PROCUREMENT PLAN Project information: Bosnia and Herzegovina – Energy Efficiency Project – P143580 Project Implementation agency: Federal Ministry of Physical Planning Date of the Procurement Plan: 4/30/2020 Period covered by this Procurement Plan: 2020-2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. If the Borrower and the Bank agreed to use the Borrower’s national open competitive procurement arrangements, it will be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. Other Relevant Procurement Information. None. PROCUREMENT Bosnia and Herzegovina : Energy Efficiency Project PLAN General Information Country: Bosnia and Herzegovina 2020-03-13 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P143580 GPN Date: 2020-03-19 Project Name: Energy Efficiency Project Loan / Credit No: IBRD / 89060, IDA / 55380, IDA / 53930 Federal Ministry of Physical Planning-Project Implementation Unit Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BEEPAF-P165405-RFB-04-W- Energy Efficiency Investmen Single Stage - One E Pending Imp 2023-10-1 23-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National 0.00 2023-04-01 2023-04-11 2023-05-09 2023-05-23 2023-06-17 ts in Public Facilities nvelope lementation 5 ction of (1+5) objects in 202 3 BEEPAF-P165405-RFB-03-W- Energy Efficiency Investmen Single Stage - One E 2022-10-1 22-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National 0.00 Signed 2022-04-01 2022-04-28 2022-04-11 2022-05-09 2022-05-30 2022-05-23 2022-06-17 2022-06-17 ts in Public Facilities nvelope 5 ction of 10 objects in 2022 BEEPAF-P165405-RFB-02-W- Energy Efficiency Investmen Single Stage - One E 2021-10-1 21-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National 573,284.47 Signed 2021-04-01 2021-05-28 2021-04-11 2021-05-28 2021-05-09 2021-06-28 2021-05-23 2021-06-30 2021-06-17 2021-07-27 ts in Public Facilities nvelope 5 ction of 13 objects in 2021 BEEPAF-P165405-RFB-05-W- Energy Efficiency Investmen Single Stage - One E 1,168,669.6 2021-10-1 21-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National Signed 2021-04-01 2021-05-31 2021-04-11 2021-05-31 2021-05-09 2021-06-30 2021-05-23 2021-07-01 2021-06-17 2021-07-27 ts in Public Facilities nvelope 7 5 ction of 12 objects in 2021. BEEPAF-P165405-RFB-06-W- Energy Efficiency Investmen Single Stage - One E 2022-10-1 22-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National 0.00 Signed 2022-04-01 2022-07-04 2022-04-11 2022-05-09 2022-08-02 2022-05-23 2022-08-25 2022-06-17 ts in Public Facilities nvelope 5 ction of 10 objects in 2022. Request for B BEEPAF-165405-RFB-07-W-2 ids - Works ( Energy Efficiency Investmen Single Stage - One E 2021-12-1 1-FBIH / Works on reconstruc IBRD / 89060 Post Request for Bids Open - National without preq 535,364.38 Signed 2021-06-15 2021-06-18 2021-06-20 2021-06-18 2021-07-20 2021-07-16 2021-07-30 2021-07-26 2021-08-16 2021-09-03 ts in Public Facilities nvelope 4 tion of 2 objects in Canton Tu ualification) zla SPD Request for B BEEPAF-165405-RFB-08-W-2 ids - Works ( Energy Efficiency Investmen Single Stage - One E 1,381,877.2 2021-12-1 1-FBIH / Works on reconstruc IBRD / 89060 Post Request for Bids Open - National without preq Signed 2021-06-15 2021-06-23 2021-06-20 2021-06-23 2021-07-20 2021-07-21 2021-07-30 2021-09-08 2021-08-16 2021-09-29 ts in Public Facilities nvelope 1 4 tion of 5 objects in ZE-DO ca ualification) nton SPD Request for B BEEPAF-165405-RFB-09-W-2 ids - Works ( Energy Efficiency Investmen Single Stage - One E 1,315,821.0 2021-12-1 1-FBIH / Works on reconstruc IBRD / 89060 Post Request for Bids Open - National without preq Signed 2021-06-16 2021-06-23 2021-06-21 2021-06-23 2021-07-21 2021-07-21 2021-07-31 2021-08-25 2021-08-17 2021-09-18 ts in Public Facilities nvelope 8 5 tion of 5 objects in ZE-DO ca ualification) nton SPD Request for B BEEPAF-165405-RFB-10-W-2 ids - Works ( Energy Efficiency Investmen Single Stage - One E 2,691,539.6 2021-12-1 1-FBIH / Works on reconstruc IBRD / 89060 Post Request for Bids Open - National without preq Signed 2021-06-17 2021-06-23 2021-06-22 2021-06-23 2021-07-22 2021-07-21 2021-08-01 2021-09-03 2021-08-18 2021-09-29 ts in Public Facilities nvelope 0 6 tion of 5 objects in ZE-DO ca ualification) nton SPD Request for B BEEPAF-165405-RFB-11-W-2 ids - Works ( Energy Efficiency Investmen Single Stage - One E 2021-12-1 1-FBIH / Works on reconstruc IBRD / 89060 Post Request for Bids Open - National without preq 925,811.86 Signed 2021-06-18 2021-06-23 2021-06-23 2021-06-23 2021-07-23 2021-07-21 2021-08-02 2021-08-25 2021-08-19 2021-09-18 ts in Public Facilities nvelope 7 tion of 5 objects in ZE-DO ca ualification) nton SPD Request for B BEEPAF-P165405-RFB-01-W- ids - Works ( Energy Efficiency Investmen Single Stage - One E 2021-12-1 20-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National without preq 0.00 Canceled 2021-06-14 2021-06-17 2021-06-17 2021-06-17 2021-07-17 2021-07-27 2021-08-13 ts in Public Facilities nvelope 1 ction of 3 objects in KS ualification) SPD BEEPAF-P165405-RFB-12-W- 21-FBIH / Works on reconstru Request for B ction of objects: LOT 1: Polikli ids - Works ( Energy Efficiency Investmen Single Stage - One E 2,143,608.7 2022-03-1 nika za plućne bolesti "Podhr IBRD / 89060 Post Request for Bids Open - National without preq Signed 2021-09-10 2021-10-01 2021-09-15 2021-10-15 2021-10-29 2021-10-29 2021-11-29 2021-11-17 2022-01-11 ts in Public Facilities nvelope 1 7 astovi, LOT 2: UKCS Klinika z ualification) a urgentnu medicinu Sarajev SPD o, LOT 3: UKCS Klinika za fizi kalnu medicinu i rehabilitacij u Sarajevo Request for B BEEPAF-P165405-RFB-13-W- ids - Works ( Energy Efficiency Investmen Single Stage - One E 2023-01-1 22-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National without preq 0.00 Signed 2022-07-16 2022-07-27 2022-07-21 2022-08-18 2022-08-25 2022-09-01 2022-08-25 2022-09-20 ts in Public Facilities nvelope 8 ction on one object in Canton ualification) Sarajevo SPD B EEP-PI 4 3580-NCB-30-W1 5 - FBIH / Works for impleme ntation of energy efficiency Energy Efficiency Investmen Single Stage - One E 1,061,492.1 IDA / 53930 Prior Request for Bids Open - National Signed 2015-09-29 2015-12-19 measures for university clinic ts in Public Facilities nvelope 8 al center Mostar Lot 1 and un iversity clinical center Tuzla s urgery clinic Gradina Lot 2 -P143580-BA-BEEP-5393BA- Energy Efficiency Investmen Single Stage - One E Under Imple NCB-W-15-5-RS / RETROFITTI IDA / 53930 Prior Request for Bids Open - National 0.00 2016-04-20 ts in Public Facilities nvelope mentation NG OF JZU BOLNICA ZVORNIK P143580-BA-BEEP-5393BA-N Energy Efficiency Investmen Single Stage - One E Under Imple CB-W-14-4-RS / Retrofitting o IDA / 53930 Prior Request for Bids Open - National 0.00 2016-04-20 ts in Public Facilities nvelope mentation f University Hospital Foca BEEP-P143580-NCB-29-W-15 -FBIH / Works for implementa tion of energy efficiency mea Energy Efficiency Investmen Single Stage - One E IDA / 53930 Prior Request for Bids Open - National 708,250.25 Signed 2015-07-08 2016-01-08 sures for University of Clinica ts in Public Facilities nvelope l Center Sarajevo (Departme nt of Orthopedic and Trauma ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BEEPAF-P165405-RFQ-04-G- 23-FBIH / "Purchasing and Ins talation (Performance Monito Energy Efficiency Investmen Request for Quota Single Stage - One E Pending Impl ring System for measuring th IBRD / 89060 Post Limited 0.00 2023-01-20 2023-02-07 2023-02-27 ts in Public Facilities tions nvelope ementation e temperature and humidity) (6 buildings) - 20232. buldin gs (allocated)" Page 1 BEEPAF-P165405-RFQ-05-G- 20-FBIH / Purchasing and Inst Energy Efficiency Investmen Request for Quota Single Stage - One E Pending Impl alation of Equipment require IBRD / 89060 Post Limited 0.00 2020-09-06 2020-09-24 2020-10-14 ts in Public Facilities tions nvelope ementation d for Energy efficiency infor mation system update (EE R evolving fund) BEEPAF-P165405-RFQ-06-G- Energy Efficiency Investmen Request for Quota Single Stage - One E 20-FBIH / Purchasing and Inst IBRD / 89060 Post Limited 27,764.72 Signed 2020-05-20 2021-01-08 2020-06-07 2021-02-16 2020-06-27 ts in Public Facilities tions nvelope alation of IT Equipment requi red PIU BEEPAF-P165405-RFQ-07-G- Energy Efficiency Investmen Request for Quota Single Stage - One E 20-FBIH / Purchasing of Furni IBRD / 89060 Post Limited 2,074.95 Completed 2020-05-20 2020-05-29 2020-06-07 2020-10-27 2020-06-27 2020-12-01 ts in Public Facilities tions nvelope ture required PIU BEEPAF-P165405-RFQ-08-G- Energy Efficiency Investmen Request for Quota Single Stage - One E Pending Impl 20-FBIH / Contract Managem IBRD / 89060 Post Limited 0.00 2020-09-20 2020-10-16 2020-12-15 ts in Public Facilities tions nvelope ementation ent Software BEEPAF-P165405-NCB-01-G- 20-FBIH / "Purchasing and Ins talation (Performance Monito Energy Efficiency Investmen Single Stage - One E ring System for measuring th IBRD / 89060 Post Request for Bids Open - National 0.00 Canceled 2020-07-15 2020-07-17 2020-08-07 2020-08-12 2020-08-16 2020-09-05 ts in Public Facilities nvelope e temperature and humidity) (20 buildings) - 2020. buldin gs (allocated)" BEEPAF-P165405-RFB-02-G- 22-FBIH / "Purchasing and Ins Energy Efficiency Investmen Single Stage - One E Pending Impl tallation (Performance Monit IBRD / 89060 Post Request for Bids Open - National 0.00 2022-01-15 2022-01-17 2022-02-07 2022-02-12 2022-02-16 2022-03-18 ts in Public Facilities nvelope ementation oring System for measuring t he temperature and humidity ) BEEPAF-P165405-NCB-02-G- 21-FBIH / "Purchasing and Ins talation (Performance Monito Energy Efficiency Investmen Single Stage - One E ring System for measuring th IBRD / 89060 Post Request for Bids Open - National 0.00 Canceled 2021-01-15 2021-01-17 2021-02-07 2021-02-12 2021-02-16 2021-03-08 ts in Public Facilities nvelope e temperature and humidity) (25 buildings) - 2020. buldin gs (allocated)" BEEPAF-P165405-RFB-03-G- 23-FBIH / "Purchasing and Ins Energy Efficiency Investmen Single Stage - One E Pending Impl tallation (Performance Monit IBRD / 89060 Post Request for Bids Open - National 0.00 2023-01-15 2023-01-17 2023-02-07 2023-02-12 2023-02-16 2023-03-18 ts in Public Facilities nvelope ementation oring System for measuring t he temperature and humidity ) BEEPAF-P165405-NCB-03-G- 22-FBIH / "Purchasing and Ins talation (Performance Monito Energy Efficiency Investmen Single Stage - One E ring System for measuring th IBRD / 89060 Post Request for Bids Open - National 0.00 Canceled 2022-01-15 2022-01-17 2022-02-07 2022-02-12 2022-02-16 2022-03-08 ts in Public Facilities nvelope e temperature and humidity) (20 buildings) - 2022. buldin gs (allocated)" BEEPAF-P165405-RFB-01-G- 21-FBIH / "Purchasing and Ins Energy Efficiency Investmen Single Stage - One E tallation (Performance Monit IBRD / 89060 Post Request for Bids Open - National 174,238.32 Signed 2021-02-03 2021-02-08 2021-02-05 2021-02-26 2021-03-02 2021-03-03 2021-03-11 2021-03-07 2021-03-24 2021-04-21 ts in Public Facilities nvelope oring System for measuring t he temperature and humidity ) (38 buildings) " BEEPAF--P165405-RFQ-09-G- 21-FBIH / Purchasing and Inst Energy Efficiency Investmen Request for Quota Single Stage - One E allation (Performance Monito IBRD / 89060 Post Limited 23,718.00 Signed 2021-07-03 2021-09-24 2021-07-26 2021-10-27 2021-08-25 ts in Public Facilities tions nvelope ring System for measuring th e temperature and humidity BEEPAF-P165405-RFQ-10-G- Energy Efficiency Investmen Request for Quota Single Stage - One E 21-FBIH / Procurement of equ IBRD / 89060 Post Limited 9,991.83 Signed 2021-06-30 2021-09-10 2021-07-23 2021-10-16 2021-09-21 ts in Public Facilities tions nvelope ipment for video conference BEEPAF-P165405-RFQ-11-G- 22-FBIH / Equipment for mea suring the heat energy consu Energy Efficiency Investmen Request for Quota Single Stage - One E IBRD / 89060 Post Limited 0.00 Canceled 2022-07-25 2022-09-07 2022-08-17 2022-10-16 mption and temperature/hu ts in Public Facilities tions nvelope midity and Equipment for re mote reading of meters in a wired M-bus system BEEPAF-P165405-RFQ-12-G- 22-FBIH / Equipment for mea suring the heat energy consu Energy Efficiency Investmen Request for Quota Single Stage - One E IBRD / 89060 Post Open - National 0.00 Signed 2022-10-13 2022-11-09 2023-03-09 mption and internal and exte ts in Public Facilities tions nvelope rnal temperatures and Equip ment for remote reading of meters in a wired M-bus syst em BEEPAF-P165405-RFB-03-G- 22-FBIH / Equipment for mea suring the heat energy consu Energy Efficiency Investmen Single Stage - One E Pending Impl IBRD / 89060 Post Request for Bids Open - National 0.00 2022-11-28 2022-11-30 2022-12-28 2022-12-29 2023-01-15 2023-05-15 mption/temperatures and Eq ts in Public Facilities nvelope ementation uipment for remote reading o f meters in a wired M-bus sys tem P143580-BA-BEEP-5393BA-S Energy Efficiency Investmen Request for Quota Open - Internationa H-G-14-13-RS / Supply of met IDA / 53930 Prior 46,774.87 Signed 2016-03-23 ts in Public Facilities tions l ering equipment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BEEPAF-P165405-RFB-01-NC S-21-FBIH / ENERGY EFFICIEN CY SERVICES for implementation of energy Energy Efficiency Investmen Single Stage - One E Pending Impl efficiency measures, includin IBRD / 89060 Post Request for Bids Open - National 0.00 2021-06-30 2021-07-05 2021-08-04 2021-08-19 2021-09-07 2023-03-11 ts in Public Facilities nvelope ementation g engineering design, constr uction works, measurement and verification of savings an d first year operations and m aintenance services CONSULTING FIRMS Page 2 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BEEPAF-P165405-CQ-01-CS- Energy Efficiency Investmen Consultant Qualifi 20-FBIH / Detailed energy au IBRD / 89060 Post Open - National 158,785.08 Signed 2020-07-10 2020-05-07 2020-07-29 2020-08-06 2020-11-11 2020-08-20 2020-12-22 2020-08-22 2021-01-12 2020-11-20 ts in Public Facilities cation Selection dits - 50 buildings BEEPAF-P165405-CQ-04-CS- Energy Efficiency Investmen Consultant Qualifi 20-FBIH / Audit of design (11 IBRD / 89060 Post Open - National 120,339.23 Signed 2020-07-10 2020-05-08 2020-07-29 2020-08-06 2021-01-28 2020-08-20 2021-02-16 2020-08-22 2021-03-04 2020-10-21 ts in Public Facilities cation Selection +9=20 buildings) BEEPAF-P165405-CQ-08-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 22-FBIH / Audit of design (14 IBRD / 89060 Post Open - National 0.00 2022-01-10 2022-01-29 2022-02-06 2022-03-08 2022-03-10 2022-05-09 ts in Public Facilities cation Selection ntation +6=20 buildings) BEEPAF-P165405-CQ-09-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 23-FBIH / Design and tecnical IBRD / 89060 Post Open - National 0.00 2023-01-10 2023-01-29 2023-02-06 2023-02-20 2023-02-22 2023-08-21 ts in Public Facilities cation Selection ntation supervision (1+5=6 buildings ) BEEPAF-P165405-CQ-10-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 23-FBIH / Audit of design (1+ IBRD / 89060 Post Open - National 0.00 2023-01-10 2023-01-29 2023-02-06 2023-02-20 2023-02-22 2023-04-23 ts in Public Facilities cation Selection ntation 5=6 buildings) BEEPAF-P165405-CQ-11-CS- Energy Efficiency Investmen Consultant Qualifi 20-FBIH / Social monitoring a IBRD / 89060 Post Open - National 251,644.22 Signed 2020-06-10 2020-05-12 2020-06-29 2020-07-07 2020-10-09 2020-07-20 2020-12-09 2020-07-23 2020-12-12 2020-10-21 ts in Public Facilities cation Selection nd evaluation (up to 18 buildi ngs) BEEPAF-P165405-CQ-12-CS- Energy Efficiency Investmen Consultant Qualifi Under Implement IBRD / 89060 Post Open - National 0.00 2020-07-10 2020-05-15 2020-07-29 2020-08-06 2020-08-20 2020-08-22 2020-11-20 20-FBIH / Energy certificates ts in Public Facilities cation Selection ation BEEPAF-P165405-CQ-14-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme IDA / 55380 Post Open - National 0.00 2022-01-10 2022-01-29 2022-02-06 2022-02-20 2022-02-22 2022-05-23 22-FBIH / Energy certificates ts in Public Facilities cation Selection ntation BEEPAF-P165405-CQ-15-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme IBRD / 89060 Post Open - National 0.00 2023-01-10 2023-01-29 2023-02-06 2023-02-20 2023-02-22 2023-05-23 23-FBIH / Energy certificates ts in Public Facilities cation Selection ntation BEEPAF-P165405-CQ-20-CS- Support for the Developmen Consultant Qualifi 20-FBIH / Training for benefic IBRD / 89060 t of Scalable Financing Mech Post Open - National 39,567.33 Signed 2020-07-10 2021-12-08 2020-07-29 2020-08-06 2022-02-11 2020-08-20 2022-03-11 2020-08-22 2022-03-22 2024-06-22 cation Selection iaries and energy manageme anisms and Capacity Buildin nts g BEEPAF-P165405-CQ-22-CS- Support for the Developmen Consultant Qualifi Pending Impleme 22-FBIH / Training for benefic IBRD / 89060 t of Scalable Financing Mech Post Open - National 0.00 2022-01-10 2022-01-29 2022-02-06 2022-02-20 2022-02-22 2025-12-23 cation Selection ntation iaries and energy manageme anisms and Capacity Buildin nts g BEEPAF-P165405-CQ-23-CS- Support for the Developmen Consultant Qualifi Pending Impleme 23-FBIH / Training for benefic IBRD / 89060 t of Scalable Financing Mech Post Open - National 0.00 2023-01-10 2023-01-29 2023-02-06 2023-02-20 2023-02-22 2026-12-23 cation Selection ntation iaries and energy manageme anisms and Capacity Buildin nts g BEEPAF-P165405-CQ-24-CS- Support for the Developmen 20-FBIH / Other training and t of Scalable Financing Mech Consultant Qualifi IBRD / 89060 Post Open - National 0.00 Canceled 2020-11-01 2020-11-15 2020-11-23 2020-12-07 2020-12-09 2024-10-09 capacity buildings (local Gov anisms and Capacity Buildin cation Selection ernments, local energy servic g e providers, etc.) BEEPAF-P165405-CQ-28-CS- Support for the Developmen Consultant Qualifi 20-FBIH / Communication an IBRD / 89060 t of Scalable Financing Mech Post Open - National 301,660.93 Signed 2020-05-10 2020-05-07 2020-05-29 2020-06-06 2020-08-03 2020-06-20 2020-10-16 2020-06-22 2020-10-17 2024-04-22 cation Selection d Promotion Public Campaign anisms and Capacity Buildin s g BEEPAF-P165405-CQ-03-CS- Energy Efficiency Investmen Consultant Qualifi 20-FBIH / Design and technic IBRD / 89060 Post Open - National 111,916.78 Signed 2020-07-10 2020-12-17 2020-07-29 2020-08-06 2021-01-26 2020-08-20 2021-02-19 2020-08-22 2021-03-04 2021-02-18 ts in Public Facilities cation Selection al supervision (10 buildings) BEEPAF-P165405-CQ-07-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 22-FBIH / Design and technic IBRD / 89060 Post Open - National 0.00 2022-01-10 2022-01-29 2022-02-06 2022-02-20 2022-02-22 2022-08-21 ts in Public Facilities cation Selection ntation al supervision (10 buildings) BEEPAF-P165405-CQ-29-CS- Energy Efficiency Investmen Consultant Qualifi 20-FBIH / Design and technic IBRD / 89060 Post Open - National 55,048.49 Signed 2020-07-10 2020-05-08 2020-07-29 2020-08-06 2021-01-26 2020-08-20 2021-02-10 2020-08-22 2021-03-04 2021-02-18 ts in Public Facilities cation Selection al supervision (10 buildings) BEEPAF-P165405-CQ-30-CS- Energy Efficiency Investmen Consultant Qualifi 21-FBIH / Design and technic IBRD / 89060 Post Open - National 289,020.60 Signed 2021-01-10 2020-12-17 2021-01-29 2021-02-06 2021-01-26 2021-02-20 2021-02-10 2021-02-22 2021-03-04 2021-08-21 ts in Public Facilities cation Selection al supervision (10 buildings) BEEPAF-P165405-CQ-31-CS- Energy Efficiency Investmen Consultant Qualifi 21-FBIH / Design and technic IBRD / 89060 Post Open - National 35,132.00 Signed 2021-01-10 2020-12-17 2021-01-29 2021-02-06 2021-01-26 2021-02-20 2021-02-19 2021-02-22 2021-03-04 2021-08-21 ts in Public Facilities cation Selection al supervision (5 buildings) BEEPAF-P165405-CQ-32-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 22-FBIH / Design and technic IBRD / 89060 Post Open - National 0.00 2022-01-10 2022-01-29 2022-02-06 2022-02-20 2022-02-22 2022-08-21 ts in Public Facilities cation Selection ntation al supervision (10 buildings) BEEPAF-P165405-CQ-05-CS- Energy Efficiency Investmen Consultant Qualifi 21-FBIH / Design and technic IBRD / 89060 Post Open - National 142,441.79 Signed 2021-06-18 2021-07-29 2021-07-02 2021-07-30 2021-07-12 2021-09-16 2021-07-27 2021-10-07 2021-08-02 2021-11-27 2021-10-31 ts in Public Facilities cation Selection al supervision (11 buildings) BEEPAF-P165405-CQ-33-CS- Energy Efficiency Investmen Consultant Qualifi 21-FBIH / Design and technic IBRD / 89060 Post Open - National 156,534.09 Signed 2021-06-18 2021-07-30 2021-07-02 2021-07-12 2021-09-22 2021-07-27 2021-10-06 2021-08-02 2021-11-27 2021-10-01 ts in Public Facilities cation Selection al supervision (7 objects) BEEPAF-P165405-CQ-06-CS- Energy Efficiency Investmen Consultant Qualifi IBRD / 89060 Post Open - National 42,051.18 Signed 2021-07-30 2021-07-30 2021-08-13 2021-08-23 2021-11-11 2021-09-06 2021-12-01 2021-09-12 2021-12-09 2021-11-11 21-FBIH / Audit of design (7 b ts in Public Facilities cation Selection uildings) BEEPAF-P165405-CQ-02-CS- Energy Efficiency Investmen Consultant Qualifi 21-FBIH / Detailed energy au IBRD / 89060 Post Open - National 199,355.48 Signed 2021-01-10 2021-08-26 2021-01-29 2021-02-06 2021-09-22 2021-02-20 2021-10-06 2021-02-22 2021-11-06 2021-05-23 ts in Public Facilities cation Selection dits - 52 buildings BEEPAF-P165405-CQ-13-CS- Energy Efficiency Investmen Consultant Qualifi IBRD / 89060 Post Open - National 135,918.81 Signed 2021-10-29 2021-12-13 2021-11-12 2021-11-22 2022-02-11 2021-12-06 2022-04-10 2021-12-12 2022-04-16 2022-02-10 21-FBIH / Energy certificates ts in Public Facilities cation Selection BEEPAF-P165405-CQ-21-CS- Support for the Developmen Consultant Qualifi Pending Impleme 21-FBIH / Training for benefic IBRD / 89060 t of Scalable Financing Mech Post Open - National 0.00 2021-10-29 2021-11-12 2021-11-22 2021-12-06 2021-12-12 2022-02-10 cation Selection ntation iaries and energy manageme anisms and Capacity Buildin nts g Page 3 BEEPAF-P165405-CQ-34-CS- 21-FBIH / Stocktaking of all p Support for the Developmen ublic buildings, development t of Scalable Financing Mech Consultant Qualifi IBRD / 89060 Post Open - National 265,077.74 Signed 2021-11-22 2021-12-13 2021-12-06 2021-12-19 2022-03-07 2022-01-08 2022-03-30 2022-01-16 2022-04-25 2022-07-15 of digital map-based platfor anisms and Capacity Buildin cation Selection m, overview of the public buil g dings that need the EE renov ation BEEPAF-P165405-CQ-35-CS- Support for the Developmen 21-FBIH / Assessment of the t of Scalable Financing Mech Consultant Qualifi energy use and energy savin IBRD / 89060 Post Open - National 239,867.10 Signed 2021-11-22 2021-12-13 2021-12-06 2021-12-19 2022-03-07 2022-01-08 2022-03-30 2022-01-16 2022-04-25 2022-07-15 anisms and Capacity Buildin cation Selection gs through EE investment in g eligible public buildings BEEPAF-P165405-CQ-36-CS- Support for the Developmen Consultant Qualifi 21-FBIH / TA to the Revolving IBRD / 89060 t of Scalable Financing Mech Post Open - National 107,010.86 Signed 2021-11-22 2021-12-08 2021-12-06 2021-12-19 2022-03-15 2022-01-08 2022-04-01 2022-01-16 2022-04-16 2022-07-15 cation Selection fund anisms and Capacity Buildin g BEEPAF-P165405-CQ-25-CS- Support for the Developmen Consultant Qualifi 20-FBIH / Capacity building M IBRD / 89060 t of Scalable Financing Mech Post Open - National 118,515.67 Signed 2021-11-22 2021-11-26 2021-12-06 2021-12-19 2022-03-22 2022-01-08 2022-03-08 2022-01-16 2022-04-19 2023-04-11 cation Selection inistry and PIU anisms and Capacity Buildin g BEEPAF-P165405-CQ-26-CS- Support for the Developmen Consultant Qualifi 21-FBIH / Targeted women tr IBRD / 89060 t of Scalable Financing Mech Post Open - National 109,392.87 Signed 2021-11-22 2021-12-08 2021-12-06 2021-12-19 2022-02-11 2021-12-21 2022-03-15 2021-12-29 2022-03-31 2022-06-27 cation Selection aining anisms and Capacity Buildin g BEEPAF-P165405-CQ-27-CS- Support for the Developmen 20-FBIH / Energy efficiency in t of Scalable Financing Mech Consultant Qualifi Under Implement IBRD / 89060 Post Open - National 0.00 2021-11-22 2021-12-08 2021-12-06 2021-12-19 2022-01-08 2022-01-16 2022-07-15 formation system updates (e. anisms and Capacity Buildin cation Selection ation g. EE Revolving fund) g BEEPAF-P165405-CQ-37-CS- Energy Efficiency Investmen Consultant Qualifi 22-FBIH / Design and works s IBRD / 89060 Post Open - National 0.00 Signed 2022-11-22 2022-11-22 2022-12-06 2022-12-16 2023-02-02 2022-12-23 2023-02-20 2022-12-28 2023-03-28 ts in Public Facilities cation Selection upervision (14 objects) BEEPAF-P165405-CQ-38-CS- Energy Efficiency Investmen Consultant Qualifi 22-FBIH / Design and works s IBRD / 89060 Post Open - National 0.00 Signed 2022-11-22 2022-11-22 2022-12-06 2022-12-16 2023-02-02 2022-12-23 2023-02-20 2022-12-28 2023-03-28 ts in Public Facilities cation Selection upervision (11 objects) BEEPAF-P16405-CQ-39-CS-2 Energy Efficiency Investmen Consultant Qualifi IBRD / 89060 Post Open - National 0.00 Signed 2022-11-22 2022-11-22 2022-12-06 2022-12-16 2023-02-02 2022-12-23 2023-02-20 2022-12-28 2023-03-28 2-FBIH / Audit of design (25 o ts in Public Facilities cation Selection bjects) BEEPAF-P165405-CQ-40-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 23-FBIH / Energy certification IBRD / 89060 Post Open - National 0.00 2023-06-20 2023-07-04 2023-07-14 2023-07-21 2023-07-26 2023-10-24 ts in Public Facilities cation Selection ntation (up to 30 objects) BEEPAF-P165405-CQ-41-CS- Support for the Developmen Consultant Qualifi Pending Impleme 23-FBIH / Energy training (up IBRD / 89060 t of Scalable Financing Mech Post Open - National 0.00 2023-06-20 2023-07-04 2023-07-14 2023-07-21 2023-07-26 2023-10-24 cation Selection ntation to 30 objects) anisms and Capacity Buildin g BEEPAF-P165405-CQ-45-CS- Support for the Developmen 23-FBIH / Provision of consult t of Scalable Financing Mech Consultant Qualifi Under Implement ing services related to the de IBRD / 89060 Post Open - National 0.00 2023-05-10 2023-05-10 2023-05-24 2023-06-10 2023-06-13 2023-06-19 2024-01-15 anisms and Capacity Buildin cation Selection ation velopment of Study of altern g ative heating systems in buil dings in FBiH BEEPAF-P165405-CQ-46-CS- 23-FBIH / Provision of consult Support for the Developmen ing services related to the pr t of Scalable Financing Mech Consultant Qualifi Under Implement IBRD / 89060 Post Open - National 0.00 2023-05-10 2023-05-10 2023-05-24 2023-06-10 2023-06-13 2023-07-16 2023-07-31 eparation and organization of anisms and Capacity Buildin cation Selection ation the Second International Con g ference on Energy Efficiency in Public Buildings BEEPAF-P165405-CQ-43-CS- 23-FBIH / Provision of consult ing services related to draftin Support for the Developmen g the amendments and additi t of Scalable Financing Mech Consultant Qualifi Under Implement ons to the Regulation on con IBRD / 89060 Post Open - National 0.00 2023-05-10 2023-05-10 2023-05-24 2023-06-01 2023-06-17 2023-07-07 2024-01-03 anisms and Capacity Buildin cation Selection ation ducting energy audits and iss g uing energy certificates and t o the Rulebook on minimum requirements for the energy characteristics of buildings BEEPAF-P165405-CQ-42-CS- 23-FBIH / Provision of consult Support for the Developmen ing services related to the de t of Scalable Financing Mech Consultant Qualifi Under Implement IBRD / 89060 Post Open - National 0.00 2023-05-10 2023-05-10 2023-05-24 2023-06-10 2023-06-13 2023-07-16 2024-02-11 velopment of the Second Op anisms and Capacity Buildin cation Selection ation erational Plan for improving g energy efficiency in FBiH inst itutions BEEPAF-P165405-CQ-44-CS- 23-FBIH / Provision of consult anting services related to the Support for the Developmen development of the Guidelin t of Scalable Financing Mech Consultant Qualifi Under Implement es for energy renovation of b IBRD / 89060 Post Open - National 0.00 2023-05-10 2023-06-15 2023-05-24 2023-06-10 2023-06-13 2023-06-19 2023-12-16 anisms and Capacity Buildin cation Selection ation uildings, which have the stat g us of a national monument or are located within the scope of the buffer zone of the nati onal monument of the ambie nt en BEEP-P143580-CQ-02-CS-15- FBIH-II / Performing works su Energy Efficiency Investmen Consultant Qualifi Open - Internationa IDA / 53930 Prior 79,112.25 Signed 2015-07-08 2015-12-18 pervision, technical monitori ts in Public Facilities cation Selection l ng and evaluation and energ y labelling BA-BEEP-CQ-08-CS-14-5393 BA-RS- / performing detailed energy audits, monitoring an Energy Efficiency Investmen Consultant Qualifi Open - Internationa d evaluation, technical desig IDA / 53930 Prior 268,186.87 Signed 2015-07-10 2015-07-14 ts in Public Facilities cation Selection l n, supervision and technical documentation for energy la bels for retrofitted public buil dings BA-BEEP-5393BA-QBS-CS-14 -16-RS / Preparation of techni Energy Efficiency Investmen Quality Based Sel Open - Internationa IDA / 53930 Prior 665,521.79 Signed 2016-05-18 2016-05-20 cal design and works supervi ts in Public Facilities ection l sion for retrofitting of public buildings BA-BEEP-CQ-22-CS-14-5393 Energy Efficiency Investmen Consultant Qualifi Open - Internationa BA-RS / communication activi IDA / 53930 Prior 327,450.52 Signed 2015-06-04 2015-06-12 ts in Public Facilities cation Selection l ties services BEEP-P143580-CQ-02-CS-15- FBIH-I / Performing Works Su Energy Efficiency Investmen Consultant Qualifi Open - Internationa IDA / 53930 Prior 13,833.13 Signed 2015-07-08 2015-12-18 pervision, Technical Monitori ts in Public Facilities cation Selection l ng and Evaluation and Energ y Labelling Page 4 BA-BEEP-CQ-08-CS-14-5393 BA-RS / Performing detailed e nergy audits, monitoring and Energy Efficiency Investmen Consultant Qualifi Open - Internationa IDA / 53930 Prior 207,519.34 Signed 2016-06-15 2015-07-14 evaluation, technical design, ts in Public Facilities cation Selection l supervision and technical do cumentation for energy label s for retrofitted public buildin gs BEEP-P143580-CQ-05-CS-15- FBIH I and II / Consulting serv Energy Efficiency Investmen Consultant Qualifi Open - Internationa ices to perform design, techn IDA / 53930 Prior 300,008.87 Signed 2016-02-12 2016-02-16 ts in Public Facilities cation Selection l ical monitoring services - (be fore and after ) Works Superv ision BEEPP143580CQ-05-CS-15-F BIH I and II / Design and tech Energy Efficiency Investmen Consultant Qualifi Open - Internationa IDA / 53930 Prior 246,401.84 Signed 2016-02-12 2016-02-16 nical monitoring ( Lump Sum ts in Public Facilities cation Selection l ) and Supervision ( Time Bas ed) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BEEPAF-P165405-IC-16-CS-2 Support for the Developmen 0-FBIH / Development / Tech t of Scalable Financing Mech Individual Consult IBRD / 89060 Post Limited 27,391.12 Signed 2020-05-10 2020-06-09 2020-05-15 2020-09-09 2020-06-20 2020-10-22 2020-06-22 2020-10-23 2024-04-22 nical Assistance for EE Revol anisms and Capacity Buildin ant Selection ving fund / Revolving Fund E g xpert BEEPAF-P165405-IC-17-CS-2 Support for the Developmen 0-FBIH / Development / Tech t of Scalable Financing Mech Individual Consult IBRD / 89060 Post Limited 19,356.37 Signed 2020-05-10 2020-06-09 2020-05-15 2020-09-09 2020-06-20 2020-10-22 2020-06-22 2020-10-23 2024-04-22 nical Assistance for EE Revol anisms and Capacity Buildin ant Selection ving fund /Financial Expert g BEEPAF-P165405-IC-18-CS-2 Support for the Developmen 0-FBIH / Development / Tech t of Scalable Financing Mech Individual Consult IBRD / 89060 Post Limited 17,832.76 Signed 2020-05-10 2020-07-23 2020-05-15 2020-09-09 2020-06-20 2020-10-22 2020-06-22 2020-10-23 2024-04-22 nical Assistance for EE Revol anisms and Capacity Buildin ant Selection ving fund /Policy & Regulator g y Expert BEEPAF-P165405-IC-19-CS-2 Support for the Developmen 0-FBIH / Development / Tech t of Scalable Financing Mech Individual Consult IBRD / 89060 Post Limited 25,448.73 Signed 2020-05-10 2020-06-09 2020-05-15 2020-09-10 2020-06-20 2020-10-22 2020-06-22 2020-10-23 2024-04-22 nical Assistance for EE Revol anisms and Capacity Buildin ant Selection ving fund / Technical Expert g BEEPAF-P165405-IC-07-CS-2 Individual Consult IBRD / 89060 Project Management Post Limited 102,941.57 Signed 2020-05-01 2020-02-21 2020-05-01 2020-05-08 2020-06-06 2020-05-18 2020-06-08 2020-05-19 2024-05-01 0-FBIH / Contract Manageme ant Selection nt Expert BEEPAF-P165405-IC-08-CS-2 Individual Consult IBRD / 89060 Project Management Post Limited 54,633.24 Signed 2020-05-01 2020-02-18 2020-05-01 2020-05-08 2020-06-06 2020-05-18 2020-06-08 2020-05-19 2024-05-01 0-FBIH / Administrative Assist ant Selection ant BEEPAF-P165405-IC-01-CS-2 Individual Consult IBRD / 89060 Project Management Prior Direct 121,680.15 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 0-FBIH / Project Leader ant Selection BEEPAF-P165405-IC-05-CS-2 Individual Consult IBRD / 89060 Project Management Prior Direct 96,181.67 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 0-FBIH / Technical Expert II ant Selection BEEPAF-P165405-IC-04-CS-2 Individual Consult IBRD / 89060 Project Management Prior Direct 96,181.67 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 0-FBIH / Technical Expert I ant Selection BEEPAF-P165405-IC-06-CS-2 Individual Consult IBRD / 89060 Project Management Prior Direct 96,181.67 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 0-FBIH / Technical Expert III ant Selection BEEPAF-P165405-IC-02-CS-2 Individual Consult IBRD / 89060 Project Management Prior Direct 96,181.67 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 0-FBIH / Procurement Special ant Selection ist BEEPAF-P165405-IC-03-CS-2 Individual Consult 0-FBIH / Financial Manageme IBRD / 89060 Project Management Prior Direct 96,181.67 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 ant Selection nt Specialist BEEPAF-P165405-IC-20-CS-2 3-FBIH / Provision of consulti ng services related to the str Support for the Developmen engthening of institutional fr t of Scalable Financing Mech Individual Consult Under Implement amework and the energy effi IBRD / 89060 Post Limited 0.00 2023-05-16 2023-06-16 2023-05-21 2023-05-31 2023-06-06 2023-12-03 anisms and Capacity Buildin ant Selection ation ciency management system g capacity development throug h design of the feasibility stu dy for establishment of the E nergy Efficiency Agency in F ederat BEEPAF-P165405-IC-21-CS-2 3-FBIH / Consultant services r Support for the Developmen elated to the diversifying fun t of Scalable Financing Mech Individual Consult Under Implement IBRD / 89060 Post Limited 0.00 2023-05-23 2023-05-28 2023-06-07 2023-06-13 2023-12-10 ding sources for financing im anisms and Capacity Buildin ant Selection ation provements in public sector g buildings in Federation of Bos nia and Herzegovina . P143580-BA-BEEP-5393BA- Energy Efficiency Investmen Individual Consult IC-CS-15-26-RS / Procuremen IDA / 53930 Prior Open 33,928.37 Signed 2017-11-06 2017-11-02 ts in Public Facilities ant Selection t Manager BEEP-P143580-IC-24-CS-14- FBIH / FOR PROJECT COORDI Energy Efficiency Investmen Individual Consult NATOR (PC) IN THE IMPLEME IDA / 53930 Prior Open 154,133.89 Terminated 2015-11-28 2015-12-17 ts in Public Facilities ant Selection NTATION UNIT OF THE FEDER ATION MINISTRY OF PHYSICA L PLANNING BEEP-P I 43580-SSS-28-CS-1 Energy Efficiency Investmen S-FBIH / Consulting services f IDA / 53930 Prior Direct Selection Direct 9,881.71 Signed 2015-12-17 ts in Public Facilities or Financial software procure ment BEEP-P143580-IC-06-CS-14- Energy Efficiency Investmen Individual Consult Under Implement IDA / 55380 Prior Open 0.00 2017-05-09 FBIH / FINANCIAL SPECIALIST ts in Public Facilities ant Selection ation BEEP-P143580-IC-005-FBIH / Technical Expert I in the Proj Energy Efficiency Investmen Individual Consult IDA / 53930 Prior Open 99,378.05 Terminated 2015-11-28 2015-12-17 ect Implementation Unit of th ts in Public Facilities ant Selection e Federation Ministry of Physi cal Planning BEEP-P143580-IC-26-CS-14- Energy Efficiency Investmen Individual Consult IDA / 53930 Prior Open 99,378.05 Terminated 2015-11-28 2015-12-17 FBH / Technical Expert ts in Public Facilities ant Selection Page 5 BEEP-P143580-IC-27-CS-14- FBH / For a Administrative As Energy Efficiency Investmen Individual Consult sistant in the Project Implem IDA / 53930 Prior Open 42,932.38 Canceled 2015-11-28 ts in Public Facilities ant Selection entation Unit of the Federatio n Ministry of Physical Plannin g BEEP-P143580-IC-003-FBIH / For a Administrative Assistan Energy Efficiency Investmen Individual Consult t in the Project Implementati IDA / 53930 Prior Open 37,108.18 Terminated 2015-12-22 2015-12-17 ts in Public Facilities ant Selection on Unit of the Federation Min istry of Physical Planning P143580-BA-BEEP-5393BA-I Energy Efficiency Investmen Individual Consult C-CS-15-25-RS / ACCOUNTAN IDA / 53930 Prior Open 67,137.44 Signed 2015-06-18 2015-08-02 ts in Public Facilities ant Selection T AND DISBURSEMENT SPECI ALIST BEEP-P143580-IC-25-CS-14- Energy Efficiency Investmen Individual Consult IDA / 53930 Prior Open 132,009.13 Terminated 2015-11-28 2015-12-17 FBIH / Procurement Specialist ts in Public Facilities ant Selection Page 6 PROCUREMENT PLAN (Textual Part) Project information: Social Safety Net Project (P167416) Project Implementation agency: Ministry of Social Inclusion and Equity (MIES) Unidad del Registro Social Date of the Procurement Plan: September 9, 2019 Period covered by this Procurement Plan: 2019 - 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. For the implementation of Component 1, the MIES may use the Country’s own procurement procedures for “Menor Cuantía,” “Infima Cuantía,” “Ferias Inclusivas” and “C atalogo Electronico Inclusivo” to procure the goods and services identified, those procedures will be complemented by specific processes and procedures established in the Operational Manual. PROCUREMENT Ecuador : Social Safety Net Project PLAN General Information Country: Ecuador 2020-01-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167416 GPN Date: 2020-02-03 Project Name: Social Safety Net Project Loan / Credit No: IBRD / 89460 Ministry of Economic and Social Inclusion Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2-MIES-7 / Adquisición de t ablets para educadoras CNH Component 2: Technical Assi Open - Internationa Single Stage - One E y repotenciación de la infraes IBRD / 89460 stance for Capacity Building Post Request for Bids 3,251,166.98 0.00 Canceled 2020-02-24 2020-04-09 2020-05-29 2020-06-28 2020-07-21 2020-09-19 l nvelope tructura tecnológica y los sist & Monitoring and Evaluation emas de información del MIE S. C2-MIES-42 / Adquisición de Component 2: Technical Assi impresora multifunción para l Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 3,000.00 0.00 Canceled 2020-02-27 2020-04-14 2020-04-29 a gestión del Equipo Ejecutor tions nvelope & Monitoring and Evaluation del Proyecto (MIES) C2-MIES-INEC-10 / Adquisici ón de equipos informáticos, t Component 2: Technical Assi Single Stage - One E Pending Impl ablets necesarios para el lev IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 58,562.53 0.00 2022-02-28 2022-03-11 2022-04-04 2022-04-18 2022-05-02 2022-06-16 nvelope ementation antamiento de información d & Monitoring and Evaluation e la Encuesta Nacional de De snutrición Infantil C2-MIES-INEC-11 / Adquisici ón de hemoglobinómetros, e quipos analizadores de hemo Component 2: Technical Assi globina cuantitativo, con sus Single Stage - One E IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 91,936.14 78,722.00 Signed 2022-02-28 2022-04-01 2022-03-11 2022-04-01 2022-04-04 2022-04-21 2022-04-18 2022-05-05 2022-05-02 2022-05-26 2022-06-16 insumos médicos y de limpie nvelope & Monitoring and Evaluation za, necesarios para el desarrollo de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-6 / Adquisició n de vestimenta identificativ a para el operativo de campo Component 2: Technical Assi Request for Quota Single Stage - One E , necesaria para la operación IBRD / 89460 stance for Capacity Building Post Open - National 21,833.78 19,368.20 Signed 2022-03-09 2022-04-06 2022-04-14 2022-06-01 2022-05-14 tions nvelope estadística para el desarrollo & Monitoring and Evaluation de las actividades de la Encu esta Nacional de Desnutrició n Infantil C2-MIES-INEC-7 / Adquisició n de suministros de oficina y Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple papelería para el desarrollo d IBRD / 89460 stance for Capacity Building Post Open - National 3,220.43 0.00 2022-03-09 2022-06-22 2022-04-14 2022-05-14 tions nvelope mentation e las actividades de la Encue & Monitoring and Evaluation sta Nacional de Desnutrición Infantil C2-MIES-INEC-9 / Adquisició Component 2: Technical Assi n de los suministros médicos, Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 20,496.56 18,821.87 Signed 2022-03-09 2022-04-26 2022-04-15 2022-05-31 2022-05-15 necesarios para el desarrollo tions nvelope & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-20 / Suministr os de impresión (materiales Component 2: Technical Assi de impresión) y repuestos (re Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 31,523.17 27,653.55 Signed 2022-03-30 2022-04-04 2022-04-27 2022-05-31 2022-06-11 puestos y accesorios) para el tions nvelope & Monitoring and Evaluation desarrollo de las actividades de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-39 / Compra d e insumos para arrojar los de Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl sechos de las pruebas técnic IBRD / 89460 stance for Capacity Building Post Open - National 2,763.81 0.00 2022-09-14 2022-11-09 2022-11-23 tions nvelope ementation as de la encuesta de desnutri & Monitoring and Evaluation ción infantil (fundas para des echo) C2-MIES-INEC-43 / Adquisici ón de suministros de impresi Component 2: Technical Assi ón y repuestos (materiales d Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 24,640.00 0.00 Canceled 2022-09-11 2022-10-09 2022-11-23 e impresión, repuestos y acc tions nvelope & Monitoring and Evaluation esorios), para la Encuesta Na cional de Desnutrición Infanti l, fase encuesta C2-MIES-INEC-44 / Adquisici ón de equipos informáticos, d Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple ispositivos móviles para el le IBRD / 89460 stance for Capacity Building Post Open - National 33,984.16 0.00 2022-09-14 2022-10-14 2022-10-21 2022-11-25 tions nvelope mentation vantamiento de información & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-38 / Adquisici ón de equipos informáticos c on sus respectivos mantenim Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl iento preventivos, necesarios IBRD / 89460 stance for Capacity Building Post Open - National 42,560.00 0.00 2022-09-21 2022-10-28 2022-11-18 tions nvelope ementation para el personal que implem & Monitoring and Evaluation enta el proyecto para la Encu esta Nacional de Desnutrició n Infantil C2-MIES-INEC-41 / Adquisici ón de suministros de oficina Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl y papelería para el desarrollo IBRD / 89460 stance for Capacity Building Post Open - National 63,097.72 0.00 2022-11-24 2022-12-30 2023-01-29 tions nvelope ementation de las actividades de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil, fase de encuest Page 1 C2-MIES-INEC-43-1 / Adquisi ción de suministros de impre Component 2: Technical Assi sión y repuestos (materiales Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 92,279.08 0.00 2022-11-18 2022-11-24 2022-12-19 2022-12-26 2022-12-30 2023-06-28 de impresión, repuestos y ac nvelope ementation & Monitoring and Evaluation cesorios), para la Encuesta N acional de Desnutrición Infan til, fase encuesta C2-MIES-INEC-40 / Compra i nsumos para las pruebas de Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple cloro e E-coli en agua dentro IBRD / 89460 stance for Capacity Building Post Open - National 1,507.16 0.00 2022-09-14 2022-12-10 2022-11-09 2022-11-23 tions nvelope mentation de la Encuesta Nacional de D & Monitoring and Evaluation esnutrición Infantil (botellas de agua) C2-MIES-INEC-42 / Adquisici ón de equipos e insumos mé dicos y químicos para la aplic Component 2: Technical Assi ación de pruebas de calidad Single Stage - One E Under Imple IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 180,117.60 0.00 2022-12-02 2022-12-09 2022-12-07 2022-12-10 2022-12-30 2022-12-16 2023-01-09 2022-12-21 2023-01-30 2023-03-16 de agua (cloro - e-coli) y prue nvelope mentation & Monitoring and Evaluation bas de anemia en sangre, inc luye suministros de limpieza para la Encuesta Nacional de Desnutrición Infantil C2-MIES-INEC-68 / Adquisici ón de suministros de oficina Component 2: Technical Assi Single Stage - One E Under Imple y papelería para el desarrollo IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 97,607.95 0.00 2023-04-30 2023-05-02 2023-05-05 2023-05-03 2023-06-16 2023-05-08 2023-07-16 2023-08-20 2024-02-16 nvelope mentation de las actividades de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil, fase de encuesta C2-MIES-INEC-69 / Adquisici ón de equipos e insumos mé dicos y químicos para la aplic Component 2: Technical Assi ación de pruebas de calidad Open - Internationa Single Stage - One E Under Imple IBRD / 89460 stance for Capacity Building Post Request for Bids 507,282.35 0.00 2023-03-15 2023-05-02 2023-03-20 2023-05-03 2023-05-01 2023-05-10 2023-05-31 2023-07-05 2024-01-01 de agua (cloro - e-coli) y prue l nvelope mentation & Monitoring and Evaluation bas de anemia en sangre, inc luye suministros de limpieza para la Encuesta Nacional de Desnutrición Infantil C2-MIES-INEC-71 / Adquisici ón de suministros de impresi Component 2: Technical Assi ón y repuestos (materiales d Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 92,276.84 0.00 2023-05-15 2023-05-20 2023-07-01 2023-07-31 2023-09-04 2024-03-02 e impresión, repuestos y acc nvelope ementation & Monitoring and Evaluation esorios), para la Encuesta Na cional de Desnutrición Infanti l, fase encuesta C2-MIES-INEC-77 / Adquisici Component 2: Technical Assi ón equipo informático, comp Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 67,200.00 0.00 2023-04-15 2023-04-20 2023-06-01 2023-07-01 2023-08-05 2024-02-01 utadoras para la implementa nvelope ementation & Monitoring and Evaluation ción del proyecto C2-MIES-INEC-73 / Adquisici ón de insumos para las prueb Component 2: Technical Assi Request for Quota Single Stage - One E as de cloro e E-coli en agua d IBRD / 89460 stance for Capacity Building Post Open - National 3,360.00 0.00 Signed 2023-03-20 2023-04-13 2023-05-15 2023-11-11 tions nvelope entro de la Encuesta Naciona & Monitoring and Evaluation l de Desnutrición Infantil (bo tellas de agua) C2-MIES-INEC-72 / Compra d e insumos para arrojar los de Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl sechos de las pruebas técnic IBRD / 89460 stance for Capacity Building Post Open - National 2,262.21 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation as de la encuesta de desnutri & Monitoring and Evaluation ción infantil (fundas para des echo) C2-MIES-INEC-85 / Adquisici Component 2: Technical Assi Single Stage - One E Pending Impl ón de vestimenta identificati IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 78,948.81 0.00 2023-06-15 2023-06-20 2023-08-01 2023-08-31 2023-10-05 2023-12-31 nvelope ementation va para el operativo de camp & Monitoring and Evaluation o 2023 C2-MIES-93 / “ADQUISICIÓN DE EQUIPOS INFORMÁTICOS PARA LA MEJORA EN EJECUCI Component 2: Technical Assi Single Stage - One E Under Imple ON DEL PROCESO DE EXCLU IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 114,456.16 0.00 2023-06-15 2023-06-01 2023-06-30 2023-08-11 2023-09-10 2023-10-15 2024-04-12 nvelope mentation SIONES E INCLUSIONES DE B & Monitoring and Evaluation ENEFICIARIOS DE LAS TRANS FERENCIAS MONETARIAS AD MINISTRADAS POR LA SANCC O” NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2-MIES-58 / CONTRATACIÓ Component 2: Technical Assi N DE OPERADORAS DE SERVI Open - Internationa Single Stage - One E IBRD / 89460 stance for Capacity Building Post Request for Bids 3,080,000.00 0.00 Canceled 2021-01-25 2021-03-11 2021-04-29 2021-05-26 2021-07-08 2022-07-08 CIOS INTEGRADOS DE INCLU l nvelope & Monitoring and Evaluation SIÓN ECONÓMICA C2-MIES-16 / Campaña de co municación que mitigue los e fectos de la Refocalizacion d Component 2: Technical Assi e los Nucleos Familiares en lo Single Stage - One E IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 900,000.00 0.00 Canceled 2020-01-30 2020-02-04 2020-03-18 2020-04-17 2020-05-12 2020-12-08 s Programas Sociales por la a nvelope & Monitoring and Evaluation plicación del nuevo Formulari o e indice del Registro Social- posibles tensiones provenien tes del cambio de legibilidad de los C2-MIES-INEC-1 / Contrataci ón del servicio de impresión Component 2: Technical Assi Request for Quota Single Stage - One E de stickers, requeridos para IBRD / 89460 stance for Capacity Building Post Open - National 1,983.91 1,960.00 Signed 2022-03-09 2022-04-06 2022-06-10 2022-04-21 tions nvelope el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-3 / Servicio de transporte en camionetas con conductor, Component 2: Technical Assi Single Stage - One E necesario para el desarrollo IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 202,507.20 466,715.20 Signed 2022-02-28 2022-03-11 2022-03-09 2022-03-11 2022-03-24 2022-03-25 2022-04-05 2022-04-06 2022-04-14 2022-04-29 2022-08-12 nvelope del & Monitoring and Evaluation operativo de campo de la Encuesta Nacional de Desnutrición Infantil C2-MIES-INEC-8 / Suministro s de impresión (materiales d Component 2: Technical Assi e impresión) y repuestos (rep Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 31,523.17 0.00 Canceled 2022-03-09 2022-04-12 2022-05-27 uestos y accesorios) para el tions nvelope & Monitoring and Evaluation desarrollo de las actividades de la Encuesta Nacional de D esnutrición Infantil Page 2 C2-MIES-INEC-12 / Contratac ión de 12 Encuestador - Antr Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple opometrista ENDI para el ope IBRD / 89460 stance for Capacity Building Post Open - National 29,728.82 0.00 2022-05-03 2022-06-15 2022-08-15 tions nvelope mentation rativo de campo de la Encues & Monitoring and Evaluation ta Nacional de Desnutrición I nfantil C2-MIES-INEC-14 / Contratac ión de 47 Encuestadores de Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple Enlistamiento para el operati IBRD / 89460 stance for Capacity Building Post Open - National 213,523.71 0.00 2022-03-04 2022-04-15 2022-08-15 tions nvelope mentation vo de campo de la Encuesta & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-15 / Contratac ión de 4 Operadores Cartogr Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple áficos de Enlistamiento para IBRD / 89460 stance for Capacity Building Post Open - National 13,224.96 0.00 2022-03-04 2022-04-15 2022-08-15 tions nvelope mentation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-16 / Contratac ión de 44 Revisores de contr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl ol de calidad ENDI para el op IBRD / 89460 stance for Capacity Building Post Open - National 67,020.80 0.00 2022-05-04 2022-06-15 2022-08-15 tions nvelope ementation erativo de campo de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil C2-MIES-INEC-17 / Contratac ión de 8 Revisores de control Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple de calidad de Enlistamiento p IBRD / 89460 stance for Capacity Building Post Open - National 24,371.20 0.00 2022-03-04 2022-04-15 2022-08-15 tions nvelope mentation ara el operativo de campo de & Monitoring and Evaluation la Encuesta Nacional de Desn utrición Infantil C2-MIES-INEC-13 / Contratac Component 2: Technical Assi ión de 24 Encuestadores END Request for Quota Single Stage - One E Under Imple IBRD / 89460 stance for Capacity Building Post Open - National 59,457.64 0.00 2022-05-03 2022-06-15 2022-08-15 I para el operativo de campo tions nvelope mentation & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-18 / Contratac ión de 12 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl erativo de campo ENDI para IBRD / 89460 stance for Capacity Building Post Open - National 31,287.86 0.00 2022-05-04 2022-06-15 2022-08-15 tions nvelope ementation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-19 / Contratac ión de 16 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple erativo de campo de Enlista IBRD / 89460 stance for Capacity Building Post Open - National 76,874.28 0.00 2022-03-04 2022-04-15 2022-08-15 tions nvelope mentation miento para el operativo de c & Monitoring and Evaluation ampo de la Encuesta Nacion al de Desnutrición Infantil C2-MIES-INEC-2 / Contrataci ón de una agencia de viajes Component 2: Technical Assi para la provisión de pasajes Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 19,756.80 0.00 Canceled 2022-03-09 2022-04-14 2022-04-12 2022-12-23 aéreos en rutas nacionales p tions nvelope & Monitoring and Evaluation ara el operativo de campo de la Encuesta Nacional de Desn utrición Infantil C2-MIES-INEC-2-2 / Contrata ción de una agencia de viaje Component 2: Technical Assi s para la provisión de pasaje Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 19,619.60 21,912.80 Signed 2022-05-26 2022-06-17 2022-06-29 2022-07-23 2022-12-30 s aéreos en rutas nacionales tions nvelope & Monitoring and Evaluation para el operativo de campo d e la Encuesta Nacional de De snutrición Infantil C2-MIES-INEC-21 / Servicio d e impresión de material infor Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple mativo y de trabajo a ser dist IBRD / 89460 stance for Capacity Building Post Open - National 7,506.29 0.00 2022-09-15 2022-10-24 2022-10-08 2022-11-08 tions nvelope mentation ribuido durante el levantamie & Monitoring and Evaluation nto de la Encuesta Nacional de Desnutrición Infantil C2-MIES-INEC-27 / Contratac ión de 16 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl erativo de campo de Enlista IBRD / 89460 stance for Capacity Building Post Open - National 70,265.96 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation miento para el operativo de c & Monitoring and Evaluation ampo de la Encuesta Nacion al de Desnutrición Infantil C2-MIES-INEC-28 / Contratac ión de 8 Operadores Cartogr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl áficos de Enlistamiento para IBRD / 89460 stance for Capacity Building Post Open - National 21,931.39 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-29 / Contratac ión de 8 Revisores de control Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl de calidad de Enlistamiento p IBRD / 89460 stance for Capacity Building Post Open - National 21,121.71 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation ara el operativo de campo de & Monitoring and Evaluation la Encuesta Nacional de Desn utrición Infantil C2-MIES-INEC-30 / Contratac ión de 12 Encuestador - Antr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl opometrista ENDI para el ope IBRD / 89460 stance for Capacity Building Post Open - National 53,924.86 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation rativo de campo de la Encues & Monitoring and Evaluation ta Nacional de Desnutrición I nfantil C2-MIES-INEC-31 / Contratac ión de 44 Revisores de contr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl ol de calidad ENDI para el op IBRD / 89460 stance for Capacity Building Post Open - National 122,871.47 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation erativo de campo de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil C2-MIES-INEC-32 / Contratac ión de 12 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl erativo de campo ENDI para IBRD / 89460 stance for Capacity Building Post Open - National 56,783.10 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-33 / Contratac Component 2: Technical Assi ión de 24 Encuestadores END Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 107,849.73 0.00 2022-09-13 2022-09-30 2022-12-30 I para el operativo de campo tions nvelope ementation & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-34 / Contratac ión de 47 Encuestadores de Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl Enlistamiento para el operati IBRD / 89460 stance for Capacity Building Post Open - National 195,226.15 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation vo de campo de la Encuesta & Monitoring and Evaluation Nacional de Desnutrición Infa ntil Page 3 C2-MIES-INEC-35 / Contratac Component 2: Technical Assi ión de 3 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 11,595.36 0.00 2022-09-13 2022-09-30 2022-12-30 e Campo 1 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-36 / Contratac Component 2: Technical Assi ión de 2 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 9,502.08 0.00 2022-09-13 2022-09-30 2022-12-30 e Campo 2 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-37 / Contratac Component 2: Technical Assi ión de 2 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 13,139.84 0.00 2022-09-13 2022-09-30 2022-12-30 e Campo 3 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-22 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi el desarrollo del operativo d IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 202,977.60 0.00 Canceled 2022-09-09 2022-09-13 2022-10-21 2022-12-31 e campo de la Encuesta Naci & Monitoring and Evaluation onal de Desnutrición Infantil, periodo: octubre-diciembre 2 022 C2-MIES-INEC-45 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi el desarrollo del operativo de Under Imple IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 53,155.20 0.00 2022-10-11 2022-10-11 2022-10-15 2022-10-17 2022-11-10 2022-12-31 campo de la Encuesta Nacion mentation & Monitoring and Evaluation al de Desnutrición Infantil, pe riodo: octubre-diciembre 202 2 (Planta Central - Quito - Enl istamiento y Encuesta) C2-MIES-INEC-46 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi el desarrollo del operativo de Under Imple IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 23,049.60 0.00 2022-10-11 2022-10-11 2022-10-15 2022-10-17 2022-11-10 2022-12-31 campo de la Encuesta Nacion mentation & Monitoring and Evaluation al de Desnutrición Infantil, pe riodo: octubre-diciembre 202 2 (Litoral - Guayaquil – Enlist amiento) C2-MIES-INEC-47 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi Under Imple el desarrollo del operativo de IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 18,816.00 0.00 2022-10-11 2022-10-11 2022-10-15 2022-10-17 2022-11-10 2022-12-31 mentation campo de la Encuesta Nacion & Monitoring and Evaluation al de Desnutrición Infantil, pe riodo: octubre-diciembre 202 2 (Litoral – Guayaquil – Encue sta) C2-MIES-INEC-48 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi el desarrollo del operativo de Under Imple IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 41,865.60 0.00 2022-10-11 2022-10-11 2022-10-15 2022-10-17 2022-11-10 2022-12-31 campo de la Encuesta Nacion mentation & Monitoring and Evaluation al de Desnutrición Infantil, pe riodo: octubre-diciembre 202 2 (Centro - Ambato – Enlista miento y Encuesta) C2-MIES-INEC-49 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi el desarrollo del operativo de Under Imple IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 41,865.60 0.00 2022-10-11 2022-10-11 2022-10-15 2022-10-17 2022-11-10 2022-12-31 campo de la Encuesta Nacion mentation & Monitoring and Evaluation al de Desnutrición Infantil, pe riodo: octubre-diciembre 202 2 (Sur - Cuenca – Enlistamien to y Encuesta) C2-MIES-INEC-50 / Contratac ión de una agencia de viaje p Component 2: Technical Assi ara la provisión de pasajes a Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 46,368.00 0.00 2022-11-25 2022-12-29 2023-12-29 éreos en rutas nacionales par tions nvelope ementation & Monitoring and Evaluation a el operativo de campo de l a Encuesta Nacional de Desn utrición Infantil año 2023 C2-MIES-INEC-51 / Contratac ión de 16 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl erativo de campo de Enlista IBRD / 89460 stance for Capacity Building Post Open - National 230,640.75 0.00 2022-11-15 2022-12-27 2023-12-28 tions nvelope ementation miento para el operativo de c & Monitoring and Evaluation ampo de la Encuesta Nacion al de Desnutrición Infantil C2-MIES-INEC-52 / Contratac ión de 8 Operadores Cartogr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl áficos de Enlistamiento para IBRD / 89460 stance for Capacity Building Post Open - National 79,358.72 0.00 2022-11-22 2022-12-30 2023-12-29 tions nvelope ementation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-53 / Contratac ión de 8 Revisores de control Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl de calidad de Enlistamiento p IBRD / 89460 stance for Capacity Building Post Open - National 73,122.56 0.00 2022-11-18 2022-12-28 2023-12-28 tions nvelope ementation ara el operativo de campo de & Monitoring and Evaluation la Encuesta Nacional de Desn utrición Infantil C2-MIES-INEC-54 / Contratac ión de 12 Encuestador - Antr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl opometrista ENDI para el ope IBRD / 89460 stance for Capacity Building Post Open - National 178,386.35 0.00 2022-11-23 2022-12-29 2023-12-29 tions nvelope ementation rativo de campo de la Encues & Monitoring and Evaluation ta Nacional de Desnutrición I nfantil C2-MIES-INEC-55 / Contratac ión de 44 Revisores de contr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl ol de calidad ENDI para el op IBRD / 89460 stance for Capacity Building Post Open - National 402,174.08 0.00 2022-11-23 2022-12-30 2023-12-28 tions nvelope ementation erativo de campo de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil C2-MIES-INEC-56 / Contratac ión de 12 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl erativo de campo ENDI para IBRD / 89460 stance for Capacity Building Post Open - National 187,740.59 0.00 2022-11-22 2022-12-30 2023-12-28 tions nvelope ementation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-57 / Contratac Component 2: Technical Assi ión de 24 Encuestadores END Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 356,772.70 0.00 2022-11-23 2022-12-29 2023-12-29 I para el operativo de campo tions nvelope ementation & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil Page 4 C2-MIES-INEC-58 / Contratac ión de 47 Encuestadores de Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl Enlistamiento para el operati IBRD / 89460 stance for Capacity Building Post Open - National 640,623.76 0.00 2022-11-23 2022-12-29 2023-12-29 tions nvelope ementation vo de campo de la Encuesta & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-59 / Contratac Component 2: Technical Assi ión de 3 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 39,758.88 0.00 2022-11-22 2022-12-30 2023-12-29 e Campo 1 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-60 / Contratac Component 2: Technical Assi ión de 2 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 32,580.80 0.00 2022-11-22 2022-12-30 2023-12-29 e Campo 2 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-61 / Contratac Component 2: Technical Assi ión de 2 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 45,053.12 0.00 2022-11-22 2022-12-30 2023-12-29 e Campo 3 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-62 / Contratac ión de 40 técnicos especializ Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl ados y servicios profesionale IBRD / 89460 stance for Capacity Building Post Open - National 99,455.36 0.00 2022-11-22 2022-12-30 2023-12-29 tions nvelope ementation s para implementar el proyec & Monitoring and Evaluation to de la Encuesta Nacional d e Desnutrición Infantil C2-MIES-81 / Servicio de tra nsporte en camionetas con c Component 2: Technical Assi onductor, necesario para el d Single Stage - One E Under Imple IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 798,004.40 0.00 2022-11-29 2022-12-09 2022-11-30 2022-12-10 2022-12-15 2022-12-20 2022-12-29 2023-11-29 esarrollo del operativo de ca nvelope mentation & Monitoring and Evaluation mpo de la Encuesta Nacional de Desnutrición Infantil, peri odo: enero-noviembre 2023 C2-MIES-INEC-63 / Servicio d e transporte necesario para e Component 2: Technical Assi l desarrollo del operativo de Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 55,080.00 0.00 2023-03-15 2023-03-20 2023-05-01 2023-05-31 2023-07-05 2024-01-01 campo de la Encuesta Nacion nvelope ementation & Monitoring and Evaluation al de Desnutrición Infantil par a la provincia de Galápagos CS-MIES-INEC-64 / Servicio d e transporte en camionetas c Component 2: Technical Assi on conductor, necesario para Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 65,365.00 0.00 2023-10-15 2023-10-20 2023-12-01 2023-12-31 2024-02-04 2024-08-02 el desarrollo del operativo d nvelope ementation & Monitoring and Evaluation e campo de la Encuesta Naci onal de Desnutrición Infantil, periodo diciembre 2023 C2-MIES-INEC-83 / Mantenim Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl iento de equipos informático IBRD / 89460 stance for Capacity Building Post Open - National 2,240.00 0.00 2023-04-20 2023-06-15 2023-12-12 tions nvelope ementation s & Monitoring and Evaluation C2-MIES-INEC-80 / Contratac ión de 4 Supervisores de ope Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl rativo de campo ENDI para el IBRD / 89460 stance for Capacity Building Post Open - National 45,824.00 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation operativo de campo de la En & Monitoring and Evaluation cuesta Nacional de Desnutric ión Infantil C2-MIES-INEC-75 / Contratac ión de 3 Encuestadores - Antr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl opometristas ENDI para el op IBRD / 89460 stance for Capacity Building Post Open - National 19,846.80 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation erativo de campo de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil (Galápagos) C2-MIES-INEC-76 / Contratac ión de 3 Supervisores de ope Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl rativo de campo ENDI para el IBRD / 89460 stance for Capacity Building Post Open - National 21,099.60 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation operativo de campo de la En & Monitoring and Evaluation cuesta Nacional de Desnutric ión Infantil (Galápagos) C2-MIES-INEC-81 / Contratac Component 2: Technical Assi ión de 1 Analista Técnico DA Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 12,120.00 0.00 2023-03-20 2023-05-15 2023-11-11 RH 2 para la Encuesta Nacio tions nvelope ementation & Monitoring and Evaluation nal de Desnutrición Infantil C2-MIES-INEC-78 / Contratac Component 2: Technical Assi ión de 8 Encuestadores ENDI Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 87,008.00 0.00 2023-03-20 2023-05-15 2023-11-11 para el operativo de campo d tions nvelope ementation & Monitoring and Evaluation e la Encuesta Nacional de De snutrición Infantil C2-MIES-INEC-82 / Contratac Component 2: Technical Assi ión de 1 Analista Técnico de Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 16,760.00 0.00 2023-03-20 2023-05-15 2023-11-11 Campo 3 para la Encuesta N tions nvelope ementation & Monitoring and Evaluation acional de Desnutrición Infan til C2-MIES-INEC-79 / Contratac ión de 4 Encuestadores - Antr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl opometristas ENDI para el op IBRD / 89460 stance for Capacity Building Post Open - National 43,504.00 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation erativo de campo de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil Component 2: Technical Assi C2-MIES-INEC-70 / Personal Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 14,792.12 0.00 2023-10-20 2023-12-15 2024-06-12 Civil- Técnicos de Campo tions nvelope ementation & Monitoring and Evaluation C2-MIES-INEC-74 / Contratac ión de 6 Encuestadores ENDI Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl para el operativo de campo d IBRD / 89460 stance for Capacity Building Post Open - National 39,693.60 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation e la Encuesta Nacional de De & Monitoring and Evaluation snutrición Infantil (Galápago s) C2-MIES-INEC-65 / Contratac ión de una agencia de viaje p Component 2: Technical Assi ara la provisión de pasajes a Single Stage - One E IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 26,556.70 0.00 Canceled 2023-03-15 2023-04-06 2023-03-20 2023-04-06 2023-05-01 2023-05-31 2023-07-05 2024-01-01 éreos en rutas nacionales par nvelope & Monitoring and Evaluation a el operativo de campo de l a Encuesta Nacional de Desn utrición Infantil C2-MIES-INEC-84 / Contratac Component 2: Technical Assi ión de 1 Auxiliar de logística Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 5,062.50 0.00 2023-05-20 2023-07-15 2023-12-31 y procesos de calidad ENDI p tions nvelope ementation & Monitoring and Evaluation ara la Encuesta Nacional de Desnutrición Infantil Page 5 C2-MIES-INEC-86 / Contratac ión de una agencia de viaje p ara la provisión de pasajes a Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl éreos en rutas nacionales par IBRD / 89460 stance for Capacity Building Post Open - National 26,556.70 0.00 2023-05-24 2023-07-19 2024-01-15 tions nvelope ementation a el operativo de campo de l & Monitoring and Evaluation a Encuesta Nacional de Desnutrición Infa ntil año 2023 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2-MIES-13 / Diseño e imple Component 2: Technical Assi Quality And Cost- Open - Internationa mentación de un sistema int IBRD / 89460 stance for Capacity Building Prior 646,000.00 0.00 Canceled 2020-02-10 2020-02-24 2020-03-27 2020-05-18 2020-05-29 2020-06-23 2020-08-11 2021-08-11 Based Selection l egrado de quejas y reclamos & Monitoring and Evaluation C2-MIES-18 / Investigación y Component 2: Technical Assi desarrollo de las encuestas p Quality And Cost- Open - Internationa IBRD / 89460 stance for Capacity Building Prior 1,200,000.00 0.00 Canceled 2020-01-17 2020-01-31 2020-03-02 2020-04-23 2020-05-11 2020-06-08 2020-07-20 2021-12-02 ara monitoreo de los resultad Based Selection l & Monitoring and Evaluation os del proyecto Multipropósit o/ENEMDU C2-MIES-19 / Contratación d Component 2: Technical Assi e Verificación Técnica de Cu Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 100,000.00 54,830.40 Completed 2020-01-17 2020-06-30 2020-01-31 2020-07-10 2020-02-18 2020-08-11 2020-03-11 2020-08-31 2020-03-18 2020-09-15 2020-04-03 2020-09-29 2020-05-06 2020-10-27 2020-12-22 2021-01-01 mplimiento de DLIs para el Pr Based Selection & Monitoring and Evaluation oyecto Red de Protección So cial - MIES 2020 C2-MIES-20 / Contratación d e Verificación Técnica de Cu Component 2: Technical Assi Quality And Cost- mplimiento de DLIs para el Pr IBRD / 89460 stance for Capacity Building Post Open - National 220,000.00 0.00 Canceled 2020-11-20 2020-12-07 2020-12-26 2021-01-17 2021-01-24 2021-02-10 2021-03-13 2023-01-02 Based Selection oyecto Red de Protección So & Monitoring and Evaluation cial - MIES 2020, 2021, 2022 C2-MIES-22 / Contratación d Component 2: Technical Assi el Servicio de Auditoría Finan Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 220,000.00 0.00 Canceled 2020-11-23 2020-11-27 2020-12-18 2021-01-13 2021-01-22 2021-02-10 2021-03-17 2022-11-07 ciera para el Proyecto Red de Based Selection & Monitoring and Evaluation Protección Social - MIES 2020 , 2021, 2022 C2-MIES-46 / Elaboración de Component 2: Technical Assi Planes de Participación de Pu Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 123,572.96 0.00 Canceled 2020-03-27 2020-04-10 2020-04-17 2020-05-14 2020-05-21 2020-05-28 2020-06-18 2020-07-06 2020-11-03 eblos y Nacionalidades Indíg Based Selection & Monitoring and Evaluation enas, Afroecuatorianos y Mo ntubios (PPNIAM) C2-MIES-48 / Elaboración de Component 2: Technical Assi Planes de Participación de Pu Quality And Cost- Under Implement IBRD / 89460 stance for Capacity Building Post Open - National 181,724.82 0.00 2020-06-18 2020-06-30 2020-07-05 2020-08-21 2020-07-09 2020-09-23 2020-07-30 2020-10-15 2020-08-12 2020-11-16 2020-08-24 2020-12-01 2020-09-11 2021-01-09 eblos y Nacionalidades Indíg Based Selection ation & Monitoring and Evaluation enas, Afroecuatorianos y Mo ntubios (PPNIAM) C2-MIES-17 / Diseño del mod elo de gestión apalancado en instrumentos jurídicos, meto Component 2: Technical Assi dológicos, operativos y tecno Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 106,388.80 