PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic of Congo, Transport and Connectivity Support Project(P161877) Project Implementation agency: Cellule Infrastructures Date of the Procurement Plan: January 10, 2020 Period covered by this Procurement Plan: January 2020 – June 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables. PROCUREMENT Congo, Democratic Republic of : DRC Transport and Connectivity Support Project PLAN General Information Country: Congo, Democratic Republic of 2020-01-12 Bank’s Approval Date of the Original Procurement Plan: 2024-06-27 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P161877 GPN Date: 2022-11-09 Project Name: DRC Transport and Connectivity Support Project Loan / Credit No: / , IDA / V2970, IDA / 71610 Cellule Infrastructures Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ZR-CI-299889-CW-RFB / MOP Demande d'offres - Construction des ouvrages Transport and digital connec Open - Internationa Single Stage - One E - DTPM Travaux - 27,000,000.0 2024-11-1 de drainage de la piste et tra IDA / V2970 A priori Appel d'offres 0.00 Annulé 2023-01-27 2023-02-01 2023-03-15 2023-04-14 2023-05-19 tivity improvement program l nvelope Droit civil français 0 7 vaux pour amélioration de la (français) sécurité de l'aéroport interna tional de Goma ZR-CI-308539-CW-RFB / MOP - Aménagement et bitumage de la RN2, tronçon Butembo Demande d'offres - Kanya Bayonga (160 km) y Transport and digital connec Open - Internationa Single Stage - One E - DTPM Travaux - 104,000,000. En cours d'e 2026-02-1 compris installation de l'infra IDA / 71610 A priori Appel d'offres 0.00 2022-08-19 2022-09-28 2022-11-04 2023-06-10 2022-11-04 2023-06-16 2022-08-24 2022-11-24 2022-12-16 2023-08-18 2023-01-15 2023-10-18 2023-02-19 tivity improvement program l nvelope Droit civil français 00 xamen 8 structure de fibre optique, ré (français) habilitation ou remplacement des puits d'eau existants et r éhabilitation infrastructures s ociales existantes ZR-CI-299885-CW-RFB / MOP - Aménagement et bitumage de la RN2, tronçon Butembo Demande d'offres - Kanya Bayonga (160 km) y Transport and digital connec Open - Internationa Single Stage - One E - DTPM Travaux - 104,000,000. 2026-01-2 compris installation de l'infra IDA / V2970 A priori Appel d'offres 0.00 Annulé 2022-10-10 2022-10-15 2022-11-26 2022-12-26 2023-01-30 tivity improvement program l nvelope Droit civil français 00 9 structure de fibre optique, ré (français) habilitation ou remplacement des puits d'eau existants et r éhabilitation infrastructures s ociales existantes ZR-CI-299881-CW-RFB / MOP - Aménagement et bitumage de la RN2, tronçon Mbuji- Ma Demande d'offres yi - Kabinda-Mbanga (130 km Transport and digital connec Open - Internationa Single Stage - One E - DTPM Travaux - 101,000,000. 2026-01-2 ) y compris installation infras IDA / V2970 A priori Appel d'offres 0.00 Annulé 2022-10-10 2022-10-15 2022-11-26 2022-12-26 2023-01-30 tivity improvement program l nvelope Droit civil français 00 9 tructure de fibre optique, réh (français) abilitation ou remplacement des puits d'eau existants et r éhabilitation infrastructures s ociales existantes ZR-CI-299876-CW-RFB / MOP - Aménagement et bitumage de la RN2, tronçon Mbuji-May Demande d'offres i - Kabinda (150 km) y compr Transport and digital connec Open - Internationa Single Stage - One E - DTPM Travaux - 125,000,000. 2026-01-2 is installation de l'infrastruct IDA / V2970 A priori Appel d'offres 0.00 Annulé 2022-10-10 2022-10-15 2022-11-26 2022-12-26 2023-01-30 tivity improvement program l nvelope Droit civil français 00 9 ure de fibre optique, réhabilit (français) ation ou remplacement des p uits d'eau existants et réhabi litation des infrastructures so ciales existantes ZR-CI-308535-CW-RFB / MOP - Aménagement et bitumage de la RN2, tronçon Mbuji May Demande d'offres i - Kabinda - Mbanga (280 km Transport and digital connec Open - Internationa Single Stage - One E - DTPM Travaux - 226,000,000. En cours d'e 2026-02-2 ) y compris installation infras IDA / 71610 A priori Appel d'offres 0.00 2022-08-26 2022-09-29 2022-11-11 2023-06-10 2022-11-11 2023-06-16 2022-08-31 2022-11-24 2022-12-23 2023-08-18 2023-01-22 2024-06-10 2023-02-26 tivity improvement program l nvelope Droit civil français 00 xamen 5 tructure de fibre optique, réh (français) abilitation ou remplacement des puits d'eau existants et r éhabilitation infrastructures s ociales existantes GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-380923-GO-RFQ / Four niture des matériels informat Transport and digital connec Single Stage - One E En cours d'ex IDA / 71610 A posteriori Demande de prix Limited 110,000.00 0.00 2023-09-29 2023-09-18 2023-11-24 2024-05-22 iques, d’un drone civil et des tivity improvement program nvelope écution logiciels d’ingénierie pour le Projet PACT ZR-CI-401052-GO-RFQ / MOP - Fourniture du mobilier de b ureau (45 chaises pour salles Transport and digital connec Single Stage - One E En attente d' de réunions, 1 fauteuil et 1 b IDA / 71610 A posteriori Demande de prix Limited 19,600.00 0.00 2024-02-20 2024-04-09 2024-05-09 tivity improvement program nvelope exécution ureau complet (table, tiroirs et retour), 4 armoires et 1 sal on visiteur pour le Coordonn ateur) pou la Cellule Infrastru ctures ZR-CI-427477-GO-RFQ / MOP - Fourniture de cent (100) co Sectoral governance for imp Limited - Internatio Single Stage - One E En attente d' uvercles en fonte pour les re IDA / 71610 A posteriori Demande de prix 100,000.00 0.00 2024-06-22 2024-08-17 2025-02-13 roved connectivity nal nvelope exécution gards de transfo des feux de balisage lumineux à l’aéropo rt de Goma ZR-CI-427482-GO-RFQ / MOP - Fourniture d'un véhicule Fly Sectoral governance for imp Limited - Internatio Single Stage - One E En attente d' IDA / 71610 A posteriori Demande de prix 350,000.00 0.00 2024-06-19 2024-08-14 2025-02-10 co pour lutte contre le péril a roved connectivity nal nvelope exécution viaire ou animalier à l’aéropo rt de Goma ZR-CI-428764-GO-RFQ / MOP - Fourniture d’un drone civil e Transport and digital connec Limited - Internatio Single Stage - One E En attente d' t des logiciels d’ingénierie po IDA / 71610 A posteriori Demande de prix 73,000.00 0.00 2024-06-22 2024-08-17 2025-02-13 tivity improvement program nal nvelope exécution ur le projet PACT (relance de s lots infructueux de la procé dure 380 923) ZR-CI-428765-GO-RFQ / MOP - Acquisition des équipement s pour le déploiement et l'ex Transport and digital connec Single Stage - One E En attente d' IDA / 71610 A posteriori Demande de prix Limited - National 73,230.00 0.00 2024-06-22 2024-08-17 2025-02-13 ploitation de la plateforme d tivity improvement program nvelope exécution e l'application de gestion des plaintes du projet PACT (AGP- PACT) Page 1 ZR-CI-430536-GO-RFB / MOP - Fournitures de matériels inf Sectoral governance for imp Single Stage - Two E En attente d' ormatiques au bénéfice des P IDA / 71610 A posteriori Appel d'offres Open - National 513,800.00 0.00 2024-06-17 2024-06-22 2024-08-03 2024-10-16 2024-11-20 2025-05-19 roved connectivity nvelope exécution arties prenantes au Projet PA CT (PTNTIC, FDSU, SOCOF, M EDD et AAC) NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-151794-NC-DIR / Mise Passation de marc / Monitoring and evaluation A posteriori Direct 50,000.00 0.00 Annulé 2020-10-01 2020-10-06 2020-11-10 2020-11-25 à jour du logiciel TOMPRO pa hé de gré à gré r TOMATE ZR-CI-416585-NC-DIR / MOP - Hébergement, maintenance Sectoral governance for imp Passation de marc En attente d' IDA / 71610 A posteriori Direct - National 3,650.00 0.00 2024-04-04 2024-04-09 2024-04-23 2025-04-23 et mise à jour du site Interne roved connectivity hé de gré à gré exécution t de la CI par IT-GROUP CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-152090-CS-CQS / Etud es techniques et économiqes Sélection fondée s Sectoral governance for imp Open - Internationa et préparation du DAO pour l / A posteriori ur les qualification 100,000.00 0.00 Annulé 2020-02-28 2020-03-20 2020-05-03 2020-06-02 2020-07-07 2020-10-20 roved connectivity l e bitumage de la RN2, tronço s des consultants n Bukavu - Walungu (38 km) ZR-CI-152092-CS-QCBS / Etu des techniques et économiqe Sélection fondée s Sectoral governance for imp Open - Internationa s et préparation du DAO pour / A posteriori ur la qualité et le 425,000.00 0.00 Annulé 2020-02-28 2020-03-20 2020-05-03 2020-05-31 2020-06-30 2020-08-04 2020-09-08 2021-02-07 roved connectivity l le bitumage de la RN2, tronç coût on Mbuji Mayi - Kabinda (159 km) ZR-CI-152088-CS-CQS / Etud es techniques et économiqes Sélection fondée s ainsi que la préparation du D Sectoral governance for imp Open - Internationa / A posteriori ur les qualification 120,000.00 0.00 Annulé 2020-01-30 2020-02-20 2020-04-04 2020-05-04 