PROCUREMENT PLAN (Textual Part) Project information: [country] [Project name] [P-number] Sri Lanka CLIMATE RESILIENCE MULTIPHASE PROGRAMMATIC APPROACH P 160005 Project Implementation agency: Ministry of Agriculture, Rural Economic Affairs, Livestock Development, Irrigation, Fisheries and Aquatic Resources Development : [insert legal name] Date of the Procurement Plan: [insert date]April 18, 2019 Period covered by this Procurement Plan: [insert from – to period]April 2019 to October 2021 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with the Procurement Regulations for IPF Borrowers (July 2016, revised November 2017) (“Procurement Regulations”), when approaching the national market, as agreed in the Procurement Plan tables in STEP, the country’s own procurement procedures may be used. When the Borrower, for the procurement of goods, works and non-consulting services, uses its own national open competitive procurement arrangements as set forth in Sri Lanka’s Procurement Guidelines 2006, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations and the following conditions: 1. Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 3. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations): accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. : In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable”Not Applicable Procurement of Second- Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables : Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Sri Lanka : Climate Resilience Multi-Phase Programmatic Approach PLAN General Information Country: Sri Lanka 2022-07-2 Bank’s Approval Date of the Original Procurement Plan: 2024-06-0 9 if none) Revised Plan Date(s): (comma delineated, leave blank Project ID: P160005 GPN Date: 9 2019-07-2 Project Name: Climate Resilience Multi-Phase Programmatic Approach 8 Loan / Credit No: IBRD / 89960 MINISTRY OF IRRIGATION Executing Agency(ies): WORKS Activity Reference No Procuremen Estimate Actual Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati High SEA/S Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Comp . / Description Component Review Type Method t Document d Amou Amount ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) H Risk Status on Documents aluation Report as Issued letion Type nt (US$) (US$) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne National Procur d d d d d d d d d SLMOI/CRES/DOM/W/NCB/ Component 1: Forecasting ement Docume 01 / Construction of Nation and Early Warning of High Request for Bid Single Stage - On 4,500,000. 2022-09- 2022-10- 2022-10- 2022-11- 2023-02- 2024-06 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 Canceled al Meteorological Center Bu Impact Weather, Floods an s e Envelope 00 30 05 26 25 17 -14 process (Non B ilding at Department of Met d Landslides ank-SPD) eorology National Procur SLMOI/CRES/ID/W/NCB/03 / Component 1: Forecasting ement Docume Refurbishment of the office and Early Warning of High Request for Bid Single Stage - On Complete 2022-08- 2022-10- 2022-09- 2022-09- 2022-11- 2022-10- 2023-01- 2022-11- 2023-02- 2023-01 IBRD / 89960 Post Open - National nt - 1 Envelope 56,000.00 0.00 space of Hydrology & DM D Impact Weather, Floods an s e Envelope d 31 12 05 26 29 17 26 14 08 -13 process (Non B ivision of Irrigation Depart d Landslides ank-SPD) ment National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MATL/RFQ/009 / Improvem limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 32,691.67 0.00 mplemen ants to main canal in Bowa tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B tation thenna scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume PUT/NCB/007 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-09- 2023-10- 2023-11- 2024-05 IBRD / 89960 Post Open - National nt - 1 Envelope 99,740.00 0.00 Canceled nts to Maiyawa tank & 1st s tenance of irrigation and s s e Envelope 02 07 18 18 22 -07 process (Non B pill in Sengaloya scheme torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID-J ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-01 AF/RFQ/003 / Improvement IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 Canceled tenance of irrigation and s tations e Envelope 07 02 -30 of Paravaikadal SWE Bund process (Non B torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- NUE/RFQ/004 / Constructio National Procur Component 5: Improving c n of canal lining from 4+33 ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 2 to 4+394, 4+426 to 4+4 IBRD / 89960 Post Limited nt - 1 Envelope 27,076.67 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -28 38, 4+516 to 4+536 & 4+5 process (Non B tation torm water infrastructure 50 to 4+580, Improvement ank-SPD) s to canal bund in main can al of Paragahaarawa schem e National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KUR/RFQ/028 / Reconstruct limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 28,270.00 0.00 Canceled ion of sluice at Kiniyama ta tenance of irrigation and s tations e Envelope 07 02 -28 process (Non B nk torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MATR/RFQ/009 / Improvem limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 22,500.00 0.00 Canceled ents to drainage canals in tenance of irrigation and s tations e Envelope 07 02 -29 process (Non B Kadawedduwa scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume ANU/RFQ/008 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 20,666.67 0.00 Canceled nts to Causeway in D4/5 Dr tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B ainage canal in Wahalkada torm water infrastructure ank-SPD) Scheme in Padaviya Divisio n CRESMPA-1/RP/WORKS/ID- National Procur ANU/RFQ/018 / Constructio Component 5: Improving c ement Docume Pending I n of Drainage undercrossin limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplemen g structure including canal tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation drop structure at stn 1+09 torm water infrastructure ank-SPD) 0 in feeder canal of Solewe wa in Rajanaganya Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAT/NCB/010 / Reconstruct limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-01 IBRD / 89960 Post Open - National nt - 1 Envelope 53,333.33 0.00 Canceled ion of Vinayagar Anicut in tenance of irrigation and s tations e Envelope 05 30 -08 process (Non B Navakiri scheme, Navakiri torm water infrastructure ank-SPD) Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume COL/RFQ/037 / Desilting an limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 25,508.34 0.00 Canceled d removing obstacles in Ha tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B ldummulla canal from 0+0 torm water infrastructure ank-SPD) 00km to 1+000km CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/RFQ/065 / Construction ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 of retangular canal lining fr IBRD / 89960 Post Limited nt - 1 Envelope 16,800.00 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -28 om stn. 0+475 to stn. 0+5 process (Non B tation torm water infrastructure 25 in Yaya 6 D canal, Tract ank-SPD) 6 DCFO Area CRESMPA-1/RP/WORKS/ID- National Procur POL/NCB/005 / Constructio Component 5: Improving c ement Docume Under Im n of 147m long concrete re limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 71,433.33 0.00 plementa ctangular canal lining from tenance of irrigation and s s e Envelope 31 07 05 16 16 20 -14 process (Non B tion stn 4+376 to stn 4+526.5 i torm water infrastructure ank-SPD) n B506/507 branch canal in Aththanakadawala unit. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MON/RFQ/026 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 31,666.67 0.00 mplemen on of FC 18 canal in LBMC tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B tation Hambegamuwa torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/103 / Constructio limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-11- 2024-05 IBRD / 89960 Post Open - National nt - 1 Envelope 50,533.33 0.00 plementa n of Gabion Walls along the tenance of irrigation and s s e Envelope 31 06 05 16 16 20 -18 process (Non B tion Rota wewa bund in MKYE in torm water infrastructure ank-SPD) Minneriya Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/027 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-10- 2023-08- 2023-09- 2023-11- 2023-10- 2023-12- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 plementa nts to Palugasmada Feeder tenance of irrigation and s s e Envelope 31 30 05 16 29 16 15 20 -14 process (Non B tion canal torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur POL/RFQ/009 / Construction Component 5: Improving c ement Docume Pending I of 50 m long concrete recta limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 37,833.33 0.00 mplemen ngular canal lining from stn tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B tation 1+202 to stn 1+252 in B50 torm water infrastructure ank-SPD) 6/507 branch canal in Atht hanakadawala unit. CRESMPA-1/RP/WORKS/ID- POL/NCB/122 / Demalishing National Procur Component 5: Improving c old damaged hump pipe tr ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 ough at stn 0+830 & const IBRD / 89960 Post Open - National nt - 1 Envelope 66,666.67 0.00 plementa tenance of irrigation and s s e Envelope 31 06 05 16 16 20 -14 ruction rectangular trough process (Non B tion torm water infrastructure structure and rectangular c ank-SPD) anal lining stn 0+730 to st n 0+920 in Jamburewela D CFO area National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I POL/RFQ/012 / Construction limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplemen of Feeder Canal for Baddep tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation anwila Tank torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I POL/RFQ/015 / Construction limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 mplemen of Godapoththa Bridge Stru tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation cture torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/NCB/140 / Constructio ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 n of the 25m long damage IBRD / 89960 Post Open - National nt - 1 Envelope 66,666.67 0.00 plementa tenance of irrigation and s s e Envelope 31 06 05 16 16 20 -14 d cantiliver wall section at process (Non B tion torm water infrastructure stn. 9+100 RB side of the E ank-SPD) MYE main canal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/037 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-10- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 plementa nsts to FC 50 canal & bund tenance of irrigation and s s e Envelope 31 30 05 16 16 20 -14 process (Non B tion road of RB main Canal in H torm water infrastructure ank-SPD) andapanagala CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MON/NCB/041 / Demolishin ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-10- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 g and Reconstruction of tro IBRD / 89960 Post Open - National nt - 1 Envelope 56,586.67 0.00 plementa tenance of irrigation and s s e Envelope 31 30 05 16 16 20 -14 ugh and lining structure at process (Non B tion torm water infrastructure 12+940 in Kumbukkana m ank-SPD) ain canal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/042 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-07- 2024-03- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 42,666.67 0.00 plementa nt of 1st Km RBMC in Maha tenance of irrigation and s s e Envelope 31 19 05 16 16 20 -14 process (Non B tion wewa torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MON/RFQ/043 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplemen nts of spill in Debara ara Ta tenance of irrigation and s tations e Envelope 05 30 -25 process (Non B tation nk torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 POL/RFQ/019 / Construction IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -28 of Godapoththa anicut process (Non B tation torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I POL/RFQ/149 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 2 Envelope 33,333.33 0.00 mplemen ts to 198 - Kongahawewa ( tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation Second stage) in Konwewa torm water infrastructure ank-SPD) DCO area National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MON/RFQ/047 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplemen n of 50m lining at 1+325 in tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B tation RB main canal in Saddatiss torm water infrastructure ank-SPD) a National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I POL/RFQ/027 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 35,433.33 0.00 mplemen ts to FC 13 canal in Sama D tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation CO area in HLMC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/031 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-11- 2024-09 IBRD / 89960 Post Open - National nt - 1 Envelope 75,933.33 0.00 plementa nts to RB 01 canal (from 55 tenance of irrigation and s s e Envelope 31 06 05 16 16 20 -15 process (Non B tion 0 m to 750m) in CP Pura Pe torm water infrastructure ank-SPD) rakum DCO area in LLMC National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I POL/RFQ/034 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 18,186.67 0.00 mplemen ts to RB6 canal in Galtham tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation barawa DCO torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MON/RFQ/57 / Rehabilitatio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 mplemen n of LB canal section 1 in K tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation aradanda Ara Tank torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MON/RFQ/58 / Rehabilitatio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 48,333.33 0.00 mplemen n of LB canal section 2 in K tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation aradanda Ara Tank torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MON/RFQ/59 / Extention to limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 43,333.33 0.00 mplemen LB and RB canals in Kiuvle tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation tank (500 m) torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I ANU/RFQ/012 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 29,300.00 0.00 mplemen nts to U/S and D/S Trough s tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B tation tructure in Ellapothana sch torm water infrastructure ank-SPD) eme, Huruluwewa Division CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c ANU/RFQ/013 / Demolishin ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 g and Reconstruction of Th IBRD / 89960 Post Limited nt - 1 Envelope 36,666.67 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -24 ubulla Regulator at RB Mai process (Non B tation torm water infrastructure n Canal in Rajanganaya Sc ank-SPD) heme CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c ANU/NCB/015 / Improveme ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-12- 2023-08- 2023-09- 2024-01- 2023-10- 2024-02- 2023-11- 2024-11 nt to LB Main Canal of Huru IBRD / 89960 Post Open - National nt - 1 Envelope 63,100.00 0.00 plementa tenance of irrigation and s s e Envelope 31 04 05 16 03 16 26 20 -14 luwewa and Ulpathgama fi process (Non B tion torm water infrastructure eld canal (FC 04) road in H ank-SPD) uruluwewa Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume ANU/NCB/024 / Renovation limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-11- 2023-08- 2023-09- 2024-01- 2023-10- 2024-02- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 56,666.67 0.00 Signed to the damaged section of tenance of irrigation and s s e Envelope 31 29 05 16 03 16 26 20 -14 process (Non B spillway in Kallanchiya tank torm water infrastructure ank-SPD) in Anuradhapura National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I ANU/RFQ/025 / Reconstruct limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplemen ion of LB 01, D 09 and FC 0 tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B tation 3 canals of Lower Main Can torm water infrastructure ank-SPD) al in Padaviya National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I ANU/RFQ/032 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 19,766.67 0.00 mplemen nts to FC34, D 09 and RBM tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B tation C in Huruluwewa scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im GAL/RFQ/006 / Dredging fie limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 32,696.67 0.00 plementa ld canals & D-canals in Hol tenance of irrigation and s tations e Envelope 05 21 30 -26 process (Non B tion uwagoda II scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im GAL/NCB/011 / Constructio limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-10- 2023-08- 2023-09- 2023-10- 2023-10- 2023-11- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 51,233.33 0.00 plementa n of bank protection for err tenance of irrigation and s s e Envelope 31 03 05 16 27 16 09 20 -14 process (Non B tion oded section in Holuwagod torm water infrastructure ank-SPD) a I scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/035 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-11- 2024-05 IBRD / 89960 Post Open - National nt - 1 Envelope 67,833.33 0.00 plementa nts to branch canal (17m t tenance of irrigation and s s e Envelope 31 06 05 16 16 20 -18 process (Non B tion o 300m) in Ekasth (1B Yaya torm water infrastructure ank-SPD) ) DCO area in LLMC National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I POL/RFQ/038 / Construction limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 26,953.33 0.00 mplemen of 145m long retaining wall tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B tation in LB side in RB 06 off D2 torm water infrastructure ank-SPD) main canal CRESMPA-1/RP/WORKS/ID- POL/RFQ/039 / Construction National Procur Component 5: Improving c of Retaining wall in D 02 ca ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 nal (Construction of 200 m IBRD / 89960 Post Limited nt - 1 Envelope 37,933.33 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -26 length Retaining wall both process (Non B tation torm water infrastructure side of the main canal from ank-SPD) No. 533 Mr. Premasiri's pad dy land to No 527 Mr. Liyan age's paddy land) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I POL/RFQ/047 / Gravelling D limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 19,906.67 0.00 mplemen 8 main canal road (about 4 tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B tation km) torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur MATR/NCB/008 / Improvem Component 5: Improving c ement Docume ents of Ellekanda tank mai limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-08- 2023-10- 2023-11- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 56,000.00 0.00 Signed n canal construction of can tenance of irrigation and s s e Envelope 31 28 05 16 27 16 13 20 -14 process (Non B al lining from CH 4+ 147.5 torm water infrastructure ank-SPD) to 4+347.5 in Kekanadura scheme ( 200m) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MATR/RFQ/011 / Improvem limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 39,200.00 0.00 mplemen ents of main canal at Nama tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation midola near karaputugala s torm water infrastructure ank-SPD) chool in Ellewela scheme CRESMPA-1/RP/WORKS/ID- National Procur MATR/NCB/014 / Improvem Component 5: Improving c ement Docume Under Im ents to uyanwewa Scheme( limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-10- 2023-11- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 54,833.33 0.00 plementa Sub1-Improvements to Uya tenance of irrigation and s s e Envelope 31 28 05 16 27 16 13 20 -14 process (Non B tion nwewa tank bund, Sub2-Im torm water infrastructure ank-SPD) provements to spill tail can al & LB main canal in Uyan wewa scheme) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MATR/NCB/016 / Improvem limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-10- 2023-11- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 53,800.00 0.00 plementa ents to Haliela main canal i tenance of irrigation and s s e Envelope 31 26 05 16 27 16 13 20 -14 process (Non B tion n Haliela scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MATR/RFQ/019 / Improvem limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-04 IBRD / 89960 Post Limited nt - 1 Envelope 21,133.33 0.00 mplemen ents of palolpitiya D'canal i tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B tation n Urapola scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MATR/RFQ/020 / Constructi limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-04 IBRD / 89960 Post Limited nt - 1 Envelope 18,600.00 0.00 mplemen on of canal lining along the tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B tation main spill cannel at wadoru torm water infrastructure ank-SPD) wa anicut in Ellewela sche me National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I POL/RFQ/050 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 27,243.33 0.00 mplemen ts to LB 1 canal in Debarell tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B tation a DCO area torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/063 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-11- 2024-05 IBRD / 89960 Post Open - National nt - 1 Envelope 72,426.67 0.00 plementa nts to FC - 03 canal in Mah tenance of irrigation and s s e Envelope 31 06 05 16 16 20 -18 process (Non B tion aweli DCO area in HLBC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I AMP/RFQ/008 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 30,980.00 0.00 mplemen nts to main Canal from Stn tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B tation 0+000 to 0+040 in Pannal torm water infrastructure ank-SPD) gama scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im AMP/NCB/009 / Reconstruct limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-11- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 61,633.33 0.00 plementa ion of DC 03 morning Glory tenance of irrigation and s s e Envelope 31 08 05 16 16 20 -14 process (Non B tion spill in RB main canal at st torm water infrastructure ank-SPD) n 25+200 in Damana unit National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I AMP/RFQ/010 / Reconstruct limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplemen ion of DR 13 MG structure tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B tation @ 11+850 in Ekkaloya MC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im AMP/NCB/011 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 91,566.67 0.00 plementa nts of structures in G 07 c tenance of irrigation and s s e Envelope 31 28 05 16 16 20 -14 process (Non B tion anal at Gonagolla unit torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c AMP/RFQ/013 / Reconstruct ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 ion of 1.5 m span ,11.5 m IBRD / 89960 Post Limited nt - 1 Envelope 32,713.33 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -26 width culvert including Ret process (Non B tation torm water infrastructure aining wall at stn 0+385 in ank-SPD) PK-28 D canal in Illukuchen ai unit Page 1 CRESMPA-1/RP/WORKS/ID- National Procur AMP/RFQ/014 / Constructio Component 5: Improving c ement Docume Pending I n of 4m span box culvert , limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 21,666.67 0.00 mplemen drainage inlet & LB turnou tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B tation t structure in SK 04/1 drain torm water infrastructure ank-SPD) age canal at the tail end of SK 11 Distributary canal CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c AMP/RFQ/016 / Improveme ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 nts to SKDC, SK-03 Distribu IBRD / 89960 Post Limited nt - 1 Envelope 22,900.00 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -27 tary canal and SK-16 Distri process (Non B tation torm water infrastructure butary canal in SKBC in Akk ank-SPD) araipattu unit. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I AMP/RFQ/017 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 49,140.00 0.00 mplemen nts to KLBC in Deegawapi u tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation nit torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c AMP/RFQ/018 / Improveme ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 nts to Seenampity Main Ch IBRD / 89960 Post Limited nt - 1 Envelope 44,260.00 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -24 annel from stn. 0+000 to st process (Non B tation torm water infrastructure n. 0+650 Km. in Veerayadi ank-SPD) unit National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I AMP/RFQ/020 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 28,171.17 0.00 mplemen n of Box culverts across Sal tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B tation madu Periyaveli Main Chl. i torm water infrastructure ank-SPD) n Paddampitty Unit National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume AMP/RFQ/022 / improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 32,600.00 0.00 Canceled nt of Udangaveli Anicut in tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B Moravil unit II torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MATL/RFQ/008 / Improvem limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 31,670.00 0.00 mplemen ents to D52 RB 2 Canal in S tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B tation tage III torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I AMP/RFQ/025 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 18,583.33 0.00 mplemen nts to Regulators and offta tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B tation kes in Sengappadai LB unit torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c AMP/RFQ/033 / Constructio ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 n of 5 m width box culvert IBRD / 89960 Post Limited nt - 1 Envelope 30,586.67 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -26 cum regulator in Kalladi ch process (Non B tation torm water infrastructure annel stn at 0+425 at Kara ank-SPD) ngowa in Nawalaru scheme CRESMPA-1/RP/WORKS/ID- National Procur AMP/RFQ/036 / Constructio Component 5: Improving c ement Docume Pending I n of two Morning Glory Spill limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 29,103.33 0.00 mplemen s in LB 24 canal & Improve tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B tation ments to structures in LB 1. torm water infrastructure ank-SPD) 1 field canal of Senagama Dambe Ela Anicut in Gonag olla Unit National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume AMP/RFQ/037 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 18,830.00 0.00 Canceled nts to Regulater structures tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B in Pannalgama scheme torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 AMP/RFQ/072 / Improveme IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -26 nt for Tank Bund process (Non B torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 AMP/RFQ/074 / Improveme IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -27 nt of Main Cannel process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume AMP/RFQ/075 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 Canceled nt of Tank Bund and Canne tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B l torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 AMP/RFQ/076 / Improveme IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -24 nt of Tank Bund process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume AMP/RFQ/078 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled nt for Tank Bund, Spill, Slui tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B ce torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KUR/RFQ/008 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 19,499.33 0.00 Canceled nts to D19 canal of Doluka tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B nda canal in Bathalagoda S torm water infrastructure ank-SPD) cheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KUR/NCB/013 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 76,666.67 0.00 Canceled nts to FC1 and FC2 canals tenance of irrigation and s s e Envelope 31 05 16 16 20 -14 process (Non B under Mukalanyaya D2 can torm water infrastructure ank-SPD) al in Bathalagoda scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I HAM/RFQ/009 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 45,896.67 0.00 mplemen nts to Police ela (0+900 - 1 tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation +050) of HLMC,Tissa Wewa torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c HAM/RFQ/010 / Improveme ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 nts to Medagoda Ela from 0 IBRD / 89960 Post Limited nt - 1 Envelope 35,060.82 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -24 +085 to 0+330 in Welipata process (Non B tation torm water infrastructure nwila RB canal of Oluwila u ank-SPD) nit in WRB scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I HAM/RFQ/012 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 46,990.00 0.00 mplemen n of canal lining from (0+0 tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation 25 - 0+124) in main canal, torm water infrastructure ank-SPD) Bandagiriya CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c HAM/RFQ/013 / Improveme ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 nts to Medagoda Ela (0+33 IBRD / 89960 Post Limited nt - 1 Envelope 37,014.67 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -24 0 - 0+595) in Welipatanwil process (Non B tation torm water infrastructure a RB canal of Oluwila Unit i ank-SPD) n WRB Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I HAM/RFQ/018 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 43,230.00 0.00 mplemen nts to FC 15,DC 02,Track 0 tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation 2,RBMC, Lunugamwehera torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c HAM/RFQ/020 / Improveme ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 nts to Overtopping section IBRD / 89960 Post Limited nt - 1 Envelope 25,490.00 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -27 at 0+412 (150m) in Nawar process (Non B tation torm water infrastructure athnamulana Canal, Urubo ank-SPD) kka - oya scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I HAM/RFQ/021 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 35,113.33 0.00 mplemen nts to FC36 DC3 Bandagiriy tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B tation a Scheme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c KUR/RFQ/016 / Constructio ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 n of regulator structure at IBRD / 89960 Post Limited nt - 1 Envelope 16,926.67 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -28 22+300 in LB Main canal in process (Non B torm water infrastructure Wariyapola (Starting point ank-SPD) of Branch canal 01) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I HAM/RFQ/025 / Installing fa limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 16,901.03 0.00 mplemen rm turn out and canal linin tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B tation g at 0+010 to 0+171 in SR torm water infrastructure ank-SPD) B RB 01 canal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I HAM/NCB/063 / Reconstruc limate resilience and main Request for Bid Single Stage - On 100,000.0 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 mplemen tion of weheragal anicut ac tenance of irrigation and s s e Envelope 0 31 05 16 16 20 -14 process (Non B tation ross malala ara torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 HAM/RFQ/076 / Improveme IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -24 nts to Wak ari wewa process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KUR/RFQ/022 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 24,666.67 0.00 Canceled n of closed under crossing tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B at 1+573 in Branch Canal 2 torm water infrastructure ank-SPD) in Wariyapola National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KUR/RFQ/027 / Improving c limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 27,814.33 0.00 mplemen anal from 0+850 to 1+055 tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B tation by half-circular pipes in We torm water infrastructure ank-SPD) llangiriya scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KUR/NCB/030 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 Canceled on of trough in LB canal of tenance of irrigation and s s e Envelope 31 05 16 16 20 -14 process (Non B Mahasiyabalangamuawa torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im GAL/NCB/017 / Constructio limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-10- 2023-11- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 40,000.00 0.00 plementa n of new Structures in Mehi tenance of irrigation and s s e Envelope 31 28 05 16 27 16 06 20 -14 process (Non B tion mulla scheme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c GAL/RFQ/029 / Improveme ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 nts to Agriculture road fro IBRD / 89960 Post Limited nt - 1 Envelope 17,980.00 0.00 mplemen tenance of irrigation and s tations e Envelope 05 30 -28 m Kammalgodayaya to Ath process (Non B tation torm water infrastructure ula Darshanarama road (1 ank-SPD) +050 km to 1+750 km) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I GAL/RFQ/030 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 3,333.33 0.00 mplemen nts to canals, flood bunds, tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B tation structures and pump house torm water infrastructure ank-SPD) in Kiribathawila scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im GAL/NCB/044 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2023-07- 2024-04- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 51,666.67 0.00 plementa on of gates of 2 and 3 anic tenance of irrigation and s s e Envelope 31 10 05 16 16 20 -14 process (Non B tion ut of Heenela torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KUR/NCB/066 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-10 IBRD / 89960 Post Open - National nt - 1 Envelope 8,000.00 0.00 Canceled nts to Digandeniya tank in tenance of irrigation and s s e Envelope 31 05 16 16 06 -31 process (Non B Narammala torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c POL/DC/002 / Installing 02 Other (with fiel limate resilience and main 2023-07- 2023-02- 2023-08- 2023-02- 2023-09- 2023-10- 2024-01 Nos of lifting hoist and othe IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,666.67 0.00 Signed tenance of irrigation and s 31 09 05 16 09 05 -07 r remedial works for Thamb n) torm water infrastructure alawewa Sluice gate in Min neriya Division CRESMPA-1/RP/WORKS/ID- MON/DC/002 / Repair and i nstallation of 10 Nos of fee Component 5: Improving c der canal gates at 01 Nos o Other (with fiel limate resilience and main 2023-07- 2023-04- 2023-08- 2023-05- 2023-09- 2023-10- 2024-01 f 5.4ft*3.3ft Regulator gate IBRD / 89960 Post Direct Selection Direct - National d for explanatio 19,055.89 0.00 Signed tenance of irrigation and s 31 28 05 02 09 12 -07 D3 and 01Nos of 5.4ft*3.3ft n) torm water infrastructure Regulator gate near 01 Nos of 5.4ft&3.3ft Regulator gat e at D 4 in main canel at M uthukeliywa Scheme in Mo naragala Division CRESMPA-1/RP/WORKS/ID- ANU/DC/005 / Fabrication a Component 5: Improving c Other (with fiel nd Installation of 03 Nos of limate resilience and main 2023-07- 2023-06- 2023-08- 2023-06- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 25,892.20 0.00 Signed regulator gates (1025x900 tenance of irrigation and s 31 01 05 06 09 -07 n) mm) of MawathaWewa Ani torm water infrastructure cut in Nachchaduwa Divisio n, Anuradhapura CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel MON/DC/025 / Construction limate resilience and main 2023-07- 2023-04- 2023-08- 2023-05- 2023-09- 2023-11- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 35,943.74 0.00 Signed of 30m long trough structur tenance of irrigation and s 31 26 05 02 09 28 -03 n) e from 0+126 to 0+156 in torm water infrastructure Main canal in Kotiyagala CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel POL/DC/022 / Construction limate resilience and main 2023-07- 2023-05- 2023-08- 2023-06- 2023-09- 2023-10- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,973.33 0.00 Signed of 30m long Retaining wall tenance of irrigation and s 31 26 05 02 09 02 -07 n) in RB side at 2+150 in LB 4 torm water infrastructure /D 2 main canal CRESMPA-1/RP/WORKS/ID- MATR/DC/004 / Fabrication, Component 5: Improving c Other (with fiel Painting & Installation of 16 limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 14,433.97 0.00 Signed 80mmx1300mm Mild Steel tenance of irrigation and s 31 30 05 09 09 -07 n) gates with gear box (04 No torm water infrastructure s) for Hapowita amuna anic ut at Matara Division, Galle CRESMPA-1/RP/WORKS/ID- HAM/DC/006 / Repair regul ar gates in GR3,GR5,GR6,G Component 5: Improving c Other (with fiel R8,GR9,GR10,GR11,GR13, limate resilience and main 2023-07- 2023-07- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 12,239.32 0.00 Signed GR14,GR18 in RBMC and F tenance of irrigation and s 31 07 05 15 09 -07 n) abricating, painting and ins torm water infrastructure talling 3 Nos of 1372mmx9 15mm mild steel regulator gates in Kaludora (GR 8) in RBMC Lunugamwehera Res CRESMPA-1/RP/WORKS/ID- ervoir Component 5: Improving c Other (with fiel MON/DC/021 / Improvemen limate resilience and main 2023-07- 2023-04- 2023-08- 2023-05- 2023-09- 2023-11- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 48,666.67 0.00 Signed ts to FC 03 canal & bund ro tenance of irrigation and s 31 26 05 02 09 28 -03 n) ad of RB main canal in Han torm water infrastructure dapanagala Wewa CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel MON/DC/003 / Impovermen limate resilience and main 2023-07- 2023-04- 2023-08- 2023-05- 2023-09- 2023-11- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 38,365.45 0.00 Signed ts to causeway at 8+620 in tenance of irrigation and s 31 26 05 02 09 28 -03 n) in bund road in Muthukandi torm water infrastructure ya Scheme CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel POL/DC/010 / Construction limate resilience and main 2023-07- 2023-05- 2023-08- 2023-06- 2023-09- 2023-10- 2023-10 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 48,440.00 0.00 Signed of retaining wall at 10+50 tenance of irrigation and s 31 26 05 02 09 02 -03 n) 0 in D1 east canal torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel RAT/DC/084 / Repairing of limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,666.67 0.00 Signed Damme Ela anicut main ga tenance of irrigation and s 31 29 05 06 09 -07 n) te torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I KAL/DC/010 / Improvement limate resilience and main 2023-07- 2023-08- 2023-09- 2024-02 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,333.33 0.00 mplemen to Aluth Ela( 5+700-11+00 tenance of irrigation and s 31 05 09 -06 n) tation 0) torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KUR/DC/002 / Repairs of M limate resilience and main 2023-07- 2023-06- 2023-08- 2023-06- 2023-09- 2023-08- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,338.26 0.00 Signed agalla RB Sluice Gate Repai tenance of irrigation and s 31 02 05 09 09 21 -07 n) r in Nikawaratiya Division torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel RAT/DC/005 / Construction limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 10,333.33 0.00 Signed of Over crossing at 7+600k tenance of irrigation and s 31 29 05 06 09 -07 n) m in RB Main canal in Kalth torm water infrastructure ota Scheme CRESMPA-1/RP/WORKS/ID- GAL/DC/002 / Fabrication,P Component 5: Improving c Other (with fiel ainting & Installation of 122 limate resilience and main 2023-07- 2023-05- 2023-08- 2023-06- 2023-09- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,873.78 0.00 Signed 0mmx1695mm Mild Steel g tenance of irrigation and s 31 31 05 20 09 01 -07 n) ates (01Nos) for Dombagah torm water infrastructure awatha Anicut at Ambalang oda Division,Galle CRESMPA-1/RP/WORKS/ID- HAM/DC/001 / Fabrication, Component 5: Improving c Other (with fiel sandblasting,painting and i limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 12,882.24 0.00 Signed nstallation 04Nos of 1600m tenance of irrigation and s 31 29 05 15 09 -07 n) mx1524mm mild steel gate torm water infrastructure s in Kahagaha amuna Anic ut, Kongalara CRESMPA-1/RP/WORKS/ID- HAM/DC/002 / Fabrication, Component 5: Improving c Other (with fiel sandblasting,painting and i limate resilience and main 2023-07- 2023-07- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 7,309.52 0.00 Signed nstallation 03Nos of 1474m tenance of irrigation and s 31 07 05 15 09 -07 n) mx1397mm mild steel regu torm water infrastructure lator gates in Heelagedeniy a amuna Anicut, Kongal ara CRESMPA-1/RP/WORKS/ID- Component 5: Improving c HAM/DC/005 / Fabrication, Other (with fiel Under Im limate resilience and main 2023-07- 2023-07- 2023-08- 2023-07- 2023-09- 2024-01 painting and installation 02 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,540.93 0.00 plementa tenance of irrigation and s 31 07 05 15 09 -07 Nos of gates in Liyangastot n) tion torm water infrastructure a and 01 No of gate in abar ana alla in RBMC Liyangast ota CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel POL/DC/001 / Improvement limate resilience and main 2023-07- 2023-02- 2023-08- 2023-02- 2023-09- 2023-10- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 33,000.00 0.00 Signed s to gates and hosting syst tenance of irrigation and s 31 09 05 16 09 05 -07 n) em of Anganmedilla anicut torm water infrastructure in Polonnaruwa CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Under Im GAL/DC/046 / Rehabilitatio limate resilience and main 2023-07- 2023-05- 2023-08- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,666.67 0.00 plementa n of 3 aniut and constructio tenance of irrigation and s 31 22 05 09 -07 n) tion n of new anicut and desiltin torm water infrastructure g Wagonneyaya canala CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KAL/DC/012 / Improvement limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2023-11- 2024-04 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,000.00 0.00 Signed s to Haliyapitiya ela (0+00 tenance of irrigation and s 