18-MONTH PROCUREMENT PLAN Project information: Nigeria Rural Access And Agricultural Marketing Project (RAAMP) - P163353 Project Implementation Agencies: Federal Ministry of Agriculture and Rural Development and State Project Implementation Units (SPIUs) Date of the Procurement Plan: September 18, 2019 Period covered by this Procurement Plan: February 2019 to July 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nigeria Public Procurement Act 2007, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [15% is applicable for those contracts identified in the Procurement Plan tables]; Works: [ 7.5% is applicable for those contracts identified in the Procurement Plan tables] I. Threshold for Prior Review – Goods, Works, Non-Consulting Services and Consulting Services Prior-review Thresholds Thresholds for Procurement Methods High Substanti Moderate Low Risk Goods, IT & Non-Consulting Shortlist of National Procurement Type Risk al Risk Risk Works ($'000) ($'000) ($'000) ($'000) Services Consultants Request Request Engineering Open for for Open Open Open Consultin & Quotatio Quotatio 10,0 15,0 20,0 Internatio National internatio National g Constructio Works n or n or 5,000 00 00 00 nal or ICB or NCB National nal or ICB or NCB National Services n ($'000) ($'000) ($'000) ($'000) ($'000) Supervision Shopping Shopping ($'000) ($'000) ($'000) Goods, IT & Non- 2,0 4,0 6,0 Consulting Services 1,500 00 00 00 ≧ < ≦ ≧ < ≦ < ≦ Consultants 1,0 2,0 4,0 20,0 20,0 5,0 5,0 1 3 5 200 (Firms) 500 00 00 00 00 00 00 00 00 00 00 Post Review: All contracts not subject to prior review shall be subject to post review. Summary of the procurement packages for Goods, Works and Non-Consulting Services (Planned for the first 18 months after project effectiveness): Selecti Market on Evaluation Approa Review Metho Options Expected ch Prequal- Domestic Expected by Estimat d (Most date of Sr. Contract (Open- ification Preferenc date of Bank ed Cost (RFP, Advantageou bid/ No Description Nation (Yes/ e Contract (Prior/ (US$) RFB, s Bid, BAFO, proposal al/ No) (Yes/No) Signature Post) RFQ, Rated Criteria opening Limited DS etc.) etc.) etc.) Procurement of Air Conditioners 2 Limited Lowest March. 1 Post 24,600 RFQ No No Feb. 2020 Horse power Evaluated Cost 2020 (Split Unit) (Goods) Procurement of Steel File cabinets, Lowest March. 2 Spiral Binding Post 12,600 Limited RFQ Evaluated Cost No No Feb. 2020 2020 Machines and Consumables (Goods) Procurement of External hard disk + software packages Lowest March. 3 (licensed MS Post 12,300 Limited RFQ Evaluated Cost No No 2020 April. 2020 Office, Autocads, Antivirus, Converter etc) (Goods) Procurement of Laptops and Lowest March. 4 Post 100,000 Limited RFQ No No May. 2020 Tablets Evaluated Cost 2020 (Goods) Procurement Lowest March. 5 Post 22,400 Limited RFQ No No April. 2020 of Evaluated Cost 2020 Photocopying Machines (Goods) Medium Sized Lowest March. 6 Refrigerators Post 10,800 Limited RFQ Evaluated Cost No No 2020 April. 2020 (Goods) Procurement of Safety Equipment (Boots, Lowest 7 Post 39,000 Limited RFQ No No June. 2020 July, 2020 Helmets, Evaluated Cost Reflective Jackets etc.) (Goods) Construction Measuring Manual Wheel Lowest August. 8 Post 6,500 Limited RFQ No No July 2020 (Surveyor’s Evaluated Cost 2020 Wheel) (Goods) Roads Maintenance Equipment for Community based road maintenance (30 Nos tipping tricycles and other Open- 1,235,0 Lowest 9 equipment Post Nationa RFB No No Sept. 2020 Dec. 2020 00 Evaluated Cost such roads l signs and; cutlasses, wheelbarrows, hand rammer, digger, helmet, watering cans, reflective jacket, long shovel, nose cover, boots etc) (Goods) Procurement of Office Equipment, Printers, Open- Digital Lowest August. 