PROCUREMENT PLAN Project information: Bosnia and Herzegovina – Energy Efficiency Project – P143580 Project Implementation agency: Federal Ministry of Physical Planning Date of the Procurement Plan: 4/30/2020 Period covered by this Procurement Plan: 2020-2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. If the Borrower and the Bank agreed to use the Borrower’s national open competitive procurement arrangements, it will be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable; Works: is not applicable. Other Relevant Procurement Information. None. PROCUREMENT Bosnia and Herzegovina : Energy Efficiency Project PLAN General Information Country: Bosnia and Herzegovina 2020-03-13 Bank’s Approval Date of the Original Procurement Plan: 2023-06-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P143580 GPN Date: 2020-03-19 Project Name: Energy Efficiency Project Loan / Credit No: IBRD / 89060, IDA / 55380, IDA / 53930 Federal Ministry of Physical Planning-Project Implementation Unit Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BEEPAF-P165405-RFB-04-W- Energy Efficiency Investmen Single Stage - One E Pending Imp 2023-10-1 23-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National 0.00 2023-04-01 2023-04-11 2023-05-09 2023-05-23 2023-06-17 ts in Public Facilities nvelope lementation 5 ction of (1+5) objects in 202 3 BEEPAF-P165405-RFB-03-W- Energy Efficiency Investmen Single Stage - One E 2022-10-1 22-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National 0.00 Signed 2022-04-01 2022-04-28 2022-04-11 2022-05-09 2022-05-30 2022-05-23 2022-06-17 2022-06-17 ts in Public Facilities nvelope 5 ction of 10 objects in 2022 BEEPAF-P165405-RFB-02-W- Energy Efficiency Investmen Single Stage - One E 2021-10-1 21-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National 573,284.47 Signed 2021-04-01 2021-05-28 2021-04-11 2021-05-28 2021-05-09 2021-06-28 2021-05-23 2021-06-30 2021-06-17 2021-07-27 ts in Public Facilities nvelope 5 ction of 13 objects in 2021 BEEPAF-P165405-RFB-05-W- Energy Efficiency Investmen Single Stage - One E 1,168,669.6 2021-10-1 21-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National Signed 2021-04-01 2021-05-31 2021-04-11 2021-05-31 2021-05-09 2021-06-30 2021-05-23 2021-07-01 2021-06-17 2021-07-27 ts in Public Facilities nvelope 7 5 ction of 12 objects in 2021. BEEPAF-P165405-RFB-06-W- Energy Efficiency Investmen Single Stage - One E 2022-10-1 22-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National 0.00 Signed 2022-04-01 2022-07-04 2022-04-11 2022-05-09 2022-08-02 2022-05-23 2022-08-25 2022-06-17 ts in Public Facilities nvelope 5 ction of 10 objects in 2022. Request for B BEEPAF-165405-RFB-07-W-2 ids - Works ( Energy Efficiency Investmen Single Stage - One E 2021-12-1 1-FBIH / Works on reconstruc IBRD / 89060 Post Request for Bids Open - National without preq 535,364.38 Signed 2021-06-15 2021-06-18 2021-06-20 2021-06-18 2021-07-20 2021-07-16 2021-07-30 2021-07-26 2021-08-16 2021-09-03 ts in Public Facilities nvelope 4 tion of 2 objects in Canton Tu ualification) zla SPD Request for B BEEPAF-165405-RFB-08-W-2 ids - Works ( Energy Efficiency Investmen Single Stage - One E 1,381,877.2 2021-12-1 1-FBIH / Works on reconstruc IBRD / 89060 Post Request for Bids Open - National without preq Signed 2021-06-15 2021-06-23 2021-06-20 2021-06-23 2021-07-20 2021-07-21 2021-07-30 2021-09-08 2021-08-16 2021-09-29 ts in Public Facilities nvelope 1 4 tion of 5 objects in ZE-DO ca ualification) nton SPD Request for B BEEPAF-165405-RFB-09-W-2 ids - Works ( Energy Efficiency Investmen Single Stage - One E 1,315,821.0 2021-12-1 1-FBIH / Works on reconstruc IBRD / 89060 Post Request for Bids Open - National without preq Signed 2021-06-16 2021-06-23 2021-06-21 2021-06-23 2021-07-21 2021-07-21 2021-07-31 2021-08-25 2021-08-17 2021-09-18 ts in Public Facilities nvelope 8 5 tion of 5 objects in ZE-DO ca ualification) nton SPD Request for B BEEPAF-165405-RFB-10-W-2 ids - Works ( Energy Efficiency Investmen Single Stage - One E 2,691,539.6 2021-12-1 1-FBIH / Works on reconstruc IBRD / 89060 Post Request for Bids Open - National without preq Signed 2021-06-17 2021-06-23 2021-06-22 2021-06-23 2021-07-22 2021-07-21 2021-08-01 2021-09-03 2021-08-18 2021-09-29 ts in Public Facilities nvelope 0 6 tion of 5 objects in ZE-DO ca ualification) nton SPD Request for B BEEPAF-165405-RFB-11-W-2 ids - Works ( Energy Efficiency Investmen Single Stage - One E 2021-12-1 1-FBIH / Works on reconstruc IBRD / 89060 Post Request for Bids Open - National without preq 925,811.86 Signed 2021-06-18 2021-06-23 2021-06-23 2021-06-23 2021-07-23 2021-07-21 2021-08-02 2021-08-25 2021-08-19 2021-09-18 ts in Public Facilities nvelope 7 tion of 5 objects in ZE-DO ca ualification) nton SPD Request for B BEEPAF-P165405-RFB-01-W- ids - Works ( Energy Efficiency Investmen Single Stage - One E 2021-12-1 20-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National without preq 0.00 Canceled 2021-06-14 2021-06-17 2021-06-17 2021-06-17 2021-07-17 2021-07-27 2021-08-13 ts in Public Facilities nvelope 1 ction of 3 objects in KS ualification) SPD BEEPAF-P165405-RFB-12-W- 21-FBIH / Works on reconstru Request for B ction of objects: LOT 1: Polikli ids - Works ( Energy Efficiency Investmen Single Stage - One E 2,143,608.7 2022-03-1 nika za plućne bolesti "Podhr IBRD / 89060 Post Request for Bids Open - National without preq Signed 2021-09-10 2021-10-01 2021-09-15 2021-10-15 2021-10-29 2021-10-29 2021-11-29 2021-11-17 2022-01-11 ts in Public Facilities nvelope 1 7 astovi, LOT 2: UKCS Klinika z ualification) a urgentnu medicinu Sarajev SPD o, LOT 3: UKCS Klinika za fizi kalnu medicinu i rehabilitacij u Sarajevo Request for B BEEPAF-P165405-RFB-13-W- ids - Works ( Energy Efficiency Investmen Single Stage - One E 2023-01-1 22-FBIH / Works on reconstru IBRD / 89060 Post Request for Bids Open - National without preq 0.00 Signed 2022-07-16 2022-07-27 2022-07-21 2022-08-18 2022-08-25 2022-09-01 2022-08-25 2022-09-20 ts in Public Facilities nvelope 8 ction on one object in Canton ualification) Sarajevo SPD B EEP-PI 4 3580-NCB-30-W1 5 - FBIH / Works for impleme ntation of energy efficiency Energy Efficiency Investmen Single Stage - One E 1,061,492.1 IDA / 53930 Prior Request for Bids Open - National Signed 2015-09-29 2015-12-19 measures for university clinic ts in Public Facilities nvelope 8 al center Mostar Lot 1 and un iversity clinical center Tuzla s urgery clinic Gradina Lot 2 -P143580-BA-BEEP-5393BA- Energy Efficiency Investmen Single Stage - One E Under Imple NCB-W-15-5-RS / RETROFITTI IDA / 53930 Prior Request for Bids Open - National 0.00 2016-04-20 ts in Public Facilities nvelope mentation NG OF JZU BOLNICA ZVORNIK P143580-BA-BEEP-5393BA-N Energy Efficiency Investmen Single Stage - One E Under Imple CB-W-14-4-RS / Retrofitting o IDA / 53930 Prior Request for Bids Open - National 0.00 2016-04-20 ts in Public Facilities nvelope mentation f University Hospital Foca BEEP-P143580-NCB-29-W-15 -FBIH / Works for implementa tion of energy efficiency mea Energy Efficiency Investmen Single Stage - One E IDA / 53930 Prior Request for Bids Open - National 708,250.25 Signed 2015-07-08 2016-01-08 sures for University of Clinica ts in Public Facilities nvelope l Center Sarajevo (Departme nt of Orthopedic and Trauma ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BEEPAF-P165405-RFQ-04-G- 23-FBIH / "Purchasing and Ins talation (Performance Monito Energy Efficiency Investmen Request for Quota Single Stage - One E Pending Impl ring System for measuring th IBRD / 89060 Post Limited 0.00 2023-01-20 2023-02-07 2023-02-27 ts in Public Facilities tions nvelope ementation e temperature and humidity) (6 buildings) - 20232. buldin gs (allocated)" Page 1 BEEPAF-P165405-RFQ-05-G- 20-FBIH / Purchasing and Inst Energy Efficiency Investmen Request for Quota Single Stage - One E Pending Impl alation of Equipment require IBRD / 89060 Post Limited 0.00 2020-09-06 2020-09-24 2020-10-14 ts in Public Facilities tions nvelope ementation d for Energy efficiency infor mation system update (EE R evolving fund) BEEPAF-P165405-RFQ-06-G- Energy Efficiency Investmen Request for Quota Single Stage - One E 20-FBIH / Purchasing and Inst IBRD / 89060 Post Limited 27,764.72 Signed 2020-05-20 2021-01-08 2020-06-07 2021-02-16 2020-06-27 ts in Public Facilities tions nvelope alation of IT Equipment requi red PIU BEEPAF-P165405-RFQ-07-G- Energy Efficiency Investmen Request for Quota Single Stage - One E 20-FBIH / Purchasing of Furni IBRD / 89060 Post Limited 2,074.95 Completed 2020-05-20 2020-05-29 2020-06-07 2020-10-27 2020-06-27 2020-12-01 ts in Public Facilities tions nvelope ture required PIU BEEPAF-P165405-RFQ-08-G- Energy Efficiency Investmen Request for Quota Single Stage - One E Pending Impl 20-FBIH / Contract Managem IBRD / 89060 Post Limited 0.00 2020-09-20 2020-10-16 2020-12-15 ts in Public Facilities tions nvelope ementation ent Software BEEPAF-P165405-NCB-01-G- 20-FBIH / "Purchasing and Ins talation (Performance Monito Energy Efficiency Investmen Single Stage - One E ring System for measuring th IBRD / 89060 Post Request for Bids Open - National 0.00 Canceled 2020-07-15 2020-07-17 2020-08-07 2020-08-12 2020-08-16 2020-09-05 ts in Public Facilities nvelope e temperature and humidity) (20 buildings) - 2020. buldin gs (allocated)" BEEPAF-P165405-RFB-02-G- 22-FBIH / "Purchasing and Ins Energy Efficiency Investmen Single Stage - One E Pending Impl tallation (Performance Monit IBRD / 89060 Post Request for Bids Open - National 0.00 2022-01-15 2022-01-17 2022-02-07 2022-02-12 2022-02-16 2022-03-18 ts in Public Facilities nvelope ementation oring System for measuring t he temperature and humidity ) BEEPAF-P165405-NCB-02-G- 21-FBIH / "Purchasing and Ins talation (Performance Monito Energy Efficiency Investmen Single Stage - One E ring System for measuring th IBRD / 89060 Post Request for Bids Open - National 0.00 Canceled 2021-01-15 2021-01-17 2021-02-07 2021-02-12 2021-02-16 2021-03-08 ts in Public Facilities nvelope e temperature and humidity) (25 buildings) - 2020. buldin gs (allocated)" BEEPAF-P165405-RFB-03-G- 23-FBIH / "Purchasing and Ins Energy Efficiency Investmen Single Stage - One E Pending Impl tallation (Performance Monit IBRD / 89060 Post Request for Bids Open - National 0.00 2023-01-15 2023-01-17 2023-02-07 2023-02-12 2023-02-16 2023-03-18 ts in Public Facilities nvelope ementation oring System for measuring t he temperature and humidity ) BEEPAF-P165405-NCB-03-G- 22-FBIH / "Purchasing and Ins talation (Performance Monito Energy Efficiency Investmen Single Stage - One E ring System for measuring th IBRD / 89060 Post Request for Bids Open - National 0.00 Canceled 2022-01-15 2022-01-17 2022-02-07 2022-02-12 2022-02-16 2022-03-08 ts in Public Facilities nvelope e temperature and humidity) (20 buildings) - 2022. buldin gs (allocated)" BEEPAF-P165405-RFB-01-G- 21-FBIH / "Purchasing and Ins Energy Efficiency Investmen Single Stage - One E tallation (Performance Monit IBRD / 89060 Post Request for Bids Open - National 174,238.32 Signed 2021-02-03 2021-02-08 2021-02-05 2021-02-26 2021-03-02 2021-03-03 2021-03-11 2021-03-07 2021-03-24 2021-04-21 ts in Public Facilities nvelope oring System for measuring t he temperature and humidity ) (38 buildings) " BEEPAF--P165405-RFQ-09-G- 21-FBIH / Purchasing and Inst Energy Efficiency Investmen Request for Quota Single Stage - One E allation (Performance Monito IBRD / 89060 Post Limited 23,718.00 Signed 2021-07-03 2021-09-24 2021-07-26 2021-10-27 2021-08-25 ts in Public Facilities tions nvelope ring System for measuring th e temperature and humidity BEEPAF-P165405-RFQ-10-G- Energy Efficiency Investmen Request for Quota Single Stage - One E 21-FBIH / Procurement of equ IBRD / 89060 Post Limited 9,991.83 Signed 2021-06-30 2021-09-10 2021-07-23 2021-10-16 2021-09-21 ts in Public Facilities tions nvelope ipment for video conference BEEPAF-P165405-RFQ-11-G- 22-FBIH / Equipment for mea suring the heat energy consu Energy Efficiency Investmen Request for Quota Single Stage - One E IBRD / 89060 Post Limited 0.00 Canceled 2022-07-25 2022-09-07 2022-08-17 2022-10-16 mption and temperature/hu ts in Public Facilities tions nvelope midity and Equipment for re mote reading of meters in a wired M-bus system BEEPAF-P165405-RFQ-12-G- 22-FBIH / Equipment for mea suring the heat energy consu Energy Efficiency Investmen Request for Quota Single Stage - One E IBRD / 89060 Post Open - National 0.00 Signed 2022-10-13 2022-11-09 2023-03-09 mption and internal and exte ts in Public Facilities tions nvelope rnal temperatures and Equip ment for remote reading of meters in a wired M-bus syst em BEEPAF-P165405-RFB-03-G- 22-FBIH / Equipment for mea suring the heat energy consu Energy Efficiency Investmen Single Stage - One E Pending Impl IBRD / 89060 Post Request for Bids Open - National 0.00 2022-11-28 2022-11-30 2022-12-28 2022-12-29 2023-01-15 2023-05-15 mption/temperatures and Eq ts in Public Facilities nvelope ementation uipment for remote reading o f meters in a wired M-bus sys tem P143580-BA-BEEP-5393BA-S Energy Efficiency Investmen Request for Quota Open - Internationa H-G-14-13-RS / Supply of met IDA / 53930 Prior 46,774.87 Signed 2016-03-23 ts in Public Facilities tions l ering equipment NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BEEPAF-P165405-RFB-01-NC S-21-FBIH / ENERGY EFFICIEN CY SERVICES for implementation of energy Energy Efficiency Investmen Single Stage - One E Pending Impl efficiency measures, includin IBRD / 89060 Post Request for Bids Open - National 0.00 2021-06-30 2021-07-05 2021-08-04 2021-08-19 2021-09-07 2023-03-11 ts in Public Facilities nvelope ementation g engineering design, constr uction works, measurement and verification of savings an d first year operations and m aintenance services CONSULTING FIRMS Page 2 Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BEEPAF-P165405-CQ-01-CS- Energy Efficiency Investmen Consultant Qualifi 20-FBIH / Detailed energy au IBRD / 89060 Post Open - National 158,785.08 Signed 2020-07-10 2020-05-07 2020-07-29 2020-08-06 2020-11-11 2020-08-20 2020-12-22 2020-08-22 2021-01-12 2020-11-20 ts in Public Facilities cation Selection dits - 50 buildings BEEPAF-P165405-CQ-04-CS- Energy Efficiency Investmen Consultant Qualifi 20-FBIH / Audit of design (11 IBRD / 89060 Post Open - National 120,339.23 Signed 2020-07-10 2020-05-08 2020-07-29 2020-08-06 2021-01-28 2020-08-20 2021-02-16 2020-08-22 2021-03-04 2020-10-21 ts in Public Facilities cation Selection +9=20 buildings) BEEPAF-P165405-CQ-08-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 22-FBIH / Audit of design (14 IBRD / 89060 Post Open - National 0.00 2022-01-10 2022-01-29 2022-02-06 2022-03-08 2022-03-10 2022-05-09 ts in Public Facilities cation Selection ntation +6=20 buildings) BEEPAF-P165405-CQ-09-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 23-FBIH / Design and tecnical IBRD / 89060 Post Open - National 0.00 2023-01-10 2023-01-29 2023-02-06 2023-02-20 2023-02-22 2023-08-21 ts in Public Facilities cation Selection ntation supervision (1+5=6 buildings ) BEEPAF-P165405-CQ-10-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 23-FBIH / Audit of design (1+ IBRD / 89060 Post Open - National 0.00 2023-01-10 2023-01-29 2023-02-06 2023-02-20 2023-02-22 2023-04-23 ts in Public Facilities cation Selection ntation 5=6 buildings) BEEPAF-P165405-CQ-11-CS- Energy Efficiency Investmen Consultant Qualifi 20-FBIH / Social monitoring a IBRD / 89060 Post Open - National 251,644.22 Signed 2020-06-10 2020-05-12 2020-06-29 2020-07-07 2020-10-09 2020-07-20 2020-12-09 2020-07-23 2020-12-12 2020-10-21 ts in Public Facilities cation Selection nd evaluation (up to 18 buildi ngs) BEEPAF-P165405-CQ-12-CS- Energy Efficiency Investmen Consultant Qualifi Under Implement IBRD / 89060 Post Open - National 0.00 2020-07-10 2020-05-15 2020-07-29 2020-08-06 2020-08-20 2020-08-22 2020-11-20 20-FBIH / Energy certificates ts in Public Facilities cation Selection ation BEEPAF-P165405-CQ-14-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme IDA / 55380 Post Open - National 0.00 2022-01-10 2022-01-29 2022-02-06 2022-02-20 2022-02-22 2022-05-23 22-FBIH / Energy certificates ts in Public Facilities cation Selection ntation BEEPAF-P165405-CQ-15-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme IBRD / 89060 Post Open - National 0.00 2023-01-10 2023-01-29 2023-02-06 2023-02-20 2023-02-22 2023-05-23 23-FBIH / Energy certificates ts in Public Facilities cation Selection ntation BEEPAF-P165405-CQ-20-CS- Support for the Developmen Consultant Qualifi 20-FBIH / Training for benefic IBRD / 89060 t of Scalable Financing Mech Post Open - National 39,567.33 Signed 2020-07-10 2021-12-08 2020-07-29 2020-08-06 2022-02-11 2020-08-20 2022-03-11 2020-08-22 2022-03-22 2024-06-22 cation Selection iaries and energy manageme anisms and Capacity Buildin nts g BEEPAF-P165405-CQ-22-CS- Support for the Developmen Consultant Qualifi Pending Impleme 22-FBIH / Training for benefic IBRD / 89060 t of Scalable Financing Mech Post Open - National 0.00 2022-01-10 2022-01-29 2022-02-06 2022-02-20 2022-02-22 2025-12-23 cation Selection ntation iaries and energy manageme anisms and Capacity Buildin nts g BEEPAF-P165405-CQ-23-CS- Support for the Developmen Consultant Qualifi Pending Impleme 23-FBIH / Training for benefic IBRD / 89060 t of Scalable Financing Mech Post Open - National 0.00 2023-01-10 2023-01-29 2023-02-06 2023-02-20 2023-02-22 2026-12-23 cation Selection ntation iaries and energy manageme anisms and Capacity Buildin nts g BEEPAF-P165405-CQ-24-CS- Support for the Developmen 20-FBIH / Other training and t of Scalable Financing Mech Consultant Qualifi IBRD / 89060 Post Open - National 0.00 Canceled 2020-11-01 2020-11-15 2020-11-23 2020-12-07 2020-12-09 2024-10-09 capacity buildings (local Gov anisms and Capacity Buildin cation Selection ernments, local energy servic g e providers, etc.) BEEPAF-P165405-CQ-28-CS- Support for the Developmen Consultant Qualifi 20-FBIH / Communication an IBRD / 89060 t of Scalable Financing Mech Post Open - National 301,660.93 Signed 2020-05-10 2020-05-07 2020-05-29 2020-06-06 2020-08-03 2020-06-20 2020-10-16 2020-06-22 2020-10-17 2024-04-22 cation Selection d Promotion Public Campaign anisms and Capacity Buildin s g BEEPAF-P165405-CQ-03-CS- Energy Efficiency Investmen Consultant Qualifi 20-FBIH / Design and technic IBRD / 89060 Post Open - National 111,916.78 Signed 2020-07-10 2020-12-17 2020-07-29 2020-08-06 2021-01-26 2020-08-20 2021-02-19 2020-08-22 2021-03-04 2021-02-18 ts in Public Facilities cation Selection al supervision (10 buildings) BEEPAF-P165405-CQ-07-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 22-FBIH / Design and technic IBRD / 89060 Post Open - National 0.00 2022-01-10 2022-01-29 2022-02-06 2022-02-20 2022-02-22 2022-08-21 ts in Public Facilities cation Selection ntation al supervision (10 buildings) BEEPAF-P165405-CQ-29-CS- Energy Efficiency Investmen Consultant Qualifi 20-FBIH / Design and technic IBRD / 89060 Post Open - National 55,048.49 Signed 2020-07-10 2020-05-08 2020-07-29 2020-08-06 2021-01-26 2020-08-20 2021-02-10 2020-08-22 2021-03-04 2021-02-18 ts in Public Facilities cation Selection al supervision (10 buildings) BEEPAF-P165405-CQ-30-CS- Energy Efficiency Investmen Consultant Qualifi 21-FBIH / Design and technic IBRD / 89060 Post Open - National 289,020.60 Signed 2021-01-10 2020-12-17 2021-01-29 2021-02-06 2021-01-26 2021-02-20 2021-02-10 2021-02-22 2021-03-04 2021-08-21 ts in Public Facilities cation Selection al supervision (10 buildings) BEEPAF-P165405-CQ-31-CS- Energy Efficiency Investmen Consultant Qualifi 21-FBIH / Design and technic IBRD / 89060 Post Open - National 35,132.00 Signed 2021-01-10 2020-12-17 2021-01-29 2021-02-06 2021-01-26 2021-02-20 2021-02-19 2021-02-22 2021-03-04 2021-08-21 ts in Public Facilities cation Selection al supervision (5 buildings) BEEPAF-P165405-CQ-32-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 22-FBIH / Design and technic IBRD / 89060 Post Open - National 0.00 2022-01-10 2022-01-29 2022-02-06 2022-02-20 2022-02-22 2022-08-21 ts in Public Facilities cation Selection ntation al supervision (10 buildings) BEEPAF-P165405-CQ-05-CS- Energy Efficiency Investmen Consultant Qualifi 21-FBIH / Design and technic IBRD / 89060 Post Open - National 142,441.79 Signed 2021-06-18 2021-07-29 2021-07-02 2021-07-30 2021-07-12 2021-09-16 2021-07-27 2021-10-07 2021-08-02 2021-11-27 2021-10-31 ts in Public Facilities cation Selection al supervision (11 buildings) BEEPAF-P165405-CQ-33-CS- Energy Efficiency Investmen Consultant Qualifi 21-FBIH / Design and technic IBRD / 89060 Post Open - National 156,534.09 Signed 2021-06-18 2021-07-30 2021-07-02 2021-07-12 2021-09-22 2021-07-27 2021-10-06 2021-08-02 2021-11-27 2021-10-01 ts in Public Facilities cation Selection al supervision (7 objects) BEEPAF-P165405-CQ-06-CS- Energy Efficiency Investmen Consultant Qualifi IBRD / 89060 Post Open - National 42,051.18 Signed 2021-07-30 2021-07-30 2021-08-13 2021-08-23 2021-11-11 2021-09-06 2021-12-01 2021-09-12 2021-12-09 2021-11-11 21-FBIH / Audit of design (7 b ts in Public Facilities cation Selection uildings) BEEPAF-P165405-CQ-02-CS- Energy Efficiency Investmen Consultant Qualifi 21-FBIH / Detailed energy au IBRD / 89060 Post Open - National 199,355.48 Signed 2021-01-10 2021-08-26 2021-01-29 2021-02-06 2021-09-22 2021-02-20 2021-10-06 2021-02-22 2021-11-06 2021-05-23 ts in Public Facilities cation Selection dits - 52 buildings BEEPAF-P165405-CQ-13-CS- Energy Efficiency Investmen Consultant Qualifi IBRD / 89060 Post Open - National 135,918.81 Signed 2021-10-29 2021-12-13 2021-11-12 2021-11-22 2022-02-11 2021-12-06 2022-04-10 2021-12-12 2022-04-16 2022-02-10 21-FBIH / Energy certificates ts in Public Facilities cation Selection BEEPAF-P165405-CQ-21-CS- Support for the Developmen Consultant Qualifi Pending Impleme 21-FBIH / Training for benefic IBRD / 89060 t of Scalable Financing Mech Post Open - National 0.00 2021-10-29 2021-11-12 2021-11-22 2021-12-06 2021-12-12 2022-02-10 cation Selection ntation iaries and energy manageme anisms and Capacity Buildin nts g Page 3 BEEPAF-P165405-CQ-34-CS- 21-FBIH / Stocktaking of all p Support for the Developmen ublic buildings, development t of Scalable Financing Mech Consultant Qualifi IBRD / 89060 Post Open - National 265,077.74 Signed 2021-11-22 2021-12-13 2021-12-06 2021-12-19 2022-03-07 2022-01-08 2022-03-30 2022-01-16 2022-04-25 2022-07-15 of digital map-based platfor anisms and Capacity Buildin cation Selection m, overview of the public buil g dings that need the EE renov ation BEEPAF-P165405-CQ-35-CS- Support for the Developmen 21-FBIH / Assessment of the t of Scalable Financing Mech Consultant Qualifi energy use and energy savin IBRD / 89060 Post Open - National 239,867.10 Signed 2021-11-22 2021-12-13 2021-12-06 2021-12-19 2022-03-07 2022-01-08 2022-03-30 2022-01-16 2022-04-25 2022-07-15 anisms and Capacity Buildin cation Selection gs through EE investment in g eligible public buildings BEEPAF-P165405-CQ-36-CS- Support for the Developmen Consultant Qualifi 21-FBIH / TA to the Revolving IBRD / 89060 t of Scalable Financing Mech Post Open - National 107,010.86 Signed 2021-11-22 2021-12-08 2021-12-06 2021-12-19 2022-03-15 2022-01-08 2022-04-01 2022-01-16 2022-04-16 2022-07-15 cation Selection fund anisms and Capacity Buildin g BEEPAF-P165405-CQ-25-CS- Support for the Developmen Consultant Qualifi 20-FBIH / Capacity building M IBRD / 89060 t of Scalable Financing Mech Post Open - National 118,515.67 Signed 2021-11-22 2021-11-26 2021-12-06 2021-12-19 2022-03-22 2022-01-08 2022-03-08 2022-01-16 2022-04-19 2023-04-11 cation Selection inistry and PIU anisms and Capacity Buildin g BEEPAF-P165405-CQ-26-CS- Support for the Developmen Consultant Qualifi 21-FBIH / Targeted women tr IBRD / 89060 t of Scalable Financing Mech Post Open - National 109,392.87 Signed 2021-11-22 2021-12-08 2021-12-06 2021-12-19 2022-02-11 2021-12-21 2022-03-15 2021-12-29 2022-03-31 2022-06-27 cation Selection aining anisms and Capacity Buildin g BEEPAF-P165405-CQ-27-CS- Support for the Developmen 20-FBIH / Energy efficiency in t of Scalable Financing Mech Consultant Qualifi Under Implement IBRD / 89060 Post Open - National 0.00 2021-11-22 2021-12-08 2021-12-06 2021-12-19 2022-01-08 2022-01-16 2022-07-15 formation system updates (e. anisms and Capacity Buildin cation Selection ation g. EE Revolving fund) g BEEPAF-P165405-CQ-37-CS- Energy Efficiency Investmen Consultant Qualifi 22-FBIH / Design and works s IBRD / 89060 Post Open - National 0.00 Signed 2022-11-22 2022-11-22 2022-12-06 2022-12-16 2023-02-02 2022-12-23 2023-02-20 2022-12-28 2023-03-28 ts in Public Facilities cation Selection upervision (14 objects) BEEPAF-P165405-CQ-38-CS- Energy Efficiency Investmen Consultant Qualifi 22-FBIH / Design and works s IBRD / 89060 Post Open - National 0.00 Signed 2022-11-22 2022-11-22 2022-12-06 2022-12-16 2023-02-02 2022-12-23 2023-02-20 2022-12-28 2023-03-28 ts in Public Facilities cation Selection upervision (11 objects) BEEPAF-P16405-CQ-39-CS-2 Energy Efficiency Investmen Consultant Qualifi IBRD / 89060 Post Open - National 0.00 Signed 2022-11-22 2022-11-22 2022-12-06 2022-12-16 2023-02-02 2022-12-23 2023-02-20 2022-12-28 2023-03-28 2-FBIH / Audit of design (25 o ts in Public Facilities cation Selection bjects) BEEPAF-P165405-CQ-40-CS- Energy Efficiency Investmen Consultant Qualifi Pending Impleme 23-FBIH / Energy certification IBRD / 89060 Post Open - National 0.00 2023-06-20 2023-07-04 2023-07-14 2023-07-21 2023-07-26 2023-10-24 ts in Public Facilities cation Selection ntation (up to 30 objects) BEEPAF-P165405-CQ-41-CS- Support for the Developmen Consultant Qualifi Pending Impleme 23-FBIH / Energy training (up IBRD / 89060 t of Scalable Financing Mech Post Open - National 0.00 2023-06-20 2023-07-04 2023-07-14 2023-07-21 2023-07-26 2023-10-24 cation Selection ntation to 30 objects) anisms and Capacity Buildin g BEEPAF-P165405-CQ-45-CS- Support for the Developmen 23-FBIH / Provision of consult t of Scalable Financing Mech Consultant Qualifi Under Implement ing services related to the de IBRD / 89060 Post Open - National 0.00 2023-05-10 2023-05-10 2023-05-24 2023-06-10 2023-06-13 2023-06-19 2024-01-15 anisms and Capacity Buildin cation Selection ation velopment of Study of altern g ative heating systems in buil dings in FBiH BEEPAF-P165405-CQ-46-CS- 23-FBIH / Provision of consult Support for the Developmen ing services related to the pr t of Scalable Financing Mech Consultant Qualifi Under Implement IBRD / 89060 Post Open - National 0.00 2023-05-10 2023-05-10 2023-05-24 2023-06-10 2023-06-13 2023-07-16 2023-07-31 eparation and organization of anisms and Capacity Buildin cation Selection ation the Second International Con g ference on Energy Efficiency in Public Buildings BEEPAF-P165405-CQ-43-CS- 23-FBIH / Provision of consult ing services related to draftin Support for the Developmen g the amendments and additi t of Scalable Financing Mech Consultant Qualifi Under Implement ons to the Regulation on con IBRD / 89060 Post Open - National 0.00 2023-05-10 2023-05-10 2023-05-24 2023-06-01 2023-06-17 2023-07-07 2024-01-03 anisms and Capacity Buildin cation Selection ation ducting energy audits and iss g uing energy certificates and t o the Rulebook on minimum