31 30 05 05 09 21 -06 n) 0 to 4+000) in Bolgoda sch torm water infrastructure eme CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel POL/DC/030 / Gravelling of limate resilience and main 2023-07- 2023-05- 2023-08- 2023-06- 2023-09- 2023-10- 2024-03 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,843.33 0.00 Signed Agri road at RB17 from 4+ tenance of irrigation and s 31 26 05 02 09 05 -07 n) 110 to 5+410 in weerapura torm water infrastructure DCO CRESMPA-1/RP/WORKS/ID- KAL/DC/002 / Fabrication , Component 5: Improving c Other (with fiel sandblasting , painting & in limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2023-10- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 38,100.00 0.00 Signed stallation of gates with lifti tenance of irrigation and s 31 30 05 05 09 09 -07 n) ng machanism and embed torm water infrastructure ded parts at Danwatte , Col ombo Division CRESMPA-1/RP/WORKS/ID- HAM/DC/003 / Fabrication, Component 5: Improving c Other (with fiel Under Im sandblasting,painting and i limate resilience and main 2023-07- 2023-07- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,327.87 0.00 plementa nstallation 02Nos of 1499m tenance of irrigation and s 31 07 05 15 09 -07 n) tion mx1753mm mild steel regu torm water infrastructure lator gates in Liyanagedeni ya amuna Anicut, Kirama a ra CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel BAD/DC/075 / Fabrication a limate resilience and main 2023-07- 2023-05- 2023-08- 2023-06- 2023-09- 2023-10- 2023-12 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,610.00 0.00 Signed nd Installation 03Nos of Re tenance of irrigation and s 31 31 05 06 09 10 -08 n) gulator Gate at Dambaraw torm water infrastructure a Main Canal Page 2 CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel RAT/DC/085 / Repairing of limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,000.00 0.00 Signed Batugedara Main Anicut ga tenance of irrigation and s 31 29 05 06 09 -07 n) te torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel GAL/DC/013 / Improvement limate resilience and main 2023-07- 2023-05- 2023-08- 2023-06- 2023-09- 2023-08- 2024-07 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 28,930.00 0.00 Signed s to Hiyare reservoir in Hol tenance of irrigation and s 31 28 05 20 09 21 -05 n) uwagoda scheme torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I GAL/DC/014 / Construction limate resilience and main 2023-07- 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 75,263.33 0.00 mplemen Olanda anicut at stn 0+025 tenance of irrigation and s 31 05 09 -03 n) tation km in Olanda channel torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I KAL/DC/019 / Improvement limate resilience and main 2023-07- 2023-08- 2023-09- 2024-02 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,000.00 0.00 mplemen s to flood controlling gate a tenance of irrigation and s 31 05 09 -06 n) tation t Kalugoda flood bund ( 1n torm water infrastructure os) gate number 2. CRESMPA-1/RP/WORKS/ID- Component 5: Improving c MATL/DC/001 / Fabrication Other (with fiel limate resilience and main 2023-08- 2023-06- 2023-08- 2023-07- 2023-09- 2024-01 & Installation 06 Nos of hoi IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,199.99 0.00 Signed tenance of irrigation and s 15 25 20 09 24 -22 sting mechanism ,Spindle n) torm water infrastructure with lifting lever at Dambul uoya Anicut CRESMPA-1/RP/WORKS/ID- MATL/DC/002 / Fabrication Component 5: Improving c Other (with fiel & Installation of 02 Nos of limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,769.99 0.00 Signed gates (900mm 1050mm & tenance of irrigation and s 31 25 05 09 09 -07 n) 1600mmx1000mm with Ho torm water infrastructure isting Mechanism (45mmx2 00mm) Bowatenne Canel CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel BAD/DC/074 / Improments limate resilience and main 2023-07- 2023-05- 2023-08- 2023-06- 2023-09- 2023-10- 2023-12 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,533.33 0.00 Signed to LB,RB and UT gate,Diyab tenance of irrigation and s 31 31 05 06 09 10 -08 n) ana oya, Bandarawela torm water infrastructure CRESMPA-1/RP/WORKS/ID- POL/DC/003 / Fabricating a Component 5: Improving c Other (with fiel nd Installing 03 No of 1250 limate resilience and main 2023-07- 2023-02- 2023-08- 2023-02- 2023-09- 2023-10- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,700.00 0.00 Signed mmx1200mm anicut gates tenance of irrigation and s 31 09 05 16 09 05 -07 n) with hoisting mechanism of torm water infrastructure LLMC 0+000 Regulator gat es in Kaudulla Division CRESMPA-1/RP/WORKS/ID- ANU/DC/003 / Fabrication a Component 5: Improving c nd Installation of 09 Nos st Other (with fiel limate resilience and main 2023-07- 2023-06- 2023-08- 2023-06- 2023-09- 2023-09- 2024-03 ainless steel gates (1480*1 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 54,914.49 0.00 Signed tenance of irrigation and s 31 02 05 06 09 27 -07 520mm) Hoisting mechanis n) torm water infrastructure ms, guide grooves and han d rail of Mora Oya Anicut in Padaviya Division, Anuradh apura CRESMPA-1/RP/WORKS/ID- MATR/DC/005 / Fabrication, Painting & Installation of 11 Component 5: Improving c 700mmx1400mm Mild Stee Other (with fiel Under Im limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2024-01 l gates with gear box (01 N IBRD / 89960 Post Direct Selection Direct - National d for explanatio 17,354.39 0.00 plementa tenance of irrigation and s 31 29 05 09 09 -07 os) for OPI/19 anicut, 1655 n) tion torm water infrastructure mmx2240mm Mild steel Ga tes with gear box (01Nos) f or OPI/26 anicut, 1670mmx 1980mm steel gates with g er box (01 Nos) OPI/27 anic CRESMPA-1/RP/WORKS/ID- ut, 1170mmx Component 5: Improving c Other (with fiel POL/DC/014 / Improvement limate resilience and main 2023-07- 2023-05- 2023-08- 2023-06- 2023-09- 2023-10- 2024-06 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 43,820.00 0.00 Signed s to RB3 canal off D1 north tenance of irrigation and s 31 26 05 02 09 03 -05 n) canal in Laxauyana DCO ar torm water infrastructure ea CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Under Im HAM/DC/007 / Repair regul limate resilience and main 2023-07- 2023-07- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 9,017.11 0.00 plementa ar gates in GR08 and GR 0 tenance of irrigation and s 31 07 05 15 09 -07 n) tion 9 in LBMC Lunugamwehera torm water infrastructure Reservoir CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel MATL/DC/003 / Fabrication, limate resilience and main 2023-08- 2023-06- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,156.40 0.00 Signed Painting & Installation of 02 tenance of irrigation and s 15 26 20 09 24 -22 n) Nos of Gate Radagalpotha torm water infrastructure Anicut (1330mmx750mm) CRESMPA-1/RP/WORKS/ID- MATL/DC/004 / Fabrication Component 5: Improving c Other (with fiel & Installation of 14 Nos of limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,642.11 0.00 Signed Gates with Locking Mechan tenance of irrigation and s 31 29 05 09 09 -07 n) ism Athirahapitiya Cannel 7 torm water infrastructure Nos of Gates (600mmx300 mm) & 07 Nos of Gates (40 0mmx300mm) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I KAL/DC/020 / Improvement limate resilience and main 2023-07- 2023-08- 2023-09- 2024-02 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,000.00 0.00 mplemen s to flood controlling gate a tenance of irrigation and s 31 05 09 -06 n) tation t Kalugoda flood bund ( 1n torm water infrastructure os) gate number 3. CRESMPA-1/RP/WORKS/ID- MATL/DC/005 / Supply & In stallation of 50 Nos of 125 Component 5: Improving c mm cast iron FTO Gates wit Other (with fiel limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2024-01 h Hoisting Mechanism and IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,196.57 0.00 Signed tenance of irrigation and s 31 30 05 09 09 -07 Fabrication and Installation n) torm water infrastructure 02 Nos of Gates (950x1280 mm) with steel groves, colu mns,beams and Hoisting M echanism (45mmx2000mm at Dewahuwa Main Cannel CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel BAD/DC/073 / Improments limate resilience and main 2023-07- 2023-05- 2023-08- 2023-06- 2023-09- 2023-10- 2023-12 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,666.67 0.00 Signed to gates at Tract 6,D2 of N tenance of irrigation and s 31 31 05 06 09 10 -08 n) agadeepa scheme Bandara torm water infrastructure wela CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel POL/DC/054 / Construction limate resilience and main 2023-07- 2023-05- 2023-08- 2023-06- 2023-09- 2023-10- 2024-06 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 24,790.00 0.00 Signed of 36m long Retaining wall tenance of irrigation and s 31 26 05 02 09 02 -05 n) at 0+500 of RB 1 off D 2 ca torm water infrastructure nal in Weerapedesa DCO ar ea CRESMPA-1/RP/WORKS/ID- MON/DC/001 / Fabrication and Installation of 02 Nos o Component 5: Improving c Other (with fiel f 3.5ft *3.0ft Sluice gates,0 limate resilience and main 2023-07- 2023-04- 2023-08- 2023-05- 2023-09- 2023-10- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 23,746.50 0.00 Signed 1 Nos of 3.3ft*5.5ft Regulat tenance of irrigation and s 31 28 05 02 09 12 -07 n) or gates, 01Nos of 4.8ft*5.5 torm water infrastructure ft Regulator gates and 02 N os of 5.5ft*6.7ft Regulator gates in Wilaoya Anicut in Monaragala Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KAL/DC/001 / Improvement limate resilience and main 2023-07- 2023-06- 2023-08- 2023-07- 2023-09- 2023-10- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,766.67 0.00 Signed s to Panape ela anicut , Ka tenance of irrigation and s 31 30 05 05 09 09 -07 n) luthara Division, Colombo torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I KAL/DC/009 / Improvement limate resilience and main 2023-07- 2023-08- 2023-09- 2024-02 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,333.33 0.00 mplemen s to Aluth Ela( 0+000-5+70 tenance of irrigation and s 31 05 09 -06 n) tation 0) torm water infrastructure CRESMPA-1/RP/WORKS/ID- HAM/DC/004 / Fabrication, Component 5: Improving c Other (with fiel Under Im sandblasting,painting and i limate resilience and main 2023-07- 2023-07- 2023-08- 2023-07- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,192.51 0.00 plementa nstallation 02Nos of 1524m tenance of irrigation and s 31 07 05 15 09 -07 n) tion mx1820mm mild steel gate torm water infrastructure s LBMC Ridiyagama Reserv oir in Koggalu ara CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel AMP/DC/034 / Deepening a limate resilience and main 2023-07- 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,666.67 0.00 Canceled nd widening of Rambakano tenance of irrigation and s 31 05 09 -07 n) ya spill tail canal from 6+0 torm water infrastructure 00 to 8+000 CRESMPA-1/RP/WORKS/ID- Component 5: Improving c BAD/DC/077 / Fabricating s Other (with fiel limate resilience and main 2023-07- 2023-05- 2023-08- 2023-06- 2023-09- 2023-10- 2024-01 pill gates and reparing turn IBRD / 89960 Post Direct Selection Direct - National d for explanatio 7,000.00 0.00 Signed tenance of irrigation and s 31 31 05 06 09 10 -07 out gates in Baduluoya ani n) torm water infrastructure cut scheme,kandaketiya Di vision,Bandarawela CRESMPA-1/RP/WORKS/ID- Component 5: Improving c BAD/DC/076 / Fabricating s Other (with fiel limate resilience and main 2023-07- 2023-05- 2023-08- 2023-12- 2023-09- 2023-10- 2024-01 pill gates and reparing turn IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,666.67 0.00 Signed tenance of irrigation and s 31 31 05 06 09 10 -07 out gates in Bathmedilla an n) torm water infrastructure icut scheme,kandaketiya Di vision,Bandarawela CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KAD/DC/008 / Construction limate resilience and main 2023-07- 2023-06- 2023-08- 2023-06- 2023-09- 2023-10- 2024-03 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,533.33 0.00 Signed of 50m long canal lining at tenance of irrigation and s 31 14 05 21 09 30 -07 n) 0+000 in feeder canal in R torm water infrastructure athnaella National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I BAT/RFQ/008 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-04 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplemen nts to Navatkadu Branch C tenance of irrigation and s tations e Envelope 20 15 -12 process (Non B tation hannel in Unnichchai Sche torm water infrastructure ank-SPD) me,Rugam Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAT/NCB/016 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-08- 2023-10- 2023-10- 2023-10- 2023-09- 2023-12- 2023-10- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 98,000.00 0.00 Signed nts to Vaikaladichenai anic tenance of irrigation and s s e Envelope 15 21 20 01 02 31 27 05 27 -29 process (Non B ut in Unnichchai Scheme, R torm water infrastructure ank-SPD) ugam Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAT/NCB/009 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-08- 2023-10- 2023-08- 2023-10- 2023-09- 2023-12- 2023-10- 2024-08 IBRD / 89960 Post Open - National nt - 1 Envelope 53,666.67 0.00 Signed nts to Peelimadu Bridge cu tenance of irrigation and s s e Envelope 15 21 20 01 24 31 27 05 27 -31 process (Non B m regulator in Vahanery Sc torm water infrastructure ank-SPD) heme, Rugam Division CRESMPA-1/RP/WORKS/ID- National Procur TRI/RFQ/005 / Improvemen Component 5: Improving c ement Docume ts to Peenganudaichan Aru limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-10 IBRD / 89960 Post Limited nt - 1 Envelope 34,533.33 0.00 Canceled Drainange canal from seew tenance of irrigation and s tations e Envelope 20 15 -09 process (Non B bridge to Vanniunamadu G torm water infrastructure ank-SPD) ated Regulator from Stn 0+ 000 to Stn 1+120 in Kanth ale CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c BAT/NCB/014 / Improveme ement Docume limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-08- 2023-10- 2023-10- 2023-10- 2023-09- 2023-12- 2023-10- 2024-08 nts to LB Main Channel bun IBRD / 89960 Post Open - National nt - 1 Envelope 55,000.00 0.00 Signed tenance of irrigation and s s e Envelope 15 21 20 01 02 31 27 05 27 -31 d access road at Stn.0 + 33 process (Non B torm water infrastructure 6 in Wadamunai Scheme in ank-SPD) Rugam Division, Baticaloa National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAT/NCB/013 / Reconstruct limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-08- 2023-10- 2023-10- 2023-10- 2023-09- 2023-12- 2023-10- 2024-08 IBRD / 89960 Post Open - National nt - 1 Envelope 57,333.33 0.00 Signed ion of Road in LB - 44A Cha tenance of irrigation and s s e Envelope 15 21 20 01 02 31 27 05 23 -31 process (Non B nnel,Navakari Scheme,Nav torm water infrastructure ank-SPD) akari Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c BAT/DC/001 / Supplying an Other (with fiel limate resilience and main 2023-08- 2023-05- 2023-08- 2023-05- 2023-09- 2023-09- 2024-01 d installing steel gate with IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,333.33 0.00 Signed tenance of irrigation and s 15 03 20 11 24 22 -22 component to sembiyadi a n) torm water infrastructure nicut in Vahanery scheme Rugam Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel BAT/DC/002 / Replacing of limate resilience and main 2023-08- 2023-05- 2023-08- 2023-05- 2023-09- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,333.33 0.00 Signed 06 Nos of gates in Wattawa tenance of irrigation and s 15 03 20 11 24 22 -22 n) la anicut in Navakiri Divisio torm water infrastructure n CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel BAT/DC/003 / Replacing of limate resilience and main 2023-08- 2023-05- 2023-08- 2023-05- 2023-09- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 9,633.33 0.00 Signed 10 Nos of gates in Navakiri tenance of irrigation and s 15 03 20 11 24 22 -22 n) anicut in Navakiri Division torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KAD/DC/001 / Fabrication, limate resilience and main 2023-08- 2023-06- 2023-08- 2023-06- 2023-09- 2023-09- 2023-12 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,250.39 0.00 Signed painting & Installation tras tenance of irrigation and s 15 13 20 21 24 19 -23 n) hrack for Gurugaloya 1300 torm water infrastructure mm 2400mm CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KAD/DC/002 / Fabrication & limate resilience and main 2023-08- 2023-06- 2023-08- 2023-06- 2023-09- 2023-09- 2023-12 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,043.26 0.00 Signed Installation of 1 nos of 105 tenance of irrigation and s 15 13 20 21 24 19 -23 n) 0x750mm Gate at Gampol torm water infrastructure a wela anicut in Kandy CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KAD/DC/003 / Fabrication & limate resilience and main 2023-08- 2023-06- 2023-08- 2023-06- 2023-09- 2023-09- 2023-12 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,962.03 0.00 Signed Installation of 03 nos Hoisti tenance of irrigation and s 15 13 20 21 24 19 -23 n) ng Mechanisms for Ulapane torm water infrastructure Anicut National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/RFQ/006 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 27,766.67 0.00 plementa ts to D4 canal from Stn 0+ tenance of irrigation and s tations e Envelope 20 15 -10 process (Non B tion 000 to Stn 1+000 in Vendr torm water infrastructure ank-SPD) asan Scheme CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c TRI/RFQ/007 / Improvemen ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-10 ts to Kattaparichchan Drain IBRD / 89960 Post Limited nt - 1 Envelope 42,900.00 0.00 Canceled tenance of irrigation and s tations e Envelope 20 15 -09 ange Canal from stn 2+200 process (Non B torm water infrastructure to Stn 3+200 in Muthur Div ank-SPD) ision National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/NCB/012 / Construction limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-08- 2023-10- 2023-10- 2023-12- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 77,100.00 0.00 plementa of D2 Bund Road at DC2/BR tenance of irrigation and s s e Envelope 15 15 20 01 31 05 -29 process (Non B tion 3/RBMC from Stn 1+000 to torm water infrastructure ank-SPD) Stn 3+625 in Mutur Divisio n CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Under Im GAM/DC/002 / Improvemen limate resilience and main 2023-08- 2023-05- 2023-08- 2023-05- 2023-09- 2023-12 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,666.67 0.00 plementa t to flood protection structu tenance of irrigation and s 15 02 20 09 24 -23 n) tion re Jaela Heen Ela torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c GAM/DC/010 / Paving of gr Other (with fiel limate resilience and main 2023-08- 2023-05- 2023-08- 2023-05- 2023-09- 2024-01- 2024-01 anite and boulders for the IBRD / 89960 Post Direct Selection Direct - National d for explanatio 12,500.00 0.00 Signed tenance of irrigation and s 15 02 20 09 24 01 -22 damged sections of the rig n) torm water infrastructure ht bank canal of the Paluoy a Anicut in the Moranna sc heme CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel GAM/DC/012 / Installation o limate resilience and main 2023-08- 2023-05- 2023-08- 2023-05- 2023-09- 2024-01- 2023-12 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 500.00 0.00 Signed f wooden stop logs for Mor tenance of irrigation and s 15 02 20 09 24 01 -23 n) anna Anicut torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c GAM/DC/015 / Paving of gr Other (with fiel limate resilience and main 2023-08- 2023-05- 2023-08- 2023-05- 2023-09- 2024-01- 2024-02 anite from 490 m to 580 m IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,000.00 0.00 Signed tenance of irrigation and s 15 02 20 09 24 01 -21 in the eroded section of left n) torm water infrastructure ban of Attanagalooya in Ko tawala scheme CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I GAM/DC/016 / Paving of gr limate resilience and main 2023-08- 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,000.00 0.00 mplemen anite at 0+400 on left bank tenance of irrigation and s 15 20 24 -21 n) tation of Keenagaspillaiwa Anicut torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I GAM/DC/018 / Paving of gr limate resilience and main 2023-08- 2023-08- 2023-09- 2024-02 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,000.00 0.00 mplemen anite for 75 m length at 60 tenance of irrigation and s 15 20 24 -21 n) tation 0 m in the downstream sec torm water infrastructure tion of the Doranagoda Ani cut National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KUR/RFQ/014 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 19,499.33 0.00 mplemen nts of D19 canal in Dolukan tenance of irrigation and s tations e Envelope 20 15 -11 process (Non B tation da canal in Bathalagoda Sc torm water infrastructure ank-SPD) heme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KUR/RFQ/017 / Contsructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 31,506.67 0.00 mplemen n of Under crossing structu tenance of irrigation and s tations e Envelope 20 15 -10 process (Non B tation re at 16+246 Km in LBMC i torm water infrastructure ank-SPD) n Deduruoya scheme. CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KUR/DC/021 / construction limate resilience and main 2023-08- 2023-06- 2023-08- 2023-06- 2023-09- 2023-12- 2024-03 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 19,723.33 0.00 Signed of Kiniyama Sluice & impro tenance of irrigation and s 15 02 20 09 24 07 -22 n) vements of main canal in Ki torm water infrastructure niyama scheme. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume PUT/NCB/013 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-10- 2023-10- 2023-12- 2024-08 IBRD / 89960 Post Open - National nt - 1 Envelope 53,333.33 0.00 Canceled nt to kuda wewa Kadupitiy tenance of irrigation and s s e Envelope 15 20 01 31 05 -31 process (Non B a oya canal spill torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume PUT/NCB/014 / Supply, fabr limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-10- 2023-10- 2023-12- 2024-08 IBRD / 89960 Post Open - National nt - 1 Envelope 46,666.67 0.00 Canceled icating, fixing, liftining gate tenance of irrigation and s s e Envelope 15 20 01 31 05 -31 process (Non B to the Thinipitiya anicut torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume PUT/NCB/015 / Constructio limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-10- 2023-10- 2023-12- 2024-08 IBRD / 89960 Post Open - National nt - 1 Envelope 40,000.00 0.00 Canceled n of gabion wall bank prote tenance of irrigation and s s e Envelope 15 20 01 31 05 -31 process (Non B ction to Buttaulu oya torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c BAT/DC/006 / Suppling and Other (with fiel limate resilience and main 2023-08- 2023-05- 2023-08- 2023-05- 2023-10- 2023-10- 2024-02 installing steel gate with co IBRD / 89960 Post Direct Selection Direct - National d for explanatio 30,300.00 0.00 Signed tenance of irrigation and s 25 03 30 11 04 10 -01 mponent to Kochcharasena n) torm water infrastructure i anicut in Unnichchai sche me Rugam Division CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c TRI/NCB/007 / Improvemen ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-08- 2023-10- 2023-09- 2023-11- 2023-12- 2024-12 ts to Kattaparichchan Drain IBRD / 89960 Post Open - National nt - 1 Envelope 42,900.00 0.00 plementa tenance of irrigation and s s e Envelope 25 15 30 11 14 10 15 -09 ange Canal from stn 2+200 process (Non B tion torm water infrastructure to Stn 3+200 in Muthur Div ank-SPD) ision CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c TRI/NCB/005 / Improvemen ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-08- 2023-10- 2023-09- 2023-11- 2023-09- 2023-12- 2024-09 ts to Peenganudaichan Aru IBRD / 89960 Post Open - National nt - 1 Envelope 34,533.33 0.00 plementa tenance of irrigation and s s e Envelope 25 15 30 11 14 10 20 15 -10 Drainange canal from Stn process (Non B tion torm water infrastructure 0+000 to Stn 1+120 in Kan ank-SPD) tale Division. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume TRI/NCB/021 / Rehabilitatio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-10 IBRD / 89960 Post Open - National nt - 1 Envelope 33,600.00 0.00 Canceled n of FC24/D4/MC from stn 0 tenance of irrigation and s tations e Envelope 20 15 -09 process (Non B +000 to stn 0+225 in Maha torm water infrastructure ank-SPD) divulwewa scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume TRI/NCB/017 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-10 IBRD / 89960 Post Open - National nt - 1 Envelope 53,333.33 0.00 Canceled ts to MKYE canal bund road tenance of irrigation and s tations e Envelope 20 15 -09 process (Non B from stn 5+000 to Stn 10+ torm water infrastructure ank-SPD) 000 in Kantale National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAT/NCB/021 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-09- 2023-10- 2023-09- 2023-11- 2023-09- 2023-12- 2024-09 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 Signed nt to Pilayarady Anicut/Reg tenance of irrigation and s s e Envelope 31 21 05 17 19 16 27 21 -16 process (Non B ulator in Kalvankai River,Ru torm water infrastructure ank-SPD) gam Scheme,Rugam Divisi on National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAT/RFQ/018 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled nts to Access road to Kanni tenance of irrigation and s tations e Envelope 30 25 -21 process (Non B yammai Anicut Navakari Sc torm water infrastructure ank-SPD) heme,Navakari Division CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c HAM/RFQ/031 / New constr ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 uction of Retaining wall at IBRD / 89960 Post Limited nt - 1 Envelope 18,016.67 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -28 0+015 - 0+047,0+400 - 0 process (Non B torm water infrastructure +446,0+570 - 0+675 in RB ank-SPD) MC of Mandagala Tank Page 3 CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c HAM/RFQ/034 / Improveme ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 nts of D/S basin of regulato IBRD / 89960 Post Limited nt - 1 Envelope 31,956.67 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -26 rs at 0+872 & 2+399 of An process (Non B torm water infrastructure dupelena L/B Main canal in ank-SPD) Urubokka - oya Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/037 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 23,666.67 0.00 Canceled on of FC 09,DC 01 in Tract tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B 07 Lunugamwehera RB torm water infrastructure ank-SPD) Component 5: Improving c CRESMPA-1/RP/WORKS/ID- Other (with fiel limate resilience and main 2023-07- 2023-08- 2023-09- 2024-09 HAM/DC/040 / Improvemen IBRD / 89960 Post Direct Selection Direct - National d for explanatio 50,000.00 0.00 Canceled tenance of irrigation and s 31 09 13 -12 ts to Pahe gate in HLMC n) torm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/043 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 Canceled nts to DC13 of Weerawila T tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B ank torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/045 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 33,666.67 0.00 Canceled nts to trough at 0+900 (80 tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B m) in LBMC, Muruthawela torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/046 / Installing fa limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 17,256.67 0.00 Canceled rm turn out & canal lining o tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B f 4th canal from 1+050 to torm water infrastructure ank-SPD) 1+350 in SCB LB canal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/048 / Canal lining limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 33,112.33 0.00 Canceled from 0+600 to 1+800 in DI tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B canal in Pahala andarawew torm water infrastructure ank-SPD) a National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/054 / Earth filling limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 17,203.33 0.00 Canceled in LBMC from 0+400 to 1+ tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B 100 in LB 8 canal torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c HAM/RFQ/055 / Improveme ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 nts to existing retaining wa IBRD / 89960 Post Limited nt - 1 Envelope 22,786.67 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -27 ll (RB) at 0+500 (180m) of process (Non B torm water infrastructure Feeder canal from Pothu w ank-SPD) ewa in Urubokka - oya sche me National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/056 / Installing fa limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 17,950.00 0.00 Canceled rm turn out & canal lining i tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B n SCB RB 01 canal from 0+ torm water infrastructure ank-SPD) 500 - 0+827 National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/059 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled nts of tank bund in pothu w tenance of irrigation and s tations e Envelope 05 30 -25 process (Non B ewa in Urubokka - oya sche torm water infrastructure ank-SPD) me National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/082 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled nts to Hakmana yaya anicu tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B t torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume AMP/DC/019 / Improvement limate resilience and main 2023-08- 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Direct Selection Direct - National nt - 1 Envelope 44,988.00 0.00 Canceled s to WG-4 D' canal includin tenance of irrigation and s 04 09 13 -12 process (Non B g necessary structure in illu torm water infrastructure ank-SPD) kkuchenai unit CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel GAL/DC/008 / Improvement limate resilience and main 2023-08- 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 45,880.00 0.00 Canceled s to main canals Idigasketi tenance of irrigation and s 04 09 13 -12 n) ya scheme torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c AMP/DC/041 / Improvement Other (with fiel limate resilience and main 2023-07- 2023-08- 2023-09- 2024-09 s to breached section of An IBRD / 89960 Post Direct Selection Direct - National d for explanatio 44,953.33 0.00 Canceled tenance of irrigation and s 31 05 09 -03 daloya river in Poochchuku n) torm water infrastructure di at stn 2+520 in Weerago da unit CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c AMP/RFQ/039 / Improveme ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 nts to downstream of M 18 IBRD / 89960 Post Limited nt - 1 Envelope 37,550.00 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -26 Regulater structure at stn 8 process (Non B torm water infrastructure +800 in Mandoor Branch c ank-SPD) anal - Annamalai unit National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im AMP/NCB/007 / Reconstruct limate resilience and main Request for Bid Single Stage - On 100,000.0 2023-07- 2023-09- 2023-08- 2023-09- 2023-10- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 plementa ion of RB End Spillway at W tenance of irrigation and s s e Envelope 0 31 28 05 16 23 16 20 -19 process (Non B tion alagama Tank in Uhana Uni torm water infrastructure ank-SPD) t CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel GAM/DC/021 / Embankmen limate resilience and main 2023-08- 2023-08- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,666.67 0.00 Canceled t to protect Pallewela left b tenance of irrigation and s 15 20 24 -22 n) ank main canal to prevent f torm water infrastructure rom erosion CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel GAM/DC/022 / Upgrading th limate resilience and main 2023-08- 2023-08- 2023-09- 2024-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,333.33 0.00 Canceled e existing left flood bund in tenance of irrigation and s 15 20 24 -22 n) Nahitiya anicut torm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume GAM/RFQ/023 / Concrete li limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 Canceled ning of a 150 m long of the tenance of irrigation and s tations e Envelope 20 15 -10 process (Non B left bank main canal of Ta torm water infrastructure ank-SPD) mmita scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im AMP/NCB/012 / Improveme limate resilience and main Request for Bid Single Stage - On 100,000.0 2023-07- 2023-11- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 plementa nts Meegahapallama Anicu tenance of irrigation and s s e Envelope 0 31 08 05 16 16 20 -14 process (Non B tion t in Damana unit torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/011 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 34,666.67 0.00 Canceled on of FC 114 in branch can tenance of irrigation and s tations e Envelope 07 02 -26 process (Non B al 9, in track III of the Muru torm water infrastructure ank-SPD) thawela scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/015 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 49,996.67 0.00 Canceled nts to FC34 , DC2 track 06, tenance of irrigation and s tations e Envelope 07 02 -26 process (Non B RBMC , Lunugamwehera sc torm water infrastructure ank-SPD) heme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/028 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 35,305.00 0.00 Canceled n of canal lining of CPO 35 f tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B rom 0+000 to 0+300 in W torm water infrastructure ank-SPD) RB scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/027 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 18,546.67 0.00 Canceled nts to DC 8B,Weerawila Sc tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B heme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/006 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 27,830.00 0.00 Canceled on of FC11,Track 01,LBMC, tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B Lunugamwehera torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/NCB/007 / New Constr limate resilience and main Request for Bid Single Stage - On 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 50,078.67 0.00 Canceled uction of canal lining at in P tenance of irrigation and s s e Envelope 31 05 16 16 20 -14 process (Non B 25 Ridiyagama main canal torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAD/RFQ/017 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 Canceled n of 15 m long R/wall at 0+ tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B 078 and 15m long at 1+98 torm water infrastructure ank-SPD) 0 in R/B side of main canal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAD/RFQ/020 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 23,000.00 0.00 Canceled nts to FC 23 in Demodara S tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B cheme torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 BAD/RFQ/021 / Rehabilitati IBRD / 89960 Post Limited nt - 1 Envelope 19,083.33 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -26 on of Mahamaditta tank process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAD/RFQ/006 / Cons. Of ca limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 Canceled nal lining from 0+300 to 0 tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B +400 in Main Canal torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MON/NCB/051 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 100,000.0 2023-07- 2023-08- 2023-09- 2023-10- 2023-11- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 Canceled on of 500m of LBMC in Weh tenance of irrigation and s s e Envelope 0 31 05 16 16 20 -14 process (Non B erakema tank torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MON/RFQ/67 / construction limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled of LB canal system in Anka tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B da tank torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MON/RFQ/68 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 43,333.33 0.00 Canceled ts to Badalkumbura Madug tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B asmulla Anicut torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-06 KAD/RFQ/010 / Improveme IBRD / 89960 Post Limited nt - 1 Envelope 20,066.67 0.00 Canceled tenance of irrigation and s tations e Envelope 20 15 -11 nts to D38 canal in stage i process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KAL/RFQ/016 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 Canceled ts to gate of Halthota anica tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B t at panape ela torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KAL/RFQ/049 / Clearing & d limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled esilting of Hikgahadeniya El tenance of irrigation and s tations e Envelope 05 30 -25 process (Non B a Bund torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KUR/RFQ/036 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 21,956.33 0.00 Canceled n of box culvert at 0+240 tenance of irrigation and s tations e Envelope 20 15 -11 process (Non B & gravelling along the main torm water infrastructure ank-SPD) canal bund road National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume ANU/RFQ/014 / Repairs of D limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 27,333.33 0.00 Canceled iulwewa Canal Spill in Nach tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B chaduwa Division torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MON/RFQ/054 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 Canceled on of FC 06 RBMC in RB of tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B Kandiyapita tank torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume GAL/RFQ/097 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 Canceled on of Niyagama Andadola c tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B anal torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MATR/CP/066 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled on yahagedramulla Anicut, tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B Polwattagedar Anicut and p torm water infrastructure ank-SPD) aragahalaga Dam National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MATR/CP/065 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 21,266.67 0.00 Canceled n of Anicut at Retaining wal tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B l Galetamba torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MATR/CP/062 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 20,666.67 0.00 Canceled n of side wall with spill at tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B Weressa Anicut torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MATR/CP/051 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 17,400.00 0.00 Canceled nts of Sadagankanda Anicu tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B t torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/NCB/017-1 / Improvem limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-09- 2023-10- 2023-11- 2023-12- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 53,333.33 0.00 plementa ents to MKYE canal bund ro tenance of irrigation and s s e Envelope 31 15 05 17 16 21 -15 process (Non B tion ad from stn 5+000 to Stn 1 torm water infrastructure ank-SPD) 5+000 in Kantale National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume TRI/RFQ/030 / Construction limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2023-11 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 Canceled of retaining walls at stn 14 tenance of irrigation and s tations e Envelope 07 02 -01 process (Non B +409 to stn 14+494 in RB torm water infrastructure ank-SPD) MC, Muthur Division stage I National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im GAL/NCB/008-1 / Improvem limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-10- 2023-09- 2023-10- 2023-10- 2023-11- 2023-11- 2023-12- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 45,880.00 0.00 plementa ents to main canals Idigask tenance of irrigation and s s e Envelope 31 03 05 17 27 16 13 21 -15 process (Non B tion etiya scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/NCB/021-1 / Rehabilitat limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-09- 2023-10- 2023-11- 2023-12- 2024-09 IBRD / 89960 Post Open - National nt - 1 Envelope 33,600.00 0.00 plementa ion of FC24/D4/MC from stn tenance of irrigation and s s e Envelope 31 15 05 17 16 21 -16 process (Non B tion 0+000 to stn 0+225 in Mah torm water infrastructure ank-SPD) adivulwewa scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAT/NCB/018 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-08- 2023-08- 2023-09- 2023-10- 2023-09- 2023-11- 2023-09- 2023-12- 2024-09 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 Signed nts to Access road to Kanni tenance of irrigation and s s e Envelope 31 21 05 17 18 16 27 21 -16 process (Non B yammai Anicut Navakari Sc torm water infrastructure ank-SPD) heme,Navakari Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume GAM/RFQ/034 / Concrete li limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 34,666.67 0.00 Canceled ning from 1+500 to 1+760 tenance of irrigation and s tations e Envelope 30 25 -20 process (Non B in left bank main canal of P torm water infrastructure ank-SPD) anugala scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im AMP/NCB/019 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-10- 2023-09- 2023-10- 2023-10- 2023-11- 2023-12- 2024-01- 2025-01 IBRD / 89960 Post Open - National nt - 1 Envelope 44,988.00 0.00 plementa nts to WG-4 D' canal includi tenance of irrigation and s s e Envelope 01 28 06 13 17 17 21 -15 process (Non B tion ng necessarry structure in i torm water infrastructure ank-SPD) llukkuchenai unit CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c AMP/RFQ/019-1 / Improvem ement Docume limate resilience and main Request for Quo Single Stage - On 2023-09- 2023-10- 2024-10 ents to WG-4 D' canal inclu IBRD / 89960 Post Limited nt - 1 Envelope 44,988.00 0.00 Canceled tenance of irrigation and s tations e Envelope 05 31 -25 ding necessarry structure i process (Non B torm water infrastructure n illukkuchenai unit (CResM ank-SPD) PA-1/RP/WORKS/ID-AMP/RF Q/019) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c AMP/DC/001 / Repairs, san Other (with fiel limate resilience and main 2023-11- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 d blasting & painting 2 Nos IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,666.67 0.00 Signed tenance of irrigation