PROCUREMENT PLAN (Textual Part) Project information: Ethiopia, Urban Productive Safety Net and Jobs Project (P169943) Project Implementation agency: Ministry of Labor and Social Affairs (MoLSA), Ministry of Urban Development and Construction (MoUDC), Urban Job Creation and Food Security Agency (UJCFSA) Date of the Procurement Plan: November 2020. Period covered by this Procurement Plan: December 2020 to December 2021. Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 revised August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Section 33(1)(a) from page 35-48 of the Proclamation Number 649/2009 of the Ethiopian Federal Government Procurement and Property Administration Proclamation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. • Open Advertising of the procurement opportunity at the national level; • The procurement is open to eligible firms from any country; • The request for bids/Proposal documents shall require that bidders/proposers submitting Bids/Proposal present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the bank’s right to sanction and the Bank’s inspection and audit right; • Contracts with an appropriate allocation of responsibilities, risks and liabilities; • Application of Standstill period and Publication of contract award information; • Maintenance of records of the procurement process; and • The Bank has the right to review procurement documentation and activities. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Is applicable for those contracts identified in the Procurement Plan; Works: Is applicable for those contracts identified in the Procurement Plan. Other Relevant Procurement Information. None PROCUREMENT Ethiopia : Urban Productive Safety Net and Jobs Project PLAN General Information Country: Ethiopia 2021-08-19 Bank’s Approval Date of the Original Procurement Plan: 2023-06-21 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P169943 GPN Date: 2020-12-18 Project Name: Urban Productive Safety Net and Jobs Project Loan / Credit No: IDA / D7320 SNNPRS Urban Job Creation and Food Security Agency Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned ET-SNNP WOLKETE-324040- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-05-0 CW-RFQ / Semi skill labor for IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 15,000.00 0.00 2022-11-27 2023-01-02 tions nvelope lementation 2 Wolkete city to build social in Urban Environment PD) frastructure ET-SNNP HOSAENA-324052- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-03-1 CW-RFQ / Semi Skill for Socia IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 4,000.00 0.00 2022-11-27 2023-01-02 tions nvelope lementation 8 l Infrastructure in Hosaena Ci Urban Environment PD) ty ET-SNNP HALABA-324060-C Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-03-1 W-RFQ / Semi skill for Social i IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 15,000.00 0.00 2022-11-20 2022-12-26 tions nvelope lementation 1 nfrastructure in Halaba city Urban Environment PD) ET-SNNP DURAME -324065- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-02-0 CW-RFQ / Semi Skill for social IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 2,000.00 0.00 2022-11-15 2022-12-21 tions nvelope lementation 4 infrastructure in Durame city Urban Environment PD) ET-SNNP DILLA -324070-CW- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Under Imple 2023-02-2 RFQ / Semi Skill for Dilla City IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 23,000.00 0.00 2022-11-15 2022-12-14 tions nvelope mentation 7 Social Infrastructure Urban Environment PD) ET-SNNP BUTA JIRA-324075- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-01-1 CW-RFQ / Semi Skill for Socia IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 6,000.00 0.00 2022-11-15 2022-12-14 tions nvelope lementation 3 l Infrastructure for Buta Jira C Urban Environment PD) ity ET-SNNP AREKA 324089-CW- Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-02-1 RFQ / Semi Skill labor for soci IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 3,000.00 0.00 2022-11-20 2022-12-22 tions nvelope lementation 0 al Infrastructure for Areka C Urban Environment PD) ity ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Request for Quota Single Stage - One E Pending