P128534 Safety Nets Project Procurement Plan June 1st 2017 I. General 1. Bank’s approval Date of the procurement Plan: February 5, 2013 (initial): Revision 12 of Updated Procurement Plan, April 20, 2017 2. Date of General Procurement Notice: Nov 24, 2014 3. Period covered by this procurement plan: The procurement period of project covered from year November 2016 to March 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Comments Threshold US$ 1. NCB (Goods) Above or equal US$ 10 million 2. NCB (Works) Above or equal US$ 10 million 3. NCB (Non-Consultant Above or equal Services) US$ 2 million 4. Individual (Goods) Above or equal Justification to be US$ 10 million included in the PP 5. Individual (Non Consultant Above or equal Justification to be Services) US$ 2 million included in the PP 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for the Safety Nets Project issued on January 2014 by Project Coordination Unit. 1 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the 18 months of the current Procurement Plan-November 2016 to March 2018 (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Descripti Estimat Packages Dome Review Comme No. on ed stic by Bank nts Cost Prefe (Prior / US$ rence Post) million (yes/ no) 1 Summary 0 0 No No of the ICB (Works) 2 Summary 0 0 No No of the ICB (Goods) 3 Summary 0 0 No No of the NCB (Works) 4 Summary 1.5 18 No Post of the NCB (Goods) 5 Summary 0.74 2 No Prior of the NCB (Non- Consultant Services) 6 Summary 0.51 16 No Post of the NCB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) Above or equal US$ 1 million 2 2 Competitive Methods Above or equal (Individual) US$ 0.3 million 3 Single Source (Firms) Above or equal Justification to be US$ 1 million included in the PP 4 Single Source (Individual) Above or equal Justification to be US$ 0.3 million included in the PP 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimat Package Review Comment of ed s by Bank s Assignmen Cost (Prior / t US$ Post) million 1 Summary 1.7 8 Prior LCS; SSS; of number CQS; of Individual contracts ; that will be let under other methods 2 Summary 2 72 Post SSS; of number CQS; of Individual contracts that will be let under other methods 3 4 PROCUREMENT Cameroon : Cameroon Social Safety Nets PLAN General Information Country: Cameroon 2017-02-14 Bank’s Approval Date of the Original Procurement Plan: Revised Plan Date(s): (comma delineated, leave blank2022-08-22 if none) Project ID: P128534 GPN Date: Project Name: Cameroon Social Safety Nets Loan / Credit No: IDA / 52240, IDA / 62230, IDA / D2980 UNITE DE GESTION DU PROJET FILETS SOCIAUX Executing Agency(ies): WORKS Activity Reference No. / Procurement Estimated Actual A Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio High SEA/SH Process Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Contract Compl Description Component Review Type Method Document Ty Amount ( mount ( t and Recommendati Signed Contract No. ch ocess n (Y/N) Risk Status n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes etion pe US$) US$) on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned CM-UGP-PFS-26069-CW-RFQ Laying the Foundations of a Single Stage - One 2018-04-0 2018-08-2 2018-04-2 2018-10-0 2018-05- / Aménagement des bureaux IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 8,300.00 7,209.40 Achevé Envelope 1 9 4 5 15 de l'antenne régionale du No porting Project Managemen rd ouest t GOODS Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-5831-GO-RFB / Laying the Foundations of a fourniture du matériel infor Safety Net System and Sup Single Stage - One 2017-01-2 2017-02-0 2017-01-2 2017-03-1 2017-01-2 2017-04-1 2017-02-1 2017-05-1 2017-04-1 2017-11-1 2017-05-0 IDA / 52240 A posteriori Appel d'offres Open - National 253,000.00 243,616.43 Achevé matique, de téléphonie, et d' porting Project Managemen Envelope 4 1 9 2 4 1 0 6 7 2 8 équipement de bureau (en 3 t lots distincts) CM-UGP-PFS-6172-GO-RFQ / Fourniture du matériel de la Single Stage - One 2017-02-1 2017-02-1 2017-04-1 2017-03-1 2017-05-1 2017-04-1 phase 3 des THIMO dans 2 c IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 188,000.00 159,198.65 Achevé Envelope 8 0 5 0 5 4 ommunes de la région de l'E xtrême Nord et 2 communes de la région de l'EST CM-UGP-PFS-6231-GO-RFQ / Fourniture des boîtes à phar macie de la phase 3 des THI Single Stage - One 2017-02-2 2017-03-0 2017-04-1 2017-04-0 2017-05-0 2017-04-1 IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 29,000.00 31,172.51 Achevé MO pour 2 communes de la r Envelope 0 3 7 7 1 4 égion de l'Extrême Nord et 2 communes de la région de l' Est CM-UGP-PFS-6307-GO-RFQ / Laying the Foundations of a Single Stage - One 2017-03-2 2017-05-1 2018-05-1 Fourniture des fournitures d IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 60,000.00 0.00 Annulé Envelope 0 5 0 e bureau au Projet Filets Soc porting Project Managemen iaux t CM-UGP-PFS-7392-GO-RFQ / Laying the Foundations of a Single Stage - One 2017-05-3 2016-12-1 2017-06-0 2017-07-1 2017-08-1 2017-09-2 2017-10-2 Fourniture des consommabl IDA / 52240 Safety Net System and Sup A posteriori Appel d'offres Open - National 130,000.00 0.00 Annulé Envelope 1 2 5 7 6 0 0 es informatiques porting Project Managemen t CM-UGP-PFS-16931-GO-RFQ Laying the Foundations of a / fourniture des pièces de re Safety Net System and Sup Single Stage - One 2017-06-1 2017-08-1 2017-07-1 2017-08-2 2017-08-1 IDA / 52240 A posteriori Demande de prix Open - National 37,500.00 32,502.70 Achevé change pour véhicules et mo porting Project Managemen Envelope 9 4 7 8 7 tos du Projet Filets Sociaux t CM-UGP-PFS-23000-GO-RFQ / fourniture des boites à pha rmacie pour la phase 4 des T Single Stage - One 2017-08-1 2017-09-0 2017-10-1 2017-10-1 2018-04-1 2017-10-2 IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 25,100.00 21,014.35 Achevé HIMO dans 2 communes de l Envelope 5 4 3 6 1 4 a région de l'Adamaoua et 1 commune de la région du No rd CM-UGP-PFS-25708-GO-RFQ Laying the Foundations of a Single Stage - One 2017-11-0 2018-03-2 2017-12-1 2018-04-0 2018-01-0 2018-04-1 / Fourniture du mobilier de b IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 8,300.00 6,813.69 Achevé Envelope 9 2 2 6 2 2 ureau de l'antenne du Nord- porting Project Managemen Ouest t CM-UGP-PFS-25990-GO-RFQ / Fourniture des boites à pha Single Stage - One 2017-10-1 2018-03-0 2017-11-1 2018-04-0 2017-12-0 2018-04-1 rmacie de la phase 5 des THI IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 25,100.00 20,966.02 Achevé Envelope 2 1 0 3 1 3 MO pour 2 communes de la r égion de l'Est et 2 commune s de la région du Nord ouest CM-UGP-PFS-26037-GO-RFQ Laying the Foundations of a / Fourniture des autocollant Safety Net System and Sup Single Stage - One 2017-09-2 2018-06-1 2017-10-1 2018-07-0 2017-10-3 2018-07-1 IDA / 52240 A posteriori Demande de prix Limited 2,000.00 2,081.57 Achevé s pour voitures et motos au porting Project Managemen Envelope 7 1 6 5 0 9 Projet Filets Sociaux t CM-UGP-PFS-23003-GO-RFQ / Fourniture du matériel et d Single Stage - One 2017-09-1 2017-09-0 2017-10-0 2017-10-1 2017-10-2 2017-11-2 es matériaux de travail pour IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 100,000.00 90,128.08 Achevé Envelope 1 4 3 6 4 2 la phase 4 des THIMO dans 2 communes de la région de l' Adamaoua CM-UGP-PFS-25561-GO-RFB Laying the Foundations of a / Fourniture du matériel roul Safety Net System and Sup Single Stage - One 2017-09-0 2017-04-2 2017-09-0 2017-09-0 2017-06-2 2017-09-0 2017-07-0 2017-09-0 2017-08-3 2017-10-0 IDA / 52240 A posteriori Appel d'offres Open - National 162,000.00 143,614.65 Signé ant autos et motos au projet porting Project Managemen Envelope 1 8 1 1 9 1 7 8 1 8 Filets Sociaux en deux lots d t istincts CM-UGP-PFS-25477-GO-RFQ Cash Transfer Program with Single Stage - One 2017-10-0 2017-11-1 2017-11-0 2017-12-2 2017-11-2 2018-01-2 / Fourniture des seaux au Pr IDA / 52240 Accompanying Measures to A posteriori Demande de prix Limited 38,000.00 26,101.20 Achevé Envelope 9 3 6 0 7 4 ojet Filets Sociaux Boost Household Productivit y CM-UGP-PFS-25475-GO-RFQ / Fourniture du matériel et d Single Stage - One 2017-09-0 2017-09-0 2017-09-2 2017-11-1 2017-10-1 2017-11-2 es matériaux de travail pour IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 61,000.00 50,255.93 Achevé Envelope 2 4 4 4 5 3 la phase 4 des THIMO dans l a région du nord , commune de Touboro CM-UGP-PFS-47595-GO-RFQ / Fourniture du matériel de l Single Stage - One 2018-06-1 2018-08-3 2018-07-3 2018-09-2 2018-08-2 2018-10-1 a phase 6 des THIMO du Proj IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 80,275.00 65,428.39 Achevé Envelope 8 1 0 7 9 8 et Filets Sociaux dans les co mmunes de Dembo et Bashé o, région du Nord CM-UGP-PFS-47606-GO-RFB / Fourniture et paramétrage Cash Transfer Program with d'un progiciel de gestion int Accompanying Measures to Single Stage - One 2018-06-2 2018-06-2 2018-07-2 2018-08-1 2018-09-1 2019-03-1 égré pour la planification, la IDA / 52240 A posteriori Appel d'offres Open - National 167,500.00 0.00 Annulé Boost Household Productivit Envelope 1 6 7 7 4 3 programmation, la budgétis y ation, le suivi évaluation et l a production des rapports et indicateurs CM-UGP-PFS-47608-GO-RFQ Cash Transfer Program with Single Stage - One 2018-03-2 2018-05-0 2018-05-2 / Fourniture des logiciels info IDA / 52240 Accompanying Measures to A posteriori Demande de prix Limited 48,400.00 0.00 Annulé Envelope 7 8 9 rmatiques au projet Filets S Boost Household Productivit ociaux y CM-UGP-PFS-16933-GO-RFQ Cash Transfer Program with / Fourniture des seaux, Tee s Accompanying Measures to Single Stage - One 2017-06-2 2017-08-1 2017-09-1 IDA / 52240 A posteriori Demande de prix Open - National 193,700.00 0.00 Annulé hirt, casquettes autocollants Boost Household Productivit Envelope 0 5 4 pour véhicules estampillés P y rojet Filets Sociaux CM-UGP-PFS-25989-GO-RFQ / Fourniture du matériel et d Single Stage - One 2018-04-0 2018-03-0 2018-05-0 2018-04-0 2018-06-0 2018-04-2 es matériaux de travail pour IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 80,275.00 72,952.92 Achevé Envelope 6 1 5 3 4 0 la phase 5 des THIMO dans 2 communes de la région du N ord ouest (Oku et Ako) CM-UGP-PFS-25987-GO-RFQ / Fourniture du matériel et d es matériaux de travail pour Single Stage - One 2018-04-0 2018-03-0 2018-05-0 2018-04-0 2018-06-0 2018-04-2 IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 80,275.00 65,815.47 Achevé la phase 5 des THIMO dans 2 Envelope 6 1 5 3 4 4 communes de la région de l' EST (Bétaré OYA et Batouri) CM-UGP-PFS-25491-GO-RFQ Laying the Foundations of a Single Stage - One 2018-04-1 2018-05-2 2019-05-2 / Fourniture du matériel de p IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 30,000.00 0.00 Annulé Envelope 9 4 4 ause café au Projet Filets So porting Project Managemen ciaux t CM-UGP-PFS-47578-GO-RFQ Cash Transfer Program with Single Stage - One 2018-06-0 2019-01-2 2018-07-1 2019-03-0 2018-08-0 2019-03-2 / Fourniture des pneus de re IDA / 52240 Accompanying Measures to A posteriori Demande de prix Limited 28,400.00 24,340.71 Achevé Envelope 4 4 6 4 6 8 charge pour des autos et mo Boost Household Productivit tos du Projet y CM-UGP-PFS-25476-GO-RFQ Cash Transfer Program with / Fourniture des tee-shirts et Accompanying Measures to Single Stage - One 2017-12-0 2018-01-2 2017-12-2 2018-03-0 2018-01-1 2018-03-2 IDA / 52240 A posteriori Demande de prix Limited 99,000.00 68,943.69 Achevé casquettes estampillés au Pr Boost Household Productivit Envelope 2 4 6 1 6 9 ojet Filets Sociaux y CM-UGP-PFS-25488-GO-RFQ Laying the Foundations of a Single Stage - One 2018-01-0 2018-03-2 2018-02-1 2018-05-2 2019-02-1 2018-12-2 / fourniture des encres pour IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 100,000.00 83,622.13 Achevé Envelope 3 9 0 2 0 0 imprimantes et photocopieu porting Project Managemen rs t CM-UGP-PFS-25487-GO-RFQ Laying the Foundations of a Single Stage - One 2017-09-1 2017-10-1 2018-10-1 / Fourniture des fournitures IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 60,000.00 0.00 Annulé Envelope 6 1 1 de bureau au Projet Filets so porting Project Managemen ciaux t CM-UGP-PFS-67485-GO-RFQ Laying the Foundations of a / Fourniture du matériel infor Safety Net System and Sup Single Stage - One 2018-07-1 2018-07-0 2018-08-1 2018-07-3 2018-09-0 2018-08-0 IDA / 52240 A posteriori Demande de prix Limited 8,250.00 6,993.13 Achevé matique et de bureautique d porting Project Managemen Envelope 5 5 9 0 2 6 e l'antenne régionale du proj t et du Nord Ouest CM-UGP-PFS-67490-GO-RFQ Laying the Foundations of a Single Stage - One 2018-07-1 2018-07-0 2018-08-1 2018-07-2 2019-08-1 2018-08-2 / Fourniture des polices d'as IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 8,250.00 3,525.35 Achevé Envelope 0 2 4 5 4 9 surance aux 40 premières m porting Project Managemen otos du projet t CM-UGP-PFS-47597-GO-RFQ / Fourniture des boîtes à pha Single Stage - One 2018-09-0 2018-08-2 2018-09-3 2018-09-1 2018-10-0 2018-09-1 IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 8,360.00 7,383.31 Achevé rmacie de la phase 6 des THI Envelope 9 9 0 4 7 9 MO du Projet Filets Sociaux CM-UGP-PFS-75801-GO-RFQ Cash Transfer Program with Single Stage - One 2018-09-1 2018-10-0 2018-10-1 2018-10-2 2018-10-1 2018-10-3 / Fourniture du matériel pour IDA / 52240 Accompanying Measures to A posteriori Demande de prix Limited 8,360.00 7,144.10 Achevé Envelope 5 1 0 4 7 1 les crèches temporaires au P Boost Household Productivit FS y CM-UGP-PFS-130190-GO-RF Q / Fourniture des licences p Laying the Foundations of a our la plateforme tomate ( Li Safety Net System and Sup Single Stage - One 2019-10-1 2019-09-3 2019-12-1 2019-11-1 2020-06-1 2020-03-0 IDA / 62230 A posteriori Demande de prix Limited 34,000.00 29,607.05 Achevé cence Multiprojet, Monosite porting Project Managemen Envelope 0 0 3 8 0 5 et Multiposte Tom2pro, Tom t 2monitoring, Tom2paie et T om2marché) CM-UGP-PFS-121205-GO-RF Laying the Foundations of a Single Stage - One 2019-10-0 2019-09-3 2019-11-2 2019-11-1 2020-03-2 2020-06-1 B / Fourniture des consomm IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 80,000.00 62,547.39 Achevé Envelope 5 0 3 8 2 2 ables informatiques au Proje porting Project Managemen t Filets Sociaux t CM-UGP-PFS-121383-GO-RF Laying the Foundations of a Q / Acquisition des fournitur Safety Net System and Sup Single Stage - One 2019-10-1 2019-09-3 2019-12-1 2019-11-1 2020-04-1 2020-06-1 IDA / 62230 A posteriori Demande de prix Limited 40,000.00 26,447.17 Achevé es de bureaux et des produit porting Project Managemen Envelope 4 0 6 8 4 2 s d'entretien de bureau en d t eux lots distincts CM-UGP-PFS-120445-GO-UN / FOURNITURE DE 756 TABL Laying the Foundations of a ETTES BIOMETRIQUES MOBI Passation de mar Safety Net System and Sup 2019-11-3 2019-07-3 2019-12-1 2019-06-0 2020-02-0 2019-11-1 2020-08-2 2021-10-1 LES et 756 BATTERIE EXTER IDA / 62230 A posteriori chés auprès des Direct 660,808.00 660,808.00 Achevé porting Project Managemen 0 1 4 7 2 3 0 9 NES TYPES POWERBANK ET agences de l'ONU t 756 SACS PHOTOVOLTAÏQUE S en deux tranches de 400 e t 356 chacune CM-UGP-PFS-171977-GO-RF B / Fourniture du matériel T Single Stage - One 2020-06-3 2020-06-1 2020-07-0 2020-08-1 2020-07-2 2020-09-1 2020-08-1 2020-10-2 2020-09-2 2020-11-1 2021-02-1 HIMO de la phase 7 des Tra IDA / D2980 Public Works Program Pilot A posteriori Appel d'offres Open - National 267,580.00 187,352.13 Achevé Envelope 0 7 5 6 8 5 4 0 1 0 6 vaux à Haute Intensité de M ain d'œuvre en 4 lots distinc ts CM-UGP-PFS-172000-GO-RF Q / Fourniture des boîtes à p Single Stage - One 2020-06-2 2020-08-1 2020-08-2 2020-09-2 2020-09-0 2020-12-1 IDA / D2980 Public Works Program Pilot A posteriori Demande de prix Limited 41,800.00 29,602.75 Achevé harmacie de la phase 7 des Envelope 0 4 6 9 9 7 THIMO en 3 lots distincts Page 1 CM-UGP-PFS-172036-GO-RF Laying the Foundations of a Single Stage - One 2020-06-2 2020-08-1 2020-08-1 2020-09-2 2020-09-0 2021-08-1 Q / Fourniture de 50 mini gro IDA / 62230 Safety Net System and Sup A posteriori Demande de prix Limited 37,500.00 23,591.16 Achevé Envelope 0 4 9 9 2 9 upes électrogènes au Projet porting Project Managemen Filets Sociaux t CM-UGP-PFS-172065-GO-RF Laying the Foundations of a B / Fourniture des consomm Safety Net System and Sup Single Stage - One 2020-12-1 2021-01-0 2020-12-2 2021-10-1 2021-02-0 2021-02-1 2021-03-0 2021-02-1 2021-04-1 2021-05-0 2022-04-1 IDA / 52240 A posteriori Appel d'offres Open - National 160,000.00 62,330.61 Signé ables informatiques à l'unité porting Project Managemen Envelope 5 8 5 5 5 0 7 6 1 4 1 de Gestion du Projet Filets S t ociaux CM-UGP-PFS-172042-GO-RF Laying the Foundations of a Single Stage - One 2021-01-0 2021-03-1 2021-07-0 2021-04-0 B / Fourniture de 4 véhicules IDA / 62230 Safety Net System and Sup A posteriori Demande de prix Open - National 200,000.00 155,468.00 Signé Envelope 6 0 5 9 pick up double cabine au Pro porting Project Managemen jet Filets Sociaux t CM-UGP-PFS-172008-GO-RF Q / Fourniture et équipemen Single Stage - One 2020-05-2 2020-07-2 2020-08-0 IDA / D2980 Public Works Program Pilot A posteriori Demande de prix Limited 50,000.00 0.00 Annulé t du matériel de crèche de la Envelope 0 6 9 Phase 7 des THIMO en 3 lots CM-UGP-PFS-213727-GO-RF Q / Fourniture des boîtes à p harmacie des phases 8 et 9 Single Stage - One 2021-05-0 2021-04-0 2021-06-3 2021-05-2 2021-07-3 2021-08-1 IDA / 62230 Public Works Program Pilot A posteriori Demande de prix Limited 50,160.00 39,218.32 Achevé des Travaux à Haute intensit Envelope 5 8 0 8 0 9 é de main d'œuvre du Projet Filets Sociaux en deux 2 lots distincts CM-UGP-PFS-205171-GO-RF Cash Transfer Program with Q / Recrutement du prestata Accompanying Measures to Single Stage - One 2021-05-0 2021-09-2 2021-06-3 2021-11-1 2021-07-1 2022-01-2 IDA / D2980 A posteriori Demande de prix Limited 15,251.00 11,916.61 Achevé ire pour la fourniture des lec Boost Household Productivit Envelope 5 7 0 8 4 0 teurs MP3 et des baffles y CM-UGP-PFS-217839-GO-RF Laying the Foundations of a Single Stage - One 2021-02-2 2021-02-1 2021-04-1 2021-03-0 2021-04-2 2021-06-0 Q / Fourniture de deux photo IDA / 62230 Safety Net System and Sup A posteriori Demande de prix Limited 8,380.00 7,603.68 Achevé Envelope 7 2 0 5 4 8 copieurs en Urgence au Proj porting Project Managemen et Filets Sociaux t CM-UGP-PFS-211488-GO-RF B / Fourniture du Matériel de Single Stage - One 2021-02-1 2021-02-1 2021-02-1 2021-03-2 2021-03-2 2021-04-2 2021-04-0 2021-06-0 2021-05-0 2021-07-0 2021-11-2 s phases 8 et 9 des Travaux IDA / 62230 Public Works Program Pilot A posteriori Appel d'offres Open - National 321,096.00 194,297.34 Achevé Envelope 0 6 5 9 3 8 1 2 4 2 9 à Haute Intensité de Main d' Œuvre (THIMO) en 4 lots dist incts CM-UGP-PFS-222852-GO-RF Laying the Foundations of a B / Acquisition des fourniture Safety Net System and Sup Single Stage - One 2021-04-1 2021-06-1 2021-04-2 2021-06-0 2021-07-0 2021-06-1 2021-07-2 2021-07-2 2021-08-1 2022-07-2 IDA / 62230 A posteriori Appel d'offres Open - National 269,944.00 94,736.43 Signé s de bureaux et des produits porting Project Managemen Envelope 5 1 0 4 9 9 9 4 9 4 d'entretien de bureau en de t ux lots distincts CM-UGP-PFS-233101-GO-RF B / Fourniture du matériel d Single Stage - One En attente d 2021-06-3 2021-07-0 2021-08-1 2021-09-1 2021-10-2 2021-11-2 e la phase 10 des Travaux à IDA / 62230 Public Works Program Pilot A posteriori Appel d'offres Open - National 227,443.00 0.00 Envelope 'exécution 0 7 8 7 2 1 Haute Intensité de Main d'œ uvre du Projet Filets Sociaux en 2 lots distincts CM-UGP-PFS-241556-GO-RF Cash Transfer Program with Q / Fourniture du matériel d Accompanying Measures to Single Stage - One En attente d 2021-08-0 2021-09-0 2021-09-1 es crèches temporaires des IDA / 62230 A posteriori Demande de prix Limited 8,384.00 0.00 Boost Household Productivit Envelope 'exécution 4 4 8 phases 8 et 9 des Travaux à y Haute Intensité de Main d'œ uvre (THIMO) CM-UGP-PFS-233093-GO-RF Q / Fourniture des boîtes à p harmacie de phase 10 des T Single Stage - One En attente d 2021-08-3 2021-10-2 2021-11-2 ravaux à Haute intensité de IDA / 62230 Public Works Program Pilot A posteriori Demande de prix Limited 35,530.00 0.00 Envelope 'exécution 0 5 4 main d'œuvre du Projet Filet s Sociaux dans les régions d e l’Extrême Nord, du Nord et de l’Adamaoua CM-UGP-PFS-241685-GO-RF B / Fourniture du matériel de travail de la phase 10 des Tr Single Stage - One En attente d 2021-08-3 2021-09-0 2021-10-1 2021-11-1 2021-12-2 2022-02-0 avaux à Haute intensité de IDA / 62230 Public Works Program Pilot A posteriori Appel d'offres Open - National 227,443.00 0.00 Envelope 'exécution 0 4 6 5 0 3 main d'œuvre (THIMO) dans les régions de l'Adamaoua, d u Nord et de l'Extrême Nord en 3 lots distincts CM-UGP-PFS-239622-GO-RF Laying the Foundations of a Q / Fourniture d'un scanner Safety Net System and Sup Single Stage - One 2021-08-1 2021-09-2 2021-09-2 2021-11-1 2021-10-1 2022-01-2 et d'un copieur en procédure IDA / 62230 A posteriori Demande de prix Limited 19,500.00 16,033.71 Achevé porting Project Managemen Envelope 7 7 8 8 2 0 d'urgence pour la passation t des marchés du Projet Filets Sociaux CM-UGP-PFS-170601-GO-RF Laying the Foundations of a B / Fourniture du matériel inf Safety Net System and Sup Single Stage - One En cours d'e 2021-10-0 2021-11-3 2021-10-1 2021-11-2 2022-01-2 2021-12-2 2022-02-0 2022-03-2 ormatique, du matériel de té IDA / 62230 A posteriori Appel d'offres Open - National 480,040.00 0.00 porting Project Managemen Envelope xécution 1 0 5 9 1 9 8 5 léphonie et des logiciels info t rmatiques au Projet Filets S ociaux en 3 lots distincts CM-UGP-PFS-281266-GO-RF Laying the Foundations of a Single Stage - One En attente d 2022-03-3 2022-04-0 2022-05-1 2022-05-2 2022-06-1 2022-12-1 B / Fourniture des consomm IDA / 52240 Safety Net System and Sup A posteriori Appel d'offres Open - National 193,750.00 0.00 Envelope 'exécution 0 9 4 9 7 4 ables informatiques au Proje porting Project Managemen t Filets Sociaux t CM-UGP-PFS-281268-GO-RF Laying the Foundations of a B / Acquisition des fourniture Safety Net System and Sup Single Stage - One En attente d 2022-04-1 