MONGOLIA ADDITIONAL FINANCING TO ULAANBAATAR CLEAN AIR PROJECT (P167421) PROJECT PROCUREMENT PLAN May 18, 2020 1 PROCUREMENT PLAN Project information: Additional Financing to Ulaanbaatar Clean Air Project (P167421) Project Implementation agency: AF UBCAP Project Implementation Unit Date of the Procurement Plan: June 2020 Period covered by this Procurement Plan: From 1st June 2020 to 31st December 2021 1. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, revised November 2017 and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking of Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. 2. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. 3. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. 3.1 National Open Competitive Procurement When the Borrower uses its own national open competitive procurement arrangements as set forth in Chapter Two of the Public Procurement Law of Mongolia enacted on December 1, 2005, as amended several times with the latest amendment on March 22, 2019, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Participation in Bidding and Preferences (i) Government-owned enterprises in Mongolia shall be eligible to participate in bidding only if they can establish that they are legally and financially autonomous, operate under commercial law, and are not a dependent of the agency contracting them. 2 (ii) A bidder declared ineligible by the World Bank, based on a determination by the World Bank that the bidder has engaged in corrupt, fraudulent, collusive, coercive or obstructive practices in competing for or in executing a World Bank- financed contract, shall be ineligible to participate and be awarded a World Bank-financed contract during the period determined by the World Bank. (iii) A firm which has been engaged by the Borrower to provide consulting services for the preparation or implementation of a project, and any of its affiliates, shall be disqualified from subsequently providing goods or works resulting from or directly related to the firm’s consulting services for such preparation or implementation. This provision does not apply to the various firms which together are performing the contractor’s obligations under a turnkey or design and build contract. (iv) Interested foreign bidders from eligible countries shall be allowed to participate without being required to associate or form joint ventures with local bidders. Foreign bidders shall be eligible to participate in bidding under the same conditions as local bidders. Mongolian bidders and goods of Mongolian origin shall be given no preference over foreign bidders, either in the bidding process or in the evaluation of bids. (v) Prior registration shall not be a requirement for any bidder to participate in bidding. (b) Request for Bids / Request for Proposals Documents (i) The request for bids/request for proposals documents shall be acceptable to the World Bank and include the WB’s provisions for fraud and corruption. (ii) In the case of contracts of more than eighteen (18) months’ duration, the procurement documents and the contract shall provide for price adjustment, based on a formula acceptable to the World Bank, which shall be disclosed to the bidders in the procurement documents. (iii) Unless agreed and established in the procurement plan, there shall be no post-bidding negotiations. No bidder shall be required, as a condition for the award of contract, to change his bid price or otherwise materially alter his bid after it has been submitted. (c) Assessment of Bidder’s Qualification Qualification criteria shall be clearly specified in the bidding documents, and only criteria so specified, shall be used to determine whether a bidder is qualified. The evaluation of the bidder’s 3 qualifications shall be conducted separately from the technical and commercial evaluation of the bid. When post qualification is applied, the assessment of bidder’s qualifications shall be carried out only after the preliminary and detailed evaluation of bids has been completed by the Recipient and, in doing so, the qualifications of the bidder who has submitted the lowest evaluated substantially responsive bid or most advantageous bid shall be assessed first. The evaluation of a bidder’s qualifications shall only take into account the bidder’s capacity and resources to perform the contract, specifically its experience and past performance on similar contracts, capabilities with respect to personnel, equipment and construction or manufacturing facilities and financial capacity. In carrying out the bid evaluation including the post-qualification assessment, the Recipient shall exercise reasonable judgment in requesting clarifications in writing from Bidders in accordance with the provisions established in the procurement documents. No bidders shall be disqualified on the ground that the bidder has tax debt. 3.2 Other National Procurement Arrangements When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. The request for bids / request for proposals / request for quotations documents should be acceptable to the Bank and jointly with the signed contract shall include the clauses related to World Bank’s Policy in regard to corrupt and fraudulent practices. The request for bids / request for proposals / request for quotations documents and the signed contract shall also include the clauses allowing the World Bank to inspect the site and/or all accounts and records relating to the performance of the contract and the submission of the bid or proposal, and to have such accounts and records audited. The standard text is attached hereafter. 4. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not applicable. 5. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not applicable. 6. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works): Not applicable. 7. Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations: Not applicable. 8. Other Relevant Procurement Information: Not applicable. 