The World Bank Implementation Status & Results Report Social Protection COVID-19 response and recovery (P178018) Social Protection COVID-19 response and recovery (P178018) EASTERN AND SOUTHERN AFRICA | Sao Tome and Principe | Social Protection & Jobs Global Practice | IBRD/IDA | Investment Project Financing | FY 2022 | Seq No: 3 | ARCHIVED on 29-Jun-2023 | ISR56949 | Implementing Agencies: Democratic Republic of Sao Tome and Principe, Ministry of Women's Rights Key Dates Key Project Dates Bank Approval Date: 02-May-2022 Effectiveness Date: 03-Jun-2022 Planned Mid Term Review Date: 25-Nov-2024 Actual Mid-Term Review Date: Original Closing Date: 30-Jun-2027 Revised Closing Date: 30-Jun-2027 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objectives of the project are to strengthen the social protection system and expand the coverage of social protection programs. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1. Institutional strengthening of the social protection sector:(Cost $4.60 M) Component 2. Social assistance programs:(Cost $12.50 M) Component 3. Project implementation support:(Cost $0.90 M) Component 4. Contingent Emergency Response Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The PDO remains relevant, and the project is on track to achieve its development objective. The COVID 19 emergency cash program (VFP-COVID- 19) ended successfully in 2022. Last payments occurred on November 18, 2022, to 15,325 beneficiaries of which 2,543 belonged to the vulnerable Family Program (VFP). The recertification and expansion of the VFP from 2500 to 4500 families is ongoing and is expected to be completed by end of July 2023. These figures will be revised as per the upcoming implementation support mission in September 2023. 6/29/2023 Page 1 of 6 The World Bank Implementation Status & Results Report Social Protection COVID-19 response and recovery (P178018) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Substantial Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Low Low Low Institutional Capacity for Implementation and Moderate Moderate Moderate Sustainability Fiduciary Substantial Substantial Substantial Environment and Social Moderate Moderate Moderate Stakeholders Low Low Low Other Moderate Low Moderate Overall Moderate Moderate Moderate Results PDO Indicators by Objectives / Outcomes Strengthening SP systems IN01313509 ►Beneficiaries of VFP regular program in the lowest 2 quintiles of the income distribution (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 90.00 90.00 90.00 95.00 Date 01-Apr-2022 07-Jun-2022 07-Jun-2022 30-Jun-2027 The indicator will be measured using a Proxy Means Test at the stage of recertification and transition Comments: between the emergency program to the regular social protection programs IN01313767 ►Increased knowledge of DPSSF staff in delivery systems (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 04-Mar-2022 07-Jun-2022 07-Jun-2022 30-Jun-2027 Successful rate of DPSSF staff that is able to pass a certain score in specific quiz on delivery systems Comments: after the trainings 6/29/2023 Page 2 of 6 The World Bank Implementation Status & Results Report Social Protection COVID-19 response and recovery (P178018) Expansion of the social protection coverage IN01313510 ►Beneficiaries of social safety net programs (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 15,325.00 15,325.00 15,325.00 16,000.00 Date 01-Apr-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 IN01313766 Beneficiaries of social safety net programs - Female (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 12,500.00 12,500.00 12,500.00 12,800.00 IN01313768 Beneficiaries of Safety Nets programs - Unconditional cash transfers (number) (Number, Corporate Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 15,325.00 15,325.00 15,325.00 16,000.00 Date 01-Apr-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 IN01313769 Beneficiaries of Safety Nets programs - Other cash transfers programs (number) (Number, Corporate Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 2,543.00 2,543.00 2,543.00 4,500.00 Date 01-Apr-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 Overall Comments PDO These figures will be revised as per the upcoming implementation support mission in September 2023. Intermediate Results Indicators by Components Component 1: Institutional strengthening of the social protection sector IN01313771 ►DPSSF staff trained in monitoring social protection programs (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15.00 Date 01-Apr-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 DPSSF staff that receive internal or external training on social protection during the timeframe of the Comments: Project 6/29/2023 Page 3 of 6 The World Bank Implementation Status & Results Report Social Protection COVID-19 response and recovery (P178018) IN01313773 ►Beneficiaries receiving cash transfers on time (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 100.00 100.00 100.00 100.00 Date 01-Apr-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 Percentage of beneficiaries receiving the cash transfers with the frequency stipulated in the Project Comments: operational manual IN01313774 ►Cash transfer payments completed by a payment service provider (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Yes Yes Yes Yes Date 01-Apr-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 Beneficiary payments that are made using an agent from a payment service provider and not by DPSSF Comments: staff IN01313775 ►Beneficiaries registered in the Social Registry (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 100.00 100.00 100.00 100.00 Date 01-Apr-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 Comments: Number of safety nets beneficiaries whose registration data are properly stored in the Social Registry IN01313776 ►Households in areas highly exposed to climate hazards pre-registered in the SIIPS (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2,500.00 Date 01-Apr-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 Number of households living in areas highly exposed areas to climate hazards that are pre-identified and Comments: register in the SIIPS IN01313777 ►Grievances digitally registered in the GRM and adapted to receive beneficiaries feedback (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 01-Apr-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 Grievances are feedback from citizens (beneficiaries and other stakeholders) registered via the Comments: digitalisation of the project’s Grievance Redress Mechanism (GRM) and related to the delivery of the project’s benefits IN01313778 6/29/2023 Page 4 of 6 The World Bank Implementation Status & Results Report Social Protection COVID-19 response and recovery (P178018) ►Capacity building plan developed for DPSSF staff (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 28-Feb-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 IN01313779 ►Customized GEMS system monitoring project conditionalities (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 04-Mar-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 Customized forms for digital data collection, developed based on the Geo-Enabling initiative for Monitoring Comments: and Supervision (GEMS) methodology, are integrated into the MIS and used to monitor project conditionalities Component 2: Social Safety Net Programs IN01313770 ►Beneficiaries of the VFP regular program participating in accompanying measures (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 88.00 88.00 50.00 Date 01-Apr-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 Percentage of the Vulnerable Families Program beneficiaries that attend sensitization sessions under the Comments: Parental Education Program IN01313772 ►Beneficiaries of the VFP regular program complying with school enrollment conditionality (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 80.00 80.00 60.00 Date 01-Apr-2022 30-Nov-2022 30-Nov-2022 30-Jun-2027 Comments: Percentage of the Vulnerable Families Program households with children are enrolled in school Overall Comments IR These figures will be revised as per the upcoming implementation support mission in September 2023. Performance-Based Conditions Data on Financial Performance 6/29/2023 Page 5 of 6 The World Bank Implementation Status & Results Report Social Protection COVID-19 response and recovery (P178018) Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P178018 IDA-E0150 Effective USD 18.00 18.00 0.00 5.72 11.73 33% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P178018 IDA-E0150 Effective 02-May-2022 20-May-2022 03-Jun-2022 30-Jun-2027 30-Jun-2027 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/29/2023 Page 6 of 6