10 Post 420,000 Nationa RFB No No June. 2020 Cameras & Evaluated Cost 2020 l Sundry Communicatio n devices (Goods) Purchase of Open- Project 2,940,0 Lowest March. 11 Prior Nationa RFB No No May. 2020 Vehicles 00 Evaluated Cost 2020 l (Goods) Server, Network System and other Open- Lowest equipment & Post 150,000 Nationa RFB Evaluated Cost No No Feb. 2020 May. 2020 accessories for l NiRTIMS and CosMos (Goods) Design and Construction of 200km of Rural Roads Open- 134,000 Rated Criteria (13 Prior Interna RFP No No Jun. 2020 Dec. 2020 ,000.00 and Cost Contracts of tional US$10.3 Million each) (Works) Construction/E stablishment Open – of Agro- 2,000,0 Lowest March. Post Nationa RFB No No July. 2021 Logistics 00 Evaluated Cost 2021 l centers/hubs at strategic locations (Multiple contracts) (Works) Construction /Rehabilitation of 10 Nos. Rural Bridges Open- 8,000,0 Lowest March. & Large Post Nationa RFB No No July. 2022 00 Evaluated Cost 2021 culverts (US$ l 0.6 M each Package) (Works) Local Community Group (LCG) and micro- enterprises maintenance Open- 14,000, Lowest of pilot roads Post Nationa RFB No No April. 2020 June.2020 000 Evaluated Cost (Multiple l Contracts in 13 States - US$ 0.002/year) (Works) II. Summary of the procurement packages for Consulting Services -Planned for the first 18 months after project effectiveness): Selection Market Method Review Approach Expected Expected Estimate (QCBS, Shortlisti Sr. by Bank (Open - date of bid/ date of Contract Description d Cost FBS, ng No (Prior/ International proposal Contract (US$) LCBS, (Yes/ No) Post) / National/ opening Signature QBS, CQS, etc.) DS etc.) Offshore & Onshore training and Workshops for Open- March. 1 the 13 states (Multiple Post 5,200,000 CQS No May. 2020 National 2020 contracts not to exceed US$ 0.1 M) (Consultancy) Consultancy Services for Detailed assessment, preliminary engineering design, ESIA, Procurement Support for Rural roads and Bridges; Road and 25,390,00 Open- 2 Bridge Supervision Prior QCBS Yes June. 2020 Nov. 2020 0 International Consultancy; Assessment of project security risk and mitigation (Multiple contracts spread in different locations) (Consultancy) Consultancy Services for design, procurement and supervision for Agro- Open- 3 logistics centers (Multiple Post 6,500,000 QCBS Yes Sep. 2020 Dec. 2020 International contracts spread in different locations) (Consultancy) Consultancy Services for the establishment of state Open- March. August. 4 road fund, and Post 5,665,000 QCBS Yes National 2020 2020 establishment of state rural access roads administration (Multiple contracts at 13 states) (Consultancy) Consultancy services on the development and operationalization of the Nigeria Rural Transport Infrastructure Management System (NiRTIMS) for sustainable road asset; Planning and Open- 5 Post 5,860,000 QCBS Yes Feb. 2020 July. 2020 implementation of the National routine maintenance system, spot improvement, periodic maintenance for rural roads. (Multiple contracts at 13 states) (Consultancy) Technical assistance consultancy services for the provision of technical advice (TA) to enhance the performance of agro- logistics centers (to ensure effective utilization of the facilities at the agro- Open- National March. 6 logistics centers); Post 4,975,000 QCBS Yes July. 2020 provision of TA and 2020 implements to farm level post-harvest agro-logistics activities and enhance the engagement of women and unemployed youth. (Multiple contracts at 13 states) (Consultancy) Consultancy services support for coordination of Open- 7 Post 2,442,000 CQS No Feb. 2020 April. 2020 project implementation at National Federal and State Levels (Multiple contracts at 13 states) (Consultancy) Consultancy services on Impact Evaluation, Baseline Data Collection, Comprehensive Technical Audit, Consultancy support for the development and Open- March. 