2020-06-08 2020-11-07 AO pour la réhabilitation et l' roved connectivity l s des consultants entretien de la RN2, tronçon Walungu-Kamituga (142 km) ZR-CI-152139-CS-CQS / Etud es techniques et économiqes Sélection fondée s Sectoral governance for imp Open - Internationa et préparation du DAO pour l / A posteriori ur les qualification 125,000.00 0.00 Annulé 2020-02-28 2020-03-20 2020-05-03 2020-06-02 2020-07-07 2020-10-20 roved connectivity l e bitumage de la RN2, tronço s des consultants n Butembo - Beni (55 km) ZR-CI-152097-CS-QCBS / Etu des techniques et économiqu Sélection fondée s Sectoral governance for imp Open - Internationa es ainsi que la préparation d IDA / V2970 A posteriori ur la qualité et le 300,000.00 660,083.90 Achevé 2020-03-27 2020-04-24 2020-04-17 2020-05-20 2020-05-31 2020-07-24 2020-06-28 2020-11-03 2020-07-28 2020-11-03 2020-09-01 2020-11-03 2020-10-06 2021-02-22 2021-03-07 2021-11-19 roved connectivity l u DAO pour la réhabilitation coût de la RN2, tronçon Beni-Bute mbo-Rutshuru (306 km) ZR-CI-152087-CS-QCBS / Etu Sélection fondée s des de sauvegardes (EIES, P Environmental and social m Open - Internationa IDA / V2970 A posteriori ur la qualité et le 450,000.00 0.00 Annulé 2020-03-27 2020-07-27 2020-04-17 2020-05-31 2020-06-28 2020-07-28 2020-09-01 2020-10-06 2021-03-07 AR et PPA) des travaux de ré easures l coût habilitation du tronçon Beni- Butembo-Rutshuru ZR-CI-151795-CS-CQS / Eval Sélection fondée s uation des risques VBG liés a Environmental and social m IDA / V2970 A posteriori ur les qualification Limited 200,000.00 149,160.00 Achevé 2020-04-12 2020-05-29 2020-04-26 2020-08-07 2020-05-26 2020-09-04 2020-06-30 2020-10-11 2020-09-29 2021-07-26 ux travaux de réhabilitation easures s des consultants de la RN2, tronçon Mbuji May i-Kabinda-Lubao ZR-CI-164527-CS-QCBS / Ela boration des cadres de sauve Sélection fondée s Environmental and social m Open - Internationa gardes (CGES y compris les ri IDA / V2970 A posteriori ur la qualité et le 300,000.00 0.00 Annulé 2020-04-06 2020-04-27 2020-06-10 2020-07-08 2020-08-07 2020-09-11 2020-10-16 2021-03-17 easures l sques VBG, CPR et CPPA) des coût travaux des routes prioritaire s ZR-CI-164534-CS-QCBS / Pré Sélection fondée s paration des documents de s Environmental and social m Open - Internationa IDA / V2970 A posteriori ur la qualité et le 200,000.00 0.00 Annulé 2020-04-10 2020-05-01 2020-06-14 2020-07-12 2020-08-11 2020-09-15 2020-10-20 2021-03-21 auvegardes (EIES et PAR) de easures l coût s travaux aéroportuaires de Beni ZR-CI-164532-CS-CQS / Anal Sélection fondée s yse technique et économiqu Sectoral governance for imp Open - Internationa IDA / V2970 A posteriori ur les qualification 100,000.00 0.00 Annulé 2020-04-30 2020-05-13 2020-05-21 2020-06-23 2020-07-04 2020-08-03 2020-09-07 2021-01-06 e pour l'aménagement de l roved connectivity l s des consultants a RP 1029 Sake-Masisi-Walik ale (287 km) ZR-CI-164603-CS-QCBS / Etu Sélection fondée s des techniques et préparatio Sectoral governance for imp Open - Internationa IDA / V2970 A posteriori ur la qualité et le 350,000.00 0.00 Annulé 2020-03-30 2020-04-20 2020-06-03 2020-07-01 2020-07-31 2020-09-04 2020-10-09 2021-03-10 n du DAO des travaux aéropo roved connectivity l coût rtuaires (Goma et Beni) ZR-CI-164588-CS-CQS / Etud e de faisabilité et assistance Sélection fondée s Sectoral governance for imp technique sur l'intégration et IDA / V2970 A posteriori ur les qualification Limited 200,000.00 0.00 Annulé 2020-04-13 2020-04-27 2020-05-27 2020-07-01 2020-12-28 roved connectivity la gestion de la fibre optique s des consultants dans les routes du projet ZR-CI-173044-CS-QCBS / Au Sélection fondée s Open - Internationa IDA / V2970 Monitoring and evaluation A posteriori 45,000.00 0.00 Signé 2020-08-03 2020-09-10 2020-08-24 2020-10-09 2020-10-07 2021-01-13 2020-11-04 2021-03-17 2020-12-04 2021-05-10 2021-01-08 2021-07-02 2021-02-12 2021-08-25 2022-02-12 dit externe des comptes ur la qualité et le l coût ZR-CI-152089-CS-CQS / Audi Sélection fondée s t organisationnel et techniqu Transport and digital connec Open - Internationa En cours d'exécut IDA / V2970 A posteriori ur les qualification 90,000.00 0.00 2020-10-05 2020-11-13 2020-10-26 2020-12-09 2021-01-08 2021-02-12 2021-04-14 e du Fonds National d'Entreti tivity improvement program l ion s des consultants en Routier (FONER) ZR-CI-190169-CS-LCS / Audit Transport and digital connec Sélection au moin Open - Internationa financier de la RVA, exercice IDA / V2970 A posteriori 60,000.00 39,300.00 Achevé 2020-09-04 2020-08-27 2020-09-25 2020-10-07 2020-11-08 2021-03-09 2020-12-06 2021-04-20 2021-01-05 2021-05-25 2021-02-09 2021-07-02 2021-03-16 2021-10-03 2021-08-13 2022-02-08 tivity improvement program dre coût l s 2019 et 2020 ZR-CI-190170-CS-LCS / audit Transport and digital connec Sélection au moin Open - Internationa financier du FONER, exercice IDA / V2970 A posteriori 60,000.00 67,000.00 Achevé 2020-09-04 2020-09-01 2020-09-25 2020-10-07 2020-11-08 2021-01-20 2020-12-06 2021-03-09 2021-01-05 2021-04-20 2021-02-09 2021-05-25 2021-03-16 2021-08-02 2021-08-13 2022-01-24 tivity improvement program dre coût l s 2019 et 2020 Page 2 ZR-CI-190171-CS-CQS / Etud e d'impact environnemental Sélection fondée s Environmental and social m Open - Internationa et social (EIES) des travaux d IDA / V2970 A posteriori ur les qualification 150,000.00 0.00 Signé 2020-09-04 2021-05-07 2020-09-25 2020-11-08 2022-03-21 2020-12-08 2021-08-17 2021-01-12 2021-09-19 2021-03-14 easures l e réhabilitation du tronçon ro s des consultants utier Beni-Butembo-Rutshuru ZR-CI-230037-CS-CQS / Elab oration du Plan en faveur des Sélection fondée s Environmental and social m Open - Internationa Populations Autochtones (PP IDA / V2970 A posteriori ur les qualification 130,340.00 0.00 Annulé 2021-05-21 2021-06-11 2021-07-25 2021-08-24 2021-09-28 2022-02-25 easures l A) lié aux travaux de bituma s des consultants ge de la RN2, tronçon Beni-B utembo ZR-CI-230401-CS-CQS / Elab oration du Plan d'Action de R Sélection fondée s Environmental and social m éinstallation (PAR) lié aux tra IDA / V2970 A posteriori ur les qualification Limited 103,448.00 0.00 Annulé 2021-05-14 2021-05-28 2021-06-27 2021-08-01 2021-11-29 easures vaux de bitumage de la RN2, s des consultants tronçon Beni-Butembo ZR-CI-230067-CS-CQS / Elab Sélection fondée s Environmental and social m Open - Internationa oration du CPR du PACT (rout IDA / V2970 A posteriori ur les qualification 285,110.00 0.00 Signé 2021-07-12 2021-07-09 2021-08-02 2021-07-15 2021-09-15 2022-09-07 2021-10-15 2021-09-21 2021-11-19 2022-10-15 2022-04-03 easures l es et aéroports) s des consultants ZR-CI-254724-CS-CQS / Actu alisation des études techniqu Sélection fondée s Environmental and social m es pour la construction des o IDA / V2970 A posteriori ur les qualification Limited 178,850.00 0.00 Annulé 2021-09-30 2021-10-18 2021-10-14 2021-11-13 2021-12-18 2022-05-17 easures uvrages de drainage et étude s des consultants économique de l’aéroport de Goma ZR-CI-254725-CS-CQS / Elab oration du schéma de princip Sélection fondée s e de plan masse (SPPM), étu Environmental and social m IDA / V2970 A posteriori ur les qualification Limited 199,650.00 0.00 Annulé 2021-09-30 2021-10-18 2021-10-14 2021-11-13 2021-12-18 2022-05-17 des de construction du mur d easures s des consultants e clôture et études technique s et économiques de l’aéropo rt de Beni-Mavivi ZR-CI-299850-CS-QCBS / MO P - Contrôle et surveillance d es travaux d'aménagement e t bitumage de la RN2, tronço Sélection fondée s Transport and digital connec Open - Internationa n Mbuji-Mayi - Kabinda - Mba IDA / V2970 A priori ur la qualité et le 6,000,000.00 0.00 Signé 2022-07-01 2022-09-30 2022-07-22 2022-11-08 2022-09-04 2023-06-13 2022-10-16 2023-08-11 2022-11-15 2024-02-21 2022-12-20 2024-04-11 2023-01-24 2024-05-20 2026-02-22 tivity improvement program l nga (280 km) y compris insta coût llation infrastructure de fibre optique, réhabilitation des pu its d'eau et infrastructures s ociales existants ZR-CI-299854-CS-QCBS / MO P - Contrôle et surveillance d es travaux d'aménagement e Sélection fondée s t bitumage de la RN2, tronço Transport and digital connec Open - Internationa IDA / V2970 A priori ur la qualité et le 3,000,000.00 0.00 Signé 2022-07-01 2022-09-30 2022-07-22 2022-11-08 2022-09-04 2023-05-09 2022-10-16 2023-07-11 2022-11-15 2024-02-09 2022-12-20 2024-03-22 2023-01-24 2024-04-23 2026-02-22 n Butembo - Kanya Bayonga tivity improvement program l coût (160 km) y compris installati on infrastructure de fibre opti que, réhabilitation des puits d'eau et infrastructures socia les existants ZR-CI-299893-CS-QCBS / MO P - ONG spécialisée pour la p Sélection fondée s Environmental and social m Open - Internationa révention et réponses