2022-06-0 2022-12-0 IDA / 62230 A posteriori Demande de prix Limited 74,580.00 0.00 s de bureau et des produits porting Project Managemen Envelope 'exécution 3 8 5 d'entretien pour le Projet Fil t ets Sociaux CM-UGP-PFS-281269-GO-RF Laying the Foundations of a Q / Fourniture des sacs pour Safety Net System and Sup Single Stage - One 2022-04-0 2022-05-1 2022-06-0 IDA / D2980 A posteriori Demande de prix Limited 44,400.00 0.00 Annulé les équipes de terrain dans l porting Project Managemen Envelope 5 7 7 e cadre de l'accompagneme t nt des bénéficiaires CM-UGP-PFS-172043-GO-RF B / Fourniture du matériel pr Cash Transfer Program with oductif pour les sanctions po Accompanying Measures to Single Stage - One En cours d'e 2022-04-0 2022-07-0 2022-04-1 2022-07-1 2022-05-2 2022-06-2 2022-07-2 2022-08-2 IDA / 62230 A posteriori Appel d'offres Open - National 235,840.00 0.00 sitives des cycles 3, 4, 5, G1 Boost Household Productivit Envelope xécution 1 8 1 5 3 2 7 6 , G2, G3 des Transferts Mon y étaires Ordinaires du Projet Filets Sociaux en 6 lots disti ncts CM-UGP-PFS-25491-GO-RFQ Laying the Foundations of a Single Stage - One En attente d 2022-04-1 2022-05-2 2022-11-1 -2 / Fourniture du nécessaire IDA / 62230 Safety Net System and Sup A posteriori Demande de prix Limited 15,000.00 0.00 Envelope 'exécution 5 0 6 de pause café au projet Filet porting Project Managemen s Sociaux t CM-UGP-PFS-232884-GO-RF Laying the Foundations of a Q / Fourniture du 2150 kits d Safety Net System and Sup Single Stage - One 2021-08-1 2021-10-1 2021-11-0 e formation et de travail, po IDA / D2980 A posteriori Demande de prix Limited 43,000.00 0.00 Annulé porting Project Managemen Envelope 3 5 5 ur les équipes de terrain dan t s le cadre de l'accompagne ment des bénéficiaires CM-UGP-PFS-172069-GO-RF Laying the Foundations of a Q / Fourniture du mobilier de Safety Net System and Sup Single Stage - One 2021-01-2 2021-03-0 2021-03-1 IDA / 62230 A posteriori Demande de prix Limited 14,820.00 0.00 Annulé bureau et d’un coffre-fort po porting Project Managemen Envelope 0 1 5 ur l’Unité de Gestion du Proj t et Filets Sociaux CM-UGP-PFS-172070-GO-RF Laying the Foundations of a Q / Fourniture des Pneus et Safety Net System and Sup Single Stage - One 2021-11-0 2021-12-2 2022-01-0 IDA / 62230 A posteriori Demande de prix Limited 28,386.00 0.00 Annulé pièces de rechange des véhi porting Project Managemen Envelope 4 3 6 cules du Projet Filets Sociau t x CM-UGP-PFS-233020-GO-RF Laying the Foundations of a Q / Fourniture et installation Safety Net System and Sup Single Stage - One 2021-06-2 2021-08-2 2021-09-2 IDA / 62230 A posteriori Demande de prix Limited 27,600.00 0.00 Annulé du dispositif de vidéoconfére porting Project Managemen Envelope 5 1 0 nce avec abonnement Zoom t et webex CM-UGP-PFS-307727-GO-RF Laying the Foundations of a Q / Fourniture et installation Safety Net System and Sup Single Stage - One En attente d 2022-09-0 2022-10-1 2022-11-0 IDA / 62230 A posteriori Demande de prix Limited 24,000.00 0.00 du matériel de vidéo confére porting Project Managemen Envelope 'exécution 5 7 7 nce au Projet Filets Sociaux t NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Repor Loan / Credit Market Approa Procurement Pr Prequalificatio Estimated A Actual Amoun Process S Draft Pre-qualificatio Prequalification Eval Draft Bidding Docu Specific Procuremen Bidding Documents Proposal Submission Description Component Review Type Method t and Recommendati Signed Contract Contract Completion No. ch ocess n (Y/N) mount (US$) t (US$) tatus n Documents uation Report ment / Justification t Notice / Invitation as Issued / Opening / Minutes on for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6232-NC-RFQ / Recrutement des agences d Single Stage - One 2017-02-1 2017-02-1 2017-04-1 2017-04-2 2017-12-0 IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 60,000.00 61,263.97 Signé e paiement pour les phases Envelope 5 0 2 4 8 3 et 4 des THIMO en lots CM-UGP-PFS-6233-NC-RFQ / Recrutement des agences d e paiement pour le paiement Cash Transfer Program with de 19500 ménages bénéficia Accompanying Measures to Single Stage - One 2017-03-0 2017-05-0 2019-04-2 ires du cycle 2 des transferts IDA / 52240 A priori Demande de prix Limited 351,000.00 0.00 Annulé Boost Household Productivit Envelope 7 5 5 monétaires dont 7500 dans l y a région de l'Extrême Nord, 5500 dans les régions du No rd et de l'Adamaoua, et 650 0 dans les régions de l'Est, d u Nord CM-UGP-PFS-6315-NC-RFQ / Cash Transfer Program with Single Stage - One 2017-02-2 2017-04-2 2017-04-2 2017-05-2 2017-05-0 2017-06-1 Impression des documents d IDA / 52240 Accompanying Measures to A posteriori Demande de prix Limited 70,000.00 22,001.63 Achevé Envelope 5 1 2 6 6 9 u Projet Boost Household Productivit y CM-UGP-PFS-6306-NC-RFQ / Laying the Foundations of a Single Stage - One 2017-03-0 2017-03-0 2017-04-2 2017-06-0 2018-04-2 2018-06-0 fourniture des polices d'assu IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 123,900.00 58,410.90 Achevé Envelope 3 6 8 7 3 8 rance maladie porting Project Managemen t CM-UGP-PFS-7385-NC-RFQ / Laying the Foundations of a Single Stage - One 2017-03-0 2017-03-0 2017-04-2 2017-06-1 2018-04-2 2018-06-1 Fourniture des polices d'ass IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 31,100.00 18,329.45 Achevé Envelope 3 6 8 5 3 4 urance automobile porting Project Managemen t CM-UGP-PFS-14464-NC-RFQ Laying the Foundations of a Single Stage - One 2017-06-1 2018-07-1 2017-06-1 2018-07-2 2018-06-1 / Renouvellement du contrat IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 8,250.00 3,553.09 Signé Envelope 3 7 9 5 4 d'assurance des 40 motos e porting Project Managemen n circulation t CM-UGP-PFS-25608-NC-RFQ Laying the Foundations of a Single Stage - One 2017-10-0 2017-10-3 2018-10-3 / Maintenance Autos UGP po IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 8,300.00 0.00 Annulé Envelope 4 1 1 ur 1 an porting Project Managemen t CM-UGP-PFS-25616-NC-RFQ Laying the Foundations of a Single Stage - One 2017-10-0 2017-11-0 2018-11-0 / Maintenance matériel bure IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 8,300.00 0.00 Annulé Envelope 7 7 7 autique et informatique UGP porting Project Managemen pour 1 an t CM-UGP-PFS-25623-NC-RFQ Laying the Foundations of a Single Stage - One 2017-10-1 2017-11-0 2018-11-0 / Maintenance froid et climat IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 8,300.00 0.00 Annulé Envelope 1 9 9 isation UGP pour 1 an porting Project Managemen t CM-UGP-PFS-25711-NC-RFQ Laying the Foundations of a / Fourniture du service de ga Safety Net System and Sup Single Stage - One 2017-12-0 2018-04-2 2018-01-0 2018-07-1 2019-01-0 IDA / 52240 A posteriori Demande de prix Limited 6,000.00 8,986.03 Signé rdiennage pour l'antenne ré porting Project Managemen Envelope 9 0 9 0 9 gionale du Nord Ouest t CM-UGP-PFS-25729-NC-RFQ Laying the Foundations of a / Fourniture des systèmes de Safety Net System and Sup Single Stage - One 2017-10-1 2018-02-2 2017-11-1 2018-03-1 2017-12-1 2018-07-0 IDA / 52240 A posteriori Demande de prix Limited 4,000.00 1,315.18 Achevé sécurité et de GPS et du ser porting Project Managemen Envelope 5 0 5 2 5 2 vice de tracking pour les aut t os CM-UGP-PFS-25892-NC-RFQ Laying the Foundations of a / Confection et la pose des p Safety Net System and Sup Single Stage - One 2017-09-3 2017-11-1 2018-02-0 2017-12-0 2018-04-0 IDA / 52240 A posteriori Demande de prix Open - National 4,000.00 7,636.09 Achevé laques signalétiques (7 plaq porting Project Managemen Envelope 0 0 8 1 9 ues directionnelles + 3 pann t eaux) CM-UGP-PFS-25980-NC-RFQ Laying the Foundations of a / Avenant au contrat de l'ag Safety Net System and Sup Single Stage - One 2017-09-1 2016-09-2 2017-09-2 2016-10-3 2018-09-2 IDA / 52240 A posteriori Demande de prix Limited 6,000.00 14,850.36 Signé ence de gardiennage de l'an porting Project Managemen Envelope 1 6 3 1 3 tenne régionale du Nord t CM-UGP-PFS-25981-NC-RFQ Laying the Foundations of a / Avenant au contrat de l'ag Safety Net System and Sup Single Stage - One 2017-09-1 2016-06-2 2017-09-2 2016-07-2 2018-09-2 IDA / 52240 A posteriori Demande de prix Limited 5,000.00 16,374.35 Signé ence de gardiennage de l'an porting Project Managemen Envelope 1 4 3 8 3 tenne régionale de l'Extrême t Nord Page 2 CM-UGP-PFS-25983-NC-RFQ Laying the Foundations of a / Avenant au contrat d'assur Safety Net System and Sup Single Stage - One 2017-09-1 2017-10-1 2017-10-1 2017-12-2 2018-08-1 2018-06-0 ance du personnel en vu de l IDA / 52240 A posteriori Demande de prix Limited 39,000.00 24,386.04 Achevé porting Project Managemen Envelope 5 9 6 0 2 8 a prise en compte du person t nel nouvellement recruté CM-UGP-PFS-30748-NC-DIR / recrutement d'une agence Cash Transfer Program with de paiement chargée d'assu Accompanying Measures to Passation de mar 2017-10-0 2018-01-0 2017-10-0 2017-11-2 2017-11-1 2018-02-1 2018-11-1 2019-07-2 IDA / 52240 A posteriori Direct 36,000.00 30,643.76 Achevé rer les transferts monétaires Boost Household Productivit ché de gré à gré 4 4 9 7 6 3 6 4 des bénéficiaires de la phas y e 2 des transferts monétaire s d'urgence du Projet Filets Sociaux CM-UGP-PFS-37510-NC-RFQ / avenant Lettre de Marché N°009/LM/MINEPAT/CTS/PFS/ UGP/CAPM/2017 du 26 mai 2 Passation de mar 2017-12-1 2018-01-0 2017-12-2 2018-01-0 2018-01-1 2018-02-1 2018-05-1 IDA / 52240 Public Works Program Pilot A posteriori Direct 6,000.00 22,354.79 Signé 017 de l'agence de paiemen ché de gré à gré 8 4 5 8 5 3 5 t pour la réalisation des paie ments des 6000 bénéficiair es des THIMO 5 dont 3000 d ans le Nord-Ouest et 3000 d ans l'Est CM-UGP-PFS-37511-NC-RFQ Laying the Foundations of a / Avenant au contrat d'assur Safety Net System and Sup Passation de mar 2017-12-1 2017-12-2 2017-12-2 2017-12-2 2018-01-0 2018-02-1 2018-07-0 ance véhicule LETTRE DE MA IDA / 52240 A posteriori Direct 4,000.00 1,207.48 Signé porting Project Managemen ché de gré à gré 8 2 3 2 9 3 8 RCHE N°011/LM/MINEPAT/CT t S/PFS/UGP/CAPM/2017 DU 0 8 JUIN 2017 CM-UGP-PFS-25853-NC-DIR / Avenant au contrat de l'ag ence de paiement chargée d es transferts monetaires du Single Stage - One 2017-09-2 2018-01-0 2017-11-2 2018-02-1 2018-05-1 IDA / 52240 Public Works Program Pilot A posteriori Demande de prix Limited 23,400.00 22,232.85 Signé cycle 2 à l'Est, le Nord ouest, Envelope 5 8 0 3 9 Douala et Yaoundé pour la p hase 5 des THIMO dont 300 0 dans la région de l'Est et 3 000 dans la région du Nord Ouest CM-UGP-PFS-47580-NC-RFQ Cash Transfer Program with Single Stage - One 2018-03-3 2018-06-1 2018-05-2 2018-08-2 2019-05-2 / Fourniture de polices d'ass IDA / 52240 Accompanying Measures to A posteriori Demande de prix Limited 28,000.00 14,785.79 Signé Envelope 1 1 6 2 6 urance autos au projet Filets Boost Household Productivit Sociaux y CM-UGP-PFS-47582-NC-RFQ Cash Transfer Program with / Confection et pause des pl Accompanying Measures to Single Stage - One 2018-04-3 2018-08-2 2018-06-1 2018-09-1 2018-07-1 2018-11-2 IDA / 52240 A posteriori Demande de prix Limited 8,250.00 7,009.83 Achevé aques signalétiques des réal Boost Household Productivit Envelope 0 3 1 2 1 3 isations du Projet Filets Soci y aux dans les communes CM-UGP-PFS-47593-NC-RFQ / Agence de paiement charg Cash Transfer Program with ée d'assurer le paiement des Accompanying Measures to Single Stage - One 2018-05-2 2018-07-1 2019-07-1 IDA / 52240 A posteriori Demande de prix Limited 19,170.00 0.00 Annulé 3000 bénéficiaires de la pha Boost Household Productivit Envelope 3 8 8 se 3 des transferts monétair y es d'urgence du du Projet Fi lets Sociaux dans le Nord Ou est CM-UGP-PFS-47602-NC-DIR / Avenant au contrat de l'ag ence de paiement chargée d 'assurer les paiement des tr Passation de mar 2018-06-2 2018-06-2 2018-07-2 2018-07-3 2018-09-1 2019-01-2 2019-02-2 ansfert monétaires du cycle IDA / 52240 Public Works Program Pilot A posteriori Direct 11,700.00 10,227.50 Achevé ché de gré à gré 1 6 0 1 2 7 6 2 dans le Nord et l'Adamaou a pour les paiements de 300 0 bénéficiaire de la phase 6 des THIMO dans la région du Nord, communes de Dembo et Bashéo CM-UGP-PFS-25707-NC-RFQ Laying the Foundations of a Single Stage - One 2017-10-0 2017-11-0 2018-11-0 / Maintenance froid et climat IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 5,000.00 0.00 Annulé Envelope 9 7 7 isation EN et NO pour 1 an porting Project Managemen t CM-UGP-PFS-25610-NC-RFQ Laying the Foundations of a Single Stage - One 2017-10-0 2017-10-3 2018-10-3 / Maintenance des Autos et IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 5,000.00 0.00 Annulé Envelope 4 1 1 Motos de l'Extrême-Nord porting Project Managemen t CM-UGP-PFS-25612-NC-RFQ Laying the Foundations of a Single Stage - One 2017-09-0 2017-09-3 2018-09-3 / Maintenance des Autos et IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 5,000.00 0.00 Annulé Envelope 3 0 0 Motos du Projet du Nord porting Project Managemen t CM-UGP-PFS-25618-NC-RFQ Laying the Foundations of a Single Stage - One 2017-10-0 2017-11-0 2018-11-0 / Maintenance matériel bure IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 5,000.00 0.00 Annulé Envelope 7 3 3 autique et informatique EN e porting Project Managemen t NO pour 1 an t CM-UGP-PFS-47255-NC-RFQ Cash Transfer Program with / Production et multiplication Accompanying Measures to Single Stage - One 2018-03-1 2018-02-2 2018-04-1 2018-03-0 2018-04-2 2018-03-1 IDA / 52240 A posteriori Demande de prix Limited 7,567.00 7,132.71 Achevé des documents des Pratique Boost Household Productivit Envelope 6 3 0 8 4 2 s familiales essentielles y CM-UGP-PFS-26101-NC-RFQ Laying the Foundations of a Single Stage - One 2017-10-1 2017-11-1 2018-11-1 / Maintenance des Autos et IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 5,000.00 0.00 Annulé Envelope 1 3 3 Motos du Nord-Ouest porting Project Managemen t CM-UGP-PFS-6311-NC-RFQ / Laying the Foundations of a Single Stage - One 2018-04-0 2018-03-0 2018-05-1 2018-03-2 2019-05-0 2018-08-2 Fourniture de police d'assur IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 8,250.00 3,228.19 Achevé Envelope 6 2 1 6 6 8 ance pour 20 motos porting Project Managemen t CM-UGP-PFS-26060-NC-RFQ Laying the Foundations of a Single Stage - One 2018-05-0 2018-03-0 2018-06-0 2018-03-2 2018-06-2 2018-03-2 / Fourniture des Systèmes d IDA / 52240 Safety Net System and Sup A posteriori Demande de prix Limited 8,500.00 1,867.92 Achevé Envelope 1 5 1 6 2 9 e sécurité pour les motos du porting Project Managemen projet (20) t CM-UGP-PFS-37512-NC-RFQ / Avenant N°2 au contrat d'a Cash Transfer Program with ssurance du personnel pour l Accompanying Measures to Passation de mar 2018-03-3 2018-03-1 2018-04-0 2018-03-2 2018-05-0 2018-04-2 2018-10-3 a prise en compte des relais IDA / 52240 A posteriori Direct 30,000.00 34,099.31 Signé Boost Household Productivit ché de gré à gré 0 9 6 2 4 4 1 communautaires recrutés da y ns le cadre de la sensibilisati on sur les pratiques familial es essentielles CM-UGP-PFS-47572-NC-RFB Cash Transfer Program with Single Stage - One 2018-05-0 2018-06-1 2018-07-0 2018-10-0 2019-07-0 / Fourniture des polices d'as IDA / 52240 Accompanying Measures to A posteriori Demande de prix Limited 130,000.00 127,074.00 Signé Envelope 7 1 2 5 2 surance au personnel du Pro Boost Household Productivit jet Filets Sociaux y CM-UGP-PFS-72576-NC-RFQ / Multiplication de certains d ocuments pour la collecte de Laying the Foundations of a s données sur les PFE de la p Safety Net System and Sup Single Stage - One 2018-09-1 2018-09-0 2018-10-2 2018-09-2 2018-11-1 2018-10-0 hase pilote pour une période IDA / 52240 A posteriori Demande de prix Limited 8,250.00 7,116.25 Achevé porting Project Managemen Envelope 6 5 8 7 1 1 de 6 mois et des questionnai t res et autres documents pou r la collecte des données da ns le cadre de la première é valuation interne du Projet CM-UGP-PFS-92192-NC-RFQ Cash Transfer Program with / Multiplication de certains d Accompanying Measures to Single Stage - One 2019-01-1 2019-01-1 2019-02-2 2019-02-0 2020-02-2 IDA / 52240 A posteriori Demande de prix Limited 6,500.00 5,551.26 Signé ocuments de collecte de don Boost Household Productivit Envelope 5 7 6 4 6 nées des PFE pour une pério y de d'un an MOF-CM-UGP-PFS-6233-NC- Cash Transfer Program with RFQ / Recrutement des agen Accompanying Measures to Single Stage - One 2017-02-2 2017-03-0 2017-05-0 2017-05-2 2019-10-2 ces de paiement pour le pai IDA / 52240 A posteriori Demande de prix Limited 351,000.00 142,058.17 Signé Boost Household Productivit Envelope 7 8 1 6 8 ement de 19500 menages b y eneficiaires du cycle 2 des tr ansferts monetaires en 3 lot s CM-UGP-PFS-121194-NC-RF Laying the Foundations of a Q / Fourniture des polices d' Safety Net System and Sup Single Stage - One 2019-09-1 2019-09-0 2019-11-0 2020-11-0 IDA / 62230 A posteriori Demande de prix Limited 28,000.00 0.00 Annulé assurance pour les autos du porting Project Managemen Envelope 0 6 5 4 Projet Filets Sociaux t CM-UGP-PFS-121367-NC-RF B / FOURNITURE D’UNE POLI Laying the Foundations of a CE D'ASSURANCE MALADIE P Safety Net System and Sup Single Stage - One 2019-08-3 2019-10-0 2019-09-1 2019-10-2 2019-11-1 2019-11-2 2019-12-2 2019-12-2 2020-12-2 IDA / 62230 A posteriori Appel d'offres Open - National 164,000.00 0.00 Annulé OUR UN AN EN FAVEUR DU P porting Project Managemen Envelope 0 9 4 6 3 5 7 3 2 ERSONNEL DU PROJET FILET t S SOCIAUX ET LEURS FAMILL ES (2019-2020) CM-UGP-PFS-152342-NC-RF Laying the Foundations of a Q / FOURNITURE DES POLICE Safety Net System and Sup Single Stage - One 2020-02-1 2020-04-1 2020-07-2 2021-04-1 IDA / 62230 A posteriori Demande de prix Open - National 28,000.00 9,512.73 Signé S D'ASSURANCE POUR SIX (0 porting Project Managemen Envelope 0 4 0 4 6) VEHICULES DU PROJET FIL t ETS SOCIAUX CM-UGP-PFS-143130-NC-RF Q / Recrutement d'une agen ce de paiement pour le trans Single Stage - One En cours d'e 2020-07-1 2020-09-2 2021-03-1 fert des paiements aux 3000 IDA / D2980 Public Works Program Pilot A posteriori Demande de prix Limited 13,500.00 0.00 Envelope xécution 0 0 9 bénéficiaires de la phase 7 des Travaux à Haute Intensit é de Main d'œuvre dans la c ommune de Mokolo CM-UGP-PFS-172111-NC-RF Laying the Foundations of a B / Fourniture d'une police d' Safety Net System and Sup Single Stage - One 2020-06-0 2020-06-2 2020-06-1 2020-07-2 2020-07-3 2020-08-2 2020-09-0 2020-10-0 2020-10-1 2021-10-0 assurance maladie pour un a IDA / 62230 A posteriori Appel d'offres Open - National 164,000.00 412,976.85 Signé porting Project Managemen Envelope 1 5 6 8 0 7 1 1 6 1 n en faveur du personnel du t Projet Filets Sociaux et leur f amille CM-UGP-PFS-175637-NC-DI R / Agence de paiement des 6000 bénéficiaires du Cycle Cash Transfer Program with 3 des transferts Monétaires Accompanying Measures to Passation de mar 2020-06-3 2018-05-0 2020-07-0 2020-08-1 2020-08-2 2020-09-1 2022-09-0 Ordinaires, des 2000 de la IDA / D2980 A posteriori Direct 165,240.00 86,914.08 Signé Boost Household Productivit ché de gré à gré 0 1 5 4 3 1 2 phase 3 des Transferts Moné y taires d’Urgence et des 300 0 de la phase 7 des THIMO dans les Régions de l’Adama oua et de l’Est en 3 lots dis tinct CM-UGP-PFS-175721-NC-DI R / Agence de paiement des bénéficiaires du Cycle 3 des Cash Transfer Program with transferts Monétaires Ordina Accompanying Measures to Passation de mar 2020-06-3 2018-05-0 2020-07-0 2020-08-1 2020-08-2 2020-09-1 2022-09-0 IDA / 62230 A posteriori Direct 237,960.00 115,704.37 Signé ires, de la phase 3 des Tran Boost Household Productivit ché de gré à gré 0 1 5 4 3 1 2 sferts Monétaires d’Urgence, y de la phase 7 des Travaux à Haute Intensité de Main d' œuvre, Régions de l’Extrêm e Nord et du Nord CM-UGP-PFS-175722-NC-DI R / Agence de Paiement des bénéficiaires du cycle 3 des Cash Transfer Program with Transferts Monétaires Ordin Accompanying Measures to Passation de mar 2020-06-3 2018-05-0 2020-07-0 2020-08-1 2020-08-2 2020-09-1 2022-09-0 aires dans la Région du Sud, IDA / 62230 A posteriori Direct 129,600.00 62,469.50 Signé Boost Household Productivit ché de gré à gré 0 1 5 4 3 1 2 Communes d'Ebolawa 2 (10 y 00), Meyomessala (1000) Ma ’an (1000) et dans les ville d e Douala et yaoundé comm unes de Douala 5 (1500),Yao undé 3 (1500), CM-UGP-PFS-175723-NC-DI R / Agence de Paiement des Cash Transfer Program with bénéficiaires de la phase 3 d Accompanying Measures to Passation de mar 2020-06-3 2020-07-0 2020-08-2 2022-09-0 es Transferts Monétaires d’U IDA / 62230 A posteriori Direct 16,200.00 0.00 Annulé Boost Household Productivit ché de gré à gré 0 5 3 2 rgence dans la Région du Su y d-Ouest, Communes de Lim be1 (500), Limbe 2 (500) Li mbe 3 (500) CM-UGP-PFS-175725-NC-DI R / Agence de Paiement des Cash Transfer Program with bénéficiaires de la phase 3 d Accompanying Measures to Passation de mar 2020-06-3 2020-07-0 2020-08-2 2022-09-0 es Transferts Monétaires d’U IDA / 62230 A posteriori Direct 21,600.00 0.00 Annulé Boost Household Productivit ché de gré à gré 0 5 3 2 rgence dans la Région du No y rd-Ouest, Communes de Ba menda 1 (500), Bamenda 2 ( 500) Bamenda 3 (1000) CM-UGP-PFS-172073-NC-RF Laying the Foundations of a Single Stage - One En cours d'e 2020-07-3 2020-07-2 2020-08-0 2020-09-1 2020-08-2 2020-10-1 2020-11-1 2021-11-1 B / Impression et reprograph IDA / 62230 Safety Net System and Sup A posteriori Appel d'offres Open - National 260,942.64 0.00 Envelope xécution 0 0 4 5 5 5 9 9 ie des documents pour le Pr porting Project Managemen ojet Filets Sociaux t CM-UGP-PFS-206581-NC-RF Laying the Foundations of a Single Stage - One 2021-03-0 2021-04-2 2022-04-2 Q / Entretien des motos du p IDA / 62230 Safety Net System and Sup A posteriori Demande de prix Limited 40,000.00 0.00 Annulé Envelope 3 8 8 rojet Filets Sociaux porting Project Managemen t CM-UGP-PFS-206582-NC-RF Laying the Foundations of a 2021-03-0 2021-06-1 2021-04-2 2021-07-0 2022-04-2 Q / Entretien des véhicules d IDA / 62230 Safety Net System and Sup A posteriori Demande de prix 22,000.00 7,099.06 Signé 3 1 8 2 8 u Projet Filets Sociaux porting Project Managemen t Page 3 CM-UGP-PFS-172015-NC-RF Q / Recrutement des agenc Single Stage - One 2020-07-0 2020-09-0 2021-09-0 IDA / D2980 Public Works Program Pilot A posteriori