9. Standard Text for Fraud & Corruption and Inspection & Audit Fraud and The Bank requires compliance with the Bank’s Anti- 4 Corruption Corruption Guidelines and its prevailing sanctions policies and procedures as set forth in the WBG’s Sanctions Framework, as set forth in Appendix to the GC. The Employer / Purchaser / Client requires the Contractor / Supplier / the Consultant to disclose any commissions or fees that may have been paid or are to be paid to agents or any other party with respect to the bidding /selection process or execution of the Contract. The information disclosed must include at least the name and address of the agent or other party, the amount and currency, and the purpose of the commission, gratuity or fee. Failure to disclose such commissions, gratuities or fees may result in termination of the Contract and/or sanctions by the Bank. Inspections The Contractor / Supplier / Consultant shall keep and and Audit shall make all reasonable efforts to cause its by the Subcontractors and Sub-consultants to keep, accurate Bank and systematic accounts and records in respect of the Works / Goods / Services in such form and details as will clearly identify relevant time changes and costs. Pursuant to paragraph 2.2 e. of Appendix to the General Conditions the Contractor / Supplier / Consultant shall permit and shall cause its subcontractors and sub-consultants to permit, the Bank and/or persons appointed by the Bank to inspect the Site and/or the accounts and records relating to the performance of the Contract and the submission of the bid / proposal, and to have such accounts and records audited by auditors appointed by the Bank if requested by the Bank. The Contractor’s / Supplier’s / Consultant’s and its Subcontractors’ and sub- consultants’ acts intended to materially impede the exercise of the Bank’s inspection and audit rights constitute a prohibited practice subject to contract termination (as well as to a determination of ineligibility pursuant to the Bank’s prevailing sanctions procedures). 5 Procurement thresholds, per method (US$ thousand) International National Request for Quotations Competitive Competitive (RFQ) Procurement Procurement Works Goods/N Works Goods/N Works Goods/NC C C >5,00 >1,000 <5,000 < 1,000 <200 <100 0 Prior reviews threshold is shown below: Prior reviews threshold for Mongolia – 2017-2019 Category High and Moderate and low risk Substantial risk Works >US$ 1 million US$ > 1.5 million Goods – NC >US$ 500,000 US$ > 500,000 Consulting >US$ 400,000 US$ > 600,000 services (firm) Individual >US$ 150,000 > US$ 200,000 consultants 6 APPENDIX TO GENERAL CONDITIONS Fraud and Corruption (Text in this Appendix shall not be modified) 1. Purpose 1.1 The Bank’s Anti-Corruption Guidelines and this annex apply with respect to procurement under Bank Investment Project Financing operations. 2. Requirements 2.1 The Bank requires that Borrowers (including beneficiaries of Bank financing); bidders, consultants, contractors and suppliers; any sub- contractors, sub-consultants, service providers or suppliers; any agents (whether declared or not); and any of their personnel, observe the highest standard of ethics during the procurement process, selection and contract execution of Bank-financed contracts, and refrain from Fraud and Corruption. 2.2 To this end, the Bank: a. Defines, for the purposes of this provision, the terms set forth below as follows: i. “corrupt practice” is the offering, giving, receiving, or soliciting, directly or indirectly, of anything of value to influence improperly the actions of another party; ii. “fraudulent practice” is any act or omission, including misrepresentation, that knowingly or recklessly misleads, or attempts to mislead, a party to obtain financial or other benefit or to avoid an obligation; iii. “collusive practice” is an arrangement between two or more parties designed to achieve an improper purpose, including to influence improperly the actions of another party; iv. “coercive practice” is impairing or harming, or threatening to impair or harm, directly or indirectly, any party or the property of the party to influence improperly the actions of a party; v. “obstructive practice” is: (a) deliberately destroying, falsifying, altering, or concealing of evidence material to the investigation or making false statements to investigators in order to materially impede a Bank investigation into allegations of a corrupt, fraudulent, coercive, or collusive practice; and/or threatening, harassing, or intimidating any party to prevent it from disclosing its knowledge of matters 7 relevant to the investigation or from pursuing the investigation; or (b) acts intended to materially impede the exercise of the Bank’s inspection and audit rights provided for under paragraph 2.2 e. below. b. Rejects a proposal for award if the Bank determines that the firm or individual recommended for award, any of its personnel, or its agents, or its sub-consultants, sub-contractors, service providers, suppliers and/ or their employees, has, directly or indirectly, engaged in corrupt, fraudulent, collusive, coercive, or obstructive practices in competing for the contract in question; c. In addition to the legal remedies set out in the relevant Legal Agreement, may take other appropriate actions, including declaring mis-procurement, if the Bank determines at any time that representatives of the Borrower or of a recipient of any part of the proceeds of the loan engaged in corrupt, fraudulent, collusive, coercive, or obstructive practices during the procurement process, selection and/or execution of the contract in question, without the Borrower having taken timely and appropriate action satisfactory to the Bank to address such practices when they occur, including by failing to inform the Bank in a timely manner at the time they knew of the practices; d. Pursuant to the Bank’s Anti- Corruption Guidelines and in accordance with the Bank’s prevailing sanctions policies and procedures, may sanction a firm or individual, either indefinitely or for a stated period of time, including by