Integrated Public Financial Management Reform Project PROCUREMENT PLAN (Textual Part) Project information: Country: Nepal Project Name: Integrated Public Financial Management Reform Project, Project ID: P164783 Project Implementation agency: 1. Public Expenditure and Financial Accountability Secretariat 2. Public Procurement Monitoring Office 3. Office of the Auditor General Date of the Procurement Plan: March 26, 2018 Period covered by this Procurement Plan: April 2018 – October 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Open Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national open market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Nepal’s Public Procurement Act 007 (1st Amendment) and the Regulations made thereunder, such arrangements shall be subject to paragraph 5.4 of the Bank’s Procurement Regulations for IPF Borrowers, July 2016 (Revised November 2017), and the following conditions (a) Model bidding documents, including contract conditions agreed with the Bank (as amended from time to time), shall be used. Bidding documents shall be made available, by mail or in person, to all who are willing to pay the required fee. (b) Eligibility to participate in a procurement process for and to be awarded the Bank financed contracts shall be as defined under the paragraph Eligibility of Section III Governance. of the Procurement Regulations for IPF Borrowers, July 2016. Foreign bidders shall not be precluded from bidding and no preference of any kind shall be given to national bidders. (c) Prospective bidders shall be given at least thirty (30) days from the date of publication of the invitation to bid or the date of availability of the bidding documents, whichever is later, to prepare and submit bids. There shall not be any restriction on the modality for delivery of bids. Bids may be withdrawn or modified any time before the deadline for submission of bids. Bids shall be opened in public in one place, immediately after the deadline for submission of bids. Bids received after the deadline for bid submission shall be rejected and returned to bidders unopened. (d) Qualification criteria (in case pre-qualifications were not carried out) shall be stated in the bidding documents for all contracts, irrespective of the value, and if a registration process is required, a foreign firm declared as the lowest evaluated bidder shall be given a reasonable opportunity to register, without let or hindrance. (e) Evaluation of bids shall be made in strict adherence to the criteria disclosed in the bidding documents. Contract shall be awarded to the qualified bidder whose bid has been determined: (a) to be substantially responsive to the bidding documents, and (b) to offer the lowest- evaluated cost. (f) For contracts subject to the Bank’s prior review, all bids shall not be rejected, the procurement process shall not be cancelled, and new bids shall not be solicited without the Bank’s prior concurrence. In case of re- bidding, the time for preparation and submission of bids shall be as set forth under provision (c) above. (g) Bids shall be valid as per the period stated in the bidding documents. For contracts subject to prior review, the extension of bid validity shall not be allowed without the prior concurrence of the Bank: (a) for the first request for extension if it is longer than four (4) weeks; and (b) for all subsequent requests for extension irrespective of the period. (h) Bid and performance securities shall be in the format included in the bidding documents. The bid security shall be valid for twenty-eight days (28) beyond the original validity period of the bid, or beyond any period of extension if requested. Performance security shall be an amount of five (5) to ten (10) percent (%) of the contract price and shall not be increased merely based on comparison of the contract price with the pre-bid cost estimate. (i) If a contract is terminated because of fundamental breach of contract by the contractor, the amount to be recovered from the contractor representing the employer’s additional costs for completing the contract shall be provisioned as agreed with the Bank in model bidding documents. (j) At the Recipient’s request, the Bank may agree to the Recipient’s use, in whole or in part, of its electronic procurement system, provided the Bank is satisfied with the adequacy of such system. (k) With respect to contracts subject to the Bank’s prior review, the Recipient shall obtain the Bank’s no objection before agreeing to: (a) a material extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services or other significant changes to the terms and conditions of the contract; (c) any variation order or amendment (except in cases of extreme urgency) which, singly or combined with all variation orders or amendments previously issued, increases the original contract amount by more than fifteen percent (15%); or (d) the proposed termination of the contract. A copy of all contract amendments shall be provided to the Bank. (l) The bidding document and contract as deemed acceptable by the Bank shall include provisions stating the Bank’s policy to sanction firms or individuals, found to have engaged in fraud and corruption as defined in paragraph 3.32 of the Procurement Regulations. (m) In accordance with paragraph 5.4(c) of the Procurement Regulations, the request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: Not applicable for those contracts identified in the Procurement Plan tables; Works: Not applicable, as no works procurement under this project. PROCUREMENT Nepal : Integrated Public Financial Management Reform Project PLAN General Information Country: Nepal 2018-04-03 Bank’s Approval Date of the Original Procurement Plan: 2023-02-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P164783 GPN Date: Project Name: Integrated Public Financial Management Reform Project Loan / Credit No: / , TF / A7475, TF / A7474 Public Expenditure and Financial Accountability Secretariat Executing Agency(ies): WORKS Activity Reference No. / Procureme Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH Ri Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method nt Docume ount (US$ and Recommendation Signed Contract o. h cess (Y/N) sk atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion nt Type ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-MOFAGA-104605-GO-DIR Component 4: PFM Reform / Procurement of laptop, sca TF / A7474 Management and Coordinati Post Direct Selection Direct 0.00 Canceled 2019-03-15 2019-03-20 2019-04-24 2019-10-21 nner and projector. on NP-MOFAGA-104609-GO-DIR Component 4: PFM Reform Request for Quota Single Stage - One E / Procurement of laptop, print TF / A7474 Management and Coordinati Post Open - National 0.00 Canceled 2019-04-20 2019-06-15 2019-12-12 tions nvelope er, scanner and projector. on NP-PEFA-106567-GO-RFB / P rocurement of IT equipment Component 4: PFM Reform such as Desktop, projectors, Single Stage - Two E TF / A7474 Management and Coordinati Post Request for Bids Open - National 68,917.65 Completed 2019-03-31 2019-05-05 2019-04-05 2019-05-09 2019-05-17 2019-06-06 2019-07-30 2019-06-14 2019-09-03 2019-06-28 2020-03-01 2019-07-15 projectors etc for strengthen nvelope on ing Project coordination unit, Project implementation unit and DPIUs. NP-PEFA-127923-GO-RFB / S Component 4: PFM Reform Single Stage - One E upply and Delivery of IT equi TF / A7474 Management and Coordinati Post Request for Bids Open - National 57,065.08 Completed 2019-09-16 2020-01-10 2019-09-26 2020-01-20 2019-10-31 2020-02-16 2019-11-30 2020-03-01 2020-01-01 2020-05-18 2020-03-01 2020-07-14 nvelope pment for the PIUs/DPIUs on NP-PEFA-127937-GO-RFQ / P Component 4: PFM Reform Request for Quota Single Stage - One E rocurement of Miscellaneous TF / A7474 Management and Coordinati Post Open - National 3,126.02 Completed 2019-09-11 2019-09-25 2019-11-06 2019-11-22 2020-01-05 2020-02-02 tions nvelope goods for office use on NP-MOF-136105-GO-RFB / Pr Component 1: Strengthening ocurement of Enterprise Dat Public Expenditure and Rev Single Stage - One E TF / A7474 Post Request for Bids Open - National 190,898.09 Completed 2019-10-01 2021-03-05 2019-10-06 2019-11-17 2021-04-04 2019-12-17 2021-05-27 2020-01-21 2021-06-14 2020-07-19 2021-07-14 abase and its License with Se enue Management