PROCUREMENT PLAN (Textual Part) Project information: Country: Bolivia. Project name: INNOVATION FOR RESILIENT FOOD SYSTEMS (ALIANZAS RURALES – PAR III) PROJECT P-number: P175672 Project Implementation agency: EMPODERAR Date of the Procurement Plan: November 21, 2022 Period covered by this Procurement Plan: 18 months Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: Not Applicable Leased Not Applicable. Procurement of Second Hand Goods Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not Applicable Works: Not Applicable PROCUREMENT Bolivia : Innovation for Resilient Food Systems (Alianzas Rurales - PAR III) Project PLAN General Information Country: Bolivia 2022-11-21 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2024-06-04 if none) Project ID: P175672 GPN Date: Project Name: Innovation for Resilient Food Systems (Alianzas Rurales - PAR III) Project Loan / Credit No: IBRD / 94370 EMPODERAR Program Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit N Market Approac Procurement Pr Prequalification High SEA/SH Process S Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Contract Comple Description Component Review Type Method Document Typ Amount (U mount (U t and Recommendati Signed Contract o. h ocess (Y/N) Risk tatus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes tion e S$) S$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned BO-EMPODERAR-428240-CW Solicitud de Cotiz -RFQ / CONSTRUCCIÓN SISTE 2. Support to Community an Solicitud de cotiza Single Stage - One ación (no docume Ejecución p 2025-01-1 IBRD / 94370 Posterior Open - National 171,717.80 0.00 2024-05-22 2024-07-17 MA DE RIEGO TECNIFICADO S d Productive Alliances ciones Envelope nto estándar del endiente 3 INDICATO AGRARIO 14 DE SE Banco) PTIEMBRE (SICAYA) BO-EMPODERAR-428342-CW Solicitud de Cotiz -RFQ / CONSTRUCCION SISTE 2. Support to Community an Solicitud de cotiza Single Stage - One ación (no docume Ejecución p 2025-01-1 IBRD / 94370 Posterior Open - National 106,434.12 0.00 2024-05-22 2024-07-17 MA DE RIEGO TECNIFICADO d Productive Alliances ciones Envelope nto estándar del endiente 3 COMUNIDAD HUERTA HUASA Banco) (TOLATA) BO-EMPODERAR-428345-CW Solicitud de Cotiz -RFQ / CONSTRUCCION SISTE 2. Support to Community an Solicitud de cotiza Single Stage - One ación (no docume Ejecución p 2025-01-1 IBRD / 94370 Posterior Open - National 183,449.76 0.00 2024-05-22 2024-07-17 MA DE RIEGO TECNIFICADO S d Productive Alliances ciones Envelope nto estándar del endiente 3 OTASI (VILA VILA) Banco) Documento de Ad BO-EMPODERAR-428376-CW quisiciones con e -RFB / CONSTRUCCION SISTE 2. Support to Community an Solicitud de oferta Single Stage - One nfoque nacional - Ejecución p 2025-03-0 IBRD / 94370 Posterior Open - National 269,857.02 0.00 2024-05-16 2024-05-21 2024-07-02 2024-08-01 2024-09-05 MA DE RIEGO VINCUNTAYA – d Productive Alliances s Envelope Proceso de un so endiente 4 CORACABA (TAPACARI) bre (No documen to estándar del B anco) BO-EMPODERAR-428355-CW Solicitud de Cotiz -RFQ / AMPLIACION DEL SIST 2. Support to Community an Solicitud de cotiza Single Stage - One ación (no docume Ejecución p 2025-01-1 IBRD / 94370 Posterior Open - National 72,733.14 0.00 2024-05-22 2024-07-17 EMA DE RIEGO UCHUCHI KAN d Productive Alliances ciones Envelope nto estándar del endiente 3 CHA EN EL MUNICIPIO DE TIR Banco) AQUE Solicitud de Cotiz BO-EMPODERAR-428357-CW 2. Support to Community an Solicitud de cotiza Single Stage - One ación (no docume Ejecución p 2025-01-1 -RFQ / CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Open - National 204,742.79 0.00 2024-05-22 2024-07-17 d Productive Alliances ciones Envelope nto estándar del endiente 3 TE PEATONAL SICAYA CHICO Banco) (SICAYA) Solicitud de Cotiz BO-EMPODERAR-428358-CW 2. Support to Community an Solicitud de cotiza Single Stage - One ación (no docume Ejecución p 2025-01-1 -RFQ / CONSTRUCCION PUEN IBRD / 94370 Posterior Open - National 133,020.71 0.00 2024-05-22 2024-07-17 d Productive Alliances ciones Envelope nto estándar del endiente 3 TE VEHICULAR LLALLAGUANI Banco) (ANZALDO) Solicitud de Cotiz BO-EMPODERAR-428462-CW 2. Support to Community an Solicitud de cotiza Single Stage - One ación (no docume Ejecución p 2025-01-1 -RFQ / CONSTRUCCIÓN PUEN IBRD / 94370 Posterior Open - National 215,838.36 0.00 2024-05-22 2024-07-17 d Productive Alliances ciones Envelope nto estándar del endiente 3 TE VEHICULAR HUALLPERO A Banco) LTO (CLIZA) Solicitud de Cotiz BO-EMPODERAR-428463-CW 2. Support to Community an Solicitud de cotiza Single Stage - One ación (no docume Ejecución p 2025-01-1 -RFQ / CONSTRUCCION PUEN IBRD / 94370 Posterior Open - National 158,320.32 0.00 2024-05-22 2024-07-17 d Productive Alliances ciones Envelope nto estándar del endiente 3 TE VEHICULAR PUCARA MAY Banco) U (VILA VILA) BO-EMPODERAR-428465-CW Solicitud de Cotiz -RFQ / CONSTRUCCION DOS 2. Support to Community an Solicitud de cotiza Single Stage - One ación (no docume Ejecución p 2025-01-1 IBRD / 94370 Posterior Open - National 246,493.56 0.00 2024-05-22 2024-07-17 PUENTES VEHICULARES KOA d Productive Alliances ciones Envelope nto estándar del endiente 3 RI Y MAYUN PUNKU (TIRAQUE Banco) ) Solicitud de Cotiz BO-EMPODERAR-428466-CW 2. Support to Community an Solicitud de cotiza Single Stage - One ación (no docume Ejecución p 2025-01-1 -RFQ / CONSTRUCCION SISTE IBRD / 94370 Posterior Open - National 192,235.34 0.00 2024-05-22 2024-07-17 d Productive Alliances ciones Envelope nto estándar del endiente 3 MA DE RIEGO CKARI MAYU Banco) GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit N Market Approac Procurement Pr Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion o. h ocess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351827-GO Solicitud de oferta Open - Internationa Single Stage - One -RFQ / COMPRA DE 29 VEHIC IBRD / 94370 3. Project Management Posterior 1,185,161.00 0.00 En ejecución 2023-03-24 2023-06-09 2023-03-29 2023-07-07 2023-05-18 2023-07-28 2023-06-17 2023-07-14 2023-07-22 2023-10-08 s l Envelope ULOS CAMIONETAS DOBRE C ABINA 4x4 BO-EMPODERAR-352389-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE TONER PA IBRD / 94370 3. Project Management Posterior Open - National 28,871.00 0.00 Finalizado 2023-03-29 2023-05-24 2023-05-02 2023-08-30 ciones Envelope RA IMPRESORAS Y FOTOCOPI AS DEL PAR III BO-EMPODERAR-352390-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE MATERIAL IBRD / 94370 3. Project Management Posterior Open - National 14,296.00 0.00 Finalizado 2023-03-29 2023-05-24 2023-05-02 2023-08-30 2023-05-05 ciones Envelope DE ESCRITORIO PARA OFICIN AS DEL PAR III BO-EMPODERAR-354355-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE LLANTAS IBRD / 94370 3. Project Management Posterior Open - National 21,430.00 0.00 Finalizado 2023-04-05 2023-05-31 2023-05-02 2023-07-31 ciones Envelope PARA VEHICULOS DEL EMPO DERAR PAR BO-EMPODERAR-360045-GO Solicitud de oferta Single Stage - One -RFB / ADQUISICION DE EQUI IBRD / 94370 3. Project Management Posterior Open - National 223,055.00 0.00 Finalizado 2023-05-03 2023-05-16 2023-05-08 2023-06-19 2023-06-19 2023-07-19 2023-06-30 2023-08-23 2023-11-30 2023-08-29 s Envelope POS DE COMPUTACION Y TAB LETS - PAR III BO-EMPODERAR-360047-GO Solicitud de oferta Single Stage - One -RFB / ADQUISICION DE IMPR IBRD / 94370 3. Project Management Posterior Open - National 139,263.00 0.00 Finalizado 2023-05-03 2023-05-24 2023-05-08 2023-06-19 2023-06-26 2023-07-19 2023-07-13 2023-08-23 2023-11-30 2023-09-25 s Envelope ESORAS, PROYECTORES Y ES CANER - PAR III BO-EMPODERAR-360049-GO -RFQ / COMPRA DE EQUIPO D E SONIDO MOVIL (PARLANTE) Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 24,200.00 0.00 Finalizado 2023-05-08 2023-07-03 2023-06-26 2023-09-30 2023-07-07 Y MICROFONOS PARA DIFUSI ciones Envelope ON DE LOS COMPONENTES D EL PAR III, EN FERIAS, TALLE RES Y OTROS. BO-EMPODERAR-360050-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE HERRAMI IBRD / 94370 3. Project Management Posterior Open - National 6,597.00 0.00 Finalizado 2023-05-08 2023-07-03 2023-05-31 2023-07-31 ciones Envelope ENTAS MENORES - PAR III BO-EMPODERAR-361175-GO -RFB / ADQUISICION DE EQUI Solicitud de oferta Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 56,692.00 0.00 Finalizado 2023-05-10 2023-06-23 2023-05-15 2023-06-26 2023-07-24 2023-07-26 2023-07-26 2023-08-30 2023-08-21 2023-10-31 2023-09-11 PO DE FILMACION Y FOTOGR s Envelope AFIA PARA EL PAR III BO-EMPODERAR-363746-GO -RFQ / COMPRA DE PAPEL PA Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 7,690.00 0.00 Finalizado 2023-05-30 2023-07-25 2023-06-19 2023-09-30 2023-06-23 RA LA OFICINA NACIONAL Y ciones Envelope DEPARTAMENTALES - PAR III BO-EMPODERAR-363747-GO -RFQ / COMPRA DE CHAMARR Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 13,047.00 0.00 Finalizado 2023-05-30 2023-07-25 2023-12-13 2023-09-30 2023-12-21 AS (PRENDAS DE VESTIR) INS ciones Envelope TITUCIONALES PARA EL PAR I II BO-EMPODERAR-363750-GO -RFB / ADQUISICION DE FOTO COPIADORAS PAR ALA UNIDA Solicitud de oferta Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 112,513.00 0.00 Finalizado 2023-05-25 2023-06-09 2023-05-30 2023-07-11 2023-07-10 2023-08-10 2023-07-14 2023-09-14 2023-12-22 2023-10-18 D DE COORDINACION NACIO s Envelope NAL Y UNIDADES OPERATIVA S DEPARTAMENTALES - PAR I II BO-EMPODERAR-363744-GO -RFQ / COMPRA DE MATERIAL Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 21,074.00 0.00 Finalizado 2023-05-30 2023-07-25 2023-06-28 2023-09-30 2023-06-29 DE ESCRITORIO PARA LA OFI ciones Envelope CINA NACIONAL Y DEPARTAM ENTALES - PAR III BO-EMPODERAR-363743-GO -RFQ / COMPRA DE TONER PA Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 33,325.00 0.00 Finalizado 2023-05-30 2023-07-25 2023-06-29 2023-10-31 2023-06-29 RA LA OFICINA NACIONAL Y ciones Envelope DEPARTAMENTALES DEL PAR III BO-EMPODERAR-363749-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE LLANTAS IBRD / 94370 3. Project Management Posterior Open - National 21,429.00 0.00 Finalizado 2023-05-30 2023-07-25 2023-09-30 ciones Envelope PARA VEHICULOS CAMIONET AS DEL PAR III BO-EMPODERAR-371927-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE MOCHILA IBRD / 94370 3. Project Management Posterior Open - National 12,317.00 0.00 Finalizado 2023-07-18 2023-09-12 2023-11-07 2023-11-18 2023-11-21 ciones Envelope S DE VIAJE PARA LAPTOP Page 1 BO-EMPODERAR-377851-GO -RFQ / Software LICENCIAS M Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 8,530.00 0.00 Finalizado 2023-08-23 2023-10-18 2023-09-27 2024-04-15 2023-09-29 ICROSOFT OFFICE 365 para l ciones Envelope os equipos de computación d el PAR III BO-EMPODERAR-377857-GO -RFQ / ADQUISICION DE CENT Solicitud de cotiza Single Stage - One RALES TELEFONICAS, TELEFO IBRD / 94370 3. Project Management Posterior Open - National 42,274.00 0.00 Finalizado 2023-08-23 2023-10-18 2023-12-06 2024-04-15 2023-12-20 ciones Envelope NOS IP, EQUIPAMIENTO NET WORKING PARA EL PAR III BO-EMPODERAR-377833-GO -RFQ / COMPRA DE TONER PA Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 28,716.00 0.00 Finalizado 2023-08-23 2023-10-18 2023-10-12 2023-10-31 2023-10-13 RA IMPRESORAS Y FOTOCOPI ciones Envelope ADORAS DEL PAR III BO-EMPODERAR-377858-GO -RFQ / ADQUISICION DE SERV Solicitud de oferta Single Stage - One Ejecución pe IDORES DE DATOS Y APLICAC IBRD / 94370 3. Project Management Posterior Open - National 67,055.00 0.00 2023-08-23 2023-08-28 2023-10-09 2023-11-08 2023-12-13 2024-06-10 s Envelope ndiente IONES, Y PROTECCION ELECT RICA DE EQUIPOS ELECTRONI COS PAR III BO-EMPODERAR-380590-GO -RFQ / COMPRA DE AIRE ACO Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 4,235.00 0.00 Finalizado 2023-09-10 2023-11-05 2023-09-27 2023-11-30 2023-10-16 NDICIONADO PARA LA UOD S ciones Envelope ANTA CRUZ - PAR III BO-EMPODERAR-380591-GO Solicitud de cotiza Single Stage - One -RFQ / ADQUISICION DE 40 SI IBRD / 94370 3. Project Management Posterior Open - National 3,090.00 0.00 Finalizado 2023-09-10 2023-11-05 2023-09-27 2023-12-30 2023-09-29 ciones Envelope LLAS PARA LA UOD SANTA C RUZ - PAR III BO-EMPODERAR-380592-GO -RFQ / ADQUISICION DE 12 M Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 997.00 0.00 Finalizado 2023-09-10 2023-11-05 2023-09-27 2023-12-30 2023-09-29 ESAS PLEGABLES