8 operationalization of the Post 5,325,000 QCBS Yes July.2020 National 2020 smartphone-based construction site monitoring system (CoSMoS) (Multiple contracts at 13 states) (Consultancy) Consultancy support for the development and monitoring of Grievance Redress Mechanism and Gender-Based Violence; Development of road safety manual and training Open- 9 Post 1,843,000 CQS No April.2020 June. 2020 at the state level; National establishment/strengtheni ng the state traffic management agencies; road safety audit. (Multiple contracts at 13 states) (Consultancy) Appendix 1 Letter of Acceptance of the World Bank’s Anti-Corruption Guidelines and Sanctions Framework Date: Invitation of Bids/Proposals No.__________ To: ___________________________________________________________________________ We, along with our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not) consultants and personnel, acknowledge and agree to abide by the World Bank’s policy regarding Fraud and Corruption (corrupt, fraudulent, collusive, coercive, and obstructive practices), as set out and defined in the World Bank’s Anti-Corruption Guidelines1 in connection with the procurement and execution of the contract (in case of award), including any amendments thereto. We declare and warrant that we, along our sub-contractors, sub-consultants, service providers, suppliers, agents (whether declared or not), consultants and personnel, , are not subject to, and are not controlled by any entity or individual that is subject to, a temporary suspension, early temporary suspension, or debarment imposed by a member of the World Bank Group, including, inter alia, a cross-debarment imposed by the World Bank Group as agreed with other international financial institutions (including multilateral development banks), or through the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement. Further, we are not ineligible under the laws or official regulations of [Insert name of Employer as per bidding document] or pursuant to a decision of the United Nations Security Council. We confirm our understanding of the consequences of not complying with the World Bank’s Anti-Corruption Guidelines, which may include the following: a. rejection of our Proposal/Bid for award of contract; b. in the case of award, termination of the contract, without prejudice to any other remedy for breach of contract; and c. sanctions, pursuant to the Bank’s Anti-corruption Guidelines and in accordance with its prevailing sanctions policies and procedures as set forth in the Bank’s Sanctions Framework. This may include a 1Guidelineson Preventing and Combating Fraud and Corruption in Projects Financed by International Bank for Reconstruction and Development Loans and the International Development Agency Credits and Grants, dated October 15, 2006, and revised in January 2011 and July 2016, as they may be revised from time to time. public declaration of ineligibility, either indefinitely or for a stated period of time, (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;2 (ii) to be a nominated3 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project. We understand that we may be declared ineligible as set out above upon: a. completion of World Bank Group sanctions proceedings according to its prevailing sanctions procedures; b. cross-debarment as agreed with other international financial institutions (including multilateral development banks); c. the application of a World Bank Group finding of non-responsibility on the basis of Fraud and Corruption in connection with World Bank Group corporate procurement; or d. temporary suspension or early temporary suspension in connection with an ongoing