aux VB IDA / V2970 A priori ur la qualité et le 3,500,000.00 0.00 Signé 2022-07-01 2023-01-25 2022-07-22 2023-02-09 2022-09-04 2023-06-28 2022-10-16 2023-08-07 2022-11-15 2023-11-15 2022-12-20 2024-03-22 2023-01-24 2024-04-24 2026-02-22 easures l G/EAS/HS sur l'axe Mbuji-ma coût yi - Kabinda - Mbanga ZR-CI-299905-CS-QCBS / MO P - Suivi des normes E&S y c Sélection fondée s Environmental and social m Open - Internationa En cours d'exame ompris VBG/EAS/HS par une t IDA / V2970 A priori ur la qualité et le 1,500,000.00 0.00 2022-07-01 2024-02-09 2022-07-22 2024-03-12 2022-09-04 2022-10-16 2022-11-15 2022-12-20 2023-01-24 2026-02-22 easures l n ierce partie sur la route Bute coût mbo - Kanya Bayonga ZR-CI-299910-CS-QCBS / MO P - Contrôle et surveillance d Sélection fondée s es travaux de construction d Transport and digital connec Open - Internationa IDA / V2970 A priori ur la qualité et le 1,300,000.00 0.00 Annulé 2022-10-07 2022-10-28 2022-12-11 2023-01-22 2023-02-21 2023-03-28 2023-05-02 2024-11-30 es ouvrages de drainage de l tivity improvement program l coût a piste et de travaux pour a mélioration de la sécurité de l'aéroport international de G oma ZR-CI-299914-CS-CQS / MOP - Actualisation des études tec Sélection fondée s Transport and digital connec hniques de drainage de la pis IDA / V2970 A posteriori ur les qualification Limited 200,000.00 0.00 Signé 2022-07-01 2022-10-04 2022-07-15 2023-02-03 2022-08-14 2023-04-14 2022-09-18 2023-06-02 2023-01-18 tivity improvement program te et des travaux pour améli s des consultants oration de la sécurité de l'aér oport de Goma ZR-CI-300125-CS-LCS / MOP Sectoral governance for imp Sélection au moin Open - Internationa En cours d'exécut - Audit financier externe du F IDA / V2970 A posteriori 135,000.00 0.00 2022-09-09 2022-12-23 2022-09-30 2023-02-06 2022-11-13 2023-09-26 2022-12-11 2024-03-19 2023-01-10 2024-03-19 2023-02-14 2024-04-09 2023-03-21 2025-08-02 roved connectivity dre coût l ion ONER, exercices 2022, 2023 et 2024 ZR-CI-300231-CS-LCS / MOP Sectoral governance for imp Sélection au moin Open - Internationa - Audit financier externe de l IDA / V2970 A posteriori 135,000.00 0.00 Signé 2022-09-09 2022-12-23 2022-09-30 2023-02-06 2022-11-13 2023-04-12 2022-12-11 2023-05-30 2023-01-10 2023-08-11 2023-02-14 2023-08-25 2023-03-21 2025-08-02 roved connectivity dre coût l a RVA, exercices 2022, 2023 et 2024 ZR-CI-300232-CS-LCS / MOP - Audit financier et opération Sectoral governance for imp Sélection au moin Open - Internationa En cours d'exécut IDA / V2970 A posteriori 135,000.00 0.00 2022-09-09 2023-01-25 2022-09-30 2023-02-06 2022-11-13 2022-12-11 2023-01-10 2023-02-14 2023-03-21 2025-08-02 nel externe de l'ARPTC, exerc roved connectivity dre coût l ion ice 2022, 2023 et 2024 ZR-CI-300233-CS-LCS / MOP Sectoral governance for imp Sélection au moin Open - Internationa En cours d'exécut - Audit de la SOCOF exercice IDA / V2970 A posteriori 135,000.00 0.00 2022-09-09 2023-01-25 2022-09-30 2023-02-06 2022-11-13 2023-05-22 2022-12-11 2023-01-10 2023-02-14 2023-03-21 2025-08-02 roved connectivity dre coût l ion 2022, 2023 et 2024 ZR-CI-300235-CS-CQS / MOP Sélection fondée s - Assistance technique à la m Environmental and social m Open - Internationa En cours d'exécut IDA / V2970 A posteriori ur les qualification 60,000.00 0.00 2022-10-03 2023-05-15 2022-10-24 2024-02-28 2022-12-07 2023-01-06 2023-02-10 2023-07-12 ise en place d'une plate-form easures l ion s des consultants e de gestion des plaintes ZR-CI-190167-CS-QCBS / Ela boration des cadres de sauve Sélection fondée s Environmental and social m Open - Internationa gardes (CGES y compris les ri IDA / V2970 A posteriori ur la qualité et le 350,000.00 0.00 Annulé 2020-09-11 2020-11-09 2020-10-02 2020-11-15 2020-12-13 2021-01-12 2021-02-16 2021-03-23 2021-07-23 easures l sques VBG, CPR et CPPA) du coût PACT (routes et aéroports) ZR-CI-205399-CS-CQS / Elab oration du Plan d'Action de R Sélection fondée s éinstallation (PAR) et du Plan Environmental and social m Open - Internationa IDA / V2970 A posteriori ur les qualification 183,000.00 0.00 Annulé 2020-11-27 2020-12-21 2020-12-18 2021-01-31 2021-03-02 2021-04-06 2021-08-04 en faveur des Populations Au easures l s des consultants tochtones (PPA) liés aux trav aux de bitumage de la RN2, t ronçon Beni-Butembo Page 3 ZR-CI-230619-CS-CQS / Actu Sélection fondée s alisation du PAR des travaux Environmental and social m IDA / V2970 A posteriori ur les qualification Limited 110,000.00 0.00 Annulé 2021-05-14 2021-06-27 2021-05-28 2021-06-27 2021-08-01 2021-08-11 de réhabilitation de la RN2, tr easures s des consultants onçon Mbuji Mayi-Kabinda ZR-CI-326290-CS-QCBS / ON G chargée de l'engagement c Sélection fondée s Environmental and social m Open - Internationa ommunautaire le long de la r IDA / 71610 A priori ur la qualité et le 2,000,000.00 0.00 Annulé 2022-11-25 2022-12-16 2023-01-29 2023-03-12 2023-04-11 2023-05-16 2023-06-20 2026-06-19 easures l oute nationale n°2, tronçon coût Mbuji Mayi-Kabinda-Mbanga ZR-CI-326292-CS-QCBS / ON G chargée de l'engagement c Sélection fondée s Environmental and social m Open - Internationa ommunautaire le long de la r IDA / 71610 A priori ur la qualité et le 1,000,000.00 0.00 Annulé 2022-11-25 2022-12-16 2023-01-29 2023-03-12 2023-04-11 2023-05-16 2023-06-20 2026-06-19 easures l oute nationale n°2, tronçon K coût anya Bayonga-Butembo ZR-CI-332359-CS-QCBS / MO Sélection fondée s P - ONG spécialisée pour la p Environmental and social m Open - Internationa IDA / 71610 A priori ur la qualité et le 1,500,000.00 0.00 Signé 2022-12-23 2023-01-25 2023-01-13 2023-02-09 2023-02-26 2023-06-27 2023-04-09 2023-08-07 2023-05-09 2023-11-22 2023-06-13 2024-03-22 2023-07-18 2024-04-23 2026-07-18 révention et réponses aux VB easures l coût G/EAS/HS sur l'axe Kanya Ba yonga-Butembo ZR-CI-332360-CS-QCBS / MO P - Suivi des normes E&S y c Sélection fondée s Environmental and social m Open - Internationa En cours d'exame ompris VBG/EAS/HS par une t IDA / 71610 A priori ur la qualité et le 3,500,000.00 0.00 2022-12-30 2024-02-09 2023-01-20 2024-03-14 2023-03-05 2023-04-16 2023-05-16 2023-06-20 2023-07-25 2026-08-23 easures l n ierce partie sur la route Mbuj coût i Mayi-Kabinda-Mbanga ZR-CI-300234-CS-QCBS / MO Sélection fondée s Sectoral governance for imp Open - Internationa En cours d'exécut P - Audit des comptes du Proj IDA / 71610 A posteriori ur la qualité et le 135,000.00 0.00 2023-07-14 2023-10-16 2023-08-04 2024-02-21 2023-09-17 2023-10-29 2023-11-28 2024-01-02 2024-02-06 2026-06-20 roved connectivity l ion et PACT, exercices 2023, 202 coût 4 et 2025 ZR-CI-368168-CS-QCBS / MO P - Etudes techniques et éco Sélection fondée s nomiques d’aménagement et Transport and digital connec Open - Internationa En cours d'exécut IDA / 71610 A posteriori ur la qualité et le 865,100.00 0.00 2023-07-07 2023-07-11 2023-07-28 2023-09-27 2023-09-10 2023-10-22 2023-11-21 2023-12-26 2024-01-30 2024-10-30 de bitumage de la RN2, tronç tivity improvement program l ion coût on Bukavu – Kasongo (444 k m), dans le cadre de la prépa ration de la phase 2 du PACT ZR-CI-368174-CS-QCBS / MO P - Audit de Sécurité Routière des travaux d'aménagement et bitumage de la RN2 Mbuji Sélection fondée s Transport and digital connec Open - Internationa En attente d'exéc mayi-Mbanga et Butembo – K IDA / 71610 A posteriori ur la qualité et le 500,000.00 0.00 2023-07-28 2023-08-18 2023-10-01 2023-11-12 2023-12-12 2024-01-16 2024-02-20 2027-04-21 tivity improvement program l ution anya Bayonga (Projets d’Exé coût cution, travaux à mi-parcours et à la fin des chantiers) et d es études techniques de la R N2 tronçon Bukavu – Kasong o ZR-CI-370995-CS-CQS / MOP - Etude d’Impact Environnem ental et Social/ Plan de Gesti Sélection fondée s on Environnementale et Soci Environmental and social m IDA / 71610 A posteriori ur les qualification Open - National 100,253.00 0.00 Annulé 2023-07-17 2023-08-14 2023-08-07 2023-09-11 2023-10-02 2023-11-06 2024-02-19 ale (EIES/PGES) des ouvrages easures s des consultants connexes des travaux d’amé nagement et de bitumage de la RN2, tronçon Mbuji-Mayi - Kabinda - Mbanga ZR-CI-370998-CS-CQS / MOP - Etude d’Impact Environnem ental et Social/ Plan de Gesti Sélection fondée s on Environnementale et Soci Environmental and social m En cours d'exame IDA / 71610 A posteriori ur les qualification Open - National 88,100.00 0.00 2023-07-17 2023-07-26 2023-08-07 2023-09-11 2023-10-02 2023-11-06 2024-02-19 ale (EIES/PGES) des ouvrages easures n s des consultants connexes des travaux d’amé nagement et de bitumage de la RN2, tronçon Kanya Bayon ga - Butembo ZR-CI-400975-CS-QCBS / MO P - Etudes techniques et éco Sélection fondée s Transport and digital connec Open - Internationa nomiques d'aménagement et IDA / 71610 A priori ur la qualité