PARA LA U ciones Envelope OD SANTA CRUZ - PAR III BO-EMPODERAR-380593-GO Solicitud de cotiza Single Stage - One -RFQ / ADQUISICION DE 12 C IBRD / 94370 3. Project Management Posterior Open - National 2,045.00 0.00 Finalizado 2023-09-10 2023-11-05 2023-09-21 2023-12-29 2023-09-25 ciones Envelope ARPAS PARA LA OFICINA NAC IONAL - PAR III BO-EMPODERAR-385259-GO -RFQ / COMPRA DE 5 SILLAS Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 692.00 0.00 Finalizado 2023-10-08 2023-12-03 2023-11-01 2024-01-27 2023-12-20 SEMIEJECUTIVAS PARA LA UFI ciones Envelope CINA UOR RIBERALTA - PAR II I BO-EMPODERAR-385263-GO -RFQ / MOBILIARIO PARA LA Solicitud de cotiza Single Stage - One UOR RIBERALTA (ESCRITORI IBRD / 94370 3. Project Management Posterior Open - National 2,872.00 0.00 Finalizado 2023-10-08 2023-12-03 2023-11-01 2024-01-27 2023-12-11 ciones Envelope O EJECUTIVO, ESTANTES DE MADERA Y MESA DE REUNIO NES) - PAR III BO-EMPODERAR-386908-GO -RFQ / COMPRA DE TONERA P Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 28,426.00 0.00 Finalizado 2023-10-16 2023-12-11 2023-11-08 2023-12-24 2023-11-10 ARA LAS NUEVAS IMPRESOR ciones Envelope AS Y FOTOCOPIADORAS DEL PAR III BO-EMPODERAR-386909-GO Solicitud de cotiza Single Stage - One -RFQ / LLANTAS PARA CAMIO IBRD / 94370 3. Project Management Posterior Open - National 25,714.00 0.00 Finalizado 2023-10-16 2023-12-11 2023-10-25 2024-02-16 ciones Envelope NETAS 4X4 FRONTIER DEL PA R III BO-EMPODERAR-388719-GO -RFQ / COMPRA DE MATERIAL Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 23,688.00 0.00 Finalizado 2023-10-25 2023-12-20 2023-11-16 2024-03-27 2023-11-21 DE ESCRITORIO PARA LAS OF ciones Envelope ICINAS DEPARTAMENTALES Y NACIONAL DEL PAR III BO-EMPODERAR-388721-GO -RFQ / COMPRA DE MOBILIAR Solicitud de cotiza Single Stage - One IO (ESTANTE DE MADERA Y E IBRD / 94370 3. Project Management Posterior Open - National 2,040.00 0.00 Finalizado 2023-10-25 2023-12-20 2023-12-13 2024-02-13 2023-12-19 ciones Envelope SCRITORIO DE MADERA) PAR A LA UOD PANDO - PAR III BO-EMPODERAR-388724-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE SILLAS EJ IBRD / 94370 3. Project Management Posterior Open - National 753.00 0.00 Finalizado 2023-10-25 2023-12-20 2023-12-13 2024-02-13 2023-12-19 ciones Envelope ECUTIVAS PARA LA UOD PAN DO - PAR III BO-EMPODERAR-388725-GO -RFQ / COMPRA DE AIRES AC Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 2,642.00 0.00 Finalizado 2023-10-25 2023-12-20 2023-12-13 2024-02-13 2023-12-19 ONDICIONADOS, RUOTER Y E ciones Envelope CRAM PARA LA UOD PANDO - PAR III BO-EMPODERAR-392009-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE SILLAS DE IBRD / 94370 3. Project Management Posterior Open - National 2,186.00 0.00 Finalizado 2023-11-12 2024-01-07 2023-11-20 2024-03-02 2023-11-28 ciones Envelope ESPERA PARA LA OFICINA NA CIONAL - PAR III BO-EMPODERAR-392010-GO -RFQ / COMPRA DE MOBILIAR Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 2,930.00 0.00 Finalizado 2023-11-12 2024-01-07 2024-03-02 2023-12-14 IO PARA LA UOD TARIJA (ESC ciones Envelope RITORIO EJECUTIVO, ESTANT ES) - PAR III BO-EMPODERAR-392468-GO -RFQ / COMPRA DE MOBILIAR Solicitud de cotiza Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 2,544.00 0.00 2023-11-14 2024-01-09 2024-03-04 IO (ESTANTES Y MUEBLE AUX ciones Envelope ndiente ILIAR) PARA LA UOD COCHAB AMBA - PAR III BO-EMPODERAR-394125-GO -RFQ / COMPRA DE ECRAM P Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 164.00 0.00 Finalizado 2023-11-25 2024-01-20 2023-12-04 2024-03-15 2023-12-12 ARA PRESENTACIONES Y REU ciones Envelope NIONES DE LA UOD TARIJA - PAR III BO-EMPODERAR-394127-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE SILLAS PA IBRD / 94370 3. Project Management Posterior Open - National 2,165.00 0.00 Finalizado 2023-11-25 2024-01-20 2023-12-01 2024-03-15 2023-12-12 ciones Envelope RA REUNIONES PARA LA UOD TARIJA - PAR III BO-EMPODERAR-394128-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE SILLOS EJ IBRD / 94370 3. Project Management Posterior Open - National 1,670.00 0.00 Finalizado 2023-11-25 2024-01-20 2023-12-01 2024-03-15 2023-12-12 ciones Envelope ECUTIVOS PARA LA UOD TARI JA - PAR III BO-EMPODERAR-394129-GO -RFQ / COMPRA DE 10 MESAS Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 880.00 0.00 Finalizado 2023-11-25 2024-01-20 2023-12-04 2024-03-15 2023-12-15 PLEGABLES PARA REUNIONE ciones Envelope S DE LA UOD TARIJA - PAR III BO-EMPODERAR-394131-GO -RFQ / COMPRA DE 10 MESAS Solicitud de cotiza Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 835.00 0.00 2023-11-25 2024-01-20 2024-03-15 PLEGABLES PARA REUNIONE ciones Envelope ndiente S DE LA UOD COCHABAMBA - PAR III BO-EMPODERAR-394132-GO -RFQ / COMPRA DE TONER PA Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 32,070.00 0.00 Finalizado 2023-11-25 2024-01-20 2023-12-01 2024-02-02 2023-12-05 RA IMPRESORAS Y FOTOCOPI ciones Envelope ADORAS DEL PAR III BO-EMPODERAR-394144-GO -RFQ / COMPRA DE 25 SILLAS Solicitud de cotiza Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 1,804.00 0.00 2023-11-25 2024-01-20 2024-03-15 PARA REUNIONES DE LA UOD ciones Envelope ndiente COCHABAMBA - PAR III BO-EMPODERAR-394149-GO -RFQ / ADQUISICION DE 24 E Solicitud de cotiza Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 48,980.00 0.00 2023-11-25 2024-01-20 2024-07-18 QUIPOS DE COMPUTACION (L ciones Envelope ndiente APTOP) PARA EL PAR III BO-EMPODERAR-396400-GO -RFQ / COMPRA DE SILLONES Solicitud de cotiza Single Stage - One EJECUTIVOS Y SEMIEJECUTIV IBRD / 94370 3. Project Management Posterior Open - National 4,112.00 0.00 Finalizado 2023-12-09 2024-02-03 2023-12-15 2024-03-29 2023-12-22 ciones Envelope OS PARA EL PERSONAL DE LA UOD SANTA CRUZ - PAR III BO-EMPODERAR-396405-GO -RFQ / COMPRA AIRES ACON Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 3,041.00 0.00 Finalizado 2023-12-09 2024-02-03 2023-12-15 2024-02-28 2023-12-22 DICIONADOS PARA LA UOD S ciones Envelope ANTA CRUZ - PAR III BO-EMPODERAR-396407-GO -RFQ / COMPRA DE MOBILIAR Solicitud de cotiza Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 6,179.00 0.00 2023-12-09 2024-02-03 2024-03-29 IO (ESCRITORIOS, ESTANTES ciones Envelope ndiente Y ARCHIVEROS) PARA LA UO D SANTA CRUZ- PAR III BO-EMPODERAR-396409-GO -RFQ / COMPRA DE AIRES AC Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 1,915.00 0.00 Finalizado 2023-12-09 2024-02-03 2024-02-28 2023-12-27 ONDICIONADOS PARA LA UO ciones Envelope R RIBERALTA - PAR III Page 2 BO-EMPODERAR-396412-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA SE SILLONES IBRD / 94370 3. Project Management Posterior Open - National 1,312.00 0.00 Finalizado 2023-12-09 2024-02-03 2023-12-14 2024-03-29 2023-12-20 ciones Envelope SEMI EJECUTIVOS PARA LA U OD BENI - PAR III BO-EMPODERAR-396414-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE ECRAM P IBRD / 94370 3. Project Management Posterior Open - National 166.00 0.00 Finalizado 2023-12-09 2024-02-03 2023-12-14 2024-03-29 2023-12-20 ciones Envelope ARA LA UOD BENI - PAR III BO-EMPODERAR-396415-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE MATERIAL IBRD / 94370 3. Project Management Posterior Open - National 22,827.00 0.00 Finalizado 2023-12-09 2024-02-03 2023-12-22 2024-05-11 2023-12-22 ciones Envelope DE ESCRITORIO Y TONER PAR A EL PAR III BO-EMPODERAR-401690-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE TONERA P IBRD / 94370 3. Project Management Posterior Open - National 21,866.00 0.00 Finalizado 2024-01-13 2024-03-09 2024-03-22 2024-01-25 ciones Envelope ARA IMPRESORAS Y FOTOCO PIADORAS BO-EMPODERAR-401692-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE MATERIAL IBRD / 94370 3. Project Management Posterior Open - National 14,577.00 0.00 Finalizado 2024-01-13 2024-03-09 2024-05-15 2024-01-25 ciones Envelope DE ESCRITORIO PARA EL PAR III BO-EMPODERAR-403599-GO -RFQ / COMPRA DE LICENCIA Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 24,952.00 0.00 Finalizado 2024-01-22 2024-03-18 2024-09-14 2024-01-31 S OFFICE 365 ESTANDAR PAR ciones Envelope A EQUIPOS DE COMPUTACIO N - PAR III BO-EMPODERAR-406714-GO -RFQ / COMPRA DE DOS AIRE Solicitud de cotiza Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 1,137.00 0.00 2024-02-05 2024-04-01 2024-05-26 S ACONDICIONADOS PARA L ciones Envelope ndiente A UOR RURRENABAQUE - PA R III BO-EMPODERAR-406717-GO Solicitud de cotiza Single Stage - One -RFQ / COMPRA DE LLANTAS IBRD / 94370 3. Project Management Posterior Open - National 29,154.00 0.00 Finalizado 2024-02-05 2024-04-01 2024-06-01 2024-03-08 ciones Envelope PARA VEHICULOS DEL EMPO DERAR PAR III BO-EMPODERAR-406804-GO -RFQ / COMPRA DE MOBILIAR Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 2,580.00 0.00 Finalizado 2024-02-05 2024-04-01 2024-05-26 2024-03-12 IO (SILLONES SEMIEJECUTIVO ciones Envelope S Y ESCRITORIOS) PARA LA U OR CAMARGO - PAR III BO-EMPODERAR-406808-GO -RFQ / COMPRA DE MESA PLE Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 969.00 0.00 Finalizado 2024-02-05 2024-04-01 2024-05-26 2024-04-09 GABLE Y SILLAS DE PLASTICO ciones Envelope PARA LA UOD PANDO - PAR II I BO-EMPODERAR-414690-GO -RFQ / COMPRA DE MATERIAL Solicitud de cotiza Single Stage - One DE ESCRITORIO Y TONER PAR IBRD / 94370 3. Project Management Posterior Open - National 43,731.00 0.00 Finalizado 2024-03-12 2024-05-07 2024-11-03 2024-03-25 ciones Envelope A LAS OFICINAS DEPARTAME NTALES Y REGIONALES DEL P AR III BO-EMPODERAR-420625-GO -RFQ / COMPRA DE TONER PA Solicitud de cotiza Single Stage - One RA IMPRESORAS Y FOTOCOPI IBRD / 94370 3. Project Management Posterior Open - National 36,443.00 0.00 En ejecución 2024-04-09 2024-06-04 2024-12-01 ciones Envelope ADORAS DE LAS OFICINAS D EPARTAMENTALES Y REGION ALES DEL PAR III BO-EMPODERAR-420626-GO -RFQ / COMPRA DE MATERIAL Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 14,577.00 0.00 Finalizado 2024-04-09 2024-06-04 2024-12-01 DE ESCRITORIO PARA LA OFI ciones Envelope CINA NACIONAL Y DEPARTAM ENTALES DEL PAR III BO-EMPODERAR-420627-GO -RFQ / COMPRA DE PAPEL PA Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 8,746.00 0.00 Finalizado 2024-04-09 2024-06-04 2024-12-01 2024-04-23 RA LA OFICINA NACIONAL Y ciones Envelope DEPARTAMENTALES - PAR III BO-EMPODERAR-426591-GO -RFQ / COMPRA DE SILLONES Solicitud de cotiza Single Stage - One Ejecución pe EJECUTIVO Y SEMIEJECUTIVO IBRD / 94370 3. Project Management Posterior Open - National 2,092.00 0.00 2024-05-13 2024-07-08 2025-01-04 ciones Envelope ndiente S PARA LA OFICINA DEPARTA MENTAL DE ORURO - PAR III BO-EMPODERAR-426594-GO -RFQ / COMPRA DE SILLAS PA Solicitud de cotiza Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 402.00 0.00 2024-05-13 2024-07-08 2025-01-04 RA REUNIONES PARA LA OFIC ciones Envelope ndiente INA DEPARTAMENTAL DE OR URO - PAR III BO-EMPODERAR-431491-GO -RFQ / COMPRA DE CAJAS DE Solicitud de cotiza Single Stage - One Ejecución pe IBRD / 94370 3. Project Management Posterior Open - National 10,189.00 0.00 2024-06-08 2024-08-03 2025-01-30 CARTON Y ARCHIVADOR DE P ciones Envelope ndiente ALANCA PARA EL PAR III NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit N Market Approac Procurement Pr Prequalification Estimated Am Actual Amount Process St Draft Pre-qualificatio Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion o. h ocess (Y/N) ount (US$) (US$) atus n Documents ation Report ent / Justification Notice / Invitation s Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351830-NC- RFQ / SERVICIO DE LIMPIEZA Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 10,760.00 0.00 Firmado 2023-03-27 2023-05-22 2023-04-03 2023-12-31 DE OFICINAS DE LA UNIDAD ciones Envelope DE COORDINACION NACIONA L BO-EMPODERAR-351831-NC- RFQ / SERVICIO DE AGENCIA Solicitud de cotiza Single Stage - One DE VIAJES PARA PASAJES AER IBRD / 94370 3. Project Management Posterior Open - National 17,492.00 0.00 Firmado 2023-03-27 2023-05-22 2023-04-03 2023-12-31 ciones Envelope EOS NACIONALES E INTERNA CIONALES DEL PERSONAL DE L PAR III BO-EMPODERAR-359799-NC- RFQ / IMPRESION DE CARTILL AS DE DIFUSION DE REQUISI 1. Capacity Building and Inst Solicitud de cotiza Single Stage - One IBRD / 94370 Posterior Open - National 50,000.00 0.00 Finalizado 2023-05-07 2023-07-02 2023-06-13 2023-08-31 2023-07-24 