PROCUREMENT PLAN (Textural Part) Project information Country: Ethiopia Project Name: Response - Recovery - Resilience for Conflict- Affected Communities in Ethiopia Project (3R- 4CACE) Project ID: P177233 Project Implementation Agency: Ministry of Finance (MoF) Date of the Procurement Plan: April 2022 Period covered by this Procurement Plan: April 2022 to June 2023 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” dated November 2020 (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Procurement Directives of the Federal and Regional Governments of Ethiopia such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second-Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations. Goods: Not Applicable Works: Not Applicable Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. Other Relevant Procurement Information: The procurement procedures for Situations in Urgent Need of Assistance or Capacity Constraints described under paragraph 12 of Section III of the World Bank Policy on IPF, which will be applicable to fast track emergency procurements shall apply. PROCUREMENT Ethiopia : Response - Recovery - Resilience for Conflict-Affected Communities in Ethiopia Project PLAN General Information Country: Ethiopia 2022-04-28 Bank’s Approval Date of the Original Procurement Plan: 2023-06-13 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P177233 GPN Date: 2022-05-30 Project Name: Response - Recovery - Resilience for Conflict-Affected Communities in Ethiopia Project Loan / Credit No: / , IDA / E0100 Ministry of Finance Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOF-290519-GO-DIR / Pr Rebuilding and Improving Ac ocurement of 40 Ambulances IDA / E0100 cess to Basic Services and Cl Prior Direct Selection Direct 2,300,000.00 0.00 Canceled 2022-06-26 2022-07-01 2022-08-05 2023-02-01 , 15 pickup vehicles, and 120 imate-resilient Community I Motor Cycles nfrastructure ET-MOF-290758-GO-DIR / Pr Rebuilding and Improving Ac ocurement of 10 Mobile emer cess to Basic Services and Cl IDA / E0100 Prior Direct Selection Direct 20,000,000.00 0.00 Canceled 2022-06-17 2022-06-22 2022-07-27 2022-11-24 gency and surgical Units , 1 imate-resilient Community I One Mobile Operating Room, nfrastructure and 5 Mobile clinics ET-MOF-290800-GO-RFQ / Pr Rebuilding and Improving Ac Request for Quota Single Stage - One E Pending Impl ocurement of office Furniture IDA / E0100 cess to Basic Services and Cl Post Limited 200,000.00 0.00 2022-06-22 2022-08-17 2022-11-15 tions nvelope ementation (Desks, Chairs, Lockable shel imate-resilient Community I ves) nfrastructure ET-MOF-290804-GO-RFQ / Pr Rebuilding and Improving Ac ocurement of IT Equipment ( cess to Basic Services and Cl Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 100,000.00 0.00 2022-07-27 2022-09-21 2022-12-20 Computers, printers, scanner imate-resilient Community I tions nvelope ementation s, photocopiers etc.) for FPCU nfrastructure and FPIU ET-MOF-290791-GO-DIR / Pr Rebuilding and Improving Ac ocurement of dignity kits for IDA / E0100 cess to Basic Services and Cl Post Direct Selection Direct 2,680,000.00 0.00 Canceled 2022-07-13 2022-11-11 2022-07-18 2022-08-22 2022-12-20 health Facilities imate-resilient Community I nfrastructure ET-MOF-290799-GO-RFQ / Pr Rebuilding and Improving Ac Request for Quota Single Stage - One E ocurement of Audio Visual Eq IDA / E0100 cess to Basic Services and Cl Post Limited 100,000.00 0.00 Canceled 2022-07-25 2022-09-19 2022-12-18 tions nvelope uipment (such Video/photo c imate-resilient Community I ameras) nfrastructure ET-MOF-290761-GO-DIR / Pr Rebuilding and Improving Ac ocurement of sexual assault cess to Basic Services and Cl IDA / E0100 Post Direct Selection Direct 500,000.00 0.00 Canceled 2022-07-11 2022-11-11 2022-07-16 2022-08-20 2022-12-18 evidence kit, Pre-exposure pr imate-resilient Community I ophylaxis (PEP) kits, emerge nfrastructure ncy contraceptives ET-MOF-331509-GO-DIR / Pr Rebuilding and Improving Ac Direct - Internation ocurement of Ambulances , IDA / E0100 cess to Basic Services and Cl Prior Direct Selection 2,400,000.00 0.00 Signed 2023-01-20 2023-01-13 2023-01-25 2023-04-06 