Demande de prix Limited 45,000.00 0.00 Annulé es de paiement pour la phas Envelope 5 9 9 e 7 des THIMO en 3 lots disti ncts CM-UGP-PFS-143140-NC-RF Q / Recrutement d'une agen ce de paiement pour le paie ment des bénéficiaires de la Single Stage - One 2020-07-1 2020-09-2 2021-03-2 phase 7 des Travaux à Haut IDA / D2980 Public Works Program Pilot A posteriori Demande de prix Limited 22,500.00 0.00 Annulé Envelope 0 6 5 e Intensité de Main d'œuvre du PFS dont 1000 dans la c ommune de Dir région de l'A damaoua et 4000 dans la commune deTouboro, région du Nord CM-UGP-PFS-143142-NC-RF Q / Recrutement d'une agen ce de paiement pour le paie ment des bénéficiaires de l Single Stage - One 2020-07-1 2020-09-2 2021-03-1 a phase 7 des Travaux à Ha IDA / D2980 Public Works Program Pilot A posteriori Demande de prix Limited 9,000.00 0.00 Annulé Envelope 0 0 9 ute Intensité de Main d'œuvr e du PFS dans la région de l' Est dont 1000 dans la comm une de Ngoura, et 1000 dan s la commune de Mandjou CM-UGP-PFS-220415-NC-RF Laying the Foundations of a Q / Fourniture de service de Safety Net System and Sup Single Stage - One 2021-04-0 2021-04-0 2021-05-0 2021-05-2 2022-05-0 IDA / 62230 A posteriori Demande de prix Limited 8,640.00 5,620.72 Signé gardiennage au bureau de l' porting Project Managemen Envelope 4 8 5 5 5 Unité de Gestion du Projet Fi t lets Sociaux CM-UGP-PFS-232595-NC-RF Laying the Foundations of a Q / Fourniture de service de Safety Net System and Sup Single Stage - One En attente d 2021-06-3 2021-07-3 2022-07-3 IDA / 62230 A posteriori Demande de prix Limited 5,760.00 0.00 gardiennage au bureau de l' porting Project Managemen Envelope 'exécution 0 1 1 Antenne régionale du projet t du Sud CM-UGP-PFS-232598-NC-RF Laying the Foundations of a Q / Fourniture de service de Safety Net System and Sup Single Stage - One En attente d 2021-07-1 2021-08-1 2022-08-1 IDA / D2980 A posteriori Demande de prix Limited 5,760.00 0.00 gardiennage au bureau de l' porting Project Managemen Envelope 'exécution 0 0 0 Antenne régionale du projet t de l'Est CM-UGP-PFS-232599-NC-RF Laying the Foundations of a Q / Fourniture de service de Safety Net System and Sup Single Stage - One En attente d 2021-07-1 2021-08-1 2022-08-1 IDA / D2980 A posteriori Demande de prix Limited 5,760.00 0.00 gardiennage au bureau de l' porting Project Managemen Envelope 'exécution 0 0 0 Antenne régionale du projet t de l'Adamaoua CM-UGP-PFS-232878-NC-RF Laying the Foundations of a Single Stage - One 2021-06-3 2021-06-2 2021-08-2 2021-08-1 2022-08-2 Q / Fourniture d'une police d' IDA / 62230 Safety Net System and Sup A posteriori Demande de prix Limited 18,400.00 6,361.56 Signé Envelope 0 4 7 8 7 assurance pour les 6 véhicul porting Project Managemen es du projet t CM-UGP-PFS-257346-NC-DI R / Recrutement par Entente Cash Transfer Program with Directe d'une Agence de Pai Accompanying Measures to Passation de mar En cours d'e 2021-10-2 2021-11-0 2021-12-2 2023-12-2 ement pour assurer les paie IDA / 62230 A posteriori Direct 48,600.00 0.00 Boost Household Productivit ché de gré à gré xécution 9 3 2 2 ments des bénéficiaires de l y a phase 4 des Transferts Mo nétaires d’Urgence du Projet Filets Sociaux CM-UGP-PFS-172112-NC-RF Laying the Foundations of a Q / Fourniture d'une police d' Safety Net System and Sup Single Stage - One En attente d 2022-03-3 2022-05-3 2023-05-3 IDA / 62230 A posteriori Demande de prix Limited 12,000.00 0.00 assurance pour 60 motos du porting Project Managemen Envelope 'exécution 0 1 1 Projet Filets Sociaux t CM-UGP-PFS-285043-NC-RF Cash Transfer Program with Q / Fourniture des services d Accompanying Measures to Single Stage - One En attente d 2022-04-2 2022-06-1 2022-12-1 IDA / 62230 A posteriori Demande de prix Limited 49,727.00 0.00 'impression et de reprograph Boost Household Productivit Envelope 'exécution 3 8 5 ie des documents du Projet y CM-UGP-PFS-172057-NC-RF Laying the Foundations of a Single Stage - One 2021-04-0 2021-05-2 2021-11-2 Q / Confection et pause des IDA / 62230 Safety Net System and Sup A posteriori Demande de prix Limited 24,000.00 0.00 Annulé Envelope 9 8 4 plaques signalitiques du Proj porting Project Managemen et Filets Sociaux t CM-UGP-PFS-206863-NC-RF Laying the Foundations of a Q / Maintenance du matériel Safety Net System and Sup Single Stage - One 2021-04-2 2021-06-1 2022-06-1 IDA / 62230 A posteriori Demande de prix Limited 8,250.00 0.00 Annulé et logiciels informatique du porting Project Managemen Envelope 0 5 5 Projet Filets Sociaux t CM-UGP-PFS-233113-NC-RF Q / Agences de paiement de la phase 10 des Travaux à Single Stage - One 2022-04-0 2022-06-2 2022-12-1 IDA / 62230 Public Works Program Pilot A posteriori Demande de prix Limited 38,250.00 0.00 Annulé Haute Intensité de Main d'Œ Envelope 9 0 7 uvre dans les régions de l'A damaoua, du Nord et de l'ex trême Nord en deux lots dist incts CM-UGP-PFS-232601-NC-RF Laying the Foundations of a Q / Fourniture des systèmes Safety Net System and Sup Single Stage - One En attente d 2022-04-1 2022-05-1 2023-03-0 IDA / 62230 A posteriori Demande de prix Limited 10,800.00 0.00 de sécurité et de GPS et du s porting Project Managemen Envelope 'exécution 0 1 7 ervice de tracking pour les a t utos du projet CM-UGP-PFS-285486-NC-DI R / Recrutement par Entente Directe de l’agence de paie Cash Transfer Program with ment CAMCCUL pour le paie Accompanying Measures to Passation de mar 2022-03-3 2022-03-3 2022-04-0 2022-04-1 2022-05-2 2022-04-2 2023-05-2 ment des frais de transport IDA / D2980 A posteriori Direct 2,974.00 2,354.56 Signé Boost Household Productivit ché de gré à gré 0 0 4 4 3 2 3 des relais communautaires c y hargés d’appuyer le projet d ans la mise en œuvre de la p hase pilote de l’expérimenta tion de l’accompagnement p lus CM-UGP-PFS-291086-NC-DI R / Recrutement des agence s de paiement chargées d'ef fectuer les paiements des b Passation de mar En cours d'e 2022-05-0 2022-05-0 2022-05-1 2022-05-1 2022-06-2 2022-12-2 énéficiaires de la phase 10 d IDA / 62230 Public Works Program Pilot A posteriori Direct 38,250.00 0.00 ché de gré à gré xécution 2 2 2 1 3 0 es Travaux à Haute Intensité de Main d'œuvre du Projet Fi lets Sociaux dans les régions de l'Extrême Nord et du Nor d et dans la région de l'Ada maoua CONSULTING FIRMS Activity Reference No. / Short List and Draft Combined Evaluatio Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Expression of Interes Request for Proposal Opening of Technica Evaluation of Techni Description Component Review Type Method Terms of Reference Request for Proposal n Report and Draft N Signed Contract Contract Completion No. ch ount (US$) nt (US$) s t Notice s as Issued l Proposals / Minutes cal Proposal s egotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6358-CS-CQS / ONG pour THIMO: 7000 béné ficiaires dans 2 communes d Sélection fondée e l'Extrême Nord, 2 commun sur les qualificati 2016-10-0 2017-02-2 2017-04-1 2017-02-2 2017-05-1 2017-03-0 2017-06-1 2018-03-2 2017-12-1 2018-04-1 IDA / 52240 Public Works Program Pilot A posteriori Open - National 429,190.00 367,605.09 Achevé 2017-02-07 es de l'Est pour la phase 3 et ons des consulta 7 8 3 2 3 3 7 3 4 0 6000 bénéficiaires: 2 comm nts unes Adamaoua, 1 commun e Nord pour la phase 4 en 2 017 (1 ONG par région) CM-UGP-PFS-54735-CS-CQS Cash Transfer Program with Sélection fondée / Consultant pour le dévelop Accompanying Measures to sur les qualificati 2018-06-1 2018-06-2 2018-10-2 2018-08-0 2019-01-2 2018-09-0 2019-03-2 2018-10-0 2019-04-1 2019-04-0 pement d'un progiciel de ge IDA / 52240 A posteriori Open - National 167,500.00 135,528.54 Signé 2018-05-30 Boost Household Productivit ons des consulta 1 0 6 3 3 2 2 7 5 5 stion intégré pour le systèm y nts e d'information du Projet Fil ets Sociaux CM-UGP-PFS-172238-CS-QC Laying the Foundations of a BS / Recrutement d'un cabin Sélection fondée Safety Net System and Sup En cours d'exécu 2020-08-2 2020-09-1 2020-11-0 2020-11-2 2020-12-2 2021-02-0 2021-03-1 2022-03-1 et pour l'audit externe du P IDA / 62230 A posteriori sur la qualité et l Open - National 36,000.00 0.00 2020-08-28 porting Project Managemen tion 5 8 1 9 9 5 2 2 rojet Filets Sociaux, finance e coût t ment additionnel , exercices 2019-2020 (18 mois) , 2021 CM-UGP-PFS-175920-CS-CQ S / Recrutement d'une ONG pour la mise en œuvre des a Sélection fondée ctivités de la Phase 8 des T sur les qualificati 2021-01-2 2021-03-0 2021-04-0 2021-05-0 2021-11-0 HIMO dans les régions du No IDA / 62230 Public Works Program Pilot A posteriori Open - National 89,678.22 0.00 Annulé 2020-12-30 ons des consulta 0 5 4 9 5 rd Ouest, Commune de Sant nts a (2000 bénéficiaires) et du Sud-Ouest, Communes de B uéa (1000 bénéficiaires) et d e Limbé II (1500 bénéficiaire s) CM-UGP-PFS-206866-CS-CQ S / Recrutement d'une ONG chargée d'accompagner le P Sélection fondée rojet Filets Sociaux dans la sur les qualificati En cours d'exécu 2020-12-1 2021-02-2 2021-04-0 2021-05-0 2021-06-0 2021-12-0 mise en œuvre de la phase IDA / 62230 Public Works Program Pilot A posteriori Open - National 165,070.00 0.00 2021-01-30 ons des consulta tion 1 0 5 5 9 6 8 des THIMO dans la région nts de l'Adamaoua (Communes de Nganha et Nyambaka) et dans la région du Centre (Co mmunes de Lembe Yezoum) CM-UGP-PFS-206867-CS-CQ S / Recrutement d'une ONG chargée d'accompagner le P Sélection fondée rojet Filets Sociaux dans la sur les qualificati En cours d'exécu 2021-02-2 2021-04-0 2021-05-0 2021-06-0 2021-12-0 mise en œuvre de la phase IDA / 62230 Public Works Program Pilot A posteriori Open - National 231,098.00 0.00 2021-01-30 ons des consulta tion 0 5 5 9 6 9 des THIMO dans les région nts s de l'Adamaoua (Commune de Meiganga), de l'Est (Com mune de Kentzou), et du Su d (Communes de Sangmeli ma et d'Ebolowa 1) CM-UGP-PFS-206928-CS-CQ Cash Transfer Program with Sélection fondée S / Recrutement de la firme Accompanying Measures to sur les qualificati En cours d'exécu 2021-01-1 2021-02-0 2021-03-1 2021-04-1 2021-05-2 2022-05-2 d'appui à la mise en œuvre IDA / D2980 A posteriori Open - National 160,000.00 0.00 2021-01-11 Boost Household Productivit ons des consulta tion 2 1 7 6 1 1 des interventions dans le ca y nts dre de l'étude quantitative s ur les VBG CM-UGP-PFS-232639-CS-CQ S / recrutement d'une ONG c Sélection fondée hargée d'accompagner le pr sur les qualificati En attente d'exé 2021-08-2 2021-10-0 2021-11-0 2021-12-0 2022-06-0 ojet dans la réalisation de la IDA / 62230 Public Works Program Pilot A posteriori Open - National 148,563.00 0.00 2021-07-30 ons des consulta cution 0 3 2 7 5 phase 10 des travaux à hau nts te Intensité de Main d'Œuvre (THIMO) dans la région de l' Extrême Nord CM-UGP-PFS-232640-CS-CQ S / Recrutement de l'ONG ch Sélection fondée argée d'accompagner le proj sur les qualificati En attente d'exé 2021-08-2 2021-10-0 2021-11-0 2021-12-0 2022-06-0 et dans la réalisation de la p IDA / 62230 Public Works Program Pilot A posteriori Open - National 132,056.00 0.00 2021-07-30 ons des consulta cution 0 3 2 7 5 hase 10 des Travaux à Haut nts e Intensité de main d'Œuvre (THIMO) dans les régions du Nord et de l'Adamaoua INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Identifie Loan / Credit Market Approa Contract Type Estimated Am Actual Amou Process Statu Draft Negotiated Co Description Component Review Type Method Terms of Reference d/Selected Consulta Signed Contract Contract Completion No. ch ount (US$) nt (US$) s ntract nt Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6328-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2016-12-2 2017-03-2 2017-04-1 2017-05-1 2017-05-2 2017-01-1 2017-06-1 IDA / 52240 A posteriori Individuel Open 12,950.00 10,372.40 Signé 2017-02-06 et l'enregistrement à Blango Boost Household Productivit 0 7 7 9 2 9 6 ua du cycle 2 des transferts y monetaires CM-UGP-PFS-6334-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-03-2 2017-04-1 2017-01-1 2017-05-2 2017-01-1 2017-06-1 2018-01-0 IDA / 52240 A posteriori Individuel Open 12,950.00 10,368.36 Achevé 2017-02-06 et l'enregistrement à Goulfe Boost Household Productivit 5 7 7 3 2 9 6 8 y du cycle 2 des transferts y monetaires CM-UGP-PFS-6337-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-03-2 2017-04-1 2017-06-1 2017-05-2 2017-01-1 2017-06-2 IDA / 52240 A posteriori Individuel Open 15,500.00 12,422.62 Signé 2017-02-06 et l'enregistrement à Makari Boost Household Productivit 5 7 7 3 2 9 1 du cycle 2 des transferts mo y netaires CM-UGP-PFS-6339-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-03-2 2017-04-1 2017-05-1 2017-05-2 2017-01-1 2017-06-1 2017-07-1 IDA / 52240 A posteriori Individuel Open 12,500.00 10,372.40 Achevé 2017-02-06 et l'enregistrement à GOBO Boost Household Productivit 7 7 7 9 2 9 6 4 du cycle 2 des transferts mo y netaires CM-UGP-PFS-6340-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-03-2 2017-04-1 2017-05-1 2017-05-2 2017-01-1 2017-06-1 IDA / 52240 A posteriori Individuel Open 12,500.00 10,379.07 Signé 2017-02-06 et l'enregistrement à BOURR Boost Household Productivit 5 7 7 6 2 9 6 HA du cycle 2 des transferts y monetaires Page 4 CM-UGP-PFS-6341-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-03-2 2017-04-1 2017-05-1 2017-05-2 2017-01-1 2017-06-1 IDA / 52240 A posteriori Individuel Open 12,500.00 10,379.07 Signé 2017-02-06 et l'enregistrement à Koza d Boost Household Productivit 5 7 7 6 2 9 6 u cycle 2 des transferts mon y etaires CM-UGP-PFS-6342-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-02-1 2017-02-1 2017-05-1 2017-02-2 2017-01-1 2017-03-2 IDA / 52240 A posteriori Individuel Open 12,500.00 10,372.40 Signé 2017-02-06 et l'enregistrement à Mogod Boost Household Productivit 6 3 4 8 4 9 1 é du cycle 2 des transferts y monetaires CM-UGP-PFS-6344-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-02-1 2017-02-1 2017-05-1 2017-02-2 2017-01-2 2017-03-2 IDA / 52240 A posteriori Individuel Open 15,500.00 11,613.54 Signé 2017-02-06 et l'enregistrement à Banyo Boost Household Productivit 5 3 4 7 4 6 6 du cycle 2 des transferts mo y netaires CM-UGP-PFS-6346-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-2 2017-02-1 2017-02-1 2017-06-2 2017-02-2 2017-01-1 2017-03-2 IDA / 52240 A posteriori Individuel Open 12,500.00 10,381.76 Signé 2017-02-06 et l'enregistrement à Tchebo Boost Household Productivit 9 3 4 8 4 9 1 a du cycle 2 des transferts y monetaires CM-UGP-PFS-6347-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-02-1 2017-02-1 2017-02-2 2017-01-2 2017-03-2 IDA / 52240 A posteriori Individuel Open 12,500.00 9,829.76 Signé 2017-02-06 et l'enregistrement à Mayo Boost Household Productivit 5 3 4 4 6 1 Oulo du cycle 2 des transfert y s monetaires CM-UGP-PFS-6348-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-02-2 2017-02-2 2017-05-2 2017-02-2 2017-01-2 2017-03-2 2017-09-1 IDA / 52240 A posteriori Individuel Open 12,500.00 9,707.50 Achevé 2017-02-06 et l'enregistrement à Rey Bo Boost Household Productivit 6 4 6 4 8 6 5 8 uba du cycle 2 des transfert y s monetaires CM-UGP-PFS-6349-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-2 2017-02-0 2017-02-1 2017-05-2 2017-02-1 2017-01-2 2017-03-0 IDA / 52240 A posteriori Individuel Open 12,500.00 9,716.26 Signé 2017-02-06 et l'enregistrement à Toubor Boost Household Productivit 2 9 0 6 2 6 9 o du cycle 2 des transferts y monetaires CM-UGP-PFS-6350-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2016-12-2 2017-02-1 2017-02-2 2017-03-0 2017-03-1 2017-03-2 2017-09-2 IDA / 52240 A posteriori Individuel Open 12,500.00 11,772.77 Achevé 2017-02-06 et l'enregistrement à Kette d Boost Household Productivit 0 8 8 4 4 9 7 u cycle 2 des transferts mon y etaires CM-UGP-PFS-6351-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-02-1 2017-02-2 2017-05-1 2017-03-0 2017-03-1 2017-03-2 IDA / 52240 A posteriori Individuel Open 12,500.00 9,713.75 Signé 2017-02-06 et l'enregistrement à Belo d Boost Household Productivit 5 8 8 7 4 4 9 u cycle 2 des transferts mon y etaires CM-UGP-PFS-6352-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-02-1 2017-02-2 2017-05-1 2017-03-0 2017-03-1 2017-03-2 IDA / 52240 A posteriori Individuel Open 12,500.00 9,703.73 Signé 2017-02-06 et l'enregistrement à Mench Boost Household Productivit 5 8 8 6 4 4 9 um Valley du cycle 2 des tra y nsferts monetaires CM-UGP-PFS-6353-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2016-12-2 2017-02-1 2017-02-2 2017-02-2 2017-03-1 2017-03-0 2017-03-1 2017-03-2 2017-08-0 IDA / 52240 A posteriori Individuel Open 15,500.00 9,020.07 Achevé 2017-02-06 et l'enregistrement à Douala Boost Household Productivit 0 8 3 8 0 4 4 9 1 3 du cycle 2 des transferts y monetaires CM-UGP-PFS-6354-CS-INDV Cash Transfer Program with / Consultant pour le ciblage Accompanying Measures to 2017-05-1 2017-02-1 2017-02-2 2017-05-2 2017-03-0 2017-03-1 2017-03-2 IDA / 52240 A posteriori Individuel Open 15,500.00 9,264.24 Signé 2017-02-06 et l'enregistrement à Yaoun Boost Household Productivit 7 8 8 4 4 4 9 dé du cycle 2 des transferts y monetaires CM-UGP-PFS-6355-CS-INDV / Consultant chargé d'amélio rer les modules du volet éco Cash Transfer Program with nomique notamment formati Accompanying Measures to 2016-12-1 2017-02-2 2017-02-0 2017-03-0 2017-03-2 2017-03-1 2017-03-2 2017-04-1 2018-09-2 on en AGR ( agriculture, peti IDA / 52240 A posteriori Individuel Open 26,260.00 22,361.04 Achevé 2017-02-10 Boost Household Productivit 5 5 9 2 1 2 1 7 4 t commerce, gestion de l'arg y ent, élevage) et former les b énéficiaires dans ces module s à l'Extrême Nord dans le c adre de la phase 2 du cycle 1 CM-UGP-PFS-6356-CS-INDV / Consultant chargé d'amélio rer les modules du volet éco Cash Transfer Program with nomique : formation en AGR Accompanying Measures to 2016-12-1 2017-02-2 2017-02-0 2017-03-0 2017-03-2 2017-03-1 2017-03-2 2017-04-1 2018-09-2 ( agriculture,petit commerce IDA / 52240 A posteriori Individuel Open 28,460.00 24,278.93 Achevé 2017-02-10 Boost Household Productivit 5 5 9 2 1 2 1 7 1 , gestion de l'argent, élevag y e) et former les bénéficiaires dans ces modules dans le N ord et l'Adamaoua dans le c adre de la phase 2 du cycle 1 CM-UGP-PFS-6357-CS-INDV / Consultant chargé d'amélio rer les modules du volet éco Cash Transfer Program with nomique : formation en AGR Accompanying Measures to 2016-12-1 2017-02-2 2017-02-0 2017-03-0 2017-03-2 2017-03-1 2017-03-2 2017-04-1 2018-10-2 ( agriculture,petit commerce IDA / 52240 A posteriori Individuel Open 31,400.00 26,919.25 Achevé 2017-02-10 Boost Household Productivit 5 5 9 2 1 2 1 7 5 , gestion de l'argent, élevag y e) et former les bénéficiaires dans ces modules dans le N ord O, Est, Dla, Ydé dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6421-CS-INDV 2017-07-1 2017-04-0 2017-03-2 2017-04-2 2017-06-0 2017-11-2 / Expert environnemental et IDA / 52240 Public Works Program Pilot A priori Individuel Open 63,840.00 0.00 Annulé 2017-02-17 3 7 9 8 2 9 social du PFS Laying the Foundations of a CM-UGP-PFS-6423-CS-INDV 2017-07-1 2017-03-2 2017-05-0 2017-04-1 2017-05-2 2017-06-2 IDA / 52240 Safety Net System and Sup A priori Individuel Open 1,920.00 0.00 Annulé 2017-02-07 / Assistant Comptable 3 8 9 8 3 8 porting Project Managemen t Laying the Foundations of a CM-UGP-PFS-6424-CS-INDV 2017-07-1 2017-03-2 2017-03-2 2017-04-1 2017-05-2 2017-06-2 IDA / 52240 Safety Net System and Sup A priori Individuel Open 1,920.00 0.00 Annulé 2017-02-07 / Assistant SPM 3 8 1 8 3 8 porting Project Managemen t CM-UGP-PFS-6327-CS-CDS / Cash Transfer Program with Sélection de cons protocole d'accord avec l'INS Accompanying Measures to 2017-02-1 2017-03-0 2017-09-2 IDA / 52240 A priori ultants par enten Direct 900,000.00 0.00 Annulé 2017-02-06 pour le dénombrement et l'e Boost Household Productivit 6 3 9 te directe nquête PMT du cycle 2 y CM-UGP-PFS-14406-CS-IND Cash Transfer Program with V / Opérateur Terrain comm Accompanying Measures to 2017-06-2 2017-06-0 2017-10-2 2017-06-1 2017-10-2 2017-06-2 2017-10-3 2019-06-2 IDA / 52240 A posteriori Individuel Open 12,960.00 7,006.15 Signé 2017-05-19 une Mayo Moskota (Extrême Boost Household Productivit 6 4 3 1 7 1 1 1 Nord) pour les transferts mo y netaires d'urgence CM-UGP-PFS-14407-CS-IND Laying the Foundations of a 2015-01-0 2017-05-0 2017-05-0 2017-05-1 2017-06-1 2017-05-1 2017-06-0 2019-05-1 V / Renouvellement du cont IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 24,000.00 81,097.42 Signé 2017-05-08 9 9 5 0 3 0 9 0 rat de l'Assistante du Coordo porting Project Managemen nnateur du Projet t CM-UGP-PFS-14409-CS-IND Laying the Foundations of a V / Renouvellement du cont Safety Net System and Sup 2015-01-0 2017-05-0 2017-05-0 2017-05-0 2017-06-1 2017-05-0 2017-06-0 2019-05-0 IDA / 52240 A posteriori Individuel Open 19,200.00 44,266.70 Signé 2017-05-05 rat de la Secrétaire de l'Unit porting Project Managemen 9 6 5 7 4 7 9 7 é de Gestion du Projet t CM-UGP-PFS-14410-CS-IND Laying the Foundations of a 2015-01-0 2017-05-0 2017-05-0 2017-05-0 2017-06-0 2017-05-0 2017-06-0 2019-05-0 V / Renouvellement contrat IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 16,800.00 38,438.87 Signé 2017-05-05 9 6 5 7 9 7 9 7 Chauffeur 1 de l'Unité de Ge porting Project Managemen stion du Projet t CM-UGP-PFS-14411-CS-IND Laying the Foundations of a 2015-06-0 2017-05-0 2015-05-0 2017-05-0 2017-06-0 2017-05-0 2017-06-0 2019-05-0 V / Renouvellement contrat IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 16,800.00 38,438.87 Signé 2017-05-05 9 6 5 7 9 7 9 7 Chauffeur 2 Unité de Gestio porting Project Managemen n du Projet t CM-UGP-PFS-14412-CS-IND Laying the Foundations of a V / Renouvellement du cont Safety Net System and Sup 2015-01-0 2017-05-0 2017-05-0 2017-05-0 2017-05-3 2017-05-0 2017-06-0 2019-05-0 IDA / 52240 A posteriori Individuel Open 16,800.00 32,191.68 Signé 2017-05-05 rat de l'Agent de liaison de l' porting Project Managemen 9 6 5 7 1 7 9 7 Unité de Gestion du Projet t CM-UGP-PFS-14463-CS-IND Laying the Foundations of a 2017-06-1 2017-06-1 2017-06-1 2019-06-1 V / Avenant au contrat de l'o IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 12,960.00 0.00 Annulé 2017-06-09 2 3 5 5 perateur de terrain de Yaoun porting Project Managemen dé 7 t CM-UGP-PFS-14460-CS-IND Laying the Foundations of a V / Avenant au contrat de l'o Safety Net System and Sup 2017-06-1 