publicly declaring such firm or individual ineligible (i) to be awarded or otherwise benefit from a Bank-financed contract, financially or in any other manner;1 (ii) to be a nominated2 sub-contractor, consultant, manufacturer or supplier, or service provider of an otherwise eligible firm being awarded a Bank-financed contract; and (iii) to receive the proceeds of any loan made by the Bank or otherwise to participate further in the preparation or implementation of any Bank-financed project; e. Requires that a clause be included in bidding/request for proposals documents and in contracts financed by a Bank loan, requiring (i) bidders, consultants, contractors, and suppliers, 1 For the avoidance of doubt, a sanctioned party’s ineligibility to be awarded a contract shall include, without limitation, (i) applying for pre-qualification, expressing interest in a consultancy, and bidding, either directly or as a nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider, in respect of such contract, and (ii) entering into an addendum or amendment introducing a material modification to any existing contract. 2 A nominated sub-contractor, nominated consultant, nominated manufacturer or supplier, or nominated service provider (different names are used depending on the particular bidding document) is one which has been: (i) included by the bidder in its pre-qualification application or bid because it brings specific and critical experience and know-how that allow the bidder to meet the qualification requirements for the particular bid; or (ii) appointed by the Borrower. 8 and their sub-contractors, sub-consultants, service providers, suppliers, agents personnel, permit the Bank to inspect3 all accounts, records and other documents relating to the submission of bids and contract performance, and to have them audited by auditors appointed by the Bank. 3 Inspections in this context usually are investigative (i.e., forensic) in nature. They involve fact-finding activities undertaken by the Bank or persons appointed by the Bank to address specific matters related to investigations/audits, such as evaluating the veracity of an allegation of possible Fraud and Corruption, through the appropriate mechanisms. Such activity includes but is not limited to: accessing and examining a firm's or individual's financial records and information, and making copies thereof as relevant; accessing and examining any other documents, data and information (whether in hard copy or electronic format) deemed relevant for the investigation/audit, and making copies thereof as relevant; interviewing staff and other relevant individuals; performing physical inspections and site visits; and obtaining third party verification of information. 9 PROCUREMENT Mongolia : Ulaanbaatar Clean Air Project PLAN General Information Country: Mongolia 2020-03-13 Bank’s Approval Date of the Original Procurement Plan: 2023-06-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P122320 GPN Date: 2020-05-23 Project Name: Ulaanbaatar Clean Air Project Loan / Credit No: IDA / 50390, IDA / 64930 UBCAP PIU Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned WPLT-01-B / Small works for A. Ger Area Particulate Matt Single Stage - One E 2015-07-1 Green Demonstration Project IDA / 50390 Prior Request for Bids Open - National 153,000.00 113,568.29 Signed 2014-08-22 2014-10-13 2015-01-14 2015-01-27 2015-02-24 2015-02-25 er Mitigation nvelope 0 at Tasgan Ovoo, Ulaanbaatar Mongolia WPLT-01-A / Small Works for A. Ger Area Particulate Matt Single Stage - One E Green Demonstration Project IDA / 50390 Prior Request for Bids Open - National 227,000.00 163,740.77 Signed 2015-01-20 2015-03-11 2015-04-14 2015-04-30 er Mitigation nvelope at Tasgan Ovoo, Lot1 AFA2-01 / Works (dismantlin A. Ger Area Particulate Matt Single Stage - One E 2021-06-1 g of HOB/s and connection to IDA / 64930 Post Request for Bids Open - National 600,000.00 312,060.70 Completed 2020-08-26 2020-07-30 2020-08-31 2020-10-12 2020-09-07 2020-11-11 2020-09-09 2020-12-16 2020-09-16 er Mitigation nvelope 4 district heating network) AFD3-01 / Supply and install ation of last mile rewiring, el D. Electricity for heating in t 2021-08-2 IDA / 64930 Post Direct Selection Direct 120,000.00 0.00 Canceled 2020-07-16 2020-09-13 2020-07-21 2020-07-27 2020-08-25 ectricity meter, in-box amper argeted ger areas 5 e breaker, and ETS monthly i nstallments collection AFD3 / Supply and Installatio D. Electricity for heating in t Request for Quota Single Stage - One E 2021-12-3 IDA / 64930 Post Limited 30,000.00 27,625.14 Signed 2021-01-29 2021-01-28 2021-02-15 2021-02-22 n of 2 tariff meters differenti argeted ger areas tions nvelope 1 al AFCA3-01 / Insulation and re Request for Quota A. Ger Area Particulate Matt Request for Quota Single Stage - One E 2022-01-0 trofitting work for school No IDA / 64930 Post Limited tions (Non Bank-S 195,000.00 197,903.33 Completed 2021-06-28 2021-07-24 2021-07-24 2021-08-17 er Mitigation tions nvelope 1 37, Chingeltei duureg PD) AFCA3-03 / Insulation and re Request for Quota A. Ger Area Particulate Matt Request for Quota Single Stage - One E 2021-12-3 trofitting work for kindergart IDA / 64930 Post Limited tions (Non Bank-S 199,000.00 209,721.39 Completed 2021-06-28 2021-07-24 2021-07-23 2021-08-17 er Mitigation tions nvelope 1 en No 133, Bayangol district PD) AFCA3-04 / Insulation and re Request for Quota A. Ger Area Particulate Matt Request for Quota Single Stage - One E 2021-12-3 trofitting work for kindergart IDA / 64930 Post Limited tions (Non Bank-S 165,000.00 223,834.30 Completed 2021-06-28 2021-07-24 2021-07-23 2021-08-17 er Mitigation tions nvelope 1 en No 114, Bayangol district PD) AFCA3-05 / Insulation and re Request for Quota A. Ger Area Particulate Matt Request for Quota Single Stage - One E 2021-12-3 trofitting work for kindergart IDA / 64930 Post Limited tions (Non Bank-S 165,000.00 172,342.73 Completed 2021-06-28 2021-07-24 2021-07-23 2021-08-17 er Mitigation tions nvelope 1 en No 83, (selected for geoth PD) ermal