The World Bank Implementation Status & Results Report Electricity Transmission Network Improvement Project (P146199) Electricity Transmission Network Improvement Project (P146199) EUROPE AND CENTRAL ASIA | Armenia | Energy & Extractives Global Practice | IBRD/IDA | Investment Project Financing | FY 2015 | Seq No: 16 | ARCHIVED on 06-Jun-2023 | ISR55657 | Implementing Agencies: High Voltage Electric Networks, Republic of Armenia, Yerevan Thermal Power Plant Key Dates Key Project Dates Bank Approval Date: 30-Mar-2015 Effectiveness Date: 21-Sep-2015 Planned Mid Term Review Date: 20-Sep-2017 Actual Mid-Term Review Date: 05-Dec-2017 Original Closing Date: 31-Dec-2019 Revised Closing Date: 31-Dec-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed project development objectives (PDO) are to improve the reliability of the power transmission network and system management, and support the Borrower's efforts in ensuring adequate electricity supply Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Project Development Objective (If project is formally restructured) The proposed project development objective (PDO) is to improve the reliability of the power transmission network. Components Table Name Component 1: Strengthening of the power transmission network:(Cost $49.71 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The rehabilitation of the YTPC and Ashnak substations has been completed. HVEN is considering a possible 5-month contract extension for the Ararat-2 substation (the current closing date is May 2024) to provide a sufficient buffer to mitigate the risks of possible delays in delivery of specific equipment caused by unforeseen events (including the impacts of Russia’s invasion of Ukraine) would lead to another extension request. The meeting of the development objective depends on the progress of works at Ararat-2 substation. 6/6/2023 Page 1 of 5 The World Bank Implementation Status & Results Report Electricity Transmission Network Improvement Project (P146199) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Low Low Macroeconomic Substantial Moderate Moderate Sector Strategies and Policies Substantial Low Low Technical Design of Project or Program Moderate Low Low Institutional Capacity for Implementation and Substantial Moderate Moderate Sustainability Fiduciary Substantial Moderate Moderate Environment and Social Moderate Moderate Moderate Stakeholders Low Low Low Other -- Moderate Moderate Overall Substantial Moderate Moderate Results PDO Indicators by Objectives / Outcomes Improvement of the reliability of the power transmission network IN01274672 ►Equipment failures per year in target substations (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 10.00 3.00 3.00 2.00 Date 30-Dec-2014 16-Dec-2022 31-Mar-2023 31-Dec-2023 The current value (3 outages) refers to 2022. Comments: IN01274673 ►Average interruption frequency per year in the project area (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.11 0.01 0.44 0.09 Date 30-Dec-2013 16-Dec-2022 31-Dec-2022 31-Dec-2023 6/6/2023 Page 2 of 5 The World Bank Implementation Status & Results Report Electricity Transmission Network Improvement Project (P146199) The indicator measures the average interruption frequency per year in the project area (defined as the entire country, but only outages related to the substations rehabilitated under the project need to be Comments: considered). The current value refers to 2022. The data for the sub-indicator measuring the number of customers is as of December 31, 2022. IN01274674 Customers served in the project area (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 1,040,000.00 1,059,724.00 1,073,374.00 1,040,000.00 IN01274675 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 2,984,000.00 2,963,234.00 2,979,200.00 2,993,000.00 Date 30-Dec-2014 16-Dec-2022 31-Dec-2022 31-Dec-2023 The latest data from the Statistical Committee of Armenia is based on Population Census in 2023. Comments: IN01274721 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 48.60 52.97 52.77 48.60 Intermediate Results Indicators by Components Component 1: Strengthening of the power transmission network IN01274722 ►Total number of substations rehabilitated under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2.00 2.00 3.00 Date 30-Dec-2014 16-Dec-2022 31-May-2023 31-Dec-2023 IN01274723 ►Percent of registered project related grievances (disaggregated by gender) responded to within stipulated service standards for response times (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 100.00 Date 30-Dec-2014 16-Dec-2022 31-Mar-2023 31-Dec-2023 Performance-Based Conditions 6/6/2023 Page 3 of 5 The World Bank Implementation Status & Results Report Electricity Transmission Network Improvement Project (P146199) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P146199 IBRD-84950 Effective USD 52.00 39.86 12.14 27.51 12.35 69% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P146199 IBRD-84950 Effective 30-Mar-2015 08-Apr-2015 21-Sep-2015 31-Dec-2019 31-Dec-2023 Cumulative Disbursements Restructuring History Level 1 Approved on 05-Jun-2017 ,Level 2 Approved on 19-Dec-2019 ,Level 2 Approved on 21-Dec-2020 Related Project(s) There are no related projects. 6/6/2023 Page 4 of 5 The World Bank Implementation Status & Results Report Electricity Transmission Network Improvement Project (P146199) 6/6/2023 Page 5 of 5