in Federa nvelope curity Features for LMBIS, PL l and Subnational Governme MBIS nts Component 1: Strengthening NP-MOF-136106-GO-RFB / Pr Public Expenditure and Rev Single Stage - One E TF / A7474 Post Request for Bids Open - National 0.00 Canceled 2019-11-01 2019-11-06 2019-12-18 2020-01-17 2020-02-21 2020-07-20 ocurement of Generator enue Management in Federa nvelope l and Subnational Governme nts Component 1: Strengthening NP-MOF-136107-GO-RFB / Pr Public Expenditure and Rev Single Stage - One E ocurement of Laptops, Deskt TF / A7474 Post Request for Bids Open - National 54,072.90 Completed 2019-10-01 2019-12-05 2019-10-06 2019-11-17 2020-01-19 2019-12-17 2020-02-23 2020-01-21 2020-04-29 2020-07-19 2020-12-15 enue Management in Federa nvelope ops, Printers and Scanners l and Subnational Governme nts Component 1: Strengthening NP-MOF-136108-GO-RFB / Pr Public Expenditure and Rev Single Stage - One E ocurement of the Software fo TF / A7474 Post Request for Bids Open - National 0.00 Canceled 2019-11-20 2019-11-25 2020-01-06 2020-02-05 2020-03-11 2020-07-09 enue Management in Federa nvelope r the Revenue Forecasting l and Subnational Governme nts NP-FCGO-137476-GO-RFP / P Component 1: Strengthening rocurement of equipment su Public Expenditure and Rev ch as Desktop, Laptop, AC, P Single Stage - One E TF / A7474 enue Management in Federa Post Request for Bids Open - National 91,074.82 Terminated 2019-10-03 2019-10-01 2019-10-08 2019-12-09 2019-11-19 2019-12-09 2019-12-19 2020-01-03 2020-01-23 2020-01-30 2020-07-21 hotocopy machine, Projector nvelope l and Subnational Governme s, Printers and other equipm nts ent for FCGO and Province le vel lab. Component 1: Strengthening NP-FCGO-153555-GO-RFQ / Public Expenditure and Rev Request for Quota Single Stage - One E Procurement of APC inrow co TF / A7475 Post Open - National 7,660.86 Completed 2020-01-27 2020-03-23 2020-06-28 2020-09-19 2020-07-09 enue Management in Federa tions nvelope oling system outdoor. l and Subnational Governme nts NP-FCGO-174747-GO-RFQ / Component 1: Strengthening Procurement of IT Infrastruct Public Expenditure and Rev Request for Quota Single Stage - One E TF / A7475 Post Open - National 10,289.04 Completed 2020-06-07 2020-11-09 2020-08-02 2020-10-20 2021-01-29 2020-12-17 ure Enhancement (Memory u enue Management in Federa tions nvelope pgrade in server, NAS, syste l and Subnational Governme m monitoring PDAs) nts NP-PAC-179846-GO-RFQ / Es Component 1: Strengthening tablishing book corner includi Public Expenditure and Rev Request for Quota Single Stage - One E Pending Impl TF / A7475 Post Open - National 0.00 2020-06-29 2020-08-24 2021-02-20 ng necessary furniture and fu enue Management in Federa tions nvelope ementation rnishing l and Subnational Governme nts Component 1: Strengthening NP-FCGO-189910-GO-RFB / P Public Expenditure and Rev Single Stage - One E rocurement of IT equipment f TF / A7474 Post Request for Bids Open - National 35,392.27 Completed 2020-09-21 2020-10-04 2020-09-26 2020-11-11 2020-10-27 2020-11-01 2020-11-11 2020-11-24 2020-12-01 2020-12-22 2021-03-01 2021-03-19 enue Management in Federa nvelope or DTCOs l and Subnational Governme nts NP-PEFA-197569-GO-RFQ / P Component 4: PFM Reform Request for Quota Single Stage - One E Under Imple TF / A7474 Post Limited 0.00 2020-10-31 2020-12-06 2021-03-06 rocurement of furniture and f Management and Coordinati tions nvelope mentation urnishing on NP-PEFA-100204-GO-DIR / Pr Component 4: PFM Reform TF / A7474 Post Direct Selection Direct 0.00 Canceled 2019-02-14 2019-02-15 2019-03-20 2019-03-24 ocurement of license of serv Management and Coordinati er. on NP-FCGO-193167-GO-RFB / Component 1: Strengthening Renewal of Existing Networks Public Expenditure and Rev Single Stage - One E TF / A7474 Post Request for Bids Open - National 234,519.42 Completed 2020-11-18 2020-11-12 2020-11-23 2021-01-04 2020-12-13 2021-01-14 2020-12-21 2021-02-08 2021-01-13 2021-05-09 2021-04-12 Device Licenses and Subscrip enue Management in Federa nvelope tion l and Subnational Governme nts Page 1 NP-FCGO-111416-GO-RFB / P rocurement of equipment su Component 1: Strengthening ch as Desktop, projectors, Se Public Expenditure and Rev Single Stage - One E rvers equipment, Storage eq TF / A7474 enue Management in Federa Post Request for Bids Open - National 0.00 Canceled 2019-04-28 2019-05-03 2019-06-14 2019-07-14 2019-08-18 2020-07-10 nvelope uipment etc for strengthenin l and Subnational Governme g Project coordination unit, P nts roject implementation unit a nd DPIUs. NP-NPC-210961-GO-RFQ / Pr Component 1: Strengthening ocurement of Laptop,Deskto Public Expenditure and Rev Request for Quota Single Stage - One E TF / A7474 Post Open - National 11,016.00 Completed 2021-02-01 2021-03-16 2021-04-19 2021-04-25 2021-05-11 p,Multi-function Printer and D enue Management in Federa tions nvelope isplay Screen for Modeling La l and Subnational Governme b Establishment nts NP-PAC-180057-GO-RFQ / Pr Component 1: Strengthening ocurement of Machinery & E Public Expenditure and Rev Request for Quota Single Stage - One E TF / A7475 Post Open - National 0.00 Canceled 2020-06-20 2020-08-15 2021-02-11 quipment (Laptop, Desktop, enue Management in Federa tions nvelope Printer, Projector, Camera, et l and Subnational Governme c.) nts NP-PAC-215079-GO-RFB / Pr Component 1: Strengthening ocurement of Laptops and ot Public Expenditure and Rev Single Stage - One E TF / A7474 Post Request for Bids Open - National 48,261.07 Completed 2021-01-25 2021-01-29 2021-01-30 2021-03-13 2021-03-05 2021-03-28 2021-02-17 2021-04-12 2021-05-09 2021-07-11 2021-12-27 her machinery equipment for enue Management in Federa nvelope PAC Members and office staff l and Subnational Governme s use nts Component 1: Strengthening NP-FCGO-189911-GO-RFB / P Public Expenditure and Rev Single Stage - One E Under Imple rocurement of Power System, TF / A7474 Post Request for Bids Open - National 0.00 2021-02-25 2021-04-07 2021-03-02 2021-04-02 2021-04-17 2021-05-08 2021-08-06 enue Management in Federa nvelope mentation Solar, Backup for DTCOs l and Subnational Governme nts Component 1: Strengthening NP-NPC-218749-GO-RFQ / Pr Public Expenditure and Rev Request for Quota Single Stage - One E ocurement of Desktop and La TF / A7474 Post Open - National 11,931.08 Completed 2021-02-20 2021-04-17 2021-05-05 2021-06-16 2021-05-20 enue Management in Federa tions nvelope ptop for use in NPBMIS l and Subnational Governme nts NP-MOF (PDMO)-235780-GO- Component 1: Strengthening DIR / Procurement of machin Public Expenditure and Rev TF / A7474 Post Direct Selection Direct 10,182.27 Completed 2021-05-21 2020-08-21 2021-05-24 2021-01-11 2021-06-07 2021-05-14 2021-07-07 2021-06-16 ery and equipment (Compute enue Management in Federa r, etc.) for Public Debt Manag l and Subnational Governme ement Office. nts Component 1: Strengthening NP-MOF (PDMO)-235783-GO- Public Expenditure and Rev DIR / Procurement of Furnitur TF / A7474 Post Direct Selection Direct 3,067.27 Completed 2021-05-21 2020-08-05 2021-05-24 2021-02-19 2021-06-07 2021-03-04 2021-07-07 2021-03-04 enue Management in Federa e and Furnishings for PDMO l and Subnational Governme nts NP-MOF (PDMO)-235789-GO- Component 1: Strengthening DIR / Procurement of VPN lice Public Expenditure and Rev TF / A7474 Post Direct Selection Direct 10,361.83 Completed 2021-05-21 2020-08-21 2021-05-26 2020-07-20 2021-06-30 2021-03-04 2021-08-04 2021-07-04 nse and equipments for DOM enue Management in Federa S system of PDMO. l and Subnational Governme nts NP-MOF-136101-GO-RFB / Pr Component 1: Strengthening ocurement of IT Equipment s Public Expenditure and Rev Single Stage - One E uch as Servers, Server RAC, TF / A7474 enue Management in Federa Post Request for Bids Open - National 137,798.37 Completed 2021-08-13 2022-01-25 2021-08-18 2022-02-23 2021-09-29 2022-02-24 2021-10-29 2022-04-04 2021-12-03 2022-04-22 2022-06-01 2022-08-07 nvelope Storage, Firewall switch, etc. l and Subnational Governme for the Data Recovery site of nts the MoF (Hetauda). Component 1: Strengthening NP-PAC-218746-GO-RFQ / Fu Public Expenditure and Rev Request for Quota Single Stage - One E rniture works for PAC at fede TF / A7474 Post Open - National 7,490.80 Completed 2021-08-10 2021-10-05 2021-04-26 2021-12-04 2021-07-09 enue Management in Federa