Procurement Plan General 1. Bank’s approval Date of the procurement Plan January 28, 2022 2. Date of General Procurement Notice: February 22, 2022 3. Period covered by this procurement plan: 18 Months (January 2022 to August, 2023) II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Annex II to the Regulation for Procurement: No. Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 2,000,000 All 2. NCB (Goods) Above US$ 2,000,000 All 3. ICB (Works) Above US$ 10,000,000 All 4. NCB (Works) Above US$ 10,000,000 All 5. (Non-Consultant Services) Above US$ 2,000,000 All 2. Prequalification. Bidders when applicable_ shall be prequalified in accordance with the provisions of paragraphs 6.23 and 6.24 of the Regulation. 3. Proposed Procedures for CDD Components (as per paragraph. 6.9 of the Regulations: Not applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Estimate Domesti Review Ref d Packag c by Bank . Description Cost es Prefere (Prior / Comments No. US$ nce Post) million (yes/no) January 17, 2022 Summary of the 1 RFB- 8.200 2 No Prior International/DIR. (Goods) Summary of the 2 RFB-National/RFQ 7.584 12 No Post (Goods) 3 Summary of the RFB-International, 9.000 1 No Prior Dir/Limited (Works) 4 Summary of the RFB-National/RFQ 13.049 9 No Post (Works) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Annex II to the Regulation Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods Above US$ 1,000,000 (Firms) 2. Single Source (Firms) All 3. Individual Above US$ 300,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of the Consultant Regulations 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref Description of Estimated Review . Assignment Cost Packag by Bank Commen No. US$ es (Prior / ts million Post) Summary of 2.000 3 Prior 1number of contracts that will be let under QCBS Summary of 26 2 number of 2.488 Post contracts that will January 17, 2022 be let under other methods January 17, 2022 PROCUREMENT Western and Central Africa : West Africa Food System Resilience Program (FSRP) Phase 2 PLAN General Information Country: Western and Central Africa 2022-05-24 Bank’s Approval Date of the Original Procurement Plan: 2024-05-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P178132 GPN Date: 2023-06-27 Project Name: West Africa Food System Resilience Program (FSRP) Phase 2 Loan / Credit No: IDA / V4240, IDA / 71950 Ministry of Food and Agriculture - Phase 2 Executing Agency(ies): WORKS Activity Reference No. / Estimated Actual Am Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification High SEA/SH R Procurement D Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Contract Complet Description Component Review Type Method Amount (U ount (US$ and Recommendation Signed Contract o. h cess (Y/N) isk ocument Type atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes ion S$) ) for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned National Procure GH-FSRP PHASE 2-368041-C Sustainability and Adaptive ment Document - W-DIR / Completion of rehabil 20,000,000.0 2026-02-1 IDA / 71950 Capacity of the Food System Prior Direct Selection Direct - National 1 Envelope proce 0.00 Canceled 2023-07-16 2023-07-21 2023-08-25 itation of KIS (Irrigation and d 0 0 's Productive Base ss (Non Bank-SPD rainage system, road networ ) k etc.) Request for Bids - GH-FSRP PHASE 2-368047-C Single Stage - One E Small Works SPD 2024-05-0 W-RFB / Rehabilitation of MO IDA / 71950 Project Management Post Request for Bids Open - National 450,000.00 0.00 Signed 2023-09-15 2023-08-25 2023-09-20 2023-08-25 2023-11-01 2023-09-26 2023-12-01 2023-10-10 2024-01-05 nvelope (1 envelope proce 4 FA Project Building for FSRP ss) GH-FSRP PHASE 2-379505-C Request for Bids - Sustainability and Adaptive W-RFB / Completion of rehabi Open - Internationa Single Stage - Two E Works (without pr 20,000,000.0 Under Imple 2027-04-0 IDA / 71950 Capacity of the Food System Prior Request for Bids 0.00 2023-10-30 2023-10-24 2023-11-04 2023-11-01 2023-12-16 2023-12-15 2024-02-28 2024-04-03 litation of KIS (Irrigation and l nvelope equalification) SP 0 mentation 3 's Productive Base drainage system, road netwo D rk etc. GH-FSRP PHASE 2-379505-C Request for Bids - Sustainability and Adaptive W-RFB -01 / Completion