heat pump) Request for Bids - AFB1-01 / Thermal renovatio B. Central Ulaanbaatar Parti Single Stage - One E Works (without pr 2021-12-3 n for precast concrete apart IDA / 64930 Post Request for Bids Open - National 330,000.00 0.00 Canceled 2021-07-02 2021-08-13 2021-07-06 2021-08-05 2021-08-13 2021-08-20 culate Matter Mitigation nvelope equalification) SP 1 ment buildings (9 floor apart D ment) Request for Bids - AFB1-02 / Thermal renovatio B. Central Ulaanbaatar Parti Single Stage - One E Works (without pr 2021-12-3 n for precast concrete apart IDA / 64930 Post Request for Bids Open - National 330,000.00 244,539.92 Completed 2021-07-02 2021-08-12 2021-07-06 2021-08-05 2021-09-13 2021-08-13 2021-09-14 2021-08-20 2021-09-17 culate Matter Mitigation nvelope equalification) SP 1 ment buildings (9-floors apar D tment) AFB1-03 / Thermal renovatio Request for Quota B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E 2021-12-3 n for precast concrete apart IDA / 64930 Post Limited tions (Non Bank-S 170,000.00 203,943.24 Completed 2021-07-09 2021-07-24 2021-08-09 2021-08-17 culate Matter Mitigation tions nvelope 1 ment buildings (5-floors apar PD) tment) AFB1-04 / Thermal renovatio Request for Quota B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E 2021-12-3 n for precast concrete apart IDA / 64930 Post Limited tions (Non Bank-S 170,000.00 202,163.05 Completed 2021-07-09 2021-08-23 2021-08-09 2021-08-28 culate Matter Mitigation tions nvelope 1 ment buildings (5-floors apar PD) tment) AFA2-02 / Dismantling of HO Request for Bids - B/s and connection to district A. Ger Area Particulate Matt Single Stage - One E Works (without pr 2021-12-3 IDA / 64930 Post Request for Bids Open - National 370,000.00 223,623.61 Completed 2021-07-28 2021-08-25 2021-07-30 2021-08-29 2021-09-23 2021-09-03 2021-09-24 2021-09-10 2021-09-28 heating network (Songinokha er Mitigation nvelope equalification) SP 1 irkhan district, HOB for schoo D l No 42) Request for Bids - AFA2-03 / Dismantling of HO A. Ger Area Particulate Matt Single Stage - One E Works (without pr 2021-12-3 B/s and connection to district IDA / 64930 Post Request for Bids Open - National 370,000.00 0.00 Canceled 2021-07-28 2021-08-25 2021-07-30 2021-08-29 2021-09-03 2021-09-10 er Mitigation nvelope equalification) SP 1 heating network D National Procure AFCA2 / Survey, design and ment Document - demonstration of Pilot projec A. Ger Area Particulate Matt Single Stage - One E 2021-12-3 IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 280,000.00 286,447.76 Signed 2021-07-16 2021-08-11 2021-07-19 2021-08-18 2021-09-10 2021-08-27 2021-09-14 2021-09-06 2021-09-25 t on Geothermal heat pump f er Mitigation nvelope 1 ss (Non Bank-SPD or kindergartens in ger area ) National Procure AFCA3-02 / Insulation and re ment Document - A. Ger Area Particulate Matt Single Stage - One E 2021-12-3 trofitting work for school No IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 240,000.00 403,486.84 Completed 2021-07-01 2022-04-11 2021-07-02 2021-08-02 2022-05-20 2021-08-09 2022-05-25 2021-08-25 2022-06-07 er Mitigation nvelope 1 49, Chingeltei district ss (Non Bank-SPD ) AFD3-02 / Supply and Install A. Ger Area Particulate Matt Other (with field f 2022-02-0 ation of last-mile rewiring, el IDA / 64930 Post Direct Selection Direct 74,000.00 73,512.58 Completed 2021-08-03 2021-08-04 2021-08-05 2021-07-29 2021-08-09 2021-08-05 er Mitigation or explanation) 5 ectricity meter, distribution b ox, and grounding AFA2-03-1 / Dismantling of H Request for Quota A. Ger Area Particulate Matt Request for Quota Single Stage - One E 2021-12-3 OB/s and connection to distri IDA / 64930 Post Limited tions (Non Bank-S 70,000.00 46,282.62 Completed 2021-11-15 2021-08-06 2021-12-01 2021-08-26 er Mitigation tions nvelope 0 ct heating network PD) AFB1-01-1 / Thermal renovat Request for Quota A. Ger Area Particulate Matt Request for Quota Single Stage - One E 2021-12-3 ion for precast concrete apar IDA / 64930 Post Limited tions (Non Bank-S 170,000.00 187,165.99 Completed 2021-11-15 2021-11-11 2021-12-01 2021-08-28 er Mitigation tions nvelope 0 tment No 8b, Somginokhairk PD) han district Request for Bids - AFCA3-06 / Insulation and re A. Ger Area Particulate Matt Single Stage - One E Small Works SPD 2022-09-3 IDA / 64930 Post Request for Bids Open - National 240,000.00 243,370.94 Completed 2022-04-01 2022-04-11 2022-04-06 2022-05-18 2022-05-20 2022-05-31 2022-05-25 2022-06-15 2022-06-16 trofitting work for school No . er Mitigation nvelope (1 envelope proce 0 . ss) Request for Bids - AFCA3-07 / Insulation and re A. Ger Area Particulate Matt Single Stage - One E Small Works SPD 2022-09-3 IDA / 64930 Post Request for Bids Open - National 240,000.00 0.00 Canceled 2022-04-01 2022-04-06 2022-05-18 2022-05-31 2022-06-15 trofitting work for school No.. er Mitigation nvelope (1 envelope proce 0 . ss) Request for Bids - AFCA3-08 / Insulation and re A. Ger Area Particulate Matt Single Stage - One E Small Works SPD 2022-09-3 IDA / 64930 Post Request for Bids Open - National 220,000.00 205,004.65 Signed 2022-04-01 2022-04-11 2022-04-06 2022-05-18 2022-05-20 2022-05-31 2022-05-25 2022-06-15 2022-06-16 trofitting work for kindergart er Mitigation nvelope (1 envelope proce 0 en No... ss) Page 1 Request for Bids - AFCA3-09 / Insulation and re A. Ger Area Particulate Matt Single Stage - One E Small Works SPD 2022-09-3 IDA / 64930 Post Request for Bids Open - National 220,000.00 0.00 Canceled 2022-04-01 2022-04-06 2022-05-18 2022-05-31 2022-06-15 trofitting work for kindergart er Mitigation nvelope (1 envelope proce 0 en No... ss) Request for Bids - AFB1-05 / Thermal renovatio B. Central Ulaanbaatar Parti Single Stage - One E Small Works SPD 2022-09-3 n for precast concrete apart IDA / 64930 Post Request for Bids Open - National 210,000.00 0.00 Canceled 2022-04-04 2022-04-09 2022-05-21 2022-06-03 2022-06-15 culate Matter Mitigation nvelope (1 envelope proce 0 ment buildings No.. ss) Request for Bids - AFB1-07 / Thermal renovatio B. Central