requirements for the energy characteristics of buildings BEEPAF-P165405-CQ-42-CS- 23-FBIH / Provision of consult Support for the Developmen ing services related to the de t of Scalable Financing Mech Consultant Qualifi Under Implement IBRD / 89060 Post Open - National 0.00 2023-05-10 2023-05-10 2023-05-24 2023-06-10 2023-06-13 2023-07-16 2024-02-11 velopment of the Second Op anisms and Capacity Buildin cation Selection ation erational Plan for improving g energy efficiency in FBiH inst itutions BEEPAF-P165405-CQ-44-CS- 23-FBIH / Provision of consult anting services related to the Support for the Developmen development of the Guidelin t of Scalable Financing Mech Consultant Qualifi Under Implement es for energy renovation of b IBRD / 89060 Post Open - National 0.00 2023-05-10 2023-06-15 2023-05-24 2023-06-10 2023-06-13 2023-06-19 2023-12-16 anisms and Capacity Buildin cation Selection ation uildings, which have the stat g us of a national monument or are located within the scope of the buffer zone of the nati onal monument of the ambie nt en BEEP-P143580-CQ-02-CS-15- FBIH-II / Performing works su Energy Efficiency Investmen Consultant Qualifi Open - Internationa IDA / 53930 Prior 79,112.25 Signed 2015-07-08 2015-12-18 pervision, technical monitori ts in Public Facilities cation Selection l ng and evaluation and energ y labelling BA-BEEP-CQ-08-CS-14-5393 BA-RS- / performing detailed energy audits, monitoring an Energy Efficiency Investmen Consultant Qualifi Open - Internationa d evaluation, technical desig IDA / 53930 Prior 268,186.87 Signed 2015-07-10 2015-07-14 ts in Public Facilities cation Selection l n, supervision and technical documentation for energy la bels for retrofitted public buil dings BA-BEEP-5393BA-QBS-CS-14 -16-RS / Preparation of techni Energy Efficiency Investmen Quality Based Sel Open - Internationa IDA / 53930 Prior 665,521.79 Signed 2016-05-18 2016-05-20 cal design and works supervi ts in Public Facilities ection l sion for retrofitting of public buildings BA-BEEP-CQ-22-CS-14-5393 Energy Efficiency Investmen Consultant Qualifi Open - Internationa BA-RS / communication activi IDA / 53930 Prior 327,450.52 Signed 2015-06-04 2015-06-12 ts in Public Facilities cation Selection l ties services BEEP-P143580-CQ-02-CS-15- FBIH-I / Performing Works Su Energy Efficiency Investmen Consultant Qualifi Open - Internationa IDA / 53930 Prior 13,833.13 Signed 2015-07-08 2015-12-18 pervision, Technical Monitori ts in Public Facilities cation Selection l ng and Evaluation and Energ y Labelling Page 4 BA-BEEP-CQ-08-CS-14-5393 BA-RS / Performing detailed e nergy audits, monitoring and Energy Efficiency Investmen Consultant Qualifi Open - Internationa IDA / 53930 Prior 207,519.34 Signed 2016-06-15 2015-07-14 evaluation, technical design, ts in Public Facilities cation Selection l supervision and technical do cumentation for energy label s for retrofitted public buildin gs BEEP-P143580-CQ-05-CS-15- FBIH I and II / Consulting serv Energy Efficiency Investmen Consultant Qualifi Open - Internationa ices to perform design, techn IDA / 53930 Prior 300,008.87 Signed 2016-02-12 2016-02-16 ts in Public Facilities cation Selection l ical monitoring services - (be fore and after ) Works Superv ision BEEPP143580CQ-05-CS-15-F BIH I and II / Design and tech Energy Efficiency Investmen Consultant Qualifi Open - Internationa IDA / 53930 Prior 246,401.84 Signed 2016-02-12 2016-02-16 nical monitoring ( Lump Sum ts in Public Facilities cation Selection l ) and Supervision ( Time Bas ed) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BEEPAF-P165405-IC-16-CS-2 Support for the Developmen 0-FBIH / Development / Tech t of Scalable Financing Mech Individual Consult IBRD / 89060 Post Limited 27,391.12 Signed 2020-05-10 2020-06-09 2020-05-15 2020-09-09 2020-06-20 2020-10-22 2020-06-22 2020-10-23 2024-04-22 nical Assistance for EE Revol anisms and Capacity Buildin ant Selection ving fund / Revolving Fund E g xpert BEEPAF-P165405-IC-17-CS-2 Support for the Developmen 0-FBIH / Development / Tech t of Scalable Financing Mech Individual Consult IBRD / 89060 Post Limited 19,356.37 Signed 2020-05-10 2020-06-09 2020-05-15 2020-09-09 2020-06-20 2020-10-22 2020-06-22 2020-10-23 2024-04-22 nical Assistance for EE Revol anisms and Capacity Buildin ant Selection ving fund /Financial Expert g BEEPAF-P165405-IC-18-CS-2 Support for the Developmen 0-FBIH / Development / Tech t of Scalable Financing Mech Individual Consult IBRD / 89060 Post Limited 17,832.76 Signed 2020-05-10 2020-07-23 2020-05-15 2020-09-09 2020-06-20 2020-10-22 2020-06-22 2020-10-23 2024-04-22 nical Assistance for EE Revol anisms and Capacity Buildin ant Selection ving fund /Policy & Regulator g y Expert BEEPAF-P165405-IC-19-CS-2 Support for the Developmen 0-FBIH / Development / Tech t of Scalable Financing Mech Individual Consult IBRD / 89060 Post Limited 25,448.73 Signed 2020-05-10 2020-06-09 2020-05-15 2020-09-10 2020-06-20 2020-10-22 2020-06-22 2020-10-23 2024-04-22 nical Assistance for EE Revol anisms and Capacity Buildin ant Selection ving fund / Technical Expert g BEEPAF-P165405-IC-07-CS-2 Individual Consult IBRD / 89060 Project Management Post Limited 102,941.57 Signed 2020-05-01 2020-02-21 2020-05-01 2020-05-08 2020-06-06 2020-05-18 2020-06-08 2020-05-19 2024-05-01 0-FBIH / Contract Manageme ant Selection nt Expert BEEPAF-P165405-IC-08-CS-2 Individual Consult IBRD / 89060 Project Management Post Limited 54,633.24 Signed 2020-05-01 2020-02-18 2020-05-01 2020-05-08 2020-06-06 2020-05-18 2020-06-08 2020-05-19 2024-05-01 0-FBIH / Administrative Assist ant Selection ant BEEPAF-P165405-IC-01-CS-2 Individual Consult IBRD / 89060 Project Management Prior Direct 121,680.15 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 0-FBIH / Project Leader ant Selection BEEPAF-P165405-IC-05-CS-2 Individual Consult IBRD / 89060 Project Management Prior Direct 96,181.67 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 0-FBIH / Technical Expert II ant Selection BEEPAF-P165405-IC-04-CS-2 Individual Consult IBRD / 89060 Project Management Prior Direct 96,181.67 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 0-FBIH / Technical Expert I ant Selection BEEPAF-P165405-IC-06-CS-2 Individual Consult IBRD / 89060 Project Management Prior Direct 96,181.67 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 0-FBIH / Technical Expert III ant Selection BEEPAF-P165405-IC-02-CS-2 Individual Consult IBRD / 89060 Project Management Prior Direct 96,181.67 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 0-FBIH / Procurement Special ant Selection ist BEEPAF-P165405-IC-03-CS-2 Individual Consult 0-FBIH / Financial Manageme IBRD / 89060 Project Management Prior Direct 96,181.67 Signed 2020-05-10 2020-06-04 2020-05-23 2020-06-04 2020-06-06 2020-06-08 2020-06-08 2020-06-10 2024-05-01 ant Selection nt Specialist BEEPAF-P165405-IC-20-CS-2 3-FBIH / Provision of consulti ng services related to the str Support for the Developmen engthening of institutional fr t of Scalable Financing Mech Individual Consult Under Implement amework and the energy effi IBRD / 89060 Post Limited 0.00 2023-05-16 2023-06-16 2023-05-21 2023-05-31 2023-06-06 2023-12-03 anisms and Capacity Buildin ant Selection ation ciency management system g capacity development throug h design of the feasibility stu dy for establishment of the E nergy Efficiency Agency in F ederat BEEPAF-P165405-IC-21-CS-2 3-FBIH / Consultant services r Support for the Developmen elated to the diversifying fun t of Scalable Financing Mech Individual Consult Under Implement IBRD / 89060 Post Limited 0.00 2023-05-23 2023-05-28 2023-06-07 2023-06-13 2023-12-10 ding sources for financing im anisms and Capacity Buildin ant Selection ation provements in public sector g buildings in Federation of Bos nia and Herzegovina . P143580-BA-BEEP-5393BA- Energy Efficiency Investmen Individual Consult IC-CS-15-26-RS / Procuremen IDA / 53930 Prior Open 33,928.37 Signed 2017-11-06 2017-11-02 ts in Public Facilities ant Selection t Manager BEEP-P143580-IC-24-CS-14- FBIH / FOR PROJECT COORDI Energy Efficiency Investmen Individual Consult NATOR (PC) IN THE IMPLEME IDA / 53930 Prior Open 154,133.89 Terminated 2015-11-28 2015-12-17 ts in Public Facilities ant Selection NTATION UNIT OF THE FEDER ATION MINISTRY OF PHYSICA L PLANNING BEEP-P I 43580-SSS-28-CS-1 Energy Efficiency Investmen S-FBIH / Consulting services f IDA / 53930 Prior Direct Selection Direct 9,881.71 Signed 2015-12-17 ts in Public Facilities or Financial software procure ment BEEP-P143580-IC-06-CS-14- Energy Efficiency Investmen Individual Consult Under Implement IDA / 55380 Prior Open 0.00 2017-05-09 FBIH / FINANCIAL SPECIALIST ts in Public Facilities ant Selection ation BEEP-P143580-IC-005-FBIH / Technical Expert I in the Proj Energy Efficiency Investmen Individual Consult IDA / 53930 Prior Open 99,378.05 Terminated 2015-11-28 2015-12-17 ect Implementation Unit of th ts in Public Facilities ant Selection e Federation Ministry of Physi cal Planning BEEP-P143580-IC-26-CS-14- Energy Efficiency Investmen Individual Consult IDA / 53930 Prior Open 99,378.05 Terminated 2015-11-28 2015-12-17 FBH / Technical Expert ts in Public Facilities ant Selection Page 5 BEEP-P143580-IC-27-CS-14- FBH / For a Administrative As Energy Efficiency Investmen Individual Consult sistant in the Project Implem IDA / 53930 Prior Open 42,932.38 Canceled 2015-11-28 ts in Public Facilities ant Selection entation Unit of the Federatio n Ministry of Physical Plannin g BEEP-P143580-IC-003-FBIH / For a Administrative Assistan Energy Efficiency Investmen Individual Consult t in the Project Implementati IDA / 53930 Prior Open 37,108.18 Terminated 2015-12-22 2015-12-17 ts in Public Facilities ant Selection on Unit of the Federation Min istry of Physical Planning P143580-BA-BEEP-5393BA-I Energy Efficiency Investmen Individual Consult C-CS-15-25-RS / ACCOUNTAN IDA / 53930 Prior Open 67,137.44 Signed 2015-06-18 2015-08-02 ts in Public Facilities ant Selection T AND DISBURSEMENT SPECI ALIST BEEP-P143580-IC-25-CS-14- Energy Efficiency Investmen Individual Consult IDA / 53930 Prior Open 132,009.13 Terminated 2015-11-28 2015-12-17 FBIH / Procurement Specialist ts in Public Facilities ant Selection Page 6 PROCUREMENT PLAN (Textual Part) Project information: Social Safety Net Project (P167416) Project Implementation agency: Ministry of Social Inclusion and Equity (MIES) Unidad del Registro Social Date of the Procurement Plan: September 9, 2019 Period covered by this Procurement Plan: 2019 - 2022 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. For the implementation of Component 1, the MIES may use the Country’s own procurement procedures for “Menor Cuantía,” “Infima Cuantía,” “Ferias Inclusivas” and “C atalogo Electronico Inclusivo” to procure the goods and services identified, those procedures will be complemented by specific processes and procedures established in the Operational Manual. PROCUREMENT Ecuador : Social Safety Net Project PLAN General Information Country: Ecuador 2020-01-06 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167416 GPN Date: 2020-02-03 Project Name: Social Safety Net Project Loan / Credit No: IBRD / 89460 Ministry of Economic and Social Inclusion Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2-MIES-7 / Adquisición de t ablets para educadoras CNH Component 2: Technical Assi Open - Internationa Single Stage - One E y repotenciación de la infraes IBRD / 89460 stance for Capacity Building Post Request for Bids 3,251,166.98 0.00 Canceled 2020-02-24 2020-04-09 2020-05-29 2020-06-28 2020-07-21 2020-09-19 l nvelope tructura tecnológica y los sist & Monitoring and Evaluation emas de información del MIE S. C2-MIES-42 / Adquisición de Component 2: Technical Assi impresora multifunción para l Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 3,000.00 0.00 Canceled 2020-02-27 2020-04-14 2020-04-29 a gestión del Equipo Ejecutor tions nvelope & Monitoring and Evaluation del Proyecto (MIES) C2-MIES-INEC-10 / Adquisici ón de equipos informáticos, t Component 2: Technical Assi Single Stage - One E Pending Impl ablets necesarios para el lev IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 58,562.53 0.00 2022-02-28 2022-03-11 2022-04-04 2022-04-18 2022-05-02 2022-06-16 nvelope ementation antamiento de información d & Monitoring and Evaluation e la Encuesta Nacional de De snutrición Infantil C2-MIES-INEC-11 / Adquisici ón de hemoglobinómetros, e quipos analizadores de hemo Component 2: Technical Assi globina cuantitativo, con sus Single Stage - One E IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 91,936.14 78,722.00 Signed 2022-02-28 2022-04-01 2022-03-11 2022-04-01 2022-04-04 2022-04-21 2022-04-18 2022-05-05 2022-05-02 2022-05-26 2022-06-16 insumos médicos y de limpie nvelope & Monitoring and Evaluation za, necesarios para el desarrollo de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-6 / Adquisició n de vestimenta identificativ a para el operativo de campo Component 2: Technical Assi Request for Quota Single Stage - One E , necesaria para la operación IBRD / 89460 stance for Capacity Building Post Open - National 21,833.78 19,368.20 Signed 2022-03-09 2022-04-06 2022-04-14 2022-06-01 2022-05-14 tions nvelope estadística para el desarrollo & Monitoring and Evaluation de las actividades de la Encu esta Nacional de Desnutrició n Infantil C2-MIES-INEC-7 / Adquisició n de suministros de oficina y Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple papelería para el desarrollo d IBRD / 89460 stance for Capacity Building Post Open - National 3,220.43 0.00 2022-03-09 2022-06-22 2022-04-14 2022-05-14 tions nvelope mentation e las actividades de la Encue & Monitoring and Evaluation sta Nacional de Desnutrición Infantil C2-MIES-INEC-9 / Adquisició Component 2: Technical Assi n de los suministros médicos, Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 20,496.56 18,821.87 Signed 2022-03-09 2022-04-26 2022-04-15 2022-05-31 2022-05-15 necesarios para el desarrollo tions nvelope & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-20 / Suministr os de impresión (materiales Component 2: Technical Assi de impresión) y repuestos (re Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 31,523.17 27,653.55 Signed 2022-03-30 2022-04-04 2022-04-27 2022-05-31 2022-06-11 puestos y accesorios) para el tions nvelope & Monitoring and Evaluation desarrollo de las actividades de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-39 / Compra d e insumos para arrojar los de Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl sechos de las pruebas técnic IBRD / 89460 stance for Capacity Building Post Open - National 2,763.81 0.00 2022-09-14 2022-11-09 2022-11-23 tions nvelope ementation as de la encuesta de desnutri & Monitoring and Evaluation ción infantil (fundas para des echo) C2-MIES-INEC-43 / Adquisici ón de suministros de impresi Component 2: Technical Assi ón y repuestos (materiales d Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 24,640.00 0.00 Canceled 2022-09-11 2022-10-09 2022-11-23 e impresión, repuestos y acc tions nvelope & Monitoring and Evaluation esorios), para la Encuesta Na cional de Desnutrición Infanti l, fase encuesta C2-MIES-INEC-44 / Adquisici ón de equipos informáticos, d Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple ispositivos móviles para el le IBRD / 89460 stance for Capacity Building Post Open - National 33,984.16 0.00 2022-09-14 2022-10-14 2022-10-21 2022-11-25 tions nvelope mentation vantamiento de información & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-38 / Adquisici ón de equipos informáticos c on sus respectivos mantenim Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl iento preventivos, necesarios IBRD / 89460 stance for Capacity Building Post Open - National 42,560.00 0.00 2022-09-21 2022-10-28 2022-11-18 tions nvelope ementation para el personal que implem & Monitoring and Evaluation enta el proyecto para la Encu esta Nacional de Desnutrició n Infantil C2-MIES-INEC-41 / Adquisici ón de suministros de oficina Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl y papelería para el desarrollo IBRD / 89460 stance for Capacity Building Post Open - National 63,097.72 0.00 2022-11-24 2022-12-30 2023-01-29 tions nvelope ementation de las actividades de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil, fase de encuest Page 1 C2-MIES-INEC-43-1 / Adquisi ción de suministros de impre Component 2: Technical Assi sión y repuestos (materiales Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 92,279.08 0.00 2022-11-18 2022-11-24 2022-12-19 2022-12-26 2022-12-30 2023-06-28 de impresión, repuestos y ac nvelope ementation & Monitoring and Evaluation cesorios), para la Encuesta N acional de Desnutrición Infan til, fase encuesta C2-MIES-INEC-40 / Compra i nsumos para las pruebas de Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple cloro e E-coli en agua dentro IBRD / 89460 stance for Capacity Building Post Open - National 1,507.16 0.00 2022-09-14 2022-12-10 2022-11-09 2022-11-23 tions nvelope mentation de la Encuesta Nacional de D & Monitoring and Evaluation esnutrición Infantil (botellas de agua) C2-MIES-INEC-42 / Adquisici ón de equipos e insumos mé dicos y químicos para la aplic Component 2: Technical Assi ación de pruebas de calidad Single Stage - One E Under Imple IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 180,117.60 0.00 2022-12-02 2022-12-09 2022-12-07 2022-12-10 2022-12-30 2022-12-16 2023-01-09 2022-12-21 2023-01-30 2023-03-16 de agua (cloro - e-coli) y prue nvelope mentation & Monitoring and Evaluation bas de anemia en sangre, inc luye suministros de limpieza para la Encuesta Nacional de Desnutrición Infantil C2-MIES-INEC-68 / Adquisici ón de suministros de oficina Component 2: Technical Assi Single Stage - One E Under Imple y papelería para el desarrollo IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 97,607.95 0.00 2023-04-30 2023-05-02 2023-05-05 2023-05-03 2023-06-16 2023-05-08 2023-07-16 2023-08-20 2024-02-16 nvelope mentation de las actividades de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil, fase de encuesta C2-MIES-INEC-69 / Adquisici ón de equipos e insumos mé dicos y químicos para la aplic Component 2: Technical Assi ación de pruebas de calidad Open - Internationa Single Stage - One E Under Imple IBRD / 89460 stance for Capacity Building Post Request for Bids 507,282.35 0.00 2023-03-15 2023-05-02 2023-03-20 2023-05-03 2023-05-01 2023-05-10 2023-05-31 2023-07-05 2024-01-01 de agua (cloro - e-coli) y prue l nvelope mentation & Monitoring and Evaluation bas de anemia en sangre, inc luye suministros de limpieza para la Encuesta Nacional de Desnutrición Infantil C2-MIES-INEC-71 / Adquisici ón de suministros de impresi Component 2: Technical Assi ón y repuestos (materiales d Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 92,276.84 0.00 2023-05-15 2023-05-20 2023-07-01 2023-07-31 2023-09-04 2024-03-02 e impresión, repuestos y acc nvelope ementation & Monitoring and Evaluation esorios), para la Encuesta Na cional de Desnutrición Infanti l, fase encuesta C2-MIES-INEC-77 / Adquisici Component 2: Technical Assi ón equipo informático, comp Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 67,200.00 0.00 2023-04-15 2023-04-20 2023-06-01 2023-07-01 2023-08-05 2024-02-01 utadoras para la implementa nvelope ementation & Monitoring and Evaluation ción del proyecto C2-MIES-INEC-73 / Adquisici ón de insumos para las prueb Component 2: Technical Assi Request for Quota Single Stage - One E as de cloro e E-coli en agua d IBRD / 89460 stance for Capacity Building Post Open - National 3,360.00 0.00 Signed 2023-03-20 2023-04-13 2023-05-15 2023-11-11 tions nvelope entro de la Encuesta Naciona & Monitoring and Evaluation l de Desnutrición Infantil (bo tellas de agua) C2-MIES-INEC-72 / Compra d e insumos para arrojar los de Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl sechos de las pruebas técnic IBRD / 89460 stance for Capacity Building Post Open - National 2,262.21 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation as de la encuesta de desnutri & Monitoring and Evaluation ción infantil (fundas para des echo) C2-MIES-INEC-85 / Adquisici Component 2: Technical Assi Single Stage - One E Pending Impl ón de vestimenta identificati IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 78,948.81 0.00 2023-06-15 2023-06-20 2023-08-01 2023-08-31 2023-10-05 2023-12-31 nvelope ementation va para el operativo de camp & Monitoring and Evaluation o 2023 C2-MIES-93 / “ADQUISICIÓN DE EQUIPOS INFORMÁTICOS PARA LA MEJORA EN EJECUCI Component 2: Technical Assi Single Stage - One E Under Imple ON DEL PROCESO DE EXCLU IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 114,456.16 0.00 2023-06-15 2023-06-01 2023-06-30 2023-08-11 2023-09-10 2023-10-15 2024-04-12 nvelope mentation SIONES E INCLUSIONES DE B & Monitoring and Evaluation ENEFICIARIOS DE LAS TRANS FERENCIAS MONETARIAS AD MINISTRADAS POR LA SANCC O” NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2-MIES-58 / CONTRATACIÓ Component 2: Technical Assi N DE OPERADORAS DE SERVI Open - Internationa Single Stage - One E IBRD / 89460 stance for Capacity Building Post Request for Bids 3,080,000.00 0.00 Canceled 2021-01-25 2021-03-11 2021-04-29 2021-05-26 2021-07-08 2022-07-08 CIOS INTEGRADOS DE INCLU l nvelope & Monitoring and Evaluation SIÓN ECONÓMICA C2-MIES-16 / Campaña de co municación que mitigue los e fectos de la Refocalizacion d Component 2: Technical Assi e los Nucleos Familiares en lo Single Stage - One E IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 900,000.00 0.00 Canceled 2020-01-30 2020-02-04 2020-03-18 2020-04-17 2020-05-12 2020-12-08 s Programas Sociales por la a nvelope & Monitoring and Evaluation plicación del nuevo Formulari o e indice del Registro Social- posibles tensiones provenien tes del cambio de legibilidad de los C2-MIES-INEC-1 / Contrataci ón del servicio de impresión Component 2: Technical Assi Request for Quota Single Stage - One E de stickers, requeridos para IBRD / 89460 stance for Capacity Building Post Open - National 1,983.91 1,960.00 Signed 2022-03-09 2022-04-06 2022-06-10 2022-04-21 tions nvelope el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-3 / Servicio de transporte en camionetas con conductor, Component 2: Technical Assi Single Stage - One E necesario para el desarrollo IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 202,507.20 466,715.20 Signed 2022-02-28 2022-03-11 2022-03-09 2022-03-11 2022-03-24 2022-03-25 2022-04-05 2022-04-06 2022-04-14 2022-04-29 2022-08-12 nvelope del & Monitoring and Evaluation operativo de campo de la Encuesta Nacional de Desnutrición Infantil C2-MIES-INEC-8 / Suministro s de impresión (materiales d Component 2: Technical Assi e impresión) y repuestos (rep Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 31,523.17 0.00 Canceled 2022-03-09 2022-04-12 2022-05-27 uestos y accesorios) para el tions nvelope & Monitoring and Evaluation desarrollo de las actividades de la Encuesta Nacional de D esnutrición Infantil Page 2 C2-MIES-INEC-12 / Contratac ión de 12 Encuestador - Antr Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple opometrista ENDI para el ope IBRD / 89460 stance for Capacity Building Post Open - National 29,728.82 0.00 2022-05-03 2022-06-15 2022-08-15 tions nvelope mentation rativo de campo de la Encues & Monitoring and Evaluation ta Nacional de Desnutrición I nfantil C2-MIES-INEC-14 / Contratac ión de 47 Encuestadores de Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple Enlistamiento para el operati IBRD / 89460 stance for Capacity Building Post Open - National 213,523.71 0.00 2022-03-04 2022-04-15 2022-08-15 tions nvelope mentation vo de campo de la Encuesta & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-15 / Contratac ión de 4 Operadores Cartogr Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple áficos de Enlistamiento para IBRD / 89460 stance for Capacity Building Post Open - National 13,224.96 0.00 2022-03-04 2022-04-15 2022-08-15 tions nvelope mentation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-16 / Contratac ión de 44 Revisores de contr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl ol de calidad ENDI para el op IBRD / 89460 stance for Capacity Building Post Open - National 67,020.80 0.00 2022-05-04 2022-06-15 2022-08-15 tions nvelope ementation erativo de campo de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil C2-MIES-INEC-17 / Contratac ión de 8 Revisores de control Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple de calidad de Enlistamiento p IBRD / 89460 stance for Capacity Building Post Open - National 24,371.20 0.00 2022-03-04 2022-04-15 2022-08-15 tions nvelope mentation ara el operativo de campo de & Monitoring and Evaluation la Encuesta Nacional de Desn utrición Infantil C2-MIES-INEC-13 / Contratac Component 2: Technical Assi ión de 24 Encuestadores END Request for Quota Single Stage - One E Under Imple IBRD / 89460 stance for Capacity Building Post Open - National 59,457.64 0.00 2022-05-03 2022-06-15 2022-08-15 I para el operativo de campo tions nvelope mentation & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-18 / Contratac ión de 12 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl erativo de campo ENDI para IBRD / 89460 stance for Capacity Building Post Open - National 31,287.86 0.00 2022-05-04 2022-06-15 2022-08-15 tions nvelope ementation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-19 / Contratac ión de 16 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple erativo de campo de Enlista IBRD / 89460 stance for Capacity Building Post Open - National 76,874.28 0.00 2022-03-04 2022-04-15 2022-08-15 tions nvelope mentation miento para el operativo de c & Monitoring and Evaluation ampo de la Encuesta Nacion al de Desnutrición Infantil C2-MIES-INEC-2 / Contrataci ón de una agencia de viajes Component 2: Technical Assi para la provisión de pasajes Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 19,756.80 0.00 Canceled 2022-03-09 2022-04-14 2022-04-12 2022-12-23 aéreos en rutas nacionales p tions nvelope & Monitoring and Evaluation ara el operativo de campo de la Encuesta Nacional de Desn utrición Infantil C2-MIES-INEC-2-2 / Contrata ción de una agencia de viaje Component 2: Technical Assi s para la provisión de pasaje Request for Quota Single Stage - One E IBRD / 89460 stance for Capacity Building Post Open - National 19,619.60 21,912.80 Signed 2022-05-26 2022-06-17 2022-06-29 2022-07-23 2022-12-30 s aéreos en rutas nacionales tions nvelope & Monitoring and Evaluation para el operativo de campo d e la Encuesta Nacional de De snutrición Infantil C2-MIES-INEC-21 / Servicio d e impresión de material infor Component 2: Technical Assi Request for Quota Single Stage - One E Under Imple mativo y de trabajo a ser dist IBRD / 89460 stance for Capacity Building Post Open - National 7,506.29 0.00 2022-09-15 2022-10-24 2022-10-08 2022-11-08 tions nvelope mentation ribuido durante el levantamie & Monitoring and Evaluation nto de la Encuesta Nacional de Desnutrición Infantil C2-MIES-INEC-27 / Contratac ión de 16 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl erativo de campo de Enlista IBRD / 89460 stance for Capacity Building Post Open - National 70,265.96 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation miento para el operativo de