IN: Ecosystem Service Improvement Project (ESIP) (P133803) I. General 1. Bank’s approval Date of the procurement Plan: [Original: May 19, 2017] 2. Date of General Procurement Notice: June 9, 2016 3. Period covered by this procurement plan: The procurement period of project covered from year May 19,2017 to November 30, 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. ICB and LIB (Goods) Above US$ 2 million All 2. NCB (Goods) Above US$2 million All 3. ICB (Works) Above US$ 10 million All 4. NCB (Works) Above US$ 10 million All 5. (Non-Consultant Services) Below US$ 2 million All [Add other methods if necessary] Procurement Methods and Threshold Category Method of Threshold (US$ Equivalent) Procurement Goods and Non- ICB >3,000,000 consultant services LIB Wherever agreed by the Bank NCB Up to 3,000,000 (with NCB conditions) Shopping Up to 100,000 DC As per Para 3.7 of the Bank Guidelines Force Account As per Para 3.9 of Guidelines Framework As per Para 3.6 of Guidelines Agreements October 12, 2017 Works ICB >40,000,000 NCB Up to 40,000,000 (with NCB conditions) Shopping Up to 200,000 Force Account As per Para 3.9 of Guidelines DC As per Para 3.7 of Guidelines Community As per Para 3.19 of Guidelines Participation Prior Review by the Bank. The Bank will prior review the following contracts: • Works (including turnkey, Supply & Installation of plant and equipment and PPP): all contracts more than US$ 10 million equivalent; and • Goods (including information technology and non-consulting services): all contracts more than US$ 2 million equivalent. There is no separate prior review threshold for direct contract and therefore, the same review threshold will apply to direct contract for goods, works and non-consulting services. The above prior review thresholds are revised as per the instructions issued while launching of New Procurement Framework (NPF) July 2016. All contracts below the specified prior review threshold value shall be subject to Post Procurement Review (PPR). In addition, Bank shall be entitled to conduct, at any time, Independent Procurement Review (IPR) of all the contracts financed under the Grant. In both the cases, the IAs shall prepare lists of contract and submit it to the Bank for conducting PPR/IPR. The PPR will be conducted on annual basis. All contracts not covered under prior review will be subject to post review during supervision missions, and/or review by consultants to be appointed by the by Bank. 2. Pre-qualification. Note applicable 3. Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: It is envisaged that there will be some form of community participation activities in this project. If anything of that sort arises, it will be done as per para 3.19 of Procurement guidelines. 4. Reference to (if any) Project Operational/Procurement Manual: The Project has prepared project Operations Manual (OM) that contains a Chapter on Procurement procedures to be adopted for the project. The OM was reviewed and agreed by the Bank to be used as a guidance note while conducting project procurement. All the contracts issued under the project will follow the World Bank’s Guidelines: Bank’s “Guidelines: Procurement under IBRD Loans and IDA Credits” dated October 12, 2017 January 2011and revised in July 2014and “Guidelines: Selection and Employment of Consultants by World Bank Borrowers” dated January 2011 and revised in July 2014. In case of any inconsistencies between the Project Operation Manual and Bank’s Procurement Guidelines, the later shall prevail. 5. Any Other Special Procurement Arrangements: Procurement of goods, works and non-consulting services shall be conducted through state’s e-procurement portal using Bank’s standard biding documents. The e-portal was assessed and cleared by the Bank. International Competitive Bidding (ICB) is the preferred method for procurement of goods, works and non-consulting services. However, it is unlikely that there will be any ICB contract. All National Competitive Bidding (NCB) shall be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines. In addition, following additional provisions as agreed with GOI task force (as amended from time to time) shall apply: • Only the model bidding documents for NCB as agreed with the GoI Task Force (and as amended from time to time), shall be used for bidding; • Invitation to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; • No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprise from any given State; • Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; • For prior review contracts, extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstance beyond the control of the Purchaser/Employer); October 12, 2017 • For prior review contracts, re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank; • The system of rejecting bids outside a pre-determined margin or “bracket” of prices shall not be used in the project; • Rates contract entered into by Directorate General of Supplies and Disposal (DGS & D) will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however, for any procurement under the Shopping procedure; • Two or three envelop system will not be used (expect when suing e-procurement system assessed and agreed by the Bank. To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders, in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders. On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned; 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness: Available in STEP III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comment Threshold 1. Competitive Methods (Firms) Above US$ 1 million All contracts 2. Single Source (Firms) Above US$ 1 million All contracts 3. Individual Above US$ 300,000 All contracts 4 CQS Up to US$ 300,000 All contracts 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None October 12, 2017 4. Consultancy Assignments with Selection Methods and Time Schedule: Available in STEP October 12, 2017 PROCUREMENT India : India Ecosystems Service Improvement Project PLAN General Information Country: India 2017-10-17 Bank’s Approval Date of the Original Procurement Plan: 2023-06-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P133803 GPN Date: Project Name: India Ecosystems Service Improvement Project Loan / Credit No: TF / A3990 Indian Council of Forestry Research and Education Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned IN-ICFRE-42836-CW-RFB / M aintenance works (whitewash ing/painting and minor repair Scaling-up Sustainable Land Single Stage - One E 2018-05-0 s, replacement of old fluores TF / A3990 and Ecosystem Management Post Request for Bids Limited 6,200.00 3,585.86 Completed 2018-04-09 2018-05-10 2018-04-14 2018-05-10 2018-04-22 2018-05-22 2018-04-23 2018-05-23 2018-04-28 2018-06-01 nvelope 7 cent tube lights with new LE in Selected Landscapes D light fixtures and fan etc.) f or renovation of the office of ESIP-PIU at ICFRE. IN-ICFRE-156606-CW-RFQ / Deepening of a pond at Naya Scaling-up Sustainable Land gaon village of Banapura For Request for Quota Single Stage - One E 2020-07-1 TF / A3990 and Ecosystem Management Post Limited 4,500.00 3,516.89 Completed 2020-03-04 2020-03-04 2020-04-10 2020-07-02 est Range (MP) for rain water tions nvelope 3 in Selected Landscapes harvesting and augmentation of water resources for upscali ng of SLEM best practices IN-ICFRE-156601-CW-RFQ / Deepening of a pond and con struction of waste weirs at Ka Scaling-up Sustainable Land Request for Quota Single Stage - One E 2020-07-1 chhar village of Bhoura Fores TF / A3990 and Ecosystem Management Post Limited 