of re Open - Internationa Single Stage - Two E Works (without pr 20,000,000.0 Pending Imp 2026-11-2 IDA / 71950 Capacity of the Food System Prior Request for Bids 0.00 2024-04-15 2024-05-27 2024-08-05 2024-10-18 2024-11-22 habilitation of KIS (Irrigation l nvelope equalification) SP 0 lementation 2 's Productive Base and drainage system, road n D etwork etc. GOODS Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-FSRP PHASE 2-368022-N Request for Quota Single Stage - One E C-RFQ / Procurement of ICT e IDA / 71950 Project Management Post Limited 97,000.00 0.00 Signed 2023-08-06 2023-07-12 2023-10-01 2023-10-31 tions nvelope quipment for FSRP (Laptops and Copiers) GH-FSRP PHASE 2-368025-G O-RFQ / Procurement of 120 Request for Quota Single Stage - One E Under Imple IDA / 71950 Project Management Post Limited 60,000.00 0.00 2023-08-06 2023-08-18 2023-10-01 2023-11-30 No. Monitoring and Evaluatio tions nvelope mentation n tools (tablets) for data colle ction GH-FSRP PHASE 2-373463-G O-RFB / Procurement of Proje Single Stage - One E ct Vehicles for FSRP (2no. sta IDA / 71950 Project Management Post Request for Bids Open - National 819,000.00 0.00 Signed 2023-10-15 2023-08-24 2023-10-20 2023-08-25 2023-12-01 2023-09-26 2023-12-31 2024-01-31 2024-02-04 2024-08-02 nvelope tion wagons, 8no. pickups, 1 no. saloon and 4no. motorcy cles) GH-FSRP PHASE 2-376363-G O-RFB / Supply and install 20 Single Stage - One E no, customized automated w IDA / 71950 Project Management Post Request for Bids Limited 1,300,000.00 0.00 Signed 2023-10-15 2023-09-04 2023-10-20 2023-09-04 2023-12-01 2023-09-28 2023-12-31 2024-01-26 2024-02-04 2024-08-02 nvelope eather stations (AWS) at GM ET synoptic stations for grou nd truthing satellite data GH-FSRP PHASE 2-382195-G O-RFB / Supply of inputs for s Sustainability and Adaptive mallholder farmers (35,000 N Single Stage - One E IDA / 71950 Capacity of the Food System Prior Request for Bids Open - National 2,600,000.00 0.00 Signed 2023-09-28 2023-10-16 2023-10-03 2023-10-24 2023-11-14 2023-12-01 2023-12-14 2024-02-12 2024-01-18 2024-04-17 PK, 17,500 UREA, 35, 000 We nvelope 's Productive Base edicides) of 50kg bags in sel ected intervention Project Ar eas. GH-FSRP PHASE 2-368039-G O-RFQ / Refurbishment of mi nister's conference room _su Request for Quota Single Stage - One E Under Imple IDA / 71950 Project Management Post Limited 70,000.00 0.00 2024-01-24 2024-01-17 2024-03-20 2024-05-19 pply of audio visuals complet tions nvelope mentation e, 20no. conference room ch airs, rehabilitation of confere nce room etc GH-FSRP PHASE 2-401959-G Sustainability and Adaptive O-RFB / Supply of Fertilizers ( Open - Internationa Single Stage - One E IDA / 71950 Capacity of the Food System Prior Request for Bids 9,260,000.00 0.00 Canceled 2024-01-12 2024-01-29 2024-01-15 2024-02-12 2024-02-26 2024-03-11 2024-04-10 190,577 Urea of 50kg bags) l nvelope 's Productive Base and (381,154 litres of Weedic ides) for smallholders GH-FSRP PHASE 2-401956-G Sustainability and Adaptive Open - Internationa Single Stage - One E O-RFB / Supply of Fertilizers f IDA / 71950 Capacity of the Food System Prior Request for Bids 20,530,000.00 0.00 Canceled 2024-01-12 2024-01-15 2024-02-12 2024-02-26 2024-03-11 2024-04-10 l nvelope or smallholders (562,430 NP 's Productive Base K of 50kg bags) GH-FSRP PHASE 2-401960-G O-RFB / Supply of Seeds for s Sustainability and Adaptive mallholder farmers (1,974,31 Open - Internationa Single Stage - One E IDA / 71950 Capacity of the Food System Prior Request for Bids 10,210,000.00 0.00 Canceled 2024-01-12 2024-01-15 2024-02-12 2024-02-26 2024-03-11 2024-04-10 2kg of rice, 679,866 kg of Ma l nvelope 's Productive Base ize hybrid, 62,219kg of Maize Pioneer (5kg per bag) and 1, 399,689 g of Vegetable seed s GH-FSRP PHASE 2-409674-G Sustainability and Adaptive O-RFB / Supply of weedicides Single Stage - One E IDA / 71950 Capacity of the Food System Prior Request for Bids Open - National 2,770,988.28 0.00 Signed 2024-02-15 2024-02-21 2024-02-17 2024-02-22 2024-03-18 2024-03-08 2024-04-01 2024-03-25 2024-04-18 2024-04-23 2024-05-18 - (381,154 litres of Weedicide nvelope 's Productive Base s) for smallholders GH-FSRP PHASE 2-409680-G Sustainability