TOS Y BENEFICIOS DEL PAR II itutional Strengthening ciones Envelope I, CUATRIPTICOS DE INFORM ACION DEL COMPONENTE 2 (Y SUB COMPONENTES) BO-EMPODERAR-363936-NC- RFQ / FABRICACION DE GLOB Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 49,562.00 0.00 Finalizado 2023-05-31 2023-07-26 2023-06-20 2023-08-31 2023-07-19 OS INFLABLES Y CARPA DE L ciones Envelope ONA (PARA EVENTOS DE DIF USION DEL PAR III) BO-EMPODERAR-363938-NC- RFQ / IMPRESION DE MATERI Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 46,584.00 0.00 Finalizado 2023-05-31 2023-07-26 2023-06-19 2023-08-31 2023-07-19 AL DE DIFUSION BANNERS Y ciones Envelope ROLLER PARA EL PAR III BO-EMPODERAR-365736-NC- RFQ / FABRICACION DE LETR Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 41,095.00 0.00 Finalizado 2023-06-11 2023-08-06 2023-06-22 2023-09-11 2023-07-28 EROS DE DIFUSION DE RESU ciones Envelope LTADOS DEL PAR II BO-EMPODERAR-367211-NC- RFQ / IMPRESION DE GUIAS P ARA ELABORACION DE PLAN Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 48,854.00 0.00 Finalizado 2023-06-19 2023-08-14 2023-07-04 2023-08-31 2023-08-21 ES DE ALIANZA, PPC, PROYEC ciones Envelope TOS DE INFRAESTRUCTURA P RODUCTIVA Y GUIA DEL MEG AS - PAR III BO-EMPODERAR-369484-NC- RFQ / IMPRESION DE MATERI AL RECREATIVO AFICHES CAL Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 48,251.00 0.00 Finalizado 2023-07-02 2023-08-27 2023-08-09 2023-10-02 2023-08-31 ENDARIO, AGENDAS, CALEN ciones Envelope DARIO DE ESCRITORIO (2023 -2024) Y CUADERNOS DE CA MPO DEL PAR III BO-EMPODERAR-375095-NC- RFQ / SERVICIO DE COLOCAD Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 17,318.00 0.00 Finalizado 2023-08-05 2023-09-30 2021-08-30 2023-11-05 2023-09-25 O DE LETREROS DEL PROYEC ciones Envelope TO DE ALIANZAS RURALES (P AR II) BO-EMPODERAR-377869-NC- RFQ / IMPRESION DE DOCUM Solicitud de oferta Single Stage - One ENTOS DEL PAR III - MEGAS, IBRD / 94370 3. Project Management Posterior Open - National 62,827.00 0.00 Finalizado 2023-08-23 2023-10-01 2023-08-28 2023-10-09 2023-11-01 2023-11-08 2023-11-03 2023-12-13 2024-06-10 2023-11-29 s Envelope GUIA DE ELABORACION PECA S, GUIA 3 Y FOLDER INSTITU CIONAL BO-EMPODERAR-396642-NC- RFQ / COMPRA DE GLOBOS D Solicitud de cotiza Single Stage - One IBRD / 94370 3. Project Management Posterior Open - National 23,411.00 0.00 Finalizado 2023-12-10 2024-02-04 2024-03-11 2024-01-19 E INFLABLES Y ROLLER PUBL ciones Envelope ICITARIO PARA DIFUSION DEL PROYECTO PAR III Page 3 BO-EMPODERAR-401637-NC- Solicitud de cotiza Single Stage - One Ejecución pe RFQ / SEGURO AUTOMOTOR IBRD / 94370 3. Project Management Posterior Open - National 39,780.00 0.00 2024-01-13 2024-03-09 2024-09-05 ciones Envelope ndiente PARA VEHICULOS DEL EMPO DERAR PAR III BO-EMPODERAR-401666-NC- Adquisición direct Ejecución pe DIR / POLIZA DE SEGURO DE IBRD / 94370 3. Project Management Posterior Direct - National 80,640.00 0.00 2024-01-08 2024-01-13 2024-02-17 2024-08-15 a ndiente SALUDO PARA EL PERSONAL DEL PAR III CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Expression of Interes Short List and Draft R Request for Proposal Opening of Technical Evaluation of Techni Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) t (US$) t Notice equest for Proposals s as Issued Proposals / Minutes cal Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-351840-CS- CQS / SERVICIOS DE CONSUL Selección basada TORÍA PARA EL DESARROLLO IBRD / 94370 3. Project Management Posterior en calificaciones d Open - National 45,000.00 0.00 Firmado 2023-03-22 2023-03-24 2023-04-12 2023-05-26 2023-05-29 2023-06-25 2023-06-26 2023-07-30 2023-11-30 DEL MÓDULO DE SUBPROYE e consultores CTOS DE INFRAESTRUCTURA PRODUCTIVA COMPLEMENTA RIA- PAR III BO-EMPODERAR-351849-CS- CQS / SELECCION DE PERSO Selección basada NAL TECNICO DE LA UNIDAD IBRD / 94370 3. Project Management Posterior en calificaciones d Open - National 42,274.00 0.00 Cancelado 2023-03-22 2023-03-24 2023-04-12 2023-05-26 2023-06-25 2023-07-30 2024-12-31 DE COORDINACION NACIONA e consultores L, UNIDADES OPERATIVAS DE PARTAMENTALES Y REGIONA LES DEL PAR III BO-EMPODERAR-368809-CS- QCBS / CONSULTORIA PARA L A EJECUCIÓN DEL PROCESO Selección basada IBRD / 94370 3. Project Management Posterior Open - National 227,405.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 DE PLANIFICACION PARTICIP en calidad y costo ATIVA COMUNITARIA (PPC) P AQUETE 1 LA PAZ (ALTIPLAN O YUNGAS) BO-EMPODERAR-369487-CS- QCBS / CONSULTORIA PARA L Selección basada A EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior Open - National 233,090.00 0.00 En ejecución 2023-06-27 2023-06-30 2023-07-18 2023-08-31 2023-09-28 2023-10-28 2023-12-02 2024-01-06 2025-01-05 en calidad y costo DE PLANIFICACION PARTICIP ATIVA COMUNITARIA (PPC) P aquete 8 LA PAZ (LAGO SUR) BO-EMPODERAR-368805-CS- QCBS / CONSULTORIA PARA L Selección basada A EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior Open - National 299,417.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 en calidad y costo DE PLANIFICACION PARTICIP ATIVA COMUNITARIA (PPC) P aquete 5 CHUQUISACA BO-EMPODERAR-368804-CS- QCBS / CONSULTORIA PARA L A EJECUCIÓN DEL PROCESO Selección basada IBRD / 94370 3. Project Management Posterior Open - National 280,466.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 DE PLANIFICACION PARTICIP en calidad y costo ATIVA COMUNITARIA (PPC) P AQUETE 6 LA PAZ (LAGO NO RTE) BO-EMPODERAR-368806-CS- QCBS / CONSULTORIA PARA L Selección basada A EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior Open - National 255,831.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 en calidad y costo DE PLANIFICACION PARTICIP ATIVA COMUNITARIA (PPC) P AQUETE 4 POTOSI - ESTE BO-EMPODERAR-369485-CS- QCBS / CONSULTORIA PARA L Selección basada A EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior Open - National 244,461.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 en calidad y costo DE PLANIFICACION PARTICIP ATIVA COMUNITARIA (PPC) P AQUETE 3 COCHABAMBA BO-EMPODERAR-368808-CS- QCBS / CONSULTORIA PARA L Selección basada A EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior Open - National 329,738.00 0.00 En ejecución 2023-06-22 2023-06-30 2023-07-13 2023-08-26 2023-09-23 2023-10-23 2023-11-27 2024-01-01 2024-12-31 en calidad y costo DE PLANIFICACION PARTICIP ATIVA COMUNITARIA (PPC) P AQUETE 2 ORURO BO-EMPODERAR-369486-CS- QCBS / CONSULTORIA PARA L Selección basada A EJECUCIÓN DEL PROCESO IBRD / 94370 3. Project Management Posterior Open - National 261,516.00 0.00 En ejecución 2023-06-27 2023-06-30 2023-07-18 2023-08-31 2023-09-28 2023-10-28 2023-12-02 2024-01-06 2025-01-05 en calidad y costo DE PLANIFICACION PARTICIP ATIVA COMUNITARIA (PPC) P aquete 7 POTOSI - OESTE BO-EMPODERAR-377856-CS- CQS / CONSULTORIA PARA DI AGNOSTICO, COMPLEMENTA Selección basada CION Y AJUSTE DE EDTP(EST IBRD / 94370 3. Project Management Posterior en calificaciones d Open - National 25,449.00 0.00 Firmado 2023-08-18 2023-08-23 2023-09-08 2023-10-22 2023-10-24 2023-11-21 2023-11-27 2023-12-26 2024-04-27 UDIO DE DISEÑO TECNICO D e consultores E PREINVERSION) DE SUB PR OYECTOS DE INFRAESTRUCT URA COMPLEMENTARIA DEL PAR III BO-EMPODERAR-393031-CS- CQS / EVALUACIÓN DE DESE MPEÑO DEL PERSONAL TÉCNI Selección basada CO DEL PROYECTO DE INNOV IBRD / 94370 3. Project Management Posterior en calificaciones d Open - National 29,621.00 0.00 Cancelado 2023-11-13 2023-11-20 2023-12-04 2024-01-17 2024-02-16 2024-03-22 2024-07-23 ACIÓN PARA SISTEMAS ALIME e consultores NTARIOS RESILIENTES (ALIAN ZAS RURALES – PAR III) Y ES TUDIO DE SATISFACCIÓN DE BENEFICIARIOS BO-EMPODERAR-409914-CS- Selección basada LCS / Contratación auditoria f IBRD / 94370 3. Project Management Posterior Open - National 36,443.00 0.00 En ejecución 2024-02-14 2024-03-01 2024-03-06 2024-04-19 2024-05-17 2024-06-16 2024-07-21 2024-08-25 2025-02-21 en el menor costo inanciera gestiones 2023, 20 24 y 2025 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amoun Draft Negotiated Con Description Component Review Type Method Process Status Terms of Reference d/Selected Consultan Signed Contract Contract Completion o. h unt (US$) t (US$) tract t Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BO-EMPODERAR-327304-CS- INDV / COORDINADOR GENE IBRD / 94370 3. Project Management Posterior Individual Direct - National 102,516.00 0.00 Firmado 2022-11-18 2022-11-21 2022-11-28 2020-11-16 2022-12-19 2020-11-16 2023-01-23 2025-11-30 RAL DEL EMPODERAR PARA E L PAR III BO-EMPODERAR-349701-CS- INDV / JEFE DE PLANIFICACIÓ IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,530.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 N Y MONITOREO BO-EMPODERAR-349709-CS- INDV / ESPECIALISTA EN ASIS IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 TENCIA TÉCNICA, DESARROL LO ORGANIZACIONAL Y PPPI BO-EMPODERAR-349711-CS- INDV / ESPECIALISTA EN ADQ IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UISICIONES BO-EMPODERAR-349715-CS- INDV / ESPECIALISTA AMBIEN IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 TAL, SEGURIDAD Y SALUD BO-EMPODERAR-349716-CS- INDV / JEFE ADMINISTRATIVO IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,530.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 FINANCIERO BO-EMPODERAR-349718-CS- INDV / ESPECIALISTA EN NEG IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Rescindido 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 OCIOS RURALES BO-EMPODERAR-349726-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / ANALISTA COMUNICA CIÓN BO-EMPODERAR-349729-CS- INDV / ANALISTA DE ADQUISI IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 CIONES PARA ALIANZAS BO-EMPODERAR-349730-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / ANALISTA DESEMBOL SOS BO-EMPODERAR-349731-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / ANALISTA FINANCIERO BO-EMPODERAR-349732-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 14,907.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / ANALISTA PROGRAMA DOR Page 4 BO-EMPODERAR-349733-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / RECEPCIONISTA UCN BO-EMPODERAR-349758-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,061.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / CHOFER UCN BO-EMPODERAR-349759-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,061.00 0.00 Finalizado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / SECRETARIA EJECUTIV A UCN BO-EMPODERAR-349760-CS- INDV / ASISTENTE DE ADQUI IBRD / 94370 3. Project Management Posterior Individual Direct - National 11,400.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 SICIONES PARA ALIANZAS BO-EMPODERAR-349761-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 12,178.00 0.00 Firmado 2023-03-14 2023-03-23 2023-03-24 2023-03-31 2023-03-27 2023-04-20 2023-04-03 2023-04-24 2023-12-31 INDV / ANALISTA DE TRANSP ARENCIA BO-EMPODERAR-349762-CS- INDV / ESPECIALISTA EN INFR IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 AESTRUCTURA BO-EMPODERAR-349763-CS- INDV / ESPECIALISTA ADMINI IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 STRATIVO FINANCIERO BO-EMPODERAR-349764-CS- INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 MENTAL UOD LA PAZ BO-EMPODERAR-349765-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOD LA PAZ BO-EMPODERAR-349766-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / CHOFER UOD LA PAZ BO-EMPODERAR-349767-CS- INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 MENTAL UOD BENI BO-EMPODERAR-349768-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 PRODUCTIVAS UOD BENI BO-EMPODERAR-349769-CS- INDV / OPERADOR REGIONAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOR CHACO (CAMIRI) BO-EMPODERAR-349770-CS- INDV / SECRETARIA UOR CHA IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 CO (CAMIRI) BO-EMPODERAR-349771-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / CHOFER UOR CHACO ( CAMIRI) BO-EMPODERAR-349772-CS- INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 MENTAL UOD PANDO BO-EMPODERAR-349773-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 PRODUCTIVAS UOD PANDO BO-EMPODERAR-349774-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / SECRETARIA UOD PAN DO BO-EMPODERAR-349775-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOR RIBERALTA BO-EMPODERAR-349776-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / SECRETARIA UOR RIB ERALTA BO-EMPODERAR-349777-CS- INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 MENTAL UOD POTOSI BO-EMPODERAR-349778-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / CHOFER UOD POTOSI BO-EMPODERAR-349779-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOD POTOSI BO-EMPODERAR-349780-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 PRODUCTIVAS UOD POTOSI BO-EMPODERAR-349781-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 PRODUCTIVAS UOR CAMARG O BO-EMPODERAR-349782-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,028.