10,000.00 6,680.33 Completed 2020-03-04 2020-03-04 2020-04-10 2020-06-26 tions nvelope 3 t Range (MP) for rain water h in Selected Landscapes arvesting and augmentation of water resources for upscali ng of SLEM best practices IN-ICFRE-156594-CW-RFQ / Deepening of three ponds an d construction of waste weirs Scaling-up Sustainable Land Request for Quota Single Stage - One E 2020-07-1 at Banbaheda village of Bhou TF / A3990 and Ecosystem Management Post Limited 12,000.00 8,291.95 Completed 2020-03-04 2020-03-04 2020-04-10 2020-06-26 tions nvelope 3 ra Forest Range (MP) for rain in Selected Landscapes water harvesting and augme ntation of water resources fo r upscaling of SLEM best prac tices IN-ICFRE-156637-CW-RFQ / Deepening of four ponds at T hiatola (Rumga), Matiadand Scaling-up Sustainable Land and Amaratikra villages of M Request for Quota Single Stage - One E 2020-07-1 TF / A3990 and Ecosystem Management Post Limited 28,000.00 17,750.10 Completed 2020-03-04 2020-03-04 2020-04-10 2020-06-27 arwahi Forest Range of Chha tions nvelope 3 in Selected Landscapes ttisgarh for rain water harves ting and augmentation of wa ter resources for upscaling of SLEM best practices IN-ICFRE-156607-CW-RFQ / Deepening of a pond at Pipar Scaling-up Sustainable Land iyakhurd viillage of Sukhtawa Request for Quota Single Stage - One E 2020-07-1 TF / A3990 and Ecosystem Management Post Limited 8,500.00 5,801.97 Completed 2020-03-04 2020-03-04 2020-04-10 2020-06-26 Forest Range (MP) for rain w tions nvelope 3 in Selected Landscapes ater harvesting and augment ation of water resources for u pscaling of SLEM best practic es IN-ICFRE-156604-CW-RFQ / Deepening of one pond and c onstruction of waste weirs at Scaling-up Sustainable Land Request for Quota Single Stage - One E 2020-07-1 Kuppa village of Bhoura Fore TF / A3990 and Ecosystem Management Post Limited 13,500.00 8,992.91 Terminated 2020-03-04 2020-03-04 2020-04-10 2020-06-26 tions nvelope 3 st Range (MP) for rain water in Selected Landscapes harvesting and augmentation of water resources for upscali ng of SLEM best practices IN-ICFRE-156609-CW-RFQ / Deepening of a ponds at Saiy adganj village of Itarsi Forest Range (MP) for rain water har Scaling-up Sustainable Land Request for Quota Single Stage - One E 2020-07-1 vesting and augmentation of TF / A3990 and Ecosystem Management Post Limited 20,500.00 14,672.64 Completed 2020-03-04 2020-03-04 2020-04-10 2020-07-13 tions nvelope 3 water resources for upscaling in Selected Landscapes of SLEM best practices. Climate proofing fish farming pond at Chchmaou village of Itarsi Forest Range (MP) IN-ICFRE-156599-CW-RFQ / Deepening of a pond and co nstruction of waste weir at T Scaling-up Sustainable Land Request for Quota Single Stage - One E 2020-07-1 etarmal village of Bhoura For TF / A3990 and Ecosystem Management Post Limited 5,500.00 3,593.75 Completed 2020-03-04 2020-03-04 2020-04-10 2020-06-26 tions nvelope 3 est Range (MP) for rain water in Selected Landscapes harvesting and augmentation of water resources for upscali ng of SLEM best practices IN-ICFRE-156638-CW-RFQ / Deepening of three ponds an d construction of waste wier at Shankarpur, Rameshpur a Scaling-up Sustainable Land Request for Quota Single Stage - One E 2020-07-1 nd Babhni villages of Raghun TF / A3990 and Ecosystem Management Post Limited 27,000.00 16,711.34 Completed 2020-03-04 2020-03-04 2020-04-10 2020-06-24 tions nvelope 3 athnagar Forest Range of Ch in Selected Landscapes hattisgarh for rain water harv esting and augmentation of water resources for upscaling of SLEM best practices IN-ICFRE-156635-CW-RFQ / Climate Proofing Fish Farmin Scaling-up Sustainable Land Request for Quota Single Stage - One E 2020-07-1 g at Bansital village of Marwa TF / A3990 and Ecosystem Management Post Limited 6,000.00 3,715.59 Completed 2020-03-04 2020-03-04 2020-04-10 2020-06-24 tions nvelope 3 hi Forest Range (Chhattisgar in Selected Landscapes h) for upscaling of SLEM best practices IN-ICFRE-156608-CW-RFQ / Deepening of two ponds at L Scaling-up Sustainable Land alpani village of Itarsi Forest Request for Quota Single Stage - One E 2020-07-1 TF / A3990 and Ecosystem Management Post Limited 8,500.00 5,926.00 Completed 2020-03-04 2020-03-04 2020-04-10 2020-06-26 Range (MP) for rain water har tions nvelope 3 in Selected Landscapes vesting and augmentation of water resources for upscaling of SLEM best practices Page 1 IN-ICFRE-156597-CW-RFQ / Deepening of two ponds at K Scaling-up Sustainable Land oylabuddi village of Bhoura F Request for Quota Single Stage - One E 2020-07-1 TF / A3990 and Ecosystem Management Post Limited 22,000.00 14,428.89 Completed 2020-03-04 2020-03-04 2020-04-10 2020-06-26 orest Range (MP) for rain wat tions nvelope 3 in Selected Landscapes er harvesting and augmentat ion of water resources for up scaling of SLEM best practice s IN-ICFRE-156605-CW-RFQ / Deepening of four ponds and construction of waste weirs a Scaling-up Sustainable Land t Baspani and Pipalgota villag Request for Quota Single Stage - One E 2020-07-1 TF / A3990 and Ecosystem Management Post Limited 21,000.00 17,170.54 Completed 2020-03-04 2020-03-04 2020-04-10 2020-07-02 es of Banapura Forest Range tions nvelope 3 in Selected Landscapes (MP) for rain water harvestin g and augmentation of water resources for upscaling of SL EM best practices IN-ICFRE-215709-CW-RFQ / F Strengthen Capacity of Gove encing of the carbon flux tow rnment Institutions in Forest Request for Quota Single Stage - One E 2021-10-0 er site alongwith constructio TF / A3990 ry and Land Management Pr Post Open - National 22,000.00 16,841.53 Completed 2021-02-07 2021-01-30 2021-04-04 2021-03-24 tions nvelope 1 n of temporary security hut ograms in Madhya Pradesh a at carbon flux installation sit nd Chhattisgarh e in Chhattisgarh IN-ICFRE-215710-CW-RFQ / F Strengthen Capacity of Gove encing of the carbon flux tow rnment Institutions in Forest Request for Quota Single Stage - One E 2021-10-0 er site alongwith constructio TF / A3990 ry and Land Management Pr Post Open - National 22,000.00 12,836.25 Completed 2021-02-07 2021-01-30 2021-04-04 2021-03-24 tions nvelope 1 n of temporary security hut ograms in Madhya Pradesh a at carbon flux installation sit nd Chhattisgarh e in Madhya Pradesh IN-ICFRE-327549-CW-RFQ / Maintenance of waste weirs Scaling-up Sustainable Land Request for Quota Request for Quota Single Stage - One E 2023-03-3 of rain water harvesting pond TF / A3990 and Ecosystem Management Post Open - National tions (Non Bank-S 12,000.00 0.00 Signed 2022-11-30 2022-11-23 2023-01-25 tions nvelope 1 s for ground water augmenta in Selected Landscapes PD) tion in the project areas of M P (04 ponds) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ICFRE-41797-GO-RFQ / Pr ocurement of office equipme nt (Desktop 15, Laptop 08, U Scaling-up Sustainable Land PS 15, Printer Laserjet 8, Sca Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 48,000.00 35,644.93 Completed 2018-01-17 2018-01-18 2018-03-14 2018-04-20 2018-09-10 2018-08-01 nner 1, Photocopier 1, LED Di tions nvelope in Selected Landscapes splay Panel 4, Telephone Con nection & Fax 1, and WiFi mo dem/connections 4) for settin g up of PIU at ICFRE for initi ation of ESIP. IN-ICFRE-42831-GO-RFQ / Of fice furniture (executive chair -18, conference table -1, exe Scaling-up Sustainable Land cutive table - 4, computer ch Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 16,000.00 10,884.88 Completed 2018-01-24 2018-01-18 2018-03-21 2018-04-23 2018-09-17 2018-06-25 air - 5, computer table - 5, b tions nvelope in Selected