and Adaptive O-RFB / Supply of Seeds for s Single Stage - One E IDA / 71950 Capacity of the Food System Prior Request for Bids Open - National 2,961,468.00 0.00 Signed 2024-02-15 2024-02-21 2024-02-17 2024-02-22 2024-03-18 2024-03-08 2024-04-01 2024-03-25 2024-04-18 2024-04-23 2024-05-18 mallholder farmers (1,974,31 nvelope 's Productive Base 2kg of rice-5kg per bag) GH-FSRP PHASE 2-409684-G Sustainability and Adaptive O-RFB / Supply of Vegetables Single Stage - One E IDA / 71950 Capacity of the Food System Prior Request for Bids Open - National 1,679,626.80 0.00 Signed 2024-02-15 2024-02-22 2024-02-17 2024-02-21 2024-03-18 2024-03-08 2024-04-01 2024-04-09 2024-04-18 2024-05-18 1,399,689 g of Vegetable see nvelope 's Productive Base ds Southern/Middle/Northern Zones Page 1 GH-FSRP PHASE 2-409687-G Sustainability and Adaptive O-RFB / Supply of Fertilizer fo Open - Internationa Single Stage - One E IDA / 71950 Capacity of the Food System Prior Request for Bids 6,158,612.45 0.00 Signed 2024-02-15 2024-02-21 2024-02-17 2024-02-22 2024-03-18 2024-02-23 2024-04-01 2024-03-21 2024-04-18 2024-05-18 r smallholder in the Northern l nvelope 's Productive Base zone (168,729 NPK of 50kg b ags) GH-FSRP PHASE 2-409691-G Sustainability and Adaptive O-RFB / Supply of Fertilizer fo Open - Internationa Single Stage - One E IDA / 71950 Capacity of the Food System Prior Request for Bids 8,211,480.63 0.00 Signed 2024-02-15 2024-02-21 2024-02-17 2024-02-22 2024-03-18 2024-03-08 2024-04-01 2024-03-21 2024-04-18 2024-05-18 r smallholder in the Middle zo l nvelope 's Productive Base ne (224,972 NPK of 50kg bag s) GH-FSRP PHASE 2-409692-G Sustainability and Adaptive O-RFB / Supply of Fertilizer fo Open - Internationa Single Stage - One E IDA / 71950 Capacity of the Food System Prior Request for Bids 6,158,612.45 0.00 Signed 2024-02-15 2024-02-21 2024-02-17 2024-02-22 2024-03-18 2024-03-08 2024-04-01 2024-03-22 2024-04-18 2024-04-10 2024-05-18 r smallholder in the Southern l nvelope 's Productive Base zone (168,729 NPK of 50kg b ags) GH-FSRP PHASE 2-409694-G Sustainability and Adaptive Open - Internationa Single Stage - One E O-RFB / Supply of Fertilizers ( IDA / 71950 Capacity of the Food System Prior Request for Bids 6,479,618.00 0.00 Signed 2024-02-15 2024-02-21 2024-02-17 2024-02-22 2024-03-18 2024-03-08 2024-04-01 2024-03-21 2024-04-18 2024-05-18 l nvelope 190,577 Urea of 50kg bags) f 's Productive Base or smallholders GH-FSRP PHASE 2-409695-G O-RFB / Supply of Seeds for s Sustainability and Adaptive Open - Internationa Single Stage - One E mallholder farmers (679,866 IDA / 71950 Capacity of the Food System Prior Request for Bids 6,588,573.00 0.00 Signed 2024-02-15 2024-02-21 2024-02-17 2024-02-22 2024-03-18 2024-03-08 2024-04-01 2024-03-25 2024-04-18 2024-04-23 2024-05-18 l nvelope kg of Maize hybrid, 62,219kg 's Productive Base of Maize Pioneer(5kg per bag ) GH-FSRP PHASE 2-412005-G Sustainability and Adaptive O-RFB / Supply and distributi Single Stage - One E Under Imple IDA / 71950 Capacity of the Food System Post Request for Bids Open - National 900,000.00 0.00 2024-03-29 2024-03-28 2024-04-12 2024-04-05 2024-06-21 2024-08-20 2024-09-24 2024-12-23 on 150no. motorbikes to Agri nvelope mentation 's Productive Base c Extension Officers for FSRP. GH-FSRP PHASE 2-420168-G Digital Advisory Services for O-RFB / Procurement of 3000 Single Stage - One E Under Imple IDA / 71950 Agriculture and Food Crisis P Post Request for Bids Open - National 1,965,000.00 0.00 2024-04-15 2024-04-07 2024-04-29 2024-04-07 2024-07-08 2024-08-07 2024-09-11 2024-10-11 no. tablets and 327no. laptop nvelope mentation reventionand Management s for AEAs and other MOFA u nits GH-FSRP PHASE 2-420175-G Digital Advisory Services for O-RFP / Establishment of Net Request for Propo Single Stage - Two E Under Imple IDA / 71950 Agriculture and Food Crisis P Prior Open - National 4,700,000.00 0.00 2024-04-15 2024-05-12 2024-05-13 2024-05-20 2024-06-12 2024-08-25 2024-09-29 2024-12-28 work Operation Centre for M sals nvelope mentation reventionand Management OFA- Data centre and networ king equipment GH-FSRP PHASE 2-428993-G Sustainability and Adaptive O-RFB / Supply of Tomatoes Single Stage - One E Pending Impl IDA / 71950 Capacity of the Food System Post Request for Bids Limited - National 550,000.00 0.00 2024-06-17 2024-06-22 2024-08-03 2024-09-02 2024-10-07 2024-12-06 Seeds (450000 g) for MOFA p nvelope ementation 's Productive Base lanting season 2024 GH-FSRP PHASE 2-429518-G O-RFB / Supply, Installation a Digital Advisory Services for Single Stage - One E Pending Impl nd Training- Provision of an i IDA / 71950 Agriculture and Food Crisis P Prior Request for Bids Open - National 2,800,000.00 0.00 2024-06-28 2024-07-12 2024-08-23 2024-10-22 2024-11-26 2025-05-25 nvelope ementation ntegrated meteorological sol reventionand Management ution for the harmonization o f GMET systems. NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Loan / Credit N Market Approac Procurement Pro Prequalification Estimated Am Actual Amount Process St Draft Pre-qualification Prequalification Evalu Draft Bidding Docum Specific Procurement Bidding Documents a Proposal Submission / Description Component Review Type Method and Recommendation Signed Contract Contract Completion o. h cess (Y/N) ount (US$) (US$) atus Documents ation Report ent / Justification Notice / Invitation s Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-FSRP PHASE 2-312496-N Request for Quota Single Stage - One E C-RFQ / Supply and Installati IDA / 71950 Project Management Post Limited 10,000.00 0.00 Signed 2022-09-26 2023-06-14 2022-11-21 2023-08-05 2023-01-20 tions nvelope on of Accounting Software GH-FSRP PHASE 2-411998-N C-RFQ / Production of footag Request for Quota Single Stage - One E Under Imple es/ video documentaries of b IDA / 71950 Project Management Post Open - National 50,000.00 0.00 2024-04-12 2024-04-26 2024-08-06 2024-11-04 tions nvelope mentation aseline conditions of facilities to be rehabilitated by project CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Expression of Interest Short List and Draft R Request for Proposals Opening of Technical Evaluation of Technic Description Component Review Type Method Process Status Terms of Reference Report and Draft Neg Signed Contract Contract Completion o. h unt (US$) (US$) Notice equest for Proposals as Issued Proposals / Minutes al Proposal otiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-FSRP PHASE 2-295997-C S-CQS / Consultancy services Sustainability and Adaptive for Feasibility studies of Lot 1 Consultant Qualifi IDA / V4240 Capacity of the Food System Post Limited 100,000.00 0.00 Signed 2022-06-07 2022-10-05 2022-06-21 2022-11-15 2022-07-05 2023-06-15 2022-08-02 2023-07-02 2022-09-21 : Development of inland valle cation Selection 's Productive Base ys at Jeduako, Asare Nkwant a rice valley (Skere Central), and Agona (Skyere South) GH-FSRP PHASE 2-296002-C S-CQS / Consultancy services Sustainability and Adaptive for Feasibility studies of Lot 2 Consultant Qualifi IDA / V4240 Capacity of the Food System Post Limited 100,000.00 0.00 Signed 2022-06-08 2022-10-05 2022-06-22 2022-11-11 2022-07-07 2023-06-15 2022-08-04 2023-07-04 2022-09-23 : Development of inland valle cation Selection 's Productive Base ys at Barekese (Atwima Nwa biagya), Juaben (Juaben), an d Donuaso (Ejusu) GH-FSRP PHASE 2-299185-C Consultant Qualifi S-CQS / Consultancy Service IDA / V4240 Project Management Post Limited 80,000.00 0.00 Signed 2022-06-15 2022-06-09 2022-06-29 2022-06-27 2022-07-14 2023-06-15 2022-08-07 2023-07-04 2022-09-26 cation Selection for the baseline survey for FS RP GH-FSRP PHASE 2-323066-C S-CQS / CONSULTANCY FOR THE PREPARATION OF ENVIR Sustainability and Adaptive ONMENTAL AND SOCIAL IMP Consultant Qualifi IDA / 71950 Capacity of the Food System Post Limited 80,000.00 0.00 Signed 2022-11-17 2022-11-15 2022-12-01 2022-11-22 2022-12-31 2023-09-13 2023-02-04 2023-10-19 2023-08-03 ACTS ASSESSMENT (ESIA) AN cation Selection 's Productive Base D ENVIRONMENTAL AND SOC IAL MANAGEMENT PLANS (ES MPs) FOR SELECTED INLAND VALLEYS IN THE ASHANTI RE GION- LOT 1 GH-FSRP PHASE 2-323065-C S-CQS / CONSULTANCY FOR THE PREPARATION OF ENVIR Sustainability and Adaptive ONMENTAL AND SOCIAL IMP Consultant Qualifi IDA / 71950 Capacity of the Food System Post Limited 80,000.00 0.00 Signed 2022-11-17 2022-11-15 2022-12-01 2022-11-22 2022-12-31 2023-09-13 2023-02-04 2023-10-19 