2017-06-1 2017-06-1 2017-12-1 IDA / 52240 A posteriori Individuel Open 3,240.00 0.00 Annulé 2017-06-09 pératrice de terrain de la co porting Project Managemen 2 3 5 2 mmune de Douala 2 t CM-UGP-PFS-14490-CS-IND Laying the Foundations of a 2017-06-2 2017-06-2 2017-06-2 2019-06-2 V / Avenant au contrat de Te IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 16,800.00 0.00 Annulé 2017-06-15 3 5 9 9 chnicienne de surface de l'U porting Project Managemen GP t CM-UGP-PFS-14454-CS-IND Laying the Foundations of a 2017-10-2 2017-06-1 2017-06-1 2015-06-1 2017-06-1 2015-06-1 2019-06-1 V / Avenant au contrat du po IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 19,200.00 34,575.36 Résilié 2017-06-09 7 2 3 5 5 7 5 int focal de la ville de Douala porting Project Managemen t CM-UGP-PFS-16811-CS-IND Laying the Foundations of a V / renouvellement de contr Safety Net System and Sup 2017-06-1 2017-06-0 2017-06-1 2017-06-0 2017-06-1 2017-06-0 2019-06-0 IDA / 52240 A posteriori Individuel Direct 12,960.00 25,629.07 Signé 2017-06-09 at opérateur de terrain 1 co porting Project Managemen 1 7 2 9 3 9 3 mmune de MOKOLO t CM-UGP-PFS-16814-CS-IND Laying the Foundations of a 2017-06-1 2017-06-0 2017-06-1 2017-06-0 2017-06-1 2017-06-0 2019-06-0 V / renouvellement contrat o IDA / 52240 Safety Net System and Sup A posteriori Individuel Direct 12,960.00 23,513.04 Signé 2017-06-09 2 7 3 9 4 9 4 pérateur de terrain 2 commu porting Project Managemen ne de MOKOLO t CM-UGP-PFS-16821-CS-IND Laying the Foundations of a V / Renouvellement de contr Safety Net System and Sup 2017-06-1 2017-06-0 2017-06-1 2017-06-0 2017-06-1 2017-06-0 2019-06-0 IDA / 52240 A posteriori Individuel Direct 12,960.00 23,513.04 Signé 2017-06-09 at de l'opérateur de terrain d porting Project Managemen 2 7 3 9 5 9 5 e la commune de MAGA t CM-UGP-PFS-16823-CS-IND Laying the Foundations of a V / Renouvellement du contr Safety Net System and Sup 2022-01-1 2017-06-1 2017-06-0 2017-06-1 2017-06-0 2017-06-1 2017-06-0 2017-12-0 IDA / 52240 A posteriori Individuel Direct 3,240.00 14,966.57 Signé 2017-06-09 at de l'opérateur de terrain porting Project Managemen 1 0 7 1 9 2 9 9 de la commune de Kar Hay t CM-UGP-PFS-16925-CS-IND Laying the Foundations of a 2017-06-1 2017-06-1 2017-06-2 2019-06-1 V / Avenant au contrat du SP IDA / 52240 Safety Net System and Sup A priori Individuel Open 63,840.00 0.00 Annulé 2017-06-12 5 9 1 1 M du Projet porting Project Managemen t CM-UGP-PFS-14451-CS-IND Laying the Foundations of a 2017-07-1 2017-06-1 2017-06-1 2017-06-1 2019-06-1 V / Renouvellement du cont IDA / 52240 Safety Net System and Sup A priori Individuel Open 46,000.00 0.00 Annulé 2017-06-09 9 0 4 5 5 rat Comptable porting Project Managemen t CM-UGP-PFS-14446-CS-IND Laying the Foundations of a V / Renouvellement du cont Safety Net System and Sup 2017-07-1 2017-06-0 2017-06-1 2017-06-1 2019-06-1 IDA / 52240 A priori Individuel Open 63,840.00 0.00 Annulé 2017-06-09 rat de l'Expert Informatique porting Project Managemen 9 9 0 5 5 et Responsable SIG du Projet t CM-UGP-PFS-14452-CS-IND Laying the Foundations of a 2017-06-1 2017-06-1 2017-06-1 2017-06-1 2019-06-1 V / Renouvellement du contr IDA / 52240 Safety Net System and Sup A priori Individuel Direct 38,400.00 0.00 Annulé 2017-06-09 2 3 3 5 5 at du Responsable Régional porting Project Managemen Extrême Nord t CM-UGP-PFS-25501-CS-IND Laying the Foundations of a V / Recrutement du respons Safety Net System and Sup 2017-08-1 2017-09-2 2017-10-2 2017-10-0 2017-11-0 2017-10-1 2017-11-0 2018-10-1 IDA / 52240 A posteriori Individuel Open 19,200.00 47,854.03 Signé 2017-08-31 able régional du Nord ouest porting Project Managemen 7 6 5 3 6 3 3 3 du projet Filets Sociaux t CM-UGP-PFS-25504-CS-IND Laying the Foundations of a V / Consultant chargé de la Safety Net System and Sup 2017-09-0 2017-09-2 2017-10-0 2017-10-0 2017-11-0 2017-10-1 2017-11-0 2018-04-1 IDA / 52240 A posteriori Individuel Open 21,500.00 80,692.20 Signé 2017-09-01 Conception et l' appui à la m porting Project Managemen 6 9 2 6 3 6 3 9 ise en œuvre du plan de co t mmunication CM-UGP-PFS-25520-CS-IND V / Recrutement de 4 consul tants pour le ciblage des bé Laying the Foundations of a néficiaires de la phase 2 des Safety Net System and Sup 2017-10-0 2017-10-1 2017-12-0 2017-10-1 2017-12-1 2017-10-2 2017-12-1 2017-11-1 2018-09-1 transferts monetaires d'urge IDA / 52240 A posteriori Individuel Open 36,400.00 30,128.36 Achevé 2017-09-07 porting Project Managemen 5 2 5 9 1 7 2 6 7 nce dans les département d t u Logone et Chari (Commun es de Blangoua, Goulfey, Ma kari) et dans le département du Mayo Tsanaga(commune de Mayo Moskota CM-UGP-PFS-25782-CS-IND Laying the Foundations of a V / Avenant N°01 au contrat Safety Net System and Sup 2014-10-1 2017-09-0 2017-06-1 2017-09-1 2017-06-1 2017-09-1 2017-08-1 2018-09-1 IDA / 52240 A posteriori Individuel Open 38,095.25 233,063.21 Signé 2017-09-06 de l'Expert informatique et r porting Project Managemen 0 9 3 0 5 1 7 1 esponsable SIG UGP t Page 5 CM-UGP-PFS-25786-CS-IND Laying the Foundations of a V / Avenant N°02 au contrat Safety Net System and Sup 2013-05-2 2017-09-0 2017-06-1 2017-09-1 2017-06-2 2017-09-1 2017-08-1 2018-09-1 IDA / 52240 A posteriori Individuel Open 38,095.25 71,473.92 Signé 2017-09-06 du Spécialiste en passation porting Project Managemen 9 9 9 0 2 1 7 1 des Marchés de l'UGP t CM-UGP-PFS-25787-CS-IND Laying the Foundations of a 2014-10-1 2017-09-0 2017-06-1 2017-09-1 2017-06-1 2017-09-1 2017-08-1 2018-09-1 V / Avenant N°1 au contrat d IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 35,555.57 167,336.95 Signé 2017-09-06 4 9 3 0 5 1 7 1 u Comptable de l'UGP porting Project Managemen t CM-UGP-PFS-25794-CS-IND Laying the Foundations of a V / Avenant N°1 au contrat d Safety Net System and Sup 2015-04-1 2017-09-0 2017-06-1 2017-09-1 2017-06-1 2017-09-1 2017-08-1 2018-09-1 IDA / 52240 A posteriori Individuel Open 19,200.00 138,374.99 Signé 2017-09-06 u Responsable régional du P porting Project Managemen 4 9 3 0 6 1 7 1 rojet Filets Sociaux dans l'Ex t trême Nord CM-UGP-PFS-25517-CS-IND V / Consultant chargé de la s Cash Transfer Program with ensibilisation des bénéficiair Accompanying Measures to 2017-09-0 2017-10-1 2017-10-2 2017-10-1 2017-11-0 2017-10-2 2017-11-0 2018-02-2 IDA / 52240 A posteriori Individuel Open 58,180.00 43,182.70 Signé 2017-09-07 es du Cycle 2 (i) à l'Extrême Boost Household Productivit 6 2 5 9 1 7 1 4 Nord, (ii) au Nord et à l'Ada y maoua, (iii) à l'Est, au Nord- ouest, à Douala et à Yaound é CM-UGP-PFS-6326-CS-CDS / Cash Transfer Program with Sélection de cons 2017-09-0 2017-08-3 2017-09-1 2017-09-2 2018-05-1 Protocole d'accord avec l'INS IDA / 52240 Accompanying Measures to A priori ultants par enten Direct 500,000.00 391,776.36 Signé 2017-08-31 5 1 6 8 4 pour la réalisation de l'enqu Boost Household Productivit te directe ête de base y CM-UGP-PFS-25509-CS-IND Cash Transfer Program with V / Recrutement de 34 relais Accompanying Measures to 2017-10-1 2017-12-3 2017-11-2 2018-01-0 2017-11-2 2018-01-1 2017-12-0 2019-01-1 2019-05-3 communautaires dans la co IDA / 52240 A posteriori Individuel Open 40,800.00 49,307.71 Signé 2017-11-30 Boost Household Productivit 3 0 0 6 4 4 7 4 1 mmune de Koza, départeme y nt du Mayo Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25508-CS-IND Cash Transfer Program with V / Recrutement de 34 relais Accompanying Measures to 2017-10-1 2018-01-2 2017-11-2 2018-02-0 2017-11-2 2018-02-1 2017-12-0 2019-02-1 communautaires dans la co IDA / 52240 A posteriori Individuel Open 40,800.00 46,287.84 Signé 2017-12-30 Boost Household Productivit 3 9 4 3 7 1 5 1 mmune de Bourrha, départe y ment du Mayo Tsanaga, Rég ion de l'Extrême Nord CM-UGP-PFS-25512-CS-IND Cash Transfer Program with V / Recrutement de 34 relais Accompanying Measures to 2017-10-1 2017-12-3 2017-11-0 2018-01-0 2017-11-2 2018-01-1 2017-12-0 2019-01-1 communautaires dans la co IDA / 52240 A posteriori Individuel Open 40,800.00 69,189.81 Signé 2017-11-30 Boost Household Productivit 3 0 8 6 2 4 5 4 mmune de Mogode, départe y ment du Mayo Tsanaga, Rég ion de l'Extrême Nord CM-UGP-PFS-25515-CS-IND Cash Transfer Program with V / Recrutement de 34 relais Accompanying Measures to 2017-10-1 2018-01-0 2017-11-2 2018-01-0 2017-11-2 2018-01-1 2017-12-0 2019-01-1 communautaires dans la co IDA / 52240 A posteriori Individuel Open 40,800.00 50,528.89 Signé 2017-11-30 Boost Household Productivit 3 2 4 9 8 7 5 7 mmune de Mayo-Oulo, dépa y rtement du Mayo Louti, Régi on du Nord CM-UGP-PFS-25516-CS-IND Cash Transfer Program with V / Recrutement de 34 relais Accompanying Measures to 2017-10-1 2018-01-0 2017-12-0 2018-01-1 2017-12-0 2018-01-1 2017-12-0 2019-01-1 communautaires dans la co IDA / 52240 A posteriori Individuel Open 40,800.00 68,555.87 Signé 2017-11-30 Boost Household Productivit 3 4 4 1 4 9 5 9 mmune de Tcheboa, départe y ment de la Bénoué, Région d u Nord CM-UGP-PFS-37431-CS-IND Laying the Foundations of a 2018-01-1 2018-01-2 2018-02-2 2018-01-2 2018-03-0 2018-01-2 2018-03-0 2019-01-2 V / Chauffeur de l'antenne ré IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 6,840.00 10,274.36 Signé 2017-12-27 1 0 8 2 6 9 6 9 gionale du Projet du Nord- O porting Project Managemen uest t CM-UGP-PFS-37432-CS-IND Laying the Foundations of a 2018-01-1 2018-01-2 2018-02-2 2018-01-2 2018-03-0 2018-02-0 2018-03-0 2019-02-0 V / Secrétaire de l'antenne r IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 9,600.00 15,722.34 Signé 2017-12-28 1 3 8 8 6 4 6 4 égionale du Projet du Nord O porting Project Managemen uest t CM-UGP-PFS-37434-CS-IND Laying the Foundations of a 2018-01-1 2017-12-2 2018-02-2 2017-12-2 2018-03-2 2017-12-2 2018-03-2 2018-12-2 V / Point focal du Projet de la IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 9,600.00 14,584.42 Signé 2017-11-30 1 2 8 6 9 8 9 8 ville de Douala porting Project Managemen t CM-UGP-PFS-25972-CS-CQS / Avenant au contrat N°001/ MINEPAT/CTS/PFS/CAPM/201 7 du 23 mars 2017 de l'ONG Sélection de cons 2017-12-2 2017-12-2 2017-12-2 2018-01-1 2018-02-1 2018-07-1 2019-05-2 chargée de la mise en œuvr IDA / 52240 Public Works Program Pilot A posteriori ultants par enten Direct 99,042.50 93,748.34 Achevé 2017-12-18 1 5 2 8 3 7 2 e des THIMO 3 dans l'Extrê te directe me Nord avec 4000 bénéfici aires pour la mise en œuvre des THIMO 5 avec 3000 bén éficiaires dans la région du Nord-ouest CM-UGP-PFS-25907-CS-CQS / Avenant au contrat N°002/ MINEPAT/CTS/PFS/CAPM/201 7 du 23 mars 2017 de l'ONG Sélection de cons 2017-12-2 2017-12-2 2017-12-2 2018-01-1 2018-02-1 2018-07-1 2018-07-2 chargée de la mise en œuvr IDA / 52240 Public Works Program Pilot A posteriori ultants par enten Direct 99,042.50 92,937.44 Achevé 2017-12-18 1 5 2 8 3 7 7 e des THIMO 3 dans la régio te directe n de l'Est avec 3000 bénéfi ciaires pour la mise en œuvr e des THIMO 5 avec 3000 bé néficiaires dans la région de l'Est CM-UGP-PFS-47367-CS-IND V / Consultant individuel cha 2018-04-0 2018-04-1 2018-04-2 2018-05-2 IDA / 52240 Public Works Program Pilot A posteriori Individuel Limited 8,250.00 0.00 Annulé 2018-03-30 rgé d'actualiser la carte des 4 8 8 8 THIMO du Projet Filets Socia ux CM-UGP-PFS-47368-CS-IND V / Consultants individuels ( Cash Transfer Program with 3) chargés du ciblage des bé Accompanying Measures to 2018-05-0 2018-05-2 2018-06-0 2018-07-1 IDA / 52240 A posteriori Individuel Open 20,256.00 0.00 Annulé 2018-04-06 néficiaires de la phase 3 des Boost Household Productivit 9 3 2 7 transferts monétaires d'urg y ence dans la région du Nord Ouest CM-UGP-PFS-47363-CS-IND V / Consultants individuels ( Cash Transfer Program with 03) chargés de compléter et Accompanying Measures to 2018-02-0 2018-04-1 2018-04-0 2018-04-2 2018-04-1 2018-05-1 2018-04-1 2019-05-1 d'améliorer les manuels de f IDA / 52240 A posteriori Individuel Open 63,040.00 87,765.09 Signé 2018-03-09 Boost Household Productivit 2 4 6 8 3 2 8 2 ormation et de former les bé y néficiaires sur les AGR pour l e cycle 2 des transferts mon étaires du Projet Filets CM-UGP-PFS-47362-CS-IND Cash Transfer Program with V / Consultant individuel cha Accompanying Measures to 2018-05-1 2018-04-1 2018-05-2 2018-04-2 2018-06-0 2018-04-3 2018-06-0 2019-04-3 IDA / 52240 A posteriori Individuel Open 8,250.00 7,158.24 Signé 2018-03-15 rgé de la traduction des doc Boost Household Productivit 5 7 3 4 1 0 1 0 uments du projet en anglais y CM-UGP-PFS-25526-CS-IND Laying the Foundations of a V / Consultant chargé de l'ac Safety Net System and Sup 2018-10-3 2017-10-1 2017-10-1 2017-10-2 2018-10-2 IDA / 52240 A posteriori Individuel Open 12,000.00 0.00 Annulé 2017-09-15 compagnement en TOM2PR porting Project Managemen 0 1 6 4 4 O, TOM2PAIE, TOM2MONITO t RING et TOM2MARCHE CM-UGP-PFS-25881-CS-IND Laying the Foundations of a 2018-08-0 2018-05-1 2018-09-1 2018-05-2 2018-09-1 2018-06-1 2018-09-1 2018-12-1 2019-02-1 V / Consultant chargé du dé IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 8,250.00 7,201.62 Achevé 2018-04-17 8 3 0 0 2 7 3 4 5 veloppement du site WEB porting Project Managemen t CM-UGP-PFS-16899-CS-IND Laying the Foundations of a 2014-10-1 2017-10-1 2017-10-1 2017-09-0 2017-10-2 2017-11-0 2019-10-1 V / Avenant au contrat de l'a IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 76,190.00 71.57 Signé 2017-10-02 4 3 8 8 3 1 3 uditeur interne porting Project Managemen t CM-UGP-PFS-47928-CS-IND Cash Transfer Program with 2018-06-2 2018-05-3 2018-11-1 2018-06-1 2018-11-2 2018-07-0 2019-01-0 2019-07-0 V / Assistant au suivi évaluat IDA / 52240 Accompanying Measures to A posteriori Individuel Open 12,000.00 10,966.15 Signé 2018-04-20 2 0 2 3 0 4 3 4 ion Boost Household Productivit y CM-UGP-PFS-47923-CS-IND Cash Transfer Program with 2018-03-2 2018-05-0 2018-10-0 2018-05-2 2018-10-1 2018-06-1 2018-10-1 2019-06-1 V / Recrutement d'un Spécia IDA / 52240 Accompanying Measures to A posteriori Individuel Open 12,000.00 26,092.28 Signé 2018-04-04 6 7 1 1 0 8 1 8 liste en Passation des March Boost Household Productivit é Assistant y CM-UGP-PFS-54610-CS-IND Cash Transfer Program with V / consultant individuel pou Accompanying Measures to 2018-03-2 2018-04-2 2018-05-1 2018-06-1 2018-12-1 r l'assistance à la migration IDA / 52240 A posteriori Individuel Limited 8,250.00 0.00 Annulé 2018-04-16 Boost Household Productivit 6 1 2 6 3 comptable vers le nouveau r y éférentiel comptable SYSCO HADA révisé CM-UGP-PFS-54615-CS-IND Cash Transfer Program with V / consultant pour assister l Accompanying Measures to 2018-10-3 2018-04-2 2018-11-1 2018-05-1 2018-12-0 2018-06-2 2018-12-0 2019-06-2 IDA / 52240 A posteriori Individuel Limited 8,250.00 10,408.76 Signé 2018-04-20 'UGP à l'utilisation optimale Boost Household Productivit 0 5 9 6 6 0 7 0 des logiciels TOM2PRO, TO y M2PAIE et TOM2MARCHE CM-UGP-PFS-54616-CS-IND V / Consultant pour la conce Cash Transfer Program with ption du masque de saisie, l Accompanying Measures to 2018-08-0 2018-04-3 2018-08-1 2018-05-2 2018-09-1 2018-06-2 2018-09-1 2018-12-2 IDA / 52240 A posteriori Individuel Limited 8,250.00 7,097.50 Signé 2018-04-25 a supervision de la saisie et l Boost Household Productivit 7 0 4 1 0 5 1 2 'analyse des données de la p y remière évaluation interne d u Projet IDA CM-UGP-PFS-47366-CS-IND Cash Transfer Program with V / Consultant individuel cha Accompanying Measures to 2018-05-0 2018-05-1 2018-05-2 2018-06-2 rgé d'actualiser la carte de p IDA / 52240 A posteriori Individuel Limited 8,250.00 0.00 Annulé 2018-04-30 Boost Household Productivit 5 9 9 8 auvreté pour les transferts y monétaires du Projet Filets S ociaux CM-UGP-PFS-47370-CS-IND Cash Transfer Program with Sélection de cons V / Avenant au contrat du po Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 IDA / 52240 A posteriori ultants par enten Direct 3,600.00 3,181.63 Signé 2018-04-20 int focal du Projet dans le Dé Boost Household Productivit 1 7 8 3 8 0 te directe partement du Mberé, région y de l'Adamaoua CM-UGP-PFS-25974-CS-CQS Sélection de cons / Contrat ONG pour la phase 2018-07-0 2018-06-0 2018-07-2 2018-07-3 2018-09-1 2019-01-2 2019-02-0 IDA / 52240 Public Works Program Pilot A posteriori ultants par enten Direct 99,042.50 85,366.88 Achevé 2018-05-30 6 des THIMO pour 3000 bén 2 9 0 0 9 6 9 te directe éficiaires dans 2 communes de la région du Nord CM-UGP-PFS-47376-CS-IND V / Avenant au contrat de l'o Cash Transfer Program with Sélection de cons pérateur de terrain de la co Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 IDA / 52240 A posteriori ultants par enten Direct 2,430.00 2,169.08 Signé 2018-04-24 mmune de la commune de l Boost Household Productivit 1 8 8 4 8 1 te directe a commune de kai kai dépar y tement du Mayo Danay, régi on de l'extrême Nord CM-UGP-PFS-47377-CS-IND Cash Transfer Program with V / Avenant au contrat de l'o Sélection de cons Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 pérateur de terrain de la co IDA / 52240 A posteriori ultants par enten Direct 2,430.00 2,147.60 Signé 2018-04-24 Boost Household Productivit 1 8 8 4 8 1 mmune de Méri, départeme te directe y nt du Diamaré, région de l'E xtrême Nord CM-UGP-PFS-47378-CS-IND Cash Transfer Program with V / Avenant au contrat de l'o Sélection de cons Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 pérateur de terrain de la co IDA / 52240 A posteriori ultants par enten Direct 2,430.00 2,147.60 Signé 2018-04-24 Boost Household Productivit 1 8 8 4 8 1 mmune de Ndoukoula, dépa te directe y rtement du Diamaré, région de l'Extrême Nord CM-UGP-PFS-47379-CS-IND Cash Transfer Program with V / Avenant au contrat de l'o Sélection de cons Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 pérateur de terrain de la co IDA / 52240 A posteriori ultants par enten Direct 2,430.00 2,169.08 Signé 2018-04-24 Boost Household Productivit 1 8 8 4 8 1 mmune de Guider, départe te directe y ment du Mayo Louti, région du Nord CM-UGP-PFS-47430-CS-IND Cash Transfer Program with V / Avenant au contrat de l'o Sélection de cons Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 pérateur de terrain de la co IDA / 52240 A posteriori ultants par enten Direct 2,430.00 2,147.60 Signé 2018-04-24 Boost Household Productivit 1 8 8 4 8 1 mmune de Lagdo, départem te directe y ent de la Bénoué, région du Nord CM-UGP-PFS-47431-CS-IND V / Avenant au contrat de l'o Cash Transfer Program with Sélection de cons pérateur de terrain N° 1 de l Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 IDA / 52240 A posteriori ultants par enten Direct 2,430.00 2,147.60 Signé 2018-04-24 a commune de Bibemi (ADA Boost Household Productivit 1 8 8 4 8 1 te directe MOU Bienvenu), départemen y t de la Bénoué, région du No rd CM-UGP-PFS-47432-CS-IND V / Avenant au contrat de l'o Cash Transfer Program with Sélection de cons pérateur de terrain N° 2 de l Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 IDA / 52240 A posteriori ultants par enten Direct 2,430.00 2,147.60 Signé 2018-04-24 a commune de Bibemi (GOU Boost Household Productivit 1 8 8 4 8 1 te directe DOUM GRANA Dieunedort), y département de la Bénoué, r égion du Nord Page 6 CM-UGP-PFS-47433-CS-IND V / Avenant au contrat de l'o Cash Transfer Program with Sélection de cons pérateur de terrain de la co Accompanying Measures to 2018-02-2 2018-04-2 2018-01-2 2018-04-2 2018-02-2 2019-04-2 IDA / 52240 A posteriori ultants par enten Direct 8,100.00 8,495.18 Signé 2018-04-18 mmune de Kar Hay pour la c Boost Household Productivit 3 2 3 8 8 8 te directe ommune de Makary dans le y département du Logone et C hari, région de l'Extrême Nor d CM-UGP-PFS-47434-CS-IND Cash Transfer Program with Sélection de cons V / Avenant au contrat de la Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2019-12-3 IDA / 52240 A posteriori ultants par enten Direct 16,800.00 15,497.59 Signé 2018-04-24 secrétaire de l'antenne régio Boost Household Productivit 1 8 8 4 8 0 te directe nale de l'Extrême Nord y CM-UGP-PFS-47435-CS-IND Cash Transfer Program with 2018-03-1 2018-07-0 2018-03-1 2018-07-0 2018-03-2 2018-07-0 2019-12-1 V / Avenant au contrat du ch IDA / 52240 Accompanying Measures to A posteriori Individuel Direct 11,340.00 7,980.91 Signé 2018-03-05 2 2 7 4 5 4 5 auffeur de l'antenne régional Boost Household Productivit e du Nord y CM-UGP-PFS-47369-CS-IND Cash Transfer Program with Sélection de cons V / Avenant au contrat du po Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-11-0 IDA / 52240 A posteriori ultants par enten Direct 3,600.00 3,188.07 Signé 2018-04-25 int focal du département du Boost Household Productivit 1 9 8 5 8 1 te directe Diamaré dans la région de l' y Extrême Nord CM-UGP-PFS-47371-CS-IND V / Avenant au contrat de l'o Cash Transfer Program with Sélection de cons pérateur de terrain N°1 de la Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 IDA / 52240 A posteriori ultants par enten Direct 2,430.00 2,147.60 Signé 2018-04-24 commune de DIR (HEBGASS Boost Household Productivit 1 8 8 4 8 1 te directe O Jean Baptiste) départeme y nt du Mbéré, région de l'Ada maoua CM-UGP-PFS-47372-CS-IND Cash Transfer Program with V / Avenant au contrat de l'o Sélection de cons Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 pérateur de terrain N° 2 de l IDA / 52240 A posteriori ultants par enten Direct 2,430.00 2,147.60 Signé 2018-04-24 Boost Household Productivit 1 8 8 4 8 1 a Commune de Dir (HOULAO te directe y Pierre) département du Mbé ré, région de l'Adamoua CM-UGP-PFS-47375-CS-IND V / Avenant au contrat de l'o Cash Transfer Program with Sélection de cons pérateur de terrain N°2 de la Accompanying Measures to 2018-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 IDA / 52240 A posteriori ultants par enten Direct 2,430.00 2,147.60 Signé 2018-04-24 commune de BOGO( Wanie Boost Household Productivit 1 8 8 4 8 1 te directe Bernard) département du Di y amaré, région de l'Extrême Nord CM-UGP-PFS-47373-CS-IND Cash Transfer Program with V / Avenant au contrat de l'o Sélection de cons Accompanying Measures to 2016-01-1 2018-04-2 2018-02-2 2018-05-0 2018-02-2 2018-10-3 pératrice de terrain N°1 de l IDA / 52240 A posteriori ultants par enten Direct 2,430.00 2,147.60 Signé 2018-04-24 Boost Household Productivit 1 8 8 4 8 1 a commune de BOGO, dépar te directe y tement du Diamaré, région d e l'Extrême Nord CM-UGP-PFS-59671-CS-CDS Cash Transfer Program