c & Monitoring and Evaluation ampo de la Encuesta Nacion al de Desnutrición Infantil C2-MIES-INEC-28 / Contratac ión de 8 Operadores Cartogr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl áficos de Enlistamiento para IBRD / 89460 stance for Capacity Building Post Open - National 21,931.39 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-29 / Contratac ión de 8 Revisores de control Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl de calidad de Enlistamiento p IBRD / 89460 stance for Capacity Building Post Open - National 21,121.71 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation ara el operativo de campo de & Monitoring and Evaluation la Encuesta Nacional de Desn utrición Infantil C2-MIES-INEC-30 / Contratac ión de 12 Encuestador - Antr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl opometrista ENDI para el ope IBRD / 89460 stance for Capacity Building Post Open - National 53,924.86 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation rativo de campo de la Encues & Monitoring and Evaluation ta Nacional de Desnutrición I nfantil C2-MIES-INEC-31 / Contratac ión de 44 Revisores de contr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl ol de calidad ENDI para el op IBRD / 89460 stance for Capacity Building Post Open - National 122,871.47 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation erativo de campo de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil C2-MIES-INEC-32 / Contratac ión de 12 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl erativo de campo ENDI para IBRD / 89460 stance for Capacity Building Post Open - National 56,783.10 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-33 / Contratac Component 2: Technical Assi ión de 24 Encuestadores END Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 107,849.73 0.00 2022-09-13 2022-09-30 2022-12-30 I para el operativo de campo tions nvelope ementation & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-34 / Contratac ión de 47 Encuestadores de Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl Enlistamiento para el operati IBRD / 89460 stance for Capacity Building Post Open - National 195,226.15 0.00 2022-09-13 2022-09-30 2022-12-30 tions nvelope ementation vo de campo de la Encuesta & Monitoring and Evaluation Nacional de Desnutrición Infa ntil Page 3 C2-MIES-INEC-35 / Contratac Component 2: Technical Assi ión de 3 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 11,595.36 0.00 2022-09-13 2022-09-30 2022-12-30 e Campo 1 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-36 / Contratac Component 2: Technical Assi ión de 2 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 9,502.08 0.00 2022-09-13 2022-09-30 2022-12-30 e Campo 2 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-37 / Contratac Component 2: Technical Assi ión de 2 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 13,139.84 0.00 2022-09-13 2022-09-30 2022-12-30 e Campo 3 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-22 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi el desarrollo del operativo d IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 202,977.60 0.00 Canceled 2022-09-09 2022-09-13 2022-10-21 2022-12-31 e campo de la Encuesta Naci & Monitoring and Evaluation onal de Desnutrición Infantil, periodo: octubre-diciembre 2 022 C2-MIES-INEC-45 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi el desarrollo del operativo de Under Imple IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 53,155.20 0.00 2022-10-11 2022-10-11 2022-10-15 2022-10-17 2022-11-10 2022-12-31 campo de la Encuesta Nacion mentation & Monitoring and Evaluation al de Desnutrición Infantil, pe riodo: octubre-diciembre 202 2 (Planta Central - Quito - Enl istamiento y Encuesta) C2-MIES-INEC-46 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi el desarrollo del operativo de Under Imple IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 23,049.60 0.00 2022-10-11 2022-10-11 2022-10-15 2022-10-17 2022-11-10 2022-12-31 campo de la Encuesta Nacion mentation & Monitoring and Evaluation al de Desnutrición Infantil, pe riodo: octubre-diciembre 202 2 (Litoral - Guayaquil – Enlist amiento) C2-MIES-INEC-47 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi Under Imple el desarrollo del operativo de IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 18,816.00 0.00 2022-10-11 2022-10-11 2022-10-15 2022-10-17 2022-11-10 2022-12-31 mentation campo de la Encuesta Nacion & Monitoring and Evaluation al de Desnutrición Infantil, pe riodo: octubre-diciembre 202 2 (Litoral – Guayaquil – Encue sta) C2-MIES-INEC-48 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi el desarrollo del operativo de Under Imple IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 41,865.60 0.00 2022-10-11 2022-10-11 2022-10-15 2022-10-17 2022-11-10 2022-12-31 campo de la Encuesta Nacion mentation & Monitoring and Evaluation al de Desnutrición Infantil, pe riodo: octubre-diciembre 202 2 (Centro - Ambato – Enlista miento y Encuesta) C2-MIES-INEC-49 / Servicio d e transporte en camionetas c on conductor, necesario para Component 2: Technical Assi el desarrollo del operativo de Under Imple IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 41,865.60 0.00 2022-10-11 2022-10-11 2022-10-15 2022-10-17 2022-11-10 2022-12-31 campo de la Encuesta Nacion mentation & Monitoring and Evaluation al de Desnutrición Infantil, pe riodo: octubre-diciembre 202 2 (Sur - Cuenca – Enlistamien to y Encuesta) C2-MIES-INEC-50 / Contratac ión de una agencia de viaje p Component 2: Technical Assi ara la provisión de pasajes a Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 46,368.00 0.00 2022-11-25 2022-12-29 2023-12-29 éreos en rutas nacionales par tions nvelope ementation & Monitoring and Evaluation a el operativo de campo de l a Encuesta Nacional de Desn utrición Infantil año 2023 C2-MIES-INEC-51 / Contratac ión de 16 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl erativo de campo de Enlista IBRD / 89460 stance for Capacity Building Post Open - National 230,640.75 0.00 2022-11-15 2022-12-27 2023-12-28 tions nvelope ementation miento para el operativo de c & Monitoring and Evaluation ampo de la Encuesta Nacion al de Desnutrición Infantil C2-MIES-INEC-52 / Contratac ión de 8 Operadores Cartogr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl áficos de Enlistamiento para IBRD / 89460 stance for Capacity Building Post Open - National 79,358.72 0.00 2022-11-22 2022-12-30 2023-12-29 tions nvelope ementation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-53 / Contratac ión de 8 Revisores de control Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl de calidad de Enlistamiento p IBRD / 89460 stance for Capacity Building Post Open - National 73,122.56 0.00 2022-11-18 2022-12-28 2023-12-28 tions nvelope ementation ara el operativo de campo de & Monitoring and Evaluation la Encuesta Nacional de Desn utrición Infantil C2-MIES-INEC-54 / Contratac ión de 12 Encuestador - Antr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl opometrista ENDI para el ope IBRD / 89460 stance for Capacity Building Post Open - National 178,386.35 0.00 2022-11-23 2022-12-29 2023-12-29 tions nvelope ementation rativo de campo de la Encues & Monitoring and Evaluation ta Nacional de Desnutrición I nfantil C2-MIES-INEC-55 / Contratac ión de 44 Revisores de contr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl ol de calidad ENDI para el op IBRD / 89460 stance for Capacity Building Post Open - National 402,174.08 0.00 2022-11-23 2022-12-30 2023-12-28 tions nvelope ementation erativo de campo de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil C2-MIES-INEC-56 / Contratac ión de 12 Supervisores de op Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl erativo de campo ENDI para IBRD / 89460 stance for Capacity Building Post Open - National 187,740.59 0.00 2022-11-22 2022-12-30 2023-12-28 tions nvelope ementation el operativo de campo de la & Monitoring and Evaluation Encuesta Nacional de Desnut rición Infantil C2-MIES-INEC-57 / Contratac Component 2: Technical Assi ión de 24 Encuestadores END Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 356,772.70 0.00 2022-11-23 2022-12-29 2023-12-29 I para el operativo de campo tions nvelope ementation & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil Page 4 C2-MIES-INEC-58 / Contratac ión de 47 Encuestadores de Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl Enlistamiento para el operati IBRD / 89460 stance for Capacity Building Post Open - National 640,623.76 0.00 2022-11-23 2022-12-29 2023-12-29 tions nvelope ementation vo de campo de la Encuesta & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-59 / Contratac Component 2: Technical Assi ión de 3 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 39,758.88 0.00 2022-11-22 2022-12-30 2023-12-29 e Campo 1 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-60 / Contratac Component 2: Technical Assi ión de 2 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 32,580.80 0.00 2022-11-22 2022-12-30 2023-12-29 e Campo 2 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-61 / Contratac Component 2: Technical Assi ión de 2 Analistas Técnicos d Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 45,053.12 0.00 2022-11-22 2022-12-30 2023-12-29 e Campo 3 para la Encuesta tions nvelope ementation & Monitoring and Evaluation Nacional de Desnutrición Infa ntil C2-MIES-INEC-62 / Contratac ión de 40 técnicos especializ Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl ados y servicios profesionale IBRD / 89460 stance for Capacity Building Post Open - National 99,455.36 0.00 2022-11-22 2022-12-30 2023-12-29 tions nvelope ementation s para implementar el proyec & Monitoring and Evaluation to de la Encuesta Nacional d e Desnutrición Infantil C2-MIES-81 / Servicio de tra nsporte en camionetas con c Component 2: Technical Assi onductor, necesario para el d Single Stage - One E Under Imple IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 798,004.40 0.00 2022-11-29 2022-12-09 2022-11-30 2022-12-10 2022-12-15 2022-12-20 2022-12-29 2023-11-29 esarrollo del operativo de ca nvelope mentation & Monitoring and Evaluation mpo de la Encuesta Nacional de Desnutrición Infantil, peri odo: enero-noviembre 2023 C2-MIES-INEC-63 / Servicio d e transporte necesario para e Component 2: Technical Assi l desarrollo del operativo de Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 55,080.00 0.00 2023-03-15 2023-03-20 2023-05-01 2023-05-31 2023-07-05 2024-01-01 campo de la Encuesta Nacion nvelope ementation & Monitoring and Evaluation al de Desnutrición Infantil par a la provincia de Galápagos CS-MIES-INEC-64 / Servicio d e transporte en camionetas c Component 2: Technical Assi on conductor, necesario para Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 65,365.00 0.00 2023-10-15 2023-10-20 2023-12-01 2023-12-31 2024-02-04 2024-08-02 el desarrollo del operativo d nvelope ementation & Monitoring and Evaluation e campo de la Encuesta Naci onal de Desnutrición Infantil, periodo diciembre 2023 C2-MIES-INEC-83 / Mantenim Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl iento de equipos informático IBRD / 89460 stance for Capacity Building Post Open - National 2,240.00 0.00 2023-04-20 2023-06-15 2023-12-12 tions nvelope ementation s & Monitoring and Evaluation C2-MIES-INEC-80 / Contratac ión de 4 Supervisores de ope Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl rativo de campo ENDI para el IBRD / 89460 stance for Capacity Building Post Open - National 45,824.00 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation operativo de campo de la En & Monitoring and Evaluation cuesta Nacional de Desnutric ión Infantil C2-MIES-INEC-75 / Contratac ión de 3 Encuestadores - Antr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl opometristas ENDI para el op IBRD / 89460 stance for Capacity Building Post Open - National 19,846.80 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation erativo de campo de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil (Galápagos) C2-MIES-INEC-76 / Contratac ión de 3 Supervisores de ope Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl rativo de campo ENDI para el IBRD / 89460 stance for Capacity Building Post Open - National 21,099.60 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation operativo de campo de la En & Monitoring and Evaluation cuesta Nacional de Desnutric ión Infantil (Galápagos) C2-MIES-INEC-81 / Contratac Component 2: Technical Assi ión de 1 Analista Técnico DA Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 12,120.00 0.00 2023-03-20 2023-05-15 2023-11-11 RH 2 para la Encuesta Nacio tions nvelope ementation & Monitoring and Evaluation nal de Desnutrición Infantil C2-MIES-INEC-78 / Contratac Component 2: Technical Assi ión de 8 Encuestadores ENDI Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 87,008.00 0.00 2023-03-20 2023-05-15 2023-11-11 para el operativo de campo d tions nvelope ementation & Monitoring and Evaluation e la Encuesta Nacional de De snutrición Infantil C2-MIES-INEC-82 / Contratac Component 2: Technical Assi ión de 1 Analista Técnico de Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 16,760.00 0.00 2023-03-20 2023-05-15 2023-11-11 Campo 3 para la Encuesta N tions nvelope ementation & Monitoring and Evaluation acional de Desnutrición Infan til C2-MIES-INEC-79 / Contratac ión de 4 Encuestadores - Antr Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl opometristas ENDI para el op IBRD / 89460 stance for Capacity Building Post Open - National 43,504.00 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation erativo de campo de la Encu & Monitoring and Evaluation esta Nacional de Desnutrició n Infantil Component 2: Technical Assi C2-MIES-INEC-70 / Personal Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 14,792.12 0.00 2023-10-20 2023-12-15 2024-06-12 Civil- Técnicos de Campo tions nvelope ementation & Monitoring and Evaluation C2-MIES-INEC-74 / Contratac ión de 6 Encuestadores ENDI Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl para el operativo de campo d IBRD / 89460 stance for Capacity Building Post Open - National 39,693.60 0.00 2023-03-20 2023-05-15 2023-11-11 tions nvelope ementation e la Encuesta Nacional de De & Monitoring and Evaluation snutrición Infantil (Galápago s) C2-MIES-INEC-65 / Contratac ión de una agencia de viaje p Component 2: Technical Assi ara la provisión de pasajes a Single Stage - One E IBRD / 89460 stance for Capacity Building Post Request for Bids Open - National 26,556.70 0.00 Canceled 2023-03-15 2023-04-06 2023-03-20 2023-04-06 2023-05-01 2023-05-31 2023-07-05 2024-01-01 éreos en rutas nacionales par nvelope & Monitoring and Evaluation a el operativo de campo de l a Encuesta Nacional de Desn utrición Infantil C2-MIES-INEC-84 / Contratac Component 2: Technical Assi ión de 1 Auxiliar de logística Request for Quota Single Stage - One E Pending Impl IBRD / 89460 stance for Capacity Building Post Open - National 5,062.50 0.00 2023-05-20 2023-07-15 2023-12-31 y procesos de calidad ENDI p tions nvelope ementation & Monitoring and Evaluation ara la Encuesta Nacional de Desnutrición Infantil Page 5 C2-MIES-INEC-86 / Contratac ión de una agencia de viaje p ara la provisión de pasajes a Component 2: Technical Assi Request for Quota Single Stage - One E Pending Impl éreos en rutas nacionales par IBRD / 89460 stance for Capacity Building Post Open - National 26,556.70 0.00 2023-05-24 2023-07-19 2024-01-15 tions nvelope ementation a el operativo de campo de l & Monitoring and Evaluation a Encuesta Nacional de Desnutrición Infa ntil año 2023 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2-MIES-13 / Diseño e imple Component 2: Technical Assi Quality And Cost- Open - Internationa mentación de un sistema int IBRD / 89460 stance for Capacity Building Prior 646,000.00 0.00 Canceled 2020-02-10 2020-02-24 2020-03-27 2020-05-18 2020-05-29 2020-06-23 2020-08-11 2021-08-11 Based Selection l egrado de quejas y reclamos & Monitoring and Evaluation C2-MIES-18 / Investigación y Component 2: Technical Assi desarrollo de las encuestas p Quality And Cost- Open - Internationa IBRD / 89460 stance for Capacity Building Prior 1,200,000.00 0.00 Canceled 2020-01-17 2020-01-31 2020-03-02 2020-04-23 2020-05-11 2020-06-08 2020-07-20 2021-12-02 ara monitoreo de los resultad Based Selection l & Monitoring and Evaluation os del proyecto Multipropósit o/ENEMDU C2-MIES-19 / Contratación d Component 2: Technical Assi e Verificación Técnica de Cu Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 100,000.00 54,830.40 Completed 2020-01-17 2020-06-30 2020-01-31 2020-07-10 2020-02-18 2020-08-11 2020-03-11 2020-08-31 2020-03-18 2020-09-15 2020-04-03 2020-09-29 2020-05-06 2020-10-27 2020-12-22 2021-01-01 mplimiento de DLIs para el Pr Based Selection & Monitoring and Evaluation oyecto Red de Protección So cial - MIES 2020 C2-MIES-20 / Contratación d e Verificación Técnica de Cu Component 2: Technical Assi Quality And Cost- mplimiento de DLIs para el Pr IBRD / 89460 stance for Capacity Building Post Open - National 220,000.00 0.00 Canceled 2020-11-20 2020-12-07 2020-12-26 2021-01-17 2021-01-24 2021-02-10 2021-03-13 2023-01-02 Based Selection oyecto Red de Protección So & Monitoring and Evaluation cial - MIES 2020, 2021, 2022 C2-MIES-22 / Contratación d Component 2: Technical Assi el Servicio de Auditoría Finan Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 220,000.00 0.00 Canceled 2020-11-23 2020-11-27 2020-12-18 2021-01-13 2021-01-22 2021-02-10 2021-03-17 2022-11-07 ciera para el Proyecto Red de Based Selection & Monitoring and Evaluation Protección Social - MIES 2020 , 2021, 2022 C2-MIES-46 / Elaboración de Component 2: Technical Assi Planes de Participación de Pu Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 123,572.96 0.00 Canceled 2020-03-27 2020-04-10 2020-04-17 2020-05-14 2020-05-21 2020-05-28 2020-06-18 2020-07-06 2020-11-03 eblos y Nacionalidades Indíg Based Selection & Monitoring and Evaluation enas, Afroecuatorianos y Mo ntubios (PPNIAM) C2-MIES-48 / Elaboración de Component 2: Technical Assi Planes de Participación de Pu Quality And Cost- Under Implement IBRD / 89460 stance for Capacity Building Post Open - National 181,724.82 0.00 2020-06-18 2020-06-30 2020-07-05 2020-08-21 2020-07-09 2020-09-23 2020-07-30 2020-10-15 2020-08-12 2020-11-16 2020-08-24 2020-12-01 2020-09-11 2021-01-09 eblos y Nacionalidades Indíg Based Selection ation & Monitoring and Evaluation enas, Afroecuatorianos y Mo ntubios (PPNIAM) C2-MIES-17 / Diseño del mod elo de gestión apalancado en instrumentos jurídicos, meto Component 2: Technical Assi dológicos, operativos y tecno Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 106,388.80 0.00 Canceled 2020-09-16 2020-09-30 2020-10-09 2020-10-22 2020-10-30 2020-11-13 2020-11-27 2020-12-15 2020-12-30 2021-04-30 lógicos para el seguimiento n Based Selection & Monitoring and Evaluation ominal de la población objeti vo de misión ternura, orienta do a la prevención de la desn utrición infantil C2-MIES-43 / GESTIÓN DE C ERTIFICACIÓN DE CALIDAD E STADÍSTICA DE OPERACIONE S ESTADÍSTICASBASADAS EN Component 2: Technical Assi REGISTROS ADMINISTRATIVO Quality And Cost- Under Implement IBRD / 89460 stance for Capacity Building Post 60,814.77 0.00 2020-11-11 2020-11-19 2020-11-25 2021-01-18 2020-12-16 2021-01-11 2021-01-22 2021-02-08 2021-03-02 2021-06-30 S DE SERVICIOS DE ATENCIÓ Based Selection ation & Monitoring and Evaluation N A PERSONAS CON DISCAPA CIDAD, DESARROLLO INFANT IL INTEGRAL, ATENCIÓN A PE RSONAS ADULTAS MAYORES, Y MOVILIDAD SOCIAL AS C2-MIES-21 / Contratación d Component 2: Technical Assi el Servicio de Auditoría Finan Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 39,144.00 0.00 Canceled 2020-12-04 2020-12-21 2020-12-18 2021-01-06 2021-01-15 2021-01-25 2021-02-09 2021-03-01 2021-04-30 ciera Período 2019 y 2020 pa Based Selection & Monitoring and Evaluation ra el Proyecto Red de Protecc ión Social – MIES C2-MIES-59 / Auditoría de Es tados Financieros de Propósit o Especial del Proyecto Red d Component 2: Technical Assi e Protección Social - MIES, fin Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 39,144.00 0.00 Canceled 2021-01-18 2021-01-15 2021-02-05 2021-02-26 2021-04-16 2021-03-19 2021-05-03 2021-04-08 2021-05-06 2021-04-26 2021-05-15 2021-06-29 anciado parcialmente a travé Based Selection & Monitoring and Evaluation s del Acuerdo Legal de Prést amo Nro. BIRF 8946-EC, por el Período 22 de julio 2019 al 31 de diciembre del 2020 C2-MIES-10 / Diseño e Imple Component 2: Technical Assi Quality And Cost- mentación de plataforma par IBRD / 89460 stance for Capacity Building Post Open - National 150,000.00 0.00 Canceled 2020-01-27 2020-02-03 2020-02-27 2020-03-16 2020-03-17 2020-04-13 2020-05-22 2021-02-16 Based Selection a registrar información de co & Monitoring and Evaluation operantes Component 2: Technical Assi C2-MIES-3 / Diseño de la Est Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 58,000.00 0.00 Canceled 2020-01-17 2020-01-20 2020-02-14 2020-03-09 2020-03-10 2020-03-29 2020-05-03 2020-08-01 rategia de Tecnología Social Based Selection & Monitoring and Evaluation C2-MIES-2 / Diseño e Implem Component 2: Technical Assi entación de la plataforma pa Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 412,500.00 0.00 Canceled 2020-02-10 2020-02-12 2020-02-25 2020-03-15 2020-03-16 2020-04-15 2020-06-08 2021-03-05 ra el registro de los servicios Based Selection & Monitoring and Evaluation de Inclusión Económica C2-MIES-5 / Diseño e implem Component 2: Technical Assi Quality And Cost- entación de un piloto de micr IBRD / 89460 stance for Capacity Building Post Open - National 71,500.00 0.00 Canceled 2020-01-17 2020-01-20 2020-02-14 2020-02-28 2020-03-02 2020-03-27 2020-05-09 2020-10-06 Based Selection oredes de emprendimientos & Monitoring and Evaluation populares C2-MIES-6 / Diseño de los Se rvicios de Fortalecimiento de Component 2: Technical Assi Capacidades y Acceso a Merc Quality And Cost- Open - Internationa IBRD / 89460 stance for Capacity Building Prior 664,469.00 0.00 Canceled 2020-01-17 2020-01-21 2020-02-24 2020-03-21 2020-03-28 2020-04-16 2020-05-04 2020-11-30 ados e Implementación de u Based Selection l & Monitoring and Evaluation n Piloto para Fortalecimiento de Capacidades Productivas en varios distritos C2-MIES-1 / Diseño e Implem Component 2: Technical Assi Quality And Cost- Open - Internationa entación de un Piloto de Mod IBRD / 89460 stance for Capacity Building Post 440,500.00 0.00 Canceled 2020-01-13 2020-01-26 2020-02-24 2020-04-10 2020-04-13 2020-05-25 2020-07-06 2020-12-03 Based Selection l alidades de CDH en varios di & Monitoring and Evaluation stritos Page 6 C2-MIES-9 / Diseño e Implem entación de aplicativos en Ta blet para el registro de la inf Component 2: Technical Assi ormación de las visitas domic Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 150,000.00 0.00 Canceled 2020-03-02 2020-03-16 2020-05-20 2020-07-06 2020-07-20 2020-08-10 2020-09-14 2021-03-13 iliarias realizadas por las edu Based Selection & Monitoring and Evaluation cadoras del CNH y los técnic os de acompañamiento famili ar del BDH; y, desarrollo de i nterfaces para sincronizar la infor C2-MIES-14 / Consultoría par a identificar, a través de map Component 2: Technical Assi as territoriales, la capacidad Quality And Cost- IBRD / 89460 stance for Capacity Building Post Open - National 300,000.00 0.00 Canceled 2020-01-17 2020-01-20 2020-02-12 2020-03-11 2020-03-13 2020-04-01 2020-04-18 2020-10-15 de oferta de servicios de DIT Based Selection & Monitoring and Evaluation y atención al adulto mayor p ertenecientes a hogares extr emadamente pobres C2-MIES-15 / Estudio de sost Component 2: Technical Assi Quality And Cost- enibilidad financiera del prog IBRD / 89460 stance for Capacity Building Post Open - National 80,000.00 0.00 Canceled 2020-02-11 2020-02-25 2020-03-17 2020-04-03 2020-04-14 2020-05-01 2020-06-05 2020-12-02 Based Selection rama Mis Mejores Años y PA & Monitoring and Evaluation M. C2-MIES-62 / AUDITORIA DE ESTADOS FINANCIEROS DE P ROPOSITO ESPECIAL DEL PR OYECTO RED DE PROTECCIÓ Component 2: Technical Assi Consultant Qualifi N SOCIAL – MIES, FINANCIAD IBRD / 89460 stance for Capacity Building Post Limited 36,708.00 36,624.00 Completed 2021-07-23 2021-08-06 2021-08-18 2021-09-14 2021-09-08 2021-10-04 2021-10-20 2021-10-07 2021-11-20 2021-12-04 cation Selection O PARCIALMENTE A TRAVES & Monitoring and Evaluation DEL ACUERDO LEGAL DE PRÉ STAMO NRO. BIRF 8946-EC, P OR EL PERIODO DEL 06 DE A GOSTO DE 2019 AL 31 DE DI CIEMBRE DE 2020. C2-MIES-24 / Evaluación de i Component 2: Technical Assi Quality And Cost- Open - Internationa mpacto de la estrategia de in IBRD / 89460 stance for Capacity Building Post 392,000.00 0.00 Canceled 2022-05-04 2022-05-23 2022-06-17 2022-07-07 2022-07-15 2022-07-29 2022-08-14 2022-12-31 Based Selection l clusión económica & Monitoring and Evaluation C2-MIES-89 / SERVICIO DE C ONSULTORÍA PARA LA FORM ULACIÓN DE UNA PROPUEST Component 2: Technical Assi A DE PLAN PARA LA MEJORA Quality And Cost- Under Implement IBRD / 89460 stance for Capacity Building Post Open - National 46,300.80 0.00 2023-04-28 2023-04-28 2023-05-15 2023-06-22 2023-06-19 2023-07-17 2023-08-09 2023-08-23 2023-09-29 2024-01-27 DE LAS INTERVENCIONES DE Based Selection ation & Monitoring and Evaluation LA POLÍTICA DE PROTECCIÓN SOCIAL, BAJO CRITERIOS DE PERTINENCIA CULTURAL Y TE RRITORIAL, PARA LA POBLACI ÓN INDÍGENA. C2-MIES-90 / EVALUACIÓN D E RESULTADOS DE LOS SERV Component 2: Technical Assi ICIOS DE DESARROLLO INFA Quality And Cost- Under Implement IBRD / 89460 stance for Capacity Building Post Open - National 64,377.45 0.00 2023-04-28 2023-04-26 2023-05-15 2023-06-19 2023-07-17 2023-08-09 2023-08-23 2023-09-29 2024-01-27 NTIL ENMARCADOS EN EL PR Based Selection ation & Monitoring and Evaluation OGRAMA “MISIÓN TERNURA” PARA EL PERÍODO 2019 - 202 1 C2-MIES-91 / EVALUACIÓN D Component 2: Technical Assi E RESULTADOS DEL PROGRA Quality And Cost- Under Implement IBRD / 89460 stance for Capacity Building Post Open - National 68,046.55 0.00 2023-04-28 2023-04-27 2023-05-15 2023-06-20 2023-06-19 2023-07-17 2023-08-09 2023-08-23 2023-09-29 2024-01-27 MA “MIS MEJORES AÑOS” PA Based Selection ation & Monitoring and Evaluation RA EL PERÍODO 2019 - 2021 C2-MIES-92 / ASISTENCIA TÉ CNICA PARA LA ELABORACIÓ Component 2: Technical Assi Quality And Cost- Under Implement N DEL PLAN NACIONAL PARA IBRD / 89460 stance for Capacity Building Post Open - National 196,214.25 0.00 2023-05-02 2023-04-28 2023-05-19 2023-06-26 2023-06-23 2023-07-21 2023-08-14 2023-08-30 2023-10-06 2024-04-13 Based Selection ation LA PROTECCIÓN INTEGRAL D & Monitoring and Evaluation E DERECHOS DE LAS PERSO NAS ADULTAS MAYORES INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C2-MIES-25 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Open 25,189.56 18,144.00 Completed 2020-01-17 2020-03-09 2020-02-18 2020-05-20 2020-02-25 2020-06-12 2020-03-25 2020-07-16 2020-12-20 2021-01-01 ant Selection alista en Protección Social / U & Monitoring and Evaluation GP C2-MIES-26 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 25,189.56 0.00 Terminated 2020-01-03 2020-02-13 2020-01-20 2020-04-14 2020-01-27 2020-04-16 2020-01-31 2020-05-05 2020-03-16 ant Selection alista en Comunicación & Monitoring and Evaluation C2-MIES-27 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Open 30,487.71 29,927.52 Completed 2020-01-06 2020-01-27 2020-02-03 2020-04-09 2020-02-24 2020-04-13 2020-03-02 2020-04-21 2020-12-27 2021-01-01 ant Selection alista Legal / UGP & Monitoring and Evaluation C2-MIES-28 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Open 30,487.71 21,168.00 Completed 2020-01-06 2020-01-27 2020-01-29 2020-02-14 2020-02-26 2020-04-22 2020-03-02 2020-05-23 2020-12-27 2021-01-01 ant Selection alista Financiero / UGP & Monitoring and Evaluation C2-MIES-29 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Open 30,487.71 24,192.00 Completed 2020-01-06 2020-01-27 2020-01-29 2020-04-14 2020-02-26 2020-04-16 2020-03-02 2020-05-05 2020-12-27 2021-01-01 ant Selection alista de Adquisiciones & Monitoring and Evaluation C2-MIES-31 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Open 30,487.71 0.00 Canceled 2020-01-06 2020-01-29 2020-02-24 2020-03-02 2020-12-27 ant Selection alista en Planificación y Monit & Monitoring and Evaluation oreo / UGP C2-MIES-32 / Contratación d e Consultor Individual Especi Component 2: Technical Assi Individual Consult alista en Evaluación de Impa IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2020-01-17 2020-02-11 2020-03-09 2020-03-13 2020-12-08 ant Selection cto (Diseños de los procesos & Monitoring and Evaluation de evaluación de impacto) C2-MIES-33 / Contratación d Component 2: Technical Assi e Consultor Individual Especi Individual Consult IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2020-01-17 2020-02-10 2020-02-24 2020-03-13 2020-12-08 alista en Estadística y Proces ant Selection & Monitoring and Evaluation amiento de Datos (Cumplimi ento de Indicadores) C2-MIES-34 / Contratación d e Consultor Individual Especi Component 2: Technical Assi alista en Sistemas de Inform Individual Consult IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2020-01-17 2020-02-10 2020-03-09 2020-03-16 2020-12-11 ación y Reportería de Datos ( ant Selection & Monitoring and Evaluation Fortalecimiento del InfoMies para permitir interoperabilida d) C2-MIES-36 / Contratación d Component 2: Technical Assi e Consultor Individual Especi Individual Consult IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2020-01-17 2020-02-07 2020-02-23 2020-03-13 2020-12-08 alista de enlace técnico con l ant Selection & Monitoring and Evaluation a Subsecretaría de Familia Page 7 C2-MIES-38 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Analist IBRD / 89460 stance for Capacity Building Post Open 19,800.00 0.00 Canceled 2020-07-16 2020-08-18 2020-09-02 2020-09-23 2021-07-20 ant Selection a de Adquisiciones & Monitoring and Evaluation C2-MIES-41 / Contratación d Component 2: Technical Assi e Consultor Individual para C Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 29,124.26 0.00 Canceled 2020-01-06 2020-01-08 2020-01-14 2020-02-07 2020-04-07 onsultas Jurídicas Específicas ant Selection & Monitoring and Evaluation para el Proyecto Red de Prot ección Social C2-MIES-45 / Consultoría par Component 2: Technical Assi Individual Consult a la Aplicación de una Consul IBRD / 89460 stance for Capacity Building Post Limited 50,000.00 0.00 Canceled 2020-01-13 2020-01-14 2020-02-04 2020-03-10 2020-06-08 ant Selection ta para los Pueblos y Naciona & Monitoring and Evaluation lidades C2-MIES-47 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Limited 11,995.31 8,568.08 Completed 2020-06-30 2020-07-08 2020-07-13 2020-07-22 2020-07-23 2020-07-31 2020-08-10 2020-08-19 2020-12-30 2021-01-01 ant Selection alista Social & Monitoring and Evaluation C2-MIES-49 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,788.75 21,591.56 Completed 2020-12-07 2020-12-12 2020-12-28 2021-03-29 2021-01-04 2021-03-30 2021-01-06 2021-04-08 2021-12-31 2021-12-18 ant Selection alista en Protección Social pe & Monitoring and Evaluation ríodo 2021 C2-MIES-50 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,788.75 0.00 Under Review 2020-12-07 2021-03-02 2020-12-28 2021-01-04 2021-01-06 2021-12-31 ant Selection alista Legal período 2021 & Monitoring and Evaluation C2-MIES-51 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,788.75 21,591.56 Completed 2020-12-07 2020-12-12 2020-12-28 2021-03-29 2021-01-04 2021-03-30 2021-01-06 2021-04-08 2021-12-31 2021-12-28 ant Selection alista Financiero período 202 & Monitoring and Evaluation 1 C2-MIES-52 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,788.75 11,995.31 Terminated 2020-12-07 2020-12-12 2020-12-28 2021-03-29 2021-01-04 2021-03-30 2021-01-06 2021-04-08 2021-12-31 ant Selection alista de Adquisiciones perío & Monitoring and Evaluation do 2021 C2-MIES-53 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,788.75 21,591.56 Completed 2020-12-07 2020-12-12 2020-12-28 2021-03-29 2021-01-04 2021-03-30 2021-01-06 2021-04-08 2021-12-31 2021-12-18 ant Selection alista Social período 2021 & Monitoring and Evaluation C2-MIES-39 / Contratación d Component 2: Technical Assi e Consultor Indovidual Especi Individual Consult IBRD / 89460 stance for Capacity Building Post Open 22,500.00 0.00 Canceled 2020-03-16 2020-03-17 2020-04-06 2020-05-20 2020-04-09 2020-04-20 2020-12-31 alista Social y de Comunicaci ant Selection & Monitoring and Evaluation ones para el Proyecto Red de Protección Social C2-MIES-57 / CONTRATACIÓ N DE UN CONSULTOR INDIVI DUAL PARA FORTALECER Y B Component 2: Technical Assi RINDAR APOYO EN LOS SERV Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 43,792.00 0.00 Canceled 2020-09-21 2020-09-29 2020-11-12 2020-12-02 2022-04-30 ICIOS QUE PRESTA LA DIREC ant Selection & Monitoring and Evaluation CIÓN DE IMPULSO JOVEN DE LA SUBSECRETARÍA DE EMPR ENDIMIENTOS Y GESTIÓN DE L CONOCIMIENTO C2-MIES-56 / CONTRATACIÓ N DE UN CONSULTOR INDIVI Component 2: Technical Assi DUAL PARA FORTALECER Y B Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 43,792.00 0.00 Canceled 2020-09-21 2020-09-29 2020-11-12 2020-12-02 2022-04-30 RINDAR APOYO EN LOS SERV ant Selection & Monitoring and Evaluation ICIOS QUE PRESTA LA DIREC CIÓN DE GESTIÓN DEL CONO CIMIENTO C2-MIES-55 / CONTRATACIÓ N DE UN CONSULTOR INDIVI Component 2: Technical Assi Individual Consult DUAL PARA FORTALECER Y B IBRD / 89460 stance for Capacity Building Post Limited 43,792.00 0.00 Canceled 2020-09-21 2020-09-29 2020-11-12 2020-12-02 2022-04-30 ant Selection RINDAR APOYO EN LOS SERV & Monitoring and Evaluation ICIOS QUE PRESTA LA DIREC CIÓN DE EMPRENDIMIENTOS C2-MIES-54 / CONTRATACIÓ N DE UN CONSULTOR INDIVI Component 2: Technical Assi DUAL PARA FORTALECER Y B Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 43,792.00 0.00 Canceled 2020-09-21 2020-09-29 2020-11-12 2020-12-02 2022-04-30 RINDAR APOYO EN LOS SERV ant Selection & Monitoring and Evaluation ICIOS QUE PRESTA LA DIREC CIÓN DE DESARROLLO DE M ERCADOS C2-MIES-37 / Contratación d e Consultor Individual Especi Component 2: Technical Assi Individual Consult alista de enlace técnico con l IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2020-01-17 2020-02-07 2020-03-09 2020-03-13 2020-12-08 ant Selection a Subsecretaría de Inclusión & Monitoring and Evaluation Económica y Movilidad Social C2-MIES-64 / CONTRATACIÓ N DE UN CONSULTOR INDIVI Component 2: Technical Assi Individual Consult DUAL ESPECIALISTA EN ADQ IBRD / 89460 stance for Capacity Building Prior Direct 9,596.25 0.00 Canceled 2021-09-07 2021-10-18 2021-09-20 2021-09-24 2021-09-30 2021-12-30 ant Selection UISICIONES PARA & Monitoring and Evaluation EL PROYECTO “RED DE PROT ECCIÓN SOCIAL” PERÍODO 20 21 C2-MIES-65 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,789.87 28,788.75 Signed 2021-11-12 2021-11-29 2021-11-29 2021-12-15 2021-12-10 2021-12-20 2021-12-27 2021-12-29 2022-12-23 ant Selection alista en Protección Social pe & Monitoring and Evaluation ríodo 2022 C2-MIES-67 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,789.87 162,377.91 Signed 2021-11-12 2021-11-29 2021-11-29 2021-12-15 2021-12-10 2021-12-20 2021-12-27 2021-12-29 2022-12-23 ant Selection alista Financiero período 202 & Monitoring and Evaluation 2 C2-MIES-68 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,789.87 28,788.75 Signed 2021-11-12 2021-11-29 2021-11-29 2021-12-15 2021-12-10 2021-12-20 2021-12-27 2021-12-29 2022-12-23 ant Selection alista de Adquisiciones perío & Monitoring and Evaluation do 2022 C2-MIES-69 / Contratación d Component 2: Technical Assi Individual Consult e Consultor Individual Especi IBRD / 89460 stance for Capacity Building Post Direct 28,789.87 28,788.75 Signed 2021-11-12 2021-11-29 2021-11-29 2021-12-15 2021-12-10 2021-12-20 2021-12-27 2021-12-29 2022-12-23 ant Selection alista Social período 2022 & Monitoring and Evaluation C2-MIES-70 / SERVICIO DE V ERIFICACION TECNICA DE CU Component 2: Technical Assi MPLIMIENTO DE DLI PARA EL IBRD / 89460 stance for Capacity Building Post Direct Selection Direct 181,863.27 162,377.91 Completed 2021-11-30 2021-11-04 2021-12-15 2021-12-15 2021-12-31 2021-12-30 2022-04-30 2022-06-25 PROYECTO "RED DE PROTEC & Monitoring and Evaluation CION SOCIAL" PERIODO 2020 -2021 C2-MIES-71 / AUDITORIA DE LOS ESTADOS FINANCIEROS DE PROPOSITO ESPECIAL DEL PROYECTO RED DE PROTECC Component 2: Technical Assi ION SOCIAL - MIES, FINANCIA IBRD / 89460 stance for Capacity Building Post Direct Selection Direct 30,240.00 29,120.00 Signed 2021-11-30 2022-01-13 2021-12-15 2022-03-04 2021-12-31 2022-05-10 2022-02-14 DO PARCIALMENTE A TRAVES & Monitoring and Evaluation DEL ACUERDO LEGAL DE PRE STAMO NRO. BIRF 8946-EC - POR EL PERÍODO 1 DE ENER O A 31 DE DICIEMBRE DE 20 21 Page 8 C2-MIES-72 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult L ESPECIALISTA DE EVALUACI IBRD / 89460 stance for Capacity Building Post Direct 16,793.44 14,394.37 Signed 2022-05-20 2022-05-12 2022-06-10 2022-06-17 2022-06-15 2022-06-21 2022-06-27 2022-06-25 2022-12-23 ant Selection ÓN DE IMPACTO PARA EL PR & Monitoring and Evaluation OYECTO “RED DE PROTECCI ÓN SOCIAL” PERÍODO 2022 C2-MIES-INEC-4 / Servicios d e consultoría para el procesa miento y análisis de los resul Component 2: Technical Assi tados de la Encuesta de Des Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 11,760.00 0.00 Canceled 2022-07-29 2022-07-15 2022-08-08 2022-09-09 2022-10-14 2022-12-31 nutrición Infantil en el marco ant Selection & Monitoring and Evaluation del rol del INEC ante el Decre to Presidencial 1211 y las res ponsabilidades establecidas en la estrategia Ecuador Crec e Sin Desn C2-MIES-INEC-5 / Servicios d e consultoría para la elabora ción de la metodología de int Component 2: Technical Assi egración de registros admini Individual Consult IBRD / 89460 stance for Capacity Building Post Limited 11,760.00 0.00 Canceled 2022-07-29 2022-07-15 2022-08-08 2022-08-25 2022-09-23 2022-12-31 strativos para el monitoreo d ant Selection & Monitoring and Evaluation e la desnutrición crónica infa ntil-DCI, en el marco del rol d el INEC ante el Decreto Presi dencial 1211 y las responsab ilidades es C2-MIES-INEC-26 / Contratac ión de servicios de consultorí a para para el seguimiento té cnico y validación de informa Component 2: Technical Assi Individual Consult Pending Impleme ción sobre prestaciones mate IBRD / 89460 stance for Capacity Building Post Direct - National 7,198.30 0.00 2022-09-16 2022-09-19 2022-09-24 2022-09-26 2022-12-30 ant Selection ntation rno-infantiles, datos antropo & Monitoring and Evaluation métricos, hemoglobina, segu ridad alimentaria y calidad d e agua, en el marco de la En cuesta Nacional C2-MIES-73 / FORMULACIÓN DE UNA PROPUESTA DE PLAN Component 2: Technical Assi PARA LA MEJORA DE LAS INT Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Post Open - National 25,540.48 0.00 2022-10-07 2022-10-31 2022-11-09 2022-12-08 2022-11-16 2022-12-15 2023-04-14 ERVENCIONES DE LA POLÍTIC ant Selection ation & Monitoring and Evaluation A DE PROTECCIÓN SOCIAL D ESDE UNA PERSPECTIVA DE GÉNERO C2-MIES-74 / AUDITORIA DE LOS ESTADOS FINANCIEROS DE PROPOSITO ESPECIAL DEL PROYECTO RED DE PROTECC Component 2: Technical Assi Under Implement IÓN SOCIAL – MIES, FINANCIA IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 21,500.00 0.00 2022-10-21 2022-10-31 2022-11-14 2022-12-29 2023-02-17 ation DO PARCIALMENTE A TRAVES & Monitoring and Evaluation DEL ACUERDO LEGAL DE PRÉ STAMO NRO. BIRF 8946-EC, P ARA EL PERÍODO DEL 01 DE ENERO AL 31 DE DICIEMBRE DE 2022 C2-MIES-75 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult Under Implement L ESPECIALISTA SOCIAL PARA IBRD / 89460 stance for Capacity Building Post Direct - National 55,178.44 0.00 2022-11-02 2022-11-22 2022-11-30 2022-12-12 2022-12-27 2024-11-26 ant Selection ation EL PROYECTO “RED DE PRO & Monitoring and Evaluation TECCIÓN SOCIAL” PERÍODO 2 023 - 2024 C2-MIES-78 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult Under Implement L ESPECIALISTA FINANCIERO IBRD / 89460 stance for Capacity Building Post Direct - National 49,266.46 0.00 2022-11-02 2022-11-22 2022-11-30 2022-12-21 2022-12-27 2024-11-28 ant Selection ation PARA EL PROYECTO “RED DE & Monitoring and Evaluation PROTECCIÓN SOCIAL” PERÍO DO 2023 - 2024 C2-MIES-INEC-5-1 / Servicios de consultoría para la elabor ación de la metodología de in Component 2: Technical Assi tegración de registros admini Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Post Limited 28,790.96 0.00 2022-11-18 2022-11-24 2022-11-23 2022-11-30 2022-12-29 2023-12-29 strativos para el monitoreo d ant Selection ation & Monitoring and Evaluation e la desnutrición crónica infa ntil-DCI, en el marco del rol d el INEC ante el Decreto Presi dencial 1211 y las responsab ilidades es C2-MIES-INEC-4-1 / Servicios de consultoría para el proces amiento y análisis de los res Component 2: Technical Assi ultados de la Encuesta de De Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Post Limited 28,790.96 0.00 2022-11-11 2022-11-24 2022-11-30 2022-12-14 2022-12-29 2023-12-29 snutrición Infantil en el marc ant Selection ation & Monitoring and Evaluation o del rol del INEC ante el Dec reto Presidencial 1211 y las r esponsabilidades establecida s en la estrategia Ecuador Cr ece Sin Desn C2-MIES-INEC-23 / Contratac ión de servicios de consultorí Component 2: Technical Assi a para la ejecución de los pro Individual Consult Pending Impleme IBRD / 89460 stance for Capacity Building Post Limited 31,188.90 0.00 2022-11-11 2022-11-25 2022-12-22 2022-12-29 2023-12-29 cesos de adquisición para la i ant Selection ntation & Monitoring and Evaluation mplementación del proyecto de la Encuesta Nacional de D esnutrición Infantil C2-MIES-INEC-24 / Contratac ión de servicios de consultorí Component 2: Technical Assi a para la ejecución de los pro Individual Consult Pending Impleme IBRD / 89460 stance for Capacity Building Post Limited 31,188.90 0.00 2022-11-18 2022-11-25 2022-12-26 2022-12-29 2023-12-28 cesos financieros en el marc ant Selection ntation & Monitoring and Evaluation o de la implementación del p royecto de la Encuesta Nacio nal de Desnutrición Infantil C2-MIES-INEC-25 / Contratac ión de servicios de consultorí Component 2: Technical Assi Individual Consult Pending Impleme a para la Coordinación de la i IBRD / 89460 stance for Capacity Building Post Direct - National 31,188.90 0.00 2022-11-18 2022-12-01 2022-12-16 2022-12-29 2023-12-29 ant Selection ntation mplementación del proyecto & Monitoring and Evaluation de la Encuesta Nacional de D esnutrición Infantil C2-MIES-76 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi L ESPECIALISTA DE PROTECC Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Post Direct - National 49,266.46 0.00 2022-11-02 2022-11-22 2022-11-30 2022-12-12 2022-12-27 2024-11-26 IÓN SOCIAL PARA EL PROYEC ant Selection ation & Monitoring and Evaluation TO “RED DE PROTECCIÓN SO CIAL” PERÍODO 2023 - 2024 C2-MIES-80 / Servicio de Ver Component 2: Technical Assi ificación Técnica de cumplimi Under Implement IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 46,546.04 0.00 2022-11-22 2022-11-29 2022-12-07 2022-12-30 2023-04-29 ento de DLI 16, para el Proye ation & Monitoring and Evaluation cto “Red de Protección Social ”, periodo 2022 C2-MIES-84 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi L ESPECIALISTA DE EVALUACI Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Post Direct - National 47,124.44 0.00 2023-01-25 2023-01-17 2023-01-30 2023-02-06 2023-02-07 2024-11-20 ÓN DE IMPACTO PARA EL PR ant Selection ation & Monitoring and Evaluation OYECTO “RED DE PROTECCI ÓN SOCIAL” PERÍODO 2023 - 2024 Page 9 C2-MIES-82 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult L ESPECIALISTA DE ADQUISIC IBRD / 89460 stance for Capacity Building Prior Direct - National 49,266.46 0.00 Canceled 2023-01-13 2023-02-16 2023-01-30 2023-03-06 2023-02-06 2023-02-07 2024-11-27 ant Selection IONES PARA EL PROYECTO “R & Monitoring and Evaluation ED DE PROTECCIÓN SOCIAL” PERÍODO 2023 - 2024 C2-MIES-83 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult L ESPECIALISTA LEGAL PARA IBRD / 89460 stance for Capacity Building Post Direct - National 49,266.46 0.00 Canceled 2023-01-13 2023-01-13 2023-01-30 2023-02-06 2023-02-14 2024-12-04 ant Selection EL PROYECTO “RED DE PROT & Monitoring and Evaluation ECCIÓN SOCIAL” PERÍODO 20 23 - 2024 C2-MIES-85 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult Under Implement L ESPECIALISTA DE ADQUISIC IBRD / 89460 stance for Capacity Building Prior Direct - National 47,124.44 0.00 2023-03-21 2023-03-31 2023-03-31 2023-04-17 2023-04-21 2023-05-09 2023-05-26 2023-11-22 ant Selection ation IONES PARA EL PROYECTO "R & Monitoring and Evaluation ED DE PROTECCIÓN SOCIAL" PERÍODO 2023-2024 C2-MIES-35 / Contratación d Component 2: Technical Assi e Consultor Individual Especi Individual Consult IBRD / 89460 stance for Capacity Building Post Open 25,189.56 0.00 Canceled 2022-03-09 2022-04-04 2022-04-18 2022-05-16 2022-12-28 alista de enlace técnico con l ant Selection & Monitoring and Evaluation a Subsecretaría de Aseguram iento No Contributivo C2-MIES-66 / Contratación d Component 2: Technical Assi e consultor individual Especi Individual Consult IBRD / 89460 stance for Capacity Building Post Direct 28,789.87 0.00 Canceled 2021-12-16 2021-12-22 2021-12-27 2021-12-31 2022-12-27 alista Legal para el Proyecto ant Selection & Monitoring and Evaluation Red de Protección Social Peri odo 2022 C2-MIES-77 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult L ESPECIALISTA DE ADQUISIC IBRD / 89460 stance for Capacity Building Post Direct - National 49,266.46 0.00 Canceled 2022-11-02 2022-11-22 2022-11-30 2022-12-14 2022-12-27 2024-11-28 ant Selection IONES PARA EL PROYECTO “R & Monitoring and Evaluation ED DE PROTECCIÓN SOCIAL” PERÍODO 2023 - 2024 C2-MIES-86 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult L ESPECIALISTA LEGAL PARA IBRD / 89460 stance for Capacity Building Post Direct - National 47,124.44 0.00 Canceled 2023-03-29 2023-03-27 2023-04-08 2023-04-29 2023-06-03 2023-11-30 ant Selection EL PROYECTO "RED DE PROT & Monitoring and Evaluation ECCIÓN SOCIAL" PERÍODO 20 23-2024 C2-MIES-87 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi L DE APOYO A LA EJECUCIÓN Individual Consult Under Implement IBRD / 89460 stance for Capacity Building Prior Open - National 9,800.00 0.00 2023-04-14 2023-05-08 2023-05-29 2023-06-09 2023-06-05 2023-06-28 2023-06-19 2023-12-22 DE LAS ADQUISICIONES DEL ant Selection ation & Monitoring and Evaluation PROYECTO RED DE PROTECC IÓN SOCIAL – PERÍODO 2023 C2-MIES-88 / CONTRATACIÓ N DE CONSULTOR INDIVIDUA Component 2: Technical Assi Individual Consult Under Implement L ESPECIALISTA LEGAL PARA IBRD / 89460 stance for Capacity Building Post Direct - National 47,124.44 0.00 2023-04-24 2023-04-12 2023-05-04 2023-05-25 2023-06-29 2023-12-26 ant Selection ation EL PROYECTO “RED DE PROT & Monitoring and Evaluation ECCIÓN SOCIAL” PERÍODO 20 23 – 2024 C2-MIES-INEC-67 / Contratac ión de servicios de consultorí a para para el seguimiento té cnico y validación de informa Component 2: Technical Assi ción sobre prestaciones mate IBRD / 89460 stance for Capacity Building Post Direct Selection Direct - National 28,789.70 0.00 Canceled 2023-04-15 2023-04-25 2023-06-29 2023-12-26 rno-infantiles, datos antropo & Monitoring and Evaluation métricos, hemoglobina, segu ridad alimentaria y calidad d e agua, en el marco de la En cuesta Nacional C2-MIES-INEC-66 / Servicios de consultoría para la elabor ación de la metodología de in Component 2: Technical Assi tegración de registros admini Individual Consult Pending Impleme IBRD / 89460 stance for Capacity Building Post Direct - National 11,995.28 0.00 2023-07-01 2023-07-11 2023-08-01 2023-09-05 2024-03-03 strativos para el monitoreo d ant Selection ntation & Monitoring and Evaluation e la desnutrición crónica infa ntil-DCI, en el marco del rol d el INEC ante el Decreto Presi dencial 1211 y las responsab ilidades es Page 10 PROCUREMENT PLAN (Textual Part) Project information: Dominica Geothermal Risk Mitigation Project(P162149) Project Implementation agency: Dominica Geothermal Development Company Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. PROCUREMENT Dominica : Dominica Geothermal Risk Mitigation Project PLAN General Information Country: Dominica 2019-05-17 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162149 GPN Date: 2019-04-10 Project Name: Dominica Geothermal Risk Mitigation Project Loan / Credit No: IDA / 63760, TF / A9531, TF / A9532 Dominica Geothermal Development Company Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned DM-DGDC-109147-CW-RFB / DEVELOPMENT OF DOMESTI Open - Internationa Single Stage - One E 32,500,000.0 2020-04-0 EPC Contract for a nominal 7 IDA / 63760 C GEOTHERMAL POWER GEN Prior Request for Bids 0.00 Canceled 2019-04-04 2019-07-19 2019-05-13 2019-09-12 2019-08-05 2019-11-20 2019-09-06 2020-02-12 2019-10-11 l nvelope 0 8 MWe geothermal power plant ERATION CAPACITY (SGPP) DM-DGDC-209335-CW-RFB / DEVELOPMENT OF DOMESTI Open - Internationa Single Stage - One E 12,000,000.0 Under Revie 2021-10-0 Integrated drilling services fo IDA / 63760 C GEOTHERMAL POWER GEN Prior Request for Bids 0.00 2020-12-18 2021-01-27 2020-12-23 2021-03-26 2021-02-03 2021-04-06 2021-03-05 2021-04-09 l nvelope 0 w 6 r reinjection and production ERATION CAPACITY (SGPP) wells. DM-DGDC-209336-CW-RFB / DEVELOPMENT OF DOMESTI Single Stage - One E 2,751,448.5 2021-10-2 Civil Works for Reinjection W TF / A9531 C GEOTHERMAL POWER GEN Post Request for Bids Open - National 1,000,000.00 Signed 2021-01-03 2021-02-12 2021-01-08 2021-02-12 2021-02-19 2021-03-25 2021-03-21 2021-04-06 2021-04-25 2021-05-02 nvelope 4 2 ell and Production Well. ERATION CAPACITY (SGPP) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-DGDC-209337-GO-RFQ / DEVELOPMENT OF DOMESTI Single Stage - One E Purchase of Master Valves fo TF / A9531 C GEOTHERMAL POWER GEN Post Request for Bids Limited 250,000.00 194,098.00 Signed 2020-12-16 2021-01-13 2020-12-16 2021-01-08 2021-01-27 2021-02-12 2021-02-26 2021-03-03 2021-04-02 2021-03-19 2021-09-29 nvelope r reinjection and production ERATION CAPACITY (SGPP) wells. DM-DGDC-209338-GO-RFQ / DEVELOPMENT OF DOMESTI Open - Internationa Single Stage - One E Drill casing for geothermal w TF / A9531 C GEOTHERMAL POWER GEN Post Request for Bids 600,000.00 683,694.00 Completed 2020-12-16 2021-01-13 2020-12-16 2021-01-14 2021-01-27 2021-02-19 2021-02-26 2021-03-08 2021-04-02 2021-03-23 2021-09-29 2021-09-22 l nvelope ells. ERATION CAPACITY (SGPP) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-DGDC-109149-NC-RFB / CONTINGENT FINANCING IN Open - Internationa Single Stage - One E IDA / 63760 Prior Request for Bids 9,000,000.00 0.00 Canceled 2019-07-01 2019-09-02 2019-11-18 2019-12-18 2020-01-22 2020-07-20 Integrated Drilling Services C AID OF ADDITIONAL DRILLIN l nvelope ontract G CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-DGDC-109150-CS-QCBS TECHNICAL ASSITANCE FOR / LGPP feasibility, environme ADVANCING LGPP TO DEVEL Quality And Cost- Open - Internationa Pending Impleme IDA / 63760 Prior 1,000,000.00 0.00 2020-03-02 2020-03-23 2020-05-06 2020-06-03 2020-07-03 2020-08-07 2020-09-11 2021-09-11 ntal impact and geothermal s OPMENT STATUS AND SOLIC Based Selection l ntation ervices ITING PRIVATE SECTOR INVE STMENT DEVELOPMENT OF DOMESTI TF0A9531 / Owner's Enginee Consultant Qualifi TF / A9531 C GEOTHERMAL POWER GEN Post Limited 300,000.00 299,690.00 Signed 2020-12-17 2020-12-11 2020-12-31 2020-12-16 2021-01-30 2021-01-18 2021-03-06 2021-02-15 2021-09-02 r for Drilling Services cation Selection ERATION CAPACITY (SGPP) DM-DGDC-221918-CS-QCBS / Owner’s Engineer for constr DEVELOPMENT OF DOMESTI uction of transmission lines a Quality And Cost- Open - Internationa IDA / 63760 C GEOTHERMAL POWER GEN Prior 2,000,000.00 2,095,595.00 Signed 2021-02-26 2021-03-09 2021-03-19 2021-04-07 2021-05-02 2021-05-05 2021-05-30 2021-06-25 2021-06-29 2021-09-21 2021-08-03 2021-12-23 2021-09-07 2022-01-30 2022-09-07 nd substations (conceptual d Based Selection l ERATION CAPACITY (SGPP) esign, bidding document, pro curement support and super vision) DM-DGDC-213499-CS-QCBS DEVELOPMENT OF DOMESTI Quality And Cost- Open - Internationa / ESIA/ESMP/RAP for Transmis IDA / 63760 C GEOTHERMAL POWER GEN Post 700,000.00 448,185.75 Signed 2021-03-05 2021-04-07 2021-03-26 2021-04-07 2021-05-09 2021-05-13 2021-06-06 2021-06-24 2021-07-06 2021-09-14 2021-08-10 2021-10-26 2021-09-14 2022-01-25 2022-09-14 Based Selection l sion Lines and Substations ERATION CAPACITY (SGPP) TECHNICAL ASSITANCE FOR DM-DGDC-307973-CS-LCS / ADVANCING LGPP TO DEVEL Least Cost Selecti Open - Internationa Financial Audit 2020/2021 to TF / A9532 Post 30,000.00 0.00 Signed 2022-08-08 2022-08-16 2022-08-29 2022-08-16 2022-09-19 2022-09-21 2022-10-19 2022-10-31 2022-10-26 2022-11-07 2022-11-12 2022-11-16 2022-12-10 2023-01-09 OPMENT STATUS AND SOLIC on l 2021/2022 ITING PRIVATE SECTOR INVE STMENT INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DM-DGDC-217694-CS-CDS / DEVELOPMENT OF DOMESTI Under Implement Legal Services for Transmissi IDA / 63760 C GEOTHERMAL POWER GEN Post Direct Selection Direct 60,000.00 0.00 2021-02-03 2021-02-09 2021-02-13 2021-04-19 2021-05-19 ation on Line Agreement with DOM ERATION CAPACITY (SGPP) LEC. DM-DGDC-333603-CS-INDV / DEVELOPMENT OF DOMESTI Individual Consult Environmental Assessment T IDA / 63760 C GEOTHERMAL POWER GEN Post Limited 100,000.00 0.00 Canceled 2022-12-27 2023-01-01 2023-01-22 2023-02-26 2023-08-25 ant Selection ransmission Lines and Substa ERATION CAPACITY (SGPP) tions DM-DGDC-333611-CS-INDV / DEVELOPMENT OF DOMESTI Individual Consult Open - Internationa Social Assessment and RAP T IDA / 63760 C GEOTHERMAL POWER GEN Post 120,000.00 0.00 Signed 2022-12-23 2022-12-24 2023-02-06 2023-01-20 2023-02-27 2023-02-27 2023-04-03 2023-09-30 ant Selection l ransmission Lines and Substa ERATION CAPACITY (SGPP) tions DM-DGDC-333709-CS-INDV / DEVELOPMENT OF DOMESTI Individual Consult Open - Internationa Environmental Assessment T IDA / 63760 C GEOTHERMAL POWER GEN Post 100,000.00 0.00 Signed 2022-12-27 2022-12-24 2023-02-10 2023-01-20 2023-03-03 2023-02-27 2023-04-07 2023-10-04 ant Selection l ransmission Lines and Substa ERATION CAPACITY (SGPP) tions-2 Page 1 TECHNICAL ASSITANCE FOR DM-DGDC-339357-CS-CDS / ADVANCING LGPP TO DEVEL Direct - Internation Under Implement Technical Analysis of 33 kV/6 IDA / 63760 Post Direct Selection 44,000.00 0.00 2023-02-10 2023-03-03 2023-02-20 2023-03-09 2023-03-28 2023-09-24 OPMENT STATUS AND SOLIC al ation 9 kV Transmission Network ITING PRIVATE SECTOR INVE STMENT DM-DGDC-362042-CS-CDS / TECHNICAL ASSITANCE FOR Transmission Network Adviso ADVANCING LGPP TO DEVEL Direct - Internation Under Implement TF / A9532 Post Direct Selection 30,000.00 0.00 2023-05-17 2023-05-18 2023-05-27 2023-05-16 2023-07-31 2023-10-29 ry Service for preparation of OPMENT STATUS AND SOLIC al ation PPSD. ITING PRIVATE SECTOR INVE STMENT Page 2 PROCUREMENT PLAN (Textual Part) Project information: Accelerating and Strengthening Skills for Economic Transformation Project) (ASSET), P167506 Project Implementation agency: Directorate of Technical Education (DTE), Technical and Madrasah Education Division (TMED), Ministry of Education (MoE) Date of the Procurement Plan: March 23, 2022 Period covered by this Procurement Plan: March 2022 to March 2025 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (dated July 2016, revised November 2017, August 2018 and November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the People’s Republic of Bangladesh (Public Procurement Act 2006 - PPA, 1st amendment to PPA (2009) and the Public Procurement Rules 2008, as amended in August 2009) , such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions : a) e-GP system of the country for national competitive bidding (NCB) shall be followed using Standard/Model Procurement documents satisfactory to the Bank b) Post bidding negotiations shall not be allowed with the lowest evaluated or any other bidder; c) Bids should be submitted and opened in public in one location immediately after the deadline for submission; d) Lottery in award of contracts shall not be allowed; e) Bidders’ qualification/experience requirement shall be mandatory f) Bids shall not be invited or rejected on the basis of percentage above or below the estimated cost. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. Procurement Responsibility: Bangladesh Bureau of Statistics (BBS) is the implementing agency (IA) who will be responsible for all procurements. Procurement Threshold Bank-financed all contracts at or above the thresholds set out in the below table 1 are subject to the Bank’s procurement prior review. Table 1: Procurement Prior Review Thresholds (US$ millions) High Substant Modera Low Type of procurement risk ial risk te risk risk Works (including turnkey, supply & installation of plant and equipment, 5 10 15 20 and PPP) Goods, information technology and 1.5 2 4 6 non-consulting services Consultants: firms 0.5 1 2 4 Consultants: individuals 0.2 0.3 0.4 0.5 Irrespective of the contract value, the following procurement activities are subject to the Bank’s procurement prior review: a. procurement processes involving contract negotiations as, described in paragraphs 6.34-36 of Section VI of the Procurement Regulation for Borrowers; b. competitive dialogue; c. sustainable procurement; and d. best and final offer. The determination of whether a contract meets the procurement prior review threshold is based on the estimated value of the contract, including all taxes and duties payable under the contract. PROCUREMENT Bangladesh : Accelerating and Strengthening Skills for Economic Transformation PLAN General Information Country: Bangladesh 2022-04-03 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167506 GPN Date: 2022-04-18 Project Name: Accelerating and Strengthening Skills for Economic Transformation Loan / Credit No: IDA / 68740 Technical and Madrasah Education Division Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure Component 3: Capacity Dev ment Document - BD-TMED-317150-CW-RFB / elopment, Project Managem Single Stage - One E Under Imple 2023-11-0 IDA / 68740 Post Request for Bids Open - National 1 Envelope proce 174,400.00 0.00 2023-02-28 2023-03-23 2023-03-21 2023-03-27 2023-05-02 2023-04-18 2023-07-01 2023-08-05 Office refurbishment of DTE ent, Social Marketing and M nvelope mentation 3 ss (Non Bank-SPD onitoring & Evaluation ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BD-TMED-286889-GO-RFB / Component 3: Capacity Dev Procurement of Desktop Com elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 66,176.47 0.00 Signed 2022-04-05 2022-05-24 2022-04-10 2022-05-22 2022-06-13 2022-06-21 2022-07-03 2022-07-26 2023-01-22 puter, UPS, Laptop Computer ent, Social Marketing and M nvelope , Photocopier, Printer,Scanne onitoring & Evaluation r, DSLR Camera,etc BD-TMED-317151-GO-RFB / Component 1: Transforming Establishment of Internet & T Formal Skills Development f Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 17,450.00 0.00 2022-10-10 2022-10-25 2022-11-04 2022-12-04 2023-01-08 2023-07-07 elecom Network of the Projec or Future of Work, Inclusiven nvelope ementation t Office ess, and Resilience BD-TMED-317152-GO-RFB / Component 3: Capacity Dev Supply & installation of Offic elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 16,280.00 0.00 Signed 2022-10-10 2022-11-30 2022-10-15 2022-11-26 2022-12-15 2022-12-26 2023-01-08 2023-01-30 2023-03-01 e Equipment (Photocopier, Pr ent, Social Marketing and M nvelope inter & Scanner) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317153-GO-RFB / elopment, Project Managem Single Stage - One E Pending Impl Supply and installation of PA IDA / 68740 Post Request for Bids Open - National 11,630.00 0.00 2022-10-11 2022-10-16 2022-11-27 2022-12-27 2023-01-31 2023-03-02 ent, Social Marketing and M nvelope ementation and multimedia system onitoring & Evaluation G2B / Supply and Installatio Component 3: Capacity Dev n of Laptop, Intercom System elopment, Project Managem Single Stage - One E Under Imple IDA / 68740 Post Request for Bids Open - National 32,500.00 0.00 2023-05-21 2023-06-12 2023-05-26 2023-06-12 2023-06-16 2023-07-31 2023-09-04 2023-12-03 and LAN for PMU including all ent, Social Marketing and M nvelope mentation accessories onitoring & Evaluation Component 3: Capacity Dev G5A / Supply of Furniture an elopment, Project Managem Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 232,550.00 0.00 2023-05-21 2023-05-26 2023-06-16 2023-07-31 2023-09-04 2024-01-02 d Fixtures for PMU office ent, Social Marketing and M nvelope ementation onitoring & Evaluation Component 3: Capacity Dev G11A / Supply of Computer elopment, Project Managem Request for Quota Single Stage - One E Under Imple IDA / 68740 Post Open - National 2,325.00 0.00 2023-05-26 2023-06-19 2023-06-22 2023-07-13 Consumables ent, Social Marketing and M tions nvelope mentation onitoring & Evaluation Component 3: Capacity Dev G15A / Supply of Stationarie elopment, Project Managem Request for Quota Single Stage - One E Pending Impl IDA / 68740 Post Open - National 1,400.00 0.00 2023-06-02 2023-06-29 2023-07-20 s for PMU office ent, Social Marketing and M tions nvelope ementation onitoring & Evaluation G57 / Supply of Materials for Component 1: Transforming Seminar, Workshops and Con Formal Skills Development f Single Stage - One E Pending Impl IDA / 68740 Post Request for Bids Open - National 232,550.00 0.00 2023-05-28 2023-06-02 2023-06-30 2023-07-30 2023-09-10 2025-09-09 ferences under framework co or Future of Work, Inclusiven nvelope ementation ntract ess, and Resilience G59 / Supply of Project Mana Component 3: Capacity Dev gement Information System elopment, Project Managem Single Stage - One E Under Imple IDA / 68740 Post Request for Bids Open - National 286,000.00 0.00 2023-05-28 2023-05-18 2023-06-02 2023-05-21 2023-06-04 2023-06-21 2023-08-03 2023-09-07 2023-12-06 Software with 04 year opera ent, Social Marketing and M nvelope mentation tional and maintenance supp onitoring & Evaluation ort Component 3: Capacity Dev BD-TMED-286891-GO-RFB / elopment, Project Managem Single Stage - One E Supply of Accounts and other IDA / 68740 Post Request for Bids Open - National 12,941.18 0.00 Canceled 2022-05-03 2022-05-08 2022-06-19 2022-07-19 2022-08-23 2023-02-19 ent, Social Marketing and M nvelope Software onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286890-GO-RFB / elopment, Project Managem Single Stage - One E IDA / 68740 Post Request for Bids Open - National 35,294.12 0.00 Canceled 2022-04-12 2022-04-17 2022-05-29 2022-06-28 2022-08-02 2023-01-29 Supply of furniture for PMU ent, Social Marketing and M nvelope onitoring & Evaluation NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Transforming NCS1A / Selection of Event Formal Skills Development f Single Stage - One E Pending Impl Management firm for Semina IDA / 68740 Post Request for Bids Open - National 55,800.00 0.00 2023-05-28 2023-06-02 2023-06-30 2023-08-29 2023-10-03 2024-03-31 or Future of Work, Inclusiven nvelope ementation rs and Workshops ess, and Resilience CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 BD-TMED-286611-CS-QCBS / Selection of firm/ institution f Component 1: Transforming or organizing seminars and w Formal Skills Development f Quality And Cost- orkshops for TTIs (1), Partner IDA / 68740 Post Open - National 228,235.29 0.00 Canceled 2022-04-03 2022-04-24 2022-06-07 2022-07-05 2022-08-04 2022-09-08 2022-10-13 2023-10-13 or Future of Work, Inclusiven Based Selection organizations (1), RPL for em ess, and Resilience ployers and workers (2) and DTE (1), project launching ce remony (1) BD-TMED-286628-CS-QCBS / Component 3: Capacity Dev Selection of Consultant for R elopment, Project Managem Quality And Cost- apid Assessment and follow- IDA / 68740 Post Open - National 117,647.06 0.00 Canceled 2022-04-20 2022-05-11 2022-06-24 2022-07-22 2022-08-21 2022-09-25 2022-10-30 2023-10-30 ent, Social Marketing and M Based Selection up on Diploma Students by D onitoring & Evaluation TE (1), Demand and Gap Ana lysis by BTEB (1) Component 3: Capacity Dev BD-TMED-286635-CS-QCBS / elopment, Project Managem Quality And Cost- Survey and Studies by BMET IDA / 68740 Post Open - National 235,294.12 0.00 Canceled 2022-04-27 2022-05-18 2022-07-01 2022-07-29 2022-08-28 2022-10-02 2022-11-06 2023-11-06 ent, Social Marketing and M Based Selection (2), NSDA (1), DTE (1) onitoring & Evaluation BD-TMED-286641-CS-FBS / S Component 3: Capacity Dev election of Consultant for TV elopment, Project Managem Fixed Budget Sele Pending Impleme IDA / 68740 Post Open - National 29,411.76 0.00 2022-04-10 2022-05-01 2022-06-14 2022-07-12 2022-08-11 2022-09-15 2022-10-20 2023-10-20 C production (1), Radio Ad pr ent, Social Marketing and M ction ntation oduction (2) onitoring & Evaluation BD-TMED-286888-CS-QCBS / Component 3: Capacity Dev Selection of Consulting Firm f elopment, Project Managem Quality And Cost- IDA / 68740 Post Open - National 174,117.65 0.00 Canceled 2022-04-24 2022-05-15 2022-06-28 2022-07-26 2022-08-25 2022-09-29 2022-11-03 2023-11-03 or Competency Standard Dev ent, Social Marketing and M Based Selection elopment for BTEB (12), BME onitoring & Evaluation T (40), S51 / Selection of Consultant for Demand and Gap Analysi Component 3: Capacity Dev s under BTEB: Analyzing the elopment, Project Managem Consultant Qualifi Skills and Competency Gaps IDA / 68740 Post Open - National 58,000.00 0.00 Under Review 2023-03-01 2023-03-23 2023-03-22 2023-05-05 2023-06-23 2023-08-04 2024-01-31 ent, Social Marketing and M cation Selection of the Selected Diploma in En onitoring & Evaluation gineering Courses Running U nder the Bangladesh Technic al Education Board S55A / Selection of Consulta nt for Survey and Studies un Component 3: Capacity Dev der BTEB on Analyzing Weak elopment, Project Managem Quality And Cost- IDA / 68740 Post Open - National 93,000.00 0.00 Under Review 2023-03-01 2023-03-23 2023-03-22 2023-05-05 2023-06-30 2023-07-30 2023-09-03 2023-10-15 2024-04-12 nesses, Prospects, and Effect ent, Social Marketing and M Based Selection iveness of Industrial Attachm onitoring & Evaluation ent of Diploma in Engineerin g Courses Running S59A / Selection of Consultin Component 3: Capacity Dev g firm for Surveys and Studie elopment, Project Managem Consultant Qualifi IDA / 68740 Post Open - National 58,000.00 0.00 Under Review 2023-03-07 2023-03-23 2023-03-28 2023-05-11 2023-06-22 2023-08-03 2024-01-30 s under NSDA (Sector: Creati ent, Social Marketing and M cation Selection ve Media) onitoring & Evaluation INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Capacity Dev BD-TMED-286652-CS-INDV / elopment, Project Managem Individual Consult Selection of Financial Manag IDA / 68740 Prior Open 352,941.18 0.00 Signed 2022-04-03 2022-04-18 2022-05-22 2022-09-21 2022-06-12 2022-10-24 2022-07-17 2023-01-13 ent, Social Marketing and M ant Selection ement Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286655-CS-INDV / elopment, Project Managem Individual Consult Selection of Junior Financial IDA / 68740 Post Open 197,647.06 0.00 Signed 2022-04-03 2022-04-16 2022-05-22 2023-02-23 2022-06-12 2023-02-23 2022-07-17 2023-01-13 ent, Social Marketing and M ant Selection Management Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286658-CS-INDV / elopment, Project Managem Individual Consult Selection of Procurement Spe IDA / 68740 Prior Open 364,705.88 0.00 Signed 2022-04-04 2022-04-17 2022-05-23 2022-09-21 2022-06-13 2022-10-27 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection cialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286660-CS-INDV / elopment, Project Managem Individual Consult Selection of Junior Procureme IDA / 68740 Prior Open 218,823.53 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2023-02-23 2022-06-13 2023-03-28 2022-07-18 2023-05-02 2023-01-14 ent, Social Marketing and M ant Selection nt Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286661-CS-INDV / elopment, Project Managem Individual Consult Selection of IDG Managemen IDA / 68740 Prior Open 317,647.06 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2022-09-21 2022-06-13 2022-10-25 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection t Specialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286883-CS-INDV / elopment, Project Managem Individual Consult Selection of ICT and MIS Spec IDA / 68740 Prior Open 282,352.94 0.00 Signed 2022-04-04 2022-04-20 2022-05-23 2022-09-21 2022-06-13 2022-10-25 2022-07-18 2023-01-14 ent, Social Marketing and M ant Selection ialist (1) onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286885-CS-INDV / elopment, Project Managem Individual Consult Under Implement Selection of E&S safeguard S IDA / 68740 Prior Open 235,294.12 0.00 2022-04-28 2022-08-07 2022-06-16 2022-07-07 2022-08-11 2023-02-07 ent, Social Marketing and M ant Selection ation pecialist (1) onitoring & Evaluation BD-TMED-316744-CS-INDV / Component 3: Capacity Dev Selection of TVET & Industry elopment, Project Managem Individual Consult Under Implement IDA / 68740 Prior Open - National 310,000.00 0.00 2022-09-27 2022-11-07 2022-11-15 2022-12-06 2023-01-10 2025-01-09 Development Management S ent, Social Marketing and M ant Selection ation pecialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-286886-CS-INDV / elopment, Project Managem Individual Consult Pending Impleme Selection of Short Term Tech IDA / 68740 Prior Open - National 350,000.00 0.00 2022-09-27 2022-11-15 2022-12-06 2023-01-10 2023-07-09 ent, Social Marketing and M ant Selection ntation nical Specialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317145-CS-INDV / elopment, Project Managem Individual Consult Selection of Monitoring & Eva IDA / 68740 Prior Open - National 590,000.00 0.00 Under Review 2022-09-30 2022-11-07 2022-11-18 2022-12-09 2023-01-13 2025-01-12 ent, Social Marketing and M ant Selection luation Specialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317147-CS-INDV / elopment, Project Managem Individual Consult Selection of Skills Training Sp IDA / 68740 Prior Open - National 310,000.00 0.00 Under Review 2022-10-05 2022-11-07 2022-11-23 2022-12-14 2023-01-18 2025-01-07 ent, Social Marketing and M ant Selection ecialist onitoring & Evaluation Component 3: Capacity Dev BD-TMED-317148-CS-INDV / elopment, Project Managem Individual Consult Under Implement Selection of Communication IDA / 68740 Prior Open - National 310,000.00 0.00 2022-10-05 2022-11-07 2022-11-23 2022-12-14 2023-01-18 2025-01-17 ent, Social Marketing and M ant Selection ation Speciaist onitoring & Evaluation Page 2 Component 3: Capacity Dev S39B / Selection of IDG Spec elopment, Project Managem Individual Consult IDA / 68740 Post Limited 34,800.00 0.00 Under Review 2023-06-08 2023-06-06 2023-06-13 2023-07-04 2023-08-15 2024-02-11 ialist (Health) ent, Social Marketing and M ant Selection onitoring & Evaluation Page 3 PROCUREMENT PLAN (Textual Part) Project information: West African Power Pool, Ghana, Cote d’Ivoire, WAPP Ghana Cote d-Ivoire Power Interconnection Project (P178923) Project Implementation agency: West African Power Pool (WAPP) Date of the Procurement Plan: March 8, 2023 Period covered by this Procurement Plan: March 2023 – Dec 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable for those contracts identified in the Procurement Plan tables] PROCUREMENT Western and Central Africa : WAPP Ghana-Cote d'Ivoire Interconnection Project PLAN General Information Country: Western and Central Africa 2023-03-13 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178923 GPN Date: Project Name: WAPP Ghana-Cote d'Ivoire Interconnection Project Loan / Credit No: / , IDA / V4680 WEST AFRICAN POWER POOL Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WAPP-348040-CS-QCBS / Update/preparation of feasibi lity studies, safeguards instru Quality And Cost- Open - Internationa Under Implement / Prior 4,000,000.00 0.00 2023-03-10 2023-03-16 2023-03-17 2023-03-17 2023-04-20 2023-05-09 2023-06-01 2023-06-15 2023-07-16 2023-08-20 2025-01-05 ments and bidding document Based Selection l ation s related to the construction of the Ghana-Côte d’Ivoire In terconnection INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BJ-WAPP-348052-CS-CDS / D evelopment and Implementa Direct - Internation Pending Impleme / Post Direct Selection 500,000.00 0.00 2023-04-02 2023-04-26 2023-06-30 2023-12-27 tion of Grid Code Gradual Co al ntation mpliance Framework (CESI) BJ-WAPP-348057-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Operation Planning Engineer ant Selection l ntation s N.1 BJ-WAPP-348069-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Operation Planning Engineer ant Selection l ntation s N.2 BJ-WAPP-348072-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Operation Planning Engineer ant Selection l ntation s N.3 BJ-WAPP-348093-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 DTS/EMS Engineer ant Selection l ntation BJ-WAPP-348095-CS-INDV / P Individual Consult Open - Internationa Pending Impleme ower System Data Base Man / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 ant Selection l ntation agement Engineer BJ-WAPP-348096-CS-INDV / P Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 ower System Data Analytics ant Selection l ntation Engineer BJ-WAPP-348102-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Market Regulation Officer ant Selection l ntation BJ-WAPP-348103-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Market Operation Officer N.1 ant Selection l ntation BJ-WAPP-348107-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 Market Operation Officer N.2 ant Selection l ntation BJ-WAPP-348110-CS-INDV / Individual Consult Open - Internationa Pending Impleme / Post 106,000.00 0.00 2023-04-02 2023-07-30 2023-08-29 2023-10-03 2024-10-02 SCADA Database Specialist ant Selection l ntation BJ-WAPP-361659-CS-CDS / C Direct - Internation Under Implement onsultancy Services for Devel IDA / V4680 Post Direct Selection 250,000.00 0.00 2023-05-22 2023-05-23 2023-06-15 2023-05-24 2023-08-19 2024-08-13 al ation opment of Transitional Provis ions Framework Page 1 PLAN DE PASSATION DE MARCHÉS Information sur le Projet : Emprunteur/Bénéficiaire République Togolaise Ministère Responsable Nom du Projet Identification P172769 Agence d’exécution du Projet : [A insérer] Date du plan de passation des marchés : [A indiquer] Période couverte par ce plan de passation des marchés : [A indiquer] Date d’approbation par la Banque du plan de passation de marchés : [A indiquer] Date de publication de l’Avis Général de Passation des Marchés : [A indiquer] Evaluation de risque par P-RAMS (Procurement Risk Assessment and Management System) : Elevé Préambule Conformément au paragraphe 5.9 du “Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI)” (Novembre 2020) (“Règlement de Passation des Marchés”), le Système électronique de la Banque de suivi systématique des transactions de marchés publics (STEP) sera utilisé pour préparer, valider et actualiser les plans de passation des marchés et effectuer toutes les transactions liées à la passation des marchés du projet. Ce texte ainsi que les tableaux du plan de passation des marchés présents dans STEP constituent le plan de passation des marchés du projet. Les conditions suivantes s'appliquent à toutes les activités de passation de marchés du plan de passation de marchés. Les autres éléments du plan de passation des marchés tels que requis au paragraphe 4.4 du Règlement de passation des marchés sont énoncés dans STEP. Les Dossiers types de passation des marchés publics de la Banque devront être utilisés pour tous les contrats soumis à la concurrence internationale, ainsi que pour tous les autres contrats soumis à cette obligation telle que spécifiée dans les tableaux du plan de passation des marchés de STEP. Procédures nationales de passation des marchés : En accord avec le paragraphe 5.3 du Règlement de passation des marchés, dans le cas où la procédure de passation des marchés se fera au niveau national (telle que spécifiée dans les tableaux du plan de passation des marchés inclus dans STEP), les procédures nationales de passation des marchés du pays considéré pourront être utilisées. Si l’Emprunteur utilise ses propres procédures d’appel d’offres national ouvert telles qu’énoncées dans la loi No. 2009-013 du 30 juin 2009 relative aux Marchés Publics et Délégation de Service Public, le Décret Nº 2009-277/PR du 11 novembre 2009 portant Code des Marchés Publics et Délégation de Service Public, et les textes d’application y afférents, ces arrangements sont soumis aux dispositions du paragraphe 5.4 du Règlement de passation des marchés et aux conditions suivantes : - Le dossier d’appel d’offres/à propositions oblige le Soumissionnaire/les proposants présentant une Offre/Proposition à déposer un agrément signé, qui sera joint à tout contrat éventuel, pour confirmer qu’il applique et respecte les Directives de la Banque pour la lutte contre la corruption, y compris sans limitation, le droit de la Banque de sanctionner et les droits de la Banque pour l’inspection e l’audit ; - Le droit de la Banque d’examiner le dossier et les activités de passation des marchés. Lorsque l’Emprunteur utilise d’autres procédures que l’appel d’offres national ouvert, ces procédures devront être en accord avec les dispositions du paragraphe 5.5 du Règlement de passation des marchés. Crédit-bail tel que spécifié au paragraphe 5.10 du Règlement de Passation des marchés : Le crédit-bail peut être utilisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Achat de biens d’occasion tel que spécifié au paragraphe 5.11 du Règlement de Passation des Marchés est autorisé pour les contrats indiqués comme tel dans le Plan de passation des marchés. « Sans objet » Préférence nationale telle que spécifiée au paragraphe 5.51 du Règlement de Passation des Marchés (Fournitures et Travaux). Fournitures : ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés Travaux ne s’applique pas pour les contrats indiqués dans les tableaux du Plan de passation des marchés L’Assistance directe à la mise en œuvre (sigle HEIS en anglais) tel que précisée aux paragraphes 3.10 et 3.11 du Règlement de Passation des marchés ne s’applique pas. Autres informations pertinentes sur la passation des marchés : Néant I. TRAVAUX, FOURNITURES ET SERVICES AUTRES QUE LES SERVICES DE CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable : Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Juillet 2016, révisé en Novembre 2017. Catégories de marchés Montants Observations estimatifs des contrats en millions de dollars américains Travaux (incluant clé à main, Fourniture et Installation, et les >= 5 Partenariat Public - Privé -PPP) Biens, Système d’Information et de Services autres que les >= 1,5 Services intellectuels Contrats à Travaux passer par (incluant clé à >= 5 entente main, directe Fourniture et Les justifications de Installation, et l’entente directe les Partenariat devront être jointes et Public - Privé - approuvées avec PPM PPP) Biens, Système d’Information et de Services >= 1,5 autres que les Services intellectuels 2. Seuils pour les méthodes de passation des marchés : Les seuils de passation des marchés se présentent comme suit au vu des conditions du marché : FOURNITURES ET SERVICES AUTRE QUE LES SERVICES DE CONSULTANTS TRAVAUX (US$ équivalent) (US$ équivalent) AOI AON DC AOI AON DC < < 100.000 ≥5.000.000 <5.000.000 200.00 ≥500.000 <500.000 0 3. Dispositions spéciales sur les marchés : Concernant les acquisitions de véhicules et de carburant, en fonction des circonstances et des besoins spécifiques du pays, le seuil pour la consultation de fournisseurs pourrait être porté à la contre-valeur d’USD 500,000 (en prenant soin de consulter tous les principaux concessionnaires de marque ou distributeurs de produits pétroliers). Liste de Marchés de Travaux, Fournitures, et Services autres que Consultant Date Type Méthode/ Montan de Comme d'Exa Modalité Appro t lance ntaire Réf. DESCRIP men de che de Estimat ment /Fin de No. TION par la passatio march if en de la prestat Banqu n des és US$ procé ions e marchés dure II. SÉLECTION DES CONSULTANTS 1. Dispositions relatives aux seuils de revue préalable des marchés : Décisions de sélection sujette à la revue préalable de la Banque comme indiqué dans Seuils requis pour les décisions de marchés soumis à la revue préalable de la Banque, tel que prévu dans les paragraphes 3.5 à 3.8 de la Section III, et de l’Annexe II du Règlement de Passation des Marchés pour les Emprunteurs sollicitant le Financement de Projets d’Investissement (FPI), en date de Novembre 2020. Méthode de Seuils de revue a priori Observations sélection/Catégories de Montants estimatifs des marchés contrats en millions de dollars américains Méthode compétitive/Firmes de >= 0.5 consultants Entente directe/firmes de Les justifications pour consultants >= 0.5 l’entente directe devront être jointes et approuvées Entente avec le PPM directe/Consultants >= 0.2 individuel Méthode Compétitive >= 0.2 (Comparaison de CVs)/ Consultants individuels 2. Liste restreinte composée entièrement de firmes nationales: La liste restreinte de consultants pour les prestations d’études d’ingénierie, de contrôle et de surveillance estimées à moins de 300,000 US$ par contrat, et pour tout autre type de prestations, estimées à moins de 100 000 US$ par contrat, peut comporter entièrement de consultants nationaux en conformité avec les dispositions des Règlements de Passation des marchés., et l’Emprunteur ne procède pas à une publication dans UNDB 