0.00 Canceled 2020-09-16 2020-09-30 2020-10-09 2020-10-22 2020-10-30 2020-11-13 2020-11-27 2020-12-15 2020-12-30 2021-04-30 lógicos para el seguimiento n Based Selection & Monitoring and Evaluation ominal de la población objeti vo de misión ternura, orienta do a la prevención de la desn utrición infantil C2-MIES-43 / GESTIÓN DE C ERTIFICACIÓN DE CALIDAD E STADÍSTICA DE OPERACIONE S ESTADÍSTICASBASADAS EN Component 2: Technical Assi REGISTROS ADMINISTRATIVO Quality And Cost- Under Implement IBRD / 89460 stance for Capacity Building Post 60,814.77 0.00 2020-11-11 2020-11-19 2020-11-25 2021-01-18 2020-12-16 2021-01-11 2021-01-22 2021-02-08 2021-03-02 2021-06-30 S DE SERVICIOS DE ATENCIÓ Based Selection ation & Monitoring and Evaluation N A PERSONAS CON DISCAPA CIDAD, DESARROLLO INFANT IL INTEGRAL, ATENCIÓN A PE RSONAS ADULTAS MAYORES, Y MOVILIDAD SOCIAL AS C2-MIES-21 / Contratación d Component 2: Technical Assi el Servicio de Auditoría Finan Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 39,144.00 0.00 Canceled 2020-12-04 2020-12-21 2020-12-18 2021-01-06 2021-01-15 2021-01-25 2021-02-09 2021-03-01 2021-04-30 ciera Período 2019 y 2020 pa Based Selection & Monitoring and Evaluation ra el Proyecto Red de Protecc ión Social – MIES C2-MIES-59 / Auditoría de Es tados Financieros de Propósit o Especial del Proyecto Red d Component 2: Technical Assi e Protección Social - MIES, fin Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 39,144.00 0.00 Canceled 2021-01-18 2021-01-15 2021-02-05 2021-02-26 2021-04-16 2021-03-19 2021-05-03 2021-04-08 2021-05-06 2021-04-26 2021-05-15 2021-06-29 anciado parcialmente a travé Based Selection & Monitoring and Evaluation s del Acuerdo Legal de Prést amo Nro. BIRF 8946-EC, por el Período 22 de julio 2019 al 31 de diciembre del 2020 C2-MIES-10 / Diseño e Imple Component 2: Technical Assi Quality And Cost- mentación de plataforma par IBRD / 89460 stance for Capacity Building Post Open - National 150,000.00 0.00 Canceled 2020-01-27 2020-02-03 2020-02-27 2020-03-16 2020-03-17 2020-04-13 2020-05-22 2021-02-16 Based Selection a registrar información de co & Monitoring and Evaluation operantes Component 2: Technical Assi C2-MIES-3 / Diseño de la Est Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 58,000.00 0.00 Canceled 2020-01-17 2020-01-20 2020-02-14 2020-03-09 2020-03-10 2020-03-29 2020-05-03 2020-08-01 rategia de Tecnología Social Based Selection & Monitoring and Evaluation C2-MIES-2 / Diseño e Implem Component 2: Technical Assi entación de la plataforma pa Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 412,500.00 0.00 Canceled 2020-02-10 2020-02-12 2020-02-25 2020-03-15 2020-03-16 2020-04-15 2020-06-08 2021-03-05 ra el registro de los servicios Based Selection & Monitoring and Evaluation de Inclusión Económica C2-MIES-5 / Diseño e implem Component 2: Technical Assi Quality And Cost- entación de un piloto de micr IBRD / 89460 stance for Capacity Building Post Open - National 71,500.00 0.00 Canceled 2020-01-17 2020-01-20 2020-02-14 2020-02-28 2020-03-02 2020-03-27 2020-05-09 2020-10-06 Based Selection oredes de emprendimientos & Monitoring and Evaluation populares C2-MIES-6 / Diseño de los Se rvicios de Fortalecimiento de Component 2: Technical Assi Capacidades y Acceso a Merc Quality And Cost- Open - Internationa IBRD / 89460 stance for Capacity Building Prior 664,469.00 0.00 Canceled 2020-01-17 2020-01-21 2020-02-24 2020-03-21 2020-03-28 2020-04-16 2020-05-04 2020-11-30 ados e Implementación de u Based Selection l & Monitoring and Evaluation n Piloto para Fortalecimiento de Capacidades Productivas en varios distritos C2-MIES-1 / Diseño e Implem Component 2: Technical Assi Quality And Cost- Open - Internationa entación de un Piloto de Mod IBRD / 89460 stance for Capacity Building Post 440,500.00 0.00 Canceled 2020-01-13 2020-01-26 2020-02-24 2020-04-10 2020-04-13 2020-05-25 2020-07-06 2020-12-03 Based Selection l alidades de CDH en varios di & Monitoring and Evaluation stritos Page 6 C2-MIES-9 / Diseño e Implem entación de aplicativos en Ta blet para el registro de la inf Component 2: Technical Assi ormación de las visitas domic Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 150,000.00 0.00 Canceled 2020-03-02 2020-03-16 2020-05-20 2020-07-06 2020-07-20 2020-08-10 2020-09-14 2021-03-13 iliarias realizadas por las edu Based Selection & Monitoring and Evaluation cadoras del CNH y los técnic os de acompañamiento famili ar del BDH; y, desarrollo de i nterfaces para sincronizar la infor C2-MIES-14 / Consultoría par a identificar, a través de map Component 2: Technical Assi as territoriales, la capacidad Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 300,000.00 0.00 Canceled 2020-01-17 2020-01-20 2020-02-12 2020-03-11 2020-03-13 2020-04-01 2020-04-18 2020-10-15 de oferta de servicios de DIT Based Selection & Monitoring and Evaluation y atención al adulto mayor p ertenecientes a hogares extr emadamente pobres C2-MIES-15 / Estudio de sost Component 2: Technical Assi Quality And Cost- enibilidad financiera del prog IBRD / 89460 stance for Capacity Building Post Open - National 80,000.00 0.00 Canceled 2020-02-11 2020-02-25 2020-03-17 2020-04-03 2020-04-14 2020-05-01 2020-06-05 2020-12-02 Based Selection rama Mis Mejores Años y PA & Monitoring and Evaluation M. C2-MIES-62 / AUDITORIA DE ESTADOS FINANCIEROS DE P ROPOSITO ESPECIAL DEL PR OYECTO RED DE PROTECCIÓ Component 2: Technical Assi Consultant Qualifi N SOCIAL – MIES, FINANCIAD IBRD / 89460 stance for Capacity Building Post Limited 36,708.00 36,624.00 Completed 2021-07-23 2021-08-06 2021-08-18 2021-09-14 2021-09-08 2021-10-04 2021-10-20 2021-10-07 2021-11-20 2021-12-04 cation Selection O PARCIALMENTE A TRAVES & Monitoring and Evaluation DEL ACUERDO LEGAL DE PRÉ STAMO NRO. BIRF 8946-EC, P OR EL PERIODO DEL 06 DE A GOSTO DE 2019 AL 31 DE DI CIEMBRE DE 2020. C2-MIES-24 / Evaluación de i Component 2: Technical Assi Quality And Cost- Open - Internationa mpacto de la estrategia de in IBRD / 89460 stance for Capacity Building Post 392,000.00 0.00 Canceled 2022-05-04 2022-05-23 2022-06-17 2022-07-07 2022-07-15 2022-07-29 2022-08-14 2022-12-31 Based Selection l clusión económica & Monitoring and Evaluation C2-MIES-89 / SERVICIO DE C ONSULTORÍA PARA LA FORM ULACIÓN DE UNA PROPUEST Component 2: Technical Assi A DE PLAN PARA LA MEJORA Quality And Cost- Under Implement IBRD / 89460 stance for Capacity Building Post Open - National 46,300.80 0.00 2023-04-28 2023-04-28 2023-05-15 2023-06-22 2023-06-19 2023-07-17 2023-08-09 2023-08-23 2023-09-29 2024-01-27 DE LAS INTERVENCIONES DE Based Selection ation & Monitoring and Evaluation LA POLÍTICA DE PROTECCIÓN SOCIAL, BAJO CRITERIOS DE PERTINENCIA CULTURAL Y TE RRITORIAL, PARA LA POBLACI ÓN INDÍGENA. C2-MIES-90 / EVALUACIÓN D E RESULTADOS DE LOS SERV Component 2: Technical Assi ICIOS DE DESARROLLO INFA Quality And Cost- Under Implement IBRD / 89460 stance for Capacity Building Post Open - National 64,377.45 0.00 2023-04-28 2023-04-26 2023-05-15 2023-06-19 2023-07-17 2023-08-09 2023-08-23 2023-09-29 2024-01-27 NTIL ENMARCADOS EN EL PR Based Selection ation & Monitoring and Evaluation OGRAMA “MISIÓN TERNURA” PARA EL PERÍODO 2019 - 202 1 C2-MIES-91 / EVALUACIÓN D Component 2: Technical Assi E RESULTADOS DEL PROGRA Quality And Cost- Under Implement IBRD / 89460 stance for Capacity Building Post Open - National 68,046.55 0.00 2023-04-28 2023-04-27 2023-05-15 2023-06-20 2023-06-19 2023-07-17 2023-08-09 2023-08-23 2023-09-29 2024-01-27 MA “MIS MEJORES AÑOS” PA Based Selection ation & Monitoring and Evaluation RA EL PERÍODO 2019 - 2021 C2-MIES-92 / ASISTENCIA TÉ CNICA PARA LA ELABORACIÓ Component 2: Technical Assi Quality And Cost- Under Implement N DEL PLAN NACIONAL PARA IBRD / 89460 stance for Capacity Building Post Open - National 196,214.25 0.00 2023-05-02 2023-04-28 2023-05-19 2023-06-26 2023-06-23 2023-07-21 2023-08-14 2023-08-30 2023-10-06 2024-04-13 Based Selection ation LA PROTECCIÓN INTEGRAL D & Monitoring and Evaluation E DERECHOS DE LAS PERSO NAS ADULTAS MAYORES INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2-MIES-25 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Open 25,189.56 18,144.00 Completed 2020-01-17 2020-03-09 2020-02-18 2020-05-20 2020-02-25 2020-06-12 2020-03-25 2020-07-16 2020-12-20 2021-01-01 ant Selection alista en Protección Social / U & Monitoring and Evaluation GP C2-MIES-26 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 25,189.56 0.00 Terminated 2020-01-03 2020-02-13 2020-01-20 2020-04-14 2020-01-27 2020-04-16 2020-01-31 2020-05-05 2020-03-16 ant Selection alista en Comunicación & Monitoring and Evaluation C2-MIES-27 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Open 30,487.71 29,927.52 Completed 2020-01-06 2020-01-27 2020-02-03 2020-04-09 2020-02-24 2020-04-13 2020-03-02 2020-04-21 2020-12-27 2021-01-01 ant Selection alista Legal / UGP & Monitoring and Evaluation C2-MIES-28 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Open 30,487.71 21,168.00 Completed 2020-01-06 2020-01-27 2020-01-29 2020-02-14 2020-02-26 2020-04-22 2020-03-02 2020-05-23 2020-12-27 2021-01-01 ant Selection alista Financiero / UGP & Monitoring and Evaluation C2-MIES-29 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Open 30,487.71 24,192.00 Completed 2020-01-06 2020-01-27 2020-01-29 2020-04-14 2020-02-26 2020-04-16 2020-03-02 2020-05-05 2020-12-27 2021-01-01 ant Selection alista de Adquisiciones & Monitoring and Evaluation C2-MIES-31 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Open 30,487.71 0.00 Canceled 2020-01-06 2020-01-29 2020-02-24 2020-03-02 2020-12-27 ant Selection alista en Planificación y Monit & Monitoring and Evaluation oreo / UGP C2-MIES-32 / Contratación d e Consultor Individual Especi Component 2: Technical Assi Individual Consult alista en Evaluación de Impa IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2020-01-17 2020-02-11 2020-03-09 2020-03-13 2020-12-08 ant Selection cto (Diseños de los procesos & Monitoring and Evaluation de evaluación de impacto) C2-MIES-33 / Contratación d Component 2: Technical Assi e Consultor Individual Especi Individual Consult IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2020-01-17 2020-02-10 2020-02-24 2020-03-13 2020-12-08 alista en Estadística y Proces ant Selection & Monitoring and Evaluation amiento de Datos (Cumplimi ento de Indicadores) C2-MIES-34 / Contratación d e Consultor Individual Especi Component 2: Technical Assi alista en Sistemas de Inform Individual Consult IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2020-01-17 2020-02-10 2020-03-09 2020-03-16 2020-12-11 ación y Reportería de Datos ( ant Selection & Monitoring and Evaluation Fortalecimiento del InfoMies para permitir interoperabilida d) C2-MIES-36 / Contratación d Component 2: Technical Assi e Consultor Individual Especi Individual Consult IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2020-01-17 2020-02-07 2020-02-23 2020-03-13 2020-12-08 alista de enlace técnico con l ant Selection & Monitoring and Evaluation a Subsecretaría de Familia Page 7 C2-MIES-38 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Analist IBRD / 89460 stance for Capacity Building Post Open 19,800.00 0.00 Canceled 2020-07-16 2020-08-18 2020-09-02 2020-09-23 2021-07-20 ant Selection a de Adquisiciones & Monitoring and Evaluation C2-MIES-41 / Contratación d Component 2: Technical Assi e Consultor Individual para C Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 29,124.26 0.00 Canceled 2020-01-06 2020-01-08 2020-01-14 2020-02-07 2020-04-07 onsultas Jurídicas Específicas ant Selection & Monitoring and Evaluation para el Proyecto Red de Prot ección Social C2-MIES-45 / Consultoría par Component 2: Technical Assi Individual Consult a la Aplicación de una Consul IBRD / 89460 stance for Capacity Building Post Limited 50,000.00 0.00 Canceled 2020-01-13 2020-01-14 2020-02-04 2020-03-10 2020-06-08 ant Selection ta para los Pueblos y Naciona & Monitoring and Evaluation lidades C2-MIES-47 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Limited 11,995.31 8,568.08 Completed 2020-06-30 2020-07-08 2020-07-13 2020-07-22 2020-07-23 2020-07-31 2020-08-10 2020-08-19 2020-12-30 2021-01-01 ant Selection alista Social & Monitoring and Evaluation C2-MIES-49 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,788.75 21,591.56 Completed 2020-12-07 2020-12-12 2020-12-28 2021-03-29 2021-01-04 2021-03-30 2021-01-06 2021-04-08 2021-12-31 2021-12-18 ant Selection alista en Protección Social pe & Monitoring and Evaluation ríodo 2021 C2-MIES-50 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,788.75 0.00 Under Review 2020-12-07 2021-03-02 2020-12-28 2021-01-04 2021-01-06 2021-12-31 ant Selection alista Legal período 2021 & Monitoring and Evaluation C2-MIES-51 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,788.75 21,591.56 Completed 2020-12-07 2020-12-12 2020-12-28 2021-03-29 2021-01-04 2021-03-30 2021-01-06 2021-04-08 2021-12-31 2021-12-28 ant Selection alista Financiero período 202 & Monitoring and Evaluation 1 C2-MIES-52 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,788.75 11,995.31 Terminated 2020-12-07 2020-12-12 2020-12-28 2021-03-29 2021-01-04 2021-03-30 2021-01-06 2021-04-08 2021-12-31 ant Selection alista de Adquisiciones perío & Monitoring and Evaluation do 2021 C2-MIES-53 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,788.75 21,591.56 Completed 2020-12-07 2020-12-12 2020-12-28 2021-03-29 2021-01-04 2021-03-30 2021-01-06 2021-04-08 2021-12-31 2021-12-18 ant Selection alista Social período 2021 & Monitoring and Evaluation C2-MIES-39 / Contratación d Component 2: Technical Assi e Consultor Indovidual Especi Individual Consult IBRD / 89460 stance for Capacity Building Post Open 22,500.00 0.00 Canceled 2020-03-16 2020-03-17 2020-04-06 2020-05-20 2020-04-09 2020-04-20 2020-12-31 alista Social y de Comunicaci ant Selection & Monitoring and Evaluation ones para el Proyecto Red de Protección Social C2-MIES-57 / CONTRATACIÓ N DE UN CONSULTOR INDIVI DUAL PARA FORTALECER Y B Component 2: Technical Assi RINDAR APOYO EN LOS SERV Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 43,792.00 0.00 Canceled 2020-09-21 2020-09-29 2020-11-12 2020-12-02 2022-04-30 ICIOS QUE PRESTA LA DIREC ant Selection & Monitoring and Evaluation CIÓN DE IMPULSO JOVEN DE LA SUBSECRETARÍA DE EMPR ENDIMIENTOS Y GESTIÓN DE L CONOCIMIENTO C2-MIES-56 / CONTRATACIÓ N DE UN CONSULTOR INDIVI Component 2: Technical Assi DUAL PARA FORTALECER Y B Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 43,792.00 0.00 Canceled 2020-09-21 2020-09-29 2020-11-12 2020-12-02 2022-04-30 RINDAR APOYO EN LOS SERV ant Selection & Monitoring and Evaluation ICIOS QUE PRESTA LA DIREC CIÓN DE GESTIÓN DEL CONO CIMIENTO C2-MIES-55 / CONTRATACIÓ N DE UN CONSULTOR INDIVI Component 2: Technical Assi Individual Consult DUAL PARA FORTALECER Y B IBRD / 89460 stance for Capacity Building Post Limited 43,792.00 0.00 Canceled 2020-09-21 2020-09-29 2020-11-12 2020-12-02 2022-04-30 ant Selection RINDAR APOYO EN LOS SERV & Monitoring and Evaluation ICIOS QUE PRESTA LA DIREC CIÓN DE EMPRENDIMIENTOS C2-MIES-54 / CONTRATACIÓ N DE UN CONSULTOR INDIVI Component 2: Technical Assi DUAL PARA FORTALECER Y B Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 43,792.00 0.00 Canceled 2020-09-21 2020-09-29 2020-11-12 2020-12-02 2022-04-30 RINDAR APOYO EN LOS SERV ant Selection & Monitoring and Evaluation ICIOS QUE PRESTA LA DIREC CIÓN DE DESARROLLO DE M ERCADOS C2-MIES-37 / Contratación d e Consultor Individual Especi Component 2: Technical Assi Individual Consult alista de enlace técnico con l IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2020-01-17 2020-02-07 2020-03-09 2020-03-13 2020-12-08 ant Selection a Subsecretaría de Inclusión & Monitoring and Evaluation Económica y Movilidad Social C2-MIES-64 / CONTRATACIÓ N DE UN CONSULTOR INDIVI Component 2: Technical Assi Individual Consult DUAL ESPECIALISTA EN ADQ IBRD / 89460 stance for Capacity Building Prior Direct 9,596.25 0.00 Canceled 2021-09-07 2021-10-18 2021-09-20 2021-09-24 2021-09-30 2021-12-30 ant Selection UISICIONES PARA & Monitoring and Evaluation EL PROYECTO “RED DE PROT ECCIÓN SOCIAL” PERÍODO 20 21 C2-MIES-65 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,789.87 28,788.75 Signed 2021-11-12 2021-11-29 2021-11-29 2021-12-15 2021-12-10 2021-12-20 2021-12-27 2021-12-29 2022-12-23 ant Selection alista en Protección Social pe & Monitoring and Evaluation ríodo 2022 C2-MIES-67 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,789.87 162,377.91 Signed 2021-11-12 2021-11-29 2021-11-29 2021-12-15 2021-12-10 2021-12-20 2021-12-27 2021-12-29 2022-12-23 ant Selection alista Financiero período 202 & Monitoring and Evaluation 2 C2-MIES-68 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,789.87 28,788.75 Signed 2021-11-12 2021-11-29 2021-11-29 2021-12-15 2021-12-10 2021-12-20 2021-12-27 2021-12-29 2022-12-23 ant Selection alista de Adquisiciones perío & Monitoring and Evaluation do 2022 C2-MIES-69 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,789.87 28,788.75 Signed 2021-11-12 2021-11-29 2021-11-29 2021-12-15 2021-12-10 2021-12-20 2021-12-27 2021-12-29 2022-12-23 ant Selection alista Social período 2022 & Monitoring and Evaluation C2-MIES-70 / SERVICIO DE V ERIFICACION TECNICA DE CU Component 2: Technical Assi MPLIMIENTO DE DLI PARA EL IBRD / 89460 stance for Capacity Building Post Direct Selection Direct 181,863.27 162,377.91 Completed 2021-11-30 2021-11-04 2021-12-15 2021-12-15 2021-12-31 2021-12-30 2022-04-30 2022-06-25 PROYECTO "RED DE PROTEC & Monitoring and Evaluation CION SOCIAL" PERIODO 2020 -2021 C2-MIES-71 / AUDITORIA DE LOS ESTADOS FINANCIEROS DE PROPOSITO ESPECIAL DEL PROYECTO RED DE PROTECC Component 2: Technical Assi ION SOCIAL - MIES, FINANCIA IBRD / 89460 stance for Capacity Building Post Direct Selection Direct 30,240.00 29,120.00 Signed 2021-11-30 2022-01-13 2021-12-15 2022-03-04 2021-12-31 2022-05-10 2022-02-14 DO PARCIALMENTE A TRAVES & Monitoring and Evaluation DEL ACUERDO LEGAL DE PRE STAMO NRO. BIRF 8946-EC - POR EL PERÍODO 1 DE ENER O A 31 DE DICIEMBRE DE 20 21 Page 8 C2-MIES-72 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult L ESPECIALISTA DE EVALUACI IBRD / 89460 stance for Capacity Building Post Direct 16,793.44 14,394.37 Signed 2022-05-20 2022-05-12 2022-06-10 2022-06-17 2022-06-15 2022-06-21 2022-06-27 2022-06-25 2022-12-23 ant Selection ÓN DE IMPACTO PARA EL PR & Monitoring and Evaluation OYECTO “RED DE PROTECCI ÓN SOCIAL” PERÍODO 2022 C2-MIES-INEC-4 / Servicios d e consultoría para el procesa miento y análisis de los resul Component 2: Technical Assi tados de la Encuesta de Des Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 11,760.00 0.00 Canceled 2022-07-29 2022-07-15 2022-08-08 2022-09-09 2022-10-14 2022-12-31 nutrición Infantil en el marco ant Selection & Monitoring and Evaluation del rol del INEC ante el Decre to Presidencial 1211 y las res ponsabilidades establecidas en la estrategia Ecuador Crec e Sin Desn C2-MIES-INEC-5 / Servicios d e consultoría para la elabora ción de la metodología de int Component 2: Technical Assi egración de registros admini Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 11,760.00 0.00 Canceled 2022-07-29 2022-07-15 2022-08-08 2022-08-25 2022-09-23 2022-12-31 strativos para el monitoreo d ant Selection & Monitoring and Evaluation e la desnutrición crónica infa ntil-DCI, en el marco del rol d el INEC ante el Decreto Presi dencial 1211 y las responsab ilidades es C2-MIES-INEC-26 / Contratac ión de servicios de consultorí a para para el seguimiento té cnico y validación de informa Component 2: Technical Assi Individual Consult Pending Impleme ción sobre prestaciones mate IBRD / 89460 stance for Capacity Building Post Direct - National 7,198.30 0.00 2022-09-16 2022-09-19 2022-09-24 2022-09-26 2022-12-30 ant Selection ntation rno-infantiles, datos antropo & Monitoring and Evaluation métricos, hemoglobina, segu ridad alimentaria y calidad d e agua, en el marco de la En cuesta Nacional C2-MIES-73 / FORMULACIÓN DE UNA PROPUESTA DE PLAN Component 2: Technical Assi PARA LA MEJORA DE LAS INT Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Post Open - National 25,540.48 0.00 2022-10-07 2022-10-31 2022-11-09 2022-12-08 2022-11-16 2022-12-15 2023-04-14 ERVENCIONES DE LA POLÍTIC ant Selection ation & Monitoring and Evaluation A DE PROTECCIÓN SOCIAL D ESDE UNA PERSPECTIVA DE GÉNERO C2-MIES-74 / AUDITORIA DE LOS ESTADOS FINANCIEROS DE PROPOSITO ESPECIAL DEL PROYECTO RED DE PROTECC Component 2: Technical Assi Under Implement IÓN SOCIAL – MIES, FINANCIA IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 21,500.00 0.00 2022-10-21 2022-10-31 2022-11-14 2022-12-29 2023-02-17 ation DO PARCIALMENTE A TRAVES & Monitoring and Evaluation DEL ACUERDO LEGAL DE PRÉ STAMO NRO. BIRF 8946-EC, P ARA EL PERÍODO DEL 01 DE ENERO AL 31 DE DICIEMBRE DE 2022 C2-MIES-75 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult Under Implement L ESPECIALISTA SOCIAL PARA IBRD / 89460 stance for Capacity Building Post Direct - National 55,178.44 0.00 2022-11-02 2022-11-22 2022-11-30 2022-12-12 2022-12-27 2024-11-26 ant Selection ation EL PROYECTO “RED DE PRO & Monitoring and Evaluation TECCIÓN SOCIAL” PERÍODO 2 023 - 2024 C2-MIES-78 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult Under Implement L ESPECIALISTA FINANCIERO IBRD / 89460 stance for Capacity Building Post Direct - National 49,266.46 0.00 2022-11-02 2022-11-22 2022-11-30 2022-12-21 2022-12-27 2024-11-28 ant Selection ation PARA EL PROYECTO “RED DE & Monitoring and Evaluation PROTECCIÓN SOCIAL” PERÍO DO 2023 - 2024 C2-MIES-INEC-5-1 / Servicios de consultoría para la elabor ación de la metodología de in Component 2: Technical Assi tegración de registros admini Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Post Limited 28,790.96 0.00 2022-11-18 2022-11-24 2022-11-23 2022-11-30 2022-12-29 2023-12-29 strativos para el monitoreo d ant Selection ation & Monitoring and Evaluation e la desnutrición crónica infa ntil-DCI, en el marco del rol d el INEC ante el Decreto Presi dencial 1211 y las responsab ilidades es C2-MIES-INEC-4-1 / Servicios de consultoría para el proces amiento y análisis de los res Component 2: Technical Assi ultados de la Encuesta de De Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Post Limited 28,790.96 0.00 2022-11-11 2022-11-24 2022-11-30 2022-12-14 2022-12-29 2023-12-29 snutrición Infantil en el marc ant Selection ation & Monitoring and Evaluation o del rol del INEC ante el Dec reto Presidencial 1211 y las r esponsabilidades establecida s en la estrategia Ecuador Cr ece Sin Desn C2-MIES-INEC-23 / Contratac ión de servicios de consultorí Component 2: Technical Assi a para la ejecución de los pro Individual Consult Pending Impleme IBRD / 89460 stance for Capacity Building Post Limited 31,188.90 0.00 2022-11-11 2022-11-25 2022-12-22 2022-12-29 2023-12-29 cesos de adquisición para la i ant Selection ntation & Monitoring and Evaluation mplementación del proyecto de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-24 / Contratac ión de servicios de consultorí Component 2: Technical Assi a para la ejecución de los pro Individual Consult Pending Impleme IBRD / 89460 stance for Capacity Building Post Limited 31,188.90 0.00 2022-11-18 2022-11-25 2022-12-26 2022-12-29 2023-12-28 cesos financieros en el marc ant Selection ntation & Monitoring and Evaluation o de la implementación del p royecto de la Encuesta Nacio nal de Desnutrición Infantil C2-MIES-INEC-25 / Contratac ión de servicios de consultorí Component 2: Technical Assi Individual Consult Pending Impleme a para la Coordinación de la i IBRD / 89460 stance for Capacity Building Post Direct - National 31,188.90 0.00 2022-11-18 2022-12-01 2022-12-16 2022-12-29 2023-12-29 ant Selection ntation mplementación del proyecto & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil C2-MIES-76 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi L ESPECIALISTA DE PROTECC Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Post Direct - National 49,266.46 0.00 2022-11-02 2022-11-22 2022-11-30 2022-12-12 2022-12-27 2024-11-26 IÓN SOCIAL PARA EL PROYEC ant Selection ation & Monitoring and Evaluation TO “RED DE PROTECCIÓN SO CIAL” PERÍODO 2023 - 2024 C2-MIES-80 / Servicio de Ver Component 2: Technical Assi ificación Técnica de cumplimi Under Implement IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 46,546.04 0.00 2022-11-22 2022-11-29 2022-12-07 2022-12-30 2023-04-29 ento de DLI 16, para el Proye ation & Monitoring and Evaluation cto “Red de Protección Social ”, periodo 2022 C2-MIES-84 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi L ESPECIALISTA DE EVALUACI Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Post Direct - National 47,124.44 0.00 2023-01-25 2023-01-17 2023-01-30 2023-02-06 2023-02-07 2024-11-20 ÓN DE IMPACTO PARA EL PR ant Selection ation & Monitoring and Evaluation OYECTO “RED DE PROTECCI ÓN SOCIAL” PERÍODO 2023 - 2024 Page 9 C2-MIES-82 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult L ESPECIALISTA DE ADQUISIC IBRD / 89460 stance for Capacity Building Prior Direct - National 49,266.46 0.00 Canceled 2023-01-13 2023-02-16 2023-01-30 2023-03-06 2023-02-06 2023-02-07 2024-11-27 ant Selection IONES PARA EL PROYECTO “R & Monitoring and Evaluation ED DE PROTECCIÓN SOCIAL” PERÍODO 2023 - 2024 C2-MIES-83 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult L ESPECIALISTA LEGAL PARA IBRD / 89460 stance for Capacity Building Post Direct - National 49,266.46 0.00 Canceled 2023-01-13 2023-01-13 2023-01-30 2023-02-06 2023-02-14 2024-12-04 ant Selection EL PROYECTO “RED DE PROT & Monitoring and Evaluation ECCIÓN SOCIAL” PERÍODO 20 23 - 2024 C2-MIES-85 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult Under Implement L ESPECIALISTA DE ADQUISIC IBRD / 89460 stance for Capacity Building Prior Direct - National 47,124.44 0.00 2023-03-21 2023-03-31 2023-03-31 2023-04-17 2023-04-21 2023-05-09 2023-05-26 2023-11-22 ant Selection ation IONES PARA EL PROYECTO "R & Monitoring and Evaluation ED DE PROTECCIÓN SOCIAL" PERÍODO 2023-2024 C2-MIES-35 / Contratación d Component 2: Technical Assi e Consultor Individual Especi Individual Consult IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2022-03-09 2022-04-04 2022-04-18 2022-05-16 2022-12-28 alista de enlace técnico con l ant Selection & Monitoring and Evaluation a Subsecretaría de Aseguram iento No Contributivo C2-MIES-66 / Contratación d Component 2: Technical Assi e consultor individual Especi Individual Consult IBRD / 89460 stance for Capacity Building Post Direct 28,789.87 0.00 Canceled 2021-12-16 2021-12-22 2021-12-27 2021-12-31 2022-12-27 alista Legal para el Proyecto ant Selection & Monitoring and Evaluation Red de Protección Social Peri odo 2022 C2-MIES-77 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult L ESPECIALISTA DE ADQUISIC IBRD / 89460 stance for Capacity Building Post Direct - National 49,266.46 0.00 Canceled 2022-11-02 2022-11-22 2022-11-30 2022-12-14 2022-12-27 2024-11-28 ant Selection IONES PARA EL PROYECTO “R & Monitoring and Evaluation ED DE PROTECCIÓN SOCIAL” PERÍODO 2023 - 2024 C2-MIES-86 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult L ESPECIALISTA LEGAL PARA IBRD / 89460 stance for Capacity Building Post Direct - National 47,124.44 0.00 Canceled 2023-03-29 2023-03-27 2023-04-08 2023-04-29 2023-06-03 2023-11-30 ant Selection EL PROYECTO "RED DE PROT & Monitoring and Evaluation ECCIÓN SOCIAL" PERÍODO 20 23-2024 C2-MIES-87 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi L DE APOYO A LA EJECUCIÓN Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Prior Open - National 9,800.00 0.00 2023-04-14 2023-05-08 2023-05-29 2023-06-09 2023-06-05 2023-06-28 2023-06-19 2023-12-22 DE LAS ADQUISICIONES DEL ant Selection ation & Monitoring and Evaluation PROYECTO RED DE PROTECC IÓN SOCIAL – PERÍODO 2023 C2-MIES-88 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult Under Implement L ESPECIALISTA LEGAL PARA IBRD / 89460 stance for Capacity Building Post Direct - National 47,124.44 0.00 2023-04-24 2023-04-12 2023-05-04 2023-05-25 2023-06-29 2023-12-26 ant Selection ation EL PROYECTO “RED DE PROT & Monitoring and Evaluation ECCIÓN SOCIAL” PERÍODO 20 23 – 2024 C2-MIES-INEC-67 / Contratac ión de servicios de consultorí a para para el seguimiento té cnico y validación de informa Component 2: Technical Assi ción sobre prestaciones mate IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 28,789.70 0.00 Canceled 2023-04-15 2023-04-25 2023-06-29 2023-12-26 rno-infantiles, datos antropo & Monitoring and Evaluation métricos, hemoglobina, segu ridad alimentaria y calidad d e agua, en el marco de la En cuesta Nacional C2-MIES-INEC-66 / Servicios de consultoría para la elabor ación de la metodología de in Component 2: Technical Assi tegración de registros admini Individual Consult Pending Impleme IBRD / 89460 stance for Capacity Building Post Direct - National 11,995.28 0.00 2023-07-01 2023-07-11 2023-08-01 2023-09-05 2024-03-03 strativos para el monitoreo d ant Selection ntation & Monitoring and Evaluation e la desnutrición crónica infa ntil-DCI, en el marco del rol d el INEC ante el Decreto Presi dencial 1211 y las responsab ilidades es Page 10 PROCUREMENT PLAN (Textual Part) Project information: Dominica Geothermal Risk Mitigation Project(P162149) Project Implementation agency: Dominica Geothermal Development Company Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. PROCUREMENT Dominica : Dominica Geothermal Risk Mitigation Project PLAN General Information Country: Dominica 2019-05-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162149 GPN Date: 2019-04-10 Project Name: Dominica Geothermal Risk Mitigation Project Loan / Credit No: IDA / 63760, TF / A9531, TF / A9532 Dominica Geothermal Development Company Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned DM-DGDC-109147-CW-RFB / DEVELOPMENT OF DOMESTI Open - Internationa Single Stage - One E 32,500,000.0 2020-04-0 EPC Contract for a nominal 7 IDA / 63760 C GEOTHERMAL POWER GEN Prior Request for Bids 0.00 Canceled 2019-04-04 2019-07-19 2019-05-13 2019-09-12 2019-08-05 2019-11-20 2019-09-06 2020-02-12 2019-10-11 l nvelope 0 8 MWe geothermal power plant ERATION CAPACITY (SGPP) DM-DGDC-209335-CW-RFB / DEVELOPMENT OF DOMESTI Open - Internationa Single Stage - One E 12,000,000.0 Under Revie 2021-10-0 Integrated drilling services fo IDA / 63760 C GEOTHERMAL POWER GEN Prior Request for Bids 0.00 2020-12-18 2021-01-27 2020-12-23 2021-03-26 2021-02-03 2021-04-06 2021-03-05 2021-04-09 l nvelope 0 w 6 r reinjection and production ERATION CAPACITY (SGPP) wells. DM-DGDC-209336-CW-RFB / DEVELOPMENT OF DOMESTI Single Stage - One E 2,751,448.5 2021-10-2 Civil Works for Reinjection W TF / A9531 C GEOTHERMAL POWER GEN Post Request for Bids Open - National 1,000,000.00 Signed 2021-01-03 2021-02-12 2021-01-08 2021-02-12 2021-02-19 2021-03-25 2021-03-21 2021-04-06 2021-04-25 2021-05-02 nvelope 4 2 ell and Production Well. ERATION CAPACITY (SGPP) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-DGDC-209337-GO-RFQ / DEVELOPMENT OF DOMESTI Single Stage - One E Purchase of Master Valves fo TF / A9531 C GEOTHERMAL POWER GEN Post Request for Bids Limited 250,000.00 194,098.00 Signed 2020-12-16 2021-01-13 2020-12-16 2021-01-08 2021-01-27 2021-02-12 2021-02-26 2021-03-03 2021-04-02 2021-03-19 2021-09-29 nvelope r reinjection and production ERATION CAPACITY (SGPP) wells. DM-DGDC-209338-GO-RFQ / DEVELOPMENT OF DOMESTI Open - Internationa Single Stage - One E Drill casing for geothermal w TF / A9531 C GEOTHERMAL POWER GEN Post Request for Bids 600,000.00 683,694.00 Completed 2020-12-16 2021-01-13 2020-12-16 2021-01-14 2021-01-27 2021-02-19 2021-02-26 2021-03-08 2021-04-02 2021-03-23 2021-09-29 2021-09-22 l nvelope ells. ERATION CAPACITY (SGPP) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-DGDC-109149-NC-RFB / CONTINGENT FINANCING IN Open - Internationa Single Stage - One E IDA / 63760 Prior Request for Bids 9,000,000.00 0.00 Canceled 2019-07-01 2019-09-02 2019-11-18 2019-12-18 2020-01-22 2020-07-20 Integrated Drilling Services C AID OF ADDITIONAL DRILLIN l nvelope ontract G CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-DGDC-109150-CS-QCBS TECHNICAL ASSITANCE FOR / LGPP feasibility, environme ADVANCING LGPP TO DEVEL Quality And Cost- Open - Internationa Pending Impleme IDA / 63760 Prior 1,000,000.00 0.00 2020-03-02 2020-03-23 2020-05-06 2020-06-03 2020-07-03 2020-08-07 2020-09-11 2021-09-11 ntal impact and geothermal s OPMENT STATUS AND SOLIC Based Selection l ntation ervices ITING PRIVATE SECTOR INVE STMENT DEVELOPMENT OF DOMESTI TF0A9531 / Owner's Enginee Consultant Qualifi TF / A9531 C GEOTHERMAL POWER GEN Post Limited 300,000.00 299,690.00 Signed 2020-12-17 2020-12-11 2020-12-31 2020-12-16 2021-01-30 2021-01-18 2021-03-06 2021-02-15 2021-09-02 r for Drilling Services cation Selection ERATION CAPACITY (SGPP) DM-DGDC-221918-CS-QCBS / Owner’s Engineer for constr DEVELOPMENT OF DOMESTI uction of transmission lines a Quality And Cost- Open - Internationa IDA / 63760 C GEOTHERMAL POWER GEN Prior 2,000,000.00 2,095,595.00 Signed 2021-02-26 2021-03-09 2021-03-19 2021-04-07 2021-05-02 2021-05-05 2021-05-30 2021-06-25 2021-06-29 2021-09-21 2021-08-03 2021-12-23 2021-09-07 2022-01-30 2022-09-07 nd substations (conceptual d Based Selection l ERATION CAPACITY (SGPP) esign, bidding document, pro curement support and super vision) DM-DGDC-213499-CS-QCBS DEVELOPMENT OF DOMESTI Quality And Cost- Open - Internationa / ESIA/ESMP/RAP for Transmis IDA / 63760 C GEOTHERMAL POWER GEN Post 700,000.00 448,185.75 Signed 2021-03-05 2021-04-07 2021-03-26 2021-04-07 2021-05-09 2021-05-13 2021-06-06 2021-06-24 2021-07-06 2021-09-14 2021-08-10 2021-10-26 2021-09-14 2022-01-25 2022-09-14 Based Selection l sion Lines and Substations ERATION CAPACITY (SGPP) TECHNICAL ASSITANCE FOR DM-DGDC-307973-CS-LCS / ADVANCING LGPP TO DEVEL Least Cost Selecti Open - Internationa Financial Audit 2020/2021 to TF / A9532 Post 30,000.00 0.00 Signed 2022-08-08 2022-08-16 2022-08-29 2022-08-16 2022-09-19 2022-09-21 2022-10-19 2022-10-31 2022-10-26 2022-11-07 2022-11-12 2022-11-16 2022-12-10 2023-01-09 OPMENT STATUS AND SOLIC on l 2021/2022 ITING PRIVATE SECTOR INVE STMENT INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-DGDC-217694-CS-CDS / DEVELOPMENT OF DOMESTI Under Implement Legal Services for Transmissi IDA / 63760 C GEOTHERMAL POWER GEN Post Direct Selection Direct 60,000.00 0.00 2021-02-03 2021-02-09 2021-02-13 2021-04-19 2021-05-19 ation on Line Agreement with DOM ERATION CAPACITY (SGPP) LEC. DM-DGDC-333603-CS-INDV / DEVELOPMENT OF DOMESTI Individual Consult Environmental Assessment T IDA / 63760 C GEOTHERMAL POWER GEN Post Limited 100,000.00 0.00 Canceled 2022-12-27 2023-01-01 2023-01-22 2023-02-26 2023-08-25 ant Selection ransmission Lines and Substa ERATION CAPACITY (SGPP) tions DM-DGDC-333611-CS-INDV / DEVELOPMENT OF DOMESTI Individual Consult Open - Internationa Social Assessment and RAP T IDA / 63760 C GEOTHERMAL POWER GEN Post 120,000.00 0.00 Signed 2022-12-23 2022-12-24 2023-02-06 2023-01-20 2023-02-27 2023-02-27 2023-04-03 2023-09-30 ant Selection l ransmission Lines and Substa ERATION CAPACITY (SGPP) tions DM-DGDC-333709-CS-INDV / DEVELOPMENT OF DOMESTI Individual Consult Open - Internationa Environmental Assessment T IDA / 63760 C GEOTHERMAL POWER GEN Post 100,000.00 0.00 Signed 2022-12-27 2022-12-24 2023-02-10 2023-01-20 2023-03-03 2023-02-27 2023-04-07 2023-10-04 ant Selection l ransmission Lines and Substa ERATION CAPACITY (SGPP) tions-2 Page 1 TECHNICAL ASSITANCE FOR DM-DGDC-339357-CS-CDS / ADVANCING LGPP TO DEVEL Direct - Internation Under Implement Technical Analysis of 33 kV/6 IDA / 63760 Post Direct Selection 44,000.00 0.00 2023-02-10 2023-03-03 2023-02-20 2023-03-09 2023-03-28 2023-09-24 OPMENT STATUS AND SOLIC al ation 9 kV Transmission Network ITING PRIVATE SECTOR INVE STMENT DM-DGDC-362042-CS-CDS / TECHNICAL ASSITANCE FOR Transmission Network Adviso ADVANCING LGPP TO DEVEL Direct - Internation Under Implement TF / A9532 Post Direct Selection 30,000.00 0.00 2023-05-17 2023-05-18 2023-05-27 2023-05-16 2023-07-31 2023-10-29 ry Service for preparation of OPMENT STATUS AND SOLIC al ation PPSD. ITING PRIVATE SECTOR INVE STMENT Page 2 PROCUREMENT PLAN (Textual Part) Project information: Accelerating and Strengthening Skills for Economic Transformation Project) (ASSET), P167506 Project Implementation agency: Directorate of Technical Education (DTE), Technical and Madrasah Education Division (TMED), Ministry of Education (MoE) Date of the Procurement Plan: March 23, 2022 Period covered by this Procurement Plan: March 2022 to March 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (dated July 2016, revised November 2017, August 2018 and November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules 2008, as amended in August 2009) , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions : a) e-GP system of the country for national competitive bidding (NCB) shall be followed using Standard/Model Procurement documents satisfactory to the Bank b) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; c) Bids should be submitted and opened in public in one location immediately after the deadline for submission; d) Lottery in award of contracts shall not be allowed; e) Bidders’ qualification/experience requirement shall be mandatory f) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. Procurement Responsibility: Bangladesh Bureau of Statistics (BBS) is the implementing agency (IA) who will be responsible for all procurements. Procurement Threshold Bank-financed all contracts at or above the thresholds set out in the below table 1 are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) High Substant Modera Low Type of procurement risk ial risk te risk risk Works (including turnkey, supply & installation of plant and equipment, 5 10 15 20 and PPP) Goods, information technology and 1.5 2 4 6 non-consulting services Consultants: firms 0.5 1 2 4 Consultants: individuals 0.2 0.3 0.4 0.5 Irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: a. procurement processes involving contract negotiations as, described in paragraphs 6.34-36 of Section VI of the Procurement Regulation for Borrowers; b. competitive dialogue; c. sustainable procurement; and d. best and final offer. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract, including all taxes and duties payable under the contract. PROCUREMENT Bangladesh : Accelerating and Strengthening Skills for Economic Transformation PLAN General Information Country: Bangladesh 2022-04-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167506 GPN Date: 2022-04-18 Project Name: Accelerating and Strengthening Skills for Economic Transformation Loan / Credit No: IDA / 68740 Technical and Madrasah Education Division Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure Component 3: Capacity Dev ment Document - BD-TMED-317150-CW-RFB / elopment, Project Managem Single Stage - One E Under Imple 2023-11-0 IDA / 68740 Post Request for Bids Open - National 1 Envelope proce 174,400.00 0.00 2023-02-28 2023-03-23 2023-03-21 2023-03-27 2023-05-02 2023-04-18 2023-07-01 2023-08-05 Office refurbishment of DTE ent, Social Marketing and M nvelope mentation 3 ss (Non Bank-SPD onitoring & Evaluation ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-TMED-286889-GO-RFB / Component 3: Capacity Dev Procurement of Desktop Com elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 66,176.47 0.00 Signed 2022-04-05 2022-05-24 2022-04-10 2022-05-22 2022-06-13 2022-06-21 2022-07-03 2022-07-26 2023-01-22 puter, UPS, Laptop Computer ent, Social Marketing and M nvelope , Photocopier, Printer,Scanne onitoring & Evaluation r, DSLR Camera,etc BD-TMED-317151-GO-RFB / Component 1: Transforming Establishment of Internet & T Formal Skills Development f Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 17,450.00 0.00 2022-10-10 2022-10-25 2022-11-04 2022-12-04 2023-01-08 2023-07-07 elecom Network of the Projec or Future of Work, Inclusiven nvelope ementation t Office ess, and Resilience BD-TMED-317152-GO-RFB / Component 3: Capacity Dev Supply & installation of Offic elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 16,280.00 0.00 Signed 2022-10-10 2022-11-30 2022-10-15 2022-11-26 2022-12-15 2022-12-26 2023-01-08 2023-01-30 2023-03-01 e Equipment (Photocopier, Pr ent, Social Marketing and M nvelope inter & Scanner) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317153-GO-RFB / elopment, Project Managem Single Stage - One E Pending Impl Supply and installation of PA IDA / 68740 Post Request for Bids Open - National 11,630.00 0.00 2022-10-11 2022-10-16 2022-11-27 2022-12-27 2023-01-31 2023-03-02 ent, Social Marketing and M nvelope ementation and multimedia system onitoring & Evaluation G2B / Supply and Installatio Component 3: Capacity Dev n of Laptop, Intercom System elopment, Project Managem Single Stage - One E Under Imple IDA / 68740 Post Request for Bids Open - National 32,500.00 0.00 2023-05-21 2023-06-12 2023-05-26 2023-06-12 2023-06-16 2023-07-31 2023-09-04 2023-12-03 and LAN for PMU including all ent, Social Marketing and M nvelope mentation accessories onitoring & Evaluation Component 3: Capacity Dev G5A / Supply of Furniture an elopment, Project Managem Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 232,550.00 0.00 2023-05-21 2023-05-26 2023-06-16 2023-07-31 2023-09-04 2024-01-02 d Fixtures for PMU office ent, Social Marketing and M nvelope ementation onitoring & Evaluation Component 3: Capacity Dev G11A / Supply of Computer elopment, Project Managem Request for Quota Single Stage - One E Under Imple IDA / 68740 Post Open - National 2,325.00 0.00 2023-05-26 2023-06-19 2023-06-22 2023-07-13 Consumables ent, Social Marketing and M tions nvelope mentation onitoring & Evaluation Component 3: Capacity Dev G15A / Supply of Stationarie elopment, Project Managem Request for Quota Single Stage - One E Pending Impl IDA / 68740 Post Open - National 1,400.00 0.00 2023-06-02 2023-06-29 2023-07-20 s for PMU office ent, Social Marketing and M tions nvelope ementation onitoring & Evaluation G57 / Supply of Materials for Component 1: Transforming Seminar, Workshops and Con Formal Skills Development f Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 232,550.00 0.00 2023-05-28 2023-06-02 2023-06-30 2023-07-30 2023-09-10 2025-09-09 ferences under framework co or Future of Work, Inclusiven nvelope ementation ntract ess, and Resilience G59 / Supply of Project Mana Component 3: Capacity Dev gement Information System elopment, Project Managem Single Stage - One E Under Imple IDA / 68740 Post Request for Bids Open - National 286,000.00 0.00 2023-05-28 2023-05-18 2023-06-02 2023-05-21 2023-06-04 2023-06-21 2023-08-03 2023-09-07 2023-12-06 Software with 04 year opera ent, Social Marketing and M nvelope mentation tional and maintenance supp onitoring & Evaluation ort Component 3: Capacity Dev BD-TMED-286891-GO-RFB / elopment, Project Managem Single Stage - One E Supply of Accounts and other IDA / 68740 Post Request for Bids Open - National 12,941.18 0.00 Canceled 2022-05-03 2022-05-08 2022-06-19 2022-07-19 2022-08-23 2023-02-19 ent, Social Marketing and M nvelope Software onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286890-GO-RFB / elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 35,294.12 0.00 Canceled 2022-04-12 2022-04-17 2022-05-29 2022-06-28 2022-08-02 2023-01-29 Supply of furniture for PMU ent, Social Marketing and M nvelope onitoring & Evaluation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Transforming NCS1A / Selection of Event Formal Skills Development f Single Stage - One E Pending Impl Management firm for Semina IDA / 68740 Post Request for Bids Open - National 55,800.00 0.00 2023-05-28 2023-06-02 2023-06-30 2023-08-29 2023-10-03 2024-03-31 or Future of Work, Inclusiven nvelope ementation rs and Workshops ess, and Resilience CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 BD-TMED-286611-CS-QCBS / Selection of firm/ institution f Component 1: Transforming or organizing seminars and w Formal Skills Development f Quality And Cost- orkshops for TTIs (1), Partner IDA / 68740 Post Open - National 228,235.29 0.00 Canceled 2022-04-03 2022-04-24 2022-06-07 2022-07-05 2022-08-04 2022-09-08 2022-10-13 2023-10-13 or Future of Work, Inclusiven Based Selection organizations (1), RPL for em ess, and Resilience ployers and workers (2) and DTE (1), project launching ce remony (1) BD-TMED-286628-CS-QCBS / Component 3: Capacity Dev Selection of Consultant for R elopment, Project Managem Quality And Cost- apid Assessment and follow- IDA / 68740 Post Open - National 117,647.06 0.00 Canceled 2022-04-20 2022-05-11 2022-06-24 2022-07-22 2022-08-21 2022-09-25 2022-10-30 2023-10-30 ent, Social Marketing and M Based Selection up on Diploma Students by D onitoring & Evaluation TE (1), Demand and Gap Ana lysis by BTEB (1) Component 3: Capacity Dev BD-TMED-286635-CS-QCBS / elopment, Project Managem Quality And Cost- Survey and Studies by BMET IDA / 68740 Post Open - National 235,294.12 0.00 Canceled 2022-04-27 2022-05-18 2022-07-01 2022-07-29 2022-08-28 2022-10-02 2022-11-06 2023-11-06 ent, Social Marketing and M Based Selection (2), NSDA (1), DTE (1) onitoring & Evaluation BD-TMED-286641-CS-FBS / S Component 3: Capacity Dev election of Consultant for TV elopment, Project Managem Fixed Budget Sele Pending Impleme IDA / 68740 Post Open - National 29,411.76 0.00 2022-04-10 2022-05-01 2022-06-14 2022-07-12 2022-08-11 2022-09-15 2022-10-20 2023-10-20 C production (1), Radio Ad pr ent, Social Marketing and M ction ntation oduction (2) onitoring & Evaluation BD-TMED-286888-CS-QCBS / Component 3: Capacity Dev Selection of Consulting Firm f elopment, Project Managem Quality And Cost- IDA / 68740 Post Open - National 174,117.65 0.00 Canceled 2022-04-24 2022-05-15 2022-06-28 2022-07-26 2022-08-25 2022-09-29 2022-11-03 2023-11-03 or Competency Standard Dev ent, Social Marketing and M Based Selection elopment for BTEB (12), BME onitoring & Evaluation T (40), S51 / Selection of Consultant for Demand and Gap Analysi Component 3: Capacity Dev s under BTEB: Analyzing the elopment, Project Managem Consultant Qualifi Skills and Competency Gaps IDA / 68740 Post Open - National 58,000.00 0.00 Under Review 2023-03-01 2023-03-23 2023-03-22 2023-05-05 2023-06-23 2023-08-04 2024-01-31 ent, Social Marketing and M cation Selection of the Selected Diploma in En onitoring & Evaluation gineering Courses Running U nder the Bangladesh Technic al Education Board S55A / Selection of Consulta nt for Survey and Studies un Component 3: Capacity Dev der BTEB on Analyzing Weak elopment, Project Managem Quality And Cost- IDA / 68740 Post Open - National 93,000.00 0.00 Under Review 2023-03-01 2023-03-23 2023-03-22 2023-05-05 2023-06-30 2023-07-30 2023-09-03 2023-10-15 2024-04-12 nesses, Prospects, and Effect ent, Social Marketing and M Based Selection iveness of Industrial Attachm onitoring & Evaluation ent of Diploma in Engineerin g Courses Running S59A / Selection of Consultin Component 3: Capacity Dev g firm for Surveys and Studie elopment, Project Managem Consultant Qualifi IDA / 68740 Post Open - National 58,000.00 0.00 Under Review 2023-03-07 2023-03-23 2023-03-28 2023-05-11 2023-06-22 2023-08-03 2024-01-30 s under NSDA (Sector: Creati ent, Social Marketing and M cation Selection ve Media) onitoring & Evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Capacity Dev BD-TMED-286652-CS-INDV / elopment, Project Managem Individual Consult Selection of Financial Manag IDA / 68740 Prior Open 352,941.18 0.00 Signed 2022-04-03 2022-04-18 2022-05-22 2022-09-21 2022-06-12 2022-10-24 2022-07-17 2023-01-13 ent, Social Marketing and M ant Selection ement Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286655-CS-INDV / elopment, Project Managem Individual Consult Selection of Junior Financial IDA / 68740 Post Open 197,647.06 0.00 Signed 2022-04-03 2022-04-16 2022-05-22 2023-02-23 2022-06-12 2023-02-23 2022-07-17 2023-01-13 ent, Social Marketing and M ant Selection Management Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286658-CS-INDV / elopment, Project Managem Individual Consult Selection of Procurement Spe IDA / 68740 Prior Open 364,705.88 0.00 Signed 2022-04-04 2022-04-17 2022-05-23 2022-09-21 2022-06-13 2022-10-27 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection cialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286660-CS-INDV / elopment, Project Managem Individual Consult Selection of Junior Procureme IDA / 68740 Prior Open 218,823.53 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2023-02-23 2022-06-13 2023-03-28 2022-07-18 2023-05-02 2023-01-14 ent, Social Marketing and M ant Selection nt Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286661-CS-INDV / elopment, Project Managem Individual Consult Selection of IDG Managemen IDA / 68740 Prior Open 317,647.06 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2022-09-21 2022-06-13 2022-10-25 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection t Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286883-CS-INDV / elopment, Project Managem Individual Consult Selection of ICT and MIS Spec IDA / 68740 Prior Open 282,352.94 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2022-09-21 2022-06-13 2022-10-25 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection ialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286885-CS-INDV / elopment, Project Managem Individual Consult Under Implement Selection of E&S safeguard S IDA / 68740 Prior Open 235,294.12 0.00 2022-04-28 2022-08-07 2022-06-16 2022-07-07 2022-08-11 2023-02-07 ent, Social Marketing and M ant Selection ation pecialist (1) onitoring & Evaluation BD-TMED-316744-CS-INDV / Component 3: Capacity Dev Selection of TVET & Industry elopment, Project Managem Individual Consult Under Implement IDA / 68740 Prior Open - National 310,000.00 0.00 2022-09-27 2022-11-07 2022-11-15 2022-12-06 2023-01-10 2025-01-09 Development Management S ent, Social Marketing and M ant Selection ation pecialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286886-CS-INDV / elopment, Project Managem Individual Consult Pending Impleme Selection of Short Term Tech IDA / 68740 Prior Open - National 350,000.00 0.00 2022-09-27 2022-11-15 2022-12-06 2023-01-10 2023-07-09 ent, Social Marketing and M ant Selection ntation nical Specialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317145-CS-INDV / elopment, Project Managem Individual Consult Selection of Monitoring & Eva IDA / 68740 Prior Open - National 590,000.00 0.00 Under Review 2022-09-30 2022-11-07 2022-11-18 2022-12-09 2023-01-13 2025-01-12 ent, Social Marketing and M ant Selection luation Specialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317147-CS-INDV / elopment, Project Managem Individual Consult Selection of Skills Training Sp IDA / 68740 Prior Open - National 310,000.00 0.00 Under Review 2022-10-05 2022-11-07 2022-11-23 2022-12-14 2023-01-18 2025-01-07 ent, Social Marketing and M ant Selection ecialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317148-CS-INDV / elopment, Project Managem Individual Consult Under Implement Selection of Communication IDA / 68740 Prior Open - National 310,000.00 0.00 2022-10-05 2022-11-07 2022-11-23 2022-12-14 2023-01-18 2025-01-17 ent, Social Marketing and M ant Selection ation Speciaist onitoring & Evaluation Page 2 Component 3: Capacity Dev S39B / Selection of IDG Spec elopment, Project Managem Individual Consult IDA / 68740 Post Limited 34,800.00 0.00 Under Review 2023-06-08 2023-06-06 2023-06-13 2023-07-04 2023-08-15 2024-02-11 ialist (Health) ent, Social Marketing and M ant Selection onitoring & Evaluation Page 3 PROCUREMENT PLAN (Textual Part) Project information: West African Power Pool, Ghana, Cote d’Ivoire, WAPP Ghana Cote d-Ivoire Power Interconnection Project (P178923) Project Implementation agency: West African Power Pool (WAPP) Date of the Procurement Plan: March 8, 2023 Period covered by this Procurement Plan: March 2023 – Dec 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] PROCUREMENT Western and Central Africa : WAPP Ghana-Cote d'Ivoire Interconnection Project PLAN General Information Country: Western and Central Africa 2023-03-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178923 GPN Date: Project Name: WAPP Ghana-Cote d'Ivoire Interconnection Project Loan / Credit No: / , IDA / V4680 WEST AFRICAN POWER POOL Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WAPP-348040-CS-QCBS / Update/preparation of feasibi lity studies, safeguards instru Quality And Cost- Open - Internationa Under Implement / Prior 4,000,000.00 0.00 2023-03-10 2023-03-16 2023-03-17 2023-03-17 2023-04-20 2023-05-09 2023-06-01 2023-06-15 2023-07-16 2023-08-20 2025-01-05 ments and bidding document Based Selection l ation s related to the construction of the Ghana-Côte d’Ivoire In terconnection INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WAPP-348052-CS-CDS / D evelopment and Implementa Direct - Internation Pending Impleme / Post Direct Selection 500,000.00 0.00 2023-04-02 2023-04-26 2023-06-30 2023-12-27 tion of Grid Code Gradual Co al ntation mpliance Framework (CESI) BJ-WAPP-348057-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Operation Planning Engineer ant Selection l ntation s N.1 BJ-WAPP-348069-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Operation Planning Engineer ant Selection l ntation s N.2 BJ-WAPP-348072-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Operation Planning Engineer ant Selection l ntation s N.3 BJ-WAPP-348093-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 DTS/EMS Engineer ant Selection l ntation BJ-WAPP-348095-CS-INDV / P Individual Consult Open - Internationa Pending Impleme ower System Data Base Man / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 ant Selection l ntation agement Engineer BJ-WAPP-348096-CS-INDV / P Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 ower System Data Analytics ant Selection l ntation Engineer BJ-WAPP-348102-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Market Regulation Officer ant Selection l ntation BJ-WAPP-348103-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Market Operation Officer N.1 ant Selection l ntation BJ-WAPP-348107-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Market Operation Officer N.2 ant Selection l ntation BJ-WAPP-348110-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 SCADA Database Specialist ant Selection l ntation BJ-WAPP-361659-CS-CDS / C Direct - Internation Under Implement onsultancy Services for Devel IDA / V4680 Post Direct Selection 250,000.00 0.00 2023-05-22 2023-05-23 2023-06-15 2023-05-24 2023-08-19 2024-08-13 al ation opment of Transitional Provis ions Framework Page 1 PLAN DE PASSATION DE MARCHÉS Information sur le Projet : Emprunteur/Bénéficiaire République Togolaise Ministère Responsable Nom du Projet Identification P172769 Agence d’exécution du Projet : [A insérer] Date du plan de passation des marchés : [A indiquer] Période couverte par ce plan de passation des marchés : [A indiquer] Date d’approbation par la Banque du plan de passation de marchés : [A indiquer] Date de publication de l’Avis Général de Passation des Marchés : [A indiquer] Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System) : Elevé Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Novembre 2020) (“Règlement de Passation des Marchés”), le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la loi No. 2009-013 du 30 juin 2009 relative aux Marchés Publics et Délégation de Service Public, le Décret Nº 2009-277/PR du 11 novembre 2009 portant Code des Marchés Publics et Délégation de Service Public, et les textes d’application y afférents, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : - Le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/les proposants présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection e l’audit ; - Le droit de la Banque d’examiner le dossier et les activités de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés Travaux ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés ne s’applique pas. Autres informations pertinentes sur la passation des marchés : Néant I. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Juillet 2016, révisé en Novembre 2017. Catégories de marchés Montants Observations estimatifs des contrats en millions de dollars américains Travaux (incluant clé à main, Fourniture et Installation, et les >= 5 Partenariat Public - Privé -PPP) Biens, Système d’Information et de Services autres que les >= 1,5 Services intellectuels Contrats à Travaux passer par (incluant clé à >= 5 entente main, directe Fourniture et Les justifications de Installation, et l’entente directe les Partenariat devront être jointes et Public - Privé - approuvées avec PPM PPP) Biens, Système d’Information et de Services >= 1,5 autres que les Services intellectuels 2. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : FOURNITURES ET SERVICES AUTRE QUE LES SERVICES DE CONSULTANTS TRAVAUX (US$ équivalent) (US$ équivalent) AOI AON DC AOI AON DC < < 100.000 ≥5.000.000 <5.000.000 200.00 ≥500.000 <500.000 0 3. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). Liste de Marchés de Travaux, Fournitures, et Services autres que Consultant Date Type Méthode/ Montan de Comme d'Exa Modalité Appro t lance ntaire Réf. DESCRIP men de che de Estimat ment /Fin de No. TION par la passatio march if en de la prestat Banqu n des és US$ procé ions e marchés dure II. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujette à la revue préalable de la Banque comme indiqué dans Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Méthode de Seuils de revue a priori Observations sélection/Catégories de Montants estimatifs des marchés contrats en millions de dollars américains Méthode compétitive/Firmes de >= 0.5 consultants Entente directe/firmes de Les justifications pour consultants >= 0.5 l’entente directe devront être jointes et approuvées Entente avec le PPM directe/Consultants >= 0.2 individuel Méthode Compétitive >= 0.2 (Comparaison de CVs)/ Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux en conformité avec les dispositions des Règlements de Passation des marchés., et l’Emprunteur ne procède pas à une publication dans UNDB 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission ; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels telles des situations d’urgence en conformité au Règlement de Passation des marchés II- Liste de Marchés de Services de Consultants Date Méthod Comm Montan Type de Ré e de entair t d'Exam Approch lancem f. DESCRIPTION passati e/Fin Estimat en par e de ent de No DES MISSIONS on des des if en la Marché la . marché presta US$ Banque procéd s tions ure Lexique des Sigles et Abréviations ARMP Autorité de Régulation des Marchés Publics AOI Appel d’Offres International AON Appel d’Offres National A Revue a posteriori posteriori A Priori Revue a priori CI Consultant Individuel DC Demande de Cotations DNCMP Direction Nationale de Contrôle des Marchés Publics ED Sélection Directe ou Entente Directe PPM Plan de Passation des Marchés SFQ Sélection Fondée sur la Qualité SFQC Sélection Fondée sur la Qualité et le Coût SMC Sélection au Moindre Coût SQC Sélection fondée sur les Qualifications des Consultants PROCUREMENT Western and Central Africa : West Africa Food System Resilience Program (FSRP) PLAN General Information Country: Western and Central Africa 2022-08-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172769 GPN Date: Project Name: West Africa Food System Resilience Program (FSRP) Loan / Credit No: IDA / 69980, IDA / D9250 FOOD SYSTEM RESILIENCE PROGRAM - NIGER Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure NE-FRSP-NE-306233-CW-RF ment Document - Request for Quota Single Stage - One E 2023-01-3 Q / Travaux d'extension du si IDA / 69980 Project Management Post Limited 1 Envelope proce 121,951.00 0.00 Signed 2022-08-20 2022-09-22 2022-09-12 tions nvelope 0 ège de l’UGP PARIIS pour le c ss (Non Bank-SPD ompte du FSRP ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306159-GO-RFB Sustainability and adaptive c / Acquisition pour doter le CR Single Stage - One E IDA / 69980 apacity of the food system’s Post Request for Bids Open - National 313,589.00 0.00 Signed 2022-09-05 2022-12-12 2022-09-10 2022-12-13 2022-10-10 2023-01-16 2022-10-25 2023-01-27 2022-11-29 2023-03-29 S et les labos en équipement nvelope productive base s complémentaires clés NE-FRSP-NE-306190-GO-RFB Sustainability and adaptive c Single Stage - One E / Acquisition de semences (A IDA / 69980 apacity of the food system’s Post Request for Bids Open - National 143,728.00 0.00 Completed 2022-08-31 2022-10-07 2022-09-05 2022-10-10 2022-10-05 2022-11-02 2022-10-15 2022-11-23 2022-11-15 2022-12-30 2023-01-21 nvelope ppui en intrants agricoles) productive base NE-FRSP-NE-306228-GO-RFQ Request for Quota Single Stage - One E IDA / 69980 Project Management Post Limited 52,265.00 0.00 Completed 2022-10-25 2023-03-30 2022-11-21 2022-12-31 2023-04-16 / Acquisition de mobilier de b tions nvelope ureau NE-FRSP-NE-306961-GO-RFQ Request for Quota Single Stage - One E / Acquisition de matériel infor IDA / 69980 Project Management Post Limited 52,265.00 38,580.81 Completed 2022-08-15 2022-08-22 2022-08-31 2022-09-09 2022-10-15 2022-09-26 tions nvelope matique pour l'équipe FSRP NE-FRSP-NE-342474-GO-RFQ / Acquisition d'équipements c Digital advisory services for Request for Quota Single Stage - One E Pending Impl omplémentaires et mise en IDA / D9250 agriculture and food crisis pr Post Limited 52,632.00 0.00 2023-06-06 2023-06-14 2023-07-14 tions nvelope ementation marche de la station de réce evention and management ption des données satellitale s de la DGPIA et DGGR NE-FRSP-NE-342493-GO-RFQ Digital advisory services for / Equipement des structures, Request for Quota Single Stage - One E Pending Impl IDA / D9250 agriculture and food crisis pr Post Limited 17,545.00 0.00 2023-06-05 2023-06-13 2023-07-13 renforcement de la cellule gé tions nvelope ementation evention and management omatique par acquisition des drones. NE-FRSP-NE-342526-GO-RFQ / Acquisitions de Kits de com Digital advisory services for Request for Quota Single Stage - One E Pending Impl munication, d'information de IDA / D9250 agriculture and food crisis pr Post Limited 13,000.00 0.00 2023-04-05 2023-04-13 2023-04-30 tions nvelope ementation s impacts potentiels aux agro evention and management pasteurs et décideurs NE-FRSP-NE-342538-GO-RFQ Regional food market integr Request for Quota Single Stage - One E Pending Impl / Equipement des laboratoire IDA / D9250 Post Limited 43,333.00 0.00 2023-03-20 2023-03-28 2023-05-02 ation and trade tions nvelope ementation s (LABOCEL, DGPV, LANA, LT A et LNCCS) NE-FRSP-NE-342565-GO-RFQ Regional food market integr Request for Quota Single Stage - One E Pending Impl / Acquisition de matériel de c IDA / D9250 Post Limited 26,315.00 0.00 2023-04-15 2023-04-25 2023-05-10 ation and trade tions nvelope ementation ollecte des données NE-FRSP-NE-342578-GO-RFB Sustainability and adaptive c Single Stage - One E Under Imple / Appui en intrants des cultur IDA / D9250 apacity of the food system’s Post Request for Bids Open - National 221,053.00 0.00 2023-03-15 2023-03-24 2023-03-20 2023-03-31 2023-04-20 2023-04-27 2023-04-28 2023-05-27 2023-05-22 2023-06-26 nvelope mentation es pluviales (semences et en productive base grais) NE-FRSP-NE-342588-GO-RFB Single Stage - One E Under Imple IDA / D9250 Project Management Post Request for Bids Open - National 390,351.00 0.00 2023-03-15 2023-03-23 2023-03-20 2023-03-23 2023-04-19 2023-04-27 2023-04-28 2023-05-15 2023-05-25 2023-07-29 / Acquisition de matériel roul nvelope mentation ant NE-FRSP-NE-342590-GO-RFQ Request for Quota Single Stage - One E / Acquisition de Motos au pro IDA / D9250 Project Management Post Limited 13,160.00 0.00 Completed 2023-03-13 2023-03-01 2023-03-21 2023-03-31 2023-04-05 tions nvelope fit de l'UCP et les Régions NE-FRSP-NE-342591-GO-RFQ Request for Quota Single Stage - One E / Acquisition de Matériels info IDA / D9250 Project Management Post Limited 26,315.00 0.00 Completed 2023-03-03 2023-03-06 2023-03-10 2023-03-31 2023-04-05 tions nvelope rmatiques au profit de l'UCP NE-FRSP-NE-342499-GO-RFQ Digital advisory services for Request for Quota Single Stage - One E Pending Impl / Achats d'équipements infor IDA / D9250 agriculture and food crisis pr Post Limited 35,088.00 0.00 2023-05-07 2023-05-16 2023-05-31 tions nvelope ementation matiques (Ordinateurs et Tél evention and management éphones) NE-FRSP-NE-306204-GO-RFB / Acquisition de Matériels info Regional food market integr Single Stage - One E Pending Impl IDA / D9250 Post Request for Bids Open - National 122,807.00 0.00 2023-06-12 2023-06-17 2023-07-17 2023-07-27 2023-08-26 2023-10-10 rmatiques pour les structures ation and trade nvelope ementation et partenaires du FSRP NE-FRSP-NE-361809-GO-RFQ Sustainability and adaptive c / Acquisition de semences en Request for Quota Single Stage - One E IDA / D9250 apacity of the food system’s Post Limited 87,000.00 0.00 Completed 2023-05-29 2023-06-01 2023-06-09 2023-06-24 complément de quantités po tions nvelope productive base ur la campagne hivernale 20 23 NE-FRSP-NE-364001-GO-RFB / Fourniture et installation d' Regional food market integr Single Stage - One E Pending Impl un générateur d'azote liquid IDA / D9250 Post Request for Bids Open - National 280,700.00 0.00 2023-06-15 2023-06-22 2023-07-21 2023-07-31 2023-08-31 2023-11-30 ation and trade nvelope ementation e en appui aux unités de con servations de semences ani males NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306238-NC-DIR / Fourniture et installation du IDA / 69980 Project Management Post Direct Selection Direct - National 17,422.00 0.00 Signed 2022-08-30 2022-09-09 2022-09-04 2022-10-07 2022-09-23 2023-09-23 logiciel informatique et comp table TOM2PRO CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306060-CS-CQS / Recrutement consultant po Digital advisory services for Consultant Qualifi Pending Impleme ur l'évaluation des capacités IDA / 69980 agriculture and food crisis pr Post Open - National 43,554.00 0.00 2022-08-30 2022-09-20 2022-11-03 2022-12-03 2022-12-30 2023-02-28 cation Selection ntation techniques et les besoins en evention and management formation pour soutenir le PD O du FSRP NE-FRSP-NE-306174-CS-CQS Sustainability and adaptive c Consultant Qualifi / Recrutement des ONGs pou IDA / 69980 apacity of the food system’s Post Open - National 300,000.00 0.00 Signed 2022-08-20 2022-10-10 2022-09-10 2022-10-24 2022-10-24 2022-12-14 2022-11-23 2023-02-20 2022-12-28 2023-12-28 cation Selection r l'Elaboration d'un Plan GIP productive base NE-FRSP-NE-306184-CS-CQS Sustainability and adaptive c / Recrutement consultant po Consultant Qualifi Pending Impleme IDA / 69980 apacity of the food system’s Post Open - National 69,686.00 0.00 2022-08-25 2022-09-15 2022-10-25 2022-11-24 2022-12-16 2023-02-14 ur l’Élaboration des schémas cation Selection ntation productive base d’aménagements de bassin v ersant NE-FRSP-NE-306187-CS-CQS Consultant Qualifi Under Implement / Recrutement Consultant po IDA / 69980 Project Management Post Open - National 36,794.00 0.00 2022-09-05 2022-12-08 2022-09-20 2023-01-26 2022-10-11 2023-05-05 2022-10-26 2022-11-01 2022-12-16 cation Selection ation ur l’Etude de référence NE-FRSP-NE-306235-CS-QCB Quality And Cost- S / Recrutement d’un Consult IDA / 69980 Project Management Post Open - National 8,711.00 0.00 Signed 2022-08-30 2022-09-05 2022-09-20 2022-10-13 2022-10-31 2022-12-22 2022-11-30 2023-01-20 2022-12-09 2023-02-28 2022-12-21 2023-02-28 2023-01-25 2024-01-25 Based Selection ant pour l’Audit annuel du pr ojet NE-FRSP-NE-342601-CS-CQS / Recrutement d'un consultan Sustainability and adaptive c Consultant Qualifi Open - Internationa Pending Impleme t pour les études de faisabilit IDA / D9250 apacity of the food system’s Post 263,160.00 0.00 2023-04-10 2023-04-20 2023-05-30 2023-07-05 2023-07-27 2024-01-23 cation Selection l ntation é technique de l'aménageme productive base nt des petits périmètres irrig ués NE-FRSP-NE-342663-CS-QCB Sustainability and adaptive c S / Recrutement d'un consult Quality And Cost- Open - Internationa Pending Impleme IDA / D9250 apacity of the food system’s Post 352,632.00 0.00 2023-05-05 2023-05-26 2023-07-09 2023-08-06 2023-09-05 2023-10-10 2023-11-14 2024-11-13 ant chargé des étude techniq Based Selection l ntation productive base ues des seuils de correction NE-FRSP-NE-342655-CS-QCB S / Recrutement d'un consult Sustainability and adaptive c ant pour les études de faisab Quality And Cost- Open - Internationa IDA / D9250 apacity of the food system’s Post 307,000.00 0.00 Under Review 2023-04-15 2023-05-20 2023-05-02 2023-06-15 2023-07-17 2023-07-28 2023-08-18 2023-09-22 2023-12-31 ilité technique et contrôle de Based Selection l productive base s travaux d'une petite retenu e d'eau dans la région de Till abéry NE-FRSP-NE-361744-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 300,000.00 0.00 2023-05-22 2023-05-26 2023-06-12 2023-07-12 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Zinder NE-FRSP-NE-361758-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 300,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Tahoua NE-FRSP-NE-361797-CS-CQS Sustainability and adaptive c / Recrutement d'ONG pour l'é Consultant Qualifi Under Implement IDA / D9250 apacity of the food system’s Post Limited 200,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 laboration d'un Plan GIP (Ges cation Selection ation productive base tion Intégrée du Paysage) da ns la région de Diffa NE-FRSP-NE-361801-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 200,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Tillabéry NE-FRSP-NE-361866-CS-QCB S / Recrutement d’un cabinet pour l’étude de faisabilité (AP Sustainability and adaptive c Quality And Cost- Open - Internationa S/APD/EIES/DAO) et le contrôl IDA / D9250 apacity of the food system’s Post 307,000.00 0.00 Under Review 2023-05-22 2023-05-20 2023-06-12 2023-07-24 2023-08-21 2023-08-31 2023-09-08 2023-10-13 2024-10-12 Based Selection l e des travaux d’aménageme productive base nt des bas-fonds (seuils d’ép andage/petits barrages) dans les régions de Tahoua et INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306128-CS-IND Digital advisory services for Individual Consult Pending Impleme V / Recrutement consultant p IDA / 69980 agriculture and food crisis pr Post Limited 17,422.00 0.00 2022-08-15 2022-08-22 2022-09-05 2022-09-15 2022-11-14 ant Selection ntation our la mise à jour des param evention and management ètres d’analyse NE-FRSP-NE-306140-CS-IND V / Recrutement consultant p Digital advisory services for our identifier/répertorier les f Individual Consult IDA / 69980 agriculture and food crisis pr Post Limited 52,265.00 0.00 Signed 2022-10-10 2022-12-07 2022-10-31 2023-02-22 2022-11-15 2023-04-25 2022-11-16 2022-12-31 ournisseurs et évaluation des ant Selection evention and management besoins de services hydro m étéo, phyto, et agro météo (I ncluant le secteur privée) NE-FRSP-NE-306156-CS-IND V / Recrutement d'un prestat Digital advisory services for Individual Consult Pending Impleme aire pour l'identification des t IDA / 69980 agriculture and food crisis pr Post Limited 17,422.00 0.00 2022-09-15 2022-09-30 2022-10-12 2022-10-15 2022-11-29 ant Selection ntation ypes de services et des mod evention and management alités d'engagement du sect eur privé NE-FRSP-NE-306516-CS-CDS / Service de consultant pour l IDA / 69980 Project Management Post Direct Selection Direct - National 26,132.00 0.00 Completed 2022-08-15 2022-08-19 2022-08-22 2022-09-20 2022-09-07 2022-10-07 2023-03-23 e recrutement du personnel complémentaire du FSRP Page 2 NE-FRSP-NE-306199-CS-IND V / Recrutement d'un Consult Regional food market integr Individual Consult ant pour l’Identification des a IDA / 69980 Post Limited 10,180.00 0.00 Canceled 2022-09-26 2022-10-10 2022-10-31 2022-11-15 2022-12-30 ation and trade ant Selection cteurs dans les chaines de va leur de Niébé et Oignon NE-FRSP-NE-309010-CS-IND V / Recrutement d'un Consult Regional food market integr Individual Consult IDA / 69980 Post Limited 5,500.00 0.00 Canceled 2022-09-26 2022-10-10 2022-10-31 2022-11-01 2022-12-01 ant pour l’Identification des a ation and trade ant Selection cteurs dans la chaine de vale ur Bétail-viande-lait NE-FRSP-NE-342594-CS-IND V / Recrutement d’un Consult Individual Consult ant pour l' Elaboration d'un g IDA / D9250 Project Management Post Limited 17,545.00 0.00 Under Review 2023-02-20 2023-02-22 2023-02-28 2023-03-10 2023-03-13 2023-05-02 ant Selection