2023-08-03 ACTS ASSESSMENT (ESIA) AN cation Selection 's Productive Base D ENVIRONMENTAL AND SOC IAL MANAGEMENT PLANS (ES MPs) FOR SELECTED INLAND VALLEYS IN THE ASHANTI RE GION- LOT 2 Page 2 GH-FSRP PHASE 2-323064-C S-CQS / CONSULTANCY FOR THE PREPARATION OF ENVIR Sustainability and Adaptive ONMENTAL AND SOCIAL IMP Consultant Qualifi IDA / 71950 Capacity of the Food System Post Limited 80,000.00 0.00 Signed 2022-11-17 2022-11-15 2022-12-01 2022-11-22 2022-12-31 2023-09-13 2023-02-04 2023-10-19 2023-08-03 ACTS ASSESSMENT (ESIA) AN cation Selection 's Productive Base D ENVIRONMENTAL AND SOC IAL MANAGEMENT PLANS (ES MPs) FOR SELECTED INLAND VALLEYS IN THE ASHANTI RE GION- LOT 3 GH-FSRP PHASE 2-323063-C S-CQS / CONSULTANCY FOR THE PREPARATION OF ENVIR Sustainability and Adaptive ONMENTAL AND SOCIAL IMP Consultant Qualifi IDA / 71950 Capacity of the Food System Post Limited 150,000.00 0.00 Signed 2022-11-17 2022-11-11 2022-12-01 2022-11-22 2022-12-31 2023-09-15 2023-02-04 2023-10-19 2023-08-03 ACTS ASSESSMENT (ESIA) AN cation Selection 's Productive Base D ENVIRONMENTAL AND SOC IAL MANAGEMENT PLANS (ES MPs) FOR SELECTED INLAND VALLEYS IN THE BONO EAST REGION GH-FSRP PHASE 2-323067-C S-CQS / Consultancy for the f Sustainability and Adaptive easibility Studies for develop Consultant Qualifi IDA / 71950 Capacity of the Food System Post Limited 200,000.00 0.00 Signed 2022-11-30 2022-11-11 2022-12-14 2022-12-12 2023-01-13 2023-08-23 2023-02-17 2023-10-25 2023-08-16 ment of selected Inland Valle cation Selection 's Productive Base ys for improved Rainfed Agri cultural Production Bono East -LOT 3 GH-FSRP PHASE 2-323068-C S-CQS / Consultancy for the f Sustainability and Adaptive easibility Studies for develop Consultant Qualifi IDA / 71950 Capacity of the Food System Post Limited 200,000.00 0.00 Signed 2022-11-30 2022-11-11 2022-12-14 2022-12-12 2023-01-13 2023-08-23 2023-02-17 2023-10-25 2023-08-16 ment of selected Inland Valle cation Selection 's Productive Base ys for improved Rainfed Agri cultural Production Bono East -LOT 4 GH-FSRP PHASE 2-312497-C S-CQS / Consultancy Service Consultant Qualifi IDA / 71950 Project Management Post Limited 25,000.00 0.00 Canceled 2022-10-05 2022-10-19 2022-11-18 2022-12-23 2023-06-21 for Updating of National Irrig cation Selection ation Policy and Strategic Pla n for GIDA GH-FSRP PHASE 2-343254-C Digital Advisory Services for S-CQS / Consultancy Service Consultant Qualifi IDA / V4240 Agriculture and Food Crisis P Post Limited 80,000.00 0.00 Signed 2023-02-22 2023-07-10 2023-03-08 2023-07-10 2023-04-07 2024-02-23 2023-05-12 2023-11-08 for the assessment of the Hy cation Selection reventionand Management dromet, Agrimet, and Agro-a dvisory Systems GH-FSRP PHASE 2-347906-C S-CQS / Consultancy Service Sustainability and Adaptive for Update of Engineering De Consultant Qualifi IDA / V4240 Capacity of the Food System Post Limited 80,000.00 0.00 Canceled 2023-05-16 2023-05-03 2023-05-30 2023-06-29 2023-08-03 2024-01-30 sign and Construction Superv cation Selection 's Productive Base ision for the rehabilitation of the Tanoso Irrigation Scheme (TIS) GH-FSRP PHASE 2-365051-C Consultant Qualifi S-CQS / Recruitment of Cons IDA / 71950 Project Management Post Limited 30,000.00 0.00 Signed 2023-06-12 2023-08-03 2023-06-26 2023-08-15 2023-07-26 2024-01-18 2023-08-30 2023-11-28 cation Selection ultant to develop Project We bsite GH-FSRP PHASE 2-343156-C Least Cost Selecti S-LCS / Consultancy for Finan IDA / V4240 Project Management Post Open - National 90,000.00 0.00 Signed 2023-06-16 2023-06-15 2023-06-30 2023-07-25 2023-07-20 2023-08-16 2023-07-25 2023-09-15 2023-08-04 2023-09-29 2023-08-22 2023-10-17 2023-09-08 2023-10-08 on cial Audit for FSRP (FISCAL Ye ar 2022-2025) GH-FSRP PHASE 2-376440-C S-QCBS / Engagement of NG O to support the implementa Sustainability and Adaptive Quality And Cost- tion of Integrated Land Mana IDA / 71950 Capacity of the Food System Prior Open - National 2,000,000.00 0.00 Under Review 2023-10-15 2024-05-18 2023-11-05 2023-12-19 2024-01-16 2024-02-15 2024-03-21 2024-04-25 2028-03-01 Based Selection gement (ILM) activities under 's Productive Base FSRP intervention areas-Targ et Area 1-Eastern Region, Gr eater Accra