Ulaanbaatar Parti Single Stage - One E Small Works SPD 2022-09-3 n for precast concrete apart IDA / 64930 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2022-04-04 2022-04-09 2022-05-21 2022-06-03 2022-06-15 culate Matter Mitigation nvelope (1 envelope proce 0 ment buildings No.. ss) Request for Bids - AFB1-08 / Thermal renovatio B. Central Ulaanbaatar Parti Single Stage - One E Small Works SPD 2022-09-3 n for precast concrete apart IDA / 64930 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2022-04-04 2022-04-09 2022-05-21 2022-06-03 2022-06-15 culate Matter Mitigation nvelope (1 envelope proce 0 ment buildings No ss) Request for Bids - AFA2-04 / Dismantling of HO A. Ger Area Particulate Matt Single Stage - One E Small Works SPD 2022-11-0 B/s and connection to district IDA / 64930 Post Request for Bids Open - National 300,000.00 0.00 Signed 2022-06-02 2022-09-19 2022-06-07 2022-07-19 2022-10-31 2022-07-29 2022-11-02 2022-08-15 er Mitigation nvelope (1 envelope proce 1 heating network ss) Request for Bids - AFA2-05 / Dismantling of HO A. Ger Area Particulate Matt Single Stage - One E Small Works SPD 2022-10-3 B/s and connection to district IDA / 64930 Post Request for Bids Open - National 300,000.00 160,689.10 Completed 2022-06-02 2022-06-30 2022-06-07 2022-07-19 2022-08-12 2022-07-29 2022-08-12 2022-08-15 2022-09-01 er Mitigation nvelope (1 envelope proce 0 heating network ss) Request for Bids - AFBW1 / Construction of Gre B. Central Ulaanbaatar Parti Single Stage - One E Small Works SPD Pending Imp 2022-08-0 IDA / 64930 Post Request for Bids Open - National 450,000.00 0.00 2022-03-15 2022-03-20 2022-04-22 2022-04-29 2022-05-05 ening facilities culate Matter Mitigation nvelope (1 envelope proce lementation 1 ss) AFCA3-09-1 / Insulation and Request for Quota retrofitting work for kinderga A. Ger Area Particulate Matt Request for Quota Single Stage - One E 2022-12-2 IDA / 64930 Post Limited tions (Non Bank-S 121,000.00 102,298.80 Completed 2022-05-02 2022-05-16 2022-06-27 2022-06-16 rten No 154, 12 khoroo, Chin er Mitigation tions nvelope 4 PD) geltei district, Ulaanbaatar AFCA3-07-1 / Insulation and Request for Quota retrofitting work for kinderga A. Ger Area Particulate Matt Request for Quota Single Stage - One E 2022-12-2 IDA / 64930 Post Limited tions (Non Bank-S 107,000.00 90,654.61 Completed 2022-05-02 2022-05-16 2022-06-27 2022-06-18 rten No 208, 8 khoroo, Nalaik er Mitigation tions nvelope 4 PD) h district, Ulaanbaatar AFB1-05-1 / Thermal renovat Request for Quota ion for precast concrete apar B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E 2022-12-2 IDA / 64930 Post Limited tions (Non Bank-S 112,230.00 106,400.01 Completed 2022-05-02 2022-05-16 2022-06-27 2022-06-18 tment buildings No U-4, 18 k culate Matter Mitigation tions nvelope 4 PD) horoo, Somginokhairkhan dis trict, Ulaanbaatar AFB1-07-1 / Thermal renovat Request for Quota ion for precast concrete apar B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E 2022-12-2 IDA / 64930 Post Limited tions (Non Bank-S 140,890.00 130,319.74 Completed 2022-05-02 2022-05-16 2022-06-27 2022-06-25 tment buildings No 1-58, 19 culate Matter Mitigation tions nvelope 4 PD) khoroo, Songinokhairkhan dis trict, Ulaanbaatar AFB1-08-1 / Thermal renovat Request for Quota ion for precast concrete apar B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E 2022-12-2 IDA / 64930 Post Limited tions (Non Bank-S 112,600.00 104,193.46 Completed 2022-05-02 2022-05-16 2022-06-27 2022-06-25 tment buildings No 2-60, 19 culate Matter Mitigation tions nvelope 4 PD) khoroo, Songinokhairkhan dis trict, Ulaanbaatar AFB1-06-1 / Thermal renovat Request for Quota B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E 2022-12-3 ion for precast concrete apar IDA / 64930 Post Limited tions (Non Bank-S 186,890.00 177,702.27 Completed 2022-05-17 2022-05-16 2022-06-21 2022-06-16 culate Matter Mitigation tions nvelope 1 tment No 2G, 13 khoroo, Bay PD) angol district AFA2-06 / Small work for cut National Procure ting external heating pipeline ment Document - relating to the "Dismantling o A. Ger Area Particulate Matt 2022-07-0 IDA / 64930 Post Direct Selection Direct 1 Envelope proce 7,000.00 9,286.00 Completed 2022-06-28 2022-06-29 2022-06-28 2022-06-27 2022-06-29 2022-07-09 f HOBs and connection to the er Mitigation 5 ss (Non Bank-SPD district heating network in 6t ) h khoroo, Khan-Uul district" Request for Bids - AFB1-06 / Thermal renovatio B. Central Ulaanbaatar Parti Single Stage - One E Small Works SPD 2022-09-3 n for precast concrete apart IDA / 64930 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2022-04-04 2022-04-09 2022-05-21 2022-06-03 2022-06-15 culate Matter Mitigation nvelope (1 envelope proce 0 ment buildings No.. ss) Request for Bids - AFCA2-01 / Supply and instal A. Ger Area Particulate Matt Single Stage - One E Small Works SPD 2022-12-3 lation of geothermal heat pu IDA / 64930 Post Request for Bids Open - National 280,000.00 0.00 Canceled 2022-05-02 2022-05-07 2022-06-13 2022-06-20 2022-07-04 er Mitigation nvelope (1 envelope proce 1 mp system for School/ or kin ss) dergarten No... National Procure AFCA3-11 / Insulation and re ment Document - A. Ger Area Particulate Matt Single Stage - One E Under Imple 2023-08-3 trofitting work for school No IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 360,000.00 0.00 2023-04-03 2023-03-29 2023-04-10 2023-05-10 2023-04-28 2023-05-17 2023-05-05 2023-05-25 er Mitigation nvelope mentation 1 57, Chingeltei district, 11 kho ss (Non Bank-SPD roo ) National Procure AFCA3-10 / Insulation and re ment Document - B. Central Ulaanbaatar Parti Single Stage - One E Under Imple 2023-08-3 trofitting work for school No3 IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 360,000.00 0.00 2023-04-03 2023-03-29 2023-04-10 2023-05-10 2023-04-28 2023-05-17 2023-05-05 2023-05-24 culate Matter Mitigation nvelope mentation 1 9, Chingeltei district, 10 khor ss (Non Bank-SPD oo ) National Procure AFB1-14 / Thermal renovatio ment Document - B. Central Ulaanbaatar