Imp 2023-03-0 98-CW-RFQ / Semi skill for so IDA / D7320 e Safety Net to Improve the Post Limited tions (Non Bank-S 35,000.00 0.00 2022-11-26 2023-01-02 tions nvelope lementation 3 cial infrastructures in Arba Mi Urban Environment PD) nch City ET-SNNP SODO UJCFSA-3477 Request for Quota Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Imp 2023-07-1 18-CW-RFQ / Refurbishment IDA / D7320 Post Limited tions (Non Bank-S 62,000.00 0.00 2023-03-16 2023-04-14 ment tions nvelope lementation 3 of arada OSSP in sodo by 2.2 PD) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-SNNP SODO-249201-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of safety IDA / D7320 e Safety Net to Improve the Post Limited 41,431.00 21,535.96 Completed 2021-08-29 2021-11-11 2021-09-29 2021-12-11 2021-10-29 2021-12-15 tions nvelope materials for Sodo city Urban Environment ET-SNNP SODO-249203-GO- Expand the Urban Productiv Request for Quota Single Stage - One E RFQ / Procurement of Hand t IDA / D7320 e Safety Net to Improve the Post Limited 11,199.00 19,146.14 Completed 2021-08-29 2021-11-11 2021-09-29 2021-11-11 2021-10-29 2021-12-21 tions nvelope ools for Sodo city Urban Environment ET-SNNP ARBA MINCH-2492 Expand the Urban Productiv Request for Quota Single Stage - One E 06-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 44,587.00 265.89 Completed 2021-08-29 2021-10-05 2021-09-29 2021-11-09 2021-10-29 2021-11-26 tions nvelope safety materials for Arba min Urban Environment ch city ET-SNNP ARBA MINCH-2492 Expand the Urban Productiv Request for Quota Single Stage - One E 08-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 11,245.00 19,128.13 Completed 2021-08-29 2021-09-28 2021-09-29 2021-11-03 2021-10-29 2021-11-30 tions nvelope Hand tools for Arba minch cit Urban Environment y ET-SNNP HASAINA-249212-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 38,954.00 21,829.68 Completed 2021-08-29 2021-10-29 2021-09-29 2021-11-20 2021-10-29 2021-11-27 tions nvelope y Material for Hosaina city Urban Environment ET-SNNP HOSAINA-249213-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 9,853.00 18,279.83 Completed 2021-08-29 2021-10-29 2021-09-29 2021-11-20 2021-10-29 2021-11-27 tions nvelope tools for Hosaina City Urban Environment ET-SNNP DILLA-249215-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of safety IDA / D7320 e Safety Net to Improve the Post Limited 31,589.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation materials for Dilla city Urban Environment ET-SNNP DILLA-249217-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of hand t IDA / D7320 e Safety Net to Improve the Post Limited 8,597.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation ools for Dilla city Urban Environment ET-SNNP BUTAJIRA-249221- Expand the Urban Productiv Request for Quota Single Stage - One E GO-RFQ / Procurement of Saf IDA / D7320 e Safety Net to Improve the Post Limited 17,709.00 1,241.35 Completed 2021-08-29 2021-11-16 2021-09-29 2021-11-21 2021-10-29 2021-11-27 tions nvelope ety materials for Butajira city Urban Environment ET-SNNP BUTAJIRA-249224- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of ha IDA / D7320 e Safety Net to Improve the Post Limited 5,242.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation nd tools for Butajira city Urban Environment ET-SNNP AREKA-249228-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 34,336.00 0.00 2021-08-29 2021-09-26 2021-10-26 tions nvelope ementation materials for Areka city Urban Environment ET-SNNP AREKA-249232-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Hand t IDA / D7320 e Safety Net to Improve the Post Limited 8,968.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation olls for Areka city Urban Environment Page 1 ET-SNNP WOLKETE-249234- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of saf IDA / D7320 e Safety Net to Improve the Post Limited 31,121.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation ety material for wolkete city Urban Environment ET-SNNP WOLKETE-249236- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of ha IDA / D7320 e Safety Net to Improve the Post Limited 8,275.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation nd tools for wolkete city Urban Environment ET-SNNP HALABA-249239-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 28,065.