with Sélection de cons 2016-01-1 2018-05-1 2018-05-3 2018-05-1 2018-05-3 2018-11-1 / Opérateur de terrain de la IDA / 52240 Accompanying Measures to A posteriori ultants par enten Direct 3,240.00 2,391.05 Signé 2018-04-30 1 0 0 9 1 5 commune de Douala 4 Boost Household Productivit te directe y CM-UGP-PFS-59673-CS-IND Cash Transfer Program with V / Recrutement du Respons Accompanying Measures to 2018-06-1 2018-06-0 2018-10-1 2018-06-1 2018-11-1 2018-06-2 2018-12-0 2019-06-2 IDA / 52240 A posteriori Individuel Open 19,200.00 16,630.56 Signé 2018-05-04 able régional de l'antenne d Boost Household Productivit 2 6 0 3 6 2 3 2 u Nord du Projet Filets Socia y ux CM-UGP-PFS-59789-CS-CDS / Audit financier et comptabl e des comptes du Projet de Cash Transfer Program with Sélection de cons Remise à niveau des Réseau Accompanying Measures to 2018-04-2 2018-04-3 2018-03-2 2018-05-1 2018-07-3 2020-05-1 IDA / 52240 A posteriori ultants par enten Direct 54,000.00 46,581.42 Signé 2018-04-26 x de Transport d'Electricité e Boost Household Productivit 0 0 3 4 1 3 te directe t Réforme du Secteur (PRRT y ERS): exercices 2017-2018 - 2019 et du Projet Filets Soc iaux (PFS) : exercices 2017- 2018 CM-UGP-PFS-67474-CS-CDS Laying the Foundations of a / Avenant au contrat de l'op Sélection de cons Safety Net System and Sup 2015-12-3 2018-07-0 2018-05-0 2018-07-0 2018-05-0 2019-01-0 érateur de terrain de la com IDA / 52240 A posteriori ultants par enten Direct 3,240.00 2,831.73 Signé 2018-06-29 porting Project Managemen 0 3 2 9 8 5 mune de Yaoundé 1er NGO te directe t SICK ELEANOR RHOLY épous e KAM CM-UGP-PFS-67475-CS-CDS / Avenant au contrat de l'op Laying the Foundations of a Sélection de cons érateur de terrain de la com Safety Net System and Sup 2015-12-3 2018-07-0 2018-05-0 2018-07-0 2018-05-0 2019-01-0 IDA / 52240 A posteriori ultants par enten Direct 3,240.00 2,831.73 Signé 2018-06-29 mune de Funfong, départem porting Project Managemen 0 3 2 9 8 5 te directe ent du Boyo région du Nord t Ouest AGHA-AH EVARISTUS ALANJI CM-UGP-PFS-67477-CS-CDS / Avenant au contrat de l'op Laying the Foundations of a Sélection de cons érateur de terrain de la com Safety Net System and Sup 2015-12-3 2018-07-0 2018-05-0 2018-07-0 2018-05-0 2019-01-0 IDA / 52240 A posteriori ultants par enten Direct 3,240.00 2,831.73 Signé 2018-06-29 mune de Balikumbat départ porting Project Managemen 0 3 2 9 8 5 te directe ement du Ngo Ketungja régi t on du Nord Ouest TAJIPUKU ALPHONSE TAMIGHANG CM-UGP-PFS-67478-CS-CDS / avenant au contrat de l'opé Laying the Foundations of a Sélection de cons rateur de terrain N1 de la co Safety Net System and Sup 2015-12-3 2018-07-0 2018-05-0 2018-07-0 2018-05-0 2019-01-0 IDA / 52240 A posteriori ultants par enten Direct 3,240.00 2,831.73 Signé 2018-06-29 mmune de Messamena dépa porting Project Managemen 0 3 2 9 8 5 te directe rtement du Haut Nyong régi t on de l'Est TSALA MVOGO BE RNARD JEAN CM-UGP-PFS-67479-CS-CDS Laying the Foundations of a Sélection de cons / Avenant au contrat du poin Safety Net System and Sup 2015-12-3 2018-07-0 2015-05-0 2018-07-0 2018-05-0 2019-01-0 IDA / 52240 A posteriori ultants par enten Direct 4,800.00 4,195.15 Signé 2018-06-29 t focal du département du H porting Project Managemen 0 3 4 9 8 5 te directe aut Nyong région de l'Est MB t ILLA Pierre Valery CM-UGP-PFS-67481-CS-CDS Laying the Foundations of a / avenant au contrat de l'opé Sélection de cons Safety Net System and Sup 2015-12-3 2018-07-0 2018-06-2 2018-07-1 2018-06-2 2018-11-0 rateur de terrain N°2 de la c IDA / 52240 A posteriori ultants par enten Direct 2,160.00 1,887.82 Signé 2018-07-02 porting Project Managemen 0 6 5 2 9 9 ommune de Messamena ESS te directe t OMBA YANNICK ALBERT NGU EM CM-UGP-PFS-67482-CS-CDS Laying the Foundations of a / Avenant au contrat de l'op Sélection de cons Safety Net System and Sup 2015-12-3 2018-07-0 2018-05-1 2018-07-0 2018-05-1 2018-08-0 2018-06-3 érateur de terrain N°2 de la IDA / 52240 A posteriori ultants par enten Direct 540.00 471.95 Achevé 2018-06-29 porting Project Managemen 0 3 0 8 5 7 0 commune de Lagdo, départe te directe t ment de la Bénoué, région d u Nord SIRINA ELVIS CM-UGP-PFS-67517-CS-IND Laying the Foundations of a Sélection de cons 2018-07-0 2018-07-1 2019-07-1 V / Responsable Administrati IDA / 52240 Safety Net System and Sup A posteriori ultants par enten Direct 38,095,248.00 0.00 Annulé 2018-06-29 4 1 1 f et Financier du Projet porting Project Managemen te directe t CM-UGP-PFS-72586-CS-IND Laying the Foundations of a 2018-09-1 2018-09-0 2018-09-1 2018-09-2 2018-09-1 2018-10-2 2018-09-1 2019-10-2 V / Recrutement d'un opérat IDA / 52240 Safety Net System and Sup A posteriori Individuel Direct 5,940.00 5,136.94 Signé 2018-08-23 3 2 4 3 7 8 7 8 eur de terrain pour la comm porting Project Managemen une de Koza t CM-UGP-PFS-81429-CS-IND V / consultants national séni Laying the Foundations of a or chargé d'appuyer la Banq Safety Net System and Sup 2018-10-0 2018-10-2 2018-11-2 2018-11-1 2018-11-2 2018-12-2 2018-11-3 2019-03-2 2019-09-0 ue mondiale et le Projet Filet IDA / 52240 A posteriori Individuel Limited 24,600.00 21,307.91 Achevé 2018-10-18 porting Project Managemen 5 5 6 5 8 0 0 0 4 s Sociaux dans la préparatio t n d'une évaluation qualitativ e sur les Violences Basées s ur le Genre (VBG) au Camer oun CM-UGP-PFS-83718-CS-IND Laying the Foundations of a 2018-10-2 2018-12-3 2019-03-1 2019-01-2 2019-03-1 2019-02-2 2019-04-0 2021-02-2 V / Responsable Administrati IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 38,096.00 125,993.93 Signé 2018-11-11 2 0 3 0 8 4 1 3 f et Financier du Projet Filets porting Project Managemen Sociaux t CM-UGP-PFS-83719-CS-IND Laying the Foundations of a 2018-10-2 2018-12-3 2019-02-1 2019-01-2 2019-03-0 2019-02-2 2019-03-1 2020-02-2 V / Expert en sauvegardes s IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 38,095.00 25,544.73 Signé 2018-11-11 4 0 9 0 4 4 5 4 ociales du Projet Filets Socia porting Project Managemen ux t CM-UGP-PFS-83720-CS-IND Laying the Foundations of a V / coach du responsable de Safety Net System and Sup 2018-11-0 2019-01-0 2019-03-0 2019-01-2 2019-03-1 2019-03-0 2019-04-1 2019-08-3 IDA / 52240 A posteriori Individuel Open 38,095.00 19,480.26 Résilié 2018-11-18 s activités d'accompagneme porting Project Managemen 1 6 7 7 1 3 7 0 nt du Projet Filets Sociaux t CM-UGP-PFS-83722-CS-IND Laying the Foundations of a 2018-11-0 2019-01-0 2019-02-1 2019-01-2 2019-02-2 2019-03-0 2019-02-2 2020-03-0 V / Assistant en Gestion des IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 14,400.00 10,329.66 Signé 2018-11-18 1 6 8 7 0 3 0 2 Ressources Humaines et du porting Project Managemen matériel t CM-UGP-PFS-83723-CS-IND Laying the Foundations of a V / Assistant au Responsable Safety Net System and Sup 2018-11-1 2019-01-0 2019-03-0 2019-01-2 2019-03-0 2019-03-0 2019-03-0 2020-03-0 IDA / 52240 A posteriori Individuel Open 14,400.00 9,119.51 Signé 2018-11-18 du Systeme d'Information porting Project Managemen 3 6 1 7 6 3 6 2 du Projet Filets Sociaux t MOF-CM-UGP-PFS-14460-CS Laying the Foundations of a Sélection de cons -CDS / Avenant au contrat d Safety Net System and Sup 2017-06-1 2017-06-0 2017-06-1 2017-06-1 2017-12-1 IDA / 52240 A posteriori ultants par enten Direct 3,240.00 2,785.30 Signé 2017-06-09 e l'opératrice de terrain de l porting Project Managemen 3 9 6 7 3 te directe a commune de Douala 2 t MOF-UGP-PFS-14463-CS-CD Laying the Foundations of a Sélection de cons 2017-06-1 2017-06-0 2017-06-2 2017-06-1 2019-06-2 S / Avenant au contrat de l'o IDA / 52240 Safety Net System and Sup A posteriori ultants par enten Direct 12,960.00 25,147.34 Signé 2017-01-12 2 9 3 5 3 perateur de terrain de Yaoun porting Project Managemen te directe dé 7 t MOF-UGP-PFS-14490-CS-CD Laying the Foundations of a Sélection de cons 2015-01-1 2017-06-2 2017-06-2 2017-07-0 2017-07-0 2019-07-0 S / Avenant au contrat de Te IDA / 52240 Safety Net System and Sup A posteriori ultants par enten Direct 16,800.00 14,442.29 Signé 2017-06-15 3 3 3 2 3 2 chnicienne de surface de l'U porting Project Managemen te directe GP t MOF-CM-UGP-PFS-6421-CS-I Laying the Foundations of a 2017-02-1 2017-04-0 2017-05-1 2017-04-2 2017-05-1 2017-06-0 2017-06-0 2019-06-0 NDV / Expert environnement IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 63,840.00 110,857.53 Signé 2017-02-17 0 7 7 8 8 2 9 2 al et social du PFS porting Project Managemen t Laying the Foundations of a MOF-CM-UGP-PFS-6423-CS-I 2017-01-1 2017-03-2 2017-05-1 2017-04-1 2017-05-1 2017-05-2 2017-06-1 2018-05-2 2018-06-1 IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 9,600.00 27,305.89 Signé 2017-02-07 NDV / Assistant Comptable 1 8 7 8 7 3 3 3 3 porting Project Managemen t Laying the Foundations of a MOF-CM-UGP-PFS-6424-CS-I 2017-01-1 2017-03-2 2017-04-1 2017-04-1 2017-04-2 2017-05-2 2017-05-1 2018-05-2 IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 9,600.00 6,156.07 Résilié 2017-02-07 NDV / Assistant SPM 1 8 2 8 1 3 0 3 porting Project Managemen t CM-UGP-PFS-108883-CS-IND Laying the Foundations of a 2019-03-2 2019-06-1 2019-08-0 2019-07-0 2019-08-1 2019-08-0 2019-09-0 2020-08-0 2020-08-3 V / Auditeur interne du Proje IDA / 52240 Safety Net System and Sup A posteriori Individuel Open 45,714.00 29,878.57 Achevé 2019-04-19 4 6 8 7 3 4 9 3 1 t Filets Sociaux porting Project Managemen t CM-UGP-PFS-111619-CS-CD Cash Transfer Program with S / Avenant N°01 au contrat Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2019-12-0 de l'Opérateur de Terrain 1 IDA / 52240 A posteriori ultants par enten Direct 2,160.00 1,832.99 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 5 de la Commune de Banyo, D te directe y épartement du Mayo Banyo, Région de l'Adamaoua CM-UGP-PFS-111629-CS-CD Cash Transfer Program with S / Avenant Contrat de l'Opé Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2019-12-0 rateur de Terrain 2 de la Co IDA / 52240 A posteriori ultants par enten Direct 2,160.00 1,845.59 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 5 mmune de Banyo, Départem te directe y ent du Mayo Banyo, Région de l'Adamaoua CM-UGP-PFS-111638-CS-CD Cash Transfer Program with S / Avenant contrat de l'Opér Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-1 2020-01-1 ateur de Terrain de la Comm IDA / 52240 A posteriori ultants par enten Direct 2,898.00 2,459.26 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 8 6 une de Bélo, Département d te directe y u Boyo, Région du Nord-Oue st CM-UGP-PFS-111640-CS-CD Cash Transfer Program with Sélection de cons S / Avenant au contrat de l'O Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-1 2020-01-1 IDA / 52240 A posteriori ultants par enten Direct 2,898.00 32,024.07 Signé 2019-05-22 pérateur de Terrain 1 de Do Boost Household Productivit 2 1 4 5 8 6 te directe uala IIIe, Ville de Douala y CM-UGP-PFS-111642-CS-CD Cash Transfer Program with Sélection de cons S / Avenant de l'Opérateur d Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-1 2020-01-1 IDA / 52240 A posteriori ultants par enten Direct 2,898.00 32,052.15 Signé 2019-05-22 e Terrain 2 de la Commune Boost Household Productivit 2 1 4 5 8 6 te directe de Douala IIIe, Ville de Doual y a CM-UGP-PFS-111643-CS-CD Cash Transfer Program with Sélection de cons S / Avenant de l'Opérateur d Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-1 2020-01-1 IDA / 52240 A posteriori ultants par enten Direct 2,898.00 15,181.83 Signé 2019-05-22 e Terrain 1 de la Commune Boost Household Productivit 2 1 4 5 8 6 te directe de Ketté, Département de la y Kadey, Région de l'Est CM-UGP-PFS-111658-CS-CD Cash Transfer Program with S / Avenant contrat de l'Opér Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-1 2020-01-1 ateur de Terrain 2 de la Com IDA / 52240 A posteriori ultants par enten Direct 2,898.00 15,181.83 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 8 6 mune de Ketté, Départemen te directe y t de la Kadey, Région de l'Es t Page 7 CM-UGP-PFS-111662-CS-CD Cash Transfer Program with Sélection de cons S / Avenant contrat de l'Opér Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-1 2020-01-1 IDA / 52240 A posteriori ultants par enten Direct 2,898.00 32,052.15 Signé 2019-05-22 atrice de Terrain 1 de la Co Boost Household Productivit 2 1 4 5 8 6 te directe mmune de Yaoundé IIe, Ville y de Yaoundé CM-UGP-PFS-111664-CS-CD Cash Transfer Program with S / Avenant contrat de l'Opér Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2019-11-0 ateur de Terrain de la Comm IDA / 52240 A posteriori ultants par enten Direct 1,620.00 1,374.74 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 4 une de Blangoua, Départem te directe y ent du Logone et Chari, Régi on de l'Extrême-Nord CM-UGP-PFS-111670-CS-CD Cash Transfer Program with S / Avenant contrat de l'Opér Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2019-11-0 ateur de Terrain de la Comm IDA / 52240 A posteriori ultants par enten Direct 1,620.00 1,374.74 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 4 une de Bourha, Départemen te directe y t du Mayo Tsanaga, Région de l'Extrême-Nord CM-UGP-PFS-111678-CS-CD Cash Transfer Program with S / Avenant contrat de l'Opér Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2019-11-0 ateur de Terrain de la Comm IDA / 52240 A posteriori ultants par enten Direct 1,620.00 1,374.74 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 4 une de Gobo, Département te directe y du Mayo Danay, Région de l' Extrême-Nord CM-UGP-PFS-111681-CS-CD Cash Transfer Program with S / Avenant contrat de l'Opér Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2019-11-0 ateur de Terrain de la Comm IDA / 52240 A posteriori ultants par enten Direct 1,620.00 1,374.74 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 4 une de Goulfey, Départemen te directe y t du Logone et Chari, Région de l'Extrême-Nord CM-UGP-PFS-111685-CS-CD Cash Transfer Program with S / Avenant contrat de l'Opér Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2019-11-0 ateur de Terrain de la Comm IDA / 52240 A posteriori ultants par enten Direct 1,620.00 1,374.74 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 4 une de Koza, Département d te directe y u Mayo Tsanaga, Région de l 'Extrême-Nord CM-UGP-PFS-111688-CS-CD Cash Transfer Program with S / Avenant contrat de l'Opér Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2020-05-0 ateur de Terrain de la Comm IDA / 52240 A posteriori ultants par enten Direct 4,860.00 4,124.22 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 6 une de Makari, Département te directe y du Logone et Chari, Région de l'Extrême-Nord CM-UGP-PFS-111691-CS-CD Cash Transfer Program with S / Avenant de l'Opérateur d Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2020-05-0 e Terrain de la Commune de IDA / 52240 A posteriori ultants par enten Direct 4,860.00 4,124.22 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 6 Mogodé, Département du M te directe y ayo Tsanaga, Région de l'Ext rême-Nord CM-UGP-PFS-111692-CS-CD Cash Transfer Program with S / Avenant contrat de l'Opér Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2019-12-0 ateur de Terrain de la Comm IDA / 52240 A posteriori ultants par enten Direct 2,160.00 1,832.99 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 5 une de Mayo Oulo, Départe te directe y ment du Mayo Louti, Région du Nord CM-UGP-PFS-111696-CS-CD Cash Transfer Program with S / Avenant de l'Opérateur d Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2020-05-0 e Terrain de la Commune de IDA / 52240 A posteriori ultants par enten Direct 4,860.00 4,124.22 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 6 Rey Bouba, Département du te directe y Mayo Rey, Région du Nord CM-UGP-PFS-111698-CS-CD Cash Transfer Program with S / Avenant de l'Opérateur d Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2020-05-0 e Terrain de la Commune de IDA / 52240 A posteriori ultants par enten Direct 4,898.00 4,124.22 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 6 Tchéboa, Département de la te directe y Bénoué, Région du Nord CM-UGP-PFS-111699-CS-CD Cash Transfer Program with S / Avenant de l'Opérateur d Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2019-12-0 e Terrain 1 de la Commune IDA / 52240 A posteriori ultants par enten Direct 2,160.00 1,832.99 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 5 de Touboro, Département du te directe y Mayo Rey, Région du Nord CM-UGP-PFS-111725-CS-CD Cash Transfer Program with Sélection de cons S / Avenant contrat Point Fo Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-1 2020-01-1 IDA / 52240 A posteriori ultants par enten Direct 4,293.00 22,491.60 Signé 2019-05-22 cal du Projet Filets Sociaux d Boost Household Productivit 2 1 4 5 8 6 te directe ans le Département de la Ka y dey, Région de l'Est CM-UGP-PFS-111726-CS-CD Cash Transfer Program with S / Avenant contrat Point Fo Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2020-05-0 cal du Projet Filets Sociaux d IDA / 52240 A posteriori ultants par enten Direct 7,200.00 6,109.96 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 6 ans le Département du Logo te directe y ne et Chari, Région de l'Extr ême-Nord CM-UGP-PFS-111727-CS-CD Cash Transfer Program with S / Avenant contrat Point Fo Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2019-12-0 cal du Projet Filets Sociaux d IDA / 52240 A posteriori ultants par enten Direct 3,200.00 2,715.54 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 5 ans le Département du Mayo te directe y Banyo, Région de l'Adamaou a CM-UGP-PFS-111735-CS-CD Cash Transfer Program with S / Avenant contrat Point Fo Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2019-11-0 cal du Projet Filets Sociaux d IDA / 52240 A posteriori ultants par enten Direct 2,400.00 2,036.65 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 4 ans le Département du Mayo te directe y Danay, Région de l'Extrême- Nord CM-UGP-PFS-111737-CS-CD Cash Transfer Program with S / Avenant contrat Point Fo Sélection de cons Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-2 2020-05-0 cal du Projet Filets Sociaux d IDA / 52240 A posteriori ultants par enten Direct 7,200.00 6,109.96 Signé 2019-05-22 Boost Household Productivit 2 1 4 5 0 6 ans le Département Mayo Ts te directe y anaga, Région de l'Extrême- Nord CM-UGP-PFS-111739-CS-CD Cash Transfer Program with Sélection de cons S / Avenant contrat Point Fo Accompanying Measures to 2017-01-1 2019-06-0 2019-03-1 2019-08-0 2019-03-1 2020-01-1 IDA / 52240 A posteriori ultants par enten Direct 4,293.00 47,484.67 Signé 2019-05-22 cal du Projet Filets Sociaux d Boost Household Productivit 2 1 4 5 8 6 te directe ans la Ville de Yaoundé y CM-UGP-PFS-121795-CS-CD S / Consultant chargé de l'él Laying the Foundations of a Sélection de cons aboration de la méthodologi Safety Net System and Sup 2019-07-1 2019-12-1 2019-10-2 2020-02-1 2020-01-0 2020-03-1 IDA / 62230 A posteriori ultants par enten Direct 28,000.00 23,174.93 Signé 2019-11-30 e de choix et d’opérationnali porting Project Managemen 2 9 9 3 9 4 te directe sation du choix des commun t es bénéficiaires du Projet Fil ets Sociaux CM-UGP-PFS-141188-CS-IND Laying the Foundations of a V / Recrutement d'un point Safety Net System and Sup 2020-02-0 2020-02-2 2020-03-3 2022-03-3 Focal dans la ville de Doua IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 Annulé 2019-12-10 porting Project Managemen 4 5 1 1 la, région du littoral pour la t phase 3 des Transferts Moné taires ordinaires CM-UGP-PFS-141191-CS-IND Laying the Foundations of a V / Recrutement d'un Point Safety Net System and Sup 2020-02-0 2020-02-2 2020-03-3 2022-03-3 Focal dans la ville de Yaound IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 Annulé 2019-12-10 porting Project Managemen 4 5 1 1 é pour la cycle 3 des Transf t erts Monétaires ordinaires CM-UGP-PFS-141758-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 100 Safety Net System and Sup En cours d'exécu 2019-10-1 2020-01-2 2020-02-1 2020-03-2 2020-10-1 0 bénéficiaires de la Phase 3 IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 2019-11-29 porting Project Managemen tion 5 4 4 0 6 des TMU du Projet Filets Soci t aux dans la commune de Wa za, département du Logone et Chari, région de l'Extrême -Nord CM-UGP-PFS-143558-CS-IND V / Recrutement de l'enquêt Laying the Foundations of a eur Chercheur N°1 de l'équi Safety Net System and Sup 2019-09-2 2019-12-2 2019-11-2 2020-01-0 2019-11-2 2020-02-0 2019-11-2 2020-06-0 2020-04-2 pe septentrionale dans le ca IDA / 62230 A posteriori Individuel Limited 5,394.00 7,761.40 Achevé 2019-11-29 porting Project Managemen 7 0 5 3 6 7 7 6 1 dre de la préparation d'une t évaluation qualitative sur les Violences Basées sur le Genr e (VBG) au Cameroun CM-UGP-PFS-143560-CS-IND V / Recrutement de l'enquêt Laying the Foundations of a eur Chercheur N°2 de l'équi Safety Net System and Sup 2019-09-2 2019-12-2 2019-11-2 2020-01-0 2019-11-2 2020-02-0 2019-12-0 2020-06-0 2020-04-2 pe septentrionale dans le ca IDA / 62230 A posteriori Individuel Limited 5,394.00 7,761.40 Achevé 2019-11-29 porting Project Managemen 7 0 6 3 6 7 6 6 0 dre de la préparation d'une t évaluation qualitative sur les Violences Basées sur le Genr e (VBG) au Cameroun CM-UGP-PFS-143562-CS-IND V / Recrutement de l'enquêt Laying the Foundations of a eur Chercheur N°3 de l'équi Safety Net System and Sup 2019-09-2 2019-12-2 2019-11-2 2020-01-0 2019-11-2 2020-02-0 2019-12-1 2020-06-0 2020-04-2 pe septentrionale dans le ca IDA / 62230 A posteriori Individuel Limited 5,394.00 7,761.40 Achevé 2019-11-29 porting Project Managemen 7 0 6 3 6 7 6 6 0 dre de la préparation d'une t évaluation qualitative sur les Violences Basées sur le Genr e (VBG) au Cameroun CM-UGP-PFS-143563-CS-IND V / Recrutement de l'enquêt Laying the Foundations of a eur Chercheur N°4 de l'équi Safety Net System and Sup 2019-09-2 2019-12-2 2019-11-2 2020-01-0 2019-11-2 2020-02-0 2019-11-2 2020-06-0 2020-03-0 pe septentrionale dans le ca IDA / 62230 A posteriori Individuel Limited 5,394.00 7,719.29 Achevé 2019-11-29 porting Project Managemen 7 0 6 3 6 7 7 6 4 dre de la préparation d'une t évaluation qualitative sur les Violences Basées sur le Genr e (VBG) au Cameroun CM-UGP-PFS-143564-CS-IND V / Recrutement de l'enquêt Laying the Foundations of a eur