2023-03-24 2023-09-20 al Hardtop vehicle and Motor C imate-resilient Community I ycles nfrastructure ET-MOF-355251-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 21,506.09 0.00 2023-05-03 2023-05-22 2023-06-21 and Office Furniture for Adaa nt tions nvelope ementation r Woreda(Zone 1) under Afar Region ET-MOF-355258-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 21,506.09 0.00 2023-05-03 2023-05-22 2023-06-21 and Office Furniture for Kone nt tions nvelope ementation ba Woreda(Zone 2) under Af ar Region ET-MOF-355260-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 21,506.09 0.00 2023-05-03 2023-05-22 2023-06-21 and Office Furniture for Ewa nt tions nvelope ementation Woreda(Zone 3) under Afar R egion ET-MOF-355264-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 21,506.09 0.00 2023-05-03 2023-05-22 2023-06-21 and Office Furniture for Hade nt tions nvelope ementation leela Woreda(Zone 5) under Afar Region ET-MOF-355394-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 7,930.14 0.00 2023-05-03 2023-05-22 2023-06-21 and office furniture for Bulen nt tions nvelope ementation Woreda under Benishangul G umz Region ET-MOF-355399-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 7,930.14 0.00 2023-05-03 2023-05-16 2023-06-15 and office furniture for Mand nt tions nvelope ementation ura Woreda under Benishang ul Gumz Region ET-MOF-355404-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 7,930.14 0.00 2023-05-03 2023-05-22 2023-06-21 and office furniture for Sedal nt tions nvelope ementation Woreda under Benishangul G umz Region ET-MOF-355408-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 19,269.67 0.00 2023-05-03 2023-05-25 2023-06-24 and office furniture for Buleh nt tions nvelope ementation ora Woreda under Oromia R egion ET-MOF-355434-GO-RFQ / Pr ocurement ICT Equipment's a Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 17,706.25 0.00 2023-05-02 2023-05-24 2023-06-23 nd office furniture for Dagam nt tions nvelope ementation Woreda under Oromia Regio n ET-MOF-355435-GO-RFQ / Pr ocurement of ICT Material an Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 19,175.49 0.00 2023-05-02 2023-05-12 2023-06-11 d Office equipment's for Sibu nt tions nvelope ementation Sire under Oromia Region Page 1 ET-MOF-355436-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 11,648.45 0.00 2023-05-02 2023-05-21 2023-06-20 and office furniture for Sekot nt tions nvelope ementation a Zurya Woreda under Amha ra Region ET-MOF-355438-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 11,648.45 0.00 2023-05-02 2023-05-21 2023-06-20 and office furniture for Debar nt tions nvelope ementation k Woreda under Amhara Regi on ET-MOF-355443-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 11,648.45 0.00 2023-05-02 2023-05-21 2023-06-20 and office furniture for Meket nt tions nvelope ementation under Amhara Region ET-MOF-355444-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 11,648.45 0.00 2023-05-02 2023-05-21 2023-06-20 and office furniture for Delan nt tions nvelope ementation ta Woreda under Amhara Re gion ET-MOF-355446-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 11,648.45 0.00 2023-05-01 2023-05-20 2023-06-19 and office furniture for Dessi nt tions nvelope ementation e under Amhara Region ET-MOF-355447-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 11,648.45 0.00 2023-05-01 2023-05-20 2023-06-19 and office furniture for Kemis nt tions nvelope ementation sie Woreda under Amhara Re gion ET-MOF-355449-GO-RFQ / Pr ocurement of ICT Equipment Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl IDA / E0100 Post Limited 11,648.45 0.00 2023-05-02 2023-05-22 2023-06-21 and office furniture for Ataye nt tions nvelope ementation Woreda under Amhara Regio n ET-MOF-355450-GO-RFQ / Pr Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl ocurement of Office Equipme IDA / E0100 Post Limited 60,804.77 0.00 2023-05-02 2023-05-29 2023-06-28 nt tions nvelope ementation nt for Federal project Coordin ation Unit(FPCU) ET-MOF-355451-GO-RFQ / Pr Adaptive Project Manageme Request for Quota Single Stage - One E Pending Impl ocurement of Office Furniture