-05-04 2020-10-05 2020-06-17 2020-11-15 2020-07-15 2020-12-23 2020-07-29 2021-03-09 2020-08-26 2021-04-01 2020-09-30 2021-05-29 2021-01-28 2022-07-03 pour l'élaboration d'un PAR Based Selection l eas pour l'ensemble du quartier de Balbala Ancien DJ-FDH-155172-CS-QCBS / R Participatory upgrading inve ecrutement d'un consultant p Quality And Cost- Open - Internationa IDA / 63380 stments in selected urban ar Post 100,000.00 76,150.00 Signed 2020-04-13 2021-01-26 2020-05-04 2021-02-07 2020-06-17 2021-04-27 2020-07-15 2021-06-02 2020-07-29 2021-06-23 2020-08-26 2021-07-14 2020-09-30 2021-09-27 2021-01-28 our l'élaboration d'un EIES po Based Selection l eas ur l'ensemble du quartier de Balbala Ancien DJ-FDH-125272-CS-QCBS / E Participatory upgrading inve tudes techniques et supervisi Quality And Cost- Open - Internationa IDA / 63380 stments in selected urban ar Post 150,000.00 285,750.00 Terminated 2020-08-16 2020-08-25 2020-09-06 2020-09-02 2020-10-20 2020-10-13 2020-11-17 2020-11-18 2020-12-01 2020-12-23 2021-01-05 2021-01-06 2021-02-09 2021-02-15 2021-06-09 on des travaux de la restruct Based Selection l eas uration de Balbala Ancien DJ-FDH-126404-CS-QCBS / R ecrutement d'un consultant p Participatory upgrading inve Quality And Cost- our le développement d'un m IDA / 63380 stments in selected urban ar Post Open - National 51,000.00 0.00 Canceled 2019-11-04 2019-11-25 2019-12-24 2020-01-21 2020-01-22 2020-02-26 2020-04-01 2020-06-30 Based Selection écanisme de gestion de plain eas tes pour l'Ingénierie Sociale DJ-FDH-216884-CS-QCBS / E Support to the elaboration of Quality And Cost- Open - Internationa tude de restructuration et d'a IDA / 63380 the ZSP strategic framework Post 150,000.00 213,967.70 Signed 2021-02-10 2021-02-03 2021-03-03 2021-02-12 2021-04-16 2021-04-27 2021-05-14 2021-06-02 2021-06-13 2021-06-23 2021-07-18 2021-07-14 2021-08-22 2021-10-01 2022-05-15 Based Selection l lignement du quartier Djebel and investment plan DJ-FDH-216885-CS-QCBS / E Support to the elaboration of tude de restructuration et d'a Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 150,000.00 259,167.60 Signed 2021-02-10 2021-02-03 2021-03-03 2021-02-12 2021-04-16 2021-04-27 2021-05-14 2021-06-02 2021-06-13 2021-06-23 2021-07-18 2021-07-14 2021-08-22 2021-09-02 2022-05-15 lignement de la zone de Djag Based Selection l and investment plan a-Bouldhouq(Quartier 7) DJ-FDH-216882-CS-QCBS / El Support to the elaboration of Quality And Cost- Open - Internationa aboration du plan de restruct IDA / 63380 the ZSP strategic framework Post 150,000.00 218,471.92 Signed 2021-02-10 2021-02-03 2021-03-03 2021-02-12 2021-04-16 2021-04-27 2021-05-14 2021-06-02 2021-06-13 2021-06-23 2021-07-18 2021-07-14 2021-08-22 2021-10-01 2022-06-18 Based Selection l uration du quartier d'Arhiba and investment plan DJ-FDH-216881-CS-QCBS / El Support to the elaboration of Quality And Cost- Open - Internationa aboration d'une étude de res IDA / 63380 the ZSP strategic framework Post 150,000.00 227,090.69 Signed 2021-02-10 2021-02-03 2021-03-03 2021-02-12 2021-04-16 2021-04-27 2021-05-14 2021-06-02 2021-06-13 2021-06-23 2021-07-18 2021-07-14 2021-08-22 2021-09-02 2022-07-18 Based Selection l tructuration de la zone de Vi and investment plan etnam DJ-FDH-216880-CS-QCBS / E Support to the elaboration of tude de marché du logement Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 200,000.00 188,615.45 Signed 2021-02-10 2021-02-03 2021-03-03 2021-02-07 2021-04-16 2021-04-27 2021-05-14 2021-06-02 2021-06-13 2021-06-23 2021-07-18 2021-07-14 2021-08-22 2021-10-01 2022-02-18 et la promotion d'un habitat Based Selection l and investment plan abordable à Djibouti DJ-FDH-239884-CS-LCS / Rec rutement d'un cabinet en vu Least Cost Selecti IDA / 63380 Project management Post Open - National 30,000.00 12,285.36 Signed 2021-07-15 2021-11-09 2021-08-05 2021-09-18 2022-01-20 2021-10-16 2022-02-23 2021-11-15 2022-03-09 2021-12-20 2022-03-23 2022-01-24 2022-05-06 2024-01-24 e de l’audit comptable et fina on ncier exercices 2021 et 2022 DJ-FDH-266463-CS-QCBS / R ecrutement d’un consultant Support to the elaboration of pour l’élaboration de l’étude Quality And Cost- Open - Internationa IDA / D7590 the ZSP strategic framework Post 150,000.00 175,793.78 Signed 2021-11-01 2021-11-08 2021-11-22 2022-01-06 2022-01-05 2022-02-07 2022-02-02 2022-03-09 2022-03-04 2022-03-23 2022-04-08 2022-04-06 2022-05-13 2022-05-13 2022-10-10 de diagnostic participatif et l Based Selection l and investment plan a rédaction de plan d’action sur la mise en œuvre de la lo i nationale sur les refugies DJ-FDH-266451-CS-QCBS / S ervices de consultation d’un Support to the elaboration of Quality And Cost- Open - Internationa bureau d’études pour l’élabo IDA / D7590 the ZSP strategic framework Post 150,000.00 249,680.00 Signed 2021-10-20 2021-10-21 2021-11-10 2021-12-24 2021-12-29 2022-01-21 2022-02-02 2022-02-20 2022-02-23 2022-03-27 2022-03-16 2022-05-01 2022-05-09 2023-02-25 Based Selection l ration des plans de restructu and investment plan ration des villages d’Ali Adde h et Holl-Holl DJ-FDH-267022-CS-QCBS / E tudes techniques et supervisi Participatory upgrading inve Quality And Cost- Open - Internationa on des travaux de constructi IDA / 63380 stments in selected urban ar Post 150,000.00 349,400.00 Signed 2021-12-29 2022-01-13 2022-01-19 2022-03-04 2022-03-01 2022-04-01 2022-04-06 2022-05-01 2022-04-13 2022-06-05 2022-04-27 2022-07-10 2022-05-20 2023-01-06 Based Selection l on des équipements du quart eas ier 9 « Balbala ancien » Page 3 DJ-FDH-269624-CS-QCBS / R ecrutement d'un consultant p Participatory upgrading inve our la mise en place d’un mé Consultant Qualifi Open - Internationa Under Implement IDA / 63380 stments in selected urban ar Post 150,000.00 0.00 2022-04-13 2022-05-09 2022-05-04 2022-07-27 2022-06-17 2022-09-05 2022-07-17 2022-08-21 2022-11-27 canisme de micro-crédit en cation Selection l ation eas matériaux et préparation d’u n manuel des procédures op érationnelles DJ-FDH-267549-CS-QCBS / S upervision des travaux de co Participatory upgrading inve Quality And Cost- Open - Internationa nstruction des voiries de Balb IDA / 63380 stments in selected urban ar Post 150,000.00 170,000.00 Signed 2021-12-29 2022-02-25 2022-01-19 2022-03-04 2022-04-25 2022-04-15 2022-05-25 2022-05-15 2022-06-01 2022-06-19 2022-06-15 2022-07-24 2022-08-19 2023-01-25 Based Selection l ala Nord et des infrastructure eas s (Voirie, AEP, et électricité) de Balbala Ancien DJ-FDH-291720-CS-QCBS / E tudes techniques APS-APD-EI Participatory upgrading inve ES et DAO des travaux des re Quality And Cost- Open - Internationa IDA / 63380 stments in selected urban ar Post 150,000.00 144,000.00 Signed 2022-01-15 2021-10-26 2022-02-05 2022-03-21 2022-03-01 2022-05-02 2022-04-06 2022-06-01 2022-04-20 2022-07-06 2022-05-04 2022-08-10 2022-06-03 2023-02-08 structuration et mise en plac Based Selection l eas e des équipements et infrastr uctures dans le quartier de T ora Dora DJ-FDH-291738-CS-QCBS / E tudes techniques APS-APD-EI ES et DAO des travaux des re Participatory upgrading inve Quality And Cost- Open - Internationa structuration et mise en plac IDA / 63380 stments in selected urban ar Post 150,000.00 159,425.00 Signed 2022-01-15 2021-10-26 2022-02-05 2022-03-21 2022-03-01 2022-05-02 2022-04-06 2022-06-01 2022-04-13 2022-07-06 2022-04-27 2022-08-10 2022-05-20 2023-02-08 Based Selection l e des équipements et infrastr eas uctures dans les quartiers de Balbala T9, Balbala Q11, Qua rawil / Pompage et Harirad). DJ-FDH-291737-CS-QCBS / L’ élaboration du cadre financie Support to the elaboration of r, institutionnel, organisation Quality And Cost- Open - Internationa Under Implement IDA / D7590 the ZSP strategic framework Post 100,000.00 0.00 2022-03-06 2022-03-06 2022-03-27 2022-05-10 2022-05-05 2022-06-21 2022-06-08 2022-07-21 2022-06-23 2022-08-25 2022-07-13 2022-09-29 2023-03-28 nel et humain de la Société I Based Selection l ation and investment plan mmobilière et d’Aménageme nt Foncier de Djibouti (SIAF) DJ-FDH-291736-CS-QCBS / L’ Participatory upgrading inve élaboration d’un plan d’actio Quality And Cost- Open - Internationa Under Implement IDA / 63380 stments in selected urban ar Post 100,000.00 0.00 2022-04-06 2022-04-06 2022-04-27 2022-06-10 2022-06-02 2022-07-22 2022-07-13 2022-08-21 2022-07-20 2022-09-25 2022-08-02 2022-10-30 2023-01-28 n de réinstallation – PAR pour Based Selection l ation eas les quartiers de Balbala nord DJ-FDH-291716-CS-QCBS / L’ Support to the elaboration of Quality And Cost- Open - Internationa Under Implement élaboration d’un plan de mis IDA / D7590 the ZSP strategic framework Post 250,000.00 0.00 2022-03-06 2022-01-18 2022-03-27 2022-05-10 2022-05-26 2022-06-21 2022-07-06 2022-07-21 2022-08-17 2022-08-25 2022-08-31 2022-09-29 2023-02-26 Based Selection l ation e à niveau des anciens quarti and investment plan ers de Djibouti DJ-FDH-291718-CS-QCBS / E tude d’impact environnemen Participatory upgrading inve Quality And Cost- Open - Internationa Under Implement tal et social de restructuratio IDA / 63380 stments in selected urban ar Post 100,000.00 0.00 2022-03-06 2021-11-26 2022-03-27 2022-05-10 2022-06-11 2022-06-21 2022-07-20 2022-07-21 2022-08-02 2022-08-25 2022-08-24 2022-09-29 2022-12-28 Based Selection l ation n et d’alignement (EIES) des eas 4 quartiers de balbala nord DJ-FDH-272107-CS-QCBS / E Support to the elaboration of tudes urbaines et techniques Quality And Cost- Open - Internationa IDA / 63380 the ZSP strategic framework Post 200,000.00 345,428.00 Signed 2021-09-01 2021-09-13 2021-09-22 2021-11-05 2021-12-07 2021-12-17 2022-01-05 2022-01-16 2022-01-19 2022-02-20 2022-02-02 2022-03-27 2022-05-09 2022-09-23 des quartiers de Layableh-Mo Based Selection l and investment plan ustiquaire et WARABLEH II DJ-FDH-269606-CS-QCBS / E tude technique des travaux d Participatory upgrading inve e construction des 2 voies de Quality And Cost- Open - Internationa Under Implement IDA / 63380 stments in selected urban ar Post 150,000.00 0.00 2021-12-19 2022-04-04 2022-01-09 2022-02-22 2022-05-23 2022-04-05 2022-07-06 2022-05-05 2022-07-20 2022-06-09 2022-08-02 2022-07-14 2023-01-10 désenclavement de Balbala Based Selection l ation eas Nord et des infrastructures ( Voirie, AEP, et électricité) de Balbala Ancien DJ-FDH-126441-CS-QCBS / R ecrutement d'un consultant p Support to the elaboration of Quality And Cost- Open - Internationa Under Implement our la mise en place d’une ba IDA / 63380 the ZSP strategic framework Post 250,000.00 0.00 2022-07-20 2022-07-20 2022-08-10 2022-08-21 2022-09-23 2022-09-26 2022-11-04 2022-10-27 2022-11-18 2022-11-09 2022-12-23 2022-12-14 2023-01-27 2023-10-24 Based Selection l ation se de données des ménages and investment plan de la zone de Balbala nord DJ-FDH-318103-CS-QCBS / R Support to the elaboration of ecrutement d'un bureau d’ét Quality And Cost- Open - Internationa Under Implement IDA / 63380 the ZSP strategic framework Post 150,000.00 0.00 2022-09-26 2022-09-28 2022-10-17 2022-10-20 2022-11-14 2022-11-15 2022-12-29 2022-12-14 2023-01-12 2023-01-11 2023-02-16 2023-03-23 2023-09-19 udes pour l’étude de restruct Based Selection l ation and investment plan uration et d’alignement du q uartier Bâche-à-eau DJ-FDH-341171-CS-QCBS / EI Participatory upgrading inve Quality And Cost- Open - Internationa Under Implement IDA / 63380 Post 100,000.00 0.00 2023-02-08 2023-02-01 2023-03-01 2023-04-14 2023-05-14 2023-05-28 2023-07-02 2023-08-06 2023-11-04 ES pour les 2 voies de Balbal stments in selected urban ar Based Selection l ation a Nord eas INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-FDH-34539-CS-INDV / Rec Support to the elaboration of Individual Consult Under Implement rutement d'un expert en app IDA / V0980 the ZSP strategic framework Prior Open 195,000.00 0.00 2017-10-29 2019-07-26 2017-12-17 2017-12-06 2018-01-07 2019-07-08 2018-02-11 2019-02-11 ant Selection ation ui à l'unité de gestion de l'av and investment plan ance DJ-FDH-34597-CS-CDS / Recr Support to the elaboration of utement d'un consultant pou IDA / V0980 the ZSP strategic framework Prior Direct Selection Direct 210,000.00 184,345.00 Completed 2017-10-30 2017-11-09 2017-10-29 2018-01-13 2018-01-29 2018-07-12 2018-09-30 r la stratégie de resorption d and investment plan es quartiers DJ-FDH-34616-CS-INDV / Rec Individual Consult rutement d'un consultant en IDA / V0980 Prior Open 30,000.00 0.00 Canceled 2017-11-12 2017-12-31 2018-01-21 2018-02-25 2019-02-25 ant Selection passation des marchés DJ-FDH-34623-CS-INDV / Rec Support to the elaboration of Individual Consult rutement d'un consultant po IDA / V0980 the ZSP strategic framework Post Open 5,000.00 9,200.00 Completed 2017-11-15 2017-11-20 2018-01-03 2017-12-26 2018-01-24 2018-01-09 2018-02-28 2018-01-15 2018-03-30 2018-02-23 ant Selection ur l'élaboration d'un plan de and investment plan communication DJ-FDH-40539-CS-CDS / Recr Participatory upgrading inve utement d'un consultant pou IDA / V0980 stments in selected urban ar Post Direct Selection Direct 40,000.00 28,100.00 Completed 2017-12-20 2017-12-30 2018-03-05 2018-02-07 2018-04-04 2018-03-20 r l'actualisations des études t eas echniques d'investissements prioritaires DJ-FDH-49621-CS-INDV / Rec rutement d'un expert dans le Support to the elaboration of cadre d'une étude d'évaluati Individual Consult IDA / V0980 the ZSP strategic framework Post Open 40,000.00 57,189.50 Completed 2017-12-04 2017-12-20 2018-01-22 2018-01-14 2018-02-12 2018-01-25 2018-03-19 2018-02-26 2018-06-17 2018-03-26 on des impacts environneme ant Selection and investment plan ntaux et sociaux (EIES) et de la gestion environnemental ( CGES) Page 4 DJ-FDH-51532-CS-INDV / Rec rutement d'un expert dans le Support to the elaboration of Individual Consult cadre de politique de réinstal IDA / V0980 the ZSP strategic framework Post Open 30,000.00 91,540.00 Completed 2017-12-04 2017-12-20 2018-01-22 2018-01-14 2018-02-12 2018-01-30 2018-03-19 2018-02-26 2018-04-23 2018-03-26 ant Selection lation des populations (CPR) and investment plan et dans le plan de réinstallati on des populations (PAR) DJ-FDH-59799-CS-INDV / Rec Individual Consult rutement d'un consultant cha IDA / V0980 Project management Post Open 45,000.00 31,740.00 Signed 2018-04-18 2018-04-18 2018-06-06 2018-06-07 2018-06-27 2018-06-12 2018-08-01 2018-07-01 2019-08-01 ant Selection rgé de la communication DJ-FDH-68703-CS-INDV / Rec rutement d'un consultant po Individual Consult ur la préparation du manuel IDA / V0980 Project management Post Open 30,000.00 28,750.00 Completed 2018-07-08 2018-08-26 2018-05-07 2018-09-16 2018-06-04 2018-10-21 2018-06-06 2018-11-15 2018-07-10 ant Selection de procédures du projet inté gré de résorption de bidonvill es DJ-FDH-68731-CS-INDV / Rec Individual Consult rutement d'un spécialiste en IDA / V0980 Project management Post Open 120,000.00 18,000.00 Completed 2018-07-31 2018-11-12 2018-09-18 2018-11-19 2018-10-09 2018-12-02 2018-11-13 2018-12-18 2019-11-13 2019-09-18 ant Selection sauvegarde DJ-FDH-127350-CS-INDV / Re Individual Consult crutement d'un assistant co IDA / 63380 Project management Post Open 20,000.00 53,486.88 Terminated 2019-08-18 2019-04-25 2019-09-13 2019-06-13 2019-09-27 2019-06-20 2019-11-01 2019-07-07 2020-10-31 ant Selection mptable pour appuyer le cha rgé fiduciaire DJ-FDH-126386-CS-CDS / Re Support to the elaboration of crutement d'un consultant po IDA / 63380 the ZSP strategic framework Post Direct Selection Direct 30,000.00 28,035.00 Signed 2019-08-18 2019-07-17 2019-08-28 2019-07-28 2019-10-17 2019-08-29 2019-12-16 ur une enquête socio-écono and investment plan mique de Balbala Ancien DJ-FDH-126407-CS-INDV / Re crutement d'un consultant po Participatory upgrading inve Individual Consult ur le recensement de structu IDA / 63380 stments in selected urban ar Post Open 40,000.00 19,910.00 Signed 2019-11-04 2021-02-23 2019-12-23 2021-04-15 2020-01-13 2021-04-15 2020-02-17 2021-04-16 2020-05-17 ant Selection res associatives et communa eas utaires existantes pour l'Ingé nierie Sociale DJ-FDH-127773-CS-INDV / Re Participatory upgrading inve crutement d'un animateur co Individual Consult IDA / 63380 stments in selected urban ar Post Direct 27,000.00 22,918.14 Signed 2019-11-04 2019-10-01 2019-11-14 2019-11-03 2019-11-21 2019-11-20 2019-12-26 2019-12-02 2020-06-23 mmunautaire pour la zone 4 ant Selection eas pour la durée du projet (Ingé nierie Sociale) DJ-FDH-127772-CS-INDV / Re Participatory upgrading inve crutement d'un animateur co Individual Consult IDA / 63380 stments in selected urban ar Post Direct 27,000.00 22,918.14 Signed 2019-11-04 2019-10-01 2019-11-14 2020-01-03 2019-11-21 2019-11-20 2019-12-26 2019-12-02 2020-12-25 mmunautaire pour la zone 3 ant Selection eas pour la durée du projet (Ingé nierie Sociale) DJ-FDH-127771-CS-INDV / Re Participatory upgrading inve crutement d'un animateur co Individual Consult IDA / 63380 stments in selected urban ar Post Direct 27,000.00 22,918.14 Signed 2019-11-04 2019-10-01 2019-11-14 2019-11-03 2019-11-21 2019-11-20 2019-12-26 2019-12-01 2020-12-25 mmunautaire pour la zone 2 ant Selection eas pour la durée du projet (Ingé nierie Sociale) DJ-FDH-127770-CS-INDV / Re Participatory upgrading inve crutement d'un animateur co Individual Consult IDA / 63380 stments in selected urban ar Post Direct 27,000.00 22,918.14 Signed 2019-11-04 2019-10-01 2019-11-14 2019-11-03 2019-11-21 2019-11-20 2019-12-26 2019-12-02 2020-12-25 mmunautaire pour la zone 1 ant Selection eas pour la durée du projet (Ingé nierie Sociale) DJ-FDH-127774-CS-INDV / Re Participatory upgrading inve crutement d'un animateur co Individual Consult IDA / 63380 stments in selected urban ar Post Direct 27,000.00 22,918.14 Signed 2019-11-04 2019-10-01 2019-11-14 2019-11-03 2019-11-21 2019-11-20 2019-12-26 2019-12-02 2020-06-23 mmunautaire pour la zone 5 ant Selection eas pour la durée du projet (Ingé nierie Sociale) DJ-FDH-148119-CS-INDV / Re Individual Consult crutement d'un expert en ap IDA / 63380 Project management Post Open 185,000.00 234,230.00 Completed 2019-12-02 2019-12-02 2020-01-20 2020-06-15 2020-02-10 2020-06-30 2020-03-16 2020-08-14 2021-03-16 2022-03-01 ant Selection pui de restructuration DJ-FDH-154472-CS-INDV / Re crutement d'un consultant po Individual Consult IDA / 63380 Project management Post Direct 5,000.00 3,229.88 Completed 2020-01-19 2019-12-17 2020-01-29 2019-12-29 2020-02-19 2019-12-29 2020-03-25 2019-12-31 2020-05-04 2020-02-11 ur la mise à jour des docume ant Selection nts de sauvegarde (CGES et CPR) DJ-FDH-155179-CS-INDV / Re Participatory upgrading inve crutement d'un consultant po Individual Consult IDA / 63380 stments in selected urban ar Post Open 50,000.00 36,225.00 Completed 2020-04-13 2020-02-11 2020-06-01 2020-06-11 2020-06-22 2020-06-25 2020-07-27 2020-07-15 2020-09-10 2020-10-15 ur l'élaboration d'un EIES pou ant Selection eas r le site d'accueil de 110 Ha DJ-FDH-154518-CS-CDS / Co Support to the elaboration of ntrat entre l'ARULoS et la RT IDA / 63380 the ZSP strategic framework Post Direct Selection Direct 30,000.00 25,501.90 Signed 2020-04-01 2020-05-11 2020-04-11 2020-05-17 2020-06-15 2020-06-02 2021-06-15 D pour la communication sur and investment plan le PIRB DJ-FDH-171635-CS-CDS / Re crutement d'un consultant po Support to the elaboration of ur les études techniques d'un IDA / 63380 the ZSP strategic framework Post Direct Selection Direct 260,000.00 305,275.74 Completed 2020-04-30 2020-05-03 2020-05-10 2020-05-27 2020-06-29 2020-08-11 2021-02-01 2021-08-11 site de 100 Ha dans la zone d and investment plan e prévention et de relogeme nt à Balbala Sud DJ-FDH-202546-CS-INDV / Re crutement d'un consultant po Individual Consult IDA / 63380 Project management Post Direct 25,000.00 22,960.73 Completed 2020-11-02 2020-10-14 2020-11-12 2020-10-20 2020-11-17 2020-10-21 2020-11-24 2020-10-26 2020-12-14 2020-11-12 ur la mise à jour des docume ant Selection nts de sauvegarde (CGES et CPR) DJ-FDH-209731-CS-INDV / Él aboration d'un PAR pour les Emergency response to COV Individual Consult IDA / 63380 Post Open 50,000.00 9,350.00 Signed 2021-01-03 2021-05-08 2021-02-21 2021-05-23 2021-03-14 2021-05-26 2021-04-18 2021-07-14 2021-06-17 ménages installés dans le lit ID-19 and to the floods ant Selection d'oued Langobaleyeh DJ-FDH-236686-CS-INDV / Re Individual Consult crutement d'un spécialiste e IDA / D7590 Project management Post Open 50,000.00 25,920.00 Signed 2021-06-15 2021-06-14 2021-08-03 2021-08-05 2021-08-24 2021-09-01 2021-09-28 2021-09-20 2022-09-28 ant Selection n sauvegarde environnement al DJ-FDH-127351-NC-RFQ / Act Support to the elaboration of ivités de communication pou IDA / 63380 the ZSP strategic framework Post Direct Selection Direct 20,000.00 0.00 Canceled 2019-11-03 2019-11-13 2020-01-17 2020-07-15 r préparer un reportage vidé and investment plan o sur le PZB DJ-FDH-239883-CS-INDV / Re Individual Consult IDA / 63380 Project management Post Limited 30,000.00 17,828.96 Signed 2021-06-01 2021-06-01 2021-06-06 2021-05-26 2021-06-27 2021-05-27 2021-08-01 2021-05-31 2022-08-01 crutement d'un assistant co ant Selection mptable DJ-FDH-236692-CS-INDV / Re Individual Consult crutement d'un spécialiste e IDA / D7590 Project management Post Open 50,000.00 33,366.11 Signed 2021-07-12 2021-06-14 2021-08-30 2021-08-05 2021-09-20 2021-09-13 2021-10-25 2021-10-01 2022-10-25 ant Selection n suivi-évaluation Page 5 DJ-FDH-266863-CS-CDS / Re crutement d'un consultant po IDA / D7590 Project management Post Direct Selection Direct 20,000.00 17,952.00 Signed 2021-07-01 2021-07-03 2021-07-11 2021-07-11 2021-08-29 2021-08-23 2021-11-27 ur la mise à jour du manuel d es procédures du PIRB DJ-FDH-265961-CS-INDV / Se rvices de consultation local p Participatory upgrading inve Individual Consult our l’élaboration d’une étude IDA / 63380 stments in selected urban ar Post Open 20,000.00 19,679.83 Signed 2021-10-15 2021-10-17 2021-12-03 2021-12-28 2021-12-24 2022-01-12 2022-01-28 2022-01-24 2022-04-28 ant Selection de profilage des jeunes du qu eas artier 9 « Balbala Ancien »-M ASS DJ-FDH-266453-CS-INDV / Re Participatory upgrading inve crutement d'un consultant po Individual Consult IDA / 63380 stments in selected urban ar Post Open 20,000.00 21,824.00 Signed 2021-08-01 2021-08-02 2021-08-26 2021-09-08 2021-08-31 2021-09-16 2021-10-05 2021-09-20 2022-02-02 ur la supervision des travaux ant Selection eas d'ouvrage hydraulique de Na ssib DJ-FDH-265965-CS-CDS / Etu des techniques APS-APD-EIES et DAO des travaux des restr Participatory upgrading inve ucturation et mise en place d IDA / 63380 stments in selected urban ar Post Direct Selection Direct 150,000.00 0.00 Canceled 2021-10-20 2021-10-30 2022-01-03 2022-07-02 es équipements et infrastruct eas ures dans les quartiers de Ba lbala T9, Balbala Q11, Quara wil / Pompage et Harirad). DJ-FDH-266452-CS-CDS / Etu des techniques APS-APD-EIES Participatory upgrading inve et DAO des travaux des restr IDA / 63380 stments in selected urban ar Post Direct Selection Direct 150,000.00 0.00 Canceled 2021-10-21 2021-10-31 2021-12-14 2022-06-12 ucturation et mise en place d eas es équipements et infrastruct ures dans le quartier de Tora Dora DJ-FDH-236676-CS-INDV / Re Individual Consult crutement d'un spécialiste e IDA / D7590 Project management Post Open 50,000.00 0.00 Canceled 2021-06-15 2021-06-14 2021-08-03 2021-08-24 2021-09-28 2022-09-28 ant Selection n passation de marché DJ-FDH-126351-CS-INDV / Re Support to the elaboration of crutement d'un consultant po Individual Consult IDA / 63380 the ZSP strategic framework Post Direct 30,000.00 0.00 Canceled 2020-02-02 2020-02-12 2020-03-04 2020-04-08 2020-05-23 ur appuyer le gouvernement ant Selection and investment plan à organiser la conférence des bailleurs DJ-FDH-297935-CS-INDV / EX Support to the elaboration of PERT D’APPUI A LA DIRECTIO Individual Consult Under Implement IDA / D7590 the ZSP strategic framework Post Open 150,000.00 0.00 2022-06-12 2022-05-29 2022-08-12 2022-10-31 2022-09-02 2023-01-18 2022-10-07 2023-10-07 N DES DOMAINES ET DE LA C ant Selection ation and investment plan ONSERVATION FONCIERE DJ-FDH-305006-CS-INDV / Re crutement d’un consultant n Support to the elaboration of ational pour la rédaction du Individual Consult Under Implement IDA / D7590 the ZSP strategic framework Post Open - National 20,000.00 0.00 2022-07-24 2022-07-25 2022-09-11 2022-10-06 2022-10-02 2022-12-15 2022-11-06 2023-03-06 manuel des procédures et de ant Selection ation and investment plan s opérations aux activités ex écutées par le MASS dans le cadre du PIRB DJ-FDH-305011-CS-INDV / Re crutement d’un consultant in Support to the elaboration of Individual Consult Open - Internationa Under Implement ternational du volet l’ingénie IDA / D7590 the ZSP strategic framework Post 60,000.00 0.00 2022-07-24 2022-07-25 2022-09-23 2022-10-14 2022-11-18 2023-05-17 ant Selection l ation rie sociale relative aux activit and investment plan és exécutées par le MASS da ns le cadre du PIRB DJ-FDH-345218-CS-CDS / Re crutement d'un spécialiste e IDA / D7590 Project management Post Direct Selection Direct - National 26,000.00 0.00 Canceled 2023-02-23 2023-03-05 2023-04-23 2024-04-22 n sauvegarde environnement al DJ-FDH-353343-CS-INDV / RE CRUTEMENT D’UN CONSULT Support to the elaboration of Individual Consult Open - Internationa Under Implement ANT D’APPUI AUPRES DE L’O IDA / D7590 the ZSP strategic framework Post 72,000.00 0.00 2023-03-28 2023-03-07 2023-05-16 2023-06-06 2023-07-11 2024-07-10 ant Selection l ation FFICE NATIONAL D’ASSISTAN and investment plan CE AUPRES DES REFUGIES ET SINISTRES DJ-FDH-358947-CS-INDV / Re Support to the elaboration of Individual Consult Under Implement crutement d'un animateur so IDA / D7590 the ZSP strategic framework Post Direct - National 22,250.00 0.00 2022-12-05 2022-12-05 2022-12-15 2023-01-05 2023-02-09 2023-08-08 ant Selection ation cial pour la MASS- Zone 1 and investment plan DJ-FDH-358958-CS-INDV / Re Support to the elaboration of Individual Consult Under Implement crutement d'un animateur so IDA / D7590 the ZSP strategic framework Post Direct - National 22,250.00 0.00 2022-12-05 2022-12-05 2022-12-15 2023-01-05 2023-02-09 2025-11-10 ant Selection ation cial pour la MASS- Zone 2 and investment plan DJ-FDH-358950-CS-INDV / Re Support to the elaboration of Individual Consult Under Implement crutement d'un animateur so IDA / D7590 the ZSP strategic framework Post Direct - National 22,250.00 0.00 2022-12-05 2022-12-05 2022-12-15 2023-01-05 2023-02-09 2025-11-10 ant Selection ation cial pour la MASS- Zone 3 and investment plan DJ-FDH-358953-CS-INDV / Re Support to the elaboration of Individual Consult Under Implement crutement d'un animateur so IDA / D7590 the ZSP strategic framework Post Direct - National 22,250.00 0.00 2022-12-05 2022-12-05 2022-12-15 2023-01-05 2023-02-09 2025-11-10 ant Selection ation cial pour la MASS- Zone 4 and investment plan DJ-FDH-358940-CS-INDV / Re Support to the elaboration of Individual Consult Under Implement crutement d'un animateur so IDA / D7590 the ZSP strategic framework Post Direct - National 22,250.00 0.00 2022-12-05 2022-12-05 2022-12-15 2023-01-05 2023-02-09 2025-11-10 ant Selection ation cial pour la MASS- Zone 5 and investment plan DJ-FDH-353478-CS-INDV / Re Individual Consult IDA / 63380 Project management Post Open - National 50,000.00 0.00 Under Review 2021-12-05 2021-12-07 2022-01-23 2022-02-13 2022-03-20 2023-03-20 crutement d'un auditeur inte ant Selection rne Page 6 PROCUREMENT Uganda : Irrigation for Climate Resilience Project (ICRP) PLAN General Information Country: Uganda 2019-01-08 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163836 GPN Date: 2022-06-03 Project Name: Irrigation for Climate Resilience Project (ICRP) Loan / Credit No: / , TF / A9023, IDA / 65650 Ministry of Water and Environment Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - UG-MWE-230714-CW-RFB / Open - Internationa Single Stage - Two E Works (without pr 20,220,000.0 Under Imple 2024-08-1 Works for Construction of Ka IDA / 65650 Comp. 1 - Irrigation Services Prior Request for Bids 0.00 2020-12-23 2021-04-21 2020-12-29 2021-04-21 2021-04-20 2021-04-20 2021-07-14 2022-07-13 2021-08-18 l nvelope equalification) SP 0 mentation 7 buyanda Dam in Isingiro Dist D rict UG-MWE-165320-CW-RFB / Open - Internationa Single Stage - One E 20,220,000.0 2024-02-0 Works for Construction of Ka IDA / 65650 Comp. 1 - Irrigation Services Prior Request for Bids 0.00 Canceled 2020-07-17 2020-12-23 2020-08-16 2020-12-24 2020-09-30 2020-12-04 2021-02-08 l nvelope 0 8 buyanda Dam in Isingiro Dist rict UG-MWE-219013-CW-RFB / Construction works for Kabuy Open - Internationa Single Stage - Two E 19,080,000.0 2023-09-2 IDA / 65650 Comp. 1 - Irrigation Services Prior Request for Bids 0.00 Canceled 2021-02-19 2021-04-09 2021-06-04 2021-08-17 2021-09-21 anda Off-Farm Network up to l nvelope 0 1 the block in Isingiro District Request for Bids - UG-MWE-258580-CW-RFB / Open - Internationa Single Stage - Two E Works (without pr 17,880,000.0 2025-04-2 Construction of Kabuyanda O IDA / 65650 Comp. 1 - Irrigation Services Prior Request for Bids 0.00 Canceled 2021-11-01 2021-11-22 2022-01-03 2022-03-18 2022-04-22 l nvelope equalification) SP 0 1 ff-farm Network up to the blo D ck Request for Bids - UG-MWE-258584-CW-RFB / Single Stage - One E Small Works SPD Pending Imp 2024-03-0 Construction of Scheme facili IDA / 65650 Comp. 1 - Irrigation Services Post Request for Bids Open - National 1,200,000.00 0.00 2021-11-01 2021-11-15 2021-12-27 2022-01-26 2022-03-02 nvelope (1 envelope proce lementation 1 ties for Kabuyanda Irrigation ss) Scheme UG-MWE-301171-CW-RFB / Request for Bids - Construction works for Kabuy Open - Internationa Single Stage - One E Works (without pr 17,880,000.0 Under Imple 2024-11-1 IDA / 65650 Comp. 1 - Irrigation Services Prior Request for Bids 0.00 2022-07-15 2022-08-25 2022-07-29 2022-08-29 2022-09-09 2022-11-17 2022-10-19 2023-03-31 2022-11-23 anda Irrigation Scheme off-fa l nvelope equalification) SP 0 mentation 2 rm Network pipe network in I D singiro district GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MWE-204550-GO-RFQ / P rocurement of assorted indig enous seedlings for restorati on planting and maintenance Single Stage - One E IDA / 65650 Comp. 1 - Irrigation Services Post Request for Bids Limited 300,000.00 272,798.43 Signed 2020-12-11 2021-05-03 2020-12-16 2021-05-03 2021-01-27 2021-05-18 2021-02-26 2021-05-26 2021-04-02 2021-10-23 2021-09-29 of: nvelope Lot 1- 250,000 seedlings for Rwoho 1 Lot 2- 250,000 seedlings for Rwoho 2 UG-MWE-253400-GO-RFB / S upply of 7No. Station Wagon Comp. 3 - Institutional Stren Single Stage - One E and 18No. Double Cabin Pick IDA / 65650 gthening and Implementatio Prior Request for Bids Open - National 1,980,000.00 0.00 Signed 2021-09-24 2022-05-24 2021-09-29 2022-05-25 2021-10-27 2022-07-11 2021-11-19 2022-08-30 2021-12-24 2023-04-02 2022-12-24 nvelope up Vehicles for Irrigation for n Support Climate Resilience Project (IC RP). UG-MWE-253505-GO-RFQ / S Comp. 3 - Institutional Stren upply of 4No. paper shredder Request for Quota Single Stage - One E Pending Impl IDA / 65650 gthening and Implementatio Post Limited 3,000.00 0.00 2021-09-29 2021-11-24 2022-02-22 and 3No. Spiral binding mach tions nvelope ementation n Support ine & accessories. UG-MWE-261019-GO-RFB / S upply of IT equipment for ICR P: LOT 1: Laptops LOT 2: Des Comp. 3 - Institutional Stren ktop Computers, UPS, Tablet Single Stage - One E Under Imple IDA / 65650 gthening and Implementatio Post Request for Bids Open - National 524,670.00 0.00 2021-11-12 2022-03-15 2021-11-17 2022-03-29 2021-12-29 2022-04-14 2022-01-28 2022-05-24 2022-03-04 2022-08-31 s, External HDD, GPS, Digital nvelope mentation n Support Cameras and Drones LOT 3: Heavy Duty Photocopier, Mul tifunctional Printers, Printers, Scanners and Projectors UG-MWE-276558-GO-RFQ / S Comp. 3 - Institutional Stren upply and Installation of Vide IDA / 65650 gthening and Implementatio Post Direct Selection Direct 75,000.00 76,064.56 Signed 2022-02-21 2022-04-01 2022-02-26 2022-04-11 2022-04-02 2022-06-28 2022-09-29 o conferencing facilities at th n Support e MWE Premises (DWD Board room) UG-MWE-313236-GO-RFQ / P rocurement of Furniture (One 30-seater Conference table, Comp. 3 - Institutional Stren Request for Quota Single Stage - One E Under Imple 24 chairs, 6 executive boardr IDA / 65650 gthening and Implementatio Post Limited 42,000.00 0.00 2022-09-21 2022-09-28 2022-11-16 2023-03-16 tions nvelope mentation oom table chairs, 15 cool me n Support sh extra chairs without wheel s, 1 coffee table and 1 Office blinds for DWD Boardroom UG-MWE-341983-GO-RFB / S Comp. 3 - Institutional Stren Single Stage - One E Pending Impl IDA / 65650 Post Request for Bids Open - National 125,000.00 0.00 2023-02-26 2023-03-05 2023-04-16 2023-05-16 2023-06-20 2023-10-18 upply of 25 No. Motorcycles gthening and Implementatio nvelope ementation n Support UG-MWE-349700-GO-RFQ / P Comp. 3 - Institutional Stren Request for Quota Single Stage - One E Pending Impl rocurement of IEC Materials f IDA / 65650 gthening and Implementatio Post Limited 13,500.00 0.00 2023-03-22 2023-05-17 2023-05-24 tions nvelope ementation or the launch of ICRP Project n Support UG-MWE-360810-GO-DIR / P Comp. 2 - Support Services f Pending Impl rocurement of eVoucher Man IDA / 65650 or Agricultural Production an Post Direct Selection Direct - National 1,237,000.00 0.00 2023-05-18 2023-05-28 2023-06-17 2025-06-06 ementation agement System d Value Chain Development NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 UG-MWE-165038-NC-RFQ / P rovision of hotel services(acc Comp. 3 - Institutional Stren Request for Quota Single Stage - One E Pending Impl ommodation and meals) and TF / A9023 gthening and Implementatio Post Limited 28,800.00 0.00 2020-07-23 2020-09-04 2020-09-18 tions nvelope ementation conferencing facilities for Sta n Support ff Training on capacity buildi ng on engineering software UG-MWE-183725-NC-RFB / P rocurement of Non-Consultan Single Stage - One E IDA / 65650 Comp. 1 - Irrigation Services Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2020-07-17 2020-07-30 2020-08-24 2020-09-23 2020-10-28 2021-10-28 cy Services to undertake Rw nvelope oho Reafforestation UG-MWE-204547-NC-RFQ / N on Consulting services for Re Single Stage - One E storation planting and maint IDA / 65650 Comp. 1 - Irrigation Services Post Request for Bids Limited 700,000.00 599,099.16 Signed 2020-12-04 2021-04-07 2020-12-09 2021-04-07 2021-01-20 2021-04-22 2021-02-19 2021-05-19 2021-03-26 2021-09-23 2024-03-25 nvelope enance of : Lot 1: 500HA -Rwoho 1 Lot 2: 500HA -Rwoho 2 UG-MWE-232817-NC-DIR / Pr Pending Impl ocurement of catering servic IDA / 65650 Comp. 1 - Irrigation Services Post Direct Selection Direct 4,400.00 0.00 2021-05-06 2021-05-11 2021-06-15 2021-07-15 ementation es for the ICRP Project Launc h UG-MWE-232833-NC-DIR / Pr ocurement of mobile Public A Request for Quota Single Stage - One E Pending Impl IDA / 65650 Comp. 1 - Irrigation Services Post Limited 7,000.00 0.00 2021-05-22 2021-07-17 2022-01-13 ddress systems and including tions nvelope ementation multi screen video Conferenc e facilities. UG-MWE-232825-NC-DIR / Pr ocurement of printing service Request for Quota Single Stage - One E Pending Impl IDA / 65650 Comp. 1 - Irrigation Services Post Limited 44,000.00 0.00 2021-06-05 2021-07-31 2022-01-27 s for IEC materials for project tions nvelope ementation launch and GRC training. UG-MWE-320322-NC-RFQ / P rocurement of Hotel services Comp. 3 - Institutional Stren Request for Quota Single Stage - One E Pending Impl for training of staff for trainin IDA / 65650 gthening and Implementatio Post Limited 43,030.00 0.00 2022-10-26 2022-12-21 2022-12-26 tions nvelope ementation g in web-based M& E System n Support - Geo enabling Monitoring sy stem UG-MWE-341990-NC-RFQ / P Comp. 3 - Institutional Stren Request for Quota Single Stage - One E Pending Impl rocurement of catering servic IDA / 65650 gthening and Implementatio Post Limited 18,700.00 0.00 2023-03-24 2023-05-19 2023-05-26 tions nvelope ementation es for launch of ICRP Project n Support UG-MWE-342971-NC-RFQ / P Comp. 3 - Institutional Stren rocurement of Events Manag Request for Quota Single Stage - One E Pending Impl IDA / 65650 gthening and Implementatio Post Limited 18,300.00 0.00 2023-03-25 2023-05-20 2023-05-27 ement Services for the launc tions nvelope ementation n Support h and groundbreaking of ICR P Project in Kabuyanda UG-MWE-358080-NC-RFB / N on-Consultancy Services for Supporting Communities to I Single Stage - One E Under Revie mplement Priority catchment IDA / 65650 Comp. 1 - Irrigation Services Prior Request for Bids Open - National 2,096,478.00 0.00 2023-05-01 2023-05-06 2023-06-17 2023-07-17 2023-08-21 2025-08-10 nvelope w Management Measures arou nd Lot 1: Kabuyanda Irrigatio n Scheme and Lot 2: Matand a Irrigation Scheme CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MWE-89181-CS-QCBS / C onsultancy services to carry Quality And Cost- Open - Internationa Under Implement / Comp. 1 - Irrigation Services Prior 500,000.00 0.00 2018-12-27 2019-01-11 2019-01-10 2019-06-27 2019-02-23 2020-12-06 2019-03-13 2021-01-29 2019-04-12 2021-09-13 2019-05-17 2022-03-09 2019-06-21 2020-06-20 out Feasibility Studies for Am Based Selection l ation agoro Irrigation Scheme in To roro District UG-MWE-89184-CS-QCBS / C onsultancy services to carry Quality And Cost- Open - Internationa / Comp. 1 - Irrigation Services Prior 500,000.00 0.00 Canceled 2018-12-27 2019-01-10 2019-02-21 2019-03-14 2019-04-13 2019-05-18 2019-06-22 2020-06-21 out Design for Amagoro Irrig Based Selection l ation Scheme in Tororo Distri ct UG-MWE-165064-CS-QCBS / Supervision of Construction Quality And Cost- Open - Internationa IDA / 65650 Comp. 1 - Irrigation Services Prior 3,572,000.00 0.00 Signed 2020-07-17 2020-08-04 2020-08-07 2020-09-09 2020-09-20 2021-06-21 2020-10-18 2021-08-03 2020-11-17 2022-01-27 2020-12-22 2022-08-22 2021-01-26 2023-04-02 2024-04-25 works for Kabuyanda Dam & Based Selection l Irrigation Scheme Network in Isingiro District UG-MWE-165070-CS-QCBS / Consultancy Services to unde rtake Supervision of Environ Quality And Cost- mental and Social Safe guard IDA / 65650 Comp. 1 - Irrigation Services Prior Open - National 1,314,500.00 0.00 Signed 2020-07-16 2020-11-01 2020-08-06 2021-01-25 2020-09-19 2022-01-31 2020-10-17 2022-03-23 2020-11-16 2022-10-18 2020-12-21 2023-01-09 2021-01-25 2023-04-05 2023-07-26 Based Selection s Implementation in the cons truction of Kabuyanda dam a nd irrigation scheme in Isingi ro District UG-MWE-165199-CS-QCBS / Consultancy Services to prep Consultant Qualifi Under Implement are a micro catchment mana IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 300,000.00 0.00 2020-07-17 2020-07-16 2020-08-07 2020-09-20 2020-10-20 2020-11-24 2021-05-23 cation Selection ation gement plan for the micro-ca tchment around Kabuyanda i rrigation scheme UG-MWE-165319-CS-QCBS / Consultancy Services to prep Consultant Qualifi Under Implement are a micro catchment mana IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 300,000.00 0.00 2020-07-17 2020-07-16 2020-08-07 2020-09-20 2020-10-20 2020-11-24 2021-05-23 cation Selection ation gement plan for the micro-ca tchment around Matanda irri gation scheme UG-MWE-165067-CS-QCBS / Consultancy Services for Imp lementation Support for Sust Quality And Cost- Open - Internationa IDA / 65650 Comp. 1 - Irrigation Services Prior 1,700,000.00 0.00 Canceled 2020-07-16 2020-08-06 2020-09-19 2020-10-17 2020-11-16 2020-12-21 2021-01-25 2025-01-24 ainable Management of Kabu Based Selection l yanda Irrigation Scheme Infr astructure in Isingiro District UG-MWE-189803-CS-CQS / C Comp. 3 - Institutional Stren onsultancy Services to under Consultant Qualifi Under Implement IDA / 65650 gthening and Implementatio Post Open - National 133,333.00 0.00 2020-08-31 2021-10-15 2020-09-21 2020-11-04 2020-12-04 2021-01-08 2021-07-07 take a project baseline study cation Selection ation n Support (gender sensitive) for the ICR P. UG-MWE-188203-CS-QCBS / Consultancy Services for pro Comp. 2 - Support Services f Quality And Cost- Under Implement vision of agricultural extensio IDA / 65650 or Agricultural Production an Prior Open - National 1,550,300.00 0.00 2020-10-23 2021-07-14 2020-11-13 2022-01-28 2020-12-27 2022-06-23 2021-01-24 2022-09-01 2021-02-23 2023-01-04 2021-03-30 2023-05-19 2021-05-04 2023-05-04 Based Selection ation n services to improve produc d Value Chain Development tion and productivity in Kabu yanda irrigation scheme Page 2 UG-MWE-186214-CS-QCBS / Lot 2: Consultancy Services f Comp. 2 - Support Services f Quality And Cost- Open - Internationa Under Implement or provision of agricultural ex IDA / 65650 or Agricultural Production an Prior 547,024.00 0.00 2020-10-23 2021-09-13 2020-11-13 2022-02-14 2020-12-27 2022-09-05 2021-01-24 2021-02-23 2021-03-30 2021-05-04 2023-05-04 Based Selection l ation tension services to improve p d Value Chain Development roduction and productivity in Agoro irrigation scheme. UG-MWE-186210-CS-QCBS / Lot 1: Consultancy Services f Comp. 2 - Support Services f or provision of agricultural ex Quality And Cost- Open - Internationa Under Implement IDA / 65650 or Agricultural Production an Prior 360,600.00 0.00 2020-10-23 2021-07-13 2020-11-13 2022-02-14 2020-12-27 2022-09-05 2021-01-24 2021-02-23 2021-03-30 2021-05-04 2023-05-04 tension services to improve p Based Selection l ation d Value Chain Development roduction and productivity in Olweny irrigation scheme. UG-MWE-186647-CS-QCBS / LOT 1: Consultancy services f Comp. 2 - Support Services f Quality And Cost- Open - Internationa Under Implement or value chain development ( IDA / 65650 or Agricultural Production an Prior 900,595.00 0.00 2020-12-04 2021-11-11 2020-12-25 2022-01-17 2021-02-07 2022-06-23 2021-03-07 2022-08-19 2021-04-06 2022-11-25 2021-05-11 2023-04-27 2021-06-15 2025-06-14 Based Selection l ation studies, platforms and linkag d Value Chain Development es) in Kabuyanda & Matanda UG-MWE-186650-CS-QCBS / LOT 2: Consultancy services f Comp. 2 - Support Services f Quality And Cost- Open - Internationa Under Implement or value chain development ( IDA / 65650 or Agricultural Production an Prior 878,120.00 0.00 2020-12-04 2022-01-24 2020-12-25 2022-05-03 2021-02-07 2022-09-06 2021-03-07 2022-10-18 2021-04-06 2023-05-21 2021-05-11 2021-06-15 2025-06-14 Based Selection l ation studies, platforms and linkag d Value Chain Development es) in Olweny and Agoro UG-MWE-204499-CS-CQS / C Consultant Qualifi onsultancy Services for ESIA IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 400,000.00 0.00 Canceled 2020-12-04 2021-02-23 2020-12-25 2021-02-07 2021-03-09 2021-04-13 2023-04-13 cation Selection studies for Amagoro UG-MWE-204537-CS-QCBS / Consultancy Services for the development of Off-Farm Infr Quality And Cost- IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 500,000.00 0.00 Canceled 2020-12-04 2021-06-15 2020-12-25 2021-02-07 2021-03-07 2021-04-06 2021-05-11 2021-06-15 2022-12-15 astructure management mod Based Selection el and its establishment for t he Kabuyanda irrigation sche me in Isingiro District. UG-MWE-204541-CS-CQS / C onsultancy services to imple Consultant Qualifi ment and support GBV/VAC a IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 250,000.00 0.00 Canceled 2020-12-04 2021-02-23 2020-12-25 2021-06-01 2021-02-07 2021-03-09 2021-04-13 2022-04-13 cation Selection ctivities by NGO in Kabuyand a irrigation scheme in Isingir o district. UG-MWE-204546-CS-CQS / C onsultancy services for under Consultant Qualifi Under Implement taking HIV/AIDS/COVID 19 m IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 150,000.00 0.00 2020-12-04 2021-04-06 2020-12-25 2021-11-15 2021-02-07 2021-03-09 2021-04-13 2021-10-10 cation Selection ation ainstreaming for the Kabuyn da irrigation scheme in Isingi ro District UG-MWE-253412-CS-CQS / C onsultancy Services to imple Consultant Qualifi Under Implement ment and support GBV/VAC a IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 250,000.00 0.00 2021-10-04 2022-04-01 2021-11-01 2021-12-15 2022-01-14 2022-02-18 2022-08-17 cation Selection ation ctivities by NGO in Matanda i rrigation scheme in Kanungu district. UG-MWE-253413-CS-CQS / C onsultancy services for under Consultant Qualifi Under Implement taking HIV/AIDS/COVID 19 m IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 150,000.00 0.00 2021-10-04 2022-01-13 2021-11-01 2021-12-15 2022-01-14 2022-02-18 2023-02-18 cation Selection ation ainstreaming for the Matand a irrigation scheme in Kanun gu district. UG-MWE-255147-CS-CQS / C onsultancy services for provi sion of extension services an Comp. 2 - Support Services f Consultant Qualifi Pending Impleme d improving access to quality IDA / 65650 or Agricultural Production an Post Limited 166,184.00 0.00 2021-10-04 2021-10-25 2021-11-24 2021-12-29 2023-12-29 cation Selection ntation agricultural inputs, post-harv d Value Chain Development est handling and market link ages in the proposed Nyimur irrigation scheme, Lamwo dis trict UG-MWE-253410-CS-QCBS / Consultancy Services for Sta Quality And Cost- Under Implement IDA / 65650 Comp. 1 - Irrigation Services Prior Open - National 1,100,000.00 0.00 2022-02-18 2022-06-17 2022-03-18 2022-07-13 2022-05-01 2022-11-14 2022-05-29 2022-12-28 2022-06-28 2022-08-02 2022-09-06 2023-09-06 keholder engagement in Mat Based Selection ation anda irrigation scheme in Ka nungu district. UG-MWE-189779-CS-QCBS / Consultancy Services for Imp Quality And Cost- lementation Support for Off-F IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 1,100,000.00 0.00 Canceled 2020-12-04 2020-12-25 2021-02-07 2021-03-07 2021-04-06 2021-05-11 2021-06-15 2024-06-14 Based Selection arm infrastructure developm ent of Kabuyanda Irrigation s cheme in Isingiro District UG-MWE-276555-CS-QCBS / Consultancy services for Stak Quality And Cost- Under Implement IDA / 65650 Comp. 1 - Irrigation Services Prior Open - National 1,100,000.00 0.00 2022-02-14 2022-03-17 2022-03-07 2022-06-09 2022-04-20 2022-09-14 2022-05-18 2022-10-24 2022-06-17 2023-05-02 2022-07-22 2022-08-26 2023-08-26 eholders Engagement in Kab Based Selection ation uyanda Irrigation Scheme (Isi ngiro District) UG-MWE-304502-CS-CQS / C Consultant Qualifi Under Implement onsultancy services for ESIA f IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 400,000.00 0.00 2022-07-29 2022-07-19 2022-08-12 2022-09-25 2022-10-25 2022-11-29 2024-11-18 cation Selection ation or Amagoro UG-MWE-304501-CS-CQS / C onsultancy services to imple Consultant Qualifi Under Implement ment and support GBV/VAC a IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 250,000.00 0.00 2022-07-29 2022-07-25 2022-08-12 2022-09-25 2022-10-25 2022-11-29 2025-05-17 cation Selection ation ctivities in Kabuyanda Irriga tion Scheme in Isingiro distric t UG-MWE-354662-CS-QBS / C onsultancy Services for Const Quality And Cost- Open - Internationa Under Implement IDA / 65650 Comp. 1 - Irrigation Services Prior 2,800,000.00 0.00 2023-04-21 2023-05-29 2023-05-05 2023-06-20 2023-06-30 2023-08-04 2026-01-20 ruction Supervision of Matan Based Selection l ation da Irrigation scheme Infrastr ucture and facilities UG-MWE-354710-CS-QCBS / Consultancy services for sup Quality And Cost- Under Implement ervision of Environmental an IDA / 65650 Comp. 1 - Irrigation Services Prior Open - National 800,000.00 0.00 2023-04-20 2023-05-29 2023-05-11 2023-06-24 2023-07-22 2023-08-21 2023-09-25 2023-10-30 2026-04-17 Based Selection ation d Social safeguards Impleme ntation in the Construction of Matanda Irrigation scheme UG-MWE-307942-CS-QCBS / Consultancy services for Dev elopment of off-farm Infrastr Quality And Cost- IDA / 65650 Comp. 1 - Irrigation Services Prior Open - National 500,000.00 0.00 Canceled 2022-08-18 2022-08-05 2022-09-08 2022-08-05 2022-10-22 2022-11-19 2022-12-19 2023-01-23 2023-02-27 2025-02-26 ucture Management Model a Based Selection nd its establishment for Kabu yanda Irrigation scheme in Isi ngiro District Page 3 UG-MWE-253411-CS-QCBS / Consultancy Services for the development of Off-Farm Infr Quality And Cost- IDA / 65650 Comp. 1 - Irrigation Services Prior Open - National 500,000.00 0.00 Canceled 2021-10-04 2022-07-26 2021-11-01 2022-08-23 2021-12-15 2022-01-12 2022-02-11 2022-03-18 2022-04-22 2023-04-22 astructure management mod Based Selection el and its establishment for t he Matanda irrigation schem e in Kanungu district. UG-MWE-354715-CS-QCBS / Consultancy Services for the development of Off-Farm Infr Quality And Cost- Open - Internationa IDA / 65650 Comp. 1 - Irrigation Services Prior 870,190.00 0.00 Under Review 2023-04-20 2023-05-11 2023-06-24 2023-07-22 2023-08-21 2023-09-25 2023-10-30 2025-10-19 astructure management mod Based Selection l el and its establishment for K abuyanda irrigation scheme UG-MWE-354719-CS-QCBS / Consultancy Services for the development of Off-Farm Infr Quality And Cost- Open - Internationa Pending Impleme IDA / 65650 Comp. 1 - Irrigation Services Prior 870,190.00 0.00 2023-04-20 2023-05-11 2023-06-24 2023-07-22 2023-08-21 2023-09-25 2023-10-30 2025-10-19 astructure management mod Based Selection l ntation el and its establishment for t he Matanda irrigation schem e in Kanungu district. UG-MWE-354784-CS-QCBS / Consultancy services for con ducting Environmental and S Quality And Cost- Pending Impleme ocial Impact Assessment (ESI IDA / 65650 Comp. 1 - Irrigation Services Prior Open - National 800,000.00 0.00 2023-04-27 2023-05-18 2023-07-01 2023-07-29 2023-08-28 2023-10-02 2023-11-06 2024-11-05 Based Selection ntation A) and Resettlement Action P lan (RAP) studies for Enengo Irrigation scheme in Rukungir i and Kanungu district UG-MWE-354771-CS-QCBS / Consultancy services for deta Quality And Cost- Pending Impleme IDA / 65650 Comp. 1 - Irrigation Services Prior Open - National 1,000,000.00 0.00 2023-04-20 2023-05-11 2023-06-24 2023-07-22 2023-08-21 2023-09-25 2023-10-30 2024-10-29 iled design of Amagoro Irriga Based Selection ntation tion scheme in Tororo District UG-MWE-354777-CS-QCBS / Consultancy services for feas Quality And Cost- Open - Internationa Pending Impleme IDA / 65650 Comp. 1 - Irrigation Services Prior 800,000.00 0.00 2023-04-20 2023-05-11 2023-06-24 2023-07-22 2023-08-21 2023-09-25 2023-10-30 2024-04-27 ibility study for Enengo Irriga Based Selection l ntation tion scheme in Rukungiri and Kanungu districts UG-MWE-354780-CS-QCBS / Consultancy services for deta Quality And Cost- Pending Impleme IDA / 65650 Comp. 1 - Irrigation Services Prior Open - National 800,000.00 0.00 2023-04-20 2023-05-11 2023-06-24 2023-07-22 2023-08-21 2023-09-25 2023-10-30 2024-10-29 iled design of Enengo Irrigati Based Selection ntation on scheme in Rukungiri and Kanungu districts UG-MWE-355662-CS-QCBS / Consultancy services for Res Quality And Cost- Pending Impleme ettlement Action Plan (RAP) s IDA / 65650 Comp. 1 - Irrigation Services Post Open - National 400,000.00 0.00 2023-04-20 2023-05-11 2023-06-24 2023-07-22 2023-08-21 2023-09-25 2023-10-30 2024-05-02 Based Selection ntation tudies for Amagoro Irrigation scheme in Tororo District UG-MWE-358894-CS-QCBS / Consultancy services for Desi Quality And Cost- Open - Internationa IDA / 65650 Comp. 1 - Irrigation Services Prior 795,578.00 0.00 Canceled 2023-05-05 2023-05-26 2023-07-09 2023-08-06 2023-09-05 2023-10-10 2023-11-14 2024-05-12 gn of Kabuyanda off-farm Ne Based Selection l twork within the block UG-MWE-369462-CS-CQS / C onsultancy services for Desig Consultant Qualifi IDA / 65650 Comp. 1 - Irrigation Services Post Limited 300,000.00 0.00 Under Review 2023-07-05 2023-06-29 2023-07-19 2023-08-18 2023-09-22 2024-09-21 n of Kabuyanda off-farm Net cation Selection work within the block INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UG-MWE-140235-CS-CDS / C onsultancy Services for Detai TF / A9023 Comp. 1 - Irrigation Services Prior Direct Selection Direct 500,000.00 1,255,094.53 Signed 2019-10-22 2019-11-27 2019-11-01 2019-12-17 2020-01-05 2021-02-25 2020-12-30 led Design for Matanda Irriga tion Scheme in Kanungu Dist rict UG-MWE-156897-CS-INDV / I NDIVIDUAL CONSULTANT DA M DESIGN AND CONSTRUCTI ON SPECIALIST AS A MEMBER Comp. 3 - Institutional Stren Individual Consult Under Implement OF THE DAM SAFETY PANEL TF / A9023 gthening and Implementatio Post Direct 37,000.00 0.00 2020-02-07 2020-08-27 2020-02-17 2020-03-02 2020-03-16 2020-04-15 ant Selection ation OF EXPERTS (DSPE) TO REVI n Support EW DETAILED DESIGN FOR M ATANDA IRRIGATION SCHEM E UNDER THE IRRIGATION FO R CLIMATE RESILIENCE - Mrs. Ljiljana Spasic-Gril UG-MWE-156898-CS-INDV / I NDIVIDUAL CONSULTANT GE OLOGIST/GEOTECHNICAL EX PERT AS AMEMBER OF DAM S Comp. 3 - Institutional Stren Individual Consult Under Implement AFETY PANEL OF EXPERTS (D TF / A9023 gthening and Implementatio Post Direct 37,000.00 0.00 2020-02-07 2020-08-27 2020-02-17 2020-03-02 2020-03-30 2020-04-02 ant Selection ation SPE) TO REVIEW DETAILED D n Support ESIGN FOR KABUYANDA IRRI GATION SCHEME UNDER THE IRRIGATION FOR CLIMATE RE SILIENCE PROJECT (ICRP)- Mr Pavlos G.Marinos UG-MWE-156899-CS-INDV / I NDIVIDUAL CONSULTANT HY DROLOGIST AS MEMBER OF T HE DAM SAFETY PANEL OF E Comp. 3 - Institutional Stren Individual Consult Under Implement XPERTS (DSPE) TO REVIEW D TF / A9023 gthening and Implementatio Post Direct 37,000.00 0.00 2020-02-07 2020-08-27 2020-02-17 2020-03-02 2020-03-30 2020-04-29 ant Selection ation ETAILED DESIGN FOR MATAN n Support DA IRRIGATION SCHEME UND ER THE IRRIGATION FOR CLI MATE RESILIENCE PROJECT (I CRDP) - Mr Henry Kayondo N tale UG-MWE-165062-CS-CQS / P reparation of additional studi Under Implement es and surveys for the Enviro TF / A9023 Comp. 1 - Irrigation Services Post Direct Selection Direct 95,000.00 0.00 2020-07-30 2020-07-24 2020-08-09 2020-10-13 2021-05-11 ation nmental and Social Impact A ssessment (ESIA) for Kabuya nda Irrigation Scheme UG-MWE-185126-CS-INDV / Consultancy Services for Indi vidual Specialist (Hydrologist Individual Consult IDA / 65650 Comp. 1 - Irrigation Services Post Open 250,000.00 0.00 Canceled 2020-08-07 2020-09-25 2020-10-16 2020-11-20 2023-11-20 ) as Panel of Dam Safety Exp ant Selection erts for Construction Supervi sion of Kabuyanda and Mata nda Dams Page 4 UG-MWE-185128-CS-INDV / Consultancy Services for Indi vidual Specialist ( Geologist) Individual Consult IDA / 65650 Comp. 1 - Irrigation Services Post Open 250,000.00 0.00 Canceled 2020-08-07 2020-09-25 2020-10-16 2020-11-20 2023-11-20 as Panel of Dam Safety Exper ant Selection ts for construction Supervisio n of Kabuyanda and Matand a Dams UG-MWE-186652-CS-INDV / Procurement of individual co Comp. 3 - Institutional Stren Individual Consult nsultant for the position of Pr IDA / 65650 gthening and Implementatio Post Open 135,000.00 142,116.79 Signed 2020-08-06 2020-08-27 2020-09-24 2021-08-26 2020-10-15 2021-12-14 2020-11-19 2022-03-12 2022-11-19 ant Selection oject Environment Safeguard n Support s Specialist as part of the PST UG-MWE-186655-CS-INDV / Procurement of an individual Comp. 3 - Institutional Stren Individual Consult consultant for the position of IDA / 65650 gthening and Implementatio Post Open 135,000.00 142,116.79 Signed 2020-08-07 2020-08-27 2020-09-25 2021-08-26 2020-10-16 2021-11-25 2020-11-20 2022-03-12 2022-11-20 ant Selection Project Social Safeguards Sp n Support ecialist to support the PST UG-MWE-186656-CS-INDV / Comp. 3 - Institutional Stren Procurement of an individual Individual Consult IDA / 65650 gthening and Implementatio Post Open 135,000.00 141,916.13 Signed 2020-08-06 2020-08-27 2020-09-24 2021-09-15 2020-10-15 2022-01-21 2020-11-19 2022-03-12 2022-11-19 consultant for the position of ant Selection n Support Project Procurement Speciali st as part of the PST UG-MWE-186657-CS-INDV / Comp. 3 - Institutional Stren Procurement of an individual Individual Consult IDA / 65650 gthening and Implementatio Post Open 135,000.00 142,116.79 Signed 2020-08-06 2020-08-27 2020-09-24 2021-08-26 2020-10-15 2021-11-25 2020-11-19 2022-03-12 2022-11-19 consultant for the position of ant Selection n Support Project M&E Specialist UG-MWE-186665-CS-INDV / Comp. 3 - Institutional Stren Procurement of an Individual Individual Consult IDA / 65650 gthening and Implementatio Post Open 135,000.00 142,397.72 Signed 2020-08-07 2020-08-27 2020-09-25 2021-08-26 2020-10-16 2021-11-25 2020-11-20 2022-03-12 2022-11-20 consultant for the position of ant Selection n Support the Project Agri-Business Spe cialist UG-MWE-186666-CS-INDV / Comp. 3 - Institutional Stren Procurement of an individual Individual Consult IDA / 65650 gthening and Implementatio Post Open 90,000.00 94,182.66 Signed 2020-08-07 2020-08-27 2020-09-25 2021-08-26 2020-10-16 2021-11-24 2020-11-20 2022-03-12 2022-11-20 consultant for the position of ant Selection n Support Project Support Officer/ Com munications Officer UG-MWE-186202-CS-CDS / P rocurement of an individual c Comp. 3 - Institutional Stren Pending Impleme onsultant to undertake the H TF / A9023 gthening and Implementatio Post Direct Selection Direct 18,000.00 0.00 2020-08-28 2020-09-07 2020-10-28 2021-01-26 ntation EC RAS and GeoStudio Traini n Support ng for the implementation ag ency staff. UG-MWE-185129-CS-INDV / Consultancy Services for Indi vidual Specialist(Dam Engine Individual Consult IDA / 65650 Comp. 1 - Irrigation Services Post Open 250,000.00 0.00 Canceled 2020-08-07 2020-09-25 2020-10-16 2020-11-20 2023-11-20 er ) as Panel of Dam Safety E ant Selection xperts for construction Super vision of Kabuyanda and Mat anda Dams UG-MWE-196180-CS-INDV / Consultancy Services for Indi vidual Specialist ( Geologist) Individual Consult Under Implement IDA / 65650 Comp. 1 - Irrigation Services Post Direct 250,000.00 0.00 2020-10-02 2021-02-19 2020-10-12 2020-11-02 2020-12-07 2022-12-07 as Panel of Dam Safety Exper ant Selection ation ts for construction Supervisio n of Kabuyanda and Matanda Dams UG-MWE-196176-CS-INDV / Consultancy Services for Indi vidual Specialist (Hydrologist Individual Consult Under Implement IDA / 65650 Comp. 1 - Irrigation Services Post Direct 250,000.00 0.00 2020-10-02 2021-02-19 2020-10-12 2020-11-02 2020-12-07 2022-12-07 ) as Panel of Dam Safety Exp ant Selection ation erts for Construction Supervi sion of Kabuyanda and Mata nda Dams UG-MWE-196185-CS-INDV / Consultancy Services for Indi vidual Specialist(Dam Engine Individual Consult Under Implement IDA / 65650 Comp. 1 - Irrigation Services Post Direct 250,000.00 0.00 2020-10-02 2021-02-19 2020-10-12 2020-11-02 2020-12-07 2022-12-07 er ) as Panel of Dam Safety E ant Selection ation xperts for construction Super vision of Kabuyanda and Mat anda Dams UG-MWE-256200-CS-INDV / Comp. 3 - Institutional Stren Procurement of an individual Individual Consult Under Implement IDA / 65650 gthening and Implementatio Post Open 90,000.00 0.00 2021-10-25 2022-04-22 2021-12-13 2022-01-03 2022-02-07 2024-02-07 consultant for the position of ant Selection ation n Support the Grant Fund Manager UG-MWE-258589-CS-INDV / Comp. 3 - Institutional Stren Procurement of 2 no. (two) S Individual Consult Under Implement IDA / 65650 gthening and Implementatio Post Open 180,000.00 0.00 2021-11-01 2022-07-14 2021-12-20 2022-01-10 2022-02-14 2024-02-14 ociologists to support the im ant Selection ation n Support plementation of farmer-led ir rigation strategies UG-MWE-258597-CS-CDS / P rocurement of an Individual Consultant Geologist/Geotec hnical expert as a member of Comp. 3 - Institutional Stren Pending Impleme the Dam Safety Panel of Exp IDA / 65650 gthening and Implementatio Post Direct Selection Direct 250,000.00 0.00 2021-10-25 2021-11-04 2022-01-08 2025-01-07 ntation erts (DSPE) to Review the De n Support tailed Design for Matanda Irri gation Scheme and Construct ion Supervision of Kabuyand a and Matanda Dams. UG-MWE-258595-CS-INDV / Comp. 3 - Institutional Stren Procurement of 3 no. (three) Individual Consult Under Implement IDA / 65650 gthening and Implementatio Prior Open 270,000.00 0.00 2021-11-01 2021-12-20 2022-01-10 2022-02-14 2022-04-28 Irrigation Engineers to suppo ant Selection ation n Support rt the Implementation of Co mponent 3 UG-MWE-258594-CS-INDV / Comp. 3 - Institutional Stren Procurement of 3 no. (three) Individual Consult Pending Impleme IDA / 65650 gthening and Implementatio Post Open 194,400.00 0.00 2021-11-01 2021-12-20 2022-01-10 2022-02-14 2022-08-13 Matching Grant Assistants to ant Selection ntation n Support support the Implementation of Component 2 UG-MWE-304499-CS-INDV / Comp. 3 - Institutional Stren Individual Consult Under Implement IDA / 65650 Post Open - National 194,400.00 0.00 2022-07-29 2022-07-19 2022-09-16 2022-10-07 2022-11-11 2024-10-31 Recruitment of three (03) Gr gthening and Implementatio ant Selection ation ants officers n Support UG-MWE-317092-CS-CDS / C onsultancy services for additi Under Implement onal technical investigations IDA / 65650 Comp. 1 - Irrigation Services Post Direct Selection Direct - National 363,451.00 0.00 2022-10-21 2022-10-06 2022-10-31 2023-01-04 2023-04-04 ation for detailed designs for Mata nda Irrigation Scheme Page 5 UG-MWE-324660-CS-INDV / Comp. 3 - Institutional Stren Procurement of Individual Co Individual Consult Under Implement IDA / 65650 gthening and Implementatio Post Open - National 147,000.00 0.00 2022-11-18 2022-12-14 2022-12-21 2023-01-11 2023-02-15 2025-02-04 nsultant for the Position of Fi ant Selection ation n Support nancial Management Speciali st Page 6 Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan: Original: 14 November 2013 - Revision, February 2 2017 2. Date of General Procurement Notice: July 2014 3. Period covered by this procurement plan: The procurement period of project covered from year February to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: July 9, 2010 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project IDA 53580-CG et IDA 59860-CG issued by Unité de Gestion de Projet. 5. Any Other Special Procurement Arrangements: 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary of the ICB (Works) Summary of the ICB (Goods) Summary of the NCB (Works) Summary of the NCB (Goods) Summary of the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 July 9, 2010 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary of number of contracts that will be let under QCBS Summary 0.5 10 Post of number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Congo, Republic of : CG Rep. LISUNGI Safety Nets System Project PLAN General Information Country: Congo, Republic of 2017-02-16 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P145263 GPN Date: Project Name: CG Rep. LISUNGI Safety Nets System Project Loan / Credit No: IDA / 53580, IDA / 59860, IDA / 63690 CG - LISUNGI - Safety Nets Projects Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CG-PL-SFS-TVX/035 / Recrut ement d une entreprise char Project management, Monito Request for Quota Single Stage - One E 2021-06-2 IDA / 63690 Post Limited 189,672.00 0.00 Canceled 2020-11-04 2020-12-30 gee de l amenagement des b ring and Evaluation (M&E) tions nvelope 8 ureau de l antenne departem entale GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PL/SFS-002-FR-CF / Mobil ier de bureau et petit matéri Project management, Monito Request for Quota Single Stage - One E IDA / 53580 Post Limited 38,258.00 0.00 Canceled 2017-11-25 2018-01-20 2018-07-19 el technique complémentaire ring and Evaluation (M&E) tions nvelope s pour l'UGP et CAS pilotes (0 2 lots) CG-PL/SFS-005-FR-CF / Fourn Project management, Monito Request for Quota Single Stage - One E itures de bureau et petit mat IDA / 53580 Post Limited 20,000.00 0.00 Canceled 2017-11-20 2018-01-15 2018-07-14 ring and Evaluation (M&E) tions nvelope ériel technique pour l'UGP Strengthening the demand-s CG-PL/SFS-015-C / Matériels Single Stage - One E IDA / 53580 ide of services through cash Prior Request for Bids Open - National 689,655.00 0.00 Canceled 2018-03-13 2018-03-18 2018-04-29 2018-05-29 2018-07-03 2018-12-30 informatiques zones pilotes nvelope transfer program CG-PL/SFS-004-FR-CF / Equip Project management, Monito Single Stage - One E ements et autre matériel pou IDA / 53580 Post Request for Bids Open - National 290,000.00 0.00 Canceled 2018-12-31 2019-01-05 2019-02-16 2019-03-18 2019-04-22 2019-10-19 ring and Evaluation (M&E) nvelope r les sept (07) CAS pilotes CG-PL/SFS-003-FR-CF / Bate Project management, Monito Request for Quota Single Stage - One E IDA / 53580 Post Limited 30,904.00 0.00 Canceled 2019-01-05 2019-03-02 2019-08-29 au balainière pour la CAS de ring and Evaluation (M&E) tions nvelope Makoua CG-PL/SFS-001-FR-CF / Mobil Project management, Monito Request for Quota Single Stage - One E ier de bureau et petit matéri IDA / 53580 Post Limited 9,500.00 0.00 Canceled 2018-12-04 2019-01-29 2019-07-28 ring and Evaluation (M&E) tions nvelope el technique pour l'UGP CG-LISUNGI-064-FNT / Acqui Strengthening the demand-s sition matériel informatique, Request for Quota Single Stage - One E IDA / 59860 ide of services through cash Post Open - National 43,636.00 40,349.99 Completed 2018-11-05 2018-12-31 2018-10-02 2019-06-29 2018-11-06 Acquisition du matériel infor tions nvelope transfer program matique pour le projet Lisung i CG-PL-SFS-FNT/032 / Acquisi tion des moyens roulants et nautiques (vehicules double Project management, Monito Request for Quota Single Stage - One E IDA / 63690 Post Limited 512,027.00 689,422.04 Signed 2020-10-05 2020-11-18 2020-11-30 2021-01-06 2021-05-29 canbine, motos DT, pirogues ring and Evaluation (M&E) tions nvelope motorisees, hors bord) pour l antenne departementale de l a Likouala CG-PL-SFS-FNT/034 / Acquisi tion du mobilier de bureau p Project management, Monito Request for Quota Single Stage - One E IDA / 63690 Post Limited 68,971.00 0.00 Signed 2020-12-15 2021-09-22 2021-02-09 2021-08-08 our la DDAS likouala et les C ring and Evaluation (M&E) tions nvelope AS de Impfondo, Betou, Enye lle, Ignie et Kintele CG-PL-SFS-FNT/033 / Acquisi tion du materiel informatique Project management, Monito Single Stage - One E Under Imple et technique (materiel inform IDA / 63690 Post Request for Bids Open - National 381,240.00 0.00 2020-10-30 2020-08-04 2020-11-04 2023-05-01 2020-12-16 2021-10-01 2021-01-15 2021-10-20 2021-02-19 2021-08-18 ring and Evaluation (M&E) nvelope mentation atique, source d energie, acc es internet, cartes de benefic iaires) CG-PL-SFS-FNT/041 / TOM2P RO FULL WEB, Acquisition, in Project management, Monito stallation et operationnalisati IDA / 63690 Post Direct Selection Direct 58,362.00 46,172.54 Signed 2020-09-15 2021-03-03 2020-09-20 2021-03-09 2020-10-25 2021-04-10 2021-04-23 ring and Evaluation (M&E) on du logiciel de gestion fina nciere et comptable TOM 2 P RO FULL WEB CG-PL-SFS-FNT/065 / Materie l didactique, Acquisition du di Establishment of key buildin dactique, pedagogique et ma g blocks of a national safety Single Stage - One E nuels scolaires au profit des IDA / 63690 Post Request for Bids Open - National 363,459.00 251,517.91 Signed 2021-09-01 2021-09-30 2021-09-06 2022-05-29 2021-10-18 2021-09-17 2021-11-17 2021-10-04 2021-12-22 2022-01-22 2022-06-20 net program and enhancem nvelope structures du Ministere prima ent of local capacities ire, secondaire charge de l al phabetisation du departeme nt de la Likouala CG-PL-SFS-FNT/087 / Acquisi tion du materiel informatique Establishment of key buildin et de communication au profi g blocks of a national safety Request for Quota Single Stage - One E IDA / 63690 Post Limited 35,189.00 0.00 Canceled 2021-11-20 2022-01-15 2022-07-14 t du comite departemental d net program and enhancem tions nvelope e verification et de validation ent of local capacities du departement de la Likoual a CG-PL-SFS-SCES/088 / Acqui Establishment of key buildin sition des moyens roulants et g blocks of a national safety Request for Quota Single Stage - One E nautiques au profit du comite IDA / 63690 Post Limited 87,972.00 0.00 Canceled 2021-11-20 2022-01-15 2022-07-14 net program and enhancem tions nvelope departemntal de verification ent of local capacities et de validation du departem ent de la Likouala CG-PL-SFS-MED/112 / Achat Establishment of key buildin des medicaments pour 14 ce g blocks of a national safety ntres de sante, 3 hôpitaux de IDA / 63690 Post Direct Selection Direct 98,639.00 79,165.71 Signed 2022-02-18 2022-01-17 2022-02-23 2022-01-20 2022-03-30 2022-06-22 2022-09-26 net program and enhancem base et 2 districts sanitaires ent of local capacities du departement de la Likoual a Page 1 CG-PL-SFS-FNT/113 / Acquisi tion des kits scolaires au prof Establishment of key buildin it des enfants des menages n g blocks of a national safety Request for Quota Single Stage - One E on beneficiaires des transfert IDA / 63690 Post Limited 79,741.00 0.00 Completed 2022-04-06 2022-09-15 2022-06-01 2022-11-28 2023-01-10 net program and enhancem tions nvelope s monetaires conditionnels et ent of local capacities Transferts monetaires lies au activites generatrices de rev enus (TMC/TMAGR) CG-PL-SFS-FNT/114 / Acquisi Establishment of key buildin tion des equipements de prot g blocks of a national safety Request for Quota Single Stage - One E ection individuelle au profit d IDA / 63690 Post Limited 124,011.00 0.00 Signed 2022-04-06 2022-05-30 2022-06-01 2022-11-28 net program and enhancem tions nvelope es apprentis beneficiaires de ent of local capacities s formations qualifiantes CG-PL-SFS-FNT/138 / Acquisi tion du materiel de laboratoir Establishment of key buildin e au profit des CSI et hopitau g blocks of a national safety Request for Quota Single Stage - One E IDA / 63690 Post Limited 51,589.00 0.00 Signed 2022-12-05 2022-11-15 2023-01-30 2023-07-29 x dans le cadre de mise en o net program and enhancem tions nvelope euvre du financement base s ent of local capacities ur la performance dans le do maine de la sante CG-PL-SFS/FNT/139 / Acquisi tion des equipements de prot Establishment of key buildin ection individuelle et kits d'a g blocks of a national safety IDA / 63690 Post Direct Selection Direct - National 95,234.00 0.00 Signed 2022-12-01 2022-10-08 2022-12-06 2022-10-14 2023-01-10 2023-07-09 pprentissage au profit des je net program and enhancem unes beneficiaires de la form ent of local capacities ation professionnelle du depa rtement de la Likouala NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PL/SFS-014-C / Société d Project management, Monito Request for Quota Single Stage - One E IDA / 59860 Post Limited 82,754.00 0.00 Canceled 2018-03-17 2018-05-12 2018-11-08 e Gardiennage, PSG ring and Evaluation (M&E) tions nvelope CG-LISUNGI-034-CS-ED / TO Project management, Monito IDA / 59860 Post Direct Selection Direct 13,333.00 13,089.02 Completed 2018-05-16 2018-08-08 2018-05-21 2018-08-08 2018-06-25 2018-10-02 2018-12-22 2018-10-18 MPRO, Mise à jour logiciel TO ring and Evaluation (M&E) MPRO CG-LISUNGI-058-CS / Contra t BPC paiement ménages des Establishment of key buildin zones d'extension 2 (Gambo g blocks of a national safety IDA / 59860 Post Direct Selection Direct 181,401.00 173,765.12 Signed 2018-10-15 2018-10-01 2018-10-20 2018-09-18 2018-11-24 2018-09-20 2019-05-23 ma, Ngo, Dolisie, Nganga Lin net program and enhancem golo) et des ménages éligible ent of local capacities s aux AGR dans toutes les zo nes du projet. CG-LISUNGI-060-CS / Contra Establishment of key buildin t LOT 2 avec la BPC pour le p g blocks of a national safety Request for Quota Single Stage - One E IDA / 53580 Post Open - National 263,630.00 0.00 Canceled 2018-12-05 2019-01-30 2019-07-29 aiement des ménages de Tal net program and enhancem tions nvelope angaï, Moungali, Oyo ent of local capacities CS-LISUNGI-005-CI / Societe de gardiennage Renouvellem Project management, Monito IDA / 59860 Post Direct Selection Direct 82,754.00 82,034.60 Completed 2019-05-30 2018-12-21 2019-06-04 2018-12-26 2019-07-09 2019-12-27 2020-01-05 2020-01-01 ent de contrat avec la societ ring and Evaluation (M&E) e de gardiennage CG-PL-SFS-SNC/037 / Societe de gardiennage et d entretie Project management, Monito n, renouvellement de contrat IDA / 63690 Post Direct Selection Direct 85,615.00 89,248.14 Completed 2020-11-09 2019-12-24 2020-11-14 2019-12-24 2020-12-19 2020-01-04 2021-06-17 2020-07-23 ring and Evaluation (M&E) entre l UGP et la societe de g ardiennage et d entretien PS G Balai magique CG-PL-SFS-SCES/067 / DEDE, Establishment of key buildin Contrat de services de forma g blocks of a national safety tion apprentissage avec l'eta IDA / 63690 Post Direct Selection Direct 1,583.00 2,902.82 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 net program and enhancem blissement DEDE pour la for ent of local capacities mation pratique de 5 apprent is en maçonnerie CG-PL-SFS-SCES/068 / EFON Establishment of key buildin GA, Contrat de services de fo g blocks of a national safety rmation apprentissage avec IDA / 63690 Post Direct Selection Direct 2,111.00 3,985.87 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 net program and enhancem etablissement EFONGA pour l ent of local capacities a formation pratique de 5 jeu nes en soudure CG-PL-SFS-SCES/069 / GEES, Establishment of key buildin Contrat de services de forma g blocks of a national safety tion apprentissage avec etab IDA / 63690 Post Direct Selection Direct 1,583.00 2,905.70 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-04 2021-12-25 2021-05-12 2022-06-23 net program and enhancem lissement GEES pour la form ent of local capacities ation pratique de 5 jeunes en menuiserie CG-PL-SFS-SCES/071 / MARLI N MOZ, Contrat de services d Establishment of key buildin e formation apprentissage av g blocks of a national safety IDA / 63690 Post Direct Selection Direct 2,111.00 3,985.87 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 ec etablissement MARTIN MO net program and enhancem Z pour la formation pratique ent of local capacities de 10 apprentis en productio n et pose de paves CG-PL-SFS-SCES/072 / MBAS SAMO, Contrat de services d Establishment of key buildin e formation apprentissage av g blocks of a national safety IDA / 63690 Post Direct Selection Direct 2,111.00 3,870.43 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 ec etablissement MBASSAMO net program and enhancem Apiculture pour la formation ent of local capacities pratique de 10 apprentis en apiculture CG-PL-SFS-SCES/073 / MONA Establishment of key buildin NA, contrat de services de fo g blocks of a national safety rmation apprentissage avec IDA / 63690 Post Direct Selection Direct 1,583.00 2,989.40 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 net program and enhancem etablissement MONANA pour ent of local capacities la formation pratique de 3 ap prentis en menuiserie CG-PL-SFS-SCES/074 / ALEX ANDRE, Contrat de service d Establishment of key buildin e formation apprentissage av g blocks of a national safety IDA / 63690 Post Direct Selection Direct 3,695.00 6,975.28 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 ec etablissement ALEXANDR net program and enhancem E pour la formation pratique ent of local capacities de 10 apprentis en menuiseri e et en mecanique automobil e CG-PL-SFS-SCES/075 / ANUC , Contrat de service de forma Establishment of key buildin tion apprentissage avec Asso g blocks of a national safety IDA / 63690 Post Direct Selection Direct 1,055.00 1,991.57 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 ciation des Navigants Unis du net program and enhancem Congo (ANUC) pour la format ent of local capacities ion pratique de 10 apprentis en conduite des hors bords Page 2 CG-PL-SFS-SCES/076 / NING BALA, Contrat de service de f Establishment of key buildin ormation apprentissage avec g blocks of a national safety IDA / 63690 Post Direct Selection Direct 3,167.00 0.00 Canceled 2021-11-15 2021-11-20 2021-12-25 2022-06-23 etablissement NINGBALA Do net program and enhancem minique pour la formation pr ent of local capacities atique de 10 apprentis en me nuiserie CG-PL-SFS-SCES/077 / EVEN Establishment of key buildin CIA, Contrat de service de for g blocks of a national safety mation apprentissage avec e IDA / 63690 Post Direct Selection Direct 2,111.00 3,985.87 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 net program and enhancem tablissement EVENCIA pour l ent of local capacities a formation pratique de 10 a pprentis en coiffure CG-PL-SFS-SCES/078 / MAGN OMELE, Contrat de service d Establishment of key buildin e formation apprentissage av g blocks of a national safety IDA / 63690 Post Direct Selection Direct 1,583.00 2,989.40 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 ec etablissement MAGNOMEL net program and enhancem E Remy pour la formation pra ent of local capacities tique de 5 apprentis en plom berie sanitaire CG-PL-SFS-SCES/079 / MASS AKATA ONANA, Contrat de se Establishment of key buildin rvice de formation apprentiss g blocks of a national safety IDA / 63690 Post Direct Selection Direct 3,695.00 6,970.49 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 age avec etablissement MAS net program and enhancem SAKATA ONANA pour la form ent of local capacities ation pratique de 3 apprentis en menuiserie et soudure CG-PL-SFS-SCES/080 / MONT BLANC, Contrat de service de Establishment of key buildin formation apprentissage ave g blocks of a national safety IDA / 63690 Post Direct Selection Direct 950.00 2,391.52 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 c etablissement MONT BLAN net program and enhancem C pour la formation pratique ent of local capacities de 3 apprentis en menuiserie -garnissage CG-PL-SFS-SCES/081 / SEXIN Establishment of key buildin E, Contrat de service de form g blocks of a national safety ation apprentissage avec eta IDA / 63690 Post Direct Selection Direct 1,055.00 1,992.94 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 net program and enhancem blissement SEXINE pour la fo ent of local capacities rmation de 3 apprentis en coi ffure esthetique CG-PL-SFS-SCES/082 / VIVEZ LE PRESENT, Contrat de servi Establishment of key buildin ce de formation apprentissag g blocks of a national safety IDA / 63690 Post Direct Selection Direct 1,583.00 2,989.40 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-12 2022-06-23 e avec etablissement VIVEZ net program and enhancem LE PRESENT pour la formatio ent of local capacities n pratique de 5 apprentis en menuiserie CG-PL-SFS-SCES/070 / JC SE RVICES, Contrat de services Establishment of key buildin de formation apprentissage a g blocks of a national safety IDA / 63690 Post Direct Selection Direct 2,128.00 4,151.26 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-05 2022-06-23 vec etablissement JC SERVIC net program and enhancem ES pour la formation pratique ent of local capacities de 5 jeunes en mecanique ge nerale CG-PL-SFS-SCES/066 / BISO Establishment of key buildin na BISO, Contrat de services g blocks of a national safety de formation apprentissage a IDA / 63690 Post Direct Selection Direct 2,128.00 4,151.26 Signed 2021-11-15 2021-04-01 2021-11-20 2021-05-03 2021-12-25 2021-05-05 2022-06-23 net program and enhancem vec l'etablissement Biso na B ent of local capacities iso pour la formation de 5 ap prentis en coupe-couture CG-PL-SFS-SCES/089 / AKAM Establishment of key buildin A NGALA, Contrat de services g blocks of a national safety de formation apprentissage a IDA / 63690 Post Direct Selection Direct 1,597.00 3,142.66 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-03 2022-01-09 2021-05-12 2022-07-08 net program and enhancem vec atelier AKAMA NGALA po ent of local capacities ur la formation de 5 apprenti s en maçonnerie CG-PL-SFS-SCES/090 / ATA E LONDO ETUMBA, Contrat de Establishment of key buildin services de formation appren g blocks of a national safety IDA / 63690 Post Direct Selection Direct 1,065.00 4,190.21 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 tissage avec l'atelier ATA EL net program and enhancem ONDO ETUMBA pour la forma ent of local capacities tion de 5 apprentis en maraic hage CG-PL-SFS-SCES/091 / Patiss Establishment of key buildin erie BIBIANE, Contrat de serv g blocks of a national safety ices de formation apprentiss IDA / 63690 Post Direct Selection Direct 1,065.00 2,095.10 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 net program and enhancem age avec la patisserie BIBIAN ent of local capacities E pour la formation de 5 appr entis en patisserie CG-PL-SFS-SCES/094 / KIMB ANGUISTE, Contrat de servic Establishment of key buildin es de formation apprentissag g blocks of a national safety e avec l'atelier de maçonneri IDA / 63690 Post Direct Selection Direct 1,597.00 3,142.66 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 net program and enhancem e Ensemble des constructeur ent of local capacities s kimbanguistes pour la form ation de 5 apprentis en maço nnerie CG-PL-SFS-SCES/095 / LA PR Establishment of key buildin OVIDENCE, Contrat de servic g blocks of a national safety es de formation apprentissag IDA / 63690 Post Direct Selection Direct 1,597.00 3,142.66 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 net program and enhancem e avec l'atelier LA PROVIDEN ent of local capacities CE pour la formation de 5 ap prentis en menuiserie CG-PL-SFS-SCES/096 / MABO Establishment of key buildin NGA, Contrat de services de f g blocks of a national safety ormation apprentissage avec IDA / 63690 Post Direct Selection Direct 1,065.00 2,095.10 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 net program and enhancem l'atelier MABONGA pour la for ent of local capacities mation de 5 apprentis en ma raichage CG-PL-SFS-SCES/097 / MBO Establishment of key buildin MBO, Contrat de services de g blocks of a national safety Pending Impl formation apprentissage ave IDA / 63690 Post Direct Selection Direct 1,597.00 0.00 2021-11-30 2021-12-05 2022-01-09 2022-07-08 net program and enhancem ementation c l'atelier MBOMBO pour la fo ent of local capacities rmation de 5 apprentis en m açonnerie CG-PL-SFS-SCES/098 / MIRAY ESSA, contrat de services de Establishment of key buildin formation apprentissage ave g blocks of a national safety IDA / 63690 Post Direct Selection Direct 1,065.00 2,095.10 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 c le salon de coiffure MIRAYE net program and enhancem SSA pour la formation de 5 a ent of local capacities pprentis en coiffure esthetiqu e Page 3 CG-PL-SFS-SCES/099 / SALA NGOLO, Contrat de services Establishment of key buildin de formation apprentissage a g blocks of a national safety IDA / 63690 Post Direct Selection Direct 4,259.00 6,285.31 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 vec l'atelier SALANGOLO pou net program and enhancem r la formation de 10 apprenti ent of local capacities s en mecanique automobile e t soudure. CG-PL-SFS-SCES/100 / AMES Establishment of key buildin FE, Contrat de service de for g blocks of a national safety mation apprentissage avec l' IDA / 63690 Post Direct Selection Direct 4,259.00 8,380.42 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 net program and enhancem atelier AMESFE pour la forma ent of local capacities tion de 10 apprentis en coup e couture CG-PL-SFS-SCES/101 / ETS M Establishment of key buildin OBILE, Contrat de service de g blocks of a national safety IDA / 63690 Post Direct Selection Direct 2,130.00 4,190.21 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 formation apprentissage pou net program and enhancem r la formation de 5 apprentis ent of local capacities en soudure CG-PL-SFS-SCES/102 / BATH Establishment of key buildin EIKA, Contrat de service de f g blocks of a national safety ormation apprentissage avec IDA / 63690 Post Direct Selection Direct 1,597.00 3,142.66 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 net program and enhancem l'atelier BATHEIKA pour la for ent of local capacities mation de 5 apprentis en me nuiserie CG-PL-SFS-SCES/103 / BOZA Establishment of key buildin PETA, Contrat de service de f g blocks of a national safety ormation apprentissage avec IDA / 63690 Post Direct Selection Direct 1,597.00 3,142.66 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 net program and enhancem l'atelier BOZAPETA pour la fo ent of local capacities rmation de 5 apprentis en ch arpente bois CG-PL-SFS-SCES/104 / CHAN Establishment of key buildin CELVIE COIFFURE, Contrat de g blocks of a national safety service de formation apprent IDA / 63690 Post Direct Selection Direct 1,065.00 2,095.10 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 net program and enhancem issage avec atelier Chancelvi ent of local capacities e Coiffure pour la formation d e 5 apprentis en coiffure CG-PL-SFS-SCES/105 / APICU LTURE ENYELLE, Contrat de s Establishment of key buildin ervices de formation apprent g blocks of a national safety IDA / 63690 Post Direct Selection Direct 1,065.00 2,036.65 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 issage avec le centre d'Apicu net program and enhancem lture d'Enyelle pour la format ent of local capacities ion de 5 apprentis en apicult ure CG-PL-SFS-SCES/106 / DZAK Establishment of key buildin AS, Contrat de service ce for g blocks of a national safety mation apprentissage avec a IDA / 63690 Post Direct Selection Direct 4,259.00 8,399.81 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 net program and enhancem telier de couture DZAKAS po ent of local capacities ur la formation de 10 apprent is en coupe couture CG-PL-SFS-SCES/107 / MOLE Establishment of key buildin NDE, Contrat de service de fo g blocks of a national safety rmation apprentissage avec l IDA / 63690 Post Direct Selection Direct 1,597.00 3,149.93 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 net program and enhancem 'établissement MOLENDE pou ent of local capacities r la formation de 5 apprentis en maçonnerie CCG-PL-SFS-SCES/108 / HABI B COUTURE, Contrat de servi Establishment of key buildin ce de formation apprentissag g blocks of a national safety IDA / 63690 Post Direct Selection Direct 4,259.00 4,073.30 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 e avec l'atlier de couture HA net program and enhancem BIB pour la formation de 10 a ent of local capacities pprentis en coupe couture CG-PL-SFS-SCES/109 / LA PO LYTECHNIQUE, Contrat de se Establishment of key buildin rvice de formation apprentiss g blocks of a national safety IDA / 63690 Post Direct Selection Direct 2,130.00 2,036.65 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 age avec l'atelier LA POLYTE net program and enhancem CHNIQUE pour la formation d ent of local capacities e 10 apprentis en maraichag e CG-PL-SFS-SCES/110 / TOUT Establishment of key buildin LE TEMPS, Contrat de service g blocks of a national safety de formation apprentissage a IDA / 63690 Post Direct Selection Direct 1,597.00 2,099.95 Signed 2021-11-30 2021-04-01 2021-12-05 2021-05-04 2022-01-09 2021-05-12 2022-07-08 net program and enhancem vec etablissement tout le te ent of local capacities mps pour la formation de 5 a pprentis en charpente CG-PL-SFS-CS/115 / Contrat Establishment of key buildin entre le CDVV et la DDSSS d g blocks of a national safety e la Likouala relatif a la mise IDA / 63690 Post Direct Selection Direct 70,475.00 0.00 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-03 2022-10-11 2023-04-09 net program and enhancem en oeuvre du financement ba ent of local capacities se sur la performance dans l e domaine de la sante CG-PL-SFS-CS/117 / Contrat de service entre le Comite de partemental de verification e Establishment of key buildin t de validation de la Likouala g blocks of a national safety IDA / 63690 Post Direct Selection Direct 36,203.00 0.00 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-03 2022-10-11 2023-04-09 et le district sanitaire de Imfo net program and enhancem ndo pour la mise en oeuvre d ent of local capacities u financement base sur la pe rformance dans le domaine d e la sante CG-PL-SFS-CS/120 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et l hopital de IDA / 63690 Post Direct Selection Direct 179,245.00 0.00 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-03 2022-10-11 2023-04-09 net program and enhancem base de Impfondo pour la mi ent of local capacities se en oeuvre du financement base sur la performance dan s le domaine de la sante CG-PL-SFS-CS/121 / Contrat de service entre le comite de Establishment of key buildin partemental de validation et g blocks of a national safety de verification de la Likouala IDA / 63690 Post Direct Selection Direct 160,801.00 0.00 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-03 2022-10-11 2023-04-09 net program and enhancem et l hopital de base de Betou ent of local capacities pour la mise en oeuvre du fin ancement base sur la perfor mance dans le domaine de la sante CG-PL-SFS-CS/122 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 118,693.00 114,476.87 Signed 2022-09-01 2022-08-31 2022-09-06 2022-01-04 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante de Enyelle pour la mise ent of local capacities en oeuvre du financement ba se sur la performance dans l e domaine de la sante Page 4 CG-PL-SFS-CS/123 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 34,756.00 32,956.86 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-04 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante de Thanry pour la mise ent of local capacities en oeuvre du financement ba se sur la performance dans l e domaine de la sante CG-PL-SFS-CS/124 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 59,714.00 47,468.19 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-04 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante de Mouale pour la mise ent of local capacities en oeuvre du financement ba se sur la performance dans l e domaine de la sante CG-PL-SFS-CS/125 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 45,569.00 0.00 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-03 2022-10-11 2023-04-09 net program and enhancem sante de Mokabi pour la mise ent of local capacities en oeuvre du financement ba se sur la performance dans l e domaine de la sante CG-PL-SFS-CS/126 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 132,740.00 122,648.13 Signed 2022-09-01 2022-08-31 2022-09-06 2022-01-03 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante de Dongou pour la mis ent of local capacities e en oeuvre du financement base sur la performance dan s le domaine de la sante CG-PL-SFS-CS/127 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 45,839.00 43,465.95 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-04 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante de Boyele pour la mise ent of local capacities en oeuvre du financement ba se sur la performance dans l e domaine de la sante CG-PL-SFS-CS/128 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 73,131.00 105,314.75 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-04 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante de Moungoungui pour l ent of local capacities a mise en oeuvre du finance ment base sur la performanc e dans le domaine de la sant e CG-PL-SFS-CS/129 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 41,133.00 39,927.55 Signed 2022-09-01 2022-08-31 2022-09-06 2022-01-03 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante de Mombenzele pour la ent of local capacities mise en oeuvre du financem ent base sur la performance dans le domaine de la sante CG-PL-SFS-CS/130 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le poste de IDA / 63690 Post Direct Selection Direct 44,587.00 43,279.54 Signed 2022-09-01 2022-08-31 2022-09-06 2022-01-04 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante de Mboua pour la mise ent of local capacities en oeuvre du financement ba se sur la performance dans l e domaine de la sante CG-PL-SFS-CS/131 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 128,798.00 122,915.77 Signed 2022-08-01 2022-08-31 2022-08-06 2022-01-04 2022-09-10 2022-01-11 2023-03-09 net program and enhancem sante de Liranga pour la mis ent of local capacities e en oeuvre du financement base sur la performance dan s le domaine de la sante CG-PL-SFS-CS/132 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 78,887.00 76,571.38 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-04 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante de Epena pour la mise ent of local capacities en oeuvre du financement ba se sur la performance dans l e domaine de la sante CG-PL-SFS-CS/133 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 75,848.00 73,624.42 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-04 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante Elikia pour la mise en o ent of local capacities euvre du financement base s ur la performance dans le do maine de la sante CG-PL-SFS-CS/134 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 82,294.00 78,535.92 Signed 2022-09-01 2022-01-03 2022-09-06 2022-01-04 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante Divine pour la mise en ent of local capacities oeuvre du financement base sur la performance dans le d omaine de la sante CG-PL-SFS-CS/135 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le centre de IDA / 63690 Post Direct Selection Direct 109,764.00 104,751.53 Signed 2022-09-01 2022-08-31 2022-09-06 2022-01-04 2022-10-11 2022-01-11 2023-04-09 net program and enhancem sante de Bohona pour la mis ent of local capacities e en oeuvre du financement base sur la performance dan s le domaine de la sante CG-PL-SFS-CS/137 / Contrat de service entre le comite de Establishment of key buildin partemental de verification e g blocks of a national safety t de validation et le district s IDA / 63690 Post Direct Selection Direct 26,549.00 0.00 Signed 2022-09-01 2022-08-31 2022-09-06 2022-01-03 2022-10-11 2023-04-09 net program and enhancem anitaire Enyelle Betou pour la ent of local capacities mise en oeuvre du financem ent base sur la performance dans le domaine de la sante CG-PL-SFS-SC/112 / Golf Bra vo, contrat de service de for Establishment of key buildin mation apprentissage avec le g blocks of a national safety Under Imple prestataire de formation qual IDA / 63690 Post Direct Selection Direct - National 3,738.00 0.00 2022-10-03 2021-04-01 2022-10-08 2021-05-03 2022-11-12 2023-05-11 net program and enhancem mentation ifiante etablissement garage- ent of local capacities golf Bravo et frères pour la fo rmation de 10 apprentis en mécanique automobile Page 5 CG-PL-SFS-SC/113 / La Repe ntance, Contrat de service de Establishment of key buildin formation apprentissage ave g blocks of a national safety Under Imple c le prestataire de formation IDA / 63690 Post Direct Selection Direct - National 3,738.00 0.00 2022-10-03 2022-07-29 2022-10-08 2022-11-12 2023-05-11 net program and enhancem mentation qualifiante etablissement la r ent of local capacities epentance pour la formation de 10 apprentis en mecaniqu e generale CG-PL-SFS-SC/114 / Contrat de service entre l Unite de G estion du Projet Lisungi et le Establishment of key buildin Comite Departemental de ve g blocks of a national safety Pending Impl IDA / 63690 Post Direct Selection Direct - National 123,747.00 0.00 2022-10-01 2022-10-06 2022-11-10 2023-05-09 rification et de validation rela net program and enhancem ementation tif a la mise en oeuvre du fin ent of local capacities ancement base sur la perfor mance dans le domaine de la sante dans le departement d e la likouala CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-LISUNGI-018-CS-QC / Spé cialiste transferts monétaires Project management, Monito Consultant Qualifi IDA / 59860 Post Open - National 60,000.00 31,776.48 Completed 2018-05-07 2018-04-25 2018-05-28 2018-07-11 2018-06-12 2018-08-10 2018-06-27 2018-09-14 2018-07-04 2019-03-13 2021-12-31 , recrutement spécialiste tran ring and Evaluation (M&E) cation Selection sferts monétaires pour le proj et Lisungi CG-LISUNGI-019-CS-QC / Spé Project management, Monito Consultant Qualifi cialiste AGR, Recrutement sp IDA / 59860 Post Open - National 60,000.00 31,776.48 Completed 2018-05-09 2018-05-10 2018-05-30 2018-07-26 2018-07-13 2018-08-06 2018-08-12 2018-08-06 2018-09-16 2018-07-04 2019-03-15 2019-12-31 ring and Evaluation (M&E) cation Selection écialiste AGR du projet Lisun gi CG-LISUNGI-020-CS-QC / Aid Project management, Monito Consultant Qualifi e comptable, Recrutement ai IDA / 59860 Post Open - National 13,500.00 9,435.80 Completed 2018-06-07 2018-07-26 2018-06-28 2018-07-26 2018-08-11 2018-09-24 2018-09-10 2018-08-18 2018-10-15 2018-09-27 2019-04-13 2019-06-30 ring and Evaluation (M&E) cation Selection de comptable pour le projet L isungi CG-LISUNGI-017-CS-QC / Co Project management, Monito Consultant Qualifi mptable, Recrutement compt IDA / 59860 Post Open - National 38,000.00 19,721.89 Completed 2018-08-20 2018-07-26 2018-09-10 2018-07-26 2018-10-24 2018-08-17 2018-11-23 2018-10-15 2018-12-28 2018-10-23 2019-06-26 2019-06-30 ring and Evaluation (M&E) cation Selection able du projet Lisungi CG-LISUNGI-064-CS / Recrut ement d'une association loca le pour le suivi, l'encadremen Establishment of key buildin t et l'accompagnement des b g blocks of a national safety Consultant Qualifi énéficiaires du programme A IDA / 59860 Post Open - National 164,500.00 328,777.96 Completed 2018-11-30 2018-11-19 2018-12-21 2019-02-03 2018-12-12 2019-03-05 2019-01-22 2019-04-09 2019-02-01 2019-10-06 2019-12-31 net program and enhancem cation Selection GR et des cash transferts de ent of local capacities Brazzaville centre (Makélékél é, Bacongo, Moungali, Talang aï, Mfilou, Madibou, Djiri, Nga nga lingolo) (LOT 2) CG-LISUNGI-065-CS / Recrut ement d'une association loca Establishment of key buildin le pour le suivi, l'encadremen g blocks of a national safety Consultant Qualifi t et l'accompagnement des b IDA / 59860 Post Open - National 130,500.00 271,116.76 Completed 2018-11-30 2018-11-19 2018-12-21 2019-02-03 2018-12-12 2019-03-05 2019-01-22 2019-04-09 2019-02-01 2019-10-06 2019-12-31 net program and enhancem cation Selection énéficiaires du programme A ent of local capacities GR et des cash transferts de l a zone sud (Dolisie 1, Dolisie 2, Mvoumvou, Loandjili) (LOT 3) CG-LISUNGI-062-CS / Recrut ement d'une association loca Establishment of key buildin le pour le suivi, l'encadremen g blocks of a national safety Consultant Qualifi t et l'accompagnement des b IDA / 59860 Post Open - National 105,000.00 321,847.42 Completed 2018-11-30 2018-11-19 2018-12-21 2019-02-03 2018-12-12 2019-03-05 2019-01-22 2019-04-09 2019-02-01 2019-10-06 2019-12-31 net program and enhancem cation Selection énéficiaires du programme A ent of local capacities GR et des cash transferts de Oyo, Makoua, Ngo et Gambo ma (LOT 1) CS-LISUNGI-001-FRM / Cabin Project management, Monito Quality And Cost- et d audit independant-Recru IDA / 59860 Post Open - National 13,119.00 0.00 Canceled 2019-03-30 2019-03-05 2019-04-20 2019-06-03 2019-07-01 2019-07-31 2019-09-04 2019-10-09 2020-10-08 ring and Evaluation (M&E) Based Selection tement d un cabinet d audit i ndependant CG-PL/SFS-013-QC / Cabinet Project management, Monito Quality And Cost- IDA / 59860 Post Open - National 10,000.00 0.00 Canceled 2018-03-10 2018-03-31 2018-05-14 2018-06-11 2018-07-11 2018-08-15 2018-09-19 2019-09-19 d'audit, E&Y ring and Evaluation (M&E) Based Selection CG-PL-SFS-SC/046 / Associat ion locale Recrutement d une association locale (ASLO) cha Establishment of key buildin rgee de l encadrement et l ac g blocks of a national safety Consultant Qualifi Under Implement IDA / 63690 Post Open - National 131,520.00 0.00 2021-04-30 2020-12-20 2021-05-21 2021-01-13 2021-07-04 2021-08-03 2021-09-07 2022-03-06 compagnement des menage net program and enhancem cation Selection ation s des disdtricts de Impfondo, ent of local capacities Dongou et Enyelle porteurs d e micro projets et des jeunes candidats a la formation prof essionnelle CG-PL-SFS-CS/044 / Agence de paiement Recrutement d Establishment of key buildin une agence de paiement cha g blocks of a national safety Quality And Cost- Under Implement rgee d assurer le versement IDA / 63690 Post Open - National 343,576.00 0.00 2021-05-31 2020-12-20 2021-06-21 2021-01-13 2021-08-04 2021-09-01 2021-10-01 2021-11-05 2021-12-10 2022-12-10 net program and enhancem Based Selection ation des allocations aux menages ent of local capacities eligibles des districts de Braz zaville (Ignie et Kintele) et de Pointe Noire (Lot 2) CG-PL-SFS-SC/048 / ONG Re crutement d une ONG charge Strengthening the demand-s Quality And Cost- e du ciblage et de la selectio IDA / 63690 ide of services through cash Post Open - National 490,000.00 266,425.49 Completed 2021-05-31 2020-12-27 2021-06-21 2022-05-29 2021-08-04 2021-04-23 2021-09-01 2021-04-28 2021-10-01 2021-04-29 2021-11-05 2021-05-03 2021-12-10 2021-05-15 2022-12-10 2021-07-01 Based Selection n des menages de la Likoual transfer program a (Impfondo, Dongou, Betou et Enyelle) (Lot 1) CG-PL-SFS-SC/058 / Agence de communication Recrutem Project management, Monito Quality And Cost- ent d une agence de commu IDA / 63690 Post Open - National 318,993.00 262,032.41 Signed 2021-05-31 2021-04-23 2021-06-21 2021-05-19 2021-08-04 2021-06-01 2021-09-01 2021-06-01 2021-10-01 2021-06-10 2021-11-05 2021-06-22 2021-12-10 2021-09-04 2022-12-10 ring and Evaluation (M&E) Based Selection nication nationale et instituti onnelle pour le projet Lisungi CG-PL-SFS-SC/049 / ONG Re crutement d une ONG charge Strengthening the demand-s Quality And Cost- Under Implement e du ciblage et de la selectio IDA / 63690 ide of services through cash Post Open - National 253,346.00 0.00 2021-05-31 2020-12-27 2021-06-21 2021-08-04 2021-09-01 2021-10-01 2021-11-05 2021-12-10 2022-12-10 Based Selection ation n des beneficiaires de Brazza transfer program ville (Ignie et Kintele) et de P ointe Noire CG-PL-SFS-SC/050 / UNHCR Strengthening the demand-s Recrutement du HCR pour l a UN Agencies (Dire IDA / 63690 ide of services through cash Post Direct 333,000.00 451,175.63 Signed 2021-07-10 2021-04-15 2022-01-06 ppui au monitoring et la prise ct) transfer program en charge des groupes specif iques Page 6 CG-PL-SFS-CS/043 / Agence de paiement Recrutement d Establishment of key buildin une agence de paiement cha g blocks of a national safety Quality And Cost- Under Implement IDA / 63690 Post Open - National 666,942.00 0.00 2021-05-31 2020-12-20 2021-06-21 2021-01-13 2021-08-04 2021-09-01 2021-10-01 2021-11-05 2021-12-10 2022-12-10 rgee d assurer le versement net program and enhancem Based Selection ation des allocations aux menages ent of local capacities eligibles des districts de Impf ondo, Dongou et Enyelle (Lot 1) CG-PL-SFS-SC/045 / Associat ion locale recrutement d une association locale (ASLO) cha Establishment of key buildin rgee de l encadrement et l ac g blocks of a national safety Quality And Cost- Under Implement IDA / 63690 Post Open - National 278,171.00 0.00 2021-05-31 2020-12-20 2021-06-21 2021-01-13 2021-08-04 2021-09-01 2021-10-01 2021-11-05 2021-12-10 2022-12-10 compagnement des menage net program and enhancem Based Selection ation s du district de Betou porteur ent of local capacities s de micro projets et des jeu nes candidats a la formation professionnelle (Lot 1) CG-PL-SFS-SC/047 / Associat ion locale Recrutement d une association locale chargee de Establishment of key buildin l encadrement et l accompag g blocks of a national safety Quality And Cost- Under Implement nement des menages des dis IDA / 63690 Post Open - National 211,053.00 0.00 2021-05-31 2020-12-20 2021-06-21 2021-01-13 2021-08-04 2021-09-01 2021-10-01 2021-11-05 2021-12-10 2022-12-10 net program and enhancem Based Selection ation tricts de Ignie et kintele et de ent of local capacities Pointe Noire porteurs de micr o projets et des jeunes candi dats a la formation professio nnelle (lot 3) CG-PL-SFS-SC/141 / Recrute ment d un cabinet charge de Project management, Monito Quality And Cost- realiser l audit financier des IDA / 63690 Post Open - National 26,188.00 0.00 Signed 2023-02-28 2023-01-18 2023-03-21 2023-02-14 2023-05-04 2023-03-11 2023-06-01 2023-03-24 2023-07-01 2023-04-06 2023-08-05 2023-05-04 2023-09-09 2024-09-08 ring and Evaluation (M&E) Based Selection exercices 2022 et 2023 du pr ojet Lisungi systeme de filets sociaux INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PL/SFS-006-SC-ED / RSEL Project management, Monito -Responsable de suivi et éval IDA / 53580 Prior Direct Selection Direct 24,000.00 0.00 Canceled 2017-11-02 2017-11-12 2018-01-16 2018-07-15 ring and Evaluation (M&E) uation pour la CAS de Bacon go CG-PL/SFS-008-SC-ED / Audit Project management, Monito eur interne, monsieur GNAH IDA / 53580 Prior Direct Selection Direct 3,900.00 42,941.28 Signed 2017-04-17 2017-04-27 2017-07-01 2017-04-17 2017-12-28 ring and Evaluation (M&E) OUA FEUKEU, par tacite reco nduction CG-PL/SFS-009-SC-ED / Spéc ialiste en Transferts Monétair Project management, Monito IDA / 53580 Prior Direct Selection Direct 3,530.00 38,256.84 Signed 2017-03-28 2017-04-01 2017-04-20 2016-02-15 2017-10-17 es, madame DANY GANDZIRI ring and Evaluation (M&E) , par tacite reconduction CG-PL/SFS-011-SC-ED / Spéc Project management, Monito ialiste en suivi et Evaluation, IDA / 53580 Prior Direct Selection Direct 30,000.00 32,205.96 Signed 2018-01-31 2018-02-10 2018-04-16 2017-03-27 2018-10-13 ring and Evaluation (M&E) Madame Jocelyne Sandra Eln a YAMA CG-PL/SFS-012-ED / Spéciali ste Développement Système Project management, Monito IDA / 53580 Prior Direct Selection Direct 28,000.00 30,058.90 Signed 2018-01-31 2018-02-10 2018-04-16 2016-12-15 2018-10-13 Informatique, Mr Bernard Hu ring and Evaluation (M&E) gues OYEKA IBARA, par tacit e reconduction CG-PL/SFS-010-SC-ED / RAFC Project management, Monito IDA / 53580 Prior Direct Selection Direct 2,940.00 32,205.96 Signed 2017-03-27 2017-03-31 2017-04-27 2017-03-27 2017-10-24 -Responsable Administratif et ring and Evaluation (M&E) Financier CG-LISUNGI-016-CS-ED / Ad Project management, Monito ministrateur Recrutement Ad IDA / 59860 Post Direct Selection Direct 60,000.00 32,334.84 Completed 2018-03-20 2018-03-28 2018-03-24 2018-03-28 2018-04-05 2018-03-30 2018-10-02 2020-12-31 ring and Evaluation (M&E) ministrateur base de donnée s RSU CG-LISUNGI-021-CS-ED / RSE L Makoua, Contrat de service Project management, Monito IDA / 59860 Post Direct Selection Direct 20,000.00 3,589.86 Completed 2018-05-02 2018-02-01 2018-05-12 2018-02-01 2018-07-16 2018-02-01 2019-01-12 2019-12-31 de consultant avec Responsa ring and Evaluation (M&E) ble Suivi Evaluation de Mako ua CG-PL/SFS-007-SC-INDIV / C onsultant local pour l'Etude s Project management, Monito Individual Consult IDA / 53580 Post Open 30,000.00 0.00 Canceled 2018-11-26 2019-01-14 2019-02-04 2019-03-11 2019-09-07 ur les populations spécifique ring and Evaluation (M&E) ant Selection s (Personnes handicapées et peuples autochtones) CG-LISUNGI-022-CS-ED / RSE L Oyo, Contrat de service de Project management, Monito IDA / 59860 Post Direct Selection Direct 20,000.00 3,815.35 Completed 2018-05-02 2018-02-01 2018-05-12 2018-02-01 2018-07-16 2018-02-01 2019-01-12 2019-12-31 consultant Responsable Suivi ring and Evaluation (M&E) Evaluation de Oyo CG-LISUNGI-023-CS-ED / RSE L Makelekele, Contrat de ser Project management, Monito IDA / 59860 Post Direct Selection Direct 20,000.00 4,880.10 Completed 2018-05-02 2018-02-01 2018-05-12 2018-02-01 2018-07-16 2018-02-01 2019-01-12 2020-12-31 vice de consultant Responsa ring and Evaluation (M&E) ble Suivi évaluation locale de Makelekele CG-LISUNGI-024-CS-ED / RSE L Moungali, Contrat de servic Project management, Monito IDA / 59860 Post Direct Selection Direct 20,000.00 7,009.59 Completed 2018-05-02 2018-02-01 2018-05-12 2018-02-01 2018-07-16 2018-02-01 2019-01-12 2019-12-31 e de consultant Responsable ring and Evaluation (M&E) suivi évaluation de Moungali CG-LISUNGI-025-CS-ED / Cha uffeur de liaison, Contrat de Project management, Monito IDA / 59860 Post Direct Selection Direct 7,890.00 3,254.10 Completed 2018-05-02 2018-05-18 2018-05-12 2018-05-18 2018-07-16 2018-02-01 2019-01-12 2019-12-31 service de consultant, Chauff ring and Evaluation (M&E) eur de liaison de la CAS de M akoua CG-LISUNGI-026-CS-ED / Cha uffeur du coordonnateur, Con Project management, Monito IDA / 59860 Post Direct Selection Direct 8,500.00 2,704.07 Completed 2018-05-02 2018-05-10 2018-05-12 2018-05-18 2018-07-16 2018-02-01 2019-01-12 2019-12-31 trat de service de consultant, ring and Evaluation (M&E) chauffeur du coordonnateur du projet Lisungi CG-LISUNGI-027-CS-ED / Spé cialiste en gestion financière, Project management, Monito Contrat de service de consult IDA / 59860 Post Direct Selection Direct 31,976.00 33,911.89 Completed 2018-05-02 2018-05-18 2018-05-12 2018-05-18 2018-07-16 2018-04-02 2019-01-12 2021-12-31 ring and Evaluation (M&E) ant, spécialiste en gestion fin ancière du projet lisungi CG-LISUNGI-028-CS-ED / Ass istante administrative, Contr Project management, Monito IDA / 59860 Post Direct Selection Direct 25,500.00 9,050.36 Completed 2018-05-02 2018-05-16 2018-05-12 2018-05-17 2018-07-16 2018-02-01 2019-01-12 2021-06-30 at de service de consultant, ring and Evaluation (M&E) Assistante administrative du projet Lisungi Page 7 CG-LISUNGI-029-CS-ED / Cha uffeur de liaison UGP, Contra Project management, Monito t de service de consultant, C IDA / 59860 Post Direct Selection Direct 7,890.00 2,551.55 Completed 2018-05-02 2018-05-10 2018-05-12 2018-05-17 2018-07-16 2018-02-01 2019-01-12 2019-12-31 ring and Evaluation (M&E) hauffeur de liaison de l'unité de Gestion du Projet Lisungi CG-LISUNGI-030-CS-ED / Cha uffeur de liaison CAS Mounga Project management, Monito li, Contrat de service de cons IDA / 59860 Post Direct Selection Direct 7,890.00 2,509.95 Completed 2018-05-02 2018-05-18 2018-05-12 2018-05-18 2018-07-16 2018-02-01 2019-01-12 2019-12-31 ring and Evaluation (M&E) ultant, Chauffeur de liaison d e la CAS de Moungali CG-LISUNGI-031-CS-ED / Cha uffeur de liaison CAS Mvoum Project management, Monito vou, Contrat de service de co IDA / 59860 Post Direct Selection Direct 8,766.00 3,476.69 Completed 2018-05-02 2018-02-01 2018-05-12 2018-02-01 2018-07-16 2018-02-01 2019-01-12 2019-12-31 ring and Evaluation (M&E) nsultant Chauffeur de liaison de la CAS de Mvoumvou à Po inte Noire CG-LISUNGI-032-CS-ED / Spé cialiste en développement de systèmes informatiques, Con Project management, Monito IDA / 59860 Post Direct Selection Direct 25,666.00 0.00 Under Review 2018-05-02 2018-02-01 2018-05-12 2018-07-16 2019-01-12 trat de service de consultant ring and Evaluation (M&E) Spécialiste en développemen t de systèmes informatiques du projet Lisungi CG-LISUNGI-033-CS-ED / Spé cialiste en gestion financière, Project management, Monito Contrat de service de consult IDA / 59860 Post Direct Selection Direct 5,000.00 31,776.48 Completed 2018-05-02 2018-05-17 2018-05-12 2018-05-17 2018-07-16 2016-01-09 2019-01-12 2021-12-31 ring and Evaluation (M&E) ant spécialiste en gestion fin ancière du projet Lisungi CS-LISUNGI-033-CS-CI / Web master designer, Recruteme Project management, Monito Individual Consult IDA / 59860 Post Open 34,000.00 17,940.58 Completed 2018-08-20 2018-07-26 2018-10-08 2018-08-06 2018-10-29 2018-06-27 2018-12-03 2018-07-04 2019-06-01 2019-12-31 nt d'un consultant webmaste ring and Evaluation (M&E) ant Selection r designer pour le projet Lisu ngi CG-LISUNGI-034-CS-CI / Coor donnateur cellule technique, Project management, Monito Individual Consult IDA / 59860 Post Open 60,000.00 31,452.66 Signed 2018-08-20 2018-07-26 2018-10-08 2018-09-14 2018-10-29 2018-09-18 2018-12-03 2018-09-27 2019-06-01 Recrutement du coordonnate ring and Evaluation (M&E) ant Selection ur de la cellule technique du RSU CG-LISUNGI-035-CS-CI / Cont rat de service de consultant , Project management, Monito Responsable suivi et évaluati IDA / 53580 Post Direct Selection Direct 12,000.00 10,592.16 Signed 2018-08-20 2018-08-04 2018-08-30 2018-08-04 2018-11-03 2016-06-06 2019-05-02 ring and Evaluation (M&E) on local de la circonscription d'action sociale (CAS) de Mvo umvou CG-LISUNGI-036-CS-CI / Cont rat de service de consultant, Project management, Monito IDA / 53580 Post Direct Selection Direct 36,000.00 31,893.12 Signed 2018-08-20 2018-08-01 2018-08-30 2018-08-01 2018-11-03 2016-02-15 2019-05-02 Spécialiste en suivi évaluatio ring and Evaluation (M&E) n du projet Lisungi CG-LISUNGI-037-CS-CI / Cont rat de service de consultant- Project management, Monito IDA / 53580 Post Direct Selection Direct 36,000.00 31,776.48 Signed 2018-08-20 2018-08-05 2018-08-30 2018-08-06 2018-11-03 2016-02-15 2019-05-02 Spécialiste en réseau et syst ring and Evaluation (M&E) èmes informatiques du projet Lisungi CG-LISUNGI-038-CS-CI / Cont rat de service de consultant, Project management, Monito Chauffeur du projet auprès d IDA / 59860 Post Direct Selection Direct 6,500.00 5,514.70 Completed 2018-08-30 2018-10-19 2018-09-09 2018-10-20 2018-11-13 2018-09-13 2019-05-12 2019-06-30 ring and Evaluation (M&E) es circonscriptions d'action s ociale (CAS) de Talangaï et D jiri. CG-LISUNGI-039-CS-CI / Cont rat de service de consultant, Project management, Monito chauffeur du projet auprès d IDA / 59860 Post Direct Selection Direct 6,500.00 5,467.30 Completed 2018-08-30 2018-08-01 2018-09-09 2018-09-13 2018-11-13 2018-09-13 2019-05-12 2019-12-31 ring and Evaluation (M&E) es circonscriptions d'action s ociale de Bacongo et Makele kele. CG-LISUNGI-040-CS-CI / Cont rat de service de consultant, Project management, Monito IDA / 59860 Post Direct Selection Direct 6,500.00 5,514.70 Completed 2018-08-30 2018-10-19 2018-09-09 2018-10-19 2018-11-13 2018-09-13 2019-05-12 2019-06-30 Chauffeur du projet auprès d ring and Evaluation (M&E) e la CAS de Makelekele. CG-LISUNGI-041-CS-CI / Cont Project management, Monito rat de service de consultant, IDA / 59860 Post Direct Selection Direct 6,500.00 0.00 Canceled 2018-08-30 2018-09-09 2018-11-13 2019-05-12 ring and Evaluation (M&E) chauffeur du projet à la CAS de Oyo CG-LISUNGI-042-CS-CI / Cont rat de service de consultant, Project management, Monito IDA / 53580 Post Direct Selection Direct 43,200.00 38,271.74 Signed 2018-08-30 2018-08-03 2018-09-09 2018-08-03 2018-11-13 2017-03-28 2019-05-12 spécialiste en transferts mon ring and Evaluation (M&E) étaires du projet Lisungi CG-LISUNGI-043-CS-CI / Cont rat de service de consultant s Project management, Monito IDA / 53580 Post Direct Selection Direct 33,600.00 29,658.05 Completed 2018-08-30 2018-08-05 2018-09-09 2018-08-05 2018-11-13 2016-02-17 2019-05-12 2021-12-31 pécialiste en développement ring and Evaluation (M&E) de systèmes informatiques d u projet Lisungi CG-LISUNGI-044-CS-CI / Cont rat de service de consultant r Project management, Monito esponsable suivi évaluation l IDA / 53580 Post Direct Selection Direct 12,000.00 10,592.16 Completed 2018-08-30 2018-08-03 2018-09-09 2018-08-03 2018-11-13 2016-07-16 2019-05-12 2020-12-31 ring and Evaluation (M&E) ocal de la circonscription d'a ction sociale de Makelekele CG-LISUNGI-046-CS-CI / Cont Project management, Monito rat de service de consultant IDA / 53580 Post Direct Selection Direct 6,312.00 5,571.48 Completed 2018-08-30 2018-08-04 2018-09-09 2018-08-04 2018-11-13 2016-07-01 2019-05-12 2021-12-31 ring and Evaluation (M&E) chauffeur de l'Unité de gestio n du projet CG-LISUNGI-048-CS-CI / Cont rat de service de consultant Project management, Monito IDA / 53580 Post Direct Selection Direct 6,312.00 0.00 Canceled 2018-08-30 2018-09-09 2018-11-13 2019-05-12 chauffeur du projet Lisungi à ring and Evaluation (M&E) la CAS de Mvoumvou CG-LISUNGI-049-CS-CI / Cont Project management, Monito rat de service de consultant IDA / 53580 Post Direct Selection Direct 6,312.00 5,571.48 Completed 2018-08-30 2018-08-04 2018-09-09 2018-08-04 2018-11-13 2016-09-13 2019-05-12 2019-12-31 ring and Evaluation (M&E) chauffeur du projet à la CAS de Mvoumvou CG-LISUNGI-050-CS-CI / Cont rat de service de consultant r Project management, Monito IDA / 53580 Post Direct Selection Direct 12,000.00 10,592.16 Completed 2018-09-03 2018-08-03 2018-09-13 2018-08-04 2018-11-17 2016-09-27 2019-05-16 2019-12-31 esponsable suivi évaluation l ring and Evaluation (M&E) ocal de la CAS de Moungali Page 8 CG-LISUNGI-051-CS-CI / Cont rat de service de consultant r Project management, Monito IDA / 53580 Post Direct Selection Direct 12,000.00 10,592.16 Completed 2018-09-03 2018-08-03 2018-09-13 2018-08-03 2018-11-17 2016-06-09 2019-05-16 2019-12-31 esponsable suivi évaluation d ring and Evaluation (M&E) e la CAS de Oyo CG-LISUNGI-052-CS-CI / Cont Project management, Monito rat de service de consultant IDA / 53580 Post Direct Selection Direct 6,312.00 5,571.48 Completed 2018-09-03 2018-08-04 2018-09-13 2018-08-04 2018-11-17 2016-09-08 2019-05-16 2019-12-31 ring and Evaluation (M&E) chauffeur du projet à la CAS de Makoua CG-LISUNGI-053-CS-CI / Cont rat de service de consultant Project management, Monito IDA / 53580 Post Direct Selection Direct 7,200.00 6,355.30 Completed 2018-09-03 2018-08-04 2018-09-13 2018-08-04 2018-11-17 2016-07-12 2019-05-16 2019-12-31 chauffeur de l'unité de gestio ring and Evaluation (M&E) n du projet Lisungi. CG-LISUNGI-054-CS-CI / Cont Project management, Monito rat de service de consultant, IDA / 53580 Post Direct Selection Direct 20,400.00 18,072.77 Completed 2018-09-03 2018-08-03 2018-09-13 2018-08-03 2018-11-17 2016-08-01 2019-05-16 2021-06-30 ring and Evaluation (M&E) assistante administrative du projet. CG-LISUNGI-055-CS-CI / Cont rat de service de consultant r Project management, Monito IDA / 53580 Post Direct Selection Direct 12,000.00 10,592.16 Completed 2018-09-03 2018-08-05 2018-09-13 2018-08-05 2018-11-17 2016-06-03 2019-05-16 2020-12-31 esponsable suivi évaluation l ring and Evaluation (M&E) ocal de la CAS de Makoua CG-LISUNGI-056-CS-CI / Cont Project management, Monito rat de service de consultant IDA / 53580 Post Direct Selection Direct 6,312.00 5,571.48 Completed 2018-09-03 2018-08-06 2018-09-13 2018-08-06 2018-11-17 2016-07-12 2019-05-16 2019-12-31 ring and Evaluation (M&E) chauffeur de l'unité de gestio n du projet CG-LISUNGI-057-CS-CI / Ave nant au Contrat de service d Project management, Monito IDA / 53580 Post Direct Selection Direct 20,400.00 0.00 Canceled 2018-09-03 2018-09-13 2018-11-17 2019-05-16 e consultant assistante admi ring and Evaluation (M&E) nistrative du projet Lisungi CG-LISUNGI-047-CS-CI / Cont rat de service de consultant Project management, Monito Responsable suivi évaluation IDA / 53580 Post Direct Selection Direct 12,000.00 10,596.30 Signed 2018-08-30 2018-09-11 2018-09-09 2018-09-11 2018-11-13 2016-06-03 2019-05-12 ring and Evaluation (M&E) local de la circonscription d'a ction sociale (CAS) de Talan gaï CG-LISUNGI-045-CS-CI / Cont Project management, Monito rat de service de consultant IDA / 53580 Post Direct Selection Direct 48,000.00 42,385.20 Signed 2018-08-30 2018-09-11 2018-09-09 2018-09-11 2018-11-13 2016-02-16 2019-05-12 ring and Evaluation (M&E) Auditeur interne du projet Lis ungi CG-LISUNGI-058-CS-CI / Res ponsable sauvegarde environ Project management, Monito Individual Consult nemental, Recrutement d'un IDA / 59860 Post Open 60,000.00 31,090.50 Signed 2018-10-15 2018-11-12 2018-12-03 2019-01-03 2018-12-24 2019-01-03 2019-01-28 2019-01-04 2019-07-27 ring and Evaluation (M&E) ant Selection responsable sauvegarde envi ronnementale pour le projet Lisungi CG-LISUNGI-063-CS-CI / Pres tataire informatique, Contrat Project management, Monito Individual Consult IDA / 59860 Post Direct 6,000.00 5,183.34 Completed 2018-10-31 2018-11-12 2018-11-10 2019-01-03 2018-12-01 2019-01-03 2019-01-05 2019-01-04 2019-07-04 2019-12-31 de service de consultant pres ring and Evaluation (M&E) ant Selection tataire informatique CG-LISUNGI-064-CI / CTPAD, Establishment of key buildin Contrat avec la CTPAD porta g blocks of a national safety nt mise en œuvre des mesur IDA / 59860 Post Direct Selection Direct 117,189.00 103,308.59 Completed 2018-10-31 2018-11-28 2018-11-10 2019-04-10 2019-01-14 2019-04-10 2019-07-13 2019-12-31 net program and enhancem es de sauvegarde pour les po ent of local capacities pulations autochtones de Ng o et Gamboma CG-LISUNGI-059-CS / Avena Establishment of key buildin nt au contrat avec l'agence d g blocks of a national safety e paiement (BPC) relatif au p IDA / 53580 Post Direct Selection Direct 314,409.00 0.00 Canceled 2018-12-24 2019-01-03 2019-03-09 2019-09-05 net program and enhancem aiement des ménages de Ma ent of local capacities kelekele, Bacongo, Mvoumvo u et Makoua (LOT 1) CG-LISUNGI-066-CS / Contra Strengthening the demand-s t de prestation de service av IDA / 53580 ide of services through cash Prior Direct Selection Direct 537,278.00 280,314.44 Completed 2018-12-24 2018-12-17 2019-01-03 2019-02-19 2019-03-09 2018-11-30 2019-09-05 2019-12-31 ec l'agence de communicatio transfer program n GLAD SERVICES. CS-LISUNGI-001-CI / Informa ticien-geomaticien-Recrutem Project management, Monito Individual Consult IDA / 59860 Post Open 24,000.00 16,852.13 Completed 2019-03-30 2019-03-05 2019-05-18 2019-04-10 2019-06-08 2019-04-10 2019-07-13 2019-04-16 2020-01-09 2019-07-01 ent d un informaticien geom ring and Evaluation (M&E) ant Selection aticien charge du Registre So cial Unique (RSU) CS-LISUNGI-002-CI / Respon sable Administratif et Financi Project management, Monito IDA / 59860 Post Direct Selection Direct 35,000.00 35,522.97 Completed 2019-05-15 2019-03-01 2019-05-25 2019-03-29 2019-07-29 2019-04-01 2020-01-25 2019-12-31 er Renouvellement de contra ring and Evaluation (M&E) t avec le Responsable admini stratif et financier CS-LISUNGI-003-CI / Adminis trateur Renouvellement de c Project management, Monito ontrat avec l Administrateur IDA / 59860 Post Direct Selection Direct 15,000.00 15,224.13 Completed 2019-05-30 2019-03-25 2019-06-09 2019-04-01 2019-08-13 2019-04-01 2020-02-09 2019-12-31 ring and Evaluation (M&E) base de donnees et systeme s informatiques du projet Lis ungi CS-LISUNGI-004-CI / Speciali ste en developpement Renou Project management, Monito vellement de contrat avec le IDA / 59860 Post Direct Selection Direct 14,000.00 14,209.19 Completed 2019-05-30 2019-01-02 2019-06-09 2019-01-02 2019-08-13 2019-01-02 2020-02-09 2019-12-31 ring and Evaluation (M&E) specialiste en developpemen t de systemes informatiques CS-LISUNGI-006-CI / Chauffe ur Recrutement d un chauffe Project management, Monito Individual Consult IDA / 59860 Post Open 5,260.00 0.00 Canceled 2019-05-30 2018-11-05 2019-07-18 2019-08-08 2019-09-12 2020-03-10 ur du projet Lisungi pour la ci ring and Evaluation (M&E) ant Selection rconscription d action sociale de Ngo et Gamboma CS-LISUNGI-007-FRM / Instit ut National de la Statistique Contrat avec l Institut Nation Strengthening the demand-s al de la Statistique pour reali IDA / 59860 ide of services through cash Post Direct Selection Direct 148,662.00 147,369.19 Signed 2019-05-30 2019-03-01 2019-06-09 2019-04-05 2019-08-13 2019-04-06 2020-02-09 ser les enquetes socio demo transfer program graphiques sur l evaluation d e la resilience et etude d imp act des transferts monetaires sur les beneficiaires du projet CG-PL-SFS-CI/005 / Respons able sauvegarde environnem entale, Recrutement d un res Project management, Monito Individual Consult IDA / 63690 Post Open 49,142.00 46,716.32 Completed 2020-09-28 2020-05-21 2020-11-16 2020-07-21 2020-12-07 2020-08-12 2021-01-11 2020-09-22 2021-07-10 2022-01-01 ponsable sauvegarde environ ring and Evaluation (M&E) ant Selection nementale et sociale pour l a ntenne departementale Likou ala Page 9 CG-PL-SFS-CI/010 / Assistant administratif et financier, Rec Project management, Monito Individual Consult rutement d un assistant admi IDA / 63690 Post Open 52,763.00 95.01 Completed 2020-11-23 2020-07-10 2021-01-11 2020-11-02 2021-02-01 2020-11-02 2021-03-08 2020-11-04 2021-09-04 2022-01-01 ring and Evaluation (M&E) ant Selection nistratif et financier pour l Un ite de Gestion du Projet CG-PL-SFS-CI/011 / Respons able sauvegarde environnem entale, Recrutement d un res Project management, Monito Individual Consult IDA / 63690 Post Open 49,142.00 18,473.13 Completed 2020-07-27 2020-05-21 2020-09-14 2020-07-21 2020-10-05 2020-08-11 2020-11-09 2020-09-22 2021-05-08 2022-01-01 ponsable sauvegarde environ ring and Evaluation (M&E) ant Selection nementale pour l antenne de partementale du projet Lisun gi dans la Likouala CG-PL-SFS-CI/020 / RTM, ren ouvellement de Contrat avec Project management, Monito monsieur MAKAYA Aubert Mo IDA / 63690 Post Direct Selection Direct 93,111.00 31,362.12 Completed 2020-09-21 2020-04-30 2020-10-01 2020-01-03 2020-12-05 2020-01-08 2021-06-03 2021-01-01 ring and Evaluation (M&E) linard, actuel responsable tra nsfert monétaire du projet Li sungi CG-PL-SFS-CI/023 / Geomati cien, Renouvellement de con Project management, Monito trat avec monsieur MOUAND IDA / 63690 Post Direct Selection Direct 74,489.00 25,089.70 Completed 2020-09-21 2020-04-30 2020-10-01 2020-01-06 2020-12-05 2020-01-08 2021-06-03 2021-01-01 ring and Evaluation (M&E) A Van-Dyck, actuel informati cien geomaticien charge du RSU CG-PL-SFS-CI/029 / Chauffeu r du coordonnateur du projet, renouvellement de Contrat a Project management, Monito IDA / 63690 Post Direct Selection Direct 18,622.00 5,982.37 Completed 2020-09-21 2020-05-02 2020-10-01 2020-01-07 2020-12-05 2020-01-08 2021-06-03 2020-02-01 vec monsieur MOUELET Gisc ring and Evaluation (M&E) ard D'Estaing, actuel chauffe ur du Coordonnateur du Proj et CG-PL-SFS-CI/025 / Comptab le, Renouvellement de contra Project management, Monito IDA / 63690 Post Direct Selection Direct 59,971.00 110.19 Completed 2020-09-21 2020-04-30 2020-10-01 2020-01-06 2020-12-05 2020-01-08 2021-06-03 2021-01-01 t avec monsieur MANKOLOLO ring and Evaluation (M&E) Pierre Brice, actuel comptabl e du projet Lisungi CG-PL-SFS-CI/009 / Secretair e Comptable, Recrutement d Project management, Monito Individual Consult IDA / 63690 Post Open 33,624.00 0.00 Canceled 2020-11-23 2021-01-11 2021-02-01 2021-03-08 2021-09-04 un secretaire comptable pour ring and Evaluation (M&E) ant Selection l antenne departementale de la Likouala CG-PL-SFS-CI/012 / Specialis te sauvegarde sociale 2, Recr Project management, Monito Individual Consult utement d un specialiste sau IDA / 63690 Post Open 49,142.00 18,473.13 Completed 2020-07-27 2020-04-30 2020-09-14 2020-07-21 2020-10-05 2020-08-11 2020-11-09 2020-09-22 2021-05-08 2022-01-01 ring and Evaluation (M&E) ant Selection vegarde sociale 2 pour l ante nne departementale du proje t dans la Likouala CG-PL-SFS-CI/003 / Specialis te mesures d accompagnem Project management, Monito Individual Consult ent, Recrutement d un Speci IDA / 63690 Post Open 77,593.00 0.00 Canceled 2020-09-25 2020-11-13 2020-12-04 2021-01-08 2021-07-07 ring and Evaluation (M&E) ant Selection aliste mesures d accompagn ement, sante et education po ur l UGP CG-PL-SFS-CI/004 / Spécialis te formation qualifiante, acco Project management, Monito Individual Consult IDA / 63690 Post Open 93,111.00 0.00 Canceled 2020-09-21 2020-11-09 2020-11-30 2021-01-04 2021-07-03 mpagnement et insertion po ring and Evaluation (M&E) ant Selection ur l unite de gestion du proje t CG-PL-SFS-CI/017 / Chauffeu r de liaison Ignie, Recruteme Project management, Monito Individual Consult IDA / 63690 Post Open 10,346.00 0.00 Canceled 2020-12-21 2020-10-20 2021-02-08 2021-03-01 2021-04-05 2021-10-02 nt d un chauffeur de liaison p ring and Evaluation (M&E) ant Selection our la CAS de Ignie CG-PL-SFS-CI/016 / Chauffeu r pinassier Betou, Recruteme Project management, Monito Individual Consult IDA / 63690 Post Open 10,346.00 0.00 Canceled 2020-11-23 2020-10-20 2021-01-11 2021-02-01 2021-03-08 2021-09-04 nt d un chauffeur pinassier p ring and Evaluation (M&E) ant Selection our la CAS de Betou CG-PL-SFS-CI/026 / Aide com ptable, renouvellement de C Project management, Monito ontrat avec madame HOUEN IDA / 63690 Post Direct Selection Direct 27,933.00 9,408.64 Completed 2020-09-21 2020-04-30 2020-10-01 2020-01-06 2020-12-05 2020-01-08 2021-06-03 2021-01-01 ring and Evaluation (M&E) ADIO LEHO Benicia, actuelle aide comptable du projet Lis ungi. CG-PL-SFS-CI/018 / Chauffeu r de liaison CAS Kintele, Recr Project management, Monito Individual Consult IDA / 63690 Post Open 10,346.00 0.00 Canceled 2020-12-01 2020-10-20 2021-01-19 2021-02-09 2021-03-16 2021-09-12 utement d un chauffeur de li ring and Evaluation (M&E) ant Selection aison pour la CAS de Kintele CG-PL-SFS-CI/024 / Assistant developpeur informaticien, R enouvellement de contrat av Project management, Monito IDA / 63690 Post Direct Selection Direct 24,830.00 8,363.23 Completed 2020-09-21 2020-04-30 2020-10-01 2020-01-03 2020-12-05 2020-01-08 2021-06-03 2021-01-01 ec monsieur KAYI Constant Je ring and Evaluation (M&E) an Frederic, actuel asssistant informatique du projet Lisung i. CG-PL-SFS-CI/007 / Respons able suivi evaluation, Recrut Project management, Monito Individual Consult ement d un responsable suivi IDA / 63690 Post Open 49,142.00 14,123.54 Signed 2020-11-23 2020-07-10 2021-01-11 2020-10-05 2021-02-01 2020-11-02 2021-03-08 2020-11-03 2021-09-04 ring and Evaluation (M&E) ant Selection evaluation pour l antenne de partementale de la Likouala CG-PL-SFS-CI/022 / Respons able programmation et devel oppement de systemes infor matiques, Renouvellement d Project management, Monito IDA / 63690 Post Direct Selection Direct 86,904.00 29,271.31 Completed 2020-09-21 2020-04-30 2020-10-01 2020-01-03 2020-12-05 2020-01-08 2021-06-03 2021-01-01 e contrat avec monsieur OY ring and Evaluation (M&E) EKA IBARA Hugues, actuel Sp ecialiste en developpement d e systemes informatiques du projet Lisungi CG-PL-SFS-CI/031 / Chauffeu r de liaison, Renouvellement Project management, Monito de contrat avec monsieur NSI IDA / 63690 Post Direct Selection Direct 18,622.00 6,272.42 Completed 2020-09-21 2020-05-02 2020-10-01 2020-01-06 2020-12-05 2020-01-08 2021-06-03 2022-01-01 ring and Evaluation (M&E) EMO Droctovee, actuellemen t chauffeur de liaison de l'UG P CG-PL-SFS-CI/030 / Chauffeu r de liaison de l'UGP, Contrat Project management, Monito de service de consultant ave IDA / 63690 Post Direct Selection Direct 18,622.00 32.06 Completed 2020-09-21 2020-05-02 2020-10-01 2020-01-06 2020-12-05 2020-01-08 2021-06-03 2021-01-01 ring and Evaluation (M&E) c monsieur MOUKALA Irvain, actuellement chauffeur de lia ison de l'UGP Page 10 CG-PL-SFS-CI/001 / Expert p assation des marches, Recrut Project management, Monito Individual Consult IDA / 63690 Post Open 82,766.00 19,943.39 Signed 2020-09-21 2020-04-30 2020-11-09 2020-07-13 2020-11-30 2020-08-11 2021-01-04 2020-11-06 2021-07-03 ement d'un expert passation ring and Evaluation (M&E) ant Selection des marches pour l Unite de Gestion du Projet CG-PL-SFS-CI/013 / Specialis te sauvegarde sociale 2, Recr Project management, Monito Individual Consult utement d un specialiste sau IDA / 63690 Post Open 49,142.00 18,484.83 Completed 2020-07-27 2020-04-30 2020-09-14 2020-07-21 2020-10-05 2020-08-11 2020-11-09 2020-09-22 2021-05-08 2022-01-01 ring and Evaluation (M&E) ant Selection vegarde sociale pour l anten ne departementale de la Liko uala CG-PL-SFS-CI/015 / Chauffeu r pinassier Enyelle, Recrutem Project management, Monito Individual Consult IDA / 63690 Post Open 10,346.00 0.00 Canceled 2020-11-23 2020-10-20 2021-01-11 2021-02-01 2021-03-08 2021-09-04 ent d un chauffeur pinassier ring and Evaluation (M&E) ant Selection pour la CAS de Enyelle CG-PL-SFS-CI/019 / RAF, Ren ouvellement de contrat avec Project management, Monito monsieur BOUKORO Edouard IDA / 63690 Post Direct Selection Direct 108,630.00 36,589.14 Completed 2020-09-21 2020-04-30 2020-10-01 2020-01-06 2020-12-05 2020-01-08 2021-06-03 2021-01-01 ring and Evaluation (M&E) , actuel responsable administ ratif et financier du projet Lis ungi CG-PL-SFS-CI/014 / Chauffeu r pinassier Impfondo, Recrute Project management, Monito Individual Consult IDA / 63690 Post Open 10,346.00 0.00 Canceled 2020-11-23 2020-10-20 2021-01-11 2021-02-01 2021-03-08 2021-09-04 ment d un chauffeur pinassie ring and Evaluation (M&E) ant Selection r pour la CAS d'Impfondo CG-PL-SFS-CI/027 / Assistant e administrative, renouvelle ment de Contrat pour 6 mois Project management, Monito IDA / 63690 Post Direct Selection Direct 8,784.00 9,399.45 Completed 2020-04-20 2020-04-30 2020-04-30 2020-01-07 2020-07-04 2020-01-08 2020-12-31 2021-01-01 avec madame MASSOLOKA A ring and Evaluation (M&E) lice Dahlias, actuelle assistan te administrative du projet. CG-PL-SFS-CI/021 / RPAGR, Contrat de service de consult ant avec monsieur ITSOUA G Project management, Monito IDA / 63690 Post Direct Selection Direct 2,586.00 15,681.06 Completed 2020-08-17 2020-04-30 2020-08-27 2020-01-06 2020-10-31 2020-01-08 2021-04-29 2021-01-01 uy Fulgence, actuel responsa ring and Evaluation (M&E) ble programme Activites gen eratrices de revenus du proj et Lisungi. CG-PL-SFS-CI/036 / Stagiaire developpeur informaticien, C Project management, Monito IDA / 63690 Post Direct Selection Direct 18,622.00 0.00 Canceled 2020-11-16 2020-11-26 2021-01-30 2021-07-29 ontrat avec mr MALAKY Princ ring and Evaluation (M&E) e, developpeur informaticien CG-PL-SFS-CI/038 / Expert fo rmation, recrutement d un ex Project management, Monito Individual Consult pert formation, insertion prof IDA / 63690 Post Open 93,111.00 32,592.78 Completed 2020-09-30 2020-07-21 2020-11-18 2020-10-06 2020-12-09 2020-11-02 2021-01-13 2020-11-04 2021-07-12 2022-01-01 ring and Evaluation (M&E) ant Selection essionnelle et AGR pour l Uni te de Gestion du Projet CG-PL-SFS-CI/039 / Administ rateur base de donnees Recr Project management, Monito Individual Consult utement d un Administrateur IDA / 63690 Post Open 93,111.00 32,429.52 Completed 2020-09-30 2020-07-21 2020-11-18 2020-09-25 2020-12-09 2020-11-02 2021-01-13 2020-11-04 2021-07-12 2022-01-01 ring and Evaluation (M&E) ant Selection base de donnees et systeme s d information du projet Lisu ngi CG-PL-SFS-CI/040 / Expert sa Project management, Monito Individual Consult nte Recrutement de l expert IDA / 63690 Post Open 77,593.00 32,429.52 Completed 2020-10-30 2020-07-21 2020-12-18 2020-10-14 2021-01-08 2020-11-02 2021-02-12 2020-11-10 2021-08-11 2022-01-01 ring and Evaluation (M&E) ant Selection sante financement base sur l a performance CG-PL-SFS-SC/051 / Sous pre fecture Recrutement de la so Strengthening the demand-s us prefecture de Impfondo p IDA / 63690 ide of services through cash Post Direct Selection Direct 54,049.00 0.00 Under Review 2021-05-29 2021-05-13 2021-06-08 2021-08-12 2022-02-08 our le ciblage, la contreverifi transfer program cation et le suivi des conditio nnalites CG-PL-SFS-SC/052 / Sous pre fecture de Enyelle Recrutem Strengthening the demand-s ent de la sous prefecture de IDA / 63690 ide of services through cash Post Direct Selection Direct 54,049.00 0.00 Under Review 2021-04-30 2021-05-13 2021-05-10 2021-07-14 2022-01-10 Enyelle pour le ciblage, la co transfer program ntre verification et le suivi de s conditionnalites CG-PL-SFS-SC/053 / Sous pre fecture Betou Recrutement d Strengthening the demand-s e la sous prefecture de Betou IDA / 63690 ide of services through cash Post Direct Selection Direct 54,049.00 0.00 Under Review 2021-05-31 2021-05-13 2021-06-10 2021-08-14 2022-02-10 pour le ciblage, la contre veri transfer program fication et le suivi des conditi onnalites CG-PL-SFS-SC/054 / Sous pre fecture Ignie Recrutement de Strengthening the demand-s la sous prefecture de Ignie p IDA / 63690 ide of services through cash Post Direct Selection Direct 16,426.00 0.00 Under Review 2021-05-31 2021-05-13 2021-06-10 2021-08-14 2022-02-10 our le ciblage, la contre verifi transfer program cation et le suivi des conditio nnalites CG-PL-SFS-SC/055 / Sous pre fecture Kintele Recrutement Strengthening the demand-s de la sous prefecture de kint IDA / 63690 ide of services through cash Post Direct Selection Direct 16,426.00 0.00 Under Review 2021-05-31 2021-05-13 2021-06-10 2021-08-14 2022-02-10 ele pour le ciblage, la contre transfer program verification et le suivi des co nditionnalites CG-PL-SFS-SC/056 / DDAS Br azzaville Recrutement de la Strengthening the demand-s Direction departementale de IDA / 63690 ide of services through cash Post Direct Selection Direct 43,366.00 0.00 Under Review 2021-05-31 2021-05-13 2021-06-10 2021-08-14 2022-02-10 s affaires sociales de Brazzav transfer program ille pour le ciblage, la contre verification et le suivi des co nditionnalites CG-PL-SFS-SC/057 / DDAS Po inte Noire Recrutement de la Strengthening the demand-s Sous prefecture de Pointe No IDA / 63690 ide of services through cash Post Direct Selection Direct 14,568.00 0.00 Under Review 2021-05-31 2021-05-13 2021-06-10 2021-08-14 2022-02-10 ire pour le ciblage, la contre transfer program verification et le suivi des co nditionnalites CG-PL-SFS-SC/083 / ADPH, C ontrat de prestation de form Establishment of key buildin ation qualifiante avec Agenc g blocks of a national safety e de Developpement et Prote IDA / 63690 Post Direct Selection Direct 6,334.00 0.00 Signed 2021-11-15 2021-03-22 2021-11-25 2021-05-03 2022-01-29 2022-07-28 net program and enhancem ction Humanitaire (ADPH) po ent of local capacities ur la formation de 45 jeunes en coupe-couture, soudure et apiculture Page 11 CG-PL-SFS-SCES/084 / CMI, Contrat de prestation de for Establishment of key buildin mation qualifiante avec Cent g blocks of a national safety IDA / 63690 Post Direct Selection Direct 6,334.00 0.00 Signed 2021-11-15 2021-03-22 2021-11-25 2021-05-03 2022-01-29 2022-07-28 re des Metiers industriels (C net program and enhancem MI) pour la formation qualifia ent of local capacities nte de 20 jeunes vulnérables en maçonnerie CG-PL-SFS-SCES/085 / ELIKIA , Contrat de prestation de for mation qualifiante avec le Ce Establishment of key buildin ntre d Apprentissage Catholi g blocks of a national safety IDA / 63690 Post Direct Selection Direct 14,253.00 15,422.50 Signed 2021-11-15 2021-04-01 2021-11-25 2021-05-03 2022-01-29 2021-05-12 2022-07-28 que ELIKIA pour la formation net program and enhancem qualifiante de 60 jeunes vuln ent of local capacities erables en coupe-couture (15 ), maçonnerie (15), menuiser ie (15) et maraichage (15) CG-PL-SFS-SCES/086 / MISER ICORDIEUX, Contrat de prest ation de formation qualifiant Establishment of key buildin e avec le Centre d Apprentiss g blocks of a national safety IDA / 63690 Post Direct Selection Direct 14,779.00 0.00 Signed 2021-11-15 2021-03-22 2021-11-25 2021-05-03 2022-01-29 2022-07-28 age Sainte Famille des Miseri net program and enhancem cordieux pour la formation q ent of local capacities ualifiante de 50 jeunes vulne rables en coupe-couture (20) , patisserie (15) et restaurati on (15) CG-PL-SFS-SC/111 / Centre d 'apprentissage catholique Lik Establishment of key buildin ouala Timber, Contrat de ser g blocks of a national safety IDA / 63690 Post Direct Selection Direct 43,123.00 0.00 Signed 2021-11-30 2021-03-22 2021-12-10 2021-05-03 2022-02-13 2022-08-12 vice de consultant avec le Ce net program and enhancem ntre d'apprentissage catholiq ent of local capacities ue Likouala Timber pour la fo rmation de 165 jeunes CG-PL-SFS-SC/140 / Contrat relatif a la collecte des donné Project management, Monito Pending Impleme es auprès des peuples autoc IDA / 63690 Post Direct Selection Direct - National 20,096.00 0.00 2023-01-10 2023-01-20 2023-03-26 2023-09-22 ring and Evaluation (M&E) ntation htones dans le cadre de l'éva luation de l'impact du projet Lisungi CG-PL-SFS-SC/142 / Contrat relatif au ciblage des ménag Strengthening the demand-s es réfugiés additionnels ayan IDA / 63690 ide of services through cash Post Direct Selection Direct - National 25,063.00 0.00 Signed 2023-05-08 2023-04-24 2023-05-18 2023-05-08 2023-07-22 2024-01-18 t déposé des plaintes à l'UGP transfer program pour erreur de ciblage CG-PL-SFS-SC/143 / Contrat relatif a la mission d encadre ment et d accompagnement Strengthening the demand-s de 1100 menages refugies s IDA / 63690 ide of services through cash Post Direct Selection Direct - National 75,820.00 0.00 Signed 2023-05-22 2023-05-20 2023-06-01 2023-05-22 2023-08-05 2024-02-01 electionnes a l issue du traite transfer program ment des plaintes dans le ca dre du Projet Lisungi System e de Filets Sociaux CG-PL-SFS-SC/144 / Recrute ment d un cabinet charge de Project management, Monito IDA / 63690 Post Direct Selection Direct - National 32,824.00 0.00 Under Review 2023-06-20 2023-06-21 2023-06-30 2023-09-03 2024-03-01 realiser l audit de cloture du ring and Evaluation (M&E) Projet Lisungi Systeme de Fil ets Sociaux CG-PL-SFS-SC/145 / Contrat entre l UGP et l Inspection ge Establishment of key buildin nerale de la sante relatif a l'e g blocks of a national safety valuation des prestations des IDA / 63690 Post Direct Selection Direct - National 19,849.00 0.00 Under Review 2023-06-22 2023-06-19 2023-07-02 2023-09-05 2024-03-03 net program and enhancem services de sante dans le cad ent of local capacities re de la mise en oeuvre du F BP dans le departement de la Likouala CG-PL-SFS-SC/146 / Contrat Strengthening the demand-s entre l UGP et la CAS de Beto IDA / 63690 ide of services through cash Post Direct Selection Direct - National 30,801.00 0.00 Under Review 2023-06-23 2023-06-19 2023-07-03 2023-09-06 2024-03-04 u relatif a la contre verificatio transfer program n et au suivi des conditionnal ites CG-PL-SFS-SC/147 / Contrat Strengthening the demand-s entre l UGP et la CAS de Don IDA / 63690 ide of services through cash Post Direct Selection Direct - National 9,405.00 0.00 Under Review 2023-06-22 2023-06-19 2023-07-02 2023-09-05 2024-03-03 gou relatif a la contre verifica transfer program tion et au suivi des condition nalites CG-PL-SFS-SC/148 / Contrat Strengthening the demand-s entre l UGP et la CAS de Eny IDA / 63690 ide of services through cash Post Direct Selection Direct - National 13,835.00 0.00 Under Review 2023-06-22 2023-06-19 2023-07-02 2023-09-05 2024-03-03 elle relatif a la contre verifica transfer program tion et au suivi des condition nalites CG-PL-SFS-SC/149 / Contrat Strengthening the demand-s entre l UGP et la CAS de Impf IDA / 63690 ide of services through cash Post Direct Selection Direct - National 3,818.00 0.00 Under Review 2023-06-22 2023-06-19 2023-07-02 2023-09-05 2024-03-03 ondo District relatif a la contr transfer program e verification et au suivi des conditionnalites CG-PL-SFS-SC/150 / Conrat e Strengthening the demand-s ntre l UGP et la CAS Impfond IDA / 63690 ide of services through cash Post Direct Selection Direct - National 3,520.00 0.00 Under Review 2023-06-22 2023-06-19 2023-07-02 2023-09-05 2024-03-03 o Urbain relatif a la contre ve transfer program rification et au suivi des cond itionnalites CG-PL-SFS-SC/151 / Contrat Strengthening the demand-s entre l UGP tet la DDAS Likou IDA / 63690 ide of services through cash Post Direct Selection Direct - National 29,542.00 0.00 Under Review 2023-06-22 2023-06-19 2023-07-02 2023-09-05 2024-03-03 ala relatif a la contre verificat transfer program ion et le suivi des conditionn alites CG-PL-SFS-SC/152 / Contrat Strengthening the demand-s entre l UGP et la CAS de Igni IDA / 63690 ide of services through cash Post Direct Selection Direct - National 4,510.00 0.00 Under Review 2023-06-22 2023-06-19 2023-07-02 2023-09-05 2024-03-03 e relatif a la contre verificatio transfer program n et au suivi des conditionnal ites CG-PL-SFS-SC/153 / Contrat Strengthening the demand-s entre l UGP et la CAS de Kint IDA / 63690 ide of services through cash Post Direct Selection Direct - National 2,947.00 0.00 Under Review 2023-06-22 2023-06-19 2023-07-02 2023-09-05 2024-03-03 ele relatif a la contre verificat transfer program ion et au suivi des conditionn alites Page 12 Strengthening Pedagogy and Governance (P176105) Requesting Unit: LCC7C, Responsible Unit: HLCED/LCRVP Lending Instrument: Investment Project Financing Net commitment: 40 M PROCUREMENT Uruguay : Strengthening Pedagogy and Governance in Uruguayan Public Schools Project PLAN General Information Country: Uruguay 2022-08-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176105 GPN Date: 2022-07-13 Project Name: Strengthening Pedagogy and Governance in Uruguayan Public Schools Project Loan / Credit No: IBRD / 93310 National administration of Public Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ESCUELA 114 RIVERA 30614 3-CW-RFB 2022 / Escuela qui Component 3: Improving Infr Request for Quota ntil 2. Construcción de 3 aula Single Stage - One E Under Imple 2024-03-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National tions (Non Bank-S 1,200,000.00 0.00 2022-09-01 2023-01-27 2022-09-01 2022-10-01 2022-10-31 2023-03-31 s, rehabilitación de 6 aulas, c nvelope mentation 1 ary Services PD) omedor, cocina, dirección y s shh en la Escuela 114 Depart amento de Rivera ESCUELA 2 RÍO NEGRO -306 144-CW-RFB 2022 / Escuela Component 3: Improving Infr Request for Quota quintil 2. Ampliación de 1 aul Single Stage - One E Under Imple 2024-03-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National tions (Non Bank-S 1,500,000.00 0.00 2022-11-01 2022-11-28 2022-11-01 2022-12-01 2022-12-28 2022-12-31 2023-01-20 2023-05-02 a, rehabilitación de 5 aulas, c nvelope mentation 1 ary Services PD) omedor, cocina, dirección y s shh en la Escuela 2 Departa mento de Río Negro ESCUELA 301 CANELONES-3 06147-CW-RFB 2022 / Escuel Component 3: Improving Infr Request for Quota Single Stage - One E Under Imple 2023-10-3 a quintil 2. Ampliación 7 aula IBRD / 93310 astructure and Complement Post Request for Bids Open - National tions (Non Bank-S 750,000.00 0.00 2022-11-01 2022-11-28 2022-11-01 2022-12-01 2022-12-28 2022-12-31 2023-01-20 2023-05-02 nvelope mentation 1 s en la Escuela 301 de la loca ary Services PD) lidad de Marindia, Departam ento de Canelones ESCUELA 68 DURAZNO 3061 49-CW-RFB 2022 / Escuela q National Procure uintil 2. Ampliación de 3 aula Component 3: Improving Infr ment Document - Single Stage - One E Pending Imp 2024-06-3 s, comedor, cocina y rehabilit IBRD / 93310 astructure and Complement Post Request for Bids Open - National 1 Envelope proce 1,500,000.00 0.00 2023-03-01 2023-03-01 2023-03-31 2023-04-30 2023-09-01 nvelope lementation 0 ación de 6 aulas, dirección y ary Services ss (Non Bank-SPD sala de maestros en la Escue ) la 68 del Departamento de D urazno PBC ESC 4 MTDEO-305968-C W-RFQ / Mantenimiento corre Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-02-0 ctivo - pavimentos en aula y IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 62,000.00 0.00 Signed 2022-09-10 2022-11-15 tions nvelope 3 reforma aula en Planta Alta. ary Services PD) Escuela n° 4 de Mdeo. PBC ESC. 183 MDEO-2023- 3 Component 3: Improving Infr Request for Quota 05971-CW-RFQ / Mantenimie Request for Quota Single Stage - One E Pending Imp 2023-08-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 15,000.00 0.00 2023-06-06 2023-07-07 nto correctivo - Conexión ga tions nvelope lementation 1 ary Services PD) s por cañería en la escuela n ° 183 de Montevideo. PBC ESC 29 ROCHA-305966- Component 3: Improving Infr Request for Quota CW-RFQ / Mantenimiento cor Request for Quota Single Stage - One E 2023-03-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 171,000.00 0.00 Signed 2022-09-12 2022-12-18 rectivo Ampliación para aloja tions nvelope 4 ary Services PD) r aulas inicial en la escuela n ° 29 de Rocha. PBC ESC 88 RIVERA -305970 Component 3: Improving Infr Request for Quota -CW-RFQ / Mantenimiento cor Request for Quota Single Stage - One E 2023-04-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 150,000.00 0.00 Signed 2022-09-09 2022-12-11 rectivo. Reforma baño, const tions nvelope 7 ary Services PD) rucción de rampa y muro en Esc. 88 Rivera PBC ESC. 20 MONTEVIDEO- 305973-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-12-0 ento correctivo. Adecuación i IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 150,000.00 0.00 2023-05-07 2023-08-04 tions nvelope lementation 4 nstalación eléctrica en la esc ary Services PD) uela n° 20 de Montevideo. PBC ESC. 53 MONTEVIDEO- 305943-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-05-2 ento correctivo - Reparación IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 25,000.00 0.00 2023-03-07 2023-04-08 tions nvelope lementation 6 filtraciones en cocina y aulas ary Services PD) . Escuela n° 53 de Montevide o. PBC ESC. 371 MDEO-2023- 3 Component 3: Improving Infr Request for Quota 05983-CW-RFQ / Mantenimie Request for Quota Single Stage - One E Pending Imp 2024-01-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 122,000.00 0.00 2023-06-09 2023-09-05 nto Correctivo.Ampliación co tions nvelope lementation 3 ary Services PD) cina, escuela n° 371 de Mont evideo. PBC ESC. 42 MALDONADO 3 05981-CW-RFQ / Mantenimie Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-12-2 nto correctivo - Ampliación d IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 244,000.00 0.00 2023-05-08 2023-08-20 tions nvelope lementation 9 e cocina y comedor en la esc ary Services PD) uela n° 42 de Maldonado. PBC ESC. 126 COLONIA 3059 Component 3: Improving Infr Request for Quota 67-CW-RFQ / Mantenimiento Request for Quota Single Stage - One E Pending Imp 2023-04-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 170,000.00 0.00 2022-10-07 2023-01-11 correctivo. Adecuación del sa tions nvelope lementation 5 ary Services PD) neamiento. Escuela n° 126 d e Colonia. PBC ESC. 75 ROCHA -30595 Component 3: Improving Infr Request for Quota 4-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E Pending Imp 2023-01-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 86,000.00 0.00 2022-09-06 2022-11-15 orrectivo Reparación parcial tions nvelope lementation 6 ary Services PD) de filtraciones en la escuela n° 75 de Rocha. PBC ESC. 72 ROCHA- 30595 2-CW-RFQ / Mantenimiento c Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-1 orrectivo . Impermeabilizació IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 32,000.00 0.00 2023-06-09 2023-08-22 tions nvelope lementation 7 n de cubiertas y pintura en la ary Services PD) escuela n° 72 de Rocha PBC ESC. 156 CANELONES- 305960-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-03-3 ento correctivo Adecuación IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 10,000.00 0.00 Signed 2023-02-07 2023-03-12 tions nvelope 1 de la Instalación Sanitaria - R ary Services PD) ed primaria . Escuela n° 156 de Canelones Page 1 PBC ESC. 24 RIVERA 305994 -CW-RFQ / Mantenimiento cor Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-03-2 rectivo. Sustitución de pisos IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 49,000.00 0.00 Signed 2022-11-11 2023-02-07 tions nvelope 0 en aulas prefabricadas. Escu ary Services PD) ela n° 24 de Vichadero - Rive ra. PBC ESC. 9 COLONIA -30596 Component 3: Improving Infr Request for Quota 2-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E Pending Imp 2023-11-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 122,000.00 0.00 2023-04-07 2023-07-02 orrectivo -. Saneamiento y re tions nvelope lementation 5 ary Services PD) forma de cocina en la escuel a n° 9 de Colonia. PBC ESC 278 CANELONES 30 Component 3: Improving Infr Request for Quota 5949-CW-RFQ / Mantenimien Request for Quota Single Stage - One E Pending Imp 2023-02-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 110,000.00 0.00 2022-09-13 2022-12-02 to correctivo. Impermeabiliza tions nvelope lementation 5 ary Services PD) ción azotea, Esc. 278 El Dora do, Canelones PBC ESC. 80 TACUAREMBÓ- Component 3: Improving Infr Request for Quota 305958-CW-RFQ / Mantenimi Request for Quota Single Stage - One E Pending Imp 2023-10-0 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 100,000.00 0.00 2023-03-06 2023-06-09 ento correctivo. Sustitución d tions nvelope lementation 2 ary Services PD) e techos en la escuela n° 80 de Tacuarembo. PBC ESC 183 MTDEO- 2022- 305959-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota ento correctivo. Impermeabili Request for Quota Single Stage - One E Pending Imp 2022-12-3 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 61,000.00 0.00 2022-09-19 2022-11-25 zación de Tanque , adecuaci tions nvelope lementation 0 ary Services PD) ón sistema bombeo y tanque inferiores, reparación dintele s- Escuela n° 183 de Montevi deo. PBC ESC 112 CERRO LARGO -305957-CW-RFQ / Mantenim Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2022-12-0 iento correctivo - Adecuació IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 37,000.00 0.00 Signed 2022-09-06 2022-10-04 tions nvelope 2 n cubierta , Impermeabilizac ary Services PD) ión . Esc. 112, Melo, Cerro La rgo PBC ESC 285 CANELONES-3 05982-CW-RFQ / Mantenimie Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-11-1 nto correctivo - Reparación IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 24,500.00 0.00 2022-09-12 2022-10-11 tions nvelope lementation 1 muros de contención, escuel ary Services PD) a n° 285, Toledo, Canelones PBC ESC 27 FLORES--30598 Component 3: Improving Infr Request for Quota 6-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E 2022-10-3 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 24,500.00 0.00 Signed 2022-09-08 2022-09-23 orrectivo. Acondicionamiento tions nvelope 1 ary Services PD) de Salón en la escuela n° 27 de Trinidad, Flores PBC ESC.359 Y 361 DE MDE O- 305956-CW-RFQ / Manteni miento correctivo. Imperme Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E 2023-01-1 abilización techo en la escuel IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 60,000.00 0.00 Signed 2022-09-06 2022-11-18 tions nvelope 8 a n° 359 de Montevideo e im ary Services PD) permeabiización por filtracio nes cañería abastecimiento e n la escuela n° 361 PBC ESC 14 PAY 3 RIO NEGR O 305946-CW-RFQ / Manteni miento correctivo. .- Repara Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Under Imple 2023-04-0 ción cubierta liviana en escu IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 12,500.00 0.00 2023-02-07 2023-03-12 tions nvelope mentation 9 ela n° 14 de Paysandu. y rep ary Services PD) aración techo cocina e imper meabilización en la escuela 3 de Rio Negro. PBC ESC. 87 CERRO LARGO- 305961-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-06-0 ento correctivo. Refacción In IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 25,000.00 0.00 2023-04-07 2023-05-02 tions nvelope lementation 2 stalación Sanitaria, desagüe ary Services PD) s de primaria. Escuela n° 87 de Cerro Largo PBC ESC 213/186 CANELONE S 312896-CW-RFQ / Manteni miento correctivo . Escuela 2 Component 3: Improving Infr Request for Quota 13 Jardines de Pando: trabajo Request for Quota Single Stage - One E Pending Imp 2024-02-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 180,000.00 0.00 2023-09-02 2023-12-15 s en la fosa séptica - pozo b tions nvelope lementation 3 ary Services PD) ombeo y en la Escuela 186 P arque del Plata: trabajos en l a Red Primaria - nivelación te rreno, portón con entrada ve hículos PBC ESC 6 SORIANO 312900 -CW-RFQ / Mantenimiento cor Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2024-03-0 rectivo Escuela 6 Soriano por IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 150,000.00 0.00 2023-09-02 2023-11-30 tions nvelope lementation 4 trabajos tratamiento más em ary Services PD) isor hacia curso de agua PBC ESC 268 PINAR 312907- Component 3: Improving Infr Request for Quota CW-RFQ / Mantenimiento cor Request for Quota Single Stage - One E Pending Imp 2024-02-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 180,000.00 0.00 2023-09-02 2023-12-22 rectivo Escuela 268 Pinar Nor tions nvelope lementation 0 ary Services PD) te, Canelones: trabajos en la planta tratamiento PBC ESC 100 SAN JOSE 3129 Component 3: Improving Infr Request for Quota 09-CW-RFQ / Mantenimiento Request for Quota Single Stage - One E Pending Imp 2023-11-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 15,000.00 0.00 2023-09-02 2023-10-01 correctivo Escuela 100 de Sa tions nvelope lementation 4 ary Services PD) n José re ejecución de muro medianero PBC ESC 74 ROCHA -312911 -CW-RFQ / Mantenimiento cor Component 3: Improving Infr Request for Quota rectivo Esc 74 Chuy, Rocha. Request for Quota Single Stage - One E Pending Imp 2023-05-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 245,000.00 0.00 2022-09-02 2022-11-28 Reacondicionamiento y refac tions nvelope lementation 9 ary Services PD) ción de 2 aulas, SSHH, despe nsa cocina, depósito, ilumina ción y pintura. PBC ESC.153 MONTEVIDEO- 305978-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota ento correctivo.. Ajuste eléctr Request for Quota Single Stage - One E Pending Imp 2023-03-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 4,000.00 0.00 2023-02-07 2023-03-10 ica cocina, comedor y dos au tions nvelope lementation 7 ary Services PD) las e iluminación exterior en el local de la escuela n° 153 de Montevideo PBC ESC. 291 CANELONES-3 43143-CW-RFQ / Mantenimie nto correctivo. Retiro de equi Component 3: Improving Infr Request for Quota pamiento y luminarias. Demo Request for Quota Single Stage - One E 2023-03-2 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 5,300.00 0.00 Signed 2023-02-24 2023-03-17 lición revoques fondo losa y li tions nvelope 7 ary Services PD) mpieza. Re colocación lumin arias y equipamiento en el lo cal de la Escuela N° 291 de C anelones Page 2 ESC.36 PINTADO-350338-C Component 3: Improving Infr Request for Quota W-RFQ / Obras de Conexión d Request for Quota Single Stage - One E 2023-04-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 3,800.00 0.00 Signed 2023-03-22 2023-03-31 e aulas pre fabricadas e insta tions nvelope 0 ary Services PD) lación de iluminación exterior . Escuela Quintil 1. Request for Quota PBC OBRA ESC. 98 SORIANO Component 3: Improving Infr tions - Small Work 351478-CW-DIR / Reparación Pending Imp 2023-06-1 IBRD / 93310 astructure and Complement Post Direct Selection Direct - National s (Emergency) SP 6,000.00 0.00 2023-03-26 2023-03-31 2023-05-22 de canalón sobre fachada de lementation 1 ary Services D -Non Competiti Escuela N° 98 de Soriano ve National Procure OBRA ESC 190 MTDEO -351 Component 3: Improving Infr ment Document - 489-CW-RFB / Obra Nueva (c Single Stage - One E Pending Imp 2025-05-2 IBRD / 93310 astructure and Complement Post Request for Bids Open - National 1 Envelope proce 2,350,000.00 0.00 2023-10-23 2023-10-23 2023-11-22 2023-12-22 2024-05-21 omedor, 2 aulas y cocina) y nvelope lementation 1 ary Services ss (Non Bank-SPD Reciclaje (9 aulas, administra ) ción y SSHH) PBC- ESC 113 MDEO -35795 Component 3: Improving Infr Request for Quota 9-CW-RFQ / Mantenimiento c Request for Quota Single Stage - One E 2023-05-1 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 6,000.00 0.00 Signed 2023-04-26 2023-05-11 orrectivo - Obras en la Escuel tions nvelope 9 ary Services PD) a n° 113 de Mdeo , abasteci miento de agua. OBRAS ESC 317 MDEO -358 384-CW-RFQ / OBRAS DE MA Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-05-1 NTENIMIENTO INSTALACIÓN IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 3,800.00 0.00 2023-05-03 2023-05-15 tions nvelope lementation 9 DE GAS EN LA ESCUELA 317 ary Services PD) DE MONTEVIDEO- ESCUELA QUINTIL 1 PBC ESC. 186 CANELONES-3 59767-CW-RFQ / Mantenimie Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-07-1 nto Correctivo Esc. 186 Parq IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 5,000.00 0.00 2023-05-09 2023-05-21 tions nvelope lementation 9 ue del Plata, Canelones. Trab ary Services PD) ajos Instalacion Electrica National Procure OBRA ESC. 9 MDEO.-361867 Component 3: Improving Infr ment Document - -CW-RFB / Obra de rehabilita Single Stage - One E Pending Imp 2023-06-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National 1 Envelope proce 1,300,000.00 0.00 2021-06-22 2021-06-27 2021-08-08 2021-09-07 2021-10-12 ción en Escuela 9 La Teja, De nvelope lementation 0 ary Services ss (Non Bank-SPD partamento de Montevideo ) SO ESC 6 TACUAREMBO-361 Component 3: Improving Infr Request for Bids - 872-CW-RFB / Obras de refac Single Stage - One E Pending Imp 2023-06-3 IBRD / 93310 astructure and Complement Post Request for Bids Open - National Works SPD (after 1,500,000.00 0.00 2021-10-20 2021-10-25 2021-12-06 2022-01-05 2022-02-09 ción y ampliación en la Escue nvelope lementation 0 ary Services prequalification) la 6 Departamento de Tacuar embó PBC OBRA ESC. 292 MDEO. 363682-CW-RFQ / Obra en Es Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-09-0 cuela N° 292 de Montevideo. IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 38,000.00 0.00 2023-06-04 2023-08-03 tions nvelope lementation 7 Impermeabilización tanque s ary Services PD) uperior, suministro tanque in ferior y bomba. PBC OBRA ESC. 187 CANEL. Component 3: Improving Infr Request for Quota - 363685-CW-RFQ / Obra Esc Request for Quota Single Stage - One E Pending Imp 2023-08-3 IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 25,000.00 0.00 2023-06-07 2023-08-06 uela N° 187 de Canelones Im tions nvelope lementation 1 ary Services PD) permeabilización tanque de agua. PBC OBRA ESC.108 CANELO NES 368083-CW-RFQ / Mante Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-07-2 nimiento Correctivo, obra res IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 6,000.00 0.00 2023-06-28 2023-07-12 tions nvelope lementation 1 paldo PBC - Esc. 108 de Can ary Services PD) elones. Tanque bombeo para cocina PBC OBRA ESC. 327 MDEO.- 368224-CW-RFQ / Mantenimi Component 3: Improving Infr Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-10-2 ento correctivo Esc. 327 de IBRD / 93310 astructure and Complement Post Open - National tions (Non Bank-S 38,000.00 0.00 2023-06-28 2023-09-04 tions nvelope lementation 1 Montevideo. Recomposición ary Services PD) de revoques de cielorrasos y jardineras. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOB. DIR. Y MAESTROS 306 885-GO-RFB / Adquisición de mobiliario para docentes. Esc Component 3: Improving Infr Single Stage - One E Pending Impl ritorios y sillas para maestros IBRD / 93310 astructure and Complement Post Request for Bids Open - National 81,000.00 0.00 2022-10-07 2022-10-12 2022-11-11 2022-11-25 2023-02-17 2023-05-19 nvelope ementation y directores de escuelas de T ary Services iempo Completo , mesas par a sala de reuniones y bibliote cas. MOBILIARIO ESCOLAR 30665 9-GO-RFB / Adquisición de m Component 3: Improving Infr Single Stage - One E esas y sillas para aulas de ed IBRD / 93310 astructure and Complement Post Request for Bids Open - National 430,580.00 0.00 Signed 2023-02-13 2022-11-29 2023-02-18 2023-03-20 2022-12-28 2023-04-03 2023-01-20 2023-06-26 2023-10-24 nvelope ucación inicial y primaria, en ary Services Escuelas de Tiempo Complet o. VAJILLA Y ALUMINIO 306661- Component 3: Improving Infr GO-RFB / Adquisición de vajill Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Request for Bids Open - National 68,000.00 0.00 2023-05-08 2023-05-10 2023-06-05 2023-06-19 2023-09-08 2024-01-07 a para comedores escolares nvelope ementation ary Services y equipamiento de menage p ara cocinas de ETC. ELECTRODOMÉSTICOS 3066 Component 3: Improving Infr 66-GO-RFB / Adquisición de h Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Request for Bids Open - National 87,500.00 0.00 2023-04-03 2023-04-05 2023-05-02 2023-05-16 2023-07-31 2023-10-02 eladeras, freezers, licuadoras nvelope ementation ary Services , batidoras para ETC EQUIP. SEMI INDUSTRIAL 30 Component 3: Improving Infr 6667-GO-RFQ / Adquisición d Request for Quota Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Open - National 24,300.00 0.00 2023-04-05 2023-05-15 2023-07-15 e equipamiento semi industri tions nvelope ementation ary Services al cocinas, hornos y anafes, P ara ETC CORTINAS PARA ETC UY-ANE P-321164-GO-RFB / Confecci Component 3: Improving Infr Single Stage - One E ón y colocación de cortinas c IBRD / 93310 astructure and Complement Post Request for Bids Open - National 112,000.00 0.00 Signed 2022-11-04 2022-12-14 2022-11-07 2022-12-02 2022-12-14 2022-12-09 2022-12-29 2023-02-13 2024-12-31 nvelope on barrotes o rieles en Escuel ary Services as de Tiempo Completo LIBROS COLECC. ANDARIEG A 343436-GO-RFQ / Libros pa Component 3: Improving Infr Request for Quota Single Stage - One E Under Imple ra biblioteca de colección an IBRD / 93310 astructure and Complement Post Open - National 2,400.00 0.00 2023-03-06 2023-03-21 2023-04-02 tions nvelope mentation dariega, creación de espacio ary Services lúdico recreativo en escuela N° 6 de Tacuarembó Page 3 EQUIP AUDIVISUALES DSPE- Component 1: Improving Te Request for Quota Single Stage - One E Under Imple 347492-GO-RFQ / Equipamie IBRD / 93310 acher Training and Pedagogi Post Open - National 8,500.00 0.00 2023-03-13 2023-04-19 2023-07-19 tions nvelope mentation nto Audiovisual para streami cal Content ng para la DSPE LIC. ZOOM EDUCATIVO 2023 -357617-GO-DIR / Renovació Component 4: Strengthening n de 23 licencias de Zoom Ed Under Imple IBRD / 93310 Evaluation Systems and Proj Post Direct Selection Direct - National 2,525.00 0.00 2023-04-23 2023-04-25 2023-04-23 2023-04-25 2023-05-23 2024-05-23 ucativo que permitan cumplir mentation ect Management con la planificación de los cur sos de Formación en servicio para el 2023 EQUIP. AUDIOVISUAL 30668 Component 3: Improving Infr 2-GO-RFQ / Adquisición de eq Request for Quota Single Stage - One E Under Imple IBRD / 93310 astructure and Complement Post Open - National 15,000.00 0.00 2023-04-28 2023-05-22 2023-08-21 uip. audiovisual. parlantes, p tions nvelope mentation ary Services royectores, para Escuelas de Tiempo Completo. DSPE EQUIP. SALA STREAMI NG 361828-GO-RFQ / Nuevo Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl Solicitud de Cotización para l IBRD / 93310 acher Training and Pedagogi Post Open - National 6,250.00 0.00 2023-05-23 2023-06-26 2023-09-25 tions nvelope ementation a compra de equipamiento a cal Content udiovisual para sala de strea ming para la DSPE. PIZARRAS MÓVILES PARA ET Component 3: Improving Infr Single Stage - One E Pending Impl C 363486-GO-RFB / Adquisici IBRD / 93310 astructure and Complement Post Request for Bids Open - National 80,000.00 0.00 2023-06-01 2023-06-06 2023-06-18 2023-06-22 2023-08-21 2023-11-19 nvelope ementation ón de pizarrones móviles par ary Services a ETC EQUIP PSICOMOTRICIDAD-36 3524-GO-RFB / Adquisición M Component 3: Improving Infr aterial didáctico para salas d Single Stage - One E Pending Impl IBRD / 93310 astructure and Complement Post Request for Bids Open - National 85,280.00 0.00 2023-05-29 2023-05-30 2023-06-14 2023-06-23 2023-08-28 2023-11-27 e psicomotricidad, juego y m nvelope ementation ary Services ovimientos. Se equipara apro ximadamente 40 escuelas . MOBILIARIO 10 Y 11 AÑOS-3 66129-GO-RFB / Adquisición Component 3: Improving Infr Single Stage - One E Pending Impl de sillas y mesas educación IBRD / 93310 astructure and Complement Post Request for Bids Open - National 240,000.00 0.00 2023-06-14 2023-06-15 2023-07-17 2023-07-21 2023-10-02 2023-12-29 nvelope ementation primaria de 10 y 11 años par ary Services a Escuelas de Tiempo Compl eto LIBROS C.ANDARIEGA - 3683 03-GO-RFQ / Adquisicion Libr os Coleccion Andariega para Component 3: Improving Infr Request for Quota Single Stage - One E Pending Impl las Esc. 9 y 190 de Montevi IBRD / 93310 astructure and Complement Post Open - National 5,200.00 0.00 2023-07-03 2023-07-20 2023-08-31 tions nvelope ementation deo , Esc 5 de Cerro Largo y ary Services completar libros que quedaro n desierto en llamado ID 343 436 (Esc. 6 de Tacuarembó) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONGRESO CEIBAL 2023-30 6197-NC-RFQ / Congreso CEI Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl BAL, Noviembre 2023. 200 p IBRD / 93310 acher Training and Pedagogi Post Open - National 24,000.00 0.00 2023-08-13 2023-09-23 2023-11-13 tions nvelope ementation articipantes por día, (Alojami cal Content ento, cena, almuerzo y 2 coff ee break) JORN. FORM. INSP.2023 DSP E 306198-NC-RFQ / Jornada d e formación para inspectores de la Dir. Sec. de Planificació Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl IBRD / 93310 Post Open - National 18,000.00 0.00 2023-07-28 2023-09-01 2023-10-26 n Educ. 7 sedes: Salto, Coloni Management Teams tions nvelope ementation a, Durazno, Maldonado, Cane lones y 2 en Montevideo. dos encuentros en set y nov de 2 023 alojamiento y alimentaci ón IMPRESION LIBRO FS 2022-3 Component 1: Improving Te 06368-NC-RFQ / PAEPU - Imp Request for Quota Single Stage - One E Pending Impl IBRD / 93310 acher Training and Pedagogi Post Open - National 5,900.00 0.00 2023-03-11 2023-04-28 2023-05-29 resión Libro "Formación en S tions nvelope ementation cal Content ervicio 2022", 2000 ejemplar es FORM.Y COORD 2023- PAEP U -306375-NC-RFQ / Jornada Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl de Formadores y Coordinado IBRD / 93310 acher Training and Pedagogi Post Open - National 2,900.00 0.00 2023-06-09 2023-10-02 2023-11-22 tions nvelope ementation res 2023, 2 dias, 180 particip cal Content antes (Desayuno y coffee Bre ak) SEMINARIO 2023- PAEPU-30 Component 1: Improving Te 6376-NC-RFQ / Seminario Do Request for Quota Single Stage - One E Pending Impl IBRD / 93310 acher Training and Pedagogi Post Open - National 42,200.00 0.00 2023-08-07 2023-10-27 2023-11-27 centes 2023. Dos dias, 260 p tions nvelope ementation cal Content articipantes (Alojamiento, ali mentación y sala) JORNADA TUTORES 2023- D SPE-307160-NC-RFQ / Jornad Component 2: Strengthening Request for Quota Single Stage - One E a con Tutores de la Dirección IBRD / 93310 Post Open - National 2,000.00 0.00 Signed 2023-08-20 2023-09-09 2023-10-30 Management Teams tions nvelope Sectorial de Planificación Edu cativa 60 participantes. Alim entación INSPEC Y DIRECT 2023-PAEP U-306373-NC-RFQ / Jornada d Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl e Inspectores y Directores 20 IBRD / 93310 Post Open - National 2,300.00 0.00 2023-07-08 2023-08-18 2023-10-08 Management Teams tions nvelope ementation 23, un dia, 55 participantes ( desayuno, coffee break, alm uerzo y sala) DSPE IMPRESION LIB 306899 -GO-RFQ 2023 / Impresión lib Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl rillos para Inspectores y Dire IBRD / 93310 Post Open - National 10,000.00 0.00 2023-08-09 2023-09-05 2023-10-05 Management Teams tions nvelope ementation ctores solicitados por la Direc ción Sectorial de Planificació n Estratégica DSPE JORNADA MENTORES - 335388-NC-RFQ / Jornada a r Component 2: Strengthening Request for Quota Single Stage - One E Under Imple ealizarse en 2 instancias de 3 IBRD / 93310 Post Open - National 30,500.00 0.00 2023-01-13 2023-01-26 2023-03-03 Management Teams tions nvelope mentation días. 150 participantes por d ia. Alojamiento, alimentación y traslados. DSPE JORNADA INSP. ZONA 335389-NC-RFQ / Jornada de Inspectores de zona de la DG Component 2: Strengthening Request for Quota Single Stage - One E Under Imple IBRD / 93310 Post Open - National 10,500.00 0.00 2023-01-13 2023-01-26 2023-02-09 EIP a realizarse el 9 de febrer Management Teams tions nvelope mentation o de 2023. 260 participantes. Alojamiento, Alimentación y t raslado Page 4 DSPE JORNADA INSP/MENTO RES 343442-NC-RFQ / Alimen Component 2: Strengthening Pending Impl tación y hospedaje para insp IBRD / 93310 Post Direct Selection Direct - National 2,800.00 0.00 2023-02-17 2023-02-17 2023-03-01 2023-03-03 Management Teams ementation ectores participantes en la Jo rnada de Mentores del 3 de marzo de 2023 EDICIÓN LIBRO F.S. 2022 - 3 Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl 47804-NC-RFQ / Edición de li IBRD / 93310 acher Training and Pedagogi Post Open - National 2,000.00 0.00 2023-03-24 2023-05-07 2023-07-06 tions nvelope ementation bro "Formación en servicio 2 cal Content 022- PAEPU " IMPRESIÓN LIBRO 349293-N Component 1: Improving Te C-DIR / Impresión de 500 eje Pending Impl IBRD / 93310 acher Training and Pedagogi Post Direct Selection Direct - National 2,800.00 0.00 2023-03-20 2023-03-21 2023-03-28 2023-04-27 mplares del libro "Un camino ementation cal Content recorrido y nuevas expectati vas". JORNADA TRANSF CURRICUL AR-363702-NC-RFQ / Encuent Component 1: Improving Te Request for Quota Single Stage - One E Pending Impl ro en territorio. jornada Tran IBRD / 93310 acher Training and Pedagogi Post Open - National 2,500.00 0.00 2023-06-01 2023-06-13 2023-06-30 tions nvelope ementation sformación Curricular- Logísti cal Content ca necesaria para dicha Jorna da. DSPE JORNADA FORM INSP. 365048-NC-RFQ / Primera edi ción del curso correspondient Component 2: Strengthening Request for Quota Single Stage - One E Pending Impl e al Programa de formación e IBRD / 93310 Post Open - National 12,500.00 0.00 2023-06-08 2023-06-20 2023-06-30 Management Teams tions nvelope ementation n gestión para Inspectores d e la ANEP (2023 - 2024).. Ser vicio de Alimentación y aloja miento para 300 participante s. DIEE IMPLE.O. T. CURRICULA 368081-NC-RFQ / Contratació n de Empresa consultora par Component 4: Strengthening Request for Quota Single Stage - One E a realizar grupos de discusió IBRD / 93310 Evaluation Systems and Proj Post Open - National 18,300.00 0.00 Canceled 2023-07-03 2023-08-04 2023-12-29 tions nvelope n con docentes de la ANEP e ect Management n el marco de las actividades del Observatorio de la Transf ormación Curricular Integral. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DIEE-IMPLEMENTACIÓN. OTI -368967-CS-FBS / CONTRATA CIÓN DE UNA CONSULTORÍA Component 4: Strengthening PARA REALIZAR GRUPOS DE Fixed Budget Sele Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Open - National 18,300.00 0.00 2023-06-26 2023-06-28 2023-07-05 2023-07-11 2023-07-24 2023-07-28 2023-08-30 2024-10-31 DISCUSIÓN CON DOCENTES ction ntation ect Management DE LA ANEP EN EL MARCO D E LAS ACTIVIDADES DEL OBS ERVATORIO DE LA TRANSFO RMACIÓN CURRICULAR INTE GRAL INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AGRIM. 68 DURAZNO -30616 Component 3: Improving Infr 8-CS-INDV 2022 / Consultoría Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 1,500.00 0.00 2022-08-10 2022-08-16 2022-08-20 2022-10-01 2022-11-01 Agrimensura para la Escuela ant Selection ation ary Services 68 Departamento de Durazn o CIVIL ESC 68 DURAZNO 306 Component 3: Improving Infr 215-CS-INDV 2022 / Consulto Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 6,000.00 0.00 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 ría Proyecto de Estructura pa ant Selection ation ary Services ra la Escuela 68 Departamen to de Durazno ELECT ESC 68 DURAZNO 30 Component 3: Improving Infr 6216-CS-INDV 2022 / Consult Individual Consult IBRD / 93310 astructure and Complement Post Limited 5,000.00 0.00 Canceled 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 oría Eléctrica para la Escuela ant Selection ary Services 68 Departamento de Durazn o METRAJE 68 DURAZNO 3062 Component 3: Improving Infr 17-CS-INDV 2022 / Consultorí Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 2,500.00 0.00 2022-12-11 2022-12-17 2022-12-21 2023-02-01 2023-03-03 a Metraje para la Escuela 68 ant Selection ation ary Services Departamento de Durazno SANITAR 68 DURAZNO -306 Component 3: Improving Infr 221-CS-INDV 2022 / Consulto Individual Consult IBRD / 93310 astructure and Complement Post Limited 3,500.00 0.00 Canceled 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 ría Sanitaria para la Escuela ant Selection ary Services 68 Departamento de Durazn o BOMBEROS 68 DURAZNO 30 Component 3: Improving Infr 6223-CS-INDV 2022 / Consult Individual Consult Under Implement IBRD / 93310 astructure and Complement Post Limited 2,500.00 0.00 2022-11-11 2022-11-17 2022-11-21 2023-01-02 2023-02-01 oría Bomberos para la Escuel ant Selection ation ary Services a 68 Departamento de Duraz no CIVIL 301 CANELONES 3062 Component 3: Improving Infr 24-CS-INDV 2022 / Consultorí Individual Consult IBRD / 93310 astructure and Complement Post Limited 3,000.00 0.00 Canceled 2022-08-10 2022-08-16 2022-08-20 2022-10-01 2022-10-31 a Poyecto Esctructura para la ant Selection ary Services Escuela 301 Departamento d e Canelones METRAJ 301 CANELONES 30 Component 3: Improving Infr 6225-CS-INDV 2022 / Consult Individual Consult IBRD / 93310 astructure and Complement Post Limited 1,500.00 0.00 Canceled 2022-08-10 2022-08-16 2022-08-20 2022-10-01 2022-10-31 oría Metraje para la Escuela ant Selection ary Services 301 Departamento de Canelo nes CIVIL ESC 42 AIGUA 306230- Component 3: Improving Infr CS-INDV 2022 / Consultoría P Individual Consult Pending Impleme IBRD / 93310 astructure and Complement Post Limited 4,000.00 0.00 2022-12-11 2022-12-17 2022-12-21 2023-02-01 2023-03-03 royecto Estructura para la Es ant Selection ntation ary Services cuela 42 Aiguá, Departament o de Maldonado UEP EXPERTO TECNICO OBR Component 4: Strengthening AS-305386-CS-INDV / Contrat Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 acion de un Experto Técnico ant Selection ation ect Management 40hrs Area Obras del 1/1/23 al 30/6/27 UEP EXP. B AREA PROYECTO Component 4: Strengthening Individual Consult Under Implement S-305353-CS-INDV / Contrata IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ción de 1 Experto "B" 40 hrs ect Management - Área Proyecto Page 5 UEP EXP TEC PLANIFICACION Component 4: Strengthening -305371-CS-INDV / Contratac Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ión -de un Experto Técnico 4 ant Selection ation ect Management 0 hrs Planificación Planta Físi ca del 1/1/23 al 30/6/27 UEP EXPERTO B - OBRAS 30 Component 4: Strengthening 5389-CS-INDV / Contratación Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 de 1 Experto "B" 40 hrs Obra ant Selection ation ect Management s del 1/1/23 al 30/6/27 UEP EXP B ADQUISICIONES 3 Component 4: Strengthening 05612-CS-INDV / Contratació Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 Under Review 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 n de 1 Experto B 40 hrs para ant Selection ect Management el Área Adquisiciones del 1/1 /23 al 30/6/27 UEP 2 EXPERTOS A ADQUIS- Component 4: Strengthening 305405-CS-INDV / Contrataci Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 on 2 Expertos "A" 40hrs Are ant Selection ect Management a Adquisiciones del 1/1/23 al 30/6/27 UEP EXP B MANTENIMIENTO- 306892-CS-INDV / Contrataci Component 4: Strengthening Individual Consult Under Implement ón de 1 Exp B área de Opera IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ciones y Mantenimiento - Pla ect Management nta Fisica. Del 1/1/23 al 30/6/ 27 METRAJE ESC 42 AIGUA 306 232-CS-INDV 2022 / Consulto Component 3: Improving Infr Individual Consult Pending Impleme r Arquitecto Metrajista para IBRD / 93310 astructure and Complement Post Limited 1,500.00 0.00 2023-01-08 2023-01-14 2023-01-18 2023-03-01 2023-03-31 ant Selection ntation Obra en la Escuela 42 Aiguá, ary Services Departamento de Maldonad o D.O. ESC 114 MDEO 306234 Component 3: Improving Infr Pending Impleme -CS-CDS 2022 / Dirección de IBRD / 93310 astructure and Complement Post Direct Selection Direct - National 14,500.00 0.00 2023-02-08 2023-02-19 2023-04-01 2024-05-02 ntation Obra Escuela 114 de Montevi ary Services deo UEP EXP. TEC AREA PROYEC Component 4: Strengthening TO-305347-CS-IND / Contrata Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ción de un Experto Técnico ant Selection ation ect Management 40 hrs para Área de Proyecto el 1/1/23 al 30/6/27 UEP EXP TEC INFORMATICO Component 4: Strengthening 305624-CS-INDV / Contrataci Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 104,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ón de 1 Experto Técnico 20 ant Selection ation ect Management hrs Área Informática del 1/1/ 23 al 30/6/27 UEP 2 EXPERTOS A OBRA-30 Component 4: Strengthening 5922-CS-INDV / Contratación Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 de 2 Expertos "A" en Área Ob ant Selection ation ect Management ras del 1/1/23 al 30/6/27 UEP DIRECTOR TEC ADQUISI .-305403-CS-INDV / Contrata Component 4: Strengthening Individual Consult ción de 1 Director Técnico 4 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 223,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-28 2022-11-04 2022-12-30 2027-06-30 ant Selection 0 hrs- Coordinador Área Adq ect Management uisiciones del 1/1/23 al 30/6/ 27 UEP 2 EXP. A PROYECTOS-30 5352-CS-INDV / Contratación Component 4: Strengthening Individual Consult Under Implement de 2 Expertos A 40 hrs- Arq IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation uitectos para el área de Proy ect Management ectos - del 1/1/23 al 30/6/27 UEP EXP. TECNICO PPP-ANEP Component 4: Strengthening -305659-CS-INDV / Contratac Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 Under Review 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ion Experto Tecnico 40hrs - ant Selection ect Management PPP del 1/1/23 al 30/6/27 UEP EXP. C -DIEE-ANEP-3059 45-CS-INDV / Contratación de Component 4: Strengthening Individual Consult Under Implement 1 Experto "C" 20 hs - para tr IBRD / 93310 Evaluation Systems and Proj Post Direct - National 78,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation abajar junto al equipo de la ect Management DIEE - ANEP del 1/1/23 al 30/ 6/27 UEP EXP C EQUIPAMIENTO 3 05617-CS-INDV / Contratació Component 4: Strengthening Individual Consult Under Implement n DE 1 Experto "C" 40 hrs p IBRD / 93310 Evaluation Systems and Proj Post Direct - National 155,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ara el área de Planificación ect Management y Equipamiento del 1/1/23 al 30/6/27 UEP EXP TEC MONITOREO 3 Component 4: Strengthening 05618-CS-INDV / Contratació Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 104,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 n de 1 Experto Técnico 20 h ant Selection ect Management rs para el Área Monitoreo del 1/1/23 al 30/6/27 UEP EXPERTO A INFORMATIC Component 4: Strengthening A 305625-CS-INDV / Contrata Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 190,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ción de 1 Experto "A" 40 hrs ant Selection ation ect Management en el Área Informática del 1/1/23 al 30/6/27 UEP EXP. B PLANIFICACION 3 Component 4: Strengthening 05384-CS-INDV / Contratació Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 n de 1 Experto "B" 40 hrs Pl ant Selection ation ect Management anificación Planta Física del 1 /1/23 al 30/6/27 UEP EXP TEC MANTENIMIENT O 305392-CS-IND / Contratac Component 4: Strengthening Individual Consult Under Implement ión de un Experto Técnico 40 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation hrs Area de Operaciones y M ect Management antenimiento del 1/1/23 al 30 /6/27 UEP EXP A EQUIPAMIENTO 3 05615-CS-INDV / Contratació Component 4: Strengthening Individual Consult Under Implement n de 1 Experto "A" 40 hrs Ár IBRD / 93310 Evaluation Systems and Proj Post Direct - National 190,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation ea de Planificación y Equipa ect Management miento del 1/1/23 al 30/6/27 UEP COORD. GRAL-305342- Component 4: Strengthening CS-INDV / Contratación de C Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 250,000.00 0.00 Under Review 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 oordinador General 40 hrs de ant Selection ect Management l 1/1/23 al 30/6/27 Page 6 UEP DIR TEC JURIDICA 305 Component 4: Strengthening 655-CS-IND / Contratación d Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 167,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 e 1 Director Técnico 30 hrs ant Selection ation ect Management Asesoría Jurídica del 1/1/23 al 30/6/27 UEP EXP.TECN EQUIPAMIEN TO 305614-CS-IND / Contrata Component 4: Strengthening Individual Consult Under Implement ción de 1 Experto Técnico 4 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 207,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ant Selection ation 0 hrs Área Planificación y Eq ect Management uipamiento del 1/1/23 al 30/6 /27 UEP EXP A MONITOREO 305 Component 4: Strengthening 620-CS-INDV / Contratación Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 190,000.00 0.00 Under Review 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 de 1 Experto "A" 40 hrs Área ant Selection ect Management Monitoreo del 1/!/23 al 30/6/ 27 UEP EXP B OPERAC Y MANTE N-305400-CS-INDV / Contrata Component 4: Strengthening Individual Consult Under Implement cion de 1 Expertos "B" 40 hrs IBRD / 93310 Evaluation Systems and Proj Post Direct - National 170,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ant Selection ation Area Operaciones y Manteni ect Management miento del 1/1/23 al 30/6/27 UEP 2 EXP A MANTENI 3053 Component 4: Strengthening 96-CS-INDV / Contratación de Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 2 Expertos "A" 40 hrs Área O ant Selection ation ect Management peraciones y Mantenimiento del 1/1/23 al 30/6/27 UEP 2 EXP.A PLANIFICACION Component 4: Strengthening 305381-CS-INDV / Contrataci Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 380,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ón de 2 Expertos "A" 40 hrs ant Selection ation ect Management Área Planificación Planta Físi ca de 1/1/23 al 30/6/27 UEP ASIST TEC A INFORM 3 Component 4: Strengthening 05652-CS-INDV / Contratació Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 132,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 n de 1 Asistente Técnico "A ant Selection ation ect Management " 40 hrs Área Informática del 1/1/23 al 30/6/27 UEP EXPERTO A INFORMATIC Component 4: Strengthening A 305653-CS-INDV / Contrata Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 95,000.00 0.00 2022-08-19 2022-12-01 2022-08-29 2022-11-04 2022-12-30 2027-06-30 ción de Experto "A" 20 hrs Ár ant Selection ation ect Management ea Informática del 1/1/23 al 3 0/6/27 D.O. SORIANO/COLONIA -31 1367-CS-CDS / Confección de Recaudos y Dirección de obr a para la Escuela N°65 Merce Component 3: Improving Infr Under Implement des. Dirección de Obra en la IBRD / 93310 astructure and Complement Post Direct Selection Direct - National 8,000.00 0.00 2022-08-29 2022-08-30 2022-10-17 2023-12-29 ation Esc. N° 9 La Paz y n° 126 Nu ary Services eva Helvecia de Colonia y rec uados y DO planes de mante nimiento en aprox 10 Escuel as de Colonia y 10 de Sorian o DGEIP EVALUACION EDUCAT . 312919-CS-INDV / Asesor e Component 4: Strengthening Individual Consult Pending Impleme n el campo de la Evaluación IBRD / 93310 Evaluation Systems and Proj Post Open - National 190,000.00 0.00 2022-09-26 2022-11-04 2022-12-09 2022-12-23 2027-06-30 ant Selection ntation Educativa, para la División d ect Management e Planeamiento Educativo de la DGEIP - ANEP DGEIP INVESTIG EDUCATIVA -312920-CS-INDV / Asesor en Component 4: Strengthening el campo de investigación ed Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Open - National 190,000.00 0.00 2022-09-12 2022-11-07 2022-12-09 2022-12-23 2027-06-30 ucativa que trabajara compa ant Selection ntation ect Management rtido entre la División de Plan eamiento Educativo de la DG EIP - ANEP y el PAEPU UEP DIRECTOR TEC FINANZA S 305613-CS-INDV / Contrata Component 4: Strengthening Individual Consult Under Implement ción de 1 Director Técnico 4 IBRD / 93310 Evaluation Systems and Proj Post Direct - National 223,000.00 0.00 2022-08-18 2022-12-01 2022-08-18 2022-11-04 2022-12-30 2027-06-30 ant Selection ation 0 hrs - Coordinador Área Fina ect Management nzas del 1/1/23 al 30/6/27 ARQ DIR OBRA 2022-27-300 884-CS-INDV / Contratación Directores de Obras 2022 - 2 027 , 50 D.O. de Construcció Component 3: Improving Infr Individual Consult Under Implement n y/o rehabilitación , 60 D.O. IBRD / 93310 astructure and Complement Post Open - National 350,000.00 0.00 2022-08-26 2022-12-21 2022-12-22 2023-02-10 2027-06-30 ant Selection ation obras de mantenimiento pre ary Services ventivo y correctivo en locale s escolares de Tiempo Pedag ógico ampliado ( T.C.,T. ext., Jardines de Jornada Completa , Aprender) AS TEC ADQUISICIONES -319 Component 4: Strengthening 052-CS-INDV / Contratación d Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Direct - National 218,000.00 0.00 2022-09-30 2022-10-10 2022-12-16 2023-02-10 2027-06-30 e 1 Experto "B" 40 hrs Área A ant Selection ation ect Management dquisiciones Vigencia 1/1/23 al 30/6/27 DIEE – ASIST CCSS -319059- CS-INDV / Contratación de u Component 4: Strengthening n Asistente CCSS - Técnico " Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 29,000.00 0.00 Canceled 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2023-12-31 A" 40 hrs para la Dirección d ant Selection ect Management e Investigación Evaluación E ducativa – ANEP del 1/1/23 al 31/12/2023 DIEE - ASIST COMUNIC -3190 64-CS-INDV / Contratación de un Asistente Comunicación Component 4: Strengthening Individual Consult Pending Impleme Experto "C" 20 hrs para la Di IBRD / 93310 Evaluation Systems and Proj Post Direct - National 8,000.00 0.00 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2023-12-31 ant Selection ntation rección de Investigación Eval ect Management uación Educativa – ANEP. Vig encia 6 meses: del 1/4/23 al 31/8/2023 DO ESC 74 Y 29 ROCHA -321 165-CS-INDV / Director de Ob Component 3: Improving Infr Individual Consult Under Implement ra para la Escuela n° 74 de la IBRD / 93310 astructure and Complement Post Open - National 9,500.00 0.00 2022-10-17 2022-10-18 2022-11-28 2022-12-02 2023-03-31 ant Selection ation Barra del Chuy y Esc 29 La C ary Services oronilla - Departamento de R ocha PONENTE EVAL, COMPETENC IA-332229-CS-INDV / Contrat ación consultor para el coloq uio interactivo con Formació Component 2: Strengthening Under Implement IBRD / 93310 Post Direct Selection Direct - National 580.00 0.00 2022-12-27 2022-12-27 2023-02-17 2023-02-27 n en Servicio del PAEPU, el dí Management Teams ation a 27 de febrero, actividad qu e es parte de una propuesta coordinada con autoridades de la ANEP- DGEIP Y CFP . Page 7 D.O. ESC. 80 TACUAREMBÓ 341291-CS-CDS / Confección de recaudos y dirección de o bra de la Escuela N° 80 de Ta Component 3: Improving Infr Under Implement cuarembó, en base a la lista IBRD / 93310 astructure and Complement Post Direct Selection Direct - National 3,200.00 0.00 2023-02-13 2023-02-20 2023-03-22 2023-09-18 ation de prelación de Directores de ary Services Obra por región en todo el Ur uguay, resultado de una llam ado abierto y homologado po r el CODICEN del año 2019. DIEE - PROF CCSS 319055-C S-INDV / Dos profesionales d e las Ciencias Sociales Senior para el análisis y el reporte d Component 4: Strengthening Individual Consult e resultados con experiencia IBRD / 93310 Evaluation Systems and Proj Post Direct - National 68,000.00 0.00 Canceled 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2024-01-03 ant Selection en procesar información y el ect Management aboración de informes para l a Dirección de Investigación Evaluación Educativa - ANEP Experto C 40 horas. DIEE ANALISTA ESTAD-3190 62-CS-INDV / Contratación de Component 4: Strengthening un Analista Estadístico Exper Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 34,000.00 0.00 Canceled 2022-09-30 2022-10-10 2022-11-16 2023-01-02 2023-12-31 to "C" 40 hrs para la Direcci ant Selection ect Management ón de Investigación Evaluaci ón Educativa – ANEP del 1/1/ 23 al 31/12/2023 DIEE - PROF. CCSS 341374-C S-INDV / Dos profesionales d e las Ciencias Sociales Senior para el análisis y el reporte d Component 4: Strengthening Individual Consult Under Implement e resultados con experiencia IBRD / 93310 Evaluation Systems and Proj Post Open - National 72,000.00 0.00 2023-02-20 2023-03-29 2023-03-29 2023-05-02 2024-04-30 ant Selection ation en procesamiento de informa ect Management ción y elaboración de inform es para la Dirección de Inves tigación y Evaluación Educati va - ANEP Experto C 40 horas . TUTORES CURSO INSP. 3413 01-CS-CQS / Llamado a aspir antes para la Contratación d Component 2: Strengthening Individual Consult Under Implement IBRD / 93310 Post Open - National 165,000.00 0.00 2023-02-09 2023-03-17 2023-03-11 2023-04-01 2023-07-03 2024-12-31 e 10 tutores para cursos de F Management Teams ant Selection ation ormación de Inspectores de ANEP. Por tres períodos de 6 meses, renovables hasta 202 4 ESP. MODULO 1 COHORTE 2 - 349681-CS-CDS / DSPE-ANE P, Doc. Especialista a cargo del Módulo Centro educativo, Component 2: Strengthening Under Implement familia y comunidad, para el IBRD / 93310 Post Direct Selection Direct - National 800.00 0.00 2023-03-19 2023-03-28 2023-03-22 2023-04-21 2023-04-29 Management Teams ation 2do Cohorte a llevarse a cab o en abril de 2023, del curso correspondiente al Programa de formación en gestión para directores de los centros edu cativos CONSULTOR VERIFICADOR - 351846-CS-INDV / Consultori Component 4: Strengthening Individual Consult Under Implement a Individual para verificación IBRD / 93310 Evaluation Systems and Proj Post Limited 1,300.00 0.00 2023-03-27 2023-03-31 2023-04-14 2023-05-19 2023-06-05 ant Selection ation de Indicadores con Condicion ect Management es basadas en desempeño DIEE ANALISTA ESTD-34135 1-CS-INDV / Llamado para la contratación de dos analistas estadístico para la muestra y Component 4: Strengthening Individual Consult Under Implement el procesamiento de informa IBRD / 93310 Evaluation Systems and Proj Post Open - National 72,000.00 0.00 2023-03-31 2023-05-19 2023-05-19 2023-06-22 2024-06-20 ant Selection ation ción con conocimiento de R y ect Management tecnica de Muestreo para la Dirección de Investigación y Evaluación Educativa. Contra tación por un año. DIEE ENAP E y Sea+ DSPE MÓD. GEST. EDUC.202 3-357783-CS-CDS / Contratac ión Docente especializado p ara el módulo Gestión Educat Component 2: Strengthening Under Implement iva orientada por datos para l IBRD / 93310 Post Direct Selection Direct - National 2,200.00 0.00 2023-04-23 2023-05-03 2023-06-11 2023-08-31 Management Teams ation a toma de decisiones, para el 3er. Cohorte del Programa d e Formación Directores y 1er cohorte para el Programa de Formación de Inspectores. DSPE MÓD HERR GESTIÓN-2 3 357787-CS-CDS / Contratac ión consultor Mag. Mora Pode stá Docente especializada pa Component 2: Strengthening Under Implement IBRD / 93310 Post Direct Selection Direct - National 8,700.00 0.00 2023-04-23 2023-05-03 2023-06-11 2023-09-28 ra el módulo herramientas p Management Teams ation ara la gestión educativa 2do. y 3er. cohorte PFD y 1er. coh orte PFI y Formación en Servi cio Centros María Espínola UEP TEC SANITARIO--357956 Component 4: Strengthening -CS-INDV / Contratación de u Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Post Open - National 150,000.00 0.00 2023-04-26 2023-05-24 2023-06-23 2023-08-01 2027-06-30 n Exp C - Técnico Sanitario p ant Selection ation ect Management ara el componente Planta Fí sica del PAEPU. UEP TEC ELECTRICISTA-3579 Component 4: Strengthening 58-CS-INDV / Contrato de un Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Open - National 150,000.00 0.00 Canceled 2023-04-26 2023-04-26 2023-05-27 2023-06-26 2023-08-04 2027-06-30 Técnico Electricista para el c ant Selection ect Management omponente Planta Física del PAEPU DSPE CONS LIC. COMUNICAC IO-359768-CS-CDS / LLamad o Consultor Licenciado en Co Component 2: Strengthening Individual Consult municación, Experto "B", 24h IBRD / 93310 Post Open - National 100,000.00 0.00 Canceled 2023-05-22 2023-06-19 2023-06-23 2023-07-31 2027-06-30 Management Teams ant Selection rs., como apoyo desde una p erspectiva de comunicación al Proceso de Transformació n Educativa. CIVIL ESC. 190 MTDEO-3617 92-CS-INDV / Consultoría par Component 3: Improving Infr Individual Consult Pending Impleme a realizar el proyecto de calc IBRD / 93310 astructure and Complement Post Limited 9,800.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation ulo estructural de la obra en l ary Services a Escuela N°190 de Montevi deo SANITARIA ESC. 190 MTDEO- 361796-CS-INDV / Consultorí Component 3: Improving Infr Individual Consult Pending Impleme a para llevar a cabo el proy IBRD / 93310 astructure and Complement Post Limited 3,700.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation ecto de la Instalación Sanitari ary Services o para las obras en la Esc. 1 90 de Montevideo Page 8 ELECTRICISTA ESC 190 MTD E-361798-CS-INDV / Consulto Component 3: Improving Infr Individual Consult Pending Impleme ría para realizar proyecto de l IBRD / 93310 astructure and Complement Post Limited 7,400.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation a Instalación Eléctrica para l ary Services a obra a realizarse en la Esc. 190 de Montevideo. BOMBERO ESC. 190 MTDEO- 361799-CS-INDV / Consultarí Component 3: Improving Infr Individual Consult Pending Impleme a para proyecto de Instalació IBRD / 93310 astructure and Complement Post Limited 2,200.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation n protección contra incendio ary Services , para Esc. 190 de Montevide o METRAJISTA ESC. 190 MTDE O-361800-CS-INDV / Consulta Component 3: Improving Infr Individual Consult Pending Impleme ría para realizar el Metraje y IBRD / 93310 astructure and Complement Post Limited 2,200.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-08-09 ant Selection ntation presupuesto de la obra en la ary Services Esc. 190 de Montevideo DSPE ESP LIDERAZGO COHO R 3-361853-CS-CDS / DSPE-A NEP . Docente Especialista a Component 2: Strengthening Individual Consult IBRD / 93310 Post Direct - National 1,100.00 0.00 Under Review 2023-05-22 2023-05-23 2023-06-16 2023-07-12 2023-08-31 cargo del Módulo Liderazgo e Management Teams ant Selection ducativo, para el 3er Cohorte a llevarse a cabo en el 2023 DSPE ESP GESTION CURRIC.- 361856-CS-CDS / DSPE-ANEP . Docente Especialista a carg o del Módulo Gestión curricul Component 2: Strengthening Individual Consult IBRD / 93310 Post Direct - National 2,200.00 0.00 Under Review 2023-05-22 2023-05-24 2023-05-29 2023-07-03 2023-10-31 ar del centro educativo: apoy Management Teams ant Selection o en la gestión para la transf ormación curricular, para el 3 er Cohorte a llevarse a cabo en 2023, DSPE ESP CENTRO COMUNID AD-361857-CS-INDV / Docent e Especialista a cargo del Mó Component 2: Strengthening Individual Consult dulo Centro educativo, famili IBRD / 93310 Post Open - National 1,100.00 0.00 Under Review 2023-05-19 2023-06-25 2023-06-25 2023-07-28 2023-10-31 Management Teams ant Selection a y comunidad del Programa de formación en gestión de c entros educativos de la ANEP - 3ER COHORTE AÑO 2023. DIEE ASIST. CCSS 361864-C S-INDV / Un Profesional Asist ente de las Ciencias Sociales Component 4: Strengthening Individual Consult para el análisis y el reporte d IBRD / 93310 Evaluation Systems and Proj Post Open - National 45,500.00 0.00 Under Review 2022-11-21 2023-01-09 2023-01-30 2023-03-06 2024-12-31 ant Selection e resultados para la Direcció ect Management n de Investigación Evaluació n Educativa – ANEP. Técnico A 40 hs ASIS. TEC. ADQUISICIONES-3 61871-CS-INDV / Consultor E xperto B para cumplir funcio Component 4: Strengthening nes en el área de Adquisicion Individual Consult Under Implement IBRD / 93310 Evaluation Systems and Proj Prior Open - National 185,000.00 0.00 2022-10-01 2023-06-15 2022-11-19 2022-12-10 2023-01-14 2027-06-30 es del PAEPU. Con experienc ant Selection ation ect Management ia en normativa local y del B anco Mundial para la contrat ación de Bienes, Obras y Ser vicios de Consultoría y No Co nsultoría. AGRIMENSOR- ESC 190 Y 27 7-361865-CS-INDV / Consulto Component 3: Improving Infr Individual Consult Under Implement ria para el proyecto de agri IBRD / 93310 astructure and Complement Post Limited 7,400.00 0.00 2023-05-19 2023-05-25 2023-05-29 2023-07-10 2023-09-11 ant Selection ation mensura para las Escuelas ary Services 190 de Montevideo y 277 de Canelones UEP DIR. TÉC. F.S. 363512-C Component 4: Strengthening S-INDV / Contratación de 1 Di Individual Consult IBRD / 93310 Evaluation Systems and Proj Post Direct - National 223,000.00 0.00 Under Review 2023-05-24 2023-06-03 2023-08-10 2023-10-05 2027-06-30 rector Técnico Coordinador d ant Selection ect Management e Formación en Servicio. D.O. ESC. 301 CANELONES - Component 3: Improving Infr 363691-CS-INDV / Arquitecto Individual Consult Pending Impleme IBRD / 93310 astructure and Complement Post Direct - National 40,000.00 0.00 2023-05-26 2023-05-29 2023-05-29 2023-06-13 2024-06-29 Director de Obra para la Escu ant Selection ntation ary Services ela 301 de Montevideo UEP DIREC TEC P. FISICA-36 Component 4: Strengthening 3507-CS-INDV / Contratación Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Direct - National 201,964.00 0.00 2023-05-31 2023-06-10 2023-06-10 2023-07-01 2027-06-30 1 Director Técnico 40hrs . Co ant Selection ntation ect Management ordinador Area Planta Física del 1/7/23 al 30/6/27 DSPE LIC. COMUNICACIÓN -3 65049-CS-INDV / Consultor Li cenciado en Comunicación, c Component 2: Strengthening Individual Consult Pending Impleme IBRD / 93310 Post Limited 13,200.00 0.00 2023-06-12 2023-06-13 2023-06-23 2023-08-01 2023-12-29 omo apoyo desde una perspe Management Teams ant Selection ntation ctiva de comunicación al Pro ceso de Transformación Educ ativa. ESPEC GESTION CENTRO ED UC-365392-CS-INDV / Contra tación Especialista en Gestió n de Centros Educativos para Component 2: Strengthening Individual Consult Pending Impleme participar como Ponente en e IBRD / 93310 Post Direct - National 800.00 0.00 2023-06-09 2023-06-09 2023-06-12 2023-07-04 2023-08-31 Management Teams ant Selection ntation l 3er cohorte del Curso Corre spondiente al Programa de fo rmación en gestión para Dire ctores de los Centros Educati vos en todos los niveles. UEP TEC ELECTRICISTA--365 Component 4: Strengthening 398-CS-INDV / Contratación T Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Open - National 150,000.00 0.00 2023-06-12 2023-07-13 2023-08-12 2023-09-20 2027-06-30 écnico Electricista para el Co ant Selection ntation ect Management mponente Planta Física de PA EPU UEP ARQ SUP OBRAS 36613 Component 4: Strengthening 0-CS-INDV / Arq. Supervisor d Individual Consult Pending Impleme IBRD / 93310 Evaluation Systems and Proj Post Direct - National 120,000.00 0.00 2023-06-16 2023-06-16 2023-06-21 2023-07-24 2027-06-30 e Obras - Consultor Experto ant Selection ntation ect Management A 40 horas, para la UEP - PAE PU Page 9 Plan de Passation de marchés I. Généralités 1. L'information sur le projet : Pays : Madagascar ; Emprunteur : République de Madagascar ; Nom de projet : Projet Filets Sociaux de Sécurité – Financement Additionnel (P160 544) ; Numéro du Crédit : D1450-MG ; Agence d’exécution du Projet : Unité Programme National de Nutrition Communautaire. 2. Date d’approbation du Plan de passation de marchés par la Banque : - ; Révision : - ; 3. Date de notification du Plan Général de Passation de marchés : - ; 4. Période couverte par le Plan de Passation de marchés : DOUZE (12) mois. II. Biens et Travaux et Services hors consultants 1. Seuil de Revue préalable : Les décisions de passation de marchés sujet aux revues préalables de la Banque comme indiqué dans le paragraphe 3.1 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) et sur la base de l'évaluation de la capacité de l'agence d’exécution : Seuil de Méthode de Passation de revue à Commentaires marchés priori (USD) Les montants 1 Biens : AOI/AON/UN/ED 2 000 000 estimatifs des marchés prévus 2 Travaux : AOI/AON/ED 10 000 000 sont au-dessous des seuils. Niveau de Services autres que 3 2 000 000 risque : consultants : AOI/AON/UN/ED « SUBSTANTIEL » 2. Pré-qualification (selon les dispositions des paragraphes 6.19 à 6.24 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable. 3. Procédures proposées pour les composantes CDD (selon le paragraphe. 6.52 et 6.53 de la Section VI du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016)) : Non Applicable 4. Référence (s’il y en a) au Manuel d’exécution du projet / Manuel de Passation de marchés : Manuels en cours de mise à jour 5. Tout autre arrangement spécial en passation de marchés : Non Applicable. 6. Allotissement de fournitures avec méthodes et calendrier : [Enumérer d’abord les allotissements qui nécessitent la revue préalable de la Banque, ensuite les autres allotissements] 1 2 3 4 5 6 7 8 9 Réf. No Description Contrat Approche/Méthod Revue de la Coût Pré- Préféren Date Commentaire e de sélection Banque (à estimatif qualificati ce prévue s priori / à (USD) on nationale d’ouverture posteriori) Oui / Non Oui / Non des soumission s Lot 1 : N°9 : Impression et Achevée multiplication de bulletins LIMITE 01 A.11 COT Post 12 000,00 NON NON 21-juin-18 Lot 2 : N°10 : en périodiques (02 numéros NATIONAL attente semestrielles) Maquette Acquisition outils de LIMITE Ordre de Service 03 A.11 COT Post 10 000,00 NON NON 13-mai-18 communication (Pagnes) NATIONAL signé Acquisition divers Pas encore LIMITE 04 A.17 équipements et mobiliers COT Post 5 000,00 NON NON 14-févr-19 lancée NATIONAL de bureau A programmer Acquisition de 293,2 SELECTION 1 475 246 Nouvelle activité 05 A.13 ED Post NON NON 12-févr-19 tonnes de Plumpy Sup DIRECTE ,46 PTA 2019 Acheminement vers LIMITE Nouvelle activité 06 A.13 Districts de 293,2 tonnes COT Post 77 644,55 NON NON 19-févr-19 NATIONAL PTA 2019 de Plumpy Sup Confection d’outils pour les sites : impression et LIMITE Nouvelle activité A.6.0 COT Post 11 812,50 NON NON 04-juin-19 livraison d’outils de NATIONAL PTA 2019 gestion : Registres Confection de plaques d'indication des sites et A.11.0 Supports de LIMITE Nouvelle activité COT Post 27 514,03 NON NON 04-juin-19 .1 communication : NATIONAL PTA 2019 Impression plaque, livrets et bulletins périodiques 1 2 3 4 5 6 7 8 9 Réf. No Description Contrat Approche/Méthod Revue de la Coût Pré- Préféren Date Commentaire e de sélection Banque (à estimatif qualificati ce prévue s priori / à (USD) on nationale d’ouverture posteriori) Oui / Non Oui / Non des soumission s Confection de Pagnes et A.11.0 T-shirt, Blouses pour LIMITE 17 578,13 Nouvelle activité .2 COT Post NON NON 04-juin-19 intervenants (Reny NATIONAL PTA 2019 mavitrika, …) Acquisition de matériels informatiques adaptés à l'actualisation du SIG et LIMITE Nouvelle activité A.14 COT Post 13 312,50 NON NON 04-juin-19 du développement du NATIONAL PTA 2019 Géoportail des données en ligne III. Sélection de consultants 1. Seuil de Revue Préalable : Décisions de sélection sujet à la revue préalable de la Banque comme indiqué dans le paragraphe 3 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016) : Méthode de sélection Seuil de Commentaires revue à priori (USD) 1. Méthode compétitive (firmes) 1 000 000 Les montants 2. Entente directe (firmes) 1 000 000 estimatifs des 3. Méthode compétitive (Consultant 300 000 contrats prévus individuel) sont au-dessous 4. Entente directe (Consultant 300 000 des seuils. individuel) Niveau de risque : « SUBSTANTIEL » 2. Liste restreinte composée entièrement de consultants nationaux : Selon les dispositions du paragraphe 7.25 de l'Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (Juillet 2016), la liste restreinte de consultants peut comporter entièrement des consultants nationaux pour les cas suivants : Catégorie de Montant estimatif consultant 1. Firmes Inférieur à USD 300 000 2. Consultants individuels Inférieur à USD 100 000 3. Tout autre arrangement spécial de Sélection de consultants : Non applicable 4. Tâches de consultation avec des méthodes de sélection et calendrier 1 2 3 4 5 6 7 Réf. No Description des missions Approche/Méth Revue de la Coût Date Commentaires ode de Banque (à estimatif prévue de sélection priori / à (USD) soumission posteriori) s des proposition s Consultant en charge de la maintenance Nouvelle activité PTA 01 A.14 ED ED Post 12 000,00 29-avril-19 du système Géoportail 2019 Consultants chargés de saisie des Nouvelle activité PTA 02 A.16 Registres des sites ED ED Post 34 321,33 20-mai-19 2019 Consultant Individuel en charge de Nouvelle activité PTA 03 B.2 l’élaboration de l’ICR INDV ED Post 5 000,00 21-mai-19 2019 IV. Activités de renforcement de capacités de l’Agence d’exécution avec calendrier 1. Dans cette section, les activités de renforcement de capacité acceptées (quelques articles pourraient être des recommandations de CPAR) sont énumérées avec le calendrier No. Résultats Coût Durée Date de Commentaires escomptés / estimatif estimative début Description de l’activité PROCUREMENT Madagascar : Social Safety Net Project PLAN General Information Country: Madagascar 2017-03-2 Bank’s Approval Date of the Original Procurement Plan: 2023-05-1 2 if none) Revised Plan Date(s): (comma delineated, leave blank Project ID: P149323 GPN Date: 9 Project Name: Social Safety Net Project Loan / Credit No: IDA / 57080, IDA / D1450, IDA / D4340, IDA / D7740 Intervention Funds for Development Executing Agency(ies): WORKS Activity Reference No Procuremen Estimate Actual Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati High SEA/S Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Comp . / Description Component Review Type Method t Document d Amou Amount ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) H Risk Status on Documents aluation Report as Issued letion Type nt (US$) (US$) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne d d d d d d d d d DRA13TRINF17001 / Trava Component 1: Building a s ux de construction de l' infr Request for Pro Single Stage - On 39,648.5 Complete 2017-07- 2017-08- 2017-07- 2017-08- 2017-08- 2017-09- 2017-08- 2017-09- 2017-08- 2017-10- 2017-12 IDA / 57080 afety net for the poor in se Post Limited 42,419.35 astructure N°01 dans la rég posals e Envelope 8 d 24 25 25 25 04 04 14 11 28 10 -06 lected rural areas ion Analanjirofo (Toamasin a). DRA13TRINF17002 / Trava Component 1: Building a s ux de construction de l'infr Request for Pro Single Stage - On 35,816.1 Complete 2017-07- 2017-08- 2017-07- 2017-08- 2017-08- 2017-09- 2017-08- 2017-09- 2017-08- 2017-10- 2017-12 IDA / 57080 afety net for the poor in se Post Limited 42,419.35 astructure N°02 dans la rég posals e Envelope 2 d 24 25 25 25 04 04 14 11 28 10 -06 lected rural areas ion Analanjirofo (Toamasin a). DRK13MPETR17001 / TRA Component 1: Building a s Request for Bid Single Stage - On 37,996.1 Complete 2017-07- 2017-10- 2017-07- 2017-10- 2017-08- 2017-10- 2017-08- 2017-10- 2017-08- 2017-11- 2017-12 VAUX DE REHABILITATION IDA / 57080 afety net for the poor in se Post Limited 41,129.03 s e Envelope 7 d 13 05 20 05 04 20 07 20 21 10 -19 DES OUVRAGES VOHITRIN lected rural areas DRY ILAKATRA ARA13TRMPE17005 / Trav Component 1: Building a s Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-09- 2018-12 aux de construction infrastr IDA / 57080 afety net for the poor in se Post Limited 42,164.52 0.00 Canceled s e Envelope 28 31 15 18 05 -21 ucture de base n°05 lected rural areas ARA13TRMPE17006 / Trav Component 1: Building a s Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-09- 2018-12 aux de construction infrastr IDA / 57080 afety net for the poor in se Post Limited 42,164.52 0.00 Canceled s e Envelope 28 31 15 18 05 -21 ucture de base n°06 lected rural areas ARA13TRMPE17007 / Trav Component 1: Building a s Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-09- 2018-12 aux de construction infrastr IDA / 57080 afety net for the poor in se Post Limited 42,164.52 0.00 Canceled s e Envelope 28 31 15 18 05 -21 ucture de base n°07 post c lected rural areas atastrophe ARA13TRMPE17008 / Trav Component 1: Building a s Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-09- 2018-12 aux de construction infrastr IDA / 57080 afety net for the poor in se Post Limited 42,164.52 0.00 Canceled s e Envelope 28 31 15 18 05 -21 ucture de base n°08 post c lected rural areas atastrophe ARA13TRMPE17009 / Trav Component 1: Building a s Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-08- 2018-12 aux de construction infrastr IDA / 57080 afety net for the poor in se Post Limited 42,164.52 0.00 Canceled s e Envelope 28 31 15 18 26 -11 ucture de base n°09 post c lected rural areas atastrophe ARA13TRMPE17010 / Trav Component 1: Building a s Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-09- 2018-12 aux de construction infrastr IDA / 57080 afety net for the poor in se Post Limited 42,164.52 0.00 Canceled s e Envelope 28 31 15 18 05 -21 ucture de base n°10 post c lected rural areas atastrophe ARA13TRMPE17011 / Trav Component 1: Building a s Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-09- 2018-12 aux de construction infrastr IDA / 57080 afety net for the poor in se Post Limited 42,164.52 0.00 Canceled s e Envelope 28 31 15 18 05 -21 ucture de base n°11 post c lected rural areas atastrophe DRP83TRMPE17007 / TRAV Component 1: Building a s Request for Pro Single Stage - On 2017-07- 2017-08- 2017-08- 2017-08- 2017-08- 2018-12 AUX DE REHABILITATION E IDA / 57080 afety net for the poor in se Post Limited 42,741.94 0.00 Canceled posals e Envelope 26 01 16 17 31 -31 PP POSTENAWO AMBOVOM lected rural areas BE7 DRP83TRMPE17006 / TRAV Component 1: Building a s Request for Pro Single Stage - On 2017-07- 2017-08- 2017-08- 2017-08- 2017-08- 2018-12 AUX DE REHABILITATION E IDA / 57080 afety net for the poor in se Post Limited 42,741.94 0.00 Canceled posals e Envelope 26 01 16 17 31 -31 PP POSTENAWO AMBOVOM lected rural areas BE6 DRP83TRMPE17005 / TRAV Component 1: Building a s Request for Pro Single Stage - On 2017-07- 2017-08- 2017-08- 2017-08- 2017-08- 2018-12 AUX DE REHABILITATION E IDA / 57080 afety net for the poor in se Post Limited 42,741.94 0.00 Canceled posals e Envelope 26 01 16 17 31 -31 PP POSTENAWO AMBOVOM lected rural areas BE5 DRP83TRMPE17003 / TRAV Component 1: Building a s Request for Pro Single Stage - On 2017-07- 2017-08- 2017-08- 2017-08- 2017-08- 2018-12 AUX DE REHABILITATION E IDA / 57080 afety net for the poor in se Post Limited 42,741.94 0.00 Canceled posals e Envelope 26 01 16 17 31 -31 PP POSTENAWO AMBOVOM lected rural areas BE3 DRP83TRMPE17004 / TRAV Component 1: Building a s Request for Pro Single Stage - On 2017-07- 2017-08- 2017-08- 2017-08- 2017-08- 2018-12 AUX DE REHABILITATION E IDA / 57080 afety net for the poor in se Post Limited 42,741.94 0.00 Canceled posals e Envelope 26 01 16 17 31 -31 PP POSTENAWO AMBOVOM lected rural areas BE4 DRP83TRMPE17002 / TRAV Component 1: Building a s Request for Pro Single Stage - On 2017-07- 2017-08- 2017-08- 2017-08- 2017-08- 2018-12 AUX DE REHABILITATION E IDA / 57080 afety net for the poor in se Post Limited 42,741.94 0.00 Canceled posals e Envelope 26 01 16 17 31 -31 PP POSTENAWO AMBOVOM lected rural areas BE2 DRP83TRMPE17001 / TRAV Component 1: Building a s Request for Pro Single Stage - On 2017-07- 2017-08- 2017-08- 2017-08- 2017-08- 2018-12 AUX DE REHABILITATION E IDA / 57080 afety net for the poor in se Post Limited 42,741.94 0.00 Canceled posals e Envelope 26 01 16 17 31 -31 PP POSTENAWO AMBOVOM lected rural areas BE1 DRP13TRMPE17001 / TRAV Component 1: Building a s AUX DE RAHABILITATION P Request for Bid Single Stage - On 61,209.3 Terminat 2017-08- 2017-09- 2017-08- 2017-09- 2017-09- 2017-09- 2017-10- 2017-10- 2017-11- 2018-10 IDA / 57080 afety net for the poor in se Post Open - National 85,483.87 OST ENAWO EPP AMBOVO s e Envelope 7 ed 23 13 25 24 13 26 16 09 21 -09 lected rural areas MBE CENTRE ET EPP SEVOHIPOTY DRP13TRMPE17002 / TRAV Component 1: Building a s Request for Bid Single Stage - On 40,164.9 Complete 2017-08- 2017-09- 2017-08- 2017-09- 2017-09- 2017-09- 2017-10- 2017-10- 2017-11- 2018-10 AUX DE REHABILITATION P IDA / 57080 afety net for the poor in se Post Open - National 42,741.94 s e Envelope 5 d 23 13 25 24 13 26 16 09 20 -09 OST ENAWO EPP AMPAMAT lected rural areas A SUD DRP13TRMPE17003 / TRAV Component 1: Building a s AUX DE REHABILITATION P Request for Bid Single Stage - On 71,667.2 Complete 2017-08- 2017-09- 2017-08- 2017-09- 2017-09- 2017-09- 2017-10- 2017-10- 2017-11- 2018-10 IDA / 57080 afety net for the poor in se Post Open - National 85,483.87 OST ENAWO EPP KOROMA s e Envelope 4 d 23 13 25 24 13 26 16 09 27 -09 lected rural areas SOALAVA ET EPP AMPAHIJOLOKE DRP13TRMPE17004 / TRAV Component 1: Building a s AUX DE REHABILITATION P Request for Bid Single Stage - On 72,467.4 Complete 2017-08- 2017-09- 2017-08- 2017-09- 2017-09- 2017-09- 2017-10- 2017-10- 2017-11- 2018-10 IDA / 57080 afety net for the poor in se Post Open - National 85,483.87 OST ENAWO EPP LAHIMANA s e Envelope 2 d 23 13 25 24 13 26 31 09 27 -09 lected rural areas RA HAUT ET EPP ANDANGORO ARA13TRMPE17001 / Trav Component 1: Building a s Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-09- 2018-12 aux de construction CEG B IDA / 57080 afety net for the poor in se Post Limited 42,164.52 0.00 Canceled s e Envelope 28 31 15 18 05 -21 ELAOKA LOKOHO - BELAOK lected rural areas A LOKOHO - ANDAPA ARA13TRMPE17012 / Trav Component 1: Building a s aux de construction/réhabil Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-09- 2018-12 IDA / 57080 afety net for the poor in se Post Limited 42,216.13 0.00 Canceled itation CSB AMBINANIFAHO s e Envelope 28 31 15 18 05 -21 lected rural areas - AMBINANIFAHO - ANTALA HA ARA13TRMPE17002 / Trav Component 1: Building a s Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-09- 2018-12 aux de construction EPP A IDA / 57080 afety net for the poor in se Post Limited 42,164.52 0.00 Canceled s e Envelope 28 31 15 18 05 -21 MPAPAMENA I - ANDRATAM lected rural areas ARINA - SAMBAVA DRP83TRMPE17008 / REH Component 1: Building a s Request for Bid Single Stage - On 49,172.1 Complete 2017-09- 2017-11- 2017-10- 2017-11- 2017-11- 2017-11- 2017-12- 2017-11- 2018-02- 2018-11 AB EPP ANJATOKA AMBOVO IDA / D1450 afety net for the poor in se Post Open - National 40,967.74 s e Envelope 7 d 28 14 02 02 14 06 18 20 13 -20 MBE 1 lected rural areas DRP83TRMPE17009 / REH Component 1: Building a s Request for Bid Single Stage - On 35,265.4 Complete 2017-09- 2017-11- 2017-10- 2017-11- 2017-11- 2017-11- 2017-12- 2017-11- 2018-02- 2018-11 AB EPP AMPAMOLORA AMB IDA / D1450 afety net for the poor in se Post Open - National 40,967.74 s e Envelope 6 d 28 14 02 02 14 06 18 20 13 -20 OVOMBE 2 lected rural areas DRP83TRMPE17010 / REH Component 1: Building a s Request for Bid Single Stage - On 48,527.1 Complete 2017-09- 2017-11- 2017-10- 2017-11- 2017-11- 2017-11- 2017-12- 2017-11- 2018-02- 2018-11 AB EPP AMBOASARY I AMB IDA / D1450 afety net for the poor in se Post Open - National 40,967.74 s e Envelope 7 d 28 14 02 02 14 06 18 20 13 -20 OVOMBE 4 lected rural areas DRP83TRMPE17011 / REH Component 1: Building a s Request for Bid Single Stage - On 37,445.9 Complete 2017-09- 2017-11- 2017-10- 2017-11- 2017-11- 2017-11- 2017-12- 2017-11- 2018-02- 2018-11 AB EPP ANKALITSANDRAKE IDA / D1450 afety net for the poor in se Post Open - National 40,967.74 s e Envelope 8 d 28 14 02 02 14 06 18 20 13 -20 AMBOVOMBE 3 lected rural areas DRP83TRMPE17012 / REH Component 1: Building a s Request for Bid Single Stage - On 41,927.0 Complete 2017-09- 2017-11- 2017-10- 2017-11- 2017-11- 2017-11- 2017-12- 2017-11- 2018-03- 2018-11 AB EPP ANKILIROE AMBOV IDA / D1450 afety net for the poor in se Post Open - National 40,967.74 s e Envelope 2 d 28 14 02 02 14 06 18 20 13 -20 OMBE 1 lected rural areas DRP83TRMPE17013 / REH Component 1: Building a s Request for Bid Single Stage - On 34,283.6 Complete 2017-09- 2017-11- 2017-10- 2017-11- 2017-11- 2017-11- 2017-12- 2017-11- 2018-02- 2018-11 AB EPP VOHIBARY AMBOAS IDA / D1450 afety net for the poor in se Post Open - National 40,967.74 s e Envelope 3 d 28 14 02 02 14 06 18 21 13 -21 ARY I lected rural areas DRP83TRMPE17014 / REH Component 1: Building a s Request for Bid Single Stage - On 35,003.1 Complete 2017-09- 2017-11- 2017-10- 2017-11- 2017-11- 2017-11- 2017-12- 2017-11- 2018-02- 2018-11 AB EPP BELAY AMBOASARY IDA / D1450 afety net for the poor in se Post Open - National 40,967.74 s e Envelope 5 d 28 14 02 02 14 06 18 21 13 -21 2 lected rural areas DRP83TRMPE17015 / REH Component 1: Building a s Request for Bid Single Stage - On 41,516.2 Complete 2017-09- 2017-11- 2017-10- 2017-11- 2017-11- 2017-11- 2017-12- 2017-11- 2018-02- 2018-11 AB EPP SOARAVINA LIMBY IDA / D1450 afety net for the poor in se Post Open - National 40,967.74 s e Envelope 9 d 28 14 02 02 14 06 18 21 12 -21 AMBOASARY 4 lected rural areas DRP83TRMPE17016 / REH Component 1: Building a s Request for Bid Single Stage - On 34,945.4 Complete 2017-09- 2017-11- 2017-10- 2017-11- 2017-11- 2017-11- 2017-12- 2017-11- 2018-02- 2018-11 AB EPP ANKILIMANARA AM IDA / D1450 afety net for the poor in se Post Open - National 40,967.74 s e Envelope 0 d 28 14 02 02 14 06 18 21 13 -21 BOASARY 1 lected rural areas DRP13TRMPE18001 / TRAV Component 1: Building a s Request for Bid Single Stage - On 43,011.2 Complete 2018-05- 2018-05- 2018-05- 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-07- 2019-07 AUX REPRISES EPP CENTRE IDA / 57080 afety net for the poor in se Post Open - National 47,602.52 s e Envelope 6 d 04 22 10 11 21 15 21 02 12 -02 ET EPP SEVOHIPOTY AMBO lected rural areas VOMBE ARA13TRMPE17004 / Trav Component 1: Building a s Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-09- 2017-09 aux de reconstruction EPP IDA / 57080 afety net for the poor in se Post Limited 10,469.16 0.00 Canceled s e Envelope 28 31 15 18 05 -05 Ankorabe - CR Ambohimala lected rural areas za - SAMBAVA ARA13TRMPE17003 / Trav Component 1: Building a s Request for Bid Single Stage - On 2017-07- 2017-07- 2017-08- 2017-08- 2017-09- 2017-09 aux de construction EPP Ma IDA / 57080 afety net for the poor in se Post Limited 11,988.04 0.00 Canceled s e Envelope 28 31 15 18 05 -05 hitsiarongana - CR Ambodi lected rural areas voara - SAMBAVA DRS13TRMPE1801 / TRAV Component 1: Building a s AUX DE REPRISE RECONST Request for Bid Single Stage - On 85,466.6 2018-04- 2018-02- 2018-04- 2018-05- 2018-02- 2018-05- 2018-03- 2018-06- 2018-04- 2018-09 IDA / 57080 afety net for the poor in se Post Open - National 45,245.17 Signed RUCTION EPP MAHITSIARO s e Envelope 5 25 14 25 25 14 28 19 09 11 -15 lected rural areas NGANA - CR AMBODIVOAR A - SAMBAVA DRS13TRMPE1802 / TRAV Component 1: Building a s AUX DE REPRISE RECONST Request for Bid Single Stage - On 2018-04- 2018-04- 2018-05- 2018-05- 2018-06- 2018-09 IDA / 57080 afety net for the poor in se Post Open - National 55,325.60 0.00 Canceled RUCTION EPP ANKORABE - s e Envelope 25 25 25 28 09 -15 lected rural areas CR AMBOHIMALAZA - SAMB AVA DRS13TRMPE1701 / Trava Component 1: Building a s ux de reconstruction CEG B Request for Bid Single Stage - On 56,278.2 2018-01- 2017-12- 2018-01- 2018-02- 2017-12- 2018-02- 2017-01- 2018-03- 2018-02- 2018-07 IDA / 57080 afety net for the poor in se Post Open - National 66,418.96 Signed ELAOKA LOKOHO - CR BELA s e Envelope 5 10 12 15 14 12 21 11 12 21 -10 lected rural areas OKA LOKOHO - District AND APA - Région SAVA DRS13TRMPE1702 / Trava Component 1: Building a s ux de reconstruction EPP S Request for Bid Single Stage - On 47,979.3 2018-01- 2017-12- 2018-01- 2018-02- 2017-12- 2018-02- 2018-01- 2018-03- 2018-02- 2018-07 IDA / 57080 afety net for the poor in se Post Open - National 56,624.69 Signed ARAHANDRANO - CR AMBO s e Envelope 5 10 12 15 14 12 21 11 12 21 -10 lected rural areas DIAMPANA - District SAMBA VA - Région SAVA DRS13TRMPE1703 / Trava Component 1: Building a s ux de reconstruction EPP A Request for Bid Single Stage - On 57,329.1 2018-01- 2017-12- 2018-01- 2018-02- 2017-12- 2018-02- 2018-01- 2018-03- 2018-02- 2018-07 IDA / 57080 afety net for the poor in se Post Open - National 67,659.27 Signed MPAMPAMENA I - CR ANDR s e Envelope 9 10 12 15 14 12 21 11 12 21 -10 lected rural areas ATAMARINA - District SAMB AVA - Région SAVA DRS13TRMPE1704 / Trava ux de reconstruction École Component 1: Building a s Request for Bid Single Stage - On 39,854.1 2018-01- 2017-12- 2018-01- 2018-02- 2017-12- 2018-02- 2018-01- 2018-03- 2018-02- 2018-07 Communautaire ANDALAM IDA / 57080 afety net for the poor in se Post Open - National 47,035.39 Signed s e Envelope 2 10 12 15 14 12 21 11 12 21 -10 AHITSY - CR ANTSIRABE NO lected rural areas RD - District VOHEMAR - Ré gion SAVA DRS13TRMPE1705 / Trava Component 1: Building a s ux de reconstruction École Request for Bid Single Stage - On 64,386.6 2018-01- 2017-12- 2018-01- 2018-02- 2017-12- 2018-02- 2018-01- 2018-03- 2018-02- 2018-07 IDA / 57080 afety net for the poor in se Post Open - National 75,988.36 Signed Communautaire NOSIMBAR s e Envelope 1 10 12 15 14 12 21 11 12 21 -10 lected rural areas Y - CR TSARABARIA - Distric t VOHEMAR - Région SAVA DRS13TRMPE1706 / Trava Component 1: Building a s ux de réhabilitation/reconst Request for Bid Single Stage - On 53,663.4 2017-12- 2017-12- 2018-01- 2018-02- 2017-12- 2018-02- 2018-01- 2018-03- 2018-02- 2018-07 IDA / 57080 afety net for the poor in se Post Open - National 63,332.95 Signed ruction EPP SAHAMAZAVA - s e Envelope 0 04 12 15 14 12 21 11 12 21 -10 lected rural areas CU ANDAPA - District ANDA PA - Région SAVA DRS13TRMPE1707 / Trava Component 1: Building a s ux de réhabilitation/reconst Request for Bid Single Stage - On 60,913.3 2017-12- 2017-12- 2018-01- 2018-02- 2017-12- 2018-02- 2018-01- 2018-03- 2018-02- 2018-07 IDA / 57080 afety net for the poor in se Post Open - National 71,678.29 Signed ruction CEG AMPAHANA - C s e Envelope 6 04 12 15 14 12 21 11 12 21 -10 lected rural areas R AMPAHANA - District ANT ALAHA - Région SAVA DRS13TRMPE1708 / Trava Component 1: Building a s ux de réhabilitation CEG M Request for Bid Single Stage - On 55,306.1 2017-12- 2017-12- 2018-01- 2018-02- 2017-12- 2018-02- 2018-01- 2018-03- 2018-02- 2018-07 IDA / 57080 afety net for the poor in se Post Open - National 65,080.20 Signed AHERIFODY - CU ANTALAH s e Envelope 9 04 12 15 14 12 21 11 12 21 -10 lected rural areas A - District ANTALAHA - Ré gion SAVA DRS13TRMPE1709 / Trava Component 1: Building a s ux de réhabilitation EPP AM Request for Bid Single Stage - On 53,033.1 2017-12- 2017-12- 2018-01- 2018-02- 2017-12- 2018-02- 2018-01- 2018-03- 2018-02- 2018-07 IDA / 57080 afety net for the poor in se Post Open - National 62,405.47 Signed BATOFISAKA - CU ANTALAH s e Envelope 6 04 12 15 14 12 21 11 12 21 -10 lected rural areas A - District ANTALAHA - Ré gion SAVA DRS13TRMPE1710 / Trava Component 1: Building a s ux de réhabilitation/reconst Request for Bid Single Stage - On 47,965.5 2017-12- 2017-12- 2018-01- 2018-02- 2017-12- 2018-02- 2018-01- 2018-03- 2018-02- 2018-07 IDA / 57080 afety net for the poor in se Post Open - National 56,442.27 Signed ruction CSB AMBINANIFAH s e Envelope 5 04 12 15 14 12 21 11 12 21 -10 lected rural areas O - CR AMBINANIFAHO - Dis trict ANTALAHA - Région SA VA DRK13MPETR18001 / TRA Component 1: Building a s Request for Bid Single Stage - On 40,290.1 2018-06- 2018-08- 2018-06- 2018-06- 2018-06- 2018-08- 2018-06- 2018-09- 2018-07- 2018-09- 2018-10 VAUX DE RÉHABILITATION/ IDA / 57080 afety net for the poor in se Post Limited 43,593.75 Signed s e Envelope 6 05 16 12 28 27 27 30 11 14 11 -12 RECONSTRUCTION ECOLE lected rural areas 1 VOHIPENO DRF13TRMPE18001 / TRAV Component 1: Building a s Request for Bid Single Stage - On 40,576.6 Complete 2018-07- 2018-08- 2018-08- 2018-08- 2018-08- 2018-09- 2018-08- 2018-09- 2018-09- 2018-09- 2018-12 AUX DE RECONSTRUCTION IDA / 57080 afety net for the poor in se Post Limited 45,125.00 s e Envelope 5 d 31 23 07 23 22 04 25 04 08 24 -07 EPP AMBOHIMAHASOA 01 lected rural areas DRF13TRMPE18002 / TRAV Component 1: Building a s Request for Bid Single Stage - On 34,770.7 Complete 2018-07- 2018-08- 2018-08- 2018-08- 2018-08- 2018-09- 2018-08- 2018-09- 2018-09- 2018-09- 2018-12 AUX DE RECONSTRUCTION IDA / 57080 afety net for the poor in se Post Limited 45,125.00 s e Envelope 6 d 31 23 07 23 22 03 25 04 08 21 -07 D'UNE ECOLE PRIMAIRE AM lected rural areas BOHIMAHASOA 02 DRT13TRMPE18001 / Trav Component 1: Building a s aux de réhabilitation/recon Request for Bid Single Stage - On 40,789.9 Complete 2018-07- 2018-09- 2018-07- 2018-09- 2018-08- 2018-11- 2018-08- 2018-11- 2018-08- 2018-12- 2019-12 IDA / 57080 afety net for the poor in se Post Limited 47,419.35 struction d'une école dans l s e Envelope 4 d 24 20 26 27 10 09 18 12 30 05 -13 lected rural areas e District d'Arivonimamo DRT13TRMPE18002 / Trav Component 1: Building a s Request for Bid Single Stage - On 45,102.6 Complete 2018-07- 2018-09- 2018-07- 2018-09- 2018-08- 2018-11- 2018-08- 2018-11- 2018-08- 2018-12- 2019-12 aux de réhabilitation/recon IDA / 57080 afety net for the poor in se Post Limited 47,419.35 s e Envelope 4 d 24 20 26 27 10 09 18 12 30 05 -13 struction d'une école dans l lected rural areas e District de Faratsiho DRF13TRMPE19001 / TRAV Component 1: Building a s Under Im Request for Bid Single Stage - On 28,611.0 2019-06- 2019-06- 2019-06- 2019-06- 2019-07- 2019-07- 2019-07- 2019-07- 2019-07- 2019-07- 2019-09 AUX DE RECONSTRUCTION IDA / 57080 afety net for the poor in se Post Limited 29,750.00 plementa s e Envelope 0 16 24 23 27 08 12 11 22 25 25 -23 D'UNE EPP DANS LE FOKON lected rural areas tion TANY ANKAZOTANA DRA13TVX2001 / Travaux Component 1: Building a s de curage mécanisé de lit d Request for Quo Single Stage - On 2020-01- 2020-01- 2020-01- 2020-01- 2020-02 IDA / D4340 afety net for the poor in se Post Limited 4,500.00 4,019.45 Signed e rivière en amont du péri tations e Envelope 29 28 30 31 -05 lected rural areas mètre à Amparafaravola et Ambatondrazaka DRA11 DC TRV 20002 / Tr avaux de restauration des Component 1: Building a s Under Im Request for Quo Single Stage - On 2020-09- 2020-11- 2020-11- 2021-05 stèles et des panneaux d'af IDA / D4340 afety net for the poor in se Post Limited 8,500.00 0.00 plementa tations e Envelope 20 02 15 -14 fichage TMDH et FSP dans l lected rural areas tion es districts de Mahanoro - Vatomandry Et Toamasina I I DRF 12_DC_TRV_ESP_ 200 Component 1: Building a s 1 / Travaux de construction Request for Quo Single Stage - On 2020-11- 2020-12- 2021-02 IDA / D4340 afety net for the poor in se Post Limited 6,500.00 0.00 Canceled de 47 espaces physiques tations e Envelope 08 26 -24 lected rural areas TMDH dans le district d'Am bohimahasoa DG20_DC_TRAVAUX_RECO NS_2001 / Travaux de reco Component 1: Building a s nstruction et fourniture d'é Request for Quo Single Stage - On 870,000.0 487,927. 