Parti Single Stage - One E Pending Imp 2023-09-1 n for precast concrete apart IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 240,000.00 0.00 2023-03-30 2023-04-03 2023-05-03 2023-05-10 2023-05-17 culate Matter Mitigation nvelope lementation 5 ment buildings No ..., .... distr ss (Non Bank-SPD ict, ... khoroo ) National Procure AFBW1-01 / Construction of A. Ger Area Particulate Matt Single Stage - One E ment Document - 2023-09-1 Greening facilities, Chingeltei IDA / 64930 Post Request for Bids Open - National 280,000.00 0.00 Canceled 2023-03-30 2023-04-03 2023-05-03 2023-05-10 2023-05-17 er Mitigation nvelope 1 Envelope proce 5 district, ss (Non Bank-SPD National ) Procure AFCA3-15 / Insulation and re ment Document - A. Ger Area Particulate Matt Single Stage - One E Pending Imp 2023-08-3 trofitting work for kindergart IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 265,000.00 0.00 2023-04-03 2023-04-10 2023-05-10 2023-05-17 2023-05-24 er Mitigation nvelope lementation 1 en No85, Bayanzurkh district, ss (Non Bank-SPD 14 khoroo ) National Procure AFB1-10 / Thermal renovatio ment Document - n for precast concrete apart B. Central Ulaanbaatar Parti Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 245,000.00 0.00 2023-03-30 2023-04-03 2023-05-03 2023-05-10 2023-05-17 ment buildings No 4, Songino culate Matter Mitigation nvelope lementation 5 ss (Non Bank-SPD khairkhan district, 20 khoroo ) National Procure AFB1-13 / Thermal renovatio ment Document - n for precast concrete apart B. Central Ulaanbaatar Parti Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 360,000.00 0.00 2023-03-30 2023-04-03 2023-05-03 2023-05-10 2023-05-17 ment buildings No 23V and 2 culate Matter Mitigation nvelope lementation 5 ss (Non Bank-SPD 3G, Songinokhairkhan district ) , 29 khoroo National Procure AFB1-11 / Thermal renovatio ment Document - n for precast concrete apart B. Central Ulaanbaatar Parti Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 246,000.00 0.00 2023-03-30 2023-04-03 2023-05-03 2023-05-10 2023-05-17 ment buildings No 3, Bayang culate Matter Mitigation nvelope lementation 5 ss (Non Bank-SPD ol district, 13 khoroo ) National Procure AFCA3-12 / Insulation and re ment Document - A. Ger Area Particulate Matt Single Stage - One E Under Imple 2023-08-3 trofitting work for kindergart IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 265,000.00 0.00 2023-04-03 2023-03-27 2023-04-10 2023-05-10 2023-04-28 2023-05-17 2023-05-24 er Mitigation nvelope mentation 1 en No 97, Bayangol district, 7 ss (Non Bank-SPD khoroo ) Page 2 National Procure AFCA3-13 / Insulation and re ment Document - A. Ger Area Particulate Matt Single Stage - One E Pending Imp 2023-08-3 trofitting work for kindergart IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 265,000.00 0.00 2023-04-03 2023-04-10 2023-05-10 2023-05-17 2023-05-24 er Mitigation nvelope lementation 1 en No 151, Nalaikh district, 1 ss (Non Bank-SPD khoroo ) National Procure AFB1-12 / Thermal renovatio ment Document - n for precast concrete apart B. Central Ulaanbaatar Parti Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 360,000.00 0.00 2023-03-30 2023-04-03 2023-05-03 2023-05-10 2023-05-17 ment buildings No 23A and 2 culate Matter Mitigation nvelope lementation 5 ss (Non Bank-SPD 3B, Songinokhairkhan district ) , 29 khoroo National Procure AFCA3-14 / Insulation and re ment Document - A. Ger Area Particulate Matt Single Stage - One E Pending Imp 2023-08-3 trofitting work for kindergart IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 265,000.00 0.00 2023-04-03 2023-04-10 2023-05-10 2023-05-17 2023-05-24 er Mitigation nvelope lementation 1 en No169, Bayanzurkh distric ss (Non Bank-SPD t, 32 khoroo ) National Procure AFA2-07 / Dismantling of HO ment Document - A. Ger Area Particulate Matt Single Stage - One E Pending Imp 2023-09-1 B's and connection to district IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 310,000.00 0.00 2023-03-30 2023-04-03 2023-05-03 2023-05-10 2023-05-17 er Mitigation nvelope lementation 5 heating network ss (Non Bank-SPD ) National Procure AFB1-09 / Thermal renovatio ment Document - n for precast concrete apart B. Central Ulaanbaatar Parti Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 245,000.00 0.00 2023-03-30 2023-04-03 2023-05-01 2023-05-08 2023-05-15 ment buildings No 3, Songino culate Matter Mitigation nvelope lementation 5 ss (Non Bank-SPD khairkhan district, 20 khoroo ) National Procure AFH1 / Thermal Renovation f ment Document - A. Ger Area Particulate Matt Single Stage - One E Pending Imp 2023-10-0 or the public hospital “Nation IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 308,425.00 0.00 2023-05-15 2023-05-20 2023-06-19 2023-06-26 2023-07-05 er Mitigation nvelope lementation 1 al Center for Mental Health” ss (Non Bank-SPD ) National Procure AFCA3-16 / Insulation and re ment Document - A. Ger Area Particulate Matt Single Stage - One E Pending Imp 2023-10-0 trofitting work for school No IDA / 64930 Post Request for Bids Open - National 1 Envelope proce 292,089.00 0.00 2023-06-01 2023-06-05 2023-07-05 2023-07-10 2023-07-20 er Mitigation nvelope lementation 1 77 Bayanzurkh district, 8 kho ss (Non Bank-SPD roo ) AFB1-14-1 / Thermal renovat Request for Quota ion for precast concrete apar B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 199,464.00 0.00 2023-06-19 2023-07-18 tment building #2D, 13 khor culate Matter Mitigation tions nvelope lementation 9 PD) oo, Bayangol district, Ulaanb aatar AFB1-15 / Thermal renovatio Request for Quota n for precast concrete apart B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 159,118.00 0.00 2023-06-19 2023-07-18 ment building #16, 5 khoroo, culate Matter Mitigation tions nvelope lementation 8 PD) Chingeltei district, Ulaanbaat ar AFB1-16 / Thermal renovatio Request for Quota n for precast concrete apart B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 153,988.00 0.00 2023-06-19 2023-07-18 ment building #17, 5 khoroo, culate Matter Mitigation tions nvelope lementation 