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / SECRETARIA UOR CAM ARGO BO-EMPODERAR-349783-CS- INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 MENTAL UOD COCHABAMBA BO-EMPODERAR-349784-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOD COCHABAMBA BO-EMPODERAR-349785-CS- INDV / SECRETARIA UOD COC IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 HABAMBA BO-EMPODERAR-349786-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOD CHUQUISACA BO-EMPODERAR-349787-CS- INDV / ANALISTA AMBIENTAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOD CHUQUISACA BO-EMPODERAR-349788-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / CHOFER UOD CHUQUI SACA BO-EMPODERAR-349789-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / CHOFER UOD TARIJA BO-EMPODERAR-349790-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOD TARIJA BO-EMPODERAR-349791-CS- INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 MENTAL UOD ORURO BO-EMPODERAR-349792-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Finalizado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / SECRETARIA UOD ORU RO BO-EMPODERAR-349793-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOD ORURO BO-EMPODERAR-349794-CS- INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 23,063.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 MENTAL UOD SANTA CRUZ BO-EMPODERAR-349796-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOD SANTA CRUZ BO-EMPODERAR-349797-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 PRODUCTIVAS UOD SANTA C RUZ Page 5 BO-EMPODERAR-349799-CS- INDV / SECRETARIA UOD SAN IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 TA CRUZ BO-EMPODERAR-349801-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / CHOFER UOD SANTA CRUZ BO-EMPODERAR-349803-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 INDV / CHOFER UOD SANTA CRUZ BO-EMPODERAR-349804-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 PRODUCTIVAS UOR CHIQUIT ANIA BO-EMPODERAR-349805-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-14 2023-03-24 2023-03-24 2023-03-31 2023-03-27 2023-04-03 2023-04-03 2023-04-05 2023-12-31 PRODUCTIVAS UOD LA PAZ BO-EMPODERAR-350019-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-03-15 2023-03-25 2023-03-28 2023-04-03 2023-12-31 PRODUCTIVAS UOR RURREN ABAQUE BO-EMPODERAR-350025-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOD PANDO BO-EMPODERAR-350029-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-04-05 2023-12-31 COMUNITARIAS UOR CHIQUIT ANIA BO-EMPODERAR-350037-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-03-15 2023-03-25 2023-03-28 2023-04-03 2023-12-31 COMUNITARIAS UOD SANTA CRUZ BO-EMPODERAR-350145-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-04-05 2023-12-31 UOR CHACO (CAMIRI) BO-EMPODERAR-350155-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-04-05 2023-12-31 PRODUCTIVAS UOD CHUQUIS ACA BO-EMPODERAR-350156-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-04-05 2023-12-31 2024-04-10 PRODUCTIVAS UOD COCHAB AMBA BO-EMPODERAR-350157-CS- INDV / OFICIAL DE INFRAEST IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-03-15 2023-03-24 2023-03-25 2023-03-31 2023-03-28 2023-04-03 2023-04-03 2023-04-05 2023-12-31 RUCTURA UOD COCHABAMB A BO-EMPODERAR-354356-CS- INDV / ANALISTA SOCIAL Y G IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,050.00 0.00 Firmado 2023-03-31 2023-05-04 2023-04-10 2023-03-31 2023-04-13 2023-04-03 2023-04-19 2023-04-05 2023-12-31 ENERO UOD SANTA CRUZ - P AR III BO-EMPODERAR-354357-CS- INDV / ANALISTA SOCIAL Y G IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,050.00 0.00 Firmado 2023-03-31 2023-05-04 2023-04-10 2023-03-31 2023-04-13 2023-04-03 2023-04-19 2023-04-05 2023-12-31 ENERO UOD LA PAZ - PAR III BO-EMPODERAR-356762-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-12 2023-05-04 2023-05-15 2023-12-31 UOD LA PAZ BO-EMPODERAR-356764-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 PRODUCTIVAS UOD LA PAZ BO-EMPODERAR-356765-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 PRODUCTIVAS UOR CHACO ( CAMIRI) BO-EMPODERAR-356766-CS- INDV / ANALISTA AMBIENTAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-06-12 2023-12-31 UOR CHACO (CAMIRI) BO-EMPODERAR-356767-CS- INDV / ANALISTA SOCIAL Y G IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-07-21 2023-05-04 2023-07-27 2023-12-31 ENERO UOR CHACO (CAMIRI) BO-EMPODERAR-356768-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-12 2023-05-04 2023-05-15 2023-12-31 UOR CHACO (CAMIRI) BO-EMPODERAR-356769-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 2023-05-02 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 INDV / CHOFER UOD PANDO BO-EMPODERAR-356770-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 2023-05-02 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 INDV / CHOFER UOR RIBERAL TA BO-EMPODERAR-356771-CS- INDV / OFICIAL DE SUB PROY IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-05-11 2023-05-04 2023-05-15 2023-12-31 ECTOS DE INFRAESTRUCTUR A UOD POTOSI BO-EMPODERAR-356773-CS- INDV / ANALISTA AMBIENTAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-06-07 2023-05-04 2023-06-12 2023-12-31 UOD POTOSI BO-EMPODERAR-356785-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 2023-05-02 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 INDV / CHOFER UOD COCHAB AMBA BO-EMPODERAR-356787-CS- INDV / ANALISTA AMBIENTAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-06-07 2023-05-04 2023-06-12 2023-12-31 UOD COCHABAMBA BO-EMPODERAR-356788-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 PRODUCTIVAS UOD CHUQUIS ACA BO-EMPODERAR-356789-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-05-15 2023-05-04 2023-05-15 2023-12-31 2023-09-12 COMUNITARIAS UOD TARIJA BO-EMPODERAR-356790-CS- INDV / ANALISTA AMBIENTAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-06-08 2023-05-04 2023-06-12 2023-12-31 UOD TARIJA BO-EMPODERAR-356792-CS- INDV / ANALISTA FIDUCIARIA IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-05-12 2023-05-04 2023-05-15 2023-12-31 UOD ORURO BO-EMPODERAR-356793-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Rescindido 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-06-22 2023-05-04 2023-06-27 2023-12-31 PRODUCTIVAS UOD ORURO BO-EMPODERAR-356794-CS- INDV / OFICIAL DE SUB PROY IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-05-12 2023-05-04 2023-05-15 2023-12-31 ECTOS DE INFRAESTRUCTUR A UOD ORURO BO-EMPODERAR-356795-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-06-26 2023-05-04 2023-06-29 2023-12-31 COMUNITARIAS UOD ORURO BO-EMPODERAR-356797-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 2023-05-02 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 INDV / CHOFER UOD ORURO BO-EMPODERAR-356798-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-03 2023-04-24 2023-03-31 2023-04-27 2023-03-31 2023-05-04 2023-06-29 2023-12-31 UOD SANTA CRUZ BO-EMPODERAR-356802-CS- INDV / OFICIAL DE SUB PROY IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Finalizado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-05-11 2023-05-04 2023-05-15 2023-12-31 2024-04-01 ECTOS DE INFRAESTRUCTUR A UOD SANTA CRUZ BO-EMPODERAR-356806-CS- INDV / ANALISTA AMBIENTAL IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Firmado 2023-04-14 2023-05-04 2023-04-24 2023-03-31 2023-04-27 2023-06-07 2023-05-04 2023-06-12 2023-12-31 UOD SANTA CRUZ Page 6 BO-EMPODERAR-356808-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,208.00 0.00 Firmado 2023-04-14 2023-05-02 2023-04-24 2023-03-31 2023-04-27 2023-05-10 2023-05-04 2023-05-10 2023-12-31 INDV / CHOFER UOR CHIQUIT ANIA BO-EMPODERAR-360043-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,155.00 0.00 Firmado 2023-05-03 2023-05-04 2023-05-13 2023-03-31 2023-05-16 2023-05-10 2023-05-23 2023-05-10 2023-12-31 PRODUCTIVAS UOD TARIJA BO-EMPODERAR-360838-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,834.00 0.00 Firmado 2023-05-09 2023-05-12 2023-05-19 2023-03-31 2023-05-22 2023-05-16 2023-05-29 2023-05-17 2023-12-31 INDV / CHOFER UOD LA PAZ BO-EMPODERAR-360840-CS- INDV / ANALISTA SOCIAL Y G IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,155.00 0.00 Firmado 2023-05-09 2023-05-12 2023-05-19 2023-03-31 2023-05-22 2023-07-26 2023-05-29 2023-07-26 2023-12-31 ENERO UOD TARIJA BO-EMPODERAR-360845-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,963.00 0.00 Firmado 2023-05-09 2023-05-12 2023-05-19 2023-03-31 2023-05-22 2023-05-16 2023-05-29 2023-05-17 2023-12-31 INDV / SECRETARIA UOR CHI QUITANIA BO-EMPODERAR-367088-CS- INDV / SECRETARIA PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 2023-06-13 2023-06-15 2023-08-01 2023-06-30 2023-08-22 2023-06-30 2023-09-26 2023-07-06 2023-12-31 UOD LA PAZ - PAR III BO-EMPODERAR-367089-CS- INDV / SECRETARIA PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Firmado 2023-06-13 2023-06-15 2023-08-01 2023-10-11 2023-08-22 2023-10-25 2023-09-26 2023-10-30 2023-12-31 UOD POTOSI - PAR III BO-EMPODERAR-367091-CS- INDV / SECRETARIA PARA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 2023-06-13 2023-06-15 2023-08-01 2023-07-10 2023-08-22 2023-08-02 2023-09-26 2023-08-10 2023-12-31 D CHUQUISACA - PAR III BO-EMPODERAR-367092-CS- INDV / SECRETARIA PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,223.00 0.00 Finalizado 2023-06-13 2023-06-15 2023-08-01 2023-09-11 2023-08-22 2023-09-19 2023-09-26 2023-09-21 2023-12-31 UOD TARIJA - PAR III BO-EMPODERAR-367213-CS- CDS / SELECCION DE PERSO NAL TECNICO DE LA UNIDAD Selección directa IBRD / 94370 3. Project Management Posterior Direct - National 42,274.00 0.00 Firmado 2023-06-14 2023-06-15 2023-06-24 2023-06-15 2023-08-28 2023-12-31 DE COORDINACION NACIONA de consultores L, UNIDADES OPERATIVAS DE PARTAMENTALES Y REGIONA LES DEL PAR III BO-EMPODERAR-368606-CS- INDV / ESPECIALISTA EN PPC IBRD / 94370 3. Project Management Posterior Individual Open - National 12,470.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-10-23 2024-12-31 Y PROYECTOS CONSULTOR I NDIVIDUAL DE LINEA - PAR III BO-EMPODERAR-368729-CS- INDV / ESPECIALISTA EN RIEG IBRD / 94370 3. Project Management Posterior Individual Open - National 12,471.00 0.00 Finalizado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 2024-01-02 O CONSULTOR INDIVIDUAL D E LINEA - PAR III BO-EMPODERAR-368731-CS- INDV / ANALISTA EN PLANIFIC IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 ACION Y PROYECTOS CONSU LTOR INDIVIDUAL DE LINEA - PAR III BO-EMPODERAR-368732-CS- INDV / PROFESIONAL EN CUE IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-10-23 2024-12-31 STION DE GENERO CONSULT OR INDIVIDUAL DE LINEA - PA R III BO-EMPODERAR-368733-CS- INDV / OFICIAL DE SUBPROYE CTOS DE INFRAESTRUCTURA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 PARA LA UOD LA PAZ CONS ULTOR INDIVIDUAL DE LINEA - PAR II BO-EMPODERAR-368734-CS- INDV / OFICIAL DE SUBPROYE CTOS DE RIEGO PARA LA UO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 D LA PAZ CONSULTOR INDIV IDUAL DE LINEA PAR III BO-EMPODERAR-368735-CS- INDV / ANALISTA AMBIENTAL IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2024-02-18 2023-08-31 2024-04-24 2023-10-05 2024-12-31 PARA LA UOD LA PAZ, CONS ULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-368737-CS- INDV / ASISTENTE DE SUBPR OYECTOS COMUNITARIOS PA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,560.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-09-11 2023-08-31 2023-09-20 2023-10-05 2023-09-25 2024-12-31 RA LA UOD LA PAZ, CONSULT OR INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-368739-CS- INDV / ASISTENTE DE SUBPR OYECTOS PRODUCTIVOS PAR IBRD / 94370 3. Project Management Posterior Individual Open - National 7,560.