tions nvelope ral parliament secretariat l and Subnational Governme nts NP-MOF-136104-GO-RFB / Pr Component 1: Strengthening ocurement of IT equipment s Public Expenditure and Rev Single Stage - One E uch as Server, Server RAC, S TF / A7474 enue Management in Federa Post Request for Bids Open - National 197,158.30 Signed 2021-08-08 2022-01-25 2021-08-13 2022-02-23 2021-09-24 2022-02-24 2021-10-24 2022-03-31 2021-11-28 2022-04-22 2022-05-27 nvelope erver Visualization (vmware), l and Subnational Governme Computing unit etc for the D nts ata Center Site at MOF NP-MOF-245804-GO-RFB / Pr Component 1: Strengthening ocurement of Hardware/Soft Public Expenditure and Rev Single Stage - One E Pending Impl ware/Equipment and Security TF / A7474 enue Management in Federa Post Request for Bids Open - National 0.00 2021-08-10 2021-08-15 2021-09-26 2021-10-26 2021-11-30 2022-05-29 nvelope ementation Devices Licenses for data arc l and Subnational Governme hive, data visualization, serv nts er and network security. NP-MOF-245807-GO-RFB / Pr Component 1: Strengthening ocurement of high ends Ente Public Expenditure and Rev Single Stage - One E TF / A7474 Post Request for Bids Open - National 37,167.31 Completed 2021-08-08 2022-01-25 2021-08-13 2022-02-23 2021-09-24 2022-02-24 2021-10-24 2022-04-04 2021-11-28 2022-04-22 2022-05-27 rprise level Laptops, Monitors enue Management in Federa nvelope , and Printer. l and Subnational Governme nts NP-MOF (PDMO)-235954-GO- Component 1: Strengthening DIR / Optical fibre connectivit Public Expenditure and Rev y from GIDC tp PDMO DOMS TF / A7474 enue Management in Federa Post Direct Selection Direct 0.00 Canceled 2021-05-24 2021-05-29 2021-06-19 2021-07-24 protection software license p l and Subnational Governme urchase and renew (Edited) nts NP-PEFA-197568-GO-RFQ / P rocurement of Computer, Pri Component 4: PFM Reform Request for Quota Single Stage - One E nter, laptop, projector, server TF / A7474 Management and Coordinati Post Limited 1,966.49 Completed 2020-10-31 2021-03-25 2020-12-08 2021-04-21 2021-03-08 2021-04-21 tions nvelope , scanner and other Electroni on c Equipment for office operat ion NP-FCGO-271314-GO-RFQ / Component 1: Strengthening Procurement of equipment s Public Expenditure and Rev Request for Quota Single Stage - One E Pending Impl uch as Desktop, Laptop, AC, TF / A7474 enue Management in Federa Post Open - National 0.00 2022-01-07 2022-03-04 2022-06-02 tions nvelope ementation Photocopy machine, Projecto l and Subnational Governme rs, Printers and other equipm nts ent for FCGO. NP-NPC-273707-GO-RFB / Pr Component 1: Strengthening ocurement of Desktop, Scann Public Expenditure and Rev Single Stage - One E Pending Impl TF / A7474 Post Request for Bids Open - National 0.00 2022-01-19 2022-01-24 2022-03-07 2022-03-17 2022-04-14 2022-05-14 er, Printer & Multi function D enue Management in Federa nvelope ementation evice l and Subnational Governme nts Component 1: Strengthening NP-PAC-276696-GO-RFB / Pr Public Expenditure and Rev Single Stage - One E Under Imple ocurement of Computer, Lapt TF / A7474 Post Request for Bids Open - National 0.00 2022-02-10 2022-03-07 2022-02-15 2022-03-07 2022-03-29 2022-04-15 2022-04-28 2022-04-26 2022-06-02 2022-11-29 enue Management in Federa nvelope mentation op and other IT Equipment's l and Subnational Governme nts NP-MOF-280770-GO-RFB / R Component 1: Strengthening enewal and procurement of Public Expenditure and Rev Single Stage - One E Under Imple TF / A7474 Post Request for Bids Open - National 0.00 2022-03-02 2022-12-16 2022-03-02 2022-12-19 2022-04-01 2022-04-04 2022-04-12 2022-05-17 Supply, Commissioning, Insta enue Management in Federa nvelope mentation llation of Existing IT Equipme l and Subnational Governme nt License of DOMS. nts Page 2 NP-MOF-280775-GO-RFB / R enewal and procurement of S Component 1: Strengthening upply, Delivery, Commissioni Public Expenditure and Rev Single Stage - One E Pending Impl ng, and Installation of Existin TF / A7474 enue Management in Federa Post Request for Bids Open - National 0.00 2022-03-02 2022-03-02 2022-04-01 2022-04-04 2022-04-12 2022-05-17 nvelope ementation g Database License with Sec l and Subnational Governme urity Features ( complete for nts ecasting and reporting soluti on) for PFM System(DOMS, P LMBIS). NP-MOF-280795-GO-DIR / Di Component 1: Strengthening rect Procurement of Acrobate Public Expenditure and Rev Pending Impl License for Budget Books( Re TF / A7474 enue Management in Federa Post Direct Selection Direct 0.00 2022-02-28 2022-03-01 2022-03-03 2022-03-18 ementation dbook, Budget Speech, Fiscal l and Subnational Governme Transfer, etc. )Development nts and Creation. NP-PEFA-285842-GO-RFB / P Component 4: PFM Reform Single Stage - One E TF / A7474 Post Request for Bids Open - National 90,981.64 Completed 2022-03-25 2022-04-08 2022-03-30 2022-05-11 2022-05-08 2022-06-10 2022-05-30 2022-07-15 2022-06-09 2023-01-11 2022-08-09 rocurement of Laptop Management and Coordinati nvelope on NP-PEFA-264199-GO-RFB / P rocurement of Computer, Pri Component 4: PFM Reform Single Stage - One E nter, laptop, projector, server TF / A7474 Management and Coordinati Post Request for Bids Open - National 62,502.67 Completed 2021-11-26 2022-01-31 2021-12-01 2022-01-12 2022-03-02 2022-02-11 2022-03-14 2022-03-18 2022-04-26 2022-09-14 2022-07-12 nvelope , scanner and other Electroni on c Equipment for office operat ion Component 1: Strengthening NP-NPC-286229-GO-RFQ / Pr Public Expenditure and Rev Request for Quota Single Stage - One E Pending Impl ocurement of software for m TF / A7474 Post Limited 0.00 2022-03-30 2022-04-13 2022-06-12 enue Management in Federa tions nvelope ementation odeling lab l and Subnational Governme nts NP-NPC-210967-GO-RFQ / Pr Component 1: Strengthening ocurement of Software Syste Public Expenditure and Rev Request for Quota Single Stage - One E TF / A7474 Post Open - National 0.00 Canceled 2021-01-30 2021-03-13 2021-05-12 m for Establishing Modeling L enue Management in Federa tions nvelope ab in National Planning Com l and Subnational Governme mission nts NP-NPC-242564-GO-DIR / pr Component 1: Strengthening ocurement of Software and D Public Expenditure and Rev TF / A7474 Post Direct Selection Direct 0.00 Canceled 2021-07-08 2021-07-08 2021-07-08 2021-07-14 ata base system for establish enue Management in Federa ment of Modeling Lab in NPC l and Subnational Governme nts NP-MOF-325906-GO-RFQ / Pr Component 1: Strengthening ocurement of the Software fo Public Expenditure and Rev Request for Quota Single Stage - One E Pending Impl TF / A7475 Post Limited 0.00 2022-12-02 2023-01-27 2023-03-21 r Revenue Forecasting Softw enue Management in Federa tions nvelope ementation are for analyzing various mo l and Subnational Governme dels through it. nts NP-MOF-245819-GO-DIR / De Component 1: Strengthening sign and Develop a workflow Public Expenditure and Rev on LMBIS and PLMBIS that c TF / A7474 enue Management in Federa Post Direct Selection Direct 0.00 Canceled 2021-09-05 2021-09-10 2021-10-15 2022-04-13 aptures Physical and Financi l and Subnational Governme al progress in the system. nts Component 1: Strengthening NP-NPC-337006-GO-RFB / Pr Public Expenditure and Rev Single Stage - One E Pending Impl ocurement of Hardware Devi TF / A7475 Post Request for Bids Open - National 0.00 2023-01-24 2023-01-29 2023-03-12 2023-04-11 2023-05-16 2023-06-20 enue Management in Federa nvelope ementation ces l and Subnational Governme nts Component 1: Strengthening NP-FCGO-343756-GO-RFQ / Public Expenditure and Rev Request for Quota Single Stage - One E Pending Impl Procurement of CCTV Surveill TF / A7474 Post Limited 0.00 2023-02-22 2023-03-14 2023-03-17 enue Management in Federa tions nvelope ementation ance System l and Subnational Governme nts NP-FCGO-343764-GO-RFQ / Component 1: Strengthening Procurement of Digital Infor Public Expenditure and Rev Request for Quota Single Stage - One E Pending Impl TF / A7474 Post Limited 0.00 2023-02-22 2023-03-18 2023-04-17 mation Display System (Citiz enue Management in Federa tions nvelope ementation en Charter and others) l and Subnational Governme nts NP-FCGO-343778-GO-RFQ / Component 1: Strengthening Procurement of Power backu Public Expenditure and Rev Request for Quota Single Stage - One E Pending Impl TF / A7474 Post Limited 0.00 