IDA / E0100 Post Limited 15,916.79 0.00 2023-05-04 2023-06-08 2023-07-08 nt tions nvelope ementation for Federal Project Coordinati on Unit(FPCU) Rebuilding and Improving Ac ET-MOF-290756-GO-DIR / Pr IDA / E0100 cess to Basic Services and Cl Post Direct Selection Direct 2,400,000.00 0.00 Canceled 2022-05-26 2023-01-04 2022-05-31 2023-01-06 2022-07-05 2022-11-02 ocurement of Medicines imate-resilient Community I nfrastructure ET-MOF-290760-GO-DIR / Pr Rebuilding and Improving Ac ocurement of 50 Colposcopie cess to Basic Services and Cl IDA / E0100 Post Direct Selection Direct 150,000.00 0.00 Canceled 2022-06-22 2022-11-11 2022-06-27 2023-01-06 2022-08-01 2022-11-29 s with monitors (40 HCs and imate-resilient Community I 10 Primary Hospitals) nfrastructure ET-MOF-290757-GO-DIR / Pr ocurement of medical equip Rebuilding and Improving Ac ment (10 sets of Operating R cess to Basic Services and Cl IDA / E0100 Post Direct Selection Direct 9,000,000.00 0.00 Canceled 2022-07-06 2022-11-11 2022-07-11 2023-01-06 2022-08-15 2022-11-13 oom, 40 sets of Health Cente imate-resilient Community I r, 10 Primary Hospital and 10 nfrastructure One stop Center Medical Equi pment) ET-MOF-361498-GO-DIR / Pr Rebuilding and Improving Ac ocurement of Medical equip cess to Basic Services and Cl Direct - Internation Under Imple IDA / E0100 Prior Direct Selection 11,450,000.00 0.00 2023-05-22 2023-05-29 2023-05-27 2023-07-16 2024-01-12 ment and Medicine for conflic imate-resilient Community I al mentation t Affected health Facilities nfrastructure ET-MOF-363461-GO-DIR / Pr Rebuilding and Improving Ac Direct - Internation Pending Impl ocurement of Educational D IDA / E0100 cess to Basic Services and Cl Post Direct Selection 376,738.13 0.00 2023-05-29 2023-06-05 2023-06-19 2023-09-17 al ementation esktop Computers imate-resilient Community I nfrastructure NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOF-300392-NC-DIR / Pro Rebuilding and Improving Ac curement of Third Party Servi cess to Basic Services and Cl IDA / E0100 Prior Direct Selection Direct 25,000,000.00 25,000,000.00 Signed 2022-06-18 2022-06-20 2022-06-23 2022-06-21 2022-07-30 2022-07-20 2023-07-30 ce Provider in the High Risk o imate-resilient Community I f Conflict areas (Component nfrastructure 1) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOF-290906-CS-CQS / Se Rebuilding and Improving Ac Consultant Qualifi Pending Impleme lection of a consultancy firm IDA / E0100 cess to Basic Services and Cl Post Open - National 800,000.00 0.00 2022-07-13 2022-08-03 2022-09-16 2022-10-16 2022-11-20 2023-05-19 cation Selection ntation to function as Mobile Support imate-resilient Community I Team nfrastructure ET-MOF-290907-CS-QCBS / C Rebuilding and Improving Ac onsultancy firm Selection to cess to Basic Services and Cl Quality And Cost- Open - Internationa Pending Impleme Conduct Process Evaluation o IDA / E0100 Post 1,200,000.00 0.00 2022-09-21 2022-10-12 2022-11-25 2022-12-23 2023-01-22 2023-02-26 2023-04-02 2024-04-01 imate-resilient Community I Based Selection l ntation f the 3R4CACE project activiti nfrastructure es for project life (MoF) ET-MOF-290910-CS-QCBS / S Rebuilding and Improving Ac election of a consultant firm cess to Basic Services and Cl Quality And Cost- Pending Impleme IDA / E0100 Post Open - National 1,000,000.00 0.00 2022-08-29 2022-09-19 2022-11-02 2022-11-30 2022-12-30 2023-02-03 2023-03-10 2024-03-09 to provide training on deliver imate-resilient Community I Based Selection ntation y of MHPSS (for the wider sch nfrastructure ool community) ET-MOF-329648-CS-CQS / Co Adaptive Project Manageme Consultant Qualifi Under Implement nsultant firm to Conduct Bas IDA / E0100 Post Limited 250,000.00 0.00 2022-12-09 2022-12-10 2022-12-30 2023-03-07 2023-01-13 2023-05-30 2023-02-17 2023-08-16 nt cation Selection ation eline survey of 3R-4CACE pro ject ET-MOF-290905-CS-CQS / Co Rebuilding and Improving Ac nsultant firm Selection to co cess to Basic Services and Cl Consultant Qualifi IDA / E0100 Post Open - National 250,000.00 0.00 Canceled 2022-06-23 2022-07-14 2022-08-27 2022-09-26 2022-10-31 2023-04-29 nduct Woredas Needs, Confli