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation y materials for Halaba city Urban Environment ET-SNNP HALABA-249241-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of hand IDA / D7320 e Safety Net to Improve the Post Limited 7,730.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation tools for Halaba city Urban Environment ET-SNNP TEPI-249245-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of safety ma IDA / D7320 e Safety Net to Improve the Post Limited 26,687.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation terials for Tepi city Urban Environment ET-SNNP TEPI-249247-GO-RF Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Q / Procurement of hand tool IDA / D7320 e Safety Net to Improve the Post Limited 6,842.00 0.00 2021-08-25 2021-09-25 2021-10-25 tions nvelope ementation s for Tepi city Urban Environment ET-SNNP DURAME-249252-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 24,432.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation y materials for Durame city Urban Environment ET-SNNP DURAME-249254-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 6,786.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation tools for Durame city Urban Environment ET-SNNP MIZAN-249260-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 24,883.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation materials for mizan aman cit Urban Environment y ET-SNNP MIZAN-249262-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of hand t IDA / D7320 e Safety Net to Improve the Post Limited 6,406.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation ools for Mizan Aman city Urban Environment ET-SNNP BODITY-249267-GO Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of safety IDA / D7320 e Safety Net to Improve the Post Limited 25,511.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation materials for Bidity city Urban Environment ET-SNNP BODITY-249269-GO Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of hand t IDA / D7320 e Safety Net to Improve the Post Limited 6,716.00 0.00 2021-08-29 2021-09-29 2021-10-29 tions nvelope ementation ools for Bodity City Urban Environment ET-SNNP SAWULA-249271-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 20,193.00 17,587.87 Completed 2021-08-29 2021-11-01 2021-09-29 2021-11-20 2021-10-29 2022-01-13 tions nvelope y materials for Sawula city Urban Environment ET-SNNP SAWULA-249272-G Expand the Urban Productiv Request for Quota Single Stage - One E O-RFQ / Procurement of hand IDA / D7320 e Safety Net to Improve the Post Limited 6,490.00 3,432.53 Completed 2021-08-29 2021-11-01 2021-09-29 2021-11-20 2021-10-29 2022-04-05 tions nvelope tools for sawula city Urban Environment ET-SNNP UJCFSA-324018-GO -RFQ / Procurement of laptop Foster Urban Youth Employ Request for Quota Single Stage - One E computer, printer and Project IDA / D7320 Post Limited 9,230.00 0.00 Canceled 2022-11-09 2022-12-04 2023-01-03 ment tions nvelope or for wolayta sodo city in th e youth apprenticeship progr am ET-SNNP UJCFSA-324019-GO -RFQ / Procurement of office Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Impl IDA / D7320 Post Limited 200.00 0.00 2022-11-13 2022-12-12 2023-01-12 table and chair for Wolayta s ment tions nvelope ementation odo city in the Youth Apprent iceship program ET-SNNP SODO-324021-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of hand t IDA / D7320 e Safety Net to Improve the Post Limited 49,500.00 0.00 2022-11-13 2022-12-12 2023-01-11 tions nvelope ementation ools for Sodo City Urban Environment ET-SNNP SODO-324023-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 98,000.00 0.00 2022-11-13 2022-12-12 2023-01-11 tions nvelope ementation Material for Sodo city Urban Environment ET-SNNP SODO-324024-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Leathe IDA / D7320 e Safety Net to Improve the Post Limited 44,000.00 0.00 2022-11-13 2022-12-12 2023-01-11 tions nvelope ementation r Glove for Sodo city Urban Environment ET-SNNP SODO-324027-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Local C IDA / D7320 e Safety Net to Improve the Post Limited 35,000.00 0.00 2022-11-13 2022-12-12 2023-01-11 tions nvelope ementation onstruction