and s 30 01 05 06 09 22 -08 of LB main cannel radial ga n) torm water infrastructure tes at Senanayaka Samudr aya trifurcation in Ampara Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c AMP/DC/003 / Fabrication, s Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 and blasting & painting & I IBRD / 89960 Post Direct Selection Direct - National d for explanatio 33,133.33 0.00 Signed tenance of irrigation and s 15 31 20 06 24 22 -23 nstallation of Rottai pickup n) torm water infrastructure anicut & repair other gates in Potuvil Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c AMP/DC/004 / Fabrication, s Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 and blasting , painting & In IBRD / 89960 Post Direct Selection Direct - National d for explanatio 29,200.00 0.00 Signed tenance of irrigation and s 15 15 20 06 24 22 -23 stallation of Lower Paddm n) torm water infrastructure pitiya anicut gates in Sam manthura Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ANU/DC/001 / Fabrication a Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 nd installation of 16Nos of IBRD / 89960 Post Direct Selection Direct - National d for explanatio 32,953.47 0.00 Signed tenance of irrigation and s 15 30 20 06 24 26 -23 Regulator gates of high lev n) torm water infrastructure el main canel in Nachchadu wa Division, Anuradhapura CRESMPA-1/RP/WORKS/ID- AMP/DC/005 / Fabrication, s Component 5: Improving c Other (with fiel and blasting & painting & I limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 49,800.00 0.00 Signed nstallation 12 Nos of regula tenance of irrigation and s 15 26 20 06 24 22 -23 n) tor gates for Panayadi, Se torm water infrastructure mbukulam and Mudalaikkal in Akkarapattu Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel AMP/DC/002 / Fabrication, s limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-07 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,166.67 0.00 Signed and blasting & painting 4 N tenance of irrigation and s 15 01 20 06 24 22 -22 n) os of gates for reulator RB torm water infrastructure MC in Akkarapattu Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c AMP/DC/006 / Fabrication, s Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 and blasting , painting & In IBRD / 89960 Post Direct Selection Direct - National d for explanatio 49,500.00 0.00 Signed tenance of irrigation and s 15 31 20 06 24 22 -23 stallation of gates for Udan n) torm water infrastructure gavelly anicut in Moravil 2 unit in Sammanthura Divisi on CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ANU/DC/002 / Fabrication a Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 nd installation of 08Nos of IBRD / 89960 Post Direct Selection Direct - National d for explanatio 17,645.02 0.00 Signed tenance of irrigation and s 15 30 20 06 24 27 -23 Regulator gates of Low lev n) torm water infrastructure el main canal in Nachchadu wa Division, Anuradhapura CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Under Im GAM/DC/019 / Rehabilitatio limate resilience and main 2023-12- 2023-05- 2023-12- 2023-05- 2024-01- 2024-02 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,000.00 0.00 plementa n of the right bank access r tenance of irrigation and s 15 02 20 09 24 -05 n) tion oad to Tammita scheme torm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/RFQ/014 / Supply, fabri limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 mplemen cating, fixing, liftining gate tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation to the Thinipitiya anicut torm water infrastructure ank-SPD) National Procur SLMOI/CRES/ID/W/S/30 / D Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 evelopment and Improvem IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 5,500.00 0.00 mplemen tations e Envelope 20 14 -12 ents at the Ampara Field Of Impact Weather, Floods an process (Non B tation fice d Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/21 / D Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 evelopment and Improvem IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 11,570.00 0.00 plementa tations e Envelope 20 14 -12 ents at the Nakkala Field O Impact Weather, Floods an process (Non B tion ffice d Landslides ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/RFQ/015 / Construction limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 40,000.00 0.00 mplemen of gabion wall bank protect tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation ion to Buttaulu oya torm water infrastructure ank-SPD) Page 4 National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im PUT/RFQ/018 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 plementa ts to FC - 2 in LB MC in Kud tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B tion aottupallama in Neelabem torm water infrastructure ank-SPD) ma Scheme CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KAL/DC/005 / Improvement limate resilience and main 2023-12- 2023-06- 2023-12- 2023-07- 2024-01- 2023-09- 2024-06 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 14,000.00 0.00 Signed s to Liyanagoda ela (0+90 tenance of irrigation and s 15 28 20 05 24 25 -22 n) 0 - 3+500) torm water infrastructure SLMOI/CRES/ID/W/S/12 / C Component 1: Forecasting Request for Qu Pending I Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of Electric Fenc IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 2,346.67 0.00 mplemen tations e Envelope 20 14 -12 e at Galgamuwa Field Offic Impact Weather, Floods an ank-SPD) tation e d Landslides SLMOI/CRES/ID/W/S/13 / D Component 1: Forecasting Request for Qu Pending I Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 evelopment and Improvem IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 4,403.33 0.00 mplemen tations e Envelope 20 14 -12 ents at Horowpathana Field Impact Weather, Floods an ank-SPD) tation Office d Landslides SLMOI/CRES/ID/W/S/18 / C Component 1: Forecasting Request for Qu Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of PVC Coated IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 6,573.33 0.00 plementa tations e Envelope 20 14 -12 Wire Mesh Fence at Putupa Impact Weather, Floods an ank-SPD) tion ula Field Office d Landslides CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KAL/DC/004 / Improvement limate resilience and main 2023-12- 2023-06- 2023-12- 2023-07- 2024-01- 2023-09- 2024-06 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,666.67 0.00 Signed s to Liyanagoda ela (0+00 tenance of irrigation and s 15 28 20 05 24 25 -22 n) 0 - 0+900) torm water infrastructure SLMOI/CRES/ID/W/S/10 / C Component 1: Forecasting Request for Qu Pending I Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of Field Office a IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 43,276.67 0.00 mplemen tations e Envelope 20 14 -12 t Kalawellawa Gauging Stat Impact Weather, Floods an ank-SPD) tation ion in Kuda Ganga d Landslides CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c HAM/RFQ/035 / New constr ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-07 uction of Retaining wall at IBRD / 89960 Post Limited nt - 1 Envelope 18,016.67 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -13 0+015 - 0+047,0+400 - 0 process (Non B torm water infrastructure +446,0+570 - 0+675 in RB ank-SPD) MC of Mandagala Tank SLMOI/CRES/ID/W/S/09 / C Component 1: Forecasting Request for Qu Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of Field Office a IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 21,786.67 0.00 plementa tations e Envelope 20 14 -12 t Magura Gauging Station Impact Weather, Floods an ank-SPD) tion d Landslides SLMOI/CRES/ID/W/S/11 / C Component 1: Forecasting Request for Qu Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of Field Office a IBRD / 89960 and Early Warning of High Post Open - National otations (Non B 17,673.33 0.00 plementa tations e Envelope 20 14 -12 t Peradeniya Gauging Stati Impact Weather, Floods an ank-SPD) tion on d Landslides Component 5: Improving c CRESMPA-1/RP/WORKS/ID- Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-10- 2024-06 BAD/DC/004 / Improvement IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,000.00 0.00 Signed tenance of irrigation and s 15 31 20 06 24 20 -22 s to FC 1/RBMC n) torm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MATR/RFQ/015 / Improvem limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplemen ents to sub canals of B can tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation al in Akuressa Scheme lift i torm water infrastructure ank-SPD) rrigation system CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KUR/DC/028 / Improvement limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-11- 2024-06 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,246.67 0.00 Signed s to Kahaliya Anicut and b tenance of irrigation and s 15 02 20 09 24 22 -22 n) und road in Hulugalla sche torm water infrastructure me National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im BAT/NCB/020 / Constructio limate resilience and main Request for Bid Single Stage - On 2023-12- 2024-03- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 56,666.67 0.00 plementa n in Concrete canel lining i tenance of irrigation and s s e Envelope 15 12 20 31 01 05 -31 process (Non B tion n Irassakal tank torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- VAV/DC/001 / Fabrication & Component 5: Improving c Installation of 04 Nos.of Lift Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-08 ing Mechanism, Lifting Rod, IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,534.29 0.00 Signed tenance of irrigation and s 15 31 20 09 24 26 -21 Passerel, Pedestal Base for n) torm water infrastructure Regulator Gates & Hand- R ail of Kal - Aru Anicut Gates in Vavuniya Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im BAD/NCB/012 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2024-09 IBRD / 89960 Post Open - National nt - 1 Envelope 51,333.33 0.00 plementa nts to FC 24 in Dehigama S tenance of irrigation and s s e Envelope 15 11 20 31 01 05 -02 process (Non B tion cheme torm water infrastructure ank-SPD) National Procur SLMOI/CRES/ID/W/S/14 / D Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 evelopment and Improvem IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 10,470.00 0.00 mplemen tations e Envelope 20 14 -12 ents at Thaldena Field Offic Impact Weather, Floods an process (Non B tation e d Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/15 / C Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of PVC Coated IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 4,053.33 0.00 plementa tations e Envelope 20 14 -12 Wire Mesh Fence at Rathna Impact Weather, Floods an process (Non B tion pura Field Office d Landslides ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im BAT/NCB/022 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-12- 2024-03- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 70,000.00 0.00 plementa nts to Tank Bund at Kanga tenance of irrigation and s s e Envelope 15 12 20 31 01 05 -31 process (Non B tion niyar Tank torm water infrastructure ank-SPD) National Procur SLMOI/CRES/ID/W/S/17 / D Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 evelopment and Improvem IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 8,936.67 0.00 plementa tations e Envelope 20 14 -12 ents at Kuda Oya Field Offi Impact Weather, Floods an process (Non B tion ce d Landslides ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I HAM/DC/015 / Improvemen limate resilience and main 2023-12- 2023-12- 2024-01- 2025-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 46,886.67 0.00 mplemen ts to FC34,DC2,Track 06,RB tenance of irrigation and s 15 20 24 -18 n) tation MC Lunugamwehera torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Under Im HAM/DC/011 / Rehabilitatio limate resilience and main 2023-12- 2023-07- 2023-12- 2023-07- 2024-01- 2025-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 32,150.00 0.00 plementa n of FC114 in tract iii D9,M tenance of irrigation and s 15 07 20 15 24 -18 n) tion uruthawela Scheme torm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im BAD/NCB/003 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 87,333.33 0.00 plementa nts to Medala trough at 1+ tenance of irrigation and s s e Envelope 15 11 20 31 01 05 -31 process (Non B tion 615 torm water infrastructure ank-SPD) National Procur SLMOI/CRES/ID/W/S/16 / C Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of a Gate at Du IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 1,160.00 0.00 plementa tations e Envelope 20 14 -12 namale Field Office Impact Weather, Floods an process (Non B tion d Landslides ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel BAD/DC/001 / Improvement limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-10- 2024-07 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 14,666.67 0.00 Signed s to RB canal at 6+220 in tenance of irrigation and s 15 31 20 06 24 20 -22 n) Medaela torm water infrastructure National Procur SLMOI/CRES/ID/W/S/20 / D Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 evelopment and Improvem IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 15,163.33 0.00 plementa tations e Envelope 20 14 -12 ents at Wellawaya Field Off Impact Weather, Floods an process (Non B tion ice d Landslides ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im BAD/NCB/007 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 51,333.33 0.00 plementa nts to 1+034 canal spill in tenance of irrigation and s s e Envelope 15 11 20 31 01 05 -31 process (Non B tion LBMC in Sorabora Scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/RFQ/024 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplemen ts to D3 canal from 0+700 tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B tation km in Radavi Bendi Ela Sch torm water infrastructure ank-SPD) eme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I HAM/RFQ/030 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 45,433.33 0.00 mplemen nts to FC - 4 Gemunupura tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation main canal of Gemunupura torm water infrastructure ank-SPD) Scheme in Tissa Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MAN/RFQ/067 / Widening t limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 IBRD / 89960 Post Limited nt - 1 Envelope 35,000.00 0.00 mplemen he feeder canal under Koor tenance of irrigation and s tations e Envelope 20 14 -08 process (Non B tation ai Irrigation Scheme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MON/RFQ/017 / Constructio ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 n of 83m long Retaining wa IBRD / 89960 Post Limited nt - 1 Envelope 24,400.00 0.00 mplemen tenance of irrigation and s tations e Envelope 20 14 -10 ll at LB side from 0+615 to process (Non B tation torm water infrastructure 0+693 in RBMC Hambega ank-SPD) muwa tank National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KILI/NCB/005 / Reconstructi limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 mplemen on of Saravanas Bridge at L tenance of irrigation and s s e Envelope 15 20 31 01 05 -31 process (Non B tation B Main Canal of Iranamadu torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- TRI/DC/004 / Fabrication & I Component 5: Improving c Other (with fiel nstallation of 03 Nos of mil limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 14,039.92 0.00 Signed d steel gates with Screw ty tenance of irrigation and s 15 08 20 22 24 16 -23 n) pe hoisting mechanisms for torm water infrastructure Wendrasan Raja Amuna Re gulator in Kantale Division, Trincomalee CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c TRI/RFQ/024 / Improvemen ement Docume Under Im limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 ts to Kattaparichchan Drain IBRD / 89960 Post Limited nt - 1 Envelope 49,666.67 0.00 plementa tenance of irrigation and s tations e Envelope 20 14 -10 ange canal from stn 1+050 process (Non B tion torm water infrastructure to stn 2+200 in Muthur Divi ank-SPD) sion National Procur CRESMPA-1/RP/WORKS/ID-J Component 5: Improving c ement Docume Pending I AF/NCB/007 / Rehabilitation limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 mplemen of Vallai to Vatharavaththai tenance of irrigation and s s e Envelope 15 20 31 01 05 -31 process (Non B tation Fllod protection bund torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c MAN/DC/008 / Fabrication Other (with fiel limate resilience and main 2023-12- 2023-02- 2023-12- 2023-02- 2024-01- 2023-09- 2024-05 & Installation of 01 No.of S IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,287.66 0.00 Signed tenance of irrigation and s 15 13 20 16 24 26 -23 S Gate of Nalavankulam Fe n) torm water infrastructure eder Canal in Giants Tank S cheme in Murunkan Divisio n CRESMPA-1/RP/WORKS/ID- TRI/DC/001 / Improvements Component 5: Improving c Other (with fiel to gates & hoisting system limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 22,113.59 0.00 Signed and fabrication and Installa tenance of irrigation and s 15 08 20 22 24 05 -23 n) tion of Trash racks and han torm water infrastructure drail for Batahathara Regu altor in Kantale Division, Tri ncomalee CRESMPA-1/RP/WORKS/ID- Component 5: Improving c MAN/DC/007 / Fabrication Other (with fiel limate resilience and main 2023-12- 2023-02- 2023-12- 2023-02- 2024-01- 2023-09- 2024-05 & Installation of 02Nos of S IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,498.14 0.00 Signed tenance of irrigation and s 15 13 20 16 24 26 -23 S Gates of Sundukkuli Main n) torm water infrastructure Regulator in Giants Tank Sc heme in Murunkan Division CRESMPA-1/RP/WORKS/ID- GAL/DC/003 / Fabrication,P Component 5: Improving c Other (with fiel ainting & Installation of 134 limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,094.18 0.00 Signed 0mmx2075mm Stainless St tenance of irrigation and s 15 31 20 20 24 01 -23 n) eel gates with Gear Box (0 torm water infrastructure 2Nos) for Midigamu ela ani cut at Ambalangoda Divisio n, Galle National Procur SLMOI/CRES/ID/W/NCB/27 / Component 1: Forecasting ement Docume Pending I Request for Bid Single Stage - On 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2024-10 Construction of Field Office IBRD / 89960 and Early Warning of High Post Open - National nt - 1 Envelope 57,383.33 0.00 mplemen s e Envelope 15 20 31 01 05 -02 at Holombuwa Gauging Sta Impact Weather, Floods an process (Non B tation tion d Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/28 / C Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of Field Office a IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 29,413.33 0.00 plementa tations e Envelope 20 14 -12 t Norwood Gauging Station Impact Weather, Floods an process (Non B tion d Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/29 / C Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of Field Office a IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 27,000.00 0.00 plementa tations e Envelope 20 14 -12 t Glencourse Gauging Stati Impact Weather, Floods an process (Non B tion on d Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/19 / C Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of a Gate with F IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 3,576.67 0.00 plementa tations e Envelope 20 14 -12 ence at the Katharagama F Impact Weather, Floods an process (Non B tion ield Office d Landslides ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/RFQ/017 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 mplemen ts to D - 2 canal in Maha An tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation darawawewa Scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KUR/RFQ/024 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 IBRD / 89960 Post Limited nt - 1 Envelope 38,036.67 0.00 mplemen n of box culvert at 0+240 a tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B tation nd graveling of main canal torm water infrastructure ank-SPD) bund road in Madulla sche me National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MATR/RFQ/012 / Improvem limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 21,366.67 0.00 mplemen ents of canal system in Wal tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B tation gama north area in Kiralak torm water infrastructure ank-SPD) ale scheme CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MON/RFQ/016 / Demolishin ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-09 g and Reconstruction of 38 IBRD / 89960 Post Limited nt - 1 Envelope 17,843.33 0.00 mplemen tenance of irrigation and s tations e Envelope 20 14 -11 m long trough structure at process (Non B tation torm water infrastructure 1 + 750 in Maganda Oya a ank-SPD) nicut National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MON/RFQ/028 / Demolishin limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 28,973.33 0.00 mplemen g damaged trough & Canal tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation lining at 2+250 in main can torm water infrastructure ank-SPD) al in Hulandawa LB canal National Procur SLMOI/CRES/ID/W/S/26 / D Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 evelopment and Improvem IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 8,480.00 0.00 plementa tations e Envelope 20 14 -12 ents at the Baddegama Fiel Impact Weather, Floods an process (Non B tion d Office d Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/25 / C Component 1: Forecasting ement Docume Pending I Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of Field Office a IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 26,130.00 0.00 mplemen tations e Envelope 20 14 -12 t Moraketiya Gauging Stati Impact Weather, Floods an process (Non B tation on d Landslides ank-SPD) Request for Bid SLMOI/CRES/ID/W/ICB/02 / Component 2: Flood Risk Pending I Request for Bid Open - Internatio Single Stage - On s - Small Works 16,750,00 2023-12- 2023-12- 2024-02- 2024-05- 2024-08- 2026-07 Construction of Ambatale S IBRD / 89960 Mitigation Investments in t Prior 0.00 mplemen s nal e Envelope SPD (1 envelop 0.00 15 29 27 27 01 -22 alinity Barrier he lower Kelani basin tation e process) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c TRI/RFQ/039 / Reconstructi ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-09 on of Pattiyanoor tank LB C IBRD / 89960 Post Limited nt - 1 Envelope 21,333.33 0.00 mplemen tenance of irrigation and s tations e Envelope 20 14 -11 .O Spill at stn 0+180 cum c process (Non B tation torm water infrastructure auseway Kinniya D.S.Divisi ank-SPD) on in Trincomalee District National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/RFQ/019 / Construction limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 33,500.00 0.00 plementa of Retaining walls at stn 4+ tenance of irrigation and s tations e Envelope 20 14 -15 process (Non B tion 920 in LBMC, Muthur Divisi torm water infrastructure ank-SPD) on stage I National Procur SLMOI/CRES/ID/W/S/24 / I Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 mprovements and supplyin IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 3,950.00 0.00 plementa tations e Envelope 20 14 -12 g water connection to the Impact Weather, Floods an process (Non B tion Giriulla Field Office d Landslides ank-SPD) National Procur SLMOI/CRES/ID/W/S/22 / C Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 onstruction of a Gate with F IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 3,280.00 0.00 plementa tations e Envelope 20 14 -12 ence, Flood Light Post at Si Impact Weather, Floods an process (Non B tion yabalanduwa Filed Office d Landslides ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I TRI/RFQ/059 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplemen ts to Kurankupanchan tank tenance of irrigation and s tations e Envelope 20 14 -08 process (Non B tation in Kinniya D.S.Division torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel ANU/DC/014 / Repairs of Di limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2025-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 27,333.33 0.00 Signed ulwewa Canal Spill in Nach tenance of irrigation and s 15 01 20 06 24 01 -18 n) chaduwa Division torm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I COL/NCB/024 / Balancae w limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 93,750.00 0.00 mplemen ork of Boralesgamuwa tank tenance of irrigation and s s e Envelope 15 20 31 01 05 -31 process (Non B tation U/S area Improvement Proj torm water infrastructure ank-SPD) ect - Stage (IV) CRESMPA-1/RP/WORKS/ID- KUR/DC/007 / Supply & Inst Component 5: Improving c Other (with fiel allation of Cast Iron gates limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,981.75 0.00 Signed with hoisting mechanism (1 tenance of irrigation and s 15 02 20 09 24 02 -23 n) 2 Nos,230mm) at Usgala S torm water infrastructure cheme in Galgamuwa Divisi on,Kurunegala National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MAN/RFQ/032 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplemen nts to LB Main Canal under tenance of irrigation and s tations e Envelope 20 14 -08 process (Non B tation Viyadikulam tank torm water infrastructure ank-SPD) National Procur SLMOI/CRES/ID/W/S/23 / D Component 1: Forecasting ement Docume Under Im Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 evelopment and Improvem IBRD / 89960 and Early Warning of High Post Limited nt - 1 Envelope 9,960.00 0.00 plementa tations e Envelope 20 14 -12 ents at Badalgama Field Of Impact Weather, Floods an process (Non B tion fice d Landslides ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/RFQ/022 / improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 23,600.00 0.00 plementa ts to Allai kanthale raja Ela tenance of irrigation and s tations e Envelope 20 14 -17 process (Non B tion connecting road. torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c PUT/RFQ/010 / Canal lining ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 from 2+234km to 2+374k IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplemen tenance of irrigation and s tations e Envelope 20 14 -12 m of main canal in paddy l process (Non B tation torm water infrastructure ands for resettled people in ank-SPD) Nelumgama 2nd village CRESMPA-1/RP/WORKS/ID- KUR/DC/005 / Supply and i Component 5: Improving c Other (with fiel nstallation of Sluice Gate ( limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,332.43 0.00 Canceled CI gate 600 mm) and repla tenance of irrigation and s 15 02 20 09 24 -23 n) cing hoisting mechanism in torm water infrastructure Kirithalana Sluice in Katuga mpola Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/RFQ/006 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplemen ts to BC2 from 1 + 270km t tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B tation o 1 + 410km in Mahauswe torm water infrastructure ank-SPD) wa Scheme CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel NUE/DC/003 / Improvement limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2025-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 37,056.67 0.00 Signed to main canal from 3+000k tenance of irrigation and s 15 31 20 21 24 22 -18 n) m to 3+800km in Bolagand torm water infrastructure awala scheme. CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MAN/RFQ/011 / Reconstruct ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 ion of box culvert & Improv IBRD / 89960 Post Limited nt - 1 Envelope 40,000.00 0.00 mplemen tenance of irrigation and s tations e Envelope 20 14 -08 ements to Peruveli spill tail process (Non B tation torm water infrastructure canal and agricultural road ank-SPD) under 12th mile sluice of G T Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume NUE/DC/001 / Improvement limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-10- 2024-06 IBRD / 89960 Post Direct Selection Direct - National nt - 1 Envelope 16,786.67 0.00 Signed s to main canal from 1+50 tenance of irrigation and s 15 31 20 21 24 30 -22 process (Non B 0 km to 3+000 in Ma ela s torm water infrastructure ank-SPD) cheme Page 5 National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 KAD/RFQ/009 / Improveme IBRD / 89960 Post Limited nt - 1 Envelope 22,133.33 0.00 mplemen tenance of irrigation and s tations e Envelope 20 14 -11 nts to D17 canal in stage ii process (Non B tation torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 AMP/RFQ/073 / Improveme IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 mplemen tenance of irrigation and s tations e Envelope 20 14 -10 nt for Tank Bund and Spill process (Non B tation torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c MAN/DC/005 / Fabrication Other (with fiel limate resilience and main 2023-12- 2023-02- 2023-12- 2023-11- 2024-01- 2023-09- 2024-05 & Installation of 01 No.01of IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,045.63 0.00 Signed tenance of irrigation and s 15 09 20 16 24 26 -23 SS gate for Periyanochchik n) torm water infrastructure ulam Spill in Silavathurai D ivision National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KUR/RFQ/023 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 27,814.33 0.00 mplemen n of half round pipe canal i tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation n Barawa eba from 0+850 torm water infrastructure ank-SPD) to 1+055 CRESMPA-1/RP/WORKS/ID- National Procur GAL/DC/001 / Fabrication,P Component 5: Improving c ement Docume ainting & Installation of 170 limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National nt - 1 Envelope 30,331.39 0.00 Signed 0mmx1960mm Stainless St tenance of irrigation and s 15 02 20 20 24 01 -23 process (Non B eel gates with Gear Box (0 torm water infrastructure ank-SPD) 4 Nos) for Obadawatha ani cut at Ambalangoda Divisio n, Galle CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel BAT/DC/005 / Gear arrange limate resilience and main 2023-12- 2023-05- 2023-12- 2023-05- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,716.67 0.00 Signed ment and replacing of gate tenance of irrigation and s 15 07 20 11 24 22 -23 n) s for Thumpalai anicut in N torm water infrastructure avakiri Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c KUR/DC/003 / Repairs, sand Other (with fiel limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 blasting,Painting and install IBRD / 89960 Post Direct Selection Direct - National d for explanatio 8,518.36 0.00 Signed tenance of irrigation and s 15 02 20 09 24 10 -23 ation of 08 Nos of vertical g n) torm water infrastructure ates 1500Wx1650H in Nika pitiya Anicut in Katugampol a Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/RFQ/023 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 17,000.00 0.00 plementa ts to Mollipothana LBMC ca tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B tion nal bund road from stn 0+0 torm water infrastructure ank-SPD) 00 to stn 2+000 CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel RAT/DC/086 / Repairing of t limate resilience and main 2023-12- 2023-06- 2023-12- 2023-07- 2024-01- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,666.67 0.00 Signed urnout gates in Ambagaha tenance of irrigation and s 15 29 20 06 24 -23 n) wela Ela in Panamura sche torm water infrastructure me CRESMPA-1/RP/WORKS/ID- KUR/DC/006 / Fabrication,s Component 5: Improving c Other (with fiel and blasting, painting and i limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,000.00 0.00 Signed nstallation of gates with hoi tenance of irrigation and s 15 02 20 09 24 02 -23 n) sting mechanisms at Batuw torm water infrastructure aththa Regulators,in Hiriyal a Division, Kurunegala CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel BAT/DC/010 / Reconstructio limate resilience and main 2023-12- 2023-05- 2023-12- 2023-05- 2024-01- 2023-08- 2024-10 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 50,833.33 0.00 Signed n of Vinayagar Anicut in,Na tenance of irrigation and s 15 04 20 11 24 10 -20 n) vakari Scheme, Navakari Di torm water infrastructure vision National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I TRI/RFQ/035 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplemen ts of Channel System Near tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B tation the Olukolla Sumith House torm water infrastructure ank-SPD) to 1km Drainage CRESMPA-1/RP/WORKS/ID- TRI/DC/002 / Fabrication & I Component 5: Improving c nstallation of 04 Nos of mil Other (with fiel limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 d steel Anicut slide gates ( IBRD / 89960 Post Direct Selection Direct - National d for explanatio 28,678.23 0.00 Signed tenance of irrigation and s 15 08 20 22 24 05 -23 1800x1800mm) with hoisti n) torm water infrastructure ng mechanisms and all co mponents and handrail for Portankadu regulator in Ka ntale Division, Trincomalee National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 GAM/NCB/053 / Reconstruc IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 mplemen tenance of irrigation and s s e Envelope 15 20 31 01 05 -31 tion of the Katiyala Anicut process (Non B tation torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- PUT/DC/002 / Fabrication & Component 5: Improving c Other (with fiel Installation of deteriorated limate resilience and main 2023-12- 2023-05- 2023-12- 2023-05- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 23,402.62 0.00 Signed Verticle regulator gates an tenance of irrigation and s 15 03 20 10 24 01 -23 n) d repair their necessary hoi torm water infrastructure sting mechanisms, in RBMC Inginimitiya Scheme CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel MAN/DC/004 / Fabrication limate resilience and main 2023-12- 2023-02- 2023-12- 2023-02- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 2,146.36 0.00 Signed & Installation of 01 No.of S tenance of irrigation and s 15 09 20 16 24 26 -23 n) S gate for Sadaiyappan Spil torm water infrastructure l in Silavathurai Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel POL/DC/146 / Improvement limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2024-10 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 23,686.67 0.00 Signed s to FC 3 canal under Pulas tenance of irrigation and s 15 26 20 02 24 -20 n) thigama DCO area torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel COL/DC/015 / Removing of limate resilience and main 2023-12- 2023-07- 2023-12- 2023-07- 2024-01- 2025-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,625.00 0.00 Signed water weeds in Thalangam tenance of irrigation and s 15 21 20 30 24 -18 n) a tank in Kaduwela torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c BAT/DC/011 / Construction Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-05- 2024-01- 2023-08- 2024-07 of overcrossing in RB Main IBRD / 89960 Post Direct Selection Direct - National d for explanatio 25,133.33 0.00 Signed tenance of irrigation and s 15 07 20 11 24 10 -22 Channal at Stn 18+800 in n) torm water infrastructure Unnichchai Scheme,Rugam Division CRESMPA-1/RP/WORKS/ID- TRI/DC/003 / Painting 02 N Component 5: Improving c os of Radial gate Structure Other (with fiel limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 using Colta, installing stainl IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,347.37 0.00 Signed tenance of irrigation and s 15 08 20 22 24 05 -23 ess steel cables,fabrication n) torm water infrastructure of handrail and repair guid e wheel of Kusumankada A nicut in Kantale Division, Tr incomalee CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel COL/DC/005 / Desilting of U limate resilience and main 2023-12- 2023-07- 2023-12- 2023-07- 2024-01- 2024-06 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,000.00 0.00 Signed nnecessary obstracles in H tenance of irrigation and s 15 21 20 30 24 -22 n) aldummulla Canal 0+000 t torm water infrastructure o 1+000 CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel POL/DC/113 / Improvement limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-10- 2024-07 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,123.33 0.00 Signed s to South canal bund road tenance of irrigation and s 15 26 20 02 24 05 -22 n) in Swarnapaligama DCO torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel PUT/DC/007 / Improvemem limate resilience and main 2023-12- 2023-05- 2023-12- 2023-05- 2024-01- 2023-08- 2025-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 90,000.00 0.00 Signed nts to Maiyawa tank & 1st s tenance of irrigation and s 15 03 20 10 24 21 -18 n) pill in sengaloya Scheme torm water infrastructure CRESMPA-1/RP/WORKS/ID- MAN/DC/002 / Fabrication Component 5: Improving c Other (with fiel & Installation of 10 Nos. of limate resilience and main 2023-12- 2023-02- 2023-12- 2023-02- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 9,134.56 0.00 Signed Rads & 5th Gear Box for Gi tenance of irrigation and s 15 09 20 16 24 26 -23 n) ants Tank Head Sluice Gate torm water infrastructure of Giants Tank Scheme in Murunkan Division CRESMPA-1/RP/WORKS/ID- MATR/DC/002 / Fabrication, Component 5: Improving c Other (with fiel Painting & Installation of 17 limate resilience and main 2023-12- 2023-06- 2023-12- 2023-07- 2024-01- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,009.60 0.00 Signed 00mmx1320mm Mild Steel tenance of irrigation and s 15 30 20 09 24 -23 n) gates with gear box (01No torm water infrastructure s) for Indurumulla anicut at Matara Division, Galle CRESMPA-1/RP/WORKS/ID- Component 5: Improving c MATR/DC/007 / Supply and Other (with fiel Pending I limate resilience and main 2023-12- 2023-12- 2024-01- 2024-05 Installation of gear motors, IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,288.22 0.00 mplemen tenance of irrigation and s 15 20 24 -23 worm & Wheel gear boxes n) tation torm water infrastructure and Electrical wiring of gra vity gates in Thudawa Pum p House CRESMPA-1/RP/WORKS/ID- Component 5: Improving c POL/DC/144 / 77 m long ca Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-10- 2024-07 nal lining at 2+800 and Co IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,423.33 0.00 Signed tenance of irrigation and s 15 26 20 02 24 16 -22 nstruction of 22 m long ret n) torm water infrastructure aining wall at 1+940 in RB side in LB 3 off D1 east can al CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel MAN/DC/006 / Fabrication limate resilience and main 2023-12- 2023-02- 2023-12- 2023-02- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,919.91 0.00 Signed & Installation of 02 No.of S tenance of irrigation and s 15 14 20 16 24 26 -23 n) S gate for Palaikkuli Regula torm water infrastructure tor Spill in Silavathurai Divi sion CRESMPA-1/RP/WORKS/ID- Component 5: Improving c BAT/DC/004 / Supplying an Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-05- 2024-01- 2023-09- 2024-05 d installing steel gate with IBRD / 89960 Post Direct Selection Direct - National d for explanatio 7,000.00 0.00 Signed tenance of irrigation and s 15 04 20 11 24 22 -23 component to Vellaviraloda n) torm water infrastructure i anicut in Rugam Scheme Rugam Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c BAT/DC/007 / Suppling and Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-05- 2024-01- 2023-09- 2024-05 installing steel gate with co IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,433.33 0.00 Signed tenance of irrigation and s 15 05 20 11 24 22 -23 mponent to Udayandasenai n) torm water infrastructure anicut in Unnichchai schem e Rugam Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Under Im PUT/DC/011 / Construction limate resilience and main 2023-12- 2023-04- 2023-12- 2023-05- 2024-01- 2025-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 50,000.00 0.00 plementa of flood bund to avoid inun tenance of irrigation and s 15 21 20 05 24 -18 n) tion dation of paddy lands durin torm water infrastructure g floods CRESMPA-1/RP/WORKS/ID- GAL/DC/005 / Fabrication,P Component 5: Improving c Other (with fiel ainting & Installation of 170 limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 7,544.65 0.00 Signed 0mmx1600mm Mild Steel g tenance of irrigation and s 15 31 20 20 24 01 -23 n) ates with Gear Box (02Nos) torm water infrastructure for Wathurawayaya anicut at Gingaga Division, Galle CRESMPA-1/RP/WORKS/ID- MATR/DC/001 / Fabrication, Component 5: Improving c Other (with fiel Painting & Installation of 16 limate resilience and main 2023-12- 2023-06- 2023-12- 2023-07- 2024-01- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,284.75 0.00 Signed 75mmx1650mm Mild Steel tenance of irrigation and s 15 30 20 09 24 -23 n) gates (02Nos) for Waduwa torm water infrastructure kanda anicut at Matara Divi sion, Galle CRESMPA-1/RP/WORKS/ID- MATR/DC/003 / Fabrication, Component 5: Improving c Other (with fiel Painting & Installation of 16 limate resilience and main 2023-12- 2023-06- 2023-12- 2023-07- 2024-01- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,391.54 0.00 Signed 80mmx2360mm Mild Steel tenance of irrigation and s 15 30 20 09 24 -23 n) gates (02Nos) for Meegah torm water infrastructure agoda anicut at Matara Divi sion, Galle CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I GAL/DC/048 / Rehabilitatio limate resilience and main 2023-12- 2023-12- 2024-01- 2024-07 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,666.67 0.00 mplemen n of Mihirithanna pumphou tenance of irrigation and s 15 20 24 -22 n) tation se torm water infrastructure CRESMPA-1/RP/WORKS/ID- MATR/DC/006 / Supply and Component 5: Improving c Other (with fiel Pending I Installation of gear motors, limate resilience and main 2023-12- 2023-12- 2024-01- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,288.22 0.00 mplemen worm & Wheel gear boxes tenance of irrigation and s 15 20 24 -23 n) tation and Electrical wiring of gra torm water infrastructure vity gates in Magallagoda p ump house, Matara Divisio n, Galle CRESMPA-1/RP/WORKS/ID- VAV/DC/003 / Fabrication & Component 5: Improving c Other (with fiel Installation of 05 Nos.of Ca limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-04 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,362.15 0.00 Signed st Iron Gates with all Comp tenance of irrigation and s 15 31 20 09 24 26 -23 n) onents at FC- 19th, FC-21st torm water infrastructure , FC - 24th & D - 05 of Muh athankulam Scheme in Vav uniya Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel POL/DC/073 / Improvement limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 10,566.67 0.00 Signed s to FC3/RB17 canal in Bau tenance of irrigation and s 15 26 20 02 24 02 -23 n) ddharthagama DCO area torm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/RFQ/009 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 mplemen ts to Karawita spill