3. Autre arrangement spécial de Sélection de consultants : Le seuil pour l’utilisation de la méthode de sélection de consultant fondée sur les qualifications des consultants est déterminé au cas par cas en tenant compte de la nature et de la complexité de la mission ; cependant, ce seuil ne devrait pas dépasser la contre-valeur de USD 300,000 sauf dans des cas exceptionnels telles des situations d’urgence en conformité au Règlement de Passation des marchés II- Liste de Marchés de Services de Consultants Date Méthod Comm Montan Type de Ré e de entair t d'Exam Approch lancem f. DESCRIPTION passati e/Fin Estimat en par e de ent de No DES MISSIONS on des des if en la Marché la . marché presta US$ Banque procéd s tions ure Lexique des Sigles et Abréviations ARMP Autorité de Régulation des Marchés Publics AOI Appel d’Offres International AON Appel d’Offres National A Revue a posteriori posteriori A Priori Revue a priori CI Consultant Individuel DC Demande de Cotations DNCMP Direction Nationale de Contrôle des Marchés Publics ED Sélection Directe ou Entente Directe PPM Plan de Passation des Marchés SFQ Sélection Fondée sur la Qualité SFQC Sélection Fondée sur la Qualité et le Coût SMC Sélection au Moindre Coût SQC Sélection fondée sur les Qualifications des Consultants PROCUREMENT Western and Central Africa : West Africa Food System Resilience Program (FSRP) PLAN General Information Country: Western and Central Africa 2022-08-09 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P172769 GPN Date: Project Name: West Africa Food System Resilience Program (FSRP) Loan / Credit No: IDA / 69980, IDA / D9250 FOOD SYSTEM RESILIENCE PROGRAM - NIGER Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure NE-FRSP-NE-306233-CW-RF ment Document - Request for Quota Single Stage - One E 2023-01-3 Q / Travaux d'extension du si IDA / 69980 Project Management Post Limited 1 Envelope proce 121,951.00 0.00 Signed 2022-08-20 2022-09-22 2022-09-12 tions nvelope 0 ège de l’UGP PARIIS pour le c ss (Non Bank-SPD ompte du FSRP ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306159-GO-RFB Sustainability and adaptive c / Acquisition pour doter le CR Single Stage - One E IDA / 69980 apacity of the food system’s Post Request for Bids Open - National 313,589.00 0.00 Signed 2022-09-05 2022-12-12 2022-09-10 2022-12-13 2022-10-10 2023-01-16 2022-10-25 2023-01-27 2022-11-29 2023-03-29 S et les labos en équipement nvelope productive base s complémentaires clés NE-FRSP-NE-306190-GO-RFB Sustainability and adaptive c Single Stage - One E / Acquisition de semences (A IDA / 69980 apacity of the food system’s Post Request for Bids Open - National 143,728.00 0.00 Completed 2022-08-31 2022-10-07 2022-09-05 2022-10-10 2022-10-05 2022-11-02 2022-10-15 2022-11-23 2022-11-15 2022-12-30 2023-01-21 nvelope ppui en intrants agricoles) productive base NE-FRSP-NE-306228-GO-RFQ Request for Quota Single Stage - One E IDA / 69980 Project Management Post Limited 52,265.00 0.00 Completed 2022-10-25 2023-03-30 2022-11-21 2022-12-31 2023-04-16 / Acquisition de mobilier de b tions nvelope ureau NE-FRSP-NE-306961-GO-RFQ Request for Quota Single Stage - One E / Acquisition de matériel infor IDA / 69980 Project Management Post Limited 52,265.00 38,580.81 Completed 2022-08-15 2022-08-22 2022-08-31 2022-09-09 2022-10-15 2022-09-26 tions nvelope matique pour l'équipe FSRP NE-FRSP-NE-342474-GO-RFQ / Acquisition d'équipements c Digital advisory services for Request for Quota Single Stage - One E Pending Impl omplémentaires et mise en IDA / D9250 agriculture and food crisis pr Post Limited 52,632.00 0.00 2023-06-06 2023-06-14 2023-07-14 tions nvelope ementation marche de la station de réce evention and management ption des données satellitale s de la DGPIA et DGGR NE-FRSP-NE-342493-GO-RFQ Digital advisory services for / Equipement des structures, Request for Quota Single Stage - One E Pending Impl IDA / D9250 agriculture and food crisis pr Post Limited 17,545.00 0.00 2023-06-05 2023-06-13 2023-07-13 renforcement de la cellule gé tions nvelope ementation evention and management omatique par acquisition des drones. NE-FRSP-NE-342526-GO-RFQ / Acquisitions de Kits de com Digital advisory services for Request for Quota Single Stage - One E Pending Impl munication, d'information de IDA / D9250 agriculture and food crisis pr Post Limited 13,000.00 0.00 2023-04-05 2023-04-13 2023-04-30 tions nvelope ementation s impacts potentiels aux agro evention and management pasteurs et décideurs NE-FRSP-NE-342538-GO-RFQ Regional food market integr Request for Quota Single Stage - One E Pending Impl / Equipement des laboratoire IDA / D9250 Post Limited 43,333.00 0.00 2023-03-20 2023-03-28 2023-05-02 ation and trade tions nvelope ementation s (LABOCEL, DGPV, LANA, LT A et LNCCS) NE-FRSP-NE-342565-GO-RFQ Regional food market integr Request for Quota Single Stage - One E Pending Impl / Acquisition de matériel de c IDA / D9250 Post Limited 26,315.00 0.00 2023-04-15 2023-04-25 2023-05-10 ation and trade tions nvelope ementation ollecte des données NE-FRSP-NE-342578-GO-RFB Sustainability and adaptive c Single Stage - One E Under Imple / Appui en intrants des cultur IDA / D9250 apacity of the food system’s Post Request for Bids Open - National 221,053.00 0.00 2023-03-15 2023-03-24 2023-03-20 2023-03-31 2023-04-20 2023-04-27 2023-04-28 2023-05-27 2023-05-22 2023-06-26 nvelope mentation es pluviales (semences et en productive base grais) NE-FRSP-NE-342588-GO-RFB Single Stage - One E Under Imple IDA / D9250 Project Management Post Request for Bids Open - National 390,351.00 0.00 2023-03-15 2023-03-23 2023-03-20 2023-03-23 2023-04-19 2023-04-27 2023-04-28 2023-05-15 2023-05-25 2023-07-29 / Acquisition de matériel roul nvelope mentation ant NE-FRSP-NE-342590-GO-RFQ Request for Quota Single Stage - One E / Acquisition de Motos au pro IDA / D9250 Project Management Post Limited 13,160.00 0.00 Completed 2023-03-13 2023-03-01 2023-03-21 2023-03-31 2023-04-05 tions nvelope fit de l'UCP et les Régions NE-FRSP-NE-342591-GO-RFQ Request for Quota Single Stage - One E / Acquisition de Matériels info IDA / D9250 Project Management Post Limited 26,315.00 0.00 Completed 2023-03-03 2023-03-06 2023-03-10 2023-03-31 2023-04-05 tions nvelope rmatiques au profit de l'UCP NE-FRSP-NE-342499-GO-RFQ Digital advisory services for Request for Quota Single Stage - One E Pending Impl / Achats d'équipements infor IDA / D9250 agriculture and food crisis pr Post Limited 35,088.00 0.00 2023-05-07 2023-05-16 2023-05-31 tions nvelope ementation matiques (Ordinateurs et Tél evention and management éphones) NE-FRSP-NE-306204-GO-RFB / Acquisition de Matériels info Regional food market integr Single Stage - One E Pending Impl IDA / D9250 Post Request for Bids Open - National 122,807.00 0.00 2023-06-12 2023-06-17 2023-07-17 2023-07-27 2023-08-26 2023-10-10 rmatiques pour les structures ation and trade nvelope ementation et partenaires du FSRP NE-FRSP-NE-361809-GO-RFQ Sustainability and adaptive c / Acquisition de semences en Request for Quota Single Stage - One E IDA / D9250 apacity of the food system’s Post Limited 87,000.00 0.00 Completed 2023-05-29 2023-06-01 2023-06-09 2023-06-24 complément de quantités po tions nvelope productive base ur la campagne hivernale 20 23 NE-FRSP-NE-364001-GO-RFB / Fourniture et installation d' Regional food market integr Single Stage - One E Pending Impl un générateur d'azote liquid IDA / D9250 Post Request for Bids Open - National 280,700.00 0.00 2023-06-15 2023-06-22 2023-07-21 2023-07-31 2023-08-31 2023-11-30 ation and trade nvelope ementation e en appui aux unités de con servations de semences ani males NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Page 1 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306238-NC-DIR / Fourniture et installation du IDA / 69980 Project Management Post Direct Selection Direct - National 17,422.00 0.00 Signed 2022-08-30 2022-09-09 2022-09-04 2022-10-07 2022-09-23 2023-09-23 logiciel informatique et comp table TOM2PRO CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306060-CS-CQS / Recrutement consultant po Digital advisory services for Consultant Qualifi Pending Impleme ur l'évaluation des capacités IDA / 69980 agriculture and food crisis pr Post Open - National 43,554.00 0.00 2022-08-30 2022-09-20 2022-11-03 2022-12-03 2022-12-30 2023-02-28 cation Selection ntation techniques et les besoins en evention and management formation pour soutenir le PD O du FSRP NE-FRSP-NE-306174-CS-CQS Sustainability and adaptive c Consultant Qualifi / Recrutement des ONGs pou IDA / 69980 apacity of the food system’s Post Open - National 300,000.00 0.00 Signed 2022-08-20 2022-10-10 2022-09-10 2022-10-24 2022-10-24 2022-12-14 2022-11-23 2023-02-20 2022-12-28 2023-12-28 cation Selection r l'Elaboration d'un Plan GIP productive base NE-FRSP-NE-306184-CS-CQS Sustainability and adaptive c / Recrutement consultant po Consultant Qualifi Pending Impleme IDA / 69980 apacity of the food system’s Post Open - National 69,686.00 0.00 2022-08-25 2022-09-15 2022-10-25 2022-11-24 2022-12-16 2023-02-14 ur l’Élaboration des schémas cation Selection ntation productive base d’aménagements de bassin v ersant NE-FRSP-NE-306187-CS-CQS Consultant Qualifi Under Implement / Recrutement Consultant po IDA / 69980 Project Management Post Open - National 36,794.00 0.00 2022-09-05 2022-12-08 2022-09-20 2023-01-26 2022-10-11 2023-05-05 2022-10-26 2022-11-01 2022-12-16 cation Selection ation ur l’Etude de référence NE-FRSP-NE-306235-CS-QCB Quality And Cost- S / Recrutement d’un Consult IDA / 69980 Project Management Post Open - National 8,711.00 0.00 Signed 2022-08-30 2022-09-05 2022-09-20 2022-10-13 2022-10-31 2022-12-22 2022-11-30 2023-01-20 2022-12-09 2023-02-28 2022-12-21 2023-02-28 2023-01-25 2024-01-25 Based Selection ant pour l’Audit annuel du pr ojet NE-FRSP-NE-342601-CS-CQS / Recrutement d'un consultan Sustainability and adaptive c Consultant Qualifi Open - Internationa Pending Impleme t pour les études de faisabilit IDA / D9250 apacity of the food system’s Post 263,160.00 0.00 2023-04-10 2023-04-20 2023-05-30 2023-07-05 2023-07-27 2024-01-23 cation Selection l ntation é technique de l'aménageme productive base nt des petits périmètres irrig ués NE-FRSP-NE-342663-CS-QCB Sustainability and adaptive c S / Recrutement d'un consult Quality And Cost- Open - Internationa Pending Impleme IDA / D9250 apacity of the food system’s Post 352,632.00 0.00 2023-05-05 2023-05-26 2023-07-09 2023-08-06 2023-09-05 2023-10-10 2023-11-14 2024-11-13 ant chargé des étude techniq Based Selection l ntation productive base ues des seuils de correction NE-FRSP-NE-342655-CS-QCB S / Recrutement d'un consult Sustainability and adaptive c ant pour les études de faisab Quality And Cost- Open - Internationa IDA / D9250 apacity of the food system’s Post 307,000.00 0.00 Under Review 2023-04-15 2023-05-20 2023-05-02 2023-06-15 2023-07-17 2023-07-28 2023-08-18 2023-09-22 2023-12-31 ilité technique et contrôle de Based Selection l productive base s travaux d'une petite retenu e d'eau dans la région de Till abéry NE-FRSP-NE-361744-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 300,000.00 0.00 2023-05-22 2023-05-26 2023-06-12 2023-07-12 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Zinder NE-FRSP-NE-361758-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 300,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Tahoua NE-FRSP-NE-361797-CS-CQS Sustainability and adaptive c / Recrutement d'ONG pour l'é Consultant Qualifi Under Implement IDA / D9250 apacity of the food system’s Post Limited 200,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 laboration d'un Plan GIP (Ges cation Selection ation productive base tion Intégrée du Paysage) da ns la région de Diffa NE-FRSP-NE-361801-CS-CQS / Recrutement d'ONG pour l'é Sustainability and adaptive c Consultant Qualifi Under Implement laboration d'un Plan GIP (Ges IDA / D9250 apacity of the food system’s Post Limited 200,000.00 0.00 2023-05-22 2023-05-26 2023-06-05 2023-07-05 2023-08-15 2025-08-14 cation Selection ation tion Intégrée du Paysage) da productive base ns la région de Tillabéry NE-FRSP-NE-361866-CS-QCB S / Recrutement d’un cabinet pour l’étude de faisabilité (AP Sustainability and adaptive c Quality And Cost- Open - Internationa S/APD/EIES/DAO) et le contrôl IDA / D9250 apacity of the food system’s Post 307,000.00 0.00 Under Review 2023-05-22 2023-05-20 2023-06-12 2023-07-24 2023-08-21 2023-08-31 2023-09-08 2023-10-13 2024-10-12 Based Selection l e des travaux d’aménageme productive base nt des bas-fonds (seuils d’ép andage/petits barrages) dans les régions de Tahoua et INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NE-FRSP-NE-306128-CS-IND Digital advisory services for Individual Consult Pending Impleme V / Recrutement consultant p IDA / 69980 agriculture and food crisis pr Post Limited 17,422.00 0.00 2022-08-15 2022-08-22 2022-09-05 2022-09-15 2022-11-14 ant Selection ntation our la mise à jour des param evention and management ètres d’analyse NE-FRSP-NE-306140-CS-IND V / Recrutement consultant p Digital advisory services for our identifier/répertorier les f Individual Consult IDA / 69980 agriculture and food crisis pr Post Limited 52,265.00 0.00 Signed 2022-10-10 2022-12-07 2022-10-31 2023-02-22 2022-11-15 2023-04-25 2022-11-16 2022-12-31 ournisseurs et évaluation des ant Selection evention and management besoins de services hydro m étéo, phyto, et agro météo (I ncluant le secteur privée) NE-FRSP-NE-306156-CS-IND V / Recrutement d'un prestat Digital advisory services for Individual Consult Pending Impleme aire pour l'identification des t IDA / 69980 agriculture and food crisis pr Post Limited 17,422.00 0.00 2022-09-15 2022-09-30 2022-10-12 2022-10-15 2022-11-29 ant Selection ntation ypes de services et des mod evention and management alités d'engagement du sect eur privé NE-FRSP-NE-306516-CS-CDS / Service de consultant pour l IDA / 69980 Project Management Post Direct Selection Direct - National 26,132.00 0.00 Completed 2022-08-15 2022-08-19 2022-08-22 2022-09-20 2022-09-07 2022-10-07 2023-03-23 e recrutement du personnel complémentaire du FSRP Page 2 NE-FRSP-NE-306199-CS-IND V / Recrutement d'un Consult Regional food market integr Individual Consult ant pour l’Identification des a IDA / 69980 Post Limited 10,180.00 0.00 Canceled 2022-09-26 2022-10-10 2022-10-31 2022-11-15 2022-12-30 ation and trade ant Selection cteurs dans les chaines de va leur de Niébé et Oignon NE-FRSP-NE-309010-CS-IND V / Recrutement d'un Consult Regional food market integr Individual Consult IDA / 69980 Post Limited 5,500.00 0.00 Canceled 2022-09-26 2022-10-10 2022-10-31 2022-11-01 2022-12-01 ant pour l’Identification des a ation and trade ant Selection cteurs dans la chaine de vale ur Bétail-viande-lait NE-FRSP-NE-342594-CS-IND V / Recrutement d’un Consult Individual Consult ant pour l' Elaboration d'un g IDA / D9250 Project Management Post Limited 17,545.00 0.00 Under Review 2023-02-20 2023-02-22 2023-02-28 2023-03-10 2023-03-13 2023-05-02 ant Selection uide simplifié de gestion fina ncière pour les partenaires NE-FRSP-NE-342595-CS-IND V / Recrutement d'un consult Sustainability and adaptive c Individual Consult Pending Impleme ant pour l'élaboration d'une c IDA / D9250 apacity of the food system’s Post Limited 17,545.00 0.00 2023-04-03 2023-04-13 2023-04-20 2023-04-21 2023-05-31 ant Selection ntation artographie des groupes vuln productive base érables et constitution des b ases de données NE-FRSP-NE-342596-CS-IND Sustainability and adaptive c V / Recrutement d'un consult Individual Consult Pending Impleme IDA / D9250 apacity of the food system’s Post Limited 26,667.00 0.00 2023-04-01 2023-04-10 2023-04-21 2023-04-25 2023-06-14 ant pour l'élaboration de 3 pl ant Selection ntation productive base ans d’aménagement des zon es humides Page 3 PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Africa CDC Regional Investment Financing Program, P167916 Project Implementation agency: Ministry of Health and Ethiopian Public Health Institute Date of the Procurement Plan: August 19,2019 Period covered by this Procurement Plan: August 2019 to August 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement plan; Works: is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. PROCUREMENT Eastern and Southern Africa : Africa CDC Regional Investment Financing Project PLAN General Information Country: Eastern and Southern Africa 2020-02-24 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P167916 GPN Date: 2019-08-27 Project Name: Africa CDC Regional Investment Financing Project Loan / Credit No: IDA / 65040, IDA / 65030 Ministry of Health Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZM-MOH-139096-CW-RFB / C onstruction of Four Storey La Open - Internationa Single Stage - One E 19,407,600.0 2023-12-0 boratory Complex, Office co IDA / 65030 Public Health Assets Post Request for Bids 0.00 Canceled 2021-11-15 2022-01-31 2022-01-31 2021-11-20 2022-04-11 2022-05-11 2022-06-15 l nvelope 0 7 mplex and ancillary Building, Road works and drainage an d parking for ZNPHI/RCC ZM-MOH-320075-CW-RFQ / T ender for the Two (2) Comme Request for Quota rcial Borehole Siting, Drilling, Request for Quota Single Stage - One E 2023-06-1 IDA / 65040 Public Health Assets Post Limited tions (Non Bank-S 85,330.00 0.00 Canceled 2022-10-22 2022-12-17 Pump Installations, Fabricatio tions nvelope 5 PD) n and Erection of Steel Stora ge Water Tanks and Related Water works ZM-MOH-318958-CW-RFB / T Request for Bids - ender for the Construction of Single Stage - One E Small Works SPD 2023-08-0 1.6KM Perimeter Fence, Thre IDA / 65030 Public Health Assets Post Request for Bids Open - National 369,575.00 0.00 Canceled 2022-10-17 2022-10-06 2022-10-22 2022-12-03 2023-01-02 2023-02-06 nvelope (1 envelope proce 5 e (3) Guard Houses, Access R ss) oads and Installation of Temp oral Power Supply. ZM-MOH-325305-CW-RFB / T Request for Bids - ender for the Construction of Single Stage - One E Small Works SPD Under Imple 2023-09-1 1.6KM Perimeter Fence, Thre IDA / 65030 Public Health Assets Post Request for Bids Open - National 485,068.00 0.00 2022-11-23 2022-11-08 2022-11-28 2023-01-09 2022-12-16 2023-02-08 2023-01-20 2023-03-15 nvelope (1 envelope proce mentation 1 e (3) Guard Houses, Access R ss) oads and Installation of Temp oral Power Supply. ZM-MOH-325381-CW-RFQ / T ender for the Two (2) Comme Request for Quota rcial Borehole Siting, Drilling, Request for Quota Single Stage - One E Pending Imp 2023-07-2 IDA / 65030 Public Health Assets Post Limited tions (Non Bank-S 111,995.00 0.00 2022-11-28 2023-01-23 Pump Installations, Fabricatio tions nvelope lementation 2 PD) n and Erection of Steel Stora ge Water Tanks and Related Water works ZM-MOH-358223-CW-RFB / R National Procure efurbishment of BSL 2 Labor ment Document - Single Stage - One E Pending Imp 2024-06-0 atories at choma Veterinary l IDA / 65040 Public Health Assets Post Request for Bids Open - National 1 Envelope proce 449,503.69 0.00 2023-08-14 2023-08-19 2023-09-30 2023-10-30 2023-12-04 nvelope lementation 1 ab, Livingstone, Chinsali and ss (Non Bank-SPD Mansa, General Hospitals ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZM-MOH-139092-GO-RFQ / P Request for Quota Single Stage - One E IDA / 65030 Project Management Post Limited 10,000.00 83,170.45 Completed 2020-11-29 2020-12-29 2021-01-24 2021-04-24 2021-07-23 2021-04-24 rocurement of Office Equipm tions nvelope ent ZM-MOH-186758-GO-RFQ / P Request for Quota Single Stage - One E IDA / 65030 Project Management Post Limited 10,000.00 120,908.07 Completed 2020-11-21 2021-02-22 2021-01-16 2021-03-17 2021-07-15 2021-03-17 rocurement of Furniture for t tions nvelope he PIU ZM-MOH-139012-GO-UN / Pr UN Agencies (Dire Under Imple IDA / 65040 Public Health Assets Post Direct 605,000.00 0.00 2021-01-04 2021-01-09 2021-02-13 2021-08-12 ocurement of ten (10) motor ct) mentation vehicles ZM-MOH-139045-GO-RFQ / P Request for Quota Single Stage - One E rocurement of ECHO Equipm IDA / 65030 Public Health Assets Post Limited 44,417.00 401.40 Completed 2021-01-23 2021-02-24 2021-03-20 2021-04-13 2021-09-16 2021-04-13 tions nvelope ent for Laboratories in Provin ces and Districts. ZM-MOH-139067-GO-RFB / P Single Stage - One E IDA / 65030 Public Health Assets Post Request for Bids Open - National 117,000.00 0.00 Canceled 2020-12-01 2020-12-06 2021-01-17 2021-02-16 2021-03-23 2021-09-19 rocurement of EBS Tools nvelope ZM-MOH-139015-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Tools and Equi IDA / 65030 Public Health Assets Post Limited 48,000.00 0.00 Canceled 2021-08-28 2021-10-23 2022-04-21 tions nvelope pment for the Point of Entry ZM-MOH-139071-GO-RFB / P Open - Internationa Single Stage - One E rocurement of equipment for IDA / 65030 Public Health Assets Post Request for Bids 428,520.00 171,242.14 Signed 2021-02-15 2021-04-06 2021-02-20 2021-04-03 2021-05-04 2021-05-03 2021-05-18 2021-06-07 2021-07-13 2021-12-04 l nvelope Sentinel Sites ZM-MOH-139030-GO-RFQ / P rocurement of Laboratory Re Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 17,000.00 0.00 Canceled 2021-01-23 2021-03-20 2021-09-16 agents stock for entrice disea tions nvelope se surveillance sites ZM-MOH-176260-GO-RFQ / P rocurement of Influenza sam Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 31,518.00 0.00 Canceled 2021-04-10 2021-06-05 2021-12-02 ple collection supplies for sen tions nvelope tinel surveillance sites ZM-MOH-139032-GO-RFB / P Open - Internationa Single Stage - One E rocurement of Strategic Labo IDA / 65030 Public Health Assets Post Request for Bids 313,890.00 0.00 Canceled 2021-06-14 2021-04-06 2021-06-19 2021-07-31 2021-08-30 2021-10-04 2022-04-02 l nvelope ratory Reagents Stocks ZM-MOH-139005-GO-RFB / P Open - Internationa Single Stage - One E IDA / 65030 Public Health Assets Post Request for Bids 550,000.00 0.00 Canceled 2022-02-15 2022-02-20 2022-04-03 2022-05-03 2022-06-07 2022-12-04 rocurement of PHEOC Equip l nvelope ment ZM-MOH-186751-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Lab Reagents/ IDA / 65030 Public Health Assets Post Limited 2,250.00 0.00 Canceled 2021-05-22 2021-07-17 2022-01-13 tions nvelope consumables for Research Page 1 ZM-MOH-176266-GO-RFQ / P rocurement of Laboratory rea Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 34,496.00 0.00 Canceled 2021-05-22 2021-07-17 2022-01-13 gent stocks for enteric diseas tions nvelope e surveillance sites ZM-MOH-186753-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Bicycles for co IDA / 65030 Public Health Assets Post Limited 17,000.00 0.00 Canceled 2020-11-24 2021-01-19 2021-07-18 tions nvelope mmunity volunteers ZM-MOH-139021-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Equipment for IDA / 65030 Public Health Assets Post Limited 22,685.00 0.00 Canceled 2021-06-26 2021-08-21 2022-02-17 tions nvelope two (2) Sentinel Surveillance Sites ZM-MOH-176274-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Communicatio IDA / 65030 Public Health Assets Post Limited 7,950.00 0.00 Canceled 2021-01-16 2021-03-13 2021-09-09 tions nvelope n Equipment ZM-MOH-260183-GO-RFQ / P rocurement of Office Equipm Request for Quota Single Stage - One E Under Imple ent (11 Laptops, 2 Scanners, IDA / 65030 Project Management Post Limited 36,286.00 0.00 2021-11-20 2022-04-11 2022-01-15 2022-07-14 tions nvelope mentation 2 Shredders, 1 Industrial Cop ier and 4 (3 in 1 ) printers for PIU ZM-MOH-259349-GO-RFQ / P rinting of (500) Event Based Surveillance guidelines, (150 Request for Quota Single Stage - One E Under Imple IDA / 65030 Public Health Assets Post Limited 26,470.58 0.00 2022-03-26 2022-04-01 2022-05-21 2022-11-17 0) report books and (1500) r tions nvelope mentation egisters for 42 Districts to fac ilitate operationalisation of E BS concepts in Districts ZM-MOH-259353-GO-RFQ / P rocurement of (1500) Bags, ( 3000) Pens (1500) T. Shirts a Request for Quota Single Stage - One E Under Imple IDA / 65030 Public Health Assets Post Limited 77,558.82 0.00 2022-03-26 2022-04-01 2022-05-21 2022-11-17 nd (1500) Caps for Event Ba tions nvelope mentation sed Surveillance Volunteers/ Community based in 42 Distr icts. ZM-MOH-259355-GO-RFB / P rocurement of Equipment for ILI/SARI Surveillance ((1) App lied Biosystem 7500 Real Ti Single Stage - One E me PCR System, (1) Automat IDA / 65030 Public Health Assets Post Request for Bids Open - National 146,848.83 0.00 Canceled 2022-03-21 2022-03-26 2022-05-07 2022-06-06 2022-07-11 2023-01-07 nvelope ed nuclei acid extraction syst em, (1) 24 slot refrigerated E ppendorf microcentrifuge, (1) Reagents storage refrigerato r and (5) 3000 KVA UPS ZM-MOH-259356-GO-RFQ / P rocurement of reagents and Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 16,544.11 0.00 Canceled 2022-03-28 2022-05-23 2022-11-19 consumables for ILI/SARI Sur tions nvelope veillance for Virology Lab at UTH. ZM-MOH-259361-GO-RFQ / P rocurement of safety gear for onsite inspections (Helmets ( Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 6,679.00 0.00 Canceled 2022-03-19 2022-05-14 2022-11-10 50), Safety Boots (50), Work tions nvelope Suits (50), Ear Muffs (100), G oggles (50), N95 Masks (150) and Gloves (50)) ZM-MOH-259358-GO-RFQ / P rinting of Epidemic Prepared Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 16,176.47 0.00 Canceled 2022-09-17 2022-11-12 2023-05-11 ness and Response Guideline tions nvelope s and PHEOC SOPs. ZM-MOH-260140-GO-RFQ / P rocurement of office furnitur Request for Quota Single Stage - One E Pending Impl e (13 Office desks, (13) Offic IDA / 65030 Project Management Post Limited 18,571.00 0.00 2022-03-26 2022-05-21 2022-11-17 tions nvelope ementation e Chairs and 13 Filling cabine ts for PIU. See attached speci fications and Distribution list. ZM-MOH-259357-GO-RFQ / P rocurement of two (2 to 8 de grees) thermo scientific (TSX series high performance lab r Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 37,500.00 0.00 Canceled 2022-04-04 2022-05-30 2022-11-26 efrigerators, (4) freezer -80 U tions nvelope pright, (2) freezer-40 Upright , freezer installation, calibrati on, validation and commissio ning services. ZM-MOH-325228-GO-RFB / P rocurement of (400) Laptops, (400) Laptop Bags, (400) Mic Single Stage - One E Under Imple rosoft Office Installation Kit a IDA / 65040 Public Health Assets Post Request for Bids Open - National 858,750.00 0.00 2022-12-21 2022-11-08 2022-12-26 2023-02-06 2022-12-07 2023-03-08 2023-01-31 2023-04-12 2023-10-09 nvelope mentation nd (400) Anti- Virus for 116 D istricts and 284 Health Facilit ies to enhance digitization of Data Management ZM-MOH-325229-GO-RFB / P rocurement of ECHO Equipm ent (30) Television Sets, (30) Single Stage - One E Under Imple TV screen mounting kit, (30) IDA / 65030 Public Health Assets Post Request for Bids Open - National 117,188.00 0.00 2022-12-12 2022-11-08 2022-12-17 2023-01-28 2022-12-07 2023-02-27 2023-01-30 2023-04-03 2023-09-30 nvelope mentation USB Conference Camera, 30 I nternet routers, 30 HDMI Cab les and 30 Adaptors for Distri ct Health Offices ZM-MOH-325232-GO-RFQ / P Request for Quota Single Stage - One E Under Imple rocurement of Office Furnitur IDA / 65030 Project Management Post Limited 6,875.00 0.00 2022-12-25 2023-01-17 2023-02-19 2023-08-18 tions nvelope mentation e for the Project Implementat ion Unit