World Bank Group sanctions proceeding. For avoidance of doubt, the foregoing effects of ineligibility do not extend to a sanctioned firm’s or individual’s execution of its ongoing Bank-financed contracts (or its ongoing sub-agreements under such contracts) that are not the subject of a material modification, as determined by the Bank. We shall permit, and shall cause our sub-contractors, sub-consultants, agents (whether declared or not), personnel, consultants, service providers or suppliers, to permit the Bank to inspect4 all accounts, records, 2 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 3 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 4 Inspections in this context are usually investigative (i.e., forensic) in nature: they involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not and other documents relating to the procurement process and/or contract execution (in the case of award), and to have them audited by auditors appointed by the Bank. We agree to preserve all accounts, records, and other documents (whether in hard copy or electronic format) related to the procurement and execution of the contract. Name of the Bidder/Consultant: Name of the person duly authorized to sign the Bid/Proposal on behalf of the Bidder/Consultant: Title of the person signing the Letter: limited to accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data, and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third-party verification of information. PROCUREMENT Nigeria : Nigeria Rural Access and Agricultural Marketing Project PLAN General Information Country: Nigeria 2021-04-23 Bank’s Approval Date of the Original Procurement Plan: 2023-06-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163353 GPN Date: Project Name: Nigeria Rural Access and Agricultural Marketing Project Loan / Credit No: IDA / 65190 AKWA IBOM RAAMP Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned NG-AKWA IBOM RAAMP-230 Request for Bids - Component A. Improvement 755-CW-RFB / Construction o Single Stage - One E Small Works SPD Pending Imp 2024-04-1 IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 900,000.00 0.00 2022-09-28 2022-10-03 2022-11-14 2022-12-14 2023-01-18 f 100 meters Cross - Drainag nvelope (1 envelope proce lementation 2 Infrastructure e Structures (Culverts/Bridge ss) s) on Rural Roads Request for Bids - NG-AKWA IBOM RAAMP-280 Component A. Improvement Single Stage - One E Small Works SPD Under Imple 2023-06-3 436-CW-RFB / Upgrading/ Co IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 600,000.00 0.00 2022-07-04 2022-10-25 2022-07-25 2022-12-16 2022-07-27 2022-11-22 2022-08-26 2022-09-23 nvelope (1 envelope proce mentation 0 nstruction of 11km of priority Infrastructure ss) pilot Road NG-AKWA IBOM RAAMP-280 Request for Bids - Component A. Improvement 438-CW-RFB / Physical impro Single Stage - One E Small Works SPD Pending Imp 2024-06-2 IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 1,000,000.00 0.00 2022-09-19 2022-10-10 2022-10-12 2022-11-11 2022-12-09 vement of about 2 nos. Agro- nvelope (1 envelope proce lementation 6 Infrastructure logistics Centers (ALCs) ss) Request for Bids - NG-AKWA IBOM RAAMP-230 Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-01-0 747-CW-RFB / Spot Improve IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 5,000,000.00 0.00 2022-07-26 2022-08-16 2022-08-18 2022-09-08 2022-10-13 nvelope (1 envelope proce lementation 6 ment of about 225 km Rural ance Enhancement and Sect ss) Roads or Reform Request for Bids - NG-AKWA IBOM RAAMP-280 Component A. Improvement Single Stage - One E Small Works SPD Pending Imp 2024-06-1 431-CW-RFB / Rural Roads up IDA / 65190 of Rural Access and Trading Post Request for Bids Open - National 2,000,000.00 