in karaw tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B tation ita Scheme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I GAL/DC/056 / Rehabilitatio limate resilience and main 2023-12- 2023-12- 2024-01- 2024-07 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,000.00 0.00 mplemen n of Thudugala canal (Hika tenance of irrigation and s 15 20 24 -22 n) tation duwa, Nakanda, Wellawatt torm water infrastructure a vaulgoda, nalagasdeniya) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel POL/DC/093 / Construction limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-10- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,926.67 0.00 Signed of 152m long Retaining wal tenance of irrigation and s 15 26 20 02 24 02 -20 n) l at 0+550 in LB side in RB torm water infrastructure 12 off D1 east canal. CRESMPA-1/RP/WORKS/ID- COL/DC/002 / Supply and in Component 5: Improving c Other (with fiel stall new flood control gate limate resilience and main 2023-12- 2023-07- 2023-12- 2023-07- 2024-01- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 10,000.00 0.00 Signed (H = 1525mm x B=1370m tenance of irrigation and s 15 21 20 30 24 -23 n) m) with SS embbeded part torm water infrastructure s and hoisting (Tunnel Radi us = 2') Ranwala Muththett upola MF CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel PUT/DC/001 / Fabrication & limate resilience and main 2023-12- 2023-05- 2023-12- 2023-05- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 18,667.25 0.00 Signed Installation of deteriorated tenance of irrigation and s 15 03 20 10 24 01 -23 n) gates and repair their nece torm water infrastructure ssary hoisting mechanisms National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MAN/RFQ/015 / Reparing a limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 IBRD / 89960 Post Limited nt - 1 Envelope 40,000.00 0.00 mplemen nd improvements to Illanda tenance of irrigation and s tations e Envelope 20 14 -08 process (Non B tation kulam feeder tank in Akathi torm water infrastructure ank-SPD) murippu Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im KUR/NCB/032 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 61,020.00 0.00 plementa nts to D2 canal & construct tenance of irrigation and s s e Envelope 15 04 20 31 01 05 -31 process (Non B tion ion of retaining wall at 14+ torm water infrastructure ank-SPD) 600 in Dolukanda main can al National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/RFQ/019 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 mplemen ts of canal section in FC - 2, tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation FC - 3 (Tr - 3) canal RBMC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/RFQ/004 / Reconstructi limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 6,666.67 0.00 mplemen on of damaged pier of trou tenance of irrigation and s tations e Envelope 20 14 -13 process (Non B tation gh structure in DI canal of torm water infrastructure ank-SPD) Radavi Bendi ela Scheme CRESMPA-1/RP/WORKS/ID- Component 5: Improving c MAN/DC/001 / Fabrication Other (with fiel limate resilience and main 2023-12- 2023-02- 2023-12- 2023-02- 2024-01- 2023-09- 2024-05 & Installation of 04 Nos.of IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,478.80 0.00 Signed tenance of irrigation and s 15 09 20 16 24 26 -23 Canal Spill Gates of Giants n) torm water infrastructure Tank Scheme in Murunkan Division CRESMPA-1/RP/WORKS/ID- COL/DC/004 / Fabrication, s Component 5: Improving c andblasting, painting and i Other (with fiel limate resilience and main 2023-12- 2023-07- 2023-12- 2023-07- 2024-01- 2024-05 nstallation of 01 no of 1400 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 12,433.33 0.00 Signed tenance of irrigation and s 15 21 20 30 24 -23 Wx2250H mild steel vertica n) torm water infrastructure l gate with lifting mechnis m and embodeded parts an d hoisting at Lanarol Mawat ha CRESMPA-1/RP/WORKS/ID- Component 5: Improving c COL/DC/003 / Fabrication, S Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-07- 2024-01- 2024-05 andblasting, Painting & Inst IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,666.67 0.00 Signed tenance of irrigation and s 15 01 20 30 24 -23 allation of gates with lifting n) torm water infrastructure mechanism and replace ge ar box at Thalangama National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/RFQ/023 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 mplemen ts to FC - 09, D2 canal in Tr tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B tation .02 in Ingnimitiya RBMC torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c VAV/DC/002 / Repair,Fabric Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 ation & Installation of SS G IBRD / 89960 Post Direct Selection Direct - National d for explanatio 9,271.35 0.00 Signed tenance of irrigation and s 15 31 20 09 24 26 -23 ates & Shop planks at Pava n) torm water infrastructure tkulam LB Main Canal in Va vuniya Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im AMP/NCB/045 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-11- 2024-04- 2023-11- 2024-01- 2024-02- 2024-03- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 plementa nts JW-10 channel in Palla tenance of irrigation and s s e Envelope 20 08 25 06 05 11 -06 process (Non B tion noya scheme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel VAV/DC/008 / Improvement limate resilience and main 2023-08- 2023-05- 2023-08- 2023-06- 2023-09- 2023-10- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 47,400.00 0.00 Signed s to Purana canal in LB mai tenance of irrigation and s 15 31 20 09 24 30 -18 n) n canal at Pavatkulam torm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im AMP/NCB/060 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-11- 2024-04- 2023-11- 2024-01- 2024-02- 2024-03- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 43,333.33 0.00 plementa nts to PG-2 canal In Pannal tenance of irrigation and s s e Envelope 20 08 25 06 05 11 -06 process (Non B tion gama scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume AMP/NCB/075 / Drainage i limate resilience and main Request for Bid Single Stage - On 100,000.0 2023-11- 2023-11- 2024-01- 2024-02- 2024-03- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 Canceled mprovement of Upparu rive tenance of irrigation and s s e Envelope 0 20 25 06 05 11 -06 process (Non B r torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I COL/NCB/016 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 62,500.00 0.00 mplemen nts to Kelani River LB 24+0 tenance of irrigation and s s e Envelope 15 20 31 01 05 -31 process (Non B tation 00 to 25+320 km in Waikki torm water infrastructure ank-SPD) watte GS Division. CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel COL/DC/001 / Fabrication, S limate resilience and main 2023-12- 2023-07- 2023-12- 2023-07- 2024-01- 2023-10- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 66,666.67 0.00 Signed andblasting, Painting & Inst tenance of irrigation and s 15 23 20 30 24 05 -23 n) allation of gates with lifting torm water infrastructure mechanism at Weniwelkola CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel MAN/DC/003 / Fabrication limate resilience and main 2023-12- 2023-02- 2023-12- 2023-02- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,110.12 0.00 Signed & Installation of 01 No.of S tenance of irrigation and s 15 09 20 16 24 26 -23 n) S Gate for Karunagakithalv torm water infrastructure u Spill in Silavathurai Divisi on National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im AMP/NCB/090 / Remidial M limate resilience and main Request for Bid Single Stage - On 2023-11- 2024-04- 2023-11- 2024-01- 2024-02- 2024-03- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 96,666.67 0.00 plementa easures for D/S improveme tenance of irrigation and s s e Envelope 20 08 25 06 05 11 -06 process (Non B tion nts of Navalaru Main Anicut torm water infrastructure ank-SPD) in Navalaru Scheme Page 6 CRESMPA-1/RP/WORKS/ID- VAV/DC/004 / Fabrication & Component 5: Improving c Other (with fiel Installation of SS gate for T limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-04 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 4,712.62 0.00 Signed urnout & Regulator for Bra tenance of irrigation and s 15 31 20 09 24 26 -23 n) nch Canal of RB Main Canal torm water infrastructure of Pavatkulam Scheme in V avuniya Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im AMP/NCB/091 / Improveme limate resilience and main Request for Bid Single Stage - On 2023-11- 2024-04- 2023-11- 2024-01- 2024-02- 2024-03- 2025-01 IBRD / 89960 Post Open - National nt - 1 Envelope 40,000.00 0.00 plementa nts to Thangapulla main ca tenance of irrigation and s s e Envelope 20 08 25 06 05 11 -05 process (Non B tion nal in Karandaoya scheme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel KAL/DC/006 / Clearing & de limate resilience and main 2023-12- 2023-06- 2023-12- 2023-07- 2024-01- 2023-11- 2024-08 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 20,000.00 0.00 Signed silting of Dummalamodara tenance of irrigation and s 15 30 20 05 24 21 -21 n) Ela - (1+600 to 5+000) torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Under Im HAM/DC/014 / Improvemen limate resilience and main 2023-12- 2023-07- 2023-12- 2023-07- 2024-01- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,160.00 0.00 plementa ts to Spill approach of Uduk tenance of irrigation and s 15 07 20 15 24 -23 n) tion iriwila tank,Urubokka - Oya torm water infrastructure Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I HAM/RFQ/029 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 27,830.00 0.00 mplemen on of FC11,Track 01,LBMC, tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation Lunugamwehera torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I VAV/RFQ/006 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 29,933.33 0.00 mplemen nts to LB - 02 canal off D-1 tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation 5 canal off RB main canal a torm water infrastructure ank-SPD) t Pavatkulam CRESMPA-1/RP/WORKS/ID- GAL/DC/004 / Fabrication,P Component 5: Improving c Other (with fiel ainting & Installation of 165 limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,577.72 0.00 Signed 0mmx1200mm Mild Steel g tenance of irrigation and s 15 31 20 20 24 01 -23 n) ates with Gear Box (02Nos) torm water infrastructure for Ala ihalayaya anicut at Gingaga Division, Galle CRESMPA-1/RP/WORKS/ID- BAD/DC/072 / Improments Component 5: Improving c to D1 & D2 Canal regulato Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 r gates, canal spill gates at IBRD / 89960 Post Direct Selection Direct - National d for explanatio 8,766.67 0.00 Signed tenance of irrigation and s 15 31 20 06 24 20 -23 1+250 of LBMC and 2 Nos n) torm water infrastructure gates at D3 canal of LBMC of Sorabora wewa, Mapaka da Division, Bandarawela CRESMPA-1/RP/WORKS/ID- KUR/DC/001 / Fabrication, s Component 5: Improving c Other (with fiel and blasting, painting and i limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 23,789.58 0.00 Signed nstallation of 05 Nos of Ver tenance of irrigation and s 15 02 20 09 24 02 -23 n) tical gates 1550Wx1250H f torm water infrastructure or Walpaluwa Wewa and Pa nda Wewa in Wariyapola Di vision . CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel POL/DC/081 / Construction limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,133.33 0.00 Signed of 45m long retaining wall tenance of irrigation and s 15 26 20 02 24 02 -23 n) at 0+550 in LB 2/D 2 main torm water infrastructure canal CRESMPA-1/RP/WORKS/ID- KAL/DC/003 / Fabrication , Component 5: Improving c sandblasting , painting & in Other (with fiel limate resilience and main 2023-12- 2023-06- 2023-12- 2023-11- 2024-01- 2023-10- 2024-05 stallation of mild steel verti IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,833.33 0.00 Signed tenance of irrigation and s 15 30 20 07 24 09 -23 cal gate with lifting macha n) torm water infrastructure nism and embedded parts at Kolamediriya anicut at B algoda Scheme in Kaluthar a Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I KAL/DC/008 / Fabrication of limate resilience and main 2023-12- 2023-12- 2024-01- 2024-04 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,333.33 0.00 mplemen Damaged Gates at 0+800 tenance of irrigation and s 15 20 24 -23 n) tation at RB Low Level Canal torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Under Im POL/DC/141 / Improvement limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2024-10 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,050.00 0.00 plementa s to FC 01 canal in D3 Sout tenance of irrigation and s 15 26 20 02 24 -20 n) tion h canal in D3 unit torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c KUR/DC/004 / Repair, Fixin Other (with fiel limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 g Hoisting Mechanisms of 0 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 18,046.64 0.00 Signed tenance of irrigation and s 15 02 20 09 24 02 -23 6 Nos of vertical gates 160 n) torm water infrastructure 0Wx1830H in Madulla Anic ut in Katugampola Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I KAL/DC/018 / Improvement limate resilience and main 2023-12- 2023-12- 2024-01- 2024-06 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 15,000.00 0.00 mplemen s to flood controlling gate a tenance of irrigation and s 15 20 24 -22 n) tation t Kalugoda flood bund ( 1n torm water infrastructure os) gate number 1. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/RFQ/013 / Construction limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 27,666.67 0.00 plementa of retaining walls at Stn 4+ tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tion 800 in LBMC Mutur Division torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- ANU/DC/004 / Refabrication Component 5: Improving c Other (with fiel of lifting eye brackets and, limate resilience and main 2023-12- 2023-05- 2023-12- 2023-06- 2024-01- 2023-09- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 6,475.83 0.00 Signed replacing all lifting wire rop tenance of irrigation and s 15 30 20 06 24 27 -23 n) es and turn buckels of radi torm water infrastructure al gates at Ellapothana Ani cut in Huruluwewa Division, Anuradhapura National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MON/RFQ/63 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 mplemen ts to Kirioruwa Tank bund a tenance of irrigation and s tations e Envelope 20 14 -08 process (Non B tation nd sluice torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/RFQ/008 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 22,866.67 0.00 plementa ts to D7 Drainange Channel tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tion /LBMC from Stn 0+000 to S torm water infrastructure ank-SPD) tn 4+130 in Muthur Divisio n National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/RFQ/014 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 26,000.00 0.00 plementa ts of LB2/D10 Canal from st tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tion n 0+000 to stn 1+100 in M torm water infrastructure ank-SPD) orawewa Scheme CRESMPA-1/RP/WORKS/ID- National Procur BAT/RFQ/017 / Reconstructi Component 5: Improving c ement Docume Pending I on of Causeway at Puliyadi limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 34,666.67 0.00 mplemen across unit 38 & 39 unit 40 tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation connecting Road at Stn 0 + torm water infrastructure ank-SPD) 865 in Navakari Scheme,Na vakari Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I BAT/RFQ/012 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 40,000.00 0.00 mplemen nts to Pandarakkadu small tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation bridge cum regulator in Ru torm water infrastructure ank-SPD) gam Scheme,Rugam Divisi on CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c KUR/RFQ/019 / Improveme ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-09 nts canal bund from 12+2 IBRD / 89960 Post Limited nt - 1 Envelope 20,423.33 0.00 mplemen tenance of irrigation and s tations e Envelope 20 14 -11 40 km to 12+465 km & con process (Non B tation torm water infrastructure struction of under crossing ank-SPD) structure at 12+561 in LB MC CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c GAM/NCB/001 / Constructio ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 n of over-crossing across H IBRD / 89960 Post Open - National nt - 1 Envelope 57,333.33 0.00 mplemen tenance of irrigation and s s e Envelope 15 20 31 01 05 -31 orakndavila drainage canal process (Non B tation torm water infrastructure in Bemmulla Deranagoda Ir ank-SPD) rigation scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/RFQ/011 / Gravelling M limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 22,000.00 0.00 plementa ollipothana LBMC Bund Roa tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tion d from Stn 3+900 to Stn 6 torm water infrastructure ank-SPD) +650 in Kanthale National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KUR/RFQ/029 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 29,146.67 0.00 mplemen nts to FC18 of LBMC in Mag tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation alla scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KAD/RFQ/004 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 mplemen nts to FC 26 at Murapola el tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tation a scheme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I MATR/DC/009 / Improveme limate resilience and main 2023-12- 2023-12- 2024-01- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 22,500.00 0.00 mplemen nts to drainage canals in K tenance of irrigation and s 15 20 24 -20 n) tation adawedduwa scheme torm water infrastructure CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c TRI/RFQ/043 / Reconstructi ement Docume Pending I limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 on of Velverikulam LB C.O IBRD / 89960 Post Limited nt - 1 Envelope 30,366.67 0.00 mplemen tenance of irrigation and s tations e Envelope 20 14 -12 Spill at stn 0+200 in Town process (Non B tation torm water infrastructure & Gravets DS Division in Tri ank-SPD) ncomalee District National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/RFQ/029 / Desilting wor limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 26,333.33 0.00 plementa k in Helaba yaya Egoda Ya tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tion ya drainage canal stn 0+00 torm water infrastructure ank-SPD) 0 to stn 2+200 National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/RFQ/030-1 / Constructi limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 25,333.33 0.00 plementa on of retaining walls at stn tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B tion 14+409 to stn 14+494 in R torm water infrastructure ank-SPD) BMC,Muthur Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im TRI/RFQ/031 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 IBRD / 89960 Post Limited nt - 1 Envelope 21,333.33 0.00 plementa ts to Muthur canal bund ro tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B tion ad from stn 0+000 to stn 1 torm water infrastructure ank-SPD) +200 in Muthur Division CRESMPA-1/RP/WORKS/ID- KUR/DC/005-2 / Supply and Component 5: Improving c Other (with fiel installation of Sluice Gate ( limate resilience and main 2023-12- 2023-06- 2023-12- 2023-06- 2024-01- 2023-10- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 1,332.43 0.00 Signed CI gate 600 mm) and repla tenance of irrigation and s 15 02 20 09 24 02 -23 n) cing hoisting mechanism in torm water infrastructure Kirithalana Sluice in Katuga mpola Division CRESMPA-1/RP/WORKS/ID- Component 5: Improving c HAM/DC/033 / Improvemen Other (with fiel limate resilience and main 2023-12- 2023-05- 2023-12- 2023-07- 2024-01- 2024-05 t to flood bund at 480m D/ IBRD / 89960 Post Direct Selection Direct - National d for explanatio 13,225.00 0.00 Signed tenance of irrigation and s 14 31 19 15 23 -22 S of Hunnakumbura anicut n) torm water infrastructure urubokka oya, in urubokka oya scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I GAL/RFQ/014 / Constructio limate resilience and main Request for Quo Single Stage - On 2024-01- 2024-03- 2025-01 IBRD / 89960 Post Limited nt - 1 Envelope 18,665.00 0.00 mplemen n Olanda Anicut at stn 0+0 tenance of irrigation and s tations e Envelope 20 16 -10 process (Non B tation 25 in Olanda channel in Hol torm water infrastructure ank-SPD) uwagoda scheme National Procur SLMOI/CRES/ID/W/NCB/31 / Component 1: Forecasting ement Docume Renovation of the Governm and Early Warning of High Request for Bid Single Stage - On 2024-02- 2024-02- 2024-02- 2024-03- 2024-04- 2024-07 IBRD / 89960 Post Open - National nt - 1 Envelope 78,125.00 0.00 Canceled ent Audit Branch at the Mai Impact Weather, Floods an s e Envelope 01 06 27 19 16 -15 process (Non B n Building of the Irrigation d Landslides ank-SPD) Department - Head Office Component 5: Improving c CRESMPA-1/RP/WORKS/ID- Other (with fiel limate resilience and main 100,000.0 2024-01- 2023-11- 2024-02- 2023-11- 2024-03- 2025-03 AMP/DC/075 / Drainage im IBRD / 89960 Post Direct Selection Direct - National d for explanatio 0.00 Signed tenance of irrigation and s 0 31 07 05 14 11 -06 provement of Upparu river n) torm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I AMP/NCB/92 / Iprovements limate resilience and main Request for Bid 2024-01- 2024-02- 2024-03- 2024-04- 2024-05- 2024-11 IBRD / 89960 Post nt - 1 Envelope 20,000.00 0.00 mplemen of Palliayadia main anicut i tenance of irrigation and s s 31 05 18 17 22 -18 process (Non B tation n Karandaoya scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/008 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 Canceled ts to Canal System in Halmi tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B lla Wewa in Hatharas Kotu torm water infrastructure ank-SPD) wa National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MON/RFQ/024 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 26,000.00 0.00 Canceled n of canal lining and box cu tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B lvert from 0+053 to 0+165 torm water infrastructure ank-SPD) in Dambewewa RB main ca nal National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 MON/RFQ/60 / Improvemen IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -24 ts to Kindaliya tank canal process (Non B torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 MON/RFQ/61 / Improvemen IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -24 t to Nawaara Tank LB canal process (Non B torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 MON/RFQ/62 / Improvemen IBRD / 89960 Post Limited nt - 1 Envelope 48,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -24 t to Nawaara Tank RB canal process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MON/RFQ/64 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 Canceled ts to Kirioruwa Tank canal s tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B ystem torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 MON/RFQ/65 / Rehabilitatio IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -08 n of Waliara tank - LB canal process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MON/RFQ/66 / Rehabilitatio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 48,333.33 0.00 Canceled n of Thenagallanda Tank ca tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B nal system torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/008 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 16,666.67 0.00 plementa nts of Canal System in Hal tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -28 process (Non B tion milla Wewa in Hatharas Kot torm water infrastructure ank-SPD) uwa National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/043 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 19,383.33 0.00 Canceled ts to D 01 canal in Ranketh tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B a DCO area in LLMC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/051 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 31,206.67 0.00 Canceled ts to D - 3 canal in Weerak tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B eppetipola DCO area in HL torm water infrastructure ank-SPD) BC 1A National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/056 / Filling pot h limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 25,000.00 0.00 Canceled oll and gravelling along LB tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B 06 canal off D04 canal torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/058 / Gravelling t limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-01 IBRD / 89960 Post Limited nt - 1 Envelope 18,490.00 0.00 Canceled o Canal bund road from 7+ tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B 000 to 7+332 of RB1 off D2 torm water infrastructure ank-SPD) main canal National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 POL/RFQ/059 / Improvemen IBRD / 89960 Post Limited nt - 1 Envelope 34,716.67 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -28 ts to FC - 32 canal process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/060 / Filling pot h limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-01 IBRD / 89960 Post Limited nt - 1 Envelope 22,400.00 0.00 Canceled olls in LB03 , FC02 off LB03 tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B , FC03 off LB03 in D04 can torm water infrastructure ank-SPD) al CRESMPA-1/RP/WORKS/ID- POL/RFQ/061 / Demolished existing hume pipe culvert National Procur Component 5: Improving c & construction of 11.4m lo ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 ng box culvert at stn. 0+60 IBRD / 89960 Post Limited nt - 1 Envelope 17,966.67 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -26 0, construction of 27m long process (Non B torm water infrastructure rectangular canal lining & 8 ank-SPD) m long box culvert at stn. 0 +750 & construction of 6m long wall and 6m long box culvert at stn. 0+820 in Ku National Procur mCRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/062 / Canal lining limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 37,776.67 0.00 Canceled at 0+036 to 0+215 in LB 6 tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B off D 2 canal torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/070 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 22,960.00 0.00 Canceled ts to FC - 01 canal in Govis tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B etha DCO area in HLBC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/071 / Rehabilitatio limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 34,833.00 0.00 Canceled n of LB11/D28/LBMC in Min tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B neriya Division torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/075 / Construction limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 36,833.33 0.00 Canceled of conc. Lining from 0+140 tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B to 0+290 of LB 01 FC / D0 torm water infrastructure ank-SPD) 5 / RB-01 in Girithale Main Canal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/079 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 36,033.33 0.00 Canceled ts to RB 07/ii of D07 / RB 0 tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B 1 MC in Girithale Scheme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur POL/RFQ/084 / Contruction Component 5: Improving c ement Docume of 80m long U type canal li limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 39,100.00 0.00 Canceled ning from stn 0+046 to stn tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B 0+126 in Batuhena (FC 59 torm water infrastructure ank-SPD) Canal) Nikapitiya D canal i n Elahara division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/087 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 25,366.67 0.00 Canceled ts to RB/1 tail end in D07 c tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B anal in Girithale Scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/095 / Gravelling & limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 18,133.33 0.00 Canceled Forming Bund Road of FC0 tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B 9 & FC11 / LB 01 in Girithal torm water infrastructure ank-SPD) e Main Canal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/098 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 28,333.33 0.00 Canceled ts to RB 5 canal in Kalinga tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B DCO area in LLMC torm water infrastructure ank-SPD) Page 7 National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 POL/RFQ/099 / Improvemen IBRD / 89960 Post Limited nt - 1 Envelope 38,200.00 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -30 ts to D 10 / RB 01 process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/101 / Construction limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 41,113.33 0.00 Canceled of 230 m long retaining wal tenance of irrigation and s tations e Envelope 05 30 -29 process (Non B l at 1+550 in RB side in RB torm water infrastructure ank-SPD) 10 off D1 east canal CRESMPA-1/RP/WORKS/ID- POL/RFQ/112 / Construction of the 18m long rectangula National Procur Component 5: Improving c r canal lining at stn. 0+000 ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 , demolished old damage e IBRD / 89960 Post Limited nt - 1 Envelope 21,666.67 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -26 xisting hume pipe trough st process (Non B torm water infrastructure ructure & reconstruction of ank-SPD) 8m long rectangular trough structure at stn. 0+018 & c onstruction 36m long retai ning wall structure at stn. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/114 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 21,666.67 0.00 Canceled ts to D - 1 canal in Samagi tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B DCO in LLMC torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/RFQ/128 / Construction ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 of canal lining from stn. 3+ IBRD / 89960 Post Limited nt - 1 Envelope 21,666.66 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -26 400 to stn. 3+510 in B503 process (Non B torm water infrastructure Sirikanduyaya Katuwa cana ank-SPD) l in Sirikanduyaya DCFO ar ea. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/134 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 Canceled ts to Trough structure at st tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B n. 2+770 in Ihakuluwewa torm water infrastructure ank-SPD) main canal (510 LB Canal) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MON/NCB/024 / Constructio ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2024-12 n of canal lining and box cu IBRD / 89960 Post Open - National nt - 1 Envelope 26,000.00 0.00 mplemen tenance of irrigation and s s e Envelope 19 19 29 29 03 -30 lvert from 0+053 to 0+165 process (Non B tation torm water infrastructure in Dambewewa RB main ca ank-SPD) nal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/135 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 36,430.00 0.00 Canceled ts to FC 4 canal in Boowew tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B a scheme torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 MON/NCB/60 / Improvemen IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 plementa tenance of irrigation and s s e Envelope 19 19 19 29 29 03 -28 ts to Kindaliya tank canal process (Non B tion torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/142 / Construction limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 28,333.33 0.00 Canceled of Canal Spill at 29+290 in tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B D37/LBMC in Vihara mawat torm water infrastructure ank-SPD) ha DCO in Minneriya Sche me National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 MON/NCB/61 / Improvemen IBRD / 89960 Post Open - National nt - 1 Envelope 30,000.00 0.00 plementa tenance of irrigation and s s e Envelope 19 19 19 29 29 03 -28 t to Nawaara Tank LB canal process (Non B tion torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 MON/NCB/62 / Improvemen IBRD / 89960 Post Open - National nt - 1 Envelope 30,000.00 0.00 plementa tenance of irrigation and s s e Envelope 19 19 19 29 29 03 -28 t to Nawaara Tank RB canal process (Non B tion torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/RFQ/143 / Improvemen ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 ts to Elikibulawa (B 508) Ca IBRD / 89960 Post Limited nt - 2 Envelope 20,000.00 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -26 nal from stn. 1+500 to stn. process (Non B torm water infrastructure 2+760 in Elikibulawa DCFO ank-SPD) Area National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/148 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 2 Envelope 10,490.00 0.00 Canceled ts to LB side bund at 8+20 tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B 0 in D1 east canal torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/64 / Improvemen limate resilience and main Request for Bid Single Stage - On 100,000.0 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 plementa ts to Kirioruwa Tank canal s tenance of irrigation and s s e Envelope 0 19 19 19 29 29 03 -28 process (Non B tion ystem torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/RFQ/153 / Demolishing ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 and New Constrction of 16 IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -26 0 m long retaining wall fro process (Non B torm water infrastructure m 0+000 km to 0+160km ank-SPD) D17 /LBMC National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 MON/NCB/65 / Rehabilitatio IBRD / 89960 Post Open - National nt - 1 Envelope 30,000.00 0.00 plementa tenance of irrigation and s s e Envelope 19 19 19 29 29 03 -28 n of Waliara tank - LB canal process (Non B tion torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/66 / Rehabilitatio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 plementa n of Thenagallanda Tank ca tenance of irrigation and s s e Envelope 19 19 19 29 29 03 -28 process (Non B tion nal system torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/NCB/043 / Improveme ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-04 nts to D01 canal in Ranket IBRD / 89960 Post Open - National nt - 1 Envelope 19,383.33 0.00 plementa tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -29 ha DCO area from 5+875 t process (Non B tion torm water infrastructure o 5+925 in LLMC in Kaudull ank-SPD) a Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/051 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 31,206.67 0.00 plementa nts to D 03 canal in Weerak tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -28 process (Non B tion eppetipola DCO area in HL torm water infrastructure ank-SPD) BC 1A in Kaudulla division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/133 / Rehabilitatio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 Canceled n of the Spill Canal (RB01) tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B & Bund Road / LB-01 in Giri torm water infrastructure ank-SPD) thale Main Canal CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/NCB/056 / Filling pot h ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 ole and gravelling along LB IBRD / 89960 Post Open - National nt - 1 Envelope 25,000.00 0.00 plementa tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -30 06 canal off D04 canal in G process (Non B tion torm water infrastructure alamuna scheme in Minneri ank-SPD) ya division CRESMPA-1/RP/WORKS/ID- National Procur POL/NCB/058 / Gravelling t Component 5: Improving c ement Docume Under Im o canal bund from 7+000 t limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 18,490.00 0.00 plementa o 7+332 of RB 1/ D02 main tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -30 process (Non B tion canal and from 0+000 to 1 torm water infrastructure ank-SPD) +132 of LB05 /RB01 D02 m ain canal in PSS in Polonnar uwa Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume POL/RFQ/106 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 IBRD / 89960 Post Limited nt - 1 Envelope 21,666.67 0.00 Canceled ts to D - 2A canal in Sahan tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B a DCO area in HLBC1 torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/059 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 plementa nts to FC 32 canal in Pragat tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -28 process (Non B tion hi DCO area in Kaudulla Div torm water infrastructure ank-SPD) ision National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/111 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 63,066.67 0.00 plementa nts of D2/6 in D06 canal in tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -28 process (Non B tion Giritale scheme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/NCB/127 / Constructio ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 n of canal lining at 0+057 t IBRD / 89960 Post Open - National nt - 1 Envelope 24,246.67 0.00 plementa tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -30 o 0+289 in D31/FC 17 cana process (Non B tion torm water infrastructure l in Kusumpokuna DCO are ank-SPD) a in Minneriya Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/060 / Filling potho limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2024-07 IBRD / 89960 Post Open - National nt - 1 Envelope 27,333.33 0.00 plementa les and gravelling along in tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -30 process (Non B tion LB/03 FC02 off LB03 & FC0 torm water infrastructure ank-SPD) 3 off LB03 in D04 canal CRESMPA-1/RP/WORKS/ID- POL/NCB/061 / Demolished existing hume pipe culvert National Procur Component 5: Improving c & construction of 11.4m lo ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 ng box culvert at stn. 0+60 IBRD / 89960 Post Open - National nt - 1 Envelope 17,966.67 0.00 plementa tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -30 0, construction of 27m long process (Non B tion torm water infrastructure rectangular canal lining & 8 ank-SPD) m long box cunvert at stn. 0+750 & construction of 6 m long wall and 6m long bo x culvert at stn. 0+820 CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/NCB/062 / Constructio ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2024-08 n of 197m long canal lining IBRD / 89960 Post Open - National nt - 1 Envelope 36,666.67 0.00 plementa tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -08 from stn.0+036 to 0+194 a process (Non B tion torm water infrastructure nd stn 0+195 to 0+234 in ank-SPD) LB6 canal off D2 main cana l in PSS National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/070 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 22,666.67 0.00 plementa nts to FC - 01 canal in Govi tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -30 process (Non B tion setha DCO area in HLBC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/071 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 plementa on of LB11canal in D28/LB tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -28 process (Non B tion MC in Minneriya Division torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/NCB/075 / Constructio ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 n of conc. Lining from 0+1 IBRD / 89960 Post Open - National nt - 1 Envelope 36,666.67 0.00 plementa tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -28 40 to 0+290 of LB 01 FC / process (Non B tion torm water infrastructure D05 / RB-01 in Girithale Mai ank-SPD) n Canal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/130 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 9,633.33 0.00 plementa nts to LB09 in D6 canal in tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -30 process (Non B tion Girithale Scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/136 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 42,953.33 0.00 plementa nts of D 12 canal from 0+4 tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -30 process (Non B tion 75 to 0+940 in Giritale sch torm water infrastructure ank-SPD) eme in Minneriya Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/079 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 36,033.33 0.00 plementa nts of RB2/7 in D 07 canal i tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -30 process (Non B tion n Giritale scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/139 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 24,160.00 0.00 plementa nts to Erige oya bund and a tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -30 process (Non B tion ccess road in Erige oya sch torm water infrastructure ank-SPD) eme in Minneriya division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/084 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 37,666.67 0.00 plementa n of U type canal lining for tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -28 process (Non B tion stn.0+044.4 to stn.0+134. torm water infrastructure ank-SPD) 4 Nilapitiya Batuhena D ca nal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/087 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 25,366.67 0.00 plementa nts of RB1/1 in D 07 canal i tenance of irrigation and s s e Envelope 19 21 19 29 29 03 -30 process (Non B tion n Giritale scheme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur POL/NCB/095 / Gravelling & Component 5: Improving c ement Docume Under Im bund forming of FC 09 & FC limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 18,133.33 0.00 plementa 11 canal bund road of LB 0 tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -30 process (Non B tion 1 of LBMC in Purana Janapa torm water infrastructure ank-SPD) daya DCFO area in Giritale scheme of Minneriya Divisi on National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/031-1 / Improve limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 18,546.67 0.00 Canceled ments to DC 8B,Weerawila tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B Scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/032 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 35,305.00 0.00 Canceled n of canal lining of CPO 35 f tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B rom 0+000 to 0+300 in W torm water infrastructure ank-SPD) RB scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/098 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 plementa nts to RB 5 canal in Kalinga tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -28 process (Non B tion DCO area in LLMC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/034-1 / Improve limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 29,683.33 0.00 Canceled ments to FC - 4 Gemunupu tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B ra main canal of Gemunup torm water infrastructure ank-SPD) ura Scheme in Tissa Divisio n National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/066 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 22,463.33 0.00 Canceled n of Retaining wall Bibilago tenance of irrigation and s tations e Envelope 20 14 -14 process (Non B da yaya torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/099 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 36,666.67 0.00 plementa nts of D 10 of RB 01 canal tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -28 process (Non B tion 0+000 to 0+435 in Giritale torm water infrastructure ank-SPD) scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume HAM/RFQ/069 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled n of feeder canal to Kalumu tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B ththa wewa torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/101 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 41,113.33 0.00 plementa n of 230 m long retaining w tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -28 process (Non B tion all at 1+550 in RB side in R torm water infrastructure ank-SPD) B 10 off D1 east canal CRESMPA-1/RP/WORKS/ID- POL/NCB/112 / Constructio n of the 18m long rectangu National Procur Component 5: Improving c lar canal lining at stn. 0+00 ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 0, demolished old damage IBRD / 89960 Post Open - National nt - 1 Envelope 21,666.67 0.00 plementa tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -30 existing hume pipe trough process (Non B tion torm water infrastructure structure & reconstruction ank-SPD) of 8m long rectangular trou gh structure at stn. 0+018 & construction 36m long re taining wall structure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/114 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 21,666.67 0.00 plementa nts to D - 1 canal in Samagi tenance of irrigation and s s e Envelope 19 14 19 29 29 03 -30 process (Non B tion DCO in LLMC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im HAM/NCB/031 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-04- 2024-05- 2024-07- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 18,546.67 0.00 plementa nts to DC 8B,Weerawila Sc tenance of irrigation and s s e Envelope 19 21 19 29 18 29 03 -30 process (Non B tion heme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/NCB/128 / Constructio ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 n of canal lining from stn. 3 IBRD / 89960 Post Open - National nt - 1 Envelope 21,666.67 0.00 plementa tenance of irrigation and s s e Envelope 19 17 19 29 29 03 -30 +400 to stn. 3+510 in B50 process (Non B tion torm water infrastructure 3 Sirikanduyaya Katuwa ca ank-SPD) nal in Sirikanduyaya DCFO area. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im HAM/NCB/032 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-04 IBRD / 89960 Post Open - National nt - 1 Envelope 35,305.00 0.00 plementa n of canal lining of CPO 35 f tenance of irrigation and s s e Envelope 19 23 19 29 29 03 -29 process (Non B tion rom 0+000 to 0+300 in W torm water infrastructure ank-SPD) RB scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/134 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 26,666.67 0.00 plementa nts to Trough structure at s tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -30 process (Non B tion tn. 2+770 in Ihakuluwewa torm water infrastructure ank-SPD) main canal (510 LB Canal) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I HAM/NCB/034 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 29,683.33 0.00 mplemen nts to FC - 4 Gemunupura tenance of irrigation and s s e Envelope 19 19 29 29 03 -30 process (Non B tation main canal of Gemunupura torm water infrastructure ank-SPD) Scheme in Tissa Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I HAM/NCB/066 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2024-10 IBRD / 89960 Post Open - National nt - 1 Envelope 22,463.33 0.00 mplemen n of Retaining wall Bibilago tenance of irrigation and s s e Envelope 19 19 29 29 03 -01 process (Non B tation da yaya torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I HAM/NCB/069 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen n of feeder canal to Kalumu tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 process (Non B tation ththa wewa torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MATR/RFQ/024 / Improvem limate resilience and main Request for Quo Limited - Nationa Single Stage - On 2024-02- 2024-04- 2025-04 IBRD / 89960 Post nt - 1 Envelope 41,333.33 0.00 mplemen ents to in denagama RB m tenance of irrigation and s tations l e Envelope 24 20 -15 process (Non B tation ain canal in Denagama sch torm water infrastructure ank-SPD) eme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MATR/RFQ/025 / Improvem limate resilience and main Request for Quo Limited - Nationa Single Stage - On 2024-02- 2024-04- 2024-10 IBRD / 89960 Post nt - 1 Envelope 17,000.00 0.00 mplemen ents to Sapugoda Katuimb tenance of irrigation and s tations l e Envelope 24 20 -17 process (Non B tation ula L/B main canal in Sapu torm water infrastructure ank-SPD) goda scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/135 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 36,430.00 0.00 plementa nts to FC 4 canal in Boowe tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -30 process (Non B tion wa scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/142 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 28,333.33 0.00 plementa n of canal spill at 29+290 i tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -30 process (Non B tion n D 37 in LBMC canal in Vih torm water infrastructure ank-SPD) aramawatha DCO area CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/NCB/143 / Improveme ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 nts to Elikibulawa (B 508) C IBRD / 89960 Post Open - National nt - 1 Envelope 20,000.00 0.00 plementa tenance of irrigation and s s e Envelope 19 22 19 29 29 03 -30 anal from stn. 2+100 to stn process (Non B tion torm water infrastructure . 2+760 in Elikibulawa DCF ank-SPD) O Area CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/NCB/148 / Improveme ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 nts to LB side bund of D1 e IBRD / 89960 Post Open - National nt - 1 Envelope 10,490.00 0.00 plementa tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -30 ast canal at 8+100 in D1 E process (Non B tion torm water infrastructure ast canal in Polonnaruwa Di ank-SPD) vision Page 8 CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c POL/NCB/153 / Demolishing ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 and New Constrction of 16 IBRD / 89960 Post Open - National nt - 1 Envelope 23,333.33 0.00 plementa tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -30 0 m long retaining wall fro process (Non B tion torm water infrastructure m 0+000 km to 0+160km ank-SPD) D17 /LBMC National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume COL/RFQ/008 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 18,750.00 0.00 Canceled n of retaining wall near Pall tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B ekumbura Anicut torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume COL/RFQ/071 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 Canceled nts to Muneta Bokkuwa in tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B Bodhiyawatta canal torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KAL/RFQ/015 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 Canceled ts to Kahaunage Ela MFP b tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B und (0+000 - 0+930) km a torm water infrastructure ank-SPD) nd Structure National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-04 KAL/RFQ/022 / Cleaing & I IBRD / 89960 Post Limited nt - 1 Envelope 18,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -27 mprovement egaloya ela process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KAL/RFQ/026 / Construction limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 Canceled of Agricultural road (From tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B walpita cemetry to Pabola) torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c RAT/RFQ/002 / Improveme ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-04 nts to RB Bank of the Rakw IBRD / 89960 Post Limited nt - 1 Envelope 18,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -27 ana Ganga from 0+125 to process (Non B torm water infrastructure 0+170 from Wellawa Anicu ank-SPD) t structure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume RAT/RFQ/010 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-04 IBRD / 89960 Post Limited nt - 1 Envelope 21,666.67 0.00 Canceled nts to canal section from 0 tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B +420 to 0+720 in D2 LBMC torm water infrastructure ank-SPD) in Kalthota scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume RAT/RFQ/012 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 17,333.33 0.00 Canceled n of canal lining in Paththa tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B duwela D Canal & FC 02 torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume RAT/RFQ/013 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-03 IBRD / 89960 Post Limited nt - 1 Envelope 17,000.00 0.00 Canceled n of Under crossing structu tenance of irrigation and s tations e Envelope 05 30 -28 process (Non B re at Saddathissa Main can torm water infrastructure ank-SPD) al to cross for Elephants National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume RAT/RFQ/022 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-04 IBRD / 89960 Post Limited nt - 1 Envelope 22,000.00 0.00 Canceled nts to FC02/D1/RBMC in Kal tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B thota scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume RAT/RFQ/032 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 28,333.33 0.00 Canceled nts of downstream of spill o tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B f Wewelanda Scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I COL/NCB/071 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 26,666.67 0.00 mplemen nts to Muneta Bokkuwa in tenance of irrigation and s s e Envelope 19 19 29 29 03 -30 process (Non B tation Bodhiyawatta canal torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KAL/NCB/015 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-02 IBRD / 89960 Post Open - National nt - 1 Envelope 23,333.33 0.00 Canceled nts to Kahaunage Ela MFP tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 process (Non B bund (0+000 - 0+930) km torm water infrastructure ank-SPD) and Structure National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-01 KAL/NCB/022 / Cleaing & I IBRD / 89960 Post Open - National nt - 1 Envelope 18,333.33 0.00 mplemen tenance of irrigation and s s e Envelope 19 19 29 29 03 -29 mprovement egaloya ela process (Non B tation torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KAL/NCB/026 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 26,666.67 0.00 mplemen n of Agricultural road (From tenance of irrigation and s s e Envelope 19 19 29 29 03 -30 process (Non B tation walpita cemetry to Pabola) torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c RAT/NCB/002 / Improveme ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-01 nts to RB Bank of the Rakw IBRD / 89960 Post Open - National nt - 1 Envelope 18,333.33 0.00 mplemen tenance of irrigation and s s e Envelope 19 19 29 29 03 -29 ana Ganga from 0+125 to process (Non B tation torm water infrastructure 0+170 from Wellawa Anicu ank-SPD) t structure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I RAT/NCB/010 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-01 IBRD / 89960 Post Open - National nt - 1 Envelope 21,666.67 0.00 mplemen nts to canal section from 0 tenance of irrigation and s s e Envelope 19 19 29 29 03 -29 process (Non B tation +420 to 0+720 in D2 LBMC torm water infrastructure ank-SPD) in Kalthota scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I RAT/NCB/012 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 17,333.33 0.00 mplemen n of canal lining in Paththa tenance of irrigation and s s e Envelope 19 19 29 29 03 -30 process (Non B tation duwela D Canal & FC 02 torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I RAT/NCB/013 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 17,000.00 0.00 mplemen n of Under crossing structu tenance of irrigation and s s e Envelope 19 19 29 29 03 -30 process (Non B tation re at Saddathissa Main can torm water infrastructure ank-SPD) al to cross for Elephants National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I RAT/NCB/022 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-01 IBRD / 89960 Post Open - National nt - 1 Envelope 22,000.00 0.00 mplemen nts to FC02/D1/RBMC in Kal tenance of irrigation and s s e Envelope 19 19 29 29 03 -29 process (Non B tation thota scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I RAT/NCB/032 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 28,333.33 0.00 mplemen nts of downstream of spill o tenance of irrigation and s s e Envelope 19 19 29 29 03 -30 process (Non B tation f Wewelanda Scheme torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MAN/RFQ/009 / Flood dama ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 ge reparing and improvem IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -11 enst to Kooramattai feeder process (Non B torm water infrastructure tanks Headwork under Viya ank-SPD) dikulam Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MAN/RFQ/014 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled nts to Periyaudaippu main tenance of irrigation and s tations e Envelope 20 14 -08 process (Non B canal under Periyaudaippu torm water infrastructure ank-SPD) sluice of GT Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MAN/RFQ/017 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled nts to Vanchiyankulam Spill tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B tail canal under 11th mile s torm water infrastructure ank-SPD) luice of GT Scheme CRESMPA-1/RP/WORKS/ID- National Procur MAN/RFQ/019 / Reconstruct Component 5: Improving c ement Docume ion of Turnout Structures fo limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 Canceled r Achankulam and Periveli tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B feeder tanks with road cros torm water infrastructure ank-SPD) sing under 12th Mile sluice of Giants Tank National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MAN/RFQ/021 / Reparing a limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled nd Improvements to Aalank tenance of irrigation and s tations e Envelope 20 14 -08 process (Non B ulam feeder canal under Ak torm water infrastructure ank-SPD) athimurippu Scheme CRESMPA-1/RP/WORKS/ID- National Procur MAN/RFQ/025 / Reconstruct Component 5: Improving c ement Docume ion of Trifurcation structure limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled along Muthalaikuththu - Uyi tenance of irrigation and s tations e Envelope 20 14 -08 process (Non B lankulam drainage path un torm water infrastructure ank-SPD) der Adaikkalamoddai Sluice of GT Scheme CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MAN/RFQ/028 / Improveme ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 nts and formation of Neduv IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -08 arampu feeder tank bund & process (Non B torm water infrastructure spill tail canal under Periya ank-SPD) udauppu sluice of GT Sche me CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MAN/RFQ/049 / Bund impro ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 vement, Sluice, Spill Constr IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -08 uction and canal cutting in process (Non B torm water infrastructure Periyamurippkulam of Muru ank-SPD) kan ASC CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MAN/RFQ/059 / Solaikkula ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 m tank bund improvement, IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -08 Sluice,Spill construction & process (Non B torm water infrastructure Canal cutting in P.P Potken ank-SPD) y ASC CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MAN/NCB/009 / Flood dama ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-02 ge reparing and improvem IBRD / 89960 Post Open - National nt - 1 Envelope 23,333.33 0.00 mplemen tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 enst to Kooramattai feeder process (Non B tation torm water infrastructure tanks Headwork under Viya ank-SPD) dikulam Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MAN/NCB/014 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen nts to Periyaudaippu main tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 process (Non B tation canal under Periyaudaippu torm water infrastructure ank-SPD) sluice of GT Scheme CRESMPA-1/RP/WORKS/ID- National Procur MAN/NCB/019 / Reconstruc Component 5: Improving c ement Docume Pending I tion of Turnout Structures f limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-02 IBRD / 89960 Post Open - National nt - 1 Envelope 23,333.33 0.00 mplemen or Achankulam and Periveli tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 process (Non B tation feeder tanks with road cro torm water infrastructure ank-SPD) ssing under 12th Mile sluic e of Giants Tank National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MAN/NCB/021 / Reparing a limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen nd Improvements to Aalank tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 process (Non B tation ulam feeder canal under Ak torm water infrastructure ank-SPD) athimurippu Scheme CRESMPA-1/RP/WORKS/ID- National Procur MAN/NCB/025 / Reconstruc Component 5: Improving c ement Docume Pending I tion of Trifurcation structur limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen e along Muthalaikuththu - tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 process (Non B tation Uyilankulam drainage path torm water infrastructure ank-SPD) under Adaikkalamoddai Slu ice of GT Scheme CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MAN/NCB/028 / Improveme ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 nts and formation of Neduv IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 arampu feeder tank bund & process (Non B tation torm water infrastructure spill tail canal under Periya ank-SPD) udauppu sluice of GT Sche me CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MAN/NCB/049 / Bund impro ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 vement, Sluice, Spill Constr IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 uction and canal cutting in process (Non B tation torm water infrastructure Periyamurippkulam of Muru ank-SPD) kan ASC National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MAN/NCB/053 / Formation limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2024-10 IBRD / 89960 Post Open - National nt - 1 Envelope 6,666.67 0.00 mplemen of Agri road In Sinnakankan tenance of irrigation and s s e Envelope 19 19 29 29 03 -01 process (Non B tation kulam - Periyakankankulam torm water infrastructure ank-SPD) road of Uyilankulam ASC National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 BAT/RFQ/019 / Desiting of IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -10 Mahiladitheevu Kulam process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAT/RFQ/023 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled n of Retaining wall & Impro tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B vements to Anicut cum brid torm water infrastructure ank-SPD) ge Manalpitty Anicut National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 BAT/NCB/019 / Desiting of IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 plementa tenance of irrigation and s s e Envelope 19 12 19 29 29 03 -30 Mahiladitheevu Kulam process (Non B tion torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im BAT/NCB/023 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 plementa n of Retaining wall & Impro tenance of irrigation and s s e Envelope 19 12 19 29 29 03 -30 process (Non B tion vements to Anicut cum brid torm water infrastructure ank-SPD) ge Manalpitty Anicut National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MUL/RFQ/001 / Restoring Fl limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-01 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled ood Damage Embankment tenance of irrigation and s tations e Envelope 20 14 -09 process (Non B of Vavunikkulam Canal Agri torm water infrastructure ank-SPD) cultural Road, Vavunikkula m CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MUL/RFQ/002 / Restoring Fl ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-01 ood Damage Embankment IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -09 of Madawalasingam Canal process (Non B torm water infrastructure Agricultural Road, Madawal ank-SPD) asingam National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MUL/RFQ/003 / Restoring Fl limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-01 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled ood Damage Embankment tenance of irrigation and s tations e Envelope 20 14 -09 process (Non B of Udayarkaddu Canal Agri torm water infrastructure ank-SPD) cultural Road, Udayarkadd u CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MUL/RFQ/004 / Restoring Fl ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-01 ood Damage Embankment IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -09 of Muththayankaddu Canal process (Non B torm water infrastructure Agricultural Road, Muththa ank-SPD) yankaddu National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MUL/RFQ/005 / Restoring Fl limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-01 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled ood Damage Embankment tenance of irrigation and s tations e Envelope 20 14 -09 process (Non B of Kalvilan Canal Agricultur torm water infrastructure ank-SPD) al Road, Kalvilan Tank CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MUL/RFQ/006 / Restoring Fl ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-01 ood Damage Embankment IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -09 of Ampalaperumal Canal A process (Non B torm water infrastructure gricultural Road, Ampalap ank-SPD) erumal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MUL/RFQ/008 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-01 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled on of Idaikaddukulam in Pu tenance of irrigation and s tations e Envelope 20 14 -09 process (Non B thukudiyiruppu ASC Divisio torm water infrastructure ank-SPD) n National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MUL/RFQ/009 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-01 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled on of Thachchadampan Ta tenance of irrigation and s tations e Envelope 20 14 -09 process (Non B nk in Olumadu ASC Division torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MUL/RFQ/010 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 Canceled on of Chalampankulam in tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B Padiyamkulam ASC Divisio torm water infrastructure ank-SPD) n National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MUL/RFQ/012 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 IBRD / 89960 Post Limited nt - 1 Envelope 23,333.33 0.00 Canceled on of Sinnathekilankulam i tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B n Padiyamkulam ASC Divisi torm water infrastructure ank-SPD) on National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MUL/RFQ/013 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 Canceled on of Siththandimurippukul tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B am under in Olumadu ASC torm water infrastructure ank-SPD) Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MUL/NCB/001 / Restoring Fl limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen ood Damage Embankment tenance of irrigation and s s e Envelope 19 19 29 29 03 -01 process (Non B tation of Vavunikkulam Canal Agri torm water infrastructure ank-SPD) cultural Road, Vavunikkula m CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MUL/NCB/002 / Restoring Fl ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 ood Damage Embankment IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen tenance of irrigation and s s e Envelope 19 19 29 29 03 -01 of Madawalasingam Canal process (Non B tation torm water infrastructure Agricultural Road, Madawal ank-SPD) asingam National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MUL/NCB/003 / Restoring Fl limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen ood Damage Embankment tenance of irrigation and s s e Envelope 19 19 29 29 03 -01 process (Non B tation of Udayarkaddu Canal Agri torm water infrastructure ank-SPD) cultural Road, Udayarkadd u CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MUL/NCB/004 / Restoring Fl ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 ood Damage Embankment IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen tenance of irrigation and s s e Envelope 19 19 29 29 03 -01 of Muththayankaddu Canal process (Non B tation torm water infrastructure Agricultural Road, Muththa ank-SPD) yankaddu National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MUL/NCB/005 / Restoring Fl limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen ood Damage Embankment tenance of irrigation and s s e Envelope 19 19 29 29 03 -01 process (Non B tation of Kalvilan Canal Agricultur torm water infrastructure ank-SPD) al Road, Kalvilan Tank CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MUL/NCB/006 / Restoring Fl ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 ood Damage Embankment IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen tenance of irrigation and s s e Envelope 19 19 29 29 03 -01 of Ampalaperumal Canal A process (Non B tation torm water infrastructure gricultural Road, Ampalap ank-SPD) erumal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MUL/NCB/008 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen on of Idaikaddukulam in Pu tenance of irrigation and s s e Envelope 19 19 29 29 03 -01 process (Non B tation thukudiyiruppu ASC Divisio torm water infrastructure ank-SPD) n National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MUL/NCB/009 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen on of Thachchadampan Ta tenance of irrigation and s s e Envelope 19 19 29 29 03 -01 process (Non B tation nk in Olumadu ASC Division torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MUL/NCB/010 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-02 IBRD / 89960 Post Open - National nt - 1 Envelope 23,333.33 0.00 mplemen on of Chalampankulam in tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 process (Non B tation Padiyamkulam ASC Divisio torm water infrastructure ank-SPD) n National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MUL/NCB/012 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-02 IBRD / 89960 Post Open - National nt - 1 Envelope 23,333.33 0.00 mplemen on of Sinnathekilankulam i tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 process (Non B tation n Padiyamkulam ASC Divisi torm water infrastructure ank-SPD) on Page 9 National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume VAV/RFQ/011 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 18,933.33 0.00 Canceled nts to FC - 08 A canal at Mu tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B hathankulam torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume VAV/RFQ/015 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 IBRD / 89960 Post Limited nt - 1 Envelope 24,033.33 0.00 Canceled nts to LB main canal at Raj tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B endrankulam torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I VAV/NCB/011 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 18,933.33 0.00 mplemen nts to FC - 08 A canal at Mu tenance of irrigation and s s e Envelope 19 19 29 29 03 -30 process (Non B tation hathankulam torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I VAV/NCB/015 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-02 IBRD / 89960 Post Open - National nt - 1 Envelope 24,033.33 0.00 mplemen nts to LB main canal at Raj tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 process (Non B tation endrankulam torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KILI/RFQ/012 / Reconstructi limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-01 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled on of LR anicut in Kilinochc tenance of irrigation and s tations e Envelope 20 14 -09 process (Non B hi ASC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KILI/RFQ/014 / Construction limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 Canceled of Kariyampiddykulam RB tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B & LB channel in Poonagary torm water infrastructure ank-SPD) ASC National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KILI/RFQ/015 / Construction limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled of Puthulyankulam Main Ch tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B annel I & II in kilinochchi AS torm water infrastructure ank-SPD) C National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KILI/RFQ/016 / Construction limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 30,000.00 0.00 Canceled Of Maniyankulam RB & LB tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B channel in Akkarayankulam torm water infrastructure ank-SPD) ASC National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KILI/NCB/012 / Reconstructi limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen on of LR anicut in Kilinochc tenance of irrigation and s s e Envelope 19 19 29 29 03 -01 process (Non B tation hi ASC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KILI/NCB/014 / Construction limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 26,666.67 0.00 mplemen of Kariyampiddykulam RB tenance of irrigation and s s e Envelope 19 19 29 29 03 -30 process (Non B tation & LB channel in Poonagary torm water infrastructure ank-SPD) ASC National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KILI/NCB/015 / Construction limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-01 IBRD / 89960 Post Open - National nt - 1 Envelope 20,000.00 0.00 mplemen of Puthulyankulam Main Ch tenance of irrigation and s s e Envelope 19 19 29 29 03 -29 process (Non B tation annel I & II in kilinochchi AS torm water infrastructure ank-SPD) C National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KILI/NCB/016 / Construction limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-04 IBRD / 89960 Post Open - National nt - 1 Envelope 30,000.00 0.00 mplemen Of Maniyankulam RB & LB tenance of irrigation and s s e Envelope 19 19 29 29 03 -29 process (Non B tation channel in Akkarayankulam torm water infrastructure ank-SPD) ASC National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KILI/NCB/019 / Construction limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2024-10 IBRD / 89960 Post Open - National nt - 1 Envelope 23,333.33 0.00 Canceled of thiuakamkulam RB & LB tenance of irrigation and s s e Envelope 19 19 29 29 03 -31 process (Non B channel torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID-J Component 5: Improving c ement Docume AF/RFQ/001 / Rehabilitation limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled of Kappothu - Vatharavatht tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B hai Flood Protection band torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID-J Component 5: Improving c ement Docume AF/RFQ/002 / Rehabilitation limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2025-02 IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 Canceled of Semani - Kopay flood pro tenance of irrigation and s tations e Envelope 20 14 -08 process (Non B tection bund torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID-J ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 AF/RFQ/004 / Rehabilitation IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -10 of Kantharodai Tank process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID-J Component 5: Improving c ement Docume Pending I AF/NCB/001 / Rehabilitation limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-04 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen of Kappothu - Vatharavatht tenance of irrigation and s s e Envelope 19 19 29 29 03 -29 process (Non B tation hai Flood Protection band torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID-J Component 5: Improving c ement Docume Pending I AF/NCB/002 / Rehabilitation limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 mplemen of Semani - Kopay flood pro tenance of irrigation and s s e Envelope 19 19 29 29 03 -28 process (Non B tation tection bund torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID-J ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-04 AF/NCB/004 / Rehabilitation IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 mplemen tenance of irrigation and s s e Envelope 19 19 29 29 03 -29 of Kantharodai Tank process (Non B tation torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MON/RFQ/029 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled on of FC 02 in LBMC in LB t tenance of irrigation and s tations e Envelope 05 30 -25 process (Non B ank in Mahawewa torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MON/RFQ/032 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled on of FC 01 RBMC in LB Ka tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B ndiyapitiya tank torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/029 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 33,333.33 0.00 plementa on of FC 02 in LBMC in LB t tenance of irrigation and s s e Envelope 19 19 19 29 29 03 -01 process (Non B tion ank in Mahawewa torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/032 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-02- 2024-04- 2024-05- 2024-07- 2025-02 IBRD / 89960 Post Open - National nt - 1 Envelope 20,000.00 0.00 plementa on of FC 01 RBMC in LB Ka tenance of irrigation and s s e Envelope 19 19 19 29 29 03 -28 process (Non B tion ndiyapitiya tank torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-09 KAD/RFQ/013 / Rehabilitati IBRD / 89960 Post Limited nt - 1 Envelope 18,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -11 on of Araththana Uda Ela process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KAD/NCB/012 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 16,666.67 0.00 mplemen on of Thelaginalla anicut & tenance of irrigation and s s e Envelope 19 19 29 29 03 -30 process (Non B tation canal torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-03- 2024-04- 2024-06- 2025-05 POL/NCB/154 / Rehabilitati IBRD / 89960 Post Open - National nt - 1 Envelope 83,333.33 0.00 Canceled tenance of irrigation and s s e Envelope 11 16 29 28 02 -28 on of Wettinakaadu Anicut process (Non B torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-03- 2024-04- 2024-05- 2024-06- 2025-06 POL/NCB/155 / Rehabilitati IBRD / 89960 Post Open - National nt - 1 Envelope 40,000.00 0.00 Canceled tenance of irrigation and s s e Envelope 28 04 15 15 19 -14 on of Meeranmeli Anicut process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/154-1 / Rehabilita limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 73,527.76 0.00 plementa tion of Wettakadu Anicut in tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -28 process (Non B tion Pulasthigama ASC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/155-1 / Repairing limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-04- 2024-02- 2024-04- 2024-05- 2024-07- 2025-06 IBRD / 89960 Post Open - National nt - 1 Envelope 36,690.43 0.00 plementa of Anicut and Construction tenance of irrigation and s s e Envelope 19 15 19 29 29 03 -28 process (Non B tion of Retaining wall at Meeran torm water infrastructure ank-SPD) weli Anicut Sewagama ASC SLMOI/CRES/ID/W/FA/34 / I Component 1: Forecasting Other (with fiel Pending I 100,000.0 2024-03- 2024-03- 2024-04- 2024-10 mprovements to the Hydra IBRD / 89960 and Early Warning of High Post Direct Selection Direct - National d for explanatio 0.00 mplemen 0 17 22 26 -23 ulics Research Lab of the Ir Impact Weather, Floods an n) tation rigation Department d Landslides National Procur SLOMI/CRES/DOM/W/NCB/ Component 1: Forecasting ement Docume Pending I 33 / Refurbishment of Offic and Early Warning of High Request for Bid Single Stage - On 1,690,000. 2024-05- 2024-05- 2024-07- 2024-08- 2024-09- 2026-03 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 mplemen e Premises of 20 Regional Impact Weather, Floods an s e Envelope 00 01 01 10 09 13 -07 process (Non B tation Offices of the Department d Landslides ank-SPD) of Meteorology National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume PUT/RFQ/034 / Reconstructi limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 Canceled on of damaged drop struct tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B ures & box culvert (D1-Tr.0 torm water infrastructure ank-SPD) 5) in Ingnimitiya LBMC SLMOI/CRES/ID/W/NCB/04 / National Procur Development of Flood Moni Component 1: Forecasting ement Docume toring and Operation Cente and Early Warning of High Request for Bid Single Stage - On 520,000.0 2023-12- 2023-12- 2024-01- 2024-01- 2024-03- 2024-09 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 Canceled r coupled with CCTV Flood Impact Weather, Floods an s e Envelope 0 15 20 10 25 14 -10 process (Non B Level Monitoring System at d Landslides ank-SPD) Hydrology & Disaster Mana gement Division National Procur SLMOI/CRES/DMC/W/NCB/0 Component 1: Forecasting ement Docume Request for Bid Single Stage - On 400,000.0 2023-12- 2023-12- 2024-01- 2024-02- 2024-03- 2024-06 8 / Refurbishment of EOC a IBRD / 89960 and Early Warning of High Post Open - National nt - 1 Envelope 0.00 Canceled s e Envelope 0 15 20 10 09 22 -20 t Disaster Management Ce Impact Weather, Floods an process (Non B ntre d Landslides ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c GAL/DC/045 / Construction Other (with fiel limate resilience and main 2023-07- 2023-08- 2023-09- 2023-12 of Bogawelayaya canal, im IBRD / 89960 Post Direct Selection Direct - National d for explanatio 3,333.33 0.00 Canceled tenance of irrigation and s 31 05 09 -08 provement of canal banks n) torm water infrastructure and connecting to Lenagala main canal CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel GAL/DC/059 / Construction limate resilience and main 2023-12- 2023-12- 2024-01- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 5,000.00 0.00 Canceled of Kirinuge canal and impro tenance of irrigation and s 15 20 24 -23 n) vement of canal banks torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I GAM/DC/017 / Concrete lini limate resilience and main 2024-03- 2024-04- 2024-05- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 24,166.67 0.00 mplemen ng from 2+100m to 2+150 tenance of irrigation and s 29 08 18 -15 n) tation m of left bank main canal o torm water infrastructure f Kinigama anicut CRESMPA-1/RP/WORKS/ID- National Procur AMP/NCB/024 / Reconstruct Component 5: Improving c ement Docume Pending I ion of Kythiyadi regulator c limate resilience and main Request for Bid Single Stage - On 2024-03- 2024-04- 2024-05- 2024-05- 2024-06- 2024-10 IBRD / 89960 Post Open - National nt - 1 Envelope 22,460.00 0.00 mplemen um bridge stucture includin tenance of irrigation and s s e Envelope 29 03 03 17 21 -19 process (Non B tation g construction of boulder p torm water infrastructure ank-SPD) acking rip rap at both side i n upper Weerayadi unit CRESMPA-1/RP/WORKS/ID- National Procur AMP/RFQ/024 / Improveme Component 5: Improving c ement Docume nts to D/S of Kythiyadi regu limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 22,460.00 0.00 Canceled lator cum Bridge Structure tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B including construction of b torm water infrastructure ank-SPD) older Packing Rip Rap at bo th side In Upper weerayadi Unit CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c AMP/RFQ/063 / Tank Bund ement Docume limate resilience and main Request for Quo Single Stage - On 2023-11- 2024-01- 2024-10 Repair L = 1150m IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 Canceled tenance of irrigation and s tations e Envelope 25 20 -16 Repair of sluice (02Nos) process (Non B torm water infrastructure Repair of main channel 2.2 ank-SPD) km CRESMPA-1/RP/WORKS/ID- National Procur AMP/RFQ/077 / Constructio Component 5: Improving c ement Docume n of RB-36 Drainage canal limate resilience and main Request for Quo Single Stage - On 2023-11- 2024-01- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled and construction of 4.0m s tenance of irrigation and s tations e Envelope 25 20 -17 process (Non B pan box type culvert at ST torm water infrastructure ank-SPD) N 3+665 in Thillaiaru Branc h canal in Akkaraipatthu CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c ANU/RFQ/006 / Constructio ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 n of channel spill in Mahaw IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -24 ilachchiya RB main canal B process (Non B torm water infrastructure reached section at 5+ 650k ank-SPD) m in Anuradhapura National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume ANU/RFQ/011 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 20,033.33 0.00 Canceled nts to spill structure of Thir tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B appankadawala tank in Hur torm water infrastructure ank-SPD) uluwewa Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume ANU/RFQ/023 / Rehabilitati limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 46,200.00 0.00 Canceled on of FC05 Canal at LB slui tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B ce in Thuruwila in Nachcha torm water infrastructure ank-SPD) duwa scheme CRESMPA-1/RP/WORKS/ID- National Procur ANU/RFQ/019 / Demolishin Component 5: Improving c ement Docume g & re-construction of Bala limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled yawewa Regulator includin tenance of irrigation and s tations e Envelope 05 30 -27 process (Non B g casting & installation of s torm water infrastructure ank-SPD) teel gates in Upper Main Ca nal in Padaviya scheme. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume ANU/RFQ/034 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-09 IBRD / 89960 Post Limited nt - 1 Envelope 46,666.67 0.00 Canceled nts to CP canal in Halpanu tenance of irrigation and s tations e Envelope 05 30 -24 process (Non B ela anicut scheme in Anura torm water infrastructure ank-SPD) dhapura National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume ANU/RFQ/038 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 19,666.67 0.00 Canceled nts to D8 Road RBMC Hurul tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B uwewa scheme torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-07 BAD/RFQ/002 / Improveme IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 05 30 -26 nts of Aluth Ela Main Canal process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAD/RFQ/008 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 31,333.33 0.00 Canceled n of canal lining at 0+285 i tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B n Badulu oya main canal in torm water infrastructure ank-SPD) Badulu oya scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAD/RFQ/009 / Constructio limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 27,333.33 0.00 Canceled n of Canal lining at 0+320 tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B of main canal torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 BAD/RFQ/010 / Improveme IBRD / 89960 Post Limited nt - 2 Envelope 26,666.67 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -12 nts to FC 2/RBMC process (Non B torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAD/RFQ/011 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 36,000.00 0.00 Canceled nts to canal lining from 0+ tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B 000 to 7+500 in main cana torm water infrastructure ank-SPD) l National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAD/RFQ/045 / Concreating limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-06 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled 6 km of Avukana canal in U tenance of irrigation and s tations e Envelope 05 30 -26 process (Non B vathanna GN division torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume COL/RFQ/021 / Additional e limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-05 IBRD / 89960 Post Limited nt - 1 Envelope 37,500.00 0.00 Canceled stimate at Weniwelkola ne tenance of irrigation and s tations e Envelope 20 14 -14 process (Non B w anicut torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume GAM/RFQ/023-1 / Concrete limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-12 IBRD / 89960 Post Limited nt - 1 Envelope 34,400.00 0.00 Canceled lining of a 150 m long of th tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B e left bank main canal of T torm water infrastructure ank-SPD) ammita scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KAL/RFQ/023 / Constrution limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-09- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 34,333.33 0.00 Canceled of retainning wall in Ilukpat tenance of irrigation and s tations e Envelope 05 30 -25 process (Non B ha main road damage part torm water infrastructure ank-SPD) near Dewalaya National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume BAT/RFQ/024 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 Canceled nts to Downstream of Co - tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B Spill at Meiynkai Tank torm water infrastructure ank-SPD) Component 5: Improving c CRESMPA-1/RP/WORKS/ID- Other (with fiel limate resilience and main 2023-07- 2023-08- 2023-09- 2024-09 POL/DC/007 / Construction IBRD / 89960 Post Direct Selection Direct - National d for explanatio 26,666.67 0.00 Canceled tenance of irrigation and s 31 05 09 -03 of Thibiriela anicut n) torm water infrastructure CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel POL/DC/004 / Constrction o limate resilience and main 2023-12- 2023-12- 2024-01- 2025-01 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,666.67 0.00 Canceled f Spillway for Dambagahaul tenance of irrigation and s 15 20 24 -18 n) patha Tank torm water infrastructure National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume COL/NCB/008 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-01 IBRD / 89960 Post Open - National nt - 1 Envelope 18,750.00 0.00 Canceled n of retaining wall near Pall tenance of irrigation and s s e Envelope 19 19 29 29 03 -29 process (Non B ekumbura Anicut torm water infrastructure ank-SPD) SLMOI/CRES/DOM/W/NCB/ 32 / Refurbishment of Offic National Procur e Premises in the Head Offi Component 1: Forecasting ement Docume Pending I ce of the Department of Me and Early Warning of High Request for Bid Single Stage - On 1,260,000. 2024-05- 2024-05- 2024-06- 2024-06- 2024-07- 2025-04 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 mplemen teorology including NMC M Impact Weather, Floods an s e Envelope 00 20 25 15 29 20 -16 process (Non B tation ain Building, Auditorium, C d Landslides ank-SPD) onference Hall, Visitors Are a, Security Hut, Rest Room, and Internal Road Develop ment National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im AMP/NCB/092 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 16,666.67 0.00 plementa nts of Palliayadia main anic tenance of irrigation and s s e Envelope 12 08 14 05 12 31 -27 process (Non B tion ut in Karandaoya scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im ANU/NCB/034 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 35,780.00 0.00 plementa on of CP canal in Halpanuel tenance of irrigation and s s e Envelope 08 11 10 01 11 30 -26 process (Non B tion a Anicut Scheme in Anurad torm water infrastructure ank-SPD) hapura Division. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im ANU/NCB/032 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 19,766.67 0.00 plementa nts to FC34/D9/RBMC Hurul tenance of irrigation and s s e Envelope 09 11 11 02 09 30 -26 process (Non B tion uwewa scheme torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 BAD/NCB/002 / Improveme IBRD / 89960 Post Open - National nt - 1 Envelope 32,333.33 0.00 plementa tenance of irrigation and s s e Envelope 05 24 08 29 09 28 -24 nts of Aluth Ela Main Canal process (Non B tion torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im ANU/NCB/023 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 46,200.00 0.00 plementa on of FC05 Canal at LB slui tenance of irrigation and s s e Envelope 09 11 11 02 09 30 -26 process (Non B tion ce in Thuruwila in Nachcha torm water infrastructure ank-SPD) duwa scheme. Page 10 National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I KAL/NCB/023 / Constrution limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 34,333.33 0.00 mplemen of retainning wall in Ilukpat tenance of irrigation and s s e Envelope 09 11 02 09 30 -26 process (Non B tation ha main road damage part torm water infrastructure ank-SPD) near Dewalaya CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c HAM/NCB/035 / New constr ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-09 uction of Retaining wall at IBRD / 89960 Post Open - National nt - 1 Envelope 20,933.33 0.00 mplemen tenance of irrigation and s s e Envelope 09 11 02 12 31 -28 0+015 - 0+047,0+400 - 0 process (Non B tation torm water infrastructure +446,0+570 - 0+675 in RB ank-SPD) MC of Mandagala Tank National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im AMP/NCB/063 / Tank Bund limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 26,666.67 0.00 plementa Repair L = 1150m repair of tenance of irrigation and s s e Envelope 08 08 10 01 11 30 -26 process (Non B tion sluice (02Nos) repair of mai torm water infrastructure ank-SPD) n channel 2.2km National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume ANU/NCB/011 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 14,430.00 0.00 Canceled nts to spill structure Thirap tenance of irrigation and s s e Envelope 08 10 01 08 29 -25 process (Non B pankadawala Tank in Hurul torm water infrastructure ank-SPD) uwewa Division. CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c ANU/NCB/047 / Repairing t ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-09 ank bund, reconstruction of IBRD / 89960 Post Open - National nt - 1 Envelope 25,000.00 0.00 plementa tenance of irrigation and s s e Envelope 10 11 12 03 10 31 -28 RB sluice, replace LB sluice process (Non B tion torm water infrastructure gate and reconstruction of ank-SPD) spill in Medawachchiya National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im BAD/NCB/011 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 36,000.00 0.00 plementa nts to FC 24 in Dehigama S tenance of irrigation and s s e Envelope 05 24 08 29 06 25 -21 process (Non B tion cheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im BAD/NCB/008 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 31,333.33 0.00 plementa n of canal lining at 0+285 i tenance of irrigation and s s e Envelope 10 24 12 03 10 29 -25 process (Non B tion n Badulu oya main canal in torm water infrastructure ank-SPD) Badulu oya scheme National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 BAD/NCB/010 / Improveme IBRD / 89960 Post Open - National nt - 1 Envelope 26,666.67 0.00 plementa tenance of irrigation and s s e Envelope 10 24 12 03 10 29 -25 nts to FC 2/RBMC process (Non B tion torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur AMP/NCB/077 / Constructio Component 5: Improving c ement Docume Under Im n of RB-36 Drainage canal limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 20,000.00 0.00 plementa and construction of 4.0m s tenance of irrigation and s s e Envelope 08 08 10 01 08 27 -23 process (Non B tion pan box type culvert at ST torm water infrastructure ank-SPD) N 3+665 in Thillaiaru Branc h canal in Akkaraipatthu National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im BAD/NCB/009 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 27,333.33 0.00 plementa n of Canal lining at 0+320 tenance of irrigation and s s e Envelope 05 24 08 29 09 30 -26 process (Non B tion of main canal torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im ANU/NCB/041 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 23,116.67 0.00 plementa on of tank bund (500m), sl tenance of irrigation and s s e Envelope 05 11 08 29 09 30 -26 process (Non B tion uice and canal (100m) in G torm water infrastructure ank-SPD) alenbindunuwewa CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c ANU/NCB/019 / Demolishin ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 g & re-construction of Bala IBRD / 89960 Post Open - National nt - 1 Envelope 31,650.00 0.00 plementa tenance of irrigation and s s e Envelope 05 11 07 28 05 24 -20 yawewa Regulator includin process (Non B tion torm water infrastructure g casting & installation of s ank-SPD) teel gates in UMC in Padavi ya Scheme. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im ANU/NCB/006 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 36,596.67 0.00 plementa n of channel spill in Mahawi tenance of irrigation and s s e Envelope 05 11 08 29 09 30 -26 process (Non B tion lachchiya RB main canal Br torm water infrastructure ank-SPD) eached section at 5+ 650k m National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume ANU/NCB/038 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 19,666.67 0.00 Canceled nts to D8 canal road in RB tenance of irrigation and s s e Envelope 05 08 29 09 30 -26 process (Non B MC in Huruluwewa scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im BAT/NCB/024 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-03- 2024-04- 2024-05- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 plementa nts to Downstream of Co - tenance of irrigation and s s e Envelope 10 12 12 03 10 29 -25 process (Non B tion Spill at Meiynkai Tank torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im POL/NCB/156 / Repairing of limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 40,000.00 0.00 plementa anicut and construction of r tenance of irrigation and s s e Envelope 10 22 12 03 10 31 -27 process (Non B tion etaining wall at Soalayaru torm water infrastructure ank-SPD) Anicut Medirigiriya ASC CRESMPA-1/RP/WORKS/ID- Component 5: Improving c AMP/DC/041-1 / Improveme Other (with fiel Pending I limate resilience and main 2024-04- 2024-04- 2024-04- 2024-11 nts to breached section of IBRD / 89960 Post Direct Selection Direct - National d for explanatio 44,966.67 0.00 mplemen tenance of irrigation and s 06 08 19 -15 Andaloya river in Poochchu n) tation torm water infrastructure kudi at stn 2+520 in Weera goda unit CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c AMP/NCB/111 / Renovation ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-12 of Tank Bund L = 800m an IBRD / 89960 Post Open - National nt - 1 Envelope 30,000.00 0.00 mplemen tenance of irrigation and s s e Envelope 10 12 03 10 31 -27 d Improvement of sluice (0 process (Non B tation torm water infrastructure 2 Nrs), Improvement of Mai ank-SPD) n Channel L = 400m CRESMPA-1/RP/WORKS/ID- PUT/NCB/005 / 100m Concr National Procur Component 5: Improving c ete retaining wall from 4 + ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 232 to 4 + 332 and constru IBRD / 89960 Post Open - National nt - 1 Envelope 47,930.00 0.00 mplemen tenance of irrigation and s s e Envelope 05 08 29 09 28 -24 ction of Drainage under cro process (Non B tation torm water infrastructure ssing structure at 4+450 in ank-SPD) downstream of syphon stru cture in RB main canal in T abbowa Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/NCB/013-1 / Improvem limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 67,800.00 0.00 mplemen ent to Kuda wewa Kadupiti tenance of irrigation and s s e Envelope 05 08 29 09 28 -24 process (Non B tation ya oya canal spill torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c PUT/NCB/016 / Removing o ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 f damaged trough structure IBRD / 89960 Post Open - National nt - 1 Envelope 25,910.00 0.00 mplemen tenance of irrigation and s s e Envelope 05 08 29 09 28 -24 and construction of new on process (Non B tation torm water infrastructure e @ 1st km in LBMC in Kott ank-SPD) ukachchiya Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/NCB/020 / Concrete ca limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 37,610.00 0.00 mplemen nal lining from 0 + 000 to 0 tenance of irrigation and s s e Envelope 04 07 28 08 27 -23 process (Non B tation +150 km in 3rd canal torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/NCB/023 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 29,300.00 0.00 mplemen nts to FC-09, D2 canal in Tr tenance of irrigation and s s e Envelope 05 08 29 09 28 -24 process (Non B tation .02 in Inginimitya RBMC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/NCB/026 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 25,010.00 0.00 mplemen nts to flood damaged in FC- tenance of irrigation and s s e Envelope 05 08 29 09 28 -24 process (Non B tation 16 canal in Tr.02 in Inginim torm water infrastructure ank-SPD) itiya RBMC National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I GAM/NCB/034 / Concrete li limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 32,670.00 0.00 mplemen ning from 1+500 to 1+760 tenance of irrigation and s s e Envelope 05 08 29 09 28 -24 process (Non B tation in left bank main canal of P torm water infrastructure ank-SPD) anugala scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im GAL/NCB/015 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 19,500.00 0.00 plementa nts to agricultural road fro tenance of irrigation and s s e Envelope 05 10 08 29 09 28 -24 process (Non B tion m Maliyagoda to Athumale torm water infrastructure ank-SPD) (3+340 km to 4+090 km) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c GAL/NCB/018 / Improveme ement Docume Under Im limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-11 nts to canal system & Cons IBRD / 89960 Post Open - National nt - 1 Envelope 17,415.00 0.00 plementa tenance of irrigation and s s e Envelope 05 10 08 29 09 28 -24 truction of pumping structu process (Non B tion torm water infrastructure re in Warahena paddy rese ank-SPD) arch center National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MATR/NCB/026 / Improvem limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-12 IBRD / 89960 Post Open - National nt - 1 Envelope 40,400.00 0.00 plementa ents to Heen ela Anicut (Re tenance of irrigation and s s e Envelope 05 10 08 29 09 28 -24 process (Non B tion novation of canal Spill) torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Under Im PUT/DC/021 / Improvement limate resilience and main 2023-10- 2023-04- 2023-10- 2023-05- 2023-11- 2024-05 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 16,666.67 0.00 plementa s to SD 2 canal in D2 canal tenance of irrigation and s 16 21 21 10 25 -23 n) tion of Radavi Bendi Ela Schem torm water infrastructure e National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MAN/NCB/047 / rmation of limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 2 Envelope 16,666.67 0.00 plementa Agri Road in Sinna Pulavuel tenance of irrigation and s s e Envelope 06 08 08 29 09 28 -24 process (Non B tion i - Sulthankulam road of Vi torm water infrastructure ank-SPD) dathaltheevu ASC National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 COL/NCB/021 / Rehabilitati IBRD / 89960 Post Open - National nt - 1 Envelope 81,341.00 0.00 mplemen tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 on of Weniwelkola anicut process (Non B tation torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MATR/RFQ/051 / Improvem limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 17,400.00 0.00 Canceled ents of Sadagankanda Anic tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B ut torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume PUT/RFQ/012 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 Canceled ts to damaged brick canal li tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B ning section in D2 (Tr.01 ) torm water infrastructure ank-SPD) canal of Ingirimitiya LBMC CRESMPA-1/RP/WORKS/ID- PUT/RFQ/005 / 100m Concr National Procur Component 5: Improving c ete retaining wall from 4 + ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 232 to 4 + 332 and constru IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled tenance of irrigation and s tations e Envelope 20 14 -10 ction of Drainage under cro process (Non B torm water infrastructure ssing structure at 4+450 in ank-SPD) dowunstream of sypon stru cture in RB main canal in T abbowa Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume PUT/RFQ/013 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-11 IBRD / 89960 Post Limited nt - 1 Envelope 53,333.33 0.00 Canceled t to kuda wewa Kadupitiya tenance of irrigation and s tations e Envelope 20 14 -10 process (Non B oya canal spill torm water infrastructure ank-SPD) CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c PUT/RFQ/016 / Removing of ement Docume limate resilience and main Request for Quo Single Stage - On 2023-08- 2023-10- 2024-07 damaged trough structure IBRD / 89960 Post Limited nt - 1 Envelope 26,666.67 0.00 Canceled tenance of irrigation and s tations e Envelope 20 15 -11 and construction of new on process (Non B torm water infrastructure e @ 1st km in LBMC in Kott ank-SPD) ukachchiya Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume PUT/RFQ/020 / Concrete ca limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 IBRD / 89960 Post Limited nt - 1 Envelope 16,666.67 0.00 Canceled nal lining from 0 + 000 to 0 tenance of irrigation and s tations e Envelope 20 14 -12 process (Non B +150 km in 3rd canal torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume PUT/RFQ/026 / Improvemen limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 IBRD / 89960 Post Limited nt - 1 Envelope 20,000.00 0.00 Canceled ts to flood damaged in FC - tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B 16 canal in Tr.02 in Inginim torm water infrastructure ank-SPD) itiya RBMC CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c GAL/RFQ/018 / Improveme ement Docume limate resilience and main Request for Quo Single Stage - On 2024-02- 2024-04- 2025-02 nts to canal system & Cons IBRD / 89960 Post Limited nt - 1 Envelope 9,000.00 0.00 Canceled tenance of irrigation and s tations e Envelope 12 08 -02 truction of pumping structu process (Non B torm water infrastructure re in Warahena paddy rese ank-SPD) arch center National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume GAL/RFQ/015 / Improveme limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-10 IBRD / 89960 Post Limited nt - 1 Envelope 19,616.67 0.00 Canceled nts to agricultural road fro tenance of irrigation and s tations e Envelope 20 14 -11 process (Non B m Maliyagoda to Athumale torm water infrastructure ank-SPD) (3+340 km to 4+090 km) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume TRI/RFQ/055 / Improvemen limate resilience and main Request for Quo Single Stage - On 2024-02- 2024-03- 2025-03 IBRD / 89960 Post Limited nt - 1 Envelope 33,333.33 0.00 Canceled ts to D2 off RB Main chann tenance of irrigation and s tations e Envelope 03 30 -25 process (Non B el 0+175 to 0+500 in Maha torm water infrastructure ank-SPD) kalanpaththu Irrigation sch eme CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c TRI/RFQ/054 / Improvemen ement Docume limate resilience and main Request for Quo Single Stage - On 2023-12- 2024-02- 2024-08 t to main channel and D1 c IBRD / 89960 Post Limited nt - 1 Envelope 50,000.00 0.00 Canceled tenance of irrigation and s tations e Envelope 19 13 -11 hannel 0+000m to 0+300 process (Non B torm water infrastructure m in Galmittiyawa Irrigatio ank-SPD) n scheme CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c TRI/NCB/054 / Improvemen ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 t to main channel and D1 c IBRD / 89960 Post Open - National nt - 1 Envelope 49,780.00 0.00 mplemen tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 hannel 0+000m to 0+300 process (Non B tation torm water infrastructure m in Galmittiyawa Irrigatio ank-SPD) n scheme. CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c TRI/NCB/055 / Improvemen ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 t to D2 off RB main channel IBRD / 89960 Post Open - National nt - 1 Envelope 33,320.00 0.00 mplemen tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 0+175m to 0+500 in Maha process (Non B tation torm water infrastructure kalampaththu Irrigation sch ank-SPD) eme. National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/NCB/010 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 16,670.00 0.00 mplemen n of Canal Lining from 2+2 tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 process (Non B tation 34km to 2+374km of Nelu torm water infrastructure ank-SPD) mgama main canal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I PUT/NCB/019 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 30,000.00 0.00 mplemen nts of canal section in FC - tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 process (Non B tation 2,FC - 3 (Tr - 3) canal RBMC torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im PUT/NCB/024 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 16,670.00 0.00 plementa nts to D3 canal from 0+70 tenance of irrigation and s s e Envelope 24 05 24 15 19 31 -27 process (Non B tion 0km in Radavi Bendi Ela Sc torm water infrastructure ank-SPD) heme CRESMPA-1/RP/WORKS/ID- National Procur COL/NCB/019 / Constructio Component 5: Improving c ement Docume Pending I n of regulator cum tractor c limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-08 IBRD / 89960 Post Open - National nt - 1 Envelope 38,350.00 0.00 mplemen rossing at 0+450 & Retaini tenance of irrigation and s s e Envelope 25 25 16 21 31 -29 process (Non B tation ng wall from 0+422 to 0+4 torm water infrastructure ank-SPD) 47 at both sides in Godaga ma Panagoda canal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I VAV/NCB/006 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 29,940.00 0.00 mplemen nts to LB - 02 canal off D-1 tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 process (Non B tation 5 canal off RB main canal a torm water infrastructure ank-SPD) t Pavatkulam National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I TRI/NCB/060 / Improvemen limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 41,370.00 0.00 mplemen ts of D4 Canal from Stn 0+ tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 process (Non B tation 000 to Stn 1+400 m Peram torm water infrastructure ank-SPD) aduwa Scheme National Procur CRESMPA/1/RP/WORKS/ID/ Component 5: Improving c ement Docume Under Im MON/NCB/069 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 20,000.00 0.00 plementa on of FC canal , Bund road tenance of irrigation and s s e Envelope 24 29 24 10 15 19 31 -27 process (Non B tion system at Demaliya schem torm water infrastructure ank-SPD) e National Procur CRESMPA/1/RP/WORKS/ID/ Component 5: Improving c ement Docume Under Im MON/NCB/071 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 33,340.00 0.00 plementa nts of Nagala Maha Wewa tenance of irrigation and s s e Envelope 24 30 24 15 19 31 -27 process (Non B tion and Kuda Wewa in Nagala torm water infrastructure ank-SPD) National Procur CRESMPA/1/RP/WORKS/ID/ Component 5: Improving c ement Docume Under Im MON/NCB/073 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 33,340.00 0.00 plementa on of Bediwewa Canal syst tenance of irrigation and s s e Envelope 24 30 24 15 19 31 -27 process (Non B tion em in Badiyawa torm water infrastructure ank-SPD) National Procur CRESMPA/1/RP/WORKS/ID/ Component 5: Improving c ement Docume Under Im MON/NCB/074 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-05- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 20,000.00 0.00 plementa on of Manarawana LBMC at tenance of irrigation and s s e Envelope 24 01 24 15 19 31 -27 process (Non B tion 2+400 to 4+200 torm water infrastructure ank-SPD) National Procur CRESMPA/1/RP/WORKS/ID/ Component 5: Improving c ement Docume Under Im MON/NCB/075 / Improveme limate resilience and main Request for Bid Single Stage - On 666,670.0 2024-04- 2024-05- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 plementa nts of syphon structure of tenance of irrigation and s s e Envelope 0 24 01 24 15 19 30 -26 process (Non B tion Handapanagala RBMC torm water infrastructure ank-SPD) National Procur CRESMPA/1/RP/WORKS/ID/ Component 5: Improving c ement Docume MON/NCB/084 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 30,000.00 0.00 Canceled n of 50m Canal lining from tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 process (Non B 5+892 to 5+942 in Badulu torm water infrastructure ank-SPD) oya Main Canal National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/102 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-05- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 50,000.00 0.00 plementa on of Main canal in Yudaga tenance of irrigation and s s e Envelope 24 01 24 15 19 31 -27 process (Non B tion nawa scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/103 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 100,000.0 2024-04- 2024-05- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 plementa on of Distributary Canal an tenance of irrigation and s s e Envelope 0 24 01 24 15 19 31 -27 process (Non B tion d Field Canals in Yudagana torm water infrastructure ank-SPD) wa Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/105 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-05- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 33,000.00 0.00 plementa nts in Spill parthway of Alu tenance of irrigation and s s e Envelope 24 01 24 15 19 31 -27 process (Non B tion galge tank torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/106 / Improveme limate resilience and main Request for Bid Single Stage - On 100,000.0 2024-04- 2024-05- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 plementa nts to Akkarawissa 20 feed tenance of irrigation and s s e Envelope 0 24 01 24 15 19 31 -27 process (Non B tion er canal torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 MON/NCB/110 / Rehabilitati IBRD / 89960 Post Open - National nt - 1 Envelope 26,670.00 0.00 mplemen tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 on of Morabedda anicut process (Non B tation torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MON/NCB/111 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 40,000.00 0.00 mplemen on of Morabedda Canal Sys tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 process (Non B tation tem torm water infrastructure ank-SPD) National Procur Component 5: Improving c CRESMPA-1/RP/WORKS/ID- ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 100,000.0 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 MON/NCB/112 / Repairs to IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 mplemen tenance of irrigation and s s e Envelope 0 24 24 15 19 31 -27 Dunumewa Tank process (Non B tation torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I MON/NCB/113 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 60,000.00 0.00 mplemen on of Dunumewa Canal Sys tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 process (Non B tation tem torm water infrastructure ank-SPD) Page 11 CRESMPA-1/RP/WORKS/ID- National Procur Component 5: Improving c MON/NCB/115 / Demolishin ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 g and Reconstruction of ac IBRD / 89960 Post Open - National nt - 1 Envelope 83,335.00 0.00 mplemen tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 cess road to wallicave with process (Non B tation torm water infrastructure embankment protection in ank-SPD) manik ganga CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Under Im GAL/DC/019 / Rehabilitatio limate resilience and main 2024-04- 2023-05- 2024-04- 2023-06- 2024-05- 2024-11 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 54,420.00 0.00 plementa n of Paththinigoda Bridge n tenance of irrigation and s 26 19 26 20 18 -14 n) tion ear Uthurupitigala Flood Bu torm water infrastructure nd CRESMPA/1/RP/WORKS/ID/ Component 5: Improving c Other (with fiel Pending I MON/DC/070 / Clearing Wat limate resilience and main 2024-04- 2024-04- 2024-05- 2024-11 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 83,335.00 0.00 mplemen er weeds in surface of Deta tenance of irrigation and s 26 26 18 -14 n) tation gamuwa tank torm water infrastructure National Procur SLMOI/CRES/ID/W/NCB/35 / Component 1: Forecasting ement Docume Under Im Renovation of the Office Bu and Early Warning of High Request for Bid Single Stage - On 204,700.0 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 plementa ilding of Hydraulics Resear Impact Weather, Floods an s e Envelope 0 25 22 25 16 21 31 -27 process (Non B tion ch Lab of the Irrigation Dep d Landslides ank-SPD) artment National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/090 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-05- 2024-04- 2024-05- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 29,400.00 0.00 plementa nts to tail end of LBMC in H tenance of irrigation and s s e Envelope 03 30 03 24 26 31 -27 process (Non B tion ambegamuwa scheme torm water infrastructure ank-SPD) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/093 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 33,935.00 0.00 plementa nts To Madippamulla D-Can tenance of irrigation and s s e Envelope 03 01 03 24 26 31 -27 process (Non B tion al 0+000 To 0+525 in Dehi torm water infrastructure ank-SPD) aththawela Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/095 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 21,970.00 0.00 plementa n of Canal Lining At 3+290 tenance of irrigation and s s e Envelope 03 01 03 24 26 31 -27 process (Non B tion to 3+360 LBMC in Dehiatht torm water infrastructure ank-SPD) hawela Scheme National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Under Im MON/NCB/107 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 27,500.00 0.00 plementa nt to Akkara 20, Canal syst tenance of irrigation and s s e Envelope 03 01 03 24 26 31 -27 process (Non B tion em torm water infrastructure ank-SPD) National Procur SLMOI/CRES/NBRO/W/NCB/ Component 1: Forecasting ement Docume Pending I 36 / Establishment of a Geo and Early Warning of High Request for Bid Single Stage - On 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 62,500.00 0.00 mplemen -spatial Processing and VR Impact Weather, Floods an s e Envelope 03 04 25 28 31 -27 process (Non B tation Unit for National Building R d Landslides ank-SPD) esearch Organization CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I GAL/DC/082 / Fabrication, P limate resilience and main 2024-05- 2024-05- 2024-05- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 55,000.00 0.00 mplemen ainting & Installation of 560 tenance of irrigation and s 06 11 28 -25 n) tation 0 mm x1500 mm Mild Steel torm water infrastructure Gate for Olanda Ela Anicuit CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I BAT/DC/026 / Fixing Gates limate resilience and main 2024-05- 2024-05- 2024-05- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 11,700.00 0.00 mplemen and Lifting Arrangements f tenance of irrigation and s 07 12 28 -25 n) tation or Vaikaladicenai Anicuit in torm water infrastructure Batticaloa National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MON/NCB/114 / Improveme limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 66,670.00 0.00 Canceled nts to canal system from M tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 process (Non B ailagama tank to Weherake torm water infrastructure ank-SPD) ma tank National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume MUL/NCB/013 / Rehabilitati limate resilience and main Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-07- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 26,666.67 0.00 Canceled on of Siththandimurippukul tenance of irrigation and s s e Envelope 19 19 29 29 03 -30 process (Non B am under in Olumadu ASC torm water infrastructure ank-SPD) Division National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume KILI/NCB/004 / Improving a limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2025-03 IBRD / 89960 Post Open - National nt - 1 Envelope 60,000.00 0.00 Canceled nd restoring the bund of Ku tenance of irrigation and s s e Envelope 15 20 31 01 05 -31 process (Non B damuruddy (Earth work, Ri torm water infrastructure ank-SPD) p-rap) National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume COL/NCB/017 / Constructio limate resilience and main Request for Bid Single Stage - On 2023-12- 2023-12- 2024-01- 2024-03- 2024-04- 2024-07 IBRD / 89960 Post Open - National nt - 1 Envelope 87,500.00 0.00 Canceled n of drain near Bogahawatt tenance of irrigation and s s e Envelope 15 20 31 01 05 -04 process (Non B a road and Shantha Anthon torm water infrastructure ank-SPD) i road at Weliwita National Procur SLMOI/CRES/ID/W/S/31 / R Component 1: Forecasting ement Docume Pending I Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-08 enovation of room no 417 o IBRD / 89960 and Early Warning of High Post nt - 1 Envelope 17,300.00 0.00 mplemen tations l e Envelope 08 29 -27 f the Irrigation Department Impact Weather, Floods an process (Non B tation - Head Office d Landslides ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I KAL/DC/015 / Improvement limate resilience and main 2024-05- 2024-05- 2024-05- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 9,700.00 0.00 mplemen s to Kahaunage Ela MFP bu tenance of irrigation and s 15 18 28 -25 n) tation nd (0+000 - 0+930) km an torm water infrastructure d Structure National Procur SLMOI/CRES/PCT/W/NCB/3 ement Docume Pending I Component 4: Project Man Request for Bid Single Stage - On 233,000.0 2024-05- 2024-05- 2024-06- 2024-06- 2024-06- 2024-10 7 / Improvements to the ex IBRD / 89960 Post Open - National nt - 1 Envelope 0.00 mplemen agement s e Envelope 0 17 18 08 13 14 -12 isting Office Building of CR process (Non B tation esMPA-PCT ank-SPD) CRESMPA-1/RP/WORKS/ID- Component 5: Improving c Other (with fiel Pending I GAM/DC/011 / Construction limate resilience and main 2024-05- 2024-05- 2024-06- 2024-09 IBRD / 89960 Post Direct Selection Direct - National d for explanatio 22,630.00 0.00 mplemen of canal lining of Ma ovita K tenance of irrigation and s 22 25 02 -30 n) tation BMC from 1+200km to 1+3 torm water infrastructure 55km in Panugala scheme CRESMPA-1/RP/WORKS/ID- GAM/NCB/009 / Widening a National Procur Component 5: Improving c nd gravelling of LBMC road ement Docume Pending I limate resilience and main Request for Bid Single Stage - On 2024-05- 2024-05- 2024-06- 2024-06- 2024-06- 2024-12 in Ma-Owita anicut in Dee-E IBRD / 89960 Post Open - National nt - 1 Envelope 53,000.00 0.00 mplemen tenance of irrigation and s s e Envelope 22 23 13 16 24 -21 li Oya from 0+000 to 0+40 process (Non B tation torm water infrastructure 0 and construction of canal ank-SPD) lining of Ma-Owita LBMC fro m 0+400 to 0+410 to prev ent scouring National Procur CRESMPA-1/RP/WORKS/ID- Component 5: Improving c ement Docume Pending I GAM/NCB/023 / Constructio limate resilience and main Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11 IBRD / 89960 Post Open - National nt - 1 Envelope 34,400.00 0.00 mplemen n of 150m long canal lining tenance of irrigation and s s e Envelope 24 24 15 19 31 -27 process (Non B tation for LBMC in Thammita Sche torm water infrastructure ank-SPD) me in Gampaha Division. GOODS Activity Reference No Estimated A Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati Actual Amou Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Completio . / Description Component Review Type Method mount (US$ ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) nt (US$) Status on Documents aluation Report as Issued n ) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d d d d d d SLMOI/CRES/ID/G/NCB/05 / Component 1: Forecasting Procurement of Computers and Early Warning of High Request for Bid Single Stage - On 2022-08- 2022-10- 2022-08- 2022-10- 2022-09- 2022-11- 2022-10- 2023-01- 2022-11- 2023-03- 2023-03- and UPS for Hydrology and IBRD / 89960 Post Open - National 52,000.00 0.00 Signed Impact Weather, Floods an s e Envelope 26 10 28 18 18 09 03 04 09 22 09 Disaster Management Divis d Landslides ion at Irrigational Departm ent SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting 02 / Procurement of IT and and Early Warning of High Request for Bid Single Stage - On 2022-10- 2022-10- 2022-10- 2022-11- 2023-01- 2022-12- 2023-07- 2023-01- 2023-09- 2023-05- IBRD / 89960 Post Open - National 203,500.00 0.00 Signed other related equipment an Impact Weather, Floods an s e Envelope 26 12 28 18 19 02 18 08 13 08 d High-end server for NBR d Landslides O SLMOI/CRES/ID/G/NCB/04 / Component 1: Forecasting Procurement of hydrologica and Early Warning of High Request for Bid Single Stage - On 2022-08- 2022-10- 2022-09- 2022-10- 2022-09- 2022-11- 2022-10- 2022-12- 2022-11- 2023-03- l measuring equipment and IBRD / 89960 Post Open - National 172,000.00 0.00 Canceled Impact Weather, Floods an s e Envelope 31 10 02 18 23 09 14 28 20 20 weather instruments for Hy d Landslides drology and Disaster Mana gement Division SLMOI/CRES/NBRO/G/S/03 Component 1: Forecasting / Procurement of Digital Pa and Early Warning of High Request for Quo Single Stage - On 2022-10- 2023-01- 2023-05- IBRD / 89960 Post Limited 35,500.00 0.00 Canceled nals for displaying ARG Sys Impact Weather, Floods an tations e Envelope 28 09 09 tem and other sensor netw d Landslides orks of NBRO SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting 03 / Procurement of Digital and Early Warning of High Request for Bid Single Stage - On 2022-10- 2022-10- 2022-10- 2022-12- 2023-01- 2023-01- 2023-05- 2023-02- 2023-06- 2023-06- 2023-07- IBRD / 89960 Post Open - National 70,000.00 0.00 Completed Panels for Displaying ARG S Impact Weather, Floods an s e Envelope 17 12 22 03 18 02 03 06 13 06 13 ystem and other Sensor Ne d Landslides tworks of NBRO SLMOI/CRES/NBRO/G/DS/0 Component 1: Forecasting Under Impl 2023-09- 2023-08- 2023-09- 2023-09- 2023-10- 2024-01- 8 / Procurement of ArcGIS P IBRD / 89960 and Early Warning of High Post Direct Selection Direct - National 22,800.00 0.00 ementatio 18 03 23 18 28 26 ro for the National Building Impact Weather, Floods an n Research Organisation d Landslides SLMOI/CRES/NBRO/G/S/06 Component 1: Forecasting / Procurement of office furn and Early Warning of High Request for Quo Single Stage - On 2022-10- 2022-12- 2023-04- IBRD / 89960 Post Limited 22,000.00 0.00 Canceled iture for Landslide Early Wa Impact Weather, Floods an tations e Envelope 02 14 13 rning Center at National Bu d Landslides ilding Research Organizatio n SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting Under Impl 09 / Upgrade and Maintena and Early Warning of High Request for Bid Single Stage - On 2023-10- 2023-12- 2023-10- 2023-12- 2023-12- 2024-01- 2024-01- 2024-04- 2024-02- 2024-05- IBRD / 89960 Post Open - National 695,000.00 0.00 ementatio nce of Automated Rain-Gua Impact Weather, Floods an s e Envelope 20 05 25 08 06 09 05 19 09 09 n ge Systems in 14 Landslide d Landslides Prone Districts SLMOI/CRES/ID/G/NCB/04- Component 1: Forecasting 2 / Procurement of Hydrolo Pending I and Early Warning of High Request for Bid Single Stage - On 2023-12- 2023-12- 2024-01- 2024-02- 2024-03- 2024-06- gical Measuring Equipment IBRD / 89960 Post Open - National 172,000.00 0.00 mplement Impact Weather, Floods an s e Envelope 22 24 14 04 12 10 and Weather Instruments f ation d Landslides or Hydrology and Disaster Management Division SLMOI/CRES/DOM/G/NCB/1 Component 1: Forecasting 5 / Procurement of ICT and Pending I and Early Warning of High Request for Bid Single Stage - On 2024-02- 2024-03- 2024-04- 2024-05- 2024-06- 2024-12- office equipment in the hea IBRD / 89960 Post Open - National 71,515.00 0.00 mplement Impact Weather, Floods an s e Envelope 29 05 