Materials for Sod Urban Environment o city ET-SNNP SODO-324028-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Cerami IDA / D7320 e Safety Net to Improve the Post Limited 49,000.00 0.00 2022-11-13 2022-12-12 2023-01-11 tions nvelope ementation c Tails for sodo city Urban Environment ET-SNNP SODO-324029-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of hollow IDA / D7320 e Safety Net to Improve the Post Limited 8,500.00 0.00 2022-11-13 2022-12-12 2023-01-11 tions nvelope ementation concrete Block and terrazzo Urban Environment ET-SNNP SODO-324030-GO- Expand the Urban Productiv Pending Impl DIR / Procurement of cement IDA / D7320 e Safety Net to Improve the Post Direct Selection Direct - National 87,000.00 0.00 2022-11-21 2022-11-26 2022-12-11 2023-02-09 ementation for Sodo City Urban Environment ET-SNNP SODO-324031-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Tents f IDA / D7320 e Safety Net to Improve the Post Limited 49,000.00 0.00 2022-11-14 2022-12-13 2023-01-12 tions nvelope ementation or child protection for SODO Urban Environment City ET-SNNP WOLKETE-324032- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Ha IDA / D7320 e Safety Net to Improve the Post Limited 7,800.00 0.00 2022-11-13 2022-12-12 2023-01-11 tions nvelope ementation nd tools for wolkete city Urban Environment ET-SNNP WOLKETE-324034- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Saf IDA / D7320 e Safety Net to Improve the Post Limited 49,000.00 0.00 2022-11-13 2022-12-25 2023-01-24 tions nvelope ementation ety Materials for Wolkete City Urban Environment Page 2 ET-SNNP WOLKETE-324036- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Ind IDA / D7320 e Safety Net to Improve the Post Limited 24,380.00 0.00 2022-11-13 2022-12-12 2023-01-11 tions nvelope ementation ustrial Construction materials Urban Environment ET-SNNP WOLKETE-324037- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Loc IDA / D7320 e Safety Net to Improve the Post Limited 41,000.00 0.00 2022-11-13 2022-12-12 2023-01-11 tions nvelope ementation al Construction Materials Urban Environment ET-SNNP SAWULA-324041-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 14,000.00 0.00 2022-11-13 2022-12-12 2023-01-11 tions nvelope ementation Tools for Sawula City Urban Environment ET-SNNP SAWULA-324043-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 52,000.00 0.00 2022-11-14 2022-12-20 2023-01-19 tions nvelope ementation y Materials for Sawula City Urban Environment ET-SNNPSAWULA-324044-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Indu IDA / D7320 e Safety Net to Improve the Post Limited 22,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation strial Construction Materials Urban Environment ET-SNNP SAWULA -324045- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Loc IDA / D7320 e Safety Net to Improve the Post Limited 9,000.00 0.00 2022-11-14 2022-12-13 2023-01-12 tions nvelope ementation al Construction Materials Urban Environment ET-SNNPHOSANA 324047-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of hand IDA / D7320 e Safety Net to Improve the Post Limited 97,000.00 0.00 2022-11-15 2022-12-14 2023-01-26 tions nvelope ementation tools for HOSAENA City Urban Environment ET-SNNP HOSAENA -324048- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Saf IDA / D7320 e Safety Net to Improve the Post Limited 97,500.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation ety Materials Urban Environment ET-SNNP HOSAENA-324050- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Ind IDA / D7320 e Safety Net to Improve the Post Limited 33,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation ustrial Construction Materials Urban Environment ET-SNNP HOSAENA-324051- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Loc IDA / D7320 e Safety Net to Improve the Post Limited 58,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation al Construction materials Urban Environment ET-SNNP HALABA-324053-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 26,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation Tools for Halaba City Urban Environment ET-SNNP HALABA -324055-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 48,000.00 0.00 2022-11-15 2022-12-15 2023-01-14 tions nvelope ementation y Materials for Halaba City Urban Environment ET-SNNP HALABA-324056-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Indu IDA / D7320 e Safety Net to Improve the Post Limited 35,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation strial Construction Materials f Urban Environment or Halaba City ET-SNNP HALABA-324059-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Local IDA / D7320 e Safety Net to Improve the Post Limited 2,000.00 0.00 2022-11-15 2022-12-13 2023-01-12 tions nvelope ementation Construction materials Urban Environment ET-SNNP DURAME-324061-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 60,500.