Landscapes ook shelf - 4, filing cabinet - 4) are essentially required fo r setting up of ESIP Impleme nting Unit at ICFRE Hqs. IN-ICFRE-42840-GO-RFQ / Pr ocurement of various office s tationery items (photocopy p Scaling-up Sustainable Land aper, file folders, note sheets Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 3,100.00 0.00 Canceled 2018-01-30 2018-06-30 2018-02-12 2018-02-23 , file boards etc.) and other tions nvelope in Selected Landscapes miscellaneous items (printer cartridges, etc.) are require f or establishing the PIU office and initiation of the project w orks. IN-ICFRE-63322-GO-RFQ / Pr ocurement of 1) Microsoft Off Scaling-up Sustainable Land Request for Quota Single Stage - One E ice Professional Software for TF / A3990 and Ecosystem Management Post Open - National 7,000.00 4,365.70 Completed 2018-06-09 2018-07-09 2018-08-04 2019-02-15 2019-01-31 2019-03-30 tions nvelope multiple computers and 2) A in Selected Landscapes ntivirus software for multiple computers IN-ICFRE-63329-GO-RFQ / Pr Scaling-up Sustainable Land ocurement of technical equi Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 6,500.00 3,187.46 Completed 2018-06-09 2018-06-30 2018-08-04 2019-03-20 2019-01-31 2019-03-30 pment: GPS 2, Digital SLR Ca tions nvelope in Selected Landscapes mera 4, and Handy-cam 1 IN-ICFRE-66932-GO-RFQ / Pr ocurement of Window Air Co Scaling-up Sustainable Land nditioner (4 Nos.) for the offi Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 3,000.00 1,626.64 Completed 2018-06-27 2018-07-09 2018-08-22 2019-02-07 2019-02-18 2019-03-15 ce of ESIP-PIU as existing old tions nvelope in Selected Landscapes Air Conditioners are not funct ioning properly and replacem ent of the same is needed. IN-ICFRE-151553-GO-RFQ / P Investments for Improving F rocurement of two Forestry P Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 4,000.00 804.92 Completed 2020-01-20 2020-02-05 2020-02-24 2020-02-19 2020-03-31 2020-03-09 ro Hypsometer Laser Range tions nvelope dscapes Finder and two spherical cro wn densitometer IN-ICFRE-153092-GO-RFQ / T raining/workshop kits (with b ag, note book and pen) 2000 Investments for Improving F nos. are required for the part Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 20,000.00 0.00 Canceled 2020-01-22 2020-02-24 2020-03-31 icipants of training program tions nvelope dscapes mes and workshops to be org anised under ESIP on forest c arbon stocks measurement a nd on SLEM best practices. IN-ICFRE-150868-GO-RFQ / P rocurement of office equipm Request for Quota Single Stage - One E TF / A3990 Project Management Post Limited 20,000.00 12,910.48 Completed 2020-03-11 2020-03-12 2020-04-15 2020-05-21 2020-05-22 2020-07-03 ent (Tablet-08, Multimedia pr tions nvelope ojector-02, Laptop-05, Printer -03) IN-ICFRE-151550-GO-RFQ / P rocurement of office furnitur e (office table 3 No., executiv Request for Quota Single Stage - One E TF / A3990 Project Management Post Limited 3,200.00 2,951.15 Completed 2020-03-11 2020-03-06 2020-04-15 2020-05-05 2020-05-22 2020-06-09 e chair 05 No. and visitor Cha tions nvelope irs 10 No.) for the ESIP field U nit at TFRI, Jabalpur (MP) and for ESIP-pIU at ICFRE. Page 2 IN-ICFRE-151554-GO-RFB / P rocurement and installation o f two Eddy Co-variance Syste ms with towers for measure Investments for Improving F Single Stage - Two E ment of forest carbon flux in TF / A3990 orest Quality in Selected Lan Post Request for Bids Open - National 400,000.00 363,992.57 Completed 2020-05-22 2020-05-15 2020-05-27 2020-05-15 2020-07-08 2020-06-30 2020-09-20 2020-08-11 2020-10-25 2020-09-26 2021-04-23 2021-04-01 nvelope the state of Chhattisgarh an dscapes d Madhya Pradesh. Training t o the staff of ICFRE and State Forest Department of Chhatti sgarh and Madhya Pradesh. IN-ICFRE-180819-GO-RFQ / P Scaling-up Sustainable Land Request for Quota Single Stage - One E rocurement of brood lac inse TF / A3990 and Ecosystem Management Post Open - National 26,000.00 20,417.01 Completed 2020-06-28 2020-06-22 2020-08-23 2020-07-23 2021-02-19 2020-12-22 tions nvelope cts (3700 kg) including trans in Selected Landscapes portation charges IN-ICFRE-180823-GO-RFQ / P Scaling-up Sustainable Land Request for Quota Single Stage - One E rocurement of miscellaneous TF / A3990 and Ecosystem Management Post Open - National 32,000.00 22,024.51 Completed 2020-06-28 2020-06-22 2020-08-23 2020-07-23 2021-02-19 2020-12-22 tions nvelope tools and items required for l in Selected Landscapes ac cultivation IN-ICFRE-198915-GO-RFQ / P Request for Quota Single Stage - One E TF / A3990 Project Management Post Open - National 3,500.00 1,682.12 Completed 2020-11-21 2020-11-06 2021-01-16 2020-12-03 2021-07-15 2021-01-21 rocurement of one 5KVA onli tions nvelope ne UPS IN-ICFRE-209680-GO-RFQ / P Request for Quota Single Stage - One E TF / A3990 Project Management Post Limited 1,000.00 588.72 Completed 2021-01-02 2021-01-08 2021-02-27 2021-01-09 2021-08-26 2021-03-24 rocurement of office furnitur tions nvelope e IN-ICFRE-216697-GO-RFQ / P rocurement of one PTZ Cam Request for Quota Single Stage - One E TF / A3990 Project Management Post Open - National 4,000.00 3,057.38 Completed 2021-02-13 2021-02-08 2021-04-10 2021-03-19 2021-10-07 2021-03-31 era and one conference phon tions nvelope e for video conferencing IN-ICFRE-220281-GO-RFQ / P rocurement of Arc GIS Deskt Investments for Improving F Request for Quota Single Stage - One E op Advanced 10.8 with Exten TF / A3990 orest Quality in Selected Lan Post Open - National 35,000.00 30,566.35 Completed 2021-03-06 2021-02-27 2021-05-01 2021-03-19 2021-10-28 2021-03-31 tions nvelope sion - tools Geo Statistical An dscapes alyst 10.8 and Spatial Analys t 10.8 Software IN-ICFRE-220294-GO-RFQ / P Investments for Improving F rocurement of ERDAS Profess Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Open - National 30,000.00 24,128.91 Completed 2021-03-06 2021-02-26 2021-05-01 2021-03-19 2021-10-28 2021-03-31 ional Version 20 or latest wit tions nvelope dscapes h IMAGINE Expansion Pack S oftware IN-ICFRE-220304-GO-RFQ / P Investments for Improving F rocurement of SYSTAT Versio Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Open - National 3,000.00 1,206.45 Completed 2021-03-06 2021-02-27 2021-05-01 2021-03-19 2021-10-28 2021-03-31 n 13.2 software required for tions nvelope dscapes processing of Carbon Flux da ta IN-ICFRE-220305-GO-RFQ / P Investments for Improving F Request for Quota Single Stage - One E TF / A3990 Post Open - National 10,000.00 7,352.00 Completed 2021-03-06 2021-03-01 2021-05-01 2021-03-19 2021-10-28 2021-09-01 rocurement of two Workstati orest Quality in Selected Lan tions nvelope ons dscapes IN-ICFRE-220311-GO-RFQ / P Scaling-up Sustainable Land rocurement of Two Rack Serv Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 70,000.00 28,303.21 Completed 2021-03-06 2021-02-25 2021-05-01 2021-03-19 2021-10-28 2021-09-01 ers and One Hardware-Based tions nvelope in Selected Landscapes Web Application Firewall (WA F) IN-ICFRE-222797-GO-RFQ / P Request for Quota Single Stage - One E rocurement of executive des TF / A3990 Project Management Post Limited 3,000.00 1,755.78 Completed 2021-03-15 2021-03-10 2021-05-10 2021-03-25 2021-11-06 2021-08-26 tions nvelope k with accessories IN-ICFRE-222800-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Air conditioner TF / A3990 Project Management Post Limited 2,400.00 1,608.14 Completed 2021-03-15 2021-03-15 2021-05-10 2021-03-27 2021-11-06 2021-06-09 tions nvelope s (3 nos.) for office of ESIP-PI U IN-ICFRE-222804-GO-RFQ / P Request for Quota