2020-11- 2020-11- 2020-12- 2021-02- 2021-03 IDA / D4340 afety net for the poor in se Post Limited Signed quipements et mobiliers de tations e Envelope 0 66 12 11 24 27 -24 lected rural areas s infrastructures Socio-éco nomiques de base dans la r égion BOeny répartis en di x (10) lots DG20_DC_TRAVAUX_REHA B_2002 / Travaux de réhabi Component 1: Building a s litation et fourniture d'équi Request for Quo Single Stage - On 160,000.0 242,212. 2020-11- 2020-11- 2020-12- 2021-03- 2021-03 IDA / D4340 afety net for the poor in se Post Limited Signed pements et mobiliers des i tations e Envelope 0 49 12 11 24 27 -24 lected rural areas nfrastructures Socio-écono miques de base dans la rég ion Boeny répartis en deux (02) lots DRT13 DC TRAVAUXMPE 2 1001 / Travaux de réhabilit Component 1: Building a s Pending I ation et de reconstruction Request for Quo Single Stage - On 195,000.0 2021-02- 2021-03- 2021-09 IDA / D4340 afety net for the poor in se Post Limited 0.00 mplemen des infrastructures commu tations e Envelope 0 02 31 -27 lected rural areas tation nautaires de base dans les Régions d'Analamanga et d e Menabe - 05 Lots DG_AON_TRAVAUX_RECON S_2101 / Travaux de recon struction et fourniture d'éq Component 1: Building a s Request for Bid Single Stage - On 350,000.0 342,812. 2021-01- 2021-02- 2021-01- 2021-03- 2021-03- 2021-03- 2021-04- 2021-04- 2021-05- 2021-07 uipements et mobiliers des IDA / D4340 afety net for the poor in se Post Open - National Signed s e Envelope 0 87 25 09 30 01 12 31 05 28 28 -27 infrastructures Socio-écono lected rural areas miques de base dans la rég ion B0eny répartis en quatr e (04) lots, Région Boeny, District de Soalala DRA_21001_DC_TRAV_MPE / Travaux de reconstruction Component 1: Building a s Under Im Request for Quo Single Stage - On 100,000.0 2021-04- 2021-05- 2021-08 des infrastructures socio-é IDA / D4340 afety net for the poor in se Post Open - National 0.00 plementa tations e Envelope 0 05 22 -20 conomiques de base avec f lected rural areas tion ourniture des mobiliers - R égion d'Alaotra Mangoro DRK_21002_DC_ESP PHYSI QUE / Mise en place de tren Component 1: Building a s Request for Qu Pending I Request for Quo Single Stage - On 2021-06- 2021-08- 2021-11 te (30) Espaces Physiques IDA / D4340 afety net for the poor in se Post Open - National otations (Non B 1,700.00 0.00 mplemen tations e Envelope 19 14 -12 pour les sites témoins TMD lected rural areas ank-SPD) tation H répartis en trois lots de T âcherons. DRT_21009_DC_TRAV_MPE Component 1: Building a s Request for Qu Under Im / Reconstruction des Infrast Request for Quo Single Stage - On 100,000.0 2021-07- 2021-08- 2022-03 IDA / D4340 afety net for the poor in se Post Open - National otations (Non B 0.00 plementa ructures de base communa tations e Envelope 0 15 22 -31 lected rural areas ank-SPD) tion utaires dans les Districts d' Anjozorobe et de Miandriva zo DRT_21006_DC_STELE_CO Component 1: Building a s Request for Qu Pending I NS / Construction de stèle i Request for Quo Single Stage - On 2021-07- 2021-08- 2021-11 IDA / D4340 afety net for the poor in se Post Open - National otations (Non B 810.81 0.00 mplemen ndicatif des activités FSP d tations e Envelope 15 22 -30 lected rural areas ank-SPD) tation ans le District d'Arivonima mo DRU_21006_DC_TRAVAUX _MPE / Travaux de reconstr Component 1: Building a s Request for Qu uction des Infrastructures s Request for Quo Single Stage - On 61,903.8 2021-08- 2022-07- 2021-09- 2022-04- 2022-12 IDA / D4340 afety net for the poor in se Post Open - National otations (Non B 80,300.00 Signed ocio-économiques de base tations e Envelope 1 07 20 22 26 -22 lected rural areas ank-SPD) avec fournitures des mobili ers dans la Région Atsimo Andrefana DG_21019_AO_RECONSTR UCTION_8LOTS / Travaux d Request for Bid Component 1: Building a s e reconstruction des infrast Request for Bid Single Stage - On s - Works Frenc 400,000.0 380,767. 2021-08- 2021-10- 2021-09- 2021-10- 2021-11- 2021-10- 2021-12- 2021-11- 2022-02- 2022-02 IDA / D4340 afety net for the poor in se Post Open - National Signed ructures communautaires d s e Envelope h Civil Law (Fre 0 00 31 06 07 05 08 19 29 16 12 -14 lected rural areas e base dans les régions Sof nch) SPD ia et Boeny répartis en huit (08) lots Page 1 DG_21020_DC_REHABILITA Component 1: Building a s Request for Qu TION_ANALALAVA / Travau Request for Quo Single Stage - On 109,141. 2021-09- 2021-10- 2022-02- 2022-01 IDA / D4340 afety net for the poor in se Post Open - National otations (Non B 65,000.00 Signed x de réhabilitation du Lycé tations e Envelope 82 05 24 12 -22 lected rural areas ank-SPD) e Alidy Aboudou à Analalav a, Région Sofia DRT_21005_DC_STELE_RE Component 1: Building a s Request for Qu Pending I HAB / Réhabilitation de stèl Request for Quo Single Stage - On 2021-07- 2021-08- 2021-11 IDA / D4340 afety net for the poor in se Post Open - National otations (Non B 729.73 0.00 mplemen e dans les Districts d'Antan tations e Envelope 15 22 -30 lected rural areas ank-SPD) tation ifotsy, Betafo et Faratsiho, soit en trois (03) lots DG_21017_DC_RECONS_P Component 1: Building a s Request for Qu Request for Quo Single Stage - On 175,000.0 234,506. 2021-08- 2021-10- 2021-12- 2022-01 ONT_ANDRANOMAVO / Tra IDA / D4340 afety net for the poor in se Post Open - National otations (Non B Signed tations e Envelope 0 20 25 13 10 -11 vaux de reconstruction du lected rural areas ank-SPD) Pont Andranomavo DRA_21006_AO_TRX _MPE Request for Bid _7 LOTS / Travaux de recon Component 1: Building a s Pending I Request for Bid Single Stage - On s - Works Frenc 693,900.0 2021-08- 2021-08- 2021-09- 2021-10- 2021-11- 2022-02 struction des infrastructure IDA / D4340 afety net for the poor in se Post Open - National 0.00 mplemen s e Envelope h Civil Law (Fre 0 23 30 27 11 08 -06 s communautaires de base lected rural areas tation nch) SPD dans la Région Analanjirofo repartis en sept (07) lots DRA_21016_DC_TRX _MPE _LYCÉE AMPASIMBE / Trava Component 1: Building a s Request for Qu Under Im Request for Quo Single Stage - On 126,400.0 2021-11- 2022-01- 2022-04 ux de reconstruction des in IDA / D4340 afety net for the poor in se Post Open - National otations (Non B 0.00 plementa tations e Envelope 0 19 06 -06 frastructures communautai lected rural areas ank-SPD) tion res de base dans la région Analanjirofo lot unique National Procur DRU_21019_DC_TRAVAUX Component 1: Building a s ement Docume Under Im STELES_TMDH_FSP_FA3 / Tr Request for Quo Single Stage - On 2021-12- 2022-09- 2022-02- 2022-06 IDA / D7740 afety net for the poor in se Post Open - National nt - 1 Envelope 7,900.00 0.00 plementa avaux d'installation des stè tations e Envelope 14 09 08 -08 lected rural areas process (Non B tion les et panneaux dans les si ank-SPD) tes TMDH et FSP FA3 DRA_22004_DC_STELE_CO National Procur NS_TMDH FSP FA3 / Constr Component 1: Building a s ement Docume Under Im uction de stèle indicatif des Request for Quo Single Stage - On 2022-03- 2022-08- 2022-04- 2022-06 IDA / D7740 afety net for the poor in se Post Open - National nt - 1 Envelope 9,800.00 0.00 plementa activités FSP ET TMDH dan tations e Envelope 08 16 26 -15 lected rural areas process (Non B tion s les Districts : Vavatenina- ank-SPD) Fenoarivo Atsinanana- Amb atondrazaka - Ampafarafav ola DRP82_DC_TRV2001 / Trav aux de construction des 10 Component 1: Building a s Request for Quo Single Stage - On 2020-10- 2020-12- 2021-06 3 espaces physiques DPEI IDA / D4340 afety net for the poor in se Post Limited 30,000.00 0.00 Canceled tations e Envelope 20 15 -13 dans les districts Amboasar lected rural areas y sud, Ambovombe Androy, Tsihombe, Bekily et Beloha DRT_22010_AON_TRAVAU X_INFRA_FA3 / Travaux de r Request for Bid econstruction des infrastru Component 1: Building a s Under Im Request for Bid Single Stage - On s - Works Frenc 334,000.0 2022-10- 2022-10- 2022-11- 2022-11- 2022-12- 2023-07 ctures communautaires de IDA / D7740 afety net for the poor in se Post Open - National 0.00 plementa s e Envelope h Civil Law (Fre 0 09 16 13 27 18 -06 bases endommagées dans lected rural areas tion nch) SPD le District d'Ankazobe, dan s le District d'Anjozorobe et dans le District d'Antanana rivo Antsimondrano Request for Qu DRP_22004_DC_PETITS TR Component 1: Building a s otations - Small Under Im AVAUX_POST CYCLONI / Pet Request for Quo Single Stage - On 159,000.0 2022-08- 2022-09- 2022-10- 2022-12 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 plementa its travaux post cyclonique tations e Envelope 0 13 26 08 -07 lected rural areas ncy) SPD -Com tion s: réhabilitation des écoles petitive et CSB DRF_22010_DC_PETIS TRA VAUX_POST-CAT / Petits Tr Request for Qu avaux post-cycloniques: d Component 1: Building a s otations - Small Under Im ans le cadre de la réponse Request for Quo Single Stage - On 2022-08- 2022-09- 2022-11 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 31,500.00 0.00 plementa aux catastrophes. 02 lots d tations e Envelope 02 20 -19 lected rural areas ncy) SPD -Com tion e travaux de réfection toitu petitive re et peinture CEG Ambato vory - CU Fianarantsoa et C EG Mahasoabe - CR Mahas oabe - District Vohibato DRK_22009_AO_PETITS TR AVAUX_POST-CATA / Petits travaux post-cycloniques ré Request for Bid Component 1: Building a s Under Im partis en trente trois (33) lo Request for Bid Single Stage - On s - Small Works 660,000.0 2022-08- 2022-09- 2022-08- 2022-09- 2022-09- 2022-10- 2022-10- 2022-11- 2022-12- 2023-05 IDA / D7740 afety net for the poor in se Post Open - National 0.00 plementa ts dans les Districts de Nos s e Envelope SPD (1 envelop 0 11 17 16 21 27 03 27 22 01 -30 lected rural areas tion y Varika(05), Mananjary(07 e process) ), Ifanadiana (01), Manakar a(04), Vohipeno(03), Farafa ngana(10), Vangaindrano(0 3). DG_22040_DC_PETITS TRA VAUX REHAB_RELANCE / Tr Component 1: Building a s Request for Qu Under Im Request for Quo Single Stage - On 2022-10- 2022-12- 2022-12- 2023-03 avaux de réhabilitation des IDA / D7740 afety net for the poor in se Post Open - National otations (Non B 80,000.00 0.00 plementa tations e Envelope 28 07 16 -16 infrastructures communaut lected rural areas ank-SPD) tion aires de base répartis en 4 lots DRA_22017_AON_TRAVAU X_RECONS_OUV_FA3 / Trav Request for Bid aux de Reconstruction des Component 1: Building a s Under Im Request for Bid Single Stage - On s - Small Works 619,000.0 2022-12- 2023-03- 2022-12- 2023-03- 2023-01- 2023-03- 2023-02- 2023-03- 2023-07 ponts endommagées par d IDA / D7740 afety net for the poor in se Post Open - National 0.00 plementa s e Envelope SPD (1 envelop 0 07 04 12 24 18 28 17 23 -21 es catastrophes naturelles lected rural areas tion e process) dans les régions d'Atsinan ana et d' Analanjirofo , rep artis en huit ( 08) lots DRF_22015_DC_TRVX _RE C_BAT__VAG1_URGENCE / Travaux de reconstruction Component 1: Building a s Request for Qu Under Im Request for Quo Single Stage - On 140,000.0 2022-11- 2023-02- 2023-01- 2023-05 et fourniture d’équipement IDA / D7740 afety net for the poor in se Post Open - National otations (Non B 0.00 plementa tations e Envelope 0 30 23 03 -03 s et mobiliers des infrastru lected rural areas ank-SPD) tion ctures de base en bâtimen t dans la Région Haute Mat siatra 1ère Vague , Réparti s en trois ( 03) lots DRF_22016_DC_TRVX _RE H_BAT__VAG2_URGENCE / Component 1: Building a s Request for Qu Under Im Travaux de réhabilitation e Request for Quo Single Stage - On 2023-01- 2023-03- 2023-02- 2023-06 IDA / D7740 afety net for the poor in se Post Open - National otations (Non B 71,000.00 0.00 plementa t fournitures d’équipement tations e Envelope 26 17 26 -26 lected rural areas ank-SPD) tion s et mobiliers d'infrastructu re de base en bâtiment dan s la Région Amoron'i Mania 2ème Vague DRU_22005_DC_TRVX_REC O_BAT_VAG1_POST CAT / T Component 1: Building a s Request for Qu Under Im ravaux de reconstruction d Request for Quo Single Stage - On 139,000.0 2022-11- 2023-01- 2023-01- 2023-05 IDA / D7740 afety net for the poor in se Post Open - National otations (Non B 0.00 plementa es infrastructures de base tations e Envelope 0 29 17 16 -16 lected rural areas ank-SPD) tion en bâtiment dans la région Atsimo Andrefana 1ère Vag ue , repartis en trois ( 03) l ots DRF_23003_DC_TRVX _RE Request for Qu H_OUV_VAG1_URGENCE / T Component 1: Building a s otations - Small Under Im ravaux de réhabilitation de Request for Quo Single Stage - On 2023-02- 2023-03- 2023-03- 2024-01 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 80,000.00 0.00 plementa Pont à Andreamalama , Co tations e Envelope 02 17 27 -21 lected rural areas ncy) SPD -Com tion mmune Rurale Talata Apan petitive o,District de Vohibato, Régi on Haute Matsiatra DRK_23002_DC_TRAVAUX_ REH_FA3_URGENCE / Trava Request for Qu ux de réhabilitation/reconst Component 1: Building a s otations - Small Under Im ruction des infrastructures Request for Quo Single Stage - On 3,248,000. 2023-02- 2023-04- 2023-05- 2024-02 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 plementa de base dans la Région Atsi tations e Envelope 00 22 21 03 -27 lected rural areas ncy) SPD -Com tion mo Atsinanana répartie en petitive Trente neuf (39) lots dans l a Région Atsimo Atsinanan a, Fitovinany et Vatovavy_ Vague 2 DRA_23001_DC_TRAV_POS TCYCL_URGENCE_FA3 / Tra Request for Qu vaux d'urgence post cyclon Component 1: Building a s otations - Small Under Im ique pour la réhabilitation e Request for Quo Single Stage - On 500,000.0 2023-02- 2023-04- 2023-04- 2023-05 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 plementa t la reconstruction des infra tations e Envelope 0 13 06 24 -24 lected rural areas ncy) SPD -Com tion structures sociales et com petitive munautaires de base dans la Région Analanjirofo et la Région Atsinanana repartis en quatre lots DRF_23001_DC_TRVX_ECO LE_VAG1_URGENCE / Trava Request for Qu ux de réhabilitation et four Component 1: Building a s otations - Small Under Im nitures d’équipements et m Request for Quo Single Stage - On 150,000.0 2023-02- 2023-03- 2023-03- 2024-01 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 plementa obiliers des infrastructures tations e Envelope 0 02 15 16 -10 lected rural areas ncy) SPD -Com tion de base en bâtiment scolai petitive res (EPP, Lycée et CEG) da ns la Région Haute Matsiatr a 1ère Vague , répartis en deux ( 02) lots DRK_23004_DC_TRAVAUX_ REH_FA3_URGENCE / Trava Request for Qu ux de réhabilitation/reconst Component 1: Building a s otations - Small Under Im Request for Quo Single Stage - On 2,466,000. 2023-03- 2023-05- 2023-05- 2024-03 ruction des infrastructures IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 plementa tations e Envelope 00 22 20 31 -26 de base dans la Région de lected rural areas ncy) SPD -Com tion Vatovavy, Fitovinany et At petitive simo Atsinanana répartie e n trente neuf (39) lots _Vag ue 3 DRU_22004_DC_TRVX_REH Request for Qu A_PC_URGENCE / Travaux d Component 1: Building a s otations - Small Under Im Request for Quo Single Stage - On 2023-01- 2023-03- 2023-03- 2023-07 e réhabilitation d'une infras IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 47,000.00 0.00 plementa tations e Envelope 31 16 08 -06 tructure de base dans la Ré lected rural areas ncy) SPD -Com tion gion Atsimo Andrefana, rep petitive artie en Un (01) lot_Vague 1 DRF_23004_DC_TRVX _RE C_ECOL__VAG2_URGENC / Request for Qu Travaux de réhabilitation e Component 1: Building a s otations - Small Under Im t fournitures d’équipement Request for Quo Single Stage - On 491,000.0 2023-03- 2023-04- 2023-05- 2024-02 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 plementa s et mobiliers des infrastru tations e Envelope 0 22 06 03 -27 lected rural areas ncy) SPD -Com tion ctures de base en bâtimen petitive t scolaires (EPP) dans la Ré gion Amoron'i Mania et Ihor ombe 2ème Vague , réparti s en six ( 06) lots DRK_23001_DC_TRAVAUX_ Request for Qu REH_FA3_URGENCE / Trava Component 1: Building a s otations - Small Under Im ux de réhabilitation/reconst Request for Quo Single Stage - On 1,402,000. 2023-02- 2023-03- 2023-04- 2024-02 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 plementa ruction des infrastructures tations e Envelope 00 08 03 19 -13 lected rural areas ncy) SPD -Com tion de base dans la Région Atsi petitive mo Atsinanana et Fitovinan y répartie en quatre (04) lo ts_Vague 1 DRK_22017_AON_TRAVAU X_REH_FA3_URGENCE / Tra Request for Bid Component 1: Building a s Pending I vaux de réhabilitation des i Request for Bid Single Stage - On s - Works Frenc 559,000.0 2022-12- 2022-12- 2023-01- 2023-02- 2023-03- 2023-09 IDA / D7740 afety net for the poor in se Post Open - National 0.00 mplemen nfrastructures de base dan s e Envelope h Civil Law (Fre 0 01 08 05 02 09 -05 lected rural areas tation s la Région Atsimo Atsinan nch) SPD ana répartie en deux (02) l ots_Vague 1 DRK_22018_AON_TRAVAU X_REC_FA3_URGENCE / Tra Request for Bid Component 1: Building a s Pending I vaux de reconstruction de Request for Bid Single Stage - On s - Works Frenc 1,083,000. 2022-12- 2022-12- 2023-01- 2023-02- 2023-03- 2023-09 IDA / D7740 afety net for the poor in se Post Open - National 0.00 mplemen s infrastructures de base d s e Envelope h Civil Law (Fre 00 01 08 05 02 09 -05 lected rural areas tation ans la Région de Fitovinany nch) SPD et Atsimo Atsinanana repar tie en quatre (04) lots_Vag ue 1 DRK_22019_AON_TRAVAU X_REH_FA3_URGENCE / Tra Request for Bid vaux de réhabilitation des Component 1: Building a s Pending I Request for Bid Single Stage - On s - Works Frenc 356,000.0 2023-01- 2023-01- 2023-02- 2023-03- 2023-04- 2023-10 infrastructures de base dan IDA / D7740 afety net for the poor in se Post Open - National 0.00 mplemen s e Envelope h Civil Law (Fre 0 20 27 24 24 28 -25 s la Région Atsimo Atsinan lected rural areas tation nch) SPD ana répartie en trois (03) lo ts dans la Région Atsimo At sinanana_Vague 2 DG_23004_DC_TRAVAUX_ Request for Qu RELANCE_URGENCE / Trava Component 1: Building a s otations - Small Under Im Request for Quo Single Stage - On 2023-02- 2023-04- 2023-04- 2023-08 ux de reconstruction EPP A IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 50,000.00 0.00 plementa tations e Envelope 20 28 03 -01 MPARIHIMAROMASO - CR B lected rural areas ncy) SPD -Com tion eronono - District Anjozoro petitive be - Région Analamanga DRP_23003_DC_TRAVAUX_ POSTCYCLONE_URGENCE / Request for Qu Travaux de réhabilitation d Component 1: Building a s otations - Small Under Im u pont radier Maromby Dist Request for Quo Single Stage - On 126,000.0 2023-02- 2023-05- 2023-05- 2023-09 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 plementa rict Amboasary Sud dans le tations e Envelope 0 27 11 29 -26 lected rural areas ncy) SPD -Com tion cadre de la réhabiltation de petitive s infrastructures communa utaires de base endommag ées par les cyclones DRP_23002_DC_TRAVAUX_ POSTCYCLONE_URGENCE / Request for Qu Travaux réhabilitation/reco Component 1: Building a s otations - Small Under Im nstruction infrastructures c Request for Quo Single Stage - On 507,000.0 2023-02- 2023-03- 2023-07 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 plementa ommunautaires de base en tations e Envelope 0 15 27 -25 lected rural areas ncy) SPD -Com tion dommagées par les catastr petitive ophes naturelles dans les R égions Anosy et Androy, ré partis en cinq (05) lots: DRP_23001_DC_TRAVAUX_ POSTCYCLONE_URGENCE / Request for Qu Travaux de réhabilitation/r Component 1: Building a s otations - Small Under Im Request for Quo Single Stage - On 415,000.0 2023-02- 2023-05- 2023-03- 2023-07 econstruction infrastructur IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 plementa tations e Envelope 0 15 04 27 -25 es communautaires base e lected rural areas ncy) SPD -Com tion ndommagées par cyclone, petitive dans la Région Anosy, répa rtis en trois (03) lots DRK_23003_DC_TRAVAUX_ Request for Qu REH_OUV_FA3_URGENCE / Component 1: Building a s otations - Small Pending I Travaux de réhabilitation/r Request for Quo Single Stage - On 2023-02- 2023-04- 2023-08 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 52,000.00 0.00 mplemen econstruction de pont Ivoit tations e Envelope 22 19 -17 lected rural areas ncy) SPD -Com tation ra dans la Commune Anosy petitive , District de Farafangana, R égion Atsimo Atsinanana _ Vague 2 DRF_23002_DC_TRVX_SAN TE_VAG1_URGENCE / Trava Request for Qu ux de réhabilitation et four Component 1: Building a s otations - Small Under Im Request for Quo Single Stage - On 2023-02- 2023-03- 2023-03- 2023-07 nitures d’équipements et m IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 65,000.00 0.00 plementa tations e Envelope 02 08 27 -25 obiliers des infrastructures lected rural areas ncy) SPD -Com tion de base sanitaire (CSBII) da petitive ns la Région Haute Matsiatr a 1ère Vague repartis en d eux (02) lots DRP_23004_DC_PETITS TR AVAUX CONSTRUCTION / Tr avaux de construction d'un Component 1: Building a s Request for Qu Under Im Centre communautaire ave Request for Quo Single Stage - On 2023-02- 2023-03- 2023-04- 2023-05 IDA / D7740 afety net for the poor in se Post Open - National otations (Non B 17,000.00 0.00 plementa c mise en place de deux (0 tations e Envelope 11 14 08 -08 lected rural areas ank-SPD) tion 2) stèles multi usages, incl uant fresques dans le Fkt B etsideda, Commune Maroal omainty, District d'Ambovo mbe DG_23025_DC_TRAVAUX_ Request for Qu URGENCE_FREDDY / Travau Component 1: Building a s otations - Small Under Im x de réhabilitation/reconstr Request for Quo Single Stage - On 270,000.0 2023-05- 2023-05- 2023-06- 2023-10 IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 plementa uction des infrastructures c tations e Envelope 0 08 11 19 -17 lected rural areas ncy) SPD -Com tion ommunautaires de base da petitive ns le cadre de la réponse a ux catastrophes DRA_23002_DC_TRAV_POS TCYCL_URGENCE_FA3 / Tra Request for Qu vaux d'urgence post cyclon Component 1: Building a s otations - Small Request for Quo Single Stage - On 154,000.0 2023-04- 2023-05- 2023-09 ique pour la réhabilitation e IDA / D7740 afety net for the poor in se Post Open - National Works (Emerge 0.00 Canceled tations e Envelope 0 22 24 -21 t la reconstruction des infra lected rural areas ncy) SPD -Com structures sociales et com petitive munautaires de base dans l a Région Atsinanana en lot unique DG_23027_DC_CLOISONNE Component 1: Building a s Request for Qu Under Im MENT_BUREAUX_ANOSY / T Request for Quo Single Stage - On 2023-05- 2023-05- 2023-07- 2023-07 IDA / D7740 afety net for the poor in se Post Open - National otations (Non B 20,000.00 0.00 plementa ravaux de cloisonnement d tations e Envelope 19 24 07 -10 lected rural areas ank-SPD) tion es nouveaux bureaux du FI D Anosy GOODS Activity Reference No Estimated A Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati Actual Amou Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Completio . / Description Component Review Type Method mount (US$ ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) nt (US$) Status on Documents aluation Report as Issued n ) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d d d d d d DG11FRMAC17001 / March Component 1: Building a s és multiples divers divers tr Request for Quo Single Stage - On 2017-05- 2017-11- 2017-05- 2017-12- 2017-06- 2018-01- IDA / 57080 afety net for the poor in se Post Limited 5,143.58 643.46 Completed avaux d'impression pour m tations e Envelope 06 20 29 11 19 09 lected rural areas esures d'accompagnement DG11FRMAC17002 / March Component 1: Building a s és multiples divers outils p Request for Quo Single Stage - On 2017-05- 2017-05- 2017-05- 2017-07- 2017-06- 2017-08- IDA / 57080 afety net for the poor in se Post Limited 20,391.54 3,661.76 Completed our mesures d'accompagne tations e Envelope 06 30 29 03 19 21 lected rural areas ment ACTP (pins, pochette à épargne...) DG20FRINFO17003 / Marc Component 1: Building a s Request for Quo Single Stage - On 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-07- hés multiples achats matér IDA / 57080 afety net for the poor in se Post Limited 39,275.35 29,954.89 Completed tations e Envelope 06 12 29 20 19 13 iels informatiques lected rural areas DG11FRCPS17004 / March Component 1: Building a s Request for Quo Single Stage - On 2017-05- 2017-09- 2017-06- 2017-10- 2017-07- és multiples (Outils de trav IDA / 57080 afety net for the poor in se Post Limited 16,212.53 12,826.60 Signed tations e Envelope 16 12 09 13 09 ail et d'identification des C lected rural areas PS) DG20FRCOMM1801 / Four Component 2: Strengtheni nitures d'outils de commun ng safety net administratio Request for Quo Single Stage - On 2018-03- 2018-03- 2018-03- 2018-04- 2018-04- IDA / 57080 Post Limited 2,250.00 1,311.87 Signed ication - travaux d'impressi n, monitoring and social ac tations e Envelope 07 15 26 13 25 on (autocollant, pochette p countability orte documents....) DG20FRCOMM1802 / FOUR Component 2: Strengtheni Request for Quo Single Stage - On 2018-03- 2017-11- 2018-04- 2017-12- 2018-05- NITURES D'OUTILS DE COM IDA / 57080 ng safety net administratio Post Limited 850.00 4,330.86 Signed tations e Envelope 22 22 30 07 30 MUNICATION - GOODIES n, monitoring and social ac countability DG20FRCOMM1803 / FOUR Component 2: Strengtheni Request for Quo Single Stage - On 2018-03- 2018-03- 2018-03- 2018-04- 2018-04- NITURES D'OUTILS DE COM IDA / 57080 ng safety net administratio Post Limited 3,250.00 1,408.07 Signed tations e Envelope 08 21 31 12 30 MUNICATION (tee shirt, cas n, monitoring and social ac quette, gilet...) countability DG20FRCONSINFO1804 / A Component 2: Strengtheni Request for Quo Single Stage - On 2018-05- 2018-06- 2018-06- 2018-09- 2018-07- 2018-10- chat consommables inform IDA / 57080 ng safety net administratio Post Limited 5,800.00 5,916.55 Completed tations e Envelope 08 14 02 11 02 19 atiques n, monitoring and social ac countability Component 2: Strengtheni DG20FRANTVIR1805 / Ach Request for Quo Single Stage - On 2018-05- 2018-05- 2018-06- 2018-06- 2018-06- IDA / 57080 ng safety net administratio Post Limited 15,200.00 3,060.99 Completed at antivirus tations e Envelope 08 26 06 25 11 n, monitoring and social ac countability DG12FREVEILPE1806 / Ach Component 1: Building a s Request for Quo Single Stage - On 2018-05- 2018-06- 2018-06- 2018-08- 2018-07- 2018-08- at fournitures de stimulatio IDA / 57080 afety net for the poor in se Post Limited 19,300.00 18,319.60 Completed tations e Envelope 11 13 07 16 07 24 n et éveil petite enfance lected rural areas Component 1: Building a s DG12FRJOUEPE1807 / Ach Request for Bid Single Stage - On 2018-05- 2018-06- 2018-05- 2018-06- 2018-07- 2018-06- 2018-09- 2018-06- 2018-09- 2018-07- 2018-12- IDA / 57080 afety net for the poor in se Post Open - National 38,600.00 44,974.99 Completed at jouets petite enfance s e Envelope 10 18 11 10 23 17 03 27 21 27 13 lected rural areas Component 1: Building a s DG12FRAFFTMDH1808 / IM Request for Quo Single Stage - On 2018-06- 2018-04- 2018-06- 2018-06- 2018-07- 2018-06- IDA / 57080 afety net for the poor in se Post Limited 8,190.00 3,286.23 Completed PRESSION AFFICHES TMDH tations e Envelope 07 19 19 20 10 22 lected rural areas DG11FRBANDMAC1809 / C Component 1: Building a s ONFECTION BANDEROLES Request for Quo Single Stage - On 2018-06- 2018-08- 2018-07- 2018-09- 2018-08- IDA / 57080 afety net for the poor in se Post Limited 27,176.00 21,167.67 Signed EN BACHE POUR MESURE D tations e Envelope 12 10 02 05 01 lected rural areas 'ACCOMPAGNEMENT TMDH DG12FRRADCART1820 / A Component 1: Building a s Request for Quo Single Stage - On 2018-08- 2018-08- 2018-09- 2018-11- 2018-10- 2018-12- chat radios carte et carte S IDA / 57080 afety net for the poor in se Post Limited 13,500.00 11,611.58 Signed tations e Envelope 11 16 03 20 03 07 D DPEI lected rural areas DG12FRDEPLMAC1822 / Fo Component 1: Building a s Request for Quo Single Stage - On 2018-08- 2018-07- 2018-09- 2018-08- 2018-10- urniture de Dépliants MACC IDA / 57080 afety net for the poor in se Post Limited 1,340.00 542.16 Signed tations e Envelope 11 06 03 28 03 TMDH lected rural areas Component 1: Building a s DG12FRJOUDPEI1823 / Ach Request for Bid Single Stage - On 2018-08- 2018-06- 2018-08- 2018-09- 2018-07- 2018-09- 2018-09- 2018-09- 2018-09- 2018-10- 2018-11- IDA / 57080 afety net for the poor in se Post Open - National 24,000.00 28,442.41 Completed at jouets pour le DPEI LOT1 s e Envelope 10 21 14 13 23 18 03 25 21 25 12 lected rural areas Page 2 DG12FRJOUDPEI1824 / Ach Component 1: Building a s Request for Bid Single Stage - On 2018-08- 2018-06- 2018-08- 2018-09- 2018-07- 2018-09- 2018-09- 2018-09- 2018-09- 2018-10- 2018-10- at jouets pour le DPEI LOT IDA / 57080 afety net for the poor in se Post Open - National 14,800.00 15,842.59 Completed s e Envelope 10 21 14 13 23 18 03 25 13 25 29 2 lected rural areas DG12FRDPEI1825 / Achat f Component 1: Building a s Request for Quo Single Stage - On 2018-08- 2018-08- 2018-09- 2018-11- 2018-10- 2018-11- ournitures pour atelier de IDA / 57080 afety net for the poor in se Post Limited 8,130.00 4,782.55 Completed tations e Envelope 13 14 04 13 04 15 créativité pour les parents lected rural areas DPEI DG20FRCALEND1827 / Fou Component 2: Strengtheni Request for Quo Single Stage - On 2018-11- 2018-11- 2018-12- 2019-01- 2019-01- rniture de calendriers et ag IDA / 57080 ng safety net administratio Post Limited 19,600.00 31,104.66 Signed tations e Envelope 22 22 13 07 03 endas 2019 n, monitoring and social ac countability DG20FRMATINFO1901 / AC Component 2: Strengtheni Request for Quo Single Stage - On 2019-08- 2019-08- 2019-09- 2019-10- 2019-09- 2019-11- HATS DES MATÉRIELS INFO IDA / D1450 ng safety net administratio Post Limited 65,000.00 31,819.93 Completed tations e Envelope 12 29 09 21 24 06 RMATIQUES n, monitoring and social ac countability DG20FRCALEND1902 / ÉDI Component 2: Strengtheni Request for Quo Single Stage - On 2019-08- 2019-09- 2019-09- 2019-10- 2019-09- TION DES CALENDRIERS ET IDA / 57080 ng safety net administratio Post Limited 50,000.00 9,544.50 Signed tations e Envelope 11 04 05 21 27 AGENDA FID 2020 n, monitoring and social ac countability DG20FRSENS19002 / BAC Component 2: Strengtheni Request for Quo Single Stage - On 2019-09- 2019-09- 2019-10- 2019-10- 2019-11- HE DE SENSIBILISATION 8 T IDA / 57080 ng safety net administratio Post Limited 95,000.00 35,780.64 Signed tations e Envelope 30 27 25 22 10 HEMES SES ET EF n, monitoring and social ac countability DG20FRSUPPSENSMACC19 Component 1: Building a s Request for Quo Single Stage - On 2019-08- 2019-09- 2019-09- 2019-10- 2019-09- 01 / Marchés multiples: Co IDA / D1450 afety net for the poor in se Post Limited 150,000.00 119,191.21 Signed tations e Envelope 16 19 10 21 20 nfection des supports de se lected rural areas nsibilisation DGFRNVEH190901 / Acqui Component 2: Strengtheni UN Agencies (Di 2019-09- 2019-09- 2019-09- 2019-09- 2019-10- 2019-10- 2020-01- sition de huit véhicules de IDA / D1450 ng safety net administratio Post Direct 350,000.00 319,913.76 Signed rect) 20 25 25 25 30 15 28 supervisions n, monitoring and social ac countability DG20AONINFO_BUR_TECH Component 1: Building a s 20001 / Acquisition de mat Request for Bid Single Stage - On 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- 2020-03- 2020-05- 2020-04- 2020-08- 2020-06- IDA / D1450 afety net for the poor in se Post Open - National 150,000.00 135,472.01 Signed ériels et équipements (Infor s e Envelope 06 08 11 22 09 23 12 27 04 26 lected rural areas matiques, Bureautiques, Te chniques) DG20DCREGINS_TUL / Con Component 1: Building a s Under Impl Request for Quo Single Stage - On 2019-12- 2020-01- 2020-01- 2020-02- fection registre d'inscriptio IDA / 57080 afety net for the poor in se Post Limited 600.00 0.00 ementatio tations e Envelope 10 23 02 01 n pour Toliary II lected rural areas n DG20AONRADIOS20001 / Component 1: Building a s Request for Bid Single Stage - On 2020-01- 2020-05- 2020-01- 2020-02- 2020-06- 2020-03- 2020-09- 2020-05- 2020-10- 2020-07- Acquisition de radios et acc IDA / D4340 afety net for the poor in se Post Open - National 43,000.00 37,898.34 Signed s e Envelope 13 15 18 29 16 30 02 04 20 03 essoires lected rural areas DG20UNOPSVEHIC19001 / Component 2: Strengtheni UN Agencies (Di 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2019-12- 2020-04- Acquisition de neuf (09) vé IDA / D4340 ng safety net administratio Post Direct 428,000.00 350,899.22 Signed rect) 12 05 17 05 21 12 20 hicules de supervision n, monitoring and social ac countability DG20AONJOUETS20001 / A Component 1: Building a s Request for Bid Single Stage - On 2020-02- 2020-05- 2020-02- 2020-03- 2020-06- 2020-04- 2020-09- 2020-06- 2020-10- 2020-08- cquisition de jouets (toutes IDA / D4340 afety net for the poor in se Post Open - National 300,000.00 111,100.42 Signed s e Envelope 10 04 15 28 12 27 04 01 21 30 directions et toutes compo lected rural areas santes) DG20FRLIVREDUCATIFS19 Component 1: Building a s Request for Quo Single Stage - On 2020-01- 2020-09- 2020-03- 2020-11- 2020-05- 02 / ACHAT DE LIVRES EDU IDA / D4340 afety net for the poor in se Post Limited 39,000.00 40,662.41 Signed tations e Envelope 17 17 13 21 12 CATIFS lected rural areas DG20FRQUINC1903 / ACH Component 1: Building a s Request for Quo Single Stage - On 2020-01- 2020-04- 2020-03- 2020-10- 2020-05- AT DE DIVERSES QUINCAIL IDA / D4340 afety net for the poor in se Post Limited 23,000.00 10,484.56 Signed tations e Envelope 15 17 13 22 12 LERIES lected rural areas Component 2: Strengtheni DG20FRMMB1904 / ACHAT Request for Quo Single Stage - On 2020-01- 2020-08- 2020-03- 2020-11- 2020-05- IDA / D4340 ng safety net administratio Post Limited 10,000.00 5,379.33 Signed DE MOBILIERS DE BUREAU tations e Envelope 13 28 09 03 08 n, monitoring and social ac countability Component 1: Building a s DG20FRBADGES1905 / IMP Request for Quo Single Stage - On 2020-01- 2020-04- 2020-03- 2020-07- 2020-03- IDA / D4340 afety net for the poor in se Post Limited 10,000.00 5,852.04 Signed RESSION BADGES tations e Envelope 18 27 14 07 20 lected rural areas DG20FRCONFECPANN1906 Component 2: Strengtheni Pending I Request for Quo Single Stage - On 2020-01- 2020-03- 2020-05- / CONFECTION DE PANNEA IDA / D4340 ng safety net administratio Post Limited 9,000.00 0.00 mplement tations e Envelope 20 16 15 UX D'AFFICHAGE ET MALLE n, monitoring and social ac ation S countability DG20AOCOMBACHES2200 01 / Confections de support Component 1: Building a s Request for Bid Single Stage - On 2020-01- 2020-02- 2020-03- 2020-04- 2020-05- 2020-12- s de communication en bâc IDA / D4340 afety net for the poor in se Post Open - National 350,000.00 0.00 Canceled s e Envelope 27 01 14 13 18 31 hes - Marchés multiples po lected rural areas ur toutes composantes et t outes Directions DG20AOCOMMTISSUS2000 1 / Confection de supports Component 1: Building a s Request for Bid Single Stage - On 2020-02- 2020-03- 2020-02- 2020-03- 2020-04- 2020-04- 2020-06- 2020-06- 2020-08- 2020-12- de communication en tissu IDA / D4340 afety net for the poor in se Post Open - National 126,000.00 64,270.45 Signed s e Envelope 10 17 15 28 28 27 22 01 20 31 s - Marchés multiples pour lected rural areas toutes composantes et tout es directions. Component 1: Building a s Pending I DG20FRKITVSLA1907 / AC Request for Quo Single Stage - On 2020-01- 2020-03- 2020-05- IDA / D4340 afety net for the poor in se Post Limited 5,000.00 0.00 mplement HAT KIT VSLA tations e Envelope 22 18 17 lected rural areas ation DG20AOBOITESAIMAGES2 Component 1: Building a s Request for Bid Single Stage - On 2020-01- 2020-02- 2020-03- 2020-04- 2020-05- 2020-12- 0001 / Confection boîtes à i IDA / D4340 afety net for the poor in se Post Open - National 145,000.00 0.00 Canceled s e Envelope 27 01 14 13 18 31 mages lected rural areas DG20FRNTBURDIRAVEC19 Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-01- 2020-03- 2020-05- 08 / ACHAT FOURNITURE D IDA / D4340 afety net for the poor in se Post Limited 30,000.00 0.00 mplement tations e Envelope 29 25 24 E BUREAU (AVEC) POUR LE lected rural areas ation S DIRs DG20AOIMPRESSIONSUPP Component 1: Building a s Pending I ORT20001 / Impression et Request for Bid Single Stage - On 2020-01- 2020-01- 2020-02- 2020-03- 2020-05- 2020-12- IDA / D4340 afety net for the poor in se Post Open - National 130,000.00 0.00 mplement multiplication de divers out s e Envelope 13 18 29 30 04 31 lected rural areas ation ils de travail - Toutes Direct ions DG20DCCOMMPAPIERS200 01 / Confection de supports Component 1: Building a s Request for Quo Single Stage - On 2020-02- 2020-04- 2020-04- 2020-07- 2020-12- de communications en papi IDA / D4340 afety net for the poor in se Post Limited 35,000.00 26,127.65 Signed tations e Envelope 08 17 04 01 31 er : Affiches, Dépliants, ... - lected rural areas Marchés multiples pour tou tes Directions DG20FRCOFFCADENAS190 Component 1: Building a s 9 / CONFECTION COFFRETS Request for Quo Single Stage - On 2020-01- 2020-04- 2020-03- 2020-07- 2020-05- IDA / D4340 afety net for the poor in se Post Limited 35,200.00 8.72 Signed AVEC CADENAS(AVEC Inclu tations e Envelope 15 02 11 07 10 lected rural areas sion Financière) pour les DI R DG20FRCUVETAVEC1910 / Component 1: Building a s Under Impl Request for Quo Single Stage - On 2020-01- 2020-03- 2020-05- ACHAT DE CUVETTES (AVE IDA / D4340 afety net for the poor in se Post Limited 10,000.00 0.00 ementatio tations e Envelope 18 14 13 C Inclusion Financière) pou lected rural areas n r les DIRs DG20FRSACFICEL1911 / C Component 1: Building a s Request for Quo Single Stage - On 2020-01- 2020-04- 2020-03- 2020-07- 2020-05- ONFECTION SAC A FICELLE IDA / D4340 afety net for the poor in se Post Limited 10,000.00 52,185.87 Signed tations e Envelope 25 17 21 07 20 (Inclusion Financière) pour lected rural areas les DIRs DG20DC_2010_CLEARBAG Component 1: Building a s Under Impl Request for Quo Single Stage - On 2020-04- 2020-04- 2020-05- 2020-06- / Acquisition de pochettes IDA / D4340 afety net for the poor in se Post Limited 40,000.00 0.00 ementatio tations e Envelope 01 21 27 17 plastiques (Clearbag) lected rural areas n DG20DC_2013_IMPRESSIO Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-03- 2020-04- 2020-05- N_OUTILS / Impression et IDA / 57080 afety net for the poor in se Post Limited 10,000.00 0.00 mplement tations e Envelope 30 28 28 multiplication d'outils de tr lected rural areas ation avail (AVEC) DG20DC_2012_BACHES / F Component 1: Building a s Request for Quo Single Stage - On 2020-04- 2020-04- 2020-05- 2020-07- 2020-07- ourniture de supports de se IDA / D4340 afety net for the poor in se Post Limited 50,000.00 45,300.32 Signed tations e Envelope 01 27 27 01 26 nsibilisation en bâches lected rural areas DG20DC_2011_BOITESAIM Component 1: Building a s Request for Quo Single Stage - On 2020-03- 2020-06- 2020-05- 2020-10- 2020-07- AGES / Fourniture de boites IDA / D4340 afety net for the poor in se Post Limited 60,000.00 31,428.70 Signed tations e Envelope 28 03 23 07 22 à images lected rural areas DRU12CFMOB20001 / ACQ Component 2: Strengtheni Request for Quo Single Stage - On 2020-06- 2020-07- 2020-08- 2020-07- 2020-10- 2021-02- UISITION DE MOBILIERS DE IDA / D4340 ng safety net administratio Post Limited 3,804.72 3,786.40 Completed tations e Envelope 29 28 02 31 01 05 BUREAUX n, monitoring and social ac countability DG20_DC_PC_TABLET_201 Component 1: Building a s Request for Quo Single Stage - On 2020-07- 2020-08- 2020-09- 4 / Acquisition de tablettes IDA / D4340 afety net for the poor in se Post Limited 50,000.00 0.00 Canceled tations e Envelope 13 24 21 et powerbank lected rural areas DG20_DC_ PRINT_THERM_ Component 1: Building a s Request for Quo Single Stage - On 2020-07- 2020-09- 2020-10- 2016 / Acquisition d'imprim IDA / D4340 afety net for the poor in se Post Limited 45,000.00 0.00 Canceled tations e Envelope 27 07 05 antes thermiques lected rural areas DG20_DC_EQPT_COMM_20 12 / Acquisition de matériel s et équipements pour le s Component 1: Building a s ervice communication répa Request for Quo Single Stage - On 2020-07- 2020-09- 2020-08- 2021-01- 2020-09- IDA / D4340 afety net for the poor in se Post Limited 20,000.00 2,596.76 Signed rtis en trois (03) lots : tations e Envelope 20 11 31 29 28 lected rural areas Lot N°01 : Appareils photo numériques Lot N°02 : Dictaphones Lot N°03 : Interphones DG20_DC_MATINFO_2015 / Acquisition d'équipements i Component 2: Strengtheni nformatiques et techniques ng safety net administratio Request for Quo Single Stage - On 2020-08- 2020-08- 2020-09- 2020-10- 2020-11- répartis en trois (03) lots : IDA / D4340 Post Limited 100,000.00 7,654.08 Signed n, monitoring and social ac tations e Envelope 05 12 30 29 29 LOT N°01 : Ordinateurs por countability tables LOT N°02 : Onduleurs LOT N°03 : Clés USB DRP82_DC_FOURNALPHA2 Component 1: Building a s Pending I 003 / Acquisition des fourni Request for Quo Single Stage - On 2020-09- 2020-11- 2020-12- IDA / D4340 afety net for the poor in se Post Limited 3,400.00 0.00 mplement tures de bureau, consompti tations e Envelope 22 10 10 lected rural areas ation bles informatiques repartis en deux lots. DRA12 DC FRN 20001 / A Component 1: Building a s Pending I cquisition de divers matéri Request for Quo Single Stage - On 2020-09- 2020-11- 2020-12- IDA / D4340 afety net for the poor in se Post Limited 35,800.00 0.00 mplement els, matériaux et des intra tations e Envelope 22 03 03 lected rural areas ation nts pour les bénéficiaires d u programme TMDH ET FSP DRK_DC_FRN_BENEF_FSP/ Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-11- 2021-01- TMDH20 / Acquisition de di IDA / D4340 afety net for the poor in se Post Limited 9,400.00 0.00 mplement tations e Envelope 22 03 02 vers goodies lected rural areas ation DRK_DC_FRN_EP_FSP/TMD Component 1: Building a s Pending I H20 / Acquisition des matér Request for Quo Single Stage - On 2020-09- 2020-11- 2021-01- IDA / D4340 afety net for the poor in se Post Limited 98,000.00 0.00 mplement iaux divers pour l'améliorat tations e Envelope 22 03 02 lected rural areas ation ion des espaces physiques TMDH et FSP DRT11 DC FR MAT 20001 / Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-10- 2021-03- Acquisition des intrants agr IDA / D4340 afety net for the poor in se Post Limited 6,329.00 0.00 mplement tations e Envelope 21 30 31 icoles pour les ménages bé lected rural areas ation néficiaires du TMDH. DRT11 DC FR SEC 20001 / Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-11- 2020-12- Acquisition de fournitures d IDA / D4340 afety net for the poor in se Post Limited 592.00 0.00 mplement tations e Envelope 27 05 05 iverses pour la sécurisation lected rural areas ation du bureau du FID DRT12 DC FR LOTS 20001 Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-10- 2020-11- 2020-12- / Acquisition de divers good IDA / D4340 afety net for the poor in se Post Limited 9,610.00 0.00 mplement tations e Envelope 01 11 11 ies pour le TMDH lected rural areas ation DG20_DC_SECURITE_PANN Component 1: Building a s Request for Quo Single Stage - On 2020-11- 2021-03- 2020-12- 2021-06- 2021-01- EAU_2036 / Acquisition pan IDA / D4340 afety net for the poor in se Post Limited 2,000.00 3,284.39 Signed tations e Envelope 02 24 28 25 27 neaux d'indication lumineu lected rural areas x DRF11 DC_VIDEO 2001 / T Component 1: Building a s Request for Quo Single Stage - On 2020-11- 2020-12- 2020-12- 2020-12- 2021-01- ournage video succes story IDA / D4340 afety net for the poor in se Post Limited 4,500.00 172.33 Signed tations e Envelope 01 02 20 16 19 du programme TMDH et FS lected rural areas P DRF 12_DC_FRN_BENEF 20 Component 1: Building a s Request for Quo Single Stage - On 2020-10- 2020-11- 2020-12- 2020-11- 2021-01- 03 / Acquisition des divers IDA / D4340 afety net for the poor in se Post Limited 8,450.00 7,234.73 Signed tations e Envelope 28 11 15 28 14 goodies pour les Mères Lea lected rural areas ders et CPS DG20_DC_KIT_FRNT_2039 Component 1: Building a s Request for Quo Single Stage - On 2020-11- 2021-06- 2021-01- 2021-07- 2021-02- / Acquisition de divers four IDA / D4340 afety net for the poor in se Post Limited 65,000.00 24,599.51 Signed tations e Envelope 06 02 08 24 07 nitures et petits matériels lected rural areas DG20_DC_PNEUS_GROUPE Component 1: Building a s Request for Quo Single Stage - On 2020-10- 2020-10- 2020-12- 2021-03- 2021-03- _2040 / Acquisition groupé IDA / D4340 afety net for the poor in se Post Limited 70,000.00 21,930.04 Signed tations e Envelope 28 23 30 04 30 e des enveloppes pneumati lected rural areas ques DG20_DC_GOODIES2021_ Component 1: Building a s Request for Quo Single Stage - On 2020-11- 2020-11- 2020-12- 2021-01- 2021-01- 2008 / Acquisition de goodi IDA / D4340 afety net for the poor in se Post Limited 5,000.00 9,414.12 Signed tations e Envelope 12 12 22 07 06 es pour 2021 lected rural areas DG20_ED_SUPPL_NUT_204 1 / Acquisition de suppléme Component 1: Building a s 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-03- nt nutritionnel (Plumpy Sup IDA / D4340 afety net for the poor in se Post Direct Selection Direct 800,000.00 586,813.42 Signed 12 12 12 06 03 25 03 ) destinés aux régions victi lected rural areas mes de la Malnutrition Aigü e Modérée (MAM) DG20_ED_SUPPL_NUT_204 2 / Acquisition de suppléme Component 1: Building a s 2020-10- 2020-10- 2020-10- 2020-10- 2020-11- 2020-11- 2020-11- nt nutritionnel (Plumpy Sup IDA / D4340 afety net for the poor in se Post Direct Selection Direct 5,000.00 3,738.81 Signed 25 20 25 20 08 03 15 ) destiné aux régions victi lected rural areas mes de la Malnutrition Aigü e Modérée (MAM) DG20_DC_FRNT_2038 / Ac Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-11- 2021-01- 2021-09- quisition de fournitures de IDA / D4340 afety net for the poor in se Post Limited 30,000.00 0.00 mplement tations e Envelope 19 21 15 bureau lected rural areas ation DG20_DC_PRODENTRET_2 Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-11- 2021-01- 2021-09- 040 / Acquisition de produit IDA / D4340 afety net for the poor in se Post Limited 10,000.00 0.00 mplement tations e Envelope 19 21 15 s d'entretien lected rural areas ation DG20_DC_CONSINFO_2039 Component 1: Building a s Request for Quo Single Stage - On 2020-11- 2020-12- 2021-01- 2021-03- 2021-09- / Acquisition de consomptib IDA / D4340 afety net for the poor in se Post Limited 90,000.00 115,671.56 Signed tations e Envelope 19 11 21 31 15 les informatiques lected rural areas DRU12MPE21001 / Acquisi Component 1: Building a s tion des outils et matériels Request for Quo Single Stage - On 2020-12- 2021-09- 2021-02- 2022-03- 2021-04- IDA / D4340 afety net for the poor in se Post Limited 13,400.00 20,910.86 Signed pour Espaces physiques en tations e Envelope 15 21 09 01 10 lected rural areas DPEI des Bénéficiaires TMD H - Betioky Sud et Toliara II DRA12 DC FRN 20006 / A Component 1: Building a s Pending I cquisition de divers matéri Request for Quo Single Stage - On 2020-12- 2021-01- 2021-07- IDA / D4340 afety net for the poor in se Post Limited 8,600.00 0.00 mplement els et des intrants pour les tations e Envelope 07 20 19 lected rural areas ation bénéficiaires du programm e TMDH ET FSP DG20_DC_TPE_CARTE_204 1 / Acquisition de TPE et ca Component 1: Building a s Request for Quo Single Stage - On 2020-12- 2020-12- 2021-01- 2021-02- 2021-02- rtes destinés aux bénéficiai IDA / D4340 afety net for the poor in se Post Limited 95,000.00 63,291.34 Signed tations e Envelope 02 11 13 24 12 res et sites pilotes pour le lected rural areas nouveau mécanisme de pai ements DRF20_DC FRN_CABLAGE RESEAUX / Acquisition de f Component 1: Building a s Request for Quo Single Stage - On 2020-12- 2020-12- 2021-01- 2020-12- 2021-01- ournitures et accessoires p IDA / D4340 afety net for the poor in se Post Limited 1,400.00 1,925.64 Signed tations e Envelope 08 03 13 13 18 our les réseaux téléphoniq lected rural areas ue et internet_ Nouveau bu reau Antenne Ambositra DRF_DC_FRN ALPHA_2004 / Acquisition des fourniture Component 1: Building a s s pour le centre Alphabétis Request for Quo Single Stage - On 2021-01- 2021-01- 2021-02- 2021-02- 2021-03- IDA / D4340 afety net for the poor in se Post Limited 5,200.00 1,241.64 Signed ation du programme FSP Is tations e Envelope 13 27 04 26 06 lected rural areas andra et Manandriana ainsi que du programme TMDH Ambohimahasoa DG_DC_MOB_ANTENNES_2 Component 1: Building a s 101 / Acquisition de mobilie Request for Quo Single Stage - On 2021-01- 2021-03- 2021-03- 2021-06- 2021-04- IDA / D4340 afety net for the poor in se Post Limited 10,000.00 9,985.73 Signed rs de bureau destinés à la tations e Envelope 30 04 20 17 19 lected rural areas mise en place des antenne s du FID DG_DC_GROUPE_ELECT_2 Component 1: Building a s 103 / Acquisition d'un grou Request for Quo Single Stage - On 2021-01- 2021-06- 2021-03- 2021-08- 2021-05- IDA / D4340 afety net for the poor in se Post Limited 15,000.00 9,925.63 Signed pe électrogène destiné à l' tations e Envelope 30 23 20 17 19 lected rural areas Antenne du FID à Ambositr a DRA12 DC FRN 20009 / A Component 1: Building a s Pending I cquisition de diverses fourn Request for Quo Single Stage - On 2021-01- 2021-03- 2021-03- IDA / D4340 afety net for the poor in se Post Limited 35,800.00 0.00 mplement itures pour les bénéficiaires tations e Envelope 27 01 31 lected rural areas ation du programme TMDH ET FS P réparties en six (06) lots DRA13DC FRNTALPHABETI Component 1: Building a s Pending I SATION / Acquisition de fou Request for Quo Single Stage - On 2021-01- 2021-02- 2021-03- IDA / D4340 afety net for the poor in se Post Limited 1,700.00 0.00 mplement rnitures scolaires pour l'al tations e Envelope 27 18 20 lected rural areas ation phabétisation_Lot unique DG_DC_ANTIVIRUS_2104 / Component 1: Building a s Request for Quo Single Stage - On 2021-02- 2021-02- 2021-03- 2021-04- 2021-04- 2022-01- Acquisition de logiciels anti IDA / D4340 afety net for the poor in se Post Limited 10,000.00 5,799.26 Completed tations e Envelope 06 15 27 20 26 20 virus lected rural areas DG_DC_TPE_NFC_21007 / Acquisition de TPE et carte Component 1: Building a s Request for Quo Single Stage - On 2021-02- 2021-02- 2021-04- 2021-05- 2021-05- s destinés aux bénéficiaires IDA / D4340 afety net for the poor in se Post Limited 40,000.00 38,134.05 Signed tations e Envelope 22 26 05 15 05 et sites pilotes pour le nouv lected rural areas eau mécanisme de paieme nts DG_DC_APPAREILS_TELEP Component 1: Building a s H_21002 / Acquisition de p Request for Quo Single Stage - On 2021-02- 2021-03- 2021-04- 2021-06- 2021-05- IDA / D4340 afety net for the poor in se Post Limited 7,500.00 1,818.17 Signed ostes téléphoniques fixes, tations e Envelope 20 24 10 19 10 lected rural areas autocom avec standard DG_DC_MAT_INFO_21003 / Component 1: Building a s Request for Quo Single Stage - On 2021-03- 2021-05- 2021-07- 2021-06- Acquisition de matériels inf IDA / D4340 afety net for the poor in se Post Open - National 95,000.00 92,531.22 Signed tations e Envelope 13 03 14 02 ormatiques répartis en deu lected rural areas x (02) lots DG_21011_EQPT_INFO / Ac Component 1: Building a s Request for Quo Single Stage - On 2021-05- 2021-06- 2021-10- 2021-07- 2021-11- quisition de divers équipem IDA / D4340 afety net for the poor in se Post Open - National 50,000.00 27,042.02 Signed tations e Envelope 05 25 30 25 25 ents informatiques répartis lected rural areas en 4 lots DG_21014_DC_APN / Acqui Component 1: Building a s Request for Quo Single Stage - On 2021-05- 2021-07- 2021-10- 2021-08- 2021-10- sition d'appareil photo num IDA / D4340 afety net for the poor in se Post Open - National 5,000.00 5,291.88 Completed tations e Envelope 22 03 02 17 20 érique avec accessoires po lected rural areas ur le FID DRF_21003_DC_ACHAT PN Component 1: Building a s Request for Quo Single Stage - On 2021-05- 2021-07- 2021-07- 2021-07- EUS / ACHAT DES PNEUS B IDA / D4340 afety net for the poor in se Post Open - National 5,882.35 4,950.13 Signed tations e Envelope 11 06 27 26 F ANTI-BOUES lected rural areas DRU_21001_DC_CONCOUR SMEILLEURSGT / Acquisitio n des lots pour le concours Component 1: Building a s Request for Quo Single Stage - On 2021-06- 2022-04- 2021-07- 2022-05- 2021-08- 2022-06- meilleurs groupes de travai IDA / D4340 afety net for the poor in se Post Open - National 14,500.00 1,645.98 Completed tations e Envelope 19 19 24 04 23 17 l, Mères Leaders, AVEC, ad lected rural areas optant, et meilleur CGE po ur les 3 interventions du FS P- Ankazoabo sud répartis en deux (02) lots. DRK_21005_DC_ALPH_TMD Component 1: Building a s Pending I HFSP / Acquisition de fourni Request for Quo Single Stage - On 2021-06- 2021-08- 2021-10- IDA / D4340 afety net for the poor in se Post Open - National 7,750.00 0.00 mplement tures et outillages en deux tations e Envelope 15 10 09 lected rural areas ation lots pour la formation d'alp habétisation TMDH et FSP Page 3 DRK_21001_DC_TROPH_M EILLEURE / Acquisition des Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-06- 2021-07- 2021-08- divers trophées réparties e IDA / D4340 afety net for the poor in se Post Open - National 5,700.00 0.00 mplement tations e Envelope 15 20 19 n deux (02) lots pour les m lected rural areas ation eilleurs groupes, adoptant, site IP, site AVEC DRF_21006_DC_ALPHA / A Component 1: Building a s Pending I chat des Fournitures pour l Request for Quo Single Stage - On 2021-06- 2021-08- 2021-08- IDA / D4340 afety net for the poor in se Post Limited 4,864.86 0.00 mplement es nouveaux centres d'Alph tations e Envelope 09 04 24 lected rural areas ation abétisation réparties en 02 Lots FSP et TMDH DRA_21004_DC_CONCOUR S MEILLEURS GROUPE / Ac quisition des lots pour le co Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-06- 2021-07- 2021-08- ncours des meilleurs grou IDA / D4340 afety net for the poor in se Post Open - National 5,670.00 0.00 mplement tations e Envelope 21 26 25 pe AVEC - ML - RC - ALPH lected rural areas ation ABETISEURS - adoptants de s bénéficiaires TMDH - FSP , repartis en quatre (04) Lo ts DRT_21004_DC_TROPH_M EILLEUR_FSP / Acquisition d Component 1: Building a s Pending I e lots pour les concours org Request for Quo Single Stage - On 2021-07- 2021-08- 2021-09- IDA / D4340 afety net for the poor in se Post Open - National 19,962.16 0.00 mplement anisés au niveau des Group tations e Envelope 05 12 11 lected rural areas ation es de travail FSP dans les D istricts d'Antanifotsy et d'Ar ivonimamo, répartis en qua tre (04) lots. DG_21015_CONSOM_INFO Component 1: Building a s Request for Quo Single Stage - On 2021-06- 2021-08- 2021-11- 2021-12- / Acquisition de consomptib IDA / D4340 afety net for the poor in se Post Open - National 95,000.00 82,066.21 Signed tations e Envelope 21 16 03 31 les informatiques lected rural areas DG_DC21016_FRNT_ENTR Component 1: Building a s Request for Quo Single Stage - On 2021-06- 2021-08- 2021-11- 2022-02- ET / Acquisition de fournitu IDA / D4340 afety net for the poor in se Post Open - National 50,000.00 4,191.27 Signed tations e Envelope 23 18 10 14 res de bureau et produits d lected rural areas 'entretien DG20_DC_BOITES_PHARM Component 1: Building a s Request for Quo Single Stage - On 2020-11- 2020-11- 2021-01- 2021-03- 2021-02- A_2034 / Acquisition de boî IDA / D4340 afety net for the poor in se Post Limited 4,000.00 3,498.26 Signed tations e Envelope 04 16 06 11 20 tes à pharmacie / FIAVOTA lected rural areas DRP82_DC_INTRANTAGRI2 Component 1: Building a s Request for Quo Single Stage - On 2021-07- 2022-06- 2021-08- 2022-05- 2021-10- 2022-07- 002 / Acquisition des intran IDA / D4340 afety net for the poor in se Post Open - National 23,600.00 18,735.74 Completed tations e Envelope 03 07 06 28 05 28 ts agricoles pour les group lected rural areas es des ménages DRA_21005_DC_ALPHA TM Component 1: Building a s Pending I DH / Achat des Fournitures Request for Quo Single Stage - On 2021-07- 2021-08- 2022-02- IDA / D4340 afety net for the poor in se Post Open - National 2,220.00 0.00 mplement pour les nouveaux centres tations e Envelope 19 27 23 lected rural areas ation d'Alphabétisation TMDH ET FSP DRP_21008_DC_IMPRES D UPLIC OUTIL MACC / Presta Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-07- 2021-08- 2021-10- tion pour l'impression et du IDA / D4340 afety net for the poor in se Post Open - National 21,700.00 0.00 mplement tations e Envelope 03 08 07 plication des outils des mes lected rural areas ation ures d'accompagnement p our le second semestre DRP_21006_DC_INTRANT Component 1: Building a s Pending I CUMA / Acquisition des se Request for Quo Single Stage - On 2021-07- 2021-08- 2021-10- IDA / D4340 afety net for the poor in se Post Open - National 9,300.00 0.00 mplement mences en Cultures Maraîc tations e Envelope 03 07 06 lected rural areas ation hères pour les groupes des ménages bénéficiaires DG_21018_UNOPS_VEHICU Component 2: Strengtheni 2021-08- 2021-08- 2021-08- 2021-08- 2021-10- 2021-08- 2022-01- LES / Acquisition de véhicul IDA / D4340 ng safety net administratio Post Direct Selection Direct 400,000.00 351,832.68 Signed 02 10 16 10 04 19 02 es de supervision auprès d n, monitoring and social ac e l'UNOPS countability DG_21020_AON_EQPT_INF Component 2: Strengtheni O_BUR / Acquisition de mat ng safety net administratio Request for Bid Single Stage - On 2021-08- 2021-09- 2021-08- 2021-09- 2021-11- 2021-10- 2022-01- 2021-11- 2022-03- 2022-01- 2022-04- IDA / D4340 Post Open - National 200,000.00 113,864.58 Signed ériels informatiques et bure n, monitoring and social ac s e Envelope 21 29 26 23 02 21 21 18 14 17 24 autiques _ Marchés à lots countability multiples DG_21021_DC_ACC_INFO / Component 2: Strengtheni Acquisition de diverses co ng safety net administratio Request for Quo Single Stage - On 2021-08- 2021-10- 2022-03- 2021-11- IDA / D4340 Post Open - National 40,000.00 50,167.83 Signed mposantes et pièces de rec n, monitoring and social ac tations e Envelope 14 02 04 16 hanges informatiques _ Ma countability rchés à lots multiples DRP_21009_DC_FOURNALP HATMDH / Achat des fourni tures pour les nouveaux ce Component 1: Building a s Request for Quo Single Stage - On 2021-08- 2022-05- 2021-10- 2022-03- 2021-12- 2022-04- ntres Alphabétisations TMD IDA / D4340 afety net for the poor in se Post Open - National 7,900.00 4,012.86 Completed tations e Envelope 21 20 16 24 15 20 H dans les districts Amboas lected rural areas ary sud, Ambovombe, Tsih ombe, Beloha et Bekily, Ré gion Androy et Anosy. DG_21031_DC_FOURN_DIV Component 1: Building a s / Acquisition de diverses fo Request for Quo Single Stage - On 2021-09- 2021-11- 2022-01- 2022-01- IDA / D4340 afety net for the poor in se Post Open - National 65,000.00 24,065.23 Signed urnitures pour les activités tations e Envelope 09 18 18 17 lected rural areas AVEC, MACC, DPEI de la DT M. Marchés à lots multiples . DG_21032_ED_SUPPL_NUT Component 1: Building a s / Fourniture et livraison de 2021-08- 2021-08- 2021-08- 2021-08- 2021-09- 2021-10- 2021-12- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 400,000.00 412,525.40 Signed supplément nutritionnel po 20 23 20 24 24 01 23 lected rural areas ur la prise en charge des e nfants malnutri dans le Sud DRT_21015_DC_ACHATS_K ITS_MACC_FSP / Achat de K its DPEI, AVEC, CdP et alph abétisation pour les 6 000 Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-09- 2021-11- 2022-05- nouveaux bénéficiaires FSP IDA / D4340 afety net for the poor in se Post Open - National 15,200.00 0.00 mplement tations e Envelope 30 11 30 du District d'Arivonimamo lected rural areas ation FA2 rajout de 6000 nouvea ux bénéficiaires et TMDH d ans le District de Faratsiho répartis en huit (08) lots Acquisition de fournitures p DRT_21016_DC_ACHAT_LO Component 1: Building a s Under Impl Request for Quo Single Stage - On 2021-09- 2021-10- 2021-12- TS_ADOPTANTS_TMDH / Ac IDA / D4340 afety net for the poor in se Post Open - National 3,100.00 0.00 ementatio tations e Envelope 15 27 26 hat de Lots Meilleurs Adopt lected rural areas n ants - RC - CPS DRP_21011_DC_KIT AVEC / Acquisition des kits pour le s nouveaux groupes d'Asso Component 1: Building a s Pending I ciation Villageoise d’Épargn Request for Quo Single Stage - On 2021-09- 2021-10- 2021-12- IDA / D4340 afety net for the poor in se Post Open - National 1,500.00 0.00 mplement e et de Crédit dans la zone tations e Envelope 13 27 26 lected rural areas ation d'intervention du program me TMDH dans les 05 distri cts (Amboasary, Ambovom be, Beloha, Tshombe et Be kily), en un lot DRF_21013_DC_CADRE_IM PRESSION_TMDH_FSP / Acq Component 1: Building a s Under Impl uisition des cadres vitrées Request for Quo Single Stage - On 2021-09- 2022-05- 2021-11- 2021-11- IDA / D4340 afety net for the poor in se Post Open - National 2,400.00 0.00 ementatio avec impression des certifi tations e Envelope 25 12 05 25 lected rural areas n cats pour les meilleurs bén éficiaires, ML, CPS, RC, AGE C TMDH et FSP DRF_21014_DC_SEMENCE Component 1: Building a s Pending I S_TMDH_FSP / Acquisition d Request for Quo Single Stage - On 2021-09- 2021-11- 2021-12- IDA / D4340 afety net for the poor in se Post Open - National 10,400.00 0.00 mplement es lots de semences, répart tations e Envelope 27 11 01 lected rural areas ation ies en 02 lots pour les mén ages TMDH et FSP DRF_21015_DC_MATÉRIEL S AGRI_TMDH_FSP / Acquisi Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-09- 2021-11- 2021-11- tion des matériels et petits IDA / D4340 afety net for the poor in se Post Open - National 50,000.00 0.00 mplement tations e Envelope 25 09 29 outillages pour les bénéfici lected rural areas ation aires FSP et TMDH, répartie s en 03 lots DRF_21016_DC_JEUNES PL Component 1: Building a s Under Impl ANTS _TMDH_FSP / Acquisit Request for Quo Single Stage - On 2021-09- 2021-11- 2021-11- IDA / D4340 afety net for the poor in se Post Open - National 85,000.00 0.00 ementatio ion des Intrants _jeunes pla tations e Envelope 25 09 29 lected rural areas n nts pour les bénéficiaires T MDH et FSP DRA_21013_AO_MAT ET O Component 1: Building a s Pending I UTI AGRI _FSP / Acquisition Request for Bid Single Stage - On 2021-09- 2021-09- 2021-10- 2021-11- 2021-12- 2022-01- IDA / D4340 afety net for the poor in se Post Open - National 112,900.00 0.00 mplement des matériels et petits outil s e Envelope 20 27 27 08 02 16 lected rural areas ation lages agricoles pour les bé néficiaires FSP DRA_21015_DC_CONFECTI ON TE SHIRT _FSP / Acqui Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-09- 2021-11- 2022-01- sition de Tee SHIRT avec IDA / D4340 afety net for the poor in se Post Open - National 32,300.00 0.00 mplement tations e Envelope 24 08 07 message positif pour les lected rural areas ation bénéficiaires du programm e FSP DRT_21027_AON_INTR_AG Component 1: Building a s Under Impl RI_TMDH_FSP / Acquisition Request for Bid Single Stage - On 2021-10- 2022-02- 2021-10- 2022-02- 2021-11- 2022-03- 2021-11- 2021-12- 2022-03- IDA / D4340 afety net for the poor in se Post Open - National 132,100.00 0.00 ementatio d'intrants agricoles réparti s e Envelope 11 11 16 23 15 14 25 17 31 lected rural areas n e en trois (03) lots pour FS P et TMDH DRA_21012_DC_JEUNES PL Component 1: Building a s ANTS _FSP / Acquisition des Request for Quo Single Stage - On 2021-09- 2022-08- 2021-11- 2022-06- 2021-12- IDA / D4340 afety net for the poor in se Post Open - National 116,300.00 15,256.94 Signed Intrants _jeunes plants , ar tations e Envelope 25 16 09 16 09 lected rural areas bre fruitiers et semences pour les bénéficiaires FSP DG_21036_DC_PNEUMATI Component 3: Building the QUES / Acquisition d'envelo institutional capacity for c Request for Quo Single Stage - On 2021-10- 2021-12- 2022-03- 2022-06- ppes pneumatiques pour le IDA / D4340 oordination, monitoring an Post Open - National 80,000.00 93,818.71 Signed tations e Envelope 16 14 08 12 s véhicules du FID (Directio d evaluation of the social p n Générale et Direction Int rotection syst em errégionales) DG_21037_DC_RESEAUX_B Component 3: Building the UREAUX / Fourniture de ma institutional capacity for c Request for Quo Single Stage - On 2021-10- 2021-12- 2022-02- 2022-01- tériels, équipements et inst IDA / D4340 oordination, monitoring an Post Open - National 45,000.00 18,756.41 Signed tations e Envelope 23 11 03 25 allation de réseaux filaires d evaluation of the social p dans les nouveaux bureaux rotection syst em du FID répartis en trois (03) lots. DRT_21029_AON_MAT_AG Component 1: Building a s Under Impl RI_TMDH_FSP / Acquisition Request for Bid Single Stage - On 2021-10- 2022-02- 2021-10- 2022-02- 2021-11- 2021-11- 2021-12- 2022-03- IDA / D4340 afety net for the poor in se Post Open - National 215,300.00 0.00 ementatio de matériels agricoles répa s e Envelope 11 11 16 23 15 25 17 31 lected rural areas n rtie en deux (02) lots pour FSP et TMDH DRK_21011_DC_INTRANTS Component 1: Building a s Under Impl _AGRI_FSP / Acquisition des Request for Quo Single Stage - On 2021-10- 2021-12- 2022-01- IDA / D7740 afety net for the poor in se Post Open - National 64,100.00 0.00 ementatio Intrants agricoles réparti e tations e Envelope 10 05 04 lected rural areas n n deux lots pour le FSP DRT_21030_DC_TROPH_M EILLEUR_01_FSP / Acquisiti on de lots pour la remise d Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-11- 2021-12- 2022-02- e trophées des concours de IDA / D4340 afety net for the poor in se Post Open - National 600.00 0.00 mplement tations e Envelope 04 16 14 s activités FSP dans les Dist lected rural areas ation ricts d'Antanifotsy et d'Ariv onimamo, RELANCE du lot 01 suite à des offres infruct ueuses DRK_21012_AO_MATERIEL Component 1: Building a s Request for Bid Single Stage - On 2021-11- 2022-01- 2021-11- 2022-01- 2022-02- 2022-01- 2022-05- 2022-03- 2022-09- S _AGRI_FSP / Acquisition d IDA / D7740 afety net for the poor in se Post Open - National 350,000.00 0.00 Signed s e Envelope 15 14 20 01 14 31 09 07 03 es matériels agricoles FSP lected rural areas et TMDH DRU_21010_AON_MAT_AG Component 1: Building a s Under Impl RI_TMDH_FSP / Acquisition Request for Bid Single Stage - On 2021-10- 2022-03- 2021-10- 2022-05- 2021-11- 2022-04- 2021-12- 2022-04- 2021-12- 2022-06- IDA / D4340 afety net for the poor in se Post Open - National 249,000.00 0.00 ementatio de matériels agricoles rép s e Envelope 25 02 30 21 09 01 09 01 23 21 lected rural areas n artie en trois (03) lots pour FSP et TMDH DRU_21011_DC_INTR_AGR Component 1: Building a s Under Impl I_TMDH_FSP / Acquisition d' Request for Quo Single Stage - On 2021-10- 2022-05- 2021-12- 2021-12- IDA / D4340 afety net for the poor in se Post Open - National 91,000.00 0.00 ementatio intrants agricoles répartie tations e Envelope 30 21 04 31 lected rural areas n en deux (02) lots pour FSP et TMDH DRA_21021_AO_MATERIEL _AGRI_SEMENCE _TMDH / A Component 1: Building a s Pending I Request for Bid Single Stage - On 2021-11- 2021-11- 2021-12- 2022-01- 2022-01- 2022-03- cquisition des matériels ,pe IDA / D4340 afety net for the poor in se Post Open - National 258,000.00 0.00 mplement s e Envelope 15 18 20 04 27 18 tits outillages agricoles et s lected rural areas ation emences pour les bénéfici aires TMDH DRK_21013_DC_KIT_AVEC Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-11- 2022-01- 2022-03- _TMDH / Acquisition fournit IDA / D4340 afety net for the poor in se Post Open - National 872.00 0.00 mplement tations e Envelope 20 03 04 ures pour les nouvelles AV lected rural areas ation EC_TMDH Vohipeno DRK_21014_DC_INTRANTS Component 1: Building a s _AGRI_TMDH / Acquisition d Request for Bid Single Stage - On 2021-11- 2022-07- 2021-11- 2021-12- 2022-03- 2021-12- 2022-05- 2022-01- 2022-05- IDA / D4340 afety net for the poor in se Post Open - National 80,650.00 0.00 Signed es Intrants agricoles pour s e Envelope 15 18 20 20 02 30 09 21 05 lected rural areas le pack de sortie des ména ges bénéficiaires TMDH DRK_21015_DC_CONFECT Component 1: Building a s T-SHIRT_TMDH / FSP / Conf Request for Quo Single Stage - On 2021-11- 2022-01- 2022-03- IDA / D4340 afety net for the poor in se Post Open - National 34,310.00 0.00 Signed ection de T-shirt pour les tations e Envelope 19 03 04 lected rural areas bénéficiaires TMDH et pou FSP DG_21044_UN_VEHICULES Component 1: Building a s 2021-11- 2022-01- 2021-12- 2022-01- 2022-01- 2022-02- 2022-04- SUPERVISION / Acquisition IDA / D7740 afety net for the poor in se Post Direct Selection Direct 1,000,000.00 938,976.34 Signed 26 31 10 31 28 17 28 de véhicules de supervision lected rural areas DRA_21025_DC_IMPRESSI Component 1: Building a s Pending I ON ET PHOTOCOPIE _ / Im Request for Quo Single Stage - On 2021-11- 2022-01- 2022-07- IDA / D4340 afety net for the poor in se Post Open - National 3,200.00 0.00 mplement pression et multiplication d tations e Envelope 27 06 05 lected rural areas ation e divers outils de travail DG_21046_AON_FRNT_MA CC_FSP / Acquisition de div erses fournitures et access Component 1: Building a s Request for Bid Single Stage - On 2021-12- 2022-01- 2021-12- 2022-01- 2022-02- 2022-02- 2022-03- 2022-03- 2022-06- 2022-05- oires pour les Mesures d'Ac IDA / D4340 afety net for the poor in se Post Open - National 150,000.00 182,810.77 Signed s e Envelope 03 11 10 21 15 18 31 11 04 10 compagnement dans le cad lected rural areas re du Programme Filets Soc iaux Productifs (FSP) répart is en cinq (05) lots DRU_21025_DC_FRNT_ENT Component 1: Building a s Request for Quo Single Stage - On 2021-12- 2022-05- 2022-02- 2022-05- 2022-08- RET / Acquisition de fournit IDA / D7740 afety net for the poor in se Post Open - National 5,800.00 2,593.96 Signed tations e Envelope 14 31 08 05 07 ures de bureau et produits lected rural areas d'entretien DG_21051_DC_MOBILIERS Component 1: Building a s / Acquisition de mobiliers d Request for Quo Single Stage - On 2021-12- 2022-02- 2022-02- 2022-05- 2022-03- 2022-07- IDA / D4340 afety net for the poor in se Post Open - National 50,000.00 76,487.32 Completed e bureau destinés à la mise tations e Envelope 27 16 07 21 24 06 lected rural areas en place de nouvelles Direc tions Interrégionales DG_21052_DC_EQUIPMENT S_BUREAU / Acquisition de Component 1: Building a s matériels et équipements d Request for Quo Single Stage - On 2021-12- 2022-04- 2022-02- 2022-06- 2022-03- IDA / D4340 afety net for the poor in se Post Open - National 10,000.00 29,099.53 Signed estinés à la mise en place tations e Envelope 27 05 07 03 24 lected rural areas de nouvelles directions inte rrégionales répartis en deu x (02) lots DG_21054_DC_RESEAU_DI R_ANTSIRABE / Fourniture Component 1: Building a s Request for Quo Single Stage - On 2021-12- 2022-02- 2022-02- 2022-06- 2022-03- 2022-07- de matériels, équipements IDA / D4340 afety net for the poor in se Post Open - National 15,000.00 12,811.72 Completed tations e Envelope 24 16 11 11 28 06 et installation de réseaux fi lected rural areas laires dans les nouveaux b ureaux du FID_Antsirabe DRF_21028_AON_ ACHATS Component 1: Building a s Under Impl _LOTS_MATÉRIELS / Achats Request for Bid Single Stage - On 2021-12- 2022-02- 2021-12- 2022-01- 2022-03- 2022-02- 2022-05- 2022-03- 2022-04- IDA / D4340 afety net for the poor in se Post Open - National 360,000.00 0.00 ementatio des Lots petits matériels et s e Envelope 20 08 25 24 16 08 20 04 03 lected rural areas n outillages pour les bénéfici aires TMDH et FSP DRT_21032_DC_ACHATS_K ITS_MACC_FSP / [RELANCE] Achat de Kits DPEI, AVEC, C dP et alphabétisation pour Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-01- 2022-02- 2022-02- 2022-03- les 6 000 nouveaux bénéfic IDA / D4340 afety net for the poor in se Post Open - National 1,900.00 0.00 ementatio tations e Envelope 04 25 15 27 iaires FSP du District d'Ariv lected rural areas n onimamo FA2 rajout de 60 00 nouveaux bénéficiaires et TMDH dans le District d e Faratsiho répartis en deu x lots DG_21058_OUTILLAGES D Component 1: Building a s E BORD / Acquisition d'outil Request for Quo Single Stage - On 2022-01- 2022-03- 2022-02- 2022-06- 2022-04- 2022-06- IDA / D4340 afety net for the poor in se Post Open - National 30,000.00 8,493.30 Completed lages et équipements de sé tations e Envelope 08 08 26 03 27 17 lected rural areas curité pour les véhicules de supervisions DRA_21027_DC_FRNT_ENT Component 1: Building a s Request for Quo Single Stage - On 2022-02- 2022-08- 2022-03- 2022-07- 2023-03- RET / Acquisition de fournit IDA / D4340 afety net for the poor in se Post Open - National 9,800.00 6,837.74 Signed tations e Envelope 14 16 28 14 28 ures de bureau et produits lected rural areas d'entretien DRF_21026_DC_FRNT_ENT Component 1: Building a s Pending I Request for Quo Single Stage - On 2022-02- 2022-03- 2022-04- RET / Achat des produits d' IDA / D4340 afety net for the poor in se Post Open - National 4,800.00 0.00 mplement tations e Envelope 05 25 24 entretien lected rural areas ation DRF_21027_DC_FRNT_BUR EAU / Achat des fournitures Component 1: Building a s Pending I Request for Quo Single Stage - On 2022-02- 2022-03- 2022-04- de bureau, fourniture de fo IDA / D4340 afety net for the poor in se Post Open - National 15,900.00 0.00 mplement tations e Envelope 05 25 24 rmation des Acteurs locaux lected rural areas ation et consommable informatiq ue DG_21056_DC_FRNT_BUR_ ENTRET_2022 / Acquisition Component 1: Building a s de fournitures de bureau et Request for Quo Single Stage - On 2022-02- 2022-03- 2022-03- 2022-06- 2022-12- 2022-06- IDA / D4340 afety net for the poor in se Post Open - National 30,000.00 15,395.69 Completed produits d'entretien de l'an tations e Envelope 07 08 21 09 31 22 lected rural areas née 2022 pour la Direction Générale répartis en quatr e (04) lots DRT_21033_DC_FRNT_ENT RET_CONS / Acquisition de Component 1: Building a s fournitures de bureau, de p Request for Quo Single Stage - On 2022-02- 2022-06- 2022-03- 2022-08- 2022-12- IDA / D4340 afety net for the poor in se Post Open - National 9,600.00 7,226.60 Signed roduits d'entretien et de co tations e Envelope 17 10 31 17 31 lected rural areas nsommables informatiques pour l'année 2022, répartie en deux (02) lots DRA_21028_DC_CONSOMA Component 1: Building a s BLE_ INFORMATIQUE / Acqu Request for Quo Single Stage - On 2022-02- 2022-08- 2022-03- 2022-07- 2023-03- IDA / D4340 afety net for the poor in se Post Open - National 11,800.00 5,100.99 Signed isition de fournitures de co tations e Envelope 14 16 28 09 28 lected rural areas nsommable informatique ( cartouche d' encre et toner ) DG_22001_DC_GROUPES_ Component 1: Building a s ELECTROGENES / Acquisitio Request for Quo Single Stage - On 2022-02- 2022-04- 2022-04- 2022-06- 2022-06- 2022-07- IDA / D4340 afety net for the poor in se Post Open - National 75,000.00 65,977.00 Completed n de groupes électrogènes tations e Envelope 22 05 05 03 04 16 lected rural areas pour le FID répartis en quat re (04) lots DRF_22001_DC_ACQUISITI Component 1: Building a s Under Impl ON SEMENCES_TMDH_F / R Request for Quo Single Stage - On 2022-02- 2022-05- 2022-03- 2022-04- IDA / D4340 afety net for the poor in se Post Open - National 10,500.00 0.00 ementatio elance Achat des semence tations e Envelope 08 12 23 02 lected rural areas n s pour les bénéficiaires TM DH et FSP DG_22006_DC_DISTRIBUT Component 1: Building a s Under Impl EUR_EAU_BUREAU / Acquisi Request for Quo Single Stage - On 2022-02- 2022-04- 2022-04- 2022-06- IDA / D4340 afety net for the poor in se Post Open - National 5,000.00 0.00 ementatio tion de distributeurs d'eau tations e Envelope 21 12 04 03 lected rural areas n chaude et froide pour les n ouveaux bureaux du FID DRB_22004_DC_FRNT_ENT R_2022 / Acquisition de fou Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-02- 2023-03- 2022-04- 2022-12- rnitures de bureau, consom IDA / D4340 afety net for the poor in se Post Open - National 20,000.00 0.00 ementatio tations e Envelope 14 30 04 31 mables et produits d'entret lected rural areas n ien destinés à la Direction Antsirabe pour l'année 202 2 DRP_22001_DC_FOURNITU RE_BUREAU / Acquisition d Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-03- 2022-06- 2022-04- 2022-11- e fournitures et consomma IDA / D4340 afety net for the poor in se Post Open - National 71,000.00 0.00 ementatio tations e Envelope 18 08 29 05 bles bureautique et produit lected rural areas n s d'entretien pour l'année 2 022 répartis en quatre (4) l ots DRA_22012_DC_ALPHA_FA Component 1: Building a s Pending I 3 / Acquisition des fournitur Request for Quo Single Stage - On 2022-05- 2022-06- 2022-08- IDA / D7740 afety net for the poor in se Post Open - National 36,700.00 0.00 mplement e pour les centres d'alphab tations e Envelope 03 27 26 lected rural areas ation étisation TMDH et FSP Page 4 DG_22018_DC_INTRANTS_ Component 1: Building a s Request for Quo Single Stage - On 2022-05- 2022-06- 2022-07- 2022-08- AGRI / Acquisition d'intrant IDA / D4340 afety net for the poor in se Post Open - National 90,000.00 0.00 Signed tations e Envelope 16 29 04 03 s agricoles destinés aux bé lected rural areas néficiaires du FIAVOTA DRP_22008_DC_JEUNES PL ANTS _TMDH_IP / Acquisitio Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-05- 2022-06- 2022-08- n des Intrants _jeunes plant IDA / D7740 afety net for the poor in se Post Open - National 44,415.00 0.00 ementatio tations e Envelope 04 20 24 s , arbre fruitiers pour les b lected rural areas n énéficiaires TMDH dans les zones FIAVOTA DRF_22012_DC_FOURNITU RES _TMDH_FSP / Acquisitio Component 1: Building a s Pending I Request for Quo Single Stage - On 2022-05- 2022-07- 2022-08- n des diverses fournitures IDA / D4340 afety net for the poor in se Post Open - National 74,961.00 0.00 mplement tations e Envelope 27 14 13 pour les bénéficiaires FSP e lected rural areas ation t TMDH des 06 districts da ns le cadre des activités M ACC DG_22026_DC_MOB_BUR / Component 1: Building a s Request for Quo Single Stage - On 2022-06- 2022-09- 2022-08- 2022-09- Acquisition de divers matér IDA / D7740 afety net for the poor in se Post Open - National 20,000.00 0.00 Signed tations e Envelope 17 05 05 19 iels et mobiliers de bureau lected rural areas DRP_21002_DC_INTRANT_ Component 1: Building a s MORINGA / Acquisition des Request for Quo Single Stage - On 2021-05- 2021-06- 2021-08- IDA / D4340 afety net for the poor in se Post Open - National 9,500.00 0.00 Canceled semences de moringa pour tations e Envelope 09 21 05 lected rural areas les groupes des ménages b énéficiaires DG_22010_DC_EQPT_SURE TE_BUREAUX / Fourniture e Component 1: Building a s Request for Quo Single Stage - On 2022-07- 2022-08- 2022-09- 2022-11- t installation des équipeme IDA / D7740 afety net for the poor in se Post Open - National 50,000.00 0.00 Signed tations e Envelope 15 18 09 08 nts de sureté dans les Bure lected rural areas aux du FID répartis en 09 l ots DG_22014_DC_ACC_INFO / Component 1: Building a s Acquisition de diverses co Request for Quo Single Stage - On 2022-09- 2022-09- 2022-10- 2022-12- IDA / D7740 afety net for the poor in se Post Open - National 30,000.00 0.00 Signed mposantes et pièces de rec tations e Envelope 08 21 27 26 lected rural areas hanges informatiques DG_22013_AO_EQUIPEME Component 1: Building a s NTS_INFO_BUR / Acquisitio Request for Bid Single Stage - On 2022-08- 2022-09- 2022-08- 2022-09- 2022-09- 2022-10- 2022-10- 2022-11- 2022-10- 2023-01- IDA / D7740 afety net for the poor in se Post Open - National 250,000.00 0.00 Signed n de matériels et équipeme s e Envelope 01 01 08 05 05 04 03 24 31 29 lected rural areas nts informatiques et burea utiques DG_22009_AO_CONSINFO Component 1: Building a s Request for Bid Single Stage - On 2022-08- 2022-08- 2022-08- 2022-08- 2022-09- 2022-09- 2022-10- 2022-10- 2022-11- 2023-03- / Acquisition de consomptib IDA / D7740 afety net for the poor in se Post Open - National 300,000.00 0.00 Signed s e Envelope 01 16 08 18 07 20 05 18 02 21 les informatiques pour l'an lected rural areas née 2022 DG_22027_DC_TROUSSE_S Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-08- 2022-08- 2022-09- 2022-11- ECOURS / Acquisition de tr IDA / D7740 afety net for the poor in se Post Open - National 65,000.00 0.00 ementatio tations e Envelope 05 10 30 29 ousses de premier secours lected rural areas n DG_22031_DC_VIDEOCON Component 1: Building a s Request for Quo Single Stage - On 2022-08- 2022-09- 2022-10- 2023-01- FERENCE / Fourniture et ins IDA / D7740 afety net for the poor in se Post Open - National 40,000.00 0.00 Signed tations e Envelope 26 08 28 26 tallation de stations de vid lected rural areas éoconférence DRU_21012_DC_MAT_INTR Component 1: Building a s _ELEVAGE / Acquisition de Request for Quo Single Stage - On 2021-10- 2021-11- 2021-12- IDA / D4340 afety net for the poor in se Post Open - National 12,800.00 0.00 Canceled matériels et intrants de pet tations e Envelope 30 30 31 lected rural areas its élévages pour TMDH DRU_21013_DC_MAT_PETI Component 1: Building a s Request for Quo Single Stage - On 2021-10- 2021-11- 2021-12- TS COMMERCES / Acquisitio IDA / D4340 afety net for the poor in se Post Open - National 14,000.00 0.00 Canceled tations e Envelope 30 28 31 n de matériels de petits co lected rural areas mmerces pour TMDH DG_21029_ED_LIVRES_ED Component 1: Building a s 2021-09- 2021-09- 2021-10- 2021-11- UCATIFS / Fourniture et livr IDA / D4340 afety net for the poor in se Post Direct Selection Direct 85,000.00 0.00 Canceled 03 08 13 27 aison de livres éducatifs. M lected rural areas archés à lots multiples DG_22035_DC_SEMENCES Component 1: Building a s _TMDH / Acquisition semen Request for Quo Single Stage - On 2022-09- 2022-10- 2022-11- 2022-12- IDA / D7740 afety net for the poor in se Post Open - National 5,000.00 0.00 Signed ces maraîchères dans le ca tations e Envelope 16 06 04 04 lected rural areas dre de l'Inclusion Productiv e DG_22036_DC_MAT_AGRI_ Component 1: Building a s TMDH / Acquisition de mat Request for Quo Single Stage - On 2022-09- 2022-10- 2022-11- 2022-12- IDA / D7740 afety net for the poor in se Post Open - National 30,000.00 0.00 Signed ériels agricoles dans le cad tations e Envelope 16 06 04 04 lected rural areas re de l'inclusion productive DG_22038_AON_PHONES_ Component 1: Building a s Request for Bid Single Stage - On 2022-09- 2022-09- 2022-09- 2022-10- 2022-10- 2022-11- 2022-11- 2022-11- 2022-12- 2023-02- TMDH / Acquisition de post IDA / D4340 afety net for the poor in se Post Open - National 115,000.00 0.00 Signed s e Envelope 16 28 23 03 21 02 18 23 16 14 es téléphoniques mobiles lected rural areas DG_22039_DC_INTERCALAI Component 1: Building a s Request for Quo Single Stage - On 2022-09- 2022-10- 2022-11- 2022-12- RES_TMDH / Acquisition d'i IDA / D7740 afety net for the poor in se Post Open - National 10,000.00 0.00 Signed tations e Envelope 23 12 11 11 ntercalaires plastiques lected rural areas DG_22045_DC_RESEAU_M ANAKARA / Fourniture de m Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-11- 2022-12- 2022-12- 2023-01- atériels, équipements et in IDA / D7740 afety net for the poor in se Post Open - National 5,000.00 0.00 ementatio tations e Envelope 04 20 16 15 stallation de réseaux filaire lected rural areas n s dans les nouveaux burea ux du FID_Manakara DG_22051_DC_BOITES_DO Component 1: Building a s Request for Quo Single Stage - On 2022-12- 2022-12- 2023-01- 2023-03- LEANCES / Fourniture et liv IDA / D7740 afety net for the poor in se Post Open - National 60,000.00 0.00 Signed tations e Envelope 09 20 27 28 raison de boîtes de doléanc lected rural areas es DG_22046_DC_GROUPES_ Component 1: Building a s Request for Quo Single Stage - On 2022-12- 2022-12- 2023-01- 2023-03- ELECTROGENES / Acquisitio IDA / D7740 afety net for the poor in se Post Open - National 70,000.00 0.00 Signed tations e Envelope 08 19 26 27 n de groupes électrogènes lected rural areas DG_22052_DC_FOUR_DIV_ Component 1: Building a s Under Impl AVEC_TMDH / Acquisition d Request for Quo Single Stage - On 2022-12- 2023-02- 2023-02- 2023-03- IDA / D4340 afety net for the poor in se Post Open - National 90,000.00 0.00 ementatio e fournitures diverses pour tations e Envelope 19 14 13 30 lected rural areas n les Inclusions Productives e t Financières_TMDH DG_22053_DC_INTRANTS_ Component 1: Building a s TMDH / Acquisition divers i Request for Quo Single Stage - On 2023-01- 2023-02- 2023-03- 2023-08- IDA / D7740 afety net for the poor in se Post Open - National 90,000.00 0.00 Signed ntrants et outillages pour le tations e Envelope 16 03 06 13 lected rural areas s bénéficiaires du program me TMDH DRU_22009_DC_INTRAN F ORM IP TMDH FA3 / Acquisi Component 1: Building a s Pending I Request for Quo Single Stage - On 2023-02- 2023-04- 2023-07- tion des intrants de formati IDA / D7740 afety net for the poor in se Post Open - National 5,400.00 0.00 mplement tations e Envelope 20 10 09 on PARE, RC,CPS en Inclusi lected rural areas ation on Productive du program me TMDH FSS FA3 DRA_22019_DC_FRNT_BUR Component 1: Building a s Under Impl _ENTRET_2023 / Acquisitio Request for Quo Single Stage - On 2023-02- 2023-06- 2023-04- 2023-04- IDA / D7740 afety net for the poor in se Post Open - National 30,000.00 0.00 ementatio n de fournitures de bureau tations e Envelope 13 29 21 24 lected rural areas n et produits d'entretien pour l'année 2023 DRT_23006_DC_FRNT_BUR _ENTRET_2023 / Acquisitio n des fournitures de burea u, des produits d'entretien Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-12- 2023-04- 2023-02- 2023-12- et des consomptibles infor IDA / D7740 afety net for the poor in se Post Open - National 16,500.00 0.00 ementatio tations e Envelope 27 07 07 04 matiques répartis en trois l lected rural areas n ots: lot 1: Fournitures de burea u lot 2: Produits d'entretien lot 3: Consomptibles inform DG_23001_DC_PNEUMATI atiques Component 1: Building a s Under Impl Request for Quo Single Stage - On 2023-02- 2023-04- 2023-04- 2023-09- QUES / Acquisition d'envelo IDA / D7740 afety net for the poor in se Post Open - National 100,000.00 0.00 ementatio tations e Envelope 27 27 17 30 ppes pneumatiques pour l' lected rural areas n année 2023 DG_23002_DC_BUREAU_E Component 1: Building a s NTRETIEN / Acquisition de f Request for Quo Single Stage - On 2023-02- 2023-02- 2023-04- 2023-10- IDA / D7740 afety net for the poor in se Post Open - National 20,000.00 0.00 Signed ournitures de bureau et de tations e Envelope 20 14 10 31 lected rural areas produits d'entretien pour l' année 2023 DRP_23005_DC_FOURNITU RE KIT AVEC / Acquisition d Component 1: Building a s Under Impl Request for Quo Single Stage - On 2023-02- 2023-02- 2023-04- 2023-05- e Fourniture de KIT AVEC - IDA / D7740 afety net for the poor in se Post Open - National 28,000.00 0.00 ementatio tations e Envelope 11 03 08 23 pour les nouveaux 487 Gro lected rural areas n upes AVEC dans le progra mme TMDH FIAVOTA DRP_23007_DC_FOURNITU RES_JEUNES PLANTS / Acqu Component 1: Building a s Under Impl isition de jeunes plants pou Request for Quo Single Stage - On 2023-02- 2023-03- 2023-04- 2023-06- IDA / D7740 afety net for the poor in se Post Open - National 27,000.00 0.00 ementatio r la Campagne de reboisem tations e Envelope 15 02 19 18 lected rural areas n ent pour les Mères Leaders dans les anciennes zones F IAVOTA, repartie en cinq (0 5) lots. DRF_23006_DC_FOURN_M ATX CONSTR_FSP / Fournitu re et livraison des matériau Component 1: Building a s Pending I Request for Quo Single Stage - On 2023-02- 2023-04- 2023-05- x de construction pour la m IDA / D7740 afety net for the poor in se Post Open - National 11,000.00 0.00 mplement tations e Envelope 23 18 18 ise en place des espaces d lected rural areas ation e bien être dans le District de Lalangina, Vohibato, Ma nandriana et Fandriana pou r le programme FSP DRF_23005_DC_PANNEAU_ PUB_TMDH_FSP_FSU / Mise Component 1: Building a s Pending I en place de Panneaux publ Request for Quo Single Stage - On 2023-02- 2023-03- 2023-05- IDA / D7740 afety net for the poor in se Post Open - National 7,000.00 0.00 mplement icitaire du programme au n tations e Envelope 02 27 06 lected rural areas ation iveau de chaque District p our les 3 programmes TMD H-FSP-FSU DRP_23006_DC_FOURNITU RE ALPHABETISATION / Acq Component 1: Building a s Under Impl Request for Quo Single Stage - On 2023-02- 2023-02- 2023-04- 2023-05- uisition de Fourniture de fo IDA / D7740 afety net for the poor in se Post Open - National 20,000.00 0.00 ementatio tations e Envelope 11 17 15 30 rmation-outils didactiques lected rural areas n pour les Centres d' alphabé tisation dans la Région Ano sy, DG_23011_DC_FOURNITUR Component 1: Building a s Under Impl ES_PMA / Acquisition de Pet Request for Quo Single Stage - On 2023-03- 2023-05- 2023-05- 2023-06- IDA / D7740 afety net for the poor in se Post Open - National 80,000.00 0.00 ementatio its Matériels Agricole repart tations e Envelope 27 23 15 29 lected rural areas n is en quatre (04) lots DG_23012_DC_FOURNITUR Component 1: Building a s Under Impl Request for Quo Single Stage - On 2023-03- 2023-05- 2023-05- 2023-07- ES_SEMENCES / Acquisition IDA / D7740 afety net for the poor in se Post Open - National 20,000.00 0.00 ementatio tations e Envelope 27 23 18 02 de semences réparties en lected rural areas n deux (02) lots DG_23006_DC_RADIO_CAR Component 1: Building a s Under Impl Request for Quo Single Stage - On 2023-04- 2023-04- 2023-06- 2023-07- TES_TMDH / Acquisition de IDA / D7740 afety net for the poor in se Post Open - National 15,000.00 0.00 ementatio tations e Envelope 10 20 05 05 radio et cartes mémoires lected rural areas n DG_23020_DC_MAT_INFO / Component 1: Building a s Pending I Fourniture et livraison d'éq Request for Quo Single Stage - On 2023-05- 2023-06- 2023-08- IDA / D7740 afety net for the poor in se Post Open - National 80,000.00 0.00 mplement uipements informatiques et tations e Envelope 03 23 07 lected rural areas ation accessoires répartis en troi s (03) lots DG_23028_DC_MOBILIERS Component 1: Building a s Under Impl _BUREAUX / Acquisition de Request for Quo Single Stage - On 2023-05- 2023-06- 2023-06- 2023-08- IDA / D7740 afety net for the poor in se Post Open - National 30,000.00 0.00 ementatio divers matériels et mobilier tations e Envelope 12 02 30 14 lected rural areas n s pour les nouveaux burea ux du FID Anosy DG_23022_AO_SECURISATI ON_RESEAU / Acquisition d Component 1: Building a s Pending I Request for Bid Single Stage - On 2023-05- 2023-05- 2023-06- 2023-07- 2023-08- 2023-10- e matériels et équipements IDA / D7740 afety net for the poor in se Post Open - National 300,000.00 0.00 mplement s e Envelope 12 19 18 16 13 12 et mise en place système d lected rural areas ation e sécurisation des réseaux DG_23016_DC_RESEAUX_B UREAUX_ANOSY / Fournitur Component 1: Building a s Under Impl e de matériels, équipement Request for Quo Single Stage - On 2023-05- 2023-06- 2023-07- 2023-08- IDA / D7740 afety net for the poor in se Post Open - National 25,000.00 0.00 ementatio s et installation de réseaux tations e Envelope 26 13 21 20 lected rural areas n informatiques et téléphoniq ues pour les nouveaux bur eaux du FID DG_23021_AO_CONS_INFO Component 1: Building a s Pending I Request for Bid Single Stage - On 2023-05- 2023-05- 2023-06- 2023-07- 2023-08- 2023-10- / Fourniture et livraison de IDA / D7740 afety net for the poor in se Post Open - National 200,000.00 0.00 mplement s e Envelope 19 26 25 23 20 31 divers consomptibles infor lected rural areas ation matiques DG_23017_DC_FRNT_SCL_ Component 1: Building a s Under Impl Request for Quo Single Stage - On 2023-06- 2023-06- 2023-07- 2023-08- AVEC_TMDH / Acquisition d IDA / D7740 afety net for the poor in se Post Open - National 25,000.00 0.00 ementatio tations e Envelope 02 02 28 27 e fournitures scolaires lected rural areas n DRP_23009_DC_FOURNITU RE_MATERIAUX ESPACE / A Component 1: Building a s Pending I cquisition des matériaux po Request for Quo Single Stage - On 2023-05- 2023-07- 2023-09- IDA / D7740 afety net for the poor in se Post Open - National 3,900.00 0.00 mplement ur la construction des 17 es tations e Envelope 30 18 01 lected rural areas ation paces physiques dans le ca dre des mesures d'accomp agnement DPE TMDH FIAV OTA MG-FID-9596-GO-UN / DGP Component 2: Strengtheni UN Agencies (Di 2017-01- 2017-03- 2017-02- 2017-03- 2017-03- 2017-03- 2017-03- O127849-1-2 ACQUISITION IDA / D1450 ng safety net administratio Prior Direct 203,654.39 211,043.69 Signed rect) 29 23 12 24 03 03 03 6 VEHICULES PICK UP 4X4 n, monitoring and social ac countability NON CONSULTING SERVICES Activity Reference No Estimated A Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati Actual Amou Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Completio . / Description Component Review Type Method mount (US$ ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) nt (US$) Status on Documents aluation Report as Issued n ) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d d d d d d DRF11CFPAI17001 / MARC Component 1: Building a s Request for Bid Single Stage - On 2017-04- 2017-09- 2017-04- 2017-09- 2017-05- 2017-09- 2017-05- 2017-09- 2017-06- 2017-10- 2019-06- 2019-10- HES MULTIPLES POUR LE P IDA / 57080 afety net for the poor in se Post Limited 2,363.33 5,479.26 Signed s e Envelope 18 14 21 14 22 25 25 25 02 03 03 18 AIEMENT DES BÉNÉFICIAIR lected rural areas ES ACTP DRF12CFPAI17002 / MARC Component 1: Building a s Request for Bid Single Stage - On 2017-06- 2017-06- 2017-07- 2017-07- 2017-08- 2019-08- HES MULTIPLES POUR LE P IDA / 57080 afety net for the poor in se Post Limited 8,459.93 0.00 Canceled s e Envelope 19 21 25 27 10 10 AIEMENT DES BÉNÉFICIAIR lected rural areas ES TMDH DRT12CFPAI17001 / March Component 1: Building a s Request for Bid Single Stage - On 2017-05- 2017-05- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2017-05- 2017-06- 2017-06- 2019-11- é multiple pour paiement d IDA / 57080 afety net for the poor in se Post Limited 5,198.00 3,463.83 Signed s e Envelope 02 16 08 16 07 23 10 30 17 02 30 es bénéficiaires TMDH lected rural areas DRT12PRPAI17001 / March Component 1: Building a s Request for Bid Single Stage - On 2017-08- 2017-09- 2017-09- 2017-09- 2017-10- 2019-11- é multiple pour paiement d IDA / 57080 afety net for the poor in se Post Limited 13,819.00 0.00 Canceled s e Envelope 30 05 15 30 06 30 es bénéficiaires du TMDH (l lected rural areas ot 1) DRT12PRPAI17002 / March Component 1: Building a s Request for Bid Single Stage - On 2017-08- 2017-09- 2017-09- 2017-09- 2017-10- 2019-11- é multiple pour paiement d IDA / 57080 afety net for the poor in se Post Limited 10,730.00 0.00 Canceled s e Envelope 30 05 15 30 06 30 es bénéficiaires du TMDH ( lected rural areas Lot 2) DRF11CFPAI18001 / MARC Component 1: Building a s Request for Bid Single Stage - On 2018-04- 2018-04- 2018-04- 2018-05- 2019-05- HES MULTIPLES POUR LE P IDA / 57080 afety net for the poor in se Post Limited 2,363.33 0.00 Canceled s e Envelope 10 15 25 08 08 AIEMENT DES BÉNÉFICIAIR lected rural areas ES ACTP DRF12CFPAI18001 / MARC Component 1: Building a s Request for Bid Single Stage - On 2018-02- 2018-03- 2018-03- 2018-03- 2019-03- HES MULTIPLES POUR LE P IDA / 57080 afety net for the poor in se Post Limited 7,156.06 0.00 Canceled s e Envelope 27 04 11 22 22 AIEMENT DES BÉNÉFICIAIR lected rural areas ES TMDH Component 2: Strengtheni DG20TOMWEB / Migration 2020-01- 2019-12- 2020-01- 2019-12- 2020-02- 2020-02- 2020-03- IDA / D4340 ng safety net administratio Post Direct Selection Direct 30,000.00 38,504.81 Signed vers TOM WEB 16 20 21 19 25 21 26 n, monitoring and social ac countability DG20AORTRANSMONMOB Component 1: Building a s Pending I BANK / Prestations de servi Request for Bid Single Stage - On 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2020-12- IDA / D4340 afety net for the poor in se Post Limited 500,000.00 0.00 mplement ces de transfert monétaire s e Envelope 13 18 17 03 01 31 lected rural areas ation par Mobile Money - Marché s multiples DG20AORTRANSMONINSFI Component 1: Building a s Pending I N / Prestations de services Request for Bid Single Stage - On 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2020-12- IDA / D4340 afety net for the poor in se Post Limited 360,000.00 0.00 mplement de transfert monétaire par s e Envelope 13 18 17 03 01 31 lected rural areas ation les Institutions Financières - Marchés multiples DRU12AORTRANSMONAGE Component 1: Building a s NTPAYEURS / Prestations d Request for Bid Single Stage - On 2020-01- 2020-09- 2020-01- 2020-09- 2020-02- 2020-10- 2020-03- 2020-12- 2020-04- 2020-12- 2020-12- 2021-12- IDA / D4340 afety net for the poor in se Post Limited 120,000.00 17,866.61 Completed e services de transfert mon s e Envelope 13 16 18 16 17 12 03 02 01 16 31 18 lected rural areas étaire - Marchés multiples DRT12AORTRANSMONAGE Component 1: Building a s Pending I NTPAYEURS / Prestations d Request for Bid Single Stage - On 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2020-12- IDA / D4340 afety net for the poor in se Post Limited 120,000.00 0.00 mplement e services de transfert mon s e Envelope 13 18 17 03 01 31 lected rural areas ation étaire - Marchés multiples DRP82AORTRANSMONAGE Component 1: Building a s NTPAYEURS / Prestations d Request for Bid Single Stage - On 2020-01- 2020-09- 2020-01- 2020-09- 2020-02- 2020-10- 2020-03- 2020-11- 2020-04- 2020-12- 2020-12- IDA / D4340 afety net for the poor in se Post Limited 120,000.00 276,823.08 Signed e services de transfert mon s e Envelope 13 25 18 25 17 23 03 19 01 05 31 lected rural areas étaire - Marchés multiples DRK11AORTRANSMONAGE Component 1: Building a s Pending I NTPAYEURS / Prestations d Request for Bid Single Stage - On 2020-01- 2020-01- 2020-02- 2020-03- 2020-04- 2020-12- IDA / D4340 afety net for the poor in se Post Limited 120,000.00 0.00 mplement e services de transfert mon s e Envelope 13 18 17 03 01 31 lected rural areas ation étaire - Marchés multiples DRF12AORTRANSMONAGE Component 1: Building a s NTPAYEURS / Prestations d Request for Bid Single Stage - On 2020-01- 2020-09- 2020-01- 2020-09- 2020-02- 2020-10- 2020-03- 2020-11- 2020-04- 2020-12- 2020-12- IDA / D4340 afety net for the poor in se Post Limited 120,000.00 47,590.24 Signed e services de transfert mon s e Envelope 13 23 18 24 17 07 03 19 01 02 31 lected rural areas étaire - Marchés multiples DRA13AORTRANSMONAGE Component 1: Building a s NTPAYEURS / Prestations d Request for Bid Single Stage - On 2020-01- 2020-09- 2020-01- 2020-09- 2020-02- 2020-10- 2020-03- 2020-10- 2020-04- 2020-11- 2020-12- IDA / D4340 afety net for the poor in se Post Limited 120,000.00 6,434.50 Signed e services de transfert mon s e Envelope 13 17 18 17 17 06 03 27 01 11 31 lected rural areas étaire - Marchés multiples DG20ED_TM_AIRTEL / Pres tation de services de transf ert monétaire (Octobre 201 9 à Août 2020) Component 1: Building a s 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- TMDH dans les districts de IDA / D4340 afety net for the poor in se Post Direct Selection Direct 200,000.00 206,825.81 Signed 02 24 09 28 06 27 30 TOAMASINA II,MAHANORO, lected rural areas AMBOHIMAHASOA,VOHIPE NO, BETIOKY SUD, BETAFO, FARATSIHO ACTP dans le district de MA NAKARA DG20ED_TM_OTIVTANA / P restation de services de tra Component 1: Building a s 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- nsfert monétaire (Octobre IDA / D4340 afety net for the poor in se Post Direct Selection Direct 15,000.00 13,733.40 Signed 02 24 09 28 06 24 30 2019 à Août 2020) lected rural areas TMDH dans les districts de AMBOHIMAHASOA, BETAFO , FARATSIHO DG20ED_TM_ORANGE / Pr estation de services de tra Component 1: Building a s nsfert monétaire (Octobre 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 30,000.00 20,916.45 Signed 2019 à Août 2020) 02 24 09 28 06 24 30 lected rural areas ACTP dans les districts de V ATOMANDRY, ANTANIFOTS Y, ISANDRA, MANAKARA DG20ED_TM_OTIVZL / Pres tation de services de transf Component 1: Building a s 2020-03- 2020-03- 2020-04- 2020-09- ert monétaire (Octobre 201 IDA / D4340 afety net for the poor in se Post Direct Selection Direct 30,000.00 0.00 Canceled 02 09 06 30 9 à Août 2020) TMDH dans lected rural areas les districts de TOAMASINA II,MAHANORO DRF11CFPAI20002 / Presta tions de Services pour le Tr Component 1: Building a s ansferts Monétaires aux bé 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-04- 2020-07- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,560.00 3,193.21 Signed néficiaires de filets de sécu 03 27 08 04 12 01 11 lected rural areas rités sociaux en Argent Con tre Travail Productif (ACTP) District ISANDRA. – LOT 02. Page 5 DRP82EDAP20009 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 6,800.00 8,839.55 Signed s dans les communes ANTA 02 02 09 05 06 19 30 lected rural areas RITARIKA-IMONGY-NIKOLY, District Tsihombe Lot 23 DRP82EDAP20012 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- s dans les communes AMB IDA / D4340 afety net for the poor in se Post Direct Selection Direct 30,000.00 24,266.00 Signed 02 02 09 28 06 28 30 AZOA-ERADA-TSIMANANDA lected rural areas -AMBOVOMBE, District Amb ovombe Lot 10 et Lot 14 DRF12CFPAI20001 / Presta tions de Service pour le Tra Component 1: Building a s nsferts Monétaires des bén 2020-03- 2020-02- 2020-03- 2020-04- 2020-04- 2020-03- 2020-07- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 5,922.00 7,161.72 Signed éficiaires TMDH dans les co 03 26 08 09 12 20 11 lected rural areas mmunes de Morafeno, Befe ta et Ambatosoa -District A mbohimahasoa DRT12CFPAI20001 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s s dans les cinq Fokontany d 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2020-09- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 7,859.88 7,510.34 Completed e la Commune de Valabeto 02 19 09 06 06 20 30 17 lected rural areas kana et dans les huit Fokon tany de la Commune de Vi naninony Sud, District de F aratsiho, Région de Vakina nkaratra. DRT11CFPAI20004 / Presta tion de service de transfert monétaire aux bénéficiaire s dans les trente Fokontany Component 1: Building a s 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-04- 2020-09- 2020-07- des six Terroirs (Ambohito IDA / D4340 afety net for the poor in se Post Direct Selection Direct 8,745.40 7,506.63 Completed 02 19 09 06 06 03 30 24 mpoina, Ampitatafika, Amb lected rural areas atotokana, Ambohikamban a, Ambatomiady, Antambo homena), dans le District d' Antanifotsy, Région de Vaki nankaratra. DRP82EDAP20018 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 9,200.00 9,699.37 Signed s dans les communes AMB 02 02 09 28 06 26 30 lected rural areas OHIMALAZA, ANALAMARY, AMBONAIVO, District Ambo vombe. Lot 13 DRT12CFPAI20002 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s s du TMDH dans les cinq Fo 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2020-09- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 6,987.77 6,676.57 Completed kontany de la Commune d' 02 19 09 06 06 20 30 23 lected rural areas Andranomiady et dans les s ept Fokontany de la Comm une de Vinaninony Sud, Dis trict de Faratsiho, Région d e Vakinankaratra. DRF11CFPAI20003 / Presta tions de Services pour le Tr ansferts Monétaires aux bé Component 1: Building a s 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-04- 2020-07- néficiaires de filets de sécu IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,608.00 3,193.21 Signed 03 27 08 04 12 01 11 rités sociaux lected rural areas en Argent Contre Travail Pr oductif (ACTP) District ISANDRA. – LOT 03. DRP82EDAP20004 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- s dans les communes ANKA IDA / D4340 afety net for the poor in se Post Direct Selection Direct 17,200.00 30,085.64 Signed 02 02 09 27 06 25 30 RANABO NORD, ANTSAKOA lected rural areas MARO, MAROVIRO, MORAF ENO BEKILY, TSIKOLAKY, Di strict Bekily. Lot 19 et Lot 2 2 DRP82EDAP20014 / Presta tion de service de transfert Component 1: Building a s 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- monétaire aux bénéficiaire IDA / D4340 afety net for the poor in se Post Direct Selection Direct 10,200.00 8,918.64 Signed 02 02 09 27 06 21 30 s dans la commune MAROL lected rural areas INTA, District Beloha. Lot 18 DRP82EDAP20003 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 19,600.00 27,759.40 Signed s dans les communes AMB 02 02 09 28 06 28 30 lected rural areas OVOMBE et SIHANAMARO, District Ambovombe. Lot 15 et Lot 03 DRP82EDAP20010 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 26,900.00 29,548.28 Signed s dans les communes MAR 02 02 09 27 06 27 30 lected rural areas OALOPOTY-TSIHOMBE, Dist rict Ambovombe et Tsihom be. Lot 02 et Lot 25 DRP82EDAP20016 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 29,200.00 22,824.76 Signed s dans les communes SIHA 02 02 09 28 06 28 30 lected rural areas NAMARO-AMBOASARY, Dist rict Ambovombe et Amboa sary. Lot 04 et Lot 29 DRP82EDAP20017 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 6,900.00 9,058.43 Signed s dans la commune AMBOA 02 02 09 28 06 28 30 lected rural areas SARY sud, District Amboasa ry sud. Lot 30 DRF11CFPAI20001 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-04- 2020-09- s de filets de sécurités soci IDA / D4340 afety net for the poor in se Post Direct Selection Direct 3,416.00 2,794.21 Signed 02 27 09 04 06 01 30 aux lected rural areas en Argent Contre Travail Pr oductif (ACTP) District ISANDRA. – LOT 01. DRU11EDAP20003 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-04- 2020-09- 2020-08- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 1,638.98 3,785.39 Completed s dans TERROIR 01D TANA 02 02 09 09 06 15 30 22 lected rural areas NDAVA – FSP DISTRICT ANK AZOABO – REGION ATSIMO ANDREFANA DRF11CFPAI20005 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-04- 2020-07- s de filets de sécurités soci IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,360.00 3,360.48 Signed 03 27 08 04 12 01 11 aux lected rural areas en Argent Contre Travail Pr oductif (ACTP) District ISANDRA. – LOT 05. DRA11CFPAI20003 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 7,905.00 5,197.31 Signed s ACT P dans le DISTRICT 02 26 09 06 06 20 30 lected rural areas VATOMANDRY TERROIRS IL AKA EST - AMPANALANA - N IAROVANA - ANDRORANGA DRP82EDAP20007 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 39,800.00 19,860.88 Signed s dans les communes ANJA 02 02 09 27 06 21 30 lected rural areas MPALY-TRANOVAHO, Distri ct Tsihombe et Beloha. Lot 07 et Lot 06 DRP82EDAP20015 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-04- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 13,000.00 12,532.32 Signed s dans la commune MAROA 02 02 09 28 06 10 30 lected rural areas LOMAINTY, District Ambovo mbe Lot 11 DRP82EDAP20006 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 6,800.00 13,247.38 Signed s dans les communes AND 02 02 09 28 06 27 30 lected rural areas ALATANOSY, MAROVATO B EFENO, District Ambovomb e Lot 12 DRK12CFPAI20002 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- s du programme Filets soci IDA / D4340 afety net for the poor in se Post Direct Selection Direct 14,000.00 5,395.76 Signed 02 06 09 28 06 20 30 aux de sécurités, composa lected rural areas nte TMDH dans le District d e Vohipeno : Commune Rur ale de Mahazoarivo et Com mune Rurale d'Ilakatra. DRP82EDAP20019 / Presta Component 1: Building a s tion de service de transfert 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,600.00 7,317.23 Signed monétaire aux bénéficiaire 02 02 09 28 06 28 30 lected rural areas s dans la commune de BEH ARA, District Amboasary su d DRK12CFPAI20001 / Presta tion de transfert Monétaire aux bénéficiaires des filets Component 1: Building a s 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- sociaux de sécurités " com IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,131.53 4,604.70 Signed 02 06 09 28 06 20 30 posante TMDH" dans le Dis lected rural areas trict de Vohipeno : Commu ne Rurale de MAHASOABE et Commune Rurale de SA HALAVA DRK11CFPAI20001 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s s du programme Argent Co 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2020-04- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 8,024.80 6,496.78 Signed ntre Travail Productif dans l 02 28 09 28 06 02 30 lected rural areas e District de Manakara pou r les Terroirs suivants : IONI LAHY, AMBORONDRA, VOHI MASINA SUD, AMBAHIVE, V OHILAVA. DRP82EDAP20002 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 23,000.00 12,663.76 Signed s dans les communes de B 02 02 09 27 06 25 30 lected rural areas EVITIKY, MANAKOMPY, TAN AMBAO TSIRANDRANY. Lot 20 DRP82EDAP20013 / Presta tion de service de transfert Component 1: Building a s 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- monétaire aux bénéficiaire IDA / D4340 afety net for the poor in se Post Direct Selection Direct 34,800.00 15,996.55 Signed 02 02 09 27 06 24 30 s dans les communes KOP lected rural areas OKY-BELOHA, District Beloh a Lot 17 et Lot 16 DRT11CFPAI20002 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-04- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 3,303.70 3,798.71 Signed s dans les onze Fokontany 02 19 09 06 06 03 30 lected rural areas des deux Terroirs (Ambilon a, Mananitra), dans le Distri ct d'Antanifotsy, Région de Vakinankaratra. DRU11EDAP20004 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-04- 2020-09- 2020-08- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 6,576.23 3,257.16 Completed s dans TERROIRS 05D TAN 02 02 09 09 06 15 30 21 lected rural areas DRANO ET 06D ANTSOHA – FSP DISTRICT ANKAZOABO – REGION ATSIMO ANDREF ANA DRP82EDAP20005 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 13,500.00 16,760.14 Signed s dans les communes ANIV 02 02 09 27 06 25 30 lected rural areas ORANO MITSINJO et BERAK ETA, District Bekily. Lot 21 DRU11EDAP20002 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s s dans TERROIRS 02D MIA 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-04- 2020-09- 2020-08- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 6,020.70 4,065.14 Completed RY-CENTRE, 07D ANKILIVAL 02 02 09 09 06 15 30 22 lected rural areas OBE, 08D ANKILIMARO ET 0 9D ANDRANOTERAKY – FSP DISTRICT ANKAZOABO – R EGION ATSIMO ANDREFAN A DRK11CPAI20002 / Prestat ion de service de transfert monétaires aux bénéficiair Component 1: Building a s 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2020-04- 2020-09- es du programme ACT_P da IDA / D4340 afety net for the poor in se Post Direct Selection Direct 6,348.10 4,548.45 Signed 02 28 09 28 06 02 30 ns District de Manakara po lected rural areas ur les terroirs : AMBOHITRO VA, SAHANAMBOHITRA, BE NIHAONANA, FIADANANA ( CR Fenomby). DRF11CFPAI20004 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2020-07- s de filets de sécurités soci IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,544.00 3,718.23 Signed 03 27 08 04 12 31 11 aux lected rural areas en Argent Contre Travail Pr oductif (ACTP) District ISANDRA. – LOT 04. DRP82EDAP20008 / Presta tion de service de transfert Component 1: Building a s 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- monétaire aux bénéficiaire IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,600.00 8,317.64 Signed 02 02 09 27 06 25 30 s dans la commune BELIND lected rural areas O MAHASOA, District Bekily . Lot 09 DRP82EDAP20001 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 15,000.00 20,979.41 Signed s dans la commune de Sam 02 02 09 28 06 28 30 lected rural areas pona, District Amboasary s ud. Lot 26 DRP82EDAP20011 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- s dans les communes MAR IDA / D4340 afety net for the poor in se Post Direct Selection Direct 35,300.00 43,429.71 Signed 02 02 09 27 06 28 30 OVATO, FAUX CAP,NIKOLY lected rural areas CENTRE-TRANOVAHO, Distr ict de Tsihombe et Beloha. Lot 24 et Lot 05 DRT11CFPAI20001 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-04- 2020-09- 2020-07- s dans les quinze Fokontan IDA / D4340 afety net for the poor in se Post Direct Selection Direct 5,398.50 3,167.82 Completed 02 19 09 06 06 03 30 25 y des trois Terroirs (Tsarah lected rural areas onenana, Belanitra, Mahats injo), dans le District d'Anta nifotsy, Région de Vakinan karatra. DRU13APPC20001 / Presta tion de service de transfert Component 1: Building a s 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-09- 2020-09- monétaire aux bénéficiaire IDA / D4340 afety net for the poor in se Post Direct Selection Direct 38,303.05 23,907.85 Completed 02 02 09 09 20 26 16 15 s dans les Communes d'AN lected rural areas DROKA et ANKILIABO, Distri ct d'AMPANIHY - POST SEC HERESSE DRU13APPC20002 / Presta tion de service de transfert Component 1: Building a s 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-09- 2020-09- monétaire aux bénéficiaire IDA / D4340 afety net for the poor in se Post Direct Selection Direct 8,793.96 5,489.19 Completed 02 02 09 09 20 26 16 05 s dans la Commune de TA lected rural areas MEANTSOA, District de BET IOKY SUD - POST SECHERE SSE DRU11EDAP20001 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-04- 2020-09- 2020-08- s dans TERROIRS 03D ANK IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,988.20 2,962.37 Completed 02 02 09 09 06 12 30 28 ILIMIAVOTSE ET 04D AMPA lected rural areas NDRAMITSETAKY – FSP DIS TRICT ANKAZOABO – REGI ON ATSIMO ANDREFANA DRT11CFPAI20003 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-04- 2020-09- 2020-07- s dans les douze Fokontany IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,107.00 2,922.69 Completed 02 19 09 06 06 03 30 23 des trois Terroirs (Ambatod lected rural areas idy, Ambatolahy, Soamana ndrariny), dans le District d 'Antanifotsy, Région de Vak inankaratra. DRA11CFPAI20002 / Presta tion de service de transfert monétaire aux bénéficiaire Component 1: Building a s 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2020-09- s ACT P dans le DISTRICT IDA / D4340 afety net for the poor in se Post Direct Selection Direct 6,535.00 4,582.39 Signed 02 26 09 06 06 20 30 VATOMANDRY TERROIRS lected rural areas SAHAMATEVINA - TANAMBA O VATRAKAKA - AMBODIVO ANATO- AMBALAVOLO DRP82EDAP20020 / Presta Component 1: Building a s tion de service de transfert 2020-03- 2020-03- 2020-03- 2020-02- 2020-04- 2020-03- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 6,900.00 10,263.08 Signed monétaire aux bénéficiaire 02 02 09 28 06 24 30 lected rural areas s dans la commune MAROA LOPOTY DRA11CFPAI20001 / Presta tion de service de transfert Component 1: Building a s monétaire aux bénéficiaire 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2020-10- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 8,095.00 4,100.25 Signed s ACT P dans le DISTRICT 05 26 12 06 09 21 03 lected rural areas VATOMANDRY TERROIRS T SARASAMBO - BENGIVY - A NTANAMBAO MAHATSARA - TSIVANGIANA DG20ED_TM_PAOMA_2001 / Prestation de services de transfert monétaire (Octobr Component 1: Building a s e 2019 à Août 2020) dans l 2020-03- 2020-02- 2020-04- 2020-03- 2020-05- 2020-05- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 120,000.00 18,594.20 Signed es nouvelles zones d'interv 30 24 06 26 04 05 30 lected rural areas ention du FID : Arivonimam o-Région Analamanga, Man adriana-Région Amoron'i M ania et Toliara2-Région Sud Ouest DG20ED_COVID_TMNC200 5 / Prestation de services d Component 1: Building a s e Transfert Monétaire Non 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-08- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 250,000.00 22,706.01 Signed Conditionnel (avril à mai 20 11 10 18 10 28 22 10 lected rural areas 20) aux ménages vulnérabl es les plus touchés par le c onfinement DG20DC_OUTILS_SOCOP2 Component 1: Building a s Under Impl Request for Quo Single Stage - On 2020-04- 2020-05- 2020-06- 016 / Impression et multipli IDA / 57080 afety net for the poor in se Post Limited 5,000.00 0.00 ementatio tations e Envelope 18 23 06 cation d’outils de travail po lected rural areas n ur les SOCOP DG20ED_COVID_TMNC200 6 / Prestation de services d e Transfert Monétaire Non Component 1: Building a s 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-07- Conditionnel (avril à mai 20 IDA / D4340 afety net for the poor in se Post Direct Selection Direct 50,000.00 70,110.76 Signed 20 10 27 10 11 23 10 20) aux ménages vulnérabl lected rural areas es les plus touchés par le c onfinement - Antananarivo périphérie, Toamasina et Fi anarantsoa Page 6 DG20_DC__SUPPORT_COM M_2011 / Confection et livr aison de divers supports de communication répartis en Component 1: Building a s Request for Quo Single Stage - On 2020-07- 2020-08- 2020-08- 2020-11- 2020-09- quatre (04) lots: IDA / D4340 afety net for the poor in se Post Limited 10,000.00 8,907.43 Signed tations e Envelope 14 28 25 11 22 Lot N°01 : Stylo, clé USB, s lected rural areas upports en plexi, … Lot N°02 : Supports en tiss us Lot N°03 : Supports en bâc hes N°04 : Supports en/ papi DG20_ED_TMNC2007 Lot Pre station er de services de Tran Component 1: Building a s sfert Monétaire Non Conditi 2020-08- 2020-07- 2020-08- 2020-07- 2020-08- 2020-08- 2020-10- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 45,000.00 47,220.02 Signed onnel aux ménages vulnér 03 30 10 30 24 06 31 lected rural areas ables les plus touchés par l e confinement - Antananari vo, Toamasina et Fianarant soa DG20_ED_COVID_TMNC_2 008 / Prestation de service s de Transfert Monétaire N Component 1: Building a s 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-08- on Conditionnel (TOSIKA FA IDA / D4340 afety net for the poor in se Post Direct Selection Direct 15,000.00 15,188.75 Signed 01 10 01 10 06 23 04 MENO) aux ménages vulné lected rural areas rables les plus touchés par le confinement - Antananar ivo, Toamasina et Fianaran tsoa DG20_ED_COVID_TMNC_2 009 / Prestation de service s de Transfert Monétaire N Component 1: Building a s 2020-08- 2020-08- 2020-08- 2020-08- 2020-09- 2020-08- 2020-12- on Conditionnel (TOSIKA FA IDA / D4340 afety net for the poor in se Post Direct Selection Direct 20,000.00 20,930.40 Signed 21 24 21 24 11 28 10 MENO) aux ménages vulné lected rural areas rables les plus touchés par le confinement - Antananar ivo, Toamasina et Fianaran tsoa DRA11 DC VIDEO 20003 / Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-11- 2021-03- Tournage vidéo de success IDA / D4340 afety net for the poor in se Post Limited 4,800.00 0.00 mplement tations e Envelope 29 17 17 story FSP et TMDH lected rural areas ation DRA12 DC LOCVOITURE 2 Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-11- 2021-02- 0004 / Location de voitures IDA / D4340 afety net for the poor in se Post Limited 4,500.00 0.00 mplement tations e Envelope 22 03 01 de transport lected rural areas ation DG20_DC_CABSAISIEPLAIN Component 1: Building a s TE_2033 / Prestation de ser Request for Quo Single Stage - On 2020-09- 2020-09- 2020-10- 2020-10- 2020-11- IDA / D4340 afety net for the poor in se Post Limited 1,500.00 880.65 Signed vice d'un cabinet chargé de tations e Envelope 15 08 27 30 10 lected rural areas saisie des plaintes reçues _ Tosika Fameno DRK_DC_VIDEO_FSP/TMDH Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-10- 2020-12- 20 / Tournage Vidéo de suc IDA / D4340 afety net for the poor in se Post Limited 6,000.00 0.00 mplement tations e Envelope 10 29 28 cess story à Manakara et V lected rural areas ation ohipeno DRK_DC_LOC_VEH_FSP/TM Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-11- 2021-02- DH20 / Location de véhicul IDA / D4340 afety net for the poor in se Post Limited 10,100.00 0.00 mplement tations e Envelope 24 12 10 es de transport lected rural areas ation DRP82_DC_LOCATIONVOI2 Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-10- 2020-12- 004 / Location de voitures _ IDA / D4340 afety net for the poor in se Post Limited 42,700.00 0.00 mplement tations e Envelope 25 25 24 Région Anosy lected rural areas ation DRP82_DC_TOURNVIDEO2 Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-10- 2020-12- 005 / Tournage vidéo pour l IDA / D4340 afety net for the poor in se Post Limited 2,100.00 0.00 mplement tations e Envelope 25 25 24 es activités AVEC et inclusi lected rural areas ation on productive DRP82_DC_IMPRESOUTIL2 Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-10- 2020-10- 2020-11- 006 / Impression et multipli IDA / D4340 afety net for the poor in se Post Limited 2,600.00 0.00 mplement tations e Envelope 05 21 20 cation de documents lected rural areas ation DRT11 DC LOCVEH 20001 Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-11- 2020-12- / Location de véhicules de t IDA / D4340 afety net for the poor in se Post Limited 6,312.00 0.00 mplement tations e Envelope 25 01 21 ransport pour FSP et TMDH lected rural areas ation - 02 lots DRT11 DC EDIT REPRO 20 Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-10- 2020-12- 001 / Impression et multipli IDA / D4340 afety net for the poor in se Post Limited 5,871.00 0.00 mplement tations e Envelope 21 28 27 cation de documents - 03 l lected rural areas ation ots Component 1: Building a s Pending I DRT11 PROD VID 20001 / Request for Quo Single Stage - On 2020-10- 2020-11- 2021-01- IDA / D4340 afety net for the poor in se Post Limited 1,351.00 0.00 mplement Tournage vidéo pour le FSP tations e Envelope 07 13 12 lected rural areas ation DRA12 DC EDIT REPRO 20 Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-09- 2020-10- 2021-04- 005 / Impression et multipli IDA / D4340 afety net for the poor in se Post Limited 39,500.00 0.00 mplement tations e Envelope 24 31 29 cation de documents et out lected rural areas ation ils de travail DG20_DC_VIDEO_COMM_2 Component 1: Building a s Request for Quo Single Stage - On 2020-11- 2021-06- 2021-01- 2021-10- 2021-07- 037 / Tournage vidéo pour l IDA / D4340 afety net for the poor in se Post Limited 40,000.00 2,157.78 Signed tations e Envelope 06 11 08 07 07 a Direction Générale lected rural areas DRF DC_LOC VEH 2001 / L Component 1: Building a s Request for Quo Single Stage - On 2020-10- 2021-03- 2020-12- 2021-03- 2021-01- ocation de véhicules de tra IDA / D4340 afety net for the poor in se Post Limited 6,500.00 699.60 Signed tations e Envelope 26 16 18 27 17 nsport pour FSP et TMDH - lected rural areas 02 lots DRF DC_MOB_2002 / Acqui Component 1: Building a s Request for Quo Single Stage - On 2020-10- 2020-08- 2020-12- 2020-11- 2021-01- sition des mobiliers de bure IDA / D4340 afety net for the poor in se Post Limited 4,170.00 3,191.74 Signed tations e Envelope 19 28 14 12 23 au pour l'antenne à Ambosi lected rural areas tra DG20_AO_SUPPORTS_COM Component 1: Building a s Under Impl M_OUTILS_2007 / Impressio Request for Bid Single Stage - On 2020-11- 2020-11- 2020-11- 2020-11- 2020-12- 2021-01- 2021-01- 2021-02- 2021-04- IDA / D4340 afety net for the poor in se Post Open - National 300,000.00 0.00 ementatio n et multiplication de supp s e Envelope 12 23 19 27 19 15 18 15 16 lected rural areas n orts de communication et o utils de travail DRP82_DC_TRANSMONAG Component 1: Building a s Pending I ENTPAYEURS / Prestation d Request for Quo Single Stage - On 2020-12- 2021-02- 2021-07- IDA / D4340 afety net for the poor in se Post Limited 42,000.00 0.00 mplement e Service de Transfert Mon tations e Envelope 07 01 31 lected rural areas ation étaire _ Marché Multiple: L ot 07, Lot 11 et Lot 12 DRP82_ED_TRANSMONAGE NTPAYEURS / Prestation de Component 1: Building a s Pending I service de transfert monét 2020-11- 2020-11- 2020-12- 2021-01- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 7,700.00 0.00 mplement aire aux bénéficiaires dans 25 30 10 15 lected rural areas ation les communes Ambovombe , Tsihombe, Beraketa et Mo rafeno Bekily DRF20_ED_TRSF_2003 TM DH / Prestations de service Component 1: Building a s 2020-11- 2020-11- 2020-11- 2020-12- 2020-12- 2020-12- 2021-01- pour le paiement des bénéf IDA / D4340 afety net for the poor in se Post Direct Selection Direct 1,390.00 1,234.98 Signed 25 26 30 01 20 16 19 iciaires du programme TMD lected rural areas H de la commune Camp Ro bin DRT12 ED TRANSMONAGE Component 1: Building a s Pending I 2020-11- 2020-12- 2020-12- 2021-02- NTPAYEUR 20001 / Prestati IDA / D4340 afety net for the poor in se Post Direct Selection Direct 10,153.00 0.00 mplement 26 03 23 06 ons de services de transfer lected rural areas ation t monétaire. DRA11ED TRANSMONAGE Component 1: Building a s Under Impl 2020-11- 2020-12- 2020-12- 2020-12- 2020-12- 2021-02- NTPAYEUR 20008 / Prestati IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,000.00 0.00 ementatio 27 09 04 15 24 07 ons de services de transfer lected rural areas n t monétaire. DRK12EDTRANSMONAGEN Component 1: Building a s Pending I TPAYEUR2001 / Prestation 2020-11- 2020-12- 2020-12- 2021-02- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 5,500.00 0.00 mplement de services de transfert mo 27 04 24 07 lected rural areas ation nétaire TMDH dans le Distri ct de Vohipeno DRU11CFLOC21001 / Prest ation de service pour locati Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-05- 2021-06- 2022-03- on de voiture pour visite d' IDA / D4340 afety net for the poor in se Post Limited 1,200.00 0.00 mplement tations e Envelope 10 09 31 échange des Bénéficiaires lected rural areas ation FSP Ankazoabo Sud aux au tres Districts DRU11CFPRO21001 / Prest Component 1: Building a s Pending I ation de service pour tourn Request for Quo Single Stage - On 2020-12- 2021-01- 2022-03- IDA / D4340 afety net for the poor in se Post Limited 1,800.00 0.00 mplement age et production de film s tations e Envelope 06 11 31 lected rural areas ation ucess story et réalisation - FSP Ankazoabo Sud DRU11APED20001 / Presta tion de service de transfert Component 1: Building a s monétaire, Agence payeur 2020-11- 2020-12- 2020-12- 2020-12- 2020-12- 2020-12- 2021-02- 2021-02- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 3,900.00 1,591.59 Completed pour les 03 transferts, 9è in 28 01 03 01 11 17 15 20 lected rural areas tervention - FSP ANKAZOAB O SUD et le transfert octob re-décembre 2020 - TMDH Betioky Sud DRA11 DC VIDEO 20007 / Component 1: Building a s Pending I Request for Quo Single Stage - On 2020-12- 2021-01- 2021-07- Prestation de service :Tour IDA / D4340 afety net for the poor in se Post Limited 4,800.00 0.00 mplement tations e Envelope 07 20 19 nage vidéo de success stor lected rural areas ation y FSP et TMDH DRF21_DC_TRSF AGENTPA YEUR 2001 / Prestations de Component 1: Building a s Request for Quo Single Stage - On 2021-01- 2021-01- 2021-03- 2021-02- 2021-09- services de transfert monét IDA / D4340 afety net for the poor in se Post Limited 80,000.00 17,946.68 Signed tations e Envelope 30 22 27 27 23 aire pour le programme FS lected rural areas P Manandriana -Marchés m ultiples DRA12 DC LOCVEHICULE Component 1: Building a s Pending I 20006 / Location de véhicul Request for Quo Single Stage - On 2021-01- 2021-02- 2021-04- IDA / D4340 afety net for the poor in se Post Limited 1,000.00 0.00 mplement es pour acheminement des tations e Envelope 17 23 14 lected rural areas ation supports et des jouets TMD H DRT11 DC LOCVEH 21001 Component 1: Building a s Pending I / Location de véhicules de t Request for Quo Single Stage - On 2021-02- 2021-03- 2021-05- IDA / D4340 afety net for the poor in se Post Limited 2,702.00 0.00 mplement ransport de matériels MAC tations e Envelope 17 19 08 lected rural areas ation C pour le FSP et TMDH sur sites, répartis en deux lots. DRU ED TRANSMONAGENT Component 1: Building a s 2021-02- 2021-02- 2021-02- 2021-02- 2021-03- 2021-03- 2021-09- PAYEUR 21001 / Prestation IDA / D4340 afety net for the poor in se Post Direct Selection Direct 13,200.00 7,367.40 Signed 12 10 19 11 08 06 30 s de services de transfert lected rural areas monétaire. DRK ED TRANSMONAGENT PAYEUR_21001 / Prestation Component 1: Building a s Pending I 2021-02- 2021-02- 2021-03- 2021-10- s de service pour le paieme IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,800.00 0.00 mplement 12 17 24 03 nt des bénéficiaires du pro lected rural areas ation gramme TMDH de la comm une de VOHIPENO DRP_ED_TRANSMONAGEN TPAYEURS21001 / Prestatio ns de services de transfert Component 1: Building a s Pending I 2021-02- 2021-02- 2021-03- 2021-09- monétaire avec le nouveau IDA / D4340 afety net for the poor in se Post Direct Selection Direct 8,400.00 0.00 mplement 12 17 08 30 mécanisme de paiement a lected rural areas ation ux bénéficiaires dans les co mmunes Ambovombe, Tsih ombe, Beraketa et Morafen o Bekily DRT ED TRANSMONAGENT Component 1: Building a s Under Impl PAYEUR 21001 / Prestation 2021-02- 2020-12- 2021-02- 2020-12- 2021-03- 2021-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 11,755.00 0.00 ementatio s de services de transfert 12 03 19 03 08 30 lected rural areas n monétaire aux bénéficiaire s du FSP et TMDH. DG_ED_TRANSFERTMON_2 1006 / Prestations de servi Component 1: Building a s ces de transferts monétaire 2021-02- 2021-03- 2021-02- 2021-03- 2021-03- 2021-04- 2021-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 25,000.00 30,594.18 Signed s avec le nouveau mécanis 12 16 19 17 08 14 30 lected rural areas me de paiement aux bénéfi ciaires des programmes TM DH et ACTP DG_DC_IMPRESSION_CART Component 1: Building a s Request for Quo Single Stage - On 2021-02- 2021-03- 2021-03- 2021-05- 2021-05- ES_21008 / Impression et r IDA / D4340 afety net for the poor in se Post Limited 45,000.00 40,235.05 Signed tations e Envelope 23 16 29 13 28 eprogrammation des cartes lected rural areas DRT12 DC PROD VID 2100 Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-03- 2021-05- 2021-07- 1 / Tournage de vidéo sur l' IDA / D4340 afety net for the poor in se Post Open - National 1,081.00 0.00 mplement tations e Envelope 11 14 13 inclusion productive du TM lected rural areas ation DH. DRP_21003_DC_LOCVOITU Component 1: Building a s Pending I RE_MATERIELDPEI / Locatio Request for Quo Single Stage - On 2021-05- 2021-07- 2021-08- IDA / D4340 afety net for the poor in se Post Open - National 5,000.00 0.00 mplement n de voiture pour le transp tations e Envelope 12 08 07 lected rural areas ation ort des matériels DPEI vers les sites TMDH DG_21013_DC_MULTIPL_S Component 1: Building a s UPPORTS / Impression et m Request for Quo Single Stage - On 2021-06- 2021-08- 2021-10- IDA / D4340 afety net for the poor in se Post Open - National 30,000.00 0.00 Canceled ultiplication de supports de tations e Envelope 22 10 09 lected rural areas communication et outils de travail répartis en 03 lots DRK_21004_DC_FILM_COM Component 1: Building a s Pending I M / Enregistrement et tourn Request for Quo Single Stage - On 2021-06- 2021-08- 2022-02- IDA / D4340 afety net for the poor in se Post Open - National 5,100.00 0.00 mplement age vidéo des réalisations tations e Envelope 15 10 06 lected rural areas ation des activités FSP et TMDH DRK_21006_DC_DUPLI_DO CALPHA / Duplication des d Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-06- 2021-08- 2021-10- ocuments et livres pour les IDA / D4340 afety net for the poor in se Post Open - National 2,600.00 0.00 mplement tations e Envelope 15 10 09 apprenants de la formation lected rural areas ation Alphabétisation FSP et TMD H DRT_21010_DC_IMPR_FICH Component 1: Building a s Pending I E SUIV_FSP / Impression de Request for Quo Single Stage - On 2021-06- 2021-07- 2021-08- IDA / D4340 afety net for the poor in se Post Limited 368.11 0.00 mplement fiche de suivi ménages pou tations e Envelope 13 22 21 lected rural areas ation r les bénéficiaires FSP dans le District d'Antanifotsy DRF_21002_DC_LOC VEH BENEF_FSP_TMDH / Locatio n de voitures pour la visite Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-08- 2021-10- 2021-10- -échange des bénéficiaires IDA / D4340 afety net for the poor in se Post Open - National 8,108.50 0.00 mplement tations e Envelope 01 01 31 FSP et TMDH, réparties en lected rural areas ation 03 Lots: Lot 01 pour TMDH Ambohimahasoa - Lot 02 p our FSP Isandra - Lot 03 po ur FSP Manandriana DRK_21008_DC_LOC_VEHI CULE / Location de véhicule pour transport des matériel Component 1: Building a s Under Impl Request for Quo Single Stage - On 2021-06- 2023-05- 2021-08- 2021-10- s et jouets sur 16 sites TMD IDA / D4340 afety net for the poor in se Post Open - National 6,950.00 0.00 ementatio tations e Envelope 15 23 11 10 H et Transport des bénéfici lected rural areas n aires pour la visite d'échan ge et foires régionaux de d eux composantes. DRF_21008_DC_FILM COM Component 1: Building a s Pending I M / Enregistrement et prod Request for Quo Single Stage - On 2021-07- 2021-09- 2021-10- IDA / D4340 afety net for the poor in se Post Open - National 1,081.88 0.00 mplement uction des films sur les réal tations e Envelope 12 10 10 lected rural areas ation isations des bénéficiaires T MDH et FSP DRF_21007_DC_PROD SPO Component 1: Building a s Pending I T / Production d'un spot vid Request for Quo Single Stage - On 2021-07- 2021-09- 2021-11- IDA / D4340 afety net for the poor in se Post Open - National 1,600.00 0.00 mplement éo en dialecte locale pour l tations e Envelope 12 10 09 lected rural areas ation a sortie de programme des 02 composantes TMDH et F SP. DG_21022_DC_LOCATION_ Component 2: Strengtheni Request for Quo Single Stage - On 2021-08- 2021-10- 2022-04- 2024-12- SERVEUR / Location de ser IDA / D4340 ng safety net administratio Post Open - National 10,000.00 32,917.50 Signed tations e Envelope 21 16 27 31 veurs pour les bases de do n, monitoring and social ac nnées du FID countability DG_21027_AO_SUPPORTS_ COMM / Impression et multi Component 1: Building a s Request for Bid Single Stage - On 2021-08- 2021-10- 2021-09- 2021-10- 2021-11- 2021-11- 2022-04- 2021-12- 2022-04- 2021-12- plication d'outils de commu IDA / D4340 afety net for the poor in se Post Open - National 400,000.00 107,538.87 Signed s e Envelope 28 07 04 04 05 03 08 01 27 31 nication sur différents supp lected rural areas orts. Marchés à lots multipl es DG_21028_AO_BOITES_IM Component 1: Building a s Request for Bid Single Stage - On 2021-08- 2022-03- 2021-08- 2022-03- 2021-09- 2022-03- 2021-10- 2022-05- 2021-11- 2022-07- 2021-12- AGES / Multiplication de boî IDA / D4340 afety net for the poor in se Post Open - National 105,000.00 20,064.13 Signed s e Envelope 21 01 28 08 27 31 27 30 24 09 24 tes à images lected rural areas DG_21030_AO_OUTILS_TR Component 1: Building a s Request for Bid Single Stage - On 2021-08- 2021-11- 2021-09- 2021-10- 2021-12- 2021-10- 2022-01- 2021-11- 2022-02- 2021-12- AVAIL / Impression d'outils IDA / D4340 afety net for the poor in se Post Open - National 150,000.00 12,670.34 Signed s e Envelope 25 12 01 01 14 31 19 28 22 28 de travail. Marchés à lots m lected rural areas ultiples DRT_21012_DC_LOC_VEH_ VE_TMDH_FSP / Location vé Component 1: Building a s Request for Quo Single Stage - On 2021-09- 2021-10- 2022-04- 2021-12- hicule pour visite échange IDA / D4340 afety net for the poor in se Post Open - National 1,300.00 1,480.14 Signed tations e Envelope 15 27 09 26 des bénéficiaires FSP et TM lected rural areas DH réparti en deux (02) lot s DRT_21014_DC_MULTISER VICE_AVEC_ALPHA_FSP / Im pressions diverses répartie s en deux (02) lots: AVEC, Component 1: Building a s Pending I Coup de Pouce, et alphabét Request for Quo Single Stage - On 2021-09- 2021-10- 2022-05- IDA / D4340 afety net for the poor in se Post Open - National 6,300.00 0.00 mplement isation pour les bénéficiaire tations e Envelope 15 27 15 lected rural areas ation s FSP dans le District d'Ariv onimamo - FA2 rajout de 6000 nouveaux bénéficiair es et TMDH dans le District de Faratsiho Impression des contrat DRT_21018_DC_PROD_VID Component 1: Building a s Under Impl ÉO_TMDH_FSP / Production Request for Quo Single Stage - On 2021-08- 2021-10- 2021-12- IDA / D4340 afety net for the poor in se Post Open - National 3,300.00 0.00 ementatio vidéo MACC, IP et success s tations e Envelope 30 11 10 lected rural areas n tories pour TMDH et FSP. DRT_21013_DC_ASSURAN Component 1: Building a s Under Impl CE_VE_TMDH_FSP / Assura Request for Quo Single Stage - On 2021-09- 2022-02- 2021-10- 2021-12- IDA / D4340 afety net for the poor in se Post Open - National 1,200.00 0.00 ementatio nce voyage pour visite éch tations e Envelope 15 25 27 26 lected rural areas n ange des bénéficiaires FSP et TMDH DRA_21009_DC_TRANSFER T MONETAIRE_FA3 / Sélecti Component 1: Building a s Under Impl on Opérateur Mobile en ch Request for Quo Single Stage - On 2021-09- 2021-11- 2021-11- 2023-12- IDA / D4340 afety net for the poor in se Post Limited 50,000.00 0.00 ementatio arge du service de transfer tations e Envelope 25 23 20 22 lected rural areas n t monétaire du programme Filets Sociaux de Sécurité F A3 Marché à lots multiples DRT_21024_AON_AP_TMD H_FSP_FA3 / Recrutement d Component 1: Building a s Under Impl Request for Bid Single Stage - On 2021-09- 2022-04- 2021-10- 2021-11- 2022-01- 2021-12- 2022-01- 2025-01- 'Agences payeurs du TMDH IDA / D4340 afety net for the poor in se Post Open - National 1,610,000.00 0.00 ementatio s e Envelope 30 08 12 18 17 05 10 10 et du FSP, réparties en ving lected rural areas n t-huit (28) lots pour FSS FA 3. DRA_21014_DC_IMPR POS TER ET CERTIFICAT _ / Pres Component 1: Building a s Request for Quo Single Stage - On 2021-09- 2022-08- 2021-11- 2022-04- 2021-12- tation pour l'impression et IDA / D4340 afety net for the poor in se Post Open - National 37,000.00 1,952.57 Signed tations e Envelope 25 16 14 08 29 duplication des des poster lected rural areas s format A2 et de certificat des bénéficiaires FSP DRU_21007_AO_TRANSFE RT_MONETAIRE_FA3 / Sélec tion de prestataires de serv ices en charge du service d Component 1: Building a s Request for Bid Single Stage - On 2021-09- 2021-12- 2021-09- 2022-05- 2021-10- 2022-01- 2021-10- 2022-02- 2021-11- 2022-03- 2024-10- e transfert monétaire du pr IDA / D7740 afety net for the poor in se Post Open - National 270,000.00 75,993.78 Signed s e Envelope 13 07 18 13 18 17 28 17 22 29 31 ogramme Filets Sociaux de lected rural areas Sécurité FA3: TMDH à Saka raha, TMDH à Toliara II, FSP à Morombe et TMNC à Amp anihy. Marché repartis en 0 8 LOTS DRK_21009_AO_TRANSFER T_MONETAIRE_FA3 / Recrut Component 1: Building a s Pending I ement Agence payeur/de p Request for Bid Single Stage - On 2021-10- 2021-10- 2021-11- 2021-11- 2021-12- 2024-12- IDA / D7740 afety net for the poor in se Post Open - National 630,000.00 0.00 mplement aiement TMDH du district I s e Envelope 15 20 19 29 24 02 lected rural areas ation kongo-Farafangana et FSP du district Vangaindrano re partis sur 07 lots. DRF_21010_AO_TRANSFER T MONETAIRE_PGP_FA3 / S élection de prestataires de Component 1: Building a s Under Impl services en charge du servi Request for Bid Single Stage - On 2021-09- 2021-12- 2021-09- 2023-02- 2021-10- 2022-01- 2021-11- 2021-12- 2023-12- IDA / D7740 afety net for the poor in se Post Open - National 660,000.00 0.00 ementatio ce de transfert monétaire d s e Envelope 15 07 20 20 20 17 04 03 31 lected rural areas n u programme Filets Sociau x de Sécurité FA3 Marché à lots multiples (13 lots) : 04 lots TMDH et 09 lots FSP Page 7 DG_21035_AO_TRANSFERT _MONETAIRE_FSU / Sélectio n de prestataires de servic Component 1: Building a s es en charge du service de Request for Bid Single Stage - On 2021-10- 2021-11- 2021-10- 2021-11- 2021-12- 2021-11- 2022-04- 2021-12- 2022-05- 2024-12- IDA / D7740 afety net for the poor in se Post Open - National 530,000.00 148,670.90 Signed transfert monétaire du pro s e Envelope 09 10 14 13 10 23 06 15 18 31 lected rural areas gramme Filets Sociaux Urb ains dans la Commune Urb aine d'Antananarivo. Marché répartis en vingt (2 0) lots. DRF_21011_DC_OPERAT M OBILE_FA3 / Sélection d'un Component 1: Building a s Pending I Opérateur Mobile en charg Request for Quo Single Stage - On 2021-09- 2021-11- 2023-12- IDA / D7740 afety net for the poor in se Post Limited 30,000.00 0.00 mplement e du service de transfert m tations e Envelope 25 29 31 lected rural areas ation onétaire du programme Fil ets Sociaux de Sécurité FA 3 Marché à lot unique. DRP_21010_AO_TRANSFER TMONETAIRE_FA3 / Sélectio n de prestataires de servic Component 1: Building a s Request for Bid Single Stage - On 2021-09- 2021-12- 2021-09- 2022-07- 2021-10- 2022-01- 2021-10- 2022-02- 2021-11- 2022-03- 2024-10- es en charge du service de IDA / D4340 afety net for the poor in se Post Open - National 410,000.00 174,838.21 Signed s e Envelope 13 06 18 29 18 17 28 02 17 18 31 transfert monétaire du pro lected rural areas gramme Filets Sociaux de Sécurité FA3. Marché réparti en onze (11 ) lots. DRA_21008_AO_TRANSFER T MONETAIRE_FA3 / Sélecti Component 1: Building a s on de prestataires de servi Request for Bid Single Stage - On 2021-10- 2021-12- 2021-10- 2022-09- 2021-11- 2022-01- 2021-11- 2022-03- 2021-12- 2022-04- 2024-11- IDA / D7740 afety net for the poor in se Post Open - National 440,000.00 30,465.75 Signed ces en charge du service d s e Envelope 08 07 13 08 12 17 22 03 14 05 25 lected rural areas e transfert monétaire du pr ogramme Filets Sociaux de sécurité retaris en quatorze (14 ) lots DG_21033_DC_GOODIES_2 Component 2: Strengtheni Request for Quo Single Stage - On 2021-09- 2021-10- 2021-12- 2021-11- 022 / Edition de goodies fin IDA / D4340 ng safety net administratio Post Open - National 30,000.00 28,528.61 Signed tations e Envelope 08 20 24 19 d'année 2021 n, monitoring and social ac countability DRF_21017_DC_CONFECTI ON T SHIRT_TMDH_FSP / Co Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-11- 2021-12- 2022-01- nfecion des Tee SHIRTs av IDA / D4340 afety net for the poor in se Post Open - National 2,500.00 0.00 mplement tations e Envelope 01 23 12 ec message positif pour les lected rural areas ation bénéficiaires du programm e TMDH et FSP DRK_21012_DC_SUPPORT_ IP_TMDH_FSP / Prestation d Component 1: Building a s Pending I Request for Quo Single Stage - On 2021-11- 2022-01- 2022-07- e service pour Impression d IDA / D7740 afety net for the poor in se Post Open - National 65,640.00 0.00 mplement tations e Envelope 20 15 14 e supports de formation en lected rural areas ation Inclusion Productive TMDH et FSP DRU_21009_ED_TRSMOAG PAYEUR_TMNC FA2-FA3 / S Component 1: Building a s 2021-10- 2021-10- 2021-10- 2021-10- 2021-11- 2021-10- 2022-05- élection d'Agences chargée IDA / D4340 afety net for the poor in se Post Direct Selection Direct 56,630.00 15,398.85 Signed 25 01 30 01 16 02 31 s du service de paiement d lected rural areas es bénéficiaires TMNC SUD Toliara DRU_21014_DC_LOC VOIT Component 1: Building a s Request for Quo Single Stage - On Terminate 2021-10- 2022-05- 2021-11- 2022-07- 2021-12- URES / Transports des mat IDA / D4340 afety net for the poor in se Post Open - National 19,700.00 4,515.73 tations e Envelope d 30 21 28 21 31 ériels et intrants pour FSP e lected rural areas t TMDH DG_21039_IMPRESSION PI ECE_IDENT_BENEF / Fournit Component 1: Building a s Request for Bid Single Stage - On 2021-11- 2021-12- 2021-12- 2022-01- 2022-02- 2022-01- 2022-02- 2022-02- 2022-06- 2022-03- ure et impression pièces d'i IDA / D4340 afety net for the poor in se Post Open - National 400,000.00 31,672.11 Signed s e Envelope 27 13 04 01 01 29 11 26 29 28 dentification des bénéficiair lected rural areas es réparties en deux (02) lo ts. DRF_21024_AAO_RECRUTE MENT_AP_FSP_FA3 / Recrut Component 1: Building a s Pending I Request for Bid Single Stage - On 2021-12- 2021-12- 2022-01- 2022-02- 2022-03- 2024-12- ement des Agences Payeur IDA / D7740 afety net for the poor in se Post Open - National 215,105.00 0.00 mplement s e Envelope 06 11 22 21 28 31 s assurant le paiement des lected rural areas ation bénéficiaires TMDH_ FSP__ FA3 DRA_21026_DC_LOC VEH Component 1: Building a s Under Impl _TMDH FSP / Location véhic Request for Quo Single Stage - On 2021-11- 2022-08- 2021-12- 2022-02- IDA / D4340 afety net for the poor in se Post Open - National 2,000.00 0.00 ementatio ule pour visite échange des tations e Envelope 22 16 25 23 lected rural areas n bénéficiaires FSP et TMDH r épartis en deux (02) lots DG_21047_AON_SUPPORT S COMM FSP / Confection d Component 1: Building a s Request for Bid Single Stage - On 2021-11- 2022-03- 2021-12- 2022-03- 2022-01- 2022-04- 2022-01- 2022-07- 2022-02- 2022-09- 2022-03- e supports de communicati IDA / D4340 afety net for the poor in se Post Open - National 250,000.00 155,929.39 Signed s e Envelope 27 04 04 09 01 05 29 21 26 05 28 on pour le Programme Filet lected rural areas s Sociaux Productifs réparti s en trois (03) lots DRU_21026_DC_LOC VEHI Component 1: Building a s Under Impl Request for Quo Single Stage - On 2021-12- 2022-09- 2022-02- 2023-02- CULE / Location de véhicule IDA / D7740 afety net for the poor in se Post Open - National 8,500.00 0.00 ementatio tations e Envelope 15 16 09 09 pour les missions de super lected rural areas n vision DG_21053_DC_PANNEAUX Component 1: Building a s _VISIBILITE / Conception et Request for Quo Single Stage - On 2021-12- 2022-05- 2022-02- 2022-02- IDA / D4340 afety net for the poor in se Post Open - National 3,000.00 0.00 Signed installation de panneaux d tations e Envelope 29 23 09 24 lected rural areas e visibilité des Bureaux FID en deux (02) lots DRU_21017_DC_PROD VID EO_TMDH_FSP_FA3 / Presta Component 1: Building a s Pending I tion de service pour tourna Request for Quo Single Stage - On 2021-12- 2022-02- 2025-03- IDA / D7740 afety net for the poor in se Post Open - National 7,100.00 0.00 mplement ge et production de film his tations e Envelope 19 13 28 lected rural areas ation toire de vie et grandes éta pes des programmes TMDH et FSP FA3 DRP_21012_DC_LOCVEHIC ULE / Location de véhicules pour le programme de FSS FA2 répartie en deux (2) lot Component 1: Building a s Pending I Request for Quo Single Stage - On 2022-02- 2022-04- 2022-09- s: IDA / D4340 afety net for the poor in se Post Open - National 19,100.00 0.00 mplement tations e Envelope 14 09 06 - Lot 1 : Véhicules 4X4 pour lected rural areas ation le transport des missionnai res du FID - Lot 2 : Véhicules utilitaire s pour le transport des mat ériels MACC/IP vers les site sDG_22002_DC_TRANSITAI TMDH RE_VEHICULES / Sélection Component 1: Building a s Request for Quo Single Stage - On 2022-02- 2022-03- 2022-03- 2022-04- 2022-08- de prestataire en charge d IDA / D4340 afety net for the poor in se Post Open - National 30,000.00 8,236.50 Signed tations e Envelope 08 03 22 19 31 u dédouanement et de l'im lected rural areas matriculation des véhicules de supervision. DRF_22002_DC_TRANSPO Component 1: Building a s Under Impl RT_LOTS TMDH_FSP / Trans Request for Quo Single Stage - On 2022-02- 2022-03- 2022-04- IDA / D4340 afety net for the poor in se Post Open - National 9,500.00 0.00 ementatio port des Lots et KITS de sor tations e Envelope 08 19 03 lected rural areas n tie des bénéficiaires TMDH, FSP DRA_22005_DC_TRANSPO Component 1: Building a s Pending I RT_LOTS TMDH_FSP / Trans Request for Quo Single Stage - On 2022-02- 2022-03- 2022-04- IDA / D4340 afety net for the poor in se Post Open - National 1,100.00 0.00 mplement port des Lots et KITS de sor tations e Envelope 14 28 12 lected rural areas ation tie des bénéficiaires TMDH, FSP DRB_22005_INPRESSION_ Component 1: Building a s Pending I MULTIPLICATION / Services Request for Quo Single Stage - On 2022-02- 2022-04- 2022-05- IDA / D4340 afety net for the poor in se Post Open - National 7,500.00 0.00 mplement d'impression et multiplicati tations e Envelope 21 04 04 lected rural areas ation on d'outils et de supports d e formation DG_22007_AO_AGENTS PA YEURS_FA3 / Sélection de p Component 1: Building a s Under Impl Request for Bid Single Stage - On 2022-04- 2022-04- 2022-04- 2022-05- 2022-05- 2022-05- 2022-05- 2022-07- 2022-06- 2024-10- restataires de services en c IDA / D7740 afety net for the poor in se Post Open - National 750,000.00 0.00 ementatio s e Envelope 01 06 08 23 10 24 24 28 14 31 harge du service de transfe lected rural areas n rt monétaire tous program mes confondus répartis en 16 lots. DG_21024_DC_MAQUETTE Component 1: Building a s Request for Quo Single Stage - On 2021-09- 2021-10- 2021-11- 2021-12- _FSP_R / Acquisition de ma IDA / D4340 afety net for the poor in se Post Open - National 1,000.00 890.93 Signed tations e Envelope 06 25 03 24 quette de zonage permacul lected rural areas ture DRF_22005_ED_ AGENCE P AYEUR_TMNC URGENCE / R Component 1: Building a s Pending I 2022-03- 2022-03- 2022-04- 2022-06- ecrutement des Agences p IDA / D7740 afety net for the poor in se Post Direct Selection Direct 8,750.00 0.00 mplement 24 29 08 07 ayeurs par Entente Directe lected rural areas ation pour le transfert des bénéfi ciaires TMNC réparties en 0 6 lots DG_21024_DC_MAQUETTE Component 1: Building a s Request for Quo 2021-08- 2021-10- 2021-10- 2021-12- _FSP / Acquisition de maqu IDA / D4340 afety net for the poor in se Post 1,000.00 0.00 Canceled tations 29 05 18 17 ette de zonage permacultu lected rural areas re DRT_22013_DC_PANNEAU_ Component 1: Building a s PUB_FSP_FA3 / Mise en pla Request for Quo Single Stage - On 2022-04- 2022-10- 2022-07- 2023-07- IDA / D7740 afety net for the poor in se Post Open - National 18,300.00 0.00 Signed ce de panneau publicitaire tations e Envelope 30 13 03 03 lected rural areas du programme au niveau d e chaque District FSP FA3 DG_22011_DC_AUTOCOLL Component 1: Building a s Request for Quo Single Stage - On 2022-04- 2022-08- 2022-06- 2022-06- ANTS / Impression autocoll IDA / D4340 afety net for the poor in se Post Open - National 5,000.00 0.00 Signed tations e Envelope 29 01 17 30 ants d'identification lected rural areas DRF_22011_DC_TRSPRT_O UTILS_MACC_TMDH_FSP / L Component 1: Building a s Pending I Request for Quo Single Stage - On 2022-05- 2022-07- 2022-08- ocation de camion pour le t IDA / D7740 afety net for the poor in se Post Open - National 26,316.00 0.00 mplement tations e Envelope 29 07 06 ransport des Outils MACC d lected rural areas ation es bénéficiaires du progra mme FSP et TMDH des 06 Districts DRP_22007_DC_LOCATION Component 1: Building a s Pending I CAMION / Location de 2 ca Request for Quo Single Stage - On 2022-05- 2022-06- 2022-09- IDA / D4340 afety net for the poor in se Post Open - National 5,100.00 0.00 mplement mions pour le transport des tations e Envelope 04 22 20 lected rural areas ation matériels MACC et IP vers l es sites d'intervention TMD H DRA_22011_DC_PROD VID EO_TMDH_FSP_FA3 / Presta Component 1: Building a s Under Impl tion de service pour tourna Request for Quo Single Stage - On 2022-05- 2023-01- 2022-07- 2023-07- IDA / D7740 afety net for the poor in se Post Open - National 7,800.00 0.00 ementatio ge et production de film his tations e Envelope 11 24 06 06 lected rural areas n toire de vie et grandes éta pes des programmes TMDH et FSP FA3 DRK_22012_DC_TRANSP_P Component 1: Building a s Pending I ACK_FSP_TMDH / Location Request for Quo Single Stage - On 2022-05- 2022-06- 2022-07- IDA / D4340 afety net for the poor in se Post Open - National 5,000.00 0.00 mplement de camion pour le transpor tations e Envelope 11 19 04 lected rural areas ation t des packs de sortie TMDH /FSP DRA_22013_DC_LOC CAMI ON_TRANSP OUTILS_M / Lo Component 1: Building a s Pending I Request for Quo Single Stage - On 2022-05- 2022-06- 2022-08- cation de camion pour le tr IDA / D4340 afety net for the poor in se Post Open - National 5,200.00 0.00 mplement tations e Envelope 09 20 19 ansport des outils MACC d lected rural areas ation es programmes TMDH/FSP FA3 DRA_22010_DC_PANNEAU _AFFICHAGE _FSP TMDH / C Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-07- 2023-01- 2022-08- 2023-02- onfection et pose panneau IDA / D7740 afety net for the poor in se Post Open - National 12,600.00 0.00 ementatio tations e Envelope 04 24 29 25 d'affichage grand format e lected rural areas n n vue de visibilité de progr amme DRA_22015_DC_IMPRESSI ON ET DUPLICATION / Imp Component 1: Building a s Pending I Request for Quo Single Stage - On 2022-07- 2022-09- 2022-10- ression et multiplication de IDA / D4340 afety net for the poor in se Post Open - National 1,980.00 0.00 mplement tations e Envelope 25 05 05 contrat de six mille (6000) lected rural areas ation bénéficiaires du programm e FSU sur papier A 4 DG_21025_CONNEXION_IN Component 2: Strengtheni Request for Quo Single Stage - On 2021-09- 2021-10- 2022-12- TERNET / Service d'accès in IDA / D4340 ng safety net administratio Post Limited 10,000.00 0.00 Canceled tations e Envelope 01 27 31 ternet avec box n, monitoring and social ac countability DRK_22010_DC_STELE_FS Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-07- 2022-11- 2022-09- 2023-03- P_TMDH / Confection et mis IDA / D7740 afety net for the poor in se Post Open - National 4,600.00 0.00 ementatio tations e Envelope 24 23 18 17 e en place des stèles FSP ( lected rural areas n 02) et TMDH (04) DRF_22009_DC_STELE_FSP Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-07- 2022-09- 2022-10- _TMDH / Confection et pose IDA / D7740 afety net for the poor in se Post Open - National 5,270.00 0.00 ementatio tations e Envelope 31 25 25 de stèles au niveau des 05 lected rural areas n Districts DRT_22012_DC_STÈLE_FSP Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-09- 2022-09- 2022-10- 2023-04- _FA3 / Confection et pose d IDA / D7740 afety net for the poor in se Post Open - National 8,000.00 0.00 ementatio tations e Envelope 03 02 29 27 es stèles FSP. lected rural areas n DRU_22003_DC_TRANSFM ONE_TMDH FA3 RELANCE / Component 1: Building a s Under Impl Sélection de prestataires d Request for Quo Single Stage - On 2022-09- 2022-10- 2022-10- 2024-11- IDA / D7740 afety net for the poor in se Post Open - National 35,000.00 0.00 ementatio e services en charge du ser tations e Envelope 04 05 30 08 lected rural areas n vice de transfert monétaire du programmes TMDH répa rtis en 01 lot (Relance). DG_22033_DC_MAQUETTE Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-09- 2022-12- 2022-10- 2022-12- S_TMDH / Confection de m IDA / D7740 afety net for the poor in se Post Open - National 10,000.00 0.00 ementatio tations e Envelope 09 07 28 27 aquettes sites vitrines TMD lected rural areas n H DG_22034_DC_OUTILS_PA Component 1: Building a s Request for Quo Single Stage - On 2022-09- 2022-10- 2022-10- 2022-11- PIER_TMDH / Impression et IDA / D7740 afety net for the poor in se Post Open - National 15,000.00 0.00 Signed tations e Envelope 13 17 25 24 multiplication de badges et lected rural areas affiches TMDH DG20DC_COVID_COMM20 Component 1: Building a s 17 / Multiplication d'outils d Request for Quo Single Stage - On 2020-04- 2020-04- 2020-05- IDA / 57080 afety net for the poor in se Post Limited 15,000.00 0.00 Canceled e sensibilisation dans le ca tations e Envelope 16 22 06 lected rural areas dre de la mise en œuvre de s TMNC (COVID19) DG_22005_ED_AP_TMNC_A NA_URGENCE / Sélection d Component 1: Building a s e prestataires chargés de p 2022-02- 2022-02- 2022-02- 2022-03- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 30,000.00 0.00 Canceled aiement des Transferts Mo 07 07 28 30 lected rural areas nétaires Non Conditionnels au bénéfice des sinistrés su ite au passage de Anna DG_22041_DC_GOODIES_2 Component 1: Building a s Request for Quo Single Stage - On 2022-10- 2022-11- 2022-12- 2023-01- 023 / Confection de goodie IDA / D7740 afety net for the poor in se Post Open - National 45,000.00 0.00 Signed tations e Envelope 28 09 16 15 s pour l'année 2023 lected rural areas DRP_22010_DC_STELE TM DH_FSS FA3 / Mise en place Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-10- 2022-11- 2022-12- 2023-06- de stèle FIAVOTA pour les n IDA / D7740 afety net for the poor in se Post Open - National 6,500.00 0.00 ementatio tations e Envelope 25 25 20 18 ouvelles communes d'inter lected rural areas n vention du programme FSS Financement Addtionnel 3 DRP_22011_DC_PANNEAU Component 1: Building a s Pending I X FIAVOTA_AZ / Mise en pla Request for Quo Single Stage - On 2022-11- 2023-01- 2023-07- IDA / D7740 afety net for the poor in se Post Open - National 6,100.00 0.00 mplement ce de Panneaux d'affichage tations e Envelope 20 15 14 lected rural areas ation des indicateurs pertinents pour les 2 Régions FIAVOTA DRP_22012_DC_PRODUCTI Component 1: Building a s Pending I ON VIDEO CAP_FIAVOT / To Request for Quo Single Stage - On 2022-10- 2022-12- 2023-06- IDA / D7740 afety net for the poor in se Post Open - National 2,200.00 0.00 mplement urnage et production de vi tations e Envelope 20 15 13 lected rural areas ation déo de capitalisation du pr ogramme FIAVOTA DRF_22018_DC_FRNT_BUR _ENTRET / Achat et livraiso Component 1: Building a s Under Impl n des fournitures de burea Request for Quo Single Stage - On 2022-11- 2023-01- 2023-01- 2023-06- IDA / D7740 afety net for the poor in se Post Open - National 45,000.00 0.00 ementatio u, produit d'entretien de la tations e Envelope 25 25 13 30 lected rural areas n Direction Inter-Régional du FID Fianarantsoa repartie e n trois (03) lots DG_22050_DC_AP_TMNC_A CT_PC_URGENCE / Sélectio n de prestataires (Agences Component 1: Building a s Pending I Request for Quo Single Stage - On 2022-12- 2023-01- 2023-07- de paiement) chargés du s IDA / D7740 afety net for the poor in se Post Open - National 200,000.00 0.00 mplement tations e Envelope 24 28 27 ervice de transferts monét lected rural areas ation aires et paiements des bén éficiaires des ACT/TMNC po st-cycloniques DRU_22006_DC_LOC VOIT URE_MAT_INTRA_EMBEL / T Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-11- 2023-01- 2023-01- 2023-04- ransports des matériels et i IDA / D7740 afety net for the poor in se Post Open - National 18,000.00 0.00 ementatio tations e Envelope 21 23 01 01 ntrants pour FSP/TMDH et lected rural areas n matériels d'embellissement TMDH (03 lots) DRU_21002_DC_LOCVOITU RES_VISITES ECHTMDH / Lo Component 1: Building a s Request for Quo Single Stage - On 2021-04- 2021-05- 2021-11- cations de voitures pour vis IDA / D4340 afety net for the poor in se Post Open - National 3,800.00 0.00 Canceled tations e Envelope 24 29 25 ites d'échange des Bénéfici lected rural areas aires TMDH en deux (02) lo ts : Districts Betioky et Toli ara II DRF_22023_DC_LOCATION _VEHICUL__FA3 / Location d Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-11- 2023-02- 2023-01- 2023-12- es vehicules pour les missi IDA / D7740 afety net for the poor in se Post Open - National 32,000.00 0.00 ementatio tations e Envelope 29 08 17 31 on au sein de la Direction I lected rural areas n nter-Regionale de Fianaran tsoa DRA_22021_DC_CONS STE Component 1: Building a s Pending I LE_CONFECTION_FSU / Con Request for Quo Single Stage - On 2022-12- 2023-02- 2023-08- IDA / D7740 afety net for the poor in se Post Open - National 5,000.00 0.00 mplement fection et pose de stèles et tations e Envelope 24 18 17 lected rural areas ation de panneaux de visibilité d e programme FSU DG_22054_DC_DIVERS_SU Component 1: Building a s Request for Quo Single Stage - On 2022-12- 2023-02- 2023-01- 2023-02- PPORTS_TMDH / Confection IDA / D4340 afety net for the poor in se Post Open - National 35,000.00 0.00 Signed tations e Envelope 05 02 23 22 de supports et outils pour l lected rural areas e programme TMDH DRK_22016_DC_VIDEO / T Component 1: Building a s Under Impl Request for Quo Single Stage - On 2022-12- 2023-06- 2023-01- 2023-07- ournage des vidéos pour la IDA / D7740 afety net for the poor in se Post Open - National 6,000.00 0.00 ementatio tations e Envelope 06 16 31 30 réalisation des activités TM lected rural areas n DH, FSP, et INFRA DRT_23002_DC_PROD_FIL Component 1: Building a s Pending I M_FSP_FA3 / Production de Request for Quo Single Stage - On 2023-06- 2023-08- 2023-11- IDA / D7740 afety net for the poor in se Post Open - National 8,000.00 0.00 mplement film success story au nivea tations e Envelope 24 05 03 lected rural areas ation u des bénéficiaires FSP dan s les six Districts. DRT_23005_DC_IMPRES_D UPLIC_ OUTILS / Impression et multiplication de divers Component 1: Building a s Under Impl documents répartis en deu Request for Quo Single Stage - On 2022-12- 2023-03- 2023-02- 2024-01- IDA / D7740 afety net for the poor in se Post Open - National 15,000.00 0.00 ementatio x lots: tations e Envelope 24 06 04 30 lected rural areas n lot 1: Multiplication de 36 0 00 Job aids livret technique lot 2: Multiplication contrat s des bénéficiaires FSP DRP_23008_DC_SERVICES _DUPLICATION_ALPHAB / M ultiplication des matériels d Component 1: Building a s Under Impl Request for Quo Single Stage - On 2023-02- 2023-04- 2023-04- 2023-05- idactiques pour les Centre IDA / D7740 afety net for the poor in se Post Open - National 41,000.00 0.00 ementatio tations e Envelope 15 02 12 27 s d'alphabétisation dans le lected rural areas n s nouvelles et anciennes co mmunes d'intervention FIA VOTA.- Région Anosy DG_23013_DC_MULTIPL_O UTILS_DOC_2023 / Impressi Component 1: Building a s Under Impl Request for Quo Single Stage - On 2023-04- 2023-06- 2023-05- 2023-06- on et Multiplication d'outils IDA / D7740 afety net for the poor in se Post Open - National 40,000.00 0.00 ementatio tations e Envelope 06 15 29 29 pour la sous composante F lected rural areas n SP_TMDH et FSU (DRA et DI RGEN) DRK_23006_DC_PANNEAU PUB_FSP_TMDH / Confectio Component 1: Building a s Pending I n et mise en place des pan Request for Quo Single Stage - On 2023-05- 2023-06- 2023-12- IDA / D7740 afety net for the poor in se Post Open - National 9,000.00 0.00 mplement neaux publicitaires - impre tations e Envelope 02 27 24 lected rural areas ation ssion affichage grand form at en vue de visibilité du pr ogramme FSS FA3 DG_23024_DC_LOCATION_ Component 1: Building a s Under Impl Request for Quo Single Stage - On 2023-06- 2023-05- 2023-08- 2024-10- SERVEUR_CLOUD / Fournitu IDA / D7740 afety net for the poor in se Post Open - National 10,000.00 0.00 ementatio tations e Envelope 09 15 04 31 re de service de location de lected rural areas n serveur cloud Page 8 DG_23018_DC_SUPPORTS_ Component 1: Building a s Pending I COMM_2023 / Confection et Request for Quo Single Stage - On 2023-05- 2023-07- 2023-08- IDA / D7740 afety net for the poor in se Post Open - National 80,000.00 0.00 mplement multiplication de supports tations e Envelope 26 21 20 lected rural areas ation de communication répartis en 04 lots CONSULTING FIRMS Activity Reference No Short List and Draft Opening of Technic Combined Evaluati Loan / Credit Market Appro Contract Type Estimated A Actual Amo Process Stat Expression of Inter Request for Propos Evaluation of Tech Contract Completio . / Description Component Review Type Method Terms of Reference Request for Propos al Proposals / Minut on Report and Draf Signed Contract No. ach mount (US$) unt (US$) us est Notice als as Issued nical Proposal n als es t Negotiated Contr Planned Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne act Actual Planne Actual Planne Actual d d d d d d d d DRP83CFAGEX17001 / EN Component 1: Building a s Consultant Qual 2017-04-0 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-05- 2017-05- 2017-05- 2017-06- 2017-07- CADREMENT ACT POST CAT IDA / D1450 afety net for the poor in se Post ification Selecti Open - National 4,375.00 6,543.44 Completed 7 05 14 01 09 10 17 14 19 13 13 A RANOPISO REGION ANOS lected rural areas on Y DRP83CFAGEX17002 / EN Component 1: Building a s Consultant Qual 2017-04-0 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- CADREMENT ACT POST CAT IDA / D1450 afety net for the poor in se Post ification Selecti Open - National 4,375.00 0.00 Canceled 7 14 01 10 14 13 A ANALAPATSY REGION AN lected rural areas on OSY DRF11CFAGEC17001 / MA Component 1: Building a s Quality And Cos 2017-04-2 2019-03- 2017-04- 2017-05- 2019-03- 2017-06- 2019-03- 2017-07- 2019-04- 2017-07- 2017-07- 2018-07- RCHES MULTIPLES ENCADR IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 10,117.37 0.00 Canceled 3 11 30 18 15 02 26 03 02 06 10 10 EMENT DES UTB EN ACTP lected rural areas n DRA13MOINF17001 / Maitr Component 1: Building a s Consultant Qual ise d'œuvre des infrastruct 2017-05-0 2017-07- 2017-05- 2017-05- 2017-07- 2017-06- 2017-07- 2017-06- 2017-08- 2018-12- 2019-03- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 5,161.29 4,544.55 Completed ures N°01 et N°02 dans la r 8 05 15 22 05 06 28 13 02 26 27 lected rural areas on égion d' Analanjirofo (Toam asina). DRK13CFMO17001 / MAIT Component 1: Building a s RISE D'ŒUVRE DES TRAVA Least Cost Sele 2017-05-1 2017-06- 2017-05- 2017-05- 2017-07- 2017-06- 2017-07- 2017-06- 2017-07- 2017-06- 2017-08- 2017-06- 2017-08- 2017-12- 2018-04- IDA / 57080 afety net for the poor in se Post Open - National 3,870.97 5,215.22 Completed UX DE REHABILITATION DE ction 0 15 10 20 13 04 24 05 25 08 07 15 10 12 19 lected rural areas S OUVRAGRES VOHITRINDR Y ILAKATRA DRP83CFBE17001 / MAITRI Component 1: Building a s Least Cost Sele 2017-05-0 2017-06- 2017-05- 2017-06- 2017-06- 2017-06- 2017-07- 2017-06- 2017-07- 2017-06- 2017-07- 2017-07- 2017-08- 2018-12- 2019-09- SE D'OEUVRE EPP POST CA IDA / 57080 afety net for the poor in se Post Open - National 6,774.19 5,600.27 Completed ction 9 30 10 06 30 21 14 21 17 27 17 07 04 31 03 TA ENAWO AMBOVOMBE 1 lected rural areas DRP83CFBE17002 / MAITRI Component 1: Building a s Least Cost Sele 2017-05-0 2017-07- 2017-05- 2017-06- 2017-06- 2017-06- 2017-07- 2017-06- 2017-07- 2017-06- 2017-07- 2017-07- 2017-08- 2018-12- 2019-07- SE D'OEUVRE EPP POSTEN IDA / 57080 afety net for the poor in se Post Open - National 9,032.26 7,169.65 Completed ction 9 17 09 06 30 21 14 21 17 27 17 07 07 31 08 AWO AMBOVOMBE2 lected rural areas DG11CFAGFDF17001 / Age nce chargée de l'élaboratio n d'un guide pour la format ion des formateurs des age Component 1: Building a s Consultant Qual 2017-05-1 2017-05- 2017-06- 2017-07- 2017-08- 2019-04- nces de mise en oeuvre en IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 60,000.00 0.00 Canceled 2 19 11 25 02 30 matière d'épargne commu lected rural areas on nautaire et de développem ent d'affaires dans les activ ités ACT-P du Projet de Filet s Sociaux mis en oeuvre pa r le FID DG23CFFORMSIG17002 / F Component 2: Strengtheni Consultant Qual 2017-06-0 2017-06- 2017-06- 2017-06- 2017-08- 2017-07- 2017-09- 2017-07- 2017-09- 2017-08- 2017-10- ormation des personnels d IDA / 57080 ng safety net administratio Post ification Selecti Open - National 693.75 1,580.42 Completed 7 07 14 27 18 17 05 21 13 20 17 u FID sur l'utilisation des SI n, monitoring and social ac on G countability DRT11CFPLAN17001 / Age nce de planification chargé Component 1: Building a s Consultant Qual 2017-07-1 2017-07- 2017-08- 2017-08- 2017-09- 2019-04- e du suivi et supervision de IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 15,000.00 0.00 Canceled 8 19 07 27 03 26 s chantier, suivi évaluation lected rural areas on communautaire, mise à jou r des PAMO DRT11CFPLAN17002 / Age nce de planification chargé Component 1: Building a s Consultant Qual 2017-07-1 2017-07- 2017-08- 2017-08- 2017-09- 2019-04- e du suivi et supervision de IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 15,000.00 0.00 Canceled 8 19 07 27 03 26 s chantiers, suivi évaluatio lected rural areas on n communautaire, mise à j our des PAMO DRT11CFPLAN17003 / Age nce de planification chargé Component 1: Building a s Consultant Qual 2017-07-1 2017-07- 2017-08- 2017-08- 2017-09- 2019-04- e du suivi et supervision de IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 15,000.00 0.00 Canceled 8 19 07 27 03 26 s chantiers, suivi évaluatio lected rural areas on n communautaire, mise à j our des PAMO DG81CFPLAT1701 / FOURN Component 1: Building a s Consultant Qual 2017-07-2 2017-07- 2017-08- 2017-09- 2017-09- 2018-12- ITURE DE SERVICE EN PLAT IDA / D1450 afety net for the poor in se Post ification Selecti Open - National 30,000.00 0.00 Canceled 6 28 17 11 15 14 E FORME INTERNET DE COL lected rural areas on LECTE DE DONNÉES DRK11CFSECCS1702 / Sui Component 1: Building a s Quality And Cos vi-Évaluation Communautai 2017-08-2 2017-08- 2017-09- 2017-10- 2017-10- 2017-10- 2017-10- 2020-04- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 7,419.35 0.00 Canceled re, Mis a jours PAMO, Contr 1 22 10 08 12 19 29 16 lected rural areas n ôle et Suivi UTB ONILAHY - FENOMBY - BENIHAONANA DRK11CFSECCS1703 / Sui vi-Évaluation Communautai Component 1: Building a s Quality And Cos re, Mis a jours PAMO, Contr 2017-08-2 2017-08- 2017-09- 2017-10- 2017-10- 2017-10- 2017-10- 2020-04- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 9,677.42 0.00 Canceled ôle et Suivi UTB VOHILAVA 1 22 10 08 12 19 29 16 lected rural areas n - AMBOHIMANARIVO MANG AIKA - SAHANABOHITRA - A MBORONDRA DRK11CFSECCS1704 / Sui vi-Évaluation Communautai Component 1: Building a s Quality And Cos 2017-08-2 2017-08- 2017-09- 2017-10- 2017-10- 2017-10- 2017-10- 2020-04- re, Mis a jours PAMO, Contr IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 7,419.35 0.00 Canceled 1 22 10 08 12 19 29 16 ôle et Suivi UTB MAROFARI lected rural areas n HY - MIZILO GARA - FENOA RIVO DG12CFCIB1701 / Ciblage Component 1: Building a s Consultant Qual 2017-09-0 2017-09- 2017-09- 2017-10- 2017-10- 2017-12- Enquête Enregistrement bé IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,135.48 0.00 Canceled 7 07 23 14 27 26 néficiaires nouvelles com lected rural areas on munes BETIOKY LOT 1 DG12CFCIB1702 / Ciblage Component 1: Building a s Consultant Qual Enquête Enregistrement bé 2017-09-0 2017-09- 2017-09- 2017-10- 2017-10- 2017-12- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 2,090.32 0.00 Canceled néficiaires nouvelles com 7 07 23 14 17 16 lected rural areas on munes VOHIPENO LOT 2 DRT11CFPLAN17004 / Age nce de planification chargé Component 1: Building a s Quality And Cos 2017-11-1 2017-05- 2017-11- 2017-11- 2018-01- 2017-12- 2018-02- 2017-12- 2018-02- 2018-01- 2018-03- 2018-01- 2018-04- 2019-04- e de suivi et de supervision IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 15,000.00 14,243.10 Signed 3 31 14 30 22 28 23 28 27 08 27 18 17 30 de chantier, suivi évaluatio lected rural areas n n communautaire, mise à j our PAMO DRT11CFPLAN17005 / Age nce de planification chargé Component 1: Building a s Quality And Cos 2017-11-1 2017-05- 2017-11- 2017-11- 2018-01- 2017-12- 2018-02- 2017-12- 2018-02- 2018-01- 2018-03- 2018-01- 2018-04- 2019-04- e du suivi et supervision de IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 15,000.00 12,029.98 Signed 3 31 14 30 22 28 23 28 27 08 27 18 17 30 s chantiers, suivi évaluatio lected rural areas n n communautaire, mise à j our des PAMO DRT11CFPLAN17006 / Age nce de planification chargé Component 1: Building a s Quality And Cos 2017-11-1 2017-05- 2017-11- 2017-11- 2018-01- 2017-12- 2018-02- 2017-12- 2018-02- 2018-01- 2018-01- 2019-04- e du suivi et supervision de IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 15,000.00 0.00 Canceled 3 31 14 30 22 28 23 28 27 08 18 30 s chantiers, suivi évaluatio lected rural areas n n communautaire, mise à j our des PAMO Component 1: Building a s Consultant Qual DRT11CFSEN1701 / Agenc 2017-11-1 2017-11- 2017-12- 2018-01- 2018-01- 2019-05- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 21,564.13 0.00 Canceled e de sensibilisation 7 24 11 03 11 31 lected rural areas on DRA11CFSEN1701 / Agenc Component 1: Building a s Consultant Qual 2017-11-1 2017-11- 2017-12- 2018-01- 2018-01- 2019-05- e de Sensibilisation ACTP V IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 20,584.64 0.00 Canceled 7 24 11 03 11 31 atomandry lected rural areas on DRK11CFAGEC17001 / CO Component 1: Building a s Quality And Cos LLECTE DE DONNÉES ET E 2017-11-2 2018-01- 2017-11- 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-03- 2018-01- 2018-04- 2020-01- 2019-08- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 64,516.13 30,964.76 Completed NCADREMENT UTB FENOAR 8 03 29 18 05 08 20 12 07 16 18 21 13 21 21 lected rural areas n IVO II ET MIZILO GARA MAN AKARA DRK11CFAGEC17002 / CO Component 1: Building a s Quality And Cos Under Impleme 2017-11-2 2017-11- 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2020-01- LLECTE DE DONNÉES ET E IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 32,258.06 0.00 ntation 8 29 18 08 12 16 21 21 NCADREMENT UTB MAROF lected rural areas n ARIHY MANAKARA Component 1: Building a s Quality And Cos DRK12CFAGEC17001 / MA 2017-12-0 2017-12- 2018-01- 2018-01- 2018-01- 2018-02- 2018-02- 2020-02- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 4,356.33 0.00 Canceled RCHE MULTIPLE 3 04 05 26 30 03 08 08 lected rural areas n Component 1: Building a s Quality And Cos DRK12CFAGEC17002 / MA 2017-12-0 2017-12- 2018-01- 2018-01- 2018-01- 2018-02- 2018-02- 2020-02- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 5,576.44 0.00 Canceled RCHE MULTIPLE 3 04 05 26 30 03 08 08 lected rural areas n DRU11CFAGEC001 / ACTP Component 1: Building a s Quality And Cos 2017-11-2 2017-10- 2017-12- 2017-12- 2017-11- 2018-01- 2017-11- 2018-01- 2017-12- 2018-01- 2018-02- 2018-01- 2018-03- 2020-01- Encadrement marché multi IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 14,696.97 11,730.49 Signed 9 25 14 20 13 10 28 13 01 23 06 30 09 30 ples UTB 06 Antsoha lected rural areas n DRF11CFAGEC180001 / M Component 1: Building a s Quality And Cos 2018-03-1 2019-03- 2018-04- 2018-05- 2019-03- 2018-05- 2019-03- 2018-06- 2019-04- 2018-06- 2019-06- 2018-06- 2019-06- 2019-06- 2019-08- ARCHE MULTIPLE AGENCE IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 10,117.37 6,275.27 Completed 1 11 01 16 15 31 26 02 11 06 03 10 11 10 21 D'ENCADREMENT ACTP lected rural areas n DRF13PCAGEX18001 / EN Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 648.14 Completed 6 15 17 19 16 02 18 07 18 28 16 CT Post catastrophe FKT1 - lected rural areas on Ifanadiana DRF13PCAGEX18002 / EN Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 Canceled 6 15 17 19 18 02 07 28 CT Post catastrophe FKT2 - lected rural areas on Ifanadiana DRF11CFSENS18001 / AGE Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-02- 2018-02- 2019-02- NCE DE SENSIBILISATION A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 22,975.07 0.00 Canceled 6 17 24 12 19 19 CTP ISANDRA lected rural areas on DRT13CFAGEX1801 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 362.71 Completed 7 11 17 17 12 02 15 07 15 28 27 atastrophe dans le Fokonta lected rural areas on ny 1, Antananarivo Renivoh itra DRT13CFAGEX1802 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 362.71 Completed 7 11 17 17 12 02 15 07 15 28 27 atastrophe dans le Fokonta lected rural areas on ny 2, Antananarivo Renivoh itra DRT13CFAGEX1803 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 362.71 Completed 7 11 17 17 12 02 15 07 15 28 27 atastrophe dans le Fokonta lected rural areas on ny 3, Antananarivo Renivoh itra DRA13CFAGEX18001 / LOT Component 1: Building a s Consultant Qual 1 ENCADREMENT - PAIEME 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 16,591.05 1,741.78 Completed NT ACT POST CATASTROP 7 14 17 17 15 02 16 07 17 28 19 lected rural areas on HE DES 04 FKT DIST BRICK AVILLE DRA13CFAGEX18002 / LOT Component 1: Building a s Consultant Qual 2 ENCADREMENT - PAIEME 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-03- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 12,442.25 1,189.19 Completed NT ACT POST CATASTROP 7 14 17 17 14 02 16 07 17 28 06 lected rural areas on HE DES 04 FKT DIST TOAM ASINA II DRA13CFAGEX18003 / LOT Component 1: Building a s Consultant Qual 3 ENCADREMENT - PAIEME 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 16,589.67 1,577.47 Completed NT ACT POST CATASTROP 7 14 17 17 14 02 16 07 17 28 19 lected rural areas on HE DES 04 FKT DIST TOAM ASINA I DRA13CFAGEX18004 / LOT Component 1: Building a s Consultant Qual 4 ENCADREMENT - PAIEME 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-03- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 16,589.67 1,624.03 Completed NT ACT POST CATASTROP 7 14 17 17 14 02 16 07 17 28 06 lected rural areas on HE DES 04 FKT DIST TOAM ASINA I DRA13CFAGEX18005 / LOT Component 1: Building a s Consultant Qual 5 ENCADREMENT - PAIEME 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-03- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 16,589.67 1,561.19 Completed NT ACT POST CATASTROP 7 14 17 17 15 02 16 07 17 28 07 lected rural areas on HE DES 04 FKT DIST TOAM ASINA I DRA13CFAGEX18006 / LOT Component 1: Building a s Consultant Qual 6 ENCADREMENT - PAIEME 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 12,442.25 1,197.21 Completed NT ACT POST CATASTROP 7 14 17 17 15 02 16 07 17 28 15 lected rural areas on HE DES 03 FKT DIST TOAM ASINA I DRA13CFAGEX18007 / LOT Component 1: Building a s Consultant Qual 7 ENCADREMENT - PAIEME 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 12,442.25 1,217.56 Completed NT ACT POST CATASTROP 7 14 17 17 15 02 16 07 17 28 15 lected rural areas on HE DES 03 FKT DIST TOAM ASINA I DRT13CFAGEX1804 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 362.71 Completed 7 11 17 17 12 02 15 07 15 28 27 atastrophe dans le Fokonta lected rural areas on ny 4, Antananarivo Renivoh itra DRT13CFAGEX1805 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 366.91 Completed 7 11 17 17 12 02 15 07 15 28 28 atastrophe dans le Fokonta lected rural areas on ny 5, Antananarivo Renivoh itra DRT13CFAGEX1806 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 366.91 Completed 7 11 17 17 12 02 15 07 15 28 28 atastrophe dans le Fokonta lected rural areas on ny 6, Antananarivo Renivoh itra DRT13CFAGEX1807 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 373.05 Completed 7 11 17 17 12 02 15 07 15 28 28 atastrophe dans le Fokonta lected rural areas on ny 7, Antananarivo Renivoh itra DRT13CFAGEX1808 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 367.51 Completed 7 11 17 17 12 02 15 07 15 28 28 atastrophe dans le Fokonta lected rural areas on ny 8, Antananarivo Renivoh itra DRT13CFAGEX1809 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-04- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 380.35 Completed 7 11 17 17 12 02 15 07 15 28 30 atastrophe dans le Fokonta lected rural areas on ny 9, Antananarivo Renivoh itra DRT13CFAGEX1810 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-04- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 380.35 Completed 7 11 17 17 12 02 15 07 15 28 24 atastrophe dans le Fokonta lected rural areas on ny 10, Antananarivo Renivo hitra DRT13CFAGEX1811 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-04- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 380.35 Completed 7 11 17 17 12 02 15 07 15 28 30 atastrophe dans le Fokonta lected rural areas on ny 1, Antananarivo Atsimo ndrano DRT13CFAGEX1812 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-04- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 380.35 Completed 7 11 17 17 12 02 15 07 15 28 30 atastrophe dans le Fokonta lected rural areas on ny 2, Antananarivo Atsimo ndrano DRT13CFAGEX1813 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-04- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 374.26 Completed 7 11 17 17 12 02 15 07 15 28 18 atastrophe dans le Fokonta lected rural areas on ny 3, Antananarivo Atsimo ndrano DRT13CFAGEX1814 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-04- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 374.26 Completed 7 11 17 17 12 02 15 07 15 28 18 atastrophe dans le Fokonta lected rural areas on ny 4, Antananarivo Atsimo ndrano DRT13CFAGEX1815 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-04- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 374.26 Completed 7 11 17 17 12 02 15 07 15 28 18 atastrophe dans le Fokonta lected rural areas on ny 5, Antananarivo Atsimo ndrano DRT13CFAGEX1816 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-04- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 374.26 Completed 7 11 17 17 12 02 15 07 15 28 18 atastrophe dans le Fokonta lected rural areas on ny 6, Antananarivo Atsimo ndrano DRT13CFAGEX1817 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 372.74 Completed 7 11 17 17 12 02 15 07 15 28 27 atastrophe dans le Fokonta lected rural areas on ny 7, Antananarivo Atsimo ndrano DRT13CFAGEX1818 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 372.74 Completed 7 11 17 17 12 02 15 07 15 28 27 atastrophe dans le Fokonta lected rural areas on ny 8, Antananarivo Atsimo ndrano DRT13CFAGEX1819 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 372.74 Completed 7 11 17 17 12 02 15 07 15 28 27 atastrophe dans le Fokonta lected rural areas on ny 9, Antananarivo Atsimo ndrano DRT13CFAGEX1820 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-02- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 372.90 Completed 7 11 17 17 12 02 15 07 15 28 27 atastrophe dans le Fokonta lected rural areas on ny 10, Antananarivo Atsim ondrano DRT13CFAGEX1821 / Enca Component 1: Building a s Consultant Qual drement et paiement des b 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-03- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 402.86 Completed énéficiaires de l'ACT post c 7 11 17 17 12 02 15 07 15 28 16 lected rural areas on atastrophe dans le Fokonta ny 1, Andasibe DRT13CFAGEX1822 / Enca Component 1: Building a s Consultant Qual drement et paiement des b 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-03- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 402.86 Completed énéficiaires de l'ACT post c 7 11 17 17 12 02 15 07 15 28 16 lected rural areas on atastrophe dans le Fokonta ny 1, Moramanga DRT13CFAGEX1823 / Enca Component 1: Building a s Consultant Qual drement et paiement des b 2018-01-1 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- 2018-01- 2018-02- 2018-01- 2018-02- 2018-03- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 402.86 Completed énéficiaires de l'ACT post c 7 11 17 17 12 02 15 07 15 28 16 lected rural areas on atastrophe dans le Fokonta ny 2, Moramanga DRK13CFAGEX18001 / EN Component 1: Building a s Consultant Qual Under Impleme 2018-01-1 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 ntation 9 19 19 04 09 20 CT Post catastrophe FKT1 - lected rural areas on MANAKARA Page 9 DRK13CFAGEX18002 / EN Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 Canceled 9 19 19 04 09 20 CT Post catastrophe FKT2 - lected rural areas on MANAKARA DRK13CFAGEX18003 / EN Component 1: Building a s Consultant Qual Under Impleme 2018-01-1 2017-02- 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 ntation 9 23 19 19 04 09 20 CT Post catastrophe FKT3 - lected rural areas on VOHIPENO DRK13CFAGEX18004 / EN Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 Canceled 9 19 19 04 09 20 CT Post catastrophe FKT4 - lected rural areas on VOHIPENO DRK13CFAGEX18005 / EN Component 1: Building a s Consultant Qual Under Impleme 2018-01-1 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 ntation 9 19 19 04 09 20 CT Post catastrophe FKT5 - lected rural areas on MANANJARY DRK13CFAGEX18006 / EN Component 1: Building a s Consultant Qual 2018-01-1 2018-01- 2018-01- 2018-02- 2018-02- 2018-02- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 Canceled 9 19 19 04 09 20 CT Post catastrophe FKT6 - lected rural areas on MANANJARY Component 2: Strengtheni Consultant Qual DG20CFFEXC1801 / Forma 2018-02-0 2018-03- 2018-02- 2018-02- 2018-02- 2018-03- 2018-03- IDA / 57080 ng safety net administratio Post ification Selecti Open - National 1,109.25 0.00 Canceled tion en Excel avancé DRS 1 28 06 24 27 02 17 n, monitoring and social ac on countability Component 2: Strengtheni Consultant Qual DG20CFFEXC1802 / Forma 2018-02-0 2018-03- 2018-02- 2018-02- 2018-02- 2018-03- 2018-03- IDA / 57080 ng safety net administratio Post ification Selecti Open - National 1,109.25 0.00 Canceled tion en Excel avancé DRA 1 28 06 24 27 02 17 n, monitoring and social ac on countability DG20CFFEXC1803 / Forma Component 2: Strengtheni Consultant Qual 2018-02-0 2018-03- 2018-02- 2018-02- 2018-02- 2018-03- 2018-03- tion en excel avancé DRT e IDA / 57080 ng safety net administratio Post ification Selecti Open - National 1,109.25 0.00 Canceled 1 28 06 24 27 02 03 t DG n, monitoring and social ac on countability Component 2: Strengtheni Consultant Qual DG20CFFEXC1804 / Forma 2018-02-0 2018-03- 2018-02- 2018-02- 2018-02- 2018-03- 2018-03- IDA / 57080 ng safety net administratio Post ification Selecti Open - National 1,109.25 0.00 Canceled tion en excel avancé DRF 1 28 06 24 27 02 17 n, monitoring and social ac on countability Component 2: Strengtheni Consultant Qual DG20CFFEXC1805 / Forma 2018-02-0 2018-03- 2018-02- 2018-02- 2018-02- 2018-03- 2018-03- IDA / 57080 ng safety net administratio Post ification Selecti Open - National 1,109.25 0.00 Canceled tion en excel avancé DRK 1 28 06 24 27 02 17 n, monitoring and social ac on countability Component 2: Strengtheni Consultant Qual DG20CFFEXC1806 / Forma 2018-02-0 2018-03- 2018-02- 2018-02- 2018-02- 2018-03- 2018-03- IDA / 57080 ng safety net administratio Post ification Selecti Open - National 1,109.25 0.00 Canceled tion en excel avancé DRU 1 28 06 24 27 02 17 n, monitoring and social ac on countability Component 2: Strengtheni Consultant Qual DG20CFFEXC1807 / Forma 2018-02-0 2018-03- 2018-02- 2018-02- 2018-02- 2018-03- 2018-03- IDA / 57080 ng safety net administratio Post ification Selecti Open - National 1,109.25 0.00 Canceled tion en excel avancé DRP 1 28 06 24 27 02 17 n, monitoring and social ac on countability DG20CFFPORT1809 / Form Component 2: Strengtheni Consultant Qual 2018-02-0 2018-03- 2018-02- 2018-03- 2018-03- 2018-03- 2018-04- ation en gestion de portefe IDA / 57080 ng safety net administratio Post ification Selecti Open - National 9,317.73 0.00 Canceled 7 28 12 06 09 14 13 uille d'activitées n, monitoring and social ac on countability DG20CFRECDG1811 / CABI Component 2: Strengtheni Quality And Cos 2018-01-3 2017-09- 2018-01- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- 2018-03- 2018-02- 2018-04- 2018-03- 2018-06- 2018-04- 2018-12- NET EN CHARGE DU RECR IDA / 57080 ng safety net administratio Post t-Based Selectio Open - National 2,580.65 1,661.18 Completed 0 19 30 30 08 30 09 01 14 16 10 02 07 01 05 UTEMENT D'UN DIRECTEUR n, monitoring and social ac n GENERAL countability DRT13CFAGEX1824 / Enca Component 1: Building a s Consultant Qual drement et paiement des b 2018-02-2 2018-02- 2018-02- 2018-02- 2018-02- 2018-03- 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 364.53 Completed énéficiaires de l'ACT post c 7 23 27 28 26 03 02 10 02 31 16 lected rural areas on ata dans le Fokontany 1 à Antananarivo Atsimondran o DRT13CFAGEX1825 / Enca Component 1: Building a s Consultant Qual drement et paiement des b 2018-02-2 2018-02- 2018-02- 2018-02- 2018-02- 2018-03- 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 364.53 Completed énéficiaires de l'ACT post c 7 23 27 28 26 03 02 10 02 31 16 lected rural areas on ata dans le Fokontany 2 à Antananarivo Atsimondran o DRF13PCAGEX18003 / EN Component 1: Building a s Consultant Qual 2018-02-2 2018-02- 2018-02- 2018-03- 2018-02- 2018-03- 2018-02- 2018-03- 2018-02- 2018-03- 2018-03- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 3,987.72 Completed 8 22 28 01 27 04 27 10 28 31 23 CT Post Catastrophe FKT 8 lected rural areas on AMBALAVAO DRF13PCAGEX18004 / EN Component 1: Building a s Consultant Qual 2018-02-2 2018-02- 2018-03- 2018-03- 2018-03- 2018-03- CADREMENT -PAIEMENT AC IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 Canceled 8 28 01 04 10 31 T Post Catastrophe FKT 9 A lected rural areas on mbalavao DG13CFAGEX1801 / ENCA Component 1: Building a s Consultant Qual 2018-03-0 2018-02- 2018-03- 2018-03- 2018-03- 2018-03- 2018-03- 2018-03- 2018-03- 2018-09- DREMENT PAIEMENT ACT P IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 12,442.26 1,149.03 Signed 1 23 02 07 28 08 05 10 08 06 OST CATASTROPHE 3 COM lected rural areas on MUNES MAHAJANGA DRK11CFSECCS1701 / Sui vi-Evaluation Communautai re,Mis à jour PAMO, côntrol e et suivi UTB VATANA-MIT Component 1: Building a s Quality And Cos ANTY OUEST-VOHIBOATAV Under Impleme 2017-08-2 2017-08- 2017-08- 2017-09- 2017-10- 2017-10- 2017-10- 2017-10- 2020-04- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 34,193.54 0.00 O-AMBALAROKA-AMBOHITR ntation 1 22 22 10 08 12 19 29 16 lected rural areas n OVA-MAROFARIHY-MIZILO GARA-FENOARIVO-VOHILAV A-AMBOHIMANARIVO MAN GAIKA-SAHANABOHITRA-A MBORONDRA-ONILAHY FEN OMBY-BENIHAONANA DRK13CFAGEX18007 / EN Component 1: Building a s Consultant Qual Under Impleme 2018-03-0 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 ntation 1 01 01 17 22 02 CT Post Catastrophe FKT6 - lected rural areas on Farafangana DRK13CFAGEX18008 / EN Component 1: Building a s Consultant Qual 2018-03-0 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 Canceled 1 01 01 17 22 02 CT Post catastrophe FKT7 - lected rural areas on Farafangana DRK13CFAGEX18009 / EN Component 1: Building a s Consultant Qual Under Impleme 2018-03-0 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 ntation 1 01 01 17 22 02 CT Post catastrophe FKT8 - lected rural areas on Vangaindrano DRK13CFAGEX18010 / EN Component 1: Building a s Consultant Qual 2018-03-0 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- CADREMENT - PAIEMENT A IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 Canceled 1 01 01 17 22 02 CT Post catastrophe FKT9 - lected rural areas on Vangaindrano DRA11CFAGEC18001 / REP Component 1: Building a s Quality And Cos RISE ENCADREMENT ACTP 2018-03-0 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- 2018-03- 2018-04- 2018-03- 2018-04- 2018-04- 2018-04- 2018-05- 2019-06- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 16,569.33 8,508.26 Signed UTB TANAMBAO VAHATRAK 4 02 04 05 06 02 28 03 28 08 10 14 07 30 lected rural areas n AKA- LOT 7 - DISTRICT VA TOMANDRY DRA11CFAGEC18002 / REP Component 1: Building a s Quality And Cos RISE ENCADREMENT ACTP 2018-03-0 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- 2018-03- 2018-04- 2018-03- 2018-04- 2018-04- 2018-04- 2018-05- 2019-06- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 17,442.67 10,451.31 Signed UTB SAHAMATEVINA -LOT 3 4 02 04 05 06 02 28 03 28 08 10 14 07 30 lected rural areas n - DISTRICT VATOMANDRY DRA11CFAGEC18003 / REP Component 1: Building a s Quality And Cos RISE ENCADREMENT ACTP 2018-03-0 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- 2018-03- 2018-04- 2018-03- 2018-04- 2018-04- 2018-04- 2018-05- 2019-06- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 28,899.30 14,286.57 Signed UTB AMPANALANA - UTB A 4 02 04 05 06 02 28 03 28 08 10 15 07 30 lected rural areas n MBALAVOLO - LOT 4 - DIST RICT VATOMANDRY DG13CFAGEX1802 / ENCA Component 1: Building a s Consultant Qual 2018-03-1 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- DREMENT PAIEMENT ACT P IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 Canceled 5 16 21 22 24 23 OST CATASTROPHE ANKAT lected rural areas on AFAHELY CU AMBANJA DG13CFAGEX1803 / ENCA Component 1: Building a s Consultant Qual 2018-03-1 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- DREMENT PAIEMENT ACT P IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 Canceled 5 16 21 22 24 23 OST CATA TANAMBAO V CU lected rural areas on AMBANJA DG13CFAGEX1804 / ENCA Component 1: Building a s Consultant Qual 2018-03-1 2018-03- 2018-03- 2018-03- 2018-03- 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- DREMENT PAIEMENT ACT P IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 1,532.04 Signed 5 16 16 21 20 22 20 24 20 23 OST CATA BEGAVO I CU AM lected rural areas on BANJA DG13CFAGEX1805 / ENCA Component 1: Building a s Consultant Qual 2018-03-1 2018-03- 2018-03- 2018-03- 2018-03- 2018-04- DREMENT PAIEMENT ACT P IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 4,147.42 0.00 Canceled 5 16 21 22 24 23 OST CATA BEGAVO II CU A lected rural areas on MBANJA DRP81CFAGEE18001 / ENC Component 1: Building a s Consultant Qual 2018-04-2 2018-01- 2018-04- 2018-04- 2018-01- 2018-05- 2018-01- 2018-05- 2018-03- 2019-12- ADREMENT REPRISE AGEE IDA / D1450 afety net for the poor in se Post ification Selecti Open - National 43,932.00 36,059.11 Signed 5 19 25 25 19 02 20 03 06 31 TMNC TRANOVAHO BELOH lected rural areas on A DRU11CFAGSEN18001 / A Component 1: Building a s Consultant Qual 2018-04-2 2018-05- 2018-06- 2018-07- 2018-07- 2019-12- CT-P Agence de Sensibilisat IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 9,600.00 0.00 Canceled 8 01 03 06 19 31 ion des UTB dans le district lected rural areas on d'Ankazoabo ARA13CFMO17001 / Maîtri Component 1: Building a s Least Cost Sele 2017-05-2 2017-07- 2017-05- 2017-05- 2017-07- 2017-06- 2017-07- 2017-06- 2017-07- 2017-06- 2017-07- 2017-06- 2017-08- 2018-09- se d'œuvre CEG BELAOKA IDA / 57080 afety net for the poor in se Post Open - National 2,593.10 15,402.99 Signed ction 4 13 24 25 13 09 24 10 26 14 28 23 03 23 LOKOHO - CR BELAOKA LO lected rural areas KOHO - ANDAPA ARA13CFMO17002 / maîtri Component 1: Building a s se d'œuvre travaux EPP SA Least Cost Sele 2017-05-2 2017-05- 2017-05- 2017-06- 2017-06- 2017-06- 2017-06- 2018-09- IDA / 57080 afety net for the poor in se Post Open - National 2,593.10 0.00 Canceled RAHANDRANO - CR AMBOD ction 4 24 25 09 10 14 23 23 lected rural areas IAMPANA - SAMBAVA ARA13CFMO17003 / maîtri Component 1: Building a s Least Cost Sele 2017-05-2 2017-05- 2017-05- 2017-06- 2017-06- 2017-06- 2017-06- 2018-09- se d'œuvre EPP MAHITSIAR IDA / 57080 afety net for the poor in se Post Open - National 2,593.10 0.00 Canceled ction 4 24 25 09 10 14 23 23 ONGANA - CR AMBODIVOA lected rural areas RA - SAMBAVA ARA13CFMO17004 / maîtri Component 1: Building a s Least Cost Sele 2017-05-2 2017-05- 2017-05- 2017-06- 2017-06- 2017-06- 2017-06- 2018-09- se d'œuvre EPP ANKORABE IDA / 57080 afety net for the poor in se Post Open - National 2,593.10 0.00 Canceled ction 4 24 25 09 10 14 23 23 - CR AMBOHIMALAZA - SAM lected rural areas BAVA ARA13CFMO17005 / maîtri Component 1: Building a s Least Cost Sele 2017-05-2 2017-05- 2017-05- 2017-06- 2017-06- 2017-06- 2017-06- 2018-09- se d'œuvre EPP AMPAMPA IDA / 57080 afety net for the poor in se Post Open - National 2,593.10 0.00 Canceled ction 4 24 25 09 10 14 23 23 MENA I - CR ANDRATAMARI lected rural areas NA - SAMBAVA ARA13CFMO17006 / maîtri Component 1: Building a s se d'œuvre ECOLE COMMU Least Cost Sele 2017-05-2 2017-05- 2017-05- 2017-06- 2017-06- 2017-06- 2017-06- 2018-09- IDA / 57080 afety net for the poor in se Post Open - National 2,593.10 0.00 Canceled NAUTAIRE ANDALAMAHITS ction 4 24 25 09 10 14 23 23 lected rural areas Y - CR ANTSIRABE NORD - VOHEMAR ARA13CFMO17007 / maîtri Component 1: Building a s se d'œuvre ECOLE COMMU Least Cost Sele 2017-05-2 2017-05- 2017-05- 2017-06- 2017-06- 2017-06- 2017-06- 2018-09- IDA / 57080 afety net for the poor in se Post Open - National 2,593.10 0.00 Canceled NAUTAIRE NOSIMBARY - CR ction 4 24 25 09 10 14 23 23 lected rural areas TSARABARIA - VOHEMAR ARA13CFMO17008 / maîtri Component 1: Building a s Least Cost Sele 2017-05-2 2017-06- 2017-05- 2017-05- 2017-06- 2017-06- 2017-07- 2017-06- 2017-06- 2017-06- 2017-07- 2017-06- 2017-07- 2018-09- se d'œuvre EPP SAHAMAZA IDA / 57080 afety net for the poor in se Post Open - National 3,806.90 17,180.60 Signed ction 4 28 24 25 28 09 07 10 28 14 10 23 26 23 VA - CU ANDAPA - ANDAPA lected rural areas ARA13CFMO17009 / maîtri Component 1: Building a s Least Cost Sele 2017-05-2 2017-05- 2017-05- 2017-06- 2017-06- 2017-06- 2017-06- 2018-09- se d'œuvre CEG AMPAHAN IDA / 57080 afety net for the poor in se Post Open - National 3,806.90 0.00 Canceled ction 4 24 25 09 10 14 23 23 A - CR AMPAHANA - ANTAL lected rural areas AHA ARA13CFMO17010 / maîtri Component 1: Building a s Least Cost Sele 2017-05-2 2017-05- 2017-05- 2017-06- 2017-06- 2017-06- 2017-06- 2018-09- se d'œuvre CEG MAHERIFO IDA / 57080 afety net for the poor in se Post Open - National 4,146.55 0.00 Canceled ction 4 24 25 09 10 14 23 23 DY - CU ANTALAHA - ANTAL lected rural areas AHA ARA13CFMO17011 / maîtri Component 1: Building a s Least Cost Sele 2017-05-2 2017-05- 2017-05- 2017-06- 2017-06- 2017-06- 2017-06- 2018-09- se d'œuvre EPP AMBATOFIS IDA / 57080 afety net for the poor in se Post Open - National 4,064.48 0.00 Canceled ction 4 24 25 09 10 14 23 23 AKA - CU ANTALAHA - ANTA lected rural areas LAHA ARA13CFMO17012 / maîtri Component 1: Building a s Least Cost Sele 2017-05-2 2017-05- 2017-05- 2017-06- 2017-06- 2017-06- 2017-06- 2018-09- se d'œuvre CSB AMBINANIF IDA / 57080 afety net for the poor in se Post Open - National 3,791.38 0.00 Canceled ction 4 24 25 09 10 14 23 23 AHO - CR AMBINANIFAHO - lected rural areas ANTALAHA DRK11CFAGSEN18001 / A Component 1: Building a s Quality And Cos 2018-04-3 2018-04- 2018-05- 2018-06- 2018-06- 2018-07- 2018-07- 2020-01- CTP Agence de sensibilisati IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 26,758.24 0.00 Canceled 0 30 21 05 08 14 27 23 on district Manakara lected rural areas n DRK11CFAGEC18001 / CO Component 1: Building a s Quality And Cos LLECTE DE DONNEES ET E Pending Imple 2018-06-0 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-07- 2019-01- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 57,096.77 0.00 NCADREMENT UTB AMBOHI mentation 5 06 25 16 20 24 29 05 lected rural areas n MANARIVO MANGAIKA- UTB VATANA - UTB VOHILAVA DRK13CFMO18001 / MAÎT Component 1: Building a s Least Cost Sele Pending Imple 2018-06-0 2018-06- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-12- RISE D' OEUVRE TRAVAUX IDA / 57080 afety net for the poor in se Post Open - National 4,843.75 0.00 ction mentation 5 05 15 30 01 04 11 08 DE RÉHABILITATION D' UN lected rural areas ECOLE A VOHIPENO DRF13CFMO18001 / MAITR Component 1: Building a s Quality And Cos ISE D'OEUVRE POUR LA RE 2018-06-0 2018-07- 2018-06- 2018-06- 2018-07- 2018-07- 2018-07- 2018-07- 2018-07- 2018-07- 2018-07- 2018-07- 2018-07- 2018-11- 2019-08- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 4,750.00 3,706.50 Completed CONSTRUCTION DES ECOL 6 03 11 27 11 12 18 13 18 23 24 30 30 27 26 lected rural areas n ES DISTRICT AMBOHIMAHA SOA DRT13CFMO18001 / Maîtri Component 1: Building a s Consultant Qual se d'œuvre des travaux de 2018-06-1 2018-08- 2018-06- 2018-06- 2018-08- 2018-06- 2018-09- 2018-07- 2018-09- 2019-12- 2019-09- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 2,580.65 2,323.92 Completed réhabilitation/reconstructio 2 13 12 18 23 29 04 05 11 13 25 lected rural areas on n d'une école dans le Distri ct d'Arivonimamo DRT13CFMO18002 / Maîtri Component 1: Building a s Consultant Qual se d'œuvre des travaux de 2018-06-1 2018-08- 2018-06- 2018-06- 2018-08- 2018-06- 2018-09- 2018-07- 2018-09- 2019-12- 2019-09- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 2,580.65 2,323.92 Completed réhabilitation/reconstructio 2 13 12 18 23 29 04 05 11 13 25 lected rural areas on n d'une école dans le Distri ct de Faratsiho DG20CFFORMGRH1814 / F Component 2: Strengtheni Consultant Qual 2018-06-1 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- ORMATION EN GESTION DE IDA / 57080 ng safety net administratio Post ification Selecti Open - National 745.00 0.00 Canceled 0 13 07 22 29 28 S RESSOURCES HUMAINES n, monitoring and social ac on countability DG20CFFORMFINPUB1815 Component 2: Strengtheni Consultant Qual 2018-06-1 2018-06- 2018-07- 2018-07- 2018-07- 2018-08- / FORMATION EN FINANCE IDA / 57080 ng safety net administratio Post ification Selecti Open - National 745.00 0.00 Canceled 0 13 07 22 29 28 PUBLIQUE n, monitoring and social ac on countability DG11CFENQML1818 / ENQ Component 1: Building a s Consultant Qual 2018-06-1 2018-07- 2018-06- 2018-06- 2018-08- 2018-07- 2018-09- 2018-07- 2018-09- 2018-08- 2019-01- UETE EMPLOI DU TEMPS DE IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 10,000.00 9,331.43 Completed 1 05 14 27 03 07 11 12 19 11 07 S MERES LEADERS lected rural areas on DG20CFAUDTMNC1819 / I nvestigation au niveau des sites du Programme de Tra Component 1: Building a s Consultant Qual 2018-07-1 2018-08- 2018-07- 2018-07- 2018-09- 2018-08- 2018-10- 2018-08- 2018-11- 2018-09- nsfert Monétaire aux bénéfi IDA / D1450 afety net for the poor in se Post ification Selecti Open - National 30,000.00 4,159.19 Signed 1 09 12 30 14 09 19 15 27 14 ciaires de filets de sécurité lected rural areas on s sociaux du FID dans le Di stricts d'Ambovombe, Amb oasary Atsimo, Bekily, Belo ha et Tsihombe DG20CFEVALPERS1821 / A Component 2: Strengtheni Consultant Qual 2018-08-1 2018-08- 2018-09- 2018-09- 2018-09- 2019-09- cquisition Logiciel d'évaluat IDA / 57080 ng safety net administratio Post ification Selecti Open - National 6,100.00 0.00 Canceled 2 17 01 16 20 20 ion du personnel en ligne n, monitoring and social ac on countability DRU13CFAGEX19001 / EN CADREMENT ET SUPERVISI Component 1: Building a s Quality And Cos 2019-02-0 2019-01- 2019-02- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-03- 2019-03- ON DE MICRO- PROJET 1 A IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 620.08 Completed 4 24 05 06 27 08 27 08 28 10 28 10 28 12 14 HAUTE INTENSITE DE MAIN- lected rural areas n D'ŒUVRE ACTP PC FKT AN KIEMBE HAUT MAHAVATSE 1er DRUI3CFAGEX19002 / ENC ADREMENT ET SUPERVISIO Component 1: Building a s Quality And Cos N DE MICRO- PROJET 2 A H 2019-02-0 2019-01- 2019-02- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-03- 2019-03- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 692.05 Completed AUTE INTENSITE DE MAIN- 4 24 05 06 27 08 27 08 28 10 28 10 28 12 14 lected rural areas n D'ŒUVRE ACT PC FKT ANK IEMBE HAUT- TANAMBAO M OTOMBE MAHAVATSE 1er DRU13CFAGEX19003 / EN CADREMENT ET SUPERVISI Component 1: Building a s Quality And Cos 2019-02-0 2019-01- 2019-02- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-03- 2019-03- ON DE MICRO- PROJET A H IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 678.21 Completed 4 24 05 06 27 08 27 08 28 10 28 10 28 12 14 AUTE INTENSITE DE MAIN- lected rural areas n D'ŒUVRE ACT PC FKT ANKI EMBE BAS DRU13CFAGEX19004 / EN CADREMENT ET SUPERVISI Component 1: Building a s Quality And Cos 2019-02-0 2019-01- 2019-02- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-03- 2019-03- ON DES MICRO- PROJETS A IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 610.20 Completed 4 24 05 06 27 08 27 08 28 10 28 10 28 12 27 HAUTE INTENSITE DE MAIN- lected rural areas n D'ŒUVRE ACT PC MAHAVA TSE II OUEST DRU13CFAGEX19005 / EN CADREMENT ET SUPERVISI Component 1: Building a s Quality And Cos 2019-02-0 2019-01- 2019-02- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-02- 2019-01- 2019-03- 2019-03- ON DES MICRO- PROJETS A IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 610.20 Completed 4 24 05 06 27 08 27 08 28 10 28 10 28 12 27 HAUTE INTENSITE DE MAIN- lected rural areas n D'ŒUVRE ACT PC FKT MAH AVATSE II EST DG20CFCABRECR1901 / R Component 2: Strengtheni Consultant Qual ECRUTEMENT DU CHEF DE ng safety net administratio 2019-02-0 2019-02- 2019-02- 2019-02- 2019-04- 2019-03- 2019-06- 2019-03- 2019-06- 2019-12- IDA / 57080 Post ification Selecti Open - National 3,000.00 2,280.43 Signed SERVICE DES RESSOURCES n, monitoring and social ac 7 21 12 25 05 18 06 23 06 31 on HUMAINES ET AUTRE PERS countability ONNEL DU FID DG20CFMANUEL1902 / Éla Component 2: Strengtheni Quality And Cos boration manuel mesures d ng safety net administratio 2019-02-0 2019-02- 2019-03- 2019-04- 2019-04- 2019-04- 2019-05- 2019-06- IDA / 57080 Post t-Based Selectio Open - National 30,000.00 0.00 Canceled 'accompagnement et révisi n, monitoring and social ac 7 28 13 10 15 23 01 15 n on différents manuels du FI countability D DG20CFPLAT1903 / CONC Component 2: Strengtheni Quality Based S 2019-02-2 2019-03- 2019-03- 2019-04- 2019-05- 2019-05- 2019-05- 2020-09- EPTION ET MISE EN PLACE IDA / 57080 ng safety net administratio Post Open - National 150,000.00 0.00 Canceled election 8 05 31 28 03 06 16 14 D'UNE PLATEFORME DE CO n, monitoring and social ac LLECTE DE DONNEES countability DRA13CFAGEX19001 / LOT Component 1: Building a s Consultant Qual 1 ENCADREMENT - PAIEME 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 26,269.47 1,990.66 Completed NT ACT POST CATASTROP 0 26 20 25 26 05 26 10 27 26 11 lected rural areas on HE DES 08 FKT DIST TOAM ASINA I DRA13CFAGEX19002 / LOT Component 1: Building a s Consultant Qual 2 ENCADREMENT - PAIEME 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 26,269.47 2,010.49 Completed NT ACT POST CATASTROP 0 26 20 25 26 05 26 10 27 26 11 lected rural areas on HE DES 08 FKT DIST TOAM ASINA I DRA13CFAGEX19003 / LOT Component 1: Building a s Consultant Qual 3 ENCADREMENT - PAIEME 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 26,269.47 1,893.42 Completed NT ACT POST CATASTROP 0 26 20 25 26 05 26 10 27 26 11 lected rural areas on HE DES 08 FKT DIST TOAM ASINA I DRA13CFAGEX19004 / LOT Component 1: Building a s Consultant Qual 4 ENCADREMENT - PAIEME 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 26,269.47 2,062.47 Completed NT ACT POST CATASTROP 0 26 20 25 26 05 26 10 27 26 11 lected rural areas on HE DES 08 FKT DIST TOAM ASINA I DRA13CFAGEX19005 / LOT Component 1: Building a s Consultant Qual 5 ENCADREMENT - PAIEME 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 26,269.47 2,094.54 Completed NT ACT POST CATASTROP 0 26 20 25 26 05 26 10 27 26 11 lected rural areas on HE DES 08 FKT DIST TOAM ASINA I DRA13CFAGEX19006 / LOT Component 1: Building a s Consultant Qual 6 ENCADREMENT - PAIEME 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 26,269.47 2,008.28 Completed NT ACT POST CATASTROP 0 26 20 25 26 05 26 10 27 26 13 lected rural areas on HE DES 08 FKT DIST TOAM ASINA I DRA13CFAGEX19007 / LOT Component 1: Building a s Consultant Qual 7 ENCADREMENT - PAIEME 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 26,269.47 2,019.34 Completed NT ACT POST CATASTROP 0 26 20 25 26 05 26 10 27 26 12 lected rural areas on HE DES 08 FKT DIST TOAM ASINA I DRA13CFAGEX19008 / LOT Component 1: Building a s Consultant Qual 8 ENCADREMENT - PAIEME 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 26,269.47 2,006.07 Completed NT ACT POST CATASTROP 0 26 20 25 26 05 26 10 27 26 11 lected rural areas on HE DES 08 FKT DIST TOAM ASINA I DRA13CFAGEX19009 / LOT Component 1: Building a s Consultant Qual 9 ENCADREMENT - PAIEME 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-05- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 26,269.47 2,647.50 Completed NT ACT POST CATASTROP 0 26 20 25 26 05 26 10 27 26 25 lected rural areas on HE DES 08 FKT DIST TOAM ASINA I Page 10 DRA13CFAGEX19010 / LOT Component 1: Building a s Consultant Qual 10 ENCADREMENT - PAIEM 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 26,269.47 2,008.28 Completed ENT ACT POST CATASTROP 0 26 20 25 26 05 26 10 28 26 14 lected rural areas on HE DES 08 FKT DIST TOAM ASINA I DRA13CFAGEX19011 / LOT Component 1: Building a s Consultant Qual 11 ENCADREMENT - PAIEM 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 29,553.16 2,474.54 Completed ENT ACT POST CATASTROP 0 26 20 25 26 05 26 10 28 26 12 lected rural areas on HE DES 09 FKT DIST TOAM ASINA I DRA13CFAGEX19012 / LOT Component 1: Building a s Consultant Qual 12 ENCADREMENT - PAIEM 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 29,553.16 2,196.63 Completed ENT ACT POST CATASTROP 0 26 20 25 26 05 26 10 28 26 12 lected rural areas on HE DES 09 FKT DIST TOAM ASINA I DRA13CFAGEX19013 / LOT Component 1: Building a s Consultant Qual 13 ENCADREMENT - PAIEM 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 29,553.16 2,238.08 Completed ENT ACT POST CATASTROP 0 26 20 25 26 05 26 10 28 26 13 lected rural areas on HE DES 09 FKT DIST TOAM ASINA I DRA13CFAGEX19014 / LOT Component 1: Building a s Consultant Qual 14 ENCADREMENT - PAIEM 2019-03-2 2019-03- 2019-03- 2019-03- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-04- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 29,553.16 2,218.13 Completed ENT ACT POST CATASTROP 0 26 20 25 26 05 26 10 28 26 12 lected rural areas on HE DES 09 FKT DIST TOAM ASINA I