and Central Regi on GH-FSRP PHASE 2-376443-C S-QCBS / Engagement of NG O to support the implementa Sustainability and Adaptive tion of Integrated Land Mana Quality And Cost- IDA / 71950 Capacity of the Food System Prior Open - National 2,000,000.00 0.00 Under Review 2023-10-15 2024-05-18 2023-11-05 2023-12-19 2024-01-16 2024-02-15 2024-03-21 2024-04-25 2028-04-24 gement (ILM) activities under Based Selection 's Productive Base FSRP intervention areas-Targ et Area 2- Northern Region, North-East Region and Upper East Region GH-FSRP PHASE 2-376430-C S-QCBS / Engagement of NG O to support the implementa Sustainability and Adaptive Quality And Cost- tion of Integrated Land Mana IDA / 71950 Capacity of the Food System Prior Open - National 2,000,000.00 0.00 Under Review 2023-10-15 2024-05-16 2023-11-05 2023-12-19 2024-01-16 2024-02-15 2024-03-21 2024-04-25 2028-04-24 Based Selection gement (ILM) activities under 's Productive Base FSRP intervention areas-Targ et Area 3- Ashanti Region, Bo no Region and Bono East Reg ion GH-FSRP PHASE 2-376554-C Digital Advisory Services for S-QCBS / Recruitment of con Quality And Cost- IDA / 71950 Agriculture and Food Crisis P Prior Open - National 2,000,000.00 0.00 Canceled 2023-10-15 2023-11-05 2023-12-19 2024-01-16 2024-02-15 2024-03-21 2024-04-25 2026-04-25 sultant to develop Ghana Agr Based Selection reventionand Management iculture & Agribusiness Platfo rm for MOFA GH-FSRP PHASE 2-381624-C S-QCBS / Recruitment of con Sustainability and Adaptive Quality And Cost- Under Implement sultants for the design and c IDA / 71950 Capacity of the Food System Post Open - National 450,000.00 0.00 2023-09-28 2023-10-04 2023-10-19 2023-10-11 2023-12-18 2023-11-22 2024-01-15 2023-12-21 2024-03-15 2024-01-12 2024-04-19 2024-05-24 2025-11-15 Based Selection ation onstruction supervision of ve 's Productive Base terinary laboratories in Accra and Dormaa GH-FSRP PHASE 2-381629-C S-QCBS / Recruitment of con Sustainability and Adaptive sultants for design and const Quality And Cost- Pending Impleme IDA / 71950 Capacity of the Food System Post Open - National 350,000.00 0.00 2023-10-31 2023-11-21 2024-01-04 2024-02-01 2024-03-02 2024-04-06 2024-05-11 2025-11-02 ruction supervision of labs (G Based Selection ntation 's Productive Base ene bank labs, tissue culture labs, etc.) for SRI, WRI and G LDB. GH-FSRP PHASE 2-382711-C S-QCBS / Consultancy for des Sustainability and Adaptive Quality And Cost- Open - Internationa Under Implement ign and construction supervis IDA / 71950 Capacity of the Food System Post 750,000.00 0.00 2023-10-30 2023-10-13 2023-11-20 2024-01-19 2024-02-16 2024-04-16 2024-05-21 2024-06-25 2026-12-12 Based Selection l ation ion of rehabilitation of WETA 's Productive Base irrigation scheme (WIS) GH-FSRP PHASE 2-409669/2 4-CS-QCBS / Consultancy Ser Sustainability and Adaptive vice for the Update of Engine Quality And Cost- Open - Internationa Under Implement IDA / 71950 Capacity of the Food System Post 790,000.00 0.00 2024-02-20 2024-02-15 2024-03-31 2024-02-15 2024-05-12 2024-05-15 2024-06-05 2024-06-29 2024-07-20 2025-05-04 ering Design and Constructio Based Selection l ation 's Productive Base n Supervision for the Rehabili tation of the Tanoso Irrigatio n Scheme (TaIS) Page 3 GH-FSRP PHASE 2-379503-C S-CQS / Recruitment of consu Digital Advisory Services for Consultant Qualifi ltant to develop TORs of mod IDA / V4240 Agriculture and Food Crisis P Post Open - National 220,000.00 0.00 Canceled 2023-09-28 2023-10-06 2023-10-28 2023-10-11 2024-01-26 2024-03-26 2024-04-30 2024-07-29 cation Selection ules under Ghana Agriculture reventionand Management & Agribusiness Platform for MOFA INDIVIDUAL CONSULTANTS Activity Reference No. / Loan / Credit N Market Approac Contract Type Estimated Amo Actual Amount Invitation to Identifie Draft Negotiated Cont Description Component Review Type Method Process Status Terms of Reference Signed Contract Contract Completion o. h unt (US$) (US$) d/Selected Consultant ract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GH-FSRP PHASE 2-296005-C S-INDV / Consultancy service Individual Consult IDA / V4240 Project Management Post Direct 40,000.00 0.00 Canceled 2022-06-06 2022-07-20 2022-06-16 2022-07-07 