Single Stage - One E rocurement of office tables a TF / A3990 Project Management Post Limited 2,100.00 2,135.76 Completed 2021-03-15 2021-03-10 2021-05-10 2021-03-23 2021-11-06 2021-04-01 tions nvelope nd chairs for consultants IN-ICFRE-222806-GO-RFQ / P Request for Quota Single Stage - One E TF / A3990 Project Management Post Limited 1,600.00 0.00 Canceled 2021-03-15 2021-05-10 2021-11-06 rocurement of DSLR camera tions nvelope IN-ICFRE-222990-GO-RFQ / P Request for Quota Single Stage - One E rocurement of LED display pa TF / A3990 Project Management Post Limited 1,200.00 527.94 Completed 2021-03-17 2021-03-15 2021-05-12 2021-03-27 2021-11-08 2021-07-08 tions nvelope nel for online conferencing a nd meetings IN-ICFRE-222996-GO-RFQ / P Scaling-up Sustainable Land rocurement of Training kits f Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Limited 12,500.00 9,276.74 Completed 2021-03-17 2021-03-10 2021-05-12 2021-03-23 2021-11-08 2021-04-01 or beneficiaries of the trainin tions nvelope in Selected Landscapes g programmes to be organis ed on SLEM upscaling IN-ICFRE-249352-GO-RFQ / P Scaling-up Sustainable Land urchase of Brood Lac (Range Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 99,500.00 54,661.64 Completed 2021-09-11 2021-09-02 2021-11-06 2021-10-19 2022-01-13 2022-03-24 eni strain for Baisakhi Crop) tions nvelope in Selected Landscapes along with nylon mesh & rop e IN-ICFRE-249361-GO-RFQ / P Scaling-up Sustainable Land Request for Quota Single Stage - One E urchase of Improved Cook St TF / A3990 and Ecosystem Management Post Open - National 99,500.00 62,790.63 Completed 2021-09-07 2021-09-06 2021-11-02 2021-10-20 2022-05-01 2021-12-29 tions nvelope oves (ICS) for ESIP areas of M in Selected Landscapes adhya Pradesh IN-ICFRE-249363-GO-RFQ / P Scaling-up Sustainable Land Request for Quota Single Stage - One E urchase of Improved Cook St TF / A3990 and Ecosystem Management Post Open - National 99,500.00 54,322.84 Completed 2021-09-07 2021-09-06 2021-11-02 2021-10-20 2022-05-01 2022-01-18 tions nvelope oves (ICS) for ESIP areas of C in Selected Landscapes hhattisgarh IN-ICFRE-252948-GO-RFQ / P Scaling-up Sustainable Land urchase of High-Density Polyt Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Limited 99,500.00 96,596.14 Completed 2021-09-25 2021-09-23 2021-11-20 2021-11-18 2022-05-19 2022-03-30 hene Vermi Beds for ESIP are tions nvelope in Selected Landscapes as of Madhya Pradesh IN-ICFRE-252950-GO-RFQ / P Scaling-up Sustainable Land urchase of High-Density Polyt Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Limited 80,000.00 72,757.28 Completed 2021-09-25 2021-09-23 2021-11-20 2021-11-18 2022-05-19 2022-03-22 hene Vermi Beds for ESIP are tions nvelope in Selected Landscapes as of Chhattisgarh IN-ICFRE-253408-GO-RFQ / P Scaling-up Sustainable Land urchase of Earthworms for ve Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Limited 50,000.00 22,079.82 Completed 2021-10-05 2021-10-11 2021-11-30 2022-01-11 2022-05-29 2022-08-10 rmicomposting in ESIP areas tions nvelope in Selected Landscapes of Madhya Pradesh IN-ICFRE-253409-GO-RFQ / P Scaling-up Sustainable Land Request for Quota Single Stage - One E urchase of earthworms for ve TF / A3990 and Ecosystem Management Post Limited 40,000.00 16,630.77 Completed 2021-10-05 2021-10-11 2021-11-30 2022-01-11 2022-05-29 2022-03-30 tions nvelope rmicomposting in ESIP areas in Selected Landscapes of Chhattisgarh Page 3 IN-ICFRE-260145-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Desktop Comp TF / A3990 Project Management Post Open - National 10,000.00 8,013.56 Completed 2021-11-27 2021-12-13 2022-01-22 2022-01-07 2022-03-31 2022-02-24 tions nvelope uters (06 Nos.) Scaling-up Sustainable Land IN-ICFRE-266898-GO-RFQ / P Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Limited 7,000.00 0.00 Canceled 2021-12-18 2021-12-10 2022-02-07 2022-03-26 rocurement of Training Bags tions nvelope in Selected Landscapes IN-ICFRE-272292-GO-RFB / P rocurement of gravity based Scaling-up Sustainable Land drip irrigation system and po Single Stage - Two E TF / A3990 and Ecosystem Management Post Request for Bids Open - National 1,300,000.00 0.00 Canceled 2022-01-21 2022-01-14 2022-01-26 2022-01-18 2022-02-28 2022-03-25 2022-04-15 2022-06-30 rtable sprinkler irrigation syst nvelope in Selected Landscapes em for upscaling in the ESIP areas of Chhattisgarh and Ma dhya Pradesh IN-ICFRE-273192-GO-RFB / P rocurement of Open Top Dru Scaling-up Sustainable Land ms for upscaling of SLEM bes Single Stage - One E TF / A3990 and Ecosystem Management Post Request for Bids Open - National 218,000.00 0.00 Canceled 2022-01-24 2022-01-18 2022-01-29 2022-01-19 2022-03-01 2022-03-31 2022-05-05 2022-07-29 t practice related to Biopestic nvelope in Selected Landscapes ides & Biofertilizers applicati on for productivity enhancem ent in the ESIP areas of MP a nd CG IN-ICFRE-274231-GO-RFQ / P Scaling-up Sustainable Land urchase of Vegetable Seeds Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Limited 99,000.00 25,730.12 Completed 2022-02-02 2022-02-02 2022-03-09 2022-04-22 2022-04-30 2022-06-23 Mini-Kit for the ESIP areas of tions nvelope in Selected Landscapes Chhattisgarh and Madhya Pra desh IN-ICFRE-278460-GO-RFQ / I mproved Cook Stoves (ICS) t Scaling-up Sustainable Land o be purchased for distributio Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 60,000.00 0.00 Canceled 2022-02-22 2022-02-18 2022-04-12 2022-05-31 n to the local communities of tions nvelope in Selected Landscapes ESIP areas of Chhattisgarh fo r promoting sustainable land management Scaling-up Sustainable Land IN-ICFRE-278462-GO-RFQ / P Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Limited 7,000.00 5,852.70 Completed 2022-02-22 2022-02-18 2022-04-15 2022-03-10 2022-05-31 2022-03-29 rocurement of Training Bags tions nvelope in Selected Landscapes IN-ICFRE-281491-GO-RFQ / P urchase of tall seedlings of fr Scaling-up Sustainable Land Request for Quota Single Stage - One E uit trees for upscaling of WA TF / A3990 and Ecosystem Management Post Open - National 95,600.00 30,811.85 Completed 2022-04-06 2022-03-10 2022-06-01 2022-06-03 2022-11-28 2022-09-21 tions nvelope DI: A tree-based farming syst in Selected Landscapes em in the ESIP areas of Chha ttisgarh IN-ICFRE-281496-GO-RFQ / P urchase of tall seedlings of fr Scaling-up Sustainable Land Request for Quota Single Stage - One E uit trees for upscaling of WA TF / A3990 and Ecosystem Management Post Open - National 43,500.00 0.00 Canceled 2022-04-06 2022-03-10 2022-06-01 2022-11-28 tions nvelope DI: A tree-based farming syst in Selected Landscapes em in the ESIP areas of Mad hya Pradesh IN-ICFRE-283929-GO-RFQ / P Request for Quota Single Stage - One E TF / A3990 Project Management Post Open - National 2,000.00 0.00 Canceled 2022-03-25 2022-04-29 2022-05-20 2022-07-30 rocurement of Printers (04 N tions nvelope os.) IN-ICFRE-283930-GO-RFQ / P Request for Quota Single Stage - One E TF / A3990 Project Management Post Open - National 1,500.00 0.00 Canceled 2022-03-25 2022-04-29 2022-05-20 2022-07-30 rocurement of Photocopier M tions nvelope achine IN-ICFRE-288256-GO-RFQ / I mproved Cook Stoves (ICS) t Scaling-up Sustainable Land o be purchased for distributio Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 60,000.00 49,505.81 Completed 2022-04-18 2022-04-23 2022-06-13 2022-05-27 2022-12-10 2022-07-15 n to the local communities of tions nvelope in Selected Landscapes ESIP areas of Chhattisgarh fo r promoting sustainable land management IN-ICFRE-288260-GO-RFB / P rocurement of Open Top Dru