PROCUREMENT PLAN (Textual Part) Project information: Improving Connectivity and Urban Infrastructure in Cabo Verde - P178644 Implementation agency: UGPE (Unidade de Gestão de Projetos Especiais) Date of the Procurement Plan: April 24, 2023 Period covered by this Procurement Plan: April 24, 2022 - April 23, 2024 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. “Not Applicable” Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. “Not Applicable” Other Relevant Procurement Information. Retroactive Financing used shall be consistent with Sections I, II and III of these Procurement Regulations and within the limits specified in the Legal Agreement. PROCUREMENT Cabo Verde : Improving Connectivity and Urban Infrastructure in Cabo Verde PLAN General Information Country: Cabo Verde 2023-12-01 Bank’s Approval Date of the Original Procurement Plan: 2024-05-31 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178644 GPN Date: Project Name: Improving Connectivity and Urban Infrastructure in Cabo Verde Loan / Credit No: IDA / V4790, IDA / 74360, IDA / 74370 Ministry of Infrastructure, Territory Planning and Housing Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Documento Nacio nal de Licitação - O-ST-09/2023 / Reabilitation processo de 1 env Em fase de I and Constrution of Road Estr Solicitação de Ofe Single Stage - One E 2024-09-1 IDA / V4790 Posterior Open - National elope (Document 4,553,381.00 0.00 mplementa 2023-11-30 2023-12-22 2023-12-05 2024-01-16 2024-02-05 2024-02-15 2024-03-21 ada Saltos - Pingo Chuva - Ar rtas nvelope 7 o Não Padrão do ção ribada Banco Mundial - D ocumento Padrão de Aquisição Documento (DPA Nacio ) de Licitação - nal O-ST-01/2024 / Reabilitação processo de 1 env Solicitação de Ofe Open - Internationa Single Stage - One E 2024-11-1 e Asfaltagem da Estrada Fun IDA / V4790 Posterior elope (Document 2,906,413.00 0.00 Cancelado 2024-01-31 2024-01-30 2024-02-05 2024-03-18 2024-04-17 2024-05-22 rtas l nvelope 8 dura/Ribeira Barca o Não Padrão do Banco Mundial - D ocumento Padrão de Aquisição Documento (DPA Nacio N.º O-ST-05/2024/P178644_ ) de Licitação - nal 02/MIOTH / Reabilitação e Asf processo de 1 env Implementa Solicitação de Pro Single Stage - Two E 2026-05-1 altagem da Estrada EN3-ST-1 IDA / 74360 Posterior Open - National elope (Document 2,906,413.00 0.00 ção Pendent 2024-03-06 2024-05-22 2024-05-22 2024-03-11 2024-07-31 2024-10-13 2024-11-17 postas nvelope 1 8 Fundura – Ribeira da Barca, o Não Padrão do e na Ilha de Santiago Banco Mundial - D ocumento Padrão de Aquisição Documento (DPA Nacio Nº O- SA-02/2024/P178644_ ) de Licitação - nal 02/MIOTH / Empreitada de C processo de 1 env Implementa onstrução da Estrada de Pen Solicitação de Pro Single Stage - Two E 2026-06-1 IDA / 74360 Posterior Open - National elope (Document 1,937,609.00 0.00 ção Pendent 2024-04-10 2024-06-26 2024-06-26 2024-04-15 2024-09-04 2024-11-17 2024-12-22 etração na Ribeira Caibros (c postas nvelope 5 o Não Padrão do e alçada), na Ilha de Santo Ant Banco Mundial - D ão ocumento Padrão de Aquisição (DPA ) GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Nº C- ST-03/2024/P178644_ Seleção Baseada 02/MIOTH / Estudos e Projeto IDA / 74360 Posterior na Qualidade e Cu Open - National 100,000.00 0.00 Cancelado 2024-01-30 2024-02-20 2024-04-04 2024-05-02 2024-06-01 2024-07-06 2024-08-10 2025-08-10 de Execução para Construçã sto o da EN, Igreja – Cutelo Gom es, Ilha de Santiago Nº C- ST-05/2024/P178644_ 02/MIOTH / Estudos e Projeto Seleção Baseada de Execução para Reabilitaçã IDA / V4790 Posterior na Qualidade e Cu Open - National 96,880.00 0.00 Cancelado 2024-01-31 2024-02-21 2024-04-05 2024-05-03 2024-06-02 2024-07-07 2024-08-11 2025-08-11 o e Asfaltagem da Estrada Fu sto ndura/Ribeira da Barca, Ilha de Santiago C -ST-01/2024/P178644_01/ Seleção Baseada MIOTH / Elaboration of Projec Em fase de Imple IDA / V4790 Posterior nas Qualificações Open - National 38,752.00 0.00 2024-01-31 2024-02-07 2024-02-21 2024-04-05 2024-05-05 2024-06-09 2024-12-06 t for the Requalification of th mentação dos Consultores e Urban Center of João Teves Nº C- SN-04/2024/P178644_ Seleção Baseada 02/MIOTH / Estudos e Projeto IDA / 74360 Posterior na Qualidade e Cu Open - National 100,000.00 0.00 Cancelado 2024-01-30 2024-02-20 2024-04-04 2024-05-02 2024-06-01 2024-07-06 2024-08-10 2025-08-10 de Execução para Construçã sto o da EN, Juncalinho – Carriça l, Ilha São Nicolau Nº C- ST-06/2024/P178644_ 