2023-02-22 2023-03-18 2023-04-17 p system (Battery) for DTCO' enue Management in Federa tions nvelope ementation s. l and Subnational Governme nts NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-PEFA-106556-NC-RFP / In Component 4: PFM Reform Request for Quota Single Stage - One E teraction with economic jour TF / A7474 Management and Coordinati Post Limited 10,650.54 Completed 2019-03-25 2019-12-30 2019-04-07 2020-01-10 2019-04-10 2020-07-06 tions nvelope nalist regarding PFM . on NP-PEFA-106564-NC-DIR / C Component 4: PFM Reform onduct ACCA course for PFM TF / A7474 Management and Coordinati Post Direct Selection Direct 0.00 Canceled 2019-03-20 2019-03-25 2019-04-29 2019-05-06 strengthening. on NP-PEFA-108474-NC-RFQ / IP Component 4: PFM Reform Request for Quota Single Stage - One E TF / A7474 Post Limited 0.00 Canceled 2019-05-05 2019-06-30 2019-12-27 SAS Certification course for P Management and Coordinati tions nvelope FM staff. on NP-PEFA-106572-NC-RFQ / P Component 4: PFM Reform Request for Quota Single Stage - One E ublic hearing at local level re TF / A7474 Management and Coordinati Post Open - National 0.00 Canceled 2019-05-10 2019-07-05 2020-01-01 tions nvelope garding PFM issues. on NP-PEFA-106575-NC-RFQ / C Component 4: PFM Reform Request for Quota Single Stage - One E onduct training for social aud TF / A7474 Management and Coordinati Post Open - National 0.00 Canceled 2019-05-06 2019-07-01 2019-12-28 tions nvelope it at SNG levels. on NP-PEFA-108636-NC-RFB / T Component 4: PFM Reform Single Stage - One E TF / A7474 Post Request for Bids Open - National 24,938.06 Signed 2019-04-02 2020-08-10 2019-04-03 2019-04-09 2019-05-15 2020-08-10 2019-06-14 2020-08-10 2019-07-19 2020-10-12 2020-01-15 uition and logistic costs for A Management and Coordinati nvelope CCA course. on NP-PEFA-110216-NC-RFQ / C Component 4: PFM Reform Request for Quota Single Stage - One E onduct training for social aud TF / A7474 Management and Coordinati Post Limited 15,598.82 Completed 2019-04-20 2019-05-07 2019-06-15 2019-05-16 2019-12-12 2019-06-11 tions nvelope it at SNG levels. on NP-PEFA-110214-NC-RFQ / P Component 4: PFM Reform Request for Quota Single Stage - One E ublic hearing at local level re TF / A7474 Management and Coordinati Post Limited 0.00 Canceled 2019-04-22 2019-06-17 2019-12-14 tions nvelope garding PFM issues. on NP-PEFA-127935-NC-RFQ / P Component 4: PFM Reform roduction and broadcasting o Request for Quota Single Stage - One E TF / A7474 Management and Coordinati Post Limited 4,114.53 Completed 2019-09-07 2020-02-25 2019-10-20 2020-03-12 2020-07-16 2020-07-05 f the awareness-raising progr tions nvelope on ams on PFM issues through Media. Page 3 NP-PEFA-127943-NC-RFQ / P Component 4: PFM Reform Request for Quota Single Stage - One E TF / A7474 Post Limited 4,049.92 Completed 2019-10-20 2020-02-25 2019-12-15 2020-03-12 2020-02-13 2020-07-09 repare PEFA Documentary Management and Coordinati tions nvelope on Component 1: Strengthening NP-PEFA-127947-NC-RFQ / C Public Expenditure and Rev Request for Quota Single Stage - One E onduct Training for Social Au TF / A7474 Post Limited 0.00 Canceled 2019-09-23 2019-11-18 2020-05-16 enue Management in Federa tions nvelope dit l and Subnational Governme nts NP-FCGO-134003-NC-RFQ / P Component 1: Strengthening rocurement of the Service for Public Expenditure and Rev Request for Quota Single Stage - One E the Developing and Updating TF / A7474 enue Management in Federa Post Open - National 7,099.01 Completed 2019-09-23 2019-11-18 2019-11-12 2020-05-16 2020-07-14 tions nvelope the Computerized Governme l and Subnational Governme nt Accounting System nts NP-FCGO-134006-NC-RFQ / P Component 1: Strengthening rocurement of the Service for Public Expenditure and Rev Request for Quota Single Stage - One E TF / A7474 Post Open - National 7,830.57 Completed 2019-09-23 2019-11-18 2020-01-07 2020-05-16 2020-07-13 Developing Public Assets Ma enue Management in Federa tions nvelope nagement System l and Subnational Governme nts NP-FCGO-134008-NC-RFQ / P Component 1: Strengthening rocurement of the Service for Public Expenditure and Rev Request for Quota Single Stage - One E TF / A7474 Post Open - National 6,437.74 Completed 2019-09-23 2019-11-18 2020-03-18 2020-05-16 2021-06-17 the Enhancement of the Elec enue Management in Federa tions nvelope tronic Fund Transfer System l and Subnational Governme nts NP-PEFA-127938-NC-RFQ / In Component 4: PFM Reform Request for Quota Single Stage - One E teraction program with econ TF / A7474 Management and Coordinati Post Limited 10,590.06 Completed 2020-01-15 2019-12-30 2020-03-04 2020-01-10 2020-08-31 2020-07-06 tions nvelope omic journalist/societies on NP-NPC-154037-NC-RFQ / Pr Component 1: Strengthening ocurement of Consulting Ser Public Expenditure and Rev Request for Quota Single Stage - One E vices for Up-scaling of Nation TF / A7475 enue Management in Federa Post Limited 15,852.94 Completed 2020-01-27 2020-01-27 2020-03-23 2020-02-03 2020-09-19 2020-10-02 tions nvelope al Project Bank Management l and Subnational Governme Information System (NPBMIS) nts NP-FCGO-162671-NC-DIR / P Component 1: Strengthening rocurement of development Public Expenditure and Rev TF / A7475 Post Direct Selection Direct 4,171.01 Completed 2020-03-31 2020-01-26 2020-04-05 2020-02-03 2020-05-10 2020-04-24 2020-11-06 2020-07-10 of reimbursement managem enue Management in Federa ent information system l and Subnational Governme nts NP-PAC-187650-NC-RFQ / De Component 1: Strengthening sign and Develop Public Acco Public Expenditure and Rev Request for Quota Single Stage - One E TF / A7475 Post Open - National 12,720.10 Completed 2020-09-04 2020-10-30 2021-11-25 2021-04-28 2022-04-25 unting Committee Managem enue Management in Federa tions nvelope ent Information System (PAC l and Subnational Governme MIS) nts Component 1: Strengthening NP-FCGO-189912-NC-RFQ / Public Expenditure and Rev Request for Quota Single Stage - One E Development of online NPSA TF / A7474 Post Limited 13,756.68 Signed 2020-09-05 2020-09-17 2020-10-31 2020-10-14 2021-04-29 enue Management in Federa tions nvelope S reporting System l and Subnational Governme nts NP-FCGO-189917-NC-RFQ / Component 1: Strengthening Service Level Agreement (SL Public Expenditure and Rev Request for Quota Single Stage - One E TF / A7474 Post Limited 0.00 Canceled 2020-09-05 2020-10-31 2021-04-29 A) for Active Directory (AD) f enue Management in Federa tions nvelope or the Enhancement of Secur l and Subnational Governme ity of PFM System nts NP-PEFA-197577-NC-RFQ / C Component 4: PFM Reform onduct study on feasibility an Request for Quota Single Stage - One E TF / A7474 Management and Coordinati Post Limited 0.00 Canceled 2020-10-31 2020-12-06 2021-03-06 d development of central pay tions nvelope on roll system for GON Component 1: Strengthening NP-FCGO-231427-NC-RFB / Public Expenditure and Rev Single Stage - One E Development /Enhancement TF / A7475 Post Request for Bids Limited 14,241.17 Signed 2021-04-26 2021-05-07 2021-05-01 2021-05-07 2021-05-16 2021-05-10 2021-05-21 2021-05-12 2021-06-01 2021-05-13 2021-08-01 enue Management in Federa nvelope of RMIS and Rajaswa Portal l and Subnational Governme nts Component 1: Strengthening NP-MOF(PDMO)-240463-NC- Public Expenditure and Rev Pending Impl DIR / Email, Internet , Networ TF / A7474 Post Direct Selection Direct 0.00 2021-06-20 2021-06-22 2021-06-29 2021-07-15 enue Management in Federa ementation king and server support l and Subnational Governme nts NP-PEFA-127949-NC-DIR / Fi Component 4: PFM Reform nancial Report Analysis Traini TF / A7474 Management and Coordinati Post Direct Selection Direct 0.00 Canceled 2019-08-25 2019-08-30 2019-09-17 2019-09-26 ng for the Accounts staffs of t on he GON through ICAN NP-FCGO-189915-NC-RFQ / Component 1: Strengthening Development of Consolidated Public Expenditure and Rev Request for Quota Single Stage - One E Pending Impl TF / A7474 Post Limited 0.00 2020-09-05 2020-10-31 2021-04-29 Fund Accounting and Reporti enue Management in Federa tions nvelope ementation ng System l and Subnational Governme nts NP-FCGO-187333-NC-RFQ / I Component 1: Strengthening mplementation of review rep Public Expenditure and Rev Request for Quota Single Stage - One E Pending Impl TF / A7474 Post Limited 0.00 2020-11-04 2020-12-30 