Chercheur N°1 de l'équi Safety Net System and Sup 2019-09-2 2019-12-2 2019-11-2 2020-01-0 2019-11-2 2020-02-0 2019-12-0 2020-06-0 2020-04-2 pe Adamaoua-Est dans le ca IDA / 62230 A posteriori Individuel Limited 4,902.00 7,200.12 Achevé 2019-11-29 porting Project Managemen 7 0 5 3 6 7 6 6 3 dre de la préparation d'une t évaluation qualitative sur les Violences Basées sur le Genr e (VBG) au Cameroun CM-UGP-PFS-143565-CS-IND V / Recrutement de l'enquêt Laying the Foundations of a eur Chercheur N°2 de l'équi Safety Net System and Sup 2019-09-2 2019-12-2 2019-11-2 2020-01-0 2019-11-2 2020-02-0 2019-12-0 2020-06-0 2020-02-2 pe Adamaoua-Est dans le ca IDA / 62230 A posteriori Individuel Limited 4,902.00 7,200.12 Achevé 2019-11-29 porting Project Managemen 7 0 5 3 6 7 6 6 5 dre de la préparation d'une t évaluation qualitative sur les Violences Basées sur le Genr e (VBG) au Cameroun CM-UGP-PFS-143567-CS-IND V / Recrutement de l'enquêt Laying the Foundations of a eur Chercheur N°3 de l'équi Safety Net System and Sup 2019-09-2 2019-12-2 2019-11-2 2020-01-0 2019-11-2 2020-02-0 2019-12-1 2020-06-0 2020-04-2 pe Adamaoua-Est dans le ca IDA / 62230 A posteriori Individuel Limited 4,902.00 7,200.12 Achevé 2019-11-29 porting Project Managemen 7 0 5 3 6 7 3 6 0 dre de la préparation d'une t évaluation qualitative sur les Violences Basées sur le Genr e (VBG) au Cameroun CM-UGP-PFS-143568-CS-IND V / Recrutement de l'enquêt Laying the Foundations of a eur Chercheur N°4 de l'équi Safety Net System and Sup 2019-09-2 2019-12-2 2019-11-2 2020-01-0 2019-11-2 2020-02-0 2019-12-0 2020-06-0 2020-04-2 pe Adamaoua-Est dans le ca IDA / 62230 A posteriori Individuel Limited 4,394.00 7,200.12 Achevé 2019-11-29 porting Project Managemen 7 0 5 3 6 7 6 6 0 dre de la préparation d'une t évaluation qualitative sur les Violences Basées sur le Genr e (VBG) au Cameroun CM-UGP-PFS-152346-CS-IND V / RECRUTEMENT DU CONS Laying the Foundations of a ULTANT CHARGE D’INSTALL Safety Net System and Sup 2020-01-2 2020-02-0 2020-01-2 2020-02-2 2020-02-0 2020-04-0 2020-02-2 2020-07-0 ER ET DE PARAMETRER LES IDA / 62230 A posteriori Individuel Limited 7,500.00 6,007.08 Signé 2020-01-31 porting Project Managemen 2 7 2 8 5 4 1 3 LOGICIELS TOM2PRO, TOM2 t MARCHE ET TOM2PAIE D’UN E PART ET D’AUTRE PART DE RENFORCER LES CAPACITES DE L’UGP CM-UGP-PFS-142945-CS-CD S / Recrutement d'une ONG Sélection de cons pour la mise en œuvre des a En cours d'exécu 2019-10-1 2020-02-2 2020-05-0 2020-12-3 IDA / D2980 Public Works Program Pilot A posteriori ultants par enten Direct 99,042.00 0.00 2020-02-10 ctivités de la Phase 7 des TH tion 5 9 4 0 te directe IMO dans la région de l'Extrê me Nord, commune de Moko lo CM-UGP-PFS-142946-CS-CD S / Recrutement d'une ONG Sélection de cons En cours d'exécu 2020-02-2 2020-02-2 2020-05-0 2020-12-3 pour la mise en œuvre des a IDA / D2980 Public Works Program Pilot A posteriori ultants par enten Direct 132,056.00 0.00 2020-02-10 tion 8 9 4 0 ctivités de la Phase 7 des TH te directe IMO dans la région du Nord , commune de Touboro Page 8 CM-UGP-PFS-142944-CS-CD S / Recrutement d'une ONG pour la mise en œuvre des a Sélection de cons En cours d'exécu 2019-10-1 2020-02-2 2020-05-0 2020-12-3 ctivités de la Phase 7 des T IDA / D2980 Public Works Program Pilot A posteriori ultants par enten Direct 99,042.00 0.00 2020-02-10 tion 6 9 4 0 HIMO dans les régions de l' te directe Adamaoua (commune de Dir ) et de l'Est (Communes de Ngoura et de Mandjou) CM-UGP-PFS-141791-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 200 Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-04-1 0 bénéficiaires du cycle 3 de IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 2020-06-30 porting Project Managemen en 5 5 5 0 8 s TMO du Projet Filets Sociau t x dans la commune de Garo ua Boulaï , département du Lom et Djérem, région de l'E st CM-UGP-PFS-141143-CS-IND V / Recrutement de l' Opérat eur de Terrain N°1 du Proje Laying the Foundations of a t Filets Sociaux de la Comm Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 une de Logone Birni, départ porting Project Managemen en 0 5 5 0 0 ement du Logone et Chari, r t égion de l'Extrême Nord pou r le cycle 3 des Transferts M onétaires Ordinaires CM-UGP-PFS-141192-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 100 Safety Net System and Sup 2019-10-1 2020-08-2 2020-04-1 2020-09-1 2020-04-1 2020-10-2 2020-05-1 2021-05-1 0 bénéficiaires de la Phase 3 IDA / D2980 A posteriori Individuel Open 7,560.00 10,955.52 Signé 2020-06-30 porting Project Managemen 6 5 1 5 5 0 3 8 des TMU du Projet Filets Soci t aux dans la commune de Fot okol, département du Logon e et Chari, région de l'Extrê me-Nord CM-UGP-PFS-141091-CS-IND Laying the Foundations of a V / Recrutement d'un Respo Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 nsable Régional dans la Régi IDA / D2980 A posteriori Individuel Open 38,400.00 0.00 2020-06-30 porting Project Managemen en 0 5 5 0 0 on de l'Est pour la cycle 3 d t es Transferts Monétaires ord inaires CM-UGP-PFS-141718-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain I de la Comm Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 une de Meiganga, départem porting Project Managemen en 0 5 5 0 0 ent du Mbéré, région de l'Ad t amaoua pour le cycle 3 des Transferts Monétaires Ordin aires CM-UGP-PFS-141717-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain N°2 de la Co Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 mmune de Logone Birni, dép IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 porting Project Managemen en 0 5 5 0 0 artement du Logone et Chari t , région de l'Extrême Nord p our le cycle 3 des Transferts Monétaires Ordinaires CM-UGP-PFS-141793-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 300 Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 0 bénéficiaires du cycle 3 de IDA / D2980 A posteriori Individuel Open 12,950.00 0.00 2020-06-30 porting Project Managemen en 5 5 5 0 0 s TMO du Projet Filets Sociau t x dans la commune de Toub oro, département du Mayo-R ey, région du Nord CM-UGP-PFS-141162-CS-IND V / Recrutement d'un Opérat Laying the Foundations of a eur de Terrain dans la Com Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 mune de Meyomessala, Dép IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 porting Project Managemen tion 0 5 5 0 0 artement du Dja et Lobo, rég t ion du Sud pour le cycle 3 de s Transferts Monétaires Ordi naires CM-UGP-PFS-141731-CS-IND V / Recrutement de l'Opérat eur de Terrain N°2 du Projet Laying the Foundations of a Filets Sociaux dans la Com Safety Net System and Sup 2019-10-1 2020-08-2 2020-05-1 2020-09-1 2020-05-1 2020-10-2 2020-06-0 2022-10-2 IDA / 62230 A posteriori Individuel Open 12,960.00 11,666.27 Signé 2020-06-30 mune de Moulvoudaye , dép porting Project Managemen 0 5 7 5 9 0 9 0 artement du Mayo Kani, régi t on de l'Extrême- Nord pour l e cycle 3 des Transferts Mon étaires Ordinaires CM-UGP-PFS-141171-CS-IND V / Recrutement d'un Opéra Laying the Foundations of a teur de Terrain dans la Com Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-10-2 mune de Fotokol, départeme IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 2020-06-30 porting Project Managemen tion 0 5 5 0 0 nt du Logone et Chari, régio t n de l'Extrême Nord pour la phase 3 des Transferts Moné taires d'Urgence CM-UGP-PFS-141780-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 200 Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-05-1 0 bénéficiaires du cycle 3 de IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 2020-06-30 porting Project Managemen en 5 5 5 0 8 s TMO du Projet Filets Sociau t x dans la commune de Meig anga , département du Mbér é, région de l'Adamaoua CM-UGP-PFS-141196-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 200 Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-05-1 0 bénéficiaires du cycle 3 de IDA / 62230 A posteriori Individuel Open 10,400.00 0.00 2020-06-30 porting Project Managemen tion 5 5 5 0 8 s TMO du Projet Filets Sociau t x dans la commune de Madri ngrin , département du May o-Rey, région du Nord CM-UGP-PFS-141170-CS-IND V / Recrutement d'un Opéra Laying the Foundations of a teur de Terrain dans la Com Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-10-2 mune de Waza, départemen IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 2020-06-30 porting Project Managemen en 0 5 5 0 0 t du Logone et Chari, région t de l'Extrême Nord pour la ph ase 3 des Transferts Monétai res d'Urgence CM-UGP-PFS-141801-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 100 Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-05-1 0 bénéficiaires du cycle 3 de IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 2020-06-30 porting Project Managemen tion 5 5 5 0 8 s TMO du Projet Filets Sociau t x dans la commune de Ma'a n , département de la Valée du Ntem, région du Sud CM-UGP-PFS-141167-CS-IND V / Recrutement d'un Opéra Laying the Foundations of a teur de Terrain dans la Com Safety Net System and Sup 2019-10-1 2020-08-2 2020-05-2 2020-09-1 2020-05-2 2020-10-2 2020-06-1 2021-10-2 IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 Signé 2020-06-30 mune de Meiganga, départe porting Project Managemen 0 5 6 5 8 0 1 0 ment du Mbéré, région de l' t Adamaoua pour la phase 3 d es Transferts Monétaires d'U rgence CM-UGP-PFS-141168-CS-IND V / Recrutement d'un Opéra Laying the Foundations of a teur de Terrain dans la Com Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-10-2 IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 2020-06-30 mune de Ngaoui, départeme porting Project Managemen en 0 5 5 0 0 nt du Mbéré, région de l'Ada t maoua pour la phase 3 des T ransferts Monétaires d'Urge nce CM-UGP-PFS-141160-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain N°1 de la la Safety Net System and Sup 2019-10-1 2020-08-2 2020-04-1 2020-09-1 2020-04-1 2020-10-2 2020-05-1 2022-10-2 Commune de Madingring , d IDA / 62230 A posteriori Individuel Open 12,960.00 11,502.26 Signé 2020-06-30 porting Project Managemen 0 5 1 5 6 0 3 0 épartement du Mayo Rey, ré t gion du Nord pour le cycle 3 des Transferts Monetaires Or dinaires CM-UGP-PFS-141755-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 100 Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-05-1 0 bénéficiaires de la Phase 3 IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 2020-06-30 porting Project Managemen tion 5 5 5 0 8 des TMU du Projet Filets Soci t aux dans la commune de Ng aoui, département du Mbéré , région de l'Adamaoua CM-UGP-PFS-141794-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 100 Safety Net System and Sup 2019-10-1 2020-08-2 2020-03-1 2020-09-1 2020-03-1 2020-10-2 2020-04-1 2021-05-1 0 bénéficiaires du cycle 3 de IDA / 62230 A posteriori Individuel Open 6,320.00 7,329.97 Signé 2020-06-30 porting Project Managemen 6 5 6 5 9 0 7 8 s TMO du Projet Filets Sociau t x dans la commune d' Ebolo wa II, département de la Mvi la, région du Sud CM-UGP-PFS-141184-CS-IND Laying the Foundations of a V / Recrutement d'un Point Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 Focal dans le département IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 2020-06-30 porting Project Managemen tion 0 5 5 0 0 du Mayo Rey, région du Nor t d pour la cycle 3 des Transf erts Monétaires ordinaires CM-UGP-PFS-141145-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain N°1 du Projet Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 Filets Sociaux dans la Com IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 porting Project Managemen en 0 5 5 0 0 mune de Bétaré Oya, dépar t tement du Lom et Djérem, r égion de l'Est pour le cycle 3 des Transferts Monétaires Or dinaires CM-UGP-PFS-141787-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 150 Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-05-1 0 bénéficiaires du cycle 3 d IDA / D2980 A posteriori Individuel Open 7,850.00 0.00 2020-06-30 porting Project Managemen en 5 5 5 0 8 es TMO du Projet Filets Socia t ux dans la commune de Log one Birni, département du L ogone et Chari, région de l'E xtrême-Nord CM-UGP-PFS-141812-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 150 Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-05-1 IDA / 62230 A posteriori Individuel Open 7,850.00 0.00 2020-06-30 0 bénéficiaires du cycle 3 de porting Project Managemen en 5 5 5 0 8 s TMO du Projet Filets Sociau t x dans la commune de Yaou ndé III , Ville de Yaoundé CM-UGP-PFS-141727-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain N°2 du Projet Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 Filets Sociaux dans la Com IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 porting Project Managemen tion 0 5 5 0 0 mune de Bétaré Oya, dépar t tement du Lom et Djérem, r égion de l'Est pour le cycle 3 des Transferts Monétaires Or dinaires CM-UGP-PFS-141164-CS-IND V / Recrutement d'un Opérat Laying the Foundations of a eur de Terrain dans la Com Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 mune de Ma'am, Départeme IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 porting Project Managemen tion 0 5 5 0 0 nt de la Vallée du Ntem, rég t ion du Sud pour le cycle 3 de s Transferts Monétaires Ordi naires CM-UGP-PFS-141800-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 100 Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-05-1 0 bénéficiaires du cycle 3 d IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 2020-06-30 porting Project Managemen en 5 5 5 0 8 es TMO du Projet Filets Socia t ux dans la commune de Mey omessala, département du Dja et Lobo, région du Sud CM-UGP-PFS-141159-CS-IND V / Recrutement de l'Opérat eur de Terrain N°1 du Projet Laying the Foundations of a Filets Sociaux dans la Com Safety Net System and Sup 2019-10-1 2020-08-2 2020-05-0 2020-09-1 2020-05-1 2020-10-2 2020-06-0 2022-10-2 IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Signé 2020-06-30 mune de Moulvoudaye , dép porting Project Managemen 0 5 9 5 2 0 9 0 artement du Mayo Kani, régi t on de l'Extrême- Nord pour l e cycle 3 des Transferts Mon étaires Ordinaires CM-UGP-PFS-141097-CS-IND Laying the Foundations of a V / Recrutement d'un Respo Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 nsable Régional dans la Régi IDA / 62230 A posteriori Individuel Open 38,400.00 0.00 2020-06-30 porting Project Managemen tion 0 5 5 0 0 on du SUD pour la cycle 3 d t es Transferts Monétaires ord inaires Page 9 CM-UGP-PFS-141163-CS-IND V / Recrutement d'un Opérat Laying the Foundations of a eur de Terrain dans la Com Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 mune d'Ebolowa II, départe porting Project Managemen en 0 5 5 0 0 ment de la Mvila, région du t Sud pour le cycle 3 des Tran sferts Monétaires Ordinaires CM-UGP-PFS-141141-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain N°1 du Projet Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 Filets Sociaux de la Commu IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 porting Project Managemen tion 0 5 5 0 0 ne de Meiganga, départeme t nt du Mbéré, région de l'Ada maoua pour le cycle 3 des Tr ansferts Monétaires Ordinair es CM-UGP-PFS-141161-CS-IND V / Recrutement de 3 Opérat Laying the Foundations of a eurs de Terrain dans la Com Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-04-2 2020-09-1 2020-04-3 2020-10-2 2022-10-2 IDA / D2980 A posteriori Individuel Open 38,880.00 0.00 2020-06-30 mune de Touboro, départe porting Project Managemen tion 0 5 4 5 0 0 0 ment du Mayo-Rey, région d t u Nord pour le cycle 3 des Tr ansferts Monétaires Ordinair es CM-UGP-PFS-141735-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain N°2 de la la Safety Net System and Sup 2019-10-1 2020-08-2 2020-04-1 2020-09-1 2020-04-1 2020-10-2 2020-05-1 2022-10-2 Commune de Madingring , d IDA / 62230 A posteriori Individuel Open 12,960.00 11,567.97 Signé 2020-06-30 porting Project Managemen 0 5 1 5 7 0 3 0 épartement du Mayo Rey, ré t gion du Nord pour le cycle 3 des Transferts Monetaires Or dinaires CM-UGP-PFS-141155-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain N°1 du Projet Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 filets sociaux dans la Comm IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 porting Project Managemen tion 0 5 5 0 0 une de Garoua-Boulaï, dépa t rtement du Lom et Djérem, r égion de l'Est pour le cycle 3 des Transferts Monétaires Or dinaires CM-UGP-PFS-141785-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 200 Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-05-1 0 bénéficiaires du cycle 3 de IDA / 62230 A posteriori Individuel Open 10,400.00 0.00 2020-06-30 porting Project Managemen tion 5 5 5 0 8 s TMO du Projet Filets Sociau t x dans la commune de Moul voudaye , département du M ayo Kani, région de l'Extrêm e-Nord CM-UGP-PFS-141183-CS-IND V / Recrutement d'un Point Laying the Foundations of a Focal dans le département Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 2020-06-30 du Logone et Chari, région d porting Project Managemen tion 0 5 5 0 0 e l'Extrême Nord pour la cycl t e 3 des Transferts Monétaire s ordinaires CM-UGP-PFS-141804-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des1500 Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-05-1 IDA / 62230 A posteriori Individuel Open 7,850.00 0.00 2020-06-30 bénéficiaires du cycle 3 des porting Project Managemen en 5 5 5 0 8 TMO du Projet Filets Sociaux t dans la commune de Douala V , Ville de Douala CM-UGP-PFS-141187-CS-IND V / Recrutement d'un Point Laying the Foundations of a Focal dans le département Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 IDA / 62230 A posteriori Individuel Open 19,200.00 0.00 2020-06-30 du Mayo Kani, région de l'Ex porting Project Managemen tion 0 5 5 0 0 trême Nord pour la cycle 3 t des Transferts Monétaires or dinaires CM-UGP-PFS-141084-CS-IND Laying the Foundations of a V / Recrutement d'un Respo Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 nsable Régional dans la Régi IDA / D2980 A posteriori Individuel Open 38,400.00 0.00 2020-06-30 porting Project Managemen tion 0 5 5 0 0 on de l'Adamaoua pour la c t ycle 3 des Transferts Monéta ires ordinaires CM-UGP-PFS-141729-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain N°2 du Projet Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 filets sociaux dans la Comm IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 porting Project Managemen tion 0 5 5 0 0 une de Garoua-Boulaï, dépa t rtement du Lom et Djérem, r égion de l'Est pour le cycle 3 des Transferts Monétaires Or dinaires CM-UGP-PFS-141725-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain N°2 du Projet Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2022-10-2 Filets Sociaux de la Commu IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2020-06-30 porting Project Managemen tion 0 5 5 0 0 ne de Meiganga, départeme t nt du Mbéré, région de l'Ada maoua pour le cycle 3 des Tr ansferts Monétaires Ordinair es CM-UGP-PFS-141193-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 200 Safety Net System and Sup En cours d'exam 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-05-1 0 bénéficiaires du cycle 3 de IDA / D2980 A posteriori Individuel Open 10,400.00 0.00 2020-06-30 porting Project Managemen en 5 5 5 0 8 s TMO du Projet Filets Sociau t x dans la commune de Bétar é Oya , département du Lom et Djérem, région de l'Est CM-UGP-PFS-172114-CS-IND Laying the Foundations of a En cours d'exécu 2020-10-2 2020-07-1 2020-12-1 2020-08-0 2020-09-1 2021-09-1 V / Recrutement d'un Assista IDA / 62230 Safety Net System and Sup A posteriori Individuel Open 14,400.00 0.00 2020-05-25 tion 8 6 7 6 0 0 nt SPM porting Project Managemen t CM-UGP-PFS-172210-CS-IND Laying the Foundations of a V / Recrutement d'un consul Safety Net System and Sup En cours d'exécu 2020-06-2 2020-08-1 2020-09-0 2020-10-0 2021-10-0 tant pour la traduction des d IDA / 62230 A posteriori Individuel Open 41,122.00 0.00 2020-06-22 porting Project Managemen tion 9 3 3 8 8 ocuments du Projet Filets So t ciaux en Anglais/ Français CM-UGP-PFS-141752-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 100 Safety Net System and Sup En cours d'exécu 2019-10-1 2020-08-2 2020-09-1 2020-10-2 2021-05-1 0 bénéficiaires de la Phase 3 IDA / D2980 A posteriori Individuel Open 7,560.00 0.00 2020-06-30 porting Project Managemen tion 5 5 5 0 8 des TMU du Projet Filets Soci t aux dans la commune de Me iganga, département du Mb éré, région de l'Adamaoua CM-UGP-PFS-176264-CS-IND V / Recrutement par Entent e Directe d'un Consultant po Laying the Foundations of a ur le ciblage des 2000 bénéfi Safety Net System and Sup 2020-06-3 2020-06-2 2020-07-2 2020-07-1 2020-07-2 2020-08-1 2020-08-2 2021-02-1 IDA / D2980 A posteriori Individuel Direct 10,400.00 7,273.30 Signé 2020-06-10 ciaires du cycle 3 des TMO d porting Project Managemen 0 0 7 1 9 5 6 1 u Projet Filets Sociaux dans l t a commune de Meiganga , d épartement du Mbéré, Régio n de l'Adamaoua CM-UGP-PFS-141174-CS-IND V / Recrutement d'un Opéra Laying the Foundations of a teur de Terrain dans la Com Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-10-2 mune de Bamenda II, départ IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé 2020-06-30 porting Project Managemen 5 5 0 0 ement de MEZAM, région du t Nord-Ouest pour la phase 3 des Transferts Monétaires d' Urgence CM-UGP-PFS-141763-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 500 Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-05-1 bénéficiaires de la Phase 3 d IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Annulé 2020-06-30 porting Project Managemen 5 5 0 8 es TMU du Projet Filets Socia t ux dans la commune de Ba menda II , département de l a Mezam, région du Nord-Ou est CM-UGP-PFS-141771-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 500 Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-05-1 bénéficiaires de la Phase 3 d IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Annulé 2020-06-30 porting Project Managemen 5 5 0 8 es TMU du Projet Filets Socia t ux dans la commune de Lim bé III, département du Fako, région du Sud-Ouest CM-UGP-PFS-141765-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 100 Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-05-1 0 bénéficiaires de la Phase 3 IDA / 62230 A