DRF13PCMO19001 / MAITR ISE D'OEUVRE POUR LA RE Component 1: Building a s Least Cost Sele 2019-05-0 2019-05- 2019-05- 2019-07- 2019-05- 2019-08- 2019-06- 2019-09- 2019-06- 2019-10- 2019-06- 2019-11- 2019-06- 2020-01- 2019-09- CONSTRUCTION D'UNE EC IDA / 57080 afety net for the poor in se Post Open - National 2,352.94 2,464.11 Completed ction 8 08 23 06 29 03 11 02 12 07 13 11 20 10 27 OLE DANS LE FOKONTANY lected rural areas ANKAZOTANA CR AMBOHIM ANANA DRT13CFAGEX1901 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 244.53 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 15 17 09 lected rural areas on ny Avaradoha, Commune A NTANANARIVO RENIVOHIT RA, District ANTANANARIV O III DRT13CFAGEX1904 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 244.53 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 10 lected rural areas on ny d'Andravoahangy, Com mune d'ANTANANARIVO R ENIVOHITRA, District d'ANT ANANARIVO III DRT13CFAGEX1903 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 244.53 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 10 lected rural areas on ny Ankorondrano Est, Com mune ANTANANARIVO RE NIVOHITRA, District ANTAN ANARIVO III DRT13CFAGEX1902 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 244.53 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 10 lected rural areas on ny Besarety, Commune AN TANANARIVO RENIVOHITR A, District ANTANANARIVO I II DRT13CFAGEX1912 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 248.82 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 15 17 03 lected rural areas on ny d'Androndrakely, Comm une d'ANTANANARIVO REN IVOHITRA, District d'ANTAN ANARIVO II DRT13CFAGEX1913 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 248.82 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 04 lected rural areas on ny de Tsiadana, Commune d'ANTANANARIVO RENIVO HITRA, District d'ANTANAN ARIVO II DRT13CFAGEX1914 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 248.82 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 15 17 03 lected rural areas on ny de Mandroseza, Commu ne d'ANTANANARIVO RENI VOHITRA, District d'ANTAN ANARIVO II DRT13CFAGEX1905 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 244.53 Completed 8 08 08 10 08 28 10 04 16 17 10 ny d'Ankorondrano Ouest, lected rural areas on Commune d'ANTANANARIV O RENIVOHITRA, District d' ANTANANARIVO III DRT13CFAGEX1906 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 244.53 Completed 8 08 08 10 08 28 10 04 15 17 15 ny d'Andranomanalina Isotr lected rural areas on y , Commune d'ANTANANA RIVO RENIVOHITRA, Distric t d'ANTANANARIVO I DRT13CFAGEX1907 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 244.53 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 15 17 15 lected rural areas on ny Andohatapenaka II, Com mune ANTANANARIVO RE NIVOHITRA, District ANTAN ANARIVO I DRT13CFAGEX1908 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 244.53 Completed 8 08 08 10 08 28 10 04 15 17 15 ny d'Andavamamba Anatih lected rural areas on azo I , Commune d'ANTANA NARIVO RENIVOHITRA, Dis trict d'ANTANANARIVO I DRT13CFAGEX1909 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 244.53 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 15 17 15 lected rural areas on ny Antetezanafovoany I, Co mmune ANTANANARIVO R ENIVOHITRA, District ANTA NANARIVO I DRT13CFAGEX1910 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 244.53 Completed 8 08 08 10 08 28 10 04 16 17 16 ny d'Antohomadinika sud, lected rural areas on Commune d'ANTANANARIV O RENIVOHITRA, District d' ANTANANARIVO I DRT13CFAGEX1911 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-07- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 248.82 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 04 lected rural areas on ny Ambohipotsy, Commune ANTANANARIVO RENIVOHI TRA, District ANTANANARIV O II DRT13CFAGEX1927 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 248.82 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 06 lected rural areas on ny d'Andranomena, Comm une d'ANTANANARIVO REN IVOHITRA, District d'ANTAN ANARIVO VI DRT13CFAGEX1933 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 276.47 Completed atastrophe dans le Fokonta 8 08 08 10 10 28 10 04 03 17 09 lected rural areas on ny d'Antanetibe , Commun e d'Ambohitrimanjaka, Dist rict d'AMBOHIDRATRIMO DRT13CFAGEX1934 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 276.47 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 03 17 09 lected rural areas on ny de Lavahitsiny, Commu ne d'Anosiala, District d'AM BOHIDRATRIMO DRT13CFAGEX1938 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 09 lected rural areas on ny de Manankasina, Comm une d'Ambohitrimanjaka, D istrict d'AMBOHIDRATRIMO DRT13CFAGEX1943 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 300.06 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 16 lected rural areas on ny de Fihaonana ville, Com mune de Fihaonana, Distric t d'ANKAZOBE DRT13CFAGEX1946 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 17 lected rural areas on ny d'Ambohimanatrika, Co mmune de Soavina, District d'ANTANANARIVO ATSIMON DRANO DRT13CFAGEX1947 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 17 lected rural areas on ny de Tongarivo, Commune de Tanjombato, District d'A NTANANARIVO ATSIMONDR ANO DRT13CFAGEX1948 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 08 04 04 17 17 lected rural areas on ny d'Amboatavo, Commun e d'Ambavahaditokana, Dis trict d'ANTANANARIVO ATSI MONDRANO DRT13CFAGEX1949 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 08 04 03 17 16 lected rural areas on ny d'Anosimasina, Commu ne de Bemasoandro, Distric t d'ANTANANARIVO ATSIMO NDRANO DRT13CFAGEX1950 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 13 lected rural areas on ny de Namehana, Commun e de Sabotsy Namehana, D istrict d'ANTANANARIVO AV ARADRANO DRT13CFAGEX1951 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 13 lected rural areas on ny de Manaritsoa, Commun e de Sabotsy Namehana, D istrict d'ANTANANARIVO AV ARADRANO DRT13CFAGEX1956 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 346.40 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 06 lected rural areas on ny de Marohisana, Commu ne d'AMBOHIPIHAONANA, District d'AMBATOLAMPY, DRT13CFAGEX1957 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 346.40 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 06 lected rural areas on ny de Fihaonana, Commun e d'ANDRAVOLA VOHIPENO , District d'AMBATOLAMPY DRT13CFAGEX1958 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 271.58 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 11 lected rural areas on ny d'Antobiniaro, Commun e d'ANTANIFOTSY, District d'ANTANIFOTSY DRT13CFAGEX1959 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 271.58 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 11 lected rural areas on ny d'Ambohimandroso A, C ommune d'AMBOHIMANDR OSO, District d'ANTANIFOT SY DRT13CFAGEX1960 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 327.20 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 13 lected rural areas on ny de Tsarafara Andranobe , Commune d'ANTSIRABE, District d'ANTSIRABE I DRT13CFAGEX1915 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 248.82 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 15 17 03 lected rural areas on ny Ambolokandrina, Comm une ANTANANARIVO RENI VOHITRA, District ANTANA NARIVO II DRT13CFAGEX1916 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 254.35 Completed 8 08 08 10 08 28 10 04 15 17 08 ny d'Anosipatrana Ouest, C lected rural areas on ommune d'ANTANANARIVO RENIVOHITRA, District d'A NTANANARIVO IV DRT13CFAGEX1917 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 254.35 Completed 8 08 08 10 08 28 10 04 16 17 09 ny de Mandrangobato II, Co lected rural areas on mmune d'ANTANANARIVO RENIVOHITRA, District d'AN TANANARIVO IV DRT13CFAGEX1918 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 254.35 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 09 lected rural areas on ny d'Ivolaniray, Commune d'ANTANANARIVO RENIVO HITRA, District d'ANTANAN ARIVO IV DRT13CFAGEX1919 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 254.35 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 09 lected rural areas on ny d'Anosibe II, Commune d'ANTANANARIVO RENIVO HITRA, District d'ANTANAN ARIVO IV DRT13CFAGEX1920 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 254.35 Completed 8 08 08 10 08 28 10 04 16 17 09 ny d'Ampefiloha Ambodiran lected rural areas on o, Commune d'ANTANANAR IVO RENIVOHITRA, District d'ANTANANARIVO IV DRT13CFAGEX1921 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 262.65 Completed 8 08 08 10 08 28 10 04 15 17 12 ny Ambohidahy Ankadindra lected rural areas on mamy, Commune ANTANA NARIVO RENIVOHITRA, Dis trict ANTANANARIVO V DRT13CFAGEX1922 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 262.65 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 13 lected rural areas on ny d'Ankerana, Commune d'ANTANANARIVO RENIVO HITRA, District d'ANTANAN ARIVO V DRT13CFAGEX1923 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 262.65 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 13 lected rural areas on ny de Soavimasoandro, Co mmune d'ANTANANARIVO RENIVOHITRA, District d'AN TANANARIVO V DRT13CFAGEX1924 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 262.65 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 13 lected rural areas on ny de Manjakaray, Commu ne d'ANTANANARIVO RENI VOHITRA, District d'ANTAN ANARIVO V DRT13CFAGEX1925 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 262.65 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 08 04 15 17 12 lected rural areas on ny d'Anjanahary II O, Com mune d'ANTANANARIVO R ENIVOHITRA, District d'ANT ANANARIVO V DRT13CFAGEX1926 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 248.82 Completed 8 08 08 10 08 28 10 04 16 17 06 ny d'Ambonivoninkely, Co lected rural areas on mmune d'ANTANANARIVO RENIVOHITRA, District d'AN TANANARIVO VI DRT13CFAGEX1928 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 248.82 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 06 lected rural areas on ny d'Ambatolampy, Comm une d'ANTANANARIVO REN IVOHITRA, District d'ANTAN ANARIVO VI DRT13CFAGEX1929 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 248.82 Completed 8 08 08 10 08 28 10 04 16 17 06 ny d'Ambohimiadana Nord, lected rural areas on Commune d'ANTANANARIV O RENIVOHITRA, District d' ANTANANARIVO VI DRT13CFAGEX1930 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 248.82 Completed 8 08 08 10 08 28 10 04 16 17 06 ny d'Antanety Avaratra, Co lected rural areas on mmune d'ANTANANARIVO RENIVOHITRA, District d'AN TANANARIVO VI Page 11 DRT13CFAGEX1931 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 276.47 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 10 lected rural areas on ny d'Ambohinambo, Comm une de Talatamaty, District d'AMBOHIDRATRIMO DRT13CFAGEX1963 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 267.22 Completed 8 08 08 10 08 28 10 04 16 17 11 atastrophe dans le Fokonta lected rural areas on ny d'Ambano, Commune d' AMBANO, District d'ANTSIR ABE II DRT13CFAGEX1964 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 340.84 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 06 lected rural areas on ny d'Ambohibary Iray Tsimi vaky, Commune d'AMBOHI BARY, District d'ANTSIRABE II DRT13CFAGEX1965 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 267.22 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 11 lected rural areas on ny de Betafo Centre ville, C ommune de BETAFO, Distri ct de BETAFO DRT13CFAGEX1966 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 267.22 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 11 lected rural areas on ny de Belanitra, Commune d'AMBOHIMASINA, District de BETAFO DRT13CFAGEX1967 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 340.84 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 15 17 05 lected rural areas on ny de Faratsiho centre, Co mmune de FARATSIHO, Dis trict de FARATSIHO DRT13CFAGEX1968 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 340.84 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 06 lected rural areas on ny de Manarintsoa, Commu ne de MIANDRARIVO, Distri ct de FARATSIHO DRT13CFAGEX1969 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 327.20 Completed 8 08 08 10 08 28 10 04 16 17 13 atastrophe dans le Fokonta lected rural areas on ny de Fidirana, Commune d e FIDIRANA, District de MA NDOTO DRT13CFAGEX1970 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 327.20 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 13 lected rural areas on ny d'Ankazomiriotra, Com mune d'ANKAZOMIRIOTRA, District de MANDOTO DRT13CFAGEX1932 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 276.47 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 10 lected rural areas on ny de Faralaza, Commune de Talatamaty, District d'A MBOHIDRATRIMO DRT13CFAGEX1935 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 09 lected rural areas on ny de Mandrosoa, Commun e d'Anosiala, District d'AMB OHIDRATRIMO DRT13CFAGEX1936 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 09 lected rural areas on ny d'Ankadindravola, Com mune d'Ivato , District d'AM BOHIDRATRIMO DRT13CFAGEX1937 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 09 lected rural areas on ny d'Ambohitrinilahy, Com mune de Mahereza, District d'AMBOHIDRATRIMO DRT13CFAGEX1939 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 304.83 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 03 17 15 lected rural areas on ny d'Ambohibao, Commune d'Antehiroka, District d'AM BOHIDRATRIMO DRT13CFAGEX1940 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 299.94 Completed 8 08 08 10 08 28 10 04 04 17 16 atastrophe dans le Fokonta lected rural areas on ny d'Ankazobe I, Commune d'Ankazobe, District d'ANK AZOBE DRT13CFAGEX1941 / Enca drement et paiement des b Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- énéficiaires de l'ACT post c IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 299.94 Completed 8 08 08 10 08 28 10 04 04 17 16 atastrophe dans le Fokonta lected rural areas on ny d'Ankazobe II, Commun e d'Ankazobe, District d'AN KAZOBE DRT13CFAGEX1942 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 300.06 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 16 lected rural areas on ny d'Ambohitrankizy, Com mune d'Ankazobe, District d'ANKAZOBE DRT13CFAGEX1944 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-06- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 03 17 03 lected rural areas on ny d'Antsahabe, Commune de Bongatsara, District d'A TSIMONDRANO DRT13CFAGEX1945 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 03 17 16 lected rural areas on ny d'Ankadilalampotsy, Co mmune d'Ankaraobato, Dis trict d'ANTANANARIVO ATSI MONDRANO DRT13CFAGEX1952 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 13 lected rural areas on ny d'Ambohitrarahaba, Co mmune d'Ankadikely ilafy, District d'ANTANANARIVO A VARADRANO DRT13CFAGEX1953 / Enca drement et paiement des b énéficiaires de l'ACT post c Component 1: Building a s Consultant Qual 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- atastrophe dans le Fokonta IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed 8 08 08 10 08 28 10 04 04 17 13 ny d'Ambohimangakely, Co lected rural areas on mmune d'Ambohimangakel y, District d'ANTANANARIV O AVARADRANO DRT13CFAGEX1954 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 10 28 10 04 04 17 13 lected rural areas on ny d'Ambolo, Commune de Talata volonondry, District d'ANTANANARIVO AVARAD RANO DRT13CFAGEX1955 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 277.12 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 04 17 10 lected rural areas on ny d'Ambatomalaza, Comm une d'Alasora, District d'AN TANANARIVO AVARADRAN O DRT13CFAGEX1961 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 327.20 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 13 lected rural areas on ny de Vohitrarivo, Commun e d'ANTSIRABE, District d'A NTSIRABE I DRT13CFAGEX1962 / Enca drement et paiement des b Component 1: Building a s Consultant Qual énéficiaires de l'ACT post c 2019-05-0 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-05- 2019-06- 2019-05- 2019-06- 2019-07- IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 3,521.00 327.20 Completed atastrophe dans le Fokonta 8 08 08 10 08 28 10 04 16 17 13 lected rural areas on ny d'Ambalavato, Commun e d'ANTSIRABE, District d'A NTSIRABE I DG20CETUDFAISB1901 / C Component 2: Strengtheni abinet en charge de l'étude ng safety net administratio Quality Based S 2019-07-1 2019-08- 2019-08- 2019-09- 2019-10- 2019-10- 2019-10- 2020-10- de faisabilité et d'évaluatio IDA / 57080 Post Open - National 75,000.00 0.00 Canceled n, monitoring and social ac election 9 09 24 23 08 13 19 18 n d'un projet de numérisati countability on du système de paiemen t et d'enregistrement DG20CABRECERTBTF1901 / Recrutement d'un Cabinet Component 2: Strengtheni Consultant Qual en charge de la collecte de ng safety net administratio 2019-07-1 2019-08- 2019-08- 2019-08- 2019-12- 2019-08- 2020-02- 2019-08- 2020-02- 2019-11- IDA / 57080 Post ification Selecti Open - National 39,000.00 30,298.59 Signed s données en vue de la rec n, monitoring and social ac 9 01 09 17 17 22 05 28 28 26 on ertification des bénéficiaire countability s des activités TMDH du Di strict de Betafo dans le cad re du projet FSS DG11CETUDFMOBMON190 1 / Cabinet en charge de l'é Component 1: Building a s Consultant Qual 2019-08-1 2019-08- 2019-09- 2019-10- 2019-10- 2019-12- tude de faisabilité du paie IDA / 57080 afety net for the poor in se Post ification Selecti Open - National 70,000.00 0.00 Canceled 6 31 13 04 11 10 ment par mobile money da lected rural areas on ns toutes les zones d'interv ention du FID DRT11CFAGEC19002 / Enc Component 1: Building a s Quality And Cos adrement des bénéficiaires 2019-12-0 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-04- 2022-08- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 24,000.00 21,773.35 Signed de l'ACT-P dans le District d 6 14 09 27 24 11 13 16 20 29 27 06 08 14 lected rural areas n 'Antanifotsy : UTB AMBILO NA I et UTB MANANITRA - l ot 2 DRT11CFAGEC19003 / Enc adrement des bénéficiaires Component 1: Building a s Quality And Cos 2019-12-0 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-04- 2022-08- de l'ACT-P dans le District d IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 22,000.00 20,440.87 Signed 6 14 09 27 24 11 13 16 20 29 27 06 08 14 'Antanifotsy : UTB SOAMA lected rural areas n NANDRARINY et UTB ANDO HAFARIHY - lot 3 DRT11CFAGEC19004 / Enc adrement des bénéficiaires Component 1: Building a s Quality And Cos 2019-12-0 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-04- 2022-08- de l'ACT-P dans le District d IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 31,000.00 28,674.37 Signed 6 14 09 27 24 11 13 16 20 29 27 06 08 14 'Antanifotsy : UTB AMBATO lected rural areas n DIDY et UTB AMBATOLAHY - lot 4 DRT11CFAGEC19005 / Enc adrement des bénéficiaires Component 1: Building a s Quality And Cos 2019-12-0 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-04- 2022-08- de l'ACT-P dans le District d IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 22,000.00 18,513.86 Signed 6 14 09 27 24 11 13 16 20 29 27 06 08 14 'Antanifotsy : UTB ANTAMB lected rural areas n OHOMENA et UTB AMBATO MIADY - lot 5 DRT11CFAGEC19006 / Enc adrement des bénéficiaires Component 1: Building a s Quality And Cos 2019-12-0 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-04- 2022-08- de l'ACT-P dans le District d IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 26,000.00 11,207.75 Signed 6 14 09 27 24 11 13 16 20 29 27 06 08 14 'Antanifotsy : UTB TSARAH lected rural areas n ONENANA et UTB MAHATSI NJO - lot 6 DRT11CFAGEC19007 / Enc adrement des bénéficiaires Component 1: Building a s Quality And Cos 2019-12-0 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-04- 2022-08- de l'ACT-P dans le District d IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 24,000.00 22,860.36 Signed 6 14 09 27 24 11 13 16 20 29 27 06 08 14 'Antanifotsy : UTB AMPITA lected rural areas n TAFIKA et UTB AMBOHIMAN DROSO A - lot 7 DRT11CFAGEC19008 / Enc Component 1: Building a s Quality And Cos 2019-12-0 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-04- 2022-08- adrement des bénéficiaires IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 19,000.00 17,742.69 Signed 6 14 09 27 24 11 13 16 20 29 27 06 08 14 de l'ACT-P dans le District d lected rural areas n 'Antanifotsy : DRT11CFAGEC19009 / Enc adrement des bénéficiaires Component 1: Building a s Quality And Cos 2019-12-0 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-04- 2022-08- de l'ACT-P dans le District d IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 29,000.00 26,462.39 Signed 6 14 09 27 24 11 16 16 20 29 27 06 08 14 'Antanifotsy : UTB ANTEM lected rural areas n OTRA et UTB ANTANAMBA O - lot 9 DRT11CFAGEC19010 / Enc Component 1: Building a s Quality And Cos adrement des bénéficiaires 2019-12-0 2020-02- 2019-12- 2019-12- 2020-06- 2020-01- 2020-07- 2020-01- 2020-08- 2020-01- 2020-09- 2020-02- 2020-10- 2022-08- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 52,000.00 20,581.35 Signed de l'ACT-P dans le District d 6 14 09 27 17 11 07 16 18 29 16 06 16 14 lected rural areas n 'Arivonimamo : Terroir 1 e t Terroir 2 - LOT 1 DRT11CFAGEC19011 / Enc Component 1: Building a s Quality And Cos adrement des bénéficiaires 2019-12-0 2020-02- 2019-12- 2019-12- 2020-06- 2020-01- 2020-07- 2020-01- 2020-08- 2020-01- 2020-09- 2020-02- 2020-10- 2022-08- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 52,000.00 23,930.77 Signed de l'ACT-P dans le District d 6 14 09 27 17 11 07 16 18 29 16 06 16 14 lected rural areas n 'Arivonimamo : Terroir 3 e t Terroir 4 - LOT 2 DRK11CFPLAN19001 / AGE NCE DE PLANIFICATION CH Component 1: Building a s Quality And Cos 2019-11-2 2019-12- 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2020-02- 2020-04- 2022-06- ARGÉE DU SUIVI ET SUPER IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 73,000.00 37,265.85 Signed 8 05 13 15 03 14 28 19 28 27 02 05 17 14 VISION DES CHANTIERS, SU lected rural areas n IVI-ÉVALUATION COMMUNA UTAIRE, MISE A JOUR DES P AMO DRF11CFAP19001 / RECRU Component 1: Building a s Quality And Cos 2019-12-1 2019-12- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-05- 2020-01- 2020-05- 2022-06- TEMENT AGENCE DE PLANI IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 73,000.00 44,526.45 Signed 2 04 12 12 05 11 06 11 11 16 13 26 30 04 FICATION ACTP POUR LE DI lected rural areas n STRICT D'ISANDRA DRF11CFAP19002 / RECRU Component 1: Building a s Quality And Cos 2019-12-1 2019-12- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-04- 2022-06- TEMENT AGENCE DE PLANI IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 73,000.00 33,223.70 Signed 2 04 12 12 05 11 06 11 11 16 26 26 11 04 FICATION DANS LE DISTRIC lected rural areas n T DE MANANDRIANA Component 1: Building a s Quality And Cos DRK11CFAGEC19001 / AG 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2022-04- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 94,200.00 36,006.47 Signed ENCE D'ENCADREMENT 8 07 03 21 20 20 09 22 09 26 10 07 27 07 lected rural areas n DRF11CFCCI19001 / RECR Component 1: Building a s Quality And Cos 2019-12-0 2020-01- 2019-12- 2020-02- 2020-03- 2020-03- 2020-04- 2020-04- 2020-04- 2020-05- 2020-05- 2020-06- 2020-05- 2020-12- UTEMENT CABINET DE CIBL IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 6,000.00 12,561.84 Signed 5 20 26 08 19 07 17 06 28 11 11 15 29 12 AGE POUR LE DISTRICT DE lected rural areas n MANANDRIANA DRF11CFAGEC19001 / REC Component 1: Building a s Quality And Cos 2020-01-1 2020-02- 2020-02- 2020-03- 2020-02- 2020-04- 2020-03- 2020-05- 2020-03- 2020-06- 2020-03- 2020-07- 2020-04- 2022-07- RUTEMENT AGENCE D'ENC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 100,000.00 23,251.39 Signed 5 14 05 20 21 17 10 17 13 21 25 26 08 16 ADREMENT LOT 01 ACTP IS lected rural areas n ANDRA DRF11CFAGEC19002 / REC Component 1: Building a s Quality And Cos 2020-01-1 2020-02- 2020-02- 2020-03- 2020-02- 2020-04- 2020-03- 2020-05- 2020-03- 2020-06- 2020-03- 2020-07- 2020-03- 2022-07- RUTEMENT AGENCE D'ENC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 100,000.00 9,573.11 Signed 5 14 05 20 21 17 10 17 13 21 24 26 31 16 ADREMENT ACTP LOT 02 IS lected rural areas n ANDRA DRF11CFAGEC19003 / REC Component 1: Building a s Quality And Cos RUTEMENT AGENCE D'ENC 2020-01-1 2020-02- 2020-02- 2020-03- 2020-02- 2020-04- 2020-03- 2020-05- 2020-03- 2020-06- 2020-03- 2020-07- 2020-03- 2022-07- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 100,000.00 10,427.57 Signed ADREMENT ACTP POUR LE 5 14 05 20 21 17 13 17 16 21 26 26 31 16 lected rural areas n DISTRICT ISANDRA LOT 03 DRF11CFAGEC19004 / REC Component 1: Building a s Quality And Cos 2020-01-1 2020-02- 2020-02- 2020-03- 2020-02- 2020-04- 2020-03- 2020-05- 2020-03- 2020-06- 2020-03- 2020-07- 2020-03- 2022-07- RUTEMENT AGENCE D'ENC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 100,000.00 18,292.81 Signed 5 14 05 20 21 17 10 17 13 21 24 26 31 16 ADREMENT ACTP ISANDRA lected rural areas n LOT 04 DRF11CFAGEC19005 / REC Component 1: Building a s Quality And Cos 2020-01-1 2020-02- 2020-02- 2020-03- 2020-02- 2020-04- 2020-03- 2020-05- 2020-03- 2020-06- 2020-03- 2020-07- 2020-04- 2022-07- RUTEMENT AGENCE D'ENC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 100,000.00 8,061.54 Signed 5 14 05 20 21 17 10 17 13 21 25 26 01 16 ADREMENT ACTP LOT 05 DI lected rural areas n STRICT ISANDRA DRF11CFAGEC19006 / REC Component 1: Building a s Quality And Cos 2020-01-1 2020-02- 2020-02- 2020-03- 2020-02- 2020-04- 2020-03- 2020-05- 2020-03- 2020-06- 2020-03- 2020-07- 2020-04- 2022-07- RUTEMENT AGENCED'ENCA IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 100,000.00 21,371.74 Signed 5 14 05 20 21 17 13 17 13 21 24 26 07 16 DREMENT ACTP DISTRICT I lected rural areas n SANDRA LOT 06 DRF11CFAGEC19007 / REC Component 1: Building a s Quality And Cos 2020-01-1 2020-02- 2020-02- 2020-03- 2020-02- 2020-04- 2020-03- 2020-05- 2020-03- 2020-06- 2020-03- 2020-07- 2020-04- 2022-07- RUTEMENT AGENCE D'ENC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 100,000.00 21,010.12 Signed 5 14 05 20 21 17 10 17 13 21 24 26 07 16 ADREMENT ACTP LOT 01 DI lected rural areas n STRICT MANANDRIANA Component 1: Building a s Quality And Cos DRK11CFAGEC19002 / AG 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2022-04- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 94,200.00 40,613.64 Signed ENCE D'ENCADREMENT 8 07 03 21 20 20 06 22 06 26 23 07 25 07 lected rural areas n DRK11CFAGEC19003 / AG Component 1: Building a s Quality And Cos 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2022-04- ENCE D'ENCADREMENT AC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 94,200.00 49,055.55 Signed 8 07 03 21 20 20 06 22 06 26 12 07 27 07 TP lected rural areas n DRK11CFAGEC19004 / AG Component 1: Building a s Quality And Cos 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2022-04- ENCE D'ENCADREMENT AC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 94,200.00 39,918.86 Signed 8 07 03 21 20 20 06 22 06 26 23 07 25 07 TP lected rural areas n DRK11CFAGEC19005 / AG Component 1: Building a s Quality And Cos 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2022-04- ENCE D'ENCADREMENT AC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 94,200.00 20,142.28 Signed 8 07 03 21 20 20 06 22 06 26 23 07 25 07 TP lected rural areas n DRK11CFAGEC19006 / AG Component 1: Building a s Quality And Cos 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2022-04- ENCE D'ENCADREMENT AC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 94,200.00 25,731.47 Signed 8 07 03 21 20 20 06 22 06 26 10 07 26 07 TP lected rural areas n DRK11CFAGEC19007 / AG Component 1: Building a s Quality And Cos 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2022-04- ENCE D'ENCADREMENT AC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 94,800.00 24,303.04 Signed 8 07 03 21 20 20 06 22 06 26 12 07 25 07 TP lected rural areas n DRU11CFPLAN19001 / AGE NCE DE PLANIFICATION CH Component 1: Building a s Quality And Cos ARGÉE DE LA PLANIFICATIO Pending Imple 2020-02- 2022-08- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 73,000.00 0.00 N, DU SUIVI ET SUPERVISIO mentation 09 09 lected rural areas n N DES CHANTIERS, SUIVI-É VALUATION COMMUNAUTAI RE, MISE A JOUR DES PAMO DRU11CFAGEC19001 / RE Component 1: Building a s Quality And Cos 2020-01-1 2019-06- 2020-02- 2020-03- 2020-02- 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-03- 2020-04- 2020-04- 2022-04- CRUTEMENT AGENCE D'EN IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 84,246.00 29,022.55 Signed 3 12 03 03 08 18 14 21 20 02 25 09 01 09 CADREMENT ACTP LOT 01 lected rural areas n DISTRICT ANKAZOABO DRT11CFPLAN19001 / Age Component 1: Building a s Quality And Cos 2019-12-1 2019-12- 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-04- 2020-02- 2020-04- 2020-02- 2020-05- 2022-08- nce de planification de l'AC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 32,000.00 20,580.12 Signed 1 04 12 28 06 25 27 25 03 11 21 21 06 29 TP Antanifotsy lected rural areas n DRU11CFAGEC19002 / RE Component 1: Building a s Quality And Cos 2020-01-1 2019-06- 2020-02- 2020-03- 2020-02- 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-03- 2020-04- 2020-04- 2022-04- CRUTEMENT AGENCE D'EN IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 70,129.00 13,408.73 Signed 3 12 03 03 08 18 14 21 18 02 25 09 01 09 CADREMENT ACTP LOT 02 lected rural areas n DISTRICT ANKAZOABO DRU11CFAGEC19003 / RE Component 1: Building a s Quality And Cos 2020-01-1 2019-06- 2020-02- 2020-03- 2020-02- 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-03- 2020-04- 2020-04- 2022-04- CRUTEMENT AGENCE D'EN IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 88,493.00 22,106.55 Signed 3 12 03 03 08 18 19 21 20 02 26 09 01 09 CADREMENT ACTP LOT 03 lected rural areas n DISTRICT ANKAZOABO DRU11CFAGEC19004 / RE Component 1: Building a s Quality And Cos 2020-01-1 2019-06- 2020-02- 2020-03- 2020-02- 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-03- 2020-04- 2020-04- 2022-04- CRUTEMENT AGENCE D'EN IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 51,649.00 13,252.75 Signed 3 12 03 03 08 18 18 21 20 02 25 09 01 09 CADREMENT ACTP LOT 04 lected rural areas n DISTRICT ANKAZOABO Page 12 DRU11CFAGEC19005 / RE Component 1: Building a s Quality And Cos 2020-01-1 2019-06- 2020-02- 2020-03- 2020-02- 2020-03- 2020-03- 2020-03- 2020-03- 2020-04- 2020-03- 2020-04- 2020-04- 2022-04- CRUTEMENT AGENCE D'EN IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 78,278.00 11,759.96 Signed 3 12 03 03 08 18 14 21 17 02 25 09 01 09 CADREMENT ACTP LOT 05 lected rural areas n DISTRICT ANKAZOABO DRT11CFPLAN19002 / Age Component 1: Building a s Quality And Cos 2019-12-1 2019-12- 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2020-02- 2020-04- 2020-02- 2020-05- 2022-08- nce de planification de l'AC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 32,000.00 20,342.91 Signed 1 04 12 28 06 25 27 25 03 11 21 21 06 29 TP Antanifotsy lected rural areas n DRT11CFPLAN19003 / Age Component 1: Building a s Quality And Cos 2019-12-1 2019-12- 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-04- 2020-02- 2020-04- 2020-02- 2020-05- 2022-08- nce de planification de l'AC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 32,000.00 23,229.65 Signed 1 04 12 28 06 25 27 25 03 11 21 21 06 29 TP Antanifotsy lected rural areas n DRT11CFPLAN19004 / Age Component 1: Building a s Quality And Cos 2019-12-1 2019-12- 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2020-02- 2020-04- 2020-02- 2020-05- 2022-08- nce de planification de l'AC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 21,000.00 30,286.02 Signed 1 04 12 28 06 25 27 25 06 11 21 21 06 29 TP Arivonimamo lected rural areas n DRT11CFCIC19001 / Cabin Component 1: Building a s Quality And Cos et chargé de l'appui au cibl 2019-12-1 2020-01- 2019-12- 2019-12- 2020-03- 2020-01- 2020-04- 2020-01- 2020-04- 2020-02- 2020-06- 2020-02- 2020-07- 2020-07- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 36,500.00 10,175.79 Signed age communautaire des ac 1 24 12 28 20 25 06 25 27 11 08 21 25 20 lected rural areas n tivités ACTP dans le District d'Arivonimamo DRA11CFAGEC19001 / EN Component 1: Building a s Quality And Cos CADREMENT INTERVETION 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2021-02- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 13,000.00 20,833.96 Signed 1 - 02 ACTIVITES ARGENT 8 20 13 21 21 20 12 30 12 07 25 21 04 20 lected rural areas n CONTRE TRAVAIL PRODUCT IF TERROIR ILAKA EST DRA11CFAGEC19002 / EN Component 1: Building a s Quality And Cos CADREMENT INTERVETION 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2021-02- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 12,500.00 14,942.14 Signed 1 - 02 ACTIVITES ARGENT 8 20 13 21 21 20 13 30 13 07 25 21 04 20 lected rural areas n CONTRE TRAVAIL PRODUCT IF TERROIR TSIVANGIANA DRA11CFAGEC19003 / EN CADREMENT INTERVETION Component 1: Building a s Quality And Cos 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2021-02- 1 - 02 ACTIVITES ARGENT IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 14,300.00 24,116.95 Signed 8 20 13 21 21 20 11 30 11 07 25 21 04 20 CONTRE TRAVAIL PRODUCT lected rural areas n IF TERROIR AMPANALNA e t TERROIR AMBALAVOLO DRA11CFAGEC19004 / EN CADREMENT INTERVETION Component 1: Building a s Quality And Cos 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2021-02- 1 - 02 ACTIVITES ARGENT IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 13,200.00 19,960.39 Signed 8 20 13 21 21 20 11 30 24 07 25 21 04 20 CONTRE TRAVAIL PRODUCT lected rural areas n IF TERROIR NIAROVANA CA ROLINE DRA11CFAGEC19005 / EN Component 1: Building a s Quality And Cos CADREMENT INTERVETION 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2021-02- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 8,500.00 15,154.88 Signed 1 - 02 ACTIVITES ARGENT 8 20 13 21 21 20 13 30 13 07 25 21 04 20 lected rural areas n CONTRE TRAVAIL PRODUCT IF TERROIR TSARASAMBO DRA11CFAGEC19006 / EN CADREMENT INTERVETION Component 1: Building a s Quality And Cos 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2021-02- 1 - 02 ACTIVITES ARGENT IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 8,500.00 13,949.82 Signed 8 20 13 21 21 20 12 30 12 07 25 21 04 20 CONTRE TRAVAIL PRODUCT lected rural areas n IF TERROIR TANAMBAO VA TRAKAKA DRA11CFAGEC19007 / EN Component 1: Building a s Quality And Cos CADREMENT INTERVETION 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2021-02- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 11,800.00 17,256.96 Signed 1 - 02 ACTIVITES ARGENT 8 20 13 21 21 20 12 30 24 07 27 21 04 20 lected rural areas n CONTRE TRAVAIL PRODUCT IF TERROIR SAHAMATEVINA DRA11CFAGEC19008 / EN CADREMENT INTERVETION Component 1: Building a s Quality And Cos 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2021-02- 1 - 02 ACTIVITES ARENT C IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 11,400.00 24,800.93 Signed 8 20 13 21 21 20 13 30 24 07 27 21 04 20 ONTRE TRAVAIL PRODUCTI lected rural areas n F TERROIR AMBODIVOANA NTO et TERROIR BEANGIVY DRA11CFPLAN19001 / Plan ifications : opérationnalisat ion des plans au mois de fé Component 1: Building a s Quality And Cos 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-04- 2020-02- 2020-04- 2022-04- vrier 2019 et assurent le s IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 73,900.00 28,282.56 Signed 8 04 13 20 04 19 05 24 27 01 04 13 23 13 uivi de mise en œuvre et l’ lected rural areas n appui au suivi-évaluation c ommunautaire ( 2 intervent ions à 04 activités) DG20CFAGEX2001 / Agenc Component 3: Building the e d'encadrement et de paie institutional capacity for c Consultant Qual 2020-01-0 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- ment ACT Post Catastrophe IDA / D4340 oordination, monitoring an Post ification Selecti Open - National 15,000.00 13,103.61 Signed 7 08 07 13 08 17 10 20 11 31 de 2 sites: assainissement d evaluation of the social p on et curage canal à FIOFIO et rotection syst em à Ambalavola DG20CFAGEX2002 / Agenc Component 3: Building the e d'encadrement et de paie institutional capacity for c Consultant Qual 2020-01-0 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- ment ACT Post Catastrophe IDA / D4340 oordination, monitoring an Post ification Selecti Open - National 15,000.00 13,103.61 Signed 7 08 07 13 08 17 10 20 11 31 de 2 sites: assainissement d evaluation of the social p on et curage canal à Mahavok rotection syst em y Avaratra et Tsararano No sikely DRT13CFAGEX2001 / Enca drement et paiement des b énficiaires de l'ACT postcat Component 1: Building a s Consultant Qual 2020-01-1 2020-01- 2020-01- 2020-01- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-02- astrophe dans deux secteu IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 7,000.00 617.46 Completed 4 14 14 16 15 03 17 10 21 24 07 rs dans le Fokontany d'Am lected rural areas on panotokana, Commune urb aine d'Antananarivo, Distric t d'Antananarivo V, Région d'Analamanga DG20CFAGEX2003 / Encad rement et paiement ACT Po Component 1: Building a s Consultant Qual 2020-01-1 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-01- 2020-02- st Catastrophe: travaux d'u IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 28,000.00 26,256.00 Signed 6 08 17 24 24 28 29 28 31 08 rgence d'assainissement et lected rural areas on de nettoyage dans le Fokon tany de Tsararano Ambany DRA13CFAGEX20002 / PRE STATION DE SERVICE POUR LA REALISATION DE MICRO- Component 1: Building a s Consultant Qual PROJETS A HAUTE INTENSIT 2020-01-2 2020-01- 2020-01- 2020-01- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 21,710.00 1,865.18 Signed E DE MAIN-D’OEUVRE : EN 8 28 28 30 28 12 29 17 31 19 lected rural areas on CADREMENT ET PAIEMENT ACT POST CATASTROPHE D ES 03 FKT COMMUNE RURA LE ILAFY DIST AMBATON DRAZAKA DRA13CFAGEX20001 / PRE STATION DE SERVICE POUR LA REALISATION DE MICRO- Component 1: Building a s Consultant Qual PROJETS A HAUTE INTENSIT 2020-01-2 2020-01- 2020-01- 2020-01- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 21,710.00 1,858.99 Signed E DE MAIN-D’OEUVRE : EN 8 28 28 30 29 12 29 17 31 19 lected rural areas on CADREMENT ET PAIEMENT ACT POST CATASTROPHE D ES 03 FKT COMMUNE RURA LE TANAMBE DIST AMPAR AFARAVOLA DRA13CFAGEX20003 / DR A13CFAGEX20003 PRESTA TION DE SERVICE POUR LA REALISATION DE MICRO- P Component 1: Building a s Consultant Qual 2020-02-0 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- ROJETS A HAUTE INTENSITE IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 17,310.00 1,348.33 Signed 5 12 05 07 13 20 12 25 15 27 DE MAIN-D’OEUVRE : ENC lected rural areas on ADREMENT ET PAIEMENT A CT POST CATASTROPHE DE S 04 FKT COMMUNE URBAI NE AMBATONDRAZAKA D IST AMBATONDRAZAKA DRA13CFAGEX20004 / DR A13CFAGEX20004 PRESTA TION DE SERVICE POUR LA REALISATION DE MICRO- P Component 1: Building a s Consultant Qual 2020-02-0 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- ROJETS A HAUTE INTENSITE IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 17,310.00 1,363.82 Signed 5 12 05 07 13 20 14 25 15 27 DE MAIN-D’OEUVRE : ENC lected rural areas on ADREMENT ET PAIEMENT A CT POST CATASTROPHE DE S 04 FKT COMMUNE RURAL E TANAMBE DIST AMPARA FARAVOLA DRA13CFAGEX20005 / DR A13CFAGEX20005 PRESTA TION DE SERVICE POUR LA REALISATION DE MICRO- P Component 1: Building a s Consultant Qual 2020-02-0 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- ROJETS A HAUTE INTENSITE IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 17,310.00 1,372.09 Signed 5 12 05 07 13 20 14 25 15 27 DE MAIN-D’OEUVRE : ENC lected rural areas on ADREMENT ET PAIEMENT A CT POST CATASTROPHE DE S 04 FKT COMMUNE RURAL E BEANANA DIST AMPARAF ARAVOLA DRA13CFAGEX20006 / DR A13CFAGEX20006 PRESTA TION DE SERVICE POUR LA REALISATION DE MICRO- P Component 1: Building a s Consultant Qual 2020-02-0 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- ROJETS A HAUTE INTENSITE IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 17,310.00 1,334.17 Signed 5 12 05 07 13 20 13 25 15 27 DE MAIN-D’OEUVRE : ENC lected rural areas on ADREMENT ET PAIEMENT A CT POST CATASTROPHE DE S 04 FKT COMMUNE URBAI NE MORAMANGA DIST MO RAMANGA DG20CFAGEX2004 / Encad rement et paiement ACT Po Component 3: Building the st Catastrophe: travaux d'u institutional capacity for c Consultant Qual rgence d'assainissement et 2020-02-1 2020-01- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-04- IDA / D4340 oordination, monitoring an Post ification Selecti Open - National 30,000.00 26,089.51 Signed de nettoyage dans les Foko 5 08 15 21 14 25 25 28 26 28 d evaluation of the social p on ntany MATIAKOHO, ANTAFI rotection syst em AKASAKA,ANTANAMARIAZY , ANTANAMARIAZY - Comm une : AMBILOBE - District : AMBILOBE - Région : DIANA DG20CFAGEX2005 / Encad rement et paiement ACT Po st Catastrophe: travaux d'u Component 3: Building the rgence d'assainissement et institutional capacity for c Consultant Qual 2020-02-1 2020-02- 2020-02- 2020-02- 2020-02- 2020-02- 2020-04- de nettoyage dans les Foko IDA / D4340 oordination, monitoring an Post ification Selecti Open - National 25,000.00 0.00 Canceled 5 25 15 21 25 28 28 ntany SENGALOKA, MATSA d evaluation of the social p on BORILAIDAMA, MATSABORI rotection syst em LAIDAMA, MANTALIMARO A NDREFANA - Commune : A MBILOBE - District : AMBIL OBE - Région : DIANA DG20CFAGEX2006 / Encad rement et paiement ACT Po Component 3: Building the st Catastrophe: travaux d'u institutional capacity for c Consultant Qual rgence d'assainissement et 2020-02-1 2020-01- 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- 2020-02- 2020-03- 2020-04- IDA / D4340 oordination, monitoring an Post ification Selecti Open - National 15,000.00 12,778.13 Signed de nettoyage dans les Foko 5 08 15 21 14 25 05 28 06 28 d evaluation of the social p on ntany AMBALAMAHATSINJO rotection syst em , TSARATANANA - Commu ne : AMBILOBE - District : A MBILOBE - Région : DIANA DRA13CFAGEX20007 / PRE STATION DE SERVICE POUR LA REALISATION DE MICRO- Component 1: Building a s Consultant Qual PROJETS A HAUTE INTENSIT 2020-02-2 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- 2020-02- 2020-03- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 12,664.00 1,007.37 Signed E DE MAIN-D’OEUVRE : EN 0 24 20 22 25 06 26 11 28 31 lected rural areas on CADREMENT ET PAIEMENT ACT POST CATASTROPHE D ES 03 FKT COMMUNE URBA INE MAHANORO DIST MA HANORO DRA13CFAGEX20008 / PRE STATION DE SERVICE POUR LA REALISATION DE MICRO- Component 1: Building a s Consultant Qual PROJETS A HAUTE INTENSIT 2020-02-2 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- 2020-02- 2020-03- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 16,889.00 1,357.94 Signed E DE MAIN-D’OEUVRE : EN 0 24 20 22 25 06 26 11 28 31 lected rural areas on CADREMENT ET PAIEMENT ACT POST CATASTROPHE D ES 04 FKT COMMUNE URBA INE MAHANORO DIST MA HANORO DRA13CFAGEX20009 / PRE STATION DE SERVICE POUR LA REALISATION DE MICRO- Component 1: Building a s Consultant Qual PROJETS A HAUTE INTENSIT 2020-02-2 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- 2020-02- 2020-03- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 12,664.00 1,023.90 Signed E DE MAIN-D’OEUVRE : EN 0 24 20 22 25 06 26 11 28 31 lected rural areas on CADREMENT ET PAIEMENT ACT POST CATASTROPHE D ES 03 FKT COMMUNE RURA LE AMBODIHARINA DIST M AHANORO DRA13CFAGEX20010 / PRE STATION DE SERVICE POUR LA REALISATION DE MICRO- Component 1: Building a s Consultant Qual PROJETS A HAUTE INTENSIT 2020-02-2 2020-02- 2020-02- 2020-02- 2020-02- 2020-03- 2020-02- 2020-03- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 12,664.00 1,007.76 Signed E DE MAIN-D’OEUVRE : EN 0 24 20 22 25 06 26 11 28 31 lected rural areas on CADREMENT ET PAIEMENT ACT POST CATASTROPHE D ES 03 FKT COMMUNE URB AINE VATOMANDRY DIST VATOMANDRY DG20CFAGEX2007 / Presta tion d'une Agence d'encadr Component 3: Building the ement pour la mise en œuv institutional capacity for c Consultant Qual 2020-03-1 2020-03- 2020-05- 2020-06- 2020-07- 2021-01- re de micro-projet ACT PC d IDA / D4340 oordination, monitoring an Post ification Selecti Open - National 15,000.00 0.00 Canceled 0 31 14 13 18 14 ans les Fokontany AMBOND d evaluation of the social p on RONA et AMBATOMITRAKA rotection syst em - Commune : ANTALAHA - District : ANTALAHA - Régio n : SAVA, DG20CFAGEX2008 / Presta tion d'une Agence d'encadr Component 3: Building the ement pour la mise en œuv institutional capacity for c Consultant Qual 2020-03-1 2020-03- 2020-05- 2020-06- 2020-07- 2021-01- re de micro-projet ACT PC d IDA / D4340 oordination, monitoring an Post ification Selecti Open - National 15,000.00 0.00 Canceled 0 31 14 13 18 14 ans les Fokontany ANKOAL d evaluation of the social p on ABE et ANTSONASONA - Co rotection syst em mmune : ANTALAHA - Distri ct : ANTALAHA - Région : S AVA, DRF11CFAGEC19008 / REC Component 1: Building a s Quality And Cos 2020-01-0 2020-02- 2020-01- 2020-02- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2020-05- 2020-03- 2020-06- 2020-04- 2022-05- RUTEMENT AGENCE D'ENC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 100,000.00 23,314.16 Signed 6 14 13 10 21 09 10 08 13 06 24 03 07 24 ADREMENT ACTP LOT 09 DI lected rural areas n STRICT ISANDRA DRT11CFAGEC19001 / Enc adrement des bénéficiaires Component 1: Building a s Quality And Cos 2019-12-0 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-04- 2022-08- de l'ACT-P dans le District d IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 43,000.00 34,080.10 Signed 6 14 09 27 24 11 13 16 20 29 27 06 08 14 'Antanifotsy : UTB BELANIT lected rural areas n RA et UTB AMBOHITOMPOI NA - lot 3 DRF11CFAGEC20001 / PRE STATAIRE DE SERVICE DES Component 1: Building a s Quality And Cos AGEC POUR L'ENCADREME 2020-05-2 2020-02- 2020-06- 2020-07- 2020-06- 2020-08- 2020-06- 2020-09- 2020-07- 2020-11- 2020-07- 2020-12- 2020-08- 2022-11- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 60,000.00 15,120.67 Signed NT DES TRAVAUX ET DES B 7 14 17 31 09 28 22 27 02 01 09 06 12 26 lected rural areas n ENEFICIAIRES DANS LE CA DRE DU PROGRAMME ACTP - TERROIR AMBOVOMBE - MANANDRIANA DRT11CFPLAN19005 / Age Component 1: Building a s Quality And Cos 2019-12-1 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2020-02- 2022-08- nce de planification de l'AC IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 21,000.00 0.00 Canceled 1 12 28 25 25 11 21 29 TP Arivonimamo lected rural areas n DRK11CFPLAN20001 / Rec rutement d'une Agence de Component 1: Building a s Quality And Cos Under Impleme 2020-06-1 2020-07- 2020-07- 2020-07- 2020-08- 2020-08- 2020-08- 2020-09- 2022-11- Planification chargée du sui IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 53,380.00 0.00 ntation 9 03 04 11 10 15 23 04 03 vi et supervisions des chan lected rural areas n tiers des 15 terroirs dans le districts de Manakara. DRU11CFAGEC19006 / RE Component 1: Building a s Quality And Cos 2020-01-1 2020-02- 2020-03- 2020-03- 2020-03- 2020-04- 2020-04- 2022-04- CRUTEMENT AGENCE D'EN IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 27,202.00 0.00 Canceled 3 03 03 18 21 02 09 09 CADREMENT ACTP LOT 06 lected rural areas n DISTRICT ANKAZOABO DRF11_SMC_AGEC2001 / S élection d'Agences chargée s de l'encadrement des tra Component 1: Building a s Least Cost Sele 2020-06-3 2020-08- 2020-06- 2020-07- 2020-07- 2020-08- 2020-08- 2020-09- 2020-08- 2020-10- 2020-08- 2020-12- 2020-09- 2022-12- vaux et des bénéficiaires d IDA / D4340 afety net for the poor in se Post Open - National 450,000.00 114,340.20 Signed ction 0 10 30 14 10 11 18 08 21 20 25 08 30 08 ans le cadre du programme lected rural areas FSP dans la Région Haute Matsiatra - District de Mana ndriana répartis en huit (08 ) lots DG20_SMC_BE_MO_2001 / Sélection de bureaux d'étu de chargés de la maîtrise d Component 1: Building a s Least Cost Sele 2020-06-3 2020-05- 2020-06- 2020-07- 2020-07- 2020-08- 2020-07- 2020-09- 2020-08- 2020-10- 2020-08- 2020-11- 2020-09- 2021-11- ’œuvre des infrastructures IDA / D4340 afety net for the poor in se Post Open - National 100,000.00 53,331.15 Signed ction 0 27 30 07 03 04 31 01 14 06 20 10 08 10 socio-économiques de base lected rural areas dans la Région Boeny, Distr icts de Soalala et Mahajang a 2, répartie en quatre (04) lots DRA11CFAGEC19009 / EN CADREMENT INTERVETION Component 1: Building a s Quality And Cos 2019-11-2 2020-02- 2019-12- 2019-12- 2020-02- 2020-01- 2020-03- 2020-01- 2020-03- 2020-02- 2020-03- 2020-02- 2020-04- 2021-02- 1 - 02 ACTIVITES ARENT C IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 12,900.00 20,535.04 Signed 8 20 13 21 21 20 11 30 24 07 27 21 04 20 ONTRE TRAVAIL PRODUCTI lected rural areas n F TERROIR ANDRORANGA et BEANGIVY DRU13CFAGEX19013 / EN Component 1: Building a s Quality And Cos CADREMENT ET SUPERVISI 2019-02-0 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 0.00 Canceled ON DES MICRO- PROJETS A 4 12 14 17 17 20 20 22 lected rural areas n HAUTE INTENSITE DE MAIN- D'ŒUVRE ACT PC FKT 13 DRU13CFAGEX19006 / EN CADREMENT ET SUPERVISI Component 1: Building a s Quality And Cos 2019-02-0 2019-01- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- ON DES MICRO- PROJETS A IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 0.00 Canceled 4 24 05 06 04 08 05 08 05 10 10 12 HAUTE INTENSITE DE MAIN- lected rural areas n D'ŒUVRE ACT PC FKT TAN AMBAO MOTOMBE DRU13CFAGEX19011 / EN Component 1: Building a s Quality And Cos CADREMENT ET SUPERVISI 2019-02-0 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 0.00 Canceled ON DES MICRO- PROJETS A 4 12 14 17 17 20 20 22 lected rural areas n HAUTE INTENSITE DE MAIN- D'ŒUVRE ACT PC FKT 11 DRU13CFAGEX19009 / EN CADREMENT ET SUPERVISI Component 1: Building a s Quality And Cos 2019-02-0 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- ON DES MICRO- PROJETS A IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 0.00 Canceled 4 05 06 08 08 10 10 12 HAUTE INTENSITE DE MAIN- lected rural areas n D'ŒUVRE ACT PC FKT MAH AVATSE II EST DRU13CFAGEX19010 / EN Component 1: Building a s Quality And Cos CADREMENT ET SUPERVISI 2019-02-0 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 0.00 Canceled ON DES MICRO- PROJETS A 4 12 14 17 17 20 20 22 lected rural areas n HAUTE INTENSITE DE MAIN- D'ŒUVRE ACT CP FKT 10 DRU13CFAGEX19012 / EN Component 1: Building a s Quality And Cos CADREMENT ET SUPERVISI 2019-02-0 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 0.00 Canceled ON DES MICRO- PROJETS A 4 12 14 17 17 20 20 22 lected rural areas n HAUTE INTENSITE DE MAIN- D'ŒUVRE ACT PC FKT 12 DRU13CFAGEX19015 / EN Component 1: Building a s Quality And Cos CADREMENT ET SUPERVISI 2019-02-0 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 0.00 Canceled ON DES MICRO- PROJETS A 4 12 14 17 17 20 20 22 lected rural areas n HAUTE INTENSITE DE MAIN- D'ŒUVRE ACT PC FKT 15 DRU13CFAGEX19014 / EN Component 1: Building a s Quality And Cos CADREMENT ET SUPERVISI 2019-02-0 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 0.00 Canceled ON DES MICRO- PROJETS A 4 12 14 17 17 20 20 22 lected rural areas n HAUTE INTENSITE DE MAIN- D'ŒUVRE ACT PC FKT 14 DRU13CFAGEX19007 / EN CADREMENT ET SUPERVISI Component 1: Building a s Quality And Cos 2019-02-0 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- ON DES MICRO- PROJETS A IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 0.00 Canceled 4 05 06 08 08 10 10 12 HAUTE INTENSITE DE MAIN- lected rural areas n D'ŒUVRE ACT PC FKT TAN AMBAO DRU13CFAGEX19008 / EN CADREMENT ET SUPERVISI Component 1: Building a s Quality And Cos 2019-02-0 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-03- ON DES MICRO- PROJETS A IDA / 57080 afety net for the poor in se Post t-Based Selectio Open - National 704.05 0.00 Canceled 4 05 06 08 08 10 10 12 HAUTE INTENSITE DE MAIN- lected rural areas n D'ŒUVRE ACT PC FKT MAH AVATSE II OUEST DRT11CFAGEC20001 / Rec Component 1: Building a s Quality And Cos rutement d'Agence d'encad Under Impleme 2020-09-2 2020-02- 2020-09- 2020-10- 2020-11- 2020-11- 2020-11- 2020-12- 2022-10- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 135,905.00 0.00 rement des bénéficiaires d ntation 1 14 21 05 02 09 30 21 02 lected rural areas n u FSP dans le District d'Ariv onimamo _ 05 lots. Page 13 DRT13CFMO20001 / Recru tement de bureaux d'étude chargés de la maitrise d'œ Component 1: Building a s Quality And Cos uvre des travaux de recons Under Impleme 2020-09-2 2020-10- 2020-09- 2020-10- 2020-11- 2020-11- 2020-11- 2020-12- 2022-02- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 25,000.00 0.00 truction et de réhabilitation ntation 1 23 21 08 07 17 29 17 25 lected rural areas n des infrastructures socio-éc onomiques de base dans le s régions Analamanga et M enabe _ Deux (02) lots DRA13 SFQC CFMO 20001 / Recrutement d'un bureau d'étude chargé de la maîtri Component 1: Building a s Quality And Cos Under Impleme 2020-09-2 2020-10- 2020-10- 2020-10- 2020-11- 2020-11- 2020-12- 2020-12- 2021-12- se d'œuvre des travaux de IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 10,000.00 0.00 ntation 5 01 10 20 19 29 09 24 24 reconstruction et de réhabil lected rural areas n itation des infrastructures s ocio-économiques de base dans la Région Alaotra Man goro DG20_SMC_AUDIT_TF_201 8 / Recrutement d'un cabin Component 1: Building a s Least Cost Sele 2020-10-1 2020-10- 2020-10- 2020-11- 2020-11- 2020-12- 2020-12- 2020-12- 2020-12- 2021-01- 2020-12- 2021-02- 2021-01- 2021-04- et chargé de l'audit financi IDA / D4340 afety net for the poor in se Post Open - National 20,000.00 6,808.51 Signed ction 9 27 26 16 06 16 03 30 11 27 17 24 08 25 er des activités relatives à l lected rural areas a mise en œuvre du Tosika Fameno DRK11_SFQC_AGEC20008 / Prestation de service d'en Component 1: Building a s Quality And Cos Pending Imple 2020-11-2 2020-12- 2020-12- 2021-01- 2021-01- 2021-01- 2021-02- 2021-02- cadrement des bénéficiaire IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 13,800.00 0.00 mentation 7 02 20 19 21 25 06 09 s des terroirs de Sahanamb lected rural areas n ohitra et de Sahanambohitr a dans le District de Manak ara DRA11_SFQC_PLAN20001 / Recrutement agence de pla nification pour l'opérationn Component 1: Building a s Quality And Cos 2020-11-3 2021-01- 2020-12- 2020-12- 2020-01- 2021-01- 2020-03- 2021-01- 2020-03- 2021-02- 2020-03- 2021-02- 2020-04- 2022-02- alisation des plans au mois IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 22,000.00 28,497.70 Signed 0 22 15 22 24 21 09 26 19 03 30 16 29 16 de Mars 2021 et assure le s lected rural areas n uivi de mise en œuvre et l’ appui au suivi-évaluation c ommunautaire ( PAMO acti vité n°11 ) DG_SQC_FILM_COMM_210 Component 1: Building a s Consultant Qual 1 / Sélection d'une agence 2021-01-2 2021-07- 2021-02- 2021-08- 2021-04- 2021-10- 2021-05- 2021-11- 2021-06- 2021-12- 2021-09- IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 40,000.00 14,615.45 Signed chargée de la conception e 9 08 19 31 04 14 04 18 08 07 06 lected rural areas on t réalisation de microfilms de sensibilisation DG_SQC_ANALYSE_ORGA_ FID_2101 / Sélection d'un c Component 1: Building a s Consultant Qual 2021-03-0 2021-03- 2021-03- 2021-04- 2021-04- 2021-05- 2021-06- 2021-06- 2021-07- 2021-11- abinet en charge de l'analy IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 20,000.00 26,736.10 Signed 8 15 15 12 23 12 21 02 20 29 se organisationnelle et de l lected rural areas on a mise en œuvre du manag ement qualité du FID DG_21010_SMC_BE_MO_S OFIA / Sélection de bureau x d'étude chargés de la ma Component 1: Building a s îtrise d’œuvre des infrastru Least Cost Sele 2021-04-0 2021-04- 2021-04- 2021-05- 2021-05- 2021-06- 2021-06- 2021-06- 2021-07- 2021-07- 2021-07- 2021-08- 2021-08- 2022-08- IDA / D4340 afety net for the poor in se Post Open - National 35,000.00 20,087.43 Signed ctures socio-économiques ction 5 26 12 17 18 14 29 28 10 19 21 09 18 09 lected rural areas de base dans la Région Sofi a, Districts de Ambato Boe ny, Antsohihy, Port Berger, Analalava, répartis en deux (02) lots DRA_21002_SMC_BE_MO / Recrutement des bureaux d'études pour la maitrise d' Component 1: Building a s Least Cost Sele Under Impleme 2021-03-2 2021-04- 2021-04- 2021-04- 2021-05- 2021-06- 2021-06- 2021-07- 2022-07- œuvre des travaux de réha IDA / D4340 afety net for the poor in se Post Open - National 57,000.00 0.00 ction ntation 5 27 09 21 19 02 16 05 05 bilitation et reconstruction lected rural areas des infrastructures socio éc onomique de base dans la r égion Analanjirofo DRT_21002_SMC_CIB_BEN Component 1: Building a s / Recrutement d'un cabinet Least Cost Sele Under Impleme 2021-03-3 2021-03- 2021-04- 2021-04- 2021-05- 2021-05- 2021-06- 2021-07- 2021-10- IDA / D4340 afety net for the poor in se Post Open - National 30,000.00 0.00 de ciblage des 6 000 nouve ction ntation 1 31 01 23 21 28 14 03 31 lected rural areas aux bénéficiaires du FSP Ar ivonimamo. DRT_21001_SQC_BE_MO / Recrutement de bureaux d' Component 1: Building a s Consultant Qual Under Impleme 2021-04-1 2021-04- 2021-04- 2021-05- 2021-05- 2021-06- 2022-06- étude en vue de la maîtrise IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 10,000.00 0.00 ntation 3 13 23 15 30 11 11 d’œuvre des travaux dans l lected rural areas on es Régions d'Analamanga e t de Menabe en 2 lots. DRU_21003_SQC_MAÎTRIS E D’ŒUVRE / Maîtrise d'œu Component 1: Building a s Consultant Qual 2021-04-1 2021-04- 2021-04- 2021-05- 2021-05- 2021-06- 2021-06- 2021-06- 2021-06- 2022-06- vre pour les travaux de rec IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 4,000.00 4,250.06 Signed 2 12 19 24 18 08 14 18 25 18 onstruction - CEG Ambolofo lected rural areas on ty et Ecole Préscolaire Amb olofoty DRT_21003_SQC_AGEC / A gences d'encadrement pou Component 1: Building a s Consultant Qual Under Impleme 2021-06-3 2021-11- 2021-07- 2021-08- 2021-08- 2021-08- 2022-03- r les 6 000 nouveaux bénéf IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 100,077.22 0.00 ntation 0 10 15 04 09 16 31 iciaires Filets Sociaux Prod lected rural areas on uctifs (FSP) du District d'Ari vonimamo DRA_21003_SQC_CIC_TMD H / Recrutement de cabinet Component 1: Building a s Consultant Qual de ciblage communautaire 2021-06-3 2021-10- 2021-07- 2022-08- 2021-07- 2021-12- 2021-08- 2022-01- 2021-08- 2022-02- 2022-02- IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 69,500.00 98,813.37 Signed des bénéficiaires TMDH FA 0 27 15 23 30 07 04 25 20 18 16 lected rural areas on 3;réparti en quatre (04) lot s dans les Régions d'Alao tra Mangoro et d'Analanjiro fo DRF_21001_SQC_CIC_TMD H / Recrutement Agence de Component 1: Building a s Consultant Qual Under Impleme 2021-07-0 2021-11- 2021-07- 2021-08- 2021-09- 2021-09- 2021-12- Ciblage assurant le ciblage IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 32,432.43 0.00 ntation 6 03 27 21 05 25 24 communautaire des bénéfi lected rural areas on ciaires TMDH pour le FSS F A3, répartis en 08 lots DRT_21008_SQC_CIC_TMD H / Ciblage communautaire Component 1: Building a s Consultant Qual Under Impleme 2021-06-3 2021-10- 2021-07- 2021-08- 2021-08- 2021-08- 2021-12- des bénéficiaires TMDH po IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 149,189.19 0.00 ntation 0 27 15 04 09 16 14 ur le FSS FA3, réparti en tro lected rural areas on is (03) lots dans la Région Vakinankaratra DRP_21005_SQC_CIC_TMD H / Ciblage communautaire Component 1: Building a s Consultant Qual Under Impleme 2021-06-2 2021-10- 2021-07- 2022-05- 2021-07- 2021-12- 2021-08- 2021-09- 2021-11- des bénéficiaires TMDH po IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 20,000.00 0.00 ntation 8 27 13 20 28 13 25 14 13 ur le FSS FA 3 repartis en 0 lected rural areas on 7 lots dans les régions d'An osy et Androy DRU_21005_SQC_CIC_TMD H / Ciblage communautaire Component 1: Building a s Consultant Qual 2021-07-1 2021-10- 2021-08- 2022-05- 2021-08- 2021-12- 2021-08- 2022-01- 2021-08- 2022-02- 2021-11- 2022-08- des bénéficiaires TMDH po IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 23,200.00 31,271.29 Completed 5 28 14 12 23 10 26 27 28 23 26 11 ur le FSS FA 3 reparti en un lected rural areas on (01) lot dans la région Atsi mo Andrefana DRK_21001_SFQC_CIB_BE Component 1: Building a s Quality And Cos N / Sélection de 03 agence Pending Imple 2021-06-1 2021-06- 2021-07- 2021-08- 2021-09- 2021-10- 2021-10- 2021-12- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 168,000.00 0.00 s de ciblages des bénéficiai mentation 0 24 22 21 05 03 31 20 lected rural areas n res du programme TMDH F SS-FA3 DRK_21001_SQC_CIC_TMD Component 1: Building a s Consultant Qual H / Sélection de 03 agence Under Impleme 2021-06-3 2021-10- 2021-07- 2021-08- 2021-08- 2021-08- 2021-11- IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 168,000.00 0.00 s de ciblages des bénéficiai ntation 0 27 15 04 09 16 14 lected rural areas on res du programme TMDH F SS-FA3 DRA_ 21007_ SMC _BE MO _LYCEE AMPASIMBE / Recru tement de bureau d'étude Component 1: Building a s chargé de la maîtrise d'œu Least Cost Sele Under Impleme 2021-08-1 2021-08- 2021-09- 2021-09- 2021-10- 2021-10- 2021-11- 2021-11- 2022-11- IDA / D4340 afety net for the poor in se Post Open - National 4,060.00 0.00 vre des travaux de reconstr ction ntation 9 30 03 13 11 18 02 18 18 lected rural areas uction et de réhabilitation d es infrastructures socio-éco nomiques de base : Lycée Ampasimbe Manantsatrana DRT_21017_SQC_AGEX_M Component 1: Building a s Consultant Qual Pending Imple 2021-09-1 2021-09- 2021-10- 2021-10- 2021-11- 2022-10- AJ_TMDH_FA3 / Recruteme IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 13,800.00 0.00 mentation 5 30 20 25 10 26 nt de trois (03) AGEX pour lected rural areas on MAJ pour FSS FA3 DRT_21019_SQC_CIC_FSP_ FA3 / Recrutement de cabi Component 1: Building a s Consultant Qual Under Impleme 2021-09-3 2021-12- 2021-10- 2022-03- 2021-11- 2022-05- 2021-11- 2022-10- 2021-11- 2022-11- net de ciblage communaut IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 46,000.00 0.00 ntation 0 13 15 09 04 30 09 31 28 13 aire des bénéficiaires FSP r lected rural areas on épartis en cinq (05) lots da ns les Huits Districts pour l e FSS FA3 DRT_21023_SMC_APL_FSP_ FA3 / Recrutement d'Agenc Component 1: Building a s Least Cost Sele Under Impleme 2021-08-3 2022-01- 2021-08- 2021-09- 2021-10- 2021-10- 2021-11- 2021-11- 2024-11- es de Planification FSP répa IDA / D4340 afety net for the poor in se Post Open - National 114,100.00 0.00 ction ntation 0 14 31 20 20 25 09 29 29 rtie en six (06) lots dans les lected rural areas Huits Districts pour le FSS F A3. DRT_21026_SMC_AGEC_FS P_FA3 / Recrutement d'Age Component 1: Building a s Least Cost Sele Under Impleme 2021-08-3 2021-09- 2021-10- 2021-11- 2021-11- 2021-12- 2022-01- 2025-01- nces d'encadrement (AGEC IDA / D4340 afety net for the poor in se Prior Open - National 1,751,400.00 0.00 ction ntation 0 07 11 17 29 28 31 31 ) FSP répartis en vingt-trois lected rural areas (23) lots dans les Huits Dis tricts pour le FSS FA3 DG_21038_SQC_CENTRE_F Component 3: Building the Consultant Qual ORMATION_ANGLAIS / Séle institutional capacity for c 2021-10-1 2022-03- 2021-10- 2022-04- 2021-11- 2022-07- 2021-11- 2022-10- 2021-12- 2022-03- IDA / D4340 Post ification Selecti Open - National 2,000.00 0.00 Signed ction d'un centre de format oordination, monitoring an 1 27 25 07 15 08 22 11 13 13 on ion en langue Anglaise d evaluation of the social p rotection syst em DRK_21016_SFQC_AGEC_F Component 1: Building a s Quality And Cos SP / Recrutement Agence d 2021-11-1 2022-03- 2021-11- 2022-03- 2021-12- 2022-05- 2022-01- 2022-06- 2022-01- 2022-09- 2022-01- 2022-10- 2022-01- 2023-01- IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 238,000.00 0.00 Signed 'encadrement FSP dans le 5 07 20 31 08 25 07 24 09 20 13 10 25 20 lected rural areas n District de Vangaindrano DRF_21023_SFQC_RECRUT EMENT_AGEC_FSP_FA3 / Re Component 1: Building a s Quality And Cos Under Impleme 2021-12-0 2022-03- 2021-12- 2022-02- 2022-05- 2022-03- 2022-06- 2022-04- 2022-07- 2022-05- 2022-06- 2024-12- crutement de quinze (15) IDA / D7740 afety net for the poor in se Post t-Based Selectio Open - National 458,912.92 0.00 ntation 6 03 27 09 27 09 28 08 04 13 17 31 AGEC assurant l'encadrem lected rural areas n ent des terroirs pour les 04 districts _ FSP__FA3 DRA_21022_SFQC_AGEC _ FSP_FA3 / Recrutement DIX Component 1: Building a s Quality And Cos Under Impleme 2021-11-2 2022-02- 2021-12- 2022-03- 2022-01- 2022-02- 2022-02- 2022-03- 2022-04- 2025-04- (10) AGEC assurant l'encad IDA / D4340 afety net for the poor in se Post t-Based Selectio Open - National 417,000.00 0.00 ntation 2 23 07 08 13 10 25 14 07 06 rement FSP dans les Distric lected rural areas n ts d'Amparafaravola et de Fenoarivo Atsinanana DRA_21023_SQC _PLAN_FS P_FA3 / Recrutement deux Component 1: Building a s Consultant Qual Under Impleme 2021-12-1 2022-02- 2021-12- 2022-03- 2022-02- 2022-02- 2022-03- 2025-01- (02) Agences de planificati IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 41,000.00 0.00 ntation 3 02 20 14 07 14 08 21 on du programme FSP da lected rural areas on ns les Districts d'Amparafar avola et de Fenoarivo Atsin anana DRF_21021_SQC_RECRUTE Component 1: Building a s Consultant Qual MENT_CIC_FSP_FA3 / Recru Under Impleme 2021-12-1 2022-03- 2021-12- 2022-01- 2022-05- 2022-02- 2022-03- 2022-07- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 44,000.00 0.00 tement Agence de Ciblage ntation 3 03 28 26 23 10 07 05 lected rural areas on reparties en 03 lots _ FSP_ _FA3 DRF_21022_SQC_RECRUTE Component 1: Building a s Consultant Qual MENT_APL_FSP_FA3 / Recru Under Impleme 2021-12-1 2022-02- 2021-12- 2022-01- 2022-07- 2022-02- 2022-03- 2024-12- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 88,000.00 0.00 tement Agence de Planifica ntation 3 25 28 26 01 10 07 30 lected rural areas on tion reparties en 04 lots _ FSP__FA3 DRA_21024_SQC_CIB_FSP_ FA3 / Recrutement de cabi Component 1: Building a s Consultant Qual net de ciblage communaut Under Impleme 2021-12-1 2022-02- 2022-01- 2022-03- 2022-02- 2022-02- 2022-03- 2022-09- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 21,000.00 0.00 aire des bénéficiaires FSP ntation 3 02 07 14 14 21 14 10 lected rural areas on FA3 ;réparti en quatre (02) lots dans les Régions d'Ala otra Mangoro et d'Analanjir ofo DRU_21024_SFQC_AGEC_F Component 1: Building a s Quality And Cos SP FA3 / Recrutement TROI Under Impleme 2021-12-1 2022-02- 2021-12- 2022-03- 2022-02- 2022-06- 2022-03- 2022-07- 2022-03- 2022-08- 2022-04- 2022-10- 2022-05- 2025-05- IDA / D7740 afety net for the poor in se Post t-Based Selectio Open - National 160,700.00 0.00 S (03) Agences d'encadrem ntation 0 22 31 09 09 02 09 01 19 30 08 05 09 08 lected rural areas n ent du programme FSP FA3 DG_21048_SMC_AUDIT_TE CH_PC_FSP / Sélection d'un Component 1: Building a s Least Cost Sele 2021-12-1 2022-05- 2021-12- 2022-01- 2022-02- 2022-03- 2022-03- 2022-04- 2022-06- cabinet chargé de l'Audit T IDA / D4340 afety net for the poor in se Post Open - National 30,000.00 0.00 Canceled ction 7 30 24 21 18 04 25 15 14 echnique et Evaluation des lected rural areas activités de relèvement po st-cata DG_21055_SQC_AGEC_IPU Component 1: Building a s Consultant Qual / Sélection de partenaires ( 2022-01-0 2022-03- 2022-01- 2022-04- 2022-01- 2022-07- 2022-02- 2022-10- 2022-02- 2024-03- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 50,000.00 0.00 Signed Associations/ONG) en char 1 15 01 26 29 01 05 03 26 31 lected rural areas on ge de l'encadrement des B énéficiaires DRF_21033_QC_AGEX_IPU Component 1: Building a s Consultant Qual Under Impleme 2022-01-1 2022-04- 2022-01- 2022-02- 2022-07- 2022-02- 2022-03- 2023-12- / Recrutement des AGEX p IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 48,600.00 0.00 ntation 0 12 10 07 12 14 07 31 our IPU réparties en 02 lots lected rural areas on DRF_21032_QC_AGEX / MA Component 1: Building a s Consultant Qual J FSU / Recrutement des AG Pending Imple 2022-01-1 2022-01- 2022-03- 2022-03- 2022-04- 2022-07- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 3,600.00 0.00 EX chargés de faire la mise mentation 0 31 01 16 14 13 lected rural areas on à jour des données FSU rép arties en 02 lots. DRK_21022_QC_COL_DON Component 1: Building a s Consultant Qual _TMDH / Recrutement de n Pending Imple 2021-12-2 2022-01- 2022-02- 2022-02- 2022-03- 2022-06- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 32,800.00 0.00 euf (09) AGEX pour la colle mentation 0 10 08 23 24 22 lected rural areas on cte de données et mise à jo ur des bénéficiaires TMDH DRA_21033_QC_AGEX _MA Component 1: Building a s Consultant Qual J_FSU / Recrutement des A Pending Imple 2021-12-2 2022-01- 2022-02- 2022-02- 2022-03- 2022-06- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 6,200.00 0.00 GEX chargés de faire la mis mentation 0 10 16 23 24 22 lected rural areas on e à jour des données FSU r éparties en DEUX ( 02) lots. DRA_21032_QC_COL_DON Component 1: Building a s Consultant Qual _TMDH / Recrutement de SI Under Impleme 2022-02-0 2023-03- 2022-02- 2022-03- 2022-03- 2022-04- 2022-11- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 36,300.00 0.00 X (06) AGEX pour la collect ntation 7 17 21 07 14 04 30 lected rural areas on e de données et mise à jou r des bénéficiaires TMDH DRU_21023_SQC_AG PLAN Component 1: Building a s Consultant Qual Under Impleme 2021-12-1 2022-03- 2021-12- 2022-03- 2022-02- 2022-06- 2022-02- 2022-03- 2025-02- IF_FSP FA3 / Recrutement A IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 16,500.00 0.00 ntation 0 14 31 25 13 07 23 26 25 gence de planification du p lected rural areas on rogramme FSP FA3 DRF_21029_QC_AGEX_ CO L DONN_TMDH / Recruteme Component 1: Building a s Consultant Qual Under Impleme 2022-02-0 2023-03- 2022-02- 2023-04- 2022-03- 2022-04- 2022-05- 2022-12- nt des AGEX chargés de fai IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 31,000.00 0.00 ntation 2 03 23 07 24 08 07 30 re la collecte des données lected rural areas on des bénéficiaires TMDH _ F SS FA3 réparties en 04 lots. DRA_22003_SQC_BUREAU Component 1: Building a s Consultant Qual X_ETUDES_PC / Sélection d Pending Imple 2022-02-1 2022-02- 2022-03- 2022-03- 2022-04- 2023-11- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 26,400.00 0.00 e Bureaux d'étude chargés mentation 4 28 22 29 27 27 lected rural areas on de la maîtrise d'œuvre des travaux post-catastrophe DRT_22004_SQC_APL_FSP_ FA3 / Recrutement d'Agenc Component 1: Building a s Consultant Qual Under Impleme 2022-02-0 2022-03- 2022-02- 2022-03- 2022-03- 2022-05- 2022-04- 2022-05- 2022-04- 2024-12- e de Planification FSP répar IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 144,000.00 0.00 ntation 7 01 17 09 11 18 01 18 20 31 tie en six (06) lots dans les lected rural areas on six (06) Districts pour le FS S FA3 DRT_22005_SQC_AGEC_FS P_FA3 / Recrutement d'Age Component 1: Building a s Consultant Qual Under Impleme 2022-02-0 2022-04- 2022-02- 2022-04- 2022-10- 2022-05- 2022-12- 2022-05- 2024-12- nces d'encadrement des bé IDA / D7740 afety net for the poor in se Prior ification Selecti Open - National 1,501,200.00 0.00 ntation 7 06 22 03 07 08 08 29 31 néficiaires FSP répartis en lected rural areas on dix-neuf (19) lots dans les six (06) Districts pour le FS S FA3 DRB_22001_SQC_APL_FSP_ FA3 / Recrutement d'Agenc Component 1: Building a s Consultant Qual Under Impleme 2022-02-0 2022-03- 2022-02- 2022-03- 2022-03- 2022-05- 2022-04- 2022-04- 2024-12- e de Planification FSP répar IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 32,000.00 0.00 ntation 7 08 17 10 11 20 01 20 31 tie en deux (02) lots dans l lected rural areas on es deux (02) Districts pour le FSS FA3 DRB_22002_SQC_AGEC_FS P_FA3 / Recrutement d'Age Component 1: Building a s Consultant Qual Under Impleme 2022-02-0 2022-03- 2022-02- 2022-03- 2022-03- 2022-05- 2022-03- 2022-04- 2024-12- nces d'encadrement des bé IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 333,600.00 0.00 ntation 7 08 22 10 14 27 19 07 31 néficiaires FSP répartis en lected rural areas on quatre (04) lots dans les d eux (02) Districts pour le F SS FA3 DG_22004_SQC_AGENCE_ COMM / Sélection d'une Ag Component 1: Building a s Consultant Qual ence chargée d'accompagn 2022-02-0 2022-07- 2022-02- 2022-08- 2022-03- 2022-10- 2022-05- 2023-01- 2022-05- 2024-12- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 75,000.00 0.00 Signed er le FID dans la campagne 7 19 21 01 30 11 04 19 25 31 lected rural areas on de communication opératio nnelle du Projet FSS et de s es Programmes DRK_21017_SQC_PLAN_FS Component 1: Building a s Consultant Qual P / Recrutement d'un agen 2021-12-0 2022-04- 2021-12- 2022-04- 2022-02- 2022-05- 2022-03- 2022-07- 2022-04- 2022-10- IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 24,000.00 0.00 Signed ce de planification pour la 9 12 30 26 12 30 14 20 18 15 lected rural areas on composante FSP dans le Di strict de Vangaindrano DRP_22003_SQC_AGEX AC T_PC_EMNATI_URGENCE / R ecrutement des AGEXs pou r assurer l'encadrement de Component 1: Building a s Consultant Qual Under Impleme 2022-04-0 2022-06- 2022-04- 2022-07- 2022-04- 2022-04- 2022-04- 2022-05- s bénéficiaires de l'ACT HIM IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 12,500.00 0.00 ntation 1 03 01 21 15 22 22 22 O dans la réalisation des Tr lected rural areas on avaux de nettoyage, assain issement et re profilage de s infrastructures endomma gées par le cyclone EMNATI . (repartis en 19 lots) DG_22008_SQC_CAB_EVAL _LISTE_URGENCE / Sélectio n d'un Cabinet chargé de c Component 1: Building a s Consultant Qual Under Impleme 2022-03-2 2022-04- 2022-03- 2022-04- 2022-04- 2022-04- 2022-05- ollecte de données en vue IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 12,000.00 0.00 ntation 8 01 28 11 18 18 18 de l'évaluation de la qualité lected rural areas on de la liste des bénéficiaires du TMNC (Tosika Fameno) dans la commune urbaine d'Antananarivo. DG_22022_SQC_BE_MO_P OST-CATA / Bureaux d'étud Component 1: Building a s Consultant Qual es chargés de la maîtrise d' Under Impleme 2022-05-2 2022-07- 2022-06- 2022-07- 2022-07- 2022-08- 2022-08- 2022-09- 2023-09- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 200,000.00 0.00 œuvre des travaux de reco ntation 7 04 10 20 15 29 26 16 15 lected rural areas on nstruction/réhabilitation de s infrastructures socio-éco nomiques de base DRA_22009_QC_AGEX_IPU Component 1: Building a s Consultant Qual Under Impleme 2022-04-1 2023-02- 2022-04- 2022-05- 2022-05- 2022-06- 2024-04- / Recrutement des AGEX po IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 18,000.00 0.00 ntation 9 15 19 17 24 14 08 ur IPU réparties en 02 lots lected rural areas on DRK_22011_SQC_AGEX_AC T_HIMO_URGENCE / Sélecti Component 1: Building a s Consultant Qual Under Impleme 2022-05-0 2022-07- 2022-05- 2022-08- 2022-05- 2022-05- 2022-05- 2022-07- on d'agence d'exécution po IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 41,400.00 0.00 ntation 9 15 09 16 23 30 30 14 ur la réalisation des activité lected rural areas on s ACT reparties en 03 lots DG_22017_SQC_FORM_CO Component 1: Building a s Consultant Qual Pending Imple 2022-05-1 2022-05- 2022-07- 2022-08- 2022-09- 2022-12- MMDIGIT / Centre de forma IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 1,500.00 0.00 mentation 6 30 13 12 09 08 tion en communication digi lected rural areas on tale DG_22025_SQC_FORM_AGI LE / Consultant en charge d Component 1: Building a s Consultant Qual Under Impleme 2022-06-1 2023-03- 2022-07- 2023-03- 2022-08- 2022-09- 2022-09- 2022-10- e la formation de l'équipe d IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 3,000.00 0.00 ntation 7 02 01 16 05 02 23 23 u FID de la méthode de ges lected rural areas on tion de projet informatique AGILE DRP_21007_SQC_CIC_TMN C / Ciblage communautaire des ménages bénéficiaires Component 1: Building a s Consultant Qual 2021-06-2 2021-07- 2021-07- 2021-08- 2021-08- 2021-10- du Transfert Monétaire Non IDA / D4340 afety net for the poor in se Post ification Selecti Open - National 20,800.00 0.00 Canceled 8 03 18 15 25 24 Conditionnel dans la comm lected rural areas on une d'Ambonaivo, Manako mpy, Tsikolaky, Morafeno, Belindo Mahasoa Page 14 DRU_22001_SQC_AGEX_A CT HIMO_URGENCE / Sélect ion de partenaires (AGEX) c Component 1: Building a s Consultant Qual hargés du ciblage, de l'enc 2022-03-2 2022-04- 2022-03- 2022-04- 2022-04- 2022-04- 2022-05- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 8,100.00 0.00 Canceled adrement et du paiement d 8 29 28 11 18 18 18 lected rural areas on es bénéficiaires de l'ACT_HI MO, repartis en trois (03) lo ts dont 2 lots pour Benenitr a et 1 lot pour Morombe DRU_22002_QC_AGEX_CO LLECT_DONN_TMDH_FA3 / Component 1: Building a s Consultant Qual Recrutement des AGEX cha Under Impleme 2022-07-2 2023-03- 2022-08- 2023-05- 2022-09- 2022-09- 2022-10- 2023-10- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 32,000.00 0.00 rgés de faire la collecte des ntation 2 22 12 06 10 25 24 19 lected rural areas on données des bénéficiaires TMDH _ FSS FA3 réparties e n 04 lots. DRK_22013_SQC_AGEX_AC T_HIMO_URGENCE / Sélecti Component 1: Building a s Consultant Qual Under Impleme 2022-08-0 2022-09- 2022-08- 2022-09- 2022-10- 2022-11- 2022-12- 2023-04- on d'agence d'exécution po IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 27,900.00 0.00 ntation 4 01 25 23 08 07 12 11 ur la réalisation des activité lected rural areas on s ACT reparties en 02 lots DG_22048_SQC_AGEX_AC T_PC_URGENCE / Sélection Component 1: Building a s Consultant Qual de partenaires (AGEX) char Under Impleme 2022-12-1 2023-01- 2022-12- 2023-01- 2023-01- 2023-03- 2023-03- 2023-09- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 60,000.00 0.00 gés de l'appui aux ciblage, ntation 2 13 26 16 30 13 20 16 lected rural areas on encadrement des travaux e t supervision des paiement s des ACT post-cycloniques DG_22049_SQC_AGEX_TM NC_PC_URGENCE / Sélectio Component 1: Building a s Consultant Qual n de partenaires (AGEX) ch Under Impleme 2023-01-1 2023-02- 2023-01- 2023-02- 2023-02- 2023-03- 2023-04- 2023-10- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 500,000.00 0.00 argés de l'appui aux ciblag ntation 3 01 20 02 17 19 09 06 lected rural areas on e, supervision des paiemen ts et mesures d'accompagn ement des TMNC post-cycl oniques DG_22003_SQC_BUREAUX Component 1: Building a s Consultant Qual _ETUDES_PC / Sélection de 2022-02-0 2022-04- 2022-02- 2022-05- 2022-03- 2022-04- 2022-05- 2023-12- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 20,000.00 0.00 Canceled Bureaux d'étude chargés d 8 06 15 06 15 12 03 31 lected rural areas on e la maîtrise d'œuvre des t ravaux post-catastrophe DRT_23003_SQC_APL_FSP_ Component 1: Building a s Consultant Qual Pending Imple 2023-01-1 2023-02- 2023-03- 2023-03- 2023-04- 2024-10- FA3 / Recrutement d'Agenc IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 180,000.00 0.00 mentation 6 06 07 14 04 05 es de planification répartie lected rural areas on s en six (06) lots DG_23005_SQC_AGEX_AC T_PC_URGENCE / Sélection Component 1: Building a s Consultant Qual de partenaires (AGEX) char Under Impleme 2023-02-0 2023-02- 2023-02- 2023-03- 2023-03- 2023-05- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 10,000.00 0.00 gés de l'appui aux ciblage, ntation 6 13 27 06 13 12 lected rural areas on encadrement des travaux e t supervision des paiement s des ACT post-cycloniques (CHENESO) DG_23007_SQC_AGEX_AC T_FREDDY_URGENCE / Séle ction de partenaires (AGEX Component 1: Building a s Consultant Qual Pending Imple 2023-03-1 2023-03- 2023-03- 2023-04- 2023-04- 2023-06- ) chargés des ciblage, enca IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 27,000.00 0.00 mentation 5 22 29 05 12 11 drement travaux et supervi lected rural areas on sion de paiement des béné ficiaires ACT après le passa ge du Cyclone FREDDY DG_23010_SQC_AGEX_TM NC_FREDDY_URGENCE / Sél Component 1: Building a s Consultant Qual ection de partenaires (AGE Pending Imple 2023-03-1 2023-03- 2023-03- 2023-04- 2023-04- 2023-06- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 37,000.00 0.00 X) chargés des ciblage, sup mentation 7 24 31 07 14 13 lected rural areas on ervision de paiement et MA CC des bénéficiaires du TM NC post Freddy DG_23015_SQC_AGEC_FSU Component 1: Building a s Consultant Qual / Sélection de partenaires ( Pending Imple 2023-04-0 2023-04- 2023-05- 2023-06- 2023-07- 2024-10- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 36,000.00 0.00 AGEC) chargés de l'encadr mentation 1 15 13 10 01 31 lected rural areas on ement des bénéficiaires du programme FSU DRK_23005_SQC_AGEX_ C OL_DON_TMDH_FA3 / Recru Component 1: Building a s Consultant Qual tement des agences d’exéc Under Impleme 2023-03-3 2023-05- 2023-04- 2023-05- 2023-05- 2023-06- 2023-07- 2023-12- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 22,000.00 0.00 ution chargés de la collecte ntation 0 05 20 13 19 03 02 29 lected rural areas on de données auprès des mé nages bénéficiaires TMDH_ FSS FA3 répartie en deux ( 02) lots DG_23014_SFQC_AGEC_T Component 1: Building a s Quality And Cos MDH / Sélection de partena Pending Imple 2023-05-1 2023-06- 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11- IDA / D7740 afety net for the poor in se Post t-Based Selectio Open - National 600,000.00 0.00 ires (AGEC) chargés de l'en mentation 8 08 20 17 14 19 16 15 lected rural areas n cadrement des bénéficiaire s du programme TMDH DG_23023_SQC_CABINET_ Component 1: Building a s Consultant Qual PGI / Recrutement d'un cab Pending Imple 2023-05-2 2023-06- 2023-07- 2023-08- 2023-08- 2023-12- IDA / D7740 afety net for the poor in se Post ification Selecti Open - National 10,000.00 0.00 inet chargé du développem mentation 6 02 07 04 25 31 lected rural areas on ent du Progiciel de Gestion Intégré (PGI) du FID INDIVIDUAL CONSULTANTS Activity Reference No Invitation to Identif Loan / Credit Market Appro Contract Type Estimated A Actual Amo Process Stat Draft Negotiated C Contract Completio . / Description Component Review Type Method Terms of Reference ied/Selected Consu Signed Contract No. ach mount (US$) unt (US$) us ontract n ltant Planned Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d DRU12CICMP17001 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-06- 2017-05- 2017-06- 2017-05- 2017-06- 2017-06- 2017-11- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 754.72 558.23 Completed ultant Selection 1 08 03 20 09 28 15 30 29 16 nt bénéficiaires TMDH Beti lected rural areas oky CI1 DRF12CICMP17001 / COMP Component 1: Building a s Individual Cons 2017-04-1 2017-05- 2017-05- 2017-05- 2017-05- 2017-06- 2017-05- 2017-07- 2017-06- 2017-11- LEMENTATION ENREGISTRE IDA / 57080 afety net for the poor in se Post Limited 968.56 576.99 Completed ultant Selection 1 02 03 31 09 23 15 04 29 30 MENT BENEFICIAIRES TMD lected rural areas H AMBOHIMAHASOA DRT12CICMP17001 / Comp Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2017-06- 2017-12- lémentation enregistremen IDA / 57080 afety net for the poor in se Post Limited 782.16 787.85 Completed ultant Selection 1 10 03 09 12 15 12 29 22 t bénéficiaires TMDH du Dis lected rural areas trict de Faratsiho DRA12CICMP17001 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 645.76 576.60 Completed ultant Selection 1 11 03 28 09 23 15 07 29 14 nt béneficiaire TMDH TOAM lected rural areas ASINAII et MAHANORO DRK12CICMP17001 / COM Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-06- 2017-05- 2017-06- 2017-05- 2017-07- 2017-06- 2017-08- PLEMENT ENREGISTREMEN IDA / 57080 afety net for the poor in se Post Limited 1,016.04 1,418.36 Completed ultant Selection 1 11 03 29 09 30 15 01 29 01 T TMDH VOHIPENO lected rural areas DRA12CICMP17002 / comp Component 1: Building a s lémentation enregistremen Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- IDA / 57080 afety net for the poor in se Post Limited 645.76 610.62 Completed t béneficiaires TMDH TOAM ultant Selection 1 10 03 28 09 23 15 07 29 14 lected rural areas ASINA II et MAHANORO DRF12CICMP17002 / COMP Component 1: Building a s Individual Cons 2017-04-1 2017-05- 2017-05- 2017-07- 2017-05- 2017-07- 2017-05- 2017-07- 2017-06- 2017-11- LEMENTATION ENREGISTRE IDA / 57080 afety net for the poor in se Post Limited 968.56 467.35 Completed ultant Selection 1 02 03 01 09 03 15 04 29 30 MENT BENEFICIAIRES TMD lected rural areas H AMBOHIMAHASOA DRT12CICMP17002 / Comp Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2017-06- 2017-07- lémentation enregistremen IDA / 57080 afety net for the poor in se Post Limited 782.16 748.17 Completed ultant Selection 1 10 03 09 12 15 12 29 04 t bénéficiaires TMDH du Dis lected rural areas trict de Faratsiho DRF12CICMP17003 / COMP Component 1: Building a s Individual Cons 2017-04-1 2017-05- 2017-05- 2017-05- 2017-05- 2017-06- 2017-05- 2017-07- 2017-06- 2017-11- LEMENTATION ENREGISTRE IDA / 57080 afety net for the poor in se Post Limited 968.56 464.25 Completed ultant Selection 1 02 03 31 09 23 15 04 29 26 MENT BENEFICIAIRES TMD lected rural areas H AMBOHIMAHASOA DRK12CICMP17002 / COM Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-06- 2017-05- 2017-06- 2017-05- 2017-07- 2017-06- 2017-08- PLEMENTATION ENREGISTR IDA / 57080 afety net for the poor in se Post Limited 1,016.04 776.19 Completed ultant Selection 1 11 03 29 09 30 15 01 29 01 EMENT TMDH VOHIPENO lected rural areas DRA12CICMP17003 / comp Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- lémentation enregistremen IDA / 57080 afety net for the poor in se Post Limited 645.76 583.03 Completed ultant Selection 1 10 03 28 09 23 15 07 29 14 t béneficiaires TMDH Toam lected rural areas asina II et Mahanoro DRA12CICMP17004 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 645.76 733.54 Completed ultant Selection 1 10 03 28 09 23 15 07 29 14 nt béneficiaire TMDH Toam lected rural areas asinaII et Mahanoro DRU12CICMP17002 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-06- 2017-05- 2017-06- 2017-05- 2017-06- 2017-06- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 754.72 565.12 Terminated ultant Selection 1 08 03 20 09 28 15 30 29 nt bénéficiaires TMDH Beti lected rural areas oky CI2 DRA12CICMP17005 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 645.76 648.44 Completed ultant Selection 1 10 03 28 09 23 15 07 29 14 nt béneficiaires TMDH Toa lected rural areas masinaII et Mahanoto DRU12CICMP17004 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-06- 2017-05- 2017-06- 2017-05- 2017-07- 2017-06- 2017-11- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 754.72 1,067.83 Completed ultant Selection 1 08 03 19 09 28 15 03 29 28 nt bénéficiaires TMDH Beti lected rural areas oky CI4 DRA12CICMP17006 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 645.76 644.57 Completed ultant Selection 1 10 03 28 09 23 15 07 29 14 nt béneficiaire TMDH Toam lected rural areas asina II et Mahanoro DRU12CICMP17005 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-06- 2017-05- 2017-06- 2017-05- 2017-07- 2017-06- 2017-11- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 754.72 579.33 Completed ultant Selection 1 08 03 20 09 28 15 03 29 27 nt bénéficiaires TMDH Beti lected rural areas oky CI5 DRA12CICMP17007 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 645.76 666.63 Completed ultant Selection 1 10 03 28 09 23 15 07 29 14 nt bénéficiaire TMDH Toam lected rural areas asina II et Mahanoro DRU12CICMP17003 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-06- 2017-05- 2017-06- 2017-05- 2017-07- 2017-06- 2017-11- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 754.12 757.08 Completed ultant Selection 1 08 03 19 09 28 15 03 29 28 nt bénéficiaires TMDH Beti lected rural areas oky CI3 DRA12CICMP17008 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 645.76 661.09 Completed ultant Selection 1 10 03 28 09 23 15 07 29 14 nt bénéficiaire TMDH Toam lected rural areas asina II et Mahanoro DRA12CICMP17009 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 645.76 642.20 Completed ultant Selection 1 10 03 28 09 23 15 07 29 14 nt bénéficiaire TMDH Toam lected rural areas asina II et Mahanoro DRA12CICMP17010 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 645.76 673.07 Completed ultant Selection 1 10 03 27 09 23 15 07 29 14 nt bénéficiaire TMDH Toam lected rural areas asina II et Mahanoro DRA12CICMP17011 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 645.76 514.63 Completed ultant Selection 1 10 03 28 09 23 15 07 29 14 nt bénéficiaire TMDH Toam lected rural areas asina II et Mahanoro DRA12CICMP17012 / Com Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-04- 2017-05- 2017-05- 2017-05- 2017-06- 2017-06- 2017-09- plémentation enregistreme IDA / 57080 afety net for the poor in se Post Limited 645.76 597.96 Completed ultant Selection 1 10 03 27 09 23 15 07 29 14 nt bénéficiaire TMDH Toam lected rural areas asina II et Mahanoro DRK12CICMP17003 / COM Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-06- 2017-05- 2020-06- 2017-05- 2017-07- 2017-06- 2017-08- PLEMENTATION DES BENEF IDA / 57080 afety net for the poor in se Post Limited 1,016.04 1,727.02 Completed ultant Selection 1 11 03 29 09 30 15 01 29 01 ICIAIRES TMDH VOHIPENO lected rural areas DRK12CICMP17004 / COM Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-06- 2017-05- 2017-06- 2017-05- 2017-07- 2017-06- 2017-08- PLEMENTATION ENREGISTR IDA / 57080 afety net for the poor in se Post Limited 1,016.04 446.31 Completed ultant Selection 1 11 03 29 09 30 15 01 29 01 EMENT TMDH VOHIPENO lected rural areas DRT12CICMP17003 / Comp Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2017-06- 2018-01- lémentation enregistremen IDA / 57080 afety net for the poor in se Post Limited 782.16 762.67 Completed ultant Selection 1 10 03 09 12 15 12 29 09 t bénéficiaires TMDH du Dis lected rural areas trict de Faratsiho DRT12CICMP17004 / Comp Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2017-06- 2017-11- lémentation enregistremen IDA / 57080 afety net for the poor in se Post Limited 782.16 773.52 Completed ultant Selection 1 10 03 09 12 15 12 29 07 t bénéficiaires TMDH du Dis lected rural areas trict de Faratsiho DRT12CICMP17005 / Comp Component 1: Building a s Individual Cons 2017-04-1 2017-04- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2017-06- 2018-01- lémentation enregistremen IDA / 57080 afety net for the poor in se Post Limited 782.16 751.44 Completed ultant Selection 1 10 03 09 12 15 12 29 04 t bénéficiaires TMDH du Dis lected rural areas trict de Faratsiho DRF12CISAI17001 / SAISIE Component 1: Building a s SUR BASE DE DONNÉES LE Individual Cons 2017-04-1 2017-05- 2017-04- 2017-06- 2017-05- 2017-06- 2017-05- 2017-06- 2017-12- 2018-01- IDA / 57080 afety net for the poor in se Post Limited 218.75 1,366.22 Completed S INFORMATIONS SUR LES ultant Selection 8 09 20 15 18 16 24 21 31 16 lected rural areas MÉNAGES BENEFICIAIRES E N TMDH DRF12CISAI17002 / SAISIE Component 1: Building a s DANS LA BASE DE DONNÉE Individual Cons 2017-04-1 2017-05- 2017-04- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2017-12- 2018-01- IDA / 57080 afety net for the poor in se Post Limited 218.75 1,365.16 Completed S LES INFORMATIONS CON ultant Selection 8 15 20 30 18 16 24 21 31 16 lected rural areas CERNANT LES MÉNAGES BÉ NÉFICIAIRES TMDH DRF12CISAI17003 / SAISIE Component 1: Building a s DANS LA BASE DE DONNÉE Individual Cons 2017-04-1 2017-05- 2017-04- 2017-06- 2017-05- 2017-06- 2017-05- 2017-06- 2017-12- 2018-01- IDA / 57080 afety net for the poor in se Post Limited 218.75 1,370.21 Completed S LES INFORMATIONS CON ultant Selection 8 09 20 15 18 16 24 21 31 16 lected rural areas CERNANT LES MÉNAGES BÉ NÉFICIAIRES TMDH DRF11CISAI17001 / SAISIE Component 1: Building a s DANS LA BASE DE DONNÉE Individual Cons 2017-04-1 2017-05- 2017-04- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2017-12- 2018-01- IDA / 57080 afety net for the poor in se Post Limited 218.75 1,353.05 Completed S LES INFORMATIONS CON ultant Selection 8 15 20 30 18 16 24 21 31 16 lected rural areas CERNANT LES MÉNAGES BÉ NÉFICIAIRES ACTP DRF11CISAI17002 / SAISIE Component 1: Building a s DANS LA BASE DE DONNÉE Individual Cons 2017-04-1 2017-05- 2017-04- 2017-05- 2017-05- 2017-06- 2017-05- 2017-06- 2017-12- 2018-12- IDA / 57080 afety net for the poor in se Post Limited 218.75 3,089.48 Completed S LES INFORMATIONS CON ultant Selection 8 09 20 30 18 16 24 21 31 15 lected rural areas CERNANT LES MÉNAGES BÉ NÉFICIAIRES ACTP DRF11CISAI17003 / SAISIE Component 1: Building a s DANS LA BASE DE DONNÉE Individual Cons 2017-04-1 2017-05- 2017-04- 2017-06- 2017-05- 2017-06- 2017-05- 2017-06- 2017-12- 2018-01- IDA / 57080 afety net for the poor in se Post Limited 218.75 216.35 Completed S LES INFORMATIONS CON ultant Selection 8 09 20 15 18 16 24 21 31 16 lected rural areas CERNANT LES MÉNAGES BÉ NÉFICIAIRES ACTP DRK12CISAI17001 / SAISIE DANS LA BASE DE DONNÉE Component 1: Building a s Individual Cons Under Impleme 2017-04-2 2019-01- 2017-05- 2019-01- 2017-05- 2017-06- 2017-12- S LES INFORMATIONS CON IDA / 57080 afety net for the poor in se Post Limited 2,250.00 0.00 ultant Selection ntation 5 10 17 15 27 05 31 CERNANT LES MÉNAGES BÉ lected rural areas NÉFICIAIRES TMDH VOHIPE NO DIRK12CISAI17002 / SAISI E DANS LA BASE DE DONN Component 1: Building a s Individual Cons Under Impleme 2017-04-2 2017-05- 2017-05- 2017-06- 2017-06- ÉES LES INFORMATIONS CO IDA / 57080 afety net for the poor in se Post Limited 2,250.00 0.00 ultant Selection ntation 5 17 27 05 25 NCERNANT LES MÉNAGES lected rural areas BÉNÉFICIAIRES TMDH VOHI PENO DIRK11CISAI17001 / SAISI E DANS LA BASE DE DONN Component 1: Building a s Individual Cons 2017-04-2 2017-04- 2017-05- 2017-06- 2017-05- 2017-06- 2017-06- 2017-06- 2017-12- 2018-12- ÉES LES INFORMATIONS CO IDA / 57080 afety net for the poor in se Post Limited 2,250.00 1,009.32 Completed ultant Selection 5 25 17 20 27 22 05 23 31 22 NCERNANT LES MÉNAGES lected rural areas BÉNÉFICIAIRES ACTP MANA KARA DIRK11CISAI17002 / SAISI E DANS LA BASE DE DONN Component 1: Building a s Individual Cons 2017-04-2 2017-04- 2017-05- 2017-06- 2017-05- 2017-06- 2017-06- 2017-06- 2017-12- 2018-12- ÉES DES INFORMATIONS C IDA / 57080 afety net for the poor in se Post Limited 2,250.00 1,164.60 Completed ultant Selection 5 25 17 20 27 22 05 23 31 22 ONCERNANT LES MÉNAGES lected rural areas BÉNÉFICIAIRES ACTP MANA KARA DRA12CISAI17001 / Saisie Component 1: Building a s des Registres de corespons Individual Cons 2017-04-2 2017-04- 2017-05- 2017-05- 2017-10- 2017-06- 2017-10- 2018-01- IDA / 57080 afety net for the poor in se Post Limited 1,166.67 416.99 Signed abilité et Mise à jour des do ultant Selection 8 26 20 26 10 01 10 01 lected rural areas nnées des ménages bénéfi ciaires sur MIS TMDH. DRA12CISAI17002 / Saisie Component 1: Building a s des registres de corespons Individual Cons 2017-04-2 2017-04- 2017-05- 2017-10- 2017-05- 2017-10- 2017-06- 2017-10- 2017-12- IDA / 57080 afety net for the poor in se Post Limited 1,166.67 416.99 Signed abilité et mise à jour des d ultant Selection 8 26 20 09 26 10 01 10 31 lected rural areas onnées des ménages bénéf iciaires sur MIS TMDH. DRA12CISAI17003 / Saisie Component 1: Building a s des registres de corespons Individual Cons 2017-04-2 2017-04- 2017-05- 2017-10- 2017-05- 2017-10- 2017-06- 2017-10- 2017-12- IDA / 57080 afety net for the poor in se Post Limited 1,166.67 416.99 Signed abilité et mise à jour des d ultant Selection 8 26 20 09 26 10 01 10 31 lected rural areas onnées des ménages bénéf iciaires sur MIS TMDH. DRA12CISAI17004 / Saisie Component 1: Building a s des registres de corespons Individual Cons 2017-04-2 2017-04- 2017-05- 2017-10- 2017-05- 2017-10- 2017-06- 2017-10- 2017-12- IDA / 57080 afety net for the poor in se Post Limited 1,166.67 416.99 Signed abilité et mise à jour des d ultant Selection 8 26 20 09 26 10 01 10 31 lected rural areas onnées des ménages bénéf iciaires sur MIS TMDH. DRA12CISAI17005 / Saisie Component 1: Building a s des registres de corespons Individual Cons 2017-04-2 2017-04- 2017-05- 2017-10- 2017-05- 2017-10- 2017-06- 2017-10- 2017-12- IDA / 57080 afety net for the poor in se Post Limited 1,166.67 416.99 Signed abilité et mise à jour des d ultant Selection 8 26 20 09 26 10 01 10 31 lected rural areas onnées des ménages bénéf iciaires sur MIS TMDH. DRA12CISAI17006 / Saisie Component 1: Building a s des registres de corespons Individual Cons 2017-04-2 2017-04- 2017-05- 2017-10- 2017-05- 2017-10- 2017-06- 2017-10- 2017-12- IDA / 57080 afety net for the poor in se Post Limited 1,166.67 416.99 Signed abilité et mise à jour des d ultant Selection 8 26 20 09 26 10 01 10 31 lected rural areas onnées des ménages bénéf iciaires sur MIS TMDH. DRA12CISAI17007 / Saisie Component 1: Building a s des registres de corespons Individual Cons 2017-04-2 2017-04- 2017-05- 2017-10- 2017-05- 2017-10- 2017-06- 2017-10- 2017-12- IDA / 57080 afety net for the poor in se Post Limited 1,166.67 416.99 Signed abilité et mise à jour des d ultant Selection 8 26 20 09 26 10 01 10 31 lected rural areas onnées des ménages bénéf iciaires sur MIS TMDH. DRT11CISAI17001 / Opérat Component 1: Building a s Individual Cons 2017-04-2 2017-04- 2017-05- 2017-05- 2017-08- 2017-06- 2017-08- 2019-05- eur de saisie : saisie des fic IDA / 57080 afety net for the poor in se Post Limited 2,250.00 1,389.96 Terminated ultant Selection 7 26 19 30 07 04 23 31 hes de présence et traitem lected rural areas ent sur MIS DRT11CISAI17002 / Opérat Component 1: Building a s Individual Cons 2017-04-2 2017-04- 2017-05- 2017-05- 2017-08- 2017-06- 2017-08- 2019-05- 2019-09- eur de saisie : saisie des fic IDA / 57080 afety net for the poor in se Post Limited 2,250.00 2,153.63 Completed ultant Selection 7 26 19 30 11 04 23 31 23 hes de présence et traitem lected rural areas ent sur MIS DRT11CISAI17003 / Opérat Component 1: Building a s Individual Cons 2017-04-2 2017-04- 2017-05- 2017-05- 2017-08- 2017-06- 2017-08- 2019-05- 2019-09- eur de saisie : saisie des fic IDA / 57080 afety net for the poor in se Post Limited 2,250.00 3,516.25 Completed ultant Selection 7 26 19 30 07 04 23 31 24 hes de présence et traitem lected rural areas ent sur MIS DRT11CISAI17004 / Opérat Component 1: Building a s Individual Cons 2017-04-2 2017-04- 2017-05- 2017-05- 2017-08- 2017-06- 2017-08- 2019-05- eur de saisie : saisie des fic IDA / 57080 afety net for the poor in se Post Limited 2,250.00 622.96 Terminated ultant Selection 7 26 19 30 07 04 23 31 hes de présence et traitem lected rural areas ent sur MIS DRT11CISAI17005 / Opérat Component 1: Building a s Individual Cons 2017-04-2 2017-04- 2017-05- 2017-05- 2017-08- 2017-06- 2017-08- 2019-05- eur de saisie : saisie des fic IDA / 57080 afety net for the poor in se Post Limited 2,250.00 622.96 Terminated ultant Selection 7 26 19 30 10 04 23 31 hes de présence et traitem lected rural areas ent sur MIS DRT11CISAI17006 / Opérat Component 1: Building a s Individual Cons 2017-04-2 2017-04- 2017-05- 2017-05- 2017-08- 2017-06- 2017-08- 2019-05- 2019-09- eur de saisie : saisie des fic IDA / 57080 afety net for the poor in se Post Limited 2,250.00 4,030.30 Completed ultant Selection 7 26 19 30 14 04 23 31 24 hes de présence et traitem lected rural areas ent sur MIS DRU12CISAI001 / saisie de Component 1: Building a s Individual Cons 2017-05-3 2017-06- 2017-06- 2017-06- 2017-06- 2017-07- 2017-08- 2017-07- 2018-01- 2019-10- s enregistrement TMDH op IDA / 57080 afety net for the poor in se Post Limited 900.00 184.90 Completed ultant Selection 1 08 05 23 27 06 01 10 28 30 érateur de saisie lected rural areas DRU12CISAI17002 / SAISIE Component 1: Building a s Individual Cons 2017-05-3 2017-06- 2017-06- 2017-06- 2017-06- 2017-06- 2017-08- 2017-07- 2018-01- 2019-10- DES ENREGISTREMENTS T IDA / 57080 afety net for the poor in se Post Limited 900.00 184.90 Completed ultant Selection 1 09 05 23 27 23 01 07 28 30 MDH OPERATEUR DE SAISI lected rural areas E DRU12CISAI17003 / Saisie Component 1: Building a s Individual Cons 2017-05-3 2017-06- 2017-06- 2017-06- 2017-06- 2017-07- 2017-08- 2017-07- 2018-01- 2019-10- des enregistrements TMDH IDA / 57080 afety net for the poor in se Post Limited 900.00 185.18 Completed ultant Selection 1 08 05 23 27 06 01 07 28 30 opérateur de saisie lected rural areas Page 15 DRU12CISAI17004 / Saisie Component 1: Building a s Individual Cons 2017-05-3 2017-06- 2017-06- 2017-07- 2017-06- 2017-07- 2017-08- 2017-08- 2018-01- 2019-10- des enregistrements TMDH IDA / 57080 afety net for the poor in se Post Limited 900.00 185.18 Completed ultant Selection 1 09 05 28 27 06 01 07 28 23 opérateur de saisie lected rural areas DRT11CFAGEC17001 / Pris Component 1: Building a s e de photos pour les cartes 2017-07-1 2017-07- 2017-09- 2017-10- IDA / 57080 afety net for the poor in se Post Direct Selection Direct 2,125.40 0.00 Canceled des récepteurs et enregistr 8 26 01 01 lected rural areas ement en vue de la complé mentation des bénéficiaire s DRT11CFAGEC17002 / Pris e de photos pour les cartes Component 1: Building a s 2017-07-1 2017-07- 2017-09- 2017-10- des récepteurs et enregistr IDA / 57080 afety net for the poor in se Post Direct Selection Direct 728.23 0.00 Canceled 8 26 01 01 ement en vue de la complé lected rural areas mentation des bénéficiaire s (avenant au contrat) DRT11CFAGEC17003 / Pris e de photos pour les cartes Component 1: Building a s 2017-07-1 2017-07- 2017-09- 2017-10- des récepteurs et enregistr IDA / 57080 afety net for the poor in se Post Direct Selection Direct 1,035.89 0.00 Canceled 8 26 01 01 ement en vue de la complé lected rural areas mentation des bénéficiaire s (avenant au contrat) DRT11CFAGEC17004 / Pris e de photos pour les cartes Component 1: Building a s 2017-07-1 2017-07- 2017-09- 2017-10- des récepteurs et enregistr IDA / 57080 afety net for the poor in se Post Direct Selection Direct 861.45 0.00 Canceled 8 26 01 01 ement en vue de la complé lected rural areas mentation des bénéficiaire s (avenant au contrat) DRT11CFAGEC17005 / Pris e de photos pour les cartes Component 1: Building a s 2017-07-1 2017-07- 2017-09- 2017-10- des récepteurs et enregistr IDA / 57080 afety net for the poor in se Post Direct Selection Direct 528.39 0.00 Canceled 8 26 01 01 ement en vue de la complé lected rural areas mentation des bénéficiaire s (avenant au contrat) DRT11CFAGEC17006 / Pris e de photos pour les cartes Component 1: Building a s 2017-07-1 2017-07- 2017-09- 2017-10- des récepteurs et enregistr IDA / 57080 afety net for the poor in se Post Direct Selection Direct 825.89 0.00 Canceled 8 26 01 01 ement en vue de la complé lected rural areas mentation des bénéficiaire s (avenant au contrat) DRT11CFAGEC17007 / Pris e de photos pour les cartes Component 1: Building a s 2017-07-1 2017-07- 2017-09- 2017-10- des récepteurs et enregistr IDA / 57080 afety net for the poor in se Post Direct Selection Direct 1,862.34 0.00 Canceled 8 26 01 01 ement en vue de la complé lected rural areas mentation des bénéficiaire s (avenant au contrat) DRT11CFAGEC17008 / Pris e de photos pour les cartes Component 1: Building a s 2017-07-1 2017-07- 2017-09- 2017-10- des récepteurs et enregistr IDA / 57080 afety net for the poor in se Post Direct Selection Direct 872.18 0.00 Canceled 8 26 01 01 ement en vue de la complé lected rural areas mentation des bénéficiaire s (avenant au contrat) DRT11CFAGEC17009 / Pris e de photos pour les cartes Component 1: Building a s 2017-07-1 2017-07- 2017-09- 2017-10- des récepteurs et enregistr IDA / 57080 afety net for the poor in se Post Direct Selection Direct 1,067.50 0.00 Canceled 8 26 01 01 ement en vue de la complé lected rural areas mentation des bénéficiaire s (avenant au contrat) DRT12CISAI17001 / Opérat Component 1: Building a s eur de saisie : chargé de la Individual Cons 2017-07-1 2017-04- 2017-07- 2017-08- 2017-11- 2017-08- 2017-11- 2019-11- 2019-09- IDA / 57080 afety net for the poor in se Post Limited 3,483.87 5,275.68 Completed saisie des données du TMD ultant Selection 8 26 28 22 02 25 06 23 20 lected rural areas H sur MIS (coresponsabilité s, mise à jour) DRT12CISAI17002 / Opérat Component 1: Building a s eur de saisie : chargé de la Individual Cons 2017-07-1 2017-04- 2017-07- 2017-08- 2017-11- 2017-08- 2017-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 3,483.87 1,838.22 Terminated saisie des données du TMD ultant Selection 8 26 28 22 02 25 06 23 lected rural areas H sur MIS (coresponsabilité s, mise à jour) DRT12CISAI17003 / Opérat Component 1: Building a s eur de saisie : chargé de la Individual Cons 2017-07-1 2017-04- 2017-07- 2017-08- 2017-11- 2017-08- 2017-11- 2019-11- 2019-09- IDA / 57080 afety net for the poor in se Post Limited 3,483.87 5,076.09 Completed saisie des données du TMD ultant Selection 8 26 28 22 02 25 06 23 20 lected rural areas H sur MIS (coresponsabilité s, mise à jour) DRT12CISAI17004 / Opérat Component 1: Building a s eur de saisie : chargé de la Individual Cons 2017-07-1 2017-04- 2017-07- 2017-08- 2017-11- 2017-08- 2017-11- 2019-11- 2019-09- IDA / 57080 afety net for the poor in se Post Limited 3,483.87 4,226.01 Completed saisie des données du TMD ultant Selection 8 26 28 22 02 25 06 23 20 lected rural areas H sur MIS (coresponsabilité s, mise à jour) DRT12CISAI17005 / Opérat Component 1: Building a s eur de saisie : chargé de la Individual Cons 2017-07-1 2017-04- 2017-07- 2017-08- 2017-11- 2017-08- 2017-11- 2019-11- 2019-09- IDA / 57080 afety net for the poor in se Post Limited 3,483.87 5,275.68 Completed saisie des données du TMD ultant Selection 8 26 28 22 02 25 06 23 20 lected rural areas H sur MIS (coresponsabilité s, mise à jour) DRT12CISAI17006 / Opérat Component 1: Building a s eur de saisie : chargé de la Individual Cons 2017-07-1 2017-04- 2017-07- 2017-08- 2017-11- 2017-08- 2017-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 3,483.87 1,906.13 Terminated saisie des données du TMD ultant Selection 8 26 28 22 02 25 06 23 lected rural areas H sur MIS (coresponsabilité s, mise à jour) Component 1: Building a s DRP81CISAI17001 / CI OPE Individual Cons 2017-07-2 2017-04- 2017-08- 2017-10- 2017-08- 2017-10- 2017-08- 2017-10- 2018-02- IDA / 57080 afety net for the poor in se Post Limited 1,600.00 1,373.00 Signed RATEUR DE SAISIE SUD 1 ultant Selection 1 27 06 16 14 16 17 17 13 lected rural areas Component 1: Building a s DRP81CISAI17002 / CI OPE Individual Cons 2017-07-2 2017-04- 2017-08- 2017-12- 2017-08- 2017-12- 2017-08- 2017-12- 2018-02- IDA / 57080 afety net for the poor in se Post Limited 1,600.00 1,373.00 Signed RATEUR DE SAISIE SUD 2 ultant Selection 1 27 06 07 14 07 17 08 13 lected rural areas Component 1: Building a s DRP81CISAI17003 / CI OPE Individual Cons 2017-07-2 2017-04- 2017-08- 2017-10- 2017-08- 2017-10- 2017-08- 2017-10- 2018-02- IDA / 57080 afety net for the poor in se Post Limited 1,600.00 1,373.00 Signed RATEUR DE SAISIE SUD 3 ultant Selection 1 27 06 16 14 16 17 17 13 lected rural areas Component 1: Building a s DRP81CISAI17004 / CI OPE Individual Cons 2017-07-2 2017-04- 2017-08- 2017-10- 2017-08- 2017-10- 2017-08- 2017-10- 2018-02- IDA / 57080 afety net for the poor in se Post Limited 1,600.00 1,373.00 Signed RATEUR DE SAISIE SUD 4 ultant Selection 1 27 06 16 14 16 17 17 13 lected rural areas Component 1: Building a s DRP81CISAI17005 / CI OPE Individual Cons 2017-07-2 2017-04- 2017-08- 2017-10- 2017-08- 2017-10- 2017-08- 2017-10- 2018-02- IDA / 57080 afety net for the poor in se Post Limited 1,600.00 1,373.00 Signed RATEUR DE SAISIE SUD 5 ultant Selection 1 27 06 16 14 23 17 17 13 lected rural areas DRT12CICIB1701 / Consult Component 1: Building a s ant Individuel Socio-organis Individual Cons 2017-11-1 2017-11- 2017-11- 2017-12- 2018-01- 2017-12- 2018-01- 2018-02- 2018-07- IDA / 57080 afety net for the poor in se Post Limited 2,258.06 2,169.33 Completed ateur chargé de l'enregistr ultant Selection 4 16 22 13 16 18 16 06 02 lected rural areas ement des bénéficiaires DRT12CICIB1702 / Consult Component 1: Building a s ant Individuel Socio-organis Individual Cons 2017-11-1 2017-11- 2017-11- 2017-12- 2018-01- 2017-12- 2018-01- 2018-02- 2018-07- IDA / 57080 afety net for the poor in se Post Limited 2,258.06 2,174.85 Completed ateur chargé de l'enregistr ultant Selection 4 16 22 13 16 18 16 06 02 lected rural areas ement des bénéficiaires DRT12CICIB1703 / Consult Component 1: Building a s ant Individuel Socio-organis Individual Cons 2017-11-1 2017-11- 2017-11- 2017-12- 2018-01- 2017-12- 2018-01- 2018-02- 2018-07- IDA / 57080 afety net for the poor in se Post Limited 2,258.06 2,069.77 Completed ateur chargé de l'enregistr ultant Selection 4 16 22 13 16 18 16 06 02 lected rural areas ement des bénéficiaires DRK12CIACC17001 / ACCO Component 1: Building a s Individual Cons 2017-11-2 2017-09- 2017-12- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-12- 2018-11- MPAGNATEUR SPÉCIALISE IDA / 57080 afety net for the poor in se Post Open 5,806.45 4,688.91 Completed ultant Selection 2 01 09 03 10 13 12 24 12 24 MANAKARA lected rural areas DRK12CIACC17002 / ACCO Component 1: Building a s Individual Cons 2017-11-2 2017-09- 2017-12- 2017-09- 2017-12- 2017-09- 2017-12- 2017-09- 2018-12- 2017-11- MPAGNATEUR SPÉCIALISE IDA / 57080 afety net for the poor in se Post Open 5,806.45 754.33 Completed ultant Selection 2 01 09 25 10 26 12 26 12 28 MANAKARA lected rural areas DRK12CIACC17003 / ACCO Component 1: Building a s Individual Cons 2017-11-2 2017-09- 2017-12- 2017-11- 2017-12- 2017-11- 2017-12- 2017-11- 2018-12- 2018-11- MPAGNATEUR SPÉCIALISE IDA / 57080 afety net for the poor in se Post Open 5,806.45 4,911.34 Completed ultant Selection 2 22 09 03 10 13 12 24 12 24 MANAKARA lected rural areas DRK12CICMP17005 / CIBL Component 1: Building a s Individual Cons 2017-11-2 2017-11- 2017-12- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- AGE - ENQUÊTE - ENREGIST IDA / 57080 afety net for the poor in se Post Open 343.75 297.94 Completed ultant Selection 3 23 10 15 11 04 13 16 12 16 REMENT BÉNÉFICIAIRES M lected rural areas ANAKARA DRK12CICMP17006 / CIBL Component 1: Building a s Individual Cons 2017-11-2 2017-11- 2017-12- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-05- AGE - ENQUÊTE - ENREGIST IDA / 57080 afety net for the poor in se Post Open 196.88 988.87 Completed ultant Selection 3 23 10 12 11 04 13 16 12 31 REMENT MANAKARA lected rural areas DRK12CICMP17007 / CIBL Component 1: Building a s Individual Cons 2017-11-2 2017-11- 2017-12- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- AGE - ENQUÊTE - ENREGIST IDA / 57080 afety net for the poor in se Post Open 196.88 1,205.68 Completed ultant Selection 3 23 10 20 11 12 13 16 12 16 REMENT BÉNÉFICIAIRES MA lected rural areas NAKARA DRK12CICMP17008 / CIBL Component 1: Building a s Individual Cons 2017-11-2 2017-11- 2017-12- 2017-12- 2017-12- 2018-01- AGE - ENQUÊTE - ENREGIST IDA / 57080 afety net for the poor in se Post Open 196.88 0.00 Canceled ultant Selection 3 23 10 11 13 12 REMENT BÉNÉFICIAIRES MA lected rural areas NAKARA DRK12CICMP17009 / CIBL Component 1: Building a s Individual Cons 2017-11-2 2017-11- 2017-12- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- AGE - ENQUÊTE - ENREGIST IDA / 57080 afety net for the poor in se Post Open 196.88 960.92 Completed ultant Selection 3 23 10 15 11 04 13 16 12 16 REMENT BÉNÉFICIAIRES MA lected rural areas NAKARA DRK12CICMP17010 / CIBL Component 1: Building a s Individual Cons 2017-11-2 2017-11- 2017-12- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- AGE - ENQUÊTE - ENREGIST IDA / 57080 afety net for the poor in se Post Open 196.88 294.83 Completed ultant Selection 3 23 10 15 11 04 13 16 12 16 REMENT BÉNÉFICIAIRES MA lected rural areas NAKARA DRK12CICMP17011 / CIBL Component 1: Building a s Individual Cons 2017-11-2 2017-11- 2017-12- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- AGE - ENQUÊTE - ENREGIST IDA / 57080 afety net for the poor in se Post Open 196.88 742.04 Completed ultant Selection 3 23 10 15 11 04 13 16 12 16 REMENT BÉNÉFICIAIRES MA lected rural areas NAKARA DRK12CICMP17012 / CIBL Component 1: Building a s Individual Cons 2017-11-2 2017-11- 2017-12- 2017-12- 2017-12- 2018-01- AGE - ENQUÊTE - ENREGIST IDA / 57080 afety net for the poor in se Post Open 196.88 0.00 Canceled ultant Selection 3 23 10 11 13 12 REMENT BÉNÉFICIAIRES MA lected rural areas NAKARA DRK12CICMP17013 / CIBL Component 1: Building a s Individual Cons 2017-11-2 2017-11- 2017-12- 2018-01- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-03- AGE - ENQUÊTE - ENREGIST IDA / 57080 afety net for the poor in se Post Open 196.88 4,139.68 Completed ultant Selection 3 23 10 05 11 05 13 20 12 01 REMENT BÉNÉFICIAIRES MA lected rural areas NAKARA Component 1: Building a s DRU12CISAI17005 / opérat Individual Cons 2017-11-2 2017-12- 2017-12- 2018-01- 2019-01- IDA / 57080 afety net for the poor in se Post Open 900.00 0.00 Canceled eur de saisie novembre 01 ultant Selection 8 23 28 02 02 lected rural areas Component 1: Building a s DRU12CISAI17006 / opérat Individual Cons 2017-11-2 2017-12- 2017-12- 2018-01- 2018-01- IDA / 57080 afety net for the poor in se Post Open 900.00 0.00 Canceled eur de saisie novembre 02 ultant Selection 8 23 28 02 05 lected rural areas DRU12CICMP17006 / TMD Component 1: Building a s H CISO ciblage, enquête, e Individual Cons 2017-11-3 2017-04- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- IDA / 57080 afety net for the poor in se Post Open 210.00 508.43 Signed nregistrement bénéficiaires ultant Selection 0 10 20 07 07 18 10 10 17 lected rural areas nouvelles communes nove mbre 01 DRU12CICMP17007 / TMD Component 1: Building a s H CISO ciblage, enquête, e Individual Cons 2017-11-2 2017-04- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- IDA / 57080 afety net for the poor in se Post Open 210.00 586.15 Signed nregistrement bénéficiaires ultant Selection 9 10 19 07 06 18 09 10 16 lected rural areas nouvelles communes nove mbre 01 DRU12CICMP7008 / TMDH Component 1: Building a s CISO ciblage, enquête, enr Individual Cons 2017-11-2 2017-04- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- IDA / 57080 afety net for the poor in se Post Open 210.00 785.65 Signed egistrement bénéficiaires n ultant Selection 9 10 19 07 06 18 09 10 16 lected rural areas ouvelles communes novem be 01 DRU12CICMP17009 / TMD Component 1: Building a s H CISO ciblage, enquête, e Individual Cons 2017-11-2 2017-04- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- IDA / 57080 afety net for the poor in se Post Open 210.00 793.60 Signed nregistrement bénéficiaires ultant Selection 9 10 19 07 06 18 09 10 16 lected rural areas nouvelles communes nove mbre 01 DRU12CICMP17010 / TMD Component 1: Building a s H CISO ciblage, enquête, e Individual Cons 2017-11-2 2017-04- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- IDA / 57080 afety net for the poor in se Post Open 210.00 640.52 Signed nregistrement bénéficiaires ultant Selection 9 10 19 07 06 18 09 10 16 lected rural areas nouvelles communes nove mbre 01 DRU12CICMP17011 / TMD Component 1: Building a s H CISO ciblage, enquête, e Individual Cons 2017-11-2 2017-04- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- 2018-05- IDA / 57080 afety net for the poor in se Post Open 210.00 720.97 Completed nregistrement bénéficiaires ultant Selection 9 10 19 07 06 18 09 10 16 28 lected rural areas nouvelles communes nove mbre 01 DRU12CICMP17012 / TMD Component 1: Building a s H CISO ciblage, enquête, e Individual Cons 2017-11-2 2017-04- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- 2018-05- IDA / 57080 afety net for the poor in se Post Open 210.00 660.44 Completed nregistrement bénéficiaires ultant Selection 9 10 19 07 06 18 09 10 16 25 lected rural areas nouvelles communes nove mbre 01 DRU12CICMP17013 / TMD Component 1: Building a s H CISO ciblage, enquête, e Individual Cons 2017-11-2 2017-04- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- IDA / 57080 afety net for the poor in se Post Open 210.00 675.03 Signed nregistrement bénéficiaires ultant Selection 9 10 19 07 06 18 09 10 16 lected rural areas nouvelles communes nove mbre 01 DRU12CICMP17014 / TMD Component 1: Building a s H CISO ciblage, enquête, e Individual Cons 2017-11-2 2017-04- 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- IDA / 57080 afety net for the poor in se Post Open 210.00 673.26 Signed nregistrement bénéficiaires ultant Selection 9 10 19 05 06 09 09 10 16 lected rural areas nouvelles communes nove mbre 01 DRU12CICMP17015 / TMD Component 1: Building a s H CISO ciblage, enquête, e Individual Cons 2017-11-2 2017-04- 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- IDA / 57080 afety net for the poor in se Post Open 210.00 722.85 Signed nregistrement bénéficiaire ultant Selection 9 10 19 15 06 17 09 18 16 lected rural areas s nouvelles communes nov embre 01 DRU12CICMP17016 / TMD Component 1: Building a s H CISO ciblage, enquête, e Individual Cons 2017-11-2 2017-04- 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- IDA / 57080 afety net for the poor in se Post Open 210.00 845.13 Signed nregistrement bénéficiaires ultant Selection 9 10 19 15 06 17 09 18 16 lected rural areas nouvelles communes nove mbre 01 DRU12CICMP17017 / TMD Component 1: Building a s H CISO ciblage, enquête, e Individual Cons 2017-11-2 2017-04- 2017-12- 2018-01- 2018-01- 2018-01- 2018-01- 2018-01- 2018-02- IDA / 57080 afety net for the poor in se Post Open 210.00 740.81 Signed nregistrement bénéficiaires ultant Selection 9 10 19 15 06 17 09 18 16 lected rural areas nouvelles communes nove mbre 01 DRU12CICMP17018 / TMD Component 1: Building a s H CI Chef d'Equipe ciblage, Individual Cons 2017-11-2 2017-04- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- IDA / 57080 afety net for the poor in se Post Open 366.67 538.34 Terminated enquête, enregistrement b ultant Selection 9 10 19 07 06 18 09 10 16 lected rural areas énéficiaires nouvelles com munes novembre 01 DRU12CICMP17019 / TMD Component 1: Building a s H CI Chef d'Equipe ciblage, Individual Cons 2017-11-2 2017-04- 2017-12- 2017-12- 2018-01- 2017-12- 2018-01- 2018-01- 2018-02- 2018-06- IDA / 57080 afety net for the poor in se Post Open 366.67 1,275.09 Completed enquête, enregistrement b ultant Selection 9 10 19 07 06 18 09 10 16 11 lected rural areas énéficiaires nouvelles com munes novembre 01 DRU12CIACC17001 / TMD Component 1: Building a s Individual Cons 2017-11-2 2017-09- 2017-12- 2017-11- 2018-01- 2017-11- 2018-01- 2018-01- 2019-01- H Accompagnateur Spéciali IDA / 57080 afety net for the poor in se Post Open 7,000.00 6,069.11 Signed ultant Selection 9 20 19 07 06 16 09 03 09 sé nouvelles communes no lected rural areas vembre 01 DRU12CIACC17002 / TMD Component 1: Building a s Individual Cons 2017-12-1 2018-01- 2018-02- 2018-03- 2018-08- H CI Marché multiple nove IDA / 57080 afety net for the poor in se Post Open 2,600.00 0.00 Canceled ultant Selection 0 22 12 01 28 mbre 01 lected rural areas DRA12CIACC17002 / ACCO Component 1: Building a s Individual Cons 2017-11-2 2017-09- 2017-12- 2018-02- 2017-12- 2018-02- 2017-12- 2018-02- 2018-12- MPAGNATEUR SPECIALISE IDA / 57080 afety net for the poor in se Post Open 8,360.91 5,238.95 Signed ultant Selection 0 22 07 02 08 06 10 14 10 DISTRICT TOAMASINA II lected rural areas Component 1: Building a s DRA12CIACC18001 / ACCO Individual Cons 2018-01-1 2017-09- 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-12- IDA / 57080 afety net for the poor in se Post Open 8,360.91 5,053.55 Signed MPAGNATEUR SPECIALISE ultant Selection 7 20 01 02 03 14 06 14 31 lected rural areas DRT11CIANIM1801 / Consu Component 1: Building a s Individual Cons 2018-01-1 2018-02- 2018-02- 2018-02- 2018-12- ltant Individuel animateur IDA / 57080 afety net for the poor in se Post Open 3,735.48 0.00 Canceled ultant Selection 7 06 13 24 03 de l'ACTP ans les 18 UTB à lected rural areas Antanifotsy. DRT12CIACC1801 / Consul tant Individuel chargé du re nforcement de capacité de Component 1: Building a s Individual Cons 2018-02-2 2018-04- 2018-03- 2018-04- 2018-06- 2018-04- 2018-06- 2019-04- 2019-09- s Mères Leaders et des acc IDA / 57080 afety net for the poor in se Post Open 6,397.85 7,203.01 Completed ultant Selection 0 06 31 05 11 09 13 30 20 ompagnements des Espace lected rural areas s de bien-être du projet de Protection Sociale du FID ( Accompagnateur) BETAFO 1 DRT12CIACC1802 / Consul tant Individuel chargé du re nforcement de capacité de Component 1: Building a s Individual Cons 2018-02-2 2018-04- 2018-03- 2018-04- 2018-06- 2018-04- 2018-06- 2019-04- 2019-09- s Mères Leaders et des acc IDA / 57080 afety net for the poor in se Post Open 6,397.85 7,352.71 Completed ultant Selection 0 06 31 05 11 09 13 30 20 ompagnements des Espace lected rural areas s de bien-être du projet de Protection Sociale du FID ( Accompagnateur) BETAFO 2 DRT12CIACC1803 / Consul tant Individuel chargé du re nforcement de capacité de Component 1: Building a s Individual Cons 2018-02-2 2018-04- 2018-03- 2018-04- 2018-06- 2018-04- 2018-06- 2019-04- 2019-09- s Mères Leaders et des acc IDA / 57080 afety net for the poor in se Post Open 6,397.85 8,294.02 Completed ultant Selection 0 06 31 05 11 09 13 30 20 ompagnements des Espace lected rural areas s de bien-être du projet de Protection Sociale du FID ( Accompagnateur) BETAFO 3 DG20CFFTOM1808 / Form Component 2: Strengtheni 2018-02-0 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-02- 2018-03- ation des RSE en Logiciel T IDA / 57080 ng safety net administratio Post Direct Selection Direct 743.37 741.77 Completed 1 05 08 08 14 16 24 19 OMPORTAIL n, monitoring and social ac countability DG20CFLOGRH1812 / Con Component 2: Strengtheni 2018-01-3 2017-11- 2018-01- 2017-11- 2018-02- 2018-02- 2018-03- ception Logiciel pour la ges IDA / 57080 ng safety net administratio Post Direct Selection Direct 20,685.35 20,584.06 Signed 0 03 30 13 09 26 11 tion des Ressources Humai n, monitoring and social ac nes countability DRF12CIAS17001 / ACCOM Component 1: Building a s PAGNATEUR SPECIALISE PO Individual Cons 2018-01-3 2017-09- 2018-02- 2017-11- 2018-02- 2017-11- 2018-02- 2017-11- 2019-02- 2019-10- IDA / 57080 afety net for the poor in se Post Open 7,722.66 6,578.73 Completed UR : CU AMBOHIMAHASOA ultant Selection 0 20 12 08 14 07 19 15 14 14 lected rural areas - CR MORAFENO - CR BEFE TA Component 2: Strengtheni DG20CIFSQL1810 / Format Individual Cons 2018-05-1 2019-04- 2018-05- 2019-05- 2018-06- 2019-05- 2018-07- 2019-05- 2018-07- 2019-06- IDA / 57080 ng safety net administratio Post Limited 743.37 581.17 Completed ion des RSE en SQL ultant Selection 5 03 20 08 10 13 15 16 30 11 n, monitoring and social ac countability DRA12CIACC17001 / ACCO Component 1: Building a s Individual Cons 2017-11-2 2017-09- 2017-12- 2018-01- 2017-12- 2018-01- 2017-12- 2018-01- 2018-12- MPAGNATEUR SPÉCIALISE IDA / 57080 afety net for the poor in se Post Open 8,360.91 5,275.89 Terminated ultant Selection 0 20 07 15 08 17 10 26 10 DISTRICT MAHANORO lected rural areas DRT12CICIB1704 / Consult Component 1: Building a s ant individuel Socio-organis Individual Cons 2018-03-1 2017-11- 2018-03- 2018-03- 2018-01- 2018-04- 2018-01- 2018-05- 2018-07- IDA / 57080 afety net for the poor in se Post Limited 2,258.06 2,187.89 Completed ateur chargé de l'enregistr ultant Selection 4 16 14 30 15 02 16 22 02 lected rural areas ement des bénéficiaires DRT12CICIB1705 / Consult Component 1: Building a s ant individuel Socio-organis Individual Cons 2018-03-1 2017-11- 2018-03- 2018-03- 2018-01- 2018-04- 2018-01- 2018-05- 2018-07- IDA / 57080 afety net for the poor in se Post Limited 2,258.06 1,934.14 Completed ateur chargé de l'enregistr ultant Selection 4 16 14 30 15 02 16 22 02 lected rural areas ement des bénéficiaires DRK11CISAI18001 / SAISI Component 1: Building a s DES DONNÉES DANS LE MI Individual Cons 2018-03-1 2018-03- 2018-04- 2018-05- 2018-04- 2018-05- 2018-04- 2018-05- 2018-10- 2019-01- IDA / 57080 afety net for the poor in se Post Open 2,419.37 1,408.72 Completed S CONCERNANT LES MÉNA ultant Selection 5 15 14 02 17 16 21 23 18 01 lected rural areas GES BÉNÉFICIAIRES ACTP MANAKARA DRK12CISAI18002 / SAISI Component 1: Building a s Individual Cons Under Impleme 2018-03-1 2018-04- 2018-04- 2018-04- 2018-10- DES DONNÉES DANS LE MI IDA / 57080 afety net for the poor in se Post Open 2,419.35 0.00 ultant Selection ntation 5 14 17 21 18 S DES BÉNÉFICIAIRES TMD lected rural areas H VOHIPENO DRP81CIOS18001 / CI OPE Component 1: Building a s Individual Cons 2018-04-2 2018-03- 2018-04- 2018-03- 2018-05- 2018-03- 2018-05- 2018-03- 2018-12- RATEUR DE SAISIE SUD18 IDA / D1450 afety net for the poor in se Post Limited 2,000.00 278.50 Terminated ultant Selection 4 08 24 19 09 19 11 22 31 1 lected rural areas DRP81CIOS18002 / CI OPE Component 1: Building a s Individual Cons 2018-04-2 2018-03- 2018-04- 2018-03- 2018-05- 2018-03- 2018-05- 2018-03- 2018-12- RATEUR DE SAISIE SUD18 IDA / D1450 afety net for the poor in se Post Limited 2,000.00 1,847.81 Signed ultant Selection 4 08 24 21 09 21 11 22 31 2 lected rural areas Page 16 DRP81CIOS18003 / CI OPE Component 1: Building a s Individual Cons 2018-04-2 2018-03- 2018-04- 2018-03- 2018-05- 2018-03- 2018-05- 2018-03- 2018-12- RATEUR DE SAISIE SUD18 IDA / D1450 afety net for the poor in se Post Limited 2,000.00 1,847.81 Signed ultant Selection 4 08 24 21 09 21 11 22 31 3 lected rural areas DRP81CIOS18004 / CI OPE Component 1: Building a s Individual Cons 2018-04-2 2018-03- 2018-04- 2018-03- 2018-05- 2018-03- 2018-05- 2018-03- 2018-12- RATEUR DE SAISIE SUD18 IDA / D1450 afety net for the poor in se Post Limited 2,000.00 1,847.81 Signed ultant Selection 4 08 24 21 09 21 11 22 31 4 lected rural areas DRP81CIOS18005 / CI OPE Component 1: Building a s Individual Cons 2018-04-2 2018-03- 2018-04- 2018-03- 2018-05- 2018-03- 2018-05- 2018-03- 2018-12- RATEUR DE SAISIE SUD18 IDA / D1450 afety net for the poor in se Post Limited 2,000.00 1,847.81 Signed ultant Selection 4 08 24 21 09 21 11 22 31 5 lected rural areas DRP81CIOS18006 / CI OPE Component 1: Building a s Individual Cons 2018-04-2 2018-03- 2018-04- 2018-03- 2018-05- 2018-03- 2018-05- 2018-03- 2018-12- RATEUR DE SAISIE SUD18 IDA / D1450 afety net for the poor in se Post Limited 2,000.00 1,847.81 Signed ultant Selection 4 08 24 21 09 21 11 22 31 6 lected rural areas DRT12CIACC1804 / Consul tant Individuel chargé du re nforcement de capacité de Component 1: Building a s Individual Cons 2018-04-2 2018-04- 2018-05- 2018-05- 2018-06- 2018-06- 2018-06- 2019-06- 2019-09- s Mères Leaders et des acc IDA / 57080 afety net for the poor in se Post Open 7,741.94 7,242.05 Completed ultant Selection 5 06 18 23 11 05 13 30 20 ompagnements des Espace lected rural areas s de bien-être du projet de Protection Sociale du FID ( Accompagnateur) BETAFO 4 DRT12CIACC1805 / Renfor cements de capacité des M Component 1: Building a s ères Leaders et des accom Individual Cons 2018-04-2 2018-04- 2018-05- 2018-05- 2018-06- 2018-06- 2018-06- 2019-06- 2019-09- IDA / 57080 afety net for the poor in se Post Open 7,741.94 7,471.95 Completed pagnements des Espaces d ultant Selection 6 06 18 23 11 05 13 30 18 lected rural areas e bien-être du projet de Pro tection Sociale du FID (Acc ompagnateur) BETAFO 5 DRT12CIACC1806 / Renfor cements de capacité des M Component 1: Building a s ères Leaders et des accom Individual Cons 2018-04-2 2018-04- 2018-05- 2018-05- 2018-06- 2018-06- 2018-06- 2019-06- 2019-09- IDA / 57080 afety net for the poor in se Post Open 7,741.94 7,391.76 Completed pagnements des Espaces d ultant Selection 6 06 18 23 11 05 13 30 16 lected rural areas e bien-être du projet de Pro tection Sociale du FID (Acc ompagnateur) BETAFO 6 DRT12CIACC1807 / Renfor cements de capacité des M Component 1: Building a s ères Leaders et des accom Individual Cons 2018-04-2 2018-04- 2018-05- 2018-05- 2018-06- 2018-06- 2018-06- 2019-06- 2019-09- IDA / 57080 afety net for the poor in se Post Open 7,741.94 6,975.81 Completed pagnements des Espaces d ultant Selection 6 06 18 23 11 05 13 30 20 lected rural areas e bien-être du projet de Pro tection Sociale du FID (Acc ompagnateur) BETAFO 7 DRT12CIACC1808 / Renfor cements de capacité des M Component 1: Building a s ères Leaders et des accom Individual Cons 2018-04-2 2018-04- 2018-05- 2018-05- 2018-06- 2018-06- 2018-06- 2019-06- 2019-09- IDA / 57080 afety net for the poor in se Post Open 7,741.94 7,457.16 Completed pagnements des Espaces d ultant Selection 6 06 18 23 11 05 13 30 20 lected rural areas e bien-être du projet de Pro tection Sociale du FID (Acc ompagnateur) BETAFO 8 DRF12CISAI17004 / SAISIE Component 1: Building a s DANS LA BASE DE DONNÉE Individual Cons 2018-04-2 2018-04- 2018-05- 2018-05- 2018-12- IDA / 57080 afety net for the poor in se Post Limited 218.75 0.00 Canceled S LES INFORMATIONS CON ultant Selection 7 29 09 12 19 lected rural areas CERNANT LES MÉNAGES BÉ NÉFICIAIRES TMDH DRT11CIASS1801 / Recrut ement de consultant indivi duel accompagnateur spéci Component 1: Building a s Individual Cons 2018-06-0 2018-06- 2018-06- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2019-10- 2019-09- alisé pour la mise en œuvr IDA / 57080 afety net for the poor in se Post Open 8,225.80 6,013.54 Completed ultant Selection 5 11 27 09 06 10 13 13 13 27 e du développement de la lected rural areas petite enfance intensifié et l'éducation des ménages d u programme ACTP DRT11CIASS1802 / Recrut ement de consultant indivi duel accompagnateur spéci Component 1: Building a s Individual Cons 2018-06-0 2018-06- 2018-06- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2019-05- alisé pour la mise en œuvr IDA / 57080 afety net for the poor in se Post Open 5,483.80 5,093.52 Terminated ultant Selection 5 11 27 09 06 10 13 13 13 e du développement de la lected rural areas petite enfance intensifié et l'éducation des ménages d u programme ACTP DRT11CIASS1803 / Recrut ement de consultant indivi duel accompagnateur spéci Component 1: Building a s Individual Cons 2018-06-0 2018-06- 2018-06- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2019-05- 2019-09- alisé pour la mise en œuvr IDA / 57080 afety net for the poor in se Post Open 5,483.80 8,730.42 Completed ultant Selection 5 11 27 09 06 10 13 13 13 27 e du développement de la lected rural areas petite enfance intensifié et l'éducation des ménages d u programme ACTP DRT11CIASS1804 / Recrut ement de consultant indivi duel accompagnateur spéci Component 1: Building a s Individual Cons 2018-06-0 2018-06- 2018-06- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2019-05- 2019-09- alisé pour la mise en œuvr IDA / 57080 afety net for the poor in se Post Open 5,483.80 5,694.30 Completed ultant Selection 5 11 27 09 06 10 13 13 13 27 e du développement de la lected rural areas petite enfance intensifié et l'éducation des ménages d u programme ACTP DRT11CISUP18001 / Mise Component 1: Building a s Individual Cons 2018-06-0 2018-06- 2018-06- 2018-06- 2018-08- 2018-06- 2018-08- 2019-06- à jour PAMO et supervision IDA / 57080 afety net for the poor in se Post Limited 7,612.90 1,376.60 Terminated ultant Selection 7 11 12 19 16 25 29 30 des travaux dans 6 UTB AC lected rural areas TP à Antanifotsy DRT11CISEC18001 / Mise Component 1: Building a s en œuvre du suivi évaluati Individual Cons 2018-06-0 2018-06- 2018-06- 2018-08- 2018-06- 2018-08- 2018-06- 2018-08- 2019-06- 2019-06- IDA / 57080 afety net for the poor in se Post Limited 2,022.58 2,243.52 Completed on communautaire (SEC) s ultant Selection 7 11 12 14 19 22 25 29 30 18 lected rural areas ur 6 UTB de l'ACTP à Antani fotsy DRA12CIASS18003 / ACCO Component 1: Building a s MPAGNEMENT BENEFICIAR Individual Cons 2018-06-0 2018-06- 2018-06- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2019-10- IDA / 57080 afety net for the poor in se Post Open 8,225.80 6,121.82 Signed ES - ACTIVITES DE SENSIBIL ultant Selection 5 11 27 07 06 07 13 30 06 lected rural areas ISATION - MISE EN ŒUVRE DPE ET EP DRA12CIASS18004 / ACCO Component 1: Building a s MPAGNEMENT BENEFICIAR Individual Cons 2018-06-0 2018-06- 2018-06- 2018-08- 2018-07- 2018-08- 2018-07- 2018-08- 2019-05- IDA / 57080 afety net for the poor in se Post Open 5,483.87 5,509.85 Signed ES - ACTIVITES DE SENSIBIL ultant Selection 5 11 27 07 06 07 13 30 14 lected rural areas ISATION - MISE EN ŒUVRE DPE ET EP DRA12CIPAMO18005 / MIS Component 1: Building a s E A JOUR PAMO ET SUPERV Individual Cons 2018-06-0 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2019-06- IDA / 57080 afety net for the poor in se Post Limited 6,106.45 5,310.61 Signed ISIONS DES TRAVAUX DAN ultant Selection 5 11 10 29 17 03 23 14 28 lected rural areas S 06 UTB ACT P DISTRICT DE VATOMANDRY DRA12CIPAMO18006 / MIS Component 1: Building a s E A JOUR PAMO ET SUPERV Individual Cons 2018-06-0 2018-08- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2019-06- IDA / 57080 afety net for the poor in se Post Limited 6,106.45 3,588.37 Terminated ISION DES TRAVAUX DANS ultant Selection 6 30 11 28 18 01 24 24 29 lected rural areas 06 UTB ACT P DISTRICT DE VATOMANDRY DRA12CISEC18007 / MISE Component 1: Building a s EN ŒUVRE DE SUIVI EVALU Individual Cons 2018-06-0 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2019-06- IDA / 57080 afety net for the poor in se Post Limited 2,021.61 1,719.81 Terminated ATION COMMUNAUTAIRE ( ultant Selection 6 11 11 29 18 04 24 22 29 lected rural areas SEC) dans 04 UTB ACT P VA TOMANDRY DRA12CISEC18008 / MISE Component 1: Building a s EN ŒUVRE DE SUIVI EVALU Individual Cons 2018-06-0 2018-06- 2018-06- 2018-10- 2018-06- 2018-10- 2018-06- 2018-10- 2019-06- IDA / 57080 afety net for the poor in se Post Limited 2,021.61 1,170.60 Terminated ATION COMMUNAUTAIRE ( ultant Selection 6 11 11 01 18 02 24 24 29 lected rural areas SEC) dans 04 UTB ACT P VA TOMANDRY DRA12CISEC1809 / MISE E Component 1: Building a s N ŒUVRE DE SUIVI EVALUA Individual Cons 2018-06-0 2018-08- 2018-06- 2018-09- 2018-06- 2018-10- 2018-06- 2018-10- 2019-06- IDA / 57080 afety net for the poor in se Post Limited 2,021.61 1,152.51 Signed TION COMMUNAUTAIRE ( S ultant Selection 6 30 11 28 18 02 24 24 29 lected rural areas EC) dans 04 UTB ACT P VAT OMANDRY DRA12CISAI18001 / MISE A JOURS INFORMATIONS DES Component 1: Building a s Individual Cons 2018-06-0 2018-06- 2018-06- 2018-06- 2019-06- BÉNÉFICIAIRES ET SAISI D IDA / 57080 afety net for the poor in se Post Limited 1,935.48 0.00 Canceled ultant Selection 6 11 18 29 29 E FICHE DE PRÉSENCE DES lected rural areas TRAVAILLEURS ACTP DISTR ICT VATOMANDRY DRA12CISAI18002 / MISE A JOURS INFORMATIONS DES Component 1: Building a s Individual Cons 2018-06-0 2018-06- 2018-06- 2018-11- 2018-06- 2018-11- 2018-06- 2018-11- 2019-06- BÉNÉFICIAIRES ET SAISI D IDA / 57080 afety net for the poor in se Post Limited 1,935.48 209.67 Signed ultant Selection 6 06 11 08 18 12 29 26 29 E FICHE DE PRESENCE DES lected rural areas TRAVAILLEURS ACTP DISTR ICT VATOMANDRY DRF11CIAS18001 / RECRU TEMENT DE CONSULTANT I NDIVIDUEL ACCOMPAGNAT Component 1: Building a s Individual Cons 2018-06-1 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2018-07- 2018-08- 2019-06- 2019-10- EUR SPÉCIALISÉ POUR LA M IDA / 57080 afety net for the poor in se Post Open 5,483.87 6,135.30 Completed ultant Selection 1 08 24 23 26 03 01 06 26 07 ISE EN ŒUVRE DU DÉVELO lected rural areas PPEMENT DE LA PETITE EN FANCE INTENSIFIÉ ET L'ÉD UCATION DES MÉNAGES D U PROGRAMME ACTP 01 DRF11CIAS18002 / RECRU TEMENT DE CONSULTANT I NDIVIDUEL ACCOMPAGNAT Component 1: Building a s Individual Cons 2018-06-1 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2018-07- 2018-08- 2019-06- 2019-10- EUR SPÉCIALISÉ POUR LA M IDA / 57080 afety net for the poor in se Post Open 5,483.87 6,126.12 Completed ultant Selection 1 08 24 23 26 03 01 06 26 07 ISE EN ŒUVRE DU DÉVELO lected rural areas PPEMENT DE LA PETITE EN FANCE INTENSIFIÉ ET L'ÉD UCATION DES MÉNAGES D U PROGRAMME ACTP02 DRF11CIAS18003 / RECRU TEMENT DE CONSULTANT I NDIVIDUEL ACCOMPAGNAT Component 1: Building a s Individual Cons 2018-06-1 2018-06- 2018-06- 2018-07- 2018-06- 2018-08- 2018-07- 2018-08- 2019-09- 2019-10- EUR SPÉCIALISÉ POUR LA M IDA / 57080 afety net for the poor in se Post Open 8,225.81 6,135.30 Completed ultant Selection 1 08 24 23 26 03 01 06 24 04 ISE EN ŒUVRE DU DÉVELO lected rural areas PPEMENT DE LA PETITE EN FANCE INTENSIFIÉ ET L'ÉD UCATION DES MÉNAGES D U PROGRAMME ACTP03 DG20CFFTOMAF1810 / FO Component 2: Strengtheni 2018-06-1 2018-06- 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-07- RMATION RECYCLAGE EN T IDA / 57080 ng safety net administratio Post Direct Selection Direct 700.00 564.21 Completed 1 11 14 19 25 29 10 11 OM2PRO EQUIPE SAF n, monitoring and social ac countability DG20CICOMMDPEI1811 / C Component 1: Building a s ONSULTANT EN COMMUNIC Individual Cons 2018-06-0 2018-07- 2018-06- 2018-07- 2018-07- 2018-07- 2018-07- 2018-07- 2019-01- 2018-12- IDA / 57080 afety net for the poor in se Post Open 13,859.00 39,582.66 Completed ATION DANS LES MESURES ultant Selection 6 09 29 10 01 16 05 16 01 28 lected rural areas D'ACCOMPAGNEMENT DES TRANSFERTS MONETAIRES DRK11CIAS18001 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons Pending Imple 2018-06-0 2018-06- 2018-06- 2018-06- 2019-09- IDA / 57080 afety net for the poor in se Post Open 8,225.67 0.00 R SPÉCIALISÉ DE SENSIBILI ultant Selection mentation 7 24 25 27 20 lected rural areas SATION ACTP MANAKARA DRK11CIAS18002 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons Pending Imple 2018-06-0 2018-06- 2018-06- 2018-06- 2019-04- IDA / 57080 afety net for the poor in se Post Open 5,483.78 0.00 R SPÉCIALISÉ DE SENSIBILI ultant Selection mentation 7 24 25 27 23 lected rural areas SATION ACTP MANAKARA DRK11CIAS18003 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons Under Impleme 2018-06-0 2018-06- 2018-06- 2018-06- 2018-06- 2019-04- IDA / 57080 afety net for the poor in se Post Open 5,483.78 0.00 R SPÉCIALISÉ DE SENSIBILI ultant Selection ntation 7 11 24 25 27 23 lected rural areas SATION ACTP MANAKARA DRK11CIAS18004 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons Pending Imple 2018-06-0 2018-06- 2018-06- 2018-06- 2019-04- IDA / 57080 afety net for the poor in se Post Open 5,483.78 0.00 R SPÉCIALISÉ DE SENSIBILI ultant Selection mentation 7 24 25 27 23 lected rural areas SATION ACTP MANAKARA DRU12CIASS18001 / Recru tement de consultant indivi duel accompagnateur spéci Component 1: Building a s Individual Cons 2018-06-0 2018-06- 2018-06- 2018-07- 2018-07- 2018-08- 2018-07- 2018-08- 2019-10- alisé pour la mise en œuvr IDA / 57080 afety net for the poor in se Post Open 8,226.00 6,088.70 Signed ultant Selection 7 11 29 31 08 02 15 31 08 e du développement de la lected rural areas petite enfance intensifié et l'éducation des ménages d u programme ACTP DRU12CIASS18002 / Recru Component 1: Building a s tement de consultant indivi Individual Cons 2018-06-0 2018-06- 2018-06- 2018-09- 2018-07- 2018-09- 2018-07- 2018-09- 2019-05- IDA / 57080 afety net for the poor in se Post Open 5,484.00 5,794.39 Signed duel accompagnateur spéci ultant Selection 7 11 29 10 08 13 15 28 16 lected rural areas alisé pour la suivi des sensi bilisations DG20CIFORMGOUV1812 / Component 2: Strengtheni Individual Cons 2018-06-0 2018-06- 2018-06- 2018-06- 2018-06- 2018-06- 2018-07- 2018-06- 2018-07- 2018-07- Formation en Gouvernance IDA / 57080 ng safety net administratio Post Limited 120.00 503.16 Completed ultant Selection 7 11 12 18 30 22 07 28 22 31 citoyenne n, monitoring and social ac countability DG20CFFORMAUD1813 / F Component 2: Strengtheni 2018-10-0 2018-10- 2018-11- 2018-11- ORMATION EN AUDIT INTER IDA / 57080 ng safety net administratio Post Direct Selection Direct 300.00 0.00 Canceled 1 11 05 20 NE n, monitoring and social ac countability DG20CFFORMPERMA1816 Component 2: Strengtheni 2018-06-1 2018-09- 2018-06- 2018-11- 2018-07- 2018-12- 2018-08- 2018-12- / FORMATION EN PERMACU IDA / 57080 ng safety net administratio Post Direct Selection Direct 1,489.00 1,242.33 Completed 7 21 24 06 17 04 01 05 LTURE n, monitoring and social ac countability DG20CFFORMEDACT1817 / Component 2: Strengtheni 2018-06-1 2018-10- 2018-06- 2018-11- 2018-07- 2018-11- 2018-08- 2018-11- FORMATION EN METHODE IDA / 57080 ng safety net administratio Post Direct Selection Direct 2,977.00 2,201.70 Completed 7 22 24 05 17 23 01 27 D'EDUCATION ACTIVE n, monitoring and social ac countability DRA12CISAI18010 / OPERA Component 1: Building a s Individual Cons 2018-06-1 2018-06- 2018-06- 2018-08- 2018-06- 2018-08- 2018-07- 2018-08- 2018-12- TEUR DE SAISIE DES DONN IDA / 57080 afety net for the poor in se Post Limited 967.74 550.58 Signed ultant Selection 8 20 23 21 30 22 11 30 31 ES SUR MIS MENAGES BEN lected rural areas EFICIAIRES TMDH DRU12CIASDPEI18001 / Re Component 1: Building a s crutement de consultant in Individual Cons 2018-07-2 2018-07- 2018-08- 2018-08- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- IDA / 57080 afety net for the poor in se Post Open 4,500.00 5,234.89 Signed dividuel accompagnateur s ultant Selection 0 18 16 30 25 03 02 13 12 lected rural areas pécialisé pour les activités de DPEI TMDH DRT12CIASS1801 / Recrut ement de consultant indivi duel accompagnateur spéci Component 1: Building a s Individual Cons 2018-07-2 2018-07- 2018-08- 2018-09- 2018-08- 2018-09- 2018-08- 2018-09- 2019-08- 2019-09- alisé pour la mise en œuvr IDA / 57080 afety net for the poor in se Post Open 5,806.45 6,308.57 Completed ultant Selection 1 19 14 06 27 05 31 06 31 20 e du développement de la lected rural areas petite enfance intensifié et l'éducation des ménages d u programme TMDH DRT12CIASS1802 / Recrut ement de consultant indivi duel accompagnateur spéci Component 1: Building a s Individual Cons 2018-07-2 2018-08- 2018-08- 2018-08- 2019-08- alisé pour la mise en œuvr IDA / 57080 afety net for the poor in se Post Open 5,806.45 0.00 Canceled ultant Selection 1 14 27 31 31 e du développement de la lected rural areas petite enfance intensifié et l'éducation des ménages d u programme TMDH DRK12CIAS18001 / ACCOM Component 1: Building a s Individual Cons Under Impleme 2018-07-2 2017-04- 2018-08- 2018-08- 2018-08- 2019-08- PAGNATEUR SPECIALISE DP IDA / 57080 afety net for the poor in se Post Open 5,625.00 0.00 ultant Selection ntation 3 26 09 10 12 12 EI_1 lected rural areas DRK12CIAS18002 / ACCOM Component 1: Building a s Individual Cons Under Impleme 2018-07-2 2018-04- 2018-08- 2018-08- 2018-08- 2019-08- PAGNATEUR SPECIALISE DP IDA / 57080 afety net for the poor in se Post Open 5,625.00 0.00 ultant Selection ntation 3 26 09 10 12 12 EI_2 lected rural areas DRU11CICI18004 / ACTP CI Component 1: Building a s SO Ciblage à l'intégration d Individual Cons 2018-08-0 2018-09- 2018-08- 2018-09- 2018-08- 2018-10- 2018-09- 2018-10- 2018-10- IDA / 57080 afety net for the poor in se Post Open 2,140.10 815.78 Signed es nouveaux ménages dan ultant Selection 2 09 22 20 27 01 03 26 08 lected rural areas s le district d'Ankazoabo DRU11CICI18003 / ACTP CI Component 1: Building a s SO Ciblage à l'intégration d Individual Cons 2018-08-0 2018-09- 2018-08- 2018-09- 2018-08- 2018-10- 2018-09- 2018-10- 2018-10- IDA / 57080 afety net for the poor in se Post Open 2,140.10 709.19 Signed es nouveaux ménages dan ultant Selection 2 09 22 20 27 01 03 26 08 lected rural areas s le district d'Ankazoabo DRU11CICI18005 / ACTP CI Component 1: Building a s SO Ciblage à l'intégration d Individual Cons 2018-08-0 2018-09- 2018-08- 2018-09- 2018-08- 2018-10- 2018-09- 2018-10- 2018-10- IDA / 57080 afety net for the poor in se Post Open 2,140.10 710.70 Signed es nouveaux ménages dan ultant Selection 2 09 22 20 27 01 03 26 08 lected rural areas s le district d'Ankazoabo DRU11CICI18006 / ACTP CI Component 1: Building a s SO Ciblage à l'intégration d Individual Cons 2018-08-0 2018-09- 2018-08- 2018-09- 2018-08- 2018-10- 2018-09- 2018-10- 2018-10- IDA / 57080 afety net for the poor in se Post Open 2,140.10 687.52 Signed es nouveaux ménages dan ultant Selection 2 09 22 20 27 01 03 26 08 lected rural areas s le district d'Ankazoabo DRU11CICI18007 / ACTP CI Component 1: Building a s SO Ciblage à l'intégration d Individual Cons 2018-08-0 2018-09- 2018-08- 2018-09- 2018-08- 2018-10- 2018-09- 2018-10- 2018-10- IDA / 57080 afety net for the poor in se Post Open 2,140.10 826.57 Signed es nouveaux ménages dan ultant Selection 2 09 22 28 27 01 03 26 08 lected rural areas s le district d'Ankazoabo DRU11CICI18008 / ACTP CI Component 1: Building a s Chef d'équipe Ciblage à l'in Individual Cons 2018-08-0 2018-09- 2018-08- 2018-09- 2018-08- 2018-10- 2018-09- 2018-10- 2018-10- IDA / 57080 afety net for the poor in se Post Open 3,009.51 1,306.52 Signed tégration des nouveaux mé ultant Selection 2 09 22 20 27 01 03 26 08 lected rural areas nages dans le district d'Ank azoabo DRT11CICIB1801 / Consult ant individuel socio-organis Component 1: Building a s Individual Cons 2018-08-0 2018-09- 2018-08- 2018-09- 2018-08- 2018-09- 2018-09- 2018-10- 2018-10- 2019-02- ateur chargé du ciblage de IDA / 57080 afety net for the poor in se Post Open 532.25 510.34 Completed ultant Selection 7 10 26 24 31 27 02 03 02 15 s bénéficiaires complément lected rural areas aires de l'ACTP à Antanifots y. DRT11CICIB1802 / Consult ant individuel socio-organis Component 1: Building a s Individual Cons 2018-08-0 2018-09- 2018-08- 2018-09- 2018-08- 2018-09- 2018-09- 2018-10- 2018-10- 2019-02- ateur chargé du ciblage de IDA / 57080 afety net for the poor in se Post Open 532.25 468.96 Completed ultant Selection 7 10 26 24 31 27 02 03 02 15 s bénéficiaires complément lected rural areas aires de l'ACTP à Antanifots y. DRT11CICIB1803 / Consult ant individuel socio-organis Component 1: Building a s Individual Cons 2018-08-0 2018-09- 2018-08- 2018-09- 2018-08- 2018-09- 2018-09- 2018-10- 2018-10- 2019-02- ateur chargé du ciblage de IDA / 57080 afety net for the poor in se Post Open 532.25 496.55 Completed ultant Selection 7 10 26 24 31 27 02 03 02 15 s bénéficiaires complément lected rural areas aires de l'ACTP à Antanifots y. DRT11CICIB1804 / Consult ant individuel socio-organis Component 1: Building a s Individual Cons 2018-08-0 2018-09- 2018-08- 2018-09- 2018-08- 2018-09- 2018-09- 2018-10- 2018-10- 2019-02- ateur chargé du ciblage de IDA / 57080 afety net for the poor in se Post Open 532.25 441.38 Completed ultant Selection 7 10 26 24 31 27 02 03 02 15 s bénéficiaires complément lected rural areas aires de l'ACTP à Antanifots y. DRT11CICIB1805 / Consult ant individuel socio-organis Component 1: Building a s Individual Cons 2018-08-0 2018-09- 2018-08- 2018-09- 2018-08- 2018-09- 2018-09- 2018-10- 2018-10- 2019-02- ateur chargé du ciblage de IDA / 57080 afety net for the poor in se Post Open 532.25 400.00 Completed ultant Selection 7 10 26 24 31 27 02 03 02 15 s bénéficiaires complément lected rural areas aires de l'ACTP à Antanifots y. Component 1: Building a s DRP81CIAS18001 / ASDRP Individual Cons 2018-08-1 2018-08- 2018-09- 2018-10- 2018-09- 2018-10- 2018-09- 2018-10- 2019-09- IDA / D1450 afety net for the poor in se Post Open 5,806.45 5,193.93 Signed AMBOASARY ultant Selection 4 22 10 08 17 16 27 26 22 lected rural areas Component 1: Building a s DRP81CIAS18002 / ASDRP Individual Cons 2018-08-1 2018-08- 2018-09- 2018-10- 2018-09- 2018-10- 2018-09- 2018-10- 2019-09- IDA / D1450 afety net for the poor in se Post Open 5,806.45 4,864.83 Signed AMBOVOMBE ultant Selection 4 22 10 08 17 16 27 26 22 lected rural areas Component 1: Building a s DRP81CIAS18003 / ASDRP Individual Cons 2018-08-1 2018-08- 2018-09- 2018-10- 2018-09- 2018-10- 2018-09- 2018-10- 2019-09- IDA / D1450 afety net for the poor in se Post Open 5,806.45 5,424.28 Signed TSIHOMBE ultant Selection 4 22 10 08 17 16 27 26 22 lected rural areas DG12CIANALTMC1826 / AN Component 1: Building a s Individual Cons 2018-08-2 2018-09- 2018-08- 2018-09- 2018-09- 2018-09- 2018-09- 2018-10- 2018-10- 2018-12- ALYSE COMPLEMENTAIRE T IDA / 57080 afety net for the poor in se Post Limited 1,250.00 1,704.54 Completed ultant Selection 0 06 25 13 04 25 10 01 10 07 MC BETAFO lected rural areas Component 1: Building a s DRP81CIOS18009 / OPERA Individual Cons 2018-11-0 2018-09- 2018-11- 2018-09- 2018-11- 2018-09- 2018-11- 2018-09- 2018-12- IDA / D1450 afety net for the poor in se Post Open 764.71 710.53 Signed TEUR DE SAISIE BEKILY ultant Selection 5 05 05 17 05 17 05 17 31 lected rural areas DRP81CIOS18010 / OPERA Component 1: Building a s Individual Cons 2018-11-0 2018-11- 2018-11- 2019-01- 2018-11- 2019-02- 2018-11- 2019-02- 2019-03- TEUR DE SAISIE A TSIHOMB IDA / D1450 afety net for the poor in se Post Open 882.00 1,237.10 Signed ultant Selection 5 05 21 28 23 04 28 04 31 E lected rural areas Page 17 DG12CIAUDAMBALAK1828 / REDACTION (1) D'UN RAP PORT CIRCONSTANCIEL SU R L'ACCIDENT SURVENU A Component 2: Strengtheni LA MISSION DE SUPERVISIO ng safety net administratio Individual Cons 2018-12-1 2018-12- 2018-12- 2018-12- 2018-12- 2018-12- 2018-12- 2018-12- 2019-03- IDA / 57080 Post Direct 25,000.00 20,882.00 Terminated N DE PAIEMENT AYANT ENT n, monitoring and social ac ultant Selection 1 05 13 06 17 10 21 10 26 RAINE LE DECES D'UN EMP countability LOYE DE FID (2) D'UN RAPP ORT SUR L'ANALYSE DES RI SQUES, DES PRATIQUES ET DISPOSITIONS EN MATIÈRE DE SÉCURITÉ DRA12CISAI18011 / SAISIE DE CORESPONSABILITE SC Component 1: Building a s Individual Cons 2018-12-2 2017-02- 2019-01- 2019-01- 2019-01- 2019-01- 2019-01- 2019-02- 2019-07- OLAIRE , DES FICHES DE P IDA / 57080 afety net for the poor in se Post Open 1,261.93 876.95 Signed ultant Selection 0 07 09 18 11 18 18 08 17 RESENCE ET MISE A JOUR D lected rural areas 'INFORMATION DES BENEFI CIAIRES TMDH DRA12CIACC18012 / ACCO MPAGNATEUR SPÉCIALISE Component 1: Building a s DISTRICT MAHANORO REN Individual Cons 2018-12-2 2018-06- 2018-12- 2018-11- 2018-12- 2018-11- 2019-01- 2019-01- 2019-04- IDA / 57080 afety net for the poor in se Post Limited 1,379.03 3,181.95 Signed FORCEMENT DE CAPACITE ultant Selection 0 11 25 30 28 30 07 30 07 lected rural areas ET DE FORMATION DES ME RES LEADER ET ACCOMPAG NEMENT DES ESPACE DE BI EN ETRE DRP81CIOS19001 / OPERA Component 1: Building a s Individual Cons 2019-01-2 2019-01- 2019-01- 2019-02- 2019-01- 2019-02- 2019-02- 2019-02- 2019-06- TEUR DE SAISIE AMBOVOM IDA / D1450 afety net for the poor in se Post Open 1,246.20 944.17 Signed ultant Selection 2 22 29 08 30 13 01 13 30 BE lected rural areas Component 1: Building a s DRP81CIOS19002 / OPERA Individual Cons 2019-02-1 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-02- 2019-06- IDA / D1450 afety net for the poor in se Post Open 1,063.70 947.77 Signed TEUR DE SAISIE DRP ultant Selection 9 06 19 08 20 13 20 13 30 lected rural areas DRA11CISEC19001 / MISE Component 1: Building a s EN ŒUVRE DE SUIVI EVALU Individual Cons 2019-02-1 2019-03- 2019-03- 2019-03- 2019-06- IDA / 57080 afety net for the poor in se Post Limited 614.41 0.00 Canceled ATION COMMUNAUTAIRE ( ultant Selection 9 06 11 20 18 lected rural areas SEC) dans 04 UTB ACT P VA TOMANDRY DRF12CIAS19001 / CONSU Component 1: Building a s Individual Cons 2019-03-2 2017-09- 2019-04- 2018-11- 2019-04- 2018-11- 2019-04- 2018-12- 2019-07- 2019-03- LTANT TEMPORAIRE ACCO IDA / 57080 afety net for the poor in se Post Open 1,224.26 1,178.49 Completed ultant Selection 5 21 07 27 09 28 14 07 13 15 MPAGNATEURS SPECIALISE lected rural areas S Component 1: Building a s DRF12CIAS19002 / RECRU Individual Cons 2019-03-2 2017-09- 2019-04- 2018-11- 2019-04- 2018-11- 2019-04- 2018-12- 2019-07- 2019-03- IDA / 57080 afety net for the poor in se Post Open 1,224.26 1,178.18 Completed TEMENT AS TEMPORAIRE ultant Selection 5 21 07 27 09 28 14 07 13 15 lected rural areas Component 1: Building a s DRF12CIAS19003 / RECRU Individual Cons 2019-02-2 2019-02- 2019-03- 2019-04- 2019-03- 2019-04- 2019-03- 2019-04- 2019-06- 2019-08- IDA / 57080 afety net for the poor in se Post Open 1,500.00 1,393.83 Completed TEMENT AS TEMPORAIRE ultant Selection 0 13 05 15 07 19 12 24 10 08 lected rural areas Component 1: Building a s DRF12CIAS19004 / RECRU Individual Cons 2019-02-2 2019-02- 2019-03- 2019-05- 2019-03- 2019-05- 2019-03- 2019-06- 2019-06- 2019-10- IDA / 57080 afety net for the poor in se Post Open 1,500.00 1,394.23 Completed TEMENT AS TEMPORAIRE ultant Selection 0 13 05 14 07 31 12 03 10 04 lected rural areas DG20CIMANUTMDH1901 / MISE A JOUR DU MANUEL D Component 2: Strengtheni E PROCÉDURES ng safety net administratio Individual Cons 2019-03-1 2019-04- 2019-04- 2019-04- 2019-06- DES PROGRAMMES DE TRA IDA / 57080 Post Open 6,000.00 0.00 Canceled n, monitoring and social ac ultant Selection 4 12 19 29 28 NSFERT MONÉTAIRE POUR countability LE DÉVELOPPEMENT HUMAI N PROJET FILETS SOCIAUX DE SÉCURITÉ DG20CIMANUMACC1902 / MISE A JOUR DU MANUEL D Component 2: Strengtheni E PROCÉDURES ng safety net administratio Individual Cons 2019-03-1 2019-04- 2019-04- 2019-04- 2019-06- DES MESURES D'ACCOMPA IDA / 57080 Post Open 6,000.00 0.00 Canceled n, monitoring and social ac ultant Selection 4 12 19 29 28 GNEMENT DU PROGRAMME countability FILETS SOCIAUX DE SÉCURI TÉ EXÉCUTE PAR LE FID DG20CIMANUSE1903 / MIS Component 2: Strengtheni E A JOUR DU MANUEL DE P ng safety net administratio Individual Cons 2019-03-1 2019-03- 2019-04- 2019-04- 2019-04- 2019-05- 2019-04- 2019-05- 2019-06- 2019-07- IDA / 57080 Post Open 6,000.00 2,802.48 Completed ROCEDURES n, monitoring and social ac ultant Selection 4 15 12 29 19 02 29 03 28 31 SUIVI EVALUATION PROJET countability FILETS SOCIAUX DE SECURI TE DG20CIMANUACTP1904 / Component 2: Strengtheni MISE A JOUR DE MANUEL D ng safety net administratio Individual Cons 2019-03-1 2019-04- 2019-04- 2019-04- 2019-06- E PROCÉDURE DES OPÉRAT IDA / 57080 Post Open 6,000.00 0.00 Canceled n, monitoring and social ac ultant Selection 4 12 19 29 28 IONS « ARGENT CONTRE T countability RAVAIL PRODUCTIF » PROJ ET FILETS SOCIAUX DE SÉ CURITÉ DG20CIMANUADMPM1905 / MISE A JOUR DES MANUEL Component 2: Strengtheni S DE PROCÉDURES ADMINI ng safety net administratio Individual Cons 2019-03-1 2019-03- 2019-04- 2019-04- 2019-04- 2019-05- 2019-04- 2019-05- 2019-06- IDA / 57080 Post Open 6,000.00 2,593.12 Signed STRATIVES ET FINANCIÈRE n, monitoring and social ac ultant Selection 4 15 12 26 19 06 29 06 28 S ET PASSATION DE MARCH countability E PROJET FILETS SOCIAUX DE SÉCURITÉ DRF13CIOS19005 / RECRU Component 1: Building a s TEMENT CONSULTANT INDI Individual Cons 2019-05-2 2019-06- 2019-05- 2019-06- 2019-06- 2019-06- 2019-06- 2019-06- 2019-09- 2019-09- IDA / 57080 afety net for the poor in se Post Limited 617.65 453.58 Completed VIDUEL TEMPORAIRE POUR ultant Selection 0 04 22 17 19 18 25 19 23 03 lected rural areas LA SAISIE DES DONNEES D ANS LE MIS DG20CABCSPM1905 / CABI Component 2: Strengtheni NET EN CHARGE DU RECRU ng safety net administratio 2019-05-1 2019-05- 2019-05- 2019-05- 2019-06- 2019-06- 2019-06- 2019-09- IDA / 57080 Post Direct Selection Direct 3,000.00 2,279.51 Completed TEMENT DU CHEF DE SERVI n, monitoring and social ac 3 14 28 29 09 28 29 16 CE PASSATION DES MARCH countability ES DG20CFORMRSE1901 / Re Component 2: Strengtheni nforcement de capacités e ng safety net administratio 2019-07-1 2019-07- 2019-07- 2019-07- 2019-07- 2019-08- 2019-08- 2019-09- IDA / 57080 Post Direct Selection Direct 3,000.00 4,952.32 Completed n Suivi Évaluation de l'équi n, monitoring and social ac 8 19 24 29 28 16 07 10 pe Suivi Évaluation du FID countability DG20CISTATECON1901 / R ecrutement d'un Statisticie Component 1: Building a s n-économiste chargé de la Individual Cons 2019-07-2 2019-08- 2019-09- 2019-09- 2019-09- 2019-12- 2019-09- 2020-01- 2019-12- IDA / 57080 afety net for the poor in se Post Open 6,000.00 3,199.72 Signed modélisation pour le recérti ultant Selection 5 01 14 16 15 13 23 10 22 lected rural areas fication des bénéficiaires d es activités TMDH du Distri ct de Betafo dans le cadre du Projet FSS DG20CICOMM1901 / Recru Component 2: Strengtheni Individual Cons 2019-08-1 2019-08- 2019-09- 2019-09- 2019-09- 2019-09- 2019-09- 2019-09- 2019-11- tement d 'un Consultant en IDA / 57080 ng safety net administratio Post Open 4,000.00 3,458.49 Signed ultant Selection 4 28 09 05 14 09 19 09 18 communication n, monitoring and social ac countability DG20CIPM1902 / Recrute Component 2: Strengtheni Individual Cons 2019-09-0 2019-08- 2019-09- 2019-09- 2019-09- 2019-06- 2019-09- 2019-07- 2019-12- 2019-09- ment consultant en Passati IDA / 57080 ng safety net administratio Post Direct 4,000.00 2,282.03 Completed ultant Selection 1 30 03 03 05 12 07 02 06 16 on de marchés n, monitoring and social ac countability DRA12CISIGN19002 / Cons ultant individuel en charge Component 1: Building a s Individual Cons 2019-10-1 2019-10- 2019-10- 2019-10- 2019-12- des suivis des IDA / 57080 afety net for the poor in se Post Limited 222.22 0.00 Canceled ultant Selection 8 23 26 30 09 signatures des contrats des lected rural areas bénéficiaires TMDH en vue de FSS-FA2 - DIST MAHANO RO DRA12CISIGN19001 / Cons ultant individuel en charge Component 1: Building a s Individual Cons 2019-10-1 2019-10- 2019-10- 2019-10- 2019-12- des suivis des IDA / 57080 afety net for the poor in se Post Limited 222.22 0.00 Canceled ultant Selection 8 23 26 30 09 signatures des contrats des lected rural areas bénéficiaires TMDH en vue de FSS-FA2 - DIST MAHANO RO DRA12CISIGN19003 / Cons ultant individuel en charge Component 1: Building a s Individual Cons 2019-10-1 2019-10- 2019-10- 2019-10- 2019-12- des suivis des IDA / 57080 afety net for the poor in se Post Limited 222.22 0.00 Canceled ultant Selection 8 23 26 30 09 signatures des contrats des lected rural areas bénéficiaires TMDH en vue de FSS-FA2 - DIST TOAMASI NA II DRA12CISIGN19004 / Cons ultant individuel en charge Component 1: Building a s Individual Cons 2019-10-1 2019-10- 2019-10- 2019-10- 2019-12- des suivis des IDA / 57080 afety net for the poor in se Post Limited 222.22 0.00 Canceled ultant Selection 8 23 26 30 09 signatures des contrats des lected rural areas bénéficiaires TMDH en vue de FSS-FA2 - DIST TOAMASI NA II DRT12CICONT1901 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 138.31 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 28 28 23 30 28 30 06 lected rural areas H dans le District de Faratsi ho DRT12CICONT1902 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 130.20 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 28 30 06 lected rural areas H dans le District de Faratsi ho DRT12CICONT1903 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 130.96 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 29 30 07 lected rural areas H dans le District de Faratsi ho DRT12CICONT1904 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 157.04 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 28 30 06 lected rural areas H dans le District de Faratsi ho DRT12CICONT1905 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 157.04 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 29 30 07 lected rural areas H dans le District de Faratsi ho DRT12CICONT1906 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 147.80 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 29 30 07 lected rural areas H dans le District de Faratsi ho DRT12CICONT1907 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 140.74 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 28 30 06 lected rural areas H dans le District de Faratsi ho DRT12CICONT1908 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 151.61 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 28 30 06 lected rural areas H dans le District de Faratsi ho DRT12CICONT1909 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 166.82 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 28 30 06 lected rural areas H dans le District de Faratsi ho DRT12CICONT1910 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 135.31 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 29 30 07 lected rural areas H dans le District de Faratsi ho DRT12CICONT1911 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 152.70 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 29 30 07 lected rural areas H dans le District de Faratsi ho DRT12CICONT1912 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 147.26 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 29 30 07 lected rural areas H dans le District de Faratsi ho DRT12CICONT1913 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 151.61 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 29 30 07 lected rural areas H dans le District de Faratsi ho DRT12CICONT1914 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 147.80 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 29 30 07 lected rural areas H dans le District de Faratsi ho DRT12CICONT1915 / Signa Component 1: Building a s ture et dispatch des contra Individual Cons 2019-10-2 2019-09- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- IDA / 57080 afety net for the poor in se Post Limited 138.89 147.26 Completed ts des bénéficiaires du TMD ultant Selection 2 19 23 23 28 28 30 29 30 07 lected rural areas H dans le District de Faratsi ho DRP82CISIGN19024 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 271.37 Completed ultant Selection 4 23 26 28 28 28 28 28 07 07 KILY1 lected rural areas DRP82CISIGN19025 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 248.50 Completed ultant Selection 4 23 26 28 28 28 28 28 07 07 KILY2 lected rural areas DRP82CISIGN19026 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 KILY3 lected rural areas DRP82CISIGN19001 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURECONTRATMGAMB IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 OASARY1 lected rural areas DRP82CISIGN19002 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURECONTRATAMBOA IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 SARY2 lected rural areas DRP82CISIGN19027 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 KILY4 lected rural areas DRP82CISIGN19003 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOA IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 SARY3 lected rural areas DRP82CISIGN19004 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOA IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 SARY4 lected rural areas DRP82CISIGN19005 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOA IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 25 28 30 28 17 28 18 07 SARY5 lected rural areas DRP82CISIGN19006 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOA IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 SARY6 lected rural areas DRP82CISIGN19007 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOA IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 SARY7 lected rural areas DRP82CISIGN19008 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOA IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 SARY8 lected rural areas DRP82CISIGN19009 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOA IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 28 25 28 30 28 01 28 01 07 SARY9 lected rural areas DRP82CISIGN19010 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOB IDA / D1450 afety net for the poor in se Post Limited 225.83 188.06 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE11 lected rural areas DRP82CISIGN19028 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 KILY5 lected rural areas DRP82CISIGN19029 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 KILY6 lected rural areas DRP82CISIGN19030 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 KILY7 lected rural areas DRP82CISIGN19031 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 KILY8 lected rural areas DRP82CISIGN19032 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 LOHA1 lected rural areas DRP82CISIGN19033 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 LOHA2 lected rural areas DRP82CISIGN19034 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 LOHA3 lected rural areas DRP82CISIGN19035 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-11- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 28 26 28 28 28 28 28 07 07 LOHA4 lected rural areas DRP82CISIGN19036 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 LOHA5 lected rural areas DRP82CISIGN19037 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 LOHA6 lected rural areas DRP82CISIGN19011 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 188.06 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE12 lected rural areas DRP82CISIGN19039 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 LOHA8 lected rural areas DRP82CISIGN19038 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG BE IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 LOHA7 lected rural areas DRP82CISIGN19012 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE13 lected rural areas DRP82CISIGN19040 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG TSI IDA / D1450 afety net for the poor in se Post Limited 225.83 187.93 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 HOMBE1 lected rural areas DRP82CISIGN19013 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE14 lected rural areas DRP82CISIGN19041 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG TSI IDA / D1450 afety net for the poor in se Post Limited 225.83 187.93 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 HOMBE2 lected rural areas DRP82CISIGN19042 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG TSI IDA / D1450 afety net for the poor in se Post Limited 225.83 187.93 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 HOMBE3 lected rural areas Page 18 DRP82CISIGN19043 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG TSI IDA / D1450 afety net for the poor in se Post Limited 225.83 187.93 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 HOMBE4 lected rural areas DRP82CISIGN19044 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-11- GNATURE CONTRAT MG TSI IDA / D1450 afety net for the poor in se Post Limited 225.83 187.93 Completed ultant Selection 4 26 26 28 28 28 28 28 07 07 HOMBE5 lected rural areas DRP82CISIGN19045 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG TSI IDA / D1450 afety net for the poor in se Post Limited 225.83 187.93 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 HOMBE6 lected rural areas DRP82CISIGN19046 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG TSI IDA / D1450 afety net for the poor in se Post Limited 225.83 187.93 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 HOMBE7 lected rural areas DRP82CISIGN19047 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG TSI IDA / D1450 afety net for the poor in se Post Limited 225.83 187.93 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 HOMBE8 lected rural areas DRP82CISIGN19048 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG TSI IDA / D1450 afety net for the poor in se Post Limited 225.83 187.77 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 HOMBE9 lected rural areas DRP82CISIGN19014 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE15 lected rural areas DRP82CISIGN19049 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG TSI IDA / D1450 afety net for the poor in se Post Limited 225.83 187.77 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 HOMBE10 lected rural areas DRP82CISIGN19050 / CI SI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURE CONTRAT MG TSI IDA / D1450 afety net for the poor in se Post Limited 225.83 187.77 Completed ultant Selection 4 26 25 28 30 28 01 29 02 08 HOMBE11 lected rural areas DRP82CISIGN19015 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE16 lected rural areas DRP82CISIGN19016 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE17 lected rural areas DRP82CISIGN19017 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE18 lected rural areas DRP82CISIGN19018 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE21 lected rural areas DRP82CISIGN19019 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 29 28 03 28 05 28 06 07 OMBE22 lected rural areas DRP82CISIGN19020 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE23 lected rural areas DRP82CISIGN19021 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE24 lected rural areas DRP82CISIGN19022 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 191.34 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE25 lected rural areas DRP82CISIGN19023 / CISI Component 1: Building a s Individual Cons 2019-10-2 2019-10- 2019-10- 2019-10- 2019-10- 2019-10- 2019-11- 2019-10- 2019-12- 2019-11- GNATURECONTRATAMBOV IDA / D1450 afety net for the poor in se Post Limited 225.83 187.96 Completed ultant Selection 4 26 25 28 30 28 01 28 02 07 OMBE26 lected rural areas DRK11CIAS19001 / RECRU Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- TEMENT ACCOMPAGNATEU IDA / D4340 afety net for the poor in se Post Open 10,000.00 5,584.90 Signed ultant Selection 9 10 19 17 22 07 09 24 08 R SPÉCIALISÉ ACTP lected rural areas DRA12CISOMAJ19003 / Co nsultants Individuels charg Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- és de la mise à jour des do IDA / D4340 afety net for the poor in se Post Limited 510.00 518.67 Signed ultant Selection 8 20 03 03 06 10 10 25 24 nnées sur les ménages TM lected rural areas DH DISTRICT TOAMASINA I I ET MAHANORO DRF12CIMAJ19001 / RECR UTEMENT CONSULTANT IN Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- DIVIDUEL POUR LA MISE A J IDA / D4340 afety net for the poor in se Post Limited 1,625.00 647.46 Signed ultant Selection 5 19 10 22 13 24 17 25 31 OUR DES MENAGES BENEFI lected rural areas CIAIRES TMDH DISTRICT A MBOHIMAHASOA DRF12CIMAJ19002 / RECR Component 1: Building a s UTEMENT CONSULTANT IN Individual Cons 2019-12-0 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 1,625.00 647.46 Signed DIVIDUEL POUR LA MISE A J ultant Selection 4 19 09 22 12 24 16 25 30 lected rural areas OUR DES BENEFICIAIRES T MDH DISTRICT AMBOHIMA HASOA DRF12CIMAJ19003 / RECR Component 1: Building a s UTEMENT CONSULTANT IN Individual Cons 2019-12-0 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 1,625.00 647.46 Signed DIVIDUEL POUR LA MISE A J ultant Selection 5 19 10 22 13 24 17 25 31 lected rural areas OUR DES BENEFICIAIRES T MDH DISTRICT AMBOHIMA HASOA DRF12CIMAJ19004 / RECR Component 1: Building a s UTEMENT CONSULTANT IN Individual Cons 2019-12-0 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 1,625.00 647.46 Signed DIVIDUEL POUR LA MISE A J ultant Selection 5 19 10 22 13 11 17 25 31 lected rural areas OUR DES BENEFICIAIRES T MDH DISTRICT AMBOHIMA HASOA DRF12CIOS19001 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-02- 2021-12- TEMENT OPERATEUR DE SA IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,210.34 Signed ultant Selection 2 19 17 10 24 13 14 01 27 ISIE TMDH DISTRICT AMBO lected rural areas HIMAHASOA DRF12CIOS19002 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-02- 2021-12- TEMENT OPERATEUR DE SA IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,210.34 Signed ultant Selection 2 19 17 10 24 13 14 01 27 ISIE TMDH DISTRICT AMBO lected rural areas HIMAHASOA DRF12CIOS19003 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-02- 2021-01- TEMENT OPERATEUR DE SA IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,216.28 Signed ultant Selection 2 19 17 10 24 13 14 01 08 ISIE TMDH DISTRICT AMBO lected rural areas HIMAHASOA DRF12CIOS19004 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-02- 2021-01- TEMENT OPERATEUR DE SA IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,216.28 Signed ultant Selection 2 19 17 10 24 13 14 01 08 ISIE TMDH DISTRICT AMBO lected rural areas HIMAHASOA DRF11CIOS19001 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-03- 2020-12- TEMENT OPERATEUR DE SA IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,023.73 Signed ultant Selection 2 19 17 24 07 27 11 03 31 ISIE ACTP DISTRICT ISANDR lected rural areas A DRF11CIOS19002 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-01- TEMENT OPERATEUR DE SA IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,023.73 Signed ultant Selection 2 19 17 24 24 27 14 03 08 ISIE ACTP DISTRICT ISANDR lected rural areas A DRF11CIOS19003 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-01- TEMENT OPERATEUR DE SA IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,023.73 Signed ultant Selection 2 19 17 24 24 27 14 03 08 ISIE ACTP DISTRICT ISANDR lected rural areas A DRF11CIOS19004 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- TEMENT OPERATEUR DE SA IDA / D4340 afety net for the poor in se Post Limited 5,000.00 1,748.72 Signed ultant Selection 2 19 17 26 24 01 14 02 08 ISIE ACTP DISTRICT MANAN lected rural areas DRIANA DRA12CISOMAJ19001 / Mis Component 1: Building a s e à jour des données sur le Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 510.00 530.05 Signed s ménages TMDH DISTRICT ultant Selection 8 20 03 03 06 10 10 25 24 lected rural areas TOAMASINA II ET MAHANO RO DRA12CISOMAJ19002 / MI SE A JOUR DES INFORMATI Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- ONS SUR LES MENAGES BE IDA / D4340 afety net for the poor in se Post Limited 510.00 525.91 Signed ultant Selection 8 20 03 03 06 10 10 25 24 NEFICIAIRES DES ACTIVITE lected rural areas S TMDH DISTRICRT TOAMA SINA II ET MAHANORO DRA12CISOMAJ19004 / MI SE A JOUR DES INFORMATI Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- ONS SUR LES MENAGES BE IDA / D4340 afety net for the poor in se Post Limited 510.00 532.89 Signed ultant Selection 8 20 03 03 06 10 10 25 24 NEFICIAIRES DES ACTIVITE lected rural areas S TMDH - DISTRICT TOAMA SINA II ET MAHANORO DRA12CISOMAJ19005 / MI SE A JOUR DES INFORMATI Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- ONS SUR LES MENAGES BE IDA / D4340 afety net for the poor in se Post Limited 510.00 527.46 Signed ultant Selection 8 20 03 03 06 10 10 25 24 NEFICIAIRES DES ACTIVITE lected rural areas S TMDH DANS LE DISTRICR T TOAMASINA II ET MAHAN ORO DRA12CISOMAJ19006 / MI SE A JOUR DES INFORMATI Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- ONS SUR LES MENAGES BE IDA / D4340 afety net for the poor in se Post Limited 510.00 523.84 Signed ultant Selection 8 20 03 03 06 10 10 25 24 NEFICIAIRES DES ACTIVITE lected rural areas S TMDH DANS LE DISTRICR T TOAMASINA II ET MAHAN ORO DRA12CISOMAJ19007 / MI SE A JOUR DES INFORMATI Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- ONS SUR LES MENAGES BE IDA / D4340 afety net for the poor in se Post Limited 510.00 521.26 Signed ultant Selection 8 20 03 03 06 10 10 25 24 NEFICIAIRES DES ACTIVITE lected rural areas S TMDH DANS LE DISTRICR T TOAMASINA II ET MAHAN ORO DRA12CISOMAJ19008 / MI SE A JOUR DES INFORMATI Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- ONS SUR LES MENAGES BE IDA / D4340 afety net for the poor in se Post Limited 510.00 525.65 Signed ultant Selection 8 20 03 03 06 10 10 25 24 NEFICIAIRES DES ACTIVITE lected rural areas S TMDH DANS LE DISTRICR T TOAMASINA II ET MAHAN ORO DRK11CIAS19002 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- IDA / D4340 afety net for the poor in se Post Open 10,000.00 5,584.90 Signed R SPÉCIALISÉ MESURE D'A ultant Selection 9 19 19 17 22 07 09 24 08 lected rural areas CCOMPAGNEMENT ACTP DRK11CIAS19003 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- IDA / D4340 afety net for the poor in se Post Open 10,000.00 5,584.90 Signed R SPÉCIALISÉ MESURE D'A ultant Selection 9 19 19 17 22 07 09 24 08 lected rural areas CCOMPAGNEMENT ACTP DRK11CIAS19004 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- IDA / D4340 afety net for the poor in se Post Open 10,000.00 5,584.90 Signed R SPÉCIALISÉ MESURE D'A ultant Selection 9 19 19 17 22 07 09 23 08 lected rural areas CCOMPAGNEMENT ACTP DRK11CIAS19005 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- IDA / D4340 afety net for the poor in se Post Open 10,000.00 5,584.90 Signed R SPÉCIALISÉ MESURE D'A ultant Selection 9 19 19 17 22 07 09 24 08 lected rural areas CCOMPAGNEMENT ACTP DRK11CIAS19006 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons Pending Imple 2019-11-2 2019-12- 2019-12- 2020-01- 2021-01- IDA / D4340 afety net for the poor in se Post Open 10,000.00 0.00 R SPÉCIALISÉ MESURE D'A ultant Selection mentation 9 19 22 09 08 lected rural areas CCOMPAGNEMENT ACTP DRF11CIOS19005 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- TEMENT OPERATEUR DE SA IDA / D4340 afety net for the poor in se Post Limited 5,000.00 1,748.72 Signed ultant Selection 2 19 17 26 24 01 14 02 08 ISIE ACTP DISTRICT MANAN lected rural areas DRIANA DRF12CISOCOP19001 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- IDA / D4340 afety net for the poor in se Post Limited 165.00 25.83 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 17 28 07 06 05 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19002 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- IDA / D4340 afety net for the poor in se Post Limited 165.00 41.32 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 17 28 07 06 05 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19003 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- IDA / D4340 afety net for the poor in se Post Limited 165.00 36.16 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 17 28 07 06 05 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19004 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- IDA / D4340 afety net for the poor in se Post Limited 165.00 38.75 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 17 28 07 06 05 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19005 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- IDA / D4340 afety net for the poor in se Post Limited 165.00 36.16 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 17 28 07 06 05 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19006 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- IDA / D4340 afety net for the poor in se Post Limited 165.00 33.58 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 17 28 07 06 05 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19007 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 38.75 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19008 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 33.58 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19009 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 46.48 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19010 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 33.58 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19011 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 25.82 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19012 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 36.15 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19013 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 41.33 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19014 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 51.66 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19015 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 33.58 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19016 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 51.65 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19017 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 41.32 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19018 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 33.58 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19019 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 43.91 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19020 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 25.83 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19021 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 36.16 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19022 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 36.16 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19023 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 33.58 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19024 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 33.58 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19025 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 51.66 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19026 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 41.33 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19027 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 51.66 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA Page 19 DRF12CISOCOP19028 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 33.58 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19029 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 36.16 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19030 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 25.83 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CISOCOP19031 / RE Component 1: Building a s CRUTEMENT CONSULTANT Individual Cons 2019-12-0 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 165.00 25.82 Signed INDIVIDUEL CHARGE COUP ultant Selection 5 18 10 27 31 28 04 06 02 lected rural areas DE POUCE TMDH DISTRICT AMBOHIMAHASOA DRF12CIASTMDH19001 / R Component 1: Building a s ECRUTEMENT ACCOMPAGN Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2022-02- IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,898.20 Signed ATEUR SPECIALISE TMDH D ultant Selection 2 20 17 05 07 12 11 25 03 lected rural areas ANS LE DISTRICT D'AMBOHI MAHASOA DRF12CIASTMDH19002 / R Component 1: Building a s ECRUTEMENT ACCOMPAGN Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2022-02- IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,898.20 Signed ATEUR SPECIALISE TMDH D ultant Selection 2 20 17 05 07 18 11 25 03 lected rural areas ANS LE DISTRICT D'AMBOHI MAHASOA DRF12CIASTMDH19003 / R Component 1: Building a s ECRUTEMENT ACCOMPAGN Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2022-02- IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,898.20 Signed ATEUR SPECIALISE TMDH D ultant Selection 2 20 17 05 07 18 11 25 03 lected rural areas ANS LE DISTRICT D'AMBOHI MAHASOA DRF12CIASTMDH19004 / R Component 1: Building a s ECRUTEMENT ACCOMPAGN Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2022-02- IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,898.20 Signed ATEUR SPECIALISE TMDH D ultant Selection 2 20 17 05 07 18 11 25 03 lected rural areas ANS LE DISTRICT D'AMBOHI MAHASOA DRF12CIASTMDH19005 / R Component 1: Building a s ECRUTEMENT ACCOMPAGN Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2021-08- IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,896.86 Signed ATEUR SPECIALISE TMDH D ultant Selection 2 20 17 05 07 18 11 25 04 lected rural areas ANS LE DISTRICT D'AMBOHI MAHASOA DRF11CIAS19001 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2020-01- 2019-12- 2020-03- 2020-01- 2020-04- 2020-02- 2020-05- 2021-08- TEMENT ACCOMPAGNATEU IDA / D4340 afety net for the poor in se Post Limited 10,000.00 5,632.42 Signed ultant Selection 2 27 17 17 07 13 11 01 04 R SPECIALISE ACTP DANS L lected rural areas E DISTRICT D'ISANDRA DRF11CIAS19002 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-03- 2020-01- 2020-04- 2020-02- 2020-05- 2021-08- TEMENT ACCOMPAGNATEU IDA / D4340 afety net for the poor in se Post Limited 10,000.00 5,632.42 Signed ultant Selection 2 06 17 13 07 15 11 01 04 R SPECIALISE ACTP DANS L lected rural areas E DISTRICT D'ISANDRA DRF11CIAS19004 / RECRU Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-03- 2020-01- 2020-04- 2020-02- 2020-05- 2021-08- TEMENT ACCOMPAGNATEU IDA / D4340 afety net for the poor in se Post Limited 10,000.00 5,632.42 Signed ultant Selection 2 06 17 13 07 15 11 01 04 R SPECIALISE ACTP DANS L lected rural areas E DISTRICT D'ISANDRA DRF11CIAS19005 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons 2019-12-1 2020-02- 2019-12- 2020-03- 2020-01- 2020-04- 2020-02- 2020-05- 2021-08- IDA / D4340 afety net for the poor in se Post Limited 10,000.00 5,632.42 Signed R SPECIALISE ACTP DANS L ultant Selection 2 06 17 13 07 15 11 01 04 lected rural areas E DISTRICT DE MANANDRIA NA DRF11CIAS19006 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons 2019-12-1 2020-02- 2019-12- 2020-03- 2020-01- 2020-04- 2020-02- 2020-05- 2021-08- IDA / D4340 afety net for the poor in se Post Limited 10,000.00 5,632.42 Signed R SPECIALISE ACTP DANS L ultant Selection 2 06 17 13 07 15 11 01 04 lected rural areas E DISTRICT DE MANANDRIA NA DRF11CIAS19003 / RECRU Component 1: Building a s TEMENT ACCOMPAGNATEU Individual Cons 2019-12-1 2020-02- 2019-12- 2020-03- 2020-01- 2020-04- 2020-02- 2020-05- 2021-08- IDA / D4340 afety net for the poor in se Post Limited 10,000.00 5,632.42 Signed R SPECIALISE ACTP DANS L ultant Selection 2 06 17 13 07 15 11 01 04 lected rural areas E DISTRICT DE MANANDRIA NA DRP82CIOS20007 / CI OPE Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-03- RATEUR DE SAISIE BELOHA IDA / D4340 afety net for the poor in se Post Limited 2,916.67 2,158.12 Signed ultant Selection 9 23 09 24 16 20 08 02 07 1 lected rural areas DRP82CIOS20008 / CI OPE Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-03- RATEUR DE SAISIE BELOHA IDA / D4340 afety net for the poor in se Post Limited 2,916.67 2,184.02 Signed ultant Selection 9 23 09 24 16 28 08 02 07 2 lected rural areas DG20SCISEC_SYS_INFO / P Component 2: Strengtheni ool de consultants individu ng safety net administratio Individual Cons 2019-11-2 2019-11- 2019-12- 2020-06- 2020-01- 2020-08- 2020-02- 2020-09- 2020-04- IDA / D4340 Post Open 10,000.00 6,385.42 Signed els chargé de l'étude sécuri n, monitoring and social ac ultant Selection 8 18 26 05 09 18 06 10 06 sation du système informat countability ique DRP82CIOS20009 / CI OPE Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-02- 2020-02- 2020-12- RATEUR DE SAISIE BELOHA IDA / D4340 afety net for the poor in se Post Limited 2,916.67 2,184.02 Signed ultant Selection 3 23 08 24 29 28 02 02 31 3 lected rural areas DG20SCI_SUP_BETAFO1 / Component 1: Building a s Individual Cons 2019-12-0 2019-10- 2020-01- 2020-02- 2020-01- 2020-02- 2020-02- 2020-03- 2020-04- Superviseur des enquêteur IDA / D4340 afety net for the poor in se Post Open 1,000.00 1,033.20 Signed ultant Selection 9 29 06 07 20 11 17 10 17 s pour la re-certification bé lected rural areas néficiaires Betafo (1) DG20SCI_SUP_BETAFO2 / Component 1: Building a s Individual Cons 2019-12-0 2019-10- 2020-01- 2020-02- 2020-01- 2020-02- 2020-02- 2020-03- 2020-04- Superviseur des enquêteur IDA / D4340 afety net for the poor in se Post Open 1,000.00 1,033.20 Signed ultant Selection 9 29 06 07 20 11 17 10 17 s pour la re-certification bé lected rural areas néficiaires Betafo (2) DG20SCI_SUP_BETAFO3 / Component 1: Building a s Individual Cons 2019-12-0 2019-10- 2020-01- 2020-02- 2020-01- 2020-02- 2020-02- 2020-03- 2020-04- Superviseur des enquêteur IDA / D4340 afety net for the poor in se Post Open 1,000.00 1,033.20 Signed ultant Selection 9 29 06 07 20 11 17 10 17 s pour la re-certification bé lected rural areas néficiaires Betafo (3) DG20SCI_SUP_BETAFO4 / Component 1: Building a s Individual Cons 2019-12-0 2019-10- 2020-01- 2020-06- 2020-01- 2020-02- 2020-02- 2020-03- 2020-04- Superviseur des enquêteur IDA / D4340 afety net for the poor in se Post Open 1,000.00 1,033.20 Signed ultant Selection 9 29 06 07 20 11 17 10 17 s pour la re-certification bé lected rural areas néficiaires Betafo (4) DRA12CISOMAJ19010 / MI SE A JOUR DES INFORMATI Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- ONS DES MENAGES BENEF IDA / D4340 afety net for the poor in se Post Limited 510.00 526.42 Signed ultant Selection 8 20 03 17 06 10 10 25 24 ICIAIRES DES ACTIVITES TM lected rural areas DH DANS LE DISTRICT TOA MASINA II ET MAHANORO DRP82CIOS20001 / OPERA Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-03- TEURDESAISIEDRPAMBOVO IDA / D4340 afety net for the poor in se Post Limited 2,916.67 2,158.12 Signed ultant Selection 8 23 09 24 16 20 08 02 07 MBE1 lected rural areas DRP82CIOS20010 / CI OPE Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-03- RATEUR DE SAISIE TSIHOM IDA / D4340 afety net for the poor in se Post Limited 2,916.67 2,183.45 Signed ultant Selection 9 23 09 24 16 28 08 02 07 BE 1 lected rural areas DRA12CISOMAJ19009 / MI Component 1: Building a s SE A JOUR DES INFORMATI Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 510.00 525.91 Signed ONS DES MENAGES BENEF ultant Selection 8 20 03 03 06 10 10 25 24 lected rural areas ICIAIRES TMDH DISTRICT T OAMASINA II ET MAHANOR O DRP82CIOS20011 / CI OPE Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-03- RATEUR DE SAISIE TSIHOM IDA / D4340 afety net for the poor in se Post Limited 2,916.67 2,183.45 Signed ultant Selection 9 23 09 24 16 28 08 02 07 BE 2 lected rural areas DRT12CIAS19001 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,693.22 Signed ultant Selection 6 20 21 10 28 14 18 03 31 e cadre du TMDH à Betafo lected rural areas 1 DRT12CIAS19002 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,550.96 Signed ultant Selection 6 20 21 10 28 14 18 03 31 e cadre du TMDH à Betafo lected rural areas 2 DRT12CIAS19003 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,622.09 Signed ultant Selection 6 20 21 10 28 14 18 03 31 e cadre du TMDH à Betafo lected rural areas 3 DRT12CIAS19004 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,693.22 Signed ultant Selection 6 20 21 10 28 14 18 03 31 e cadre du TMDH à Betafo lected rural areas 4 DRT12CIAS19005 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,693.22 Signed ultant Selection 6 20 21 10 28 14 18 03 31 e cadre du TMDH à Betafo lected rural areas 5 DRT12CIAS19006 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,206.69 Signed ultant Selection 6 20 21 11 28 14 18 03 31 e cadre du TMDH à Faratsi lected rural areas ho 1 DRT12CIAS19007 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,693.22 Signed ultant Selection 6 20 21 10 28 14 18 03 31 e cadre du TMDH à Faratsi lected rural areas ho 2 DRT12CIAS19008 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,693.22 Signed ultant Selection 6 20 21 10 28 14 18 03 31 e cadre du TMDH à Faratsi lected rural areas ho 3 DRT12CIAS19009 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,693.22 Signed ultant Selection 6 20 21 10 28 14 18 03 31 e cadre du TMDH à Faratsi lected rural areas ho 4 DRP82CIOS20002 / OPERA Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-03- TEURDESAISIEDRPAMBOVO IDA / D4340 afety net for the poor in se Post Limited 2,916.67 2,173.30 Signed ultant Selection 8 23 09 24 16 20 08 02 07 MBE2 lected rural areas DRT12CIAS19010 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,693.22 Signed ultant Selection 6 20 21 10 28 14 18 03 31 e cadre du TMDH à Faratsi lected rural areas ho 5 DRT12CIAS19011 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,500.00 5,550.96 Signed ultant Selection 6 20 21 10 28 14 18 03 31 e cadre du TMDH-DPEI 1 lected rural areas DRT12CIAS19012 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,500.00 5,550.96 Signed ultant Selection 6 20 21 10 28 14 18 03 31 e cadre du TMDH-DPEI lected rural areas DRT12CIAS19013 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-02- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 6,641.58 Signed ultant Selection 6 20 21 23 28 28 18 29 31 e cadre du TMDH-Inclusion lected rural areas Productive DRT12CIAS19014 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-02- 2021-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 8,000.00 5,682.15 Signed ultant Selection 6 20 21 23 28 28 18 29 31 e cadre du TMDH-Inclusion lected rural areas Productive DRP82CIOS20003 / OPERA Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-03- TEURDESAISIEDRPAMBOVO IDA / D4340 afety net for the poor in se Post Limited 2,916.67 2,170.16 Signed ultant Selection 8 23 09 24 16 20 08 02 07 MBE3 lected rural areas DRA12CISOMAJ19011 / MI Component 1: Building a s SE A JOUR DES INFORMATI Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 510.00 501.09 Signed ONS DES MENAGES BENEF ultant Selection 8 20 03 20 06 10 10 25 24 lected rural areas ICIAIRES TMDH DISTRICT T OAMASINA II ET MAHANOR O DRK11CIOSACTP19001 / C Component 1: Building a s ONSULTANT INDIVIDUEL C Individual Cons 2019-12-0 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-01- IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,078.75 Signed HARGE DE LA SAISIE DE DO ultant Selection 9 18 14 18 21 31 11 08 05 lected rural areas NNÉES SUR MIS DANS LE C ADRE DE L' ACTP DRP82CIOS20004 / OPERA Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-03- TEURDESAISIEDRPAMBOVO IDA / D4340 afety net for the poor in se Post Limited 2,916.67 2,170.16 Signed ultant Selection 8 23 09 24 16 20 08 02 07 MBE4 lected rural areas DRT12CISOCOP19001 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 91.92 Completed ultant Selection 6 17 21 08 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRK11CIOSACTP19003 / O Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-01- 2020-04- PÉRATEUR DE SAISIE DANS IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,078.75 Completed ultant Selection 9 18 14 18 21 31 11 08 05 10 LE CADRE DE L'ACTP lected rural areas DRT12CISOCOP19002 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 103.41 Completed ultant Selection 6 17 21 08 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRT12CISOCOP19003 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 111.02 Completed ultant Selection 6 17 21 08 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRT12CISOCOP19004 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 114.90 Completed ultant Selection 6 17 21 08 28 27 18 19 16 19 coup de pouce TMDH lected rural areas DRT12CISOCOP19005 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 114.90 Completed ultant Selection 6 17 21 08 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRT12CISOCOP19006 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 103.41 Completed ultant Selection 6 17 21 08 28 27 18 19 16 19 coup de pouce TMDH lected rural areas DRT12CISOCOP19007 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 103.41 Completed ultant Selection 6 17 21 07 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRT12CISOCOP19008 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 91.79 Completed ultant Selection 6 17 21 08 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRK12CIASTMDH19001 / C Component 1: Building a s ONSULTANT INDIVIDUEL AC Individual Cons 2019-12-1 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2021-02- IDA / D4340 afety net for the poor in se Post Limited 6,250.00 5,112.95 Signed COMPAGNATEUR SPÉCIALIS ultant Selection 2 19 17 03 07 10 11 26 10 lected rural areas E DANS LE CADRE DU TMD H DRT12CISOCOP19009 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 91.92 Completed ultant Selection 6 17 21 08 28 27 18 19 16 19 coup de pouce TMDH lected rural areas DRP82CIOS20013 / CI OPE Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-03- RATEUR DE SAISIE BEKILY IDA / D4340 afety net for the poor in se Post Limited 2,916.67 2,183.69 Signed ultant Selection 9 23 09 24 16 29 08 02 07 1 lected rural areas DRT12CISOCOP19010 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 114.90 Completed ultant Selection 6 17 21 16 28 27 18 19 16 19 coup de pouce TMDH lected rural areas DRT12CISOCOP19011 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 114.90 Completed ultant Selection 6 17 21 20 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRT12CISOCOP19012 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 114.90 Completed ultant Selection 6 17 21 20 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRT12CISOCOP19013 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 103.41 Completed ultant Selection 6 17 21 27 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRP82CIOS20014 / CI OPE Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-03- RATEUR DE SAISIE BEKILY IDA / D4340 afety net for the poor in se Post Limited 2,916.67 2,183.69 Signed ultant Selection 9 23 09 24 16 29 08 02 07 2 lected rural areas DRT12CISOCOP19014 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 68.94 Completed ultant Selection 6 17 21 07 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRT12CISOCOP19015 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 91.79 Completed ultant Selection 6 17 21 07 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRT12CISOCOP19016 / So Component 1: Building a s Individual Cons 2019-12-1 2020-05- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 103.27 Signed ultant Selection 6 18 21 07 28 27 18 19 16 coup de pouce du TMDH lected rural areas DRT12CISOCOP19017 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 68.94 Completed ultant Selection 6 17 21 07 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRT12CISOCOP19018 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 111.02 Completed ultant Selection 6 17 21 07 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRT12CISOCOP19019 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 103.41 Completed ultant Selection 6 17 21 08 28 27 18 19 16 19 coup de pouce TMDH lected rural areas DRT12CISOCOP19020 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 103.41 Completed ultant Selection 6 17 21 07 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas DRT12CISOCOP19021 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 111.02 Completed ultant Selection 6 17 21 07 28 27 18 19 16 19 coup de pouce TMDH lected rural areas DRT12CISOCOP19023 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 91.92 Completed ultant Selection 6 17 21 10 28 27 18 19 16 19 coup de pouce TMDH lected rural areas DRT12CISOCOP19024 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 114.90 Completed ultant Selection 6 17 21 20 28 27 18 19 16 19 coup de pouce TMDH lected rural areas DRT12CISOCOP19025 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 114.90 Completed ultant Selection 6 17 21 28 28 28 18 19 16 19 coup de pouce TMDH lected rural areas DRT12CISOCOP19026 / So Component 1: Building a s Individual Cons 2019-12-0 2020-02- 2019-12- 2020-01- 2020-02- 2020-12- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Direct 100.00 0.00 Canceled ultant Selection 3 17 13 03 07 31 coup de pouce TMDH lected rural areas DRK12CIASTMDH19002 / C Component 1: Building a s ONSULTANT INDIVIDUEL AC Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2021-02- IDA / D4340 afety net for the poor in se Post Limited 6,250.00 5,112.95 Signed COMPAGNATEUR SPECIALIS ultant Selection 2 19 17 03 07 10 11 26 10 lected rural areas E DANS LE CADRE DU TMD H DRT12CISOCOP19022 / So Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-05- 2020-07- 2020-09- cio-organisateur chargé du IDA / D4340 afety net for the poor in se Post Limited 100.00 91.92 Completed ultant Selection 6 17 21 10 28 27 18 19 16 19 coup de pouce du TMDH lected rural areas Page 20 DRT12CIMAJ19001 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 298.07 Completed a mise à jour des informati ultant Selection 6 20 21 12 28 12 18 13 07 20 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19002 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-09- IDA / D4340 afety net for the poor in se Post Limited 300.00 485.04 Completed a mise à jour des informati ultant Selection 6 20 21 10 28 12 18 13 07 03 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRK12CIASTMDH19003 / C Component 1: Building a s ONSULTANT INDIVIDUEL AC Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2021-02- IDA / D4340 afety net for the poor in se Post Limited 6,250.00 5,114.93 Signed COMPAGNATEUR SPÉCIALIS ultant Selection 2 19 17 03 07 10 11 26 10 lected rural areas É DANS LE CADRE DU TMD H DRT12CIMAJ19003 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-09- IDA / D4340 afety net for the poor in se Post Limited 300.00 479.62 Completed a mise à jour des informati ultant Selection 6 20 21 10 28 12 18 13 07 03 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19004 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 292.65 Completed a mise à jour des informati ultant Selection 6 20 21 12 28 12 18 13 07 12 lected rural areas ons sur les ménages bénéfi ciaires du TMDH Component 1: Building a s DRP82CIMAJ19001 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE1 ultant Selection 8 05 06 10 22 lected rural areas DRT12CIMAJ19005 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 292.65 Completed a mise à jour des informati ultant Selection 6 20 21 10 28 11 18 13 07 12 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19006 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 474.20 Completed a mise à jour des informati ultant Selection 6 20 21 10 28 12 18 13 07 20 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19007 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 298.07 Completed a mise à jour des informati ultant Selection 6 20 21 10 28 11 18 13 07 14 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19008 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 495.88 Completed a mise à jour des informati ultant Selection 6 20 21 11 28 12 18 13 07 20 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19009 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 303.49 Completed a mise à jour des informati ultant Selection 6 20 21 11 28 11 18 13 07 12 lected rural areas ons sur les ménages bénéfi ciaires du TMDH Component 1: Building a s DRP82CIMAJ19002 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE2 ultant Selection 8 05 06 10 22 lected rural areas DRT12CIMAJ19010 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 308.91 Completed a mise à jour des informati ultant Selection 6 20 21 10 28 11 18 13 07 12 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19011 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 509.42 Completed a mise à jour des informati ultant Selection 6 20 21 10 28 12 18 13 07 14 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRK12CIASTMDH19004 / C Component 1: Building a s ONSULTANT INDIVIDUEL AC Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2021-02- IDA / D4340 afety net for the poor in se Post Limited 6,250.00 5,114.93 Signed COMPAGNATEUR SPECIALIS ultant Selection 2 19 17 03 07 10 11 26 10 lected rural areas E DANS LE CADRE DU TMD H DRT12CIMAJ19012 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 468.78 Completed a mise à jour des informati ultant Selection 6 20 21 10 28 12 18 13 07 14 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19013 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 292.65 Completed a mise à jour des informati ultant Selection 6 20 21 12 28 12 18 13 07 14 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19014 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 300.00 476.91 Completed a mise à jour des informati ultant Selection 6 20 21 10 28 12 18 13 07 14 lected rural areas ons sur les ménages bénéfi ciaires du TMDH Component 1: Building a s DRP82CIMAJ19003 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVMBE3 ultant Selection 8 05 06 10 22 lected rural areas DRK12CIASTMDH19005 / C Component 1: Building a s ONSULTANT INDIVIDUEL AC Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2021-02- IDA / D4340 afety net for the poor in se Post Limited 6,250.00 5,114.93 Signed COMPAGNATEUR SPÉCIALIS ultant Selection 2 19 17 03 07 10 11 26 10 lected rural areas É DANS LE CADRE DU TMD H DRK12CIASTMDH19006 / C Component 1: Building a s ONSULTANT INDIVIDUEL AC Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2021-02- IDA / D4340 afety net for the poor in se Post Limited 6,250.00 5,112.95 Signed COMPAGNATEUR SPECIALIS ultant Selection 2 19 17 03 07 10 11 26 10 lected rural areas E DANS LE CADRE DU TMD H Component 1: Building a s DRP82CIMAJ19004 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE4 ultant Selection 8 05 06 10 22 lected rural areas DRK12CIASTMDH19007 / C Component 1: Building a s ONSULTANT INDIVIDUEL AC Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2021-02- IDA / D4340 afety net for the poor in se Post Limited 6,250.00 5,112.95 Signed COMPAGNATEUR SPÉCIALIS ultant Selection 2 19 17 03 07 10 11 26 10 lected rural areas E DANS LE CADRE DU TMD H DRK12CIASTMDH19008 / C Component 1: Building a s ONSULTANT INDIVIDUEL AC Individual Cons 2019-12-1 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2021-02- IDA / D4340 afety net for the poor in se Post Limited 6,250.00 5,112.95 Signed COMPAGNATEUR SPÉCIALIS ultant Selection 2 19 17 03 07 10 11 26 10 lected rural areas É DANS LE CADRE DU TMD H Component 1: Building a s DRP82CIMAJ19005 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE5 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19006 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE6 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19007 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVMBE7 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19008 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVMBE8 ultant Selection 8 05 06 10 22 lected rural areas DRT12CIOS19001 / Opérat Component 1: Building a s Individual Cons 2019-12-1 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,138.46 Signed ultant Selection 6 13 21 12 28 13 18 15 17 du TMDH lected rural areas Component 1: Building a s DRP82CIMAJ19009 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE9 ultant Selection 8 05 06 10 22 lected rural areas DRT12CIOS19002 / Opérat Component 1: Building a s Individual Cons 2019-12-1 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,138.46 Signed ultant Selection 6 13 21 12 28 13 18 15 17 du TMDH lected rural areas DRT12CIOS19003 / Opérat Component 1: Building a s Individual Cons 2019-12-1 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,138.46 Signed ultant Selection 6 13 21 12 28 13 18 15 17 du TMDH lected rural areas DRT12CIOS19004 / Opérat Component 1: Building a s Individual Cons 2019-12-1 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,133.89 Signed ultant Selection 6 13 21 12 28 13 18 15 17 du TMDH lected rural areas Component 1: Building a s DRP82CIMAJ19010 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE10 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19011 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE11 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19012 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE12 ultant Selection 8 05 06 10 22 lected rural areas DRT11CIOS19001 / Opérat Component 1: Building a s Individual Cons 2019-12-1 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,129.79 Signed ultant Selection 6 13 21 12 28 13 18 15 17 de l'ACTP lected rural areas DRT11CIOS19002 / Opérat Component 1: Building a s Individual Cons 2019-12-1 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,129.79 Signed ultant Selection 6 13 21 12 28 13 18 15 17 de l'ACTP lected rural areas DRA12CISOMAJ19012 / MI Component 1: Building a s SE A JOUR DES INFORMATI Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 510.00 526.42 Signed ONS DES MENAGES BENEF ultant Selection 8 20 03 17 06 10 10 25 24 lected rural areas ICIAIRES TMDH DISTRICT T OAMASINA II ET MAHANOR O DRT11CIOS19003 / Opérat Component 1: Building a s Individual Cons 2019-12-1 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,129.79 Signed ultant Selection 6 13 21 12 28 13 18 15 17 de l'ACTP lected rural areas DRT11CIOS19004 / Opérat Component 1: Building a s Individual Cons 2019-12-1 2020-01- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,129.79 Signed ultant Selection 6 13 21 12 28 13 18 15 17 de l'ACTP lected rural areas Component 1: Building a s DRP82CIMAJ19013 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE13 ultant Selection 8 05 06 10 22 lected rural areas DRT11CIOS19005 / Opérat Component 1: Building a s Individual Cons 2019-12-1 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2022-02- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,129.79 Signed ultant Selection 6 13 21 12 11 13 15 15 07 de l'ACTP lected rural areas DRT11CIOS19006 / Opérat Component 1: Building a s Individual Cons 2019-12-1 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-02- 2020-02- 2022-02- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,138.46 Signed ultant Selection 6 13 21 12 11 13 15 15 07 de l'ACTP lected rural areas Component 1: Building a s DRP82CIMAJ19014 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE14 ultant Selection 8 05 06 10 22 lected rural areas DRA12CISOMAJ19013 / MI Component 1: Building a s SE A JOUR DES INFORMATI Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 510.00 504.32 Signed ONS DES MENAGES BENEF ultant Selection 8 20 03 03 06 10 10 25 24 lected rural areas ICIAIRES TMDH DISTRICT T OAMASINA II ET MAHANOR O DRA12CISOMAJ19014 / MI Component 1: Building a s SE A JOUR DES INFORMATI Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 510.00 501.48 Signed ONS DES MENAGES BENEF ultant Selection 8 20 03 04 06 10 10 25 24 lected rural areas ICIAIRES TMDH DISTRICT T OAMASINA II ET MAHANOR O Component 1: Building a s DRP82CIMAJ19015 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE15 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19026 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA1 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19016 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOVOMBE16 ultant Selection 8 05 06 10 22 lected rural areas DRT11CIAS19001 / Accom Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 6,000.00 5,451.49 Signed ultant Selection 6 07 21 18 28 07 18 08 17 e cadre de l’ACTP lected rural areas Component 1: Building a s DRP82CIMAJ19027 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA2 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19017 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOASARY1 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19028 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA3 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19018 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOASARY2 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19029 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA4 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19019 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOASARY3 ultant Selection 8 05 06 10 22 lected rural areas DRA12CIOS19001 / Saisie des fiches de coresponsabil ité scolaires, des fiches de Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-01- 2021-01- présence, des états de paie IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,324.70 Signed ultant Selection 2 20 07 08 14 09 03 31 02 ments et mise à jour des in lected rural areas formations des bénéficiaire s du projet TMDH – ACT P d ans le progiciel MIS. DRT11CIAS19002 / Accom Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 6,000.00 5,663.50 Signed ultant Selection 6 07 21 16 28 01 18 03 17 e cadre de l’ACTP lected rural areas DRK11CIOSTMDH19001 / Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- OPÉRATEUR DE SAISIE DAN IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,081.41 Signed ultant Selection 2 18 17 18 24 04 14 08 08 S LE CADRE DU TMDH lected rural areas Component 1: Building a s DRP82CIMAJ19030 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA5 ultant Selection 8 05 06 10 22 lected rural areas DRT11CIAS19003 / Accom Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 6,000.00 5,610.50 Signed ultant Selection 6 07 21 17 28 01 18 03 17 e cadre de l'ACTP lected rural areas DRT11CIAS19004 / Accom Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 6,000.00 5,769.50 Signed ultant Selection 6 07 21 16 28 01 18 03 17 e cadre de l’ACTP lected rural areas DRT11CIAS19005 / Accom Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 6,000.00 5,769.50 Signed ultant Selection 6 07 21 16 28 07 18 08 17 e cadre de l'ACTP lected rural areas Component 1: Building a s DRP82CIMAJ19020 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOASARY4 ultant Selection 8 05 06 10 22 lected rural areas DRK11CIOSTMDH19002 / Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- OPÉRATEUR DE SAISIE DAN IDA / 57080 afety net for the poor in se Post Limited 5,000.00 2,078.75 Signed ultant Selection 2 18 17 18 24 04 14 08 08 S LE CADRE DU TMDH lected rural areas DRT11CIAS19006 / Accom Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 6,000.00 5,928.50 Signed ultant Selection 6 07 21 17 28 01 18 03 17 e cadre de l’ACTP lected rural areas DRK11CIOSTMDH19003 / Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2019-12- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- OPÉRATEUR DE SAISIE DAN IDA / 57080 afety net for the poor in se Post Limited 5,000.00 2,078.75 Signed ultant Selection 2 18 17 18 24 04 14 08 08 S LE CADRE DU TMDH lected rural areas DRT11CIAS19007 / Accom Component 1: Building a s Individual Cons 2019-12-1 2020-02- 2019-12- 2020-07- 2019-12- 2020-08- 2020-01- 2020-10- 2021-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 6,000.00 5,423.68 Signed ultant Selection 6 07 21 22 28 31 18 01 17 e cadre de l'ACTP lected rural areas Component 1: Building a s DRP82CIMAJ19021 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOASARY5 ultant Selection 8 05 06 10 22 lected rural areas DRT11CIAS19008 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2021-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 6,000.00 0.00 Canceled ultant Selection 6 21 28 18 17 e cadre de l’ACTP -Inclusio lected rural areas n Productive Component 1: Building a s DRP82CIMAJ19031 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA6 ultant Selection 8 05 06 10 22 lected rural areas DRT11CIAS19009 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2021-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 6,000.00 0.00 Canceled ultant Selection 6 21 28 18 17 e cadre de l'ACTP-Inclusion lected rural areas Productive DRK11CIOSTMDH19004 / Component 1: Building a s Individual Cons Pending Imple 2019-12-1 2019-12- 2019-12- 2020-01- 2021-01- OPÉRATEUR DE SAISIE DAN IDA / D4340 afety net for the poor in se Post Limited 5,000.00 0.00 ultant Selection mentation 2 17 24 14 08 S LE CADRE DU TMDH lected rural areas DRA11CIOS19002 / Saisie des fiches de coresponsabil ité scolaires, des fiches de Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-01- 2021-01- présence, des états de paie IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,324.70 Signed ultant Selection 2 20 07 08 14 09 03 31 02 ments et mise à jour des in lected rural areas formations des bénéficiaire s du projet TMDH – ACT P d ans le progiciel MIS. Component 1: Building a s DRP82CIMAJ19022 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOASARY6 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19032 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA7 ultant Selection 8 05 06 10 22 lected rural areas Page 21 Component 1: Building a s DRP82CIMAJ19023 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOASARY7 ultant Selection 8 05 06 10 22 lected rural areas DRA11CIOS19003 / Saisie des fiches de coresponsabil ité scolaires, des fiches de Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-01- 2021-01- présence, des états de paie IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,324.70 Signed ultant Selection 2 20 07 08 14 09 03 31 02 ments et mise à jour des in lected rural areas formations des bénéficiaire s du projet TMDH – ACT P d ans le progiciel MIS. Component 1: Building a s DRP82CIMAJ19024 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOASARY8 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19033 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA8 ultant Selection 8 05 06 10 22 lected rural areas DRA11CIOS19001 / Saisie des fiches de coresponsabil ité scolaires, des fiches de Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-01- 2021-01- présence, des états de paie IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,324.70 Signed ultant Selection 2 20 07 08 14 09 03 31 02 ments et mise à jour des in lected rural areas formations des bénéficiaire s du projet TMDH – ACT P d ans le progiciel MIS. Component 1: Building a s DRP82CIMAJ19025 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPAMBOASARY9 ultant Selection 8 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19034 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA9 ultant Selection 9 05 06 10 22 lected rural areas DRA12CIOS19003 / Saisie des fiches de coresponsabil Component 1: Building a s ité scolaires ET des états d Individual Cons 2019-12-0 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-01- 2021-01- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,324.70 Signed e paiements et mise à jour ultant Selection 2 20 07 08 14 09 03 31 02 lected rural areas des informations des bénéf iciaires du projet TMDH dan s le progiciel MIS. DRA12CIOS19002 / Saisie des fiches de coresponsabil Component 1: Building a s ité scolaires ET des états d Individual Cons 2019-12-0 2019-12- 2019-12- 2020-01- 2019-12- 2020-01- 2020-01- 2020-01- 2021-01- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,324.70 Signed e paiements et mise à jour ultant Selection 2 20 07 08 14 09 03 31 02 lected rural areas des informations des bénéf iciaires du projet TMDH dan s le progiciel MIS. DRK12CIMAJ19001 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 19 13 07 17 20 31 lected rural areas DONNEES DES MENAGES T MDH DRA12CISOCOP19001 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 32.31 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent Bénéficiares TMDH - DI ST MAHANORO ET TOAMAS INA II DRA12CISOCOP19002 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 30.49 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19003 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 38.76 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19004 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 31.01 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19005 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 32.30 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19006 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 36.18 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19007 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 31.01 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 06 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19008 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 37.47 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRK12CIMAJ19002 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 03 13 07 17 20 31 lected rural areas DONNEES DES MENAGES T MDH DRA12CISOCOP19009 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 36.18 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19010 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 29.72 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 17 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19011 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 