2021-06-28 ort of equipments supporting enue Management in Federa tions nvelope ementation IT based PFM Systems of FCG l and Subnational Governme O. nts NP-FCGO-193174-NC-RFB / C Component 1: Strengthening onsulting Service for Applicat Public Expenditure and Rev ion Programming Interface (A Single Stage - One E Pending Impl TF / A7474 enue Management in Federa Post Request for Bids Open - National 0.00 2020-09-30 2020-10-05 2020-11-16 2020-12-16 2021-01-20 2021-07-19 PI) Management Solution and nvelope ementation l and Subnational Governme Single Sign on Solution for Us nts er Authentication and Identif y Management Needs NP-PEFA-256323-NC-RFQ / T Component 4: PFM Reform Request for Quota Single Stage - One E raining and orientation progr TF / A7474 Management and Coordinati Post Limited 9,966.06 Completed 2021-10-05 2021-10-05 2021-10-08 2021-10-06 2022-04-06 2022-05-27 tions nvelope am for economic journalists. on NP-FCGO-190150-NC-RFB / C onsulting Service for Enhanc Component 1: Strengthening ement of Functional and Non Public Expenditure and Rev Single Stage - One E Pending Impl functional Features (Two fact TF / A7474 enue Management in Federa Post Request for Bids Open - National 0.00 2020-09-07 2020-09-12 2020-10-24 2020-11-23 2020-12-28 2021-06-26 nvelope ementation or Authentication, Digital Sig l and Subnational Governme nature, Central Payroll Syste nts m etc.) on Existing PFM Syste ms (CGAS, TSA, RMIS, SuTRA ) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1: Strengthening NP-PEFA-54368-CS-CQS / Ad Public Expenditure and Rev Consultant Qualifi option of NFRS in selected St / Post Open - National 0.00 Canceled 2018-05-15 2018-06-05 2018-07-19 2018-08-18 2018-09-22 2019-03-21 enue Management in Federa cation Selection ate Owned Enterprises. l and Subnational Governme nts Page 4 Component 1: Strengthening NP-PEFA-54365-CS-CQS / Co Public Expenditure and Rev Quality And Cost- Open - Internationa nduct Study for IFMIS Develo / Post 0.00 Canceled 2018-05-01 2018-05-22 2018-07-05 2018-08-02 2018-09-01 2018-10-06 2018-11-10 2019-11-10 enue Management in Federa Based Selection l pment. l and Subnational Governme nts NP-PEFA-54396-CS-CQS / De Component 1: Strengthening veloping Operating Procedur Public Expenditure and Rev Consultant Qualifi / Post Limited 0.00 Canceled 2018-04-30 2018-05-14 2018-06-13 2018-07-18 2019-01-14 e and Capacity Development enue Management in Federa cation Selection of Federal and Province PAC l and Subnational Governme members. nts NP-PEFA-91339-CS-QCBS / T o Develop an action plan for Component 1: Strengthening Assortment, Up Gradation an Public Expenditure and Rev d Enhancement of the Existin Quality And Cost- Open - Internationa TF / A7475 enue Management in Federa Post 255,275.00 Completed 2018-12-14 2018-12-14 2019-01-04 2018-12-18 2019-02-17 2019-03-28 2019-03-17 2019-03-28 2019-04-16 2019-06-16 2019-05-21 2019-08-01 2019-06-25 2019-09-05 2020-06-24 2022-07-14 g IT based Public Financial M Based Selection l l and Subnational Governme anagement (PFM) Systems in nts transition to Complete Integrated Financia l Management Information Sy stem. Component 1: Strengthening NP-ICAN-100178-CS-CQS / G Public Expenditure and Rev Consultant Qualifi AP Analysis for NFRS applicat TF / A7475 Post Open - National 4,485.65 Completed 2019-02-18 2019-03-10 2019-03-10 2019-04-21 2019-05-09 2019-05-22 2019-06-08 2021-07-01 2019-06-14 2019-07-16 2019-10-12 2019-11-18 enue Management in Federa cation Selection ion in NOC. l and Subnational Governme nts NP-PEFA-100215-CS-CQS / Pr Component 4: PFM Reform Consultant Qualifi TF / A7474 Prior Open - National 0.00 Canceled 2019-02-13 2019-04-03 2019-02-14 2019-03-11 2019-04-10 2019-05-15 2019-11-11 ocurement of procurement c Management and Coordinati cation Selection onsultant. on NP-PEFA-106570-CS-CQS / C Component 4: PFM Reform Consultant Qualifi onsulting service for PFM stra TF / A7474 Management and Coordinati Post Open - National 0.00 Canceled 2019-04-01 2019-04-22 2019-06-05 2019-07-05 2019-08-09 2020-02-05 cation Selection tegy update. on NP-PEFA-106582-CS-CQS / S Component 1: Strengthening tudy and preparation of capit Public Expenditure and Rev Consultant Qualifi TF / A7474 Post Open - National 0.00 Canceled 2019-04-02 2019-04-03 2019-05-17 2019-06-16 2019-07-21 2020-01-17 al investment project apprais enue Management in Federa cation Selection al guideline. l and Subnational Governme nts Component 1: Strengthening NP-PEFA-106583-CS-CQS / C Public Expenditure and Rev Consultant Qualifi onduct study on unreported TF / A7474 Post Limited 0.00 Canceled 2019-03-26 2019-04-09 2019-05-09 2019-06-13 2019-12-10 enue Management in Federa cation Selection government operation. l and Subnational Governme nts NP-MOFAGA-108463-CS-CQS / Improvement of revenue m Component 4: PFM Reform Consultant Qualifi anagement system for local TF / A7474 Management and Coordinati Post Open - National 0.00 Canceled 2019-03-24 2019-04-14 2019-05-28 2019-06-27 2019-08-01 2020-01-28 cation Selection government and strengtheni on ng capacity of local level rev enue advisory committee. NP-MOFAGA-104594-CS-CQS Component 4: PFM Reform Consultant Qualifi / Developing internal control TF / A7474 Management and Coordinati Post Open - National 0.00 Canceled 2019-03-29 2019-03-30 2019-05-27 2019-06-26 2019-07-31 2020-01-27 cation Selection and audit system for local go on vernment. NP-FCGO-110199-CS-QCBS / Component 1: Strengthening Consulting services for NPSA Public Expenditure and Rev Quality And Cost- TF / A7474 Prior Open - National 0.00 Canceled 2019-04-18 2019-04-29 2019-05-09 2019-05-06 2019-06-27 2019-09-02 2019-08-06 2019-11-03 2019-08-21 2019-09-19 2019-10-20 2021-06-30 S implementation (Federal, S enue Management in Federa Based Selection tate and Local Level). l and Subnational Governme nts NP-FCGO-110189-CS-CQS / I Component 1: Strengthening nternational consultant for p Public Expenditure and Rev Consultant Qualifi TF / A7474 Post Limited 0.00 Canceled 2019-04-12 2019-05-15 2019-06-14 2019-07-19 2021-06-30 eer review and quality check enue Management in Federa cation Selection of NPSAS (on Intermittent ba l and Subnational Governme sis). nts NP-PEFA-57243-CS-CQS / Tra Component 1: Strengthening ining Need Assessment and Public Expenditure and Rev Consultant Qualifi TF / A7474 Post Open - National 0.00 Canceled 2019-03-19 2019-03-20 2019-04-21 2019-05-03 2019-05-24 2019-06-28 2019-12-25 Roadmap development for P enue Management in Federa cation Selection FM capacity building of GoN l and Subnational Governme staffs. nts NP-FCGO-128326-CS-QCBS / Component 1: Strengthening Internal Control System Sam Public Expenditure and Rev Quality And Cost- TF / A7474 Post Open - National 160,485.30 Signed 2019-09-02 2019-09-01 2019-09-23 2019-09-25 2019-10-21 2019-12-09 2019-11-30 2020-01-14 2019-12-21 2020-02-28 2019-12-29 2020-03-15 2020-02-02 2020-07-09 2021-02-01 ple manual preparation for F enue Management in Federa Based Selection ederal level and Province lev l and Subnational Governme el economic entities nts Component 1: Strengthening NP-PEFA-54360-CS-CQS / De Public Expenditure and Rev Consultant Qualifi velop Medium Term Revenue / Post Open - National 0.00 Canceled 2018-06-14 2018-07-05 2018-08-18 2018-09-17 2018-10-22 2019-04-20 enue Management in Federa cation Selection Forecasting Framework. l and Subnational Governme nts Component 1: Strengthening NP-PEFA-54359-CS-CQS / De Public Expenditure and Rev Consultant Qualifi velop PFM Road map and Um / Post Open - National 0.00 Canceled 2018-05-31 2018-06-21 2018-08-04 2018-09-03 2018-10-08 2019-04-06 enue Management in Federa cation Selection brella Grant Policy for SNG's. l and Subnational Governme nts Component 1: Strengthening NP-ICAN-100180-CS-CQS / N Public Expenditure and Rev Consultant Qualifi FRS Application in Nepal Oil TF / A7475 Post Open - National 0.00 Canceled 2019-10-02 2019-10-22 2019-12-21 2020-01-05 2020-01-26 2020-07-24 enue Management in Federa cation Selection Corporation . l and Subnational Governme nts NP-ICAN-100181-CS-CQS / D Component 1: Strengthening evelop Software to facilitate l Public Expenditure and Rev Consultant Qualifi TF / A7475 Post Open - National 0.00 Canceled 2019-03-15 2019-04-04 2019-06-03 2019-06-18 2019-07-09 2020-01-05 earning, monitoring and regu enue