uide simplifié de gestion fina ncière pour les partenaires NE-FRSP-NE-342595-CS-IND V / Recrutement d'un consult Sustainability and adaptive c Individual Consult Pending Impleme ant pour l'élaboration d'une c IDA / D9250 apacity of the food system’s Post Limited 17,545.00 0.00 2023-04-03 2023-04-13 2023-04-20 2023-04-21 2023-05-31 ant Selection ntation artographie des groupes vuln productive base érables et constitution des b ases de données NE-FRSP-NE-342596-CS-IND Sustainability and adaptive c V / Recrutement d'un consult Individual Consult Pending Impleme IDA / D9250 apacity of the food system’s Post Limited 26,667.00 0.00 2023-04-01 2023-04-10 2023-04-21 2023-04-25 2023-06-14 ant pour l'élaboration de 3 pl ant Selection ntation productive base ans d’aménagement des zon es humides Page 3 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Africa CDC Regional Investment Financing Program, P167916 Project Implementation agency: Ministry of Health and Ethiopian Public Health Institute Date of the Procurement Plan: August 19,2019 Period covered by this Procurement Plan: August 2019 to August 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement plan; Works: is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. PROCUREMENT Eastern and Southern Africa : Africa CDC Regional Investment Financing Project PLAN General Information Country: Eastern and Southern Africa 2020-02-24 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167916 GPN Date: 2019-08-27 Project Name: Africa CDC Regional Investment Financing Project Loan / Credit No: IDA / 65040, IDA / 65030 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZM-MOH-139096-CW-RFB / C onstruction of Four Storey La Open - Internationa Single Stage - One E 19,407,600.0 2023-12-0 boratory Complex, Office co IDA / 65030 Public Health Assets Post Request for Bids 0.00 Canceled 2021-11-15 2022-01-31 2022-01-31 2021-11-20 2022-04-11 2022-05-11 2022-06-15 l nvelope 0 7 mplex and ancillary Building, Road works and drainage an d parking for ZNPHI/RCC ZM-MOH-320075-CW-RFQ / T ender for the Two (2) Comme Request for Quota rcial Borehole Siting, Drilling, Request for Quota Single Stage - One E 2023-06-1 IDA / 65040 Public Health Assets Post Limited tions (Non Bank-S 85,330.00 0.00 Canceled 2022-10-22 2022-12-17 Pump Installations, Fabricatio tions nvelope 5 PD) n and Erection of Steel Stora ge Water Tanks and Related Water works ZM-MOH-318958-CW-RFB / T Request for Bids - ender for the Construction of Single Stage - One E Small Works SPD 2023-08-0 1.6KM Perimeter Fence, Thre IDA / 65030 Public Health Assets Post Request for Bids Open - National 369,575.00 0.00 Canceled 2022-10-17 2022-10-06 2022-10-22 2022-12-03 2023-01-02 2023-02-06 nvelope (1 envelope proce 5 e (3) Guard Houses, Access R ss) oads and Installation of Temp oral Power Supply. ZM-MOH-325305-CW-RFB / T Request for Bids - ender for the Construction of Single Stage - One E Small Works SPD Under Imple 2023-09-1 1.6KM Perimeter Fence, Thre IDA / 65030 Public Health Assets Post Request for Bids Open - National 485,068.00 0.00 2022-11-23 2022-11-08 2022-11-28 2023-01-09 2022-12-16 2023-02-08 2023-01-20 2023-03-15 nvelope (1 envelope proce mentation 1 e (3) Guard Houses, Access R ss) oads and Installation of Temp oral Power Supply. ZM-MOH-325381-CW-RFQ / T ender for the Two (2) Comme Request for Quota rcial Borehole Siting, Drilling, Request for Quota Single Stage - One E Pending Imp 2023-07-2 IDA / 65030 Public Health Assets Post Limited tions (Non Bank-S 111,995.00 0.00 2022-11-28 2023-01-23 Pump Installations, Fabricatio tions nvelope lementation 2 PD) n and Erection of Steel Stora ge Water Tanks and Related Water works ZM-MOH-358223-CW-RFB / R National Procure efurbishment of BSL 2 Labor ment Document - Single Stage - One E Pending Imp 2024-06-0 atories at choma Veterinary l IDA / 65040 Public Health Assets Post Request for Bids Open - National 1 Envelope proce 449,503.69 0.00 2023-08-14 2023-08-19 2023-09-30 2023-10-30 2023-12-04 nvelope lementation 1 ab, Livingstone, Chinsali and ss (Non Bank-SPD Mansa, General Hospitals ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZM-MOH-139092-GO-RFQ / P Request for Quota Single Stage - One E IDA / 65030 Project Management Post Limited 10,000.00 83,170.45 Completed 2020-11-29 2020-12-29 2021-01-24 2021-04-24 2021-07-23 2021-04-24 rocurement of Office Equipm tions nvelope ent ZM-MOH-186758-GO-RFQ / P Request for Quota Single Stage - One E IDA / 65030 Project Management Post Limited 10,000.00 120,908.07 Completed 2020-11-21 2021-02-22 2021-01-16 2021-03-17 2021-07-15 2021-03-17 rocurement of Furniture for t tions nvelope he PIU ZM-MOH-139012-GO-UN / Pr UN Agencies (Dire Under Imple IDA / 65040 Public Health Assets Post Direct 605,000.00 0.00 2021-01-04 2021-01-09 2021-02-13 2021-08-12 ocurement of ten (10) motor ct) mentation vehicles ZM-MOH-139045-GO-RFQ / P Request for Quota Single Stage - One E rocurement of ECHO Equipm IDA / 65030 Public Health Assets Post Limited 44,417.00 401.40 Completed 2021-01-23 2021-02-24 2021-03-20 2021-04-13 2021-09-16 2021-04-13 tions nvelope ent for Laboratories in Provin ces and Districts. ZM-MOH-139067-GO-RFB / P Single Stage - One E IDA / 65030 Public Health Assets Post Request for Bids Open - National 117,000.00 0.00 Canceled 2020-12-01 2020-12-06 2021-01-17 2021-02-16 2021-03-23 2021-09-19 rocurement of EBS Tools nvelope ZM-MOH-139015-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Tools and Equi IDA / 65030 Public Health Assets Post Limited 48,000.00 0.00 Canceled 2021-08-28 2021-10-23 2022-04-21 tions nvelope pment for the Point of Entry ZM-MOH-139071-GO-RFB / P Open - Internationa Single Stage - One E rocurement of equipment for IDA / 65030 Public Health Assets Post Request for Bids 428,520.00 171,242.14 Signed 2021-02-15 2021-04-06 2021-02-20 2021-04-03 2021-05-04 2021-05-03 2021-05-18 2021-06-07 2021-07-13 2021-12-04 l nvelope Sentinel Sites ZM-MOH-139030-GO-RFQ / P rocurement of Laboratory Re Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 17,000.00 0.00 Canceled 2021-01-23 2021-03-20 2021-09-16 agents stock for entrice disea tions nvelope se surveillance sites ZM-MOH-176260-GO-RFQ / P rocurement of Influenza sam Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 31,518.00 0.00 Canceled 2021-04-10 2021-06-05 2021-12-02 ple collection supplies for sen tions nvelope tinel surveillance sites ZM-MOH-139032-GO-RFB / P Open - Internationa Single Stage - One E rocurement of Strategic Labo IDA / 65030 Public Health Assets Post Request for Bids 313,890.00 0.00 Canceled 2021-06-14 2021-04-06 2021-06-19 2021-07-31 2021-08-30 2021-10-04 2022-04-02 l nvelope ratory Reagents Stocks ZM-MOH-139005-GO-RFB / P Open - Internationa Single Stage - One E IDA / 65030 Public Health Assets Post Request for Bids 550,000.00 0.00 Canceled 2022-02-15 2022-02-20 2022-04-03 2022-05-03 2022-06-07 2022-12-04 rocurement of PHEOC Equip l nvelope ment ZM-MOH-186751-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Lab Reagents/ IDA / 65030 Public Health Assets Post Limited 2,250.00 0.00 Canceled 2021-05-22 2021-07-17 2022-01-13 tions nvelope consumables for Research Page 1 ZM-MOH-176266-GO-RFQ / P rocurement of Laboratory rea Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 34,496.00 0.00 Canceled 2021-05-22 2021-07-17 2022-01-13 gent stocks for enteric diseas tions nvelope e surveillance sites ZM-MOH-186753-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Bicycles for co IDA / 65030 Public Health Assets Post Limited 17,000.00 0.00 Canceled 2020-11-24 2021-01-19 2021-07-18 tions nvelope mmunity volunteers ZM-MOH-139021-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Equipment for IDA / 65030 Public Health Assets Post Limited 22,685.00 0.00 Canceled 2021-06-26 2021-08-21 2022-02-17 tions nvelope two (2) Sentinel Surveillance Sites ZM-MOH-176274-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Communicatio IDA / 65030 Public Health Assets Post Limited 7,950.00 0.00 Canceled 2021-01-16 2021-03-13 2021-09-09 tions nvelope n Equipment ZM-MOH-260183-GO-RFQ / P rocurement of Office Equipm Request for Quota Single Stage - One E Under Imple ent (11 Laptops, 2 Scanners, IDA / 65030 Project Management Post Limited 36,286.00 0.00 2021-11-20 2022-04-11 2022-01-15 2022-07-14 tions nvelope mentation 2 Shredders, 1 Industrial Cop ier and 4 (3 in 1 ) printers for PIU ZM-MOH-259349-GO-RFQ / P rinting of (500) Event Based Surveillance guidelines, (150 Request for Quota Single Stage - One E Under Imple IDA / 65030 Public Health Assets Post Limited 26,470.58 0.00 2022-03-26 2022-04-01 2022-05-21 2022-11-17 0) report books and (1500) r tions nvelope mentation egisters for 42 Districts to fac ilitate operationalisation of E BS concepts in Districts ZM-MOH-259353-GO-RFQ / P rocurement of (1500) Bags, ( 3000) Pens (1500) T. Shirts a Request for Quota Single Stage - One E Under Imple IDA / 65030 Public Health Assets Post Limited 77,558.82 0.00 2022-03-26 2022-04-01 2022-05-21 2022-11-17 nd (1500) Caps for Event Ba tions nvelope mentation sed Surveillance Volunteers/ Community based in 42 Distr icts. ZM-MOH-259355-GO-RFB / P rocurement of Equipment for ILI/SARI Surveillance ((1) App lied Biosystem 7500 Real Ti Single Stage - One E me PCR System, (1) Automat IDA / 65030 Public Health Assets Post Request for Bids Open - National 146,848.83 0.00 Canceled 2022-03-21 2022-03-26 2022-05-07 2022-06-06 2022-07-11 2023-01-07 nvelope ed nuclei acid extraction syst em, (1) 24 slot refrigerated E ppendorf microcentrifuge, (1) Reagents storage refrigerato r and (5) 3000 KVA UPS ZM-MOH-259356-GO-RFQ / P rocurement of reagents and Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 16,544.11 0.00 Canceled 2022-03-28 2022-05-23 2022-11-19 consumables for ILI/SARI Sur tions nvelope veillance for Virology Lab at UTH. ZM-MOH-259361-GO-RFQ / P rocurement of safety gear for onsite inspections (Helmets ( Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 6,679.00 0.00 Canceled 2022-03-19 2022-05-14 2022-11-10 50), Safety Boots (50), Work tions nvelope Suits (50), Ear Muffs (100), G oggles (50), N95 Masks (150) and Gloves (50)) ZM-MOH-259358-GO-RFQ / P rinting of Epidemic Prepared Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 16,176.47 0.00 Canceled 2022-09-17 2022-11-12 2023-05-11 ness and Response Guideline tions nvelope s and PHEOC SOPs. ZM-MOH-260140-GO-RFQ / P rocurement of office furnitur Request for Quota Single Stage - One E Pending Impl e (13 Office desks, (13) Offic IDA / 65030 Project Management Post Limited 18,571.00 0.00 2022-03-26 2022-05-21 2022-11-17 tions nvelope ementation e Chairs and 13 Filling cabine ts for PIU. See attached speci fications and Distribution list. ZM-MOH-259357-GO-RFQ / P rocurement of two (2 to 8 de grees) thermo scientific (TSX series high performance lab r Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 37,500.00 0.00 Canceled 2022-04-04 2022-05-30 2022-11-26 efrigerators, (4) freezer -80 U tions nvelope pright, (2) freezer-40 Upright , freezer installation, calibrati on, validation and commissio ning services. ZM-MOH-325228-GO-RFB / P rocurement of (400) Laptops, (400) Laptop Bags, (400) Mic Single Stage - One E Under Imple rosoft Office Installation Kit a IDA / 65040 Public Health Assets Post Request for Bids Open - National 858,750.00 0.00 2022-12-21 2022-11-08 2022-12-26 2023-02-06 2022-12-07 2023-03-08 2023-01-31 2023-04-12 2023-10-09 nvelope mentation nd (400) Anti- Virus for 116 D istricts and 284 Health Facilit ies to enhance digitization of Data Management ZM-MOH-325229-GO-RFB / P rocurement of ECHO Equipm ent (30) Television Sets, (30) Single Stage - One E Under Imple TV screen mounting kit, (30) IDA / 65030 Public Health Assets Post Request for Bids Open - National 117,188.00 0.00 2022-12-12 2022-11-08 2022-12-17 2023-01-28 2022-12-07 2023-02-27 2023-01-30 2023-04-03 2023-09-30 nvelope mentation USB Conference Camera, 30 I nternet routers, 30 HDMI Cab les and 30 Adaptors for Distri ct Health Offices ZM-MOH-325232-GO-RFQ / P Request for Quota Single Stage - One E Under Imple rocurement of Office Furnitur IDA / 65030 Project Management Post Limited 6,875.00 0.00 2022-12-25 2023-01-17 2023-02-19 2023-08-18 tions nvelope mentation e for the Project Implementat ion Unit ZM-MOH-325233-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl rocurement of AutoCAD 2022 IDA / 65030 Project Management Post Limited 6,248.00 0.00 2022-12-17 2023-02-11 2023-08-10 tions nvelope ementation Design Package ZM-MOH-325234-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Computer Wor IDA / 65030 Project Management Post Limited 5,918.00 0.00 Signed 2022-12-25 2023-03-01 2023-02-19 2023-08-18 tions nvelope kstation for Designing ZM-MOH-325235-GO-RFQ / P Request for Quota Single Stage - One E IDA / 65030 Project Management Post Limited 8,773.00 0.00 Signed 2022-12-24 2023-02-23 2023-02-18 2023-08-17 rocurement of Data Server tions nvelope Page 2 ZM-MOH-325231-GO-RFQ / P rocurement of Office Equipm ent for PIU (2) Projectors, (1) Request for Quota Single Stage - One E Under Imple IDA / 65030 Project Management Post Limited 50,656.00 0.00 2022-12-17 2022-11-19 2023-02-11 2023-08-10 A3 Printer (10) Laptops, (2) s tions nvelope mentation canner, (1) Fridges, (1) Electr ic Kettles, (1) Microwave, (2) 3 in 1 Printers ZM-MOH-345808-GO-RFQ / P rocurement of Laptops, Micro Human Resources Developm Request for Quota Single Stage - One E Under Imple soft Office, Antivirus and Rou IDA / 65040 Post Limited 18,735.00 0.00 2023-03-25 2023-03-01 2023-05-20 2023-11-16 ent tions nvelope mentation ters for the for Field Epidemi ology under the Work Force Development ZM-MOH-346154-GO-DIR / Pr ocurement of portable labs a Contingent Emergency Resp Pending Impl nd water testing kits and equ IDA / 65040 Post Direct Selection Direct - National 256,410.25 0.00 2023-03-28 2023-04-02 2023-05-07 2023-11-03 onse Component (CERC) ementation ipment (chlorometers, lovibo nd comparators and DPT tabl ets) ZM-MOH-346155-GO-DIR / Pr ocure of laboratory reagents Contingent Emergency Resp Under Imple IDA / 65040 Post Direct Selection Direct - National 128,205.12 0.00 2023-03-28 2023-04-06 2023-04-02 2023-05-07 2023-11-03 and consumables for cholera onse Component (CERC) mentation confirmation and genomic se quencing. ZM-MOH-346152-GO-DIR / Pr ocurement of liquid and gran Contingent Emergency Resp Pending Impl ular chlorine for water treatm IDA / 65040 Post Direct Selection Direct - National 292,307.69 0.00 2023-03-28 2023-04-02 2023-05-07 2023-11-03 onse Component (CERC) ementation ent at CTC and disinfection of latrines and HH - National ZM-MOH-358224-GO-RFB / P rocurement of laboratory rea Single Stage - One E Pending Impl gents and consumables to su IDA / 65040 Public Health Assets Post Request for Bids Open - National 111,628.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 nvelope ementation pport surveillance and detect ion of priority public health p athogens ZM-MOH-358228-GO-RFQ / P rocurement of Office tables a Request for Quota Single Stage - One E Pending Impl IDA / 65040 Public Health Assets Post Limited 16,744.18 0.00 2023-07-01 2023-08-26 2024-02-22 nd chairs for the operationali tions nvelope ementation zation of the National and 2 s ub national PHEOCs ZM-MOH-358309-GO-RFQ / P rocurement of fire system (fir e alarm, fire extinguisher and Request for Quota Single Stage - One E Pending Impl IDA / 65040 Public Health Assets Post Limited 4,186.04 0.00 2023-07-05 2023-08-30 2024-02-26 smoke detectors) for the ope tions nvelope ementation rationalization of the Nationa l and 2 National sub PHEOCs ZM-MOH-358313-GO-RFQ / P rocurement of security syste Request for Quota Single Stage - One E Pending Impl m (CCTV and Biometric syste IDA / 65040 Public Health Assets Post Limited 5,581.39 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation m) for the operationalization of the National and 2 Nationa l sub PHEOCs ZM-MOH-358325-GO-RFQ / P rocurement of assorted IT Eq Request for Quota Single Stage - One E Pending Impl IDA / 65040 Public Health Assets Post Limited 39,581.39 0.00 2023-07-05 2023-08-30 2024-02-26 uipment for the operationaliz tions nvelope ementation ation of the National and 2 N ational sub PHEOCs ZM-MOH-358327-GO-RFQ / P rocurement of 85’’Television Request for Quota Single Stage - One E Pending Impl sets and TV Screen for the op IDA / 65040 Public Health Assets Post Limited 9,302.32 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation erationalization of the Nation al and 2 National sub PHEOC s. ZM-MOH-358329-GO-RFB / P rocurement of Equipment for BSL 2 Laboratories at Kasam Single Stage - One E Pending Impl a, Mongu, choma, Chpata Vet IDA / 65040 Public Health Assets Post Request for Bids Open - National 1,106,064.66 0.00 2023-07-31 2023-08-05 2023-09-16 2023-10-16 2023-11-20 2024-05-18 nvelope ementation erinary lab, Livingstone, Chin sali, Mansa, Lewanika, Chipat a General Hospitals CVRL, ZN PHIRL ZM-MOH-358331-GO-DIR / Pr ocurement of (3) 13-seater h ardtop land cruiser to suppor t sample referral and respons Direct - Internation Pending Impl e for strengthening of diseas IDA / 65040 Public Health Assets Post Direct Selection 209,472.53 0.00 2023-06-30 2023-07-05 2023-08-09 2024-02-05 al ementation e prevention and control cap abilities for Zambia, and (1) Utility Motor Vehicle establis hment of an ICT center (inclu ding hardware and sof ZM-MOH-358332-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl rocurement of ECHO Equipm IDA / 65040 Public Health Assets Post Limited 87,209.30 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation ent for District Health Offices ZM-MOH-358335-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl rocurement of Data Server B IDA / 65040 Public Health Assets Post Limited 25,814.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation ackup for ERP and establish ment of ICT Centre ZM-MOH-358336-GO-RFQ / U Request for Quota Single Stage - One E Pending Impl pgrading of the existing ZNP IDA / 65040 Public Health Assets Post Limited 3,414.63 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation HI Data Server ZM-MOH-358344-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl rocurement of 48U Server Ra IDA / 65040 Public Health Assets Post Limited 5,581.40 0.00 2023-06-25 2023-08-20 2024-02-16 tions nvelope ementation ck Rack with Console ZM-MOH-362045-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl rocurement of Personal Prote IDA / 65040 Project Management Post Limited 3,372.09 0.00 2023-07-01 2023-08-26 2024-02-22 tions nvelope ementation ctive clothing for ACDCP PIU NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZM-MOH-139082-NC-RFQ / P Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 12,215.00 0.00 Canceled 2021-07-11 2021-09-05 2022-03-04 rinting of One Health Guidlin tions nvelope es Page 3 ZM-MOH-176271-NC-RFQ / P Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 2,172.00 0.00 Canceled 2021-05-08 2021-07-03 2021-12-30 rinting of Legal Frameworks tions nvelope ZM-MOH-139027-NC-RFQ / P Request for Quota Single Stage - One E rinting of Epidemic Prepared IDA / 65030 Public Health Assets Post Limited 5,000.00 0.00 Canceled 2021-06-27 2021-08-22 2022-02-18 tions nvelope ness and Response Guidlines ZM-MOH-139018-NC-RFQ / P Request for Quota Single Stage - One E rinting of point of entry guide IDA / 65030 Public Health Assets Post Limited 5,000.00 0.00 Canceled 2022-08-13 2022-10-08 2023-04-06 tions nvelope lines and SOPs ZM-MOH-139034-NC-RFQ / P rinting of QMS materials, Lab Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 54,125.00 0.00 Canceled 2022-09-10 2022-11-05 2023-05-04 oratory Quality Manuals, Job tions nvelope Aids, SOPs and Laboratory H andbooks ZM-MOH-260137-NC-RFQ / P Request for Quota Single Stage - One E rocurement of services for fu IDA / 65030 Project Management Post Limited 1,105.00 0.00 Canceled 2022-03-26 2022-05-21 2022-11-17 tions nvelope nctional Vehicle Management System ZM-MOH-325241-NC-RFQ / P Request for Quota Single Stage - One E Under Imple rocurement of Functional Pay IDA / 65030 Project Management Post Limited 5,872.00 0.00 2022-12-17 2022-11-09 2023-02-11 2023-08-10 tions nvelope mentation roll System for the ACDCP Pr oject ZM-MOH-325244-NC-RFQ / P rocurement of Microsoft Dyn Request for Quota Single Stage - One E Pending Impl IDA / 65030 Project Management Post Limited 43,328.00 0.00 2022-12-10 2023-02-04 2023-08-03 amics 365 (IFMIS and Navisio tions nvelope ementation n) for ACDCP and Covid-19 Pr oject CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZM-MOH-139108-CS-QCBS / Design and Supervision and Management Consultant for t Quality And Cost- Open - Internationa IDA / 65030 Public Health Assets Prior 3,800,000.00 0.00 Canceled 2020-12-01 2020-12-22 2021-02-04 2021-03-04 2021-04-03 2021-05-08 2021-06-12 2022-06-12 he Construction of the four st Based Selection l orey BSL 3 Laboratory, Office Complex and ancillary buildin gs, and parking for ZNPHI/RC C. ZM-MOH-139349-CS-CQS / C Governance, Advocacy, and Consultant Qualifi onsultancy services for the D IDA / 65040 Post Open - National 100,000.00 0.00 Canceled 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 Operational Frameworks cation Selection evelopment of a Legal Frame work ZM-MOH-259373-CS-CQS / C onsultancy Services for the D Consultant Qualifi IDA / 65030 Public Health Assets Post Limited 74,433.33 0.00 Canceled 2021-11-08 2022-03-04 2021-11-22 2021-12-22 2022-01-26 2022-07-25 evelopment of Surveillance S cation Selection ystem DHIS2 Tracker ZM-MOH-139350-CS-CQS / P Consultant Qualifi rovision of consultancy servic IDA / 65040 Project Management Post Open - National 9,387.00 0.00 Canceled 2021-06-07 2021-06-28 2021-08-11 2021-09-10 2021-10-15 2022-04-13 cation Selection es for the Development of M &E Tools ZM-MOH-318996-CS-QCBS / Consultancy Services for Proj ect Management for the desi Quality And Cost- Open - Internationa Under Implement gn and Supervision of the Co IDA / 65030 Public Health Assets Post 491,429.00 0.00 2022-11-14 2022-10-06 2022-12-05 2023-01-18 2023-02-15 2023-03-17 2023-04-21 2023-05-26 2024-05-25 Based Selection l ation nstruction of a Building Com plex Including Offices, BSL-3 Laboratory and Ancillary Buil dings for ZNPHI/RCC. ZM-MOH-318959-CS-QCBS / Provision of Consultancy Serv Quality And Cost- Open - Internationa Under Implement ices for the Design, Construct IDA / 65030 Public Health Assets Prior 778,095.24 0.00 2022-11-14 2022-12-05 2023-01-18 2023-02-15 2023-03-17 2023-04-21 2023-05-26 2024-05-25 Based Selection l ation ion Supervision and Equippin g of the ZNPHI Building Com plex ZM-MOH-259551-CS-CQS / P Consultant Qualifi rovision of Consultancy Servi IDA / 65030 Project Management Post Limited 14,622.00 0.00 Canceled 2021-11-08 2022-11-18 2021-11-22 2021-12-22 2022-01-26 2022-07-25 cation Selection ces for the Development of M &E Systems ZM-MOH-369387-CS-CQS / P rovision of Consultancy servi Consultant Qualifi Pending Impleme IDA / 65040 Project Management Post Limited 23,255.81 0.00 2023-07-24 2023-08-07 2023-09-06 2023-10-11 2024-04-08 ces for the Development of M cation Selection ntation onitoring and Evaluation Syst em INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZM-MOH-161147-CS-INDV / Recruitment of a Project Coor Individual Consult IDA / 65040 Project Management Post Open 60,000.00 116,980.27 Signed 2020-04-13 2020-08-07 2020-06-01 2020-12-10 2020-06-22 2021-03-15 2020-07-27 2021-03-23 2021-01-23 dinator for the Africa Centre f ant Selection or Disease Control Project ZM-MOH-186783-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult IDA / 65030 Prior Direct 149,860.89 0.00 Canceled 2020-08-17 2020-12-17 2020-08-27 2020-09-17 2020-10-22 2021-04-20 Head-Workforce Developmen ent ant Selection t for Leadership and Technic al Expertise ZM-MOH-186769-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult IDA / 65030 Prior Direct 149,860.89 197,247.71 Signed 2020-08-17 2020-12-24 2020-08-27 2021-02-02 2020-09-17 2021-02-28 2020-10-22 2021-03-02 2021-04-20 Head-Laboratory Systems an ent ant Selection d Network Leadership and Te chnical Expertise ZM-MOH-186793-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult Head- Epidemic Preparednes IDA / 65030 Prior Direct 149,860.89 197,247.71 Signed 2020-08-17 2020-12-24 2020-08-27 2021-02-02 2020-09-17 2021-02-28 2020-10-22 2021-03-02 2021-04-20 ent ant Selection s and Response Leadership a nd Technical Expertise ZM-MOH-186779-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult IDA / 65030 Prior Direct 149,860.89 0.00 Under Review 2020-08-17 2020-12-17 2020-08-27 2020-09-17 2020-10-22 2021-04-20 Head- Information Systems f ent ant Selection or Leadership and Technical Expertise Page 4 ZM-MOH-186762-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult IDA / 65030 Prior Direct 248,032.89 315,596.33 Signed 2020-09-28 2020-12-24 2020-10-08 2021-02-02 2020-10-29 2021-02-28 2020-12-03 2021-03-02 2021-06-01 Leadership and Technical Ex ent ant Selection pertise (Director ZNPHI) ZM-MOH-139344-CS-INDV / Consultancy services for the Individual Consult Design Validation consultant IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-01 2021-01-19 2021-02-09 2021-03-16 2021-09-12 ant Selection (Quality Assurance) Refrigera tion and Air conditioning Engi neer ZM-MOH-186775-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult Head-Surveillance and Disea IDA / 65030 Prior Direct 149,860.89 197,247.71 Signed 2020-08-17 2020-12-17 2020-08-27 2021-02-02 2020-09-17 2021-02-28 2020-10-22 2021-03-02 2021-04-20 ent ant Selection se Intelligence for Leadership and Technical Expertise ZM-MOH-139352-CS-CQS / C Individual Consult onsultancy services for the D IDA / 65040 Project Management Post Limited 7,929.00 0.00 Canceled 2021-04-13 2021-04-18 2021-05-09 2021-06-13 2021-12-10 ant Selection evelopment of Baseline Surv ey Tools ZM-MOH-186795-CS-CDS / R ecruitment and retention of Human Resources Developm Individual Consult IDA / 65030 Post Direct 149,860.89 0.00 Canceled 2021-08-09 2021-08-19 2021-09-09 2021-10-14 2022-04-12 Head Public Health Research ent ant Selection Leadership and Technical Ex pert. ZM-MOH-139346-CS-INDV / Consultancy services for the Individual Consult IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-03-14 2021-02-08 2021-03-01 2021-04-05 2021-10-02 Design Validation consultant ant Selection (Quality Assurance) Electro M echanical Engineer. ZM-MOH-139340-CS-INDV / Consultancy services for the Individual Consult Design Validation consultant IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 ant Selection (Quality Assurance) Laborato ry and Medical Equipment Sp ecialist ZM-MOH-139303-CS-INDV / Consultancy services for the Individual Consult Design Validation consultant IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 ant Selection (Quality Assurance) Environ mental Safeguards Specialist . ZM-MOH-139320-CS-INDV / Consultancy services for the Individual Consult IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 Design Validation consultant ant Selection (Quality Assurance) Civil/Stru ctural Engineer ZM-MOH-139338-CS-INDV / Consultancy services for the Individual Consult IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 Design Validation consultant ant Selection (Quality Assurance) Social Sa feguards Specialist. ZM-MOH-139341-CS-INDV / Consultancy services for the Individual Consult IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-03-14 2021-02-08 2021-03-01 2021-04-05 2021-10-02 Design Validation consultant ant Selection (Quality Assurance) Architect ZM-MOH-139114-CS-INDV / Consultancy Services for the Individual Consult IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-03-14 2021-02-08 2021-03-01 2021-04-05 2021-10-02 Design Validation Consultant ant Selection (Quality Assurance) Infectiou s Disease Specialist. ZM-MOH-202428-CS-CDS / R Individual Consult ecruitment of an Infectious D IDA / 65030 Project Management Prior Direct 126,954.09 133,370.48 Signed 2020-11-23 2021-04-06 2020-12-03 2021-09-17 2020-12-24 2021-10-14 2021-01-28 2021-10-02 2021-07-27 ant Selection isease Specialist ZM-MOH-202432-CS-CDS / R Individual Consult ecruitment of a Monitoring a IDA / 65030 Project Management Prior Direct 71,265.60 142,568.81 Signed 2020-11-23 2021-01-25 2020-12-03 2021-02-26 2020-12-24 2021-02-28 2021-01-28 2021-03-02 2021-07-27 ant Selection nd Evaluation Officer ZM-MOH-202434-CS-CDS / R Individual Consult IDA / 65030 Project Management Prior Direct 71,265.60 108,154.51 Signed 2020-11-23 2020-12-16 2020-12-03 2021-02-02 2020-12-24 2021-02-28 2021-01-28 2021-03-02 2021-07-27 ecruitment of a Procurement ant Selection Officer ZM-MOH-202436-CS-CDS / R Individual Consult IDA / 65030 Project Management Prior Direct 71,265.60 114,963.50 Signed 2020-11-23 2021-01-25 2020-12-03 2021-02-26 2020-12-24 2021-02-28 2021-01-28 2021-03-02 2021-07-27 ecruitment of an Accountant ant Selection ZM-MOH-202430-CS-CDS / R Individual Consult IDA / 65030 Project Management Prior Direct 126,954.09 0.00 Canceled 2020-11-23 2021-03-26 2020-12-03 2020-12-24 2021-01-28 2021-07-27 ecruitment of a Public Health ant Selection Specialist ZM-MOH-202433-CS-CDS / R Individual Consult IDA / 65030 Project Management Prior Direct 71,265.60 105,971.41 Signed 2020-11-23 2021-01-25 2020-12-03 2021-02-26 2020-12-24 2021-02-28 2021-01-28 2021-03-02 2021-07-27 ecruitment of an Internal Aud ant Selection itor ZM-MOH-218315-CS-CDS / R Individual Consult ecruitment of an Environmen IDA / 65030 Project Management Post Open 126,954.09 0.00 Canceled 2021-02-28 2021-02-11 2021-04-18 2021-05-09 2021-06-13 2021-12-10 ant Selection t and Social Safeguards Spec ialist ZM-MOH-220876-CS-INDV / Individual Consult RECRUITMENT OF A SOCIAL S IDA / 65030 Project Management Prior Direct 126,954.09 0.00 Canceled 2021-03-08 2021-06-01 2021-03-18 2021-04-08 2021-05-13 2021-11-09 ant Selection AFEGUARDS SPECIALIST ZM-MOH-218308-CS-CQS / R Individual Consult Under Implement ecruitment of a Civil Enginee IDA / 65030 Project Management Post Open 126,954.09 0.00 2021-03-31 2021-07-22 2021-05-19 2021-06-09 2021-07-14 2022-01-10 ant Selection ation r for ACDCP ZM-MOH-218314-CS-CDS / R Individual Consult ecruitment of Human Resour IDA / 65030 Project Management Post Direct 71,265.60 0.00 Canceled 2021-03-31 2021-04-10 2021-05-01 2021-06-05 2021-12-02 ant Selection ce and Administration officer ZM-MOH-218305-CS-CDS / R Human Resources Developm Individual Consult IDA / 65030 Post Direct 126,954.09 0.00 Canceled 2021-03-31 2021-09-17 2021-04-10 2021-05-01 2021-06-05 2021-12-02 ecruitment of a Laboratory S ent ant Selection pecialist ZM-MOH-218307-CS-CQS / R Individual Consult IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-03-31 2021-05-24 2021-05-19 2022-11-08 2021-06-09 2022-11-08 2021-07-14 2022-01-10 ecruitment of an Architect ant Selection ZM-MOH-218306-CS-CDS / R Human Resources Developm Individual Consult IDA / 65030 Prior Direct 126,954.09 145,620.44 Signed 2021-03-31 2021-04-16 2021-04-10 2021-09-17 2021-05-01 2021-09-20 2021-06-05 2021-11-20 2021-12-02 ecruitment of One Health Sp ent ant Selection ecialist Page 5 ZM-MOH-218310-CS-CQS / R Individual Consult ecruitment of a Financial Ma IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-03-31 2021-05-24 2021-05-19 2022-05-08 2021-06-09 2022-05-16 2021-07-14 2022-01-10 ant Selection nagement Specialist ZM-MOH-218312-CS-CQS / R Individual Consult IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-03-31 2021-05-24 2021-05-19 2022-01-04 2021-06-09 2022-06-15 2021-07-14 2022-01-10 ecruitment of a Procurement ant Selection Specialist ZM-MOH-236033-CS-INDV / Individual Consult Recruitment of an Internal Au IDA / 65030 Project Management Post Open 126,954.09 0.00 Canceled 2021-06-07 2021-05-28 2021-07-26 2021-08-16 2021-09-20 2022-03-19 ant Selection ditor (Specialist) ZM-MOH-241182-CS-INDV / Individual Consult Recruitment of an Environm IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-06-30 2021-08-27 2021-08-18 2022-11-09 2021-09-08 2022-11-09 2021-10-13 2022-04-11 ant Selection ental Safeguards Specialist ZM-MOH-241184-CS-INDV / Individual Consult IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-06-30 2021-08-27 2021-08-18 2022-08-29 2021-09-08 2022-11-07 2021-10-13 2022-04-11 Recruitment of an Internal Au ant Selection ditor ZM-MOH-253276-CS-INDV / Recruitment of a Procuremen t Specialist on exceptional ba sis to help build capacity for Human Resources Developm Individual Consult IDA / 65030 Post Direct 126,954.09 0.00 Canceled 2021-09-27 2021-09-13 2021-10-07 2021-10-07 2021-10-28 2021-10-07 2021-12-02 2022-05-31 ZNPHI. The officer will be sec ent ant Selection onded from the Public Servic e Management Division(PSM D) and this will be done on Di rect Selection basis. ZM-MOH-250665-CS-INDV / Recruitment of a Public Healt Individual Consult IDA / 65030 Project Management Post Direct 126,954.09 145,620.44 Signed 2021-09-20 2021-09-13 2021-09-30 2021-09-17 2021-10-21 2021-09-17 2021-11-25 2021-11-20 2022-05-24 h Specialist- Integrated Disea ant Selection se Surveillance Response (PH S-IDSR) ZM-MOH-253752-CS-INDV / Recruitment of an IT Speciali Individual Consult IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-09-27 2021-09-21 2021-11-15 2022-08-29 2021-12-06 2022-10-27 2022-01-10 2022-07-09 st (Digital Solutions). The con ant Selection sultant will be recruited throu gh the Open Market. ZM-MOH-253280-CS-INDV / Recruitment of a Financial M anagement Specialist on exc Human Resources Developm Individual Consult eptional basis to help build c IDA / 65030 Post Direct 126,954.90 0.00 Canceled 2021-09-27 2021-09-13 2021-10-07 2021-10-28 2021-12-02 2022-05-31 ent ant Selection apacity for ZNPHI. The Office r will be seconded from office of the Accountant General an d will be done on Direct Sele ction basis. ZM-MOH-253281-CS-INDV / Recruitment of a Senior Inter nal Auditor on exceptional ba Human Resources Developm Individual Consult sis to help build capacity for IDA / 65030 Post Direct 126,954.09 0.00 Canceled 2021-09-27 2021-09-13 2021-10-07 2021-10-21 2021-10-28 2021-12-02 2022-05-31 ent ant Selection ZNPHI. The officer will be sec onded from Office of the Con troller of Internal Audit. This will be done on Direct Selecti on basis ZM-MOH-282216-CS-INDV / Individual Consult Consultancy services for enh IDA / 65030 Public Health Assets Post Limited 4,365.43 0.00 Canceled 2022-03-21 2022-03-26 2022-04-16 2022-05-21 2022-11-17 ant Selection ancement of ZNPHI Website ZM-MOH-282436-CS-INDV / Consultancy services to Cond Human Resources Developm Individual Consult Under Implement uct Institution Assessment an IDA / 65030 Post Limited 25,000.00 0.00 2022-03-21 2022-11-07 2022-03-26 2022-04-16 2022-05-21 2022-11-17 ent ant Selection ation d preparation of a comprehe nsive Human resources need s Assessment ZM-MOH-327703-CS-INDV / Individual Consult IDA / 65030 Project Management Post Open - National 126,954.09 0.00 Signed 2022-12-20 2022-11-22 2023-02-07 2022-08-29 2023-02-28 2022-10-27 2023-04-04 2023-10-01 Recruitment of a Laboratory ant Selection Specialist ZM-MOH-327704-CS-INDV / Individual Consult Recruitment of a Social Safeg IDA / 65030 Project Management Post Open - National 126,954.09 0.00 Completed 2022-12-20 2022-11-22 2023-02-07 2022-09-20 2023-02-28 2022-11-02 2023-04-04 2023-10-01 2022-11-11 ant Selection uards Specialist ZM-MOH-362043-CS-INDV / Recruitment of a Monitoring Individual Consult Pending Impleme IDA / 65040 Project Management Post Open - National 116,263.40 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2024-04-06 and Evaluation Specialist for ant Selection ntation the ACDCP Project Implemen tation Unit. Page 6 Republic of Malawi EGENCO LTD 18 MONTHS PROCUREMENT PLAN- MALAWI EMERGENCY POWER RESTORATION PROJECT I. General 1.Project information Country: Malawi Project Name: Malawi Emergency Power Restoration Project (MEPRP) Project ID: P178914 2.Project Implementation Agency: EGENCO Limited 3.Date of the Procurement Plan: May 17, 2022 4.Period covered by this Procurement Plan: May 2022 to October 2023 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Disposal of Public Assets Act, 2017 of the Republic of Malawi, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations as follows:  Provision of “set-asides” contracts for small enterprises shall not be applied.  Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis.  Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and practices. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification. Not expected for the works/goods packages in the procurement plan. VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable VII. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). (a) Goods: Not Applicable for those contracts identified in the Procurement Plan tables. (b) Works: Not Applicable for those contracts identified in the Procurement Plan tables. IX. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: If requested by the Recipient, the World Bank will provide procurement hands-on expanded implementation support (HEIS) to help expedite preparation of bidding documents. X. Other Relevant Procurement Information: - (a) Proposed Procedures for CDD Components: Not Applicable (b) Reference to (if any) Project Operational/Procurement Manual: EGENCO and ESCOM will prepare a Procurement Manual which will be part of the Project Implementation Manual (PIM) to elaborate procurement arrangements under the proposed Project. The Procurement Plan will also form part of the PIM. XI. Any Other Special Procurement Arrangements: Being emergency project, simple and fast procurement and selection processes fit for purpose in an emergency will be used including the following streamlined procurement arrangements: (i) increased thresholds for Requests for Quotations (RFQ) to US$1 million for goods and services and US$5 million for works; (ii) direct contracting of firms as appropriate; (iii) Limited Competition with identified manufacturers and suppliers for other items; (iv) Use of procurement agents; (v) Force account, as needed; (vi) Bid Securing Declaration may be used instead of the bid security; (vii) Advance payment may be increased to 40 percent, while secured with the advance payment guarantee; (viii) The time for submission of bids/proposal can be shortened to seven - 15 days in competitive national and international procedures, and to three days for the Request for Quotations, however if bidders request an extension, it should be granted, and (ix) The retroactive financing may be applied to the contracts procured in advance for the purpose of this Project objective using procurement procedures consistent with Sections I, II and III of the World Bank’s Procurement Regulations and consistent with the Financing Agreement of this Project. XII. Procurement Approach and Prior Review Thresholds: Based on the overall procurement risk rating of “Substantial”, the thresholds for the Bank’s prior review and procurement method threshold are provided in the table below: Prior-review Thresholds for Procurement Methods Thresholds Procureme Substanti Works Goods, IT & Non-Consulting Shortlist of National nt al Services Consultants Type Risk ($`000) Works 10,000 Open Request Request Internatio for for Engineerin Open Open nal or Quotatio Open Quotatio Consultin g& Nation Nation ICB n or Internatio n or g Constructi al or al or ($'000 National nal or ICB National Services on NCB NCB Shoppin ($'000) Shoppin ($'000) Supervisio ($'000) ($'000) g g n ($'000) ($'000) ($'000) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultant 1,000 s (Firms) Individual 300 7,000 7,000 200 1,000 1,000 100 200 300 Consultant s Note Given that the project will finance a combination of goods, services, and works for emergency response as per OP 8.00, there is normally no prior review, and there will be no Standstill Period, provided that utilities will informally share documentation for quality assurance purposes before contractual commitments. XIII. Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: PROCUREMENT PLAN A. Works 1 2 3 4 5 6 7 8 9 10 Ref Contract Estimated Market Selectio Prequa Domesti Review Expecte Expecte . Description Cost Approa n lificatio c by d bid d No. US$ ch Method n Prefere Bank opening Contrac (yes/no nce (Prior / date t ) (yes/no) Post) Signatu re Date 1 Reconstruction of 193,000.00 Limited RFQ No No Post 01-Jul-22 30-Jul-22 Chilala Bridge 2 Extension of 500,000.00 Limited RFQ No No Post 01-Jul- 30-Jul-22 Stoplog guides /22 and repair of slabs 3 Maintenance of 400,000.00 Limited RFQ No No Post 01-Aug- 31-Aug- Spillway ( Supply 22 22 of wire ropes for 5 Gates) 4 Desilting of River 1,100,000.0 Limited RFB No No Post 01-Jul-22 30-Jul-2 Left Bank Channel 0 5 Rehabilitation or 28,876,769. Limited RFB Yes No Prior 01-Apr- 01-Aug- upgrade of the 00 23 23 Dam Supply, delivery 600,000.00 Limited RFQ No No Post 01-Oct- 31-Oct- 6 and installation of 22 22 Cooling Water System B. Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimated Market Selecti Prequ Domesti Revie Expecte Expecte No. Description Cost Approach on alifica c w d bid d US$ Method tion Prefere by opening Contrac (yes/n nce Bank date t o) (yes/no) (Prior Signatu / Post) re Date 1. Motor Vehicles (4 240,000.00 Limited RFQ No No Post 20-May- 31-May- x 4 D/Cab ) 22 22 2. Office Furniture & 25,000.00 Limited RFQ No No Post 20-May- 31-May- Equipment 22 22 C. Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimate Market Selecti Shortlisti Revie Expected Expected No. Description d Approa on ng w proposal Contract Cost ch Method (Yes/No) by opening Signature US$ Bank date Date (Prior / Post) 1. ESIA for Dam Rehabilitation 1,200,000 Limited CQS No Post 01-Aug-22 30-Aug-22 Assessment and Prep of .00 Safeguard Studies and Plans 2. Engineering Consultancy 4,200,000 Limited CQS No Post 30-Jun-22 15-Jul-22 Services OE Phase 2 for the .00 Assessment of the Rehabilitation or Upgrade for the dam Dam Expert – dam safety 240,000.0 Direct DIR No Post 01-Aug-22 30-Aug-22 3. panel 0 Geotechnical Expert – dam 240,000.0 Direct DIR No Post 01-Aug-22 30-Aug-22 4. safety panel 0 5. Hydro-mechanical Expert – 120,000.0 Direct DIR No Post 01-Aug-22 30-Aug-22 dam safety panel 0 6. Hydrological Expert – dam 240,000.0 Direct DIR No Post 01-Aug-22 30-Aug-22 safety panel 0 7. Environmental Engineer on 50,000.00 Direct DIR No Post 01-Aug-22 30-Aug-22 Panel of Experts 7. Social Expert on Panel of 50,000.00 Direct DIR No Post 01-Aug-22 30-Aug-22 Expert 8. Hiring of Environmental. 168,000.0 Limited INDV Yes Post 27-May- 01=Jun-22 Safeguard Specialist for the 0 22 PIU 9. Hiring of Procurement 168,000.0 Limited INDV Yes Post 27-May- 01-Jun-22 Specialist for the PIU 0 22 10. Hiring of Social Specialist 168,000.0 Limited INDV Yes Post 27-May- 01-Jun22 for the PIU 0 22 11 Hiring of a Dam Engineer 40,000.0 Limited INDV Yes Post 20-Jun22 01-Jul22 for the PIU. (To review 0 design and construction supervision of cofferdam done by SVTP consultant during Phase I) RFB – Request for Quotations; RFB – Request form Bids; CQS- Consultant’s Based Qualifications; INDV - Individual Consultant Selection and DIR– Direct Selection. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Malawi : Emergency Power Restoration Project PLAN General Information Country: Malawi 2022-09-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178914 GPN Date: Project Name: Emergency Power Restoration Project Loan / Credit No: IDA / E0970 Electricity Generation Company Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned EGC012/WBP178914/W/RFB/ Request for Quota Component 1: Kapichira Da FY2022-23 / Reconstruction Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-03-2 IDA / E0970 m Rehabilitation and Strengt Post Limited 300,000.00 0.00 2022-09-25 2022-09-29 Works for the Tempory Chilal tions nvelope s (Emergency) SP lementation 8 hening a bridge on Access Road T14 D -Competitive 6 Request for Quota EGC049/W/FY2022-23 / Exte Component 1: Kapichira Da Request for Quota Single Stage - One E tions - Small Work 2023-04-2 nsion of the Stoplog Guides f IDA / E0970 m Rehabilitation and Strengt Post Limited 500,000.00 0.00 Canceled 2022-08-11 2022-10-24 tions nvelope s (Emergency) SP 2 or Spillway hening D -Competitive Request for Quota EGC035/WB/W/RFB/FY2022- Component 1: Kapichira Da Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-06-1 23 / Construction Works to R IDA / E0970 m Rehabilitation and Strengt Post Limited 1,000,000.00 0.00 2022-10-19 2022-12-14 tions nvelope s (Emergency) SP lementation 2 einforce Embankment Dam i hening D -Competitive n Phase I MW-EGENCO-324258-CW-RF Request for Bids - Component 1: Kapichira Da B / Reconstruction Works for Single Stage - One E Small Works SPD Pending Imp 2024-04-1 IDA / E0970 m Rehabilitation and Strengt Post Request for Bids Limited 1,000,000.00 0.00 2023-06-27 2023-07-02 2023-08-13 2023-09-12 2023-10-17 the Permanent Chilala Bridge nvelope (1 envelope proce lementation 4 hening on Access Road T146 ss) MW-EGENCO-314183-CW-RF Request for Bids - Component 1: Kapichira Da B / Rehabilitation Works for t Single Stage - One E Works (without pr 29,000,000.0 Pending Imp 2024-03-2 IDA / E0970 m Rehabilitation and Strengt Prior Request for Bids Limited 0.00 2023-06-11 2023-06-16 2023-07-28 2023-08-27 2023-10-01 he Spillway, Embankment Da nvelope equalification) SP 0 lementation 9 hening m, and Dam Instrumentation D Equipment MW-EGENCO-314838-CW-RF Request for Quota Component 1: Kapichira Da Q / Supply, Delivery, Installat Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-2 IDA / E0970 m Rehabilitation and Strengt Post Limited 730,000.00 0.00 2023-08-06 2023-10-01 ion and Commissioning of Up tions nvelope s (Emergency) SP lementation 9 hening graded Cooling System D -Competitive Request for Quota MW-EGENCO-366933-CW-RF Component 1: Kapichira Da Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-04-0 Q / Extension of the Stoplog IDA / E0970 m Rehabilitation and Strengt Post Limited 500,000.00 0.00 2023-08-12 2023-10-07 tions nvelope s (Emergency) SP lementation 4 Guides for Spillway hening D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EGC/158/SS/G/FY20-23 / Sup Component 1: Kapichira Da ply and Delivery of lifting wir Request for Quota Single Stage - One E Pending Impl IDA / E0970 m Rehabilitation and Strengt Post Limited 400,000.00 0.00 2022-07-05 2022-07-16 2023-01-12 e ropes for 5 spillway gate fo tions nvelope ementation hening r the Immediate Maintenance of Spillway EGC05/WBP178914/G/RFQ/F Component 1: Kapichira Da Y2022-23 / Procurement of 3 Request for Quota Single Stage - One E Under Imple IDA / E0970 m Rehabilitation and Strengt Post Limited 240,000.00 0.00 2022-06-22 2022-06-22 2022-08-18 2023-02-14 (No.). x Motor vehicles (2.5lit tions nvelope mentation hening res, 4x4 Twin Cab with Cano py) for PIU EGC04/WBP178914/G/RFQ/F Y2022-23 / Procurement of of Component 1: Kapichira Da Request for Quota Single Stage - One E fice furniture and equipment: IDA / E0970 m Rehabilitation and Strengt Post Limited 25,000.00 0.00 Canceled 2022-06-23 2022-06-22 2022-08-09 2023-02-05 tions nvelope 7 (No.) x laptops, 7 (No.) Des hening ks and chairs, 3 (No.) x Fridg es) MW-EGENCO-324081-GO-RF Component 1: Kapichira Da Request for Quota Single Stage - One E Pending Impl Q / Procurement of Mobile ph IDA / E0970 m Rehabilitation and Strengt Post Limited 40,000.00 0.00 2022-11-20 2023-01-15 2023-07-14 tions nvelope ementation one Handsets and airtime. 7 hening (seven) EGC32/WBP/RFQ/2022-23 / S upply of Gabion baskets and Component 1: Kapichira Da Request for Quota Single Stage - One E Under Imple Geotextiles for Reconstructio IDA / E0970 m Rehabilitation and Strengt Post Limited 143,000.00 0.00 2022-09-30 2022-09-29 2022-10-07 2022-10-21 tions nvelope mentation n Works for the Temporary C hening hilala bridge on Access Road T146 EGC02/WBP178914/G/RFQ/F Component 1: Kapichira Da Request for Quota Single Stage - One E Pending Impl Y2022-23 / Supply and delive IDA / E0970 m Rehabilitation and Strengt Post Limited 17,900.00 0.00 2022-07-10 2022-08-09 2022-08-23 tions nvelope ementation ry of Laptops hening MW-EGENCO-355611-GO-RF Component 1: Kapichira Da Q / Supply of Culverts for Rec Request for Quota Single Stage - One E Pending Impl IDA / E0970 m Rehabilitation and Strengt Post Limited 76,000.00 0.00 2022-09-30 2022-10-10 2022-10-24 onstruction Works for the Te tions nvelope ementation hening mporary Chilala bridge on Ac cess Road T146 EGC04/WBP178914/G/RFQ/F Component 1: Kapichira Da Y2022-23. / Supply of Office Request for Quota Single Stage - One E Pending Impl IDA / E0970 m Rehabilitation and Strengt Post Limited 25,000.00 0.00 2022-06-22 2022-08-09 2022-08-23 Furniture and Equipment: 7 ( tions nvelope ementation hening No.) Desks and chairs, 3 (No. ) x Fridges) MW-EGENCO-349167-GO-RF Component 1: Kapichira Da Single Stage - One E Pending Impl B / Supply, Delivery and Insta IDA / E0970 m Rehabilitation and Strengt Post Request for Bids Limited 1,334,545.00 0.00 2023-08-20 2023-08-25 2023-10-06 2023-11-05 2023-12-10 2024-06-07 nvelope ementation llation of Dam Instrumentatio hening n Equipment MW-EGENCO-324264-GO-RF Component 1: Kapichira Da Request for Quota Single Stage - One E Pending Impl Q / Supply and Delivery of ea IDA / E0970 m Rehabilitation and Strengt Post Limited 852,787.00 0.00 2023-08-11 2023-10-06 2024-04-03 tions nvelope ementation rthen and quarry materials fo hening r Phase 2 MW-EGENCO-368399-GO-RF Component 1: Kapichira Da Request for Quota Single Stage - One E Pending Impl Q / Supply and delivery of 1n IDA / E0970 m Rehabilitation and Strengt Post Limited 75,000.00 0.00 2023-07-01 2023-08-26 2024-02-22 tions nvelope ementation o. Motor Vehicle hening NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-EGENCO-324251-NC-RF Component 1: Kapichira Da Q / Hiring of 50-ton mobile cr Request for Quota Single Stage - One E Pending Impl IDA / E0970 m Rehabilitation and Strengt Post Limited 145,000.00 0.00 2022-09-20 2022-09-24 2023-03-23 ane and tipper trucks, and Ex tions nvelope ementation hening cavators for Spillways MW-EGENCO-324253-NC-RF Component 1: Kapichira Da Q / Hiring of Tipper trucks, B Request for Quota Single Stage - One E Under Imple IDA / E0970 m Rehabilitation and Strengt Post Limited 995,000.00 0.00 2022-07-29 2022-07-28 2022-08-02 2023-01-29 ull Dossers, Dampers and Ex tions nvelope mentation hening cavators for Desilting of Rive r left bank channel CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-EGENCO-324259-CS-CQ S / Consultancy Services for Component 1: Kapichira Da ESIA for Dam Rehabilitation Consultant Qualifi IDA / E0970 m Rehabilitation and Strengt Post Limited 1,200,000.00 0.00 Canceled 2022-11-28 2023-03-31 2022-12-12 2023-01-11 2023-02-15 2023-08-14 Assessment and Preparation cation Selection hening of Safeguards Studies and pl ans – supervision of impleme ntation of E&S plans EGC09/WBP178914/S/RFP/FY 2022-24 / Engineering Consul tancy Services for upgrade of the Dam, Design, procureme Component 1: Kapichira Da Consultant Qualifi Under Implement nt support , supervision , up IDA / E0970 m Rehabilitation and Strengt Post Limited 4,200,000.00 0.00 2022-08-11 2022-08-11 2022-08-11 2022-08-11 2022-11-09 2022-11-12 2023-05-11 cation Selection ation grade operation manuals, da hening m break analysis, prepare e mergency preparedness plan , dam safety report and Sedi ment Management Plan MW-EGENCO-324256-CS-CQ Component 1: Kapichira Da S / Recruitment of consultant Consultant Qualifi IDA / E0970 m Rehabilitation and Strengt Post Limited 50,000.00 0.00 Canceled 2023-01-23 2023-02-06 2023-03-08 2023-04-12 2023-10-09 (Firm) for capacity building in cation Selection hening OHS and working in fast flow ing water MW-EGENCO-362145-CS-CQ S / Consultancy Services for t he Environmental and Social Component 1: Kapichira Da Impact Assessment (ESIA) for Consultant Qualifi Open - Internationa IDA / E0970 m Rehabilitation and Strengt Prior 1,200,000.00 0.00 Under Review 2023-05-19 2023-05-18 2023-05-19 2023-05-23 2023-06-18 2023-07-03 2023-08-07 2024-02-03 Dam Rehabilitation Assessm cation Selection l hening ent and Preparation of Safeg uards Studies and Plans – Su pervision of Implementation of E&S Plans MW-EGENCO-324260-CS-CQ Component 1: Kapichira Da S / Consultancy Services for Consultant Qualifi Pending Impleme IDA / E0970 m Rehabilitation and Strengt Post Limited 100,000.00 0.00 2023-08-28 2023-09-11 2023-10-11 2023-11-15 2024-05-13 Disaster Risk analysis and E cation Selection ntation hening mergency preparedness for t he project life cycle INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-EGENCO-314823-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of Dam Expert on P IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Under Review 2022-10-01 2023-06-26 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection anel of Experts hening MW-EGENCO-314816-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of an Hydrological IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Under Review 2022-10-01 2023-06-26 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection Expert on Panel of Experts hening MW-EGENCO-314824-CS-IND Component 1: Kapichira Da Individual Consult Pending Impleme V / Hiring of Enviromental Saf IDA / E0970 m Rehabilitation and Strengt Post Limited 216,000.00 0.00 2022-10-01 2022-10-06 2022-10-27 2022-12-01 2023-05-30 ant Selection ntation eguards Specialist in PIU hening EGC06/WBP178914/S/RFP/FY Component 1: Kapichira Da 2022-23 / Design and Constr Individual Consult Direct - Internation Pending Impleme IDA / E0970 m Rehabilitation and Strengt Post 168,000.00 0.00 2022-08-02 2022-08-02 2022-08-19 2022-09-10 2023-03-09 uction Supervision Services f ant Selection al ntation hening or construction of the Cofferd am EGC011/WBP178914/S/RFP/F Component 1: Kapichira Da Y2022-23 / Geological Servic Individual Consult Direct - Internation Pending Impleme IDA / E0970 m Rehabilitation and Strengt Post 20,000.00 0.00 2022-08-30 2022-09-01 2022-09-02 2022-09-19 2023-03-18 es for CSD Cofferdam Design ant Selection al ntation hening and Foundation Construction MW-EGENCO-324248-CS-IND Component 1: Kapichira Da Individual Consult Pending Impleme V / Aerial Photography and M IDA / E0970 m Rehabilitation and Strengt Post Limited 50,000.00 0.00 2022-10-26 2022-10-28 2023-01-22 2023-02-26 2023-08-25 ant Selection ntation apping (Drone Survey) hening EGC07/WBP178914/S/RFP/FY Component 1: Kapichira Da Individual Consult Direct - Internation Pending Impleme 2022-23 / Hiring of Sediment IDA / E0970 m Rehabilitation and Strengt Post 168,000.00 0.00 2022-07-18 2022-07-20 2022-08-05 2022-08-16 2023-02-12 ant Selection al ntation Management Expert hening MW-EGENCO-324250-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of Monitoring and E IDA / E0970 m Rehabilitation and Strengt Post Limited 144,000.00 0.00 Canceled 2022-11-28 2022-12-03 2022-12-24 2023-01-28 2023-07-27 ant Selection valuation Specialist hening EGC023/WBP178914/S/RFP/F Component 1: Kapichira Da Individual Consult Pending Impleme Y2022-33 / Hiring of Social a IDA / E0970 m Rehabilitation and Strengt Post Limited 216,000.00 0.00 2022-05-27 2022-06-01 2022-06-08 2022-06-27 2022-12-24 ant Selection ntation nd Gender Safeguards Speci hening alist for PIU MW-EGENCO-314790-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of a Social Develop IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Canceled 2023-07-31 2023-08-13 2023-09-03 2023-10-08 2024-04-05 ant Selection ment Specialist on Panel of E hening xperts EGC022/WBP178914/S/RFP/F Component 1: Kapichira Da Individual Consult Pending Impleme Y2022-32 / Hiring of Procure IDA / E0970 m Rehabilitation and Strengt Post Open - National 216,000.00 0.00 2022-05-23 2022-06-06 2022-06-27 2022-07-10 2025-05-25 ant Selection ntation ment Specialist for PIU hening Page 2 MW-EGENCO-366924-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of Geotechnical Ex IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Under Review 2023-06-16 2023-06-26 2023-06-26 2023-07-17 2023-08-21 2024-02-17 ant Selection pert on Dam Safety Panel of hening Experts MW-EGENCO-366926-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of Hydromechanica IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Under Review 2023-06-16 2023-06-26 2023-06-26 2023-07-17 2023-08-21 2024-02-17 ant Selection l Expert on Dam Safety Panel hening of Experts MW-EGENCO-314833-CS-IND Component 1: Kapichira Da V / Hiring of an Environmenta Individual Consult IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Under Review 2023-07-31 2023-06-26 2023-08-10 2023-08-31 2023-10-05 2024-04-02 l and Social Management Spe ant Selection hening cialist on Panel of Experts Page 3 PROCUREMENT PLAN (Textual Part) Project information: [Vietnam] [JSDF - STRENGTHENING PREPAREDNESS AND RESPONSE TO COVID-19 AT THE GRASSROOTS LEVEL IN VIETNAM] [P174401] Project Implementation agency: [Institute for Social Development Studies] Date of the Procurement Plan: [April 27, 2022] Period covered by this Procurement Plan: [April 2022 – December 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Vietnam Public Procurement Law dated 2013 and the regulations guiding its implementation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations, ensuring compliance with the core principles of the WB’s Procurement Regulations and using sample procurement documents acceptable to the WB. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Hands-on Expanded Implementation Support (HEIS): Not Applicable. PROCUREMENT Vietnam : JSDF - Strengthening Preparedness and Response to COVID-19 at the Grassroots level in Vietnam PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2022-04-28 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-18 none) Project ID: P174401 GPN Date: 2022-04-08 Project Name: JSDF - Strengthening Preparedness and Response to COVID-19 at the Grassroots level in Vietnam Loan / Credit No: TF / B6532 Institute for Social Development Studies Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management and Ad G-1 / Office Equipment 202 Request for Quota Single Stage - One E TF / B6532 ministration, Monitoring and Post Open - National 20,400.00 0.00 Signed 2022-07-05 2022-07-28 2022-08-27 2 tions nvelope Evaluation, and Knowledge Dissemination Building capacities at the gr assroots level in Preparedne G-2 / Office Equipment 202 Request for Quota Single Stage - One E Pending Impl TF / B6532 ss for, Response to, Recover Post Open - National 16,000.00 0.00 2023-06-04 2023-06-28 2023-07-28 3 tions nvelope ementation y and Resilience from COVID -19 and ot her health emerg encies NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management and Ad CQS-1 / Consultant firm to c Consultant Qualifi TF / B6532 ministration, Monitoring and Post Open - National 25,000.00 23,955.15 Signed 2022-04-28 2022-05-13 2022-05-18 2022-05-30 2022-06-30 2022-07-11 2022-08-10 2022-07-14 2022-08-21 2022-10-12 onduct baseline survey cation Selection Evaluation, and Knowledge Dissemination Project Management and Ad Consultant Qualifi Under Implement CQS-2 / Recruit Audit firm TF / B6532 ministration, Monitoring and Post Open - National 15,000.00 0.00 2022-10-10 2022-12-22 2022-10-12 2022-11-16 2022-12-31 2023-01-05 2025-06-20 cation Selection ation Evaluation, and Knowledge Dissemination INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Building capacities at the gr assroots level in Preparedne CSI-1 / Senior Project Officer Individual Consult TF / B6532 ss for, Response to, Recover Prior Limited 76,800.00 75,477.42 Signed 2022-04-27 2022-04-29 2022-04-28 2022-04-29 2022-05-12 2022-05-10 2022-05-16 2022-05-12 2024-12-31 Cum Procurement Specialist ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne Individual Consult CSI-2 / Project Officer TF / B6532 ss for, Response to, Recover Post Limited 54,400.00 53,471.47 Signed 2022-04-28 2022-04-29 2022-04-29 2022-05-05 2022-05-06 2022-05-06 2022-05-11 2022-05-07 2024-12-31 ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-3 / Chief Technical Mana Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 47,520.00 46,260.69 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-09 2022-06-06 2022-05-16 2022-05-07 2025-01-12 ger working for CPMU ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.2 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-10 2022-05-10 2022-05-16 2022-05-13 2024-12-31 tor for Khanh Hoa ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.1 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Terminated 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-10 2022-05-10 2022-05-17 2022-05-12 2024-12-31 tor for Vinh Phuc ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.3 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-08 2022-05-10 2022-05-11 2022-05-12 2024-12-31 tor for Long An ant Selection y and Resilience from COVID -19 and ot her health emerg encies Project Management and Ad CSI-5 / Communication Speci Individual Consult TF / B6532 ministration, Monitoring and Post Open 18,000.00 0.00 Signed 2022-06-27 2023-06-20 2022-07-23 2022-07-28 2022-07-25 2022-07-29 2022-07-26 2024-12-31 alist ant Selection Evaluation, and Knowledge Dissemination Developing and piloting mod CSI-6 / Network Operation T els to support the most vuln Individual Consult TF / B6532 Post Open - National 59,850.00 0.00 Signed 2022-08-08 2022-08-09 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-12-31 echnical Specialist erable groups in the prepare ant Selection dness and response to COVI D-19 Page 1 Building capacities at the gr CSI-7 / Consultant to develo assroots level in Preparedne Individual Consult p intersectoral collaboration TF / B6532 ss for, Response to, Recover Post Open - National 7,500.00 7,070.78 Signed 2022-08-08 2023-01-11 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-08-29 2022-12-31 ant Selection plan y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr CSI-8 / Consultant to develo assroots level in Preparedne p guideline on infection prev Individual Consult TF / B6532 ss for, Response to, Recover Post Open - National 4,050.00 3,872.10 Signed 2022-08-08 2023-05-19 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-09-29 2022-12-31 ention and control inside co ant Selection y and Resilience from COVID mmunity health stations -19 and ot her health emerg encies CSI-9 / Consultant to develo Building capacities at the gr p Guideline on provision of e assroots level in Preparedne Individual Consult ssential healthcare services TF / B6532 ss for, Response to, Recover Post Open - National 9,150.00 8,754.30 Signed 2022-08-08 2023-06-20 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-08-29 2022-12-31 ant Selection and patient management, tre y and Resilience from COVID atment support and patient r -19 and ot her health emerg eferral during pandemics encies Raising awareness and know CSI-10 / Consultant to devel ledge towards changing attit Individual Consult op Guideline on risk commun TF / B6532 Post Open - National 7,600.00 7,239.14 Signed 2022-08-08 2022-08-09 2022-08-19 2022-08-25 2022-08-22 2022-08-26 2022-08-24 2022-09-08 2022-12-31 udes and behavior of the co ant Selection ication mmunity through risk comm unication CSI-11 / Consultant to upgra Project Management and Ad Individual Consult Under Implement de website for establishment TF / B6532 ministration, Monitoring and Post Open - National 2,000.00 0.00 2022-11-14 2022-11-14 2022-11-25 2022-11-26 2022-12-01 2022-12-31 ant Selection ation and operation of an informati Evaluation, and Knowledge on hub Dissemination Building capacities at the gr CSI-4.1.1 / Vinh Phuc Provinc assroots level in Preparedne ial Project Coordinator (Termi Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 19,000.00 0.00 2023-05-04 2023-05-04 2023-05-11 2023-05-12 2023-05-15 2024-12-31 nate contract CSI-4.1/2022, r ant Selection ation y and Resilience from COVID ecruit new person on board) -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne Individual Consult Under Implement CSI-12 / Project Assistant TF / B6532 ss for, Response to, Recover Post Open - National 20,000.00 0.00 2023-06-01 2023-05-22 2023-06-22 2023-06-24 2023-06-26 2024-12-31 ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-13 / Midterm review con Individual Consult Pending Impleme TF / B6532 ss for, Response to, Recover Post Open - National 7,000.00 0.00 2023-06-01 2023-06-27 2023-06-30 2023-07-05 2023-09-01 sultant ant Selection ntation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-14 / Community develop Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Open - National 24,000.00 0.00 2023-06-15 2023-06-20 2023-06-29 2023-06-30 2023-07-01 2024-12-31 ment Specialist ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.1 / Vinh Phuc Provinci Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 al Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.2 / Khanh Hoa Provin Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 cial Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.3 / Long An Provincial Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Page 2 PROCUREMENT PLAN (Textual Part) Project information: Azerbaijan; Improved Livelihoods for IDPs in Azerbaijan Project (ILIDP) P178125 Project Implementation agency: State Committee for Affairs of Refugees and Internally Displaced Persons Date of the Procurement Plan: 18.10.2022 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Public Procurement Law of the Republic of Azerbaijan, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is not applicable Works:is not applicable PROCUREMENT Azerbaijan : SPF: Improved Livelihoods for Internally Displaced Persons in Azerbaijan PLAN General Information Country: Azerbaijan 2023-05-02 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178125 GPN Date: 2023-04-11 Project Name: SPF: Improved Livelihoods for Internally Displaced Persons in Azerbaijan Loan / Credit No: / State Committee for Affairs of Refugees and Internally Displaced Persons Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCRI/P178125-AZ/005 / Proc Component 2: Job placemen Single Stage - One E Pending Impl urement of equipment for tra / t and business development Post Request for Bids Open - National 390,000.00 0.00 2024-12-12 2024-12-17 2025-01-17 2025-01-27 2025-02-04 2025-07-04 nvelope ementation ining graduates, Round 2 support SCRI/P178125-AZ/004 / Proc Component 2: Job placemen Single Stage - One E Pending Impl urement of equipment for tra / t and business development Post Request for Bids Open - National 390,000.00 0.00 2024-03-28 2024-04-02 2024-05-02 2024-05-14 2024-05-22 2025-05-22 nvelope ementation ining graduates, Round 1 support NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCRI/P178125-AZ/002 / Hirin Component 3: Civic engage Least Cost Selecti Pending Impleme g the services of an Audit fir / ment, social cohesion, monit Post Open - National 18,084.00 0.00 2023-09-01 2023-09-11 2023-09-19 2023-10-04 2023-10-11 2023-10-25 2023-10-30 2025-12-30 on ntation m oring and operational suppor t SCRI/P178125-AZ/003 / Hirin Component 2: Job placemen Consultant Qualifi Pending Impleme g the Consultant Firm on bu / t and business development Post Open - National 65,200.00 0.00 2024-01-01 2024-01-15 2024-01-29 2024-02-05 2024-02-12 2025-02-12 cation Selection ntation siness training providers support SCRI/P178125-AZ/001 / Hirin Component 3: Civic engage Consultant Qualifi Under Implement g of Citizen Engagement Ser / ment, social cohesion, monit Post Open - National 250,000.00 0.00 2023-05-15 2023-05-19 2023-05-30 2023-06-16 2023-06-22 2023-06-27 2025-12-31 cation Selection ation vice Provider oring and operational suppor t INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SCRI/P178125-AZ/006 / Ment Component 1: Skills develop Individual Consult Under Implement / Post Open - National 24,000.00 0.00 2023-05-23 2023-05-19 2023-06-07 2023-06-07 2023-06-09 2025-06-09 or Coordinator ment ant Selection ation SCRI/P178125-AZ/007 / Ment Component 1: Skills develop Individual Consult Under Implement / Post Open - National 19,200.00 0.00 2023-05-23 2023-05-19 2023-06-12 2023-06-12 2023-06-14 2025-06-16 or ment ant Selection ation SCRI/P178125-AZ/008 / Ment Component 1: Skills develop Individual Consult Under Implement / Post Open - National 19,200.00 0.00 2023-05-23 2023-05-19 2023-06-12 2023-06-12 2023-06-14 2025-06-16 or ment ant Selection ation SCRI/P178125-AZ/009 / Ment Component 1: Skills develop Individual Consult Under Implement / Post Open - National 19,200.00 0.00 2023-05-23 2023-05-19 2023-06-12 2023-06-12 2023-06-14 2025-06-16 or ment ant Selection ation SCRI/P178125-AZ/010 / Ment Component 1: Skills develop Individual Consult Under Implement / Post Open - National 19,200.00 0.00 2023-05-23 2023-05-19 2023-06-12 2023-06-12 2023-06-14 2025-06-16 or ment ant Selection ation SCRI/P178125-AZ/011 / Moni Component 3: Civic engage Individual Consult Under Implement toring and Evaluation Special / ment, social cohesion, monit Post Open - National 21,600.00 0.00 2023-05-23 2023-05-19 2023-06-14 2023-06-14 2023-06-16 2025-06-16 ant Selection ation ist oring and operational suppor t SCRI/P178125-AZ/012 / Envi Component 3: Civic engage Individual Consult Under Implement ronmental and Social Safegu / ment, social cohesion, monit Post Open - National 6,750.00 0.00 2023-05-23 2023-05-19 2023-06-14 2023-06-14 2023-06-16 2024-09-16 ant Selection ation ard Specialist oring and operational suppor t SCRI/P178125-AZ/013 / Ment Component 1: Skills develop Individual Consult Pending Impleme / Post Open - National 19,200.00 0.00 2023-06-02 2023-06-19 2023-06-19 2023-06-21 2025-06-20 or ment ant Selection ntation SCRI/P178125-AZ/019 / Cons Component 3: Civic engage ultant on Technical services ment, social cohesion, monit Pending Impleme / Post Direct Selection Direct - National 8,470.59 0.00 2023-06-05 2023-06-08 2023-06-09 2025-12-31 on "1 C 2.0 Accounting" soft oring and operational suppor ntation ware for Financial Manageme t nt System Page 1 Procurement Plan For Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project A World Bank Financed Project Project ID: P165129 [Procurement Plan Period: First 18 months of the Project] Covering the Period: January 2020 to June 2021 Submitted By Project Management Unit [PMU] Himachal Pradesh Forest Department Government of Himachal Pradesh India 2 3 PROCUREMENT PLAN Country: INDIA Borrower: Government of India on behalf of Government of Himachal Pradesh Project Name: Integrated Development for Source Sustainability and Climate Resilient Rain-fed Agriculture Project Project Implementation Agency: Project Management Unit [PMU], Himachal Pradesh Forestry Department [HPFD], Government of Himachal Pradesh Date of General Procurement Notice: December 18, 2019 Bank’s Approval Date of the Procurement Plan: Original … Revision 1: Revision 2: Date of the Procurement Plan: December 2019 Period covered by this Procurement Plan: January 2020 to June 2021 Applicable Procurement Rules. The Procurement of goods, works, consulting and non-consulting services to be financed by the Loan will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers [dated July 2016; revised November 2017 and August 2018], and the provisions of the Loan Agreement. If there is conflict between government decrees, rules, and regulations and the Bank Procurement Regulations, then Bank’s Procurement Regulations shall prevail. The project will be subject to World Bank Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by IBRD Loans and IDA Credits and Grants [“Anti-Corruption Guidelines”], dated October 15, 2006 and revised in January 2011 and as of July 1, 2016. The project will use the online tool Systematic Tracking of Exchanges in Procurement [STEP] to prepare, clear, and update its procurement plan, for monitoring procurement activities and for communication between the Borrower and the Bank. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under Paragraph 4.4 of the Procurement Regulations are set forth in STEP. Unless otherwise agreed with the World Bank, the World Bank’s Standard Procurement Documents [SPD], Requests for Proposals, and Forms of Consultant Contract will be used. Procurement under national procedures will be carried out based on National Procurement Procedures [NPP] conditions agreed with the Government of India. Procurement estimated at Indian Rupees [INR] 5 Lakhs and above will be submitted through government eProcurement systems provided by NIC 4 www.hptender.gov.in which have been assessed and deemed acceptable by the Bank against Multilateral Development Bank [MDB] requirements. Financial Management [FM] Manual. The FM Manual prepared for the project shall have a separate chapter on Procurement which will provide clear guidance on applicable procurement arrangement, procedures and thresholds, and shall be made available on the project website. Community Operations Manual [COM]. The COM prepared for the project will have clear directives for the community [GPs/individual beneficiaries] with regard to eligible procurement expenditures and agreed procurement arrangements, procedures and thresholds, and shall be made available on the project website. This will serve as a guidebook for procurement, with a view to providing operating instructions and bring in greater transparency and predictability in procurement procedures under the Project. Procurement Arrangements and Profile. Procurement under the Project will be carried out at the central level by the Project Management Unit [PMU] headed by the Chief Project Director [CPD] established for the Project, at the District level by the District Project Officers assisted by the Accounts Assistant at the District Level in each of the 10 District Project Offices [DPOs] located in the Districts covered under the Project [Shimla, Solan, Sirmour, Bilaspur, Hamirpur, Mandi, Kullu, Chamba, Kangra and Una], and by beneficiary GPs [supported by DPOs] at the GP level, in accordance with their approved Gram Panchayat Resource Management Plans [GP-RMP]/MG/OMIF. Officials of the PMU have prior experience of implementing a World Bank financed project and have also undergone training in STEP. GPs will need to be capacitated and provided basic procurement training on applicable procurement procedures and procurement documentation requirements outlined in COM, before initiating their procurements. To meet the readiness requirements of the Department of Economic Affairs [DEA] of the Government of India, the Project has already initiated and awarded contract for critical consultancy package for Environmental and Social Assessment to be retroactively financed by the Bank. The project envisages procurement of low-risk, low-value goods, works and services as below: a. Goods and Non-Consulting Services to be procured under the project are likely to include the following. At State/PMU level, purchase of IT Equipment such laptops, computers, printer, etc., procurement of printing services for IEC, office vehicles, office furniture, etc. are envisaged. At District and GP level, procurement activities will include procurement of Barbed Wire, U/Staple, Tools, Gunny Bags, Vermicompost/ Farm yard Manure, Sand, Seeds, Wooden posts/ poles, Seedlings, Grass tufts, Sign boards/hand prints, seed testing instrument, Seed, Fertilizer, Pesticide, Livestock - Small and Large Ruminants, Agricultural Tools and Implements, equipment, Farm machinery, e.g., power tiller, chaff cutters, pipes, tarpaulins, Medicines, supplements, sprinklers, seedlings, etc. b. Procurement of Minor Civil Works is likely to include the following. At State/ PMU level, procurement of minor civil works will include extension, refurbishment and repair of office buildings, etc. At District and GP level, procurement activities will include procurement of works for construction of Water storage tanks, water channels, vermicompost pits, livestock Mangers, foot bridges, water lifting pumps, GI pipes, accessories, installation of ropeways, Ponds, Check Dams, Subsurface Dykes, Sump Wells etc. and labor contracts for preparing land 5 for nursery, preparing nursery beds, water tank, works of filling gunny bags, sowing of seeds, preparing temporary nursery sheds, watering, hoeing, weeding, , fencing, bush cutting, pit digging, planting seedlings, preparing contour trenches, planting grass tufts, drainage line treatment works, fire management works, allowances and incentives for fire management, Spring development, eradication of exotic weed- lantana, etc. It may be noted that civil works at GP level are demand driven. There are no major civil works contracts envisaged in the project. c. Consultancy Services to be procured under the project are likely to include services for developing a web-based portal for Integrated Financial Management Information System [IFMS], Water Monitoring and Modelling, Value Chain Scoping Studies, Technical Support Study for addressing the needs of Transhumant, M and E, MIS, Baseline Survey, External and Internal Audit, Third Party Verification agent to verify achievement of Disbursement Related Results [DLR]s, need based assessments and studies, individual experts, etc. No consultancy services contracts envisaged at the District/Sub-district levels. The project includes several features of a decentralized, demand-driven project, and activities to be taken up at the community level by selected beneficiaries shall be as per the GP-RMP approved by the PMU of the HP Forestry Department/MG/OMIF. The threshold of procurement activities at community level is expected not to exceed Request for Quotation [RFQ] threshold. Community-level procurement shall follow Community-Driven Development [CDD] arrangements as per the Bank’s Procurement Regulations and as outlined in the Community Operations Manual [COM] currently under preparation. Given other on-going government programs, the activities to be funded following COM shall be identified upfront to avoid double-dipping and will require very close monitoring and oversight. Project Procurement Strategy for Development [PPSD] and Procurement Plan. According to the requirement of the Regulations, a Project Procurement Strategy for Development [PPSD] has been developed, based on which the Procurement Plan for the first 18 months has been prepared. The PPSD describes how procurement in this project will support the Project Development Objective [PDO] and deliver value for money under a risk-based approach. It provides adequate supporting market analysis for the selection methods detailed in the procurement plan. The procurement plan specifies for each contract: [i] a description of the activities/contracts; [ii] selection methods to be applied; [iii] estimated cost; [iv] time schedules; [v] World Bank review requirements; and [vi] any other relevant procurement information. PMU shall submit to the World Bank, for its review and approval, any updates of the procurement plan approved by the World Bank. The project will use Systematic Tracking of Exchanges in Procurement [STEP] system for all its procurement activities carried out at the PMU [Centre] and District levels. Summary from PPSD. The project is preparing its Procurement Strategy document. As per the draft document, the project’s total value is US $100 million of which procurement spend is approximately 80 %. Extensive market analysis has been carried out for procurement packages and decisions on packages are made to ensure adequate participation of bidders. Consultancy contracts are framed based on market research and packaging decided in terms of scope of services and period. Based on the need assessment, the project has decided to 6 use Government e Marketplace [GeM]1 for procurement of Goods up to US $100,000 and as mentioned under the paragraph in the Procurement Plan on National Procurement Procedures. Procurement Capacity Building. Though project staff has past experience of implementing World Bank financed HP Mid-Himalayan Watershed Development Project [HPMHWDP] governed by the Bank’s Procurement Guidelines, however, they need to be exposed to the Procurement Regulations applicable to the Project. HP Forestry Department will be sending key procurement staff of PMU and DPOs to the Indian Institute of Management [IIM], Lucknow or the Administrative Staff College of India [ASCI], Hyderabad from time to time to attend procurement training on World Bank Procurement Framework [PF] applicable to the project. Presently, project staff from PMU and two DPOs will be attending the two-week residential training program on World Bank Procurement Regulations conducted at ASCI, Hyderabad in February 2020. These officials will subsequently provide training to other project staffs prior to implementation of the procurement activities in the project. The PMU/DPOs/APOs will also provide basic procurement training to GPs/Beneficiaries once the Gram Panchayat Resource Management Plan [GP-RMP] is approved by DPO/PMU, and before commencing implementation of GP-RMP. The project officials can also avail of the free Massive Open Online Course on public procurement www.procurementlearning.org offered by the Bank to build their capacity. The Bank had already conducted one training on STEP for PMU officials and will organize STEP training again on need basis for the concerned DPOs staff in near future. Procurement Planning. For each contract to be financed by the Loan, the different procurement methods or consultant selection methods to be used, the need for pre-qualification, estimated costs, prior review requirements, and time frame will be reflected in the Procurement Plan to be agreed between the Borrower and the Bank team. The Procurement Plan will be uploaded in STEP by PMU/DPOs and the approved procurement plan will be disclosed on the project website and Bank’s external website. The procurement plan for the first 18 months of project implementation and all its updates will be submitted to the Bank through STEP, and will lay out the appropriate, fit for purpose market approach and selection methods for procurement of goods, works, non-consulting and consulting services financed by the Bank. It will be updated at least annually or as required to reflect the actual project implementation needs and improvements in institutional capacity. eProcurement. Currently, the Himachal Pradesh Forestry Department of the Government of Himachal Pradesh is using e-procurement system for its procurement. However, PMU housed in the Forestry Department will be carrying out procurement using eProcurement for the first time in the project, therefore, their capacity building needs to be done for eProcurement. The project will make use of Government of India’s National Informatics Centre [NIC] platform assessed by the Bank against Multilateral Development Bank [MDB] requirements for procurements estimated at INR 5 Lakhs and above. Advance Contracting with Retroactive Financing. For effective project implementation and start-up, the project has initiated advance contracting of critical consultancies for Preparation of Environmental and Social Framework [ESF] and Project Implementation Plan [PIP], and procurement of small value goods such 1 https://gem.gov.in/ 7 as tools, gunny bags, seeds, IT equipment and accessories, vehicles, etc.] and works [very small value labor contracts for Development of Nurseries [52 nos.] in 26 clusters in 10 Districts covering 428 GPs. The total value of this spend is approximately 1.2 % of the Bank loan. Payment made by PMU/HPFD for these contracts following World Bank procurement procedures during the 12 months prior to the tentative Loan signing date shall be eligible for retroactive financing. Record Keeping. All records pertaining to award of tenders/selection of consultants, including tender notification/advertisement, register pertaining to sale and receipt of bids, bid/proposal opening minutes, bid/technical and financial evaluation reports, comparative statements, Goods, Receipt Note [GRN] and all correspondence pertaining to bid evaluation, communication sent to/with the Bank in the process, bid securities, and approval of invitation/evaluation of bids/proposals would be maintained by the PMU and at DPO/GP level. Contract Management. The PMU, HPFD will be responsible for overall procurement and contract management under the project. At the Centre, procurement staff will be responsible for contract monitoring and supervision of contracts awarded by PMU. At DPO level, contract monitoring and supervision will be done by technical staff at DPOs/APOs level [Agriculture, Animal Husbandry/Engineering staff of technical wing of DPO level and Forest Extension and Social Extension staff at APO level] to ensure timely delivery of quality outputs from the procurement contracts in the project areas. All payments will be made by DPOs for district and sub-district level procurements after receipt of Goods receipt Note [GRN]. Work Completion Certificates, etc. The Integrated Financial Management Information System [IFMIS] being developed under the Project will facilitate monitoring of various procurement activities in terms of physical and financial achievements on a monthly basis. The day to day monitoring of procurement activities will be done by APOs/DPOs at field level which will be updated in the online web-based system at district level and will be reviewed by PMU at the Centre. Complaint Handling Mechanism. A complaint handling mechanism to address procurement-related complaints under the Project will be developed and implemented by the PMU/DPOs to the satisfaction of the Bank. Upon receipt of complaints, immediate action would be initiated to acknowledge the complaint and to redress it within a reasonable timeframe. All complaints will be addressed at levels higher than the level at which the procurement process was undertaken, or the decision was taken. Any complaint received will also be forwarded to the Bank for information, and the Bank would be kept informed after the complaint is redressed. Leased Assets: Not Applicable Procurement of Secondhand Goods: Not Applicable Domestic Preference: The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement Thresholds and Prior Review Thresholds. The table below describes various procurement methods to be used for activities financed by the Loan. 8 Table 1: Procurement Thresholds Procurement approach and method Thresholds [US$ equivalent] Open International [Goods, IT, and >10 million Non-consulting services] – Request for Bids [RFB] Open National [Goods, IT, and Non- >100,000 and up to 10 million consulting services] – Request for Bids [RFB] National Request for Quotation Up to 100,000 [RFQ] – [Goods/Works/Non- consulting Services] Open International [Works] – >40 million Request for Bids [RFB] Open National [Works] - Request for >100,000 and up to 40 million Bids [RFB] Direct Selection With prior agreement, based on justification Framework Agreement For Goods/Works/Non-consulting services: According to paragraphs 6.57-6.59 of Section VI of the Regulations. For Consulting services: According to paragraph 7.33 of Section VII the Regulations. Force Account In accordance with paragraphs 6.54 and 6.55 of Section VI of the Procurement Regulations, and with prior agreement in Procurement plan with the Bank. Consulting Services [Firms] CQS: As per requirements of paragraphs 7.11 and 7.12 of Section VII of the Regulations. LCS, FBS: in justified cases QCBS, QBS: in all other packages Shortlist of National Consultants Up to 800,000 Procurement prior-review thresholds2. Based on the current procurement risk rating of ‘Moderate’, the World Bank will prior review the following contracts: (a) Works [including turnkey, supply and installation of plant and equipment and PPP]: All contracts more than US $15 million equivalent 2 Determination of whether a contract meets the prior review threshold is based on : (i) the total value of the contract, including all taxes and duties payable under the contract; (ii) a contract whose cost estimate was below the Bank’s prior review threshold is subject to prior review if the price of the lowest evaluated responsive bid (or, in the case of consulting services, the financial offer of the selected firm) exceeds such threshold at the bid evaluation stage; and (iii) in the case of a slice and package arrangement, the prior review threshold is determined based on the aggregate value of individual contracts to be awarded under such arrangement. 9 (b) Goods and Information Technology: All contracts > US $4 million equivalent (c) Non-consulting Services: All contracts > US $4 million equivalent (d) Consulting Services: Firms: All contracts >US $2 million equivalent (e) Consulting Services: Individuals: All contracts > US $400,000 equivalent (f) Direct Selection: The justification of Direct Selection for all contracts The above thresholds are for the initial 18-month implementation period. Based on the procurement performance of the project, these thresholds may be subsequently modified. Even for large-value post review cases, the inputs of the World Bank on technical specifications will be obtained by the project. Irrespective of the thresholds, Terms of Reference shall be prior reviewed by Bank. The prior review thresholds will also be indicated in the Procurement Plan. The Procurement Plan will be subsequently updated annually [or at any other time if required] and will reflect any change in the prior review thresholds. The details of National Procurement Procedures are outlined in the Procurement Plan. Prior review contracts. In the case of contracts subject to prior review, PMU, HPFD/DPOs will seek the World Bank’s no objection before granting/agreeing to: [a] an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; [b] any substantial modification of the scope of Works, goods, IT system; non-consulting services, or consulting services and other significant changes to the terms and conditions of the contract; [c] any variation order or amendment [except in cases of extreme urgency] that, singly or combined with all variation orders or amendments previously issued, increases the original contract amount by more than 15 percent; and [d] the proposed termination of the contract. Complaints received in all prior review cases shall be sent to Bank for review and the response to the complaint in such cases, shall be cleared with the Bank. Complaints with allegations of fraud and corruption, shall be shared with Bank, irrespective of the thresholds. Disclosure of procurement information. The following documents shall be disclosed on the project/state websites: [a] Procurement Plan and its updates; [b] an invitation for bids for procurement of Works, Goods, IT system procurement and non-consulting services; [c] request for expression of interest for selection/hiring of consulting services; [d] contract awards of Works, Goods, IT system procurement and non-consulting services procured following international and national procedures; [e] a list of contracts/purchase orders placed following RFQ [Request for Quotation] procedures on a quarterly basis; [f] a list of contracts following direct contracting [DC] on a quarterly basis; [g] an annual financial and physical progress report of all contracts; and [h] an action taken report on the complaints received on a quarterly basis. The following details shall be sent to the World Bank for publishing on the United Nations Development Business and the World Bank external website: [a] Specific Procurement Notice [i.e., invitation for bids] for procurement of Works, Goods, IT system procurement and non-consulting services using open international procedures; [b] Requests for Expression of Interests above US $800,000; [c] contract award details of all procurement of Works, Goods, IT system procurement and non-consulting services using open international procedure; and [d] a list of contracts/purchase orders placed following DC procedures on a quarterly basis. Further, the implementing agency will also publish on their websites any information required under the provisions of ‘suo moto’ disclosure as specified by the Right to Information Act. 10 National Procurement Procedure Conditions. National competition for the procurement of Works, Goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: I. Only the model bidding documents for National Competitive Procurement [NCP] agreed with the GOI Task Force [and as amended for time to time], shall be used for bidding. II. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. III. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state- owned enterprises, small-scale enterprises or enterprises from any given State. IV. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. V. Government e-Marketplace [GeM] set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations [RFQ] method. VI. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. VII. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. VIII. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. IX. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. X. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social [including sexual exploitation and abuse and gender-based violence], health and safety [“ESHS”] risks and impacts. Oversight and Monitoring by the Bank. All contracts not covered under prior review by the Bank will be subject to post review during implementation support missions and/or special post review missions, including missions by consultants hired by the Bank. The Bank may conduct, at any time, Independent Procurement Reviews [IPRs] of all the contracts financed under the loan. High risk procurements, if any, will be identified for increased procurement and contract management support and indicated in the procurement plan. Bank team will provide additional due diligence and independent review of the contract performance of such identified procurements. 11 Procurement Review by the PMU, HPFD. Independent procurement post review [PPR] with reporting requirements and agreed with the Bank [As per Para 4 of Annex II of the Procurement Regulations] will be undertaken for the project for PMU’s own internal due diligence. PMU will hire PPR consultants as per Terms of Reference and reporting requirements agreed with the Bank to conduct PPR of PMU and DPOs on a half yearly basis. Other Special Selection Arrangements/Requirement Procurement by communities will be governed by the procedures outlined in the Community Operations Manual [COM] currently under preparation and in accordance with Paras 6.52 and 6.53 of Section VI of the Regulations. COM will be disclosed on the Project website. Procurement Plan as per STEP Tables: 12 PROCUREMENT India : Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2020-07-30 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-18 none) Project ID: P165129 GPN Date: 2019-12-19 Project Name: Integrated Project for Source Sustainability and Climate Resilient Rain-fed Agriculture in Himachal Pradesh Loan / Credit No: IBRD / 90410 District Project Office, Bilaspur, Himachal Pradesh Forestry Department Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-DPO, BILASPUR-179223-C W-RFQ / 188 hectare area wil l be covered under Lantana r Component 1. Sustainable L Request for Quota Single Stage - One E 2021-07-1 emoval in different locations IBRD / 90410 and and Water Resource Ma Post Limited 80,731.00 98,720.34 Completed 2020-11-21 2020-11-11 2021-01-20 2021-04-19 tions nvelope 9 by CRS method during Nove nagement mber & December 2020 and Feb March 2020..This involve s multiple contracts of low va lue. IN-DPO, BILASPUR-178938-C W-RFQ / Raising of plantation s is under process ans starte Component 1. Sustainable L d during monsoon period of 2 Request for Quota Single Stage - One E 2021-02-0 IBRD / 90410 and and Water Resource Ma Post Limited 67,074.00 70,599.83 Completed 2020-06-15 2020-07-17 2020-08-10 2020-08-14 020, of different forestry spe tions nvelope 6 nagement cies in 200 hectare area at di fferent location.This involves multiple contracts of low valu e hence limited approach wa s adopted. IN-DPO, BILASPUR-179224-C W-RFQ / Planting of grass see dling along the contour trenc hes in plantation Area . Total Component 1. Sustainable L Request for Quota Single Stage - One E 2020-12-0 143 Hectare will be covered IBRD / 90410 and and Water Resource Ma Post Limited 5,680.00 4,714.30 Completed 2020-08-25 2020-08-20 2020-09-18 2020-11-25 tions nvelope 2 at different location during A nagement ug 20. This involves multiple contracts of low value based on different location, limited approach will be adopted. IN-DPO, BILASPUR-179245-C W-RFQ / Construction of Prim ary Water Harvesting in the shape of Village Ponds (Manu Component 1. Sustainable L Request for Quota Single Stage - One E 2021-04-1 al Excavation) in different loc IBRD / 90410 and and Water Resource Ma Post Limited 139,896.00 0.00 Canceled 2020-09-25 2020-10-17 tions nvelope 5 ations 2020-21. Keeping in vi nagement ew of low value of contracts and availability of perspectiv e bidder, limited market appr oach will be adopted. IN-DPO, BILASPUR-178945-C W-RFQ / Fencing of plantatio n area with wooden fence po st and barbed wire for raising Component 1. Sustainable L Request for Quota Single Stage - One E 2022-01-0 of plantation in the rainy sea IBRD / 90410 and and Water Resource Ma Post Limited 119,430.00 0.00 Canceled 2021-06-12 2021-07-10 tions nvelope 6 son of 2021. The total area w nagement ill be covered approx 155 ha. This involves multiple contra cts of low value, hence limite d approach will be adopted. IN-DPO, BILASPUR-178935-C W-RFQ / Renovation and impr ovement of 44 existing Natu Component 1. Sustainable L ral Water Sources (springs) w Request for Quota Single Stage - One E 2021-06-1 IBRD / 90410 and and Water Resource Ma Post Limited 73,333.00 9,233.63 Completed 2020-10-25 2022-01-19 2020-12-20 2022-02-08 ater bodies in various locatio tions nvelope 8 nagement ns includes multiple contract s of low value and site specifi c contracts. Hence limited m arket approach will be adopt ed. IN-DPO, BILASPUR-179219-C W-RFQ / Raising of Seedling i n Nursery (2021) at different Component 1. Sustainable L Request for Quota Single Stage - One E 2021-10-1 4 locations. Limited approac IBRD / 90410 and and Water Resource Ma Post Limited 22,002.00 8,868.67 Completed 2020-12-20 2020-02-12 2021-02-14 2020-09-01 tions nvelope 2 h will be adopted as the pers nagement pective bidders are available at different locations and als o based on low value contrac t. IN-DPO, BILASPUR-179203-C W-RFQ / Lantana removal in different locations (120 hect are) by CRS method in 2019- Component 1. Sustainable L Request for Quota Single Stage - One E 2020-09-1 20. This involve multiple cont IBRD / 90410 and and Water Resource Ma Post Limited 37,091.00 37,233.92 Completed 2020-06-16 2020-02-13 2020-08-11 2021-04-14 tions nvelope 0 racts and limited approach w nagement as adopted. Prospective bidd ers were available and distan ce between sites was 10 to 6 0 Kilometres at different loca tion. IN-DPO, BILASPUR-178898-G O-RFQ / Site Development of Nurseries (4 Nos) at different locations . The sites were sca Component 1. Sustainable L Request for Quota Single Stage - One E 2021-01-3 ttered and distance varies fro IBRD / 90410 and and Water Resource Ma Post Limited 16,047.00 15,056.19 Completed 2020-07-12 2020-01-06 2020-08-04 2020-06-26 tions nvelope 1 m 10-60 km . Keeping in vie nagement w of low value and availabilit y of perspective bidder, limit ed market approach was ado pted. Work completed. IN-DPO, BILASPUR-178909-G O-RFQ / Raising of Seedling i n four Nurseries for plantatio n. Four different contract we Component 1. Sustainable L Request for Quota Single Stage - One E 2020-10-0 re awarded during march 20 IBRD / 90410 and and Water Resource Ma Post Limited 44,004.00 30,814.81 Completed 2020-07-12 2020-02-12 2020-09-06 2020-03-14 tions nvelope 6 20. The limited market appro nagement ach was adopted. because of availability of perspective bid ders and value of each contr act was below threshold. Page 1 IN-DPO, BILASPUR-178913-C W-RFQ / Fencing of plantatio n area with wooden fence po st and barbed wire in 200 He Component 1. Sustainable L Request for Quota Single Stage - One E 2020-10-0 ctare. It involves multiple con IBRD / 90410 and and Water Resource Ma Post Limited 146,089.00 103,657.36 Completed 2020-06-25 2020-06-16 2020-07-29 2020-07-10 tions nvelope 2 tracts. Limited approach was nagement adopted as the perspective b idders are available at differe nt locations and based on lo w value of each contract. IN-DPO, BILASPUR-178919-C W-RFQ / Contour trenching i n plantation including grass s Component 1. Sustainable L Request for Quota Single Stage - One E 2021-01-1 eedlings in 142 hectare area IBRD / 90410 and and Water Resource Ma Post Limited 23,856.00 29,469.55 Completed 2020-11-06 2020-08-20 2020-11-20 2020-11-27 tions nvelope 9 during Sep 2020. This involv nagement e multiple contracts of low va lue and limited market appro ach will be adopted. IN-DPO, BILASPUR-236000-C W-RFQ / Raising of Seedling i n four Nurseries for plantatio Component 1. Sustainable L n. Four different contract will Request for Quota Single Stage - One E Other (with field f 2022-08-3 IBRD / 90410 and and Water Resource Ma Post Limited 7,440.00 1,118.37 Completed 2021-07-15 2021-10-28 2021-08-03 2022-01-14 be awarded. The limited mar tions nvelope or explanation) 1 nagement ket approach was adopted, b ecause of availability of pers pective bidders and value of each contract was below thre shold IN-DPO, BILASPUR-236002-C W-RFQ / Maintenance of See dling in four Nurseries for pla ntation. Four different contra Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-3 ct will be awarded during m IBRD / 90410 and and Water Resource Ma Post Limited 25,640.00 17,521.86 Completed 2021-06-30 2021-11-13 2021-07-17 2022-03-29 tions nvelope or explanation) 1 arch 2021. The limited marke nagement t approach was adopted. bec ause of availability of perspe ctive bidders and value of ea ch contract was below thresh old IN-DPO, BILASPUR-236004-C W-RFQ / Procurement of Barb ed wire and U/Nails for Adva Component 1. Sustainable L nce work for Plantation 2021- Request for Quota Single Stage - One E Other (with field f 2021-08-1 IBRD / 90410 and and Water Resource Ma Post Limited 30,096.00 27,732.71 Completed 2021-06-10 2021-07-21 2021-06-27 2021-08-04 22. The procurement will be tions nvelope or explanation) 1 nagement done after approval. Limited market approach will be ado pted because of low value an d availability of bidders. IN-DPO, BILASPUR-236007-C W-RFQ / Procurement of Woo den Fence Post for Advance Component 1. Sustainable L work of Plantation 2021-22. T Request for Quota Single Stage - One E Other (with field f 2021-08-0 IBRD / 90410 and and Water Resource Ma Post Limited 38,400.00 18,168.80 Completed 2021-06-10 2021-07-22 2021-06-25 2021-08-18 he procurement may be com tions nvelope or explanation) 9 nagement pleted before 30th June 2021 . Limited market approach w as adopted because of low v alue and availability of bidde rs. IN-DPO, BILASPUR-236010-C W-RFQ / Advance work of pla ntation in 180 Hectare area i Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2021-12-2 n different locations, it involv IBRD / 90410 and and Water Resource Ma Post Limited 49,661.00 54,059.73 Completed 2021-06-14 2021-07-13 2021-06-29 2021-08-05 tions nvelope or explanation) 6 es Fencing of area and pit wo nagement rk for plants. the activity will take place in July 2021 to Se ptember 2021. IN-DPO, BILASPUR-236011-C W-RFQ / Raising of plantation s in 180 hectare area during Component 1. Sustainable L monsoon period of 2021, of d Request for Quota Single Stage - One E Other (with field f 2022-01-1 IBRD / 90410 and and Water Resource Ma Post Limited 86,200.00 59,098.12 Completed 2021-07-01 2021-06-17 2021-07-17 2021-07-14 ifferent forestry species in 18 tions nvelope or explanation) 3 nagement 0 hectare area at different lo cations. This involves multipl e contracts of low value henc e limited approach was adop ted IN-DPO, BILASPUR-236239-C W-RFQ / GI Wire for Crate wir e Structure to be constructed Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-01-2 in 500 CUM3 different locatio IBRD / 90410 and and Water Resource Ma Post Limited 4,618.00 5,032.68 Completed 2021-07-12 2021-08-13 2021-07-31 2021-10-12 tions nvelope or explanation) 7 n during 2021. This involves nagement multiple contracts of low valu e based on different location, limited approach will be adop ted. IN-DPO, BILASPUR-236242-C W-RFQ / Maintt. Lantana in di fferent locations (234 hectar e) by CRS Method in 2020-2 Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-05-1 1. This involve multiple contr IBRD / 90410 and and Water Resource Ma Post Limited 15,742.00 14,102.18 Completed 2021-10-16 2021-12-10 2021-11-15 2022-01-08 tions nvelope or explanation) 4 acts and limited approach to nagement be adopted. Prospective bidd ers invited and distance betw een sites is 10 to 60 Kilometr es at different location. IN-DPO, BILASPUR-236244-C W-RFQ / 2nd year Maintt. Lan tana in different locations (12 0 hectare) by CRS method in Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-05-1 2019-20. This involve multipl IBRD / 90410 and and Water Resource Ma Post Limited 4,709.00 5,871.59 Completed 2021-10-20 2021-12-28 2021-11-15 2022-02-15 tions nvelope or explanation) 4 e contracts and limited appro nagement ach to be adopted. Prospecti ve bidders invited and distan ce between sites is 10 to 60 Kilometers at different locati on IN-DPO, BILASPUR-236245-C W-RFQ / Construction of Prim ary Water Harvesting in the s hape of Village Ponds (Mecha Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-01-3 nical Excavation) in different IBRD / 90410 and and Water Resource Ma Post Limited 41,200.00 19,044.31 Completed 2021-07-12 2021-09-10 2021-08-04 2022-02-20 tions nvelope or explanation) 1 locations 2021-22. Keeping i nagement n view of low value of contra cts and availability of perspe ctive bidder, limited market a pproach will be adopted. IN-DPO, BILASPUR-236246-C W-RFQ / Construction of CC C heck Dams to store for dom estic and wild animals use an Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-05-3 d irrigation facilities for farm IBRD / 90410 and and Water Resource Ma Post Limited 63,555.00 29,016.35 Completed 2021-07-20 2022-01-11 2021-08-11 2022-02-05 tions nvelope or explanation) 1 ers in 2021-22. . Keeping in v nagement iew of low value of contracts and availability of perspectiv e bidder, limited market appr oach will be adopted. Page 2 IN-DPO, BILASPUR-236248-C W-RFQ / Construction of Wat er Harvesting Structure in th Component 1. Sustainable L e shape of Earthen Dams in Request for Quota Single Stage - One E Other (with field f 2022-05-3 IBRD / 90410 and and Water Resource Ma Post Limited 30,720.00 0.00 Canceled 2021-07-20 2021-08-12 different locations 2021-22. tions nvelope or explanation) 1 nagement Keeping in view of low value of contracts and availability o f perspective bidder, limited market approach will be ado pted. IN-DPO, BILASPUR-236250-C W-RFQ / Construction of Wat er Harvesting Structure in th Component 1. Sustainable L e shape of Masonry Dams in Request for Quota Single Stage - One E Other (with field f 2022-02-1 IBRD / 90410 and and Water Resource Ma Post Limited 42,336.00 0.00 Canceled 2021-07-27 2021-08-14 different locations 2021-22. tions nvelope or explanation) 0 nagement Keeping in view of low value of contracts and availability o f perspective bidder, limited market approach will be ado pted. IN-DPO, BILASPUR-236252-C W-RFQ / Construction of Wat er Harvesting Structure in th Component 1. Sustainable L e shape of Sub Surface Dyke Request for Quota Single Stage - One E Other (with field f 2022-02-2 IBRD / 90410 and and Water Resource Ma Post Limited 62,400.00 0.00 Canceled 2021-08-10 2021-08-31 s in different locations 2021- tions nvelope or explanation) 7 nagement 22. Keeping in view of low va lue of contracts and availabili ty of perspective bidder, limit ed market approach will be a dopted. IN-DPO, BILASPUR-236258-C W-RFQ / Construction of Wat er Distribution Structure in th e shape of Minor & Lift Irrigat Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-03-1 ion Schemes in different loca IBRD / 90410 and and Water Resource Ma Post Limited 53,072.00 5,390.89 Completed 2021-08-25 2022-01-31 2021-09-20 2022-02-20 tions nvelope or explanation) 9 tions 2021-22. Keeping in vie nagement w of low value of contracts a nd availability of perspective bidder, limited market appro ach will be adopted. IN-DPO, BILASPUR-236262-C W-RFQ / Construction of Wat er Storage Structure in the s Component 2. Improved Agri hape of Water Tanks in differ Request for Quota Single Stage - One E Other (with field f 2022-02-1 IBRD / 90410 cultural Productivity and Val Post Limited 96,080.00 56,337.07 Completed 2021-07-22 2021-09-22 2021-08-19 2022-03-17 ent locations 2021-22. Keepi tions nvelope or explanation) 5 ue Addition ng in view of low value of con tracts and availability of pers pective bidder, limited marke t approach will be adopted. IN-DPO, BILASPUR-236753-C W-RFQ / Construction of Wat er Harvesting Structure in th Component 1. Sustainable L e shape of Sump Well in diffe Request for Quota Single Stage - One E Other (with field f 2022-02-0 IBRD / 90410 and and Water Resource Ma Post Limited 32,304.00 0.00 Canceled 2021-07-15 2021-08-07 rent locations 2021-22. Keepi tions nvelope or explanation) 3 nagement ng in view of low value of con tracts and availability of pers pective bidder, limited marke t approach will be adopted. IN-DPO, BILASPUR-236763-C W-RFQ / Construction of Wat er Harvesting Structure for w Component 2. Improved Agri ater Distribution in the shape Request for Quota Single Stage - One E Other (with field f 2022-03-0 IBRD / 90410 cultural Productivity and Val Post Limited 93,333.00 0.00 Canceled 2021-08-17 2021-09-09 of Tank in different locations tions nvelope or explanation) 8 ue Addition 2021-22. Keeping in view of l ow value of contracts and av ailability of perspective bidde r, limited market approach wi ll be adopted. IN-DPO, BILASPUR-236764-C W-RFQ / Construction of Mark et Linkage system to farmers Component 2. Improved Agri the shape of Foot Bridges in Request for Quota Single Stage - One E Other (with field f 2022-04-0 IBRD / 90410 cultural Productivity and Val Post Limited 60,000.00 14,021.69 Completed 2021-09-17 2022-02-11 2021-10-08 2022-03-01 different locations 2021-22. tions nvelope or explanation) 6 ue Addition Keeping in view of low value of contracts and availability o f perspective bidder, limited market approach will be ado pted. IN-DPO, BILASPUR-207423-G O-RFQ / Demonstration plots of Wheat and Peas seed, 20 demonstration plot of Wheat Component 2. Improved Agri Request for Quota Single Stage - One E Other (with field f 2021-12-1 and 20 Demonstration plot of IBRD / 90410 cultural Productivity and Val Post Limited 1,025.00 483.13 Completed 2021-05-28 2020-10-17 2021-06-18 2020-11-11 tions nvelope or explanation) 5 Peas for both APO Berthin an ue Addition d APO Ghumarwin, Total 80 n os. of demonstration plot whi ch includes seed, fertilizers a nd weedicides for the crop. IN-DPO, BILASPUR-241534-C W-RFQ / Maintenance of plan tations in 174.5 hectare area Component 1. Sustainable L in monsoon period of 2021, o Request for Quota Single Stage - One E Other (with field f 2022-01-1 IBRD / 90410 and and Water Resource Ma Post Limited 19,885.00 14,960.50 Completed 2021-06-30 2021-07-13 2021-07-15 2021-08-05 f different forestry species in tions nvelope or explanation) 1 nagement 174.5 hectare area at differe nt locations. This involves m ultiple contracts of low value hence limited approach was adopted IN-DPO, BILASPUR-241535-C W-RFQ / Construction of Wat er Harvesting Structure for w ater Distribution in the shape Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-04-2 of small Kuhals in different l IBRD / 90410 and and Water Resource Ma Post Limited 16,000.00 0.00 Canceled 2021-09-04 2021-10-25 tions nvelope or explanation) 3 ocations 2021-22. Keeping in nagement view of low value of contract s and availability of perspecti ve bidder, limited market ap proach will be adopted. IN-DPO, BILASPUR-241536-C W-RFQ / Procurement of High Efficiency Micro Irrigation in Component 1. Sustainable L the shape of Sprinklers for fa Request for Quota Single Stage - One E Other (with field f 2022-04-1 IBRD / 90410 and and Water Resource Ma Post Limited 8,000.00 0.00 Canceled 2021-08-25 2021-10-13 rmers during 2021-22. Keepi tions nvelope or explanation) 1 nagement ng in view of low value of con tracts and availability of pers pective bidder, limited marke t approach will be adopted. IN-DPO, BILASPUR-178931-C W-RFQ / Treatment of Draina ge line by constructing veget Component 1. Sustainable L ative check barriers, dry ston Request for Quota Single Stage - One E Other (with field f 2022-03-1 IBRD / 90410 and and Water Resource Ma Post Open - National 65,270.00 27,052.32 Completed 2021-07-17 2021-09-11 2022-03-17 e check barriers & create wir tions nvelope or explanation) 0 nagement e check barriers. This include s 100-150 site specific contra cts of low value hence limite d market approach will be ad opted. Page 3 IN-DPO, BILASPUR-204294-C W-RFQ / Maintt. Lantana in d ifferent locations (120 hecta re) by CRS method in 2019-2 Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-02-2 0. This involve multiple contr IBRD / 90410 and and Water Resource Ma Post Open - National 6,912.00 6,867.51 Completed 2021-07-05 2021-08-30 2020-12-29 tions nvelope or explanation) 6 acts and limited approach to nagement be adopted. Prospective bidd ers invited and distance betw een sites is 10 to 60 Kilometr es at different location. IN-DPO, BILASPUR-242767-C W-RFQ / Procurement of Woo den Fence Post for Fencing w Component 1. Sustainable L ork of Additional 45 Hect Are Request for Quota Single Stage - One E Other (with field f 2022-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 9,600.00 0.00 Canceled 2021-07-15 2021-08-02 a Taken for Plantation 2021- tions nvelope or explanation) 9 nagement 22. The procurement will be done after approval. For this activity separate RFQs will be invited for each APO. IN-DPO, BILASPUR-242771-C W-RFQ / Fencing of plantatio n area with wooden fence po Component 1. Sustainable L st and barbed wire in 45 Hect Request for Quota Single Stage - One E Other (with field f 2022-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 12,400.00 10,147.11 Completed 2021-07-15 2021-07-31 2021-08-22 are. It involves multiple contr tions nvelope or explanation) 7 nagement acts. For this activity separat e RFQs will be invited for eac h work and estimated cost of each RFQ will not exceed thr eshold limit. IN-DPO, BILASPUR-242774-C W-RFQ / Raising of plantation s is under process and starte Component 1. Sustainable L d during monsoon period of 2 Request for Quota Single Stage - One E Other (with field f 2022-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 13,460.00 12,367.76 Completed 2021-07-12 2021-07-27 2021-08-06 021, of different forestry spe tions nvelope or explanation) 3 nagement cies in additional 45 Hect hec tare area at different location s. This involves multiple cont racts of low value. IN-DPO, BILASPUR-243405-C W-RFQ / Contour trenching in plantation including grass se edlings in 115 hectare area d Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-01-2 uring August 2021. This invol IBRD / 90410 and and Water Resource Ma Post Open - National 20,180.00 20,786.02 Completed 2021-07-15 2021-08-02 2021-08-22 tions nvelope or explanation) 9 ves multiple contracts of low nagement value. Prospective bidders wi ll be invited and distance bet ween sites is 10 to 60 Kilome tres at different location. IN-DPO, BILASPUR-243407-C W-RFQ / Sowing of grass see dling along the contour trenc Component 1. Sustainable L hes in plantation Area. Total Request for Quota Single Stage - One E Other (with field f 2022-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 2,800.00 4,312.54 Completed 2021-07-15 2021-08-02 2021-08-22 70 Hectare will be covered at tions nvelope or explanation) 9 nagement different location during Aug 2021. Prospective bidders inv ited and distance between sit es is 10 to 60 Kilometres at d ifferent location. IN-DPO, BILASPUR-243409-C W-RFQ / Grass tufts Planting i n Drainage Line Areas at diff erent locations. Total area wi Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-01-2 ll be covered 17.5 hectares. IBRD / 90410 and and Water Resource Ma Post Open - National 2,240.00 2,287.72 Completed 2021-07-15 2021-08-02 2021-08-22 tions nvelope or explanation) 9 This involves multiple contra nagement cts of low value. Prospective bidders will be invited and di stance between sites is 10 to 60 Kilometres at diffe IN-DPO, BILASPUR-260568-C W-RFQ / Demonstration of Ve rmin Compositing Pits under Component 1. Sustainable L Climate Smart Agriculture for Request for Quota Single Stage - One E Other (with field f 2022-08-3 IBRD / 90410 and and Water Resource Ma Post Open - National 12,000.00 0.00 Canceled 2022-01-12 2022-03-04 the farmers of the Project Ar tions nvelope or explanation) 1 nagement eas of the District in different locations 2021-22. Keeping i n view of low value, open ma rket approach will be adopte d. IN-DPO, BILASPUR-260569-C W-RFQ / Eradication of exotic species Lantana in the month Component 1. Sustainable L of December 2021 to March Request for Quota Single Stage - One E Other (with field f 2022-08-0 IBRD / 90410 and and Water Resource Ma Post Open - National 46,440.00 37,148.35 Completed 2021-12-28 2022-02-03 2022-03-07 2022 Total area 100 Hectare tions nvelope or explanation) 2 nagement s. Cleaning of Lantana by (CR S Method) 1st cut, 2nd cut 3r d cut (Sprouts) 3 times in ye ar upto March 2023. IN-DPO, BILASPUR-260567-C W-RFQ / Construction of Roof Rain Water Harvesting Struct ure for Rain Water Storage T Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-10-0 ank for Community in in diffe IBRD / 90410 and and Water Resource Ma Post Open - National 20,000.00 0.00 Canceled 2022-03-15 2022-04-08 tions nvelope or explanation) 5 rent locations 2021-22. Keepi nagement ng in view of low value of con tracts and availability of pers pective bidder, open market approach will be adopted. IN-DPO, BILASPUR-293967-C W-RFQ / Procurement of work s for planting of 50 hect. are Component 1. Sustainable L a to be planted in rainy seas Request for Quota Single Stage - One E Other (with field f 2022-12-2 IBRD / 90410 and and Water Resource Ma Post Open - National 16,400.00 7,377.32 Signed 2022-06-06 2022-06-30 2022-08-24 on 2022. The procurement wi tions nvelope or explanation) 7 nagement ll be done from open market, keeping in view of low value of contracts and availability o f open market approach will be adopted. IN-DPO, BILASPUR-293968-C W-RFQ / Procurement for fen cing works of 50 hect. area t Component 1. Sustainable L o be planted in rainy season Request for Quota Single Stage - One E Other (with field f 2022-12-1 IBRD / 90410 and and Water Resource Ma Post Open - National 20,000.00 7,184.99 Signed 2022-06-03 2022-06-22 2022-07-30 2022. The procurement will b tions nvelope or explanation) 9 nagement e done from open market, ke eping in view of low value of contracts and availability of o pen market approach will be adopted. IN-DPO, BILASPUR-293969-C W-RFQ / Maintenance of 174. 5 hectare area of plantation Component 1. Sustainable L during rainy season 2022. Th Request for Quota Single Stage - One E Other (with field f 2022-12-1 IBRD / 90410 and and Water Resource Ma Post Open - National 19,285.00 12,987.64 Signed 2022-06-03 2022-06-22 2022-07-20 e maintenance of plantation tions nvelope or explanation) 9 nagement will be done rainy season 20 22, keeping in view of low val ue of contracts and availabili ty of open market approach will be adopted. Page 4 IN-DPO, BILASPUR-293970-C W-RFQ / 1st year Maintenanc e of 227 hectare area of plan tation during rainy season 20 Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2022-12-1 22. The maintenance of plant IBRD / 90410 and and Water Resource Ma Post Open - National 7,240.00 17,944.57 Signed 2022-06-03 2022-06-22 2022-07-20 tions nvelope or explanation) 9 ation will be done rainy seas nagement on 2022, keeping in view of l ow value of contracts and av ailability of open market appr oach will be adopted. IN-DPO, BILASPUR-293971-C W-RFQ / Preparation of trenc hes in contours approximatel y 50 hect area in the plantati Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-01-0 on area planted during rainy IBRD / 90410 and and Water Resource Ma Post Open - National 9,250.00 0.00 2022-06-20 2022-10-03 2022-07-07 tions nvelope or explanation) mentation 3 season 2022 . The maintena nagement nce of plantation will be done rainy season 2022, keeping i n view of low value of contra cts and availability of open m arke IN-DPO, BILASPUR-293972-C W-RFQ / Sowing of grass app roximately 50 hect area in th e plantation area planted dur Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2022-12-2 ing rainy season 2022 . The g IBRD / 90410 and and Water Resource Ma Post Open - National 2,030.00 0.00 2022-06-03 2022-10-03 2022-06-30 tions nvelope or explanation) mentation 7 rass will be sown in rainy sea nagement son approximately 50 hect. a rea during 2022, keeping in v iew of low value of contracts and availability of open mark et IN-DPO, BILASPUR-293974-C W-RFQ / Eradication of exotic species Lantana in the month Component 1. Sustainable L of November 2022 to March Request for Quota Single Stage - One E Other (with field f Under Imple 2023-04-3 IBRD / 90410 and and Water Resource Ma Post Open - National 47,565.00 0.00 2022-10-12 2023-01-19 2022-11-01 2023 Total area 100 Hectare tions nvelope or explanation) mentation 0 nagement s. Cleaning of Lantana by (CR S Method) 1st cut, 2nd cut 3r d cut (Sprouts) 3 times in ye ar upto March 2023. IN-DPO, BILASPUR-293976-C W-RFQ / 1st year maintenanc e eradication of exotic specie Component 1. Sustainable L s Lantana in the month of No Request for Quota Single Stage - One E Other (with field f Under Imple 2023-04-3 IBRD / 90410 and and Water Resource Ma Post Open - National 6,460.00 0.00 2022-10-12 2023-01-19 2022-11-01 vember 2022 to March 2023 tions nvelope or explanation) mentation 0 nagement Total area 100 Hectares. Cle aning of Lantana by (CRS Me thod) 1st cut, 2nd cut 3rd cut (Sprouts) 3 times in year upt o March 2025. IN-DPO, BILASPUR-293977-C W-RFQ / 2nd year maintenan ce eradication of exotic speci Component 1. Sustainable L es Lantana in the month of N Request for Quota Single Stage - One E Other (with field f Under Imple 2023-04-3 IBRD / 90410 and and Water Resource Ma Post Open - National 15,475.00 0.00 2022-10-12 2023-01-19 2022-11-01 ovember 2022 to March 202 tions nvelope or explanation) mentation 0 nagement 3 Total area 234 Hectares. Cl eaning of Lantana by (CRS M ethod) 1st cut, 2nd cut 3rd c ut (Sprouts) 3 times in year u pto March 2024. IN-DPO, BILASPUR-293978-C W-RFQ / 3rd year maintenan ce eradication of exotic speci Component 1. Sustainable L es Lantana in the month of N Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-04-3 IBRD / 90410 and and Water Resource Ma Post Open - National 4,710.00 0.00 2022-10-12 2022-11-01 ovember 2022 to March 202 tions nvelope or explanation) lementation 0 nagement 3 Total area 120 Hectares. Cl eaning of Lantana by (CRS M ethod) 1st cut, 2nd cut 3rd c ut (Sprouts) 3 times in year u pto March 2023. IN-DPO, BILASPUR-293981-C W-RFQ / Construction of crat e wire check barriers for drai nage line treatment during 2 Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-04-0 022-23. These structure are t IBRD / 90410 and and Water Resource Ma Post Open - National 34,050.00 0.00 2022-09-12 2022-10-04 tions nvelope or explanation) mentation 2 o be constructed at different nagement locations of various GPs unde r Project . Keeping in view of low value of contracts and av ailability of perspective bid IN-DPO, BILASPUR-293982-C W-RFQ / Construction of Dry Stone check barriers for drai Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-04-0 nage line treatment during 2 IBRD / 90410 and and Water Resource Ma Post Open - National 51,520.00 0.00 2022-09-12 2022-10-04 tions nvelope or explanation) lementation 2 022-23. Keeping in view of lo nagement w value of contracts and avai lability of perspective bidder, open market approach will b e adopted. IN-DPO, BILASPUR-293983-C W-RFQ / Construction of vege tative check barriers for drai Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-04-0 nage line treatment during 2 IBRD / 90410 and and Water Resource Ma Post Open - National 3,200.00 0.00 2022-09-12 2022-10-04 tions nvelope or explanation) lementation 2 022-23. Keeping in view of lo nagement w value of contracts and avai lability of perspective bidder, open market approach will b e adopted. IN-DPO, BILASPUR-293997-C W-RFQ / Construction of Roof Rain Water Tank for commun Component 1. Sustainable L ity at different location in diff Request for Quota Single Stage - One E Other (with field f 2022-12-1 IBRD / 90410 and and Water Resource Ma Post Open - National 49,150.00 0.00 Canceled 2022-05-28 2022-06-16 erent GPs of the Project durin tions nvelope or explanation) 3 nagement g 2022-23. Keeping in view o f low value of contracts and a vailability of perspective bidd er, open market approach wil l be adopted. IN-DPO, BILASPUR-294270-C W-RFQ / Construction of foot bridges for providing market Component 1. Sustainable L linkages to farmers during 20 Request for Quota Single Stage - One E Other (with field f 2023-03-0 IBRD / 90410 and and Water Resource Ma Post Open - National 60,000.00 0.00 Canceled 2022-08-12 2022-09-03 22-23. These structures will b tions nvelope or explanation) 2 nagement e constructed in various GPs under Project. Keeping in vie w of low value of contracts o pen market approach will be adopted. IN-DPO, BILASPUR-294281-C W-RFQ / Construction of Man gers for animal feeding at dif Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-04-1 ferent location in different GP IBRD / 90410 and and Water Resource Ma Post Open - National 6,000.00 0.00 2022-10-02 2022-10-21 tions nvelope or explanation) lementation 9 s of the Project during 2022- nagement 23. Keeping in view of low va lue of contracts, open market approach will be adopted. Page 5 IN-DPO, BILASPUR-293985-C W-RFQ / Construction of CC c heck Dams for Primary Water Harvesting at different locati Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-03-0 on in different GPs of the Proj IBRD / 90410 and and Water Resource Ma Post Open - National 96,480.00 0.00 Canceled 2022-08-17 2022-09-08 tions nvelope or explanation) 7 ect during 2022-23. Keeping nagement in view of low value of contra cts and availability of perspe ctive bidder, open market ap proach will be adopted. IN-DPO, BILASPUR-293990-C W-RFQ / Construction of Mak howal type Structure for Prim Component 1. Sustainable L ary Water Harvesting at diffe Request for Quota Single Stage - One E Other (with field f 2023-01-1 IBRD / 90410 and and Water Resource Ma Post Open - National 84,993.00 0.00 Canceled 2022-06-30 2022-07-21 rent location in different GPs tions nvelope or explanation) 7 nagement of the Project during 2022-23 . There will be 8-10 contracts in single RFQ by adopting op en market approach . IN-DPO, BILASPUR-293995-C W-RFQ / Construction of Wat er Tanks for Secondary Wate r Harvesting Structure Lift sc Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-1 heme at different location in IBRD / 90410 and and Water Resource Ma Post Open - National 72,000.00 0.00 2022-09-01 2022-10-02 2022-09-20 tions nvelope or explanation) mentation 9 different GPs of the Project d nagement uring 2022-23. Low value of multiple contracts and availa bility of perspective bidder o pen market approach adopt ed. IN-DPO, BILASPUR-293988-C W-RFQ / Construction of Mas onry Dams for Primary Water Harvesting at different locati Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f 2023-03-0 on in different GPs of the Proj IBRD / 90410 and and Water Resource Ma Post Open - National 94,960.00 0.00 Canceled 2022-08-12 2022-09-02 tions nvelope or explanation) 1 ect during 2022-23. Keeping nagement in view of low value of contra cts and availability of perspe ctive bidder, open market ap proach will be adopted. IN-DPO, BILASPUR-293989-C W-RFQ / Construction of Grav ity Check Dams for Primary Water Harvesting at different Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-2 location in different GPs of th IBRD / 90410 and and Water Resource Ma Post Open - National 63,333.00 0.00 2022-09-03 2023-02-27 2022-09-24 tions nvelope or explanation) mentation 3 e Project during 2022-23. Ke nagement eping in view of low value of contracts and availability of p erspective bidder, open mark et approach will be adopted. IN-DPO, BILASPUR-293991-C W-RFQ / Construction of Larg e Storage Structures for Prim Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-2 ary Water Harvesting at diffe IBRD / 90410 and and Water Resource Ma Post Open - National 60,000.00 0.00 2022-09-01 2023-02-06 2022-09-22 tions nvelope or explanation) mentation 1 rent location in different GPs nagement of the Project during 2022-23 . The procurement will be do ne by adopting open market approach. IN-DPO, BILASPUR-293992-C W-RFQ / Construction of Wat er Tanks for Secondary Wate Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-1 r Harvesting Structure Gravit IBRD / 90410 and and Water Resource Ma Post Open - National 26,667.00 0.00 2022-09-01 2023-02-06 2022-09-20 tions nvelope or explanation) mentation 9 y scheme at different locatio nagement n in different GPs of the Proje ct during 2022-23 for irrigati on purpose to the farmers gr oups. IN-DPO, BILASPUR-293984-C W-RFQ / Construction of Cem ent Concrete checks barriers Component 1. Sustainable L for drainage line treatment d Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-04-0 IBRD / 90410 and and Water Resource Ma Post Open - National 48,280.00 0.00 2022-09-17 2022-10-09 uring 2022-23. Keeping in vie tions nvelope or explanation) lementation 7 nagement w of low value of contracts a nd availability of perspective bidder, open market approac h will be adopted. IN-DPO, BILASPUR-310104-C W-RFQ / Construction of Wat er Pond for Primary Water Ha Component 1. Sustainable L rvesting at different location Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-02-0 IBRD / 90410 and and Water Resource Ma Post Open - National 49,440.00 0.00 2022-08-30 2022-09-16 of the Project. Keeping in vie tions nvelope or explanation) lementation 8 nagement w of low value of contracts a nd availability of perspective bidders, open market approa ch will be adopted. IN-DPO, BILASPUR-310381-C W-RFQ / Construction of Roof Rain Water Tank for commun Component 1. Sustainable L ity at different location in diff Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-3 IBRD / 90410 and and Water Resource Ma Post Open - National 45,870.00 0.00 2022-09-16 2023-02-06 2022-10-02 erent GPs of the Project. Kee tions nvelope or explanation) mentation 1 nagement ping in view of low value of c ontracts and availability of p erspective bidders, open mar ket approach will be adopted . IN-DPO, BILASPUR-311240-C W-RFQ / Construction of Mak howal type Structure for Prim Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-04-0 ary Water Harvesting at diffe IBRD / 90410 and and Water Resource Ma Post Open - National 45,000.00 0.00 2022-09-14 2023-02-06 2022-10-03 tions nvelope or explanation) mentation 1 rent location in different GPs nagement of the Project. There will be 8 -10 contracts in single RFQ b y adopting open market appr oach . IN-DPO, BILASPUR-311241-C W-RFQ / Construction of Mas onry Dams for Primary Water Component 1. Sustainable L Harvesting at different locati Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-1 IBRD / 90410 and and Water Resource Ma Post Open - National 26,500.00 0.00 2022-09-01 2023-02-06 2022-09-17 on in different GPs of the Proj tions nvelope or explanation) mentation 6 nagement ect. Keeping in view of low v alue of contracts and availabi lity of perspective bidder, op en market approach will be a dopted. IN-DPO, BILASPUR-311242-C W-RFQ / Construction of CC c heck Dams for Primary Water Component 1. Sustainable L Harvesting at different locati Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-1 IBRD / 90410 and and Water Resource Ma Post Open - National 63,480.00 0.00 2022-09-01 2023-01-21 2022-09-16 on in different GPs of the Proj tions nvelope or explanation) mentation 5 nagement ect. Keeping in view of low v alue of contracts and availabi lity of perspective bidders, o pen market approach will be adopted. Page 6 IN-DPO, BILASPUR-311243-C W-RFQ / Construction of foot bridges for providing market linkages to farmers for their Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2023-03-3 produce from feilds. These st IBRD / 90410 and and Water Resource Ma Post Open - National 62,500.00 0.00 2022-09-12 2022-10-01 tions nvelope or explanation) lementation 0 ructures will be constructed i nagement n various GPs under Project. Keeping in view of low value of contracts open market app roach will be adopted. IN-DPO, BILASPUR-311286-C W-RFQ / Construction of Linin g of traditional irrigation Cha Component 1. Sustainable L nnels for irrigation at differe Request for Quota Single Stage - One E Other (with field f Under Imple 2023-03-2 IBRD / 90410 and and Water Resource Ma Post Open - National 30,200.00 0.00 2022-09-06 2023-02-06 2022-09-24 nt location in different GPs of tions nvelope or explanation) mentation 3 nagement the Project. Keeping in view of low value of contracts and availability of perspective bid der, open market approach w ill be adopted. IN-DPO, BILASPUR-342623-G O-RFQ / Raising of Seedling i n Nursery (2023) at different Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-10-1 4 locations. Keeping in view IBRD / 90410 and and Water Resource Ma Post Open - National 10,800.00 0.00 2023-03-06 2023-03-23 2023-04-14 tions nvelope or explanation) mentation 1 of low value of contracts and nagement availability of perspective bid der, open market approach w ill be adopted. IN-DPO, BILASPUR-357542-C W-RFQ / Management of exot Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2024-03-1 ic species i.e. eradication of l IBRD / 90410 and and Water Resource Ma Post Open - National 62,000.00 0.00 2023-05-06 2023-06-25 tions nvelope or explanation) mentation 5 antana and others invasive al nagement ien species during 2023-24 a rea approximately 95 Hac. IN-DPO, BILASPUR-360091-C Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-1 W-RFQ / Construction of foot IBRD / 90410 and and Water Resource Ma Post Open - National 33,100.00 0.00 2023-05-27 2023-06-15 tions nvelope or explanation) mentation 2 Bridges 2023-24 under APO nagement Ghumarwin IN-DPO, BILASPUR-360126-C Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-0 W-RFQ / Construction of foot IBRD / 90410 and and Water Resource Ma Post Open - National 33,300.00 0.00 2023-05-23 2023-06-11 tions nvelope or explanation) mentation 8 Bridges 2023-24 under APO nagement Berthin IN-DPO, BILASPUR-361203-C W-RFQ / Construction of CC C Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2024-01-2 heck Dams /HEAD WALL GRA IBRD / 90410 and and Water Resource Ma Post Open - National 23,250.00 0.00 2023-05-29 2023-07-24 tions nvelope or explanation) mentation 0 VITY SCHEME under APO Gh nagement umarwin & Berthin 2023-24 IN-DPO, BILASPUR-360139-C Component 1. Sustainable L W-RFQ / Renovation/ Constru Request for Quota Single Stage - One E Other (with field f Under Imple 2024-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 11,500.00 0.00 2023-06-04 2023-07-30 ction of Water Bouries 2023- tions nvelope or explanation) mentation 6 nagement 24 under APO Ghumarwin IN-DPO, BILASPUR-360144-C Component 2. Improved Agri W-RFQ / Construction of Tank Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-01-3 IBRD / 90410 cultural Productivity and Val Post Open - National 19,506.00 0.00 2023-06-09 2023-08-04 s for Lift Irrigation Scheme 2 tions nvelope or explanation) lementation 1 ue Addition 023-24 Under APO Ghumarw in & Berthin. IN-DPO, BILASPUR-360147-C Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2024-02-0 W-RFQ / Construction of Pon IBRD / 90410 and and Water Resource Ma Post Open - National 32,000.00 0.00 2023-06-13 2023-08-08 tions nvelope or explanation) mentation 4 d under APO Ghumarwin & B nagement erthin 2023-24 IN-DPO, BILASPUR-360412-C Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Under Imple 2023-12-2 W-RFQ / Construction of Roo IBRD / 90410 and and Water Resource Ma Post Open - National 76,000.00 0.00 2023-06-13 2023-06-29 tions nvelope or explanation) mentation 6 f Rain Water Tank for commu nagement nity 2023-24 IN-DPO, BILASPUR-360780-C W-RFQ / Management of exot ic species i.e. eradication of l Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-01-1 antana and others invasive al IBRD / 90410 and and Water Resource Ma Post Open - National 6,650.00 0.00 2023-06-15 2023-07-22 tions nvelope or explanation) lementation 8 ien species during 2023-24 ( nagement Maintt. 2nd year ) area appro ximately 100 Hac. Under APO Berthin & Ghumarwin Distt. Bilaspur IN-DPO, BILASPUR-363144-C W-RFQ / Forestry Planting an Component 1. Sustainable L d Fencing (Maint. 1st Year) d Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-01-0 IBRD / 90410 and and Water Resource Ma Post Open - National 262.00 0.00 2023-06-04 2023-07-11 uring 2023-24 area approxi tions nvelope or explanation) lementation 7 nagement mately 36 Hac. Under APO B erthin & Ghumarwin Distt. B ilaspur IN-DPO, BILASPUR-363149-C W-RFQ / Forestry Planting an Component 1. Sustainable L d Fencing (Maint. 2nd Year) d Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-01-1 IBRD / 90410 and and Water Resource Ma Post Open - National 14,550.00 0.00 2023-06-15 2023-07-22 uring 2023-24 area approxi tions nvelope or explanation) lementation 8 nagement mately 227 Hac. Under APO Berthin & Ghumarwin Distt. Bilaspur IN-DPO, BILASPUR-363284-C W-RFQ / Forestry Planting an Component 1. Sustainable L d Fencing (Maint. 