02/MIOTH / Fiscalização dos Seleção Baseada Em fase de Imple Trabalhos de Construção da IDA / 74360 Posterior na Qualidade e Cu Open - National 131,938.00 0.00 2024-03-06 2024-05-07 2024-03-27 2024-05-10 2024-06-07 2024-07-07 2024-08-11 2024-09-15 2025-09-15 mentação Estrada Circular de Cidade V sto elha (asfalto), Ilha de Santiag o Nº C- ST-08/2024/P178644_ 02/MIOTH / Fiscalização da E Seleção Baseada Em fase de Imple mpreitada de Reabilitação e IDA / 74360 Posterior na Qualidade e Cu Open - National 96,880.00 0.00 2024-02-14 2024-03-05 2024-03-06 2024-04-19 2024-05-17 2024-06-16 2024-07-21 2024-08-25 2025-08-25 mentação Asfaltagem da Estrada Fundu sto ra/Ribeira da Barca, Ilha de S antiago N.º C-ST-10/2024/P178644_ 02/MIOTH / Fiscalização da E Seleção Baseada Em fase de Imple mpreitada de Construção da IDA / 74360 Posterior na Qualidade e Cu Open - National 48,440.00 0.00 2024-05-29 2024-05-07 2024-06-19 2024-08-02 2024-08-30 2024-09-29 2024-11-03 2024-12-08 2025-12-08 mentação Estrada Igreja São Miguel - C sto utelo Gomes, Ilha de Santiag o Nº C- ST-01/2024/P178644_ Seleção Baseada 02/MIOTH / Supervision Cons Open - Internationa IDA / 74370 Posterior na Qualidade e Cu 160,000.00 0.00 Cancelado 2024-01-15 2024-01-16 2024-02-05 2024-03-20 2024-04-17 2024-05-17 2024-06-21 2024-07-26 2025-07-26 trution of Road Estrada Salto l sto s - Pingo Chuva - Arribada Page 1 Nº C- ST-11/2024/P178644_ 02/MIOTH / Fiscalização da E Seleção Baseada Implementação P mpreitada de Construção da IDA / 74360 Posterior na Qualidade e Cu Open - National 160,000.00 0.00 2024-02-14 2024-03-06 2024-04-19 2024-05-17 2024-06-16 2024-07-21 2024-08-25 2025-08-25 endente estrada Pingo Chuva - Saltos sto - Arribada, Ilha de Santiago C-SN-01/2024/P178644_01/ Seleção Baseada MIOTH / Elaboration of Projec Implementação P IDA / 74360 Posterior na Qualidade e Cu Open - National 58,128.00 0.00 2024-02-28 2024-03-20 2024-05-03 2024-05-31 2024-06-30 2024-08-04 2024-09-08 2025-09-08 t for the Urban Requalificatio endente sto n of the Seafront of Tarrafal de São Nicolau C-SV-02/2024/P178644_01/ Seleção Baseada Implementação P MIOTH / Elaboration of Projec IDA / 74360 Posterior na Qualidade e Cu Open - National 36,330.00 0.00 2024-02-21 2024-03-13 2024-04-26 2024-05-24 2024-06-23 2024-07-28 2024-09-01 2025-09-01 endente t for the Urban Requalificatio sto n of Covada Bruxa C-SN-02/2024/P178644_01/ Seleção Baseada MIOTH / Elaboration of Projec Implementação P IDA / 74360 Posterior na Qualidade e Cu Open - National 33,908.00 0.00 2024-02-28 2024-03-20 2024-05-03 2024-05-31 2024-06-30 2024-08-04 2024-09-08 2025-09-08 t for the Requalification of th endente sto e Historic Center of of Ribeira Brava Nº C- SA-02/2024/P178644_ 02/MIOTH / Fiscalização dos Seleção Baseada Implementação P Trabalhos de Construção da IDA / 74360 Posterior na Qualidade e Cu Open - National 96,880.00 0.00 2024-03-27 2024-04-17 2024-05-31 2024-06-28 2024-07-28 2024-09-01 2024-10-06 2025-10-06 endente Estrada de Acesso à Ribeira sto dos Bodes/Ribeira Fria, Ilha d e Santo Antão C-SV-01/2024/P178644_01/ Seleção Baseada Implementação P MIOTH / Elaboration of Projec IDA / 74360 Posterior na Qualidade e Cu Open - National 41,174.00 0.00 2024-02-21 2024-03-13 2024-04-26 2024-05-24 2024-06-23 2024-07-28 2024-09-01 2025-09-01 endente t for the Urban Requalificatio sto n of Fernando Pó Nº C- SA-09/2024/P178644_ 02/MIOTH / Fiscalização da E Seleção Baseada Open - Internationa Implementação P mpreitada de Construção da IDA / 74360 Posterior na Qualidade e Cu 96,880.00 0.00 2024-03-13 2024-04-03 2024-05-17 2024-06-14 2024-07-14 2024-08-18 2024-09-22 2025-09-22 l endente Estrada de penetração da Ri sto beira Caibros (calçada), Ilha de Santo Antão INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Nº C -ST-04/2024/P178644_ Em fase de Imple 02/MIOTH / Project Managem IDA / V4790 Posterior Individual Open - National 180,000.00 0.00 2024-01-19 2024-01-23 2024-03-04 2024-03-25 2024-04-29 2024-10-26 mentação ent for MIOTH Nº C -ST-12/2024/P178644_ Implementação P 02/MIOTH / Especialista Ambi IDA / 74360 Posterior Individual Open - National 22,500.00 0.00 2024-04-30 2024-06-18 2024-07-09 2024-08-13 2025-02-09 endente ental PMCIU CV-MIOTH-429149-CS-INDV / Implementação P RECRUITMENT OF AN INTERN IDA / 74360 Posterior Individual Open - National 20,160.00 0.00 2024-06-10 2024-07-29 2024-08-19 2024-09-23 2025-03-22 endente AL AUDITOR FOR THE PROJEC T Page 2