33.59 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19012 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 36.18 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19013 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 27.13 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19014 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 27.13 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19015 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 27.13 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19016 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 27.13 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19017 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 31.01 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19018 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 31.01 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19019 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 31.01 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19020 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 33.59 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19021 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 27.13 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19022 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 31.01 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 30 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19023 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 31.01 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CISOCOP19024 / Ré alisation des Mesures d’Acc Component 1: Building a s ompagnement  Coup de po Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2019-12- 2020-05- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 170.00 28.48 Signed uce (affirmation de soi, pla ultant Selection 8 14 03 17 10 22 31 05 28 lected rural areas nification) à chaque paiem ent - Bénéficiares TMDH - D IST MAHANORO ET TOAMA SINA II DRA12CIASSDPEI19001 / R éalisation des Mesures d’Ac Component 1: Building a s compagnement orientées à Individual Cons 2019-11-2 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- 2020-03- 2021-01- IDA / D4340 afety net for the poor in se Post Limited 5,700.00 4,816.00 Signed l’Education Parentale pour l ultant Selection 8 19 03 07 24 19 28 04 27 lected rural areas e Développement de la Peti te Enfance Intensifié (DPEI) des bénéficiaires du Progra mme TMDH DRA12CIASSDPEI19002 / R éalisation des Mesures d’Ac Component 1: Building a s compagnement orientées à Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2020-01- 2020-03- 2021-01- IDA / D4340 afety net for the poor in se Post Limited 5,700.00 4,817.87 Signed l’Education Parentale pour l ultant Selection 8 19 03 07 24 19 28 04 27 lected rural areas e Développement de la Peti te Enfance Intensifié (DPEI) des bénéficiaires du Progra mme TMDH DRA12CIASSDPEI19003 / R éalisation des Mesures d’Ac Component 1: Building a s compagnement orientées à Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2020-01- 2020-03- 2021-01- IDA / D4340 afety net for the poor in se Post Limited 5,700.00 4,832.08 Signed l’Education Parentale pour l ultant Selection 8 19 03 07 24 19 28 04 27 lected rural areas e Développement de la Peti te Enfance Intensifié (DPEI) des bénéficiaires du Progra mme TMDH DRA12CIASSDPEI19004 / R éalisation des Mesures d’Ac Component 1: Building a s compagnement orientées à Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2020-01- 2020-03- 2021-01- IDA / D4340 afety net for the poor in se Post Limited 5,700.00 4,827.19 Signed l’Education Parentale pour l ultant Selection 8 19 03 07 24 19 28 04 27 lected rural areas e Développement de la Peti te Enfance Intensifié (DPEI) des bénéficiaires du Progra mme TMDH DRA12CIASSDPEI19005 / R éalisation des Mesures d’Ac Component 1: Building a s compagnement orientées à Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2020-01- 2020-03- 2021-01- IDA / D4340 afety net for the poor in se Post Limited 5,700.00 4,841.43 Signed l’Education Parentale pour l ultant Selection 8 19 03 07 24 19 28 04 27 lected rural areas e Développement de la Peti te Enfance Intensifié (DPEI) des bénéficiaires du Progra mme TMDH DRA12CIASSIP19001 / Réa lisation des Mesures d’Acco mpagnement orientées à l' Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- INCLUSION productive des IDA / D4340 afety net for the poor in se Post Limited 5,700.00 4,841.43 Signed ultant Selection 8 19 03 30 24 04 28 22 27 bénéficiaires du Programm lected rural areas e TMDH ,Développement bi en être de la famille , AVEC et coup de pouce DRA12CIASSIP19002 / Réa lisation des Mesures d’Acco mpagnement orientées à l' Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2021-01- INCLUSION productive des IDA / D4340 afety net for the poor in se Post Limited 5,700.00 4,840.12 Signed ultant Selection 8 19 03 29 24 04 28 22 27 bénéficiaires du Programm lected rural areas e TMDH ,Développement bi en être de la famille , AVEC et coup de pouce DRA11CIASSDPEIIP19002 / Réalisation des Mesures d’ Accompagnement orientée Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- s à l’Education Parentale p IDA / D4340 afety net for the poor in se Post Limited 6,000.00 5,362.31 Signed ultant Selection 8 07 03 10 24 09 10 23 09 our le Développement de l lected rural areas a Petite Enfance Intensifié ( DPEI) , DBE , AVEC, Coup d e POUCE, IP des bénéficiair es du Programme ACT P DRA11CIASSDPEIIP19003 / Réalisation des Mesures d’ Accompagnement orientée Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- s à l’Education Parentale p IDA / D4340 afety net for the poor in se Post Limited 6,000.00 5,160.83 Signed ultant Selection 8 07 03 10 24 09 10 23 09 our le Développement de l lected rural areas a Petite Enfance Intensifié ( DPEI) , DBE , AVEC, Coup d e POUCE, IP des bénéficiair es du Programme ACT P DRA11CIASSDPEIIP19004 / Réalisation des Mesures d’ Accompagnement orientée Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- s à l’Education Parentale p IDA / D4340 afety net for the poor in se Post Limited 6,000.00 4,990.36 Signed ultant Selection 8 07 03 10 24 09 10 23 09 our le Développement de l lected rural areas a Petite Enfance Intensifié ( DPEI) , DBE , AVEC, Coup d e POUCE, IP des bénéficiair es du Programme ACT P DRA11CIASSDPEIIP19001 / Réalisation des Mesures d’ Accompagnement orientée Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-03- 2019-12- 2020-04- 2020-01- 2020-04- 2021-01- s à l’Education Parentale p IDA / D4340 afety net for the poor in se Post Limited 6,000.00 5,163.93 Signed ultant Selection 8 07 03 10 24 09 10 23 09 our le Développement de l lected rural areas a Petite Enfance Intensifié ( DPEI) , DBE , AVEC, Coup d e POUCE, IP des bénéficiair es du Programme ACT P DRK12CIMAJ19003 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 03 13 07 17 20 21 lected rural areas DONNÉES DES MÉNAGES T MDH DRK12CIMAJ19004 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 03 13 07 17 20 31 lected rural areas DONNEES DES MENAGES T MDH DRK12CIMAJ19005 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 18 10 18 13 07 17 20 31 lected rural areas DONNEES DES MENAGES T MDH DRK12CIMAJ19006 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 03 13 07 17 20 31 lected rural areas DONNÉES DES MENAGES T MDH Component 1: Building a s DRP82CIMAJ19035 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA9 ultant Selection 9 05 06 10 22 lected rural areas DRK12CIMAJ19007 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons Under Impleme 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2019-12- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 0.00 GE DE LA MISE A JOUR DES ultant Selection ntation 5 19 10 21 13 17 31 lected rural areas DONNÉES DES MÉNAGES T MDH DRK12CIMAJ19008 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-04- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 03 13 07 17 20 31 lected rural areas DONNÉES DES MÉNAGES T MDH DRK12CIMAJ19009 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 03 13 07 17 20 31 lected rural areas DONNEES DES MENAGES T MDH DRK12CIMAJ19010 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 03 13 07 17 20 31 lected rural areas DONNÉES DES MÉNAGES T MDH Page 22 DRK12CIMAJ19011 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 03 13 07 17 20 31 lected rural areas DONNES DES MÉNAGES TM DH DRP82ASIP20001 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- PAGNATEURIPDRPAMBOVO IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,487.05 Signed ultant Selection 9 19 18 04 19 26 08 02 07 MBE1 lected rural areas DRK12CIMAJ19012 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 03 13 07 17 20 31 lected rural areas DONNÉES DES MÉNAGES T MDH DRK12CIMAJ19013 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 25 13 26 17 27 31 lected rural areas DONNÉES DES MÉNAGES T MDH DRP82ASIP20002 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- PAGNATEURIPDRPAMBOVO IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,487.05 Signed ultant Selection 9 19 18 04 19 26 08 02 07 MBE2 lected rural areas DRP82ASIP20003 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- PAGNATEURIPDRPAMBOVO IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,487.05 Signed ultant Selection 9 19 18 04 19 26 08 02 07 MBE3 lected rural areas DRK12CIMAJ19014 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 03 13 07 17 20 31 lected rural areas DONNÉES DES MÉNAGES T MDH Component 1: Building a s DRP82CIMAJ19036 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA11 ultant Selection 9 05 06 10 22 lected rural areas DRK12CIMAJ19015 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2019-12- 2020-02- 2019-12- 2020-02- 2019-12- 2020-02- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 500.00 358.75 Signed GE DE LA MISE A JOUR DES ultant Selection 5 19 10 07 13 07 17 20 31 lected rural areas DONNÉES DES MÉNAGES T MDH DRP82ASIP20004 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- PAGNATEURIPDRPAMBOVO IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,483.81 Signed ultant Selection 9 19 18 04 19 26 08 02 07 MBE4 lected rural areas Component 1: Building a s DRP82CIMAJ19037 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBELOHA12 ultant Selection 9 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19038 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE1 ultant Selection 9 05 06 10 22 lected rural areas DRP82ASIP20005 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- PAGANTEURIPDRPAMBOVO IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,483.81 Signed ultant Selection 9 19 18 04 19 12 08 02 07 MBE5 lected rural areas Component 1: Building a s DRP82CIMAJ19039 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE2 ultant Selection 9 05 06 10 22 lected rural areas DRP82ASIP20006 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-05- 2019-12- 2020-05- 2020-01- 2020-05- 2021-03- PAGNATEURIPDRPAMBOVO IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,941.88 Signed ultant Selection 9 19 18 12 19 13 08 14 07 MBE6 lected rural areas Component 1: Building a s DRP82CIMAJ19040 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE3 ultant Selection 9 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19041 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2020-06- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE4 ultant Selection 9 05 06 10 22 lected rural areas DRP82ASIP20007 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- PAGNATEURIPDRPAMBOAS IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,486.11 Signed ultant Selection 9 19 18 04 19 12 08 02 07 ARY1 lected rural areas Component 1: Building a s DRP82CIMAJ19043 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE6 ultant Selection 9 05 06 10 22 lected rural areas DRP82ASIP20008 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-04- 2019-12- 2020-05- 2020-01- 2020-05- 2021-03- PAGNATEURIPDRPAMBOAS IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,943.82 Signed ultant Selection 9 19 18 17 19 13 08 14 07 ARY2 lected rural areas Component 1: Building a s DRP82CIMAJ19044 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE7 ultant Selection 9 05 06 10 22 lected rural areas DRP82ASIP20009 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-04- 2019-12- 2020-05- 2020-01- 2020-05- 2021-03- PAGNATEURIPDRPAMBOAS IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,943.82 Signed ultant Selection 9 19 18 17 19 13 08 14 07 ARY3 lected rural areas Component 1: Building a s DRP82CIMAJ19045 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE8 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19001 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 25.82 Completed ultant Selection 9 19 04 16 11 17 01 18 29 20 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82CIMAJ19046 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE9 ultant Selection 9 05 06 10 22 lected rural areas DRP82ASMACC20001 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,511.08 Signed ultant Selection 9 19 18 05 19 12 08 02 07 AMBOVOMBE1 lected rural areas Component 1: Building a s DRP82CIMAJ19047 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE10 ultant Selection 9 05 06 10 22 lected rural areas DRP82ASMACC20002 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,511.08 Signed ultant Selection 9 19 18 05 19 12 08 02 07 AMBOVOMBE2 lected rural areas Component 1: Building a s DRP82CIMAJ19049 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE12 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19002 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.63 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20003 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,511.08 Signed ultant Selection 9 19 18 05 19 12 08 02 07 AMBOVOMBE3 lected rural areas Component 1: Building a s DRP82CIMAJ19050 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE13 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19003 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.63 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82CIMAJ19051 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE14 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19004 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.63 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20004 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,511.08 Signed ultant Selection 9 19 18 05 19 12 08 02 07 AMBOVOMBE4 lected rural areas DRK12CISOCOP19005 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.63 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRK12CISOCOP19006 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.63 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82CIMAJ19053 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE16 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19007 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20005 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,511.08 Signed ultant Selection 9 19 18 05 19 12 08 02 07 AMBOVOMBE5 lected rural areas Component 1: Building a s DRP82CIMAJ19054 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBEKILY1 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19008 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82CIMAJ19055 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBEKILY2 ultant Selection 9 05 06 10 22 lected rural areas DRP82ASMACC20006 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,511.08 Signed ultant Selection 9 19 18 05 19 12 08 02 07 AMBOVOMBE6 lected rural areas Component 1: Building a s DRP82CIMAJ19056 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBEKILY3 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19009 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82CIMAJ19057 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBEKILY4 ultant Selection 9 05 06 10 22 lected rural areas DRP82ASMACC20007 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,511.08 Signed ultant Selection 9 19 18 05 19 12 08 02 07 AMBOASARY1 lected rural areas DRK12CISOCOP19010 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 16 01 18 29 RGE DU COUP DE POUCE lected rural areas DRK12CISOCOP19011 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.74 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRK12CISOCOP19012 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 25.86 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82CIMAJ19059 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBEKILY6 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19013 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.74 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82CIMAJ19060 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBEKILY7 ultant Selection 9 05 06 10 22 lected rural areas DRP82ASMACC20008 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,511.08 Signed ultant Selection 9 19 18 05 19 12 08 02 07 AMBOASARY2 lected rural areas DRK12CISOCOP19014 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82CIMAJ19061 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBEKILY8 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19015 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRK12CISOCOP19016 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-06- 2019-12- 2020-06- 2020-01- 2020-06- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 56.96 Signed ultant Selection 9 19 04 12 11 12 01 17 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20009 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,511.08 Signed ultant Selection 9 19 18 05 19 12 08 02 07 AMBOASARY3 lected rural areas Component 1: Building a s DRP82CIMAJ19062 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBEKILY9 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19017 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.82 Signed ultant Selection 9 07 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82CIMAJ19063 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBEKILY10 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19018 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82CIMAJ19064 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBEKILY11 ultant Selection 9 05 06 10 22 lected rural areas DRK12CISOCOP19019 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.74 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRK12CISOCOP19020 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRK12CISOCOP19021 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.74 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20010 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,530.79 Signed ultant Selection 9 19 18 05 19 12 08 02 07 BELOHA1 lected rural areas DRK12CISOCOP19022 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20011 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,538.62 Signed ultant Selection 9 19 18 05 19 12 08 02 07 BELOHA2 lected rural areas DRK12CISOCOP19023 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20012 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,123.00 Signed ultant Selection 9 19 18 10 19 17 08 22 07 BELOHA3 lected rural areas DRK12CISOCOP19024 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.74 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20013 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,529.44 Signed ultant Selection 9 19 18 05 19 12 08 02 07 TSIHOMBE1 lected rural areas DRK12CISOCOP19025 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRK12CISOCOP19026 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20014 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,529.44 Signed ultant Selection 9 19 18 05 19 12 08 02 07 TSIHOMBE2 lected rural areas DRK12CISOCOP19027 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20015 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,529.44 Signed ultant Selection 9 19 18 05 19 12 08 02 07 TSIHOMBE3 lected rural areas DRK12CISOCOP19028 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Page 23 DRP82ASMACC20016 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,529.44 Signed ultant Selection 9 19 18 05 19 12 08 02 07 BEKILY1 lected rural areas DRK12CISOCOP19029 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRK12CISOCOP19030 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20017 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,529.44 Signed ultant Selection 9 19 18 05 19 12 08 02 07 BEKILY2 lected rural areas DRK12CISOCOP19031 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRK12CISOCOP19032 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRP82ASMACC20018 / AC Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-04- 2021-03- COMPAGNATEURMACCDRP IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,536.87 Signed ultant Selection 9 19 18 05 19 12 08 02 07 BEKILY3 lected rural areas DRK12CISOCOP19033 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.85 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82ASIP20010 / ACCOM Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-03- 2021-03- IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,536.33 Signed PAGNATEURIPDRPBELOHA1 ultant Selection 9 19 18 04 19 13 08 31 07 lected rural areas DRK12CISOCOP19034 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.69 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas DRK12CISOCOP19035 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 82.82 Signed ultant Selection 9 19 04 16 11 17 01 18 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82ASIP20011 / ACCOM Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-03- 2021-03- IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,536.33 Signed PAGNATEURIPDRPBELOHA2 ultant Selection 9 19 18 04 19 13 08 31 07 lected rural areas DRK12CISOCOP19036 / CO Component 1: Building a s Individual Cons 2019-11-2 2020-02- 2019-12- 2020-06- 2019-12- 2020-06- 2020-01- 2020-06- 2020-06- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 25.88 Signed ultant Selection 9 19 04 12 11 12 01 17 29 RGE DU COUP DE POUCE lected rural areas Component 1: Building a s DRP82ASIP20012 / ACCOM Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-03- 2021-03- IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,536.33 Signed PAGNATEURIPDRPBELOHA3 ultant Selection 9 19 18 04 19 13 08 31 07 lected rural areas DRP82ASIP20013 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-03- 2021-03- PAGNATEURIPDRPTSIHOMB IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,544.29 Signed ultant Selection 9 19 18 04 19 13 08 31 07 E1 lected rural areas DRP82ASIP20014 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-03- 2021-03- PAGNATEURIPDRPTSIHOMB IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,544.29 Signed ultant Selection 9 19 18 04 19 13 08 31 07 E2 lected rural areas DRP82ASIP20015 / ACCOM Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-03- 2019-12- 2020-03- 2020-01- 2020-03- 2021-03- PAGNATEURIPDRPTSIHOMB IDA / D4340 afety net for the poor in se Post Limited 5,000.00 3,546.59 Signed ultant Selection 9 19 18 04 19 13 08 31 07 E3 lected rural areas Component 1: Building a s DRP82ASIP20016 / ACCOM Individual Cons 2019-11-2 2019-12- 2019-12- 2020-05- 2019-12- 2020-05- 2020-01- 2020-05- 2021-03- IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,712.15 Signed PAGNATEURIPDRPBEKILY1 ultant Selection 9 19 18 11 19 14 08 27 07 lected rural areas Component 1: Building a s DRP82ASIP20017 / ACCOM Individual Cons Under Impleme 2019-11-2 2019-12- 2019-12- 2019-12- 2020-01- 2021-03- IDA / D4340 afety net for the poor in se Post Limited 5,000.00 0.00 PAGNATEURIPDRPBEKILY2 ultant Selection ntation 9 19 18 19 08 07 lected rural areas DRU11CIAS19001 / Accom pagnateur spécialisé dans l Component 1: Building a s Individual Cons 2020-02-0 2020-01- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2020-05- 2022-03- e cadre de l'ACTP - Inclusio IDA / D4340 afety net for the poor in se Post Limited 10,000.00 7,864.93 Signed ultant Selection 3 14 13 23 05 10 22 01 22 n économique, Développe lected rural areas ment et Bien être de la fam ille - District Ankazoabo - L OT 01 DRU11CIAS19004 / Accom pagnateur spécialisé dans l Component 1: Building a s Individual Cons 2020-02-0 2020-01- 2020-02- 2020-07- 2020-03- 2020-08- 2020-03- 2020-08- 2022-03- e cadre de l'ACTP - Inclusio IDA / D4340 afety net for the poor in se Post Limited 10,000.00 4,641.69 Signed ultant Selection 3 14 13 20 05 17 22 29 22 n économique, Développe lected rural areas ment et Bien être de la fam ille - District Ankazoabo - L OT 04 DRU11CIAS19002 / Accom pagnateur spécialisé dans l Component 1: Building a s Individual Cons 2020-02-0 2020-01- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2020-05- 2022-03- e cadre de l'ACTP - Inclusio IDA / D4340 afety net for the poor in se Post Limited 10,000.00 6,990.64 Signed ultant Selection 3 14 13 23 05 10 22 01 22 n économique, Développe lected rural areas ment et Bien être de la fam ille - District Ankazoabo - L OT 02 DRU11CIOS19001 / Opérat Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-01- 2020-12- 2020-12- eur de saisie dans de cadre IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,307.53 Completed ultant Selection 9 16 14 18 19 15 07 17 31 16 de l'ACTP lected rural areas DRU11CIOS19003 / Opérat Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2020-04- 2019-12- 2020-05- 2020-01- 2020-05- 2020-12- 2020-09- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 5,000.00 781.44 Completed ultant Selection 9 16 14 30 19 05 07 06 31 03 de l'ACTP lected rural areas DRU11CIOS19002 / Opérat Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2020-04- 2019-12- 2020-04- 2020-01- 2020-04- 2020-12- 2020-12- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 5,000.00 1,724.82 Completed ultant Selection 9 16 14 02 19 06 07 11 31 16 de l'ACTP lected rural areas DRU12CIOS19004 / Opérat Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2020-04- 2019-12- 2020-05- 2020-01- 2020-05- 2020-12- 2020-08- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 5,000.00 781.44 Completed ultant Selection 9 16 14 30 19 05 07 06 31 29 du TMDH lected rural areas DRU12CIOS19001 / OPÉRA Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-01- 2020-12- 2020-12- TEUR DE SAISIE DANS LE C IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,307.53 Completed ultant Selection 9 16 14 18 19 15 07 17 31 16 ADRE DU TMDH lected rural areas DRU12CIOS19003 / Opérat Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2019-12- 2019-12- 2020-04- 2020-01- 2020-04- 2020-12- 2020-12- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 5,000.00 1,698.69 Completed ultant Selection 9 16 14 18 19 17 07 18 31 16 du TMDH lected rural areas DRU12CIAS19001 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2022-01- 2020-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 10,000.00 4,550.42 Completed ultant Selection 6 21 06 10 13 18 24 07 24 16 e cadre du TMDH - Inclusio lected rural areas n Productive DRU12CIAS19010 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2022-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 10,000.00 1,916.06 Terminated ultant Selection 6 21 06 17 13 18 24 07 24 e cadre du TMDH-Inclusion lected rural areas Productive DRU12CIAS19002 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2022-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 10,000.00 4,584.78 Terminated ultant Selection 6 21 06 13 13 18 24 07 24 e cadre du TMDH - Inclusio lected rural areas n Productive DRU12CIAS19009 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2022-01- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 10,000.00 4,816.01 Terminated ultant Selection 6 21 06 10 13 18 24 11 24 e cadre du TMDH-Inclusion lected rural areas Productive DRU12CIAS19003 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2022-01- 2020-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 10,000.00 4,673.40 Completed ultant Selection 6 21 06 10 13 18 24 07 24 16 e cadre du TMDH - Inclusio lected rural areas n Productive DRU12CIAS19008 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2022-01- 2020-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 10,000.00 4,971.00 Completed ultant Selection 6 21 06 10 13 18 24 07 24 18 e cadre du TMDH-Inclusion lected rural areas Productive DRU12CIAS19004 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2022-01- 2020-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 10,000.00 4,849.86 Completed ultant Selection 6 21 06 10 13 18 24 11 24 18 e cadre du TMDH - Inclusio lected rural areas n Productive DRU12CIAS19007 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2022-01- 2020-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 10,000.00 4,936.61 Completed ultant Selection 6 21 06 10 13 18 24 07 24 18 e cadre du TMDH-Inclusion lected rural areas Productive DRU12CIAS19005 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2022-01- 2020-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 10,000.00 4,932.14 Completed ultant Selection 6 21 06 10 13 18 24 07 24 18 e cadre du TMDH - Inclusio lected rural areas n Productive DRU12CISOCOP19001 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-02- 2020-01- 2020-05- 2020-01- 2020-05- 2020-01- 2020-05- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 29.81 Signed ultant Selection 4 14 07 07 20 08 27 26 25 RGE DU COUP DE POUCE lected rural areas DRU12CIAS19006 / Accom Component 1: Building a s Individual Cons 2019-12-1 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-03- 2022-01- 2020-12- pagnateur spécialisé dans l IDA / D4340 afety net for the poor in se Post Limited 10,000.00 4,790.87 Completed ultant Selection 6 21 06 14 13 18 24 11 24 18 e cadre du TMDH-Inclusion lected rural areas Productive DRU12CISOCOP19002 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-02- 2020-01- 2020-05- 2020-01- 2020-05- 2020-01- 2020-05- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 29.81 Signed ultant Selection 4 14 07 05 20 08 27 26 25 RGE DU COUP DE POUCE lected rural areas DRU12CISOCOP19003 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-02- 2020-01- 2020-05- 2020-01- 2020-05- 2020-01- 2020-05- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 24.63 Signed ultant Selection 4 14 07 07 20 08 27 26 25 RGE DU COUP DE POUCE lected rural areas DRU12CISOCOP19004 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-02- 2020-01- 2020-05- 2020-01- 2020-05- 2020-01- 2020-05- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 24.63 Signed ultant Selection 4 14 07 07 20 08 27 26 25 RGE DU COUP DE POUCE lected rural areas DRU12CISOCOP19005 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-02- 2020-01- 2020-05- 2020-01- 2020-05- 2020-01- 2020-05- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 24.63 Signed ultant Selection 4 14 07 07 20 08 27 26 25 RGE DU COUP DE POUCE lected rural areas DRU12CISOCOP19008 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-02- 2020-01- 2020-05- 2020-01- 2020-05- 2020-01- 2020-05- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 29.81 Signed ultant Selection 4 14 07 07 20 08 27 26 25 RGE DU COUP DE POUCE lected rural areas DRU12CISOCOP19006 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-02- 2020-01- 2020-05- 2020-01- 2020-05- 2020-01- 2020-05- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 24.63 Signed ultant Selection 4 14 07 07 20 08 27 26 25 RGE DU COUP DE POUCE lected rural areas DRU12CIMAJ19001 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post Limited 850.00 677.07 Signed GE DE LA MISE A JOUR DES ultant Selection 9 21 06 07 10 17 17 27 17 lected rural areas DONNÉES DES MÉNAGES T MDH BETIOKY DRU12CIMAJ19006 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post Limited 850.00 822.62 Signed GE DE LA MISE A JOUR DES ultant Selection 9 21 06 07 10 17 17 27 17 lected rural areas DONNÉES DES MÉNAGES T MDH BETIOKY DRU12CIMAJ19007 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post Limited 850.00 798.89 Signed GE DE LA MISE A JOUR DES ultant Selection 9 21 06 07 10 17 17 27 17 lected rural areas DONNÉES DES MÉNAGES T MDH BETIOKY DRU12CIMAJ19002 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post Limited 850.00 744.64 Signed GE DE LA MISE A JOUR DES ultant Selection 9 21 06 07 10 17 17 27 17 lected rural areas DONNÉES DES MÉNAGES T MDH BETIOKY DRU12CIMAJ19008 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2020-01- 2020-03- 2020-01- 2020-03- 2020-01- 2020-03- 2020-03- IDA / D4340 afety net for the poor in se Post Limited 850.00 694.63 Signed GE DE LA MISE A JOUR DES ultant Selection 9 21 06 11 10 13 17 14 17 lected rural areas DONNÉES DES MÉNAGES T MDH BETIOKY DRU12CIMAJ19003 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post Limited 850.00 770.63 Signed GE DE LA MISE A JOUR DES ultant Selection 9 21 06 07 10 17 17 27 17 lected rural areas DONNÉES DES MÉNAGES T MDH BETIOKY DRU12CIMAJ19009 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post Limited 850.00 622.25 Terminated GE DE LA MISE A JOUR DES ultant Selection 9 21 06 07 10 17 17 27 17 lected rural areas DONNÉES DES MÉNAGES T MDH BETIOKY DRU12CIMAJ19004 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post Limited 850.00 725.41 Signed GE DE LA MISE A JOUR DES ultant Selection 9 21 06 07 10 17 17 27 17 lected rural areas DONNÉES DES MÉNAGES T MDH BETIOKY DRU12CIMAJ19010 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post Limited 850.00 731.65 Signed GE DE LA MISE A JOUR DES ultant Selection 9 21 06 07 10 07 17 27 17 lected rural areas DONNÉES DES MÉNAGES T MDH BETIOKY DRU12CIMAJ19005 / CONS Component 1: Building a s ULTANT INDIVIDUEL CHAR Individual Cons 2019-12-0 2019-12- 2020-01- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- IDA / D4340 afety net for the poor in se Post Limited 850.00 772.83 Signed GE DE LA MISE A JOUR DES ultant Selection 9 21 06 12 10 17 17 27 17 lected rural areas DONNÉES DES MÉNAGES T MDH BETIOKY DRU12CICMP19001 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,288.03 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19034 / Cons Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2020-01- 2020-01- 2020-04- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 0.00 Canceled ultant Selection 9 19 06 13 10 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19002 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,108.10 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19033 / Cons Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2020-01- 2020-01- 2020-04- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 0.00 Canceled ultant Selection 9 19 06 13 10 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19003 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,005.55 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19032 / Cons Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2020-01- 2020-01- 2020-04- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 0.00 Canceled ultant Selection 9 19 06 13 10 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19031 / Cons Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2020-01- 2020-01- 2020-04- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 0.00 Canceled ultant Selection 9 19 06 13 10 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19030 / Cons Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2020-01- 2020-01- 2020-04- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 0.00 Canceled ultant Selection 9 19 06 13 10 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19029 / Cons Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2020-01- 2020-01- 2020-04- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 0.00 Canceled ultant Selection 9 19 06 13 10 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19028 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 870.96 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19027 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,230.22 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19004 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,022.45 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19005 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 715.12 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19026 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-02- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 772.22 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19006 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,076.73 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19025 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 736.16 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19024 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 863.07 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19007 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,010.73 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19023 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 725.50 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19008 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 764.84 Completed ultant Selection 9 14 19 17 06 21 14 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19022 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 744.14 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19009 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 806.02 Completed ultant Selection 9 14 19 17 06 21 14 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19021 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 704.73 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19010 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,047.65 Completed ultant Selection 9 14 19 17 06 21 14 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II Page 24 DRU12CICMP19020 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 834.52 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19011 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,152.49 Completed ultant Selection 9 14 19 17 06 21 14 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19019 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 713.08 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19012 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 904.61 Completed ultant Selection 9 14 19 17 06 21 14 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19018 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 982.47 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19013 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 727.05 Completed ultant Selection 9 14 19 17 06 21 14 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19017 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,145.14 Completed ultant Selection 9 14 19 21 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19014 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 813.03 Completed ultant Selection 9 14 19 17 06 21 14 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19016 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,273.44 Completed ultant Selection 9 14 19 17 06 21 13 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19015 / Cons Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-08- ultant Individuel chargé du IDA / D4340 afety net for the poor in se Post Limited 1,750.00 1,044.38 Completed ultant Selection 9 14 19 17 06 21 14 27 10 05 ciblage des bénéficiaires T lected rural areas MDH Toliary II DRU12CICMP19035 / Cons Component 1: Building a s ultant Individuel Chef d'équ Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-07- IDA / D4340 afety net for the poor in se Post Limited 2,625.00 1,420.39 Completed ipe chargé du ciblage des b ultant Selection 9 14 19 17 06 20 14 27 10 29 lected rural areas énéficiaires TMDH Toliary II DRU12CICMP19037 / Cons Component 1: Building a s ultant Individuel chef d'équ Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-07- IDA / D4340 afety net for the poor in se Post Limited 2,625.00 1,404.81 Completed ipe chargé du ciblage des b ultant Selection 9 14 19 17 06 20 14 27 10 29 lected rural areas énéficiaires TMDH Toliary II DRU12CICMP19036 / Cons Component 1: Building a s ultant Individuel Chef d'équ Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- 2020-07- IDA / D4340 afety net for the poor in se Post Limited 2,625.00 1,441.17 Completed ipe chargé du ciblage des b ultant Selection 9 14 19 17 06 20 14 27 10 29 lected rural areas énéficiaires TMDH Toliary II DRU12CICMP19038 / Cons Component 1: Building a s ultant Individuel chef d'équ Individual Cons 2019-12-0 2020-01- 2019-12- 2020-02- 2020-01- 2020-02- 2020-01- 2020-02- 2020-04- IDA / D4340 afety net for the poor in se Post Limited 2,625.00 1,010.19 Terminated ipe chargé du ciblage des b ultant Selection 9 14 19 17 06 20 14 27 10 lected rural areas énéficiaires TMDH Toliary II DRK11CIOSACTP19002 / O Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2021-01- PÉRATEUR DE SAISIE DANS IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,078.75 Signed ultant Selection 9 18 14 18 21 31 11 08 05 LE CADRE DE L'ACTP lected rural areas DRU11CIAS19003 / Accom pagnateur spécialisé dans l Component 1: Building a s Individual Cons 2020-02-0 2020-01- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2020-05- 2022-03- e cadre de l'ACTP - Inclusio IDA / D4340 afety net for the poor in se Post Limited 10,000.00 6,165.19 Signed ultant Selection 3 14 13 23 05 10 22 01 22 n économique, Développe lected rural areas ment et Bien être de la fam ille - District Ankazoabo - L OT 03 DRU12CI0S19002 / OPÉRA Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2019-12- 2019-12- 2020-08- 2020-01- 2020-08- 2020-12- 2020-12- TEUR DE SAISIE DANS LE C IDA / D4340 afety net for the poor in se Post Limited 5,000.00 830.30 Completed ultant Selection 9 16 14 18 19 17 07 25 31 16 ADRE DU TMDH lected rural areas DRU12CIOS19002 / Opérat Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2019-12- 2019-12- 2020-01- 2020-01- 2020-02- 2020-01- 2020-08- 2020-12- eur de saisie dans le cadre IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,307.53 Completed ultant Selection 9 16 14 18 04 15 08 17 06 16 du TMDH lected rural areas DG20SCIDESSINATEUR200 Component 1: Building a s Individual Cons 2020-01-2 2020-11- 2020-01- 2021-03- 2020-02- 2021-06- 2020-03- 2021-06- 2020-12- 01 / Consultant Individuel - IDA / D4340 afety net for the poor in se Post Limited 2,000.00 4,025.60 Signed ultant Selection 0 19 25 31 15 03 21 10 31 Dessinateur lected rural areas DG20CIEMSING2001 / Recr Component 2: Strengtheni Individual Cons 2020-01-2 2020-01- 2020-02- 2020-02- 2020-02- 2020-03- 2020-03- 2020-03- 2020-07- utement des membres de l' IDA / 57080 ng safety net administratio Post Limited 1,000.00 1,792.21 Signed ultant Selection 7 07 01 18 22 06 28 10 26 Equipe Mobile de Soutien - n, monitoring and social ac Ingénieur N°01 countability DG20CIEMSSO2001 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-01- 2020-02- 2020-01- 2020-02- 2020-02- 2020-03- 2020-02- 2020-07- IDA / 57080 Post Limited 1,000.00 1,911.42 Signed Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 07 01 07 22 03 28 05 26 Socio-Organisateur N°01 countability DG20CIEMSSO2002 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-01- 2020-02- 2020-01- 2020-02- 2020-02- 2020-03- 2020-02- 2020-07- IDA / 57080 Post Limited 1,000.00 1,922.08 Signed Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 07 01 07 22 03 28 07 26 Socio-Organisateur N°02 countability DG20CIEMSSO2003 / Recr Component 1: Building a s utement des membres de l' Individual Cons 2020-01-2 2020-01- 2020-02- 2020-02- 2020-02- 2020-03- 2020-03- 2020-03- 2020-07- IDA / D4340 afety net for the poor in se Post Limited 1,000.00 1,929.62 Signed Equipe Mobile de Soutien - ultant Selection 7 07 01 18 22 06 28 10 26 lected rural areas Socio-Organisateur N°03 DG20CIEMSSO2004 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- 2020-03- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 1,844.15 Signed Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 07 01 27 22 06 28 10 26 Socio-Organisateur N°04 countability DG20CIEMSSO2005 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- 2020-03- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 1,558.44 Signed Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 07 01 27 22 06 28 10 26 Socio-Organisateur N°05 countability DG20CIEMSSO2006 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- 2020-03- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 1,564.56 Signed Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 07 01 27 22 06 28 10 26 Socio-Organisateur N°06 countability DG20CIEMSSO2007 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- 2020-03- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 1,558.44 Signed Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 07 01 27 22 06 28 10 26 Socio-Organisateur N°07 countability DG20CIEMSSO2008 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-01- 2020-02- 2020-01- 2020-02- 2020-03- 2020-03- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 1,922.08 Signed Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 07 01 27 22 06 28 10 26 Socio-Organisateur N°08 countability DG20CIEMSSO2009 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-02- 2020-02- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 0.00 Canceled Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 01 22 28 26 Socio-Organisateur N°09 countability DG20CIEMSSO2010 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-02- 2020-02- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 0.00 Canceled Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 01 22 28 26 Socio-Organisateur N°10 countability DG20CIEMSSO2011 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-02- 2020-02- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 0.00 Canceled Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 01 22 28 26 Socio-Organisateur N°03 countability DG20CIEMSSO2012 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-02- 2020-02- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 0.00 Canceled Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 01 22 28 26 Socio-Organisateur N°12 countability DG20CIEMSSO2013 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-02- 2020-02- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 0.00 Canceled Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 01 22 28 26 Socio-Organisateur N°13 countability DG20CIEMSSO2014 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-02- 2020-02- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 0.00 Canceled Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 01 22 28 26 Socio-Organisateur N°14 countability DG20CIEMSSO2015 / Recr Component 2: Strengtheni utement des membres de l' ng safety net administratio Individual Cons 2020-01-2 2020-02- 2020-02- 2020-03- 2020-07- IDA / 57080 Post Limited 1,000.00 0.00 Canceled Equipe Mobile de Soutien - n, monitoring and social ac ultant Selection 7 01 22 28 26 Socio-Organisateur N°15 countability DG20CIEMSING2002 / Recr Component 2: Strengtheni Individual Cons 2020-01-2 2020-01- 2020-02- 2020-01- 2020-02- 2020-02- 2020-03- 2020-07- utement des membres de l' IDA / 57080 ng safety net administratio Post Limited 1,000.00 0.00 Canceled ultant Selection 7 07 01 07 22 03 28 26 Equipe Mobile de Soutien - n, monitoring and social ac Ingénieur N°02 countability DG20CIEMSING2003 / Recr Component 2: Strengtheni Individual Cons 2020-01-2 2020-02- 2020-02- 2020-03- 2020-07- utement des membres de l' IDA / 57080 ng safety net administratio Post Limited 1,000.00 0.00 Canceled ultant Selection 7 01 22 28 26 Equipe Mobile de Soutien - n, monitoring and social ac Ingénieur N°03 countability DG20CIEMSING2004 / Recr Component 2: Strengtheni Individual Cons 2020-01-2 2020-02- 2020-02- 2020-03- 2020-07- utement des membres de l' IDA / 57080 ng safety net administratio Post Limited 1,000.00 0.00 Canceled ultant Selection 7 01 22 28 26 Equipe Mobile de Soutien - n, monitoring and social ac Ingénieur N°04 countability DG20CIEMSING2005 / Recr Component 2: Strengtheni Individual Cons 2020-01-2 2020-02- 2020-02- 2020-03- 2020-07- utement des membres de l' IDA / 57080 ng safety net administratio Post Limited 1,000.00 0.00 Canceled ultant Selection 7 01 22 28 26 Equipe Mobile de Soutien - n, monitoring and social ac Ingénieur N°05 countability Component 1: Building a s DRP81CIMACC20001 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-05- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,234.30 Signed ACC PSRC1 ultant Selection 8 25 17 10 17 02 20 08 18 lected rural areas Component 1: Building a s DRP81CIMACC20002 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-05- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,234.30 Signed ACC PSRC2 ultant Selection 8 25 17 10 17 02 20 08 18 lected rural areas Component 1: Building a s DRP81CIMACC20003 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-05- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,233.69 Signed ACC PSRC3 ultant Selection 8 25 17 10 17 02 20 08 18 lected rural areas Component 1: Building a s DRP81CIMACC20004 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-05- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,233.69 Signed ACC PSRC4 ultant Selection 8 25 17 10 17 02 20 08 18 lected rural areas Component 1: Building a s DRP81CIMACC20005 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-05- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,233.69 Signed ACC PSRC5 ultant Selection 8 25 17 10 17 02 20 08 18 lected rural areas Component 1: Building a s DRP81CIMACC20006 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-05- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,233.69 Signed ACC PSRC6 ultant Selection 8 25 17 09 17 02 20 08 18 lected rural areas Component 1: Building a s DRP81CIMACC20007 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,324.70 Signed ACC PSRC7 ultant Selection 8 25 17 10 17 28 20 01 18 lected rural areas Component 1: Building a s DRP81CIMACC20008 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-04- 2020-02- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,324.70 Signed ACC PSRC8 ultant Selection 8 25 17 10 17 28 20 01 18 lected rural areas Component 1: Building a s DRP81CIMACC20009 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-04- 2020-02- 2020-04- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 1,162.35 Signed ACC PSRC9 ultant Selection 8 25 17 09 17 20 20 30 18 lected rural areas Component 1: Building a s DRP81CIMACC20010 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-04- 2020-02- 2020-04- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 1,162.35 Signed ACC PSRC10 ultant Selection 8 25 17 10 17 20 20 30 18 lected rural areas Component 1: Building a s DRP81CIMACC20011 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-02- 2020-02- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 0.00 Canceled ACC PSRC11 ultant Selection 8 25 17 17 20 18 lected rural areas Component 1: Building a s DRP81CIMACC20012 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-04- 2020-02- 2020-04- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 1,162.35 Signed ACC PSRC12 ultant Selection 8 25 17 10 17 20 20 30 18 lected rural areas Component 1: Building a s DRP81CIMACC20013 / CI M Individual Cons 2020-02-0 2020-02- 2020-02- 2020-04- 2020-02- 2020-04- 2020-02- 2020-04- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 2,500.00 2,324.70 Signed ACC PSRC13 ultant Selection 8 25 17 10 17 20 20 30 18 lected rural areas DRP82CIMAJ190053 / REC RUTEMENT DE 53 CONSULT Component 1: Building a s Individual Cons 2020-02-2 2019-12- 2020-03- 2020-02- 2020-03- 2020-03- 2020-04- 2020-03- 2020-04- ANTS INDIVIDUELS EN CHA IDA / D4340 afety net for the poor in se Post Limited 19,555.20 11,732.99 Signed ultant Selection 7 23 03 29 18 02 08 06 28 RGE DE LA MISE A JOUR DE lected rural areas S MÉNAGES BÉNÉFICIAIRES TMDH DRU13CICIB20001 / Presta tion de service de 50 Cons ultants Individuels de cibla Component 1: Building a s Individual Cons 2020-03-0 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- ge des Bénéficiaires dans l IDA / D4340 afety net for the poor in se Post Limited 10,416.67 219.56 Completed ultant Selection 4 02 06 06 09 06 09 11 21 25 es Communes d'Androka, A lected rural areas nkiliabo (District d'Ampanih y) et Tameantsoa (District de Betioky) - TMNC POST S ECHERESSE DRU13ASMACC20001 / Pre station de service de 10 Co nsultants Accompagnateur Component 1: Building a s s Spécialisés en mesures d' Individual Cons 2020-03-0 2020-03- 2020-03- 2020-04- 2020-03- 2020-04- 2020-03- 2020-05- 2020-09- 2020-09- IDA / D4340 afety net for the poor in se Post Limited 20,000.00 1,786.14 Completed accompagnement des Bén ultant Selection 4 10 09 16 13 24 20 01 16 29 lected rural areas éficiaires dans les Commun es d'Androka, Ankiliabo (Di strict Ampanihy) et Tamea ntsoa (District Betioky sud) - TMNC DRT12CIMAJ19015 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2020-02- IDA / D4340 afety net for the poor in se Post Limited 300.00 0.00 Canceled a mise à jour des informati ultant Selection 6 21 28 18 07 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19016 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2020-02- IDA / D4340 afety net for the poor in se Post Limited 300.00 0.00 Canceled a mise à jour des informati ultant Selection 6 21 28 18 07 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19017 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2020-02- IDA / D4340 afety net for the poor in se Post Limited 300.00 0.00 Canceled a mise à jour des informati ultant Selection 6 21 28 18 07 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19018 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2020-02- IDA / D4340 afety net for the poor in se Post Limited 300.00 0.00 Canceled a mise à jour des informati ultant Selection 6 21 28 18 07 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19019 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2020-02- IDA / D4340 afety net for the poor in se Post Limited 300.00 0.00 Canceled a mise à jour des informati ultant Selection 6 21 28 18 07 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRT12CIMAJ19020 / Consu Component 2: Strengtheni ltant individuel chargé de l ng safety net administratio Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2020-02- IDA / D4340 Post Limited 300.00 0.00 Canceled a mise à jour des informati n, monitoring and social ac ultant Selection 6 21 28 18 07 ons sur les ménages bénéfi countability ciaires du TMDH DRT12CIMAJ19021 / Consu Component 1: Building a s ltant individuel chargé de l Individual Cons 2019-12-1 2019-12- 2019-12- 2020-01- 2020-02- IDA / D4340 afety net for the poor in se Post Limited 300.00 0.00 Canceled a mise à jour des informati ultant Selection 6 21 28 18 07 lected rural areas ons sur les ménages bénéfi ciaires du TMDH DRP81CICIBLAGE20003 / R ecrutement de 23 Consulta nts Individuels chargé de ci Component 1: Building a s Individual Cons 2020-03-1 2020-01- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- 2020-03- blage et Enregistrement de IDA / D4340 afety net for the poor in se Post Limited 2,800.00 914.16 Signed ultant Selection 2 13 16 04 16 04 17 06 23 s bénéficiaires PSRC vague lected rural areas 2 dans les Communes Andr anobory, Sampona, Maroal opoty, Maroalomainty et Fa ux cap DRP81CIMACC20014 / Six (06) Consultants Individuel Component 1: Building a s s chargés d'accompagnem Individual Cons 2020-03-2 2020-02- 2020-03- 2020-04- 2020-03- 2020-04- 2020-04- 2020-05- 2020-08- IDA / D4340 afety net for the poor in se Post Limited 15,000.00 6,972.84 Signed ent des bénéficiaires PSRC ultant Selection 7 25 30 10 31 21 01 12 31 lected rural areas vague 2, dans les commun es Faux cap, Sampona, And ranobory, Maroalopoty et M aroalomainty. DG20ED_COVID_AGEX200 Component 3: Building the 1 / Prestation de services d institutional capacity for c e l’AGEX chargée de la sup 2020-04-1 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- IDA / D4340 oordination, monitoring an Post Direct Selection Direct 5,000.00 6,851.04 Signed ervision du ciblage des bén 0 08 17 08 01 25 30 d evaluation of the social p éficiaires des TMNC comme rotection syst em réponse au Covid19 – CUA 2ème arrondissement DG20ED_COVID_AGEX200 Component 3: Building the 3 / Prestation de services d institutional capacity for c e l’AGEX chargée de la sup 2020-04-1 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- IDA / D4340 oordination, monitoring an Post Direct Selection Direct 5,000.00 6,264.92 Signed ervision du ciblage des bén 0 08 17 08 01 25 30 d evaluation of the social p éficiaires des TMNC comme rotection syst em réponse au Covid19 – CUA 3ème arrondissement DG20ED_COVID_AGEX200 Component 3: Building the 4 / Prestation de services d institutional capacity for c e l’AGEX chargée de la sup 2020-04-1 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- IDA / D4340 oordination, monitoring an Post Direct Selection Direct 5,000.00 7,325.83 Signed ervision du ciblage des bén 0 08 17 08 01 25 30 d evaluation of the social p éficiaires des TMNC comme rotection syst em réponse au Covid19 – CUA 5ème arrondissement DG20ED_COVID_AGEX200 Component 3: Building the 6 / Prestation de services d institutional capacity for c e l’AGEX chargée de la sup 2020-04-1 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- IDA / D4340 oordination, monitoring an Post Direct Selection Direct 5,000.00 7,455.32 Signed ervision du ciblage des bén 0 08 17 08 01 25 30 d evaluation of the social p éficiaires des TMNC comme rotection syst em réponse au Covid19 – CUA 6ème arrondissement DG20ED_COVID_CABVALID Component 3: Building the 2001 / Prestation de servic institutional capacity for c es d’un cabinet chargé de l 2020-04-1 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- IDA / D4340 oordination, monitoring an Post Direct Selection Direct 35,000.00 2,853.91 Signed a validation et de la synchr 0 06 17 08 01 18 30 d evaluation of the social p onisation des données de r rotection syst em ecensement bénéficiaires d es TMNC comme réponse a u Covid19 Page 25 DRA20ED COVID19 AGEX 20001 / Prestation de l’AGE X chargée pour la mise en Component 1: Building a s œuvre et la supervision de 2020-04-1 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-06- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 7,300.00 7,084.65 Signed l’opération de recensement 6 14 23 22 30 23 04 lected rural areas des ménages bénéficiaires des TMNC comme réponse au Covid19 - CUT - 28 FKT - ARRONDISSEMENT ANJOM A ET MORARANO DRA20ED COVID19 AGEX 20002 / Prestation de l’AGE X chargée pour la mise en Component 1: Building a s œuvre et la supervision de 2020-04-1 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-06- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 4,100.00 3,985.70 Signed l’opération de recensement 6 14 23 21 30 23 04 lected rural areas des ménages bénéficiaires des TMNC comme réponse au Covid19 - CUT - 10 FKT - ARRONDISSEMENT ANKIRI HIRY DRA20ED COVID19 AGEX 20003 / Prestation de l’AGE X chargée pour la mise e n œuvre et la supervision d Component 1: Building a s 2020-04-1 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-06- e l’opération de recenseme IDA / D4340 afety net for the poor in se Post Direct Selection Direct 5,200.00 5,522.51 Signed 6 14 23 21 30 23 04 nt des ménages bénéficiair lected rural areas es des TMNC comme répo nse au Covid19 - 16 FKT - A RRONDISSEMENT ANKIRIHI RY ET COMMUNE SUBURB AINE DE TOAMASINA DRA20ED COVID19 AGEX 20004 / Prestation de l’AGE X chargée pour la mise e Component 1: Building a s n œuvre et la supervision d 2020-04-1 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-06- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 6,280.00 6,089.61 Signed e l’opération de recenseme 6 14 23 21 30 23 04 lected rural areas nt des ménages bénéficiair es des TMNC comme répo nse au Covid19 - CUT - 19 FKT - ARRONDISSEMENT M ORARANO DRA20ED COVID19 AGEX 20005 / Prestation de l’AGE X chargée pour la mise en Component 1: Building a s œuvre et la supervision de 2020-04-1 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-06- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 9,580.00 9,286.14 Signed l’opération de recensement 6 14 23 21 30 23 04 lected rural areas des ménages bénéficiaires des TMNC comme réponse au Covid19 - CUT 43 FKT - ARRONDISSEMENT TANAM BAO V ET AMBODIMANGA DRA20ED COVID19 AGEX 20006 / Prestation de l’AGE X chargée pour la mise en Component 1: Building a s œuvre et la supervision de 2020-04-1 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-06- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 7,930.00 7,688.03 Signed l’opération de recensement 6 14 23 21 30 23 04 lected rural areas des ménages bénéficiaires des TMNC comme réponse au Covid19 - CUT - 34 FKT - ARRONDISSEMENT ANKIRIH IRY ET AMBODIMANGA DRF20ED_COVID_AGEX 20 01 / Prestation de services Component 3: Building the de l’AGEX chargée de la su institutional capacity for c 2020-04-1 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- pervision du ciblage des bé IDA / D4340 oordination, monitoring an Post Direct Selection Direct 2,000.00 1,787.47 Signed 6 14 23 17 29 25 29 néficiaires des TMNC comm d evaluation of the social p e réponse au Covid19 – CU rotection syst em F – Arrondissement Andrain jato atsimo et Andrainjato avaratra DRF20ED_COVID_AGEX 20 04 / Prestation de services Component 1: Building a s de l’AGEX chargée de la su 2020-04-1 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 2,000.00 1,711.81 Signed pervision du ciblage des bé 6 14 23 16 29 24 29 lected rural areas néficiaires des TMNC comm e réponse au Covid19 – CU F - Arrondissement Tanana Ambony DRF20ED_COVID_AGEX 20 05 / Prestation de services de l’AGEX chargée de la su Component 1: Building a s 2020-04-1 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- pervision du ciblage des bé IDA / D4340 afety net for the poor in se Post Direct Selection Direct 5,000.00 4,398.69 Signed 6 14 23 16 29 25 29 néficiaires des TMNC comm lected rural areas e réponse au Covid19 – Dis trict de Lalangina – Axe Ala kamisy Ambohimaha DRF20ED _COVID_AGEX 2 006 / Prestation de service Component 1: Building a s s de l’AGEX chargée de la s 2020-04-1 2020-04- 2020-04- 2020-04- 2020-04- 2020-04- 2020-05- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 5,000.00 3,914.27 Signed upervision du ciblage des b 6 14 23 16 29 25 29 lected rural areas énéficiaires des TMNC com me réponse au Covid19 – D istrict de Lalangina Axe A mbalakely DG20ED_COVID_AGEX200 7 / Prestation de services d e l’AGEX chargée de la sup Component 1: Building a s ervision du ciblage des bén 2020-04-2 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 10,000.00 19,830.26 Signed éficiaires des TMNC comme 0 14 27 16 11 29 10 lected rural areas réponse au Covid19 – Anta nanarivo Atsimondrano : A NDOHARANOFOTSY, TANJO MBATO, ANKARAOBATO, A NDRANONAHOATRA DG20ED_COVID_AGEX200 8 / Prestation de services d e l’AGEX chargée de la sup ervision du ciblage des bén Component 1: Building a s éficiaires des TMNC comme 2020-04-2 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 10,000.00 19,435.96 Signed réponse au Covid19 – Anta 0 14 27 16 11 29 10 lected rural areas nanarivo Atsimondrano : A NOSIZATO ANDREFANA, A MPITATAFIKA, AMBOHIDRA PETO, ITAOSY, ALAKAMISY FENOARIVO, FIOMBONANA, ANKADIMANGA DG20ED_COVID_AGEX200 9 / Prestation de services d e l’AGEX chargée de la sup Component 1: Building a s 2020-04-2 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- ervision du ciblage des bén IDA / D4340 afety net for the poor in se Post Direct Selection Direct 10,000.00 15,295.48 Signed 0 14 27 16 11 30 10 éficiaires des TMNC comme lected rural areas réponse au Covid19 – Amb ohidratrimo : AMBOHITRIM ANJAKA, AMBOHIDRATRIMO , ANTEHIROKA DG20ED_COVID_AGEX201 0 / Prestation de services d e l’AGEX chargée de la sup Component 1: Building a s 2020-04-2 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- ervision du ciblage des bén IDA / D4340 afety net for the poor in se Post Direct Selection Direct 10,000.00 15,639.00 Signed 0 14 27 16 11 29 10 éficiaires des TMNC comme lected rural areas réponse au Covid19 – Amb ohidratrimo : ANOSIALA, A MBATOLAMPY, IVATO, TALA TAMATY DG20ED_COVID_AGEX201 1 / Prestation de services d e l’AGEX chargée de la sup Component 1: Building a s 2020-04-2 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- ervision du ciblage des bén IDA / D4340 afety net for the poor in se Post Direct Selection Direct 10,000.00 13,406.34 Signed 0 14 27 16 11 29 10 éficiaires des TMNC comme lected rural areas réponse au Covid19 – Anta nanarivo Avaradrano : SAB OTSY NAMEHANA, ANKADIK ELY ILAFY DG20ED_COVID_AGEX201 2 / Prestation de services d e l’AGEX chargée de la sup Component 1: Building a s 2020-04-2 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-07- ervision du ciblage des bén IDA / D4340 afety net for the poor in se Post Direct Selection Direct 10,000.00 18,103.08 Signed 0 14 27 16 11 29 10 éficiaires des TMNC comme lected rural areas réponse au Covid19 – Anta nanarivo Avaradrano : AMB OHIMANAMBOLA, ALASORA DG20ED_COVID_AGEX200 Component 3: Building the 5 / Prestation de services d institutional capacity for c e l’AGEX chargée de la sup 2020-04-1 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-06- IDA / D4340 oordination, monitoring an Post Direct Selection Direct 5,000.00 6,267.70 Signed ervision du ciblage des bén 0 08 17 08 01 25 30 d evaluation of the social p éficiaires des TMNC comme rotection syst em réponse au Covid19 – CUA 5ème et 6ème arrondissem ents DG20ED_COVID_AGEX200 2 / Prestation de services d Component 1: Building a s e l’AGEX chargée de la sup 2020-04-1 2020-04- 2020-04- 2020-04- 2020-05- 2020-04- 2020-06- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 5,000.00 6,737.25 Signed ervision du ciblage des bén 0 08 17 08 01 25 30 lected rural areas éficiaires des TMNC comme réponse au Covid19 – CUA 2ème et 3ème arrondissem ents DRF20ED-COVID-AGEX 20 02 / Prestation de services de l’AGEX chargée de la su Component 1: Building a s 2020-04-2 2020-04- 2020-05- 2020-04- 2020-07- 2020-04- 2020-08- pervision du ciblage des bé IDA / D4340 afety net for the poor in se Post Direct Selection Direct 2,000.00 2,180.42 Signed 3 14 03 16 07 25 06 néficiaires des TMNC comm lected rural areas e réponse au Covid19 – CU F Arrondissement Lalazana , Manolafaka et Vatosola DRF20ED_COVID_AGEX 20 03 / Prestation de services Component 1: Building a s de l’AGEX chargée de la su 2020-04-2 2020-04- 2020-05- 2020-04- 2020-07- 2020-04- 2020-08- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 2,000.00 2,040.84 Signed pervision du ciblage des bé 3 14 03 16 07 24 06 lected rural areas néficiaires des TMNC comm e réponse au Covid19 – CU F – Arrondissement Tanana Ambany DRU13CIOS20001 / PREST ATION DE SERVICE DE CON SULTANT INDIVIDUEL, OPÉ Component 1: Building a s Individual Cons 2020-04-2 2019-12- 2020-04- 2020-04- 2020-05- 2020-05- 2020-05- 2020-05- 2020-11- 2020-08- RATEUR DE SAISIE DANS LE IDA / D4340 afety net for the poor in se Post Limited 1,250.00 781.44 Completed ultant Selection 2 16 27 30 04 04 12 05 08 29 S COMMUNES D'ANDROKA lected rural areas ET ANKILIABO (DISTRICT A MPANIHY) ET TAMEANTSOA (DISTRICT DE BETIOKY) - T MNC POST SECHERESSE DRF11CIAS19007 / PREST ATION DE 02 CONSULTANT Component 1: Building a s Individual Cons 2020-05-0 2020-02- 2020-05- 2020-03- 2020-05- 2020-04- 2020-07- 2020-05- 2021-07- S INDIVIDUELS ACCOMPAG IDA / D4340 afety net for the poor in se Post Limited 20,000.00 5,632.42 Signed ultant Selection 4 06 09 13 30 15 04 01 04 NATEURS SPECIALISES POU lected rural areas R LE PROGRAMME ACTP DA NS LE DISTRICT DE MANAN DRIANA Component 1: Building a s DRP82CIMAJ19042 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE5 ultant Selection 9 05 06 10 22 lected rural areas DRP82CIOS20006 / OPERA Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2021-03- TEURDESAISIEDRPAMBOAS IDA / D4340 afety net for the poor in se Post Limited 2,916.67 0.00 Canceled ultant Selection 8 09 16 08 07 ARY2 lected rural areas DRP82CIOS20005 / OPERA Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2020-02- TEURDESAISIEDRPAMBOAS IDA / D4340 afety net for the poor in se Post Limited 2,916.67 0.00 Canceled ultant Selection 8 09 16 08 19 ARY1 lected rural areas Component 1: Building a s DRP82CIMAJ19048 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE11 ultant Selection 9 05 06 10 22 lected rural areas DRP82CIOS20012 / CI OPE Component 1: Building a s Individual Cons 2019-11-2 2019-12- 2019-12- 2020-01- 2021-03- RATEUR DE SAISIE TSIHOM IDA / D4340 afety net for the poor in se Post Limited 2,916.67 0.00 Canceled ultant Selection 9 09 16 08 07 BE 3 lected rural areas Component 1: Building a s DRP82CIMAJ19052 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPTSIHOMBE15 ultant Selection 9 05 06 10 22 lected rural areas Component 1: Building a s DRP82CIMAJ19058 / CIMIS Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- IDA / D4340 afety net for the poor in se Post Limited 305.55 0.00 Canceled EAJOURDRPBEKILY5 ultant Selection 9 05 06 10 22 lected rural areas DRK12CIASTMDH20001 / C ONSULTANT INDIVIDUEL C Component 1: Building a s HARGE DES MESURES D'AC Individual Cons Under Impleme 2020-07-1 2020-07- 2020-07- 2020-08- 2020-09- 2021-09- IDA / D4340 afety net for the poor in se Post Limited 5,000.00 0.00 COMPAGNEMENT POUR LE ultant Selection ntation 3 30 18 08 12 12 lected rural areas TRANSFERT MONÉTAIRE PO UR LE DÉVELOPPEMENT HU MAIN (TMDH) DRA12CISOMAJ19015 / MI Component 1: Building a s SE A JOUR DES INFORMATI Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 510.00 0.00 Canceled ONS DES MENAGES BENEF ultant Selection 8 20 03 06 10 24 lected rural areas ICIAIRES TMDH DISTRICT T OAMASINA II ET MAHANOR O DRA12CISOMAJ19016 / MI Component 1: Building a s SE A JOUR DES INFORMATI Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 510.00 0.00 Canceled ONS DES MENAGES BENEF ultant Selection 8 03 06 10 24 lected rural areas ICIAIRES TMDH DISTRICT T OAMASINA II ET MAHANOR O DRA12CISOMAJ19017 / MI Component 1: Building a s SE A JOUR DES INFORMATI Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 510.00 0.00 Canceled ONS DES MENAGES BENEF ultant Selection 8 03 06 10 24 lected rural areas ICIAIRES TMDH DISTRICT T OAMASINA II ET MAHANOR O DRU12CIEI20001 / CONSU Component 1: Building a s LTANTS CHARGES DE L’EN Individual Cons Pending Imple 2020-07-1 2020-08- 2020-08- 2020-08- 2020-10- IDA / D4340 afety net for the poor in se Post Open 25,200.00 0.00 QUÊTE POUR ÉVALUATION ultant Selection mentation 5 11 21 26 15 lected rural areas D'IMPACT EN DPEI- TMDH A TOLIARA II DRU12CIEI20002 / CONSU Component 1: Building a s LTANTS CHARGES DE LA S Individual Cons Pending Imple 2020-07-1 2020-08- 2020-08- 2020-08- 2020-10- IDA / D4340 afety net for the poor in se Post Open 4,100.00 0.00 UPERVISION DE L’ENQUÊTE ultant Selection mentation 5 11 21 26 15 lected rural areas POUR ÉVALUATION D'IMPA CT EN DPEI- TMDH TOLIARA II DG20_CI_SYST_PAIEMENT_ 2003 / Consultant en charg Component 2: Strengtheni e de la mise en place du s ng safety net administratio Individual Cons 2020-07-2 2020-07- 2020-08- 2020-08- 2020-09- 2020-09- 2020-09- 2020-09- 2020-12- IDA / D4340 Post Open 10,000.00 16,631.24 Signed ystème intégré de paiemen n, monitoring and social ac ultant Selection 2 20 26 31 09 18 30 23 29 t électronique du projet FS countability S dans toutes les zones d’i ntervention du FID DRK11CIASACTP2001 / CO NSULTANTS INDIVIDUELS C HARGES DE LA MISE EN OE UVRE DES MESURES D'ACC Component 1: Building a s OMPAGNEMENT DES BÉNÉF Individual Cons Pending Imple 2020-07-2 2020-08- 2020-08- 2020-09- 2021-09- IDA / D4340 afety net for the poor in se Post Open 24,000.00 0.00 ICIAIRES DU PROGRAMME F ultant Selection mentation 9 18 21 08 08 lected rural areas ILETS SOCIAUX PRODUCTIF S DU FONDS D'INTERVENTI ON POUR LE DÉVELOPPEME NT DANS LE DISTRICT DE M ANAKARA _ 04 ACCOMPAG NATEURS SPECIALISES DRA12CISOMAJ19018 / MI Component 1: Building a s SE A JOUR DES INFORMATI Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2019-12- 2020-01- IDA / D4340 afety net for the poor in se Post Limited 510.00 0.00 Canceled ONS DES MENAGES BENEF ultant Selection 8 20 03 06 10 24 lected rural areas ICIAIRES TMDH DISTRICT T OAMASINA II ET MAHANOR O DG20ED_COVID_AGEX201 3 / Prestations de services des Agences chargées de l Component 1: Building a s 2020-08-0 2020-07- 2020-08- 2020-07- 2020-09- 2020-08- 2020-12- a supervision des deuxièm IDA / D4340 afety net for the poor in se Post Direct Selection Direct 100,000.00 93,874.63 Signed 3 27 10 31 21 25 20 es paiements des TMNC co lected rural areas mme réponse au Covid19 – Antananarivo suburbaines - réparties en 06 lots. DG20_ED_MAINTENANCE_ Component 2: Strengtheni MIS_2001 / Consultant en c ng safety net administratio 2020-08-0 2020-06- 2020-08- 2020-08- 2020-09- 2020-09- 2021-09- IDA / D4340 Post Direct Selection Direct 10,000.00 12,563.66 Signed harge de la maintenance d n, monitoring and social ac 3 22 10 11 07 29 07 u système d'information du countability FID (Logiciel MIS) DRA12 EDCISOCOP 20001 / Consultants Individuels ch Component 1: Building a s argé de la délivrance des c Under Impleme 2020-08-0 2020-02- 2020-08- 2020-08- 2020-08- 2020-09- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 1,000.00 0.00 oups de pouce (SOCOP) au ntation 5 19 14 13 20 19 lected rural areas x bénéficiaires des Transfer ts Monétaires pour le Dével oppement Humain (TMDH) DG20_CI_PLAINTECOVID20 Component 1: Building a s 19 / Consultant Individuel c Individual Cons 2020-08-1 2020-06- 2020-08- 2020-08- 2020-08- 2020-08- 2020-08- 2020-08- 2020-10- IDA / D4340 afety net for the poor in se Post Limited 2,000.00 721.60 Signed hargé du traitement des pl ultant Selection 0 30 10 14 24 18 31 20 31 lected rural areas aintes sur le TOSIKA FAME NO DG20_ED_EMSCOVID2016 / Consultants Individuels ch argés de la supervision et l Component 1: Building a s Individual Cons 2020-08-1 2020-07- 2020-08- 2020-08- 2020-08- 2020-08- 2020-08- 2020-08- 2020-10- e suivi des activités Transf IDA / D4340 afety net for the poor in se Post Direct 20,000.00 10,229.66 Signed ultant Selection 0 30 17 14 24 17 31 19 31 erts Monétaires Non Condit lected rural areas ionnels à Antananarivo (Co mmunes Urbaine et Périph ériques) _ Sept (07) consult ants Individuels DRU12CISOCOP19007 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2020-01- 2020-01- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 0.00 Canceled ultant Selection 4 07 20 27 25 RGE DU COUP DE POUCE lected rural areas DRU12CISOCOP19011 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2020-01- 2020-01- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 0.00 Canceled ultant Selection 4 07 20 27 25 RGE DU COUP DE POUCE lected rural areas DRU12CISOCOP19009 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2020-01- 2020-01- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 0.00 Canceled ultant Selection 4 07 20 27 25 RGE DU COUP DE POUCE lected rural areas DRU12CISOCOP19012 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2020-01- 2020-01- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 0.00 Canceled ultant Selection 4 07 20 27 25 RGE DU COUP DE POUCE lected rural areas DRU12CISOCOP19010 / CO Component 1: Building a s Individual Cons 2019-12-0 2020-01- 2020-01- 2020-01- 2020-07- NSULTANT INDIVIDUEL CHA IDA / D4340 afety net for the poor in se Post Limited 166.00 0.00 Canceled ultant Selection 4 07 20 27 25 RGE DU COUP DE POUCE lected rural areas DRT11CIAS20001 / Recrut Component 1: Building a s ement de 06 Accompagnat Individual Cons Under Impleme 2020-08-2 2020-01- 2020-10- 2020-10- 2020-11- 2021-11- IDA / D4340 afety net for the poor in se Post Open 35,027.00 0.00 eurs Spécialisés dans le ca ultant Selection ntation 8 29 02 23 06 06 lected rural areas dre du FSP à Antanifotsy et à Arivonimamo DRT11CIOS20001 / Recrut Component 1: Building a s ement de deux (02) Opérat Individual Cons Pending Imple 2020-09-2 2020-10- 2020-10- 2020-11- 2021-11- IDA / D4340 afety net for the poor in se Post Limited 4,865.00 0.00 eurs de saisie dans le cadr ultant Selection mentation 1 05 19 02 02 lected rural areas e du FSP dans le District d’ Arivonimamo DRF11CIOS20001 / Recrut Component 1: Building a s Individual Cons 2020-09-1 2020-09- 2020-09- 2020-10- 2020-09- 2020-10- 2020-10- 2020-11- 2021-10- ement d'un Opérateur de s IDA / D4340 afety net for the poor in se Post Limited 5,000.00 2,379.87 Signed ultant Selection 8 08 23 28 28 29 05 03 05 aisie pour le programme A lected rural areas CTP Manandriana DRF11CIAS20001 / Recrut Component 1: Building a s ement de 05 Accompagnat Individual Cons 2020-09-0 2020-09- 2020-10- 2020-10- 2020-10- 2020-10- 2020-11- 2020-10- 2021-11- IDA / D4340 afety net for the poor in se Post Open 70,000.00 27,319.69 Signed eurs Spécialisés dans le ca ultant Selection 5 11 10 20 31 29 28 31 28 lected rural areas dre du programme ’ACTP : Manandriana DRA12 CIASSDPEI 20001 / Component 1: Building a s Recrutement des Accompa Individual Cons Under Impleme 2020-09-1 2021-01- 2020-11- 2020-11- 2020-12- 2021-12- IDA / D4340 afety net for the poor in se Post Open 5,700.00 0.00 gnateurs Spécialisés charg ultant Selection ntation 4 20 02 17 04 04 lected rural areas és des mesures d’accompa gnement - TMDH DG20_CI_THEATRE_RADIO Component 1: Building a s Individual Cons 2020-10-2 2020-11- 2020-12- 2021-09- 2021-01- 2021-09- 2021-02- 2021-10- 2021-08- _2017 / Recrutement de co IDA / D4340 afety net for the poor in se Post Open 1,500.00 1,237.40 Signed ultant Selection 6 19 23 22 13 24 10 12 09 nsultant chargé de l'écritur lected rural areas e théatre radiophonique DG20_CI_ED_PLAINTE_TF_ Component 1: Building a s 2020 / Consultant Individue Individual Cons 2020-10-1 2020-10- 2020-10- 2020-10- 2020-11- 2020-10- 2020-11- 2020-11- 2021-01- IDA / D4340 afety net for the poor in se Post Direct 2,000.00 1,419.25 Signed l chargé du traitement des ultant Selection 2 21 22 23 05 28 12 05 11 lected rural areas plaintes sur le TOSIKA FAM ENO Page 26 DRU12CIAS20001 / Consul tant Individuel, Accompagn Component 1: Building a s Individual Cons 2020-11-0 2020-11- 2020-11- 2020-11- 2020-12- 2020-11- 2021-01- 2020-11- 2021-07- ateur Spécialisé en Inclusio IDA / D4340 afety net for the poor in se Post Limited 1,600.00 1,015.78 Signed ultant Selection 6 19 11 05 02 19 06 20 05 n Productive dans le cadre lected rural areas du programme TMDH à Bet ioky Sud et Toliara II DRK11CISAI18003 / SAISIE Component 1: Building a s Individual Cons 2019-01-2 2019-03- 2019-04- 2019-05- 2019-11- DES DONNES DANS MIS DE IDA / 57080 afety net for the poor in se Post Open 1,645.47 0.00 Canceled ultant Selection 4 14 04 09 05 S BENEFICIAIRES TMDH lected rural areas DRU12CIAS20002 / Recrut ement d’un Consultant Indi Component 1: Building a s viduel, Accompagnateur Sp Individual Cons 2020-11-1 2021-01- 2020-11- 2020-12- 2020-11- 2020-12- 2020-11- 2021-01- 2020-12- 2021-02- IDA / D4340 afety net for the poor in se Post Limited 750.00 1,131.68 Completed écialisé en Mesures d'acco ultant Selection 1 06 16 15 17 17 19 07 31 27 lected rural areas mpagnement dans le cadre du programme TMDH à Bet ioky Sud et Toliara II DRF_ED_12CIAS 2002 TMD H / Recrutement de 05 Acc Component 1: Building a s Individual Cons 2020-12-0 2021-01- 2020-12- 2021-01- 2020-12- 2021-01- 2021-01- 2021-04- 2021-12- ompagnateurs Spécialisés IDA / D4340 afety net for the poor in se Post Direct 34,000.00 29,654.76 Signed ultant Selection 1 11 11 14 16 15 05 02 31 dans le cadre du programm lected rural areas e TMDH dans le district d'A mbohimahasoa DRF_ED_12CIOS 2002 / Re Component 1: Building a s Individual Cons 2020-12-0 2021-01- 2020-12- 2020-12- 2020-12- 2020-12- 2021-01- 2021-01- 2021-12- crutement de 07 Consultan IDA / D4340 afety net for the poor in se Post Direct 18,666.67 11,915.55 Signed ultant Selection 1 04 11 15 16 21 05 07 31 ts Individuels Opérateurs d lected rural areas e Saisie DRT12 ED CIOS 20001 / Re Component 1: Building a s Individual Cons Pending Imple 2020-12-0 2020-12- 2020-12- 2021-01- 2021-12- crutement de dix (10) opér IDA / D4340 afety net for the poor in se Post Direct 29,160.00 0.00 ultant Selection mentation 1 12 29 01 31 ateurs de saisie dans le ca lected rural areas dre du FSP et du TMDH. DRT12 ED CIAS 20001 / Re Component 1: Building a s crutement de douze (12) a Individual Cons Pending Imple 2020-12-0 2020-12- 2020-12- 2021-01- 2021-12- IDA / D4340 afety net for the poor in se Post Direct 87,996.00 0.00 ccompagnateurs spécialisé ultant Selection mentation 1 12 29 01 31 lected rural areas s dans le cadre du TMDH à Faratsiho et à Betafo. DRT11 ED CFCIC20001 / C Component 1: Building a s abinet chargé de l'appui au Pending Imple 2020-11-3 2020-12- 2021-01- 2021-02- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 9,342.00 0.00 ciblage communautaire de mentation 0 12 01 15 lected rural areas s activités ACTP dans le Dis trict d'Arivonimamo. DRT11 ED CFPLAN 20001 / Component 1: Building a s Pending Imple 2020-11-3 2020-12- 2021-01- 2021-02- Agence de planification de l IDA / D4340 afety net for the poor in se Post Direct Selection Direct 27,993.00 0.00 mentation 0 12 01 15 'ACTP Arivonimamo. lected rural areas DRT12 CIAS 20001 / Recru Component 1: Building a s tement de deux (02) acco Individual Cons Pending Imple 2020-12-0 2020-12- 2020-12- 2021-01- 2021-12- IDA / D4340 afety net for the poor in se Post Limited 14,666.00 0.00 mpagnateur spécialisé dan ultant Selection mentation 8 09 24 01 31 lected rural areas s le cadre du TMDH à Betaf o. DRA11ED CIOS 20011 / Re Component 1: Building a s crutement de SIX (06 ) opé Individual Cons Under Impleme 2020-12-0 2021-03- 2020-12- 2021-01- 2021-01- 2022-01- IDA / D4340 afety net for the poor in se Post Direct 15,000.00 0.00 rateurs de saisie dans le ca ultant Selection ntation 2 21 12 02 31 31 lected rural areas dre du FSP et du TMDH. DRA12ED CI ASS 20012 / Component 1: Building a s Recrutement de six (06) a Individual Cons Pending Imple 2020-12-0 2020-12- 2020-12- 2021-01- 2022-01- IDA / D4340 afety net for the poor in se Post Direct 36,000.00 0.00 ccompagnateurs spécialisé ultant Selection mentation 1 11 21 05 05 lected rural areas s dans le cadre du TMDH à MAHANORO et TOAMASIN A II DRU12CIAS21001 / Recrut ement des Consultants indi Component 1: Building a s Individual Cons 2020-11-2 2021-01- 2020-12- 2020-12- 2020-12- 2020-12- 2021-01- 2021-01- 2022-03- 2022-05- viduels AS en charge de m IDA / D4340 afety net for the poor in se Post Direct 53,900.00 6,012.70 Completed ultant Selection 8 06 08 15 13 15 06 07 31 04 esures d'accompagnement lected rural areas TMDH - Betioky Sud et Toli ara II (nombre: 07) DRU12CIAS21002 / Recrut ement des Consultants indi Component 1: Building a s viduels Accompagnateurs S Individual Cons 2020-11-2 2021-01- 2020-12- 2020-12- 2020-12- 2020-12- 2021-01- 2021-01- 2022-03- IDA / D4340 afety net for the poor in se Post Direct 23,100.00 5,793.11 Signed pécialisés en charge des In ultant Selection 8 06 08 14 13 14 06 07 31 lected rural areas clusions productives TMDH - Betioky Sud et Toliara II ( nombre: 03) DRU12CIOS21001 / Recrut ement des Consultants indi Component 1: Building a s Individual Cons 2020-11-2 2020-12- 2020-12- 2021-01- 2020-12- 2021-01- 2021-01- 2021-01- 2022-03- 2022-03- viduels Opérateurs de saisi IDA / D4340 afety net for the poor in se Post Direct 17,400.00 2,840.72 Completed ultant Selection 8 15 08 06 13 06 06 07 31 25 e - TMDH Betioky Sud, Tolia lected rural areas ra II et FSP Ankazoabo Sud (nombre: 06) DRU11CIAS21001 / Recrut ement des Consultants indi Component 1: Building a s viduels Accompagnateurs S Individual Cons 2020-11-2 2021-02- 2020-12- 2021-04- 2020-12- 2021-04- 2021-01- 2021-05- 2022-03- IDA / D4340 afety net for the poor in se Post Direct 27,000.00 7,397.74 Signed pécialisés en charge des m ultant Selection 8 01 08 13 13 14 06 04 31 lected rural areas esures d'accompagnement FSP - Ankazoabo Sud (nom bre: 04) DRP82CIOS21001 / Recrut Component 1: Building a s Individual Cons Under Impleme 2020-11-2 2021-01- 2020-12- 2020-12- 2021-01- 2022-03- ement des 11 Opérateurs d IDA / D4340 afety net for the poor in se Post Direct 31,000.00 0.00 ultant Selection ntation 8 14 08 14 07 31 e Saisie TMDH FIAVOTA lected rural areas DRP82ASMACC21001 / Re crutement des 18 Accompa Component 1: Building a s gnateurs spécialisés charg Individual Cons Pending Imple 2020-11-2 2020-12- 2020-12- 2021-01- 2022-03- IDA / D4340 afety net for the poor in se Post Direct 121,000.00 0.00 és de Mesure d'accompagn ultant Selection mentation 8 08 14 08 31 lected rural areas ement pour le Transfert Mo nétaire pour le Développe ment Humain (TMDH) DRP82ASIP21001 / Recrut ement des 18 Accompagna Component 1: Building a s teurs spécialisés en charge Individual Cons Pending Imple 2020-11-2 2020-12- 2020-12- 2021-01- 2022-03- IDA / D4340 afety net for the poor in se Post Direct 155,000.00 0.00 de l'inclusion Productive po ultant Selection mentation 8 08 14 08 31 lected rural areas ur le Transfert Monétaire p our le Développement Hum ain (TMDH) DRK12EDCIASIP21001 / Re Component 1: Building a s crutement de deux (02)Acc Individual Cons Pending Imple 2020-12-0 2020-12- 2020-12- 2021-01- 2021-12- IDA / D4340 afety net for the poor in se Post Direct 12,800.00 0.00 ompagnateurs spécialisés c ultant Selection mentation 2 13 30 02 28 lected rural areas hargé de l'inclusion produc tive TMDH DRK12EDCIOS21001 / Rec Component 1: Building a s Individual Cons Pending Imple 2020-12-0 2020-12- 2021-01- 2021-01- 2022-01- rutement des sept (07) Op IDA / D4340 afety net for the poor in se Post Direct 18,600.00 0.00 ultant Selection mentation 2 13 03 06 01 érateurs de saisie TMDH et lected rural areas FSP DRK12EDCIASMACC21001 Component 1: Building a s / Recrutement cinq (05) Ac Individual Cons Pending Imple 2020-12-0 2020-12- 2020-12- 2021-01- 2021-12- IDA / D4340 afety net for the poor in se Post Direct 31,800.00 0.00 compagnateurs spécialisés ultant Selection mentation 2 13 30 02 28 lected rural areas de la composante TMDH du District de Vohipeno DRF_CIOS 2003 / Recrute Component 1: Building a s ment de 03 Opérateurs de Individual Cons 2021-01-0 2021-06- 2021-01- 2021-03- 2021-01- 2021-03- 2021-01- 2021-03- 2022-03- IDA / D4340 afety net for the poor in se Post Limited 7,500.00 3,266.59 Signed Saisie pour le programme F ultant Selection 8 29 13 02 18 15 28 16 31 lected rural areas SP Isandra et TMDH Amboh imahasoa DRA11CIASSDPEIIP20002 / Recrutement d'accompagn ateur spécialisé pour la Ré alisation des Mesures d’Acc Component 1: Building a s Individual Cons Pending Imple 2021-01-1 2021-01- 2021-02- 2021-03- 2021-09- ompagnement orientées à l IDA / D4340 afety net for the poor in se Post Limited 6,000.00 0.00 ultant Selection mentation 9 24 14 21 17 ’Education Parentale pour l lected rural areas e Développement de la Peti te Enfance Intensifié (DPEI) , DBE , AVEC, Coup de POU CE, IP des bénéficiaires du Programme ACT P DRA 12 CIASS 20002 / Rec Component 1: Building a s rutement 01 accompagnat Individual Cons Under Impleme 2021-01-1 2021-03- 2021-02- 2021-02- 2021-02- 2022-02- IDA / D4340 afety net for the poor in se Post Open 5,700.00 0.00 eur spécialisé en MACC pou ultant Selection ntation 2 22 05 10 18 18 lected rural areas r le TMDH Mahanoro et To amasina II DRK12CIAS21001 / Recrut Component 1: Building a s ement d'un(e) Accompagn Individual Cons Under Impleme 2021-01-1 2021-05- 2021-02- 2021-02- 2021-02- 2022-03- IDA / D4340 afety net for the poor in se Post Open 6,802.84 0.00 ateur Spécialisé TMDH. Dat ultant Selection ntation 8 27 07 10 28 31 lected rural areas e fin contrat prévue Mars 2 022 DRF_12CIAS 2003 TMDH / Recrutement d'un Accomp Component 1: Building a s Individual Cons 2021-01-0 2021-01- 2021-01- 2021-03- 2021-01- 2021-03- 2021-01- 2021-03- 2021-04- agnateur Spécialisé Tempo IDA / D4340 afety net for the poor in se Post Limited 1,666.67 530.14 Signed ultant Selection 8 18 13 02 18 03 28 04 28 raire pour le programme T lected rural areas MDH- District Ambohimaha soa DRF_12CIASIP 2004 TMDH / Recrutement de 02 Acco Component 1: Building a s Individual Cons 2021-01-1 2021-01- 2021-01- 2021-03- 2021-01- 2021-03- 2021-02- 2021-03- 2022-03- mpagnateurs IDA / D4340 afety net for the poor in se Post Limited 13,333.33 10,973.90 Signed ultant Selection 3 13 18 02 28 03 12 04 31 Spécialisés Inclusion produ lected rural areas ctive dans le cadre du prog ramme TMDH dans le distri ct d’Ambohimahasoa DRA CIOS 20001 / Recrute Component 1: Building a s ment de 05 Opérateurs de Individual Cons Under Impleme 2021-01-1 2021-05- 2021-02- 2021-02- 2021-02- 2022-02- IDA / D4340 afety net for the poor in se Post Open 13,140.00 0.00 saisie pour TMHD Mahanor ultant Selection ntation 2 07 03 05 11 11 lected rural areas o - Toamasina II et FSP V atomandry DRT11 CIAS 21001 / Recru Component 1: Building a s tement d'un accompagnate Individual Cons Pending Imple 2021-02-0 2021-02- 2021-02- 2021-02- 2022-03- IDA / D4340 afety net for the poor in se Post Limited 4,427.00 0.00 ur spécialisé dans le cadre ultant Selection mentation 8 16 22 25 31 lected rural areas du FSP à Arivonimamo. DRF_11CIAS 2005 FSP / Re Component 1: Building a s crutement Accompagnateu Individual Cons 2021-02-0 2021-06- 2021-02- 2021-06- 2021-02- 2021-06- 2021-03- 2021-07- 2022-03- IDA / D4340 afety net for the poor in se Post Limited 7,777.77 4,067.82 Signed r Spécialisé dans le cadre d ultant Selection 9 17 14 22 24 29 20 01 31 lected rural areas u programme FSP Isandra DRA_ED_AGEX_TMNC_PC_ MAROANTSETRA_21001 / P restations d'une Agence d' Component 1: Building a s Under Impleme 2021-02-1 2021-03- 2021-02- 2021-03- 2021-04- Exécution (AGEX) chargée IDA / D4340 afety net for the poor in se Post Direct Selection Direct 15,000.00 0.00 ntation 0 22 17 17 16 du ciblage, de l'enregistre lected rural areas ment et des paiements des bénéficiaires de TMNC/PC d ans le district de Maroantse tra Région Atsinanana. DG_CI_FORMATEUR_SECU RITE_21004 / Recrutement Component 1: Building a s Individual Cons 2021-03-0 2021-04- 2021-03- 2021-05- 2021-03- 2021-08- 2021-05- 2021-08- 2021-10- d'un consultant individuel c IDA / D4340 afety net for the poor in se Post Limited 10,000.00 5,395.94 Signed ultant Selection 1 12 06 21 27 16 01 26 28 hargé de la formation en se lected rural areas courisme et en sécurité rou tière DG_CI_ED_MANUEL_TMUR Component 1: Building a s BAIN_21005 / Recrutement Individual Cons 2021-03-0 2021-03- 2021-03- 2021-03- 2021-04- 2021-04- 2021-04- 2021-04- 2021-07- IDA / D4340 afety net for the poor in se Post Direct 5,000.00 3,982.66 Signed d'un consultant individuel c ultant Selection 1 03 15 15 05 01 19 09 18 lected rural areas hargé de l'élaboration du M anuel de Transfert Urbain DRK11CIOSFSP21001 / Re Component 1: Building a s Individual Cons Under Impleme 2021-01-0 2021-05- 2021-01- 2021-05- 2021-01- 2021-05- 2021-02- 2022-03- crutement de deux (02 ) o IDA / D4340 afety net for the poor in se Post Limited 5,669.03 0.00 ultant Selection ntation 8 27 13 18 20 21 10 31 pérateurs de saisie dans le lected rural areas cadre du FSP. DRK11CIAS21001 / Recrut Component 1: Building a s Individual Cons Under Impleme 2021-01-1 2021-06- 2021-02- 2021-02- 2021-02- 2022-03- ement d'un Consultant Indi IDA / D4340 afety net for the poor in se Post Open 6,802.84 0.00 ultant Selection ntation 8 16 07 10 28 31 viduel Accompagnateur sp lected rural areas écialisé FSP. DRU12CIAS21004 / Accom pagnateurs Spécialisés en charge des mesures d'acco Component 1: Building a s Individual Cons 2021-01-1 2021-01- 2021-01- 2021-02- 2021-02- 2021-04- 2021-03- 2021-04- 2022-03- 2022-07- mpagnement des Bénéficia IDA / D4340 afety net for the poor in se Post Limited 24,500.00 6,585.32 Completed ultant Selection 9 19 20 18 15 06 01 07 31 13 ires dans le cadre du progr lected rural areas amme FSP Ankazoabo Sud et TMDH à Betioky Sud ou Toliara II (nombre: 03) DRA 12 CIASS 21001 / Rec Component 1: Building a s rutement 01 accompagnat Individual Cons Under Impleme 2021-03-0 2021-03- 2021-03- 2021-03- 2021-04- 2022-03- IDA / D4340 afety net for the poor in se Post Open 5,100.00 0.00 eur spécialisé en MACC pou ultant Selection ntation 4 22 26 30 05 01 lected rural areas r le TMDH Mahanoro et Toa masina II DG_21009_CI_PILOT_SEC_ SYS / Recrutement d'un co Component 1: Building a s Individual Cons 2021-03-2 2021-04- 2021-05- 2021-09- 2021-05- 2022-01- 2021-06- 2022-02- 2021-12- nsultant individuel chargé IDA / D4340 afety net for the poor in se Post Open 10,000.00 12,396.78 Signed ultant Selection 6 19 14 15 28 31 18 02 15 du pilotage de la mise en pl lected rural areas ace des recommandations pour la sécurité informatiq ue du FID DRF_21004_SCI_AS_FSP / Component 1: Building a s Recrutement d' un (01) Acc Individual Cons Under Impleme 2021-03-2 2021-06- 2021-03- 2021-05- 2021-04- 2021-04- 2022-03- IDA / D4340 afety net for the poor in se Post Limited 6,486.48 0.00 ompagnateur Spécialisé po ultant Selection ntation 2 17 27 20 01 11 30 lected rural areas ur le programme FSP Mana ndriana DRA_21001_ SCI _ASIP _M ACC / Recrutement 01 acco Component 1: Building a s Individual Cons Under Impleme 2021-05-0 2021-06- 2021-05- 2021-05- 2021-07- 2022-01- mpagnateur spécialisé en IDA / D4340 afety net for the poor in se Post Limited 4,800.00 0.00 ultant Selection ntation 5 23 10 31 05 01 mesures d'accompagneme lected rural areas nt - Inclusion Productive T MDH Mahanoro et Toamasi na II DRK_21002_SCI_OS_TMDH Component 1: Building a s Individual Cons Under Impleme 2021-05-0 2021-07- 2021-05- 2021-05- 2021-06- 2021-12- / Recrutement d'un opérate IDA / D4340 afety net for the poor in se Post Limited 500.00 0.00 ultant Selection ntation 6 09 11 18 08 31 ur de saisie TMDH. lected rural areas DRU_21004_CI_OSMISFSP / Component 1: Building a s Individual Cons Under Impleme 2021-06-0 2021-09- 2021-07- 2021-10- 2021-07- 2021-11- 2021-07- 2022-03- Recrutement d'un Opérate IDA / D4340 afety net for the poor in se Post Open 2,160.00 0.00 ultant Selection ntation 1 17 04 25 09 11 10 31 ur de saisie sur MIS- FSP An lected rural areas kazoabo Sud DRT_21007_CI_OSMIS_FSP / Consultants individuels O Component 1: Building a s Individual Cons Under Impleme 2021-06-3 2021-08- 2021-08- 2021-08- 2021-08- 2022-03- pérateurs de saisie des don IDA / D4340 afety net for the poor in se Post Open 11,675.58 0.00 ultant Selection ntation 0 10 04 09 16 31 nées dans le progiciel MIS lected rural areas pour le District d'Arivonima mo DRF_21005_SCI_OS FSP / R Component 1: Building a s Individual Cons 2021-07-0 2021-07- 2021-08- 2021-09- 2021-08- 2021-09- 2021-09- 2021-10- 2022-03- ecrutement d'un Opérateur IDA / D4340 afety net for the poor in se Post Open 2,189.19 1,355.94 Signed ultant Selection 7 22 05 17 15 17 04 02 31 de Saisie FSP Manandriana lected rural areas DRT_21011_CI_AS_FSP / R ecrutement de deux accom Component 1: Building a s Individual Cons Under Impleme 2021-07-0 2021-08- 2021-08- 2021-08- 2021-08- 2022-03- pagnateurs spécialisés pou IDA / D4340 afety net for the poor in se Post Open 14,270.27 0.00 ultant Selection ntation 5 31 09 14 24 31 r les mesures d'accompagn lected rural areas ement dans le District d'An tanifotsy DG_21023_ED_MAINTENA Component 2: Strengtheni NCE_TOMPORTAIL / Consult ng safety net administratio 2021-08-1 2022-06- 2021-08- 2022-07- 2021-10- 2024-12- IDA / D4340 Post Direct Selection Direct 30,000.00 0.00 Signed ant en charge de la mainte n, monitoring and social ac 4 13 24 11 28 31 nance du logiciel de gestio countability n financière du FID DRT_21020_CI_OS_TMDH_ FA3 / Recrutement de sept Component 1: Building a s Individual Cons Pending Imple 2021-08-3 2021-09- 2021-10- 2021-10- 2022-10- (07) CI Opérateurs de saisi IDA / D4340 afety net for the poor in se Post Open 6,900.00 0.00 ultant Selection mentation 0 29 04 21 21 e du FSS FA3 pour le TMDH lected rural areas dans les Districts de Mando to et d'Antsirabe II. DRT_21021_CI_AS_RAJOUT _BÉNÉF_FSP / Recrutement Component 1: Building a s de six (06) CI Accompagnat Individual Cons Under Impleme 2021-09-1 2021-08- 2021-10- 2021-10- 2021-11- 2022-03- IDA / D4340 afety net for the poor in se Post Open 42,900.00 0.00 eurs Spécialisés pour FSS F ultant Selection ntation 5 31 20 25 13 31 lected rural areas A2 - Rajout de 6000 nouve aux bénéficiaires FSP dans le District d'Arivonimamo DG_21034_CI_EVAL_MACC _DPEI / Recrutement d'un C Component 1: Building a s onsultant chargé de la colle Individual Cons Under Impleme 2021-08-2 2021-08- 2021-09- 2021-10- 2021-10- 2021-12- IDA / D4340 afety net for the poor in se Post Open 3,000.00 0.00 cte de données en vue de l ultant Selection ntation 7 26 24 01 22 31 lected rural areas a réalisation de l’évaluation du processus des mesures d’accompagnement DPEi DRF_21009_CI_AS_TEMPO Component 1: Building a s Individual Cons Under Impleme 2021-08-1 2021-08- 2021-08- 2021-08- 2021-09- 2021-12- RAIRE TMDH / Recrutement IDA / D4340 afety net for the poor in se Post Limited 1,621.62 0.00 ultant Selection ntation 9 31 24 29 17 16 d'un AS TMDH Temporaire lected rural areas DG_21016_CI_RPM_DIR / R Component 2: Strengtheni ecrutement de six (06) Res ng safety net administratio Individual Cons 2021-09-1 2021-09- 2021-10- 2022-03- 2021-11- 2022-03- 2021-11- 2022-04- 2023-10- ponsables Passation de Ma IDA / D4340 Post Open 120,000.00 77,960.54 Signed n, monitoring and social ac ultant Selection 5 23 20 03 03 04 24 26 31 rchés affectés aux niveaux countability des Directions Interrégional es du FID DRA_21010_SCI_ASFS _FA 3 / Recrutement de 22 ( vin Component 1: Building a s gt - deux) CI Accompagnat Individual Cons Under Impleme 2021-09-1 2021-10- 2021-10- 2021-10- 2021-11- 2022-04- IDA / D7740 afety net for the poor in se Post Open 88,000.00 0.00 eurs Spécialisés pour la mi ultant Selection ntation 0 07 11 21 01 30 lected rural areas se en œuvre des Fonds de Soutien aux bénéficiaires d es programmes FSP et TMD H DRU_21008_SCI_AS FS_FA 3 / Recrutement de 13 (Trei Component 1: Building a s ze) CI Accompagnateurs Sp Individual Cons 2021-09-1 2021-10- 2021-10- 2022-03- 2021-10- 2022-04- 2021-11- 2022-04- 2022-06- IDA / D7740 afety net for the poor in se Post Open 52,000.00 76,434.84 Signed écialisés pour la mise en œ ultant Selection 0 07 16 28 26 09 01 10 29 lected rural areas uvre des Fonds de Soutien aux bénéficiaires des progr ammes FSP et TMDH DRF_21012_SCI_ASFS_FA3 / Recrutement de 23 (Vingt Component 1: Building a s trois) CI Accompagnateurs Individual Cons Under Impleme 2021-09-1 2021-10- 2021-10- 2021-10- 2021-11- 2022-06- IDA / D7740 afety net for the poor in se Post Open 92,000.00 0.00 Spécialisés pour la mise en ultant Selection ntation 0 26 04 09 01 30 lected rural areas œuvre des Fonds de Soutie n aux bénéficiaires des pro grammes FSP et TMDH DRT_21028_CI_AS_TMDH_ FSP_FS / Recrutement de CI Component 1: Building a s Accompagnateurs Spécialis Individual Cons Under Impleme 2021-09-1 2021-10- 2021-10- 2021-10- 2021-11- 2022-06- IDA / D7740 afety net for the poor in se Post Open 80,000.00 0.00 és pour la mise en œuvre d ultant Selection ntation 0 14 09 18 01 29 lected rural areas es Fonds de Soutien aux bé néficiaires des programme s FSP et TMDH DRP20_ED_KERE_TMNC20 01 / Sélection d'Agences d' Exécution (AGEX) chargées du ciblage, l’enregistremen Component 1: Building a s Pending Imple 2020-11-1 2020-11- 2020-12- 2021-06- t et le paiement des bénéfi IDA / D4340 afety net for the poor in se Post Direct Selection Direct 50,000.00 0.00 mentation 1 23 21 19 ciaires de Transfert Monéta lected rural areas ire Non Conditionnels com me réponse à la Crise Alim entaire et Nutritionnelle da ns le district Amboasary et Beloha DRK_21010_SCI_ASFS_FA3 / Recrutement de vingt sep Component 1: Building a s t (27) CI Accompagnateurs Individual Cons Under Impleme 2021-09-1 2021-10- 2021-10- 2021-10- 2021-11- 2022-05- IDA / D7740 afety net for the poor in se Post Open 108,000.00 0.00 Spécialisés pour la mise en ultant Selection ntation 0 14 16 26 01 31 lected rural areas œuvre des Fonds de Soutie n aux bénéficiaires des pro grammes FSP et TMDH DRU_21015_ED_CI AS_TM Component 1: Building a s NC FA2-FA3 / Sélection de 2021-10-2 2021-11- 2021-11- 2021-11- 2021-11- 2022-02- 2022-05- 2022-05- IDA / D4340 afety net for the poor in se Post Direct Selection Direct 48,000.00 15,957.32 Completed 15 (Quinze) accompagnate 5 19 04 23 20 23 31 10 lected rural areas urs spécialisés des bénéfici aires TMNC SUD TOLIARA DRA_21017_SCI_AS IP_FA2 / Recrutement de UN ( 01) Component 1: Building a s Individual Cons Under Impleme 2021-11-0 2021-12- 2021-11- 2021-11- 2021-12- 2022-04- accompagnateur spécialisé IDA / D4340 afety net for the poor in se Post Open 2,070.00 0.00 ultant Selection ntation 2 08 25 26 01 30 en Inclusion Productive TM lected rural areas DH Mahanoro et Toamasin a II DRP_21013_SCI_AS_FA2_F A3 / Recrutement de 99 Ac Component 1: Building a s Individual Cons Under Impleme 2021-11-0 2022-01- 2021-12- 2022-05- 2022-01- 2022-06- 2022-02- 2025-02- compagnateurs Spécialisés IDA / D4340 afety net for the poor in se Post Open 650,000.00 0.00 ultant Selection ntation 8 28 27 25 17 16 21 21 pour la mise en œuvre des lected rural areas Mesures d'Accompagneme nt TMDH et TMNC SUD Page 27 DRU_21016_SCI_AS MACC_ IP_FA3 / Recrutement de 2 2 (Vingt deux) CI Accompa Component 1: Building a s Individual Cons 2021-11-1 2022-02- 2022-01- 2022-05- 2022-01- 2022-08- 2022-04- 2022-08- 2025-04- gnateurs Spécialisés pour l IDA / D7740 afety net for the poor in se Post Open 318,423.00 377,216.48 Signed ultant Selection 2 08 05 20 26 05 04 19 03 a mise en œuvre des mesu lected rural areas res d'accompagnement et i nclusion productive aux bé néficiaires des programme s FSP et TMDH DRT_21022_CI_AS_MACC_I P_TMDH_FA3 / Recrutemen Component 1: Building a s Individual Cons Under Impleme 2021-09-3 2022-01- 2021-11- 2021-11- 2021-11- 2024-11- t de trente quatre (34) CI A IDA / D4340 afety net for the poor in se Post Open 496,500.00 0.00 ultant Selection ntation 0 28 04 09 28 27 S TMDH dont dix-sept (17) lected rural areas CI AS MACC et dix-sept (17 ) CI AS IP TMDH pour FSS F A3 DRT_21031_CI_AS_FSP_FA Component 1: Building a s Individual Cons Under Impleme 2021-11-1 2022-02- 2021-12- 2022-05- 2021-12- 2022-07- 2021-12- 2024-12- 3 / Recrutement de quaran IDA / D7740 afety net for the poor in se Post Open 856,500.00 0.00 ultant Selection ntation 5 09 12 05 17 01 29 28 te quatre (44) CI AS FSP po lected rural areas ur FSS FA3 DRF_21018_SCI_RECRUTE Component 1: Building a s MENT _AS MACC _TMDH / R Individual Cons Under Impleme 2021-11-2 2022-01- 2021-12- 2022-01- 2022-02- 2024-12- IDA / D7740 afety net for the poor in se Post Open 568,422.00 0.00 ecrutement de trente (30) ultant Selection ntation 4 29 28 07 01 31 lected rural areas CI AS pour MACC et IP TMD H. DRA_21018_SCI_AS FSP_F Component 1: Building a s Individual Cons Under Impleme 2021-11-1 2022-02- 2021-12- 2021-12- 2022-01- 2025-01- A3 / Recrutement de dix (1 IDA / D7740 afety net for the poor in se Post Open 194,600.00 0.00 ultant Selection ntation 5 16 13 20 04 03 0) CI AS FSP pour FSS FA3 lected rural areas DRA_21019_SCI_AS TMDH_ Component 1: Building a s FA3 / Recrutement TRENT Individual Cons Under Impleme 2021-11-1 2021-12- 2021-12- 2022-01- 2025-01- IDA / D7740 afety net for the poor in se Post Open 580,000.00 0.00 E QUATRE ( 34 ) CI AS MAC ultant Selection ntation 5 13 20 04 03 lected rural areas C ET ASS IP TMDH pour FSS FA3 DRK_21018_SCI_CIC_FSP / Component 1: Building a s Individual Cons Under Impleme 2021-11-1 2022-03- 2022-01- 2022-06- 2022-01- 2022-02- 2022-05- Recrutement de quatre (04 IDA / D7740 afety net for the poor in se Post Open 8,000.00 0.00 ultant Selection ntation 5 07 08 24 29 28 29 ) Ciblage Communautaire F lected rural areas SP Vangaindrano DRK_21020_SCI_AS MACC_ Component 1: Building a s Individual Cons Under Impleme 2021-11-1 2022-02- 2022-01- 2022-01- 2022-04- 2025-03- FSP / Sélection de six (06) IDA / D7740 afety net for the poor in se Post Open 116,800.00 0.00 ultant Selection ntation 5 15 08 29 07 22 Accompagnateurs spécialis lected rural areas és MACC FSP DRK_21019_SCI_AS MACC_ Component 1: Building a s Individual Cons Under Impleme 2021-11-1 2021-12- 2022-01- 2022-09- 2022-01- 2022-12- 2022-02- 2022-05- IP TMDH / Sélection de tre IDA / D7740 afety net for the poor in se Prior Open 583,800.00 0.00 ultant Selection ntation 5 14 08 28 29 19 28 29 nte (30) Accompagnateurs lected rural areas Spécialisés TMDH. DG_21040_SCI_FORMATIO Component 1: Building a s N MSPROJECT FSP / Recrute Individual Cons Under Impleme 2021-11-2 2022-05- 2022-01- 2022-01- 2022-02- 2022-03- IDA / D4340 afety net for the poor in se Post Open 5,000.00 0.00 ment d'un consultant indivi ultant Selection ntation 6 16 14 28 18 20 lected rural areas duel formateur en MS PROJ ECT DG_21041_SCI_FORMATIO N CLIMAT / Recrutement d' Component 1: Building a s Individual Cons 2021-11-1 2022-05- 2021-12- 2022-10- 2022-01- 2022-10- 2022-01- 2022-02- un consultant individuel ch IDA / D4340 afety net for the poor in se Post Open 5,000.00 0.00 Signed ultant Selection 9 30 31 07 07 05 28 27 argé de la formation en act lected rural areas ivités sur les changements climatiques DG_21042_SCI_FORMATIO Component 1: Building a s Individual Cons Under Impleme 2021-12-1 2023-02- 2022-01- 2022-02- 2022-03- 2022-04- N SIG / Recrutement d'un c IDA / D4340 afety net for the poor in se Post Open 5,000.00 0.00 ultant Selection ntation 0 03 28 11 04 03 onsultant individuel format lected rural areas eur en SIG DRF_21019_SCI_AS_MACC_ Component 1: Building a s Individual Cons Under Impleme 2021-11-2 2022-02- 2021-12- 2022-01- 2022-02- 2024-12- FSU_FA3 / Recrutement de IDA / D7740 afety net for the poor in se Post Open 58,378.00 0.00 ultant Selection ntation 4 24 28 07 01 31 quatre (04) CI AS MACC FS lected rural areas U_ FSS FA3 DRF_21020_SCI_RECRUTE Component 1: Building a s MENT_AS_ MACC_FSP__ / R Individual Cons Under Impleme 2021-11-2 2022-02- 2021-12- 2022-06- 2022-01- 2022-02- 2024-12- IDA / D7740 afety net for the poor in se Post Open 435,800.00 0.00 ecrutement de Vingt trois ( ultant Selection ntation 4 15 28 10 07 01 31 lected rural areas 23) AS MACC_ FSP_FA3 DRF_21025_SCI_OS_TMDH Component 1: Building a s _FSP_FA3 / Recrutement de Individual Cons Under Impleme 2021-12-0 2022-02- 2021-12- 2022-05- 2022-01- 2022-02- 2024-12- IDA / D7740 afety net for the poor in se Post Open 162,000.00 0.00 dix neuf (19) CI Opérateurs ultant Selection ntation 7 24 27 05 11 09 30 lected rural areas de saisie pour FSS FA3 DRA_21020_SCI_AS MACC _ FSU_FA3 / Recrutement d e CINQ (05 ) CI Accomp Component 1: Building a s Individual Cons Under Impleme 2021-11-1 2022-02- 2021-12- 2021-12- 2022-01- 2025-01- agnateurs Spécialisés (AS) IDA / D7740 afety net for the poor in se Post Open 86,000.00 0.00 ultant Selection ntation 5 24 13 20 04 03 pour la mise en œuvre des lected rural areas Mesures d'Accompagneme nt du programme Filets Soc iaux Urbains (FSU) dans la CU Toamasina DG_21045_SCI_RPM / Recr Component 1: Building a s utement Responsable Pass Individual Cons Under Impleme 2021-11-2 2021-11- 2021-12- 2021-12- 2024-10- IDA / D4340 afety net for the poor in se Post Direct 40,000.00 0.00 ation de Marché au niveau ultant Selection ntation 0 27 04 11 31 lected rural areas de la Direction Générale DRU_21020_CI_OS_TMDH_ Component 1: Building a s FSP_FA3 / Recrutement de Individual Cons Under Impleme 2021-12-1 2022-02- 2022-02- 2022-02- 2022-03- 2025-03- IDA / D7740 afety net for the poor in se Post Open 9,950.00 0.00 CINQ (05) Opérateurs de sa ultant Selection ntation 7 09 04 14 03 03 lected rural areas isie TMDH et FSP FA3 DRU_21021_CI_CIC_TMDH Component 1: Building a s FA3 / Recrutement de TRE Individual Cons 2021-12-1 2022-02- 2022-02- 2022-03- 2023-03- IDA / D7740 afety net for the poor in se Post Open 22,100.00 0.00 Canceled NTE (30) Consultants Indivi ultant Selection 6 03 13 16 15 lected rural areas duels chargés de collecte d e données TMDH FA3 DRU_21022_CI_CIB_FSP FA Component 1: Building a s 3 / Recrutement de TROIS ( Individual Cons Under Impleme 2021-12-1 2022-03- 2022-02- 2022-08- 2022-02- 2022-09- 2022-03- 2022-07- IDA / D7740 afety net for the poor in se Post Open 8,250.00 0.00 03) Consultants Individuels ultant Selection ntation 6 07 03 18 13 13 16 14 lected rural areas chargés de ciblage commu nautaire FSP FA3 DG_21049_CI_EMS_SO / Re Component 1: Building a s crutement de Socio-Organi Individual Cons 2021-12-1 2022-01- 2022-02- 2022-02- 2022-02- 2022-02- 2022-03- 2022-04- 2022-09- IDA / D7740 afety net for the poor in se Post Open 30,000.00 90,321.60 Signed sateurs affectés comme Eq ultant Selection 7 31 06 21 13 24 06 30 02 lected rural areas uipe Mobile de Soutien DG_21050_SCI_EMS_ING / Component 1: Building a s Individual Cons 2021-12-1 2022-01- 2022-02- 2022-02- 2022-02- 2022-02- 2022-03- 2022-06- 2022-12- Recrutement d'Ingénieurs IDA / D7740 afety net for the poor in se Post Open 20,000.00 9,506.80 Signed ultant Selection 7 31 06 17 20 18 13 09 31 affectés comme Equipe Mo lected rural areas bile de Soutien DRF_21030_DRF_SCI / DIGI TALISATION_TMDH / Recrut Component 1: Building a s Individual Cons Under Impleme 2022-01-1 2022-03- 2022-02- 2022-03- 2022-04- 2022-12- ement des huit (08) Consul IDA / D7740 afety net for the poor in se Post Open 22,000.00 0.00 ultant Selection ntation 7 25 20 07 05 30 tants Individuels pour faire lected rural areas la digitalisation Collecte Co responsabilité FSSFA3 DRA_21031_SCI_CI_CORES _TMDH / Sélection d'un Con Component 1: Building a s Individual Cons Under Impleme 2021-12-2 2022-03- 2022-02- 2022-02- 2022-04- 2023-04- sultant Individuel pour la d IDA / D7740 afety net for the poor in se Post Open 2,800.00 0.00 ultant Selection ntation 0 25 07 28 04 04 igitalisation de Collecte Cor lected rural areas esponsabilité FSSFA3 (Site pilote) DG_21057_SCI_AS_FSU / R ecrutement de Consultants Component 1: Building a s Individuels (Accompagnate Individual Cons 2021-12-3 2022-01- 2022-02- 2022-05- 2022-02- 2022-07- 2022-03- 2022-07- 2024-10- IDA / D7740 afety net for the poor in se Post Open 250,000.00 166,408.55 Signed urs Spécialisés) affectés à l ultant Selection 1 31 04 23 11 08 04 09 31 lected rural areas 'activité Filets Sociaux Urba ins au niveau de la Directio n Générale DRP_21015_SCI_CI DIGITA L CORES TMDH / Recrutem Component 1: Building a s ent des trois (03) Consulta Individual Cons Under Impleme 2022-01-1 2022-03- 2022-02- 2022-07- 2022-03- 2022-03- 2022-09- IDA / D7740 afety net for the poor in se Post Open 14,300.00 0.00 nts Individuels pour effectu ultant Selection ntation 7 23 20 25 07 27 23 lected rural areas er la Collecte de Corespon sabilité digitalisée dans les sites pilotes TMDH FSS FA 3 DRA_21030_SCI_OS TMDH FSP FSU _FA3 / Recrutemen t des SEIZE ( 16) Opérate urs de saisie pour les bén Component 1: Building a s éficiaires du programme T Individual Cons Under Impleme 2022-02-0 2022-02- 2022-03- 2022-03- 2022-04- 2024-12- IDA / D7740 afety net for the poor in se Post Open 127,800.00 0.00 MDH District VAVATENINA ultant Selection ntation 7 23 07 14 02 31 lected rural areas ET AMBATONDRAZAKA - d u programme FSP District FENERIVE EST et AMPARAF ARAVOLA et du programme FSU de la Commune Urbai ne de TOAMASINA DRU_21029_CI_CI CORES / Recrutement des CI chargé Component 1: Building a s Individual Cons Under Impleme 2021-12-2 2022-04- 2022-02- 2022-03- 2022-04- 2023-04- s de collecte de coresponsa IDA / D7740 afety net for the poor in se Post Open 1,026.00 0.00 ultant Selection ntation 2 01 09 02 06 06 bilité TMDH FA3 (pilote digi lected rural areas talisation collecte corespon sabilité) nombre 02 DRT_22001_ED_AGEX_CIB LAGE_TMNC_URGENCE / Sé Component 1: Building a s lection de partenaires (AGE Under Impleme 2022-02-0 2022-03- 2022-02- 2022-02- 2022-04- IDA / D7740 afety net for the poor in se Post Direct Selection Direct 30,000.00 0.00 X) chargés de l'appui au ci ntation 1 03 10 24 30 lected rural areas blage des familles sinistrée s bénéficiaires du Transfert Monétaire Non Conditionne l (TMNC) DRA_22001_ED_AGEX_ACT _HIMO_URGENCE / Sélectio Component 1: Building a s n de partenaires (AGEX) ch Under Impleme 2022-01-3 2022-03- 2022-02- 2022-02- 2022-04- IDA / D7740 afety net for the poor in se Post Direct Selection Direct 11,220.00 0.00 argés du ciblage, de l'enca ntation 1 06 07 28 09 lected rural areas drement et du paiement de s bénéficiaires de l'ACT_HI MO, repartis en six (06) lots DRT_22003_ED_AGEX_ACT _HIMO_URGENCE / Sélectio Component 1: Building a s Under Impleme 2022-02-0 2022-03- 2022-02- 2022-03- 2022-04- n de partenaires (AGEX) ch IDA / D7740 afety net for the poor in se Post Direct Selection Direct 700.00 0.00 ntation 1 08 08 01 15 argés du ciblage, de l'enca lected rural areas drement et du paiement de s bénéficiaires de l'ACT_HI MO. DRT_22006_CI_OS_FSP_FA Component 1: Building a s Individual Cons Under Impleme 2022-02-1 2022-03- 2022-03- 2022-04- 2022-04- 2024-12- 3 / Recrutement de quatorz IDA / D7740 afety net for the poor in se Post Open 122,600.00 0.00 ultant Selection ntation 4 04 26 05 17 31 e (14) CI OS FSP pour FSS F lected rural areas A3 DRB_22003_CI_OS_TMDH_ Component 1: Building a s FSP_FA3 / Recrutement de Individual Cons Under Impleme 2022-02-1 2022-02- 2022-03- 2022-05- 2022-03- 2022-04- 2025-01- IDA / D7740 afety net for the poor in se Post Open 90,000.00 0.00 consultants Opérateurs de ultant Selection ntation 4 25 21 18 28 18 01 lected rural areas Saisie affectés à la Directio n Antsirabe pour FSS FA3 DRK_21021_SCI_CORES_T Component 1: Building a s MDH / Recrutement d'un CI Individual Cons Under Impleme 2022-02-0 2022-03- 2022-03- 2022-03- 2022-08- 2023-03- IDA / D7740 afety net for the poor in se Post Open 1,500.00 0.00 chargés de collecte de core ultant Selection ntation 7 25 15 25 25 24 lected rural areas sponsabilité TMDH FA3 DRA_22007_SCI_AS TMNC _PC_URGENCE / Recruteme Component 1: Building a s nt de douze (12) Accom Individual Cons Under Impleme 2022-02-2 2022-03- 2022-03- 2022-04- 2022-04- 2022-10- IDA / D7740 afety net for the poor in se Post Open 37,900.00 0.00 pagnateurs Spécialisés (AS ultant Selection ntation 8 09 21 04 11 08 lected rural areas ) pour la mise en œuvre de s Mesures d'Accompagnem ent du programme TMNC P C DRF_22003_SCI_AS_TMNC_ PC _URGENCE / Recruteme Component 1: Building a s nt de Onze (11 ) Accompag Individual Cons Under Impleme 2022-02-2 2022-03- 2022-03- 2022-04- 2022-04- 2022-10- IDA / D7740 afety net for the poor in se Post Open 35,000.00 0.00 nateurs Spécialisés pour ac ultant Selection ntation 8 17 21 04 11 08 lected rural areas compagnement des bénéfi ciaires des activités de TM NC Post Catastrophes DRK_22003_SCI_AS_TMNC _PC_URGENCE / Recruteme Component 1: Building a s nt de dix - huit (18) CI Acco Individual Cons Under Impleme 2022-02-2 2022-03- 2022-03- 2022-04- 2022-04- 2022-10- IDA / D7740 afety net for the poor in se Post Open 49,000.00 0.00 mpagnateurs Spécialisés p ultant Selection ntation 8 07 21 04 11 08 lected rural areas our accompagnement des bénéficiaires des activités de TMNC Post Catastrophes DRT_22007_CI_AS_TMNC_P C_FA3_URGENCE / Recrute Component 1: Building a s ment de CI Accompagnate Individual Cons Under Impleme 2022-02-2 2022-03- 2022-03- 2022-04- 2022-04- 2022-10- IDA / D7740 afety net for the poor in se Post Open 72,000.00 0.00 urs Spécialisés pour accom ultant Selection ntation 8 03 21 04 11 08 lected rural areas pagnement des bénéficiair es des activités de TMNC P ost Catastrophes DRK_22005_SCI_OS_TMDH _FSP_FA3 / Recrutement de dix ( 10) Opérateurs de sai Component 1: Building a s Individual Cons Under Impleme 2022-03-0 2022-04- 2022-03- 2022-04- 2022-05- 2025-01- sie pour les bénéficiaires d IDA / D7740 afety net for the poor in se Post Open 75,500.00 0.00 ultant Selection ntation 4 26 24 08 07 21 u programme TMDH Distric lected rural areas t Farafangana, District Ikon go et du programme FSP Di strict Vangaindrano DRP_22002_SCI_OS_TMDH _FA3 / Recrutement des 34 Opérateurs de saisie pour l Component 1: Building a s es bénéficiaires du progra Individual Cons Under Impleme 2022-03-0 2022-03- 2022-04- 2022-07- 2022-04- 2022-07- 2022-04- 2022-12- IDA / D7740 afety net for the poor in se Post Open 35,550.00 0.00 mme TMDH dans les 06 dis ultant Selection ntation 7 23 03 01 13 04 23 31 lected rural areas tricts dont Taolagnaro et A mboasary Sud dans la régi on d'Anosy et Ambovombe, Beloha, Bekily et Tsihombe dans la région d'Androy DRF_22004_ED_AGEX_ACT Component 1: Building a s _HIMO URGENCE / Recrute Under Impleme 2022-03-2 2022-04- 2022-04- 2022-04- 2022-05- IDA / D7740 afety net for the poor in se Post Direct Selection Direct 28,700.00 0.00 ment par Entente Directe d ntation 4 25 02 16 31 lected rural areas es AGEX ACT/HIMO en 02 l ots DRK_22004_ED_AGEX_ACT _PC_URGENCE / Recruteme nt des AGEXs pour assurer l'encadrement des bénéfici Component 1: Building a s Under Impleme 2022-03-0 2022-07- 2022-03- 2022-08- 2022-04- 2022-05- aires de l'ACT HIMO dans la IDA / D7740 afety net for the poor in se Post Direct Selection Direct 334,200.00 0.00 ntation 3 15 17 30 21 31 réalisation des Travaux de lected rural areas nettoyage, assainissement et re profilage des infrastru ctures endommagées par l e cyclone BATSIRAI. Travau x répartis en dix-huit (18) L DRF_22006_ED_AGEX_CIB ots. Component 1: Building a s LAGE_TMNC_URGENCE / Re Under Impleme 2022-03-2 2022-04- 2022-04- 2022-04- 2022-06- IDA / D7740 afety net for the poor in se Post Direct Selection Direct 9,700.00 0.00 crutement par Entente Dire ntation 4 25 03 18 17 lected rural areas cte des AGEX pour le ciblag e TMNC réparties en 10 Lot s DG_22020_SCI_EMS_ING_U Component 1: Building a s Individual Cons 2022-05-2 2022-08- 2022-06- 2022-09- 2022-07- 2022-09- 2022-07- 2023-05- RGENCES / Ingénieurs affec IDA / D7740 afety net for the poor in se Post Open 100,000.00 0.00 Signed ultant Selection 0 01 24 13 01 19 15 14 tés comme Equipe Mobile d lected rural areas e Soutien DG_22012_SCI_RPM_DIR_V Component 1: Building a s 2 / Recrutement de Respon Individual Cons Under Impleme 2022-04-2 2022-07- 2022-06- 2022-07- 2022-07- 2024-10- IDA / D7740 afety net for the poor in se Post Open 40,000.00 0.00 sables de Passation de Mar ultant Selection ntation 9 12 17 01 29 31 lected rural areas chés aux niveaux des Direc tions Interrégionales DG_22015_SCI_EVAL_COM M / Consultant Individuel c Component 1: Building a s Individual Cons 2022-05-1 2022-06- 2022-07- 2022-08- 2023-07- hargé de l'évaluation de la IDA / D7740 afety net for the poor in se Post Open 10,000.00 0.00 Canceled ultant Selection 6 27 04 01 31 communication des Progra lected rural areas mmes mis en œuvre par le FID DG_22016_SCI_COACHING _STAFF / Consultant individ Component 1: Building a s Individual Cons Under Impleme 2022-05-0 2023-02- 2022-06- 2022-06- 2022-07- 2022-12- uel chargé de l'accompagn IDA / D7740 afety net for the poor in se Post Open 5,000.00 0.00 ultant Selection ntation 9 10 20 27 25 22 ement en communication d lected rural areas u staff de la Direction Géné rale DG_22019_SCI_OS_MIS / C Component 1: Building a s onsultants individuels char Individual Cons Under Impleme 2022-05-1 2022-07- 2022-07- 2022-07- 2022-07- 2024-10- IDA / D7740 afety net for the poor in se Post Open 30,000.00 0.00 gés de la saisie des donnée ultant Selection ntation 3 21 01 08 29 31 lected rural areas s dans le MIS au niveau de la Direction Générale DG_22021_SCI_EMS_SO_U Component 1: Building a s Individual Cons Under Impleme 2022-05-2 2022-06- 2022-06- 2022-09- 2022-07- 2022-07- 2023-05- RGENCE / Socio organisate IDA / D7740 afety net for the poor in se Post Open 150,000.00 0.00 ultant Selection ntation 0 23 24 07 01 15 14 urs affectés comme Equipe lected rural areas Mobile de Soutien DG_22023_SCI_CAPITALISA Component 1: Building a s TION_MACC / Consultant In Individual Cons Pending Imple 2022-05-2 2022-07- 2022-07- 2022-08- 2022-11- IDA / D7740 afety net for the poor in se Post Open 7,000.00 0.00 dividuel chargé de la capita ultant Selection mentation 7 15 29 19 30 lected rural areas lisation des acquis des Prog rammes TMDH et FSP DRP_21004_SCI_ASMACC_ TMNC / Recrutement des 0 3 consultants Individuels A Component 1: Building a s Individual Cons 2021-06-2 2021-07- 2021-07- 2021-07- 2021-08- 2021-11- ccompagnateurs Spécialisé IDA / D4340 afety net for the poor in se Post Open 4,700.00 0.00 Canceled ultant Selection 8 01 23 28 07 05 s dans le cadre de Transfer lected rural areas t Monétaire Non Conditionn el dans la commune d'Ifota ka, District d'Amboasary Component 1: Building a s DRP82ASIP20018 / ACCOM Individual Cons 2019-11-2 2019-12- 2019-12- 2019-12- 2020-01- 2021-03- IDA / D4340 afety net for the poor in se Post Limited 5,000.00 0.00 Canceled PAGNATEURIPDRPBEKILY3 ultant Selection 9 19 18 19 08 07 lected rural areas DG_22028_SCI_AUDIT_TEC H_INFRA_PC / Sélection d'u Component 1: Building a s Individual Cons Under Impleme 2022-08-0 2022-09- 2022-09- 2022-10- 2022-11- 2023-05- n consultant individuel char IDA / D7740 afety net for the poor in se Post Open - National 30,000.00 0.00 ultant Selection ntation 5 06 21 12 16 15 gé de l'Audit Technique des lected rural areas infrastructures après les tr avaux post-catastrophes DG_22030_SCI_AUDIT_TEC H_INFRA_HIMO_FSP / Sélect ion d'un consultant individu Component 1: Building a s Individual Cons Under Impleme 2022-08-0 2022-09- 2022-09- 2022-10- 2022-11- 2023-02- el chargé de l'audit techniq IDA / D7740 afety net for the poor in se Post Open - National 15,000.00 0.00 ultant Selection ntation 8 09 26 17 14 12 ue des petites infrastructur lected rural areas es par système Haute Inten sité de Main d’œuvre (HIM O) du Programme Filets So ciaux Productifs (FSP) DG_21016_CI_APM_DIR / R ecrutement de six (06) Assi Component 1: Building a s Individual Cons 2021-07-1 2021-07- 2021-08- 2021-09- 2021-09- 2022-12- stants Passation de Marché IDA / D4340 afety net for the poor in se Post Open 50,000.00 0.00 Canceled ultant Selection 9 15 23 06 27 31 s affectés aux niveaux des lected rural areas Directions Interrégionales d u FID DG_21059_CI_ED_AS_FSU1 / Recrutement de Consulta Component 1: Building a s 2021-12-2 2022-01- 2022-01- 2022-01- nts Individuels chargé de l' IDA / D7740 afety net for the poor in se Post Direct Selection Direct 3,000.00 0.00 Canceled 7 03 17 31 accompagnement des bén lected rural areas éficiaires du premier paiem ents Filets Sociaux Urbains DG_22029_DCI_CONCEPT_ PROG_CRISE / Sélection d'u n consultant individuel en c Component 1: Building a s Individual Cons 2022-08-0 2022-08- 2022-08- 2022-08- 2022-09- 2022-08- 2022-09- 2022-08- 2022-12- harge de l'appui à la prépar IDA / D7740 afety net for the poor in se Post Direct - National 7,000.00 4,421.78 Signed ultant Selection 1 04 13 05 03 12 10 13 09 ation du Programme de rép lected rural areas onse aux crises économiqu es et à l'extension des prog rammes en cours DRA_22014_ED_AGEX_ACT _POST CATA / Recrutement Component 1: Building a s Under Impleme 2022-08-0 2022-08- 2022-08- 2022-08- 2022-10- de partenaires (AGEX) char IDA / D7740 afety net for the poor in se Post Direct Selection Direct - National 1,980.00 0.00 ntation 5 10 10 20 04 gés du ciblage et de l'enca lected rural areas drement des bénéficiaires en ACT HIMO DG_22032_SCI_AS_TMDH_ Component 1: Building a s Individual Cons Under Impleme 2022-08-3 2022-10- 2022-10- 2022-10- 2022-11- 2024-10- MACC_IP / Recrutement de IDA / D7740 afety net for the poor in se Post Open - National 120,000.00 0.00 ultant Selection ntation 1 10 05 19 09 31 treize (13) Accompagnateu lected rural areas rs Spécialisés DG_22037_SCI_CIB_COMM Component 1: Building a s UNAUTAIRE_TMDH / Consul Individual Cons Under Impleme 2022-09-0 2023-03- 2022-10- 2023-05- 2022-10- 2022-11- 2023-06- IDA / D7740 afety net for the poor in se Post Open - National 5,000.00 0.00 tant individuel chargé du ci ultant Selection ntation 2 15 21 02 28 18 06 lected rural areas blage et de la mise à jour d es bénéficiaires Page 28 DG20CI_2017_SIGVEHIC / Prestation d'un spécialiste Component 1: Building a s Individual Cons 2020-04-0 2020-04- 2020-05- 2020-05- 2020-08- en développement web : C IDA / D4340 afety net for the poor in se Post Limited 3,000.00 0.00 Canceled ultant Selection 3 17 01 15 13 onception d'un système de lected rural areas gestion des véhicules du FI D. DG20CI_2018_SIGVEHIC / Prestation d'un spécialiste Component 1: Building a s Individual Cons 2020-04-0 2020-04- 2020-05- 2020-05- 2020-08- en développement mobile : IDA / D4340 afety net for the poor in se Post Limited 3,000.00 0.00 Canceled ultant Selection 3 17 01 15 13 Conception d'un système d lected rural areas e gestion des véhicules du FID. DG20SCICOMMUNICATION Component 1: Building a s Individual Cons 2019-12-0 2019-12- 2020-01- 2020-02- 2020-08- 20001 / Consultant Individu IDA / D4340 afety net for the poor in se Post Open 5,000.00 0.00 Canceled ultant Selection 3 29 19 23 21 el - Assistance Technique e lected rural areas n communication DG_22042_SCI_AS_TMNC_ SUD_URGENCE / Recrutem Component 1: Building a s Individual Cons Under Impleme 2022-10-2 2022-11- 2022-11- 2022-12- 2022-12- 2023-06- ent d'Accompagnateurs Sp IDA / D7740 afety net for the poor in se Post Open - National 120,000.00 0.00 ultant Selection ntation 1 14 25 02 09 30 écialisés dans le cadre de l lected rural areas a réponse aux soudures da ns le sud DG_22043_SCI_EMS_TMNC _SUD_URGENCE / Recrutem Component 1: Building a s Individual Cons Under Impleme 2022-10-2 2022-11- 2022-11- 2022-12- 2022-12- 2023-06- ent de Socio-Organisateurs IDA / D7740 afety net for the poor in se Post Open - National 15,000.00 0.00 ultant Selection ntation 1 08 25 02 09 30 affectés comme Equipe Mo lected rural areas bile de Soutien en réponse aux soudures dans le sud DG_22044_SCI_OS_TMNC_ SUD_URGENCE / Recrutem Component 1: Building a s Individual Cons Under Impleme 2022-10-2 2022-11- 2022-11- 2022-11- 2022-12- 2023-06- ent de 04 Opérateurs de Sa IDA / D7740 afety net for the poor in se Post Open - National 6,000.00 0.00 ultant Selection ntation 1 14 25 25 02 23 isie chargés de la mise à jo lected rural areas ur des données MIS_TMNC sud DRP_22013_SCI_AS TMDH FIAVOTA / Recrutement d'A Component 1: Building a s ccompagnateurs Spécialisé Individual Cons Under Impleme 2022-10-1 2022-12- 2022-12- 2022-12- 2023-01- 2023-07- IDA / D7740 afety net for the poor in se Post Open - National 15,000.00 0.00 s pour l'appui à la mise en ultant Selection ntation 3 02 01 22 26 25 lected rural areas oeuvre des Mesures d'Acco mpagnement dans les Com munes d'intervention FIAV OTA DG_22047_SCI_SOCIO_PC_ URGENCE / Recrutement d Component 1: Building a s Individual Cons Under Impleme 2022-12-0 2022-12- 2023-01- 2023-01- 2023-01- 2023-04- e consultants individuels ch IDA / D7740 afety net for the poor in se Post Open - National 50,000.00 0.00 ultant Selection ntation 5 20 09 16 23 23 argés de l'appui à la mise e lected rural areas n œuvre des activités ACT et/ou TMNC post-cycloniqu es DRF_22020_CI_AS_ FSP__F Component 1: Building a s A3 / Recrutement d'un Acc Individual Cons Under Impleme 2022-12-1 2023-04- 2023-01- 2023-01- 2023-02- 2024-09- IDA / D7740 afety net for the poor in se Post Open - National 11,000.00 0.00 ompagnateur Spécialisé po ultant Selection ntation 9 01 16 23 13 30 lected rural areas ur le programme FSP Fandr iana DRF_22021_CI_OS_ FSP__F Component 1: Building a s A3 / Recrutement d'un Opé Individual Cons Under Impleme 2022-12-1 2023-03- 2023-01- 2023-01- 2023-02- 2023-12- IDA / D7740 afety net for the poor in se Post Open - National 3,000.00 0.00 rateur de saisie pour le pro ultant Selection ntation 9 10 16 23 13 31 lected rural areas gramme FSP Manandriana DRF_22022_CI_PLANIFIC_ F Component 1: Building a s SP__FA3 / Recrutement des Individual Cons Under Impleme 2022-12-1 2023-05- 2023-01- 2023-01- 2023-02- 2023-10- IDA / D7740 afety net for the poor in se Post Open - National 298,000.00 0.00 14 Consultants Individuels ultant Selection ntation 9 01 16 23 13 31 lected rural areas chargés la planification des activités du programme FS P DRU_22008_SCI_AS MACC IP TMDH FA3 ADDIT / Recru tement de Cinq (05) CI Acc Component 1: Building a s ompagnateurs Spécialisés Individual Cons Under Impleme 2022-11-1 2023-01- 2022-12- 2022-12- 2023-01- 2024-10- IDA / D7740 afety net for the poor in se Post Open - National 38,000.00 0.00 pour la mise en œuvre des ultant Selection ntation 6 20 17 27 13 04 lected rural areas mesures d'accompagneme nt et inclusion productive a ux bénéficiaires du progra mmes TMDH district Toliara II (ancien site témoin) DRK_22014_SCI_PLAN_FSP _FA3 / Recrutement d'un co Component 1: Building a s Individual Cons Pending Imple 2022-12-0 2023-01- 2023-02- 2023-03- 2023-09- nsultant individuel FSP char IDA / D7740 afety net for the poor in se Post Open - National 7,000.00 0.00 ultant Selection mentation 1 19 09 16 12 gé de la planification pour l lected rural areas es 12 terroirs dans le Distri ct de Vangaindrano DRK_22015_SCI_TMDH_FA Component 1: Building a s 3 / Sélection des consultant Individual Cons Pending Imple 2022-12-0 2023-01- 2023-02- 2023-03- 2023-09- IDA / D7740 afety net for the poor in se Post Open - National 40,000.00 0.00 s individuels chargés de la ultant Selection mentation 1 19 09 16 12 lected rural areas mise à jour de ciblage des bénéficiaires TMDH DG_22056_SCI_PLANIFICAT ION_FSP_FA3 / Recrutemen Component 1: Building a s t Consultants Individuels ch Individual Cons Under Impleme 2022-12-1 2023-01- 2023-01- 2023-02- 2023-03- 2023-10- IDA / D7740 afety net for the poor in se Post Open - National 40,000.00 0.00 argés de la supervision de l ultant Selection ntation 9 25 23 13 06 31 lected rural areas a mise en œuvre et mise à jour des activités pour les i nterventions n° 03 et N° 04 DG_22057_SCI_AUDIT_INF Component 1: Building a s RAS_FSP_FA3 / Recrutemen Individual Cons Under Impleme 2023-01-0 2023-02- 2023-02- 2023-03- 2023-04- 2023-10- IDA / D7740 afety net for the poor in se Post Open - National 7,500.00 0.00 t de consultant individuel c ultant Selection ntation 9 20 27 20 17 14 lected rural areas hargé de l’audit technique des petites infrastructures DG_22058_SCI_AUDIT_AM ENAGEMENT_FSP / Recrute Component 1: Building a s Individual Cons Under Impleme 2023-01-0 2023-02- 2023-02- 2023-03- 2023-04- 2023-10- ment de consultant individ IDA / D7740 afety net for the poor in se Post Open - National 7,500.00 0.00 ultant Selection ntation 9 20 27 20 17 14 uel chargé de l'audit techni lected rural areas que des aménagements et autres activités DG_21043_SCI_FORMATIO Component 1: Building a s N PHOTO / Recrutement d' Individual Cons 2021-11-1 2021-12- 2022-01- 2022-01- 2022-02- IDA / D4340 afety net for the poor in se Post Open 2,000.00 0.00 Canceled un consultant individuel ch ultant Selection 9 31 07 28 27 lected rural areas argé de la formation en ph otographie DRT_23004_CI_AS_FOND D Component 1: Building a s E SOUTIEN_FSS FA3_ / Recr Individual Cons Pending Imple 2023-02-0 2023-03- 2023-04- 2023-05- 2024-02- IDA / D7740 afety net for the poor in se Post Open - National 45,000.00 0.00 utement de CI AS pour Fon ultant Selection mentation 6 27 17 08 11 lected rural areas ds de Soutien FSS FA3 pour le District Arivonimamo DG_23003_SCI_SMQ / Séle ction d'un consultant indivi Component 1: Building a s Individual Cons Under Impleme 2023-02-0 2023-01- 2023-03- 2023-04- 2023-04- 2023-12- duel chargé de la mise en IDA / D7740 afety net for the poor in se Post Open - National 20,000.00 0.00 ultant Selection ntation 6 27 13 03 24 31 place du Système de Mana lected rural areas gement Qualité au sein du FID DG_23008_SCI_SOCIO_PC FREDDY_URGENCE / Recrut Component 1: Building a s ement de consultants indivi Individual Cons Pending Imple 2023-03-1 2023-03- 2023-04- 2023-04- 2023-07- IDA / D7740 afety net for the poor in se Post Open - National 18,000.00 0.00 duels chargés de l'appui à l ultant Selection mentation 7 31 07 14 13 lected rural areas a mise en œuvre des activi tés ACT et/ou TMNC post-c ycloniques FREDDY DG_23009_SCI_OS_PC FRE DDY_URGENCE / Recrutem Component 1: Building a s ent de consultants individu Individual Cons Pending Imple 2023-03-1 2023-03- 2023-04- 2023-04- 2023-07- IDA / D7740 afety net for the poor in se Post Open - National 1,500.00 0.00 els Opérateurs de saisie ch ultant Selection mentation 7 31 07 14 13 lected rural areas argés de la mise à jour de données MIS post-cycloniq ues FREDDY DRF_23007_CI_DIGITAL_T MDH__FA3 / Recrutement d Component 1: Building a s e Consultants Individuels C Individual Cons Pending Imple 2023-04-0 2023-05- 2023-05- 2023-06- 2024-10- IDA / D7740 afety net for the poor in se Post Open - National 21,000.00 0.00 hargés de digitalisation de ultant Selection mentation 1 13 27 17 31 lected rural areas collecte de coresponsabilit é et des collectes de donné es pour le programme TMD H FSS FA3 Page 29 REPUBLIQUE DU NIGER PROJET REGIONAL MINISERE DE LA SANTE PUBLIQUE, DE D’AUTONOMISATION DES LA POPULATION ET DES AFFAIRES FEMMES ET DIVIDENDES SOCIALES DEMOGRAPHIQUES AU SAHEL UNITE DE GESTION DU PROJET .......................................... RESUME DU PLAN DE PASSATION DES MARCHES SUR L’AVANCE DE PREPARATION (APP) DU PROJET SWEDD II NIGER 1 Seuils pour examen préalable, approches et méthodes de passation des marchés – Travaux, Fournitures, et Services non-consultant ; Examen Approches et méthode de passation des marchés (US$) Catégorie préalable Ouverte Ouverte Nationale Demande de (US$) Internationale (AOI) (AON) cotation (DC) Travaux ≥ 5 000 000 ≥ 5 000 000 <5 000 000 ≤ 200 000 Fournitures et Services non- ≥ 1 500 000 ≥ 500 000 < 500 000 ≤ 100 000 consultant Revue a posteriori : Tous les contrats non soumis à l’examen préalable de la Banque seront soumis à la revue a postériori Sommaire des marchés de Fournitures, Travaux et Services non-consultant prévus sur l’avance de préparation (APP) du Projet SWEDD II NIGER Méthod Méthod Préqu Préfér Date Date Monta Ré Type e de e ali- ence prévisio prévision nt Approch Type de f. DESCRIPTION DU d'Exam passati d'évalu ficati Nation nnelle nelle de Estima es du process No MARCHES en de la on des ation on ale d'ouvert signature tif en marché us . Banque marché envisag (Oui/ (Oui/N ure des du US$ s ée Non) on) offres marché Acquisition de matériels 15 Coût National 1 étape et fournitures diverses 000 évalué Postério e 1 1 pour l’UGP DC le Non Non Mai-22 Juin-22 ri /Restrei envelop moins nte pe disant Achat de tablettes pour 4,000 la mission Coût National 1 étape d’identification des évalué Postério e 1 2 cibles pour l’évaluation DC le Non Non Juil-22 Aout-22 ri /Restrei envelop de l'impact d'une moins nte pe formation à l'initiative disant personnelle en 2 Méthod Méthod Préqu Préfér Date Date Monta Ré Type e de e ali- ence prévisio prévision nt Approch Type de f. DESCRIPTION DU d'Exam passati d'évalu ficati Nation nnelle nelle de Estima es du process No MARCHES en de la on des ation on ale d'ouvert signature tif en marché us . Banque marché envisag (Oui/ (Oui/N ure des du US$ s ée Non) on) offres marché Entreprenariat destinée aux adolescentes et jeunes femmes des Espaces Sûrs au Niger TOTAL 15 000 Légende : DC : Demande de Cotation 3 Seuils pour examen préalable, approches et méthodes de passation des marchés – Services de Consultant Catégorie Liste restreinte composée uniquement de nationaux Examen préalable Services de Service d’ingénierie et de (US$) Consultant (US$) supervision de construction (US$) Consultants (Firmes) ≥ 500 000 ≤ 300 000 ≤ 500 000 Consultants Individuel ≥ 200 000 N/A N/A Note: Les contrats de service de consultant dont le coût estimatif est supérieur ou égal à l’équivalent de US $ 200,000 pour les Services d’ingénierie et de supervision de construction, et de US $ 100 000 pour les autres Services feront l’objet d’une publication d’avis à manifestation d’intérêt (AMI) dans le ‘’United Nations Développent Business (UNDB) online’’ en plus de la publication dans un journal national officiel de larges diffusion. Sommaire des contrats de service de consultants prévus sur l’avance de préparation (APP) du Projet SWEDD II NIGER Méthod Date Date Montan Liste Type e de prévision prévision t Approc Méthode restrein Réf. d'Exame passati nelle nelle de DESCRIPTION DES SERVICES Estimat hes du d'évaluation te No. n par la on des d'ouvert signatur if marché envisagée (Oui/No Banque marché ure des e du (USD) n) s offres marché Recrutement d’un consultant pour 80 000 Postério l’élaboration du Cadre de Gestion ri Environnementale et Sociale (CGES) et du Plan d’action de Qualification prévention et de réponse des s, 1 SCI Limitée Non Juin-22 Aout-22 risques d’exploitation et d’abus Expérience/ sexuels (EAS) et de harcèlement Critère notés sexuel (HS) et l’évaluation des risques sécuritaires et de fragilité du projet du projet SWEDD II Niger 4 Méthod Date Date Montan Liste Type e de prévision prévision t Approc Méthode restrein Réf. d'Exame passati nelle nelle de DESCRIPTION DES SERVICES Estimat hes du d'évaluation te No. n par la on des d'ouvert signatur if marché envisagée (Oui/No Banque marché ure des e du (USD) n) s offres marché Recrutement d’un consultant pour 20 000 Postério Qualification l’étude sur la prise en compte du ri s, 3 SCI Limitée Non Juin-22 Aout-22 genre Expérience/ Critère notés Recrutement d’un consultant pour 20 000 Postério Qualification l’étude sur la problématique de ri s, 3 SCI Limitée Non Juin-22 Aout-22 l’employabilité des jeunes dans la Expérience/ zone d’intervention Critère notés Recrutement d’un consultant pour 20 Postério Qualification l’étude sur le devenir des filles 000 ri s, 4 SCI Limitée Non Juin-22 Aout-22 bénéficiaires des formations dans Expérience/ les CFM financés par le projet Critère notés Recrutement d’un consultant pour 30 000 Postério l’élaboration du Plan ri Qualification d’Engagement des parties s, 5 SCI Limitée Non Juin-22 Aout-22 prenantes et du Mécanisme de Expérience/ Gestion des Plaintes du projet du Critère notés projet SWEDD II Niger Recrutement d’un consultant pour 20 000 Postério Qualification l’élaboration des Procédures de ri s, 6 SCI Limitée Non Juin-22 Aout-22 gestion de la main d’œuvre du Expérience/ projet SWEDD II Niger Critère notés TOTAL 190 000 Légende : SCI : Sélection de Consultant Individuel 5 PROCUREMENT Western and Central Africa : Sub-Saharan Women’s Empowerment and Demographic Dividend Project Plus PLAN General Information Country: Western and Central Africa 2023-05-19 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P176693 GPN Date: Project Name: Sub-Saharan Women’s Empowerment and Demographic Dividend Project Plus Loan / Credit No: IDA / V4450 SWEDD-CONGO Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-SWEDD-CG-361160-GO- 3. Foster regional and nation RFQ-23 / Grands équipement al commitment and capacity Request for Quota Single Stage - One E Pending Impl s de bureau pour les 9 memb IDA / V4450 Post Limited 15,336.00 0.00 2023-07-09 2023-09-03 2024-03-01 for policymaking and gender tions nvelope ementation res de l'UGP (9 ordinateurs, 0 equality 1 imprimante et 01 onduleur ) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-SWEDD-CG-357356-CS-E 3. Foster regional and nation D-SERONDE. B -23 / Recrute al commitment and capacity Direct - Internation Pending Impleme ment d'un consultant individ IDA / V4450 Post Direct Selection 36,602.00 0.00 2023-05-29 2023-06-08 2023-08-12 2024-02-08 for policymaking and gender al ntation uel pour élaborer la strategie equality de passation des marchés (P PSD) CG-SWEDD-CG-357364-CS-I NDV-23 / Elaborer une straté 1. Design and implement ge gie de ciblage des bénéficiair nder transformative interven Individual Consult Pending Impleme es et réaliser un dénombrem IDA / V4450 tions that promote girls’ and Post Open - National 32,773.00 0.00 2023-06-22 2023-08-10 2023-08-31 2023-10-05 2024-04-02 ant Selection ntation ent exhaustif et l'identificatio women’s social and economi n des adolescentes et jeunes c autonomy filles vulnérables dans les zo nes d'intervention du projet CG-SWEDD-CG-357365-CS-I NDV-23 / Etude des opportun 1. Design and implement ge ités économiques et des obst nder transformative interven Individual Consult Pending Impleme acles d'accès pour les femme IDA / V4450 tions that promote girls’ and Post Open - National 32,773.00 0.00 2023-07-19 2023-09-06 2023-09-27 2023-11-01 2024-04-29 ant Selection ntation s, des métiers porteurs et de women’s social and economi s offres de formation professi c autonomy onnelle pour les jeunes femm es dans les zones sélectionné es. CG-SWEDD-CG-357369-CS-I NDV-23 / Etude sur l'état des 2. Improve the availability of services conviviaux aux adol quality RMNCAHN services a Individual Consult Pending Impleme escents et jeunes femmes et IDA / V4450 Post Open - National 20,975.00 0.00 2023-08-21 2023-10-09 2023-10-30 2023-12-04 2024-06-01 nd qualified health workers ant Selection ntation des stratégies d'amélioration at the community level de la demande en SRAJ dans les zones d'intervention du p rojet CG-SWEDD-CG-361144-CS-I 1. Design and implement ge NDV / Étude pour l'adaptatio nder transformative interven Individual Consult Pending Impleme IDA / V4450 Post Open - National 32,773.00 0.00 2023-07-27 2023-09-14 2023-10-05 2023-11-09 2024-05-07 n des activités Composante tions that promote girls’ and ant Selection ntation DBC aux populations autocht women’s social and economi ones c autonomy CG-SWEDD-CG-361150-CS-I 2. Improve the availability of NDV / Étude dernier kilomètr quality RMNCAHN services a Individual Consult Pending Impleme IDA / V4450 Post Open - National 20,975.00 0.00 2023-08-21 2023-10-09 2023-10-30 2023-12-04 2024-06-01 e PF complémentaire à Kobik nd qualified health workers ant Selection ntation isa at the community level CG-SWEDD-CG-361158-CS-I 3. Foster regional and nation Individual Consult Pending Impleme NDV-23 / Elaboration du man IDA / V4450 al commitment and capacity Post Open - National 29,884.00 0.00 2023-08-15 2023-10-03 2023-10-24 2023-11-28 2024-05-26 ant Selection ntation uel d'exécution du projet du for policymaking and gender projet equality Page 1 PROCUREMENT PLAN(Textual Part) Project information: INDIA, Assam Agribusiness and Rural Transformation Project (APART) Project Implementation agency: Assam Rural Infrastructure and Agricultural Services Society (ARIASS)is the main agency. Date of the Procurement Plan (Textual Part) : February 03, 2022 Period covered by this Procurement Plan:Until publication of next version of the Procurement Plan (Textual Part). Preamble In accordance with paragraph5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”)the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plansand conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEPconstitute the Procurement Plan for the Project.The following conditionsapply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Procurement for the project will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers, July 2016, applicable to Investment Project Financing (IPF). The project will be subject to the World Bank’s Anticorruption Guidelines, dated October 15, 2006, as revised in January 2011 and July 2016. The table below describes various procurement methods to be used for activities financed by the loan. The thresholds (Table 1) indicated will govern the procurement approach and methods; Table 1: Procurement Thresholds Procurement Approaches and Methods Thresholds (US$ equivalent) Open international (works – including turnkey, Any value activity supply and installation of plant and equipment and PPP) Open national (works – including turnkey, supply Below 40 million and installation of plant and equipment and PPP) Open international (goods, IT system, and non- Any value activity consulting services) Open national (goods, IT system, and non- Below 10 million consulting services) National request for quotation (goods and Up to 100,000 works) Direct selection No threshold; For works, goods, non-consulting services and IT system procurement: According to paragraphs 6.8– 6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Shortlist of national consultants Up to 2,000,000 Procurement prior-review thresholds. The World Bank will prior review the following contracts: 1. Works (including turnkey, supply and installation of plant and equipment and PPP): All contracts more than US$ 15 million equivalent 2. Goods, IT system and Non-consulting services: All contracts more than US$4 million equivalent 3. Consultants: All contracts >US$2 million equivalent for firms and >US$400,000 equivalent for individuals 4. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds 5. Additional provisions as mentioned at paragraph 2.2, 2.3, 2.4 & 2.5 of Annex I (Mandatory Procurement Prior Review Thresholds) under Bank Procedure (Effective August 01, 2018), “Procurement in IPF and Other Operational Procurement Matters” will also apply. National Procurement Arrangements:National competition for the procurement of works, goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: 1. Only the model bidding documents for National Competitive Procurement (NCP) agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding. 2. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. 3. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. 4. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. 5. Government e-Marketplace (GeM) set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. 6. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. 7. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 8. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 9. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. 10. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. Domestic preference-The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement of Works, Goods (Supply and Installation; and IT Equipment), Non-Consultancy Services and Consultancy Services – As per procurement plan approved in STEP. PROCUREMENT India : Assam Agribusiness and Rural Transformation Project PLAN General Information Country: India 2021-02-18 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155617 GPN Date: Project Name: Assam Agribusiness and Rural Transformation Project Loan / Credit No: IBRD / 87800 Directorate of Horticulture and Food Processing Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-OPIU-HORTI-345891-CW- RFB / Construction of Paver B lock Road with covered R.C.C Request for Bids - Component C: Fostering Mar Drainage system from Car po Single Stage - Two E Small Works SPD Pending Imp 2024-02-0 IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 42,000.00 0.00 2023-03-06 2023-03-11 2023-04-22 2023-07-05 2023-08-09 rch area of Engineering Wing nvelope (2 envelope proce lementation 5 ence Enhancement , HQ to Directorate of Horticu ss) lture & Food Processing, Assa m, Khanapara, Guwahati-22 under APART. IN-OPIU-HORTI-361975-CW- Request for Bids - RFB / CONSTRUCTION OF (18 Component C: Fostering Mar Single Stage - Two E Small Works SPD Under Imple 2024-04-2 0 UNITS) 100 SQM BAMBOO IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 175,000.00 0.00 2023-05-22 2023-05-29 2023-05-27 2023-07-08 2023-09-20 2023-10-25 nvelope (2 envelope proce mentation 2 STRUCTURE POLY HOUSE UN ence Enhancement ss) DER STATE FLORICULTURE M ISSION. National Procure IN-OPIU-HORTI-361984-CW- Component C: Fostering Mar ment Document - RFB / CONSTRUCTION OF (90 Single Stage - Two E Under Imple 2024-04-2 IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 70,000.00 0.00 2023-05-22 2023-05-30 2023-05-27 2023-07-08 2023-09-20 2023-10-25 UNITS) 100 SQM SHADENET nvelope mentation 2 ence Enhancement ss (Non Bank-SPD HOUSE UNDER STATE FLORIC ) ULTURE MISSION National Procure IN-OPIU-HORTI-361991-CW- Component C: Fostering Mar ment Document - Single Stage - Two E Under Imple 2024-04-2 RFB / Earth Filling work at CO IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 105,000.00 0.00 2023-05-28 2023-06-20 2023-06-02 2023-07-14 2023-09-26 2023-10-31 nvelope mentation 8 E Khetri ence Enhancement ss (Non Bank-SPD ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-OPIU-HORTI-220126-GO-D IR / 1. Cucumber seeds- 328. 17 kg, 2. Bottle gourd seed- Component C: Fostering Mar 1174.035kg, 3. Okra seed - 2 IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 453,583.33 450,301.48 Completed 2021-02-26 2020-04-26 2021-03-03 2020-04-26 2021-04-07 2020-04-27 2021-05-07 2021-03-05 110.56 kg of of vegetable se ence Enhancement eds was procured for distrib ution to around 65200 rural h ouseholds within the APART districts IN-OPIU-HORTI-287020-GO-R Component C: Fostering Mar FQ / Procurement of 6 nos. P Request for Quota Single Stage - One E Under Imple IBRD / 87800 ket-led Production and Resili Post Open - National 65,000.00 0.00 2022-04-08 2022-06-03 2022-11-30 ortable Potato Grader for Ka tions nvelope mentation ence Enhancement mrup, Nagaon, Sonitpur and Darrang District. IN-OPIU-HORTI-297580-GO-R Component C: Fostering Mar Request for Quota Single Stage - One E FQ / Procurement of Lemon G IBRD / 87800 ket-led Production and Resili Post Open - National 30,000.00 0.00 Canceled 2022-06-04 2022-07-30 2023-01-26 tions nvelope rass Planting Materials ence Enhancement IN-OPIU-HORTI-304640-GO-R Component C: Fostering Mar FB / Procurement of 20 nos o Single Stage - Two E Under Imple IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 210,000.00 0.00 2022-07-22 2023-01-30 2022-07-27 2022-09-07 2023-03-09 2022-11-20 2023-05-18 2022-12-25 2023-06-23 f four wheeler transport vehi nvelope mentation ence Enhancement cle for carrying agri-horti co mmodities under APART IN-OPIU-HORTI-323936-GO-R Component C: Fostering Mar FQ / Supply and Installation o Request for Quota Single Stage - One E Under Imple IBRD / 87800 ket-led Production and Resili Post Open - National 72,000.00 0.00 2022-11-10 2023-01-05 2023-07-04 f Food Processing and Agri-In tions nvelope mentation ence Enhancement put Equipment under OPIU-H orti (APART) IN-OPIU-HORTI-327335-GO-R Component C: Fostering Mar FQ / Procurement of 4 nos. o Request for Quota Single Stage - One E Under Imple IBRD / 87800 ket-led Production and Resili Post Open - National 75,000.00 0.00 2022-12-09 2023-02-03 2023-08-02 f Mini Processing Plants with tions nvelope mentation ence Enhancement shade for Medicinal and Aro matic Plants. IN-OPIU-HORTI-327987-GO-R Component C: Fostering Mar FQ / Procurement of Modular Request for Quota Single Stage - One E Under Imple IBRD / 87800 ket-led Production and Resili Post Open - National 14,000.00 0.00 2022-12-09 2023-02-03 2023-08-02 furnishing and accessories fo tions nvelope mentation ence Enhancement r the APART/MAP at OPIU-Hor ti IN-OPIU-HORTI-356295-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar Under Imple egetable Seeds of the varieti IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 114,000.00 0.00 2023-04-17 2023-04-11 2023-04-22 2023-04-24 2023-05-27 2023-11-23 mentation es viz. Okra-Radha17, Bottle ence Enhancement Gourd- Bharti 26 & Cucumbe r- Mastani. (Package-1) IN-OPIU-HORTI-356298-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar Under Imple egetable Seeds of the varieti IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 35,000.00 0.00 2023-04-17 2023-04-06 2023-04-22 2023-05-27 2023-11-23 mentation es viz. Okra-Indus 101, Bottle ence Enhancement Gourd- Ankit & Cucumber- Ka mini. (Package-2) IN-OPIU-HORTI-356300-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar Under Imple egetable Seeds of the varieti IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 36,500.00 0.00 2023-04-17 2023-04-11 2023-04-22 2023-05-27 2023-11-23 mentation es viz. Okra-Sophia 09, Bottle ence Enhancement Gourd- Kanchan & Cucumber - Garima. (Package-3) IN-OPIU-HORTI-356305-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar Under Imple egetable Seeds of the varieti IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 12,700.00 0.00 2023-04-17 2023-04-11 2023-04-22 2023-04-19 2023-05-27 2023-11-23 mentation es viz. Okra-Payal, Bottle Go ence Enhancement urd- Chandini & Cucumber- D iksha. (Package-4) Page 1 IN-OPIU-HORTI-356436-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar Under Imple egetable Seeds of the varieti IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 54,000.00 0.00 2023-04-17 2023-04-11 2023-04-22 2023-05-27 2023-11-23 mentation es viz. Okra-Indus 161, Bottle ence Enhancement Gourd- Mridula & Cucumber- Shama. (Package-5) IN-OPIU-HORTI-356437-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar Under Imple egetable Seeds of the varieti IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 13,000.00 0.00 2023-04-17 2023-04-06 2023-04-22 2023-05-27 2023-11-23 mentation es viz. Okra-Madhurima, Bott ence Enhancement le Gourd- Warun & Cucumber - WC 102. (Package-6) IN-OPIU-HORTI-356439-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar Under Imple egetable Seeds of the varieti IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 14,500.00 0.00 2023-04-17 2023-04-06 2023-04-22 2023-05-27 2023-11-23 mentation es viz. Okra-Ashmit 11, Bottl ence Enhancement e Gourd- Sarika 444 & Cucu mber- Ganga. (Package-7) IN-OPIU-HORTI-356442-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar Under Imple egetable Seeds of the varieti IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 12,000.00 0.00 2023-04-17 2023-04-06 2023-04-22 2023-05-27 2023-11-23 mentation es viz. Okra-Madhuri, Bottle ence Enhancement Gourd- Warun & Cucumber- L axmi. (Package-8) IN-OPIU-HORTI-356444-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar Under Imple egetable Seeds of the varieti IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 26,000.00 0.00 2023-04-17 2023-04-06 2023-04-22 2023-05-27 2023-11-23 mentation es viz. Okra-Riya, Bottle Gour ence Enhancement d- Kapili & Cucumber- Zorro. (Package-9) IN-OPIU-HORTI-356449-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar egetable Seeds of the varieti Under Imple IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 34,000.00 0.00 2023-04-17 2023-04-11 2023-04-22 2023-05-27 2023-11-23 es viz. Okra-NOKH 1003, Bott mentation ence Enhancement le Gourd- NSBH 1012 & Cucu mber- Kareena. (Package-10) IN-OPIU-HORTI-356450-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar egetable Seeds of the varieti Under Imple IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 32,000.00 0.00 2023-04-17 2023-04-11 2023-04-22 2023-05-27 2023-11-23 es viz. Okra-PAN2199, Bottle mentation ence Enhancement Gourd- PAN 16000 & Cucumb er- PAN 1692. (Package-11) IN-OPIU-HORTI-356451-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar Under Imple egetable Seeds of the varieti IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 39,500.00 0.00 2023-04-17 2023-04-06 2023-04-22 2023-05-27 2023-11-23 mentation es viz. Okra-MO 203, Bottle G ence Enhancement ourd- Mahima & Cucumber- V ardan. (Package-12) IN-OPIU-HORTI-356452-GO-D IR / Procurement of Hybrid V Component C: Fostering Mar Under Imple egetable Seeds of the varieti IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 39,000.00 0.00 2023-04-17 2023-04-11 2023-04-22 2023-04-24 2023-05-27 2023-11-23 mentation es viz. Okra-BSS 954, Bottle ence Enhancement Gourd- Semal & Cucumber- B SS 949. (Package-13) IN-OPIU-HORTI-358289-GO-R Component C: Fostering Mar FQ / Procurement of Tissue C Request for Quota Single Stage - One E Under Imple IBRD / 87800 ket-led Production and Resili Post Open - National 37,000.00 0.00 2023-05-06 2023-07-01 2023-12-28 ulture Banana Saplings (G-9) tions nvelope mentation ence Enhancement and compatible mulch film. IN-OPIU-HORTI-358298-GO-R FQ / Procurement of 3 nos. of Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Mini Processing Plants for oil IBRD / 87800 ket-led Production and Resili Post Open - National 57,000.00 0.00 2023-05-06 2023-07-01 2023-12-28 tions nvelope ementation extraction of Medicinal and A ence Enhancement romatic Plants (Tulsi/Lemon Grass). IN-OPIU-HORTI-361988-GO-R Component C: Fostering Mar FB / Supply of Tissue Culture Single Stage - Two E Under Imple IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 288,000.00 0.00 2023-05-22 2023-05-29 2023-05-27 2023-07-08 2023-09-20 2023-10-25 2024-04-22 Flower Planting Materials und nvelope mentation ence Enhancement er the State Floriculture Missi on NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 REPUBLIC OF MOZAMBIQUE MINISTRY OF PUBLIC WORKS, HOUSING AND WATER RESOURCES PROJECT PROCUREMENT STRATEGY FOR DEVELOPMENT (PPSD) FOR SAFER ROAD FOR SOCIAL AND ECONOMIC INTEGRATION PROJECT IN MOZAMBIQUE (P174639) Multi-Phase Programmatic Approach Project PHASE 1 1 February 2023 2 ABBREVIATIONS AND ACRONYMS ANE National Road Administration (Administração Nacional de Estradas) ESF Environmental and social framework GBV Gender-based Violence GDP Gross Domestic Product GoM Government of Mozambique IDA International Development Association IFRDP Integrated Feeder Road Development Project ILO International Labor Organization INATRO National Institute of Land Transport (Instituto Nacional de Transportes Rodoviários) IPF Investment Project Financing MOPWWR Ministry of Public Works and Water Resources MTC Ministry of Transport and Communication MPA Multiphase Programmatic Approach OPBRC Output- and performance-based road contracts PDO Project Development Objective PIU Project Implementation Unit PPP Public-private partnership PPSD Project procurement strategy for development SATCP Southern Africa Trade and Connectivity Project SDG Sustainable Development Goal SEA Sexual exploitation and abuse SH Sexual harassment SRSEIP Safer Roads for Social and Economic Integration Project 3 Table of Contents 1 Project Overview ..................................................................3 1.1 Project Financing by Component for Phase I: .................................4 1.2 Project Beneficiaries.......................................................................5 1.3 Choice of OPBRC Approach ............................................................6 2 Overview of Country, Borrower and Marketplace ...................8 2.1 Operational Context .......................................................................8 2.2 Governance aspects.......................................................................8 2.3 Economic Aspects ..........................................................................9 2.4 Sustainability Aspects ....................................................................9 2.5 Technological Aspects ..................................................................10 2.6 Technical Challenges....................................................................11 2.7 Regulatory Challenges .................................................................11 2.8 Personnel/Cultural Challenges......................................................12 2.9 Summary of PESTLE Analysis .......................................................12 3 Client Capability and PIU Assessment ..................................17 3.1 Experience ...................................................................................17 3.1.1 Contract management capability and capacity ......................17 3.1.2 Complaints management and dispute resolution systems .....18 4 Market Analysis..................................................................19 4.1 Market sector dynamics ...............................................................19 4.2 Summary of Suppliers ..................................................................19 4.3 Financial .......................................................................................22 5 Procurement Trends ...........................................................22 6 Procurement Risk Analysis ..................................................23 7 Procurement Objective .......................................................25 8 Summary of PPSD to inform the bank’s preparation of the PAD 25 8.1 Recommended Procurement Approach for the Project ................25 List of Tables Table 1: MPA Budget Breakdown by Component .......................................4 Table 2: PESTLE Analysis .........................................................................12 Table 3: Consultants ................................................................................20 Table 4: Contractors ................................................................................21 Table 5: Procurement Risk Analysis .........................................................23 Table 6: Procurement Thresholds ............................................................26 4 Table 7:List of procurement processes under both ANE and MTC PIUs by Component: .............................................................................................27 1 Project Overview Country: Republic of Mozambique Full Project Name: Safer Road for Social and Economic Integration Project in Mozambique – Phase 1 Total Finance (US$): 850m (In three phases) Project Number: P174639 Summary of Project The Project Development Objective (PDO) is Development Objectives to improve road connectivity, safety, climate resilience, and accessibility to jobs and socio-economic opportunities along the North South N1 corridor. The Multi-Phase Programmatic Approach Project has five components: 5 1.1 Project Financing by Component for Phase I: Table 1: MPA Budget Breakdown by Component MPA: S afer Roads for Socio-Economic Integration in Mozambique Project Financing, Phase 1 IDA Counterpart Total Project Components Financing Financing Financing (US $, m l) (US$, m l) (US$, m l) 100% 0% 100% Com ponent 1:S afe and Resilient Road Connectivity 356.86 0.00 356.86 Preparation of concept designs and supervision for OPBRC civil works 27.40 0.00 27.40 Road safety audit services for MPA priority sections 2.00 0.00 2.00 OPBRC civil works (including 15%contingencies and RAP Implementation Support) 295.66 0.00 295.66 Preparation of high crash risk improvement program, detailed designs and supervision 4.80 0.00 4.80 High crash risk improvement civil works 25.00 0.00 25.00 Safe school program designs and civil works 2.00 0.00 2.00 Com ponent 2: Com m unityEng agem ent and Wom en Em powerm ent 6.80 0.00 6.80 Gender analysis and development of Gender Action Plan 0.40 0.00 0.40 Preparation of feeder road maintenance packages and implementation support 1.50 0.00 1.50 Implementation of community based pilots and economic empowerment activities 4.50 0.00 4.50 Adaptation of community mobilization strategy 0.40 0.00 0.40 Com ponent 3: Im proved R oad S afetyManag em ent 9.80 0.00 9.80 Road safety technical assistance to MTC/INATRO 2.50 0.00 2.50 Development and installation of crash database 1.00 0.00 1.00 Organizational review of INATRO 0.15 0.00 0.15 Motorization management diagnostic study 0.80 0.00 0.80 Diagnostic review of inter-city public bus aperations 1.00 0.00 1.00 Preparation and implementation of post-crash response pilot 1.00 0.00 1.00 Financing of other RS priority activities to be defined by diagnostic studies 3.35 0.00 3.35 Com ponent 4: Institutional Developm ent and Project Manag em ent 26.54 0.00 26.54 SEA/SH/GBV prevention and management third party service provider 6.00 0.00 6.00 SEA/SH/GBV prevention and management third party monitoring 1.50 0.00 1.50 ESF system assessment 0.20 0.00 0.20 Preparation of climate resilient design manuals 0.50 0.00 0.50 Preparation of new road bill and of auxiliary surveys and studies 1.10 0.00 1.10 Review of PPP framework in the road sector and preparation of PPP feasibility roadmap 0.80 0.00 0.80 Development of primary network tolling strategy 0.50 0.00 0.50 Institutional improvement and capacity building of procurement and contract management of ANE 0.30 0.00 0.30 Weighbridge system analysis and update 1.00 0.00 1.00 Capacity building of RF/ANE and preparation of future phases/projects 7.64 0.00 7.64 Operating costs, goods, training, audit of project accounts 7.00 0.00 7.00 Com ponent 5: Conting ent Em ergencyR esponse 0.00 0.00 0.00 Total F inancing 400.00 0.00 400.00 6 Proposed Development Objective(s) and Components The Multi-Phase Programmatic Approach (MPA) Project has five components: i) Safe and Resilient Road Connectivity; ii) Community Engagement and Women Empowerment; iii) Improved Road Safety Management; iv) Institutional Development and Project Management; v) Contingency and Emergency Response. The program areas are defined as priority sections of N1 North-South corridor in the Republic of Mozambique. The North South national road corridor is critical for the development and integration of the fragile northern provinces with the rest of the country. The N1 is the main corridor linking the poorest and most isolated regions in the North of the country to Maputo and the South. Investments in this corridor have been short- sighted, fragmented and reactive in the past, while investment priority was mainly granted to the international east-west corridors transhipping freight from the Mozambican ports to the neighbouring countries. There has been sporadic interest from the development partners to address damages in the aftermath of major climatic events like cyclones or to rehabilitate limited sections in very poor condition. An MPA approach will provide the opportunity for rolling out an integrated and long-term engagement, that gradually evolves the way in which road programs are developed in the country. Building upon the achievements of each phase the program will address in a holistic manner the connectivity needs along the corridor, create social inclusion and economic empowerment opportunities for the beneficiary communities and support institutional strengthening initiatives to guarantee the sustainability of the road sector within a given fiscal framework The MPA will support government's programs aimed at gradually moving towards managing the paved national network under the Output and Performance-Based Road Contract modality (OPBRC) and improving road safety, network resilience, and creating jobs through community-based road maintenance works. This MPA will be delivered over three (3) simultaneous overlapping operations spread over 3 IDA cycles. The total cost of three operations under this MPA is $ 850m IDA Grants, with the first phase costing $ 400m IDA grant. 1.2 Project Beneficiaries The project will provide support in the following areas: 7 1. Infrastructure Design and Construction: The project will prepare road rehabilitation designs that incorporate improved road safety aspects and increased climate resilience. The sections of road will be packaged in OPBRC lots that incorporate detailed design, construction and extended maintenance horizons into each contract. A program of improvements for high crash risk locations for the entire length of the N1 will be implemented. All schools in the vicinity of the N1 will benefit from small engineering works, such as fencing, speed calming measures, installation of road signs, as well as the training of students in road safety considerations. 2. Community Engagement and Women Empowerment: The project will undertake community and gender studies in order to identify methods for skills training and community mobilization aimed at making women less vulnerable to SEA/SH/GBV. The project will support the development of women’s self-help groups and propose pilot projects to enhance community engagement and women empowerment. Over time the project will develop and implement mechanisms to facilitate women-led road maintenance of feeder roads and other transport-oriented microenterprises. 3. Development of Improved Road Safety Management: This component will finance: necessary technical assistance at MTC and INATRO to help the government achieve SDG 3.6 (decrease the number of road crash fatalities by 50 percent by 2030); the development and installation of a traffic accident database; an organizational review of INATRO; a motorization management diagnostic study; a diagnostic review of intercity bus operations; an analysis of PPP options to attract private sector financing to improve long-distance bus service; and the preparation and implementation of a post-crash response pilot along the N1 corridor jointly with the Ministry of Health and other relevant stakeholders. This component will also have an unallocated amount reserved for other road safety priority needs as recommended in various diagnostic studies through this proposed project, the IFRDP, and the Southern Africa Trade and Connectivity Project (SATCP) (P164847). In addition, this component will aim to tackle entry barriers to greater numbers of females enjoying professional employment in the transport sector and will finance activities aimed at increasing female representation in ANE and INATRO. 4. Institutional Development for Project Management, Environmental and Social Safeguarding and Climate Resilience: This component will finance institutional development, capacity building, and project management costs. Consulting services and technical assistance activities will include: (i) 8 improvement of the results-based management and reporting framework for ANE, support for the design and adoption of user satisfaction surveys; (ii) third-party GBV/SEA/SH prevention and management service provider; third-party GBV/SEA/SH monitoring; environmental and social system assessment at ANE; enhancement of the capacity of service providers; (iii) preparation of additional climate-resilient design manuals; (iv) preparation of a new road bill, including auxiliary stakeholder surveys, public consultations, and studies; (v) the review of road sector financing and operationalization of the road map for PPP, including increasing ANE capacity in procurement and contract management; (vi) development of a primary network tolling strategy; (vii) assessment and update of the current weighbridge system; (viii) capacity building for the Road Fund and ANE and preparation of future phases of the MPA program; and (ix) project operating costs, goods, training, and audits of project accounts. 5. Contingent Emergency Response: The project will facilitate the rapid financing of emergency needs through the reallocation of uncommitted funds under the project. 1.3 Choice of OPBRC Approach The project will adopt the Output and Performance-Based Road Contract approach generally referred to by the acronym OPBRC. This approach combines the detailed design work, the construction implementation and an extended period of maintenance into one contract. The OPBRC contract identifies the standards that are to be used in the design process and the minimum level-of-service conditions that are expected to be maintained during the maintenance period. Contractors tender on the basis of a concept design provided in the bidding document but they are also expected to undertake considerable survey work as part of the bidding process in order to fully understand the technical challenges that the terrain and the available construction materials will present. The OPBRC bid price is effectively a lump-sum which covers the three tasks mentioned above. There is no remeasurement except for emergency works or additional works that might be included after the award of contract. Alterations to the bid price are generally restricted to those issues that could not be identified or anticipated at the time of tender. It should be noted that this transfers considerable additional risk to the contractor as s/he is paid for outputs rather than measured inputs. The inclusion of relatively long-term maintenance periods in the OPBRC contract helps to reinforce the importance of good design and construction work. Failures in design or construction would be expected to surface before the end of the maintenance period which is typically ten years. 9 Hence, the contract automatically brings pressure on the contractor to work diligently in order that s/he is not faced with expensive repairs to be completed during the maintenance period. The security that comes from this extended maintenance period and the use of level-of-service standards also allows the client and the financing agency to have a greater level of confidence that the road will perform according to expectations. The user- oriented mandate of ANE-IP makes OPBRC an ideal mechanism for achieving their aims. Another facet of the OPBRC approach is the potential for innovative thinking and solutions that might satisfy the contract requirements in a more efficient way. Contractors tend to have their own preferences and skill-sets that might lead them to adopt solutions that are appropriate to their own way of doing things. This combination of freedom to design according to the contractor’s capacity together with the freedom to innovate for more efficient solutions is intended to benefit the client in both cost and quality. Given that the contractor has much greater responsibility for the longer- term results under the OPBRC contract, a change of focus is also applied for the supervision consultant. Under OPBRC the consultant is normally referred to as a monitoring consultant. The team for monitoring is normally reduced in size and scope of work but will contain highly experienced staff who are expected to identify issues and shortcomings in the designs and works without the need for an extensive team of technicians supervising every move. Following on from this, the relationship between the contractor and the consultant can avoid the conflict that often arises under conventional contracts and should embrace a highly cooperative approach that identifies and resolves issues before they are built into the final works. A direct result of this should be that the consultant aims to avoid holding back the contractor with approvals for many stages of the process. This should lead to a contractor who is only limited by his own construction capacity. Time savings from OPBRC contracts are intended to benefit the client and the contractor. Despite frequent references to cost savings, OPBRC contracts do not always lead to reduced costs. Over time it is expected that contractors will become more confident in their ability to deliver at certain costs but cost savings should not be expected in the early years of the OPBRC approach. The potential for OPBRC to resolve many of the difficulties encountered under conventional contracting approaches makes it an attractive choice. The points made above reflect an ideal approach under OPBRC. Misunderstandings and conflicts can still arise if one or more of the parties are not sufficiently knowledgeable regarding the responsibilities and objectives. The Mozambican Road agency, ANE-IP, has been applying OPBRC for some years now and it is expected that the skills gained in the sector to date will allow the tenders under the MPA Project to be successfully concluded with potential advantages in both time and the quality of the outcome. 10 2 Overview of Country, Borrower and Marketplace 2.1 Operational Context The MPA will support improvement of the N1 North South corridor, which is one of the key road links in the country and the most important infrastructure need by the GOM to unlock development potential in central and northern Mozambique and integrate the isolated provinces with the rest of the country. The MPA’s facilitation of inter-regional North-South trade through the rehabilitation of the N1 road corridor and the inclusion of road sections in the fragile conflict affected provinces of Cabo Delgado and Sofala can contribute to poverty reduction and address the underlying causes of fragility and insecurity in northern and central Mozambique. The inclusion of social component addressing the needs of women and implementing a community-based road maintenance program on selected feeder roads in the program areas will also benefit women, youth and other vulnerable members of the community through income generation and skills training. The beneficiaries of the program includes all users of the corridor, which is a diverse group, including local people living along the N1 program areas, as well as inter-provincial road users, such as large freight companies transporting commerce along the nearly 2,500 km corridor, extractive industries getting their minerals to the ports, farmers and traders transporting agricultural commodities to urban centres and the many SMEs involved in these activities. Over 5 million people are estimated to be connected to the rest of the country and better integrated to the national economy as a result of the proposed program. The total program will create both direct and indirect jobs through construction and maintenance activities and will facilitate enhanced economic activities because of improved transportation services. Road users, including transport service passengers engaged in economic and social activities along the North- South corridor in Mozambique and in neighbouring countries in the north, will benefit from the improved road condition, enhanced regional integration, safer road journeys and the reduction in travel time and operational costs. 2.2 Governance aspects The country remains susceptible to further security concerns, though a return to full-scale civil war is unlikely. Bureaucratic delays in the award of contracts are probable since some procurement will follow a Post Review approach and will consequently require approval from the Administrative Court before any payment is made: 11 The Governance related challenges/solutions are as follows: • To maintain a safe and secure working environment for contractors to implement the works. This is particularly relevant to sections in Cabo Delgado but is essential throughout the country; • To create confidence in bidders that payments through the contracts will be completed in a timely manner; • To ensure that vehicle overloading on the roads does not prejudice the work during both construction and maintenance. Vehicle overloading can rapidly lead to the deterioration of the road pavement and the subsequent failure of the road; • To provide for the maintenance of the rehabilitated roads and ensure that this is implemented to the accepted standards. In the longer term the infrastructure will need periodic maintenance (resealing or overlay) at the appropriate point in time in order to extend its effective period of service; • To ensure that, while the program will enhance transport infrastructure and road access, it does not create unintended consequences for the communities where they operate, including Gender-Based Violence (GBV). Appropriate awareness must be raised to mitigate negative impacts. 2.3 Economic Aspects Mozambique has been dedicating substantial fiscal resources to transport infrastructure development—more than other countries in the region to upgrade its network. The Government allocated on average USD400 million (2 percent of GDP) annually to the road sector from 2010 to 2018. Before the debt crisis, the Government had spent a significant amount of money rehabilitating and upgrading national roads, with a peak of 64 percent of the total spending in the road sector in 2014. As a result of this intensive government investment in upgrading projects, the total length of paved roads increased by 35 percent, from approximately 6,100 km in 2010 to 8,268 km in 2020. These investments led to significant improvements and travel time reductions notably along the East-West corridors. However, investments in the North-South corridor along the N1 have not had the same attention and today, of the total 2,471 km nearly half are in poor condition, across areas of high climate vulnerability, contributing to the economic isolation of the northern provinces of the country. After the debt crisis, available resources diminished to about USD200 million (1 percent of GDP) in 2018. According to the World Bank analysis, currently available resources are insufficient to provide adequate maintenance for the road network. Under 12 a constrained budget scenario analysis, approximately USD182 million per year would be needed to achieve maximum net present value from the current paved road network; approximately USD400 million per year for the total road network. With current resources (~USD200 million), it is likely that the road asset value will continue to deteriorate. In order to address this deficit Mozambique needs to: (i) on the one hand, improve the efficiency in the use of the available funds (in terms of prioritization programs, construction methods, contracting modalities etc), and (ii) increase and diversify the sources of revenue over the long run. 2.4 Sustainability Aspects The OPBRC approach includes a long-term maintenance horizon which is expected to help to reduce the potential for short term failures of pavements as has occurred for some sections in the recent past. The pressure brought by the responsibility for longer term maintenance will incline the contractor to pay greater attention to quality control and construction standards. Evidence suggests that the longer the term of maintenance the more pressure is felt to achieve a superior result. Clearly there will be a cut-off point, whereby shorter terms of maintenance will not create sufficient pressure to construct to an adequate quality. Five years is suggested as a minimum term for the maintenance component of the OPBRC contracts. ANE and the Road Fund (FE) recognise the need to prioritise periodic maintenance (reseal or overlay) to prevent medium term failure. A reseal on a DBST surface in its eighth year is typical. This should be programmed and implemented at the right point in time regardless of the appearance of the road. The addition of the reseal will greatly extend the life of the road surface if implemented at the right time. Too late and the road will deteriorate regardless of the reseal. Economists and engineers can demonstrate that the periodic maintenance of paved roads brings one of the highest levels of economic returns of any activity in the road sector. 2.5 Technological Aspects The program areas are defined as the sections of N1 road corridor of Mozambique. This corridor is the key to Mozambique’s North-South connectivity: N1 is the longest and most important Mozambican highway running parallel to the Indian Ocean connecting the southern province of Maputo to the most northern province of Cabo Delgado. It is 2471 km long, crossing eight provinces (Maputo, Gaza, Inhambane, Manica, Sofala, Zambezia, Nampula and Cabo Delgado), connecting some of the most populated areas of the nation (the main cities of Maputo, Beira and 13 Nampula) and six provincial capitals, namely: Maputo, Xai-Xai, Maxixe/Inhambane, Nicoadala/Quelimane, Nampula and Pemba. The N1 corridor also links up to four major international (east-west) road and rail corridors, namely the N4 from the Port of Maputo to South Africa (Johannesburg), the N6/N7 from the Port of Beira to the hinterland of Zimbabwe, Zambia, Malawi and Democratic Republic of Congo, the N11 from the Port of Quelimane to Malawi / Zambia and the N13 from the Port of Nacala to Malawi / Zambia. Prioritization and phasing of program roads: During the preparation of the proposed program, the N1 corridor was inspected and a rapid inventory and condition survey was carried out in October 2021. According to the survey results (presented in more details in Annex 3), approximately 40 percent (1,053 km) of N1 corridor is in a poor condition and requires major rehabilitation. The proximity of the N1 to the Indian Ocean and its increasing exposure to tropical storms and cyclones has negatively impacted accessibility on some sections of the N1, cutting off fragile regions, impacting logistics, commodities prices, access to health and education services as well as impeding humanitarian relief and post disaster recovery efforts. The very poor condition of some of these road sections means that they can no longer be maintained and require urgent rehabilitation and/or reconstruction including replacement of some bridges. Further investigations will be carried out during concept design stages. Proposed contractual modality: The proposed investment and maintenance work under MPA will be delivered through OPBRC. As mentioned above, OPBRC is different from traditional ad-measurement civil works contracts insofar as the Contractor takes on responsibility for specific outcomes or results defined in the contract, by agreeing to meet predefined "Service Levels" that are specified by the Employer. During the bidding process, contractors will compete by proposing fixed lump-sum prices for assuring pre-defined Service Levels on the roads, during a 10-year period. Besides the rehabilitation and improvement works, OPBRC will also address routine maintenance and periodic maintenance cycle towards the end of the OPBRC. Under OPBRC the Contractors will not be paid directly for "inputs" or physical works, but rather on the basis of outputs (per km road improvement / rehabilitation) and outcomes (achievement of service levels over the performance period). The detailed design will be prepared by the Contractor, hence transferring some of the risks to the contractor. Basic concept designs will be prepared by the Employer/ANE to ensure that 1As a result of cyclone Gombe (March 2022), the N1 between Nicoadala and Namacura was closed for 4 days for light vehicles, and 6 days for heavy vehicles. 14 minimum design standards are adhered to and bids are prepared on equal terms (are comparable). 2.6 Technical Challenges A number of problems that have occurred on previous N1 rehabilitation projects have been related to materials availability. Lessons from those projects must be highlighted and the bidding documents must include orientation of the bidders to provide durable solutions that overcome the previous issues. In particular, the decisions that are made regarding the road pavement materials will be critical to a successful result. Maintenance of Adjacent Feeder Roads: Many rural road maintenance systems have been tried over the preceding decades. These have included the lengthman approach, the area-based maintenance system and also OPBRC among others. A key aspect in developing a maintenance system for feeder roads will be achieving the maintenance of access despite the increasing impact of heavy rain and flooding brought about by the changing climate and the impact of increasing population on land use in catchment areas. Ideally a system needs to be capable of delivering minor repairs to bridges and smaller drainage structures in order to reduce the occurrence of loss of access through failure of such structures. 2.7 Regulatory Challenges Vehicle overloading in Mozambique is a serious risk to the longevity of road infrastructure and a major road safety hazard. Weights and cargo combinations of motor vehicles is regulated by Decree 14/2008 of 25 June 2008, issued by the Council of Ministers. Vehicle loading is controlled through the establishment of fixed and portable weighbridges in the country, managed by ANE, IP. Of the 15 fixed weighbridges, 7 are located on the N1 corridor. An additional 2 fixed weighbridges are being constructed on the N1, at Lurio River in Cabo Delgado and on the north bank of Save River in Sofala. Evidence from ANE as well as from a Vehicle Load Monitoring (VLM) survey done in 2016 suggests that the incidence of vehicle overloading has reduced from over 30 percent in the early 2000s to less than 20 percent in 2020, albeit still very high. The Government is seeking further support to modernize the weighbridge equipment with automated systems to minimize the human factor as well as to allow for remote operations. The MPA is proposed to finance the preparation and support the enactment, and execution of a new Road Bill (Act). The Road Bill will cover: definitions; road management; road classification, ownership, public versus private 15 roads; road asset conservation and management; climate resilient road construction, improvement and maintenance works; road safety based on principles of Safe System Approach and in line with UN Road Safety Pillars; road use, road access and road restrictions; financial provisions for road management; offences, penalties and recoveries; etc. This is a comprehensive undertaking that would require careful considerations of the entire road network planning, financing, management, and execution and the long-term nature of the MPA framework will be an ideal instrument. 2.8 Personnel/Cultural Challenges The mobilisation of international staff by large contractors and the use of a largely migrant workforce can bring with it significant challenges in ensuring the harmonious interaction between the various contributors to infrastructure development and their host communities. Managing cultural differences and expectations for a large community with differing needs and traditions can be a considerable challenge. Contractors will be expected to comply with all GBV/SEA/SH clauses in the construction contracts. The contractors and consultants will need to develop codes of conduct for all staff, communicate the key behavioural expectations outlined in those documents and maintain regular meetings with all stakeholders in order to identify issues before they pass the threshold and become problems or incidents. Codes of conduct must be translated into appropriate languages and be signed by the individuals employed on the project such that the room for misunderstandings is ruled out. A grievance redress mechanism will be essential in allowing voices to be heard in an appropriate manner. All of this will be aimed at minimising the potential for incidents that might impact on the delivery of the much- needed infrastructure. Key conclusions As a large country in great need of improved infrastructure, Mozambique will benefit from the realisation of the objectives of this project. The conditions for implementing the project are in place and the challenges can be overcome through careful consideration of the broader environment in which the project will operate. 2.9 Summary of PESTLE Analysis 16 A Political, Economic, Social, Technological, Legal and Environmental (PESTLE) analysis was used to assess the operating and business environmental influences and how they directly or indirectly influence and shape a market. The key findings from the PESTLE analysis are as follows: Table 2: PESTLE Analysis Context Factor Opportunity and Threat There is strong multi-party political support Government for improvements to the N1 hence there is low Support risk of the loss of political support. The damaged sections of the N1 that are in poor condition are a major concern to the Prioritizatio Government. Strong criticism of GOM policy n would be noted if the N1 was not a focus of attention for infrastructure investment. Political The N1 is considered to have high strategic importance when considering national National security. The sections in Cabo Delgado in Security particular will help to re-establish normality after the recent local conflict situation. Having the full length of the N1 in good or fair condition is an important consideration for National national unity. Neglected sections would lead Unity those areas of the country to feel forgotten by central government. The N1 is a major driver of economic development. Keeping the N1 road in acceptable condition is critical in the support of local, national and regional economic growth. A major component of the traffic blend are heavy goods vehicles and large Regional buses. Vehicle operating costs for these Developmen vehicles have a direct impact on transport t pricing. Economic The N1 in good condition provides a significant economic boost to local and national suppliers and can provide considerable stimulus to local economies alongside the road. The N1 as a transport corridor is the only Affordable accessible means of travel between provinces transport and to the capital city for the vast majority of Mozambicans. Air transport is outside of the 17 Context Factor Opportunity and Threat financial capacity of the majority of the country’s population. The increasing population growth in urban centers in the country require that food and Essential other produce is efficiently and economically Supply transported from rural areas. The N1 Chain provides the infrastructure required to Infrastructur transport agricultural production to urban e centers and distribute farm inputs to rural areas. The adoption of the OPBRC approach will mean that financial capacity and previous experience requirements for bidders will lead to the exclusion of all domestic contracting companies from the bidding process. Inclusion of some local companies through Capacity sub-contracting arrangements may help to Developmen increase the national input to these works. t Ultimately, the lack of any long-term plan to bring domestic contractors up to a level where future contracts for such works are accessible will be considered a failure from the perspective of the domestic construction market. As mentioned above, the unity of the country is supported by the equitable distribution of investment to all regions. Directing Equity of infrastructure investment to the upkeep of Investment this critical transport corridor is a visible indicator that government is acting in the interest of all its citizens. The N1 is the most important supply and distribution route for goods and medicines, Social Health and particularly considering that these are wellbeing frequently dispatched from Maputo at the southern limits of the country. The reverse of the previous note is also true. The N1 provides access from the provinces to Facilitation the capital city and the regional capitals of of Social Beira and Nampula. Higher education Participation establishments are generally based in the major cities. Many residents in these cities have arrived from rural areas and frequently 18 Context Factor Opportunity and Threat return for family visits. This is particularly true for labor working in the mining sector in South Africa as they return with loaded vehicles during their annual leave. The construction contracts proposed as part of this project will have a positive impact for the creation of employment and business Employment opportunities both local to the construction Generation activities and at regional hubs where company procurement and support services might be based. Mozambique has high potential as a tourist destination. The development of this potential could be greatly supported if road conditions along the major transport corridors are maintained at an acceptable level. In Opening particular, the overland tourist market for Up/Post private family travel and larger organized Pandemic group tours may struggle to develop if the N1 and connected trunk roads do not gain sufficient investment. The tourism sector has been severely hit by Covid-19 and by perceived security issues in recent years. The adoption of performance-based contracts (OPBRC) in this project with long maintenance periods (10 years) will help to guarantee a Results significantly long horizon for the maintenance Orientated of the roads in good or fair condition. Durability has been an issue for previous rehabilitation works that did not incorporate Technolo extended maintenance periods. gy Through the project, support will be provided Extending to the development of maintenance capacity the Reach to at local community level for minor rural roads Adjacent connected to the N1 or in the vicinity of the Stakeholder works sections. This is expected to increase s the zone of impact for the benefits that accrue to affected communities. The road agencies in Mozambique are Future currently heavily dependent on external Maintenance contractors for sealed road provision. As a Capacity minimum objective, the development of domestic capacity for periodic maintenance 19 Context Factor Opportunity and Threat in parallel with such projects should be considered. In a broader sense, the exclusive use of internationally owned contractors reduces the beneficial results of public capital investment projects and misses the opportunity to attain longer term locally based capacity development beyond the actual infrastructure itself. Such infrastructure construction projects will require skilled staff that may not be available in the local or national setting. The authorization for firms to bring such Immigration specialists while being restricted with respect to other lesser skilled staff requires clear presentation of the rules and regulations prior to bidding in order that difficulties are avoided. The responsibilities of the parties to the contract with respect to compensation of Compensati project affected persons must be clearly on to Project elaborated in the bidding documents. The Affected preparation of Resettlement Action Plans People (RAPs) and the mechanisms for the payment of compensation can lead to significant delays if teams are unprepared. Legal Contractors will be required to comply with labor laws and Health and Safety Regulations. Clear reference to all the appropriate laws and institutional responsibilities should be Compliance outlined in the bidding documents. Further, with Local the contractor will be responsible for Laws and management of his plant and equipment for Regulation the duration of the contract. The development of adequately safe practices for traffic management will be critical to avoiding accidents and loss of life from misuse. The successful contractors will naturally be concerned regarding the control of over- loading on newly constructed sections of Load Control road. The risk for the contractor from overloaded heavy goods vehicles using the newly constructed road is a very real concern. The extent to which a contractor can manage traffic along the road during construction 20 Context Factor Opportunity and Threat needs to be clearly laid out in the bidding documents. The N1 tends to run parallel with the coastline of Mozambique. This means that most sections of the road will have a number of major river crossings with susceptibility to flood damage in a changing climate scenario. The risk of flooding that exceeds the normally anticipated flood levels is becoming a greater concern as recent cyclones have shown us. Flood Risk Some recent improvements have been made to the ANE suite of design documents but more remains to be done. Lessons on the most appropriate types of crossing structures are still being learnt and documented. The client is advised to clarify his expectations in the bidding document so that the intended transfer of risk to the contractor is done in an open and transparent manner. The contractor is expected to comply with all environmental protection laws. Methods for the control of potential damage from Environm hazardous practices and materials is to be ent Environment developed by the contractor in his/her al contractor Environmental and Social Legislation Management Plans (cESMPs). It should be made clear that relevant laws will be applied, and the fines or steps required to resolve damage to the environment must be completed. The presence of heavy plant and construction teams in often remote environments presents an opportunity for environmental improvements to be incorporated into the Increased works. These may include efforts to reduce Beneficial runoff from barren catchments through tree Impact planting and the incorporation of catchment through management through landscaping and Peripheral accepted environmentally beneficial Works techniques. The potential for contractors to implement such improvements, which may be beneficial in reducing excessive flooding and could provide communities with improvements to their surroundings, could be 21 Context Factor Opportunity and Threat explored through the development of local stakeholder engagement clauses. The development in recent years of solar street lighting provides the opportunity for communities to benefit from such investment at selected locations. Villages, towns and urban sections of the road and major junctions should be identified during concept design for such potential improvements. The provision of facilities to provide safe and environmentally controlled rest points for drivers and others engaged in long distance road transport should be considered under the project. Such installations would help to reduce the negative impact of drivers randomly parking vehicles overnight. 3 Client Capability and PIU Assessment 3.1 Experience Recent projects such as the IDA funded IFRDP have helped to create a small team of professionals within ANE who have gained significant experience of delivering infrastructure under World Bank funding and conditions. A dedicated Project Implementation Unit (PIU) has been established within ANE which will focus exclusively on the World Bank projects that impact on the road sector. This PIU currently covers the IFRDP, the SATCP and the MPA (SRSEIP). The staff allocated to this PIU are recognised as being some of the most experienced employed by ANE. A similar PIU will be established in the MTC which will provide similar implementation management for the relevant activities. The major works under the MPA are to be implemented following the Output and Performance-Based Road Contract (OPBRC) approach. In recent years, ANE has managed OPBRC works in the province of Gaza. These works were initiated in response to climate emergencies and were also financed by WB. Four sections of road were rehabilitated following extensive damage from flooding. A concept design was prepared and four civil works contracts were then tendered for repair and rehabilitation works on sections of the N220, N221, R859 and the R452. These contracts omitted the longer-term maintenance normally expected with OPBRC projects as they included 22 Design and Build only. Initial difficulties were encountered due to the lack of familiarity with OPBRC contract forms. This shortcoming extended to the consultants and the contractors who also exhibited an initial lack of understanding of the expectations of OPBRC largely due to the lack of experience. Despite some delays, these works were successfully implemented. The learning curve has now been traversed and the road sector actors at the appropriate level are now generally aware of the particularities of OPBRC. ANE has an ongoing OPBRC contract under the IFRDP that covers the rehabilitation and improvement of the N10/N1 from Quelimane to Namacurra (68km). Hence, the combined experience now available within ANE and the pool of service providers is sufficient to raise the expectation that successful implementation of performance-based road infrastructure contracts is achievable. Despite this, ANE intends to include the recruitment of an experienced Procurement Specialist and two procurement officers to reinforce the PIU for an initial period of two years with the objective of reducing the workload on the existing staff which will help to reduce delays in processing procurement issues. Funding for these positions will come from the IFRDP budget. MTC also plan to recruit a procurement specialist to help support their procurement activities. In this case, funding will be made available under Component 3 of the MPA. 3.1.1 Contract management capability and capacity ANE and MTC further anticipate the need to hire additional staff to support the project through the implementation period. This will include technical, environmental and social oversight of civil works and road safety activities. The following specialists will be hired among others: ANE - PIU Headquarter Level:  One Environmental Specialist;  One Social/ Resettlement Specialist;  One GBV/SEA/SH Expert;  One Senior Highway Engineer;  One Road Safety Expert; and  One Drainage/ Bridges Engineer. ANE - PIU Provincial Level:  One Environmental Specialist – each per province;  One Social/ Resettlement Specialist – each per province;  One GBV/SEA/SH Expert – each per province; and 23  One Occupational Health and Safety (OHS) Officer – each per province. MTC - PIU Headquarter Level:  One Data Base Specialist-Safety (development of a centralized Database for the collection of road safety statistics);  One Road Safety Training Specialist (development of road safety training at schools and community);  One Road Safety Infrastructure Development Expert (parking areas, training deport, vehicle inspection deport);  One Communication Specialist (production and management of road safety campaigns). MTC – Short Term:  One Road Safety Training Specialist (capacity development of enforcement officials);  One Road Safety Training Specialist (technical inspection of vehicles and driver training);  One Road Safety Specialist with emphasis on policy development (safety policy). In order to improve, enhance the project monitoring, transparency, social accountability and supervision of the works to be implemented in all targeted provincial roads, an innovative system with a mechanism for collecting data and images of infrastructures being constructed or finished will be implemented together with a mechanism for analysing images and data collected in real time using smartphones or drones with appropriate software. Vehicles as well as computer equipment, software and other accessories will be made available for the project team. 3.1.2 Complaints management and dispute resolution systems In terms of procurement, the complaints management and dispute resolution systems stated in the Mozambique Procurement Regulation, Decree 5/2016 of March 8, 2016, will be followed and complemented by the project-specific overall grievance and redress mechanism that will be established. The capacity of national and local institutions involved in the implementation of the project will be strengthened through project activities with that objective. Implementation will also rely on partnerships 24 with local organizations and firms. The project will have a Project Operational Manual and will specify the instruments to be used per activity. Key conclusions The PIU within ANE is considered to possess the broad capabilities required to achieve the goals of the project. The recruitment of additional staff outlined above and the further training that will be accessed through the project budget are expected to provide the necessary additional support that will reinforce implementation capacity in the relevant institutions. ANE and RF will take responsibility for the management and performance of its contracts unless such work is considered very specialized. However, where there is a requirement for specialised skills, ANE will seek to recruit and develop such skills and competencies around procurement and contract management. It should be noted that ANE has a Contract Management department which provides technical support for managing current contracts. It is acknowledged that further training will be necessary for staff at various levels throughout the implementation of the MPA. Training in WB Procurement regulations will be an important part of the project capacity building program. Certain other training activities are dependant upon the outcome of the studies that aim to identify appropriate interventions. For example, under the feeder roads maintenance work in Component 2 there is likely to be a requirement for training of community members in road construction and maintenance. Details for such training will be identified as the diagnostic tasks are completed. Hence, at this stage, the breakdown of the training budget must await the guidance of those studies. 4 Market Analysis 4.1 Market sector dynamics The road sections are proposed to be divided into large lots for the bidding process. This will attract relatively large international contractors. The potential to win more than one lot will increase this interest further still. Under these conditions the opportunities for domestic contractors will be limited to junior joint venture partnerships or as sub-contractors. Post pandemic availability of contractors and consultants is beginning to return to normal levels regarding construction resources (staff and equipment). It is hoped that competition will therefore be strong given the extended period of furlough or even unemployment suffered by many technical staff. On the other hand, companies may take the view that 25 recovery in the balance sheet needs to happen more quickly leading to higher prices. 4.2 Summary of Suppliers Based on recent tenders launched within the road sector for similar services and OPBRC civil works, the following firms are active in Mozambique and would be expected to express interest in bidding for work under the project: Table 3: Consultants Consultants Name Head Previou/RF Office Experience AIC Progetti Italy Yes LEA Associates South Yes India Asia Pvt. Ltd TYPSA Spain Yes SARI Consulting Ltd UK Yes SATRA India Yes TNM Limited Israel Yes Gauff Germany Yes Civil & Planning Yes Zimbabwe Group Aarvee Associates India Yes SWMoz SVOSVE Mozambique Yes Prospectiva SA Portugal Yes Soosung Engineering South Korea Yes B.V.I Consulting South Africa Yes 26 Consultants Name Head Previou/RF Office Experience Studi International Tunisia Yes SIPCA Engineering Yes Spain Consultants WAPCOS India Yes BETAR Portugal Yes NIPPON KOEI Co. Ltd Japan Yes Korea Engineering Yes South Korea Consultants Corp Korea Consultants Yes South Korea International Table 4: Contractors Previous Contractors Head Office ANE/RF Name Experience China Henan International China Yes Corporation Group China Railway International China Yes Group SINOHYDRO China Yes Corporation Anhui Foreign Economic China Yes Construction Group 27 Previous Contractors Head Office ANE/RF Name Experience Mota-Engil Engenharia e Portugal Yes Construção China Road and China Yes Bridge Corporation Gabriel Couto Portugal Yes Conduril Portugal Yes Engenharia China State Communication China Yes Engineering Corporation Group W.B.H.O. South Africa Yes China Jiangxi Corporation for International China Yes Economic and Techinical Cooperation Posco Engineering and Construction South Korea Yes LTD AFCONS India Yes Infraestrutures Ltd Zhongmei China Yes Engineering Group China Comunication China Yes Constrution Company, Ltd 4.3 Financial 28 Inflation internationally is noted as a concern as indicators are suggesting a widespread increase in the cost of many commodities including food and fuel. For machine-based works where fuel is a significant component of the cost, these factors will almost certainly trigger some caution among bidders potentially leading to increased costs overall. As mentioned above, the recent stability in the value of the Metical against the US Dollar is positive and the anticipated restart for the natural gas projects in Cabo Delgado may help to maintain this value. 5 Procurement Trends In the local market, international firms are not barred from open national competitive bidding processes. For low value, low risk assignments, the national and international firms compete on equal terms. Assignments can therefore be won by either national or international firms and there have been good responses from the market. However, for high risk, high value and relatively complex works and consultancies, where the market is approached internationally, in most cases only international firms will meet the technical and financial evaluation and qualification criteria. The strong institutional experience gained within ANE and from project advisory staff will support the Project teams for all procurement requirements and in the management of contracts with diverse suppliers at national and international level. Based on the list of contracts identified, the project will prepare a Procurement Plan for clearance by the Bank covering the first 18 months of project implementation. The Procurement Plan will be updated at least annually or as required to reflect the actual project implementation needs and improvement in institutional capacity. This will be updated during implementation to more fully capture the activities that are not yet defined. Interventions will be further identified following the completion of technical strategic planning, flood mapping and risk planning which will help in identifying the location and design requirements of specific investments. Key Conclusions There is no restriction to the participation of international bidders even in open national bidding processes. Several international firms are registered with local offices in Mozambique. Often, foreign companies form a consortium with local companies in order to benefit from their local market knowledge and logistical capabilities. However, given that the N1 29 rehabilitation works are relatively high value contracts and highly technical consulting services, the international market approach will also be used. The agencies will therefore continue to endeavour to understand and engage with the market in order that the selected procurement approach (national, international and limited) will produce the best results from the specific markets strategically while also ensuring that adequate qualification and evaluation criteria, with appropriate technical specifications (conformance) or adequate performance requirements, commensurate with the type, value and risk of the assignments, are used. 6 Procurement Risk Analysis The key issues and risks concerning procurement for implementation of the project are described in the table below: Table 5: Procurement Risk Analysis Description of Risk Description Risk Type Risk Owner Mitigation 1. Lack of Substantial • The PIU at ANE has All responsible experience of broad previous unit the new PIU for experience in implementing similar projects as the project at an implementing MTC. agency and will support the newly hired project team through work experience on other programs/projects. • Capacity building provided by the World Bank for upskilling the team involved. 2. Lack of Substantial The Bank will provide All responsible adherence to constant support to unit procedures due staff to ensure to inadequate adherence to the understanding of Procurement the World Bank Regulations. Procurement Regulations for IPF Borrowers 3. Challenges of Substantial The PIU will closely All responsible bids submission monitor market unit due to COVID-19 trends, and promptly movement propose more efficient restrictions procurement imposed by approaches and many countries methods. 30 Description of Risk Description Risk Type Risk Owner Mitigation worldwide. 4. Ministries/ Substantial • Establish a steering Agencies committee to coordination in resolve the the overlapping issues implementation and supervise and of the activities support the project may challenge implementation. achievement of • Clear definition of PDO (definition roles and of communication roles/responsibili mechanism ties and between the parts. communication between them – may make coordination of activities difficult). 5. Delays in the Substantial Establish a check list All responsible administrative of main concerns unit courts. during the procurement implementation and monitor the critical phases and the required documentation. In addition, make sure no national supplier or consultant is hired without Cadastro Único. 6. Bidders Substantial Utilise the World Bank All responsible deliberately Procurement unit under-bid, Regulations for IPF hence, reduce Borrowers. quality and manage variation to recover margins. Abnormally high/low bids 7. Poor planning of Substantial Improve contract All responsible projects, management skills, unit contract KPI’s to measure the administration outputs rather than and quality of solely the inputs rehabilitation 8. Variation in Substantial Improve All responsible scope of specifications, Terms unit 31 Description of Risk Description Risk Type Risk Owner Mitigation work/market of reference and cost prices after modelling projects. award of Also, improve contract supplier’s engagement 9. Exchange rate Substantial Close monitoring of All responsible volatility financial markets unit between the US Dollar and Metical 10. Poor Substantial Provide storage All responsible transport and facilities in the unit storage links in rehabilitation the project locations relevant Provinces 11. Supplier Substantial Improve the All responsible collusion and marketing of future unit exploitation projects and request attendance at pre bid meetings or at Association of Contractor meetings 7 Procurement Objective The Procurement Objective is: To take full responsibility for procurement under the Multi-Phase Programmatic Approach Project, by procuring the necessary works, goods and services for its implementation in order to attend the Project’s Development Objective; which is to improve safety, resilience, and accessibility to jobs and socio-economic opportunities along the North South N1 corridor. Ensure timely, transparent and competitive bidding processes at the national and international level and acquire goods and services of good quality that represent good value for money. 