16 16 20 17 d office and regional offices ation d Landslides of the department of Meteo rology SLMOI/CRES/ID/G/NCB/28 / Component 1: Forecasting Pending I Request for Bid Single Stage - On 2024-03- 2024-03- 2024-05- 2024-06- 2024-07- 2025-07- Procurement of Lab Equip IBRD / 89960 and Early Warning of High Post Open - National 680,000.00 0.00 mplement s e Envelope 11 11 20 19 24 24 ment for the Hydraulic Res Impact Weather, Floods an ation earch Laboratory d Landslides SLMOI/CRES/DOM/G/S/17 / Component 1: Forecasting Under Impl Procurement of office furnit and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-03- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post 44,000.00 0.00 ementatio ure lot 1: for the head offic Impact Weather, Floods an tations l e Envelope 20 09 15 11 n e and regional offices of th d Landslides e department of Meteorolo gy SLMOI/CRES/DOM/G/S/20 / Component 1: Forecasting Request for Quo Single Stage - On 2024-03- 2024-04- 2024-10- Upgrade of IBL system in th IBRD / 89960 and Early Warning of High Post Limited 16,665.00 0.00 Canceled tations e Envelope 05 30 27 e head office of the depart Impact Weather, Floods an ment of meteorology d Landslides SLOMI/CRES/DOM/G/NCB/2 Component 1: Forecasting 4 / Refurbishment of office and Early Warning of High Request for Bid Single Stage - On 2024-02- 2024-03- 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 500,000.00 0.00 Canceled premises of 23 regional offi Impact Weather, Floods an s e Envelope 29 05 16 16 20 17 ces of the department of d Landslides meteorology SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting Under Impl 14 / Supply and Installation and Early Warning of High Request for Bid Single Stage - On 2024-03- 2024-05- 2024-03- 2024-04- 2024-05- 2024-06- 2025-12- IBRD / 89960 Post Open - National 367,000.00 0.00 ementatio of 100 Nos of Automated R Impact Weather, Floods an s e Envelope 20 11 20 19 09 13 05 n ain-Gauge Systems in 14 L d Landslides andslide Prone Districts SLMOI/CRES/DOM/G/NCB/1 8 / procurement of Lot 1: h ydrogen generator for radi Component 1: Forecasting osonde balloon for head off and Early Warning of High Request for Bid Single Stage - On 2024-02- 2024-03- 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 269,700.00 0.00 Canceled ice, Lot 2: hydrogen genera Impact Weather, Floods an s e Envelope 29 05 16 16 20 17 tors for pilot balloons for re d Landslides gional offices, Lot 3: Procur ement of tools for Instrume nt division and electronic di vision in the head office of SLMOI/CRES/ID/G/NCB/24 the DOM / Component 1: Forecasting Procurement of ICT Equipm and Early Warning of High Request for Bid Single Stage - On 2024-03- 2024-03- 2024-04- 2024-05- 2024-06- 2024-12- ents for the Development o IBRD / 89960 Post Open - National 370,000.00 0.00 Canceled Impact Weather, Floods an s e Envelope 01 06 17 17 21 18 f MHEWS by upscaling the d Landslides MOBILISE Platform in Kalut hara District SLMOI/CRES/DOM/G/S/19 / Component 1: Forecasting Procurement of Private Aut Under Impl and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-03- 2024-05- 2024-11- omatic Branch Exchange (P IBRD / 89960 Post 6,700.00 0.00 ementatio Impact Weather, Floods an tations l e Envelope 27 22 18 ABX) System in the Head n d Landslides Office of the Department of Meteorology SLMOI/CRES/DOM/G/ICB/1 Component 1: Forecasting 8-1 / Supplying and Installi Under Impl and Early Warning of High Request for Bid Open - Internatio Single Stage - On 2024-03- 2024-04- 2024-03- 2024-04- 2024-04- 2024-05- 2024-06- 2025-12- ng Hydrogen Generators fo IBRD / 89960 Post 435,000.00 0.00 ementatio Impact Weather, Floods an s nal e Envelope 08 01 08 18 22 12 16 08 r Radiosonde Balloon and P n d Landslides ilot Balloons for the Depart ment of Meteorology, Sri La nka SLMOI/CRES/ID/G/DP/34 / Component 1: Forecasting Pending I Upgrading the available Ar and Early Warning of High 2024-03- 2024-04- 2024-05- 2024-08- IBRD / 89960 Post Direct Selection Direct - National 110,000.00 0.00 mplement cGIS licenses at the Irrigati Impact Weather, Floods an 27 01 06 04 ation on Department for ArcGIS P d Landslides ro SLMOI/CRES/DOM/G/NCB/1 Component 1: Forecasting Under Impl 6 / Installation of solar pow and Early Warning of High Request for Bid Single Stage - On 2024-03- 2024-03- 2024-03- 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 23,000.00 0.00 ementatio er systems in the head offi Impact Weather, Floods an s e Envelope 22 29 27 26 16 20 17 n ce of the Department of Me d Landslides teorology SLMOI/CRES/DOM/G/NCB/2 Component 1: Forecasting Under Impl 1 / Procurement of 02 Nos and Early Warning of High Request for Bid Single Stage - On 2024-03- 2024-03- 2024-04- 2024-05- 2024-06- 2024-10- IBRD / 89960 Post Open - National 234,000.00 0.00 ementatio of Outdoor Weather Displa Impact Weather, Floods an s e Envelope 22 27 26 16 20 18 n y for the Head Office of the d Landslides Department of Meteorology SLMOI/CRES/DOM/G/DP/20 Component 1: Forecasting Pending I / Upgrade of IBL System in and Early Warning of High Direct - Internati 2024-03- 2024-04- 2024-05- 2024-08- IBRD / 89960 Post Direct Selection 34,000.00 0.00 mplement the Head Office of the Dep Impact Weather, Floods an onal 29 08 18 16 ation artment of Meteorology d Landslides SLMOI/CRES/ID/G/NCB/11 / Component 1: Forecasting Pending I Purchasing 3 Nos of LiDAR and Early Warning of High Request for Bid Single Stage - On 2024-03- 2024-03- 2024-04- 2024-05- 2024-06- 2024-10- IBRD / 89960 Post Open - National 170,000.00 0.00 mplement Drones for Real-Time Flood Impact Weather, Floods an s e Envelope 29 31 30 15 19 17 ation Mapping Including Staff Tra d Landslides ining for Operations SLMOI/CRES/ID/G/NCB/32 / Supply and Installation of N Component 1: Forecasting Pending I ecessary Monitoring and Di and Early Warning of High Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11- IBRD / 89960 Post Open - National 540,000.00 0.00 mplement ssemination Equipment, IC Impact Weather, Floods an s e Envelope 10 12 03 10 29 25 ation T Systems and Civil Works f d Landslides or the Development of the Flood Monitoring and Oper ation Room SLMOI/CRES/DOM/G/ICB/2 Component 1: Forecasting Under Impl 3 / Supplying Digital Meteo and Early Warning of High Request for Bid Open - Internatio Single Stage - On 2024-04- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11- IBRD / 89960 Post 120,000.00 0.00 ementatio rological Theodolite for Dep Impact Weather, Floods an s nal e Envelope 03 05 06 17 21 27 31 27 n artment of Meteorology, Sri d Landslides Lanka SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting 10 / Upgrading Air and Rain Under Impl and Early Warning of High Request for Bid Single Stage - On 2024-04- 2024-03- 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-09- water Sensor Network for N IBRD / 89960 Post Open - National 1,000,000.00 0.00 ementatio Impact Weather, Floods an s e Envelope 05 19 08 29 09 09 30 27 on - regulatory Supplement n d Landslides al Informational Monitoring (NSIM) Applications in Sri L anka SLMOI/CRES/NBRO/G/NCG/ Component 1: Forecasting 07 / Procurement of office f Pending I and Early Warning of High Request for Bid Single Stage - On 2024-04- 2024-04- 2024-04- 2024-05- 2024-05- 2024-11- urniture for Landslide Early IBRD / 89960 Post Open - National 65,000.00 0.00 mplement Impact Weather, Floods an s e Envelope 05 08 29 06 27 23 Warning Center at National ation d Landslides Building Research Organiza tion SLMOI/CRES/ID/G/NCB/26 / Component 1: Forecasting Supply, Installation, Commi Pending I and Early Warning of High Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2025-01- ssioning & Testing of Auto IBRD / 89960 Post Open - National 740,000.00 0.00 mplement Impact Weather, Floods an s e Envelope 10 12 03 10 29 24 mated Real-Time Monitorin ation d Landslides g Stations in Major Reservo ir Schemes SLMOI/CRES/ID/G/NCB/25 / Component 1: Forecasting Supply and Installation of 1 Pending I and Early Warning of High Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11- 00 Hydrological Stations (in IBRD / 89960 Post Open - National 1,050,000.00 0.00 mplement Impact Weather, Floods an s e Envelope 10 12 03 10 29 25 cluding rainfall gauges whe ation d Landslides re necessary) for 27 River Basins SLMOI/CRES/PCT/G/S/35 / Component 1: Forecasting Pending I Request for Quo Limited - Nationa Single Stage - On 2024-04- 2024-04- 2024-05- Purchasing of a Financial M IBRD / 89960 and Early Warning of High Post 3,350.00 0.00 mplement tations l e Envelope 08 29 29 anagement Software Impact Weather, Floods an ation d Landslides SLMOI/CRES/DMC/G/S/37 / Component 1: Forecasting Under Impl Request for Quo Limited - Nationa Single Stage - On 2024-04- 2024-05- 2024-08- Procurement of 5kw Gener IBRD / 89960 and Early Warning of High Post 25,000.00 0.00 ementatio tations l e Envelope 26 31 29 ator for Disaster Managem Impact Weather, Floods an n ent Centre d Landslides SLMOI/CRES/DMC/G/NCB/3 8 / Procurement of Equipm Component 1: Forecasting ent (High Power Rechargea Under Impl and Early Warning of High Request for Bid Single Stage - On 2024-04- 2024-05- 2024-04- 2024-05- 2024-05- 2024-05- 2024-08- ble Torch, Safety Helments, IBRD / 89960 Post Open - National 100,000.00 0.00 ementatio Impact Weather, Floods an s e Envelope 24 02 24 15 20 31 29 Manila Ropes, Rescue Tube n d Landslides s and Emergency Lights) fo r controlling Emergency Sit uations in Sri Lanka for DM C SLMOI/CRES/DMC/G/S/39 / Component 1: Forecasting Under Impl Request for Quo Limited - Nationa Single Stage - On 2024-04- 2024-05- 2024-08- Procurement of First Aid Kit IBRD / 89960 and Early Warning of High Post 1,670.00 0.00 ementatio tations l e Envelope 30 30 28 s for the Disaster Managem Impact Weather, Floods an n ent Centre d Landslides SLMOI/CRES/DOM/G/NCB/3 Component 1: Forecasting 3 / Procurement of Tools fo and Early Warning of High Request for Bid Single Stage - On 2024-03- 2024-03- 2024-04- 2024-04- 2024-05- 2025-11- r Instrument Division and E IBRD / 89960 Post Open - National 6,000.00 0.00 Canceled Impact Weather, Floods an s e Envelope 20 20 19 21 26 17 lectronic Division in the He d Landslides ad Office of the Departmen t of Meteorology SLMOI/CRES/DOM/G/S/33 / Component 1: Forecasting Procurement of Tools for In Under Impl and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-04- 2024-05- 2024-05- 2024-08- strument Division and Elect IBRD / 89960 Post 6,000.00 0.00 ementatio Impact Weather, Floods an tations l e Envelope 30 03 29 27 ronic Division in the Head n d Landslides Office of the Department of Meteorology SLMOI/CRES/DOM/G/ICB/2 Component 1: Forecasting Under Impl 2 / Repairing Existing AWS and Early Warning of High Request for Bid Open - Internatio Single Stage - On 2024-04- 2024-05- 2024-04- 2024-05- 2024-06- 2024-06- 2024-06- 2024-12- IBRD / 89960 Post 300,000.00 0.00 ementatio and ARGS in the Head Offic Impact Weather, Floods an s nal e Envelope 26 17 26 20 10 15 30 27 n e of the Department of Met d Landslides eorology SLMOI/CRES/DMC/G/NCB/4 Component 1: Forecasting Under Impl 0 / Procurement of PABX So and Early Warning of High Request for Bid Single Stage - On 2024-04- 2024-05- 2024-04- 2024-05- 2024-05- 2024-05- 2024-08- IBRD / 89960 Post Open - National 90,000.00 0.00 ementatio lutions for Inter-Communic Impact Weather, Floods an s e Envelope 26 10 26 17 21 31 29 n ation of DMC and DDMCUs d Landslides SLMOI/CRES/DMC/G/S/41 / Component 1: Forecasting Under Impl Procurement of GPS Vehicl and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-04- 2024-05- 2024-08- IBRD / 89960 Post 3,400.00 0.00 ementatio e Tracking Devices for Disa Impact Weather, Floods an tations l e Envelope 29 28 26 n ster Management Centre d Landslides SLMOI/CRES/DMC/G/S/42 / Component 1: Forecasting Under Impl Request for Quo Limited - Nationa Single Stage - On 2024-04- 2024-05- 2024-08- Procurement of Mobile Pho IBRD / 89960 and Early Warning of High Post 32,500.00 0.00 ementatio tations l e Envelope 29 29 27 nes for the Disaster Manag Impact Weather, Floods an n ement Centre d Landslides SLMOI/CRES/DMC/G/S/43 / Component 1: Forecasting Pending I Printing of Leaflets for Com and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-04- 2024-05- 2024-08- IBRD / 89960 Post 17,000.00 0.00 mplement munity Awareness for the Impact Weather, Floods an tations l e Envelope 30 29 27 ation Disaster Management Cent d Landslides re SLMOI/CRES/DOM/G/S/44 / Component 1: Forecasting Procurement of Office Furni and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-04- 2024-05- 2024-08- IBRD / 89960 Post 24,500.00 0.00 Canceled ture for the Hydraulics Res Impact Weather, Floods an tations l e Envelope 30 29 27 earch Laboratory, Irrigation d Landslides Department SLMOI/CRES/NBRO/G/S/47 Component 1: Forecasting Under Impl / Procurement of Office Fur and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-08- IBRD / 89960 Post 14,180.00 0.00 ementatio niture for Landslide Early W Impact Weather, Floods an tations l e Envelope 06 31 29 n arning Centre at National B d Landslides uilding Research Organizati on Page 12 SLMOI/CRES/DOM/G/S/46 / Component 1: Forecasting Under Impl Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-05- 2024-07- Procurement of Electrical A IBRD / 89960 and Early Warning of High Post 17,330.00 0.00 ementatio tations l e Envelope 07 03 31 30 ppliances for the Departme Impact Weather, Floods an n nt of Meteorology d Landslides SLMOI/CRES/ID/G/NCB/45 / Component 1: Forecasting Pending I Request for Bid Single Stage - On 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-08- Procurement of High-End C IBRD / 89960 and Early Warning of High Post Open - National 36,650.00 0.00 mplement s e Envelope 03 03 24 26 31 29 omputers under CResMPA. Impact Weather, Floods an ation d Landslides SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting Under Impl 48 / Procurement of Aware and Early Warning of High Request for Bid Single Stage - On 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-07- IBRD / 89960 Post Open - National 52,000.00 0.00 ementatio ness Center Chairs for Nati Impact Weather, Floods an s e Envelope 03 03 03 24 26 31 30 n onal Building Research Org d Landslides anization SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting Pending I 49 / Procurement of Aware and Early Warning of High Request for Bid Single Stage - On 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-08- IBRD / 89960 Post Open - National 56,600.00 0.00 mplement ness Center Multi-Media Un Impact Weather, Floods an s e Envelope 03 03 24 26 31 29 ation it for National Building Res d Landslides earch Organization. SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting Under Impl 50 / Supply, Installation an and Early Warning of High Request for Bid Single Stage - On 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-08- IBRD / 89960 Post Open - National 119,000.00 0.00 ementatio d Maintenance of 200 kWp Impact Weather, Floods an s e Envelope 03 03 03 24 26 31 29 n Solar System to National B d Landslides uilding Research Organizati on SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting 51 / Supply, Installation an Under Impl and Early Warning of High Request for Bid Single Stage - On 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-08- d Deployment of Sub Early IBRD / 89960 Post Open - National 50,000.00 0.00 ementatio Impact Weather, Floods an s e Envelope 03 10 03 24 26 31 29 Warning Unit at NBRO Rath n d Landslides napura District Office inclu ding basic IT Equipment SLMOI/CRES/NBRO/G/S/52 Component 1: Forecasting Pending I / Supply and Installation of and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-07- IBRD / 89960 Post 15,000.00 0.00 mplement Automated Sensor Network Impact Weather, Floods an tations l e Envelope 07 31 30 ation for National Building Resea d Landslides rch Organization SLMOI/CRES/NBRO/G/S/53 Component 1: Forecasting Under Impl / Procurement of Image Pro and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-08- IBRD / 89960 Post 30,000.00 0.00 ementatio cessing Computers for Nati Impact Weather, Floods an tations l e Envelope 07 31 29 n onal Building Research Org d Landslides anization SLMOI/CRES/NBRO/G/S/54 Component 1: Forecasting Under Impl Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-07- / Procurement of Field Equi IBRD / 89960 and Early Warning of High Post 30,000.00 0.00 ementatio tations l e Envelope 07 31 30 pment for National Building Impact Weather, Floods an n Research Organization d Landslides SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting 55 / Procurement of Drones Pending I and Early Warning of High Request for Bid Single Stage - On 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2024-08- , LiDar Sensors, and other IBRD / 89960 Post Open - National 80,000.00 0.00 mplement Impact Weather, Floods an s e Envelope 03 03 24 26 31 29 Drone based equipment for ation d Landslides National Building Research Organization SLMOI/CRES/ID/G/S/44 / Pr Component 1: Forecasting Under Impl ocurement of Office Furnitu and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-07- IBRD / 89960 Post 24,480.00 0.00 ementatio re for the Hydraulics Resea Impact Weather, Floods an tations l e Envelope 07 31 30 n rch Laboratory, Irrigation D d Landslides epartment SLMOI/CRES/NBRO/G/S/57 Component 1: Forecasting Under Impl Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-07- / Procurement of ETABS Sof IBRD / 89960 and Early Warning of High Post 7,200.00 0.00 ementatio tations l e Envelope 07 31 30 tware for National Building Impact Weather, Floods an n Research Organization d Landslides SLMOI/CRES/NBRO/G/S/58 Component 1: Forecasting Under Impl / Procurement of gINT Profe and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-07- IBRD / 89960 Post 2,700.00 0.00 ementatio ssional Software for Nation Impact Weather, Floods an tations l e Envelope 07 31 30 n al Building Research Organi d Landslides zation SLMOI/CRES/NBRO/G/S/59 Component 1: Forecasting Under Impl / Procurement of SAP2000 and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-07- IBRD / 89960 Post 7,200.00 0.00 ementatio Software for National Buildi Impact Weather, Floods an tations l e Envelope 07 31 30 n ng Research Organization d Landslides SLMOI/CRES/NBRO/G/S/60 Component 1: Forecasting Under Impl / Procurement of ZondST2D and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-07- IBRD / 89960 Post 4,350.00 0.00 ementatio Software for National Buildi Impact Weather, Floods an tations l e Envelope 07 31 30 n ng Research Organization d Landslides SLMOI/CRES/NBRO/G/S/62 Component 1: Forecasting / Procurement of MATLAB S and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-07- IBRD / 89960 Post 14,000.00 0.00 Canceled oftware with extension for Impact Weather, Floods an tations l e Envelope 07 31 30 National Building Research d Landslides Organization SLMOI/CRES/NBRO/G/S/64 Component 1: Forecasting Under Impl / Procurement of MS Office and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-07- IBRD / 89960 Post 1,000.00 0.00 ementatio 365 Software for National Impact Weather, Floods an tations l e Envelope 07 31 30 n Building Research Organiza d Landslides tion SLMOI/CRES/NBRO/G/DP/6 Component 1: Forecasting Pending I 1 / Procurement of ArcGIS and Early Warning of High 2024-05- 2024-05- 2024-05- 2024-07- IBRD / 89960 Post Direct Selection Direct - National 270,400.00 0.00 mplement Software for National Buildi Impact Weather, Floods an 06 13 31 30 ation ng Research Organization d Landslides SLMOI/CRES/NBRO/G/S/65 Component 1: Forecasting Pending I / Procurement of Microsoft and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-07- IBRD / 89960 Post 7,000.00 0.00 mplement Windows Server for Nation Impact Weather, Floods an tations l e Envelope 07 31 30 ation al Building Research Organi d Landslides zation SLMOI/CRES/NBRO/G/DP/6 Component 1: Forecasting Pending I 6 / Procurement of SarProz and Early Warning of High Direct - Internati 2024-05- 2024-05- 2024-05- 2024-07- IBRD / 89960 Post Direct Selection 22,000.00 0.00 mplement InSAR Processing Software Impact Weather, Floods an onal 06 20 29 28 ation for National Building Resea d Landslides rch Organization SLMOI/CRES/NBRO/G/S/67 Component 1: Forecasting / Procurement of GMS-Grou Pending I and Early Warning of High Request for Quo Limited - Internat Single Stage - On 2024-05- 2024-05- 2024-07- nd Water Modeling System IBRD / 89960 Post 22,000.00 0.00 mplement Impact Weather, Floods an tations ional e Envelope 07 31 30 v10.8 (Aquaveo) for Nation ation d Landslides al Building Research Organi zation SLMOI/CRES/NBRO/G/S/68 Component 1: Forecasting / Procurement of Arc Hydro Pending I and Early Warning of High Request for Quo Limited - Internat Single Stage - On 2024-05- 2024-05- 2024-07- Groundwater Pro Software f IBRD / 89960 Post 3,700.00 0.00 mplement Impact Weather, Floods an tations ional e Envelope 07 31 30 or ArcGIS Pro (Aquaveo) for ation d Landslides National Building Research Organization SLMOI/CRES/NBRO/G/DP/6 Component 1: Forecasting Pending I 9 / Procurement of Pix4d Fi and Early Warning of High 2024-05- 2024-05- 2024-05- 2024-07- IBRD / 89960 Post Direct Selection Direct - National 5,000.00 0.00 mplement eld Software for National B Impact Weather, Floods an 06 20 29 28 ation uilding Research Organizati d Landslides on SLMOI/CRES/NBRO/G/DP/7 Component 1: Forecasting Pending I 0 / Procurement of VR siml and Early Warning of High Direct - Internati 2024-05- 2024-05- 2024-05- 2024-07- IBRD / 89960 Post Direct Selection 1,450.00 0.00 mplement ab Software for National Bu Impact Weather, Floods an onal 06 20 31 30 ation ilding Research Organizatio d Landslides n SLMOI/CRES/NBRO/G/DP/7 Component 1: Forecasting Pending I 1 / Procurement of Tsurvey and Early Warning of High 2024-05- 2024-05- 2024-05- 2024-07- IBRD / 89960 Post Direct Selection Direct - National 1,600.00 0.00 mplement Android Field Software for Impact Weather, Floods an 06 20 31 30 ation National Building Research d Landslides Organization SLMOI/CRES/NBRO/G/S/72 Component 1: Forecasting Under Impl / Procurement of Terra Proc and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-07- IBRD / 89960 Post 3,750.00 0.00 ementatio essing Software for Nationa Impact Weather, Floods an tations l e Envelope 07 31 30 n l Building Research Organiz d Landslides ation SLMOI/CRES/DOM/G/S/74 / Component 1: Forecasting Under Impl Supply and Installation of N and Early Warning of High Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-05- 2024-08- IBRD / 89960 Post 3,330.00 0.00 ementatio etwork Extension of Local A Impact Weather, Floods an tations l e Envelope 10 31 29 n rea network (LAN) for the D d Landslides epartment of Meteorology. SLMOI/CRES/DMC/G/NCB/3 Component 1: Forecasting 5 / Procurement of PA Syst Under Impl and Early Warning of High Request for Bid Single Stage - On 2024-04- 2024-05- 2024-04- 2024-05- 2024-05- 2024-05- 2024-11- ems, Manual Sirens and Me IBRD / 89960 Post Open - National 580,660.00 0.00 ementatio Impact Weather, Floods an s e Envelope 25 10 25 16 21 31 27 gaphones for DMC for Com n d Landslides munity Strengthening in Sri Lanka SLMOI/CRES/DMC/G/NCB/3 Component 1: Forecasting Request for Bid Single Stage - On 2024-04- 2024-04- 2024-05- 2024-05- 2024-05- 2024-10- 6 / Procurement of Megaph IBRD / 89960 and Early Warning of High Post Open - National 450,000.00 0.00 Canceled s e Envelope 24 24 15 20 31 28 ones for Disaster Managem Impact Weather, Floods an ent Centre d Landslides SLMOI/CRES/ID/G/NCB/29 / Component 1: Forecasting Pending I Request for Bid Single Stage - On 2024-05- 2024-05- 2024-06- 2024-06- 2024-06- 2024-12- Procurement of ICT Equipm IBRD / 89960 and Early Warning of High Post Open - National 213,000.00 0.00 mplement s e Envelope 10 12 02 09 18 15 ent Impact Weather, Floods an ation d Landslides SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting Pending I 75 / Procurement of ICT Eq and Early Warning of High Request for Bid Single Stage - On 2024-05- 2024-05- 2024-06- 2024-06- 2024-06- 2024-10- IBRD / 89960 Post Open - National 300,000.00 0.00 mplement uipment for the Strengthen Impact Weather, Floods an s e Envelope 15 16 06 13 28 26 ation ing of Landslide Resilience d Landslides by NBRO SLMOI/CRES/NBRO/G/NCB/ 76 / Purchasing of Electroni Component 1: Forecasting Pending I c devices for data collectio and Early Warning of High Request for Bid Single Stage - On 2024-05- 2024-05- 2024-06- 2024-06- 2024-06- 2024-10- IBRD / 89960 Post Open - National 74,670.00 0.00 mplement n and integration into lands Impact Weather, Floods an s e Envelope 15 16 06 13 28 26 ation lide databases to support E d Landslides mergency Management an d Early Warning activities SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting Pending I 77 / Procurement of Workst and Early Warning of High Request for Bid Single Stage - On 2024-05- 2024-05- 2024-06- 2024-06- 2024-06- 2024-10- IBRD / 89960 Post Open - National 750,000.00 0.00 mplement ations for Heavy Data Anal Impact Weather, Floods an s e Envelope 16 17 07 14 29 27 ation ysis for Processing the Lan d Landslides dslide Susceptibility Mappi ng SLMOI/CRES/NBRO/G/NCB/ Component 1: Forecasting Pending I 78 / Digitizing the Factor M and Early Warning of High Request for Bid Single Stage - On 2024-05- 2024-05- 2024-06- 2024-06- 2024-06- 2024-10- IBRD / 89960 Post Open - National 21,000.00 0.00 mplement aps for Deriving the Landsli Impact Weather, Floods an s e Envelope 16 17 07 14 28 26 ation de Susceptibility Maps for d Landslides NBRO SLMOI/CRES/ID/G/S/31 / Pr Component 1: Forecasting Pending I Request for Quo Limited - Nationa Single Stage - On 2024-05- 2024-06- 2024-10- ocurement of Smart Boards IBRD / 89960 and Early Warning of High Post 27,000.00 0.00 mplement tations l e Envelope 16 05 03 , Video Conferencing Syste Impact Weather, Floods an ation m and LED TV d Landslides SLMOI/CRES/ID/G/NCB/30 / Component 1: Forecasting Pending I Request for Bid Single Stage - On 2024-05- 2024-05- 2024-06- 2024-06- 2024-06- 2024-10- Procurement of Photocopie IBRD / 89960 and Early Warning of High Post Open - National 59,400.00 0.00 mplement s e Envelope 15 15 05 12 23 21 rs, Printers and Scanners Impact Weather, Floods an ation d Landslides SLMOI/CRES/ID/G/ICB/27 / Component 1: Forecasting Pending I Request for Bid Open - Internatio Single Stage - On 2024-05- 2024-05- 2024-07- 2024-07- 2024-07- 2025-01- Procurement of High-Resol IBRD / 89960 and Early Warning of High Post 1,000,000.00 0.00 mplement s nal e Envelope 17 17 01 08 23 19 ution DEM Covering the ent Impact Weather, Floods an ation ire Sri Lanka d Landslides SLMOI/CRES/NBRO/G/DP/7 Component 1: Forecasting Pending I 9 / Procurement of MATLAB and Early Warning of High Direct - Internati 2024-05- 2024-06- 2024-06- 2024-07- IBRD / 89960 Post Direct Selection 14,000.00 0.00 mplement Software with extension for Impact Weather, Floods an onal 31 02 12 27 ation National Building Research d Landslides Organization. SLMOI/CRES/ID/G/S/79 / Pr Component 1: Forecasting Pending I Request for Quo Limited - Nationa Single Stage - On 2024-06- 2024-07- 2024-09- ocurement of ICT Equipme IBRD / 89960 and Early Warning of High Post 8,500.00 0.00 mplement tations l e Envelope 15 01 29 nt for PCT and MOI Impact Weather, Floods an ation d Landslides SLMOI/CRES/ID/G/S/80 / Pr Component 1: Forecasting Pending I Request for Quo Limited - Nationa Single Stage - On 2024-06- 2024-07- 2024-10- ocurement of a Server for IBRD / 89960 and Early Warning of High Post 10,000.00 0.00 mplement tations l e Envelope 15 06 04 CRIP Data Storage for ID Impact Weather, Floods an ation d Landslides NON CONSULTING SERVICES Activity Reference No Estimated A Draft Bidding Doc Specific Procureme Proposal Submissio Bid Evaluation Rep Loan / Credit Market Appro Procurement Prequalificati Actual Amou Process Draft Pre-qualificati Prequalification Ev Bidding Documents Contract Completio . / Description Component Review Type Method mount (US$ ument / Justificatio nt Notice / Invitatio n / Opening / Minut ort and Recommen Signed Contract No. ach Process on (Y/N) nt (US$) Status on Documents aluation Report as Issued n ) n n es dation for Award Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d d d d d d SLMOI/CRES/PCT/NCS/NCB/ 01 / Conducting Bathymetri Component 1: Forecasting c Surveys, LiDAR Drone Sur and Early Warning of High Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-06- 2024-12- veys and River Cross Sectio IBRD / 89960 Post Open - National 1,774,193.55 0.00 Canceled Impact Weather, Floods an s e Envelope 20 25 07 07 11 08 ns in Kelani, Kalu, Gin, Atta d Landslides nagalu Oya, Maha Oya, Be nthara, Polwathumodara a nd Nilwala River Basin SLMOI/CRES/PCT/NCS/NCB/ 02 / Conducting Bathymetri Component 1: Forecasting c Surveys, LiDAR Drone Sur and Early Warning of High Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-06- 2024-12- veys and River Cross Sectio IBRD / 89960 Prior Open - National 2,000,000.00 0.00 Canceled Impact Weather, Floods an s e Envelope 20 25 07 07 11 08 ns in Yan Oya, Deduru Oya, d Landslides Kirindi Oya, alawe, Kumbuk kan Oya, Manik Ganga, He da Oya and Kala Oya River Basins SLMOI/CRES/PCT/NCS/NCB/ 03 / Carrying out Bathymet ric Surveys, LiDAR Drone S Component 1: Forecasting urveys and River Cross Sec and Early Warning of High Request for Bid Single Stage - On 2024-02- 2024-02- 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Prior Open - National 2,296,774.19 0.00 Canceled tions in Mahaweli, Malwath Impact Weather, Floods an s e Envelope 20 25 07 07 11 08 u Oya, Maduru Oya, Munde d Landslides ni Aru, Ma Oya, Per Aru, Ka nakarayan Aru, Paranki Aru , Pali Aru, Gal Oya and Kara balan Oya River Basin SLMOI/CRES/ID/NCS/ICB/04 Component 1: Forecasting Pending I / Carrying out Bathymetric and Early Warning of High Request for Bid Open - Internatio Single Stage - Tw 2024-03- 2024-03- 2024-05- 2024-07- 2024-08- 2025-02- IBRD / 89960 Prior 3,812,000.00 0.00 mplement Surveys and LiDAR Drone S Impact Weather, Floods an s nal o Envelope 22 27 11 09 13 09 ation urveys for 22 River Basins d Landslides SLMOI/CRES/ID/NCS/ICB/05 Component 1: Forecasting / Conducting a LiDAR Surve and Early Warning of High Request for Bid Open - Internatio Single Stage - Tw 2024-05- 2024-05- 2024-07- 2024-08- 2024-08- 2025-02- IBRD / 89960 Prior 1,954,000.00 0.00 Canceled y and LiDAR DEM for Landsl Impact Weather, Floods an s nal o Envelope 17 19 03 07 24 20 ide-Prone Districts in Sri La d Landslides nka SLMOI/CRES/NBRO/NCS/IC Component 1: Forecasting Pending I B/05 / Conducting a LiDAR and Early Warning of High Request for Bid Open - Internatio Single Stage - Tw 2024-05- 2024-05- 2024-07- 2024-07- 2024-08- 2025-04- IBRD / 89960 Prior 2,463,000.00 0.00 mplement Survey and Preparation of Impact Weather, Floods an s nal o Envelope 17 17 01 29 15 12 ation a LiDAR DEM for Landslide- d Landslides Prone Districts in Sri Lanka CONSULTING FIRMS Activity Reference No Short List and Draft Opening of Technic Combined Evaluati Loan / Credit Market Appro Contract Type Estimated A Actual Amo Process Stat Expression of Inter Request for Propos Evaluation of Tech Contract Completio . / Description Component Review Type Method Terms of Reference Request for Propos al Proposals / Minut on Report and Draf Signed Contract No. ach mount (US$) unt (US$) us est Notice als as Issued nical Proposal n als es t Negotiated Contr Planned Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne Actual Planne act Actual Planne Actual Planne Actual d d d d d d d d SLMOI/CRES/ID/C/CQS/28 / Component 2: Flood Risk Consultant Qual 2022-09-3 2022-10- 2022-12- 2023-01- 2023-02- 2023-05- Consultancy Services for S IBRD / 89960 Mitigation Investments in t Post ification Selecti Open - National 25,000.00 0.00 Canceled 0 21 04 03 07 08 ocio-economic Survey for he lower Kelani basin on Wee Oya Reservoir SLMOI/CRES/ID/C/CQS/10 / Component 1: Forecasting Consultant Qual Developing a cloud-based and Early Warning of High 2022-08-3 2022-10- 2022-09- 2022-10- 2022-11- 2023-05- IBRD / 89960 Post ification Selecti Limited 28,000.00 0.00 Canceled Web Portal for archiving an Impact Weather, Floods an 1 05 20 20 24 23 on d displaying data gathered d Landslides from various systems SLMOI/CRES/ID/C/QCBS/03 Component 2: Flood Risk Quality And Cos Pending Imple 2023-01-1 2023-02- 2023-03- 2023-04- 2023-05- 2023-06- 2023-07- 2024-01- / Preparation of Environme IBRD / 89960 Mitigation Investments in t Post t-Based Selectio Open - National 225,000.00 0.00 mentation 6 06 22 19 19 23 28 24 ntal Impact Assessments fo he lower Kelani basin n r Wee Oya Reservoir SLMOI/CRES/ID/C/QCBS/05 Component 2: Flood Risk Quality And Cos / Consultancy Service for D Open - Internatio 2022-09-1 2022-10- 2022-10- 2022-10- 2022-12- 2023-05- 2023-01- 2023-07- 2023-03- 2023-09- 2023-05- 2024-01- 2023-07- 2024-03- 2026-05- IBRD / 89960 Mitigation Investments in t Prior t-Based Selectio 2,500,000.00 0.00 Signed esign Review and Construc nal 2 12 12 20 26 15 25 19 26 26 09 25 07 21 13 he lower Kelani basin n tion Supervision of Salinity Barrier at Ambatale SLMOI/CRES/PCT/C/CQS/24 Consultant Qual / Developing of the Web Ba Component 4: Project Man 2022-09-1 2023-02- 2022-09- 2023-03- 2022-10- 2022-12- 2023-06- IBRD / 89960 Post ification Selecti Limited 25,000.00 0.00 Canceled sed Management Informati agement 5 13 29 27 29 03 01 on on System (MIS) for CResM PA SLMOI/CRES/ID/C/CQS/06 / Component 2: Flood Risk Consultant Qual 2022-09-1 2022-11- 2022-10- 2022-11- 2022-12- 2023-04- Biodiversity Assessment for IBRD / 89960 Mitigation Investments in t Post ification Selecti Limited 30,000.00 0.00 Canceled 5 01 05 04 09 08 Wee Oya Reservoir Area he lower Kelani basin on SLMOI/CRES/ID/C/CQS/29 / Component 2: Flood Risk Consultant Qual Pending Imple 2022-12-1 2023-01- 2023-03- 2023-05- 2026-08- Hiring of Consultants for Da IBRD / 89960 Mitigation Investments in t Post ification Selecti Limited 40,000.00 0.00 mentation 5 14 15 15 27 m Safety Review Panel for he lower Kelani basin on Wee Oya Reservoir SLMOI/CRES/ID/C/QCBS/01 Component 2: Flood Risk Quality And Cos / Preparation of Detail Engi Open - Internatio 2022-09-1 2022-10- 2022-10- 2022-10- 2023-02- 2023-02- 2023-04- 2023-06- 2023-07- 2024-04- IBRD / 89960 Mitigation Investments in t Prior t-Based Selectio 3,500,000.00 0.00 Canceled neering Design and Bidding nal 5 11 15 20 12 26 27 25 23 18 he lower Kelani basin n Document for Wee Oya Res ervoir SLMOI/CRES/DOM/C/QCBS/ Component 1: Forecasting 30 / Consultancy Services f Quality And Cos and Early Warning of High Open - Internatio 2023-01-1 2023-01- 2023-03- 2023-04- 2023-05- 2023-06- 2023-07- 2024-07- or Systems Integration for t IBRD / 89960 Prior t-Based Selectio 3,000,000.00 0.00 Canceled Impact Weather, Floods an nal 0 31 16 13 13 17 22 21 he Modernization of the De n d Landslides partment of Meteorology, S ri Lanka SLMOI/CRES/DOM/C/QCBS/ Component 1: Forecasting 30-2 / Consultancy Service Quality And Cos and Early Warning of High Open - Internatio 2023-06-1 2023-06- 2023-07- 2023-06- 2023-08- 2023-09- 2023-10- 2023-11- 2023-12- 2026-12- s for Systems Integration fo IBRD / 89960 Prior t-Based Selectio 3,000,000.00 0.00 Canceled Impact Weather, Floods an nal 2 07 03 23 16 13 13 17 22 31 r the Modernization of the n d Landslides Department of Meteorology , Sri Lanka SLMOI/CRES/ID/C/QCBS/01 Component 2: Flood Risk Quality And Cos -3 / Preparation of Detail En Open - Internatio Under Impleme 2023-07-0 2023-07- 2023-08- 2023-12- 2024-05- 2023-12- 2024-01- 2024-02- 2024-05- 2024-04- 2024-05- 2025-06- IBRD / 89960 Mitigation Investments in t Prior t-Based Selectio 2,400,000.00 0.00 gineering Design and Biddi nal ntation 5 18 04 02 01 16 10 14 07 13 11 11 he lower Kelani basin n ng Document for Wee Oya Reservoir SLMOI/CRES/ID/C/QCBS/01 Component 2: Flood Risk Quality And Cos -2 / Preparation of Detail En Open - Internatio 2023-06-1 2023-07- 2023-11- 2023-11- 2024-01- 2024-03- 2024-04- 2025-02- IBRD / 89960 Mitigation Investments in t Prior t-Based Selectio 2,400,000.00 0.00 Canceled gineering Design and Biddi nal 2 12 09 23 22 21 18 12 he lower Kelani basin n ng Document for Wee Oya Reservoir SLMOI/CRES/DOM/C/QCBS/ Component 1: Forecasting 30-3 / Consultancy Service Quality And Cos and Early Warning of High Open - Internatio Under Impleme 2023-08-0 2023-08- 2023-08- 2023-08- 2023-10- 2024-02- 2023-11- 2024-03- 2023-12- 2024-01- 2024-02- 2026-12- s for Systems Integration fo IBRD / 89960 Prior t-Based Selectio 3,000,000.00 0.00 Impact Weather, Floods an nal ntation 4 04 25 11 08 01 05 18 05 09 13 31 r the Modernization of the n d Landslides Department of Meteorology , Sri Lanka SLMOI/CRES/PCT/C/QCBS/3 1 / Consultancy Service for Design, Developing, Install Quality And Cos Component 4: Project Man Under Impleme 2023-08-1 2023-10- 2023-09- 2023-10- 2023-11- 2023-12- 2024-01- 2024-02- 2024-07- & Maintain a Web-based M IBRD / 89960 Post t-Based Selectio Open - National 65,000.00 0.00 agement ntation 4 23 04 18 15 15 19 23 12 anagement Information Sys n tem and GIS Application for Climate Resilience Multipha se Programmatic Approach (CResMPA) SLMOI/CRES/DMC/C/CQS/1 Component 1: Forecasting 8 / Engineering assistance f Consultant Qual and Early Warning of High 2022-09-1 2022-10- 2022-11- 2022-12- 2023-06- or the architectural and int IBRD / 89960 Post ification Selecti Limited 20,000.00 0.00 Canceled Impact Weather, Floods an 9 03 02 07 05 erior designing of EOC cons on d Landslides idering the maximum utiliz ation of the existing resour ces SLMOI/CRES/ID/C/QCBS/38 Component 1: Forecasting Quality And Cos / Developing a Cloud-Based and Early Warning of High Under Impleme 2023-12-1 2023-11- 2024-01- 2024-02- 2024-03- 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post t-Based Selectio Open - National 50,000.00 0.00 Web Portal for Archiving an Impact Weather, Floods an ntation 5 22 05 18 17 16 21 25 10 n d Displaying Data Gathered d Landslides from Various Systems SLMOI/CRES/DMC/C/QCBS/ Component 1: Forecasting 18 / Engineering Assistance Quality And Cos and Early Warning of High 2023-12-1 2024-01- 2024-02- 2024-03- 2024-04- 2024-05- 2024-06- 2025-06- for the Architectural and Int IBRD / 89960 Post t-Based Selectio Open - National 22,000.00 0.00 Canceled Impact Weather, Floods an 5 05 18 17 16 21 25 25 erior Designing of EOC Con n d Landslides sidering the Maximum Utili zation of the Existing Reso urces Page 13 SLMOI/CRES/DMC/C/CQS/1 2 / Comprehensive Study o Component 1: Forecasting Consultant Qual n Data Availability, potenti and Early Warning of High 2023-12-1 2024-01- 2024-02- 2024-03- 2024-04- 2024-10- IBRD / 89960 Post ification Selecti Open - National 44,000.00 0.00 Canceled al Application of Spatial an Impact Weather, Floods an 5 05 18 19 23 20 on d non spatial data for DRM d Landslides and development of govern ance mechanism for utilizat ion SLMOI/CRES/DMC/C/QCBS/ 32 / Consultancy Service fo Component 1: Forecasting Quality And Cos r Enhancing Institutional Ca and Early Warning of High 2023-12-2 2024-01- 2024-02- 2024-03- 2024-04- 2024-05- 2024-06- 2025-06- IBRD / 89960 Post t-Based Selectio Open - National 62,500.00 0.00 Canceled pacity and Existing Informa Impact Weather, Floods an 0 10 23 22 21 26 30 30 n tion Systems for Disaster Ri d Landslides sk Reduction and Response at Disaster Management C entre SLMOI/CRES/PCT/C/CQS/42 Consultant Qual / Developing a Project Web Component 4: Project Man Pending Imple 2024-01-3 2024-02- 2024-03- 2024-04- 2024-10- IBRD / 89960 Post ification Selecti Limited 1,100.00 0.00 site for Climate Resilience agement mentation 1 20 21 25 22 on Multi-Phase Programmatic Approach (CResMPA) SLMOI/CRES/PCT/C/CQS/43 Consultant Qual / Developing Video and Aud Component 4: Project Man Pending Imple 2024-01-3 2024-02- 2024-03- 2024-04- 2024-10- IBRD / 89960 Post ification Selecti Limited 9,375.00 0.00 io Conference Facilities for agement mentation 1 20 21 25 22 on the PCT Conference Room SLMOI/CRES/DOM/CS/CQS/ Component 1: Forecasting Consultant Qual 96 / Hiring consultancy ser and Early Warning of High 2024-02-2 2024-03- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post ification Selecti Limited 227,272.73 0.00 Canceled vices for the conservation o Impact Weather, Floods an 9 20 19 24 20 on f historial climate data con d Landslides verting into digital form SLMOI/CRES/DOM/CS/CQS/ 97 / Hiring civil work/archit Component 1: Forecasting Consultant Qual ectural firm to prepare esti and Early Warning of High 2024-02-2 2024-03- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post ification Selecti Limited 99,666.67 0.00 Canceled mates, BOQ, and tender do Impact Weather, Floods an 9 20 19 24 20 on cuments for refurbishment d Landslides of head office premises an d regional offices SLMOI/CRES/ID/C/QCBS/40 Component 1: Forecasting Quality And Cos / Development of Real-Tim and Early Warning of High 2024-02-0 2024-02- 2024-02- 2024-04- 2024-05- 2024-06- 2024-07- 2024-08- 2025-02- IBRD / 89960 Post t-Based Selectio Open - National 156,250.00 0.00 Canceled e Flood Forecasting Models Impact Weather, Floods an 7 11 28 12 10 09 14 18 14 n for Kelani and Kalu River B d Landslides asins. SLMOI/CRES/ID-COL/C/IC/1 Component 1: Forecasting Consultant Qual Under Impleme 2024-02-1 2024-01- 2024-02- 2024-03- 2024-05- 2024-10- 19 / Individual Consultant ( IBRD / 89960 and Early Warning of High Post ification Selecti Limited 2,100.00 0.00 ntation 5 22 29 30 04 31 Project Engineer) for Colom Impact Weather, Floods an on bo – DI Office d Landslides SLMOI/CRES/ID-RAT/C/IC/1 Component 1: Forecasting Consultant Qual Under Impleme 2024-02-1 2024-01- 2024-02- 2024-03- 2024-05- 2024-10- 16 / Individual Consultant ( IBRD / 89960 and Early Warning of High Post ification Selecti Limited 1,500.00 0.00 ntation 5 05 29 30 04 31 Engineering Assistant) for Impact Weather, Floods an on Rathnapura – DI Office d Landslides SLMOI/CRES/ID-RAT/C/IC/1 Component 1: Forecasting Consultant Qual Under Impleme 2024-02-1 2024-01- 2024-02- 2024-03- 2024-05- 2024-10- 17 / Individual Consultant ( IBRD / 89960 and Early Warning of High Post ification Selecti Limited 1,500.00 0.00 ntation 5 05 29 30 04 31 Engineering Assistant) for Impact Weather, Floods an on Rathnapura – DI Office d Landslides SLMOI/CRES/ID-RAT/C/IC/1 Component 1: Forecasting Consultant Qual Under Impleme 2024-02-1 2024-01- 2024-02- 2024-03- 2024-05- 2024-10- 18 / Individual Consultant ( IBRD / 89960 and Early Warning of High Post ification Selecti Limited 1,500.00 0.00 ntation 5 05 29 30 04 31 Engineering Assistant) for Impact Weather, Floods an on Rathnapura – DI Office d Landslides SLMOI/CRES/ID/C/QCBS/12 3 / Development of Real-Ti Component 1: Forecasting Quality And Cos