Scaling-up Sustainable Land ms for upscaling of SLEM bes Single Stage - One E TF / A3990 and Ecosystem Management Post Request for Bids Open - National 225,000.00 191,916.92 Completed 2022-04-14 2022-04-26 2022-04-19 2022-04-27 2022-05-31 2022-05-23 2022-06-30 2022-05-31 2022-08-04 2022-07-09 2023-01-31 t practice related to Biopestic nvelope in Selected Landscapes ides & Biofertilizers applicati on for productivity enhancem ent in the ESIP areas of MP a nd CG IN-ICFRE-288261-GO-RFB / P rocurement of gravity based Scaling-up Sustainable Land drip irrigation system and po Single Stage - One E TF / A3990 and Ecosystem Management Post Request for Bids Open - National 1,200,000.00 0.00 Canceled 2022-04-18 2022-04-27 2022-04-23 2022-04-27 2022-06-04 2022-05-23 2022-07-04 2022-08-08 2023-02-04 rtable sprinkler irrigation syst nvelope in Selected Landscapes em for upscaling in the ESIP areas of Chhattisgarh and Ma dhya Pradesh IN-ICFRE-294538-GO-RFQ / P Scaling-up Sustainable Land rocurement of paddy seeds f Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 35,000.00 0.00 Canceled 2022-05-19 2022-05-13 2022-06-14 2022-07-15 or ESIP areas of Chhattisgarh tions nvelope in Selected Landscapes and Madhya Pradesh IN-ICFRE-294546-GO-RFQ / P Scaling-up Sustainable Land rocurement of maize seeds f Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 56,000.00 0.00 Canceled 2022-05-20 2022-05-13 2022-07-08 2022-08-08 or ESIP areas of Chhattisgarh tions nvelope in Selected Landscapes and Madhya Pradesh IN-ICFRE-294951-GO-RFQ / P urchase of tall seedlings of fr Scaling-up Sustainable Land Request for Quota Single Stage - One E uit trees for upscaling of WA TF / A3990 and Ecosystem Management Post Open - National 30,000.00 20,438.95 Completed 2022-05-22 2022-05-13 2022-07-17 2022-06-27 2022-08-31 2022-09-21 tions nvelope DI: A tree-based farming syst in Selected Landscapes em in the ESIP areas of Madh ya Pradesh IN-ICFRE-313853-GO-RFQ / P Scaling-up Sustainable Land rocurement of training kits (7 Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 18,000.00 0.00 Completed 2022-09-17 2022-09-09 2022-11-12 2023-05-11 000 Nos.) for organization of tions nvelope in Selected Landscapes the trainings on Scaling up of SLEM Best Practices IN-ICFRE-313870-GO-RFQ / P Request for Quota Single Stage - One E TF / A3990 Project Management Post Open - National 4,500.00 0.00 Completed 2022-09-18 2022-10-04 2022-11-13 2023-05-12 2023-01-15 rocurement of Projectors (04 tions nvelope Nos.) IN-ICFRE-315131-GO-RFQ / P Scaling-up Sustainable Land urchase of Brood Lac (Range Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 50,000.00 0.00 Completed 2022-09-17 2022-09-16 2022-10-19 2022-11-09 eni strain for Baisakhi Crop) tions nvelope in Selected Landscapes 8160 kg along with nylon me sh & rope IN-ICFRE-315133-GO-RFQ / P Request for Quota Single Stage - One E TF / A3990 Project Management Post Open - National 12,000.00 0.00 Completed 2022-10-01 2022-09-26 2022-11-26 2022-12-30 urchase of conference chairs tions nvelope for ESIP-PIU IN-ICFRE-315160-GO-RFQ / P Request for Quota Single Stage - One E urchase of multifunction prin TF / A3990 Project Management Post Open - National 7,000.00 0.00 Completed 2022-10-03 2022-10-20 2022-11-28 2022-12-30 2023-04-02 tions nvelope ters (1 coloured and 3 mono) Page 4 IN-ICFRE-315171-GO-RFQ / P Request for Quota Single Stage - One E TF / A3990 Project Management Post Open - National 4,000.00 0.00 Completed 2022-10-01 2022-09-29 2022-11-26 2023-03-31 urchase of office file cabinets tions nvelope (6 Nos.) IN-ICFRE-315178-GO-RFQ / P Request for Quota Single Stage - One E urchase of water purifiers wit TF / A3990 Project Management Post Open - National 3,600.00 0.00 Completed 2022-09-28 2022-10-20 2022-11-23 2022-12-30 tions nvelope h hot and cold dispenser (02 Nos) IN-ICFRE-315186-GO-RFQ / P urchase of High-Density Polyt Scaling-up Sustainable Land Request for Quota Single Stage - One E hene Vermi Beds (1200 Nos.) TF / A3990 and Ecosystem Management Post Open - National 60,000.00 0.00 Completed 2022-10-01 2022-09-20 2022-11-26 2023-03-30 tions nvelope for ESIP areas of Madhya Pra in Selected Landscapes desh and Chhattisgarh IN-ICFRE-315189-GO-RFQ / P Scaling-up Sustainable Land urchase of earthworms (3600 Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Limited 27,000.00 0.00 Completed 2022-10-08 2022-09-19 2022-12-03 2023-04-28 kg) for vermicomposting in E tions nvelope in Selected Landscapes SIP areas of Madhya Pradesh and Chhattisgarh IN-ICFRE-315240-GO-RFB / P urchase of Vegetable Seeds Scaling-up Sustainable Land Single Stage - One E Mini-kits (14320 Nos.) of Rabi TF / A3990 and Ecosystem Management Post Request for Bids Open - National 128,000.00 0.00 Completed 2022-09-14 2022-09-16 2022-09-19 2022-09-16 2022-10-10 2022-10-10 2022-10-17 2022-10-11 2022-10-31 2022-12-30 2023-01-20 nvelope season for the ESIP areas of in Selected Landscapes Chhattisgarh and Madhya Pra desh IN-ICFRE-315241-GO-RFB / P urchase of Improved Cook St oves (5515 Nos.) for distribut Scaling-up Sustainable Land Single Stage - One E ion to the additional benefici TF / A3990 and Ecosystem Management Post Request for Bids Open - National 132,000.00 0.00 Completed 2022-09-19 2022-09-16 2022-09-24 2022-09-16 2022-10-24 2022-11-07 2022-11-11 2022-11-07 2022-12-16 2023-06-14 nvelope aries of ESIP areas of Chhatti in Selected Landscapes sgarh and Madhya Pradesh f or promoting sustainable lan d management IN-ICFRE-318613-GO-RFB / P rocurement of HDPE Azolla G rowing Beds (7000 beds) wit Scaling-up Sustainable Land Single Stage - One E h accessories and mother A TF / A3990 and Ecosystem Management Post Request for Bids Open - National 481,000.00 0.00 Signed 2022-10-10 2022-10-13 2022-10-15 2022-11-23 2022-11-08 2022-12-16 2022-11-14 2022-12-16 2022-12-05 2023-03-10 nvelope zolla seeds (culture) for scali in Selected Landscapes ng up of SLEM practice in the ESIP landscapes of Madhya P radesh and Chhattisgarh IN-ICFRE-318635-GO-RFQ / P Request for Quota Single Stage - One E rocurement of Conference Ha TF / A3990 Project Management Post Limited 16,000.00 0.00 Completed 2022-10-14 2022-10-21 2022-12-02 2023-05-31 tions nvelope ll Projectors (04 Nos.) with pr ojection screens IN-ICFRE-320781-GO-RFB / P rocurement of gravity based Scaling-up Sustainable Land drip irrigation system and po Single Stage - One E TF / A3990 and Ecosystem Management Post Request for Bids Open - National 1,200,000.00 0.00 Signed 2022-10-19 2022-11-23 2022-10-24 2022-11-23 2022-12-05 2022-12-19 2022-12-16 2022-12-22 2023-01-20 2023-03-24 rtable sprinkler irrigation syst nvelope in Selected Landscapes em for upscaling in the ESIP areas of Chhattisgarh and Ma dhya Pradesh IN-ICFRE-327547-GO-RFQ / P rocurement of Agriculture Sp Scaling-up Sustainable Land Request for Quota Single Stage - One E ray Pumps for biopesticides a TF / A3990 and Ecosystem Management Post Open - National 65,000.00 0.00 Canceled 2022-11-30 2023-02-28 2023-01-25 2023-03-31 tions nvelope pplication for productivity en in Selected Landscapes hancement in the ESIP areas of MP and CG (2177 Nos.) Strengthen Capacity of Gove IN-ICFRE-345007-GO-RFQ / P rnment Institutions in Forest Request for Quota Single Stage - One E rocurement of Workshop Kits TF / A3990 Post Limited 10,000.00 0.00 Completed 2023-03-05 2023-02-28 2023-03-20 2023-04-28 2023-04-03 ry and Land Management Pr tions nvelope (200 Nos.) ograms in Madhya Pradesh a nd Chhattisgarh IN-ICFRE-345076-GO-RFQ / P Request for Quota Single Stage - One E TF / A3990 Project Management Post Open - National 