et le 3,300,000.00 0.00 Annulé 2024-02-20 2024-03-12 2024-04-25 2024-06-07 2024-07-07 2024-08-25 2024-10-06 2025-08-06 tivity improvement program l de bitumage de la RN1, tronç coût on Mbuji Mayi - Nguba (933 k m) ZR-CI-406481-CS-CQS / MOP - Assistance technique pour l Sélection fondée s a mise en place des normes t Sectoral governance for imp Open - Internationa En cours d'exame IDA / 71610 A posteriori ur les qualification 100,000.00 0.00 2024-02-16 2024-04-23 2024-03-08 2024-04-21 2024-05-21 2024-06-18 2024-12-15 echniques et des règles d'ing roved connectivity l n s des consultants énierie et d'esthétique relativ es à la pose de réseaux en fi bre optique en RDC ZR-CI-406475-CS-CQS / MOP - Assistance technique relativ Sélection fondée s e à la conception et l'implém Sectoral governance for imp Open - Internationa En cours d'exame IDA / 71610 A posteriori ur les qualification 250,000.00 0.00 2024-02-16 2024-04-23 2024-03-08 2024-04-14 2024-05-14 2024-06-11 2024-12-08 entation des instruments de l roved connectivity l n s des consultants a régulation des marchés de gros et de détail des services de télécommunication ZR-CI-406610-CS-QCBS / MO Sélection fondée s P - Audit organisationnel, tec Sectoral governance for imp En attente d'exéc IDA / 71610 A posteriori ur la qualité et le 300,000.00 0.00 2024-02-13 2024-02-27 2024-04-04 2024-05-17 2024-06-16 2024-07-21 2024-08-25 2024-11-25 hnique et des compétences d roved connectivity ution coût e la Cellule Infrastructures ZR-CI-416452-CS-CQS / MOP - Evaluation des risques VBG y compris EAS/HS et de la ca Sélection fondée s pacité de réaction/réponse d Environmental and social m En cours d'exame IDA / 71610 A posteriori ur les qualification Open - National 116,030.00 0.00 2024-04-02 2024-05-22 2024-04-23 2024-06-06 2024-07-06 2024-08-10 2024-12-03 es structures de prise en cha easures n s des consultants rge des survivantes en faveu r des communautés riveraine s de la RN2, tronçon Mbanga- Penemwanga ZR-CI-416570-CS-CQS / MOP - Actualisation des EIES des t Sélection fondée s ravaux de bitumage de la RN Environmental and social m En cours d'exame IDA / 71610 A posteriori ur les qualification Open - National 146,995.00 0.00 2024-04-09 2024-05-23 2024-04-30 2024-06-13 2024-07-13 2024-08-17 2024-11-30 2, tronçon Mbanga-Penemwa easures n s des consultants nga, dans le cadre de la prép aration de la phase 2 du PAC T ZR-CI-416576-CS-CQS / MOP - Actualisation du Cadre de G Sélection fondée s Environmental and social m En cours d'exame estion Environnementale et S IDA / 71610 A posteriori ur les qualification Open - National 209,475.00 0.00 2024-04-09 2024-06-19 2024-04-30 2024-06-13 2024-07-13 2024-08-17 2024-12-15 easures n ociale (CGES), dans le cadre s des consultants de la préparation de la phase 2 du PACT Page 4 ZR-CI-427107-CS-QCBS / MO P - Consultant firme chargé d e l'évaluation des capacités d Sélection fondée s Sectoral governance for imp Open - Internationa En cours d'exame e gestion de la sécurité routi IDA / 71610 A posteriori ur la qualité et le 300,000.00 0.00 2024-06-17 2024-06-17 2024-07-08 2024-08-21 2024-09-18 2024-10-18 2024-11-22 2024-12-27 2025-12-27 roved connectivity l n ère, élaboration d'une straté coût gie nationale de sécurité rout ière et d'un plan d'action con nexe pour sa mise en œuvre ZR-CI-427109-CS-QCBS / MO P - Consultant firme chargé d e la conception et mise en pl Sélection fondée s ace d'une base des données Sectoral governance for imp Open - Internationa En cours d'exame IDA / 71610 A posteriori ur la qualité et le 550,000.00 0.00 2024-06-17 2024-06-17 2024-07-08 2024-08-21 2024-09-18 2024-10-18 2024-11-22 2024-12-27 2025-12-27 nationale sur la sécurité routi roved connectivity l n coût ère et les accidents et Forma t° des cadres et agents de l'a dministration du MTIP, MTVC, Ministère de l'Intérieur et Sé curité ZR-CI-427110-CS-CQS / MOP - Consultant Firme chargé de Sélection fondée s l'élaboration d'une stratégie Sectoral governance for imp Open - Internationa En attente d'exéc IDA / 71610 A posteriori ur les qualification 250,000.00 0.00 2024-06-17 2024-07-08 2024-08-21 2024-09-20 2024-10-25 2025-04-23 nationale de contrôle de la c roved connectivity l ution s des consultants harge à l'essieu avec un plan de mise en œuvre et un prog ramme pilote ZR-CI-427111-CS-QCBS / MO P - Consultant Firme chargé de la réalisation de l'étude d Sélection fondée s e faisabilité des projets de Pa Sectoral governance for imp Open - Internationa En cours d'exame IDA / 71610 A posteriori ur la qualité et le 400,000.00 0.00 2024-06-17 2024-06-17 2024-07-08 2024-08-21 2024-09-18 2024-10-18 2024-11-22 2024-12-27 2025-12-27 rtenariat Public-Privé sur la g roved connectivity l n coût est° du pesage routier sur les routes nationales de la RDC et les routes urbaines de vill es de Kin, L'shi, Klz et Mtd ZR-CI-427112-CS-CQS / MOP - Consultant Firme chargé de la réalisation de l'étude de fa Sélection fondée s Sectoral governance for imp Open - Internationa En cours d'exame isabilité des projets de Parte IDA / 71610 A posteriori ur les qualification 100,050.00 0.00 2024-06-17 2024-06-17 2024-07-08 2024-08-21 2024-09-20 2024-10-25 2025-04-23 roved connectivity l n nariat Public-Privé portant s s des consultants ur l'organisation et la collect e de la redevance sur la char ge à l'essieu en RD Congo ZR-CI-427114-CS-QCBS / MO P- Consultant firme chargé d e l'Assistance Technique pou Sélection fondée s r la création d’une base de d Transport and digital connec Open - Internationa En attente d'exéc IDA / 71610 A posteriori ur la qualité et le 600,000.00 0.00 2024-06-17 2024-07-08 2024-08-21 2024-09-18 2024-10-18 2024-11-22 2024-12-27 2025-12-27 onnées d’inventaire des actif tivity improvement program l ution coût s routiers et d’équipements p our des enquêtes routières m odernisées et de sécurités ro utières en RDC ZR-CI-427117-CS-CQS / MOP Sélection fondée s - Assistance technique pour l Sectoral governance for imp Open - Internationa En attente d'exéc IDA / 71610 A posteriori ur les qualification 100,000.00 0.00 2024-06-17 2024-07-08 2024-08-21 2024-09-20 2024-10-25 2025-04-23 a mise en place d’un observa roved connectivity l ution s des consultants toire des marchés de téléco mmunications ZR-CI-427118-CS-QCBS / MO P - Consultant Firme chargé Sélection fondée s de l'étude sur la mise en œu Sectoral governance for imp Open - Internationa En attente d'exéc IDA / 71610 A posteriori ur la qualité et le 486,000.00 0.00 2024-06-17 2024-07-08 2024-08-21 2024-09-18 2024-10-18 2024-11-22 2024-12-27 2025-12-27 vre du plan stratégique d’acc roved connectivity l ution coût ès aux services universels et l’opérationnalisation du FDSU ZR-CI-427279-CS-CQS / MOP - Elaboration du Cadre légal Sélection fondée s Sectoral governance for imp En attente d'exéc pour la gestion des déchets d IDA / 71610 A posteriori ur les qualification Open - National 100,000.00 0.00 2024-06-17 2024-07-08 2024-08-21 2024-09-20 2024-10-25 2025-04-23 roved connectivity ution es équipements électriques e s des consultants t électroniques en RDC ZR-CI-427461-CS-CQS / MOP - Assistance technique pour l Sélection fondée s Sectoral governance for imp Open - Internationa En attente d'exéc a mise en place des outils de IDA / 71610 A posteriori ur les qualification 210,000.00 0.00 2024-06-17 2024-07-08 2024-08-21 2024-09-20 2024-10-25 2025-04-23 roved connectivity l ution gouvernance institutionnelle s des consultants et du développement de la S OCOF ZR-CI-427465-CS-QCBS / MO P - Consultant Firme Conseill er en transaction dans le cad Sélection fondée s re du Contrat de Partenariat Sectoral governance for imp Open - Internationa En attente d'exéc IDA / 71610 A posteriori ur la qualité et le 400,000.00 0.00 2024-06-17 2024-07-08 2024-08-21 2024-09-18 2024-10-18 2024-11-22 2024-12-27 2025-12-27 Public-Privé portant sur le fou roved connectivity l ution coût rreau de fibre optique des tro nçons routiers Mbuji Mayi - K abinda - Mbanga - Bukavu et Butembo - Kanya Bayonga ZR-CI-427468-CS-LCS / MOP Sectoral governance for imp Sélection au moin Open - Internationa En cours d'exame - Audit organisationnel et tec IDA / 71610 A posteriori 198,000.00 0.00 2024-06-17 2024-06-17 2024-07-08 2024-08-21 2024-09-18 2024-10-18 2024-11-22 2024-12-27 2025-06-25 roved connectivity dre coût l n hnique de la Régie des Voies Aériennes ZR-CI-428322-CS-CQS / MOP - Actualisation du Plan d'Acti on de Réinstallation (PAR) de Sélection fondée s s travaux de bitumage de la r Environmental and social m En attente d'exéc IDA / 71610 A posteriori ur les qualification Open - National 144,360.00 0.00 2024-06-17 2024-07-08 2024-08-21 2024-09-20 2024-10-25 2025-04-23 oute nationale numéro 2 RN2 easures ution s des consultants ), tronçon Mbanga - Penemw anga (2 voies x 2), dans les p rovinces du