3rd Year) d Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 8,161.00 0.00 2023-06-18 2023-07-25 uring 2023-24 area approxi tions nvelope or explanation) lementation 1 nagement mately 175 Hac. Under APO Berthin & Ghumarwin Distt. Bilaspur IN-DPO, BILASPUR-363287-C W-RFQ / Contour Trenching Component 1. Sustainable L out side plantation area duri Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-01-2 IBRD / 90410 and and Water Resource Ma Post Open - National 8,500.00 0.00 2023-06-22 2023-07-29 ng 2023-24 area approximat tions nvelope or explanation) lementation 5 nagement ely 40 Hac. Under APO Berth in & Ghumarwin Distt. Bilas pur IN-DPO, BILASPUR-363331-C W-RFQ / Cement Concrete Ch Component 1. Sustainable L Request for Quota Single Stage - One E Other (with field f Pending Imp 2024-02-0 eck Barriers 2023-24 area a IBRD / 90410 and and Water Resource Ma Post Open - National 16,550.00 0.00 2023-06-29 2023-08-05 tions nvelope or explanation) lementation 1 pproximately 350 Cum Under nagement APO Berthin & Ghumarwin Distt. Bilaspur GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7 IN-DPO, BILASPUR-178840-G O-RFQ / Procurement of Blac k Polythene Bag 0.556 MT of size 5" X 9" inches 250 gaug Component 1. Sustainable L Request for Quota Single Stage - One E e automatically double seale IBRD / 90410 and and Water Resource Ma Post Limited 1,150.00 1,172.94 Completed 2020-06-15 2020-01-08 2020-08-10 2020-03-03 2020-08-25 2020-05-19 tions nvelope d by heat process. Limited m nagement arket approach was adopted because of low value and ava ilability of bidders. Work has already been completed in M arch 2020. IN-DPO, BILASPUR-178844-C W-RFQ / Procurement of Barb ed wire and U/Nails for 4 Nur series and Advance work for Component 1. Sustainable L Request for Quota Single Stage - One E Plantation 2020-21. The proc IBRD / 90410 and and Water Resource Ma Post Limited 10,417.00 10,600.40 Completed 2020-07-12 2020-02-27 2020-08-04 2020-03-19 2020-08-19 2020-07-11 tions nvelope urement has already been co nagement mpleted in March 2020. Limit ed market approach was ado pted because of low value an d availability of bidders. IN-DPO, BILASPUR-179154-G O-RFQ / Grass Sowing/Grass t ufts along Drainage line at di Component 1. Sustainable L Request for Quota Single Stage - One E fferent locations. Total area IBRD / 90410 and and Water Resource Ma Post Limited 11,650.00 6,027.89 Completed 2020-08-30 2020-08-20 2020-10-27 2020-11-25 2021-04-25 2021-02-27 tions nvelope will be covered 91 hectares. nagement This involves multiple contra cts of low value, hence limite d approach will be adopted. IN-DPO, BILASPUR-178832-G O-RFQ / Procurement of Polyt hene Bag for raising nurserie Component 1. Sustainable L s(2020-21) of size 5" X 9" inc Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Limited 2,300.00 2,342.10 Completed 2020-06-20 2020-01-08 2020-08-16 2021-01-24 2020-08-31 2021-03-04 hes 250 gauge automatically tions nvelope nagement double sealed by heat proces s. Perforation of 6 holes in 2 r ows of 3 holes in each in the lower 2/3 portion dia of holes 3mm IN-DPO, BILASPUR-178838-C W-RFQ / Procurement of See d and of Root Stock for raisin g Nurseries at different locati Component 1. Sustainable L Request for Quota Single Stage - One E ons during February 2020. IBRD / 90410 and and Water Resource Ma Post Limited 2,485.00 2,550.42 Completed 2020-07-09 2020-02-15 2020-08-05 2020-03-04 2020-08-15 2020-03-24 tions nvelope Work has already been comp nagement leted and subject to RF. Limit ed market approach was ado pted because of low value a nd availability of bidders. IN-DPO, BILASPUR-236759-G O-RFQ / Procurement of Pipe s & Pumps to be distributed t o the Farmers during 2021-2 Component 2. Improved Agri Request for Quota Single Stage - One E 2. The procurement will take IBRD / 90410 cultural Productivity and Val Post Limited 26,667.00 0.00 Canceled 2021-09-08 2021-09-28 2022-03-15 tions nvelope place as per request from far ue Addition mers of the District. Limited market approach was adopte d because of low value and a vailability of bidders. IN-DPO, BILASPUR-236774-C W-RFQ / Demonstration plots of Rabi and Kharif in the sha Component 2. Improved Agri pe of one bigha plot of each Request for Quota Single Stage - One E IBRD / 90410 cultural Productivity and Val Post Open - National 13,333.00 3,341.41 Completed 2021-09-04 2021-10-30 2022-03-22 2022-04-28 2022-03-30 farmers of both APO Berthin tions nvelope ue Addition and APO Ghumarwin. Mutlipl e high value crop demonstrat ion plot which includes seed, fertilizers and weedicides for the crop. IN-DPO, BILASPUR-242765-G O-RFQ / Procurement of Barb ed wire and U/Nails for Fenci ng work of Additional 45 Hec Component 1. Sustainable L Request for Quota Single Stage - One E t Area Taken for Plantation 2 IBRD / 90410 and and Water Resource Ma Post Open - National 7,410.00 5,281.50 Completed 2021-07-12 2021-07-28 2021-08-24 2022-01-24 2021-10-01 tions nvelope 021-22. The procurement will nagement be done after approval. Open market approach will be ado pted because of low value an d availability of bidders. IN-DPO, BILASPUR-241537-G O-RFQ / Procurement of agric ulture equipment's (Tarpauli Component 1. Sustainable L n) for farmers to secure the f Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 13,333.00 0.00 Canceled 2022-01-10 2022-01-27 2022-07-26 arm products during 2021-22 tions nvelope nagement . Keeping in view of low valu e of contracts and availability of perspective bidder, open market approach will be ado pted. IN-DPO, BILASPUR-260565-G O-RFQ / Procurement of equi pment to the Nomads pass o Component 1. Sustainable L ver and local animal breeder Request for Quota Single Stage - One E IBRD / 90410 and and Water Resource Ma Post Open - National 8,000.00 0.00 Canceled 2021-12-30 2022-01-18 2022-03-04 s of the District during 2021- tions nvelope nagement 22. Keeping in view of low va lue of contracts and availabili ty of perspective bidder, Ope n market approach will be ad opted. IN-DPO, BILASPUR-260571-G O-RFQ / Procurement of servi ces relevant charts and broc hures of the Project activities Component 1. Sustainable L Request for Quota Single Stage - One E implemented in the District a IBRD / 90410 and and Water Resource Ma Post Open - National 5,590.00 0.00 Canceled 2022-01-17 2022-02-01 2022-04-30 tions nvelope nd are to be implemented du nagement ring 2021-22. Keeping in vie w of low value of contracts a nd availability of perspective bidder, Limited market appro ach IN-DPO, BILASPUR-260573-G O-RFQ / Procurement of Fore stry Boards to be fixed in the area where Forestry works h Component 1. Sustainable L Request for Quota Single Stage - One E as already been done during IBRD / 90410 and and Water Resource Ma Post Open - National 8,000.00 5,847.47 Completed 2021-12-20 2022-01-10 2022-02-23 2022-05-10 2022-03-30 tions nvelope 2020-21 and 2021-22. Keepi nagement ng in view of low value of con tracts and availability of pers pective bidder, open market approach will be adopted. Page 8 IN-DPO, BILASPUR-281144-G O-RFQ / Procurement of mate rial for the transhumant of Pr oject Area involves Tents, Jac Component 1. Sustainable L Request for Quota Single Stage - One E kets, Sleeping Bags, Shoes, S IBRD / 90410 and and Water Resource Ma Post Open - National 3,360.00 0.00 Canceled 2022-03-03 2022-03-18 2022-05-17 tions nvelope olar Mobile Charger, Battery, nagement Rucksack Bags, Tarpaulins, and Veterinary Aid Kit. Cumul ative value of this activity inv olves multiple contracts. IN-DPO, BILASPUR-293964-G O-RFQ / Procurement of Barb ed Wire and U/Nails for 50 he ct. area to be planted in rain Component 1. Sustainable L Request for Quota Single Stage - One E y season 2022. The procure IBRD / 90410 and and Water Resource Ma Post Open - National 8,705.00 4,179.72 Completed 2022-06-03 2022-06-22 2022-07-28 2022-12-19 2022-08-09 tions nvelope ment will be done from open nagement market, keeping in view of lo w value of contracts and avai lability of open market appro ach will be adopted. IN-DPO, BILASPUR-293965-G O-RFQ / Procurement of Euca lyptus Fence Posts for 50 hec t. area to be planted in rainy Component 1. Sustainable L Request for Quota Single Stage - One E season 2022. The procureme IBRD / 90410 and and Water Resource Ma Post Open - National 10,667.00 11,465.70 Completed 2022-06-03 2022-06-22 2022-07-28 2022-12-19 2022-08-31 tions nvelope nt will be done from open ma nagement rket, keeping in view of low v alue of contracts and availabi lity of open market approach will be adopted. IN-DPO, BILASPUR-294295-G O-RFQ / Procurement of hydr oponic unit based natural far Component 1. Sustainable L Request for Quota Single Stage - One E ming during 2022-23. Keepin IBRD / 90410 and and Water Resource Ma Post Open - National 7,200.00 0.00 Canceled 2022-08-11 2022-08-29 2023-02-25 tions nvelope g in view of low value of cont nagement racts and availability of persp ective bidder, open market a pproach will be adopted. IN-DPO, BILASPUR-293980-C W-RFQ / Procurement of GI W Component 1. Sustainable L ire for construction of crate w Request for Quota Single Stage - One E Pending Impl IBRD / 90410 and and Water Resource Ma Post Open - National 13,600.00 0.00 2022-09-10 2022-10-03 2023-04-01 ire check barriers for drainag tions nvelope ementation nagement e line treatment during 2022- 23.Sigle RFQ will be called by adopting open market appro ach. IN-DPO, BILASPUR-342626-G O-RFQ / Procurement of High Definition Polythene Pipe for l inkage of Primary Water Harv Component 1. Sustainable L Request for Quota Single Stage - One E Pending Impl esting Structure to Secondar IBRD / 90410 and and Water Resource Ma Post Open - National 38,285.00 0.00 2023-03-07 2023-03-22 2023-09-18 tions nvelope ementation y Water Harvesting Structure nagement during 2022-23. Keeping in vi ew of low value of contract a nd availability of perspective bidders, open market approa ch NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 9 PROCUREMENT PLAN (Textual Part) Project information: Nigeria Sustainable Urban and Rural Water Supply, Sanitation and Hygiene Program P170734 Project Implementation Agency: Federal Ministry of Water Resources and Seven (7) States (Ekiti, Delta, Gombe, Imo, Kaduna, Katsina & Plateau Date of the Procurement Plan: 25th November, 2021 Period covered by this Procurement Plan: January 2022 to June 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan Tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Table 1: Summary of the procurement packages for Goods Market Selectio Evaluation Expect Approa Revie n Options Expected ed ch w by Estimat Method (Most date of date of Sr. Contract (Open- Bank ed Cost (RFP, Advantageo bid/ Contra No Description Nation (Prior/ (US$) RFB, us Bid, proposal ct al/ Post) RFQ, DS BAFO, Rated opening Signat Limited etc.) Criteria etc.) ure etc.) Procurement of Operational Vehicles (6 Nos operational Lowest 25/01/202 01/02/2 1 vehicles: 3 for FPIU, Post 500,000 Limited RFQ 2 022 Evaluated Cost 1 each for CNC, PEWASH and NWRI) Goods Procurement of ICT Equipment (Audio Visual, Internet etc) Open- 08/02/202 01/03/2 2 Post 400,000 RFB for FPIU/FMWR, CNC, National Lowest 2 022 PEWASH, NAP & Evaluated Cost NWRI offices (Goods) Procurement of Office Equipment & Furniture (Laptop, 08/02/202 08/03/2 3 Desktop, Table, Post 100,000 Limited RFQ Lowest 2 022 Chair) for FPIU, CNC, Evaluated Cost PEWASH, NAP, & NWRI (Goods) 1,000,0 Total 00 Table 2: Summary of the procurement packages for Consulting Services Selection Market Method Approach Expected Review (QCBS, Expected Estimat (Open - Shortlisti date of Sr. by Bank FBS, date of Contract Description ed Cost Internation ng bid/ No (Prior/ LCBS, Contract (US$) al/ (Yes/ No) proposal Post) QBS, Signature National/ opening CQS, DS etc.) etc.) 25/01/202 1 Procurement of an M&E Specialist Post 50,000 Limited INDV No 11/01/2022 2 Consultancy Services for Engagement 14/01/202 2 of Environmental Safeguard Post 50,000 Limited INDV No 7/12/2021 1 Specialist Consultancy Services for Engagement 14/01/202 3 Post 50,000 Limited INDV No 7/12/2021 of Social Safeguard Specialist 1 Consultancy Services for Engagement 25/01/202 4 of Technical Assistance for Program Post 50,000 Limited INDV No 11/01/2022 2 Operational Manual Consultancy Services to Support 19/04/202 5 States’ in meeting the Readiness Post 300,000 Limited CQS No 5/04/2022 2 criteria to participate in the project. Consultancy services for review year 17/05/202 6 2000 National Water Supply and Post 300,000 Limited CQS No 3/05/2022 2 Sanitation Policy Consultancy Services for Development of a National Social and 300,000 Limited 22/03/202 7 Post CQS No 8/03/2022 Behaviour Change Communication 2 (SBCC) Strategy Consultancy Services for 29/03/202 8 Development of a National Market- Post 300,000 Limited CQS No 15/03/2022 2 Based Sanitation Strategy Consultancy Services for 9 Post CQS No 22/03/2022 5/04/200 Development of Information, 300,000 Limited Education and Communication (IEC) and Training Materials Consultancy Services for Development of Strategy and Roadmap/Framework for Open- 31/05/202 10 Prior 500,000 QCBS Yes 10/05/2022 Implementation of Water, Sanitation International 2 & Hygiene (WASH) Management Information System (MIS) Consultancy Services for the 5,000,00 Open- 11 engagement of Independent Prior QCBS Yes 15/03/2022 5/04/2022 0 International Verification Agent (IVA) for P4R 7,200,0 Total Consultancy Services 00 PROCUREMENT Nigeria : Nigeria Sustainable Urban and Rural Water Supply, Sanitation and Hygiene Program-for-Results PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2022-06-02 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-18 none) Project ID: P170734 GPN Date: Project Name: Nigeria Sustainable Urban and Rural Water Supply, Sanitation and Hygiene Program-for-Results Loan / Credit No: IDA / 68820 SURWASH KATSINA Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-SURWASH KATSINA-2957 Request for Quota Single Stage - One E Pending Impl 99-GO-RFQ / Procurement of IDA / 68820 Post Limited 208,081.00 0.00 2022-05-31 2022-06-28 2022-07-26 tions nvelope ementation 3no. 4x4WD (Pickup)Van NG-SURWASH KATSINA-2957 91-GO-RFQ / Procurement of Laptop PCs, Desk topPCs, HP Printers, Photocopying Machi Request for Quota Single Stage - One E Under Imple ne, Scanner, Video, Projector, IDA / 68820 Post Limited 40,000.00 0.00 2022-05-30 2022-06-28 2022-07-26 tions nvelope mentation Conferencing system, still ca meras, camcorders, Wifi inter net facilities hard drive( 2TB) splash drives(32 GB) & shred ing merchines NG-SURWASH KATSINA-2957 82-GO-RFQ / Procurement of Office Tables,Exercutive Chai Request for Quota Single Stage - One E Pending Impl rs,Visitors Chairs,15 Seater C IDA / 68820 Post Limited 41,775.00 0.00 2022-05-29 2022-07-05 2022-08-02 tions nvelope ementation onference, Office Cabinet (Fir e Proof) Extention Box and St ablizers, Standing fans, Fridg e, Smart Tv,and water Dispe nser. NG-SURWASH KATSINA-2957 Request for Quota Single Stage - One E Pending Impl 85-GO-RFQ / Procurement of IDA / 68820 Post Limited 10,000.00 0.00 2022-06-25 2022-07-29 2022-08-26 tions nvelope ementation Application Packages and Sof twaeres NG-SURWASH KATSINA-3652 Request for Quota Single Stage - One E Pending Impl 36-GO-RFQ / Procurement of IDA / 68820 Post Limited 109,489.00 0.00 2023-06-10 2023-07-07 2023-08-06 tions nvelope ementation 1 vehicle (2022/2023) for SPI U NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-SURWASH KATSINA-3591 Consultant Qualifi 10-CS-CQS / Engagement of IDA / 68820 Post Limited 45,000.00 0.00 Canceled 2023-05-22 2023-06-05 2023-06-19 2023-07-03 2026-07-02 cation Selection External Auditor for three (3) Years INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-SURWASH KATSINA-3138 98-CS-INDV / Engagement of Individual Consult Pending Impleme IDA / 68820 Post Limited 34,146.00 0.00 2022-09-05 2022-09-12 2022-09-19 2022-09-24 2023-09-24 Technical Assistance Consult ant Selection ntation ant for Social Safeguards NG-SURWASH KATSINA-3139 03-CS-INDV / Engagement of Individual Consult Pending Impleme IDA / 68820 Post Limited 34,146.00 0.00 2022-09-05 2022-09-12 2022-09-19 2022-09-24 2023-09-24 consultant Monitoring and Ev ant Selection ntation aluation Consultancy Service s NG-SURWASH KATSINA-2957 98-CS-INDV / Engagement of Individual Consult IDA / 68820 Post Limited 20,000.00 0.00 Canceled 2022-06-06 2022-06-10 2022-06-17 2022-07-01 2022-09-29 Technical Assistance Consult ant Selection ant for Social Safeguards NG-SURWASH KATSINA-2957 87-CS-INDV / Engagement of Individual Consult IDA / 68820 Post Limited 20,000.00 0.00 Canceled 2022-06-06 2022-06-10 2022-06-17 2022-07-01 2022-09-29 Technical Assistance Consult ant Selection ant for Environmental Safegu ards NG-SURWASH KATSINA-2957 94-CS-INDV / Engagement of Individual Consult IDA / 68820 Post Limited 20,000.00 0.00 Canceled 2022-06-06 2022-06-10 2022-06-17 2022-07-01 2022-09-29 consultant Monitoring and Ev ant Selection aluation Consultancy Service s NG-SURWASH KATSINA-3139 01-CS-INDV / Engagement of Individual Consult Pending Impleme IDA / 68820 Post Limited 34,146.00 0.00 2022-09-05 2022-09-12 2022-09-19 2022-09-24 2023-09-19 Technical Assistance Consult ant Selection ntation ant for Environmental Safegu ards Page 1 NG-SURWASH KATSINA-3620 31-CS-CDS / Engagement of Pending Impleme IDA / 68820 Post Direct Selection Direct - National 45,000.00 0.00 2023-05-29 2023-06-08 2023-06-24 2026-06-08 External Auditor for Three (3) ntation Years as Post Review Activity Page 2 Republic of Malawi 12 MONTHS PROCUREMENT PLAN- MALAWI EMERGENCY OPERATION TO PROTECT ESSENTIAL HEALTH SERVICES I. General 1.Project information Country: Malawi Project Name: Malawi Emergency Operation to Protect Essential Health Services Project ID: P180231 2.Project Implementation Agency: Ministry of Health (MoH) 3.Date of the Procurement Plan: December 1, 2022 4.Period covered by this Procurement Plan: December 2022 to November 2023 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Disposal of Public Assets Act, 2017 of the Republic of Malawi, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations as follows:  Provision of “set-asides” contracts for small enterprises shall not be applied.  Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis.  Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and practices. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification. Not expected for the works/goods packages in the procurement plan. VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable VII. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). (a) Goods: Not Applicable for those contracts identified in the Procurement Plan tables. (b) Works: Not Applicable for those contracts identified in the Procurement Plan tables. IX. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not Applicable X. Other Relevant Procurement Information: - (a) Proposed Procedures for CDD Components: Not Applicable (b) Reference to (if any) Project Operational/Procurement Manual: The MoH and CMST will develop a Procurement Manual which will be part of the Project Implementation Manual (PIM) to elaborate procurement arrangements under the proposed Project. The Procurement Plan will also form part of the PIM. XI. Any Other Special Procurement Arrangements: Being emergency project, simple and fast procurement and selection processes fit for purpose in an emergency will be used including the following streamlined procurement arrangements: (i) use of simple and fast procurement and selection methods fit for purpose in an emergency situation; (ii) procurement from UN Agencies enabled and expedited by World Bank procedures and standard agreements; (iii) increased thresholds for Requests for Quotations (RFQ) to US$1 million for goods and services and US$5 million for works; (iv) direct contracting of firms as appropriate; (v) Limited Competition with identified suppliers and contractors; (vi) use of procurement agents; and (vii) force account, as needed. Bid Securing Declaration may be used instead of the bid security. Advance payment may be increased to 40 percent, while secured with the advance payment guarantee. The time for submission of bids/proposal can be shortened to seven - fifteen days in competitive national and international procedures, and to three days for the Request for Quotations, however if bidders request an extension, it should be granted. The retroactive financing may be applied to the contracts procured in advance for the purpose of this Project objective using procurement procedures consistent with Sections I, II and III of the World Bank’s Procurement Regulations and consistent with the Financing Agreement of this Project. The Recipient will conduct all emergency procurements under this Project as post review. XII. Procurement Approach and Prior Review Thresholds: Based on the overall procurement risk rating of “Substantial”, the thresholds for the Bank’s prior review and procurement method threshold are provided in the table below: Prior-review Thresholds for Procurement Methods Thresholds Procureme Substanti Works Goods, IT & Non-Consulting Shortlist of National nt al Services Consultants Type Risk ($`000) Works 10,000 Open Request Request Internatio for for Engineerin Open Open nal or Quotatio Open Quotatio Consultin g& Nation Nation ICB n or Internatio n or g Constructi al or al or ($'000 National nal or ICB National Services on NCB NCB Shoppin ($'000) Shoppin ($'000) Supervisio ($'000) ($'000) g g n ($'000) ($'000) ($'000) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultant 1,000 s (Firms) Individual 300 7,000 7,000 200 1,000 1,000 100 200 300 Consultant s Note Given that the project will finance a combination of goods, services, and works for emergency response as per OP 12.00, there will be no prior review, and there will be no Standstill Period, provided that Procurement Entities will informally share documentation for quality assurance purposes before contractual commitments. XIII. Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: PROCUREMENT PLAN A. Works 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimated Market Selecti Prequ Domesti Revie Expecte Expecte No. Description Cost Approa on alifica c w d bid d US$ ch Method tion Prefere by opening Contrac (yes/n nce Bank date t o) (yes/no) (Prior Signatu / Post) re Date 1. N/A B. Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimate Market Selectio Prequ Domesti Revie Expecte Expecte No. Description d Approac n alifica c w d bid d Cost h Method tion Prefere by opening Contrac US$ (yes/n nce Bank date t o) (yes/no) (Prior Signatu / Post) re Date 1. Supply and Delivery 5,000,000 Direct UN N/A N/A Prior 31/01/23 28/02/23 of Essential .00 Medicines and Related Supplies 2. Supply and Delivery 30,000.0 Limited RFQ N/A N/A Post 31/01/23 11/02/23 of ten (10) Laptop 0 Computers, One (1) Heavy duty printer, one (1) light duty printer and one (1) scanner C. Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Market Selectio Shortlisti Revie Expect Expected No. Description Cost Approa n ng w ed Contract US$ ch Method (Yes/No) by propos Signatur Bank al e Date (Prior openin / Post) g date 1. Hiring of Procurement 108,000.00 Limited INDV Yes Post 12/01/2 31/01/22 Specialist 2 2. Hiring of Project officer 70,000.000 Limited INDV Yes Post 12/01/2 31/01/22 2 UN – UN Agency; RFQ – Request for Quotation; and INDV - Individual Consultant Selection. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. Title of the person signing the Letter: PROCUREMENT Malawi : Malawi Emergency Project to Protect Essential Health Services PLAN General Information Country: Malawi 2023-02-21 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P180231 GPN Date: Project Name: Malawi Emergency Project to Protect Essential Health Services Loan / Credit No: IDA / E1540 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOH-342522-GO-RFQ / Request for Quota Single Stage - One E IDA / E1540 Project management Post Limited 30,000.00 0.00 Signed 2023-03-02 2023-04-12 2023-03-21 2023-03-28 Supply and Delivery of ICT Eq tions nvelope uipment MW-MOH-342544-GO-DIR / S Direct - Internation Pending Impl upply and Delivery of Essenti IDA / E1540 Project management Post Direct Selection 5,000,000.00 0.00 2023-02-27 2023-03-04 2023-04-02 2023-06-01 al ementation al Medicines and Related Sup plies MW-MOH-360666-GO-RFQ / Request for Quota Single Stage - One E Supply, Delivery, Installation IDA / E1540 Project management Post Limited 5,800.00 0.00 Signed 2023-05-19 2023-05-18 2023-06-10 2023-06-24 tions nvelope and Training of Accounting S oftware NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-MOH-342532-CS-INDV / Individual Consult IDA / E1540 Project management Post Limited 108,000.00 0.00 Signed 2023-01-05 2023-01-05 2023-01-26 2023-01-19 2023-02-02 2023-02-17 2023-02-05 2025-02-04 Hiring of Procurement Specia ant Selection list MW-MOH-342513-CS-INDV / Individual Consult IDA / E1540 Project management Post Limited 70,000.00 0.00 Signed 2023-02-17 2023-02-28 2023-03-10 2023-03-23 2023-03-15 2023-05-25 2023-03-17 2025-03-16 Hiring of Project Officer ant Selection Page 1 3 MONTHS PROCUREMENT PLAN Project information: P173820 - Kenya Covid-19 Emergency Response Project Implementation agency: Ministry of Health and Kenya Medical Supplies Agency Date of the Procurement Plan: March 25 2021 Period covered by this Procurement Plan: Three months Preamble In accordance with paragraph 5.9 of the World Bank’s Procurement Regulations for IPF Borrowers for Goods, Works, Non-Consulting and Consulting Services, dated July 1, 2016 (revised in November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Paragraph 5.3 of the Procurement Regulations will not apply. When approaching the national market, the country’s own procurement procedures shall not be used due to restrictions on eligibility of otherwise eligible firms to participate in NCB. The Regulations will apply. However, the Borrower may use its own procurement arrangements as set forth in the Public Procurement and Disposal Act, 2003 Request for Quotation such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions: In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods : Applicable for those contracts identified in the Procurement Plan tables Works: applicable for those contracts identified in the Procurement Plan tables This being an emergency project, increased thresholds for Requests for Quotations (RFQ) to US$1 million for goods and services and US$5 million for works; Other Relevant Procurement Information:- Prior Procurement Arrangements: The Procurement Arrangements as indicated in the below table and within the thresholds indicated in the below tables will be used. The thresholds for the Bank’s prior review requirements are also provided in the table below: Table: Prior review Thresholds High Procurement Type Risk Works 5.0 Goods, It & Non-Consulting 1.5 Services Consultants (Firms) 0.5 Individual Consultants 0.2 Prequalification. Not expected for any works or goods packages in the procurement plan. Proposed Procedures for CDD Components: Applicable Reference to (if any) Project Operational/Procurement Manual: the CHERP team will prepare a Procurement manual, which will also be part of the Project Implementation Manual. Any Other Special Procurement Arrangements: None Procurement Packages/PLAN with Procurement Arrangements and Time Schedule: as per the Table below: Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub- contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank- financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Kenya : KENYA COVID-19 HEALTH EMERGENCY RESPONSE PROJECT PLAN General Information Country: Kenya 2020-04-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P173820 GPN Date: 2020-04-08 Project Name: KENYA COVID-19 HEALTH EMERGENCY RESPONSE PROJECT Loan / Credit No: IDA / 65980, IDA / 68230 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-MOH-168125-CW-RFQ / R enovations of regional level a mbulance command centres in 14 designated high risk co Response, capacity building Request for Quota Single Stage - One E Pending Imp 2020-12-1 untiesthe renovations will be IDA / 65980 Post Limited 123,900.00 0.00 2020-04-22 2020-06-17 and training tions nvelope lementation 4 done in the following countie s: Nairobi, Mombasa, Kisumu, Kiambu, , Uasingishu, Kajiado , Machakos, Kakamega, Naku ru, Garissa, Wajir, Busia, KE-MOH-168121-CW-RFQ / C onstruction of 20 bed isolatio n units in level 5 hospitals in eastern, coast and North eas Quarintine, isolation and tre Request for Quota Single Stage - One E 2020-12-1 IDA / 65980 Post Limited 1,792,000.00 0.00 Canceled 2020-04-22 2020-06-17 tern regions:These units will atement centres tions nvelope 4 be constructed in the followi ng level 5 Hospitals: Machak os, Mombasa, Makueni and G arissa Level 5 Hospitals KE-MOH-168116-CW-RFQ / C onstruction of 10 bed isolatio n units in level 4 facilities in Quarintine, isolation and tre Request for Quota Single Stage - One E 2020-12-1 IDA / 65980 Post Limited 1,960,000.00 0.00 Canceled 2020-04-22 2020-06-17 western and nyanza Regions: atement centres tions nvelope 4 in Busia, Bungoma, Vihiga, Si aya, Migori, Homabay and Ny amira Counties KE-MOH-168118-CW-RFQ / C onstruction of 10 bed isolatio n units in 10 level 4 Hospitals Quarintine, isolation and tre Request for Quota Single Stage - One E 2020-12-1 in Rift valley region: in Bome IDA / 65980 Post Limited 2,800,000.00 0.00 Canceled 2020-04-22 2020-06-17 atement centres tions nvelope 4 t,Uasin gishu,West Pokot, Tur kana, Kericho, Narok, Nandi, Baringo, Elgeyo Marakwet an d Kajiado Counties KE-MOH-168120-CW-RFQ / C onstruction of 20 bed isolatio n unit in level 5 Hospitals in Quarintine, isolation and tre Request for Quota Single Stage - One E 2020-12-1 Rift and western regions:The IDA / 65980 Post Limited 1,792,000.00 0.00 Canceled 2020-04-22 2020-06-17 atement centres tions nvelope 4 se units will be constructed i n the following Level 5 hospit als: Kisii, Kisumu,Kakamega and Nakuru level 5 Hospitals KE-MOH-168119-CW-RFQ / C onstruction of 20 bed isolatio n units in 3 level 5 hospitals i n central region and 3 Nation Quarintine, isolation and tre Request for Quota Single Stage - One E 2020-12-1 IDA / 65980 Post Limited 3,136,000.00 0.00 Canceled 2020-04-22 2020-06-17 al Referral Hospitals in Nairo atement centres tions nvelope 4 bi region: in Thika, Meru ,Nye ri and Embu Level 5 Hospital s and Kenyatta National, Mba gathi IDU and Kenyatta Uni R eferral Hospitals KE-MOH-168113-CW-RFQ / C onstruction of 10 bed isolatio n units in Level 4 Hospitals in Quarintine, isolation and tre Request for Quota Single Stage - One E 2020-12-1 Coast and North eastern regi IDA / 65980 Post Limited 2,240,000.00 0.00 Canceled 2020-04-22 2020-06-17 atement centres tions nvelope 4 ons: The units will be constru cted in Kwale, Kilifi, Lamu, Ta na river, Wajir, Mandera, Tait a Taveta and Kitui Counties KE-MOH-168117-CW-RFQ / C onstruction of 10 bed isolatio n units in 10 level 4 Hospitals in Central, Eastern and Nairo Quarintine, isolation and tre Request for Quota Single Stage - One E 2020-12-1 IDA / 65980 Post Limited 2,800,000.00 0.00 Canceled 2020-04-22 2020-06-17 bi Regions: in Marsabit, Isiol atement centres tions nvelope 4 o, Samburu, Laikipia, Nyanda rua, Kirinyaga, Tharaka Nithi, Muranga,Kiambu and Nairobi counties. KE-MOH-168126-CW-RFB / C Response, capacity building Single Stage - One E 2021-02-0 onstruction of National Public IDA / 65980 Post Request for Bids Open 6,900,000.00 0.00 Canceled 2020-04-17 2020-04-22 2020-06-03 2020-07-03 2020-08-07 and training nvelope 3 Health Institute in Nairobi KE-MOH-188956-CW-RFB / R enovation of infectious disea se units at Mama Lucy Kibaki Availability of safe blood and Single Stage - One E Pending Imp 2021-05-2 IDA / 65980 Post Request for Bids Open - National 2,600,000.00 0.00 2020-08-23 2020-08-28 2020-09-18 2020-10-18 2020-11-22 Hospital and at Kenyatta Uni blood products nvelope lementation 1 versity teaching and Referal and Research Hospital (KUTR RH) and lady Northey Clinic KE-MOH-188962-CW-RFQ / R enovation of 3 regional blood Availability of safe blood and Request for Quota Single Stage - One E Under Imple 2021-03-1 IDA / 65980 Post Limited 210,000.00 0.00 2020-08-26 2021-01-12 2020-09-18 centres: Kisii, Embu and Mo blood products tions nvelope mentation 7 mbasa blood centres KE-MOH-188964-CW-RFQ / R Availability of safe blood and Request for Quota Single Stage - One E Pending Imp 2021-02-1 IDA / 65980 Post Limited 90,000.00 0.00 2020-10-16 2020-11-18 enovation of 6 cold rooms blood products tions nvelope lementation 6 KE-MOH-196712-CW-RFQ / P roposed Medical Gases Instal Quarintine, isolation and tre Request for Quota Single Stage - One E Pending Imp 2021-03-0 IDA / 65980 Post Limited 126,000.00 0.00 2020-10-21 2020-12-09 lation works at COVID-19 Isol atement centres tions nvelope lementation 9 ation Centre in Madalder Lev el 4 Hospital KE-MOH-196714-CW-RFQ / P roposed Medical Gases Instal lation works at COVID-19 Isol Quarintine, isolation and tre Request for Quota Single Stage - One E Pending Imp 2021-04-1 IDA / 65980 Post Limited 235,000.00 0.00 2020-11-27 2021-01-15 ation Centres in atement centres tions nvelope lementation 5 Lot 1. Kisumu Level 4 Hospit al Lot 2. Langalanga Sub-count y Hospital in Nakuru County Page 1 KE-MOH-196704-CW-RFQ / P roposed Medical Gases Instal lation works at COVID-19 Isol Quarintine, isolation and tre Request for Quota Single Stage - One E Under Imple 2021-04-1 ation Centres: IDA / 65980 Post Limited 274,000.00 0.00 2020-11-27 2021-01-12 2021-01-15 atement centres tions nvelope mentation 5 Lot 1. Alupe Sub-County Hos pital in Busia County Lot 2. Macalder Level 4 Hospi tal in Migori County KE-MOH-196713-CW-RFQ / P roposed Medical Gases Instal lation works at COVID-19 Isol Quarintine, isolation and tre Request for Quota Single Stage - One E Pending Imp 2021-04-1 ation Centres: IDA / 65980 Post Limited 240,500.00 0.00 2020-11-27 2021-01-15 atement centres tions nvelope lementation 5 Lot 1. Gede Health Centre in Kilifi County Lot 2. Msambweni Level 4 Ho spital in Kwale County KE-MOH-196707-CW-RFQ / P roposed Medical Gases Instal lation works at COVID-19 Isol Quarintine, isolation and tre Request for Quota Single Stage - One E Pending Imp 2021-04-1 ation Centres: IDA / 65980 Post Limited 194,000.00 0.00 2020-11-27 2021-01-15 atement centres tions nvelope lementation 5 Lot 1. Mwatate Level 4 Hospi tal in Taita Taveta County Lot 2. Kauwi Level 4 Hospital in Kitui County KE-MOH-196711-CW-RFQ / P roposed Medical Gases Instal lation works at COVID-19 Isol Quarintine, isolation and tre Request for Quota Single Stage - One E Under Imple 2021-04-1 IDA / 65980 Post Limited 249,000.00 0.00 2020-11-27 2021-01-12 2021-01-15 ation Centres: atement centres tions nvelope mentation 5 Lot 1. Garissa Referral Hospit al Lot 2. Kaimur Isolation Hospit al in Mandera County KE-MOH-196710-CW-RFQ / P roposed Medical Gases Instal lation works at COVID-19 Isol Quarintine, isolation and tre Request for Quota Single Stage - One E Under Imple 2021-04-1 ation Centres: IDA / 65980 Post Limited 226,500.00 0.00 2020-11-27 2021-01-12 2021-01-15 atement centres tions nvelope mentation 5 Lot 1. Kangundo Level 4 Hos pital in Machakos County Lot 2. Ngong Level 4 Hospital in Kajiado County KE-MOH-196904-CW-RFQ / P roposed Refurbishment of Co Quarintine, isolation and tre Request for Quota Single Stage - One E Pending Imp 2021-04-2 IDA / 65980 Post Limited 550,000.00 0.00 2020-11-18 2020-12-30 vid-19 Isolation facility at Ma atement centres tions nvelope lementation 9 ma Lucy Kibaki Hospital, Nair obi County KE-MOH-216886-CW-RFQ / P roposed Renovation works at the Kenyatta University Teac Quarintine, isolation and tre Request for Quota Single Stage - One E 2021-06-2 hing and Referral Hospital to IDA / 65980 Post Limited 350,000.00 0.00 Canceled 2021-02-19 2021-03-24 atement centres tions nvelope 2 include Interior fit outs for th e Infectious Disease Unit (ID U) and Inclusion of Negative Pressure system at the IDU KE-MOH-227278-NC-DIR / Re furbishment of the proposed Community discussion and i Request for Quota Single Stage - One E Pending Imp 2021-11-2 IDA / 65980 Post Limited 150,000.00 0.00 2021-04-11 2021-05-26 719 Call Centre Room in th nformation outreach tions nvelope lementation 2 e Ministry of Health. KE-MOH-233744-CW-RFQ / P roposed Medical Gas Installat ion Works at Marimani Outr Request for Quota each Hospital -Mombasa Cou Medical supplies and equipm Request for Quota Single Stage - One E tions - Small Work Pending Imp 2021-07-1 nty (Lot 1),Mtongwe Outreac IDA / 65980 Post Limited 432,000.00 0.00 2021-05-17 2021-06-30 ent tions nvelope s (Emergency) SP lementation 4 h hospital-Mombasa County ( D -Competitive Lot 2).Port Reitz Subcounty H ospital-Mombasa County (Lo t 3) and Moi Voi Hospital -Ta ita Taveta county (Lot 4) KE-MOH-233865-CW-RFQ / P roposed Medical Gas Installat Request for Quota ion works at Chepyakwai He Medical supplies and equipm Request for Quota Single Stage - One E tions - Small Work Pending Imp 2021-08-2 IDA / 65980 Post Limited 160,000.00 0.00 2021-05-19 2021-06-28 alth Centre -Uasin Gishu Cou ent tions nvelope s (Emergency) SP lementation 0 nty (Lot 1) and Kamalel Isola D -Competitive tion Centre-Uasin Gishu Cou nty (Lot 2) KE-MOH-233867-CW-RFQ / P roposed Medical Gas Installat Request for Quota ion Work at Moiben Sub Hos Medical supplies and equipm Request for Quota Single Stage - One E tions - Small Work Pending Imp 2021-07-1 IDA / 65980 Post Limited 216,000.00 0.00 2021-05-16 2021-06-08 pital-Uasin Gishu County( Lot ent tions nvelope s (Emergency) SP lementation 6 1) and Kericho County Refer D -Competitive ral Hospital- Kericho County( Lot 2) KE-MOH-233868-CW-RFQ / P Request for Quota roposed medical Gas Installat Medical supplies and equipm Request for Quota Single Stage - One E tions - Small Work Pending Imp 2022-01-0 ion works at Pumwani Hospit IDA / 65980 Post Limited 216,000.00 0.00 2021-05-18 2021-07-05 ent tions nvelope s (Emergency) SP lementation 1 al - Nairobi County (Lot 1) an D -Competitive d Kitui County Hospital ( Lot 2) KE-MOH-233869-CW-RFQ / P Request for Quota roposed Medical Gas installat Medical supplies and equipm Request for Quota Single Stage - One E tions - Small Work Pending Imp 2021-09-1 IDA / 65980 Post Limited 225,000.00 0.00 2021-05-20 2021-07-21 ion works at Nakuru Level 5 ent tions nvelope s (Emergency) SP lementation 6 Hospital in Nakuru County. D -Competitive KE-MOH-250046-CW-RFQ / P roposed renovation Works an Request for Quota d negative pressure system i Quarintine, isolation and tre Request for Quota Single Stage - One E tions - Small Work Under Imple 2022-04-2 nstallation to the Infectious D IDA / 65980 Post Limited 291,740.00 0.00 2021-09-05 2021-10-31 atement centres tions nvelope s (Emergency) SP mentation 9 isease Unit (IDU) at the Keny D -Competitive atta University Teaching, Ref erral and Research Hospital, Nairobi County KE-MOH-249998-CW-RFQ / P Request for Quota roposed Works at Kenyatta U Quarintine, isolation and tre Request for Quota Single Stage - One E tions - Small Work Pending Imp 2022-04-2 IDA / 65980 Post Limited 443,813.50 0.00 2021-09-05 2021-10-31 niversity, Teaching, Referral atement centres tions nvelope s (Emergency) SP lementation 9 and Research Hospital, Nairo D -Competitive bi County KE-MOH-02/2022-2023-CW- National Procure RFQ / Proposed Civil works to ment Document - Operationalization Medical W Request for Quota Single Stage - One E Pending Imp 2023-12-1 IDA / 65980 Medical waste disposal Post Limited 1 Envelope proce 200,000.00 0.00 2023-04-25 2023-06-20 aste Treatment Equipment a tions nvelope lementation 7 ss (Non Bank-SPD t Kenyatta University Teachin ) g, Research and Referral Hos pital Page 2 KE-MOH-07-2022/2023-CW- RFQ / Construction of Microw National Procure ave Shed, Supply, Delivery In ment Document - Request for Quota Single Stage - One E Pending Imp 2023-12-2 stallation and Commissioning IDA / 65980 Medical waste disposal Post Limited 1 Envelope proce 230,000.00 0.00 2023-04-28 2023-06-23 tions nvelope lementation 0 of 50Kg/hr Waste Treatment ss (Non Bank-SPD Equipment-Micro Wave Type ) to Kangundo Hospital in Mac hakos County KE-MOH-04-2022-2023-CW- RFB / Proposed Construction of Microwave Sheds, Supply, Request for Bids - Delivery Installation and Com Single Stage - One E Under Imple 2023-12-2 IDA / 65980 Medical waste disposal Post Request for Bids Open - National Plant SPD (withou 1,150,000.00 0.00 2023-06-09 2023-06-12 2023-06-13 2023-06-15 2023-07-04 2023-07-10 2023-07-26 missioning of Waste Treatme nvelope mentation 9 t prequalification) nt Equipment-Micro Wave Ty pe in Mama Lucy Kibaki, Lan galanga, Gatundu, Msambw eni, Tigoni and Kangundo Ho spitals KE-MOH-05-2022/2023-CW- RFB / Proposed Construction Request for Bids - of Incinerator Sheds, Supply, Single Stage - One E Under Imple 2023-12-2 IDA / 65980 Medical waste disposal Post Request for Bids Open - National Plant SPD (withou 1,100,000.00 0.00 2023-06-09 2023-06-12 2023-06-13 2023-06-15 2023-07-04 2023-07-10 2023-07-26 Delivery Installation and Com nvelope mentation 9 t prequalification) missioning of Incinerators in Alupe, Kauwi, Hola, Loitokto k and Garissa Hospitals. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOH-168069-GO-UN / Pr ocure assorted Lab Personal Protective Equipment, Medical supplies and equipm UN Agencies (Dire Pending Impl Assorted emergency ICU equi IDA / 65980 Post Direct 985,175.00 0.00 2020-04-20 2020-04-25 2020-05-30 2020-11-26 ent ct) ementation pment, supplies and consum ables Assorted Lab equipment and Lab supplies KE-MOH-168095-GO-RFQ / Pr inting and distribution of ass Response, capacity building Request for Quota Single Stage - One E Pending Impl orted surveillance , SOP and IDA / 65980 Post Limited 150,000.00 0.00 2020-04-19 2020-06-14 2020-12-11 and training tions nvelope ementation data collection tools"4000 No . MOH 502, 2000 No. MOH 5 03 and 10000 No. MOH 505 KE-MOH-168128-GO-RFQ / Pr int and distribute 250000 No. Community discussion and i Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 234,000.00 0.00 2020-04-22 2020-06-17 2020-12-14 A4 size pamphlets, 100000 N nformation outreach tions nvelope ementation o. A2 posters and 100 Roll up banners KE-MOH-00001-GO-DIR / Pro Medical supplies and equipm cure 250 No. Gradian Compr IDA / 65980 Prior Direct Selection Direct 4,000,000.00 1,600,000.00 Signed 2020-03-27 2020-04-27 2020-03-27 2020-05-19 2020-03-30 2020-03-31 2020-12-31 ent ehensive Critical Care ventill ators KE-MOH-173622-GO-RFQ / T Response, capacity building Request for Quota Single Stage - One E IDA / 65980 Post Limited 24,750.00 22,142.52 Signed 2020-05-30 2020-05-28 2020-07-25 2020-06-09 2021-01-21 ablet for case management, and training tions nvelope 75 No KE-MOH-173494-GO-RFQ / p rocurement of 2 fireproof cab Project implementation and Request for Quota Single Stage - One E IDA / 65980 Post Limited 5,600.00 19,769.48 Completed 2020-06-01 2020-05-28 2020-07-27 2020-06-09 2021-01-23 2020-07-01 inets, 2 microwave, 2 water monitoring tions nvelope dispensers, 1 fridge KE-MOH-173502-GO-RFQ / Pr ocurement of 11 laptops, 1 L CD projector, 11 mobile phon Response, capacity building Request for Quota Single Stage - One E IDA / 65980 Post Limited 27,700.00 26,777.78 Signed 2020-06-02 2020-05-28 2020-07-28 2020-06-09 2021-01-24 es, 1 colour multi-functional and training tions nvelope printer ,1 b/w light duty print er, 2 wifi routers, 10 modems KE-MOH-173541-GO-RFQ / p rocurement of furniture as fol lows: , 2 office desks, 1 exec Project implementation and Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 15,700.00 0.00 2020-06-01 2020-07-27 2021-01-23 utive table , 2 executive chai monitoring tions nvelope ementation r high back orthopedic, 1 sec retarial chair, 4 visitors chair s, 9 executive chair high bac k swivel KE-MOH-175673-GO-DIR / Pr ocurement of 15 heavy duty Response, capacity building IDA / 65980 Post Direct Selection Direct 1,020,000.00 797,272.69 Signed 2020-05-27 2020-05-19 2020-06-01 2020-06-04 2020-07-06 2020-06-12 2021-01-02 double cabin vehicle, and 1 h and training eavy duty passenger vehicle KE-MOH-173607-GO-DIR / Ai rtime for 2125 community he alth extension workers for 3 Project implementation and Pending Impl IDA / 65980 Post Direct Selection Direct 129,150.00 0.00 2020-05-28 2020-06-02 2020-07-07 2021-01-03 months @KES 2000 per mont monitoring ementation h, Airtime for 11 project pers onnel for 3 months@ KES 50 00 per month KE-MOH-173609-GO-RFQ / Pr Quarintine, isolation and tre Request for Quota Single Stage - One E IDA / 65980 Post Limited 147,200.00 0.00 Canceled 2020-06-02 2020-06-09 2020-07-28 2021-01-24 ocurement of 1840 No. Ther atement centres tions nvelope moguns KE-MOH-168100-GO-RFQ / Pr int and distribute guidelines, booklets, modules and forms: Response, capacity building Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 75,000.00 0.00 2020-06-05 2020-07-31 2021-01-27 2000 contact tracing forms, and training tions nvelope ementation 2000 No. case investigation f orms and training modules KE-MOH-178412-GO-RFQ / Pr ocure assorted items to set u p grievance hotline: 1.No. Gri evance Redress Mechanism Project implementation and Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 12,500.00 0.00 2020-06-10 2020-06-24 2020-12-21 Software, 1 No. 4 way work s monitoring tions nvelope ementation tation, 4 No. Desktop compu ters, 1 No. Medium duty 3-i n -1 printer, 3 No. Telephone handsets and 2 No. mobile p hone KE-MOH-182114-GO-RFQ / Pr Project implementation and Request for Quota Single Stage - One E Pending Impl ocurement of 5 No. Laptop c IDA / 65980 Post Limited 9,500.00 0.00 2020-07-02 2020-07-21 2021-01-17 monitoring tions nvelope ementation omputers and 5 No. mobile P hones KE-MOH-173603-GO-RFQ / p Medical supplies and equipm Request for Quota Single Stage - One E Pending Impl rocurement of 368 hand was IDA / 65980 Post Limited 552,000.00 0.00 2020-06-08 2020-08-03 2021-01-30 ent tions nvelope ementation hing stations and accessorie s Page 3 KE-MOH-184648-GO-RFQ / Pr inting of 500 copies of Grieva nce Redress Mechanism one pager,1000 copies of Gender Project implementation and Request for Quota Single Stage - One E Pending Impl Based Violence/SEA one pag IDA / 65980 Post Limited 7,700.00 0.00 2020-07-20 2020-07-28 2020-10-30 monitoring tions nvelope ementation er,1000 copies of Abbreviate d Code of Conduct, 200 copie s of Grievance Redress Mech anism Register Log and 1000 copies of Patient feedback fo rm KE-MOH-188957-GO-RFQ / Pr inting of 38,286 copies of bo Availability of safe blood and Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 111,852.00 0.00 2020-08-28 2020-09-18 2020-12-23 oklets, forms,charts, Register blood products tions nvelope ementation s and reporting tools KE-MOH-188960-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 100,800.00 0.00 2020-08-26 2020-09-25 2021-03-24 ocure 144 blood donor coach blood products tions nvelope ementation es KE-MOH-189116-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of 140,000 Haem IDA / 65980 Post Limited 142,800.00 0.00 2020-08-29 2020-10-24 2021-04-22 blood products tions nvelope ementation oglobin estimation cuvettes KE-MOH-189120-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of 3,000 Quadrupl IDA / 65980 Post Limited 24,000.00 0.00 2020-08-30 2020-10-25 2021-04-23 blood products tions nvelope ementation e blood bags KE-MOH-189122-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of 10,000 Tripple IDA / 65980 Post Limited 60,000.00 0.00 2020-08-30 2020-10-25 2021-04-23 blood products tions nvelope ementation Blood Bags KE-MOH-189123-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of 12,000 Double IDA / 65980 Post Limited 60,000.00 0.00 2020-08-30 2020-10-25 2021-04-23 blood products tions nvelope ementation Blood Bags KE-MOH-189126-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 7,500.00 0.00 2020-08-30 2020-10-25 2021-04-23 ocurement of 2,500 Single Bl blood products tions nvelope ementation ood Bags KE-MOH-189129-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of 2,500 Paediatri IDA / 65980 Post Limited 17,500.00 0.00 2020-08-30 2020-10-25 2021-04-23 blood products tions nvelope ementation c Blood bags KE-MOH-188959-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocure 2 refrigerated vehicles IDA / 65980 Post Limited 180,000.00 0.00 2020-10-20 2021-03-02 2021-02-18 blood products tions nvelope ementation for ferring large amounts of b lood KE-MOH-189103-GO-DIR / Pr ocurement of 21,000 TTI scre Availability of safe blood and Pending Impl IDA / 65980 Post Direct Selection Direct 105,000.00 0.00 2020-09-27 2020-10-02 2020-10-28 2020-11-27 ening reagents Murex for Eti blood products ementation max machines in all the 6 re gional testing sites KE-MOH-189093-GO-DIR / Pr Availability of safe blood and Under Imple ocurement of 54,000 TTI Scr IDA / 65980 Post Direct Selection Direct 594,000.00 0.00 2020-09-27 2020-09-16 2020-10-02 2020-09-23 2020-10-28 2020-11-27 blood products mentation eening reagents Liaison for Li asion Equipment KE-MOH-189110-GO-DIR / Pr ocurement of 66,000 Blood G Availability of safe blood and Pending Impl IDA / 65980 Post Direct Selection Direct 264,000.00 0.00 2020-09-27 2020-10-02 2020-10-28 2020-11-27 rouping reagents Qwalys for blood products ementation Blood Grouping machines in Embu and Nakuru KE-MOH-176216-GO-RFB / P Medical supplies and equipm Single Stage - One E Pending Impl ROVISION OF 24-HOUR STAN IDA / 65980 Post Request for Bids Open - National 486,000.00 0.00 2020-09-24 2020-09-24 2020-10-07 2020-10-14 2020-11-11 2021-05-10 ent nvelope ementation DBY AMBULANCE SERVICES F OR 6 MONTHS KE-MOH-196696-GO-RFQ / Pr Medical supplies and equipm Request for Quota Single Stage - One E Pending Impl ocurement of assorted Furnit IDA / 65980 Post Limited 33,600.00 0.00 2020-10-12 2020-11-06 2020-12-04 ent tions nvelope ementation ure for use in Mama Lucy Ho spital KE-MOH-196698-GO-RFQ / Pr Medical supplies and equipm Request for Quota Single Stage - One E Pending Impl ocurement of ICT equipment IDA / 65980 Post Limited 28,000.00 0.00 2020-10-09 2020-11-11 2020-12-11 ent tions nvelope ementation for use in Mama Lucy Hospita l KE-MOH-196699-GO-RFQ / Pr Medical supplies and equipm Request for Quota Single Stage - One E Pending Impl ocurement of Laundry equip IDA / 65980 Post Limited 180,000.00 0.00 2020-10-12 2020-11-30 2020-12-30 ent tions nvelope ementation ment for use in Mama Lucy H ospital KE-MOH-189135-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of 6 Hematology IDA / 65980 Post Limited 93,600.00 0.00 2020-11-27 2020-12-13 2021-01-22 blood products tions nvelope ementation analyzer and 72 Hematology analyzer kits KE-MOH-196868-GO-RFQ / Pr ocurement of blood collectio n and processing equipment Availability of safe blood and Request for Quota Single Stage - One E Pending Impl as follows: IDA / 65980 Post Limited 584,700.00 0.00 2020-11-13 2021-01-01 2021-04-01 blood products tions nvelope ementation 1. 15 manual component sep arator 2. 18 automated component expressor/extractor KE-MOH-196697-GO-RFQ / Pr ocure 100 Pillows with covers , 200 Blankets, 200 pairs of b Medical supplies and equipm Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 26,500.00 0.00 2020-11-11 2020-12-13 2021-01-10 ed sheets (large), 200 Draw s ent tions nvelope mentation heets, 40 window curtain rail s and 40 hospital window cur tains for Mama Lucy Hospital KE-MOH-189013-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocure 20 backup diesel gener IDA / 65980 Post Limited 950,000.00 0.00 2020-11-22 2020-12-21 2021-03-22 blood products tions nvelope ementation ators 10-12 KVA KE-MOH-189113-GO-DIR / Pr ocurement of 102,000 blood Availability of safe blood and Pending Impl IDA / 65980 Post Direct Selection Direct 601,800.00 0.00 2020-11-06 2020-11-11 2020-11-24 2020-12-24 grouping reagents Immucore blood products ementation for six regional testing centre s KE-MOH-200443-GO-RFQ / Pr ocurement of assorted blood processing equipment broke Availability of safe blood and Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 260,700.00 0.00 2020-11-14 2020-12-19 2021-03-19 n down as follows: blood products tions nvelope ementation 1. 35 Tube Sealer 2. 155 Tube Strippers Page 4 KE-MOH-200449-GO-RFQ / Pr ocurement of Availability of safe blood and Request for Quota Single Stage - One E Pending Impl 1. 8 refrigerated centrifuges IDA / 65980 Post Limited 571,550.00 0.00 2020-11-20 2021-01-01 2021-04-01 blood products tions nvelope ementation 2. 8 platelet agitators 3. 33 blood weighing scales KE-MOH-200457-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 280,000.00 0.00 2020-11-09 2020-12-21 2021-03-21 ocurement of 800 Apheresis blood products tions nvelope ementation kits KE-MOH-201450-GO-RFQ / Pr Medical supplies and equipm Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 15,000.00 0.00 2020-11-20 2020-12-29 2021-01-29 ocurement of a Public Addres ent tions nvelope ementation s System KE-MOH-196873-GO-RFQ / Pr ocurement of assorted Blood cold chain broken down as fo Availability of safe blood and Request for Quota Single Stage - One E Pending Impl llows: IDA / 65980 Post Limited 565,500.00 0.00 2020-11-13 2021-01-01 2021-04-01 blood products tions nvelope ementation 1. 8 blood bank refrigerators 2. 8 blood bank freezers 3. 1 bio bank 4. 231 blood transportation b oxes KE-MOH-188958-GO-DIR / Pr ocure 10 customized 7 seate Availability of safe blood and r passenger vans separate co IDA / 65980 Post Direct Selection Direct 700,000.00 0.00 Completed 2020-11-29 2021-06-03 2020-12-04 2021-06-03 2020-12-19 2021-01-18 2022-01-16 blood products mpartment for commodities and blood bags with overhea d carrier KE-MOH-204854-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 150,000.00 0.00 2020-12-05 2020-11-09 2021-01-05 2021-02-04 ocurement of Blood cold roo blood products tions nvelope mentation ms KE-MOH-203440-GO-RFQ / Pr ocurement of parts to enable Availability of safe blood and Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 15,000.00 0.00 2021-01-22 2021-02-22 2021-04-23 repair of equipment at the Ke blood products tions nvelope ementation nya National Blood Transfusi on by the Engineer KE-MOH-189012-GO-RFQ / S upply and Installation of No. Availability of safe blood and Request for Quota Single Stage - One E Pending Impl 40 Air conditioners (18 BTU) IDA / 65980 Post Limited 80,000.00 0.00 2021-02-07 2021-03-18 2021-09-14 blood products tions nvelope ementation to be installed in the various Kenya National Blood Transfu sion Centres countrywide KE-MOH-196881-GO-RFQ / Pr ocurement of assorted Temp erature monitors broken dow n as follows: Availability of safe blood and Request for Quota Single Stage - One E Pending Impl 1. 78 remote temperature m IDA / 65980 Post Limited 112,200.00 0.00 2021-02-08 2021-03-29 2021-06-27 blood products tions nvelope ementation onitor fitted on static cold ch ain equipment 2. 144 remote temperature monitor fitted on mobile cold chain equipment KE-MOH-215327-GO-RFQ / Pr ocurement of 100 No. High f Medical supplies and equipm Request for Quota Single Stage - One E Pending Impl low nasal cannulas required IDA / 65980 Post Limited 800,000.00 0.00 2021-02-10 2021-03-24 2021-06-22 ent tions nvelope ementation during oxygen therapy for cri tically ill patients including C OVID-19 patients KE-MOH-216887-GO-RFQ / Pr ocurement of Furniture for us Quarintine, isolation and tre Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 47,000.00 0.00 2021-02-14 2021-03-26 2021-05-25 e at the Kenyatta University atement centres tions nvelope ementation Teaching and Referral Hospit al Isolation Facility KE-MOH-226662-GO-RFQ / Pr Project implementation and Request for Quota Single Stage - One E Pending Impl ocure 2 No laptops ,2 No Mod IDA / 65980 Post Limited 4,000.00 0.00 2021-04-10 2021-05-29 2021-06-28 monitoring tions nvelope ementation ems and 2 No Mobile phones KE-MOH-227263-GO-RFQ / S Community discussion and i Request for Quota Single Stage - One E Pending Impl upply, Delivery, Installation o IDA / 65980 Post Limited 93,600.00 0.00 2021-04-13 2021-06-08 2021-12-05 nformation outreach tions nvelope ementation f hardware and networking f or the Call Centre KE-MOH-229145-GO-DIR / Su pply, Delivery ,Installation of Medical supplies and equipm IDA / 65980 Post Direct Selection Direct 500,000.00 0.00 Completed 2021-04-13 2021-04-13 2021-04-15 2021-04-22 2021-04-28 2021-06-08 2021-12-10 two (2 No) 20,000 liter Bulk ent Oxygen tank and Accessories KE-MOH-229791-GO-RFQ / S upply and Delivery of Person Medical supplies and equipm Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 426,821.00 0.00 2021-04-22 2021-04-26 2021-04-28 2021-05-11 al Protective Equipment's for ent tions nvelope mentation the COVID-19 testing labora tories KE-MOH-229861-GO-RFQ / S upply and Delivery of 2,070 p Medical supplies and equipm Request for Quota Single Stage - One E Pending Impl ieces of 500 ml Sanitizers an IDA / 65980 Post Limited 13,747.00 0.00 2021-04-26 2021-05-31 2021-06-07 ent tions nvelope ementation d 42 (No)pack of 100 Biohaz ard Bags for COVID -19 Test ing Laboratories KE-MOH-233863-GO-DIR / Su pply and Delivery of bulk 20, 000 liters of cryogenic liqui d medical Oxygen in KNH M Medical supplies and equipm bagathi Hospital and bulk 2 IDA / 65980 Post Direct Selection Direct 1,440,000.00 0.00 Signed 2021-05-13 2021-05-13 2021-05-18 2021-08-18 2021-06-22 2022-03-23 ent 0,000 liters of cryogenic liq uid medical Oxygen in Keny atta University Teaching and Referral Hospital for 24 times in each Hospital. KE-MOH-235971-GO-DIR / Su pply, Delivery Installation and commissioning of a 10, Medical supplies and equipm 000 liter liquid Oxygen tank IDA / 65980 Post Direct Selection Direct 490,000.00 0.00 Canceled 2021-05-26 2021-05-31 2021-07-05 2022-05-31 ent (1 No) and supply of Medic al Oxygen for one year (24 ti mes) in Nakuru Level 5 Hospi tal -Nakuru County KE-MOH-235998-GO-DIR / Su pply, Delivery ,Installation an d commissioning of a 8,000 li Medical supplies and equipm ter liquid Oxygen tank (1 No) IDA / 65980 Post Direct Selection Direct 408,000.00 0.00 Canceled 2021-05-26 2021-05-31 2021-07-05 2022-05-31 ent and supply of Medical Oxyge n for one year (24 times) in K ericho County Referral Hospit al-Kericho County Page 5 KE-MOH-236003-GO-DIR / Su pply, Delivery, Installation an d commissioning of a 6 ,000 l Medical supplies and equipm iter liquid Oxygen tank (1 No) IDA / 65980 Post Direct Selection Direct 316,000.00 0.00 Canceled 2021-05-26 2021-05-31 2021-06-23 2022-06-29 ent and supply of Medical Oxyge n for one year (24 times) in Pumwani Hospital -Nairobi Co unty as per specifications. KE-MOH-235999-GO-DIR / Su pply, Delivery Installation an d commissioning of a 8,000 li Medical supplies and equipm IDA / 65980 Post Direct Selection Direct 408,000.00 0.00 Canceled 2021-05-31 2021-06-05 2021-07-10 2022-06-29 ter liquid Oxygen tank (1 No) ent and supply of Medical Oxyge n for one year (24 times) in K itui County Hospital-Kitui Co unty KE-MOH-240389-GO-DIR / Su pply and Delivery of 384 uni ts of Medical Air in 7,600 litr Medical supplies and equipm Pending Impl IDA / 65980 Post Direct Selection Direct 12,288.00 0.00 2021-06-25 2021-06-30 2021-08-04 2022-01-31 e cylinder at Moiben Sub Hos ent ementation pital -Uasin Gishu County (Lo t 1) and Kericho County Refe rral Hospital (Lot 2) KE-MOH-240474-GO-RFQ / Pr ocure Spare parts for repairs Availability of safe blood and Request for Quota Single Stage - One E Pending Impl of various cold chain equipm IDA / 65980 Post Limited 43,750.00 0.00 2021-06-27 2021-08-12 2022-02-08 blood products tions nvelope ementation ent and servicing tools for K enya National Blood Transfus ion services KE-MOH-244311-GO-RFQ / Pr ocurement of One Hundred T housand (100,000 No.) Spin Medical supplies and equipm Request for Quota Single Stage - One E Pending Impl column manual RNA extracti IDA / 65980 Post Limited 646,200.00 0.00 2021-08-04 2021-08-31 2021-10-11 ent tions nvelope ementation on kits (pack of 200 reactions ) to be delivered to twenty se ven (27 No.) Ministry of Healt h supported laboratories. KE-MOH-244775-GO-RFQ / P urchase of 24 No. audio recor Community discussion and i Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 2,400.00 0.00 2021-08-07 2021-10-02 2022-03-31 ders to record vernacular au nformation outreach tions nvelope mentation dio messages for the VMG co mmunities KE-MOH-244807-GO-RFQ / Pr ocurement COVID-19 testing Medical supplies and equipm Request for Quota Single Stage - One E Pending Impl reagents consumables to be IDA / 65980 Post Limited 63,903.80 0.00 2021-08-04 2021-09-01 2021-10-15 ent tions nvelope ementation delivered to Twenty seven (2 7No.) Ministry of Health supp orted laboratories. KE-MOH-240381-GO-DIR / Su pply and Delivery of 1,680 un its of Medical Air in 7,600 Lit Medical supplies and equipm Pending Impl IDA / 65980 Post Direct Selection Direct 53,760.00 0.00 2021-07-28 2021-08-02 2021-09-06 2021-10-31 er Cylinders in Uasin Gishu, N ent ementation akuru, Mombasa, Taita tavet a, Nairobi and Kitui Counties. KE-MOH-244809-GO-RFQ / S upply and installation of gen Availability of safe blood and Request for Quota Single Stage - One E Under Imple erator houses for the 20 unit IDA / 65980 Post Limited 50,000.00 0.00 2021-08-17 2021-09-28 2021-09-14 2021-10-28 blood products tions nvelope mentation s of 12 KVA diesel powered g enerators in blood satellite c enters within the Country. KE-MOH-250286-GO-DIR / Su pply and delivery of compres Medical supplies and equipm Under Imple IDA / 65980 Post Direct Selection Direct 1,205,000.00 0.00 2021-08-31 2021-10-06 2021-09-05 2021-10-10 2022-04-08 sed medical oxygen and liqui ent mentation d oxygen to support COVID-1 9 response KE-MOH-253487-GO-DIR / Pr Availability of safe blood and Under Imple ocurement of two (2No.) cust IDA / 65980 Post Direct Selection Direct 180,000.00 0.00 2021-09-16 2021-12-14 2021-09-21 2021-10-26 2022-04-24 blood products mentation omized motor vehicles MOH/CHERP/VACC/01/2021- 2022 / Procure 13,333,333 N o. Doses of vaccine,14,667,5 Medical supplies and equipm Pending Impl IDA / 65980 Prior Direct Selection Direct 116,253,234.41 0.00 2021-08-09 2021-08-14 2021-09-18 2022-03-17 00 No.Auto-disable syringe w ent ementation ith needle,146,675 No. safety boxes for safe needle dispos al KE-MOH-253446-GO-RFQ / Pr ocurement of Personal Protec Medical supplies and equipm Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 495,928.00 0.00 2021-09-25 2021-11-02 2021-11-20 2022-05-19 tive Equipment (PPEs) for CO ent tions nvelope mentation VID-19 Testing Laboratories KE-MOH-253423-GO-RFQ / Pr ocurement of Pediatric High Medical supplies and equipm Request for Quota Single Stage - One E Under Imple Flow Nasal Cannula consuma IDA / 65980 Post Limited 649,000.00 0.00 2021-09-30 2021-10-28 2021-11-30 ent tions nvelope mentation bles (1,000No.) and Heated B reathing Circuit (6,000No.) KE-MOH-253431-GO-RFQ / Pr ocurement of Adult High Flo Medical supplies and equipm Request for Quota Single Stage - One E Under Imple w Nasal Cannula (HFNC): 6,0 IDA / 65980 Post Limited 838,150.00 0.00 2021-09-30 2021-10-28 2021-11-30 ent tions nvelope mentation 00No. consumables, 5,000No . Humidification chamber and 1,200No. Air filters. KE-MOH-261311-GO-RFQ / Pr Gender Based Violence Resp Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 167,953.52 0.00 2021-11-12 2022-01-07 2022-07-06 ocurement of Post Rape Care onse tions nvelope mentation (PRC) kits KE-MOH-261292-GO-RFQ / Pr ocurement of office equipme Project implementation and Request for Quota Single Stage - One E Pending Impl nt, furniture, photocopier ma IDA / 65980 Post Limited 60,610.00 0.00 2021-12-27 2022-02-21 2022-08-20 monitoring tions nvelope ementation chines, laptops and mobile p hones for the Project Manage ment Team (PMT) KE-MOH-268683-GO-RFQ / Pr Project implementation and Request for Quota Single Stage - One E Pending Impl ocurement of 40ft by 80ft pa IDA / 65980 Post Limited 12,000.00 0.00 2021-12-27 2022-02-21 2022-08-20 monitoring tions nvelope ementation rtitioned container store KE-MOH-275963-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E ocurement of liaison reagent IDA / 65980 Post Limited 4,716.23 0.00 Canceled 2022-02-12 2022-04-09 2022-10-06 blood products tions nvelope s and accessories KE-MOH-275975-GO-RFQ / Pr ocurement of temperature m Availability of safe blood and Request for Quota Single Stage - One E IDA / 65980 Post Limited 21,350.00 0.00 Completed 2022-02-12 2022-03-01 2022-04-09 2022-10-06 2022-09-21 onitoring devices- 500pcs of blood products tions nvelope Blood Bank Thermometers Page 6 KE-MOH-276060-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of 82No. boxes of IDA / 65980 Post Limited 7,171.37 0.00 2022-02-12 2022-04-09 2022-10-06 blood products tions nvelope ementation wash system liquid KE-MOH-276064-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E ocurement of liaison reagent' IDA / 65980 Post Limited 5,554.07 0.00 Canceled 2022-02-26 2022-04-23 2022-10-20 blood products tions nvelope s accessories KE-MOH-275952-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E ocurement of 240No. 200 Te IDA / 65980 Post Limited 136,620.00 0.00 Canceled 2022-02-26 2022-04-23 2022-10-20 blood products tions nvelope st kits Liaison XI Murex HBS AG KE-MOH-275947-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E ocurement of 240No. 200Tes IDA / 65980 Post Limited 136,620.00 0.00 Canceled 2022-03-02 2022-04-23 2022-10-20 blood products tions nvelope t kits of Liaison XI Murex HIV AG/AB KE-MOH-275960-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E ocurement of 240No., 200 te IDA / 65980 Post Limited 101,527.10 0.00 Canceled 2022-03-02 2022-04-27 2022-10-24 blood products tions nvelope st kits Liaison Treponema scr een KE-MOH-276066-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 9,962.02 0.00 2022-03-02 2022-04-27 2022-10-24 ocurement of assorted blood blood products tions nvelope ementation products KE-MOH-275980-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E IDA / 65980 Post Limited 12,000.00 0.00 Canceled 2022-03-02 2022-04-27 2022-10-24 ocurement of 120No. Hygro blood products tions nvelope meters KE-MOH-275973-GO-RFQ / Pr ocurement of 1,969 No. 50 te Availability of safe blood and Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 142,752.50 0.00 2022-03-02 2022-03-01 2022-04-27 2022-10-24 sts Hemoglobin Estimation C blood products tions nvelope mentation uvettes for use with Hema C hroma HB meter KE-MOH-275958-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Under Imple ocurement of 480No. 100 te IDA / 65980 Post Limited 173,591.60 0.00 2022-03-02 2022-03-09 2022-04-23 2022-10-20 blood products tions nvelope mentation st kits Liaison XI Murex HCV AB KE-MOH-279996-GO-DIR / Pr ocurement of assorted cold c Medical supplies and equipm Under Imple IDA / 65980 Prior Direct Selection Direct 8,044,746.97 0.00 2022-03-14 2022-04-11 2022-03-19 2022-07-25 2022-04-23 2022-10-20 hain equipment, associated s ent mentation pare parts and post installati on services KE-MOH-288063-GO-RFQ / Pr ocurement of twenty four (24 Availability of safe blood and Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 8,400.00 0.00 2022-04-16 2022-06-11 2022-12-08 No.) blood pressure machine blood products tions nvelope ementation s and twelve (12No.) hemogl obin meters KE-MOH-288060-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of twelve (12No.) IDA / 65980 Post Limited 9,300.00 0.00 2022-04-16 2022-06-11 2022-12-08 blood products tions nvelope ementation manual plasma extractors KE-MOH-288018-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E ocurement of seven (7No) ref IDA / 65980 Post Limited 321,000.00 0.00 Completed 2022-04-16 2022-04-15 2022-06-11 2022-12-08 2023-01-27 blood products tions nvelope rigerated centrifuge KE-MOH-288069-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Under Imple ocurement of 1,940No. Apher IDA / 65980 Post Limited 562,600.00 0.00 2022-04-16 2022-06-10 2022-06-11 2022-12-08 blood products tions nvelope mentation esis kits to be used with Aph eresis machine KE-MOH-288103-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of 211No. assort IDA / 65980 Post Limited 112,180.00 0.00 2022-04-16 2022-06-11 2022-12-08 blood products tions nvelope ementation ed Hematology analyzers KE-MOH-288107-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of 42No. assorted IDA / 65980 Post Limited 198,340.00 0.00 2022-04-16 2022-06-11 2022-12-08 blood products tions nvelope ementation coagulation kits KE-MOH-288022-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E ocurement of five (5No.) plat IDA / 65980 Post Limited 125,000.00 0.00 Completed 2022-04-16 2022-04-15 2022-06-11 2022-12-08 2023-01-28 blood products tions nvelope elet agitators KE-MOH-288029-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of twelve (12No.) IDA / 65980 Post Limited 6,160.00 0.00 2022-04-16 2022-06-11 2022-12-08 blood products tions nvelope ementation blood weighing scales KE-MOH-288017-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E ocurement of 15No. blood ba IDA / 65980 Post Limited 300,000.00 0.00 Completed 2022-04-16 2022-04-15 2022-06-11 2022-12-08 2023-01-28 blood products tions nvelope nk freezers KE-MOH-288050-GO-RFQ / Pr ocurement of thirty six (36No Availability of safe blood and Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 4,320.00 0.00 2022-04-16 2022-06-11 2022-12-08 .) digital thermometers and t blood products tions nvelope ementation wenty four (24No.) pair of sci ssors KE-MOH-288034-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of Forty eight (48 IDA / 65980 Post Limited 18,600.00 0.00 2022-04-16 2022-06-11 2022-12-08 blood products tions nvelope ementation No.) cool boxes (large and s mall size) KE-MOH-298204-GO-RFQ / Pr ocurement of 113 Desktop co Availability of safe blood and Request for Quota Single Stage - One E IDA / 65980 Post Limited 372,770.00 0.00 Signed 2022-06-22 2022-06-07 2022-08-17 2023-02-13 mputers, 113 UPS and 146 L blood products tions nvelope aptop computers KE-MOH-298933-GO-RFQ / Pr ocurement of wireless intern et network connectivity for K enya National Blood Transfus Availability of safe blood and Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 507,747.50 0.00 2022-06-22 2022-06-07 2022-08-17 2023-02-13 ion and Organ Trans[plant Se blood products tions nvelope mentation rvice (KNBTTS) six (6) region al sites, 23 satellite sites with more than three (3) rooms a nd 11 satellite sites with one (1) room KE-MOH-298941-GO-RFQ / Pr ocurement of 100No. Wireles Availability of safe blood and Request for Quota Single Stage - One E Pending Impl s Local Area Network (LAN) a IDA / 65980 Post Limited 15,960.00 0.00 2022-06-25 2022-08-20 2023-02-16 blood products tions nvelope ementation daptors and 36No. Automati c Voltage Switcher (AVS 30) f or KNBTS KE-MOH-288013-GO-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E ocurement of 15No. blood ba IDA / 65980 Post Limited 225,000.00 0.00 Completed 2022-06-25 2022-05-04 2022-08-20 2023-02-16 2023-01-27 blood products tions nvelope nk refrigerators Page 7 KE-MOH-298712-GO-RFQ / Pr ocurement of 190 No. Barcod Availability of safe blood and Request for Quota Single Stage - One E Under Imple e scanners, 96No. Ordinary p IDA / 65980 Post Limited 200,900.00 0.00 2022-07-03 2022-06-07 2022-08-28 2023-02-24 blood products tions nvelope mentation rinters, 94No. Label printers, 1,250No Printer ribbons and 1,250 Printer ribbon labels KE-MOH-300691-NC-RFQ / Pr ocurement of printing service s to print 8,000No policy doc ument, intergovernmental fr Availability of safe blood and Request for Quota Single Stage - One E amework on blood services IDA / 65980 Post Limited 80,000.00 0.00 Signed 2022-07-30 2022-08-01 2022-09-24 2023-03-23 blood products tions nvelope management, standards, ma nuals and guidelines for the Kenya National Blood Transfu sion, Tissue and Human Orga n Transplant Services (KNBTT S) KE-MOH-306741-GO-RFQ / Pr ocurement of ABO/Rh Blood Availability of safe blood and Request for Quota Single Stage - One E IDA / 65980 Post Limited 445,992.00 0.00 Completed 2022-08-07 2022-08-10 2022-10-02 2023-03-31 2023-01-14 Grouping reagent Kits for use blood products tions nvelope in the Six KNBTTS Sites acros s the Country KE-MOH-307619-GO-RFB / Pr ocurement of 1000 Apheresis Kits, 3 Units of Hematology A nalysers, 52 Hematology Kits Availability of safe blood and Single Stage - One E Under Imple , 36 Hematology Controls an IDA / 65980 Post Request for Bids Open - National 575,614.00 0.00 2022-08-10 2022-06-10 2022-08-15 2023-04-14 2022-09-26 2022-06-20 2022-10-26 2022-11-30 2023-05-29 blood products nvelope mentation d 36 Hematology Calibrators, 6 Units of Coagulation Analys ers, 12 Reagent sets for FII, 1 2 Reagents sets for FVII and 12 Quality Controls KE-MOH-307911-GO-RFQ / Pr ocurement of ICT Equipment Availability of safe blood and Request for Quota Single Stage - One E IDA / 65980 Post Limited 94,360.00 0.00 Completed 2022-08-13 2022-06-07 2022-10-08 2023-04-06 's for KNBTS; 40 Desktops 1 blood products tions nvelope 6 Laptops, 100 Wireless LAN and 36AVS KE-MOH-310387-GO-RFQ / Pr ocurement of Goods for KNB TS Mini Data Center to assist Availability of safe blood and Request for Quota Single Stage - One E Pending Impl in data security and continuo IDA / 65980 Post Limited 584,250.00 0.00 2022-08-30 2022-10-25 2023-04-23 blood products tions nvelope ementation us functioning of Damu-Ke sy stem. The data center will be located at KNBTS Headquart ers Nairobi KE-MOH-322982-GO-RFQ / Pr ocurement of 60No. Label Pri Availability of safe blood and Request for Quota Single Stage - One E IDA / 65980 Post Limited 156,000.00 0.00 Signed 2022-10-30 2023-02-20 2022-12-25 2023-06-23 nters for Kenya National Bloo blood products tions nvelope d Transfusion Services KE-MOH-323698-GO-RFQ / S upply, Delivery Installation, t esting and commissioning of 768,000 liters Oxygen Tanks Medical supplies and equipm Request for Quota Single Stage - One E Under Imple in 4 lots: Lot 1 Nakuru Count IDA / 65980 Post Open - National 555,343.00 0.00 2022-12-21 2023-02-15 2023-08-14 ent tions nvelope mentation y Hospital 10000 Liters Lot 2 Kitui County Hospital 8000 Li ters Lot 3 Kitui County Hospit al 8000 Liters Lot 4 Pumwani Hospital 6000 Liters KE-MOH-330324-GO-RFQ / Pr ocurement of the following R egisters for KNBTS: Clinical/L Availability of safe blood and Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 20,250.00 0.00 2022-12-27 2023-02-20 2023-02-21 2023-08-20 aboratory Register 1500 Piec blood products tions nvelope mentation es, Cross Match Register 600 Pieces, Blood Component Re gister 600 Pieces KE-MOH-330973-GO-RFQ / Pr ocurement of 504 vials of Ex Availability of safe blood and Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 9,600.00 0.00 2023-01-27 2023-02-24 2023-03-24 2023-09-20 ternal Quality Assurance Pan blood products tions nvelope mentation els for KTTA for a period of 1 2 Months KE-MOH-01-2022/2023-GO-R FQ / Supply and delivery of 1 3Desktops, 13UPs and 11Lap Availability of safe blood and Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 64,200.00 0.00 2023-04-01 2023-04-19 2023-05-27 2023-11-23 tops for Kenya Tissue and Tr blood products tions nvelope mentation ansplant Authority Blood Ma nagement Information Syste m (Damu-Ke) KE-MOH-03-2022/2023-GO-R FQ / Procurement of 3 Laptop Project implementation and Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 12,800.00 0.00 2023-04-24 2023-06-19 2023-12-16 s, 5 desktops and 1 printer fo monitoring tions nvelope mentation r Project Management Team KE-MOH-16-2022/2023-GO-R FQ / Procurement of 10No. La ptops, Customer Relationship Community discussion and i Request for Quota Single Stage - One E Under Imple Management Software, Micro IDA / 65980 Post Limited 50,000.00 0.00 2023-05-15 2023-07-10 2024-01-06 nformation outreach tions nvelope mentation soft Professional 2021 Licens e, Firewall Annual License for two years and 10No. Call Cen ter Headsets KE-MOH-18-2022/2023-GO-R FQ / Power Back Up and CCT Community discussion and i Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 88,000.00 0.00 2023-05-10 2023-07-05 2024-01-01 V Cameras for call center at nformation outreach tions nvelope ementation Primary Healthcare KE-MOH-168074-GO-DIR / Pr Response, capacity building IDA / 65980 Post Direct Selection Direct 150,000.00 0.00 Canceled 2020-04-20 2020-04-25 2020-05-30 2020-11-26 ocure 3000 mobile phones and training KE-MOH-06-2022/2023-GO-R Community discussion and i Request for Quota Single Stage - One E Pending Impl FQ / Supply and Delivery of A IDA / 65980 Post Limited 62,000.00 0.00 2023-05-20 2023-07-15 2024-01-11 nformation outreach tions nvelope ementation utomatic Fire suppression Sy stem KE-MOH-320083-GO-RFQ / Pr ocurement of 3 Micro Centrif Medical supplies and equipm Request for Quota Single Stage - One E Under Imple uge, 3 Laboratory Water Bat IDA / 68230 Post Limited 45,473.00 0.00 2023-05-20 2023-07-15 2024-01-11 ent tions nvelope mentation h and 3 Bio-safety Class II Ca binet for National Laboratory Services KE-MOH-189091-GO-DIR / Pr Availability of safe blood and ocure 54,000 Abbot Reagent IDA / 65980 Post Direct Selection Direct 648,000.00 0.00 Canceled 2020-09-27 2020-10-02 2020-10-28 2020-11-27 blood products s Testing Kits for Abbot Equip ment Page 8 KE-MOH-08-2022/2023-GO-R FB / Supply and Delivery of 1 42,816 pieces of Double Bloo Availability of safe blood and Single Stage - One E Pending Impl d Bags, 39,350 pieces of Trip IDA / 68230 Post Request for Bids Open - National 1,240,000.00 0.00 2023-06-09 2023-06-13 2023-07-12 2023-07-17 2023-08-02 2023-10-31 blood products nvelope ementation le Blood Bags, 11,309 pieces of Quadruple Blood Bags for Kenya Tissue and Transplant Authority NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOH-168078-NC-RFQ / D evelopment of a platform for Response, capacity building Event based surveillance at t IDA / 65980 Post Direct Selection Direct 40,000.00 0.00 Canceled 2020-04-17 2020-04-22 2020-05-27 2020-11-23 and training he facilities and Community based surveillance at the co mmunity level KE-MOH-185606-NC-RFB / P ROVISION OF 24 HOUR STAN D BY AMBULANCE SERVICE: 1 Response, capacity building Single Stage - One E Pending Impl IDA / 65980 Post Request for Bids Open - National 1,752,000.00 0.00 2020-07-28 2020-08-02 2020-08-12 2020-08-19 2020-09-03 2021-03-02 6 AMBULANCES(6 ADVANCE and training nvelope ementation D CARDIAC LIFE SUPPORT & 10 BASIC LIFE SUPPORT) FOR A PERIOD OF 1 YEAR(365 DA YS) KE-MOH-189139-NC-DIR / Pr ocurement of Courier Service s to transport blood samples, Availability of safe blood and Pending Impl components, supplies and ot IDA / 65980 Post Direct Selection Direct 198,000.00 0.00 2020-08-26 2020-08-31 2020-10-05 2021-04-03 blood products ementation her documents from the Nati onal Blood Transfusion centr e to the other parts of the co untry. KE-MOH-204853-NC-RFQ / Pr Availability of safe blood and Request for Quota Single Stage - One E Pending Impl ocurement of a Quality Assur IDA / 65980 Post Limited 25,000.00 0.00 2020-12-05 2021-01-05 2021-02-04 blood products tions nvelope ementation ance Scheme KE-MOH-212377-NC-RFQ / R Availability of safe blood and Request for Quota Single Stage - One E