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-08-04 2023-08-31 2023-08-22 2023-10-05 2023-08-28 2024-12-31 A UOD LA PAZ, CONSULTOR I NDIVIDUAL DE LINEA PAR III BO-EMPODERAR-368740-CS- INDV / OFICIAL DE ALIANZAS PRODUCTIVAS PARA LA UOR IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 RURRENABAQUE, CONSULTO R INDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-368743-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 PARA LA UOR RURRENABAQU E, CONSULTOR INDIVIDUL DE LINEA PAR III BO-EMPODERAR-368744-CS- INDV / SECRETARIA PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-27 2023-08-31 2023-08-21 2023-10-05 2023-08-23 2024-12-31 UOR RURRENABAQUE, CONS ULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-368745-CS- INDV / CHOFER PARA LA UOR IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-27 2023-08-31 2023-08-16 2023-10-05 2023-08-21 2024-12-31 RURRENABAQUE, CONSULTO R INDIVIDUAL DE LINEA PAR I II BO-EMPODERAR-368747-CS- INDV / OFICIAL DE SUBPROYE IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 CTOS DE INFRAESTRUCTURA PARA LA UOD BENI, CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368749-CS- INDV / ANALISTA AMBIENTAL IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-19 2023-08-31 2023-09-20 2023-10-05 2023-10-03 2024-12-31 PARA LA UOD BENI, CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368750-CS- INDV / ANALISTA SOCIAL Y G IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-10-23 2024-12-31 ENERO PARA LA UOD BENI, C ONSULTOR DE LINEA PAR III BO-EMPODERAR-368751-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 PARA LA UOD BENI, CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368752-CS- INDV / SECRETARIA PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-04 2023-08-31 2023-07-24 2023-10-05 2023-08-01 2024-12-31 UOD BENI, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368754-CS- INDV / CHOFER PARA LA UOD IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-04 2023-08-31 2023-07-25 2023-10-05 2023-08-01 2024-12-31 BENI, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368756-CS- INDV / ANALISTA SOCIAL Y G IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-10-23 2024-12-31 ENERO PARA LA UOD CHACO (CAMIRI), CONSULTOR DE LIN EA PAR III BO-EMPODERAR-368758-CS- INDV / OFICIAL DE SUBPROYE CTOS DE INFRAESTRUCTURA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 PARA LA UOD CHACO (CAMIR I), CONSULTOR DE LINEA PAR III BO-EMPODERAR-368760-CS- INDV / OFICIAL DE SUBPROYE IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-26 2024-12-31 CTOS DE RIEGO UOD CHACO (CAMIRI), CONSULTOR DE LIN EA PAR III Page 7 BO-EMPODERAR-368766-CS- INDV / OFICIAL DE SUBPROYE CTOS DE INFRAESTRUCTURA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-10-30 2023-10-05 2023-11-06 2024-12-31 PARA LA UOD PANDO, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368767-CS- INDV / OFICIAL DE SUBPROYE IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-20 2024-12-31 CTOS DE RIEGO PARA LA UO D PANDO, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368768-CS- INDV / ANALISTA AMBIENTAL IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Finalizado 2023-06-22 2023-06-23 2023-08-10 2023-07-19 2023-08-31 2023-09-20 2023-10-05 2023-10-04 2024-12-31 PARA LA UOD PANDO, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368769-CS- INDV / ANALISTA SOCIAL Y G IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-11-01 2024-12-31 ENERO PARA LA UOD PANDO, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368770-CS- INDV / ASISTENTE DE SUB PR IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-08-04 2023-08-31 2023-08-21 2023-10-05 2023-08-28 2024-12-31 OYECTOS PRODUCTIVOS PAR A LA UOD PANDO, CONSULT OR DE LINEA PAR III BO-EMPODERAR-368771-CS- INDV / OFICIAL DE ALIANZA P IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 RODUCTIVAS PARA LA UOD R IBERALTA, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368772-CS- INDV / ANALISTA SOCIAL EN IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-10-30 2024-12-31 GENERO PARA LA UOD POTO SI, CONSULTOR DE LINEA PA R III BO-EMPODERAR-368773-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 COMUNITARIAS PARA LA UO D POTOSI, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368774-CS- INDV / OFICIAL DE SUBPROYE IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 CTOS DE REIGO PARA LA UO D POTOSI, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368775-CS- INDV / ASISTENTE DE SUB PR OYECTOS COMUNITARIOS PA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-10-11 2023-08-31 2023-10-26 2023-10-05 2023-11-01 2024-12-31 RA LA UOD POTOSI, CONSUL TOR DE LINEA PAR III BO-EMPODERAR-368776-CS- INDV / ASISTENTE DE SUB PR IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-15 2023-10-05 2023-08-23 2024-12-31 OYECTOS PRODUCTIVOS PAR A LA UOD POTOSI, CONSULT OR DE LINA PAR III BO-EMPODERAR-368778-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 PRODUCTIVAS PARA LA UOR CAMARGO, CONSULTOR DE L INEA PAR III BO-EMPODERAR-368779-CS- INDV / CHOFER PARA LA UOR IBRD / 94370 3. Project Management Posterior Individual Open - National 5,222.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-18 2023-08-31 2023-09-29 2023-10-05 2023-09-06 2024-12-31 CAMARGO, CONSULTOR DE L INEA PAR III BO-EMPODERAR-368780-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-20 2023-10-05 2023-10-16 2024-12-31 PARA LA UOR CAMARGO, CO NSULTOR DE LINEA PAR III BO-EMPODERAR-368781-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 COMUNITARIAS PARA LA UO D COCHABAMBA, CONSULTO R DE LINEA PAR III BO-EMPODERAR-368783-CS- INDV / ANALISTA SOCIAL Y G IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-11-01 2024-12-31 ENERO PARA LA UOD COCHA BAMBA, CONSULTOR DE LINE A PAR III BO-EMPODERAR-368784-CS- INDV / ASISTENTE DE SUBPR OYECTOS COMUNITARIOS PA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-09-11 2023-08-31 2023-09-21 2023-10-05 2023-10-03 2024-12-31 RA LA UOD COCHABAMBA, C ONSULTOR DE LINEA PAR III BO-EMPODERAR-368785-CS- INDV / ASISTENTE DE SUB PR OYECTOS PRODUCTIVOS PAR IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-09-11 2023-08-31 2023-09-21 2023-10-05 2023-10-03 2024-12-31 A LA UOD COCHABAMBA, CO NSULTOR DE LINEA PAR III BO-EMPODERAR-368786-CS- INDV / OFICIAL DE SUBPROYE CTOS DE INFRAESTRUCTURA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 PARA LA UOD CHUQUISACA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368787-CS- INDV / OFICIAL DE SUB PROY IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 ECTOS DE RIEGO PARA LA U OD CHUQUISCA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368788-CS- INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Open - National 15,375.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-20 2023-10-05 2023-10-03 2024-12-31 MENTAL UOD CHUQUISCA, C ONSULTOR DE LINEA PAR III BO-EMPODERAR-368789-CS- INDV / ASISTENTE DE SUB PR OYECTOS COMUNITARIOS PA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Rescindido 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-22 2023-10-05 2023-08-28 2024-12-31 RA LA UOD CHUQUISCA, CON SULTOR DE LINEA PAR III BO-EMPODERAR-368790-CS- INDV / ASISTENTE DE SUB PR OYECTOS PRODUCTIVOS PAR IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-22 2023-10-05 2023-08-28 2024-12-31 A LA UOD CHUQUISACA, CON SULTOR DE LINEA PAR III BO-EMPODERAR-368791-CS- INDV / OFICIAL DE SUBPROYE CTOS DE INFRAESTRUCTURA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 PARA LA UOD TARIJA, CONSU LTOR DE LINEA PAR III BO-EMPODERAR-368792-CS- INDV / OFICIAL DE SUBPROYE IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-19 2024-12-31 CTOS DE RIEGO PARA LA UO D TARIJA, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368794-CS- INDV / OFICIAL DE SUBPROYE IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 CTOS DE RIEGO PARA LA UO D ORURO, CONSULTOR DE LI NEA PAR III BO-EMPODERAR-368795-CS- INDV / ANALISTA AMBIENTAL IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 PARA LA UOD ORURO, CONS ULTOR DE LINEA PAR III BO-EMPODERAR-368796-CS- INDV / ANALISTA SOCIAL Y G IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-30 2023-08-31 2023-09-28 2023-10-05 2023-10-23 2024-12-31 ENERO PARA LA UOD ORURO , CONSULTOR DE LINEA PAR I II BO-EMPODERAR-368797-CS- INDV / ASISTENTE DE SUBPR IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-21 2023-10-05 2023-08-22 2024-12-31 OYECTOS COMUNITARIOS PA RA LA UOD ORURO, CONSUL TOR DE LINEA PAR III Page 8 BO-EMPODERAR-368798-CS- INDV / ASISTENTE DE SUBPR IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-08 2023-10-05 2023-08-14 2024-12-31 OYECTOS PRODUCTIVOS PAR A LA UOD ORURO, CONSULT OR DE LINEA PAR III BO-EMPODERAR-368799-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 COMUNITARIAS PARA LA UO D SANTA CRUZ, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368800-CS- INDV / OFICIAL DE SUBPROYE IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-10-06 2023-10-05 2023-11-01 2024-12-31 CTOS DE RIEGO PARA LA UO D SANTA CRUZ, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368801-CS- INDV / ASISTENTE DE SUB PR OYECTOS PRODUCTIVOS PAR IBRD / 94370 3. Project Management Posterior Individual Open - National 7,600.00 0.00 Firmado 2023-06-22 2023-06-29 2023-08-10 2023-07-20 2023-08-31 2023-08-22 2023-10-05 2023-08-28 2024-12-31 A LA UOD SANTA CRUZ, CON SULTOR DE LINEA PAR III BO-EMPODERAR-368802-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 11,366.00 0.00 Firmado 2023-06-22 2023-06-23 2023-08-10 2023-07-02 2023-08-31 2023-09-06 2023-10-05 2023-09-18 2024-12-31 PARA LA UOR CHIQUITANIA, CONSULTOR DE LINEA PAR III BO-EMPODERAR-368803-CS- INDV / CONSULTOR INDIVIDU Selección directa AL POR PRODUCTO PARA AC IBRD / 94370 3. Project Management Posterior Direct - National 2,611.00 0.00 Finalizado 2023-06-22 2023-06-26 2023-07-02 2023-07-18 2023-09-05 2023-07-26 2024-03-03 de consultores TUALIZAR EL REGISTRO DE A CTIVIDADES APROBADAS EN EL STEP BO-EMPODERAR-357205-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-17 2023-05-03 2023-04-27 2023-04-30 2023-05-07 2023-12-31 UOD BENI BO-EMPODERAR-356753-CS- INDV / RESPONSABLE EN PPC IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Cancelado 2023-04-14 2023-04-24 2023-04-27 2023-05-04 2023-12-31 Y PROYECTOS BO-EMPODERAR-369772-CS- INDV / OPERADOR REGIONAL IBRD / 94370 3. Project Management Posterior Individual Open - National 12,471.00 0.00 Firmado 2023-06-30 2023-07-12 2023-08-18 2023-07-19 2023-09-08 2023-09-20 2023-10-13 2023-10-03 2024-04-10 UOR CAMARGO BO-EMPODERAR-356786-CS- INDV / OFICIAL DE SUB PROY IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-14 2023-05-04 2023-04-24 2023-04-27 2023-05-04 2023-12-31 ECTOS DE RIEGO UOD COCH ABAMBA BO-EMPODERAR-374370-CS- INDV / ANALISTA DE ADQUISI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,472.00 0.00 Firmado 2023-07-26 2023-08-09 2023-09-13 2023-08-30 2023-10-04 2023-10-18 2023-11-08 2023-11-06 2023-12-31 CIONES PARA INFRAESTRUCT URA - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374371-CS- INDV / ASISTENTE FINANCIER IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-26 2023-10-04 2023-09-13 2023-11-03 2023-10-04 2023-11-13 2023-11-08 2023-11-16 2023-12-31 O PARA LA UCN - CONSULTO R DE LINEA PAR III BO-EMPODERAR-374372-CS- INDV / ASISTENTE DE SUBPR OYECTOS DE INFRAESTRUCT IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-26 2023-08-17 2023-09-13 2023-11-10 2023-10-04 2023-11-23 2023-11-08 2023-11-27 2023-12-31 URA PARA LA UOD LA PAZ - C ONSULTOR DE LINEA PAR III BO-EMPODERAR-374381-CS- INDV / ASISTENTE DE SUBPR IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 En ejecución 2023-07-26 2023-08-17 2023-09-13 2023-10-04 2023-11-08 2023-12-31 OYECTOS DE RIEGO PARA LA UOD LA PAZ - CONSULTOR D E LINEA PAR III BO-EMPODERAR-374563-CS- INDV / OFICIAL DE SUBPROYE IBRD / 94370 3. Project Management Posterior Individual Open - National 9,472.00 0.00 En ejecución 2023-07-27 2023-08-09 2023-09-14 2023-10-05 2023-11-09 2023-12-31 CTOS DE RIEGO UOD BENI - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374566-CS- INDV / ASISTENTE DE SUBPR OYECTOS DE INFRAESTRUCT IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 