Lomami et du Ma niema (préparation PACT 2) ZR-CI-416572-CS-CQS / MOP - Prestation de service d'un c Sélection fondée s onsultant firme chargé de l'a Environmental and social m En cours d'exame IDA / 71610 A posteriori ur les qualification Open - National 103,870.00 0.00 2024-04-09 2024-05-30 2024-04-30 2024-06-13 2024-07-13 2024-08-17 2025-01-14 ctualisation du Cadre de Polit easures n s des consultants ique de Réinstallation (CPR), dans le cadre de la préparati on de la phase 2 du PACT ZR-CI-429204-CS-CQS / MOP - Actualisation du Plan de Ge stion de la Biodiversité (PGB) Sélection fondée s Environmental and social m Open - Internationa En attente d'exéc , tronçons Mbuji Mayi - Kabin IDA / 71610 A posteriori ur les qualification 531,669.00 0.00 2024-06-17 2024-07-08 2024-08-21 2024-09-20 2024-10-25 2025-04-23 easures l ution da et Kabinda – Mbanga dan s des consultants s les provinces du Kasaï Orie ntal et du Lomami et Kanyab ayonga ZR-CI-432946-CS-CQS / MOP - Prestations de cabinet de c Sélection fondée s onseil en transactions pour l’ Sectoral governance for imp Limited - Internatio En attente d'exéc IDA / 71610 A posteriori ur les qualification 300,000.00 0.00 2024-07-10 2024-07-24 2024-08-23 2024-09-27 2025-03-26 extension de la dorsale de fib roved connectivity nal ution s des consultants re optique en République Dé mocratique du Congo (RDC) Page 5 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-CI-151569-CS-INDV / Mis e à jour du manuel de procéd Transport and digital connec / A posteriori Individuel Limited 35,000.00 0.00 Annulé 2020-03-01 2020-03-06 2020-03-27 2020-05-01 2020-10-28 ures administratives, compta tivity improvement program bles, financières, et de pass ation des marchés ZR-CI-152128-CS-INDV / Mis e à jour du manuel d'exécuti / Monitoring and evaluation A posteriori Individuel Limited 35,000.00 0.00 Signé 2020-04-01 2020-11-23 2020-04-06 2021-03-18 2020-04-27 2021-07-13 2020-06-01 2023-03-22 2020-08-31 on du projet ZR-CI-164594-CS-CDS / Actu alisation des études techniqu Sélection de cons es et économiques ainsi que Sectoral governance for imp IDA / V2970 A posteriori ultants par entent Direct 200,000.00 382,540.00 Achevé 2020-03-30 2020-05-20 2020-04-09 2020-07-29 2020-06-13 2020-09-26 2020-09-13 2021-10-15 du DAO pour la réhabilitation roved connectivity e directe de la RN2, tronçon Mbuji May i - Kabinda - Lubao (332 km) par AIC PROGETTI ZR-CI-164593-CS-INDV / Ana Environmental and social m lyse sécuritaire du projet et é IDA / V2970 A posteriori Individuel Open 200,000.00 0.00 Annulé 2020-04-27 2020-06-15 2020-07-06 2020-08-10 2021-02-06 easures laboration du plan de gestion de la sécurité ZR-CI-164590-CS-INDV / Act ualisation du PPA des travau Environmental and social m x de rehabilitation de la RN2, IDA / V2970 A posteriori Individuel Direct 50,000.00 0.00 Annulé 2020-05-26 2020-06-18 2020-06-05 2020-06-26 2020-07-31 2020-10-29 easures tronçon Mbuji Mayi-Kabinda-L ubao par Bruno BOLEKYMO ZR-CI-164605-CS-INDV / Act ualisation du PAR des travau Environmental and social m x de réhabilitation de la RN2, IDA / V2970 A posteriori Individuel Direct 100,000.00 0.00 Annulé 2020-05-26 2020-08-10 2020-06-05 2020-06-26 2020-07-31 2020-10-29 easures tronçon Mbuji Mayi-Kabinda-L ubao par Mamadou DIEDHIO U ZR-CI-164585-CS-INDV / Act ualisation des EIES des trava Environmental and social m ux de réhabilitation de la RN IDA / V2970 A posteriori Individuel Direct 120,000.00 143,236.00 Signé 2020-05-26 2020-06-18 2020-06-05 2020-07-29 2020-06-26 2020-08-20 2020-07-31 2020-09-22 2020-10-29 easures 2, tronçon Mbuji Mayi-Kabind a-Lubao par Adama ZARE ZR-CI-173049-CS-INDV / Che En cours d'exécut f de Section Routes au sein d IDA / V2970 Monitoring and evaluation A posteriori Individuel Open 60,000.00 0.00 2020-05-26 2023-04-26 2020-07-14 2020-08-04 2020-09-08 2021-09-08 ion e la Cellule Infrastructures ZR-CI-181740-CS-INDV / Pre stations de service au poste IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 55,825.00 183,425.00 Signé 2020-06-26 2020-07-14 2020-06-28 2020-07-14 2020-06-29 2020-09-30 2020-07-01 2020-12-19 2021-01-31 de Coordonnateur de la Cellu le Infrastructures par Théoph ile NTELA LUNGUMBA ZR-CI-181736-CS-INDV / Pre stations de service au poste de Chef de Section Administr IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 35,000.00 55,000.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-29 2020-07-01 2020-11-22 2021-01-31 ation et Finances au sein de l a Cellule Infrastructures par Pierre BUNDOKI NDONGALA ZR-CI-181744-CS-INDV / Pre stations de service au poste IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 18,900.00 18,900.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-26 2021-01-31 de Comptable au sein de la C ellule Infrastructures par Jean -Jacques MAKUNZA ZR-CI-181742-CS-INDV / Pre stations de service au poste de Gestionnaire de Projet Tra IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 24,920.00 39,160.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-22 2021-01-31 nsport au sein de la Cellule In frastructures par Théodore N GAMBILA VAN MAZIREL ZR-CI-181732-CS-INDV / Pre stations de service au poste de Responsable de Passation IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 31,990.00 50,270.00 Signé 2020-06-26 2020-07-30 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-22 2021-01-31 des Marchés de la Cellule Infr astructures par Damien MAN YAMALA MAKANDAKELE ZR-CI-181739-CS-INDV / Pre stations de service au poste de Chargé de Passation des IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 24,570.00 38,610.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-10-30 2020-07-01 2020-11-22 2021-01-31 Marchés au sein de la Cellule Infrastructures par Godefroid KASENDE MESO ZR-CI-181735-CS-INDV / Pre stations de service au poste Environmental and social m de Spécialiste en sauvegarde IDA / V2970 A posteriori Individuel Direct 28,560.00 95,900.00 Achevé 2020-06-26 2020-08-03 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-22 2021-01-31 2021-08-29 easures s environnementales au sein de la Cellule Infrastructures p ar Aimé KABAMBA ZR-CI-181731-CS-INDV / Pre stations de service au poste Environmental and social m de Spécialiste en sauvegarde IDA / V2970 A posteriori Individuel Direct 23,450.00 36,850.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-22 2021-01-31 easures s sociales au sein de la Cellul e Infrastructures par Félix TS HIABA ZR-CI-181737-CS-INDV / Pre stations de service au poste d'Expert Senior SIG au sein d IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 28,560.00 44,880.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-22 2021-01-31 e la Cellule Infrastructures pa r Patrick MBUY'A SAKAFUKU ZR-CI-181734-CS-INDV / Pre stations de service au poste Sectoral governance for imp IDA / V2970 A posteriori Individuel Direct 15,120.00 23,760.00 Signé 2020-06-26 2020-07-09 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-26 2021-01-31 d'Assistante à la Coordinatio roved connectivity n de la Cellule Infrastructures par Marianne IKOBO ZR-CI-181743-CS-INDV / Pre stations de service au poste IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 8,540.00 13,420.00 Signé 2020-06-26 2020-09-29 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-22 2021-01-31 de Chauffeur à la Coordinatio n de la Cellule Infrastructures par Noël MATUNGULU ZR-CI-181741-CS-INDV / Pre stations de service au poste IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 12,390.00 19,470.00 Signé 2020-06-26 2020-07-10 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-26 2021-01-31 d'Assistante au projet au sein de la Cellule Infrastructures p ar Mélanie KAYIBA Page 6 ZR-CI-181738-CS-INDV / Pre stations de service au poste IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 8,260.00 12,980.00 Signé 2020-06-26 2020-08-20 2020-06-28 2020-07-09 2020-06-29 2020-09-30 2020-07-01 2020-11-22 2021-01-31 de Chauffeur au sein de la Ce llule Infrastructures par Jean- Pierre KILONGOKELE ZR-CI-182253-CS-INDV / Pre stations de service au poste d'Ingénieur Assistant 1 à la S IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 17,500.00 27,500.00 Signé 2020-06-29 2020-08-04 2020-07-01 2020-08-24 2020-07-02 2020-09-30 2020-07-04 2020-11-22 2021-01-31 ection Routes de la Cellule In frastructures par Cyrille KIBU LU ZR-CI-182250-CS-INDV / Pre stations de service au poste d'Ingénieur Assistant 2 à la S IDA / V2970 Monitoring and evaluation A posteriori Individuel Direct 17,500.00 27,500.00 Signé 2020-06-29 2020-08-04 2020-07-01 2020-08-24 2020-07-02 2020-09-30 2020-07-04 2020-11-22 2021-01-31 ection Routes de la Cellule In frastructures par Ange MUSH IGO ZR-CI-186421-CS-INDV / App uis ponctuels à l'évaluation d IDA / V2970 Monitoring and evaluation A posteriori Individuel Limited 42,000.00 