0.00 2022-09-29 2022-10-20 2022-10-22 2022-11-21 2022-12-19 nvelope (1 envelope proce lementation 1 grading of about 40km Infrastructure ss) Request for Bids - NG-AKWA IBOM RAAMP-230 Component B. Asset Manage Single Stage - One E Small Works SPD Pending Imp 2024-04-0 673-CW-RFB / Backlog Maint IDA / 65190 ment, Agro-logistics Perform Post Request for Bids Open - National 2,500,000.00 0.00 2022-09-27 2022-10-02 2022-11-13 2022-12-13 2023-01-10 nvelope (1 envelope proce lementation 4 enance/Rehabilitation of 100 ance Enhancement and Sect ss) km Rural Roads or Reform GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 299-GO-RFQ / Purchase of off IDA / 65190 evelopment, Project Manage Post Limited 50,000.00 0.00 2022-06-07 2022-07-12 2022-08-11 tions nvelope ementation ice furniture and equipment ment and Risk Mitigation NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Under Imple 389-GO-RFQ / Purchase of 1 IDA / 65190 evelopment, Project Manage Post Limited 33,000.00 0.00 2022-05-23 2022-08-30 2022-06-27 2022-07-27 tions nvelope mentation no. 30 KVA Generators ment and Risk Mitigation NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 590-GO-RFQ / Purchase of pr IDA / 65190 evelopment, Project Manage Post Limited 50,000.00 0.00 2022-06-27 2022-08-01 2022-08-31 tions nvelope ementation omotional materials (Flip Cha ment and Risk Mitigation rt, Memo etc.) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 280-GO-RFQ / Purchase of 2n IDA / 65190 evelopment, Project Manage Post Limited 150,000.00 0.00 2022-06-13 2022-07-25 2022-08-24 tions nvelope ementation os. of operating project vehic ment and Risk Mitigation les NG-AKWA IBOM RAAMP-230 339-GO-RFQ / Purchase of 15 nos. laptops, 10nos, Desktop Component C. Institutional D Request for Quota Single Stage - One E Pending Impl s, 10nos Printers/Fax, 2Nos H IDA / 65190 evelopment, Project Manage Post Limited 80,000.00 0.00 2022-06-20 2022-07-25 2022-08-24 tions nvelope ementation eavy Duty Photocopiers 10No ment and Risk Mitigation s Scanners, 1 nos Projector, I nternet Installation, Air Condi tioners, and Consumables NG-AKWA IBOM RAAMP-230 409-GO-RFQ / Purchase of Sa feguard equipment (PPEs, fir Component C. Institutional D st aid kits, environmental mo Request for Quota Single Stage - One E Pending Impl IDA / 65190 evelopment, Project Manage Post Limited 80,000.00 0.00 2022-07-02 2022-08-13 2022-09-12 nitoring and tracking equipm tions nvelope ementation ment and Risk Mitigation ent including in-situ air qualit y kits, noise meter, PH meter , caution tapes, measuring ta pes, camera, GPS etc.) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Request for Quota Single Stage - One E Pending Impl 391-GO-RFQ / Purchase of da IDA / 65190 evelopment, Project Manage Post Limited 10,000.00 0.00 2022-04-08 2022-05-20 2022-07-04 tions nvelope ementation ta Collection Gadgets (6Nos) ment and Risk Mitigation AKS/RAAMP/RFQ/O1/23 / Pro Component C. Institutional D Request for Quota Single Stage - One E Pending Impl curement of office stationerie IDA / 65190 evelopment, Project Manage Post Limited 10,000.00 0.00 2023-07-17 2023-08-24 2023-09-07 tions nvelope ementation s and Consumables for AKS R ment and Risk Mitigation AAMP NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 NG-AKWA IBOM RAAMP-280 293-CS-QCBS / Consultancy S Component A. Improvement ervices for Design and Super Quality And Cost- Open - Internationa Under Implement IDA / 65190 of Rural Access and Trading Post 430,000.00 0.00 2022-03-09 2022-06-09 2022-04-08 2022-08-17 2022-05-06 2022-10-06 2022-06-03 2022-11-17 2022-07-03 2022-12-15 2022-08-07 2022-09-11 2024-11-29 vision of 160 km Rural Road Based Selection l ation Infrastructure Upgrading (Design & Build; N on-Design & Build contracts) NG-AKWA IBOM RAAMP-230 440-CS-CQS / Consultancy se rvices for Design and Supervi Component B. Asset Manage sion of Backlog Maintenance, ment, Agro-logistics Perform Consultant Qualifi IDA / 65190 Post Open - National 365,000.00 0.00 Canceled 2021-05-10 2021-05-17 2021-06-23 2021-07-07 2021-08-04 2023-12-22 Spot Improvement, Performa ance Enhancement and Sect cation Selection nce Based Maintenance Cont or Reform ract (PBMC) and Cross-draina ge Structures (bridges/ culve rts) in Akwa Ibom State NG-AKWA IBOM RAAMP-280 Component A. Improvement 333-CS-CQS / Consultancy se Consultant Qualifi Under Implement IDA / 65190 of Rural Access and Trading Post Open - National 120,000.00 0.00 2022-03-20 2022-03-08 2022-04-10 2022-05-19 2022-05-08 2022-08-09 2022-06-07 2022-09-07 2022-07-12 2023-05-08 rvices for the Design review cation Selection ation Infrastructure and Supervision of 11 Km of priority Pilot road NG-AKWA IBOM RAAMP-280 337-CS-QCBS / Consultancy S Component A. Improvement Quality And Cost- Open - Internationa Under Implement ervices for Design and Super IDA / 65190 of Rural Access and Trading Post 395,000.00 0.00 2022-03-20 2022-03-09 2022-04-19 2022-12-24 2022-06-14 2023-02-03 2022-06-28 2022-07-19 2022-08-09 2022-09-06 2024-11-14 Based Selection l ation vision of physical improveme Infrastructure nt of 5 to 6 nos. Agro-logistic s Centers (ALCs) NG-AKWA IBOM RAAMP-230 412-CS-CQS / Consultancy Se Component A. Improvement rvices for Design and Supervi Consultant Qualifi IDA / 65190 of Rural Access and Trading Post Open - National 350,000.00 0.00 Canceled 2021-09-06 2021-09-13 2021-10-20 2021-11-03 2021-12-01 2024-06-18 sion of Rural Road Upgrading cation Selection Infrastructure (Design & Build) and Improve ment of Agro-Logistics Hubs ( ALHs) in Akwa Ibom State. NG-AKWA IBOM RAAMP-282 Component B. Asset Manage 705-CS-CQS / Consultancy Se ment, Agro-logistics Perform Consultant Qualifi Under Implement rvices for Design and Supervi IDA / 65190 Post Open - National 180,000.00 0.00 2022-03-20 2022-06-09 2022-04-10 2022-06-08 2022-05-15 2022-08-31 2022-05-29 2022-10-13 2022-06-26 2023-06-21 ance Enhancement and Sect cation Selection ation sion of Backlog maintenance/ or Reform Réhabilitation of roads (125K M) NG-AKWA IBOM RAAMP-282 708-CS-CQS / Consultancy Se Component B. Asset Manage rvices for Design and Supervi ment, Agro-logistics Perform Consultant Qualifi Under Implement IDA / 65190 Post Open - National 200,000.00 0.00 2022-03-28 2022-03-08 2022-04-18 2022-06-08 2022-05-23 2022-08-30 2022-06-06 2022-10-21 2022-07-04 2023-06-29 sion of Spot Improvement (3 ance Enhancement and Sect cation Selection ation 00KM) and construction of 50 or Reform linear meter Cross-drainage s tructures (bridges/culverts) NG-AKWA IBOM RAAMP-280 320-CS-CQS / Consultancy se rvices for Design and Supervi Component B. Asset Manage sion of Backlog Maintenance/ ment, Agro-logistics Perform Consultant Qualifi IDA / 65190 Post Open - National 212,000.00 0.00 Canceled 2022-03-01 2022-03-22 2022-04-19 2022-05-03 2022-05-31 2023-05-26 Rehabilitation (125km), Spot ance Enhancement and Sect cation Selection Improvement (300km), and c or Reform onstruction of 50 linear mete r Cross-drainage Structures ( bridges/culverts) AKS/RAAMP/ESMP/CQS/01/2 3 / Consultancy Services for preparation of ESMP for Rural Component C. Institutional D Consultant Qualifi Pending Impleme Roads (Upgrading of Rural Ro IDA / 65190 evelopment, Project Manage Post Limited 120,000.00 0.00 2023-07-12 2023-07-26 2023-08-16 2023-09-11 2024-09-10 cation Selection ntation ads, Spot Improvement, Cros ment and Risk Mitigation s-drainage structure, and Ba cklog Maintenance/Rehabilita tion) for AKS RAAMP AKS/RAAMP/RAP/CQS/02/23 / Consultancy