8 PD) Chingeltei district, Ulaanbaat ar AFB1-17 / Thermal renovatio Request for Quota n for precast concrete apart B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 150,107.00 0.00 2023-06-19 2023-07-18 ment building #18, 5 khoroo, culate Matter Mitigation tions nvelope lementation 8 PD) Chingeltei district, Ulaanbaat ar AFB1-18 / Thermal renovatio Request for Quota n for precast concrete apart B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 100,465.00 0.00 2023-06-19 2023-07-18 ment building #7A, 19 khoro culate Matter Mitigation tions nvelope lementation 8 PD) o, Songinokhairkhan district, Ulaanbaatar AFB1-19 / Thermal renovatio Request for Quota n for precast concrete apart B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 94,874.00 0.00 2023-06-19 2023-07-18 ment building #7B, 19 khoro culate Matter Mitigation tions nvelope lementation 8 PD) o, Songinokhairkhan district, Ulaanbaatar AFB1-20 / Thermal renovatio Request for Quota n for precast concrete apart B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 101,049.00 0.00 2023-06-19 2023-07-18 ment building #7V, 19 khoro culate Matter Mitigation tions nvelope lementation 8 PD) o, Songinokhairkhan district, Ulaanbaatar AFB1-21 / Thermal renovatio Request for Quota n for precast concrete apart B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 191,434.00 0.00 2023-06-19 2023-07-18 ment building #8A, 19 khoro culate Matter Mitigation tions nvelope lementation 8 PD) o, Songinokhairkhan district, Ulaanbaatar AFB1-22 / Thermal renovatio Request for Quota n for precast concrete apart B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 140,446.00 0.00 Canceled 2023-06-19 2023-07-18 ment building #24, 6 khoroo, culate Matter Mitigation tions nvelope 8 PD) Chingeltei district, Ulaanbaat ar AFB1-23 / Thermal renovatio Request for Quota n for precast concrete apart B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 137,433.00 0.00 2023-06-19 2023-07-18 ment building #25, 6 khoroo, culate Matter Mitigation tions nvelope lementation 8 PD) Chingeltei district, Ulaanbaat ar AFB1-24 / Thermal renovatio Request for Quota n for precast concrete apart B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 120,000.00 0.00 2023-06-19 2023-07-18 ment building #14, 18 khoro culate Matter Mitigation tions nvelope lementation 8 PD) o, Songinokhairkhan district, Ulaanbaatar AFB1-25 / Insulation and retr Request for Quota ofitting work for Educational B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-09-1 IDA / 64930 Post Limited tions (Non Bank-S 70,425.00 0.00 2023-06-19 2023-07-18 complex for Children/ "Youth culate Matter Mitigation tions nvelope lementation 8 PD) center"/, 8 khoroo, Bayanzur kh distrcit, Ulaanbaatar AFBW1-02 / Construction of Request for Quota B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-10-0 Greening facilities for the Nat IDA / 64930 Post Limited tions (Non Bank-S 182,663.00 0.00 2023-06-21 2023-07-24 culate Matter Mitigation tions nvelope lementation 1 ional Federation for the Blind PD) AFBW1-03 / Construction of Request for Quota Green facilities for the "Moun B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-10-0 IDA / 64930 Post Limited tions (Non Bank-S 189,053.00 0.00 2023-06-21 2023-07-24 tain Fitness" area, 17 khoroo, culate Matter Mitigation tions nvelope lementation 1 PD) Chingeltei district, Ulaanbaat ar AFB1-22-1 / Thermal renovat Request for Quota B. Central Ulaanbaatar Parti Request for Quota Single Stage - One E Pending Imp 2023-10-0 ion for concrete apartment N IDA / 64930 Post Limited tions (Non Bank-S 162,000.00 0.00 2023-06-28 2023-08-01 culate Matter Mitigation tions nvelope lementation 1 o 16, 1 khoroo, Baganuur dis PD) trict, Ulaanbaatar GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 AFD2-01 / Supply, installatio D. Electricity for heating in t Open - Internationa Single Stage - One E n & after sales service of ETS IDA / 64930 Prior Request for Bids 990,000.00 780,612.00 Completed 2020-08-01 2020-07-27 2020-08-06 2020-07-28 2020-12-15 2020-09-16 2021-01-14 2020-10-06 2021-02-18 2020-10-23 2022-02-18 2022-03-17 argeted ger areas l nvelope heaters and accessary equip ment for rollout AFA3 / Supply of tools and e quipment for the MUB inspec A. Ger Area Particulate Matt Single Stage - One E IDA / 64930 Post Request for Bids Open - National 200,000.00 90,735.05 Completed 2020-08-03 2020-09-03 2020-08-08 2020-09-19 2020-10-02 2020-10-19 2020-10-12 2020-11-23 2020-10-23 2021-05-22 2021-01-16 tion agency for air quality me er Mitigation nvelope asurement and enforcement of new stove standard AFA3-01 / Supply of air quali A. Ger Area Particulate Matt Single Stage - One E ty monitoring stations for MU IDA / 64930 Post Request for Bids Open - National 750,000.00 508,554.41 Completed 2021-02-01 2021-05-13 2021-02-06 2021-03-08 2021-06-18 2021-03-12 2021-07-19 2021-04-01 2021-08-03 2021-06-30 2022-03-18 er Mitigation nvelope B and after sales service /2 s ets/ NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SWHB-01 // IDA 5039-MN / S A. Ger Area Particulate Matt Consultant Qualifi Open - Internationa MALL WATER HEATING BOILE IDA / 50390 Prior 180,000.00 80,409.73 Signed 2014-01-13 2014-02-27 2014-03-21 2014-03-26 2014-04-04 2014-04-05 2014-03-21 er Mitigation cation Selection l R MARKET STUDY Audit Services / Project Fina A. Ger Area Particulate Matt Consultant Qualifi Open - Internationa IDA / 50390 Prior 5,900,000.00 5,692.73 Signed 2014-10-22 2014-07-18 ncial Audit er Mitigation cation Selection l CPLG-01 / CONSULTING SER VICE FOR PREPARATION OF F A. Ger Area Particulate Matt Quality And Cost- Open - Internationa IDA / 50390 Prior 421,312.00 14,920.00 Signed 2015-06-11 2015-06-13 EASIBILITY STUDY OF A CITY er Mitigation Based Selection l GREENING INVESTMENT OF U LAANBAATAR D. Electricity for heating in t Consultant Qualifi AFD4 / ETS M&E IDA / 64930 Post Open - National 100,000.00 109,149.19 Signed 2020-07-06 2020-07-30 2020-07-17 2020-08-09 2020-08-16 2020-08-25 2020-08-30 2020-08-27 2020-09-24 