32,000.00 0.00 Signed 2023-03-05 2023-03-09 2023-04-13 2023-04-13 rocurement of Video Wall tions nvelope IN-ICFRE-358380-GO-RFQ / P urchase of tall seedlings of fr Scaling-up Sustainable Land uit trees for upscaling of WA Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Limited 38,000.00 0.00 Signed 2023-05-07 2023-04-26 2023-07-02 2023-07-30 DI: A tree-based farming syst tions nvelope in Selected Landscapes em in the ESIP areas of Narh arpur Forest Range, Kanker F orest Division, Chhattisgarh IN-ICFRE-358383-GO-RFQ / P rocurement of Open Top Dru ms for upscaling of SLEM bes Scaling-up Sustainable Land t practice related to Biopestic Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Limited 65,000.00 0.00 Signed 2023-05-07 2023-04-26 2023-07-02 2023-07-30 ides & Biofertilizers applicati tions nvelope in Selected Landscapes on for productivity enhancem ent in the ESIP areas of Narh arpur Forest Range, Kanker F orest Division, Chhattisgarh NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ICFRE-151168-NC-RFQ / P rinting of Baseline Report on Investments for Improving F Request for Quota Single Stage - One E Forest Carbon Stocks of Mad TF / A3990 orest Quality in Selected Lan Post Limited 10,000.00 1,289.35 Completed 2020-01-20 2020-01-29 2020-02-24 2020-06-03 2020-03-31 2020-11-24 tions nvelope hya Pradesh and Chhattisgar dscapes h (200 copies of each report) IN-ICFRE-151156-NC-RFQ / P rinting of Baseline Report of Scaling-up Sustainable Land Request for Quota Single Stage - One E Socio Economic Survey of Ma TF / A3990 and Ecosystem Management Post Limited 10,000.00 1,266.73 Completed 2020-01-20 2020-01-29 2020-02-24 2020-06-03 2020-03-31 2020-09-18 tions nvelope dhya Pradesh and Chhattisga in Selected Landscapes rh (200 copies of each report ) IN-ICFRE-151166-NC-RFQ / P rinting of Resource Manual o n Measurement of Forest Car Investments for Improving F Request for Quota Single Stage - One E bon Stocks for Capacity Build TF / A3990 orest Quality in Selected Lan Post Limited 60,000.00 2,593.78 Completed 2020-01-20 2020-01-29 2020-02-24 2020-06-03 2020-03-31 2020-09-18 tions nvelope ing of State Forest Departme dscapes nt of Madhya Pradesh and Ch hattisgarh (in English 1000 c opies and in Hindi 1000 copie s) IN-ICFRE-151561-CW-DIR / L aboratory analysis for estima Investments for Improving F tion of carbon stocks from pl TF / A3990 orest Quality in Selected Lan Post Direct Selection Direct 6,000.00 1,530.69 Completed 2020-01-20 2020-01-30 2020-01-25 2020-02-10 2020-02-14 2020-06-04 2020-03-31 2020-07-14 ant and soil samples of proje dscapes ct areas of Chhattisgarh thro ugh Indira Gandhi Krishi Vish wavidhalaya, Raipur (CG) Page 5 IN-ICFRE-153627-NC-DIR / La boratory analysis for estimati Investments for Improving F on of carbon stocks from pla TF / A3990 orest Quality in Selected Lan Post Direct Selection Direct 6,000.00 0.00 Canceled 2020-01-20 2020-01-25 2020-02-14 2020-03-31 nt and soil samples of project dscapes areas of MP through TFRI, Jab alpur (MP) IN-ICFRE-153654-NC-RFQ / P Scaling-up Sustainable Land Request for Quota Single Stage - One E rinting of flyers in Hindi and TF / A3990 and Ecosystem Management Post Limited 30,000.00 14,763.70 Completed 2020-02-01 2020-01-29 2020-03-06 2020-06-04 2020-03-31 2020-08-26 tions nvelope English languages on SLEM b in Selected Landscapes est practices IN-ICFRE-209498-NC-RFQ / P rinting of calendar on SLEM a Investments for Improving F wareness and Flyers and Pa Request for Quota Single Stage - One E TF / A3990 orest Quality in Selected Lan Post Limited 40,000.00 21,093.24 Completed 2020-12-26 2020-12-16 2021-02-20 2021-02-11 2021-08-19 2021-03-31 mphlets on SLEM Best Practic tions nvelope dscapes es, brochure and training ma nual on Forest Carbon Stocks Measurement IN-ICFRE-217426-NC-RFB / H iring of agency for SLEM awa reness and conveying the me Scaling-up Sustainable Land ssage for adoption of SLEM b Single Stage - Two E TF / A3990 and Ecosystem Management Post Request for Bids Open - National 150,000.00 0.00 Canceled 2021-02-12 2021-03-31 2021-02-17 2021-03-31 2021-06-13 2021-07-18 2022-01-14 est practices through mobile nvelope in Selected Landscapes display vehicle and skit show in the villages of selected lan dscapes of Chhattisgarh and Madhya Pradesh IN-ICFRE-281500-NC-RFQ / P Scaling-up Sustainable Land rinting of Final Report of Roa Request for Quota Single Stage - One E TF / A3990 and Ecosystem Management Post Open - National 10,500.00 6,934.22 Completed 2022-03-26 2022-03-24 2022-05-21 2022-05-10 2022-11-17 dmap for Institutional and Pol tions nvelope in Selected Landscapes icy Mainstreaming of SLEM in other sectors CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ICFRE-142423-CS-CQS / H iring of an External Auditor ( Consultant Qualifi TF / A3990 Project Management Post Open - National 15,000.00 1,050.42 Completed 2019-10-24 2019-11-08 2019-10-27 2019-11-26 2019-12-10 2019-12-20 2020-01-09 2019-12-20 2020-02-13 2019-12-26 2020-08-11 2020-07-15 AG&CAG empanelled) for Eco cation Selection system Services Improvemen t Project IN-ICFRE-154297-CS-CQS / D evelopment of Road Map for I Scaling-up Sustainable Land Consultant Qualifi nstitutional and Policy Mainst TF / A3990 and Ecosystem Management Post Open - National 219,500.00 173,246.34 Completed 2020-01-24 2020-02-05 2020-02-14 2020-02-13 2020-03-29 2020-06-08 2020-04-28 2020-07-28 2020-06-02 2020-09-04 2020-12-29 2022-02-05 cation Selection reaming of Sustainable Land in Selected Landscapes and Ecosystem Management (SLEM) in India IN-ICFRE-154299-CS-CQS / E valuation of the working/ effe ctiveness of Van Vigyan Kenr das (VVKs) established in diff Scaling-up Sustainable Land Consultant Qualifi erent states in fulfilling the o TF / A3990 and Ecosystem Management Post Open - National 30,000.00 36,202.07 Completed 2020-01-24 2020-02-05 2020-02-14 2020-02-14 2020-03-29 2020-06-08 2020-04-28 2020-07-28 2020-06-02 2020-08-27 2020-11-29 2022-02-05 cation Selection bjectives of forestry extensio in Selected Landscapes n services to enable technolo gies from Lab to Land and m ake practicable suggestions t o improve upon the IN-ICFRE-154300-CS-CQS / D eveloping an online National Scaling-up Sustainable Land Reporting Database Portal fo Consultant Qualifi TF / A3990 and Ecosystem Management Post Open - National 150,000.00 137,735.35 Completed 2020-01-24 2020-02-05 2020-02-14 2020-02-14 2020-03-29 2020-06-15 2020-04-28 2020-07-31 2020-06-02 2020-10-27 2020-11-29 2022-08-04 r Capturing Trends and Statu cation Selection in Selected Landscapes s of Key Progress and Perfor mance Indicators on Land De gradation and Desertification IN-ICFRE-68368-CS-QCBS / D evelopment of Road Map for I Scaling-up Sustainable Land Quality And Cost- nstitutional and Policy Mainst TF / A3990 and Ecosystem Management Post Open - National 219,500.00 0.00 Canceled 2019-02-04 2019-06-04 2019-02-25 2019-09-22 2019-04-10 2019-05-08 2019-06-07 2019-07-12 2019-08-16 2020-08-15 Based Selection reaming of in Selected Landscapes Sustainable Land and Ecosys tem Management (SLEM) in I ndia IN-ICFRE-101330-CS-QCBS / Developing an online Nationa Scaling-up Sustainable Land l Reporting Database Portal f Consultant Qualifi TF / A3990 and Ecosystem Management Post Open - National 150,000.00 0.00 Canceled 2019-06-17 2019-06-04 2019-07-08 2019-09-22 2019-08-21 2019-09-20 2019-10-25 2020-04-22 or Capturing Trends and Stat cation Selection in Selected Landscapes us of Key Progress and Perfor mance Indicators on Land De gradation and Desertification IN-ICFRE-117954-CS-CQS / E valuation of the