2023-08-17 2023-09-14 2023-09-15 2023-10-05 2023-10-04 2023-11-09 2023-10-05 2023-12-31 URA PARA LA UOD COCHABA MBA - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374567-CS- INDV / ASISTENTE DE SUBPR OYECTOS DE INFRAESTRUCT IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 2023-08-17 2023-09-14 2023-11-15 2023-10-05 2023-11-23 2023-11-09 2023-11-29 2023-12-31 URA PARA LA UOD CHUQUIS ACA - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374569-CS- INDV / ASISTENTE DE SUBPR OYECTOS DE INFRAESTRUCT IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 2023-08-17 2023-09-14 2023-09-14 2023-10-05 2023-09-28 2023-11-09 2023-10-04 2023-12-31 URA PARA LA UOD TARIJA - C ONSULTOR DE LINEA PAR III BO-EMPODERAR-374570-CS- INDV / ASISTENTE DE SUBPR OYECTOS DE INFRAESTRUCT IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 2023-08-17 2023-09-14 2023-09-14 2023-10-05 2023-09-20 2023-11-09 2023-09-26 2023-12-31 URA PARA LA UOD ORURO - CONSULTOR DE LINEA PAR III BO-EMPODERAR-374572-CS- INDV / ASISTENTE DE SUBPR OYECTOS DE INFRAESTRUCT IBRD / 94370 3. Project Management Posterior Individual Open - National 6,333.00 0.00 Firmado 2023-07-27 2023-08-17 2023-09-14 2023-08-31 2023-10-05 2023-09-19 2023-11-09 2023-09-21 2023-12-31 URA PARA LA UOD SANTA CR UZ - CONSULTOR DE LINEA P AR III BO-EMPODERAR-356761-CS- IBRD / 94370 3. Project Management Posterior Individual Direct - National 18,706.00 0.00 Cancelado 2023-04-14 2023-06-14 2023-04-24 2023-04-27 2023-05-04 2023-12-31 INDV / RESPONSABLE EN SIS TEMAS BO-EMPODERAR-356799-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 17,049.00 0.00 Cancelado 2023-04-14 2023-05-03 2023-04-24 2023-04-27 2023-05-04 2023-12-31 PRODUCTIVAS UOD SANTA C RUZ BO-EMPODERAR-374632-CS- INDV / OFICIAL DE SUBPROYE IBRD / 94370 3. Project Management Posterior Individual Direct - National 9,471.00 0.00 Firmado 2023-07-27 2023-08-09 2023-08-06 2023-03-31 2023-08-09 2023-08-28 2023-08-16 2023-09-04 2023-12-31 CTOS DE RIEGO PARA LA UO D COCHABAMBA -PAR III BO-EMPODERAR-375094-CS- INDV / ANALISTA EN FORTAL ECIMIENTO ORGANIZACIONA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,577.00 0.00 Firmado 2023-07-31 2023-08-23 2023-09-18 2023-08-30 2023-10-09 2023-10-18 2023-11-13 2023-11-01 2024-01-05 L PARA LA UCN CONSULTOR INDIVIDUAL DE LINEA PARA E L PAR II BO-EMPODERAR-374600-CS- CDS / Consultor Individual po r producto para ajuste de her IBRD / 94370 3. Project Management Posterior Individual Direct - National 24,942.00 0.00 Firmado 2023-08-18 2023-08-23 2023-08-28 2023-09-06 2023-09-18 2023-09-06 2023-10-23 2023-09-07 2024-04-20 ramientas y apoyo al inicio e n el sistema de información g erencial georreferenciado del PAR III BO-EMPODERAR-377834-CS- INDV / LEGAL JURIDICO CONS IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,333.00 0.00 Firmado 2023-08-18 2023-08-23 2023-08-28 2023-03-31 2023-08-31 2023-08-31 2023-09-07 2023-09-04 2023-12-31 ULTOR INDIVIDUAL DE LINEA PARA LA UNIDAD DE COORDI NACION NACIONAL BO-EMPODERAR-378752-CS- INDV / CHOFER PARA LA UOD IBRD / 94370 3. Project Management Posterior Individual Open - National 3,481.00 0.00 Firmado 2023-08-24 2023-09-04 2023-10-12 2023-10-11 2023-11-02 2023-10-23 2023-12-07 2023-10-24 2025-03-04 COCHABAMBA CONSULTOR I NDIVIDUAL DE LINEA - PAR III BO-EMPODERAR-379304-CS- INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Direct - National 10,250.00 0.00 Firmado 2023-08-28 2023-09-04 2023-09-07 2023-09-08 2023-09-10 2023-09-11 2023-09-17 2024-06-15 MENTAL DE TARIJA CONSULT OR INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-379305-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Direct - National 7,577.00 0.00 Firmado 2023-08-28 2023-09-04 2023-09-07 2023-03-31 2023-09-10 2023-09-11 2023-09-17 2023-09-13 2024-06-15 PARA LA UOR RIBERALTA CO NSULTOR DE LINEA PARA EL PAR III Page 9 BO-EMPODERAR-379535-CS- INDV / 50 Facilitadores (apro ximadamente) UOD La Paz: F acilitador de la Unidad Opera 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 tiva Departamental La Paz, C itutional Strengthening onsultor por producto, Encar gado de la elaborar planes d e alianza (planes de negocio) para su financiamiento BO-EMPODERAR-379536-CS- INDV / 20 Facilitadores (apro ximadamente) UOR Rurrenab aque: Facilitador de la Unida 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 69,980.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 d Operativa Regional Rurren itutional Strengthening abaque, Consultor por produ cto, Encargado de la elaborar planes de alianza (planes de negocio) para su financiamie nto BO-EMPODERAR-379537-CS- INDV / 30 Facilitadores (apro ximadamente) UOD Oruro: F acilitador de la Unidad Opera 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 tiva Departamental Oruro, Co itutional Strengthening nsultor por producto, Encarg ado de la elaborar planes de alianza (planes de negocio) p ara su financiamiento BO-EMPODERAR-379538-CS- INDV / 30 Facilitadores UOD Potosi (aproximadamente): F acilitador de la Unidad Opera 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 tiva Departamental Potosi, C itutional Strengthening onsultor por producto, Encar gado de la elaborar planes d e alianza (planes de negocio) para su financiamiento BO-EMPODERAR-379539-CS- INDV / 45 Facilitadores UOD Cochabamba (aproximadame nte): Facilitador de la Unidad 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 Operativa Departamental Co itutional Strengthening chabamba, Consultor por pro ducto, Encargado de la elabo rar planes de alianza (planes de negocio) para su financia miento BO-EMPODERAR-379540-CS- INDV / 15 Facilitadores UOR CAMARGO (aproximadament e): Facilitador de la Unidad O 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 52,485.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 perativa Regional Camargo, itutional Strengthening Consultor por producto, Enca rgado de la elaborar planes d e alianza (planes de negocio) para su financiamiento BO-EMPODERAR-379541-CS- INDV / 40 Facilitadores UOD Tarija (aproximadamente): F acilitador de la Unidad Opera 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 139,960.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 tiva Departamental Tarija, Co itutional Strengthening nsultor por producto, Encarg ado de la elaborar planes de alianza (planes de negocio) p ara su financiamiento BO-EMPODERAR-379542-CS- INDV / 15 Facilitadores UOR Chiquitania (aproximadamen te): Facilitador de la Unidad 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 52,485.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 Operativa Regional Chiquitan itutional Strengthening ia, Consultor por producto, E ncargado de la elaborar plan es de alianza (planes de neg ocio) para su financiamiento BO-EMPODERAR-379543-CS- INDV / 50 Facilitadores UOD Santa Cruz (aproximadament e): Facilitador de la Unidad O 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 174,950.00 0.00 En ejecución 2023-08-29 2023-09-04 2023-10-17 2023-11-07 2023-12-12 2024-06-09 perativa Departamental Sant itutional Strengthening a Cruz, Consultor por product o, Encargado de la elaborar p lanes de alianza (planes de n egocio) para su financiamien to BO-EMPODERAR-379654-CS- INDV / 10 Facilitadores UOD BENI (aproximadamente): Fa cilitador de la Unidad Operati 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 34,990.00 0.00 En ejecución 2023-08-30 2023-09-04 2023-10-18 2023-11-08 2023-12-13 2024-06-10 va Departamental Beni, Cons itutional Strengthening ultor por producto, Encargad o de la elaborar planes de ali anza (planes de negocio) par a su financiamiento BO-EMPODERAR-379660-CS- INDV / 20 Facilitadores UOD PANDO (aproximadamente): Facilitador de la Unidad Oper 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 69,980.00 0.00 En ejecución 2023-08-30 2023-09-04 2023-10-18 2023-11-08 2023-12-13 2024-06-10 ativa Departamental de Pand itutional Strengthening o Consultor por producto, En cargado de la elaborar plane s de alianza (planes de nego cio) para su financiamiento BO-EMPODERAR-379662-CS- INDV / 10 Facilitadores UOR Riberalta (aproximadamente) : Facilitador de la Unidad Ope 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 34,990.00 0.00 En ejecución 2023-08-30 2023-09-04 2023-10-18 2023-11-08 2023-12-13 2024-06-10 rativa Regional Riberalta, Co itutional Strengthening nsultor por producto, Encarg ado de la elaborar planes de alianza (planes de negocio) p ara su financiamiento BO-EMPODERAR-381938-CS- INDV / 40 Facilitadores UOD Chuquisaca (aproximadamen te): Facilitador de la Unidad 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 139,960.00 0.00 En ejecución 2023-09-13 2023-10-02 2023-11-01 2023-11-22 2023-12-27 2024-06-24 Operativa Departamental Ch itutional Strengthening uquisaca, Consultor por prod ucto, Encargado de la elabor ar planes de alianza (planes de negocio) para su financia miento BO-EMPODERAR-381939-CS- INDV / 30 Facilitadores UOR CHACO -CAMIRI (aproximada mente): Facilitador de la Uni 1. Capacity Building and Inst IBRD / 94370 Posterior Individual Open - National 104,970.00 0.00 En ejecución 2023-09-13 2023-10-02 2023-11-01 2023-11-22 2023-12-27 2024-06-24 dad Operativa Regional Chac itutional Strengthening o, Consultor por producto, En cargado de la elaborar plane s de alianza (planes de nego cio) para su financiamiento BO-EMPODERAR-385098-CS- INDV / CHOFER II PARA LA U IBRD / 94370 3. Project Management Posterior Individual Open - National 2,611.00 0.00 Firmado 2023-10-02 2023-10-04 2023-11-20 2023-11-03 2023-12-11 2023-11-08 2024-01-15 2023-11-09 2025-01-31 OD ORURO - PAR III BO-EMPODERAR-385099-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 5,683.00 0.00 Firmado 2023-10-02 2023-10-04 2023-11-20 2023-10-22 2023-12-11 2023-11-24 2024-01-15 2023-12-11 2025-01-31 II PARA LA UOD COCHABAMB A - PAR III CONSULTOR INDIVI DUAL DE LINEA BO-EMPODERAR-385101-CS- INDV / ANALISTA FINANCIERO IBRD / 94370 3. Project Management Posterior Individual Open - National 5,683.00 0.00 Firmado 2023-10-02 2023-10-04 2023-11-20 2023-10-22 2023-12-11 2023-11-24 2024-01-15 2023-12-11 2025-01-31 (SISIN) PARA LA UNIDAD DE CORDINACION NACIONAL - P AR III BO-EMPODERAR-385102-CS- INDV / ASISTENTE DE SUB PR IBRD / 94370 3. Project Management Posterior Individual Open - National 3,780.00 0.00 Firmado 2023-10-02 2023-10-05 2023-11-20 2023-11-07 2023-12-11 2023-11-10 2024-01-15 2023-11-14 2025-01-31 OYECTOS DE INFRAESTRUCT URA PARA LA UOD POTOSI - PAR III BO-EMPODERAR-385111-CS- CDS / 8 PROFESIONALES DE APOYO PARA DISTINTAS ARE IBRD / 94370 3. Project Management Posterior Individual Direct - National 24,075.00 0.00 Firmado 2023-10-06 2023-10-16 2023-10-16 2023-10-25 2023-11-06 2023-12-14 2023-12-11 2023-12-18 2024-06-08 AS DEL PAR III - PRACTICAS P ROFESIONALES (CONSULTOR ES POR PRODUCTO) BO-EMPODERAR-385109-CS- CDS / CONSULTORIA POR PR ODUCTO: PROFESIONAL DE A IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,582.00 0.00 Finalizado 2023-10-04 2023-10-13 2023-10-14 2023-11-14 2023-11-04 2023-11-15 2023-12-09 2023-11-20 2024-06-06 POYO A EVALUACION DE SUB PROYECTOS DE INFRAESTRU CTURA UNIDAD DE COORDIN ACION NACIONAL BO-EMPODERAR-388726-CS- INDV / OFICIAL DE SUB PROY IBRD / 94370 3. Project Management Posterior Individual Direct - National 3,789.00 0.00 Firmado 2023-10-20 2023-10-23 2023-10-30 2023-11-23 2023-11-02 2023-11-30 2023-11-09 2023-12-06 2024-03-25 ECTOS COMUNITARIOS PARA LA UOD CHUQUISACA - PAR II I Page 10 BO-EMPODERAR-390112-CS- INDV / OFICIAL DE ALIANZA P IBRD / 94370 3. Project Management Posterior Individual Open - National 23,413.00 0.00 Firmado 2023-10-27 2023-11-07 2023-12-15 2024-01-28 2024-01-05 2024-04-10 2024-02-09 2024-12-31 ARA LA UOD ORURO - CONSU LTOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-391003-CS- CDS / SERVICIO DE CONSULT ORIA DE DESARROLLO DE SI STEMA PARA LA ADMINISTRA Selección directa IBRD / 94370 3. Project Management Posterior Direct - National 50,522.00 0.00 Firmado 2023-11-01 2023-11-07 2023-11-11 2023-11-28 2024-01-15 2024-07-13 CION DE LA LICITACION, EJEC de consultores UCION Y CIERRE DE SUB PRO YECTOS DE INFRAESTRUCTU RA PRODUCTIVA COMPLEME NTARIA - PAR III (ETAPA II) BO-EMPODERAR-396645-CS- CDS / EVALUACIÓN DE DESE MPEÑO DEL PERSONAL TÉCNI CO DEL PROYECTO DE INNOV Selección directa IBRD / 94370 3. Project