8 Summary of PPSD to inform the Bank’s preparation of the PAD 8.1 Recommended Procurement Approach for the Project a. Contract Strategy Goods, services and civil works will be prepared in economical packages to attract local and foreign bidders who are qualified, can offer good prices 32 and can demonstrate their ability to complete contracts within stipulated timeframe resulting in good value for money. Packaging for procurement is decided in such a way that encourages adequate participation and is based on two principal forms of procurement packaging. (i) the grouping (or bulking) of procurement requirements within a procurement category for the purpose of acquiring them under a single contract, and (ii) the division of one requirement into multiple lots, where bidders can submit bids for one, several or all lots (as would be stipulated in the procurement documents), and where a contract could be awarded for each lot. The following have been taken into account when considering procurement packaging: i. The likelihood of local suppliers being able to fulfill the requirements and whether the packaging would limit their participation. ii. If the group of requirements are needed (or can be received) simultaneously or whether there are different delivery dates between requirements. Unless the selected supplier can deliver at the various selected delivery intervals, receiving all the goods at one time could result in a potential logistical problem; therefore, under these circumstances it may be preferable not to package the various requirements. iii. The availability of several suppliers that can provide a combination of procurement categories as may be required in the case of supply, installation, commissioning and training. iv. If the PIU lacks the capacity to coordinate several suppliers, this may create a preference for packaging to reduce the number of suppliers that the PIU would have to coordinate. b. Procurement Approaches for the required works, goods, non-consulting and consulting services under the proposed projects Based on the project requirements, technical solutions and supply base, procurement strategy for the proposed Project is as follows: i. Works: Most of the civil works are complex. Therefore, for civil works for Road rehabilitation and maintenance, an international market approach will be adopted with request for bids, single stage bidding or with post-qualification will be used. ii. Goods: Most of Goods have been packaged into International/National market approach, request for bids, single stage bidding will be used. 33 iii. Non-consulting Services: Most non-consulting services have been packaged into International/National market approach, request for bids, single stage bidding will be used. Other small requirements such as system for appointment, booking, and management and nonphysical entry points and Printing of Road Safety handbooks and Brochures have been packaged into Limited market approach, Request for Quotations. iv. Consulting Services: For specialized consulting assignments, consulting services for conceptual designs and construction supervision of Road Rehabilitation and Maintenance works, Open International market approach and Quality and Cost Based Selection (QCBS) will be used. For PIU and other individual consultants will be hired through open and limited Individual Consultant Selection. For less complex consulting assignments Open national market approach will be used. Additionally, since there may be reduced competition due to COVID, Bid Securing Declaration may be used instead of the bid security, the time for submission of bids/proposal can be extended in competitive national and international procedures, if bidders request an extension and, Direct Selection will also be used under all procurement categories as appropriate, based on technical expertise and previous performance, and financial capacity. c. Procurement Thresholds The table below shows the Thresholds and Procurement Methods to be used under the Project given a risk rating of Substantial. Table 6: Procurement Thresholds Prior-review Thresholds for Procurement Methods Thresholds Procurem Limit for Post Works Goods, IT & Non-Consulting Shortlist of National ent Review Services Consultants Type ($`000) Works 10,000 Open Reques Reques Internatio t for t for Engineeri Open Open nal or Quotati Open Quotati Consulti ng & Nation Nation ICB on or internatio on or ng Constructi al or al or ($' M) Nationa nal or ICB Nationa Services on NCB NCB l ($' M) l ($' M) Supervisi ($' M) ($' M) Shoppin Shoppin on ($' M) g ($' M) g ($' M) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultan 1,000 10 10 0.5 2 2 0.2 0.3 0.3 ts (Firms) Individual 300 Consultan ts d. Procurement Plan 34 Based on the list of contracts, which cover the duration of Phase I of the MPA and identified in the tables below, the project will prepare and the Bank will be requested to clear the Procurement Plan which will be updated at least annually or as required, to reflect the actual project implementation needs and improvement in institutional capacity. Table 7:List of procurement processes under both ANE and MTC PIUs by Component: MPA Component 1: Safe and Resilient Road Connectivity Procurem ent Estimated Cost Bank Approach/ Selection No. Activity Description Category Oversight Me thod (USD) Com petition Prior- Open Request for 1 Rehabilitation and maintenance of N1 road fromInchope – Gorongosa (70 km) 42,817,049 Works review International Bids Prior- Open Request for 2 Rehabilitation and maintenance of N1 road fromGorongosa - Caia Lot 1 (0-84km) 50,434,225 Works review International Bids Prior- Open Request for 3 Rehabilitation and maintenance of N1 road fromGorongosa - Caia Lot 2 (84-168km) 42,485,867 Works review International Bids Prior- Open Request for 4 Rehabilitation and maintenance of N1 road fromChimuara – Nicoadala Lot 1 (0-88km) 52,610,561 Works review International Bids Prior- Open Request for 5 Rehabilitation and maintenance of N1 road fromChimuara – Nicoadala Lot 2 (88-176km) 52,610,561 Works review International Bids Prior- Open Request for 6 Rehabilitation and maintenance of N1 road fromMetoro – Pemba (94km) 54,701,737 Works review International Bids Consultancy services for Conceptual Design, bidding documents, support in procurement and supervision for the Prior- Open 7 Rehabilitation and Maintenance of OPBRC civil works of N1: Package 1: Inchope-Gorongosa (70km ) and 8,600,000 Consultancy QCBS review International Gorongosa-Caia Lot 1 (0-84km ) Consultancy services for Conceptual Design, bidding documents, support in procurement and supervision for the Prior- Open 8 Rehabilitation and Maintenance of OPBRC civil works of N1: Package 2: Gorongosa-Caia Lot 2 (84-168km ) and 9,000,000 Consultancy QCBS review International Metoro - Pem ba (94km ) Consultancy services for Conceptual Design, bidding documents, support in procurem ent and supervision for the Prior- Open 9 Rehabilitation and Maintenance of OPBRC civil works of N1: Package 3: Chim uara-Nicoadala Lot 1 (0-88km ) 9,800,000 Consultancy QCBS review International and Chim uara-Nicoadala Lot 2 (88-176km ) Consultancy services for Preparation, Design and supervision of civil works for the High Crash risk improvement Prior- Open 10 4,800,000 Consultancy QCBS program review International Post- 11 Consultancy services for Design and supervision of the civil works for the Safe school program 160,000 Consultancy Open National QCBS review Prior- Open 12 Consultancy services for Road Safety Audit for MPA priority sections 2,000,000 Consultancy QCBS review International Prior- Open 13 High crash risk improvement civil works 25,000,000 Works QCBS review International Post- 14 Safe school programcivil works 1,840,000 Works Open National QCBS review Total Component 1 356,860,000 MPA Component 2: CommunityEngagement and Women Empowerment Procurem ent Estimated Cost Bank Approach/ Selection No. Activity Description Category Oversight Me thod (USD) Com petition Prior- Open 1 Consultancy services for Preparation of feeder road maintenance packages and implementation support 1,500,000 Consultancy QCBS review International Post- Open 2 Consultancy services for Gender analysis and development of Gender Action Plan 400,000 Consultancy QCBS review International Post- Open 3 Consultancy services for Development/ adaptation of community mobilization strategy 400,000 Consultancy QCBS review International Feeder roads pilot projects implementation and economic empowerment activities - to be defined by diagnostic Post- 4 4,500,000 Works Open National QCBS study review Total Component 2 6,800,000 35 MPA Component 3: Improved Road SafetyManagement Procurem ent Estimated Cost Bank Approach/ Selection No. Activity Description Category Oversight Me thod (USD) Com petition Prior- Open 1 Consultancy services for Road safety technical assistance to the MTC/INATRO 2,500,000 Consultancy QCBS review International Prior- Open 2 Consultancy services for Development and installation of crash database 1,000,000 Consultancy QCBS review International Post- 3 Consultancy services for Organizational review of INATRO 150,000 Consultancy Open National QCBS review Prior- Open 4 Consultancy services for Motorization management diagnostic study 800,000 Consultancy QCBS review International Prior- Open 5 Consultancy services for Diagnostic review of inter-city public bus operations 1,000,000 Consultancy QCBS review International Post- 6 Consultancy services for Preparation of post-crash response pilot 100,000 Consultancy Open National QCBS review 7 Financing of other RS priority activities to be defined by diagnostic studies 3,350,000 Various - - - 8 Implementation of post-crash response pilot 900,000 Various - - - Total Component 3 9,800,000 36 MPA Component 4: Institutional Development and Project Management Procurem ent Estimated Cost Bank Approach/ Selection No. Activity Description Category Oversight Me thod (USD) Com petition Prior- Open 1 Consultancy services for SEA/SH/GBV Prevention and Management – Third Party Service Provider 6,000,000 Consultancy QCBS review International Prior- Open 2 Consultancy services for SEA/SH/GBV Prevention and Management – Third party Monitoring Services 1,500,000 Consultancy QCBS review International Post- Open 3 Consultancy services for ESF systemassessment 200,000 Consultancy QCBS review International Post- Open 4 Consultancy services for Preparation of Climate resilient Design manuals 500,000 Consultancy QCBS review International Prior- Open 5 Consultancy services for preparation of a new road Bill and of auxiliary surveys and studies 1,100,000 Consultancy QCBS review International Consultancy services for review of PPP framework in the Road Sector and preparation of PPP feasibility Post- Open 6 800,000 Consultancy QCBS roadmap review International Post- Open 7 Consultancy services for Development of a primary road network tolling strategy 500,000 Consultancy QCBS review International Prior- Open 8 Consultancy services for Vehicle Load Management (weighbridge) analysis and of auxiliary surveys and studies 1,000,000 Consultancy QCBS review International RF/ANE Supplementary Support Post- 9 Consultancy services of Environmental Specialist for ANE PIU 250,000 Consultancy Open IC review Post- 10 Consultancy services of Social/ Resettlement Specialist for ANE PIU 250,000 Consultancy Open IC review Post- 11 Consultancy services of GBV Specialist for ANE PIU 250,000 Consultancy Open IC review Prior- 12 Consultancy services of Drainage/ Bridge Engineer for ANE PIU 400,000 Consultancy Open IC review Prior- 13 Consultancy services of Senior Highway Engineer for ANE PIU 400,000 Consultancy Open IC review Prior- 14 Consultancy services of Road Safety Expert for ANE PIU 720,000 Consultancy Open IC review Prior- 15 Consultancy services of Road Safety Infrastructure specialist for ANE-MTC PIU 720,000 Consultancy Open IC review Post- 16 Consultancy services of Monitoring and Evaluation Specialist for ANE PIU 250,000 Consultancy Open IC review Prior- 17 Consultancy services of Procurement Specialist for ANE PIU 300,000 Consultancy Open IC review Post- 18 Consultancy services of Environmental Specialist for ANE PIU, Cabo Delgado province; 250,000 Consultancy Open IC review Post- 19 Consultancy services of Environmental Specialist for ANE PIU, Sofala province; 250,000 Consultancy Open IC review Post- 20 Consultancy services of Environmental Specialist for ANE PIU, Zambezia province; 250,000 Consultancy Open IC review Post- 21 Consultancy services of Social/ Resettlement Specialists for ANE PIU, Zambézia provinces; 250,000 Consultancy Open IC review Post- 22 Consultancy services of Social/ Resettlement Specialists for ANE PIU, Cabo Delgado province; 250,000 Consultancy Open IC review Post- 23 Consultancy services of Social/ Resettlement Specialists for ANE PIU, Sofala province; 250,000 Consultancy Open IC review Post- 24 Consultancy services of GBV Specialists for ANE PIU, Cabo Delgado province; 250,000 Consultancy Open IC review Post- 25 Consultancy services of GBV Specialists for ANE PIU, Sofala province; 250,000 Consultancy Open IC review Post- 26 Consultancy services of GBV Specialists for ANE PIU, Zambézia province; 250,000 Consultancy Open IC review Post- 27 Consultancy services of Occupational, Health and Safety Officers for ANE PIU, Zambézia province; 200,000 Consultancy Open IC review Post- 28 Consultancy services of Occupational, Health and Safety Officers for ANE PIU, Sofala province; 200,000 Consultancy Open IC review Post- 29 Consultancy services of Occupational, Health and Safety Officers for ANE PIU, Cabo Delgado province; 200,000 Consultancy Open IC review MTC Supplementary Support Prior- 30 Consultancy services of Road Safety Specialist (policy) for MTC PIU 350,000 Consultancy Open IC review Prior- 31 Consultancy services of Road Safety Specialist (data management) for MTC PIU 350,000 Consultancy Open IC review Prior- 32 Consultancy services of Procurement Specialist for MTC PIU 300,000 Consultancy Open IC review Prior- 33 Consultancy services of Database Specialist (road safety) for MTC PIU 350,000 Consultancy Open IC review Post- 34 Consultancy services of Assistant Accountant for MTC PIU 200,000 Consultancy Open IC review 35 Operating costs, goods, training, audit of project accounts (Yet to be defined) 7,000,000 Various - - - Total Component 4 26,540,000 Grand Total 400,000,000 37 38 PROCUREMENT Mozambique : Mozambique Safer Roads for Socio-Economic Integration Program PLAN General Information Country: Mozambique 2023-04-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174639 GPN Date: Project Name: Mozambique Safer Roads for Socio-Economic Integration Program Loan / Credit No: IDA / E0780 National Road Authority Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 47A003041/CP/25/2023 / Co nsultancy services for Conce ptual Design, bidding docum ents, support in procurement Component 1: Safe and Resil Quality And Cost- Open - Internationa and supervision for the Reha IDA / E0780 Prior 8,600,000.00 0.00 Canceled 2023-04-03 2023-04-24 2023-06-07 2023-07-05 2023-08-04 2023-09-08 2023-10-13 2034-04-08 ient Road Connectivity Based Selection l bilitation and Maintenance of OPBRC civil works of N1: Pac kage 1: Inchope - Gorongosa (70km) and Gorongosa - Caia Lot 1 (0-84km) 47A003041/CP/26/2023 / Co nsultancy services for Conce ptual Design, bidding docum ents, support in procurement Component 1: Safe and Resil Quality And Cost- Open - Internationa IDA / E0780 Prior 9,000,000.00 0.00 Canceled 2023-04-03 2023-04-24 2023-06-07 2023-07-05 2023-08-04 2023-09-08 2023-10-13 2034-04-08 and supervision for the Reha ient Road Connectivity Based Selection l bilitation and Maintenance of OPBRC civil works of N1: Pac kage 2: Gorongosa - Caia Lot 2 (84-168km) and Metoro - P emba (94km) 47A003041/CP/27/2023 / Co nsultancy services for Conce ptual Design, bidding docum ents, support in procurement Component 1: Safe and Resil Quality And Cost- Open - Internationa and supervision for the Reha IDA / E0780 Prior 9,800,000.00 0.00 Canceled 2023-04-03 2023-04-24 2023-06-07 2023-07-05 2023-08-04 2023-09-08 2023-10-13 2024-10-30 ient Road Connectivity Based Selection l bilitation and Maintenance of OPBRC civil works of N1: Pac kage 3: Chimuara -Nicoadala Lot 1 (0-88km) and Chimuara -Nicoadala Lot 2 (88-176km) 47A003041/CP/30/2023 / Co nsultancy Services for Conce ptual Design, Bidding Docum ents and Support in Procure Component 1: Safe and Resil Quality And Cost- Open - Internationa Under Implement ment of OPBRC Civil Works of IDA / E0780 Prior 1,970,000.00 0.00 2023-05-16 2023-05-21 2023-05-22 2023-05-22 2023-07-15 2023-08-29 2023-09-12 2023-10-10 2023-11-14 2024-08-10 ient Road Connectivity Based Selection l ation N1: Package 1: Inchope - Gor ongosa (70km) and Gorongo sa - Caia Lot 1 (0-84km) in S ofala Province under Design, Build, and Transfer Methodol ogy 47A003041/CP/31/2023 / Co nsultancy Services for Conce ptual Design, Bidding Docum ents and Support in Procure Component 1: Safe and Resil Quality And Cost- Open - Internationa Under Implement IDA / E0780 Prior 2,100,000.00 0.00 2023-05-16 2023-05-21 2023-05-22 2023-05-22 2023-07-15 2023-08-29 2023-09-12 2023-10-10 2023-11-14 2024-08-10 ment of OPBRC Civil Works of ient Road Connectivity Based Selection l ation N1: Package 2: Gorongosa - Caia Lot 2 (84-168km) and M etoro - Pemba (94km) under Design, Build, and Transfer M ethodology 47A003041/CP/32/2023 / Co nsultancy Services for Conce ptual Design, Bidding Docum ents and Support in Procure Component 1: Safe and Resil Quality And Cost- Open - Internationa Under Implement ment of OPBRC Civil Works of IDA / E0780 Prior 2,200,000.00 0.00 2023-05-16 2023-05-21 2023-05-22 2023-05-22 2023-07-15 2023-08-29 2023-09-12 2023-10-10 2023-11-14 2024-08-10 ient Road Connectivity Based Selection l ation N1: Package 3: Chimuara - Ni coadala Lot 1 (0-88km) and Chimuara - Nicoadala Lot 2 ( 88-176km) under Design, Bui ld, and Transfer Methodology INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 47A003041/CP/47/2023 / Co Component 4: Institutional D Individual Consult Pending Impleme nsultancy services of Environ IDA / E0780 evelopment and Project Man Post Open - National 212,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection ntation mental Specialist for ANE PIU agement 47A003041/CP/49/2023 / Co Component 4: Institutional D Individual Consult Open - Internationa Pending Impleme nsultancy services of GBV Sp IDA / E0780 evelopment and Project Man Post 212,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection l ntation ecialist for ANE PIU agement Page 1 47A003041/CP/50/2023 / Co Component 4: Institutional D Individual Consult Open - Internationa Pending Impleme nsultancy services of Drainag IDA / E0780 evelopment and Project Man Prior 400,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection l ntation e/ Bridge Engineer for ANE PI agement U 47A003041/CP/51/2023 / Co Component 4: Institutional D Individual Consult Open - Internationa Pending Impleme nsultancy services of Senior IDA / E0780 evelopment and Project Man Post 273,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection l ntation Highway Engineer for ANE PI agement U 47A003041/CP/52/2023 / Co Component 4: Institutional D Individual Consult Open - Internationa Pending Impleme nsultancy services of Road S IDA / E0780 evelopment and Project Man Prior 450,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection l ntation afety Expert for ANE PIU agement 47A003041/CP/53/2023 / Co Component 4: Institutional D Individual Consult Open - Internationa Pending Impleme nsultancy services of Road S IDA / E0780 evelopment and Project Man Prior 300,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection l ntation afety Infrastructure specialist agement for ANE-MTC PIU 47A003041/CP/54/2023 / Co Component 4: Institutional D Individual Consult Open - Internationa Pending Impleme nsultancy services of Monitor IDA / E0780 evelopment and Project Man Post 250,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection l ntation ing and Evaluation Specialist agement for ANE PIU 47A003041/CP/55/2023 / Co Component 4: Institutional D Individual Consult Open - Internationa Pending Impleme nsultancy services of Procure IDA / E0780 evelopment and Project Man Prior 300,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection l ntation ment Specialist for ANE PIU agement 47A003041/CP/56/2023 / Co Component 4: Institutional D nsultancy services of Environ Individual Consult Open - Internationa Pending Impleme IDA / E0780 evelopment and Project Man Post 250,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 mental Specialist for ANE PIU ant Selection l ntation agement , Cabo Delgado province 47A003041/CP/57/2023 / Co Component 4: Institutional D Individual Consult Open - Internationa Pending Impleme nsultancy services of Environ IDA / E0780 evelopment and Project Man Post 250,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection l ntation mental Specialist for ANE PIU agement , Sofala province 47A003041/CP/58/2023 / Co Component 4: Institutional D nsultancy services of Environ Individual Consult Open - Internationa Pending Impleme IDA / E0780 evelopment and Project Man Post 250,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 mental Specialist for ANE PIU ant Selection l ntation agement , Zambezia province 47A003041/CP/62/2023 / Co Component 4: Institutional D Individual Consult Open - Internationa Pending Impleme nsultancy services of GBV Sp IDA / E0780 evelopment and Project Man Post 250,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection l ntation ecialists for ANE PIU, Cabo D agement elgado province 47A003041/CP/63/2023 / Co Component 4: Institutional D Individual Consult Open - Internationa Pending Impleme nsultancy services of GBV Sp IDA / E0780 evelopment and Project Man Post 250,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection l ntation ecialists for ANE PIU, Sofala p agement rovince 47A003041/CP/64/2023 / Co Component 4: Institutional D Individual Consult Open - Internationa Pending Impleme nsultancy services of GBV Sp IDA / E0780 evelopment and Project Man Post 250,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 ant Selection l ntation ecialists for ANE PIU, Zambéz agement ia province 47A003041/CP/65/2023 / Co Component 4: Institutional D nsultancy services of Occupa Individual Consult Pending Impleme IDA / E0780 evelopment and Project Man Post Open - National 250,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 tional, Health and Safety Offi ant Selection ntation agement cers for ANE PIU, Zambézia p rovince 47A003041/CP/66/2023 / Co Component 4: Institutional D nsultancy services of Occupa Individual Consult Pending Impleme IDA / E0780 evelopment and Project Man Post Open - National 250,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 tional, Health and Safety Offi ant Selection ntation agement cers for ANE PIU, Sofala provi nce 47A003041/CP/67/2023 / Co Component 4: Institutional D nsultancy services of Occupa Individual Consult Pending Impleme IDA / E0780 evelopment and Project Man Post Open - National 250,000.00 0.00 2023-04-24 2023-06-12 2023-07-03 2023-08-07 2027-08-06 tional, Health and Safety Offi ant Selection ntation agement cers for ANE PIU, Cabo Delga do province 47A003041/CP/33/2023 / Pro Component 4: Institutional D Individual Consult Open - Internationa IDA / E0780 Prior 360,000.00 0.00 Under Review 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2025-10-15 ject Director for Center of Ex evelopment and Project Man ant Selection l cellence agement 47A003041/CP/34/2023 / Pro Component 4: Institutional D Individual Consult Open - Internationa IDA / E0780 Prior 300,000.00 0.00 Under Review 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2025-10-15 ject Manager for Center of Ex evelopment and Project Man ant Selection l cellence agement 47A003041/CP/35/2023 / Pro Component 4: Institutional D Individual Consult Open - Internationa curement Expert for Center o IDA / E0780 evelopment and Project Man Prior 300,000.00 0.00 Under Review 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2025-10-15 ant Selection l f Excellence agement 47A003041/CP/36/2023 / Fin Component 4: Institutional D Individual Consult Open - Internationa ancial Management Expert f IDA / E0780 evelopment and Project Man Prior 300,000.00 0.00 Under Review 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2025-10-15 ant Selection l or Center of Excellence agement 47A003041/CP/37/2023 / En Component 4: Institutional D Individual Consult Open - Internationa vironmental Safeguards Expe IDA / E0780 evelopment and Project Man Prior 300,000.00 0.00 Under Review 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2025-10-15 ant Selection l rt for Center of Excellence agement 47A003041/CP/38/2023 / So Component 4: Institutional D Individual Consult Open - Internationa cial Safeguards Expert for Ce IDA / E0780 evelopment and Project Man Prior 300,000.00 0.00 Under Review 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2025-10-15 ant Selection l nter of Excellence agement 47A003041/CP/39/2023 / Mo Component 4: Institutional D Individual Consult Open - Internationa nitoring & Evaluation Expert f IDA / E0780 evelopment and Project Man Prior 300,000.00 0.00 Under Review 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2025-10-15 ant Selection l or Center of Excellence agement Page 2 Procurement Plan I. General 1. Project Information Country: Tanzania Project Name: Resilient Natural Resources Management for Growth Project Project ID: P150523 2. Project Implementation Agency: Ministry of Natural Resources and Tourism (MNRT) Tanzania National Parks (TANAPA) Tanzania Wildlife Management Authority (TAWA) National Irrigation Commission (NIrC) Rufiji Basin Water Board (RBWB) 3. Date of the Procurement Plan: June 2017 4. Period Covered by this Procurement Plan: First 18 Months Procurement Plan II. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works and Non-Consulting Services Procurement Approaches and Methods (US$ Prior Review millions) Category (US$ Open Open Request for millions) International National Quotation (RfQ) Works ≥5 ≥ 15.0 < 15 < 0.2 Goods, IT, and non- ≥1.5 ≥5 <5 < 0.1 consulting services B. Consulting Services Category Prior Review Short List of National Consultants (US$ (US$ million) millions) Consulting Engineering and Services Construction Supervision Consultants ≥ 0.5 <0.3 < 0.3 (Firms) Individual ≥ 0.2 NA. NA. 1 Consultants [Overall Project Procurement Risk is HIGH] Notes: Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National News Paper(s) of wide circulation and/or Regional News Paper(s). 2 III. Packages for Goods, Works and Non-Consulting Services Sr./ No Contract Description Estimate Review Market Selection Evaluation Procurement Prequa Domesti Expected Expected d Cost by Bank Approach Method Options Process: lificatio c date of date of (US$) (Prior/Pos (Open- (RFP, RFB, (BAFO, (Single/Multipl n Preferen bid/ Contract t) National/ RFQ, DS Rated e Stages; (Yes/ ce proposal Signature International etc.) Criteria One/Two No) (Yes/No) opening Limited etc.) etc.) Envelopes etc) Goods Works Non-Consulting Services 3 I. Packages for Consulting Services Sr. No Contract Description Estimated Review Market Selection Shortlisti Expected date of Expected date Cost (US$) by Bank Approach Method ng bid/ proposal of Contract (Prior/Pos (Open- (QCBS, FBBS, (Yes/ No) opening Signature t) National/ LCBS, QBS, International CQS, DS etc.) Limited etc.) 4 PROCUREMENT Tanzania : Tanzania: Resilient Natural Resource Management for Tourism and Growth PLAN General Information Country: Tanzania 2017-06-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150523 GPN Date: 2018-08-17 Project Name: Tanzania: Resilient Natural Resource Management for Tourism and Growth Loan / Credit No: IDA / Q9740, IDA / 61430 Ministry of Natural Resources and Tourism Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 4. Project management, insti TZ-MNRT-16999-GO-RFQ / Pr tutional strengthening, quali Request for Quota Single Stage - One E ocurement of Printers and Co IDA / Q9740 Post Open - National 7,222.94 Completed 2017-06-11 2017-07-09 2019-04-10 2018-01-05 2019-05-01 ty assurance and control, an tions nvelope mputers d monitoring and evaluation 4. Project management, insti TZ-MNRT-40866-GO-RFQ / S tutional strengthening, quali Request for Quota Single Stage - One E upply of IT Equipment for PC IDA / 61430 Post Open - National 0.00 Canceled 2018-02-11 2018-04-08 2018-10-05 ty assurance and control, an tions nvelope U and M&E d monitoring and evaluation 4. Project management, insti TZ-MNRT-40876-GO-DIR / Lic tutional strengthening, quali ense for financial manageme IDA / 61430 Post Direct Selection Direct 0.00 Canceled 2018-01-28 2018-02-02 2018-03-09 2018-09-05 ty assurance and control, an nt d monitoring and evaluation TZ-MNRT-82691-GO-UN / Pro 4. Project management, insti curement of Motor Vehicles f tutional strengthening, quali UN Agencies (Dire IDA / 61430 Prior Direct 339,714.00 Signed 2018-10-25 2019-11-25 2018-10-30 2021-04-09 2018-12-04 2020-08-09 2019-06-02 or the Project Coordination U ty assurance and control, an ct) nit and Implementing Agenci d monitoring and evaluation es TZ-MNRT-129698-GO-RFQ / 4. Project management, insti Supply of office equipment a tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 11,042.03 Completed 2019-09-14 2019-11-07 2019-11-09 2020-04-05 2020-05-07 2020-04-30 nd computers to support imp ty assurance and control, an tions nvelope rovement of institution capac d monitoring and evaluation ities TZ-MNRT-130397-GO-DIR / S 4. Project management, insti upply of EPICOR Licences, Co tutional strengthening, quali IDA / 61430 Post Direct Selection Direct 0.00 Canceled 2019-09-16 2019-09-21 2019-10-26 2020-04-23 nfiguration and Training of us ty assurance and control, an ers under REGROW Project d monitoring and evaluation TZ-MNRT-187392-GO-RFQ / 4. Project management, insti Supply of office equipment, R tutional strengthening, quali Request for Quota Single Stage - One E esearch equipment's and co IDA / 61430 Post Open - National 0.00 Canceled 2020-08-10 2020-10-05 2021-04-03 ty assurance and control, an tions nvelope mputers to support improve d monitoring and evaluation ment of institutional capaciti es- TAWIRI TZ-MNRT-194866-GO-RFQ / 4. Project management, insti Procurement of Moto vehicle tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 0.00 Canceled 2020-10-03 2020-11-28 2021-05-27 s for the Project Coordination ty assurance and control, an tions nvelope Unit d monitoring and evaluation TZ-MNRT-187377-GO-RFQ / 4. Project management, insti Supply of office equipment a tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 3,579.13 Completed 2020-09-26 2020-10-10 2020-11-21 2020-12-01 2021-05-20 2021-02-24 nd computers to support imp ty assurance and control, an tions nvelope rovement of institutional cap d monitoring and evaluation acities for TFS 4. Project management, insti TZ-MNRT-60449-GO-RFB / su tutional strengthening, quali Request for Quota Single Stage - One E pply of office furniture's for T IDA / 61430 Post Limited 2,808.79 Completed 2020-09-26 2020-09-08 2020-11-21 2021-04-17 2021-05-20 2022-02-26 ty assurance and control, an tions nvelope AWIRI office d monitoring and evaluation 4. Project management, insti TZ-MNRT-195448-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 0.00 Canceled 2020-09-26 2020-09-06 2020-11-21 2021-05-20 Supply of ICT Equipment's ty assurance and control, an tions nvelope d monitoring and evaluation TZ-MNRT-205778-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Supply of soil sampling equip IDA / 61430 and improve infrastructure i Post Limited 20,982.00 Completed 2020-11-25 2020-12-23 2021-01-20 2021-04-17 2021-07-19 2022-02-23 tions nvelope ment's and pasture meter n priority Protected Areas TZ-MNRT-205782-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Supply of range finder, binoc IDA / 61430 and improve infrastructure i Post Limited 15,415.30 Completed 2020-11-25 2020-11-30 2021-01-20 2021-04-17 2021-07-19 2022-02-23 tions nvelope ular and walker talker n priority Protected Areas 1. Strengthen management TZ-MNRT-205784-GO-RFQ / Request for Quota Single Stage - One E IDA / 61430 and improve infrastructure i Post Limited 6,831.17 Completed 2020-11-25 2020-11-30 2021-01-20 2021-04-17 2021-07-19 2022-02-23 supply of Sharman traps tions nvelope n priority Protected Areas 1. Strengthen management TZ-MNRT-205786-GO-DIR / S IDA / 61430 and improve infrastructure i Post Direct Selection Direct 18,568.33 Completed 2020-11-20 2021-02-19 2020-11-25 2020-09-04 2020-12-30 2021-04-17 2021-06-28 2021-07-02 upply of Animal Drugs n priority Protected Areas 4. Project management, insti TZ-MNRT-201735-GO-RFB / tutional strengthening, quali Supply of Collar Equipment's IDA / 61430 Prior Direct Selection Direct 0.00 Canceled 2020-11-20 2020-11-25 2020-12-30 2021-06-28 ty assurance and control, an for TAWIRI office d monitoring and evaluation 4. Project management, insti TZ-MNRT-208411-GO-DIR / P tutional strengthening, quali rocurement of One Unit of M IDA / 61430 Post Direct Selection Direct 0.00 Canceled 2020-12-07 2021-02-19 2020-12-12 2020-12-17 2021-01-16 2021-07-15 ty assurance and control, an otor vehicle for PCU d monitoring and evaluation 4. Project management, insti TZ-MNRT-226293-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E SUPPLY OF ICT EQUIPMENTS IDA / 61430 Post Limited 40,452.75 Completed 2021-04-04 2021-04-06 2021-05-30 2021-07-14 2021-11-26 2022-03-31 ty assurance and control, an tions nvelope FOR TAWIRI d monitoring and evaluation Page 1 4. Project management, insti TZ-MNRT-228083-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 2,900.39 Completed 2021-01-24 2021-01-19 2021-03-21 2021-05-18 2021-09-17 2021-07-02 Supply of Laptop for TTB ty assurance and control, an tions nvelope d monitoring and evaluation 4. Project management, insti TZ-MNRT-228080-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 6,884.60 Completed 2019-05-24 2020-05-21 2019-07-19 2021-02-17 2020-01-15 2021-04-21 Supply of ICT Equipments ty assurance and control, an tions nvelope d monitoring and evaluation 4. Project management, insti TZ-MNRT-228082-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 4,397.11 Completed 2019-05-24 2020-05-21 2019-07-19 2021-02-17 2020-01-15 2021-04-21 Supply of Furnitures ty assurance and control, an tions nvelope d monitoring and evaluation 4. Project management, insti TZ-MNRT-234689-GO-DIR / S tutional strengthening, quali UPPLY OF COLLAR EQUIPMEN IDA / 61430 Post Direct Selection Direct 153,627.28 Signed 2021-05-31 2021-05-06 2021-06-05 2021-05-27 2021-07-10 2021-10-09 2022-01-06 ty assurance and control, an T FOR TAWIRI d monitoring and evaluation TZ-MNRT-233355-GO-RFQ / 4. Project management, insti SUPPLY OF ICT EQUIPMENTS tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 9,124.14 Completed 2021-06-26 2021-08-27 2021-08-21 2021-12-01 2022-02-17 2022-03-31 FOR COMMUNICATION SPECI ty assurance and control, an tions nvelope ALIST d monitoring and evaluation 4. Project management, insti TZ-MNRT-239701-GO-DIR / S tutional strengthening, quali IDA / 61430 Post Direct Selection Direct 81,011.83 Completed 2021-09-06 2021-09-24 2021-09-11 2021-09-28 2021-10-16 2021-12-11 2022-04-14 2022-05-11 UPPLY OF MOTORVEHICLE ty assurance and control, an d monitoring and evaluation TZ-MNRT-266807-GO-RFQ / 4. Project management, insti Designing, Printing and Suppl tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 8,634,384.58 Completed 2021-12-13 2021-12-14 2022-02-07 2022-03-06 2022-08-06 2022-07-08 y of Promotional Materials for ty assurance and control, an tions nvelope REGROW Project -PCU d monitoring and evaluation TZ-MNRT-266810-GO-RFQ / 4. Project management, insti Supply of Video Conference T tutional strengthening, quali Request for Quota Single Stage - One E Under Imple IDA / 61430 Post Limited 0.00 2021-12-13 2022-06-24 2022-02-07 2022-08-06 ools for REGROW Project - PC ty assurance and control, an tions nvelope mentation U d monitoring and evaluation TZ-MNRT-266811-GO-RFQ / 4. Project management, insti Designing, Printing and Suppl tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 59,310.68 Signed 2021-12-11 2021-12-14 2022-02-05 2022-02-23 2022-08-04 y of Promotional Materials for ty assurance and control, an tions nvelope Tourism destination for Sout d monitoring and evaluation hern Circuit - TTB 4. Project management, insti TZ-MNRT-263005-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E Procurement of ICT Equipme IDA / 61430 Post Limited 11,106.37 Signed 2021-12-13 2021-12-13 2022-02-07 2022-07-07 2022-08-06 ty assurance and control, an tions nvelope nt for TTB d monitoring and evaluation 4. Project management, insti TZ-MNRT-266923-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E Supply of IC Equipment for P IDA / 61430 Post Limited 35,336.08 Completed 2021-12-13 2021-12-14 2022-02-07 2022-02-23 2022-08-06 2022-04-08 ty assurance and control, an tions nvelope CU and TAWIRI d monitoring and evaluation TZ-MNRT-281885-GO-DIR / P rocurement of Two (02) Units 1. Strengthen management of 4WD Standard Land Cruise IDA / 61430 and improve infrastructure i Post Direct Selection Direct 0.00 Signed 2022-03-01 2022-08-16 2022-03-06 2022-08-22 2022-04-10 2022-10-07 r Station Wagon and One (01 n priority Protected Areas ) Unit of Special Filming Vehi cle 4WD Land Cruiser Double Cabin TZ-MNRT-298741-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Supply of Camera Traps for T IDA / 61430 and improve infrastructure i Post Limited 0.00 Signed 2022-06-12 2022-06-22 2022-08-07 2023-02-03 tions nvelope AWIRI n priority Protected Areas 4. Project management, insti TZ-MNRT-298751-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E Supply of office equipment fo IDA / 61430 Post Limited 0.00 Completed 2022-06-12 2022-06-23 2022-08-07 2023-02-03 2023-03-04 ty assurance and control, an tions nvelope r PCU d monitoring and evaluation TZ-MNRT-278600-GO-RFB / 1. Strengthen management Single Stage - One E Procurement of One (01) Unit IDA / 61430 and improve infrastructure i Post Request for Bids Limited 0.00 Canceled 2022-02-18 2022-03-11 2022-02-23 2022-03-15 2022-04-06 2022-05-06 2022-06-10 2022-12-07 nvelope of Overland Truck n priority Protected Areas 4. Project management, insti TZ-MNRT-263004-GO-RFQ / tutional strengthening, quali Request for Quota Single Stage - One E Procurement of Office Furnitu IDA / 61430 Post Limited 0.00 Canceled 2021-12-13 2021-12-13 2022-02-07 2022-08-06 ty assurance and control, an tions nvelope re for TTB d monitoring and evaluation TZ-MNRT-315129-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E SUPPLY OF ICT EQUIPMENT F IDA / 61430 and improve infrastructure i Post Limited 0.00 Signed 2022-09-21 2022-11-08 2022-11-09 2022-12-09 tions nvelope OR PCU AND TTB n priority Protected Areas TZ- MNRT-311822-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Supply of field equipment an IDA / 61430 and improve infrastructure i Post Open - National 0.00 Signed 2022-09-03 2022-10-29 2023-04-27 tions nvelope d supplies n priority Protected Areas TZ- MNRT-309778-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E supply of office furniture for IDA / 61430 and improve infrastructure i Post Open - National 0.00 Signed 2022-09-03 2022-10-29 2023-04-27 tions nvelope TTB n priority Protected Areas TZ-MNRT-306355-GO-RFB / 1. Strengthen management Procurement of One (01) Unit IDA / 61430 and improve infrastructure i Post Direct Selection Direct - National 0.00 Canceled 2022-08-03 2022-08-08 2022-09-12 2023-03-11 of Overland Safari Truck for T n priority Protected Areas TB TZ-MNRT-311822-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E SUPPLY OF FIELD EQUIPMEN IDA / 61430 and improve infrastructure i Post Open - National 0.00 Canceled 2022-09-03 2022-10-29 2023-04-27 tions nvelope T AND SUPPLIES n priority Protected Areas TZ-MNRT-309778-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Supply of Office Furniture for IDA / 61430 and improve infrastructure i Post Open - National 0.00 Canceled 2022-09-03 2022-10-29 2023-04-27 tions nvelope TTB n priority Protected Areas TZ-MNRT-356525-GO-RFQ / 1. Strengthen management Request for Quota Single Stage - One E Under Imple Procurement of ICT equipme IDA / 61430 and improve infrastructure i Post Limited 0.00 2023-05-24 2023-05-24 2023-07-19 2024-01-15 tions nvelope mentation nt for PCU n priority Protected Areas NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 TZ-MNRT-315140-NC-RFQ / P 4. Project management, insti RITING AND SUPPLY OF PRO tutional strengthening, quali Request for Quota Single Stage - One E IDA / 61430 Post Limited 0.00 Signed 2022-09-16 2022-11-08 2022-10-21 2022-11-20 MOTIONAL MATRIALS FOR PC ty assurance and control, an tions nvelope U d monitoring and evaluation TZ-MNRT-324543-NC-RFQ / 1. Strengthen management DESIGNING AND PRINTING O Request for Quota Single Stage - One E IDA / 61430 and improve infrastructure i Post Limited 0.00 Signed 2022-11-07 2022-11-04 2023-01-02 2023-07-01 F PROMOTIONAL MATERIALS tions nvelope n priority Protected Areas FOR KARIBU KUSINI 2022 TZ-MNRT-326000-NC-RFQ / 1. Strengthen management Designing, Printing and Suppl Request for Quota Single Stage - One E IDA / 61430 and improve infrastructure i Post Limited 0.00 Signed 2022-11-27 2022-12-14 2023-01-22 2023-07-21 y of Promotional Materials for tions nvelope n priority Protected Areas Southern Tourism Circuit - TT B TZ-MNRT-362835-NC-RFQ / Designing, Printing and Suppl 1. Strengthen management y of Promotional Materials for Request for Quota Single Stage - One E Under Imple IDA / 61430 and improve infrastructure i Post Limited 0.00 2023-05-28 2023-06-05 2023-07-23 2024-01-19 Southern Circuit Cultural Tou tions nvelope mentation n priority Protected Areas rism Enterprises , Kilifair and Saba Saba Exhibitions for TT B. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MNRT-17017-CS-QCBS / P 2. Strengthen alternative liv rovision of consultancy servic elihoods for targeted comm Quality And Cost- Open - Internationa es for environmental and soc IDA / Q9740 Prior 396,851.50 Signed 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-22 2017-06-27 2016-11-03 2018-06-27 unities in proximity to the pr Based Selection l ial impact assessment includi iority Protected Areas ng ESMF, RPF and PF TZ-MNRT-17022-CS-CQS / C onsultancy services to condu 2. Strengthen alternative liv ct a curriculum development elihoods for targeted comm Consultant Qualifi Pending Impleme workshop and elaborate a far IDA / Q9740 Post Open - National 0.00 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-27 2017-12-24 unities in proximity to the pr cation Selection ntation mer field school program on iority Protected Areas on-farm water and crop man agement in the irrigation sch eme on the usangu plains TZ-MNRT-17027-CS-QCBS / P 3. Strengthen landscape ma rovision of consultancy servic nagement and infrastructure es to undertake a reconnaiss Quality And Cost- Open - Internationa IDA / Q9740 investments in and upstrea Prior 539,043.75 Under Review 2017-06-06 2017-06-27 2017-06-27 2017-06-27 2017-06-27 2017-07-04 2017-10-27 2017-08-08 2016-11-02 2018-08-08 ance study of structural mea Based Selection l m of the Ruaha National Par sure to augment dry season f k lows in Ruaha National Park, Southern Tanzania TZ-MNRT-17052-CS-QCBS / Consultancy on locally based 1. Strengthen management tourism product developmen Quality And Cost- IDA / Q9740 and improve infrastructure i Prior Open - National 460,881.13 Signed 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-07-22 2017-06-27 2017-07-25 2018-06-27 t and socio- economic assess Based Selection n priority Protected Areas ment of communities adjace nt to selected protected area s in southern Tanzania TZ-MNRT-17054-CS-QCBS / c 3. Strengthen landscape ma onsultancy service to undert nagement and infrastructure Quality And Cost- ake a reconnaissance survey IDA / Q9740 investments in and upstrea Prior Open - National 562,591.20 Signed 2017-06-06 2017-06-23 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-06-06 2017-07-17 2017-06-27 2017-07-21 2018-06-27 Based Selection of agricultural water manage m of the Ruaha National Par ment in usangu flats Souther k n Tanzania TZ-MNRT-40665-CS-QCBS / 4. Project management, insti Market research and product tutional strengthening, quali Quality And Cost- IDA / 61430 Prior Open - National 274,194.24 Signed 2018-01-30 2018-05-13 2018-02-20 2018-06-12 2018-04-05 2019-01-22 2018-05-03 2019-02-25 2018-06-02 2019-08-01 2018-07-07 2021-09-20 2018-08-11 2020-05-30 2019-08-11 market development strateg ty assurance and control, an Based Selection y d monitoring and evaluation TZ-MNRT-40894-CS-CQS / O 1. Strengthen management ption for PPP and private sect Consultant Qualifi IDA / 61430 and improve infrastructure i Post Open - National 0.00 Canceled 2018-03-05 2018-03-26 2018-05-09 2018-06-08 2018-07-13 2019-01-09 or investment opportunities i cation Selection n priority Protected Areas n the project area TZ-MNRT-57587-CS-QCBS / Consultancy services for desi 1. Strengthen management gning drawing and preparati Quality And Cost- IDA / 61430 and improve infrastructure i Post Open - National 0.00 Canceled 2018-04-13 2018-05-04 2018-06-17 2018-07-15 2018-08-14 2018-09-18 2018-10-23 2019-10-23 on of bill of quantity and tend Based Selection n priority Protected Areas er document for construction of southern circuit managem ent center TZ-MNRT-40895-CS-CQS / Th e Preparation of an Impleme 2. Strengthen alternative liv ntation Plan to Develop Viabl elihoods for targeted comm Consultant Qualifi IDA / 61430 Post Open - National 0.00 Canceled 2018-02-06 2018-02-27 2018-09-19 2018-04-12 2018-05-12 2018-06-16 2018-12-13 e Goods and Services Supply unities in proximity to the pr cation Selection Capacity in Selected Commu iority Protected Areas nities under the REGROW Pro ject TZ-MNRT-270518-CS-CQS / P 4. Project management, insti ROVISION OF CONSULTANCY tutional strengthening, quali Consultant Qualifi Under Implement SERVICE FOR FOR DEVELOP IDA / 61430 Post Open - National 0.00 2021-12-23 2022-01-07 2022-01-13 2022-01-21 2022-02-26 2022-03-23 2022-03-28 2022-08-19 2022-05-02 2022-10-29 ty assurance and control, an cation Selection ation MENT AND PRODUCTION OF d monitoring and evaluation CONTENT FOR SOCIAL MEDIA PLATFORMS TZ-MNRT-270522-CS-CQS / P ROVISION OF CONSULTANCY 4. Project management, insti SERVICE FOR FACILITATION tutional strengthening, quali Consultant Qualifi IDA / 61430 Post Open - National 0.00 Signed 2021-12-23 2022-01-07 2022-01-13 2022-01-21 2022-02-26 2022-03-23 2022-03-28 2022-08-19 2022-05-02 2022-10-29 OF FOUR (4) LOCAL CHANNE ty assurance and control, an cation Selection LS FOR 30 DAYS EACH TO DE d monitoring and evaluation VELOP DOMESTIC TOURISM P ROMOTIONAL VIDEOS TZ-MNRT-270524-CS-CQS / P 4. Project management, insti ROVISION OF CONSULTANCY tutional strengthening, quali Consultant Qualifi Under Implement SERVICE OF BROADCASTING IDA / 61430 Post Open - National 0.00 2021-12-23 2022-01-07 2022-01-13 2022-01-21 2022-02-26 2022-03-22 2022-03-28 2022-08-19 2022-05-02 2022-10-29 ty assurance and control, an cation Selection ation TANZANIA TOURISM DESTINA d monitoring and evaluation TION THROUGH TV SPOT WIT HIN USA AND CHINA TZ-MNRT-271999-CS-CQS / P 4. Project management, insti rovision of Consultancy Servi tutional strengthening, quali Consultant Qualifi IDA / 61430 Post Open - National 0.00 Signed 2022-01-14 2022-01-07 2022-02-04 2022-01-21 2022-03-20 2022-03-22 2022-04-19 2022-08-19 2022-05-24 2022-11-20 ces for Upgrading a Biodivers ty assurance and control, an cation Selection ity Database d monitoring and evaluation TZ-MNRT-270516-CS-CQS / P 4. Project management, insti ROVISON OF CONSULTANCY tutional strengthening, quali Quality And Cost- Open - Internationa IDA / 61430 Post 0.00 Canceled 2022-01-14 2022-01-17 2022-02-04 2022-01-26 2022-03-20 2022-04-17 2022-05-17 2022-06-21 2022-07-26 2023-07-26 SERVICE FOR DIGITAL BILLBO ty assurance and control, an Based Selection l ARDS ADVERTISEMENT IN EU d monitoring and evaluation ROPE AND TANZANIA Page 3 TZ-MNRT-286005-CS-QCBS / PROVISION OF CONSULTANC 1. Strengthen management Quality And Cost- Open - Internationa Under Implement Y SERVICES FOR DIGITAL BIL IDA / 61430 and improve infrastructure i Post 0.00 2022-03-25 2022-06-15 2022-04-15 2022-08-12 2022-05-29 2022-06-26 2022-07-26 2022-08-30 2022-10-04 2023-10-04 Based Selection l ation LBOARDS ADVERTISEMENT I n priority Protected Areas N EUROPE AND TANZANIA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MNRT-17056-CS-INDV / u ndertaking of an assessment 2. Strengthen alternative liv of current benefit sharing mo elihoods for targeted comm Individual Consult IDA / Q9740 Post Open 31,500.00 Signed 2017-06-06 2016-01-15 2017-06-06 2016-08-15 2017-06-06 2016-10-10 2017-06-27 2016-10-21 2017-12-24 dels associated with with nat unities in proximity to the pr ant Selection ural resources and tourism a iority Protected Areas nd lesson learned from best practises 4. Project management, insti TZ-MNRT-17058-CS-INDV / I tutional strengthening, quali Individual Consult IDA / Q9740 Post Open 28,331.15 Completed 2017-06-06 2017-06-06 2017-06-06 2016-10-20 2017-06-06 2016-12-05 2017-06-27 2016-12-16 2017-12-24 2018-02-01 nstitutional assessment ty assurance and control, an ant Selection d monitoring and evaluation TZ-MNRT-18592-CS-INDV / C 4. Project management, insti onsultancy Services for revie tutional strengthening, quali Individual Consult wing the existing documents IDA / Q9740 Post Open 99,957.00 Signed 2017-06-20 2017-07-20 2017-06-20 2015-11-17 2017-06-20 2016-02-15 2017-07-11 2016-03-15 2018-01-07 ty assurance and control, an ant Selection and preparation of Project Im d monitoring and evaluation plementation manual (PIM) fo r REGROW Project. 4. Project management, insti TZ-MNRT-40659-CS-INDV / T tutional strengthening, quali Individual Consult IDA / 61430 Post Open 0.00 Canceled 2018-01-28 2018-03-18 2018-04-08 2018-05-13 2018-11-09 raining need asesment ty assurance and control, an ant Selection d monitoring and evaluation 4. Project management, insti TZ-MNRT-40899-CS-INDV / D tutional strengthening, quali Individual Consult IDA / 61430 Post Open 0.00 Canceled 2018-02-28 2018-04-18 2018-05-09 2018-06-13 2018-12-10 evelopment of web page ty assurance and control, an ant Selection d monitoring and evaluation TZ-MNRT-57593-CS-INDV / C onsultancy service for prepar 4. Project management, insti ation of communication strat tutional strengthening, quali Individual Consult IDA / 61430 Post Open 0.00 Canceled 2018-04-23 2019-11-21 2018-06-11 2018-07-02 2018-08-06 2019-02-02 egy for Resilient natural Reso ty assurance and control, an ant Selection urces management for Touris d monitoring and evaluation m and Growth (REGROW) Pro ject TZ-MNRT-57596-CS-INDV / C onsultancy services for estab 4. Project management, insti lishment of baseline for Moni tutional strengthening, quali Individual Consult IDA / 61430 Post Open 159,500.00 Signed 2018-04-20 2020-02-04 2018-06-08 2021-04-14 2018-06-29 2021-10-26 2018-08-03 2021-11-23 2019-01-30 toring and Evaluation for Resi ty assurance and control, an ant Selection lient natural Resource Manag d monitoring and evaluation ement for Tourism and Growt h (REGROW) Project TZ-MNRT-57448-CS-INDV / p 4. Project management, insti rovision of Financial Manage tutional strengthening, quali Individual Consult IDA / 61430 Prior Open 0.00 Canceled 2018-04-15 2018-05-13 2018-06-03 2018-06-24 2018-07-29 2019-01-25 ment support services by Jun ty assurance and control, an ant Selection e 2018 d monitoring and evaluation 4. Project management, insti TZ-MNRT-57449-CS-INDV / P tutional strengthening, quali Individual Consult rovision of procurement supp IDA / 61430 Prior Open 0.00 Canceled 2018-04-10 2018-05-13 2018-05-29 2018-06-19 2018-07-24 2019-01-20 ty assurance and control, an ant Selection ort services by June 2018 d monitoring and evaluation TZ-MNRT-65394-CS-INDV / C 4. Project management, insti onsultancy Services for provi tutional strengthening, quali Individual Consult IDA / 61430 Post Open 0.00 Canceled 2018-06-07 2018-06-07 2018-07-26 2018-08-16 2018-09-20 2019-03-19 sion of Environmental and So ty assurance and control, an ant Selection cial Safeguards Management d monitoring and evaluation and supervision. TZ-MNRT-187352-CS-INDV / Facilitate the establishment 1. Strengthen management Individual Consult of an e- learning training plat IDA / 61430 and improve infrastructure i Post Open 0.00 Canceled 2020-09-01 2021-03-10 2020-10-20 2020-11-10 2020-12-15 2021-06-13 ant Selection form on southern tourism cir n priority Protected Areas cuit for international travel a gents for TTB TZ-MNRT-196123-CS-INDV / 1. Strengthen management Consultancy services for pre Individual Consult IDA / 61430 and improve infrastructure i Post Limited 0.00 Canceled 2020-10-01 2021-03-10 2020-10-06 2020-10-27 2020-12-01 2021-05-30 paration of design and printi ant Selection n priority Protected Areas ng Southern Circuit Tourism Map for TTB TZ-MNRT-234690-CS-CQS / 1. Strengthen management Consultancy work for a Statis Individual Consult IDA / 61430 and improve infrastructure i Post Limited 0.00 Canceled 2021-06-21 2021-08-22 2021-06-26 2021-09-20 2021-07-17 2021-08-21 2022-02-17 tic Training for Wildlife Resea ant Selection n priority Protected Areas rchers at the TAWIRI TZ-MNRT-254343-CS-INDV / 4. Project management, insti Provision of Consultancy Serv tutional strengthening, quali Individual Consult IDA / 61430 Post Limited 27,000.00 Completed 2021-09-27 2021-09-21 2021-10-02 2021-09-30 2021-10-23 2021-11-13 2021-11-27 2021-12-02 2022-05-26 2022-06-01 ices of Procurement Speciali ty assurance and control, an ant Selection st for REGROW Project d monitoring and evaluation TZ-MNRT-234690 - CS-CQS - 4. Project management, insti 1 / Consultancy work for a St tutional strengthening, quali Individual Consult IDA / 61430 Post Limited 15,000.00 Completed 2021-06-21 2021-08-22 2021-06-26 2021-09-20 2021-07-17 2021-12-08 2021-08-21 2021-12-22 2022-02-17 2022-01-18 atistic Training for Wildlife Re ty assurance and control, an ant Selection searchers at the TAWIRI d monitoring and evaluation TZ-MNRT-306399-CS-CDS / P rovision of Consultancy Servi ce for Environmental and Soc 1. Strengthen management ial Impact Assessment Study IDA / 61430 and improve infrastructure i Post Direct Selection Direct - National 0.00 Signed 2022-08-03 2022-08-12 2022-08-13 2022-09-02 2022-10-17 2023-04-15 for the Construction of South n priority Protected Areas ern Circuit Tourism Marketin g Destination Centre and Wil dlife Research Centre at Kihe sa Kilolo in Iringa Municipal. TZ-MNRT-306381-CS-CDS / Consultancy service for prep aration of detailed engineeri 1. Strengthen management ng design, tender document Direct - Internation IDA / 61430 and improve infrastructure i Post Direct Selection 0.00 Signed 2022-09-12 2022-09-08 2022-09-22 2022-09-08 2022-11-26 2024-04-30 and supervision of constructi al n priority Protected Areas on of the Southern Circuit To urism Marketing Destination and Wildlife Research Centre at Kihesa Kilolo in Iringa for T TB and TAWIRI Page 4 TZ-MNRT-325456-CS-INDV / 1. Strengthen management Provision of Consultancy Serv Individual Consult Pending Impleme IDA / 61430 and improve infrastructure i Post Open - National 0.00 2022-11-17 2023-01-05 2023-01-26 2023-03-02 2023-08-29 ices for development of Sout ant Selection ntation n priority Protected Areas hern Tourism Circuit Map TZ-MNRT-325457-CS-INDV / Consultancy Services to facili 1. Strengthen management tate establishment (develop Individual Consult Under Implement IDA / 61430 and improve infrastructure i Post Open - National 0.00 2022-11-17 2022-11-22 2023-01-05 2023-01-26 2023-03-02 2023-08-29 ment) of an e - learning traini ant Selection ation n priority Protected Areas ng platform on Tanzania Sout hern Tourism Circuit for Inter national Travel Agents and M edia Page 5 PROCUREMENT PLAN I. General 1. Project information: · Project Name: Innovative Private Sector Development · Country: West Bank and Gaza · Project Code: P164412 Date of Bank Approval: 19-Apr-18 II. Goods, information technology and non-consulting services 1. Procurement Methods and Thresholds Method of Category Procurement Threshold Prior Review Threshold (US$ Equivalent) (US$ Equivalent) Goods, information RFB/RFP- technology and non- Open All contracts above US$ consulting services International No threshold 2 million RFB-Open National <500,000 None RFQ <100,000 None Direct All contracts above US$ Selection No threshold 2 million 2. Pre-qualification: NA 3. Reference to Project Operational and Procurement Manual: NA 4. Any Other Special Procurement Arrangements: III. Selection of Consultants 1. Selection Methods and Thresholds Selection Category Method Threshold Prior Review Threshold (US$ Equivalent) (US$ Equivalent) Consulting Services All contracts above US$ Firms QCBS/QBS No threshold 1 million FBS/LCS/CQS <300,000 None Direct All contracts above US$ Selection No threshold 1 million All contracts above Individuals IC No threshold $300,000 Direct All contracts above Selection No threshold $300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants. 3. All TORs will be subject to the Bank's prior review PROCUREMENT West Bank and Gaza : Innovative Private Sector Development PLAN General Information Country: West Bank and Gaza 2019-12-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164412 GPN Date: Project Name: Innovative Private Sector Development Loan / Credit No: TF / A7439, TF / B5149 Development Alternative Inc., Europe Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-168812-GO-CP / Tact ical activities-Physical infrast Building an Outsourcing Hub Commercial Practi Single Stage - One E TF / A7439 Post Open - National 45,120.00 Completed 2020-05-28 2020-07-09 2020-06-04 2020-07-09 2020-06-28 2020-08-16 2020-07-05 2020-09-01 2020-07-12 2020-10-06 2020-10-15 2021-04-05 ructure IT security and techn in Gaza ces nvelope ology Upgrade for GGateway. GZ-DAI-199376-GO-CP / Proc urement of software, licence Entrepreneurship Ecosystem Commercial Practi Single Stage - One E TF / A7439 Post Limited 6,000.00 Completed 2020-10-20 2020-10-25 2020-10-25 2020-10-25 2020-11-10 2020-11-08 2020-11-15 2020-11-23 2020-11-19 2020-12-01 2020-12-13 2020-12-17 s and hardware for Covid-19 Development ces nvelope Rapid Response beneficiaries . GZ-DAI-252713-GO-DIR / Up dating the accounting softwa re at Ggateway, and transferi Building an Outsourcing Hub TF / A7439 Post Direct Selection Direct 2,320.00 Completed 2021-09-12 2021-09-15 2021-09-14 2021-09-15 2021-09-19 2021-09-15 2021-09-30 2021-09-16 ng from single user to networ in Gaza k, and purchase another lice nse for the accountant of GG ateway. GZ-DAI-252791-GO-RFQ / Pr Building an Outsourcing Hub Request for Quota Single Stage - One E TF / A7439 Post Limited 65,739.00 Completed 2021-10-08 2022-01-04 2021-11-23 2022-01-06 2022-04-24 2022-03-16 ocurement of 25 laptops for in Gaza tions nvelope GGateway. GZ-DAI-254178-GO-RFQ / Pr ocurement of furniture and e quipment for the beneit of fir Entrepreneurship Ecosystem Request for Quota Single Stage - One E TF / B5149 Post Limited 100,355.98 Completed 2021-10-10 2021-11-14 2021-11-15 2022-03-14 2022-05-02 2022-04-26 ms that will benefit from Gaz Development tions nvelope a Tech and Innovative recove ry. The amount is an estimat ed one. GZ-DAI-276046-GO-RFQ / Pr Building an Outsourcing Hub Request for Quota Single Stage - One E ocurement of 7 laptops to GG TF / A7439 Post Limited 13,601.00 Completed 2022-02-02 2022-05-02 2022-02-11 2022-04-18 2022-02-20 2022-05-16 in Gaza tions nvelope ateway-VLSI training. GZ-DAI-277957-GO-RFQ / Pr ocurement of Laptops and IT Entrepreneurship Ecosystem Request for Quota Single Stage - One E TF / B5149 Post Limited 6,423.00 Completed 2022-02-13 2022-02-10 2022-03-01 2022-03-28 2022-04-14 2022-03-29 Equipment for Pre Investmen Development tions nvelope t Grants Beneficiary Compani es. GZ-DAI-297770-GO-RFQ / Pr ocurement of a laptop and C Entrepreneurship Ecosystem Request for Quota Single Stage - One E TF / A7439 Post Limited 10,696.00 Completed 2022-06-07 2022-06-07 2022-06-30 2022-06-28 2022-07-31 2022-07-15 amera for Lam'et Afkar Comp Development tions nvelope any (Under Pre Investment G rants Component). GZ-DAI-212340-GO-CP / Proc Building an Outsourcing Hub Commercial Practi Single Stage - Two E urement of Laptops for the b TF / A7439 Post Limited 0.00 Canceled 2021-01-14 2021-01-18 2021-01-25 2021-01-28 2021-01-29 2021-02-16 in Gaza ces nvelope enefit of Ggateway- UNQORK Training GZ-DAI-306295-GO-RFQ / Pr Building an Outsourcing Hub Request for Quota Single Stage - One E ocurement of UPS and Batter TF / A7439 Post Limited 4,170.00 Completed 2022-07-28 2022-07-31 2022-08-08 2022-08-04 2022-08-10 2022-09-16 in Gaza tions nvelope ies for GGateway. GZ-DAI-308719-GO-DIR / A contract will be signed with t he supplier of batteries for th e benefit of GGateway. Thes Building an Outsourcing Hub TF / A7439 Post Direct Selection Direct - National 4,800.00 Completed 2022-08-10 2022-08-07 2022-08-11 2022-08-07 2022-08-17 2022-08-08 2022-08-21 2022-08-19 e batteries are available in st in Gaza ock and are required by GGat eway urgently. IPSD did a pro curement for this item, and a lready has the prices. GZ-DAI-317949-GO-RFQ / Pr ocurement of IT Equipment f Entrepreneurship Ecosystem Request for Quota Single Stage - One E TF / B5149 Post Limited 0.00 Completed 2022-10-05 2022-10-05 2022-10-30 2022-11-17 2023-01-11 or the benefit of Pre-Investm Development tions nvelope ent Grans recipients. GZ-DAI-324157-GO-RFQ / Pr ocurement of Laptops and IT Entrepreneurship Ecosystem Request for Quota Single Stage - One E TF / B5149 Post Limited 0.00 Completed 2022-11-03 2022-10-31 2022-11-16 2023-05-15 2023-01-06 Equipment for Pre Investmen Development tions nvelope t and Co Investment Grants r ecipients. GZ-DAI-324160-GO-RFQ / Pr Building an Outsourcing Hub Request for Quota Single Stage - One E ocurement of laptops and IT TF / A7439 Post Limited 0.00 Completed 2022-11-03 2022-11-17 2022-12-16 2023-06-26 2022-12-30 in Gaza tions nvelope equipment for the benefit of GGateway. GZ-DAI-355716-GO-RFQ / Pr Building an Outsourcing Hub Request for Quota Single Stage - One E ocurement of a laptop for the TF / A7439 Post Limited 0.00 Canceled 2023-04-16 2023-05-07 2023-06-07 in Gaza tions nvelope benefit of GGateway Managi ng Director. GZ-DAI-361015-GO-RFQ / De Entrepreneurship Ecosystem Request for Quota Single Stage - One E Pending Impl liver ICT goods for GGateway TF / A7439 Post Limited 0.00 2023-06-15 2023-08-10 2024-02-06 Development tions nvelope ementation 's newly rented office space. GZ-DAI-361701-GO-RFQ / Pr ocurement of Laptops for Pre Entrepreneurship Ecosystem Request for Quota Single Stage - One E TF / B5149 Post Limited 0.00 Completed 2023-05-23 2023-05-21 2023-06-18 2023-07-02 Investment Grants beneficiar Development tions nvelope ies in the West Bank and Gaz a. Page 1 GZ-DAI-367143-GO-RFQ / Pr ocurement of MacbookPro-16 Entrepreneurship Ecosystem Request for Quota Single Stage - One E Pending Impl TF / B5149 Post Limited 0.00 2023-06-18 2023-06-26 2023-07-17 Inch for the benefit of a Pre-I Development tions nvelope ementation nvestment Grant Beneficiary. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-168505-NC-CP / IPSD Website design, branding,de Entrepreneurship Ecosystem Commercial Practi Single Stage - One E TF / A7439 Post Limited 4,779.20 Completed 2020-04-14 2020-04-14 2020-04-16 2020-04-14 2020-04-23 2020-04-21 2020-04-26 2020-04-28 2020-04-27 2020-05-04 2020-05-18 2020-07-20 velopment,registration and h Development ces nvelope osting for 5 years,and suppor t for 1 year GZ-DAI-225376-NC-CP / Red Entrepreneurship Ecosystem Commercial Practi TF / A7439 Post Direct 2,041.60 Completed 2021-03-21 2021-03-21 2021-03-22 2021-03-18 2021-03-25 2021-03-28 2021-05-02 esign of IPSD website. Development ces GZ-DAI-168728-NC-CP / con Entrepreneurship Ecosystem Commercial Practi Single Stage - One E duct a home based business TF / A7439 Post Open - National 0.00 Canceled 2020-06-01 2020-06-04 2020-06-18 2020-06-25 2020-06-30 2020-12-30 Development ces nvelope awareness campaign. GZ-DAI-338263-NC-DIR / Pro curement of the following ins urances: Professional Indemn Building an Outsourcing Hub TF / A7439 Post Direct Selection Direct - National 0.00 Canceled 2023-02-07 2023-02-07 2023-02-13 2024-02-11 ity Insurance and General Lia in Gaza bility Insurance. Ggateway wi ll sign the contract with the i nsurance company. GZ-DAI-345738-NC-RFQ / Pr ocurement of Laptops and m Entrepreneurship Ecosystem Request for Quota Single Stage - One E TF / B5149 Post Limited 0.00 Completed 2023-03-06 2023-03-02 2023-03-27 2023-06-01 2023-03-30 onitors for the benefit of Co-I Development tions nvelope nvestment Grants beneficiar y. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-149973-CS-CCP / Re Entrepreneurship Ecosystem Commercial Practi sident Technical Advisor with TF / A7439 Post Direct 4,100.00 Terminated 2019-12-12 2020-01-01 2019-12-12 2019-11-01 2019-12-12 2019-10-14 2020-11-30 Development ces in the Ministry of Nationmal E conomy. GZ-DAI-149979-CS-CCP / Su bcomponent Manager 1.3 an d 1.4, implementing a new a Entrepreneurship Ecosystem Commercial Practi TF / A7439 Post Direct 75,107.94 Signed 2019-12-12 2019-12-07 2019-12-12 2019-10-22 2019-12-12 2019-10-23 2020-11-23 utomated company registrati Development ces on system and developing ho me-based business framewor k. GZ-DAI-150492-CS-CCP / Ma nager Subcomponent 1.2- De Entrepreneurship Ecosystem Commercial Practi TF / A7439 Post Direct 80,000.00 Completed 2019-12-15 2020-01-01 2019-12-26 2019-10-01 2020-01-05 2019-11-11 2021-01-04 2021-01-07 veloping a dynamic start-up f Development ces inance ecosystem GZ-DAI-150513-CS-CCP / Ma nager Subcomponent 1.1- Im Entrepreneurship Ecosystem Commercial Practi proving Market Linkages to A TF / A7439 Post Direct 60,449.38 Terminated 2019-12-16 2019-12-01 2019-12-16 2019-11-14 2019-12-16 2019-11-15 2020-11-30 Development ces rab communities in regional entrepreneurship ecosystem s. GZ-DAI-150514-CS-CCP / Pro Commercial Practi TF / A7439 Project Management Post Direct 83,967.94 Signed 2019-12-16 2019-10-20 2019-12-16 2019-10-23 2019-12-16 2019-10-24 2020-11-02 curement Specialist ces GZ-DAI-150524-CS-CCP / Pro Entrepreneurship Ecosystem Commercial Practi TF / A7439 Post Direct 96,000.00 Completed 2019-12-16 2019-11-01 2019-12-16 2019-10-01 2019-12-16 2019-11-01 2020-11-16 2020-11-19 ject Director Development ces GZ-DAI-150532-CS-CCP / Co Building an Outsourcing Hub Commercial Practi TF / A7439 Post Direct 56,000.00 Completed 2019-12-16 2019-10-01 2019-12-16 2019-12-01 2019-12-16 2019-11-12 2020-11-30 2021-02-01 ordinator for G-Gateway in Gaza ces GZ-DAI-150533-CS-CCP / Fin Commercial Practi TF / A7439 Project Management Post Direct 68,427.00 Signed 2019-12-16 2020-01-01 2019-12-17 2019-10-10 2019-12-17 2019-11-04 2020-11-02 ancial Management Specialis ces t GZ-DAI-158953-CS-CQS / Hir ing of Resident Technical Adv Commercial Practi TF / A7439 Project Management Post Limited 113,678.76 Signed 2020-02-11 2019-12-01 2020-02-13 2020-01-26 2020-02-16 2020-01-27 2020-02-17 2020-02-02 2020-02-20 2020-02-19 2020-03-01 2020-02-24 2021-02-28 isor to the Palestinian Ministr ces y of National Economy. GZ-DAI-168624-CS-CCP / Co nduct Assessment and Desig Entrepreneurship Ecosystem Commercial Practi TF / A7439 Post Direct 54,667.00 Completed 2020-04-17 2020-03-16 2020-04-30 2020-06-09 2020-05-03 2020-06-13 2020-07-16 2021-02-18 n of Market Access Programs Development ces for Regional and Internationa l Markets. GZ-DAI-168839-CS-INDV / C Entrepreneurship Ecosystem Commercial Practi onduct Local Market Assessm TF / A7439 Post Limited 0.00 Canceled 2020-05-07 2020-05-11 2020-05-21 2020-05-25 2020-05-28 2020-06-02 2020-07-09 Development ces ent (Supply Side)-Activity 1. GZ-DAI-168879-CS-CCP / Ext ernal consultating firm to im Entrepreneurship Ecosystem Commercial Practi TF / A7439 Post Direct 82,845.00 Signed 2020-04-19 2020-04-15 2020-04-29 2020-06-09 2020-05-07 2020-06-15 2020-08-10 2021-02-04 plement qualitative and quan Development ces titative ecosystem assessme nt (Scope2). GZ-DAI-168689-CS-CCP / Co nsultancy Services for Legal , Institutional, Business Proces Entrepreneurship Ecosystem Commercial Practi TF / A7439 Post Open - National 325,305.56 Terminated 2020-05-01 2020-04-18 2020-05-04 2020-07-22 2020-05-31 2020-10-12 2020-06-30 2020-11-15 2020-07-07 2020-12-09 2020-07-09 2021-01-07 2020-07-13 2021-01-08 2020-11-30 s and ICT Assessment for Bus Development ces iness Registry System at the Ministry of National Economy /Palestine. GZ-DAI-177900-CS-CCP / Co nduct Covid-19 Business Puls Entrepreneurship Ecosystem Commercial Practi e Survey . The Survey will be TF / A7439 Post Direct 44,526.00 Completed 2020-06-11 2020-06-14 2020-06-25 2020-06-22 2020-06-29 2020-06-24 2020-10-02 2020-11-13 Development ces sole sourced to the Palestinia n Central Bureau of Statistics (PCBS). Page 2 GZ-DAI-181591-CS-CCP / Ma rket Assessment Study-Dema Building an Outsourcing Hub Commercial Practi TF / A7439 Post Limited 31,100.00 Terminated 2020-08-27 2020-08-23 2020-09-07 2020-11-05 2020-10-09 2020-10-14 2020-10-23 2020-11-09 2020-10-30 2020-12-01 2020-11-12 2020-12-21 2021-03-18 nd and Supply side for GGate in Gaza ces way in the MENA region. GZ-DAI-187571-CS-CCP / Im Building an Outsourcing Hub Commercial Practi Open - Internationa proving GGateway Digital Pre TF / A7439 Post 53,888.89 Completed 2020-08-16 2020-08-13 2020-08-20 2020-08-20 2020-09-27 2020-10-22 2020-10-20 2020-11-30 2020-10-27 2020-12-21 2020-11-04 2021-01-11 2020-11-11 2021-01-25 2021-04-30 2023-01-09 in Gaza ces l sence and Brand. GZ-DAI-168752-CS-CCP / GG Building an Outsourcing Hub Commercial Practi ateway Registration in Ramal TF / A7439 Post Limited 63,005.50 Signed 2020-09-15 2020-09-15 2020-09-24 2020-09-29 2020-10-25 2020-10-29 2020-11-12 2020-11-24 2020-11-25 2020-11-30 2020-12-04 2020-12-07 2021-12-04 2021-02-17 in Gaza ces lah, and provide time-based l egal services. GZ-DAI-192300-CS-CCP / Co nducting Business and Finan Entrepreneurship Ecosystem Commercial Practi TF / A7439 Post Limited 46,400.00 Completed 2020-09-10 2020-09-16 2020-09-17 2020-10-05 2020-10-04 2020-11-11 2020-10-11 2020-12-06 2020-10-15 2020-12-09 2020-10-20 2020-12-16 2021-01-26 2021-06-25 cial Training for Startups, Ear Development ces ly-stage Enterprises and SME s. GZ-DAI-193082-CS-CCP / Dig Entrepreneurship Ecosystem Commercial Practi ital Marketing Technical Assis TF / A7439 Post Limited 840.00 Terminated 2020-09-10 2020-09-16 2020-09-17 2020-09-29 2020-10-01 2020-10-26 2020-10-05 2020-11-03 2020-10-11 2020-10-29 2020-10-16 2020-11-10 2020-12-22 Development ces tance to IPSD. GZ-DAI-205831-CS-CCP / Au Commercial Practi dit of IPSD , first year. Novem TF / A7439 Project Management Post 0.00 Canceled 2020-11-25 2020-11-27 2020-12-22 2021-01-07 2021-01-15 2021-02-04 2021-02-12 2021-04-23 ces ber 2019-December 2020. GZ-DAI-211369-CS-CCP / Co Entrepreneurship Ecosystem Commercial Practi nduct Home Based Buinesses TF / A7439 Post Limited 0.00 Canceled 2021-01-06 2021-01-17 2021-01-20 2021-02-24 2021-03-17 2021-04-02 2021-04-13 2021-10-27 Development ces Assessment. GZ-DAI-211249-CS-CCP / Inv Entrepreneurship Ecosystem Commercial Practi estment Readiness Advisory TF / A7439 Post Limited 0.00 Canceled 2020-12-30 2020-12-24 2021-01-14 2021-02-15 2021-03-04 2021-03-12 2021-03-29 2023-03-29 Development ces Services Program- Years1 an d2 GZ-DAI-211802-CS-CCP / Re gister of a group of firms loca Entrepreneurship Ecosystem Commercial Practi TF / A7439 Post Limited 28,107.60 Signed 2020-12-31 2020-12-31 2021-01-14 2021-01-06 2021-02-04 2021-01-25 2021-02-11 2021-02-02 2021-02-14 2021-02-10 2021-02-18 2021-02-25 2021-07-18 ted in Ramallah and Gaza at Development ces the Ministry of National Econ omy in Ramallah. GZ-DAI-213888-CS-CCP / Inv Entrepreneurship Ecosystem Commercial Practi estment Readiness Advisory TF / A7439 Post Limited 378,098.00 Completed 2021-01-14 2021-01-17 2021-01-18 2021-01-19 2021-02-18 2021-03-04 2021-03-14 2021-03-16 2021-03-21 2021-04-05 2021-03-28 2021-04-18 2022-03-27 2022-09-08 Development ces Services Program -Year 1. GZ-DAI-216529-CS-CCP / Co Entrepreneurship Ecosystem Commercial Practi Open - Internationa nduct Holistic Assesment of TF / A7439 Post 148,650.00 Completed 2021-02-01 2021-02-01 2021-02-10 2021-02-07 2021-03-19 2021-03-25 2021-04-16 2021-04-27 2021-04-28 2021-05-24 2021-05-02 2021-05-25 2021-05-09 2021-06-17 2021-11-29 Development ces l Home Based Businesses in P alestine. GZ-DAI-223680-CS-CCP / Re view and reformulate GGate way’s existing internal syste ms; Specifically: the Financial Building an Outsourcing Hub Commercial Practi TF / A7439 Post Limited 0.00 Canceled 2021-03-10 2021-03-10 2021-03-21 2021-03-28 2021-04-22 2021-05-06 2021-05-19 2021-05-26 2022-01-09 and Procurement systems, in in Gaza ces cluding GGateway manuals a nd software, to meet current and future GGateway expans ion requirements. GZ-DAI-225389-CS-CCP / Vid Entrepreneurship Ecosystem Commercial Practi TF / A7439 Post Limited 3,596.00 Completed 2021-03-22 2021-03-28 2021-03-24 2021-03-30 2021-04-11 2021-05-19 2021-04-18 2021-06-06 2021-04-21 2021-06-06 2021-04-24 2021-11-16 2022-05-29 2022-10-24 eo production service for IPS Development ces D. GZ-DAI-227566-CS-CCP / Co nduct Covid-19 Business Puls Entrepreneurship Ecosystem Commercial Practi TF / A7439 Post Direct 47,850.00 Completed 2021-04-05 2021-04-05 2021-04-15 2021-05-10 2021-04-18 2021-05-18 2021-09-26 2022-02-14 e second survey. The survey Development ces will be carried out by PCBS. GZ-DAI-228049-CS-CCP / Co nsulting Services for the impl Entrepreneurship Ecosystem Commercial Practi ementation of "Target Marke TF / A7439 Post Direct 201,434.00 Terminated 2021-04-11 2021-04-15 2021-04-25 2021-04-20 2021-05-16 2021-04-24 2022-05-16 Development ces t Access Programs"(Internati onalization Accelerator Progr am). GZ-DAI-242559-CS-CQS / De velop GGateway's Financial a Building an Outsourcing Hub Consultant Qualifi nd Procurement Managemen TF / A7439 Post Limited 96,512.00 Completed 2021-07-08 2021-07-14 2021-07-11 2021-07-28 2021-08-22 2021-11-14 2021-09-15 2021-11-22 2022-04-15 2022-06-06 in Gaza cation Selection t Systems (LumpSum and Ti me based contracts) GZ-DAI-246753-CS-CQS / Or ganizational and Human Res Building an Outsourcing Hub Consultant Qualifi TF / A7439 Post Limited 11,470.00 Terminated 2021-08-08 2021-08-18 2021-08-12 2021-08-22 2021-09-30 2022-01-11 2021-10-18 2022-02-09 2022-04-30 ources (HR)Management Con in Gaza cation Selection sultancies fir GGateway. GZ-DAI-264589-CS-CQS / Pro vide technical assistance nee ded to design the and imple ment a new governance stru Building an Outsourcing Hub Consultant Qualifi Under Implement TF / A7439 Post Limited 0.00 2021-11-30 2021-11-25 2021-12-07 2022-01-06 2022-02-01 2022-08-31 cture for the GGateway’ boar in Gaza cation Selection ation d including its mandate, stru cture, bylaws, qualification a nd selection of board membe rs and term of service . GZ-DAI-279562-CS-CQS / IPS Consultant Qualifi D audit ( Two year contract TF / B5149 Project Management Post Limited 8,120.00 Completed 2022-02-20 2022-02-23 2022-02-22 2022-03-03 2022-03-15 2022-04-26 2022-03-24 2022-04-30 2023-06-20 cation Selection 2021 and 2022). GZ-DAI-287435-CS-CQS / GG Building an Outsourcing Hub Consultant Qualifi ateway Social Enterprise Man TF / A7439 Post Limited 0.00 Signed 2022-04-07 2022-07-21 2022-04-21 2022-07-31 2022-05-21 2022-10-13 2022-06-05 2022-12-29 in Gaza cation Selection agement Consultancy. GZ-DAI-287448-CS-CQS / Pro Entrepreneurship Ecosystem Quality And Cost- gram for Angel Investment d TF / B5149 Post Open - National 0.00 Signed 2022-04-19 2022-04-20 2022-04-28 2022-06-09 2022-06-21 2022-07-07 2022-08-17 2022-08-02 2022-09-18 2022-08-28 2022-09-18 2022-09-19 2024-03-31 Development Based Selection evelopment. GZ-DAI-297765-CS-QCBS / C apacity Building of the Progr Quality And Cost- TF / A7439 Project Management Post Open - National 0.00 Signed 2022-06-05 2022-06-07 2022-06-12 2022-07-21 2022-08-02 2022-08-21 2022-09-08 2022-09-10 2022-11-25 2022-09-24 2022-09-26 2022-10-17 2023-06-17 ams and projects Unit at the Based Selection Ministry of National Economy . GZ-DAI-168731-CS-CCP / De sign the technical and functio Entrepreneurship Ecosystem Commercial Practi Open - Internationa TF / A7439 Post 0.00 Canceled 2020-08-20 2020-08-27 2020-09-16 2020-10-01 2020-10-06 2020-10-08 2020-10-11 2021-01-05 nal specifications of beneficia Development ces l ries' data base /portal. Page 3 GZ-DAI-168817-CS-CCP / In- Building an Outsourcing Hub Commercial Practi Depth operational and financ TF / A7439 Post Limited 0.00 Canceled 2020-05-03 2020-05-17 2020-05-31 2020-06-07 2020-06-11 2020-06-18 2020-09-14 in Gaza ces ial assessment of G-Gateway . GZ-DAI-168736-CS-CCP / Tra ining and capacity building to Entrepreneurship Ecosystem Commercial Practi conduct workshops, and dev TF / A7439 Post Limited 0.00 Canceled 2020-05-28 2020-06-04 2020-06-26 2020-07-02 2020-07-08 2020-07-15 2021-02-07 Development ces elop curriculum for angel gro ups/syndicates/networks. GZ-DAI-168748-CS-CCP / Tec Building an Outsourcing Hub Commercial Practi Open - Internationa hnical capacity building on n TF / A7439 Post 0.00 Canceled 2020-08-02 2020-08-06 2020-08-20 2020-09-03 2020-09-10 2020-09-14 2020-09-22 2021-01-04 in Gaza ces l ew market technology. GZ-DAI-306990-CS-CQS / Vid Entrepreneurship Ecosystem Consultant Qualifi eo Production Services for th TF / B5149 Post Limited 5,000.00 Completed 2022-08-04 2022-08-07 2022-08-11 2022-08-21 2022-08-18 2022-09-15 2022-09-11 2022-09-27 2022-10-31 2022-11-09 Development cation Selection e benefit of IRIS Solutions Co mpany. GZ-DAI-306993-CS-CDS / Hu man Resources (HR) manage Building an Outsourcing Hub Consultant Qualifi ment Consultancies for GGat TF / A7439 Post Limited 0.00 Signed 2022-08-14 2022-08-23 2022-08-28 2022-09-01 2022-09-15 2022-10-20 2022-10-20 2023-05-31 in Gaza cation Selection eway. IPSD will send the ToR to two shortlisted companies, requesting their profiles. GZ-DAI-317948-CS-CQS / Co Entrepreneurship Ecosystem Consultant Qualifi mmunication Campaign for t TF / B5149 Post Limited 0.00 Signed 2022-09-29 2022-10-04 2022-10-03 2022-10-24 2022-11-01 2022-12-14 2022-11-15 2023-05-14 Development cation Selection he companies law. GZ-DAI-335892-CS-CQS / Vid eo Production Services that Entrepreneurship Ecosystem Consultant Qualifi TF / B5149 Post Limited 0.00 Signed 2023-01-16 2023-01-25 2023-01-19 2023-02-01 2023-02-09 2023-03-12 2023-02-15 2023-04-02 will be used to highlight the i Development cation Selection mpact of IPSD on a number o f beneficiaries. GZ-DAI-355715-CS-CQS / Mo Entrepreneurship Ecosystem Consultant Qualifi tion Graphic Services for the TF / B5149 Post Limited 0.00 Canceled 2023-04-11 2023-04-11 2023-04-16 2023-04-18 2023-04-23 2023-10-31 Development cation Selection benefit of Qiam Company, un der PI Grants. GZ-DAI-360156-CS-CQS / Hir e the services of consultancy Entrepreneurship Ecosystem Consultant Qualifi Under Implement firm to deliver Technical ICT t TF / A7439 Post Open - National 0.00 2023-05-11 2023-05-15 2023-06-01 2023-08-01 2023-09-10 2023-09-28 2024-03-10 Development cation Selection ation raining to ICT specialists at t he Ministry of National Econo my. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GZ-DAI-168701-CS-CCP / Ass essment of Home Based Busi Entrepreneurship Ecosystem Individual Consult TF / A7439 Post Limited 0.00 Canceled 2020-05-10 2020-05-17 2020-05-31 2020-06-07 2020-12-10 nesses in West Bank (institut Development ant Selection ional and Legal Consultanciy) . GZ-DAI-168732-CS-CCP / Ext ernal consultant to implemen Entrepreneurship Ecosystem Individual Consult t local qualitative eco system TF / A7439 Post Limited 30,000.00 Completed 2020-04-19 2020-04-16 2020-04-26 2020-06-15 2020-04-30 2020-07-22 2020-05-07 2020-07-30 2020-08-01 2021-01-19 Development ant Selection assessment , program design and mentoring .Scope 1 GZ-DAI-168733-CS-CCP / Ext ernal consultant to implemen Entrepreneurship Ecosystem Individual Consult t local qualitative ecosysyem TF / A7439 Post Limited 20,000.00 Signed 2020-04-26 2020-06-14 2020-05-03 2020-04-28 2020-05-10 2020-08-04 2020-05-14 2020-08-07 2020-08-09 2021-01-11 Development ant Selection assessment , program design and mentoring, scope 3. GZ-DAI-168735-CS-CCP / Ext ernal Junior local consultant t o initially screen grant applic Individual Consult TF / A7439 Project Management Post Limited 15,400.00 Completed 2020-04-21 2020-04-20 2020-04-26 2020-05-05 2020-04-30 2020-06-01 2020-05-11 2020-06-02 2020-12-11 2020-12-17 ations, engage entrepreneuri ant Selection al community and general fol low up with potential benefici aries. GZ-DAI-168744-CS-CCP / Pro Building an Outsourcing Hub Individual Consult Pending Impleme vision of capacity building for TF / A7439 Post Limited 0.00 2020-10-01 2020-10-08 2020-10-15 2020-10-20 2021-02-28 in Gaza ant Selection ntation IT professionals and freelanc ers. GZ-DAI-199377-CS-INDV / Hi Entrepreneurship Ecosystem Individual Consult TF / A7439 Post Direct 15,600.00 Terminated 2020-10-15 2020-10-14 2020-10-25 2020-10-29 2020-11-01 2020-11-01 2020-11-15 2020-11-03 2021-11-15 re a part time M&E Specialist Development ant Selection for IPSD. GZ-DAI-200595-CS-INDV / IP Entrepreneurship Ecosystem Individual Consult SD Project Director Position t TF / A7439 Post Open 97,200.00 Signed 2020-10-23 2020-10-20 2020-11-25 2020-12-23 2020-12-16 2020-12-24 2020-12-23 2021-01-05 2021-12-21 Development ant Selection o be advertised on jobs.ps. GZ-DAI-200827-CS-INDV / D AI Country Director Said Abu Hijleh will immediately take o ver the role of acting Project Individual Consult Director , and will dedicate 3 TF / A7439 Project Management Post Direct 51,879.75 Completed 2020-10-22 2020-10-22 2020-10-25 2020-10-18 2020-10-26 2020-10-18 2020-10-29 2020-10-19 2021-01-18 ant Selection 6 working days over the next three months to achieve proj ect outcomes in coordination with Ministry of National Eco nomy &World Bank. GZ-DAI-200855-CS-INDV / Hi re a Business Development S Building an Outsourcing Hub Individual Consult TF / A7439 Post Open 0.00 Canceled 2020-10-23 2020-10-22 2020-12-21 2021-01-11 2021-01-30 2024-01-30 pecialist for G-Gateway for th in Gaza ant Selection e life of the project ( 3 years) GZ-DAI-208715-CS-INDV / Is suing a new contract to Ninar u Shtayyeh: revising her Ter Entrepreneurship Ecosystem Individual Consult ms of Reference, changing h TF / A7439 Post Direct 13,068.00 Completed 2020-12-09 2020-12-14 2020-12-12 2020-12-01 2020-12-13 2020-12-15 2020-12-16 2020-12-17 2021-05-15 2021-05-16 Development ant Selection er title to: Technical Coordina tor, instead of Junior Consult ant, and revising her rate. Le vel of Effort is 110 days. GZ-DAI-210436-CS-INDV / Hi Entrepreneurship Ecosystem Individual Consult re Component 1.2 lead" Dev TF / A7439 Post Limited 67,200.00 Signed 2020-12-17 2020-12-21 2020-12-20 2020-12-16 2020-12-21 2020-12-21 2020-12-23 2020-12-22 2021-12-22 Development ant Selection elop a dynamic startup finan ce ecosystem". GZ-DAI-211246-CS-CCP / Hir Individual Consult TF / A7439 Project Management Post Limited 0.00 Terminated 2020-12-24 2020-12-24 2021-01-12 2021-01-03 2021-01-24 2021-01-19 2021-02-01 2021-01-19 2022-02-01 e Operations Coordinator-We ant Selection st Bank. Page 4 GZ-DAI-211247-CS-CCP / Hir e Operations Coordinator-Ga Individual Consult TF / A7439 Project Management Post Limited 12,000.00 Signed 2020-12-24 2020-12-29 2021-01-10 2021-01-03 2021-01-21 2021-01-17 2021-02-01 2021-01-19 2022-02-01 za, Full Time , split between I ant Selection PSD and Techstart projects. GZ-DAI-211801-CS-INDV / Hi Individual Consult re Communication Officer. All TF / A7439 Project Management Post Direct 16,250.00 Terminated 2020-12-31 2021-01-03 2021-01-04 2020-09-01 2021-01-05 2021-01-10 2021-01-07 2021-01-22 2022-01-06 ant Selection ocated for both Techstart an d IPSD projects. GZ-DAI-211800-CS-INDV / Hi re Environmental and Social Individual Consult TF / A7439 Project Management Post Direct 12,000.00 Signed 2020-12-31 2021-01-03 2021-01-04 2021-01-03 2021-01-05 2021-01-20 2021-01-07 2021-01-11 2022-01-06 Officer -Split between IPSD a ant Selection nd Techstart Projects. GZ-DAI-216385-CS-INDV / Hi Individual Consult re Operations Coordinator for TF / A7439 Project Management Post Limited 31,200.00 Signed 2021-01-28 2021-02-01 2021-02-04 2021-04-05 2021-02-11 2021-04-26 2021-02-18 2021-05-05 2022-02-17 ant Selection IPSD-West Bank. GZ-DAI-219416-CS-INDV / C ontract an individual consult ant to support the developm ent of Component 1, Activity Entrepreneurship Ecosystem Individual Consult TF / A7439 Post Direct 25,200.00 Terminated 2021-02-17 2021-02-16 2021-02-20 2021-02-22 2021-02-22 2021-02-21 2021-02-25 2021-03-02 2022-02-24 2 of the IPSD with a particula Development ant Selection r focus on bridging the early commercialization funding ga p to investment through the Pre-Investment grant progra m. GZ-DAI-220261-CS-INDV / C onsultant services to suppor t the development of Compo nent 1, Activity 2 of the IPSD Entrepreneurship Ecosystem Individual Consult with a particular focus on sti TF / A7439 Post Direct 30,238.00 Terminated 2021-02-21 2021-02-22 2021-02-24 2021-03-03 2021-02-28 2021-02-22 2021-03-04 2021-03-04 2022-03-03 Development ant Selection mulating private investment by first-time angels and enco uraging investment syndicati on between seasoned and le ss-experienced investors. GZ-DAI-220989-CS-INDV / Hi re GGateway Managing Direc tor as part of GGateway Expa Building an Outsourcing Hub Individual Consult nsion to external markets an TF / A7439 Post Open 36,000.00 Completed 2021-02-25 2021-02-24 2021-03-28 2021-04-20 2021-04-04 2021-09-06 2021-04-13 2021-09-06 2022-04-12 2022-03-07 in Gaza ant Selection d presence in the West Bank. GGATEWAY WILL BE SIGNING THE CONTRACT with the sele cted candidate. GZ-DAI-223418-CS-INDV / Pr ocurement Plan for Manager Entrepreneurship Ecosystem Individual Consult component 1.1 - Improving M TF / A7439 Post Limited 67,980.00 Terminated 2021-03-11 2021-03-09 2021-03-16 2021-05-17 2021-03-25 2021-05-23 2021-04-07 2021-05-29 2022-04-06 Development ant Selection arket Linkages to Arab comm unities in regional entreprene urship ecosystems. GZ-DAI-225401-CS-INDV / Tr Entrepreneurship Ecosystem Individual Consult anslation Services for IPSD-R TF / A7439 Post Limited 8,000.00 Completed 2021-03-22 2021-03-28 2021-03-25 2021-04-01 2021-04-14 2021-04-07 2021-04-22 2021-04-12 2021-09-30 2022-04-11 Development ant Selection etainership agreement. GZ-DAI-234777-CS-INDV / Is sue a new contract to Ninaru Entrepreneurship Ecosystem TF / A7439 Post Direct Selection Direct 30,680.00 Signed 2021-05-20 2021-05-24 2021-05-23 2021-05-25 2021-05-24 2021-05-26 2022-05-23 Shtayyeh as technical coordi Development nator, to hire her on full time bases with IPSD. GZ-DAI-246767-CS-INDV / Hi Individual Consult Under Implement re short term technical and G TF / A7439 Project Management Post Limited 0.00 2021-08-11 2021-08-15 2021-08-19 2021-09-06 2021-09-19 2022-03-20 ant Selection ation rants Support Officer. GZ-DAI-251486-CS-INDV / C onsultancy Services to suppo rt the development of Compo nent 1, Activity 2 of the IPSD Entrepreneurship Ecosystem Individual Consult with a particular focus on pro TF / A7439 Post Limited 70,000.00 Signed 2021-09-16 2021-09-14 2021-09-23 2021-11-24 2021-10-21 2021-11-29 2021-11-04 2021-12-01 2022-11-03 Development ant Selection moting and supporting the d evelopment of new angel gro ups in the WB&G while poten tially linking in regional ecos ystems and diaspora. GZ-DAI-253584-CS-CDS / Hir Building an Outsourcing Hub e Saba & Co. as Ggateway ta TF / A7439 Post Direct Selection Direct 24,360.00 Completed 2021-09-16 2021-09-21 2021-09-19 2021-09-26 2021-09-23 2021-10-07 2022-06-30 2022-10-05 in Gaza x exemption consultant. GZ-DAI-264591-CS-CDS / Em Building an Outsourcing Hub bedded C Programming with TF / A7439 Post Direct Selection Direct 6,133.30 Completed 2021-11-25 2021-12-13 2021-12-05 2022-07-27 2021-12-31 2022-08-06 2022-03-31 2022-10-17 in Gaza IMT school in Egypt. GZ-DAI-266910-CS-CDS / Le gal Consultancy Services for G_Gateway. Amendment of e Building an Outsourcing Hub TF / A7439 Post Direct Selection Direct 7,620.00 Completed 2021-12-12 2021-12-08 2021-12-22 2021-12-22 2022-01-10 2021-12-24 2022-04-28 2022-01-01 xisting contract between GG in Gaza atway and the Legal Firm (Al Hatu Law Firm), with regards to Ggateway Legal Structure. GZ-DAI-266944-CS-CDS / Co Building an Outsourcing Hub operation between GGatewa TF / A7439 Post Direct Selection Direct 0.00 Canceled 2021-12-23 2022-01-23 2021-12-31 2022-02-14 2022-02-05 2022-06-09 in Gaza y and Ani Tech LLC in trainin g resources. GZ-DAI-268805-CS-INDV / Th Individual Consult is job will be split equally bet TF / A7439 Project Management Post Open 27,600.00 Signed 2021-12-19 2021-12-16 2022-01-21 2022-02-01 2022-01-30 2022-03-28 2022-02-02 2022-04-01 2023-02-02 ant Selection ween IPSD and Techstart (50 -50). GZ-DAI-276049-CS-CDS / Ta x Consultancy Services for G Gateway-West Bank, includin g opening tax file at the MoF Building an Outsourcing Hub TF / A7439 Post Direct Selection Direct 8,800.00 Signed 2022-02-08 2022-02-08 2022-02-14 2022-05-13 2022-02-23 2022-04-29 2023-02-22 in Ramallah. The contract will in Gaza be sole sourced to Deloitte, s ince Saba (Branch of Deloitte in Gaza) is providing tax cons ultancy services to GGatewa y-Gaza. GZ-DAI-279042-CS-INDV / Hi ring Communications Lead C Building an Outsourcing Hub Individual Consult onsultant for GGateway. GGa TF / A7439 Post Direct 5,814.00 Terminated 2022-02-17 2022-03-01 2022-02-27 2022-02-06 2022-02-27 2022-03-14 2022-03-02 2022-03-18 2023-03-01 in Gaza ant Selection teway will be signing the co ntract with the communicatio ns specialist. Page 5 GZ-DAI-283310-CS-CDS / Le gal Assistance for the autom Entrepreneurship Ecosystem TF / A7439 Post Direct Selection Direct 121,220.00 Signed 2022-03-08 2022-03-10 2022-03-09 2022-03-08 2022-03-09 2022-03-21 2022-08-18 ation of the Company registr Development ation and Capacity Building f or MoNE. GZ-DAI-288720-CS-CDS / Hir Building an Outsourcing Hub e a Digital Academy Consulta TF / A7439 Post Direct Selection Direct 36,288.00 Completed 2022-04-12 2022-04-18 2022-04-19 2022-04-06 2022-04-20 2022-04-16 2023-01-20 2023-01-17 in Gaza nt for GGateway. GZ-DAI-295815-CS-CDS / Co nduct Business and financial Entrepreneurship Ecosystem TF / B5149 Post Direct Selection Direct 16,563.64 Completed 2022-05-21 2022-05-26 2022-05-28 2022-05-16 2022-06-12 2022-06-09 2022-12-12 2022-08-26 trainings for startups and SM Development Es that benefited from Covid- 19 grants of 2022. GZ-DAI-290996-CS-INDV / Hi Building an Outsourcing Hub Individual Consult TF / A7439 Post Direct 0.00 Canceled 2022-04-18 2022-04-19 2022-04-19 2022-04-22 2022-04-22 2022-06-01 2023-05-31 re GGateway Managing Direc in Gaza ant Selection tor. GZ-DAI-295810-CS-CDS / Ph ase 2 of IRAS Program. Since the consultant concluded ph ase 1 successfully, phase 2 Entrepreneurship Ecosystem TF / A7439 Post Direct Selection Direct 552,143.80 Signed 2022-06-02 2022-06-06 2022-06-08 2022-06-08 2022-06-22 2022-07-14 2023-09-16 will be implemented by the s Development ame consultant. The direct s election is considered as a fol low on, in accordance with th e IPSD project operations ma nual. GZ-DAI-301208-CS-INDV / C ontract senior consultant to s Entrepreneurship Ecosystem Individual Consult upport component 1, activity TF / A7439 Post Limited 0.00 Signed 2022-07-10 2022-08-14 2022-07-17 2022-11-14 2022-08-07 2022-11-21 2022-08-14 2023-02-13 Development ant Selection 1 of IPSD, with particular foc us on improving market linka ges. GZ-DAI-301206-CS-CDS / Co- Entrepreneurship Ecosystem Individual Consult Investment Grants Committe TF / A7439 Post Direct 0.00 Signed 2022-07-03 2022-09-08 2022-07-17 2022-09-13 2022-07-25 2022-09-21 2022-07-30 2023-07-27 Development ant Selection e member. Review up to 30 a pplications. GZ-DAI-317950-CS-CDS / A c ontract will be signed with a l Entrepreneurship Ecosystem TF / B5149 Post Direct Selection Direct - National 0.00 Signed 2022-10-02 2022-10-18 2022-10-12 2022-10-23 2022-10-23 2023-04-21 aw firm to register branches Development of international companies in the West Bank. GZ-DAI-324604-CS-CDS / Im plementation of Automated B Entrepreneurship Ecosystem Direct - Internation usiness Registry at the Minist TF / A7439 Post Direct Selection 0.00 Signed 2022-11-17 2022-11-16 2022-11-21 2022-11-24 2022-12-20 2024-11-17 Development al ry of National Economy. The procurement will be Sole Sou rced to UNCTAD. GZ-DAI-331504-CS-INDV / Hi Individual Consult TF / A7439 Project Management Post Limited 0.00 Signed 2022-12-29 2023-01-12 2023-01-03 2023-02-26 2023-01-10 2023-04-12 2023-03-01 2024-02-29 re a junior accountant for IPS ant Selection D. GZ-DAI-331510-CS-INDV / Hi Individual Consult Under Implement re a grants/Procurement Offi TF / A7439 Project Management Post Limited 0.00 2022-12-20 2023-01-12 2023-01-05 2023-01-26 2023-02-21 2024-02-20 ant Selection ation cer for IPSD. GZ-DAI-331516-CS-INDV / Hi Individual Consult Under Implement re an intern who will be provi TF / A7439 Project Management Post Limited 0.00 2022-12-27 2023-01-12 2023-01-02 2023-01-16 2023-02-01 2023-07-31 ant Selection ation ding support to M&E Unit at I PSD. GZ-DAI-331852-CS-INDV / Hi re Technical Coordinator for I Entrepreneurship Ecosystem Individual Consult Under Implement TF / A7439 Post Limited 0.00 2022-12-15 2023-01-12 2022-12-29 2023-01-19 2023-02-15 2023-08-14 PSD, who will work with activi Development ant Selection ation ty managers in implementing IPSD activities. GZ-DAI-331494-CS-CDS / HR Building an Outsourcing Hub services and market salaries TF / A7439 Post Direct Selection Direct - National 0.00 Signed 2023-01-19 2023-03-02 2023-01-29 2023-03-06 2023-02-06 2023-06-06 in Gaza data for the benefit of GGate way. GZ-DAI-346935-CS-CDS / Sy nopses Training. Provide tech nical coaching services to GG Building an Outsourcing Hub Direct - Internation Under Implement TF / A7439 Post Direct Selection 0.00 2023-03-12 2023-03-14 2023-03-17 2023-03-26 2023-10-03 ateway. Beneficiaries will be in Gaza al ation hardware engineers ,who will be part of train and hire mod el. GZ-DAI-345740-CS-CDS / Hir e a Partnership and Develop Building an Outsourcing Hub ment Consultant for GGatew TF / B5149 Post Direct Selection Direct - National 0.00 Signed 2023-02-28 2023-03-27 2023-03-08 2023-03-28 2023-03-16 2024-01-15 in Gaza ay. GGateway will sign the co ntract with the consultant. GZ-DAI-357373-CS-CDS / Sof tware development for the b Entrepreneurship Ecosystem TF / B5149 Post Direct Selection Direct - National 0.00 Signed 2023-04-30 2023-04-27 2023-05-06 2023-05-02 2023-05-12 2024-02-10 enefit of Co Investment Gran Development t Recipient (Bonoud). GZ-DAI-358885-CS-INDV / Hi re Manager of subcomponent Entrepreneurship Ecosystem Individual Consult Under Implement 1.1 "Improving Market Linkag TF / A7439 Post Open - National 0.00 2023-05-02 2023-05-03 2023-06-13 2023-07-04 2023-08-01 2024-07-31 Development ant Selection ation es to Arab Communities in re gional entrepreneurship Ecos ystems". GZ-DAI-360168-CS-INDV / Hi re M&E Specialist for IPSD an Individual Consult Under Implement TF / A7439 Project Management Post Open - National 0.00 2023-05-10 2023-05-10 2023-06-20 2023-07-04 2023-09-01 2024-08-31 d Techstart. This position will ant Selection ation be allocated for both IPSD an d Techstart. GZ-DAI-360171-CS-INDV / Hi re a Consultant to implement Entrepreneurship Ecosystem Individual Consult Under Implement TF / B5149 Post Limited 0.00 2023-05-14 2023-05-15 2023-05-28 2023-06-18 2023-07-13 2024-07-12 'Business Advisory Services Development ant Selection ation Under the Nexus Program". GZ-DAI-361010-CS-INDV / Hi re a consultant to implement Entrepreneurship Ecosystem Individual Consult Under Implement TF / B5149 Post Limited 0.00 2023-05-14 2023-05-15 2023-05-28 2023-06-18 2023-07-19 2024-07-18 "Business Advisory Services Development ant Selection ation Under the Nexus Program". GZ-DAI-360153-CS-INDV / Hi Entrepreneurship Ecosystem Individual Consult Under Implement re 1ICT specialist for the Auto TF / A7439 Post Open - National 0.00 2023-05-16 2023-05-22 2023-06-25 2023-07-16 2023-08-18 2024-08-17 Development ant Selection ation mated Business Registry Syst em activity. GZ-DAI-361003-CS-INDV / Hi Entrepreneurship Ecosystem Individual Consult Under Implement re 1 ICT Specialist for the Aut TF / A7439 Post Open - National 0.00 2023-05-16 2023-05-22 2023-06-25 2023-07-16 2023-08-07 2024-08-06 Development ant Selection ation omated Business Registry Ac tivity. Page 6 GZ-DAI-361704-CS-CDS / Vid eo Production Services for th Entrepreneurship Ecosystem TF / B5149 Post Direct Selection Direct - National 0.00 Signed 2023-05-25 2023-05-17 2023-06-04 2023-06-05 2023-06-22 2023-07-23 e benefit of Pre Investment G Development rant Beneficiary ( Turqat Co mpany). GZ-DAI-361707-CS-CDS / Re view Home Based Business l Entrepreneurship Ecosystem Under Implement egal and institutional report f TF / A7439 Post Direct Selection Direct - National 0.00 2023-05-24 2023-05-18 2023-06-08 2023-07-09 2024-01-10 Development ation or IPSD, including the provisi on of recommendations and i dentifying gaps. Page 7 PROCUREMENT PLAN (Textual Part) Project information: [Benin] [Benin Global Partnership for Education Project Phase 3] [P-167432] Project Implementation agency: Ministry of Preschool and Primary Education] Date of the Procurement Plan: January 6, 2020 Period covered by this Procurement Plan: January 6 to December 31, 2020. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is applicable for those contracts identified in the Procurement Plan tables]; Works: [is applicable for those contracts identified in the Procurement Plan tables] PROCUREMENT Benin : Benin Global Partnership for Education Project Phase 3 PLAN General Information Country: Benin 2020-03-05 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167432 GPN Date: 2020-03-02 Project Name: Benin Global Partnership for Education Project Phase 3 Loan / Credit No: / , TF / B0364 PROJECT TECHNICAL SUPPORT AND MONITORING UNIT Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UATS-152375-GO-RFB / A cquisition d’un (01) véhicule 4X4 station wagon et d’un (0 1) véhicule PICK – UP 4X4 do Component 1 : Improving th Single Stage - One E Under Imple uble cabines au profit de l'Un / Post Request for Bids Open - National 258,621.00 0.00 2020-01-28 2020-10-16 2020-02-02 2020-03-15 2020-11-30 2020-04-14 2020-12-01 2020-05-19 2020-11-15 e Quality of Basic Education nvelope mentation ité d’Appui Technique et de S uivi du Programme PME 3 et de deux (02) mini bus de 30 places avec climatisation d'o rigine au profit des CPSA BJ-UATS-152379-GO-RFQ / A cquisition de pièces de recha nge au profit de l'Unité d’App Component 1 : Improving th Request for Quota Single Stage - One E Under Imple / Post Open - National 25,862.00 0.00 2020-02-08 2020-04-19 2020-04-04 2020-10-01 ui Technique et de Suivi du P e Quality of Basic Education tions nvelope mentation rogramme Partenariat Mondi al pour l’Education (UATS/PM E 3) BJ-UATS-152289-GO-RFB / A cquisition de matériels et con sommables informatiques et divers équipements, matériel Component 1 : Improving th Single Stage - One E s, fournitures et mobiliers de TF / B0364 Post Request for Bids Open - National 346,896.00 444,096.03 Completed 2020-03-30 2020-10-16 2020-04-04 2021-12-14 2020-05-16 2020-11-30 2020-06-15 2021-01-22 2020-07-20 2021-04-27 2021-01-16 2021-06-16 e Quality of Basic Education nvelope bureau au profit de l’UATS, d e l’INFRE, du STP/PSE, de la DPHTA et d’autres structures puis des tablettes électroniq ues au profit des BJ-UATS-152381-GO-RFB / A cquisition de matériels et éq uipements d'enseignement, d'appareils spécifiques et de Component 1 : Improving th Single Stage - One E Under Imple TF / B0364 Post Request for Bids Open - National 379,310.00 0.00 2020-04-20 2020-12-30 2020-04-25 2021-12-17 2020-06-06 2021-02-01 2020-07-06 2021-02-22 2020-08-10 2021-02-06 mobilité, de kits scolaires et e Quality of Basic Education nvelope mentation de vivres au profit des enfant s handicapés des écoles spéc ialisées et d'Équipements su pplémentaires au profit des E NI et ENS BJ-UATS-164562-GO-RFB / F ourniture pluriannuelle de qu Component 3: Strengthening atre mille (4000) repas dans l Single Stage - One E TF / B0364 the Delivery of Education Se Post Request for Bids Open - National 103,448.00 19,803.69 Completed 2020-05-11 2020-12-07 2020-05-16 2020-06-27 2021-02-01 2020-07-27 2021-02-12 2020-08-31 2021-04-08 2021-02-27 2021-11-18 e cadre des réunions et ateli nvelope rvices ers au niveau des départeme nts de l'Ouémé et du Littoral BJ-UATS-164565-GO-RFQ / A cquisition d'un logiciel Tablea u soft (licence 1 an pour 5 ut Component 3: Strengthening ilisateurs), d'équipements de Request for Quota Single Stage - One E TF / B0364 the Delivery of Education Se Post Limited 65,517.00 103,180.12 Signed 2020-04-18 2020-04-07 2020-06-13 2020-10-08 2020-12-10 filtrage de bande passante et tions nvelope rvices d'équipements de numérisati on de documents et stockage de données au profit de la DI P secondaire BJ-UATS-164564-GO-RFQ / A cquisition et mise en place d' équipements électriques et r Component 3: Strengthening éseau pour le renforcement Request for Quota Single Stage - One E Under Imple TF / B0364 the Delivery of Education Se Post Limited 87,810.00 0.00 2020-05-02 2020-06-27 2020-12-24 du DATA CENTER du MEMP et tions nvelope mentation rvices d'équipements réseau et TEL ECOM pour l'extension de l'in tranet du MEMP élargi aux str uctures externes BJ-UATS-164584-GO-DIR / Co nvention de financement de l 'UNICEF pour la fourniture et Component 2: Improving Eq Pending Impl TF / B0364 Post Direct Selection Direct 1,292,433.00 0.00 2020-03-30 2020-04-04 2020-05-09 2020-11-05 la distribution des kits scolair uity in Basic Education ementation es aux écoliers des écoles pri maires publiques (CI et CP) BJ-UATS-199919-GO-RFQ / A cquisition pluriannuelle de fo urnitures de bureau, de cons ommables informatiques et d Component 1 : Improving th Request for Quota Single Stage - One E Pending Impl TF / B0364 Post Limited 54,545.00 0.00 2020-10-24 2020-12-19 2021-06-17 e produits d’entretien au prof e Quality of Basic Education tions nvelope ementation it des structures financées pa r le PPME 3 dans le cadre de l 'exécution de leurs différente s activités BJ-UATS-224401-GO-RFB / A cquisition et mise en place d' équipements électriques et r éseau pour le renforcement Component 1 : Improving th Single Stage - One E Pending Impl TF / B0364 Post Request for Bids Open - National 137,000.00 0.00 2021-03-25 2021-03-30 2021-05-11 2021-06-10 2021-07-15 2022-01-11 du DATA CENTER du MEMP et e Quality of Basic Education nvelope ementation d'équipements réseau et TEL ECOM pour l'extension de l'in tranet du MEMP élargi aux str uctures externes BJ-UATS-262345-GO-RFB / A cquisition d'intrants (papiers, Component 1 : Improving th Single Stage - One E TF / B0364 Post Request for Bids Open - National 320,000.00 243,142.74 Signed 2021-11-15 2021-11-16 2021-11-20 2021-11-26 2022-01-01 2021-12-10 2022-01-31 2021-12-13 2022-03-07 2022-02-03 2022-09-03 encres, etc...) pour la multipli e Quality of Basic Education nvelope cation des documents pédag ogiques de CI. Page 1 BJ-UATS-281282-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl cquisition de deux (2) véhicul TF / B0364 the Delivery of Education Se Post Limited 64,000.00 0.00 2022-03-15 2022-05-10 2022-11-06 tions nvelope ementation es pick-up 4X4 double cabine rvices s BJ-UATS-305418-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E TF / B0364 Post Open - National 17,000.00 0.00 Signed 2022-08-02 2022-09-27 2023-03-26 cquisition de 12 motos au pr the Delivery of Education Se tions nvelope ofit de ISEH rvices BJ-UATS-316236-GO-RFQ / A Component 3: Strengthening Request for Quota Single Stage - One E cquisition de 50 tablettes co TF / B0364 the Delivery of Education Se Post Open - National 16,364.00 0.00 Signed 2022-10-04 2022-11-29 2023-05-28 tions nvelope mplémentaires rvices BJ-UATS-305409-GO-RFQ / A cquisition de matériels infor Component 2: Improving Eq Request for Quota Single Stage - One E matiques au profit de l'UATS, TF / B0364 Post Open - National 95,000.00 0.00 Canceled 2022-10-04 2023-02-06 2022-11-29 2023-05-28 uity in Basic Education tions nvelope de la DPSHPA, de la DDASM et des CPS des Collines. BJ-UATS-310167-GO-RFQ / A cquisition de matériels et éq Component 2: Improving Eq Request for Quota Single Stage - One E uipements spécifiques puis d' TF / B0364 Post Open - National 36,473.00 0.00 Canceled 2022-10-08 2022-12-13 2022-12-03 2023-06-01 uity in Basic Education tions nvelope aide techniques de mobilité a u profit des enfants handicap és des Collines BJ-UATS-310156-GO-RFQ / A Component 2: Improving Eq Request for Quota Single Stage - One E cquisition de kits scolaires au TF / B0364 Post Open - National 9,100.00 0.00 Signed 2022-10-05 2022-11-30 2023-05-29 uity in Basic Education tions nvelope profit des enfants handicapé s des Collines BJ-UATS-310162-GO-RFQ / A cquisition de vivre et autres Component 2: Improving Eq Request for Quota Single Stage - One E produits de premières nécess TF / B0364 Post Open - National 14,345.00 0.00 Signed 2022-10-11 2022-12-06 2023-06-04 uity in Basic Education tions nvelope ité aux apprenants référencé s dans les écoles et centre d e référence BJ-UATS-338647-GO-RFQ / A CQUISITION DE KITS SCOLAIR Component 1 : Improving th Request for Quota Single Stage - One E TF / B0364 Post Open - National 10,000.00 0.00 Signed 2023-04-26 2023-03-14 2023-06-21 2023-12-18 ES AU PROFIT DES LAUREATS e Quality of Basic Education tions nvelope DU JEU " LES PTITS CHAMPIO NS DE LA LECTURE " BJ-UATS-340453-GO-RFQ / A cquisitions de matériels et éq Component 2: Improving Eq Request for Quota Single Stage - One E uipements spécifiques puis d' TF / B0364 Post Open - National 36,473.00 0.00 Canceled 2023-03-05 2023-03-08 2023-04-30 2023-10-27 uity in Basic Education tions nvelope aides techniques de mobilité au profit des enfants handica pés des Collines. BJ-UATS-338633-GO-RFQ / A Component 3: Strengthening cquisition de matériels et con Request for Quota Single Stage - One E TF / B0364 the Delivery of Education Se Post Open - National 9,990.00 0.00 Signed 2023-04-04 2023-02-28 2023-05-30 2023-11-26 sommables informatiques et tions nvelope rvices fournitures de bureau au prof it du STP-PDDSE BJ-UATS-362967-GO-RFQ / A cquisition d’équipement des Component 3: Strengthening Request for Quota Single Stage - One E Under Imple salles de la RSE/INFRE pour l TF / B0364 the Delivery of Education Se Post Open - National 83,300.00 0.00 2023-06-19 2023-06-15 2023-08-14 2024-02-10 tions nvelope mentation a production audio et visuelle rvices pour l'enseignement à distan ce BJ-UATS-344231-GO-RFB / A cquisition d'équipement des Component 3: Strengthening Single Stage - One E salles de la RSE/INFRE pour l TF / B0364 the Delivery of Education Se Post Request for Bids Open - National 140,000.00 0.00 Canceled 2023-04-04 2023-04-09 2023-05-21 2023-06-20 2023-07-25 2024-01-21 nvelope a production audio et visuelle rvices pour l'enseignement à distan ce NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UATS-152389-NC-RFQ / R ecrutement pluriannuel d'un prestataire pour l'assurance Component 3: Strengthening Request for Quota Single Stage - One E Under Imple maladie du personnel et des / the Delivery of Education Se Post Open - National 34,483.00 0.00 2020-02-22 2020-04-18 2020-10-15 tions nvelope mentation véhicules de l'Unité d’Appui T rvices echnique et de Suivi du Progr amme Partenariat Mondial po ur l’Education (UATS/PME 3) BJ-UATS-152388-GO-RFB / I mpression du livret de lectur e initiale pour les élèves de l Component 1 : Improving th Open - Internationa Single Stage - One E TF / B0364 Prior Request for Bids 2,324,138.00 0.00 Canceled 2020-04-20 2020-04-25 2020-06-06 2020-07-06 2020-08-10 2021-02-06 a 1ère année et de la 2ème a e Quality of Basic Education l nvelope nnée et des guides de l'ensei gnant (2ème année de Math ématiques) BJ-UATS-164567-NC-RFQ / A cquisition et installation d’un logiciel de gestion financière Component 1 : Improving th Request for Quota Single Stage - One E et comptable au profit de l'U TF / B0364 Post Limited 20,690.00 12,915.45 Signed 2020-05-02 2020-04-09 2020-06-27 2020-09-12 2020-12-24 e Quality of Basic Education tions nvelope nité d’Appui Technique et de Suivi du Programme Partenar iat Mondial pour l’Education ( UATS/PME 3) BJ-UATS-152397-NC-RFB / R ecrutement d'un prestataire pour la distribution de nouve aux livrets de lecture initiale Component 1 : Improving th Single Stage - One E Pending Impl et autres matériels pour les é TF / B0364 Post Request for Bids Open - National 248,276.00 0.00 2020-06-15 2020-06-20 2020-08-01 2020-08-31 2020-10-05 2021-04-03 e Quality of Basic Education nvelope ementation lèves du CI et du CP ainsi qu e des programmes et guides pédagogiques élaborés du 1e r cycle secondaire dans toute s les communes du Bénin BJ-UATS-164583-NC-DIR / Co nvention de financement de l Component 2: Improving Eq Pending Impl 'appui à l'intégration scolaire TF / B0364 Post Direct Selection Direct 517,241.00 0.00 2020-03-30 2020-04-04 2020-05-09 2020-11-05 uity in Basic Education ementation des enfants handicapés dans le département Zou à travers le Volet ISEH BJ-UATS-152399-NC-RFQ / R Component 3: Strengthening Request for Quota Single Stage - One E ecrutement d'un prestataire TF / B0364 the Delivery of Education Se Post Open - National 8,621.00 6,802.14 Completed 2020-03-19 2021-12-17 2020-05-14 2020-10-08 2020-11-10 2020-10-23 tions nvelope pour assurer le déménageme rvices nt de l'UATS Page 2 BJ-UATS-199961-NC-RFQ / R ecrutement d’un prestataire pour les travaux d’impressio n pour l’atelier de formation Component 1 : Improving th Request for Quota Single Stage - One E Pending Impl TF / B0364 Post Limited 20,000.00 0.00 2020-10-24 2020-12-19 2021-06-17 des enseignants de la 1ère a e Quality of Basic Education tions nvelope ementation nnée (Cours d’Initiation) et d es directeurs d'écoles à l'utili sation de nouveaux program mes, guides et manuels révis és BJ-UATS-201666-NC-RFQ / R estauration des participants à l’atelier de formation des e nseignants de la 1ère année Component 1 : Improving th Request for Quota Single Stage - One E (Cours d’Initiation) et des dir TF / B0364 Post Limited 11,818.00 7,235.65 Signed 2020-11-04 2020-08-24 2020-12-30 2020-09-08 2021-06-28 e Quality of Basic Education tions nvelope ecteurs d'écoles à l'utilisation de nouveaux programmes, g uides et manuels révisés (lec ture-écriture et mathématiqu e) phase pilote BJ-UATS-201668-NC-RFQ / I mpression de nouveaux prog rammes pour écoliers et de modules de formation et guid Component 1 : Improving th Request for Quota Single Stage - One E TF / B0364 Post Limited 47,273.00 93,085.96 Signed 2020-11-14 2020-11-24 2021-01-09 2020-12-12 2021-07-08 es de professeur dans les ma e Quality of Basic Education tions nvelope tières de français, de mathé matiques, de PCT et d'anglai s pour la phase d'expériment ation au niveau des écoles d u secondaire BJ-UATS-215241-NC-RFB / Im pression des nouveaux livres de lecture initiale et cahiers Component 1 : Improving th Open - Internationa Single Stage - One E Under Imple d’activité pour les élèves de l TF / B0364 Post Request for Bids 2,324,138.00 0.00 2021-01-20 2021-04-13 2021-01-25 2021-04-14 2021-03-08 2021-06-14 2021-04-07 2021-05-12 2021-11-08 e Quality of Basic Education l nvelope mentation a 1ère année et de la 2ème a nnée et de divers documents pédagogiques pour enseigna nts et écoliers du primaire BJ-UATS-224056-NC-DIR / Co nvention de partenariat avec la FERCAB dans le cadre de l Component 1 : Improving th Pending Impl a campagne de sensibilisatio TF / B0364 Post Direct Selection Direct 27,273.00 0.00 2021-03-25 2021-03-30 2021-05-04 2021-10-31 e Quality of Basic Education ementation n pour la scolarisation des en fants dans les onze commun es des départements du Borg ou et de l'Alibori BJ-UATS-164558-NC-RFB / Im pression de divers document Component 1 : Improving th Single Stage - One E Under Imple TF / B0364 Post Request for Bids Open - National 931,897.00 0.00 2021-04-28 2021-03-31 2021-05-03 2021-06-14 2021-06-14 2021-07-14 2021-08-18 2022-02-14 s pédagogiques pour écoliers e Quality of Basic Education nvelope mentation et enseignants du secondaire BJ-UATS-224064-NC-RFQ / R ecrutement d'une imprimerie pour la multiplication des no Component 1 : Improving th Request for Quota Single Stage - One E uveaux documents du CP da TF / B0364 Post Limited 36,500.00 89,227.59 Completed 2021-04-17 2021-08-13 2021-06-12 2021-08-25 2021-12-09 2021-12-28 e Quality of Basic Education tions nvelope ns le cadre de la mise à l'ess ai au cours de la rentrée 202 1 - 2022 et d'autres docume nts du Projet BJ-UATS-199929-NC-RFQ / R ecrutement d’une agence de communication pour la conce ption et la production des out Component 1 : Improving th Request for Quota Single Stage - One E Pending Impl TF / B0364 Post Limited 30,909.00 0.00 2020-10-31 2020-12-26 2021-06-24 ils/supports de communicatio e Quality of Basic Education tions nvelope ementation n et de sensibilisation au prof it de la DEP ainsi que la couv erture médiatique des activit és du Projet BJ-UATS-278117-NC-RFQ / M ultiplication de module de for Component 1 : Improving th Request for Quota Single Stage - One E TF / B0364 Post Limited 37,000.00 9,496.77 Signed 2022-02-22 2022-03-07 2022-04-19 2022-04-09 2022-10-16 mation coaching + tableau d e Quality of Basic Education tions nvelope e bord du CEP 2021 BJ-UATS-278056-NC-DIR / Int ervention chirurgicale de l'hô Component 2: Improving Eq Under Imple pital BETHESDA au profit des TF / B0364 Post Direct Selection Direct 7,900.00 0.00 2022-02-17 2022-03-03 2022-02-22 2022-03-29 2022-09-25 uity in Basic Education mentation enfants handicapés du dépar tements des Collines. BJ-UATS-287673-NC-RFQ / R Component 3: Strengthening ecrutement d’une imprimerie Request for Quota Single Stage - One E Pending Impl TF / B0364 the Delivery of Education Se Post Limited 68,000.00 0.00 2022-05-04 2022-06-29 2022-12-26 pour la multiplication des pla tions nvelope ementation rvices nches thématiques BJ-UATS-316233-NC-DIR / Si gnature d'un contrat avec la Component 1 : Improving th TF / B0364 Post Direct Selection Direct - National 18,182.00 0.00 Signed 2022-09-21 2022-09-23 2022-09-26 2022-10-06 2022-10-31 2023-04-29 Fédération des Radios Comm e Quality of Basic Education unautaires et Assimilées du B énin BJ-UATS-338639-NC-RFQ / F OURNITURE DES OUTILS DE COMMUNICATION PROMOTIO Component 2: Improving Eq Request for Quota Single Stage - One E NNELS ET DE SENSIBILISATIO TF / B0364 Post Open - National 30,000.00 0.00 Signed 2023-05-20 2023-03-30 2023-07-15 2024-01-11 uity in Basic Education tions nvelope N POUR LA PROMOTION DE L A SCOLARISATION DES FILLE S ET SUR L’INSERTION SCOL AIRE DES ENFANTS HANDICA PES BJ-UATS-338662-NC-RFQ / R ecrutement d’un prestataire pour l’impression des docum Component 3: Strengthening Request for Quota Single Stage - One E Pending Impl ents d’évaluation sur échanti TF / B0364 the Delivery of Education Se Post Open - National 20,000.00 0.00 2023-05-24 2023-07-19 2024-01-15 tions nvelope ementation llonnage des élèves du CP et rvices du CM1 au titre de l’année sc olaire 2022-2023 (prétest et post-test) BJ-UATS-338664-NC-RFQ / I mpression complémentaire d es programmes de guides pé dagogiques (Guides de l’ense Component 1 : Improving th Request for Quota Single Stage - One E Under Imple TF / B0364 Post Open - National 40,000.00 0.00 2023-03-01 2023-04-12 2023-04-26 2023-10-23 ignant, Guide d’organisation e Quality of Basic Education tions nvelope mentation pédagogique et matériel, Gui de d’évaluation) de français, mathématiques, sciences et anglais au 1er Cycle du seco ndaire BJ-UATS-338677-NC-RFQ / R ecrutement d'une agence po Component 3: Strengthening ur la réalisation des supports Request for Quota Single Stage - One E Pending Impl TF / B0364 the Delivery of Education Se Post Open - National 30,000.00 0.00 2023-04-10 2023-06-05 2023-12-02 magazines de capitalisations tions nvelope ementation rvices des acquis du projet et de do cumentaires aux normes de l a Banque mondiale Page 3 BJ-UATS-338669-NC-RFQ / R ecrutement d'une agence po ur la production des émission Component 2: Improving Eq Request for Quota Single Stage - One E s à caractère pédagogique p TF / B0364 Post Open - National 18,230.00 0.00 Canceled 2023-05-10 2023-07-05 2024-01-01 uity in Basic Education tions nvelope our accompagner les enseign ants du CI dans l'exécution d es nouveaux curricula révisé s de mathématiques et de fr ançais CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UATS-152416-CS-CQS / R ecrutement d'un Consultant pour la réalisation d'une étud Component 1 : Improving th Consultant Qualifi Pending Impleme / Post Open - National 8,621.00 0.00 2020-02-26 2020-03-18 2020-05-01 2020-05-31 2020-07-05 2021-01-01 e sur les déterminants de la r e Quality of Basic Education cation Selection ntation épartition inéquitable des en seignants au niveau des com munes BJ-UATS-152418-CS-CQS / R Component 3: Strengthening Consultant Qualifi Under Implement ecrutement d'une ONG pour l / the Delivery of Education Se Post Open - National 25,862.00 0.00 2020-02-26 2021-02-11 2020-03-11 2021-12-17 2020-05-06 2020-06-10 2020-12-07 cation Selection ation e contrôle citoyen rvices BJ-UATS-152420-CS-CQS / R ecrutement d'un Consultant Component 3: Strengthening pour l'étude sur les causes d Consultant Qualifi Under Implement / the Delivery of Education Se Post Open - National 51,724.00 0.00 2020-02-28 2020-03-24 2020-03-13 2021-12-17 2020-05-08 2020-11-13 2020-06-12 2020-12-09 e la dégradation des principa cation Selection ation rvices ux indicateurs des sous-secte urs des enseignements prim aire et secondaire BJ-UATS-152421-CS-CQS / R ecrutement d'un Consultant pour la réalisation d'une étud e sur les défis sous-jacents, l Component 3: Strengthening Consultant Qualifi Pending Impleme es opportunités, les implicati / the Delivery of Education Se Post Open - National 34,483.00 0.00 2020-02-28 2020-03-13 2020-05-08 2020-06-12 2020-12-09 cation Selection ntation ons budgétaires ainsi qu'une rvices stratégie pour la mise en œu vre de l'éducation de base co nformément au plan sectoriel de l'éducation BJ-UATS-164561-CS-CQS / R ecrutement d'un Consultant ( Cabinet) chargé de l'évaluati Component 1 : Improving th Consultant Qualifi TF / B0364 Post Open - National 275,862.00 258,812.72 Completed 2020-03-30 2020-04-10 2020-04-20 2021-12-20 2020-06-03 2021-02-19 2020-07-03 2021-03-04 2020-08-07 2021-03-26 2021-02-03 2021-11-25 on sur échantillonnage des c e Quality of Basic Education cation Selection ompétences et pratiques péd agogiques des enseignants BJ-UATS-164577-CS-CQS / R ecrutement d'une ONG charg Component 2: Improving Eq Consultant Qualifi ée de la mobilisation commu TF / B0364 Post Open - National 31,034.00 0.00 Under Review 2020-04-20 2020-05-24 2020-05-11 2020-06-24 2020-07-24 2020-08-28 2021-02-24 uity in Basic Education cation Selection nautaire au niveau des com munes du Borgou ciblés par l e Projet BJ-UATS-164554-CS-CQS / R ecrutement d'un consultant ( Component 3: Strengthening Cabinet) pour mettre à la dis Consultant Qualifi TF / B0364 the Delivery of Education Se Post Open - National 193,966.00 17,254.20 Signed 2020-06-15 2020-08-14 2020-07-06 2021-12-20 2020-08-19 2021-03-04 2020-09-18 2021-05-28 2020-10-23 2021-11-10 2021-04-21 position du MEMP et du MEST cation Selection rvices FP 25 statisticiens en vue d'a ppuyer la production des ann uaires statistiques BJ-UATS-164559-CS-LCS / Re Component 3: Strengthening crutement d'un Consultant (C Least Cost Selecti TF / B0364 the Delivery of Education Se Post Open - National 82,759.00 20,616.43 Completed 2020-04-20 2019-05-10 2020-05-11 2021-12-17 2020-06-24 2020-08-26 2020-07-22 2020-11-06 2020-08-21 2020-11-06 2020-09-25 2020-11-19 2020-10-30 2021-01-23 2021-04-28 2021-09-29 abinet) pour réaliser l'audit fi on rvices nancier et l'audit des marché s du programme BJ-UATS-164578-CS-CQS / R ecrutement d'une ONG charg Component 2: Improving Eq Consultant Qualifi Under Implement ée de la mobilisation commu TF / B0364 Post Open - National 31,034.00 0.00 2020-04-20 2020-05-24 2020-05-11 2021-12-17 2020-06-24 2020-07-24 2020-08-28 2021-02-24 uity in Basic Education cation Selection ation nautaire au niveau des com munes de l'Alibori ciblés par l e Projet BJ-UATS-164582-CS-CQS / R ecrutement d'un Consultant ( Component 3: Strengthening Consultant Qualifi Cabinet) pour la vérification TF / B0364 the Delivery of Education Se Post Open - National 172,414.00 187,967.25 Signed 2020-04-20 2019-04-10 2020-05-11 2021-12-20 2020-06-24 2020-10-20 2020-07-24 2020-11-09 2020-08-28 2021-01-09 2021-02-24 cation Selection des indicateurs liés au décais rvices sement de la part variable de projet BJ-UATS-223170-CS-CQS / R ecrutement d’un consultant ( éditeur) pour les travaux d’é Component 1 : Improving th Consultant Qualifi dition des nouveaux livres de TF / B0364 Post Open - National 54,545.00 0.00 Under Review 2021-03-10 2021-03-15 2021-03-31 2021-05-14 2021-06-13 2021-07-18 2022-01-14 e Quality of Basic Education cation Selection lecture initiale et cahiers d’a ctivité pour les élèves de la 1 ère année et de la 2ème ann ée BJ-UATS-224053-CS-CQS / R ecrutement d’un Consultant ( cabinet médical) pour la Con Component 1 : Improving th Consultant Qualifi Under Implement TF / B0364 Post Open - National 81,818.00 0.00 2021-03-25 2021-03-25 2021-04-15 2021-05-29 2021-06-28 2021-08-02 2022-01-29 sultation, les soins médicaux, e Quality of Basic Education cation Selection ation les traitements chirurgicaux et l'appareillage aux enfants handicapés des Collines INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-UATS-152401-CS-INDV / R ecrutement d'un Spécialiste Component 2: Improving Eq Individual Consult Under Implement / Post Open 38,793.00 0.00 2020-02-25 2020-03-16 2020-04-14 2020-12-01 2020-05-05 2020-10-26 2020-06-09 2020-12-06 en Ingénierie pédagogique a uity in Basic Education ant Selection ation u profit de la DIIP BJ-UATS-152407-CS-INDV / R ecrutement d'un Consultant Component 1 : Improving th Individual Consult Under Implement / Post Open 38,793.00 0.00 2020-02-19 2020-03-16 2020-04-08 2020-04-29 2020-06-03 2020-11-30 Spécialiste en évaluation des e Quality of Basic Education ant Selection ation acquis au profit de l'INFRE BJ-UATS-152408-CS-INDV / R Component 1 : Improving th Individual Consult Under Implement ecrutement d'un Consultant / Post Open 17,241.00 0.00 2020-02-20 2020-03-16 2020-04-09 2020-12-01 2020-04-30 2021-01-01 2020-06-04 2020-12-01 e Quality of Basic Education ant Selection ation en illustration des documents pédagogiques Page 4 BJ-UATS-152410-CS-INDV / R Component 3: Strengthening Individual Consult Pending Impleme ecrutement d'un Spécialiste / the Delivery of Education Se Post Open 38,793.00 0.00 2020-02-21 2020-04-10 2020-05-01 2020-06-05 2020-12-02 ant Selection ntation en communication rvices BJ-UATS-152412-CS-INDV / R ecrutement d'un Consultant I Component 1 : Improving th Individual Consult Pending Impleme / Post Open 15,174.00 0.00 2020-02-21 2020-04-10 2020-05-01 2020-06-05 2020-12-02 nternational pour assurer les e Quality of Basic Education ant Selection ntation formations au niveau du prim aire BJ-UATS-152413-CS-INDV / R ecrutement d'un Consultant Component 1 : Improving th Individual Consult Pending Impleme / Post Open 10,603.00 0.00 2020-02-24 2020-04-13 2020-05-04 2020-06-08 2020-12-05 National pour assurer les for e Quality of Basic Education ant Selection ntation mations au niveau du primair e BJ-UATS-164560-CS-INDV / R ecrutement d'un Consultant Component 3: Strengthening Individual Consult Under Implement pour assurer la formation des TF / B0364 the Delivery of Education Se Post 6,897.00 0.00 2020-04-27 2021-04-24 2020-06-15 2020-07-06 2020-08-10 2021-02-06 ant Selection ation acteurs de la chaîne de pass rvices ation de marchés du Progra mme BJ-UATS-152409-CS-INDV / R ecrutement d'un Consultant Component 3: Strengthening Individual Consult pour la vérification des indica / the Delivery of Education Se Post Open 38,793.00 0.00 Canceled 2020-02-20 2020-04-09 2020-04-30 2020-06-04 2020-12-01 ant Selection teurs liés au décaissement d rvices e la part variable de projet BJ-UATS-201660-CS-INDV / R ecrutement d'un Consultant Spécialiste Chirurgien Pédiatr Component 1 : Improving th Individual Consult TF / B0364 Post Limited 4,545.00 0.00 Canceled 2020-10-31 2020-11-05 2020-11-26 2020-12-31 2021-06-29 e pour les consultations, soin e Quality of Basic Education ant Selection s et traitements chirurgicaux des enfants handicapés des c ollines BJ-UATS-199935-CS-INDV / R ecrutement d'un Enseignant i Component 1 : Improving th Individual Consult tinérant pour les communes TF / B0364 Post Limited 6,364.00 0.00 Under Review 2020-11-09 2021-03-25 2020-11-14 2020-12-05 2021-01-09 2021-07-08 e Quality of Basic Education ant Selection de Bantè, Savalou et Dassa ( Département des Collines) BJ-UATS-201661-CS-INDV / R ecrutement d'un Consultant Spécialiste Kinésithérapeute Component 1 : Improving th Individual Consult TF / B0364 Post Limited 4,545.00 0.00 Canceled 2020-10-31 2020-11-05 2020-11-26 2020-12-31 2021-06-29 Orthoprothésiste pour les co e Quality of Basic Education ant Selection nsultations, soins et traiteme nts chirurgicaux des enfants handicapés des collines BJ-UATS-201662-CS-INDV / R ecrutement d'un Consultant Spécialiste Ophtalmologue p Component 1 : Improving th Individual Consult TF / B0364 Post Limited 4,545.00 0.00 Canceled 2020-10-31 2020-11-05 2020-11-26 2020-12-31 2021-06-29 our les consultations, soins e e Quality of Basic Education ant Selection t traitements chirurgicaux de s enfants handicapés des coll ines BJ-UATS-201664-CS-INDV / R ecrutement d'un Consultant Spécialiste Otorhinolaryngolo Component 1 : Improving th Individual Consult TF / B0364 Post Limited 4,545.00 0.00 Canceled 2020-10-31 2020-11-05 2020-11-26 2020-12-31 2021-06-29 giste (ORL) pour les consultat e Quality of Basic Education ant Selection ions, soins et traitements chi rurgicaux des enfants handic apés des collines BJ-UATS-201665-CS-INDV / R ecrutement d'un Enseignant i Component 1 : Improving th Individual Consult Under Implement tinérant pour les communes TF / B0364 Post Limited 6,364.00 0.00 2020-11-09 2021-03-25 2020-11-14 2020-12-05 2021-01-09 2021-07-08 e Quality of Basic Education ant Selection ation de Ouèssè, Savè et Glazoué ( Département des Collines) BJ-UATS-223173-CS-INDV / R ecrutement d’un Consultant I nternational pour appuyer la Component 1 : Improving th Individual Consult Pending Impleme mise en œuvre des activités TF / B0364 Post Direct 109,091.00 0.00 2021-03-29 2021-04-08 2021-04-29 2021-06-03 2021-11-30 e Quality of Basic Education ant Selection ntation de révision des curricula de C I et CP et de formation des e nseignants sur les nouveaux documents de CI et CP BJ-UATS-224059-CS-INDV / R ecrutement d'un Consultant Spécialiste en évaluation des Component 1 : Improving th Individual Consult Pending Impleme TF / B0364 Post Limited 38,793.00 0.00 2021-03-25 2021-03-30 2021-04-20 2021-05-25 2021-11-21 apprentissages en appui à l’I e Quality of Basic Education ant Selection ntation nstitut National pour la Form ation et la Recherche en Edu cation (INFRE) BJ-UATS-224070-CS-INDV / R Component 1 : Improving th Individual Consult Pending Impleme ecrutement d'un Assistant Ad TF / B0364 Post Open 20,464.00 0.00 2021-03-10 2021-04-28 2021-05-19 2021-06-23 2021-12-20 e Quality of Basic Education ant Selection ntation ministratif au profit de l'UATS BJ-UATS-224072-NC-RFQ / R Component 1 : Improving th Individual Consult Pending Impleme ecrutement d’un consultant TF / B0364 Post Limited 5,455.00 0.00 2021-03-25 2021-03-30 2021-04-20 2021-05-25 2021-11-21 e Quality of Basic Education ant Selection ntation pour la réalisation d’un site w eb pour le Projet BJ-UATS-255850-CS-INDV / R Component 3: Strengthening Individual Consult enouvellement du contrat de TF / B0364 the Delivery of Education Se Post Direct 83,465.00 0.00 Under Review 2021-10-01 2021-10-14 2021-10-11 2021-11-01 2021-12-06 2022-06-04 ant Selection la Spécialiste en Gestion fina rvices ncière BJ-UATS-255865-CS-INDV / R Component 3: Strengthening Individual Consult enouvellement du contrat du TF / B0364 the Delivery of Education Se Post Direct 43,221.00 0.00 Under Review 2021-10-01 2021-10-14 2021-10-11 2021-11-01 2021-12-06 2022-06-04 ant Selection Comptable rvices BJ-UATS-255867-CS-INDV / R Component 3: Strengthening Individual Consult enouvellement du contrat du TF / B0364 the Delivery of Education Se Post Direct 78,809.00 0.00 Under Review 2021-10-01 2021-10-14 2021-10-11 2021-11-01 2021-12-06 2022-06-04 ant Selection Spécialiste en Suivi Evaluatio rvices n BJ-UATS-258364-CS-INDV / R Component 3: Strengthening ecrutement d'un Spécialiste Individual Consult Under Implement TF / B0364 the Delivery of Education Se Post Open 63,000.00 0.00 2021-11-15 2021-11-26 2022-01-03 2022-01-24 2022-02-28 2022-08-27 en Passation des Marchés au ant Selection ation rvices profit de l'UATS - PM3 BJ-UATS-281280-CS-INDV / R enouvellement du contrat du consultant spécialiste en ing Component 1 : Improving th Individual Consult Pending Impleme TF / B0364 Post Direct 100,000.00 0.00 2022-03-08 2022-03-18 2022-04-08 2022-05-13 2022-11-09 énierie pédagogique pour la e Quality of Basic Education ant Selection ntation poursuite des activités relativ es à la révision des curricula de CI et de CP Page 5 BJ-UATS-281281-CS-INDV / R enouvellement du contrat de la contrat relatif à l'accompa Component 1 : Improving th Individual Consult Pending Impleme TF / B0364 Post Direct 100,000.00 0.00 2022-03-08 2022-03-18 2022-04-08 2022-05-13 2022-11-09 gnement du MEMP dans la ra e Quality of Basic Education ant Selection ntation révision des curricula de fran çais et de mathématique au CI-CP BJ-UATS-357390-CS-INDV / R ECRUTEMENT D’UN CONSULT Component 3: Strengthening Individual Consult Under Implement ANT INDIVIDUEL POUR LA RE TF / B0364 the Delivery of Education Se Post Limited 10,000.00 0.00 2023-04-21 2023-05-16 2023-04-26 2023-06-14 2023-05-17 2023-06-21 2023-12-18 ant Selection ation ALISATION DE L’AUDIT ENVIR rvices ONNEMENTAL ET SOCIAL DU PROJET BJ-UATS-357388-CS-CDS / R ecrutement de l'IIPE pour un e assistance technique dans l Component 3: Strengthening e cadre de l’évaluation natio Direct - Internation TF / B0364 the Delivery of Education Se Post Direct Selection 40,000.00 0.00 Under Review 2023-05-29 2023-05-19 2023-06-08 2023-08-12 2024-02-08 nale des acquis scolaires des al rvices écoliers de CP et de CM1 en f rançais et en mathématiques dans les écoles primaires pu bliques et privées du BENIN. Page 6 PROCUREMENT PLAN (Textual Part) Project information: Timor-Leste Basic Education Strengthening and Transformation Project (P166744) Project Implementation agency: Ministry of Education, Youth and Sport (MOEYS) Date of the Procurement Plan: February 26, 2020. Period covered by this Procurement Plan: July 1, 2020 to December 31, 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, the procedures applicable to the procurement of Goods, Works, Non-Consulting services and Consulting Services under the contracts awarded on the basis of National Open Competitive Procurement shall be those procurement methods set forth in the Timor Leste Procurement Legal Regime Decree Law 10/2005, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When the Borrower uses its own national open competitive procurement arrangements as set forth Timor Leste Procurement Legal Regime Decree Law 10/2005, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1. The procurement is open to eligible firms from any country; 2. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; 3. Right for the Bank to review procurement documentation and activities; 4. Maintenance of records of the Procurement process; 5. Procurement Documents acceptable to the Bank shall be used; 6. Bids shall be evaluated using only post-qualification for procurement of goods, works and non-consulting services. 7. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health safety ("ESHS") risks impacts. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Timor-Leste : Basic Education Strengthening and Transformation Project PLAN General Information Country: Timor-Leste 2020-10-28 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166744 GPN Date: 2020-11-16 Project Name: Basic Education Strengthening and Transformation Project Loan / Credit No: IDA / 65510, TF / B2130 Ministry of Education Youth and Sport Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned 001/BEST/TL / 3 packages of new classrooms construction Component 1: Developing 2 Single Stage - One E Pending Imp 2022-08-0 (each package covers differe IDA / 65510 Post Request for Bids Open - National 1,100,000.00 0.00 2021-07-01 2021-07-06 2021-08-17 2021-09-16 2022-02-04 1st Century Learning Spaces nvelope lementation 3 nt municipalities) - 3 schools in 3 different municipalities BEST/WORKS/RFQ01 / PIMU Component 5: Project Manag Request for Quota Single Stage - One E Other (with field f 2022-03-3 TF / B2130 Post Open - National 22,655.50 0.00 Canceled 2021-12-01 2021-12-15 Office Refurbishment ement and Implementation tions nvelope or explanation) 1 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 003/BEST/TL / Provision & In Component 4: Data Driven P Request for Quota Single Stage - One E Under Imple stallation of hardware, includ TF / B2130 lanning, Budgeting, Financin Post Open - National 80,000.00 0.00 2020-11-06 2022-05-19 2022-02-04 2022-08-03 tions nvelope mentation ing servers, software at MoE g and Implementation YS for EMIS 033/BEST/TL / Office electro nic- equipment (computer, pr Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 20,000.00 20,000.00 Signed 2020-10-09 2022-06-21 2020-12-04 2022-05-07 2021-06-02 inter potocopier machine, sc ement and Implementation tions nvelope anner, camera etc) 031/BEST/TL / Furniture and Fixtures for PIMU including Ai Component 5: Project Manag Request for Quota TF / B2130 Post 20,000.00 8,830.00 Signed 2020-10-10 2020-12-05 2022-03-01 2021-06-03 r conditions, telephones, des ement and Implementation tions ks and chairs and office rack s 030/BEST/TL / Purchasing an Component 3: Improving Te d distribution of set of age/gr Single Stage - One E Pending Impl TF / B2130 aching-Learning Material an Prior Request for Bids Open - National 741,000.00 0.00 2021-01-19 2021-01-24 2021-03-07 2021-04-06 2021-06-18 2021-12-15 ade appropriate children's b nvelope ementation d Assessment ooks for Cycle 1 and 2 and fa brication of book corners 002/BEST/TL / Provision and Installation of relevant hardw Component 4: Data Driven P Single Stage - One E Pending Impl are and internet connectivity TF / B2130 lanning, Budgeting, Financin Post Request for Bids Open - National 120,000.00 0.00 2021-08-03 2021-08-08 2021-09-19 2021-10-19 2022-06-05 2022-12-02 nvelope ementation in selected municipal offices g and Implementation and selected central schools 004/BEST/TL / Operational v Component 1: Developing 2 Request for Quota Single Stage - One E IDA / 65510 Post Open - National 80,000.00 36,500.00 Signed 2021-12-05 2022-05-18 2022-01-30 2022-03-02 2022-03-31 ehicles for the use of PIMU 1st Century Learning Spaces tions nvelope 057/BEST/TL / Operational M Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 2,000.00 1,495.00 Signed 2022-05-03 2022-08-11 2022-06-28 2022-08-13 2022-12-25 otorcycle for PIMU Office ement and Implementation tions nvelope 062/BEST/TL / PIMU Operatio Component 5: Project Manag Request for Quota Single Stage - One E nal Vehicles (1 Pick-up, 4WD TF / B2130 Post Open - National 43,500.00 0.00 Completed 2022-07-01 2022-12-03 2022-08-26 2023-02-22 2023-01-06 ement and Implementation tions nvelope and 1 sedan for Dili-based op eration) 065/BEST/TL / PIMU Office i Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 5,000.00 0.00 Terminated 2022-06-10 2022-12-03 2022-08-05 2023-02-01 mprovement (Work Space im ement and Implementation tions nvelope provement) BEST/GOODS/RFQ032 / PIMU Component 5: Project Manag Request for Quota Single Stage - One E TF / B2130 Post Open - National 22,654.45 22,654.45 Signed 2022-01-15 2022-07-28 2022-03-12 2022-02-22 2022-09-08 Office Refurbishment ement and Implementation tions nvelope 094/BEST/TL / RFQ to purcha Component 4: Data Driven P Request for Quota Single Stage - One E se 25 tablets for Master Train TF / B2130 lanning, Budgeting, Financin Post Open - National 17,500.00 0.00 Completed 2022-11-14 2022-12-27 2023-01-09 2023-07-08 2023-01-12 tions nvelope ers Training g and Implementation 101/BEST/TL / Purchase of e quipment for topography sur vey (Digital Theodolite) Total Station complete set with su Component 1: Developing 2 Request for Quota Single Stage - One E Pending Impl IDA / 65510 Post Open - National 7,500.00 0.00 2023-03-13 2023-05-08 2023-11-04 pporting stuffs: 1 unit of alu 1st Century Learning Spaces tions nvelope ementation minum tripod, 1 unit of leveli ng/reading staff (5 meter), 1- unit hardcase, and waterproo f protective cover NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 070/BEST/TL / A higher educ ation (University or Institute) to provide 36 junior engineer s for School Infrastructure da Component 1: Developing 2 Request for Quota Single Stage - One E IDA / 65510 Post Open - National 198,508.00 0.00 Canceled 2022-08-02 2022-09-27 2023-03-26 ta collection including perdie 1st Century Learning Spaces tions nvelope m and supervision managem ent; (Remuniration, Payment Perdiem,Comunication Fees, Rental of Equipment, Other O perational Se CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 006/BEST/TL / Consultant Fir m (Experts) for Quality assur Component 1: Developing 2 Consultant Qualifi Pending Impleme IDA / 65510 Post Open - National 175,000.00 0.00 2021-07-01 2021-07-22 2021-09-04 2021-10-04 2021-11-08 2022-05-07 ance of new construction and 1st Century Learning Spaces cation Selection ntation rehabilitation of school infras tructures 009/BEST/TL / A Firm to desi Component 3: Improving Te gn the implementation, analy Consultant Qualifi Open - Internationa Under Implement TF / B2130 aching-Learning Material an Post 400,000.00 0.00 2021-01-31 2022-10-04 2021-02-21 2023-01-17 2021-04-06 2021-05-06 2021-06-10 2021-12-07 sis and reporting of EGRA an cation Selection l ation d Assessment d EGMA and basic capacity b uilding (grades 1,2, 3) 061/BEST/TL / Consultant fir Component 5: Project Manag Consultant Qualifi Open - Internationa Under Implement TF / B2130 Post 42,000.00 0.00 2022-04-29 2023-03-06 2022-05-20 2023-06-15 2022-07-03 2022-08-02 2022-09-06 2023-03-05 m for External Auditors for B ement and Implementation cation Selection l ation EST Project 036/BEST/TL / Online system and training/orientation of sc Component 1: Developing 2 Consultant Qualifi Pending Impleme IDA / 65510 Post Open - National 45,000.00 0.00 2021-02-01 2021-02-22 2021-04-07 2021-05-07 2021-06-11 2021-12-08 hool infrastructure managem 1st Century Learning Spaces cation Selection ntation ent or module linked to EMIS (Component I) 047/BEST/TL / Consultant Fir Component 3: Improving Te m to design the implementat Consultant Qualifi Pending Impleme TF / B2130 aching-Learning Material an Post Open - National 350,000.00 0.00 2022-04-28 2022-05-19 2022-07-02 2022-08-01 2022-09-05 2023-03-04 ion, analysis and reporting of cation Selection ntation d Assessment EGRA and EGMA (grades 1,2, 3) 060/BEST/TL / Consultant Fir Component 1: Developing 2 Consultant Qualifi Pending Impleme m for school infrastructure su IDA / 65510 Post Open - National 328,385.00 0.00 2022-04-29 2022-05-20 2022-07-03 2022-08-02 2022-09-06 2023-03-05 1st Century Learning Spaces cation Selection ntation pervision and quality control 059/BEST/TL / Consultant Fir m for detailed engineering d Component 1: Developing 2 Quality And Cost- Pending Impleme IDA / 65510 Prior Open - National 900,000.00 0.00 2022-06-19 2022-07-10 2022-08-23 2022-09-20 2022-10-20 2022-11-24 2022-12-29 2023-12-29 esign, bidding document pre 1st Century Learning Spaces Based Selection ntation paration/Works and supervisi on. 034/BEST/TL / Implementati Component 1: Developing 2 Consultant Qualifi Open - Internationa on of school census includin IDA / 65510 Post 450,000.00 0.00 Canceled 2021-01-19 2022-01-20 2021-02-09 2022-07-11 2021-03-25 2022-04-24 2021-04-24 2021-05-29 2021-11-25 1st Century Learning Spaces cation Selection l g school infrastructure and E MIS census 005A/BEST/TL / A Firm for sy stem core development for t Component 4: Data Driven P he integrated for Sistema de Quality And Cost- Open - Internationa Pending Impleme TF / B2130 lanning, Budgeting, Financin Post 500,000.00 0.00 2022-12-01 2022-12-22 2023-02-04 2023-03-04 2023-04-03 2023-05-08 2023-06-12 2024-06-11 Gestao Escolar, PMIS and EMI Based Selection l ntation g and Implementation S and other data base syste m, software development/mo dification/testing/production 005/BEST/TL / A Firm for sys tem core development for th Component 4: Data Driven P e integrated for Sistema de G Quality And Cost- Open - Internationa TF / B2130 lanning, Budgeting, Financin Post 500,000.00 0.00 Canceled 2021-06-01 2021-12-13 2021-06-22 2021-08-05 2021-09-02 2021-10-02 2021-11-06 2022-02-01 2022-12-29 estao Escolar, PMIS and EMIS Based Selection l g and Implementation and other data base system, software development/modifi cation/testing/production 037-2023/BEST/TL / Consult ancy Services DED of School Infrastructure facilities (21st Component 1: Developing 2 Quality And Cost- Pending Impleme Century learning spaces), Re IDA / 65510 Post Open - National 824,315.00 0.00 2023-06-27 2023-07-18 2023-08-31 2023-09-28 2023-10-28 2023-12-02 2024-01-06 2025-01-05 1st Century Learning Spaces Based Selection ntation muneration Cost -Phase 1, R eimbursable -phase 1, Remu neration Cost -Phase 2, Reim bursable -phase 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 021/BEST/TL / Infrastructure Component 5: Project Manag Individual Consult Development Specialist of 21 IDA / 65510 Post Open 135,000.00 0.00 Canceled 2020-10-09 2020-11-09 2020-11-27 2020-12-18 2021-01-22 2023-07-21 ement and Implementation ant Selection st Century School standards 035/BEST/TL / Consultant for implementation of a school i Component 1: Developing 2 Individual Consult Under Implement nfrastucture survey of a smal IDA / 65510 Post Limited 18,000.00 0.00 2021-02-01 2021-11-04 2021-02-06 2021-02-27 2021-04-03 2021-09-30 1st Century Learning Spaces ant Selection ation l purposive sample of school to test the prioritazation guid elines 037/BEST/TL / Technical exp Component 2: Improving Te Individual Consult ert in education (curriculum, TF / B2130 Post Open 205,200.00 205,200.00 Terminated 2020-10-23 2021-11-11 2020-12-11 2021-12-03 2021-01-01 2022-01-14 2021-02-05 2022-01-29 2023-02-20 acher Effectiveness ant Selection training, school management ) 022/BEST/TL / TA for enhanci ng the reporting and dashbo ard facilities of the classroom Component 2: Improving Te Individual Consult Under Implement observation module to gener TF / B2130 Post Open 20,000.00 0.00 2021-08-02 2021-09-20 2021-10-11 2021-11-15 2022-05-14 acher Effectiveness ant Selection ation ate and display aggregate da ta on results of classroom ob servations by indicator, scho ol, cluster and municipal offic e 015/BEST/TL / Review and U Component 2: Improving Te Individual Consult Pending Impleme pgrade training materials for TF / B2130 Post Open 20,000.00 0.00 2020-12-15 2021-02-02 2021-02-23 2021-03-30 2021-09-26 acher Effectiveness ant Selection ntation school leaders training 016/BEST/TL / Upgrading/De Component 2: Improving Te Individual Consult Pending Impleme velop teacher training monit TF / B2130 Post Open 20,000.00 0.00 2021-01-01 2021-02-19 2021-03-12 2021-04-16 2021-10-13 acher Effectiveness ant Selection ntation oring/observation tool for INF ORDEPE 017/BEST/TL / Training obser Component 2: Improving Te Individual Consult Pending Impleme vation/evaluation report on t TF / B2130 Post Open 20,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 acher Effectiveness ant Selection ntation eachers training quality 011/BEST/TL / Curriculum sp Component 3: Improving Te ecialist for reviewing and qu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Limited 25,000.00 0.00 2021-01-29 2021-02-03 2021-02-24 2021-03-31 2021-09-27 ality checks for 3rd cycle boo ant Selection ntation d Assessment ks (language and social scien ces) 018/BEST/TL / Curriculum sp Component 3: Improving Te ecialist for reviewing and qu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Open 15,000.00 0.00 2021-01-29 2021-03-19 2021-04-09 2021-05-14 2021-11-10 ality assurance for 3rd cycle ant Selection ntation d Assessment TLM (natural sciences) 027/BEST/TL / Curriculum sp Component 3: Improving Te Individual Consult Pending Impleme ecialist for revision and qualit TF / B2130 aching-Learning Material an Post Open 15,000.00 0.00 2021-01-29 2021-03-19 2021-04-09 2021-05-14 2021-11-10 ant Selection ntation y assurance for 3rd cycle TL d Assessment M (mathematics) Page 2 007BEST/TL / A consultant to Component 3: Improving Te Individual Consult Pending Impleme develop Physical Education B TF / B2130 aching-Learning Material an Post Open 38,400.00 0.00 2020-11-13 2021-01-01 2021-01-22 2021-02-26 2022-02-25 ant Selection ntation ook and Manual for Grade 7 ( d Assessment Third Cycle) 020/BEST/TL / Financial Man Component 5: Project Manag Individual Consult TF / B2130 Post Open 151,200.00 151,200.00 Signed 2020-10-04 2020-11-09 2020-11-22 2022-06-03 2020-12-13 2022-06-03 2021-01-17 2021-10-28 2023-01-17 agement Specialist ement and Implementation ant Selection 023/BEST/TL / Procurement Component 5: Project Manag Individual Consult TF / B2130 Post Open 151,200.00 40,650.00 Terminated 2020-10-02 2020-11-09 2020-11-20 2021-10-13 2020-12-11 2021-10-25 2021-01-15 2021-10-19 2023-01-15 Specialist ement and Implementation ant Selection 013/BEST/TL / Environmenta Component 5: Project Manag Individual Consult TF / B2130 Post Open 124,200.00 124,200.00 Signed 2020-12-01 2020-11-09 2021-01-19 2022-01-11 2021-02-09 2021-10-18 2021-03-16 2021-10-28 2023-03-16 l and Social safeguard specia ement and Implementation ant Selection list 024/BEST/TL / M&E Specialis Component 5: Project Manag Individual Consult TF / B2130 Post Open 108,000.00 0.00 Canceled 2020-12-01 2020-11-09 2021-01-19 2021-02-09 2021-03-16 2023-03-16 t for PIMU ement and Implementation ant Selection 012/BEST/TL / ICT specialist Component 5: Project Manag Individual Consult TF / B2130 Post Open 118,000.00 118,000.00 Terminated 2020-10-29 2020-11-09 2020-12-17 2021-10-13 2021-01-07 2021-10-13 2021-02-11 2021-10-19 2023-02-10 for PIMU ement and Implementation ant Selection 032/BEST/TL / Administratio Component 5: Project Manag Individual Consult TF / B2130 Post Open 67,500.00 0.00 Canceled 2020-11-01 2020-11-09 2020-12-20 2021-01-10 2021-02-14 2023-02-14 n assistant to PIMU ement and Implementation ant Selection 008/BEST/TL / A consultant t o design a Paper based temp late for supporting the acquis Component 3: Improving Te ition, packaging, and distribu Individual Consult Pending Impleme TF / B2130 aching-Learning Material an Post Open 4,500.00 0.00 2021-02-01 2021-03-22 2021-04-12 2021-05-17 2021-08-31 tion of TLM, estimate the nu ant Selection ntation d Assessment mber of books to be printed each year, and provide the s chools with updates on the st atus on their TLM needs; 038/BEST/TL / A consultant t Component 3: Improving Te Individual Consult Pending Impleme o develop Art Book and Manu TF / B2130 aching-Learning Material an Post Open 38,400.00 0.00 2020-11-13 2021-01-01 2021-01-22 2021-02-26 2022-02-25 ant Selection ntation al for Grade 7th d Assessment 019/BEST/TL / Project manag Component 5: Project Manag Individual Consult TF / B2130 Prior Open 305,100.00 0.00 Canceled 2020-10-08 2020-11-15 2020-11-26 2020-12-17 2021-01-08 2023-01-08 er for PMIU ement and Implementation ant Selection BEST/INDV/005 / Monitoring Component 5: Project Manag Individual Consult IDA / 65510 Post Open 119,025.00 119,025.00 Signed 2021-10-15 2021-11-11 2021-11-17 2022-01-11 2021-12-08 2022-01-17 2022-01-12 2022-01-30 2024-07-10 and Evaluation Specialist ement and Implementation ant Selection BEST/INDV/001 / BEST Proje Component 5: Project Manag Individual Consult TF / B2130 Post Open 244,350.00 64,304.46 Signed 2021-10-15 2021-01-24 2021-12-03 2021-11-04 2021-12-24 2021-10-25 2022-01-28 2021-10-28 2022-07-27 ct Manager ement and Implementation ant Selection BEST/INDV/006 / Infrastructu Component 5: Project Manag Individual Consult TF / B2130 Post Open 180,675.00 180,675.00 Signed 2021-10-15 2021-11-11 2021-12-03 2022-05-14 2021-12-24 2022-01-16 2022-01-28 2022-01-30 2022-07-27 re Development Specialist ement and Implementation ant Selection BEST/INDV/008 / Administrat Component 5: Project Manag Individual Consult TF / B2130 Post Open 56,250.00 56,250.00 Signed 2021-11-15 2021-11-11 2021-12-10 2022-01-18 2021-12-13 2022-01-18 2021-12-14 2022-01-30 2022-12-30 ion Assistant to PIMU ement and Implementation ant Selection BEST/INDV/003 / Procureme Component 5: Project Manag Individual Consult TF / B2130 Post Open 126,000.00 126,000.00 Signed 2021-12-05 2021-11-25 2022-01-23 2022-02-28 2022-02-13 2022-03-04 2022-03-20 2022-03-19 2022-09-16 nt Specialist (National) ement and Implementation ant Selection 025/BEST/TL / Architect to pr Component 1: Developing 2 Individual Consult Under Implement oduce standardized designs IDA / 65510 Post Open 30,000.00 0.00 2020-12-02 2022-05-18 2021-01-20 2021-02-10 2021-03-17 2021-09-13 1st Century Learning Spaces ant Selection ation and infrastructure standards 014/BEST/TL / Quality assura nce consultant for reviewing Component 4: Data Driven P Individual Consult Pending Impleme designing and development TF / B2130 lanning, Budgeting, Financin Post Open 15,000.00 0.00 2021-11-01 2021-12-20 2022-01-10 2022-02-14 2022-08-13 ant Selection ntation of system for infrastructure c g and Implementation omponent in EMIS (in 2020 a nd 2021) 010/BEST/TL / Technical Spe cialist to support the develop ment and finalization of the p Component 1: Developing 2 Individual Consult Pending Impleme IDA / 65510 Post Open 20,000.00 0.00 2020-10-30 2020-12-18 2021-01-08 2021-02-12 2021-08-11 rioritization methodology , pr 1st Century Learning Spaces ant Selection ntation eparation of prioritization pla n including priority list for sc hool construction 043/BEST/TL / Technical Assi stance to update school lead Component 2: Improving Te Individual Consult TF / B2130 Post Open 17,500.00 0.00 Signed 2022-05-08 2022-06-26 2022-06-26 2022-09-14 2022-07-17 2022-12-22 2022-08-21 2023-02-17 ers training package, develo acher Effectiveness ant Selection ping of training materials (inc luding the use experts) 039/BEST/TL / Technical Assi stance for school infrastructu Component 1: Developing 2 Individual Consult Under Implement IDA / 65510 Post Open 27,000.00 0.00 2022-04-28 2022-06-23 2022-06-16 2022-06-21 2022-07-07 2022-08-11 2023-02-07 re planning and prioritization 1st Century Learning Spaces ant Selection ation guideline development and t esting Component 3: Improving Te 045/BEST/TL / Specialist in b Individual Consult TF / B2130 aching-Learning Material an Post Open 60,000.00 51,180.00 Signed 2022-04-28 2022-06-10 2022-06-16 2022-08-23 2022-07-07 2022-08-20 2022-08-11 2022-09-02 2023-02-07 asic Education Curriculum ant Selection d Assessment 072/BEST/TL / An Internation Component 1: Developing 2 Individual Consult Open - Internationa IDA / 65510 Post 63,750.00 39,869.30 Completed 2022-07-25 2022-07-29 2022-09-12 2022-09-12 2022-10-03 2022-09-24 2022-11-07 2022-10-08 2023-05-06 2022-11-21 al Team Leader for School Ce 1st Century Learning Spaces ant Selection l nsus 073/BEST/TL / Local Technic al Consultant 1 Person (Exp ert for Design the instrument Component 1: Developing 2 Individual Consult /Questionnaire Format and T IDA / 65510 Post Open - National 22,000.00 20,730.00 Signed 2022-07-25 2022-07-29 2022-09-12 2022-09-26 2022-10-03 2022-09-14 2022-11-07 2022-09-26 2023-05-06 1st Century Learning Spaces ant Selection abulation) duration of the co ntract 4 months ( estamate $ 4,400/month incluiding Tax 1 0%) Prepare Questionnaire F orm 074/BEST/TL / TA to develop an application (Kobo Toolbox Component 1: Developing 2 Direct - Internation Under Implement IDA / 65510 Post Direct Selection 11,928.00 0.00 2022-10-28 2022-10-28 2022-11-07 2022-11-06 2023-01-11 2023-07-10 or Cs-Pro) to support School 1st Century Learning Spaces al ation Census Data Collection Proce ss 086/BEST/TL / ICT Specialist Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open - National 73,352.00 0.00 2022-10-13 2022-09-29 2022-12-01 2022-12-22 2023-01-26 2023-07-25 for BEST Project ement and Implementation ant Selection ation 044/BEST/TL / Technical Assi stance to develop or upgrade Component 2: Improving Te Individual Consult TF / B2130 Post Open 20,250.00 0.00 Canceled 2022-04-28 2022-06-28 2022-06-16 2022-07-07 2022-08-11 2023-02-07 teacher training monitoring/ acher Effectiveness ant Selection Observation Tool and module Page 3 087/BEST/TL / Procurement Component 5: Project Manag Individual Consult Under Implement Officer to Support BEST PIMU TF / B2130 Post Open - National 64,500.00 0.00 2022-12-06 2023-04-13 2023-01-24 2023-02-14 2023-03-21 2023-09-17 ement and Implementation ant Selection ation with procurement related act ivities 098/BEST/TL / LM -Tracking Component 3: Improving Te System Development to supp Individual Consult Under Implement TF / B2130 aching-Learning Material an Post Open - National 20,000.00 0.00 2022-12-09 2022-12-02 2023-01-30 2023-02-20 2023-03-27 2023-09-23 ort the acquisition, packagin ant Selection ation d Assessment g, and distribution of TLM; es timate Component 4: Data Driven P 095/BEST/TL / TA- EMIS Dev Individual Consult Open - Internationa Pending Impleme TF / B2130 lanning, Budgeting, Financin Post 39,000.00 0.00 2022-12-26 2023-02-13 2023-03-06 2023-04-10 2023-10-07 elopment Assessment ant Selection l ntation g and Implementation 072A/BEST/TL / International Component 4: Data Driven P Individual Consult Open - Internationa Under Implement position School Census Team TF / B2130 lanning, Budgeting, Financin Post 58,000.00 0.00 2023-01-05 2022-12-03 2023-02-23 2023-03-16 2023-04-20 2023-10-17 ant Selection l ation Leader g and Implementation Component 4: Data Driven P 099/BEST/TL / ICT EMIS Deve Individual Consult Open - Internationa Under Implement TF / B2130 lanning, Budgeting, Financin Post 38,000.00 0.00 2023-01-05 2023-01-26 2023-02-23 2023-06-05 2023-03-16 2023-06-20 2023-04-20 2023-10-17 lopment Analyst ant Selection l ation g and Implementation 082/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Maliana Municipa 1st Century Learning Spaces ant Selection lity 083/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Oecussi Municipa 1st Century Learning Spaces ant Selection lity 078/BEST/TL / Polo Bases Su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-17 2022-07-29 2022-09-04 2022-09-25 2022-10-30 2023-04-28 pervisor for Dili Municipality 1st Century Learning Spaces ant Selection 069/BEST/TL / Polo-based su Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 pervisor for Manufahi Munici 1st Century Learning Spaces ant Selection pality 080/BEST/TL / Polo Bases Su pervisor for Baucau Municip Component 1: Developing 2 Individual Consult IDA / 65510 Post Open - National 2,250.00 0.00 Canceled 2022-07-25 2022-07-29 2022-09-12 2022-10-03 2022-11-07 2023-05-06 ality (duration of Contract 3 1st Century Learning Spaces ant Selection months $ 750/month) 037A/BEST/TL / Technical ex pert in education (curriculum Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open - National 87,200.00 0.00 2023-01-10 2023-02-07 2023-02-28 2023-03-21 2023-04-25 2023-10-22 , training, school manageme ement and Implementation ant Selection ation nt) 28 months Contract 028/BEST/TL / Independent v Component 2: Improving Te Individual Consult Under Implement TF / B2130 Post Open - National 15,000.00 0.00 2021-06-30 2023-05-17 2021-08-18 2021-09-08 2021-10-13 2022-04-11 erification of DLI achievemen acher Effectiveness ant Selection ation ts 026-2023/IDV/BEST/TL / Proj Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 115,000.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-05-03 2023-07-26 2024-01-22 ect Manager ement and Implementation ation 025-2023/IDV/BEST/TL / Proc Component 5: Project Manag Pending Impleme TF / B2130 Post Direct Selection Direct - National 88,500.00 0.00 2023-05-12 2023-05-22 2023-07-26 2024-01-22 urement Specialist ement and Implementation ntation 030-2023/IDV/BEST/TL / Envi Component 5: Project Manag Under Implement ronmental and Social Safegu TF / B2130 Post Direct Selection Direct - National 50,600.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-07-26 2024-01-22 ement and Implementation ation ard Specialist (ESSS) 028-2023/IDV/BEST/TL / Edu Component 4: Data Driven P Under Implement cation Infrastructure Plannin TF / B2130 lanning, Budgeting, Financin Post Direct Selection Direct - National 81,000.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-07-26 2024-01-22 ation g and Project Management S g and Implementation pecialist-National 029-2023/IDV/BEST/TL / Mon Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 52,000.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-07-26 2024-01-22 itoring and Evaluation Specia ement and Implementation ation list 027-2023/IDV/BEST/TL / Ad Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 23,500.00 0.00 2023-05-12 2023-05-03 2023-05-22 2023-05-03 2023-07-26 2024-01-22 ministration Assistant ement and Implementation ation 034-2023/IDV/BEST/TL / Inte Component 5: Project Manag Individual Consult Open - Internationa Under Implement rnational Project Managemen TF / B2130 Post 227,500.00 0.00 2023-05-12 2023-06-01 2023-06-30 2023-07-21 2023-08-25 2024-02-21 ement and Implementation ant Selection l ation t Consultant 031-2023/IDV/BEST/TL / Fina Component 5: Project Manag Individual Consult Under Implement TF / B2130 Post Open - National 58,500.00 0.00 2023-05-23 2023-06-01 2023-07-11 2023-08-01 2023-09-05 2024-03-03 nce Management Specialist ement and Implementation ant Selection ation Strengthening Forest Manag 035-2023/INDV/BEST/TL / Fin Under Implement TF / B2130 ement, Conservation, and B Post Direct Selection Direct - National 33,020.00 0.00 2023-05-23 2023-05-03 2023-06-02 2023-05-03 2023-08-06 2024-02-02 ance Officer ation usiness Development 036-2023/INDV/BEST/TL / Na Component 5: Project Manag Under Implement TF / B2130 Post Direct Selection Direct - National 63,600.00 0.00 2023-05-23 2023-05-03 2023-06-02 2023-08-06 2024-02-02 tional Project Management C ement and Implementation ation onsultant Page 4 PROCUREMENT PLAN (Textual Part) Project information: Country: Ukraine Project name: JSDF: Community-based Social Service Delivery (CSSD) Project Project №: P165346 Project Implementation agency: Ukrainian Social Investment Fund (USIF) Date of the Procurement Plan: April, 2018 Period covered by this Procurement Plan: June 2018 - May 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitutes the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in USIF Operational Manual, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: not applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: not applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: not applicable; Works: not applicable. Other Relevant Procurement Information. None. PROCUREMENT Ukraine : JSDF: Community-based Social Service Delivery Project PLAN General Information Country: Ukraine 2019-02-04 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165346 GPN Date: 2018-11-13 Project Name: JSDF: Community-based Social Service Delivery Project Loan / Credit No: TF / A8367 Ukrainian Social Investment Fund Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - UA-USIF-235516-CW-RFB / C Social Protection Services Mi Single Stage - One E Small Works SPD 2022-01-1 onstruction works within the TF / A8367 Post Request for Bids Open - National 75,100.00 0.00 Canceled 2021-05-21 2021-05-24 2021-05-26 2021-05-24 2021-06-25 2021-06-25 2021-07-05 2021-07-21 cro-projects nvelope (1 envelope proce 7 micro-project 18-61-03. Poch ss) aiv Request for Bids - UA-USIF-235573-CW-RFB / C Social Protection Services Mi Single Stage - One E Small Works SPD 2022-01-1 onstruction works within the TF / A8367 Post Request for Bids Open - National 108,200.00 0.00 Canceled 2021-05-21 2021-05-24 2021-05-26 2021-05-24 2021-06-25 2021-06-25 2021-07-05 2021-07-21 cro-projects nvelope (1 envelope proce 7 micro-project 18-61-04. Vysh ss) nivets Request for Bids - UA-USIF-236541-CW-RFB / C Social Protection Services Mi Single Stage - One E Small Works SPD 2022-02-2 onstruction works within the TF / A8367 Post Request for Bids Open - National 60,000.00 60,801.02 Completed 2021-05-27 2021-06-01 2021-06-01 2021-06-01 2021-07-01 2021-07-01 2021-07-09 2021-07-09 2021-07-26 2021-08-20 cro-projects nvelope (1 envelope proce 1 micro-project 18-51-09. Troyi ss) tsʹke Request for Bids - UA-USIF-238131-CW-RFB / C Social Protection Services Mi Single Stage - One E Small Works SPD 2022-03-2 onstruction works within the TF / A8367 Post Request for Bids Open - National 84,400.00 91,774.38 Signed 2021-06-04 2021-06-07 2021-06-08 2021-06-14 2021-07-08 2021-07-07 2021-07-15 2021-07-20 2021-07-31 2021-08-17 cro-projects nvelope (1 envelope proce 1 micro-project 18-51-06. Bilya ss) yivka Request for Bids - UA-USIF-238134-CW-RFB / C Social Protection Services Mi Single Stage - One E Small Works SPD 2022-03-2 onstruction works within the TF / A8367 Post Request for Bids Open - National 88,340.00 90,638.37 Completed 2021-06-04 2021-06-07 2021-06-08 2021-06-14 2021-07-08 2021-07-07 2021-07-15 2021-07-20 2021-07-31 2021-08-26 cro-projects nvelope (1 envelope proce 1 micro-project 18-61-01. Bors ss) hchiv Request for Bids - UA-USIF-239042-CW-RFB / C Social Protection Services Mi Single Stage - One E Small Works SPD 2022-03-2 onstruction works within the TF / A8367 Post Request for Bids Open - National 62,000.00 64,280.64 Signed 2021-06-10 2021-06-14 2021-06-15 2021-06-14 2021-07-15 2021-07-14 2021-07-22 2021-07-20 2021-08-07 2021-08-17 cro-projects nvelope (1 envelope proce 1 micro-project 18-51-10. Balta ss) Request for Bids - UA-USIF-239046-CW-RFB / C Social Protection Services Mi Single Stage - One E Small Works SPD 2022-03-2 onstruction works within the TF / A8367 Post Request for Bids Open - National 99,125.00 101,490.74 Signed 2021-06-10 2021-06-14 2021-06-15 2021-06-14 2021-07-15 2021-07-14 2021-07-22 2021-07-20 2021-08-07 2021-08-17 cro-projects nvelope (1 envelope proce 1 micro-project 18-61-05 .Zbori ss) v Request for Bids - UA-USIF-243730-CW-RFB / 2. Social Protection Services Mi Single Stage - One E Small Works SPD 2022-03-1 9/1 - Construction works with TF / A8367 Post Request for Bids Open - National 116,500.00 117,710.71 Signed 2021-07-15 2021-07-22 2021-07-20 2021-07-22 2021-08-19 2021-08-22 2021-08-26 2021-08-27 2021-09-11 2021-09-22 cro-projects nvelope (1 envelope proce 0 in the micro-project 18-51-08 ss) . Konoplyane UA-USIF-245754-CW-RFB / 2. Request for Bids - 8/1 Construction works withi Social Protection Services Mi Single Stage - One E Small Works SPD 2022-03-1 n the micro-project 18-51-07. TF / A8367 Post Request for Bids Open - National 81,500.00 83,375.29 Signed 2021-07-27 2021-07-28 2021-07-29 2021-07-28 2021-08-28 2021-08-30 2021-09-04 2021-09-16 2021-09-20 2021-10-06 cro-projects nvelope (1 envelope proce 9 Vylkovo: сonstruction works. ss) Desantne, Myrne,Vylkovo Request for Bids - UA-USIF-246393-CW-RFB / 2. Social Protection Services Mi Single Stage - One E Small Works SPD 2022-03-2 4/5 - Construction works with TF / A8367 Post Request for Bids Open - National 75,100.00 77,584.37 Signed 2021-08-02 2021-08-03 2021-08-07 2021-08-04 2021-09-06 2021-09-03 2021-09-13 2021-09-21 2021-09-29 2021-10-16 cro-projects nvelope (1 envelope proce 8 in the micro-project 18-61-03 ss) . Pochaiv Request for Bids - UA-USIF-246394-CW-RFB / 2. Social Protection Services Mi Single Stage - One E Small Works SPD 2022-03-2 5/2 - Construction works with TF / A8367 Post Request for Bids Open - National 108,200.00 112,398.75 Signed 2021-08-02 2021-08-03 2021-08-07 2021-08-04 2021-09-06 2021-09-03 2021-09-13 2021-09-21 2021-09-29 2021-10-07 cro-projects nvelope (1 envelope proce 8 in the micro-project 18-61-04 ss) . Vyshnivets UA-USIF-320988-CW-DIR / C Social Protection Services Mi Other (with field f 2023-05-0 onstruction works within the TF / A8367 Post Direct Selection Direct - National 113,500.00 0.00 Signed 2022-10-17 2022-10-19 2022-10-21 2022-10-19 2022-10-24 cro-projects or explanation) 3 micro-project 18-61-02. Skal a-Podilska UA-USIF-368302-CW-DIR / Pe rformance of the small-value Social Protection Services Mi Other (with field f Under Imple 2023-09-0 TF / A8367 Post Direct Selection Direct - National 2,000.00 0.00 2023-06-23 2023-06-27 2023-06-28 2023-07-03 construction works within the cro-projects or explanation) mentation 1 micro-project 18-61-04. Vysh nivets GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UA-USIF-130173-GO-RFQ / 1. Development of Social Prote Request for Quota Single Stage - One E TF / A8367 Post Limited 100,000.00 111,452.00 Completed 2019-09-08 2019-09-06 2019-11-03 2019-11-28 2020-05-01 2020-03-01 4/1 - Оffice and computer eq ction Services Delivery Capa tions nvelope uipment city UA-USIF-206306-GO-RFQ / 2. Social Protection Services Mi Request for Quota Single Stage - One E 4/1 Оffice and computer equi TF / A8367 Post Open - National 13,200.00 12,667.12 Completed 2020-11-30 2021-01-20 2020-12-17 2021-02-20 2021-01-18 2021-03-26 cro-projects tions nvelope pment for Pochaiv communit y UA-USIF-206309-GO-RFQ / 2. Social Protection Services Mi Request for Quota Single Stage - One E TF / A8367 Post Open - National 7,000.00 0.00 Canceled 2020-11-30 2020-12-29 2020-12-17 2021-01-18 4/2- furniture for Pochaiv co cro-projects tions nvelope mmunity UA-USIF-211332-GO-RFQ / Bi Development of Social Prote Request for Quota Single Stage - One E TF / A8367 Post Open - National 70,000.00 60,358.37 Completed 2020-12-24 2021-01-13 2021-01-30 2021-02-20 2021-03-31 2021-04-23 cycles for Social Protection te ction Services Delivery Capa tions nvelope ams city UA-USIF-217802-GO-RFQ / 1. Development of Social Prote Request for Quota Single Stage - One E TF / A8367 Post Open - National 61,000.00 53,798.12 Completed 2021-02-10 2021-02-05 2021-03-21 2021-04-22 2021-05-20 2021-05-29 4/3 Scooters for Social Protec ction Services Delivery Capa tions nvelope tion teams city UA-USIF-219683-GO-RFQ / 2. Social Protection Services Mi Request for Quota Single Stage - One E 4/3 Furniture for the Pochaiv TF / A8367 Post Open - National 7,000.00 0.00 Canceled 2021-02-19 2021-03-30 2021-04-29 cro-projects tions nvelope community UA-USIF-221495-GO-RFQ / F Social Protection Services Mi Request for Quota Single Stage - One E TF / A8367 Post Open - National 7,000.00 6,136.42 Completed 2021-02-28 2021-03-04 2021-04-09 2021-04-08 2021-05-09 2021-05-07 urniture for the Pochaiv com cro-projects tions nvelope munity UA-USIF-235494-GO-RFQ / F Social Protection Services Mi Request for Quota Single Stage - One E urniture and equipment for Z TF / A8367 Post Open - National 13,700.00 15,860.53 Completed 2021-05-26 2021-05-24 2021-06-30 2021-08-03 2021-07-30 2021-10-27 cro-projects tions nvelope boriv community-Microprojec t 18-61-05 Page 1 UA-USIF-236531-GO-RFQ / F Social Protection Services Mi Request for Quota Single Stage - One E urniture and safe within the TF / A8367 Post Open - National 2,000.00 2,665.95 Completed 2021-06-01 2021-06-01 2021-07-07 2021-08-17 2021-08-06 2021-09-16 cro-projects tions nvelope micro-project 18-51-09. Troyi tsʹke UA-USIF-241912-GO-RFQ / 1. Development of Social Prote Request for Quota Single Stage - One E TF / A8367 Post Open - National 70,000.00 70,361.25 Completed 2021-07-12 2021-07-12 2021-08-20 2021-09-02 2021-10-19 2021-10-30 4/4 Furniture for social prote ction Services Delivery Capa tions nvelope ction units city UA-USIF-264436-GO-RFQ / 2. Social Protection Services Mi Request for Quota Single Stage - One E 3/1 Furniture and Equipment TF / A8367 Post Open - National 10,800.00 12,070.48 Completed 2021-11-30 2021-12-14 2022-01-02 2022-01-25 2022-03-03 2022-02-19 cro-projects tions nvelope for Skala-Podilska. Microproje ct 18-61-02 UA-USIF-270903-GO-RFQ / 2. 4/5- Office and special equip Social Protection Services Mi Request for Quota Single Stage - One E TF / A8367 Post Open - National 30,636.00 0.00 Canceled 2022-01-17 2022-01-10 2022-03-17 2022-05-16 ment within the micro-projec cro-projects tions nvelope t 18-61-03. Pochaiv UA-USIF-271937-GO-RFQ / 2. Social Protection Services Mi Request for Quota Single Stage - One E 4/6-Furniture and safe within TF / A8367 Post Open - National 10,537.00 5,633.19 Completed 2022-01-17 2022-01-10 2022-03-17 2022-04-01 2022-05-16 2022-08-16 cro-projects tions nvelope the micro-project 18-61-03. P ochaiv UA-USIF-279468-GO-RFQ / 2. Social Protection Services Mi Request for Quota Single Stage - One E 5/2-Furniture within micro-pr TF / A8367 Post Open - National 18,800.00 14,174.00 Completed 2022-02-22 2022-02-23 2022-04-10 2022-04-07 2022-05-10 2022-05-14 cro-projects tions nvelope oject 18-61-04. Vyshnivets UA-USIF-279472-GO-RFQ / 2. 5/3- Office and special equip Social Protection Services Mi Request for Quota Single Stage - One E TF / A8367 Post Open - National 11,000.00 0.00 Canceled 2022-02-22 2022-02-23 2022-04-10 2022-05-10 ment within the micro-projec cro-projects tions nvelope t 18-61-04. Vyshnivets UA-USIF-279479-GO-RFQ / 2. Social Protection Services Mi Request for Quota Single Stage - One E 10/4-Equipment within the m TF / A8367 Post Open - National 33,500.00 0.00 Canceled 2022-02-22 2022-02-23 2022-04-10 2022-05-10 cro-projects tions nvelope icro-project 18-51-09. Troyits ʹke UA-USIF-297107-GO-DIR / 1. Development of Social Prote 4/5-Supply of lifts for the disa TF / A8367 ction Services Delivery Capa Post Direct Selection Direct 13,900.00 13,751.66 Completed 2022-05-27 2022-05-27 2022-05-31 2022-05-31 2022-06-01 2022-06-11 2022-09-14 2022-08-26 bled. Skala-Podilska site city UA-USIF-298065-GO-DIR / Eq uipment and tools for creativ Social Protection Services Mi TF / A8367 Post Direct Selection Direct 1,414.00 1,399.87 Completed 2022-06-03 2022-06-08 2022-06-06 2022-06-08 2022-06-07 2022-06-09 2022-08-06 2022-06-09 e workshop within the micro- cro-projects project 18-61-04. Vyshnivets UA-USIF-298069-GO-DIR / H Social Protection Services Mi ousehold equipment within t TF / A8367 Post Direct Selection Direct 2,849.00 2,820.45 Completed 2022-06-03 2022-06-08 2022-06-06 2022-06-08 2022-06-07 2022-06-09 2022-08-06 2022-06-15 cro-projects he micro-project 18-51-09. Tr oyitsʹke UA-USIF-315158-GO-DIR / D Development of Social Prote TF / A8367 Post Direct Selection Direct - National 6,650.00 6,570.80 Completed 2022-09-09 2022-09-09 2022-09-15 2022-09-14 2022-09-16 2022-09-24 2022-10-28 2022-12-31 elivery of handouts with logo ction Services Delivery Capa s city UA-USIF-325902-GO-RFQ / F Development of Social Prote Request for Quota Single Stage - One E urniture for six communities TF / A8367 ction Services Delivery Capa Post Open - National 27,800.00 0.00 Signed 2022-11-17 2022-11-10 2022-12-23 2023-03-01 tions nvelope of Ternopil and Odesa region city s UA-USIF-332554-GO-RFQ / O ffice and interactive equipme Social Protection Services Mi Request for Quota Single Stage - One E TF / A8367 Post Open - National 157,500.00 0.00 Signed 2022-12-25 2022-12-21 2023-02-13 2023-04-30 nt for 10 communities of Ode cro-projects tions nvelope sa and Ternopil regions UA-USIF-333584-GO-RFQ / E ducational games and toys. T Social Protection Services Mi Request for Quota Single Stage - One E ools of speech therapist, psy TF / A8367 Post Open - National 16,500.00 0.00 Signed 2022-12-28 2023-01-12 2023-02-26 2023-03-28 cro-projects tions nvelope chologist office for 10 comm unities of Ternopil and Odesa regions UA-USIF-342898-GO-DIR / Es timated Contract Value: 4000 Social Protection Services Mi TF / A8367 Post Direct Selection Direct - National 4,000.00 0.00 Signed 2023-02-15 2023-02-15 2023-02-20 2023-02-21 2023-03-27 2023-06-25 $ cro-projects Description of Proposed Cont ract: delivery of furniture UA-USIF-343341-GO-RFQ / S Social Protection Services Mi Request for Quota Single Stage - One E ports equipment within the TF / A8367 Post Open - National 50,000.00 0.00 Signed 2023-02-27 2023-02-20 2023-04-10 2023-05-10 cro-projects tions nvelope micro-projects UA-USIF-346743-GO-RFQ / R Social Protection Services Mi Request for Quota Single Stage - One E ehabilitation equipment withi TF / A8367 Post Open - National 65,175.00 0.00 Signed 2023-03-11 2023-03-06 2023-05-06 2023-07-05 cro-projects tions nvelope n the micro-projects UA-USIF-352794-GO-DIR / Pr Project Management and Ad oduction and delivery of infor ministration, Monitoring and TF / A8367 Post Direct Selection Direct - National 1,400.00 0.00 Signed 2023-03-28 2023-03-28 2023-04-03 2023-04-14 2023-04-07 2023-05-07 mation signs (Name of the p Evaluation, and Knowledge roject and executors) Dissemination UA-USIF-357071-GO-DIR / Pr Project Management and Ad oduction and delivery of boo TF / A8367 ministration, Monitoring and Post Direct Selection Direct - National 973.00 0.00 Signed 2023-04-18 2023-04-18 2023-04-23 2023-04-24 2023-05-08 2023-06-07 klets Evaluation, and Knowledge Dissemination UA-USIF-359867-GO-RFQ / S Social Protection Services Mi Request for Quota Single Stage - One E TF / A8367 Post Limited 31,750.00 0.00 Completed 2023-05-10 2023-05-11 2023-05-17 2023-06-16 2023-06-10 upply of sports equipment cro-projects tions nvelope UA-USIF-360334-GO-DIR / Su Development of Social Prote TF / A8367 Post Direct Selection Direct - National 49,800.00 0.00 Signed 2023-05-09 2023-05-11 2023-05-12 2023-05-15 2023-05-16 2023-07-15 pply of office and electronic ction Services Delivery Capa equipment city UA-USIF-360583-GO-RFQ / P Development of Social Prote Request for Quota Single Stage - One E TF / A8367 Post Open - National 7,650.00 0.00 Signed 2023-05-10 2023-05-22 2023-06-21 urchase of televisions ction Services Delivery Capa tions nvelope city UA-USIF-362311-GO-RFQ / S Social Protection Services Mi Request for Quota Single Stage - One E TF / A8367 Post Open - National 6,050.00 0.00 Signed 2023-06-02 2023-07-20 2023-08-19 ewing equipment cro-projects tions nvelope UA-USIF-362316-GO-DIR / Su Social Protection Services Mi pply of professional kitchen e TF / A8367 Post Direct Selection Direct - National 25,050.00 0.00 Signed 2023-05-19 2023-05-19 2023-05-24 2023-05-22 2023-06-08 2023-07-13 cro-projects quipment and furniture UA-USIF-368258-GO-DIR / Su Social Protection Services Mi Under Imple pply of the roller shutters wit TF / A8367 Post Direct Selection Direct - National 641.00 0.00 2023-06-23 2023-06-27 2023-06-28 2023-07-03 2023-08-02 cro-projects mentation hin microproject 18-61-03. P ochaiv UA-USIF-368273-GO-DIR / Su Social Protection Services Mi Under Imple pply of the air conditioner wit TF / A8367 Post Direct Selection Direct - National 1,299.00 0.00 2023-06-23 2023-06-27 2023-06-28 2023-07-03 2023-08-02 cro-projects mentation hin microproject 18-61-03. P ochaiv Page 2 UA-USIF-368286-GO-DIR / Su Social Protection Services Mi Under Imple pply of the window grilles wit TF / A8367 Post Direct Selection Direct - National 875.00 0.00 2023-06-23 2023-06-27 2023-06-28 2023-07-03 2023-08-02 cro-projects mentation hin microproject 18-61-03. P ochaiv UA-USIF-368297-GO-DIR / Su pply of the benches, urns, an Social Protection Services Mi Under Imple TF / A8367 Post Direct Selection Direct - National 845.00 0.00 2023-06-23 2023-06-27 2023-06-28 2023-07-03 2023-08-02 d decorative street elements cro-projects mentation within the microproject 18-51 -10. Balta NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UA-USIF-87362-NC-RFQ / №2 Social Protection Services Mi Request for Quota Single Stage - One E .1. Preparation of designs for TF / A8367 Post Open - National 110,000.00 0.00 Canceled 2019-07-11 2019-09-19 2021-03-01 cro-projects tions nvelope minor civil works UA-USIF-87376-NC-DIR / №2. Social Protection Services Mi TF / A8367 Post Direct Selection Direct 62,000.00 0.00 Canceled 2018-11-16 2018-11-21 2018-12-26 2022-03-20 14. Local operating costs cro-projects Project Management and Ad UA-USIF-87392-NC-DIR / №3. TF / A8367 ministration, Monitoring and Post Direct Selection Direct 28,000.00 0.00 Canceled 2018-11-16 2018-11-21 2018-12-26 2022-05-01 8. Operating costs Evaluation, and Knowledge Dissemination UA-USIF-139107-NC-APA / 1. Development of Social Prote 3/2 - organizing and providin Request for Quota Single Stage - One E TF / A8367 ction Services Delivery Capa Post Limited 40,000.00 0.00 Canceled 2019-10-22 2019-10-22 2019-11-06 2019-12-23 g support of trainings for am tions nvelope city algamated communities to pr epare applications UA-USIF-145123-NC-RFQ / 1. Development of Social Prote 3/3 «Organization and provisi Request for Quota Single Stage - One E TF / A8367 ction Services Delivery Capa Post Limited 40,000.00 23,685.60 Completed 2019-11-13 2019-11-13 2019-11-22 2019-11-21 2020-02-01 2019-12-10 on of logistical support for tra tions nvelope city ining applications for united communities» UA-USIF-315153-NC-DIR / Or ganization and provision of m Development of Social Prote aterial and technical support TF / A8367 ction Services Delivery Capa Post Direct Selection Direct - National 47,000.00 43,540.95 Completed 2022-09-09 2022-09-09 2022-09-15 2022-09-14 2022-09-19 2022-09-24 2022-11-23 2022-12-12 offline training seminars for c city ommunities implementing mi cro-projects (Odesa and Ter nopil regions). Project Management and Ad UA-USIF-368304-NC-RFP / Ed Request for Quota Single Stage - One E Under Imple TF / A8367 ministration, Monitoring and Post Open - National 21,000.00 0.00 2023-06-30 2023-07-13 2023-09-29 ucational video production tions nvelope mentation Evaluation, and Knowledge Dissemination CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UA-USIF-87174-CS-CQS / №1 Development of Social Prote Consultant Qualifi .1. Technical assistance to co TF / A8367 ction Services Delivery Capa Post Open - National 100,000.00 0.00 Canceled 2018-11-14 2018-11-28 2018-12-19 2019-01-02 2019-02-06 2019-08-05 cation Selection mmunities of Ternopil oblast city UA-USIF-87176-CS-CQS / №1 Development of Social Prote Consultant Qualifi .2. Technical assistance to co TF / A8367 ction Services Delivery Capa Post Open - National 80,000.00 0.00 Canceled 2018-11-14 2018-11-28 2018-12-19 2019-01-02 2019-02-06 2019-08-05 cation Selection mmunities of Odesa oblast city UA-USIF-87388-CS-CQS / №3 Project Management and Ad .1. Baseline, midterm and fin ministration, Monitoring and Consultant Qualifi TF / A8367 Post Open - National 50,000.00 0.00 Canceled 2018-11-16 2018-11-30 2018-12-28 2019-01-11 2019-02-01 2022-04-03 al evaluation surveys (local c Evaluation, and Knowledge cation Selection onsultant specialized in socia Dissemination l research) UA-USIF-111904-CS-CQS / № Development of Social Prote Consultant Qualifi 1.1. Technical assistnace to c TF / A8367 ction Services Delivery Capa Post Open - National 100,000.00 99,170.00 Completed 2019-04-25 2019-04-15 2019-05-01 2019-05-01 2019-06-04 2019-05-19 2019-06-19 2019-06-23 2019-06-19 2019-12-20 2020-03-01 cation Selection ommunities of Ternopil oblas city t UA-USIF-111907-CS-CQS / № Development of Social Prote Consultant Qualifi 1.2. Technical assistnace to c TF / A8367 ction Services Delivery Capa Post Open - National 80,000.00 23,995.50 Completed 2019-04-25 2019-04-15 2019-05-01 2019-05-01 2019-06-05 2019-05-19 2019-06-21 2019-06-13 2019-06-21 2019-12-10 2020-03-01 cation Selection ommunities of Odesa oblast city UA-USIF-123453-CS-CQS / 3. Project Management and Ad 1./1 Baseline evaluation surv ministration, Monitoring and Consultant Qualifi TF / A8367 Post Open - National 20,000.00 20,000.00 Completed 2019-07-18 2019-07-18 2019-08-08 2019-09-11 2019-09-06 2019-10-11 2019-09-18 2019-11-15 2019-09-18 2020-05-13 2020-01-24 eys (local consultant speciali Evaluation, and Knowledge cation Selection zed in social research) Dissemination UA-USIF-154573-CS-LCS / 3. Project Management and Ad Least Cost Selecti 7/1 Annual financial audits (i TF / A8367 ministration, Monitoring and Post Open - National 17,500.00 7,315.05 Completed 2020-01-23 2020-02-04 2020-01-30 2020-01-31 2020-02-11 2020-02-28 2020-03-10 2020-03-13 2020-03-12 2020-03-27 2020-04-01 2020-04-14 2020-04-16 2020-05-15 2020-05-15 on ncluding procurement issues) Evaluation, and Knowledge for 2019 Dissemination UA-USIF-189461-CS-CQS / S ervices for the preparation of Social Protection Services Mi Consultant Qualifi design and estimate docume TF / A8367 Post Open - National 73,500.00 67,580.79 Signed 2020-08-28 2020-08-28 2020-09-18 2020-09-25 2020-09-30 2020-10-19 2020-12-01 2020-10-23 2020-12-06 2022-09-10 cro-projects cation Selection ntation and author's supervis ion of construction works UA-USIF-199452-CS-CQS / 2. 1/1_Services for the preparat Social Protection Services Mi Consultant Qualifi ion of design and estimate d TF / A8367 Post Open - National 9,600.00 9,597.28 Completed 2020-10-16 2020-10-20 2020-10-30 2020-11-05 2020-11-04 2020-11-27 2020-11-21 2020-12-07 2020-11-22 2020-12-10 2022-04-30 2021-05-21 cro-projects cation Selection ocumentation and author's s upervision of construction wo rks - Skala-Podilska UA-USIF-215895-CS-LCS / An Project Management and Ad Least Cost Selecti nual financial audits (includin TF / A8367 ministration, Monitoring and Post Open - National 10,000.00 6,601.83 Completed 2021-01-29 2021-02-04 2021-01-29 2021-02-01 2021-01-19 2021-02-15 2021-02-19 2021-02-20 2021-02-23 2021-03-02 2021-03-05 2021-03-05 2021-03-23 2021-05-07 2021-06-09 on g procurement issues)-2020 Evaluation, and Knowledge Dissemination UA-USIF-219699-CS-CQS / 3. Project Management and Ad 9/1 Training events for non-p ministration, Monitoring and Consultant Qualifi TF / A8367 Post Open - National 10,500.00 1,500.06 Completed 2021-02-15 2021-02-24 2021-03-03 2021-03-05 2021-03-15 2021-04-05 2021-03-29 2021-04-05 2021-04-15 2021-04-21 2021-06-01 2021-06-26 articipating communities (Ter Evaluation, and Knowledge cation Selection nopil and Odesa oblasts) Dissemination UA-USIF-238136-CS-CQS / T Social Protection Services Mi Consultant Qualifi echnical supervision services TF / A8367 Post Open - National 1,200.00 1,227.60 Completed 2021-06-04 2021-06-07 2021-07-08 2021-07-27 2021-08-10 2021-08-01 2021-08-25 2021-08-18 2021-08-29 2022-03-21 2023-03-04 cro-projects cation Selection within the micro-project 18-6 1-01. Borshchiv Page 3 UA-USIF-239047-CS-QBS / Te chnical supervision services Social Protection Services Mi Consultant Qualifi TF / A8367 Post Open - National 1,150.00 1,363.83 Signed 2021-06-14 2021-06-14 2021-07-07 2021-07-26 2021-08-10 2021-07-31 2021-08-26 2021-08-17 2021-08-31 2022-03-21 within the micro-project 18-5 cro-projects cation Selection 1-06. Bilyayivka UA-USIF-239050-CS-CQS / T Social Protection Services Mi Consultant Qualifi echnical supervision services TF / A8367 Post Open - National 1,100.00 1,034.17 Completed 2021-06-14 2021-06-14 2021-07-11 2021-07-30 2021-08-10 2021-08-04 2021-09-01 2021-08-21 2021-09-03 2022-03-21 cro-projects cation Selection within the micro-project 18-5 1-09. Troyitsʹke UA-USIF-239058-CS-CQS / T Social Protection Services Mi Consultant Qualifi echnical supervision services TF / A8367 Post Open - National 1,150.00 954.15 Signed 2021-06-14 2021-06-18 2021-07-07 2021-07-26 2021-08-10 2021-07-31 2021-09-01 2021-08-17 2021-09-02 2022-03-21 cro-projects cation Selection within the micro-project 18-5 1-10. Balta UA-USIF-239059-CS-CQS / T Social Protection Services Mi Consultant Qualifi echnical supervision services TF / A8367 Post Open - National 1,300.00 1,176.60 Completed 2021-06-14 2021-06-14 2021-07-07 2021-07-26 2021-08-10 2021-07-31 2021-08-25 2021-08-17 2021-08-29 2022-03-21 2023-03-04 cro-projects cation Selection within the micro-project 18-6 1-05 .Zboriv UA-USIF-249847-CS-CQS / 2. 8/2 Technical supervision ser Social Protection Services Mi Consultant Qualifi TF / A8367 Post Open - National 1,525.00 1,143.32 Signed 2021-08-30 2021-08-23 2021-09-20 2021-12-17 2021-10-11 2021-09-16 2021-10-16 2021-10-15 2021-11-01 2021-10-19 2022-03-14 vices within the micro-project cro-projects cation Selection 18-51-07. Vylkovo UA-USIF-352813-CS-LCS / An Project Management and Ad Least Cost Selecti nual financing audit (includin TF / A8367 ministration, Monitoring and Post Open - National 10,000.00 0.00 Signed 2023-03-30 2023-03-29 2023-03-30 2023-03-30 2023-04-10 2023-04-13 2023-04-25 2023-04-18 2023-04-26 2023-04-24 2023-04-28 2023-05-10 2023-06-30 on g procurement issues)-01/01/ Evaluation, and Knowledge 22-31/12-22 Dissemination INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UA-USIF-87374-CS-INDV / № Social Protection Services Mi Individual Consult 2.12. Local Capacity Building TF / A8367 Post Open 43,000.00 25,525.00 Completed 2018-11-16 2019-02-06 2018-12-12 2019-03-13 2018-12-26 2019-04-01 2019-01-02 2019-04-01 2022-03-20 2019-09-30 cro-projects ant Selection Consultant (Ternopil oblast) UA-USIF-87375-CS-INDV / № Social Protection Services Mi Individual Consult 2.13. Local Capacity Building TF / A8367 Post Open 43,000.00 25,800.00 Completed 2018-11-16 2019-02-06 2018-12-12 2019-03-11 2018-12-26 2019-03-13 2019-01-02 2019-03-18 2022-03-20 2020-02-14 cro-projects ant Selection Consultant (Odesa oblast) Project Management and Ad UA-USIF-87381-CS-INDV / № Individual Consult TF / A8367 ministration, Monitoring and Post Open 86,000.00 88,000.00 Completed 2018-11-16 2018-09-20 2018-12-19 2018-10-30 2018-12-26 2018-12-29 2018-12-26 2018-12-29 2022-04-30 2020-05-16 3.3. Project Coordinator ant Selection Evaluation, and Knowledge Dissemination UA-USIF-87389-CS-INDV / № Project Management and Ad Individual Consult 3.2. Implementation Complet TF / A8367 ministration, Monitoring and Post Open 2,000.00 0.00 Canceled 2022-03-01 2022-03-26 2022-04-05 2022-04-05 2022-05-05 ant Selection ion Report, local consultant Evaluation, and Knowledge Dissemination UA-USIF-87391-CS-CDS / №3 .6. PIU staff* Project Management and Ad * PIU staff - 4 persons (2 civil ministration, Monitoring and engineers, procurement spec TF / A8367 Post Direct Selection Direct 148,000.00 0.00 Canceled 2018-11-17 2018-11-27 2019-01-16 2022-01-02 Evaluation, and Knowledge ialist and financial manager). Dissemination It is not a procurement categ ory as per para 7.32 of the Pr ocurement Regulations. UA-USIF-0090004-CS-INDV / Project Management and Ad Individual Consult 3.5. Training, monitoring and TF / A8367 ministration, Monitoring and Post Open 40,000.00 39,600.00 Completed 2019-02-13 2019-02-06 2019-03-01 2019-03-11 2019-03-01 2019-03-11 2019-03-01 2019-03-13 2022-04-30 2020-07-13 ant Selection evaluation specialist Evaluation, and Knowledge Dissemination UA-USIF-134897-CS-INDV / 2 Development of Social Prote Individual Consult .12/1 Community Capacity B TF / A8367 ction Services Delivery Capa Post Open 36,300.00 18,000.00 Completed 2019-09-18 2019-09-20 2019-10-14 2019-10-15 2019-10-15 2019-10-16 2019-11-05 2019-10-16 2022-03-31 2020-09-23 ant Selection uilding Consultant (Ternopil o city blast) UA-USIF-139098-CS-CAPA / 1 Development of Social Prote .3/1 Trainings for amalgamat TF / A8367 ction Services Delivery Capa Post Direct Selection Direct 20,000.00 19,336.57 Completed 2019-10-21 2019-10-22 2019-10-22 2019-11-19 2019-11-06 2019-11-19 2019-12-23 2019-12-12 ed communities to prepare a city pplications UA-USIF-159174-CS-INDV / 2 Development of Social Prote Individual Consult .13/1 Community Capacity B TF / A8367 ction Services Delivery Capa Post Open 26,200.00 26,200.00 Signed 2020-02-12 2020-02-07 2020-03-10 2020-03-02 2020-03-12 2020-03-02 2020-03-17 2020-03-03 2021-12-31 ant Selection uilding Consultant (Odesa ob city last) Project Management and Ad UA-USIF-175883-CS-INDV / 3 Individual Consult TF / A8367 ministration, Monitoring and Post Open 61,700.00 60,700.00 Signed 2020-05-27 2020-05-29 2020-06-15 2020-06-17 2020-06-15 2020-07-01 2020-06-15 2020-07-02 2022-10-31 .3/1 Project Coordinator ant Selection Evaluation, and Knowledge Dissemination UA-USIF-184742-CS-INDV / T Project Management and Ad Individual Consult raining, monitoring and evalu TF / A8367 ministration, Monitoring and Post Open 21,400.00 20,400.00 Completed 2020-07-20 2020-07-22 2020-08-05 2020-08-10 2020-08-05 2020-08-10 2020-08-06 2020-08-15 2022-02-01 2022-10-08 ant Selection ation specialist Evaluation, and Knowledge Dissemination UA-USIF-187646-CS-INDV / T Development of Social Prote raining in the format of cons Individual Consult TF / A8367 ction Services Delivery Capa Post Open 3,500.00 3,500.00 Completed 2020-08-07 2020-08-19 2020-08-25 2020-09-10 2020-08-25 2020-09-11 2020-08-26 2020-09-12 2020-11-16 2020-12-25 ultations on service designer ant Selection city s created or organized in co mmunities UA-USIF-195704-CS-INDV / 2 Social Protection Services Mi Individual Consult .12/2 Community Capacity B TF / A8367 Post Open 23,000.00 21,800.00 Signed 2020-09-23 2020-09-24 2020-10-10 2020-10-19 2020-10-11 2020-11-02 2020-10-12 2020-11-03 2021-05-01 cro-projects ant Selection uilding Consultant (Ternopil o blast) UA-USIF-206301-CS-CDS / sa feguard consultant - impleme Project Management and Ad ntation of environmental and ministration, Monitoring and social screening of 10 micro- TF / A8367 Post Direct Selection Direct 2,000.00 2,000.00 Completed 2020-11-25 2020-12-07 2020-12-02 2020-12-14 2020-12-04 2020-12-15 2021-01-31 2021-02-13 Evaluation, and Knowledge projects approved for implem Dissemination entation, and development o f Environmental and Social M anagement Plans for them UA-USIF-259211-CS-INDV / 3 Project Management and Ad .9/2 Training online events fo ministration, Monitoring and Individual Consult TF / A8367 Post Open 15,500.00 12,207.14 Completed 2021-10-25 2021-11-05 2021-11-16 2021-11-29 2021-11-17 2021-11-30 2021-12-02 2022-04-11 2022-05-01 2022-07-02 r communities (Ternopil and Evaluation, and Knowledge ant Selection Odesa oblasts) 2021-2022 Dissemination Project Management and Ad UA-USIF-275323-CS-CDS / Ci TF / A8367 ministration, Monitoring and Post Direct Selection Direct 10,400.00 5,300.00 Completed 2022-01-27 2022-02-01 2022-01-28 2022-02-01 2022-02-01 2022-02-13 2022-09-30 2022-10-08 vil engineer (Ternopil oblast) Evaluation, and Knowledge Dissemination Project Management and Ad UA-USIF-275334-CS-CDS / Ci TF / A8367 ministration, Monitoring and Post Direct Selection Direct 10,400.00 5,300.00 Signed 2022-01-27 2022-02-01 2022-01-28 2022-02-01 2022-02-01 2022-02-13 2022-09-30 vil engineer (Odesa oblast) Evaluation, and Knowledge Dissemination Page 4 UA-USIF-285753-CS-CDS / '3. Project Management and Ad 7/3- Annual financial audit (in TF / A8367 ministration, Monitoring and Post Direct Selection Direct 7,520.00 7,451.64 Completed 2022-03-23 2022-04-26 2022-04-02 2022-04-18 2022-04-20 2022-04-25 2022-06-15 2022-07-07 cluding procurement issues)- Evaluation, and Knowledge 2021 Dissemination UA-USIF-292667-CS-CDS / 2. 1/2 - Preparation of designs a Social Protection Services Mi TF / A8367 Post Direct Selection Direct 8,550.00 8,472.41 Signed 2022-04-29 2022-05-06 2022-04-30 2022-05-06 2022-05-16 2022-05-07 2023-04-30 nd author's supervision for m cro-projects inor civil works - Skala-Podils ka UA-USIF-319025-CS-CDS / 3. Project Management and Ad 13 Civil engineer (Ternopil ob TF / A8367 ministration, Monitoring and Post Direct Selection Direct - National 2,750.00 0.00 Signed 2022-10-05 2022-10-03 2022-10-06 2022-09-30 2022-10-10 2023-04-30 last) Evaluation, and Knowledge Dissemination UA-USIF-321577-CS-CDS / 2. 3/3 Technical supervision ser Social Protection Services Mi TF / A8367 Post Direct Selection Direct - National 1,252.00 0.00 Signed 2022-10-21 2022-10-19 2022-10-21 2022-10-19 2022-10-24 2023-05-03 vices within the micro-project cro-projects 18-61-02. Skala-Podilska UA-USIF-323975-CS-INDV / 3 Project Management and Ad Individual Consult .5/2 Training, monitoring and TF / A8367 ministration, Monitoring and Post Open - National 10,800.00 0.00 Signed 2022-11-01 2022-11-03 2022-11-21 2022-11-28 2022-11-22 2022-11-29 2022-11-22 2023-08-31 ant Selection evaluation specialist Evaluation, and Knowledge Dissemination UA-USIF-357733-CS-CDS / Tr Project Management and Ad aining under the advanced tr TF / A8367 ministration, Monitoring and Post Direct Selection Direct - National 5,874.00 0.00 Completed 2023-04-20 2023-04-21 2023-04-21 2023-04-21 2023-04-21 2023-06-20 2023-05-31 aining program Evaluation, and Knowledge Dissemination UA-USIF-357738-CS-CDS / Or ganization and conduct of tra Development of Social Prote ining for community in accor TF / A8367 ction Services Delivery Capa Post Direct Selection Direct - National 2,200.00 0.00 Signed 2023-04-24 2023-04-20 2023-05-01 2023-04-28 2023-05-09 2023-08-07 dance with the developed ind city ividual training program. UA-USIF-357741-CS-CDS / Or ganization and conduct of tra Development of Social Prote ining for community in accor TF / A8367 ction Services Delivery Capa Post Direct Selection Direct - National 2,200.00 0.00 Signed 2023-04-24 2023-04-20 2023-05-01 2023-04-28 2023-05-09 2023-08-07 dance with the developed ind city ividual training program. UA-USIF-357746-CS-CDS / Or ganization and conduct of tra Development of Social Prote ining for community in accor TF / A8367 ction Services Delivery Capa Post Direct Selection Direct - National 2,200.00 0.00 Signed 2023-04-24 2023-04-21 2023-05-01 2023-04-28 2023-05-09 2023-08-07 dance with the developed ind city ividual training program UA-USIF-357749-CS-CDS / Or ganization and conduct of tra Development of Social Prote ining for community in accor TF / A8367 ction Services Delivery Capa Post Direct Selection Direct - National 2,200.00 0.00 Signed 2023-04-24 2023-04-21 2023-05-01 2023-04-28 2023-05-09 2023-08-07 dance with the developed ind city ividual training program UA-USIF-362461-CS-CDS / Pr Development of Social Prote actical trainings for psycholo TF / A8367 ction Services Delivery Capa Post Direct Selection Direct - National 2,000.00 0.00 Signed 2023-05-19 2023-05-29 2023-05-23 2023-05-23 2023-06-01 2023-07-18 gists and specialists in the so city cial sphere Page 5 Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. July 9, 2010 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 82 5 No Prior of the ICB (Works) Summary 43.77 15 No Prior of the ICB (Goods) Summary 64.53 18 No Post 1st of the NCB contrac (Works) t for Prior Review Summary 1.86 4 No Post 1st of the NCB contrac (Goods) t for Prior Review Summary 0.45 1 No Prior of the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 4.17 7 Prior of number of contracts that will be let under QCBS Summary 0.83 1 Prior CQS of number of contracts that will be let under other July 9, 2010 methods July 9, 2010 PROCUREMENT Georgia : Third Regional Development Project PLAN General Information Country: Georgia 2016-08-11 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150696 GPN Date: Project Name: Third Regional Development Project Loan / Credit No: IBRD / 84940 Municipal Development Fund of Georgia Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IBRD/RDPIII/CW/NCB/30-201 6 / Arrangement of parking lo Single Stage - One E 2017-06-2 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 470,209.00 390,757.60 Signed 2016-09-14 2016-09-13 2016-09-14 2016-10-16 2016-10-13 2016-11-15 2016-10-24 2016-12-27 2016-11-15 t at Dariali Monastery and re nvelope 5 habilitation of access road to monastery residence IBRD/RDPIII/CW/NCB/06-201 Single Stage - One E 2018-05-0 6 / Arrangement of tourism i IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 400,000.00 227,239.14 Completed 2017-01-24 2016-10-22 2017-01-24 2017-02-25 2016-11-22 2017-03-27 2016-12-20 2017-05-08 2017-01-18 nvelope 8 nfrastructure at Sapara Mona stery IBRD/RDPIII/CW/NCB/10-201 Single Stage - One E 2017-06-2 6 / Rehabilitation and safety IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 700,000.00 540,489.73 Completed 2016-09-13 2016-03-28 2016-09-13 2016-10-15 2016-04-28 2016-11-14 2016-07-04 2016-12-26 2016-07-20 nvelope 4 measures of access road to Gogasheni village IBRD/RDPIII/CW/NCB/02-201 Single Stage - One E 2018-07-2 6 / Restoration of Stepantsmi IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 724,540.00 167,343.14 Completed 2016-10-04 2016-10-22 2016-10-04 2016-11-05 2016-11-22 2016-12-05 2016-12-12 2017-01-16 2016-12-20 nvelope 0 nda Museum Complex IBRD/RDPIII/CW/NCB/28-201 6 / Rehabilitation of access ro Single Stage - One E 2017-06-1 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 591,893.00 526,423.90 Signed 2016-08-31 2016-08-24 2016-08-31 2016-10-02 2016-09-26 2016-11-01 2016-10-10 2016-12-13 2016-10-19 ad of village Gergeti, arrange nvelope 1 ment of foot trail to Trinity C hurch IBRD/RDPIII/CW/NCB/20-201 Single Stage - One E 2017-12-2 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 500,000.00 256,812.04 Terminated 2017-01-15 2016-12-15 2017-01-15 2017-02-16 2017-01-24 2017-03-18 2017-02-23 2017-04-29 2017-03-22 6 / Arrangement of Bakuriani nvelope 5 Central Trail IBRD/RDPIII/CW/NCB/09-201 Single Stage - One E 2018-05-1 6 / Arrangement of tourism i IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 700,000.00 697,900.84 Completed 2017-04-04 2017-03-10 2017-04-04 2017-05-04 2017-04-20 2017-06-03 2017-05-05 2017-07-15 2017-05-24 nvelope 1 nfrastructure at Khertvisi Co mplex IBRD/RDPIII/CW/NCB/29-201 6 / Arrangement of safety me Single Stage - One E 2018-10-2 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 200,000.00 233,680.27 Completed 2017-07-17 2017-08-15 2017-07-17 2017-08-18 2017-09-14 2017-09-17 2017-10-30 2017-10-29 2017-11-27 asures and tourism infrastruc nvelope 9 ture at Vanis Qvabebi IBRD/RDPIII/CW/NCB/11-201 Single Stage - One E 2018-04-2 7 / Arrangement of Tourist In IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 670,000.00 778,723.48 Completed 2017-07-17 2017-07-12 2017-07-17 2017-08-16 2017-08-11 2017-09-15 2017-08-31 2017-10-27 2017-09-19 nvelope 5 frastructure at Vardzia Caves IBRD/RDPIII/CW/NCB/11-201 Single Stage - One E 2018-08-2 6 / Arrangement of Tourist In IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 600,000.00 0.00 Canceled 2017-05-15 2017-04-25 2017-05-15 2017-06-16 2017-05-25 2017-07-16 2017-08-27 nvelope 7 frastructure at Vardzia Caves IBRD/RDPIII/CW/NCB/04-201 7 / Adaptation of the Mtskhet Single Stage - One E 3,697,765.4 2019-08-1 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 2,780,000.00 Completed 2017-11-03 2017-11-03 2017-11-03 2017-12-05 2017-12-04 2018-01-04 2017-12-20 2018-02-15 2017-12-26 a old cinema building for est nvelope 1 9 ablishment of the Mtskheta a rchaeological museum IBRD/RDPIII/CW/NCB/23-201 Single Stage - One E 1,778,926.6 2019-03-0 6 / Rehabilitation of Abastum IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 900,000.00 Signed 2017-11-30 2017-12-20 2017-11-30 2017-12-30 2018-01-30 2018-01-29 2018-05-25 2018-03-05 2018-06-11 nvelope 6 5 ani Observatory IBRD/RDPIII/CW/NCB/36-201 Single Stage - One E 2,222,955.8 2019-02-2 7 / Rehabilitation of Abastum IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 1,060,000.00 Completed 2017-11-20 2017-12-20 2017-11-20 2017-12-22 2018-01-22 2018-01-21 2018-02-19 2018-02-25 2018-03-16 nvelope 8 5 ani Historical Wooden House s IBRD/RDPIII/CW/NCB/37-201 Single Stage - One E 2018-07-1 7 / Rehabilitation of an acces IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 410,000.00 373,248.96 Completed 2017-12-11 2017-12-20 2017-12-11 2018-01-12 2018-01-22 2018-02-11 2018-02-08 2018-03-18 2018-02-19 nvelope 6 s road to village Mirashkhani IBRD/RDPIII/CW/NCB/38-201 Single Stage - One E 2019-12-2 7 / Rehabilitation of Abastum IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 9,000,000.00 0.00 Canceled 2018-09-17 2018-09-22 2018-11-03 2018-12-03 2019-01-07 nvelope 3 ani Water and Sewage Syste ms IBRD/RDPIII/CW/NCB/34-201 Single Stage - One E 2019-12-3 7 / Rehabilitation of Abastum IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 9,000,000.00 0.00 Canceled 2018-10-10 2018-10-15 2018-11-26 2018-12-26 2019-01-30 nvelope 1 ani Water Supply and Waste water Systems IBRD/RDPIII/CW/NCB/08-201 7 / Restoration of Saro Darba Single Stage - One E 2019-12-3 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 750,000.00 0.00 Canceled 2018-06-04 2018-06-04 2018-07-06 2018-08-05 2018-09-16 zi houses, rehabilitation of ac nvelope 0 cess road and tourism infrast ructure IBRD/RDPIII/CW/NCB/32-201 Single Stage - One E 2019-10-0 7 / Mitarbi Road Rehabilitatio IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 2,200,000.00 0.00 Canceled 2018-06-11 2018-06-16 2018-07-28 2018-08-27 2018-10-01 nvelope 1 n and Didveli Parking Extensi on IBRD/RDPIII/CW/NCB/12-201 7 / Mtskheta integrated urba n regeneration (including reh Single Stage - One E 2019-12-3 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 4,000,000.00 0.00 Canceled 2019-04-22 2019-04-22 2019-05-24 2019-06-23 2019-08-04 abilitation and enhancement nvelope 0 of Mtskheta Recreation Park and Jvari Tourism Infrastruct ure) IBRD/RDPIII/CW/NCB/13-201 Single Stage - One E 2019-12-2 7 / Development of Tourism i IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2018-10-01 2018-10-01 2018-11-02 2018-12-02 2019-01-13 nvelope 9 nfrastructure at Jvari monast ery IBRD/RDPIII/CW/NCB/31-201 Single Stage - One E 1,298,081.8 2019-04-0 7 / Rehabilitation of access ro IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 1,130,000.00 Completed 2018-03-26 2018-04-30 2018-03-26 2018-04-27 2018-05-30 2018-05-27 2018-06-20 2018-07-08 2018-06-27 nvelope 9 4 ad to Zedazeni Monastery Page 1 IBRD/RDPIII/CW/NCB/15-201 7 / Rehabilitation of Dusheti Single Stage - One E 2019-12-2 Archeological Base, access ro IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 3,000,000.00 0.00 Canceled 2019-03-05 2019-03-05 2019-04-02 2019-05-02 2019-06-06 nvelope 3 ad to place and tourism infra structure (Chilashiviliebi pala ce) IBRD/RDPIII/CW/NCB/01-201 6 / Arrangement of tourism i nfrastructure at Ananuri castl Single Stage - One E 2019-08-1 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 170,000.00 0.00 Canceled 2018-04-30 2018-04-30 2018-06-01 2018-07-01 2018-08-12 e (improvement of parking, t nvelope 2 ourism infrastructure and arr angement of small artisan m arketplaces) IBRD/RDPIII/CW/NCB/14-201 6 / Rehabilitation of historical Single Stage - One E 2019-12-3 streets in Dusheti (infrastruc IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 1,888,000.00 411,953.34 Terminated 2018-06-14 2018-06-25 2018-06-15 2018-07-15 2018-07-25 2018-07-30 2018-11-08 2018-08-17 2018-11-26 nvelope 0 tural rehabilitation, street lig hting posts and restoration of houses' facades and roofs) IBRD/RDPIII/CW/SH/01-2018 / Arrangement of access road Request for Quota Single Stage - One E 2019-06-0 , gas infrastructure and inter IBRD / 84940 Infrastructure Investment Post Open - National 90,000.00 89,609.43 Completed 2019-02-10 2019-04-07 2019-03-21 tions nvelope 6 net supply for hotel Sevsamo ra LTD, in Mtsketa Municipalit y IBRD/RDPIII/CW/NCB/07-201 7 / Arrangement of Tourist In Single Stage - One E 1,135,554.3 2020-12-1 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 900,000.00 Signed 2019-03-18 2019-04-12 2019-03-18 2019-04-17 2019-05-13 2019-05-17 2019-05-28 2019-06-28 2019-06-22 frastructure and Urgent Rest nvelope 7 9 oration Works for Zarzma Mo nastery IBRD/RDPIII/CW/NCB/18-201 Single Stage - One E 2020-11-2 7 / Arrangement of tourism i IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 3,000,000.00 0.00 Canceled 2019-03-12 2019-03-12 2019-04-11 2019-05-11 2019-06-08 nvelope 9 nfrastructure at Gudauri IBRD/RDPIII/CW/NCB/19-201 Single Stage - One E 2021-08-0 7 / Restoration and Adaptatio IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 1,150,000.00 990,165.92 Signed 2019-11-11 2019-05-17 2019-11-11 2019-12-11 2019-06-17 2020-01-10 2019-07-04 2020-02-14 2019-08-03 nvelope 7 n of Borjomi Cavalry Building as a Museum IBRD/RDPIII/CW/NCB/39-201 Single Stage - One E 2,043,543.2 2020-11-3 7 / Restoration of Stepantsmi IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 740,000.00 Signed 2019-03-06 2019-06-21 2019-03-06 2019-04-05 2019-08-30 2019-05-05 2019-09-16 2019-06-09 2019-10-20 nvelope 5 0 nda Museum Complex (Phase 2) IBRD/RDPIII/CW/NCB/40-201 Single Stage - One E 2019-12-0 9 / Arrangement of Bakuriani IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 1,110,000.00 960,495.30 Signed 2019-04-10 2019-04-08 2019-04-10 2019-05-10 2019-05-22 2019-05-31 2019-06-03 2019-07-12 2019-06-30 nvelope 9 Central Trail and Road (Phas e 2) IBRD/RDPIII/CW/NCB/41-202 Single Stage - One E 2021-05-0 0 / Urban Regeneration of His IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 1,600,000.00 460,823.02 Signed 2020-02-03 2020-07-27 2020-02-06 2020-03-07 2020-08-27 2020-03-28 2021-03-15 2020-05-02 2021-03-28 nvelope 2 torical Streets in Dusheti - P hase II IBRD/RDPIII/CW/DC/01-2020 / Urban Regeneration of Hist 2020-06-0 IBRD / 84940 Infrastructure Investment Post Direct Selection Direct 280,000.00 243,610.94 Signed 2020-01-30 2020-06-26 2020-02-04 2020-06-04 2020-03-10 2020-06-26 orical Streets in Dusheti (Urg 8 ent Remaining works) IBRD/RDPIII/CW/NCB/42-202 Single Stage - One E 2020-08-0 0 / Arrangement of Lighting P IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 200,000.00 167,382.50 Completed 2020-02-10 2020-06-23 2020-02-13 2020-03-14 2020-07-23 2020-04-04 2020-08-05 2020-05-09 2020-08-14 nvelope 7 osts for Bakuriani Central Tra il IBRD/RDPIII/DSI/ICB/01-2020 / Detailed Design Preparation Open - Internationa Single Stage - One E 15,434,114.4 13,302,899. 