Services for pre Component C. Institutional D paration of RAP for Rural Roa Consultant Qualifi Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 120,000.00 0.00 2023-07-12 2023-07-26 2023-08-16 2023-09-11 2024-09-10 ds (Upgrading of Rural Roads cation Selection ntation ment and Risk Mitigation , Spot Improvement, Cross-dr ainage structure, and Backlo g Maintenance/Rehabilitation ) INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-AKWA IBOM RAAMP-280 Component C. Institutional D 394-CS-INDV / Consultancy S Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Signed 2022-03-07 2022-04-05 2022-03-28 2022-06-14 2022-04-04 2022-07-25 2022-04-18 2023-04-13 ervices for the engagement o ant Selection ment and Risk Mitigation f TA on Security Specialist NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult 466-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 40,000.00 0.00 Canceled 2022-06-08 2022-06-29 2022-07-13 2022-08-03 2023-08-03 ant Selection f Technical Assistant (Gender ment and Risk Mitigation Based Violent) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult 504-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-06-16 2022-07-07 2022-07-21 2022-08-11 2023-08-11 ant Selection f Technical Assistant (Social ment and Risk Mitigation Safeguard) NG-AKWA IBOM RAAMP-230 Component C. Institutional D 522-CS-INDV / Engagement o Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-06-23 2022-07-14 2022-07-28 2022-08-18 2023-08-18 f Technical Assistant (Environ ant Selection ment and Risk Mitigation mental Safeguard) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult 533-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2022-06-30 2022-07-21 2022-08-04 2022-08-25 2023-08-25 ant Selection f Technical Assistant (Procure ment and Risk Mitigation ment) NG-AKWA IBOM RAAMP-230 Component C. Institutional D Individual Consult Under Implement 538-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2022-07-08 2022-05-25 2022-07-29 2022-05-10 2022-08-12 2022-07-12 2022-09-02 2023-09-02 ant Selection ation f Technical Assistant (Infrastr ment and Risk Mitigation ucture) NG-AKWA IBOM RAAMP-280 406-CS-INDV / Consultancy S Component C. Institutional D Individual Consult Under Implement ervices for engagement of Te IDA / 65190 evelopment, Project Manage Post Open 25,000.00 0.00 2022-07-18 2021-06-25 2022-08-22 2021-08-13 2022-08-29 2021-08-16 2022-09-12 2023-09-12 ant Selection ation chnical Assistant (TA) for Dat ment and Risk Mitigation a Entry Specialist (DES) NG-AKWA IBOM RAAMP-280 398-CS-INDV / Consultancy S Component C. Institutional D Individual Consult Under Implement ervices for engagement of TA IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 2022-07-26 2021-06-25 2022-08-02 2021-07-16 2022-08-16 2022-09-06 2023-09-01 ant Selection ation for Geographic Information S ment and Risk Mitigation ystem (GIS) Specialist Page 2 NG-AKWA IBOM RAAMP-313 481-CS-CDS / CONSULTANCY SERVICE FOR UPDATING OF E NVIRONMENTAL AND SOCIAL Component C. Institutional D Under Implement MANAGEMENT PLAN (ESMP) F IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-12 2022-09-15 2022-09-26 2022-10-31 2023-04-29 ation OR 11KM OWOT UTA – NUNG ment and Risk Mitigation OKU EKERE – AFAHA UDOE E YOP – EDEOBOM UTUAT MAR KET JUNCTION ROAD IN NSIT IBOM & IBESIKPO ASUTAN IN AKWA STATE NG-AKWA IBOM RAAMP-313 511-CS-CDS / CONSULTANCY SERVICES FOR UPDATING OF RESETTLEMENT ACTION PLA Component C. Institutional D Under Implement N (RAP) FOR 11KM OWOT UT IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-19 2022-09-15 2022-10-03 2022-11-07 2023-05-06 ation A – NUNG OKU EKERE – AFAH ment and Risk Mitigation A UDOE EYOP – EDEOBOM UT UAT MARKET JUNCTION ROA D IN NSIT IBOM & IBESIKPO A SUTAN IN AKWA STATE NG-AKWA