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation Tools for Durame city Urban Environment ET-SNNP DURAME-324062-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 98,000.00 0.00 2022-11-15 2022-12-15 2023-01-14 tions nvelope ementation y Materials for Durame city Urban Environment ET-SNNP DURAME-324063-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Indu IDA / D7320 e Safety Net to Improve the Post Limited 18,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation strial Construction Materials Urban Environment ET-SNNP DURAME -324064- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Loc IDA / D7320 e Safety Net to Improve the Post Limited 3,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation al Construction Material for D Urban Environment urame city ET-SNNP DILLA-324066-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Hand T IDA / D7320 e Safety Net to Improve the Post Limited 65,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation ools for Dilla City Urban Environment ET-SNNP DILLA -324067-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 96,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation Materials Urban Environment ET-SNNP DILLA -324068-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Industr IDA / D7320 e Safety Net to Improve the Post Limited 65,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation ial Construction Materials for Urban Environment Dill City ET-SNNP DILLA -324069-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Local C IDA / D7320 e Safety Net to Improve the Post Limited 40,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation onstruction Materials Urban Environment ET-SNNP BUTAJIRA-324071- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Ha IDA / D7320 e Safety Net to Improve the Post Limited 23,500.00 0.00 2022-11-12 2022-12-11 2023-01-10 tions nvelope ementation nd Tools for Butajira City Urban Environment ET-SNNP BUTAJIRA-324072- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Saf IDA / D7320 e Safety Net to Improve the Post Limited 72,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation ety Materials for Buta jira Cit Urban Environment y ET-SNNP BUTA JIRA -324073- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Ind IDA / D7320 e Safety Net to Improve the Post Limited 41,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation ustrial Construction Material f Urban Environment or Buta Jira City ET-SNNP BUTA JIRA-324074- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of Loc IDA / D7320 e Safety Net to Improve the Post Limited 13,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation al Construction materials for Urban Environment Buta Jira City ET-SNNP BODETE -324078-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 12,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation tools for Bodete Urban Environment Page 3 ET-SNNP BODETE 324079-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Safet IDA / D7320 e Safety Net to Improve the Post Limited 42,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation y Materials for Bodete City Urban Environment ET-SNNP BODETE -324080-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Indu IDA / D7320 e Safety Net to Improve the Post Limited 13,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation strial Construction Materials Urban Environment ET-SNNP BODETE-324082-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of Local IDA / D7320 e Safety Net to Improve the Post Limited 7,000.00 0.00 2022-11-15 2022-12-14 2023-01-13 tions nvelope ementation Construction Materials for Bo Urban Environment dity City