0.00 Annulé 2020-08-14 2020-09-01 2020-08-19 2020-09-09 2020-10-14 2021-04-12 es offres des marchés prévus au PPA du PACT ZR-CI-152119-CS-INDV / Etu de de marchés du projet et p IDA / V2970 Monitoring and evaluation A posteriori Individuel Limited 75,000.00 0.00 Annulé 2020-06-15 2020-06-20 2020-07-11 2020-08-15 2020-10-15 réparation de la stratégie de passation de marchés ZR-CI-151728-CS-INDV / Ela Environmental and social m boration des procédures de g IDA / V2970 A posteriori Individuel Open 150,000.00 0.00 Annulé 2020-04-27 2020-06-15 2020-07-06 2020-08-10 2020-11-08 easures estion de la main d'oeuvre ZR-CI-215461-CS-INDV / Pre stations de services de Comp Sectoral governance for imp En cours d'exécut IDA / V2970 A posteriori Individuel Open 42,000.00 0.00 2021-01-29 2021-02-15 2021-03-22 2021-03-26 2021-04-12 2022-04-12 table du projet PACT au sein roved connectivity ion de la Cellule Infrastructures ZR-CI-230075-CS-INDV / Exp ert en fibre optique et dévelo Sectoral governance for imp IDA / V2970 A posteriori Individuel Open 48,000.00 0.00 Annulé 2021-05-07 2021-06-25 2021-07-16 2021-08-20 2022-08-20 ppement numérique au sein roved connectivity de la Cellule Infrastructures ZR-CI-230031-CS-CDS / Actu alisation des EIES des travau Sélection de cons Environmental and social m x de réhabilitation de la RN2, IDA / V2970 A posteriori ultants par entent Direct 227,490.00 216,171.00 Signé 2021-05-07 2021-04-16 2021-05-17 2021-05-25 2021-07-21 2021-08-05 2021-11-18 easures tronçon Mbuji Mayi-Kabinda-L e directe ubao par la firme SERF BURKI NA ZR-CI-241060-CS-INDV / Pre stations de services au poste Environmental and social m d'Expert Violences Basées su IDA / V2970 A posteriori Individuel Direct 38,500.00 28,000.00 Signé 2021-06-28 2021-08-19 2021-07-04 2022-03-14 2021-07-07 2022-03-14 2021-07-31 2022-03-18 2022-05-31 easures r le Genre au sein de la Cellul e Infrastructures par Madam e Liliane MUSAU KAZADI ZR-CI-241107-CS-INDV / Ela boration du Cadre de planific Environmental and social m IDA / V2970 A posteriori Individuel Limited 195,241.00 0.00 Signé 2021-07-14 2021-06-03 2021-07-19 2021-06-21 2021-08-09 2021-09-14 2021-09-13 2023-03-10 2022-01-26 ation en faveur des Populatio easures ns Autochtones (CPPA) du Pr ojet ZR-CI-241053-CS-INDV / Ela boration du Cadre de gestion Environmental and social m IDA / V2970 A priori Individuel Limited 304,250.00 0.00 Annulé 2021-07-12 2021-07-17 2021-08-07 2021-09-11 2022-02-08 environnementale et sociale easures (CGES) du Projet ZR-CI-254730-CS-INDV / Pre stations de service au poste Sectoral governance for imp d'Expert en Sauvegarde Envi IDA / V2970 A posteriori Individuel Open 31,500.00 25,000.00 Signé 2021-09-30 2021-10-12 2021-11-09 2021-12-17 2021-11-23 2021-12-21 2021-12-02 2022-01-16 2022-05-31 roved connectivity ronnementale et Responsabl e de l’Unité Environnemental e et Sociale de la CI ZR-CI-254728-CS-INDV / Con sultant individuel Ingénieur r Transport and digital connec IDA / V2970 A posteriori Individuel Direct 30,000.00 0.00 Signé 2021-09-30 2021-10-19 2021-10-10 2022-09-01 2021-10-24 2021-10-29 2021-11-16 2021-10-18 2022-04-15 outier en appui à l’équipe du tivity improvement program projet PACT, par Billy TSHIBA MBE ZR-CI-258766-CS-INDV / Pre station de service d’élaborati on du cadre de Gestion Envir Transport and digital connec IDA / V2970 A posteriori Individuel Direct 54,033.00 0.00 Achevé 2021-10-19 2021-10-22 2021-10-20 2021-10-25 2021-10-22 2021-11-03 2021-10-25 2021-11-25 2021-11-24 2022-05-31 onnementale et Sociale (CGE tivity improvement program S) du Projet d’Appui à la Con nectivité et au Transport (PA CT). ZR-CI-215454-CS-CDS / Réali sation par AECOM Consultant s Inc. des études diachroniqu es, durant la période de 10 d Sélection de cons Environmental and social m ernières années, de l’évolutio IDA / V2970 A posteriori ultants par entent Direct 136,055.00 0.00 Signé 2022-01-28 2022-02-15 2022-01-31 2022-04-14 2022-02-25 2022-07-26 2022-05-26 easures n environnementale et social e directe e par télédétection dans la b ande de 10 km centrée sur le s axes routiers Mbuji-Mayi – L ubao et Goma – Beni ZR-CI-275374-CS-CDS / Audi t financier du Fonds National Sélection de cons Sectoral governance for imp d'Entretien Routier (FONER), IDA / V2970 A posteriori ultants par entent Direct 33,500.00 0.00 Signé 2022-02-24 2022-04-04 2022-03-06 2022-03-04 2022-05-10 2022-05-20 2022-06-24 roved connectivity exercice 2021, par le groupe e directe ment de cabinets PROWAY & TUNEC ZR-CI-278031-CS-CDS / Audi Sélection de cons t financier de la Régie des Vo Environmental and social m IDA / V2970 A posteriori ultants par entent Direct 19,650.00 0.00 Annulé 2022-02-24 2022-03-03 2022-03-06 2022-05-10 2022-06-24 ies Aériennes (RVA), exercice easures e directe 2021 par le Cabinet MAZARS ZR-CI-278036-CS-CDS / RET RO - CEPTM - Contrôle et sur Sélection de cons Environmental and social m En cours d'exécut veillance des travaux d'achè IDA / V2970 A posteriori ultants par entent Direct 170,668.00 0.00 2022-03-01 2022-03-04 2022-03-11 2022-05-15 2022-12-15 easures ion vement de la tour de contrôl e directe e de l'aéroport de Goma par l a firme INTAIRPLAN GmbH ZR-CI-300085-CS-INDV / MO P - Assistance technique à l'é valuation des capacités de g Sectoral governance for imp estion de la sécurité routière, IDA / V2970 A priori Individuel Open 300,000.00 0.00 Annulé 2022-11-01 2022-12-20 2023-01-10 2023-02-14 2023-08-13 roved connectivity élaboration d'une stratégie n ationale de sécurité routière et d'un plan d'action connexe pour sa mise en œuvre Page 7 ZR-CI-300278-CS-INDV / MO Sectoral governance for imp En cours d'exame P - Consultants indépendants IDA / V2970 A priori Individuel Open 300,000.00 0.00 2022-07-15 2022-09-29 2022-09-02 2023-08-09 2022-09-23 2022-10-28 2027-04-27 roved connectivity n pour appui à l'évaluation des offres ZR-CI-300288-CS-INDV / Ela boration du Plan en faveur d es populations autochtones ( Environmental and social m IDA / V2970 A posteriori Individuel Direct 100,000.00 0.00 Signé 2022-07-01 2022-09-05 2022-07-11 2022-07-26 2022-08-01 2022-09-30 2022-09-05 2022-10-19 2022-12-20 PPA) des travaux routiers sur easures le tronçon Kabinda - Mbanga par Fortunat BAMPORIKI BISA NGA ZR-CI-300297-CS-CDS / Elab oration du Plan d'Action de R Sélection de cons éinstallation (PAR) des trava Environmental and social m IDA / V2970 A posteriori ultants par entent Direct 200,000.00 0.00 Signé 2022-07-01 2022-09-15 2022-07-11 2022-07-26 2022-09-14 2022-11-03 2023-01-04 ux routiers sur la RN2, tronço easures e directe n Butembo - Kanya Bayonga par la firme OKAPI Environne ment & Génie Civil ZR-CI-300299-CS-CDS / Actu alisation du Plan d'Action de Sélection de cons Réinstallation (PAR) des trav Environmental and social m IDA / V2970 A posteriori ultants par entent Direct 160,000.00 0.00 Signé 2022-07-01 2022-09-05 2022-07-11 2022-07-26 2022-09-14 2022-10-21 2023-01-04 aux routiers de la RN2, tronç easures e directe on Kabinda - Mbanga, par le Groupement de firmes ACEM S / SOTUEC International ZR-CI-300377-CS-INDV / MO P - Elaboration des Plans de Gestion Environnementale et Sociale (PGES) des travaux a Environmental and social m uxiliaires aux travaux routier IDA / V2970 A priori Individuel Open 400,000.00 0.00 Annulé 2022-07-15 2022-09-02 2022-09-23 2022-10-28 2023-01-26 easures s sur la RN2, tronçons Mbuji- Mayi - Kabinda - Mbanga et B utembo - Kanya Bayonga : ré habilitation des écoles, centr es de santé, puits d'eau ZR-CI-300382-CS-CDS / Audi t comptable, financier et de p Sélection de cons Sectoral governance for imp assation des marchés de la R IDA / V2970 A posteriori ultants par entent Direct 20,000.00 0.00 Signé 2022-06-27 2022-07-14 2022-07-07 2022-05-24 2022-07-16 2022-08-11 2022-09-14 roved connectivity VA, exercice 2021 par le cabi e directe net GRANT THORNTON ZR-CI-300383-CS-INDV / MIT Sectoral governance for imp En attente d'exéc IDA / V2970 A posteriori Individuel Open 108,000.00 0.00 2022-07-08 2022-09-08 2022-09-15 2022-10-06 2023-10-06 P - Coordonnateur de la CI roved connectivity ution ZR-CI-164587-CS-INDV / Etu Sectoral governance for imp des économiques des activit IDA / V2970 A posteriori Individuel Limited 40,000.00 0.00 Annulé 2020-04-06 2022-02-26 2020-04-11 2020-05-02 2020-06-06 2020-12-03 roved connectivity és aéroportuaires (Goma et B eni) ZR-CI-300379-CS-INDV / Act Environmental and social m ualisation du Plan de Gestion IDA / V2970 A posteriori Individuel Open 150,000.00 0.00 Annulé 2022-07-01 2022-08-19 2022-09-09 2022-10-14 2022-12-28 easures de la Biodiversité (PGB) ZR-CI-300380-CS-CDS / Audi t de sécurité routière des étu des techniques de conceptio Sélection de cons Environmental and social m n pour l'aménagement et le IDA / V2970 A posteriori ultants par entent Direct 215,000.00 