me Flood Forecasting Mode and Early Warning of High 2024-02-1 2024-02- 2024-03- 2024-04- 2024-05- 2024-06- 2024-07- 2024-08- 2025-08- IBRD / 89960 Post t-Based Selectio Open - National 267,741.94 0.00 Canceled ls for Yan Oya, Deduburu O Impact Weather, Floods an 9 11 11 24 22 21 26 30 30 n ya, Kirindi Oya, Walawe, Ku d Landslides mukkan Oya, Manik Ganga, Heda Oya and Kala Oya Riv er Basins SLMOI/CRES/ID/C/QCBS/12 4 / Development of Real-Ti Component 1: Forecasting me Flood Forecasting Mode Quality And Cos and Early Warning of High 2024-02-1 2024-02- 2024-03- 2024-04- 2024-05- 2024-06- 2024-07- 2024-08- 2025-08- ls for Mahaweli, Malwathu IBRD / 89960 Post t-Based Selectio Open - National 267,741.94 0.00 Canceled Impact Weather, Floods an 9 11 11 24 22 21 26 30 30 Oya, Maduru Oya, Mundeni n d Landslides Aru, Ma Oya, Per Aru, Kana karayan Aru, Paranki Aru P ali Aru, Gal Oya and Karaba lan Oya River Basins SLMOI/CRES/ID/C/QCBS/13 Component 1: Forecasting Quality And Cos 4 / Development of Real-Ti and Early Warning of High Open - Internatio Pending Imple 2024-03-2 2024-04- 2024-06- 2024-08- 2024-09- 2024-10- 2024-11- 2026-12- IBRD / 89960 Prior t-Based Selectio 1,060,000.00 0.00 me Flood Forecasting Mode Impact Weather, Floods an nal mentation 8 27 26 10 24 10 07 31 n ls for 22 River Basins in Sri d Landslides Lanka SLMOI/CRES/DOM/C/CQS/9 7 / Hiring civil work/archite Component 1: Forecasting Consultant Qual ctural firm to prepare estim and Early Warning of High 2024-02-2 2024-03- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post ification Selecti Limited 493,593.03 0.00 Canceled ates, BOQ and tender docu Impact Weather, Floods an 5 10 09 14 10 on ments for refurbishment of d Landslides head office office premises and regional offices SLMOI/CRES/DOM/C/QCBS/ 97 / Hiring a Civil Work/Arc Component 1: Forecasting hitectural Firm to Prepare E Quality And Cos and Early Warning of High Under Impleme 2024-03-0 2024-03- 2024-03- 2024-04- 2024-04- 2024-05- 2024-05- 2024-06- 2025-06- stimates, BOQ and Tender IBRD / 89960 Post t-Based Selectio Open - National 310,000.00 0.00 Impact Weather, Floods an ntation 4 22 18 01 29 06 25 29 29 Documents for the Refurbis n d Landslides hment of Head Office Premi ses and Regional Offices of the Department of Meteoro logy SLOMI/CRES/DOM/C/CQS/9 Component 1: Forecasting Consultant Qual 6 / Hiring consultancy servi and Early Warning of High 2024-02-2 2024-03- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post ification Selecti Limited 227,272.73 0.00 Canceled ces for conservation of hist Impact Weather, Floods an 9 20 19 24 20 on orical climate data converti d Landslides ng into digital form SLMOI/CRES/ID/C/CQS/125 Component 1: Forecasting Consultant Qual / Consultancy Services for I and Early Warning of High Limited - Nationa 2024-04-1 2024-04- 2024-05- 2024-06- 2024-10- IBRD / 89960 Post ification Selecti 240,000.00 0.00 Canceled dentifying Locations for Ne Impact Weather, Floods an l 0 24 24 28 26 on w Hydrological Stations in d Landslides 27 River Basins SLMOI/CRES/ID/C/QCBS/12 Component 1: Forecasting Quality And Cos 5 / Consultancy Services fo and Early Warning of High Under Impleme 2024-04-0 2024-05- 2024-04- 2024-04- 2024-05- 2024-05- 2024-06- 2024-06- 2024-10- IBRD / 89960 Post t-Based Selectio Open - National 240,000.00 0.00 r Identifying Locations for N Impact Weather, Floods an ntation 5 02 08 20 18 23 11 30 28 n ew Hydrological Stations in d Landslides 27 River Basins SLMOI/CRES/DMC/C/QCBS/ 41 / Consultant Services to Upgrade the Emergency Pr Component 1: Forecasting Quality And Cos eparedness and Response and Early Warning of High 2023-12-2 2024-01- 2024-03- 2024-03- 2024-04- 2024-06- 2024-07- 2025-12- IBRD / 89960 Post t-Based Selectio Open - National 62,500.00 0.00 Canceled Capacity of the Disaster Ma Impact Weather, Floods an 9 19 03 31 30 04 09 31 n nagement Centre (Emerge d Landslides ncy Operations Center, Dist rict Offices, Call Center, Co mmunication Networks and Early Warning Disseminatio SLMOI/CRES/NBRO/C/QCBS n) Component 1: Forecasting Quality And Cos /135 / Consultancy Services and Early Warning of High 2024-03-1 2024-04- 2024-05- 2024-06- 2024-07- 2024-08- 2024-09- 2025-09- IBRD / 89960 Prior t-Based Selectio Open - National 1,000,000.00 0.00 Canceled for Preparation and Establis Impact Weather, Floods an 5 05 19 16 16 20 24 24 n hment of a National Buildin d Landslides g Code for Sri Lanka SLMOI/CRES/DMC/C/QCBS/ 41-1 / Consultancy Service s to upgrade the Emergenc Component 1: Forecasting y Preparedness and Respo Quality And Cos and Early Warning of High 2024-04-2 2023-12- 2024-04- 2024-05- 2024-05- 2024-05- 2024-05- 2024-05- 2025-11- nse Capacity of the Disaste IBRD / 89960 Post t-Based Selectio Open - National 300,000.00 0.00 Under Review Impact Weather, Floods an 4 01 29 02 19 22 28 31 22 r Management Centre (IT & n d Landslides Communication Networks a nd Early Warning Dissemin ation, Emergency Operatio ns Center, District Offices, and Call Center) SLMOI/CRES/DMC/C/QCBS/ 137 / Consultant Service fo Component 1: Forecasting Quality And Cos r Designing and Developing and Early Warning of High Open - Internatio Pending Imple 2024-05-1 2024-05- 2024-06- 2024-07- 2024-08- 2024-09- 2024-09- 2025-09- IBRD / 89960 Prior t-Based Selectio 1,500,000.00 0.00 a Decision Support System Impact Weather, Floods an nal mentation 0 31 14 29 18 11 30 30 n (DSS) to Enhance Emergen d Landslides cy Preparedness and Respo nse for Disaster Risk Reduc tion SLMOI/CRES/ID/C/CQS/136 Component 2: Flood Risk Consultant Qual / Consultancy Services for Pending Imple 2024-05-0 2024-05- 2024-06- 2024-06- 2024-07- 2025-01- IBRD / 89960 Mitigation Investments in t Post ification Selecti Open - National 33,300.00 0.00 Conducting a Baseline Stud mentation 3 17 21 28 19 15 he lower Kelani basin on y on the Existing Salinity B arrier at Ambathale SLMOI/CRES/ID/C/CQS/125 Component 1: Forecasting Consultant Qual -1 / Consultancy Services f and Early Warning of High Limited - Nationa Pending Imple 2024-05-0 2024-05- 2024-05- 2024-06- 2024-10- IBRD / 89960 Post ification Selecti 240,000.00 0.00 or Identifying Locations for Impact Weather, Floods an l mentation 6 20 27 11 09 on New Hydrological Stations i d Landslides n 27 River Basins SLMOI/CRES/NBRO/C/QCBS Component 1: Forecasting Quality And Cos /138 / Development of Lan and Early Warning of High Open - Internatio Pending Imple 2024-05-1 2024-06- 2024-06- 2024-08- 2024-08- 2024-09- 2024-09- 2025-09- IBRD / 89960 Post t-Based Selectio 750,000.00 0.00 dslide Resilience Analytical Impact Weather, Floods an nal mentation 7 07 19 03 10 03 22 22 n and Advisory System for N d Landslides BRO SLMOI/CRES/NBRO/C/CQS/ Component 1: Forecasting Consultant Qual 139 / Development of the S and Early Warning of High Limited - Nationa Pending Imple 2024-05-1 2024-05- 2024-06- 2024-07- 2025-01- IBRD / 89960 Post ification Selecti 100,000.00 0.00 econd Phase of the Landsli Impact Weather, Floods an l mentation 7 20 19 05 01 on de Information Managemen d Landslides t System SLMOI/CRES/ID/C/QCBS/02 / Consultancy Services for Component 2: Flood Risk Quality And Cos Conducting a Social Impact Pending Imple 2024-05-2 2024-06- 2024-06- 2024-07- 2024-08- 2024-09- 2024-10- 2025-07- IBRD / 89960 Mitigation Investments in t Post t-Based Selectio Open - National 134,000.00 0.00 Assessment (SIA) and mentation 2 05 19 17 16 13 02 29 he lower Kelani basin n Preparation of a Resettlem ent Action Plan (RAP) for th e Construction of Wee Oya Reservoir SLMOI/CRES/PCT/C/QCBS/3 1-1 / Consultancy Service f or Design, Developing, Inst Consultant Qual Component 4: Project Man Limited - Nationa 2024-05-2 2024-06- 2024-06- 2024-06- 2024-12- all & Maintain a Web-based IBRD / 89960 Post ification Selecti 65,000.00 0.00 Canceled agement l 4 07 21 23 20 Management Information S on ystem for Climate Resilienc e Multiphase Programmatic Approach (CResMPA) SLMOI/CRES/PCT/C/CQS/14 Consultant Qual 0 / Hiring a Consultancy Fir Component 4: Project Man Limited - Nationa Pending Imple 2024-06-1 2024-07- 2024-07- 2024-07- 2024-10- IBRD / 89960 Post ification Selecti 50,000.00 0.00 m to Prepare the Mid-Term agement l mentation 4 05 15 17 15 on Review Report for the Borr ower SLMOI/CRES/PCT/C/CQS/31 -1 / Consultancy Service for Design, Developing, Install Consultant Qual Component 4: Project Man Limited - Nationa Pending Imple 2024-06-1 2024-06- 2024-07- 2024-07- 2024-12- & Maintain a Web-based M IBRD / 89960 Post ification Selecti 65,000.00 0.00 agement l mentation 4 28 12 19 06 anagement Information Sys on tem for Climate Resilience Multiphase Programmatic A pproach (CResMPA) INDIVIDUAL CONSULTANTS Activity Reference No Invitation to Identif Loan / Credit Market Appro Contract Type Estimated A Actual Amo Process Stat Draft Negotiated C Contract Completio . / Description Component Review Type Method Terms of Reference ied/Selected Consu Signed Contract No. ach mount (US$) unt (US$) us ontract n ltant Planned Actual Planne Actual Planne Actual Planne Actual Planne Actual d d d d LK-MAREALIFA-302011-CS- Component 1: Forecasting INDV / Cres/ID/C/IC/26 - Indi and Early Warning of High Individual Cons 2022-07-1 2022-07- 2022-08- 2022-09- 2023-03- vidual consultant for ICT inf IBRD / 89960 Post Limited 8,000.00 0.00 Canceled Impact Weather, Floods an ultant Selection 5 20 10 14 13 rastructure development of d Landslides flood monitoring and opera tion room SLMOI/CRES/ID/C/IC/26 / In Component 1: Forecasting dividual consultant for ICT i and Early Warning of High Individual Cons 2022-08-2 2022-09- 2022-09- 2022-11- 2022-09- 2023-03- 2022-10- 2023-04- 2023-04- IBRD / 89960 Post Limited 8,000.00 0.00 Signed nfrastructure development Impact Weather, Floods an ultant Selection 9 14 03 01 24 02 29 03 27 of flood monitoring and ope d Landslides ration room SLMOI/CRES/PCT/C/DS/23 / Consortium Architectural C Component 1: Forecasting onsultancy Services of Prop and Early Warning of High 2022-11-1 2022-11- 2023-01- 2024-08- IBRD / 89960 Post Direct Selection Direct - National 47,000.00 0.00 Canceled osed Disaster Risk Reducti Impact Weather, Floods an 5 25 29 01 on Observation, Forecastin d Landslides g and Communication Hubs for Department of Meteorol ogy SLMOI/CRES/ID/C/DS/27 / C onsultancy Services for upd Component 2: Flood Risk Under Impleme 2023-02-0 2023-05- 2023-02- 2023-04- 2026-03- ating the Environmental an IBRD / 89960 Mitigation Investments in t Post Direct Selection Direct - National 25,000.00 0.00 ntation 1 25 11 28 15 d Social Impact Assessmen he lower Kelani basin t for Ambathale Salinity Ba rrier SLMOI/CRES/PCT/C/IC/34 / Individual Consultant (Rese Component 4: Project Man Individual Cons 2023-09-2 2023-10- 2023-10- 2023-10- 2023-11- 2024-10- IBRD / 89960 Post Limited 4,400.00 0.00 Canceled ttlement Mobilization) for t agement ultant Selection 2 04 17 22 01 31 he Social and Resettlement Unit - CResMPA SLMOI/CRES/PCT/C/IC/35 / Individual Consultant (Soci Component 4: Project Man Individual Cons Under Impleme 2023-09-2 2023-10- 2023-10- 2023-10- 2023-11- 2024-10- IBRD / 89960 Post Limited 4,400.00 0.00 al Mobilization) for the Soci agement ultant Selection ntation 2 25 17 22 01 31 al and Resettlement Unit - CResMPA SLMOI/CRES/PCT/C/IC/36 / Individual Consultant (Soci Component 4: Project Man Individual Cons Under Impleme 2023-09-2 2023-10- 2023-10- 2023-10- 2023-11- 2024-10- IBRD / 89960 Post Limited 4,400.00 0.00 al Safeguard) for the Social agement ultant Selection ntation 2 25 17 22 01 31 and Resettlement Unit - CR esMPA Component 1: Forecasting SLMOI/CRES/PCT/C/DS/25 / 2023-12-1 2023-12- 2024-02- 2024-11- IBRD / 89960 and Early Warning of High Post Direct Selection Direct - National 6,400.00 0.00 Canceled Hiring of Local Expert - ICT 5 25 28 24 Impact Weather, Floods an d Landslides SLMOI/CRES/PCT/C/IC/37 / Individual Consultant for Fi Component 4: Project Man Individual Cons Under Impleme 2023-12-1 2023-12- 2024-01- 2024-01- 2024-01- 2025-01- IBRD / 89960 Post Limited 2,000.00 0.00 nancial Database and MIS agement ultant Selection ntation 5 28 09 14 24 23 Operator for Accounts Divis ion - CResMPA SLMOI/CRES/PCT/C/IC/34-1 / Individual Consultant for Component 4: Project Man Individual Cons Under Impleme 2023-12-1 2023-11- 2024-01- 2024-01- 2024-01- 2025-01- IBRD / 89960 Post Limited 4,400.00 0.00 Community Development f agement ultant Selection ntation 5 17 09 14 24 23 or the Social and Resettlem ent Unit - CResMPA SLMOI/CRES/ID/C/IC/45 / In Component 1: Forecasting Individual Cons Under Impleme 2023-12-3 2023-12- 2024-02- 2024-03- 2024-04- 2024-10- dividual Consultant (Civil E IBRD / 89960 and Early Warning of High Post Open - National 2,100.00 0.00 ultant Selection ntation 1 11 18 10 14 11 ngineer) for the Hydrology Impact Weather, Floods an and DM Division of ID d Landslides SLMOI/CRES/ID/C/IC/44 / In Component 1: Forecasting dividual Consultant (Civil E and Early Warning of High Individual Cons Under Impleme 2024-01-3 2023-12- 2024-03- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 ngineer) for the Hydrology Impact Weather, Floods an ultant Selection ntation 1 11 20 10 15 11 and DM Division of ID Head d Landslides Office SLMOI/CRES/ID/C/IC/46 / In Component 1: Forecasting dividual Consultant (Civil E and Early Warning of High Individual Cons Under Impleme 2024-01-3 2023-12- 2024-03- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 ngineer) for the Hydrology Impact Weather, Floods an ultant Selection ntation 1 11 20 10 15 11 and DM Division of ID Head d Landslides Office SLMOI/CRES/ID/C/IC/47 / In Component 1: Forecasting dividual Consultant (Civil E and Early Warning of High Individual Cons Under Impleme 2024-01-3 2023-12- 2024-03- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 ngineer) for the Hydrology Impact Weather, Floods an ultant Selection ntation 1 11 20 10 15 11 and DM Division of ID Head d Landslides Office SLMOI/CRES/ID-COL/C/IC/4 Component 5: Improving c 8 / Individual Consultant (Pr limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 oject Engineer) for Director tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 Irrigation Office at Colombo torm water infrastructure SLMOI/CRES/ID-KAN/C/IC/4 Component 5: Improving c 9 / Individual Consultant (Pr limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 oject Engineer) for Director tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 Irrigation Office at Kandy torm water infrastructure SLMOI/CRES/ID-MAN/C/IC/5 Component 5: Improving c 0 / Individual Consultant (Pr limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 oject Engineer) for Director tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 Irrigation Office at Mannar torm water infrastructure SLMOI/CRES/ID-POL/C/IC/5 Component 5: Improving c 1 / Individual Consultant (Pr limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 oject Engineer) for Director tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 Irrigation Office at Polonnar torm water infrastructure uwa SLMOI/CRES/ID-POL/C/IC/5 Component 5: Improving c 2 / Individual Consultant (Pr limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 oject Engineer) for the Con tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 struction and Development torm water infrastructure Division of ID Head Office SLMOI/CRES/ID/C/IC/53 / In Component 5: Improving c dividual Consultant (Project limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 Engineer) for the Construct tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 ion and Development Divisi torm water infrastructure on of ID Head Office SLMOI/CRES/PCT/C/IC/54 / Individual Consultant (Proje Component 4: Project Man Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 ct Engineer) for the Project agement ultant Selection ntation 5 11 04 25 30 26 Coordinating Unit of CResM PA SLMOI/CRES/PCT/C/IC/55 / Individual Consultant (Proje Component 4: Project Man Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 ct Engineer) for the Project agement ultant Selection ntation 5 11 04 25 30 26 Coordinating Unit of CResM PA SLMOI/CRES/DOM/C/IC/56 / Component 1: Forecasting Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- Individual Consultant (Proje IBRD / 89960 and Early Warning of High Post Open - National 1,500.00 0.00 ultant Selection ntation 5 11 04 25 30 26 ct Officer) for the Departm Impact Weather, Floods an ent of Meteorology d Landslides SLMOI/CRES/NBRO/C/IC/57 Component 1: Forecasting Individual Cons Under Impleme 2024-02-2 2023-12- 2024-04- 2024-05- 2024-06- 2024-12- / Individual Consultant (Proj IBRD / 89960 and Early Warning of High Post Open - National 1,500.00 0.00 ultant Selection ntation 2 11 11 02 06 03 ect Officer) for NBRO Impact Weather, Floods an d Landslides SLMOI/CRES/DMC/C/IC/58 / Component 1: Forecasting Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- Individual Consultant (Proje IBRD / 89960 and Early Warning of High Post Open - National 1,500.00 0.00 ultant Selection ntation 5 11 04 25 30 26 ct Officer) for DMC Impact Weather, Floods an d Landslides SLMOI/CRES/PCT/C/IC/59 / Component 4: Project Man Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- Individual Consultant (Proje IBRD / 89960 Post Open - National 1,500.00 0.00 agement ultant Selection ntation 5 11 04 25 30 26 ct Officer) for PCT of CResM PA SLMOI/CRES/PCT/C/IC/60 / Component 4: Project Man Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- Individual Consultant (Proje IBRD / 89960 Post Open - National 1,500.00 0.00 agement ultant Selection ntation 5 11 04 25 30 26 ct Officer) for PCT of CResM PA SLMOI/CRES/PCT/C/IC/61 / Component 4: Project Man Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- Individual Consultant (Proje IBRD / 89960 Post Open - National 1,500.00 0.00 agement ultant Selection ntation 4 11 03 24 29 25 ct Officer) for PCT of CResM PA SLMOI/CRES/ID-AMP/C/IC/6 Component 5: Improving c 2 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Ampara – tenance of irrigation and s ultant Selection ntation 5 10 04 25 30 26 DI Office torm water infrastructure SLMOI/CRES/ID-ANU/C/IC/6 Component 5: Improving c 3 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Anuradha tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 pura – DI office torm water infrastructure SLMOI/CRES/ID-BAD/C/IC/6 Component 5: Improving c 4 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Badulla – tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 DI Office torm water infrastructure Page 14 SLMOI/CRES/ID-BAD/C/IC/6 Component 5: Improving c 5 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Badulla – tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 DI Office torm water infrastructure SLMOI/CRES/ID-BAT/C/IC/6 Component 5: Improving c 6 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Batticaloa tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 – DI Office torm water infrastructure SLMOI/CRES/ID-COL/C/IC/6 Component 5: Improving c 7 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Colombo – tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 DI Office torm water infrastructure SLMOI/CRES/ID-COL/C/IC/6 Component 5: Improving c 8 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Colombo – tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 DI Office torm water infrastructure SLMOI/CRES/ID-GAL/C/IC/6 Component 5: Improving c 9 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Galle – DI tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 Office torm water infrastructure SLMOI/CRES/ID-HAM/C/IC/7 Component 5: Improving c 0 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Hambanto tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 ta – DI Office torm water infrastructure SLMOI/CRES/ID-KAN/C/IC/7 Component 5: Improving c 1 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Kandy – DI tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 Office torm water infrastructure SLMOI/CRES/ID-MAN/C/IC/7 Component 5: Improving c 2 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Mannar – tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 DI Office torm water infrastructure SLMOI/CRES/ID-MAN/C/IC/7 Component 5: Improving c 3 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Mannar – tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 DI Office torm water infrastructure SLMOI/CRES/ID-MON/C/IC/ Component 5: Improving c 74 / Individual Consultant ( limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 Draughtsman) for Monerag tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 ala – DI Office torm water infrastructure SLMOI/CRES/ID-MON/C/IC/ Component 5: Improving c 75 / Individual Consultant ( limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 Draughtsman) for Monerag tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 ala – DI Office torm water infrastructure SLMOI/CRES/ID-POL/C/IC/7 Component 5: Improving c 6 / Individual Consultant (D limate resilience and main Individual Cons 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 135.00 0.00 Canceled raughtsman) for Polonnaru tenance of irrigation and s ultant Selection 5 11 04 25 30 26 wa – DI Office torm water infrastructure SLMOI/CRES/ID-POL/C/IC/7 Component 5: Improving c 7 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Polonnaru tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 wa – DI Office torm water infrastructure SLMOI/CRES/ID-POL/C/IC/7 Component 5: Improving c 8 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Polonnaru tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 wa – DI Office torm water infrastructure SLMOI/CRES/ID-POL/C/IC/7 Component 5: Improving c 9 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Polonnaru tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 wa – DI Office torm water infrastructure SLMOI/CRES/ID-PUT/C/IC/8 Component 5: Improving c 0 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Puttalam – tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 DI Office torm water infrastructure SLMOI/CRES/ID-PUT/C/IC/8 Component 5: Improving c 1 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Puttalam – tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 DI Office torm water infrastructure SLMOI/CRES/ID-TRI/C/IC/82 Component 5: Improving c / Individual Consultant (Dra limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 135.00 0.00 ughtsman) for Trincomalee tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 – DI Office torm water infrastructure SLMOI/CRES/ID-TRI/C/IC/83 Component 5: Improving c / Individual Consultant (Dra limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 ughtsman) for Trincomalee tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 – DI Office torm water infrastructure SLMOI/CRES/ID/C/IC/84 / In Component 5: Improving c dividual Consultant (Draug limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 htsman) for Construction a tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 nd Development Division of torm water infrastructure ID - Head Office SLMOI/CRES/ID/C/IC/85 / In Component 5: Improving c dividual Consultant (Draug limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 htsman) for Construction a tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 nd Development Division of torm water infrastructure ID - Head Office SLMOI/CRES/ID/C/IC/86 / In Component 5: Improving c dividual Consultant (Draug limate resilience and main Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 htsman) for Construction a tenance of irrigation and s ultant Selection ntation 5 11 04 25 30 26 nd Development Division of torm water infrastructure ID - Head Office SLMOI/CRES/PCT/C/IC/87 / Individual Consultant (Drau Component 4: Project Man Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 ghtsman) for the Project Co agement ultant Selection ntation 5 11 04 25 30 26 ordinating Unit of CResMPA SLMOI/CRES/PCT/C/IC/88 / Individual Consultant (Drau Component 4: Project Man Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 ghtsman) for the Project Co agement ultant Selection ntation 5 11 04 25 30 26 ordinating Unit of CResMPA SLMOI/CRES/ID/C/IC/89 / In Component 1: Forecasting dividual Consultant (Hydrol and Early Warning of High Individual Cons Under Impleme 2024-02-1 2023-12- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,275.00 0.00 ogy Assistants) for the Hyd Impact Weather, Floods an ultant Selection ntation 5 11 04 25 30 26 rology and Disaster Manag d Landslides ement Division of ID SLMOI/CRES/ID/C/IC/90 / In Component 1: Forecasting dividual Consultant (Hydrol and Early Warning of High Individual Cons Under Impleme 2024-02-2 2023-12- 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 1,275.00 0.00 ogy Assistants) for the Hyd Impact Weather, Floods an ultant Selection ntation 9 11 18 09 13 10 rology and Disaster Manag d Landslides ement Division of ID SLMOI/CRES/ID/C/IC/91 / In Component 1: Forecasting dividual Consultant (Hydrol and Early Warning of High Individual Cons Under Impleme 2024-02-2 2023-12- 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 1,275.00 0.00 ogy Assistants) for the Hyd Impact Weather, Floods an ultant Selection ntation 9 11 18 09 13 10 rology and Disaster Manag d Landslides ement Division of ID SLMOI/CRES/PCT/C/IC/92 / Individual Consultant (Tech Component 4: Project Man Individual Cons Under Impleme 2024-02-2 2023-12- 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 1,275.00 0.00 nical Assistants) for the Pro agement ultant Selection ntation 9 11 18 09 13 10 ject Coordinating Unit of CR esMPA SLMOI/CRES/PCT/C/IC/93 / Individual Consultant (Tech Component 4: Project Man Individual Cons Under Impleme 2024-02-2 2023-12- 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 1,275.00 0.00 nical Assistants) for the Pro agement ultant Selection ntation 9 11 18 09 13 10 ject Coordinating Unit of CR esMPA SLMOI/CRES/PCT/C/IC/94 / Individual Consultant (Tech Component 4: Project Man Individual Cons Under Impleme 2024-02-2 2023-12- 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 1,275.00 0.00 nical Assistants) for the Pro agement ultant Selection ntation 9 11 18 09 13 10 ject Coordinating Unit of CR esMPA SLMOI/CRES/PCT/C/IC/95 / Individual Consultant (Tech Component 4: Project Man Individual Cons Under Impleme 2024-02-2 2023-12- 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 1,275.00 0.00 nical Assistants) for the Pro agement ultant Selection ntation 9 11 18 09 13 10 ject Coordinating Unit of CR esMPA SLMOI/CRES/PCT/C/DS/43 / Hiring of a Senior Procurem Component 4: Project Man Under Impleme 2024-01-1 2023-12- 2024-01- 2024-03- 2024-09- IBRD / 89960 Post Direct Selection Direct - National 6,570.00 0.00 ent Consultant for the Proc agement ntation 0 22 20 25 21 urement and Contract Man agement Division of CResM PA SLMOI/CRES/ID-COL/C/IC/9 Component 5: Improving c 6 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Colombo – tenance of irrigation and s ultant Selection ntation 5 19 04 25 30 26 DI Office torm water infrastructure SLMOI/CRES/ID-COL/C/IC/9 Component 5: Improving c 7 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Colombo – tenance of irrigation and s ultant Selection ntation 5 19 04 25 30 26 DI Office torm water infrastructure SLMOI/CRES/ID-KIL/C/IC/98 Component 5: Improving c / Individual Consultant (Dra limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 ughtsman) for Kilinochchiy tenance of irrigation and s ultant Selection ntation 5 16 04 25 30 26 a – DI Office torm water infrastructure SLMOI/CRES/ID-MON/C/IC/ Component 5: Improving c 99 / Individual Consultant ( limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 Draughtsman) for Monarag tenance of irrigation and s ultant Selection ntation 5 08 04 25 30 26 ala – DI Office torm water infrastructure SLMOI/CRES/PCT/C/IC/100 / Individual Consultant (Proj Component 4: Project Man Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,065.50 0.00 ect Engineer) for the Projec agement ultant Selection ntation 5 10 04 25 30 26 t Coordinating Unit of CRes MPA SLMOI/CRES/ID-KIL/C/IC/10 Component 5: Improving c 1 / Individual Consultant (Pr limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 oject Engineer) for Director tenance of irrigation and s ultant Selection ntation 5 22 04 25 30 26 Irrigation Office at Kilinochc torm water infrastructure hi SLMOI/CRES/ID-MAN/C/IC/1 Component 5: Improving c 02 / Individual Consultant ( limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 Project Engineer) for Direct tenance of irrigation and s ultant Selection ntation 5 22 04 25 30 26 or Irrigation Office at Mann torm water infrastructure ar SLMOI/CRES/ID-KIL/C/IC/10 Component 5: Improving c 3 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Kilinochchi tenance of irrigation and s ultant Selection ntation 5 16 04 25 30 26 – DI Office torm water infrastructure SLMOI/CRES/ID-MAN/C/IC/1 Component 5: Improving c 04 / Individual Consultant ( limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,500.00 0.00 Engineering Assistant) for tenance of irrigation and s ultant Selection ntation 5 05 04 25 30 26 Mannar – DI Office torm water infrastructure SLMOI/CRES/DOM/C/IC/106 Component 5: Improving c / Individual Consultant (Ma limate resilience and main Individual Cons Pending Imple 2024-02-1 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,200.00 0.00 nagement Assistant) for th tenance of irrigation and s ultant Selection mentation 5 04 25 30 26 e Department of Meteorolo torm water infrastructure gy SLMOI/CRES/ID/C/IC/109 / I Component 5: Improving c ndividual Consultant (Mana limate resilience and main Individual Cons Pending Imple 2024-02-1 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,200.00 0.00 gement Assistant) for ID - C tenance of irrigation and s ultant Selection mentation 5 04 25 30 26 om 1 torm water infrastructure SLMOI/CRES/ID/C/IC/110 / I Component 5: Improving c ndividual Consultant (Mana limate resilience and main Individual Cons Pending Imple 2024-02-1 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,200.00 0.00 gement Assistant) for ID - C tenance of irrigation and s ultant Selection mentation 5 04 25 30 26 om 2 & 5 torm water infrastructure SLMOI/CRES/ID/C/IC/111 / I Component 5: Improving c ndividual Consultant (Mana limate resilience and main Individual Cons Pending Imple 2024-02-1 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,200.00 0.00 gement Assistant) for ID - tenance of irrigation and s ultant Selection mentation 5 04 25 30 26 Hydrology Department torm water infrastructure SLMOI/CRES/ID-MAN/C/IC/1 Component 5: Improving c 05 / Individual Consultant ( limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,500.00 0.00 Engineering Assistant) for tenance of irrigation and s ultant Selection ntation 5 05 04 25 30 26 Mannar – DI Office torm water infrastructure SLMOI/CRES/ID-POL/C/IC/7 Component 5: Improving c 6-2 / Individual Consultant ( limate resilience and main Individual Cons Pending Imple 2024-02-1 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 Draughtsman) for Polonnar tenance of irrigation and s ultant Selection mentation 5 04 25 30 26 uwa – DI Office torm water infrastructure SLMOI/CRES/ID-KIL/C/IC/11 Component 5: Improving c 3 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Kilinochchi tenance of irrigation and s ultant Selection ntation 5 16 04 25 30 26 ya – DI Office torm water infrastructure SLMOI/CRES/ID-KIL/C/IC/11 Component 5: Improving c 4 / Individual Consultant (D limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Kilinochchi tenance of irrigation and s ultant Selection ntation 5 16 04 25 30 26 ya – DI Office torm water infrastructure SLMOI/CRES/ID-JAF/C/IC/11 Component 5: Improving c 5 / Individual Consultant (D limate resilience and main Individual Cons Pending Imple 2024-02-1 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,350.00 0.00 raughtsman) for Jaffna – DI tenance of irrigation and s ultant Selection mentation 5 04 25 30 26 Office torm water infrastructure SLMOI/CRES/ID-KIL/C/IC/11 Component 5: Improving c 2 / Individual Consultant (Pr limate resilience and main Individual Cons Under Impleme 2024-02-1 2024-01- 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 2,100.00 0.00 oject Engineer) for Director tenance of irrigation and s ultant Selection ntation 5 22 04 25 30 26 Irrigation Office at Kilinochc torm water infrastructure hi SLMOI/CRES/ID-RAT/C/IC/1 Component 5: Improving c 26 / Individual Consultant ( limate resilience and main Individual Cons Pending Imple 2024-02-2 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 1,500.00 0.00 Engineering Assistant) for tenance of irrigation and s ultant Selection mentation 9 18 09 13 10 Rathnapura – DI Office torm water infrastructure SLMOI/CRES/ID-POL/C/IC/1 Component 5: Improving c 27 / Individual Consultant ( limate resilience and main Individual Cons Under Impleme 2024-02-2 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 1,500.00 0.00 Engineering Assistant) for P tenance of irrigation and s ultant Selection ntation 9 18 09 13 10 olonnaruwa – DI Office torm water infrastructure SLMOI/CRES/PCT/C/IC/130 / Individual Consultant (Eng Component 4: Project Man Individual Cons Pending Imple 2024-02-2 2024-04- 2024-05- 2024-06- 2024-12- IBRD / 89960 Post Open - National 1,500.00 0.00 ineering Assistant) for the agement ultant Selection mentation 9 18 09 13 10 Project Coordinating Unit of CResMPA SLMOI/CRES/NBRO/C/DS/1 21 / Consultancy Services f Component 1: Forecasting or the Development of a M and Early Warning of High Direct - Internati 2024-02-2 2024-03- 2024-05- 2025-05- ulti-Hazard Early Warning S IBRD / 89960 Post Direct Selection 500,000.00 0.00 Canceled Impact Weather, Floods an onal 9 10 14 14 ystem (MHEWS) by upscali d Landslides ng the MOBILISE Platform u nder CResMPA by hiring St anford University, UK SLMOI/CRES/DMC/C/IC/107 Component 5: Improving c / Individual Consultant (Ma limate resilience and main Individual Cons 2024-02-1 2024-04- 2024-04- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,200.00 0.00 Canceled nagement Assistant) for D tenance of irrigation and s ultant Selection 5 04 25 30 26 MC torm water infrastructure SLMOI/CRES/DMC/C/DS/39 Component 1: Forecasting / Individual Consultant (Re and Early Warning of High Individual Cons 2023-12-1 2023-11- 2023-12- 2024-01- 2024-02- 2025-02- IBRD / 89960 Post Direct - National 3,200.00 0.00 Canceled mote Sensing and GIS) for Impact Weather, Floods an ultant Selection 5 13 25 15 19 18 Data Base Development an d Landslides d Analysis SLMOI/CRES/DMC/C/IC/32 / Individual consultant for En Component 1: Forecasting hancing Institutional Capac and Early Warning of High Individual Cons 2024-02-0 2024-02- 2024-03- 2024-04- 2025-02- IBRD / 89960 Post Limited 16,200.00 0.00 Canceled ity and Existing Information Impact Weather, Floods an ultant Selection 9 14 06 10 04 Systems for Disaster Risk R d Landslides eduction and Response at Disaster Management Cent re SLMOI/CRES/DMC/C/IC/33 / Component 1: Forecasting Individual Consultant (Rem and Early Warning of High Individual Cons 2023-09-2 2023-10- 2023-10- 2023-10- 2023-11- 2024-10- ote Sensing and GIS) for Es IBRD / 89960 Post Limited 3,200.00 0.00 Canceled Impact Weather, Floods an ultant Selection 2 05 17 22 01 31 tablishing the Exposure an d Landslides d Vulnerability Database at Disaster Management Cent re SLMOI/CRES/ID/C/DS/120 / WMO Technical Assistant fo Component 1: Forecasting r Component 1 of CResMPA and Early Warning of High Direct - Internati 2024-03-2 2024-05- 2024-04- 2024-06- 2026-12- IBRD / 89960 Prior Direct Selection 8,000,000.00 0.00 Under Review for Development of Forecas Impact Weather, Floods an onal 5 06 04 08 31 ting and Early Warning of H d Landslides igh Impact Weather, Floods , and Landslides in Sri Lank a SLMOI/CRES/PCT/C/IC/128 / Individual Consultant (Ma Component 4: Project Man Individual Cons Limited - Nationa Pending Imple 2024-03-2 2024-04- 2024-04- 2024-04- 2024-10- IBRD / 89960 Post 1,200.00 0.00 nagement Assistant) for th agement ultant Selection l mentation 9 03 08 27 24 e Project Coordinating Unit of CResMPA SLMOI/CRES/PCT/C/IC/129 / Individual Consultant (Ma Component 4: Project Man Individual Cons Limited - Nationa Pending Imple 2024-03-2 2024-04- 2024-04- 2024-04- 2024-10- IBRD / 89960 Post 1,200.00 0.00 nagement Assistant) for th agement ultant Selection l mentation 9 03 08 27 24 e Project Coordinating Unit of CResMPA SLMOI/CRES/PCT/C/IC/131 / Individual Consultant for F Component 4: Project Man Individual Cons Pending Imple 2024-04-2 2024-05- 2024-05- 2024-05- 2024-11- IBRD / 89960 Post Open - National 1,100.00 0.00 inancial Database and MIS agement ultant Selection mentation 5 14 19 30 26 Operator for Accounts Divis ion of CResMPA SLMOI/CRES/NBRO/C/IC/10 Component 1: Forecasting Individual Cons Pending Imple 2024-04-3 2024-05- 2024-05- 2024-05- 2024-11- 8 / Individual Consultant (M IBRD / 89960 and Early Warning of High Post Open - National 1,200.00 0.00 ultant Selection mentation 0 12 19 30 26 anagement Assistant) for N Impact Weather, Floods an BRO d Landslides SLMOI/CRES/PCT/C/IC/132 Component 4: Project Man Individual Cons Pending Imple 2024-05-0 2024-05- 2024-05- 2024-05- 2026-05- / Hiring of a Short-term IT a IBRD / 89960 Post Open - National 8,400.00 0.00 agement ultant Selection mentation 6 17 19 21 21 nd GIS Consultant for CRes MPA SLMOI/CRES/PCT/C/IC/133 Component 4: Project Man Individual Cons Pending Imple 2024-05-0 2024-05- 2024-05- 2024-05- 2024-11- / Individual Consultant (Env IBRD / 89960 Post Open - National 2,000.00 0.00 agement ultant Selection mentation 6 17 19 21 17 ironmental Safeguard) for P CT-CResMPA SLMOI/CRES/PCT/C/IC/134 Component 4: Project Man Individual Cons Pending Imple 2024-05-0 2024-05- 2024-05- 2024-05- 2024-11- / Individual Consultant (Env IBRD / 89960 Post Open - National 2,000.00 0.00 agement ultant Selection mentation 8 19 21 23 19 ironmental Safeguard) for P CT-CResMPA SLMOI/CRES/PCT/C/IC/136 Component 4: Project Man Individual Cons Pending Imple 2024-05-2 2024-05- 2024-06- 2024-06- 2025-06- / Individual Consultant (Fiel IBRD / 89960 Post Open - National 3,600.00 0.00 agement ultant Selection mentation 0 31 02 04 04 d Monitoring Safeguard Ass istant) for CResMPA Page 15 SLMOI/CRES/PCT/C/IC/135 / Hiring of an Individual Co Component 4: Project Man Individual Cons Pending Imple 2024-05-2 2024-06- 2024-06- 2024-06- 2025-06- IBRD / 89960 Post Open - National 6,400.00 0.00 nsultant as Contract Manag agement ultant Selection mentation 7 13 15 16 16 ement Specialist for the CR esMPA-PCT SLMOI/CRES/PCT/C/IC/137 / Hiring of an Individual Co Component 4: Project Man Individual Cons Pending Imple 2024-05-2 2024-06- 2024-06- 2024-06- 2025-06- nsultant as Administrative IBRD / 89960 Post Open - National 2,800.00 0.00 agement ultant Selection mentation 7 07 09 11 11 Assistant for Office Manage ment and Coordination to t he CResMPA-PCT SLMOI/CRES/PCT/C/IC/138 / Hiring of an Individual Co Component 4: Project Man Individual Cons Pending Imple 2024-05-2 2024-06- 2024-06- 2024-06- 2025-06- nsultant as Administrative IBRD / 89960 Post Open - National 2,800.00 0.00 agement ultant Selection mentation 7 07 09 11 11 Assistant for Office Manage ment and Coordination to t he CResMPA-PCT SLMOI/CRES/ID/C/CQS/29- 1 / Hiring an Individual Con Component 2: Flood Risk Individual Cons Pending Imple 2024-06-1 2024-07- 2024-07- 2024-07- 2025-07- sultant as a Hydrology, Hyd IBRD / 89960 Mitigation Investments in t Post Open - National 15,000.00 0.00 ultant Selection mentation 0 02 16 18 18 raulics and Reservoir Opera he lower Kelani basin tion Expert for the Dam Saf ety Review Panel under CR esMPA SLMOI/CRES/ID/C/CQS/29- 2 / Hiring an Individual Con Component 2: Flood Risk Individual Cons Pending Imple 2024-06-1 2024-07- 2024-07- 2024-07- 2025-07- sultant as a Geotechnical E IBRD / 89960 Mitigation Investments in t Post Open - National 7,500.00 0.00 ultant Selection mentation 0 02 16 18 18 ngineering Expert for the D he lower Kelani basin am Safety Review Panel un der CResMPA SLMOI/CRES/ID/C/CQS/29- 3 / Hiring an Individual Con Component 2: Flood Risk Individual Cons Pending Imple 2024-06-1 2024-07- 2024-07- 2024-07- 2025-07- sultant as Structural Engine IBRD / 89960 Mitigation Investments in t Post Open - National 14,000.00 0.00 ultant Selection mentation 0 02 16 18 18 er/Dam Design Expert for t he lower Kelani basin he Dam Safety Review Pan el under CResMPA SLMOI/CRES/ID/C/CQS/29- 4 / Hiring an Individual Con Component 2: Flood Risk Individual Cons Pending Imple 2024-06-1 2024-07- 2024-07- 2024-07- 2025-07- sultant as an Electro-Mecha IBRD / 89960 Mitigation Investments in t Post Open - National 7,500.00 0.00 ultant Selection mentation 0 02 16 18 18 nical and Instruments Expe he lower Kelani basin rt for the Dam Safety Revie w Panel under CResMPA SLMOI/CRES/ID/C/CQS/29- Component 2: Flood Risk 5 / Hiring an Individual Con Individual Cons Pending Imple 2024-06-1 2024-07- 2024-07- 2024-07- 2025-07- IBRD / 89960 Mitigation Investments in t Post Open - National 7,500.00 0.00 sultant as a Hydro-Power E ultant Selection mentation 0 02 16 18 18 he lower Kelani basin xpert for the Dam Safety R eview Panel under CResMP A SLMOI/CRES/ID/C/CQS/29- 6 / Hiring an Individual Con Component 2: Flood Risk Individual Cons Pending Imple 2024-06-1 2024-07- 2024-07- 2024-07- 2025-07- sultant as Dam Operational IBRD / 89960 Mitigation Investments in t Post Open - National 5,850.00 0.00 ultant Selection mentation 0 02 16 18 18 and Maintenance Expert for he lower Kelani basin the Dam Safety Review Pan el under CResMPA SLMOI/CRES/ID/C/CQS/29- 7 / Hiring an Individual Con Component 2: Flood Risk Individual Cons Pending Imple 2024-06-1 2024-07- 2024-07- 2024-07- 2025-07- sultant as Landslide Mitigat IBRD / 89960 Mitigation Investments in t Post Open - National 6,000.00 0.00 ultant Selection mentation 0 02 16 18 18 ion Expert for the Dam Saf he lower Kelani basin ety Review Panel under CR esMPA SLMOI/CRES/ID/C/CQS/29- 8 / Hiring an Individual Con Component 2: Flood Risk Individual Cons Pending Imple 2024-06-1 2024-07- 2024-07- 2024-07- 2025-07- sultant as a Social Safegua IBRD / 89960 Mitigation Investments in t Post Open - National 7,000.00 0.00 ultant Selection mentation 0 02 16 18 18 rd Expert and for the Dam he lower Kelani basin Safety Review Panel under CResMPA SLMOI/CRES/ID/C/CQS/29- 9 / Hiring an Individual Con Component 2: Flood Risk Individual Cons Pending Imple 2024-06-1 2024-07- 2024-07- 2024-07- 2025-07- sultant as an Environmenta IBRD / 89960 Mitigation Investments in t Post Open - National 7,000.00 0.00 ultant Selection mentation 0 02 16 18 18 l Safeguard Expert for the he lower Kelani basin Dam Safety Review Panel u nder CResMPA Page 16