ET-SNNP AREKA -324083-GO Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of Hand IDA / D7320 e Safety Net to Improve the Post Limited 12,000.00 0.00 2022-11-15 2022-12-15 2023-01-14 tions nvelope ementation Tools for Areka City Urban Environment ET-SNNP AREKA -324085-GO Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of Safety IDA / D7320 e Safety Net to Improve the Post Limited 63,000.00 0.00 2022-11-15 2022-12-17 2023-01-16 tions nvelope ementation Materials for Areka City Urban Environment ET-SNNPAREKA -324087-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Industr IDA / D7320 e Safety Net to Improve the Post Limited 31,000.00 0.00 2022-11-15 2022-12-17 2023-01-16 tions nvelope ementation ial Construction Materials Urban Environment ET-SNNP AREKA -324088-GO Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl -RFQ / Procurement of Local IDA / D7320 e Safety Net to Improve the Post Limited 7,000.00 0.00 2022-11-16 2022-12-18 2023-01-17 tions nvelope ementation Construction Materials for Ar Urban Environment eka City ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 91-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 38,000.00 0.00 2022-11-19 2022-12-18 2023-01-17 tions nvelope ementation Hand tools for Arba Minch Cit Urban Environment y ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 92-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 96,000.00 0.00 2022-11-19 2022-12-18 2023-01-17 tions nvelope ementation Safety Clothes, hats and Mas Urban Environment ks ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 94-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 52,000.00 0.00 2022-11-19 2022-12-19 2023-01-18 tions nvelope ementation Safety Shoos and Protective Urban Environment gloves ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 95-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 22,000.00 0.00 2022-11-19 2022-12-18 2023-01-18 tions nvelope ementation Industrial Construction Materi Urban Environment als ET-SNNP ARBA MINCH -3240 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 96-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 39,000.00 0.00 2022-11-19 2022-12-21 2023-01-30 tions nvelope ementation local construction Materials Urban Environment ET-SNNP ARBA MINCH-3240 25-GO-RFQ / Procurement of Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl Industrial Construction mater IDA / D7320 e Safety Net to Improve the Post Limited 72,000.00 0.00 2023-01-18 2023-02-16 2023-03-18 tions nvelope ementation ials y for construction of publ Urban Environment ic toilets in Arba Minch city ET-SNNP UJCFSA-334510-GO -RFQ / Procurement of Desk t op computers, laptop comput Foster Urban Youth Employ Request for Quota Single Stage - One E Pending Impl IDA / D7320 Post Limited 76,425.00 0.00 2023-01-18 2023-02-16 2023-03-18 er, printer, and LCD Projector ment tions nvelope ementation for SNNPR Regional Hub and for Sodo city in youth employ ment ET-SNNP- BODETE--355120- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of ind IDA / D7320 e Safety Net to Improve the Post Limited 25,500.00 0.00 2023-06-29 2023-07-28 2023-08-27 tions nvelope ementation ustrial Construction Materials Urban Environment for bodete city ET-SNNP SODO-367412-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of seedlin IDA / D7320 e Safety Net to Improve the Post Limited 30,000.00 0.00 2023-06-29 2023-07-21 2023-08-10 tions nvelope ementation g for Wolayta Sodo City Urban Environment ET-SNNP-WOLKETE-367596- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of See IDA / D7320 e Safety Net to Improve the Post Limited 9,000.00 0.00 2023-06-29 2023-07-26 2023-08-15 tions nvelope ementation dling for Wolkete city Urban Environment ET-SNNP SAWULA-367597-G Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl O-RFQ / Procurement of seed IDA / D7320 e Safety Net to Improve the Post Limited 8,000.00 0.00 2023-06-29 2023-07-28 2023-08-17 tions nvelope ementation lings for sawula city Urban Environment ET-SNNP HOSAENA-367598- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of see IDA / D7320 e Safety Net to Improve the Post Limited 8,000.00 0.00 2023-06-29 2023-08-24 2024-02-20 tions nvelope ementation dling for Hosaena city Urban Environment ET-SNNP HALABA KOLITO-36 