posteriori Individuel Open 7,560.00 0.00 Annulé 2020-06-30 porting Project Managemen 5 5 0 8 des TMU du Projet Filets Soci t aux dans la commune de Ba menda III , département de l a Mezam, région du Nord-Ou est CM-UGP-PFS-141178-CS-IND V / Recrutement d'un Opéra Laying the Foundations of a teur de Terrain dans la Com Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-10-2 IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé 2020-06-30 mune de Limbé I, départeme porting Project Managemen 5 5 0 0 nt de Fako, région du Sud-O t uest pour la phase 3 des Tra nsferts Monétaires d'Urgenc e CM-UGP-PFS-141179-CS-IND V / Recrutement d'un Opéra Laying the Foundations of a teur de Terrain dans la Com Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-10-2 IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé 2020-06-30 mune de Limbé II, départem porting Project Managemen 5 5 0 0 ent de Fako, région du Sud- t Ouest pour la phase 3 des Tr ansferts Monétaires d'Urgen ce CM-UGP-PFS-141769-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 500 Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-05-1 bénéficiaires de la Phase 3 d IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Annulé 2020-06-30 porting Project Managemen 5 5 0 8 es TMU du Projet Filets Socia t ux dans la commune de Lim bé II, département du Fako, région du Sud-Ouest CM-UGP-PFS-141197-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 500 Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-05-1 bénéficiaires de la Phase 3 d IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Annulé 2020-06-30 porting Project Managemen 5 5 0 8 es TMU du Projet Filets Socia t ux dans la commune de Ba menda I, département de la Mezam, région du Nord-Oue st CM-UGP-PFS-141173-CS-IND V / Recrutement d'un Opéra Laying the Foundations of a teur de Terrain dans la Com Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-10-2 mune de Bamenda I, départ IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé 2020-06-30 porting Project Managemen 5 5 0 0 ement de MEZAM, région du t Nord-Ouest pour la phase 3 des Transferts Monétaires d' Urgence CM-UGP-PFS-141180-CS-IND V / Recrutement d'un Opéra Laying the Foundations of a teur de Terrain dans la Com Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-10-2 IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé 2020-06-30 mune de Limbé III, départem porting Project Managemen 5 5 0 0 ent de Fako, région du Sud- t Ouest pour la phase 3 des Tr ansferts Monétaires d'Urgen ce CM-UGP-PFS-141176-CS-IND V / Recrutement d'un Opéra Laying the Foundations of a teur de Terrain dans la Com Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-10-2 mune de Bamenda III, dépar IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 Annulé 2020-06-30 porting Project Managemen 5 5 0 0 tement de MEZAM, région d t u Nord-Ouest pour la phase 3 des Transferts Monétaires d'Urgence CM-UGP-PFS-141767-CS-IND V / Recrutement d'un Consul Laying the Foundations of a tant pour le ciblage des 500 Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2021-05-1 bénéficiaires de la Phase 3 d IDA / 62230 A posteriori Individuel Open 4,920.00 0.00 Annulé 2020-06-30 porting Project Managemen 5 5 0 8 es TMU du Projet Filets Socia t ux dans la commune de Lim bé I , département du Fako, région du Sud-Ouest CM-UGP-PFS-172022-CS-CD Cash Transfer Program with S / Convention avec l’INS po Sélection de cons Accompanying Measures to 2020-08-1 2020-09-2 2020-08-2 2020-11-1 2020-09-2 2021-05-1 ur l’enquête PMT du Cycle 3 IDA / 62230 A posteriori ultants par enten Direct 937,708.53 828,613.11 Signé 2020-09-15 Boost Household Productivit 9 7 6 1 9 0 et du Cycle G1 des transfer te directe y ts Monétaires Ordinaires du Projet Filets Sociaux; Page 10 CM-UGP-PFS-200965-CS-IND Laying the Foundations of a En cours d'exécu 2020-10-1 2021-02-0 2021-02-1 2021-03-0 2023-03-0 V / Recrutement d'un Compt IDA / 62230 Safety Net System and Sup A posteriori Individuel Open 63,983.20 0.00 2020-11-30 tion 9 6 1 5 5 able pour le Projet Filets Soci porting Project Managemen aux t CM-UGP-PFS-172276-CS-IND Laying the Foundations of a V / Consultant pour la conce Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2020-11-1 IDA / 62230 A posteriori Individuel Limited 3,000.00 0.00 Annulé 2020-08-20 ption d'une affiche de com porting Project Managemen 5 5 0 9 munication et de sensibilisat t ion sur le MGP CM-UGP-PFS-141118-CS-IND Laying the Foundations of a V / Recrutement de la Secrét Safety Net System and Sup 2021-04-0 2021-03-1 2021-04-0 2021-05-1 2023-05-1 IDA / 62230 A posteriori Individuel Open 17,203.00 0.00 Annulé 2021-01-20 aire de l'antenne régionale d porting Project Managemen 4 7 7 2 2 u Sud-Ouest du Projet Filets t Sociaux CM-UGP-PFS-141133-CS-IND Laying the Foundations of a V / Recrutement de la Secrét Safety Net System and Sup En cours d'exécu 2021-04-0 2021-03-1 2021-04-0 2021-05-1 2023-05-1 IDA / D2980 A posteriori Individuel Open 17,203.00 0.00 2021-01-20 aire de l'antenne régionale d porting Project Managemen tion 4 7 7 2 2 e l'Adamaoua du Projet Filet t s Sociaux CM-UGP-PFS-141134-CS-IND Laying the Foundations of a V / Recrutement du Chauffe Safety Net System and Sup En cours d'exécu 2021-01-2 2021-03-1 2021-04-0 2021-05-1 2023-05-1 IDA / D2980 A posteriori Individuel Open 11,612.00 0.00 2021-01-20 ur de l'antenne régionale de porting Project Managemen tion 9 7 7 2 2 l'Adamaoua du Projet Filets t Sociaux CM-UGP-PFS-141124-CS-IND Laying the Foundations of a V / Recrutement de la Secrét Safety Net System and Sup En cours d'exécu 2021-04-0 2021-03-1 2021-04-0 2021-05-1 2023-05-1 IDA / 62230 A posteriori Individuel Open 17,203.00 0.00 2021-01-20 aire de l'antenne régionale S porting Project Managemen tion 4 7 7 2 2 ud du Projet Filets Sociaux t CM-UGP-PFS-141129-CS-IND Laying the Foundations of a V / Recrutement du Chauffe Safety Net System and Sup En cours d'exécu 2021-01-2 2021-03-1 2021-04-0 2021-05-1 2023-05-1 IDA / 62230 A posteriori Individuel Open 11,612.00 0.00 2021-01-20 ur de l'antenne régionale Su porting Project Managemen tion 9 7 7 2 2 d du Projet Filets Sociaux t CM-UGP-PFS-141131-CS-IND Laying the Foundations of a V / Recrutement du Chauffe Safety Net System and Sup En cours d'exécu 2021-01-2 2021-03-1 2021-04-0 2021-05-1 2023-05-1 IDA / D2980 A posteriori Individuel Open 11,612.00 0.00 2021-01-20 ur de l'antenne régionale de porting Project Managemen tion 9 7 7 2 2 l'Est du Projet Filets Sociaux t CM-UGP-PFS-141123-CS-IND Laying the Foundations of a V / Recrutement du Chauffe Safety Net System and Sup 2021-03-1 2021-04-0 2021-05-1 2023-05-1 IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 Annulé 2021-01-20 ur de l'antenne régionale du porting Project Managemen 7 7 2 2 Sud-Ouest du Projet Filets So t ciaux CM-UGP-PFS-172280-CS-IND Laying the Foundations of a V / Consultant pour la produ Safety Net System and Sup 2021-02-1 2021-03-0 2021-04-0 2021-10-0 IDA / 62230 A posteriori Individuel Open 30,000.00 0.00 Annulé 2020-12-21 ction des séries radiophoniq porting Project Managemen 1 4 8 5 ues pour la prévention des V t BG CM-UGP-PFS-203028-CS-IND Cash Transfer Program with V / recrutement d’un consult Accompanying Measures to En cours d'exécu 2020-11-3 2020-12-0 2020-12-0 2020-12-2 2021-01-3 2021-02-1 ant individuel chargé de trad IDA / 62230 A posteriori Individuel Limited 3,000.00 0.00 2020-11-30 Boost Household Productivit tion 0 5 7 6 0 4 uire en images le contrat mo y ral du Projet Filets Sociaux CM-UGP-PFS-141130-CS-IND Laying the Foundations of a V / Recrutement de la Secrét Safety Net System and Sup En cours d'exécu 2021-04-0 2021-03-1 2021-04-0 2021-05-1 2023-05-1 IDA / D2980 A posteriori Individuel Open 17,203.00 0.00 2021-01-20 aire de l'antenne régionale d porting Project Managemen tion 4 7 7 2 2 e l'Est du Projet Filets Sociau t x CM-UGP-PFS-187235-CS-IND Laying the Foundations of a V / Recrutement du chauffeu Safety Net System and Sup 2021-01-2 2021-03-1 2021-04-0 2021-05-1 2023-05-1 IDA / 62230 A posteriori Individuel Open 11,612.00 0.00 Annulé 2021-01-20 r de l'antenne régionale du S porting Project Managemen 9 7 7 2 2 ud ouest du Projet Filets Soci t aux CM-UGP-PFS-172253-CS-IND V / Recrutement d’un Consu Laying the Foundations of a ltant pour une évaluation so Safety Net System and Sup En cours d'exam 2020-11-3 2020-12-0 2020-12-2 2021-01-3 2021-07-2 ciale et une consultation des IDA / 62230 A posteriori Individuel Limited 10,950.00 0.00 2020-11-30 porting Project Managemen en 0 5 6 0 9 populations '4B' en vue de l' t élaboration d'un Plan d'actio n Peuple Autochtone (PPA) (I DA National) CM-UGP-PFS-203162-CS-CD Laying the Foundations of a Sélection de cons En attente d'exé 2020-07-2 2020-09-2 2022-09-2 S / Spécialiste en Passation IDA / 62230 Safety Net System and Sup A posteriori ultants par enten Direct 90,541.00 0.00 2020-07-15 cution 5 8 8 des Marchés porting Project Managemen te directe t CM-UGP-PFS-203164-CS-CD Laying the Foundations of a Sélection de cons 2020-09-0 2020-11-0 2022-11-0 S / Responsable Régional du IDA / 62230 Safety Net System and Sup A posteriori ultants par enten Direct 39,787.00 0.00 Annulé 2020-08-26 5 9 9 Projet Filets Sociaux dans le porting Project Managemen te directe Nord-Ouest t Laying the Foundations of a Sélection de cons CM-UGP-PFS-203161-CS-CD En cours d'exécu 2022-02-2 2020-09-2 2020-12-0 2022-12-0 IDA / 62230 Safety Net System and Sup A posteriori ultants par enten Direct 64,890.00 0.00 2020-09-18 S / Auditeur Interne tion 4 8 2 2 porting Project Managemen te directe t CM-UGP-PFS-205157-CS-IND Cash Transfer Program with V / Recrutement du consulta Accompanying Measures to 2021-01-0 2021-01-2 2021-03-0 2021-05-3 nt pour la production de 5 sé IDA / D2980 A posteriori Individuel Limited 14,447.00 0.00 Annulé 2020-12-30 Boost Household Productivit 4 5 1 0 ries radiophoniques en 5 lan y gues (français, arabe, Fufuld é, Arabe et Koto) CM-UGP-PFS-205176-CS-IND Cash Transfer Program with V / Recrutement du consulta Accompanying Measures to En cours d'exam 2020-12-0 2021-01-0 2021-01-2 2021-03-0 2021-03-3 IDA / D2980 A posteriori Individuel Limited 8,127.00 0.00 2020-12-30 nt pour la production des im Boost Household Productivit en 8 4 5 1 1 ages pour la formation des c y ouples CM-UGP-PFS-205281-CS-IND V / Recrutement de l'opérate Laying the Foundations of a ur de terrain N°1 de la Com Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-05-3 2021-07-0 2023-07-0 IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2021-03-15 mune de Ngaoui départeme porting Project Managemen tion 5 0 1 5 5 nt du Mbere région de l'Ada t maoua pour le cycle 4 des Tr ansferts Monétaires ordinair es CM-UGP-PFS-205285-CS-IND V / Recrutement de l'opérate Laying the Foundations of a ur de Terrain N°2 de la Com Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-05-3 2021-07-0 2023-07-0 mune de Ngaoui, départeme IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2021-03-15 porting Project Managemen tion 5 0 1 5 5 nt du Mbéré, Région de l'Ada t maoua dans le cadre du cycl e 4 des Transferts Monétaire s Ordinaires du Projet filets S ociaux CM-UGP-PFS-205286-CS-IND V / Recrutement de l'opérate Laying the Foundations of a ur de Terrain N°2 de la Com Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-05-3 2021-07-0 2023-07-0 mune de Njohong, départem IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2021-03-15 porting Project Managemen tion 5 0 1 5 5 ent du Mbéré, Région de l'Ad t amaoua dans le cadre du cy cle 4 des Transferts Monétai res Ordinaires du Projet filet s Sociaux CM-UGP-PFS-205287-CS-IND V / Recrutement de l'opérate Laying the Foundations of a ur de Terrain N°1 de la Com Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-05-3 2021-07-0 2023-07-0 mune de Njohong, départem IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2021-03-15 porting Project Managemen tion 5 0 1 5 5 ent du Mbéré, Région de l'Ad t amaoua dans le cadre du cy cle 4 des Transferts Monétai res Ordinaires du Projet filet s Sociaux CM-UGP-PFS-205288-CS-IND V / Recrutement de l'Opérat eur de Terrain N°1 de la Co Laying the Foundations of a mmune de Mandjou, Départ Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-05-3 2021-06-2 2021-07-0 2021-07-0 2023-07-0 IDA / D2980 A posteriori Individuel Open 12,960.00 7,420.88 Signé 2021-03-15 ement du Lom et Djerem, Ré porting Project Managemen 5 0 5 1 1 5 5 5 gion de l'Est dans le cadre d t u cycle 4 des Transferts Mon étaires Ordinaires du Projet f ilets Sociaux CM-UGP-PFS-205290-CS-IND V / Recrutement de l'Opérat eur de Terrain N°2 de la Co Laying the Foundations of a mmune de Mandjou, Départ Safety Net System and Sup En cours d'exécu 2021-05-1 2021-05-3 2021-07-0 2023-07-0 IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2021-03-15 ement du Lom et Djerem, Ré porting Project Managemen tion 0 1 5 5 gion de l'Est dans le cadre d t u cycle 4 des Transferts Mon étaires Ordinaires du Projet f ilets Sociaux CM-UGP-PFS-205291-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain N°1 de la Co Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-05-3 2021-06-2 2021-07-0 2021-07-0 2023-07-0 mmune de Kentzou, Départe IDA / D2980 A posteriori Individuel Open 12,960.00 7,705.38 Signé 2021-03-15 porting Project Managemen 5 0 5 1 1 5 5 5 ment de la Kadey, Région de t l'Est dans le cadre du cycle 4 des Transferts Monétaires Ordinaires du Projet Filets So ciaux CM-UGP-PFS-205292-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain N°2 de la Co Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-05-3 2021-06-2 2021-07-0 2021-07-0 2023-07-0 mmune de Kentzou, Départe IDA / D2980 A posteriori Individuel Open 12,960.00 7,705.38 Signé 2021-03-15 porting Project Managemen 5 0 5 1 1 5 5 5 ment de la Kadey, Région de t l'Est dans le cadre du cycle 4 des Transferts Monétaires Ordinaires du Projet Filets So ciaux CM-UGP-PFS-205294-CS-IND V / Recrutement de l'Opérat eur de Terrain N°1 de la Co Laying the Foundations of a mmune de Makary Départe Safety Net System and Sup 2021-02-0 2021-05-0 2021-06-1 2021-05-2 2021-06-2 2021-06-2 2021-07-0 2023-06-2 IDA / D2980 A posteriori Individuel Open 12,960.00 7,795.05 Signé 2021-03-15 ment du Logone et Chari, Ré porting Project Managemen 5 3 6 4 2 8 5 8 gion de l'Extrême Nord dans t le cadre du cycle 4 des Tran sferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-205297-CS-IND V / Recrutement de l'Opérat eur de Terrain N°2 de la Co Laying the Foundations of a mmune de Makary Départe Safety Net System and Sup 2021-02-0 2021-05-0 2021-06-1 2021-05-2 2021-06-2 2021-06-2 2021-07-0 2023-06-2 IDA / D2980 A posteriori Individuel Open 12,960.00 7,795.05 Signé 2021-03-15 ment du Logone et Chari, Ré porting Project Managemen 5 3 6 4 2 8 5 8 gion de l'Extrême Nord dans t le cadre du cycle 4 des Tran sferts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-205298-CS-IND V / Recrutement de l'Opérat eur de Terrain N°1 de la Co Laying the Foundations of a mmune de Tokomberé Dépa Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-0 2021-05-2 2021-06-2 2023-06-2 IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2021-03-15 rtement du Mayo Sava, Régi porting Project Managemen tion 5 3 4 8 8 on de l'Extrême Nord dans le t cadre du cycle 4 des Transfe rts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-205301-CS-IND V / Recrutement de l'Opérat eur de Terrain N°2 de la Co Laying the Foundations of a mmune de Tokomberé Dépa Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-0 2021-05-2 2021-06-2 2023-06-2 IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2021-03-15 rtement du Mayo Sava, Régi porting Project Managemen tion 5 3 4 8 8 on de l'Extrême Nord dans le t cadre du cycle 4 des Transfe rts Monétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-141107-CS-IND Laying the Foundations of a V / Recrutement d'un Respo Safety Net System and Sup 2020-08-2 2020-09-1 2020-10-2 2022-10-2 nsable Régional dans la Régi IDA / 62230 A posteriori Individuel Open 38,400.00 0.00 Annulé 2020-06-30 porting Project Managemen 5 5 0 0 on du SUD-OUEST pour la c t ycle 3 des Transferts Monéta ires ordinaires CM-UGP-PFS-212970-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2023-07-1 ne de Mbé Département de l IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 a VINA, Région de l'Adamao t ua dans le cadre du cycle 4 des Transferts Monétaires Or dinaires du Projet Filets Soci aux CM-UGP-PFS-212971-CS-IND V / Recrutement de l'Opérat eur de Terrain de la Commu Laying the Foundations of a ne de Bankim Département Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2023-07-1 IDA / 62230 A posteriori Individuel Open 12,960.00 7,523.13 Signé 2021-03-31 du Mayo- Banyo, Région de l porting Project Managemen 5 9 6 9 2 4 5 4 'Adamaoua dans le cadre du t cycle 4 des Transferts Monét aires Ordinaires du Projet Fil ets Sociaux Page 11 CM-UGP-PFS-212972-CS-IND V / Recrutement de l'Opérat eur de Terrain de la Commu Laying the Foundations of a ne de Mayo Darlé Départem Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2023-07-1 IDA / 62230 A posteriori Individuel Open 12,960.00 7,555.74 Signé 2021-03-31 ent du Mayo- Banyo, Région porting Project Managemen 5 9 6 9 2 4 5 4 de l'Adamaoua dans le cadre t du cycle 4 des Transferts Mo nétaires Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212973-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2023-07-1 ne de Mindif Département d IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 u Mayo- Kani, Région de l'Ex t trême Nord dans le cadre du cycle 4 des Transferts Monét aires Ordinaires du Projet Fil ets Sociaux CM-UGP-PFS-212974-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2023-07-1 ne de Djoum Département d IDA / 62230 A posteriori Individuel Open 12,960.00 7,705.38 Signé 2021-03-31 porting Project Managemen 5 9 6 9 2 4 5 4 u Dja et Lobo Région du Sud t dans le cadre du cycle 4 des Transferts Monétaires Ordin aires du Projet Filets Sociaux CM-UGP-PFS-212976-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2023-07-1 ne de Meyomessala Départe IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 ment du Dja et Lobo, Région t du Sud dans le cadre du cycl e 4 des Transferts Monétaire s Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212977-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2023-07-1 ne de Douala 2ème Ville de IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 Douala dans le cadre du cycl t e 4 des Transferts Monétaire s Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212978-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2023-07-1 IDA / 62230 A posteriori Individuel Open 12,960.00 0.00 2021-03-31 ne de Yaoundé 7 Ville de Ya porting Project Managemen tion 5 9 9 4 4 oundé dans le cadre du cycl t e 4 des Transferts Monétaire s Ordinaires du Projet Filets Sociaux CM-UGP-PFS-212979-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2023-07-1 ne de Mora, Département du IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 Mayo Sava, Région de l'Extr t ême Nord dans le cadre du c ycle 5 des Transferts Monéta ires Ordinaires du Projet File ts Sociaux CM-UGP-PFS-212980-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2023-07-1 ne de Ouli, Département de l IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 a Kadey, Région de l'Est dan t s le cadre du cycle 5 des Tra nsferts Monétaires Ordinaire s du Projet Filets Sociaux CM-UGP-PFS-212981-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2023-07-1 ne de Batouri, Département IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 de la Kadey, Région de l'Est t dans le cadre du cycle 5 des Transferts Monétaires Ordin aires du Projet Filets Sociaux CM-UGP-PFS-212982-CS-IND V / Recrutement de l'Opérat eur de Terrain de la Commu Laying the Foundations of a ne de Gari -Gombo, Départe Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2023-07-1 IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2021-03-31 ment de la Boumba et Ngok porting Project Managemen tion 5 9 9 4 4 o, Région de l'Est dans le ca t dre du cycle 5 des Transfert s Monétaires Ordinaires du P rojet Filets Sociaux CM-UGP-PFS-212983-CS-IND V / Recrutement de l'Opérat eur de Terrain de la Commu Laying the Foundations of a ne de Salapoumbe, Départe Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2023-07-1 IDA / D2980 A posteriori Individuel Open 12,960.00 0.00 2021-03-31 ment de la Boumba et Ngok porting Project Managemen tion 5 9 9 4 4 o, Région de l'Est dans le ca t dre du cycle 5 des Transfert s Monétaires Ordinaires du P rojet Filets Sociaux CM-UGP-PFS-213101-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2022-07-1 IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2021-03-31 ne de Douala IV, Ville de Do porting Project Managemen tion 5 9 9 4 4 uala dans le cadre de la pha t se 4 des Transferts Monétair es d'urgence du Projet Filets Sociaux CM-UGP-PFS-213102-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2022-07-1 ne de Yaoundé III, Ville de Y IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 aoundé dans le cadre de la p t hase 4 des Transferts Monét aires d'urgence du Projet Fil ets Sociaux CM-UGP-PFS-213103-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2022-07-1 ne de Babadjou, Départeme IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 nt du Bamboutos, Région de t l'Ouest dans le cadre de la p hase 4 des Transferts Monét aires d'urgence du Projet Fil ets Sociaux CM-UGP-PFS-213104-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2022-07-1 ne de Batcham, Départeme IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 nt du Bamboutos, Région de t l'Ouest dans le cadre de la p hase 4 des Transferts Monét aires d'urgence du Projet Fil ets Sociaux CM-UGP-PFS-213105-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2022-07-1 ne de Galim, Département IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 du Bamboutos, Région de l' t Ouest dans le cadre de la ph ase 4 des Transferts Monétai res d'urgence du Projet Filet s Sociaux CM-UGP-PFS-213106-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2022-07-1 ne de foumban, Départeme IDA / 62230 A posteriori Individuel Open 6,480.