Management Posterior Direct - National 29,620.00 0.00 En ejecución 2023-12-05 2024-01-03 2023-12-15 2024-01-04 2024-02-18 2024-06-22 ACIÓN PARA SISTEMAS ALIME de consultores NTARIOS RESILIENTES (ALIAN ZAS RURALES – PAR III) Y EST UDIO DE SATISFACCIÓN DE B ENEFICIARIOS BO-EMPODERAR-397982-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2024-01-02 2024-01-30 2024-01-28 2024-02-20 2024-04-10 2024-03-26 2025-04-12 II PARA LA UOD ORURO - PAR III BO-EMPODERAR-397985-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2024-01-02 2024-01-30 2024-01-28 2024-02-20 2024-04-10 2024-03-26 2025-04-12 II PARA LA UOD POTOSI - PAR III BO-EMPODERAR-397991-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2024-01-02 2024-01-30 2024-01-28 2024-02-20 2024-04-10 2024-03-26 2025-04-12 II PARA LA UOD CHUQUISACA - PAR III BO-EMPODERAR-397993-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2024-01-02 2024-01-30 2024-01-28 2024-02-20 2024-04-10 2024-03-26 2025-04-12 II PARA LA UOD TARIJA - PAR III BO-EMPODERAR-397995-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2023-12-12 2024-01-02 2024-01-30 2024-01-28 2024-02-20 2024-04-10 2024-03-26 2025-04-12 II PARA LA UOD PANDO - PAR III BO-EMPODERAR-398015-CS- INDV / 20 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOR CH ACO (CAMIRI) BO-EMPODERAR-398005-CS- INDV / 20 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 45,772.59 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOD OR URO BO-EMPODERAR-398008-CS- INDV / 10 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOR CA MARGO BO-EMPODERAR-398011-CS- INDV / 20 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOD CO CHABAMBA BO-EMPODERAR-398012-CS- INDV / 20 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOD SA NTA CRUZ BO-EMPODERAR-398007-CS- INDV / 20 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOD CH UQUISACA BO-EMPODERAR-398006-CS- INDV / 20 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOD PO TOSI BO-EMPODERAR-398001-CS- INDV / 10 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOD PA NDO BO-EMPODERAR-398002-CS- INDV / 20 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOD LA PAZ BO-EMPODERAR-398013-CS- INDV / 10 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOR CHI QUITANIA BO-EMPODERAR-398004-CS- INDV / 10 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOR RIB ERALTA BO-EMPODERAR-398003-CS- INDV / 10 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOR RU RRENABAQUE BO-EMPODERAR-398014-CS- INDV / 10 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 22,887.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOD BE NI BO-EMPODERAR-398010-CS- INDV / 20 CONSULTORES PO 1. Capacity Building and Inst R PRODUCTO PARA LA EVALU IBRD / 94370 Posterior Individual Open - National 45,772.00 0.00 En ejecución 2023-12-19 2024-01-08 2024-02-06 2024-02-27 2024-04-02 2024-09-29 itutional Strengthening ACIÓN FINANCIERA DE ALIAN ZAS PRODUCTIVAS - UOD TA RIJA BO-EMPODERAR-399455-CS- Ejecución pendie INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 2023-12-19 2024-02-06 2024-02-27 2024-04-02 2025-04-19 nte II PARA LA UOD CAMIRI (CHA CO) - PAR III BO-EMPODERAR-401624-CS- INDV / SECRETARIA PARA LA IBRD / 94370 3. Project Management Posterior Individual Direct - National 10,309.00 0.00 Firmado 2024-01-08 2024-01-08 2024-01-18 2024-01-09 2024-01-21 2024-01-09 2024-01-28 2024-06-13 UNIDAD DE COORDINACION NACIONAL - PAR III BO-EMPODERAR-368793-CS- INDV / OPERADOR DEPARTA IBRD / 94370 3. Project Management Posterior Individual Open - National 15,375.00 0.00 Cancelado 2023-06-22 2023-06-23 2023-08-10 2023-08-31 2023-10-05 2024-12-31 MENTAL PARA LA UOD TARIJA , CONSULTOR DE LINEA PAR I II BO-EMPODERAR-403600-CS- CDS / CONSULTOR INDIVIDU Selección directa AL POR PRODUCTO PARA RE IBRD / 94370 3. Project Management Posterior Direct - National 2,690.00 0.00 Firmado 2024-01-17 2024-01-23 2024-01-27 2024-01-29 2024-04-01 2024-09-28 de consultores GISTRO DE INFORMACION EN EL SISTEMA STEP DEL PAR III BO-EMPODERAR-403941-CS- INDV / ASISTENTE DE SUB PR IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-02-14 2024-03-29 2024-03-04 2024-05-03 2024-12-31 OYECTOS DE RIEGO - UOD LA PAZ, CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-403942-CS- INDV / SECRETARIA - UOD LA IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-02-14 2024-03-29 2024-02-27 2024-05-03 2024-12-31 PAZ, CONSULTOR INDIVIDUA L DE LINEA PAR III Page 11 BO-EMPODERAR-403947-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-01-28 2024-03-29 2024-04-10 2024-05-03 2024-12-31 - UOR CHACO (CAMIRI), CON SULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-403952-CS- INDV / ASISTENTE DE SUBPR IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-02-14 2024-03-29 2024-02-26 2024-05-03 2024-12-31 OYECTOS DE RIEGO - UOD PA NDO, CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-403954-CS- INDV / OFICIAL DE SUB PROY IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-01-28 2024-03-29 2024-04-10 2024-05-03 2024-12-31 ECTOS DE RIEGO - UOD PAN DO, CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403955-CS- INDV / ANALISTA AMBIENTAL IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-01-28 2024-03-29 2024-04-10 2024-05-03 2024-12-31 Y SEGURIDAD SOCIAL - UOD PANDO, CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-403957-CS- INDV / ANALISTA SOCIAL Y D IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-01-28 2024-03-29 2024-04-10 2024-05-03 2024-12-31 E GENERO - UOD PANDO, CO NSULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-403958-CS- INDV / SECRETARIA - UOR RI IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-02-14 2024-03-29 2024-02-28 2024-05-03 2024-12-31 BERALTA, CONSULTOR INDIVI DUAL DE LINEA PAR III BO-EMPODERAR-403959-CS- INDV / ASISTENTE DE SUB PR IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-02-15 2024-03-29 2024-02-28 2024-05-03 2024-12-31 OYECTOS DE RIEGO - UOD P OTOSI, CONSULTOR INDIVID UAL DE LINEA PAR III BO-EMPODERAR-403965-CS- INDV / OFICIAL DE SUBPROYE CTOS DE INFRAESTRUCTURA IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-01-28 2024-03-29 2024-04-10 2024-05-03 2024-12-31 - UOD COCHABAMBA, CONSU LTOR INDIVIDUAL DE LINEA P AR III BO-EMPODERAR-403966-CS- INDV / ASISTENTE DE SUB PR OYECTOS DE RIEGO - UOD C IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-02-15 2024-03-29 2024-03-04 2024-05-03 2024-12-31 HUQUISACA, CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-403967-CS- INDV / SECRETARIA - UOD CH IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-03-15 2024-03-29 2024-04-02 2024-05-03 2024-12-31 UQUISACA, CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-403969-CS- INDV / SECRETARIA - UOD TA IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 RIJA, CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-403970-CS- INDV / CHOFER - UOD TARIJA, IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-02-15 2024-03-29 2024-03-08 2024-05-03 2024-12-31 CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403971-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Cancelado 2024-01-19 2024-03-08 2024-03-29 2024-05-03 2024-12-31 PRODUCTIVAS - UOD ORURO, CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-403972-CS- INDV / ASISTENTE DE SUB PR IBRD / 94370 3. Project Management Posterior Individual Open - National 15,656.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-02-15 2024-03-29 2024-02-26 2024-05-03 2024-12-31 OYECTOS DE RIEGO - UOD O RURO, CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-403973-CS- INDV / SECRETARIA - UOD OR IBRD / 94370 3. Project Management Posterior Individual Open - National 10,758.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-04-25 2024-03-29 2024-05-02 2024-05-03 2024-12-31 URO, CONSULTOR INDIVIDUA L DE LINEA PAR III BO-EMPODERAR-403977-CS- INDV / ANALISTA AMBIENTAL Y SEGURIDAD SOCIAL - UOR IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-01-28 2024-03-29 2024-04-10 2024-05-03 2024-12-31 CAMARGO, CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-403978-CS- INDV / OFICIAL DE SUB PROY IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 Firmado 2024-01-19 2024-01-24 2024-03-08 2024-01-28 2024-03-29 2024-04-10 2024-05-03 2024-12-31 ECTOS DE RIEGO - UOR CAM ARGO, CONSULTOR INDIVIDU AL DE LINEA PAR III BO-EMPODERAR-403979-CS- INDV / ANALISTA SOCIAL Y D IBRD / 94370 3. Project Management Posterior Individual Open - National 23,414.00 0.00 En ejecución 2024-01-19 2024-01-24 2024-03-08 2024-03-29 2024-05-03 2024-12-31 E GENERO - UOR CAMARGO, CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-405255-CS- INDV / ESPECIALISTA EN RIEG IBRD / 94370 3. Project Management Posterior Individual Open - National 23,549.00 0.00 Firmado 2024-01-25 2024-01-25 2024-03-14 2024-01-28 2024-04-04 2024-04-10 2024-05-09 2025-01-06 O PARA LA UCN - PAR III BO-EMPODERAR-405256-CS- INDV / ESPECIALISTA EN NEG IBRD / 94370 3. Project Management Posterior Individual Open - National 23,549.00 0.00 En ejecución 2024-01-25 2024-01-25 2024-03-14 2024-04-04 2024-05-09 2025-01-06 OCIOS PARA LA UCN - PAR III BO-EMPODERAR-406713-CS- INDV / CONSULTOR INDIVIDU AL POR PRODUCTO PARA SE IBRD / 94370 3. Project Management Posterior Individual Open - National 5,220.00 0.00 En ejecución 2024-02-09 2024-02-14 2024-03-29 2024-04-19 2024-05-24 2024-11-20 GUIMIENTO A OBSERVACION ES AL CONTROL INTERNO DE L PROYECTO PAR III BO-EMPODERAR-414687-CS- INDV / ANALISTA SOCIAL Y D IBRD / 94370 3. Project Management Posterior Individual Open - National 19,511.00 0.00 En ejecución 2024-03-07 2024-03-11 2024-04-25 2024-05-16 2024-06-20 2025-02-17 E GENERO PARA LA UOD BEN I - PAR III BO-EMPODERAR-414688-CS- INDV / ASISTENTE DE SUBPR IBRD / 94370 3. Project Management Posterior Individual Open - National 13,046.00 0.00 Firmado 2024-03-07 2024-03-11 2024-05-08 2024-03-26 2024-05-15 2024-04-12 2024-07-03 2024-08-01 OYECTOS PRODUCTIVOS PAR A LA UOD BENI - PAR III BO-EMPODERAR-414689-CS- INDV / ASISTENTE DE SUB PR IBRD / 94370 3. Project Management Posterior Individual Open - National 13,046.00 0.00 Firmado 2024-03-07 2024-03-11 2024-05-08 2024-03-26 2024-05-15 2024-04-08 2024-07-03 2024-08-01 OYECTOS DE RIEGO PARA LA UOD BENI - PAR III BO-EMPODERAR-416668-CS- INDV / ASISTENTE DE SUBPR IBRD / 94370 3. Project Management Posterior Individual Open - National 8,169.00 0.00 Firmado 2024-03-15 2024-03-20 2024-05-16 2024-04-11 2024-05-23 2024-04-24 2024-07-11 2024-08-09 OYECTOS PRODUCTIVOS II P ARA LA UOD LA PAZ - PAR III BO-EMPODERAR-416669-CS- INDV / ASISTENTE DE SUB PR IBRD / 94370 3. Project Management Posterior Individual Open - National 8,170.00 0.00 En ejecución 2024-03-15 2024-03-20 2024-05-16 2024-04-11 2024-05-23 2024-04-24 2024-07-11 2024-08-09 OYECTOS COMUNITARIOS II P ARA LA UOD LA PAZ - PAR III BO-EMPODERAR-416670-CS- INDV / OFICIAL DE ALIANZAS IBRD / 94370 3. Project Management Posterior Individual Direct - National 15,609.00 0.00 Firmado 2024-03-15 2024-03-20 2024-03-25 2024-04-01 2024-03-28 2024-03-26 2024-04-04 2024-08-19 PRODUCTIVAS PARA LA UOD ORURO - PAR III BO-EMPODERAR-420607-CS- INDV / ASISTENTE DE SUBPR OYECTOS PRODUCTIVOS PAR IBRD / 94370 3. Project Management Posterior Individual Open - National 11,741.00 0.00 En ejecución 2024-04-04 2024-04-05 2024-06-05 2024-06-12 2024-07-31 2024-08-29 A LA UOR RIBERALTA - CONS ULTOR DE LINEA PAR III BO-EMPODERAR-420608-CS- INDV / ANALISTA AMBIENTAL Y SEGURIDAD SOCIAL - UOR IBRD / 94370 3. Project Management Posterior Individual Open - National 17,560.00 0.00 En ejecución 2024-04-04 2024-04-05 2024-05-23 2024-06-13 2024-07-18 2025-03-17 RIBERALTA, CONSULTOR INDI VIDUAL DE LINEA PAR III BO-EMPODERAR-420613-CS- INDV / OFICIAL DE SUBPROYE CTOS DE INFRAESTRUCTURA IBRD / 94370 3. Project Management Posterior Individual Open - National 17,560.00 0.00 En ejecución 2024-04-04 2024-04-05 2024-05-23 2024-06-13 2024-07-18 2025-03-17 - UOR RIBERALTA, CONSULT OR INDIVIDUAL DE LINEA PA R III Page 12 BO-EMPODERAR-420615-CS- INDV / ASISTENTE DE SUB PR OYECTOS COMUNITARIOS PA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,741.00 0.00 En ejecución 2024-04-04 2024-04-05 2024-06-05 2024-06-12 2024-07-31 2024-08-29 RA LA UOR CAMARGO - CONS ULTOR DE LINEA PAR III BO-EMPODERAR-420619-CS- INDV / ASISTENTE DE SUB PR OYECTOS DE RIEGO PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 11,742.00 0.00 En ejecución 2024-04-04 2024-04-05 2024-06-05 2024-06-12 2024-07-31 2024-08-29 UOD COCHABAMBA - CONSU LTOR DE LINEA PAR III BO-EMPODERAR-420849-CS- INDV / CONSULTOR POR PRO DUCTO PROFESIONAL ESPECI IBRD / 94370 3. Project Management Posterior Individual Direct - National 6,109.00 0.00 En ejecución 2024-04-05 2024-04-08 2024-04-15 2024-05-06 2024-06-10 2024-12-07 ALISTA EN HIDROLOGIA PARA ESTUDIOS DE BALANCE HIDR ICO - PAR III BO-EMPODERAR-426145-CS- INDV / ASISTENTE FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 O PARA LA UOD LA PAZ - CO NSULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-426146-CS- INDV / ANALISTA FIDUCIARIO IBRD / 94370 3. Project Management Posterior Individual Open - National 13,658.