Pending Impl epair of Cold Rooms in the K IDA / 65980 Post Limited 200,000.00 0.00 2021-01-25 2021-02-26 2021-05-27 blood products tions nvelope ementation enya National Blood Transfus ion centres KE-MOH-212369-NC-RFQ / R Availability of safe blood and Request for Quota Single Stage - One E Pending Impl epair of Incinerators in the K IDA / 65980 Post Limited 80,000.00 0.00 2021-01-27 2021-02-26 2021-05-27 blood products tions nvelope ementation enya National Blood Transfus ion Centres KE-MOH-212379-NC-RFQ / R Availability of safe blood and Request for Quota Single Stage - One E Pending Impl epair of Generators at the Ke IDA / 65980 Post Limited 10,500.00 0.00 2021-01-24 2021-02-26 2021-05-27 blood products tions nvelope ementation nya National Blood Transfusi on Centres KE-MOH-215334-NC-DIR / Pr ovision of 24-Hour ten (No. 1 0) Standby Ambulance Servic Response, capacity building Under Imple IDA / 65980 Post Direct Selection Direct 570,000.00 0.00 2021-02-04 2021-03-18 2021-02-11 2021-03-28 2021-03-16 2021-06-14 e for 6 Months from M/S Eme and training mentation rgency Plus Medical Services of P.O Box 40712 – 00100 Na irobi KE-MOH-253414-NC-RFQ / Pr ocurement of printing service Gender Based Violence Resp Request for Quota Single Stage - One E Under Imple IDA / 65980 Post Limited 74,050.00 0.00 2021-10-31 2021-11-28 2021-12-31 s for the Gender Based Viole onse tions nvelope mentation nce (GBV) tools KE-MOH-275601-NC-RFQ / Pr ocurement of bulk Short Mes Availability of safe blood and Request for Quota Single Stage - One E Pending Impl sage Service (SMS) for Blood IDA / 65980 Post Limited 16,186.00 0.00 2022-02-12 2022-04-09 2022-10-06 blood products tions nvelope ementation Management Information Sys tems (BMIS) communication t o the blood donors KE-MOH-299841-NC-RFQ / Pr ocurement of service level a greements to undertake serv ice and maintenance of vario Availability of safe blood and Request for Quota Single Stage - One E us equipment used in the sto IDA / 65980 Post Limited 78,100.00 0.00 Signed 2022-07-03 2022-07-25 2022-08-28 2023-02-24 blood products tions nvelope rage, processing of blood an d blood products, air conditio ners, and at Kenya National Blood Transfusion and Organ Trans[plant Service (KNBTTS) KE-MOH-17-2022/2023-NC-R Availability of safe blood and Request for Quota Single Stage - One E Under Imple FQ / Procurement of Broadba IDA / 65980 Post Limited 36,000.00 0.00 2023-05-10 2023-07-05 2024-01-01 blood products tions nvelope mentation nd Internet for Six KTTA Regi ons KE-MOH-19-2022/2023-NC-R FQ / Provision of services to p Community discussion and i Request for Quota Single Stage - One E Pending Impl IDA / 65980 Post Limited 11,000.00 0.00 2023-05-17 2023-07-12 2024-01-08 artition 12No. agents booths nformation outreach tions nvelope ementation and fitting of drainage CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOH-224950-CS-CQS / Pr ocurement of Communicatio Community discussion and i Consultant Qualifi Under Implement n Consultancy Firm for the K IDA / 65980 Post Limited 750,000.00 0.00 2021-03-24 2021-03-24 2021-03-31 2022-05-20 2021-04-14 2021-05-12 2022-05-11 nformation outreach cation Selection ation enya Covid-19 Health Emerg ency Response Project KE-MOH-244763-CS-QCBS / The consultancy services for Medical supplies and equipm Consultant Qualifi Under Implement design and supervision of co IDA / 65980 Post Limited 750,000.00 0.00 2021-08-30 2021-10-26 2021-09-13 2021-10-13 2021-11-17 2022-05-16 ent cation Selection ation nstruction works and installat ion of equipment for the IDU at the KNH/Mbagathi Hospital . KE-MOH-249010-CS-QCBS / Community discussion and i Quality And Cost- Pending Impleme Consultancy services for com IDA / 65980 Prior Open - National 3,000,000.00 0.00 2021-09-20 2021-09-27 2021-10-25 2021-10-26 2021-10-28 2021-11-02 2021-12-18 2022-12-18 nformation outreach Based Selection ntation munication on COVID-19 vac cine Page 9 KE-MOH-254634-CS-CQS / pr ocurement of consultancy se Gender Based Violence Resp Consultant Qualifi Under Implement rvices of a firm to conduct as IDA / 65980 Post Limited 80,000.00 0.00 2021-10-29 2023-02-13 2021-11-06 2022-08-24 2021-11-13 2022-08-07 2021-12-02 2022-05-31 onse cation Selection ation sessment of Gender Based Vi olence (GBV) Quality Assuran ce in 10 targeted Counties KE-MOH-254972-CS-CQS / Pr ocurement of consultancy se Gender Based Violence Resp Consultant Qualifi rvices of a firm to undertake IDA / 65980 Post Limited 136,800.00 0.00 Signed 2021-10-29 2023-02-10 2021-11-12 2022-01-18 2021-12-12 2022-10-05 2022-01-16 2022-07-15 onse cation Selection support for front line health c are workers in Gender Based Violence (GBV) response. KE-MOH-254940-CS-CQS / Pr ocurement of a consultant to support the development of Gender Based Violence Resp Consultant Qualifi Under Implement Gender Based Violence (GBV IDA / 65980 Post Limited 32,000.00 0.00 2021-10-29 2023-02-13 2021-11-12 2021-11-19 2021-12-06 2022-06-04 onse cation Selection ation ) Information Education and Communication (IEC) and se nsitization materials for Com munity Own Resource Person (CORPS) KE-MOH-254642-CS-CQS / Pr ocurement of consultancy se rvices for a firm to support c Gender Based Violence Resp Consultant Qualifi IDA / 65980 Post Limited 332,000.00 0.00 Under Review 2021-10-29 2021-10-05 2021-11-06 2021-11-13 2021-11-30 2022-05-29 onsulting firm to support the onse cation Selection capacity building of service p roviders on GBV response thr ough virtual/online platform. KE-MOH-268646-CS-CQS / C onsultancy services to develo p a national demand plannin Availability of safe blood and Consultant Qualifi g, blood and blood products f IDA / 65980 Post Limited 270,000.00 0.00 Canceled 2021-12-21 2022-01-04 2022-02-03 2022-03-10 2022-09-06 blood products cation Selection orecasting, quantification an d stocking system for all tran sfusing facilities in the public sector KE-MOH-272316-CS-CQS / C onsultancy services to condu ct a nationwide survey to gui Community discussion and i Consultant Qualifi Pending Impleme IDA / 65980 Post Limited 100,000.00 0.00 2022-01-12 2022-01-26 2022-02-25 2022-04-01 2022-09-28 de community engagement a nformation outreach cation Selection ntation ctivities that will support com munity resilience and recove ry from COVID-19 in Kenya KE-MOH-292391-CS-CQS / Pr ocurement of consultancy se rvices to undertake recruitm Availability of safe blood and Consultant Qualifi Under Implement IDA / 65980 Post Limited 200,000.00 0.00 2022-05-09 2022-06-20 2022-05-23 2022-07-26 2022-06-22 2022-09-08 2022-07-27 2023-01-23 ent of 100,000 (No.) blood do blood products cation Selection ation nors for the Kenya National B lood Transfusion Services (K NBTTS) KE-MOH-306936-CS-CQS / R ecruitment of (2) Two Medica Response, capacity building Consultant Qualifi Under Implement l Laboratory Technologist Qu IDA / 65980 Post Open - National 25,380.00 0.00 2022-08-05 2022-08-08 2022-08-26 2023-04-10 2022-10-09 2022-11-08 2022-12-13 2023-06-11 and training cation Selection ation ality Management Systems f or KNBTTS for a period of 18 Months KE-MOH-318651-CS-CQS / Pr ocurement of an Integrated I ndependent Fiduciary Review Agency (IIFRA) services for a Project implementation and Consultant Qualifi Under Implement period of 12 Months to ensur IDA / 65980 Post Limited 320,000.00 0.00 2022-10-07 2022-10-17 2022-10-21 2022-11-20 2022-12-25 2023-06-23 monitoring cation Selection ation e that any systemic governa nce and accountability issues are noted as early as possibl e and on a regular basis for c orrective measures. KE-MOH-330741-CS-CQS / Hi re of a Consultancy Firm to d Availability of safe blood and Consultant Qualifi Under Implement IDA / 65980 Post Limited 100,000.00 0.00 2022-12-16 2022-12-30 2023-01-29 2023-03-05 2023-09-01 evelop and implement a com blood products cation Selection ation munication strategy for KTTA KE-MOH-07/1-2022/2023-CS- CQS / Consulting Services for Response, capacity building Consultant Qualifi Pending Impleme Environmental Impact Assess IDA / 65980 Post Limited 8,333.00 0.00 2023-06-09 2023-06-23 2023-07-07 2023-07-13 2023-09-11 and training cation Selection ntation ment for Mathare Teaching a nd Referral Hospital Telepsch iatry Center INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOH-173617-CS-INDV / H ire of 50 temporary staff for c Response, capacity building Individual Consult Under Implement all centre @ USD 1000 per p IDA / 65980 Post Limited 150,000.00 0.00 2020-05-29 2020-04-26 2020-06-03 2020-05-26 2020-06-24 2020-05-26 2020-07-29 2021-01-25 and training ant Selection ation erson per month for three m onths renewable monthly KE-MOH-173610-CS-INDV / C Community discussion and i Individual Consult Pending Impleme onsultancy for communicatio IDA / 65980 Post Limited 36,000.00 0.00 2020-06-01 2020-06-06 2020-06-27 2020-08-01 2021-01-28 nformation outreach ant Selection ntation n specialist KE-MOH-176220-CS-INDV / p rocurement of 55 Lab technol Response, capacity building Individual Consult Pending Impleme ogists to be deployed at 11 f IDA / 65980 Post Limited 123,750.00 0.00 2020-05-29 2020-06-03 2020-06-24 2020-07-29 2021-01-25 and training ant Selection ntation acilities for coordination of la b activities for three months KE-MOH-180881-CS-INDV / T emporary employment of Poi nt of EntryHealth workers as Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Limited 112,500.00 0.00 2020-06-23 2020-06-25 2020-06-29 2020-07-07 2021-01-03 follows; 15 Public Health offic and training ant Selection ntation ers, 4 Clinical officers and 6 Nurses on 6 month contract basis KE-MOH-181249-CS-INDV / E mployment of 55 Psychologis ts on a temporary basis on re Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Limited 131,250.00 0.00 2020-06-23 2020-06-28 2020-07-02 2020-07-17 2021-01-13 newable contract for 3 mont and training ant Selection ntation hs as follows: 45 assistants P sychologists and 10 senior ps ychologists Page 10 KE-MOH-178671-CS-CQS / Hi re a consultant to undertake Environmental Impact Assess Under Implement ment on sites for installation IDA / 65980 Medical waste disposal Post Direct Selection Direct 100,000.00 0.00 2020-06-23 2020-08-07 2020-06-29 2020-07-21 2021-01-17 ation of 16 incineratos for addition al tratment facilities in high p riority areas and sites forinci nerators for 6 specialised lab oratories KE-MOH-181245-CS-INDV / E mploy Consultant to extract and document the lessons le Project implementation and Individual Consult Pending Impleme IDA / 65980 Post Limited 10,000.00 0.00 2020-06-23 2020-06-24 2020-06-30 2020-08-04 2021-01-31 arned and best practices in K monitoring ant Selection ntation enya’s experience in the resp onse to the COVID-19 pande mic KE-MOH-181250-CS-INDV / E mploy a Consultant to do a r Response, capacity building Individual Consult Pending Impleme apid assessment on the statu IDA / 65980 Post Limited 14,000.00 0.00 2020-06-23 2020-06-24 2020-06-30 2020-07-15 2021-01-11 and training ant Selection ntation s of Counties to respond to th e COVID-19 pandemic KE-MOH-196780-CS-INDV / E mployment of twenty six (No. Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Limited 187,200.00 0.00 2020-10-05 2020-10-09 2020-10-16 2020-11-13 2020-12-14 26) doctors to be paid on a m and training ant Selection ntation onthly basis for a period of si x months KE-MOH-196794-CS-INDV / E mployment of Healthcare Wo Response, capacity building Individual Consult Pending Impleme rkers: Ten (No. 10) Nutritioni IDA / 65980 Post Limited 45,000.00 0.00 2020-11-15 2020-11-15 2020-11-22 2020-12-20 2021-01-19 and training ant Selection ntation sts to be paid on a monthly b asis for a period of six month s KE-MOH-196800-CS-INDV / E mployment of Healthcare Wo Response, capacity building Individual Consult Pending Impleme rkers: Ten (No. 10) psycholog IDA / 65980 Post Limited 45,000.00 0.00 2020-11-15 2020-11-20 2020-11-27 2020-12-25 2021-01-24 and training ant Selection ntation ists to be paid on a monthly basis for a period of six mont hs KE-MOH-196790-CS-INDV / E mployment of Healthcare Wo Response, capacity building Individual Consult Pending Impleme rkers: Ten (No. 10) physiothe IDA / 65980 Post Limited 45,000.00 0.00 2020-11-15 2020-11-18 2020-11-25 2020-12-23 2021-01-22 and training ant Selection ntation rapists to be paid on a month ly basis for a period of six mo nths KE-MOH-196770-CS-INDV / E mployment of Healthcare Wo Response, capacity building Individual Consult Pending Impleme rkers: laboratory liaison offic IDA / 65980 Post Limited 10,800.00 0.00 2020-11-15 2020-11-20 2020-11-27 2020-12-25 2021-01-24 and training ant Selection ntation ers to be paid on a monthly b asis for a period of six month s KE-MOH-196786-CS-INDV / E mployment of Healthcare Wo Response, capacity building Individual Consult Pending Impleme rkers: Seven (No.7) public he IDA / 65980 Post Limited 31,500.00 0.00 2020-11-15 2020-11-19 2020-11-26 2020-12-24 2021-01-24 and training ant Selection ntation alth technicians to be paid on a monthly basis for a period of six months KE-MOH-196783-CS-INDV / E mployment of Healthcare Wo Response, capacity building Individual Consult Pending Impleme rkers: One Hundred and Sixty IDA / 65980 Prior Limited 720,000.00 0.00 2020-11-15 2020-11-19 2020-11-26 2020-12-24 2021-01-24 and training ant Selection ntation (No. 160) Nurses to be paid o n a monthly basis for a perio d of six months KE-MOH-196776-CS-INDV / E mployment of Healthcare Wo Response, capacity building Individual Consult Pending Impleme rkers: Two (No. 2) logistics of IDA / 65980 Post Limited 18,000.00 0.00 2020-11-15 2020-11-18 2020-11-25 2020-12-23 2021-01-22 and training ant Selection ntation ficers for PHEOC to be paid o n a monthly basis for a perio d of six months KE-MOH-196756-CS-INDV / E mployment of Healthcare Wo rkers employed on a monthly Response, capacity building Individual Consult Pending Impleme basis for a period of six (6) m IDA / 65980 Prior Limited 531,000.00 0.00 2020-11-06 2020-11-09 2020-11-16 2020-12-14 2021-01-13 and training ant Selection ntation onths. Employment of One Hundred and Eighteen (No. 118) labor atory technicians. KE-MOH-196766-CS-INDV / E mployment of Health Care w orkers: Fifty Four (No. 54) La Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Limited 243,000.00 0.00 2020-11-15 2020-11-18 2020-11-25 2020-12-23 2021-01-22 b Information Management O and training ant Selection ntation fficers to be paid on a monthl y basis for a period of six mo nths KE-MOH-189062-CS-INDV / E mployment of One Hundred (No. 100) public health office Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Limited 450,000.00 0.00 2020-11-22 2020-11-27 2020-11-30 2020-12-28 2021-01-28 rs for monthly period of 6 mo and training ant Selection ntation nths. The contracts will be re newable after 3 months base d on performance and need. KE-MOH-196781-CS-INDV / E mployment of Healthcare Wo Response, capacity building Individual Consult Pending Impleme rkers: Thirty-two (No. 32) Clin IDA / 65980 Post Limited 144,000.00 0.00 2020-11-22 2020-11-26 2020-12-03 2020-12-24 2021-01-24 and training ant Selection ntation ical Officers to be paid on a monthly basis for a period of six months KE-MOH-203424-CS-INDV / E ngagement of a Consultant f Availability of safe blood and Individual Consult Pending Impleme or Development of a Five Yea IDA / 65980 Post Limited 25,000.00 0.00 2020-11-15 2020-11-20 2020-11-25 2020-12-16 2021-02-14 blood products ant Selection ntation r Strategic Plan for the Keny a National Blood Transfusion Services Division KE-MOH-226655-CS-INDV / H ire an individual consultant t Community discussion and i Individual Consult Pending Impleme o support implementation of IDA / 65980 Post Limited 10,500.00 0.00 2021-03-29 2021-04-03 2021-04-08 2021-04-22 2021-10-19 nformation outreach ant Selection ntation the 5th COVID-19 Knowledg e Attitude Practice (KAP) Sur vey. KE-MOH-254955-CS-INDV / P rocurement of consultancy s ervices of an individual consu Gender Based Violence Resp Individual Consult Under Implement ltant to design i.e. Conceptu IDA / 65980 Post Limited 32,000.00 0.00 2021-10-29 2023-02-13 2021-11-03 2022-01-25 2021-11-24 2022-06-08 2021-12-29 2022-06-27 onse ant Selection ation alize and produce graphic pr oducts of in Gender Based Vi olence response with copy ri ght to Ministry of Health . Page 11 MOH/CHERP/INDV/01/2021-2 022 / Procurement of consult Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open 89,250.00 0.00 2021-10-29 2021-11-11 2021-12-17 2022-01-07 2022-02-11 2022-08-10 ancy services for 20No. Psyc and training ant Selection ation hologists and 20No. Medical social workers KE-MOH-254947-CS-INDV / P rocurement of consultancy s ervices to support developm Gender Based Violence Resp Individual Consult IDA / 65980 Post Limited 15,000.00 0.00 Signed 2021-10-29 2023-02-13 2021-11-03 2022-01-18 2021-11-24 2022-10-03 2021-12-29 2022-06-27 ent of National guidelines on onse ant Selection psychosocial support for chil dren survivors of sexual viole nce KE-MOH-272984-CS-INDV / R ecruitment of four (4No.) Ana Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Open 28,800.00 0.00 2022-01-31 2022-03-21 2022-04-11 2022-05-16 2022-11-12 estheologists for the Nairobi and training ant Selection ntation Metropolitan Services (NMS) on temporary basis KE-MOH-272987-CS-INDV / R ecruitment of eight (8No.) co Response, capacity building Individual Consult Pending Impleme unselling psychologists for th IDA / 65980 Post Open 36,000.00 0.00 2022-01-31 2022-03-21 2022-04-11 2022-05-16 2022-11-12 and training ant Selection ntation e Nairobi Metropolitan Servic es (NMS) on temporary basis KE-MOH-272988-CS-INDV / R ecruitment of twenty (20No.) Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Open 90,000.00 0.00 2022-01-31 2022-03-21 2022-04-11 2022-05-16 2022-11-12 Psychologists for the Mental and training ant Selection ntation Health Services on temporar y basis KE-MOH-273003-CS-INDV / R ecruitment of twenty (20No.) Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Open 90,000.00 0.00 2022-01-31 2022-03-21 2022-04-11 2022-05-16 2022-11-12 Medical Social Workers for th and training ant Selection ntation e Mental Health Services on t emporary basis KE-MOH-273028-CS-INDV / R ecruitment of one (1No.) Acc Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Open 3,000.00 0.00 2022-01-31 2022-03-21 2022-04-11 2022-05-16 2022-11-12 ounts clerk for the Project Ma and training ant Selection ntation nagement Team (PMT) on te mporary basis KE-MOH-273030-CS-INDV / R ecruitment of one (1No.) Proc Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Open 3,000.00 0.00 2022-01-31 2022-03-21 2022-04-11 2022-05-16 2022-11-12 urement assistants for the Pr and training ant Selection ntation oject Management Team (PM T) on temporary basis KE-MOH-273031-CS-INDV / R ecruitment of assorted staff f Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Open 45,000.00 0.00 2022-01-31 2022-03-21 2022-04-11 2022-05-16 2022-11-12 or National Public Health Lab and training ant Selection ntation oratory Services (NPHLS) on t emporary basis KE-MOH-273033-CS-INDV / R ecruitment of eighty (80No.) Response, capacity building Individual Consult Pending Impleme IDA / 65980 Prior Open 360,000.00 0.00 2022-01-31 2022-03-21 2022-04-11 2022-05-16 2022-11-12 Public Health Officers (PHOs) and training ant Selection ntation for the Points of Entry (POEs) on temporary basis KE-MOH-273036-CS-INDV / R ecruitment of one (1No.) Hea Response, capacity building Individual Consult Pending Impleme lth products and technologist IDA / 65980 Post Open 66,000.00 0.00 2022-01-31 2022-03-21 2022-04-11 2022-05-16 2022-11-12 and training ant Selection ntation s technical assistant for the Health Products and Technol ogists on temporary basis KE-MOH-273037-CS-INDV / R ecruitment of one (1No.) Tele Response, capacity building Individual Consult Pending Impleme communication technical assi IDA / 65980 Post Open 21,000.00 0.00 2022-01-31 2022-03-21 2022-04-11 2022-05-16 2022-11-12 and training ant Selection ntation stant expert for the Mental H ealth Services on temporary basis KE-MOH-275565-CS-INDV / P rocurement of individual con Community discussion and i Individual Consult Pending Impleme sultancy services of a data a IDA / 65980 Post Limited 15,000.00 0.00 2022-01-31 2022-02-05 2022-02-26 2022-04-02 2022-09-29 nformation outreach ant Selection ntation nalyst to support the Covid-1 9 Knowledge, Attitude and Pr actice (KAP) Survey KE-MOH-272985-CS-INDV / R ecruitment of four (4No.) Me Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Open 28,800.00 0.00 2022-02-07 2022-03-28 2022-04-18 2022-05-23 2022-11-19 dical officers for the Nairobi and training ant Selection ntation Metropolitan Services (NMS) on temporary basis KE-MOH-272979-CS-INDV / R ecruitment of thirteen (13No. Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Open 58,500.00 0.00 2022-02-07 2022-03-28 2022-04-18 2022-05-23 2022-11-19 ) Clinical officers for the Nair and training ant Selection ntation obi Metropolitan Services (N MS) KE-MOH-273006-CS-INDV / R ecruitment of Twenty (20No.) Nutritionists (to high risk Cou Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Open 112,500.00 0.00 2022-02-07 2022-03-21 2022-04-11 2022-05-16 2022-11-12 nties and National Hospitals) and training ant Selection ntation and Five (5No.) Nutritionists f or Nairobi Metropolitan Servi ces (NMS) on temporary basi s KE-MOH-269224-CS-INDV / R Response, capacity building Individual Consult Pending Impleme ecruitment of 60No. nurses f IDA / 65980 Prior Open 270,000.00 0.00 2022-02-07 2022-03-28 2022-04-18 2022-05-23 2022-11-19 and training ant Selection ntation or Nairobi Metropolitan Servi ces KE-MOH-273026-CS-INDV / R ecruitment of two (2No.) GR Response, capacity building Individual Consult Pending Impleme M assistant officers- ESS for t IDA / 65980 Post Open 6,000.00 0.00 2022-03-14 2022-05-02 2022-05-23 2022-06-27 2022-12-24 and training ant Selection ntation he Project Management Tea m (PMT) on temporary basis KE-MOH-272999-CS-INDV / R ecruitment of seven (7No.) P Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Open 31,500.00 0.00 2022-03-11 2022-04-29 2022-05-20 2022-06-24 2022-12-21 hysiotherapists for the Menta and training ant Selection ntation l Health Services on tempora ry basis KE-MOH-272983-CS-INDV / R ecruitment of fifteen (15No.) Response, capacity building Individual Consult Pending Impleme IDA / 65980 Post Open 67,500.00 0.00 2022-03-11 2022-04-29 2022-05-20 2022-06-24 2022-12-21 Radiographers for the Nairobi and training ant Selection ntation Metropolitan Services (NMS) KE-MOH-306734-CS-INDV / R ecruitment of Two(2No.) Acc Response, capacity building Individual Consult Under Implement ounts assistants to assist in t IDA / 65980 Post Open - National 27,000.00 0.00 2022-08-01 2022-08-08 2022-09-05 2022-09-26 2022-10-31 2023-04-29 and training ant Selection ation he Project Implementation in Nairobi for a period of 18Mon ths Page 12 KE-MOH-306735-CS-INDV / R ecruitment of Two(2No) Proc Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 18,000.00 0.00 2022-08-01 2022-08-08 2022-09-19 2022-10-10 2022-11-14 2023-05-13 urement Assistant to assist in and training ant Selection ation Project implementation for 1 8 Months KE-MOH-306934-CS-INDV / R ecruitment of One(1No) MEDI Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 27,000.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 CAL OFFICER – (HEMOVIGILA and training ant Selection ation NCE SERVICES) for KNBTTS f or a period of 18Months KE-MOH-306937-CS-INDV / R ecruitment of One(1No) Medi Response, capacity building Individual Consult Under Implement cal Laboratory Technologist- IDA / 65980 Post Open - National 21,816.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 and training ant Selection ation Testing Services for KNBTTS f or a period of 18Months KE-MOH-306938-CS-INDV / R ecruitment of (10) Ten Regis Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 99,900.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 tered Nursing Officers for KN and training ant Selection ation BTTS for a period of 18 Mont hs KE-MOH-306939-CS-INDV / R ecruitment of One(1No) Regi Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 12,690.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 stered Nursing Officer for KN and training ant Selection ation BTTS for a period 18 Month KE-MOH-306940-CS-INDV / R ecruitment of One(1No) Regi Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 32,670.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 onal Coordination and Partne and training ant Selection ation rships Officer for KNBTTS for a period of 18Months KE-MOH-306941-CS-INDV / R ecruitment of One(1No) Strat Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 32,670.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 egic Information Specialist fo and training ant Selection ation r KNBTTS for a period of 18 M onths KE-MOH-306942-CS-INDV / R ecruitment of One (1No) Sen Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 21,816.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 ior Accountant for KNBTTS fo and training ant Selection ation r a period of 18 Months KE-MOH-306943-CS-INDV / R ecruitment of One Communic Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 32,670.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 ation Specialist for KNBTTS f and training ant Selection ation or a period of 18Months KE-MOH-306945-CS-INDV / R ecruitment of One Communic Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 12,690.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 ation Officer for KNBTTS for a and training ant Selection ation period of 18Months KE-MOH-306946-CS-INDV / R Response, capacity building Individual Consult Under Implement ecruitment of One Administra IDA / 65980 Post Open - National 32,670.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 and training ant Selection ation tor for KNBTTS for a period of 18Months KE-MOH-306976-CS-INDV / R ecruitment of One Administra Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 19,800.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 tive Officer for KNBTTS for a and training ant Selection ation period of 18 Months KE-MOH-306977-CS-INDV / R Response, capacity building Individual Consult Under Implement ecruitment of One ICT Specia IDA / 65980 Post Open - National 32,670.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 and training ant Selection ation list for KNBTTS for a period of 18Months KE-MOH-306979-CS-INDV / R ecruitment of One Communic Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 12,690.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 ation Officer for KNBTTS for a and training ant Selection ation period of 18 Months KE-MOH-306982-CS-INDV / R ecruitment of One Monitoring Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 19,980.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 and Evaluation Specialist for and training ant Selection ation KNBTTS for a period of 18Mo nths KE-MOH-306983-CS-INDV / R ecruitment of Two Monitoring Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 19,980.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 and Evaluation Officers for K and training ant Selection ation NBTTS for a period of 18 Mon ths KE-MOH-306985-CS-INDV / R ecruitment of One Supply Ch Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 9,990.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 ain Management Assistant fo and training ant Selection ation r KNBTTS for a period of 18M onths KE-MOH-306986-CS-INDV / R ecruitment of Office Administ Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 7,272.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 rative Assistant for KNBTTS f and training ant Selection ation or a period of 18months KE-MOH-306987-CS-INDV / R Response, capacity building Individual Consult Under Implement ecruitment of Six Drivers for IDA / 65980 Post Open - National 43,632.00 0.00 2022-08-05 2022-08-08 2022-09-23 2022-10-14 2022-11-18 2023-05-17 and training ant Selection ation KNBTTS for a period of 18Mo nths KE-MOH-306933-CS-INDV / R Response, capacity building Individual Consult Under Implement ecruitment of One (1No.) Pha IDA / 65980 Post Open - National 27,000.00 0.00 2022-08-07 2022-08-08 2022-09-25 2022-10-16 2022-11-20 2023-05-19 and training ant Selection ation rmacist for KNBTTS for a peri od of 18 Months KE-MOH-306981-CS-INDV / R ecruitment of One Biomedica Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 19,800.00 0.00 2022-08-08 2022-08-08 2022-09-26 2022-10-17 2022-11-21 2023-05-20 l Engineers for KNBTTS for a and training ant Selection ation period of 18Months KE-MOH-306978-CS-INDV / R Response, capacity building Individual Consult Under Implement ecruitment of Three ICT Offic IDA / 65980 Post Open - National 38,070.00 0.00 2022-08-07 2022-08-08 2022-09-25 2022-10-16 2022-11-20 2023-05-19 and training ant Selection ation ers for KNBTTS for a period o f 18 Months KE-MOH-306980-CS-INDV / R ecruitment of One Human Re Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 12,690.00 0.00 2022-08-07 2022-08-08 2022-09-25 2022-10-16 2022-11-20 2023-05-19 source Officer for KNBTTS for and training ant Selection ation a period of 18 Months Page 13 KE-MOH-306935-CS-INDV / R ecruitment of (15) Fifteen M Response, capacity building Individual Consult Under Implement IDA / 65980 Post Open - National 149,850.00 0.00 2022-08-07 2022-08-08 2022-09-25 2022-10-16 2022-11-20 2023-05-19 edical Laboratory Technologi and training ant Selection ation st for KNBTTS for a period of 18Months KE-MOH-307679-CS-INDV / R ecruitment of One Medical La Medical supplies and equipm Individual Consult Under Implement IDA / 65980 Post Open - National 96,000.00 0.00 2022-08-12 2022-08-08 2022-09-30 2022-10-21 2022-11-25 2023-05-24 boratory Consultant for the C ent ant Selection ation -HERP Project for a period of one year renewable KE-MOH-241051-CS-CQS / P ROCUREMENT OF TECHNICA Project implementation and Individual Consult IDA / 65980 Post Open 120,000.00 0.00 Canceled 2021-08-10 2021-09-28 2021-10-19 2021-11-23 2022-05-22 L ASSISTANT TO CO-ORDINA monitoring ant Selection TE AND SUPPORT KEMSA RE FORMS FOR ONE YEAR KE-MOH-329067-CS-INDV / H ire of an Individual Consultan Community discussion and i Individual Consult Under Implement t to support the Project to d IDA / 65980 Post Limited 12,500.00 0.00 2022-12-09 2022-12-02 2022-12-14 2022-12-08 2023-01-04 2023-02-08 2023-08-07 nformation outreach ant Selection ation o the 7th Knowledge, Attitud e and Practice (KAP) Survey. KE-MOH-330340-CS-CDS / St ep Wise Accreditation of Regi Availability of safe blood and Direct - Internation onal Blood Transfusion Cente IDA / 65980 Post Direct Selection 52,000.00 0.00 Under Review 2022-12-16 2023-02-02 2022-12-26 2023-03-01 2023-08-28 blood products al rs by African Society for Bloo d Transfusion Standards KE-MOH-07-2022/2023-CS-I NDV / Procurement of a Cons ultant to undertake Environm Response, capacity building Individual Consult Under Implement IDA / 68230 Post Limited 10,000.00 0.00 2023-05-14 2023-05-19 2023-06-09 2023-07-14 2024-01-10 ental Impact Assessment (EI and training ant Selection ation A) for the proposed Renovati on Works at Mathare Nation al Teaching and Referral Hos pital Page 14 PROCUREMENT PLAN (Textual Part) Project information: ARAB REPUBLIC OF EGYPT, EGYPT: GREATER CAIRO AIR POLLUTION MANAGEMENT AND CLIMATE CHANGE PROJECT Project Implementation agency: Ministry of Environment Date of the Procurement Plan: 25 August 2020 Period covered by this Procurement Plan: First 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. Completio Expecte Contract Contract Estimat Bank Selectio award d # Contract Description ed Cost Oversig Market Approach n Type n Launch $ ht Method Date Component 1: Enhancing the Air Quality Management (AQM) & Response System USD 4.53 M 1 Integrated Climate and Air Open/ RFP Jun 21 Dec Consulting Quality Management “Action” 0.43 M Post International 21 Services Plan 2 Establishing an Open/ RFP Sep 20 Jan Consulting integrated emission International 21 Services inventory database for Greater pollution emission inventory, and its integration with SLCP and 0.5 M Post GHG emissions inventory Cairo and Egypt: Technical Support Contract for EEAA to support the refinement of existing air 3 Establishing an Open/ RFB Sep 20 Jan Consulting SLCP/GHG monitoring International 21 Services network for Greater Cairo: Technical support contract for EEAA to provide 1.5 M Post recommendations on the deployment, operation and maintenance of proposed network. 4 AQ Skills Training and U. Open/ RFP Jun 21 Dec Consulting 0.7 M Post Curriculum Development International 21 Services 5 Economic/BCA Analysis Open/ RFP Jun 21 Dec Consulting 0.6 M Post International 21 Services 6 Equipment for Improving Air Open/ RFB Jan 21 Jul Goods 0.4 M Post Quality Forecasting International 21 7 Integrating and analyzing the Open/ RFP Aug 21 Feb Consulting 0.1 M Post air quality forecasting data International 22 Services Completio Expecte Contract Contract Estimat Bank Selectio award d # Contract Description ed Cost Oversig Market Approach n Type n Launch $ ht Method Date 8 Establishing institutional Open/ RFP Dec 21 Jun Consulting response mechanisms to high 0.3 M Post International 22 Services pollution days Component 2: Support the operationalization of SWM Master Plans in Greater Cairo USD 96 M 9 Preparation of detailed Open/ National RFP Sep 20 Oct Consulting engineering design & bidding 20 Services documents for 10th of Ramadan 0.35 M Post infrastructure and MSW landfill (including supervision) 10 Infrastructure construction Open/ RFB Dec 20 Apr Works 15.5 M Prior works for 10th of Ramadan International 21 11 MSW landfill construction works Open/ RFB Jan 21 Jun Design, build 20.5 M Prior for 10th of Ramadan International 21 and operate 12 Project management and Open/ RFP Oct 20 Mar Consulting supervision consultant for the International 21 Services 10th of Ramadan planning, 1.7 M Post management and monitoring of works and major technical assistance 13 10th of Ramadan- Open/National RFP Oct 20 April Consulting Construction and 21 Services demolition waste facility: Preparation of a bidding document, 1.5 M Post following a Design, Build and Operate modality, on the basis of analysis and studies prepared by MoE. 14 Consulting service to prepare, Open/ RFP Dec 20 Jun Consulting the detailed engineering study, International 21 Services bidding documents and to 1.2 M Post supervise closing and rehabilitation of Abou Zaabal 15 Consulting service to prepare, Open/ RFP Sep 20 Feb Consulting 1.8 M Post detailed feasibility study, International 21 Services Completio Expecte Contract Contract Estimat Bank Selectio award d # Contract Description ed Cost Oversig Market Approach n Type n Launch $ ht Method Date bidding documents, contracts, safeguard documents and to supervise the hazardous waste treatment and final disposal facility 16 Infrastructure construction wor RFP Nov 21 Jun Design, Build ks for final disposal facility 19 M Prior Open/ 22 and Operate International 17 Consulting service to prepare, RFP Nov 20 May Consulting the detailed engineering study, Open/ 21 Services bidding documents, safeguard 0.3 M Post International documents and to supervise to construct the transfer stations. 18 Infrastructure construction Open/ RFP Nov 21 Apr 5M Prior work for transfer stations. International 22 Works 19 Feasibility study for the Open/ RFP May 21 Aug Consulting environmental upgrade of El- 2M Post International 21 Services Akrasha Area, Qalyubia. 20 Technical assistance for Open/ RFP May 21 Aug Consulting establishing and/or improving 4M Post International 21 Services waste management systems 21 Provision of steam sterilization Open/ RFB Jun 21 Dec Goods equipment (autoclaves) COVID- 7.5 M Prior International 21 19 23 Provision of personal protective Open/ Local RFP Consulting equipment for enhanced safety Dec 20 Apr Services and security in solid waste 21 0.3 M Post collection – including identification of target groups and needs assessment 25 System development and Open/ RFP Consulting training for healthcare staff on International Services 2.2 M Post safe handling, transport, and April Sep disposal of healthcare waste 21 21 24 Institutional support to solid Open/ RFB Goods waste management agencies International Dec 20 Apr Prior (MoE, MoLD and SW Unit in 4M 21 Qalyubia Governorate) Completio Expecte Contract Contract Estimat Bank Selectio award d # Contract Description ed Cost Oversig Market Approach n Type n Launch $ ht Method Date Component 3: Vehicle Emission Reduction USD 4 M 26 Study for electric bus routes Open/ RFP Sep 20 Nov Consulting 0.5 M Prior (detailed Designs) International 20 Services 27 Retrofitting of existing bus Open/ RFP Apr 21 Jul Works 3.5 M Prior depot International 21 28 Procurement of e-buses Open/ RFB May 21 Sep Goods 30 M Prior International 21 Component 4: Stakeholders engagement, awareness raising and communication USD 1.91 M 29 Political economy analysis, Open/ RFP Nov 20 Feb Consulting stakeholder mapping and 0.2 M Post International 21 Services consultation 30 Implementation of SEP Open/ RFP Feb 21 May Consulting 0.45 M Post activities International 21 Services 31 Development and Open/ RFP Feb 21 May Consulting implementation of 0.22 M Post International 21 Services communication plans 32 Behavior change - community Open/ RFP Mar 21 Jun Consulting based social marketing 0.28M Post International 21 Services interventions (CBSM) 33 Implementation of priority AQM Open/ RFP Mar 21 Jun Consulting 0.22 M Post awareness campaigns International 21 Services 34 Pilot activities with NGOs, CSOs Open/ national RFP May 21 Aug Consulting 0.32 M Post 21 Services 35 Communication material, Open/Internatio RFP May 21 Aug Consulting 0.22M Post knowledge products nal 21 Services Component 5: Project Management and Monitoring & Evaluation USD 1.9 M 36 Individual consultants to Open/ RFP Sep 20 Oct Consulting 0.2 M Post support the PCU International 20 Services 37 Procurement of office furniture Open/ RFQ Sep 20 Sep Goods 0.2 M Post and IT equipment for PCU National 20 PROCUREMENT Egypt, Arab Republic of : Greater Cairo Air Pollution Management and Climate Change Project PLAN General Information Country: Egypt, Arab Republic of 2021-04-29 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172548 GPN Date: Project Name: Greater Cairo Air Pollution Management and Climate Change Project Loan / Credit No: IBRD / 91660 Egyptian Environmental Affairs Agency Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Request for B EG-EEAA-326981-CW-RFB / Support the Operationalizati ids - Works ( Works of the Primary Infrastr Open - Internationa Single Stage - One E Under Imple 2024-11-0 IBRD / 91660 on of SWM Master Plans in G Prior Request for Bids without preq 0.00 2022-11-30 2023-03-26 2022-12-05 2023-04-02 2023-01-16 2023-05-31 2023-05-16 2023-06-20 ucture of the 10th of Ramada l nvelope mentation 1 reater Cairo ualification) n Integrated Solid Waste Man SPD agement Facility GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-EEAA-273227-GO-RFQ / I Project Management and Mo Request for Quota Single Stage - One E IBRD / 91660 Post Limited 31,552.04 Signed 2022-02-01 2022-01-23 2022-03-29 2022-02-16 2022-09-25 T - Equipment nitoring & Evaluation tions nvelope EG-EEAA-298113-GO-RFQ / P Project Management and Mo Request for Quota Single Stage - One E Under Imple IBRD / 91660 Post Open - National 0.00 2022-07-13 2022-08-10 2022-09-09 roject Vehicle nitoring & Evaluation tions nvelope mentation EG-EEAA-302306-GO-RFQ / P Support the Operationalizati Request for Quota Single Stage - One E Under Imple IBRD / 91660 Post Limited 0.00 2022-07-07 2022-07-31 2022-07-31 2022-08-31 roject Office Furniture on of SWM Master Plans in G tions nvelope mentation reater Cairo EG-EEAA-302310-GO-RFQ / P Project Management and Mo Request for Quota Single Stage - One E Under Imple IBRD / 91660 Post Limited 0.00 2022-07-07 2022-08-22 2022-08-07 2022-09-06 roject Office Air Condition nitoring & Evaluation tions nvelope mentation EG-EEAA-302313-GO-RFQ / I Support the Operationalizati Request for Quota Single Stage - One E Pending Impl T Equipment for MOLD, Cairo IBRD / 91660 on of SWM Master Plans in G Post Limited 0.00 2022-07-12 2022-08-15 2022-09-14 tions nvelope ementation and Qualubeya Governorates reater Cairo EG-EEAA-333933-GO-RFQ / Project Management and Mo Request for Quota Single Stage - One E Pending Impl White Goods and Kitchen tool IBRD / 91660 Post Limited 0.00 2023-03-10 2023-05-05 2023-11-01 nitoring & Evaluation tions nvelope ementation s for Project HQ EG-EEAA-360720-GO-RFB / E Enhancing the Air Quality M Open - Internationa Single Stage - One E Pending Impl quipment for SLCP/GHG moni IBRD / 91660 anagement & Response Syst Prior Request for Bids 0.00 2023-11-15 2023-11-20 2024-01-01 2024-01-31 2024-03-06 2024-12-15 l nvelope ementation toring network & network re- em alignment EG-EEAA-360729-GO-RFB / E Enhancing the Air Quality M Open - Internationa Single Stage - One E Pending Impl quipment for Improving Air Q IBRD / 91660 anagement & Response Syst Post Request for Bids 0.00 2024-01-02 2024-01-07 2024-02-18 2024-03-19 2024-04-23 2024-07-23 l nvelope ementation uality Forecasting em NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-EEAA-355105-NC-DIR / O Enhancing the Air Quality M Under Imple IBRD / 91660 Post Direct Selection Direct - National 0.00 2022-11-15 2022-11-21 2022-11-20 2022-11-23 2022-12-25 2023-06-23 UDA Payment Services anagement & Response Syst mentation em CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-EEAA-170002- CS-QCBS / Maximize the newly establish Support the Operationalizati Quality And Cost- Open - Internationa ed WMRA financial resources IBRD / 91660 on of SWM Master Plans in G Post 73,455.52 Signed 2021-04-21 2021-04-20 2021-04-21 2021-05-04 2021-05-04 2021-06-10 2021-05-18 2021-07-07 2021-05-19 2021-07-07 2021-05-20 2021-07-11 2021-05-24 2021-08-13 2021-11-17 Based Selection l in line with the most recent reater Cairo Waste Management Regulati on Law No. 202 of 2020 EG-EEAA-170001- CS-QCBS / Project Management and Mo Quality And Cost- IBRD / 91660 Post Open - National 0.00 Canceled 2021-04-21 2021-04-30 2021-04-25 2021-05-04 2021-05-10 2021-05-30 2021-05-30 2021-06-03 2021-07-01 2022-07-01 Project Coordinator nitoring & Evaluation Based Selection EG-EEAA-239496-CS-QCBS / Consultancy for 10th of Ram adan for the Integrated Wast Support the Operationalizati e Management Facility Quality And Cost- IBRD / 91660 on of SWM Master Plans in G Post Open - National 115,849.41 Signed 2021-06-16 2021-06-30 2021-06-17 2021-06-30 2021-07-08 2021-09-21 2021-08-29 2021-11-07 2021-08-29 2021-11-30 2021-09-09 2022-01-02 2021-10-10 2022-02-08 2022-01-10 Preparation of Detailed Engin Based Selection reater Cairo eering Design and Tender Do cuments for Basic Infrastructure & Site Supervision of Construction Works EG-EEAA-252242-CS-QCBS / Electric Bus (e-bus) Demonst Quality And Cost- Open - Internationa Under Implement ration Project Detailed Planni IBRD / 91660 Vehicle Emissions Reduction Prior 0.00 2021-09-16 2021-10-20 2021-10-07 2021-11-17 2021-11-20 2022-02-08 2022-01-04 2022-03-27 2022-01-04 2022-06-26 2022-02-08 2022-11-17 2022-02-27 2023-05-30 Based Selection l ation ng and Design Study for Cair o Transport Authority (CTA) EG-EEAA-273225-CS-QCBS / Project Structuring and Trans Support the Operationalizati action Advisory Services for t Quality And Cost- Open - Internationa Under Implement IBRD / 91660 on of SWM Master Plans in G Post 0.00 2022-01-20 2022-01-18 2022-02-10 2022-03-31 2022-03-26 2022-07-08 2022-04-23 2022-08-18 2022-05-23 2022-10-05 2022-06-27 2022-09-29 2022-08-01 2023-08-01 he establishment of an Integr Based Selection l ation reater Cairo ated Solid Waste Manageme nt Facility for Qalyubia Gover norate EG-EEAA-273226-CS-QCBS / Support the Operationalizati Management and Technical S Quality And Cost- Open - Internationa IBRD / 91660 on of SWM Master Plans in G Prior 0.00 Signed 2022-01-20 2022-03-21 2022-02-10 2022-03-31 2022-03-26 2022-07-26 2022-04-23 2022-09-08 2022-05-23 2022-10-17 2022-06-27 2023-01-15 2022-08-01 2023-05-02 2025-08-01 upport for Solid Waste Mana Based Selection l reater Cairo gement Component Page 1 EG-EEAA-273277-CS-FBS / M Enhanced Capacity, Behavio Quality And Cost- IBRD / 91660 Post Open - National 0.00 Canceled 2022-02-06 2022-02-27 2022-04-12 2022-05-10 2022-06-09 2022-07-14 2022-08-18 2025-08-18 edia and Branding ral Change and Communicat Based Selection ion EG-EEAA-289919-CS-CQS / T Project Management and Mo Consultant Qualifi Under Implement IBRD / 91660 Post Limited 0.00 2022-04-14 2022-06-02 2022-04-21 2022-10-10 2022-04-28 2022-12-15 2022-05-15 2023-05-15 ranslation Service nitoring & Evaluation cation Selection ation EG-EEAA-289928-CS-CQS / E Enhancing the Air Quality M Consultant Qualifi Pending Impleme IBRD / 91660 Post Limited 0.00 2022-04-24 2022-05-08 2022-06-07 2022-07-12 2023-07-12 SIA Advisory Services anagement & Response Syst cation Selection ntation em EG-EEAA-292985-CS-CQS / Enhanced Capacity, Behavio Consultant Qualifi Under Implement IBRD / 91660 Post Limited 0.00 2022-05-01 2022-05-16 2022-05-15 2022-07-06 2022-06-14 2022-12-19 2022-07-19 2023-07-19 Media and Branding (1) ral Change and Communicat cation Selection ation ion EG-EEAA-308070-CS-LCS / E Project Management and Mo Least Cost Selecti IBRD / 91660 Post Open - National 0.00 Signed 2022-08-14 2022-08-15 2022-09-04 2022-09-25 2022-10-18 2022-12-25 2022-11-15 2023-02-05 2022-12-15 2023-02-12 2023-01-19 2023-02-19 2023-02-23 2025-03-02 xternal Financial Audit nitoring & Evaluation on EG-EEAA-247116-CS-QCBS / Management and Technical S upport Consultant for AQM - advisory services and technic Enhancing the Air Quality M Quality And Cost- Open - Internationa al assistance in managing an IBRD / 91660 anagement & Response Syst Prior 0.00 Canceled 2021-09-16 2021-10-13 2021-09-22 2021-11-11 2021-10-27 2022-01-17 2021-12-11 2022-03-10 2021-12-11 2022-04-21 2021-12-22 2023-01-04 2022-01-26 2026-07-11 Based Selection l d implementing the project a em cross a range of topics relate d to AQM planning to address air pollution and climate miti gation in Greater Cairo. EG-EEAA-346347-CS-QCBS / Technical Support for providi Enhancing the Air Quality M Quality And Cost- Open - Internationa Under Implement ng recommendations for the IBRD / 91660 anagement & Response Syst Post 0.00 2023-03-06 2023-03-11 2023-03-14 2023-03-20 2023-04-27 2023-05-03 2023-05-25 2023-06-14 2023-06-24 2023-07-29 2023-09-02 2024-10-26 Based Selection l ation deployment, operation and em maintenance of an SLCP/ GH G monitoring network EG-EEAA-346356-CS-QCBS / Enhancing the Air Quality M Developing Mobile Source E Quality And Cost- Open - Internationa Under Implement IBRD / 91660 anagement & Response Syst Post 0.00 2023-03-12 2023-03-12 2023-04-02 2023-03-20 2023-05-16 2023-06-11 2023-06-13 2023-07-13 2023-08-17 2023-09-07 2024-12-31 missions Inventory and Emis Based Selection l ation em sions Inventory Integration EG-EEAA-346366-CS-CQS / T echnical Support for Source Enhancing the Air Quality M Consultant Qualifi Open - Internationa Under Implement Apportionment Analysis - sa IBRD / 91660 anagement & Response Syst Post 0.00 2023-06-15 2023-03-30 2023-07-06 2023-04-11 2023-08-19 2023-06-11 2023-09-18 2023-10-02 2025-03-25 cation Selection l ation mpling, laboratory analysis, a em nd statistical analysis EG-EEAA-360722-CS-QCBS / Enhancing the Air Quality M Developing an Integrated Cli Quality And Cost- Open - Internationa Under Implement IBRD / 91660 anagement & Response Syst Prior 0.00 2023-05-15 2023-06-05 2023-06-01 2023-06-10 2023-07-02 2023-07-30 2023-08-17 2023-09-04 2023-09-28 2024-12-26 mate and Air Quality Manage Based Selection l ation em ment (IC-AQMP) “Action” Pla n EG-EEAA-360728-CS-QCBS / Enhancing the Air Quality M Develop advanced AQ Foreca Quality And Cost- Open - Internationa Pending Impleme IBRD / 91660 anagement & Response Syst Prior 0.00 2023-06-01 2023-06-22 2023-07-20 2023-08-17 2023-09-01 2023-10-06 2023-10-30 2025-06-30 sting system - integrating an Based Selection l ntation em d analyzing the air quality for ecasting data EG-EEAA-362805-CS-CQS / H Support the Operationalizati Consultant Qualifi Pending Impleme ealthcare Waste Managemen IBRD / 91660 on of SWM Master Plans in G Post Limited 0.00 2023-06-15 2023-06-29 2023-07-29 2023-09-02 2024-02-29 cation Selection ntation t consultant for Hospital asse reater Cairo ssment EG-EEAA-360587-CS-CQS / E Support the Operationalizati Consultant Qualifi nvironmental and Social impl IBRD / 91660 on of SWM Master Plans in G Post Open - National 0.00 Under Review 2023-05-10 2023-06-04 2023-05-31 2023-07-04 2023-07-24 2023-08-28 2024-02-24 cation Selection ementation support reater Cairo INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EG-EEAA-233536-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Open 53,554.35 Signed 2021-05-10 2021-04-30 2021-06-14 2021-07-07 2021-06-16 2021-07-28 2021-07-01 2021-08-20 2022-07-31 Project Coordinator nitoring & Evaluation ant Selection EG-EEAA-244229-CS-CDS / S Project Management and Mo IBRD / 91660 Post Direct Selection Direct 35,143.95 Signed 2021-07-16 2021-07-27 2021-07-26 2021-08-16 2021-08-01 2021-08-20 2022-08-01 enior Procurement Specialist nitoring & Evaluation EG-EEAA-244233-CS-CDS / S Project Management and Mo enior Legal and Governance IBRD / 91660 Post Direct Selection Direct 40,303.53 Signed 2021-07-18 2021-07-27 2021-07-28 2021-08-16 2021-08-01 2021-08-20 2022-08-01 nitoring & Evaluation Professional EG-EEAA-244235-CS-CDS / S Support the Operationalizati IBRD / 91660 Post Direct Selection Direct 40,303.53 Signed 2021-07-18 2021-07-27 2021-07-28 2021-08-16 2021-08-01 2021-08-20 2022-08-01 enior Waste Management Pro on of SWM Master Plans in G fessional reater Cairo EG-EEAA-250539-CS-INDV / Enhancing the Air Quality M Individual Consult IBRD / 91660 Post Limited 18,479.21 Signed 2021-08-30 2021-08-31 2021-09-06 2021-08-15 2021-09-12 2021-08-20 2021-09-17 2021-09-11 2022-09-17 Environmental Specialist anagement & Response Syst ant Selection em EG-EEAA-253220-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Limited 37,211.67 Signed 2021-09-21 2021-10-01 2021-09-26 2021-09-01 2021-09-29 2021-09-15 2021-10-04 2021-10-24 2022-09-29 Senior Financial Specialist nitoring & Evaluation ant Selection EG-EEAA-253223-CS-INDV / Project Management and Mo Individual Consult Pending Impleme IBRD / 91660 Post Limited 0.00 2021-09-21 2021-09-23 2021-09-26 2021-10-01 2022-09-29 Secretary nitoring & Evaluation ant Selection ntation EG-EEAA-253225-CS-INDV / Project Management and Mo Individual Consult Pending Impleme IBRD / 91660 Post Limited 0.00 2021-09-21 2021-09-26 2021-09-28 2021-10-04 2022-09-29 Project Assistant nitoring & Evaluation ant Selection ntation EG-EEAA-253333-CS-CDS / P reparation of Environmental Support the Operationalizati and social instrument for the IBRD / 91660 on of SWM Master Plans in G Post Direct Selection Direct 24,626.86 Signed 2021-09-26 2022-03-14 2021-10-06 2022-05-08 2021-10-31 2022-06-05 2022-04-29 10th of Ramadan Basic Infras reater Cairo tructure of the Integrated Wa ste Management Facility pac kage EG-EEAA-253222-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Limited 0.00 Canceled 2022-01-15 2022-01-25 2022-01-20 2022-02-10 2022-01-24 2022-02-15 2022-02-01 2023-01-31 Senior Procurement Specialis nitoring & Evaluation ant Selection t (2) EG-EEAA-250536-CS-INDV / Enhancing the Air Quality M Individual Consult Social Development and Gen IBRD / 91660 anagement & Response Syst Post Open 14,362.93 Signed 2022-01-05 2021-10-07 2022-02-23 2021-11-21 2022-02-25 2022-02-26 2022-03-12 2022-05-27 2023-03-11 ant Selection der Specialist em EG-EEAA-271141-CS-INDV / Enhanced Capacity, Behavio Individual Consult IBRD / 91660 Post Open 0.00 Canceled 2021-12-30 2022-01-18 2022-02-17 2022-03-10 2022-04-01 2023-03-30 Communication Senior Advis ral Change and Communicat ant Selection or ion Page 2 EG-EEAA-253428-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Limited 8,533.92 Signed 2021-12-30 2022-01-18 2022-01-04 2022-01-27 2022-01-09 2022-01-27 2022-01-16 2022-04-19 2023-01-15 Operational Manual Preparati nitoring & Evaluation ant Selection on EG-EEAA-286893-CS-INDV / Technical Evaluation Consult ant - Electric Bus (e-bus) De Individual Consult IBRD / 91660 Vehicle Emissions Reduction Post Limited 2,056.39 Signed 2022-03-26 2022-04-05 2022-03-27 2022-04-08 2022-03-29 2022-04-08 2022-03-30 2022-04-20 2022-04-30 monstration Project Detailed ant Selection Planning and Design Study fo r Cairo Transport Authority (C TA) EG-EEAA-288479-CS-INDV / Technical Evaluation Consult ant (2) - Electric Bus (e-bus) Individual Consult IBRD / 91660 Vehicle Emissions Reduction Post Limited 1,503.92 Signed 2022-04-06 2022-04-10 2022-04-07 2022-04-13 2022-04-07 2022-04-12 2022-04-10 2022-04-15 2022-05-10 Demonstration Project Detail ant Selection ed Planning and Design Stud y for Cairo Transport Authorit y (CTA) EG-EEAA-291298-CS-INDV / Enhanced Capacity, Behavio Individual Consult IBRD / 91660 Post Limited 14,023.09 Signed 2022-04-24 2022-04-27 2022-05-15 2022-08-07 2022-05-19 2022-08-07 2022-06-01 2022-09-02 2023-05-28 Communication Specialist ral Change and Communicat ant Selection ion EG-EEAA-298186-CS-CDS / S Support the Operationalizati Under Implement IBRD / 91660 Post Direct Selection Direct 0.00 2022-06-05 2022-12-11 2022-06-12 2022-06-15 2023-06-15 olid Waste Management Con on of SWM Master Plans in G ation sultant reater Cairo EG-EEAA-302288-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Limited 0.00 Signed 2022-07-14 2022-08-07 2022-07-17 2022-09-07 2022-07-24 2022-09-11 2022-08-10 2023-08-09 M&E Specialist nitoring & Evaluation ant Selection EG-EEAA-308069-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Limited 28,842.66 Signed 2022-08-07 2022-07-15 2022-08-07 2022-06-15 2022-08-07 2022-06-15 2022-08-07 2022-07-20 2023-07-31 2. Senior Procurement Specia nitoring & Evaluation ant Selection list EG-EEAA-310322-CS-CDS / 1 Project Management and Mo IBRD / 91660 Post Direct Selection Direct - National 30,400.79 Signed 2022-08-19 2022-09-15 2022-08-24 2022-08-02 2022-08-25 2022-08-03 2023-07-30 .Senior Procurement Speciali nitoring & Evaluation st EG-EEAA-310335-CS-CDS / P Project Management and Mo IBRD / 91660 Post Direct Selection Direct - National 0.00 Signed 2022-08-19 2022-09-15 2022-08-24 2022-08-02 2022-08-28 2023-07-30 roject Coordinator nitoring & Evaluation EG-EEAA-310342-CS-CDS / S Support the Operationalizati enior Solid Waste Manageme IBRD / 91660 on of SWM Master Plans in G Post Direct Selection Direct - National 0.00 Signed 2022-08-19 2022-09-15 2022-08-25 2022-08-08 2022-08-28 2023-07-30 nt Advisor reater Cairo EG-EEAA-322034-CS-CDS / T Support the Operationalizati Under Implement echnical Consultant - SUPB (S IBRD / 91660 on of SWM Master Plans in G Post Direct Selection Direct - National 0.00 2022-10-20 2023-01-03 2022-10-27 2022-10-27 2023-02-27 ation ingle Use Plastic Bags) reater Cairo EG-EEAA-322049-CS-CDS / T Support the Operationalizati Under Implement echnical Consultant (2) - SUP IBRD / 91660 on of SWM Master Plans in G Post Direct Selection Direct - National 0.00 2022-10-20 2023-01-03 2022-10-27 2022-10-27 2023-02-27 ation B (Single Use of Plastic Bags) reater Cairo EG-EEAA-322061-CS-CDS / E Project Management and Mo IBRD / 91660 Post Direct Selection Direct - National 0.00 Signed 2022-10-20 2022-08-15 2022-10-25 2022-08-09 2022-10-25 2023-08-30 nvironmental Specialist nitoring & Evaluation EG-EEAA-326989-CS-INDV / Enhancing the Air Quality M Individual Consult Open - Internationa Lead Advisory Consultant for IBRD / 91660 anagement & Response Syst Post 0.00 Signed 2022-11-24 2022-11-27 2023-01-12 2023-01-10 2023-02-02 2023-01-31 2023-03-09 2023-09-05 ant Selection l Component (1) em EG-EEAA-330429-CS-CDS / S Project Management and Mo IBRD / 91660 Post Direct Selection Direct - National 0.00 Under Review 2022-12-08 2022-12-21 2022-12-11 2022-12-15 2023-12-15 enior Financial Specialist nitoring & Evaluation EG-EEAA-330433-CS-INDV / Project Management and Mo Individual Consult IBRD / 91660 Post Limited 0.00 Under Review 2022-12-14 2023-01-30 2022-12-19 2022-12-22 2023-01-01 2024-01-01 Financial Assistant nitoring & Evaluation ant Selection EG-EEAA-346369-CS-INDV / Enhanced Capacity, Behavio Individual Consult Pending Impleme IBRD / 91660 Post Limited 0.00 2023-03-05 2023-03-10 2023-03-15 2023-03-16 2023-04-16 Project Logo Designer ral Change and Communicat ant Selection ntation ion EG-EEAA-355594-CS-INDV / Project Management and Mo Individual Consult Under Implement IBRD / 91660 Post Limited 0.00 2023-04-09 2023-04-02 2023-04-14 2023-05-18 2023-05-05 2023-06-09 2023-12-06 SENIOR PROCUREMENT SPEC nitoring & Evaluation ant Selection ation IALIST EG-EEAA-356471-CS-INDV / Enhanced Capacity, Behavio Individual Consult Pending Impleme IBRD / 91660 Post Limited 0.00 2023-04-13 2023-04-18 2023-05-09 2023-06-13 2023-12-10 Communication Specialist ral Change and Communicat ant Selection ntation ion EG-EEAA-356469-CS-INDV / Project Management and Mo Individual Consult Under Implement IBRD / 91660 Post Limited 0.00 2023-04-13 2023-04-02 2023-04-18 2023-05-09 2023-06-13 2023-12-10 M&E Specialist nitoring & Evaluation ant Selection ation EG-EEAA-360655-CS-INDV / Support the Operationalizati Individual Consult IBRD / 91660 Post Limited 0.00 Under Review 2023-05-14 2023-05-01 2023-05-19 2023-06-09 2023-06-30 2023-12-27 Project engineer on of SWM Master Plans in G ant Selection reater Cairo EG-EEAA-360725-CS-INDV / Enhancing the Air Quality M AQM Skills Training, and Univ Individual Consult Open - Internationa Pending Impleme IBRD / 91660 anagement & Response Syst Post 0.00 2023-05-16 2023-06-20 2023-07-11 2023-07-31 2025-06-17 ersity Curriculum & Licensing ant Selection l ntation em / Accrediting Development EG-EEAA-360727-CS-INDV / Enhancing the Air Quality M Provide recommendations for Individual Consult Under Implement IBRD / 91660 anagement & Response Syst Post Open - National 0.00 2023-05-08 2023-06-04 2023-06-02 2023-06-05 2023-06-27 2023-07-27 improving Emergency Respo ant Selection ation em nse Mechanism for the Black Cloud EG-EEAA-360731-CS-INDV / Enhancing the Air Quality M Environmental Expert in Air Individual Consult Under Implement IBRD / 91660 anagement & Response Syst Post Open - National 0.00 2023-06-08 2023-06-04 2023-07-11 2023-07-20 2023-07-31 2024-01-27 Quality Monitoring Networks ant Selection ation em and Source Apportionment EG-EEAA-363375-CS-CDS / S Enhancing the Air Quality M Pending Impleme ocial Development and Gend IBRD / 91660 anagement & Response Syst Post Direct Selection Direct - National 0.00 2023-05-29 2023-06-08 2023-08-12 2024-02-08 ntation er Specialist em EG-EEAA-363391-CS-CDS / S Project Management and Mo Pending Impleme IBRD / 91660 Post Direct Selection Direct - National 0.00 2023-06-14 2023-06-24 2023-08-28 2024-02-24 ENIOR PROCUREMENT SPECI nitoring & Evaluation ntation ALIST1 Page 3 PROCUREMENT PLAN Project information: Country: The People’s Republic of China Project name: World Bank loan China Plastic Waste Reduction Project- Chongqing sub-project P-number: P174267 Project Implementation agency: Chongqing Municipal PMO Chongqing Environment Sanitation Group Wulong District Construction Investment Group Co., Ltd. Chongqing Nanzhou Urban Management Co. Ltd, Date of the Procurement Plan: May 14, 2021 Period covered by this Procurement Plan: 2021-2026 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” dated November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. A. The Bank’s Standard Procurement Documents (SPDs): The Bank’s SPDs shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. B. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures (Tendering and Bidding Law of the Peoples’ Republic of China, i.e. TBL promulgated by its Order No. 21 dated August 30, 1999 and the Implementation Regulations of the TBL promulgated by its State Council Order No. 613 dated November 30, 2011 and any amendments thereof) may be used with the following conditions to meet the requirements for open competitive procurement of paragraph 5.4 of the Procurement Regulations: a. All procurement notices shall be published in a national newspaper of wide circulation, or on a widely-used website / electronic portal with free access. b. A minimum of twenty (20) business days shall be given to Bidders between the date of such advertisement (or the date of availability of procurement documents, whichever is later and the deadline for the submission of bids). The advertisement and procurement documents shall specify the deadline for the submission of bids. Potential Bidders shall be allowed to inspect and purchase procurement documents at any time prior to the deadline for the submission of bids. c. Any Bidder/Consultant should be eligible to participate in a procurement process and to be awarded a Bank-financed contract as defined in paragraphs 3.21, 3.22 and 3.23 of the Procurement Regulations. d. Bidders/Consultants shall be allowed to submit bids/proposals by mail or in person. Bidders/consultants shall not be mandatory required to be present at the bid/proposal opening session. e. Bidders should not be required to register as a condition for inspecting or purchasing procurement documents, submitting its bid or receiving contract award. A winner Bidder, shall be given reasonable opportunity of registering (if required) before contract signing without any let or hindrance. Bidding shall not be restricted to any class of contractors. f. The winning bidder shall not be required, as a condition of award, to reduce its bid price No contract negotiation shall be permitted unless agreed in the procurement plan. g. No bid may be rejected solely on the basis that the bid price exceeds any cost estimate. Rejection of all bids or re-bidding shall not be allowed solely because the number of bids is less than three (3). Rebidding shall not take place without any sound justification. h. The Bank’s procurement documents for approaching the national market or any procurement document acceptable to the Bank shall be used. All procurement documents must require that bidders/consultants present a signed acceptance at the time of bidding or submitting a proposal, to be incorporated in any resulting contract, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i. The procurement documents shall disclose the newspaper and / or the electronic means in which the information on contract award shall be published. j. The contract award notification shall identify: (a) name and address of the Borrower’s Project Implementing Unit, (b) name and reference number of the contract being awarded and the selection method used (c) names of all Bidders/Consultants that submitted bids/proposals and their prices as read out at the bid opening meeting and as evaluated (d) names of all Bidders/ Consultants whose bids/proposals were rejected either as nonresponsive or as not meeting qualification criteria or were not evaluated, with the reasons therefor and (e) the name of the successful Bidder/Consultant, the final contract price, the contract duration and a summary of its scope. k. The Borrower shall implement an effective complaint mechanism allowing bidders or consultants to complain, and have their complaints handled and responded in a timely manner. Procurement documents should indicate the complaint mechanism procedure and provide the professional title and address of the officials to whom such protests should be sent. l. The Bank shall be allowed to review procurement documentation and activities related to the activities included in the procurement plan. C. Other national procurement arrangements: When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. D. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing is not applicable for those contracts identified in the Procurement Plan tables. E. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations is not applicable. F. Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations: Goods: Domestic Preference is applicable for those contracts identified in the Procurement Plan tables. Works: Domestic Preference is not applicable for those contracts identified in the Procurement Plan tables. G. Other Relevant Procurement Information: Prior Review Threshold: The thresholds of procurement methods and the requirements for the Bank’s prior review are shown in Table1. Table1. Thresholds for Procurement Methods and Prior Review Expenditure Contract Value Procurement Prior Review Category Threshold (US$) Method Threshold (US$) 1. Civil works ≥40,000,000 International Open All contracts Competitive Procurement (International + Open) National Open ≥ 500k to Competitive All contracts ≥15 <40,000,000 Procurement million (National + Open) Request for <500,000 N/A Quotations All contracts ≥15 Any value Direct Selection million International Open Competitive ≥10,000,000 Procurement All contracts (International + Open) National Open 2. Goods/Non- ≥ 500k to Competitive All contracts ≥4 consulting services <10,000,000 Procurement million (National + Open) Request for <500,000 N/A Quotations All contracts ≥4 Any value Direct Selection million Currency Unit = Chinese Yuan (CNY) US$1.00 = CNY 6.5 Procurement Packages with Methods and Time Schedule: Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN PIU 1: Chongqing Environment and Sanitation Group (ESG) Jieshi secondary sorting & transfer station expansion - Road, 8839m2; Civil Engineering greening, ESG- Open, 2021-09- 2021-11- 2021- 1 Works 100% for kitchen waste 18835m2; station 3280 504.6 RFB Post 12 No   W-1 National 20 01 12-01 separation wall (with gate), workshop, parking 966m lot and general layout Recyclables sorting unit, Jieshi secondary 14400m2; 1# sorting & transfer storage, 2700m2; station expansion - 2# storage, Recyclable sorting 1600m2; ESG- workshop, Open, 2023-08- 2023-10- 2023- 2 Works 100% wastewater 5112 786.5 RFB Post 24 No   W-2 warehouse, National 20 01 12-01 reclamation and equipment reuse system, infrastructure and 200m2 other ancillary plant base facilities preparing and processing Xiajiaba secondary sorting & transfer station expansion – Move and rebuild ESG- Civil Engineering Open, 2021-09- 2021-11- 2021- 3 Works 100% open channel RFB Post 12 No   W-3 for kitchen waste 1452 223.38 National 20 01 12-01 inside the station sorting workshop, parking lot and general layout Xiajiaba secondary sorting & transfer road, 12500m2; greening, ESG- station expansion Open, 2023-09- 2023-10- 2023- 4 Works 100% Civil Engineering 8400m2  5248 807.4 RFB Post 24 No   W-4 National 20 01 12-01 wall/fence (with Bidding for high gates), 850m; value recycling workshop, Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN sanitation vehicle maintenance base, return water system, etc. Warehouse, 1776m2; bulky wastes crushing plant, 875m2; Zouma secondary Raw material sorting & transfer storage, 2400m2  station expansion - plastic granulation 2021-09- 2021-11- 2021- kitchen waste plant, 4800m2; ESG- Open, 20 01 12-01 5 Works 100% treatment system, pyrolytic oxidation 5809 893.7 RFB Post 14 No   W-5 National warehouse, large plant of plastic, crushing workshop 11400m2 tank and other civil zone, 648m2; works wastewater treatment unit, 340m2; textile wastes recycling unit, 3600m2 Luoqi low-value recyclables recycling base - Civil works (waste plastics raw materials storehouse, plastic Foam glass granulation manufacture 2021-09- 2021-11- 2021- ESG- workshop, plastic plant, 3600m2; Open, 20 01 12-01 6 Works 100% 9635 1482.3 RFB Post 12 No   W-6 oil cracking glass pre- National workshop, waste processing plant, spinning recycling 924m2 workshop, glass pretreatment workshop, foam glass production workshop and other civil works) Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Urban ship (floating) waste Land area, collection and 6200m2; treatment facilities excavated - Civil earthwork, woks(highway to 841.5m3; tack ESG- Open, 2022-07- 2022-09- 2022- 7 Works 100% riverside, road, filled earthwork, 8364 1286.8 RFB Post 12 No   W-7 National 20 01 12-01 approach bridge, 32430m3; road area, harbor excavated basin, slope earthwork of yard protection, dock basin, ancillary works, 6945.95m3 etc.) Urban ship (floating) waste Collection and collection and transportation treatment facilities ESG-G- system (16 Open, 2023-08- 2023-10- 2023- 8 Goods 100% – collection and 300 46.2 RFQ Post 24 No   1 forklifts16, 2 National 20 01 12-01 transfer equipment loaders 2; 2 (16 forklifts, 2 transfer carts) loaders and 2 transfer trucks) Jieshi secondary sorting & transfer station expansion – Phase II- ‘Two Wastewater ESG-G- network reclamation and Open, 2023-08- 2023-10- 2023- 9 Goods 100% 4631 712.5 RFB Prior 24 No   2 integration’ reuse system National 20 01 12-01 equipment (PP / PE, inside the Base pet, pet reuse water system and supporting system) Jieshi secondary 1. washing tower sorting & transfer of dedusting and ESG-G- station expansion – deodorizing Open, 2023-08- 2023-10- 2023- 10 Goods 100% 1250 192.3 RFB Post 24 No   3 Phase II- system; 2. National 20 01 12-01 deodorization Photocatalytic equipment oxidation unit;3. blowers 4. Plant Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN liquid atomizing system and hydraulic control system; 5. Spray dedusting system; 6. air supply system and axial flow fan Xiajiaba secondary sorting & transfer station expansion – Phase I-main Compactor equipment system, automatic (compactor, system, discharge ESG-G- automatic control Open, 2021-09- 2021-11- 2021- 11 Goods 100% chute for various 3400 523.1 RFB Prior 12 No   4 system, steel National 20 01 12-01 kinds of wastes; structure platform, lifting system and discharge chute, 20 shaped steels waste transfer containers, 10 31- ton transfer vehicles, etc.) Xiajiaba secondary sorting & transfer ESG-G- VI national Open, 2021-09- 2021-11- 2021- 12 Goods 100% station expansion – 270 41.5 RFQ Post 12 No   5 Phase I- standard National 20 01 12-01 6 tractors Xiajiaba secondary sorting & transfer ESG-G- VI national Open, 2021-09- 2021-11- 2021- 13 Goods 100% station expansion – 90 13.8 RFQ Post 12 No   6 standard National 20 01 12-01 Phase I-Six semitrailers Xiajiaba secondary collection and ESG-G- sorting & transfer Open, 2023-09- 2023-10- 2023- 14 Goods 100% station expansion – transportation 450 69.2 RFB Post 24 No   7 National 01 01 12-01 system 16 Phase II Collection forklifts16, 2 and transfer (16 Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN forklifts, 2 loaders, loaders, 5 transfer 5 transfer vehicles, trucks  etc.) 1two-screw conveyer 2Whole bottle pre- washing Xiajiaba secondary machine 3 Color sorting & transfer sorter of whole station expansion – bottle 4. Output Phase II - Two belt conveyor (no ESG-G- network PET bottle) 5. Open, 2023-08- 2023-10- 2023- 15 Goods 100% 5381 827.8 RFB Prior 24 No   8 integration’ Output belt National 20 01 12-01 equipment (PP / PE, conveyor pet, pet reuse (varicolored PET water system and bottle) 6. supporting system) Transparent PET plates washing line; 7. Cleaning line of color PET bottle. 