IBOM RAAMP-313 965-CS-CDS / CONSULTANCY SERVICE FOR THE PREPARATI ON OF ENVIRONMENTAL AND Component C. Institutional D Under Implement SOCIAL MANAGEMENT PLAN ( IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-21 2022-09-15 2022-10-05 2022-11-09 2023-05-08 ation ESMP) FOR 11.127KM NSIE – ment and Risk Mitigation UTINE – OTIEKE OFFI – URUTI NG AKS-RAAMP PILOT ROAD I N OKOBO LGA AS PART OF P RIORITY ROADS IN AKWA IBO M. NG-AKWA IBOM RAAMP-313 968-CS-CDS / CONSULTANCY SERVICES FOR THE PREPARA Component C. Institutional D TION OF RESETTLEMENT ACT Under Implement IDA / 65190 evelopment, Project Manage Post Direct Selection Direct - National 30,000.00 0.00 2022-09-26 2022-09-15 2022-10-10 2022-11-14 2023-05-13 ION PLAN (RAP) FOR 11.127K ation ment and Risk Mitigation M NSIE – UTINE – OTIEKE OFF I – URUTING AKS-RAAMP PILO T ROAD IN OKOBO LGA AS PA RT OF PRIORITY ROADS IN AK WA IBOM. NG-AKWA IBOM RAAMP-322 Component C. Institutional D Individual Consult Under Implement 098-CS-INDV / ENGAGEMENT IDA / 65190 evelopment, Project Manage Prior Limited 40,000.00 0.00 2022-10-31 2022-11-01 2022-11-14 2023-02-28 2022-11-28 2023-06-01 2022-12-12 2024-12-01 ant Selection ation OF PROCUREMENT SPECIALIS ment and Risk Mitigation T NG-AKWA IBOM RAAMP-350 642-CS-INDV / Consultancy S ervice for the Preparation of Environmental and Social Ma Component C. Institutional D Individual Consult Pending Impleme nagement Plan (ESMP) and R IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 2023-04-05 2023-04-19 2023-05-03 2023-05-24 2024-05-23 ant Selection ntation AP For 11.127km Nsie – Utine ment and Risk Mitigation – Otieke Offi – Uruting Aks-RA AMP Pilot Road in Okobo LGA s as Part of Priority Roads in Akwa Ibom State. NG-AKWA IBOM RAAMP-347 Component C. Institutional D Individual Consult 731-CS-INDV / Engagement o IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2023-03-15 2023-04-18 2023-04-05 2023-04-19 2023-05-10 2024-05-09 ant Selection f Technical Assistant (Social ment and Risk Mitigation Safeguard) NG-AKWA IBOM RAAMP-347 Component C. Institutional D 741-CS-INDV / Engagement o Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2023-03-26 2023-03-20 2023-04-16 2023-04-30 2023-05-21 2024-05-20 f Technical Assistant (Environ ant Selection ment and Risk Mitigation mental Safeguard) NG-AKWA IBOM RAAMP-347 Component C. Institutional D 738-CS-INDV / Engagement o Individual Consult IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 Canceled 2023-03-20 2023-04-10 2023-04-24 2023-05-15 2024-05-14 f Technical Assistant (Environ ant Selection ment and Risk Mitigation mental Safeguard) AKS/RAAMP/ES/INDV/01/23 / Component C. Institutional D Consultancy Service for the E Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2023-08-01 2023-08-15 2023-08-29 2023-10-03 2024-03-01 ngagement of TA Environme ant Selection ntation ment and Risk Mitigation nt to support SPIU NG-AKWA IBOM RAAMP-350 636-CS-INDV / Consultancy S ervice for updating of Enviro nmental and Social Manage Component C. Institutional D Individual Consult Pending Impleme ment Plan (ESMP) and RAP fo IDA / 65190 evelopment, Project Manage Post Limited 25,000.00 0.00 2023-03-27 2023-04-10 2023-04-24 2023-05-22 2024-05-21 ant Selection ntation r 11km Owot Uta – Nung Oku ment and Risk Mitigation Ekere – Afaha Udoe Eyop – E de obom Utuat Market Juncti on Road in Nsit Ibom & Ibesik po Asutan LGAs in Akwa Stat e AKS/RAAMP/SS/INDV/02/23 / Component C. Institutional D Consultancy Services for Eng Individual Consult Pending Impleme IDA / 65190 evelopment, Project Manage Post Limited 30,000.00 0.00 2023-07-13 2023-07-27 2023-08-10 2023-08-31 2024-01-28 agement of TA Social Safegu ant Selection ntation ment and Risk Mitigation ard to support SPIU Page 3