2022-08-11 2022-09-10 to prepare ESIA Lot 1: Wheta ant Selection & Tanoso Irrigation Schemes GH-FSRP PHASE 2-296009-C S-INDV / Consultancy service Individual Consult to prepare ESIA Lot 2: Jeduak IDA / V4240 Project Management Post Direct 40,000.00 0.00 Canceled 2022-06-09 2022-07-22 2022-06-19 2022-07-10 2022-08-14 2022-09-13 ant Selection o, Asare Nkwanta, Barekese, Agona, Juaben, and Donuaso Inland Valleys GH-FSRP PHASE 2-296019-C S-CDS / Consultancy service f Sustainability and Adaptive or the preparation of the da IDA / V4240 Capacity of the Food System Post Direct Selection Direct 80,000.00 0.00 Signed 2022-05-31 2022-06-21 2022-06-10 2023-09-22 2022-08-14 2022-09-13 m safety assessment ( Tanos 's Productive Base o, Wheta and affected Inland valleys) GH-FSRP PHASE 2-296338-C S-INDV / Consultancy service Individual Consult for Identification of appropria IDA / V4240 Project Management Post Limited 25,000.00 0.00 Signed 2022-06-08 2022-06-21 2022-06-13 2022-07-05 2022-07-04 2022-08-26 2022-08-08 2022-11-20 2022-09-07 ant Selection te grant model to support th e youth, women and SMEs GH-FSRP PHASE 2-296339-C S-INDV / Recruitment of Cons Individual Consult IDA / V4240 Project Management Post Limited 80,000.00 0.00 Signed 2022-06-10 2022-06-01 2022-06-15 2022-07-13 2022-07-06 2022-07-19 2022-08-10 2022-08-15 2022-09-29 ultant to develop Project Impl ant Selection ementation Manual GH-FSRP PHASE 2-296340-C S-INDV / Recruitment of Cons Individual Consult IDA / V4240 Project Management Post Limited 30,000.00 0.00 Canceled 2022-06-15 2022-08-30 2022-06-20 2022-07-11 2022-08-15 2022-09-24 ultant to develop Project Co ant Selection mmunications Strategy GH-FSRP PHASE 2-296342-C Individual Consult S-INDV / Recruitment of Cons IDA / V4240 Project Management Post Limited 50,000.00 0.00 Signed 2022-06-08 2022-06-07 2022-06-13 2022-06-09 2022-07-04 2022-07-25 2022-08-08 2022-08-12 2022-09-27 ant Selection ultant to develop project M& E manuals MOFA/FSRP/PPA/IC/2022/07 / Recruitment of Social Safegu IDA / V4240 Project Management Post Direct Selection Direct 45,000.00 54,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-02-02 2022-09-15 ard Specialist for FSRP MOFA/FSRP/PPA/IC/2022/04 / Recruitment of Procurement IDA / V4240 Project Management Post Direct Selection Direct 25,000.00 35,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-22 2022-09-15 Specialist for FSRP MOFA/FSRP/PPA/IC/2022/05 / Recruitment of Financial Ma IDA / V4240 Project Management Post Direct Selection Direct 55,000.00 66,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-02-02 2022-09-15 nagement Specialist for FSRP MOFA/FSRP/PPA/IC/2022/10 / IDA / V4240 Project Management Post Direct Selection Direct 45,000.00 54,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-02-02 2022-09-15 Recruitment of Agric Econom ist for FSRP MOFA/FSRP/PPA/IC/2022/06 / Recruitment of Agribusiness IDA / V4240 Project Management Post Direct Selection Direct 50,000.00 60,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-02-02 2022-09-15 Specialist for FSRP MOFA/FSRP/PPA/IC/2022/09 / Recruitment of Environment IDA / V4240 Project Management Post Direct Selection Direct 45,000.00 54,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-02-02 2022-09-15 al Safeguard Specialist for FS RP MOFA/FSRP/PPA/IC/2022/03 / Recruitment of Snr. Rural Inf IDA / V4240 Project Management Post Direct Selection Direct 50,000.00 60,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-01-22 2022-09-15 rastructure Engineer for FSRP MOFA/FSRP/PPA/IC/2022/01 / Recruitment of Project Coord IDA / V4240 Project Management Post Direct Selection Direct 65,000.00 78,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-02-02 2022-09-15 inator for FSRP MOFA/FSRP/PPA/IC/2022/08 / IDA / V4240 Project Management Post Direct Selection Direct 45,000.00 54,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-02-02 2022-09-15 Recruitment of M & E Specia list for FSRP MOFA/FSRP/PPA/IC/2022/02 / Recruitment of Opration Ma IDA / V4240 Project Management Post Direct Selection Direct 55,000.00 66,000.00 Signed 2022-01-03 2022-01-03 2022-01-13 2021-12-30 2022-03-19 2022-02-02 2022-09-15 nager for FSRP GH-FSRP PHASE 2-298765-C S-INDV / Consultancy