1 washing tower of dedusting and deodorizing system,  2 Xiajiaba secondary Photocatalytic sorting & transfer oxidation unit  2023-09- 2023-10- 2023- station expansion – 3blowers 4. Plant ESG-G- Open, 01 01 12-01 16 Goods 100% Phase II - liquid atomizing 1792 275.7 RFB Post 12 No   9 National system and deodorization hydraulic control equipment system;  6. Spray dedusting system; 7. air supply system and axial flow fan Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Xiajiaba secondary sorting & transfer ESG-G- station expansion – Photometric Open, 2021-09- 2021-11- 2021- 17 Goods 100% 448 68.9 RFB Post 12 No   10 Phase II - equipment National 20 01 12-01 photovoltaic system equipment Zouma secondary 2021-09- 2021-11- 2021- ESG-G- sorting & transfer VI national Open, 20 01 12-01 18 Goods 100% 2286 351.7 NBF Post 14 No   11 station expansion - standard National Phase I-41 tractors Zouma secondary sorting & transfer 2021-09- 2021-11- 2021- ESG-G- VI national Open, 20 01 12-01 19 Goods 100% station expansion - 615 94.6 RFB Post 14 No   12 standard National Phase I-41 semi- trailers Zouma secondary sorting & transfer 2021-09- 2021-11- 2021- ESG-G- Refuse transfer Open, 20 01 12-01 20 Goods 100% station expansion - 1679 258.3 RFB Post 14 No   13 container National Phase I-73 transfer containers Zouma secondary sorting & transfer 2021-09- 2021-11- 2021- ESG-G- Electric forklifts Open, 20 01 12-01 21 Goods 100% station expansion - 368 56.6 RFB Post 14 No   14  2T  National Phase II-2T electric forklift Luoqi low-value 1 single shaft recyclables shredder; 2 2021-09- 2021-11- 2021- ESG-G- recycling base- butterfly screw Open, 20 01 12-01 22 Goods 100% 1015 156.2 RFB Post 14 No   15 plastic cleaning mud press; 3 National and granulation crusher  4 equipment granulators Complete set of 2021-09- 2021-11- 2021- Luoqi low-value ESG-G- optical separation Open, 20 01 12-01 23 Goods 100% recyclables 572 88.0 RFB Post 12 No   16 equipment; National recycling base- broken glass waste glass zigzag screening Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN pretreatment machine; Eddy equipment current separator; injection screw air compressor; relaxation vibrating screen; natural gas burner Luoqi low-value recyclables 2021-09- 2021-11- 2021- ESG-G- Foam glass Open, 20 01 12-01 24 Goods 100% recycling base- 1650 253.8 RFB Post 12 No   17 production National Foam glass production Photometric sorter; Air pressure device; Co rotating Luoqi low-value parallel two-way recyclables screw extruder; 2021-09- 2021-11- 2021- ESG-G- recycling base- Biaxial shear Open, 20 01 12-01 25 Goods 100% 1802.5 277.3 RFB Post 12 No   18 waste textile crusher; National recycling pelletizer; equipment Loosening machine; carding machine; acupuncture machine 1. automatic compression box; 2. Steel mesh Urban ship framework plastic (floating) waste composite pipe; 3. collection and 2021-09- 2021-11- 2021- Steel mesh ESG-G- treatment facilities Open, 20 01 12-01 26 Goods 100% framework plastic 946 145.5 RFB Post 12 No   19 -mechanical National composite pipe; 4. equipment (oil spill Plastic coated storage tanks and composite steel garbage cans) pipe; 5. plastic coated composite steel pipe Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Information 2022-09- 2022-11- 2022- ESG-G- ESG Information system related Open, 20 01 12-01 27 Goods 100% 4858 747.4 RFB Prior 12 No   20 system equipment and National components, etc. Liquid chromatography, inductively coupled plasma 2022-09- 2022-11- 2022- ESG Monitoring and atomic mass ESG-G- Open, 20 01 12-01 28 Goods 100% Experimental spectrometry, 762 117.2 RFB Post 12 No   21 National Center residual carbon determination of oil and other laboratory equipment PIU 2: Wulong Dev Investment Group (WL) Construction of Wulong district municipal solid Construction of waste transfer Wulong District station project, WL-W- Open, 2022-09- 2022/10/ 2022/11/ 1 Works 100% Municipal Solid including 3821 588 RFB Post 24 No   1 National 01 11 10 Waste Transfer construction, Station installation, general drawing, equipment procurement Construction of Wulong District West Area MSW Construction of Transfer Station domestic garbage WL-W- Project, including Open, 2023-09- 2023-11- 2023/12/ 2 Works 100% transfer station in 3749 577 RFB Post 18 No   2 construction, National 01 01 1 the west of Wulong installation, District general drawing and equipment procurement Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Construction of Wulong District MSW collection and transfer system and Construction of intelligent domestic garbage dispatch center collection and project, including WL-W- Open, 2022-02- 2022-04- 3 Works 100% transfer system construction 1656 255 RFB Post 2022/5/1 24 No   3 National 01 01 and command and project, dispatch center in decoration Wulong District project, installation project, general drawing project and equipment procurement Wulong District MSW Landfill closure, including Wulong District civil engineering, WL-W- Municipal Solid installation Open, 2022-02- 2022-04- 2022- 4 Works 100% 2310 355 RFB Post 12 No   4 Waste Landfill engineering, National 01 01 05-01 closure general drawing engineering and equipment engineering Construction of Wulong district kitchen waste harmless disposal Construction of plant project, harmless disposal including WL-W- Open, 2023-07- 2023-09- 2023/9/3 5 Works 100% plant for kitchen construction 3737 575 RFB Post 24 No   5 National 01 01 0 waste in Wulong project, District installation project, general drawing project, equipment procurement Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Purchase garbage Wulong District sorting collection household garbage WL-G- bucket, intelligent Open, 2021-10- 2021-12- 2022- 6 goods 100% collection system 1512 233 RFB Post 18 No   1 buried sorting National 01 01 01-05 equipment collection box and procurement other equipment Wulong District Buy machine WL-G- MSW Transfer sweeper, garbage Open, 2021-10- 2021-12- 2022- 7 goods 100% 2174 334 RFB Post 18 No   2 System Equipment truck and other National 01 01 01-05 Purchase equipment PIU3: Chongqing Nanzhou Urban Management Service Co Ltd (QJ) Construction of Qijiang District waste secondary transfer station project, including Construction of construction secondary refuse Open, 2021-12- 2022-1- 2022-2- 1 QJ-W-1 Works 100% engineering, 5769 888 RFB Post 9 No   transfer station in National 1 11 11 installation Qijiang District engineering, general layout engineering, equipment procurement The construction of Yongxin waste transfer station includes construction Construction of engineering, Open, 2021-10- 2021-12- 2022-1- 2 QJ-W-2 Works 100% Yongxin refuse 881 136 RFB Post 9 No   installation National 1 11 11 transfer station engineering, general layout engineering and equipment procurement Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Construction of Hengshan, Yongcheng and Construction of Guofu waste waste transfer transfer stations, stations in Open, 2021-12- 2022-1- 2022-2- 3 QJ-W-3 Works 100% including 2661 409 RFB Post 9 No   Hengshan, National 1 11 11 construction, Yongcheng and installation, Guofu general layout and equipment procurement The construction of Shihao, Anshan, and Qushui refuse Construction of transfer stations Shihao, Anshan, Open, 2021-12- 2022-1- 2022-2- 4 QJ-W-4 Works 100% includes 2854 439 RFB Post 9 No   and Qushui refuse National 1 11 11 construction, transfer station installation, general layout, and equipment procurement The construction of Qijiang large waste dismantling station includes construction Construction of engineering, Open, 2022-10- 2022- 5 QJ-W-5 Works 100% large waste 756 116 RFB Post 2022-9-1 9 No   installation National 11 11-11 dismantling station engineering, general layout engineering and equipment procurement Civil engineering of Civil engineering domestic waste Open, 2022-8- 2022-9- 6 QJ-W-6 Works 100% of waste sorting 1267 195 RFB Post 2022-7-1 9 No   sorting collection National 11 11 collection point point Estima Expecte Sour Contrac ted Estimat Review d Date Expecte Contrac Procurem ce of Selecti t Advance S/ Ref. Cost ed Cost Market by WB of d Bid t Remark ent Fund Contract Name Main Activities on Period Contract N No. (CNY: (USD: Approach (Prior/P Publicat Opening Signing s Category s Method (Month ing 10,000 10,000) ost) ion of Date Date (WB) ) ) SPN Procurement of Procurement of Open, 2022-10- 2022-11- 2022- 7 QJ-G-1 Goods 100% 1910 294 RFB Post 3 No   waste sorting bins waste sorting bins National 1 11 12-11 Domestic waste Procurement of classification domestic waste Open, 2022-10- 2022-11- 2022- 8 QJ-G-2 Goods 100% information classification 243 37 RFQ Post 3 No   National 1 11 12-11 platform information procurement platform Reconstruction and Purchase and expansion of the installation of new Open, 2022-8- 2022-9- 9 QJ-G-3 Goods 100% original garbage equipment in 1184 182 RFB Post 2022-7-1 6 No   National 11 11 collection station in garbage collection 30 towns station Prior Review Threshold: The thresholds of procurement methods and the requirements for the Bank’s prior review are shown in Table2 according to the Procurement Regulations dated November 2020. Table 2. Thresholds for Procurement Methods and Prior Review Contract Expenditure Value Procurement Prior Review Category Threshold Method Threshold (US$) (US$) QCBS/QBS/LCS/FB ≥300,000 All contracts ≥2 S million <300,000 FBS, LCS, CQS Direct Selection All contracts ≥1 for firms million Consultant Services Selection of All contracts Individual ≥400,000 Consultant Direct Selection for All contacts ≥ individuels 400,000 Notes: QCBS: Quality- and Cost-Based DS: Direct Selection Selection IC: Individual Consultant QBS: Quality-Based Selection selection FBS: Fixed Budget Selection N/A: Not Applicable LCS: Least Cost Selection CQS: Consultants’ Qualifications-based Selection Currency Unit = Chinese Yuan (CNY) US$1.00 = CNY 6.5 Procurement Packages with Methods and Time Schedule: Revi Estima ew Expecte Expect Sour Contra Estimat ted Selecti d Date Contra Procure ce of Procurem by ed Bid ct Advance S/ Ref. ed Cost Cost on WB of ct ment Fund Contract Name Main Activities ent Openi Period Contract Remarks N No. (CNY: (USD: Metho Publicat Signin Category s Method (Prio ng (Mont ing 10,000) 10,000 d r/ ion of g Date (WB) Date h) ) SPN Post) PIU 1: Chongqing Environment and Sanitation Group (ESG) Make research and study to propose Research on the fiscal policy ESG-T- Consulting 100 and tax incentive policy recommendations Open, 2022- 2022- 1 75 11.5 CQS Post 2022-9-1 36 No   1 services % of low value recyclables for fiscal and tax National 10-11 11-11 in Chongqing incentive of low value recyclables in Chongqing Research and Study to propose policy Research on the system recommendation for ESG-T- Consulting 100 of charge-by-quantity charging system Open, 2021-12- 2022- 2022- 2 75 11.5 CQS Post 48 No   2 services % for household solid based on quantity of National 01 01-11 01-31 wastes wastes yield for household solid wastes Make research and studies to propose analytical results on Research on new green various materials, materials, new technologies, ESG-T- Consulting 100 Open, 2023-12- 2024- 2024- 3 technology, new processes and 75 11.5 CQS Post 36 No   3 services % National 01 01-11 02-01 process and new equipment of equipment of plastics plastics; and to propose recommendation inventories. Study on Preparation Research and study and accelerated to development a ESG-T- Consulting 100 degradation of heat Open, 2021-12- 2022- 2022- 4 new kind of 75 11.5 CQS Post 48 No   4 services % resistant polylactide National 01 01-11 02-11 polylactide for lunch based disposable lunch box products box Revi Estima ew Expecte Expect Sour Contra Estimat ted Selecti by d Date Contra Procure ce of Procurem ed Bid ct Advance S/ Ref. ed Cost Cost on WB of ct ment Fund Contract Name Main Activities ent Openi Period Contract Remarks N No. (CNY: (USD: Metho Publicat Signin Category s Method (Prio ng (Mont ing 10,000) 10,000 d r/ ion of g Date (WB) Date h) ) SPN Post) Make studies to propose paths and Implementation path draft technical and technical guidelines guidelines for ESG-T- Consulting 100 for comprehensive Open, 2021-09- 2021- 2021- 5 comprehensive 100 15.4 CQS Post 24 No   5 services % utilization of domestic National 20 11-01 12-01 utilization of waste (plastic) domestic waste resources in Chongqing (plastic) resources in Chongqing Public awareness by media, advertisement, and door-to-door publicity to various Publicity and training units (communities, ESG-T- 100 for capacity building institutions and so Trainin 6 Training 200 30.8 N/A N/A N/A N/A N/A 72 No   6 % MSW segregation and on); training of g/SOE recycling - city proper relevant personnel, to strengthen the capacity for ensuring the MSW front-end segregation in city proper PIU 2: Wulong Dev Investment Group (WL) Public awareness by media, advertisement, and door-to-door Publicity and training publicity to various 100 for capacity building Trainin 1 WL-T-1 Training units (communities, 400 61 N/A N/A N/A N/A N/A 72 No   % MSW segregation and g/SOE institutions and so recycling - Wulong on); training of relevant personnel, to strengthen the capacity for ensuring the MSW front-end Revi Estima ew Expecte Expect Sour Contra Estimat ted Selecti by d Date Contra Procure ce of Procurem ed Bid ct Advance S/ Ref. ed Cost Cost on WB of ct ment Fund Contract Name Main Activities ent Openi Period Contract Remarks N No. (CNY: (USD: Metho Publicat Signin Category s Method (Prio ng (Mont ing 10,000) 10,000 d r/ ion of g Date (WB) Date h) ) SPN Post) segregation in Wulong District Research and study; policy work; Improvement of information system Open, Consulting 100 agricultural mulching to improve the 2021- 2021- 2 WL-T-2 300 46 QCBS Internation Post 2021-9-1 72 No   services % film recycling and reuse agricultural mulching 10-11 11-11 al system - Wulong film recycling and reuse system in Wulong District Research and study; policy work; Qijiang Integrated information system Open, Consulting 100 Urban-rural MSW 2021- 2021- 3 WL-T-3 to improve the 352 54 QCBS Internation Post 2021-9-1 72 No   services % management system 10-11 11-11 integrated urban- al Improvement rural management system in Wulong Research on whole Research and study process information to propose a set of Consulting 100 Open, 2021- 2021- 4 WL-T-4 management system of methods for whole- 75 12 CQS Post 2021-9-1 72 No   services % National 10-11 11-11 MSW (including plastic process information wastes) system construction Make research and study to propose Study on the system policy and mechanism of recommendations Consulting 100 recycling and utilization for the system and Open, 2021- 2021- 5 WL-T-5 75 12 CQS Post 2021-9-1 72 No   services % of plastic pesticide mechanism of National 10-11 11-11 packaging waste in recycling and Chongqing utilization of plastic pesticide packaging waste in Chongqing Subto         1202 185                   tal Revi Estima ew Expecte Expect Sour Contra Estimat ted Selecti by d Date Contra Procure ce of Procurem ed Bid ct Advance S/ Ref. ed Cost Cost on WB of ct ment Fund Contract Name Main Activities ent Openi Period Contract Remarks N No. (CNY: (USD: Metho Publicat Signin Category s Method (Prio ng (Mont ing 10,000) 10,000 d r/ ion of g Date (WB) Date h) ) SPN Post) PIU3: Chongqing Nanzhou Urban Management Service Co Ltd (QJ) Public awareness by media, advertisement, and door-to-door publicity to various Publicity and training units (communities, 100 for capacity building institutions and so Trainin 1 QJ-T-1 Training 600 92 N/A N/A N/A N/A N/A 72 No   % MSW segregation and on); training of g/SOE recycling - Qijiang relevant personnel, to strengthen the capacity for ensuring the MSW front-end segregation in Qijiang District Research and study; policy work; Qijiang Integrated information system Open, Consulting 100 Urban-rural MSW to improve the 2021- 2021- 2 QJ-T-2 266 41 QCBS Internation Post 2021-9-1 72 No   services % management system integrated urban- 10-11 11-11 al Improvement rural management system in Qijiang District Consulting Improvement of Research and study; Open, 100 2021- 2021- 3 QJ-T-3 services, agricultural film policy work; 400 62 QCBS Internation Post 2021-9-1 72 No   % 10-11 11-11 training recycling capacity information system al Study on the management system of Research and study; Consulting 100 Open, 2021- 2021- 4 QJ-T-4 rural waste agricultural policy work; 75 12 CQS post 2021-9-1 72 No   services % National 10-11 11-11 film recycling and information system resource utilization Study on MSW Make research and Consulting 100 study to propose Open, 2021- 2021- 5 QJ-T-5 segregation system in 75 12 CQS post 2021-9-1 72 No   services % National 10-11 11-11 Chongqing policy recommendations Revi Estima ew Expecte Expect Sour Contra Estimat ted Selecti by d Date Contra Procure ce of Procurem ed Bid ct Advance S/ Ref. ed Cost Cost on WB of ct ment Fund Contract Name Main Activities ent Openi Period Contract Remarks N No. (CNY: (USD: Metho Publicat Signin Category s Method (Prio ng (Mont ing 10,000) 10,000 d r/ ion of g Date (WB) Date h) ) SPN Post) for MSW segregation system in Chongqing CPMO contract management, financial management and audit, environment Open, Consulting 100 Project management 2021- 2021- 1 PM-T-1 management, 2259 347.54 QCBS internation Prior 2021-9-1 72 No services % consulting service 10-11 11-11 technical design & al BD review, including project performance evaluation & results of promotion Construction Construction Open, Consulting 100 supervision 2021- 2021- 2 PM-T-2 supervision consulting 3000 461.59 QCBS internation Prior 2021-9-1 72 No services % consulting service 10-11 11-11 service al Municipality for all projects level comprehens Social assessment, Social assessment, Consulting 100 Open, 2021- 2021- ive 3 PM-T-3 resettlement external resettlement 100 15.38 CQS Post 2021-9-1 72 No services % National 10-11 11-11 arrangemen monitoring external monitoring t Incremental Operating Costs for CQPMO, Wulong PMO and Qijiang PMO, PIUs & Training and workshops for plastic Incremental Operating 100 wastes reduction to Trainin 4 PM-T-4 Training Costs (Training, 200 30.77 N/A N/A N/A N/A N/A 72 No % enhance the g/SOE Workshops, Etc.) institutional capacity in the Districts for implementing municipal solid wastes sorting and management PROCUREMENT China : China Plastic Waste Reduction Project PLAN General Information Country: China 2021-08-02 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174267 GPN Date: 2021-07-23 Project Name: China Plastic Waste Reduction Project Loan / Credit No: IBRD / 92660 Ningbo Plastic Waste Reduction project Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure NBSHJ-W-1 / Civil works of se Component 3 Improvements ment Document - Single Stage - One E 11,838,221.0 2024-01-1 wage treatment plant of Ning IBRD / 92660 to Municipal Solid Waste Ma Post Request for Bids Open - National 1 Envelope proce 0.00 Signed 2022-08-31 2022-06-09 2022-09-05 2022-10-03 2022-07-26 2022-10-17 2022-08-19 2022-11-21 nvelope 0 5 bo resource recycling base nagement and Plastic Recycl ss (Non Bank-SPD ing ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NBSHJ-S-1 / Supply and Insta Component 3 Improvements Open - Internationa Single Stage - One E llation of Ningbo resource rec IBRD / 92660 to Municipal Solid Waste Ma Prior Request for Bids 9,684,995.00 0.00 Signed 2022-08-31 2022-11-10 2022-09-07 2022-11-30 2022-10-19 2023-01-31 2022-11-18 2023-03-08 2022-12-23 2023-05-27 2024-02-22 l nvelope ycling base WWTP nagement and Plastic Recycl ing NBDBS-G-18 / Computers, te st phones, front end, back en d, UI design, test and product Component 3 Improvements and project management too to Municipal Solid Waste Ma Request for Quota Single Stage - One E IBRD / 92660 Post Open - National 451,100.00 0.00 Signed 2022-11-16 2022-12-08 2023-01-11 2024-01-11 ls (mainly including office, Na nagement and Plastic Recycl tions nvelope vicat Premium, Redis, JetBrai ing ns, Xshell Plus7,Adobe 2020, Figma, Sketch, PS, mockingb ot, Shimo, etc) NBDBS-G-1 / 1000 sets of pl Component 3 Improvements ates and accessories of bin c to Municipal Solid Waste Ma Single Stage - One E ases, including stainless stee IBRD / 92660 Prior Request for Bids Open - National 3,182,800.00 0.00 Canceled 2021-07-26 2021-08-09 2021-09-08 2021-09-29 2021-10-27 2022-03-26 nagement and Plastic Recycl nvelope l plates and accessories (pow ing der coating included) . NBDBS-G-2 / 1000 sets of co ntrol system modules, includi Component 3 Improvements ng but not limited to capaciti to Municipal Solid Waste Ma Single Stage - One E ve touchscreen assembly, co IBRD / 92660 Prior Request for Bids Open - National 2,387,100.00 0.00 Canceled 2021-07-26 2021-08-09 2021-09-08 2021-09-29 2021-10-27 2022-03-26 nagement and Plastic Recycl nvelope ntroller assembly, switch ass ing embly, RFID module, industri al personal computer assemb ly, pneumatic valve module, etc. NBDBS-G-3 / 1000 sets of se Component 3 Improvements nsor module, including patter to Municipal Solid Waste Ma Single Stage - One E Under Imple IBRD / 92660 Post Request for Bids Open - National 2,961,908.46 0.00 2023-01-13 2023-01-31 2023-02-01 2023-03-07 2023-03-15 2023-04-11 2023-04-14 2023-04-28 2023-05-19 2023-11-15 n recognition camera, EdgeB nagement and Plastic Recycl nvelope mentation oard-lite computer card, RFID ing module plus tag, etc. NBDBS-G-4 / 1000 sets of pa Component 3 Improvements rts and accessories, including to Municipal Solid Waste Ma Single Stage - One E Under Imple wiring-harness-making acces IBRD / 92660 Post Request for Bids Open - National 1,080,626.38 0.00 2023-01-13 2023-01-31 2023-01-18 2023-03-07 2023-03-01 2023-04-12 2023-03-31 2023-04-26 2023-05-05 2023-11-01 nagement and Plastic Recycl nvelope mentation sories, fastener accessories, ing consumables accessories, et c. Component 3 Improvements NBDBS-G-02 / 1000 sets of c Single Stage - One E Under Imple IBRD / 92660 to Municipal Solid Waste Ma Prior Request for Bids Open - National 5,093,395.45 0.00 2023-01-17 2023-02-14 2023-02-07 2023-02-26 2023-03-21 2023-03-29 2023-04-20 2023-06-11 2023-05-25 2023-11-21 ontrol system modules, nvelope mentation nagement and Plastic Recycl ing NBDBS-G-01 / 1000 sets of p Component 3 Improvements lates and accessories of bin c to Municipal Solid Waste Ma Single Stage - One E ases, including stainless stee IBRD / 92660 Prior Request for Bids Open - National 5,663,402.50 0.00 Canceled 2023-01-12 2023-02-14 2023-02-02 2023-02-26 2023-03-16 2023-03-28 2023-04-15 2023-05-09 2023-05-20 2023-11-16 nagement and Plastic Recycl nvelope l plates and accessories (pow ing der coating included) . NBDBS-G-01-2 / 1000 sets of Component 3 Improvements plates and accessories of bin to Municipal Solid Waste Ma Single Stage - One E Under Imple cases, including stainless ste IBRD / 92660 Prior Request for Bids Open - National 5,663,402.50 0.00 2023-05-26 2023-06-01 2023-06-02 2023-06-07 2023-06-30 2023-07-30 2023-09-03 2024-01-31 nagement and Plastic Recycl nvelope mentation el plates and accessories (po ing wder coating included) . NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NBTA-6 / Technical upgrade Component 2 Sub National a Quality And Cost- Open - Internationa Under Implement service for waste segregation IBRD / 92660 nd Local Technical Assistanc Post 752,340.00 0.00 2023-01-13 2023-01-30 2023-02-03 2023-02-06 2023-03-19 2023-04-16 2023-05-16 2023-06-20 2023-07-25 2027-07-24 Based Selection l ation smart management platform e and Capacity Building NBTA-08 / Research on Data and Information Security Man Component 2 Sub National a Consultant Qualifi Under Implement agement Based on Ningbo m IBRD / 92660 nd Local Technical Assistanc Post Open - National 94,042.00 0.00 2023-01-16 2023-01-30 2023-02-06 2023-02-06 2023-03-22 2023-04-21 2023-05-26 2024-05-25 cation Selection ation unicipal waste segregation s e and Capacity Building mart management platform INDIVIDUAL CONSULTANTS Page 1 Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 PROCUREMENT PLAN (Textual Part) P163264 - Cambodia Agricultural Sector Project information: Diversification Project Project Implementation agency: Ministry of Agriculture, Forestry and Fisheries (MAFF) Ministry of Rural Development (MRD), Ministry of Water Resources and Meteorology (MOWRAM), and Ministry of Economy and Finance (MEF) Date of the Procurement Plan: November 19, 2018 Period covered by this Procurement Plan: 18 months procurement plan Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Royal Kingdom of Cambodia’s Updated Procurement Manual for All Externally Financed Projects/Programs (“Procurement Manual”), promulgated through the Sub-decree 74 dated May 22, 2012, which is issued pursuant to Article 3 of the Kingdom of Cambodia’s Law on Public Procurement dated January 14, 2012, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. i. Procurement shall be open to eligible firms from any country; ii. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights as per attached confirming application of, and compliance with, the Bank’s Anti- Corruption Guidelines, including format; iii. Each Project shall put in place an effective complaint review system that includes review by the implementing agency and subsequent review by another party not involved in the in the procurement process, if not satisfied with the review of the implementing agency. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not Applicable Other Relevant Procurement Information. Except the credit line facilities (tentatively US$30 million) under the sub- component 1.2 Financing Agriculture Diversification of the project that will be administered by the Rural Development Bank acting as the Treasury Bank on behalf of the Government, and channelled through the financial intermediaries (participating financial institutes); all the procurement activities under other components and sub-components including the matching grant facility under Cambodia Agricultural Sector Diversification Project will be governed by World Bank Procurement Regulation for IPF Borrowers, July 2016 (revised November 2017 and Revised August 2018) PROCUREMENT Cambodia : Cambodia Agricultural Sector Diversification Project PLAN General Information Country: Cambodia 2019-09-24 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163264 GPN Date: Project Name: Cambodia Agricultural Sector Diversification Project Loan / Credit No: IDA / 63660 Ministry of Rural Development Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned MRD-CASDP-RW01 / Improve Request for Bids - ment of 20.07 km DBST and Component 2: Supporting Pu Open - Internationa Single Stage - One E Works (without pr 2023-12-2 IDA / 63660 Post Request for Bids 3,500,000.00 0.00 Signed 2022-12-30 2022-12-28 2023-01-04 2023-01-26 2023-02-18 2023-03-14 2023-05-19 2023-05-17 2023-06-23 2.46 km Laterite Rural Roads blic Infrastructure l nvelope equalification) SP 0 in Kampong Cham Province D MRD-CASDP-ICB-RW02 / Imp Request for Bids - rovement of 45.09 km of roa Component 2: Supporting Pu Open - Internationa Single Stage - One E Works (without pr Under Imple 2025-02-0 IDA / 63660 Post Request for Bids 6,556,101.00 0.00 2023-05-19 2023-05-19 2023-05-24 2023-07-08 2023-10-06 2023-11-13 ds in Battambong, Kampong blic Infrastructure l nvelope equalification) SP mentation 5 Chhnang, Preah Vihear, and D Stung Treng Province GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MRD-190326-GO-RFQ / M Component 2: Supporting Pu Request for Quota Single Stage - One E otorcycles for MRD and Provi IDA / 63660 Post Open - National 23,400.00 21,879.00 Completed 2020-09-19 2020-11-14 2020-12-16 2021-01-13 2021-01-05 blic Infrastructure tions nvelope ncial PIUs for MRD KH-MRD-197129-GO-RFB / Pi Component 2: Supporting Pu Single Stage - One E IDA / 63660 Post Request for Bids Open - National 112,000.00 80,200.00 Completed 2020-10-15 2020-11-23 2020-10-20 2020-11-19 2020-12-09 2020-12-19 2020-12-14 2021-01-23 2020-12-19 2021-07-22 2021-03-04 ckups for MRD-CASDP team blic Infrastructure nvelope KH-MRD-200488-GO-RFQ / O Component 2: Supporting Pu Request for Quota Single Stage - One E ffice Furniture for PMU and Pr IDA / 63660 Post Open - National 20,000.00 19,566.72 Completed 2020-11-09 2020-12-15 2020-12-16 2020-12-29 2020-12-31 blic Infrastructure tions nvelope ovincial PIU MRD KH-MRD-211023-GO-RFQ / E Component 2: Supporting Pu Request for Quota Single Stage - One E IDA / 63660 Post Open - National 69,900.00 67,885.00 Completed 2021-09-09 2021-11-23 2021-10-01 2022-02-21 2021-11-06 quipment of survey for Civil blic Infrastructure tions nvelope Works KH-MRD-200486-GO-RFQ / O Component 2: Supporting Pu Request for Quota Single Stage - One E ffice Equipment for PMU and IDA / 63660 Post Open - National 41,500.00 0.00 Canceled 2020-11-09 2021-01-01 2021-03-02 blic Infrastructure tions nvelope Provicial PIUs for MRD KH-MRD-200486-GO-RFQ-2 / - Desktop computer : 14 unit s - Laptop computer : 11 units - Laser printer (B/W)(A4) : 3 u Component 2: Supporting Pu Request for Quota Single Stage - One E IDA / 63660 Post Open - National 58,800.00 61,000.00 Completed 2021-08-22 2021-11-08 2021-09-07 2022-01-07 2021-09-11 nits blic Infrastructure tions nvelope - Color printer (A4 & A3) : 1 u nit - Digital camera (GPS build in ) : 1 unit - Digital laser copy, printer, a nd scanner A3-A4: 1 units Laser printer & scanner / P -KH-MRD-285458-GO-RFQ Component 2: Supporting Pu Request for Quota Single Stage - One E IDA / 63660 Post Open - National 45,000.00 48,400.00 Signed 2022-06-29 2022-09-14 2022-07-30 2023-01-12 roject vehicle ( pick-up) blic Infrastructure tions nvelope NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MRD-129390-CS-INDV / P Component 2: Supporting Pu Individual Consult IDA / 63660 Post Open 18,000.00 81,351.00 Signed 2019-09-04 2020-08-01 2019-09-30 2021-01-06 2019-10-07 2021-03-11 2019-10-17 2021-08-03 2021-04-09 rocurement Specialist blic Infrastructure ant Selection KH-MRD-128596-CS-INDV / F Component 2: Supporting Pu Individual Consult IDA / 63660 Post Open 18,000.00 105,390.00 Terminated 2019-09-04 2019-12-12 2019-10-02 2020-07-31 2019-10-09 2020-08-05 2019-10-20 2020-08-26 2021-04-12 inance Specialist blic Infrastructure ant Selection KH-MRD-153851-CS-INDV / E Component 2: Supporting Pu Individual Consult ngineering Team Leader -Nat IDA / 63660 Post Open 157,500.00 62,100.00 Signed 2020-08-30 2021-07-23 2020-10-18 2021-11-30 2020-11-08 2021-12-08 2020-12-13 2021-12-20 2024-08-24 blic Infrastructure ant Selection ional Road Engineer KH-MRD-186706-CS-INDV / T Component 2: Supporting Pu Individual Consult opographic Survey / Road De IDA / 63660 Post Open 108,000.00 30,360.00 Signed 2020-08-30 2021-07-23 2020-10-18 2021-12-22 2020-11-08 2021-12-24 2020-12-13 2022-01-05 2023-11-28 blic Infrastructure ant Selection sign Engineer-National MRD-2019-IC-CS-8 / De-mini Component 2: Supporting Pu Individual Consult IDA / 63660 Post Open 30,000.00 31,050.00 Signed 2020-08-30 2021-07-23 2020-10-18 2021-12-17 2020-11-08 2021-12-21 2020-12-13 2021-12-31 2021-10-09 ng/UXO Specialist blic Infrastructure ant Selection KH-MRD-186708-CS-INDV / R Component 2: Supporting Pu Individual Consult Under Implement IDA / 63660 Post Open 90,000.00 0.00 2020-12-01 2023-02-23 2021-01-19 2023-06-09 2021-02-09 2023-06-12 2021-03-16 2024-02-29 esident Engineer 01 blic Infrastructure ant Selection ation Page 1 KH-MRD-186709-CS-INDV / L Component 2: Supporting Pu Individual Consult IDA / 63660 Post Open 72,000.00 28,980.00 Signed 2020-08-30 2021-07-23 2020-10-18 2022-04-22 2020-11-08 2022-04-27 2020-12-13 2022-05-01 2023-11-28 ab & Material Engineer blic Infrastructure ant Selection KH-MRD-211032-CS-INDV / F Component 2: Supporting Pu Individual Consult IDA / 63660 Post Open 18,000.00 36,000.00 Signed 2021-01-05 2021-02-08 2021-02-18 2021-08-09 2021-02-25 2021-08-16 2021-03-08 2021-08-27 2021-12-31 inacial Management Assistan blic Infrastructure ant Selection t KH-MRD-186707-CS-INDV / S Component 2: Supporting Pu Individual Consult IDA / 63660 Post Open 36,000.00 30,360.00 Signed 2021-08-13 2021-08-02 2021-10-01 2021-12-22 2021-10-22 2021-12-24 2021-11-26 2022-01-12 2023-05-20 tructural / QS / QC-Engineer- blic Infrastructure ant Selection National Page 2 PROCUREMENT PLAN (Textual Part) Project information: Country: Guyana Project Name: Guyana Strengthening Human Capital through Education Project (GHCP) Project Number: P177741 Project Implementation agency: Ministry of Education Date of the Procurement Plan: September 21, 2022 Period covered by this Procurement Plan: September 21, 2022, to September 20, 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the National Procurement Act of 2003 and regulations, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables]; Works: is not applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Guyana : Guyana Strengthening Human Capital through Education Project PLAN General Information Country: Guyana 2022-09-22 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177741 GPN Date: Project Name: Guyana Strengthening Human Capital through Education Project Loan / Credit No: IDA / 71330 Ministry of Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Improve Servi GY-MOE-312412-GO-RFB / Pr ce Delivery and Enhance the Single Stage - One E Under Imple IDA / 71330 Post Request for Bids Open - National 278,927.00 0.00 2022-09-12 2023-02-13 2022-09-14 2023-02-22 2022-10-26 2023-03-14 2022-11-25 2022-12-16 2023-03-16 ocurement of Textbooks Learning Environment at the nvelope mentation Secondary Level Component 1: Improve Servi GY-MOE-303409-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Post Direct Selection 1,186,000.00 0.00 2022-09-12 2022-11-11 2022-09-20 2023-02-07 2022-10-31 2023-01-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level Component 1: Improve Servi GY-MOE-303375-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Post Direct Selection 343,246.00 0.00 2022-07-13 2022-11-11 2022-07-21 2023-02-07 2022-08-31 2022-11-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level Component 1: Improve Servi GY-MOE-303402-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Post Direct Selection 644,400.00 0.00 2022-09-12 2022-11-11 2022-09-20 2023-02-07 2022-10-31 2023-01-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level Component 1: Improve Servi GY-MOE-303405-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Prior Direct Selection 4,277,600.00 0.00 2022-09-12 2022-11-14 2022-09-20 2023-02-09 2022-10-31 2023-01-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level Component 1: Improve Servi GY-MOE-303401-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Post Direct Selection 757,427.00 0.00 2022-09-12 2022-11-11 2022-09-20 2023-02-07 2022-10-31 2023-01-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level Component 1: Improve Servi GY-MOE-303410-GO-DIR / Pr ce Delivery and Enhance the Direct - Internation Under Imple IDA / 71330 Post Direct Selection 510,400.00 0.00 2022-09-12 2022-11-11 2022-09-20 2023-02-07 2022-10-31 2023-01-29 ocurement of Textbooks Learning Environment at the al mentation Secondary Level GY-MOE-361539-GO-RFQ / O Component 4: Project Manag Request for Quota Single Stage - One E IDA / 71330 Post Limited 4,000.00 0.00 Canceled 2023-05-28 2023-07-12 2023-08-11 ffice Furniture ement and Monitoring and E tions nvelope valuation GY-MOE-360008-GO-RFQ / O Component 4: Project Manag Request for Quota Single Stage - One E Under Imple IDA / 71330 Post Limited 10,000.00 0.00 2023-05-30 2023-05-31 2023-06-24 2023-07-24 ffice Equipment ement and Monitoring and E tions nvelope mentation valuation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY-MOE-329249-CS-QCBS / Component 2: Strengthen Sk Consultant Qualifi Open - Internationa Under Implement Tracer Study of TVET Gradua IDA / 71330 ills Development and Techni Post 300,000.00 0.00 2023-01-03 2022-12-01 2023-01-24 2023-01-12 2023-02-21 2023-03-13 2023-04-27 2023-10-24 cation Selection l ation tes cal and Vocational Training GY-MOE-329251-CS-QCBS / Component 2: Strengthen Sk Consultant Qualifi Open - Internationa Under Implement National Skills Audit Consulta IDA / 71330 ills Development and Techni Post 150,000.00 0.00 2023-01-03 2022-12-01 2023-01-24 2023-01-12 2023-02-08 2023-02-28 2023-04-14 2023-10-11 cation Selection l ation ncy cal and Vocational Training INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GY-MOE-317475-CS-INDV / P Component 4: Project Manag Individual Consult IDA / 71330 Post Open - National 71,691.00 0.00 Canceled 2022-11-01 2022-09-29 2022-12-20 2022-12-23 2023-01-10 2024-01-10 roject Coordinator ement and Monitoring and E ant Selection valuation GY-MOE-343185-CS-INDV / P Component 4: Project Manag Individual Consult IDA / 71330 Post Open - National 47,100.00 0.00 Signed 2023-02-26 2023-02-27 2023-03-21 2023-05-11 2023-03-24 2023-05-11 2023-04-02 2024-04-01 roject Engineer ement and Monitoring and E ant Selection valuation GY-MOE-343188-CS-INDV / Component 4: Project Manag Individual Consult IDA / 71330 Post Open - National 31,400.00 0.00 Signed 2023-02-26 2023-02-27 2023-03-30 2023-05-04 2023-03-31 2023-05-10 2023-05-01 2024-04-30 Monitoring & Evaluation Offic ement and Monitoring and E ant Selection er valuation GY-MOE-343179-CS-CDS / Pr Component 4: Project Manag Individual Consult IDA / 71330 Post Direct - National 6,000.00 0.00 Signed 2023-02-22 2023-02-25 2023-02-24 2023-03-22 2023-02-26 2023-03-24 2023-02-28 2023-08-31 ocurement Officer (shared) ement and Monitoring and E ant Selection valuation Page 1 GY-MOE-343183-CS-CDS / Fi Component 4: Project Manag Individual Consult IDA / 71330 Post Direct - National 6,000.00 0.00 Signed 2023-02-22 2023-02-27 2023-02-24 2023-03-24 2023-02-26 2023-03-24 2023-02-28 2023-09-30 nance Officer (shared) ement and Monitoring and E ant Selection valuation GY-MOE-346230-CS-INDV / P Component 4: Project Manag Individual Consult IDA / 71330 Post Direct - National 71,691.00 0.00 Signed 2023-03-01 2023-03-10 2023-03-04 2023-03-14 2023-03-06 2023-03-16 2023-03-31 2024-03-30 roject Coordinator ement and Monitoring and E ant Selection valuation GY-MOE-346231-CS-INDV / S Component 4: Project Manag Individual Consult IDA / 71330 Post Direct - National 6,000.00 0.00 Signed 2023-03-01 2023-03-12 2023-03-05 2023-05-24 2023-03-07 2023-05-24 2023-04-02 2024-04-01 ocial Specialist (Part-time) ement and Monitoring and E ant Selection valuation GY-MOE-355798-CS-INDV / F Component 4: Project Manag Individual Consult Under Implement IDA / 71330 Post Open - National 24,000.00 0.00 2023-04-20 2023-04-16 2023-05-30 2023-06-04 2023-06-19 2024-06-18 inance Assistant ement and Monitoring and E ant Selection ation valuation GY-MOE-355800-CS-INDV / P Component 4: Project Manag Individual Consult Under Implement IDA / 71330 Post Open - National 24,000.00 0.00 2023-04-20 2023-04-16 2023-05-30 2023-06-04 2023-06-19 2024-06-18 rocurement Assistant ement and Monitoring and E ant Selection ation valuation GY-MOE-355814-CS-CDS / E Component 4: Project Manag Under Implement IDA / 71330 Post Direct Selection Direct - National 8,000.00 0.00 2023-05-23 2023-05-22 2023-06-09 2023-06-29 2024-06-28 nvironmental Specialist (Part ement and Monitoring and E ation Time) valuation Component 1: Improve Servi GY-MOE-361519-CS-CDS / Sc ce Delivery and Enhance the Under Implement IDA / 71330 Post Direct Selection Direct - National 35,000.00 0.00 2023-05-18 2023-06-09 2023-05-28 2023-06-14 2023-10-12 hool Facility Plan Learning Environment at the ation Secondary Level GY-MOE-365697-CS-INDV / D Component 4: Project Manag Individual Consult Under Implement IDA / 71330 Post Open - National 150,000.00 0.00 2023-06-11 2023-06-14 2023-07-20 2023-07-21 2023-08-07 2024-08-06 evelopment of TVET Policy ement and Monitoring and E ant Selection ation valuation Page 2 PLAN DE PASSATION DE MARCHÉS (Partie Textuelle) Information sur le Projet : Western Africa, Solar Development in Sub-Saharan Africa Project – Phase 1 (Sahel), P162580 Agence d’exécution du Projet : WAPP (West African Power Pool) Date du plan de passation des marchés : 3 Mai 2018 Période couverte par ce plan de passation des marchés : 05/2018- 11/2019 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016) (“Règlement de Passation des Marchés”) l’Emprunteur utilise les outils électroniques de planification et de suivi de la passation des marchés (STEP) pour préparer, valider et actualiser ses plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Cette partie textuelle ainsi que les tableaux du plan de passation des marchés dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types d’appel d’offres publiés par la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale ainsi que pour tous les autres contrats spécifiés dans les tableaux du plan de passation des marchés inclus dans STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, au cas où la procédure de passation des marché est retenue (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures de passation de marchés du pays considéré peuvent être appliquées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres ouvert telles qu’énoncées dans le code des marchés publics du WAPP et le « Manuel de Procédures de Passation de Marchés » de Septembre 2011, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres du WAPP ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués dans le Plan de passation des marchés : « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués dans le Plan de passation des marchés : « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas Travaux : ne s’applique pas PROCUREMENT Western and Central Africa : Solar Development in Sub-Saharan Africa - Phase 1 (Sahel) PLAN General Information Country: Western and Central Africa 2018-09-12 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162580 GPN Date: 2018-11-26 Project Name: Solar Development in Sub-Saharan Africa - Phase 1 (Sahel) Loan / Credit No: IDA / D3320 WEST AFRICAN POWER POOL Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WAPP-178035-GO-DIR / R ecruitment of GENERAL ELEC Regional Solar Parks Prepara TRIC SOLUTION SAS for the i IDA / D3320 Post Direct Selection Direct 1,271,219.00 1,467,674.00 Signed 2020-06-18 2020-06-23 2020-06-23 2020-07-09 2020-07-28 2021-02-20 2021-01-24 tion. ntegration of renewable ener gy sources in the ICC project BJ-WAPP-366941-GO-RFQ / A Regional Solar Integration, D Request for Quota Open - Internationa Single Stage - One E Pending Impl cquisition of workstations for IDA / D3320 ispatch and Capacity Buildin Post 10,000.00 0.00 2023-06-30 2023-08-25 2023-11-23 tions l nvelope ementation Plexos software g. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WAPP-77483-NC-RFQ / Sol Regional Solar Parks Prepara Open - Internationa Single Stage - One E ar resource ground measure IDA / D3320 Post Request for Bids 1,000,000.00 0.00 Canceled 2019-02-01 2019-10-04 2019-02-06 2019-03-20 2019-04-19 2019-05-24 2019-11-20 tion. l nvelope ment campaign BJ-WAPP-149751-NC-RFB / N Regional Solar Parks Prepara Open - Internationa Single Stage - One E ew-Solar resource ground m IDA / D3320 Prior Request for Bids 3,000,000.00 3,012,974.94 Signed 2019-12-15 2019-12-23 2019-12-20 2020-04-29 2020-01-31 2020-05-18 2020-03-01 2020-06-15 2020-04-05 2020-09-01 2020-10-02 tion. l nvelope easurement campaign BJ-WAPP-303428-NC-DIR / G eotechnical Study for a 150 Regional Solar Parks Prepara IDA / D3320 Post Direct Selection Direct 25,000.00 0.00 Signed 2022-07-17 2022-10-03 2022-07-24 2022-10-05 2022-10-09 2023-04-07 MWp WAPP Regional Solar Po tion. wer Park in The Gambia BJ-WAPP-313752-NC-DIR / Ac Regional Solar Integration, D Direct - Internation Under Imple IDA / D3320 Post Direct Selection 155,000.00 0.00 2022-09-11 2022-09-13 2022-09-18 2022-09-13 2022-10-23 2023-10-23 quisition of PLEXOS Software ispatch and Capacity Buildin al mentation for ICC g. BJ-WAPP-316335-NC-DIR / C Regional Solar Integration, D Direct - Internation Under Imple ontractualisation de SCATEC IDA / D3320 ispatch and Capacity Buildin Post Direct Selection 168,844.00 0.00 2022-09-19 2022-09-20 2022-09-21 2022-09-26 2022-10-10 2022-11-30 al mentation pour organisation voyage d'e g. tudes en RSA BJ-WAPP-330508-NC-DIR / C Regional Solar Integration, D ontractualisation de Grid-Indi Direct - Internation IDA / D3320 ispatch and Capacity Buildin Post Direct Selection 372,800.00 0.00 Signed 2022-12-09 2022-12-07 2022-12-12 2022-12-13 2022-12-23 2023-02-12 a ( anciennement POSOCO) p al g. our organisation voyage d'et udes en INDE (ER) BJ-WAPP-358786-NC-DIR / A Regional Solar Integration, D CQUISITION DE DONNEES SA Direct - Internation Under Imple IDA / D3320 ispatch and Capacity Buildin Post Direct Selection 40,000.00 0.00 2023-05-03 2023-04-26 2023-05-10 2023-05-11 2023-06-14 2023-08-13 TELLITAIRES SUR L’ENSOLEIL al mentation g. LEMENT DE 12 SITES- SolarGi s BJ-WAPP-360311-NC-DIR / C ontractualisation avec RENA Regional Solar Integration, D C - Voyage d'études en Allem Direct - Internation Under Imple IDA / D3320 ispatch and Capacity Buildin Post Direct Selection 311,000.00 0.00 2023-05-15 2023-05-09 2023-05-18 2023-05-12 2023-05-29 2023-10-26 agne : programme 2 : exploit al mentation g. ation et integration de la pro duction d’energie solaire dan s le reseau BJ-WAPP-366938-NC-DIR / V Regional Solar Integration, D Direct - Internation Pending Impl SAT subscription extension w IDA / D3320 ispatch and Capacity Buildin Post Direct Selection 210,000.00 0.00 2023-06-19 2023-06-26 2023-07-31 2025-05-31 al ementation ith GE Digital (France) for ICC g. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF- REF-2 / Reinforcing the Regional Solar Parks Prepara Consultant Qualifi Open - Internationa Under Implement IDA / D3320 Post 300,000.00 0.00 2018-11-01 2019-07-10 2018-11-22 2019-01-05 2019-02-04 2019-03-11 2019-09-07 Information and Control Cent tion. cation Selection l ation er ( ICC) MOF-REF-3 / Definition and i Regional Solar Parks Prepara Quality And Cost- Open - Internationa IDA / D3320 Prior 1,000,000.00 591,611.98 Signed 2019-01-15 2019-07-17 2019-02-05 2019-09-19 2019-03-21 2019-12-05 2019-04-18 2020-02-03 2019-05-18 2020-02-17 2019-06-22 2020-04-30 2019-07-27 2020-05-20 2020-07-26 mplementation of Grid Code tion. Based Selection l MOF-REF-4 / Feasibility Stu Regional Solar Parks Prepara Quality And Cost- Open - Internationa dies for regional Solar parks i IDA / D3320 Prior 1,500,000.00 1,519,014.94 Under Review 2018-04-01 2018-05-18 2018-07-17 2018-09-20 2018-09-10 2018-10-10 2018-09-27 2018-11-14 2019-03-04 2018-12-19 2019-03-11 2019-12-19 tion. Based Selection l n Burkina and Mali MOF- REF-5 / Environmental Regional Solar Parks Prepara Quality And Cost- Open - Internationa IDA / D3320 Post 800,000.00 777,699.81 Signed 2018-09-17 2018-09-18 2018-10-08 2018-11-23 2018-11-21 2019-03-07 2018-12-19 2019-05-13 2019-01-18 2019-06-07 2019-02-22 2019-06-07 2019-03-29 2019-10-03 2020-03-28 &Socal studies Burkina Faso tion. Based Selection l MOF- REF-6 / Environmental Regional Solar Parks Prepara Quality And Cost- Open - Internationa IDA / D3320 Post 800,000.00 497,800.00 Signed 2018-12-17 2019-02-20 2019-01-07 2019-02-21 2019-02-20 2019-05-14 2019-03-20 2019-07-15 2019-04-19 2019-07-22 2019-05-24 2019-08-26 2019-06-28 2019-09-14 2020-06-27 &Social studies Mali tion. Based Selection l MOF- REF-8 / Transaction Ad Regional Solar Parks Prepara Quality And Cost- Open - Internationa IDA / D3320 Prior 1,000,000.00 0.00 Canceled 2018-10-01 2018-10-22 2018-12-05 2019-01-02 2019-02-01 2019-03-08 2019-04-12 2020-04-11 viser for auctions ( firm) tion. Based Selection l Page 1 BJ-WAPP-77487-CS-CQS / Re Regional Solar Parks Prepara Consultant Qualifi Open - Internationa newable Task force Consulta IDA / D3320 Post 300,000.00 0.00 Canceled 2019-02-15 2021-07-28 2019-03-08 2019-04-21 2019-05-21 2019-06-25 2019-12-22 tion. cation Selection l nt ( Technical Assistance) BJ-WAPP-102157-CS-QCBS / Regional Solar Parks Prepara Quality And Cost- Open - Internationa ML-Transaction Adviser for a IDA / D3320 Post 600,000.00 598,345.74 Signed 2019-02-27 2019-02-26 2019-03-20 2019-02-26 2019-05-03 2019-05-17 2019-05-31 2019-07-15 2019-06-30 2019-07-19 2019-08-04 2019-08-26 2019-09-08 2019-09-11 2020-09-07 tion. Based Selection l uctions in Mali ( firm) BJ-WAPP-102161-CS-QCBS / Regional Solar Parks Prepara Quality And Cost- Open - Internationa BF-Transaction Adviser for au IDA / D3320 Post 600,000.00 1,098,212.64 Signed 2019-02-27 2019-02-26 2019-03-20 2019-02-21 2019-05-03 2019-05-17 2019-05-31 2019-07-15 2019-06-30 2019-07-15 2019-08-04 2019-08-22 2019-09-08 2019-10-11 2020-09-07 tion. Based Selection l ctions in Burkina ( firm) BJ-WAPP-102164-CS-QCBS / Regional Solar Parks Prepara Quality And Cost- Open - Internationa Gambia- Feasibility Studies f IDA / D3320 Post 650,000.00 600,838.95 Signed 2019-04-15 2019-12-10 2019-05-06 2019-09-25 2019-06-19 2019-12-12 2019-07-17 2020-02-17 2019-08-16 2020-03-12 2019-09-20 2020-04-02 2019-10-25 2020-05-21 2020-10-24 tion. Based Selection l or regional Solar parks in the Gambia BJ-WAPP-102165-CS-QCBS / Gambia- Environmental &Soc Regional Solar Parks Prepara Quality And Cost- Open - Internationa IDA / D3320 Post 800,000.00 201,315.00 Signed 2019-04-15 2020-06-18 2019-05-06 2020-08-13 2019-06-19 2020-10-08 2019-07-17 2020-11-23 2019-08-16 2020-12-02 2019-09-20 2020-12-14 2019-10-25 2021-03-04 2020-10-24 al studies for Regional Solar tion. Based Selection l Parc in the Gambia BJ-WAPP-102167-CS-QCBS / Regional Solar Parks Prepara Quality And Cost- Open - Internationa Gambia-Transaction Adviser f IDA / D3320 Post 600,000.00 1,003,163.09 Signed 2019-05-15 2020-05-15 2019-06-05 2020-08-19 2019-07-19 2021-05-06 2019-08-16 2021-07-12 2019-09-15 2021-07-16 2019-10-20 2022-02-03 2019-11-24 2022-02-21 2020-11-23 tion. Based Selection l or auctions in Gambia ( firm) BJ-WAPP-149747-CS-LCS / A Regional Solar Parks Prepara Least Cost Selecti Open - Internationa udit du Projet Parcs solaires e IDA / D3320 Post 50,000.00 18,852.85 Signed 2020-02-15 2020-11-09 2020-03-07 2020-11-17 2020-04-20 2021-02-18 2020-05-18 2021-04-06 2020-06-17 2021-04-19 2020-07-22 2021-04-24 2020-08-26 2021-05-18 2021-02-22 tion. on l xercices 2018- 2019 et 2020 BJ-WAPP-154248-CS-CQS / El Regional Solar Integration, D aboration d'un programme d Consultant Qualifi Open - Internationa IDA / D3320 ispatch and Capacity Buildin Post 162,500.00 257,218.17 Signed 2020-01-26 2020-02-06 2020-02-16 2020-02-26 2020-03-31 2020-05-22 2020-04-30 2020-09-11 2020-06-04 2020-10-25 2020-12-01 e formation et certification e cation Selection l g. n énergies renouvelables BJ-WAPP-172292-CS-QCBS / Regional Solar Parks Prepara Quality And Cost- Open - Internationa Niger- Feasibility Studies for r IDA / D3320 Post 650,000.00 732,445.49 Signed 2020-05-10 2020-05-07 2020-05-31 2020-06-12 2020-07-14 2020-08-28 2020-08-11 2020-10-11 2020-09-10 2020-10-20 2020-10-15 2020-11-17 2020-11-19 2021-03-15 2021-11-19 tion. Based Selection l egional Solar parks in Niger BJ-WAPP-172293-CS-QCBS / Regional Solar Parks Prepara Quality And Cost- Open - Internationa IDA / D3320 Post 600,000.00 897,128.76 Signed 2020-08-13 2021-12-16 2020-09-03 2022-02-16 2020-10-17 2022-04-28 2020-11-14 2022-06-13 2020-12-14 2022-06-17 2021-01-18 2022-06-30 2021-02-22 2022-08-24 2022-02-22 Niger-Transaction Adviser for tion. Based Selection l auctions BJ-WAPP-172294-CS-QCBS / Regional Solar Parks Prepara Quality And Cost- Open - Internationa Niger-Environmental &Social IDA / D3320 Post 600,000.00 447,772.14 Signed 2020-09-25 2020-12-04 2020-10-16 2021-02-08 2020-11-29 2021-04-20 2020-12-27 2021-06-14 2021-01-26 2021-06-23 2021-03-02 2021-07-19 2021-04-06 2021-11-02 2022-04-06 tion. Based Selection l studies for regional Solar par ks in Niger BJ-WAPP-246914-CS-QCBS / New Task Force -GROUPE DE Regional Solar Parks Prepara Quality And Cost- Open - Internationa IDA / D3320 Post 400,000.00 266,608.60 Signed 2021-08-17 2021-08-13 2021-08-27 2021-09-11 2021-09-30 2021-10-19 2021-10-28 2022-01-18 2021-11-07 2022-03-08 2021-11-28 2022-03-22 2022-01-02 2022-04-26 2022-08-30 TRAVAIL SUR LES ÉNERGIES tion. Based Selection l RENOUVELABLES VARIABLES INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WAPP-77470-CS-INDV / In Regional Solar Integration, D Individual Consult dividual Consultant for Varia IDA / D3320 ispatch and Capacity Buildin Prior Open 450,000.00 407,500.00 Signed 2018-09-17 2018-09-18 2018-11-05 2019-02-14 2018-11-26 2020-09-25 2018-12-31 2019-04-12 2019-06-29 ant Selection ble Renewable Energies (VRE g. ) BJ-WAPP-102168-CS-INDV / Regional Solar Parks Prepara Individual Consult IDA / D3320 Post Open 250,000.00 247,200.00 Signed 2019-05-15 2020-01-22 2019-07-03 2021-01-26 2019-07-24 2021-02-10 2019-08-28 2021-02-16 2020-02-24 Social Expert (Individual Con tion. ant Selection sultant) BJ-WAPP-102169-CS-INDV / Regional Solar Parks Prepara Individual Consult IDA / D3320 Post Open 250,000.00 0.00 Canceled 2019-04-15 2019-06-03 2019-06-24 2019-07-29 2020-01-25 Accountant Individual Consul tion. ant Selection tant BJ-WAPP-119924-CS-INDV / Regional Solar Integration, D Individual Consult IDA / D3320 Post Open 250,000.00 135,000.00 Signed 2019-06-27 2021-04-21 2019-08-15 2021-09-03 2019-09-05 2021-10-20 2019-10-10 2021-09-25 2020-04-07 Assistant Project Coordinato ispatch and Capacity Buildin ant Selection r g. BJ-WAPP-119925-CS-INDV / E Regional Solar Integration, D Individual Consult IDA / D3320 Prior Open 500,000.00 484,754.80 Signed 2019-06-27 2019-10-21 2019-08-15 2020-02-20 2019-09-05 2020-04-21 2019-10-10 2020-05-23 2020-04-07 nvironmental Expert ispatch and Capacity Buildin ant Selection g. BJ-WAPP-119942-CS-CDS / A Regional Solar Integration, D IDA / D3320 Post Direct Selection Direct 250,000.00 249,900.00 Signed 2019-06-27 2020-10-15 2019-07-07 2020-01-13 2019-09-10 2020-01-20 2020-03-08 ccountant Expert- New ispatch and Capacity Buildin g. BJ-WAPP-170212-CS-INDV / Regional Solar Parks Prepara Individual Consult New- Recrutement d'un Expe IDA / D3320 Post Open 175,000.00 0.00 Canceled 2020-04-30 2020-04-29 2020-06-18 2020-07-09 2020-08-13 2021-02-09 tion. ant Selection rt en Energie renouvelable BJ-WAPP-172291-CS-INDV / P Regional Solar Parks Prepara Individual Consult IDA / D3320 Prior Direct 500,000.00 547,509.40 Signed 2020-05-15 2020-06-15 2020-05-22 2020-06-22 2020-05-25 2020-07-14 2020-06-20 2020-07-21 2020-12-17 rocurement Specialist- New tion. ant Selection BJ-WAPP-178032-CS-CDS / R ecruitment of EDF for the su Regional Solar Parks Prepara pervision of the integration IDA / D3320 Post Direct Selection Direct 113,361.00 83,618.17 Signed 2020-06-18 2020-06-23 2020-06-28 2020-07-22 2020-09-01 2020-10-28 2021-02-28 tion. of renewable energy sources integration in ICC project BJ-WAPP-218370-CS-INDV / Recrutement d'un Responsab Regional Solar Parks Prepara Individual Consult Under Implement IDA / D3320 Post Open 150,000.00 0.00 2021-02-14 2021-04-16 2021-04-04 2021-04-25 2021-05-30 2021-11-26 le Administratif (ve) et Comp tion. ant Selection ation table au Comité National CIG RE AO BJ-WAPP-229341-CS-CDS / I GR-Consultant pour Audit de Regional Solar Parks Prepara IDA / D3320 Post Direct Selection Direct 50,000.00 23,215.82 Completed 2021-04-19 2021-04-20 2021-04-29 2021-05-24 2021-05-29 2021-10-23 2021-07-18 2022-05-26 Surete pour la realisation du tion. PSVR au Burkina Faso BJ-WAPP-231168-CS-INDV / E Regional Solar Parks Prepara Individual Consult xpert en Energie renouvelabl IDA / D3320 Post Limited 350,000.00 193,168.84 Signed 2021-04-30 2021-05-18 2021-05-05 2021-07-22 2021-05-26 2021-07-22 2021-06-30 2021-09-10 2021-12-27 tion. ant Selection e - Non resident BJ-WAPP-235741-CS-CDS / M ali- Etude de faisabilité pour l Regional Solar Parks Prepara IDA / D3320 Post Direct Selection Direct 600,000.00 894,819.63 Signed 2021-05-25 2021-08-25 2021-05-31 2021-09-23 2021-07-10 2022-05-29 2021-10-08 ’hybridation solaire de la cen tion. trale hydroélectrique de Man antali Page 2 BJ-WAPP-258656-CS-CDS / Et udes complementaires de fai Regional Solar Parks Prepara IDA / D3320 Post Direct Selection Direct 550,000.00 497,889.00 Signed 2021-10-22 2021-10-22 2021-10-26 2021-10-25 2021-11-10 2021-11-22 2022-02-10 sabilite du parc solaire au Ma tion. li par NODALIS-HSF BJ-WAPP-259062-CS-CDS / S Regional Solar Parks Prepara econd Expert en Energies Re IDA / D3320 Post Direct Selection Direct 200,000.00 150,388.60 Signed 2021-10-24 2021-11-09 2021-10-31 2021-11-11 2021-11-21 2021-12-08 2022-05-20 tion. nouvelables non Resident BJ-WAPP-278781-CS-INDV / Consultant pour la conceptio Regional Solar Integration, D Individual Consult n et la mise en ligne d'un por IDA / D3320 ispatch and Capacity Buildin Post Open 36,288.00 29,876.00 Signed 2022-02-25 2022-03-03 2022-04-15 2022-05-19 2022-05-06 2022-05-19 2022-06-10 2022-06-15 2022-09-08 ant Selection tail web du comité national C g. IGRE Afrique de l’Ouest (CN CIGRE-AO) BJ-WAPP-313749-CS-CDS / S Regional Solar Integration, D Direct - Internation IDA / D3320 Post Direct Selection 132,250.00 0.00 Signed 2022-09-11 2022-09-13 2022-09-21 2022-10-06 2022-11-15 2023-11-15 upport to Working groups -Ph ispatch and Capacity Buildin al ase 3 g. BJ-WAPP-340022-CS-CDS / N Regional Solar Integration, D Direct - Internation Under Implement IDA / D3320 Post Direct Selection 53,148.00 0.00 2023-02-11 2023-03-23 2023-02-13 2023-02-06 2023-02-16 2023-10-31 ouveau contrat Gaffar Bawa, ispatch and Capacity Buildin al ation Comptable g. BJ-WAPP-361654-CS-CDS / Fi Regional Solar Parks Prepara Direct - Internation Under Implement nalization of the WAPP Grid C IDA / D3320 Post Direct Selection 250,000.00 0.00 2023-05-16 2023-05-23 2023-05-20 2023-05-24 2023-06-02 2023-10-30 tion. al ation ode and Tariff Comparative A nalysis Page 3 Procurement Plan I. General 1. Project Information Country : India Borrower : Directorate of Inland and Transport, Govt. of Assam Project Name : Assam Inland Water Transport Project [P157929] Loan Nos. : Project under preparation Bank’s Approval Date of the Procurement Plan: Nov 25, 2016 [through STEP] 2. Date of General Procurement Notice: Sep 20, 2016 3. Period covered by this Procurement plan: 18 months 4. Risk Rating for the Implementing Agencies: Substantial at PCN stage may be modified II. Goods and Non-consulting Services. 1. (a) Procurement Methods Procurement Method Threshold (US$ Equivalent) 1 Open International (Goods) Above 3 million 2 Open National (Goods) Above 100,000 and up to 3 million (with NCB conditions) – as per para 3.3 and 3.4 of the Guidelines 3 Open International (Works) Above 40 million Open National (Works) Above 100,000 3 Shopping (Goods/Works) Up to 100,000 and up to 40 million 4. Open International (Non- Above 3 million consulting Services) 5 Open National (Non-consulting Up to 3 million Services) 6 Direct Contract As per para 3.7 of Guidelines (b) Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Sl. Category Prior Review Threshold Comments No. (US$ Equivalent) 1 1 Works Above US$ 10.0 million All Contracts 1 Goods Above US$ 2.0 million All Contracts 2 Non-consulting Services Above US$ 2.0 million All Contracts 2. Pre-qualification: Bidders shall be pre-qualified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines): Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Under preparation 5. NCB Provisions: a) Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding; b) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; c) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State; d) Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; e) Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/Employer); f) Re-bidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; g) Rate contracts entered into by Directorate General of Supplies and Disposals (DGS&D) will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such 2 contracts will be acceptable however for any procurement under the Shopping procedures; h) Two or three envelope system will not be used (except when using e- procurement system assessed and agreed by the Bank). 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) Refer STEP system III. Selection of Consultants 1. (a) Procurement Methods Sl. Procurement Method Threshold (US$ Equivalent) N o. 1 Selection based on Consultants’ Up to 300,000 Qualifications / Least Cost Selection 2 Single-source Selection of As per para 3.9 – 3.11 of Guidelines consulting firms 3 Selection of Individual As per Section V of Guidelines Consultants/ Sole Source Procedures for the Selection of Individual Consultants 4 Quality- and Cost-based For all other cases Selection/ Quality-based Selection/ Selection under a Fixed Budget 5 i. International Shortlist Above US$ 800,000 ii. Shortlist may comprise Up to US$ 800,000 national consultants only (b) Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods (Firms) Above USD 1.0 million All Contracts 2. Individual Up to US$ 300,000 All Contracts 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost up to US$ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3 3. Any Other Special Selection Arrangements: NA IV. Other Requirements / Information (applicable for all procurements) a) Even for Post Review cases, the inputs of Bank on TORs will be obtained by project. b) The above thresholds are for the initial 18-month implementation period. Based on the procurement performance of the project, these thresholds may be subsequently modified. c) The prior review thresholds will also be indicated in the procurement plan. The procurement plan will be subsequently updated annually (or at any other time, if required), and will reflect any change in prior review thresholds. d) The World Bank will carry out an annual ex-post procurement review falling below the prior review thresholds indicated above. To avoid any doubts, the Bank may conduct at any time Independent Procurement Reviews (IPRs) of all the contracts financed under the grant. 4 5 PROCUREMENT India : Assam Inland Water Transport Project PLAN General Information Country: India 2016-11-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157929 GPN Date: 2016-09-20 Project Name: Assam Inland Water Transport Project Loan / Credit No: IBRD / P4830, IBRD / 90260 Directorate of Inland Water Transport, Assam Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-IWT-31053-CW-DIR / Cons Fleet safety improvements a 2018-05-1 IBRD / P4830 Post Direct Selection Direct 7,500.00 7,901.16 Signed 2017-10-05 2017-09-14 2017-10-10 2017-09-11 2017-11-14 2017-10-06 truction activities nd modernization 3 IN-IWT-37426-CW-RFQ / Up- gradation & Face-lift of 5nos. Vessels owned by the Direct or of Inland Water Transport Institutional, regulatory and Request for Quota Single Stage - One E 2018-07-1 IBRD / P4830 Post Open - National 54,000.00 0.00 Canceled 2017-11-23 2018-01-18 Under department of Transp safety strengthening tions nvelope 7 ort Govt. of Assam .The Ves sels name are S B Naharbil , SDB Rupknowar,Sb Boginodi, RPL Ushaban,MB Kameshwari IN-IWT-37481-CW-RFQ / Ref urbishment & Up-gradation of 8 nos Floating Terminal Viz . Tameswari,Sewali,Ganesh,J Institutional, regulatory and Request for Quota Single Stage - One E 2018-07-1 IBRD / P4830 Post Open - National 80,000.00 0.00 Canceled 2017-11-25 2018-01-20 onardon ,Damodar,Sukreswa safety strengthening tions nvelope 9 r,DLB Neothani & Pobitora o wned by the Director of IWT, under department of Transpo rt,Govt. of Assam IN-IWT-41703-CW-RFQ / Ren ovation And Up-gradation of t he office of the SPD ,AIWTD Society cum Commissioner Fleet safety improvements a Request for Quota Single Stage - One E 2018-09-0 & Secretary Transport Depart IBRD / P4830 Post Open - National 17,540.00 0.00 Canceled 2018-01-10 2018-03-07 nd modernization tions nvelope 3 ment,Govt of Assam includin g cabins for Transport Specia list,AIWTDS and common are as of SPD Chambers at Assa m Secretariat,Dispur Guwaha ti-6 IN-IWT-69953-CW-RFB / Sup ply,Erection,Installation and Commissioning of Passenger Elevator for Project Manage Fleet safety improvements a Request for Quota Single Stage - One E 2019-04-0 IBRD / P4830 Post Open - National 29,500.00 0.00 Canceled 2018-08-15 2018-10-10 ment Unit(PMU) of Assam Inl nd modernization tions nvelope 8 and Water Transport Develop ment Society at 3rd Floor of Director of Inland Water Tran sport,Ulubari,Guwahati-7810 07 IN-IWT-69606-CW-RFB / Ren ovation & Refurbishment wor k for Project Management U Fleet safety improvements a Single Stage - One E 2019-04-2 IBRD / P4830 Post Request for Bids Open - National 177,900.00 0.00 Canceled 2018-07-25 2018-07-23 2018-07-26 2018-08-25 2018-08-27 2018-09-24 2018-10-29 nit (PMU) of AIWTD Society at nd modernization nvelope 7 3rd Floor, Director of Inland Water Transport Department, Ulubari, Guwahati, 781007 IN-IWT-77416-CW-RFB / Ren ovation & Refurbishment wor k for Project Management Un Fleet safety improvements a Single Stage - One E 2019-05-0 IBRD / P4830 Post Request for Bids Open - National 139,100.00 138,110.09 Signed 2018-09-11 2018-09-12 2018-09-13 2018-10-04 2018-10-11 2018-10-09 2018-11-19 2018-11-02 2018-12-04 it (PMU) of AIWTD Society at nd modernization nvelope 1 3rd Floor, Director of Inland Water Transport Department, Ulubari, Guwahati, 781007 IN-IWT-89250-CW-RFQ / Ren ovation and refurbishment w ork for Project management Fleet safety improvements a Request for Quota Single Stage - One E 2019-08-1 IBRD / P4830 Post Open - National 41,415.00 36,072.93 Signed 2018-12-19 2019-02-13 2019-02-21 Unit (PMU)-II of AIWT Project nd modernization tions nvelope 2 at 4th Floor,Transport Depart ment,Block-D,Janata Bhawan ,Dispur, Guwahati, 781006 IN-IWT-104351-CW-RFB / De velopment of three (3) ferry t Improvement in terminal infr Open - Internationa Single Stage - Two E 30,000,000.0 2022-12-0 IBRD / P4830 Prior Request for Bids 0.00 Canceled 2019-07-01 2019-07-06 2019-08-17 2019-10-30 2019-12-04 erminals at North Guwahati, astructure l nvelope 0 3 South Guwahati & Majuli und er phase I. IN-IWT-120461-CW-RFB / Wo rks for repair and retrofitting of Assam Inland Water Trans Fleet safety improvements a Single Stage - One E 2020-04-1 port vessels IBRD / P4830 Post Request for Bids Open - National 697,303.64 0.00 Canceled 2019-06-30 2019-07-05 2019-08-16 2019-09-15 2019-10-20 nd modernization nvelope 7 Location: Guwahati, Vessels Name (5 nos.): MV Kaziranga , RPL Bagbor, RPL Nambor, S. B. Tuni, S.B. Naharbil at Guw ahati IN-IWT-120463-CW-RFB / Ret rofitting works for repair and retrofitting of Assam Inland Fleet safety improvements a Single Stage - One E 2020-04-1 Water Transport vessels Loca IBRD / P4830 Post Request for Bids Open - National 753,491.33 0.00 Canceled 2019-06-30 2019-07-05 2019-08-16 2019-09-15 2019-10-20 nd modernization nvelope 7 tion: Guwahati, Vessels Nam e (4 nos.): M.B Kameswari, M .V Melvinjones, M.B Mahalaks hmi, M.V Chandardinga: IN-IWT-120473-CW-RFB / Wo rks for repair and retrofitting of Assam Inland Water Trans Fleet safety improvements a Single Stage - One E 2020-04-1 IBRD / P4830 Post Request for Bids Open - National 440,857.26 0.00 Canceled 2019-06-30 2019-07-05 2019-08-16 2019-09-15 2019-10-20 port vessels Location: Nemati nd modernization nvelope 7 , Vessels Name (3 nos.): M.V Kameng, RPL Dolgobinda,RPL Mahabh airobi IN-IWT-120887-CW-RFB / Wo rks for repair and retrofitting of Assam Inland Water Trans Fleet safety improvements a Single Stage - One E 2020-04-1 IBRD / P4830 Post Request for Bids Open - National 432,213.00 0.00 Canceled 2019-06-30 2019-07-05 2019-08-16 2019-09-15 2019-10-20 port vessels Location: Dhubri nd modernization nvelope 7 & Goalpara, Vessels Name (3 nos.): RPL Jogighopa, RPL Bra hmaputra, RPL Dorika Page 1 IN-IWT-120899-CW-RFB / De velopment of River Terminal Improvement in terminal infr Single Stage - Two E 21,039,737.7 2020-06-2 IBRD / P4830 Prior Request for Bids Open - National 0.00 Canceled 2019-06-30 2019-07-25 2019-09-05 2019-11-18 2019-12-23 Infrastructure on the river Br astructure nvelope 2 0 ahmaputra at Aphalamukh, Majuli. IN-IWT-121796-CW-RFB / Ret Fleet safety improvements a Single Stage - One E 2020-04-2 rofitting & repairing of 15 nos IBRD / P4830 Post Request for Bids Open - National 2,323,865.23 0.00 Canceled 2019-07-11 2019-07-13 2019-07-14 2019-07-14 2019-08-25 2019-09-16 2019-09-24 2019-10-29 nd modernization nvelope 6 of IWT Vessels IN-IWT-211145-CW-RFB / Up Institutional, regulatory and Single Stage - Two E 2022-08-1 gradation of exisiting floating IBRD / 90260 Post Request for Bids Open - National 431,571.82 0.00 Canceled 2021-01-20 2021-01-27 2021-03-18 2021-06-21 2021-08-15 safety strengthening nvelope 5 Crew Training Center (CTC) a t Guwahati IN-IWT-211408-CW-RFB / Co Improvement in terminal infr Single Stage - Two E 2023-01-0 nstruction of Terminals at No IBRD / 90260 Prior Request for Bids Open - National 8,130,081.30 0.00 Canceled 2021-06-12 2021-06-19 2021-08-13 2021-11-16 2022-01-10 astructure nvelope 5 rth Guwahati, Assam IN-IWT-211441-CW-RFB / Est ablishment of Integrated Co Project Management Suppor Single Stage - Two E Pending Imp 2023-04-0 IBRD / 90260 Post Request for Bids Open - National 1,355,013.55 0.00 2021-09-03 2021-09-10 2021-11-04 2022-02-07 2022-04-03 mmand Control Center and t nvelope lementation 3 River Information Services (R IS) IN-IWT-213624-CW-RFB / Up Institutional, regulatory and Single Stage - One E 2022-07-1 gradation of exisiting floating IBRD / 90260 Post Request for Bids Open - National 446,933.52 0.00 Canceled 2021-01-20 2021-01-27 2021-03-18 2021-05-07 2021-07-16 safety strengthening nvelope 6 Crew Training Center (CTC) a t Guwahati IN-IWT-217815-CW-RFB / Ret Fleet safety improvements a Single Stage - One E 2022-08-0 IBRD / 90260 Post Request for Bids Open - National 833,333.33 730,513.66 Signed 2021-02-15 2021-02-16 2021-02-20 2021-02-16 2021-04-11 2021-04-27 2021-05-31 2021-06-25 2021-08-01 2022-04-28 rofitting of 07 (Seven) Nos. I nd modernization nvelope 1 WT Vessels Request for Bids - IN-IWT-244480-CW-RFB / Co Improvement in terminal infr Single Stage - Two E Works (without pr 15,465,335.0 39,431,210. 