imate-resilient Community I cation Selection ct and Capacity assessment ( nfrastructure MoF) Page 2 INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOF-290913-CS-INDV / H Rebuilding and Improving Ac Individual Consult Pending Impleme iring of Contract Administrati / cess to Basic Services and Cl Post Open 18,000.00 0.00 2022-09-20 2022-11-08 2022-11-29 2023-01-03 2024-01-03 ant Selection ntation on specialist for FPCU imate-resilient Community I nfrastructure ET-MOF-290912-CS-INDV / H Rebuilding and Improving Ac Individual Consult iring of a Procurement specia IDA / E0100 cess to Basic Services and Cl Prior Limited 27,000.00 0.00 Canceled 2022-06-13 2022-06-18 2022-07-09 2022-08-13 2023-08-13 ant Selection lists for FPCU imate-resilient Community I nfrastructure ET-MOF-290915-CS-INDV / H Adaptive Project Manageme Individual Consult iring of Financial Managemen IDA / E0100 Post Open 18,000.00 0.00 Canceled 2022-06-23 2022-07-21 2022-08-11 2022-09-01 2022-10-06 2023-10-06 nt ant Selection t Specialist at FPCU Rebuilding and Improving Ac ET-MOF-296625-CS-INDV / Pr Individual Consult IDA / E0100 cess to Basic Services and Cl Post Limited 20,000.00 0.00 Canceled 2022-06-22 2022-06-27 2022-07-18 2022-08-22 2023-08-22 oject coordinator for FPCU ant Selection imate-resilient Community I nfrastructure ET-MOF-296624-CS-CDS / Pr Rebuilding and Improving Ac ocurement of Third Party Ser cess to Basic Services and Cl IDA / E0100 Prior Direct Selection Direct 25,000,000.00 0.00 Canceled 2022-06-30 2022-06-09 2022-07-10 2022-06-13 2022-09-13 2023-03-12 vice Provider in the High Risk imate-resilient Community I of Conflict areas (Componen nfrastructure t 1) ET-MOF-305222-CS-INDV / R Adaptive Project Manageme Individual Consult ecruitment of Social Safegua IDA / E0100 Post Limited 18,000.00 0.00 Signed 2022-07-21 2022-08-02 2022-07-26 2022-07-24 2022-08-16 2022-09-12 2022-09-20 2023-09-20 nt ant Selection rd Specialist for the Ministry of Finance PCU ET-MOF-290914-CS-INDV / H Adaptive Project Manageme Individual Consult iring of Environmental Specia / Post Open 18,000.00 0.00 Canceled 2022-08-18 2022-07-21 2022-10-06 2022-10-27 2022-12-01 2023-12-01 nt ant Selection list at FPCU ET-MOF-307215-CS-INDV / R Adaptive Project Manageme Individual Consult ecruitment of Environmental IDA / E0100 Post Limited 18,000.00 0.00 Signed 2022-08-11 2022-08-11 2022-08-16 2022-08-03 2022-09-06 2022-08-09 2022-10-11 2023-10-11 nt ant Selection risk management specialist ET-MOF-307219-CS-INDV / R Adaptive Project Manageme Individual Consult ecruitment of Financial Mana IDA / E0100 Post Limited 18,000.00 0.00 Signed 2022-08-11 2022-08-11 2022-08-16 2022-08-11 2022-09-06 2022-09-13 2022-10-11 2023-10-11 nt ant Selection gement Specialist at FPCU ET-MOF-314056-CS-INDV / H Rebuilding and Improving Ac Individual Consult iring of a Project Coordinator IDA / E0100 cess to Basic Services and Cl Post Direct - National 30,000.00 0.00 Signed 2022-09-05 2022-09-09 2022-09-15 2022-06-01 2022-10-06 2022-06-06 2022-11-10 2023-11-10 ant Selection at FPCU imate-resilient Community I nfrastructure ET-MOF-314057-CS-INDV / H Rebuilding and Improving Ac Individual Consult Under Implement iring of a Procurement specia IDA / E0100 cess to Basic Services and Cl Post Direct - National 30,000.00 0.00 2022-09-05 2023-04-11 2022-09-15 2022-10-06 2022-11-10 2023-11-10 ant Selection ation lists for FPCU imate-resilient Community I nfrastructure ET-MOF-342748-CS-CDS / Co Rebuilding and Improving Ac nsultancy Service in Conducti cess to Basic Services and Cl Direct - Internation IDA / E0100 Post Direct Selection 250,000.00 0.00 Signed 2023-02-19 2023-02-20 2023-03-01 2023-02-27 2023-05-05 2023-11-01 ng Woreda Needs, Conflict a imate-resilient Community I al nd Capacity Assessment nfrastructure ET-MOF-360954-CS-INDV / R Rebuilding and Improving Ac Individual Consult Pending Impleme ecruitment of Deputy Project IDA / E0100 cess to Basic Services and Cl Post Direct - National 15,000.00 0.00 2023-05-22 2023-06-01 2023-06-04 2023-06-08 2024-06-07 ant Selection ntation Coordinator at Federal Level. imate-resilient Community I nfrastructure Page 3