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 7600-GO-RFQ / Procurement IDA / D7320 e Safety Net to Improve the Post Limited 9,500.00 0.00 2023-06-28 2023-07-25 2023-08-14 tions nvelope ementation of seedling for Halaba Kolito Urban Environment city ET-SNNP- DURAME-367602- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of see IDA / D7320 e Safety Net to Improve the Post Limited 7,500.00 0.00 2023-06-29 2023-07-26 2023-08-15 tions nvelope ementation dling for Durame city Urban Environment ET-SNNP -DILLA-367603-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of seedlin IDA / D7320 e Safety Net to Improve the Post Limited 8,000.00 0.00 2023-06-29 2023-07-26 2023-08-15 tions nvelope ementation gs for Dilla city Urban Environment ET-SNNP- BUTAJIRA-367604- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of see IDA / D7320 e Safety Net to Improve the Post Limited 9,000.00 0.00 2023-06-29 2023-07-26 2023-08-15 tions nvelope ementation dlingd for butajira Urban Environment ET-SNNP - BODETE-367606- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl GO-RFQ / Procurement of see IDA / D7320 e Safety Net to Improve the Post Limited 2,500.00 0.00 2023-06-29 2023-07-26 2023-08-15 tions nvelope ementation dling for Bodete City Urban Environment ET-SNNP- ARBA MINCH-3676 Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl 08-GO-RFQ / Procurement of IDA / D7320 e Safety Net to Improve the Post Limited 25,000.00 0.00 2023-06-29 2023-07-26 2023-08-15 tions nvelope ementation seedling for Arba Minch city Urban Environment ET-SNNP-AREKA-367613-GO- Expand the Urban Productiv Request for Quota Single Stage - One E Pending Impl RFQ / Procurement of Seedlin IDA / D7320 e Safety Net to Improve the Post Limited 2,500.00 0.00 2023-06-29 2023-07-26 2023-08-15 tions nvelope ementation g for Areka city Urban Environment Page 4 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-SNNP UJCFSA-248275-CS- Institutional Strengthening, INDV / Recruitment of Public Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Open 5,600.00 0.00 2021-08-20 2021-09-23 2021-10-08 2021-11-02 2022-11-02 work specialist with ability to ant Selection ntation nitoring and Evaluation handle Lively hood ET-SNNP UJCFSA-248272-CS- Institutional Strengthening, INDV / Recruitment of individ Individual Consult Pending Impleme IDA / D7320 Project Management and Mo Post Open 5,600.00 0.00 2021-09-06 2021-10-10 2021-10-20 2021-11-14 2022-11-14 ual consultant/ Safeguard sp ant Selection ntation nitoring and Evaluation ecialist for SNNPRS Regional hub ET-SNNP UJCFSA-324014-CS- Institutional Strengthening, Individual Consult Under Implement INDV / Recruitment of procur IDA / D7320 Project Management and Mo Post Limited 5,000.00 0.00 2022-11-07 2023-01-04 2022-11-12 2022-12-03 2022-12-28 2023-12-28 ant Selection ation ement Specialist for SNNP Re nitoring and Evaluation gional Hub ET-SNNP UJCFSA-324015-CS- Institutional Strengthening, Individual Consult Under Implement INDV / Recruitment of Gende IDA / D7320 Project Management and Mo Post Open - National 5,000.00 0.00 2022-11-07 2023-01-04 2022-12-12 2022-12-22 2023-01-23 2024-01-23 ant Selection ation r Specialist for SNNP regional nitoring and Evaluation Hub ET-SNNP UJCFSA-324016-CS- Institutional Strengthening, Individual Consult Under Implement INDV / Recruitment of safegu IDA / D7320 Project Management and Mo Post Open - National 5,000.00 0.00 2022-11-07 2023-01-04 2022-12-12 2022-12-27 2023-01-27 2024-01-27 ant Selection ation ard Specialist for SNNP Regio nitoring and Evaluation nal Hub ET-SNNP UJCFSA-324017-CS- INDV / Recruitment of Youth Foster Urban Youth Employ Individual Consult Under Implement IDA / D7320 Post Open - National 4,000.00 0.00 2022-11-07 2023-01-04 2022-12-12 2022-12-27 2023-01-27 2024-01-27 Employment apprenticeship ment ant Selection ation specialist for Wolayta Sodo C ity ET-SNNP UJCFSA-324020-CS- INDV / Recruitment of Public Institutional Strengthening, Individual Consult Under Implement Work Specialist with assignm IDA / D7320 Project Management and Mo Post Open - National 5,000.00 0.00 2022-11-07 2023-01-04 2022-12-27 2023-01-11 2023-02-11 2024-02-11 ant Selection ation ent to handle the Livelihood nitoring and Evaluation component for SNNP Regiona l hub Page 5