Management in Federa cation Selection lation. l and Subnational Governme nts Component 1: Strengthening NP-ICAN-100184-CS-CQS / Pr Public Expenditure and Rev Consultant Qualifi eparation of NFRS Manual a TF / A7475 Post Open - National 0.00 Canceled 2019-03-28 2019-04-17 2019-06-26 2019-07-21 2019-08-11 2020-08-10 enue Management in Federa cation Selection nd Training Material . l and Subnational Governme nts NP-NPC-136095-CS-CQS / Co Component 1: Strengthening nsulting Services for IT Soluti Public Expenditure and Rev Consultant Qualifi TF / A7474 Post Limited 4,208.16 Completed 2019-10-01 2021-05-12 2019-10-08 2021-05-12 2019-10-15 2021-05-17 2019-11-12 2021-05-17 2020-02-10 2021-06-29 on to Automate Medium Ter enue Management in Federa cation Selection m Expenditure Framework (M l and Subnational Governme TEF) nts NP-PEFA-127932-CS-QCBS / Component 1: Strengthening Training Need Assessment a Public Expenditure and Rev Quality And Cost- TF / A7474 Post Open - National 66,297.52 Completed 2020-02-10 2020-01-01 2020-03-02 2020-01-14 2020-03-31 2020-03-16 2020-04-28 2020-06-19 2020-05-19 2020-07-08 2020-06-23 2020-09-07 2020-07-28 2020-10-12 2020-11-25 2022-07-12 nd Roadmap development fo enue Management in Federa Based Selection r PFM capacity building of Go l and Subnational Governme N staffs. nts Component 1: Strengthening NP-NPC-154035-CS-CQS / Na Public Expenditure and Rev Consultant Qualifi tional Consultancy Services t TF / A7475 Post Limited 13,540.46 Completed 2020-01-22 2020-04-23 2020-02-05 2020-05-14 2020-03-06 2020-05-21 2020-04-10 2020-08-10 2020-10-07 2021-05-12 enue Management in Federa cation Selection o Strengthen the MTEF l and Subnational Governme nts Page 5 NP-PEFA-160945-CS-CQS / Pr Component 1: Strengthening ocurement of consulting serv Public Expenditure and Rev Consultant Qualifi Under Implement TF / A7475 Post Open - National 0.00 2020-03-31 2020-11-05 2020-04-21 2020-06-04 2020-07-04 2020-08-08 2021-02-04 ices for mapping NFRS imple enue Management in Federa cation Selection ation mentation status in SOEs l and Subnational Governme nts NP-MOFAGA-174042-CS-CQS Component 1: Strengthening / Procurement of Consultant f Public Expenditure and Rev Consultant Qualifi TF / A7475 Post Open - National 21,326.50 Completed 2020-05-17 2020-05-17 2020-06-07 2020-07-21 2020-06-15 2020-08-20 2020-06-23 2020-09-24 2020-09-03 2021-03-23 2021-11-15 or Preparing of Model Interna enue Management in Federa cation Selection l Control Guidelines for Local l and Subnational Governme Governments nts NP-PAC-174272-CS-QCBS / P Component 1: Strengthening rocurement of Consulting Ser Public Expenditure and Rev vices for Development of Trai Quality And Cost- TF / A7475 enue Management in Federa Post Open - National 43,002.85 Signed 2020-05-27 2021-07-07 2020-06-17 2021-04-16 2020-07-31 2021-09-14 2020-08-28 2021-11-17 2020-09-27 2021-12-01 2020-11-01 2021-12-21 2020-12-06 2022-01-19 2021-12-06 ning Manual and Conduction Based Selection l and Subnational Governme of Training for Federal and Pr nts ovincial PAC Members and St affs. NP-PEFA-180054-CS-CQS / D Component 4: PFM Reform Consultant Qualifi rafting of Citizen Engagemen TF / A7475 Management and Coordinati Post Open - National 21,144.67 Completed 2020-06-24 2020-06-19 2020-07-15 2020-06-19 2020-08-28 2020-09-03 2020-09-27 2020-12-03 2020-11-01 2020-12-28 2021-04-30 2022-03-14 cation Selection t Strategy in PFM of Nepal on NP-PEFA-151560-CS-CQS / N Component 1: Strengthening ational Consultancy Services Public Expenditure and Rev Consultant Qualifi TF / A7475 Post Open - National 0.00 Canceled 2019-12-30 2020-01-13 2020-02-10 2020-02-17 2020-03-09 2020-03-18 to Strengthen the Medium-Te enue Management in Federa cation Selection rm Expenditure Framework. l and Subnational Governme nts NP-PAC-204280-CS-CQS / Co Component 1: Strengthening nsulting services for Develop Public Expenditure and Rev ment of Operational Manual Consultant Qualifi TF / A7475 enue Management in Federa Post Open - National 0.00 Canceled 2020-11-12 2020-12-03 2021-01-01 2021-01-16 2021-02-06 2021-05-07 and Training Materials and co cation Selection l and Subnational Governme nduction of Training for Fede nts ral and Provincial PAC Memb ers and Staffs' NP-PAC-215084-CS-CQS / Pr Component 1: Strengthening ocurement of Consulting Ser Public Expenditure and Rev Consultant Qualifi TF / A7474 Post Open - National 0.00 Canceled 2021-02-01 2021-02-22 2021-03-30 2021-04-14 2021-05-19 2021-09-19 vices for study and developm enue Management in Federa cation Selection ent of PAC Operation Guideli l and Subnational Governme nes. nts NP-ICAN-129889-CS-CQS / Pr Component 4: PFM Reform Consultant Qualifi eparation of NFRS Manual an TF / A7474 Management and Coordinati Post Limited 0.00 Canceled 2019-10-14 2019-11-13 2019-12-28 2020-01-26 2021-01-25 cation Selection d Training Materials on NP-ICAN-129887-CS-CQS / N Component 4: PFM Reform Consultant Qualifi FRS Application in Nepal Oil TF / A7474 Management and Coordinati Post Limited 0.00 Canceled 2019-09-17 2019-10-17 2019-12-01 2020-01-05 2021-01-04 cation Selection Corporation on Component 1: Strengthening NP-FCGO-190144-CS-LCS / D Public Expenditure and Rev Least Cost Selecti Pending Impleme evelopment of Internal Audit TF / A7474 Post Open - National 0.00 2020-09-07 2020-09-28 2020-11-11 2020-12-09 2021-01-08 2021-02-12 2021-03-19 2021-09-15 enue Management in Federa on ntation Charter l and Subnational Governme nts NP-FCGO-190142-CS-LCS / C Component 1: Strengthening onsulting Service for develop Public Expenditure and Rev Least Cost Selecti Pending Impleme TF / A7474 Post Open - National 0.00 2020-09-07 2020-09-28 2020-11-11 2020-12-09 2021-01-08 2021-02-12 2021-03-19 2021-09-15 ing Guidelines for Pubic Asse enue Management in Federa on ntation t Valuation. l and Subnational Governme nts NP-FCGO-190143-CS-LCS / C Component 1: Strengthening onsulting Service for Public E Public Expenditure and Rev Least Cost Selecti Pending Impleme TF / A7474 Post Open - National 0.00 2020-09-07 2020-09-28 2020-11-11 2020-12-09 2021-01-08 2021-02-12 2021-03-19 2021-09-15 xpenditure Tracking Survey ( enue Management in Federa on ntation PETS) l and Subnational Governme nts NP-NPC-259760-CS-CQS / De Component 1: Strengthening veloping Unified Standard Gu Public Expenditure and Rev idelines for Identification, Ap Consultant Qualifi Pending Impleme TF / A7474 enue Management in Federa Post Open - National 0.00 2021-10-26 2021-11-16 2021-12-14 2021-12-21 2022-01-18 2022-07-17 praisal and Selection and Pri cation Selection ntation l and Subnational Governme oritization of Government Pro nts jects to be funded under the National Project Bank NP-MOF-280793-CS-CQS / Su Component 1: Strengthening pport, Maintenance, and Enh Public Expenditure and Rev Consultant Qualifi Under Implement ancement of Budget System TF / A7474 enue Management in Federa Post Limited 0.00 2022-03-01 2022-03-16 2022-03-11 2022-03-13 2022-03-14 2022-07-12 cation Selection ation (LMBIS, PLMBIS) for federal a l and Subnational Governme nd Provincial Governments. nts INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Actual Amount Invitation to Identifie Draft Negotiated Cont Component Review Type Method Contract Type Process Status Teams of Reference Signed Contract Contract Completion Description o. h (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NP-PEFA-86197-CS-INDV / Pr Component 4: PFM Reform Individual Consult TF / A7475 Prior Limited 0.00 Canceled 2018-11-09 2018-11-14 2018-11-16 2018-12-09 2019-06-07 ocurement of procurement C Management and Coordinati ant Selection onsultant. on NP-PEFA-91340-CS-INDV / To upgrade the newly formed U Component 1: Strengthening nified CoA to align with GFS Public Expenditure and Rev Manual 2014 in order to rem Individual Consult TF / A7475 enue Management in Federa Post Limited 0.00 Canceled 2018-12-14 2018-12-19 2019-01-09 2019-02-13 2019-08-12 ove redundancies, improve c ant Selection l and Subnational Governme oherence, and simplify codin nts g thereby capture all key fisc al information required for fis cal management decision ma king . NP-PEFA-91341-CS-INDV / Th e Consultant for this activity will manage a process for id entifying the best possible ar Component 4: PFM Reform Individual Consult chitecture for responsive and TF / A7475 