2022-10-1 IBRD / 84940 Infrastructure Investment Prior Request for Bids Signed 2020-11-23 2020-12-24 2020-12-14 2021-02-05 2021-01-28 2021-03-01 2021-03-14 2021-04-14 2021-04-25 2021-05-15 and Rehabilitation of Blue an l nvelope 5 90 7 d Green corridor in Abastuma ni (Design/Build) IBRD/RDPIII/CW/NCB/26-201 Single Stage - One E 2022-06-1 6 / Tourism Infrastructure de IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 3,260,000.00 0.00 Canceled 2021-04-05 2021-07-12 2021-04-05 2021-05-07 2021-08-13 2021-06-06 2021-10-21 2021-07-18 nvelope 3 velopment at Bakuriani Recr eation Park Request for Bids - IBRD/RDPIII/CW/NCB/43-202 Single Stage - One E Small Works SPD 2,538,464.7 2022-12-2 1 / Urban Regeneration of His IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 2,300,000.00 Signed 2021-05-31 2021-06-18 2021-06-03 2021-07-03 2021-07-19 2021-07-24 2021-10-13 2021-08-28 2021-11-29 nvelope (1 envelope proce 0 1 torical Streets in Dusheti - P ss) hase III Request for Bids - IBRD/RDPIII/CW/NCB/22-201 Single Stage - One E Small Works SPD 2024-04-1 6 / Rehabilitation of historical IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 3,200,000.00 0.00 Canceled 2022-06-30 2022-07-05 2022-08-16 2022-09-15 2022-10-20 nvelope (1 envelope proce 2 houses in Abastumani ss) Request for Bids - IBRD/RDPIII/CW/NCB/45-202 Single Stage - One E Small Works SPD 3,172,402.5 2023-05-0 1 / Tourism Infrastructure De IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 4,600,000.00 Signed 2021-12-15 2021-12-27 2021-12-18 2022-01-17 2022-02-07 2022-02-07 2022-02-22 2022-03-14 2022-04-02 nvelope (1 envelope proce 6 8 velopment at Bakuriani Recr ss) eation Park IBRD/RDPIII/CW/NCB/47-202 1 / Conservation-Restoration Request for Bids - of Historic Fortress-Settleme Single Stage - One E Small Works SPD 2023-12-1 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 3,100,000.00 0.00 Canceled 2022-03-30 2022-04-02 2022-05-02 2022-05-23 2022-06-27 nt Zakagori Complex and Sus nvelope (1 envelope proce 9 tainable Preservation, Faciliti ss) es Development and upgradi ng of Truso Protected Landsc ape IBRD/RDPIII/CW/NCB/48-202 Request for Bids - 1 / Arrangement of basic and Single Stage - One E Small Works SPD 1,917,986.6 2023-09-1 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 1,500,000.00 Signed 2021-12-28 2022-07-04 2021-12-31 2022-01-30 2022-08-05 2022-02-20 2022-08-30 2022-03-27 2022-10-01 recreational infrastructure in nvelope (1 envelope proce 0 8 Tbilisi National Park ss) Request for Bids - IBRD/RDPIII/DB/NCB/01-2021 Single Stage - One E Works – Roads (O 2022-12-2 / Bakuriani urban rehabilitati IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 1,300,000.00 0.00 Canceled 2022-01-25 2022-11-29 2022-01-28 2022-11-29 2022-02-27 2022-03-20 2022-04-24 nvelope utput and Perform 0 on of roads ance Based Road Contracts) Request forSPD Bids - IBRD/RDPIII/DB/NCB/02-2021 Single Stage - One E Works – Roads (O 4,494,971.6 2023-09-1 / Construction of Bakuriani B IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 4,200,000.00 Signed 2021-12-20 2021-12-29 2021-12-23 2022-01-22 2022-02-09 2022-02-12 2022-03-02 2022-03-19 2022-04-07 nvelope utput and Perform 0 0 us-Station ance Based Road Contracts) SPD IBRD/RDPIII/CW/NCB/46-202 Request for Bids - 1 / Arrangement and Constru Single Stage - One E Small Works SPD 2023-09-0 ction of Sustainable Visitor Tr IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 7,500,000.00 0.00 Canceled 2021-12-15 2021-12-23 2021-12-18 2022-01-17 2022-02-01 2022-02-07 2022-03-14 nvelope (1 envelope proce 5 ails and Mountain Huts for Ka ss) zbegi, Pshav-Khevsureti and Tusheti Protected Areas IBRD/RDPIII/CW/NCB/46-202 Request for Bids - 1-2 / Arrangement and Const Single Stage - One E Small Works SPD 2024-01-2 ruction of Sustainable Visitor IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 8,900,000.00 0.00 Canceled 2022-05-10 2022-05-11 2022-05-13 2022-06-12 2022-06-13 2022-07-03 2022-08-07 nvelope (1 envelope proce 9 Trails and Mountain Huts for ss) Kazbegi, Pshav-Khevsureti an d Tusheti Protected Areas Page 2 IBRD/RDPIII/CW/NCB/46-202 Request for Bids - 1-3 / Arrangement and Const Single Stage - One E Small Works SPD 2024-08-1 ruction of Sustainable Visitor IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 8,900,000.00 0.00 Signed 2022-08-23 2022-08-25 2022-08-26 2022-09-25 2022-09-26 2022-10-16 2022-10-24 2022-11-20 nvelope (1 envelope proce 1 Trails and Mountain Huts for ss) Kazbegi, Pshav-Khevsureti an d Tusheti Protected Areas IBRD/RDPIII/DB/NCB/01-2021 Request for Bids - -2 / Design & Construction fo Works – Roads (O Single Stage - One E Under Imple 2024-07-1 r Road Rehabilitation, Arrang IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National utput and Perform 3,672,000.00 0.00 2023-05-18 2023-05-19 2023-05-21 2023-05-19 2023-06-20 2023-07-11 2023-08-15 nvelope mentation 0 ement of Pedestrian and Bicy ance Based Road cle Infrastructure in Bakurian Contracts) SPD i Request for Bids - IBRD/RDPIII/CW/NCB/44-202 Single Stage - One E Small Works SPD Under Imple 2023-05-2 1 / Roscha Park Rehabilitatio IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 920,000.00 0.00 2022-02-25 2023-06-09 2022-02-28 2022-03-30 2022-04-20 2022-05-25 nvelope (1 envelope proce mentation 5 n in Abastumani ss) IBRD/RDPIII/CW/NCB/35-201 Single Stage - One E 1,020,345.4 2019-07-3 7 / Rehabilitation of Bakurian IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 1,150,000.00 Completed 2017-11-15 2017-08-29 2017-11-20 2018-01-01 2017-09-29 2018-01-31 2017-10-11 2018-03-07 2017-10-31 nvelope 4 0 i-Tsikhisjvari Road IBRD/RDPIII/CW/NCB/33-201 7 / Rehabilitation of Abastum Single Stage - One E 2019-07-2 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 700,000.00 0.00 Canceled 2017-11-06 2017-11-11 2017-12-23 2018-01-22 2018-02-26 ani Historical Central Park an nvelope 1 d riverbed sides and bridges IBRD/RDPIII/CW/NCB/27-201 Single Stage - One E 2017-11-1 IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 1,000,000.00 969,981.12 Completed 2016-12-01 2016-12-09 2016-12-06 2017-01-17 2017-01-16 2017-02-16 2017-02-23 2017-03-23 2017-03-22 6 / Rehabilitation of Dusheti nvelope 8 Central Park IBRD/RDPIII/CW/NCB/03-201 Single Stage - One E 1,335,323.5 Under Revie 5 / Restoration of access roa IBRD / 84940 Infrastructure Investment Prior Request for Bids Open - National 1,500,000.00 2015-12-01 2015-12-21 nvelope 0 w d to Sapara Monastery GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA/RDPIII/G/NCB/01-2017 / Single Stage - One E Supply of furniture and show IBRD / 84940 Institutional Development Post Request for Bids Open - National 925,000.00 0.00 Canceled 2019-07-22 2019-07-27 2019-09-07 2019-10-07 2019-11-11 2019-12-31 nvelope cases for Mtskheta Archaeolo gical Museum IDA/RDPIII/G/NCB/02-2017 / Single Stage - One E Supply of furniture and show IBRD / 84940 Institutional Development Post Request for Bids Open - National 740,000.00 0.00 Canceled 2019-08-12 2019-08-17 2019-09-16 2019-10-14 2019-11-11 2019-12-31 nvelope cases for Stepantsminda Mus eum IBRD/RDPIII/G/DC/01-2019 / Single Stage - One E IBRD / 84940 Institutional Development Post Request for Bids Open - National 4,000.00 2,745.56 Completed 2019-03-11 2019-03-12 2019-03-11 2019-03-21 2019-03-24 2019-04-17 2019-04-03 2019-04-17 2019-05-03 2019-05-07 Supply of FIDIC Books nvelope IBRD/RDPIII/G/NCB/02-2017 / Single Stage - One E Pending Impl Supply of furniture and show IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 400,000.00 0.00 2020-04-22 2020-04-27 2020-05-27 2020-06-26 2020-08-07 2020-11-05 nvelope ementation cases for Stepantsminda Mus eum IBRD/RDPIII/G/NCB/03-2019 / Single Stage - One E Pending Impl IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 570,000.00 0.00 2019-04-10 2019-04-10 2019-05-10 2019-06-09 2019-07-21 2019-10-19 Supply of Goods for CH Sites nvelope ementation IBRD/RDPIII/G/SH/01-2019 / Request for Quota Single Stage - One E Supply of a snow plow machi IBRD / 84940 Institutional Development Post Open - National 55,000.00 65,891.74 Completed 2019-12-07 2020-01-18 2020-01-24 2020-02-17 2020-06-24 tions nvelope ne for Abastumani Observato ry IBRD/RDPIII/G/SH/02-2020 / Request for Quota Single Stage - One E Supply of digital equipment f IBRD / 84940 Institutional Development Post Open - National 16,800.00 14,362.16 Completed 2020-08-15 2020-09-26 2020-09-16 2020-11-25 2020-11-11 tions nvelope or MDF PR activities IBRD/RDPIII/G/SH/03-2020 / Supply of digital equipment a Request for Quota Single Stage - One E IBRD / 84940 Institutional Development Post Open - National 29,200.00 0.00 Canceled 2020-08-29 2020-10-10 2021-01-08 nd accessories for Mtskheta tions nvelope Archaeological Museum IBRD/RDPIII/G/SH/05-2020 / Supply of computer, network Request for Quota Single Stage - One E IBRD / 84940 Institutional Development Post Open - National 69,000.00 63,585.59 Completed 2020-09-05 2020-10-17 2020-10-17 2021-01-15 2021-02-13 and audio system equipment tions nvelope and accessories for Abastum ani Observatory IBRD/RDPIII/G/SH/04-2020 / Request for Quota Single Stage - One E Supply of office and outdoor f IBRD / 84940 Institutional Development Post Open - National 33,500.00 26,774.77 Completed 2020-09-05 2020-10-17 2020-10-08 2021-02-14 2021-03-11 tions nvelope urniture for Abastumani Obse rvatory IBRD/RDPIII/G/NCB/04-2020 / Supply of lab and office furnit Single Stage - One E IBRD / 84940 Institutional Development Post Request for Bids Open - National 107,000.00 0.00 Canceled 2020-08-24 2020-09-10 2020-08-29 2020-10-10 2020-10-12 2020-11-09 2020-12-14 2021-03-24 ure and other equipment for nvelope Mtskheta Archaeological Mus eum IBRD/RDPIII/G/SH/06-2020 / Supply of laboratory equipm Request for Quota Single Stage - One E IBRD / 84940 Institutional Development Post Open - National 85,000.00 0.00 Canceled 2020-09-07 2020-11-02 2021-02-10 ent and consumables for Mts tions nvelope kheta Archaeological Museu m IBRD/RDPIII/G/NCB/04-2020- 2 / Supply of lab and office fu Single Stage - One E IBRD / 84940 Institutional Development Post Request for Bids Open - National 107,000.00 84,081.69 Signed 2020-11-10 2020-11-09 2020-11-15 2020-12-27 2020-12-10 2021-01-26 2020-12-24 2021-03-02 2021-01-23 2021-06-30 rniture and other equipment nvelope for Mtskheta Archaeological Museum IBRD/RDPIII/G/SH/03-2020-2 / Supply of digital equipment Request for Quota Single Stage - One E IBRD / 84940 Institutional Development Post Open - National 29,200.00 0.00 Canceled 2020-11-25 2021-01-06 2021-04-06 and accessories for Mtskheta tions nvelope Archaeological Museum IBRD/RDPIII/G/SH/06-2020-2 / Supply of lab equipment an Request for Quota Single Stage - One E IBRD / 84940 Institutional Development Post Open - National 85,000.00 0.00 Canceled 2020-12-20 2021-02-14 2021-05-25 d consumables for Mtskheta tions nvelope Archaeological Museum IBRD/RDPIII/G/NCB/05-2020- 1 / Supply of lab equipment a Single Stage - One E IBRD / 84940 Institutional Development Post Request for Bids Open - National 116,803.00 101,951.90 Signed 2020-12-27 2020-12-25 2021-01-01 2021-02-12 2021-02-01 2021-03-14 2021-03-11 2021-04-18 2021-04-02 2021-08-16 nd consumables for Mtskheta nvelope Archaeological Museum Page 3 IBRD/RDPIII/G/SH/03-2020-2- 2 / Supply of digital equipme Request for Quota Single Stage - One E IBRD / 84940 Institutional Development Post Open - National 40,350.00 1,167.69 Signed 2021-04-06 2021-05-18 2021-05-14 2021-08-16 nt and accessories for Mtskh tions nvelope eta Archaeological Museum IBRD/RDPIII/G/SH/07-2021 / Supply of supplementary equ Request for Quota Single Stage - One E IBRD / 84940 Institutional Development Post Open - National 12,650.00 12,733.12 Completed 2021-11-10 2021-12-22 2021-11-30 2022-06-20 2022-04-08 ipment for the snow plow ma tions nvelope chine for Abastumani Observ atory IBRD/RDPIII/G/ICB/01-2021 / Open - Internationa Single Stage - One E Supply of Telescope and Do IBRD / 84940 Institutional Development Prior Request for Bids 2,610,000.00 3,006,984.32 Signed 2021-11-29 2021-12-21 2021-12-04 2022-01-14 2022-01-15 2022-03-01 2022-02-14 2022-03-31 2022-03-21 2022-06-02 2023-09-12 l nvelope me for Abastumani Observat ory IBRD/RDPIII/G/NCB/01-2017 / Single Stage - One E Supply of furniture and show IBRD / 84940 Infrastructure Investment Post Request for Bids Open - National 750,000.00 0.00 Signed 2022-04-11 2022-07-12 2022-04-16 2022-05-16 2022-08-22 2022-06-15 2022-09-12 2022-07-27 2022-12-24 nvelope cases for Mtskheta Archaeolo gical Museum IBRD/RDPIII/G/NCB/06-2022 / Single Stage - One E Supply of IT equipment for M IBRD / 84940 Institutional Development Post Request for Bids Open - National 350,000.00 0.00 Canceled 2022-05-02 2022-10-07 2022-05-07 2022-06-18 2022-11-07 2022-07-18 2022-08-29 2022-12-27 nvelope tskheta Archaeological Muse um IBRD/RDPIII/G/NCB/07-2022 / Single Stage - One E Pending Impl Supply of Multimedia for Mts IBRD / 84940 Institutional Development Post Request for Bids Open - National 510,000.00 0.00 2022-05-23 2022-05-28 2022-07-09 2022-08-08 2022-09-19 2023-01-17 nvelope ementation kheta Archaeological Museu m IBRD/RDPIII/G/SH/08-2022 / Request for Quota Single Stage - One E Pending Impl Supply of Graphic Design of IBRD / 84940 Institutional Development Post Open - National 85,000.00 0.00 2022-06-20 2022-08-01 2022-10-30 tions nvelope ementation Signs for Mtskheta Archaeolo gical Museum IBRD/RDPIII/G/NCB/06-2022- Single Stage - One E 1 / Supply of IT equipment fo IBRD / 84940 Institutional Development Post Request for Bids Open - National 350,000.00 0.00 Signed 2022-11-20 2022-11-18 2022-11-25 2022-12-25 2022-12-19 2023-01-24 2023-03-31 2023-03-07 2023-08-14 nvelope r Mtskheta Archaeological Mu seum NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IBRD/RDPIII/CS/CQS/11-2016 / Preparation of Detailed Engi neering Design for Rehab. of access road to Mitarbi and Ko Consultant Qualifi khta ropeways, Extension of IBRD / 84940 Infrastructure Investment Post Open - National 50,000.00 54,803.15 Completed 2017-04-17 2017-06-07 2017-05-02 2017-06-15 2017-07-21 2017-07-15 2017-08-06 2017-08-08 2017-08-07 2017-12-06 2019-10-22 cation Selection Parking Lot and Arrang. of Inf rastructure at Didveli and Arr ang. of a Parking Lot, Access Road and Infrast. for the New Ropeway in Gudauri IBRD/RDP/RDPIII/SRMIDP/CS/ CQS/01-2017 / Consulting Se rvices for Preparation of Deta iled Designs for Arrangement Consultant Qualifi IBRD / 84940 Infrastructure Investment Post Open - National 12,613.00 13,693.61 Completed 2017-04-03 2017-04-25 2017-04-24 2017-06-07 2017-05-25 2017-07-07 2017-06-20 2017-08-11 2017-06-23 2017-11-09 2017-12-06 of Access Roads for 5 Sites a cation Selection nd Arrangement of Access Ro ads and Road Lightening for 3 sites Under Puplic Private I nvestment (PPI) Component IBRD/RDP/RDPIII/SRMIDP/CS/ CQS/02-2017 / Consulting Se rvices for Preparation of Deta iled Designs for Arrangement Consultant Qualifi of Gas Supply System for 3 Si IBRD / 84940 Infrastructure Investment Post Open - National 2,200.00 8,101.83 Completed 2017-04-04 2017-07-11 2017-04-25 2017-06-08 2017-08-17 2017-07-08 2017-09-14 2017-08-12 2017-11-08 2017-10-26 2018-04-03 cation Selection tes Under Public Private Inve stment (PPI) Component. (TA covers also PPI components of RDP and SRMIDP. The PP r eflects RDPIII amount only fo r 1 site). IBRD/RDPIII/CS/CQS/15-2017 Consultant Qualifi Open - Internationa / Performance monitoring an IBRD / 84940 Institutional Development Post 250,000.00 249,994.80 Completed 2017-06-09 2017-06-06 2017-06-23 2017-07-27 2017-07-20 2017-08-06 2017-10-03 2017-08-16 2017-11-30 2019-12-24 2020-03-03 cation Selection l d evaluation activities IBRD/RDPIII/CS/CQS/16-2016 / Preparation of design docu Consultant Qualifi IBRD / 84940 Institutional Development Post Open - National 98,850.00 61,137.00 Signed 2017-08-10 2017-08-22 2017-08-31 2017-10-14 2017-10-20 2017-11-13 2017-11-20 2017-12-18 2017-12-04 2018-05-17 mentation for restoration and cation Selection adaptation of Borjomi Cavalr y Building as a Museum IBRD/RDPIII/CS/CQS/14-2017 Consultant Qualifi Open - Internationa / Design Review and Supervi IBRD / 84940 Institutional Development Post 197,479.00 0.00 Canceled 2018-10-10 2018-10-31 2018-12-14 2019-01-13 2019-02-17 2019-12-14 cation Selection l sion of Civil Works (Phase II) IBRD/RDPIII/CS/CQS/21-2017 / Business start-up/expansion Consultant Qualifi IBRD / 84940 Institutional Development Post Open - National 90,000.00 83,374.30 Completed 2018-02-12 2018-02-12 2018-03-05 2018-04-18 2018-03-30 2018-05-18 2018-05-04 2018-06-22 2018-05-08 2019-12-14 2020-01-16 advisory service to tourism S cation Selection MEs (Mtskheta-Mtianeti Regi on) IBRD/RDPIII/CS/CQS/20-2017 / Preparation of consulting se Consultant Qualifi rvices for Mtskheta Archeolo IBRD / 84940 Institutional Development Post Open - National 203,470.00 0.00 Canceled 2018-05-25 2018-06-15 2018-07-29 2018-08-28 2018-10-02 2019-03-31 cation Selection gical Museum Museography, Management Plan and Detail Design for Showcases IBRD/RDPIII/CS/CQS/01-2017 / Preparation of sustainable s Consultant Qualifi Open - Internationa IBRD / 84940 Institutional Development Post 200,000.00 0.00 Canceled 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-07-17 ite and museum managemen cation Selection l t plans for Projects' cultural h eritage sites IBRD/RDPIII/CS/CQS/02-2017 Consultant Qualifi Open - Internationa / Setting up of destination m IBRD / 84940 Institutional Development Post 200,000.00 0.00 Canceled 2018-10-25 2018-11-15 2018-12-29 2019-01-28 2019-03-04 2019-08-31 cation Selection l anagement office in each reg ion Page 4 IBRD/RDPIII/CS/CQS/23-2018 / Design Review and Constru Consultant Qualifi ction Supervision for the Reh IBRD / 84940 Institutional Development Post Open - National 730,000.00 0.00 Canceled 2018-03-15 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2019-12-25 cation Selection abilitation of Abastumani Wa ter Supply and Wastewater S ystems IBRD/RDPIII/CS/QCBS/03-201 8 / Preparation of Detailed D Quality And Cost- Open - Internationa esigns and Construction Sup IBRD / 84940 Institutional Development Post 600,000.00 1,167,725.44 Terminated 2018-01-25 2018-05-30 2018-02-15 2018-02-08 2018-03-31 2018-06-08 2018-04-28 2018-07-23 2018-05-28 2018-08-30 2018-07-02 2018-09-21 2018-08-06 2018-12-04 2019-12-29 Based Selection l ervision for the Intergrated U rban Upgrading of Abastuma ni Cultural&Wellness Town IBRD/RDPIII/CS/LCS/02-2018 Least Cost Selecti Open - Internationa / Project Audit of 2018 and 2 IBRD / 84940 Institutional Development Post 20,000.00 166,262.00 Terminated 2018-10-22 2018-12-14 2018-11-12 2018-12-26 2019-01-14 2019-01-23 2019-01-29 2019-02-22 2019-02-18 2019-03-29 2019-02-27 2019-05-03 2019-03-23 2020-05-02 on l 019 fiscal years IBRD/RDPIII/CS/CQS/17-2016 / Revision of Detailed Design Documentation for Arrangem ent of Tourism Infrastructure Consultant Qualifi IBRD / 84940 Institutional Development Post Open - National 41,150.00 0.00 Canceled 2018-03-20 2018-04-10 2018-05-24 2018-06-23 2018-07-28 2018-12-25 at Jvari Monastery and Prepa cation Selection ration of Detailed Design Doc umentation in accordance wi th UNESCO recommendation s in Mtskheta Municipality IBRD/RDPIII/CS/CQS/18-2018 / Preparation of Detailed Desi Consultant Qualifi IBRD / 84940 Institutional Development Post Open - National 98,700.00 190,000.00 Signed 2018-04-16 2018-05-01 2018-05-07 2018-05-10 2018-06-20 2018-07-25 2018-07-20 2019-03-12 2018-08-24 2019-03-12 2019-01-21 gn for Tourism Infrastructure cation Selection Development at Bakuriani Re creation Park IBRD/RDPIII/CS/QCBS/05-201 8 / Preparation of Detailed D esigns and Construction Sup ervision for the Intergrated U Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 600,000.00 0.00 Under Review 2018-03-20 2019-02-26 2018-04-10 2018-12-19 2018-05-24 2018-06-21 2018-07-21 2018-08-25 2018-09-29 2019-12-23 rban Regeneration of Mtskhe Based Selection l ta (including rehabilitation an d enhancement of Mtskheta Recreation Park and tourism i nfrastructure at Jvari Monast ery) IBRD/RDPIII/CS/QCBS/06-201 8 / Preparation of Detailed D esigns and Construction Sup ervision for the Protected Are Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 600,000.00 0.00 Canceled 2018-02-26 2018-11-13 2018-03-19 2018-03-05 2018-05-02 2018-06-15 2018-05-30 2019-02-25 2018-06-29 2019-03-20 2018-08-03 2018-09-07 2019-12-31 a Sustainable Infrastructure/F Based Selection l acilities Development and Int egrated regeneration of Tbili si National Park and Its Gate way Settlements IBRD/RDPIII/CS/QCBS/04-201 8 / Review and Finalization of Designs of Abastumani WS s ystem and WTP, Preparation Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 1,300,000.00 0.00 Canceled 2018-08-03 2018-08-17 2018-08-13 2018-09-21 2018-10-12 2018-11-02 2018-11-16 2018-11-22 2021-11-26 of DD of WW Network, Prepar Based Selection l ation of Employers Requirem ents and Specifications for D esign-Build Contract of WWT P and Construction Supervisi on IBRD/RDPIII/CS/CQS/04-2016 Consultant Qualifi IBRD / 84940 Institutional Development Post Open - National 85,000.00 0.00 Canceled 2020-10-15 2020-11-05 2020-12-19 2021-01-18 2021-02-22 2021-08-21 / Outreach and Communicati cation Selection on for RDP3 IBRD/RDPIII/CS/CQS/08-2016 / Design Preparation for Reha Consultant Qualifi bilitation of Dusheti Archaeol IBRD / 84940 Infrastructure Investment Post Open - National 110,000.00 0.00 Canceled 2019-03-11 2019-04-01 2019-05-15 2019-06-14 2019-07-19 2020-01-15 cation Selection ogical Base, Access road to p alace and tourism infrastruct ure (Chilashvilebi Palace) IBRD/RDPIII/CS/CQS/19-2018 / Preparation of consulting se rvices for Stepantsminda Mu Consultant Qualifi seum Museography, Detail D IBRD / 84940 Institutional Development Post Open - National 150,000.00 0.00 Canceled 2019-06-10 2019-08-21 2019-07-01 2019-08-14 2019-09-13 2019-10-18 2020-02-15 cation Selection esign for Showcases and Dev elopment of sustainable man agement plans for cultural he ritage monuments of the proj ect IBRD/RDPIII/QCBS/08-2019 / Preparation of consulting ser vices for Mtskheta Archeologi cal Museum Museography, D Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 350,000.00 0.00 Canceled 2019-04-10 2019-05-01 2019-06-07 2019-07-07 2019-07-21 2019-08-11 2019-08-30 2019-12-28 etailed Design for Showcases Based Selection l and development of sustaina ble management plans for cu ltural heritage monuments of the project IBRD/RDPIII/CS/QCBS/02-201 6 / Stakeholder Training, Civi Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 300,000.00 0.00 Canceled 2020-04-01 2020-04-22 2020-06-21 2020-07-19 2020-08-09 2020-09-06 2020-10-04 2021-04-02 c Engagement and Capacity Based Selection l Building to increase sustaina bility in project sites IBRD/RDPIII/CS/QCBS/07-201 9 / Preparation of Detailed D Quality And Cost- Open - Internationa esign Documentation and Mo IBRD / 84940 Institutional Development Post 1,000,000.00 778,336.12 Signed 2019-03-07 2019-03-05 2019-03-28 2019-03-11 2019-05-04 2019-04-23 2019-06-03 2019-06-14 2019-06-24 2019-07-16 2019-07-15 2019-08-01 2019-07-29 2019-09-03 2020-06-23 Based Selection l bility Plan for Bakuriani Urba n Upgrade and Supervision IBRD/RDPIII/CS/CQS/22-2019 / Preparation of Detailed Desi Consultant Qualifi gn Documentation for Juta-R IBRD / 84940 Institutional Development Post Open - National 200,000.00 0.00 Canceled 2019-03-18 2019-05-30 2019-04-08 2019-05-01 2019-05-22 2019-06-21 2019-07-26 2019-11-23 cation Selection oshka-Arkhoti-Shatili-Tusheti Mountain Huts and Supervisi on IBRD/RDPIII/CS/CQS/06- 201 6 / Design Preparation for De Consultant Qualifi velopment of Shatili Heritage IBRD / 84940 Infrastructure Investment Post Open - National 75,000.00 0.00 Canceled 2018-09-03 2018-09-24 2018-11-07 2018-12-07 2019-01-11 2019-07-10 cation Selection Village; and Arrangement of East Caucasus Trekking Rout e/Mountain Huts IBRD/RDPIII/CS/CQS/06-2016 / Design Preparation for Deve Consultant Qualifi lopment of Shatili Heritage Vi IBRD / 84940 Infrastructure Investment Post Open - National 75,000.00 0.00 Canceled 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 cation Selection llage; and Arrangement of Ea st Caucasus Trekking Route/ Mountain Huts Page 5 IBRD/RDPIII/CS/QCBS/09-201 9 / Detailed Designs and Con struction Supervision for the Sustainable Conservation an Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 700,000.00 0.00 Canceled 2019-05-15 2019-06-27 2019-06-05 2019-05-06 2019-07-10 2019-08-09 2019-08-30 2019-09-13 2019-09-27 2022-08-12 d Facilities Development for Based Selection l Truso Protected Landscape (i ncluding Conservation of the Historic Fortress of the Zakag ori Complex) IBRD/RDPIII/CS/QCBS/10-201 9 / Preparation of Detailed D esign and Construction Super Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 350,000.00 0.00 Canceled 2019-06-10 2019-09-13 2019-07-01 2019-09-19 2019-07-29 2019-11-26 2019-08-28 2019-12-25 2019-09-18 2020-03-27 2019-10-12 2020-04-27 2019-11-02 2021-12-21 vision for the Sustainable Pre Based Selection l servation, Facilities Develop ment and Upgrading of Tbilisi National Park IBRD/RDPIII/CS/CQS/23-2019 / Preparation of Mtskheta Arc Consultant Qualifi Open - Internationa IBRD / 84940 Institutional Development Post 250,000.00 0.00 Canceled 2019-06-14 2019-06-04 2019-07-05 2019-06-20 2019-08-09 2019-09-08 2019-10-13 2020-08-08 haeological Museum Expositi cation Selection l on Concept, Interior Design a nd Management Plan IBRD/RDPIII/CS/CQS/24-2019 / Development Concept, Deta iled Designs and Constructio Consultant Qualifi n Supervision for the Sustain IBRD / 84940 Institutional Development Post Open - National 200,000.00 0.00 Canceled 2019-06-25 2019-06-19 2019-07-02 2019-06-21 2019-08-15 2019-09-03 2019-09-05 2019-10-03 2020-03-31 cation Selection able Visitor Trails and Mount ain Huts for Kazbegi, Pshav-K hevsureti, and Tusheti Protec ted Areas IBRD/RDPIII/CS/QCBS/11-201 9 / Detailed Designs and Con struction Supervision for the Sustainable Conservation an Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 700,000.00 525,679.33 Signed 2019-07-22 2019-07-31 2019-07-27 2019-08-01 2019-08-31 2019-10-30 2019-09-30 2019-12-10 2019-10-21 2020-01-23 2019-11-04 2020-02-07 2019-11-18 2020-03-14 2022-10-03 d Facilities Development for Based Selection l Truso Protected Landscape (i ncluding Rehabilitation of the Historic Fortress of the Zakag ori Complex) IBRD/RDPIII/CS/CQS/25-2019 / Preparation of Mtskheta Arc Consultant Qualifi Open - Internationa IBRD / 84940 Institutional Development Post 250,000.00 88,624.10 Signed 2019-08-26 2019-09-13 2019-09-16 2019-09-17 2019-10-21 2019-12-06 2019-11-20 2020-04-29 2019-12-25 2020-04-24 2020-10-20 haeological Museum Expositi cation Selection l on Concept, Interior Design a nd Management Plan IBRD/RDPIII/CS/QCBS/12-201 9 / Preparation of Stepantsmi Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 150,000.00 0.00 Canceled 2019-12-02 2020-01-17 2019-12-23 2020-01-27 2020-02-05 2020-03-04 2020-04-03 2020-05-08 2020-06-12 2021-04-08 nda Museum Exposition Conc Based Selection l ept, Interior Design and Man agement Plan IBRD/RDPIII/CS/QCBS/13-202 Quality And Cost- Open - Internationa 0 / Project Results Monitoring IBRD / 84940 Institutional Development Post 250,000.00 261,409.86 Signed 2020-03-18 2020-03-25 2020-04-08 2020-07-16 2020-05-13 2020-09-25 2020-06-10 2020-10-26 2020-07-10 2020-12-15 2020-08-07 2021-01-22 2020-09-04 2021-02-18 2022-12-23 Based Selection l & Evaluation for RDP3 - II Pha se IBRD/RDPIII/CS/QCBS/14-202 0 / Preparation of Detailed D Quality And Cost- Open - Internationa esign Documentation for Juta IBRD / 84940 Institutional Development Post 200,000.00 315,032.50 Signed 2020-03-25 2020-06-08 2020-04-15 2020-06-15 2020-05-29 2020-08-21 2020-06-26 2020-09-22 2020-07-26 2020-10-07 2020-08-30 2020-10-16 2020-10-04 2020-10-27 2021-10-04 Based Selection l -Roshka-Arkhoti-Shatili-Tushe ti Mountain Huts and Supervi sion IBRD/RDPIII/CS/QCBS/15-202 0 / Preparation of Museum E xposition Concept, Interior D Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 150,000.00 0.00 Canceled 2020-04-15 2020-08-06 2020-05-06 2020-08-10 2020-06-19 2020-10-21 2020-07-17 2020-11-04 2020-08-16 2021-01-27 2020-09-20 2020-10-25 2020-11-12 esign and management plan Based Selection l for the “New Cavalry House” (Cavalry Corps) as the Museu m of Decorative-Applied Arts IBRD/RDPIII/CS/QCBS/16-202 0 / Preparation of Detailed D Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 135,000.00 180,476.31 Signed 2020-06-15 2020-09-22 2020-07-06 2020-09-29 2020-08-19 2020-12-24 2020-09-16 2021-03-31 2020-10-16 2021-06-15 2020-11-20 2021-07-30 2020-12-25 2021-10-12 2021-06-23 esign Documentation for Dav Based Selection l id Kakabadze Fine Art Gallery in Kutaisi IBRD/RDPIII/CS/QCBS/17-202 / Preparation of Detailed Desi Quality And Cost- Open - Internationa IBRD / 84940 Institutional Development Post 250,000.00 317,456.94 Signed 2020-11-16 2020-11-20 2020-12-07 2020-11-24 2021-01-20 2021-06-09 2021-02-17 2021-07-19 2021-03-19 2021-09-14 2021-04-23 2021-10-01 2021-05-28 2021-11-26 2021-09-05 gn Documentation for Histori Based Selection l c Houses in Abastumani - II P hase IBRD/RDPIII/CS/QCBS/15-202 0-2 / Consultancy Service for Preparation of Museum Expo Quality And Cost- sition Concept, Interior Desig IBRD / 84940 Institutional Development Post 185,000.00 0.00 Canceled 2021-04-07 2021-04-12 2021-04-28 2021-04-13 2021-06-11 2021-08-24 2021-07-09 2021-10-01 2021-08-08 2021-12-28 2021-09-12 2021-10-17 2021-11-04 Based Selection n and management plan for t he “New Cavalry House” (Ca valry Corps) as the Museum of Decorative-Applied Arts IBRD/RDPIII/CS/QCBS/18-202 1 / Abastumani National Astr Quality And Cost- Open - Internationa ophysical Observatory New T IBRD / 84940 Institutional Development Post 305,000.00 0.00 Canceled 2021-09-02 2021-08-25 2021-09-23 2021-09-22 2021-11-06 2021-12-04 2022-01-03 2022-01-31 2022-02-28 2022-05-29 Based Selection l echnological and Interactive Science Museum Content de velopment IBRD/RDPIII/CS/QCBS/19-202 Quality And Cost- Open - Internationa 1 / Abastumani Observatory IBRD / 84940 Institutional Development Post 445,000.00 0.00 Signed 2022-04-22 2022-04-20 2022-05-13 2022-04-28 2022-06-26 2022-07-21 2022-07-24 2022-09-29 2022-08-23 2022-11-11 2022-09-20 2022-12-01 2022-10-18 2023-01-16 Based Selection l Astronomical Multimedia Spa ce IBRD/RDPIII/CS/LCS/03-2023 / Project Audit of RDP3, SRMI Least Cost Selecti Open - Internationa IBRD / 84940 Institutional Development Post 150,000.00 0.00 Signed 2023-02-15 2023-02-07 2023-02-15 2023-02-22 2023-02-09 2023-03-15 2023-03-24 2023-04-05 2023-04-04 2023-04-19 2023-04-10 2023-05-03 2026-06-01 DP-AF and Municipal Develop on l ment Fund of Georgia (as an Entity) IBRD/RDPIII/CS/CQS/10-2016 / Preparation of Detailed Desi Consultant Qualifi gn Documentation for Arrang IBRD / 84940 Infrastructure Investment Post Open - National 30,000.00 62,394.81 Signed 2017-02-17 2016-12-02 2017-03-10 2017-04-23 2017-03-23 2017-05-23 2017-05-22 2017-06-27 2017-05-24 2017-11-14 cation Selection ement of Tourist Infrastructur e and Urgent Restoration Wo rks for Zarzma Monastery IBRD/RDPIII/CS/CQS/13-2016 / Preparation of Resettlement Action Plan / Abbreviated Res ettlement Action Plan for Urb Consultant Qualifi IBRD / 84940 Infrastructure Investment Post Open - National 24,000.00 24,470.49 Completed 2017-01-05 2017-01-22 2017-01-26 2017-03-11 2017-03-14 2017-04-10 2017-03-14 2017-05-15 2017-04-06 2018-11-13 2018-11-30 an Regeneration of historical cation Selection streets in Dusheti; Urban reg eneration of Abastumani and Arrange of tourism infrastruc ture at Ananuri castle Sub-Pr ojects Page 6 IBRD/RDPIII/CS/CQS/09-2016 / Design Preparation for Rest Consultant Qualifi oration of Saro Darbazi Hous IBRD / 84940 Infrastructure Investment Post Open - National 150,000.00 0.00 Canceled 2017-03-20 2017-04-10 2017-05-24 2017-06-23 2017-07-28 2018-01-24 cation Selection es, Rehabilitation of Access R oad and Tourism Infrastructu re IBRD/RDPIII/CS/CQS/12-2016 / Training course in Microsoft Consultant Qualifi IBRD / 84940 Institutional Development Post Open - National 3,000.00 4,707.62 Completed 2016-12-05 2016-12-06 2016-12-26 2017-02-08 2017-09-15 2017-03-10 2017-10-03 2017-04-14 2017-10-03 2017-06-13 2017-12-25 Project for Donor Relations a cation Selection nd Project Management Unit of MDF IBRD/RDPIII/CS/QCBS/03-201 Quality And Cost- Open - Internationa 6 / Performance monitoring a IBRD / 84940 Institutional Development Post 400,000.00 0.00 Canceled 2017-10-20 2017-11-10 2017-12-24 2018-01-21 2018-02-20 2018-03-27 2018-05-01 2019-05-01 Based Selection l nd evaluation activities IBRD/RDPIII/CS/CQS/05-2016 / Preparation of detailed proj Consultant Qualifi ect documentation for Mtskh IBRD / 84940 Infrastructure Investment Post Open - National 76,450.00 88,758.87 Completed 2016-09-02 2016-06-01 2016-09-23 2016-11-06 2016-08-22 2016-12-06 2016-08-24 2017-01-10 2016-08-24 2017-07-09 2020-09-30 cation Selection eta Archeological Museum ac cording to UNESCO recomme ndations IBRD/RDPIII/CS/CQS/07-2016 / Preparation of Detailed Engi Consultant Qualifi neering Design for rehabilitat IBRD / 84940 Infrastructure Investment Post Open - National 20,000.00 11,908.69 Completed 2017-03-20 2017-02-24 2017-04-10 2017-05-24 2017-03-23 2017-06-23 2017-04-20 2017-07-28 2017-04-21 2017-10-11 2017-06-30 cation Selection ion of an access road to Zeda zeni Monastery Complex in M tskheta Municipality IBRD/RDPIII/CS/LCS/01-2017 Least Cost Selecti Open - Internationa IBRD / 84940 Institutional Development Post 100,000.00 0.00 Canceled 2017-04-17 2017-05-08 2017-06-21 2017-07-19 2017-08-18 2017-09-22 2017-10-27 2018-04-25 / Project audit on l IBRD/RDPIII/CS/QCBS/01-201 5 / Consulting Services for Su Consultant Qualifi Open - Internationa pervision of Civil Works to be IBRD / 84940 Infrastructure Investment Prior 4,000,000.00 4,409,584.48 Terminated 2016-03-01 2016-03-03 cation Selection l implemented under the Regi onal Development Project III (RDPIII) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SRMIDP/RDPIII/CS/IC/01-201 6 / Disbursement Assistant of the MDF for World Bank finan Individual Consult ced projects (3 years assign IBRD / 84940 Institutional Development Post Open - National 21,130.00 74,142.95 Signed 2016-10-13 2016-07-06 2016-11-10 2016-10-25 2016-11-25 2016-10-25 2016-12-31 2016-10-27 2019-12-31 ant Selection ment). The first 18 months of the Consultant's fee will be fi nanced under SRMIDP and th e next 18 months - under RD P III. IBRD/RDPIII/CS/SSS/02-2016- 1 / Business start-up/expansi IBRD / 84940 Institutional Development Prior Direct Selection Direct 89,167.00 0.00 Canceled 2016-09-19 2016-09-29 2016-10-27 2016-12-03 2018-05-27 on advisory service to touris m SMEs (Mtskheta-Mtianeti R egion) IBRD/RDPIII/CS/IC/03-2016 / Individual Consult IBRD / 84940 Institutional Development Post Open 108,000.00 0.00 Canceled 2016-09-13 2016-08-12 2016-11-01 2016-11-22 2016-12-27 2019-12-12 Structural Engineer Consulta ant Selection nt(s) IBRD/RDPIII/CS/IC/02-2016 / Individual Consult HVAC and Electrical Engineer IBRD / 84940 Institutional Development Post Open 90,000.00 0.00 Canceled 2016-09-13 2016-09-12 2016-11-01 2016-11-22 2016-12-27 2019-12-12 ant Selection Consultant(s) IBRD/RDPIII/CS/IC/08-2017 / Individual Consult IBRD / 84940 Institutional Development Post Open 48,000.00 55,103.82 Terminated 2017-07-10 2017-07-31 2017-08-12 2017-08-22 2017-09-12 2017-09-22 2017-09-12 2019-09-12 Cultural Heritage Architect ant Selection IBRD/RDPIII/CS/IC/07-2017 / Individual Consult IBRD / 84940 Institutional Development Post Open 21,250.00 62,724.79 Terminated 2017-07-14 2017-07-06 2017-08-03 2017-07-07 2017-08-08 2017-07-07 2017-08-18 2017-07-07 2019-12-26 Procurement Assistant ant Selection IBRD/RDPIII/CS/IC/04-2016 / Individual Consult Disbursement Officer for Wor IBRD / 84940 Institutional Development Post Open - National 68,870.00 0.00 Canceled 2018-09-17 2018-10-17 2018-11-01 2018-12-05 2019-12-05 ant Selection ld Bank financed projects (3 years assignment) AUDIT/C/SSS/03-2017 / Audit IBRD / 84940 Institutional Development Post Direct Selection Direct 10,000.00 50,150.00 Completed 2018-01-30 2018-02-14 2018-02-09 2018-03-23 2018-04-15 2018-03-26 2018-05-30 2018-07-12 of 2017 fiscal year IBRD/RDPIII/CS/IC/09-2018 / Individual Consult IBRD / 84940 Institutional Development Post Open 60,000.00 0.00 Canceled 2018-03-22 2018-07-11 2018-04-24 2018-04-29 2018-05-09 2019-12-30 Engineer ant Selection IBRD/RDPIII/CS/SSS/03-2018 IBRD / 84940 Institutional Development Post Direct Selection Direct 44,000.00 56,506.02 Signed 2018-03-30 2018-03-29 2018-04-04 2018-04-07 2018-04-06 2019-12-28 / Project Manager IBRD/RDPIII/CS/SSS/04-2018 / SUPERVISION OF CIVIL WOR IBRD / 84940 Institutional Development Prior Direct Selection Direct 1,020,000.00 1,958,152.94 Signed 2018-11-15 2018-11-06 2018-11-21 2018-11-30 2018-11-24 2021-11-14 KS TO BE IMPLEMENTED UND ER THE THIRD REGIONAL DE VELOPMENT PROJECT IBRD/RDPIII/CS/IC/10-2018 / Individual Consult IBRD / 84940 Institutional Development Post Open 60,000.00 181,887.25 Signed 2018-11-26 2018-12-04 2018-12-29 2019-01-03 2019-01-08 2019-01-13 2019-01-14 2020-09-04 Engineer ant Selection IBRD/RDPIII/CS/IC/11-2019 / Consultancy to survey potent Individual Consult IBRD / 84940 Institutional Development Post Limited 400.00 1,330.00 Completed 2019-04-01 2019-04-05 2019-04-03 2019-04-05 2019-04-06 2019-04-08 2019-04-08 2019-04-08 2019-04-23 2019-05-10 ial sites and buildings for Dis ant Selection persed Hotel concept pilot IBRD/RDPIII/CS/IC/12-2019 / Individual Consult IBRD / 84940 Institutional Development Post Open 11,250.00 15,248.67 Completed 2019-05-23 2019-05-20 2019-06-23 2019-07-15 2019-06-26 2019-07-31 2019-07-01 2019-07-22 2019-12-28 2021-02-19 Project Manager ant Selection IBRD/RDPIII/CS/SSS/05-2019 / Individual technical expert- Individual Consult IBRD / 84940 Institutional Development Post Direct 22,000.00 27,553.00 Signed 2019-08-19 2019-10-02 2019-08-24 2019-10-02 2019-08-29 2019-10-02 2019-09-03 2019-12-04 2020-06-29 advisory service from the Wo ant Selection rld Heritage Center (WHC/UN ESCO) IBRD/RDPIII/CS/IC/13-2019 / Individual Consult IBRD / 84940 Institutional Development Post Open 45,500.00 22,117.12 Completed 2019-10-21 2019-10-16 2019-12-14 2019-12-02 2019-12-17 2019-12-02 2019-12-23 2019-12-02 2022-12-27 2020-12-02 Architect ant Selection IBRD/RDPIII/CS/IC/14-2019 / Individual Consult IBRD / 84940 Institutional Development Post Open 60,000.00 35,629.52 Completed 2019-12-02 2020-01-20 2020-01-13 2020-03-11 2020-01-20 2020-03-13 2020-02-03 2020-03-14 2022-12-19 2022-01-01 Cultural Heritage Architect ant Selection Page 7 IBRD/RDPIII/CS/IC/15-2020 / I Individual Consult IBRD / 84940 Institutional Development Post Open 170,000.00 81,635.92 Signed 2020-04-27 2020-12-22 2020-06-08 2021-03-01 2020-06-15 2021-03-22 2020-06-29 2021-03-23 2022-12-16 nternational Expert in Museol ant Selection ogy IBRD/RDPIII/CS/SSS/06-2020 / Preparation of Stepantsmin IBRD / 84940 Institutional Development Post Direct Selection Direct 150,000.00 176,423.65 Signed 2020-04-15 2020-07-20 2020-04-21 2020-04-30 2020-06-04 2020-07-16 2020-12-01 da Museum Exposition Conce pt, Interior Design and mana gement plan IBRD/RDPIII/CS/SSS/07-2020 IBRD / 84940 Institutional Development Post Direct Selection Direct 32,000.00 31,215.19 Signed 2020-09-21 2020-09-17 2020-09-25 2020-09-18 2020-10-01 2020-09-21 2022-12-31 / Procurement Consultant IBRD/RDPIII/CS/SSS/08-2020 / Abastumani Observatory Di IBRD / 84940 Institutional Development Post Direct Selection Direct 70,800.00 0.00 Canceled 2020-11-05 2020-11-25 2020-11-11 2020-12-10 2020-12-25 2021-04-24 gital Museum Content develo pment IBRD/RDPIII/CS/IC/16-2021 / Consultant for Telescope Reh Individual Consult IBRD / 84940 Institutional Development Post Open 130,000.00 0.00 Canceled 2021-05-24 2021-06-08 2021-07-12 2021-08-02 2021-09-06 2021-12-05 abilitation in the Abastumani ant Selection Astrophysical Observatory IBRD/RDPIII/CS/IC/17-2021 / I ndividual Advisory Service fo Individual Consult IBRD / 84940 Institutional Development Post Open 250,000.00 249,782.40 Signed 2021-05-20 2021-05-19 2021-07-08 2021-08-09 2021-07-29 2021-08-09 2021-09-02 2021-08-14 2022-06-29 r promotion of selected cultu ant Selection ral heritage sites in Samtstkh e-Javakheti region IBRD/RDPIII/CS/SSS/09-2022 IBRD / 84940 Institutional Development Post Direct Selection Direct 9,027.00 9,473.70 Signed 2022-04-04 2022-04-04 2022-04-08 2022-04-11 2022-04-14 2022-04-20 2024-07-13 / Disbursement Officer IBRD/RDPIII/CS/SSS/02-2016- 2 / Business start-up/expansi IBRD / 84940 Institutional Development Prior Direct Selection Direct 140,500.00 0.00 Canceled 2016-09-19 2016-09-29 2016-10-27 2016-12-03 2018-05-27 on advisory service to touris m SMEs (Samtskhe Javakheti Region) IBRD/RDPIII/CS/IC/01-2016 / Individual Consult IBRD / 84940 Infrastructure Investment Prior Open 0.00 159,176.45 Signed 2016-06-07 2016-06-12 PROCUREMENT CONSULTANT ant Selection IBRD/RDPIII/CS/SSS/01-2015 / CULTURAL HERITAGE ADVIS ORY SERVICE TO THE NACHP (NATIONAL AGENCY FOR CUL IBRD / 84940 Infrastructure Investment Prior Direct Selection Direct 250,000.00 250,000.00 Completed 2015-10-12 2017-12-22 TURAL HERITAGE PRESERVAT ION OF GEORGIA) TO BE IMPL EMENTED UNDER THE THIRD REGIONAL DEVELOPMENT PR OJECT (RDP III) IBRD/RDPIII/CS/SSS/02-2-201 6 / Business start-up/expansi IBRD / 84940 Institutional Development Post Direct Selection Direct 140,500.00 123,379.64 Completed 2017-01-12 2016-11-21 2017-01-22 2017-01-05 2017-03-28 2017-01-24 2018-09-19 2018-09-26 on advisory service to touris m SMEs (Samtskhe Javakheti Region) IBRD/RDPIII/CS/IC/06-2016 / Individual Consult IBRD / 84940 Institutional Development Post Open 108,000.00 18,442.62 Signed 2017-01-25 2017-02-08 2017-03-15 2017-04-19 2017-04-05 2017-04-19 2017-05-10 2017-04-21 2018-05-10 Structural Engineer Consulta ant Selection nt IBRD/RDPIII/CS/SSS/02-1-201 6 / Business start-up/expansi IBRD / 84940 Institutional Development Post Direct Selection Direct 89,167.00 77,830.92 Terminated 2017-01-12 2016-11-21 2017-01-22 2017-01-05 2017-03-28 2017-01-20 2018-09-19 on advisory service to touris m SMEs (Mtskheta-Mtianeti R egion) IBRD/RDPIII/CS/IC/05- 2016 / Individual Consult IBRD / 84940 Institutional Development Post Open 90,000.00 12,295.08 Completed 2017-01-25 2017-02-08 2017-03-15 2017-04-05 2017-04-21 2017-05-10 2017-04-20 2018-05-10 2019-04-24 HVAC and Electrical Engineer ant Selection Consultant Page 8 PROCUREMENT PLAN Project information: Morocco-Resilient and Sustainable Water in Agriculture (P175747) Project Implémentation agency: Office régional de mise en valeur agricole de Tadla Date of the Procurement Plan: June 15, 2022 Period covered by this Procurement Plan: June 2022-Decenber 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Decree No 2-12-349 du 20mars 2013, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. To ensure broad consistency with the Procurement Guidelines, the following provisions will apply when using NCB under this project. Said procedures shall ensure that, inter alia: • The bidding documents include explicitly the bid evaluation method, award criteria and bidder qualification criteria. • Technical, administrative, and financial envelopes are opened immediately after the bid opening session has started and prices are read aloud. • The bids are evaluated based on the price and any other criteria expressed either in pass/fail terms or in monetary terms. • Contracts are awarded to the qualified bidder who has submitted the least-cost evaluated and substantially responsive bid as stipulated in the bidding document; and When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan. Works: is applicable for those contracts identified in the Procurement Plan. PROCUREMENT Morocco : Resilient and Sustainable Water in Agriculture PLAN General Information Country: Morocco 2022-06-16 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175747 GPN Date: Project Name: Resilient and Sustainable Water in Agriculture Loan / Credit No: IBRD / 93640 Regional Agricultural Development Office Tadla Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Request for Bids - 3/DA / Travaux de constructi Component 2: Modernization Single Stage - One E Small Works SPD 2023-04-1 on de l'Ouvrage de régularisa IBRD / 93640 of Irrigation and Drainage se Post Request for Bids Open - National 6,490,000.00 0.00 Signed 2022-07-01 2022-09-28 2022-07-06 2022-08-17 2022-10-20 2022-09-16 2022-10-24 2022-10-21 nvelope (1 envelope proce 9 tion hydraulique (Composant rvices ss) e 2) de l'ORMVAT 5/DA / Travaux de génie civil , de fourniture, transport et p Request for Bids - ose de conduites et équipem Component 2: Modernization Single Stage - One E Small Works SPD 10,848,370.3 2024-01-0 ents nécessaires pour la réali IBRD / 93640 of Irrigation and Drainage se Post Request for Bids Open - National 0.00 Canceled 2023-03-15 2023-03-20 2023-05-01 2023-05-31 2023-07-05 nvelope (1 envelope proce 0 1 sation de l'ouvrage de prise, rvices ss) de la conduite d'adduction et du réseau de distribution du secteur G9 1/DA / Travaux de génie civil , de fourniture, de transport, Request for Bids - et pose de conduites et équi Component 2: Modernization Single Stage - One E Small Works SPD 2024-01-0 pements nécessaires pour la IBRD / 93640 of Irrigation and Drainage se Post Request for Bids Open - National 6,000,000.00 0.00 Canceled 2023-03-15 2023-03-20 2023-05-01 2023-05-31 2023-07-05 nvelope (1 envelope proce 1 réalisation de l'ouvrage de pr rvices ss) ise, de la conduite d'adductio n et du réseau de distribution du secteur G5 Request for Bids - 07/DA-ORMVAT / Travaux de Component 2: Modernization Single Stage - One E Small Works SPD 2024-02-0 IBRD / 93640 Post Request for Bids Open - National 600,000.00 0.00 Canceled 2023-04-17 2023-04-22 2023-06-03 2023-07-03 2023-08-07 prise bornes et propriétés of Irrigation and Drainage se nvelope (1 envelope proce 3 rvices ss) Request for Bids - 12/DA / Travaux des adduct Component 2: Modernization Single Stage - One E Small Works SPD 10,600,000.0 Under Imple 2023-12-1 eurs et réseaux de distributio IBRD / 93640 of Irrigation and Drainage se Post Request for Bids Open - National 0.00 2023-02-25 2023-02-26 2023-03-02 2023-04-27 2023-04-13 2023-04-26 2023-05-13 2023-06-17 nvelope (1 envelope proce 0 mentation 4 n au niveau du secteur G9 /T rvices ss) adla Request for Bids - 15/DA / Travaux de prise bor Component 2: Modernization Single Stage - One E Small Works SPD Pending Imp 2024-04-0 IBRD / 93640 Post Request for Bids Open - National 900,000.00 0.00 2023-06-20 2023-06-25 2023-08-06 2023-09-05 2023-10-10 nes et propriétés au secteur of Irrigation and Drainage se nvelope (1 envelope proce lementation 7 G rvices ss) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 08/SMG-ORMVAT / Acquisitio n de véhicules pour le person Component 4: Project Manag Single Stage - One E IBRD / 93640 Post Request for Bids Open - National 130,000.00 0.00 Canceled 2023-03-15 2023-03-20 2023-05-01 2023-05-31 2023-07-05 2024-01-01 nel de l'ORMVAT exerçant po ement nvelope ur le projet REDI 10/SI-ORMVAT / Acquisition Component 4: Project Manag Request for Quota Single Stage - One E IBRD / 93640 Post Open - National 190,000.00 0.00 Canceled 2023-03-25 2023-05-20 2023-11-16 des logiciels et des progiciels ement tions nvelope 14/SI / Acquisition de logiciel Component 4: Project Manag Single Stage - One E Under Imple IBRD / 93640 Post Request for Bids Open - National 200,000.00 0.00 2023-05-25 2023-05-12 2023-05-30 2023-07-11 2023-08-10 2023-09-14 2024-03-12 et équipement informatique ement nvelope mentation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 6/DA / Contrôle de la qualité Component 2: Modernization de travaux du reconvertion d Request for Quota Single Stage - One E Under Imple IBRD / 93640 of Irrigation and Drainage se Post Open - National 120,000.00 0.00 2023-03-12 2023-05-07 2023-11-03 u secteur G5 et G9 (Compos tions nvelope mentation rvices ante 2) de l'ORMVAT CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 2/DA / Assistance technique pour le suivi et contrôle de q Component 2: Modernization Quality And Cost- Open - Internationa ualité de travaux de reconver IBRD / 93640 of Irrigation and Drainage se Post 1,600,000.00 0.00 Under Review 2022-07-01 2022-06-01 2022-07-22 2022-06-30 2022-09-04 2022-10-02 2022-11-01 2022-12-06 2023-01-10 2024-01-10 Based Selection l sion à l'irrigation localisé des rvices secteurs G5 et G9 (composa nte 2) 4/DA / Assistance technique pour le suivi et le contrôle de Component 2: Modernization Consultant Qualifi s IBRD / 93640 of Irrigation and Drainage se Post Limited 300,000.00 0.00 Canceled 2022-07-01 2022-07-28 2022-07-15 2022-08-14 2022-09-18 2023-03-17 cation Selection travaux de l'ouvrage de régul rvices arisation hydraulique (Compo sante 2) de l'ORMVAT 04/DA / Assistance techniqu e pour le suivi et le contrôle Component 2: Modernization Consultant Qualifi des travaux de l'ouvrage de r IBRD / 93640 of Irrigation and Drainage se Post Limited 300,000.00 0.00 Under Review 2022-11-24 2022-11-07 2022-12-08 2023-01-07 2023-02-11 2023-08-10 cation Selection égularisation hydraulique (co rvices mposante) de l'ORMVAT 11/DRH-ORMVAT / Formatio Component 4: Project Manag Consultant Qualifi IBRD / 93640 Post Open - National 25,000.00 0.00 Canceled 2023-03-30 2023-03-14 2023-04-20 2023-06-03 2023-07-03 2023-08-07 2024-02-03 n pour le personnel de l'ORM ement cation Selection VAT 22/DGRID / Assistance aux a Component 2: Modernization Quality And Cost- Open - Internationa Pending Impleme griculteurs les dossiers équip IBRD / 93640 of Irrigation and Drainage se Post 800,000.00 0.00 2023-07-28 2023-08-18 2023-10-01 2023-10-29 2023-11-28 2024-01-02 2024-02-06 2025-02-05 Based Selection l ntation ement interne rvices Page 1 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 16/DRH / Formation du pers Component 4: Project Manag Individual Consult onnel: Automatisation de la g IBRD / 93640 Post Limited 5,000.00 0.00 Under Review 2023-04-05 2023-04-05 2023-04-10 2023-05-01 2023-06-05 2023-12-02 ement ant Selection estion des reseaux d'irrigatio n sous pression 17/DRH / Regulation hydraul Component 4: Project Manag Individual Consult IBRD / 93640 Post Limited 5,000.00 0.00 Under Review 2023-04-05 2023-04-05 2023-04-10 2023-05-01 2023-06-05 2023-12-02 ique des canaux à ciel ouvert ement ant Selection 18/DRH / cadre envirennome Component 4: Project Manag Individual Consult nt et social CES (elements fo IBRD / 93640 Post Limited 5,000.00 0.00 Under Review 2023-04-05 2023-04-05 2023-04-10 2023-05-01 2023-06-05 2023-12-02 ement ant Selection ndamentaux du CES 19/DRH / l'initiative à resulta Component 4: Project Manag Individual Consult IBRD / 93640 Post Limited 5,000.00 0.00 Under Review 2023-04-05 2023-04-05 2023-04-10 2023-05-01 2023-06-05 2023-12-02 t rapide IRR ement ant Selection 20/DRH / Dimentionnement Component 4: Project Manag Individual Consult et installation d'un systéme d IBRD / 93640 Post Limited 5,000.00 0.00 Under Review 2023-04-05 2023-04-05 2023-04-10 2023-05-01 2023-06-05 2023-12-02 ement ant Selection e pompage photovoltique 23/DRH / Gestion de la main Component 4: Project Manag Individual Consult Pending Impleme IBRD / 93640 Post Limited 5,000.00 0.00 2023-07-10 2023-07-15 2023-08-05 2023-09-09 2024-03-07 tenance assisté par ordinate ement ant Selection ntation ur Page 2 PROCUREMENT PLAN (Textual Part) Project information: Borrower Country: South Africa Project name: Wildlife Conservation Bond Operation Project ID: P174097 Project Implementation agency: South African National Parks and The Eastern Cape Parks and Tourism Agency Date of the Procurement Plan: May 2022 Period covered by this Procurement Plan: 18 months 1. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, updated Nov. 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. 2. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. 3. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in RoSA’s Finance and Procurement procedure manual updated as of April 2021 such arrangements shall be subject to paragraph 5.3 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and other relevant provisions of the Procurement Regulations. 4. Any Other Special Procurement Arrangements: When approaching the national market, as agreed in the Procurement Plan, the Open Tender procedure of Public Procurement and Asset Disposal Act 2015 and Regulations 2016 country’s may be used. The specific Requirements for national open competitive procurement include the following: a. open advertising of the procurement opportunity at the national level. b. the procurement is open to eligible firms from any country. c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. d. contracts with an appropriate allocation of responsibilities, risks, and liabilities. e. publication of contract award information. f. rights for the Bank to review procurement documentation and activities. g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. Other national procurement arrangements (other than national open competitive procurement), that may be applied by the Borrower (such as limited/restricted competitive bidding, request for quotations/shopping, direct contracting), shall be consistent with the Bank’s Core Procurement Principles and ensure that the Bank’s Anti-Corruption Guidelines and Sanctions Framework and contractual remedies set out in its Legal Agreement apply. In all cases, the national procurement procedures to be used shall give due attention to quality and value for money aspects. 5. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Secondhand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable 6. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable Works: Not Applicable 7. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Not Applicable 8. Other Relevant Procurement Information: Not Identified for Now 9. Thresholds for Procurement Approaches and Methods/Prior Review (US$ millions) A. Goods, Works and Non-Consulting Services: Moderate Procurement Approaches and Methods (USD Prior Review millions) Category (USD millions) Open Open Request for Quotation International National (RfQ) Works ≥ 15 ≥ 20.0 < 20 ≤ 0.2 Goods, IT, and non-consulting ≥4 ≥5.0 <5.0 ≤ 0.1 services B. Consulting Services Category Prior Review Short List of National Consultants (USD million) (USD millions) Consulting Engineering and Construction Services Supervision Consultants ≥2 ≤ 0.3 ≤ 0.3 (Firms) Individual ≥ 0.4 NA. NA. Consultants (IC) Prior Review: The details of the Procurement review / oversight are defined in the Annex II of the Regulations for borrowers. Each activity’s review arrangement will be agreed in the Procurement Plan to be submitted and cleared in STEP by the Bank. PROCUREMENT South Africa : Wildlife Conservation Bond Operation PLAN General Information Country: South Africa 2022-05-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174097 GPN Date: Project Name: Wildlife Conservation Bond Operation Loan / Credit No: TF / B6356 South African National Parks Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure ZA-SANPARKS-294980-CW-R ment Document - FQ / Kabouga accommodatio Improved Rhino Conservatio Request for Quota Single Stage - One E 2023-01-2 TF / B6356 Post Limited 1 Envelope proce 190,000.00 107,362.91 Signed 2022-06-04 2022-06-03 2022-07-30 2022-08-17 n (APU Barracks) and gate ho n Management tions nvelope 6 ss (Non Bank-SPD use accommodation ) ZA-SANPARKS-317419-CW-R National Procure FQ / Construction of Nyathi A ment Document - Improved Rhino Conservatio Request for Quota Single Stage - One E 2023-06-0 PU manager residence ($ 12 TF / B6356 Post Limited 1 Envelope proce 210,000.00 0.00 Completed 2022-10-12 2022-10-16 2022-12-07 n Management tions nvelope 5 0 000) ss (Non Bank-SPD Construction of Nyathi JOC st ) aff house ( $ 90 000) National Procure ZA-SANPARKS-317426-CW-R ment Document - Improved Rhino Conservatio Request for Quota Single Stage - One E 2023-06-0 FQ / Main Camp accommodat TF / B6356 Post Limited 1 Envelope proce 110,000.00 0.00 Signed 2022-10-12 2022-10-16 2022-12-07 n Management tions nvelope 5 ion (10 bedroom APU Barrack ss (Non Bank-SPD s) ) ZA-SANPARKS-294989-CW-R FQ / Upgrading of existing inf rastructure Darlington at Req Request for Bids - uest Improved Rhino Conservatio Single Stage - One E Works (without pr 2023-03-2 Construction of 4room barrac TF / B6356 Post Request for Bids Open - National 330,000.00 0.00 Canceled 2022-06-09 2022-06-14 2022-07-26 2022-08-25 2022-09-29 n Management nvelope equalification) SP 8 ks at Kruidfontein D Construction of Darlington ga te house & staff house at Re quest Construction of Darlington ga te house & staff house at Chr ZA-SANPARKS-294999-CW-R istiana FQ / Construction of Nyathi A PU manager residence ($ 12 Request for Bids - 0 000) Improved Rhino Conservatio Single Stage - One E Works (without pr 2023-03-2 TF / B6356 Post Request for Bids Open - National 430,000.00 0.00 Canceled 2022-06-03 2022-06-08 2022-07-20 2022-08-19 2022-09-23 Construction of Nyathi JOC st n Management nvelope equalification) SP 2 aff house ( $ 90 000) D Construction Main Camp and Colchester staff accommodat ion ($ 220 000) ZA-SANPARKS-343244-CW-R Request for Quota FQ / Construction of barrack Improved Rhino Conservatio Request for Quota Single Stage - One E 2023-10-1 TF / B6356 Post Limited tions (Non Bank-S 110,000.00 0.00 Signed 2023-02-21 2023-02-15 2023-04-18 style accommodation for 10 n Management tions nvelope 5 PD) man unit in Colchester secti on of the park ZA-SANPARKS-343249-CW-R Request for Quota FQ / Construction and upgrad Improved Rhino Conservatio Request for Quota Single Stage - One E 2023-10-1 TF / B6356 Post Limited tions (Non Bank-S 152,000.00 0.00 Signed 2023-02-21 2023-02-15 2023-04-18 e of staff housing at Request n Management tions nvelope 5 PD) in Darlington section ZA-SANPARKS-343260-CW-R FQ / Construction of 4-bedroo Request for Quota Improved Rhino Conservatio Request for Quota Single Stage - One E 2023-10-1 m staff accommodation at Kr TF / B6356 Post Limited tions (Non Bank-S 187,000.00 0.00 Signed 2023-02-21 2023-02-15 2023-04-18 n Management tions nvelope 5 uidfontein and construction o PD) f 4 bedroom and gate house at Christiana. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZA-SANPARKS-291427-GO-D IR / 5x Toyota Hilux 2.4 GD6 Improved Rhino Conservatio TF / B6356 Post Direct Selection Direct 240,000.00 214,889.32 Completed 2022-05-30 2022-05-23 2022-06-04 2022-05-23 2022-07-09 2022-06-17 2023-01-05 SRX Double Cab 4x4, 1x Toy n Management ota Hilux 2.4 GD6 SRX Single Cab 4x4 ZA-SANPARKS-295581-GO-D IR / Procurement of Ranger U niform and Boots 45 x boots for rangers and g ate guards Improved Rhino Conservatio 105 x camouflage uniform ( TF / B6356 Post Direct Selection Direct 18,000.00 11,589.65 Completed 2022-05-23 2022-05-24 2022-05-28 2022-06-01 2022-07-02 2022-06-17 2022-12-29 n Management 3 sets per staff member for 3 5 staff members) 36 x Olive uniform for gate g uards ( 3 sets per staff mem ber for 12 staff members) ZA-SANPARKS-295008-GO-R FQ / Install cellphone booster s Install Radio Relay Stations 5x Install HYTERA base statio Improved Rhino Conservatio Request for Quota Single Stage - One E n radios (license is covered b TF / B6356 Post Limited 84,000.00 0.00 Completed 2022-10-08 2023-01-30 2022-12-03 2023-06-01 n Management tions nvelope y SANP) 6x Install HYTERA vehicle bas ed radios 30x HYTERA Hand held radio s including ear pieces Extra Radio Batteries Rugged phones ZA-SANPARKS-318262-GO-R FQ / 36x Ranger operations e quipment (Patrol equipment Improved Rhino Conservatio Request for Quota Single Stage - One E TF / B6356 Post Limited 60,000.00 0.00 Signed 2022-11-09 2022-11-23 2023-01-04 2023-07-03 per ranger) n Management tions nvelope 36x Tactical torches 36x Gaitors 36x Trauma Kits ZA-SANPARKS-318220-GO-D Improved Rhino Conservatio IR / 47x Camera trap (Cudde TF / B6356 Post Direct Selection Direct - National 20,000.00 0.00 Completed 2022-10-10 2022-10-14 2022-10-15 2022-10-21 2022-11-19 2023-05-18 n Management back) with security casing for each camera Page 1 ZA-SANPARKS-318228-GO-D IR / Purchase & connect 2x L Improved Rhino Conservatio TF / B6356 Post Direct Selection Direct - National 9,000.00 0.00 Completed 2022-10-10 2022-10-14 2022-10-15 2022-10-21 2022-11-19 2023-05-18 PR cameras for Addo heights n Management Potgieter & Gorah Gate ZA-SANPARKS-329443-GO-D Improved Rhino Conservatio IR / Solar System Installation TF / B6356 Post Direct Selection Direct - National 179,000.00 0.00 Signed 2022-12-02 2022-12-07 2022-12-07 2022-11-30 2023-01-11 2023-07-10 n Management for WCB Buildings ZA-SANPARKS-343044-GO-R Improved Rhino Conservatio Request for Quota Single Stage - One E FQ / Accommodation Equipm TF / B6356 Post Limited 35,000.00 0.00 Canceled 2022-11-27 2022-10-21 2023-01-22 2023-07-21 n Management tions nvelope ent for APU team ZA-SANPARKS-343073-GO-R Improved Rhino Conservatio Request for Quota Single Stage - One E TF / B6356 Post Limited 9,000.00 0.00 Completed 2022-12-10 2022-10-26 2023-02-04 2023-08-03 2023-01-28 FQ / Monitoring equipment n Management tions nvelope ZA-SANPARKS-342739-GO-R Improved Rhino Conservatio Request for Quota Single Stage - One E FQ / Personal Laptops for proj TF / B6356 Post Limited 14,928.93 0.00 Completed 2022-07-05 2022-06-30 2022-08-30 2023-02-26 2022-08-22 n Management tions nvelope ect team X 8 ZA-SANPARKS-318222-GO-R FQ / 3x Upper range Binocula rs for monitoring team ($200 0) Improved Rhino Conservatio Request for Quota Single Stage - One E Spotting scope + case ($100 TF / B6356 Post Open - National 9,000.00 0.00 Canceled 2022-10-15 2022-12-10 2023-06-08 n Management tions nvelope 0) Tripod for camera + scope ($ 1000) 2x Handheld bridge camera ( $2000) 6x rugged cameras for APU t ZA-SANPARKS-343043-GO-R eam ($3000) Improved Rhino Conservatio Request for Quota Single Stage - One E FQ / Office Furniture for Proje TF / B6356 Post Limited 4,100.00 0.00 Completed 2022-08-21 2022-08-16 2022-10-16 2023-04-14 n Management tions nvelope ct Manager and Procurement Officer ZA-SANPARKS-318266-GO-R FQ / Accommodation equipm ent/furniture (beds, stoves, t Improved Rhino Conservatio Request for Quota Single Stage - One E ables, chairs etc) for all acco TF / B6356 Post Limited 35,000.00 0.00 Canceled 2022-10-19 2022-10-24 2022-12-14 2023-06-12 n Management tions nvelope mmodation buildings Fusion Centre Furniture (Tabl es & Chairs) APU Manager Office Equipme nt ZA-SANPARKS-362454-GO-R Improved Rhino Conservatio Request for Quota Single Stage - One E FQ / Accommodation Equipm TF / B6356 Post Open - National 35,000.00 0.00 Completed 2022-11-27 2023-01-22 2023-07-21 n Management tions nvelope ent for APU team NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZA-SANPARKS-318213-NC-DI Improved Rhino Conservatio Under Imple R / Rental of Helicopter servi TF / B6356 Post Direct Selection Direct - National 25,000.00 0.00 2022-10-07 2022-10-14 2022-10-12 2022-10-21 2022-11-16 2023-05-15 n Management mentation ces for aerial monitoring ZA-SANPARKS-322247-NC-DI R / Fence construction and m aintenance contract for 6 mo Improved Rhino Conservatio TF / B6356 Post Direct Selection Direct - National 14,000.00 0.00 Terminated 2022-10-21 2022-10-26 2022-10-26 2022-10-29 2022-11-30 2023-05-29 nths (Darlington node, Kabou n Management ga Node, Nyathi Node constr uction & fence maintenance f or the park fence) ZA-SANPARKS-361463-NC-DI R / Fence construction and m aintenance contract for 6 mo Improved Rhino Conservatio TF / B6356 Post Direct Selection Direct - National 14,000.00 0.00 Completed 2022-11-02 2022-10-26 2022-11-03 2022-11-02 2022-12-08 2023-06-06 2023-03-05 nths (Darlington node, Kabou n Management ga Node, Nyathi Node constr uction & fence maintenance f or the park fence) ZA-SANPARKS-362448-NC-DI Improved Rhino Conservatio Pending Impl R / Helicopter Services for n TF / B6356 Post Direct Selection Direct - National 71,797.12 0.00 2022-04-01 2022-04-06 2022-05-11 2024-03-31 n Management ementation otching and aerial monitoring CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZA-SANPARKS-295603-CS-Q CBS / The parks intends to ap Improved Rhino Conservatio Quality And Cost- point a suitable, qualified an TF / B6356 Post Open - National 40,000.00 0.00 Canceled 2022-06-10 2022-05-31 2022-07-01 2022-08-14 2022-09-11 2022-10-11 2022-11-15 2022-12-20 2023-12-20 n Management Based Selection d well experienced consultan t for recruitment and selectio n of rangers. ZA-SANPARKS-298753-CS-C QS / The parks intends to ap Improved Rhino Conservatio Consultant Qualifi point a suitable, qualified an TF / B6356 Post Open - National 40,000.00 0.00 Signed 2022-06-20 2022-10-14 2022-07-11 2022-12-09 2022-08-24 2023-01-31 2022-09-23 2023-01-30 2022-10-28 2023-04-26 n Management cation Selection d well experienced consultan t for recruitment and selectio n of rangers. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) Project information: Pakistan, Punjab Urban Land Systems Enhancement Project (P172945) Project Implementation agency(ies): Board of Revenue Punjab (BOR) Punjab Land Registration Authority (PLRA) Date of the Procurement Plan: Nov 10, 2022 Period covered by this Procurement Plan: Nov, 2022 – Jun, 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in respective Public Procurement Rules, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: 1) The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or prospective bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2) For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3) The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4) Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5) Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6) No preference of any kind shall be given to national bidders in the bidding process. 7) Procurement methods that use two-envelope process and rated criteria shall be subject to Bank’s prior concurrence When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets: Not Applicable Procurement of Second Hand Goods: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods, Non Consulting Services and Works). Goods, Non Consulting Services: is not applicable, Works: is not applicable. PROCUREMENT Pakistan : Punjab Urban Land Systems Enhancement Project PLAN General Information Country: Pakistan 2022-11-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172945 GPN Date: 2022-11-10 Project Name: Punjab Urban Land Systems Enhancement Project Loan / Credit No: IDA / 70410 Punjab Land Records Authority Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PLRA-320999-GO-RFQ / D iesel Generator, Heavy Duty Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 45,882.00 0.00 Canceled 2023-01-06 2023-03-03 2023-06-01 Generator, Heavy Duty UPS, titutional Strengthening tions nvelope Air-Conditioner (1.5 ton) PK-PLRA-321342-GO-RFQ / O Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 81,230.00 0.00 Canceled 2023-03-06 2023-05-01 2023-07-30 ffice Furniture, Fixtures and F titutional Strengthening tions nvelope urnishing PK-PLRA-321010-GO-RFQ / A Integrated Land and Geospa Request for Quota Single Stage - One E Pending Impl nti-Virus Enterprise, Windows IDA / 70410 tial Information Systems and Post Open - National 25,294.00 0.00 2023-03-06 2023-05-01 2024-04-30 tions nvelope ementation Operating System, ArcGIS Se Services rver PK-PLRA-321015-GO-RFQ / D Integrated Land and Geospa igital Camera (DSLR), Video Request for Quota Single Stage - One E IDA / 70410 tial Information Systems and Post Open - National 9,265.00 0.00 Canceled 2023-01-11 2023-03-08 2023-09-04 Wall with encoder, Multimedi tions nvelope Services a Projector with Screen PK-PLRA-325890-GO-RFQ / D Digital Land Records and Ca Request for Quota Single Stage - One E IDA / 70410 Post Open - National 44,444.00 0.00 Signed 2022-12-06 2023-01-17 2023-01-31 2024-01-31 ata Entry Software dastral Maps for LRMIS tions nvelope PK-PLRA-336379-GO-RFQ / L Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 25,000.00 0.00 Signed 2023-02-01 2023-02-21 2023-03-29 2023-09-25 ED for Committee Room, Vid titutional Strengthening tions nvelope eo Screens PK-PLRA-338882-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E rinters, Heavy-duty Color Prin IDA / 70410 Post Open - National 50,000.00 0.00 Signed 2023-02-12 2023-02-21 2023-04-09 2023-10-06 titutional Strengthening tions nvelope ters, Network Printers, Mediu m Duty Printers PK-PLRA-338888-GO-RFQ / P rocurement of Office Softwar Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 32,000.00 0.00 Signed 2023-03-05 2023-05-25 2023-04-30 2024-04-29 e (annual subscriptions for W titutional Strengthening tions nvelope indows, Antivirus, MS Office, Zoom, SQL Server etc) PK-PLRA-338895-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E rocurement of Arc Editor, Arc IDA / 70410 Post Open - National 50,000.00 0.00 Signed 2023-03-05 2023-03-14 2023-04-30 2024-04-29 titutional Strengthening tions nvelope GIS Online (GIS Professional Advanced) PK-PLRA-320935-GO-RFQ / L Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 53,000.00 0.00 Canceled 2023-01-04 2023-03-01 2023-08-28 ogistic Support-Vehicles - 2X titutional Strengthening tions nvelope 1300cc PK-PLRA-338893-GO-RFQ / P rocurement of ArcGIS Enterpr Project Management and Ins Request for Quota Single Stage - One E ise Advanced Up to 4 cores o IDA / 70410 Post Open - National 98,000.00 0.00 Signed 2023-03-05 2023-03-14 2023-04-30 2024-04-29 titutional Strengthening tions nvelope f ArcGIS GIS Server (includes Fifty Cre ator User Type Licenses) PK-PLRA-346454-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E rocurement of Diesel Genera IDA / 70410 Post Limited 28,800.00 0.00 Signed 2023-03-08 2023-03-07 2023-03-30 2023-04-29 titutional Strengthening tions nvelope tor and ACs PK-PLRA-346459-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Limited 50,000.00 0.00 Signed 2023-03-10 2023-03-07 2023-04-03 2023-05-03 rocurement of Office Furnitur titutional Strengthening tions nvelope e & Fixture PK-PLRA-346463-GO-RFQ / F Project Management and Ins Request for Quota Single Stage - One E urnishing of Office Building ( IDA / 70410 Post Limited 20,000.00 0.00 Signed 2023-03-10 2023-03-07 2023-04-07 2023-05-07 titutional Strengthening tions nvelope Electrification, Renovation & other work) PK-PLRA-347591-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E rocurement of Laptops & Des IDA / 70410 Post Limited 50,000.00 0.00 Signed 2023-03-15 2023-03-07 2023-04-01 2023-04-16 titutional Strengthening tions nvelope ktop Computers PK-PLRA-321005-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 55,000.00 0.00 Canceled 2023-02-12 2023-02-20 2023-04-09 2023-10-06 rocurement of Laptops titutional Strengthening tions nvelope PK-PLRA-336387-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 65,000.00 0.00 Canceled 2023-02-12 2023-02-21 2023-04-09 2023-10-06 rocurement of Desktop Comp titutional Strengthening tions nvelope uters PK-PLRA-336373-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E hotocopiers, Photocopiers (C IDA / 70410 Post Open - National 12,000.00 0.00 Canceled 2023-02-01 2023-02-21 2023-03-29 2023-09-25 titutional Strengthening tions nvelope olored), Scanners PK-PLRA-321341-GO-RFQ / U Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 10,000.00 0.00 Canceled 2023-01-25 2023-02-21 2023-03-22 2023-09-18 PS (Desktop) titutional Strengthening tions nvelope PK-PLRA-336380-GO-RFQ / C Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 95,000.00 0.00 Canceled 2023-02-20 2023-02-21 2023-04-17 2025-04-16 onnectivity Infrastructure Set titutional Strengthening tions nvelope up PK-PLRA-336378-GO-RFQ / T Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 2,500.00 0.00 Canceled 2023-02-01 2023-02-21 2023-03-29 2023-09-25 elephone Sets titutional Strengthening tions nvelope PK-PLRA-347602-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Limited 10,000.00 0.00 Signed 2023-03-20 2023-03-13 2023-04-17 2023-05-08 rocurement of Desktop UPS titutional Strengthening tions nvelope Page 1 PK-PLRA-347603-GO-RFQ / I nstallation of CCTV Security Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Limited 10,000.00 0.00 Signed 2023-03-21 2023-03-07 2023-04-18 2023-05-03 Cameras & Electric Fence for titutional Strengthening tions nvelope security in Office Building PK-PLRA-347606-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Limited 4,000.00 0.00 Signed 2023-03-21 2023-03-07 2023-04-18 2023-05-03 rocurement of Data Storage titutional Strengthening tions nvelope PK-PLRA-319812-GO-RFB / 1. Printers, Network Printers, M edium Duty Printers, Heavy-d Project Management and Ins Request for Quota Single Stage - One E uty Colour Printer, Telephone IDA / 70410 Post Open - National 90,000.00 0.00 Canceled 2023-01-25 2023-03-22 2024-03-21 titutional Strengthening tions nvelope Set, Plotters, Photocopiers, S canners (Full Size) 2. Connectivity Infrastructure Setup (WiFi Services) PK-PLRA-347615-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Limited 10,000.00 0.00 Signed 2023-03-22 2023-03-15 2023-05-17 2023-06-16 rocurement of Photocopier titutional Strengthening tions nvelope PK-PLRA-347616-GO-RFQ / P rocurement & Installation of Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Limited 4,000.00 0.00 Signed 2023-03-25 2023-03-07 2023-05-20 2023-05-23 Biometric Attendance Device titutional Strengthening tions nvelope s & Paper Shredder PK-PLRA-347620-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E Under Imple IDA / 70410 Post Limited 55,000.00 0.00 2023-03-22 2023-05-24 2023-05-17 2023-07-16 rocurement of Server & Instal titutional Strengthening tions nvelope mentation lation PK-PLRA-347600-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Limited 15,000.00 0.00 Signed 2023-03-18 2023-03-07 2023-04-15 2023-04-30 rocurement of Telephone Set titutional Strengthening tions nvelope PK-PLRA-348693-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E rocurement of Hight Tech La IDA / 70410 Post Limited 30,000.00 0.00 Signed 2023-03-18 2023-03-13 2023-04-22 2023-05-22 titutional Strengthening tions nvelope ptops (Qty. 6) PK-PLRA-355462-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Limited 54,000.00 0.00 Signed 2023-04-19 2023-05-16 2023-05-13 2023-06-12 rocurement of Laptops & Wor titutional Strengthening tions nvelope kstations PK-PLRA-355463-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 25,000.00 0.00 Canceled 2023-04-21 2023-05-18 2023-06-01 2023-07-01 rocurement of Wide Format S titutional Strengthening tions nvelope canner PK-PLRA-355465-GO-RFQ / P Contingent Emergency Resp Request for Quota Single Stage - One E rocurement of Differential Gl IDA / 70410 Post Open - National 22,000.00 0.00 Signed 2023-04-19 2023-05-18 2023-06-19 2023-07-19 onse tions nvelope obal Positioning System (DGP S) Equipment PK-PLRA-355468-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 5,800.00 0.00 Canceled 2023-04-18 2023-05-18 2023-06-03 2023-11-30 rocurement of Digital Camer titutional Strengthening tions nvelope a (DSLR) PK-PLRA-361452-GO-RFB / P rocurement of Hyper Conver ged Infrastructure (HCI) with Project Management and Ins Single Stage - One E Under Imple Compute, Storage, Network a IDA / 70410 Post Request for Bids Open - National 460,000.00 0.00 2023-05-26 2023-05-27 2023-05-31 2023-05-29 2023-07-12 2023-08-11 2023-09-15 2023-10-21 titutional Strengthening nvelope mentation nd Private Cloud Virtualizatio n with Backup Solution. Hard ware base Servers, Network I nterconnect and SAN Storage for Backup PK-PLRA-361457-GO-RFQ / P rocurement of IT Accessories Project Management and Ins Request for Quota Single Stage - One E (External HDD & USB), UPS f IDA / 70410 Post Open - National 20,200.00 0.00 Signed 2023-05-27 2023-05-25 2023-07-22 2024-01-18 titutional Strengthening tions nvelope or PCs, Proxiy Device, Router , Switch, Access Points, LAN, WAN for Server Room PK-PLRA-361461-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 16,000.00 0.00 Signed 2023-05-26 2023-05-22 2023-07-21 2023-07-27 rocurement of 1000 CC car ( titutional Strengthening tions nvelope Qty 1) PK-PLRA-320991-GO-RFQ / M Integrated Land and Geospa Request for Quota Single Stage - One E IDA / 70410 Post Open - National 21,176.00 0.00 Canceled 2023-03-06 2023-05-01 2023-10-28 obile Office for Scanning of M tial Information Systems and tions nvelope assavees Services PK-PLRA-321014-GO-RFQ / S erver and Storage for Provinc Digital Land Records and Ca Request for Quota Single Stage - One E IDA / 70410 Post Open - National 99,999.00 0.00 Canceled 2023-03-06 2023-05-01 2023-10-28 ial Spatial Data Infrastructure dastral Maps for LRMIS tions nvelope and Upgradation of PLRA Dat a Center PK-PLRA-338919-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 14,000.00 0.00 Canceled 2023-03-05 2023-04-30 2024-04-29 rocurement of SAP B1 Softwa titutional Strengthening tions nvelope re PK-PLRA-320996-NC-RFB / Pr ocurement of High Resolutio Integrated Land and Geospa n Aerial Imagery/Mapping of Single Stage - One E Pending Impl IDA / 70410 tial Information Systems and Prior Request for Bids Open - National 2,941,176.47 0.00 2024-02-14 2024-02-19 2024-04-01 2024-05-01 2024-06-05 2024-12-02 entire Punjab (including Urba nvelope ementation Services n, Peri-Urban & Rural areas) and its processing along with orthorectification. PK-PLRA-363413-GO-RFQ / E stablishment of Monuments f Digital Land Records and Ca Request for Quota Single Stage - One E Under Imple IDA / 70410 Post Open - National 7,500.00 0.00 2023-06-13 2023-06-20 2023-08-08 2024-02-04 or Geodetic Control Network i dastral Maps for LRMIS tions nvelope mentation n Hafizabad & Lodhran Distri cts PK-PLRA-364487-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E Under Imple IDA / 70410 Post Open - National 4,000.00 0.00 2023-06-14 2023-06-16 2023-07-30 2023-08-29 rocurement of DSLR Camera titutional Strengthening tions nvelope mentation PK-PLRA-364490-GO-RFQ / P Project Management and Ins Request for Quota Single Stage - One E Under Imple IDA / 70410 Post Open - National 18,500.00 0.00 2023-06-18 2023-06-16 2023-07-29 2023-08-28 rocurement of Wide Format S titutional Strengthening tions nvelope mentation canner NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PLRA-334503-NC-RFB / Pr ocurement of Data Entry Ser Digital Land Records and Ca Open - Internationa Single Stage - One E vices for 03 Divisions of Punj IDA / 70410 Prior Request for Bids 2,000,000.00 0.00 Signed 2023-01-30 2023-02-09 2023-02-04 2023-02-11 2023-03-18 2023-03-29 2023-04-17 2023-05-16 2023-05-22 2023-06-22 2024-05-21 dastral Maps for LRMIS l nvelope ab (Divisions: Lahore, Faisalaba d, Sargodha) Page 2 PK-PLRA-334504-NC-RFB / Pr ocurement of Data Entry Ser Digital Land Records and Ca Open - Internationa Single Stage - One E vices for 03 Divisions of Punj IDA / 70410 Prior Request for Bids 2,000,000.00 0.00 Signed 2023-01-30 2023-02-09 2023-02-04 2023-02-11 2023-03-18 2023-03-29 2023-04-17 2023-05-16 2023-05-22 2023-06-22 2024-05-21 dastral Maps for LRMIS l nvelope ab (Divisions: Gujranwala, Gujra t, Rawalpindi) PK-PLRA-334505-NC-RFB / Pr ocurement of Data Entry Ser Digital Land Records and Ca Open - Internationa Single Stage - One E Under Imple vices for 04 Divisions of Punj IDA / 70410 Prior Request for Bids 2,000,000.00 0.00 2023-01-30 2023-02-09 2023-02-04 2023-02-11 2023-03-18 2023-03-29 2023-04-17 2023-05-15 2023-05-22 2024-05-21 dastral Maps for LRMIS l nvelope mentation ab (Divisions: Bahawalpur, Mult an, DG Khan, Sahiwal) PK-PLRA-329299-NC-RFB / Pr ocurement of Services for th e Archiving & Indexing of Old Digital Land Records and Ca Single Stage - One E IDA / 70410 Post Request for Bids Open - National 850,000.00 0.00 Signed 2023-01-06 2023-01-25 2023-01-11 2023-01-25 2023-02-22 2023-03-02 2023-03-24 2023-03-13 2023-04-28 2024-04-27 Registered Deeds in 03 Divisi dastral Maps for LRMIS nvelope ons of Punjab (Divisions: Lahore, Faisalaba d. Sargodha) PK-PLRA-335814-NC-RFB / Pr ocurement of Services for th Digital Land Records and Ca Single Stage - One E e Archiving & Indexing of Old IDA / 70410 Post Request for Bids Open - National 900,000.00 0.00 Signed 2023-01-30 2023-01-25 2023-02-04 2023-01-25 2023-03-18 2023-03-02 2023-04-17 2023-03-13 2023-05-22 2024-05-21 dastral Maps for LRMIS nvelope Registered Deeds in 03 Divisi ons of Punjab (Divisions: Gujr anwala, Gujrat, Rawalpindi) PK-PLRA-335816-NC-RFB / Pr ocurement of Services for th e Archiving & Indexing of Old Digital Land Records and Ca Single Stage - One E IDA / 70410 Post Request for Bids Open - National 860,000.00 0.00 Signed 2023-01-30 2023-01-25 2023-02-04 2023-01-25 2023-03-18 2023-03-02 2023-04-17 2023-03-13 2023-05-22 2024-05-21 Registered Deeds in 04 Divisi dastral Maps for LRMIS nvelope ons of Punjab (Divisions: Bah awalpur, Multan, DG Khan, S ahiwal) PK-PLRA-335822-NC-RFB / Pr ocurement of Services for Di Digital Land Records and Ca Single Stage - One E IDA / 70410 Post Request for Bids Open - National 550,000.00 0.00 Signed 2023-02-15 2023-02-11 2023-02-20 2023-02-13 2023-04-03 2023-03-14 2023-05-03 2023-03-28 2023-06-07 2023-12-04 gitization/Parcel Mapping of dastral Maps for LRMIS nvelope Hafizabad and Lodhran (Pilot ) Districts PK-PLRA-336166-NC-RFQ / Pr Integrated Land and Geospa ocurement of Services for Sa Request for Quota Single Stage - One E IDA / 70410 tial Information Systems and Post Open - National 105,000.00 0.00 Canceled 2023-02-04 2023-04-01 2023-09-28 tellite Imagery of Hafizabad a tions nvelope Services nd Lodhran (Pilot) Districts PK-PLRA-338883-NC-RFQ / Pr ocurement of Services for UA Integrated Land and Geospa Request for Quota Single Stage - One E V (Drone) Imagery of Model T IDA / 70410 tial Information Systems and Post Open - National 9,500.00 0.00 Canceled 2023-02-15 2023-04-12 2023-10-09 tions nvelope own (Gujranwala Developme Services nt Authority) and Sunder Ind ustrial Estate (Lahore) PK-PLRA-335818-NC-RFQ / Pr Integrated Land and Geospa ocurement of Services for UA Request for Quota Single Stage - One E IDA / 70410 tial Information Systems and Post Open - National 73,000.00 0.00 Canceled 2023-02-04 2023-04-01 2023-09-28 V (Drone) Imagery of Hafizab tions nvelope Services ad and Lodhran (Pilot) Distric ts PK-PLRA-347442-NC-RFQ / Pr Integrated Land and Geospa Request for Quota Single Stage - One E ocurement of Services for Sa IDA / 70410 tial Information Systems and Post Limited 95,000.00 0.00 Signed 2023-03-15 2023-03-13 2023-04-11 2023-10-08 tions nvelope tellite Imagery of Hafizabad Services (Pilot) District PK-PLRA-347444-NC-RFQ / Pr Integrated Land and Geospa Request for Quota Single Stage - One E ocurement of Services for Sa IDA / 70410 tial Information Systems and Post Limited 95,000.00 0.00 Signed 2023-03-15 2023-03-13 2023-05-03 2023-10-30 tions nvelope tellite Imagery of Lodhran (Pil Services ot) District PK-PLRA-347447-NC-RFQ / Pr Integrated Land and Geospa Request for Quota Single Stage - One E ocurement of Services for UA IDA / 70410 tial Information Systems and Post Open - National 50,000.00 0.00 Signed 2023-03-15 2023-03-14 2023-05-08 2023-11-04 tions nvelope V (Drone) Imagery of Hafizab Services ad (Pilot) District PK-PLRA-321007-NC-RFQ / H iring of firm for operational s Project Management and Ins Request for Quota Single Stage - One E IDA / 70410 Post Open - National 83,000.00 0.00 Canceled 2022-12-06 2023-01-31 2024-01-31 ervices (Janitorial, Security a titutional Strengthening tions nvelope nd Running errands) of the p roject PK-PLRA-321016-NC-RFQ / H iring of Firm for Trainings an Project Management and Ins Request for Quota Single Stage - One E d Workshops, Model Studies, IDA / 70410 Post Open - National 16,340.00 0.00 Canceled 2023-03-06 2023-05-01 2024-04-30 titutional Strengthening tions nvelope Exposure Visits, International Trainings, Desk Review PK-PLRA-361484-NC-RFQ / Pr Integrated Land and Geospa Request for Quota Single Stage - One E ocurement of Drone (UV) Ima IDA / 70410 tial Information Systems and Post Open - National 20,000.00 0.00 Signed 2023-05-29 2023-05-25 2023-07-22 2024-01-18 tions nvelope gery for Lodhran District Services PK-PLRA-320994-NC-RFQ / D Integrated Land and Geospa Request for Quota Single Stage - One E IDA / 70410 Post Open - National 58,824.00 0.00 Canceled 2023-01-11 2023-03-08 2024-03-07 igitization of Deeds Registry tial Information Systems and tions nvelope Services CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PLRA-326170-CS-CQS / B usiness requirements and Sy Digital Land Records and Ca Consultant Qualifi Pending Impleme IDA / 70410 Post Open - National 58,824.00 0.00 2023-03-01 2023-03-22 2023-05-05 2023-06-04 2023-07-09 2024-07-08 stem Requirements specifica dastral Maps for LRMIS cation Selection ntation tion (LRMIS Imrovement) PK-PLRA-326118-CS-CQS / G Integrated Land and Geospa Consultant Qualifi Pending Impleme eodetic Network Densificatio IDA / 70410 tial Information Systems and Post Open - National 294,118.00 0.00 2023-03-01 2023-03-22 2023-05-05 2023-06-04 2023-07-09 2024-07-08 cation Selection ntation n & Technical Design Services PK-PLRA-326653-CS-QCBS / Integrated Land and Geospa Consulting Services for Devel Quality And Cost- Open - Internationa Pending Impleme IDA / 70410 tial Information Systems and Prior 1,176,471.00 0.00 2023-03-01 2023-03-31 2023-05-14 2023-06-25 2023-07-25 2023-08-29 2023-10-03 2024-10-02 opment of PSDI portal, PSDI f Based Selection l ntation Services ramework and policy PK-PLRA-326188-CS-CQS / Hi Project Management and Ins Consultant Qualifi ring of consultancy firm for le IDA / 70410 Post Open - National 29,412.00 0.00 Canceled 2023-03-01 2023-03-22 2023-05-05 2023-06-04 2023-07-09 2024-07-08 titutional Strengthening cation Selection gal and regulatory support PK-PLRA-319863-CS-QCBS / Integrated Land and Geospa Quality And Cost- Under Implement Hiring of Consulting Firm for IDA / 70410 tial Information Systems and Post Open - National 345,685.00 0.00 2023-03-01 2023-05-19 2023-03-22 2023-05-26 2023-05-05 2023-06-02 2023-07-02 2023-08-06 2023-09-10 2024-09-09 Based Selection ation PSDI Base Map Development Services Page 3 PK-PLRA-348687-CS-LCS / Hi Project Management and Ins Least Cost Selecti Under Implement IDA / 70410 Post Open - National 44,000.00 0.00 2023-03-15 2023-05-03 2023-04-05 2023-05-08 2023-04-29 2023-06-19 2023-05-01 2023-05-15 2023-06-12 2023-07-17 2025-07-16 ring of Internal Audit Firm titutional Strengthening on ation PK-PLRA-338898-CS-CQS / Pr ocurement of Consulting Fir Digital Land Records and Ca Consultant Qualifi Pending Impleme IDA / 70410 Post Open - National 250,000.00 0.00 2023-09-29 2023-10-20 2023-12-03 2024-01-02 2024-02-06 2025-02-05 m for Data Standardization A dastral Maps for LRMIS cation Selection ntation cross Multiple Agencies INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PLRA-335824-CS-INDV / P rocurement of Individual Con Project Management and Ins Individual Consult IDA / 70410 Post Open - National 64,000.00 0.00 Signed 2023-02-15 2023-02-14 2023-04-05 2023-03-13 2023-04-26 2023-04-03 2023-05-31 2025-05-30 sultant-Data Center, Data Mi titutional Strengthening ant Selection gration and System Manage ment Specialist PK-PLRA-335826-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 7,000.00 0.00 Signed 2023-02-15 2023-02-15 2023-04-05 2023-03-13 2023-04-26 2023-05-15 2023-05-31 2024-05-30 titutional Strengthening ant Selection sultant-Revenue Officer (1) f or Pilot Districts PK-PLRA-319957-CS-INDV / P Project Management and Ins Individual Consult IDA / 70410 Post Open - National 66,706.00 0.00 Canceled 2022-12-01 2022-11-16 2023-01-19 2023-02-09 2023-03-16 2024-03-15 rocurement Specialist titutional Strengthening ant Selection PK-PLRA-319979-CS-INDV / Project Management and Ins Individual Consult IDA / 70410 Post Open - National 29,647.00 0.00 Canceled 2022-12-01 2023-01-19 2023-02-09 2023-03-16 2024-03-15 Monitoring and Evaluation Sp titutional Strengthening ant Selection ecialist PK-PLRA-319954-CS-INDV / F Project Management and Ins Individual Consult IDA / 70410 Post Open - National 74,118.00 0.00 Canceled 2022-12-01 2022-11-16 2023-01-19 2023-02-09 2023-03-16 2024-03-15 inancial Management Special titutional Strengthening ant Selection ist PK-PLRA-319967-CS-INDV / Project Management and Ins Individual Consult IDA / 70410 Post Open - National 81,529.00 0.00 Canceled 2022-12-01 2022-11-17 2023-01-19 2023-02-09 2023-03-16 2024-03-15 GIS Specialist titutional Strengthening ant Selection PK-PLRA-319975-CS-INDV / I Project Management and Ins Individual Consult IDA / 70410 Post Open - National 44,471.00 0.00 Canceled 2022-12-01 2023-01-19 2023-02-09 2023-03-16 2024-03-15 nternal Auditor titutional Strengthening ant Selection PK-PLRA-319953-CS-INDV / L Project Management and Ins Individual Consult IDA / 70410 Post Open - National 37,059.00 0.00 Canceled 2022-12-01 2022-11-17 2023-01-19 2023-02-09 2023-03-16 2024-03-15 and Revenue Specialist titutional Strengthening ant Selection PK-PLRA-319959-CS-INDV / Project Management and Ins Individual Consult IDA / 70410 Post Open - National 59,294.00 0.00 Canceled 2022-12-01 2022-11-17 2023-01-19 2023-02-09 2023-03-16 2024-03-15 Quality Assurance Specialist titutional Strengthening ant Selection PK-PLRA-319950-CS-INDV / P Project Management and Ins Individual Consult IDA / 70410 Post Open - National 118,588.00 0.00 Canceled 2022-12-01 2023-01-19 2023-02-09 2023-03-16 2024-03-15 roject Coordinator titutional Strengthening ant Selection PK-PLRA-319977-CS-INDV / Project Management and Ins Individual Consult IDA / 70410 Post Open - National 29,647.00 0.00 Canceled 2022-12-01 2023-01-19 2023-02-09 2023-03-16 2024-03-15 Manager Logistics (OM) titutional Strengthening ant Selection PK-PLRA-319966-CS-INDV / Project Management and Ins Individual Consult IDA / 70410 Post Open - National 51,882.00 0.00 Canceled 2022-12-01 2022-11-17 2023-01-19 2023-02-09 2023-03-16 2024-03-15 Database and Network Speci titutional Strengthening ant Selection alist PK-PLRA-319962-CS-INDV / I Project Management and Ins Individual Consult IDA / 70410 Post Open - National 74,118.00 0.00 Canceled 2022-12-01 2022-11-17 2023-01-19 2023-02-09 2023-03-16 2024-03-15 CT (system applications) Spe titutional Strengthening ant Selection cialist PK-PLRA-335829-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 22,000.00 0.00 Canceled 2023-02-28 2023-02-16 2023-04-18 2023-05-09 2023-06-13 2025-06-12 titutional Strengthening ant Selection sultant-Software Developme nt Executive (1) PK-PLRA-336154-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 22,000.00 0.00 Canceled 2023-02-28 2023-02-16 2023-04-18 2023-05-09 2023-06-13 2025-06-12 titutional Strengthening ant Selection sultant-Software Developme nt Executive (5) PK-PLRA-336152-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 22,000.00 0.00 Canceled 2023-02-28 2023-02-15 2023-04-18 2023-05-09 2023-06-13 2025-06-12 titutional Strengthening ant Selection sultant-Software Developme nt Executive (4) PK-PLRA-336151-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 22,000.00 0.00 Canceled 2023-02-28 2023-02-15 2023-04-18 2023-05-09 2023-06-13 2025-06-12 titutional Strengthening ant Selection sultant-Software Developme nt Executive (3) PK-PLRA-336150-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 22,000.00 0.00 Canceled 2023-02-28 2023-02-14 2023-04-18 2023-05-09 2023-06-13 2025-06-12 titutional Strengthening ant Selection sultant-Software Developme nt Executive (2) PK-PLRA-336165-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 7,000.00 0.00 Canceled 2023-02-15 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2024-05-30 titutional Strengthening ant Selection sultant-Revenue Officer (10) for Pilot Districts PK-PLRA-336164-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 7,000.00 0.00 Canceled 2023-02-15 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2024-05-30 titutional Strengthening ant Selection sultant-Revenue Officer (9) f or Pilot Districts PK-PLRA-336163-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 7,000.00 0.00 Canceled 2023-02-15 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2024-05-30 titutional Strengthening ant Selection sultant-Revenue Officer (8) f or Pilot Districts PK-PLRA-336161-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 7,000.00 0.00 Canceled 2023-02-15 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2024-05-30 titutional Strengthening ant Selection sultant-Revenue Officer (7) f or Pilot Districts PK-PLRA-336160-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 7,000.00 0.00 Canceled 2023-02-15 2023-02-14 2023-04-05 2023-04-26 2023-05-31 2024-05-30 titutional Strengthening ant Selection sultant-Revenue Officer (6) f or Pilot Districts PK-PLRA-336159-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 7,000.00 0.00 Canceled 2023-02-15 2023-02-13 2023-04-05 2023-04-26 2023-05-31 2024-05-30 titutional Strengthening ant Selection sultant-Revenue Officer (5) f or Pilot Districts PK-PLRA-336157-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 7,000.00 0.00 Canceled 2023-02-15 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2024-05-30 titutional Strengthening ant Selection sultant-Revenue Officer (4) f or Pilot Districts Page 4 PK-PLRA-336156-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 7,000.00 0.00 Canceled 2023-02-15 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2024-05-30 titutional Strengthening ant Selection sultant-Revenue Officer (3) f or Pilot Districts PK-PLRA-336155-CS-INDV / P Project Management and Ins Individual Consult rocurement of Individual Con IDA / 70410 Post Open - National 7,000.00 0.00 Canceled 2023-02-15 2023-02-15 2023-04-05 2023-04-26 2023-05-31 2024-05-30 titutional Strengthening ant Selection sultant-Revenue Officer (2) f or Pilot Districts PK-PLRA-363400-CS-INDV / Project Management and Ins Individual Consult Under Implement Hiring of Individual Consultan IDA / 70410 Post Open - National 26,000.00 0.00 2023-06-08 2023-06-15 2023-07-27 2023-08-17 2023-09-21 2025-09-20 titutional Strengthening ant Selection ation t Software Engineer PK-PLRA-363405-CS-INDV / Project Management and Ins Individual Consult Under Implement Hiring of Individual Consultan IDA / 70410 Post Open - National 26,000.00 0.00 2023-06-09 2023-06-15 2023-07-28 2023-08-18 2023-09-22 2025-09-21 titutional Strengthening ant Selection ation t Software Engineer - 2 PK-PLRA-363406-CS-INDV / Project Management and Ins Individual Consult Under Implement Hiring of Individual Consultan IDA / 70410 Post Open - National 26,000.00 0.00 2023-06-09 2023-06-15 2023-07-28 2023-08-18 2023-09-22 2025-09-21 titutional Strengthening ant Selection ation t Software Engineer - 3 PK-PLRA-363409-CS-INDV / Project Management and Ins Individual Consult Under Implement Hiring of Individual Consultan IDA / 70410 Post Open - National 26,000.00 0.00 2023-06-09 2023-06-15 2023-07-28 2023-08-18 2023-09-22 2025-09-21 titutional Strengthening ant Selection ation t Software Engineer - 4 Page 5 Procurement Plan Colombia - Plan PAZcifico: WSS Infrastructure & Service Delivery Project P156239 I. General 1. Bank’s approval Date of the procurement Plan: Original 2016/08/29; Revision 2016/12/15 and 2017/4/19 2. Date of General Procurement Notice: Dec 13, 2016 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank will be marked in the procurement plan according to the level of risk of the agency 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P156239 issued by National Unit For The Management Of Disaster Risk – UNGRD 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) Summary 40.00 1 No Prior of the ICB (Works) Summary 54.00 09 No Post of the NCB (Works) Summary 1.00 1 No Post of the NCB (Goods) III. Selection of Consultants July 9, 2010 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank will be marked in the procurement plan according to the level of risk of the agency 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_400,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million Summary 11.6 6 Post of number of contracts that will be let under QCBS Summary 1.6 5 Post CQS, of number LCBS of contracts that will be let under other methods July 9, 2010 PROCUREMENT Colombia : CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2016-12-15 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-19 none) Project ID: P156239 GPN Date: 2016-12-13 Project Name: CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project Loan / Credit No: IBRD / 86490 National Unit for the Management of Disaster Risk Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PTSP-BIRF8649-002 / Acued Component 2. Water Supply ucto Tumaco, Nariño. Aducci and Basic Sanitation Improv Single Stage - One E 2019-06-0 IBRD / 86490 Post Request for Bids Open - National 2,973,324.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 on: suministro e instalacion d ements in the Municipality o nvelope 4 e 5.5 km de tuberia en HD de f Tumaco 20" (1 de 4) PTSP-BIRF8649-003 / Acued ucto Tumaco, Nariño. Optimi zación PTAP Buchelly (incluy Component 2. Water Supply e: construccion empate con l and Basic Sanitation Improv Single Stage - One E 2019-06-0 IBRD / 86490 Post Request for Bids Open - National 1,547,966.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 a nueva aduccion de 20", co ements in the Municipality o nvelope 4 nstruccion 4 modulos de des f Tumaco arenacion, mejoramiento sist ema dosificacion coagulante, construccion 4 modulos de fl oculacion. (2 de 4) PTSP-BIRF8649-004 / Acued ucto Tumaco, Nariño. Red m Component 2. Water Supply atriz continental: suministro and Basic Sanitation Improv Single Stage - One E 2019-06-0 IBRD / 86490 Post Request for Bids Open - National 822,003.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 e instalacion de 2229 metros ements in the Municipality o nvelope 4 de tuberia HD y suministro e f Tumaco instalacion de macromedidor es. (3 de 4) PTSP-BIRF8649-005 / Acued Component 2. Water Supply ucto Tumaco, Nariño. Sumini and Basic Sanitation Improv Single Stage - One E 2019-06-0 stro e instalacion de 12331 IBRD / 86490 Post Request for Bids Open - National 1,519,053.00 0.00 Canceled 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 ements in the Municipality o nvelope 4 metros de redes de distribuci f Tumaco on de PVC RDE 21 (4 de 4) PTSP-BIRF8649-055 / CONST RUCCION DE 7.800 M DE AD UCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMP Component 2. Water Supply LIACION DE LA PTAP BUCHEL and Basic Sanitation Improv Open - Internationa Single Stage - One E 2019-01-0 IBRD / 86490 Post Request for Bids 7,779,897.00 0.00 Canceled 2017-08-25 2017-10-17 2017-08-30 2017-10-11 2018-03-14 2017-11-10 2018-06-08 2017-12-15 LI EN 50 LPS, CONSTRUCCIO ements in the Municipality o l nvelope 9 N DE 2.231 M DE RED MATRI f Tumaco Z EN TUBERIA HD, CONSTRU CCION DE 15.298 M DE REDE S DE DISTRIBUCION EN TUBE RIA PVC-POI SEGUNDO Q PTSP-BIRF8649-045 / CONST RUCCION DE 5.500 M DE AD UCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMP Component 2. Water Supply LIACION DE LA PTAP BUCHEL and Basic Sanitation Improv Single Stage - One E 2018-09-1 IBRD / 86490 Post Request for Bids Open - National 6,862,347.00 0.00 Canceled 2017-08-25 2017-08-30 2017-10-20 2017-10-11 2017-11-10 2017-12-15 LI EN 50 LPS, CONSTRUCCIO ements in the Municipality o nvelope 1 N DE 2.231 M DE RED MATRI f Tumaco Z EN TUBERIA HD, CONSTRU CCION DE 15.298 M DE REDE S DE DISTRIBUCION EN TUBE RIA PVC - POI SEGUNDO QUI NQ PTSP-BIRF8649-018 / “Red M Component 2. Water Supply enor de  distribución de la zo and Basic Sanitation Improv Single Stage - One E 2020-05-1 IBRD / 86490 Post Request for Bids Open - National 1,724,138.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 na continental fase 2 en el M ements in the Municipality o nvelope 3 unicipio de Tumaco, Departa f Tumaco mento de Nariño” PTSP-BIRF8649-017 / “Const Component 2. Water Supply rucción segunda fase de 20” and Basic Sanitation Improv Single Stage - One E 2019-05-1 en tubería de hierro dúctil pa IBRD / 86490 Post Request for Bids Open - National 1,436,782.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 ements in the Municipality o nvelope 9 ra aducción, Municipio de Sa f Tumaco n Andrés de Tumaco, Depart amento de Nariño” PTSP-BIRF8649-014 / Constr Component 1. Water Supply Single Stage - One E 2020-09-1 ucción del sistema definitivo IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1,353,180.00 0.00 Canceled 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 nvelope 0 de disposición final de residu ements in the Municipality o os. f Guapi PTSP-BIRF8649-013 / Constr Component 1. Water Supply Single Stage - One E 12,865,288.0 2021-07-3 uccion del Sistema de Manej IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 0.00 Canceled 2018-04-02 2018-05-01 2018-06-12 2018-07-12 2018-08-16 nvelope 0 1 o de las Aguas Residuales Ca ements in the Municipality o sco Urbano f Guapi PTSP-BIRF8649-019 / Constr Component 2. Water Supply Single Stage - One E 2019-04-1 ucción nuevo relleno sanitari IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 4,281,100.00 0.00 Canceled 2018-07-01 2018-07-06 2018-08-17 2018-09-16 2018-10-21 nvelope 9 o del municipio de Tumaco ements in the Municipality o f Tumaco PTSP-BIRF8649-074 / "OBRA S DE OPTIMIZACION Y AM PLIACION DEL SISTEMA DE Component 2. Water Supply ACUEDUCTO DEL DISTRIT and Basic Sanitation Improv Single Stage - One E 13,263,597.0 9,353,680.1 2020-11-2 IBRD / 86490 Post Request for Bids Open - National Signed 2019-03-04 2019-03-07 2019-03-06 2019-04-03 2019-04-26 2019-05-03 2019-05-24 2019-06-07 2019-09-13 O ESPECIAL DE TUMACO FA ements in the Municipality o nvelope 0 6 8 SE II, COMPONENTES PARA f Tumaco EL ABASTECIMIENTO A LOS SECTORES DE CONTINENTE E ISLA TUMACO". PTSP-BIRF8649-076 / "OBRA S DE OPTIMIZACION Y AMPLI Component 2. Water Supply ACION DEL SISTEMA DE ACU and Basic Sanitation Improv Single Stage - One E 5,357,696.2 2020-07-2 IBRD / 86490 Post Request for Bids Open - National 7,700,000.00 Signed 2019-04-30 2019-06-07 2019-05-05 2019-06-04 2019-07-15 2019-06-29 2019-10-21 2019-08-03 2019-12-18 EDUCTO DEL DISTRITO ESPE ements in the Municipality o nvelope 6 8 CIAL DE TUMACO FASE I, DEP f Tumaco ARTAMENTO DE NARIÑO, CO LOMBIA" PTSP-BIRF8649-064 / Constr ucción de 7.800 m de aducci ón tubería hd 20", optimizaci Component 2. Water Supply ón y ampliación PTAP Buchell and Basic Sanitation Improv Single Stage - One E 2020-04-1 i 50 lps, construcción de 2.23 IBRD / 86490 Post Request for Bids Open - National 7,733,591.00 0.00 Canceled 2018-12-28 2019-01-02 2019-01-02 2019-02-13 2019-02-26 2019-03-15 2019-04-19 ements in the Municipality o nvelope 3 1 m red matriz tubería hd, co f Tumaco nstruccion de 15.298 m rede s de distribución tubería pvc - poi segundo quinquenio del municipio de Tumaco Page 1 PTSP-BIRF8649-083 / “OPTIM IZACION Y AMPLIACION DEL Component 1. Water Supply SISTEMA DE ACUEDUCTO DE and Basic Sanitation Improv Single Stage - One E 3,118,398.3 2021-04-0 IBRD / 86490 Post Request for Bids Open - National 4,500,000.00 Signed 2019-07-10 2019-08-30 2019-07-12 2019-10-01 2019-08-09 2019-10-28 2019-09-08 2020-03-27 2019-10-13 2017-12-19 LA CABECERA MUNICIPAL DE ements in the Municipality o nvelope 0 5 GUAPI, DEPARTAMENTO DEL f Guapi CAUCA, COLOMBIA – ETAPA I ” PTSP-BIRF8649-100 / OBRAS DE OPTIMIZACIÓN Y AMPLIAC Component 2. Water Supply IÓN DEL SISTEMA DE ACUED and Basic Sanitation Improv Single Stage - One E 2020-10-1 IBRD / 86490 Post Request for Bids Open - National 1,262,000.00 902,276.97 Signed 2020-01-10 2020-01-17 2020-01-15 2020-02-14 2020-03-04 2020-03-10 2020-04-07 2020-04-14 2020-08-21 UCTO DEL DISTRITO ESPECIA ements in the Municipality o nvelope 3 L DE TUMACO, DEPARTAMEN f Tumaco TO DE NARIÑO, COLOMBIA - FASE III ETAPA I PTSP-BIRF8649-146 / Constr National Procure Component 1. Water Supply ucción de la Fase II de acued ment Document - and Basic Sanitation Improv Single Stage - One E Pending Imp 2023-05-3 ucto GUAPI (técnico+ gestión IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 3,080,000.00 0.00 2022-05-27 2022-05-29 2022-06-26 2022-07-26 2022-08-30 ements in the Municipality o nvelope lementation 0 social+ambiental) - LICITACI ss (Non Bank-SPD f Guapi ON PUBLICA NACIONAL - LPN ) PTSP-BIRF8649-147 / Constr National Procure Component 1. Water Supply ucción de la Fase III de acued ment Document - and Basic Sanitation Improv Single Stage - One E Pending Imp 2023-04-2 ucto GUAPI (técnico+ gestión IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 2,110,000.00 0.00 2022-05-27 2022-05-29 2022-06-26 2022-07-26 2022-08-30 ements in the Municipality o nvelope lementation 8 social+ambiental) - LICITACI ss (Non Bank-SPD f Guapi ON PUBLICA NACIONAL - LPN ) National Procure PTSP-BIRF8649-152 / Constr Component 1. Water Supply ment Document - Single Stage - One E Pending Imp 2023-08-0 ucción obras cierre botadero IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 557,000.00 0.00 2022-04-29 2022-05-01 2022-05-29 2022-06-28 2022-08-02 nvelope lementation 2 barrio El Olimpico GUAPI ements in the Municipality o ss (Non Bank-SPD f Guapi ) National Procure PTSP-BIRF8649-153 / Constr Component 2. Water Supply ment Document - Single Stage - One E Pending Imp 2023-08-2 ucción de obra Fase 3 etapa IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 9,950,000.00 0.00 2022-01-20 2022-01-22 2022-02-19 2022-03-21 2022-04-25 nvelope lementation 5 2 (PTAP) ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-154 / Constr Component 2. Water Supply ment Document - Single Stage - One E Pending Imp 2023-09-2 ucción de obra Fase 4 E1 (ob IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 4,820,000.00 0.00 2022-02-16 2022-02-18 2022-03-18 2022-04-17 2022-05-22 nvelope lementation 1 ras Morro) ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-155 / Constr Component 2. Water Supply ment Document - Single Stage - One E Pending Imp 2023-09-2 ucción acueducto - Fase 4 E2 IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 740,000.00 0.00 2022-02-16 2022-02-18 2022-03-18 2022-04-17 2022-05-22 nvelope lementation 1 (Paso de aguas claras) ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-163 / Constr Component 1. Water Supply ment Document - Single Stage - One E 14,500,000.0 Pending Imp 2024-12-0 ucción alcantarillado GUAPI - IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 0.00 2023-01-10 2023-01-12 2023-02-09 2023-03-11 2023-04-15 nvelope 0 lementation 3 implementación alcantarillad ements in the Municipality o ss (Non Bank-SPD o Condominial f Guapi ) National Procure PTSP-BIRF8649-165 / Constr Component 2. Water Supply ment Document - ucción alcantarillado Tumaco and Basic Sanitation Improv Single Stage - One E 14,800,000.0 Pending Imp 2024-07-1 IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 0.00 2023-02-10 2023-02-12 2023-03-12 2023-04-11 2023-05-16 (obras derivadas del ajuste al ements in the Municipality o nvelope 0 lementation 8 ss (Non Bank-SPD Plan Maestro de Alcantarillad f Tumaco ) o) National Procure PTSP-BIRF8649-166 / Constr Component 2. Water Supply ment Document - Single Stage - One E 14,800,000.0 Pending Imp 2024-01-0 ucción piloto alcantarillado C IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 1 Envelope proce 0.00 2022-09-30 2022-10-02 2022-10-30 2022-11-29 2023-01-03 nvelope 0 lementation 3 ondominial Tumaco ements in the Municipality o ss (Non Bank-SPD f Tumaco ) National Procure PTSP-BIRF8649-149 / Constr Component 1. Water Supply ment Document - ucción del centro de restaura and Basic Sanitation Improv Single Stage - One E Pending Imp 2023-01-0 IBRD / 86490 Post Request for Bids Open - National 1 Envelope proce 430,000.00 0.00 2022-01-12 2022-01-17 2022-02-28 2022-03-30 2022-05-04 ción ambiental CRAU - LICITA ements in the Municipality o nvelope lementation 5 ss (Non Bank-SPD CION PUBLICA NACIONAL - LP f Guapi ) N GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-092 / Adquisi ción de un (1) Vehículo Comp Component 2. Water Supply actador Para La Prestación D and Basic Sanitation Improv Single Stage - One E IBRD / 86490 Post Request for Bids Open - National 154,000.00 102,817.39 Signed 2019-10-28 2019-11-29 2019-11-06 2019-12-18 2020-01-21 2020-01-17 2020-03-30 2020-02-21 2020-07-22 2020-08-19 el Servicio Público De Aseo E ements in the Municipality o nvelope n El Distrito De San Andrés D f Tumaco e Tumaco Departamento de Nariño PTSP-BIRF8649-094 / CARAC Component 3. Capacity Buil TERIZACIÓN DE AGUA CRUD ding and Institutional Streng A Y MEDICIÓN DE NIVEL ESTA Request for Quota Single Stage - One E IBRD / 86490 thening of Service Providers Post Open - National 13,800.00 11,563.31 Signed 2019-11-02 2019-12-28 2021-01-28 2020-06-25 TICO EN LOS POZOS Ccgua- tions nvelope in the Municipalities of Guap 01 - Ccgua-02, MUNICIPIO GU i and Tum aco API, DEPARTAMENTO CAUCA PTSP-BIRF8649-095 / SONDA Component 3. Capacity Buil DE NIVEL PARA MEDICIÓN DE ding and Institutional Streng Request for Quota Single Stage - One E NIVEL ESTATICO EN LOS PO IBRD / 86490 thening of Service Providers Post Open - National 5,200.00 2,240.94 Signed 2019-11-02 2019-12-28 2020-11-13 2020-06-25 tions nvelope ZOS Ccgua-01 - Ccgua-02, M in the Municipalities of Guap UNICIPIO GUAPI, DEPARTAME i and Tum aco NTO CAUCA Component 3. Capacity Buil PTSP-BIRF8649-118 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E r motobombas y accesorios h IBRD / 86490 Post Open - National 81,226.00 44,630.67 Signed 2020-07-13 2020-09-07 2020-11-04 2020-10-07 thening of Service Providers tions nvelope idráulicos in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-119 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E r tanques para almacenamie IBRD / 86490 Post Open - National 90,263.00 140,822.49 Signed 2020-07-13 2020-09-07 2020-12-10 2020-10-07 thening of Service Providers tions nvelope nto de agua in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-120 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E IBRD / 86490 Post Open - National 16,197.00 17,599.95 Signed 2020-07-13 2020-09-07 2020-11-06 2020-10-22 r moto cargueros thening of Service Providers tions nvelope in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-121 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E IBRD / 86490 Post Open - National 12,009.00 56,225.83 Signed 2020-07-13 2020-09-07 2020-11-12 2020-10-22 r filtros purificadores de agua thening of Service Providers tions nvelope in the Municipalities of Guap i and Tum aco Component 3. Capacity Buil PTSP-BIRF8649-122 / Adquiri ding and Institutional Streng Request for Quota Single Stage - One E r estructuras de soporte met IBRD / 86490 Post Open - National 38,541.00 44,630.67 Signed 2020-07-13 2020-09-07 2020-11-20 2020-10-07 thening of Service Providers tions nvelope álicas in the Municipalities of Guap i and Tum aco Page 2 PTSP-BIRF8649-160 / Adquisi Component 2. Water Supply Single Stage - One E Pending Impl ción de segundo vehículo co IBRD / 86490 and Basic Sanitation Improv Post Request for Bids Open - National 141,000.00 0.00 2022-01-31 2022-02-09 2022-03-23 2022-04-22 2022-05-27 2022-11-23 nvelope ementation mpactador ements in the Municipality o f Tumaco PTSP-BIRF8649-168 / Adquisi Component 2. Water Supply ción de equipos resultado de and Basic Sanitation Improv Single Stage - One E Pending Impl IBRD / 86490 Post Request for Bids Open - National 1,037,000.00 0.00 2022-11-16 2022-11-21 2023-01-02 2023-02-01 2023-03-08 2023-12-29 la consultoría reingenieria Bu ements in the Municipality o nvelope ementation cheli (bulldozer + pajarita) f Tumaco PTSP-BIRF8649-182 / Adquiri r un (1) vehículo compactado Component 2. Water Supply r de residuos sólidos para la and Basic Sanitation Improv Single Stage - One E Pending Impl IBRD / 86490 Post Request for Bids Open - National 136,476.00 0.00 2022-07-06 2022-07-11 2022-08-22 2022-09-21 2022-10-26 2023-04-24 prestación del servicio públic ements in the Municipality o nvelope ementation o de aseo en el Distrito de Sa f Tumaco n Andrés de Tumaco – Nariño . NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-053 / Progra Component 1. Water Supply Request for Quota Single Stage - One E ma de monitoreo de aguas s IBRD / 86490 and Basic Sanitation Improv Post Limited 17,242.00 0.00 Canceled 2017-12-27 2018-02-21 2018-05-22 tions nvelope ub-superficiales ements in the Municipality o f Guapi PTSP-BIRF8649-078 / ADQUI SICIÓN EN MODALIDAD DE A Component 3. Capacity Buil RRENDAMIENTO DE UN SOFT ding and Institutional Streng WARE INTEGRAL QUE PERMIT Request for Quota Single Stage - One E IBRD / 86490 thening of Service Providers Post Open - National 86,210.00 0.00 Canceled 2019-11-18 2020-01-16 2020-10-30 A A AGUAS DE TUMACO SA E tions nvelope in the Municipalities of Guap SP, EJECUTAR EN FORMA EFI i and Tum aco CIENTE EL CONTROL DE LOS PROCESOS COMERCIALES, C ONTABLES Y FINANCIEROS" CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Water Supply PTSP-BIRF8649-015 / Consul Quality And Cost- IBRD / 86490 and Basic Sanitation Improv Post Open - National 112,024.00 101,622.79 Signed 2017-07-01 2017-10-02 2017-07-22 2017-10-02 2017-09-04 2017-11-07 2017-10-02 2018-01-19 2017-11-01 2018-02-07 2017-12-06 2018-02-15 2018-01-10 2018-02-23 2018-08-08 toría Restauración Urbana Based Selection ements in the Municipality o f Guapi PTSP-BIRF8649-021 / Asisten Component 3. Capacity Buil cia fortalecimiento institucio ding and Institutional Streng Consultant Qualifi IBRD / 86490 Post Open - National 235,000.00 78,605.00 Signed 2018-06-01 2018-05-17 2018-06-22 2018-08-05 2018-08-31 2018-09-04 2018-12-03 2018-10-09 2018-12-03 2020-09-28 nal Aguas de Tumaco en el a thening of Service Providers cation Selection rea urbana in the Municipalities of Guap i and Tum aco Component 4. Project Manag PTSP-BIRF8649-043 / Auditor Quality And Cost- IBRD / 86490 ement and Environmental a Post Open - National 450,000.00 0.00 Canceled 2017-08-01 2017-09-01 2017-10-15 2017-11-12 2017-12-12 2018-01-16 2018-02-20 2019-02-15 ia Externa Based Selection nd Social Management PTSP-BIRF8649-001 / Interve Component 2. Water Supply ntoría integral para obras de and Basic Sanitation Improv Quality And Cost- Open - Internationa IBRD / 86490 Prior 6,266,775.00 0.00 Canceled 2016-12-14 2017-01-28 2016-12-16 2017-03-14 2017-04-13 2017-05-13 2017-06-12 2017-07-07 2023-07-06 acueducto, alcantarillado y r ements in the Municipality o Based Selection l esiduos sólidos en el Municipi f Tumaco o de Tumaco. PTSP-BIRF8649-049 / Interve Component 2. Water Supply ntoria integral para obras de and Basic Sanitation Improv Quality And Cost- Open - Internationa IBRD / 86490 Prior 5,762,334.24 4,364,033.42 Signed 2017-12-20 2017-12-21 2018-01-12 2017-12-21 2018-02-25 2018-05-28 2018-03-25 2018-09-11 2018-04-24 2019-03-27 2018-05-29 2019-08-10 2018-07-03 2019-09-13 2022-07-02 acueducto y alcantarillado y ements in the Municipality o Based Selection l residuos sòlidos en el Munici f Tumaco pio de Tumaco PTSP-BIRF8649-062 / REALIZ AR LOS ESTUDIOS Y DISEÑOS PARA LA PLANTA DE TRATAM Component 1. Water Supply IENTO AGUAS RESIDUALES D and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Post Open - National 259,310.00 0.00 Canceled 2018-06-15 2018-09-04 2018-07-06 2018-08-19 2018-09-16 2018-10-01 2018-10-19 2018-11-13 2019-06-11 EL MUNICIPIO DE GUAPI, DEP ements in the Municipality o Based Selection ARTAMENTO DEL CAUCA, EN f Guapi EL MARCO DEL FONDO PARA EL DESARROLLO DEL PLAN T ODOS SOMOS PAZCÍFICO PTSP-BIRF8649-041 / Asisten Component 3. Capacity Buil cia fortalecimiento institucio ding and Institutional Streng Consultant Qualifi IBRD / 86490 Post Open - National 235,000.00 0.00 Canceled 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2020-09-28 nal Aguas de Tumaco (para e thening of Service Providers cation Selection l piloto de la politica en el are in the Municipalities of Guap a rural) i and Tum aco PTSP-BIRF8649-022 / Imple Component 4. Project Manag Least Cost Selecti mentacion del Plan de Inform IBRD / 86490 ement and Environmental a Post Open - National 400,000.00 0.00 Canceled 2017-11-01 2018-09-13 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2018-11-09 on acion, Comunicacion y Partici nd Social Management pacion PTSP-BIRF8649-016 / Interve Component 1. Water Supply ntoria Obras Alcantarillado, A and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Prior Open - National 2,333,451.00 0.00 Canceled 2018-05-21 2018-06-11 2018-07-25 2018-08-22 2018-09-21 2018-10-26 2018-11-30 2019-11-30 cueducto y Residuos Solidos ements in the Municipality o Based Selection en Municipio de Guapi f Guapi PTSP-BIRF8649-082 / Interve ntoría técnica, administrativa Component 1. Water Supply , financiera, legal, ambiental and Basic Sanitation Improv Quality And Cost- Open - Internationa y social para los estudios, dis IBRD / 86490 Prior 2,900,000.00 1,741,709.58 Signed 2019-07-10 2019-07-17 2019-08-02 2019-08-12 2019-09-15 2020-02-17 2019-10-13 2020-05-21 2019-11-12 2020-07-22 2019-12-17 2020-09-29 2020-01-21 2020-10-16 2024-01-20 ements in the Municipality o Based Selection l eños y obras de los sistemas f Guapi de acueducto y alcantarillado y proyectos de residuos sólid os del municipio de Guapi. PTSP-BIRF8649-096 / ACOMP Component 3. Capacity Buil AÑAR A EMGUAPI S.A.S. ESP ding and Institutional Streng EN LA OPERACIÓN DE LOS SE Quality And Cost- IBRD / 86490 thening of Service Providers Post Open - National 662,000.00 377,390.55 Signed 2019-10-31 2020-05-28 2019-11-21 2020-01-04 2020-07-24 2020-02-01 2020-09-22 2020-03-02 2020-10-29 2020-04-06 2020-11-23 2020-05-11 2021-03-04 2021-04-06 RVICIOS PÚBLICOS DE ACUE Based Selection in the Municipalities of Guap DUCTO, ALCANTARILLADO Y i and Tum aco ASEO Y ESTRUCTURACIÓN D EL SERVICIO PUBICOS DE AS EO. PTSP-BIRF8649-097 / Desarr ollar la Interventoría técnica, Component 3. Capacity Buil operativa, administrativa, co ding and Institutional Streng Quality And Cost- mercial, financiera, contable, IBRD / 86490 thening of Service Providers Post Open - National 215,000.00 111,207.81 Signed 2019-10-31 2020-01-28 2019-11-21 2020-01-04 2020-01-28 2020-02-01 2020-07-15 2020-03-02 2020-10-09 2020-04-06 2020-11-09 2020-05-11 2021-01-28 2021-05-11 Based Selection ambiental, social y jurídica al in the Municipalities of Guap proyecto de acompañamient i and Tum aco o a la empresa E guapi S.A. E SP. En el municipio de Guapi – Cauca. Page 3 PTSP-BIRF8649-077 / INTERV ENTORÍA TÉCNICA, ADMINIST RATIVA, FINANCIERA, CONTA Component 3. Capacity Buil BLE, AMBIENTAL, SOCIAL Y JU ding and Institutional Streng Quality And Cost- RÍDICA PARA LA "CONSULTO IBRD / 86490 thening of Service Providers Post Open - National 211,800.00 0.00 Canceled 2019-04-30 2019-10-01 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 Based Selection RÍA DE ACOMPAÑAMIENTO E in the Municipalities of Guap N LA OPERACIÓN DE LOS SER i and Tum aco VICIOS PÚBLICOS DE ACUED UCTO, ALCANTARILLADO Y A SEO PARA EMGUAPI SAS ESP PTSP-BIRF8649-079 / FORTA Component 3. Capacity Buil LECIMIENTO Y ACOMPAÑAMI ding and Institutional Streng ENTO EN LA OPERACIÓN DE Quality And Cost- IBRD / 86490 thening of Service Providers Post Open - National 1,380,000.00 0.00 Canceled 2019-04-30 2019-10-01 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 LOS SERVICIOS PÚBLICOS DE Based Selection in the Municipalities of Guap ACUEDUCTO, ALCANTARILLA i and Tum aco DO Y ASEO DEL OPERADOR DE GUAPI - FASE I, II Y III PTSP-BIRF8649-056 / Consul Component 1. Water Supply toría de Diseño de la Planta d and Basic Sanitation Improv Quality And Cost- e Tratamiento de Aguas de R IBRD / 86490 Post Open - National 141,300.00 0.00 Canceled 2018-05-02 2019-09-27 2018-05-23 2018-07-06 2018-08-03 2018-09-02 2018-10-07 2018-11-11 2019-11-11 ements in the Municipality o Based Selection esiduales para el Sistema de f Guapi Alcantarillado del Municipio d e Guapi Component 3. Capacity Buil PTSP-BIRF8649-020 / Asegur ding and Institutional Streng Quality And Cost- amiento en la prestación de l IBRD / 86490 Post Open - National 1,800,000.00 0.00 Canceled 2018-06-01 2019-09-27 2018-06-22 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 thening of Service Providers Based Selection os servicios públicos Guapi. in the Municipalities of Guap i and Tum aco PTSP-BIRF8649-112 / Auditor ía a los Estados Financieros d Component 4. Project Manag Least Cost Selecti e Propósito Especial de Proye IBRD / 86490 ement and Environmental a Post Open - National 31,050.00 0.00 Canceled 2020-05-15 2020-05-14 2020-06-05 2020-07-19 2020-08-16 2020-09-15 2020-10-20 2020-11-24 2021-04-23 on ctos Financiados por el Banc nd Social Management o Mundial a través de présta mos PTSP-BIRF8649-137 / Consul toría para realizar el ajuste y complementación a los estud Component 1. Water Supply ios y diseños de las Etapas II and Basic Sanitation Improv Consultant Qualifi IBRD / 86490 Post Open - National 77,860.00 109,528.65 Signed 2021-04-29 2021-05-10 2021-05-20 2021-06-18 2021-07-21 2021-07-08 2021-08-10 2021-08-12 2022-03-06 2021-12-12 y III del proyecto denominad ements in the Municipality o cation Selection o “OPTIMIZACIÓN Y AMPLIACI f Guapi ÓN DEL SISTEMA DE ACUEDU CTO DE LA CABECERA MUNIC IPAL DE GUAPI, CAUCA”. PTSP-BIRF8649-142 / ESTRU CTURACIÓN DE UN NUEVO E Component 3. Capacity Buil SQUEMA DE PRESTACIÓN DE ding and Institutional Streng Quality And Cost- Under Implement LOS SERVICIOS PÚBLICOS DE IBRD / 86490 thening of Service Providers Post Open - National 334,200.00 0.00 2021-09-28 2021-09-29 2021-10-19 2021-11-17 2021-12-15 2021-12-30 2022-01-28 2022-03-04 2023-02-02 Based Selection ation ACUEDUCTO Y ALCANTARILL in the Municipalities of Guap ADO EN EL MUNICIPIO DE SA i and Tum aco N ANDRÉS DE TUMACO, DEP ARTAMENTO DE NARIÑO PTSP-BIRF8649-156 / Consul Component 2. Water Supply toria de ajustes de estudios y and Basic Sanitation Improv Quality And Cost- Pending Impleme IBRD / 86490 Post Open - National 360,000.00 0.00 2022-01-20 2022-02-10 2022-03-11 2022-04-08 2022-04-23 2022-05-08 2022-06-12 2023-02-15 diseños Plan Maestro de alca ements in the Municipality o Based Selection ntation ntarillado TUMACO f Tumaco PTSP-BIRF8649-164 / Servici Component 3. Capacity Buil os resultado de consultoría d ding and Institutional Streng Quality And Cost- Pending Impleme IBRD / 86490 Post Open - National 1,700,000.00 0.00 2022-02-24 2022-03-17 2022-04-10 2022-05-08 2022-05-23 2022-06-17 2022-07-22 2023-07-22 e fortalecimiento instituciona thening of Service Providers Based Selection ntation l y el tema de aprovechamie in the Municipalities of Guap nto i and Tum aco PTSP-BIRF8649-167 / Consul Component 2. Water Supply Quality And Cost- Open - Internationa Pending Impleme toria de estudios y diseños n IBRD / 86490 and Basic Sanitation Improv Post 489,000.00 0.00 2022-06-15 2022-07-06 2022-08-19 2022-09-16 2022-10-16 2022-11-20 2022-12-25 2023-12-25 Based Selection l ntation uevo relleno sanitario ements in the Municipality o f Tumaco PTSP-BIRF8649-161 / Ejecuci Component 3. Capacity Buil ón - Fase II. Acompañamient ding and Institutional Streng o en la recepción y operación Quality And Cost- Open - Internationa Pending Impleme IBRD / 86490 thening of Service Providers Post 461,000.00 0.00 2022-02-16 2022-03-09 2022-04-22 2022-05-20 2022-06-19 2022-07-24 2022-08-28 2023-08-28 de las obras de acueducto, al Based Selection l ntation in the Municipalities of Guap cantarillado. Diseño, estructu i and Tum aco ración e implementación de l a operación del SPA PTSP-BIRF8649-159 / Consul Component 2. Water Supply Consultant Qualifi Pending Impleme toría para inclusión social de IBRD / 86490 and Basic Sanitation Improv Post Open - National 213,000.00 0.00 2022-04-27 2022-05-18 2022-07-01 2022-07-31 2022-09-04 2023-06-04 cation Selection ntation recicladores ements in the Municipality o f Tumaco PTSP-BIRF8649-158 / Consul Component 2. Water Supply Consultant Qualifi Pending Impleme toría de estudios y diseños M IBRD / 86490 and Basic Sanitation Improv Post Open - National 285,000.00 0.00 2022-01-20 2022-02-10 2022-02-25 2022-03-12 2022-04-16 2022-10-20 cation Selection ntation ineria Bucheli TUMACO ements in the Municipality o f Tumaco PTSP-BIRF8649-151 / Consul Component 1. Water Supply Consultant Qualifi Pending Impleme toría de estudios y diseños ci IBRD / 86490 and Basic Sanitation Improv Post Open - National 245,000.00 0.00 2022-03-16 2022-04-06 2022-05-05 2022-05-25 2022-06-27 2023-02-27 cation Selection ntation erre botadero barrio El Olimp ements in the Municipality o ico GUAPI f Guapi PTSP-BIRF8649-150 / Consul Component 1. Water Supply Consultant Qualifi Under Implement toría para aprovechamiento IBRD / 86490 and Basic Sanitation Improv Post Open - National 278,000.00 0.00 2022-01-17 2022-02-21 2022-02-07 2022-03-08 2022-03-28 2022-04-30 2023-01-31 cation Selection ation de residuos orgánicos ements in the Municipality o f Guapi PTSP-BIRF8649-157 / Consul Component 2. Water Supply toria de diseños de ingenierí and Basic Sanitation Improv Consultant Qualifi Pending Impleme IBRD / 86490 Post Open - National 155,000.00 0.00 2022-02-17 2022-03-10 2022-03-25 2022-04-09 2022-05-14 2022-09-15 a y proyecto social alcantarill ements in the Municipality o cation Selection ntation ado condominial Tumaco f Tumaco PTSP-BIRF8649-162 / Ejecuci Component 3. Capacity Buil ón - Fase III. Acompañamient ding and Institutional Streng Consultant Qualifi Pending Impleme o en el diseño e implementac IBRD / 86490 thening of Service Providers Post Open - National 248,000.00 0.00 2023-01-18 2023-02-08 2023-03-24 2023-04-23 2023-05-28 2023-10-28 cation Selection ntation ión del sistema de seguimien in the Municipalities of Guap to y monitoreo de la operació i and Tum aco n PTSP-BIRF8649-169 / INTERV ENTORÍA PARA LA CONSULTO RÍA QUE TIENE COMO OBJET Component 3. Capacity Buil O LA “ESTRUCTURACIÓN DE ding and Institutional Streng Consultant Qualifi Under Implement UN NUEVO ESQUEMA DE PRE IBRD / 86490 thening of Service Providers Post Open - National 78,000.00 0.00 2022-01-21 2022-02-04 2022-02-11 2022-03-12 2022-04-01 2022-05-06 2023-05-05 cation Selection ation STACIÓN DE LOS SERVICIOS in the Municipalities of Guap PÚBLICOS DE ACUEDUCTO Y i and Tum aco ALCANTARILLADO EN EL MU NICIPIO DE SAN ANDRÉS DE TUMACO, DEPARTAMENTO D E NARIÑO”. Page 4 PTSP-BIRF8649-170 / REALIZ AR LOS ESTUDIOS PARA LA C ONCEPCIÓN DE UN SISTEMA CONDOMINIAL Component 1. Water Supply DE ALCANTARILLADO SANITA and Basic Sanitation Improv Quality And Cost- Open - Internationa Under Implement IBRD / 86490 Post 408,000.00 0.00 2022-02-14 2022-02-09 2022-03-07 2022-02-17 2022-04-05 2022-05-03 2022-05-18 2022-06-22 2022-07-27 2023-03-24 RIO Y DISEÑO DE PROYECTO ements in the Municipality o Based Selection l ation S BÁSICOS PARA SU f Guapi IMPLEMENTACIÓN EN LA CAB ECERA MUNICIPAL DE GUAPI, DEPARTAMENTO DEL CAUCA. PTSP-BIRF8649-183 / Realiza r la actualización y ajuste del Estudio de evaluación de imp Component 2. Water Supply acto ambiental y social EIAS and Basic Sanitation Improv Consultant Qualifi Under Implement IBRD / 86490 Post Open - National 61,352.00 0.00 2022-07-11 2022-07-15 2022-08-01 2022-09-14 2022-10-14 2022-11-18 2023-05-17 para la optimización del relle ements in the Municipality o cation Selection ation no sanitario de Tumaco de ac f Tumaco uerdo con lo requerido por la s salvaguardas ambientales y sociales de Banco Mundial. PTSP-BIRF8649-143 / CONSU LTORÍA PARA REALIZAR LA A CTUALIZACIÓN, AJUSTE Y CO MPLEMENTACIÓN DE LOS ES Component 1. Water Supply TUDIOS Y DISEÑOS EXISTENT and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Post Open - National 363,000.00 0.00 Canceled 2021-10-18 2021-11-08 2021-12-22 2022-01-19 2022-02-18 2022-03-25 2022-04-29 2023-01-04 ES DE ALCANTARILLADO SAN ements in the Municipality o Based Selection ITARIO Y REALIZAR LOS ESTU f Guapi DIOS PARA LA CONCEPCIÓN DE UN SISTEMA CONDOMINIA L DE ALCANTARILLADO SANI TARIO Y DISEÑO DE PROYECT OS PTSP-BIRF8649-148 / Consul toría de ajuste y complement Component 1. Water Supply ación del plan maestro de alc and Basic Sanitation Improv Quality And Cost- IBRD / 86490 Post Open - National 359,000.00 0.00 Canceled 2022-02-28 2022-03-21 2022-05-04 2022-06-01 2022-07-01 2022-08-05 2022-09-09 2023-05-30 antarillado + diseños de inge ements in the Municipality o Based Selection niería + proyecto social alca f Guapi ntarillado condominial Guapi INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-010 / Apoyar el componente social, en el D epartamento del Cauca en la Component 4. Project Manag Individual Consult implementaciòn y ejecuciòn IBRD / 86490 ement and Environmental a Post Open 21,450.78 16,386.55 Completed 2017-05-11 2017-08-16 2017-06-05 2017-06-15 2017-09-06 2017-07-05 2017-09-18 2018-07-05 2018-09-17 ant Selection del FDPTSP que adelanta co nd Social Management mo entidad ejecutora la Unid ad Nacional para la Gestiòn d el Riesgo de Desastres. PTSP-BIRF8649-009 / Liderar el componente social, en la i mplementación y ejecución d Component 4. Project Manag el Fondo para el Desarrollo d Individual Consult IBRD / 86490 ement and Environmental a Post Open 82,299.37 62,869.64 Completed 2017-05-11 2017-08-28 2017-06-11 2017-06-21 2017-09-18 2018-07-01 2017-09-18 2018-12-28 2018-09-18 el Plan Todos Somos Pazcífic ant Selection nd Social Management o que adelanta como entidad ejecutora la Unidad Nacional para la Gestión del Riesgo de Desastres. PTSP-BIRF8649-007 / Brindar apoyo al FTSP que adelanta c omo entidad ejecutora la Uni dad Nacional para la Gestión Component 4. Project Manag Individual Consult del Riesgo de Desastres, en l IBRD / 86490 ement and Environmental a Post Open 48,873.76 36,452.16 Signed 2017-06-01 2017-05-22 2017-06-16 2017-07-01 2017-06-19 2017-07-21 2017-06-27 2018-07-21 ant Selection a viabilización de proyectos d nd Social Management el componente de Agua y Sa neamiento Básico, ante el Mi nisterio de Vivienda, Ciudad y Territorio - MVCT PTSP-BIRF8649-006 / Brindar apoyo al FTSP en la coordina ción de las acciones y activid Component 4. Project Manag ades al interior del MVCT rela Individual Consult IBRD / 86490 ement and Environmental a Post Open 56,033.61 40,456.30 Signed 2017-06-01 2018-04-18 2017-06-16 2017-06-21 2018-05-03 2017-07-02 2018-05-18 2018-07-02 cionadas con el crédito para ant Selection nd Social Management dar respuesta a los requerimi entos de la Banca Multilatera l y las entidades del gobierno nacional PTSP-BIRF8649-008 / Apoyar el componente social, en el D epartamento de Nariño en la implementación y ejecución Component 4. Project Manag Individual Consult del Fondo para el Desarrollo IBRD / 86490 ement and Environmental a Post Open 21,450.78 1,660.60 Signed 2017-05-18 2017-08-22 2017-06-11 2017-06-26 2017-09-12 2017-07-16 2018-04-03 2018-07-16 ant Selection del Plan Todos Somos Pazcífi nd Social Management co que adelanta como entida d ejecutora la Unidad Nacion al para la Gestión del Riesgo de Desastres. Component 4. Project Manag PTSP-BIRF8649-024 / Apoyo Individual Consult IBRD / 86490 ement and Environmental a Post Open 17,908.97 12,960.77 Completed 2017-05-16 2017-03-22 2017-07-04 2017-07-25 2017-05-19 2017-08-29 2017-05-19 2018-02-25 2018-05-18 Administrativo (nivel técnico) ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-028 / Lider d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 99,507.79 63,711.53 Completed 2017-03-01 2017-03-01 2017-03-11 2017-04-01 2017-03-06 2017-05-06 2017-03-16 2017-11-02 2018-03-15 e Adquisiciones ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-029 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 70,938.36 48,197.86 Completed 2017-04-01 2017-03-20 2017-05-20 2017-03-22 2017-06-10 2017-04-03 2017-07-15 2017-04-04 2018-01-11 2018-04-03 alista Adquisiciones ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-033 / Lider A Individual Consult IBRD / 86490 ement and Environmental a Post Direct 93,771.65 61,167.00 Signed 2017-04-01 2017-03-22 2017-04-11 2017-03-24 2017-05-02 2017-03-28 2017-06-06 2017-04-04 2017-12-03 mbiental ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-034 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 56,458.32 36,452.16 Completed 2017-06-01 2017-08-01 2017-07-20 2017-08-08 2017-08-10 2017-08-15 2017-09-14 2017-04-04 2018-03-13 2018-04-03 alista ambiental ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-035 / Lider C Individual Consult IBRD / 86490 ement and Environmental a Post Direct 99,507.79 61,167.00 Signed 2017-03-01 2017-03-02 2017-03-11 2017-04-01 2017-03-13 2017-05-06 2017-03-16 2017-11-02 omponente Agua ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-036 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Direct 63,844.53 41,645.62 Signed 2017-04-01 2017-03-17 2017-04-11 2017-05-02 2017-03-22 2017-06-06 2018-04-05 2017-12-03 alista Proyectos Agua ant Selection nd Social Management Page 5 Component 4. Project Manag PTSP-BIRF8649-037 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 56,033.61 36,452.16 Signed 2017-06-01 2017-11-01 2017-07-20 2017-08-10 2017-11-20 2017-09-14 2017-11-20 2018-03-13 alista Proyectos RSU ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-038 / Ingenie Individual Consult IBRD / 86490 ement and Environmental a Post Open 35,053.71 16,386.55 Completed 2017-06-01 2017-07-19 2017-07-20 2017-08-10 2017-08-15 2017-09-14 2017-08-31 2018-03-13 2018-08-30 ro de apoyo (Agua Tumaco) ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-039 / Ingenie Individual Consult IBRD / 86490 ement and Environmental a Post Open 35,053.71 19,500.00 Completed 2017-06-01 2017-12-12 2017-07-20 2017-08-10 2018-01-03 2017-09-14 2017-09-25 2018-03-13 2018-09-24 ro de apoyo ( Agua Guapi) ant Selection nd Social Management Component 4. Project Manag PTSP-BIRF8649-040 / Apoyo Individual Consult IBRD / 86490 ement and Environmental a Post Open 16,742.07 12,960.77 Completed 2017-06-01 2017-06-28 2017-07-20 2017-09-12 2017-08-10 2017-09-18 2017-09-14 2017-09-22 2018-03-13 2018-09-21 Administrativo (lideres) ant Selection nd Social Management PTSP-BIRF8649-023 / Coordi Component 4. Project Manag Individual Consult nación General - LUZ AMAND IBRD / 86490 ement and Environmental a Post Direct 116,664.30 71,591.30 Signed 2017-03-01 2017-03-08 2017-03-11 2017-03-16 2017-04-01 2017-03-10 2017-05-06 2017-03-16 2017-11-02 ant Selection A PULIDO nd Social Management PTSP-BIRF8649-026 / Lider Fi Component 4. Project Manag Individual Consult nanciero - CLAUDIA AGUDEL IBRD / 86490 ement and Environmental a Post Direct 99,507.79 63,711.53 Completed 2017-03-01 2017-02-15 2017-03-11 2017-04-01 2017-03-08 2017-05-06 2017-03-16 2017-11-02 2018-03-15 ant Selection O SEDANO - Por continuidad nd Social Management de Servicios PTSP-BIRF8649-031 / Lider d Component 4. Project Manag e Planeación y Seguimiento - Individual Consult IBRD / 86490 ement and Environmental a Post Direct 99,507.79 61,063.18 Signed 2017-03-01 2017-03-08 2017-03-11 2017-03-10 2017-04-01 2017-03-13 2017-05-06 2017-03-16 2017-11-02 JUAN DE DIOS CISNEROS - - P ant Selection nd Social Management or continuidad de Servicios PTSP-BIRF8649-032 / Especi Component 4. Project Manag alista Planeación y Seguimie Individual Consult IBRD / 86490 ement and Environmental a Post Direct 67,749.98 41,574.93 Signed 2017-03-01 2017-03-08 2017-03-11 2017-03-16 2017-04-01 2017-03-22 2017-05-06 2017-03-31 2017-11-02 nto - JULIAN ANDRES VALBUE ant Selection nd Social Management NA - Por continuidad de Servi cios PTSP-BIRF8649-025 / Asisten Component 4. Project Manag te Financiero y Administrativ Individual Consult IBRD / 86490 ement and Environmental a Post Direct 37,173.93 0.00 Canceled 2017-07-03 2017-07-13 2017-08-03 2017-09-07 2018-09-02 o - BEATRIZ PARRA - Continui ant Selection nd Social Management dad de Servicios PTSP-BIRF8649-048 / Tulio f Component 4. Project Manag Individual Consult uentes Especialista en Adqui IBRD / 86490 ement and Environmental a Post Direct 49,242.00 46,194.37 Signed 2017-11-02 2017-10-23 2017-11-07 2017-10-12 2017-11-08 2017-10-20 2017-11-10 2017-11-10 2018-11-09 ant Selection siciones 2 nd Social Management Component 4. Project Manag PTSP-BIRF8649-046 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 49,242.00 0.00 Canceled 2017-10-31 2017-11-06 2017-11-09 2017-11-13 2018-11-13 alista Adquisiciones 2 ant Selection nd Social Management Component 3. Capacity Buil PTSP-BIRF8649-044 / Especi ding and Institutional Streng Individual Consult alista Fortalecimiento Instituc IBRD / 86490 Post Open 49,242.00 47,560.97 Signed 2017-08-18 2017-10-12 2017-09-01 2017-11-10 2017-09-03 2017-12-20 2017-09-17 2017-12-28 2018-09-12 thening of Service Providers ant Selection ional in the Municipalities of Guap i and Tum aco PTSP-BIRF8649-51 / IEH GRU CON-Realizar los estudios y d iseños de los proyectos priori Component 2. Water Supply zados para la optimización y and Basic Sanitation Improv ampliación del sistema de ac IBRD / 86490 Post Direct Selection Direct 792,345.00 708,875.23 Signed 2017-12-18 2018-02-20 2017-12-31 2018-02-21 2018-01-15 2018-02-23 2019-01-10 ements in the Municipality o ueducto del municipio de Tu f Tumaco maco, departamento de Nari ño, en el marco del Fondo pa ra el Desarrollo del Plan Todo s Somos PAZcífico Component 4. Project Manag PTSP-BIRF8649-054 / KPMG- IBRD / 86490 ement and Environmental a Post Direct Selection Direct 35,000.00 69,291.56 Signed 2017-12-29 2018-04-04 2018-01-08 2018-04-05 2018-03-14 2018-04-13 2018-09-10 AUDITORIA EXTERNA nd Social Management PTSP-BIRF8649-057 / Antoni Component 1. Water Supply Individual Consult o Nieto - Director de Interven IBRD / 86490 and Basic Sanitation Improv Post Direct 26,897.00 25,232.22 Signed 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-19 2018-11-03 ant Selection torìa ements in the Municipality o f Guapi PTSP-BIRF8649-058 / Ramiro Component 1. Water Supply Individual Consult Gutierrez. Especialista Electr IBRD / 86490 and Basic Sanitation Improv Post Direct 6,771.00 6,351.73 Signed 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-17 2018-11-03 ant Selection o-mecànico de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-060 / Alvaro Component 1. Water Supply Individual Consult Bravo - Especialista Geotecni IBRD / 86490 and Basic Sanitation Improv Post Direct 9,233.00 8,661.44 Signed 2018-04-26 2018-04-23 2018-04-27 2018-04-24 2018-05-02 2018-05-08 2018-05-07 2018-05-17 2018-11-03 ant Selection sta de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-059 / Eduard Component 1. Water Supply Individual Consult o Gòmez - Especialista Estruc IBRD / 86490 and Basic Sanitation Improv Post Direct 9,233.00 0.00 Canceled 2018-04-26 2018-04-27 2018-05-02 2018-05-07 2018-11-03 ant Selection tural de Interventorìa ements in the Municipality o f Guapi PTSP-BIRF8649-061 / FERNA Component 1. Water Supply Individual Consult NDO VARGAS RODRÍGUEZ. E IBRD / 86490 and Basic Sanitation Improv Post Direct 9,233.00 8,661.44 Signed 2018-05-07 2018-05-04 2018-05-08 2018-05-11 2018-05-13 2018-06-08 2018-06-12 2018-06-08 2018-12-09 ant Selection specialista Estructural de Int ements in the Municipality o erventoria. f Guapi PTSP-BIRF8649-011 / Apoyar el componente social, en el D epartamento del Chocò, en la Component 4. Project Manag Individual Consult implementaciòn y ejecuciòn IBRD / 86490 ement and Environmental a Post Open 27,082.76 0.00 Canceled 2017-04-07 2017-08-22 2017-05-02 2017-05-12 2017-06-01 2018-06-01 ant Selection del FDPTSP que adelanta co nd Social Management mo entidad ejecutora la Unid ad Nacional para la Gestiòn d el Riesgo de Desastres. PTSP-BIRF8649-012 / Apoyar el componente social, en el D epartamento del Valle en la i Component 4. Project Manag Individual Consult mplementaciòn y ejecuciòn d IBRD / 86490 ement and Environmental a Post Open 27,082.76 0.00 Canceled 2017-04-07 2017-05-02 2017-05-12 2017-06-01 2018-06-01 ant Selection el FDPTSP que adelanta com nd Social Management o entidad ejecutora la Unidad Nacional para la Gestiòn del Riesgo de Desastres. Component 4. Project Manag PTSP-BIRF8649-030 / Apoyo Individual Consult IBRD / 86490 ement and Environmental a Post Open 26,159.48 0.00 Canceled 2017-06-30 2017-07-21 2017-07-23 2017-07-27 2018-07-22 en adquisiciones ant Selection nd Social Management PTSP-BIRF8649-042 / Asisten Component 4. Project Manag Individual Consult te Financiero y Administrativ IBRD / 86490 ement and Environmental a Post Open 37,173.93 0.00 Canceled 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-06-06 ant Selection o nd Social Management Page 6 CO-UNGRD-87418-CS-INDV / Brindar apoyo jurídico en la g estión predial y catastral de l Component 1. Water Supply os bienes inmuebles que sea and Basic Sanitation Improv Individual Consult n necesarios para la viabiliza IBRD / 86490 Post Open 7,763.00 7,763.00 Signed 2018-11-30 2018-11-28 2019-01-18 2019-02-08 2019-02-05 2019-03-15 2019-02-05 2019-09-11 ements in the Municipality o ant Selection ción de los proyectos que se f Guapi ejecutan en el marco del Fon do para el Desarrollo del Plan Todos Somos Pazcífico, que a delanta como entidad PTSP-BIRF8649-063 / Liderar el componente de Agua y Sa neamiento Básico, en la impl Component 4. Project Manag ementación y ejecución del F Individual Consult IBRD / 86490 ement and Environmental a Post Open 34,200.00 34,200.00 Signed 2018-12-26 2019-02-18 2019-02-13 2019-03-06 2019-04-04 2019-04-10 2019-04-08 2019-10-07 ondo para el Desarrollo del Pl ant Selection nd Social Management an Todos Somos Pazcífico qu e adelanta como entidad eje cutora la Unidad Nacional pa ra la Gestión del Riesgo de D esastres. PTSP-BIRF8649-072 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 53,560.00 26,780.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-15 2019-03-18 2019-03-18 2020-03-12 ant Selection ontratación Pilar Valero nd Social Management PTSP-BIRF8649-073 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 53,560.00 53,560.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-15 2019-03-15 2020-03-09 ant Selection ontratación Tulio Fuentes nd Social Management PTSP-BIRF8649-075 / Especi Component 4. Project Manag Individual Consult alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Post Direct 53,560.00 26,780.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-15 2019-03-18 2019-03-18 2020-03-12 ant Selection ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-069 / Líder d Component 4. Project Manag Individual Consult e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-18 2020-03-12 ant Selection ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-065 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 83,000.00 41,500.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 el Proyecto FTSP - Recontrata ant Selection nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-067 / Líder A Component 4. Project Manag Individual Consult mbiental - Recontratación Al IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 ant Selection ejandra Catacoli nd Social Management PTSP-BIRF8649-068 / Líder Fi Component 4. Project Manag Individual Consult nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-02-25 2019-03-11 2019-03-11 2019-03-14 2019-03-18 2019-03-18 2020-03-12 ant Selection udia Agudelo nd Social Management PTSP-BIRF8649-066 / Líder d Component 4. Project Manag Individual Consult e Planeación y Seguimiento - IBRD / 86490 ement and Environmental a Post Direct 70,800.00 35,400.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-15 2020-03-12 ant Selection Luis Ignacio Alfonso nd Social Management PTSP-BIRF8649-070 / Líder S Component 4. Project Manag Individual Consult ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Post Direct 23,600.00 11,800.00 Signed 2019-03-04 2019-03-12 2019-03-11 2019-03-11 2019-03-13 2019-03-18 2019-03-18 2019-07-17 ant Selection uiz nd Social Management PTSP-BIRF8649-080 / Especi Component 4. Project Manag alista Social para la Evaluaci Individual Consult IBRD / 86490 ement and Environmental a Post Open 13,140.00 0.00 Canceled 2019-04-12 2019-07-16 2019-04-29 2019-05-10 2019-05-20 2019-07-30 ón Social de los municipios d ant Selection nd Social Management e Tumaco (Nariño) y Guapi ( Cauca) PTSP-BIRF8649-084 / Electro Mecanico - Realizar apoyo a l a Interventoría Integral de lo Component 1. Water Supply s contratos de Estudios y Dis and Basic Sanitation Improv Individual Consult IBRD / 86490 Post Open 16,000.00 9,050.40 Signed 2019-07-10 2019-06-21 2019-08-28 2019-09-27 2019-09-18 2019-09-25 2019-10-23 2019-10-01 2020-04-20 eños como interventor en los ements in the Municipality o ant Selection aspectos eléctricos y mecáni f Guapi cos de los proyectos de prein versión priorizados en el com ponente de Agua y Saneamie nto Básico. PTSP-BIRF8649-081 / Direcci ón de Interventoría Integral d Component 1. Water Supply e Estudios y Diseños de los p and Basic Sanitation Improv Individual Consult IBRD / 86490 Post Open 27,000.00 12,926.59 Signed 2019-06-25 2019-07-26 2019-08-13 2019-09-10 2019-09-03 2019-10-01 2019-10-08 2019-10-12 2020-04-05 royectos de preinversión prio ements in the Municipality o ant Selection rizados en el componente de f Guapi Agua y Saneamiento Básico en el marco del préstamo BIR F. Component 4. Project Manag PTSP-BIRF8649-085 / Líder d Individual Consult IBRD / 86490 ement and Environmental a Post Open 20,000.00 25,517.85 Signed 2019-06-21 2019-07-29 2019-08-09 2019-09-24 2019-08-30 2019-09-02 2019-10-04 2019-09-07 2020-04-01 e Seguridad FTSP ant Selection nd Social Management PTSP-BIRF8649-086 / Líder S Component 4. Project Manag Individual Consult ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Post Direct 47,200.00 39,330.50 Signed 2019-07-11 2019-07-15 2019-07-12 2019-07-23 2019-07-12 2019-08-22 2019-07-18 2019-08-23 2020-03-17 ant Selection uiz nd Social Management PTSP-BIRF8649-089 / Topogr afo - Prestación de servicios profesionales para la realizac Component 1. Water Supply ión de levantamientos topogr and Basic Sanitation Improv Individual Consult áficos requeridos para el san IBRD / 86490 Post Open 13,800.00 9,943.53 Signed 2019-08-26 2019-08-22 2019-10-14 2019-09-19 2019-11-04 2019-10-18 2019-12-09 2019-10-24 2020-03-08 ements in the Municipality o ant Selection eamiento de los predios requ f Guapi eridos para la ejecución de lo s proyectos del Fondo para el Desarrollo del Plan Todos So mos PAZcífico. PTSP-BIRF8649-090 / Catastr al - Brindar apoyo técnico cat astral y de avalúos en la gest Component 1. Water Supply ión predial de los bienes inm and Basic Sanitation Improv Individual Consult IBRD / 86490 Post Open 27,600.00 8,438.74 Signed 2019-08-26 2019-08-30 2019-10-14 2019-10-01 2019-11-04 2019-10-25 2019-12-09 2019-11-06 2020-06-08 uebles que sean necesarios p ements in the Municipality o ant Selection ara la viabilización de los pro f Guapi yectos que se ejecutan en el marco del Fondo para el Des arrollo del Plan Todos Somos PAZcífico. PTSP-BIRF8649-091 / Apoyo jurídico en las gestiones juríd Component 1. Water Supply icas y administrativas que se and Basic Sanitation Improv Individual Consult requiera adelantar dentro del IBRD / 86490 Post Open 16,000.00 12,098.26 Signed 2019-08-26 2020-04-08 2019-10-14 2020-04-10 2019-11-04 2020-04-16 2019-12-09 2020-04-24 2020-06-08 ements in the Municipality o ant Selection proceso de saneamiento, adq f Guapi uisición predial y reasentami ento de población, a través d e las modalidades de enajen ación PTSP-BIRF8649-088 / Gestor Component 1. Water Supply Individual Consult a Predial - Recontratación NI IBRD / 86490 and Basic Sanitation Improv Post Direct 27,600.00 10,207.20 Signed 2019-08-30 2019-09-02 2019-09-06 2019-12-09 2019-09-06 2020-01-31 2019-09-13 2020-02-01 2020-03-12 ant Selection NFA LUCIA SANTANA ESCOBA ements in the Municipality o R. f Guapi Page 7 Component 4. Project Manag PTSP-BIRF8649-027 / Especi Individual Consult IBRD / 86490 ement and Environmental a Post Open 63,844.53 0.00 Canceled 2017-04-01 2017-04-11 2017-05-20 2017-06-10 2017-07-15 2018-01-11 alista Financiero ant Selection nd Social Management PTSP-BIRF8649-093 / JOHN O Component 4. Project Manag Individual Consult TALVARO CORTES - Especiali IBRD / 86490 ement and Environmental a Post Direct 18,000.00 11,102.00 Signed 2019-11-15 2019-11-25 2019-11-22 2020-01-02 2019-11-22 2020-01-02 2019-11-26 2020-01-03 2020-05-24 ant Selection sta de Adquisiciones nd Social Management PTSP-BIRF8649-099 / Líder d Component 4. Project Manag Individual Consult e Planeación - JOAN NATALIE IBRD / 86490 ement and Environmental a Post Direct 17,700.00 25,806.54 Signed 2019-11-15 2019-11-25 2019-11-22 2019-12-05 2019-11-22 2019-12-19 2019-11-26 2019-12-28 2020-05-24 ant Selection GARZON nd Social Management PTSP-BIRF8649-101 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 26,400.00 64,142.90 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-09 2020-03-02 2020-03-12 2020-03-18 2020-03-19 2021-03-17 el Proyecto FTSP - Recontrata ant Selection nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-102 / Líder A Component 4. Project Manag Individual Consult mbiental - Recontratación Al IBRD / 86490 ement and Environmental a Post Direct 22,520.00 54,713.29 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-10 2020-03-02 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ant Selection ejandra Catacoli nd Social Management PTSP-BIRF8649-103 / Líder Fi Component 4. Project Manag Individual Consult nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Post Direct 22,520.00 54,127.85 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-10 2020-03-02 2020-03-12 2020-03-18 2020-03-19 2021-03-17 ant Selection udia Agudelo nd Social Management PTSP-BIRF8649-104 / Líder d Component 4. Project Manag Individual Consult e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Post Direct 22,520.00 54,713.29 Signed 2020-02-24 2020-03-03 2020-03-02 2020-03-09 2020-03-02 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ant Selection ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-105 / Líder d Component 4. Project Manag Individual Consult e Seguridad FTSP - WILSON L IBRD / 86490 ement and Environmental a Post Direct 22,520.00 16,685.59 Signed 2020-02-24 2020-03-02 2020-03-02 2020-03-04 2020-03-02 2020-03-11 2020-03-06 2020-03-24 2021-03-05 ant Selection AVERDE FLÓREZ nd Social Management PTSP-BIRF8649-106 / Especi Component 4. Project Manag Individual Consult alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Post Direct 17,050.00 41,402.62 Signed 2020-02-25 2020-03-03 2020-03-03 2020-03-09 2020-03-03 2020-03-16 2020-03-18 2020-03-19 2021-03-17 ant Selection ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-107 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 56,800.00 41,391.10 Signed 2020-02-25 2020-03-03 2020-03-03 2020-03-09 2020-03-03 2020-03-12 2020-03-16 2020-03-17 2021-03-15 ant Selection ontratación Tulio Jose Fuente nd Social Management s PTSP-BIRF8649-108 / Líder C Component 4. Project Manag omponente Agua y Saneamie Individual Consult IBRD / 86490 ement and Environmental a Post Direct 37,523.00 53,829.69 Signed 2020-03-24 2020-03-24 2020-03-28 2020-03-30 2020-04-01 2020-03-31 2020-04-07 2020-04-09 2021-04-07 nto Básico - Recontratación F ant Selection nd Social Management ABIOLA IGUARAN ARAUJO PTSP-BIRF8649-110 / Liderar el componente social, en la i mplementación y ejecución d e los proyectos de agua, san Component 4. Project Manag Individual Consult eamiento y energía del Fond IBRD / 86490 ement and Environmental a Post Direct 22,520.00 16,685.59 Signed 2020-04-14 2020-04-15 2020-04-15 2020-04-03 2020-04-15 2020-04-20 2020-04-23 2020-04-24 2021-04-22 ant Selection o para el Desarrollo del Plan nd Social Management Todos Somos PAZcífico finan ciados por la Banca Multilate ral que adelanta como entida d ejecutora la Unidad PTSP-BIRF8649-087 / Especi Component 4. Project Manag alista Social para la Evaluaci Individual Consult IBRD / 86490 ement and Environmental a Post Open 13,140.00 0.00 Canceled 2019-08-23 2019-08-30 2019-09-09 2019-09-27 2019-09-20 2019-09-30 2019-12-29 ón Social de los municipios d ant Selection nd Social Management e Tumaco (Nariño) y Guapi ( Cauca) Component 4. Project Manag PTSP-BIRF8649-098 / KPMG- IBRD / 86490 ement and Environmental a Post Direct Selection Direct 34,500.00 0.00 Canceled 2019-11-25 2019-12-02 2019-11-30 2020-02-03 2020-08-01 AUDITORIA EXTERNA nd Social Management PTSP-BIRF8649-111 / “Realiz ar Los Estudios Y Diseños Par Component 1. Water Supply a La Construcción, Operación and Basic Sanitation Improv , Clausura Y Post Clausura De IBRD / 86490 Post Direct Selection Direct 7,350.00 89,848.30 Signed 2020-05-15 2020-05-14 2020-05-20 2020-06-12 2020-08-02 2020-12-17 2021-01-02 ements in the Municipality o l Centro De Restauración Am f Guapi biental Urbano – CRAU Del M unicipio De Guapi, Departam ento Del Cauca” PTSP-BIRF8649-113 / Especi alista de Planeación y Segui miento. - Brindar apoyo profe Component 4. Project Manag Individual Consult sional en la gestión de planifi IBRD / 86490 ement and Environmental a Post Open 17,050.00 42,576.52 Signed 2020-05-14 2020-05-22 2020-06-03 2020-05-25 2020-06-18 2021-05-27 2020-08-01 2021-05-28 2021-08-01 ant Selection cación, monitoreo y seguimie nd Social Management nto a las actividades del Fon do para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8649-114 / Realiza r la evaluación de medio tér mino del PROYECTO DE INFR AESTRUCTURA PARA EL SUMI Component 4. Project Manag Individual Consult NISTRO DE AGUA Y SANEAMI IBRD / 86490 ement and Environmental a Post Open 15,870.00 11,192.26 Signed 2020-05-20 2020-05-20 2020-06-14 2020-06-30 2020-06-29 2020-07-15 2020-07-10 2020-08-16 2020-11-07 ant Selection ENTO BÁSICO & PROVISIÓN nd Social Management DE SERVICIOS, en cumplimie nto de las condiciones establ ecidas en el Contrato de Prés tamo N° 8649-CO. PTSP-BIRF8649-115 / Liderar la planificación, gestión, mon itoreo y seguimiento de las di ferentes herramientas de ges Component 4. Project Manag Individual Consult tión IBRD / 86490 ement and Environmental a Post Open 22,520.00 0.00 Canceled 2020-06-24 2020-06-22 2020-07-05 2020-07-25 2020-08-10 2021-08-10 ant Selection establecidas para el cumplim nd Social Management iento de las metas y objetivo s del Fondo para el Desarroll o del Plan Todos Somos PAZcífico que a delanta como entidad ejecut PTSP-BIRF8649-116 / Auditor ora ía a los Estados Financieros d Component 4. Project Manag e Propósito Especial de Proye IBRD / 86490 ement and Environmental a Post Direct Selection Direct 31,050.00 23,247.90 Signed 2020-06-26 2020-06-22 2020-07-06 2020-07-01 2020-08-20 2020-09-26 2020-11-18 ctos Financiados por el Banc nd Social Management o Mundial a través de présta mos. PTSP-BIRF8649-117 / Liderar la planificación, gestión, mon itoreo y seguimiento de las di ferentes herramientas de ges Component 4. Project Manag Individual Consult tión establecidas para el cum IBRD / 86490 ement and Environmental a Post Limited 22,520.00 56,302.02 Signed 2020-06-23 2020-06-22 2020-06-28 2020-06-19 2020-07-08 2020-06-23 2020-07-28 2020-07-01 2021-07-28 ant Selection plimiento de las metas y obje nd Social Management tivos del Fondo para el Desar rollo del Plan Todos Somos P AZcífico que adelanta como entidad ejecutora Page 8 PTSP-BIRF8649-123 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP ECIAL Y ASEGURAMIENTO Component 4. Project Manag RAZONABLE SOBRE LOS PRO IBRD / 86490 ement and Environmental a Post Direct Selection Direct 26,600.00 23,668.95 Signed 2020-10-19 2020-11-05 2020-11-08 2020-11-19 2021-01-07 2021-02-20 2021-07-06 CESOS DE ADQUISICIONES D nd Social Management EL PROYECTO/PROGRAMA FI NANCIADO POR EL BID Y EL B ANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8649-124 / Líder C Component 4. Project Manag omponente Agua y Saneamie Individual Consult IBRD / 86490 ement and Environmental a Post Direct 27,500.00 56,506.60 Signed 2021-02-23 2021-02-25 2021-02-27 2021-04-07 2021-03-03 2021-04-07 2021-04-08 2021-04-09 2022-04-08 nto Básico - Recontratación F ant Selection nd Social Management ABIOLA IGUARAN ARAUJO PTSP-BIRF8649-125 / Directo Component 4. Project Manag ra Ejecutiva / Coordinadora d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 19,330.00 66,005.44 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-17 2021-03-03 2021-03-16 2021-03-18 2021-03-19 2022-03-18 el Proyecto FTSP - Recontrata ant Selection nd Social Management ción Luz Amanda Pulido PTSP-BIRF8649-126 / Líder d Component 4. Project Manag Individual Consult e Adquisiciones - Recontrata IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,090.91 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-17 2021-03-03 2021-02-17 2021-03-18 2021-03-20 2022-03-17 ant Selection ción Elkin Adolfo Pinilla Cañó nd Social Management n PTSP-BIRF8649-127 / Líder Fi Component 4. Project Manag Individual Consult nanciera - Recontratación Cla IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,280.26 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-16 2021-03-03 2021-03-12 2021-03-18 2021-03-19 2022-03-17 ant Selection udia Agudelo nd Social Management PTSP-BIRF8649-128 / Líder S Component 4. Project Manag Individual Consult ocial - Recontratación Kelly R IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,643.71 Signed 2021-02-24 2021-02-25 2021-02-25 2021-04-22 2021-02-25 2021-04-22 2021-04-23 2021-04-24 2022-04-22 ant Selection uiz nd Social Management PTSP-BIRF8649-129 / Líder d Component 4. Project Manag Individual Consult e Seguridad FTSP -Recontrat IBRD / 86490 ement and Environmental a Post Direct 16,500.00 56,090.91 Signed 2021-02-24 2021-02-25 2021-03-03 2021-03-22 2021-03-03 2021-02-22 2021-03-22 2021-03-24 2022-03-21 ant Selection ación WILSON LAVERDE FLÓ nd Social Management REZ PTSP-BIRF8649-130 / Especi Component 4. Project Manag Individual Consult alista Financiera - Recontrata IBRD / 86490 ement and Environmental a Post Direct 12,473.00 42,851.48 Signed 2021-03-03 2021-03-15 2021-03-10 2021-03-17 2021-03-10 2021-03-17 2021-03-18 2021-03-19 2022-03-17 ant Selection ción Sandra Lorena Peña nd Social Management PTSP-BIRF8649-132 / Especi Component 4. Project Manag Individual Consult alista de Adquisiciones - Rec IBRD / 86490 ement and Environmental a Post Direct 20,788.00 42,433.29 Signed 2021-03-03 2021-03-15 2021-03-10 2021-03-12 2021-03-10 2021-03-15 2021-03-15 2021-03-19 2022-03-14 ant Selection ontratación Tulio Jose Fuente nd Social Management s PTSP-BIRF8649-131 / Contra tación Líder Ambiental para l a ejecución y cumplimiento d Component 4. Project Manag e los Marcos de Gestión Ambi IBRD / 86490 ement and Environmental a Post Direct Selection Direct 8,244.00 28,045.46 Signed 2021-03-03 2021-03-05 2021-03-11 2021-03-05 2021-03-18 2021-03-17 2021-09-17 ental adoptados para la ejec nd Social Management ución del Fondo para el desar rollo del Plan Todos Somos P AZcífico - Fernando Rey PTSP-BIRF8649-133 / Especi alista de Planeación y Segui miento. - Brindar apoyo profe Component 4. Project Manag Individual Consult sional en la gestión de planifi IBRD / 86490 ement and Environmental a Post Open 10,394.00 17,829.14 Signed 2021-03-11 2021-03-15 2021-03-16 2021-03-24 2021-03-17 2021-03-24 2021-03-25 2021-03-27 2022-09-24 ant Selection cación, monitoreo y seguimie nd Social Management nto a las actividades del Fon do para el Desarrollo del Plan Todos Somos Pazcífico. PTSP-BIRF8649-134 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Component 4. Project Manag mplementación y ejecución d IBRD / 86490 ement and Environmental a Post Direct Selection Direct 8,244.00 0.00 Canceled 2021-04-14 2021-04-24 2021-05-17 2021-11-16 e los componentes de Capaci nd Social Management dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico - Jorge Silva PTSP-BIRF8649-135 / Contra tación Líder Fortalecimiento I nstitucional para Liderar la i Component 4. Project Manag mplementación y ejecución d Individual Consult IBRD / 86490 ement and Environmental a Post Direct 8,244.00 28,321.85 Signed 2021-04-15 2021-04-19 2021-04-23 2021-04-14 2021-04-26 2021-05-07 2021-05-17 2021-05-12 2021-11-16 e los componentes de Capaci ant Selection nd Social Management dad y Fortalecimiento Institu cional de Agua y Saneamient o Básico para el desarrollo de l Plan Todos Somos PAZcífico - Jorge Silva. PTSP-BIRF8649-136 / Especi Component 4. Project Manag alista de Adquisiciones - Rec Individual Consult IBRD / 86490 ement and Environmental a Post Direct 12,473.00 42,851.48 Signed 2021-04-22 2021-04-22 2021-04-26 2021-05-26 2021-04-26 2021-05-04 2021-05-04 2021-05-07 2022-05-03 ontratación JOHN MAURICIO ant Selection nd Social Management OTÁLVARO CORTÉS PTSP-BIRF8649-138 / Líder d Component 4. Project Manag Individual Consult e Planeación - JOAN NATALIE IBRD / 86490 ement and Environmental a Post Direct 16,490.00 56,643.71 Signed 2021-06-04 2021-06-11 2021-06-11 2021-06-22 2021-06-11 2021-06-23 2021-06-30 2021-07-01 2022-06-29 ant Selection GARZON nd Social Management PTSP-BIRF8649-139 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP ECIAL Y ASEGURAMIENTO Component 4. Project Manag RAZONABLE SOBRE LOS PRO IBRD / 86490 ement and Environmental a Post Direct Selection Direct 26,238.00 21,580.38 Signed 2021-09-06 2021-09-15 2021-09-26 2021-10-04 2021-12-22 2022-02-03 2022-07-29 CESOS DE ADQUISICIONES D nd Social Management EL PROYECTO/PROGRAMA FI NANCIADO POR EL BID Y EL B ANCO MUNDIAL A TRAVÉS DE PRÉSTAMOS PTSP-BIRF8649-140 / Líder A Component 4. Project Manag Individual Consult mbiental FTSP - Recontrataci IBRD / 86490 ement and Environmental a Post Direct 8,902.00 27,880.05 Signed 2021-09-09 2021-09-09 2021-09-09 2021-09-10 2021-09-20 2021-09-20 2021-09-23 2021-09-24 2022-03-22 ant Selection ón Fernando Rey nd Social Management PTSP-BIRF8649-141 / Especi Component 4. Project Manag alista de Planeación y Segui Individual Consult IBRD / 86490 ement and Environmental a Post Direct 22,425.00 41,939.36 Signed 2021-09-09 2021-09-09 2021-09-17 2021-09-16 2021-09-17 2021-09-20 2021-09-27 2021-09-29 2022-09-26 miento FTSP - Recontratación ant Selection nd Social Management Natalia García Medina PTSP-BIRF8649-144 / Líder d Component 3. Capacity Buil e Fortalecimiento Institucion ding and Institutional Streng Individual Consult IBRD / 86490 Post Direct 17,805.00 55,760.11 Signed 2021-10-19 2021-10-19 2021-10-19 2021-10-19 2021-10-26 2021-10-26 2021-11-11 2021-11-12 2022-11-10 al - Recontratación Jorge Silv thening of Service Providers ant Selection a in the Municipalities of Guap i and Tum aco Component 4. Project Manag PTSP-BIRF8649-145 / Líder S Individual Consult IBRD / 86490 ement and Environmental a Post Open 14,837.00 24,051.50 Signed 2021-10-27 2021-10-27 2021-11-30 2022-03-16 2021-12-03 2022-03-17 2021-12-20 2022-04-10 2022-06-19 ocial FTSP ant Selection nd Social Management Page 9 PTSP-BIRF8649-171 / Líder d Component 1. Water Supply Individual Consult e Agua BM - Recontratación F IBRD / 86490 and Basic Sanitation Improv Post Direct 31,342.00 57,727.68 Signed 2022-03-04 2022-03-04 2022-03-04 2022-03-04 2022-03-24 2022-03-09 2022-04-08 2022-04-11 2023-04-07 ant Selection abiola del Rosario Iguarán ements in the Municipality o f Guapi PTSP-BIRF8649-176 / Recont Component 4. Project Manag Individual Consult ratación Especialista de Adqu IBRD / 86490 ement and Environmental a Post Direct 23,711.00 43,671.56 Signed 2022-03-04 2022-03-04 2022-03-09 2022-03-04 2022-03-09 2022-03-04 2022-03-16 2022-03-19 2023-03-15 ant Selection isiciones - Tulio José Fuentes nd Social Management PTSP-BIRF8649-172 / Recont Component 4. Project Manag Individual Consult ratación Directora Ejecutiva- IBRD / 86490 ement and Environmental a Post Direct 22,046.00 62,078.79 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-11 2022-03-11 2022-03-11 2022-03-18 2022-03-19 2023-03-17 ant Selection Coordinadora General - Luz A nd Social Management manada Pulido PTSP-BIRF8649-173 / Recont Component 4. Project Manag Individual Consult ratación Líder de Adquisicion IBRD / 86490 ement and Environmental a Post Direct 18,805.00 52,952.63 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-11 2022-03-11 2022-03-11 2022-03-18 2022-03-21 2023-03-17 ant Selection es - Élkin Pinilla nd Social Management PTSP-BIRF8649-174 / Recont Component 4. Project Manag Individual Consult ratación Líder Financiera - Cl IBRD / 86490 ement and Environmental a Post Direct 18,805.00 53,292.14 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-04 2022-03-11 2022-04-11 2022-03-18 2022-03-19 2023-03-17 ant Selection audia Agudelo nd Social Management PTSP-BIRF8649-175 / Recont Component 4. Project Manag Individual Consult ratación Líder Ambiental - Fe IBRD / 86490 ement and Environmental a Post Direct 9,403.00 26,646.07 Signed 2022-03-04 2022-03-04 2022-03-04 2022-03-04 2022-03-15 2022-03-15 2022-03-23 2022-03-24 2022-09-22 ant Selection rnando Rey nd Social Management PTSP-BIRF8649-177 / Recont Component 4. Project Manag Individual Consult ratación Especialista Financie IBRD / 86490 ement and Environmental a Post Direct 14,226.00 40,315.98 Signed 2022-03-04 2022-03-04 2022-03-11 2022-03-04 2022-03-11 2022-03-11 2022-03-18 2022-03-19 2023-03-17 ant Selection ra - Lorena Peña nd Social Management PTSP-BIRF8649-178 / Recont Component 4. Project Manag Individual Consult Under Implement ratación Líder de Seguridad - IBRD / 86490 ement and Environmental a Post Direct 8,910.00 0.00 2022-04-26 2022-05-05 2022-05-02 2022-04-26 2022-05-02 2022-05-05 2022-11-04 ant Selection ation Wilson Laverde nd Social Management PTSP-BIRF8649-180 / Liderar los procesos de adquisicione s que adelanta la Unidad Nac ional para la Gestión del Ries Component 4. Project Manag Individual Consult go de Desastres como entida IBRD / 86490 ement and Environmental a Post Limited 17,900.00 0.00 Canceled 2022-05-23 2022-05-27 2022-05-28 2022-06-15 2022-06-02 2022-06-17 2023-06-16 ant Selection d ejecutora del Fondo para el nd Social Management Desarrollo del Plan Todos So mos PAZcífico, según las Polí ticas, normas y regulaciones del BID y Banco M. PTSP-BIRF8649-181 / Liderar la planificación, monitoreo, s eguimiento y gestión de los p réstamos del BID y el Banco Component 4. Project Manag Individual Consult Pending Impleme Mundial, ejecutados por la U IBRD / 86490 ement and Environmental a Post Direct 17,805.00 0.00 2022-06-16 2022-06-17 2022-06-24 2022-06-29 2023-06-29 ant Selection ntation nidad Nacional para la Gestió nd Social Management n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo del Plan Todos Somos FTSP PTSP-BIRF8649-184 / Brindar apoyo profesional como Espe cialista de Adquisiciones en l Component 4. Project Manag os procesos que adelanta la Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Limited 20,979.00 0.00 2022-07-11 2022-07-19 2022-07-16 2022-08-06 2022-09-10 2023-03-09 Unidad Nacional para la Gesti ant Selection ation nd Social Management ón del Riesgo de Desastres c omo entidad ejecutora del Fo ndo para el Desarrollo del Pla n Todos Somos PAZcífico. PTSP-BIRF8649-185 / Especi Component 4. Project Manag alista de Planeación y Segui Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Direct - National 20,979.00 0.00 2022-08-30 2022-08-30 2022-08-30 2022-09-28 2022-09-28 2023-09-27 miento FTSP - Recontratación ant Selection ation nd Social Management Natalia García Medina PTSP-BIRF8649-186 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Component 4. Project Manag Individual Consult Pending Impleme el marco de los préstamos de IBRD / 86490 ement and Environmental a Post Direct - National 8,319.00 0.00 2022-09-19 2022-09-19 2022-10-07 2022-10-28 2023-04-26 ant Selection ntation l BID y el Banco Mundial, ejec nd Social Management utados por la Unidad Naciona l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo PTSP-BIRF8649-187 / Coordi nar la implementación y sup ervisión de los préstamos del Component 4. Project Manag BID y el Banco Mundial, ejecu Individual Consult IBRD / 86490 ement and Environmental a Post Open - National 19,506.00 0.00 Canceled 2022-09-23 2022-09-20 2022-10-15 2022-10-17 2022-11-21 2023-05-20 tados por la Unidad Nacional ant Selection nd Social Management para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico PTSP-BIRF-8649-188 / Presta r los servicios jurídicos como especialista para los proceso s de adquisiciones del Fondo Component 4. Project Manag Individual Consult Pending Impleme para el Desarrollo del Plan To IBRD / 86490 ement and Environmental a Post Open - National 12,587.00 0.00 2022-10-10 2022-11-28 2022-12-19 2023-01-23 2023-10-23 ant Selection ntation dos Somos PAZcífico que ade nd Social Management lanta como entidad ejecutora la Uni-dad Nacional para la G estión del Riesgo de Desastr es, en el marco PTSP-BIRF-8649-189 / AUDIT ORÍA DE LOS ESTADOS FINA NCIEROS DE PROPÓSITO ESP Component 4. Project Manag ECIAL Y ASEGURAMIENTO RA Pending Impleme IBRD / 86490 ement and Environmental a Post Direct Selection Direct - National 28,410.00 0.00 2022-10-10 2022-10-16 2023-01-09 2023-05-05 ZONABLE SOBRE LOS PROCE ntation nd Social Management SOS DE ADQUISICIONES DEL PROYECTO/PROGRAMA FINA NCIADO POR EL BID Y EL BAN CO MUNDIAL A TRAVÉS DE P RÉSTAMOS - PTSP-BIRF-8649-190 / Coordi nar la implementación y sup ervisión de los préstamos del Component 4. Project Manag BID y el Banco Mundial, ejecu Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Limited 19,506.00 0.00 2022-10-14 2022-10-07 2022-10-19 2022-09-27 2022-11-09 2022-12-14 2023-06-12 tados por la Unidad Nacional ant Selection ation nd Social Management para la Gestión del Riesgo de Desastres como entidad ejec utora del Fondo para el Desa rrollo del Plan Todos Somos P AZcífico Page 10 PTSP-BIRF-8649-191 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Component 4. Project Manag Individual Consult Pending Impleme l Banco Mundial ejecutados p IBRD / 86490 ement and Environmental a Post Direct - National 5,826.00 0.00 2022-11-07 2022-11-17 2022-12-08 2023-01-12 2023-07-11 ant Selection ntation or la Unidad Nacional para la nd Social Management Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PTSP-BIRF-8649-192 / Lidera r la planificación, estructurac ión, seguimiento y gestión de Component 3. Capacity Buil los proyectos de Capacidad y ding and Institutional Streng Individual Consult Pending Impleme Fortalecimiento Institucional IBRD / 86490 thening of Service Providers Post Direct - National 4,160.00 0.00 2022-11-11 2022-11-16 2022-12-07 2023-01-11 2023-07-10 ant Selection ntation que hagan parte de los prést in the Municipalities of Guap amos del BID y el Banco Mun i and Tum aco dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Des PTSP-BIRF-8649-193 / Lidera r los procesos de adquisicion es que adelanta la Unidad Na cional para la Gestión del Rie Component 4. Project Manag Individual Consult sgo de Desastres como entid IBRD / 86490 ement and Environmental a Post Open - National 16,639.00 0.00 Signed 2022-11-11 2022-11-18 2022-12-19 2022-11-23 2023-01-09 2022-12-19 2023-02-13 2023-08-12 ant Selection ad ejecutora del Fondo para nd Social Management el Desarrollo del Plan Todos Somos PAZcífico, según las P olíticas, normas y regulacion es del BID y el Banc PTSP-BIRF-8649-194 / Lidera r las actividades relacionad as con protocolos y herrami Component 4. Project Manag entas de seguridad, para miti Pending Impleme IBRD / 86490 ement and Environmental a Post Direct Selection Direct - National 4,160.00 0.00 2022-11-10 2022-11-19 2023-01-23 2023-07-22 gar las posibles amenazas o ntation nd Social Management riesgos en la ejecución de los proyectos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, q ue ejecuta la PTSP-BIRF8649-194 / Brindar apoyo profesional como espe cialista de planeación, monit oreo, seguimiento y gestión Component 4. Project Manag Individual Consult Pending Impleme de los préstamos del Banco IBRD / 86490 ement and Environmental a Post Direct - National 23,731.00 0.00 2023-01-27 2023-02-01 2023-02-22 2023-03-29 2023-09-25 ant Selection ntation Mundial, ejecutados por la U nd Social Management nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del Fon do para el Desarrollo d PTSP-BIRF8649-195 / Liderar la planificación, seguimiento y gestión ambiental de los pr oyectos que se adelanten en Component 4. Project Manag Individual Consult Pending Impleme el marco de los préstamos de IBRD / 86490 ement and Environmental a Post Direct - National 18,822.00 0.00 2023-01-27 2023-02-01 2023-02-22 2023-03-29 2023-09-25 ant Selection ntation l BID y el Banco Mundial, ejec nd Social Management utados por la Unidad Naciona l para la Gestión del Riesgo d e Desastres como entidad ej ecutora del Fondo PTSP-BIRF-8649-195 / Realiz ar apoyo como profesional es pecializado en los procesos c ontractuales y relaciones jurí Component 4. Project Manag Individual Consult Pending Impleme dico negociales del Fondo pa IBRD / 86490 ement and Environmental a Post Limited 14,239.00 0.00 2023-02-06 2023-02-11 2023-03-04 2023-04-08 2023-10-05 ant Selection ntation ra el Desarrollo del Plan Todo nd Social Management s Somos PAZcífico - FTSP, cu ya entidad ejecutora es la Un idad Nacional para la Gestión del Riesgo de Des PTSP-BIRF-8649-196 / Brinda r apoyo profesional como Esp ecialista de Adquisiciones del préstamo 8649-CO en los pro Component 4. Project Manag Individual Consult Pending Impleme cesos que adelanta la Unidad IBRD / 86490 ement and Environmental a Post Direct - National 39,885.00 0.00 2023-02-22 2023-03-04 2023-03-25 2023-04-29 2023-10-26 ant Selection ntation Nacional para la Gestión del nd Social Management Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico, s PTSP-BIRF-8649-199 / Lidera r las actividades relacionadas con protocolos y herramienta s de seguridad, para mitigar l Component 4. Project Manag Under Implement as posibles amenazas o riesg IBRD / 86490 ement and Environmental a Post Direct Selection Direct - National 18,822.00 0.00 2023-03-13 2023-03-22 2023-03-22 2023-05-26 2023-11-22 ation os en la ejecución de los proy nd Social Management ectos que se desarrollan en e l marco de los préstamos del BID y el Banco Mundial, que ejecuta la Unida PTSP-BIRF-8649-197 / TDR - Especialista Financiera en la gestión presupuestal y financ iera de los préstamos del BID Component 4. Project Manag Individual Consult Pending Impleme y el Banco Mundial, ejecutad IBRD / 86490 ement and Environmental a Post Direct - National 14,239.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation os por la Unidad Nacional par nd Social Management a la Gestión del Riesgo de De sastres como entidad ejecuto ra del Fondo para el Desarrol lo del Plan Todos PTSP-BIRF-8649-198 / TDR- L iderar la gestión presupuesta l y financiera de los préstamo s del BID y el Banco Mundial, Component 4. Project Manag Individual Consult Pending Impleme ejecutados por la Unidad Nac IBRD / 86490 ement and Environmental a Post Direct - National 18,822.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation ional para la Gestión del Ries nd Social Management go de Desastres como entida d ejecutora del Fondo para el Desarrollo del Plan Todos So mos PAZcífico. PTSP-BIRF-8649-201 / Lidera r la planificación, estructurac ión, seguimiento y gestión de Component 3. Capacity Buil los proyectos de Capacidad y ding and Institutional Streng Individual Consult Pending Impleme Fortalecimiento Institucional IBRD / 86490 thening of Service Providers Post Direct - National 18,822.00 0.00 2023-03-13 2023-03-22 2023-04-12 2023-05-17 2023-11-13 ant Selection ntation que hagan parte de los prést in the Municipalities of Guap amos del BID y el Banco Mun i and Tum aco dial, ejecutados por la Unida d Nacional para la Gestión de l Riesgo de Desa Page 11 PTSP- BIRF-8649-200 / Lider ar el componente social de lo s proyectos que se generen e n el marco de los préstamos Component 4. Project Manag Individual Consult del Banco Mundial ejecutado IBRD / 86490 ement and Environmental a Post Limited 15,685.00 0.00 Canceled 2023-03-13 2023-04-04 2023-03-17 2023-04-07 2023-05-12 2023-11-08 ant Selection s por la Unidad Nacional para nd Social Management la Gestión del Riesgo de Des astres como entidad ejecutor a del Fondo para el Desarroll o del Plan Todos Somos PTSP-BIRF-8649-202 / Presta r los servicios juridicos como especialista al Ordenador del Gasto, en los procesos de ad Component 4. Project Manag Individual Consult Pending Impleme quisiciones, así como en las IBRD / 86490 ement and Environmental a Post Direct - National 11,965.00 0.00 2023-04-04 2023-04-14 2023-05-05 2023-06-09 2023-12-06 ant Selection ntation actividades inherentes a la ej nd Social Management ecución de los proyectos que se desarrollan en el marco d e los prestamos del BID y el Banco Mundial.. PTSP-BIRF-8649-204 / Lidera r el componente social de los proyectos que se generen en el marco de los préstamos de Component 4. Project Manag Individual Consult Under Implement l Banco Mundial ejecutados p IBRD / 86490 ement and Environmental a Post Limited 31,370.00 0.00 2023-05-05 2023-05-11 2023-05-19 2023-05-16 2023-06-09 2023-07-14 2024-01-10 ant Selection ation or la Unidad Nacional para la nd Social Management Gestión del Riesgo de Desast res como entidad ejecutora d el Fondo para el Desarrollo d el Plan Todos Somos PSTP-BIRF-8649-206 / Lidera r la planificación, monitoreo, seguimiento y gestión de los Component 4. Project Manag Individual Consult Under Implement préstamos del BID y el Banco IBRD / 86490 ement and Environmental a Post Direct - National 18,822.00 0.00 2023-05-15 2023-05-25 2023-05-25 2023-06-15 2023-07-20 2024-01-16 ant Selection ation Mundial, ejecutados por la U nd Social Management nidad Nacional para la Gestió n del Riesgo de Desastres co mo entidad ejecutora del FTS P PTSP-BIRF-8649-203 / Lidera r la planificación,estructuraci ón, seguimiento y gestión de Component 1. Water Supply los proyectos de Agua y Sane and Basic Sanitation Improv Individual Consult amiento Básico que hagan p IBRD / 86490 Post Direct - National 15,684.00 0.00 Canceled 2023-04-04 2023-04-14 2023-05-05 2023-06-09 2023-12-06 ements in the Municipality o ant Selection arte de los préstamos del Ba f Guapi nco Mundial 8649 CO y 8798 CO, ejecutados por la Unidad Nacional para la Gestión del Riesgo de Desastres... PTSP-BIRF-8649-205 / Brinda r acompañamiento técnico pr ofesional ambiental en la ges Component 4. Project Manag tión de los Planes de Manejo Individual Consult Under Implement IBRD / 86490 ement and Environmental a Post Limited 17,438.00 0.00 2023-05-15 2023-05-25 2023-05-20 2023-06-10 2023-07-15 2024-01-11 Ambiental y Estudios de Imp ant Selection ation nd Social Management acto Ambiental de los proyec tos que se desarrollen en el marco del PTSP, que adelant a como entidad ejecutora de la UNGRD PTSP-BIRF-8649-208 / Presta r los servicios de acompaña miento integral y exclusivo al Ordenador del Gasto del FTS Component 4. Project Manag Individual Consult Pending Impleme P, en las actividades inherent IBRD / 86490 ement and Environmental a Post Limited 11,866.00 0.00 2023-06-02 2023-06-07 2023-06-28 2023-08-02 2024-01-29 ant Selection ntation es a la ejecución de los proye nd Social Management ctos que se desarrollan en el marco de los préstamos del BID y el Banco Mundial, que ejecuta la UNGRD. PTSP-BIRF-8649-209 / Coordi nar y dirigir la implementació n y supervisión de los présta mos del BID y el Banco Mund Component 4. Project Manag Individual Consult Pending Impleme ial, ejecutados por la Unidad IBRD / 86490 ement and Environmental a Post Direct - National 12,872.00 0.00 2023-06-02 2023-06-12 2023-07-03 2023-08-07 2024-02-03 ant Selection ntation Nacional para la Gestión del nd Social Management Riesgo de Desastres como en tidad ejecutora del Fondo par a el Desarrollo del Plan Todos Somos PAZcífico PTSP-BIRF-8649-212 / Actual ización, ajuste y complement Component 2. Water Supply ación de estudios y diseños d and Basic Sanitation Improv Under Implement IBRD / 86490 Post Direct Selection Direct - National 133,327.00 0.00 2023-06-09 2023-06-23 2023-06-19 2023-08-23 2024-02-19 e la nueva línea de aducción ements in the Municipality o ation del sistema de acueducto del f Tumaco distrito especial de Tumaco d epartamento de Nariño. PTSP-BIRF-8649-211 / LÍDER AGUA Y SANEAMIENTO BÁSIC Component 1. Water Supply O (TUMACO - GUAPI) - Liderar and Basic Sanitation Improv Individual Consult Pending Impleme IBRD / 86490 Post Open - National 62,739.00 0.00 2023-06-20 2023-08-08 2023-08-29 2023-10-03 2024-03-31 la planificación, estructuració ements in the Municipality o ant Selection ntation n, seguimiento y gestión de l f Guapi os proyectos de Agua y Sane amiento Básico PTSP-BIRF-8649-210 / Lidera r la planificación, seguimient o y gestión ambiental de los proyectos que se adelanten e Component 4. Project Manag Individual Consult Pending Impleme n el marco de los préstamos IBRD / 86490 ement and Environmental a Post Open - National 18,822.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ant Selection ntation del BID y el Banco Mundial, e nd Social Management jecutados por la Unidad Naci onal para la Gestión del Ries go de Desastres como entida d ejecutora del FTSP Page 12 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, One WASH- Consolidated WASH Account (CWA) Project “Phase II”, P167794 Project Implementation agency: Water Development Commission (WDC) of the Ministry of Water, Irrigation and Energy (MoWIE) Date of the Procurement Plan: August 28, 2019 Period covered by this Procurement Plan: September 2019 to August 2020. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : One WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project (One WASH—CWA) PLAN General Information Country: Ethiopia Bank’s Approval Date of the Original Procurement Plan: 2020-03-11 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-19 none) Project ID: P167794 GPN Date: 2019-12-06 Project Name: One WASH—Consolidated Water Supply, Sanitation, and Hygiene Account Project (One WASH—CWA) Loan / Credit No: IDA / 64450 Benishangul Gumuz RS WIERDB Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-BGRS WIERDB-154058-C W-RFB / Drilling and construc tion of 27 Shallow Wells in As sosa Woreda (20 for commun Rural Water Supply, Sanitati Single Stage - One E 2021-02-1 ity, 1 for school and 6 for hea IDA / 64450 on, and Hygiene (Rural WAS Post Request for Bids Open - National 162,000.00 115,345.51 Completed 2020-05-01 2020-06-01 2020-05-06 2020-06-05 2020-07-20 2020-07-05 2020-09-08 2020-08-16 2020-11-24 nvelope 2 lth institution) by BGRS Wat H) er, Irrigation and Energy Res ources Development Bureau One WaSH National Program Management Unit ET-BGRS WIERDB-154090-C W-RFB / Drilling and construc tion of 26 shallow well( 20 for Rural Water Supply, Sanitati Single Stage - One E 2021-02-1 community,1 for school and IDA / 64450 on, and Hygiene (Rural WAS Post Request for Bids Open - National 156,000.00 0.00 Canceled 2020-05-01 2020-06-01 2020-05-06 2020-06-05 2020-07-20 2020-07-05 2020-08-16 nvelope 2 5 for health institution) in Dib H) ati woreda by BGRS water irr igation and energy resource development bureau OWNP P MU. ET-BGRS WIERDB-154195-C W-RFB / Construction of one Rural Water Supply, Sanitati Request for Quota Single Stage - One E Under Imple 2020-07-0 on spot spring in Dibatie Wor IDA / 64450 on, and Hygiene (Rural WAS Post Limited 2,875.00 0.00 2020-03-30 2020-05-19 tions nvelope mentation 3 eda by Woreda Water, Mines H) and Energy Resources Devel opment Office ET-BGRS WIERDB-154203-C W-RFB / Construction and ins Rural Water Supply, Sanitati tallation of 2 hand dug wells Request for Quota Single Stage - One E Under Imple 2020-07-0 IDA / 64450 on, and Hygiene (Rural WAS Post Limited 2,875.00 0.00 2020-03-30 2020-05-19 with hand pumps in Dibatie tions nvelope mentation 3 H) Woreda by Woreda Water, M ines and Energy Resources D evelopment Office ET-BGRS WIERDB-154200-C W-RFB / Construction and ins Rural Water Supply, Sanitati tallation of 1 hand dug wells Request for Quota Single Stage - One E Under Imple 2020-07-0 IDA / 64450 on, and Hygiene (Rural WAS Post Limited 1,437.50 0.00 2020-03-30 2020-05-19 with hand pumps in Assosa tions nvelope mentation 3 H) woreda by Woreda Water, Mi nes and Energy Resources D evelopment Office ET-BGRS WIERDB-154201-C W-RFB / Construction of 2 on Rural Water Supply, Sanitati Request for Quota Single Stage - One E Under Imple 2020-07-0 spot springs in Assosa by As IDA / 64450 on, and Hygiene (Rural WAS Post Limited 5,750.00 0.00 2020-03-30 2020-04-14 2020-05-20 tions nvelope mentation 4 sosa Woreda Water, Mines a H) nd Energy Resources Develo pment Office ET-BGRS WIERDB-154204-C W-RFB / Construction and ins Rural Water Supply, Sanitati tallation of 3 hand dug wells Request for Quota Single Stage - One E Pending Imp 2020-07-0 IDA / 64450 on, and Hygiene (Rural WAS Post Limited 4,312.50 0.00 2020-03-30 2020-05-19 with hand pumps in Kamashi tions nvelope lementation 3 H) woreda by Kemash woreda w ater mine and energy resour ce development office. ET-BGRS WIERDB-154065-C W-RFB / Drilling and construc tion of 23 shallow wells(20 fo r community, 1 for school an Rural Water Supply, Sanitati Single Stage - One E 2021-02-1 d 2 for health institution) in IDA / 64450 on, and Hygiene (Rural WAS Post Request for Bids Open - National 138,000.00 0.00 Canceled 2020-05-01 2020-06-13 2020-05-06 2020-06-05 2020-07-20 2020-07-05 2020-08-16 nvelope 2 Kamashi Woreda by BGRS W H) ater, Irrigation and Energy R esources Development Burea u One WaSH National Progra m Management Unit ET-BGRS REB-169678-CW-R FQ / Construction of two blo ck VIP latrine and one block Institutional Water Supply, S Request for Quota Single Stage - One E 2020-10-1 (MHM) Menstrual hayigene m IDA / 64450 anitation, and Hygiene (Insti Post Limited 22,500.00 9,282.56 Completed 2020-05-18 2020-05-20 2020-07-13 2020-07-08 tions nvelope 1 anagement with hand washi tutional WASH) ng & urinal facility for School s by Assosa woreda Educati on Office. ET-BGRS REB-170077-CW- RFQ / Construction of two bl ock VIP latrine and one block Institutional Water Supply, S Request for Quota Single Stage - One E 2020-10-1 (MHM) Menstrual hygiene m IDA / 64450 anitation, and Hygiene (Insti Post Limited 22,500.00 17,176.31 Signed 2020-05-18 2020-06-04 2020-07-13 2020-09-04 tions nvelope 1 anagement with hand washi tutional WASH) ng & urinal Facility for Schoo ls by Dibate woredas Educa tion Office. ET-BGRS WIERDB-154307-C W-RFB / Maintenance and re Rural Water Supply, Sanitati habilitate of the existing wat Request for Quota Single Stage - One E Pending Imp 2020-07-0 IDA / 64450 on, and Hygiene (Rural WAS Post Limited 2,262.68 0.00 2020-05-18 2020-06-21 er scheme Lot 1=6 HDW an tions nvelope lementation 6 H) d Lot 2 =2 SW in Kemashi woreda by water mine and e nergy resource development office ET-BGRS WIERDB-154303-C W-RFB / Maintenance and re Rural Water Supply, Sanitati habilitate of existing water s Request for Quota Single Stage - One E Pending Imp 2020-07-0 IDA / 64450 on, and Hygiene (Rural WAS Post Limited 2,262.68 0.00 2020-05-18 2020-06-22 cheme Lot 1=6 spring and Lo tions nvelope lementation 7 H) t 2=4 HDW in dibati woreda by water min and energy res ource development office ET-BGRS WIERDB-154306-C W-RFB / Maintenance and re habilitation of existing water Rural Water Supply, Sanitati Request for Quota Single Stage - One E Pending Imp 2020-07-1 schemes Lot 1= 2 spring Lot IDA / 64450 on, and Hygiene (Rural WAS Post Limited 2,262.68 0.00 2020-05-18 2020-06-30 tions nvelope lementation 5 2= 4 HDW and Lot 3= 3 SW H) in Assosa Woreda by Assosa Woreda Water, Mines and En ergy Resources Development Office Page 1 ET-BGRS RHB-170140-CW-R FQ / Construction 2 VIP Latri Institutional Water Supply, S Request for Quota Single Stage - One E Under Imple 2020-10-1 nes, 1 Placenta Pit, 1 Incinera IDA / 64450 anitation, and Hygiene (Insti Post Limited 22,333.00 0.00 2020-05-18 2020-07-13 tions nvelope mentation 1 tor and 1 west disposal Pit b tutional WASH) y Dibati Woreda Health Offic e. ET-BGRS RHB-170147-CW-R FQ / Construction of ( 2 Ven tilated improved pit latrine 1 Institutional Water Supply, S Request for Quota Single Stage - One E Under Imple 2020-10-1 in Megele 33 Kebele and 1 i IDA / 64450 anitation, and Hygiene (Insti Post Limited 21,333.00 0.00 2020-05-18 2020-07-13 tions nvelope mentation 1 n Megele 31 Kebele and 1 p tutional WASH) lacenta Pit and 1 Incinerator i n Mugufude Kebele by Asso sna Woreda Health Office. ET-BGRS RHB-170148-CW-R FQ / Construction of ( 2 Ven tilated improved pit latrine 1 Institutional Water Supply, S in Nebare Keshemado and 1 Request for Quota Single Stage - One E Pending Imp 2020-10-1 IDA / 64450 anitation, and Hygiene (Insti Post Limited 23,333.00 0.00 2020-05-18 2020-07-13 in Selga 22, 1 Placenta Pit an tions nvelope lementation 1 tutional WASH) d 1 Incinerator in Amba 11 a nd 2 west disposal Pit 1 in Nebare Keshemado and 1 in Selga 22 ) by Assosna Wore da Health Office. ET-BGRS WIERDB-188043-C W-RFB / Construction of Civil Works, Supply & Installation Urban Water Supply, Sanitati of Pipes and Fittings and Elec Single Stage - One E 1,131,605.2 2021-12-3 IDA / 64450 on, and Hygiene (Urban WAS Post Request for Bids Open - National 1,229,990.00 Signed 2020-09-21 2020-11-19 2020-09-26 2020-10-26 2020-12-24 2020-11-25 2020-12-24 2020-12-30 2021-04-03 tro-Mechanical Equipment for nvelope 2 0 H) Dobi Small Town Water Suppl y and Sanitation Project by B GRS water irrigation and ene rgy resource development bu reau OWNP PMU ET-BGRS WIERDB-188045-C W-RFB / Construction of multi - village rural water supply of Kashaf-Center RPS Kebeles ( Rural Water Supply, Sanitati Single Stage - One E 2021-10-0 Civil works, supply and install IDA / 64450 on, and Hygiene (Rural WAS Post Request for Bids Open - National 857,142.00 519,514.41 Signed 2020-09-21 2020-11-19 2020-10-21 2020-12-02 2020-12-24 2021-01-01 2020-12-24 2021-02-05 2021-04-03 nvelope 3 ation of pipes, fittings and el H) ecro-mechanical equipment) by BGRS Water, Irrigation an d Energy Resources Develop ment Bureau OWNP PMU ET-BGRS REB-199317-CW-R FQ / Construction of new two block inclusive & improved l Institutional Water Supply, S Request for Quota Single Stage - One E 2021-07-0 atrine and one block (MHM) IDA / 64450 anitation, and Hygiene (Insti Post Limited 20,900.00 21,485.41 Signed 2020-11-15 2021-02-08 2021-01-10 2021-03-23 tions nvelope 9 with incinerator ,hand washin tutional WASH) g & urinal facility in Gumba Primary School by Assosa wo reda Education Office. ET-BGRS REB-199328-CW-R FQ / Construction of new two block inclusive & improved la Institutional Water Supply, S Request for Quota Single Stage - One E Pending Imp 2021-07-0 trine and one block (MHM) wi IDA / 64450 anitation, and Hygiene (Insti Post Limited 20,900.00 0.00 2020-11-15 2021-01-10 tions nvelope lementation 9 th incinerator ,hand washing tutional WASH) & urinal facility in Zegih pri mary School by Dibati wored a Education Office. ET-BGRS REB-199330-CW-R FQ / Construction of new two block inclusive & improved la Institutional Water Supply, S Request for Quota Single Stage - One E Pending Imp 2021-07-0 trine and one block (MHM) wi IDA / 64450 anitation, and Hygiene (Insti Post Limited 20,900.00 0.00 2020-11-15 2021-01-10 tions nvelope lementation 9 th incinerator ,hand washing tutional WASH) & urinal facility in Kobi Bedes sa Primary School by Kemash i woreda Education Office. ET-BGRS RHB-199641-CW-R FQ / Construction of 1 VIP la Institutional Water Supply, S trine in Atoto , 1 waste Dispo Request for Quota Single Stage - One E Under Imple 2021-01-1 IDA / 64450 anitation, and Hygiene (Insti Post Limited 11,000.00 0.00 2020-11-15 2020-12-11 2021-01-10 sal Pit in Gambishere & 1 Sa tions nvelope mentation 9 tutional WASH) nitation Marketing Shed and 1 Incinerator in Tsentsehalu BY Assosa Woreda Health Off ice. ET-BGRS RHB-199642-CW-R FQ / Construction of 1 VIP la trine and 1 waste Disposal Pi Institutional Water Supply, S t in Mugufude HP ,1 Incinerat Request for Quota Single Stage - One E Under Imple 2021-04-1 IDA / 64450 anitation, and Hygiene (Insti Post Limited 11,800.00 0.00 2020-11-15 2020-12-10 2021-01-10 or in Megle 35, 1waste Dispo tions nvelope mentation 0 tutional WASH) sal Pit in Gumba & 1 sanitati on marketing Shed in Nebar Komishega by Assosa wored a Health Office. ET-BGRS RHB-199643-CW-R FQ / Construction of 1 VIP la Institutional Water Supply, S trine in Legabuna HP and , 1 Request for Quota Single Stage - One E Pending Imp 2021-04-1 IDA / 64450 anitation, and Hygiene (Insti Post Limited 12,100.00 0.00 2020-11-15 2021-01-10 VIP latrine and 1 Incinerator tions nvelope lementation 0 tutional WASH) & 1 west disposal in gipho H P by Dibate woreda Health Office. ET-BGRS RHB-199644-CW-R FQ / Construction of 1 west disposal pit , 1 sanitation ma rketing Shed and 1 Placenta Institutional Water Supply, S Request for Quota Single Stage - One E Pending Imp 2021-04-1 pit in Bereber health post an IDA / 64450 anitation, and Hygiene (Insti Post Limited 13,700.00 0.00 2020-11-15 2021-01-10 tions nvelope lementation 0 d 1 sanitation marketing Sh tutional WASH) ed in Gerth HP, 1 Incinerator in Hangtoke HP and 1 Inciner ator in Modermu by Dibate woreda health office. ET-BGRS RHB-199645-CW-R FQ / Construction of 1 VIP la Institutional Water Supply, S trine and 1 west disposal in J Request for Quota Single Stage - One E Pending Imp 2021-04-1 IDA / 64450 anitation, and Hygiene (Insti Post Limited 12,000.00 0.00 2020-11-15 2021-01-10 aja health post and 1 Inciner tions nvelope lementation 0 tutional WASH) ator and 1 VIP latrine in Bilbil a health post by Kamashi w oreda health office ET-BGRS RHB-204567-CW-R FQ / Construction of 1 VIP la trine ,1 west disposal, 1 Incin Institutional Water Supply, S Request for Quota Single Stage - One E Pending Imp 2021-07-2 erator and 1 placenta pit in IDA / 64450 anitation, and Hygiene (Insti Post Limited 15,000.00 0.00 2020-12-05 2021-01-30 tions nvelope lementation 9 Mirmita health center and 1 s tutional WASH) anitation marketing shade in Kemashi health center by Kamashi woreda health offi ce ET-BGRS RHB-214025-CW-R Urban Water Supply, Sanitati FQ / Construction of one sani Request for Quota Single Stage - One E Pending Imp 2021-05-1 IDA / 64450 on, and Hygiene (Urban WAS Post Limited 3,500.00 0.00 2021-02-03 2021-03-31 tation marketing shade for D tions nvelope lementation 5 H) alti Town by Beldigilu woreda Health Office. Page 2 ET-BGRS WIERDB-214147-C W-RFQ / Construction and ins Rural Water Supply, Sanitati tallation of 2 hand dug wells Request for Quota Single Stage - One E Under Imple 2021-05-1 IDA / 64450 on, and Hygiene (Rural WAS Post Limited 5,300.00 0.00 2021-02-03 2021-03-09 2021-03-31 with hand pumps in Assosa w tions nvelope mentation 5 H) oreda by Woreda Water, Min es and Energy Resources De velopment Office ET-BGRS WIERDB-188044-C W-RFB / Construction of Civil Works, Supply & Installation of Pipes and Fittings and Elec Urban Water Supply, Sanitati Single Stage - One E 2022-01-2 tro-Mechanical Equipment for IDA / 64450 on, and Hygiene (Urban WAS Post Request for Bids Open - National 1,237,409.00 0.00 Canceled 2020-09-21 2020-11-19 2020-09-26 2020-10-26 2020-12-24 2020-11-25 2020-12-30 nvelope 4 Dalati Small Town Water Sup H) ply and Sanitation Project by BGRS water irrigation and en ergy resource development b ureau OWNP PMU. ET-BGRS WIERDB-204576-C W-RFB / Description Drilling and construction of 2 4 shallow wells(20 for comm Rural Water Supply, Sanitati Single Stage - One E 2021-09-1 unity, 2 for school and 2 for h IDA / 64450 on, and Hygiene (Rural WAS Post Request for Bids Open - National 132,000.00 0.00 Canceled 2020-11-30 2020-12-16 2020-12-05 2021-01-16 2021-02-21 2021-02-15 2021-03-22 nvelope 8 ealth institution) in Kamashi H) Woreda by BGRS Water, Irrig ation and Energy Resources Development Bureau One W aSH National Program Manag ement Uni ET-BGRS WIERDB-204578-C W-RFB / Description Drilling and construction of 2 6 shallow wells(20 for comm Rural Water Supply, Sanitati Single Stage - One E 2021-09-1 unity, 2 for school and 4 for IDA / 64450 on, and Hygiene (Rural WAS Post Request for Bids Open - National 143,000.00 0.00 Canceled 2020-11-30 2020-12-16 2020-12-05 2021-01-16 2021-01-21 2021-02-15 2021-03-22 nvelope 8 health institution) in Dibati H) Woreda by BGRS Water, Irrig ation and Energy Resources Development Bureau One W aSH National Program Manag ement Unit ET-BGRS WIERDB-262537-C W-RFB / Construction of Civil Work, Supply & Installation of Request for Bids - Urban Water Supply, Sanitati Pipe & Fittings & Electro Mec Single Stage - One E Small Works SPD Under Imple 2022-09-0 IDA / 64450 on, and Hygiene (Urban WAS Post Request for Bids Open - National 1,562,500.00 0.00 2021-11-30 2022-03-04 2021-12-05 2022-01-04 2022-02-03 2022-03-10 hanical Equipment for Dalti T nvelope (1 envelope proce mentation 6 H) own Water Supply & Sanitati ss) on Project by BGRS Water Irri gation Energy Resource Dev elopment Bureau OWNP PMU . ET-BGRS REB-262720-CW-R FB / Construction of new two National Procure block inclusive & improved l Institutional Water Supply, S ment Document - Request for Quota Single Stage - One E Pending Imp 2022-04-3 atrine and one block (MHM) IDA / 64450 anitation, and Hygiene (Insti Post Limited 1 Envelope proce 25,000.00 0.00 2021-12-05 2022-01-30 tions nvelope lementation 0 Mensural hygiene managem tutional WASH) ss (Non Bank-SPD ent with incinerator at Akud ) a primary school by Asosa w oredas Finance office. ET-BGRS REB-262728-CW-R FB / Construction of new two block inclusive & improved l Institutional Water Supply, S Request for Quota Request for Quota Single Stage - One E Under Imple 2022-04-3 atrine and one block (MHM) IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 25,000.00 0.00 2021-12-05 2022-01-30 tions nvelope mentation 0 Mensural hygiene managem tutional WASH) PD) ent with incinerator at Basha buda primary Schools by As osa woredas Finance office. ET-BGRS REB-262729-CW-R FB / Construction of new two block inclusive & improved l Institutional Water Supply, S Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-04-3 atrine and one block (MHM) IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 25,000.00 0.00 2021-12-05 2022-01-30 tions nvelope lementation 0 Mensural hygiene managem tutional WASH) PD) ent with incinerator for Sch ools by Dibati woredas Finan ce office. ET-BGRS RHB-262878-CW-R FB / Construction of 1 VIP L. a t Gipo HP, 1 placentae pit an d 1 SM shade at Galessa HC, Institutional Water Supply, S Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-04-3 1 VIP L. and 1 inclinator at Le IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 23,100.00 0.00 2021-12-05 2022-01-30 tions nvelope lementation 0 gabuna HP, 1 inclinator at Mu tutional WASH) PD) dermo HP,1 WD pit at Bachat i HP,1 inclinator and 1 west d isposal pit at Jane HP by Diba ti woreda Finance Office. ET-BGRS RHB-262879-CW-R FB / Construction of 1 VIP L. a nd 1WD pit at Zigi HP, 1VIP Institutional Water Supply, S Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-04-3 L. and 1 inclinator at Gireze IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 31,600.00 0.00 2021-12-05 2022-01-30 tions nvelope lementation 0 HP, 1 VIP L. and 1WD pit at G tutional WASH) PD) ireze HC and 1 sanitation m arketing shade at Dibati HC by Dibati woreda Finance Offi ce. ET-BGRS RHB-262938-CW-R FB / Construction of 1 Inclinat or and 1WD pit at Rubalaged Institutional Water Supply, S Request for Quota a HP,1 Inclinator and 1WD pit Request for Quota Single Stage - One E Pending Imp 2022-04-3 IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 10,200.00 0.00 2021-12-05 2022-01-30 at Ateto, 1Placenta pit at Ga tions nvelope lementation 0 tutional WASH) PD) mbshire HP,1WD pit at Kushe mengle and 1 Inclinator and 1WD pit at Megele 29 by Ass osa woreda Finance office. ET-BGRS RHB-262940-CW-R FB / Construction of 1 Inclinat or and 1WD pit at Amba 10 H P, 1 SM shade at Gunba HC, Institutional Water Supply, S Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-04-3 1 Inclinator and 1 WD pit at IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 14,100.00 0.00 2021-12-05 2022-01-30 tions nvelope lementation 0 Bermili HP , 1 Inclinator and tutional WASH) PD) 1WD pit at Selega 23,1 Inclin ator and 1WD pit at Selga 24 and 1 WD pit at Tsentsalu by Assosa Woreda Financ office. ET-BGRS WIERDB-283285-C W-RFQ / Drilling and construc Rural Water Supply, Sanitati Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-11-2 tion of one hand dug well in IDA / 64450 on, and Hygiene (Rural WAS Post Limited tions (Non Bank-S 2,400.00 0.00 2022-04-04 2022-05-30 tions nvelope lementation 6 Assosa Woreda Water, Mines H) PD) and Energy Resources Devel opment Office Page 3 ET-BGRS RHB-330170-CW-R FQ / Construction of 1 VIP latr ine at Nubar Komishega HP,1 inclinator and 1 west disposa Institutional Water Supply, S Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-04-1 l pit at Megele 33 HP ,1 inclin IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 28,480.00 0.00 2022-12-17 2023-01-16 tions nvelope lementation 6 ator and 1 west disposal pit a tutional WASH) PD) t Megele 38 HP, 1 inclinator a t Megele 30 HP and 1 WDP at Gambishere HP by Abroma w oreda finance office. ET-BGRS RHB-330172-CW-R FQ / Rehabilitation and install Institutional Water Supply, S Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-04-1 ation of pump for existed wa IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 14,614.00 0.00 2022-12-17 2023-01-16 tions nvelope lementation 6 ter scheme (HDW) at selga 2 tutional WASH) PD) 2 health center by Ura wored a finance office. ET-BGRS RHB-330179-CW-R FQ / Construction of 1 placen ta pit, 1 inclinator and 1 WD Institutional Water Supply, S Request for Quota P at Dibati HC, 1 market bas Request for Quota Single Stage - One E Pending Imp 2023-04-2 IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 40,100.00 0.00 2022-12-17 2023-01-26 ed sanitation center (shade) tions nvelope lementation 6 tutional WASH) PD) at dibati Kebele, 1 VIP latrin e and 1 WDP at Zeghe HP an d 1 inclinator and 1 WDP at P arzeyit HP, by Dibati woreda Finance office. ET-BGRS REB-320975-CW-R Institutional Water Supply, S Request for Quota FQ / Construction of 1 block Request for Quota Single Stage - One E Pending Imp 2023-04-1 IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 13,200.00 0.00 2022-12-17 2023-01-16 MHM for Abramo primary sc tions nvelope lementation 6 tutional WASH) PD) hool by Abramo woreda finan ce office. ET-BGRS REB-320962-CW-R Institutional Water Supply, S Request for Quota FB / Construction of 1 block Request for Quota Single Stage - One E Pending Imp 2023-04-1 IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 13,200.00 0.00 2022-12-17 2023-01-16 MHM room for Zigihe primar tions nvelope lementation 6 tutional WASH) PD) y school by Dibati woreda Fi nance office. ET-BGRS RHB-330249-CW-R FQ / Construction of 1 VIP latr ine and 1 inclinator at Gireze Institutional Water Supply, S Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-04-1 HP,1 WDP at Gireze HC, 1 VI IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 38,700.00 0.00 2022-12-17 2023-01-16 tions nvelope lementation 6 P latrine and 1 inclinator at tutional WASH) PD) Legabuna HP and 1 Inclinator and 1 WDP at Mondermo HP, by Dibati woreda Finance offi ce. ET-BGRS RHB-330253-CW-R FQ / Construction of 1 VIP latr ine, 1 placenta pit, 1 inclinat Institutional Water Supply, S Request for Quota or and 1 WDP at Bereber H Request for Quota Single Stage - One E Pending Imp 2023-04-1 IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 71,000.00 0.00 2022-12-17 2023-01-16 C, 1VIP latrine at Gipo HP , 1 tions nvelope lementation 6 tutional WASH) PD) inclinator ,1 WDP at Galessa HC and 1 market based sani tation center (shade) at Gale ssa Kebele by Dibati woreda Finance office. ET-BGRS RHB-330261-CW-R Urban Water Supply, Sanitati Request for Quota FQ / Construction of Market B Request for Quota Single Stage - One E Pending Imp 2023-04-1 IDA / 64450 on, and Hygiene (Urban WAS Post Limited tions (Non Bank-S 6,700.00 0.00 2022-12-17 2023-01-16 ased Sanitation Center (Shad tions nvelope lementation 6 H) PD) e) at Dobi Town by Bulen wor eda Finance office ET-BGRS RHB-343727-CW-R Institutional Water Supply, S Request for Quota FQ / Construction of 1 Inciner Request for Quota Single Stage - One E Pending Imp 2023-05-1 IDA / 64450 anitation, and Hygiene (Insti Post Limited tions (Non Bank-S 2,990.00 0.00 2023-03-04 2023-04-15 ator at Gambishere health po tions nvelope lementation 5 tutional WASH) PD) st by Aburamo woreda finan ce office. ET-BGRS RHB-283950-CW-R FQ / Construction of one sani Urban Water Supply, Sanitati Request for Quota Request for Quota Single Stage - One E 2022-07-1 tation marketing shade in B IDA / 64450 on, and Hygiene (Urban WAS Post Limited tions (Non Bank-S 3,000.00 0.00 Canceled 2022-04-04 2022-05-16 tions nvelope 5 ulen woreda Dobi Town by B H) PD) ulen woreda finance office. ET-BGRS RHB-214023-CW-R Urban Water Supply, Sanitati FQ / Construction of one sani Request for Quota Single Stage - One E 2021-05-1 IDA / 64450 on, and Hygiene (Urban WAS Post Limited 3,500.00 0.00 Canceled 2021-02-03 2021-03-31 tation marketing shade for D tions nvelope 5 H) obi Town by Bulen woreda H ealth Office. ET-BGRS WIERDB-320933-C W-RFB / Drilling and Construc Request for Bids - tion of 22 shallow well (10 for Rural Water Supply, Sanitati Single Stage - One E Small Works SPD Pending Imp 2024-03-1 community,6 for health instit IDA / 64450 on, and Hygiene (Rural WAS Post Request for Bids Open - National 207,547.00 0.00 2023-05-29 2023-06-03 2023-07-15 2023-08-14 2023-09-18 nvelope (1 envelope proce lementation 6 ution and 6 for schools) for D H) ss) ibati woreda by BGRS Water I rrigation and Energy Resourc e development Bureau OWN P PMU. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-BGRS WIERDB-154155-G O-RFQ / Procurement of 12 H and Held GPS by BGRS Water Institutional Strengthening a Request for Quota Single Stage - One E IDA / 64450 Post Open - National 1,916.67 532.79 Completed 2020-03-01 2020-05-11 2020-06-20 2020-06-10 2020-07-07 , Irrigation and Energy Resou nd Project Management tions nvelope rces Development Bureau On e WaSH National Program Ma nagement Unit ET-BGRS WIERDB-154169-G O-RFQ / Procurement of offic e equipment (Lot I=10 Lapto Rural Water Supply, Sanitati p computer with accessories, Request for Quota Single Stage - One E IDA / 64450 on, and Hygiene (Rural WAS Post Open - National 12,266.67 2,380.72 Completed 2020-03-01 2020-05-11 2020-05-30 2020-06-10 2020-07-07 Lot 2=7 printers, Lot 3= 5 de tions nvelope H) sktop computer with accesso ries and Lot 4= 4 A4 scanner ) by BGRS water irrigation a nd energy resource develop ment bureau. ET-BGRS WIERDB-154177-G O-RFQ / Procurement of High quality 20 guest chairs and Rural Water Supply, Sanitati Request for Quota Single Stage - One E 12 managerial chair by BGRS IDA / 64450 on, and Hygiene (Rural WAS Post Open - National 1,533.33 91.03 Completed 2020-03-01 2020-05-11 2020-07-02 2020-06-10 2020-07-07 tions nvelope Water, Irrigation and Energy H) Resources Development Bur eau One WaSH National Prog ram Management Unit Page 4 ET-BGRS WIERDB-154189-G O-RFQ / Procurement of hand Rural Water Supply, Sanitati Request for Quota Single Stage - One E pump Spare parts as seed m IDA / 64450 on, and Hygiene (Rural WAS Post Open - National 2,886.11 532.38 Completed 2020-04-06 2020-06-23 2020-09-04 2020-07-23 2020-09-04 tions nvelope aterials by Assosa woreda w H) ater mine and energy resour ce development office. ET-BGRS WIERDB-154196-G O-RFQ / Procurement of hand Rural Water Supply, Sanitati Request for Quota Single Stage - One E Pending Impl pump Spare parts as seed m IDA / 64450 on, and Hygiene (Rural WAS Post Open - National 2,886.11 0.00 2020-04-06 2020-06-09 2020-07-24 tions nvelope ementation aterials by Dibati woreda wat H) er mine and energy resource development office. ET-BGRS WIERDB-154197-G O-RFQ / Procurement of han Rural Water Supply, Sanitati d pump Spare parts as seed Request for Quota Single Stage - One E Pending Impl IDA / 64450 on, and Hygiene (Rural WAS Post Open - National 2,886.11 0.00 2020-04-06 2020-06-23 2020-07-23 materials by Kemashi wored tions nvelope ementation H) a Water, Mines and Energy R esources Development Office ET-BGRS WIERDB-198960-G O-RFQ / procurement of hand pump spare parts for progra Rural Water Supply, Sanitati Request for Quota Single Stage - One E m woreda (Assosa,Dibati and IDA / 64450 on, and Hygiene (Rural WAS Post Limited 8,000.00 5,597.31 Terminated 2020-11-15 2021-02-17 2021-01-10 2021-03-05 2021-02-24 tions nvelope Kemashi) as seed material by H) BGRS water irrigation and en ergy resource development b ureau ET-BGRS WIERDB-198968-G O-RFQ / procurement of offic e equipment 8 laptop comp Rural Water Supply, Sanitati uter,5 Desktop computer and Request for Quota Single Stage - One E IDA / 64450 on, and Hygiene (Rural WAS Post Limited 10,200.00 7,250.92 Completed 2020-12-05 2021-02-17 2021-01-30 2021-03-06 2021-03-16 2021-03-09 1 LCD projector with accesso tions nvelope H) ries for PMU,RWCO and Pro gram woredas by BGRS wate r irrigation and energy resour ce development bureau. ET-BGRS RHB-199649-GO-R FQ / Procurement of office eq Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl uipment 7 Laptop computer IDA / 64450 Post Limited 6,000.00 0.00 2020-12-05 2021-01-30 2021-03-16 nd Project Management tions nvelope ementation with accessories, 1 LCD Proj ector and 1 Digital camera b y BGRS RHB. ET-BGRS REB-199309-GO-RF Q / Procurement of office eq uipment 3 Laptop computer Institutional Water Supply, S Request for Quota Single Stage - One E with accessories, 4 Printer, 1 IDA / 64450 anitation, and Hygiene (Insti Post Limited 7,700.00 1,567.40 Completed 2020-12-05 2020-05-11 2021-01-30 2021-05-30 2021-02-03 2021-05-30 tions nvelope LCD Projector and 1 photoco tutional WASH) py Machine for program wore da and Bureau by BGRS Edu cation Bureau. ET-RHB RHB-213878-GO-RF Q / procurement of equipmen t and seed materials for 2 sa Institutional Water Supply, S Request for Quota Single Stage - One E Pending Impl nitation marketing centers a IDA / 64450 anitation, and Hygiene (Insti Post Limited 4,000.00 0.00 2021-02-03 2021-03-31 2021-05-15 tions nvelope ementation s initial start up slab producti tutional WASH) on for organized small scale enterprise by Dibati woreda Health office. ET-BGRS RHB-214015-GO-R FQ / procurement of equipme nt and seed materials for 2 s Institutional Water Supply, S Request for Quota Single Stage - One E Pending Impl anitation marketing centers IDA / 64450 anitation, and Hygiene (Insti Post Limited 4,000.00 0.00 2021-02-03 2021-03-31 2021-05-15 tions nvelope ementation as initial start up slab produ tutional WASH) ction for organized small scal e enterprises by Assosa wor eda Health office. ET-BGRS RHB-214019-GO-R FQ / procurement of equipme nt and seed materials for 1 s Institutional Water Supply, S Request for Quota Single Stage - One E Pending Impl anitation marketing centers IDA / 64450 anitation, and Hygiene (Insti Post Limited 2,000.00 0.00 2021-02-03 2021-03-31 2021-05-15 tions nvelope ementation as initial start up slab produ tutional WASH) ction for organized small scal e enterprises by Kemashi wo reda Health office. ET-BGRS RHB-214020-GO-R FQ / procurement of equipme nt and seed materials for 1 s Urban Water Supply, Sanitati Request for Quota Single Stage - One E Pending Impl anitation marketing centers IDA / 64450 on, and Hygiene (Urban WAS Post Limited 1,500.00 0.00 2021-02-03 2021-03-31 2021-05-15 tions nvelope ementation as initial start up slab produ H) ction for Dalti Town organize d small scale enterprises by Beldigilu woreda Health offic e. ET-BGRS REB-262731-GO-RF Institutional Water Supply, S Q / Procurement of 2 Laptop Request for Quota Single Stage - One E Pending Impl IDA / 64450 anitation, and Hygiene (Insti Post Limited 2,300.00 0.00 2021-12-05 2022-01-23 2022-02-07 computers with accessories f tions nvelope ementation tutional WASH) or regional PMUs by Regional Education Bureau. ET-BGRS REB-263018-GO-RF B / Procurement of 10 Lapto Institutional Water Supply, S Request for Quota Single Stage - One E Pending Impl p computer and 1 LCD Proje IDA / 64450 anitation, and Hygiene (Insti Post Limited 11,300.00 0.00 2021-12-05 2022-01-30 2022-02-14 tions nvelope ementation ctor for woreda and Regional tutional WASH) program experts by BGRS He alth Bureau ET-BGRS-REB-263019-GO-RF Institutional Water Supply, S B / Procurement of 4 table, 4 Request for Quota Single Stage - One E Pending Impl IDA / 64450 anitation, and Hygiene (Insti Post Limited 5,400.00 0.00 2021-12-05 2022-01-30 2022-02-14 gust chair and 4 shelf by BG tions nvelope ementation tutional WASH) RS Health Bureau. ET-BGRS WIERDB-263021-G Rural Water Supply, Sanitati O-RFB / procurement of hand Request for Quota Single Stage - One E Pending Impl IDA / 64450 on, and Hygiene (Rural WAS Post Limited 2,400.00 0.00 2021-12-05 2022-01-30 2022-02-14 pump spare parts as seed m tions nvelope ementation H) aterial by Kemashi woreda Fi nance Office. ET-BGRS WIERDB-263022-G Rural Water Supply, Sanitati O-RFB / procurement of hand Request for Quota Single Stage - One E Pending Impl IDA / 64450 on, and Hygiene (Rural WAS Post Limited 2,400.00 0.00 2021-12-05 2022-01-30 2022-02-14 pump spare parts as seed m tions nvelope ementation H) aterial by Dibati woreda Fina nce Office. ET-BGRS RHB-283561-GO-R FQ / Procurement of seed ma terials (sand, gravel, cement and steel bar ) for sanitation Institutional Water Supply, S Request for Quota Single Stage - One E Pending Impl marketing centers as initial IDA / 64450 anitation, and Hygiene (Insti Post Limited 5,300.00 0.00 2022-04-04 2022-05-23 2022-06-22 tions nvelope ementation start up slab production for tutional WASH) 3 sanitation marketing shade s (Tsentsalu, Gumba and Neb are komishega) by Assosa woreda finance office Page 5 ET-BGRS RHB-283947-GO-R FQ / Procurement of seed ma terials (sand, gravel, cement Rural Water Supply, Sanitati and steel bar ) for sanitation Request for Quota Single Stage - One E Pending Impl IDA / 64450 on, and Hygiene (Rural WAS Post Limited 1,100.00 0.00 2022-04-04 2022-05-16 2022-07-15 marketing centers as initial s tions nvelope ementation H) tart up slab production for o rganized small scale enterpri ses in Bildigilu woreda (Dale ti Town) by Bildigilu woreda fi nance offoce. ET-BGRS RHB-330160-GO-R FQ / Procurement of 6 table, Rural Water Supply, Sanitati Request for Quota Single Stage - One E Pending Impl 6 chair and 6 shelf for Abram IDA / 64450 on, and Hygiene (Rural WAS Post Limited 3,559.00 0.00 2022-12-17 2023-01-11 2023-01-26 tions nvelope ementation o, Ura, Dibati, Kemashi wore H) das and Health Bureau by re gional Health bureau. ET-BGRS REB-320960-GO-RF Q / Procurement of two lapto Institutional Strengthening a Request for Quota Single Stage - One E Pending Impl IDA / 64450 Post Limited 2,909.00 0.00 2022-12-17 2023-01-17 2023-02-01 p computer 1 for Abramo wo nd Project Management tions nvelope ementation reda and 1 for REB by Region al Education bureau ET-BGRS RHB-343590-GO-R FQ / procurement of 2 Deskto Rural Water Supply, Sanitati p computer for Aburamo and Request for Quota Single Stage - One E Pending Impl IDA / 64450 on, and Hygiene (Rural WAS Post Limited 4,111.00 0.00 2023-03-03 2023-04-28 2023-05-28 Dibati woreda and 1 LCD pro tions nvelope ementation H) jector for regional health bur eau by regional Health Bure au. ET-BGRS WIERDB-359381-G O-RFQ / Procurement of hand pump spare parts Lot 1-for Di batie, Lot 2-for Kemashi, Lot Rural Water Supply, Sanitati Request for Quota Single Stage - One E Under Imple 3-for Ura and Lot 4-for Abura IDA / 64450 on, and Hygiene (Rural WAS Post Limited 11,129.00 0.00 2023-06-05 2023-07-17 2023-08-01 tions nvelope mentation mo woreda Water Offices by H) Dibatie, Kemashi, Ura and A buramo woreda finance offic es.(2900,2900,2617 and 271 2 USD respectively) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-BGRS WIERDB-154146-C S-INDV / Recruitment of one senior procurement manage ment specialist for water bur Institutional Strengthening a Individual Consult Under Implement IDA / 64450 Prior Open 8,388.00 0.00 2020-03-02 2020-10-14 2020-04-20 2020-05-11 2020-06-15 2021-06-15 eau management unit by BG nd Project Management ant Selection ation RS Water, Irrigation and Ener gy Resources Development B ureau One WaSH National Pr ogram Management Unit ET-BGRS WIERDB-157456-C S-INDV / Recruitment of 1 Ke y Staffs for Assosa Woredas Rural Water Supply, Sanitati Individual Consult WaSH Support Teams /Coordi IDA / 64450 on, and Hygiene (Rural WAS Post Open 3,896.20 2,996.37 Signed 2020-03-02 2020-06-03 2020-04-20 2020-03-27 2020-05-11 2020-04-03 2020-06-22 2020-04-04 2021-06-22 ant Selection nator/ by BGRS Water, Irrigat H) ion and Energy Resources De velopment Bureau One WaS H National Program Manage ment Unit ET-BGRS WIERDB-157458-C S-INDV / Recruitment of 1 Ke y Staffs for Dibati Woredas W Rural Water Supply, Sanitati Individual Consult aSH Support Teams /Coordin IDA / 64450 on, and Hygiene (Rural WAS Post Open 3,896.20 2,996.37 Signed 2020-03-02 2020-06-03 2020-04-20 2020-03-27 2020-05-11 2020-04-24 2020-06-22 2020-04-25 2021-06-22 ant Selection ator/ by BGRS Water, Irrigati H) on and Energy Resources De velopment Bureau One WaS H National Program Manage ment Unit ET-BGRS WIERDB-154304-C S-INDV / Recruitment of 1 Ke y Staffs for Kamashi Woredas Rural Water Supply, Sanitati Individual Consult WaSH Support Teams /Coordi IDA / 64450 on, and Hygiene (Rural WAS Post Open 3,896.20 2,998.36 Signed 2020-03-02 2020-06-03 2020-04-20 2020-03-30 2020-05-11 2020-04-03 2020-06-22 2020-04-04 2021-06-22 ant Selection nator/ by BGRS Water, Irrigat H) ion and Energy Resources De velopment Bureau One WaS H National Program Manage ment Unit Page 6 PROCUREMENT PLAN (Textual Part) Project information: Pakistan – Karachi Mobility Project – P166732 Project Implementation agency: Sindh Mass Transit Authority (SMTA) Date of the Procurement Plan: 11 February 2020 Period covered by this Procurement Plan: August 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 updated November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the most updated Sindh PPRA Rules, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1. The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2. For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5. Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6. No preference of any kind shall be given to national bidders in the bidding process. 7. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information: None. PROCUREMENT Pakistan : Karachi Mobility Project PLAN General Information Country: Pakistan 2020-02-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166732 GPN Date: 2020-01-28 Project Name: Karachi Mobility Project Loan / Credit No: IBRD / 89950 Sindh Mass Transit Authority Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-SMTA-197379-CW-RFB / Urban Road Infrastructure- Y Single Stage - Two E 12,000,000.0 Pending Imp 2022-09-0 IBRD / 89950 Prior Request for Bids Open - National 0.00 2021-10-03 2021-10-08 2021-10-28 2021-12-02 2021-12-12 Off-corridor Improvements w ellow Corridor nvelope 0 lementation 8 orks PK-SMTA-197393-CW-RFB / Urban Road Infrastructure- Y Single Stage - Two E Pending Imp 2021-09-2 IBRD / 89950 Post Request for Bids Open - National 4,000,000.00 0.00 2021-01-11 2021-01-16 2021-02-10 2021-03-12 2021-03-25 Road Maintenance and Drain ellow Corridor nvelope lementation 1 age PK-SMTA-197592-CW-RFB / P Urban Road Infrastructure- Y Open - Internationa Single Stage - Two E 24,000,000.0 2023-09-0 ackage 4: 1 km long bridge - IBRD / 89950 Prior Request for Bids 0.00 Canceled 2021-04-19 2021-05-04 2021-06-30 2021-08-20 2021-09-17 ellow Corridor l nvelope 0 7 DesignBuild Request for Propo PK-SMTA-266604-CW-RFP / P Urban Road Infrastructure- Y Request for Propo Open - Internationa Single Stage - Two E sal Design and Bu 24,000,000.0 2024-05-2 rocurement of: Package - 4 J IBRD / 89950 Prior 0.00 Canceled 2021-12-13 2021-12-27 2022-02-10 2022-04-25 2022-05-30 ellow Corridor sals l nvelope ild - Works SPD (S 0 9 AM SADIQ BRIDGE (SEGMENT ingle-stage) 3) Request for Bids - PK-SMTA-284417-CW-RFB / Urban Road Infrastructure- Y Single Stage - One E Small Works SPD 2022-12-0 CONSTRUCTION OF BOUNDA IBRD / 89950 Post Request for Bids Open - National 1,500,000.00 0.00 Canceled 2022-03-15 2022-07-13 2022-03-22 2022-07-27 2022-04-21 2022-08-30 2022-05-12 2022-06-09 ellow Corridor nvelope (1 envelope proce 6 RY WALL AND ALLIED FACILIT ss) IES AT DEPOT II PK-SMTA-334960-CW-RFP / P Request for Propo rocurement of Package - 4: N Urban Road Infrastructure- Y Request for Propo Open - Internationa Single Stage - Two E sal Design and Bu 59,000,000.0 Under Imple 2026-06-1 IBRD / 89950 Prior 0.00 2023-01-17 2023-02-14 2023-02-16 2023-02-28 2023-03-30 2023-05-09 2023-05-19 2023-06-12 EW JAM SADIQ BRIDGE (Yello ellow Corridor sals l nvelope ild - Works SPD (S 0 mentation 4 w Corridor Segment 3) ingle-stage) PK-SMTA-197341-CW-RFB / P Development and Operation Single Stage - Two E 2022-04-0 ackage-1 (Construction of De IBRD / 89950 alization of a BRT System – Y Post Request for Bids Open - National 7,800,000.00 0.00 Canceled 2021-05-07 2021-05-12 2021-06-07 2021-07-02 2021-07-06 nvelope 2 pot # 1 near Dawood Chaowr ellow Corridor angi) PK-SMTA-197347-CW-RFB / P Development and Operation Single Stage - Two E 12,300,000.0 2022-07-1 ackage-2 (Construction of De IBRD / 89950 alization of a BRT System – Y Prior Request for Bids Open - National 0.00 Canceled 2021-05-10 2021-05-15 2021-06-07 2021-07-07 2021-07-14 nvelope 0 4 pot # -2 near Indus Hospital) ellow Corridor Request for Bids - PK-SMTA-361710-CW-RFB / P Development and Operation Open - Internationa Single Stage - Two E Works (without pr 52,000,000.0 Under Imple 2025-09-0 rocurement of Package - 1: C IBRD / 89950 alization of a BRT System – Y Prior Request for Bids 0.00 2023-06-01 2023-06-06 2023-07-06 2023-08-25 2023-09-04 l nvelope equalification) SP 0 mentation 3 onstruction of Depot 1 and D ellow Corridor D epot 2 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SMTA-197012-GO-RFQ / S Capacity Building and Techn Request for Quota Single Stage - One E upply and Installation of offic IBRD / 89950 Post Open - National 15,000.00 9,021.61 Signed 2020-11-05 2021-05-24 2020-12-28 2021-09-07 2021-03-01 ical Assistance tions nvelope e furniture ( desks, chair etc. ) PK-SMTA-197002-GO-RFQ / S Capacity Building and Techn Request for Quota Single Stage - One E upply and Installation of Vide IBRD / 89950 Post Open - National 10,000.00 5,435.65 Signed 2020-10-26 2021-05-24 2020-12-16 2021-08-18 2021-03-01 ical Assistance tions nvelope o Conference Equipment Set PK-SMTA-197006-GO-RFQ / S Capacity Building and Techn Request for Quota Single Stage - One E upply and Installation of IT e IBRD / 89950 Post Open - National 33,000.00 0.00 Canceled 2020-10-20 2021-05-24 2020-12-02 2021-02-01 ical Assistance tions nvelope quipment ( computers, printe rs, scanner etc.) PK-SMTA-261316-GO-RFQ / P Capacity Building and Techn Request for Quota Single Stage - One E rocurement of: Office IT Equi IBRD / 89950 Post Open - National 33,000.00 30,566.29 Signed 2021-11-04 2021-11-19 2021-11-29 2021-10-28 2021-12-29 ical Assistance tions nvelope pment for Project Manageme nt Team PK-SMTA-333024-GO-RFQ / E stablishment of Office Portio n in SMTA Premises for Proje Capacity Building and Techn Request for Quota Single Stage - One E Pending Impl IBRD / 89950 Post Open - National 20,000.00 0.00 2023-01-04 2023-02-15 2023-05-16 ct Management team which i ical Assistance tions nvelope ementation ncludes Project Director, Spe cialists, Engineers and Techn ical Staff NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SMTA-122605-CS-QCBS / Activity -1 Title: Procurement of Consult Urban Road Infrastructure- Y Quality And Cost- Open - Internationa IBRD / 89950 Prior 15,036,000.00 9,451,030.00 Signed 2020-02-14 2020-02-14 2020-03-13 2020-03-13 2020-04-09 2020-11-05 2020-05-25 2021-01-15 2020-06-15 2021-04-08 2020-07-20 2021-07-20 2020-08-07 2021-09-06 2025-08-06 ing Services for Detail design ellow Corridor Based Selection l , procurement support and c onstruction supervision Page 1 PK-SMTA-196995-CS-QCBS / Project Management Consult ant is to be procured to ensu re professional, efficient and Capacity Building and Techn Quality And Cost- Open - Internationa Pending Impleme IBRD / 89950 Prior 1,000,000.00 0.00 2020-10-20 2020-11-02 2020-12-31 2021-02-11 2021-03-08 2021-03-22 2021-04-26 2022-04-26 optimal facilitation and coord ical Assistance Based Selection l ntation ination of the Project activitie s and assist the Project Mana gement Team and ensure ca pacity building to SMTA. PK-SMTA-219016-CS-CQS / D esign and develop a dynamic website with strong functiona lities and attractive content d Capacity Building and Techn Consultant Qualifi Under Implement IBRD / 89950 Post Open - National 20,000.00 0.00 2021-02-21 2021-02-18 2021-03-14 2022-09-01 2021-04-27 2021-05-27 2021-07-01 2025-07-05 isplay that can be easily navi ical Assistance cation Selection ation gated by a variety of user gr oups and that function as a d ynamic, up-to-date data/infor mation portal for SMTA. PK-SMTA-196998-CS-QCBS / Transit Oriented Developmen t Strategy Alongside BRT Yell ow-line Corridor for conducti Development and Operation Quality And Cost- Open - Internationa Pending Impleme ng feasibility study on Transit IBRD / 89950 alization of a BRT System – Y Post 750,000.00 0.00 2022-12-20 2022-12-31 2023-02-28 2023-04-14 2023-05-04 2023-05-19 2023-06-24 2024-06-23 Based Selection l ntation Oriented Development & Rou ellow Corridor tes, Development of TOD Str ategy in the City, Developing PPP Transaction Advisory and Land Value Capture Plan. PK-SMTA-341298-CS-QCBS / Procurement of Transaction Development and Operation Quality And Cost- Open - Internationa Under Implement Advisory Services under PPP IBRD / 89950 alization of a BRT System – Y Post 500,000.00 0.00 2023-02-08 2023-02-14 2023-02-22 2023-03-04 2023-04-07 2023-06-02 2023-05-07 2023-06-06 2023-07-04 2023-08-08 2025-02-08 Based Selection l ation Mode for Supply and Operati ellow Corridor on of Buses for Yellow Line B RTS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SMTA-197399-NC-RFB / I Capacity Building and Techn Individual Consult ndividual Consultant for Web IBRD / 89950 Post Open 7,000.00 0.00 Canceled 2020-12-01 2021-01-06 2021-01-08 2021-01-13 2021-07-12 ical Assistance ant Selection Development PK-SMTA-296961-CS-INDV / Capacity Building and Techn Individual Consult Procurement and Contract M IBRD / 89950 Post Limited 24,000.00 0.00 Under Review 2022-06-01 2022-05-27 2022-06-08 2022-06-10 2022-06-20 2023-06-20 ical Assistance ant Selection anagement Specialist PK-SMTA-302815-CS-INDV / Gender-Based Violence Traini ng Consultant The GBV consultant is part of Development and Operation Individual Consult Under Implement GAP to mitigate the risk of G IBRD / 89950 alization of a BRT System – Y Post ant Selection Limited 25,000.00 0.00 ation 2022-07-05 2022-07-17 2022-07-15 2022-07-18 2022-07-27 2023-07-27 BV during project implement ellow Corridor ation. The trainer will train th e community representatives who serve on the GBV commi ttee and relevant stakeholde rs. Page 2 PROCUREMENT PLAN (Textual Part) Project information: Pakistan – Karachi Mobility Project – P166732 Project Implementation agency: Sindh Mass Transit Authority (SMTA) Date of the Procurement Plan: 11 February 2020 Period covered by this Procurement Plan: August 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 updated November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the most updated Sindh PPRA Rules, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1. The eligibility of bidders shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 2. For national open competitive procurement, only the model procurement documents acceptable to the World Bank, shall be used. 3. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance (in the form attached) at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 4. Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts 5. Access to procurement opportunities shall not be restricted to firms that have pre-registered and/or paid a registration fee. 6. No preference of any kind shall be given to national bidders in the bidding process. 