2020-09-01 2021-09-24 argeted ger areas cation Selection AFA1 / Consulting service (d A. Ger Area Particulate Matt Consultant Qualifi etailed design of HOB rid-off IDA / 64930 Post Open - National 100,000.00 0.00 Canceled 2020-06-15 2020-07-06 2020-08-19 2020-09-18 2020-10-23 2021-04-21 er Mitigation cation Selection and connection to district he ating network) AFCA6 / PR and awareness a nd training activities on zero A. Ger Area Particulate Matt Consultant Qualifi IDA / 64930 Post Open - National 80,000.00 89,818.26 Completed 2020-08-10 2020-08-18 2020-08-13 2020-08-30 2020-09-14 2020-08-31 2020-09-23 2020-09-02 2020-09-26 2021-12-02 2022-03-16 carbon & green technology ( er Mitigation cation Selection activity 6 of complementary activities) AFCA5-01 / Study and Desig C. Public Awareness Raising, n of Pilot project for thermal r Consultant Qualifi IDA / 64930 Program Coordination and Pr Post Open - National 70,000.00 41,926.12 Signed 2021-02-19 2021-02-23 2021-03-05 2021-03-15 2021-03-24 2021-03-21 2021-05-18 2021-03-26 2021-05-20 2021-06-30 enovation of precast concret cation Selection oject Management e multiapartment buildings / 2 blocks/ AFA1-02 / Detailed design of A. Ger Area Particulate Matt Consultant Qualifi HOB (dismantling and conne IDA / 64930 Post Open - National 20,000.00 17,331.53 Completed 2021-06-16 2021-06-14 2021-06-29 2021-07-05 2021-07-22 2021-07-09 2021-07-30 2021-07-19 2021-08-03 2021-12-31 2021-10-01 er Mitigation cation Selection ction to district heating netw ork) AFA1-03 / Detailed design of A. Ger Area Particulate Matt Consultant Qualifi HOB dismantling and connec IDA / 64930 Post Open - National 30,000.00 13,770.77 Completed 2022-02-01 2022-05-30 2022-02-15 2022-03-04 2022-06-10 2022-03-16 2022-06-17 2022-03-23 2022-06-30 2022-05-31 2022-11-03 er Mitigation cation Selection tion to district heating netwo rk AFBC1 / Establishment of Gr B. Central Ulaanbaatar Parti Consultant Qualifi Pending Impleme IDA / 64930 Post Open - National 10,000.00 0.00 2022-02-01 2022-02-13 2022-02-24 2022-02-28 2022-03-01 2022-05-02 een facilities culate Matter Mitigation cation Selection ntation AFA1-01 / Detailed design of A. Ger Area Particulate Matt Consultant Qualifi HOB rid-off and connection t IDA / 64930 Post Open - National 100,000.00 0.00 Canceled 2021-02-15 2021-02-25 2021-03-09 2021-03-14 2021-03-23 2021-06-30 er Mitigation cation Selection o district heating network /in two locations/ AFA1-04 / Detailed design of A. Ger Area Particulate Matt Consultant Qualifi HOB rid-off and connection t IDA / 64930 Post Open - National 16,500.00 0.00 Canceled 2023-02-01 2023-02-15 2023-02-17 2023-02-28 2023-03-07 2023-04-21 er Mitigation cation Selection o district heating network AFAC-1 / Consulting service f or the development of geoth A. Ger Area Particulate Matt Consultant Qualifi Under Implement IDA / 64930 Post Open - National 17,500.00 0.00 2023-01-23 2023-01-23 2023-02-06 2023-02-10 2023-02-17 2023-02-24 2023-10-01 ermal heat pump system sta er Mitigation cation Selection ation ndards and general technical requirements AFCA6-01 / PR awareness pr C. Public Awareness Raising, Consultant Qualifi Under Implement ogram for Ulaanbaatar Clean IDA / 64930 Program Coordination and Pr Post Open - National 50,000.00 0.00 2023-03-01 2023-04-26 2023-03-15 2023-03-20 2023-04-03 2023-04-10 2023-12-31 cation Selection ation air project activities oject Management AFCC1 / Consulting service f C. Public Awareness Raising, Consultant Qualifi Under Implement or the preparation for ICR for IDA / 64930 Program Coordination and Pr Post Open - National 60,000.00 0.00 2023-04-03 2023-01-23 2023-04-17 2023-04-21 2023-05-01 2023-05-08 2023-12-24 cation Selection ation both phases of UBCAP oject Management AFAC1 / Detailed design for A. Ger Area Particulate Matt Consultant Qualifi Geothermal heat pump const IDA / 64930 Post Open - National 20,000.00 0.00 Canceled 2022-02-01 2022-02-13 2022-02-20 2022-02-25 2022-03-02 2022-04-01 er Mitigation cation Selection ruction work AFBC2 / Seismic resistance a B. Central Ulaanbaatar Parti Consultant Qualifi nalyze for precast concrete a IDA / 64930 Post Open - National 8,000.00 0.00 Canceled 2022-03-01 2022-03-15 2022-03-21 2022-03-31 2022-04-05 2022-06-05 culate Matter Mitigation cation Selection partment buildings to be ren ovated. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CSMST-01 / Clean Stove Sale A. Ger Area Particulate Matt s, Monitoring and Subsidy Tr IDA / 50390 Prior Direct Selection Direct 40,000.00 17,457.43 Signed 2015-03-19 2015-04-16 er Mitigation ansfer Service Page 4 HSAP-01 / INTERVENTION ST UDY FOR IMPROVEMENT OF A. Ger Area Particulate Matt IDA / 50390 Prior Direct Selection Direct 25,000.00 22,443.45 Signed 2016-02-20 AIR QUALITY IN KINDERGART er Mitigation ENS IN GER AREA OF ULAAN BAATAR CITY C-5039-MN//KLTA-01 / CERA A. Ger Area Particulate Matt IDA / 50390 Prior Direct Selection Direct 70,000.00 96,000.00 Signed 2017-06-13 MIC LINING TECHNICAL ASSIS er Mitigation TANCE SCSU-01 / Survey on househ A. Ger Area Particulate Matt IDA / 50390 Prior Direct Selection Direct 20,000.00 18,937.74 Signed 2017-12-23 old heating appliances er Mitigation AFCPIU-01 / Selection of Indi A. Ger Area Particulate Matt Individual Consult vidual Consultant to Support IDA / 64930 Post Direct 27,940.00 27,718.45 Completed 2020-06-15 2020-05-26 2020-06-25 2020-05-26 2020-07-16 2020-08-20 2020-06-09 2021-02-16 2022-02-02 er Mitigation ant Selection PIU on implementation of pro ject C. Public Awareness Raising, Pending Impleme AFC3 / Audit service IDA / 64930 Program Coordination and Pr Post Direct Selection Direct 15,000.00 0.00 2021-01-04 2021-01-14 2021-03-20 2021-05-04 ntation oject Management AFD1 / Preparation of techni D. Electricity for heating in t Individual Consult IDA / 64930 Post Limited 50,000.00 18,232.76 Completed 2020-06-22 2020-06-22 2020-06-27 2020-06-22 2020-07-18 2020-07-01 2020-08-22 2020-07-02 2021-02-18 2021-05-12 cal specification and BOQ for argeted ger areas ant Selection ETS Page 5