Management and Coordinati Post Limited 4,076.79 Completed 2018-12-14 2018-12-13 2018-12-19 2018-12-16 2019-01-09 2019-01-03 2019-02-13 2019-01-24 2019-08-12 2019-04-09 ant Selection Multi-language website of Pu on blic Expenditure and Financia l Accountability , and develop the needed functionalities an d applications. NP-PEFA-108785-CS-INDV / P Component 4: PFM Reform Individual Consult rocurement of Procurement TF / A7474 Management and Coordinati Prior Open 0.00 Canceled 2019-04-03 2019-04-15 2019-04-16 2019-05-19 2019-11-15 ant Selection Consultant (Individual). on NP-FCGO-112757-CS-INDV / I Component 1: Strengthening nternational consultant for p Public Expenditure and Rev Individual Consult TF / A7474 Post Open 0.00 Canceled 2019-04-30 2019-06-18 2019-07-09 2019-08-13 2021-07-25 eer review and quality check enue Management in Federa ant Selection of NPSAS (on Intermittent ba l and Subnational Governme sis). nts Page 6 Component 1: Strengthening NP-FCGO-111410-CS-INDV / Public Expenditure and Rev Individual Consult Training Need assessment of TF / A7474 Post Limited 0.00 Canceled 2019-05-10 2019-05-20 2019-05-30 2019-06-10 2019-12-30 enue Management in Federa ant Selection FCGO and DTCO Staff . l and Subnational Governme nts Component 1: Strengthening NP-FCGO-111412-CS-INDV / Public Expenditure and Rev Individual Consult Consulting service for improv TF / A7474 Post Limited 0.00 Canceled 2019-05-10 2019-05-20 2019-05-30 2019-06-10 2019-12-30 enue Management in Federa ant Selection ing and simplifying COAs. l and Subnational Governme nts Component 1: Strengthening NP-ICAN-100208-CS-CDS / Q Public Expenditure and Rev uality Assurance Review Man TF / A7474 Post Direct Selection Direct 0.00 Canceled 2019-04-01 2019-04-13 2019-04-26 2019-06-10 enue Management in Federa ual for Small Practices l and Subnational Governme nts NP-ICAN-95604-CS-INDV / Co Component 1: Strengthening nsultant to support on activiti Public Expenditure and Rev Individual Consult TF / A7475 Post Limited 0.00 Canceled 2019-01-28 2019-02-12 2019-02-22 2019-03-07 2019-09-03 es directly and indirectly rela enue Management in Federa ant Selection ted to NFRS implementation l and Subnational Governme nts NP-ICAN-100213-CS-INDV / I ndividual Consultant for Moni Component 1: Strengthening toring and follow up of NFRS Public Expenditure and Rev Application liaison with differ Individual Consult TF / A7474 enue Management in Federa Post Limited 0.00 Canceled 2019-02-25 2019-03-17 2019-03-22 2019-04-11 2019-10-08 ent agencies, design and pre ant Selection l and Subnational Governme pare necessary documents fo nts r activities relating to NFRS fi nanced by the project, desig n layout of the program etc. NP-NPC-129891-CS-INDV / C Component 1: Strengthening onsulting Service for providin Public Expenditure and Rev Individual Consult TF / A7474 Post Limited 14,327.90 Completed 2019-09-09 2020-08-09 2019-09-14 2019-09-19 2019-09-15 2019-10-01 2019-10-13 2019-10-01 2020-10-12 2020-07-09 g technical and management enue Management in Federa ant Selection support to the NPC l and Subnational Governme nts NP-NPC-136098-CS-INDV / N Component 1: Strengthening ational Consultancy Services Public Expenditure and Rev Individual Consult Pending Impleme TF / A7474 Post Limited 0.00 2019-10-01 2019-10-06 2019-10-20 2019-11-24 2020-05-22 to Strengthen the Medium-Te enue Management in Federa ant Selection ntation rm Expenditure Framework l and Subnational Governme nts NP-FCGO-136734-CS-INDV / Component 1: Strengthening Procurement of consulting se Public Expenditure and Rev Individual Consult TF / A7474 Post Limited 4,134.13 Completed 2019-10-03 2019-12-19 2019-10-10 2020-01-03 2019-10-31 2020-01-10 2019-12-05 2020-01-24 2020-06-02 2020-09-16 rvice for preparing internal a enue Management in Federa ant Selection udit handbook. l and Subnational Governme nts NP-FCGO-136737-CS-INDV / Component 1: Strengthening Procurement of consulting se Public Expenditure and Rev Individual Consult rvice for assessment of inter TF / A7474 enue Management in Federa Post Limited 0.00 Canceled 2019-10-03 2019-10-03 2019-10-08 2019-10-29 2019-12-03 2020-05-31 ant Selection nal audit personnel and capa l and Subnational Governme city of existing human resour nts ces Component 1: Strengthening NP-PEFA-134002-CS-INDV / Public Expenditure and Rev Individual Consult Under Implement TF / A7474 Post Direct 0.00 2020-02-02 2021-09-09 2020-02-12 2020-03-04 2020-04-08 2020-10-05 Update PFM Reform strategy enue Management in Federa ant Selection ation l and Subnational Governme nts NP-PEFA-127936-CS-QBS / C Component 4: PFM Reform Individual Consult onsulting Services for the Pre TF / A7474 Management and Coordinati Post Direct 0.00 Canceled 2020-02-10 2020-02-20 2020-03-12 2020-04-16 2020-10-13 ant Selection paration of the Citizen Engag on ement Strategy NP-PEFA-154126-CS-INDV / P Component 1: Strengthening rocurement of Consulting Ser Public Expenditure and Rev Individual Consult TF / A7475 Post Direct 4,134.13 Completed 2020-01-22 2020-01-17 2020-02-01 2020-01-23 2020-02-22 2020-02-25 2020-03-28 2020-03-04 2020-09-24 2020-07-10 vices for Drafting Internal Au enue Management in Federa ant Selection dit Standards. l and Subnational Governme nts Component 1: Strengthening NP-FCGO-153564-CS-INDV / Public Expenditure and Rev Individual Consult Procurement of Information S TF / A7475 Post Direct 7,496.87 Completed 2020-01-22 2020-04-17 2020-02-01 2020-04-17 2020-02-22 2020-04-24 2020-03-28 2020-04-27 2020-09-24 2020-11-07 enue Management in Federa ant Selection ecurity Officer l and Subnational Governme nts NP-FCGO-157445-CS-INDV / Procurement of consulting se Component 1: Strengthening rvices for technical assistanc Public Expenditure and Rev e in Preparation of Financial Individual Consult TF / A7475 enue Management in Federa Post Direct 9,780.56 Completed 2020-02-07 2020-02-03 2020-02-14 2020-02-06 2020-03-06 2020-02-16 2020-04-10 2020-02-20 2020-10-07 2020-07-07 Statements of 2075/76 under ant Selection l and Subnational Governme Nepal Public Sector Accounti nts ng Standards (NPSAS) in the Central & Province level gove rnments entities in Nepal. NP-FCGO-187636-CS-INDV / Component 1: Strengthening Consulting services for revie Public Expenditure and Rev Individual Consult TF / A7474 Post Direct 3,790.34 Completed 2020-08-26 2020-08-05 2020-09-05 2021-06-02 2020-09-09 2021-06-03 2020-09-16 2021-06-04 2020-12-16 2021-07-04 w of equipments supporting I enue Management in Federa ant Selection T based PFM Systems of FCG l and Subnational Governme O. nts NP-FCGO-189914-CS-INDV / Component 1: Strengthening Consulting Service of Charter Public Expenditure and Rev Individual Consult TF / A7474 Post Open 7,037.75 Signed 2020-08-31 2020-12-04 2020-10-19 2021-01-07 2020-11-09 2021-01-28 2020-12-14 2021-01-31 2021-06-12 ed Accountant for Improving enue Management in Federa ant Selection CFS and NPSAS Based Report l and Subnational Governme ing nts NP-PEFA-197580-CS-CDS / Ci Component 4: PFM Reform tizen Budget (enhancement TF / A7474 Management and Coordinati Post Direct Selection Direct 0.00 Canceled 2020-10-31 2020-11-10 2020-12-25 2021-03-25 of PFM for all level Governme on nt with Stakeholder citizens NP-NPC-197779-CS-INDV / Hi Component 1: Strengthening re consultant to provide tech Public Expenditure and Rev Individual Consult Pending Impleme nical and management supp TF / A7475 enue Management in Federa Post Direct 0.00 2020-10-30 2020-11-05 2020-11-11 2020-11-21 2021-08-08 ant Selection ntation ort to IPFMRP project implem l and Subnational Governme entation unit (PIU) of NPC nts NP-NPC-206933-CS-INDV / D Component 1: Strengthening ata entry operator cum office Public Expenditure and Rev Individual Consult Under Implement TF / A7475 Post Direct 0.00 2020-11-30 2020-11-12 2020-12-10 2020-12-17 2020-12-31 2021-12-26 secretary for National Project enue Management in Federa ant Selection ation Bank l and Subnational Governme nts Component 1: Strengthening NP-NPC-206936-CS-INDV / IT Public Expenditure and Rev Individual Consult Pending Impleme support cum MIS supervisor f TF / A7475 Post Direct 0.00 2020-11-30 2020-12-10 2020-12-17 2020-12-31 2021-12-26 enue Management in Federa ant Selection ntation or National Project Bank l and Subnational Governme nts NP-NPC-239385-CS-INDV / D Component 1: Strengthening eveloping Provincial Project B Public Expenditure and Rev Individual Consult Under Implement TF / A7475 Post Direct 0.00 2021-06-13 2021-06-03 2021-06-17 2021-06-20 2021-06-23 2021-07-14 ank Management Information enue Management in Federa ant Selection ation System. l and Subnational Governme nts Page 7 NP-NPC-251235-CS-INDV / Pr Component 1: Strengthening ocurement of consulting serv Public Expenditure and Rev Individual Consult Pending Impleme TF / A7474 Post Limited 0.00 2021-09-14 2021-09-19 2021-10-10 2021-11-14 2022-07-15 ices of MIS Supervisor/Proces enue Management in Federa ant Selection ntation sor for NPB l and Subnational Governme nts NP-NPC-251232-CS-INDV / Pr Component 1: Strengthening ocurement of Consulting serv Public Expenditure and Rev Individual Consult Pending Impleme ices for providing technical a TF / A7474 enue Management in Federa Post Limited 0.00 2021-09-14 2021-09-19 2021-10-10 2021-11-14 2022-07-15 ant Selection ntation nd management support (Pr l and Subnational Governme ogram Officer) to NPBMIS. nts Component 1: Strengthening NP-FCGO-111413-CS-INDV / Public Expenditure and Rev Individual Consult Pending Impleme Consulting services for Upgra TF / A7474 Post Limited 0.00 2019-05-10 2019-05-20 2019-05-30 2019-06-10 2019-12-30 enue Management in Federa ant Selection ntation ding NPSAS . l and Subnational Governme nts NP-FCGO-111411-CS-INDV / Component 1: Strengthening Consulting service for develo Public Expenditure and Rev Individual Consult Pending Impleme TF / A7474 Post Limited 0.00 2019-05-10 2019-05-20 2019-05-30 2019-06-10 2019-12-30 ping longterm strategy of FC enue Management in Federa ant Selection ntation GO. l and Subnational Governme nts NP-NPC-206929-CS-INDV / D Component 1: Strengthening eveloping sectoral guidelines Public Expenditure and Rev Individual Consult for identification, appraisal a TF / A7475 enue Management in Federa Post Limited 0.00 Canceled 2020-11-30 2020-12-05 2020-12-20 2021-01-18 2021-07-17 ant Selection nd selection and prioritizatio l and Subnational Governme n of project for agriculture se nts ctor NP-NPC-206927-CS-INDV / D Component 1: Strengthening eveloping sectoral guidelines Public Expenditure and Rev Individual Consult for identification, appraisal a TF / A7475 enue Management in Federa Post Limited 0.00 Canceled 2020-11-30 2020-12-05 2020-12-20 2021-01-18 2021-07-17 ant Selection nd selection and prioritizatio l and Subnational Governme n of project for industry secto nts r NP-NPC-168777-CS-INDV / Pr Component 1: Strengthening ocurement of Consulting Ser Public Expenditure and Rev vices for Developing Sectoral Individual Consult TF / A7475 enue Management in Federa Post Limited 0.00 Canceled 2020-05-07 2020-05-12 2020-06-02 2020-07-07 2021-01-03 Guidelines for Identification, ant Selection l and Subnational Governme Appraisal and Selection & Pri nts oritization of Projects for Soci al Sector NP-NPC-168772-CS-INDV / Pr Component 1: Strengthening ocurement of Consulting Ser Public Expenditure and Rev vices for Developing Sectoral Individual Consult TF / A7475 enue Management in Federa Post Limited 0.00 Canceled 2020-05-07 2020-05-12 2020-06-02 2020-07-07 2021-01-03 Guidelines for Identification, ant Selection l and Subnational Governme Appraisal and Selection & Pri nts oritization of Project for Irriga tion Sector NP-NPC-153603-CS-INDV / Pr Component 1: Strengthening ocurement of Consulting Ser Public Expenditure and Rev vices for Developing Sectoral Individual Consult TF / A7475 enue Management in Federa Post Limited 0.00 Canceled 2020-01-22 2020-01-27 2020-02-17 2020-03-23 2020-09-19 Guidelines for Identification, ant Selection l and Subnational Governme Appraisal and Selection and nts Prioritization of Projects for T ransport Sector NP-NPC-153601-CS-INDV / Pr Component 1: Strengthening ocurement of Consulting Ser Public Expenditure and Rev vices for Developing Sectoral Individual Consult TF / A7475 enue Management in Federa Post Limited 0.00 Canceled 2020-01-22 2020-01-27 2020-02-17 2020-03-23 2020-09-19 Guidelines for Identification, ant Selection l and Subnational Governme Appraisal and Selection and nts Prioritization of Projects for E nergy Sector NP-NPC-153607-CS-INDV / D Component 1: Strengthening eveloping Sectoral Guideline Public Expenditure and Rev Individual Consult s for Identification, Appraisal, TF / A7475 enue Management in Federa Post Limited 0.00 Canceled 2020-01-21 2020-01-26 2020-02-16 2020-03-22 2020-09-18 ant Selection and Selection and Prioritizati l and Subnational Governme on of Projects for Urban Deve nts lopment NP-MOF-259703-CS-INDV / C Component 1: Strengthening onsulting services of Senior I Public Expenditure and Rev Individual Consult Under Implement TF / A7474 Post Limited 0.00 2021-10-26 2021-11-09 2021-10-31 2021-11-17 2021-11-21 2021-12-26 2022-06-24 T PFM Expert for developmen enue Management in Federa ant Selection ation t and support of LMBIS and P l and Subnational Governme LMBIS. nts NP-PEFA/ICAN-276402-CS-C DS / Procurement of consulta Component 4: PFM Reform nt service for Development/U TF / A7474 Management and Coordinati Post Direct Selection Direct 172,500.00 Signed 2022-02-10 2022-02-10 2022-02-20 2022-03-20 2022-04-26 2022-04-13 2022-10-23 pgrading/training/Printing of on Study Materials of CA Educati on and incorporation of PFM materials in ICAN Syllabus NP-MOF-280792-CS-INDV / C Component 1: Strengthening onsulting Service for User Ma Public Expenditure and Rev Individual Consult Pending Impleme nual, Operational Guidelines, TF / A7474 enue Management in Federa Post Direct 0.00 2022-03-04 2022-03-11 2022-03-13 2022-03-18 2022-06-16 ant Selection ntation System Manuals for Federal l and Subnational Governme & Provincial Governments on nts LMBIS/PLMBIS System. NP-FCGO-286587-CS-CDS / P Component 1: Strengthening rocurement of consulting ser Public Expenditure and Rev Under Implement vice for the development of TF / A7474 enue Management in Federa Post Direct Selection Direct 0.00 2022-03-24 2022-04-24 2022-04-02 2022-04-17 2022-07-16 ation Ministerial Financial Manage l and Subnational Governme ment Information System (M nts FMIS). NP-PEFA-305822-CS-CDS / p Component 4: PFM Reform Individual Consult rocurement of PFM National TF / A7474 Management and Coordinati Post Direct - National 7,044.73 Signed 2022-07-28 2022-08-01 2022-07-29 2022-08-03 2022-07-31 2022-08-05 2022-08-02 2022-08-07 2023-07-16 ant Selection Consulting Services for IPFM on RP . NP-PEFA-312327-CS-INDV / P Component 4: PFM Reform Individual Consult Under Implement rocurement of consultant ser TF / A7474 Management and Coordinati Post Direct - National 0.00 2022-08-26 2022-08-31 2022-08-28 2022-08-29 2022-08-31 2023-07-16 ant Selection ation vice on PFM for PEFA Secret on ariat NP-FCGO-325112-CS-INDV / Component 1: Strengthening Procurement of consulting se Public Expenditure and Rev Individual Consult Pending Impleme TF / A7474 Post Direct - National 0.00 2022-11-03 2022-11-13 2022-12-04 2023-01-08 2023-07-07 rvices for NPSAS document tr enue Management in Federa ant Selection ntation anslation l and Subnational Governme nts NP-PEFA-334509-CS-CDS / Pr ocurement of Consulting serv ice for developing Modules fo Component 4: PFM Reform Pending Impleme r Treasury Accounting , Forei TF / A7474 Management and Coordinati Post Direct Selection Direct - National 0.00 2023-01-10 2023-01-16 2023-01-27 2023-07-15 ntation gn assistance management a on nd divisible funds recording with enhancement of TSA an d CGAS. Page 8 NP-PEFA-337336-CS-CDS / Pr ocurement of Consulting Ser Component 4: PFM Reform Pending Impleme vice for Developing/Producin TF / A7474 Management and Coordinati Post Direct Selection Direct - National 0.00 2023-01-19 2023-01-29 2023-04-04 2023-10-01 ntation g awareness raising Short Fil on m on PFM related issues NP-MOF-343100-CS-CDS / Pr ocurement of Consulting Ser Component 1: Strengthening vice for Support, Maintenanc Public Expenditure and Rev e, Upgradation and Enhance Pending Impleme TF / A7474 enue Management in Federa Post Direct Selection Direct - National 0.00 2023-02-15 2023-02-25 2023-05-01 2023-10-28 ment of Line Ministry Budget ntation l and Subnational Governme Information System (LMBIS), nts Provincial Line Ministry Budg et Information System (PLMB IS) with Integration. Page 9