7. When other national procurement arrangements (other than national open competitive procurement) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information: None. PROCUREMENT Pakistan : Karachi Mobility Project PLAN General Information Country: Pakistan 2020-02-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P166732 GPN Date: 2020-01-28 Project Name: Karachi Mobility Project Loan / Credit No: IBRD / 89950 Sindh Mass Transit Authority Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PK-SMTA-197379-CW-RFB / Urban Road Infrastructure- Y Single Stage - Two E 12,000,000.0 Pending Imp 2022-09-0 IBRD / 89950 Prior Request for Bids Open - National 0.00 2021-10-03 2021-10-08 2021-10-28 2021-12-02 2021-12-12 Off-corridor Improvements w ellow Corridor nvelope 0 lementation 8 orks PK-SMTA-197393-CW-RFB / Urban Road Infrastructure- Y Single Stage - Two E Pending Imp 2021-09-2 IBRD / 89950 Post Request for Bids Open - National 4,000,000.00 0.00 2021-01-11 2021-01-16 2021-02-10 2021-03-12 2021-03-25 Road Maintenance and Drain ellow Corridor nvelope lementation 1 age PK-SMTA-197592-CW-RFB / P Urban Road Infrastructure- Y Open - Internationa Single Stage - Two E 24,000,000.0 2023-09-0 ackage 4: 1 km long bridge - IBRD / 89950 Prior Request for Bids 0.00 Canceled 2021-04-19 2021-05-04 2021-06-30 2021-08-20 2021-09-17 ellow Corridor l nvelope 0 7 DesignBuild Request for Propo PK-SMTA-266604-CW-RFP / P Urban Road Infrastructure- Y Request for Propo Open - Internationa Single Stage - Two E sal Design and Bu 24,000,000.0 2024-05-2 rocurement of: Package - 4 J IBRD / 89950 Prior 0.00 Canceled 2021-12-13 2021-12-27 2022-02-10 2022-04-25 2022-05-30 ellow Corridor sals l nvelope ild - Works SPD (S 0 9 AM SADIQ BRIDGE (SEGMENT ingle-stage) 3) Request for Bids - PK-SMTA-284417-CW-RFB / Urban Road Infrastructure- Y Single Stage - One E Small Works SPD 2022-12-0 CONSTRUCTION OF BOUNDA IBRD / 89950 Post Request for Bids Open - National 1,500,000.00 0.00 Canceled 2022-03-15 2022-07-13 2022-03-22 2022-07-27 2022-04-21 2022-08-30 2022-05-12 2022-06-09 ellow Corridor nvelope (1 envelope proce 6 RY WALL AND ALLIED FACILIT ss) IES AT DEPOT II PK-SMTA-334960-CW-RFP / P Request for Propo rocurement of Package - 4: N Urban Road Infrastructure- Y Request for Propo Open - Internationa Single Stage - Two E sal Design and Bu 59,000,000.0 Under Imple 2026-06-1 IBRD / 89950 Prior 0.00 2023-01-17 2023-02-14 2023-02-16 2023-02-28 2023-03-30 2023-05-09 2023-05-19 2023-06-12 EW JAM SADIQ BRIDGE (Yello ellow Corridor sals l nvelope ild - Works SPD (S 0 mentation 4 w Corridor Segment 3) ingle-stage) PK-SMTA-197341-CW-RFB / P Development and Operation Single Stage - Two E 2022-04-0 ackage-1 (Construction of De IBRD / 89950 alization of a BRT System – Y Post Request for Bids Open - National 7,800,000.00 0.00 Canceled 2021-05-07 2021-05-12 2021-06-07 2021-07-02 2021-07-06 nvelope 2 pot # 1 near Dawood Chaowr ellow Corridor angi) PK-SMTA-197347-CW-RFB / P Development and Operation Single Stage - Two E 12,300,000.0 2022-07-1 ackage-2 (Construction of De IBRD / 89950 alization of a BRT System – Y Prior Request for Bids Open - National 0.00 Canceled 2021-05-10 2021-05-15 2021-06-07 2021-07-07 2021-07-14 nvelope 0 4 pot # -2 near Indus Hospital) ellow Corridor Request for Bids - PK-SMTA-361710-CW-RFB / P Development and Operation Open - Internationa Single Stage - Two E Works (without pr 52,000,000.0 Under Imple 2025-09-0 rocurement of Package - 1: C IBRD / 89950 alization of a BRT System – Y Prior Request for Bids 0.00 2023-06-01 2023-06-06 2023-07-06 2023-08-25 2023-09-04 l nvelope equalification) SP 0 mentation 3 onstruction of Depot 1 and D ellow Corridor D epot 2 GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SMTA-197012-GO-RFQ / S Capacity Building and Techn Request for Quota Single Stage - One E upply and Installation of offic IBRD / 89950 Post Open - National 15,000.00 9,021.61 Signed 2020-11-05 2021-05-24 2020-12-28 2021-09-07 2021-03-01 ical Assistance tions nvelope e furniture ( desks, chair etc. ) PK-SMTA-197002-GO-RFQ / S Capacity Building and Techn Request for Quota Single Stage - One E upply and Installation of Vide IBRD / 89950 Post Open - National 10,000.00 5,435.65 Signed 2020-10-26 2021-05-24 2020-12-16 2021-08-18 2021-03-01 ical Assistance tions nvelope o Conference Equipment Set PK-SMTA-197006-GO-RFQ / S Capacity Building and Techn Request for Quota Single Stage - One E upply and Installation of IT e IBRD / 89950 Post Open - National 33,000.00 0.00 Canceled 2020-10-20 2021-05-24 2020-12-02 2021-02-01 ical Assistance tions nvelope quipment ( computers, printe rs, scanner etc.) PK-SMTA-261316-GO-RFQ / P Capacity Building and Techn Request for Quota Single Stage - One E rocurement of: Office IT Equi IBRD / 89950 Post Open - National 33,000.00 30,566.29 Signed 2021-11-04 2021-11-19 2021-11-29 2021-10-28 2021-12-29 ical Assistance tions nvelope pment for Project Manageme nt Team PK-SMTA-333024-GO-RFQ / E stablishment of Office Portio n in SMTA Premises for Proje Capacity Building and Techn Request for Quota Single Stage - One E Pending Impl IBRD / 89950 Post Open - National 20,000.00 0.00 2023-01-04 2023-02-15 2023-05-16 ct Management team which i ical Assistance tions nvelope ementation ncludes Project Director, Spe cialists, Engineers and Techn ical Staff NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SMTA-122605-CS-QCBS / Activity -1 Title: Procurement of Consult Urban Road Infrastructure- Y Quality And Cost- Open - Internationa IBRD / 89950 Prior 15,036,000.00 9,451,030.00 Signed 2020-02-14 2020-02-14 2020-03-13 2020-03-13 2020-04-09 2020-11-05 2020-05-25 2021-01-15 2020-06-15 2021-04-08 2020-07-20 2021-07-20 2020-08-07 2021-09-06 2025-08-06 ing Services for Detail design ellow Corridor Based Selection l , procurement support and c onstruction supervision Page 1 PK-SMTA-196995-CS-QCBS / Project Management Consult ant is to be procured to ensu re professional, efficient and Capacity Building and Techn Quality And Cost- Open - Internationa Pending Impleme IBRD / 89950 Prior 1,000,000.00 0.00 2020-10-20 2020-11-02 2020-12-31 2021-02-11 2021-03-08 2021-03-22 2021-04-26 2022-04-26 optimal facilitation and coord ical Assistance Based Selection l ntation ination of the Project activitie s and assist the Project Mana gement Team and ensure ca pacity building to SMTA. PK-SMTA-219016-CS-CQS / D esign and develop a dynamic website with strong functiona lities and attractive content d Capacity Building and Techn Consultant Qualifi Under Implement IBRD / 89950 Post Open - National 20,000.00 0.00 2021-02-21 2021-02-18 2021-03-14 2022-09-01 2021-04-27 2021-05-27 2021-07-01 2025-07-05 isplay that can be easily navi ical Assistance cation Selection ation gated by a variety of user gr oups and that function as a d ynamic, up-to-date data/infor mation portal for SMTA. PK-SMTA-196998-CS-QCBS / Transit Oriented Developmen t Strategy Alongside BRT Yell ow-line Corridor for conducti Development and Operation Quality And Cost- Open - Internationa Pending Impleme ng feasibility study on Transit IBRD / 89950 alization of a BRT System – Y Post 750,000.00 0.00 2022-12-20 2022-12-31 2023-02-28 2023-04-14 2023-05-04 2023-05-19 2023-06-24 2024-06-23 Based Selection l ntation Oriented Development & Rou ellow Corridor tes, Development of TOD Str ategy in the City, Developing PPP Transaction Advisory and Land Value Capture Plan. PK-SMTA-341298-CS-QCBS / Procurement of Transaction Development and Operation Quality And Cost- Open - Internationa Under Implement Advisory Services under PPP IBRD / 89950 alization of a BRT System – Y Post 500,000.00 0.00 2023-02-08 2023-02-14 2023-02-22 2023-03-04 2023-04-07 2023-06-02 2023-05-07 2023-06-06 2023-07-04 2023-08-08 2025-02-08 Based Selection l ation Mode for Supply and Operati ellow Corridor on of Buses for Yellow Line B RTS INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SMTA-197399-NC-RFB / I Capacity Building and Techn Individual Consult ndividual Consultant for Web IBRD / 89950 Post Open 7,000.00 0.00 Canceled 2020-12-01 2021-01-06 2021-01-08 2021-01-13 2021-07-12 ical Assistance ant Selection Development PK-SMTA-296961-CS-INDV / Capacity Building and Techn Individual Consult Procurement and Contract M IBRD / 89950 Post Limited 24,000.00 0.00 Under Review 2022-06-01 2022-05-27 2022-06-08 2022-06-10 2022-06-20 2023-06-20 ical Assistance ant Selection anagement Specialist PK-SMTA-302815-CS-INDV / Gender-Based Violence Traini ng Consultant The GBV consultant is part of Development and Operation Individual Consult Under Implement GAP to mitigate the risk of G IBRD / 89950 alization of a BRT System – Y Post ant Selection Limited 25,000.00 0.00 ation 2022-07-05 2022-07-17 2022-07-15 2022-07-18 2022-07-27 2023-07-27 BV during project implement ellow Corridor ation. The trainer will train th e community representatives who serve on the GBV commi ttee and relevant stakeholde rs. Page 2 LIBERIA SOCIAL SAFETY NETWORK PROJECT Abbreviated Procurement Plan Attachment I – Procurement Plan I. General 1. Project Information: Country: Liberia Project Name: Social Safety Network Project Project ID No.: P155293 Credit Number: IDA 57910 Executing Agencies: Ministry of Gender, Children and Social Protection 2. Bank’s approval Date of the procurement Plan: April 28, 2016 3. Date of General Procurement Notice: TBA 4. Period covered by this procurement plan: March 2016 to August 2017 II. Goods, Supply & Installation of Plant & Equipment, Works & non- Consulting Services. 5. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: World Bank’s Guidelines: Procurement of Goods, Works, and Non-Consulting Services under IBRD Loans and IDA Credits & Grants (January 2011 edition) and revised in July 2014, and is open to all eligible bidders as defined in the guidelines. Consulting services will be selected in accordance with the World Bank’s Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers (January 2011 edition) and revised July, 2014 and Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants, dated October 15, 2006, and revised in January 2011. Table 1: Thresholds for Procurement Methods and Prior Review – Goods and Works and Non Consultant Services Expenditure Procurement Contract Value Threshold Contracts Subject to Category Method For use of Method (US$) Prior Review (US$) 1. Works ICB(Works/Supply & >=5,000,000 All contracts Installation) NCB >=200,000 - <5,000,000 As in procurement plan Shopping <200,000 None Direct Contracting All values All contracts 2. Goods and ICB >=500,000 All contracts Non NCB >=100,000 <500,000 As in procurement plan Consultant Shopping <500,000 (motor vehicles None Services only) Shopping <100,000 000 (rest not None motor vehicles) Direct Contracting All values All contracts Procurement from All values None UNOPS Agency 6. Prequalification. Not expected for the works/goods packages. 7. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: N/A 8. Reference to (if any) Project Operational/Procurement Manual: Yes 9. Any Other Special Procurement Arrangements: None 10. Procurement Packages with Methods and Time Schedule a) Works There will be no procurement of works under this project. b) Procurement of Goods and Non Consulting Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimat Procure Prequa Nation Revie Expecte Expect Comme No. (Description) ed ment lificatio al w d bid ed nts Cost Method n Prefer by opening Contra US$ (yes/no ence Bank date ct million ) (yes/n (Prior Signat o) / ure Post) Date Goods 1. Tender for Supply & 140,000. NCB No No Prior 04/04/16 05/23/1 delivery of ICT 00 6 equipment 2. Supply & Delivery of 50,000.0 Shopping No No Post 03/21/16 04/11/1 Office Furniture 0 6 3. Purchase of Smart 45,000.0 Shopping No No Post 03/21/16 04/11/1 phones (75) 0 6 4. Purchase of 50,000.0 Shopping No No Post 03/21/16 04/11/1 Stationery (2016) 0 6 5. Supply & Delivery of 100,000. Shopping No No Post 03/21/16 04/11/1 Office Vehicle (2) 00 6 6. Purchase of 50,000.0 Shopping No No Post 03/22/17 04/12/1 Stationery (2017) 0 7 7. Purchase of Internet 2,000.00 Shopping No No Post 03/21/16 04/11/1 modems 6 8. Supply, delivery and 50,000.0 Shopping installation of 0 servers and routers Non Consulting Services 9. Provision of Internet 75,000.0 Shopping No No Post 03/21/16 04/11/1 Services 0 6 10. Total 562,000 .00 III. Selection of Consultants 11. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 2: Thresholds for Consultants Selection Methods and Prior Review Contract Value Threshold Expenditure Contracts Subject to Selection Method For use of Selection Category Prior Review (US$) Method (US$) Firms QCBS,QBS >=200,000 All contracts CQS,LCS,QBS,FBS <200,000 As in procurement plan SSS All values All Contracts Individual Competitive All Contracts >=100,000 Consultants Selection (IC) IC Single Source All Contracts All Values Selection 12. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$100,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 13. Consultancy services estimated to cost above US$200,000 equivalent per contract and individual consultants assignments estimated to cost US$100,000 and above and all individual consultants hired on single source basis will be subject to prior review by the Bank. 14. The threshold for the use of Selection of Consultant firms based on Consultants’ Qualifications (CQS) is determined on a case by case basis taking into account the nature and complexity of the assignment but shall not exceed US$300,000 other than in exceptional situations and in accordance with paragraph 3.7 the Guidelines: Selection and Employment of Consultants. 15. Irrespective of the thresholds and category of risk, the Terms of Reference (TOR) for selection of consultants (firms of individuals), whether prior or post review shall be cleared by the Bank. c) Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 7 Ref. Description of Estimated Method Revie Expected Expected No. Assignment Cost of w date of Contract Comments Selectio proposal Signature US$ n by submissi Date Bank on (Prior / Post) 1. Consultancy to 1,750,000. QCBS Prior 05/30/16 07/04/16 develop Social 00 Registry 2. Program Manager for 84,000.00 IC Post 04/04/16 05/30/16 Social Registry 3. MIS Officer (2 72,000.00 IC Post 04/04/16 05/30/16 Persons) 4. Procurement 336,000.00 IC Prior 04/04/16 05/30/16 Specialist (International) 5. Operation Officer 336,000.00 IC Prior 04/04/16 05/30/16 (International) Total 2,003,000 .00 d) Training and Workshop Estimated Expected Ref. Training, workshop and study Estimated Duration Training/workshop No. tours Cost (US$) (Days) Date 1 Procurement Management in 30,000.00 TBA TBA consultancy (2 Persons) GENERAL NOTES 1. Training and capacity building: Training workshops (including training material and support), conference attendance and study tours, will be carried out based on approved annual training and allied activities plan. A detailed training and workshops’ plan giving nature of training/workshop, number of trainees/participants, duration, staff months, timing and estimated cost will be submitted to the Bank for review and approval prior to initiating the process. The selection methods will derive from the activity requirement, schedule and circumstance. After the training, the beneficiaries will be requested to submit a brief report indicating what skill have been acquired and how these skills will contribute to enhance their performance and contribute to the attainment of the Project’s development objective. 2. Operating costs: Incremental recurrent expenditures during project implementation, including maintenance of vehicles, fuel, equipment, office supplies, utilities, consumables, banking charges, advertising expenses, internet service, car insurance, travel, per diems, and accommodations, but excluding salaries of civil and public servants, will be procured using the implementing agency's administrative procedures reviewed and found acceptable by the Bank. PROCUREMENT Liberia : Liberia Social Safety Nets Project PLAN General Information Country: Liberia 2017-12-07 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155293 GPN Date: Project Name: Liberia Social Safety Nets Project Loan / Credit No: IDA / 57910, TF / A6428, TF / B4346 Ministry of Gender, Children & Social Protection Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned LR-MOGCSP-39426-CW-RFB / Renovation Works for Social Strengthening of the Nation Single Stage - One E 2019-01-0 IDA / 57910 Post Request for Bids Open - National 210,000.00 0.00 Canceled 2018-02-28 2018-05-07 2018-03-28 2018-05-30 2018-05-09 2018-06-08 2018-07-13 Registry Unit Supply and Inst al Social Safety Net System nvelope 9 allation Of Infrastructures For A Data Center GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOGCSP-39422-GO-RFQ / Strengthening of the Nation Request for Quota Single Stage - One E IDA / 57910 Post Open - National 90,000.00 0.00 Canceled 2018-03-19 2018-05-14 2018-07-18 2 x Utility Vehicles off Road al Social Safety Net System tions nvelope LR-MOGCSP-39425-GO-RFQ / ICT Colocation Services, Inter Strengthening of the Nation Request for Quota Single Stage - One E IDA / 57910 Post Open - National 90,000.00 0.00 Canceled 2018-03-14 2018-05-21 2018-07-31 net Connectivity, And Installa al Social Safety Net System tions nvelope tion of A Secure Private Leas ed Line LR-MOGCSP-39424-GO-RFB / Strengthening of the Nation Single Stage - One E Supply and Installation of IT IDA / 57910 Post Request for Bids Open - National 200,000.00 281,370.16 Terminated 2018-02-28 2018-04-13 2018-03-28 2018-04-14 2018-03-28 2018-05-18 2018-04-20 2018-07-31 2018-05-25 2018-10-10 2018-07-31 al Social Safety Net System nvelope Equipment and Software LR-MOGCSP-39421-GO-RFQ / Supply, delivery and installati Strengthening of the Nation Request for Quota Single Stage - One E TF / A6428 Post Limited 40,000.00 39,650.00 Signed 2018-12-01 2018-11-19 2019-01-26 2019-02-15 2019-07-25 on of two 30 KVA generators al Social Safety Net System tions nvelope for the Social Registry LR-MOGCSP-144406-GO-RFQ Project Management and Ca Request for Quota Single Stage - One E / Procurement Office Equipm IDA / 57910 Post Limited 30,200.00 26,350.00 Completed 2019-11-20 2019-11-26 2020-01-15 2020-02-20 2020-07-13 2020-03-11 pacity Building tions nvelope ent for LSSN LR-MOGCSP-179908-GO-DIR Project Management and Ca / Procure Cell phones for SCT IDA / 57910 Post Direct Selection Direct 36,400.00 34,600.00 Completed 2020-06-30 2020-06-30 2020-07-05 2020-06-30 2020-08-09 2020-10-17 2021-08-04 2020-12-22 pacity Building Beneficiaries LR-MOGCSP-280953-GO-RFQ Strengthening of the Nation Request for Quota Single Stage - One E IDA / 57910 Post Limited 6,000.00 0.00 Signed 2022-03-30 2022-04-05 2022-05-25 2022-11-21 / Procurement of NAS al Social Safety Net System tions nvelope LR-MOGCSP-362367-GO-RFQ Project Management and Ca Request for Quota Single Stage - One E / Procurement of Motor Vehic IDA / 57910 Post Limited 98,000.00 0.00 Signed 2023-05-27 2023-05-17 2023-07-22 2024-01-18 pacity Building tions nvelope les and Accessories LR-MOGCSP-362365-GO-RFQ Project Management and Ca Request for Quota Single Stage - One E IDA / 57910 Post Limited 15,000.00 0.00 Signed 2023-05-27 2023-05-16 2023-07-22 2024-01-18 / Furnishing of Conference Ro pacity Building tions nvelope om LR-MOGCSP-362364-GO-RFQ Project Management and Ca Request for Quota Single Stage - One E Under Imple IDA / 57910 Post Limited 12,000.00 0.00 2023-05-27 2023-05-16 2023-07-31 2024-01-27 / Procurement of Office Equip pacity Building tions nvelope mentation ment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOGCSP-3942-NC-RFQ / I CT Colocation Services, Inter Strengthening of the Nation Request for Quota Single Stage - One E TF / A6428 Post Limited 33,000.00 0.00 Canceled 2018-12-15 2018-12-07 2019-02-09 2019-08-08 net Connectivity and Installat al Social Safety Net System tions nvelope ion of a secured Private Leas ed Line LR-MOGCSP-155066-NC-DIR Project Management and Ca / Recruit Firm for Cash Delive IDA / 57910 Post Direct Selection Direct 30,000.00 30,000.00 Completed 2020-02-20 2020-01-26 2020-02-25 2020-01-31 2020-03-31 2020-02-15 2020-09-27 2021-05-06 pacity Building ry to SCT Beneficiaries LR-MOGCSP-188908-NC-DIR Cash Transfers to Extremely / Service Provider to Deliver IDA / 57910 Poor and Food Insecure Hou Prior Direct Selection Direct 600,000.00 635,000.00 Completed 2020-08-31 2020-08-28 2020-09-05 2020-08-30 2020-10-10 2020-10-17 2021-04-08 Social Cash Transfer Program seholds in Urban Areas (SCT-COVID) LR-MOGCSP-247675-NC-RFQ Strengthening of the Nation Request for Quota Single Stage - One E IDA / 57910 Post Limited 41,000.00 35,443.00 Signed 2021-09-05 2021-09-16 2021-10-31 2022-02-23 2022-10-31 / Procure Virtual Private Serv al Social Safety Net System tions nvelope er (VPS) LR-MOGCSP-254900-NC-DIR Cash Transfers to Extremely / Service Provider to Deliver IDA / 57910 Poor and Food Insecure Hou Prior Direct Selection Direct 470,000.00 649,122.00 Completed 2021-10-15 2021-09-30 2021-10-20 2021-10-14 2021-11-24 2022-02-08 2023-11-24 Social Cash Transfer Program seholds in Bomi and Maryland Counti es CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOGCSP-39451-CS-QCBS / Data Collection Firm for the Strengthening of the Nation Quality And Cost- Open - Internationa IDA / 57910 Prior 950,000.00 2,883,203.11 Completed 2018-02-28 2018-02-28 2018-03-21 2018-04-05 2018-05-09 2018-12-12 2018-06-06 2019-01-31 2018-07-06 2019-04-10 2018-08-10 2019-06-19 2018-09-14 2019-06-27 2019-09-14 development of software and al Social Safety Net System Based Selection l data collection Page 1 LR-MOGCSP-39454-CS-QCBS / Design, Develop and Imple Strengthening of the Nation Quality And Cost- Open - Internationa IDA / 57910 Prior 575,000.00 475,186.00 Completed 2018-02-28 2018-06-04 2018-03-21 2018-06-09 2018-05-31 2019-03-28 2018-06-28 2019-06-13 2018-07-28 2019-12-04 2018-09-01 2020-03-23 2018-10-06 2020-04-27 2019-10-06 2023-06-28 ment an Integrated Informati al Social Safety Net System Based Selection l on System For the MGCSP MGCSP-CS-CQS-DTC-1 / Recr Cash Transfers to Extremely Consultant Qualifi uit Firm for Data Collection fo IDA / 57910 Poor and Food Insecure Hou Post Open - National 30,000.00 71,016.00 Signed 2018-10-10 2018-11-07 2018-10-31 2018-12-10 2018-12-14 2019-02-21 2019-01-13 2019-03-11 2019-02-17 2019-04-04 2019-08-16 cation Selection r SCT Roll Out seholds MGCSP-CS-CQS-TRG-1 / Recr Cash Transfers to Extremely Consultant Qualifi IDA / 57910 Post Open - National 20,000.00 91,256.60 Completed 2018-10-10 2018-11-07 2018-10-31 2019-10-15 2018-12-14 2019-12-16 2019-01-13 2020-10-12 2019-02-17 2020-12-25 2019-08-16 2022-03-31 uit CSO/ NGO to train SCT Be Poor and Food Insecure Hou cation Selection neficiaries seholds LR-MOGCSP-39452-CS-QCBS Strengthening of the Nation Consultant Qualifi / Consultancy for Communica IDA / 57910 Post Open - National 70,000.00 0.00 Canceled 2018-04-02 2018-09-03 2018-04-23 2018-09-03 2018-06-06 2018-10-24 2018-07-06 2018-08-10 2019-02-06 al Social Safety Net System cation Selection tion Campaign LR-MOGCSP-290621-CS-CQS Strengthening of the Nation Consultant Qualifi / SR Phase II Data Collection i TF / B4346 Post Open - National 486,000.00 0.00 Canceled 2022-05-27 2022-04-25 2022-06-17 2022-05-02 2022-07-31 2022-08-30 2022-10-04 2023-04-02 al Social Safety Net System cation Selection n Grand Kru and River Gee C ounties LR-MOGCSP-348402-CS-CQS Strengthening of the Nation Consultant Qualifi / SR Phase II Data Collection i TF / A6428 Post Open - National 486,000.00 0.00 Signed 2022-04-25 2022-04-25 2022-05-16 2022-06-29 2022-07-15 2022-07-29 2022-10-12 2022-09-02 2023-03-01 al Social Safety Net System cation Selection n Grand Kru County INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MOGCSP-39455-CS-CDS / Cash Transfers to Extremely IDA / 57910 Post Direct Selection Direct 60,000.00 60,000.00 Completed 2018-01-31 2018-06-26 2018-02-17 2017-12-05 2018-04-23 2017-12-08 2019-04-23 2018-11-30 National Social Protection Co Poor and Food Insecure Hou ordinator seholds LR-MOGCSP-39458-CS-CDS / Cash Transfers to Extremely IDA / 57910 Post Direct Selection Direct 42,000.00 42,000.00 Completed 2018-01-31 2018-06-26 2018-02-17 2017-12-05 2018-04-23 2017-12-08 2019-04-23 2018-11-30 Program Manager Poor and Food Insecure Hou seholds LR-MOGCSP-39459-CS-CDS / Cash Transfers to Extremely IDA / 57910 Post Direct Selection Direct 18,000.00 18,000.00 Completed 2017-12-08 2018-09-05 2017-12-19 2017-12-07 2018-02-22 2017-12-08 2019-02-22 2018-11-30 Operation Officer Poor and Food Insecure Hou seholds LR-MOGCSP-39460-CS-CDS / Cash Transfers to Extremely IDA / 57910 Post Direct Selection Direct 13,800.00 14,400.00 Completed 2017-12-08 2018-09-05 2017-12-18 2017-12-05 2017-12-31 2017-12-08 2018-12-31 2018-11-30 Finance Officer Poor and Food Insecure Hou seholds LR-MOGCSP-39461-CS-CDS / Cash Transfers to Extremely IDA / 57910 Post Direct Selection Direct 14,400.00 13,800.00 Completed 2017-12-29 2018-09-05 2018-01-15 2017-12-05 2018-03-21 2017-12-08 2018-09-17 2018-11-30 M & E Officer Poor and Food Insecure Hou seholds LR-MOGCSP-39462-CS-CDS / Cash Transfers to Extremely IDA / 57910 Post Direct Selection Direct 20,400.00 20,400.00 Completed 2017-12-29 2018-09-05 2018-01-04 2017-12-05 2018-01-19 2017-12-08 2019-01-19 2018-11-30 Regional Coordinator region Poor and Food Insecure Hou one seholds LR-MOGCSP-39428-CS-INDV Strengthening of the Nation Individual Consult IDA / 57910 Post Open 12,000.00 0.00 Canceled 2017-12-08 2018-01-01 2018-01-14 2018-02-01 2018-05-31 / Social Registry Manager al Social Safety Net System ant Selection LR-MOGCSP-39429-CS-INDV Strengthening of the Nation Individual Consult / Operation & Logistics Office IDA / 57910 Post Open 10,000.00 0.00 Canceled 2017-12-08 2018-01-01 2018-01-14 2018-02-01 2018-05-31 al Social Safety Net System ant Selection r Social Registry LR-MOGCSP-39431-CS-INDV Strengthening of the Nation Individual Consult / Monitoring & Evaluation Offi IDA / 57910 Post Open 7,200.00 0.00 Canceled 2017-12-08 2018-01-01 2018-01-01 2018-02-01 2018-05-31 al Social Safety Net System ant Selection cer Social Registry LR-MOGCSP-39432-CS-INDV Strengthening of the Nation Individual Consult IDA / 57910 Post Open 6,000.00 0.00 Canceled 2017-12-08 2018-01-01 2018-01-14 2018-02-01 2018-05-31 / MIS Officer Social Registry al Social Safety Net System ant Selection LR-MOGCSP-39433-CS-INDV Strengthening of the Nation Individual Consult IDA / 57910 Post Open 10,000.00 0.00 Canceled 2017-12-08 2018-01-01 2018-01-14 2018-02-01 2018-05-31 / System Analyst Social Regi al Social Safety Net System ant Selection stry LR-MOGCSP-39449-CS-INDV / International Procurement S Strengthening of the Nation Individual Consult IDA / 57910 Prior Open 90,000.00 0.00 Canceled 2018-02-28 2018-02-12 2018-05-14 2018-06-04 2018-07-09 2019-07-09 pecialist for one year renewa al Social Safety Net System ant Selection ble based on performance MGCSP/WB/ LSSN/GD/013/17 Strengthening of the Nation Individual Consult / Procurement Specialist (Inte IDA / 57910 Prior Limited 90,000.00 90,000.00 Completed 2018-04-02 2018-03-29 2018-04-07 2018-05-03 2018-04-28 2018-07-24 2018-06-02 2018-07-31 2018-11-29 2023-06-28 al Social Safety Net System ant Selection rnaltional) MGCSP-REF-06 / Social Regis Strengthening of the Nation Individual Consult IDA / 57910 Post Direct 9,000.00 7,500.00 Completed 2018-04-01 2018-03-20 2018-04-11 2018-03-23 2018-05-02 2018-03-23 2018-06-06 2018-04-02 2018-12-03 2018-06-18 try Manager al Social Safety Net System ant Selection MGCSP-REF-07 / Operation & Strengthening of the Nation Individual Consult IDA / 57910 Post Direct 7,500.00 5,000.00 Completed 2018-04-01 2018-04-04 2018-04-11 2018-03-23 2018-05-02 2018-03-29 2018-06-06 2018-04-02 2018-12-03 2018-06-18 Logistics Officer Social Regist al Social Safety Net System ant Selection ry MGCSP-REF-08 / Monitoring Strengthening of the Nation Individual Consult IDA / 57910 Post Direct 5,400.00 3,600.00 Completed 2018-04-01 2018-03-20 2018-04-11 2018-03-23 2018-05-02 2018-03-23 2018-06-06 2018-04-02 2018-12-03 2018-06-18 & Evaluation Officer Social R al Social Safety Net System ant Selection egistry MGCSP-REF-09 / MIS Officer Strengthening of the Nation Individual Consult IDA / 57910 Post Direct 4,500.00 3,000.00 Completed 2018-04-01 2018-05-04 2018-04-11 2018-03-23 2018-05-02 2018-03-23 2018-06-06 2018-04-02 2018-12-03 2018-06-18 Social Registry al Social Safety Net System ant Selection MGCSP-REF-10 / System Ana Strengthening of the Nation Individual Consult IDA / 57910 Post Direct 7,500.00 5,000.00 Completed 2018-04-01 2018-03-20 2018-04-11 2018-03-23 2018-05-02 2018-03-26 2018-06-06 2018-04-02 2018-12-03 2018-06-18 lyst Social Registry al Social Safety Net System ant Selection MGCSP-REF-17 / Communica Strengthening of the Nation Individual Consult IDA / 57910 Post Open 25,200.00 34,000.00 Signed 2018-06-01 2018-09-03 2018-07-20 2018-10-24 2018-08-10 2019-01-11 2018-09-14 2019-01-16 2019-03-13 2020-08-31 tions Officer al Social Safety Net System ant Selection MGCSP-CS-INDV-TS-1 / Recr Strengthening of the Nation Individual Consult uit Short Term Technical Sup IDA / 57910 Post Direct 9,000.00 7,200.00 Completed 2018-11-17 2019-03-04 2018-11-27 2019-03-05 2018-12-18 2019-03-08 2019-01-22 2019-03-11 2019-07-21 2019-11-29 al Social Safety Net System ant Selection port for SR Data Centre MGCSP-CS-CQS-CAD-1 / Recr Project Management and Ca uit Firm for Cash Delivery for IDA / 57910 Post Direct Selection Direct 29,000.00 40,000.00 Completed 2018-11-12 2018-11-15 2018-11-22 2019-08-13 2019-01-26 2019-09-25 2019-07-25 2020-02-19 pacity Building SCTBeneficiaries LR-MOGCSP-39436-CS-INDV Strengthening of the Nation Individual Consult IDA / 57910 Post Open 21,600.00 0.00 Canceled 2018-02-28 2018-08-20 2018-09-10 2018-10-15 2019-10-15 / Network Administrator al Social Safety Net System ant Selection MGCSP-REF-01 / Social Regis Project Management and Ca Individual Consult IDA / 57910 Post Open 36,000.00 36,000.00 Completed 2018-04-10 2018-05-04 2018-05-29 2018-10-08 2018-06-19 2018-10-18 2018-07-24 2018-11-01 2019-01-20 2020-02-28 try Manager pacity Building ant Selection Page 2 MGCSP-REF-05 / System Ana Project Management and Ca Individual Consult IDA / 57910 Post Open 24,000.00 30,000.00 Completed 2018-04-10 2018-05-04 2018-05-29 2018-10-08 2018-06-19 2018-10-18 2018-07-24 2018-11-01 2019-01-20 2019-09-30 lyst pacity Building ant Selection MGCSP-REF-20 / Procuremen Project Management and Ca Individual Consult IDA / 57910 Prior Open 24,000.00 36,000.00 Signed 2018-11-21 2019-01-11 2019-01-09 2019-06-12 2019-01-30 2019-06-28 2019-03-06 2019-07-06 2019-09-02 t Officer pacity Building ant Selection MGCSP-REF-03 / Operations Project Management and Ca Individual Consult IDA / 57910 Post Open 24,000.00 24,000.00 Completed 2018-04-10 2018-05-04 2018-05-29 2018-10-08 2018-06-19 2018-10-18 2018-07-24 2018-11-01 2019-01-20 2021-07-30 and Logistics Officer 1 pacity Building ant Selection MGCSP-REF-04 / MIS Officer Project Management and Ca Individual Consult IDA / 57910 Post Open 24,000.00 24,000.00 Completed 2018-04-10 2018-05-04 2018-05-29 2018-10-08 2018-06-19 2018-10-18 2018-07-24 2018-11-01 2019-01-20 2019-09-30 for SRU pacity Building ant Selection MGCSP-CS-INDV-SCT-1 / Rec Project Management and Ca Individual Consult ruit National Social Protectio IDA / 57910 Post Open 48,000.00 48,000.00 Signed 2018-11-12 2018-11-19 2018-12-31 2019-02-22 2019-01-21 2019-02-28 2019-02-25 2019-03-06 2019-08-24 pacity Building ant Selection n Coordinator MGCSP-CS-INDV-SCT-2 / Rec Project Management and Ca Individual Consult IDA / 57910 Post Open 36,000.00 36,000.00 Signed 2018-11-12 2018-11-19 2018-12-31 2019-02-22 2019-01-21 2019-02-28 2019-02-25 2019-03-01 2019-08-24 ruit Program Manager SCT pacity Building ant Selection MGCSP-CS-INDV-SCT-3 / Rec Project Management and Ca Individual Consult IDA / 57910 Post Open 24,000.00 18,000.00 Signed 2018-11-12 2018-11-19 2019-02-03 2019-02-22 2019-02-24 2019-02-28 2019-03-31 2019-03-01 2019-09-27 ruit Operations Officer for SC pacity Building ant Selection T MGCSP-CS-INDV-SCT-4 / Rec Project Management and Ca Individual Consult IDA / 57910 Post Open 24,000.00 35,800.00 Terminated 2018-11-12 2018-11-19 2018-12-31 2019-02-22 2019-01-21 2019-02-28 2019-02-25 2019-03-01 2019-08-24 ruit Finance Officer for LSSNP pacity Building ant Selection MGCSP-CS-INDV-SCT-5 / Rec Project Management and Ca Individual Consult IDA / 57910 Post Open 18,000.00 27,000.00 Signed 2018-11-12 2018-11-19 2018-12-31 2019-02-22 2019-01-21 2019-02-28 2019-02-25 2019-03-01 2019-08-24 ruit Regional Coordinator for pacity Building ant Selection SCT MGCSP-CS-INDV-SCT-6 / Rec Project Management and Ca Individual Consult IDA / 57910 Post Open 14,400.00 14,400.00 Signed 2018-11-12 2018-11-19 2018-12-31 2019-02-22 2019-01-21 2019-02-28 2019-02-25 2019-03-01 2019-08-24 ruit GRM Officer pacity Building ant Selection MGCSP-CS-CDS-MEA-1 / Recr Project Management and Ca uit Monitoring & Evaluation A IDA / 57910 Post Direct Selection Direct 6,000.00 12,500.00 Signed 2018-11-12 2017-11-01 2018-11-22 2019-03-29 2019-01-26 2019-04-04 2019-07-25 pacity Building ssistant1 MGCSP-CS-CDS-MEA-2 / Recr Project Management and Ca uit Monitoring & Evaluation IDA / 57910 Post Direct Selection Direct 6,000.00 6,500.00 Under Review 2018-11-12 2018-11-01 2018-11-22 2019-03-29 2019-01-26 2019-04-04 2019-07-25 pacity Building Assistant2 MGCSP-CS-CDS-SW-1 / Recr Project Management and Ca IDA / 57910 Post Direct Selection Direct 4,800.00 9,600.00 Signed 2018-11-12 2018-11-01 2018-11-22 2019-03-29 2019-01-26 2019-04-04 2019-07-25 uit Social Worker 1 pacity Building MGCSP-CS-CDS-SW-2 / Recr Project Management and Ca IDA / 57910 Post Direct Selection Direct 4,800.00 9,600.00 Signed 2018-11-12 2018-11-01 2018-11-22 2019-03-29 2019-01-26 2019-04-04 2019-07-25 uit Social Worker 2 pacity Building MGCSP-CS-CDS-SW-3 / Recr Project Management and Ca IDA / 57910 Post Direct Selection Direct 4,800.00 10,000.00 Signed 2018-11-12 2018-11-01 2018-11-22 2019-03-29 2019-01-26 2019-04-04 2019-07-25 uit Social Worker 3 pacity Building MGCSP-REF-02 / Monitoring Project Management and Ca Individual Consult IDA / 57910 Post Open 24,000.00 24,000.00 Signed 2018-04-10 2018-05-04 2018-05-29 2018-10-08 2018-06-19 2018-10-18 2018-07-24 2018-11-01 2019-01-20 and Evaluation Officer pacity Building ant Selection MGCSP-CS-CDS-SW-4 / Recr Project Management and Ca IDA / 57910 Post Direct Selection Direct 4,800.00 10,000.00 Signed 2018-11-12 2018-11-01 2018-11-22 2019-03-29 2019-01-26 2019-04-04 2019-07-25 uit Social Worker 4 pacity Building LR-MOGCSP-139146-CS-IND Project Management and Ca Individual Consult IDA / 57910 Prior Limited 24,000.00 0.00 Canceled 2019-10-11 2019-10-15 2019-10-16 2019-10-08 2019-11-06 2019-12-11 2020-12-11 V / Recruit Finance Officer for pacity Building ant Selection LSSNP LR-MOGCSP-144404-CS-IND Project Management and Ca Individual Consult V / Recruit Data Base Admini IDA / 57910 Post Open 24,000.00 24,000.00 Signed 2019-11-21 2019-10-27 2020-01-09 2020-06-19 2020-01-30 2020-07-17 2020-03-05 2020-07-29 2020-09-01 pacity Building ant Selection strator, DBA LR-MOGCSP-148848-CS-IND Project Management and Ca Individual Consult V / Recruit Financial Manage IDA / 57910 Prior Open 24,000.00 0.00 Canceled 2020-01-31 2019-12-16 2020-03-20 2020-07-06 2020-04-10 2020-05-15 2020-11-11 pacity Building ant Selection ment Officer LR-MOGCSP-166124-CS-CDS Project Management and Ca IDA / 57910 Post Direct Selection Direct 36,000.00 72,000.00 Signed 2020-03-27 2020-04-05 2020-04-06 2020-04-07 2020-06-10 2020-04-14 2021-06-10 / Recruit SCT Manager pacity Building LR-MOGCSP-166128-CS-CDS Project Management and Ca IDA / 57910 Post Direct Selection Direct 36,000.00 72,000.00 Signed 2020-03-27 2020-04-05 2020-04-06 2020-04-07 2020-06-10 2020-04-14 2021-06-05 / Recruit SR Manager pacity Building LR-MOGCSP-166130-CS-IND Project Management and Ca Individual Consult IDA / 57910 Post Open 24,000.00 48,000.00 Signed 2020-06-30 2020-04-06 2020-08-18 2020-08-21 2020-09-08 2020-08-25 2020-10-13 2020-08-26 2021-10-08 V / Recruit M&E Officer pacity Building ant Selection LR-MOGCSP-179911-CS-CDS / Data Collection Software So Strengthening of the Nation TF / A6428 Post Direct Selection Direct 34,000.00 33,222.88 Completed 2020-06-30 2020-06-12 2020-07-10 2020-06-17 2020-09-13 2020-08-08 2021-09-08 lution for the Response to CO al Social Safety Net System VID-19 Pandemic LR-MOGCSP-184680-CS-CDS Project Management and Ca IDA / 57910 Post Direct Selection Direct 7,200.00 7,200.00 Completed 2020-07-30 2020-07-16 2020-08-09 2020-07-16 2020-10-13 2020-07-18 2021-04-11 2021-01-16 / Recruit Financial Managem pacity Building ent Officer LR-MOGCSP-202339-CS-IND Project Management and Ca Individual Consult V / Recruit Financial Manage IDA / 57910 Prior Open 24,000.00 24,000.00 Signed 2020-11-30 2020-10-30 2021-01-18 2021-01-27 2021-02-08 2021-06-06 2021-03-15 2021-06-26 2021-09-11 pacity Building ant Selection ment Officer LR-MOGCSP-225583-CS-IND Project Management and Ca Individual Consult V / Recruit Project Regional C IDA / 57910 Post Open 14,400.00 0.00 Canceled 2021-04-30 2021-02-16 2021-06-18 2021-07-09 2021-08-13 2022-02-09 pacity Building ant Selection oordinator (South East) LR-MOGCSP-230355-CS-IND Project Management and Ca Individual Consult V / Recruit Social Cash Transf IDA / 57910 Post Open 18,000.00 0.00 Canceled 2021-05-27 2021-05-11 2021-07-15 2021-08-05 2021-09-09 2022-09-09 pacity Building ant Selection er (SCT) Operations Officer LR-MOGCSP-280960-CS-CDS / Consultancy to update Liber Project Management and Ca Individual Consult IDA / 57910 Post Direct 30,000.00 15,000.00 Signed 2022-03-30 2022-03-07 2022-04-09 2022-03-29 2022-04-30 2022-04-01 2022-06-04 2022-04-22 2022-12-01 ia National Social Protection pacity Building ant Selection Policy and Strategy LR-MOGCSP-286810-CS-IND Project Management and Ca Individual Consult V / Recruitment of Financial IDA / 57910 Post Limited 24,000.00 0.00 Signed 2022-04-29 2021-10-05 2022-05-04 2022-04-15 2022-05-25 2022-07-21 2022-06-29 2023-06-29 pacity Building ant Selection Management Officer Page 3 LR-MOGCSP-362223-CS-CDS / Data Collection (Pilot in Urb Strengthening of the Nation IDA / 57910 Post Direct Selection Direct - National 41,925.00 0.00 Signed 2023-05-22 2023-06-02 2023-06-01 2023-06-05 2023-08-05 2023-09-19 an Communities) 9 Communi al Social Safety Net System ties in Montserrado and Marg ibi Counties LR-MOGCSP-362238-CS-IND V / Recruit Individual Consult Project Management and Ca Individual Consult Under Implement IDA / 57910 Post Direct - National 5,000.00 0.00 2023-05-26 2023-05-31 2023-06-05 2023-06-05 2023-06-26 2023-06-07 2023-07-31 2024-01-27 ant to write Implementation pacity Building ant Selection ation and Completion Report for th e LSSNP Page 4 PROCUREMENT PLAN (Textual Part) Project information: Gambia, Essential Health Services, P173287 Project Implementation agency: Ministry of Health Date of the Procurement Plan: 27 August 2020 Period covered by this Procurement Plan: 27 August to 31 December 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. – Not Applicable Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. – Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Not Applicable. Other Relevant Procurement Information. – Not Applicable PROCUREMENT Gambia, The : The Gambia Essential Health Services Strengthening Project PLAN General Information Country: Gambia, The 2020-08-27 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173287 GPN Date: 2020-11-25 Project Name: The Gambia Essential Health Services Strengthening Project Loan / Credit No: IDA / D7310, / , IDA / D9280 MINISTRY OF HEALTH Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Component 1. Improving the GM-MOH-190603-CW-RFB / Delivery and Utilization of Q Single Stage - One E Pending Imp 2021-07-2 Renovations of Bwiam Gener IDA / D7310 Post Request for Bids Open - National 500,000.00 0.00 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 uality Essential Primary Hea nvelope lementation 0 al Hospital lth Care Services GM-MOH-190606-CW-RFB / Renovations of Edward Franc Component 1. Improving the is Teaching Hospital (laborat Delivery and Utilization of Q Single Stage - One E 2021-07-2 IDA / D7310 Post Request for Bids Open - National 1,500,000.00 0.00 Canceled 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 ory, operating room, NAWEC uality Essential Primary Hea nvelope 0 ward, orthopedic ward, 6&7 lth Care Services ward, Gamtel ward, postnata l, antenatal and labor wards) GM-MOH-190611-CW-RFB / Renovations and extensions t Component 1. Improving the o Brikama Ba Health Center i Delivery and Utilization of Q Single Stage - One E Pending Imp 2021-07-2 IDA / D7310 Post Request for Bids Open - National 200,000.00 0.00 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 ncluding a new operating roo uality Essential Primary Hea nvelope lementation 0 m for cesarean delivery whic lth Care Services h will be located close to the maternity ward Component 1. Improving the GM-MOH-190612-CW-RFB / Delivery and Utilization of Q Single Stage - One E Pending Imp 2021-07-2 Renovations of staff quarters IDA / D7310 Post Request for Bids Open - National 500,000.00 0.00 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 uality Essential Primary Hea nvelope lementation 0 in selected health facilities lth Care Services Component 1. Improving the GM-MOH-244828-CW-RFQ / Request for Quota Delivery and Utilization of Q Request for Quota Single Stage - One E 2022-03-2 Renovation of Birth and Deat IDA / D7310 Post Open - National tions (Non Bank-S 43,549.00 60,356.07 Signed 2021-08-05 2021-09-30 2021-11-30 uality Essential Primary Hea tions nvelope 9 h Registry Unit Office space PD) lth Care Services GM-MOH-234824-CW-RFB / Construction of the National Emergency Treatment Centr Component 1. Improving the Request for Bids - e Intensive Care Unit, Nation Delivery and Utilization of Q Open - Internationa Single Stage - One E Works (without pr 18,800,000.0 Under Imple 2022-07-3 IDA / D7310 Prior Request for Bids 0.00 2021-10-11 2021-10-16 2021-11-27 2021-07-13 2021-12-27 2022-01-31 al Emergency Observation an uality Essential Primary Hea l nvelope equalification) SP 0 mentation 0 d Treatment Centre, National lth Care Services D Public Health Laboratory and Training Centre, National Blo od Transfusion Centre, and C onference Centre Component 1. Improving the Request for Bids - GM-MOH-204427-CW-RFB / Delivery and Utilization of Q Single Stage - One E Works (without pr Pending Imp 2022-07-3 Construction of Clinical Wast IDA / D7310 Post Request for Bids Open - National 483,795.00 0.00 2021-10-11 2021-10-16 2021-11-27 2021-12-27 2022-01-31 uality Essential Primary Hea nvelope equalification) SP lementation 0 e Treatment Center lth Care Services D GM-MOH-190600-CW-RFB / Component 1. Improving the Construction of National Bloo Delivery and Utilization of Q Single Stage - One E 2021-07-2 IDA / D7310 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 d Transfusion Center at Kanif uality Essential Primary Hea nvelope 0 ing Hospital lth Care Services Component 1. Improving the Request for Bids - GM-MOH-262766-CW-RFB / Delivery and Utilization of Q Open - Internationa Single Stage - One E Small Works SPD Under Imple 2022-10-2 Construction of a new neonat IDA / D7310 Post Request for Bids 1,000,000.00 0.00 2022-01-03 2023-03-22 2022-01-08 2023-03-22 2022-02-19 2022-03-21 2022-04-25 uality Essential Primary Hea l nvelope (1 envelope proce mentation 2 al unit at EFSTH Hospital lth Care Services ss) Component 1. Improving the GM-MOH-190608-CW-RFB / Delivery and Utilization of Q Single Stage - One E 2021-07-2 Renovations of Basse Hospita IDA / D7310 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 uality Essential Primary Hea nvelope 0 l lth Care Services Component 1. Improving the GM-MOH-190609-CW-RFB / Delivery and Utilization of Q Single Stage - One E 2021-07-2 Renovations to Brikama Hosp IDA / D7310 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 uality Essential Primary Hea nvelope 0 ital lth Care Services National Procure Component 1. Improving the GM-MOH-GM-304342-CW-RF ment Document - Delivery and Utilization of Q Single Stage - One E Pending Imp 2023-05-0 B / Construction of Basse Hos IDA / D7310 Post Request for Bids Open - National 1 Envelope proce 300,000.00 0.00 2022-07-18 2022-07-23 2022-09-03 2022-10-03 2022-11-07 uality Essential Primary Hea nvelope lementation 6 pital ss (Non Bank-SPD lth Care Services ) National Procure Component 1. Improving the GM-MOH-GM-304343-CW-RF ment Document - Delivery and Utilization of Q Single Stage - One E Pending Imp 2023-05-0 B / Construction of Brikama H IDA / D7310 Post Request for Bids Open - National 1 Envelope proce 300,000.00 0.00 2022-07-18 2022-07-23 2022-09-03 2022-10-03 2022-11-07 uality Essential Primary Hea nvelope lementation 6 ospital ss (Non Bank-SPD lth Care Services ) Component 1. Improving the GM-MOH-GM-325676-CW-RF Request for Quota Delivery and Utilization of Q Request for Quota Single Stage - One E Under Imple 2023-07-0 Q / Refurbishment of X-Ray R IDA / D7310 Post Open - National tions (Non Bank-S 50,000.00 0.00 2022-11-14 2023-01-09 uality Essential Primary Hea tions nvelope mentation 8 ooms for 5 Health Centers PD) lth Care Services Component 1. Improving the Request for Bids - GM-SWEDD-GM-341481-CW- Delivery and Utilization of Q Single Stage - One E Works (without pr Under Imple 2023-11-2 RFB / Renovation Works in As IDA / D7310 Post Request for Bids Open - National 3,700,000.00 0.00 2023-02-08 2023-02-10 2023-02-13 2023-02-10 2023-03-27 2023-04-26 2023-05-31 uality Essential Primary Hea nvelope equalification) SP mentation 7 bestos Affected Facilities lth Care Services D GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Improving the GM-MOH-190613-GO-RFB / E Delivery and Utilization of Q Open - Internationa Single Stage - One E Pending Impl quipment for renovated healt IDA / D7310 Prior Request for Bids 5,000,000.00 0.00 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 2021-07-20 uality Essential Primary Hea l nvelope ementation h facilities lth Care Services Page 1 Component 1. Improving the GM-MOH-190618-GO-RFQ / Delivery and Utilization of Q Request for Quota Single Stage - One E User devices for CRVS (tablet / Post Limited 100,000.00 0.00 Canceled 2020-10-06 2020-12-01 2021-05-30 uality Essential Primary Hea tions nvelope s, printers, etc) lth Care Services Component 1. Improving the GM-MOH-219171-GO-RFB / U Delivery and Utilization of Q Open - Internationa Single Stage - One E IDA / D7310 Post Request for Bids 310,000.00 577,123.64 Completed 2021-02-11 2021-02-12 2021-02-16 2021-02-12 2021-03-30 2021-03-02 2021-04-29 2021-03-15 2021-06-03 2021-04-07 2021-11-30 2021-06-27 ser Devices for eCRVS uality Essential Primary Hea l nvelope lth Care Services Component 1. Improving the GM-MOH-223098-GO-UN / Pr Delivery and Utilization of Q UN Agencies (Dire ocurement of Cinema Van an IDA / D7310 Post Direct 299,317.56 316,550.00 Signed 2021-03-05 2021-02-10 2021-03-10 2021-02-10 2021-04-14 2021-04-29 2021-10-11 uality Essential Primary Hea ct) d Lab Items lth Care Services Component 1. Improving the GM-MOH-236576-GO-RFQ / P Delivery and Utilization of Q Request for Quota Single Stage - One E rocurement of Laptops for HP IDA / D7310 Post Limited 10,000.00 8,092.48 Completed 2021-05-31 2021-04-19 2021-07-26 2021-05-20 2022-01-22 2021-06-26 uality Essential Primary Hea tions nvelope Unit lth Care Services GM-MOH-236579-GO-DIR / P Component 2. Project mana IDA / D7310 Post Direct Selection Direct 100,000.00 116,375.12 Signed 2021-05-26 2021-09-13 2021-05-31 2021-09-13 2021-07-05 2021-10-05 2022-01-01 rocurement of Vehicles gement Component 1. Improving the GM-MOH-258941-GO-RFQ / Delivery and Utilization of Q Request for Quota Single Stage - One E Office furniture for Birth and IDA / D7310 Post Open - National 20,000.00 67,648.72 Completed 2021-10-25 2021-12-20 2021-12-28 2022-06-18 2022-02-23 uality Essential Primary Hea tions nvelope Death Registry Unit Office lth Care Services Component 1. Improving the GM-MOH-262757-GO-DIR / P Delivery and Utilization of Q rocurement and installation o IDA / D7310 Post Direct Selection Direct 419,000.00 418,912.79 Signed 2021-11-11 2021-11-14 2021-11-16 2021-11-14 2021-12-21 2021-11-17 2022-06-19 uality Essential Primary Hea f a 50Nm3/H Oxygen Plant lth Care Services GM-MOH-262759-GO-RFB / P Component 1. Improving the rocurement of User Devices f Delivery and Utilization of Q Open - Internationa Single Stage - One E IDA / D7310 Post Request for Bids 930,000.00 2,009,084.48 Signed 2021-11-11 2021-11-15 2021-11-16 2021-11-15 2021-12-28 2021-12-29 2022-01-27 2022-01-12 2022-03-03 2022-02-01 2022-08-30 or Mass Registration and acc uality Essential Primary Hea l nvelope essories for CVRS devices lth Care Services Component 1. Improving the GM-MOH-190615-GO-RFB / C Delivery and Utilization of Q Open - Internationa Single Stage - One E ivil Registration ad Vital Stati IDA / D7310 Post Request for Bids 200,000.00 0.00 Canceled 2020-10-01 2020-10-06 2020-11-17 2020-12-17 2021-01-21 2021-07-20 uality Essential Primary Hea l nvelope stics (CRVS) software lth Care Services Component 1. Improving the GM-MOH-262775-GO-RFB / P Delivery and Utilization of Q Open - Internationa Single Stage - One E rocurement of medical equip IDA / D7310 Post Request for Bids 3,000,000.00 0.00 Canceled 2021-11-11 2021-11-16 2021-12-28 2022-01-27 2022-03-03 2022-08-30 uality Essential Primary Hea l nvelope ment for Farato NETC lth Care Services GM-MOH-262776-GO-RFQ / P Component 1. Improving the rocurement of office furnitur Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl IDA / D7310 Post Limited 14,000.00 0.00 2021-11-16 2022-01-11 2022-07-10 e and equipment/laptops and uality Essential Primary Hea tions nvelope ementation desktops for the waste treat lth Care Services ment centres Component 1. Improving the GM-MOH-258943-GO-RFQ / Delivery and Utilization of Q Request for Quota Single Stage - One E User devices accessories for IDA / D7310 Post Open - National 80,000.00 0.00 Canceled 2021-10-25 2021-12-20 2022-06-18 uality Essential Primary Hea tions nvelope CRVS lth Care Services GM-MOH-258942-GO-RFQ / Component 1. Improving the Office IT equipment for Birth Delivery and Utilization of Q Request for Quota Single Stage - One E IDA / D7310 Post Open - National 58,000.00 44,955.14 Signed 2021-11-19 2022-01-14 2021-12-28 2022-07-13 and Death Registry Unit Offic uality Essential Primary Hea tions nvelope e lth Care Services Component 1. Improving the GM-MOH-266469-GO-RFQ / Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl Waste Management Material IDA / D7310 Post Limited 20,000.00 0.00 2022-01-08 2022-03-05 2022-09-01 uality Essential Primary Hea tions nvelope ementation s lth Care Services GM-MOH-266474-GO-RFQ / Component 1. Improving the Office furniture, equipment/l Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl IDA / D7310 Post Limited 14,000.00 0.00 2022-01-08 2022-03-05 2022-09-01 aptops and desktops for the uality Essential Primary Hea tions nvelope ementation waste treatment center lth Care Services GM-MOH-266484-GO-DIR / 4 Component 1. Improving the trucks for the Regional Medic Delivery and Utilization of Q Pending Impl IDA / D7310 Post Direct Selection Direct 228,269.50 0.00 2021-12-06 2021-12-11 2022-01-15 2022-07-14 al Stores and 1 Motor Vehicle uality Essential Primary Hea ementation for NPS lth Care Services GM-MOH-266491-GO-RFB / E Component 1. Improving the quipment for the Central me Delivery and Utilization of Q Single Stage - One E Pending Impl IDA / D7310 Post Request for Bids Open - National 222,000.00 0.00 2022-01-03 2022-01-08 2022-02-19 2022-03-21 2022-04-25 2022-10-22 dical stores and 7 regional St uality Essential Primary Hea nvelope ementation ores lth Care Services Component 1. Improving the GM-MOH-266499-GO-RFB / L Delivery and Utilization of Q Single Stage - One E Pending Impl IDA / D7310 Post Request for Bids Open - National 115,540.00 0.00 2022-01-03 2022-01-08 2022-02-19 2022-03-21 2022-04-25 2022-10-22 ab Consumables uality Essential Primary Hea nvelope ementation lth Care Services GM-MOH-266519-GO-RFB / I Component 1. Improving the ntegrated Community Health Delivery and Utilization of Q Single Stage - One E Pending Impl IDA / D7310 Post Request for Bids Open - National 170,925.00 0.00 2022-01-05 2022-01-10 2022-02-21 2022-03-23 2022-04-27 2022-10-24 Kits (equipment and supplies uality Essential Primary Hea nvelope ementation ) lth Care Services GM-MOH-266520-GO-RFQ / I Component 1. Improving the T Equipment for Integrated M Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl IDA / D7310 Post Limited 2,900.00 0.00 2022-01-10 2022-03-07 2022-09-03 onitoring of Community Healt uality Essential Primary Hea tions nvelope ementation h Services Delivery lth Care Services Component 1. Improving the GM-MOH-266521-GO-RFQ / Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl IDA / D7310 Post Limited 53,050.00 0.00 2022-01-10 2022-03-07 2022-09-03 Data bundles for the tablets uality Essential Primary Hea tions nvelope ementation lth Care Services GM-MOH-274501-GO-RFQ / P Component 1. Improving the ortable 2.5-3.0 KVA diesel ge Delivery and Utilization of Q Request for Quota Single Stage - One E IDA / D7310 Post Limited 125,000.00 93,058.17 Completed 2022-01-29 2022-01-27 2022-03-26 2022-02-09 2022-09-22 2022-02-23 nerators (310 pieces) for NHI uality Essential Primary Hea tions nvelope S mass registration lth Care Services GM-MOH-274502-GO-RFQ / S Component 1. Improving the torage containers for user de Delivery and Utilization of Q Request for Quota Single Stage - One E IDA / D7310 Post Limited 15,000.00 15,848.97 Completed 2022-01-29 2022-01-27 2022-03-26 2022-02-09 2022-09-22 2022-02-23 vices (310 pieces) for NHIS m uality Essential Primary Hea tions nvelope ass registration lth Care Services Page 2 GM-MOH-274503-GO-RFQ / Component 1. Improving the White screen background for Delivery and Utilization of Q Request for Quota Single Stage - One E IDA / D7310 Post Limited 10,000.00 7,091.94 Completed 2022-01-29 2022-01-27 2022-03-26 2022-02-09 2022-09-22 2022-02-18 pictures (360 pieces) for NHI uality Essential Primary Hea tions nvelope S mass registration lth Care Services GM-MOH-274504-GO-RFQ / E Component 1. Improving the xtension Cords for user devic Delivery and Utilization of Q Request for Quota Single Stage - One E IDA / D7310 Post Limited 10,000.00 20,356.48 Completed 2022-01-29 2022-01-27 2022-03-26 2022-02-09 2022-09-22 2022-02-18 es (310 pieces) for NHIS mas uality Essential Primary Hea tions nvelope s registration lth Care Services Component 1. Improving the GM-MOH-262759-GO-DIR / A Delivery and Utilization of Q dditional Printers for NHIS Ma IDA / D7310 Post Direct Selection Direct 400,000.00 411,257.12 Completed 2022-02-04 2022-02-07 2022-02-09 2022-02-07 2022-03-16 2022-02-09 2022-09-12 2022-06-23 uality Essential Primary Hea ss Campaign. lth Care Services Component 1. Improving the GM-MOH-286715-GO-DIR / P Delivery and Utilization of Q IDA / D7310 Post Direct Selection Direct 200,000.00 189,541.89 Completed 2022-03-24 2022-03-24 2022-03-29 2022-03-24 2022-05-03 2022-04-04 2022-10-30 2022-06-24 rinters for Mass Campaign uality Essential Primary Hea lth Care Services Component 1. Improving the GM-MOH-287336-GO-DIR / In Delivery and Utilization of Q cinerators for Health Facilitie IDA / D7310 Post Direct Selection Direct 1,500,000.00 0.00 Canceled 2022-03-29 2022-04-03 2022-05-08 2022-11-04 uality Essential Primary Hea s lth Care Services Component 1. Improving the GM-MOH-289471-GO-RFB / E Delivery and Utilization of Q Open - Internationa Single Stage - One E Under Imple quipment NICU EFSTH Hospit IDA / D7310 Post Request for Bids 1,100,000.00 0.00 2022-04-09 2022-04-11 2022-04-14 2022-04-11 2022-05-26 2022-05-26 2022-06-25 2022-07-30 2023-01-26 uality Essential Primary Hea l nvelope mentation al lth Care Services GM-MOH-296510-GO-RFQ / 3 Component 1. Improving the Laptops, 1 All in One Printer, Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl IDA / D7310 Post Limited 20,000.00 0.00 2022-05-28 2022-07-23 2023-01-19 Photocopier and Scanner and uality Essential Primary Hea tions nvelope ementation 1 Shredding Machine - for NH lth Care Services IA Component 1. Improving the GM-MOH-296516-GO-RFB / X Delivery and Utilization of Q Open - Internationa Single Stage - One E Under Imple ray Machines and preinstallat IDA / D7310 Post Request for Bids 500,000.00 0.00 2022-05-23 2022-11-08 2022-05-28 2022-11-08 2022-07-09 2022-12-21 2022-08-08 2022-09-12 2023-03-11 uality Essential Primary Hea l nvelope mentation ion lth Care Services Component 1. Improving the GM-MOH-296519-GO-RFQ / 1 Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl 0 Motorbikes for Independent IDA / D7310 Post Open - National 50,000.00 0.00 2022-05-28 2022-07-23 2023-01-19 uality Essential Primary Hea tions nvelope ementation Verifiers lth Care Services Component 1. Improving the GM-MOH-296523-GO-RFQ / 1 Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl 0 Laptops for Independent V IDA / D7310 Post Open - National 20,000.00 0.00 2022-05-28 2022-07-23 2023-01-19 uality Essential Primary Hea tions nvelope ementation erifiers lth Care Services GM-MOH-296542-GO-RFQ / S Component 1. Improving the torage equipment for select Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl ed DOT, ART, and Malaria dis IDA / D7310 Post Open - National 71,000.00 0.00 2022-05-28 2022-07-23 2023-01-19 uality Essential Primary Hea tions nvelope ementation pensing sites in urgent need lth Care Services of improvement of medicines storage conditions GM-MOH-296543-GO-RFB / S Component 1. Improving the ecurity Equipment for the Ce Delivery and Utilization of Q Single Stage - One E Pending Impl IDA / D7310 Post Request for Bids Open - National 222,000.00 0.00 2022-05-23 2022-05-28 2022-07-09 2022-08-08 2022-09-12 2023-03-11 ntral medical Store and the 7 uality Essential Primary Hea nvelope ementation Regional Stores lth Care Services Component 1. Improving the GM-MOH-296308-GO-DIR / V Delivery and Utilization of Q IDA / D7310 Post Direct Selection Direct 40,000.00 0.00 Canceled 2022-05-29 2022-06-03 2022-07-08 2023-01-04 ehicle for PCU uality Essential Primary Hea lth Care Services Component 1. Improving the GM-MOH-297704-GO-RFQ / Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E NCD Survey Equipment, Rea IDA / D7310 Post 90,000.00 0.00 Canceled 2022-06-04 2022-05-31 2022-07-30 2023-01-26 uality Essential Primary Hea tions l nvelope gents and Consumables lth Care Services Component 1. Improving the GM-MOH-GM-304340-GO-RF Delivery and Utilization of Q Single Stage - One E B / User Devices for eLMIS, M IDA / D7310 Post Request for Bids Open - National 125,000.00 0.00 Signed 2022-07-15 2022-08-17 2022-07-20 2022-08-31 2022-09-28 2022-09-30 2022-10-03 2022-11-04 2023-05-03 uality Essential Primary Hea nvelope &E Unit and Call Center lth Care Services Component 1. Improving the GM-MOH-GM-300124-GO-RF Delivery and Utilization of Q Single Stage - One E B / IT Equipment for eLMIS, C IDA / D7310 Post Request for Bids Open - National 125,000.00 0.00 Canceled 2022-06-19 2022-06-24 2022-08-05 2022-09-04 2022-10-09 2023-04-07 uality Essential Primary Hea nvelope all Center and M&E Unit lth Care Services Component 1. Improving the GM-MOH-GM-300119-GO-RF Delivery and Utilization of Q Open - Internationa Single Stage - One E Under Imple B / Essential Medicines, equi IDA / D7310 Post Request for Bids 171,000.00 0.00 2022-07-20 2022-09-05 2022-07-25 2022-09-05 2022-09-05 2022-10-19 2022-10-05 2022-12-28 2022-11-09 2023-05-08 uality Essential Primary Hea l nvelope mentation pment and supplies lth Care Services Component 1. Improving the GM-MOH-311623-GO-DIR / V Delivery and Utilization of Q Pending Impl IDA / D7310 Post Direct Selection Direct - National 65,000.00 0.00 2022-08-23 2022-08-28 2022-10-02 2023-03-31 ehicle for PCU uality Essential Primary Hea ementation lth Care Services Component 1. Improving the GM-MOH-GM-319619-GO-RF Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Under Imple Q / Reagents for Chemistry A IDA / D7310 Post 26,000.00 0.00 2022-10-17 2022-11-16 2022-12-12 2023-06-10 uality Essential Primary Hea tions l nvelope mentation nalyzer - NCD Survey lth Care Services Component 1. Improving the GM-MOH-GM-319629-GO-RF Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Under Imple Q / Laboratory Materials - NC IDA / D7310 Post 95,000.00 0.00 2022-10-10 2022-11-16 2022-12-05 2023-06-03 uality Essential Primary Hea tions l nvelope mentation D Survey lth Care Services Component 1. Improving the GM-MOH-GM-319637-GO-RF Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Under Imple Q / Medical Gases for NICU E IDA / D7310 Post 90,000.00 0.00 2022-10-10 2022-11-21 2022-12-05 2023-06-03 uality Essential Primary Hea tions l nvelope mentation FSTH lth Care Services GM-MOH-GM-319638-GO-RF Component 1. Improving the Q / Hospital Furniture, Gener Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Under Imple IDA / D7310 Post 35,000.00 0.00 2022-10-10 2022-11-21 2022-12-05 2023-06-03 al Furniture and Materials for uality Essential Primary Hea tions l nvelope mentation NICU EFSTH lth Care Services Component 1. Improving the GM-MOH-266515-UN-DIR / H Delivery and Utilization of Q Direct - Internation Pending Impl IDA / D7310 Post Direct Selection 72,135.92 0.00 2022-11-18 2022-11-23 2022-12-28 2023-06-26 and operated fork lift uality Essential Primary Hea al ementation lth Care Services Page 3 Component 1. Improving the GM-MOH-GM-328596-GO-RF Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Under Imple Q / Dental Materials and Equi IDA / D7310 Post 85,000.00 0.00 2022-11-30 2023-05-17 2023-01-25 2023-07-24 uality Essential Primary Hea tions l nvelope mentation pment lth Care Services Component 1. Improving the GM-SWEDD-GM-333463-GO- Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Under Imple IDA / D7310 Post 200,000.00 0.00 2022-12-27 2023-02-21 2023-08-20 RFQ / eHRMIS uality Essential Primary Hea tions l nvelope mentation lth Care Services Component 1. Improving the GM-MOH-GM-334257-GO-RF Delivery and Utilization of Q Open - Internationa Single Stage - One E Under Imple B / Medical Equipment for Far IDA / D7310 Post Request for Bids 2,000,000.00 0.00 2023-01-02 2023-01-12 2023-01-07 2023-01-11 2023-02-18 2023-03-20 2023-04-24 2023-10-21 uality Essential Primary Hea l nvelope mentation ato Complex lth Care Services GM-MOH-GM-334258-GO-RF Component 1. Improving the B / Medical Equipment for ND Delivery and Utilization of Q Open - Internationa Single Stage - One E Under Imple IDA / D7310 Post Request for Bids 1,000,000.00 0.00 2023-01-03 2023-01-12 2023-01-08 2023-01-11 2023-02-19 2023-03-21 2023-04-25 2023-10-22 IC (National Diagnostic Imagi uality Essential Primary Hea l nvelope mentation ng Center) lth Care Services GM-MOH-GM-334259-GO-RF Component 1. Improving the B / Medical Equipment for th Delivery and Utilization of Q Open - Internationa Single Stage - One E Under Imple IDA / D7310 Post Request for Bids 1,000,000.00 0.00 2023-01-03 2023-01-12 2023-01-08 2023-01-11 2023-02-19 2023-03-21 2023-04-25 2023-10-22 e NBTC (National Blood Trans uality Essential Primary Hea l nvelope mentation fusion Center) lth Care Services GM-MOH-GM-334261-GO-RF Component 1. Improving the Q / Wall mounted lamps for F Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Under Imple IDA / D7310 Post 95,000.00 0.00 2023-01-07 2023-01-11 2023-03-04 2023-08-31 arato and NDIC (National Dia uality Essential Primary Hea tions l nvelope mentation gnostic Imaging Center) lth Care Services Component 1. Improving the GM-MOH-GM-334263-GO-RF Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Under Imple Q / Medical Gases and Bed H IDA / D7310 Post 95,000.00 0.00 2023-01-07 2023-01-11 2023-03-04 2023-08-31 uality Essential Primary Hea tions l nvelope mentation ead Units lth Care Services Component 1. Improving the GM-MOH-GM-334338-GO-RF Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl Q / Computer Based Examina IDA / D7310 Post Open - National 67,335.00 0.00 2023-01-08 2023-03-05 2023-09-01 uality Essential Primary Hea tions nvelope ementation tion Lab lth Care Services Component 1. Improving the GM-GEHSSP-GM-358247-GO- Delivery and Utilization of Q Request for Quota Single Stage - One E Under Imple IDA / D7310 Post Open - National 100,000.00 0.00 2023-04-29 2023-06-24 2023-12-21 RFQ / IT Equipment for DPI uality Essential Primary Hea tions nvelope mentation lth Care Services Component 1. Improving the GM-SWEDD-GM-358926-GO- Delivery and Utilization of Q Request for Quota Single Stage - One E Under Imple RFQ / IT Accessories ( Post C IDA / D7310 Post Open - National 60,000.00 0.00 2023-05-02 2023-06-27 2023-12-24 uality Essential Primary Hea tions nvelope mentation ampaign Activities) lth Care Services Component 1. Improving the GM-MOH-GM-361843-GO-RF Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl Q / Laptops for HIS System A IDA / D7310 Post Open - National 13,500.00 0.00 2023-05-22 2023-07-17 2024-01-13 uality Essential Primary Hea tions nvelope ementation dmins and Developer lth Care Services Component 1. Improving the GM-MOH-GM-361845-GO-RF Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Pending Impl Q / NFDQCL Medical Equipme IDA / D7310 Post 50,000.00 0.00 2023-05-21 2023-07-16 2024-01-12 uality Essential Primary Hea tions l nvelope ementation nt lth Care Services Component 1. Improving the GM-MOH-GM-361855-GO-RF Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / D7310 Post 50,000.00 0.00 2023-05-22 2023-07-17 2024-01-13 Q / BEU Medical Equipment uality Essential Primary Hea tions l nvelope ementation lth Care Services Component 1. Improving the GM-GEHSSP-GM-366047-GO- Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Pending Impl RFQ / Vehicle for National Ph IDA / D7310 Post 50,000.00 0.00 2023-06-17 2023-08-12 2024-02-08 uality Essential Primary Hea tions l nvelope ementation armaceutical Services lth Care Services Component 1. Improving the GM-GEHSSP-GM-366048-GO- Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Pending Impl RFQ / Forklifts for National Ph IDA / D7310 Post 100,000.00 0.00 2023-06-17 2023-08-12 2024-02-08 uality Essential Primary Hea tions l nvelope ementation armaceutical Services lth Care Services Component 1. Improving the GM-SWEDD-GM-366050-GO- Delivery and Utilization of Q Request for Quota Open - Internationa Single Stage - One E Pending Impl RFQ / Cargo trucks for Nation IDA / D7310 Post 100,000.00 0.00 2023-06-17 2023-08-12 2024-02-08 uality Essential Primary Hea tions l nvelope ementation al Pharmaceutical Services lth Care Services NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Improving the GM-MOH-244857-NC-RFB / C Delivery and Utilization of Q Open - Internationa Single Stage - One E onsulting services for Electro IDA / D7310 Post Request for Bids 300,000.00 0.00 Canceled 2021-07-31 2021-11-08 2021-08-05 2021-11-08 2021-09-16 2021-12-21 2021-10-16 2021-11-20 2022-05-19 uality Essential Primary Hea l nvelope nic Medical Records System lth Care Services GM-MOH-244858-NC-RFB / C Component 1. Improving the onsulting services for Electro Delivery and Utilization of Q Open - Internationa Single Stage - One E IDA / D7310 Post Request for Bids 300,000.00 0.00 Canceled 2021-07-31 2021-08-09 2021-08-05 2021-08-09 2021-09-16 2021-09-21 2021-10-16 2021-11-12 2021-11-20 2022-05-19 nic Logistics Management Inf uality Essential Primary Hea l nvelope ormation system lth Care Services GM-MOH-244856-NC-RFB / C Component 1. Improving the onsulting services for Electro Delivery and Utilization of Q Open - Internationa Single Stage - One E IDA / D7310 Post Request for Bids 300,000.00 0.00 Canceled 2021-07-31 2021-10-06 2021-08-05 2021-10-07 2021-09-16 2021-11-19 2021-10-16 2022-01-05 2021-11-20 2022-05-19 nic Human Resource Manage uality Essential Primary Hea l nvelope ment Information system lth Care Services GM-MOH-244859-NC-RFB / C Component 1. Improving the onsulting services for Nation Delivery and Utilization of Q Open - Internationa Single Stage - One E Under Imple al Health Insurance enrollme IDA / D7310 Post Request for Bids 500,000.00 0.00 2021-11-11 2022-02-03 2021-11-16 2022-02-08 2021-12-28 2022-03-21 2022-01-27 2022-05-17 2022-03-03 2022-08-30 uality Essential Primary Hea l nvelope mentation nt, provider management, an lth Care Services d claims processing system Component 1. Improving the GM-MOH-266464-NC-RFQ / N Delivery and Utilization of Q Request for Quota Single Stage - One E HIS membership enrollment IDA / D7310 Post Limited 10,000.00 9,750.82 Completed 2021-12-11 2021-12-08 2022-02-05 2022-02-06 2022-08-04 2022-09-15 uality Essential Primary Hea tions nvelope videos lth Care Services Page 4 Component 1. Improving the GM-MOH-266531-NC-RFB / D Delivery and Utilization of Q Single Stage - One E ata Entry Clerks for Mass NHI IDA / D7310 Post Request for Bids Open - National 81,370.00 0.00 Canceled 2021-12-07 2021-12-12 2022-01-23 2022-02-22 2022-03-29 2022-09-25 uality Essential Primary Hea nvelope S Registration lth Care Services Component 1. Improving the GM-MOH-266534-NC-RFB / E Delivery and Utilization of Q Single Stage - One E Pending Impl stablish internet connectivity IDA / D7310 Post Request for Bids Open - National 250,000.00 0.00 2021-12-06 2021-12-11 2022-01-22 2022-02-21 2022-03-28 2022-09-24 uality Essential Primary Hea nvelope ementation at all levels lth Care Services Component 1. Improving the GM-MOH-284593-NC-RFQ / U Delivery and Utilization of Q Request for Quota Single Stage - One E Under Imple pgrading Call Center and Gri IDA / D7310 Post Open - National 20,000.00 0.00 2022-03-20 2022-03-31 2022-05-15 2022-11-11 uality Essential Primary Hea tions nvelope mentation evance Management lth Care Services Component 1. Improving the GM-MOH-GM-300120-NC-RF Delivery and Utilization of Q Request for Quota Single Stage - One E Under Imple IDA / D7310 Post Open - National 10,000.00 0.00 2022-06-21 2022-08-16 2023-02-12 Q / Video Production NHIS uality Essential Primary Hea tions nvelope mentation lth Care Services Component 1. Improving the GM-MOH-GM-304597-NC-RF Delivery and Utilization of Q Request for Quota Single Stage - One E Under Imple IDA / D7310 Post Open - National 100,000.00 0.00 2022-07-23 2022-09-17 2023-03-16 Q / Tagging of all Assets uality Essential Primary Hea tions nvelope mentation lth Care Services Component 1. Improving the GM-SWEDD-GM-335361-NC- Delivery and Utilization of Q Request for Quota Single Stage - One E Pending Impl RFQ / ESIA and ESMP For Bas IDA / D7310 Post Open - National 100,000.00 0.00 2023-01-15 2023-03-12 2023-09-08 uality Essential Primary Hea tions nvelope ementation se and Brikama Hospitals lth Care Services CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Improving the GM-MOH-190599-CS-CQS / T Delivery and Utilization of Q Consultant Qualifi IDA / D7310 Post Open - National 13,000.00 0.00 Canceled 2020-10-01 2021-02-24 2020-10-22 2020-12-05 2021-01-04 2021-02-08 2021-08-07 arget audience analysis uality Essential Primary Hea cation Selection lth Care Services GM-MOH-190619-CS-LCS / E Component 2. Project mana Least Cost Selecti IDA / D7310 Post Open - National 50,000.00 17,109.94 Signed 2020-10-01 2021-02-22 2020-10-22 2020-12-05 2021-06-07 2021-01-02 2021-07-08 2021-02-01 2021-07-19 2021-03-08 2021-08-05 2021-04-12 2021-09-02 2021-10-09 xternal Auditor gement on GM-MOH-190598-CS-CQS / S Component 1. Improving the urvey of designated health fa Delivery and Utilization of Q Consultant Qualifi IDA / D7310 Post Open - National 50,000.00 60,784.05 Signed 2020-10-01 2020-08-18 2020-10-22 2020-09-10 2020-12-05 2020-09-28 2021-01-04 2020-11-04 2021-02-08 2021-01-21 2021-08-07 cilities asbestos products in t uality Essential Primary Hea cation Selection he buildings lth Care Services GM-MOH-190593-CS-CQS / A Component 1. Improving the rchitectural consulting servic Delivery and Utilization of Q Consultant Qualifi IDA / D7310 Post Open - National 190,000.00 267,505.00 Signed 2020-10-01 2020-08-02 2020-10-22 2020-12-05 2020-09-09 2021-01-04 2020-11-12 2021-02-08 2021-02-25 2021-08-07 es and supervision of renovat uality Essential Primary Hea cation Selection ion of designated health facili lth Care Services ties GM-MOH-205112-CS-CQS / A Component 1. Improving the ssessment of eLMIS and War Delivery and Utilization of Q Consultant Qualifi Pending Impleme ehouse Management System IDA / D7310 Post Open - National 10,500.00 0.00 2020-12-01 2020-12-22 2021-02-04 2021-03-06 2021-04-10 2021-10-07 uality Essential Primary Hea cation Selection ntation Software to strengthen LMIS lth Care Services & enhance supply visibility. GM-MOH-245308-CS-CQS / C Component 2. Project mana Consultant Qualifi Open - Internationa onsulting firm for feasibility s IDA / D7310 Post 100,000.00 0.00 Canceled 2021-07-26 2021-08-16 2021-09-29 2021-10-29 2021-12-03 2022-06-01 gement cation Selection l tudy for electronic procurem ent system GM-MOH-248608-CS-CQS / C Component 1. Improving the onsulting firm for Environme Delivery and Utilization of Q Consultant Qualifi IDA / D7310 Post Open - National 90,000.00 0.00 Canceled 2021-08-16 2021-08-16 2021-09-06 2021-10-20 2021-10-06 2021-11-19 2021-12-24 2022-06-22 ntal and Social Impact Asses uality Essential Primary Hea cation Selection sments and Plans for renovat lth Care Services ion of health facilities GM-MOH-176395-CS-QCBS / Component 1. Improving the Construction Supervision of t Delivery and Utilization of Q Consultant Qualifi Open - Internationa Pending Impleme IDA / D7310 Post 129,865.00 0.00 2021-10-11 2021-11-01 2021-12-15 2022-01-14 2022-02-18 2022-08-17 he emergency treatment Cen uality Essential Primary Hea cation Selection l ntation ter lth Care Services GM-MOH-195887-CS-CQS / C Component 1. Improving the onstruction Supervision for N Delivery and Utilization of Q Consultant Qualifi Under Implement IDA / D7310 Post Open - National 292,725.00 0.00 2021-10-11 2020-08-28 2021-11-01 2021-12-15 2020-11-06 2022-01-14 2020-11-19 2022-02-18 2022-08-17 ational Emergency Treatmen uality Essential Primary Hea cation Selection ation t Center ( Local Firm). lth Care Services GM-MOH-266460-CS-CQS / C Component 1. Improving the onsulting firm for Environme Delivery and Utilization of Q Consultant Qualifi ntal and Social Impact Asses IDA / D7310 Post Open - National 90,000.00 0.00 Signed 2021-12-03 2021-12-03 2021-12-24 2022-02-06 2022-01-26 2022-03-08 2022-03-28 2022-04-12 2022-10-09 uality Essential Primary Hea cation Selection sments and Plans for renovat lth Care Services ion of Health facilities GM-MOH-266487-CS-CQS / C Component 1. Improving the onsulting services for the Nat Delivery and Utilization of Q Consultant Qualifi Pending Impleme IDA / D7310 Post Open - National 14,865.00 0.00 2021-12-15 2022-01-05 2022-02-18 2022-03-20 2022-04-24 2022-10-21 ional Strategy Plan for Purch uality Essential Primary Hea cation Selection ntation ase and Store of Health prod lth Care Services ucts Management GM-MOH-266509-CS-CQS / C Component 1. Improving the onsulting Services to provide Delivery and Utilization of Q Consultant Qualifi Pending Impleme TA to adapts tools, on LAB qu IDA / D7310 Post Open - National 14,939.65 0.00 2022-01-04 2022-01-25 2022-03-10 2022-04-09 2022-05-14 2022-11-10 uality Essential Primary Hea cation Selection ntation antification and development lth Care Services of training material GM-MOH-266518-CS-CQS / C Component 1. Improving the onsulting Services for the de Delivery and Utilization of Q Consultant Qualifi Pending Impleme velopment of Costed integrat IDA / D7310 Post Open - National 15,020.00 0.00 2022-01-05 2022-01-26 2022-03-11 2022-04-10 2022-05-15 2022-11-11 uality Essential Primary Hea cation Selection ntation ed Community Health Strate lth Care Services gy plan including HIV/TB Component 1. Improving the GM-MOH-266523-CS-CQS / C Delivery and Utilization of Q Consultant Qualifi Pending Impleme onsulting services for Data Q IDA / D7310 Post Open - National 40,000.00 0.00 2022-01-05 2022-01-26 2022-03-11 2022-04-10 2022-05-15 2022-11-11 uality Essential Primary Hea cation Selection ntation uality Review lth Care Services GM-MOH-296306-CS-CQS / A Component 1. Improving the rchitect consulting services f Delivery and Utilization of Q Consultant Qualifi or EFSTH NICU, Bwiam Hospit IDA / D7310 Post Open - National 700,000.00 338,704.00 Signed 2022-05-21 2022-06-02 2022-06-11 2022-07-25 2022-06-17 2022-08-24 2022-07-26 2022-09-28 2022-08-20 2023-03-27 uality Essential Primary Hea cation Selection al accommodation and Diagn lth Care Services ostic Imaging Services Page 5 Component 1. Improving the GM-MOH-GM-300118-CS-CQ Delivery and Utilization of Q Consultant Qualifi Open - Internationa S / Health Planner Basse Brik IDA / D7310 Post 10,000.00 47,025.00 Signed 2022-06-16 2022-06-20 2022-07-07 2022-06-21 2022-08-20 2022-07-19 2022-09-19 2022-08-22 2022-10-24 2022-09-07 2023-04-22 uality Essential Primary Hea cation Selection l ama Hospital Concept Design lth Care Services Component 1. Improving the GM-MOH-GM-300122-CS-CQ Delivery and Utilization of Q Consultant Qualifi Under Implement S / Communication Strategy IDA / D7310 Post Open - National 15,000.00 0.00 2022-06-19 2022-07-17 2022-07-10 2022-07-17 2022-08-23 2022-09-22 2022-10-27 2023-04-25 uality Essential Primary Hea cation Selection ation NHIS lth Care Services Component 1. Improving the GM-MOH-GM-327243-CS-CQ Delivery and Utilization of Q Consultant Qualifi Under Implement S / Review of Gambia Ministr IDA / D7310 Post Open - National 30,000.00 0.00 2022-11-20 2022-11-21 2022-12-11 2023-01-24 2023-02-23 2023-03-30 2023-09-26 uality Essential Primary Hea cation Selection ation y of Health ACTS lth Care Services GM-SWEDD-GM-339271-CS- Component 1. Improving the CQS / HVAC and Medical Gas Delivery and Utilization of Q Consultant Qualifi Open - Internationa Under Implement IDA / D7310 Post 80,000.00 0.00 2023-01-31 2023-02-10 2023-02-21 2023-02-10 2023-04-06 2023-05-06 2023-06-10 2023-12-07 es Design for Basse and Brik uality Essential Primary Hea cation Selection l ation ama Hospitals lth Care Services GM-GEHSSP-GM-357601-CS- Component 1. Improving the CQS / SUPERVISION SERVICE Delivery and Utilization of Q Consultant Qualifi Under Implement S FOR FOOD AND DRUG QUA IDA / D7310 Post Open - National 120,000.00 0.00 2023-04-19 2023-04-28 2023-05-10 2023-06-23 2023-07-23 2023-08-27 2024-02-23 uality Essential Primary Hea cation Selection ation LITY CONTROL LABORATORY lth Care Services AND BIOMEDICAL ENGINEERI NG UNIT Component 1. Improving the GM-MOH-GM-361859-CS-CQ Delivery and Utilization of Q Consultant Qualifi Pending Impleme S / E&S Due Diligence for NF IDA / D7310 Post Open - National 21,000.00 0.00 2023-05-15 2023-06-05 2023-07-19 2023-08-18 2023-09-22 2024-03-20 uality Essential Primary Hea cation Selection ntation DQCL & BEU lth Care Services Component 1. Improving the GM-MOH-GM-361860-CS-CQ Delivery and Utilization of Q Consultant Qualifi Open - Internationa Pending Impleme S / Medical Equipment Super IDA / D7310 Post 20,000.00 0.00 2023-05-17 2023-06-07 2023-07-21 2023-08-20 2023-09-24 2024-03-22 uality Essential Primary Hea cation Selection l ntation vision of NFDQCL and BEU lth Care Services Component 1. Improving the GM-MOH-GM-362024-CS-CQ Delivery and Utilization of Q Consultant Qualifi Pending Impleme S / HR Performance manage IDA / D7310 Post Open - National 20,000.00 0.00 2023-05-17 2023-06-07 2023-07-21 2023-08-20 2023-09-24 2024-03-22 uality Essential Primary Hea cation Selection ntation ment Consultancy lth Care Services Component 1. Improving the GM-GEHSSP-GM-364352-CS- Delivery and Utilization of Q Consultant Qualifi Open - Internationa Under Implement CQS / ELECTRONIC CASE BAS IDA / D7310 Post 200,000.00 0.00 2023-05-30 2023-06-02 2023-06-20 2023-06-02 2023-08-03 2023-09-02 2023-10-07 2024-04-04 uality Essential Primary Hea cation Selection l ation ED SURVEILLANCE SYSTEM lth Care Services INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GM-MOH-190617-CS-INDV / Component 1. Improving the Civil Registration and Vital St Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 100,000.00 127,145.31 Signed 2020-10-01 2020-11-03 2020-11-19 2021-01-19 2020-12-10 2021-01-14 2021-01-14 2021-01-19 2021-07-13 atics (CRVS) Consulting Servi uality Essential Primary Hea ant Selection ce lth Care Services GM-MOH-208410-CS-INDV / I Component 1. Improving the nternal Medicine / Medical Su Delivery and Utilization of Q Individual Consult bspecialties : Recruitment of IDA / D7310 Post Open 54,230.00 57,000.00 Signed 2020-12-07 2020-12-08 2021-01-25 2021-03-27 2021-02-15 2021-04-23 2021-03-22 2021-05-05 2021-09-18 uality Essential Primary Hea ant Selection specialist from subregion for lth Care Services Internal Medicine / Medical S ubspecialties ( 2 Positions) GM-MOH-208445-CS-INDV / Component 1. Improving the Laboratory Medicine/ Patholo Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 54,230.00 57,000.00 Signed 2020-12-07 2020-12-08 2021-01-25 2021-03-13 2021-02-15 2021-03-25 2021-03-22 2021-03-26 2021-09-18 gy (2 Positions)- Recruitment uality Essential Primary Hea ant Selection of specialist from subregion lth Care Services GM-MOH-208446-CS-INDV / Component 1. Improving the Obstetrician Gynecologist (1 Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 54,230.00 51,000.00 Signed 2020-12-07 2020-12-08 2021-01-25 2021-04-03 2021-02-15 2021-04-23 2021-03-22 2021-05-05 2021-09-18 Position)- Recruitment of spe uality Essential Primary Hea ant Selection cialist from subregion lth Care Services GM-MOH-208448-CS-INDV / Component 1. Improving the Radiologist (1 Positions)- Rec Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 54,230.00 57,000.00 Signed 2020-12-07 2020-12-08 2021-01-25 2021-03-24 2021-02-15 2021-03-31 2021-03-22 2021-04-16 2021-09-18 ruitment of specialist from su uality Essential Primary Hea ant Selection bregion lth Care Services GM-MOH-208450-CS-INDV / Component 1. Improving the Family Medicine Specialist (2 Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 54,230.00 161,400.00 Signed 2020-12-07 2020-12-08 2021-01-25 2021-03-27 2021-02-15 2021-04-29 2021-03-22 2021-05-19 2021-09-18 Positions)- Recruitment of sp uality Essential Primary Hea ant Selection ecialist from subregion lth Care Services GM-MOH-208452-CS-INDV / Component 1. Improving the Paediatricians (3 Positions)- Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 54,230.00 216,000.00 Signed 2020-12-07 2020-12-08 2021-01-25 2021-03-10 2021-02-15 2021-03-24 2021-03-22 2021-05-05 2021-09-18 Recruitment of specialist fro uality Essential Primary Hea ant Selection m subregion lth Care Services GM-MOH-208453-CS-INDV / Component 1. Improving the Anesthesiologist (1 Position)- Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 54,230.00 111,300.00 Signed 2020-12-07 2020-12-08 2021-01-25 2021-03-24 2021-02-15 2021-04-29 2021-03-22 2021-05-19 2021-09-18 Recruitment of specialist fro uality Essential Primary Hea ant Selection m subregion lth Care Services GM-MOH-223089-CS-INDV / Recruitment of Procurement Component 2. Project mana Individual Consult IDA / D7310 Post Open 20,000.00 43,418.86 Signed 2021-03-05 2021-03-11 2021-04-23 2021-05-17 2021-05-14 2021-05-18 2021-06-18 2021-06-01 2021-12-15 2021-07-15 Officer (One Position) and Op gement ant Selection erations Officer (One Position ) Component 1. Improving the GM-MOH-223113-CS-INDV / Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 13,000.00 14,025.00 Signed 2021-03-05 2021-03-10 2021-04-23 2021-05-05 2021-05-14 2021-07-16 2021-06-18 2021-07-20 2021-12-15 Target Audience Analysis uality Essential Primary Hea ant Selection lth Care Services Component 1. Improving the GM-MOH-227727-CS-CDS / O Delivery and Utilization of Q pen CRVS technical assistanc IDA / D7310 Post Direct Selection Direct 10,000.00 0.00 Canceled 2021-04-01 2021-04-01 2021-04-11 2021-04-03 2021-06-15 2021-12-12 uality Essential Primary Hea e lth Care Services GM-MOH-244813-CS-INDV / Component 2. Project mana Individual Consult IDA / D7310 Post Open 20,000.00 17,126.55 Signed 2021-07-22 2021-07-23 2021-09-09 2021-10-04 2021-09-30 2021-10-05 2021-11-04 2021-10-22 2022-05-03 Recruitment of Operations Of gement ant Selection ficer Page 6 Component 1. Improving the GM-MOH-262760-CS-CDS / C Delivery and Utilization of Q onsulting services for CVRS a IDA / D7310 Post Direct Selection Direct 345,000.00 437,463.93 Signed 2021-11-11 2021-11-14 2021-11-21 2021-11-16 2022-01-25 2021-12-16 2022-07-24 uality Essential Primary Hea nd NHIS mass registration lth Care Services GM-MOH-262763-CS-CDS / R Component 1. Improving the ecruitment of Family Medicin Delivery and Utilization of Q IDA / D7310 Post Direct Selection Direct 170,000.00 98,400.00 Signed 2021-11-11 2021-10-04 2021-11-21 2021-10-14 2022-01-25 2021-11-17 2022-07-24 e Specialist (2 positions) and uality Essential Primary Hea Pediatrician (1 position) lth Care Services Component 1. Improving the GM-MOH-226906-CS-CDS / C Delivery and Utilization of Q onstruction Supervision for N IDA / D7310 Post Direct Selection Direct 140,727.30 213,601.00 Signed 2021-11-11 2021-02-07 2021-11-21 2021-02-08 2022-01-25 2021-05-08 2022-07-24 uality Essential Primary Hea ETC and medical equipment lth Care Services Component 1. Improving the GM-MOH-262798-CS-CDS / E Delivery and Utilization of Q nhancing grievance redress s IDA / D7310 Post Direct Selection Direct 20,000.00 0.00 Canceled 2021-11-11 2021-11-21 2022-01-25 2022-07-24 uality Essential Primary Hea ystem lth Care Services GM-MOH-273571-CS-INDV / Component 2. Project mana Individual Consult IDA / D9280 Post Open 50,000.00 22,733.15 Signed 2022-01-18 2022-01-30 2022-03-08 2022-04-04 2022-03-29 2022-05-17 2022-05-03 2022-06-07 2022-10-30 Recruitment of Senior Accou gement ant Selection ntant GM-MOH-276723-CS-INDV / Dentist Program - Recruitme nt of Oral and Maxillofacial S Component 1. Improving the urgeon, Restorative Dentistry Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 100,000.00 0.00 Canceled 2022-02-21 2022-04-11 2022-05-02 2022-06-06 2022-12-03 Specialist with emphasis on P uality Essential Primary Hea ant Selection rosthodontics and advanced lth Care Services restoration and Oral Diagnosi s with emphasis on oral medi cine, radiology and oral path ology. Component 1. Improving the GM-MOH-278947-CS-INDV / Delivery and Utilization of Q Individual Consult Oral and Maxillofacial Surgeo IDA / D7310 Post Open 50,000.00 55,000.00 Signed 2022-02-14 2022-02-27 2022-04-04 2022-06-23 2022-04-25 2022-07-06 2022-05-30 2022-07-20 2022-11-26 uality Essential Primary Hea ant Selection n - Recruitment lth Care Services GM-MOH-278949-CS-INDV / Component 1. Improving the Restorative Dentistry Speciali Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 50,000.00 55,000.00 Signed 2022-02-14 2022-02-24 2022-04-04 2022-06-28 2022-04-25 2022-07-12 2022-05-30 2022-07-20 2022-11-26 st with emphasis on Prosthod uality Essential Primary Hea ant Selection ontics and advanced restorat lth Care Services ion GM-MOH-278950-CS-INDV / Component 1. Improving the Oral Diagnosis Specialist with Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 50,000.00 55,000.00 Signed 2022-02-15 2022-02-27 2022-04-05 2022-06-16 2022-04-26 2022-07-06 2022-05-31 2022-07-20 2022-11-27 emphasis on oral medicine, r uality Essential Primary Hea ant Selection adiology and oral pathology lth Care Services Component 1. Improving the GM-MOH-294970-CS-INDV / Delivery and Utilization of Q Individual Consult Pediatric Nurse Tutor - 2 posi IDA / D7310 Post Open 30,000.00 83,500.00 Signed 2022-05-12 2022-05-31 2022-06-30 2022-08-11 2022-07-21 2022-08-31 2022-08-25 2022-09-15 2023-02-21 uality Essential Primary Hea ant Selection tions lth Care Services Component 1. Improving the GM-MOH-295418-CS-INDV / Delivery and Utilization of Q Individual Consult NHIA Benefits Package Consu IDA / D7310 Post Open 20,000.00 2.95 Signed 2022-05-17 2022-06-12 2022-07-04 2022-08-12 2022-07-25 2022-08-12 2022-08-29 2022-08-30 2023-02-25 uality Essential Primary Hea ant Selection ltancy lth Care Services Component 1. Improving the GM-MOH-295419-CS-INDV / Delivery and Utilization of Q Individual Consult IDA / D7310 Post Open 30,000.00 65,450.00 Signed 2022-05-17 2022-06-12 2022-07-05 2022-08-12 2022-07-26 2022-08-12 2022-08-30 2022-08-30 2023-02-26 NHIA Actuary Consultancy uality Essential Primary Hea ant Selection lth Care Services GM-MOH-GM-304359-CS-IND Component 1. Improving the V / Post Graduate Medical Tr Delivery and Utilization of Q Direct - Internation Pending Impleme ainer -Cardiologist (1 position IDA / D7310 Post Direct Selection 87,000.00 0.00 2022-07-18 2022-07-28 2022-10-01 2023-03-30 uality Essential Primary Hea al ntation ) lth Care Services Replacement of Consultants - Pediatricians (2 positions) Component 1. Improving the GM-SWEDD-GM-307086-CS- Delivery and Utilization of Q Direct - Internation CDS / Oral and Maxillofacial S IDA / D7310 Post Direct Selection 55,000.00 55,000.00 Signed 2022-08-06 2022-02-27 2022-08-16 2022-08-17 2022-10-20 2022-09-02 2023-04-18 uality Essential Primary Hea al urgery (Dean) lth Care Services Component 1. Improving the GM-MOH-GM-319798-CS-IND Delivery and Utilization of Q Individual Consult V / Review of Gambia Ministr IDA / D7310 Post Open - National 30,000.00 0.00 Canceled 2022-11-15 2023-01-03 2023-01-24 2023-02-28 2023-08-27 uality Essential Primary Hea ant Selection y of Health ACTS lth Care Services GM-MOH-GM-327257-CS-IND Component 1. Improving the V / Development of Costed in Delivery and Utilization of Q Individual Consult Under Implement IDA / D7310 Post Open - National 15,000.00 0.00 2022-11-18 2023-05-05 2023-01-06 2023-01-27 2023-03-03 2023-08-30 tegrated Community Health uality Essential Primary Hea ant Selection ation Strategy Plan lth Care Services Component 1. Improving the GM-SWEDD-GM-333448-CS- Delivery and Utilization of Q Pending Impleme CDS / Midterm Review House IDA / D7310 Post Direct Selection Direct - National 113,000.00 0.00 2022-12-22 2023-01-01 2023-03-07 2023-09-03 uality Essential Primary Hea ntation hold Survey lth Care Services GM-SWEDD-GM-346417-CS-I Component 1. Improving the NDV / Consultancy for the De Delivery and Utilization of Q Individual Consult Open - Internationa Under Implement IDA / D7310 Post 13,000.00 0.00 2023-03-01 2023-03-02 2023-04-19 2023-05-10 2023-06-14 2023-12-11 velopment of Laboratory Trai uality Essential Primary Hea ant Selection l ation ning curricula lth Care Services GM-SWEDD-GM-355339-CS- Component 1. Improving the CDS / Design and Supervisio Delivery and Utilization of Q Pending Impleme IDA / D7310 Post Direct Selection Direct - National 950,000.00 0.00 2023-04-06 2023-04-16 2023-06-20 2023-12-17 n of New Basse and Brikama uality Essential Primary Hea ntation Hospitals lth Care Services Component 1. Improving the GM-GEHSSP-GM-357614-CS-I Delivery and Utilization of Q Individual Consult Open - Internationa Under Implement NDV / Drafting of the Laborat IDA / D7310 Post 20,000.00 0.00 2023-04-19 2023-05-02 2023-06-07 2023-06-28 2023-08-02 2024-01-29 uality Essential Primary Hea ant Selection l ation ory Quality Manual lth Care Services GM-GEHSSP-GM-364193-CS-I NDV / Recruitment of 5 Post Component 1. Improving the Graduate Consultants (Pediat Delivery and Utilization of Q Individual Consult Open - Internationa Under Implement IDA / D7310 Post 85,000.00 0.00 2023-05-29 2023-06-02 2023-07-17 2023-08-07 2023-09-11 2024-03-09 rics/Child Health, Internal Me uality Essential Primary Hea ant Selection l ation dicine/Medical Subspecialties lth Care Services and Obstetrics and Gynaecol ogy) Component 1. Improving the GM-GEHSSP-GM-364355-CS-I Delivery and Utilization of Q Individual Consult Under Implement NDV / Environmental Consult IDA / D7310 Post Open - National 20,000.00 0.00 2023-05-30 2023-06-02 2023-07-18 2023-08-08 2023-09-12 2024-03-10 uality Essential Primary Hea ant Selection ation ant lth Care Services Page 7 PROCUREMENT PLAN (Textual Part) Project information: Kiribati Pacific Islands Regional Oceanscape Program (P165821) Project Implementation agency: Ministry of Fisheries and Marine Resource Development (MFMRD) Date of the Procurement Plan: March 20, 2019 Period covered by this Procurement Plan: March 1, 2019 – February 28, 2020. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in 2002 Kiribati Procurement Act, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. a. open advertising of the procurement opportunity at the national level; b. the procurement is open to eligible firms from any country; c. the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights; d. contracts with an appropriate allocation of responsibilities, risks, and liabilities; e. publication of contract award information; f. rights for the Bank to review procurement documentation and activities; g. an effective complaints mechanism; and h. maintenance of records of the Procurement Process. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information. Procurement in Situations of Urgent Need of Assistance or Capacity Constraints or Capacity Constraints PROCUREMENT Kiribati : Kiribati: Pacific Islands Regional Oceanscape Program PLAN General Information Country: Kiribati 2019-03-28 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165821 GPN Date: Project Name: Kiribati: Pacific Islands Regional Oceanscape Program Loan / Credit No: IDA / D5570, / Ministry of Fisheries and Marine Resource Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KI-MFMRD-243979-CW-RFQ / Delivering Effective Project Request for Quota Single Stage - One E Other (with field f 2022-03-1 The minor construction work IDA / D5570 Post Limited 8,000.00 9,223.59 Completed 2021-07-20 2021-06-01 2021-09-14 2021-07-01 Management tions nvelope or explanation) 3 cost for PROP new Office at K PF Complex GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Monitoring, C MFMRD-GD-1 / Computers, p Request for Quota Single Stage - One E IDA / D5570 ontrol and Surveillance of La Post Open - National 6,000.00 4,847.26 Signed 2019-04-01 2019-05-27 2019-07-31 2019-11-23 2019-07-31 rinter and software tions nvelope rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-GD-2 / Operation Ve Request for Quota Open - Internationa Single Stage - One E IDA / D5570 ontrol and Surveillance of La Post 120,000.00 91,917.00 Completed 2019-04-01 2019-12-01 2019-05-27 2019-07-25 2019-11-23 2019-10-09 hicle (2 units) tions l nvelope rge-Scale Oceanic Fisheries MFMRD-GD-3 / Office Furnitu Request for Quota Single Stage - One E / Post Open - National 16,500.00 4,470.89 Completed 2019-04-01 2019-11-28 2019-05-27 2019-07-30 2019-11-23 2019-08-23 re (table, chair and filing cabi tions nvelope nets) Strengthening Monitoring, C MFMRD-GD-4 / Boat (to facili Request for Quota Open - Internationa Single Stage - One E IDA / D5570 ontrol and Surveillance of La Post 58,000.00 37,351.00 Completed 2019-04-01 2020-02-24 2019-05-27 2020-03-14 2019-11-23 2020-04-29 tate coastal survey) tions l nvelope rge-Scale Oceanic Fisheries Strengthening Monitoring, C PROP-GO- RFQ1 / MCS office Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / D5570 ontrol and Surveillance of La Post 90,000.00 0.00 2024-06-08 2024-08-03 2025-01-30 furniture tions l nvelope ementation rge-Scale Oceanic Fisheries PROP-GO- RFQ5 / Hardware Strengthening Monitoring, C and software to transition fro Request for Quota Open - Internationa Single Stage - One E Pending Impl IDA / D5570 ontrol and Surveillance of La Post 150,000.00 0.00 2024-03-06 2024-05-01 2024-10-28 m paper-based data collectio tions l nvelope ementation rge-Scale Oceanic Fisheries n to an online e-reporting sys tem PROP-GO- RFQ6 / Catalyze s Diversifying Marine-Based R Request for Quota Open - Internationa Single Stage - One E Pending Impl ysteme for sustainable suppl IDA / D5570 evenue Streams for Outer Isl Post 400,000.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions l nvelope ementation y chains in up to four outer is and Coastal Communities lands KI-MFMRD-154493-GO-RFQ / Delivering Effective Project Request for Quota Single Stage - One E Pending Impl IDA / D5570 Post Open - National 21,000.00 0.00 2021-02-13 2021-04-10 2021-10-07 Office IT equipment for new Management tions nvelope ementation PMU staff KI-MFMRD-157413-CS-INDV / Delivering Effective Project Request for Quota Single Stage - One E Pending Impl IDA / D5570 Post Open - National 10,000.00 0.00 2021-02-20 2021-04-17 2021-10-14 Furniture for new PMU staff Management tions nvelope ementation PROP-GO- RFQ3 / Observer t Strengthening Monitoring, C Request for Quota Open - Internationa Single Stage - One E ransport vessel - Betio &Kiriti IDA / D5570 ontrol and Surveillance of La Post 160,000.00 0.00 Canceled 2021-03-15 2021-05-13 2021-05-10 2021-11-06 tions l nvelope mati rge-Scale Oceanic Fisheries PROP-GO- RFQ2 / Supply an Strengthening Monitoring, C Request for Propo Open - Internationa d Install 3 camera system on IDA / D5570 ontrol and Surveillance of La Prior Multi Stage 750,000.00 0.00 Canceled 2022-07-01 2022-09-16 2022-09-16 2022-07-06 2022-11-25 2023-04-13 2024-10-04 sals l 50 long-liners rge-Scale Oceanic Fisheries KI-MFMRD-250635-GO-RFQ / Strengthening Monitoring, C Request for Quota Single Stage - One E PROP Office operational vehi IDA / D5570 ontrol and Surveillance of La Post Open - National 40,000.00 37,200.60 Signed 2021-09-25 2021-09-19 2021-11-20 2021-10-19 2022-05-19 tions nvelope cle #3. rge-Scale Oceanic Fisheries KI-MFMRD-314392-GO-RFQ / Purchasing 2 Hp Notebook la Delivering Effective Project Request for Quota Single Stage - One E IDA / D5570 Post Open - National 3,070.00 0.00 Canceled 2022-09-24 2022-11-19 2023-05-18 ptops (replacement for 2 staf Management tions nvelope f) and 6 flash drives (32GB) f or PMU Staff KI-MFMRD-247579-GO-RFQ / Strengthening Monitoring, C Request for Quota Open - Internationa Single Stage - One E Observer transport vessel - B IDA / D5570 ontrol and Surveillance of La Post 160,000.00 0.00 Canceled 2022-03-06 2021-08-18 2022-05-01 2022-10-28 tions l nvelope etio & Kiritimati rge-Scale Oceanic Fisheries KI-MFMRD-247577-GO-RFB / Strengthening Monitoring, C Open - Internationa Single Stage - One E Pending Impl Supply and Install 3 camera s IDA / D5570 ontrol and Surveillance of La Post Request for Bids 750,000.00 0.00 2024-05-22 2024-05-27 2024-07-08 2024-08-07 2024-09-11 2025-03-10 l nvelope ementation ystem on 50 long-liners rge-Scale Oceanic Fisheries NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Monitoring, C PROP-CS-FIRM1 / Support a t Consultant Qualifi Open - Internationa Pending Impleme IDA / D5570 ontrol and Surveillance of La Post 100,000.00 0.00 2023-06-30 2023-07-21 2023-09-03 2023-10-03 2023-11-07 2024-05-05 rial with KFL vessels cation Selection l ntation rge-Scale Oceanic Fisheries Page 1 Strengthening Monitoring, C PROP-CS-FIRM4 / Legislative Consultant Qualifi Open - Internationa Pending Impleme IDA / D5570 ontrol and Surveillance of La Post 70,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-05-07 and policy reviews. cation Selection l ntation rge-Scale Oceanic Fisheries PROP-CS-FIRM6 / ER training Strengthening Monitoring, C - consultant (Preparation of Consultant Qualifi Open - Internationa Pending Impleme IDA / D5570 ontrol and Surveillance of La Post 80,000.00 0.00 2022-07-04 2022-07-25 2022-09-07 2022-10-07 2022-11-11 2023-05-10 materials; language translati cation Selection l ntation rge-Scale Oceanic Fisheries on - for skippers and MFMRD staff to support ER] PROP-CS-FIRM7 / Consultant/ Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme TA for Evidence and case pre IDA / D5570 ontrol and Surveillance of La Post 90,000.00 0.00 2023-03-03 2023-03-24 2023-05-07 2023-06-06 2023-07-11 2024-01-07 cation Selection l ntation paration rge-Scale Oceanic Fisheries PROP-CS-FIRM8 / Observer d Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme e-briefer and trainer training IDA / D5570 ontrol and Surveillance of La Post 140,000.00 0.00 2022-01-03 2022-01-24 2022-03-09 2022-04-08 2022-05-13 2022-11-09 cation Selection l ntation & VMS systems maintenance rge-Scale Oceanic Fisheries training PROP-CS-FIRM10 / PSM proc Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme esses and procedures (includ IDA / D5570 ontrol and Surveillance of La Post 75,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-05-07 cation Selection l ntation ing transhipment monitoring) rge-Scale Oceanic Fisheries PROP-CS-FIRM12 / Preparati on of a Kiritimati Ocean Reso Strengthening Monitoring, C urces Master Plan, Kiritimati Consultant Qualifi Open - Internationa Under Implement IDA / D5570 ontrol and Surveillance of La Post 580,000.00 0.00 2021-09-01 2022-04-08 2021-09-22 2022-04-13 2021-11-05 2022-11-16 2021-12-05 2022-01-09 2022-07-08 Sports Fishing Management cation Selection l ation rge-Scale Oceanic Fisheries Plan and the operationalisati on of the Kiritimati aquaium f ish management plan. PROP-CS-FIRM13 / Strengthe ning coastal resource licensin g systems nationwide, enhan Diversifying Marine-Based R Consultant Qualifi Open - Internationa Pending Impleme cing community participation IDA / D5570 evenue Streams for Outer Isl Post 400,000.00 0.00 2022-07-01 2022-07-22 2022-09-04 2022-10-04 2022-11-08 2023-05-07 cation Selection l ntation and strengthening the capaci and Coastal Communities ty and operational effectiven ess of MFMRD's Coastal Fishe ries Division. PROP-CS-FIRM15 / Developm Improving Seafood Toxicolog ent of a lagoon and coastal fi Consultant Qualifi Open - Internationa Pending Impleme IDA / D5570 y and Safety Measures in Sel Post 500,000.00 0.00 2020-07-01 2020-07-22 2020-09-04 2020-10-04 2020-11-08 2021-05-07 sheries pollution and seafood cation Selection l ntation ected Fisheries toxin monitoring and manag ement plan. PROP-CS-FIRM16 / Seafood T Improving Seafood Toxicolog Consultant Qualifi Open - Internationa Pending Impleme oxicology Training and Capac IDA / D5570 y and Safety Measures in Sel Post 200,000.00 0.00 2022-07-08 2022-07-29 2022-09-11 2022-10-11 2022-11-15 2023-05-14 cation Selection l ntation ity Builiding Program - design ected Fisheries consultant PROP-CS-FIRM17 / Kiribati Se Improving Seafood Toxicolog Consultant Qualifi Open - Internationa Pending Impleme afood Safety Scheme - consu IDA / D5570 y and Safety Measures in Sel Post 350,000.00 0.00 2022-06-15 2022-07-06 2022-08-19 2022-09-18 2022-10-23 2023-04-21 cation Selection l ntation ltant ected Fisheries PROP-CS-FIRM2 / Market Sta Strengthening Monitoring, C te & Catch Documentation As Consultant Qualifi Open - Internationa Pending Impleme IDA / D5570 ontrol and Surveillance of La Post 470,000.00 0.00 2021-07-01 2021-07-22 2021-09-04 2021-10-04 2021-11-08 2022-05-07 sessment (Assessing and res cation Selection l ntation rge-Scale Oceanic Fisheries ponding to market State requ irements) PROP-CS-FIRM5 / EM (install Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme ation, aministration and main IDA / D5570 ontrol and Surveillance of La Post 200,000.00 0.00 2023-08-07 2023-08-28 2023-10-11 2023-11-10 2023-12-15 2024-06-12 cation Selection l ntation tenance, data review training rge-Scale Oceanic Fisheries )- consultant PROP-CS-FIRM9 / VMS syste Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme ms maintenance and support IDA / D5570 ontrol and Surveillance of La Post 60,000.00 0.00 2024-06-03 2024-06-24 2024-08-07 2024-09-06 2024-10-11 2025-04-09 cation Selection l ntation traing rge-Scale Oceanic Fisheries PROP-CS-FIRM20 / Design an Improving Seafood Toxicolog Consultant Qualifi Open - Internationa Pending Impleme d Supervision consultant for t IDA / D5570 y and Safety Measures in Sel Post 250,000.00 0.00 2024-06-03 2024-06-24 2024-08-07 2024-09-06 2024-10-11 2025-04-09 cation Selection l ntation he Kiribati Seafood Safety La ected Fisheries boratory PROP-CS-FIRM18 / Design an Strengthening Monitoring, C Consultant Qualifi Open - Internationa Pending Impleme d Supervision of the Betio an IDA / D5570 ontrol and Surveillance of La Post 500,000.00 0.00 2022-07-01 2022-07-22 2022-09-04 2022-10-04 2022-11-08 2023-05-07 cation Selection l ntation d Kiritimati MCS facilities. rge-Scale Oceanic Fisheries KI-MFMRD-277859-CS-CQS / ToR for Policy Work and Conc Improving Seafood Toxicolog eptualizing Seafood Toxicolo Consultant Qualifi Open - Internationa Under Implement IDA / D5570 y and Safety Measures in Sel Post 245,000.00 0.00 2022-02-10 2022-03-15 2022-03-11 2022-04-04 2022-05-14 2022-06-01 2022-06-13 2022-07-18 2023-01-14 gy and Coastal Fisheries Lab cation Selection l ation ected Fisheries oratores | Financed under co mponent 3 subcomponents 3 .2 & 2.5 KI-MFMRD-309772-CS-CQS / Strengthening Monitoring, C Consultant Qualifi Open - Internationa Under Implement Combating IUU Review and U IDA / D5570 ontrol and Surveillance of La Post 30,000.00 0.00 2022-09-19 2022-09-27 2022-10-10 2022-12-07 2022-11-23 2022-12-23 2023-01-27 2023-07-26 cation Selection l ation pdate NPoA IUU rge-Scale Oceanic Fisheries KI-MFMRD-315301-CS-QCBS / Development of a lagoon an Improving Seafood Toxicolog Quality And Cost- Open - Internationa Under Implement d coastal fisheries pollution a IDA / D5570 y and Safety Measures in Sel Post 500,000.00 0.00 2022-09-19 2022-11-10 2022-10-10 2022-11-22 2022-11-23 2022-12-21 2023-01-20 2023-02-24 2023-03-31 2024-03-30 Based Selection l ation nd seafood toxin monitoring ected Fisheries and management plan. KI-MFMRD-328801-CS-QCBS / Preparation of a needs asse ssment for a CPPL Fisheries c Diversifying Marine-Based R Quality And Cost- Open - Internationa Under Implement entre on Kiritimati Island and IDA / D5570 evenue Streams for Outer Isl Post 390,000.00 0.00 2023-01-08 2023-03-01 2023-01-29 2023-05-21 2023-03-14 2023-04-11 2023-05-11 2023-06-15 2023-07-20 2024-07-19 Based Selection l ation economic assessment of the and Coastal Communities viability of developing sustai nable supply chains in the Li ne Islands. PROP-CS-FIRM3 / Transhipm Strengthening Monitoring, C ent Support implementation Consultant Qualifi Open - Internationa IDA / D5570 ontrol and Surveillance of La Post 70,000.00 0.00 Canceled 2022-01-03 2022-01-24 2022-03-09 2022-04-08 2022-05-13 2022-11-09 of the Transhipment Monitori cation Selection l rge-Scale Oceanic Fisheries ng Plan through the provision of equipment KI-MFMRD-354918-CS-QCBS Diversifying Marine-Based R Quality And Cost- Open - Internationa Under Implement / Establishment of a Marine S IDA / D5570 evenue Streams for Outer Isl Post 310,000.00 0.00 2023-04-05 2023-04-12 2023-04-26 2023-05-11 2023-06-09 2023-06-21 2023-07-07 2023-08-06 2023-09-10 2023-10-15 2024-10-14 Based Selection l ation patial Plan (MSP) for Tarawa. and Coastal Communities KI-MFMRD-317961-CS-QCBS / Preparation and Implement Diversifying Marine-Based R Quality And Cost- Open - Internationa Pending Impleme ation of Sustainable supply c IDA / D5570 evenue Streams for Outer Isl Post 500,000.00 0.00 2023-06-30 2023-07-21 2023-09-03 2023-10-01 2023-10-31 2023-12-05 2024-01-09 2025-01-08 Based Selection l ntation hain development plans for t and Coastal Communities argeted outer islands in the Gilbert Groups. Page 2 KI-MFMRD-309767-CS-CQS / Strengthening Monitoring, C Implementation of transship Consultant Qualifi Open - Internationa IDA / D5570 ontrol and Surveillance of La Post 400,000.00 0.00 Canceled 2022-09-19 2022-09-28 2022-10-10 2023-02-01 2022-11-23 2022-12-23 2023-01-27 2023-07-26 ment plan through the provis cation Selection l rge-Scale Oceanic Fisheries ion of equipment INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening Monitoring, C MFMRD-CS-IND-1 / Project M Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 47,234.00 43,600.00 Signed 2019-03-27 2019-05-01 2019-05-15 2019-04-25 2019-06-05 2019-04-29 2019-07-10 2020-05-01 2020-01-06 anager ant Selection rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-CS-IND-2 / POM Con Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 50,000.00 42,365.00 Completed 2019-03-27 2019-05-28 2019-05-15 2019-08-23 2019-06-05 2019-11-04 2019-07-10 2019-11-08 2020-01-06 2020-03-10 sultant ant Selection rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-CS-IND-3 / M&E Con Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 36,400.00 36,400.00 Signed 2019-03-27 2019-06-04 2019-05-15 2019-06-19 2019-06-05 2019-06-21 2019-07-10 2019-06-28 2020-01-06 sultant ant Selection rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-CS-IND-4 / MCS-Infor Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 70,000.00 57,450.00 Completed 2019-03-27 2019-06-04 2019-05-15 2019-09-19 2019-06-05 2019-10-15 2019-07-10 2019-10-16 2020-01-06 2019-12-18 mation System Specialist ant Selection rge-Scale Oceanic Fisheries MFMRD-CS-IND-5 / Project G Individual Consult Pending Impleme / Post Open 50,000.00 0.00 2019-03-27 2019-05-15 2019-06-05 2019-07-10 2020-01-06 ender Consultant ant Selection ntation Strengthening Monitoring, C MFMRD-CS-IND-6 / Small sca Individual Consult Under Implement / ontrol and Surveillance of La Post Open 46,000.00 0.00 2019-03-27 2019-08-23 2019-05-15 2019-06-05 2019-07-10 2020-01-06 le fisheries Scoping -Int ant Selection ation rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-CS-IND-7 / Small sca Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 14,000.00 10,000.00 Signed 2019-03-27 2019-08-23 2019-05-15 2019-10-21 2019-06-05 2019-11-04 2019-07-10 2019-11-05 2020-01-06 le fisheries Scoping -Nat ant Selection rge-Scale Oceanic Fisheries Strengthening Monitoring, C MFMRD-CS-IND-10 / Seafood Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 50,000.00 50,000.00 Completed 2019-03-27 2019-05-28 2019-05-15 2019-08-30 2019-06-05 2019-09-09 2019-07-10 2019-09-06 2020-01-06 2020-04-01 Toxicology Specialist ant Selection rge-Scale Oceanic Fisheries MFMRD-CS-IND-9 / Civil Wor Individual Consult / Post Open 75,000.00 0.00 Canceled 2019-03-27 2019-05-15 2019-06-05 2019-07-10 2020-01-06 ks Consultant-Design and Su ant Selection pervision KI-MFMRD-154029-CS-INDV / Strengthening Monitoring, C Individual Consult Pending Impleme Electronic monitoring cost re IDA / D5570 ontrol and Surveillance of La Post Open 30,000.00 0.00 2020-07-01 2020-08-19 2020-09-09 2020-10-07 2021-10-07 ant Selection ntation covery policy development rge-Scale Oceanic Fisheries KI-MFMRD-154030-CS-INDV / Strengthening Monitoring, C Individual Consult Pending Impleme Combating IUU Review and U IDA / D5570 ontrol and Surveillance of La Post Open 30,000.00 0.00 2022-07-01 2022-08-19 2022-09-09 2022-10-14 2023-04-12 ant Selection ntation pdate NPoA IUU rge-Scale Oceanic Fisheries KI-MFMRD-154272-CS-INDV / Improving Seafood Toxicolog Prepare draft legislation to i Individual Consult Pending Impleme / y and Safety Measures in Sel Post Open 200,000.00 0.00 2022-07-01 2022-12-01 2022-12-16 2023-01-13 2024-01-12 mplement the Kiribati Seafoo ant Selection ntation ected Fisheries d Safety Scheme and draft S eafood Safety Scheme KI-MFMRD-154281-CS-INDV / Delivering Effective Project Individual Consult IDA / D5570 Post Open 26,000.00 26,000.00 Terminated 2021-01-19 2021-03-02 2021-03-09 2021-05-25 2021-03-30 2021-07-05 2021-05-04 2021-07-06 2021-10-31 Finance Officer (PROP) Management ant Selection KI-MFMRD-154284-CS-INDV / Delivering Effective Project Individual Consult IDA / D5570 Post Open 36,400.00 36,400.00 Signed 2021-01-27 2020-07-31 2021-03-17 2020-09-01 2021-04-07 2020-09-14 2021-05-12 2020-09-15 2021-11-08 Gender Specialist Management ant Selection KI-MFMRD-154283-CS-INDV / Delivering Effective Project Individual Consult IDA / D5570 Post Open 26,000.00 26,000.00 Signed 2021-03-22 2021-03-18 2021-05-10 2021-05-21 2021-05-31 2021-05-21 2021-07-05 2021-05-25 2022-01-01 Operations Officer - Kiritimati Management ant Selection Island KI-MFMRD-154280-CS-INDV / Delivering Effective Project Individual Consult IDA / D5570 Post Open 26,000.00 26,000.00 Terminated 2021-03-03 2021-04-29 2021-04-21 2020-10-19 2021-05-12 2020-10-26 2021-06-16 2020-10-27 2021-12-13 Procurement Officer (PROP) Management ant Selection KI-MFMRD-157407-CS-INDV / Improving Seafood Toxicolog Individual Consult Pending Impleme Comprehensive Health Impac IDA / D5570 y and Safety Measures in Sel Post Open 150,000.00 0.00 2021-07-01 2021-08-19 2021-09-09 2021-10-14 2022-04-12 ant Selection ntation t Assessment - Proposed labo ected Fisheries ratory MFMRD-CS-IND-12 / National Strengthening Monitoring, C observer programme (Imple Individual Consult Pending Impleme IDA / D5570 ontrol and Surveillance of La Post Open 50,000.00 0.00 2021-07-01 2021-08-19 2021-09-09 2021-10-14 2022-04-12 ment Observer e-reporting fo ant Selection ntation rge-Scale Oceanic Fisheries r the domestic longline fleet) MFMRD-CS-IND-13 / National Strengthening Monitoring, C observer programme (Imple Individual Consult Pending Impleme IDA / D5570 ontrol and Surveillance of La Post Open 30,000.00 0.00 2022-07-18 2022-09-05 2022-09-26 2022-10-31 2023-04-29 ment Observer e-reporting fo ant Selection ntation rge-Scale Oceanic Fisheries r the domestic longline fleet) KI-MFMRD-154285-CS-INDV / Delivering Effective Project Individual Consult Safeguard and Communicati IDA / D5570 Post Open 36,400.00 36,400.00 Signed 2021-03-01 2021-05-11 2021-04-19 2021-05-12 2021-05-10 2021-05-12 2021-06-14 2021-05-11 2021-12-11 Management ant Selection on Specialist KI-MFMRD-225326-CS-CDS / Fisheries Specialist is needed Delivering Effective Project for the focus on the drafting IDA / D5570 Post Direct Selection Direct 25,000.00 25,000.00 Signed 2021-04-05 2021-04-14 2021-04-15 2021-04-15 2021-06-19 2021-04-21 2021-12-16 Management and finalization of certain To Rs on MSCs components. KI-MFMRD-262659-CS-QCBS Strengthening Monitoring, C / Legislation & Policy Review Individual Consult Under Implement IDA / D5570 ontrol and Surveillance of La Post Open 70,000.00 0.00 2021-11-26 2022-01-26 2022-02-05 2022-08-08 2022-02-26 2022-06-20 2022-04-02 2022-09-29 Expressionof Interest - comp ant Selection ation rge-Scale Oceanic Fisheries onent 1.1: State ofthe art MC S Facility Betio KI-MFMRD-262661-CS-CQS / Strengthening Monitoring, C Port State Measures Impleme Individual Consult Under Implement IDA / D5570 ontrol and Surveillance of La Post Open 60,000.00 0.00 2021-11-26 2021-12-09 2022-02-05 2022-02-26 2022-04-02 2022-09-29 ntation Support Consultancy ant Selection ation rge-Scale Oceanic Fisheries : Component 1 subcomponen t 1.4.5 Page 3 KI-MFMRD-262665-CS-CQS / ToR for Policy Work and Conc Improving Seafood Toxicolog eptualizing Seafood Toxicolo Individual Consult IDA / D5570 y and Safety Measures in Sel Post Open 245,000.00 0.00 Canceled 2021-11-26 2021-12-09 2022-02-15 2022-03-08 2022-04-12 2022-10-09 gy and Coastal Fishereies La ant Selection ected Fisheries boratories | Financed under c omponent 3 subcomponents 3.2 & 3.5 KI-MFMRD-290475-CS-CDS / Strengthening Monitoring, C Fisheries Specialist2 IDA / D5570 ontrol and Surveillance of La Post Direct Selection Direct 17,250.00 17,250.00 Signed 2022-04-19 2022-05-03 2022-04-29 2022-04-06 2022-05-09 2022-05-24 2022-06-09 . rge-Scale Oceanic Fisheries KI-MFMRD-290479-CS-CQS / Delivering Effective Project Individual Consult IDA / D5570 Post Open 26,000.00 26,000.00 Signed 2022-04-28 2022-02-18 2022-06-16 2022-04-14 2022-07-07 2022-04-14 2022-08-11 2022-04-26 2023-02-07 Procurement Officer Management ant Selection KI-MFMRD-154271-CS-INDV / Diversifying Marine-Based R Individual Consult CPPL Building Study & Supply IDA / D5570 evenue Streams for Outer Isl Post Open 390,000.00 0.00 Canceled 2022-04-08 2022-06-03 2022-06-24 2022-07-25 2023-07-15 ant Selection Chain in the Line Islands and Coastal Communities KI-MFMRD-328800-CS-INDV / Diversifying Marine-Based R Individual Consult Open - Internationa CPPL Building study in Kiritim IDA / D5570 evenue Streams for Outer Isl Post 70,000.00 0.00 Canceled 2023-01-08 2023-02-26 2023-03-19 2023-04-23 2023-10-20 ant Selection l ati Island. and Coastal Communities KI-MFMRD-339187-CS-INDV / Delivering Effective Project Individual Consult Under Implement IDA / D5570 Post Open - National 26,000.00 0.00 2023-01-30 2023-01-06 2023-03-20 2023-03-09 2023-04-10 2023-02-08 2023-05-15 2023-11-11 PROP Finance Officer Management ant Selection ation KI-MFMRD-339186-CS-INDV / Delivering Effective Project Individual Consult Under Implement IDA / D5570 Post Open - National 36,400.00 0.00 2023-01-30 2023-03-01 2023-03-20 2023-01-12 2023-04-10 2023-05-15 2023-11-11 PROP Gender Specialist Management ant Selection ation KI-MFMRD-346446-CS-INDV / Delivering Effective Project Individual Consult Under Implement PROP Safeguard and Commu IDA / D5570 Post Open - National 36,400.00 0.00 2023-03-01 2023-03-01 2023-04-19 2023-03-23 2023-05-10 2023-03-27 2023-06-14 2023-12-11 Management ant Selection ation nication Specialist Strengthening Monitoring, C KI-MFMRD-362570-CS-CDS / Direct - Internation Under Implement IDA / D5570 ontrol and Surveillance of La Post Direct Selection 25,000.00 0.00 2023-04-28 2023-05-19 2023-05-08 2023-05-09 2023-07-12 2024-01-08 PROP Fisheries Specialist al ation rge-Scale Oceanic Fisheries MFMRD-CS-IND-8 / Solar Salt Diversifying Marine-Based R Individual Consult Pending Impleme Rapid Assessment - Beru Nik IDA / D5570 evenue Streams for Outer Isl Post Open - National 48,000.00 0.00 2023-07-03 2023-08-21 2023-09-11 2023-10-16 2024-04-13 ant Selection ntation u and Coastal Communities KI-MFMRD-366617-CS-INDV / Strengthening Monitoring, C Individual Consult Open - Internationa Pending Impleme Technical advisor for tranship IDA / D5570 ontrol and Surveillance of La Post 40,000.00 0.00 2023-06-30 2023-08-18 2023-09-08 2023-10-13 2024-04-10 ant Selection l ntation ment monitoring support rge-Scale Oceanic Fisheries KI-MFMRD-262660-CS-CQS / Electronic Reporting (e-repor ting) Policy,Capacity Building Strengthening Monitoring, C , Implementation support an Individual Consult IDA / D5570 ontrol and Surveillance of La Post Open 60,000.00 0.00 Canceled 2021-11-26 2021-12-09 2022-02-05 2022-02-26 2022-04-02 2022-09-29 d training : Component 1 sub ant Selection rge-Scale Oceanic Fisheries components 1.1 & 1.2 | Finan ced under component 1.1.3 a nd 1.2.3 for year 1 operation al budget total is halve KI-MFMRD-262662-CS-CQS / Consultant on Electronic Mon itoring Policy, Capacity Buiildi Strengthening Monitoring, C Individual Consult ng, Implementation Support IDA / D5570 ontrol and Surveillance of La Post Open 60,000.00 0.00 Canceled 2021-11-26 2021-12-08 2022-02-05 2022-02-26 2022-04-02 2022-09-29 ant Selection and Training | Financed unde rge-Scale Oceanic Fisheries r component 1.1.3 and 1.2.3 where year 1 operational bud get is halve. KI-MFMRD-262663-CS-CQS / Observer de-briefer and train Strengthening Monitoring, C Individual Consult er training consultant | Finan IDA / D5570 ontrol and Surveillance of La Post Open 30,000.00 0.00 Canceled 2021-11-26 2021-12-08 2022-02-05 2022-02-26 2022-04-02 2022-09-29 ant Selection ced under component 1.4.9 f rge-Scale Oceanic Fisheries or year 1 operational year Page 4 PROCUREMENT PLANS (Textual Part) Information on the Projects: Ukraine Emergency COVID-19 Response Vaccination Project, P175895 Additional financing to Ukraine Emergency COVID-19 Response Vaccination Project, P177894 Project Implementation agency: Ministry of Health of Ukraine Date of the Procurement Plans: September and December 2021 Period covered by these Procurement Plans: September 2021 - March 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers”, dated November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Projects. This textual part along with the Procurement Plans tables in STEP constitute the Procurement Plans for the Projects. The following conditions apply to all procurement activities in the Procurement Plans. The other elements of the Procurement Plans as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Law of Ukraine "On Public Procurement" № 922-VIII dated December 25, 2015 and introduced by Law of Ukraine № 114-IX dated September 19, 2019 (with changes), such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements (other than national open competitive procurement arrangements) are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Works: is applicable for those contracts identified in the Procurement Plan tables. Other Relevant Procurement Information. Procurement for COVID-19 Vaccines and logistic services under Subcomponent 1.1 (COVID-19 Vaccination Support) of the Part 1 of the Projects (Strengthen Public Health System) will be carried out through retroactive financing. Procurement under Part 2 of the Projects (Support Service Delivery) will be carried out in accordance with the Loan Agreement, the Operations Manual, the Vaccines Delivery and Distribution Manual, the Anti-Corruption Guidelines and the Environmental and Social Commitment Plan. PROCUREMENT Ukraine : Ukraine Emergency COVID-19 Response and Vaccination Project PLAN General Information Country: Ukraine 2021-09-20 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P175895 GPN Date: 2022-03-11 Project Name: Ukraine Emergency COVID-19 Response and Vaccination Project Loan / Credit No: IBRD / 92500, IBRD / 93150, IBRD / 93690 Ministry of Health of Ukraine Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RF-1.1.1 / COVID-19 vaccine Strengthen public health sys Under Imple IBRD / 92500 Prior Direct Selection Direct 0.00 2021-09-30 2021-09-21 2021-10-05 2021-09-21 2021-11-09 2022-05-08 s and logistics tem mentation UN-1.2.1 / COVID-19 Antigen Strengthen public health sys IBRD / 92500 Prior Direct Selection Direct 0.00 Canceled 2021-10-05 2021-10-15 2021-11-19 2022-11-14 -based Rapid Diagnostic Test tem s UN-1.1.2 / Cold chain equip Strengthen public health sys IBRD / 92500 Prior Direct Selection Direct 14,723,388.09 Signed 2021-12-13 2021-12-09 2021-12-18 2021-12-13 2022-01-17 2022-01-01 2023-01-12 ment for COVID-19 vaccine st tem orage AF/RF-1.1.1 / COVID-19 vacci IBRD / 93150 Strengthen public health sys Prior Direct Selection Direct 105,007,763.00 Signed 2021-12-16 2021-12-16 2021-12-17 2021-12-16 2021-12-20 2021-05-01 2022-03-30 nes tem AF/RF-1.1.2 / COVID-19 vacci IBRD / 93150 Strengthen public health sys Prior Direct Selection Direct 14,992,237.50 Signed 2022-02-27 2022-02-26 2022-02-28 2022-02-26 2022-03-03 2021-06-09 2022-05-12 nes tem AF2/RF-1.1.1 / COVID-19 vac IBRD / 93690 Strengthen public health sys Prior Direct Selection Direct 91,163,261.00 Signed 2022-03-11 2022-03-12 2022-03-12 2022-03-12 2022-03-15 2021-06-09 2022-05-24 cines tem DS-1.1.7 / Procurement of m Strengthen public health sys IBRD / 92500 Post Direct Selection Direct 0.00 Signed 2022-07-13 2022-06-24 2022-07-20 2022-07-11 2022-08-10 2022-11-08 edical waste containers tem AF/RFQ-1.1.8 / Procurement Strengthen public health sys Request for Quota Single Stage - One E IBRD / 93150 Post Open - National 0.00 Signed 2022-08-17 2022-09-21 2022-11-20 of computer equipment tem tions nvelope RFB-1.1.2/1 / Procurement of Strengthen public health sys Single Stage - One E vehicles with refrigerators for IBRD / 92500 Post Request for Bids Open - National 0.00 Canceled 2022-09-05 2022-09-10 2022-10-22 2022-11-05 2022-12-10 2023-03-31 tem nvelope SOE "Ukrvaktsina" AF/RFQ-1.1.10 / Procuremen Strengthen public health sys Request for Quota Single Stage - One E t of computer equipment for IBRD / 93150 Post Open - National 0.00 Signed 2022-08-29 2022-10-03 2023-01-01 tem tions nvelope regional offices of MOH's Pub lic Health Center RFB-1.1.9 / Equipment for m Strengthen public health sys Open - Internationa Single Stage - One E Under Imple IBRD / 93150 Prior Request for Bids 0.00 2022-12-31 2023-02-08 2023-01-14 2023-05-13 2023-02-28 2023-05-16 2023-03-14 2023-04-04 2023-10-01 edical waste decontaminatio tem l nvelope mentation n RFQ-1.1.5/7 / Procurement a Strengthen public health sys Request for Quota Single Stage - One E Under Imple IBRD / 92500 Post Open - National 0.00 2022-10-02 2022-11-09 2023-02-07 nd installation of RAM tem tions nvelope mentation RFQ-1.1.15 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E Pending Impl Electronic Document Manage IBRD / 93150 Post Open - National 0.00 2023-01-10 2023-02-08 2023-04-09 tem tions nvelope ementation ment System RFQ-1.1.16 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E Under Imple IBRD / 93150 Post Open - National 0.00 2023-01-10 2023-02-08 2023-05-09 Uninterruptible Power Supply tem tions nvelope mentation RFQ-1.1.17 / Implementation Strengthen public health sys Request for Quota Single Stage - One E Pending Impl IBRD / 93150 Post Open - National 0.00 2023-01-17 2023-03-15 2024-02-08 of Controlled and Segmented tem tions nvelope ementation Network RFQ-1.1.19 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E IBRD / 93150 Post Open - National 0.00 Canceled 2023-01-17 2023-02-22 2023-04-23 Computer Equipment tem tions nvelope DS-1.1.18 / Procurement of Strengthen public health sys Direct - Internation IBRD / 92500 Prior Direct Selection 0.00 Signed 2022-12-28 2023-01-07 2022-12-28 2023-01-09 2023-01-05 2023-03-06 2024-01-05 backup power generators tem al RFQ-1.1.2/1 / Procurement o Strengthen public health sys Request for Quota Single Stage - One E Under Imple f vehicles with refrigerators f IBRD / 92500 Post Open - National 0.00 2023-04-08 2023-06-03 2023-11-30 tem tions nvelope mentation or SOE "Ukrvaktsina" DS-1.2.3 / Supply of Comput Strengthen public health sys Direct - Internation IBRD / 93150 Prior Direct Selection 0.00 Signed 2023-04-25 2023-05-09 2023-04-25 2023-05-17 2023-05-12 2023-06-26 2023-10-27 er Tomography Scanners tem al DS-1.1.2/1 / Supply of Sinov Strengthen public health sys Direct - Internation IBRD / 92500 Post Direct Selection 0.00 Canceled 2023-05-01 2023-05-01 2023-05-14 2023-07-13 enture Goods tem al DS-1.2.2/2 / Supply of Mehec Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-05-18 2023-05-18 2023-05-31 2023-07-30 o Goods tem al ementation DS-1.2.2/1 / Supply of Sinov Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-05-18 2023-05-18 2023-05-31 2023-07-30 enture Goods tem al ementation DS-1.2.2/3 / Supply of Sinop Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-05-25 2023-05-25 2023-06-07 2023-10-25 harm Goods tem al ementation RFQ-1.1.5/11 / Purchase of A Strengthen public health sys Request for Quota Single Stage - One E Pending Impl IBRD / 92500 Post Open - National 0.00 2023-07-06 2023-08-10 2023-10-09 tlassian software products tem tions nvelope ementation DS-1.2.2/4 / Supply of Therm Strengthen public health sys Direct - Internation Pending Impl IBRD / 92500 Post Direct Selection 0.00 2023-06-23 2023-06-23 2023-07-06 2024-01-02 o Fisher Scientific Goods and tem al ementation Services NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AF/DS-1.1.7 / Services of the National Contact Center for C Strengthen public health sys IBRD / 93150 Post Direct Selection Direct 701,207.15 Signed 2022-04-02 2022-04-11 2022-04-05 2022-04-11 2022-04-09 2022-05-01 2023-03-31 OVID-19 Counteraction and S tem upport during Martial Law RFQ-1.1.8/1 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Zak arpats’ka oblast’ RFQ-1.1.8/2 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Lviv s’ka oblast’ RFQ-1.1.8/3 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Ivan o-Frankivs’ka oblast’ RFQ-1.1.8/4 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Tern opils’ka oblast’ RFQ-1.1.8/5 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Cher nivets’ka oblast’ RFQ-1.1.8/6 / Services of tra nsportation and thermal disp Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-06-13 2022-07-31 2023-02-28 osal of epidemiologically haz tem tions nvelope ardous medical waste in Vinn yts’ka oblast’ RFQ-1.1.5/6 / Development of the module “Procurement, Strengthen public health sys Request for Quota Single Stage - One E IBRD / 92500 Post Open - National 0.00 Canceled 2022-09-23 2022-11-04 2023-06-02 services and basic configurat tem tions nvelope ion” of the eStock system RFQ-1.1.11 / Procurement of Strengthen public health sys Request for Quota Single Stage - One E MIS cyber vulnerabilities acc IBRD / 93150 Post Open - National 0.00 Signed 2022-10-12 2022-11-23 2023-01-22 tem tions nvelope essment software DS-1.1.5/8 / Implementation Strengthen public health sys Under Imple of SAP Ariba Contracts Mana IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-11-20 2022-11-28 2022-11-25 2022-12-13 2023-03-14 tem mentation gement module RFQ-1.1.5/5 / MOH of Ukrain Strengthen public health sys Request for Quota Single Stage - One E Under Imple IBRD / 92500 Post Open - National 0.00 2022-10-20 2022-12-15 2023-04-14 e web portal development se tem tions nvelope mentation rvices DS-1.1.20 / Transport servic Under Imple es for the delivery of equipm IBRD / 92500 Support service delivery Post Direct Selection Direct - National 0.00 2023-05-24 2023-05-12 2023-05-29 2023-05-30 2023-06-03 2023-12-31 mentation ent in Ukraine CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CQS-1.1.6 / Support to COVI Strengthen public health sys Consultant Qualifi D-19 vaccination communica IBRD / 92500 Post Open - National 0.00 Canceled 2022-01-23 2022-02-13 2022-03-13 2022-03-27 2022-04-24 2023-03-20 tem cation Selection tion campaign CQS-1.1.5/1 / Development of the module “Procurement, Strengthen public health sys Consultant Qualifi IBRD / 92500 Post Open - National 0.00 Canceled 2022-05-18 2022-06-10 2022-06-08 2022-07-13 2022-07-27 2022-08-17 2023-04-14 services and basic configurat tem cation Selection ion” of the eStock system CQS-1.1.5/2 / Optimization o Strengthen public health sys Consultant Qualifi Under Implement IBRD / 92500 Post Open - National 0.00 2022-06-15 2022-08-31 2022-07-06 2022-08-03 2022-08-10 2022-08-24 2023-03-22 f the Electronic Health Care S tem cation Selection ation ystem CQS-1.1.5/3 / Increasing the Strengthen public health sys Consultant Qualifi Under Implement capacity of the patient notific IBRD / 92500 Post Open - National 0.00 2022-06-30 2022-07-28 2022-07-21 2022-08-11 2022-08-18 2022-09-01 2022-11-30 tem cation Selection ation ation in the Electronic Health Care System CQS-1.1.5/4 / Development of a component of the format Strengthen public health sys Consultant Qualifi IBRD / 92500 Post Open - National 0.00 Under Review 2022-08-31 2022-09-27 2022-09-21 2022-10-12 2022-10-19 2022-11-02 2023-03-31 ion of COVID-certificates with tem cation Selection in the Electronic Health Care System AF/QCBS-1.1.12 / Developm Strengthen public health sys Quality And Cost- Under Implement ent of specific modules of the IBRD / 93150 Post Open - National 0.00 2022-11-22 2022-11-21 2022-12-13 2023-01-03 2023-01-31 2023-02-14 2023-03-21 2023-04-25 2023-12-21 tem Based Selection ation eStock System CQS-1.1.5/9 / Doctors` and p Strengthen public health sys Consultant Qualifi atients` login separation in t IBRD / 92500 Post Open - National 0.00 Signed 2022-12-15 2022-12-19 2023-01-05 2023-01-26 2023-03-02 2023-02-02 2023-05-16 2023-02-16 2023-06-16 tem cation Selection he eHealth CDB CQS-1.1.5/10 / Study of the Strengthen public health sys Consultant Qualifi Under Implement asynchronous data transmiss IBRD / 92500 Post Open - National 0.00 2023-01-12 2023-01-12 2023-01-26 2023-02-08 2023-03-01 2023-03-05 2023-09-01 tem cation Selection ation ion model in the eHealth CQS-1.1.18 / Development o f the new software for the es sence "Sample of biomaterial Strengthen public health sys Consultant Qualifi Under Implement IBRD / 93150 Post Open - National 0.00 2022-12-30 2023-01-12 2023-01-13 2023-01-30 2023-02-20 2023-02-24 2023-05-25 " accounting functionality alo tem cation Selection ation ng with modification of the e xisting software in the eHealt h CDB CQS-1.1.14 / Preparation of t he Terms of reference for the Strengthen public health sys Consultant Qualifi Under Implement IBRD / 93150 Post Open - National 0.00 2023-01-16 2023-03-08 2023-01-30 2023-02-16 2023-03-09 2023-03-13 2023-08-10 development of a Register of tem cation Selection ation human resources in healthca re Page 2 CQS-1.1.20 / Improvement o Strengthen public health sys Consultant Qualifi Under Implement f epidemiological surveillanc IBRD / 93150 Post Open - National 0.00 2022-12-23 2022-12-07 2023-01-13 2023-02-03 2023-02-10 2023-02-13 2023-08-12 tem cation Selection ation e processes 1.1.4/1 / Trainings on medic Strengthen public health sys Consultant Qualifi Under Implement IBRD / 92500 Post Open - National 0.00 2023-02-01 2023-01-27 2023-02-15 2023-02-28 2023-03-21 2023-03-25 2024-03-24 al waste management tem cation Selection ation CQS-1.1.21 / Development o f the new software for the es Strengthen public health sys Consultant Qualifi Under Implement sence "Care Team" accountin IBRD / 93150 Post Open - National 0.00 2023-03-12 2023-05-12 2023-03-26 2023-04-12 2023-05-03 2023-05-07 2023-09-19 tem cation Selection ation g functionality along with mo dification of the existing soft ware in the eHealth CDB INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DS-1.1.9 / Consultant for exp Strengthen public health sys ert support of vaccination ag IBRD / 92500 Post Direct Selection Direct - National 20,943.64 Signed 2022-07-20 2022-07-01 2022-07-30 2022-08-08 2022-08-10 2022-08-26 2023-03-31 tem ainst COVID-19 DS-1.1.10 / Consultant for P Strengthen public health sys Under Implement IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-08-25 2022-09-06 2022-08-30 2022-10-01 2023-03-31 ublic Health tem ation DS-1.1.11 / Immunoprophyla Strengthen public health sys Under Implement IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-08-25 2022-09-06 2022-08-30 2022-10-01 2023-03-31 xis Consultant tem ation DS-1.1.12 / Сonsultant on inf Strengthen public health sys Under Implement ormation and technical issue IBRD / 92500 Post Direct Selection Direct - National 0.00 2022-08-25 2022-09-06 2022-08-30 2022-10-01 2023-03-31 tem ation s and software IC-1.1.13 / Information Tech Strengthen public health sys Individual Consult IBRD / 92500 Post Open - National 0.00 Signed 2022-09-21 2022-09-27 2022-10-07 2022-11-12 2022-10-14 2022-11-15 2022-10-24 2023-04-22 nology Consultant tem ant Selection IC-1.1.14 / Consultancy Supp Individual Consult Pending Impleme ort to the Ministry of Health o IBRD / 92500 Support service delivery Post Open - National 0.00 2022-09-25 2022-10-11 2022-10-18 2022-10-28 2023-03-31 ant Selection ntation f Ukraine to Receive Addition al Financing DS-1.1.15 / Regional Coordin Under Implement IBRD / 92500 Support service delivery Post Direct Selection Direct - National 0.00 2022-09-18 2022-09-16 2022-09-23 2022-10-01 2023-03-31 ation Consultant ation IC-1.1.17 / Consultant for vis Strengthen public health sys Individual Consult ual accompaniment of the co IBRD / 92500 Post Open - National 0.00 Signed 2022-10-03 2022-09-27 2022-10-19 2022-10-28 2022-10-26 2022-11-03 2022-11-05 2023-05-04 tem ant Selection mmunication support for refo rms IC-1.1.16 / Medical Waste M Strengthen public health sys Individual Consult IBRD / 92500 Post Open - National 0.00 Signed 2022-09-30 2022-09-27 2022-10-22 2022-11-14 2022-10-29 2022-11-14 2022-11-06 2023-03-31 anagement Consultant tem ant Selection DS-1.1.21 / Audit of NHSU b udget reports under 9110-UA Strengthen public health sys Under Implement IBRD / 92500 Post Direct Selection Direct - National 0.00 2023-05-31 2023-06-19 2023-06-06 2023-06-30 2024-06-29 and 9250-UA Projects (2020, tem ation 2021 and 2022) and 9369-U A Project audit (2022) Page 3 Proyecto de Gestión Integral de los Riesgos en el Sistema Agroindustrial Rural (GIRSAR) Monto – USD150 MILLONES PROCUREMENT Argentina : Integrated Risk Management in the Rural Agroindustrial System PLAN General Information Country: Argentina 2019-03-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162316 GPN Date: Project Name: Integrated Risk Management in the Rural Agroindustrial System Loan / Credit No: IBRD / 88670 Rural Change Unit - Ministry of Agriculture Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned AR-UCAR-216690-CW-RFB / Subproyecto "Reacondiciona Component 2 - Agricultural r Single Stage - One E Under Imple 2022-02-1 IBRD / 88670 Post Request for Bids Open - National 340,028.00 0.00 2021-05-03 2023-01-23 2021-05-08 2021-06-19 2021-07-19 2021-08-23 miento y Mejora del Sistema isk mitigation investments nvelope mentation 9 de Riego de Buta Ranquil". N euquén AR-UCAR-186648-CW-RFB / Subproyecto "Acueducto Gan Component 2 - Agricultural r Single Stage - One E 7,662,149.7 2021-06-1 IBRD / 88670 Post Request for Bids Open - National 5,848,818.00 Signed 2020-08-24 2021-12-29 2020-09-01 2020-10-13 2022-02-24 2020-11-10 2022-04-29 2020-12-15 2022-06-04 adero La Providencia, La Ra isk mitigation investments nvelope 8 5 mada y Santa Ana" - Provinci a de Córdoba AR-UCAR-216712-CW-RFB / Subproyecto "Readecuación Component 2 - Agricultural r Single Stage - One E 2022-05-2 IBRD / 88670 Post Request for Bids Open - National 5,800,000.00 0.00 Signed 2021-08-02 2021-11-17 2021-08-07 2021-09-18 2021-12-17 2021-10-18 2022-04-21 2021-11-22 de Los sistemas de Riego sup isk mitigation investments nvelope 1 erficiales de San Blas de Los Sauces". La Rioja. AR-UCAR-216700-CW-RFB / Subproyecto "Fortalecimient National Procure o de la Cadena Productiva de ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2022-06-2 Pequeños Productores Hortíc IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 2,470,146.00 0.00 2021-09-06 2021-09-11 2021-10-23 2021-11-22 2021-12-27 isk mitigation investments nvelope lementation 5 olas y Florícolas"- Construcci ss (Non Bank-SPD ón de invernaderos y mejora ) de la comercialización. Provi ncia de Jujuy. AR-UCAR-186653-CW-RFB / Subproyecto "Rehabilitación National Procure de la dinámica hidráulica del ment Document - Component 2 - Agricultural r Single Stage - One E 6,762,382.4 2022-02-1 subsistema de la Cuenca del IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 9,726,000.00 Signed 2021-05-03 2021-06-23 2021-05-03 2021-06-14 2021-09-06 2021-07-12 2021-12-17 2021-08-16 2022-06-03 isk mitigation investments nvelope 0 4 Arroyo Baí" - Readecuación ss (Non Bank-SPD de los escurrimientos de la C ) uenca del Arroyo Baí - Provin cia de Corrientes AR-UCAR-216698-CW-RFB / National Procure Subproyecto "Desarrollo Gan ment Document - adero de la Provincia de Jujuy Component 2 - Agricultural r Single Stage - One E Pending Imp 2022-05-2 IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 2,700,000.00 0.00 2021-08-02 2021-08-07 2021-09-18 2021-10-18 2021-11-22 (Etapa I)". Mejoramiento en l isk mitigation investments nvelope lementation 1 ss (Non Bank-SPD os sistemas productivos y la ) generación de nueva estruct ura de faena . Provincia de Ju juy. AR-UCAR-216714-CW-RFB / Subproyecto "Rehabilitación National Procure de la dinámica hídrica de la c ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2022-05-2 uenca alta del Riachuelo: sub IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 3,100,000.00 0.00 2021-08-02 2021-08-07 2021-09-18 2021-10-18 2021-11-22 isk mitigation investments nvelope lementation 1 sistema de La Palmira" -Cons ss (Non Bank-SPD trucción de un sistema de ve ) rtedero de excedentes hídric os . Provincia de Corrientes. AR-UCAR-253366-CW-RFQ / Mitigación de los Impactos pr oducidos sobre los humedale Request for Quota Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Imp 2022-05-2 s por la deficiencia del escurr IBRD / 88670 Post Open - National tions (Non Bank-S 16,475.00 0.00 2021-10-02 2021-11-27 isk mitigation investments tions nvelope lementation 6 imiento en canales existente PD) s sobre el Estero Las Maloyas – Zona Alcantarillas sobre RP N° 5 AR-UCAR-216686-CW-RFB / Subproyecto "Fortalecimient Component 2 - Agricultural r Single Stage - One E 2022-02-1 IBRD / 88670 Post Request for Bids Open - National 832,160.00 0.00 Canceled 2021-05-03 2021-05-08 2021-06-19 2021-07-19 2021-08-23 o Sanitario del rodeo bovino isk mitigation investments nvelope 9 provincial". Neuquén AR-UCAR-286857-CW-RFB / Licitación de obra de reacond National Procure icionamiento y mejora de sist ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-02-1 ema de riego en el marco del IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 114,270.00 0.00 2022-05-02 2022-05-07 2022-06-18 2022-07-18 2022-08-22 isk mitigation investments nvelope lementation 8 subproyecto "Reacondiciona ss (Non Bank-SPD miento y Mejora del Sistema ) de Riego de Buta Ranquil" de la provincia del Neuquén National Procure AR-UCAR-216721-CW-RFB / ment Document - Component 2 - Agricultural r Single Stage - One E 2022-06-2 Subproyecto "Mejora de la re IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 2,955,039.00 0.00 Signed 2021-09-06 2022-05-27 2021-09-11 2021-10-23 2022-08-11 2021-11-22 2022-10-24 2021-12-27 isk mitigation investments nvelope 5 d de riego del Valle de Jáchal ss (Non Bank-SPD ". San Juan. ) AR-UCAR-296239-CW-RFB / National Procure Obra civil en el marco del Su ment Document - bproyecto MODERNIZACIÓN Component 2 - Agricultural r Single Stage - One E 10,608,695.0 Under Imple 2023-03-0 IBRD / 88670 Prior Request for Bids Open - National 1 Envelope proce 0.00 2022-05-20 2023-06-01 2022-05-25 2022-07-06 2023-05-11 2022-08-05 2023-06-28 2022-09-09 DEL SISTEMA DE RIEGO RAM isk mitigation investments nvelope 0 mentation 8 ss (Non Bank-SPD A CHIMBA RÍO TUNUYÁN INFE ) RIOR - Provincia de Mendoza AR-UCAR-216723-CW-RFB / Subproyecto "Sistema Provin Component 2 - Agricultural r Single Stage - One E 2022-06-2 IBRD / 88670 Post Request for Bids Open - National 335,000.00 0.00 Canceled 2021-09-06 2021-09-11 2021-10-23 2021-11-22 2021-12-27 cial de Información Para La G isk mitigation investments nvelope 5 estión del Riesgo Agrario". N euquén. National Procure AR-UCAR-305998-CW-RFB / ment Document - Obra correspondiente al sub Component 2 - Agricultural r Single Stage - One E 2023-05-2 IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 5,287,315.00 0.00 Canceled 2022-08-01 2023-03-02 2022-08-06 2022-09-17 2023-03-30 2022-10-17 2023-04-24 2022-11-21 proyecto "Nueva Nave de Pro isk mitigation investments nvelope 0 ss (Non Bank-SPD ductores Mercado Concentra ) dor de Neuquén" AR-UCAR-311331-CW-RFB / National Procure Obra civil en el marco del Su ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-06-2 bproyecto "Modernización y IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 3,510,607.00 0.00 2022-09-05 2022-09-10 2022-10-22 2022-11-21 2022-12-26 isk mitigation investments nvelope lementation 4 mejoras en el sistema de rieg ss (Non Bank-SPD o del Valle de Viedma" - Prov ) incia de Río Negro Page 1 AR-UCAR-311370-CW-RFB / National Procure Obra en el marco del Subpro ment Document - yecto "Reacondicionamiento Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-07-0 IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 2,859,000.00 0.00 2022-09-12 2022-09-17 2022-10-29 2022-11-28 2023-01-02 de los “prestamos” de la red isk mitigation investments nvelope lementation 1 ss (Non Bank-SPD vial provincial para el control ) de incendios forestales en la provincia de La Pampa" National Procure AR-UCAR-186659-CW-RFB / ment Document - Obras en el marco del Subpr Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-07-0 IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 5,000,150.20 0.00 2022-09-09 2022-09-19 2022-10-31 2022-11-28 2023-01-02 oyecto "Prevención y control isk mitigation investments nvelope lementation 3 ss (Non Bank-SPD de incendios forestales de la ) Provincia de Mendoza" AR-UCAR-329253-CW-RFB / National Procure Obras en el marco del Subpr ment Document - oyecto "Sistema Integral de Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-09-3 IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 4,219,000.00 0.00 2022-12-12 2022-12-17 2023-01-28 2023-02-27 2023-04-03 Mitigación, Prevención y Mon isk mitigation investments nvelope lementation 0 ss (Non Bank-SPD itoreo de incendios en las sie ) rras" de la provincia de Córd oba AR-UCAR-334580-CW-RFB / Licitación de obra de reacond National Procure icionamiento y mejora de sist ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2023-10-2 ema de riego en el marco del IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 281,100.00 0.00 2023-01-06 2023-01-11 2023-02-22 2023-03-24 2023-04-28 isk mitigation investments nvelope lementation 5 subproyecto "Reacondiciona ss (Non Bank-SPD miento y Mejora del Sistema ) de Riego de Buta Ranquil" de la provincia del Neuquén AR-UCAR-349299-CW-RFB / National Procure Licitación de obra en el marc ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2024-01-0 o del subproyecto "Readecua IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 4,800,000.00 0.00 2023-03-20 2023-03-25 2023-05-06 2023-06-05 2023-07-10 isk mitigation investments nvelope lementation 6 ción de Los sistemas de Rieg ss (Non Bank-SPD o superficiales Nonogasta, La ) Rioja - Etapa 1" AR-UCAR-216705-CW-RFB / National Procure Obra correspondiente al Sub ment Document - Component 2 - Agricultural r Single Stage - One E 15,882,287.5 Under Imple 2023-05-2 proyecto "Readecuación de c IBRD / 88670 Prior Request for Bids Open - National 1 Envelope proce 0.00 2022-08-05 2023-06-13 2022-08-10 2022-09-21 2023-06-26 2022-10-21 2022-11-25 isk mitigation investments nvelope 0 mentation 6 aminos rurales: RP S/N Tram ss (Non Bank-SPD o RPN 32 (Seguí) – RPN 34". ) Entre Ríos AR-UCAR-366791-CW-RFB / Obra civil en el marco del su National Procure bproyecto "Optimización de l ment Document - Component 2 - Agricultural r Single Stage - One E Pending Imp 2024-11-1 a Infraestructura de Riego de IBRD / 88670 Post Request for Bids Open - National 1 Envelope proce 8,500,000.00 0.00 2023-06-16 2023-06-23 2023-08-04 2023-09-03 2023-10-08 isk mitigation investments nvelope lementation 1 l Valle Bonaerense del Río Co ss (Non Bank-SPD lorado, revestimiento de Can ) ales" de la provincia de Buen os Aires AR-UCAR-311335-CW-RFB / Obra civil en el marco del su National Procure bproyecto "Optimización de l ment Document - Component 2 - Agricultural r Single Stage - One E 10,241,917.0 2023-07-0 a Infraestructura de Riego de IBRD / 88670 Prior Request for Bids Open - National 1 Envelope proce 0.00 Canceled 2022-09-19 2022-09-24 2022-11-05 2022-12-05 2023-01-09 isk mitigation investments nvelope 0 8 l Valle Bonaerense del Río Co ss (Non Bank-SPD lorado, revestimiento de Can ) ales" de la provincia de Buen os Aires GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UCAR-94920-GO-DIR / Pl Component 1 - Strengthenin ataforma de Integración, Vali IBRD / 88670 g agro-climatic information s Prior Direct Selection Direct 1,800,000.00 1,509,027.90 Signed 2019-04-15 2019-09-02 2019-04-20 2019-09-03 2019-05-25 2019-09-26 2021-05-14 dación y publicación de Infor ystems mación Agrometeorológica AR-UCAR-94928-GO-RFB / A Component 1 - Strengthenin dquisición de instrumentos y Open - Internationa Single Stage - One E IBRD / 88670 g agro-climatic information s Post Request for Bids 240,000.00 0.00 Canceled 2019-05-15 2019-05-20 2019-07-01 2019-07-31 2019-09-04 2020-03-02 emplazamiento de estacione l nvelope ystems s meteorológicas AR-UCAR-94931-GO-RFB / A dquisición y Actualización Te Component 1 - Strengthenin Single Stage - One E cnológica (Hardware - Softwa IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 150,000.00 141,313.05 Signed 2020-09-10 2021-02-12 2020-09-17 2020-10-29 2021-06-23 2020-11-26 2021-11-15 2020-12-31 2021-12-31 2021-07-01 nvelope re) para Puesta en Producció ystems n. Convenio MFI - SMN - MAG yP AR-UCAR-216754-GO-RFB / Convenio MAGyP - INTA - Adq Component 1 - Strengthenin Single Stage - One E Pending Impl uisición de equipamiento Info IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 110,000.00 0.00 2021-05-03 2021-05-08 2021-06-19 2021-07-19 2021-08-23 2022-02-19 nvelope ementation rmatico Sistema Back up / st ystems orage / procesamiento (Hard ware y software) AR-UCAR-216771-GO-RFQ / Component 3 - Agricultural E Request for Quota Single Stage - One E Pending Impl Fortalecimiento Informático IBRD / 88670 mergency Response Financi Post Open - National 25,000.00 0.00 2021-11-20 2022-01-15 2022-07-14 tions nvelope ementation MAGYP y Provincias (3.1.1.3) ng and Transfer of Agroclim atic Risks AR-UCAR-226703-GO-RFB / Component 2 - Agricultural r Single Stage - One E Pending Impl ELMI - Adquisición de reservo IBRD / 88670 Post Request for Bids Open - National 212,000.00 0.00 2021-07-01 2021-07-06 2021-08-17 2021-09-16 2021-10-21 2022-04-19 isk mitigation investments nvelope ementation rios y parcelas AR-UCAR-231943-GO-RFQ / Component 1 - Strengthenin Request for Quota Single Stage - One E Placas de telemetría 3G - Bol IBRD / 88670 g agro-climatic information s Post Open - National 49,368.00 49,368.00 Signed 2021-05-15 2021-07-10 2022-03-09 2022-01-06 tions nvelope sa de Cereales Entre Ríos ystems AR-UCAR-216745-GO-RFB / Component 1 - Strengthenin Convenio CONAE - Adquisició Single Stage - One E IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 614,333.30 0.00 Signed 2021-02-05 2021-11-03 2021-02-10 2021-03-24 2021-12-16 2021-04-23 2022-05-20 2021-05-28 2021-11-24 n de sistema de discos para nvelope ystems almacenamiento de red de al ta AR-UCAR-255413-GO-RFQ / Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl Elementos de medición para IBRD / 88670 Post Open - National 29,000.00 0.00 2021-10-09 2021-12-04 2022-06-02 isk mitigation investments tions nvelope ementation parcelas demostrativas ELMI AR-UCAR-255414-GO-RFQ / Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 71,000.00 0.00 2022-06-06 2022-08-01 2023-01-28 Parcelas demostrativas riego isk mitigation investments tions nvelope ementation ELMI AR-UCAR-186660-GO-RFQ / Component 1 - Strengthenin Adquisición de instrumentos Single Stage - One E IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 506,010.00 0.00 Signed 2021-04-01 2021-11-01 2021-04-06 2021-12-09 2021-12-09 2022-01-08 2022-05-31 2022-02-12 2022-08-11 para estaciones meteorológic nvelope ystems as convencionales - Convenio MAGyP - INTA Page 2 AR-UCAR-286858-GO-RFQ / Equipamiento informático en el marco del subproyecto "Re Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 5,846.00 0.00 2022-05-07 2022-07-02 2022-12-29 acondicionamiento y Mejora isk mitigation investments tions nvelope ementation del Sistema de Riego de Buta Ranquil" de la provincia del N euquén AR-UCAR-287085-GO-RFQ / Adquisición Equipamiento Inf ormático UEP y Consorcio Có Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl rdoba - Acueducto Ganadero IBRD / 88670 Post Open - National 17,000.00 0.00 2022-04-16 2022-06-11 2022-12-08 isk mitigation investments tions nvelope ementation "La Providencia, La Ramada y Santa Ana - Departamento Roque Sáenz Peña, Provincia de Córdoba". AR-UCAR-287086-GO-RFQ / Mobiliario UEP y Consorcio - Acueducto Ganadero "La Pro Component 2 - Agricultural r Request for Quota Single Stage - One E Under Imple IBRD / 88670 Post Open - National 3,435.00 0.00 2022-04-16 2022-06-11 2022-12-08 videncia, La Ramada y Santa isk mitigation investments tions nvelope mentation Ana - Departamento Roque S áenz Peña, Provincia de Córd oba". AR-UCAR-295703-GO-RFB / Component 1 - Strengthenin Single Stage - One E Under Imple IBRD / 88670 Prior Request for Bids Open - National 3,000,000.00 0.00 2022-06-06 2022-07-27 2022-06-11 2022-07-23 2022-09-07 2022-08-22 2022-09-26 2023-03-25 Actualización Datacenter MA g agro-climatic information s nvelope mentation GYP ystems AR-UCAR-301414-GO-RFB / 10 camionetas 4x4 en el mar co del subproyecto "Fortaleci Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 700,000.00 0.00 2022-07-04 2022-07-09 2022-08-20 2022-09-19 2022-10-24 2023-04-22 miento del sistema de preve isk mitigation investments nvelope ementation nción y control de Incendios Forestales" de la provincia d e Mendoza AR-UCAR-301415-GO-RFB / Maquinaria pesada en el mar co del subproyecto "Fortaleci Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 1,540,000.00 0.00 2022-07-04 2022-07-09 2022-08-20 2022-09-19 2022-10-24 2023-04-22 miento del sistema de preve isk mitigation investments nvelope ementation nción y control de Incendios Forestales" de la provincia d e Mendoza AR-UCAR-286853-GO-RFQ / Compra de Equipamiento Inf ormático en el marco del sub Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 20,000.00 0.00 2022-07-15 2022-09-09 2022-11-09 proyecto "Fortalecimiento Sa isk mitigation investments tions nvelope ementation nitario del rodeo bovino provi ncial" de la provincia del Neu quén AR-UCAR-301437-GO-RFQ / Equipamiento informático en Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl el marco del subproyecto "D IBRD / 88670 Post Open - National 6,600.00 0.00 2022-08-15 2022-10-10 2023-01-08 isk mitigation investments tions nvelope ementation esarrollo Ganadero de la Pro vincia de Jujuy (Etapa I)", pro vincia de Jujuy AR-UCAR-301429-GO-RFB / Maquinaria para siembra y e Component 2 - Agricultural r Single Stage - One E Pending Impl nfardado en el marco del sub IBRD / 88670 Post Request for Bids Open - National 328,000.00 0.00 2022-10-04 2022-10-09 2022-11-20 2022-12-20 2023-01-24 2023-04-24 isk mitigation investments nvelope ementation proyecto "Desarrollo Ganade ro de la Provincia de Jujuy (Et apa I)" de la provincia de Juju y AR-UCAR-301412-GO-RFQ / Equipamiento para Mejorami ento del sistema de comunic Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl ación en el marco del subpro IBRD / 88670 Post Open - National 58,000.00 0.00 2022-08-03 2022-09-28 2022-10-28 isk mitigation investments tions nvelope ementation yecto "Fortalecimiento del sis tema de prevención y control de Incendios Forestales" de l a provincia de Mendoza AR-UCAR-301413-GO-RFB / Equipamiento de Combate d e Incendios: motosierras, bo mbas, mochilas, matafuegos, Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 190,000.00 0.00 2022-10-04 2022-10-09 2022-11-20 2022-12-20 2023-01-24 2023-02-23 etc en el marco del subproye isk mitigation investments nvelope ementation cto "Fortalecimiento del siste ma de prevención y control d e Incendios Forestales" de la provincia de Mendoza AR-UCAR-301417-GO-RFQ / Estaciones Meteorológicas en el marco del subproyecto "Fo Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 77,000.00 0.00 2022-12-07 2023-02-01 2023-05-02 rtalecimiento del sistema de isk mitigation investments tions nvelope ementation prevención y control de Ince ndios Forestales" de la provin cia de Mendoza AR-UCAR-301431-GO-RFB / Maquinaria para establecimie nto "El remate" en el marco Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 290,000.00 0.00 2022-10-05 2022-10-10 2022-11-21 2022-12-21 2023-01-25 2023-04-25 del subproyecto "Desarrollo isk mitigation investments nvelope ementation Ganadero de la Provincia de J ujuy (Etapa I", provincia de Ju juy AR-UCAR-301434-GO-RFB / Equipamiento para laboratori o de genética animal en el m Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 109,000.00 0.00 2022-11-02 2022-11-07 2022-12-19 2023-01-18 2023-02-22 2023-05-23 arco del subproyecto "Desarr isk mitigation investments nvelope ementation ollo Ganadero de la Provincia de Jujuy (Etapa I)" provincia de Jujuy AR-UCAR-286851-GO-RFQ / Compra de dos corrales para manejo de Ganado en el mar Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 100,000.00 0.00 2022-07-01 2022-07-06 2022-08-17 2022-09-16 2022-10-21 2023-01-19 co del subproyecto "Fortaleci isk mitigation investments nvelope ementation miento Sanitario del rodeo b ovino provincial" de la Provin cia del Neuquén AR-UCAR-301422-GO-RFB / Compra de 2 camionetas 4x4 Component 2 - Agricultural r Single Stage - One E Pending Impl en el marco del subproyecto IBRD / 88670 Post Request for Bids Open - National 150,000.00 0.00 2022-07-26 2022-07-31 2022-09-11 2022-10-11 2022-11-15 2023-03-15 isk mitigation investments nvelope ementation "Desarrollo Ganadero de la P rovincia de Jujuy (Etapa I)" d e la provincia de Jujuy AR-UCAR-303592-GO-DIR / E staciones agrometeorológica Component 1 - Strengthenin Pending Impl s, sensores y despliegue de t IBRD / 88670 g agro-climatic information s Post Direct Selection Direct - National 60,000.00 0.00 2022-07-18 2022-07-28 2022-10-03 2023-04-01 ementation ecnología en servidor de mo ystems nitoreo provincial en la provi ncia de Chaco Page 3 AR-UCAR-231949-GO-RFB / Component 1 - Strengthenin Single Stage - One E Estaciones Meteorológicas A IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 118,800.00 0.00 Canceled 2022-01-17 2022-03-17 2022-01-22 2022-03-05 2022-05-06 2022-04-04 2022-05-09 2022-11-05 nvelope utomáticas (EMA) - provincia ystems de Formosa AR-UCAR-309138-GO-RFB / Component 1 - Strengthenin Estaciones Meteorológicas A Single Stage - One E Pending Impl IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 118,000.00 0.00 2022-08-15 2022-08-20 2022-10-01 2022-10-31 2022-12-05 2023-06-03 utomáticas (EMA) y repuesto nvelope ementation ystems s - provincia de Formosa AR-UCAR-287088-GO-RFQ / Sistema de Ventilación Conso rcio - Acueducto Ganadero "L Component 2 - Agricultural r Request for Quota Single Stage - One E IBRD / 88670 Post Open - National 3,607.00 0.00 Canceled 2022-04-16 2022-06-11 2022-12-08 a Providencia, La Ramada y isk mitigation investments tions nvelope Santa Ana - Departamento R oque Sáenz Peña, Provincia d e Córdoba". AR-UCAR-315643-GO-RFQ / Equipamiento para oficina -C Component 2 - Agricultural r Request for Quota Single Stage - One E Under Imple onsorcio- "Acueducto Ganade IBRD / 88670 Post Open - National 3,607.00 0.00 2022-09-27 2022-11-22 2023-05-21 isk mitigation investments tions nvelope mentation ro La Providencia La Ramada y Santa Ana - Córdoba" AR-UCAR-186688-GO-DIR / A Component 1 - Strengthenin ctualización Antenas. Conven IBRD / 88670 g agro-climatic information s Post Direct Selection Direct 578,334.85 0.00 Canceled 2020-09-09 2021-06-24 2020-09-16 2021-07-24 2021-10-04 2022-05-23 io MAGyP - INTA ystems AR-UCAR-286848-GO-RFB / Dos (2) camionetas 4x4 DC - Component 2 - Agricultural r Single Stage - One E Subproyecto "Fortalecimient IBRD / 88670 Post Request for Bids Open - National 147,000.00 0.00 Canceled 2022-04-04 2022-06-24 2022-07-06 2022-08-17 2022-09-16 2022-10-21 2023-02-01 isk mitigation investments nvelope o Sanitario del rodeo bovino provincial" provincia del Neu quén AR-UCAR-318605-GO-RFB / Compra de heladeras con fre ezer, conservadoras plásticas y centrífugas para conservaci Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 125,000.00 0.00 2022-09-30 2022-10-05 2022-11-02 2022-11-17 2022-12-22 2023-06-20 ón de vacunas e insumos vet isk mitigation investments nvelope ementation erinarios en el marco del sub proyecto "Fortalecimiento Sa nitario del rodeo bovino provi ncial" de la provincia del Neu quén AR-UCAR-287082-GO-RFQ / Adquisición de Vehículo para UEP Córdoba - Acueducto Ga Component 2 - Agricultural r Request for Quota Single Stage - One E IBRD / 88670 Post Open - National 35,800.00 0.00 Canceled 2022-04-16 2022-06-11 2022-12-08 nadero "La Providencia, La R isk mitigation investments tions nvelope amada y Santa Ana - Departa mento Roque Sáenz Peña, Pr ovincia de Córdoba". AR-UCAR-224910-GO-RFB / Component 2 - Agricultural r Single Stage - One E Ocho (8) Camionetas tipo pic IBRD / 88670 Post Request for Bids Open - National 320,000.00 0.00 Canceled 2021-05-03 2022-02-17 2021-05-08 2021-06-19 2022-04-05 2021-07-19 2021-08-23 2022-02-19 isk mitigation investments nvelope k up doble cabina AR-UCAR-320687-GO-RFB / T Component 2 - Agricultural r Single Stage - One E Pending Impl res (3) Camionetas tipo pick IBRD / 88670 Post Request for Bids Open - National 300,000.00 0.00 2022-10-14 2022-10-19 2022-11-03 2022-11-08 2022-11-22 2022-12-22 isk mitigation investments nvelope ementation up doble cabina AR-UCAR-318611-GO-RFQ / Adquisición de Vehículo para UEP Córdoba - Acueducto Ga Component 2 - Agricultural r Request for Quota Single Stage - One E IBRD / 88670 Post Open - National 65,000.00 0.00 Canceled 2022-10-08 2022-12-03 2023-06-01 nadero "La Providencia, La R isk mitigation investments tions nvelope amada y Santa Ana - Departa mento Roque Sáenz Peña, Pr ovincia de Córdoba". AR-UCAR-318601-GO-RFB / Dos (2) camionetas 4x4 DC - Component 2 - Agricultural r Single Stage - One E Pending Impl Subproyecto "Fortalecimient IBRD / 88670 Post Request for Bids Open - National 147,000.00 0.00 2022-09-30 2022-10-05 2022-11-16 2022-12-16 2023-01-20 2023-07-19 isk mitigation investments nvelope ementation o Sanitario del rodeo bovino provincial" provincia del Neu quén AR-UCAR-318824-GO-RFQ / Una (a) camioneta 4x4 - Sub proyecto "Rehabilitación de l Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 88,000.00 0.00 2022-10-10 2022-12-05 2023-06-03 a dinámica hidráulica del sub isk mitigation investments tions nvelope ementation sistema de la Cuenca del Arr oyo Baí – Zona Norte de Corri entes" AR-UCAR-240328-GO-RFQ / Component 1 - Strengthenin Equipamiento informático - F Request for Quota Single Stage - One E IBRD / 88670 g agro-climatic information s Post Open - National 35,155.95 0.00 Canceled 2021-09-25 2021-11-20 2022-05-19 ortalecimiento interno Oficin tions nvelope ystems a de Riesgo Agropecuario AR-UCAR-216747-GO-RFB / Convenio CONAE - Adquisició Component 1 - Strengthenin n de un sistema de antena p Open - Internationa Single Stage - One E IBRD / 88670 g agro-climatic information s Post Request for Bids 570,000.00 0.00 Canceled 2021-12-01 2022-08-26 2021-12-06 2022-08-26 2022-01-17 2022-02-16 2022-03-23 2022-09-19 ara recepción y adquisición d l nvelope ystems e datos satelitales de observac ión de la tierra en banda L y X. AR-UCAR-216747-GO-RFB-2 / Convenio CONAE - Adquisici Component 1 - Strengthenin ón de un sistema de antena Open - Internationa Single Stage - One E Under Imple IBRD / 88670 g agro-climatic information s Post Request for Bids 700,000.00 0.00 2022-11-14 2023-01-23 2022-11-19 2023-01-27 2022-12-31 2023-01-30 2023-03-06 2023-09-02 para recepción y adquisición l nvelope mentation ystems de datos satelitales de obser vación de la tierra en banda L y X. AR-UCAR-326032-GO-DIR / S Component 1 - Strengthenin Pending Impl ensores para estaciones met IBRD / 88670 g agro-climatic information s Post Direct Selection Direct - National 44,852.00 0.00 2022-11-15 2022-11-20 2022-12-26 2023-04-28 ementation eorológicas automáticas - Co ystems nvenio INTA AR-UCAR-326033-GO-DIR / T Component 1 - Strengthenin ermorresistencias de platino Pending Impl IBRD / 88670 g agro-climatic information s Post Direct Selection Direct - National 17,400.00 0.00 2022-11-15 2022-11-20 2022-12-26 2023-04-21 para estaciones meteorológic ementation ystems as automáticas de la Red INT A - Convenio INTA AR-UCAR-326040-GO-DIR / P Component 1 - Strengthenin lacas Electrónicas para Estaci Pending Impl IBRD / 88670 g agro-climatic information s Post Direct Selection Direct - National 25,000.00 0.00 2022-11-15 2022-11-20 2023-01-16 2023-03-03 ones Meteorológicas Automá ementation ystems ticas - Convenio INTA AR-UCAR-302281-GO-RFB / Activación CERC para la Provi Component 5 - Contingency Single Stage - One E ncia de Corrientes. Adquisici IBRD / 88670 Emergency Response Comp Prior Request for Bids Open - National 2,900,000.00 0.00 Canceled 2022-07-07 2022-07-22 2022-08-11 2022-08-16 2022-08-26 2022-12-24 nvelope ón de alambrado perimetral, onent (CERC) postes de acero de alto carb ono y accesorios Page 4 AR-UCAR-326153-GO-RFB / Activación CERC para la Provi Component 2 - Agricultural r Single Stage - One E ncia de Corrientes. Adquisici IBRD / 88670 Post Request for Bids Open - National 4,200,000.00 0.00 Canceled 2022-11-11 2022-11-16 2022-11-26 2022-12-06 2023-01-03 2023-07-02 isk mitigation investments nvelope ón de alambrado perimetral, postes de acero de alto carb ono y accesorios AR-UCAR-186688-GO-DIR-2 / Component 1 - Strengthenin Adquisición de Actualización Direct - Internation Pending Impl IBRD / 88670 g agro-climatic information s Post Direct Selection 580,000.00 0.00 2022-12-02 2022-12-09 2023-02-06 2023-09-25 del Sistema Receptor Satelita al ementation ystems l INTA Castelar AR-UCAR-240328-GO-RFQ-2 Component 1 - Strengthenin / Equipamiento informático - Request for Quota Single Stage - One E Pending Impl IBRD / 88670 g agro-climatic information s Post Open - National 85,000.00 0.00 2023-01-09 2023-03-27 2023-08-28 Fortalecimiento interno Ofici tions nvelope ementation ystems na de Riesgo Agropecuario AR-UCAR-332241-GO-RFB / Compra de Equipamiento Inf ormático en el marco del sub Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl proyecto "Reacondicionamie IBRD / 88670 Post Open - National 70,000.00 0.00 2023-01-07 2023-03-04 2023-08-31 isk mitigation investments tions nvelope ementation nto de los préstamos de la re d vial provincial para la prev ención y control de incendios forestales” de La Pampa AR-UCAR-332240-GO-RFB / Una (a) camioneta 4x4 - Sub proyecto "Reacondicionamie Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 80,000.00 0.00 2023-01-07 2023-03-04 2023-08-31 nto de los préstamos de la re isk mitigation investments tions nvelope ementation d vial provincial para la prev ención y control de incendios forestales” La Pampa AR-UCAR-347024-GO-DIR / R Component 1 - Strengthenin Direct - Internation Pending Impl IBRD / 88670 Post Direct Selection 575,000.00 0.00 2023-06-05 2024-06-04 epuestos radares - Convenio g agro-climatic information s al ementation INTA ystems AR-UCAR-347129-GO-RFQ / Equipamiento de Combate d e Incendios: motosierras, Sap a Rastrillo, Pulaski, machetes Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 90,300.00 0.00 2023-03-19 2023-05-14 2023-11-10 , tanque de agua portatil, etc isk mitigation investments tions nvelope ementation en el marco del subproyecto " PREVENCION, CONTROL Y R EMEDIACION DE INCENDIOS FORESTALES - CORDOBA" AR-UCAR-347132-GO-RFB / Maquinaria pesada en el mar Component 2 - Agricultural r Single Stage - One E Pending Impl co del subproyecto "Prevenci IBRD / 88670 Post Request for Bids Open - National 360,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 isk mitigation investments nvelope ementation ón, Control y Remediación de incendios forestales en la Pro vincia de Córdoba" AR-UCAR-347133-GO-RFB / Una (1) Camioneta 4x4 y Cua tro (4) Vehículos utilitarios en Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 300,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 el marco del Subproyecto "Pr isk mitigation investments nvelope ementation evención, Control y Remedia ción de incendios forestales en la Provincia de Córdoba" AR-UCAR-347178-GO-RFB / Cámara de germinación con control de temperatura e ins umos para un banco de germ Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 165,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 oplasma en el marco del Sub isk mitigation investments nvelope ementation proyecto "Prevención, Contro l y Remediación de incendios forestales en la Provincia de Córdoba" AR-UCAR-348011-GO-RFB / Compra de maquinaria vial e n el marco del subproyecto " Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Prior Request for Bids Open - National 4,300,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 Fortalecimiento Provincial de isk mitigation investments nvelope ementation Manejo Agroambiental para l a adaptación y mitigación del riesgo climático" d AR-UCAR-348015-GO-RFB / 4 Camionetas Pick up 4x4 y 3 vehículos utilitarios en el mar co del subproyecto "Fortaleci Component 2 - Agricultural r Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 350,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 miento Provincial de Manejo isk mitigation investments nvelope ementation Agroambiental para la adapt ación y mitigación del riesgo climático" de la provincia de Misiones AR-UCAR-348016-GO-RFB / Equipamiento para combate de Incendios en el marco del Component 2 - Agricultural r Single Stage - One E Pending Impl subproyecto "Fortalecimiento IBRD / 88670 Post Request for Bids Open - National 830,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 isk mitigation investments nvelope ementation Provincial de Manejo Agroam biental para la adaptación y mitigación del riesgo climátic o" provincia de Misiones AR-UCAR-348017-GO-RFB / Maquinaria y equipos para tr abajo de suelos en el marco Component 2 - Agricultural r Single Stage - One E Pending Impl del subproyecto "Fortalecimi IBRD / 88670 Post Request for Bids Open - National 1,420,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 isk mitigation investments nvelope ementation ento Provincial de Manejo Ag roambiental para la adaptaci ón y mitigación del riesgo cli mático" de la provincia de Mi siones AR-UCAR-348162-GO-RFB / Activación CERC para la Provi Component 5 - Contingency Single Stage - One E Pending Impl ncia de Corrientes. Adquisici IBRD / 88670 Emergency Response Comp Post Request for Bids Open - National 2,300,000.00 0.00 2023-03-13 2023-04-02 2023-04-12 2023-04-17 2023-05-08 2023-06-07 nvelope ementation ón de alambrado perimetral, onent (CERC) postes de quebracho y acces orios AR-UCAR-348014-GO-RFB / Vehículos pesados en el mar co del subproyecto "Fortaleci Component 2 - Agricultural r Single Stage - One E Pending Impl miento Provincial de Manejo IBRD / 88670 Post Request for Bids Open - National 1,700,000.00 0.00 2023-03-13 2023-03-18 2023-04-29 2023-05-29 2023-07-03 2023-12-30 isk mitigation investments nvelope ementation Agroambiental para la adapt ación y mitigación del riesgo climático" de la provincia de Misiones AR-UCAR-355816-GO-RFQ / Parcelas demostrativas para Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl riego en el marco del subpro IBRD / 88670 Post Open - National 8,000.00 0.00 2023-04-22 2023-06-17 2023-12-14 isk mitigation investments tions nvelope ementation yecto "Mejora de la red de ri ego del Valle de Jáchal – Can al del Alto" en San Juan Page 5 AR-UCAR-355818-GO-RFQ / Compra de Equipamiento Inf ormático en el marco del sub Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 15,000.00 0.00 2023-04-22 2023-06-17 2023-12-14 proyecto "Mejora de la red d isk mitigation investments tions nvelope ementation e riego del Valle de Jáchal – C anal del Alto" provincia de Sa n Juan AR-UCAR-357788-GO-RFB / I Component 1 - Strengthenin nstrumentos para estaciones Single Stage - One E Pending Impl IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 303,188.00 0.00 2023-05-08 2023-05-15 2023-06-15 2023-07-15 2023-08-31 2023-11-30 meteorológicas convencional nvelope ementation ystems es y automáticas - Convenio I NTA AR-UCAR-357974-GO-RFQ / Compra de heladeras con fre ezer, conservadoras plásticas y centrífugas para conservaci Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 33,000.00 0.00 2023-05-06 2023-07-01 2023-12-28 ón de vacunas e insumos vet isk mitigation investments tions nvelope ementation erinarios en el marco del sub proyecto "Fortalecimiento Sa nitario del rodeo bovino provi ncial" de la provincia del Neu quén AR-UCAR-357976-GO-RFQ / Compra de Equipamiento Inf Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl ormático en el marco del sub IBRD / 88670 Post Open - National 27,000.00 0.00 2023-04-29 2023-06-24 2023-12-21 isk mitigation investments tions nvelope ementation proyecto "FORTALECIMIENTO SANITARIO DEL RODEO BOVI NO PROVINCIAL" AR-UCAR-358057-GO-RFQ / Cámaras y equipamiento de prensa para UEP Córdoba - A Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl cueducto Ganadero "La Provi IBRD / 88670 Post Open - National 26,000.00 0.00 2023-05-08 2023-07-03 2023-12-30 isk mitigation investments tions nvelope ementation dencia, La Ramada y Santa A na - Departamento Roque Sá enz Peña, Provincia de Córdo ba" AR-UCAR-361848-GO-RFQ / Mobiliario UEP y Consorcio - Acueducto Ganadero "La Pro Component 2 - Agricultural r Request for Quota Single Stage - One E Pending Impl IBRD / 88670 Post Open - National 6,500.00 0.00 2023-05-27 2023-07-22 2024-01-18 videncia, La Ramada y Santa isk mitigation investments tions nvelope ementation Ana - Departamento Roque S áenz Peña, Provincia de Córd oba AR-UCAR-326037-GO-RFQ / Component 1 - Strengthenin Request for Quota Single Stage - One E Pending Impl Notebooks y servidores - Con IBRD / 88670 g agro-climatic information s Post Open - National 89,125.50 0.00 2022-12-05 2023-06-19 2023-10-20 tions nvelope ementation venio INTA ystems AR-UCAR-365932-GO-DIR / S egunda Activación CERC: Co Component 5 - Contingency ntratación de un servicio de Pending Impl IBRD / 88670 Emergency Response Comp Post Direct Selection Direct - National 15,000,000.00 0.00 2023-06-09 2023-06-11 2023-06-22 2023-11-19 disponibilidad de insumos ag ementation onent (CERC) ropecuarios, y entrega a peq ueños y medianos productor es AR-UCAR-257976-GO-RFB / Component 1 - Strengthenin Hardware y Software para “ Single Stage - One E Pending Impl IBRD / 88670 g agro-climatic information s Post Request for Bids Open - National 800,000.00 0.00 2023-06-26 2023-07-01 2023-08-12 2023-09-11 2023-10-16 2024-04-13 Sistemas de Información de nvelope ementation ystems Operaciones (SIO)” AR-UCAR-367631-GO-RFB / Modernización de la Red de Component 1 - Strengthenin Open - Internationa Single Stage - Two E Pending Impl Referencia Meteorológica de IBRD / 88670 g agro-climatic information s Prior Request for Bids 5,000,000.00 0.00 2023-06-20 2023-06-30 2023-08-11 2023-10-24 2023-11-28 2024-05-26 l nvelope ementation Superficie del Servicio Meteo ystems rológico Nacional (SMN) AR-UCAR-289777-GO-RFB / Modernización de la Red de Component 1 - Strengthenin Open - Internationa Single Stage - One E Referencia Meteorológica de IBRD / 88670 g agro-climatic information s Prior Request for Bids 4,764,700.00 0.00 Canceled 2022-04-25 2022-04-30 2022-06-11 2022-07-11 2022-08-15 2023-02-11 l nvelope Superficie del Servicio Meteo ystems rológico Nacional (SMN) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UCAR-247569-CS-CQS / Component 3 - Agricultural E Single Stage - One E Adquisición piloto de seguro IBRD / 88670 mergency Response Financi Post Request for Bids Open - National 800,000.00 0.00 Signed 2021-09-30 2021-11-30 2021-10-18 2021-11-29 2022-01-10 2021-12-29 2022-03-27 2022-02-02 2022-08-01 nvelope hortícola. Provincia de Bueno ng and Transfer of Agroclim s Aires atic Risks AR-UCAR-302275-NC-RFB / A Component 3 - Agricultural E dquisición piloto de seguro h mergency Response Financi Single Stage - One E Pending Impl IBRD / 88670 Post Request for Bids Open - National 300,000.00 0.00 2022-06-30 2022-07-07 2022-08-06 2022-08-21 2022-09-25 2023-05-23 ortícola (complementario). Pr ng and Transfer of Agroclim nvelope ementation ovincia de Buenos Aires atic Risks AR-UCAR-304449-NC-RFQ / Servicio de cátering para Jorn Component 1 - Strengthenin adas de capacitación en el “ Request for Quota Single Stage - One E Pending Impl IBRD / 88670 g agro-climatic information s Post Open - National 1,200.00 0.00 2022-07-20 2022-09-01 2023-02-28 USO DE INFORMACIÓN AGRO tions nvelope ementation ystems CLIMÁTICA EN LA TOMA DE D ECISIONES FRENTE AL RIESG O AGROPECUARIO” CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UCAR-216769-CS-CQS / Contratación de firma consul Component 3 - Agricultural E tora /universidad especialista mergency Response Financi Consultant Qualifi Pending Impleme IBRD / 88670 Post Open - National 21,500.00 0.00 2021-04-01 2021-04-22 2021-06-05 2021-07-05 2021-08-09 2022-02-05 en programación web para p ng and Transfer of Agroclim cation Selection ntation lataforma de carga y consult atic Risks a base histórica de Emergenc ia Agropecuaria.3.1.1.1 y 3.1. 1.2 Page 6 AR-UCAR-216775-CS-CQS / Contratación de firma consul tora especialista en program Component 3 - Agricultural E ación de sistemas para la pu mergency Response Financi Consultant Qualifi Pending Impleme blicación web de herramient IBRD / 88670 Post Open - National 40,000.00 0.00 2021-04-05 2021-04-26 2021-06-09 2021-07-09 2021-08-13 2022-02-09 ng and Transfer of Agroclim cation Selection ntation as de monitoreo y gestión de atic Risks riesgos, desarrollo y publicac ión de Índices climáticos e inf ormes de estudios técnicos. 3.1.6.1 y 3.1.6.2. AR-UCAR-226701-CS-CQS / E Component 2 - Agricultural r Consultant Qualifi Pending Impleme LMI - Desarrollo de una app e IBRD / 88670 Post Open - National 10,000.00 0.00 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 isk mitigation investments cation Selection ntation n gestión del conocimiento AR-UCAR-247570-CS-QCBS / Contratación de Auditoría Co Component 4 - Project coord Quality And Cost- Under Implement ncurrente de los subproyecto IBRD / 88670 ination, monitoring and eval Post Open - National 240,000.00 0.00 2021-08-30 2022-01-18 2021-09-20 2021-11-03 2021-12-01 2021-12-31 2022-02-04 2022-03-11 2023-03-11 Based Selection ation s de inversión pública en el uation marco del subcomponente 2. 2 AR-UCAR-318668-CS-QCBS / Component 3 - Agricultural E Contratación de firma consul mergency Response Financi Quality And Cost- Open - Internationa Pending Impleme IBRD / 88670 Post 180,000.00 0.00 2022-10-03 2022-10-24 2022-12-07 2023-01-04 2023-02-03 2023-03-10 2023-04-14 2024-04-13 tora para diseño de estrategi ng and Transfer of Agroclim Based Selection l ntation a de financiamiento de riesg atic Risks os AR-UCAR-216770-CS-CQS / Component 3 - Agricultural E Contratación de firma consul mergency Response Financi Consultant Qualifi IBRD / 88670 Post Open - National 70,000.00 0.00 Canceled 2021-04-06 2022-03-15 2021-04-27 2021-06-10 2021-07-10 2021-08-14 2022-02-10 tora/universidad para diseño ng and Transfer of Agroclim cation Selection de estrategia de financiamie atic Risks nto de riesgos. 3.1.5.1 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AR-UCAR-186662-CS-INDV / Contratación Consultor/a Esp Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 9,285.70 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ecialista en Ingeniería Civil p isk mitigation investments ant Selection ntation ara Formulación de Proyecto s AR-UCAR-186673-CS-INDV / Contratación Consultor/a Esp Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 7,000.00 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ecialista en Formulación y Ev isk mitigation investments ant Selection ntation aluación Económica de Proye ctos AR-UCAR-186678-CS-INDV / Contratación Consultor/a esp Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 9,285.70 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ecialista ambiental para form isk mitigation investments ant Selection ntation ulación de proyectos AR-UCAR-186680-CS-INDV / Contratación Consultor/a esp Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 6,964.30 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ecialista en afectación de act isk mitigation investments ant Selection ntation ivos para formulación de pro yecto AR-UCAR-186681-CS-INDV / Contratación Consultor/a esp Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 6,964.30 0.00 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ecialista en pueblos indígena isk mitigation investments ant Selection ntation s para formulación de proyec to Component 3 - Agricultural E AR-UCAR-186683-CS-INDV / Individual Consult IBRD / 88670 mergency Response Financi Post Open 5,285.70 0.00 Canceled 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 Contratración de Data Entry ant Selection ng and Transfer of Agroclim atic Risks AR-UCAR-186685-CS-INDV / Component 3 - Agricultural E Contratación de 4 Especialist mergency Response Financi Individual Consult as, Master o Doctor en econo IBRD / 88670 Post Open 59,214.30 0.00 Canceled 2020-08-17 2020-10-05 2020-10-26 2020-11-30 2021-05-29 ng and Transfer of Agroclim ant Selection mía agropecuaria y finanzas atic Risks públicas.- Buenos Aires AR-UCAR-186687-CS-CDS / B uenos Aires- Comité Técnico Component 2 - Agricultural r IBRD / 88670 Post Direct Selection Direct 74,000.00 0.00 Signed 2021-04-01 2021-07-21 2021-04-11 2021-07-08 2021-06-15 2021-12-12 de Evaluación de Subproyect isk mitigation investments os - Contrato Servicios de Co nsultoría IICA AR-UCAR-216774-CS-INDV / Component 3 - Agricultural E Especialista en economía agr mergency Response Financi Individual Consult Pending Impleme IBRD / 88670 Post Open 6,224.00 0.00 2021-05-03 2021-06-21 2021-07-12 2021-08-16 2022-02-12 aria para estudio de prefactib ng and Transfer of Agroclim ant Selection ntation ilidad para seguro en Ganade atic Risks ría AR-UCAR-216778-CS-INDV / Component 3 - Agricultural E Contratación de un consultor mergency Response Financi Individual Consult Pending Impleme IBRD / 88670 Post Open 15,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 /ra especialista en seguros p ng and Transfer of Agroclim ant Selection ntation ara adecuación póliza seguro atic Risks horticola. 3.2.2.2. AR-UCAR-216761-CS-INDV / Convenio INTA - Contratación Component 1 - Strengthenin Individual Consult Pending Impleme de 1 Especialista, Master o D IBRD / 88670 g agro-climatic information s Post Open 27,000.00 0.00 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 ant Selection ntation octor en agronomia, SIG, Tel ystems edetección.- Buenos Aires AR-UCAR-216756-CS-INDV / Component 1 - Strengthenin Individual Consult Pending Impleme Convenio INTA - Contratració IBRD / 88670 g agro-climatic information s Post Open 72,000.00 0.00 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 ant Selection ntation n de 2 Programadores ystems AR-UCAR-216760-CS-INDV / Component 1 - Strengthenin Individual Consult Pending Impleme Convenio INTA - Contratració IBRD / 88670 g agro-climatic information s Post Open 36,000.00 0.00 2021-04-30 2021-06-18 2021-07-09 2021-08-13 2022-02-09 ant Selection ntation n de 1 Ing. Electrónico ystems AR-UCAR-186682-CS-INDV / Component 3 - Agricultural E Individual Consult Pending Impleme Contratración de 2 Programa IBRD / 88670 mergency Response Financi Post Open 14,857.10 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 ant Selection ntation dor web Symfony SENIOR (Fr ng and Transfer of Agroclim ont-Backend) atic Risks AR-UCAR-216772-CS-INDV / Component 3 - Agricultural E Individual Consult Pending Impleme Especialista en economía agr IBRD / 88670 mergency Response Financi Post Open 7,780.00 0.00 2021-05-03 2021-06-21 2021-07-12 2021-08-16 2022-02-12 ant Selection ntation aria/seguros ng and Transfer of Agroclim atic Risks AR-UCAR-216776-CS-INDV / Component 3 - Agricultural E Individual Consult Pending Impleme Contratación de un actuario. IBRD / 88670 mergency Response Financi Post Open 15,000.00 0.00 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 ant Selection ntation 3.2.1.1 ng and Transfer of Agroclim atic Risks Page 7 AR-UCAR-225069-CS-INDV / Component 2 - Agricultural r Individual Consult Pending Impleme Contratación de cuatro (4) C IBRD / 88670 Post Open 29,045.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 isk mitigation investments ant Selection ntation onsultores Especialistas en Ri ego AR-UCAR-226535-CS-INDV / ELMI - 6 consultores/as en In Component 2 - Agricultural r Individual Consult Pending Impleme geniería Agrónoma o Técnico IBRD / 88670 Post Open 37,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 isk mitigation investments ant Selection ntation s/as Universitarios/as en Sist emas de Riego o carreras afi nes AR-UCAR-227311-CS-INDV / Component 1 - Strengthenin Individual Consult Especialista en Ciencias Amb IBRD / 88670 g agro-climatic information s Post Open 8,714.00 0.00 Signed 2021-06-01 2021-08-02 2021-07-20 2021-08-24 2021-08-10 2021-08-25 2021-09-14 2022-03-13 ant Selection ientales-Cambio climático ystems AR-UCAR-227312-CS-INDV / Component 1 - Strengthenin Individual Consult Pending Impleme Especialista en hidrología par IBRD / 88670 g agro-climatic information s Post Open 3,112.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 ant Selection ntation a cálculo de precipitación por ystems satélites AR-UCAR-227313-CS-INDV / Especialista informático con Component 1 - Strengthenin Individual Consult Pending Impleme conocimiento agropecuario p IBRD / 88670 g agro-climatic information s Post Open 6,224.00 0.00 2021-06-01 2021-07-20 2021-08-10 2021-09-14 2022-03-13 ant Selection ntation ara estudio de prefactibilidad ystems de Sistema de datos de daño s y pérdidas AR-UCAR-227314-CS-INDV / Component 2 - Agricultural r Individual Consult Cuatro (4) Consultores Espec IBRD / 88670 Post Open 29,045.00 0.00 Signed 2021-05-03 2021-04-01 2021-06-21 2021-05-20 2021-07-12 2021-06-07 2021-08-16 2022-02-12 isk mitigation investments ant Selection ialistas en Riego AR-UCAR-227315-CS-INDV / Dos (2) Consultores/as Econo Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open 19,087.00 0.00 Signed 2021-04-01 2021-04-01 2021-05-20 2021-05-20 2021-06-10 2021-06-10 2021-07-15 2022-01-11 mistas o idóneos especialista isk mitigation investments ant Selection s en evaluación económica d e proyectos AR-UCAR-227320-CS-INDV / Dos (2) Consultores/as en Ing Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open 19,087.00 0.00 Signed 2021-04-01 2021-04-01 2021-05-20 2021-05-20 2021-06-10 2021-05-24 2021-07-15 2022-01-11 eniaría Agrónoma o especiali isk mitigation investments ant Selection stas idóneos en producción r ural AR-UCAR-216777-CS-INDV / Component 3 - Agricultural E Contratación de dos consulto mergency Response Financi Individual Consult Pending Impleme res/as agronomos especialist IBRD / 88670 Post Open 20,000.00 0.00 2021-05-01 2021-06-19 2021-07-10 2021-08-14 2022-02-10 ng and Transfer of Agroclim ant Selection ntation as en horticultura para relev atic Risks amiento sector horticola BsA s (3.2.2.1) AR-UCAR-226536-NC-DIR / E Component 2 - Agricultural r Under Implement LMI - Diplomatura en Riego y IBRD / 88670 Post Direct Selection Direct 30,000.00 0.00 2021-05-03 2021-09-07 2021-05-13 2021-07-17 2022-01-13 isk mitigation investments ation Drenaje. Universidad Nacion al de Cuyo AR-UCAR-226709-CS-CDS / C Component 1 - Strengthenin onvenio CONAE - Contratació Under Implement IBRD / 88670 g agro-climatic information s Prior Direct Selection Direct 1,325,000.00 0.00 2021-06-14 2022-07-11 2021-06-24 2021-08-28 2022-02-24 n de firma consultora para d ation ystems esarrollo de productos, distri bución y capacitación AR-UCAR-240331-CS-INDV / Contratación de Analista Fun Component 1 - Strengthenin Individual Consult cional para los sistemas exist IBRD / 88670 g agro-climatic information s Post Open 7,000.00 0.00 Signed 2021-06-28 2021-05-03 2021-08-16 2021-07-23 2021-09-06 2021-07-27 2021-10-11 2022-04-09 ant Selection entes en sitio web de la Ofici ystems na de Riesgo Agropecuario ( ORA) AR-UCAR-247572-CS-INDV / ELMI - Contratación de 4 con Component 2 - Agricultural r Individual Consult Pending Impleme IBRD / 88670 Post Open 16,000.00 0.00 2021-08-11 2021-09-29 2021-10-20 2021-11-24 2022-05-23 sultores especialistas en pro isk mitigation investments ant Selection ntation gramación y/o desarrollo de aplicaciones AR-UCAR-255415-CS-INDV / Dos (2) Consultores/as Espec Component 2 - Agricultural r Individual Consult Pending Impleme ialistas Socio-ambientales pa IBRD / 88670 Post Open 16,000.00 0.00 2021-10-01 2021-11-19 2021-12-10 2022-01-14 2022-07-13 isk mitigation investments ant Selection ntation ra la Formulación de Proyect os con financiamiento intern acional AR-UCAR-255416-CS-INDV / Un (1) Consultor/a Especialist Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open 10,000.00 0.00 Signed 2021-10-01 2021-10-01 2021-11-19 2021-11-15 2021-12-10 2021-11-23 2022-01-14 2022-07-13 as en Ingeniería Civil para Fo isk mitigation investments ant Selection rmulación de Proyectos AR-UCAR-280638-CS-INDV / Un (1) consultor para Prepara ción de Plan Evaluación de I Component 4 - Project coord Individual Consult mpacto Subproyecto GIRSAR: IBRD / 88670 ination, monitoring and eval Post Open 1,700.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2022-09-12 ant Selection Rehabilitación de la dinámica uation hídrica del subsistema del Ar royo Baí - Zona Norte de Corr ientes AR-UCAR-286181-CS-INDV / Un (1) consultor para la prep aración del plan de evaluació Component 4 - Project coord Individual Consult n de Impacto del subproyect IBRD / 88670 ination, monitoring and eval Post Open 1,700.00 0.00 Canceled 2022-03-31 2022-05-19 2022-06-09 2022-07-14 2022-09-12 ant Selection o GIRSAR "Prevención y Cont uation rol de Incendios Forestales d e la Provincia de Mendoza" S ubcomponente 2.2 AR-UCAR-295695-CS-INDV / Component 4 - Project coord Individual Consult Under Implement Consultor para Evaluación de IBRD / 88670 ination, monitoring and eval Post Open 4,700.00 0.00 2022-06-01 2022-07-01 2022-07-20 2022-08-10 2022-09-14 2022-11-30 ant Selection ation medio término del programa uation AR-UCAR-286182-CS-INDV / Component 4 - Project coord Un (1) consultor para la prep Individual Consult Pending Impleme IBRD / 88670 ination, monitoring and eval Post Open 6,000.00 0.00 2022-03-31 2022-05-19 2022-06-01 2022-07-01 2022-10-31 aración de Plan Evaluación d ant Selection ntation uation e Impacto Subproyecto GIRS AR AR-UCAR-286856-CS-CDS / C ontratación INTA para Monito reo y muestras en el marco d Component 2 - Agricultural r Pending Impleme IBRD / 88670 Post Direct Selection Direct 334,301.00 0.00 2022-06-27 2022-07-07 2022-09-10 2023-03-09 el Subproyecto "Fortalecimie isk mitigation investments ntation nto Sanitario del rodeo bovin o provincial" de la provincia del Neuquén AR-UCAR-227319-CS-INDV / Cuatro (4) Consultores/as Es Component 2 - Agricultural r Individual Consult pecialistas Socio-ambientales IBRD / 88670 Post Open 58,174.00 0.00 Signed 2021-04-01 2021-04-01 2021-05-20 2021-05-19 2021-06-10 2021-06-09 2021-07-15 2023-03-31 isk mitigation investments ant Selection para la Formulación de Proye ctos con financiamiento inter nacional Page 8 AR-UCAR-227318-CS-INDV / Cuatro (4) Consultores/as Es Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open 38,174.00 0.00 Signed 2021-04-01 2021-04-01 2021-05-20 2021-05-20 2021-06-10 2021-06-10 2021-07-15 2022-11-30 pecialistas en Ingeniería Civil isk mitigation investments ant Selection para Formulación de Proyect os AR-UCAR-186676-CS-INDV / Contratación 3 Consultores/a Component 2 - Agricultural r Individual Consult s especialistas en conectivid IBRD / 88670 Post Open 78,000.00 0.00 Signed 2020-08-17 2021-10-01 2020-10-05 2020-11-14 2020-10-26 2020-12-04 2020-11-30 2024-12-31 isk mitigation investments ant Selection ad rural y sistemas de inform ación para formulación de pr oyectos AR-UCAR-216779-CS-INDV / Component 3 - Agricultural E Contratación de un consultor mergency Response Financi Individual Consult Pending Impleme /ra especialista en abogacía IBRD / 88670 Post Open 15,000.00 0.00 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 ng and Transfer of Agroclim ant Selection ntation y/o administración publica pa atic Risks ra proceso de adquisición se guro. 3.2.2.3 AR-UCAR-216780-CS-INDV / Contratación de 2 consultore Component 3 - Agricultural E s/as profesionales en agrono mergency Response Financi Individual Consult mía, economía agraria o para IBRD / 88670 Post Open - National 35,000.00 0.00 Signed 2022-07-15 2021-07-15 2022-09-02 2021-09-02 2022-09-23 2021-09-23 2022-10-28 2023-04-26 ng and Transfer of Agroclim ant Selection registro de productores para atic Risks Plan Piloto de seguro Hortícol a y Florícola en la provincia d e Buenos Aires AR-UCAR-216763-CS-INDV / Component 1 - Strengthenin Individual Consult Convenio INTA - Contratració IBRD / 88670 g agro-climatic information s Post Open - National 24,000.00 0.00 Signed 2022-07-15 2021-06-01 2022-09-02 2021-07-12 2022-09-23 2021-03-16 2022-10-28 2023-04-26 ant Selection n de Administrador datos - D ystems ata Entry AR-UCAR-227316-CS-INDV / Dos (2) Consultores/as Espec Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open 19,087.00 0.00 Canceled 2021-04-01 2021-05-20 2021-06-10 2021-07-15 2022-01-11 ialistas en Formulación de pr isk mitigation investments ant Selection oyectos con financiamiento i nternacional AR-UCAR-216781-CS-INDV- / Contratación de 1 consultor E Component 1 - Strengthenin Individual Consult specialista en Comunicación IBRD / 88670 g agro-climatic information s Post Limited 20,000.00 0.00 Signed 2021-06-01 2021-05-14 2021-06-06 2021-06-09 2021-06-27 2021-06-30 2021-08-01 2022-12-31 ant Selection para difusión de acciones y a ystems lcances del Programa AR-UCAR-216762-CS-INDV- / 2 Consultores Especialistas S Component 1 - Strengthenin IG- Teledetección con formac Individual Consult IBRD / 88670 g agro-climatic information s Post Limited 14,000.00 0.00 Signed 2021-06-01 2021-08-13 2021-06-06 2021-08-18 2021-06-27 2021-08-25 2021-08-01 2022-12-30 ión en geografía o ciencias a ant Selection ystems mbientales/sociales para mo nitoreo de eventos extremos con impacto agroproductivo AR-UCAR-216762-CS-INDV / Especialista SIG- Teledetecci Component 1 - Strengthenin ón con formación en geografí Individual Consult IBRD / 88670 g agro-climatic information s Post Open 6,224.00 0.00 Canceled 2021-06-01 2021-08-02 2021-07-20 2021-08-10 2021-09-14 2022-03-13 a o ciencias ambientales/soci ant Selection ystems ales para monitoreo de event os extremos con impacto agr oproductivo AR-UCAR-227316-CS-INDV- / Cuatro (4) Consultores/as Es Component 2 - Agricultural r Individual Consult IBRD / 88670 Post Open - National 60,000.00 0.00 Signed 2022-10-14 2021-04-16 2022-12-02 2021-05-05 2022-12-23 2021-05-18 2023-01-27 2024-12-31 pecialistas en Formulación d isk mitigation investments ant Selection e proyectos con financiamien to internacional AR-UCAR-332218-CS-QCBS / Contratación directa del Insti tuto Interamericano de Coop Component 4 - Project coord eración para la Agricultura (II Pending Impleme IBRD / 88670 ination, monitoring and eval Post Direct Selection Direct - National 260,000.00 0.00 2023-01-02 2023-01-12 2023-03-18 2023-09-14 CA) para actualización del es ntation uation tudio “Las explotaciones agr opecuarias familiares en la R epública Argentina” en base a datos censales 2018 AR-UCAR-360918-CS-INDV / Component 1 - Strengthenin Contratación de un consultor Individual Consult Pending Impleme IBRD / 88670 g agro-climatic information s Post Open - National 5,000.00 0.00 2023-07-01 2023-08-19 2023-09-09 2023-10-14 2024-04-11 para el Desarrollo de una apli ant Selection ntation ystems cación móvil de agrometeoro logía para INTA AR-UCAR-368710-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme Consultor/a técnica en gestió IBRD / 88670 ination, monitoring and eval Post Limited 6,530.00 0.00 2023-06-22 2023-06-27 2023-07-18 2023-08-22 2024-02-18 ant Selection ntation n financiera uation AR-UCAR-368893-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme IBRD / 88670 Post Limited 6,560.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 Consultor/a técnica en derec ination, monitoring and eval ant Selection ntation ho uation AR-UCAR-368900-CS-INDV / Component 4 - Project coord 3 Consultores/as técnicos/as Individual Consult Pending Impleme IBRD / 88670 ination, monitoring and eval Post Limited 17,400.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 en procesos de contratacione ant Selection ntation uation s y gestiones administrativas AR-UCAR-368935-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme Consultor/a especialista en G IBRD / 88670 ination, monitoring and eval Post Limited 15,370.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation estión presupuestaria uation AR-UCAR-368940-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme 2 Consultores/as técnicas en IBRD / 88670 ination, monitoring and eval Post Limited 10,870.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation gestión presupuestaria uation AR-UCAR-368941-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme Consultor/a técnica en gestió IBRD / 88670 ination, monitoring and eval Post Limited 4,900.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation n de desembolsos y subejecu uation ciones AR-UCAR-368944-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme Consultor/a técnico en Comu IBRD / 88670 ination, monitoring and eval Post Limited 6,000.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation nicación y Difusión de proyec uation tos AR-UCAR-368946-CS-INDV / Component 4 - Project coord Individual Consult Pending Impleme 3 Consultores/as técnicos/as IBRD / 88670 ination, monitoring and eval Post Limited 19,610.00 0.00 2023-06-23 2023-06-28 2023-07-19 2023-08-23 2024-02-19 ant Selection ntation en procesos de adquisiciones uation Page 9 Procurement Plan For Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project A World Bank Financed Project Project ID: P165129 [Procurement Plan Period: First 18 months of the Project] Covering the Period: January 2020 to June 2021 Submitted By Project Management Unit [PMU] Himachal Pradesh Forest Department Government of Himachal Pradesh India 2 3 PROCUREMENT PLAN Country: INDIA Borrower: Government of India on behalf of Government of Himachal Pradesh Project Name: Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project Project Implementation Agency: Project Management Unit [PMU], Himachal Pradesh Forestry Department [HPFD], Government of Himachal Pradesh Date of General Procurement Notice: December 18, 2019 Bank’s Approval Date of the Procurement Plan: Original … Revision 1: Revision 2: Date of the Procurement Plan: December 2019 Period covered by this Procurement Plan: January 2020 to June 2021 Applicable Procurement Rules. The Procurement of goods, works, consulting and non-consulting services to be financed by the Loan will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers [dated July 2016; revised November 2017 and August 2018], and the provisions of the Loan Agreement. If there is conflict between government decrees, rules, and regulations and the Bank Procurement Regulations, then Bank’s Procurement Regulations shall prevail. The project will be subject to World Bank Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants [“Anti-Corruption Guidelines”], dated October 15, 2006 and revised in January 2011 and as of July 1, 2016. The project will use the online tool Systematic Tracking of Exchanges in Procurement [STEP] to prepare, clear, and update its procurement plan, for monitoring procurement activities and for communication between the Borrower and the Bank. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under Paragraph 4.4 of the Procurement Regulations are set forth in STEP. Unless otherwise agreed with the World Bank, the World Bank’s Standard Procurement Documents [SPD], Requests for Proposals, and Forms of Consultant Contract will be used. Procurement under national procedures will be carried out based on National Procurement Procedures [NPP] conditions agreed with the Government of India. Procurement estimated at Indian Rupees [INR] 5 Lakhs and above will be submitted through government eProcurement systems provided by NIC 4 www.hptender.gov.in which have been assessed and deemed acceptable by the Bank against Multilateral Development Bank [MDB] requirements. Financial Management [FM] Manual. The FM Manual prepared for the project shall have a separate chapter on Procurement which will provide clear guidance on applicable procurement arrangement, procedures and thresholds, and shall be made available on the project website. Community Operations Manual [COM]. The COM prepared for the project will have clear directives for the community [GPs/individual beneficiaries] with regard to eligible procurement expenditures and agreed procurement arrangements, procedures and thresholds, and shall be made available on the project website. This will serve as a guidebook for procurement, with a view to providing operating instructions and bring in greater transparency and predictability in procurement procedures under the Project. Procurement Arrangements and Profile. Procurement under the Project will be carried out at the central level by the Project Management Unit [PMU] headed by the Chief Project Director [CPD] established for the Project, at the District level by the District Project Officers assisted by the Accounts Assistant at the District Level in each of the 10 District Project Offices [DPOs] located in the Districts covered under the Project [Shimla, Solan, Sirmour, Bilaspur, Hamirpur, Mandi, Kullu, Chamba, Kangra and Una], and by beneficiary GPs [supported by DPOs] at the GP level, in accordance with their approved Gram Panchayat Resource Management Plans [GP-RMP]/MG/OMIF. Officials of the PMU have prior experience of implementing a World Bank financed project and have also undergone training in STEP. GPs will need to be capacitated and provided basic procurement training on applicable procurement procedures and procurement documentation requirements outlined in COM, before initiating their procurements. To meet the readiness requirements of the Department of Economic Affairs [DEA] of the Government of India, the Project has already initiated and awarded contract for critical consultancy package for Environmental and Social Assessment to be retroactively financed by the Bank. The project envisages procurement of low-risk, low-value goods, works and services as below: a. Goods and Non-Consulting Services to be procured under the project are likely to include the following. At State/PMU level, purchase of IT Equipment such laptops, computers, printer, etc., procurement of printing services for IEC, office vehicles, office furniture, etc. are envisaged. At District and GP level, procurement activities will include procurement of Barbed Wire, U/Staple, Tools, Gunny Bags, Vermicompost/ Farm yard Manure, Sand, Seeds, Wooden posts/ poles, Seedlings, Grass tufts, Sign boards/hand prints, seed testing instrument, Seed, Fertilizer, Pesticide, Livestock - Small and Large Ruminants, Agricultural Tools and Implements, equipment, Farm machinery, e.g., power tiller, chaff cutters, pipes, tarpaulins, Medicines, supplements, sprinklers, seedlings, etc. b. Procurement of Minor Civil Works is likely to include the following. At State/ PMU level, procurement of minor civil works will include extension, refurbishment and repair of office buildings, etc. At District and GP level, procurement activities will include procurement of works for construction of Water storage tanks, water channels, vermicompost pits, livestock Mangers, foot bridges, water lifting pumps, GI pipes, accessories, installation of ropeways, Ponds, Check Dams, Subsurface Dykes, Sump Wells etc. and labor contracts for preparing land 5 for nursery, preparing nursery beds, water tank, works of filling gunny bags, sowing of seeds, preparing temporary nursery sheds, watering, hoeing, weeding, , fencing, bush cutting, pit digging, planting seedlings, preparing contour trenches, planting grass tufts, drainage line treatment works, fire management works, allowances and incentives for fire management, Spring development, eradication of exotic weed- lantana, etc. It may be noted that civil works at GP level are demand driven. There are no major civil works contracts envisaged in the project. c. Consultancy Services to be procured under the project are likely to include services for developing a web-based portal for Integrated Financial Management Information System [IFMS], Water Monitoring and Modelling, Value Chain Scoping Studies, Technical Support Study for addressing the needs of Transhumant, M and E, MIS, Baseline Survey, External and Internal Audit, Third Party Verification agent to verify achievement of Disbursement Related Results [DLR]s, need based assessments and studies, individual experts, etc. No consultancy services contracts envisaged at the District/Sub-district levels. The project includes several features of a decentralized, demand-driven project, and activities to be taken up at the community level by selected beneficiaries shall be as per the GP-RMP approved by the PMU of the HP Forestry Department/MG/OMIF. The threshold of procurement activities at community level is expected not to exceed Request for Quotation [RFQ] threshold. Community-level procurement shall follow Community-Driven Development [CDD] arrangements as per the Bank’s Procurement Regulations and as outlined in the Community Operations Manual [COM] currently under preparation. Given other on-going government programs, the activities to be funded following COM shall be identified upfront to avoid double-dipping and will require very close monitoring and oversight. Project Procurement Strategy for Development [PPSD] and Procurement Plan. According to the requirement of the Regulations, a Project Procurement Strategy for Development [PPSD] has been developed, based on which the Procurement Plan for the first 18 months has been prepared. The PPSD describes how procurement in this project will support the Project Development Objective [PDO] and deliver value for money under a risk-based approach. It provides adequate supporting market analysis for the selection methods detailed in the procurement plan. The procurement plan specifies for each contract: [i] a description of the activities/contracts; [ii] selection methods to be applied; [iii] estimated cost; [iv] time schedules; [v] World Bank review requirements; and [vi] any other relevant procurement information. PMU shall submit to the World Bank, for its review and approval, any updates of the procurement plan approved by the World Bank. The project will use Systematic Tracking of Exchanges in Procurement [STEP] system for all its procurement activities carried out at the PMU [Centre] and District levels. Summary from PPSD. The project is preparing its Procurement Strategy document. As per the draft document, the project’s total value is US $100 million of which procurement spend is approximately 80 %. Extensive market analysis has been carried out for procurement packages and decisions on packages are made to ensure adequate participation of bidders. Consultancy contracts are framed based on market research and packaging decided in terms of scope of services and period. Based on the need assessment, the project has decided to 6 use Government e Marketplace [GeM]1 for procurement of Goods up to US $100,000 and as mentioned under the paragraph in the Procurement Plan on National Procurement Procedures. Procurement Capacity Building. Though project staff has past experience of implementing World Bank financed HP Mid-Himalayan Watershed Development Project [HPMHWDP] governed by the Bank’s Procurement Guidelines, however, they need to be exposed to the Procurement Regulations applicable to the Project. HP Forestry Department will be sending key procurement staff of PMU and DPOs to the Indian Institute of Management [IIM], Lucknow or the Administrative Staff College of India [ASCI], Hyderabad from time to time to attend procurement training on World Bank Procurement Framework [PF] applicable to the project. Presently, project staff from PMU and two DPOs will be attending the two-week residential training program on World Bank Procurement Regulations conducted at ASCI, Hyderabad in February 2020. These officials will subsequently provide training to other project staffs prior to implementation of the procurement activities in the project. The PMU/DPOs/APOs will also provide basic procurement training to GPs/Beneficiaries once the Gram Panchayat Resource Management Plan [GP-RMP] is approved by DPO/PMU, and before commencing implementation of GP-RMP. The project officials can also avail of the free Massive Open Online Course on public procurement www.procurementlearning.org offered by the Bank to build their capacity. The Bank had already conducted one training on STEP for PMU officials and will organize STEP training again on need basis for the concerned DPOs staff in near future. Procurement Planning. For each contract to be financed by the Loan, the different procurement methods or consultant selection methods to be used, the need for pre-qualification, estimated costs, prior review requirements, and time frame will be reflected in the Procurement Plan to be agreed between the Borrower and the Bank team. The Procurement Plan will be uploaded in STEP by PMU/DPOs and the approved procurement plan will be disclosed on the project website and Bank’s external website. The procurement plan for the first 18 months of project implementation and all its updates will be submitted to the Bank through STEP, and will lay out the appropriate, fit for purpose market approach and selection methods for procurement of goods, works, non-consulting and consulting services financed by the Bank. It will be updated at least annually or as required to reflect the actual project implementation needs and improvements in institutional capacity. eProcurement. Currently, the Himachal Pradesh Forestry Department of the Government of Himachal Pradesh is using e-procurement system for its procurement. However, PMU housed in the Forestry Department will be carrying out procurement using eProcurement for the first time in the project, therefore, their capacity building needs to be done for eProcurement. The project will make use of Government of India’s National Informatics Centre [NIC] platform assessed by the Bank against Multilateral Development Bank [MDB] requirements for procurements estimated at INR 5 Lakhs and above. Advance Contracting with Retroactive Financing. For effective project implementation and start-up, the project has initiated advance contracting of critical consultancies for Preparation of Environmental and Social Framework [ESF] and Project Implementation Plan [PIP], and procurement of small value goods such 1 https://gem.gov.in/ 7 as tools, gunny bags, seeds, IT equipment and accessories, vehicles, etc.] and works [very small value labor contracts for Development of Nurseries [52 nos.] in 26 clusters in 10 Districts covering 428 GPs. The total value of this spend is approximately 1.2 % of the Bank loan. Payment made by PMU/HPFD for these contracts following World Bank procurement procedures during the 12 months prior to the tentative Loan signing date shall be eligible for retroactive financing. Record Keeping. All records pertaining to award of tenders/selection of consultants, including tender notification/advertisement, register pertaining to sale and receipt of bids, bid/proposal opening minutes, bid/technical and financial evaluation reports, comparative statements, Goods, Receipt Note [GRN] and all correspondence pertaining to bid evaluation, communication sent to/with the Bank in the process, bid securities, and approval of invitation/evaluation of bids/proposals would be maintained by the PMU and at DPO/GP level. Contract Management. The PMU, HPFD will be responsible for overall procurement and contract management under the project. At the Centre, procurement staff will be responsible for contract monitoring and supervision of contracts awarded by PMU. At DPO level, contract monitoring and supervision will be done by technical staff at DPOs/APOs level [Agriculture, Animal Husbandry/Engineering staff of technical wing of DPO level and Forest Extension and Social Extension staff at APO level] to ensure timely delivery of quality outputs from the procurement contracts in the project areas. All payments will be made by DPOs for district and sub-district level procurements after receipt of Goods receipt Note [GRN]. Work Completion Certificates, etc. The Integrated Financial Management Information System [IFMIS] being developed under the Project will facilitate monitoring of various procurement activities in terms of physical and financial achievements on a monthly basis. The day to day monitoring of procurement activities will be done by APOs/DPOs at field level which will be updated in the online web-based system at district level and will be reviewed by PMU at the Centre. Complaint Handling Mechanism. A complaint handling mechanism to address procurement-related complaints under the Project will be developed and implemented by the PMU/DPOs to the satisfaction of the Bank. Upon receipt of complaints, immediate action would be initiated to acknowledge the complaint and to redress it within a reasonable timeframe. All complaints will be addressed at levels higher than the level at which the procurement process was undertaken, or the decision was taken. Any complaint received will also be forwarded to the Bank for information, and the Bank would be kept informed after the complaint is redressed. Leased Assets: Not Applicable Procurement of Secondhand Goods: Not Applicable Domestic Preference: The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement Thresholds and Prior Review Thresholds. The table below describes various procurement methods to be used for activities financed by the Loan. 8 Table 1: Procurement Thresholds Procurement approach and method Thresholds [US$ equivalent] Open International [Goods, IT, and >10 million Non-consulting services] – Request for Bids [RFB] Open National [Goods, IT, and Non- >100,000 and up to 10 million consulting services] – Request for Bids [RFB] National Request for Quotation Up to 100,000 [RFQ] – [Goods/Works/Non- consulting Services] Open International [Works] – >40 million Request for Bids [RFB] Open National [Works] - Request for >100,000 and up to 40 million Bids [RFB] Direct Selection With prior agreement, based on justification Framework Agreement For Goods/Works/Non-consulting services: According to paragraphs 6.57-6.59 of Section VI of the Regulations. For Consulting services: According to paragraph 7.33 of Section VII the Regulations. Force Account In accordance with paragraphs 6.54 and 6.55 of Section VI of the Procurement Regulations, and with prior agreement in Procurement plan with the Bank. Consulting Services [Firms] CQS: As per requirements of paragraphs 7.11 and 7.12 of Section VII of the Regulations. LCS, FBS: in justified cases QCBS, QBS: in all other packages Shortlist of National Consultants Up to 800,000 Procurement prior-review thresholds2. Based on the current procurement risk rating of ‘Moderate’, the World Bank will prior review the following contracts: (a) Works [including turnkey, supply and installation of plant and equipment and PPP]: All contracts more than US $15 million equivalent 2 Determination of whether a contract meets the prior review threshold is based on : (i) the total value of the contract, including all taxes and duties payable under the contract; (ii) a contract whose cost estimate was below the Bank’s prior review threshold is subject to prior review if the price of the lowest evaluated responsive bid (or, in the case of consulting services, the financial offer of the selected firm) exceeds such threshold at the bid evaluation stage; and (iii) in the case of a slice and package arrangement, the prior review threshold is determined based on the aggregate value of individual contracts to be awarded under such arrangement. 9 (b) Goods and Information Technology: All contracts > US $4 million equivalent (c) Non-consulting Services: All contracts > US $4 million equivalent (d) Consulting Services: Firms: All contracts >US $2 million equivalent (e) Consulting Services: Individuals: All contracts > US $400,000 equivalent (f) Direct Selection: The justification of Direct Selection for all contracts The above thresholds are for the initial 18-month implementation period. Based on the procurement performance of the project, these thresholds may be subsequently modified. Even for large-value post review cases, the inputs of the World Bank on technical specifications will be obtained by the project. Irrespective of the thresholds, Terms of Reference shall be prior reviewed by Bank. The prior review thresholds will also be indicated in the Procurement Plan. The Procurement Plan will be subsequently updated annually [or at any other time if required] and will reflect any change in the prior review thresholds. The details of National Procurement Procedures are outlined in the Procurement Plan. Prior review contracts. In the case of contracts subject to prior review, PMU, HPFD/DPOs will seek the World Bank’s no objection before granting/agreeing to: [a] an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; [b] any substantial modification of the scope of Works, goods, IT system; non-consulting services, or consulting services and other significant changes to the terms and conditions of the contract; [c] any variation order or amendment [except in cases of extreme urgency] that, singly or combined with all variation orders or amendments previously issued, increases the original contract amount by more than 15 percent; and [d] the proposed termination of the contract. Complaints received in all prior review cases shall be sent to Bank for review and the response to the complaint in such cases, shall be cleared with the Bank. Complaints with allegations of fraud and corruption, shall be shared with Bank, irrespective of the thresholds. Disclosure of procurement information. The following documents shall be disclosed on the project/state websites: [a] Procurement Plan and its updates; [b] an invitation for bids for procurement of Works, Goods, IT system procurement and non-consulting services; [c] request for expression of interest for selection/hiring of consulting services; [d] contract awards of Works, Goods, IT system procurement and non-consulting services procured following international and national procedures; [e] a list of contracts/purchase orders placed following RFQ [Request for Quotation] procedures on a quarterly basis; [f] a list of contracts following direct contracting [DC] on a quarterly basis; [g] an annual financial and physical progress report of all contracts; and [h] an action taken report on the complaints received on a quarterly basis. The following details shall be sent to the World Bank for publishing on the United Nations Development Business and the World Bank external website: [a] Specific Procurement Notice [i.e., invitation for bids] for procurement of Works, Goods, IT system procurement and non-consulting services using open international procedures; [b] Requests for Expression of Interests above US $800,000; [c] contract award details of all procurement of Works, Goods, IT system procurement and non-consulting services using open international procedure; and [d] a list of contracts/purchase orders placed following DC procedures on a quarterly basis. Further, the implementing agency will also publish on their websites any information required under the provisions of ‘suo moto’ disclosure as specified by the Right to Information Act. 10 National Procurement Procedure Conditions. National competition for the procurement of Works, Goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: I. Only the model bidding documents for National Competitive Procurement [NCP] agreed with the GOI Task Force [and as amended for time to time], shall be used for bidding. II. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. III. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises or enterprises from any given State. IV. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. V. Government e-Marketplace [GeM] set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations [RFQ] method. VI. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. VII. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. VIII. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. IX. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. X. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social [including sexual exploitation and abuse and gender-based violence], health and safety [“ESHS”] risks and impacts. Oversight and Monitoring by the Bank. All contracts not covered under prior review by the Bank will be subject to post review during implementation support missions and/or special post review missions, including missions by consultants hired by the Bank. The Bank may conduct, at any time, Independent Procurement Reviews [IPRs] of all the contracts financed under the loan. High risk procurements, if any, will be identified for increased procurement and contract management support and indicated in the procurement plan. Bank team will provide additional due diligence and independent review of the contract performance of such identified procurements. 