Working/ Eff Scaling-up Sustainable Land ectiveness of Forestry Extens Consultant Qualifi TF / A3990 and Ecosystem Management Post Open - National 80,000.00 0.00 Canceled 2019-06-24 2019-06-04 2019-07-15 2019-09-22 2019-08-28 2019-09-27 2019-11-01 2020-04-29 ion System through the Van cation Selection in Selected Landscapes Vigyan Kendras and Recomm endations for its Strengtheni ng IN-ICFRE-154302-CS-CQS / D eveloping an interactive web -based platform & mobile ap Scaling-up Sustainable Land Consultant Qualifi plication with direct access a TF / A3990 and Ecosystem Management Post Open - National 25,000.00 0.00 Canceled 2020-02-04 2020-02-08 2020-02-18 2020-02-14 2020-02-25 2020-06-15 2020-03-06 2020-03-26 2020-06-30 cation Selection nd use at the farm level with in Selected Landscapes help from extension services for dissemination of SLEM be st practices to the end users IN-ICFRE-173906-CS-QCBS / Engagement of Technical Par Scaling-up Sustainable Land tner Agency/Agencies for sup Quality And Cost- TF / A3990 and Ecosystem Management Post Open - National 796,000.00 242,750.83 Completed 2020-05-25 2020-05-18 2020-05-29 2020-05-28 2020-07-12 2020-10-06 2020-08-09 2020-11-06 2020-09-08 2020-11-09 2020-10-13 2020-11-12 2020-11-17 2020-12-15 2022-06-24 porting the scaling up of SLE Based Selection in Selected Landscapes M best practices in selected l andscapes of Chhattisgarh a nd Madhya Pradesh IN-ICFRE-242011-CS-CQS / H iring of an External Auditor ( Consultant Qualifi TF / A3990 Project Management Post Open - National 4,000.00 3,963.06 Signed 2021-07-09 2021-07-09 2021-07-30 2021-08-11 2021-09-28 2021-10-18 2021-10-19 2021-11-25 2021-11-30 2021-12-03 2022-07-31 AG&CAG empaneled) for Eco cation Selection system Services Improvemen t Project IN-ICFRE-276264-CS-CQS / A n independent evaluation of overall impacts of the project Consultant Qualifi TF / A3990 Project Management Post Open - National 25,000.00 0.00 Canceled 2022-02-15 2022-02-07 2022-03-01 2022-04-01 2022-04-15 2022-05-20 2022-07-30 activities in sync with the pro cation Selection ject objectives and with the i ndicators under the Results F ramework of the project. Page 6 IN-ICFRE-296182-CS-CQS / E SIP: An independent evaluati on of overall impacts of the p Consultant Qualifi TF / A3990 Project Management Post Open - National 55,000.00 43,714.31 Signed 2022-05-21 2022-06-01 2022-06-04 2022-06-02 2022-06-16 2022-07-26 2022-06-23 2022-08-30 2022-07-03 2022-09-08 2022-11-20 roject activities in sync with t cation Selection he project objectives and wit h the indicators under the Re sults Framework of the proje ct. INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ICFRE-31731-CS-INDV / S Scaling-up Sustainable Land Individual Consult election of Natural Resource TF / A3990 and Ecosystem Management Post Open 30,000.00 26,526.68 Terminated 2017-10-20 2017-11-02 2017-12-08 2018-01-04 2017-12-29 2018-01-23 2018-02-02 2018-08-01 2020-02-02 ant Selection Management-cum-Biodiversit in Selected Landscapes y Consultant IN-ICFRE-31732-CS-INDV / S Scaling-up Sustainable Land Individual Consult election of Land Managemen TF / A3990 and Ecosystem Management Post Open 30,000.00 26,493.77 Terminated 2017-10-20 2017-11-02 2017-12-08 2018-01-04 2017-12-29 2018-01-23 2018-02-02 2018-06-19 2020-02-02 ant Selection t Consultant in Selected Landscapes IN-ICFRE-31733-CS-INDV / S Scaling-up Sustainable Land Individual Consult election of Policy-cum-Knowl TF / A3990 and Ecosystem Management Post Open 30,000.00 26,520.33 Completed 2017-10-20 2017-11-02 2017-12-08 2018-08-10 2017-12-29 2018-08-13 2018-02-02 2018-08-31 2020-02-02 2020-06-30 ant Selection edge Management Consultan in Selected Landscapes t IN-ICFRE-31736-CS-INDV / S Scaling-up Sustainable Land Individual Consult election of Monitoring and Ev TF / A3990 and Ecosystem Management Post Open 30,000.00 26,453.37 Completed 2017-10-20 2017-11-02 2017-12-08 2018-08-10 2017-12-29 2018-08-13 2018-02-02 2018-10-01 2018-08-01 2020-09-30 ant Selection aluation Consultant in Selected Landscapes IN-ICFRE-31737-CS-INDV / S Scaling-up Sustainable Land Individual Consult election of State Coordinatin TF / A3990 and Ecosystem Management Post Open 30,000.00 26,520.33 Terminated 2017-10-20 2017-11-02 2017-12-08 2018-01-04 2017-12-29 2018-01-23 2018-02-02 2018-06-29 2020-02-02 ant Selection g Consultant in Selected Landscapes IN-ICFRE-31738-CS-INDV / S Scaling-up Sustainable Land Individual Consult election of Carbon Sequestra TF / A3990 and Ecosystem Management Post Open 30,000.00 26,417.87 Completed 2017-10-20 2017-11-02 2017-12-08 2018-08-10 2017-12-29 2018-08-13 2018-02-02 2018-08-31 2020-02-02 2020-08-30 ant Selection tion Consultant in Selected Landscapes IN-ICFRE-31741-CS-INDV / S Scaling-up Sustainable Land Individual Consult election of Social Developme TF / A3990 and Ecosystem Management Post Open 30,000.00 26,453.37 Completed 2017-10-20 2017-11-02 2017-12-08 2018-01-04 2017-12-29 2018-01-23 2018-02-02 2018-06-29 2020-02-02 2020-06-28 ant Selection nt/ Community Mobilization C in Selected Landscapes onsultant IN-ICFRE-32612-CS-INDV / S Individual Consult election of Procurement Cons TF / A3990 Project Management Post Open 16,000.00 15,850.72 Completed 2017-10-21 2017-11-03 2017-12-09 2018-01-04 2017-12-30 2018-01-23 2018-02-03 2018-06-20 2020-02-03 2020-06-19 ant Selection ultant-cum-Financial Expert IN-ICFRE-32621-CS-INDV / S Individual Consult election of Establishment Co TF / A3990 Project Management Post Open 16,000.00 14,130.01 Completed 2017-10-27 2017-11-02 2017-12-15 2018-01-04 2018-01-05 2018-01-23 2018-02-09 2018-06-14 2020-02-09 2020-06-13 ant Selection nsultant-cum-Secretarial Exp ert IN-ICFRE-117949-CS-INDV / Scaling-up Sustainable Land Individual Consult Selection of Land Manageme TF / A3990 and Ecosystem Management Post Open 30,000.00 26,543.08 Completed 2019-06-17 2019-06-23 2019-08-05 2019-07-24 2019-08-26 2019-07-29 2019-09-30 2019-08-05 2020-03-28 2021-08-04 ant Selection nt Consultant in Selected Landscapes IN-ICFRE-117946-CS-INDV / Scaling-up Sustainable Land Individual Consult Selection of Natural Resource TF / A3990 and Ecosystem Management Post Open 30,000.00 26,526.68 Terminated 2019-06-17 2019-06-23 2019-08-05 2019-09-17 2019-08-26 2019-09-20 2019-09-30 2019-09-30 2020-03-28 ant Selection Management-cum-Biodiversit in Selected Landscapes y Consultant IN-ICFRE-135219-CS-INDV / Individual Consult Selection of State Coordinati TF / A3990 Project Management Post Open 30,000.00 25,279.13 Terminated 2019-10-17 2019-11-08 2019-12-05 2020-01-06 2019-12-26 2020-01-14 2020-01-30 2020-01-20 2020-07-28 ant Selection ng Consultant IN-ICFRE-165251-CS-INDV / Scaling-up Sustainable Land Individual Consult Selection of Natural Resource TF / A3990 and Ecosystem Management Post Open 32,000.00 25,211.94 Completed 2020-05-20 2020-05-15 2020-07-08 2020-07-23 2020-07-22 2020-07-23 2020-08-26 2020-08-04 2022-08-30 2022-07-31 ant Selection Management-cum-Biodiversit in Selected Landscapes y Consultant IN-ICFRE-175658-CS-INDV / Individual Consult Selection of Establishment C TF / A3990 Project Management Post Open 25,000.00 18,688.30 Completed 2020-05-28 2020-05-28 2020-06-26 2020-06-15 2020-06-30 2020-06-15 2020-07-05 2020-06-16 2022-06-30 2022-07-31 ant Selection onsultant-cum-Secretarial Ex pert IN-ICFRE-175660-CS-INDV / Individual Consult Selection of Procurement Co TF / A3990 Project Management Post Open 25,000.00 0.00 Canceled 2020-05-28 2020-05-28 2020-06-26 2020-07-07 2020-07-27 2022-06-30 ant Selection nsultant-cum-Financial Exper t IN-ICFRE-178305-CS-INDV / Individual Consult TF / A3990 Project Management Post Open 25,000.00 18,566.04 Completed 2020-06-15 2020-06-12 2020-06-26 2020-06-24 2020-06-28 2020-06-24 2020-07-21 2020-06-25 2022-06-30 2022-07-31 Selection of Financial Expert ant Selection IN-ICFRE-180830-CS-INDV / Scaling-up Sustainable Land Individual Consult Selection of Policy cum Know TF / A3990 and Ecosystem Management Post Open 35,000.00 27,733.13 Terminated 2020-06-26 2020-06-22 2020-08-14 2020-07-31 2020-09-04 2020-07-31 2020-10-09 2020-08-17 2022-06-30 ant Selection ledge Management Consulta in Selected Landscapes nt IN-ICFRE-180829-CS-INDV / Scaling-up Sustainable Land Individual Consult Selection of Social Developm TF / A3990 and Ecosystem Management Post Open 35,000.00 25,939.27 Completed 2020-06-26 2020-06-22 2020-08-14 2020-07-16 2020-09-04 2020-07-16 2020-10-09 2020-07-18 2022-07-03 2022-07-31 ant Selection ent/ Community Mobilization in Selected Landscapes Consultant IN-ICFRE-188697-CS-INDV / Scaling-up Sustainable Land Individual Consult Selection of Carbon Sequestr TF / A3990 and Ecosystem Management Post Open 35,000.00 28,199.47 Completed 2020-08-21 2020-08-31 2020-09-09 2020-09-28 2020-09-11 2020-09-28 2020-09-21 2020-09-30 2022-06-30 2022-07-31 ant Selection ation Consultant in Selected Landscapes IN-ICFRE-192651-CS-INDV / Scaling-up Sustainable Land Individual Consult Selection of Monitoring and TF / A3990 and Ecosystem Management Post Open 32,000.00 24,590.50 Completed 2020-09-15 2020-09-09 2020-10-07 2020-10-01 2020-10-14 2020-10-01 2020-11-11 2020-10-15 2022-07-30 2022-07-31 ant Selection Evaluation Consultant in Selected Landscapes IN-ICFRE-205086-CS-INDV / Individual Consult Selection of State Coordinati TF / A3990 Project Management Post Open 30,000.00 21,197.81 Terminated 2020-11-20 2020-11-18 2020-12-12 2020-12-16 2020-12-17 2020-12-16 2020-12-21 2020-12-23 2022-06-30 ant Selection ng Consultant IN-ICFRE-209455-CS-INDV / Individual Consult TF / A3990 Project Management Post Open 25,000.00 20,360.84 Completed 2020-12-21 2020-12-15 2021-02-08 2021-03-02 2021-03-01 2021-03-02 2021-04-05 2021-03-11 2022-07-31 2022-07-30 Engagement of Procurement ant Selection Consultant IN-ICFRE-209478-CS-INDV / Investments for Improving F Individual Consult Engagement of Carbon Monit TF / A3990 orest Quality in Selected Lan Post Open 25,000.00 20,277.45 Terminated 2020-12-21 2020-12-15 2021-02-08 2021-01-14 2021-03-01 2021-01-14 2021-04-05 2021-02-02 2022-07-31 ant Selection oring Consultant dscapes IN-ICFRE-242021-CS-INDV / Scaling-up Sustainable Land Engagement of individual La Individual Consult TF / A3990 and Ecosystem Management Post Open 18,000.00 14,379.78 Completed 2021-07-09 2021-07-12 2021-08-27 2021-08-03 2021-09-17 2021-08-03 2021-10-22 2021-08-06 2022-07-31 2022-07-31 nd Management Consultant u ant Selection in Selected Landscapes p to project completion perio d Page 7 IN-ICFRE-249365-CS-INDV / Scaling-up Sustainable Land Individual Consult Engagement of Policy-cum-K TF / A3990 and Ecosystem Management Post Open 12,000.00 9,593.35 Completed 2021-08-30 2021-09-01 2021-09-21 2021-10-28 2021-09-24 2021-10-28 2021-09-30 2021-11-02 2022-07-30 2022-07-31 ant Selection nowledge Management Cons in Selected Landscapes ultant IN-ICFRE-280569-CS-INDV / Investments for Improving F Individual Consult Engagement of Carbon Monit TF / A3990 orest Quality in Selected Lan Post Open 25,000.00 19,906.61 Terminated 2022-03-11 2022-03-10 2022-04-13 2022-04-26 2022-04-27 2022-04-26 2022-05-25 2022-05-05 2023-07-30 ant Selection oring Consultant dscapes IN-ICFRE-294554-CS-INDV / Individual Consult Engagement of State Coordin TF / A3990 Project Management Post Open 22,000.00 18,019.32 Signed 2022-05-17 2022-05-13 2022-07-05 2022-06-09 2022-07-26 2022-06-09 2022-08-30 2022-06-13 2023-07-30 ant Selection ating Consultant IN-ICFRE-299313-CS-INDV / Investments for Improving F Individual Consult Engagement of Carbon Sequ TF / A3990 orest Quality in Selected Lan Post Open 18,000.00 15,019.62 Signed 2022-06-15 2022-06-13 2022-08-03 2022-07-22 2022-08-24 2022-07-22 2022-09-28 2022-07-24 2023-07-30 ant Selection estration Consultant dscapes IN-ICFRE-299317-CS-INDV / Scaling-up Sustainable Land Individual Consult Engagement of Land Manage TF / A3990 and Ecosystem Management Post Open 18,000.00 15,019.62 Signed 2022-06-15 2022-06-13 2022-08-03 2022-07-22 2022-08-24 2022-07-22 2022-09-28 2022-07-24 2023-07-30 ant Selection ment Consultant in Selected Landscapes IN-ICFRE-299318-CS-INDV / Scaling-up Sustainable Land Engagement of Natural Reso Individual Consult TF / A3990 and Ecosystem Management Post Open 18,000.00 15,019.62 Signed 2022-06-15 2022-06-13 2022-08-03 2022-07-22 2022-08-24 2022-07-22 2022-09-28 2022-07-24 2023-07-30 urce Management-cum-Biodi ant Selection in Selected Landscapes versity Consultant IN-ICFRE-299319-CS-INDV / Scaling-up Sustainable Land Individual Consult Engagement of Policy-cum-K TF / A3990 and Ecosystem Management Post Open 18,000.00 15,019.62 Signed 2022-06-15 2022-06-13 2022-08-03 2022-07-22 2022-08-24 2022-07-22 2022-09-28 2022-07-24 2023-07-30 ant Selection nowledge Management Cons in Selected Landscapes ultant IN-ICFRE-299320-CS-INDV / Scaling-up Sustainable Land Engagement of Social Develo Individual Consult TF / A3990 and Ecosystem Management Post Open 18,000.00 15,019.62 Signed 2022-06-15 2022-06-13 2022-08-03 2022-07-22 2022-08-24 2022-07-22 2022-09-28 2022-07-24 2023-07-30 pment and Community Mobili ant Selection in Selected Landscapes zation Consultant IN-ICFRE-299321-CS-INDV / Scaling-up Sustainable Land Individual Consult Engagement of Monitoring a TF / A3990 and Ecosystem Management Post Open 18,000.00 15,042.22 Signed 2022-06-15 2022-06-13 2022-07-11 2022-07-22 2022-08-01 2022-07-22 2022-09-05 2022-07-24 2023-07-30 ant Selection nd Evaluation Consultant in Selected Landscapes IN-ICFRE-299325-CS-INDV / Individual Consult TF / A3990 Project Management Post Open 15,700.00 12,035.28 Terminated 2022-06-15 2022-06-13 2022-07-12 2022-07-22 2022-07-19 2022-07-22 2022-08-02 2022-07-26 2023-07-30 Engagement of Procurement ant Selection Consultant IN-ICFRE-299328-CS-INDV / Individual Consult TF / A3990 Project Management Post Open 15,700.00 12,013.59 Signed 2022-06-15 2022-06-13 2022-07-13 2022-07-22 2022-07-18 2022-07-22 2022-08-15 2022-07-24 2023-07-30 Engagement of Financial Con ant Selection sultant IN-ICFRE-299329-CS-INDV / Individual Consult Engagement of Establishmen TF / A3990 Project Management Post Open 15,700.00 12,035.28 Signed 2022-06-15 2022-06-13 2022-07-11 2022-07-22 2022-08-01 2022-07-22 2022-09-01 2022-07-24 2023-07-30 ant Selection t-cum-Secretarial Consultant IN-ICFRE-304314-CS-INDV / Investments for Improving F Individual Consult Engagement of Carbon Monit TF / A3990 orest Quality in Selected Lan Post Open - National 18,000.00 0.00 Signed 2022-07-18 2022-09-04 2022-09-05 2022-10-12 2022-09-26 2022-10-12 2022-10-31 2023-07-30 ant Selection oring Consultant dscapes IN-ICFRE-317160-CS-CDS / M Scaling-up Sustainable Land aintenance of SLEM Knowled TF / A3990 and Ecosystem Management Post Direct Selection Direct - National 60,000.00 0.00 Canceled 2022-10-04 2022-10-10 2022-10-14 2022-10-21 2022-11-18 2023-07-30 ge Sharing and Reporting Sy in Selected Landscapes stem IN-ICFRE-358909-CS-CDS / H iring of an External Auditor ( Pending Impleme AG&CAG empaneled) for Eco TF / A3990 Project Management Post Direct Selection Direct - National 2,000.00 0.00 2023-05-03 2023-05-13 2023-06-26 2023-10-30 ntation system Services Improvemen t Project up to project comple tion period Page 8