ZM-MOH-325233-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl rocurement of AutoCAD 2022 IDA / 65030 Project Management Post Limited 6,248.00 0.00 2022-12-17 2023-02-11 2023-08-10 tions nvelope ementation Design Package ZM-MOH-325234-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Computer Wor IDA / 65030 Project Management Post Limited 5,918.00 0.00 Signed 2022-12-25 2023-03-01 2023-02-19 2023-08-18 tions nvelope kstation for Designing ZM-MOH-325235-GO-RFQ / P Request for Quota Single Stage - One E IDA / 65030 Project Management Post Limited 8,773.00 0.00 Signed 2022-12-24 2023-02-23 2023-02-18 2023-08-17 rocurement of Data Server tions nvelope Page 2 ZM-MOH-325231-GO-RFQ / P rocurement of Office Equipm ent for PIU (2) Projectors, (1) Request for Quota Single Stage - One E Under Imple IDA / 65030 Project Management Post Limited 50,656.00 0.00 2022-12-17 2022-11-19 2023-02-11 2023-08-10 A3 Printer (10) Laptops, (2) s tions nvelope mentation canner, (1) Fridges, (1) Electr ic Kettles, (1) Microwave, (2) 3 in 1 Printers ZM-MOH-345808-GO-RFQ / P rocurement of Laptops, Micro Human Resources Developm Request for Quota Single Stage - One E Under Imple soft Office, Antivirus and Rou IDA / 65040 Post Limited 18,735.00 0.00 2023-03-25 2023-03-01 2023-05-20 2023-11-16 ent tions nvelope mentation ters for the for Field Epidemi ology under the Work Force Development ZM-MOH-346154-GO-DIR / Pr ocurement of portable labs a Contingent Emergency Resp Pending Impl nd water testing kits and equ IDA / 65040 Post Direct Selection Direct - National 256,410.25 0.00 2023-03-28 2023-04-02 2023-05-07 2023-11-03 onse Component (CERC) ementation ipment (chlorometers, lovibo nd comparators and DPT tabl ets) ZM-MOH-346155-GO-DIR / Pr ocure of laboratory reagents Contingent Emergency Resp Under Imple IDA / 65040 Post Direct Selection Direct - National 128,205.12 0.00 2023-03-28 2023-04-06 2023-04-02 2023-05-07 2023-11-03 and consumables for cholera onse Component (CERC) mentation confirmation and genomic se quencing. ZM-MOH-346152-GO-DIR / Pr ocurement of liquid and gran Contingent Emergency Resp Pending Impl ular chlorine for water treatm IDA / 65040 Post Direct Selection Direct - National 292,307.69 0.00 2023-03-28 2023-04-02 2023-05-07 2023-11-03 onse Component (CERC) ementation ent at CTC and disinfection of latrines and HH - National ZM-MOH-358224-GO-RFB / P rocurement of laboratory rea Single Stage - One E Pending Impl gents and consumables to su IDA / 65040 Public Health Assets Post Request for Bids Open - National 111,628.00 0.00 2023-06-01 2023-06-06 2023-07-18 2023-08-17 2023-09-21 2024-03-19 nvelope ementation pport surveillance and detect ion of priority public health p athogens ZM-MOH-358228-GO-RFQ / P rocurement of Office tables a Request for Quota Single Stage - One E Pending Impl IDA / 65040 Public Health Assets Post Limited 16,744.18 0.00 2023-07-01 2023-08-26 2024-02-22 nd chairs for the operationali tions nvelope ementation zation of the National and 2 s ub national PHEOCs ZM-MOH-358309-GO-RFQ / P rocurement of fire system (fir e alarm, fire extinguisher and Request for Quota Single Stage - One E Pending Impl IDA / 65040 Public Health Assets Post Limited 4,186.04 0.00 2023-07-05 2023-08-30 2024-02-26 smoke detectors) for the ope tions nvelope ementation rationalization of the Nationa l and 2 National sub PHEOCs ZM-MOH-358313-GO-RFQ / P rocurement of security syste Request for Quota Single Stage - One E Pending Impl m (CCTV and Biometric syste IDA / 65040 Public Health Assets Post Limited 5,581.39 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation m) for the operationalization of the National and 2 Nationa l sub PHEOCs ZM-MOH-358325-GO-RFQ / P rocurement of assorted IT Eq Request for Quota Single Stage - One E Pending Impl IDA / 65040 Public Health Assets Post Limited 39,581.39 0.00 2023-07-05 2023-08-30 2024-02-26 uipment for the operationaliz tions nvelope ementation ation of the National and 2 N ational sub PHEOCs ZM-MOH-358327-GO-RFQ / P rocurement of 85’’Television Request for Quota Single Stage - One E Pending Impl sets and TV Screen for the op IDA / 65040 Public Health Assets Post Limited 9,302.32 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation erationalization of the Nation al and 2 National sub PHEOC s. ZM-MOH-358329-GO-RFB / P rocurement of Equipment for BSL 2 Laboratories at Kasam Single Stage - One E Pending Impl a, Mongu, choma, Chpata Vet IDA / 65040 Public Health Assets Post Request for Bids Open - National 1,106,064.66 0.00 2023-07-31 2023-08-05 2023-09-16 2023-10-16 2023-11-20 2024-05-18 nvelope ementation erinary lab, Livingstone, Chin sali, Mansa, Lewanika, Chipat a General Hospitals CVRL, ZN PHIRL ZM-MOH-358331-GO-DIR / Pr ocurement of (3) 13-seater h ardtop land cruiser to suppor t sample referral and respons Direct - Internation Pending Impl e for strengthening of diseas IDA / 65040 Public Health Assets Post Direct Selection 209,472.53 0.00 2023-06-30 2023-07-05 2023-08-09 2024-02-05 al ementation e prevention and control cap abilities for Zambia, and (1) Utility Motor Vehicle establis hment of an ICT center (inclu ding hardware and sof ZM-MOH-358332-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl rocurement of ECHO Equipm IDA / 65040 Public Health Assets Post Limited 87,209.30 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation ent for District Health Offices ZM-MOH-358335-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl rocurement of Data Server B IDA / 65040 Public Health Assets Post Limited 25,814.00 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation ackup for ERP and establish ment of ICT Centre ZM-MOH-358336-GO-RFQ / U Request for Quota Single Stage - One E Pending Impl pgrading of the existing ZNP IDA / 65040 Public Health Assets Post Limited 3,414.63 0.00 2023-07-05 2023-08-30 2024-02-26 tions nvelope ementation HI Data Server ZM-MOH-358344-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl rocurement of 48U Server Ra IDA / 65040 Public Health Assets Post Limited 5,581.40 0.00 2023-06-25 2023-08-20 2024-02-16 tions nvelope ementation ck Rack with Console ZM-MOH-362045-GO-RFQ / P Request for Quota Single Stage - One E Pending Impl rocurement of Personal Prote IDA / 65040 Project Management Post Limited 3,372.09 0.00 2023-07-01 2023-08-26 2024-02-22 tions nvelope ementation ctive clothing for ACDCP PIU NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZM-MOH-139082-NC-RFQ / P Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 12,215.00 0.00 Canceled 2021-07-11 2021-09-05 2022-03-04 rinting of One Health Guidlin tions nvelope es Page 3 ZM-MOH-176271-NC-RFQ / P Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 2,172.00 0.00 Canceled 2021-05-08 2021-07-03 2021-12-30 rinting of Legal Frameworks tions nvelope ZM-MOH-139027-NC-RFQ / P Request for Quota Single Stage - One E rinting of Epidemic Prepared IDA / 65030 Public Health Assets Post Limited 5,000.00 0.00 Canceled 2021-06-27 2021-08-22 2022-02-18 tions nvelope ness and Response Guidlines ZM-MOH-139018-NC-RFQ / P Request for Quota Single Stage - One E rinting of point of entry guide IDA / 65030 Public Health Assets Post Limited 5,000.00 0.00 Canceled 2022-08-13 2022-10-08 2023-04-06 tions nvelope lines and SOPs ZM-MOH-139034-NC-RFQ / P rinting of QMS materials, Lab Request for Quota Single Stage - One E IDA / 65030 Public Health Assets Post Limited 54,125.00 0.00 Canceled 2022-09-10 2022-11-05 2023-05-04 oratory Quality Manuals, Job tions nvelope Aids, SOPs and Laboratory H andbooks ZM-MOH-260137-NC-RFQ / P Request for Quota Single Stage - One E rocurement of services for fu IDA / 65030 Project Management Post Limited 1,105.00 0.00 Canceled 2022-03-26 2022-05-21 2022-11-17 tions nvelope nctional Vehicle Management System ZM-MOH-325241-NC-RFQ / P Request for Quota Single Stage - One E Under Imple rocurement of Functional Pay IDA / 65030 Project Management Post Limited 5,872.00 0.00 2022-12-17 2022-11-09 2023-02-11 2023-08-10 tions nvelope mentation roll System for the ACDCP Pr oject ZM-MOH-325244-NC-RFQ / P rocurement of Microsoft Dyn Request for Quota Single Stage - One E Pending Impl IDA / 65030 Project Management Post Limited 43,328.00 0.00 2022-12-10 2023-02-04 2023-08-03 amics 365 (IFMIS and Navisio tions nvelope ementation n) for ACDCP and Covid-19 Pr oject CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZM-MOH-139108-CS-QCBS / Design and Supervision and Management Consultant for t Quality And Cost- Open - Internationa IDA / 65030 Public Health Assets Prior 3,800,000.00 0.00 Canceled 2020-12-01 2020-12-22 2021-02-04 2021-03-04 2021-04-03 2021-05-08 2021-06-12 2022-06-12 he Construction of the four st Based Selection l orey BSL 3 Laboratory, Office Complex and ancillary buildin gs, and parking for ZNPHI/RC C. ZM-MOH-139349-CS-CQS / C Governance, Advocacy, and Consultant Qualifi onsultancy services for the D IDA / 65040 Post Open - National 100,000.00 0.00 Canceled 2021-05-03 2021-05-24 2021-07-07 2021-08-06 2021-09-10 2022-03-09 Operational Frameworks cation Selection evelopment of a Legal Frame work ZM-MOH-259373-CS-CQS / C onsultancy Services for the D Consultant Qualifi IDA / 65030 Public Health Assets Post Limited 74,433.33 0.00 Canceled 2021-11-08 2022-03-04 2021-11-22 2021-12-22 2022-01-26 2022-07-25 evelopment of Surveillance S cation Selection ystem DHIS2 Tracker ZM-MOH-139350-CS-CQS / P Consultant Qualifi rovision of consultancy servic IDA / 65040 Project Management Post Open - National 9,387.00 0.00 Canceled 2021-06-07 2021-06-28 2021-08-11 2021-09-10 2021-10-15 2022-04-13 cation Selection es for the Development of M &E Tools ZM-MOH-318996-CS-QCBS / Consultancy Services for Proj ect Management for the desi Quality And Cost- Open - Internationa Under Implement gn and Supervision of the Co IDA / 65030 Public Health Assets Post 491,429.00 0.00 2022-11-14 2022-10-06 2022-12-05 2023-01-18 2023-02-15 2023-03-17 2023-04-21 2023-05-26 2024-05-25 Based Selection l ation nstruction of a Building Com plex Including Offices, BSL-3 Laboratory and Ancillary Buil dings for ZNPHI/RCC. ZM-MOH-318959-CS-QCBS / Provision of Consultancy Serv Quality And Cost- Open - Internationa Under Implement ices for the Design, Construct IDA / 65030 Public Health Assets Prior 778,095.24 0.00 2022-11-14 2022-12-05 2023-01-18 2023-02-15 2023-03-17 2023-04-21 2023-05-26 2024-05-25 Based Selection l ation ion Supervision and Equippin g of the ZNPHI Building Com plex ZM-MOH-259551-CS-CQS / P Consultant Qualifi rovision of Consultancy Servi IDA / 65030 Project Management Post Limited 14,622.00 0.00 Canceled 2021-11-08 2022-11-18 2021-11-22 2021-12-22 2022-01-26 2022-07-25 cation Selection ces for the Development of M &E Systems ZM-MOH-369387-CS-CQS / P rovision of Consultancy servi Consultant Qualifi Pending Impleme IDA / 65040 Project Management Post Limited 23,255.81 0.00 2023-07-24 2023-08-07 2023-09-06 2023-10-11 2024-04-08 ces for the Development of M cation Selection ntation onitoring and Evaluation Syst em INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZM-MOH-161147-CS-INDV / Recruitment of a Project Coor Individual Consult IDA / 65040 Project Management Post Open 60,000.00 116,980.27 Signed 2020-04-13 2020-08-07 2020-06-01 2020-12-10 2020-06-22 2021-03-15 2020-07-27 2021-03-23 2021-01-23 dinator for the Africa Centre f ant Selection or Disease Control Project ZM-MOH-186783-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult IDA / 65030 Prior Direct 149,860.89 0.00 Canceled 2020-08-17 2020-12-17 2020-08-27 2020-09-17 2020-10-22 2021-04-20 Head-Workforce Developmen ent ant Selection t for Leadership and Technic al Expertise ZM-MOH-186769-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult IDA / 65030 Prior Direct 149,860.89 197,247.71 Signed 2020-08-17 2020-12-24 2020-08-27 2021-02-02 2020-09-17 2021-02-28 2020-10-22 2021-03-02 2021-04-20 Head-Laboratory Systems an ent ant Selection d Network Leadership and Te chnical Expertise ZM-MOH-186793-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult Head- Epidemic Preparednes IDA / 65030 Prior Direct 149,860.89 197,247.71 Signed 2020-08-17 2020-12-24 2020-08-27 2021-02-02 2020-09-17 2021-02-28 2020-10-22 2021-03-02 2021-04-20 ent ant Selection s and Response Leadership a nd Technical Expertise ZM-MOH-186779-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult IDA / 65030 Prior Direct 149,860.89 0.00 Under Review 2020-08-17 2020-12-17 2020-08-27 2020-09-17 2020-10-22 2021-04-20 Head- Information Systems f ent ant Selection or Leadership and Technical Expertise Page 4 ZM-MOH-186762-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult IDA / 65030 Prior Direct 248,032.89 315,596.33 Signed 2020-09-28 2020-12-24 2020-10-08 2021-02-02 2020-10-29 2021-02-28 2020-12-03 2021-03-02 2021-06-01 Leadership and Technical Ex ent ant Selection pertise (Director ZNPHI) ZM-MOH-139344-CS-INDV / Consultancy services for the Individual Consult Design Validation consultant IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-01 2021-01-19 2021-02-09 2021-03-16 2021-09-12 ant Selection (Quality Assurance) Refrigera tion and Air conditioning Engi neer ZM-MOH-186775-CS-CDS / R ecruitment and Retention of Human Resources Developm Individual Consult Head-Surveillance and Disea IDA / 65030 Prior Direct 149,860.89 197,247.71 Signed 2020-08-17 2020-12-17 2020-08-27 2021-02-02 2020-09-17 2021-02-28 2020-10-22 2021-03-02 2021-04-20 ent ant Selection se Intelligence for Leadership and Technical Expertise ZM-MOH-139352-CS-CQS / C Individual Consult onsultancy services for the D IDA / 65040 Project Management Post Limited 7,929.00 0.00 Canceled 2021-04-13 2021-04-18 2021-05-09 2021-06-13 2021-12-10 ant Selection evelopment of Baseline Surv ey Tools ZM-MOH-186795-CS-CDS / R ecruitment and retention of Human Resources Developm Individual Consult IDA / 65030 Post Direct 149,860.89 0.00 Canceled 2021-08-09 2021-08-19 2021-09-09 2021-10-14 2022-04-12 Head Public Health Research ent ant Selection Leadership and Technical Ex pert. ZM-MOH-139346-CS-INDV / Consultancy services for the Individual Consult IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-03-14 2021-02-08 2021-03-01 2021-04-05 2021-10-02 Design Validation consultant ant Selection (Quality Assurance) Electro M echanical Engineer. ZM-MOH-139340-CS-INDV / Consultancy services for the Individual Consult Design Validation consultant IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 ant Selection (Quality Assurance) Laborato ry and Medical Equipment Sp ecialist ZM-MOH-139303-CS-INDV / Consultancy services for the Individual Consult Design Validation consultant IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 ant Selection (Quality Assurance) Environ mental Safeguards Specialist . ZM-MOH-139320-CS-INDV / Consultancy services for the Individual Consult IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 Design Validation consultant ant Selection (Quality Assurance) Civil/Stru ctural Engineer ZM-MOH-139338-CS-INDV / Consultancy services for the Individual Consult IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-02-08 2021-03-01 2021-04-05 2021-10-02 Design Validation consultant ant Selection (Quality Assurance) Social Sa feguards Specialist. ZM-MOH-139341-CS-INDV / Consultancy services for the Individual Consult IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-03-14 2021-02-08 2021-03-01 2021-04-05 2021-10-02 Design Validation consultant ant Selection (Quality Assurance) Architect ZM-MOH-139114-CS-INDV / Consultancy Services for the Individual Consult IDA / 65030 Public Health Assets Prior Open 300,000.00 0.00 Canceled 2020-12-21 2021-03-14 2021-02-08 2021-03-01 2021-04-05 2021-10-02 Design Validation Consultant ant Selection (Quality Assurance) Infectiou s Disease Specialist. ZM-MOH-202428-CS-CDS / R Individual Consult ecruitment of an Infectious D IDA / 65030 Project Management Prior Direct 126,954.09 133,370.48 Signed 2020-11-23 2021-04-06 2020-12-03 2021-09-17 2020-12-24 2021-10-14 2021-01-28 2021-10-02 2021-07-27 ant Selection isease Specialist ZM-MOH-202432-CS-CDS / R Individual Consult ecruitment of a Monitoring a IDA / 65030 Project Management Prior Direct 71,265.60 142,568.81 Signed 2020-11-23 2021-01-25 2020-12-03 2021-02-26 2020-12-24 2021-02-28 2021-01-28 2021-03-02 2021-07-27 ant Selection nd Evaluation Officer ZM-MOH-202434-CS-CDS / R Individual Consult IDA / 65030 Project Management Prior Direct 71,265.60 108,154.51 Signed 2020-11-23 2020-12-16 2020-12-03 2021-02-02 2020-12-24 2021-02-28 2021-01-28 2021-03-02 2021-07-27 ecruitment of a Procurement ant Selection Officer ZM-MOH-202436-CS-CDS / R Individual Consult IDA / 65030 Project Management Prior Direct 71,265.60 114,963.50 Signed 2020-11-23 2021-01-25 2020-12-03 2021-02-26 2020-12-24 2021-02-28 2021-01-28 2021-03-02 2021-07-27 ecruitment of an Accountant ant Selection ZM-MOH-202430-CS-CDS / R Individual Consult IDA / 65030 Project Management Prior Direct 126,954.09 0.00 Canceled 2020-11-23 2021-03-26 2020-12-03 2020-12-24 2021-01-28 2021-07-27 ecruitment of a Public Health ant Selection Specialist ZM-MOH-202433-CS-CDS / R Individual Consult IDA / 65030 Project Management Prior Direct 71,265.60 105,971.41 Signed 2020-11-23 2021-01-25 2020-12-03 2021-02-26 2020-12-24 2021-02-28 2021-01-28 2021-03-02 2021-07-27 ecruitment of an Internal Aud ant Selection itor ZM-MOH-218315-CS-CDS / R Individual Consult ecruitment of an Environmen IDA / 65030 Project Management Post Open 126,954.09 0.00 Canceled 2021-02-28 2021-02-11 2021-04-18 2021-05-09 2021-06-13 2021-12-10 ant Selection t and Social Safeguards Spec ialist ZM-MOH-220876-CS-INDV / Individual Consult RECRUITMENT OF A SOCIAL S IDA / 65030 Project Management Prior Direct 126,954.09 0.00 Canceled 2021-03-08 2021-06-01 2021-03-18 2021-04-08 2021-05-13 2021-11-09 ant Selection AFEGUARDS SPECIALIST ZM-MOH-218308-CS-CQS / R Individual Consult Under Implement ecruitment of a Civil Enginee IDA / 65030 Project Management Post Open 126,954.09 0.00 2021-03-31 2021-07-22 2021-05-19 2021-06-09 2021-07-14 2022-01-10 ant Selection ation r for ACDCP ZM-MOH-218314-CS-CDS / R Individual Consult ecruitment of Human Resour IDA / 65030 Project Management Post Direct 71,265.60 0.00 Canceled 2021-03-31 2021-04-10 2021-05-01 2021-06-05 2021-12-02 ant Selection ce and Administration officer ZM-MOH-218305-CS-CDS / R Human Resources Developm Individual Consult IDA / 65030 Post Direct 126,954.09 0.00 Canceled 2021-03-31 2021-09-17 2021-04-10 2021-05-01 2021-06-05 2021-12-02 ecruitment of a Laboratory S ent ant Selection pecialist ZM-MOH-218307-CS-CQS / R Individual Consult IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-03-31 2021-05-24 2021-05-19 2022-11-08 2021-06-09 2022-11-08 2021-07-14 2022-01-10 ecruitment of an Architect ant Selection ZM-MOH-218306-CS-CDS / R Human Resources Developm Individual Consult IDA / 65030 Prior Direct 126,954.09 145,620.44 Signed 2021-03-31 2021-04-16 2021-04-10 2021-09-17 2021-05-01 2021-09-20 2021-06-05 2021-11-20 2021-12-02 ecruitment of One Health Sp ent ant Selection ecialist Page 5 ZM-MOH-218310-CS-CQS / R Individual Consult ecruitment of a Financial Ma IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-03-31 2021-05-24 2021-05-19 2022-05-08 2021-06-09 2022-05-16 2021-07-14 2022-01-10 ant Selection nagement Specialist ZM-MOH-218312-CS-CQS / R Individual Consult IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-03-31 2021-05-24 2021-05-19 2022-01-04 2021-06-09 2022-06-15 2021-07-14 2022-01-10 ecruitment of a Procurement ant Selection Specialist ZM-MOH-236033-CS-INDV / Individual Consult Recruitment of an Internal Au IDA / 65030 Project Management Post Open 126,954.09 0.00 Canceled 2021-06-07 2021-05-28 2021-07-26 2021-08-16 2021-09-20 2022-03-19 ant Selection ditor (Specialist) ZM-MOH-241182-CS-INDV / Individual Consult Recruitment of an Environm IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-06-30 2021-08-27 2021-08-18 2022-11-09 2021-09-08 2022-11-09 2021-10-13 2022-04-11 ant Selection ental Safeguards Specialist ZM-MOH-241184-CS-INDV / Individual Consult IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-06-30 2021-08-27 2021-08-18 2022-08-29 2021-09-08 2022-11-07 2021-10-13 2022-04-11 Recruitment of an Internal Au ant Selection ditor ZM-MOH-253276-CS-INDV / Recruitment of a Procuremen t Specialist on exceptional ba sis to help build capacity for Human Resources Developm Individual Consult IDA / 65030 Post Direct 126,954.09 0.00 Canceled 2021-09-27 2021-09-13 2021-10-07 2021-10-07 2021-10-28 2021-10-07 2021-12-02 2022-05-31 ZNPHI. The officer will be sec ent ant Selection onded from the Public Servic e Management Division(PSM D) and this will be done on Di rect Selection basis. ZM-MOH-250665-CS-INDV / Recruitment of a Public Healt Individual Consult IDA / 65030 Project Management Post Direct 126,954.09 145,620.44 Signed 2021-09-20 2021-09-13 2021-09-30 2021-09-17 2021-10-21 2021-09-17 2021-11-25 2021-11-20 2022-05-24 h Specialist- Integrated Disea ant Selection se Surveillance Response (PH S-IDSR) ZM-MOH-253752-CS-INDV / Recruitment of an IT Speciali Individual Consult IDA / 65030 Project Management Post Open 126,954.09 0.00 Signed 2021-09-27 2021-09-21 2021-11-15 2022-08-29 2021-12-06 2022-10-27 2022-01-10 2022-07-09 st (Digital Solutions). The con ant Selection sultant will be recruited throu gh the Open Market. ZM-MOH-253280-CS-INDV / Recruitment of a Financial M anagement Specialist on exc Human Resources Developm Individual Consult eptional basis to help build c IDA / 65030 Post Direct 126,954.90 0.00 Canceled 2021-09-27 2021-09-13 2021-10-07 2021-10-28 2021-12-02 2022-05-31 ent ant Selection apacity for ZNPHI. The Office r will be seconded from office of the Accountant General an d will be done on Direct Sele ction basis. ZM-MOH-253281-CS-INDV / Recruitment of a Senior Inter nal Auditor on exceptional ba Human Resources Developm Individual Consult sis to help build capacity for IDA / 65030 Post Direct 126,954.09 0.00 Canceled 2021-09-27 2021-09-13 2021-10-07 2021-10-21 2021-10-28 2021-12-02 2022-05-31 ent ant Selection ZNPHI. The officer will be sec onded from Office of the Con troller of Internal Audit. This will be done on Direct Selecti on basis ZM-MOH-282216-CS-INDV / Individual Consult Consultancy services for enh IDA / 65030 Public Health Assets Post Limited 4,365.43 0.00 Canceled 2022-03-21 2022-03-26 2022-04-16 2022-05-21 2022-11-17 ant Selection ancement of ZNPHI Website ZM-MOH-282436-CS-INDV / Consultancy services to Cond Human Resources Developm Individual Consult Under Implement uct Institution Assessment an IDA / 65030 Post Limited 25,000.00 0.00 2022-03-21 2022-11-07 2022-03-26 2022-04-16 2022-05-21 2022-11-17 ent ant Selection ation d preparation of a comprehe nsive Human resources need s Assessment ZM-MOH-327703-CS-INDV / Individual Consult IDA / 65030 Project Management Post Open - National 126,954.09 0.00 Signed 2022-12-20 2022-11-22 2023-02-07 2022-08-29 2023-02-28 2022-10-27 2023-04-04 2023-10-01 Recruitment of a Laboratory ant Selection Specialist ZM-MOH-327704-CS-INDV / Individual Consult Recruitment of a Social Safeg IDA / 65030 Project Management Post Open - National 126,954.09 0.00 Completed 2022-12-20 2022-11-22 2023-02-07 2022-09-20 2023-02-28 2022-11-02 2023-04-04 2023-10-01 2022-11-11 ant Selection uards Specialist ZM-MOH-362043-CS-INDV / Recruitment of a Monitoring Individual Consult Pending Impleme IDA / 65040 Project Management Post Open - National 116,263.40 0.00 2023-06-26 2023-08-14 2023-09-04 2023-10-09 2024-04-06 and Evaluation Specialist for ant Selection ntation the ACDCP Project Implemen tation Unit. Page 6 Republic of Malawi EGENCO LTD 18 MONTHS PROCUREMENT PLAN- MALAWI EMERGENCY POWER RESTORATION PROJECT I. General 1.Project information Country: Malawi Project Name: Malawi Emergency Power Restoration Project (MEPRP) Project ID: P178914 2.Project Implementation Agency: EGENCO Limited 3.Date of the Procurement Plan: May 17, 2022 4.Period covered by this Procurement Plan: May 2022 to October 2023 II. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (November 2020) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. III. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. IV. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Public Procurement and Disposal of Public Assets Act, 2017 of the Republic of Malawi, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations as follows:  Provision of “set-asides” contracts for small enterprises shall not be applied.  Criteria such as environmental aspect, extent of local content, technology transfer, and managerial, scientific & operational skills development shall not be used in the evaluation of bids unless specifically agreed by the Bank on case to case basis.  Procurement Documents include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and practices. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. In accordance with paragraph 5.3 of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. The form of the Letter of Acceptance is attached in Appendix 1. V. Prequalification. Not expected for the works/goods packages in the procurement plan. VI. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable VII. Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. VIII. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). (a) Goods: Not Applicable for those contracts identified in the Procurement Plan tables. (b) Works: Not Applicable for those contracts identified in the Procurement Plan tables. IX. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: If requested by the Recipient, the World Bank will provide procurement hands-on expanded implementation support (HEIS) to help expedite preparation of bidding documents. X. Other Relevant Procurement Information: - (a) Proposed Procedures for CDD Components: Not Applicable (b) Reference to (if any) Project Operational/Procurement Manual: EGENCO and ESCOM will prepare a Procurement Manual which will be part of the Project Implementation Manual (PIM) to elaborate procurement arrangements under the proposed Project. The Procurement Plan will also form part of the PIM. XI. Any Other Special Procurement Arrangements: Being emergency project, simple and fast procurement and selection processes fit for purpose in an emergency will be used including the following streamlined procurement arrangements: (i) increased thresholds for Requests for Quotations (RFQ) to US$1 million for goods and services and US$5 million for works; (ii) direct contracting of firms as appropriate; (iii) Limited Competition with identified manufacturers and suppliers for other items; (iv) Use of procurement agents; (v) Force account, as needed; (vi) Bid Securing Declaration may be used instead of the bid security; (vii) Advance payment may be increased to 40 percent, while secured with the advance payment guarantee; (viii) The time for submission of bids/proposal can be shortened to seven - 15 days in competitive national and international procedures, and to three days for the Request for Quotations, however if bidders request an extension, it should be granted, and (ix) The retroactive financing may be applied to the contracts procured in advance for the purpose of this Project objective using procurement procedures consistent with Sections I, II and III of the World Bank’s Procurement Regulations and consistent with the Financing Agreement of this Project. XII. Procurement Approach and Prior Review Thresholds: Based on the overall procurement risk rating of “Substantial”, the thresholds for the Bank’s prior review and procurement method threshold are provided in the table below: Prior-review Thresholds for Procurement Methods Thresholds Procureme Substanti Works Goods, IT & Non-Consulting Shortlist of National nt al Services Consultants Type Risk ($`000) Works 10,000 Open Request Request Internatio for for Engineerin Open Open nal or Quotatio Open Quotatio Consultin g& Nation Nation ICB n or Internatio n or g Constructi al or al or ($'000 National nal or ICB National Services on NCB NCB Shoppin ($'000) Shoppin ($'000) Supervisio ($'000) ($'000) g g n ($'000) ($'000) ($'000) Goods, IT 2,000 & Non- Consulting ≧ < ≦ ≧ < ≦ < ≦ Services Consultant 1,000 s (Firms) Individual 300 7,000 7,000 200 1,000 1,000 100 200 300 Consultant s Note Given that the project will finance a combination of goods, services, and works for emergency response as per OP 8.00, there is normally no prior review, and there will be no Standstill Period, provided that utilities will informally share documentation for quality assurance purposes before contractual commitments. XIII. Procurement Packages/Plan with Procurement Arrangements and Time Schedule: as per the table below: PROCUREMENT PLAN A. Works 1 2 3 4 5 6 7 8 9 10 Ref Contract Estimated Market Selectio Prequa Domesti Review Expecte Expecte . Description Cost Approa n lificatio c by d bid d No. US$ ch Method n Prefere Bank opening Contrac (yes/no nce (Prior / date t ) (yes/no) Post) Signatu re Date 1 Reconstruction of 193,000.00 Limited RFQ No No Post 01-Jul-22 30-Jul-22 Chilala Bridge 2 Extension of 500,000.00 Limited RFQ No No Post 01-Jul- 30-Jul-22 Stoplog guides /22 and repair of slabs 3 Maintenance of 400,000.00 Limited RFQ No No Post 01-Aug- 31-Aug- Spillway ( Supply 22 22 of wire ropes for 5 Gates) 4 Desilting of River 1,100,000.0 Limited RFB No No Post 01-Jul-22 30-Jul-2 Left Bank Channel 0 5 Rehabilitation or 28,876,769. Limited RFB Yes No Prior 01-Apr- 01-Aug- upgrade of the 00 23 23 Dam Supply, delivery 600,000.00 Limited RFQ No No Post 01-Oct- 31-Oct- 6 and installation of 22 22 Cooling Water System B. Goods and Non-Consulting Services 1 2 3 4 5 6 7 8 9 10 Ref. Contract Estimated Market Selecti Prequ Domesti Revie Expecte Expecte No. Description Cost Approach on alifica c w d bid d US$ Method tion Prefere by opening Contrac (yes/n nce Bank date t o) (yes/no) (Prior Signatu / Post) re Date 1. Motor Vehicles (4 240,000.00 Limited RFQ No No Post 20-May- 31-May- x 4 D/Cab ) 22 22 2. Office Furniture & 25,000.00 Limited RFQ No No Post 20-May- 31-May- Equipment 22 22 C. Consultancy Services 1 2 3 4 5 6 7 8 9 Ref. Contract Estimate Market Selecti Shortlisti Revie Expected Expected No. Description d Approa on ng w proposal Contract Cost ch Method (Yes/No) by opening Signature US$ Bank date Date (Prior / Post) 1. ESIA for Dam Rehabilitation 1,200,000 Limited CQS No Post 01-Aug-22 30-Aug-22 Assessment and Prep of .00 Safeguard Studies and Plans 2. Engineering Consultancy 4,200,000 Limited CQS No Post 30-Jun-22 15-Jul-22 Services OE Phase 2 for the .00 Assessment of the Rehabilitation or Upgrade for the dam Dam Expert – dam safety 240,000.0 Direct DIR No Post 01-Aug-22 30-Aug-22 3. panel 0 Geotechnical Expert – dam 240,000.0 Direct DIR No Post 01-Aug-22 30-Aug-22 4. safety panel 0 5. Hydro-mechanical Expert – 120,000.0 Direct DIR No Post 01-Aug-22 30-Aug-22 dam safety panel 0 6. Hydrological Expert – dam 240,000.0 Direct DIR No Post 01-Aug-22 30-Aug-22 safety panel 0 7. Environmental Engineer on 50,000.00 Direct DIR No Post 01-Aug-22 30-Aug-22 Panel of Experts 7. Social Expert on Panel of 50,000.00 Direct DIR No Post 01-Aug-22 30-Aug-22 Expert 8. Hiring of Environmental. 168,000.0 Limited INDV Yes Post 27-May- 01=Jun-22 Safeguard Specialist for the 0 22 PIU 9. Hiring of Procurement 168,000.0 Limited INDV Yes Post 27-May- 01-Jun-22 Specialist for the PIU 0 22 10. Hiring of Social Specialist 168,000.0 Limited INDV Yes Post 27-May- 01-Jun22 for the PIU 0 22 11 Hiring of a Dam Engineer 40,000.0 Limited INDV Yes Post 20-Jun22 01-Jul22 for the PIU. (To review 0 design and construction supervision of cofferdam done by SVTP consultant during Phase I) RFB – Request for Quotations; RFB – Request form Bids; CQS- Consultant’s Based Qualifications; INDV - Individual Consultant Selection and DIR– Direct Selection. Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-Corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds 1Guidelines on Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Malawi : Emergency Power Restoration Project PLAN General Information Country: Malawi 2022-09-26 Bank’s Approval Date of the Original Procurement Plan: 2023-05-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178914 GPN Date: Project Name: Emergency Power Restoration Project Loan / Credit No: IDA / E0970 Electricity Generation Company Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned EGC012/WBP178914/W/RFB/ Request for Quota Component 1: Kapichira Da FY2022-23 / Reconstruction Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-03-2 IDA / E0970 m Rehabilitation and Strengt Post Limited 300,000.00 0.00 2022-09-25 2022-09-29 Works for the Tempory Chilal tions nvelope s (Emergency) SP lementation 8 hening a bridge on Access Road T14 D -Competitive 6 Request for Quota EGC049/W/FY2022-23 / Exte Component 1: Kapichira Da Request for Quota Single Stage - One E tions - Small Work 2023-04-2 nsion of the Stoplog Guides f IDA / E0970 m Rehabilitation and Strengt Post Limited 500,000.00 0.00 Canceled 2022-08-11 2022-10-24 tions nvelope s (Emergency) SP 2 or Spillway hening D -Competitive Request for Quota EGC035/WB/W/RFB/FY2022- Component 1: Kapichira Da Request for Quota Single Stage - One E tions - Small Work Pending Imp 2023-06-1 23 / Construction Works to R IDA / E0970 m Rehabilitation and Strengt Post Limited 1,000,000.00 0.00 2022-10-19 2022-12-14 tions nvelope s (Emergency) SP lementation 2 einforce Embankment Dam i hening D -Competitive n Phase I MW-EGENCO-324258-CW-RF Request for Bids - Component 1: Kapichira Da B / Reconstruction Works for Single Stage - One E Small Works SPD Pending Imp 2024-04-1 IDA / E0970 m Rehabilitation and Strengt Post Request for Bids Limited 1,000,000.00 0.00 2023-06-27 2023-07-02 2023-08-13 2023-09-12 2023-10-17 the Permanent Chilala Bridge nvelope (1 envelope proce lementation 4 hening on Access Road T146 ss) MW-EGENCO-314183-CW-RF Request for Bids - Component 1: Kapichira Da B / Rehabilitation Works for t Single Stage - One E Works (without pr 29,000,000.0 Pending Imp 2024-03-2 IDA / E0970 m Rehabilitation and Strengt Prior Request for Bids Limited 0.00 2023-06-11 2023-06-16 2023-07-28 2023-08-27 2023-10-01 he Spillway, Embankment Da nvelope equalification) SP 0 lementation 9 hening m, and Dam Instrumentation D Equipment MW-EGENCO-314838-CW-RF Request for Quota Component 1: Kapichira Da Q / Supply, Delivery, Installat Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-03-2 IDA / E0970 m Rehabilitation and Strengt Post Limited 730,000.00 0.00 2023-08-06 2023-10-01 ion and Commissioning of Up tions nvelope s (Emergency) SP lementation 9 hening graded Cooling System D -Competitive Request for Quota MW-EGENCO-366933-CW-RF Component 1: Kapichira Da Request for Quota Single Stage - One E tions - Small Work Pending Imp 2024-04-0 Q / Extension of the Stoplog IDA / E0970 m Rehabilitation and Strengt Post Limited 500,000.00 0.00 2023-08-12 2023-10-07 tions nvelope s (Emergency) SP lementation 4 Guides for Spillway hening D -Competitive GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual EGC/158/SS/G/FY20-23 / Sup Component 1: Kapichira Da ply and Delivery of lifting wir Request for Quota Single Stage - One E Pending Impl IDA / E0970 m Rehabilitation and Strengt Post Limited 400,000.00 0.00 2022-07-05 2022-07-16 2023-01-12 e ropes for 5 spillway gate fo tions nvelope ementation hening r the Immediate Maintenance of Spillway EGC05/WBP178914/G/RFQ/F Component 1: Kapichira Da Y2022-23 / Procurement of 3 Request for Quota Single Stage - One E Under Imple IDA / E0970 m Rehabilitation and Strengt Post Limited 240,000.00 0.00 2022-06-22 2022-06-22 2022-08-18 2023-02-14 (No.). x Motor vehicles (2.5lit tions nvelope mentation hening res, 4x4 Twin Cab with Cano py) for PIU EGC04/WBP178914/G/RFQ/F Y2022-23 / Procurement of of Component 1: Kapichira Da Request for Quota Single Stage - One E fice furniture and equipment: IDA / E0970 m Rehabilitation and Strengt Post Limited 25,000.00 0.00 Canceled 2022-06-23 2022-06-22 2022-08-09 2023-02-05 tions nvelope 7 (No.) x laptops, 7 (No.) Des hening ks and chairs, 3 (No.) x Fridg es) MW-EGENCO-324081-GO-RF Component 1: Kapichira Da Request for Quota Single Stage - One E Pending Impl Q / Procurement of Mobile ph IDA / E0970 m Rehabilitation and Strengt Post Limited 40,000.00 0.00 2022-11-20 2023-01-15 2023-07-14 tions nvelope ementation one Handsets and airtime. 7 hening (seven) EGC32/WBP/RFQ/2022-23 / S upply of Gabion baskets and Component 1: Kapichira Da Request for Quota Single Stage - One E Under Imple Geotextiles for Reconstructio IDA / E0970 m Rehabilitation and Strengt Post Limited 143,000.00 0.00 2022-09-30 2022-09-29 2022-10-07 2022-10-21 tions nvelope mentation n Works for the Temporary C hening hilala bridge on Access Road T146 EGC02/WBP178914/G/RFQ/F Component 1: Kapichira Da Request for Quota Single Stage - One E Pending Impl Y2022-23 / Supply and delive IDA / E0970 m Rehabilitation and Strengt Post Limited 17,900.00 0.00 2022-07-10 2022-08-09 2022-08-23 tions nvelope ementation ry of Laptops hening MW-EGENCO-355611-GO-RF Component 1: Kapichira Da Q / Supply of Culverts for Rec Request for Quota Single Stage - One E Pending Impl IDA / E0970 m Rehabilitation and Strengt Post Limited 76,000.00 0.00 2022-09-30 2022-10-10 2022-10-24 onstruction Works for the Te tions nvelope ementation hening mporary Chilala bridge on Ac cess Road T146 EGC04/WBP178914/G/RFQ/F Component 1: Kapichira Da Y2022-23. / Supply of Office Request for Quota Single Stage - One E Pending Impl IDA / E0970 m Rehabilitation and Strengt Post Limited 25,000.00 0.00 2022-06-22 2022-08-09 2022-08-23 Furniture and Equipment: 7 ( tions nvelope ementation hening No.) Desks and chairs, 3 (No. ) x Fridges) MW-EGENCO-349167-GO-RF Component 1: Kapichira Da Single Stage - One E Pending Impl B / Supply, Delivery and Insta IDA / E0970 m Rehabilitation and Strengt Post Request for Bids Limited 1,334,545.00 0.00 2023-08-20 2023-08-25 2023-10-06 2023-11-05 2023-12-10 2024-06-07 nvelope ementation llation of Dam Instrumentatio hening n Equipment MW-EGENCO-324264-GO-RF Component 1: Kapichira Da Request for Quota Single Stage - One E Pending Impl Q / Supply and Delivery of ea IDA / E0970 m Rehabilitation and Strengt Post Limited 852,787.00 0.00 2023-08-11 2023-10-06 2024-04-03 tions nvelope ementation rthen and quarry materials fo hening r Phase 2 MW-EGENCO-368399-GO-RF Component 1: Kapichira Da Request for Quota Single Stage - One E Pending Impl Q / Supply and delivery of 1n IDA / E0970 m Rehabilitation and Strengt Post Limited 75,000.00 0.00 2023-07-01 2023-08-26 2024-02-22 tions nvelope ementation o. Motor Vehicle hening NON CONSULTING SERVICES Page 1 Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-EGENCO-324251-NC-RF Component 1: Kapichira Da Q / Hiring of 50-ton mobile cr Request for Quota Single Stage - One E Pending Impl IDA / E0970 m Rehabilitation and Strengt Post Limited 145,000.00 0.00 2022-09-20 2022-09-24 2023-03-23 ane and tipper trucks, and Ex tions nvelope ementation hening cavators for Spillways MW-EGENCO-324253-NC-RF Component 1: Kapichira Da Q / Hiring of Tipper trucks, B Request for Quota Single Stage - One E Under Imple IDA / E0970 m Rehabilitation and Strengt Post Limited 995,000.00 0.00 2022-07-29 2022-07-28 2022-08-02 2023-01-29 ull Dossers, Dampers and Ex tions nvelope mentation hening cavators for Desilting of Rive r left bank channel CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-EGENCO-324259-CS-CQ S / Consultancy Services for Component 1: Kapichira Da ESIA for Dam Rehabilitation Consultant Qualifi IDA / E0970 m Rehabilitation and Strengt Post Limited 1,200,000.00 0.00 Canceled 2022-11-28 2023-03-31 2022-12-12 2023-01-11 2023-02-15 2023-08-14 Assessment and Preparation cation Selection hening of Safeguards Studies and pl ans – supervision of impleme ntation of E&S plans EGC09/WBP178914/S/RFP/FY 2022-24 / Engineering Consul tancy Services for upgrade of the Dam, Design, procureme Component 1: Kapichira Da Consultant Qualifi Under Implement nt support , supervision , up IDA / E0970 m Rehabilitation and Strengt Post Limited 4,200,000.00 0.00 2022-08-11 2022-08-11 2022-08-11 2022-08-11 2022-11-09 2022-11-12 2023-05-11 cation Selection ation grade operation manuals, da hening m break analysis, prepare e mergency preparedness plan , dam safety report and Sedi ment Management Plan MW-EGENCO-324256-CS-CQ Component 1: Kapichira Da S / Recruitment of consultant Consultant Qualifi IDA / E0970 m Rehabilitation and Strengt Post Limited 50,000.00 0.00 Canceled 2023-01-23 2023-02-06 2023-03-08 2023-04-12 2023-10-09 (Firm) for capacity building in cation Selection hening OHS and working in fast flow ing water MW-EGENCO-362145-CS-CQ S / Consultancy Services for t he Environmental and Social Component 1: Kapichira Da Impact Assessment (ESIA) for Consultant Qualifi Open - Internationa IDA / E0970 m Rehabilitation and Strengt Prior 1,200,000.00 0.00 Under Review 2023-05-19 2023-05-18 2023-05-19 2023-05-23 2023-06-18 2023-07-03 2023-08-07 2024-02-03 Dam Rehabilitation Assessm cation Selection l hening ent and Preparation of Safeg uards Studies and Plans – Su pervision of Implementation of E&S Plans MW-EGENCO-324260-CS-CQ Component 1: Kapichira Da S / Consultancy Services for Consultant Qualifi Pending Impleme IDA / E0970 m Rehabilitation and Strengt Post Limited 100,000.00 0.00 2023-08-28 2023-09-11 2023-10-11 2023-11-15 2024-05-13 Disaster Risk analysis and E cation Selection ntation hening mergency preparedness for t he project life cycle INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MW-EGENCO-314823-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of Dam Expert on P IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Under Review 2022-10-01 2023-06-26 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection anel of Experts hening MW-EGENCO-314816-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of an Hydrological IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Under Review 2022-10-01 2023-06-26 2022-10-11 2022-11-01 2022-12-06 2023-06-04 ant Selection Expert on Panel of Experts hening MW-EGENCO-314824-CS-IND Component 1: Kapichira Da Individual Consult Pending Impleme V / Hiring of Enviromental Saf IDA / E0970 m Rehabilitation and Strengt Post Limited 216,000.00 0.00 2022-10-01 2022-10-06 2022-10-27 2022-12-01 2023-05-30 ant Selection ntation eguards Specialist in PIU hening EGC06/WBP178914/S/RFP/FY Component 1: Kapichira Da 2022-23 / Design and Constr Individual Consult Direct - Internation Pending Impleme IDA / E0970 m Rehabilitation and Strengt Post 168,000.00 0.00 2022-08-02 2022-08-02 2022-08-19 2022-09-10 2023-03-09 uction Supervision Services f ant Selection al ntation hening or construction of the Cofferd am EGC011/WBP178914/S/RFP/F Component 1: Kapichira Da Y2022-23 / Geological Servic Individual Consult Direct - Internation Pending Impleme IDA / E0970 m Rehabilitation and Strengt Post 20,000.00 0.00 2022-08-30 2022-09-01 2022-09-02 2022-09-19 2023-03-18 es for CSD Cofferdam Design ant Selection al ntation hening and Foundation Construction MW-EGENCO-324248-CS-IND Component 1: Kapichira Da Individual Consult Pending Impleme V / Aerial Photography and M IDA / E0970 m Rehabilitation and Strengt Post Limited 50,000.00 0.00 2022-10-26 2022-10-28 2023-01-22 2023-02-26 2023-08-25 ant Selection ntation apping (Drone Survey) hening EGC07/WBP178914/S/RFP/FY Component 1: Kapichira Da Individual Consult Direct - Internation Pending Impleme 2022-23 / Hiring of Sediment IDA / E0970 m Rehabilitation and Strengt Post 168,000.00 0.00 2022-07-18 2022-07-20 2022-08-05 2022-08-16 2023-02-12 ant Selection al ntation Management Expert hening MW-EGENCO-324250-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of Monitoring and E IDA / E0970 m Rehabilitation and Strengt Post Limited 144,000.00 0.00 Canceled 2022-11-28 2022-12-03 2022-12-24 2023-01-28 2023-07-27 ant Selection valuation Specialist hening EGC023/WBP178914/S/RFP/F Component 1: Kapichira Da Individual Consult Pending Impleme Y2022-33 / Hiring of Social a IDA / E0970 m Rehabilitation and Strengt Post Limited 216,000.00 0.00 2022-05-27 2022-06-01 2022-06-08 2022-06-27 2022-12-24 ant Selection ntation nd Gender Safeguards Speci hening alist for PIU MW-EGENCO-314790-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of a Social Develop IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Canceled 2023-07-31 2023-08-13 2023-09-03 2023-10-08 2024-04-05 ant Selection ment Specialist on Panel of E hening xperts EGC022/WBP178914/S/RFP/F Component 1: Kapichira Da Individual Consult Pending Impleme Y2022-32 / Hiring of Procure IDA / E0970 m Rehabilitation and Strengt Post Open - National 216,000.00 0.00 2022-05-23 2022-06-06 2022-06-27 2022-07-10 2025-05-25 ant Selection ntation ment Specialist for PIU hening Page 2 MW-EGENCO-366924-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of Geotechnical Ex IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Under Review 2023-06-16 2023-06-26 2023-06-26 2023-07-17 2023-08-21 2024-02-17 ant Selection pert on Dam Safety Panel of hening Experts MW-EGENCO-366926-CS-IND Component 1: Kapichira Da Individual Consult V / Hiring of Hydromechanica IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Under Review 2023-06-16 2023-06-26 2023-06-26 2023-07-17 2023-08-21 2024-02-17 ant Selection l Expert on Dam Safety Panel hening of Experts MW-EGENCO-314833-CS-IND Component 1: Kapichira Da V / Hiring of an Environmenta Individual Consult IDA / E0970 m Rehabilitation and Strengt Post Direct - National 240,000.00 0.00 Under Review 2023-07-31 2023-06-26 2023-08-10 2023-08-31 2023-10-05 2024-04-02 l and Social Management Spe ant Selection hening cialist on Panel of Experts Page 3 PROCUREMENT PLAN (Textual Part) Project information: [Vietnam] [JSDF - STRENGTHENING PREPAREDNESS AND RESPONSE TO COVID-19 AT THE GRASSROOTS LEVEL IN VIETNAM] [P174401] Project Implementation agency: [Institute for Social Development Studies] Date of the Procurement Plan: [April 27, 2022] Period covered by this Procurement Plan: [April 2022 – December 2022] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Vietnam Public Procurement Law dated 2013 and the regulations guiding its implementation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations, ensuring compliance with the core principles of the WB’s Procurement Regulations and using sample procurement documents acceptable to the WB. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Hands-on Expanded Implementation Support (HEIS): Not Applicable. PROCUREMENT Vietnam : JSDF - Strengthening Preparedness and Response to COVID-19 at the Grassroots level in Vietnam PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2022-04-28 Revised Plan Date(s): (comma delineated, leave blank if 2023-05-18 none) Project ID: P174401 GPN Date: 2022-04-08 Project Name: JSDF - Strengthening Preparedness and Response to COVID-19 at the Grassroots level in Vietnam Loan / Credit No: TF / B6532 Institute for Social Development Studies Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management and Ad G-1 / Office Equipment 202 Request for Quota Single Stage - One E TF / B6532 ministration, Monitoring and Post Open - National 20,400.00 0.00 Signed 2022-07-05 2022-07-28 2022-08-27 2 tions nvelope Evaluation, and Knowledge Dissemination Building capacities at the gr assroots level in Preparedne G-2 / Office Equipment 202 Request for Quota Single Stage - One E Pending Impl TF / B6532 ss for, Response to, Recover Post Open - National 16,000.00 0.00 2023-06-04 2023-06-28 2023-07-28 3 tions nvelope ementation y and Resilience from COVID -19 and ot her health emerg encies NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Project Management and Ad CQS-1 / Consultant firm to c Consultant Qualifi TF / B6532 ministration, Monitoring and Post Open - National 25,000.00 23,955.15 Signed 2022-04-28 2022-05-13 2022-05-18 2022-05-30 2022-06-30 2022-07-11 2022-08-10 2022-07-14 2022-08-21 2022-10-12 onduct baseline survey cation Selection Evaluation, and Knowledge Dissemination Project Management and Ad Consultant Qualifi Under Implement CQS-2 / Recruit Audit firm TF / B6532 ministration, Monitoring and Post Open - National 15,000.00 0.00 2022-10-10 2022-12-22 2022-10-12 2022-11-16 2022-12-31 2023-01-05 2025-06-20 cation Selection ation Evaluation, and Knowledge Dissemination INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Building capacities at the gr assroots level in Preparedne CSI-1 / Senior Project Officer Individual Consult TF / B6532 ss for, Response to, Recover Prior Limited 76,800.00 75,477.42 Signed 2022-04-27 2022-04-29 2022-04-28 2022-04-29 2022-05-12 2022-05-10 2022-05-16 2022-05-12 2024-12-31 Cum Procurement Specialist ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne Individual Consult CSI-2 / Project Officer TF / B6532 ss for, Response to, Recover Post Limited 54,400.00 53,471.47 Signed 2022-04-28 2022-04-29 2022-04-29 2022-05-05 2022-05-06 2022-05-06 2022-05-11 2022-05-07 2024-12-31 ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-3 / Chief Technical Mana Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 47,520.00 46,260.69 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-09 2022-06-06 2022-05-16 2022-05-07 2025-01-12 ger working for CPMU ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.2 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-10 2022-05-10 2022-05-16 2022-05-13 2024-12-31 tor for Khanh Hoa ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.1 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Terminated 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-10 2022-05-10 2022-05-17 2022-05-12 2024-12-31 tor for Vinh Phuc ant Selection y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-4.3 / Recruiting coordina Individual Consult TF / B6532 ss for, Response to, Recover Post Limited 32,000.00 31,398.55 Signed 2022-04-28 2022-04-29 2022-05-06 2022-04-29 2022-05-08 2022-05-10 2022-05-11 2022-05-12 2024-12-31 tor for Long An ant Selection y and Resilience from COVID -19 and ot her health emerg encies Project Management and Ad CSI-5 / Communication Speci Individual Consult TF / B6532 ministration, Monitoring and Post Open 18,000.00 0.00 Signed 2022-06-27 2023-06-20 2022-07-23 2022-07-28 2022-07-25 2022-07-29 2022-07-26 2024-12-31 alist ant Selection Evaluation, and Knowledge Dissemination Developing and piloting mod CSI-6 / Network Operation T els to support the most vuln Individual Consult TF / B6532 Post Open - National 59,850.00 0.00 Signed 2022-08-08 2022-08-09 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-12-31 echnical Specialist erable groups in the prepare ant Selection dness and response to COVI D-19 Page 1 Building capacities at the gr CSI-7 / Consultant to develo assroots level in Preparedne Individual Consult p intersectoral collaboration TF / B6532 ss for, Response to, Recover Post Open - National 7,500.00 7,070.78 Signed 2022-08-08 2023-01-11 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-08-29 2022-12-31 ant Selection plan y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr CSI-8 / Consultant to develo assroots level in Preparedne p guideline on infection prev Individual Consult TF / B6532 ss for, Response to, Recover Post Open - National 4,050.00 3,872.10 Signed 2022-08-08 2023-05-19 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-09-29 2022-12-31 ention and control inside co ant Selection y and Resilience from COVID mmunity health stations -19 and ot her health emerg encies CSI-9 / Consultant to develo Building capacities at the gr p Guideline on provision of e assroots level in Preparedne Individual Consult ssential healthcare services TF / B6532 ss for, Response to, Recover Post Open - National 9,150.00 8,754.30 Signed 2022-08-08 2023-06-20 2022-08-19 2022-08-18 2022-08-22 2022-08-19 2022-08-24 2022-08-29 2022-12-31 ant Selection and patient management, tre y and Resilience from COVID atment support and patient r -19 and ot her health emerg eferral during pandemics encies Raising awareness and know CSI-10 / Consultant to devel ledge towards changing attit Individual Consult op Guideline on risk commun TF / B6532 Post Open - National 7,600.00 7,239.14 Signed 2022-08-08 2022-08-09 2022-08-19 2022-08-25 2022-08-22 2022-08-26 2022-08-24 2022-09-08 2022-12-31 udes and behavior of the co ant Selection ication mmunity through risk comm unication CSI-11 / Consultant to upgra Project Management and Ad Individual Consult Under Implement de website for establishment TF / B6532 ministration, Monitoring and Post Open - National 2,000.00 0.00 2022-11-14 2022-11-14 2022-11-25 2022-11-26 2022-12-01 2022-12-31 ant Selection ation and operation of an informati Evaluation, and Knowledge on hub Dissemination Building capacities at the gr CSI-4.1.1 / Vinh Phuc Provinc assroots level in Preparedne ial Project Coordinator (Termi Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 19,000.00 0.00 2023-05-04 2023-05-04 2023-05-11 2023-05-12 2023-05-15 2024-12-31 nate contract CSI-4.1/2022, r ant Selection ation y and Resilience from COVID ecruit new person on board) -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne Individual Consult Under Implement CSI-12 / Project Assistant TF / B6532 ss for, Response to, Recover Post Open - National 20,000.00 0.00 2023-06-01 2023-05-22 2023-06-22 2023-06-24 2023-06-26 2024-12-31 ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-13 / Midterm review con Individual Consult Pending Impleme TF / B6532 ss for, Response to, Recover Post Open - National 7,000.00 0.00 2023-06-01 2023-06-27 2023-06-30 2023-07-05 2023-09-01 sultant ant Selection ntation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-14 / Community develop Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Open - National 24,000.00 0.00 2023-06-15 2023-06-20 2023-06-29 2023-06-30 2023-07-01 2024-12-31 ment Specialist ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.1 / Vinh Phuc Provinci Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 al Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.2 / Khanh Hoa Provin Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 cial Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Building capacities at the gr assroots level in Preparedne CSI-15.3 / Long An Provincial Individual Consult Under Implement TF / B6532 ss for, Response to, Recover Post Limited 5,000.00 0.00 2023-06-21 2023-06-22 2023-06-28 2023-06-30 2023-07-03 2024-12-31 Project Assistant ant Selection ation y and Resilience from COVID -19 and ot her health emerg encies Page 2