11 Procurement Review by the PMU, HPFD. Independent procurement post review [PPR] with reporting requirements and agreed with the Bank [As per Para 4 of Annex II of the Procurement Regulations] will be undertaken for the project for PMU’s own internal due diligence. PMU will hire PPR consultants as per Terms of Reference and reporting requirements agreed with the Bank to conduct PPR of PMU and DPOs on a half yearly basis. Other Special Selection Arrangements/Requirement Procurement by communities will be governed by the procedures outlined in the Community Operations Manual [COM] currently under preparation and in accordance with Paras 6.52 and 6.53 of Section VI of the Regulations. COM will be disclosed on the Project website. Procurement Plan as per STEP Tables: 12 PROCUREMENT India : Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2020-10-12 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-19 none) Project ID: P165129 GPN Date: 2019-12-19 Project Name: Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh Loan / Credit No: IBRD / 90410 District Project Office, Kangra, Himachal Pradesh Forestry Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-DPO, KANGRA-178845-C Component 1. Sustainable L W-RFQ / Development of Ne Request for Quota Single Stage - One E 2021-08-1 IBRD / 90410 and and Water Resource Ma Post Limited 3,850.00 3,915.49 Completed 2020-12-31 2020-02-26 2021-02-16 2020-03-18 w Nursery Site at Shivnagar tions nvelope 5 nagement under APO Panchrukhi IN-DPO, KANGRA-178850-C W-RFQ / Development of Ne Component 1. Sustainable L Request for Quota Single Stage - One E 2021-02-0 w Nursery Site at Tatehal un IBRD / 90410 and and Water Resource Ma Post Limited 2,580.00 2,609.88 Completed 2020-06-15 2020-02-26 2020-08-10 2020-03-17 tions nvelope 6 der APO Panchrukhi. this acti nagement vity is already completed and is bein uploaded now. IN-DPO, KANGRA-178852-C W-RFQ / Development of Ne Component 1. Sustainable L Request for Quota Single Stage - One E 2021-02-0 w Nursery Site at Ochha und IBRD / 90410 and and Water Resource Ma Post Limited 2,375.00 3,317.59 Completed 2020-06-15 2020-02-26 2020-08-10 2020-03-18 tions nvelope 6 er APO Nagrota. this activity i nagement s already executed and is bei ng uploaded now. IN-DPO, KANGRA-178853-C Component 1. Sustainable L W-RFQ / Raising of Seedling Request for Quota Single Stage - One E 2021-02-0 IBRD / 90410 and and Water Resource Ma Post Limited 3,250.00 3,891.04 Completed 2020-06-15 2020-02-27 2020-08-10 2020-03-18 at Shivnagar Nursery under A tions nvelope 6 nagement PO Unit Panchrukhi IN-DPO, KANGRA-178868-C Component 1. Sustainable L Request for Quota Single Stage - One E 2021-02-0 W-RFQ / Raising of seedlings IBRD / 90410 and and Water Resource Ma Post Limited 1,950.00 2,445.49 Completed 2020-06-15 2020-02-27 2020-08-10 2020-03-18 tions nvelope 6 in Tatehal Nursery under APO nagement Panchrukhi IN-DPO, KANGRA-178870-C W-RFQ / Raising of nursery s Component 1. Sustainable L Request for Quota Single Stage - One E 2021-02-0 eedling in Nursery Ochha un IBRD / 90410 and and Water Resource Ma Post Limited 1,950.00 4,059.04 Completed 2020-06-15 2020-02-27 2020-08-10 2020-03-18 tions nvelope 6 der APO Nagrota, this activity nagement is already completed is bein g uploaded now. IN-DPO, KANGRA-178886-C W-RFQ / CW-RFQ / Pre-monso on/ advance work for raising Component 1. Sustainable L of plantations along drainage Request for Quota Single Stage - One E 2020-10-0 IBRD / 90410 and and Water Resource Ma Post Limited 49,700.00 40,053.46 Completed 2020-06-15 2020-06-12 2020-08-06 2020-07-21 line (both side of stream) i.e. tions nvelope 5 nagement fencing of plantation area wit h wooden poles and barbed wire. There are 7 jobs (contra ct) at different locations havi ng 2 to 5 ha area. IN-DPO, KANGRA-178923-C W-RFQ / CW-RFQ / Pre-monso on/ advance work i.e. fencing of plantation area with wood Component 1. Sustainable L Request for Quota Single Stage - One E 2020-09-2 en fence post and barbed wir IBRD / 90410 and and Water Resource Ma Post Limited 29,800.00 28,812.77 Completed 2020-06-20 2020-06-12 2020-07-27 2020-07-21 tions nvelope 5 e for raising of plantation in t nagement he rainy season of 2020 in th e forest area having open ca nopy @ 800 plants per/ha. Th ere will be 7 jobs (contract). IN-DPO, KANGRA-178936-C W-RFQ / CW-RFQ / Pre-monso on/ advance work i.e. fencing Component 1. Sustainable L of plantation area with wood Request for Quota Single Stage - One E 2020-09-3 IBRD / 90410 and and Water Resource Ma Post Limited 25,000.00 23,504.96 Completed 2020-06-15 2020-06-12 2020-08-01 2020-07-21 en fence post and barbed wir tions nvelope 0 nagement e for raising of plantation in t he rainy season of 2020 in th e forest area to increase tree cover by planting 400 plants per/ha. IN-DPO, KANGRA-178947-C W-RFQ / Raising of plantation s In the rainy season of 2020 Component 1. Sustainable L along drainage line on both s Request for Quota Single Stage - One E 2020-10-1 IBRD / 90410 and and Water Resource Ma Post Limited 11,500.00 10,757.11 Completed 2020-06-20 2020-06-15 2020-07-31 2020-07-21 ide of stream with fast growi tions nvelope 4 nagement ng forestry species @ 1100 p lants per/ha is done in 17 ha . at 7 different sites . This act ivity is completed and being uploaded now. IN-DPO, KANGRA-178949-C W-RFQ / Raising of plantation s in the rainy season of 2020 in the forest area having ope Component 1. Sustainable L Request for Quota Single Stage - One E 2020-10-0 n canopy (tree density less t IBRD / 90410 and and Water Resource Ma Post Limited 25,100.00 23,035.61 Completed 2020-06-15 2020-06-15 2020-07-20 2020-07-21 tions nvelope 3 han 0.4) @ 800 plants per/ha nagement . There are jobs (contract) of 2 to 10 ha area in different c atchments. The work is comp leted and being uploaded no w IN-DPO, KANGRA-178955-C W-RFQ / Raising of plantation s in the rainy season of 2020 Component 1. Sustainable L Request for Quota Single Stage - One E 2020-10-1 in the forest area were initia IBRD / 90410 and and Water Resource Ma Post Limited 11,700.00 10,821.40 Completed 2020-06-15 2020-06-15 2020-07-30 2020-07-21 tions nvelope 3 ted in 39 ha @ 400 plants pe nagement r/ha. There are fix jobs (contr act) of 4 to 10 ha area in diff erent catchment. IN-DPO, KANGRA-178956-C W-RFQ / Pre-winter/ advance work i.e. fencing of plantatio Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-2 n area with wooden fence po IBRD / 90410 and and Water Resource Ma Post Limited 6,400.00 5,570.93 Completed 2020-12-03 2020-10-28 2020-12-29 2020-12-02 tions nvelope 9 st and barbed wire for raising nagement of plantation in the winter se ason of 2020 in the forest ar ea having open canopy @ 80 0 plants per/ha. Page 1 IN-DPO, KANGRA-178968-C W-RFQ / Contour trenching in plantation area including gra Component 1. Sustainable L Request for Quota Single Stage - One E 2021-02-1 ss seeding in 106 ha. This act IBRD / 90410 and and Water Resource Ma Post Limited 22,900.00 23,120.17 Completed 2020-07-14 2020-06-15 2020-08-21 2020-07-21 tions nvelope 7 ivity has been executed and nagement being uploaded now. there ar e 14 jobs (contract) involving 14 sites at different locations . IN-DPO, KANGRA-178983-C W-RFQ / Treatment of Draina Component 1. Sustainable L ge Line (Soil Conservation W Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 475,300.00 513,325.37 Completed 2020-12-05 2020-12-16 2021-01-30 2022-01-02 orks) by constricting Vegetati tions nvelope 1 nagement ve check barriers, Dry stone check barriers, Create Wire c heck barriers, CC check barri ers IN-DPO, KANGRA-178984-C W-RFQ / Renovation and impr ovement of already existing Natural Water Sources (Well, Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-2 springs, traditional water bau IBRD / 90410 and and Water Resource Ma Post Limited 53,500.00 51,464.62 Completed 2020-12-20 2021-04-09 2021-01-27 2021-02-27 tions nvelope 8 ries,etc) and to improve the nagement water availability and hydro-l ogical health there will be 30 to 50 different jobs (contract s) in different locations. IN-DPO, KANGRA-178985-C W-RFQ / Management of exot Component 1. Sustainable L ic species - Removal of Lanta Request for Quota Single Stage - One E 2021-03-2 IBRD / 90410 and and Water Resource Ma Post Limited 110,450.00 114,050.24 Completed 2020-11-20 2020-10-28 2021-01-08 2020-12-02 na from target area by cut r tions nvelope 4 nagement oot stock method (75 to 100 % ) in 215 ha. at 25 to 35 diff erent locations IN-DPO, KANGRA-179055-C W-RFQ / three nurseries shall Component 1. Sustainable L be developed Baldhar in clus Request for Quota Single Stage - One E 2021-03-2 IBRD / 90410 and and Water Resource Ma Post Limited 6,000.00 5,953.51 Signed 2020-11-20 2020-10-28 2020-12-21 2020-11-22 ter- I under APO Nagrotabag tions nvelope 1 nagement wan and two under APO Baij nath shall be done cluster wi se at Shodgun and Kandwari . IN-DPO, KANGRA-179064-C W-RFQ / The raising of seedli ngs in six nurseries will be d Component 1. Sustainable L Request for Quota Single Stage - One E 2021-06-3 one during the financial yea IBRD / 90410 and and Water Resource Ma Post Limited 70,000.00 70,679.05 Signed 2020-11-20 2020-10-28 2021-01-01 2020-11-22 tions nvelope 0 r 2020-21 for planting during nagement 2021-22. Total 315000 seedli ngs will be raised at differen t location . IN-DPO, KANGRA-179083-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta Component 1. Sustainable L tion area with wooden fence Request for Quota Single Stage - One E 2021-10-2 IBRD / 90410 and and Water Resource Ma Post Limited 231,400.00 207,025.52 Completed 2021-06-25 2021-06-04 2021-07-24 2021-06-29 post and barbed wire for raisi tions nvelope 2 nagement ng of plantation in the rainy s eason of 2021 in the forest a rea to increase tree cover by planting 400 plants per/ha. IN-DPO, KANGRA-179091-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta Component 1. Sustainable L tion area with wooden fence Request for Quota Single Stage - One E 2021-10-1 IBRD / 90410 and and Water Resource Ma Post Limited 63,400.00 59,789.11 Completed 2021-06-20 2021-06-04 2021-07-19 2021-06-29 post and barbed wire for raisi tions nvelope 7 nagement ng of plantation in the rainy s eason of 2021 in the forest a rea having open canopy @ 8 00 plants per/ha. IN-DPO, KANGRA-179094-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta Component 1. Sustainable L tion area with wooden fence Request for Quota Single Stage - One E 2021-10-0 IBRD / 90410 and and Water Resource Ma Post Limited 260,000.00 132,026.01 Completed 2021-06-10 2021-06-04 2021-07-09 2021-06-29 post and barbed wire for raisi tions nvelope 7 nagement ng of D.L.T. plantations@ 11 00 plants per/ha in 83 ha dur ing the rainy season of 2021 for treatment of 44 different drainage lines IN-DPO, KANGRA-179096-C Component 1. Sustainable L W-RFQ / Contour trenching in Request for Quota Single Stage - One E 2022-01-2 IBRD / 90410 and and Water Resource Ma Post Limited 115,560.00 109,176.29 Completed 2021-06-09 2021-05-05 2021-07-29 2021-06-29 plantation area including gra tions nvelope 5 nagement ss seeding. there will be 35 t o 50 jobs (contract). IN-DPO, KANGRA-179110-C W-RFQ / Repair, Maintenance and Wood ceiling/ Paneling of Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-1 DPO Residence Dharamshala IBRD / 90410 and and Water Resource Ma Post Limited 8,000.00 4,490.61 Completed 2020-11-05 2020-06-12 2020-11-18 2020-11-10 tions nvelope 8 , Electric, sanitary , flooring nagement & distemper painting and ot her minor repair etc. there wi ll be 4 to 5 jobs. IN-DPO, KANGRA-182918-C W-RFQ / Procurement of Nurs ery Plants. 25000 nursery pla nts,17000 Dendrocalamus str Component 1. Sustainable L Request for Quota Single Stage - One E 2020-09-2 ictus (Bamboo) ,4000 Phyllan IBRD / 90410 and and Water Resource Ma Post Limited 5,000.00 4,754.14 Completed 2020-07-14 2020-06-12 2020-08-21 2020-07-14 tions nvelope 0 thus emblica (Amla) and 400 nagement 0 Szygium cumini have been procured during July ,2020 f or use in plantations during monsoon season. IN-DPO, KANGRA-184075-C W-RFQ / Primary water harve Component 1. Sustainable L sting and storage, constructi Request for Quota Single Stage - One E 2021-05-2 IBRD / 90410 and and Water Resource Ma Post Limited 36,180.00 19,081.26 Completed 2020-12-20 2021-02-26 2021-01-27 2021-03-02 on of ponds manual excavati tions nvelope 7 nagement on.there will be 15 to 20 diffe rent jobs (contracts) in differ ent locations. IN-DPO, KANGRA-184183-C W-RFQ / Management of exot Component 1. Sustainable L ic species Removal of Lanta Request for Quota Single Stage - One E 2021-03-2 IBRD / 90410 and and Water Resource Ma Post Limited 48,800.00 49,974.66 Completed 2020-11-20 2020-10-28 2021-01-08 2020-12-02 na from targeted area infeste tions nvelope 4 nagement d with lantana 50% to 75% b y cut root stock method in 1 16ha. IN-DPO, KANGRA-184184-C W-RFQ / Management of exot ic species - Removal of Lanta Component 1. Sustainable L na from target area by cut r Request for Quota Single Stage - One E 2021-03-2 IBRD / 90410 and and Water Resource Ma Post Limited 18,500.00 18,994.95 Completed 2020-10-05 2020-10-28 2020-11-23 2020-12-02 oot stock method with lantan tions nvelope 3 nagement a infestation 25 to 50% in 56 ha There will be six no's of di fferent jobs (contracts) at six different locations. Page 2 IN-DPO, KANGRA-184185-C W-RFQ / Management of exot Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-1 ic species - Removal of Lanta IBRD / 90410 and and Water Resource Ma Post Limited 3,655.00 3,753.71 Completed 2020-12-05 2020-10-28 2021-01-09 2020-12-02 tions nvelope 0 na from target area by cut r nagement oot stock method (up to 25% ) IN-DPO, KANGRA-189862-C W-RFQ / The grass sowing/ tu ft planting along drainage lin Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-2 e plantations in 17 ha area at IBRD / 90410 and and Water Resource Ma Post Limited 2,180.00 2,244.60 Completed 2020-12-25 2020-10-28 2021-01-23 2020-12-02 tions nvelope 4 seven different locations in s nagement hall be been done during 202 0-21 using RFQ separately fo r each location . IN-DPO, KANGRA-178966-C W-RFQ / Pre-winter/ advance work i.e. fencing of plantatio Component 1. Sustainable L Request for Quota Single Stage - One E 2021-03-2 n area with wooden fence po IBRD / 90410 and and Water Resource Ma Post Limited 6,400.00 3,196.31 Completed 2020-12-03 2020-10-28 2020-12-26 2020-12-02 tions nvelope 6 st and barbed wire for raising nagement of plantation in the winter se ason of 2020 in the forest ar ea having open canopy @ 40 0 plants per/ha. IN-DPO, KANGRA-204495-C W-DIR / Demonstration and p romotion of climate resilient Component 1. Sustainable L Request for Quota Single Stage - One E 2021-07-1 agriculture for Rabi crops sha IBRD / 90410 and and Water Resource Ma Post Limited 8,500.00 8,179.19 Completed 2020-11-25 2020-10-23 2021-01-20 2021-05-06 tions nvelope 9 ll be done by involving lead f nagement armers and through institutio nal partnership with partner i nstitutions like SAU,KVK's. IN-DPO, KANGRA-220266-C W-RFQ / Raising of plantation Component 1. Sustainable L s in the winter season of 202 Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 4,850.00 4,926.35 Completed 2021-02-19 2020-10-28 2021-03-09 2020-12-02 0-21 in the forest area UP107 tions nvelope 1 nagement p Nadli in GP Tatehal were ini tiated in 10ha @ 800 Plants p er/ha. IN-DPO, KANGRA-220267-C W-RFQ / Raising of plantation Component 1. Sustainable L Request for Quota Single Stage - One E 2021-04-0 s in the winter season of 202 IBRD / 90410 and and Water Resource Ma Post Limited 2,585.00 2,622.84 Completed 2021-02-19 2020-10-28 2021-03-10 2020-12-02 tions nvelope 1 0-21 in the forest area =10 h nagement a. Shajmlat Chombu in GP G adiyara @ 400 plants per/ha. IN-DPO, KANGRA-220272-C W-RFQ / Primary water harve Component 1. Sustainable L sting and storage, constructi Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 66,700.00 88,901.34 Completed 2021-02-18 2021-02-05 2021-03-11 2021-03-02 on of ponds manual excavati tions nvelope 1 nagement on.there will be 31 different j obs (contracts) in different lo cations. IN-DPO, KANGRA-220275-C W-RFQ / Renovation and impr ovement of already existing Component 1. Sustainable L Natural Water Sources (Well, Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 17,850.00 4,371.35 Signed 2021-02-19 2022-01-01 2021-03-10 2022-01-30 springs, traditional water bau tions nvelope 0 nagement ries,etc) and to improve the water availability and hydro-l ogical health there will be 8 different jobs (contracts) in d ifferent locations. IN-DPO, KANGRA-220279-C Component 1. Sustainable L W-RFQ / Treatment of Draina Request for Quota Single Stage - One E 2021-03-3 IBRD / 90410 and and Water Resource Ma Post Limited 50,000.00 46,477.59 Completed 2021-02-19 2021-02-12 2021-03-10 2021-03-02 ge Line (Soil Conservation W tions nvelope 0 nagement orks) by constricting CC che ck barriers. IN-DPO, KANGRA-236896-C W-RFQ / Raising of plantation s is proposed during the rain y season of 2021 in the fores Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E 2021-09-1 t area having open canopy (t IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 60,000.00 53,282.61 Completed 2021-05-27 2021-06-04 2021-07-06 2021-06-29 tions nvelope 9 ree density less than 0.4)@ 8 nagement PD) 00 plants per/ha . There will be 20 to 30 jobs (contracts) o f 2 to 10 ha area in different GP's in Kangra District. IN-DPO, KANGRA-236909-C W-RFQ / Raising of plantation s during the rainy season of 2021 along drainage line on Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E 2021-09-2 both side of stream with fast IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 63,000.00 61,857.43 Completed 2021-06-02 2021-06-07 2021-07-13 2021-07-06 tions nvelope 6 growing forestry species @ 1 nagement PD) 100 plants per/ha is to be do ne in 83 ha. There will be 4 0to 50 jobs (contracts) of 1 t o 5 ha.at different site. IN-DPO, KANGRA-236910-C W-RFQ / Contour trenching in Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E 2022-02-0 forest areas outside the plant IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 23,900.00 25,236.94 Completed 2021-06-24 2021-08-18 2021-08-13 2021-10-05 tions nvelope 9 ation area including grass se nagement PD) eding. there will be 15 to 20 j obs (contract). IN-DPO, KANGRA-236912-C W-RFQ / The grass sowing/ tu ft planting along drainage lin Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E 2021-09-2 e plantation areas in 83ha ar IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 11,900.00 10,521.66 Completed 2021-06-25 2021-06-07 2021-07-24 2021-07-06 tions nvelope 2 ea at different locations in sh nagement PD) all be been done during 2021 -22 using RFQ separately for each location . IN-DPO, KANGRA-236914-C W-RFQ / First year maintenan ce of 389 ha. plantation area Component 1. Sustainable L Request for Quota s done during 2020-21 under Request for Quota Single Stage - One E 2021-09-1 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 45,000.00 47,465.56 Completed 2021-06-20 2021-06-07 2021-07-17 2021-06-29 different schemes i.e. draina tions nvelope 5 nagement PD) ge line treatment=103ha. ,re -afforestation=137ha. and en richment plantations=149ha. in district Kangra. IN-DPO, KANGRA-236917-C W-RFQ / Management of exot ic species -2nd year activity i Component 1. Sustainable L Request for Quota n the targeted area in 551 h Request for Quota Single Stage - One E 2022-03-1 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 42,900.00 40,950.03 Signed 2021-06-02 2021-06-04 2021-07-21 2021-07-08 a and 3rd year activity in the tions nvelope 8 nagement PD) targeted area in 73 ha, wher e removal of Lantana was do ne by cut root stock during t he year 2020-21 and 2019-2 0 respectively. Page 3 IN-DPO, KANGRA-237217-C W-RFQ / Removal of Lantana Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E 2022-03-2 from target area by cut root IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 52,190.00 67,618.47 Completed 2021-10-05 2021-09-24 2021-11-23 2022-01-12 tions nvelope 3 stock method (75 to 100% ) i nagement PD) n 110 ha. at 10 to 20 differen t locations IN-DPO, KANGRA-237254-C W-RFQ / Treatment of Draina ge Line by vegetative check Component 1. Sustainable L Request for Quota barriers. Vegetative check ba Request for Quota Single Stage - One E 2022-02-2 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 10,000.00 6,788.03 Completed 2021-12-18 2022-01-01 2022-01-14 2022-01-28 rriers shall be provided by us tions nvelope 8 nagement PD) ing local species capable of s prouting in small and mediu m gullies having side slopes l ess than 45 degrees. IN-DPO, KANGRA-237259-C W-RFQ / filling of P/bags for r aising of seedling in eight nur Component 1. Sustainable L Request for Quota series at different location in Request for Quota Single Stage - One E 2022-02-1 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 70,000.00 27,587.78 Completed 2021-09-06 2021-12-06 2021-10-18 2022-04-01 all four units during 2021-22 tions nvelope 5 nagement PD) for raising of new planting , maintenance of plantation ar eas and Agri-silvi pasture dis tribution@ 500 seedling per GP during 2022-23. IN-DPO, KANGRA-237260-C W-RFQ / Raising and mainten ance of seedling in p/bags in Component 1. Sustainable L Request for Quota all eight nurseries at differen Request for Quota Single Stage - One E 2022-09-1 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 55,000.00 35,943.34 Completed 2021-10-04 2021-12-06 2021-11-15 2022-02-26 t location in all four units for tions nvelope 1 nagement PD) new planting , maintenance of plantation areas and Agri- silvi pasture distribution@ 50 0 seedling per GP during 202 2-23. IN-DPO, KANGRA-237268-C W-RFQ / Demonstration and promotion of climate resilient Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E Under Imple 2022-06-2 agriculture shall be done by i IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 43,000.00 0.00 2021-06-30 2022-04-04 2021-08-25 tions nvelope mentation 1 nvolving lead farmers and th nagement PD) rough institutional partnershi p with partner institutions lik e SAU,KVK's and Dr. YSP UHF . IN-DPO, KANGRA-237269-C W-RFQ / Secondary water dis tribution and water use effici Component 1. Sustainable L Request for Quota ency with tanks, channels, sp Request for Quota Single Stage - One E Under Imple 2022-03-2 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 70,000.00 0.00 2021-09-20 2022-08-24 2021-10-17 rinklers etc and by constructi tions nvelope mentation 6 nagement PD) ng water harvesting, storage and distribution infrastructur e shall be developed to incre ase the water productivity . IN-DPO, KANGRA-237270-C W-RFQ / Primary Water Distri Component 1. Sustainable L Request for Quota Request for Quota Single Stage - One E Under Imple 2022-03-3 bution (Pipes & Pumps) for g IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 27,600.00 0.00 2021-10-05 2022-09-16 2021-11-01 tions nvelope mentation 1 ravity and lift intake distribut nagement PD) ion system from primary wat er harvesting structures. IN-DPO, KANGRA-237272-C W-RFQ / construction of 10 to 12 foot bridges in different G Component 1. Sustainable L ram Panchayat in the Project Request for Quota Single Stage - One E Other (with field f 2022-03-2 IBRD / 90410 and and Water Resource Ma Post Limited 20,500.00 10,275.33 Completed 2021-11-06 2022-01-24 2021-12-21 2022-03-04 area of Kangra District to im tions nvelope or explanation) 1 nagement prove connectivity of the far mers from poor accessibility areas with the market for sup ply of inputs and sale of prod uce . IN-DPO, KANGRA-237234-C W-RFQ / Construction of CC c heck barriers for treatment o Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-0 f Drainage Line . There will b IBRD / 90410 and and Water Resource Ma Post Limited 99,300.00 31,388.08 Completed 2021-10-16 2022-01-27 2021-11-04 2022-03-18 tions nvelope or explanation) 4 e 40 to 50 Different jobs (Con nagement tracts) in different Gram Pan chayats in the selected Drai nage lines of the entire distri ct. IN-DPO, KANGRA-237228-C W-RFQ / Construction of 40 t o 50 ponds is proposed for Pr Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-1 imary water harvesting and s IBRD / 90410 and and Water Resource Ma Post Limited 97,800.00 65,614.57 Completed 2021-10-05 2022-03-01 2021-11-12 2022-02-20 tions nvelope or explanation) 2 torage at different locations nagement for harvesting rain water in the Project area in selected G P's of Kangra district . IN-DPO, KANGRA-237218-C W-RFQ / Renovation and impr ovement of 55 already existi ng Natural Water Sources (W Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-1 ell, springs, traditional water IBRD / 90410 and and Water Resource Ma Post Limited 94,000.00 77,381.09 Completed 2021-10-20 2022-01-24 2021-12-15 2022-02-22 tions nvelope or explanation) 5 bauries, etc ) to improve the nagement water availability and hydro-l ogical health ,there will be 5 5 different jobs (contracts) at different locations . IN-DPO, KANGRA-237252-C W-RFQ / Treatment of Draina Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 ge Line (Soil Conservation W IBRD / 90410 and and Water Resource Ma Post Limited 20,400.00 32,210.29 Completed 2021-10-05 2022-01-01 2021-11-30 2022-02-13 tions nvelope or explanation) 0 orks) by constricting dry ston nagement e check barriers check barrie rs in Panchrukhi unit . IN-DPO, KANGRA-237253-C W-RFQ / Treatment of Draina ge Line (Soil Conservation W Component 1. Sustainable L orks/civil structure treatment Request for Quota Single Stage - One E Other (with field f 2022-03-1 IBRD / 90410 and and Water Resource Ma Post Limited 95,000.00 108,780.97 Completed 2021-10-18 2022-01-24 2021-11-14 2022-03-01 ) by constructing crate wire c tions nvelope or explanation) 4 nagement heck barriers for retention of debris in gullies(drainage line ) receiving relatively large qu antity of run-off IN-DPO, KANGRA-236906-C W-RFQ / Raising of enrichme nt plantations is proposed un Component 1. Sustainable L der APO Dehra in Cluster - I Request for Quota Single Stage - One E Other (with field f 2021-09-2 IBRD / 90410 and and Water Resource Ma Post Limited 50,000.00 41,608.49 Completed 2021-05-27 2021-06-07 2021-07-11 2021-06-29 & II during the rainy season o tions nvelope or explanation) 4 nagement f 2021 in the forest area @ 4 00 plants per/ha . There are 12 jobs (contracts) of 9 to 15 ha area in different GP's in D ehra unit. Page 4 IN-DPO, KANGRA-237219-C W-RFQ / There will be 7-8 sit e specific different jobs (cont racts) for construction of ch Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-1 eck dams in the selected Dra IBRD / 90410 and and Water Resource Ma Post Limited 99,200.00 52,322.84 Completed 2021-11-05 2021-11-24 2021-12-02 2022-01-04 tions nvelope or explanation) 2 inage lines for Primary wate nagement r harvesting and storage by c onstructing cement concrete/ RCC check dam in the projec t area of Panchrukhi unit . IN-DPO, KANGRA-237216-C W-RFQ / Removal of Lantana from target area by cut root Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-0 stock method (75 to 100% ) i IBRD / 90410 and and Water Resource Ma Post Limited 79,500.00 74,151.32 Completed 2021-09-20 2021-09-24 2021-11-08 2021-11-12 tions nvelope or explanation) 8 n 140 ha. at 10 to 20 differen nagement t locations. There will be 10 t o 20 different jobs (contracts ) at different locations. IN-DPO, KANGRA-240030-C W-RFQ / Raising plantation is proposed in 85 ha. by plantin Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2021-09-1 g 400 plants per ha. in 8 GPs IBRD / 90410 and and Water Resource Ma Post Limited 28,500.00 28,385.74 Completed 2021-06-17 2021-06-05 2021-07-17 2021-07-06 tions nvelope or explanation) 5 of Baijnath unit there will be nagement 8 different jobs/contracts at different locations with area varying from 5 to 15 ha. at d ifferent sites. IN-DPO, KANGRA-240045-C W-RFQ / Enrichment plantati on is proposed in 80 ha area under APO Nagrota Bagwan Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2021-08-3 there will be 9 different jobs/ IBRD / 90410 and and Water Resource Ma Post Limited 26,500.00 22,393.13 Completed 2021-06-17 2021-06-04 2021-07-17 2021-06-29 tions nvelope or explanation) 1 contracts in different Gram P nagement anchayats of the unit in diff erent areas at different locati ons. Under this scheme 400 plants will be planted per ha. IN-DPO, KANGRA-240048-C W-RFQ / Monsoon planting of Enrichment plantation by pla Component 1. Sustainable L nting 400 plants per ha shall Request for Quota Single Stage - One E Other (with field f 2021-08-3 IBRD / 90410 and and Water Resource Ma Post Limited 21,500.00 17,344.04 Completed 2021-06-17 2021-06-07 2021-07-17 2021-06-29 be done in 64 ha area at 6 lo tions nvelope or explanation) 1 nagement cations in different GP's with area of 5 to 15 ha at each sit e in Panchrukhi unit of Kangr a district, there will be 6 diffe rent jobs/contracts . IN-DPO, KANGRA-240097-C W-RFQ / Renovation of existi ng village pond in GP Khaira Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2022-03-1 under Panchrukhi Unit is pro IBRD / 90410 and and Water Resource Ma Post Limited 67,600.00 0.00 2021-11-06 2022-05-28 2021-12-14 tions nvelope or explanation) mentation 4 posed by excavating earth , nagement forming embankments for ha rvesting rain water in the Pro ject area in Kangra district . IN-DPO, KANGRA-240099-C W-RFQ / Primary water harve sting and storage by renovat ing 4 existing ponds at differ Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-1 ent locations in GP Baddal, IBRD / 90410 and and Water Resource Ma Post Limited 60,000.00 17,747.44 Completed 2021-10-05 2021-12-10 2021-11-12 2021-12-30 tions nvelope or explanation) 2 Chanour and Bathal by exca nagement vating earth ,forming emban kments for harvesting rain w ater in the Project area in De hra unit of Kangra district . IN-DPO, KANGRA-240101-C W-RFQ / Treatment of Draina Component 1. Sustainable L ge Line (Soil Conservation W Request for Quota Single Stage - One E Other (with field f 2022-03-1 IBRD / 90410 and and Water Resource Ma Post Limited 40,700.00 35,424.02 Completed 2021-10-20 2022-01-01 2021-12-15 2022-02-13 orks) by constricting dry ston tions nvelope or explanation) 5 nagement e check barriers check barrie rs in the project area under A PO Nagrota Bagwan. IN-DPO, KANGRA-240102-C W-RFQ / Treatment of Draina Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 ge Line (Soil Conservation W IBRD / 90410 and and Water Resource Ma Post Limited 61,000.00 31,546.16 Completed 2021-09-06 2022-01-01 2021-11-01 2022-02-13 tions nvelope or explanation) 1 orks) by constricting dry ston nagement e check barriers check barrie rs in Baijnath unit. IN-DPO, KANGRA-240105-C W-RFQ / Treatment of Draina Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-2 ge Line (Soil Conservation W IBRD / 90410 and and Water Resource Ma Post Limited 61,200.00 32,467.66 Completed 2021-10-25 2022-01-01 2021-12-20 2022-02-13 tions nvelope or explanation) 0 orks) by constricting dry ston nagement e check barriers check barrie rs in Dehra unit. IN-DPO, KANGRA-240111-C W-RFQ / construction of cem ent concrete/RCC check dam Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-04-0 in Mehva,Sher Luhara, Kallar IBRD / 90410 and and Water Resource Ma Post Limited 94,500.00 118,085.23 Signed 2021-10-06 2021-11-22 2021-11-02 2022-01-29 tions nvelope or explanation) 1 & Jhaklehar GPs of Dehra uni nagement t for Primary water harvestin g and storage . there will be 5 to 7 check dams/ jobs(cont racts). IN-DPO, KANGRA-240114-C W-RFQ / There will be site sp ecific different jobs (contract Component 1. Sustainable L s) at different locations Prima Request for Quota Single Stage - One E Other (with field f 2022-05-0 IBRD / 90410 and and Water Resource Ma Post Limited 94,500.00 69,201.50 Completed 2021-11-05 2021-11-25 2021-12-02 2022-02-15 ry water harvesting and stor tions nvelope or explanation) 1 nagement age by constructing cement concrete/RCC check dam in d ifferent GPs of Baijnath unit. There will be 3 to 5 jobs(cont ract) for each location. IN-DPO, KANGRA-240116-C W-RFQ / Primary water harve sting and storage by constru Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-05-0 cting cement concrete/RCC c IBRD / 90410 and and Water Resource Ma Post Limited 88,000.00 99,467.97 Completed 2021-11-05 2021-12-06 2021-12-02 2022-04-17 tions nvelope or explanation) 1 heck dam in Nagrota Bagwan nagement unit .There will be site specifi c 5to7 jobs (contracts) at diff erent locations. IN-DPO, KANGRA-242775-C W-RFQ / Removal of Lantana Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-2 from target area by cut root IBRD / 90410 and and Water Resource Ma Post Open - National 23,500.00 23,172.35 Completed 2021-09-16 2021-11-08 2021-11-12 tions nvelope or explanation) 3 stock method (50 to 75% ) in nagement 50 ha. at 5 to 10 different loc ations. Page 5 IN-DPO, KANGRA-242779-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area with wooden fence Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2021-09-0 post and barbed wire for raisi IBRD / 90410 and and Water Resource Ma Post Open - National 63,000.00 59,508.54 Completed 2021-07-11 2021-08-02 2021-07-29 tions nvelope or explanation) 1 ng of plantation in the rainy s nagement eason of 2021 in the forest a rea to increase tree cover by planting 400 plants per/ha. u nder Enrichment Plantation. IN-DPO, KANGRA-242783-C W-RFQ / Afforestation includi ng advance work i.e. fencing Component 1. Sustainable L of plantation area with wood Request for Quota Single Stage - One E Other (with field f 2021-09-0 IBRD / 90410 and and Water Resource Ma Post Open - National 6,500.00 5,712.30 Completed 2021-07-12 2021-08-03 2021-07-29 en fence post and barbed wir tions nvelope or explanation) 2 nagement e and raising of plantation b y planting 800 plants per ha. in the rainy season of 2021 i n the forest area having ope n canopy . IN-DPO, KANGRA-242788-C W-RFQ / Raising of enrichme nt plantations is proposed un der APO Dehra, Panchrukhi & Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2021-09-0 Nagrota Bagwan . during the IBRD / 90410 and and Water Resource Ma Post Open - National 31,300.00 27,573.95 Completed 2021-07-11 2021-08-02 2021-07-29 tions nvelope or explanation) 1 rainy season of 2021 in the f nagement orest area @ 400 plants per/ ha . There are 12 jobs (contr acts) of 4 to 15 ha area in di fferent GP's in different unit. IN-DPO, KANGRA-242799-C W-RFQ / Contour trenching in plantation areas including rai sing of grass along the berm Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-02-0 of the contour trench. there IBRD / 90410 and and Water Resource Ma Post Open - National 20,900.00 23,952.94 Completed 2021-07-11 2021-08-05 2021-07-29 tions nvelope or explanation) 1 will 12 to13 jobs (contract). nagement This target is additional to th e already approved similar a ctivity vide reference No.IN-D PO, KANGRA-179096-CW-RF Q IN-DPO, KANGRA-281059-GO -RFQ / renovation of old she ep dip tank in Madhonagar G Component 1. Sustainable L P for dipping/bathing of shee Request for Quota Single Stage - One E Other (with field f 2022-10-2 IBRD / 90410 and and Water Resource Ma Post Open - National 13,500.00 11,375.56 Signed 2022-03-07 2022-05-02 2022-04-19 p flocks of transhumant in di tions nvelope or explanation) 9 nagement sinfectant solutions including construction of soakpits for s afe disposal of waste contam inated water after bathing IN-DPO, KANGRA-288878-C W-RFQ / Contour trenching in Component 1. Sustainable L plantation area including gra Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-0 IBRD / 90410 and and Water Resource Ma Post Open - National 53,500.00 0.00 2022-05-15 2022-07-10 ss sowing ./ planting on the b tions nvelope or explanation) mentation 6 nagement erm of contour trenches ther e will be 35 to 50 jobs (contr act). IN-DPO, KANGRA-288882-C W-RFQ / Contour trenching in Component 1. Sustainable L forest areas outside the plant Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-1 IBRD / 90410 and and Water Resource Ma Post Open - National 20,500.00 0.00 2022-05-20 2022-07-15 ation area including grass so tions nvelope or explanation) mentation 1 nagement wing/ planting on the berm of contour trenches there will b e 15 to 20 jobs (contract). IN-DPO, KANGRA-288889-C Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-0 W-RFQ / Planting of grass tuft IBRD / 90410 and and Water Resource Ma Post Open - National 5,200.00 0.00 2022-06-16 2022-07-11 tions nvelope or explanation) mentation 7 s in 39 ha. along Drainage Li nagement ne areas IN-DPO, KANGRA-288920-C W-RFQ / Treatment of Draina ge Line by vegetative check Component 1. Sustainable L barriers. Vegetative check ba Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-1 IBRD / 90410 and and Water Resource Ma Post Open - National 5,000.00 0.00 2022-12-06 2023-01-15 rriers shall be provided by us tions nvelope or explanation) mentation 6 nagement ing local species capable of s prouting in small and mediu m gullies having side slopes l ess than 45 degrees. IN-DPO, KANGRA-288924-C W-RFQ / Treatment of Draina Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2022-12-2 ge Line (Soil Conservation W IBRD / 90410 and and Water Resource Ma Post Open - National 38,000.00 0.00 2022-05-06 2022-08-30 2022-07-01 tions nvelope or explanation) mentation 8 orks) by constricting dry ston nagement e check barriers under APO B aijnath. IN-DPO, KANGRA-288928-C W-RFQ / Treatment of Draina Component 1. Sustainable L ge Line (Soil Conservation W Request for Quota Single Stage - One E Other (with field f Under Imple 2023-04-0 IBRD / 90410 and and Water Resource Ma Post Open - National 98,000.00 0.00 2022-09-05 2022-09-02 2022-10-05 orks) by constricting dry ston tions nvelope or explanation) mentation 3 nagement e check barriers under APO D ehra, Nagrota Bagwan and P anchrukhi units IN-DPO, KANGRA-288931-C W-RFQ / Treatment of Draina ge Line (Soil Conservation W Component 1. Sustainable L orks/civil structure treatment Request for Quota Single Stage - One E Other (with field f Under Imple 2023-05-1 IBRD / 90410 and and Water Resource Ma Post Open - National 52,000.00 0.00 2022-09-20 2022-09-22 2022-11-15 ) by constructing crate wire c tions nvelope or explanation) mentation 4 nagement heck barriers for retention of debris in gullies(drainage line ) receiving relatively large qu antity of run-off under APO P anchrukhi. IN-DPO, KANGRA-288932-C W-RFQ / Treatment of Draina ge Line (Soil Conservation W Component 1. Sustainable L orks/civil structure treatment Request for Quota Single Stage - One E Other (with field f Under Imple 2023-05-1 IBRD / 90410 and and Water Resource Ma Post Open - National 52,000.00 0.00 2022-09-20 2022-09-22 2022-11-15 ) by constructing crate wire c tions nvelope or explanation) mentation 4 nagement heck barriers for retention of debris in gullies(drainage line ) receiving relatively large qu antity of run-off under APO B aijnath. IN-DPO, KANGRA-288933-C W-RFQ / Treatment of Draina ge Line (Soil Conservation W Component 1. Sustainable L orks/civil structure treatment Request for Quota Single Stage - One E Other (with field f Under Imple 2023-05-1 IBRD / 90410 and and Water Resource Ma Post Open - National 52,000.00 0.00 2022-09-20 2022-09-22 2022-11-15 ) by constructing crate wire c tions nvelope or explanation) mentation 4 nagement heck barriers for retention of debris in gullies(drainage line ) receiving relatively large qu antity of run-off under APO N agrota Bagwan. Page 6 IN-DPO, KANGRA-288935-C W-RFQ / Treatment of Draina ge Line (Soil Conservation W Component 1. Sustainable L orks/civil structure treatment Request for Quota Single Stage - One E Other (with field f Under Imple 2023-05-1 IBRD / 90410 and and Water Resource Ma Post Open - National 52,000.00 0.00 2022-09-20 2022-09-22 2022-11-15 ) by constructing crate wire c tions nvelope or explanation) mentation 4 nagement heck barriers for retention of debris in gullies(drainage line ) receiving relatively large qu antity of run-off Under APO D ehra. IN-DPO, KANGRA-289134-C W-RFQ / Construction of CC c heck barriers for treatment o Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-05-1 f Drainage Line . There will b IBRD / 90410 and and Water Resource Ma Post Open - National 90,000.00 0.00 2022-09-20 2022-10-08 2022-11-15 tions nvelope or explanation) mentation 4 e 20 to 25 Different jobs (Con nagement tracts) in different Gram Pan chayats in the selected Drain age lines in Kangra District. IN-DPO, KANGRA-289171-C W-RFQ / Removal of Lantana Component 1. Sustainable L from target area by cut root Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-1 IBRD / 90410 and and Water Resource Ma Post Open - National 22,000.00 0.00 2022-06-20 2022-08-20 2022-08-15 stock method (50 to 75% ) in tions nvelope or explanation) mentation 1 nagement 50 ha. at 10 to 15 different l ocations under the jurisdictio n of DPO Kangra at Dharmah sla. IN-DPO, KANGRA-289184-C W-RFQ / Removal of Lantana Component 1. Sustainable L from target area by cut root Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-1 IBRD / 90410 and and Water Resource Ma Post Open - National 54,000.00 0.00 2022-06-20 2022-08-18 2022-08-15 stock method (75 to 100% ) i tions nvelope or explanation) mentation 1 nagement n 100 ha. at 10 to 20 differen t locations under the jurisdict ion of DPO Kangra at Dharam shala. IN-DPO, KANGRA-289193-C W-RFQ / Primary water harve sting and storage by constru Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-1 cting Ponds( Manual Excavati IBRD / 90410 and and Water Resource Ma Post Open - National 68,000.00 0.00 2022-06-20 2022-08-30 2022-08-15 tions nvelope or explanation) mentation 1 on) under the jurisdiction of nagement DPO Kangra at Dharamshala. There will be site specific 25 to 30 jobs (contracts) at diffe rent locations. IN-DPO, KANGRA-289214-C W-RFQ / Primary water harve sting and storage by constru Component 1. Sustainable L cting cement concrete check Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-1 IBRD / 90410 and and Water Resource Ma Post Open - National 41,000.00 0.00 2022-05-20 2022-08-24 2022-07-15 dams under the jurisdiction o tions nvelope or explanation) mentation 1 nagement f DPO,IDP Kangra at Dharams hala.There will be site specifi c 15 to20 jobs (contracts) at different locations. IN-DPO, KANGRA-289628-C W-RFQ / First year maintenan ce of 650 ha. plantation area s done during 2021-22 under Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-2 different schemes i.e. draina IBRD / 90410 and and Water Resource Ma Post Open - National 56,000.00 0.00 2022-06-07 2022-08-02 tions nvelope or explanation) mentation 9 ge line treatment=83 ha. ,re- nagement afforestation=106 ha. and en richment plantations=461ha. Total=650ha under the jurisd iction of DPO Kangra at Dhar amshala. IN-DPO, KANGRA-289636-C W-RFQ / 2nd year maintenan ce of 389 ha. plantation area s done during 2020-21 under Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-2 different schemes i.e. draina IBRD / 90410 and and Water Resource Ma Post Open - National 16,000.00 0.00 2022-06-07 2022-08-02 tions nvelope or explanation) mentation 9 ge line treatment=103ha. ,re nagement -afforestation=137ha. and en richment plantations=149ha. Total=389 ha. under the juris diction of DPO Kangra at Dha ramshala. IN-DPO, KANGRA-289639-C W-RFQ / Management of exot Component 1. Sustainable L ic species -2nd year activity i Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 21,500.00 0.00 2022-06-07 2022-08-02 n the targeted area in 300 ha tions nvelope or explanation) mentation 9 nagement ., where removal of Lantana was done by cut root stock m ethod during the year 2021-2 2 IN-DPO, KANGRA-289640-C W-RFQ / Management of exot Component 1. Sustainable L ic species -3rd year activity i Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 31,600.00 0.00 2022-06-07 2022-08-02 n the targeted area in 551 ha tions nvelope or explanation) mentation 9 nagement ., where removal of Lantana was done by cut root stock d uring the year 2020-21. IN-DPO, KANGRA-289868-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area with wooden fence Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-01-1 post and barbed wire for raisi IBRD / 90410 and and Water Resource Ma Post Open - National 26,000.00 27,931.35 Completed 2022-05-20 2022-07-15 2022-06-28 tions nvelope or explanation) 1 ng of plantation in the rainy s nagement eason of 2022-23 in the fores t area to increase tree cover by planting 1100 plants per/h a. under DPO Kangra. IN-DPO, KANGRA-289874-C W-RFQ / Raising plantation is proposed in 39 ha. by plantin Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-0 g 1100 plants per ha. in Kang IBRD / 90410 and and Water Resource Ma Post Open - National 29,000.00 0.00 2022-06-15 2022-08-10 tions nvelope or explanation) mentation 6 ra District. There will be 15 t nagement o 20 different jobs/contracts at different locations at diffe rent sites. IN-DPO, KANGRA-289876-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area with wooden fence Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-01-1 post and barbed wire for raisi IBRD / 90410 and and Water Resource Ma Post Open - National 16,000.00 15,734.94 Completed 2022-05-20 2022-07-15 2022-06-28 tions nvelope or explanation) 1 ng of plantation in the rainy s nagement eason of 2022-23 in the fores t area to increase tree cover by planting 800 plants per/ha . under DPO Kangra. IN-DPO, KANGRA-289878-C W-RFQ / Raising plantation is Component 1. Sustainable L proposed in 24 ha. by plantin Request for Quota Single Stage - One E Other (with field f 2023-02-0 IBRD / 90410 and and Water Resource Ma Post Open - National 15,000.00 14,689.20 Completed 2022-06-15 2022-08-10 2022-07-12 g 800 plants per ha. in Kangr tions nvelope or explanation) 6 nagement a District. There will be up to 5 different jobs/contracts at different locations at differen t sites. Page 7 IN-DPO, KANGRA-289881-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta Component 1. Sustainable L tion area with wooden fence Request for Quota Single Stage - One E Other (with field f 2023-01-1 IBRD / 90410 and and Water Resource Ma Post Open - National 100,000.00 104,453.93 Completed 2022-05-20 2022-07-15 2022-06-28 post and barbed wire for raisi tions nvelope or explanation) 1 nagement ng of plantation in the rainy s eason of 2022-23 in the fores t area to increase tree cover by planting 400 plants per/ha . under APO Dehra. IN-DPO, KANGRA-289883-C W-RFQ / Raising plantation is proposed in 154 ha. by planti Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-0 ng 400 plants per ha. in Dehr IBRD / 90410 and and Water Resource Ma Post Open - National 52,000.00 0.00 2022-06-15 2022-08-10 tions nvelope or explanation) mentation 6 a unit of Kangra District. The nagement re will be up to 20 to 25 diffe rent jobs/contracts at differe nt locations at different sites IN-DPO, KANGRA-289903-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area with wooden fence Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-01-1 post and barbed wire for raisi IBRD / 90410 and and Water Resource Ma Post Open - National 55,000.00 48,539.85 Signed 2022-05-20 2022-07-15 2022-07-07 tions nvelope or explanation) 1 ng of plantation in the rainy s nagement eason of 2022-23 in the fores t area to increase tree cover by planting 400 plants per/ha . under DPO Kangra. IN-DPO, KANGRA-289906-C W-RFQ / Raising plantation is proposed in 83 ha. by plantin Component 1. Sustainable L g 400 plants per ha. in Nagro Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-0 IBRD / 90410 and and Water Resource Ma Post Open - National 28,000.00 0.00 2022-06-15 2022-08-10 ta Bagwan , Panchrukhi and tions nvelope or explanation) mentation 6 nagement Baijnath unit of Kangra Distri ct. There will be up to 8 to 10 different jobs/contracts at dif ferent locations at different si tes IN-DPO, KANGRA-300396-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area with wooden fence Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2022-08-2 post and barbed wire for raisi IBRD / 90410 and and Water Resource Ma Post Open - National 43,400.00 0.00 2022-07-04 2022-07-28 tions nvelope or explanation) mentation 7 ng of plantation in the rainy s nagement eason of 2022-23 in the fores t area to increase tree cover by planting 400 plants per/ha .under DPO Kangra. Total=65 ha. IN-DPO, KANGRA-300397-C W-RFQ / Raising plantation is proposed in 65 ha. by plantin g 400 plants per ha. under A Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2022-08-0 PO Nagrota Bagwan=25 ha , IBRD / 90410 and and Water Resource Ma Post Open - National 22,000.00 0.00 2022-07-10 2022-08-01 tions nvelope or explanation) mentation 4 Panchrukhi=20 ha and Dehra nagement =20ha. Total=65ha. There wi ll be up to 8 to 10 different jo bs/contracts at different locat ions at different sites IN-DPO, KANGRA-300400-C W-RFQ / Contour trenching in Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-0 plantation area including gra IBRD / 90410 and and Water Resource Ma Post Open - National 18,000.00 0.00 2022-07-15 2022-08-08 tions nvelope or explanation) mentation 4 ss sowing ./ planting on the b nagement erm of contour trenches ther e will be 8to10 jobs (contract ). IN-DPO, KANGRA-301467-C W-RFQ / Eradication of 50 to 75% lantana infested areas i Component 1. Sustainable L s proposed during 2022-23 in Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-2 IBRD / 90410 and and Water Resource Ma Post Open - National 22,000.00 0.00 2022-08-20 2022-08-24 2022-09-21 addition to the already appro tions nvelope or explanation) mentation 0 nagement ved similar activity vide IN-D PO, KANGRA-289171.There w ill be 8to10 different jobs (co ntracts) at different locations . IN-DPO, KANGRA-301474-C W-RFQ / Additional removal o f lantana in 50ha area infeste d 75to100% is proposed by C Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-1 RS method during the year 2 IBRD / 90410 and and Water Resource Ma Post Open - National 27,000.00 0.00 2022-08-20 2022-08-24 2022-09-20 tions nvelope or explanation) mentation 9 022-23 in addition to the alre nagement ady approved similar activity vide IN-DPO, KANGRA-28918 4.There will be 8 to 10 differe nt jobs (contracts) . IN-DPO, KANGRA-308794-C W-RFQ / Crate wire check bar Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-05-2 riers are proposed to be cons IBRD / 90410 and and Water Resource Ma Post Open - National 65,000.00 0.00 2022-10-05 2022-10-27 2022-11-30 tions nvelope or explanation) mentation 9 tructed for DLT in various loc nagement ations in three units of Kangr a District. IN-DPO, KANGRA-308978-C W-RFQ / Contour Trenches ou tside plantation area in 55 ha Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-02-1 is proposed including grass s IBRD / 90410 and and Water Resource Ma Post Open - National 15,300.00 0.00 2022-09-24 2022-09-22 2022-11-19 tions nvelope or explanation) mentation 7 owing along the berm of the nagement contour to increase the water regime and fodder productivi ty during the year . IN-DPO, KANGRA-308992-C W-RFQ / Renovation and impr ovement of 35 already existi ng Natural Water Sources (W Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-3 ell, springs, traditional water IBRD / 90410 and and Water Resource Ma Post Limited 70,000.00 0.00 2022-11-04 2023-02-02 2022-12-30 tions nvelope or explanation) mentation 0 bauries, etc ) to improve the nagement water availability and hydro-l ogical health ,there will be 3 5 different jobs (contracts) at different locations . IN-DPO, KANGRA-309185-C W-RFQ / construction of cem ent concrete check dams for Component 1. Sustainable L Primary water harvesting an Request for Quota Single Stage - One E Other (with field f Under Imple 2023-05-2 IBRD / 90410 and and Water Resource Ma Post Open - National 75,000.00 0.00 2022-10-05 2022-10-15 2022-11-30 d diverting it to the agricultur tions nvelope or explanation) mentation 9 nagement e fields . There will be multipl e contracts at different locati ons in various GPs of Knagra Districts for the year 2022-23 . IN-DPO, KANGRA-309193-C W-RFQ / Primary Water Harv Component 1. Sustainable L esting by constructing two c Request for Quota Single Stage - One E Other (with field f Under Imple 2023-05-1 IBRD / 90410 and and Water Resource Ma Post Open - National 30,000.00 0.00 2022-09-20 2022-10-25 2022-11-15 ement concrete Gravity chec tions nvelope or explanation) mentation 4 nagement k dam/ RCC Check dam are p roposed in different GPs un der APO Dehra unit during 20 22-23. Page 8 IN-DPO, KANGRA-220286-C W-RFQ / Primary water harve Component 1. Sustainable L sting and storage by constru Request for Quota Single Stage - One E 2021-06-2 IBRD / 90410 and and Water Resource Ma Post Limited 80,000.00 0.00 Canceled 2021-03-02 2021-02-26 2021-03-29 cting cement concrete check tions nvelope 0 nagement dam. There will be site specif ic different jobs (contracts) a t different locations. IN-DPO, KANGRA-220314-C W-RFQ / Development of Mod ern Nursery includes constru ction of agro-net shed for roo Component 1. Sustainable L Request for Quota Single Stage - One E 2022-03-3 t trainers , poly house , Mali IBRD / 90410 and and Water Resource Ma Post Limited 66,700.00 0.00 Canceled 2021-03-15 2021-05-10 tions nvelope 1 hut, material mixing shed in nagement addition to site development , fencing , solar lights , devel opment of paths , irrigation and electric provision etc. IN-DPO, KANGRA-310096-C W-RFQ / construction of 3 to 5 foot bridges in different Gr Component 1. Sustainable L am Panchayat in the Project Request for Quota Single Stage - One E Other (with field f Under Imple 2023-05-2 IBRD / 90410 and and Water Resource Ma Post Open - National 30,000.00 0.00 2022-10-01 2022-10-08 2022-11-26 area of Kangra District to imp tions nvelope or explanation) mentation 5 nagement rove connectivity of the farm ers from poor accessibility ar eas with the market for suppl y of inputs and sale of produ ce . IN-DPO, KANGRA-237230-C W-RFQ / Sub Surface Dykes/S ump well will be constructed Component 1. Sustainable L Request for Quota in the sandy type river beds Request for Quota Single Stage - One E 2022-03-3 IBRD / 90410 and and Water Resource Ma Post Limited tions (Non Bank-S 88,000.00 0.00 Canceled 2021-09-05 2021-10-02 where impervious layer lies a tions nvelope 1 nagement PD) t small depth to harvest the s ub-surface flow for the purpo se of irrigation. There will be site specific different jobs (co ntracts) IN-DPO, KANGRA-309212-C W-RFQ / Masonry check dam s are proposed in different G Component 1. Sustainable L Ps of Kangra District for diver Request for Quota Single Stage - One E Other (with field f Under Imple 2023-07-1 IBRD / 90410 and and Water Resource Ma Post Open - National 35,000.00 0.00 2023-01-20 2023-06-14 2023-03-17 sion head wall for diversion o tions nvelope or explanation) mentation 5 nagement f water to agriculture fields o f the water user groups at 5 t o 7 different locations of proj ect area during 2022-23. IN-DPO, KANGRA-309015-C W-RFQ / Community Rain Ro of water harvesting structure s in Nagrota Bagwan & Baijn Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-2 ath units in 20 to 30 differe IBRD / 90410 and and Water Resource Ma Post Open - National 85,000.00 0.00 2023-02-04 2023-01-31 2023-03-26 tions nvelope or explanation) mentation 4 nt locations in Nagrota & Ba nagement ijnath units where c/o other t ype of primary water harvest ing is not feasible and house holds are densely packed . IN-DPO, KANGRA-308708-C W-RFQ / Water Distribution fr Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 om primary water harvesting IBRD / 90410 and and Water Resource Ma Post Open - National 95,000.00 0.00 2023-01-20 2023-03-17 tions nvelope or explanation) mentation 5 structures to secondary struc nagement tures, for gravity and lift dist ribution systems . IN-DPO, KANGRA-309011-C W-RFQ / Community Rain Ro Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-07-0 of water harvesting structure IBRD / 90410 and and Water Resource Ma Post Open - National 66,000.00 0.00 2023-02-05 2023-01-31 2023-04-02 tions nvelope or explanation) mentation 1 s for secondary water distri nagement bution at 20 to 30 different lo cations in Panchrukhi unit . IN-DPO, KANGRA-309190-C W-RFQ / Primary water harve Component 1. Sustainable L sting and storage by constru Request for Quota Single Stage - One E Other (with field f Under Imple 2023-06-1 IBRD / 90410 and and Water Resource Ma Post Open - National 27,000.00 0.00 2022-10-20 2022-09-24 2022-12-15 cting cement concrete Gravit tions nvelope or explanation) mentation 3 nagement y /RCC check dam in Nagrota Bagwan Unit in GP Malan duri ng 2022-23 IN-DPO, KANGRA-308989-C W-RFQ / Treatment of Draina ge Line (Soil Conservation W Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-05-3 orks) by constricting dry ston IBRD / 90410 and and Water Resource Ma Post Open - National 60,000.00 0.00 2023-01-19 2023-03-16 tions nvelope or explanation) mentation 0 e check barriers is proposed nagement to sustain the upper catchme nt . This is in addition to alre ady approved activities of si milar nature . IN-DPO, KANGRA-309000-C W-RFQ / Community Rain Ro of water harvesting structure Component 1. Sustainable L s are proposed for secondary Request for Quota Single Stage - One E Other (with field f Under Imple 2023-07-0 IBRD / 90410 and and Water Resource Ma Post Open - National 99,000.00 0.00 2023-02-05 2023-01-31 2023-04-02 water distribution at 20 to 3 tions nvelope or explanation) mentation 1 nagement 0 different locations/jobs in D ehra unit . It is not a matchin g grant activity .There will be multiple contracts for differe nt locations / sites . IN-DPO, KANGRA-321530-C Component 1. Sustainable L W-RFQ / Raising and mainten Request for Quota Single Stage - One E Other (with field f Under Imple 2023-11-0 IBRD / 90410 and and Water Resource Ma Post Open - National 37,500.00 0.00 2023-01-12 2023-03-09 ance of nurseries for plantati tions nvelope or explanation) mentation 4 nagement ons in district Kangra IN-DPO, KANGRA-337611-C W-RFQ / Water Distribution fr Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-07-1 om primary water harvesting IBRD / 90410 and and Water Resource Ma Post Open - National 50,000.00 0.00 2023-02-15 2023-03-01 2023-04-12 tions nvelope or explanation) mentation 1 structures to secondary struc nagement tures, for gravity and lift distr ibution systems . IN-DPO, KANGRA-337612-C W-RFQ / Primary water harve Component 1. Sustainable L sting and storage by constru Request for Quota Single Stage - One E Other (with field f Under Imple 2023-07-1 IBRD / 90410 and and Water Resource Ma Post Open - National 25,000.00 0.00 2023-02-20 2023-03-22 2023-04-17 cting cement concrete Gravit tions nvelope or explanation) mentation 6 nagement y /RCC check dam in Panchru khi Unit in GP Gadiyara durin g 2023 IN-DPO, KANGRA-337613-C W-RFQ / Primary water harve sting and storage by constru Component 1. Sustainable L cting cement concrete check Request for Quota Single Stage - One E Other (with field f Under Imple 2023-07-1 IBRD / 90410 and and Water Resource Ma Post Open - National 70,000.00 0.00 2023-02-15 2023-03-01 2023-04-12 dams under the jurisdiction o tions nvelope or explanation) mentation 1 nagement f DPO,IDP Kangra at Dharams hala. There will be site specifi c 10 to 15 jobs (contracts) at different locations. Page 9 IN-DPO, KANGRA-344059-C W-RFQ / removal of lantana i Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-11-2 n 100ha area infested 75 to1 IBRD / 90410 and and Water Resource Ma Post Open - National 65,000.00 0.00 2023-03-30 2023-04-19 2023-05-25 tions nvelope or explanation) mentation 1 00% is proposed by CRS met nagement hod . There will be 8 to 10 dif ferent jobs (contracts) IN-DPO, KANGRA-344071-C W-RFQ / removal of lantana i Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-11-1 n 100 ha area infested 50 to IBRD / 90410 and and Water Resource Ma Post Open - National 50,000.00 0.00 2023-03-25 2023-04-19 2023-05-20 tions nvelope or explanation) mentation 6 75 % is proposed by CRS me nagement thod . There will be 8 to 10 di fferent jobs (contracts) IN-DPO, KANGRA-347728-C Component 1. Sustainable L W-RFQ / Raising and mainten Request for Quota Single Stage - One E Other (with field f Under Imple 2023-08-1 IBRD / 90410 and and Water Resource Ma Post Open - National 13,000.00 0.00 2023-04-20 2023-03-25 2023-05-18 ance of nurseries for plantati tions nvelope or explanation) mentation 6 nagement ons in district Kangra IN-DPO, KANGRA-347735-C Component 1. Sustainable L W-RFQ / Water Distribution fr Request for Quota Single Stage - One E Other (with field f Under Imple 2024-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 63,000.00 0.00 2023-05-05 2023-06-14 2023-06-30 om primary water harvesting tions nvelope or explanation) mentation 1 nagement structures to secondary struc tures, IN-DPO, KANGRA-355916-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area 100 ha with woode Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-09-0 n fence post and barbed wire IBRD / 90410 and and Water Resource Ma Post Open - National 87,000.00 0.00 2023-06-06 2023-06-14 2023-07-09 tions nvelope or explanation) mentation 7 for raising of plantation durin nagement g the rainy season of 2023 in the forest area to increase tr ee cover by planting 400 pla nts per/ha. under APO Dehra. IN-DPO, KANGRA-355921-C W-RFQ / Pre-monsoon/ advan ce work i.e. fencing of planta tion area 70 ha with wooden Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-09-2 fence post and barbed wire f IBRD / 90410 and and Water Resource Ma Post Open - National 62,000.00 0.00 2023-06-06 2023-06-14 2023-07-25 tions nvelope or explanation) mentation 3 or raising of plantation in the nagement rainy season of 2023-24 in th e forest area to increase tree cover by planting 400 plants per/ha. under DPO Kangra. IN-DPO, KANGRA-355923-C W-RFQ / Raising plantation is proposed in 100 ha. by planti Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-09-1 ng 400 plants per ha. in Dehr IBRD / 90410 and and Water Resource Ma Post Open - National 49,000.00 0.00 2023-06-15 2023-06-28 2023-07-16 tions nvelope or explanation) mentation 4 a unit of Kangra District. Ther nagement e will be up to 10 to 15 differ ent jobs/contracts at differen t locations at different site IN-DPO, KANGRA-355926-C W-RFQ / Raising plantation is Component 1. Sustainable L proposed in 70 ha. by plantin Request for Quota Single Stage - One E Other (with field f Under Imple 2023-09-1 IBRD / 90410 and and Water Resource Ma Post Open - National 34,100.00 0.00 2023-06-15 2023-06-28 2023-07-18 g 400 plants per ha. in Nagro tions nvelope or explanation) mentation 6 nagement ta Bagwan , Panchrukhi and Baijnath unit of Kangra Distri ct. IN-DPO, KANGRA-355929-C W-RFQ / removal of lantana i Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2024-03-1 n 100ha area infested 75 to1 IBRD / 90410 and and Water Resource Ma Post Open - National 75,000.00 0.00 2023-06-20 2023-06-23 2023-08-15 tions nvelope or explanation) mentation 2 00% is proposed by CRS met nagement hod . There will be 10 to 15 d ifferent jobs (contracts) IN-DPO, KANGRA-355931-C W-RFQ / removal of lantana i Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2024-03-2 n 155 ha area infested 50 to IBRD / 90410 and and Water Resource Ma Post Open - National 95,000.00 0.00 2023-06-15 2023-06-23 2023-07-25 tions nvelope or explanation) mentation 1 75 % is proposed by CRS met nagement hod . There will be 12 to 18 d ifferent jobs (contracts) IN-DPO, KANGRA-355933-C W-RFQ / removal of lantana i Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2024-03-2 n 10ha area infested 25 to 5 IBRD / 90410 and and Water Resource Ma Post Open - National 5,000.00 0.00 2023-06-15 2023-06-19 2023-07-25 tions nvelope or explanation) mentation 1 0% is proposed by CRS meth nagement od . There will be 1 to 2 differ ent jobs (contracts) IN-DPO, KANGRA-356095-C Component 1. Sustainable L W-RFQ / contour trenching is Request for Quota Single Stage - One E Other (with field f Under Imple 2024-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 51,000.00 0.00 2023-06-06 2023-06-14 2023-08-01 proposed in 170ha in planta tions nvelope or explanation) mentation 8 nagement tion areas including grass pla nting on berms. IN-DPO, KANGRA-356096-C W-RFQ / Contour trenching o Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-01-2 utside plantation area is prop IBRD / 90410 and and Water Resource Ma Post Open - National 51,000.00 0.00 2023-06-06 2023-08-01 tions nvelope or explanation) lementation 8 osed in 170ha.including gras nagement s planting on burm of the con tour trench. IN-DPO, KANGRA-356440-C W-RFQ / First year maintenan ce of 365 ha. plantation area s done during 2022-23 under Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-11-2 different schemes i.e. draina IBRD / 90410 and and Water Resource Ma Post Open - National 36,200.00 0.00 2023-06-06 2023-06-26 2023-08-01 tions nvelope or explanation) mentation 9 ge line treatment=27 ha. ,re- nagement afforestation=36 ha. and enri chment plantations=3021ha. Total=365ha under the jurisd iction of DPO Kangra at Dhar amshala. IN-DPO, KANGRA-356441-C W-RFQ / IInd year maintenan ce of 650 ha. plantation area s done during 2021-22 under Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2024-01-2 different schemes i.e. draina IBRD / 90410 and and Water Resource Ma Post Open - National 49,700.00 0.00 2023-06-06 2023-06-26 2023-08-01 tions nvelope or explanation) mentation 8 ge line treatment=83 ha. ,re- nagement afforestation=106 ha. and en richment plantations=461ha. Total=650ha under the jurisd iction of DPO Kangra at Dhar amshala. IN-DPO, KANGRA-356443-C W-RFQ / Third year maintena nce of 389 ha. plantation are as done during 2020-21 unde Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2024-01-2 r different schemes i.e. drain IBRD / 90410 and and Water Resource Ma Post Open - National 21,500.00 0.00 2023-06-06 2023-06-26 2023-08-01 tions nvelope or explanation) mentation 8 age line treatment=103ha.,r nagement e-afforestation=137 ha. and enrichment plantations=149 ha. Total=389ha under the ju risdiction of DPO Kangra at D haramshala. Page 10 IN-DPO, KANGRA-356446-C W-RFQ / Management of exot ic species -3rd year activity II Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2024-02-1 nd year maintt. in the target IBRD / 90410 and and Water Resource Ma Post Open - National 24,000.00 0.00 2023-06-06 2023-06-26 2023-08-01 tions nvelope or explanation) mentation 7 ed area in 300 ha., where re nagement moval of Lantana was done b y cut root stock method duri ng the year 2021-22 IN-DPO, KANGRA-356447-C W-RFQ / Management of exot ic species -2nd year activity I Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2024-03-2 st Year Maintt. in the targete IBRD / 90410 and and Water Resource Ma Post Open - National 23,500.00 0.00 2023-06-06 2023-06-26 2023-08-01 tions nvelope or explanation) mentation 8 d area in 250 ha., where rem nagement oval of Lantana was done by cut root stock method during the year 2022-23 IN-DPO, KANGRA-359157-C W-RFQ / C/o Cement concret e check dams under Primary Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-11-2 water harvesting and storage IBRD / 90410 and and Water Resource Ma Post Open - National 95,000.00 0.00 2023-06-06 2023-08-01 tions nvelope or explanation) lementation 9 under the jurisdiction of DPO, nagement IDP Kangra at Dharamshala. There will be site specific 15 to 20 jobs (contracts) at diffe rent locations. IN-DPO, KANGRA-359160-C W-RFQ / Installation of electri c water lifting pumps along w ith all allied accessories incl Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-12-1 uding electrical power suppl IBRD / 90410 and and Water Resource Ma Post Open - National 40,000.00 0.00 2023-05-25 2023-07-20 tions nvelope or explanation) lementation 7 y for lift irrigation schemes f nagement rom PWHS's to secondary w ater infrastructure at Sherluh ara ,Khartkhas, Mundla, Meh wa and Jhakhlehar GP's . IN-DPO, KANGRA-359296-C W-RFQ / Treatment of Draina ge Line by vegetative check Component 1. Sustainable L barriers. Vegetative check ba Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 5,500.00 0.00 2023-06-15 2023-07-25 rriers shall be provided by us tions nvelope or explanation) lementation 1 nagement ing local species capable of s prouting in small and mediu m gullies having side slopes l ess than 45 degrees . IN-DPO, KANGRA-359297-C W-RFQ / Primary water harve sting and storage by constru Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-02-0 cting Ponds( Manual Excavati IBRD / 90410 and and Water Resource Ma Post Open - National 47,000.00 0.00 2023-06-15 2023-08-10 tions nvelope or explanation) lementation 6 on) under the jurisdiction of nagement DPO Kangra at Dharamshala. There will be site specific 15 to 20 jobs (contracts) at diffe rent locations. IN-DPO, KANGRA-359164-C W-RFQ / Treatment of Draina Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-01-3 ge Line (Soil Conservation W IBRD / 90410 and and Water Resource Ma Post Open - National 99,500.00 0.00 2023-07-05 2023-08-04 tions nvelope or explanation) lementation 1 orks) by constricting dry ston nagement e check barriers in the Projec t area of Kangra District. IN-DPO, KANGRA-359295-C W-RFQ / Crate wire check bar Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-02-2 riers are proposed to be cons IBRD / 90410 and and Water Resource Ma Post Open - National 85,000.00 0.00 2023-07-05 2023-08-30 tions nvelope or explanation) lementation 6 tructed for DLT in various loc nagement ations in Baijnath & Panchruk hi units of Kangra District. IN-DPO, KANGRA-359294-C W-RFQ / Crate wire check bar Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-02-2 riers are proposed to be cons IBRD / 90410 and and Water Resource Ma Post Open - National 62,000.00 0.00 2023-07-05 2023-08-30 tions nvelope or explanation) lementation 6 tructed for DLT in various loc nagement ations in Nagrota Bagwan & Dehra units of Kangra Distric t. IN-DPO, KANGRA-362668-C W-RFQ / Water Distribution fr Component 1. Sustainable L om primary water harvesting Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-02-1 IBRD / 90410 and and Water Resource Ma Post Open - National 99,000.00 0.00 2023-07-20 2023-09-14 structures to secondary struc tions nvelope or explanation) lementation 1 nagement tures, for gravity and lift distr ibution systems & Lining of tr aditional irrigation Channels GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DPO, KANGRA-178842-GO -RFQ / Procurement of Polyth ene bags for raising nurserie Component 1. Sustainable L s. Black recycled Polythene b Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 2,170.00 2,037.90 Completed 2020-06-15 2020-02-26 2020-08-10 2020-03-14 2021-02-06 2020-03-16 ags of Size 5’x9”gauze 150 h tions nvelope nagement aving 6 hole’s in 2 rows of 3 hole’s in each Lower 2/3 Porti on automatically double seal ed by heat process dia of hol e 0.3 mm. IN-DPO, KANGRA-199067-GO Component 1. Sustainable L -RFQ / Black Recycled Poly B Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 5,000.00 4,748.40 Completed 2020-11-20 2020-10-28 2021-01-15 2020-11-21 2021-02-14 2020-12-11 ags shall be procured for rai tions nvelope nagement sing of plants in all six nurser ies under DPO Kangra . IN-DPO, KANGRA-204490-GO -RFQ / Forestry seeds Dendro calamus strictus= 5kg and D Component 1. Sustainable L endrocalamus hamiltonii =5k Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 5,000.00 5,005.89 Completed 2020-11-12 2020-10-28 2021-01-07 2021-01-14 2021-02-06 2021-01-28 g and root shoot cuttings of tions nvelope nagement forestry plants i.e. Tectona gr andis (Teak), Terminalia Arju na (Arjun)and salix =95000 f or raising of nursery plants. IN-DPO, KANGRA-216715-GO -RFQ / Forestry seeds Dendro calamus strictus= 15kg and Component 1. Sustainable L Dendrocalamus hamiltonii = Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 5,000.00 4,735.30 Completed 2021-02-06 2020-10-28 2021-03-01 2021-02-02 2021-03-08 2021-02-02 15kg and root shoot cuttings tions nvelope nagement of forestry plants i.e. Tectona grandis (Teak), Terminalia Arj una (Arjun)and salix =90000 for raising of nursery plants u nder APO Dehra. Page 11 IN-DPO, KANGRA-237265-GO Component 1. Sustainable L -RFQ / Black Recycled Poly B Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 13,500.00 11,844.20 Completed 2021-07-20 2021-09-23 2021-08-31 2021-12-10 2021-09-30 2021-12-10 ags shall be procured for rais tions nvelope nagement ing of plants in all eight nurs eries under DPO Kangra IN-DPO, KANGRA-240094-GO Component 1. Sustainable L Request for Quota Single Stage - One E -RFQ / Procurement of GI wir IBRD / 90410 and and Water Resource Ma Post Limited 26,000.00 31,584.55 Completed 2021-09-20 2021-12-10 2021-10-12 2022-01-25 2021-11-11 2022-01-27 tions nvelope e for construction of crate wir nagement e structure . IN-DPO, KANGRA-274238-GO -RFQ / Providing and fixing of Component 1. Sustainable L sign boards for various activi Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 13,500.00 14,503.60 Completed 2022-02-13 2022-03-09 2022-03-04 2022-04-08 2022-03-23 ties taken up under the Proje tions nvelope nagement ct i.e. plantations, drainage li ne treatment and water harv esting etc. in all 64 GP's IN-DPO, KANGRA-281064-GO -RFQ / procurement of tarpa ulins,drenching guns,castrato rs,tents with sleeping bags, r Component 1. Sustainable L Request for Quota Single Stage - One E ucksacks,LED based torchs,s IBRD / 90410 and and Water Resource Ma Post Open - National 35,000.00 0.00 Canceled 2022-03-06 2022-03-24 2022-09-20 tions nvelope now shoes,water resistant ra nagement in jackets on cost shairing b asis @90:10 and medical kit s,sheep shairing units free of cost for transhumants. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 12 Himachal Pradesh Horticulture Development Project Project ID : P151744 Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan : Original: March 22, 2016 2. Date of General Procurement Notice: May 19, 2015 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Table 1: Procurement Methods Category Method of Threshold (US$ Procurement Equivalent) Goods and non- ICB >3,000,000 consulting LIB Wherever agreed by the services (including World Bank IT contracts) NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 100,000 From UN Agencies As per para 3.10 of Guidelines DC As per para 3.7 of Guidelines Force Account As per para 3.9 of Guidelines Framework As per para 3.6 of Guidelines Agreements Works ICB >40,000,000 NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 100,000 DC As per para 3.7 of Guidelines Force Account As per para 3.9 of Guidelines  Prior Review by the Bank : The World Bank will prior review all Terms of Reference and the following contracts: March 22, 2015 • Works: All contracts more than US$15.0 million equivalent; • Goods: All contracts more than US$3.0 million equivalent; • Non-Consulting Services: All contracts more than US$3.0 million equivalent;  The HPHDS will prior review the first contract issued by each implementing entity, if the estimates of those contracts are below the prior review threshold value. The Bank will conduct prior review for only those contracts whose estimates fall in the prior review threshold value. In addition, justifications for all contracts to be issued on Limited International Bidding (LIB), direct contracting or single sourcing (>US$100,000) basis will be subject to prior review by the World Bank. These thresholds are set for the initial 18 months of project implementation and are based on the procurement performance of the project, and may be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above.  All contracts below the specified prior review threshold value will be subject to Post Procurement Review (PPR). The implementing agency will prepare a list of contracts and submit it to the World Bank for this purpose. The PPR will be conducted on an annual basis. 2. Prequalification. Not applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by 5. Any Other Special Procurement Arrangements:  International Competitive Bidding (ICB) is the preferred method for procurement of goods, works and non-consulting services using the World Bank’s standard bidding document. In addition, the following methods may be adopted depending upon size and complexity of subprojects in accordance with Procurement Guidelines, and as agreed in the Procurement Plan: (a) Limited International Bidding (LIB), (b) National Competitive Bidding (NCB), (c) Shopping, (d) Framework Agreements, (e) Direct Contracting, (f) Force Account, and (g) Procurement of UN agencies. Limited International Bidding is essentially ICB by direct invitation, is used only under exceptional circumstances, and will be March 22, 2015 adopted only for packages that are specifically agreed by the World Bank to be procured following LIB.  National Competitive Bidding (NCB) for procurement of goods and works will be conducted in accordance with paragraphs 3.3 and 3.4 of the Procurement Guidelines and the following provisions: (i) Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), will be used for bidding. (ii) Invitation to bid will be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids. (iii) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, government-owned enterprises, small-scale enterprises or enterprise from any given regional government; (iv) Except with the prior concurrence of the World Bank, there will be no negotiation of price with the bidders, even with the lowest evaluated bidder; (v) For prior review contracts, extension of bid validity will not be allowed without the prior concurrence of the World Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the World Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); (vi) For prior review contracts, re-bidding will not be carried out without the prior concurrence of the World Bank; (vii) The system of rejecting bids outside a pre-determined margin or “bracket” of prices will not be used in the Project; (viii) Rates contracts entered into by the Directorate General of Supplies and Disposal (DGS & D) will not be acceptable as a substitute for NCB procedures unless agreed with the World Bank on a case-by- case basis. Such contracts will be acceptable however, for any procurement under the shopping procedure; (ix) The two or three envelop system will not be used (expect when using the e-procurement system assessed and agreed by the World Bank). March 22, 2015  Shopping. Procurement of goods, works and non-consulting services may be carried out using the shopping method (paragraph 3.5 of the Procurement Guidelines) for readily available, off-the-shelf products, or simple civil works valued at less than US$100,000 and which do not require tailor made designs as agreed with the World Bank or concerned expert agencies. Such method, if any, will be agreed in the Procurement Plan. The implementing agency and entities will solicit at least three price quotations for the purchase of goods, materials, small works, or services (non-consulting), to formulate a cost comparison report. If agreed by the World Bank, under exceptional circumstances, (such as design sensitivity due to location near a monument or appropriate technology), International Shopping may be used wherein quotations will be solicited from at least three suppliers in two different countries. Goods that otherwise qualify for shopping could be procured directly from UN agencies. In specific cases agreed with the World Bank, procurement may be made from UN agencies as per paragraph 3.10 of the Procurement Guidelines.  Direct Contracting. Direct contracting for the procurement of civil works and goods (paragraph 3.7 of the Procurement Guidelines) may be used to extend an existing contract or award a new contract. For such contracting to be justified, the World Bank must agree that the price is reasonable and that no advantage could be obtained by further competition. Direct contracting can be used to procure from the private sector, UN agencies/programs (for goods), or contractors or NGOs that are already mobilized and working in the target areas.  Force Account. When contractors/suppliers are unlikely to bid at reasonable prices because of the location and risk associated with the subproject or a certain government agency has exclusive rights to a certain type of works/supply, the borrower may use its own department’s personnel and equipment or government owned construction units, provided that the borrower has sufficient managerial capacity and possesses the required technical and financial controls to report to the World Bank on expenditure, as per paragraph 3.9 of the Procurement Guidelines.  Framework Agreements. Directorate General of Supplies and Disposal rate contracts will be acceptable as framework agreements for the procurement of goods. Regional government level rate contracts will be examined by the World Bank and if agreed upon, may also be used as framework agreements. Implementing entities also have the option to set up new framework agreements as per paragraph 3.6 of the Procurement Guidelines. March 22, 2015  Use of government institutions and enterprise. Government owned enterprise or institutions in India may be hired based on their unique and exceptional nature if their participation is considered critical to the Project implementation. In such cases, the conditions given in clauses 1.13 of the Consultant Guidelines will be satisfied and each case will be subject to prior review by the World Bank. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness : Available in separate Excel file III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Table 2: Procurement Methods Category Method of Threshold (US$ Procurement Equivalent) Consultants’ QCBS As per Section II of Guidelines services CQS Up to 300,000 SSS As per para 3.8-3.11 of Guidelines Individuals As per Section V of Guidelines LCS As per para 3.6 of Guidelines QBS As per para 3.2 of Guidelines FBS As per para 3.5 of Guidelines (i) International >800,000 shortlist Up to 800,000 (ii) Shortlist may comprise national consultants only  The World Bank will prior review all Terms of Reference and the following contracts: • All contracts more than US$1.0 million equivalent for firm; and • All contracts more US$300,000 equivalent for individuals. The HPHDS will prior review the first contract issued by each implementing entity, if the estimates of those contracts are below the March 22, 2015 prior review threshold value. The Bank will conduct prior review for only those contracts whose estimates fall in the prior review threshold value. In addition, justifications for all contracts to be issued on direct contracting or single sourcing (>US$100,000) basis will be subject to prior review by the World Bank. These thresholds are set for the initial 18 months of project implementation and are based on the procurement performance of the project, and may be modified. In addition, the Bank will carry out an annual ex post procurement review of the procurement falling below the prior review threshold mentioned above. All contracts below the specified prior review threshold value will be subject to Post Procurement Review (PPR). The implementing agency will prepare a list of contracts and submit it to the World Bank for this purpose. The PPR will be conducted on an annual basis. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements:  Selection of Consultants—Quality and Cost Based Selection: Consultant Services may be procured under contracts awarded on the basis of Quality- and Cost-based Selection in accordance with the provisions of Section II of Consultant Guidelines using the World Bank’s Standard RFP. In addition, the following selection methods may be adopted depending upon size and complexity of tasks and as agreed in the Procurement Plan: • Quality Based Selection (QBS) • Selection under Fixed Budget (FBS) • Least Cost Selection (LCS) • Single Source Selection (SSS) • Individual Consultant (IC) Single-Source Selection of consulting firms or individual experts may be used only if it presents a clear advantage over competition for the required consulting services in accordance with paragraph 3.8 of the World Bank’s Consultant Guidelines. Selection of consulting firms based on Consultants’ Qualifications (CQS) may be appropriate for assignments estimated to cost up to US$300,000 or equivalent in accordance with paragraph 3.7 of the Consultant Guidelines. Advertisement for expression of interest may be limited to the regional level for assignments estimated to cost less than US$100,000. For assignments that are estimated to cost less than US$50,000, March 22, 2015 advertisement is not mandatory as long as a shortlist of at least three proven qualified firms is established. Shortlists of consultants for services estimated to cost less than US$800,000 or the equivalent per contract may be composed entirely of national consultants (paragraph 2.7 of Consultant Guidelines). Services for assignments that meet the requirements set forth in paragraph 5.1 of the Consultant Guidelines may be procured under contracts awarded to individual consultants in accordance with the provisions of paragraphs 5.2 to 5.5 of the Consultant Guidelines. Under the circumstances described in paragraph 5.6 of the Consultant Guidelines, such contracts may be awarded to individual consultants on a sole source basis. 4. Consultancy Assignments with Selection Methods and Time Schedule: Available in separate Excel file. March 22, 2015 PROCUREMENT India : Himachal Pradesh Horticulture Development Project PLAN General Information Country: India 2017-09-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151744 GPN Date: 2017-04-03 Project Name: Himachal Pradesh Horticulture Development Project Loan / Credit No: IDA / 58380 Himachal Pradesh State Marketing Board Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned HPHDP PIU MKT WORKS 1 / Construction of Market Yard Component C: Market Devel Single Stage - Two E 2018-11-2 at Mehandli Rohru, Establish IDA / 58380 Post Request for Bids Open - National 4,620,000.00 0.00 Canceled 2017-12-20 2017-12-25 2018-02-05 2018-04-20 2018-05-25 opment nvelope 1 ment of market yard at Band rol APMC Kullu and Lahul Spit i HPHDP PIU MKT WORKS 2 / Upgradation and Modernizat ion of existing markets at fo urteen locations Parala Theo Component C: Market Devel Single Stage - Two E 11,800,000.0 2018-12-1 g , Dhalli, Solan ,Parwanoo, IDA / 58380 Post Request for Bids Open - National 0.00 Canceled 2018-01-10 2018-01-15 2018-02-26 2018-05-11 2018-06-15 opment nvelope 0 2 Palampur, Dharamsala ,Paun ta Sahib ,Takoli Mandi ,Kagni Mandi, Chamba , Patlikul, Shatt kullu and centralized in fras and civil work for IT IN-HPSMB-98463-CW-RFB / U pgradation and Modernizatio Component C: Market Devel Single Stage - Two E 2021-04-0 IDA / 58380 Post Request for Bids Open - National 1,000,000.00 364,370.76 Signed 2019-12-25 2019-11-25 2019-12-30 2019-12-17 2020-01-29 2020-01-10 2020-02-29 2020-02-22 2020-04-14 2020-05-23 n of existing Market Yard at P opment nvelope 9 aonta Sahib (Civil works) IN-HPSMB-146647-CW-RFB / Component C: Market Devel Single Stage - Two E 2021-04-1 Expansion and Modernization IDA / 58380 Post Request for Bids Open - National 285,715.00 223,637.43 Completed 2020-01-10 2020-01-10 2020-01-14 2020-02-24 2020-02-13 2020-03-19 2020-03-15 2020-05-04 2020-04-19 2020-05-27 opment nvelope 4 of Market Yard at Palampur . IN-HPSMB-146653-CW-RFB / Component C: Market Devel Single Stage - Two E 2021-05-1 Expansion and Moderization IDA / 58380 Post Request for Bids Open - National 714,286.00 0.00 Canceled 2020-01-31 2020-02-09 2020-03-10 2020-04-10 2020-05-15 opment nvelope 0 of Market Yard at Patlikuhal. IN-HPSMB-146649-CW-RFB / Component C: Market Devel Single Stage - Two E 1,161,136.1 2021-06-2 Up gradation and modernizat IDA / 58380 Post Request for Bids Open - National 714,286.00 Signed 2020-03-15 2020-07-29 2020-03-20 2020-07-29 2020-04-19 2020-08-29 2020-05-20 2020-09-09 2020-06-25 2020-10-04 opment nvelope 1 0 ion of Market Yard at Parala. IN-HPSMB-146651-CW-RFB / Component C: Market Devel Single Stage - Two E 2,156,378.3 2021-06-2 Construction of market yard IDA / 58380 Post Request for Bids Open - National 2,857,143.00 Signed 2020-03-20 2020-07-29 2020-03-25 2020-07-29 2020-04-24 2020-08-29 2020-05-25 2020-09-09 2020-06-29 2020-10-04 opment nvelope 6 4 at Mehandli, Rohru IN-HPSMB-146652-CW-RFB / Component C: Market Devel Single Stage - Two E 1,793,190.3 2021-07-0 Establishment of market yard IDA / 58380 Post Request for Bids Open - National 1,428,572.00 Signed 2020-03-30 2020-09-30 2020-04-04 2020-09-30 2020-05-04 2020-11-02 2020-06-04 2020-11-09 2020-07-09 2020-12-03 opment nvelope 6 4 at Bandrol,APMC Kullu and La haul & Spiti. IN-HPSMB-98468-CW-RFB / U pgradation and Modernizatio Component C: Market Devel Single Stage - Two E 2021-04-0 IDA / 58380 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2019-12-25 2019-12-10 2019-12-30 2019-12-17 2020-01-29 2020-02-29 2020-04-14 n of existing Market Yard at K opment nvelope 9 angni, Mandi (Civil work) IN-HPSMB-162035-CW-RFB / upgradation and modernizati Component C: Market Devel Single Stage - Two E 2021-01-2 IDA / 58380 Post Request for Bids Open - National 369,591.00 351,559.24 Signed 2020-02-28 2020-01-10 2020-03-04 2020-03-04 2020-04-15 2020-03-19 2020-06-28 2020-05-04 2020-08-02 2020-05-27 on of existing market yard at opment nvelope 9 kangni,Mandi(Civil Works) IN-HPSMB-146643-CW-RFB / Expansion and upgradation o Component C: Market Devel Single Stage - Two E 2021-03-1 IDA / 58380 Post Request for Bids Open - National 3,571,428.50 0.00 Canceled 2019-12-10 2020-02-14 2019-12-14 2020-02-24 2020-01-13 2020-02-13 2020-03-20 f capacity of terminal Market opment nvelope 5 Yard at Parwanoo IN-HPSMB-162053-CW-RFB / Up-gradation and strengtheni ng of existing terminal Marke t Yard at Parwanoo. Construc Component C: Market Devel Single Stage - Two E 1,604,768.2 2021-01-2 IDA / 58380 Post Request for Bids Open - National 1,624,783.00 Signed 2020-02-28 2020-01-10 2020-03-04 2020-04-15 2020-03-19 2020-06-28 2020-05-04 2020-08-02 2020-06-05 tion of new building, check p opment nvelope 3 9 ost, loading and unloading sh ed, water tank, civil works for ESMP Component, WS & SI a nd electrical installation work . IN-HPSMB-164045-CW-RFB / Component C: Market Devel Single Stage - Two E 2021-02-1 Expansion and Moderanizatio IDA / 58380 Post Request for Bids Open - National 648,665.00 0.00 Canceled 2020-03-12 2020-02-14 2020-03-17 2020-04-28 2020-07-11 2020-08-15 opment nvelope 1 n of Market Yard Shatt,Kullu. IN-HPSMB-196105-CW-RFB / Construction of Modern Fruit Component C: Market Devel Single Stage - Two E 1,351,788.1 2021-03-2 IDA / 58380 Post Request for Bids Open - National 1,131,896.02 Signed 2020-09-24 2020-09-30 2020-09-24 2020-09-30 2020-10-26 2020-11-02 2020-11-16 2020-11-09 2020-12-21 2020-12-06 and Vegetable Market Yard a opment nvelope 0 1 t Shilaroo,Shimla(H.P.) IN-HPSMB-218330-CW-RFB / Proposed Combined Facility Component C: Market Devel Single Stage - Two E 2022-02-0 IDA / 58380 Post Request for Bids Open - National 753,425.00 0.00 Canceled 2021-03-05 2021-09-22 2021-03-10 2021-09-23 2021-04-21 2021-11-09 2021-07-04 2022-01-14 2021-08-08 Building and Parking in Centr opment nvelope 4 e for Excellence at Shilaroo,D istt.-Shimla IN-HPSMB-238367-GO-RFB / National Procure DESIGN,SUPPLY,INSTALLATIO ment Document - N AND COMMISSIONING OF Component C: Market Devel Single Stage - Two E 2022-05-1 IDA / 58380 Post Request for Bids Open - National 2 Envelope proce 308,334.00 0.00 Canceled 2021-06-13 2021-06-09 2021-06-18 2021-06-10 2021-07-30 2021-07-12 2021-10-12 2021-11-16 WEIGH IN MTION AND BOOM opment nvelope 5 ss (Non Bank-SPD BARRIERS AT DIFFERENT MA ) RKET YARDS IN HIMACHAL P RADESH IN-HPSMB-243259-CW-RFB / National Procure UPGRADATION AND STRENG ment Document - Component C: Market Devel Single Stage - Two E 1,028,849.1 2022-12-1 THENING OF TERMINAL MARK IDA / 58380 Post Request for Bids Open - National 2 Envelope proce 1,055,942.00 Signed 2021-07-14 2021-07-20 2021-07-19 2021-07-20 2021-08-30 2021-08-23 2021-11-12 2021-09-14 2021-12-17 2021-10-07 opment nvelope 3 7 ET YARD PARWANOO-2,DISTT ss (Non Bank-SPD .-SOLAN(H.P.)(ACCESS ROAD ) OF MARKET YARD) Page 1 IN-HPSMB-244976-CW-RFB / National Procure DESIGN ,SUPPLY,INSTALLATI ment Document - ON AND COMISSIONING OF Component C: Market Devel Single Stage - Two E 2022-06-2 IDA / 58380 Post Request for Bids Open - National 2 Envelope proce 308,334.00 0.00 Canceled 2021-07-23 2021-07-26 2021-07-28 2021-07-27 2021-09-08 2021-08-27 2021-11-21 2021-12-26 WEIGH IN MOTION AND BOO opment nvelope 4 ss (Non Bank-SPD M BARRIERS AT DIFFERENT M ) ARKET YARDS IN HIMACHAL P RADESH IN-HPSMB-256554-CW-RFB / National Procure Design,Supply,Installation,Te ment Document - Component C: Market Devel Single Stage - Two E 2022-10-2 sting and Commissioning of IDA / 58380 Post Request for Bids Open - National 2 Envelope proce 308,334.00 0.00 Canceled 2021-11-22 2021-11-27 2022-01-08 2022-03-23 2022-04-27 opment nvelope 4 Weigh in Motion and Boom B ss (Non Bank-SPD arriers at different Market Ya ) rds in Himachal Pradesh National Procure IN-HPSMB-272976-CW-RFB / ment Document - Proposed Combined Facility Component C: Market Devel Single Stage - Two E 1,304,952.9 2022-12-2 IDA / 58380 Post Request for Bids Open - National 2 Envelope proce 753,425.00 Signed 2022-01-20 2022-01-20 2022-01-25 2022-01-20 2022-03-08 2022-02-21 2022-05-21 2022-03-02 2022-06-25 2022-03-29 Building and Parking in Centr opment nvelope 8 2 ss (Non Bank-SPD e for Excellence at Shilaroo , ) Distt.-Shimla(H.P.) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HPHDP PIU MKT GOODS PU Component C: Market Devel Single Stage - Two E R / Purchase of Price feed dis IDA / 58380 Post Request for Bids Open - National 120,000.00 0.00 Canceled 2017-10-16 2017-10-21 2017-12-02 2018-02-14 2018-03-21 2018-09-17 opment nvelope semination Equipment IN-HPSMB-221727-GO-RFP / DESIGN,SUPPLY,INSTALLATIO N,TESTING AND COMMISSION Component C: Market Devel Request for Propo Single Stage - Two E IDA / 58380 Post Open - National 308,334.00 0.00 Canceled 2021-03-01 2021-03-06 2021-04-17 2021-06-30 2021-08-04 2022-01-31 ING OF WEIGH IN MOTION A opment sals nvelope ND BOOM BARRIERS AT DIFF ERENT MARKET YARDS IN HI MACHAL PRADESH IN-HPSMB-218479-GO-RFB / Installation of Organic waste Component C: Market Devel Single Stage - Two E Convertor,Odour Control Equi IDA / 58380 Post Request for Bids Open - National 347,223.00 0.00 Canceled 2021-06-13 2021-07-17 2021-06-18 2021-08-07 2021-07-30 2021-08-18 2021-10-12 2021-11-16 2022-05-15 opment nvelope pments and Waste Collection Bins at Different Market Yard s in Himachal Pradesh IN-HPSMB-268041-GO-DIR / Supply,Installation,Testing an Component C: Market Devel d Commissioning of Rooftop IDA / 58380 Post Direct Selection Direct 280,000.00 332,162.18 Signed 2022-01-03 2022-01-01 2022-01-08 2022-01-17 2022-02-12 2022-02-01 2022-08-11 opment Solar Plants through Direct C ontracting at various market yard under HPHDP. IN-HPSMB-307654-GO-RFB / Supply, Installation,Testing a Component C: Market Devel Single Stage - Two E nd Commissioning of Passen IDA / 58380 Post Request for Bids Open - National 304,000.00 0.00 Signed 2022-08-08 2022-08-20 2022-08-13 2022-11-22 2022-09-05 2022-09-20 2022-09-30 2022-09-30 2022-10-23 2023-04-21 opment nvelope ger Lifts at different Market Yards in Himachal Pradesh. IN-HPSMB-361474-GO-RFB / Providing Installation ,Testin Component C: Market Devel Single Stage - Two E Under Imple g ,Commissioning of fire fight IDA / 58380 Post Request for Bids Open - National 132,860.00 0.00 2023-05-16 2023-05-19 2023-05-19 2023-05-20 2023-06-16 2023-06-28 2023-06-30 2023-12-27 opment nvelope mentation ing & sprinkler system includi ng civil and electric works for bandrol market yard. IN-HPSMB-361485-GO-RFB / Providing installation testing Component C: Market Devel Single Stage - Two E Under Imple commisioning of fire fighting IDA / 58380 Post Request for Bids Open - National 129,400.00 0.00 2023-05-16 2023-05-19 2023-05-19 2023-05-20 2023-06-16 2023-06-28 2023-06-30 2023-12-27 opment nvelope mentation and sprinkler system includin g civil and electricty works fo r Parwanoo market yard IN-HPSMB-249858-GO-RFB / Supply,Installation,Testing & Component C: Market Devel Single Stage - Two E Under Imple Commissioning of Organic w IDA / 58380 Post Request for Bids Open - National 96,688.00 0.00 2023-06-06 2023-06-04 2023-06-07 2023-06-12 2023-06-26 2023-06-29 2023-06-30 2023-09-28 opment nvelope mentation aste Convertor at Shatt,Parw anoo & Bandrol Market Yard s in Himachal Pradesh NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HPHDP PIU MKT CONSUL / Hi ring of International Consulta ncy for Business Plan Develo Component C: Market Devel Quality And Cost- Open - Internationa pment and Design for setting IDA / 58380 Post 700,000.00 744,891.15 Signed 2017-10-11 2016-06-14 2017-10-11 2017-10-11 2017-06-12 2017-10-13 2017-08-21 2017-10-28 2017-10-31 2017-12-09 2017-11-23 2018-01-14 2018-02-07 2020-11-09 opment Based Selection l up of 2 New and Upgradation of existing 14 Primary and S econdary whole sale markets of Himachal Pradesh INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN(Textual Part) Project information: INDIA, Assam Agribusiness and Rural Transformation Project (APART) Project Implementation agency: Assam Rural Infrastructure and Agricultural Services Society (ARIASS)is the main agency. Date of the Procurement Plan (Textual Part) : February 03, 2022 Period covered by this Procurement Plan:Until publication of next version of the Procurement Plan (Textual Part). Preamble In accordance with paragraph5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”)the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plansand conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEPconstitute the Procurement Plan for the Project.The following conditionsapply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Procurement for the project will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers, July 2016, applicable to Investment Project Financing (IPF). The project will be subject to the World Bank’s Anticorruption Guidelines, dated October 15, 2006, as revised in January 2011 and July 2016. The table below describes various procurement methods to be used for activities financed by the loan. The thresholds (Table 1) indicated will govern the procurement approach and methods; Table 1: Procurement Thresholds Procurement Approaches and Methods Thresholds (US$ equivalent) Open international (works – including turnkey, Any value activity supply and installation of plant and equipment and PPP) Open national (works – including turnkey, supply Below 40 million and installation of plant and equipment and PPP) Open international (goods, IT system, and non- Any value activity consulting services) Open national (goods, IT system, and non- Below 10 million consulting services) National request for quotation (goods and Up to 100,000 works) Direct selection No threshold; For works, goods, non-consulting services and IT system procurement: According to paragraphs 6.8– 6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Shortlist of national consultants Up to 2,000,000 Procurement prior-review thresholds. The World Bank will prior review the following contracts: 1. Works (including turnkey, supply and installation of plant and equipment and PPP): All contracts more than US$ 15 million equivalent 2. Goods, IT system and Non-consulting services: All contracts more than US$4 million equivalent 3. Consultants: All contracts >US$2 million equivalent for firms and >US$400,000 equivalent for individuals 4. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds 5. Additional provisions as mentioned at paragraph 2.2, 2.3, 2.4 & 2.5 of Annex I (Mandatory Procurement Prior Review Thresholds) under Bank Procedure (Effective August 01, 2018), “Procurement in IPF and Other Operational Procurement Matters” will also apply. National Procurement Arrangements:National competition for the procurement of works, goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: 1. Only the model bidding documents for National Competitive Procurement (NCP) agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding. 2. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. 3. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. 4. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. 5. Government e-Marketplace (GeM) set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. 6. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. 7. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 8. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 9. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. 10. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. Domestic preference-The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement of Works, Goods (Supply and Installation; and IT Equipment), Non-Consultancy Services and Consultancy Services – As per procurement plan approved in STEP. PROCUREMENT India : Assam Agribusiness and Rural Transformation Project PLAN General Information Country: India 2019-05-21 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155617 GPN Date: Project Name: Assam Agribusiness and Rural Transformation Project Loan / Credit No: IBRD / 87800 Assam Agricultural University Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-OPIU-AAU-220708-CW-RF Request for Bids - B / Civil works for newly setu Component C: Fostering Mar Single Stage - Two E Small Works SPD 2023-04-1 p Agricultural Market Intellig IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 178,571.42 152,693.81 Signed 2021-06-08 2021-10-01 2021-06-13 2022-03-15 2021-07-25 2021-11-02 2021-10-07 2022-01-03 2021-11-11 2022-02-11 nvelope (2 envelope proce 6 ence unit office building at A ence Enhancement ss) ssam Agricultural University, Jorhat, Assam, India IN-OPIU-AAU-231642-CW-RF Q / Minor Civil works related t Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E 2022-02-0 o setting up of Farmer Produ IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 50,328.58 42,587.56 Signed 2021-06-13 2022-03-24 2021-08-08 2022-05-08 tions nvelope 4 cer Company Coordination ce ence Enhancement PD) ntre at Assam Agricultural Un iversity, Jorhat IN-OPIU-AAU-266883-CW-RF Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E 2022-01-2 Q / Construction of low cost i IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 26,613.33 24,904.13 Completed 2021-12-22 2021-12-17 2022-01-09 2021-10-09 tions nvelope 6 nsect proof net house 12 nos ence Enhancement PD) . IN-OPIU-AAU-304487-CW-RF Q / Construction of Shed for s afe keeping of farm machiner y 7 nos. at the following AAU Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E Pending Imp 2022-10-2 stations KVK Kamrup, KVK Ba IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 26,305.49 0.00 2022-08-02 2022-09-27 tions nvelope lementation 7 rpeta, KVK Nagaon, KVK Soni ence Enhancement PD) tpur, KVK Kokrajhar, KVK Mor igaon and KVK Jorhat 1 US$ = Rs. 79.83 IN-OPIU-AAU-310859-CW-RF Q / Construction of 10 nos. lo Component C: Fostering Mar Request for Quota Request for Quota Single Stage - One E 2022-12-0 w cost insect proof net house IBRD / 87800 ket-led Production and Resili Post Open - National tions (Non Bank-S 31,305.80 0.00 Completed 2022-09-10 2022-12-13 2022-10-12 tions nvelope 1 with sprinkler/drip irrigation s ence Enhancement PD) ystem. 1$ = Rs. 79.61 IN-OPIU-AAU-326474-CW-RF B / Different Works for Devel National Procure opment of Fisheries Based In Component C: Fostering Mar ment Document - Single Stage - Two E Pending Imp 2023-11-0 tegrated Farming System Mo IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 259,518.22 0.00 2022-12-01 2022-12-06 2023-01-17 2023-04-01 2023-05-06 nvelope lementation 2 dels for Livelihood and Incom ence Enhancement ss (Non Bank-SPD e Generation of Farmers at C ) VSc., AAU, Khanapara, Guwa hati-781022, Assam National Procure IN-OPIU-AAU-358498-CW-RF Component C: Fostering Mar ment Document - B / Establishment of one (1) F Single Stage - Two E Pending Imp 2024-03-3 IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 279,878.76 0.00 2023-05-10 2023-05-15 2023-06-26 2023-09-08 2023-10-02 arm Machinery Training Cent nvelope lementation 0 ence Enhancement ss (Non Bank-SPD ers at Assam Agricultural Uni ) versity, Jorhat, Assam IN-OPIU-AAU-358501-CW-RF National Procure B / Establishment of two (2) F Component C: Fostering Mar ment Document - arm Machinery Training Cent Single Stage - Two E Pending Imp 2024-03-3 IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 508,919.26 0.00 2023-05-10 2023-05-15 2023-06-26 2023-09-08 2023-10-02 ers at KVK-Nagoan and Sarat nvelope lementation 0 ence Enhancement ss (Non Bank-SPD Chandra Singha College of A ) griculture, Dhubri under Assa m Agricultural University, Jor hat. IN-OPIU-AAU-362895-CW-RF B / Title: Development of Fish eries Based Integrated Farmi Request for Bids - ng System Models for Livelih Component C: Fostering Mar Single Stage - Two E Small Works SPD Pending Imp 2023-12-2 ood and Income Generation IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 166,910.90 0.00 2023-05-29 2023-06-03 2023-06-13 2023-06-22 2023-06-26 nvelope (2 envelope proce lementation 3 of Farmers at College of Vete ence Enhancement ss) rinary Science. AAU, Guwaha ti. Tendering for the above work was divided into two (2) pack ages. Package 1 and Packag eIN-OPIU-AAU-363142-CW-RF 2 B / Title: Development of Fish eries Based Integrated Farmi National Procure ng System Models for Livelih Component C: Fostering Mar ment Document - Single Stage - Two E Pending Imp 2023-12-2 ood and Income Generation IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 81,308.30 0.00 2023-05-29 2023-06-03 2023-06-13 2023-06-22 2023-06-26 nvelope lementation 3 of Farmers at College of Vete ence Enhancement ss (Non Bank-SPD rinary Science. AAU, Guwaha ) ti. Tendering for the above w ork was divided into two (2) packages. Package 1 and Pac kage 2 National Procure IN-OPIU-AAU-363158-CW-RF Component C: Fostering Mar ment Document - B / Title: Development of Mo Single Stage - Two E Pending Imp 2023-12-2 IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 2 Envelope proce 72,848.00 0.00 2023-05-29 2023-06-03 2023-06-13 2023-06-22 2023-06-26 del Seed bank at College of F nvelope lementation 3 ence Enhancement ss (Non Bank-SPD isheries, RAHA, Nagoan. ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-OPIU-AAU-114957-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU : Procurement of Co IBRD / 87800 Post Open - National 14,286.00 17,682.65 Completed 2019-06-29 2020-06-19 2019-08-24 2019-07-30 2019-10-23 2020-05-20 Enterprise Development tions nvelope mbine Harvester (Mini) IN-OPIU-AAU-114966-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Recir IBRD / 87800 Post Open - National 10,000.00 0.00 Canceled 2019-06-29 2019-08-24 2019-10-23 Enterprise Development tions nvelope culating Batch Dryer IN-OPIU-AAU-114971-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Indent IBRD / 87800 Post Open - National 11,429.00 11,453.62 Completed 2019-06-29 2020-06-19 2019-08-24 2019-07-30 2019-10-23 2019-11-15 Enterprise Development tions nvelope - cylinder Separator Page 1 IN-OPIU-AAU-114973-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Rice IBRD / 87800 Post Open - National 26,000.00 22,027.60 Completed 2019-06-29 2020-06-20 2019-08-24 2019-07-21 2019-10-23 2019-08-31 Enterprise Development tions nvelope Transplantor IN-OPIU-AAU-114972-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU, Procurement of Port IBRD / 87800 Post Open - National 17,143.00 18,795.72 Completed 2019-06-29 2020-06-20 2019-08-24 2019-07-30 2019-10-23 2020-02-18 Enterprise Development tions nvelope able Rice Mill. IN-OPIU-AAU-114974-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Power IBRD / 87800 Post Open - National 12,500.00 13,704.80 Completed 2019-06-29 2020-08-24 2019-08-24 2019-07-30 2019-10-23 2020-03-01 Enterprise Development tions nvelope Tiller Inclined plate planter IN-OPIU-AAU-114975-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU, Procurement of Mus IBRD / 87800 Post Open - National 10,714.00 0.00 Canceled 2019-06-29 2019-08-24 2019-10-23 Enterprise Development tions nvelope tard Seed Drill 2 Row IN-OPIU-AAU-114976-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU Procurement : Power IBRD / 87800 Post Open - National 19,643.00 11,684.97 Completed 2019-06-29 2020-08-24 2019-08-24 2019-07-30 2019-10-23 2020-01-07 Enterprise Development tions nvelope Paddy Weeder IN-OPIU-AAU-114978-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / AAU, Procurement of Maiz IBRD / 87800 Post Open - National 27,143.00 0.00 Canceled 2019-06-29 2019-08-24 2019-10-23 Enterprise Development tions nvelope e Planter (Power Tiller Operat ed). IN-OPIU-AAU-114982-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 18,571.00 13,620.24 Completed 2019-06-29 2020-06-19 2019-08-24 2019-07-30 2019-10-23 2020-02-20 Q / AAU Procurement : Potato Enterprise Development tions nvelope Planter IN-OPIU-AAU-118782-NC-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of GIS Softw IBRD / 87800 Post Open - National 12,811.42 8,008.36 Completed 2019-06-28 2020-12-24 2019-08-23 2020-02-02 2019-10-22 2020-03-14 Enterprise Development tions nvelope are, AAU Jorhat IN-OPIU-AAU-118780-GO-RF Q / Procurement of Computer Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 14,285.71 20,305.94 Completed 2019-06-28 2020-12-29 2019-08-23 2020-01-07 2019-10-22 2020-02-21 servers for satellite data proc Enterprise Development tions nvelope essing, AAU Jorhat, Through GeM . IN-OPIU-AAU-118783-NC-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of Image pr IBRD / 87800 Post Open - National 23,714.28 8,551.30 Completed 2019-06-28 2020-12-23 2019-08-23 2019-11-02 2019-10-22 2020-02-18 Enterprise Development tions nvelope ocessing software, AAU Jorha t IN-OPIU-AAU-122187-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 19,304.30 18,605.56 Completed 2019-07-16 2020-02-03 2019-08-09 2018-12-11 2019-08-15 2019-03-30 Enterprise Development tions nvelope al machine Reaper for AAU, J orhat IN-OPIU-AAU-122192-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 23,373.90 2,371.08 Completed 2019-07-16 2020-05-11 2019-08-09 2018-12-11 2019-08-15 2019-03-20 Enterprise Development tions nvelope al machine Axial Flow Thresh er for AAU, Jorhat IN-OPIU-AAU-122194-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 10,898.60 1.24 Completed 2019-07-16 2019-08-09 2018-12-11 2019-08-15 2019-03-20 Enterprise Development tions nvelope al goods Super Bag for AAU, J orhat. IN-OPIU-AAU-122197-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 15,550.70 14,673.50 Signed 2019-07-16 2021-01-02 2019-08-09 2018-12-11 2019-08-15 Enterprise Development tions nvelope al product RCC Ring Bin for A AU, Jorhat. IN-OPIU-AAU-122205-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 43,478.30 3,959.54 Completed 2019-07-16 2020-05-11 2019-08-09 2018-12-11 2019-08-15 2019-03-21 Enterprise Development tions nvelope al machine Portable Rice Mill for AAU, Jorhat. IN-OPIU-AAU-122207-GO-RF Q / Procurement of agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 18,724.60 16,997.66 Completed 2019-07-16 2020-05-19 2019-08-09 2018-12-11 2019-08-15 2019-03-21 al machine Seed cum Fertiliz Enterprise Development tions nvelope er Drill for AAU, Jorhat IN-OPIU-AAU-122213-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 10,898.60 9,958.16 Completed 2019-07-16 2020-05-19 2019-08-09 2018-12-11 2019-08-15 2019-03-21 Enterprise Development tions nvelope al machine Power weeder for AAU, Jorhat. IN-OPIU-AAU-122214-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 14,492.80 13,198.04 Completed 2019-07-16 2020-05-18 2019-08-09 2018-12-11 2019-08-15 2019-03-21 Enterprise Development tions nvelope al machine Drum Seeder for AAU, Jorhat. IN-OPIU-AAU-122217-GO-RF Component A: Enabling Agri Request for Quota Single Stage - One E Q / Procurement of agricultur IBRD / 87800 Post Open - National 25,869.60 3,354.80 Completed 2019-07-16 2020-05-18 2019-08-09 2018-12-11 2019-08-15 2019-03-20 Enterprise Development tions nvelope al machine Rice Transplanter for AAU, Jorhat IN-OPIU-AAU-157433-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Combine Harvest IBRD / 87800 Post Open - National 16,856.30 18,209.13 Completed 2020-02-19 2020-12-08 2020-04-15 2020-02-02 2020-10-12 2020-05-20 Enterprise Development tions nvelope er (Mini) for Assam Agricultur al University under APART pr oject. IN-OPIU-AAU-157434-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Re-circulating Bat IBRD / 87800 Post Open - National 9,832.84 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 Enterprise Development tions nvelope ch Dryer for Assam Agricultur al University under APART pr oject. IN-OPIU-AAU-157437-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Portable Rice Mill IBRD / 87800 Post Open - National 37,926.67 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 Enterprise Development tions nvelope for Assam Agricultural Univer sity under APART project. IN-OPIU-AAU-157442-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Indent-Cylinder S IBRD / 87800 Post Open - National 11,237.53 3,001.86 Terminated 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 Enterprise Development tions nvelope eparator for Assam Agricultur al University under APART pr oject. IN-OPIU-AAU-157444-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 11,237.53 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 al Rice Flake Machine for Ass Enterprise Development tions nvelope am Agricultural University un der APART project. IN-OPIU-AAU-157447-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Rice Transplanter IBRD / 87800 Post Open - National 25,284.45 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 Enterprise Development tions nvelope for Assam Agricultural Univer sity under APART project. Page 2 IN-OPIU-AAU-157449-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Power Paddy We IBRD / 87800 Post Open - National 13,485.04 8,068.99 Completed 2020-02-19 2020-12-29 2020-04-15 2020-06-04 2020-10-12 2020-10-11 Enterprise Development tions nvelope eder for Assam Agricultural U niversity under APART projec t. IN-OPIU-AAU-157450-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 22,475.06 18,556.93 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2020-12-15 al Machine Seed Drill for Ass Enterprise Development tions nvelope am Agricultural University un der APART project. IN-OPIU-AAU-157451-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 14,046.91 7,838.94 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2020-11-14 al Machine Drum Seeder for Enterprise Development tions nvelope Assam Agricultural University under APART project. IN-OPIU-AAU-157452-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Battery Operated IBRD / 87800 Post Open - National 16,856.30 4,034.49 Terminated 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 Enterprise Development tions nvelope Power Sprayer for Assam Agr icultural University under AP ART project. IN-OPIU-AAU-157453-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Axial Flow Thresh IBRD / 87800 Post Open - National 20,227.56 19,648.51 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2021-03-27 Enterprise Development tions nvelope er for Assam Agricultural Uni versity under APART project. IN-OPIU-AAU-157467-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 21,070.37 18,420.48 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2020-10-08 al Reaper Machine for Assam Enterprise Development tions nvelope Agricultural University under APART project. IN-OPIU-AAU-157469-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E al Machine Solar Bubble Drye IBRD / 87800 Post Open - National 9,832.84 8,716.13 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2021-01-01 Enterprise Development tions nvelope r for Assam Agricultural Univ ersity under APART project. IN-OPIU-AAU-157470-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 11,799.41 11,271.13 Completed 2020-02-19 2020-12-30 2020-04-15 2020-06-04 2020-10-12 2021-01-01 al Super Bag for Assam Agric Enterprise Development tions nvelope ultural University under APAR T project. IN-OPIU-AAU-157473-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 10,394.71 0.00 Canceled 2020-02-19 2020-04-15 2020-10-12 al RCC Ring Bin for Assam Ag Enterprise Development tions nvelope ricultural University under AP ART project. IN-OPIU-AAU-157476-GO-RF Q / Procurement of Agricultur Component A: Enabling Agri Request for Quota Single Stage - One E IBRD / 87800 Post Open - National 11,237.53 4,666.70 Completed 2020-02-19 2020-05-13 2020-04-15 2018-12-11 2020-10-12 2019-03-21 al Dry Grinding Machine for A Enterprise Development tions nvelope ssam Agricultural University under APART project. IN-OPIU-AAU-171158-GO-RF Q / Procurement of Gas Chro Component C: Fostering Mar Request for Quota Single Stage - One E matography for IRRI supporte IBRD / 87800 ket-led Production and Resili Post Open - National 37,500.00 35,538.27 Completed 2020-05-06 2020-12-23 2020-05-24 2020-05-27 2020-06-23 2021-01-23 tions nvelope d activity under APART at Ass ence Enhancement am Agricultural University, Jo rhat IN-OPIU-AAU-161173-GO-DIR / Procurement of Power Tiller Component C: Fostering Mar Operated Inclined Plate Briq Under Imple IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 714.28 0.00 2020-05-04 2020-01-10 2020-05-09 2020-01-10 2020-06-13 2020-07-13 uette Drill Cum Weeder for IR mentation ence Enhancement RI supported activity under A PART for Assam Agricultural University, Jorhat. IN-OPIU-AAU-170713-GO-DIR Component C: Fostering Mar / Procurement of Paddy seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 41,871.42 32,979.07 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-09-29 Ranjit Sub-1 for Kharif 2020 ence Enhancement under APART project for IRRI supported activities. IN-OPIU-AAU-170721-GO-DIR Component C: Fostering Mar / Procurement of Paddy Seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 16,392.85 13,550.58 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 Bahadur Sub-1 for Kharif 202 ence Enhancement 0 under APART project for IR RI supported activities. IN-OPIU-AAU-170726-GO-DIR Component C: Fostering Mar / Procurement of paddy seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 9,150.00 6,640.95 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 Swarna Sub-1 for Kharif 2020 ence Enhancement under APART project for IRRI supported activities. IN-OPIU-AAU-170729-GO-DIR Component C: Fostering Mar / Procurement of paddy seed IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 14,914.28 12,359.34 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 Bina Dhan-11 for Kharif 2020 ence Enhancement under APART project for IRRI supported activities. IN-OPIU-AAU-170768-GO-DIR / Procurement of paddy seed Component C: Fostering Mar Joha Rice (Kola/Keteki/Boku) f IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct 160.71 1,824.44 Completed 2020-05-04 2020-05-05 2020-05-09 2020-05-05 2020-05-18 2020-05-07 2020-06-17 2020-11-10 or Kharif 2020 under APART ence Enhancement project for IRRI supported act ivities. IN-OPIU-AAU-118787-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Laptop, A IBRD / 87800 ket-led Production and Resili Post Open - National 12,214.28 8,071.85 Completed 2021-02-20 2021-02-10 2021-03-12 2019-08-08 2021-03-17 2019-11-12 tions nvelope AU Jorhat through GeM ence Enhancement IN-OPIU-AAU-212813-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Construction of low cost i IBRD / 87800 ket-led Production and Resili Post Open - National 27,771.42 26,697.61 Completed 2021-03-02 2021-02-18 2021-03-10 2020-11-13 2021-03-11 2020-12-30 tions nvelope nsect proof net house under ence Enhancement APART project IN-OPIU-AAU-220372-GO-RF Component C: Fostering Mar Q / Procurement of Refrigera Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 10,714.50 10,341.90 Completed 2021-03-05 2021-02-22 2021-03-27 2020-10-23 2021-03-29 2021-01-28 tor Shaker Incubator for Bana tions nvelope ence Enhancement na Tissue Culture Lab. under APART project. IN-OPIU-AAU-220378-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Portable IBRD / 87800 ket-led Production and Resili Post Open - National 38,571.43 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope Rice Mill under APART Project ence Enhancement . IN-OPIU-AAU-220383-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Rice Tran IBRD / 87800 ket-led Production and Resili Post Open - National 68,571.43 60,338.75 Completed 2021-03-05 2021-08-03 2021-04-30 2021-08-04 2021-10-27 2021-11-27 tions nvelope splanter under APART Project ence Enhancement . Page 3 IN-OPIU-AAU-220387-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Mine Com IBRD / 87800 ket-led Production and Resili Post Open - National 17,142.86 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope bine Harvester under APART ence Enhancement project. IN-OPIU-AAU-220392-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Rice Flak IBRD / 87800 ket-led Production and Resili Post Open - National 11,428.57 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope e Machine under APART Proje ence Enhancement ct. IN-OPIU-AAU-220396-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Re-Circul IBRD / 87800 ket-led Production and Resili Post Open - National 10,000.00 0.00 Canceled 2021-03-05 2021-04-30 2021-10-27 tions nvelope ating Batch Dryer under APA ence Enhancement RT project. IN-OPIU-AAU-220398-GO-RF Q / Procurement of network Component C: Fostering Mar Request for Quota Single Stage - One E accessories for internet conn IBRD / 87800 ket-led Production and Resili Post Open - National 18,550.03 17,319.37 Completed 2021-03-05 2021-07-20 2021-04-30 2020-12-22 2021-05-20 2021-04-01 tions nvelope ectivity in the OPIU_APART GI ence Enhancement S lab and office room under APART project. IN-OPIU-AAU-231638-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Paddy se IBRD / 87800 ket-led Production and Resili Post Open - National 34,370.27 24,172.33 Completed 2021-06-13 2021-07-16 2021-07-25 2021-05-22 2021-08-24 2021-10-05 tions nvelope ed variety Ranjit Sub 1 an a ence Enhancement mount of 42390 Kg IN-OPIU-AAU-231636-GO-RF Component C: Fostering Mar Q / Procurement of Paddy se Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 15,008.10 11,175.97 Completed 2021-06-13 2021-07-16 2021-07-25 2021-05-22 2021-08-24 2021-10-05 ed variety Bahadur Sub 1 an tions nvelope ence Enhancement amount of 18510 kg. IN-OPIU-AAU-250472-GO-RF B / Procurement of 21 nos. of Component C: Fostering Mar Mini track-type Combine Har Single Stage - Two E IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 469,286.00 462,590.67 Signed 2021-09-06 2021-12-14 2021-09-11 2022-03-08 2021-09-13 2022-01-29 2021-10-25 2022-02-19 2021-11-05 2022-03-08 2021-12-05 vester for 7 newly establishe nvelope ence Enhancement d training centres and alread y established KVKs stations u nder APART IN-OPIU-AAU-250474-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 2 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 31,428.60 24,582.90 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-27 2021-11-13 tions nvelope Re-circulating Batch Dryer un ence Enhancement der APART. IN-OPIU-AAU-250477-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 16 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 73,571.40 82,760.65 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-04-23 tions nvelope Portable Rice Mill under APAR ence Enhancement T IN-OPIU-AAU-250478-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 21,142.90 21,067.24 Completed 2021-09-11 2021-11-27 2021-10-29 2021-11-16 2021-11-13 2022-03-30 tions nvelope Rice Puffing Machine under A ence Enhancement PART IN-OPIU-AAU-250480-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 2 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 21,428.60 17,917.25 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-09-01 tions nvelope Rice Flake Machine under AP ence Enhancement ART IN-OPIU-AAU-250483-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 11 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 24,857.10 17,957.25 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-03-30 tions nvelope Reaper under APART ence Enhancement IN-OPIU-AAU-250485-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 22 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 12,571.40 10,389.33 Completed 2021-09-11 2021-11-24 2021-10-29 2021-11-27 2021-11-13 2022-12-19 tions nvelope Open Drum Thresher under A ence Enhancement PART IN-OPIU-AAU-250487-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 29,714.30 27,744.25 Completed 2021-09-11 2021-11-26 2021-10-29 2021-11-16 2021-11-13 2022-03-30 tions nvelope Paddy Transplanter under AP ence Enhancement ART IN-OPIU-AAU-250490-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 13,714.30 7,874.85 Completed 2021-09-11 2021-11-27 2021-10-29 2021-11-16 2021-11-13 2022-04-01 tions nvelope Multi crop Planter under APA ence Enhancement RT IN-OPIU-AAU-250493-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 9 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 23,142.90 23,409.94 Completed 2021-09-11 2021-11-27 2021-10-29 2021-11-16 2021-11-30 2022-01-01 tions nvelope Axial Flow Thresher under AP ence Enhancement ART IN-OPIU-AAU-250494-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 15 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 10,714.30 4,574.36 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-03-31 tions nvelope Dry Grinding Machine under ence Enhancement APART IN-OPIU-AAU-250495-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 42,857.10 18,111.50 Completed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 2022-04-01 tions nvelope Laser Land Leveler ence Enhancement IN-OPIU-AAU-250496-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of 3 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 85,714.30 79,963.74 Signed 2021-09-11 2021-11-29 2021-10-29 2021-11-16 2021-11-13 tions nvelope Small Seed Processing Unit u ence Enhancement nder APART IN-OPIU-AAU-256787-GO-RF Q / Procurement of 4 nos. of Component C: Fostering Mar Request for Quota Single Stage - One E Rice Transplanter each for K IBRD / 87800 ket-led Production and Resili Post Open - National 26,780.32 26,806.20 Completed 2021-10-24 2021-11-26 2021-10-29 2021-08-04 2021-11-03 2021-09-16 tions nvelope VK, Lakhimpur and RARS, La ence Enhancement khimpur as directed by SPD, ARIAS Society. IN-OPIU-AAU-266880-GO-RF Q / Procurement of Paddy Se Component C: Fostering Mar Request for Quota Single Stage - One E ed BINA Dhan 11 (12400 kg) IBRD / 87800 ket-led Production and Resili Post Open - National 12,640.00 12,597.09 Completed 2021-12-22 2022-02-12 2022-01-11 2021-12-31 2022-01-31 2022-03-30 tions nvelope and DRR Dhan 44 (3400 kg) f ence Enhancement or BORO season under AWP 2021-22. IN-OPIU-AAU-266886-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Laptop 16 IBRD / 87800 ket-led Production and Resili Post Open - National 10,666.66 9,419.17 Completed 2021-12-22 2021-12-22 2022-01-10 2021-12-04 2022-01-26 2021-12-22 tions nvelope nos. ence Enhancement IN-OPIU-AAU-266888-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Network IBRD / 87800 ket-led Production and Resili Post Open - National 22,666.66 19,397.32 Completed 2021-12-22 2021-12-23 2022-01-02 2021-10-09 2022-01-31 2022-02-11 tions nvelope Attach Storage Drive 2 nos. ence Enhancement IN-OPIU-AAU-267155-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Field Spe IBRD / 87800 ket-led Production and Resili Post Open - National 39,333.33 0.00 Canceled 2021-12-22 2022-01-31 2022-05-31 tions nvelope ctroradiometer 1 no. ence Enhancement Page 4 IN-OPIU-AAU-267162-GO-RF Q / Drone 1 no. includes : i Drone with compatibility to change payload sensor. Component C: Fostering Mar ii Multi-spectral and thermal Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 30,986.66 0.00 Canceled 2021-12-22 2022-02-16 2022-05-31 sensors. tions nvelope ence Enhancement iii Software for drone data pr ocessing. iv License renewal and maint enance cost. IN-OPIU-AAU-272689-GO-RF Component C: Fostering Mar Q / For supply and installatio Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 25,361.82 24,749.53 Completed 2022-01-29 2022-01-21 2022-02-23 2021-06-29 2022-02-26 2021-12-10 n of GI PVC cages, Fish Seeds tions nvelope ence Enhancement , Fish Feeds, Medicine etc. in Beels at APART districts. IN-OPIU-AAU-272766-GO-RF Q / Supply of Fish Seeds, Fish Component C: Fostering Mar Request for Quota Single Stage - One E Feeds, Fertilizers, Lime etc. f IBRD / 87800 ket-led Production and Resili Post Open - National 25,361.82 561.85 Signed 2022-01-26 2022-06-07 2022-03-26 2022-04-17 2022-08-23 tions nvelope or Multiple stocking and Multi ence Enhancement ple Harvesting of Fish at diffe rent APART districts. 7(245.1)/APART/2018-19/CIP Component C: Fostering Mar Request for Quota Single Stage - One E /30923-33 / 2 nos. of Potato IBRD / 87800 ket-led Production and Resili Post Open - National 14,592.73 4,710.87 Completed 2022-02-28 2022-03-04 2022-04-25 2022-03-03 2022-05-25 2022-05-21 tions nvelope Grader. ence Enhancement 1$ = INR 75.38 IN-OPIU-AAU-304328-GO-RF Component C: Fostering Mar Q / Procurement of 3 nos. of Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 11,273.78 0.00 Completed 2022-08-02 2022-11-03 2022-09-17 2022-10-17 2023-01-06 Solar Bubble Dryer tions nvelope ence Enhancement 1 US$ = Rs. 79.83 IN-OPIU-AAU-304486-GO-RF Component C: Fostering Mar Q / 2 nos. of Ticker Board for Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 10,021.14 0.00 Completed 2022-08-12 2022-10-14 2022-10-03 2022-11-02 AMIU tions nvelope ence Enhancement 1 US$ = Rs. 79.83 IN-OPIU-AAU-312152-GO-RF Q / Procurement of Fish Seed Component C: Fostering Mar s, Fish Feeds, Lime, Fertilizer Request for Quota Single Stage - One E Pending Impl IBRD / 87800 ket-led Production and Resili Post Open - National 17,531.25 0.00 2022-09-10 2022-10-25 2023-04-23 s etc. for Multiple Stocking a tions nvelope ementation ence Enhancement nd Multiple Harvesting of Fis h under APART. 1 US$ = Rs. 79.86 IN-OPIU-AAU-304086-GO-RF Q / Procurement of 18 nos. of Component C: Fostering Mar Request for Quota Single Stage - One E Tablet for data collection to A IBRD / 87800 ket-led Production and Resili Post Open - National 10,042.62 8,894.78 Completed 2022-07-31 2022-09-08 2022-08-19 2022-07-27 2022-09-08 2022-08-31 tions nvelope MIU FDEs. ence Enhancement 1 US$ = Rs. 79.66 IN-OPIU-AAU-330903-GO-DIR Component C: Fostering Mar / Procurement of 3 nos. of El Under Imple IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 16,925.50 0.00 2023-02-08 2023-02-13 ectric Motor operated Briquet mentation ence Enhancement te Making FDP Machine. IN-OPIU-AAU-330904-GO-DIR / Procurement of 10 nos. of D Component C: Fostering Mar irect Seeder for Rice 11 Rows Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 35,513.22 0.00 2022-12-22 2022-12-27 2023-01-09 2023-02-08 FDP ZERO TILL DRILL With U ementation ence Enhancement SG Fertilizer Briquette Deep Placement applicator attach ment 5 Rows FDP Machine. IN-OPIU-AAU-337292-GO-RF Q / Procurement of Workstati Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl on computers for Satellite Da IBRD / 87800 ket-led Production and Resili Post Open - National 18,441.00 0.00 2023-02-01 2023-03-19 2023-09-15 tions nvelope ementation ta Processing under Phase II I ence Enhancement RRI Supported Activities Obj. 1 AWP 2022-23 IN-OPIU-AAU-340395-GO-RF Q / Procurement of Mapping Component C: Fostering Mar Request for Quota Single Stage - One E Under Imple Drone with Multispectral Sen IBRD / 87800 ket-led Production and Resili Post Open - National 43,028.08 0.00 2023-02-15 2023-03-30 2023-04-25 2023-10-22 tions nvelope mentation sor, Thermal Sensors and Sof ence Enhancement tware for Drone image proce ssing IN-OPIU-AAU-340401-GO-RF Component C: Fostering Mar Q / Procurement of Mapping Request for Quota Single Stage - One E Under Imple IBRD / 87800 ket-led Production and Resili Post Open - National 24,420.02 0.00 2023-02-15 2023-05-03 2023-04-25 2023-10-22 Drone with Multispectral Sen tions nvelope mentation ence Enhancement sor and software for Drone i mage processing. IN-OPIU-AAU-340403-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Procurement of Field Spe IBRD / 87800 ket-led Production and Resili Post Open - National 68,376.06 0.00 Canceled 2023-02-15 2023-03-31 2023-04-25 2023-10-22 tions nvelope ctroradiometer ence Enhancement IN-OPIU-AAU-347315-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 1 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 71,757.58 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Multi Seed Processing unit ence Enhancement IN-OPIU-AAU-347317-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 73,346.76 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Laser Land Leveler with tract ence Enhancement or IN-OPIU-AAU-347318-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 15,891.80 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Mechanical Transplanter (Wa ence Enhancement lk-behind type) IN-OPIU-AAU-348012-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 17 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 124,689.50 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2023-11-04 nvelope ementation Reaper-Cum-Binder ence Enhancement IN-OPIU-AAU-347321-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 30,561.15 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Rice Puff Machine. ence Enhancement IN-OPIU-AAU-347323-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 5 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 61,122.30 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Rice Flake machine ence Enhancement IN-OPIU-AAU-347324-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl Q / Procurement of 17 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 41,563.17 0.00 2023-03-19 2023-05-03 2023-10-30 tions nvelope ementation Cocoon ence Enhancement IN-OPIU-AAU-348010-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 6 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 183,366.91 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2024-02-02 nvelope ementation LSU or Batch Dryer ence Enhancement Page 5 IN-OPIU-AAU-348009-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 8 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 97,795.69 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2023-11-04 nvelope ementation Mechanical Transplanter (4-w ence Enhancement heel type) IN-OPIU-AAU-348008-GO-RF Component C: Fostering Mar Single Stage - Two E Pending Impl B / Procurement of 13 nos. of IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 158,917.99 0.00 2023-03-18 2023-03-23 2023-05-04 2023-07-02 2023-08-06 2023-11-04 nvelope ementation Flatbed Dryer ence Enhancement IN-OPIU-AAU-361443-GO-RF Component C: Fostering Mar Request for Quota Single Stage - One E Under Imple Q / Procurement of 4 nos. of IBRD / 87800 ket-led Production and Resili Post Open - National 9,742.14 0.00 2023-05-25 2023-06-12 2023-06-17 2023-06-27 tions nvelope mentation Chlorophyll Meter ence Enhancement IN-OPIU-AAU-361926-GO-DIR / Direct procurement of foun dation/breeder seed of Ranjit Component C: Fostering Mar Pending Impl Sub-1, Swarna Sub-1, Bahad IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 38,576.70 0.00 2023-05-23 2023-05-28 2023-06-03 2023-07-03 ementation ur Sub-1 and BINA Dhan-11 f ence Enhancement or the production of Paddy th rough the FPC Shankar Azan, Nagaon. IN-OPIU-AAU-361930-GO-DIR / Direct procurement of foun Component C: Fostering Mar dation/breeder seed of Ranjit Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 22,940.85 0.00 2023-05-23 2023-05-28 2023-06-03 2023-07-03 Sub-1, Swarna Sub-1 and Ba ementation ence Enhancement hadur Sub-1 for the productio n of Paddy through the FPC Poohar, Morigaon. IN-OPIU-AAU-361931-GO-DIR / We need to go for direct pro curement of foundation/bree Component C: Fostering Mar der seed of Ranjit Sub-1 and Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 17,407.70 0.00 2023-05-23 2023-05-28 2023-06-03 2023-07-03 Bahadur Sub-1 for the produ ementation ence Enhancement ction of Paddy through the se lected FPC Tetelia, Kamrup w hich has been earmarked in t he AWP 2023-24. IN-OPIU-AAU-364922-GO-DIR / Procurement of 2 nos. of Tr Component C: Fostering Mar ansplanter Mounted 4 Rows Pending Impl IBRD / 87800 ket-led Production and Resili Post Direct Selection Direct - National 14,261.50 0.00 2023-06-22 2023-06-27 2023-08-01 2023-09-30 with FDP Applicator ementation ence Enhancement 1US$ = INR 82.39 IN-OPIU-AAU-367108-GO-RF B / Establishing a Seed Testin Component C: Fostering Mar Single Stage - Two E Pending Impl g Laboratory in the Departm IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 79,500.00 0.00 2023-06-22 2023-06-27 2023-07-27 2023-10-09 2023-11-13 2024-03-27 nvelope ementation ent of Plant Breeding and Ge ence Enhancement netics at AAU, Jorhat-13 IN-OPIU-AAU-361311-GO-RF Q / Procurement of Tensiom Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl eter for10 nos. experiment (8 IBRD / 87800 ket-led Production and Resili Post Open - National 9,746.10 0.00 2023-06-25 2023-07-18 2023-07-28 tions nvelope ementation nos. of Tensiometer per expe ence Enhancement riment i.e; 80 nos. of Tensio meter) IN-OPIU-AAU-367650-GO-RF B / Procurement of feed testi Component C: Fostering Mar ng laboratory equipments at Single Stage - Two E Pending Impl IBRD / 87800 ket-led Production and Resili Post Request for Bids Open - National 134,293.74 0.00 2023-06-29 2023-07-04 2023-08-15 2023-10-28 2023-12-02 2024-03-31 Department of Animal Nutriti nvelope ementation ence Enhancement on, College of Veterinary Scie nce, AAU, Khanapara, Guwah ati-781022 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-OPIU-AAU-118785-NC-DIR / Procurement of data sets fo Component A: Enabling Agri IBRD / 87800 Post Direct Selection Direct 20,957.14 0.00 Canceled 2019-06-23 2019-06-28 2019-08-02 2019-10-01 r Development of Spatial dat Enterprise Development abase for extrapolation doma ins IN-OPIU-AAU-118786-NC-DIR / Procurement of Acquisition Component A: Enabling Agri IBRD / 87800 Post Direct Selection Direct 15,814.28 0.00 Canceled 2019-06-23 2019-06-28 2019-08-02 2019-10-01 planning for satellite data for Enterprise Development extrapolation domain. IN-OPIU-AAU-161469-NC-RF Q / Printing of brochures, sta Component C: Fostering Mar Request for Quota Single Stage - One E ndees, stand calendar, traini IBRD / 87800 ket-led Production and Resili Post Open - National 28,357.14 25,467.83 Completed 2020-05-09 2020-12-22 2020-07-04 2020-06-12 2020-08-03 2022-03-31 tions nvelope ng manual, booklet and fact ence Enhancement sheets under APART AAU, Jor hat. IN-OPIU-AAU-213008-NC-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / E-tendering for Rice Know IBRD / 87800 ket-led Production and Resili Post Open - National 78,571.42 34,157.89 Completed 2021-02-20 2021-07-26 2021-04-18 2021-07-27 2021-10-15 2022-09-29 tions nvelope ledge Bank video production. ence Enhancement IN-OPIU-AAU-220406-NC-RF Component C: Fostering Mar Request for Quota Single Stage - One E Q / Printing of Outreach Mate IBRD / 87800 ket-led Production and Resili Post Open - National 70,857.14 30,620.21 Completed 2021-03-05 2021-08-18 2021-04-30 2021-08-25 2021-10-27 2023-05-31 tions nvelope rials under APART Project ence Enhancement IN-OPIU-AAU-267168-NC-RF Q / Development, framework and design of web GIS and re lated decision tools includes: i. Pre-planning and prototype Component C: Fostering Mar Request for Quota Single Stage - One E development IBRD / 87800 ket-led Production and Resili Post Open - National 30,266.66 20,897.27 Completed 2021-12-22 2022-03-14 2022-02-16 2022-03-12 2022-08-15 tions nvelope ii. Technical feasibility assess ence Enhancement ment iii. Web services database an d coding iv. Support for any bug fixing , app crash etc. IN-OPIU-AAU-304481-NC-RF Q / Printing of ATLAS, brochu Component C: Fostering Mar res, booklets, and standees u Request for Quota Single Stage - One E IBRD / 87800 ket-led Production and Resili Post Open - National 30,313.94 0.00 Completed 2022-07-31 2022-10-17 2022-09-16 2022-12-15 nder APART project tions nvelope ence Enhancement 1 US$ = Rs. 79.83 IN-OPIU-AAU-310872-NC-RF Component C: Fostering Mar Request for Quota Single Stage - One E Under Imple Q / Printing of Crop Suitabilit IBRD / 87800 ket-led Production and Resili Post Open - National 10,017.86 0.00 2022-09-10 2022-10-14 2022-11-13 tions nvelope mentation y ATLAS ence Enhancement 1US$ = Rs. 79.86 Page 6 IN-OPIU-AAU-337296-NC-RF Q / Procurement of GIS Softw are for establishment of GIS f Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl acilities at multiple locations IBRD / 87800 ket-led Production and Resili Post Open - National 18,441.00 0.00 2023-02-01 2023-03-19 2023-09-15 tions nvelope ementation as sub-units within GIS lab. a ence Enhancement t AAU colleges under Phase II IRRI Supported activity Objec tive 1 AWP 2022-23 IN-OPIU-AAU-337298-NC-RF Q / Procurement of Image Pr ocessing Software for establi Component C: Fostering Mar Request for Quota Single Stage - One E Pending Impl shment of GIS facilities at mu IBRD / 87800 ket-led Production and Resili Post Open - National 31,349.89 0.00 2023-02-01 2023-03-19 2023-09-15 tions nvelope ementation ltiple locations as sub-units w ence Enhancement ithin GIS lab at AAU colleges under Phase II IRRI Supporte d activities AWP 2022-23 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7 PROCUREMENT PLAN (Textual Part) Project information: [Congo, Republic of] [Statistics Capacity Building Project] [P133731] Project Implementation agency: [Statistics Capacity Building Project] Date of the Procurement Plan: [28 Avril 2017] Period covered by this Procurement Plan: [November 29, 2016 – 31 December 2017] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in not applicable, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable Works: [is not applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information. PROCUREMENT Congo, Republic of : CG-Statistics Capacity Building Project PLAN General Information Country: Congo, Republic of 2017-06-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133731 GPN Date: Project Name: CG-Statistics Capacity Building Project Loan / Credit No: IDA / 55000, IDA / V0870, IBRD / 88510, IDA / V1720, IDA / 70540 CG-Statistics Capacity Building Project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned PSTAT-045-T-AON-20 / Trava Component 1: Institutional D Single Stage - One E 4,328,351.5 2021-01-0 ux de construction du compl IBRD / 88510 evelopment, Human Resour Prior Request for Bids Open - National 5,172,414.00 Signed 2020-03-20 2020-10-14 2020-03-25 2020-12-22 2020-05-06 2021-02-02 2020-06-05 2021-07-09 2020-07-10 2021-06-28 nvelope 2 6 exe INS -CASP ces and Organizational Struc ture GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PSTAT-014-F-ED-17 / Acquisi Component 1: Institutional D tion du logiciel PHOENIX pour evelopment, Human Resour IDA / 55000 Prior Direct Selection Direct 30,000.00 39,054.64 Signed 2017-07-30 2017-08-04 2017-09-08 2017-08-11 2018-03-07 les prix ( AFRISTAT)_ Regulari ces and Organizational Struc sation, contrat déjà signé ture PSTAT-030-F-ED-17 / Acquisi Component 1: Institutional D tion des tablettes et de leurs evelopment, Human Resour IDA / 55000 Prior Direct Selection Direct 999,129.00 999,129.00 Completed 2017-12-01 2017-12-06 2018-01-10 2017-12-15 2018-07-09 2018-01-16 accessoires (Solution solaire, ces and Organizational Struc Micro SD Card et Clé )_ UNO ture PS PSTAT-012-F-AOI-17 / Acquis Component 1: Institutional D ition des tablettes pour le Re evelopment, Human Resour Open - Internationa Single Stage - One E censement Général de la Pop IDA / 55000 Prior Request for Bids 1,000,000.00 0.00 Canceled 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 ces and Organizational Struc l nvelope ulation et de l'Habitation ( R ture GPH) et des enquêtes de l'IN S. PSTAT-013-F-AON-17 / Équip ements de matériels informa tiques pour les sectoriels, DD Component 1: Institutional D statistique, l'Assistance tech evelopment, Human Resour Single Stage - One E IDA / 55000 Prior Request for Bids Open - National 700,000.00 0.00 Canceled 2017-10-20 2017-10-25 2017-12-06 2018-01-05 2018-02-09 2018-08-08 nique de l'INS , gestion de re ces and Organizational Struc nvelope ssources des humaines de l'I ture NS, Prix et de l'UCP , et les é quipements pour le système d'archivage de l'INS et du PS TAT PSTAT-030-F-DIR-18 / Acquis Component 2: Data producti ition de 45 téléphones satelli IDA / V0870 on, Dissemination and the u Post Direct Selection Direct 81,000.00 72,151.56 Completed 2018-07-24 2018-06-12 2018-07-29 2018-06-01 2018-09-02 2018-06-13 2019-03-01 2018-07-06 taires et de 45 cartes SIM po se of Statistics ur les enquêtes de l'INS PSTAT-27-F-CF-18 / Acquisiti Component 2: Data producti Request for Quota Single Stage - One E on de mobilier de bureau pou IDA / V1720 on, Dissemination and the u Post Limited 73,000.00 60,674.66 Completed 2018-12-29 2018-10-31 2019-02-23 2018-11-15 2019-08-22 2018-12-21 tions nvelope r les bureaux de l'INS et du B se of Statistics CR PSTAT-19-F-DC-18 / Acquisiti Component 2: Data producti Request for Quota Single Stage - One E on de matériels et équipeme IDA / V0870 on, Dissemination and the u Post Limited 50,000.00 0.00 Canceled 2019-01-02 2019-02-27 2019-08-26 tions nvelope nt informatique pour le RGPH se of Statistics et le REGEC PSTAT-057-SASC-18 / Acquis ition de 15 groupes électrogè Component 2: Data producti Request for Quota Single Stage - One E nes et accessoires d'installati IDA / V0870 on, Dissemination and the u Post Limited 7,500.00 0.00 Canceled 2018-12-29 2019-02-23 2019-08-22 tions nvelope on pour le dénombrement pi se of Statistics lote (RGPH) et REGEC PSTAT-020-CF-F-19 / Acquisi Component 1: Institutional D tion de 100 GPS pour les enq evelopment, Human Resour Request for Quota Single Stage - One E IBRD / 88510 Post Limited 72,727.00 47,166.94 Completed 2019-09-04 2019-07-11 2019-10-30 2019-07-30 2020-04-27 2019-09-24 uêtes de l'Institut National de ces and Organizational Struc tions nvelope la Statistique ( REGEC, RGPH ture ) PSTAT-024-CF-F-19 / Acquisi Component 3: Project Manag Request for Quota Single Stage - One E tion de fourniture de bureau IBRD / 88510 Post Limited 18,181.00 0.00 Canceled 2019-10-05 2019-11-30 2020-05-28 ement tions nvelope et de consommables informa tique pour l'UCP PSTAT-021-CF-F-19 / Acquisi Component 1: Institutional D tion de matériels informatiqu evelopment, Human Resour Request for Quota Single Stage - One E IBRD / 88510 Post Limited 99,000.00 68,552.06 Completed 2019-10-05 2019-11-08 2019-11-30 2019-11-06 2020-05-28 2020-02-07 es pour les services statistiqu ces and Organizational Struc tions nvelope es sectoriels et personnels a ture dditionnels PSTAT-034-F-AON-19 / Acqui Component 2: Data producti sition matériel et équipemen Single Stage - One E IBRD / 88510 on, Dissemination and the u Post Request for Bids Open - National 200,000.00 70,151.78 Completed 2019-12-20 2020-02-05 2019-12-25 2020-02-17 2020-02-05 2020-03-10 2020-03-06 2020-03-10 2020-04-10 2020-06-26 2020-10-07 2020-08-13 t informatiques pour les direc nvelope se of Statistics tions départementales de la statistique ( DDS) PSTAT-036F-DC-20 / Acquisit Component 1: Institutional D Request for Quota Single Stage - One E ion et installation groupe éle IBRD / 88510 evelopment, Human Resour Post Limited 50,000.00 38,382.12 Completed 2020-01-11 2020-01-09 2020-03-07 2020-01-28 2020-09-03 2020-02-04 tions nvelope ctrogène du nouveau site de ces and Organizational Struc l'INS ture PSTAT-037F-DC-20 / Acquisit Component 2: Data producti Request for Quota Single Stage - One E ion matériels aratoires pour l IBRD / 88510 on, Dissemination and the u Post Open - National 10,000.00 28,590.67 Completed 2020-01-19 2020-03-15 2020-02-04 2020-09-11 2020-04-22 tions nvelope a cartographie se of Statistics PSTAT-038F-DC-20 / Acquisit Component 2: Data producti Request for Quota Single Stage - One E ion de 90 gilets de sauvetage IBRD / 88510 on, Dissemination and the u Post Open - National 12,000.00 4,004.95 Completed 2020-01-19 2020-03-15 2020-02-04 2020-09-11 2020-02-12 tions nvelope / cartographie se of Statistics PSTAT-039F-DC-20 / Acquisit Component 2: Data producti Request for Quota Single Stage - One E ion de 320 matelas / cartogra IBRD / 88510 on, Dissemination and the u Post Open - National 5,300.00 7,767.18 Completed 2020-01-19 2020-03-15 2020-02-04 2020-09-11 2020-02-11 tions nvelope phie se of Statistics PSTAT-040F-DC-20 / Acquisit Component 2: Data producti Request for Quota Single Stage - One E ion de 80 petits groupes élec IBRD / 88510 on, Dissemination and the u Post Open - National 16,000.00 30,085.58 Completed 2020-01-19 2020-03-15 2020-02-13 2020-09-11 2020-02-26 tions nvelope trogènes et convertisseur ch se of Statistics argeur Page 1 Component 2: Data producti PSTAT-041F-DC-20 / Acquisit Request for Quota Single Stage - One E IBRD / 88510 on, Dissemination and the u Post Open - National 17,200.00 6,580.87 Completed 2020-01-19 2020-03-15 2020-02-04 2020-09-11 2020-02-12 ionde 320 kit camping house tions nvelope se of Statistics PSTAT-042F-DC-20 / Acquisit Component 2: Data producti Request for Quota Single Stage - One E ion materiel et fourniture de IBRD / 88510 on, Dissemination and the u Post Open - National 35,000.00 47,541.46 Terminated 2020-01-19 2020-03-15 2020-02-04 2020-09-11 tions nvelope bureau / cartographie se of Statistics PSTAT-048-F-DC-20 / acquisi Component 1: Institutional D Request for Quota Single Stage - One E tion de 120 motos pour le RE IBRD / 88510 evelopment, Human Resour Post Limited 176,000.00 93,053.84 Completed 2020-04-14 2020-07-16 2020-06-09 2020-08-25 2020-12-06 2020-09-05 tions nvelope GEC ces and Organizational Struc ture PSTAT-066-F-CF-20 / Acquisi Component 2: Data producti Request for Quota Single Stage - One E tion de 50 tablettes pour le R IBRD / 88510 on, Dissemination and the u Post Limited 9,000.00 25,010.58 Completed 2020-09-15 2020-09-01 2020-11-10 2020-09-17 2021-05-09 2020-09-24 tions nvelope EGEC se of Statistics PSTAT-067-F-CF-20 / acquisit Component 2: Data producti Request for Quota Single Stage - One E ion de deux (2) ordinateurs e IBRD / 88510 on, Dissemination and the u Post Limited 6,000.00 12,610.82 Completed 2020-09-15 2020-09-03 2020-11-10 2020-10-06 2021-05-09 2020-10-13 tions nvelope t matériel informatique pour l se of Statistics e REGEC PSTAT-068-F-CF-20 / Acquisi Component 2: Data producti tion de 522 imperméables , Request for Quota Single Stage - One E IBRD / 88510 on, Dissemination and the u Post Limited 7,000.00 10,956.07 Completed 2020-09-23 2020-09-01 2020-11-18 2020-09-18 2021-05-17 2020-09-25 134 bottes et lampes de torc tions nvelope se of Statistics hes et piles pour mégaphone s PSTAT-069-F-CF-20 / concep Component 2: Data producti Request for Quota Single Stage - One E tion et impression des chasu IBRD / 88510 on, Dissemination and the u Post Limited 14,000.00 21,371.27 Completed 2020-09-27 2020-09-01 2020-11-22 2020-09-17 2021-05-21 2020-09-26 tions nvelope bles, casquettes, Tee-shirts se of Statistics Component 2: Data producti PSTAT-070-F-CF-20 / acquisit Request for Quota Single Stage - One E IBRD / 88510 on, Dissemination and the u Post Limited 14,000.00 22,604.23 Completed 2020-09-29 2020-09-02 2020-11-24 2020-09-17 2021-05-23 2020-10-02 ion de sacs à dos / REGEC tions nvelope se of Statistics Component 2: Data producti PSTAT-071-F-CF-20 / Achat b Request for Quota Single Stage - One E IBRD / 88510 on, Dissemination and the u Post Limited 9,000.00 11,488.06 Completed 2020-10-01 2020-09-01 2020-11-26 2020-09-17 2021-05-25 2020-10-03 avettes / REGEC tions nvelope se of Statistics Component 2: Data producti PSTAT-072-F-CF-20 / Achat g Request for Quota Single Stage - One E IBRD / 88510 on, Dissemination and the u Post Limited 4,000.00 10,012.53 Completed 2020-10-01 2020-09-01 2020-11-26 2020-09-17 2021-05-25 2020-09-26 el de protection/ REGEC tions nvelope se of Statistics PSTAT-076-F-CF-20 / Acquisi Component 2: Data producti Request for Quota Single Stage - One E tion matériel informatique en IBRD / 88510 on, Dissemination and the u Post Limited 30,000.00 23,978.90 Completed 2020-11-04 2020-09-25 2020-12-30 2020-10-24 2021-06-28 2020-10-25 tions nvelope quête prix extension IHPC se of Statistics PSTAT-063-F-DC-20 / Materi Component 1: Institutional D Request for Quota Single Stage - One E el pour enquête unité standa IBRD / 88510 evelopment, Human Resour Post Limited 25,000.00 0.00 Canceled 2020-03-25 2020-05-20 2020-11-16 tions nvelope rds ces and Organizational Struc ture PSTAT-053-F-DC-20 / Fournit Component 3: Project Manag Request for Quota Single Stage - One E IBRD / 88510 Post Limited 34,000.00 0.00 Canceled 2020-04-15 2020-06-10 2020-12-07 ure de bureau pour UCP ement tions nvelope PSTAT-052-F-DC-20 / mobilie Component 3: Project Manag Request for Quota Single Stage - One E IBRD / 88510 Post Limited 43,000.00 0.00 Canceled 2020-05-20 2020-07-15 2021-01-11 r de bureau ement tions nvelope PSTAT-002-F-DC-22 / Acquisi Component 2: Data producti Request for Quota Single Stage - One E tion imperméables, bottes po IBRD / 88510 on, Dissemination and the u Post Limited 7,000.00 3,075.60 Signed 2022-07-27 2022-05-10 2022-09-21 2022-05-21 2023-03-20 tions nvelope ur l'enquête EHCVM se of Statistics PSTAT-003-F-DC-22 / Masqu Component 2: Data producti Request for Quota Single Stage - One E es et gel de protection contre IBRD / 88510 on, Dissemination and the u Post Limited 5,000.00 1,073.31 Completed 2022-06-28 2022-05-10 2022-08-23 2022-05-30 2023-02-19 2022-06-10 tions nvelope la COVID se of Statistics PSTAT-005-F-DC-22 / Acquisi Component 2: Data producti Request for Quota Single Stage - One E tion sacs à dos enquête EHC IBRD / 88510 on, Dissemination and the u Post Limited 12,000.00 5,419.16 Completed 2022-05-23 2022-05-10 2022-07-18 2022-05-30 2023-01-14 2022-06-17 tions nvelope VM se of Statistics PSTAT- 005-F -ED-MENES CO Component 1: Institutional D NGO-22 / Acquisition d'un as evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 220,000.00 169,375.78 Signed 2022-04-30 2022-04-16 2022-05-05 2022-04-19 2022-06-09 2022-04-21 2022-12-06 censeur et d'un monte charg ces and Organizational Struc e pour le bâtiment de l'INS ture PSTAT-006-F-AON-22 / Acqui Component 1: Institutional D Single Stage - One E sition groupe électrogène (20 IBRD / 88510 evelopment, Human Resour Post Request for Bids Open - National 150,000.00 129,737.94 Signed 2022-05-25 2022-05-11 2022-05-30 2022-05-19 2022-07-11 2022-06-13 2022-08-10 2022-07-04 2022-09-14 2022-07-28 2023-03-13 nvelope 0 KVA) et transformateur (16 ces and Organizational Struc 0KVA) ture PSTAT-007-F-DC-22 / Mobilie Component 1: Institutional D Request for Quota Single Stage - One E Pending Impl r de bureau pour le bâtiment IBRD / 88510 evelopment, Human Resour Post Limited 20,000.00 0.00 2022-07-25 2022-09-19 2023-03-18 tions nvelope ementation du CASP ces and Organizational Struc ture PSTAT-009-F-DC-22 / acquisi Component 1: Institutional D Request for Quota Single Stage - One E tion 619 chasubles pour l'E IBRD / 88510 evelopment, Human Resour Post Limited 10,000.00 8,915.50 Completed 2022-06-28 2022-05-10 2022-08-23 2022-05-30 2023-02-19 2022-06-10 tions nvelope HCVM ces and Organizational Struc ture PSTAT-012-F-DC-22 / Acquisi Component 2: Data producti tion de 5230 seaux pour l'en Request for Quota Single Stage - One E IDA / 55000 on, Dissemination and the u Post Limited 13,000.00 0.00 Completed 2022-09-28 2022-09-09 2022-11-23 2023-05-22 2022-10-13 quête harmonisée sur les con tions nvelope se of Statistics ditions de vie des ménages ( EHCVM) PSTAT-11-F-DC-22 / acquisiti Component 2: Data producti Request for Quota Single Stage - One E on matériel d'enquête deuxiè IDA / 55000 on, Dissemination and the u Post Limited 16,000.00 0.00 Completed 2022-09-28 2022-09-09 2022-11-23 2023-05-22 2022-10-14 tions nvelope me phase de EHCVM se of Statistics PSTAT-13-F-DC-22 / Acquisiti Component 2: Data producti Request for Quota Single Stage - One E on 100 tables bancs pour le IBRD / 88510 on, Dissemination and the u Post Limited 12,000.00 0.00 Completed 2022-12-28 2022-11-15 2023-02-22 2023-08-21 2023-05-10 tions nvelope CASP se of Statistics PSTAT-014-F-DC-22 / Acquisi Component 2: Data producti Request for Quota Single Stage - One E tion de 150 malles pour docu IDA / 70540 on, Dissemination and the u Post Limited 6,930.00 0.00 Completed 2022-12-05 2022-12-20 2023-01-30 2023-07-29 tions nvelope ments techniques du RGPH se of Statistics PSTAT-016-F-22 / Acquisition Component 2: Data producti lampes torches (2500), mach Request for Quota Single Stage - One E IDA / 70540 on, Dissemination and the u Post Limited 14,000.00 0.00 Completed 2022-12-05 2022-12-20 2023-01-30 2023-07-29 ettes(50), piles (300 paquets tions nvelope se of Statistics ), boites de craies (700 boite s) pour le RGPH PSTAT-015-F-AON-22 / Acqui Component 2: Data producti sition imperméables (8500), Single Stage - One E IDA / 70540 on, Dissemination and the u Post Request for Bids Open - National 200,000.00 0.00 Completed 2022-12-20 2022-12-08 2022-12-25 2022-12-13 2023-02-05 2023-01-10 2023-03-07 2023-01-10 2023-04-11 2023-10-08 2023-03-07 bottes( 7000),Gilets de sauve nvelope se of Statistics tage pour le RGPH-5 Page 2 Component 2: Data producti PSTAT-017-F-DC-22 / Acquisi Request for Quota Single Stage - One E IDA / 70540 on, Dissemination and the u Post Limited 10,000.00 0.00 Completed 2022-12-20 2023-01-13 2023-02-14 2023-08-13 tions des banderoles (200) tions nvelope se of Statistics PSTAT-018-F-DC-22 / Acquisi Component 3: Project Manag Request for Quota Single Stage - One E tion de ordinateurs portable IDA / 70540 Post Limited 68,000.00 0.00 Completed 2023-02-04 2022-12-22 2023-04-01 2023-09-28 2023-02-24 ement tions nvelope s pour les stagiaires de l'INS PSTAT-008-F-DC-23 / Acquisi tion des équipements inform atiques ( 5ordinateurs de gr Component 2: Data producti Request for Quota Single Stage - One E ande capacité de traitement IDA / 70540 on, Dissemination and the u Post Limited 100,000.00 0.00 Completed 2023-03-13 2023-03-03 2023-05-08 2023-11-04 tions nvelope de données), 1 serveur, disq se of Statistics ue dur, 8000 cles USB, 8150 adaptateur clés USB... pour l e RGPH PSTAT-012-F-ED-SOCIETE TE Component 2: Data producti CLIB-23 / ACQUISITION DU L Direct - Internation IDA / 70540 on, Dissemination and the u Post Direct Selection 5,000.00 0.00 Canceled 2023-03-23 2023-03-28 2023-05-02 2023-10-29 OGICIEL DE SUIVI EN LIGNE D al se of Statistics ES TABLETTES DU RGPH-5 PSTAT-019-F-DC-23 / Achat Component 2: Data producti Request for Quota Single Stage - One E pneus (136) , batteries (34) p IDA / 70540 on, Dissemination and the u Post Limited 100.00 0.00 Canceled 2023-04-10 2023-06-05 2023-12-02 tions nvelope our véhicules ...dans le cadre se of Statistics du RGPH-5 PSTAT-018-F-DC-CG-23 / Fou Component 2: Data producti Request for Quota Single Stage - One E rniture et impression de 500 IDA / 70540 on, Dissemination and the u Post Limited 50,000.00 0.00 Completed 2023-06-05 2023-05-12 2023-07-31 2024-01-27 tions nvelope 0 T-Shirts complementaire a se of Statistics u RGPH-5 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PSTAT-003-F-ED-17 / Contrat maintenance et entretien ma Component 3: Project Manag IDA / 55000 Prior Direct Selection Direct 7,200.00 0.00 Canceled 2017-06-18 2017-06-23 2017-07-28 2018-01-24 tériel informatique_ Renouvel ement lement du contrat ( MAGES D 'ALLIANCES TAMA) PSTAT-004-F-ED-17 / Contrat de connexion internet. Recru tement d'une société chargé Component 3: Project Manag IDA / 55000 Prior Direct Selection Direct 60,000.00 0.00 Canceled 2017-06-25 2017-06-30 2017-08-04 2018-01-31 e de la connexion internet et ement de la fourniture de l'accès int ernet par fibre optique pour l' UCP et le BCR PSTAT-001 BIS- SASC- ED-17 / Renouvellement du contrat de service de gardiennage ( Component 3: Project Manag IDA / 55000 Prior Direct Selection Direct 34,243.00 32,136.39 Completed 2017-01-09 2018-03-19 2017-01-14 2017-02-18 2017-01-13 2017-08-17 2017-12-29 SUBLIME Congo) - Régularis ement ation dans STEP de l'ANO réç u depuis 11 janvier 2017_ co ntrat signé hors STEP PSTAT-006 BIS- SASC-ED-17 / Contrat du notaire pour la r Component 1: Institutional D édaction des contrats des bo evelopment, Human Resour IDA / 55000 Prior Direct Selection Direct 13,025.00 10,912.92 Completed 2017-03-07 2017-03-12 2017-04-16 2017-04-04 2017-10-13 2017-05-05 urses des étudiants ( Maître ces and Organizational Struc MOKOKO) _ Régularisation da ture ns STEP de l'ANO réçu depuis mars 2017 hors STEP PSTAT-002-BIS-SASC-ED-17 / Renouvellement du contrat d 'entretien des locaux de l'UC Component 3: Project Manag IDA / 55000 Prior Direct Selection Direct 9,600.00 8,418.00 Completed 2017-01-08 2017-09-14 2017-01-13 2018-03-15 2017-02-17 2017-01-13 2017-08-16 2017-12-30 P ( Service ALAN) _ Régularis ement ation dans STEP de l'ANO réç u depuis le 11 janvier 2017 h ors STEP PSTAT-002-F-ED-17 / Contrat entretien des locaux_ Renouv Component 3: Project Manag IDA / 55000 Prior Direct Selection Direct 9,600.00 0.00 Canceled 2017-06-25 2017-06-30 2017-08-04 2018-01-31 ellement du contrat d'entreti ement en des locaux de l'UCP ( SER VICE ALAN) PSTAT-001-F-ED-17 / Contrat de gardiennage- Renouvelle Component 3: Project Manag IDA / 55000 Prior Direct Selection Direct 34,243.00 0.00 Canceled 2017-06-25 2017-06-25 2017-06-25 2017-06-25 ment du contrat de gardienn ement age pour l'UCP et le BCR ( Su blime Congo) PSTAT-006-F-ED-17 / Contrat Notaire_ Recrutement d'un n Component 3: Project Manag IDA / 55000 Prior Direct Selection Direct 13,025.00 0.00 Canceled 2017-06-25 2017-06-30 2017-08-04 2018-01-31 otaire pour la rédaction des c ement ontrats des bourses des étud iants PSTAT-003-BIS-F-ED-17 / Re nouvellement du contrat de l Component 3: Project Manag IDA / 55000 Prior Direct Selection Direct 7,200.00 0.00 Canceled 2016-01-04 2016-01-04 2016-01-04 2016-01-04 2016-01-04 2016-01-04 a maintenance - entretien du ement materiel informatique PSTAT-004-BIS- F-ED-17 / Re crutement d'une société (CO Component 3: Project Manag IDA / 55000 Prior Direct Selection Direct 35,373.00 0.00 Canceled 2017-01-11 2017-01-11 NGO TELECOM) pour la conn ement exion internet de l'UCP et le l e BCR PSTAT-017BIS-SASC-17 / Rec Component 3: Project Manag Request for Quota Single Stage - One E rutement d'une société pour IDA / 55000 Post Limited 14,400.00 14,054.20 Completed 2018-01-02 2017-02-15 2018-02-27 2017-05-03 2018-08-26 2017-09-11 ement tions nvelope l'entretien du groupe électro gène et split PSTAT-007-F-CF-17 / Impres Component 2: Data producti Request for Quota Single Stage - One E sion de l'annuaire statistique IDA / 55000 on, Dissemination and the u Post Limited 20,000.00 14,054.20 Completed 2018-01-03 2017-02-15 2018-02-28 2017-05-03 2018-08-27 2017-09-11 tions nvelope 2014 du Congo se of Statistics PSTAT-017-F-17 / Recruteme nt d'une société pour l'entreti Component 3: Project Manag Request for Quota Single Stage - One E IDA / 55000 Post Limited 14,400.00 5,189.24 Completed 2018-01-03 2017-05-11 2018-02-28 2017-07-06 2018-08-27 2018-07-05 en du groupe électrogène et ement tions nvelope des split de l'UCP PSTAT-01-ASC-ED-18 / Acqui sition du logiciel TOM2PRO v Component 3: Project Manag IDA / V0870 Post Direct Selection Direct 31,000.00 28,881.02 Completed 2018-03-28 2018-03-14 2018-04-02 2017-09-11 2018-05-07 2018-03-11 2018-11-03 2018-04-25 ersion multi-projets et Mise e ement n réseau sur 3 ordinateurs ( TOMATE) Page 3 PSTAT-032-SASC-DIR-18 / Re Component 1: Institutional D nouvellement de la police as evelopment, Human Resour IDA / V0870 Post Direct Selection Direct 73,044.00 64,237.48 Completed 2018-07-04 2018-07-06 2018-07-09 2018-08-13 2018-07-10 2019-02-09 2018-07-14 surance de 16 véhicules ( INS ces and Organizational Struc et UCP) ( ALLIANZ CONGO) ture PSTAT-033-SASC-DIR-18 / Re Component 1: Institutional D crutement d'une société pour evelopment, Human Resour Request for Quota Single Stage - One E l'Entretien des locaux loués p IBRD / 88510 Post Limited 27,000.00 0.00 Canceled 2018-08-05 2018-08-30 2018-09-30 2019-03-29 ces and Organizational Struc tions nvelope ar le PSTAT pour l'Institut Nat ture ional de la Statistique PSTAT-034-SASC-DIR-18 / Re crutement d'une entreprise p Component 1: Institutional D our services d'Entretien des evelopment, Human Resour Request for Quota Single Stage - One E IBRD / 88510 Post Limited 12,000.00 0.00 Canceled 2019-01-02 2019-02-27 2019-08-26 split et le groupe électrogène ces and Organizational Struc tions nvelope des bureaux loués par le PST ture AT pour l'Institut National de la Statistique PSTAT-056-SASC-DIR-18 / Re Component 1: Institutional D nouvellement du contrat de s evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 42,164.00 15,080.71 Completed 2019-02-27 2018-12-31 2019-03-04 2018-12-31 2019-04-08 2019-01-02 2019-10-05 2019-05-31 ervices de gardiennage des l ces and Organizational Struc ocaux du PSTAT et des deux ture sites de l'INS PSTAT-058-SASC-DIR-18 / Re nouvellement du contrat pou Component 3: Project Manag IBRD / 88510 Post Direct Selection Direct 7,200.00 2,588.48 Completed 2019-01-28 2018-12-31 2019-02-02 2018-12-31 2019-03-09 2019-01-04 2019-09-05 2019-05-31 r l'entretien et maintenance ement du parc informatique du PST AT PSTAT-059-SASC-DIR-18 / Re Component 3: Project Manag nouvellement du contrat de l' IBRD / 88510 Post Direct Selection Direct 9,600.00 3,026.40 Completed 2019-01-28 2018-12-31 2019-02-02 2018-12-31 2019-03-09 2019-01-02 2019-09-05 2019-12-31 ement entretien des locaux du PSTA T PSTAT-010-CF- SASC-19 / Co Component 1: Institutional D ntrat d'assurance des véhicul evelopment, Human Resour Request for Quota Single Stage - One E IBRD / 88510 Post Limited 9,000.00 0.00 Canceled 2019-07-05 2019-08-30 2020-02-26 es de l'UCP et des véhicules ces and Organizational Struc tions nvelope affectés à l'INS pour les enqu ture êtes PSTAT-010-ED- SASC-19 / Co Component 1: Institutional D ntrat d'assurance véhicules p evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 9,000.00 5,100.73 Completed 2019-04-30 2019-04-01 2019-05-05 2019-04-01 2019-06-09 2019-04-24 2019-12-06 2019-04-25 our les de l'UCP et les véhicul ces and Organizational Struc es affectés à l'INS ture PSTAT-018-ED-SASC- 19 / Re nouvellement du contrat de s Component 3: Project Manag IBRD / 88510 Post Direct Selection Direct 4,500.00 4,232.64 Completed 2019-06-30 2019-05-31 2019-07-05 2019-05-31 2019-08-09 2019-05-31 2020-02-05 2019-12-31 ervices d'entretien des locau ement x de l'UCP PSTAT PSTAT-019-ED-SASC- 19 / Re Component 3: Project Manag nouvellement du contrat de s IBRD / 88510 Post Direct Selection Direct 7,000.00 7,003.16 Completed 2019-06-30 2019-05-31 2019-07-05 2019-05-31 2019-08-09 2019-05-31 2020-02-05 2020-12-30 ement ervice de gardiennage de l'U CP PSTAT PSTAT-020-ED-SASC- 19 / Re nouvellement du contrat de Component 3: Project Manag IBRD / 88510 Post Direct Selection Direct 3,600.00 3,532.31 Completed 2019-06-30 2019-05-31 2019-07-05 2019-05-31 2019-08-09 2019-05-31 2020-02-05 2020-01-08 prestation de service d'entret ement ien et maintenance informati que PSTAT-022-CF-SASC-19 / Im Component 2: Data producti pression des manuels de pro Request for Quota Single Stage - One E IBRD / 88510 on, Dissemination and the u Post Limited 63,636.00 53,132.96 Completed 2019-09-04 2019-06-21 2019-10-30 2019-07-11 2020-04-27 2019-08-31 ductions et diffusions statisti tions nvelope se of Statistics ques et des rapports d'étude s PSTAT-018-ED-SASC BIS-19 / Renouvellement du contrat d Component 3: Project Manag IBRD / 88510 Post Direct Selection Direct 4,500.00 0.00 Canceled 2019-06-28 2019-07-03 2019-08-07 2020-02-03 e services d'entretien des loc ement aux de l'UCP PSTAT PSTAT-043SASC-DC-20 / Loc Component 2: Data producti Request for Quota Single Stage - One E ation de 28 véhicules pour la IBRD / 88510 on, Dissemination and the u Post Open - National 45,000.00 0.00 Canceled 2020-01-19 2020-03-15 2020-09-11 tions nvelope cartographie se of Statistics Component 2: Data producti PSTAT-073-SASC-CF-20 / imp Request for Quota Single Stage - One E IBRD / 88510 on, Dissemination and the u Post Limited 13,000.00 30,551.54 Completed 2020-10-05 2020-09-23 2020-11-30 2020-10-14 2021-05-29 2020-11-03 ression des questionnaires tions nvelope se of Statistics PSTAT-074-SASC-CF-20 / Ass Component 2: Data producti Request for Quota Single Stage - One E urance au tiers des motocycl IBRD / 88510 on, Dissemination and the u Post Limited 10,000.00 0.00 Canceled 2020-10-05 2020-11-30 2021-05-29 tions nvelope ettes/ REGEC se of Statistics PSTAT-075-SASC-CF-20 / Im Component 3: Project Manag Request for Quota Single Stage - One E pression des bulletins d'infor IBRD / 88510 Post Limited 5,000.00 0.00 Canceled 2020-10-27 2020-12-22 2021-06-20 ement tions nvelope mation du PSTAT PSTAT-077-SASC-20 / Réalis Component 2: Data producti Request for Quota Single Stage - One E ation d'un spot publicitaire e IBRD / 88510 on, Dissemination and the u Post Limited 5,000.00 3,510.63 Completed 2020-11-04 2020-09-11 2020-12-30 2020-09-29 2021-06-28 2020-10-24 tions nvelope n trois langues pour le REGE se of Statistics C PSTAT-080-SASC-DC-20 / Im Component 2: Data producti Request for Quota Single Stage - One E pression des annuaires statis IBRD / 88510 on, Dissemination and the u Post Limited 25,000.00 46,894.35 Completed 2020-12-15 2020-12-01 2021-02-09 2020-12-29 2021-08-08 2021-03-13 tions nvelope tiques 2018 se of Statistics PSTAT-010-SNC-ED-CAPPED- 2022 / Recrutement par ent ente directe de l' agence de Component 2: Data producti paiement des enquêteurs ( IBRD / 88510 on, Dissemination and the u Post Direct Selection Direct 50,000.00 25,092.69 Signed 2022-06-30 2022-05-13 2022-07-05 2022-05-17 2022-08-09 2022-05-25 2023-02-05 CAPPED) dans le cadre de l'e se of Statistics nquête harmonisée sur les co nditions de vie des ménages (EHCVM) PSTAT-001-SASC-DC-22 / im Component 2: Data producti Request for Quota Single Stage - One E pression questionnaire enquê IBRD / 88510 on, Dissemination and the u Post Limited 50,000.00 0.00 Canceled 2022-06-27 2022-08-22 2023-02-18 tions nvelope te EHCVM se of Statistics PSTAT-016-SNC-DC-22 / Floc Component 2: Data producti Request for Quota Single Stage - One E age des T-Shirts (15 000) ; fl IDA / 70540 on, Dissemination and the u Post Limited 29,000.00 0.00 Completed 2022-12-25 2023-01-13 2023-02-19 2023-08-18 2023-05-08 tions nvelope ocage chasubles( 2000) se of Statistics PSTAT-02-SNC-DC-23 / Impr Component 2: Data producti Request for Quota Single Stage - One E ession des questionnaires RG IDA / 70540 on, Dissemination and the u Post Limited 138,000.00 0.00 Completed 2023-02-20 2023-03-17 2023-04-17 2023-10-14 2023-05-09 tions nvelope PH-5 se of Statistics Page 4 PSTAT-006-SNC-ED- ROGA R Component 2: Data producti OGA-23 / Composition d'une IDA / 70540 on, Dissemination and the u Post Direct Selection Direct - National 17,000.00 0.00 Completed 2023-03-10 2023-03-01 2023-03-15 2023-03-02 2023-04-19 2023-10-16 chanson pour le RGPH-5 se of Statistics PSTAT-016-SNC-ED-23 / Recr utement des agences de pai Component 2: Data producti ement ( société de téléphon Request for Quota Single Stage - One E IDA / 70540 on, Dissemination and the u Post Limited 150,000.00 0.00 Signed 2023-03-15 2023-03-15 2023-05-10 2023-11-06 ie mobile, établissement de tions nvelope se of Statistics microfinance, banque.. ) pour le paiement des agents de te rrain du RGPH CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PSTAT-015-C-QC-17 / Recrut ement d'une agence de com Component 2: Data producti munication pour la vulgarisat Consultant Qualifi IDA / 55000 on, Dissemination and the u Post Open - National 180,000.00 205,084.49 Completed 2017-07-16 2017-06-23 2017-08-06 2017-09-19 2017-11-30 2017-10-19 2018-05-30 2017-11-23 2018-06-05 2018-05-22 2020-12-02 ion des activités et produits d cation Selection se of Statistics u SSN et l'appui à la mise en œuvre du plan de communic ation du PSTAT PSTAT-17-C-SQC-18 / Sélecti Component 2: Data producti Consultant Qualifi on d'une firme chargée de co IDA / V0870 on, Dissemination and the u Post Open - National 75,000.00 0.00 Canceled 2018-05-31 2018-04-11 2018-06-21 2018-05-24 2018-08-04 2018-09-03 2018-10-08 2019-04-06 cation Selection nstituer la table de compositi se of Statistics on des aliments PSTAT-18-C-SQC-18 / SÉLEC Component 2: Data producti TION D'UNE FIRME CHARGÉE Consultant Qualifi IDA / V0870 on, Dissemination and the u Post Open - National 100,000.00 77,224.53 Signed 2018-06-29 2018-04-17 2018-07-20 2018-05-24 2018-09-02 2019-10-02 2018-10-02 2019-11-02 2018-11-06 2019-09-30 2019-05-05 D'ASSURER LE PAIEMENT DE cation Selection se of Statistics S AGENTS DE TERRAIN PSTAT-24-C-SQC-18 / Sélecti Component 1: Institutional D on d'un Bureau d'étude d'arc evelopment, Human Resour Consultant Qualifi IDA / V0870 Post Open - National 250,000.00 303,382.87 Signed 2018-06-29 2019-04-16 2018-07-20 2019-05-03 2018-09-02 2019-06-25 2018-10-02 2019-09-25 2018-11-06 2019-10-14 2019-05-05 hitecture et de vérification et ces and Organizational Struc cation Selection de suivi des travaux de const ture ruction PSTAT-029-C- SFQC-18 / Rec rutement d'un cabinet charg Component 3: Project Manag Quality And Cost- Open - Internationa Under Implement IBRD / 88510 Post 60,000.00 0.00 2018-07-31 2018-06-14 2018-08-21 2018-07-16 2018-10-04 2018-10-15 2018-11-01 2018-12-01 2019-01-05 2019-02-09 2020-02-09 e de l'audit externe du PSTAT ement Based Selection l ation exercice 2017 (PPA) -2018, 2 019 et 2020. PSTAT-24-C-SFQC-18 / Sélec Component 2: Data producti tion d'une firme chargée du Consultant Qualifi Open - Internationa IBRD / 88510 on, Dissemination and the u Prior 1,000,000.00 0.00 Canceled 2018-08-27 2018-09-17 2018-10-31 2018-11-30 2019-01-04 2019-07-03 monitoring externe de la sou cation Selection l se of Statistics s composante FBR du PSTAT Component 1: Institutional D PSTAT-047-C-QC-20 / Contrô Consultant Qualifi Open - Internationa IBRD / 88510 evelopment, Human Resour Post 135,000.00 95,952.14 Signed 2020-03-20 2020-05-18 2020-04-10 2020-05-29 2020-05-24 2020-09-18 2020-06-23 2020-10-21 2020-07-28 2020-10-28 2021-01-24 leur technique des travaux cation Selection l ces and Organizational Struc ture PSTAT-051-C-SFQC-20 / Audi Component 3: Project Manag Quality And Cost- Open - Internationa IBRD / 88510 Post 25,000.00 0.00 Canceled 2020-04-21 2020-05-12 2020-06-25 2020-07-23 2020-08-22 2020-09-26 2020-10-31 2021-10-31 t externe 2020 et 2021 ement Based Selection l PSTAT-003-C-SFQC-21 / Recr Component 3: Project Manag Quality And Cost- Open - Internationa utement cabinet audit extern IBRD / 88510 Post 45,000.00 24,174.11 Signed 2021-10-30 2021-09-17 2021-11-20 2021-10-05 2022-01-03 2021-12-06 2022-01-31 2022-01-10 2022-03-02 2022-02-14 2022-04-06 2022-02-22 2022-05-11 2022-04-02 2023-05-11 ement Based Selection l e exercice 2021,2020et 2023 PSTAT-01-SC-QC-23 / Recrut Component 2: Data producti ement agences de paiement Consultant Qualifi IDA / 70540 on, Dissemination and the u Post Open - National 150,000.00 0.00 Canceled 2023-01-25 2023-02-25 2023-02-15 2023-03-31 2023-04-30 2023-06-04 2023-12-01 des agents de terrains et sup cation Selection se of Statistics erviseurs pour le RGPH INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PSTAT-020-C-CI-17 / Recrute Component 1: Institutional D Individual Consult ment d'un consultant individ IDA / 55000 evelopment, Human Resour Prior Open 43,200.00 0.00 Canceled 2017-06-25 2017-09-14 2017-08-13 2017-09-03 2017-10-08 2018-04-06 ant Selection uel, spécialiste en ressources ces and Organizational Struc humaines ture PSTAT-005-C-ED-17 / Contra t du spécialiste en communic Component 3: Project Manag ation_ Renouvellement du co IDA / 55000 Prior Direct Selection Direct 110,376.00 0.00 Canceled 2017-06-18 2017-06-28 2017-09-01 2018-02-28 ement ntrat du spécialiste en comm unication de l'UCP sur une pé riode de 24 mois. PSTAT-018-C-ED-17 / Recrut Component 2: Data producti Individual Consult ement d'un consultant_ assis IDA / 55000 on, Dissemination and the u Prior Direct 134,000.00 0.00 Canceled 2017-06-18 2017-06-18 2017-06-18 2017-07-09 2018-01-05 ant Selection tance technique permanent se of Statistics pour le RGPH Component 3: Project Manag Individual Consult PSTAT-016-C-CI-17 / Recr IDA / 55000 Prior Open 43,200.00 0.00 Canceled 2017-06-25 2017-08-13 2017-09-03 2017-10-08 2018-04-06 ement ant Selection PSTAT-005- BIS-C-ED-17 / Re nouvellement du contrat du s Component 3: Project Manag Individual Consult IDA / 55000 Prior Direct 41,680.00 44,904.86 Completed 2017-02-28 2017-02-28 2017-02-28 2017-09-14 2017-02-28 2017-04-04 2017-02-28 2018-04-03 pécialiste en communication ement ant Selection de l'UCP pour une periode de 12 mois PSTAT-008-C-ED-17 / Recrut Component 2: Data producti ement d'un consultant indivi IDA / 55000 on, Dissemination and the u Prior Direct Selection Direct 35,400.00 0.00 Canceled 2017-06-25 2017-07-05 2017-09-08 2018-03-07 duel en cartographie censitai se of Statistics re pour le RGPH 2017 (Consu ltant JAMAGNE) PSTAT-021-C-ED-17 / Recrut ement du Coordonnateur de l 'UCP ( Dominique KIMPOUNI) Component 3: Project Manag IDA / 55000 Prior Direct Selection Direct 144,000.00 150,006.81 Completed 2017-08-14 2017-08-24 2017-10-28 2017-05-02 2018-04-26 2020-08-30 - Régularisation dans STEP d ement e l'ANO reçu depuis le 28 avr il 2017_ contrat signé hors S TEP PSTAT-022-C-CI-17 / Consult Component 1: Institutional D ant international principal po evelopment, Human Resour Individual Consult ur l'élaboration de la deuxiè IDA / 55000 Prior Limited 125,000.00 208,000.00 Signed 2017-07-10 2017-07-15 2017-08-05 2017-09-14 2017-09-09 2016-08-22 2018-03-08 ces and Organizational Struc ant Selection me édition du Plan National d ture e Développement du Congo PND-2 : 2017-2021. Page 5 PSTAT-025-C-CI-17 / consult ant international programma Component 1: Institutional D tion sectoriel et suivi évaluati evelopment, Human Resour Individual Consult IDA / 55000 Prior Limited 75,000.00 74,150.00 Completed 2016-08-15 2016-08-20 2016-09-10 2018-03-15 2016-10-15 2016-08-22 2017-04-13 2016-10-25 on pour L'élaboration de la d ces and Organizational Struc ant Selection euxième édition du Plan Nati ture onal de Développement du C ongo PND-2 : 2017-2021. PSTAT-024-C-CI-17 / Consult ant international en informati Component 1: Institutional D que, pour l'élaboration de la evelopment, Human Resour Individual Consult IDA / 55000 Prior Limited 75,000.00 138,600.00 Signed 2016-08-15 2016-08-20 2016-09-10 2017-09-14 2016-10-15 2016-08-22 2017-04-13 deuxième édition du Plan Nat ces and Organizational Struc ant Selection ional de Développement du ture Congo PND-2 : 2017-2021. PSTAT-023-C-CI-17 / Consult ant international macro bud Component 1: Institutional D gétaire l'élaboration de la de evelopment, Human Resour Individual Consult IDA / 55000 Prior Limited 75,000.00 74,150.00 Signed 2016-08-15 2016-08-20 2016-09-10 2017-09-14 2016-10-15 2016-08-29 2017-04-13 uxième édition du Plan Natio ces and Organizational Struc ant Selection nal de Développement du Co ture ngo PND-2 : 2017-2021. PSTAT-026-C-CI-17 / consult ant international suivi évalua Component 1: Institutional D tion pour L'élaboration de la evelopment, Human Resour Individual Consult IDA / 55000 Prior Limited 75,000.00 74,150.00 Completed 2016-08-15 2016-08-20 2016-09-10 2018-03-15 2016-10-15 2016-08-22 2017-04-13 2016-11-16 deuxième édition du Plan Nat ces and Organizational Struc ant Selection ional de Développement du ture Congo PND-2 : 2017-2021. PSTAT-019 BIS- C-CI-17 / Rec Component 2: Data producti Individual Consult rutement d'un consultant ind IDA / 55000 on, Dissemination and the u Post Open 12,000.00 10,310.84 Completed 2017-10-31 2017-12-19 2017-08-29 2018-01-09 2017-11-08 2018-02-13 2017-11-08 2018-08-12 2018-12-08 ant Selection ividuel pour le création du sit se of Statistics e web du PSTAT PSTAT-011-C-ED-17 / Renou vellement des contrats des i ngénieurs statisticiens et dé Component 1: Institutional D mographes de haut niveau n evelopment, Human Resour IDA / 55000 Prior Direct Selection Direct 38,400.00 0.00 Canceled 2017-02-17 2017-02-27 2017-05-03 2017-10-30 on employés, pour l'appui au ces and Organizational Struc x projets d'enquêtes et aux s ture ervices statistiques de l'INS d ans le cadre de la fidélisation et motivation (6 contrats ): B alossa Sivan PSTAT-018-BIS-C-ED-17 / Re Component 2: Data producti Individual Consult nouvellement du contrat de l IDA / 55000 on, Dissemination and the u Prior Direct 110,833.00 0.00 Canceled 2017-05-02 2017-05-02 ant Selection Assistant technique RGPH se of Statistics PSTAT-019-C-CI-17 / Recrute ment d'un consultant individ Component 3: Project Manag Individual Consult IDA / 55000 Post Open 12,000.00 0.00 Canceled 2017-06-25 2017-08-13 2017-09-03 2017-10-08 2018-04-06 uel en vue de la réalisation d ement ant Selection u site web du PSTAT PSTAT-031-C-CI-17 / Consult Component 1: Institutional D ant chargé de l'élaboration d evelopment, Human Resour Individual Consult IDA / V0870 Post Open 20,000.00 0.00 Canceled 2017-10-20 2017-10-20 2017-10-31 2017-10-31 2017-11-02 2017-11-03 u cadre de gestion environne ces and Organizational Struc ant Selection mentale et sociale dans STEP ture PSTAT-033-C-CI-17 / Consult Component 2: Data producti Individual Consult ant individuel international s IDA / V0870 on, Dissemination and the u Post Open 55,000.00 15,573.04 Completed 2018-02-28 2018-04-18 2018-03-08 2018-05-09 2018-03-29 2018-06-13 2018-03-30 2018-12-10 2018-06-06 ant Selection pécialiste en sondage se of Statistics PSTAT-034-C-CI-17 / consult Component 2: Data producti ant individuel un Expert "Dév Individual Consult IDA / V0870 on, Dissemination and the u Post Open 50,000.00 12,032.00 Completed 2018-02-28 2017-12-26 2018-04-18 2018-03-16 2018-05-09 2018-03-28 2018-06-13 2018-03-30 2018-12-10 2018-06-29 eloppeur, Collecte et Traitem ant Selection se of Statistics ent de données d'enquêtes C API" PSTAT-027-C-CI-17 / Recrute ment du Statisticien d'appui, Component 3: Project Manag Individual Consult Responsable de la Composan IDA / V0870 Post Open 45,000.00 0.00 Canceled 2018-03-12 2017-09-07 2018-04-30 2018-03-19 2018-05-21 2018-06-25 2018-12-22 ement ant Selection te 2 "Production de données, diffusion et utilisation des sta tistiques" du PSTAT PSTAT-016-BIS-C-CI-17 / Rec Component 3: Project Manag Individual Consult rutement d un Auditeur inter IDA / V0870 Post Open 45,000.00 0.00 Canceled 2018-03-12 2018-03-12 ement ant Selection ne au sein de l UCP PSTAT-029-C-CI-17 / Recrute Component 3: Project Manag Individual Consult ment d'un assistant adminis IDA / V0870 Post Open 30,000.00 16,666.46 Completed 2018-03-12 2018-03-26 2018-04-30 2018-04-17 2018-05-21 2018-04-23 2018-06-25 2018-04-23 2018-12-22 2020-12-31 ement ant Selection tratif au sein du PSTAT PSTAT-009-C-ED-17 / Recrut Component 1: Institutional D ement d'une firme pour la pr evelopment, Human Resour IDA / V0870 Post Direct Selection Direct 40,000.00 0.00 Canceled 2018-07-20 2018-07-30 2018-10-03 2019-04-01 éparation des étudiants cand ces and Organizational Struc idats aux concours statistiqu ture e (CASP) PSTAT-010-C-ED-17 / Recrut er un consultant individuel p our appuyer le CASP dans la Component 1: Institutional D préparation des candidats au evelopment, Human Resour x concours et pour la revue d IDA / V0870 Post Direct Selection Direct 70,000.00 20,068.56 Completed 2018-01-30 2017-10-25 2018-02-09 2017-12-08 2018-04-15 2018-01-23 2018-10-12 2018-03-30 ces and Organizational Struc u programme de formation st ture atistique et développement d e programmes d'études appr opriés du CASP ( Consultant GRUN REHOMME) PSTAT-035-C-ED-17 / Recrut ement de GRUN REHOMME f Component 1: Institutional D ormateur (CAPESA) pour app evelopment, Human Resour uyer l'INS et le CASP dans la IDA / V0870 Prior Direct Selection Direct 26,500.00 0.00 Canceled 2017-12-13 2017-12-23 2018-02-26 2018-08-25 ces and Organizational Struc sensibilisation, le recrutemen ture t et la préparation des candid ats aux concours d'entrée da ns les écoles africaines de st atistique PSTAT-032-C-C-17 / Appui te Component 2: Data producti chnique à la réalisation de l'E IDA / V0870 on, Dissemination and the u Post Direct Selection Direct 24,000.00 24,000.00 Completed 2017-09-03 2017-10-22 2017-11-21 2017-11-21 2018-01-31 2018-04-13 nquête Démographique et de se of Statistics Santé (SIDA, Paludisme) ICF MACRO International PSTAT-036-C-ED-17 / Recrut ement de Olga Vasyechko for Component 1: Institutional D matrice (CAPESA) pour appu evelopment, Human Resour yer l'INS et le CASP dans la s IDA / V0870 Post Direct Selection Direct 8,449.00 8,553.90 Completed 2017-12-13 2017-12-13 2017-12-23 2017-12-08 2018-02-26 2018-01-18 2018-08-25 2018-03-22 ces and Organizational Struc ensibilisation, le recrutement ture et la préparation des candida ts aux concours d'entrée dan s les écoles africaines de stat istique Page 6 PSTAT-037-C-ED-17 / Recrut ement de Jeannot Ngban for Component 1: Institutional D mateur (ISSEA) pour appuyer evelopment, Human Resour l'INS et le CASP dans la sensi IDA / V0870 Prior Direct Selection Direct 13,591.00 0.00 Canceled 2017-12-13 2017-12-23 2018-02-26 2018-08-25 ces and Organizational Struc bilisation, le recrutement et l ture a préparation des candidats aux concours d'entrée dans l es écoles africaines de statist ique PSTAT-038-C-ED-17 / Recrut ement de Justin Tchangam f Component 1: Institutional D ormateur (ISSEA) pour appuy evelopment, Human Resour er l'INS et le CASP dans la se IDA / V0870 Prior Direct Selection Direct 11,020.00 0.00 Canceled 2017-12-13 2017-12-23 2018-02-26 2018-08-25 ces and Organizational Struc nsibilisation, le recrutement ture et la préparation des candida ts aux concours d'entrée dan s les écoles africaines de stat istique PSTAT-06-C-ED-18 / Contrat Component 1: Institutional D de fidélisation des statisticie IDA / V0870 evelopment, Human Resour Post Direct Selection Direct 7,200.00 0.00 Canceled 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2019-02-10 n: ONKA MOUANDA Vivien ces and Organizational Struc ture PSTAT-07-C-ED-18 / Fidélisat Component 1: Institutional D ion des ingénieurs statisticie evelopment, Human Resour IDA / V0870 Post Direct Selection Direct 7,200.00 6,378.62 Completed 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 2018-07-26 ns et démographes: OSSOU ces and Organizational Struc NA Dukken Gaphi ture PSTAT-08-C-ED-18 / Fidélisat Component 1: Institutional D ion et motivation des ingéni IDA / V0870 evelopment, Human Resour Post Direct Selection Direct 7,200.00 4,278.22 Terminated 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 eurs statisticiens : MITOUMO ces and Organizational Struc UENI Antoine ture PSTAT-09-C-ED-18 / Fidélisat Component 1: Institutional D ion et motivation des ingéni IDA / V0870 evelopment, Human Resour Post Direct Selection Direct 7,200.00 4,252.42 Completed 2018-05-31 2018-06-11 2018-06-10 2018-08-14 2018-07-03 2019-02-10 2019-07-02 eurs statisticiens: OKANIANG ces and Organizational Struc A Murphy ture PSTAT-10-C-ED-18 / Fidélisat Component 1: Institutional D ion et motivation des ingéni evelopment, Human Resour IDA / V0870 Post Direct Selection Direct 7,200.00 4,252.42 Completed 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 2019-07-02 eurs statisticiens et démogr ces and Organizational Struc aphes: GASSAI OSSEBI ture PSTAT-11-C-ED-18 / Fidélisat Component 1: Institutional D ion et motivation des ingéni evelopment, Human Resour IDA / V0870 Post Direct Selection Direct 7,200.00 6,378.62 Completed 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 2019-07-02 eurs statisticiens et démogr ces and Organizational Struc aphes: BALOSSA Chriss Sivan ture anda PSTAT-12-C-ED-18 / Fidélisat Component 1: Institutional D ion et motivation des ingéni evelopment, Human Resour IDA / V0870 Post Direct Selection Direct 7,200.00 4,278.22 Completed 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 2019-07-02 eurs statisticiens et démogr ces and Organizational Struc aphes_ MOKOMPONI Morlond ture PSTAT-13-C-ED-18 / Fidélisat Component 1: Institutional D ion et motivation des ingéni evelopment, Human Resour IDA / V0870 Post Direct Selection Direct 7,200.00 6,417.32 Completed 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 2019-07-02 eurs statisticiens et démogr ces and Organizational Struc aphes_ IPANDZA LONDA NGA ture NGA Chriss Nawa PSTAT-15-C-ED-18 / Fidélisat Component 1: Institutional D ion et motivation des ingéni evelopment, Human Resour eurs statisticiens et démogr IDA / V0870 Post Direct Selection Direct 7,200.00 6,378.62 Completed 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 2019-07-02 ces and Organizational Struc aphes_ KAMBO GUERE KOMO ture NZO Claude Christian PSTAT-16-C-ED-18 / Fidélisat Component 1: Institutional D ion et motivation des ingéni evelopment, Human Resour IDA / V0870 Post Direct Selection Direct 7,200.00 4,252.42 Terminated 2018-05-31 2018-06-29 2018-06-10 2018-08-14 2018-07-03 2019-02-10 eurs statisticiens et démogr ces and Organizational Struc aphes_ MALONGA Philitchev ture Audrokiev PSTAT-21-C-CI-18 / Recrute Component 1: Institutional D Individual Consult ment d'un Ingénieur en Bâti IDA / V0870 evelopment, Human Resour Post Open 48,000.00 47,305.53 Completed 2018-05-31 2018-04-23 2018-07-19 2018-10-29 2018-08-09 2019-06-25 2018-09-13 2019-07-08 2019-03-12 2020-12-31 ant Selection ment national ces and Organizational Struc ture PSTAT-22-C-CI-18 / Recrute Component 1: Institutional D Individual Consult ment d'un Spécialiste en dév IDA / V0870 evelopment, Human Resour Post Open 93,000.00 42,696.50 Completed 2018-05-31 2018-04-23 2018-07-19 2018-09-19 2018-08-09 2019-06-04 2018-09-13 2019-07-08 2019-03-12 2020-12-31 ant Selection eloppement social ces and Organizational Struc ture PSTAT-23-C-CI-18 / Recrute Component 1: Institutional D Individual Consult ment d'un Spécialiste en envi IDA / V0870 evelopment, Human Resour Post Open 93,000.00 85,157.51 Completed 2018-05-31 2018-04-23 2018-07-19 2018-09-19 2018-08-09 2019-06-25 2018-09-13 2019-07-08 2019-03-12 2020-12-31 ant Selection ronnement ces and Organizational Struc ture PSTAT-25-C-CI-18 / Recrute ment d'une équipe de deux c Component 2: Data producti onsultants individuels pour la Individual Consult IDA / V0870 on, Dissemination and the u Post Limited 50,000.00 32,937.00 Completed 2018-06-18 2018-05-07 2018-06-23 2018-07-06 2018-07-14 2018-08-21 2018-08-18 2018-08-22 2019-02-14 2019-03-20 revue à mi-parcours du proje ant Selection se of Statistics t de renforcement des capaci tés en statistiques_ Chef de mission PSTAT-26-C-CI-18 / Recrute ment d'un Spécialiste en acc Component 2: Data producti Individual Consult ompagnement des systèmes IDA / V0870 on, Dissemination and the u Post Limited 25,000.00 29,337.00 Completed 2018-06-18 2018-05-07 2018-06-23 2018-07-06 2018-07-14 2018-08-21 2018-08-18 2018-08-22 2019-02-14 2019-03-20 ant Selection statistiques nationaux pour l se of Statistics a revue à mi-parcours PSTAT-27-C-CI-18 / Recrute Component 2: Data producti Individual Consult ment d'un consultant individ IDA / V0870 on, Dissemination and the u Post Open 25,000.00 0.00 Canceled 2018-05-31 2018-05-22 2018-07-19 2018-08-09 2018-09-13 2019-03-12 ant Selection uel international de la gestio se of Statistics n des plaintes PSTAT-02-C-ED-18 / Renouv Component 3: Project Manag ellement du contrat du spéci IDA / V0870 Post Direct Selection Direct 50,000.00 11,517.46 Completed 2018-05-31 2018-06-12 2018-06-10 2018-08-14 2018-07-02 2019-02-10 2018-10-01 ement aliste en communication du P STAT PSTAT-28-C-CI-18 / Renouvel Component 2: Data producti Individual Consult lement du contrat du Conseill IDA / V0870 on, Dissemination and the u Post Direct 66,000.00 58,922.48 Completed 2018-05-31 2018-06-13 2018-06-10 2018-06-25 2018-07-01 2018-06-25 2018-08-05 2018-07-02 2019-02-01 2018-12-31 ant Selection er Technique permanent du se of Statistics RGPH PSTAT-031-CI-DIR-18 / Cons Component 2: Data producti ultant individuel international Individual Consult IDA / V0870 on, Dissemination and the u Post Direct 40,000.00 32,380.00 Completed 2018-07-30 2018-06-12 2018-08-09 2018-06-20 2018-08-30 2018-06-21 2018-10-04 2018-06-22 2019-04-02 2018-07-30 pour la mission d'assistance t ant Selection se of Statistics echnique n°2 du consultant s pécialiste CAPI PSTAT-035-SASC-DIR-18 / Re Component 1: Institutional D crutement d'un consultant in evelopment, Human Resour Individual Consult IDA / V0870 Post Open 15,000.00 0.00 Canceled 2018-08-20 2018-10-08 2018-10-29 2018-12-03 2019-06-01 dividuel pour la mise en plac ces and Organizational Struc ant Selection e du site web de l'Institut Na ture tional Page 7 PSTAT-036-CI-DIR-18 / Reno uvellement du contrat de l'As Component 3: Project Manag IBRD / 88510 Post Direct Selection Direct 30,000.00 27,768.08 Completed 2018-08-31 2018-08-30 2018-09-10 2018-11-14 2018-08-31 2019-05-13 2020-12-31 sistante de Direction de l'Unit ement é de Coordination du PSTAT PSTAT-037-C-CI-18 / Recrute Component 3: Project Manag Individual Consult ment d'un Assistant en Passa IBRD / 88510 Post Open 28,800.00 0.00 Canceled 2018-08-31 2018-09-19 2018-10-19 2018-11-09 2018-12-14 2019-06-12 ement ant Selection tion des marchés au sein de l 'UCP PSTAT PSTAT-038-CI-DIR-18 / Reno Component 3: Project Manag IBRD / 88510 Post Direct Selection Direct 109,206.00 100,765.31 Completed 2018-10-29 2018-09-18 2018-11-08 2018-10-24 2019-01-12 2018-10-29 2019-07-11 2020-12-31 uvellement du contrat du RA ement FC du PSTAT PSTAT-039-CI-DIR-18 / Reno Component 3: Project Manag IBRD / 88510 Prior Direct Selection Direct 205,000.00 0.00 Canceled 2018-10-29 2018-09-28 2018-11-08 2018-12-26 2019-01-12 2019-07-11 uvellement du contrat du SS ement E du PSTAT PSTAT-040-CI-DIR-18 / Reno Component 3: Project Manag IBRD / 88510 Prior Direct Selection Direct 205,000.00 0.00 Canceled 2018-10-29 2018-09-28 2018-11-08 2018-12-26 2019-01-12 2019-07-11 uvellement du contrat du SP ement M du PSTAT PSTAT-041-CI-DIR-18 / Reno Component 3: Project Manag uvellement du contrat du Co IBRD / 88510 Post Direct Selection Direct 144,000.00 0.00 Canceled 2019-04-29 2019-05-09 2019-07-13 2020-01-09 ement ordonnateur du PSTAT PSTAT-042-CI-DIR-18 / Reno Component 3: Project Manag uvellement du contrat du Co IBRD / 88510 Post Direct Selection Direct 76,800.00 62,229.71 Completed 2019-04-30 2019-03-08 2019-05-10 2019-07-14 2019-05-10 2020-01-10 2020-12-31 ement mptable du PSTAT PSTAT-043-CI-C-18 / Recrute Component 1: Institutional D Individual Consult ment d'un responsable de la IBRD / 88510 evelopment, Human Resour Post Open 43,200.00 0.00 Canceled 2018-11-29 2018-09-19 2019-01-17 2019-02-07 2019-03-14 2019-09-10 ant Selection composante 1 ces and Organizational Struc ture PSTAT-044-CI-C-18 / Renouv Component 3: Project Manag ellement du contrat de l'Assis IBRD / 88510 Post Direct Selection Direct 41,856.00 34,678.43 Completed 2019-03-29 2019-03-08 2019-04-08 2019-06-12 2019-04-23 2019-12-09 2020-12-31 ement tant Administratif du PSTAT PSTAT-045-CI-C-18 / Renouv Component 3: Project Manag IBRD / 88510 Post Direct Selection Direct 41,856.00 36,597.96 Completed 2019-03-29 2019-03-14 2019-04-08 2019-06-12 2019-04-23 2019-12-09 2020-12-31 ellement du contrat du trésor ement ier PSTAT-046-CI-DIR-18 / Reno Component 3: Project Manag IBRD / 88510 Post Direct Selection Direct 11,008.00 0.00 Canceled 2019-02-28 2019-03-08 2019-03-10 2019-03-14 2019-05-14 2019-11-10 uvellement du contrat du Pla ement nton PSTAT-047-CI-DIR-18 / Reno Component 2: Data producti uvellement du contrat du Sta IBRD / 88510 on, Dissemination and the u Post Direct Selection Direct 94,176.00 83,340.84 Completed 2019-03-29 2019-04-02 2019-04-08 2019-04-25 2019-06-12 2019-04-29 2019-12-09 2021-01-01 tisticien d'appui _ Responsabl se of Statistics e de la composante 2 PSTAT-048-C-DIR-18 / Contr Component 1: Institutional D a IFORD _Ecole pour la forma evelopment, Human Resour IDA / V1720 Post Direct Selection Direct 42,000.00 146,367.50 Completed 2018-12-24 2018-10-17 2019-01-03 2019-03-09 2018-11-19 2019-09-05 2020-11-18 tion des Démographes pour l ces and Organizational Struc e Congo Brazzaville ture PSTAT-049-C-DIR-18 / Contr Component 1: Institutional D at avec ENSAE (Dakar) pour l evelopment, Human Resour IDA / V1720 Post Direct Selection Direct 25,000.00 37,245.83 Completed 2018-12-24 2018-10-08 2019-01-03 2019-03-09 2018-11-19 2019-09-05 2020-10-10 a formation des ingénieurs d ces and Organizational Struc es travaux statistiques pour l ture e Congo Brazzaville PSTAT-050-C-DIR-18 / Contr Component 1: Institutional D at avec ISSEA (Cameroun) po evelopment, Human Resour IDA / V1720 Post Direct Selection Direct 102,000.00 0.00 Canceled 2018-12-24 2018-10-08 2019-01-03 2019-03-09 2019-09-05 ur la formation des ingénieur ces and Organizational Struc s des travaux statistiques po ture ur le Congo Brazzaville PSTAT-051-C-DIR-18 / Contr Component 1: Institutional D at avec ENSEA (Abidjan) pour evelopment, Human Resour IDA / V1720 Post Direct Selection Direct 11,000.00 75,344.30 Completed 2018-12-24 2018-10-17 2019-01-03 2019-03-09 2018-11-19 2019-09-05 2020-11-25 la formation des ingénieurs d ces and Organizational Struc es travaux statistiques pour l ture e Congo Brazzaville PSTAT-052-CI-18 / Recrutem Component 1: Institutional D ent d'un consultant pour l'éla evelopment, Human Resour Individual Consult IDA / V1720 Post Open 30,000.00 0.00 Canceled 2018-12-24 2018-10-31 2019-02-11 2019-03-04 2019-04-08 2019-10-05 boration du PGES ( plan de g ces and Organizational Struc ant Selection estion environnemental et so ture cial PSTAT-053-CI-DIR-18 / Reno Component 3: Project Manag uvellement du contrat du Sp IBRD / 88510 Post Direct Selection Direct 113,510.00 22,621.76 Completed 2018-12-24 2018-09-18 2019-01-03 2018-12-27 2019-03-09 2018-12-27 2019-09-05 2019-03-01 ement écialiste en Communication d u PSTAT PSTAT-054-CI-DIR-18 / Reno Component 1: Institutional D uvellement du contrat du cha evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 14,400.00 0.00 Canceled 2019-04-30 2019-05-10 2019-07-14 2020-01-10 uffeur de la Direction Généra ces and Organizational Struc le de l'INS_ M'BOYAS ture PSTAT-055-CI-DIR-18 / Recru Component 3: Project Manag Individual Consult tement d'un consultant pour IDA / V1720 Post Open 20,000.00 0.00 Canceled 2019-03-26 2019-02-26 2019-05-14 2019-06-04 2019-07-09 2020-01-05 ement ant Selection l'élaboration du manuel d'ex écution du PSTAT PSTAT-059-CI-18 / Recrutem Component 1: Institutional D Individual Consult ent d'un assistant et adminis IBRD / 88510 evelopment, Human Resour Post Open 12,000.00 0.00 Canceled 2019-02-26 2019-04-16 2019-05-07 2019-06-11 2019-12-08 ant Selection tratif et logistique pour appu ces and Organizational Struc yer l'INS ture PSTAT-005-C-CI-19 / Recrute Component 2: Data producti Individual Consult ment d'un consultant individ IBRD / 88510 on, Dissemination and the u Post Open 50,000.00 37,849.72 Completed 2019-06-30 2019-08-31 2019-08-18 2019-12-03 2019-09-08 2019-12-07 2019-10-13 2019-12-18 2020-04-10 2020-11-25 ant Selection uel chargé de la mise en plac se of Statistics e du FBR PSTAT-007-C-ED-19 / Renou Component 3: Project Manag vèlement du contrat du chau IBRD / 88510 Post Direct Selection Direct 16,176.00 13,050.81 Completed 2019-07-31 2019-05-07 2019-08-10 2019-06-06 2019-10-14 2019-06-12 2020-04-11 2020-12-31 ement ffeur_ MIANTAMA PSTAT-006-CI-ED-19 / Renou Component 3: Project Manag vèlement du contrat du chau IBRD / 88510 Post Direct Selection Direct 16,176.00 13,050.81 Completed 2019-07-31 2019-05-07 2019-08-10 2019-10-14 2019-06-12 2020-04-11 2020-12-31 ement ffeur_DZALAMOU PSTAT-008-CI-ED-19 / Renou Component 3: Project Manag vèlement du contrat du chau IBRD / 88510 Post Direct Selection Direct 16,617.00 13,050.81 Completed 2019-07-31 2019-05-07 2019-08-10 2019-10-14 2019-06-12 2020-04-11 2020-12-31 ement ffeur_ BATHEAS PSTAT-009-CI-ED-19 / renou Component 3: Project Manag vèlement du contrat de Mons IBRD / 88510 Post Direct Selection Direct 8,089.00 6,180.23 Completed 2019-04-30 2019-05-07 2019-05-10 2019-05-09 2019-07-14 2019-05-10 2020-01-10 2020-05-30 ement ieur YOMES M'NOYAS chaffe ur affecté à l'INS Page 8 PSTAT-012- C-CI-19 / Régula Component 2: Data producti risation _recrutement Consul Individual Consult IBRD / 88510 on, Dissemination and the u Post Open 40,000.00 36,417.65 Completed 2016-01-10 2016-02-28 2016-03-20 2016-03-15 2016-04-24 2016-03-30 2016-10-21 2016-09-30 tants individuel charge de l'él ant Selection se of Statistics aboration des documents tec hniques du (REGEC) PSTAT-013-C- DIR- 19 / Régu Component 3: Project Manag larisation _renouvèlement du IDA / V0870 Post Direct Selection Direct 51,000.00 70,973.75 Completed 2018-12-30 2019-01-09 2019-03-15 2018-12-27 2019-09-11 2019-05-31 ement contrat du SPM. PSTAT-014-C- DIR -19 / Régu Component 3: Project Manag larisation _renouvèlement du IDA / V0870 Post Direct Selection Direct 51,000.00 44,831.02 Completed 2018-12-30 2019-01-09 2019-03-15 2018-12-27 2019-09-11 2019-05-30 ement contrat du SSE. PSTAT-015-CI-ED-19 / Fidélis Component 1: Institutional D ation et motivation des ingén evelopment, Human Resour Under Implement IBRD / 88510 Post Direct Selection Direct 7,200.00 0.00 2019-06-28 2019-04-04 2019-07-08 2019-04-25 2019-09-11 2020-03-09 ieurs statisticiens et démogr ces and Organizational Struc ation aphes _ IBARA Ngokaba (ISE) ture PSTAT-011-DIR-C-19 / Assist Component 2: Data producti ance et contrôle techniques IBRD / 88510 on, Dissemination and the u Post Direct Selection Direct 367,600.00 327,600.00 Completed 2016-04-29 2016-05-09 2016-07-13 2016-04-29 2017-01-09 2018-12-31 du Recensement Général de l se of Statistics a Population et de l'Habitatio n du Congo PSTAT-001-C-CI-19 / Recrute Component 3: Project Manag Individual Consult ment du spécialiste en passa IBRD / 88510 Prior Open 210,000.00 41,727.97 Completed 2019-07-30 2019-05-15 2019-09-17 2019-10-02 2019-10-08 2020-09-01 2019-11-12 2019-09-28 2020-05-10 2020-01-01 ement ant Selection tion des marchés de l'UCP PS TAT PSTAT-002-C-CI-19 / Recrute Component 3: Project Manag Individual Consult ment du spécialiste en Suivi- IBRD / 88510 Prior Open 210,000.00 70,646.05 Signed 2019-07-31 2019-05-15 2019-09-18 2019-10-02 2019-10-09 2020-09-01 2019-11-13 2019-09-28 2020-05-11 ement ant Selection Evaluation de l'UCP PSTAT PSTAT-003-C-CI-19 / Recrute Component 3: Project Manag Individual Consult ment du Spécialiste en Com IBRD / 88510 Prior Open 210,000.00 41,727.97 Completed 2019-07-31 2019-05-15 2019-09-18 2019-10-02 2019-10-09 2020-09-01 2019-11-13 2019-09-04 2020-05-11 2020-10-03 ement ant Selection munication de l'UCP PSTAT PSTAT-004-C-CI-19 / Recrute Component 3: Project Manag Individual Consult IBRD / 88510 Prior Open 210,000.00 50,461.73 Completed 2019-07-31 2019-05-15 2019-09-18 2019-10-02 2019-10-09 2020-09-01 2019-11-13 2019-09-03 2020-05-11 2021-01-01 ment du Coordonnateur de l' ement ant Selection UCP PSTAT PSTAT-016-C-CI-19 / Spéciali Component 1: Institutional D ste en évaluation institutionn evelopment, Human Resour Individual Consult IBRD / 88510 Post Open 50,000.00 0.00 Canceled 2019-07-31 2019-05-24 2019-09-18 2019-10-09 2019-11-13 2020-05-11 elle, organisationnelle et fonc ces and Organizational Struc ant Selection tionnelle - Reforme CASP ture PSTAT-017-C-CI-19 / Spéciali Component 1: Institutional D Individual Consult ste en Réformes des progra IBRD / 88510 evelopment, Human Resour Post Open 50,000.00 83,815.59 Completed 2019-07-31 2019-05-24 2019-09-18 2019-12-03 2019-10-09 2020-02-11 2019-11-13 2020-02-18 2020-05-11 2020-07-31 ant Selection mmes de formation_ Reform ces and Organizational Struc e CASP ture PSTAT-023-CI-ED-19 / Renou Component 3: Project Manag vèlement du contrat de la tré IBRD / 88510 Post Direct Selection Direct 30,545.00 0.00 Canceled 2019-08-30 2019-08-30 2019-09-09 2019-11-13 2020-05-11 ement sorière de l'UCP PSTAT-025-C-CI-19 / Consult Component 1: Institutional D Individual Consult ant élaboration NIES( notice IBRD / 88510 evelopment, Human Resour Post Open 30,000.00 35,590.80 Completed 2019-10-10 2019-10-24 2019-11-28 2019-09-24 2019-12-19 2019-09-25 2020-01-23 2019-09-26 2020-07-21 2020-08-02 ant Selection d'impact environnemental et ces and Organizational Struc social) ture Component 1: Institutional D PSTAT-027-C-CI-19 / Elabora Individual Consult IBRD / 88510 evelopment, Human Resour Post Open 50,000.00 24,184.88 Completed 2019-10-08 2019-10-07 2019-11-26 2019-12-03 2019-12-17 2019-12-12 2020-01-21 2019-12-16 2020-07-19 2020-03-11 tion plan de formation INS ant Selection ces and Organizational Struc ture PSTAT-028-C-END- CABINET Component 1: Institutional D LA BOUSSOLE-19 / Cabinet ét evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 50,000.00 37,930.80 Completed 2019-10-30 2019-10-14 2019-11-09 2019-10-25 2020-01-13 2019-11-07 2020-07-11 2019-12-18 udes topographiques travau ces and Organizational Struc x complexe INS-CASP ture PSTAT-029-C-ED-BCBTP-19 / Component 1: Institutional D Laboratoire études géotechni IBRD / 88510 evelopment, Human Resour Post Direct Selection Direct 100,000.00 65,909.49 Completed 2019-10-30 2019-10-14 2019-11-09 2019-10-25 2020-01-13 2019-11-06 2020-07-11 2020-01-10 ques site complexe CASP-INS ces and Organizational Struc ture PSTAT -026-C-CI-19 / Consult Component 1: Institutional D Individual Consult ant PSR ( plan succinct de réi IBRD / 88510 evelopment, Human Resour Post Open 30,000.00 0.00 Canceled 2019-10-09 2019-11-27 2019-12-18 2020-01-22 2020-07-20 ant Selection nstallation) ces and Organizational Struc ture PSTAT-033-C-ED-MBEP FOME Component 2: Data producti KONG -19 / Renouvellement IBRD / 88510 on, Dissemination and the u Post Direct Selection Direct 40,000.00 0.00 Canceled 2019-12-13 2019-11-19 2019-12-23 2020-02-26 2020-08-24 contrat consultant du systè se of Statistics me d'interview assisté par or dinateur ( CAPI) PSTAT-032-C-ED-JANVIER ME Component 2: Data producti TAGNO-19 / Renouvellement IBRD / 88510 on, Dissemination and the u Post Direct Selection Direct 40,000.00 37,738.47 Completed 2019-12-13 2019-11-20 2019-12-23 2019-12-30 2020-02-26 2020-09-04 2020-08-24 2020-12-01 contrat expert en statistique se of Statistics d'entreprise PSTAT-031- C-ED- UNFA-19 / Component 2: Data producti Assistance et contrôle techni IBRD / 88510 on, Dissemination and the u Post Direct Selection Direct 380,000.00 375,578.00 Signed 2019-12-05 2019-11-26 2019-12-15 2019-12-02 2020-02-18 2019-12-03 2020-08-16 que du RGPH du Congo se of Statistics PSTAT-035C-CI-19 / Analyse Component 2: Data producti approfondies des données de Individual Consult IBRD / 88510 on, Dissemination and the u Post Open 7,000.00 0.00 Canceled 2020-01-15 2020-03-04 2020-03-25 2020-04-29 2020-10-26 l' enquête par grappes à indi ant Selection se of Statistics cateurs multiples (MICS) 201 5 PSTAT-044-C-CI-20 / Recrut Component 1: Institutional D Individual Consult consultant enquête des mén IBRD / 88510 evelopment, Human Resour Post Open 25,000.00 0.00 Canceled 2020-05-08 2020-06-26 2020-07-17 2020-08-21 2021-02-17 ant Selection ages ces and Organizational Struc ture PSTAT-046-C-CI-20 / Consult Component 1: Institutional D Individual Consult ant etude diagnostique stat s IBRD / 88510 evelopment, Human Resour Post Open 40,000.00 47,781.62 Completed 2020-06-10 2020-05-13 2020-07-29 2020-09-25 2020-08-19 2020-09-29 2020-09-23 2020-10-06 2021-03-22 2021-03-13 ant Selection ectorielles ( forêt, mines ,gaz ces and Organizational Struc et pétrole) ture PSTAT-049-C-CI-20 / assistan Component 3: Project Manag Individual Consult IBRD / 88510 Post Open 21,000.00 0.00 Canceled 2020-04-24 2020-06-12 2020-07-03 2020-08-07 2021-02-03 t chargé de la logistique ement ant Selection PSTAT-048-C-ED-YAMEOGO Component 1: Institutional D EOUAYA -20 / Consultant en IBRD / 88510 evelopment, Human Resour Post Direct Selection Direct 25,000.00 28,263.72 Completed 2020-04-15 2020-03-01 2020-04-25 2020-03-05 2020-06-29 2020-03-10 2020-12-26 2020-12-31 quête unités non standards ces and Organizational Struc ture PSTAT-054-C-CI-20 / Consult Component 3: Project Manag Individual Consult ant national pour évaluation IBRD / 88510 Post Open 20,000.00 0.00 Canceled 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 ement ant Selection finale du PSTAT Page 9 PSTAT-050-C-CI-20 / consult Component 3: Project Manag Individual Consult ant international pour evalu IBRD / 88510 Post Open 35,000.00 0.00 Canceled 2020-09-15 2020-11-03 2020-11-24 2020-12-29 2021-06-27 ement ant Selection ation final du projet PSTAT-055-C-CI-20 / Recrute Component 1: Institutional D Individual Consult ment cslt formation cadre sta IBRD / 88510 evelopment, Human Resour Post Open 15,000.00 10,275.00 Completed 2020-05-08 2020-06-24 2020-06-26 2020-09-25 2020-07-17 2020-09-29 2020-08-21 2020-10-10 2021-02-17 2020-11-01 ant Selection t commerce extérieur ces and Organizational Struc ture PSTAT-056-C-END-EWEK ASS Component 1: Institutional D OUNGA-20 / Fidélisation et m evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 10,000.00 6,045.23 Completed 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-03-14 2020-11-30 2021-01-01 otivation des ingénieurs stati ces and Organizational Struc sticiens et démographes/ EW ture EK ASSOUNGA PSTAT-057-C-END-GANGA A NGELUS-20 / Fidélisation et Component 1: Institutional D motivation des ingénieurs st evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 10,000.00 6,127.81 Completed 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-03-14 2020-11-30 2021-01-01 atisticiens et démographes d ces and Organizational Struc e haut niveau non employés ture aux projets pour l'appui aux projets de l'INS PSTAT-058-C-END-GONBA O NDOUMA-20 / Fidélisation et Component 1: Institutional D motivation des ingénieurs st evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 10,000.00 4,082.83 Completed 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-03-14 2020-11-30 2021-01-01 atisticiens et démographes d ces and Organizational Struc e haut niveau non employés ture aux projets pour l'appui aux projets de l'INS PSTAT-059-C-END-IBARA TSI BA-20 / Fidélisation et motiva Component 1: Institutional D tion des ingénieurs statisticie evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 10,000.00 4,085.21 Completed 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-01-03 2020-11-30 2021-01-01 ns et démographes de haut n ces and Organizational Struc iveau non employés aux proj ture ets pour l'appui aux projets d e l'INS PSTAT-060-C-END-MBOUKO U PIERRICK-20 / Fidélisation e Component 1: Institutional D t motivation des ingénieurs s evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 10,000.00 4,085.21 Completed 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-01-03 2020-11-30 2021-01-01 tatisticiens et démographes ces and Organizational Struc de haut niveau non employé ture s aux projets pour l'appui au x projets de l'INS PSTAT-061-C-END-SITA BAN ZOUZI-20 / Fidélisation et mo Component 1: Institutional D tivation des ingénieurs statis evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 10,000.00 6,127.81 Completed 2020-03-20 2020-03-02 2020-03-30 2020-03-12 2020-06-03 2020-03-14 2020-11-30 2021-01-01 ticiens et démographes de h ces and Organizational Struc aut niveau non employés au ture x projets pour l'appui aux pro jets de l'INS PSTAT-062-C-CI-20 / Consult Component 1: Institutional D Individual Consult ant formation personnel en c IBRD / 88510 evelopment, Human Resour Post Open 17,000.00 0.00 Canceled 2020-05-14 2020-07-02 2020-07-23 2020-08-27 2021-02-23 ant Selection harge des comptes nationau ces and Organizational Struc x ture PSTAT-064-C-CI-20 / Consult Component 1: Institutional D Individual Consult ant statistique du secteur rur IBRD / 88510 evelopment, Human Resour Post Open 10,000.00 14,550.00 Terminated 2020-09-15 2020-08-04 2020-11-03 2019-11-16 2020-11-24 2020-09-29 2020-12-29 2020-10-10 2021-06-27 ant Selection al et environnement / Elabor ces and Organizational Struc ation SNDS II ture PSTAT-065-C-CI-20 / Consult Component 1: Institutional D ant statistiques du devlpt ins evelopment, Human Resour Individual Consult IBRD / 88510 Post Open 10,000.00 11,890.57 Signed 2020-09-15 2020-08-04 2020-11-03 2020-11-16 2020-11-24 2020-11-18 2020-12-29 2020-11-20 2021-06-27 titutionnel ressources humai ces and Organizational Struc ant Selection nes et finances/ Elaboration ture SNDS II PSTAT-066-C-ED- BOUNKAZI Component 3: Project Manag JEAN HONORE- 20 / Recrute IBRD / 88510 Post Direct Selection Direct 5,000.00 11,428.64 Terminated 2020-08-20 2020-08-04 2020-08-30 2020-08-21 2020-11-03 2020-08-26 2021-05-02 ement ment d'un chauffeur PSTAT-79-C- FRANÇOIS RAM DE -ED-20 / recrutement Con Component 2: Data producti sultant formation au système IBRD / 88510 on, Dissemination and the u Post Direct Selection Direct 50,000.00 20,260.77 Completed 2020-12-10 2020-12-28 2020-12-20 2020-10-22 2021-02-23 2021-01-05 2021-08-22 2021-02-11 de comptabilité nationale de se of Statistics s nations unies version 2008 (SCN 2008) PSTAT-30-C-ED-INS-19 / Prot Component 2: Data producti ocole d'accord entre PSTAT -I IBRD / 88510 on, Dissemination and the u Prior Direct Selection Direct 750,000.00 0.00 Canceled 2019-12-12 2019-11-21 2019-12-22 2019-11-14 2020-02-25 2020-08-23 NS pour le recrutement des e se of Statistics nquêteurs. PSTAT-081-C-CI-20 / Recrute Component 2: Data producti ment consultant formation d Individual Consult IBRD / 88510 on, Dissemination and the u Post Open 20,000.00 7,835.42 Signed 2020-12-10 2020-11-26 2021-01-28 2021-01-05 2021-02-18 2021-01-14 2021-03-25 2021-02-08 2021-09-21 es acteurs du SSN en planifi ant Selection se of Statistics cation stratégique PSTAT-082-C-CI-20 / Recrute Component 2: Data producti ment consultant pour l'élabor Individual Consult IBRD / 88510 on, Dissemination and the u Post Open 25,000.00 15,562.24 Signed 2020-12-10 2020-11-26 2021-01-28 2021-04-20 2021-02-18 2021-04-30 2021-03-25 2021-07-02 2021-09-21 ation d'une stratégie de finan ant Selection se of Statistics cement du plan d'action de l a SNDSII PSTAT-001-C-ED-LÉONARD N ABASSEMBA-21 / Consultant Component 2: Data producti pour développer l'application IBRD / 88510 on, Dissemination and the u Post Direct Selection Direct 10,000.00 7,070.28 Signed 2021-03-25 2021-03-09 2021-04-04 2021-03-29 2021-06-08 2021-03-02 2021-12-05 CAPI de l’enquête harmonisé se of Statistics e sur les conditions de vie de s ménages PSTAT-002-C-ED- EDAU SCP Component 1: Institutional D CONGO-INGEROP-21 / SUIVI evelopment, Human Resour IBRD / 88510 Post Direct Selection Direct 180,000.00 155,778.16 Signed 2021-07-26 2021-07-08 2021-08-05 2021-07-09 2021-10-09 2021-07-25 2022-04-07 ET SUPERVISION DES TRAVA ces and Organizational Struc UX DE CONSTRUCTION DU C ture OMPLEXE INS & CASP PSTAT-004-C-EN-ENSEA ABI Component 2: Data producti DJAN / Formation des étudian IBRD / 88510 on, Dissemination and the u Post Direct Selection Direct 10,000.00 0.00 Canceled 2022-03-18 2022-02-10 2022-03-28 2022-06-01 2022-11-28 ts congolais à l'ENSEA d'Abid se of Statistics jan PSTAT-006-C-ED-ENSEA DAK Component 2: Data producti AR / Convention avec l'ENSE IBRD / 88510 on, Dissemination and the u Post Direct Selection Direct 7,000.00 0.00 Canceled 2022-03-25 2022-02-10 2022-04-04 2022-06-08 2022-12-05 A de Dakar pour la formation se of Statistics des étudiants congolais PSTAT-007-C-CI-EB-LEONAR D NABASSEMBA / Renouvelle Component 2: Data producti ment contrat Leonard NABAS IBRD / 88510 on, Dissemination and the u Post Direct Selection Direct 50,000.00 37,597.36 Signed 2022-03-25 2022-02-10 2022-04-04 2022-02-22 2022-06-08 2022-03-30 2022-12-05 SEMBA pour l'appui à l'enquê se of Statistics te EHCVM et RGPH-5 Page 10 PSTAT-011-C-ED-LEONARD N ABASSEMBA-22 / DEVELOPPE MENT ET TRAITEMENT DES Component 2: Data producti DONNEES DU PROGRAMME D IDA / 55000 on, Dissemination and the u Post Direct Selection Direct - National 75,000.00 0.00 Signed 2022-10-26 2022-08-24 2022-11-05 2022-08-23 2023-01-09 2023-07-08 E TRAITEMENT DES DONNEE se of Statistics S DU RGPH-5 ET DE L'ENQUE TE HARMONISEE SUR LES CO NDITIONS DE VIE DES MENA GES (EHCVM) PSTAT-010-C-UN-UNFPA-22 / APPUI TECHNIQUE ET ASSUR Component 2: Data producti ANCE QUALITE DU CINQUIEM Direct - Internation IDA / 55000 on, Dissemination and the u Post Direct Selection 499,768.00 499,768.00 Signed 2022-10-28 2022-08-24 2022-11-07 2022-07-19 2023-01-11 2022-09-10 2023-07-10 E RECENSEMENT GENERAL D al se of Statistics E LA POPULATION ET DE L’HA BITATION DU CONGO (RGPH- 5) PSTAT-028-C-CI-17 / Recrute Component 3: Project Manag Individual Consult ment d'un (e) Trésorière ou t IDA / V0870 Post Open 30,000.00 0.00 Canceled 2018-03-12 2018-03-22 2018-04-30 2018-05-21 2018-06-25 2018-12-22 ement ant Selection résorier au sein du PSTAT Component 1: Institutional D PSTAT-04-C-CI-23 / Régularis Individual Consult Under Implement IDA / 70540 evelopment, Human Resour Post Open - National 40,000.00 0.00 2023-02-15 2023-02-14 2023-04-05 2023-04-26 2023-05-31 2023-11-27 ation recrutement architecte ant Selection ation ces and Organizational Struc ture PSTAT-03-C-CI-ED-23 / Reno Component 1: Institutional D Direct - Internation Under Implement uvellement contrat Ingénieur IDA / 70540 evelopment, Human Resour Post Direct Selection 11,800.00 0.00 2023-02-25 2023-02-23 2023-03-07 2023-05-11 2023-11-07 al ation en bâtiment ces and Organizational Struc ture PSTAT-005-C- ED- MW DDB CONGO-23 / AGENCE DE CO Component 2: Data producti MMUNICATION AUDIO-VISUEL IDA / 70540 on, Dissemination and the u Post Direct Selection Direct - National 100,000.00 0.00 Completed 2023-03-10 2023-03-05 2023-03-20 2023-03-06 2023-05-24 2023-11-20 LE POUR LA CONCEPTION, LA se of Statistics DIFFUSION ET LE SUIVI DES OUTILS MULTIMÉDIAS DE SE NSIBILISATION DU RGPH-5 PSTAT-006- SC-ED- BAL SER VICES / AGENCE DE COMMUN Component 2: Data producti ICATION SPECIALISÉE DANS L IDA / 70540 on, Dissemination and the u Post Direct Selection Direct - National 50,000.00 0.00 Completed 2023-03-09 2023-03-05 2023-03-19 2023-03-15 2023-05-23 2023-11-19 ’EDITION ET L’IMPRESSION D se of Statistics ES OUTILS DE COMMUNICATI ONS ET DE SENSIBILISATION DU RGPH-5 PSTAT-018-C-CI-ED-FATOU A Component 2: Data producti MBROISE-23 / Consultant indi Under Implement IDA / 70540 on, Dissemination and the u Post Direct Selection Direct - National 50,000.00 0.00 2023-04-17 2023-04-21 2023-04-27 2023-07-01 2023-12-28 viduel élaboration des docum ation se of Statistics ents de sauvegarde nouveau projet statistique PSTAT-017-C-ED-HAROLD C OULOMBE-23 / Recrutement Component 2: Data producti Direct - Internation d'un consultant individuel po IDA / 70540 on, Dissemination and the u Post Direct Selection 100,000.00 0.00 Signed 2023-04-20 2023-04-21 2023-04-30 2023-04-24 2023-07-04 2023-12-31 al ur l'élaboration d'un profil de se of Statistics pauvreté pour le Congo. Page 11