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 nt du Noun, Région de l'Oue t st dans le cadre de la phase 4 des Transferts Monétaires d'urgence du Projet Filets So ciaux CM-UGP-PFS-213107-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2022-07-1 ne de Touboro , Départeme IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 nt du Mayo Rey, Région du t Nord dans le cadre de la pha se 4 des Transferts Monétair es d'urgence du Projet Filets Sociaux CM-UGP-PFS-213108-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2022-07-1 ne de kette, Département d IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 4 e la Kadey, Région de l'Est t dans le cadre de la phase 4 des Transferts Monétaires d' urgence du Projet Filets Soci aux CM-UGP-PFS-213110-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-0 2021-06-0 2021-06-0 2021-07-1 2021-06-2 2022-07-1 ne de NGOURA, Départeme IDA / D2980 A posteriori Individuel Open 6,480.00 5,196.70 Signé 2021-03-31 porting Project Managemen 5 9 1 9 4 4 1 4 nt du Lom et Djerem, Régio t n de l'Est dans le cadre de la phase 4 des Transferts Moné taires d'urgence du Projet Fil ets Sociaux CM-UGP-PFS-213111-CS-IND V / Recrutement de l'Opérat Laying the Foundations of a eur de Terrain de la Commu Safety Net System and Sup En cours d'exécu 2021-05-1 2021-06-0 2021-07-1 2022-07-1 ne de Garoua , Départemen IDA / D2980 A posteriori Individuel Open 6,480.00 0.00 2021-03-31 porting Project Managemen tion 9 9 4 4 t du Lom et Djerem, Région t de l'Est dans le cadre de la p hase 4 des Transferts Monét aires d'urgence du Projet Fil ets Sociaux CM-UGP-PFS-213113-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 du cycle 4 des Transferts Mo IDA / D2980 A posteriori Individuel Open 10,400.00 6,722.39 Signé 2021-03-31 porting Project Managemen 5 9 4 9 1 4 5 9 nétaires Ordinaires du Projet t Filets Sociaux dans la Com mune de Ngaoui départeme nt du Mbere région de l'Ada maoua (2000 ménages béné ficiaires) CM-UGP-PFS-213114-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 du cycle 4 des Transferts Mo IDA / D2980 A posteriori Individuel Open 10,400.00 5,443.85 Signé 2021-03-31 porting Project Managemen 5 9 4 9 1 4 5 9 nétaires Ordinaires du Projet t Filets Sociaux dans la Com mune de Njohong départem ent du Mbere région de l'Ada maoua (2000 ménages béné ficiaires) CM-UGP-PFS-213115-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 du cycle 4 des Transferts Mo IDA / 62230 A posteriori Individuel Open 6,300.00 3,805.13 Signé 2021-03-31 porting Project Managemen 5 9 5 9 2 4 5 9 nétaires Ordinaires du Projet t Filets Sociaux dans la Com mune de Mbe département de la Vina, région de l'Adam aoua (1000 ménages bénéfi ciaires) CM-UGP-PFS-213116-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 du cycle 4 des Transferts Mo IDA / 62230 A posteriori Individuel Open 6,320.00 3,805.13 Signé 2021-03-31 porting Project Managemen 5 9 5 9 2 4 5 9 nétaires Ordinaires du Projet t dans la Commune de Banki m, département du Mayo Ba nyo région de l'Adamaoua (1 000 ménages bénéficiaires) CM-UGP-PFS-213117-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 du cycle 4 des Transferts Mo IDA / 62230 A posteriori Individuel Open 6,320.00 3,805.13 Signé 2021-03-31 porting Project Managemen 5 9 5 9 2 4 5 9 nétaires Ordinaires du Projet t dans la Commune de Mayo Darle, département du Mayo Banyo région de l'Adamaoua (1000 ménages bénéficiaires ) Page 12 CM-UGP-PFS-213118-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 du cycle 4 des Transferts Mo IDA / D2980 A posteriori Individuel Open 10,400.00 6,745.03 Signé 2021-03-31 porting Project Managemen 5 9 5 9 2 4 5 9 nétaires Ordinaires du Projet t dans la Commune de Manjo u, département du Lom et Dj erem région de l'Est (2000 ménages bénéficiaires) CM-UGP-PFS-213119-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 du cycle 4 des Transferts Mo IDA / D2980 A posteriori Individuel Open 10,400.00 6,722.39 Signé 2021-03-31 porting Project Managemen 5 9 5 9 2 4 5 9 nétaires Ordinaires du Projet t dans la Commune de Kenzo u, département de la Kadey région de l'Est (2000 ménag es bénéficiaires) CM-UGP-PFS-213120-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 du cycle 4 des Transferts Mo IDA / D2980 A posteriori Individuel Open 7,850.00 3,849.41 Signé 2021-03-31 porting Project Managemen 5 9 4 9 1 4 9 9 nétaires Ordinaires du Projet t dans la Commune de Makar y, département du Logone e t Chari région de l'Extrême N ord (1500 ménages bénéfici aires) CM-UGP-PFS-213121-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2022-02-0 du cycle 4 des Transferts Mo IDA / 62230 A posteriori Individuel Open 10,400.00 0.00 2021-03-31 porting Project Managemen tion 5 9 5 9 2 4 9 nétaires Ordinaires du Projet t dans la Commune de Toko mbere, département du May o Sava région de l'Extrême Nord (2000 ménages bénéfic iaires) CM-UGP-PFS-213122-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-07-2 2021-06-0 2021-08-3 2021-07-1 2022-02-0 du cycle 4 des Transferts Mo IDA / 62230 A posteriori Individuel Open 6,320.00 0.00 2021-03-31 porting Project Managemen tion 5 9 6 9 0 4 9 nétaires Ordinaires du Projet t dans la Commune de Mindif , département du Mayo Kani région de l'Extrême Nord (10 00 ménages bénéficiaires) CM-UGP-PFS-213123-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 du cycle 4 des Transferts Mo IDA / 62230 A posteriori Individuel Open 6,320.00 3,805.13 Signé 2021-03-31 porting Project Managemen 5 9 8 9 2 4 5 9 nétaires Ordinaires du Projet t dans la Commune de Djoum , département du Dja et Lob o région du Sud (1000 ména ges bénéficiaires) CM-UGP-PFS-213124-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-07-2 2021-06-0 2021-07-3 2021-07-1 2021-07-3 2022-02-0 du cycle 4 des Transferts Mo IDA / 62230 A posteriori Individuel Open 6,320.00 3,849.41 Signé 2021-03-31 porting Project Managemen 5 9 8 9 0 4 0 9 nétaires Ordinaires du Projet t dans la Commune de Meyo Messala, département du Dj a et Lobo région du Sud (10 00 ménages bénéficiaires) CM-UGP-PFS-213125-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 IDA / 62230 A posteriori Individuel Open 6,320.00 3,849.41 Signé 2021-03-31 du cycle 4 des Transferts Mo porting Project Managemen 5 9 8 9 2 4 5 9 nétaires Ordinaires du Projet t dans la Commune de Doual a 2ème, Ville de Douala (100 0 ménages bénéficiaires) CM-UGP-PFS-213126-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-07-1 2021-06-0 2021-07-2 2021-07-1 2021-07-2 2022-02-0 IDA / 62230 A posteriori Individuel Open 6,320.00 3,715.13 Signé 2021-03-31 du cycle 4 des Transferts Mo porting Project Managemen 5 9 9 9 1 4 1 9 nétaires Ordinaires du Projet t dans la Commune de Yaoun dé 7, Ville de Yaoundé (1000 ménages bénéficiaires) CM-UGP-PFS-213127-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 du cycle 5 des Transferts Mo IDA / D2980 A posteriori Individuel Open 6,320.00 8,179.99 Signé 2021-03-31 porting Project Managemen 5 9 5 9 1 4 9 9 nétaires Ordinaires du Projet t dans la Commune de Mora , Département du Mayo Sava Région de l'Extrême Nord (1 000 ménages bénéficiaires) CM-UGP-PFS-213129-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2022-02-0 IDA / D2980 A posteriori Individuel Open 6,320.00 0.00 2021-03-31 du cycle 5 des Transferts Mo porting Project Managemen tion 5 9 9 4 9 nétaires Ordinaires du Projet t dans la Commune de Ouli, Département de la Kadey de l'Est (1000 ménages bénéfi ciaires) CM-UGP-PFS-213135-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 IDA / D2980 A posteriori Individuel Open 6,320.00 3,870.43 Signé 2021-03-31 du cycle 5 des Transferts Mo porting Project Managemen 5 9 7 9 1 4 9 9 nétaires Ordinaires du Projet t dans la Commune de Batou ri, Département de la Kadey de l'Est (1000 ménages bén éficiaires) CM-UGP-PFS-213136-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2022-02-0 du cycle 5 des Transferts Mo IDA / D2980 A posteriori Individuel Open 6,320.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 9 nétaires Ordinaires du Projet t dans la Commune de Gari G ombo, Département de la Bo umba et Ngoko, Région de l' Est (1000 ménages bénéfici aires) CM-UGP-PFS-213137-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-07-1 2022-02-0 du cycle 5 des Transferts Mo IDA / D2980 A posteriori Individuel Open 6,320.00 0.00 2021-03-31 porting Project Managemen tion 5 9 9 4 9 nétaires Ordinaires du Projet t dans la Commune de Salap oumbe, Département de la B oumba et Ngoko, Région de l'Est (1000 ménages bénéfi ciaires) CM-UGP-PFS-213138-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-0 2021-06-0 2021-06-0 2021-07-1 2021-06-2 2022-02-0 de la phase 4 des Transferts IDA / D2980 A posteriori Individuel Open 7,560.00 5.68 Signé 2021-03-31 porting Project Managemen 5 9 1 9 7 4 2 9 Monétaires d'urgence du PF t S dans la Commune de Garo ua boulaï, Département du L om et Djerem, Région de l'E st (1000 ménages bénéficiai res) CM-UGP-PFS-213139-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-0 2021-06-0 2021-06-0 2021-07-1 2021-06-2 2022-02-0 de la phase 4 des Transferts IDA / D2980 A posteriori Individuel Open 7,560.00 5,542.81 Signé 2021-03-31 porting Project Managemen 5 9 1 9 4 4 1 9 Monétaires d'urgence du PF t S dans la Commune de Ngou ra, Département du Lom et Djerem, Région de l'Est (10 00 ménages bénéficiaires) CM-UGP-PFS-213140-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-0 2021-06-0 2021-06-0 2021-07-1 2021-06-2 2022-02-0 de la phase 4 des Transferts IDA / D2980 A posteriori Individuel Open 7,560.00 5,567.66 Signé 2021-03-31 porting Project Managemen 5 9 1 9 4 4 1 9 Monétaires d'urgence du Pro t jet dans la Commune de Ket te, Département de la Kadey , Région de l'Est (1000 mén ages bénéficiaires) CM-UGP-PFS-213142-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-0 2021-06-0 2021-06-0 2021-07-1 2021-06-2 2022-02-0 de la phase 4 des Transferts IDA / D2980 A posteriori Individuel Open 7,650.00 5,620.22 Signé 2021-03-31 porting Project Managemen 5 9 1 9 7 4 2 9 Monétaires d'urgence du Pro t jet dans la Commune de Tou boro, Département du Mayo Rey, Région du Nord (1000 ménages bénéficiaires) CM-UGP-PFS-213143-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup En cours d'exécu 2021-02-0 2021-05-1 2021-06-0 2021-06-0 2021-06-0 2021-07-1 2022-02-0 de la phase 4 des Transferts IDA / 62230 A posteriori Individuel Open 7,560.00 5,527.07 2021-03-31 porting Project Managemen tion 5 9 1 9 4 4 9 Monétaires d'urgence du Pro t jet dans la Commune de Fou mban, Département du Nou n, Région de l'Ouest (1000 ménages bénéficiaires) CM-UGP-PFS-213144-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 de la phase 4 des Transferts IDA / 62230 A posteriori Individuel Open 4,920.00 3,593.71 Signé 2021-03-31 porting Project Managemen 5 9 7 9 1 4 5 9 Monétaires d'urgence du Pro t jet dans la Commune de Gali m, Département du Bambou tos, Région de l'Ouest (500 ménages bénéficiaires) CM-UGP-PFS-213145-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 de la phase 4 des Transferts IDA / 62230 A posteriori Individuel Open 4,920.00 3,584.50 Signé 2021-03-31 porting Project Managemen 5 9 7 9 1 4 5 9 Monétaires d'urgence du Pro t jet dans la Commune de Bat cham, Département du Bam boutos, Région de l'Ouest (5 00 ménages bénéficiaires) CM-UGP-PFS-213146-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-1 2021-06-0 2021-06-2 2021-07-1 2021-07-0 2022-02-0 de la phase 4 des Transferts IDA / 62230 A posteriori Individuel Open 4,920.00 3,593.71 Signé 2021-03-31 porting Project Managemen 5 9 7 9 1 4 5 9 Monétaires d'urgence du Pro t jet dans la Commune de Bab adjou, Département du Bam boutos, Région de l'Ouest (5 00 ménages bénéficiaires) CM-UGP-PFS-213147-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-0 2021-06-0 2021-06-0 2021-07-1 2021-06-2 2022-02-0 IDA / 62230 A posteriori Individuel Open 7,560.00 5,535.12 Signé 2021-03-31 de la phase 4 des Transferts porting Project Managemen 5 9 1 9 4 4 1 9 Monétaires d'urgence du Pro t jet Filets Sociaux dans la Co mmune de Douala IV, Ville d e Douala (1000 ménages bé néficiaires) Page 13 CM-UGP-PFS-213148-CS-IND V / Consultant pour le ciblag e des villages et ménages p Laying the Foundations of a otentiellement bénéficiaires Safety Net System and Sup 2021-02-0 2021-05-1 2021-06-0 2021-06-0 2021-06-0 2021-07-1 2021-06-2 2022-02-0 IDA / 62230 A posteriori Individuel Open 7,560.00 5,635.54 Signé 2021-03-31 de la phase 4 des Transferts porting Project Managemen 5 9 1 9 4 4 1 9 Monétaires d'urgence du Pro t jet Filets Sociaux dans la Co mmune de Yaoundé III, Ville de Yaoundé (1000 ménages bénéficiaires) CM-UGP-PFS-203027-CS-IND Laying the Foundations of a V / Consultant pour la produ Safety Net System and Sup En cours d'exécu 2021-04-0 2021-04-2 2021-05-3 2021-11-2 IDA / 62230 A posteriori Individuel Limited 30,000.00 0.00 2021-03-31 ction des séries radiophoniq porting Project Managemen tion 5 6 1 7 ues pour la prévention des V t BG CM-UGP-PFS-217843-CS-IND Laying the Foundations of a V / Recrutement du chauffeu Safety Net System and Sup En cours d'exam 2021-05-2 2021-02-2 2021-03-2 2021-04-2 2023-04-2 IDA / 62230 A posteriori Individuel Limited 16,800.00 0.00 2021-02-22 r N° 3 de l'Unité de Gestion porting Project Managemen en 5 7 0 4 4 du Projet Filets Sociaux t CM-UGP-PFS-218220-CS-IND V / Recrutement du point foc Laying the Foundations of a al du département du Mbéré Safety Net System and Sup En cours d'exécu 2021-02-1 2021-04-2 2021-05-1 2021-06-2 2023-06-2 IDA / D2980 A posteriori Individuel Open 19,200.00 0.00 2021-03-02 , région de l'Adamaoua dan porting Project Managemen tion 7 7 8 2 2 s le cadre des Cycles 4 et 5 t des Transferts Monétaire Or dinaire CM-UGP-PFS-218223-CS-IND V / Recrutement du point foc Laying the Foundations of a al du département du Mayo Safety Net System and Sup 2021-02-1 2021-04-2 2021-06-1 2021-05-1 2021-06-2 2021-06-2 2021-07-0 2023-06-2 IDA / 62230 A posteriori Individuel Open 19,200.00 11,185.42 Signé 2021-03-02 Banyo, région de l'Adamaou porting Project Managemen 7 7 6 8 2 2 5 2 a dans le cadre des Cycles 4 t et 5 des Transferts Monétair e Ordinaire CM-UGP-PFS-218225-CS-IND V / Recrutement du point foc Laying the Foundations of a al du département de la Bou Safety Net System and Sup 2021-02-1 2021-04-2 2021-06-1 2021-05-1 2021-06-2 2021-06-2 2021-07-0 2023-06-2 IDA / D2980 A posteriori Individuel Open 19,200.00 11,100.38 Signé 2021-03-02 mba et Ngoko, région de l'Es porting Project Managemen 7 7 6 8 2 2 5 2 t dans le cadre des Cycles 4 t et 5 des Transferts Monétair e Ordinaire CM-UGP-PFS-218226-CS-IND Laying the Foundations of a V / Recrutement du point foc Safety Net System and Sup 2021-02-1 2021-04-2 2021-06-1 2021-05-1 2021-06-2 2021-06-2 2021-07-0 2023-06-2 al du département de la Kad IDA / D2980 A posteriori Individuel Open 19,200.00 11,100.38 Signé 2021-03-02 porting Project Managemen 7 7 5 8 1 2 5 2 ey, région de l'Est dans le ca t dre des Cycles 4 et 5 des Tr ansferts Monétaire Ordinaire CM-UGP-PFS-220028-CS-CD S / RECRUTEMENT DU CONS ULTANT CHARGE DE L'ENQU Cash Transfer Program with Sélection de cons ETE DE BASE POUR L'EVALU Accompanying Measures to En attente d'exé 2021-03-2 2021-05-2 2022-01-2 IDA / D2980 A posteriori ultants par enten Direct 499,337.00 0.00 2021-03-15 ATION D'IMPACT DES MESUR Boost Household Productivit cution 5 9 4 te directe ES D'ACCOMPAGNEMENT DU y PROJET FILETS SOCIAUX AUP RES DES POPULATIONS HOT ES ET DES REFUGIES AU CA MEROUN CM-UGP-PFS-227924-CS-IND Laying the Foundations of a En cours d'exécu 2021-04-2 2021-06-1 2021-07-0 2021-08-1 2022-08-1 V / Recrutement d'un assista IDA / 62230 Safety Net System and Sup A posteriori Individuel Open 9,600.00 0.00 2021-04-30 tion 3 8 9 3 3 nt comptable au Projet Filets porting Project Managemen Sociaux t CM-UGP-PFS-232625-CS-IND Laying the Foundations of a V / recrutement d'un technic Safety Net System and Sup En cours d'exam 2021-05-2 2021-06-3 2021-07-2 2021-08-2 2022-08-2 IDA / D2980 A posteriori Individuel Limited 1,920.00 0.00 2021-06-25 ien de surface pour l'antenn porting Project Managemen en 5 0 1 5 5 e régionale du projet de l'e t xtrême Nord CM-UGP-PFS-232631-CS-IND Laying the Foundations of a V / recrutement d'un Techni Safety Net System and Sup En cours d'exam 2021-05-2 2021-06-3 2021-07-2 2021-08-2 2022-08-2 IDA / D2980 A posteriori Individuel Limited 1,920.00 0.00 2021-06-25 cien de surface pour l'anten porting Project Managemen en 5 0 1 5 5 ne Régionale du projet du N t ord CM-UGP-PFS-232634-CS-IND Laying the Foundations of a V / recrutement d'un technic Safety Net System and Sup En cours d'exam 2021-05-2 2021-06-3 2021-07-2 2021-08-2 2022-08-2 IDA / D2980 A posteriori Individuel Limited 1,920.00 0.00 2021-06-25 ien de surface pour l'antenn porting Project Managemen en 5 0 1 5 5 e régionale du projet de l'E t st CM-UGP-PFS-232635-CS-IND Laying the Foundations of a V / recrutement d'un technic Safety Net System and Sup En cours d'exam 2021-05-2 2021-06-3 2021-07-2 2021-08-2 2022-08-2 IDA / D2980 A posteriori Individuel Limited 1,920.00 0.00 2021-06-25 ien de surface pour l'antenn porting Project Managemen en 5 0 1 5 5 e régionale du projet de l'A t damaoua CM-UGP-PFS-232636-CS-IND Laying the Foundations of a V / recrutement d'un technic Safety Net System and Sup En cours d'exam 2021-05-2 2021-06-3 2021-07-2 2021-08-2 2022-08-2 IDA / 62230 A posteriori Individuel Limited 1,920.00 0.00 2021-06-25 ien de surface pour l'antenn porting Project Managemen en 5 0 1 5 5 e régionale du projet du su t d CM-UGP-PFS-232637-CS-IND Laying the Foundations of a V / recrutement d'un deuxiè Safety Net System and Sup En cours d'exam 2021-06-2 2021-06-3 2021-07-2 2021-08-2 2022-08-2 IDA / 62230 A posteriori Individuel Limited 7,000.00 0.00 2021-06-25 me technicien de surface po porting Project Managemen en 5 0 1 5 5 ur l'Unité de Gestion du Proj t et CM-UGP-PFS-234703-CS-CD S / Convention de partenaria t avec l'Institut National de l Cash Transfer Program with a Statistique (INS) pour la ré Sélection de cons Accompanying Measures to En cours d'exécu 2021-06-0 2021-06-1 2021-06-0 2021-07-3 2022-03-2 alisation de l’enquête Proxy IDA / 62230 A priori ultants par enten Direct 1,200,000.00 0.00 2021-05-31 Boost Household Productivit tion 6 5 7 0 7 Means Test (PMT) dans les c te directe y ommunes bénéficiaires du p rogramme de transferts mon étaires ordinaires du cycle 4 et du cycle 5 du PFS CM-UGP-PFS-239536-CS-IND Laying the Foundations of a En cours d'exécu 2021-10-1 2021-08-1 2021-09-0 2021-10-1 2023-01-1 V / Recrutement d'un assista IDA / 62230 Safety Net System and Sup A posteriori Individuel Open 18,000.00 0.00 2021-06-30 tion 2 8 8 3 3 nt du Responsable Adminis porting Project Managemen tratif et Financier t CM-UGP-PFS-239633-CS-IND Laying the Foundations of a En cours d'exécu 2021-06-1 2021-07-1 2021-06-2 2021-07-3 2021-06-2 2021-09-0 2023-03-0 V / Recrutement d'un assista IDA / 62230 Safety Net System and Sup A posteriori Individuel Direct 22,857.00 0.00 2021-06-30 tion 8 0 8 1 9 4 8 nt au Spécialiste en Passatio porting Project Managemen n des Marchés t CM-UGP-PFS-249781-CS-IND V / Recrutement du consulta Laying the Foundations of a nt chargé de l'Elaboration du Safety Net System and Sup En cours d'exécu 2021-09-1 2021-10-0 2021-09-1 2021-10-2 2021-12-0 2022-01-3 Cadre de gestion environne IDA / 62230 A posteriori Individuel Limited 18,000.00 0.00 2021-09-29 porting Project Managemen tion 3 6 6 7 1 0 mentale et sociale (CGES), a t vec évaluation des risques d e sécurité, et les risques de Violence Basée sur le Genre (VBG) CM-UGP-PFS-249790-CS-IND Laying the Foundations of a V / Recrutement du consulta Safety Net System and Sup 2021-09-1 2021-10-0 2021-09-1 2021-10-2 2021-10-0 2021-12-0 2021-10-2 2022-01-3 2022-03-2 IDA / 62230 A posteriori Individuel Limited 9,030.00 7,570.82 Achevé 2021-09-29 nt chargé de l'Elaboration d porting Project Managemen 3 6 6 7 1 1 0 0 2 u Plan de Gestion de la Main t d’Œuvre (PGMO) CM-UGP-PFS-249794-CS-IND V / Recrutement d'un consul Laying the Foundations of a tant chargé de l'élaboration Safety Net System and Sup 2021-09-1 2021-10-0 2021-09-1 2021-10-2 2021-10-0 2021-12-0 2021-10-2 2022-01-3 2022-02-1 IDA / 62230 A posteriori Individuel Limited 9,030.00 6,736.15 Achevé 2021-09-29 du Plan de Mobilisation des porting Project Managemen 3 6 6 7 1 1 0 0 5 Parties Prenantes (PMPP) qui t intégrera un mécanisme de gestion des plaintes. CM-UGP-PFS-255951-CS-IND V / Recrutement d'un consul tant individuel pour l’élabora Laying the Foundations of a tion de la Stratégie de Passa Safety Net System and Sup En cours d'exécu 2021-10-1 2021-10-2 2021-10-2 2021-11-1 2021-12-2 2022-01-1 tion de Marchés pour promo IDA / 62230 A posteriori Individuel Limited 15,000.00 0.00 2021-10-20 porting Project Managemen tion 4 7 5 7 2 6 uvoir le Développement (PP t SD : Project Procurement Str ategy for Development) du P rojet Filets Sociaux adaptatif et d’Inclusion Economique CM-UGP-PFS-303170-CS-IND V / Recrutement du consulta nt national chargé d’appuyer Laying the Foundations of a l’UGP dans la préparation de Safety Net System and Sup En cours d'exécu 2022-07-1 2022-08-2 2022-09-0 2022-10-1 2023-02-1 IDA / D2980 A posteriori Individuel Open - National 10,640.00 0.00 2022-07-21 la mise en œuvre du Progra porting Project Managemen tion 5 3 6 0 1 mme d’inclusion économiqu t e des jeunes dans le cadre d u Projet Filets Sociaux Adapt atifs et Inclusion Économiqu e CM-UGP-PFS-304021-CS-IND V / Recrutement du consulta Laying the Foundations of a nt national chargé d’appuyer Safety Net System and Sup En cours d'exécu 2022-07-1 2022-08-2 2022-09-0 2022-10-1 2023-02-1 l’UGP dans la préparation de IDA / D2980 A posteriori Individuel Open - National 10,640.00 0.00 2022-07-21 porting Project Managemen tion 5 3 6 0 1 la mise en œuvre du Concou t rs de plans d’affaires dans l e cadre du Projet Filets Socia ux Adaptatifs et Inclusion Éc onomique CM-UGP-PFS-304023-CS-IND V / Recrutement du consulta Laying the Foundations of a nt national chargé d’appuyer Safety Net System and Sup En cours d'exécu 2022-07-1 2022-08-2 2022-09-0 2022-10-1 2023-02-1 l’UGP dans la préparation de IDA / D2980 A posteriori Individuel Open - National 10,640.00 0.00 2022-07-21 porting Project Managemen tion 5 3 6 0 1 la mise en œuvre du Disposi t tif de paiement numérique du Projet Filets Sociaux Ada ptatifs et Inclusion Économiq ue Page 14