0.00 Annulé 2022-07-01 2022-07-25 2022-07-11 2022-07-20 2022-10-18 easures bitumage de la RN2, tronçon e directe s Mbuji-Mayi - Kabinda - Mba nga et Butembo - Kanya Bay onga par la Firme FRED Engi neering ZR-CI-326286-CS-INDV / Aud it de la sécurité routière à la phase des études des travau Environmental and social m Direct - Internation IDA / 71610 A posteriori Individuel 99,540.00 0.00 Signé 2022-11-18 2022-11-22 2022-11-19 2022-10-20 2022-11-26 2022-12-31 2022-11-29 2023-01-10 2023-02-27 x (APD et DAO) sur les axes easures al Mbuji mayi-Kabinda-Mbanga et Kanya Bayonga-Butembo par Francisco REINA. ZR-CI-326284-CS-CDS / Actu Sélection de cons alisation du Plan de Gestion Environmental and social m Direct - Internation IDA / 71610 A posteriori ultants par entent 228,929.00 0.00 Signé 2022-12-23 2022-12-22 2022-12-30 2022-12-16 2023-01-09 2023-01-10 2023-02-23 de la Biodiversité (PGB) du P easures al e directe ACT par la firme SOTUEC Inte rnational ZR-CI-351266-CS-INDV / MO P - Prestation de services au Sectoral governance for imp En cours d'exécut poste d'Economiste de Trans IDA / 71610 A posteriori Individuel Direct - National 52,200.00 0.00 2023-03-24 2023-05-18 2023-03-29 2023-05-18 2023-03-30 2023-06-02 2023-04-01 2024-03-31 roved connectivity ion port par Monsieur Théodore NGAMBILA VAN MAZIREL ZR-CI-351274-CS-INDV / MO P - Prestation de services au poste d'Ingénieur routier 1, C Sectoral governance for imp IDA / 71610 A posteriori Individuel Direct - National 50,400.00 0.00 Signé 2023-03-24 2023-05-11 2023-03-29 2023-05-15 2023-03-30 2023-05-15 2023-04-01 2024-03-31 hargé d'Opérations sur le tro roved connectivity nçon routier Mbuji Mayi - Kab inda - Mbanga, par Monsieur Cyrille KIBULU KAPASA ZR-CI-351284-CS-INDV / MO P - Prestation de services au poste d'Ingénieur routier 2, C Sectoral governance for imp En cours d'exécut IDA / 71610 A posteriori Individuel Direct - National 50,400.00 0.00 2023-03-24 2023-05-11 2023-03-29 2023-03-30 2023-04-01 2024-03-31 hargé d'Opérations sur le tro roved connectivity ion nçon routier Kanya Bayonga - Butembo par Monsieur Ang e MUSHIGO VELU ZR-CI-351292-CS-INDV / MO P - Prestation de services au Sectoral governance for imp En cours d'exécut IDA / 71610 A posteriori Individuel Direct - National 42,000.00 0.00 2023-03-24 2023-05-11 2023-03-29 2023-03-30 2023-04-01 2024-03-31 poste de Comptable par Mon roved connectivity ion sieur Floribert MUKENO KIHU MBA ZR-CI-351304-CS-INDV / MO P - Prestation de services au Sectoral governance for imp En cours d'exécut poste de Responsable de Pas IDA / 71610 A posteriori Individuel Direct - National 66,240.00 0.00 2023-03-24 2023-05-08 2023-03-29 2023-03-30 2023-04-01 2024-03-31 roved connectivity ion sation des Marchés de la CI p ar Monsieur Damien MANYA MALA MAKANDAKELE ZR-CI-351669-CS-INDV / MO P - Prestation de services au Sectoral governance for imp poste de Spécialiste en Passa IDA / 71610 A posteriori Individuel Direct - National 52,800.00 0.00 Achevé 2023-03-24 2023-05-11 2023-03-29 2023-05-15 2023-03-30 2023-05-19 2023-04-01 2024-03-31 2024-03-31 roved connectivity tion des Marchés du Projet p ar Godefroid KASENDE MESO ZR-CI-351678-CS-INDV / MO P - Prestation de services au Sectoral governance for imp poste de Chef de Section Ad IDA / 71610 A posteriori Individuel Direct - National 63,600.00 0.00 Signé 2023-03-24 2023-05-08 2023-03-29 2023-05-08 2023-03-30 2023-05-23 2023-04-01 2023-05-23 2024-03-31 roved connectivity ministration et Finances de la CI par Madame Zady MUKE Z AWADI Page 8 ZR-CI-351688-CS-INDV / MO P - Prestation de services au poste d'Expert Environnemen Sectoral governance for imp En cours d'exécut IDA / 71610 A posteriori Individuel Direct - National 66,240.00 0.00 2023-03-24 2023-05-08 2023-03-29 2023-03-30 2023-04-01 2024-03-31 taliste et Responsable de l'U roved connectivity ion nité Environnementale et Soc iale de la CI par Monsieur Fell y BOKO LUTSU ZR-CI-351692-CS-INDV / MO P - Prestation de services au Sectoral governance for imp IDA / 71610 A posteriori Individuel Direct - National 50,400.00 0.00 Achevé 2023-03-24 2023-05-08 2023-03-29 2023-05-08 2023-03-30 2023-05-15 2023-04-01 2024-03-31 2024-03-31 poste d'Expert en Développe roved connectivity ment Social par Monsieur Féli x TSHABA MUKINAYI ZR-CI-351700-CS-INDV / MO P - Prestation de services au Sectoral governance for imp poste d'Expert en Violence B IDA / 71610 A posteriori Individuel Direct - National 50,400.00 0.00 Signé 2023-03-24 2023-05-18 2023-03-29 2023-05-23 2023-03-30 2023-05-23 2023-04-01 2023-05-23 2024-03-31 roved connectivity asée sur le Genre par Madam e Liliane MUSAU WA KAZADI ZR-CI-351702-CS-INDV / MO P - Prestation de services au Sectoral governance for imp En cours d'exécut IDA / 71610 A posteriori Individuel Direct - National 60,000.00 0.00 2023-03-24 2023-05-11 2023-03-29 2023-03-30 2023-04-01 2024-03-31 poste d'Expert Géomaticien roved connectivity ion Senior par Patrick MBUY'A SA KAFUKU ZR-CI-351724-CS-INDV / MO P - Prestation de services au Sectoral governance for imp En cours d'exécut IDA / 71610 A posteriori Individuel Direct - National 30,000.00 0.00 2023-03-24 2023-05-08 2023-03-29 2023-03-30 2023-04-01 2024-03-31 poste d'Assistante du Coordo roved connectivity ion nnateur par Madame Marian ne IKOBO ZR-CI-351732-CS-INDV / MO P - Prestation de services au Sectoral governance for imp En cours d'exécut IDA / 71610 A posteriori Individuel Direct - National 24,000.00 0.00 2023-03-24 2023-05-11 2023-03-29 2023-03-30 2023-04-01 2024-03-31 poste d'Assistante au Projet roved connectivity ion par Madame Mélanie KAYIBA ZR-CI-351738-CS-INDV / MO P - Prestation de services au Sectoral governance for imp En cours d'exécut IDA / 71610 A posteriori Individuel Direct - National 12,000.00 0.00 2023-03-24 2023-05-08 2023-03-29 2023-03-30 2023-04-01 2024-03-31 poste de Chauffeur 1 par Mo roved connectivity ion nsieur Jean-Pierre KILONGOK ELE ZR-CI-351746-CS-INDV / MO P - Prestation de services au Sectoral governance for imp En cours d'exécut IDA / 71610 A posteriori Individuel Direct - National 12,000.00 0.00 2023-03-24 2023-05-08 2023-03-29 2023-03-30 2023-04-01 2024-03-31 poste de Chauffeur 2 par Mo roved connectivity ion nsieur Noël MATUNGULU ZR-CI-365555-CS-INDV / MO Sectoral governance for imp En cours d'exécut P - Expert Environnementalis IDA / 71610 A posteriori Individuel Open - National 36,000.00 0.00 2023-07-05 2023-07-19 2023-08-23 2023-09-13 2023-10-18 2024-10-17 roved connectivity ion te Junior basé à Mbuji-Mayi ZR-CI-365559-CS-INDV / MO Sectoral governance for imp En cours d'exécut P - Expert Environnementalis IDA / 71610 A posteriori Individuel Open - National 36,000.00 0.00 2023-07-05 2023-07-19 2023-08-23 2023-09-13 2023-10-18 2024-10-17 roved connectivity ion te Junior basé à Butembo ZR-CI-365564-CS-INDV / MO P - Expert junior en Développ Sectoral governance for imp En cours d'exécut IDA / 71610 A posteriori Individuel Open - National 36,000.00 0.00 2023-07-05 2023-07-19 2023-08-23 2023-09-13 2023-10-18 2024-10-17 ement Social y compris EAS/ roved connectivity ion HS, basé à Mbuji-Mayi ZR-CI-365570-CS-INDV / MO P - Expert Junior en Développ Sectoral governance for imp En cours d'exécut IDA / 71610 A posteriori Individuel Open - National 36,000.00 0.00 2023-07-05 2023-07-19 2023-08-23 2023-09-13 2023-10-18 2024-10-17 ement Social y compris EAS/ roved connectivity ion HS, basé à Butembo ZR-CI-365612-CS-CDS / MOP - Audit des comptes du derni Sélection de cons er exercice (2022) de l'Avanc Sectoral governance for imp Direct - Internation IDA / 71610 A posteriori ultants par entent 27,000.00 0.00 Signé 2023-07-03 2023-03-13 2023-07-13 2023-04-28 2023-07-24 2023-08-23 e de Préparation du Projet (P roved connectivity al e directe PA) du PACT par le Groupem ent FICADEX TATE & ASSOCI ES et SECOFIC sarl ZR-CI-371001-CS-INDV / MO P - Prestation de services au Sectoral governance for imp En cours d'exécut poste de Gestionnaire des Ar IDA / 71610 A posteriori Individuel Direct - National 21,600.00 0.00 2023-07-17 2023-07-14 2023-07-25 2023-08-01 2023-08-11 2024-08-10 roved connectivity ion chives au sein de la CI par St agard MANGASA MOMELI ZR-CI-380939-CS-INDV / Pre stations d'un Consultant Spé Transport and digital connec En cours d'exécut IDA / 71610 A posteriori Individuel Open - National 48,000.00 0.00 2023-09-22 2023-10-16 2023-11-10 2023-12-01 2024-01-05 2024-07-03 cialiste en télécommunicatio tivity improvement program ion n au sein de la Cellule Infrast ructures ZR-CI-400772-CS-INDV / MO P-Actualisation de l’Etude d’I mpact Environnemental et S Environmental and social m Direct - Internation En cours d'exame ocial (EIES) des travaux de dr IDA / 71610 A posteriori Individuel 51,500.00 0.00 2024-02-09 2024-02-21 2024-02-14 2024-03-06 2024-03-27 2024-06-15 easures al