service Individual Consult IDA / V4240 Project Management Post Direct 40,000.00 0.00 Signed 2022-06-20 2022-06-09 2022-06-30 2022-09-28 2022-07-21 2022-09-29 2022-08-11 2022-12-06 2022-09-20 to Update ESIA for KIS and V ant Selection EA Irrigation Schemes GH-FSRP PHASE 2-295995-C S-CDS / Consultancy services Sustainability and Adaptive to Update, Review UPDATE O IDA / V4240 Capacity of the Food System Post Direct Selection Direct 80,000.00 0.00 Signed 2022-07-20 2022-07-26 2022-07-30 2022-10-26 2022-10-03 2023-06-24 2022-11-12 F DAM SAFETY ASSESSMENT 's Productive Base OF VEA DAM Irrigation Sche me GH-FSRP PHASE 2-312495-C Individual Consult S-INDV / Recruitment of Proc IDA / 71950 Project Management Prior Open - National 60,000.00 0.00 Signed 2022-09-13 2022-09-14 2022-11-01 2023-01-06 2022-11-22 2023-02-21 2022-12-27 2023-02-16 2023-12-22 ant Selection urement Specialist GH-FSRP PHASE 2-296020-C Digital Advisory Services for S-INDV / Consultancy service Individual Consult IDA / V4240 Agriculture and Food Crisis P Post Limited 80,000.00 0.00 Canceled 2022-06-30 2022-07-05 2022-07-26 2022-08-30 2022-09-29 for the assessment of the hy ant Selection reventionand Management dromet, agrimet and agro-ad visory systems GH-FSRP PHASE 2-343716-C Individual Consult S-INDV / Recruitment of Com IDA / 71950 Project Management Post Open - National 60,000.00 0.00 Signed 2023-03-01 2023-06-17 2023-04-19 2023-08-30 2023-05-10 2023-09-15 2023-06-14 2024-06-08 ant Selection munications & Outreach Spe cialist Page 4 GH-FSRP PHASE 2-343250-C S-INDV / Consultancy Service to prepare Environmental an Individual Consult d Social Impact Assessment ( IDA / V4240 Project Management Post Limited 80,000.00 0.00 Under Review 2023-02-20 2023-02-25 2023-03-18 2023-04-22 2023-10-19 ant Selection ESIA) and Environmental and Social Management Plan (ES MP) for Lot 2: Weta Irrigation Scheme GH-FSRP PHASE 2-296015-C S-INDV / Consultancy service Individual Consult IDA / V4240 Project Management Post Limited 40,000.00 0.00 Canceled 2023-06-26 2022-07-17 2023-07-01 2023-07-22 2023-08-26 2024-02-22 to prepare RAP Lot 1: Weta ant Selection & Tanoso Irrigation Schemes GH-FSRP PHASE 2-295996-C S-CDS / Consultancy services Sustainability and Adaptive for Update, Review and Engi IDA / V4240 Capacity of the Food System Post Direct Selection Direct 40,000.00 0.00 Canceled 2022-05-31 2023-02-21 2022-06-10 2022-08-14 2022-09-23 neering Design for selected ir 's Productive Base rigation systems/schemes -L ot 2: Completion of Tanoso Ir rigation Scheme GH-FSRP PHASE 2-366745-C S-INDV / Consultancy service s for preparation of the envir Individual Consult onmental and social impacts IDA / V4240 Project Management Post Limited 60,000.00 0.00 Signed 2023-06-26 2022-07-17 2023-07-01 2022-09-20 2023-07-22 2023-06-08 2023-08-05 2023-06-22 2023-12-03 ant Selection assessment (ESIA) and envir onmental and social manage ment plan (ESMP) for lot 1: T anos Irrigation scheme (TIS) GH-FSRP PHASE 2-323069-C S-INDV / CONSULTANCY FOR Individual Consult IDA / 71950 Project Management Post Limited 10,000.00 0.00 Canceled 2022-11-30 2022-12-05 2022-12-26 2023-01-30 2023-07-29 THE PREPARATION OF Emerg ant Selection ency Response Manual (ERM) GH-FSRP PHASE 2-411988-C S-INDV / RECRUITMENT OF A Individual Consult Under Implement N INDIVIDUAL CONSULTANT IDA / 71950 Project Management Post Open - National 36,000.00 0.00 2024-03-29 2024-02-28 2024-07-25 2024-04-23 2024-08-08 2024-09-21 2025-09-21 ant Selection ation ON AN AS NEEDED BASIS AS LEGAL COUNSEL TO PROVIDE LEGAL SERVICES TO FSRP GH-FSRP PHASE 2-411986-C S-INDV / RECRUITMENT OF A Individual Consult IDA / 71950 Project Management Post Open - National 36,000.00 0.00 Canceled 2024-03-29 2024-02-28 2024-07-25 2024-08-08 2024-09-21 2025-09-21 N INDIVIDUAL CONSULTANT ant Selection AS A GENDER OFFICER FOR F SRP GH-FSRP PHASE 2-429799-C S-INDV / RECRUITMENT OF A N INDIVIDUAL CONSULTANT Individual Consult Pending Impleme FOR THE UPDATE OF NATION IDA / 71950 Project Management Post Open - National 40,000.00 0.00 2024-06-28 2024-10-15 2024-11-05 2024-12-10 2025-06-08 ant Selection ntation AL IRRIGATION POLICY AND DEVELOPMENT OF FIVE-YEAR STRATEGIC PLAN/ROADMAP F OR GIDA (2025-2029) Page 5