2023-08-3 nstruction of terminal at Guw IBRD / 90260 Prior Request for Bids Open - National Signed 2021-07-26 2021-08-04 2021-07-31 2021-12-01 2021-10-09 2021-12-15 2021-12-22 2022-05-09 2022-02-06 2022-06-09 astructure nvelope equalification) SP 0 63 1 ahati Gateway Ghat (South G D uwahati) Request for Bids - IN-IWT-338275-CW-RFB / Co Improvement in terminal infr Single Stage - Two E Works (without pr 11,562,500.0 2024-11-1 nstruction of terminal at Nea IBRD / 90260 Prior Request for Bids Open - National 0.00 Canceled 2023-02-06 2023-02-15 2023-03-29 2023-05-05 2023-05-27 astructure nvelope equalification) SP 0 7 mati and Aphlamukh ferry gh D at Request for Bids - IN-IWT-338276-CW-RFB / Co Improvement in terminal infr Single Stage - Two E Works (without pr 2024-11-1 nstruction of terminal at Nort IBRD / 90260 Post Request for Bids Open - National 6,037,500.00 0.00 Canceled 2023-02-06 2023-02-16 2023-02-15 2023-02-20 2023-03-29 2023-04-28 2023-05-05 2023-05-27 astructure nvelope equalification) SP 7 h Guwahati and Umananda f D erry ghat IN-IWT-368004-CW-RFB / Co nstruction of Terminal and Ri Improvement in terminal infr Single Stage - Two E Other (with field f 17,598,750.0 Under Imple 2024-05-2 verine Infrastructure for 4 S IBRD / 90260 Prior Request for Bids Open - National 0.00 2023-06-22 2023-06-28 2023-06-27 2023-08-08 2023-10-21 2023-11-25 astructure nvelope or explanation) 0 mentation 3 maller Terminals at North Gu wahati, Umananda, Neamati and Aphalamukh GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWT-23868-GO-RFQ / Proc urement of IT equipment (De Institutional, regulatory and Request for Quota Single Stage - One E IBRD / P4830 Post Open - National 7,000.00 7,807.06 Completed 2017-08-12 2017-10-07 2017-09-13 2018-04-05 2017-10-22 sktops- 5, ipad-1, Laptops- 4, safety strengthening tions nvelope UPS- 5, Printers- 5, Antivirus- 9, Routers- 5) IN-IWT-24018-GO-RFQ / Proc urement of office furniture (E Request for Quota Single Stage - One E xecutive Tables- 11, High/Mid IBRD / P4830 Post Open - National 7,446.00 6,691.40 Signed 2017-08-14 2017-10-09 2017-09-04 2018-04-07 tions nvelope Back Chairs- 11, Visitor Chair s- 5, Storage Cabinets- 2, Ver tical Blinds) IN-IWT-31057-GO-DIR / Proc Fleet safety improvements a Request for Quota Single Stage - One E IBRD / P4830 Post Open - National 3,000.00 2,953.46 Signed 2017-10-10 2017-12-05 2017-11-08 2018-06-03 urement of air conditioners nd modernization tions nvelope IN-IWT-12473-GO-RFB / Proc Single Stage - One E urement of night navigation IBRD / P4830 Post Request for Bids Open - National 500,000.00 0.00 Canceled 2017-04-28 2017-06-28 2017-05-08 2017-09-18 2017-06-07 2017-08-06 2017-09-10 2018-03-09 nvelope equipments IN-IWT-52816-GO-RFQ / Proc urement of medium term req uirement of Computer and ot Fleet safety improvements a Request for Quota Single Stage - One E IBRD / P4830 Post Open - National 15,800.00 11,744.82 Signed 2018-04-12 2018-06-07 2018-05-16 2018-12-04 her peripherals for staffs of P nd modernization tions nvelope roject Management Unit,Assa m Inland Water Transport De velopment Society IN-IWT-52826-GO-RFQ / Proc urement of Furniture and Fixt Fleet safety improvements a Request for Quota Single Stage - One E ures for the staffs of Project IBRD / P4830 Post Open - National 14,500.00 9,331.83 Signed 2018-04-12 2018-06-07 2018-05-25 2018-12-04 nd modernization tions nvelope Management Unit of Assam I nland Water Transport Devel opment Society IN-IWT-56347-GO-RFQ / Proc urement of Air Conditioners a nd office Equipment for the P Fleet safety improvements a Request for Quota Single Stage - One E IBRD / P4830 Post Open - National 9,100.00 4,784.53 Signed 2018-04-12 2018-06-07 2018-05-07 2018-12-04 roject Management Unit of t nd modernization tions nvelope emporary office of Assam Inl and water Transport Develop ment Society IN-IWT-89197-GO-RFB / E-pr ocurement of 10 nos. 50 Pax Institutional, regulatory and Open - Internationa Single Stage - Two E Vessel with capacity of 25 m IBRD / P4830 Prior Request for Bids 8,423,417.00 9,542,035.54 Signed 2018-12-12 2019-01-08 2018-12-17 2019-01-08 2019-01-28 2019-05-31 2019-04-12 2019-09-23 2019-05-17 2020-02-01 2019-11-13 safety strengthening l nvelope otor cycles and 10 nos. 100 Pax Vessel with capacity of 5 0 nos. motor cycles IN-IWT-89251-GO-RFQ / Sup ply,Erection,Installation & Co mmissioning of Passenger El Fleet safety improvements a Request for Quota Single Stage - One E evator for PMU of AIWTD Soci IBRD / P4830 Post Open - National 29,680.00 26,438.64 Signed 2019-01-01 2019-02-26 2019-05-29 2019-08-25 nd modernization tions nvelope ety Office at 3rd floor of Dire ctorate of Inland Water Trans port office building at Ulubari , Guwahati-7. IN-IWT-89264-GO-RFQ / Sup ply & installation of Air-condit ioning equipment & office fur Fleet safety improvements a Request for Quota Single Stage - One E IBRD / P4830 Post Open - National 48,585.00 37,799.53 Signed 2019-01-30 2019-03-27 2019-05-28 2019-09-23 niture for the PMU office of AI nd modernization tions nvelope WTD Society at 3rd floor of D irectorate of IWT office buildi ng at Ulubari,Guwahati-7 Page 2 IN-IWT-120889-GO-RFB / Su pply, Installation & Commissi Fleet safety improvements a Single Stage - Two E oning of 3 NOS. Shore Statio IBRD / P4830 Post Request for Bids Open - National 821,414.42 689,915.34 Signed 2019-06-28 2019-06-28 2019-07-03 2019-07-14 2019-08-14 2019-09-05 2019-10-27 2019-09-25 2019-12-01 2020-02-26 2020-05-29 nd modernization nvelope n based Search & Rescue cu m Surveillance Vessel. IN-IWT-120895-GO-RFB / Su pply, Installation & Commissi oning of unit approved Marin Fleet safety improvements a Open - Internationa Single Stage - One E e Engine, Type approved Rev IBRD / P4830 Prior Request for Bids 12,110,028.00 0.00 Canceled 2019-06-26 2019-07-01 2019-08-12 2019-09-11 2019-10-16 2020-04-13 nd modernization l nvelope ersible Gear Box and Propulsi on System with two years ext ended warranty for Marine E ngine & Reversible Gear Box IN-IWT-120896-GO-RFB / Su pply, Installation & Commissi Fleet safety improvements a Single Stage - One E oning of 4 nos. Marine Engin IBRD / P4830 Post Request for Bids Open - National 63,407.43 51,233.56 Signed 2019-06-26 2019-06-26 2019-07-01 2019-07-14 2019-08-12 2019-07-30 2019-09-11 2019-11-21 2019-10-16 2019-10-25 2020-04-13 nd modernization nvelope es for Repowering of existing 2 Vessels of IWT, Assam. IN-IWT-120898-GO-RFB / Su Fleet safety improvements a Single Stage - One E pply, Installation & Commissi IBRD / P4830 Post Request for Bids Open - National 86,464.68 56,409.06 Signed 2019-06-30 2019-06-26 2019-07-05 2019-07-14 2019-08-16 2019-09-05 2019-09-15 2019-11-06 2019-10-20 2020-03-04 2020-04-17 2021-08-30 nd modernization nvelope oning of 3 nos. Man over Boa rd Boat IN-IWT-121962-GO-RFB / Su pply, Installation & Commissi oning of unit approved Marin Fleet safety improvements a Single Stage - One E Under Imple e Engine, Type approved Rev IBRD / P4830 Prior Request for Bids Open - National 12,110,028.00 0.00 2019-07-12 2019-07-11 2019-07-15 2019-07-12 2019-08-26 2019-09-06 2019-09-25 2019-10-04 2019-10-30 2020-04-27 nd modernization nvelope mentation ersible Gear Box and Propulsi on System with two years ext ended warranty for Marine E ngine & Reversible Gear Box IN-IWT-126237-GO-RFQ / Su pply of office equipment viz- Laptops/notepad/pad, Deskto ps, Printers, LAN routers, DSL Institutional, regulatory and Request for Quota Single Stage - One E Pending Impl R Camera,LED TV,EPBX, Wat IBRD / P4830 Post Open - National 32,149.74 0.00 2019-08-21 2019-10-16 2020-04-13 safety strengthening tions nvelope ementation er Purifier, vacuum Cleaner, HHGPS etc. to the permanen t Project Management Unit(P MU) of AIWTD Society to be procured through GeM . IN-IWT-126061-GO-RFB / Su Institutional, regulatory and Single Stage - One E pply of Life Buoy & Life jacke IBRD / P4830 Post Request for Bids Open - National 1,971,071.00 1,058,403.02 Signed 2019-08-05 2019-08-31 2019-08-11 2019-08-31 2019-09-22 2019-09-20 2019-10-22 2019-11-06 2019-11-26 2020-03-06 2020-05-24 safety strengthening nvelope ts for river Vessels and Boat s IN-IWT-128486-GO-RFB / Su pply, Installation & Commissi oning of 180 KVA Diesel Gen Set for Permanent Project Ma Institutional, regulatory and Request for Quota Single Stage - One E IBRD / P4830 Post Open - National 25,168.50 20,379.59 Signed 2019-09-01 2019-10-27 2019-09-07 2020-04-24 nagement Unit (PMU) of Assa safety strengthening tions nvelope m Inland Transport Develop ment Society at 3rd Floor,Dir ector of Inland Water Transp ort,Assam,Ulubari,Guwahati- 781007 IN-IWT-135618-GO-RFQ / Su pply & Installation of Six no Project Management Suppor Request for Quota Single Stage - One E s Desktop Computers along IBRD / P4830 Post Open - National 3,374.82 3,202.99 Signed 2019-10-05 2019-11-30 2019-11-05 2020-05-28 t tions nvelope with Printer ,Scanner for DIW T office, Ulubari Guwahati-78 1007 IN-IWT-135745-GO-RFB / E-p rocurement of 3 nos 7.5T Bo Fleet safety improvements a Single Stage - One E IBRD / P4830 Post Request for Bids Open - National 2,745,970.50 2,106,831.00 Signed 2019-09-30 2019-10-01 2019-10-05 2019-10-01 2019-11-16 2019-10-31 2019-12-16 2019-12-20 2020-01-20 2020-02-26 2020-07-18 llard Pull capacity Tug Boats nd modernization nvelope to be operated in the rivers o f Assam IN-IWT-151371-GO-RFQ / Su pply,Installation & Commissi Project Management Suppor Request for Quota Single Stage - One E IBRD / P4830 Post Open - National 5,461.00 0.00 Completed 2019-12-28 2020-02-22 2020-08-20 2021-09-13 oning of IP based Tele-confer t tions nvelope encing system in PMU office of AIWTD Society IN-IWT-161179-GO-RFQ / Su pply,Installation & Commissi Fleet safety improvements a Request for Quota Single Stage - One E Under Imple oning of 24 nos Public Addres IBRD / P4830 Post Open - National 9,510.42 0.00 2020-03-04 2020-04-29 2020-10-26 nd modernization tions nvelope mentation s System(Indoor),PA Set alon g with other accessories for DIWT Vessels. IN-IWT-165211-GO-RFQ / Su pply,Installation & Commissi oning of IP based Finger Print Project Management Suppor Request for Quota Single Stage - One E IBRD / P4830 Post Open - National 337.00 242.94 Signed 2020-03-28 2020-05-23 2020-09-03 2020-11-19 Device for Bio-metric Attenda t tions nvelope nce in the office of the perma nent Project Management Un it of AIWTD Society. IN-IWT-199307-GO-RFQ / Pro curement of IT equipment(La p top,color printer,wireless M Project Management Suppor Request for Quota Single Stage - One E ouse & Keyboard combo,i pa IBRD / 90260 Post Open - National 6,570.40 0.00 Completed 2020-10-20 2020-12-15 2021-06-13 2021-07-17 t tions nvelope d pro 11,i Mac 3.6,Book Shelf ,Canon Telephoto Zoom lens AF, etc of each quantity and 4 layer steel rack through -2 nos ) IN-IWT-211737-GO-RFQ / Pro curement of IT related Equip Project Management Suppor Request for Quota Single Stage - One E Pending Impl ment (Laptop, Printer, High S IBRD / 90260 Post Open - National 8,943.09 0.00 2021-01-22 2021-04-23 2021-05-23 t tions nvelope ementation peed Scanner, Tripod for Ca mera ,Think Pad-E14,etc) IN-IWT-211739-GO-RFQ / Pro Institutional, regulatory and Request for Quota Single Stage - One E Pending Impl curement of Dry Powder Fire IBRD / 90260 Post Open - National 94,850.95 0.00 2021-02-15 2021-06-05 2021-07-20 safety strengthening tions nvelope ementation Extinguisher under Jibonding a Scheme IN-IWT-245189-GO-RFQ / Pro Project Management Suppor Request for Quota Single Stage - One E Pending Impl curement of IT equipment for IBRD / 90260 Post Open - National 4,940.00 0.00 2021-08-21 2021-10-16 2022-04-14 t tions nvelope ementation AIWTD Society IN-IWT-245194-GO-RFQ / Pro curement of AIS 140 GPS dev ices (GPS device , Cost of ins Fleet safety improvements a Request for Quota Single Stage - One E IBRD / 90260 Post Open - National 12,640.00 7,800.59 Signed 2021-08-28 2021-10-23 2022-05-05 2022-04-21 tallation on site & 3 years wa nd modernization tions nvelope rranty) , Software license fee and sim card with 4 G data p ackage for DIWT vessels/ boa ts. IN-IWT-253711-GO-RFQ / Pro Institutional, regulatory and curement of 1600 SOLAS co IBRD / 90260 Post Direct Selection Direct 2,400.00 0.00 Completed 2021-09-16 2021-09-16 2021-09-21 2021-09-17 2021-10-26 2021-11-25 safety strengthening mpliant Life Jackets Page 3 IN-IWT-253722-GO-DIR / Pro Institutional, regulatory and curement of 100 CO2 and 10 IBRD / 90260 Post Direct Selection Direct 15,227.00 0.00 Signed 2021-09-16 2021-09-16 2021-09-21 2021-09-17 2021-10-26 2021-11-25 safety strengthening 0 foam type Fire Extinguisher IN-IWT-253788-GO-RFQ / Pro Institutional, regulatory and Request for Quota Single Stage - One E curement of Walkie talkie set IBRD / 90260 Post Open - National 9,230.00 0.00 Completed 2021-09-29 2021-11-24 2022-11-24 2021-12-27 safety strengthening tions nvelope s along with accessories IN-IWT-266212-GO-RFQ / Pro curement of 5 Laptops, 1 Des Institutional, regulatory and Request for Quota Single Stage - One E Under Imple IBRD / P4830 Post Open - National 9,929.00 0.00 2021-12-12 2022-02-11 2022-03-28 ktop, 6 Printers & 1 wifi rout safety strengthening tions nvelope mentation er for Assam IWT Regulatory Authority IN-IWT-282270-GO-RFQ / Pro curement of Laptop, Desktop Project Management Suppor Request for Quota Single Stage - One E IBRD / 90260 Post Open - National 12,714.00 0.00 Signed 2022-03-15 2022-06-17 2022-09-15 High Speed Scanner, Multi Fu t tions nvelope nction Printer & Television IN-IWT-292175-GO-RFB / Pro curement of 418 Marine Engi Fleet safety improvements a Single Stage - Two E IBRD / P4830 Prior Request for Bids Open - National 5,736,947.00 0.00 Signed 2022-05-10 2022-05-11 2022-05-15 2022-05-12 2022-07-14 2022-07-04 2022-09-26 2022-09-07 2022-10-31 2023-05-19 2023-10-31 ne, Gear Box & Propulsion sy nd modernization nvelope stem under Jibondinga Sche me. IN-IWT-302550-GO-RFQ / Pro curement of one(01) Laptop, Project Management Suppor Request for Quota Single Stage - One E one(01) All-in-one Desktop , IBRD / 90260 Post Open - National 2,571.00 0.00 Signed 2022-07-14 2022-09-18 2023-03-17 t tions nvelope 03 (Three) Multi Function Pri nter for PMU and Chariman,G B, AIWTDS IN-IWT-325881-GO-RFQ / Pro curement of High Speed scan Fleet safety improvements a Request for Quota Single Stage - One E IBRD / 90260 Post Open - National 1,486.00 0.00 Completed 2022-11-19 2023-01-14 2023-02-13 2022-12-13 ner 2 Nos for Scheme Imple nd modernization tions nvelope mentation Agency (SIA) of Jib ondinga Scheme IN-IWT-325994-GO-RFQ / Pro curement of Hand held wirele Institutional, regulatory and Request for Quota Single Stage - One E Pending Impl ss communication devices an IBRD / 90260 Post Open - National 70,570.00 0.00 2022-11-27 2023-02-20 2023-08-19 safety strengthening tions nvelope ementation d vessels mounted fix station , base station and related ac cessories. IN-IWT-352927-GO-RFQ / Pro curement of Video Walls, UPS Institutional, regulatory and Request for Quota Single Stage - One E Pending Impl IBRD / 90260 Post Open - National 23,644.00 0.00 2023-04-18 2023-06-27 2023-07-27 and Camera with installation safety strengthening tions nvelope ementation inclusive of 2 years AMC NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWT-31284-NC-DIR / Interi or and Architectural design c Fleet safety improvements a onsultancy work for the per IBRD / P4830 Post Direct Selection Direct 11,700.00 11,788.18 Signed 2017-10-06 2017-10-10 2017-10-11 2017-11-15 2017-10-13 2018-05-14 nd modernization manent PMU office of Assam IWTD Society at DIWT Compl ex, Ulubari, Guwahati. IN-IWT-49587-NC-RFQ / Sele ction of Vendor for Design,De Institutional, regulatory and Request for Quota Single Stage - One E velopment,and Maintenance IBRD / P4830 Post Limited 7,800.00 11,941.54 Signed 2018-02-25 2018-02-20 2018-04-22 2018-03-07 2018-10-19 safety strengthening tions nvelope of website for Assam Inland Water Transport Developmen t Society IN-IWT-96333-NC-RFB / Sele ction for Architect for Upgrad Institutional, regulatory and Request for Quota Single Stage - One E IBRD / P4830 Post Open - National 4,221.00 3,483.19 Signed 2019-02-20 2019-04-17 2019-06-18 2019-10-14 ation & Refurbishment of exi safety strengthening tions nvelope sting Crew Training Centre, I WT, Guwahati. IN-IWT-96337-NC-RFB / Sele ction of Film maker firm for fi Institutional, regulatory and Request for Quota Single Stage - One E IBRD / P4830 Post Open - National 28,141.00 6,106.13 Signed 2019-02-24 2019-04-21 2020-10-07 2019-10-18 lming the Assam Inland Wate safety strengthening tions nvelope rways Transport- History, Tra nsition and its future. IN-IWT-96350-NC-RFB / Aeria Improvement in terminal infr Request for Quota Single Stage - One E l Drone survey of Assam Inla IBRD / P4830 Post Open - National 12,670.00 7,576.56 Completed 2019-02-20 2019-04-17 2019-07-28 2019-10-14 2020-09-13 astructure tions nvelope nd water transport Project IN-IWT-165504-NC-RFB / App ointment of Creative Multime dia Advertising Agency for Co ntent Development and Man Project Management Suppor Single Stage - One E agement of Communication IBRD / P4830 Post Request for Bids Open - National 70,500.00 23,762.02 Signed 2020-05-28 2020-05-30 2020-06-02 2020-05-30 2020-07-14 2020-07-28 2020-08-13 2020-09-01 2020-09-17 2020-11-06 2021-03-16 t nvelope Materials (Audio, Print and A udio-Visual Materials) for the Transport Department and In land Water Transport Depart ment, Government of Assam IN-IWT-188903-NC-RFQ / Hiri ng of services of Non Govern Fleet safety improvements a Request for Quota Single Stage - One E mental Organisation(NGO) f IBRD / 90260 Post Open - National 17,042.85 0.00 Canceled 2020-08-29 2020-08-21 2020-10-24 2021-04-22 nd modernization tions nvelope or assisting in implementati on of Jibondinga Scheme und er AIWT Project IN-IWT-188905-NC-RFB / Eng agement of Insurer for Insura nce of passengers (Personal Fleet safety improvements a Single Stage - One E accident policy), and damage IBRD / 90260 Post Request for Bids Open - National 1,161,962.51 0.00 Canceled 2020-08-27 2020-08-28 2020-09-01 2020-09-01 2020-10-13 2020-11-12 2020-12-17 2021-06-15 nd modernization nvelope /loss of wooden boat hull and Propulsion System and small cargo of passengers under Ji bondinga Scheme of AIWT Pr oject IN-IWT-256602-NC-RFB / Eng agement of Insurer for Insura Fleet safety improvements a Single Stage - Two E nce of passengers (Personal IBRD / 90260 Post Request for Bids Open - National 338,697.00 0.00 Canceled 2021-10-25 2021-10-30 2021-12-19 2022-04-13 2022-05-27 2025-05-26 nd modernization nvelope accident policy) travelling in boat/vessel under Jibondinga scheme IN-IWT-296731-NC-RFB / Bas eline and user satisfaction su Institutional, regulatory and Single Stage - One E IBRD / 90260 Post Request for Bids Open - National 99,503.13 0.00 Signed 2022-05-31 2022-05-31 2022-06-07 2022-06-15 2022-08-06 2022-07-12 2022-09-05 2022-08-18 2022-10-25 2025-10-24 rvey under Assam Inland Wat safety strengthening nvelope er Transport Project. Page 4 IN-IWT-325885-NC-RFQ / Sel ection of agency for Design, Institutional, regulatory and Request for Quota Single Stage - One E Development, Implementatio IBRD / 90260 Post Open - National 14,286.00 0.00 Signed 2022-11-30 2023-01-21 2023-02-04 2023-08-03 safety strengthening tions nvelope n, Training & Support of Grie vance Management System and Tracking System IN-IWT-329681-NC-DIR / Ann ual Maintenance Contract for recently procured 100 Pax 10 Fleet safety improvements a Under Imple IBRD / 90260 Post Direct Selection Direct - National 109,754.33 0.00 2022-12-06 2022-12-01 2022-12-27 2023-02-10 2025-02-09 Vessels after expiry of warra nd modernization mentation nty period. The AMC also incl udes cost of parts and consu mables during contract perio d. IN-IWT-341548-NC-RFQ / Arc hitectural Services for setting up of office of AIWT Regulat Institutional, regulatory and Request for Quota Single Stage - One E Under Imple IBRD / 90260 Post Open - National 17,500.00 0.00 2023-03-12 2023-04-03 2023-06-03 2024-06-02 ory Authority & temporary off safety strengthening tions nvelope mentation ice of AIW Company Ltd at DI WT's office building premises at Ulubari, Guwahati (Assam) . IN-IWT-346377-NC-RFQ / Arc hitectural Services and Prepa Institutional, regulatory and Request for Quota Single Stage - One E Under Imple ration of DPR for Crew Traini IBRD / 90260 Post Open - National 25,000.00 0.00 2023-03-15 2023-05-16 2023-05-27 2024-11-17 safety strengthening tions nvelope mentation ng Centre of IWT at Pandu(G uwahati) along with Project M anagement Services IN-IWT-364032-NC-RFB / Hiri ng of Communications Agenc y for providing comprehensiv e multimedia IEC/ BCC servic Project Management Suppor Single Stage - One E Pending Impl IBRD / 90260 Post Request for Bids Open - National 35,875.00 0.00 2023-06-12 2023-06-12 2023-07-24 2023-08-08 2023-08-30 2024-08-29 es including social media and t nvelope ementation outreach activities for the Inl and Water Transport Develop ment Society for Assam IWT Project. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWT-43725-CS-CQS / Sele ction of Consultancy Services to conduct feasibility study fo Institutional, regulatory and Consultant Qualifi IBRD / P4830 Post Limited 23,580.00 0.00 Canceled 2018-01-17 2018-01-20 2018-01-31 2018-05-05 2018-03-02 2018-04-06 2018-10-03 r installing Night Navigation safety strengthening cation Selection Facilities to assist in Night Na vigation of Ferry Services on River Brahmaputra IN-IWT-47344-CS-QCBS / RE QUEST FOR EXPRESSION OF I NTEREST FOR CONSULTANCY SERVICES FOR PREPARATION OF DETAILED Institutional, regulatory and Quality And Cost- Open - Internationa IBRD / P4830 Post 468,000.00 326,101.05 Signed 2018-02-04 2018-02-08 2018-02-25 2018-02-09 2018-04-10 2018-04-03 2018-05-08 2018-05-17 2018-06-07 2018-06-12 2018-07-12 2018-07-16 2018-08-16 2018-10-22 2019-08-16 PROJECT REPORT (DPR) ALO safety strengthening Based Selection l NG WITH FRONT END ENGINE ERING DESIGN, DRAWINGS, T ENDER DOCUMENTS AND MO DULARIZATION OF DESIGN E LEMENTS FOR DEVELOPMEN T OF FERRY SERVICES IN AS MIN-IWT-47925-CS-QCBS / Hiri ng of Safeguard Consultant f Institutional, regulatory and Quality And Cost- Open - Internationa or Environmental & Social As IBRD / P4830 Post 125,000.00 285,070.30 Signed 2018-02-08 2018-02-16 2018-03-01 2018-03-09 2018-04-14 2018-04-12 2018-05-12 2018-05-14 2018-06-11 2018-05-25 2018-07-16 2018-06-01 2018-08-20 2018-06-06 2019-08-20 safety strengthening Based Selection l sessment Studies of Assam I nland Water Transport Projec t (AIWTP) IN-IWT-85281-CS-QCBS / Re quest for Expression of Intere st for Appointment of Naval A rchitect Firm for providing co Institutional, regulatory and Quality And Cost- Open - Internationa IBRD / P4830 Post 107,217.99 0.00 Canceled 2018-11-01 2018-11-01 2018-11-22 2019-01-05 2019-02-02 2019-03-04 2019-04-08 2019-05-13 2020-05-12 nsulting services regarding d safety strengthening Based Selection l esign,monitoring and supervi sion of procurement and com missioning of passenger vess els for AIWT Project IN-IWT-89165-CS-QCBS / Re quest for expression of Intere st for appointment of Naval A Institutional, regulatory and Quality And Cost- Open - Internationa IBRD / P4830 Post 201,654.00 0.00 Canceled 2018-12-07 2018-12-31 2018-12-28 2019-01-03 2019-02-10 2019-03-10 2019-04-09 2019-05-14 2019-06-18 2020-06-17 rchitectural and Marine engin safety strengthening Based Selection l eering firm for providing cons ulting services for Assam IWT project IN-IWT-100268-CS-CQS / Re quest for Expression of Intere st for engagement of Charter Institutional, regulatory and Consultant Qualifi IBRD / P4830 Post Limited 2,890.00 3,567.81 Signed 2019-02-13 2019-03-06 2019-02-27 2019-07-16 2019-03-29 2019-09-11 2019-05-03 2019-09-28 2019-10-30 ed Accountant Firm as Statut safety strengthening cation Selection ory Auditor of AIWTD Society for Financial year 2017-18 & 2018-19 IN-IWT-126634-CS-QCBS / S election of Technical Services and Supervision Consultant fi Improvement in terminal infr Quality And Cost- Open - Internationa IBRD / P4830 Prior 3,661,752.00 0.00 Canceled 2019-08-13 2019-08-25 2019-10-10 2019-11-07 2019-11-28 2019-12-27 2020-01-23 2022-01-22 rm for construction of 03(thr astructure Based Selection l ee) Terminals at Aphalamukh (Majuli), South and North Gu wahati IN-IWT-136208-CS-QCBS / C onsultancy Services for indep Project Management Suppor Quality And Cost- endent verification agency fo IBRD / P4830 Post Open - National 297,199.54 79,809.88 Signed 2019-09-30 2019-10-01 2019-10-21 2019-10-03 2019-12-04 2019-10-01 2020-01-01 2019-11-05 2020-01-31 2020-02-29 2020-03-06 2019-11-05 2020-04-10 2020-09-16 2021-04-10 t Based Selection r verification of Disbursemen t Linked Indicator(DLI) for AI WTD Project IN-IWT-198812-CS-FBS / Req uest for Proposals for Engagi Project Management Suppor Fixed Budget Sele ng chartered accounting firm IBRD / 90260 Post Open - National 8,114.28 7,895.92 Signed 2020-10-11 2020-10-12 2020-11-01 2020-12-15 2020-11-17 2021-01-12 2020-12-28 2021-02-11 2021-02-06 2021-03-18 2021-05-11 2021-04-22 2021-08-11 2022-04-22 t ction for Internal Audit of AIWTDS f or FY 2020-21 & 2021-22 IN-IWT-201063-CS-QCBS / A ppointment of Technical Serv ices and Supervision Consult Improvement in terminal infr Quality And Cost- Open - Internationa ant(TSSC) firm for providing IBRD / 90260 Post 1,302,644.39 0.00 Canceled 2020-10-29 2020-11-11 2020-11-19 2020-11-18 2021-01-13 2021-02-27 2021-05-13 2021-06-17 2021-08-06 2022-08-06 astructure Based Selection l consulting services for Constr uction of Terminal and riverin e infrastructure at Aphalamu kh,Assam Page 5 IN-IWT-211691-CS-QCBS / A Project Management Suppor Quality And Cost- IBRD / 90260 Post Open - National 20,325.20 0.00 Canceled 2021-01-03 2021-01-10 2021-01-12 2021-03-03 2021-04-17 2021-06-06 2021-07-31 2022-07-31 ppointment of Law Firm for A t Based Selection IWT Project IN-IWT-211735-CS-FBS / Hiri Project Management Suppor Fixed Budget Sele ng of Statuatory Auditor Firm IBRD / 90260 Post Open - National 3,252.03 0.00 Canceled 2021-01-25 2021-02-26 2021-02-01 2021-03-01 2021-02-03 2021-02-26 2021-03-25 2021-04-19 2021-05-09 2021-10-16 2021-06-28 2021-08-21 2023-08-21 t ction for the FY 2020-21 & 2021-2 022 IN-IWT-221779-CS-QCBS / Pr eparation of Design DPR for Improvement in terminal infr Quality And Cost- IBRD / 90260 Post Open - National 469,195.42 0.00 Signed 2021-03-01 2021-02-25 2021-03-03 2021-03-01 2021-05-07 2021-05-29 2021-06-21 2021-06-30 2021-07-31 2021-07-20 2021-09-13 2021-08-17 2021-10-27 2022-07-29 Construction of Modular Ter astructure Based Selection minals at NW-2 & NW-6. IN-IWT-236184-CS-QCBS / A ppointment of Technical Ser Improvement in terminal infr Quality And Cost- Under Implement IBRD / 90260 Post Open - National 737,946.49 0.00 2021-06-07 2021-07-14 2021-06-07 2021-07-26 2021-06-21 2021-07-22 2021-08-10 2021-08-26 2021-09-24 2021-09-24 2021-11-10 2021-10-30 2022-01-02 2024-07-04 vice and Supervision Consult astructure Based Selection ation ant for Guwahati Gateway Gh at IN-IWT-242294-CS-QCBS / Hi ring of Safeguards Consultan Project Management Suppor Quality And Cost- Under Implement t for Environmental and Soci IBRD / 90260 Post Open - National 265,387.00 0.00 2021-07-15 2021-07-22 2021-07-15 2021-07-28 2021-07-15 2021-07-28 2021-09-03 2021-09-02 2021-10-13 2021-10-26 2021-12-07 2022-01-17 2022-01-11 2022-10-08 t Based Selection ation al Assessment Studies for As sam Inland Water Transport Project, Phase-II IN-IWT-249475-CS-QCBS / Hi ring of Safeguard Monitoring Improvement in terminal infr Quality And Cost- Consultant (3rd Party Monitor IBRD / 90260 Post Open - National 29,079.00 0.00 Signed 2021-08-31 2021-08-17 2021-08-31 2021-08-31 2021-09-30 2021-10-15 2021-11-24 2021-11-14 2022-05-21 2021-12-09 2022-06-01 2022-01-17 2024-07-17 astructure Based Selection ing) at proposed developmen t of terminal at Guwahati Gat eway Ghat IN-IWT-272430-CS-QCBS / S election of General Consultan Project Management Suppor Quality And Cost- IBRD / 90260 Post Open - National 722,839.00 529,441.61 Signed 2022-01-18 2022-01-10 2022-01-19 2022-02-09 2022-01-30 2022-03-24 2022-03-01 2022-05-06 2022-03-31 2022-06-09 2022-04-15 2022-07-06 2022-05-20 2022-07-27 2024-12-31 t for Assam Inland Water Tra t Based Selection nsport Development Society (AIWTDS) IN-IWT-341536-CS-QCBS / A ppointment of Technical Serv Improvement in terminal infr Quality And Cost- Under Implement ice and Supervision Consulta IBRD / 90260 Post Open - National 655,140.63 0.00 2023-02-16 2023-04-05 2023-02-16 2023-02-28 2023-03-30 2023-04-19 2023-05-20 2023-06-10 2024-12-31 astructure Based Selection ation nt (TSSC) for 4 terminals - No rth Guwahati, Umananda, Ne amati & Aphalamukh IN-IWT-343755-CS-QCBS / Hi ring of Third Party Monitoring Improvement in terminal infr Quality And Cost- Under Implement (TPM) Consultant for 4 Small IBRD / 90260 Post Open - National 113,899.50 0.00 2023-02-23 2023-04-04 2023-02-23 2023-03-04 2023-04-01 2023-04-21 2023-05-23 2023-06-27 2025-12-13 astructure Based Selection ation er Terminals at North Guwah ati, Umananda, Neamati and Aphalamukh IN-IWT-361678-CS-QCBS / Hi ring of Consultancy firm for I Institutional, regulatory and Quality And Cost- Under Implement IBRD / 90260 Post Open - National 187,500.00 0.00 2023-05-16 2023-06-28 2023-05-16 2023-05-20 2023-06-12 2023-07-12 2023-08-17 2023-09-21 2024-03-19 ntegrated Water Transport St safety strengthening Based Selection ation rategy for Assam Inland Wat er Transport Sector TWT/GC/CS/QCBS/20106/01 / Selection of General Consul Fleet safety improvements a Quality And Cost- Open - Internationa IBRD / P4830 Prior 1,300,000.00 845,569.11 Signed 2016-11-28 2016-12-01 2016-12-23 2017-01-14 2017-04-20 2017-02-11 2017-06-30 2017-03-13 2017-07-31 2017-04-17 2017-09-21 2017-05-22 2017-09-20 2021-05-21 tant for the Assam Inland wat nd modernization Based Selection l er Transport Development So ciety TIWT/CS/QCBS/2016/2 / Sele Institutional, regulatory and Quality And Cost- ction of Consultant for Institu IBRD / P4830 Post Open - National 600,000.00 482,150.26 Signed 2017-02-28 2017-07-27 2017-03-21 2017-08-29 2017-05-04 2017-12-14 2017-06-01 2018-04-21 2017-07-01 2018-04-21 2017-08-05 2018-05-07 2017-09-09 2018-05-18 2018-09-09 safety strengthening Based Selection tionL Strengthing and Busine ss Planning TWT/CS/QCBS/20106/03 / Se lection of Consultant for Inte Institutional, regulatory and Quality And Cost- Open - Internationa IBRD / P4830 Post 800,000.00 751,990.00 Signed 2017-03-15 2017-05-10 2017-04-05 2017-06-30 2017-05-19 2017-12-06 2017-06-16 2018-02-15 2017-07-16 2018-02-15 2017-08-20 2018-03-17 2017-09-24 2018-03-26 2018-09-24 grated Strategic Developmen safety strengthening Based Selection l t Plan for Assam IWT INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-IWT-96378-CS-CDS / Enga gement of IRS for providing t echnical support services for Fleet safety improvements a IBRD / P4830 Post Direct Selection Direct 179,624.00 185,908.99 Signed 2019-02-08 2019-03-05 2019-02-18 2018-11-16 2019-04-24 2019-03-07 2019-10-21 procurement of new vessels nd modernization & repair, retrofitting and certi fication of existing vessels fo r Inland Water Transport Ass am. IN-IWT-135509-CS-CDS / Sel ection of Consultant for " Ass essment and Implementation Fleet safety improvements a IBRD / P4830 Post Direct Selection Direct 112,676.00 0.00 Canceled 2019-09-30 2019-10-10 2019-12-14 2020-06-11 of Night Navigation System f nd modernization or cross River Ferry Service o n river Brahmaputra under AI WT Project" IN-IWT-151456-CS-CDS / Sel ection of Consultant for "Ass essment and Implementation Fleet safety improvements a IBRD / P4830 Post Direct Selection Direct 458,410.56 449,884.89 Signed 2019-12-23 2019-12-30 2020-01-02 2020-01-03 2020-03-07 2020-11-03 2020-09-03 of Night Navigation System f nd modernization or cross River Ferry Service o n river Brahmaputra under AI WT Project" IN-IWT-165523-CS-CDS / De velopment of the technical, o Fleet safety improvements a rganizational and functional IBRD / P4830 Post Direct Selection Direct 7,200.00 6,845.57 Signed 2020-03-24 2020-03-27 2020-04-03 2020-07-16 2020-06-07 2021-02-26 2020-08-15 nd modernization architecture for river informa tion services on river Brahma putra under AIWT Project IN-IWT-263886-CS-CDS / Hiri Project Management Suppor ng of Statutory Auditor Firm f IBRD / P4830 Post Direct Selection Direct 1,543.00 0.00 Signed 2021-11-20 2021-11-18 2021-11-22 2021-11-20 2021-12-02 2022-05-31 t or the FY 2020-21 & 2021-20 22 IN-IWT-304347-CS-INDV / Hir ing of Individual Consultants Project Management Suppor for preparation of asset & inv IBRD / 90260 Post Direct Selection Direct - National 11,429.00 0.00 Signed 2022-08-18 2022-08-24 2022-08-28 2022-09-21 2022-11-01 2023-04-30 t entory management guidelin es/manual and Operation Ma nual of Assets IN-IWT-329195-CS-INDV / Hir ing of Individual Consultant- Institutional, regulatory and Individual Consult Under Implement IBRD / 90260 Post Open - National 17,627.62 0.00 2022-12-01 2022-12-01 2023-01-12 2023-02-02 2023-03-09 2024-03-08 Economic Regulation Expert f safety strengthening ant Selection ation or Assam IWT Regulatory Aut hority Page 6 IN-IWT-329202-CS-INDV / Hir ing of Individual Consultant - Institutional, regulatory and Individual Consult IBRD / 90260 Post Open - National 17,627.62 0.00 Canceled 2022-12-05 2022-12-01 2023-01-16 2023-02-06 2023-03-13 2024-03-12 Environmental Expert for Ass safety strengthening ant Selection am IWT Regulatory Authority IN-IWT-329201-CS-INDV / Hir ing of Individual consultant- Institutional, regulatory and Individual Consult IBRD / 90260 Post Open - National 17,627.62 0.00 Canceled 2022-12-03 2022-12-01 2023-01-14 2023-02-04 2023-03-11 2024-03-10 Safety Expert for Assam IWT safety strengthening ant Selection Regulatory Authority Page 7 Procurement Plan I. General 2. Bank’s approval Date of the procurement Plan: March 17, 2017 3. Date of General Procurement Notice: February 14, 2017 4. Period covered by this procurement plan: March 2017 to Feb 2018 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 10 Substantial installation of plant and equipment and PPP) 2. (Goods; Information Technology & 2 Substantial Non-Consulting Services) 3. Consultant Services (Firms) 1 Substantial 4. Consultant Services (Individual 0.3 Substantial Consultants) 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. March 17, 2017 9. Renewal or extension of individual consultants contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. March 17, 2017 PROCUREMENT Eastern and Southern Africa : Horn of Africa Gateway Development Project PLAN General Information Country: Eastern and Southern Africa 2020-11-25 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161305 GPN Date: 2017-02-14 Project Name: Horn of Africa Gateway Development Project Loan / Credit No: IDA / 67680 State Department of Infrastructure Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned KE-SDOI-213607-CW-RFB / R oads Division: Refurbishment of Northern Corridor Boardro Component D: Institutional S Request for Bids - om into a smart training/conf trengthening of Selected Tra Single Stage - One E Small Works SPD 2022-02-2 IDA / 67680 Post Request for Bids Open - National 400,000.00 345,852.15 Signed 2021-05-04 2021-07-27 2021-05-09 2021-08-16 2021-06-20 2021-08-26 2021-07-20 2021-10-13 2021-08-24 2022-01-19 erence room, refurbishment nsport and Related Institutio nvelope (1 envelope proce 0 of the boardroom office into ns ss) a server room, supply & insta llation of furniture and ICT eq uipment in the server room & training room. KE-SDOI-220233-CW-RFB / K Component D: Institutional S IHBT: Construction of Smart trengthening of Selected Tra Single Stage - One E Pending Imp 2023-10-2 IDA / 67680 Post Request for Bids Open - National 1,200,000.00 0.00 2021-07-01 2021-07-06 2021-08-17 2021-09-16 2021-10-21 Classrooms Block at KIHBT N nsport and Related Institutio nvelope lementation 1 airobi Industrial Area, Enterpr ns ise Road. KE-SDOI-225944-GO-RFB / KI Component D: Institutional S Request for Bids - HBT: Supply and Installation trengthening of Selected Tra Single Stage - One E Small Works SPD Under Imple 2024-02-1 of fibre/Local Area Network i IDA / 67680 Post Request for Bids Open - National 180,000.00 0.00 2023-05-03 2021-04-27 2023-05-08 2023-06-19 2023-07-19 2023-08-23 nsport and Related Institutio nvelope (1 envelope proce mentation 9 nterconnecting five compoun ns ss) ds at KIHBT Nairobi Industria l Area Offices. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-SDOI-210289-GO-RFQ / S Component D: Institutional S Request for Quota Single Stage - One E upply of 3 No. Digital Camera IDA / 67680 trengthening of Selected Tra Post Open - National 13,840.00 0.00 Canceled 2021-02-07 2021-03-01 2021-03-10 tions nvelope s nsport and Related Institutio ns KE-SDPW-197451-GO-RFB / The Procurement plan has tw o packages; Component A: Improving Mo 1. Design, supply, and install Single Stage - One E IDA / 67680 vement of People, Goods, an Prior Request for Bids Open - National 2,619,550.00 0.00 Canceled 2020-12-14 2020-12-19 2021-01-30 2021-03-01 2021-04-05 2021-10-02 ation of IT hardware (LAN) to nvelope d Digital Connectivity enhance existing system 2. Purchase of AUTODESK Sof tware, installation, testing, a nd commissioning KE-SDPW-220638-GO-RFB / Component D: Institutional S Supply, Installation & Commi trengthening of Selected Tra Single Stage - One E Under Imple IDA / 67680 Post Request for Bids Open - National 155,000.00 0.00 2021-03-08 2021-04-26 2021-03-13 2021-04-24 2021-05-24 2021-06-28 2021-12-25 ssioning of a new integrated nsport and Related Institutio nvelope mentation 60TB Network Storage Devic ns e KE-SDPW-216469-GO-RFB / Purchase of AUTODESK Softw are, installation, testing, and Component D: Institutional S commissioning trengthening of Selected Tra Single Stage - One E Lot 1. - BIM 360 Project Mana IDA / 67680 Post Request for Bids Open - National 2,283,700.00 0.00 Canceled 2021-03-08 2021-04-27 2021-03-13 2021-04-24 2021-05-24 2021-06-28 2021-12-25 nsport and Related Institutio nvelope gement System - BIM 360 (D ns esign, Build & Cost - 500, 10 0 & 50 Licenses respectively) Lot 2. - 100No. Revit AEC Coll ection Subscription Licenses KE-SDOI-210268-GO-RFB / R oads Division: Supply and del Component D: Institutional S ivery of: trengthening of Selected Tra Single Stage - One E 4 No. idrims international rou IDA / 67680 Post Request for Bids Open - National 210,000.00 175,880.39 Signed 2021-04-21 2021-09-02 2021-04-26 2021-08-16 2021-06-07 2021-08-26 2021-07-07 2021-10-04 2021-08-11 2022-01-19 2022-02-07 nsport and Related Institutio nvelope ghness index (IRI) measuring ns software - smartphone based dynamic response intelligenc e monitoring system (iDRIMS ) (3 year license) KE-SDOI-220201-GO-RFB / M Component D: Institutional S TRD: Supply & delivery of 5 N trengthening of Selected Tra Single Stage - One E Under Imple IDA / 67680 Post Request for Bids Open - National 250,000.00 0.00 2021-04-06 2021-10-12 2021-04-11 2021-10-12 2021-05-23 2021-11-10 2021-06-22 2021-11-26 2021-07-27 2022-01-23 o.: Double Cab Pick up Vehicl nsport and Related Institutio nvelope mentation es for Regional Materials Lab ns oratories KE-SDOI-221364-GO-RFQ / R oads Division: Design, supply , and installation of: (i) LAN Cabling and restructu Component D: Institutional S ring of data ports trengthening of Selected Tra Request for Quota Single Stage - One E Under Imple IDA / 67680 Post Open - National 50,000.00 0.00 2021-05-04 2021-10-12 2021-06-29 2021-07-08 (ii) Server room cooling syste nsport and Related Institutio tions nvelope mentation m ns (iii) 6No.WIFI access points (iv) 1No.Windows Server OS 2019 (v) 8 No. Server Harddrives (vi) 4 No.UPS KE-SDOI-225937-GO-RFB / KI HBT: Supply, installation and commissioning of the followi Component D: Institutional S ng software at KIHBT Nairobi trengthening of Selected Tra Single Stage - One E Pending Impl IDA / 67680 Post Request for Bids Open - National 100,000.00 0.00 2023-10-04 2023-10-09 2023-11-20 2023-12-20 2024-01-24 2024-03-24 Industrial Area Offices. nsport and Related Institutio nvelope ementation (a). Institute ns Management System (IMS) (b). Learning Management S ystem (LMS) KE-SDOI-225939-GO-RFQ / K Component D: Institutional S Request for Quota Single Stage - One E Under Imple IHBT: Supply of 40no. laptop IDA / 67680 trengthening of Selected Tra Post Open - National 60,000.00 0.00 2021-04-12 2022-01-18 2021-06-07 2021-07-07 tions nvelope mentation s at KIHBT Nairobi Industrial nsport and Related Institutio Area. ns Page 1 KE-SDPW-220632-GO-RFB / Supply, Installation and Testi ng of various ICT Hardware w Component D: Institutional S hich include 405 No. 1KVAUP trengthening of Selected Tra Single Stage - One E IDA / 67680 Post Request for Bids Open - National 180,850.00 0.00 Canceled 2021-03-08 2021-05-06 2021-03-13 2021-05-17 2021-04-24 2021-06-08 2021-05-24 2021-06-28 2021-12-25 S, 10No. Tablet Computer A, nsport and Related Institutio nvelope 16No Tablet Computer B, 5N ns o. Laptop type A, 60No. Lapt op type B, 2No. Multifunction al Copier/Printer & Scanner KE-SDOI-220235-GO-RFB / KI HBT: Supply, install and com missioning of required ICT Eq Component D: Institutional S uipment and software’s, Furn trengthening of Selected Tra Single Stage - One E Pending Impl IDA / 67680 Post Request for Bids Open - National 765,000.00 0.00 2021-06-01 2021-06-06 2021-07-18 2021-08-17 2021-09-21 2022-03-20 iture and Smart Classrooms P nsport and Related Institutio nvelope ementation resentation Workstations at ns KIHBT Nairobi Enterprise Roa d, as per specifications in the bidding document. KE-SDOI-219235-GO-RFB / M TD: Supply and Delivery of C onstruction Equipment Component D: Institutional S Lot 1. Earth Moving Equipm trengthening of Selected Tra Open - Internationa Single Stage - One E Under Imple ent (11 No.) IDA / 67680 Prior Request for Bids 2,740,000.00 0.00 2021-05-05 2023-03-28 2021-05-10 2021-06-21 2021-07-21 2021-08-25 2022-02-21 nsport and Related Institutio l nvelope mentation Lot 2. Road Construction V ns ehicles (4 No.) Lot 3. Mobile Workshop/Ser vices Trucks (1No.) KE-SDOI-221363-GO-RFB / M TD: SUPPLY AND DELIVERY O F ICT EQUIPMENT AND INSTA LLATION OF ERP PROJECT Lot 1. Uninterrupted Power S Component D: Institutional S upply (94 No.) trengthening of Selected Tra Single Stage - One E IDA / 67680 Post Request for Bids Open - National 500,960.00 0.00 Canceled 2021-05-12 2021-05-17 2021-06-28 2021-07-28 2021-09-01 2022-02-28 Lot 2. Computers (108 No.) nsport and Related Institutio nvelope Lot 3. Printers and Scanners ( ns 72No.) Lot 4. Enterprise Resource Pl anning (ERP)System and Offi ce365 Software KE-SDOI-220325-CW-RFP / KI Component D: Institutional S HBT: Supply, installation and trengthening of Selected Tra Request for Quota Single Stage - One E Pending Impl IDA / 67680 Post Open - National 40,000.00 0.00 2023-10-09 2023-11-27 2023-12-18 commissioning of CCTV Syste nsport and Related Institutio tions nvelope ementation m at KIHBT Nairobi Industrial ns Area Offices. KE-SDPW-231746-GO-RFB / Purchase of AUTODESK Softw are, installation, testing, and Component D: Institutional S commissioning Lot 1. - BIM 3 trengthening of Selected Tra Single Stage - One E Under Imple 60 Project Management Syst IDA / 67680 Prior Request for Bids Open - National 2,283,700.00 0.00 2021-04-29 2022-12-01 2021-05-04 2023-01-16 2021-06-15 2023-02-24 2021-07-15 2023-05-08 2021-08-19 2022-02-15 nsport and Related Institutio nvelope mentation em - BIM 360 (Design, Build ns & Cost - 500, 100 & 50 Licen ses respectively) Lot 2. - 100 No. Revit AEC Collection Sub scription Licenses KE-SDOI-232222-GO-RFQ / R Component D: Institutional S Request for Quota Single Stage - One E Under Imple oads Division: Supply and De IDA / 67680 trengthening of Selected Tra Post Limited 13,840.00 0.00 2021-06-06 2021-07-22 2021-08-01 2021-09-30 tions nvelope mentation livery of 3 No. Digital Camera nsport and Related Institutio s ns KE-SDOI-219889-GO-RFQ / S DoI Roads Division: Supply a nd Delivery of LOT 1. i) 8 No.-Type A Laptops Component D: Institutional S ii)22 No. - Type B laptops trengthening of Selected Tra Single Stage - One E Under Imple IDA / 67680 Post Request for Bids Open - National 200,000.00 0.00 2021-06-02 2021-07-27 2021-06-07 2021-08-16 2021-07-08 2021-08-27 2021-08-07 2021-09-10 2021-10-01 LOT 2. nsport and Related Institutio nvelope mentation i) 5-No. Type A Executive TA ns BLET ii)10No.Type B TABLET LOT 3. i) 5-No.Heavy Duty Photocop ier ii) 3-No. Laserjet printer Dupl KE-SDOI-220194-GO-RFB / M ex TRD: Design, Supply, Installa tion and Commissioning of In Component D: Institutional S tegrated Information System: trengthening of Selected Tra Single Stage - One E Under Imple Lot 1: Client Server System ( IDA / 67680 Post Request for Bids Open - National 1,000,000.00 0.00 2021-05-05 2021-10-12 2021-05-10 2021-10-12 2021-06-21 2021-11-10 2021-07-21 2021-12-17 2021-08-25 2022-02-21 nsport and Related Institutio nvelope mentation CSS); Lot 2: Library Informati ns on Management System (LIM S); Lot 3:Laboratory Manage ment System (LMS);Lot 4: Pa vement Management System (PMS) KE-NCA-189981-GO-RFP / Su Component D: Institutional S pply, installation, testing and trengthening of Selected Tra Single Stage - One E Pending Impl commissioning of the Constr IDA / 67680 Post Request for Bids Open - National 2,000,000.00 0.00 2021-10-01 2021-10-06 2021-11-17 2021-12-17 2022-01-21 2022-07-20 nsport and Related Institutio nvelope ementation uction Information System fo ns r the National Construction A uthority KE-NCA-190452-GO-RFB / Lo t I: Supply, installation, testin g and commissioning of an El Component D: Institutional S ectronic Document Managem trengthening of Selected Tra Single Stage - One E Pending Impl ent System (EDMS) for Natio IDA / 67680 Post Request for Bids Open - National 500,000.00 0.00 2021-09-01 2021-09-06 2021-10-18 2021-11-17 2021-12-22 2022-06-20 nsport and Related Institutio nvelope ementation nal Construction Authority ns Lot II: Upgrade and enhance ment of the Entreprise Resou rce Planning for NCA KE-SDOI-247326-GO-RFQ / S UPPLY AND DELIVERY OF OFF ICE EQUIPMENT FOR JOINT TE CHNICAL COMMITTEE SECRE Component D: Institutional S TARIAT trengthening of Selected Tra Request for Quota Single Stage - One E Under Imple IDA / 67680 Post Limited 24,000.00 0.00 2021-09-03 2021-09-27 2021-10-29 2022-04-27 (i) 8 No. TYPE A LAPTOP nsport and Related Institutio tions nvelope mentation (ii) 1 No. HEAVY DUTY PHOTO ns COPIER/PRINTER/SCANNER (iii) 1 No. LCD PROJECTOR (iv) 8 No. 3TB EXTERNAL HAR D DISK Page 2 KE-SDOI-220185-GO-RFB / S upply of 1 Gyratory & Marshall Compa ctors 2 Proctor Compactors & Multi Component D: Institutional S speed Testers trengthening of Selected Tra Open - Internationa Single Stage - One E Under Imple 3 Carbon Sulphur Analyzer & IDA / 67680 Post Request for Bids 2,700,000.00 0.00 2021-09-07 2021-10-12 2021-09-12 2021-10-12 2021-10-24 2021-11-24 2021-11-23 2021-12-16 2021-12-28 2022-06-26 nsport and Related Institutio l nvelope mentation Rebar Tester ns 4 Drilling Rig & Geophysical Equipment 5 Surface Profiler & Friction e quipment 6 Falling weight Deflectomet er & Axle load scales KE-SDOI-264184-GO-RFB / R Component D: Institutional S OADS: SUPPLY AND DELIVER trengthening of Selected Tra Single Stage - One E Pending Impl Y OF DESKTOP COMPUTERS 4 IDA / 67680 Post Request for Bids Open - National 106,600.00 0.00 2021-11-26 2021-12-01 2022-01-12 2022-02-11 2022-03-18 2022-09-14 nsport and Related Institutio nvelope ementation 0No. AND UNINTERRUPTIBLE ns POWER SUPPLY (UPS) 40No. TO ROADS DIVISION KE-SDOI-264212-GO-RFB / M Component D: Institutional S Single Stage - One E Under Imple TD: Design, Supply, Installati IDA / 67680 trengthening of Selected Tra Post Request for Bids Open - National 153,000.00 0.00 2021-11-28 2023-01-12 2021-12-03 2023-01-12 2022-01-14 2022-02-13 2022-03-20 2022-09-16 nvelope mentation on & Commissioning of ERP P nsport and Related Institutio roject ns KE-SDOI-264219-GO-RFB / M Component D: Institutional S Single Stage - One E Under Imple TD: Supply, Installation & Co IDA / 67680 trengthening of Selected Tra Post Request for Bids Open - National 90,000.00 0.00 2021-11-28 2023-01-12 2021-12-03 2023-01-12 2022-01-14 2022-02-13 2022-03-20 2022-09-16 nvelope mentation mmissioning of Office 365 Or nsport and Related Institutio "Equivalent" ns KE-SDOI-254757-GO-RFQ / R oads Division: Supply and De Component D: Institutional S livery of: trengthening of Selected Tra Request for Quota Single Stage - One E Pending Impl IDA / 67680 Post Limited 50,000.00 0.00 2021-09-28 2021-11-06 2022-01-05 i) Portable Document Files (P nsport and Related Institutio tions nvelope ementation DF) Management Software (3 ns 0 licenses) ii) Server Corporate antivirus with 100 end user licenses KE-SDOI-276521-GO-RFB / E Component D: Institutional S BK: Supply, Installation, Testi trengthening of Selected Tra Single Stage - One E Pending Impl IDA / 67680 Post Request for Bids Open - National 120,000.00 0.00 2022-02-11 2022-02-16 2022-03-30 2022-04-29 2022-06-03 2022-11-30 ng and Commissioning of Clo nsport and Related Institutio nvelope ementation ud Services for EBK ns KE-SDOI-276536-GO-RFB / R OADS DIVISION: SUPPLY AND Component D: Institutional S DELIVERY OF DISASTER MAN trengthening of Selected Tra Single Stage - One E Under Imple AGEMENT ITEMS (i) 2000 No. IDA / 67680 Post Request for Bids Open - National 300,000.00 0.00 2022-02-06 2022-11-08 2022-02-11 2022-11-08 2022-03-25 2022-04-24 2022-05-29 2022-11-25 nsport and Related Institutio nvelope mentation Gabion boxes (ii) 600 No. Cor ns rugated iron culverts (1.2m) ( iii) 800 No. Corrugated iron c ulverts (900mm) KE-SDOI-290326-GO-RFB / S DPW: SUPPLY INSTALLATION AND TESTING OF IT HARDWA RE Component D: Institutional S Lot 1 a) Tablet Computer Typ trengthening of Selected Tra Single Stage - One E Under Imple e A 5No. (b) Tablet computer IDA / 67680 Post Request for Bids Open - National 173,325.00 0.00 2022-05-31 2023-04-04 2022-06-05 2023-04-04 2022-07-17 2022-08-16 2022-09-20 2023-03-19 nsport and Related Institutio nvelope mentation Type B 8No. ns Lot 2 a) Laptop computer Ty pe A 3No. (b) Laptop comput er Type B 20No. Lot 3 Multifunctional Copier 1 No. Lot 4 1KVA UPS 100No. KE-SDOI-265672-GO-RFB / K Component D: Institutional S eRRA: Supply and Delivery of trengthening of Selected Tra Single Stage - One E Under Imple IDA / 67680 Post Request for Bids Open - National 630,000.00 0.00 2022-09-19 2023-01-12 2022-09-24 2023-01-12 2022-11-05 2022-12-05 2023-01-09 2023-07-08 10No 4WD Double Cabin Pick nsport and Related Institutio nvelope mentation -ups of minimum 3000cc ns KE-SDOI-264213-GO-RFB / M TD: Supply and Delivery of IC Component D: Institutional S T Equipment; trengthening of Selected Tra Single Stage - One E Under Imple Lot 1. Uninterrupted Power S IDA / 67680 Post Request for Bids Open - National 257,960.00 0.00 2021-11-28 2023-01-12 2021-12-03 2023-01-12 2022-01-14 2022-02-13 2022-03-20 2022-09-16 nsport and Related Institutio nvelope mentation upply 94 No. ns Lot 2. Computers 148 No. Lot 3 Printers and Scanners 8 7 No. KE-EBK-218313-GO-RFB / Su Component D: Institutional S Single Stage - One E pply and delivery of Motor ve IDA / 67680 trengthening of Selected Tra Post Request for Bids Open - National 440,000.00 0.00 Canceled 2021-06-15 2022-09-15 2021-06-20 2021-08-01 2021-08-31 2021-10-05 2022-04-03 nvelope hicles nsport and Related Institutio ns KE-SDOI-276689-GO-RFB / R Component D: Institutional S OADS DIVISION: SUPPLY AND trengthening of Selected Tra Single Stage - One E Under Imple IDA / 67680 Post Request for Bids Open - National 274,500.00 0.00 2022-09-27 2022-11-08 2022-10-25 2022-11-08 2022-11-25 2022-12-25 2023-01-30 2023-06-30 DELIVERY OF 4No. 4WD DOU nsport and Related Institutio nvelope mentation BLE CABIN PICK UP (4X4, 250 ns 0-3000cc,Diesel) KE-SDOI-317952-GO-RFB / E BK: SUPPLY AND DELIVERY O F; Component D: Institutional S LOT 1: 1No. 4WD Double Cab trengthening of Selected Tra Single Stage - One E Under Imple IDA / 67680 Post Request for Bids Open - National 440,000.00 0.00 2022-09-28 2022-11-08 2022-10-25 2022-11-08 2022-11-25 2022-12-25 2023-01-30 2023-06-30 in Pick-up 4x4, LWB 2400- 30 nsport and Related Institutio nvelope mentation 00cc, Diesel. ns LOT 2: 2No. Heavy Duty, Utili ty Passenger Vehicle, 4x4, L WB, 2400-3000. KE-KURA-202078-GO-RFQ / P Component A: Improving Mo rocurement of Air Quality an Request for Quota Single Stage - One E IDA / 67680 vement of People, Goods, an Post Open - National 35,000.00 0.00 Canceled 2021-02-20 2021-04-17 2021-10-14 d Noise Measurement Equip tions nvelope d Digital Connectivity ment for the ESS Department KE-SDOI-323127-GO-RFQ / K Component D: Institutional S URA:Procurement of Air Quali trengthening of Selected Tra Request for Quota Single Stage - One E Pending Impl IDA / 67680 Post Limited 35,000.00 0.00 2022-11-03 2022-12-29 2023-01-31 ty and Noise Measurement E nsport and Related Institutio tions nvelope ementation quipment for the ESS Depart ns ment KE-SDOI-265668-GO-RFB / K Component D: Institutional S Single Stage - One E eRRA: Procurement of 1No. S IDA / 67680 trengthening of Selected Tra Post Request for Bids Open - National 1,350,000.00 0.00 Canceled 2021-12-10 2021-12-15 2022-01-26 2022-02-25 2022-04-01 2022-09-28 nvelope tatic Weighbridge nsport and Related Institutio ns NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 3 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-SDOI-220180-CS-QCBS / Component D: Institutional S MTRD: Consultancy Services trengthening of Selected Tra Quality And Cost- Open - Internationa Under Implement IDA / 67680 Prior 1,000,000.00 0.00 2021-04-07 2021-04-28 2021-06-11 2021-07-09 2021-08-08 2021-09-12 2021-10-17 2022-10-17 for Pavement Performance M nsport and Related Institutio Based Selection l ation onitoring of Select Roads & Fl ns agship Projects KE-SDOI-220169-CS-QCBS / Component D: Institutional S MTRD:Consultancy Services f trengthening of Selected Tra Quality And Cost- Open - Internationa Under Implement IDA / 67680 Prior 700,000.00 0.00 2021-05-05 2021-05-26 2021-07-09 2021-08-06 2021-09-05 2021-10-10 2021-11-14 2022-11-14 or Mapping of Construction M nsport and Related Institutio Based Selection l ation aterial Sources in Coast Regi ns on KE-SDOI-220175-CS-QCBS / Component D: Institutional S MTRD: Consultancy Services trengthening of Selected Tra Quality And Cost- Open - Internationa Under Implement IDA / 67680 Prior 700,000.00 0.00 2021-05-05 2021-05-26 2021-07-09 2021-08-06 2021-09-05 2021-10-10 2021-11-14 2022-11-14 for Mapping of Construction nsport and Related Institutio Based Selection l ation Material Sources in Nairobi M ns etropolitan Region KE-SDOI-220178-CS-QCBS / Component D: Institutional S MTRD: Consultancy Services trengthening of Selected Tra Quality And Cost- Open - Internationa IDA / 67680 Prior 700,000.00 0.00 Under Review 2021-06-06 2021-06-27 2021-08-10 2021-09-07 2021-10-07 2021-11-11 2021-12-16 2022-12-16 for Mapping of Construction nsport and Related Institutio Based Selection l Material Sources in Western ns Region KE-SDOI-220177-CS-QCBS / Component D: Institutional S MTRD: Consultancy Services trengthening of Selected Tra Quality And Cost- Open - Internationa Under Implement IDA / 67680 Prior 700,000.00 0.00 2021-05-26 2021-06-16 2021-07-30 2021-08-27 2021-09-26 2021-10-31 2021-12-05 2022-12-05 for Mapping of Construction nsport and Related Institutio Based Selection l ation Material Sources in South Rift ns Region KE-SDOI-220048-CS-QCBS / Component D: Institutional S MTRD: Consultancy Services trengthening of Selected Tra Quality And Cost- Open - Internationa IDA / 67680 Prior 700,000.00 0.00 Under Review 2021-05-05 2021-05-26 2021-07-09 2021-08-06 2021-09-05 2021-10-10 2021-11-14 2022-11-14 for Mapping of Construction nsport and Related Institutio Based Selection l Material Sources in Central R ns egion KE-NCA-190474-CS-QCBS / Component D: Institutional S Development of Self regulati trengthening of Selected Tra Quality And Cost- Under Implement IDA / 67680 Post Open - National 300,000.00 0.00 2021-09-01 2023-05-18 2021-11-01 2021-12-31 2022-04-03 2022-05-03 2022-06-02 2022-07-01 2023-07-02 on framework for the Contrac nsport and Related Institutio Based Selection ation tors and construction worker ns s Associations KE-NCA-190484-CS-QCBS / I Component D: Institutional S mplementation of the integra trengthening of Selected Tra Quality And Cost- Pending Impleme IDA / 67680 Post Open - National 300,000.00 0.00 2021-10-01 2021-10-05 2021-12-04 2022-03-07 2022-04-06 2022-05-13 2022-06-05 2023-06-05 ted construction industry dev nsport and Related Institutio Based Selection ntation elopment policy. ns KE-SDOI-257442-CS-QCBS / Component D: Institutional S EBK: Consultancy Service for trengthening of Selected Tra Quality And Cost- Pending Impleme the Development of a Compli IDA / 67680 Post Open - National 452,000.00 0.00 2022-02-07 2022-02-26 2022-05-17 2022-06-14 2022-07-14 2022-08-18 2022-09-22 2023-09-22 nsport and Related Institutio Based Selection ntation ance and Enforcement Frame ns work for the Engineers Act 2 011 KE-SDOI-257439-CS-QCBS / Component D: Institutional S EBK: Provision of Consultanc trengthening of Selected Tra Quality And Cost- Pending Impleme IDA / 67680 Post Open - National 452,000.00 0.00 2022-02-06 2022-02-27 2022-04-12 2022-05-10 2022-06-09 2022-07-14 2022-08-18 2023-08-18 y Services on skills gap and c nsport and Related Institutio Based Selection ntation apacity needs assessment fo ns r Engineers KE-SDOI-257468-CS-QCBS / Component D: Institutional S EBK: Consultancy Services fo trengthening of Selected Tra Quality And Cost- Pending Impleme IDA / 67680 Post Open - National 90,335.00 0.00 2022-02-06 2022-02-27 2022-04-12 2022-05-10 2022-06-09 2022-07-14 2022-08-18 2023-08-18 r Development of Communic nsport and Related Institutio Based Selection ntation ations & Branding Strategy fo ns r EBK KE-SDOI-257457-CS-QCBS / Component D: Institutional S EBK: Consultancy services fo trengthening of Selected Tra Quality And Cost- Pending Impleme IDA / 67680 Post Open - National 90,335.00 0.00 2022-02-06 2022-02-27 2022-04-12 2022-05-10 2022-06-09 2022-07-14 2022-08-18 2023-08-18 r the development of perfor nsport and Related Institutio Based Selection ntation mance management system ns for EBK KE-SDOI-257460-CS-QCBS / Component D: Institutional S EBK: Consultancy services fo trengthening of Selected Tra Quality And Cost- Pending Impleme IDA / 67680 Post Open - National 90,335.00 0.00 2022-02-06 2022-02-27 2022-04-12 2022-05-10 2022-06-09 2022-07-14 2022-08-18 2023-08-18 r development of records ma nsport and Related Institutio Based Selection ntation nagement system for EBK ns KE-SDOI-265678-CS-QCBS / Component D: Institutional S KeRRA: Consultancy services trengthening of Selected Tra Quality And Cost- IDA / 67680 Post Open - National 93,000.00 0.00 Canceled 2021-12-05 2021-12-26 2022-02-08 2022-03-08 2022-04-07 2022-05-12 2022-06-16 2023-06-16 for development of curriculu nsport and Related Institutio Based Selection m and delivery of training ns KE-SDOI-257436-CS-QCBS / Component D: Institutional S KRB: Provision for Consultanc trengthening of Selected Tra Quality And Cost- Open - Internationa IDA / 67680 Prior 1,000,000.00 0.00 Canceled 2021-10-15 2021-11-05 2021-12-19 2022-01-16 2022-02-15 2022-03-22 2022-04-26 2023-04-26 y Services for the Developme nsport and Related Institutio Based Selection l nt of a Rural Roads Improve ns ment Program KE-SDOI-256472-CS-QCBS / Component D: Institutional S KRB: Provision of Consultanc trengthening of Selected Tra Quality And Cost- Open - Internationa IDA / 67680 Prior 3,000,000.00 0.00 Canceled 2022-02-06 2022-02-27 2022-04-12 2022-05-10 2022-06-09 2022-07-14 2022-08-18 2023-08-18 y Services for the automation nsport and Related Institutio Based Selection l of the Annual Public Roads pr ns ogram (APRP) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-SDOI-247334-CS-INDV / C onsultancy Services for Trans formation of Materials Testin Component D: Institutional S g and Research Division, Mec trengthening of Selected Tra Individual Consult hanical and Transport Divisio IDA / 67680 Post Limited 80,000.00 94,500.24 Signed 2021-08-11 2021-09-24 2021-08-20 2021-12-22 2021-09-03 2022-07-19 2021-09-23 2022-07-20 2022-03-31 nsport and Related Institutio ant Selection n and Kenya Institute of High ns ways and Building Technolog y to Semi - Autonomous Gov ernment Agencies (Individual Consultant, Local) KE-SDOI-247337-CS-INDV / C onsultancy Services for Trans formation of Materials Testin Component D: Institutional S g and Research Division, Mec trengthening of Selected Tra Individual Consult hanical and Transport Divisio IDA / 67680 Post Limited 92,000.00 152,340.00 Signed 2021-08-12 2021-08-16 2021-08-22 2021-12-22 2021-09-05 2022-06-15 2021-09-30 2022-07-23 2022-04-02 nsport and Related Institutio ant Selection n and Kenya Institute of High ns ways and Building Technolog y to Semi - Autonomous Gov ernment Agencies (Individual Consultant, International) Page 4 KE-EBK-218326-CS-QCBS / C Component D: Institutional S onsultancy Services for Traini trengthening of Selected Tra Individual Consult Under Implement IDA / 67680 Post Open 40,000.00 0.00 2021-09-21 2022-10-24 2021-11-09 2021-11-30 2022-01-04 2022-07-03 ng Needs Analysis and Skills nsport and Related Institutio ant Selection ation Gap Analysis of Engineers Bo ns ard of Kenya Staff KE-SDOI-257451-CS-INDV / E Component D: Institutional S BK: Technical Advisor to Sup trengthening of Selected Tra Individual Consult Pending Impleme IDA / 67680 Post Open 135,500.00 0.00 2022-02-06 2022-03-27 2022-04-17 2022-05-22 2022-11-18 port the Compliance & Enforc nsport and Related Institutio ant Selection ntation ement Function at EBK ns KE-SDOI-257452-CS-INDV / E BK: Consultancy Service to S Component D: Institutional S upport the Establishment of t trengthening of Selected Tra Individual Consult Pending Impleme IDA / 67680 Post Open 135,500.00 0.00 2022-02-06 2022-03-27 2022-04-17 2022-05-22 2022-11-18 he Kenya Academy of Engine nsport and Related Institutio ant Selection ntation ering & Technology and the ns Kenya School of Engineering KE-SDOI-276533-CS-INDV / R Component D: Institutional S OADS DIVISION: CONSULTAN trengthening of Selected Tra Individual Consult CY SERVICES FOR COORDINA IDA / 67680 Prior Limited 300,000.00 0.00 Signed 2022-02-06 2022-06-06 2022-02-11 2022-06-17 2022-03-04 2022-09-09 2022-04-08 2022-10-05 nsport and Related Institutio ant Selection TOR NORTH AND NORTH EAS ns TERN DEVELOPMENT INITIATI VE PROGRAMME KE-SDOI-276542-CS-INDV / R Component D: Institutional S OADS DIVISION: Consultancy trengthening of Selected Tra Individual Consult Under Implement IDA / 67680 Post Limited 80,000.00 0.00 2022-02-06 2022-05-10 2022-02-11 2022-08-18 2022-03-04 2022-11-10 2022-04-08 2022-10-05 Services for Development of nsport and Related Institutio ant Selection ation Gender Action Plan in the Tra ns nsport Sector (SDoI) KE-SDOI-257413-CS-INDV / K RB: Provision of Consultancy Component D: Institutional S Services for development, su trengthening of Selected Tra Individual Consult Pending Impleme IDA / 67680 Prior Open 300,000.00 0.00 2022-02-06 2022-03-27 2022-04-17 2022-05-22 2022-11-18 pply, and installation of Road nsport and Related Institutio ant Selection ntation Network Information Manage ns ment System Quality Assura nce Partner. KE-SDOI-257450-CS-INDV / E Component D: Institutional S Individual Consult Pending Impleme BK: Technical advisor for the IDA / 67680 trengthening of Selected Tra Post Open 135,500.00 0.00 2022-02-06 2022-03-27 2022-04-17 2022-05-22 2022-11-18 ant Selection ntation development of Accreditation nsport and Related Institutio Framework ns KE-SDOI-257456-CS-INDV / E Component D: Institutional S BK: Consultancy Services for trengthening of Selected Tra Individual Consult Pending Impleme IDA / 67680 Post Open 100,000.00 0.00 2022-02-22 2022-04-12 2022-05-03 2022-06-07 2022-12-04 the Development of ICT Syst nsport and Related Institutio ant Selection ntation em Architecture for EBK ns KE-SDOI-257408-CS-INDV / K Component D: Institutional S RB: Provision of Consultancy trengthening of Selected Tra Individual Consult Services for the Developmen IDA / 67680 Post Open 180,000.00 0.00 Canceled 2022-02-06 2023-03-27 2022-03-27 2022-04-17 2022-05-22 2022-11-18 nsport and Related Institutio ant Selection t of Communication and Stak ns eholder Engagement Framew ork for KRB KE-SDOI-358955-CS-INDV / K Component D: Institutional S RB: Provision of Consultancy trengthening of Selected Tra Individual Consult Under Implement Services for the Developmen IDA / 67680 Post Open - National 95,000.00 0.00 2023-05-22 2023-05-18 2023-06-26 2023-07-17 2023-08-21 2024-05-23 nsport and Related Institutio ant Selection ation t of Communication and Stak ns eholder Engagement Framew ork for KRB Page 5 PLAN DE PASSATION DE MARCHÉS Informations sur le Projet Emprunteur : République de Djibouti Ministère Responsable : MINISTERE DE LA COMMUNICATION CHARGE DES POSTES ET DES TELECOMMUNICATIONS Nom du Projet : PROJET DJIBOUTI NUMERIQUE (P174461) Identification : P174461_______ CREDIT IDA N° : _____ Agence d’exécution du Projet : MINISTERE DE LA COMMUNICATION CHARGE DES POSTES ET DES TELECOMMUNICATIONS Date du plan de passation des marchés : 14 Decembre 2021 Période couverte par ce plan de passation des marchés : Decembre 2021 – Février 2022 Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Juillet 2016, révisé en Novembre 2107 et Août 2018) (“Règlement de Passation des Marchés”) le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marché se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus de STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la Loi n°53/AN/09/6ème L portant Nouveau Code des Marchés Publics, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas/ Travaux ne s’applique pas/ L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés ne s’applique pas. PROCUREMENT Djibouti : Djibouti Digital Foundations Project PLAN General Information Country: Djibouti 2021-12-15 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P174461 GPN Date: Project Name: Djibouti Digital Foundations Project Loan / Credit No: IDA / 70010 Ministry of Communications, in charge of Posts and Telecommunications Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned DJ-MCPT-267997-CW-RFQ / R Request for Quota Request for Quota Single Stage - One E 2022-08-1 enovation et câblage des loc IDA / 70010 3. Project management Post Limited tions (Non Bank-S 20,000.00 0.00 Signed 2021-12-25 2022-09-03 2022-02-19 tions nvelope 8 aux de l'UGP PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MCPT-267993-GO-RFQ / A 1. Digital enabling environm Request for Quota Single Stage - One E cquisition de matériels infor IDA / 70010 Post Limited 50,000.00 0.00 Signed 2021-12-25 2022-09-19 2022-02-19 2022-08-18 ent and connectivity tions nvelope matique pour l'UGP et pour l' ARMD DJ-MCPT-267994-GO-RFQ / A 1. Digital enabling environm Request for Quota Single Stage - One E cquisition de mobilier de bur IDA / 70010 Post Limited 50,000.00 0.00 Signed 2021-12-25 2022-01-30 2022-02-19 2022-08-18 ent and connectivity tions nvelope eau pour l'UGP et pour l'ARM D DJ-MCPT-316660-GO-RFQ / A 2. Digital ecosystem, transfo Single Stage - One E Under Imple cquisition d’équipements info IDA / 70010 rmation and skills developm Post Request for Bids Open - National 100,000.00 0.00 2022-11-06 2022-11-17 2022-11-11 2023-06-12 2022-12-28 2022-12-14 2023-01-04 2023-02-08 2023-05-09 nvelope mentation rmatique pour le MENI ent DJ-MCPT-315540-GO-RFB / A Single Stage - One E cquisition de véhicules pour l IDA / 70010 3. Project management Post Request for Bids Open - National 150,000.00 0.00 Signed 2022-12-10 2022-12-22 2022-12-15 2023-04-05 2023-01-29 2023-02-01 2023-02-03 2023-02-08 2023-03-10 2023-09-06 nvelope e compte du projet et l'ARMD . DJ-MCPT-331830-NC-RFQ / A 1. Digital enabling environm Request for Quota Single Stage - One E cquisition de logiciel de Com IDA / 70010 Post Limited 20,000.00 0.00 Signed 2023-01-05 2023-01-12 2023-03-02 2023-08-29 ent and connectivity tions nvelope ptabilité SAGE pour l'ARMD. DJ-MCPT-313280-NC-DIR / Ac quisition et formation d’un lo IDA / 70010 3. Project management Post Direct Selection Direct - National 30,000.00 0.00 Signed 2023-05-03 2022-10-02 2023-05-08 2022-10-03 2023-06-12 2023-12-09 giciel de gestion financière NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MCPT-272793-CS-QCBS / Révision du cadre legal et rè 1. Digital enabling environm Quality And Cost- Open - Internationa Pending Impleme IDA / 70010 Post 100,000.00 0.00 2022-01-20 2022-02-10 2022-03-26 2022-04-23 2022-05-23 2022-06-27 2022-08-01 2023-08-01 glementaire du secteur des t ent and connectivity Based Selection l ntation élécommunications/TIC DJ-MCPT-315533-CS-CQS / R ecrutement d’un consultant c hargé de la conception et la 1. Digital enabling environm Consultant Qualifi Under Implement IDA / 70010 Post Open - National 50,000.00 0.00 2022-09-15 2022-09-21 2022-10-06 2022-11-19 2022-12-19 2023-01-23 2023-04-23 mise en ligne du portail offici ent and connectivity cation Selection ation el et du logo de l’Agence de Régulation Multisectorielle d e Djibouti (ARMD) DJ-MCPT-315534-CS-LCS / R ecrutement d’un Cabinet d’A udit National Exercices 2022, Least Cost Selecti IDA / 70010 3. Project management Post Open - National 50,000.00 0.00 Signed 2022-09-18 2022-10-03 2022-10-09 2023-05-25 2022-11-22 2023-06-05 2022-12-20 2022-12-21 2023-01-19 2022-12-27 2023-02-23 2023-02-01 2023-03-30 2023-09-26 2023 et 2024 Pour le compte on du Projet Djibouti Fondement Nu mérique (DFN) DJ-MCPT-315895-CS-QCBS / 2. Digital ecosystem, transfo Elaboration et la mise en œu Quality And Cost- Open - Internationa Under Implement IDA / 70010 rmation and skills developm Post 200,000.00 0.00 2022-11-06 2022-12-14 2022-11-25 2022-12-20 2022-12-16 2023-01-30 2023-02-06 2023-02-27 2023-04-03 2026-04-03 vre d'une stratégie de comm Based Selection l ation ent unication pour le MDENI. DJ-MCPT-324176-CS-QCBS / Elaboration et la mise en œu 1. Digital enabling environm Quality And Cost- Open - Internationa IDA / 70010 Post 150,000.00 0.00 Canceled 2022-11-06 2022-11-25 2022-12-16 2023-01-30 2023-02-06 2023-02-27 2023-04-03 2026-04-03 vre d'une stratégie de comm ent and connectivity Based Selection l unication pour le MCPT. DJ-MCPT-350252-CS-QCBS / Recrutement d’un Cabinet In ternational pour une Assistan 1. Digital enabling environm Quality And Cost- Open - Internationa Under Implement ce Technique au profit de l’A IDA / 70010 Post 200,000.00 0.00 2023-03-27 2023-04-10 2023-04-17 2023-04-24 2023-04-25 2023-06-09 2023-06-23 2023-07-07 2023-08-11 2024-08-10 ent and connectivity Based Selection l ation utorité de Régulation Multisectorielle d e Djibouti (ARMD). DJ-MCPT-350264-CS-QCBS / Recrutement d'un cabinet co 1. Digital enabling environm Quality And Cost- Open - Internationa Under Implement nseil pour l'étude des besoin IDA / 70010 Post 250,000.00 0.00 2023-03-27 2023-04-12 2023-04-17 2023-04-24 2023-05-08 2023-06-22 2023-07-06 2023-07-28 2023-09-01 2023-09-02 ent and connectivity Based Selection l ation s en bande passante pour les bâtiments du Gouvernement Page 1 DJ-MCPT-361747-CS-CQS / Et 2. Digital ecosystem, transfo Consultant Qualifi Under Implement ude pour le plan du futur sièg IDA / 70010 rmation and skills developm Post Open - National 120,000.00 0.00 2023-06-05 2023-06-04 2023-06-20 2023-06-19 2023-07-12 2023-07-27 2023-08-31 2024-02-27 cation Selection ation e du MDENI ent INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DJ-MCPT-267999-CS-CDS / R Individual Consult ecrutement d'un Responsabl IDA / 70010 3. Project management Post Direct 28,000.00 0.00 Signed 2021-12-20 2022-06-14 2021-12-30 2022-08-02 2022-01-20 2022-07-01 2022-02-24 2022-08-23 ant Selection e Administratif et Financier p our le projet DJ-MCPT-267998-CS-CDS / R Individual Consult ecrutement d'un responsable IDA / 70010 3. Project management Post Direct 28,000.00 0.00 Signed 2021-12-20 2022-06-15 2021-12-30 2022-08-02 2022-01-20 2022-08-02 2022-02-24 2022-08-23 ant Selection en passation de marchés DJ-MCPT-272799-CS-INDV / L 'élaboration d'un cahier de c 1. Digital enabling environm Individual Consult Pending Impleme IDA / 70010 Post Limited 70,000.00 0.00 2022-01-25 2022-01-30 2022-02-20 2022-03-27 2022-09-23 harge et licenses pour les ser ent and connectivity ant Selection ntation vices des télécommunication s DJ-MCPT-272803-CS-INDV / Individual Consult Recrutement Consultant(e) I IDA / 70010 3. Project management Post Open 28,000.00 0.00 Signed 2022-01-30 2022-03-23 2022-03-20 2022-06-04 2022-04-10 2022-06-15 2022-05-15 2022-11-11 ant Selection ndividuel spécialiste environ nement et social . DJ-MCPT-283123-CS-INDV / S pécialiste en communication 1. Digital enabling environm Individual Consult Under Implement IDA / 70010 Post Open 14,000.00 0.00 2022-03-20 2022-06-02 2022-05-08 2022-10-10 2022-05-29 2022-11-01 2022-07-03 2022-12-30 relationnel avec les consom ent and connectivity ant Selection ation mateurs et les parties prenan tes pour l'ARMD DJ-MCPT-283166-CS-INDV / 1. Digital enabling environm Individual Consult Chargé de mission du secteu IDA / 70010 Post Open 14,000.00 0.00 Signed 2022-03-20 2022-06-02 2022-05-08 2022-10-10 2022-05-29 2022-10-27 2022-07-03 2022-12-30 ent and connectivity ant Selection r de télécommunication pour l’ARMD DJ-MCPT-283171-CS-INDV / E 1. Digital enabling environm Individual Consult conomiste-analyste financier IDA / 70010 Post Open 14,000.00 0.00 Signed 2022-03-20 2022-06-02 2022-05-08 2022-10-10 2022-05-29 2022-10-27 2022-07-03 2022-12-30 ent and connectivity ant Selection sous-secteur électricité pour l’ARMD DJ-MCPT-313283-CS-INDV / 1. Digital enabling environm Individual Consult Recrutement d'un juriste pou IDA / 70010 Post Limited 27,000.00 0.00 Signed 2022-09-10 2022-10-20 2022-09-15 2022-11-02 2022-10-06 2022-12-04 2022-11-10 2023-01-09 ent and connectivity ant Selection r le compte de l'ARMD DJ-MCPT-283175-CS-INDV / I 1. Digital enabling environm Individual Consult IDA / 70010 Post Open 14,000.00 0.00 Canceled 2022-03-20 2022-06-02 2022-05-08 2022-05-29 2022-07-03 2022-12-30 ngénieure informatique pour ent and connectivity ant Selection l'ARMD DJ-MCPT-272800-CS-INDV / 1. Digital enabling environm Individual Consult IDA / 70010 Post Limited 25,000.00 0.00 Canceled 2022-01-20 2022-07-25 2022-01-25 2022-02-15 2022-03-22 2022-09-18 Conception d'un site Internet ent and connectivity ant Selection pour l'ARMD DJ-MCPT-272802-CS-INDV / 1. Digital enabling environm Individual Consult IDA / 70010 Post Limited 20,000.00 0.00 Canceled 2022-01-20 2022-07-25 2022-01-25 2022-02-15 2022-03-22 2022-09-18 Conception d'un Logo pour l' ent and connectivity ant Selection ARMD DJ-MCPT-329665-CS-INDV / 2. Digital ecosystem, transfo Individual Consult Open - Internationa Under Implement Recrutement d’un Conseiller IDA / 70010 rmation and skills developm Post 100,000.00 0.00 2022-12-10 2023-01-19 2023-01-28 2023-02-18 2023-03-25 2024-03-19 ant Selection l ation en Economie Numérique et I ent nnovation DJ-MCPT-329673-CS-INDV / Recrutement d'un consultant 1. Digital enabling environm Individual Consult Open - Internationa Under Implement IDA / 70010 Post 80,000.00 0.00 2022-12-10 2022-12-14 2023-01-28 2023-02-18 2023-03-25 2023-09-21 individuel pour l'élaboration ent and connectivity ant Selection l ation d'une stratégie de communic ation pour le MCPT. DJ-MCPT-358639-CS-INDV / 1. Digital enabling environm Individual Consult Open - Internationa Under Implement Mise en place d'une stratégie IDA / 70010 Post 100,000.00 0.00 2023-05-15 2023-06-11 2023-06-18 2023-07-09 2023-08-13 2024-02-09 ent and connectivity ant Selection l ation nationale de démocratisation du haut débit DJ-MCPT-369128-CS-CDS / R ecrutement Consultant Indivi Pending Impleme duel spécialiste environneme IDA / 70010 3. Project management Post Direct Selection Direct - National 28,000.00 0.00 2023-07-05 2023-07-15 2023-09-18 2024-09-12 ntation nt et social le projet régional e et le suivis du projet Nation ale. Page 2