n ainage de l’aéroport internati onal de Goma, dans la provin ce du Nord-Kivu par Pierre An dré Turcotte. ZR-CI-406515-CS-CDS / MOP - Etudes techniques et écono Sélection de cons Transport and digital connec Direct - Internation En cours d'exécut miques d'aménagement et d IDA / 71610 A posteriori ultants par entent 900,200.00 0.00 2024-02-12 2024-03-07 2024-02-26 2024-05-08 2025-02-08 tivity improvement program al ion e bitumage de la RN2, tronço e directe n Mbanga - Penemwanga (40 0 km) par AIC PROGETTI ZR-CI-406510-CS-INDV / MO P-Audit de sécurité routière d es travaux d’aménagement e Transport and digital connec Direct - Internation En cours d'exame t de bitumage de la RN2, tro IDA / 71610 A posteriori Individuel 258,200.00 0.00 2024-02-09 2024-03-07 2024-02-23 2024-03-15 2024-04-05 2027-06-19 tivity improvement program al n nçons Mbuji Mayi – Kabinda – Mbanga (280 km) et Kanyaba yonga - Butembo (160 km) p ar Francesco Reina ZR-CI-401041-CS-INDV / MO P -Prestation de services au p Transport and digital connec En cours d'exécut oste de Spécialiste en Passati IDA / 71610 A posteriori Individuel Open - National 50,400.00 0.00 2024-02-12 2024-02-19 2024-04-03 2024-04-13 2024-05-04 2025-05-04 tivity improvement program ion on des Marchés 2 pour le pro jet PACT au sein de la Cellule Infrastructures ZR-CI-416442-CS-INDV / MO P - Assistance technique pour Sectoral governance for imp Open - Internationa En attente d'exéc l'établissement du diagnostic IDA / 71610 A posteriori Individuel 58,335.00 0.00 2024-04-01 2024-05-20 2024-06-10 2024-07-15 2024-09-13 roved connectivity l ution de l'organisation institutionn elle de la Cellule Infrastructur es Page 9 ZR-CI-416444-CS-INDV / MO P - Prestation de services au Sectoral governance for imp En cours d'exécut poste d'Assistante au Coordo IDA / 71610 A posteriori Individuel Direct - National 30,000.00 0.00 2024-03-29 2024-04-24 2024-04-01 2024-04-03 2024-04-06 2025-04-06 roved connectivity ion nnateur de la Cellule Infrastr uctures par Yvette ASERO ZR-CI-416448-CS-INDV / MO Sectoral governance for imp En cours d'exame P - Prestation de services au IDA / 71610 A posteriori Individuel Open - National 50,400.00 0.00 2024-04-08 2024-06-17 2024-05-27 2024-05-30 2024-06-09 2025-06-09 roved connectivity n poste d'Ingénieur Chargé des Opérations 1 ZR-CI-416517-CS-CDS / MOP - Actualisation des études to pographiques d'aménageme Sélection de cons Transport and digital connec Direct - Internation nt et bitumage de la RN2, tro IDA / 71610 A posteriori ultants par entent 260,409.00 0.00 Annulé 2024-04-01 2024-04-06 2024-04-27 2024-09-24 tivity improvement program al nçon Kanyabayonga-Butemb e directe o avec une plate de 2x2 voie s de circulation par le Groupe ment BECETP - ART & GENIE ZR-CI-416522-CS-CDS / MOP - Actualisation des études to pographiques d'aménageme Sélection de cons nt et de bitumage de la RN2, Transport and digital connec Direct - Internation En cours d'exécut IDA / 71610 A posteriori ultants par entent 380,000.00 0.00 2024-04-01 2024-04-19 2024-04-06 2024-04-27 2024-09-24 tronçon Mbujimayi-Kabinda- tivity improvement program al ion e directe Mbanga avec une plate form e de 2x2 voies de circulation par le Groupement BECETP - ART & GENIE ZR-CI-416530-CS-CDS / MOP - Actualisation du PAR des tra Sélection de cons vaux de bitumage de la RN2, Transport and digital connec IDA / 71610 A posteriori ultants par entent Direct - National 145,360.00 0.00 Annulé 2024-04-03 2024-05-06 2024-04-08 2024-04-29 2024-08-12 tronçon Mbujimayi-Kabinda- tivity improvement program e directe Mbanga avec plate de 2x2 vo ies de circulation par le Bure au ACEMS ZR-CI-416537-CS-CDS / MOP - Actualisation du PAR des tra Sélection de cons vaux de bitumage de la RN2, Transport and digital connec En attente d'exéc IDA / 71610 A posteriori ultants par entent Direct - National 125,640.00 0.00 2024-04-03 2024-04-08 2024-04-29 2024-07-28 tronçon Kanyabayonga-Bute tivity improvement program ution e directe mbo avec une plateforme de 2x2 voies de circulation par OKAPI EGC ZR-CI-416562-CS-CDS / MOP - Actualisation des EIES des t Sélection de cons ravaux de bitumage de la RN Transport and digital connec Direct - Internation En cours d'exame IDA / 71610 A posteriori ultants par entent 209,475.00 0.00 2024-04-05 2024-05-14 2024-04-10 2024-05-01 2024-08-14 2, tronçon Mbujimayi-Kabind tivity improvement program al n e directe a-Mbanga avec plateforme à 2x2 voies de circulation par S ERF BURKINA ZR-CI-416565-CS-CDS / MOP - Actualisation des EIES des t Sélection de cons ravaux de bitumage de la RN Transport and digital connec Direct - Internation IDA / 71610 A posteriori ultants par entent 202,125.00 0.00 Annulé 2024-04-05 2024-04-10 2024-05-01 2024-08-14 2, tronçon Kanyabayonga-Bu tivity improvement program al e directe tembo avec une plateforme à 2x2 voies de circulation par S OTUEC International ZR-CI-427113-CS-INDV / MO P - Consultant individuel pour Sectoral governance for imp Open - Internationa En attente d'exéc IDA / 71610 A posteriori Individuel 48,000.00 0.00 2024-06-17 2024-08-05 2024-08-26 2024-09-30 2025-03-29 l'actualisation du Manuel d'O roved connectivity l ution pérations de l'Entretien Routi er en RDC ZR-CI-428350-CS-INDV / MO P - Prestations d'un Expert en Transport and digital connec En cours d'exame Environnement et Biodiversit IDA / 71610 A posteriori Individuel Open - National 48,000.00 0.00 2024-06-17 2024-06-11 2024-08-05 2024-08-26 2024-09-30 2025-03-29 tivity improvement program n é (EEB) basé (e) à Kinshasa a u sein de la Cellule Infrastruc tures ZR-CI-428356-CS-INDV / MO P - Prestations d'un Expert en Développement Social (EDS) Transport and digital connec En cours d'exame IDA / 71610 A posteriori Individuel Direct - National 50,400.00 0.00 2024-06-17 2024-05-31 2024-06-27 2024-07-18 2024-08-22 2025-02-18 basé à Kinshasa au sein de la tivity improvement program n Cellule Infrastructures, par M onsieur Bienvenu MUCHUKIW A NGUSU. ZR-CI-429228-CS-CDS / MOP - Etude technique pour (i) la r éhabilitation du tronçon endo Sélection de cons Sectoral governance for imp Direct - Internation En attente d'exéc mmagé de la piste de l'aérop IDA / 71610 A posteriori ultants par entent 300,200.00 0.00 2024-07-10 2024-07-20 2024-09-23 2025-03-22 roved connectivity al ution ort de Goma, (ii) de l'aménag e directe ement des aires d'extrémités de la piste et (ii) de réparatio n des accotements ZR-CI-432876-CS-CDS / MOP Sélection de cons - Mise à jour du Plan de Gesti Environmental and social m Direct - Internation En attente d'exéc IDA / 71610 A posteriori ultants par entent 500,000.00 0.00 2024-07-10 2024-07-20 2024-09-23 2025-03-22 on de la Biodiversite (PGB) d easures al ution e directe u PACT par entente directe a vec la firme WCS ZR-CI-432930-CS-INDV / MO P - Prestations de services de Consultant individuel au post e d’Assistante au Projet au se Transport and digital connec En attente d'exéc IDA / 71610 A posteriori Individuel Direct - National 24,000.00 0.00 2024-07-10 2024-07-20 2024-08-10 2024-09-14 2025-03-13 in de la Cellule Infrastructure tivity improvement program ution s, dans le cadre du Projet d’A ppui à la Connectivité et au T ransport (AP2-PACT)-Mariann e IKOBO FUMUKANI ZR-CI-432984-CS-INDV / MO Sectoral governance for imp En attente d'exéc P - Audit technique des infras IDA / 71610 A posteriori Individuel Limited - National 50,000.00 0.00 2024-07-10 2024-07-15 2024-08-05 2024-09-09 2025-03-08 roved connectivity ution tructures de la SOCOF ZR-CI-434798-CS-CDS / MOP - Mise à jour du PAR / actuali sation et finalisation de l’EIES /PGES des ouvrages connexe Sélection de cons Environmental and social m En attente d'exéc s des travaux de bitumage a IDA / 71610 A posteriori ultants par entent Direct - National 186,982.00 0.00 2024-07-10 2024-07-20 2024-09-23 2025-03-22 easures ution vec la plateforme de 1 x 2 vo e directe ies, dans la province du Nord Kivu, dans le cadre du projet PACT 1, par entente directe a vec OKAPI EGC SARL ZR-CI-434840-CS-CDS / MOP - Actualisation des PAR, EIES, PPA et finalisation EIES/PGES des ouvrages connexes, trav Sélection de cons Environmental and social m En attente d'exéc aux bitumage tronçons routi IDA / 71610 A posteriori ultants par entent Direct - National 360,934.00 0.00 2024-07-10 2024-07-20 2024-09-23 2025-03-22 easures ution ers Mbuji Mayi – Kabinda et K e directe abinda – Mbanga avec platef orme de 2 voies x 2, dans KO et LOM par entente directe a vec la firme AREAU Page 10 ZR-CI-435132-CS-INDV / MO P - Audit organisationnel, tec Transport and digital connec Limited - Internatio En attente d'exéc IDA / 71610 A posteriori Individuel 123,610.00 0.00 2024-07-10 2024-07-15 2024-08-05 2024-09-09 2025-03-08 hnique et des competences d tivity improvement program nal ution e la Cellule Infrastructures Page 11