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 PARA LA UOD RURRENABAQ UE - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426147-CS- INDV / OPERADOR DEPERTA IBRD / 94370 3. Project Management Posterior Individual Open - National 18,475.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 MENTAL DEL BENI - CONSULT OR INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-426174-CS- INDV / ASISTENTE DE SUBPR OYECTOS PRODUCTIVOS PAR IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 A LA UOD CHACO - CAMIRI, C ONSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-426183-CS- INDV / ASISTENTE DE SUBPR OYECTOS DE INFRAESTRUCT IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 URA PARA LA UOD PANDO - C ONSULTOR INDIVIDUAL DE LI NEA PAR III BO-EMPODERAR-426184-CS- INDV / ASISTENTE FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 O PARA LA UOD PANDO - CO NSULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-426186-CS- INDV / ASISTENTE FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 O PARA LA UOD POTOSI - CO NSULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-426188-CS- INDV / OFICIAL DE SUBPROYE CTOS PRODUCTIVOS PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 13,658.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 A UOD POTOSI - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426190-CS- INDV / ASISTENTE FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 O PARA LA UOD COCHABAMB A - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426192-CS- INDV / ASISTENTE FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 O PARA LA UOD CHUQUISAC A - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426195-CS- INDV / ASISTENTE SUBPROYE CTOS PRODUCTIVOS PARA L IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 A UOD TARIJA - CONSULTOR I NDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426198-CS- INDV / ASISTENTE FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 O PARA LA UOD TARIJA - CON SULTOR INDIVIDUAL DE LINE A PAR III BO-EMPODERAR-426202-CS- INDV / ASISTENTE FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 O PARA LA UOD ORURO - CO NSULTOR INDIVIDUAL DE LIN EA PAR III BO-EMPODERAR-426205-CS- INDV / ASISTENTE DE SUBPR OYECTOS DE RIEGO PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 UOD SANTA CRUZ - CONSULT OR INVIDUAL DE LINEA PAR II I BO-EMPODERAR-426207-CS- INDV / ASISTENTE FIDUCIARI IBRD / 94370 3. Project Management Posterior Individual Open - National 9,132.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 O PARA LA UOD SANTA CRUZ - CONSULTOR INDIVIDUAL DE LINEA PAR III BO-EMPODERAR-426208-CS- INDV / SECRETARIA PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,275.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 UOR RIBERALTA - CONSULTO R DE LINEA PAR III BO-EMPODERAR-426209-CS- INDV / SECRETARIA PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 6,275.00 0.00 En ejecución 2024-05-06 2024-05-08 2024-06-24 2024-07-15 2024-08-19 2025-04-18 UOR CHIQUITANIA - CONSUL TOR INDIVIDUAL DE LINEA PA R III BO-EMPODERAR-426411-CS- INDV / TECNICO DE ARCHIVO IBRD / 94370 3. Project Management Posterior Individual Open - National 6,957.00 0.00 En ejecución 2024-05-08 2024-05-23 2024-06-26 2024-07-17 2024-08-21 2025-02-17 - CONSULTOR INDIVIDUAL PO R PRODUCTO PAR III BO-EMPODERAR-426348-CS- INDV / AUXILIAR DE INFRAES IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,213.00 0.00 En ejecución 2024-05-08 2024-05-13 2024-05-18 2024-06-08 2024-07-13 2025-01-09 TRUCTURA PARA LA OFICINA NACIONAL - CONSULTOR DE LINEA PAR III BO-EMPODERAR-426356-CS- INDV / AUXILIAR AMBIENTAL Ejecución pendie IBRD / 94370 3. Project Management Posterior Individual Direct - National 4,213.00 0.00 2024-05-08 2024-05-18 2024-06-08 2024-07-13 2025-01-09 PARA LA OFICINA NACIONAL - nte CONSULTOR DE LINEA PAR III BO-EMPODERAR-426408-CS- INDV / TECNICO DE ACTIVOS IBRD / 94370 3. Project Management Posterior Individual Open - National 6,957.00 0.00 En ejecución 2024-05-08 2024-05-23 2024-06-26 2024-07-17 2024-08-21 2025-02-17 FIJOS - CONSULTOR INDIVIDU AL POR PRODUCTO PAR III BO-EMPODERAR-428467-CS- INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie A PARA LA CONSTRUCCIÓN S IBRD / 94370 Posterior Individual Open - National 9,437.32 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 d Productive Alliances nte ISTEMA DE RIEGO TECNIFICA DO SINDICATO AGRARIO 14 DE SEPTIEMBRE (SICAYA) BO-EMPODERAR-428469-CS- INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie A PARA LA CONSTRUCCIÓN S IBRD / 94370 Posterior Individual Open - National 5,642.25 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 d Productive Alliances nte ISTEMA DE RIEGO TECNIFICA DO COMUNIDAD HUERTA HU ASA (TOLATA) BO-EMPODERAR-428470-CS- INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie A PARA LA CONSTRUCCION S IBRD / 94370 Posterior Individual Open - National 11,009.70 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 d Productive Alliances nte ISTEMA DE RIEGO TECNIFICA DO SOTASI (VILA VILA) BO-EMPODERAR-428472-CS- INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie A PARA LA AMPLIACIÓN DEL IBRD / 94370 Posterior Individual Open - National 4,475.22 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 d Productive Alliances nte SISTEMA DE RIEGO UCHUCHI KANCHA EN EL MUNICIPIO DE TIRAQUE BO-EMPODERAR-428476-CS- INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie IBRD / 94370 Posterior Individual Open - National 9,908.47 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 A PARA LA CONSTRUCCIÓN P d Productive Alliances nte UENTE PEATONAL SICAYA CH ICO (SICAYA) Page 13 BO-EMPODERAR-428478-CS- INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie IBRD / 94370 Posterior Individual Open - National 6,651.64 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 A PARA LA CONSTRUCCION P d Productive Alliances nte UENTE VEHICULAR LLALLAGU ANI (ANZALDO) BO-EMPODERAR-428479-CS- INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie IBRD / 94370 Posterior Individual Open - National 12,842.57 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 A PARA LA CONSTRUCCIÓN P d Productive Alliances nte UENTE VEHICULAR HUALLPE RO ALTO (CLIZA) BO-EMPODERAR-428482-CS- INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie IBRD / 94370 Posterior Individual Open - National 7,922.49 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 A PARA LA CONSTRUCCIÓN P d Productive Alliances nte UENTE VEHICULAR PUCARA MAYU (VILA VILA) BO-EMPODERAR-428484-CS- INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie A PARA LA CONSTRUCCIÓN D IBRD / 94370 Posterior Individual Open - National 12,331.09 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 d Productive Alliances nte OS PUENTES VEHICULARES K OARI Y MAYUN PUNKU (TIRA QUE) BO-EMPODERAR-428488-CS- INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie IBRD / 94370 Posterior Individual Open - National 13,461.47 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 A PARA LA CONSTRUCCIÓN S d Productive Alliances nte ISTEMA DE RIEGO CKARI MAY U BO-EMPODERAR-428506-CS- INDV / SUPERVISIÓN TÉCNIC 2. Support to Community an Ejecución pendie A PARA LA CONSTRUCCIÓN S IBRD / 94370 Posterior Individual Open - National 13,486.88 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 d Productive Alliances nte ISTEMA DE RIEGO VINCUNTA YA – CORACABA (TAPACARI) BO-EMPODERAR-428510-CS- INDV / ASISTENCIA TÉCNICA 2. Support to Community an Ejecución pendie PARA LA CONSTRUCCIÓN SIS IBRD / 94370 Posterior Individual Open - National 9,558.55 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 d Productive Alliances nte TEMA DE RIEGO TECNIFICAD O SINDICATO AGRARIO 14 DE SEPTIEMBRE (SICAYA) BO-EMPODERAR-428513-CS- INDV / ASISTENCIA TÉCNICA 2. Support to Community an Ejecución pendie PARA LA CONSTRUCCIÓN SIS IBRD / 94370 Posterior Individual Open - National 4,471.22 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 d Productive Alliances nte TEMA DE RIEGO TECNIFICAD O COMUNIDAD HUERTA HUA SA (TOLATA) BO-EMPODERAR-428515-CS- INDV / ASISTENCIA TÉCNICA 2. Support to Community an Ejecución pendie IBRD / 94370 Posterior Individual Open - National 11,009.70 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 PARA LA CONSTRUCCION SIS d Productive Alliances nte TEMA DE RIEGO TECNIFICAD O SOTASI (VILA VILA) BO-EMPODERAR-428518-CS- INDV / ASISTENCIA TÉCNICA 2. Support to Community an Ejecución pendie PARA LA CONSTRUCCION SIS IBRD / 94370 Posterior Individual Open - National 13,486.88 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 d Productive Alliances nte TEMA DE RIEGO VINCUNTAYA – CORACABA (TAPACARI) BO-EMPODERAR-428521-CS- INDV / ASISTENCIA TÉCNICA 2. Support to Community an Ejecución pendie PARA LA AMPLIACION DEL SI IBRD / 94370 Posterior Individual Open - National 5,575.80 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 d Productive Alliances nte STEMA DE RIEGO UCHUCHI K ANCHA EN EL MUNICIPIO DE TIRAQUE BO-EMPODERAR-428523-CS- INDV / ASISTENCIA TÉCNICA 2. Support to Community an Ejecución pendie IBRD / 94370 Posterior Individual Open - National 11,286.16 0.00 2024-05-17 2024-07-05 2024-07-26 2024-08-30 2025-02-26 PARA LA CONSTRUCCIÓN SIS d Productive Alliances nte TEMA DE RIEGO CKARI MAYU BO-EMPODERAR-430688-CS- INDV / OFICIAL DE INFRAEST Ejecución pendie RUCTURA PARA LA UOR RUR IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 2024-05-29 2024-07-17 2024-08-07 2024-09-11 2025-05-11 nte RENABAQUE - CONSULTOR I NDIVIDUAL DE LINEA PAR III BO-EMPODERAR-430689-CS- INDV / ANALISTA EN ASPECT OS AMBIENTALES DE SALUD Ejecución pendie IBRD / 94370 3. Project Management Posterior Individual Open - National 11,706.00 0.00 2024-05-29 2024-07-17 2024-08-07 2024-09-11 2025-05-11 Y SEGURIDAD DE LA UOR RU nte RRENABAQUE - CONSULTOR I NVIDUAL DE LINEA DEL PAR I II BO-EMPODERAR-430690-CS- INDV / ANALISTA SOCIAL Y D Ejecución pendie E GENERO PARA LA UOR RUR IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 2024-05-29 2024-07-17 2024-08-07 2024-09-11 2025-05-11 nte RENABAQUE - CONSULTOR I NDIVIDUAL DE LINEA PAR III BO-EMPODERAR-430691-CS- INDV / ASISTENTE DE SUBPR Ejecución pendie OYECTOS COMUNITARIOS PA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,827.00 0.00 2024-05-29 2024-07-17 2024-08-07 2024-09-11 2025-05-11 nte RA LA UOD POTOSI - CONSUL TOR INDIVIDUAL DE LINEA PA RA EL PAR III BO-EMPODERAR-430692-CS- INDV / OFICIAL DE INFRAEST Ejecución pendie IBRD / 94370 3. Project Management Posterior Individual Open - National 11,707.00 0.00 2024-05-29 2024-07-17 2024-08-07 2024-09-11 2025-05-11 RUCTURA PARA LA UOR CAM nte ARGO - CONSULTOR INDIVID UAL DE LINEA PAR IIII BO-EMPODERAR-430693-CS- INDV / CHOFER PARA LA UOD Ejecución pendie IBRD / 94370 3. Project Management Posterior Individual Open - National 5,379.00 0.00 2024-05-29 2024-07-17 2024-08-07 2024-09-11 2025-05-11 TARIJA - CONSULTOR INDIVID nte UAL DE LINEA PAR III BO-EMPODERAR-430694-CS- INDV / ASISTENTE DE SUBPR Ejecución pendie OYECTOS DE RIEGO PARA LA IBRD / 94370 3. Project Management Posterior Individual Open - National 7,827.00 0.00 2024-05-29 2024-07-17 2024-08-07 2024-09-11 2025-05-11 nte UOD TARIJA - CONSULTOR IN DIVIDUAL DE LINEA PAR III BO-EMPODERAR-431493-CS- CDS / ASISTENTE DE ADQUISI Selección directa Ejecución pendie IBRD / 94370 3. Project Management Previa Direct - National 9,173.00 0.00 2024-06-03 2024-06-13 2024-08-17 2025-02-13 CIONES II - CONSULTOR INDI de consultores nte VIDUAL DE LINEA PAR III Page 14